UTTAR PRADESH ELECTRICITY SUPPLY CODE - Indian ...
-
Upload
khangminh22 -
Category
Documents
-
view
1 -
download
0
Transcript of UTTAR PRADESH ELECTRICITY SUPPLY CODE - Indian ...
1
UTTAR PRADESH ELECTRICITY SUPPLY CODE- 2002 (DISTRIBUTION CODE)
INDEX
CHAPTER 1 Introduction…………………………………………………………… 5 Electricity Supply Code Review Panel…………………………………..5
CHAPTER 2 Definitions……………………………………………………………… 7 Notes and Explanation ………………………………………………… 12 CHAPTER 3 System of Supply and Classification of Consumers………………….14 System of Supply………………………………………………………..14 Classification of Supply…………………………………………………14 Charges for Supply……………………………………………………...15 Statutory Levies ……………………………………………………… 16 CHAPTER 4 Procedure for Grant of Supply………………………………………...17 Licensee’s Obligation to Supply…………………………………………17 Application for Supply…………………………………………………...18 Application for Temporary Supply………………………………………21 General Conditions of Supply… ……………………………………….. 22 Security Deposit……………………………………………..…………...25 Wiring on Consumer’s Premises……………………………………….. .27 Protective Load…………………………………………………………. .29
Conditions When Supply Shall Not Be Given…………………………...30 Temporary Disconnection………………………………………………. 31 Permanent Disconnection……………………………………………… ..32 Procedure for Reconnection…………………………………………… 32 Reduction in Contracted Load……………………………………………32 Procedure for Enhancement of Load..……………………………………34 Transfer of Connection and Mutation of Names…………………………35 Resale of Energy………………………………………………………… 36
CHAPTER 5 Metering ………………………………………………………………....38
Requirements of Meter …………………………………………………. 38 Testing of Meter…………………………………………………………..40 Defective Meters …………………………………………………………41 Meter Not Recording …………………………………………………… 42 Burnt Meter ……….…………………………………………………….. 42 Lost Meters..…………………………………………………………….………43
Deleted: DRAFT OF¶
2
CHAPTER 6 Bills ……………………………………………………………………..45 Advance Payment of Bills………………………………………………46 Disputed Bills ………………………………………………………… . 47 Billing in case of Theft of Electricity/Tempering of Meter……………..47 Billing in case of Excess Load…………………………………………..48 Billing in case of Unauthorized, Supply/Sale or Use of Electricity……. 49 Mode of Payment………………………………………………………..49 Rebate and Late Payment Surcharge…………………………………….51 Recovery of Arrears …………………………………………………….51 CHAPTER 7
Standards of Service and Procedure for Redressal of Consumer Grievances…………………………………...52 Availability of Supply and Its Quality………………………………….. 52 Procedure of Redressal of Consumer Grievances……………………….54 Monitoring of Redressal of Grievances ………………………………...55 Complaints before the Commission …………………………………… 56
CHAPTER 8 Force Majure and Restrictions on Supply of Power…………………58 Annexure: 3.1………………………………………………………………….. 60
Existing Consumer Categories Annexure 4.1……………………………………………………………………61 Application From for Requisition of Supply of Energy Annexure 4.2……………………………………………………………………65
Indemnity Bond Annexure 4.3……………………………………………………………………66 Format for Work Completion Certificate and Test Results Annexure 4.4……………………………………………………………………71 Application Form For Requisition of Temporary Supply of Energy Annexure 4.5……………………………………………………………………73 Procedure for Determination of Contracted Load Annexure 4.6……………………………………………………………………74 Format for Disconnection Annexure 4.7……………………………………………………………………75 Format for Intimation to Consumer After Termination of Agreement Annexure 4.8 …………………………………………………………………...76
Format for Intimation to Consumer After Temporary Disconnection of Supply Annexure 4.9……………………………………………………………………77 Application Form for Enhancement/Reduction of Contract Demand Annexure 4.10………………………………………………………………….78 Format for Transfer of Connection/Mutation of Name Annexure 5.1……………………………………………………………………79 Meter Related Complaints or Testing Meter Annexure 6.1………………………………………………………………….…80 Minimum Details to be Indicated on Electricity Bill Annexure 6.2…………………………………………………………………….81 Format for Application of Advance Payment
3
Annexure 7.1…………………………………………………………………….82 Complaint to the Executive Engineer Annexure 7.2…………………………………………………………………….83 Procedure for Complaints to Appellate Committee
Chapter 1
Introduction
1.1 The Electricity Supply Code (hereinafter called ‘Code’) details the obligations of the
Licensee and consumers vis-à-vis each other and specifies the set of practices that
shall be adopted by the Licensee to provide efficient, cost-effective and consumer
friendly service to the consumers. It specifically details the following:
(a) The procedure for connection, disconnection, reconnection, assessment of
load and for enhancement or reduction of load.
(b) Practices relating to payment of bills and consumer metering.
(c) Standards of Performance for the Licensee; and
(d) Procedure for Redressal of Consumer Grievances
Electricity Supply Code Review Panel
1.2 The Commission shall set up an Electricity Supply Code Review Panel (ESCRP) to
review the Code on regular basis. ESCRP shall consist of representatives of all the
Supply Licensees. The panel shall meet at least once every six (6) months.
1.3 ESCRP shall consist of following Members:
(a) One representative each from every distribution supply Licensees of the State
to be nominated by the Licensee.
(b) One representative of STU.
(c) Representatives of the consumers to be nominated by the Commission. of
these, three representatives shall be from LT consumers, two from HT/EHT
consumers and two from registered consumer bodies. At least two
representatives from the above shall be from the category of the domestic
consumers.
(d) Director (Distribution) of UP Power Corporation Limited (UPPCL) shall be
the Ex-officio Chairman and Chief General Manager (Commercial) shall be
the Member Secretary of ESCRP.
1.4 The Secretary of ESCRP shall send the proceedings of the meetings of the Review
Panel to the Commission within 15 days of the meeting.
4
1.5 The Commission may amend the Code suo moto or on the recommendations of
ESCRP. However, before any amendment is made in the Code, comments on the
proposed changes shall be obtained from all the Supply Licensees and public.
1.6 Any change in the Distribution Code shall be published by the Licensee by publishing
the extracts of the changes in at least two newspapers having wide circulation in the
area of supply apart from keeping the copies of changes in all local offices.
5
Chapter 2
Definitions
2.1 Words, terms and expressions defined in the Uttar Pradesh Electricity Reforms Act,
1999, Indian Electricity Act, 1910 and Electricity (Supply) Act, 1948 and the Rules
made under these Acts as amended from time to time and used in this Code shall
have and carry the same meaning as defined and assigned in the said Acts and Rules.
2.2 In this Code, unless it is repugnant to the context:
(a) “Act” means the Uttar Pradesh Electricity Reforms Act 1999 (UP Act, 24 of
1999).
(b) “Agreement” means an agreement, with its grammatical variations and
cognate expressions, entered into by the Licensee and the consumer under this
Code.
(c) “Apparatus” means electrical apparatus and includes all machines, fittings,
accessories and appliances in which conductors are used.
(d) “Area of Supply” means the geographic area within which alone a Licensee is
for the time being authorised by his license to supply electrical energy.
(e) “Billing Cycle or Billing Period” means the period for which regular
electricity bills are prepared for different categories of consumers by the
Licensee.
(f) “Breakdown” means an occurrence relating to the equipments of the electric
energy supply system including electrical line that prevents its normal
functioning.
(g) “Bulk supply” means the sale of electricity to any person for resale.
(h) “Calendar Year” means the period from the first day of January of a year to
the thirty first day of December, of the same year.
(i) “Commission” means the Uttar Pradesh Electricity Regulatory Commission
constituted under the Act.
(j) “Conductor” means any wire, cable, bar, tube, rail or plate used for
conducting electrical energy and so arranged as to be electrically connected to
a system.
IE Act of 1910
Rule 1956
Deleted: wherever
6
(k) “Connected Load” means aggregate of the manufacturer’s rating of all energy
consuming devices, in the consumer’s premises, which can be simultaneously
used This shall be expressed in KW, KVA or BHP units and shall be
determined as per the procedure laid down by the Licensee with the approval
of the Commission.
(l) “Consumer” means and includes any person who or whose installation is
supplied with electricity or who has executed an agreement with the Licensee
for the supply of electricity or any person whose installation is for the time
being connected for the purpose of receiving the electricity or whose
installation has been temporarily disconnected.
(m) “Consumer Installation” means the whole of the electric wires, fittings,
motors, transformers and apparatus installed and wired by the consumer or on
his behalf in one and the same premises starting from the point of supply and
includes apparatus that is available on his premises for being connected or
envisaged to be connected to the installation but is for the time being not
connected.
(n) “Contracted Load” means maximum KW, KVA or BHP units agreed to be
supplied by the Licensee which may be different than connected load and
reflected in the agreement between the parties.
(o) “Date of Commencement of Supply” is the date when the Licensee energizes
consumer installation by connecting to the Distribution mains.
(p) “Demand Charge” for a billing period means a charge levied on the consumer
based on the contracted load or maximum demand (Refer clause 2.2 (ag))
which ever is higher.
(q) “Distribution mains” means the portion of any main with which a service line
is, or is intended to be, immediately connected.
(r) “Distribution System” means any system consisting mainly of cables, service
lines and overhead lines, electrical plant and meters having design voltage of
33KV and below. The distribution system shall not include any part of a
transmission system except the terminal equipment used for the supply of
electricity to extra high voltage (66 KV and above) consumers.
(s) “Electrical Inspector” means an Electrical Inspector appointed under Section
36 of IE Act, 1910. Deleted: and Rule 4(A) of I.E. Rules 1956.
7
(t) “Emergency Rostering” Load shedding carried out by disconnecting at short
notice or no notice for safety of personnel and equipment.
(u) “Energy charge” refers to a charge levied on the consumer based on the
quantity of electricity supplied.
(v) “Extra High Tension (EHT)” means a voltage exceeding 33000 Volts under
normal conditions subject to the percentage variation permissible under the
Indian Electricity Rules 1956.
(w) “Financial Year” means the period beginning from first of April in a English
calender year and ending with the thirty first of the March of the next year.
(x) “Feeder” means a HT or EHT distributor, emanating from a sub station, to
which a distribution sub station or HT or EHT consumers are connected.
(y) “Fixed Charges” shall be as per the provisions of the Tariff order.
(z) “High Tension” means a voltage level between 650 volts and 33000 Volts
under normal conditions subject to the percentage variation permissible under
the Indian Electricity Rules 1956.
(aa) “Independent feeder” means a feeder constructed at the cost of a consumer
and supplying the electricity to only that consumer.
(ab) “Licence” means a licence granted under chapter V of the Uttar Pradesh
Electricity Reforms Act 1999 for distribution and/or retail supply and /or bulk
supply.
(ac) “Licensed Electrical Contractor (LEC)” means a contractor licensed under
rule 45 of the Indian Electricity Rules 1956.
(ad) Licensee” means a person who holds a licence under IE Act, 1910 or UP
Electricity Reforms Act, 1999.
(ae) “Load Factor” is the ratio of the total number of units consumed during a
given period to the total number of units which have been consumed had the
load been maintained throughout the same period and shall usually be
expressed as the following percentage:
Actual units consumed in a given period *100 Load Factor in Percentage =
Contracted load in KW* No. of Hours in the period Note: * means multiplied by
Formatted: Bullets and Numbering
Deleted: consumed
Deleted: (z)
8
(af) “Low Tension (LT)” means a voltage that does not exceed, 250 volts between
phase and neutral or 440 volts between any two phases under normal
conditions subject to the percentage variation permissible under the Indian
Electricity Rules 1956.
(ag) “Maximum Demand” means the average amount of KW or KVA, as the case
may be, delivered at the point of supply of the consumer and recorded during
a thirty minute period of maximum use in the billing period, however, subject
to the Licensee reserving the right to shorten this period in special classes of
consumer, if necessary, with the approval of the Commission.
(ah) “Meter” means an equipment used for measuring electrical quantities like
energy in KWh, maximum demand in KW or KVA, reactive energy in KVAR
hours etc. including accessories like Current Transformers (CT) and Potential
Transformers (PT) where used in conjunction with such meter and any
enclosure used for housing or fixing such meter or its accessories and any
devices like switches or MCB or fuses used for protection and testing
purposes.
(ai) “Minimum Charge” shall be as per the provisions of the tariff order.
(aj) “Occupier” means the owner or person in occupation of the premises where
energy is used or proposed to be used.
(ak) “Phased Contract Demand” means contract demand agreed to be availed in a
phased manner.
(al) “Point of Supply” means the outgoing terminals of the Licensee’s
cutouts/MCB fixed in the premises of the Consumer in case of LT
installations and the outgoing terminals of the Licensee’s Metering cubicle
placed before any Consumer’s apparatus in case of HT or EHT installations.
In the absence of any metering cubicle or the metering being on the LT side in
case of H T installations, the point of commencement of supply shall be the
incoming terminals of the Consumer’s main switchgear.
(am) “Power factor” means the ratio of watts to Volt-amperes, or the ratio of KWh
to KVAh; as applicable, for the duration for which, it is to be determined.
(an) “Premises” means the area/portion of the building/shed/field etc., for which,
the electric connection has been applied for or sanctioned for a single
consumer.
9
(ao) “Protective Load” means a load not subjected to normal rostering.
(ap) “Rules” mean the Indian Electricity Rules 1956.
(aq) “Service Line” means an electric supply line through which energy is, or is
intended to be supplied by the Licensee from a distributing main to a single or
group of Consumers from the same point of the distributing main.
(ar) “SLDC” means State Load Dispatch Centre, where operation of the Power
System in the state and its integration with other power systems is coordinated
round the clock on real time basis.
(as) “State Transmission Utility (STU)” means the Utility notified by the
Government of U.P. under Sub-Section (1) of section 27B of the Indian
Electricity Act, 1910, as amended in 1998, and whose functions have been
outlined under section 55 of the Amendments to the Electricity (Supply) Act
1948. UPPCL has been declared an STU vide U.P. Government Gazette
No.151/P-1/2000-74 dated January14, 2000.
(at) “Tariff Order” in respect of a Licensee is the most recent order issued by the
Commission for that Licensee indicating the rates to be charged by the
Licensee from various categories of consumers for the supply of electrical
energy and services.
(au) “Tariff Schedule” is the most recent schedule of charges for supply of
electricity and services issued by the Licensee as per the provisions of the
Tariff order for that Licensee.
(au) “Theft” means abstraction of electricity either through bypassing the meter by
some arrangement or tampering with the meter to cause it to record less
energy than actually passing through it or through illegal tapping of the supply
from the Licensee’s network.
(av) “Transmission System” means the system consisting of extra high voltage
electric lines having design voltage above 66KV owned or operated by a
transmission Licensee/STU authorised to transmit electricity for the purpose
of its transportation from power station to sub-station, from power station to
another power station, from one sub station to another, or from any external
interconnection including 33/11 KV bays and associated equipment up to the
interconnection with the distribution system (including plant and apparatus
Deleted: ¶
Deleted: 33
10
and meters owned or used in connection with the transmission of electricity),
and excluding the distribution system.
(aw) “UP Electricity Grid Code” means the document notified by the Commission
describing the responsibilities for planning and operation of the power system
in Uttar Pradesh.
Notes and Explanations
2.3.1 Note I If any rating is in KVA, the same may be converted to KW by multiplying the
KVA figure with a power factor of 0.85; if the same or any other apparatus is rated
by the manufacturer in HP, the HP rating shall be converted into KW by multiplying
it by 0.746.
Names of Offices and Designation of Officers
2.3.2 Note II In this code the names of offices such as Sub Divisional office, Divisional
office, Circle office etc. and designations of officers such as Assistant Engineer, Sub
Divisional Officer, Executive Engineer, Deputy General Manager (DGM) etc. refer to
the existing names of the offices / designation of officers of the Uttar Pradesh Power
Corporation Ltd. In case of other Licensees, they shall refer to the appropriate office
/ designation of officer to be notified by them with the approval of the Commission.
Abbreviations used in the Code
2.3.3 Note III Following abbreviations have been used in this code:
a. V = Volt
b. A = Ampere
c. KV = Kilo Volt
d. KA = Kilo Ampere
e. KWh = Kilo Watt Hour
f. KVA = Kilo Volt Ampere
g. CT = Current Transformer
h. PT = Potential Transformer
i. KVAh = Kilo Volt Ampere Hour
j. B.H.P. = Brake Horse Power
k. W = Watt
l. KW = Kilo Watt
m. CB = Circuit Breaker
n. MCB = Miniature Circuit Breaker
11
o. LEC = Licensed Electrical Contractor
p. KVAR = Kilo Volt Ampere Reactive
q. SWG = Standard Wire Gauge
r. LEC = Licensed Electrical Contractor
12
Chapter 3
System of Supply and Classification of Consumers
System of Supply
3.1 The Licensee shall supply power at a frequency of 50 Hz +/- 2% with voltage
variation limits as per Rule 54 of I.E. Rules 1956. The power supply shall be as far as
possible uninterrupted.
3.2 The declared voltage of the AC supply is as follows:
(1) Low Tension (LT) - Single Phase: 230 volts between phases and neutral.
- Three Phase: 400 volts between phases.
(2) High Tension (HT) - Three Phase: 6.6 KV/11 KV/33 KV. For existing
Railway Traction supply shall be single phase at 25
KV.
(3) Extra High Tension (EHT) - Three Phase: 66 KV/ 132 KV/ 220 KV. Two Phase
at 132 KV/220KV for existing Railway Traction.
Classification of Supply
3.3 The supply shall be given generally at following voltages on the basis of the
contracted load:
Category System of Supply
Low Tension
(a) All installations (other than irrigation pumping and agricultural
services) with a contracted load less than 5 KW
Single phase at 230 V
(b) Irrigation pumping and agricultural services and all
installations with a contracted load of 5KW or more and up to 50
KW / 63 KVA
3 Phase, 4 wire at 400 V
High Tension
Contracted load exceeding 63 KVA and up to 3000 KVA 3 Phase at 6.6 / 11 KV
Contracted load exceeding 3000 KVA and up to 10000 KVA 3 Phase at 33 KV
Extra High Tension
Contracted load exceeding 10000 KVA 3 Phase at 132 / 220 KV
Formatted
Formatted
Formatted
Deleted: would be Alternating Current (AC
Deleted: Rule 55 of 1956
13
3.4 Load for Arc/Induction furnaces, Rolling Mills, Re-rolling Mills and Mini steel plants
shall be released only through an independent feeder and all necessary charges shall
be paid by the consumer.
3.5 Supply may be given at independent feeder in other cases at the request of the
consumer if he is willing to bear all applicable charges.
3.6 The above classification of supply shall apply to new connections to be granted after
the notification of this Code and existing services shall not be affected.
3.7 The Licensee may, depending upon the technical conditions of the distribution
system, give supply at a different voltage and phase than the classification indicated
above in clause 3.3.
Power Factor
3.8 It shall be obligatory for the consumer to maintain the average power factor of his
load more than 0.85 during any billing period. The Licensee may disconnect the
supply temporarily if power factor is below 0.70 during any billing period as per
details given in clause 4.66.1. Licensee may charge a penalty and / or give an
incentive for high /low power factors as per the tariff order of the Commission.
3.9 Load Balancing
The consumer taking three-phase supply shall balance his load in such a way that the
difference in loading between each phase does not exceed 5% of the average loading
between the phases.
3.10 Classification of Consumers
The Licensee may classify or reclassify consumers into various categories from time
to time and may fix different tariffs for different classes of consumers with the
approval of the Commission. The existing classification is given in Annex 3.1.
Charges for Supply
3.11.1 Tariff and other charges for the supply of electricity shall be announced by the
Licensee with the approval of the Commission in accordance with Section 24 of the
Act. Such tariffs or charges shall take effect only after seven days from the date of
publication in at least two daily Newspapers having wide circulation in the area of
supply. The charges may include:
(a) Minimum monthly charges /fixed charges / yearly charges.
(b) Demand charges.
(c) Energy charges.
Deleted: Licensee may levy a penalty and / or give an incentive for high /low power factors as per the tariff order of the Commission.
Deleted: of any consumer
Deleted: <#>¶
14
(d) Synchronization charges.
(e) Protective load charges.
The Licensee may also realize other charges including, but not restricted to,
connection charges, re-connection charges, delayed payment surcharge, fuel
surcharge, power purchase surcharge and power factor penalty/incentive, with the
prior approval of the Commission.
3.11.2 The Licensee shall publish Tariff Schedule on its web site immediately after the
Commission has approved it. The Licensee shall also make available copies of the
Tariff Schedule to consumers at a reasonable price.
Statutory Levies
3.12 Statutory levies such as electricity duty, taxes or any other duties etc. shall be payable
by the consumer as per law.
Deleted: 2
15
Chapter 4
Procedure for Grant of Supply
Licensee’s Obligation to Supply
4.1 The Licensee shall on an application by the owner or occupier of any premises,
located in his area of supply, give supply of electricity to such premises within the
time specified in this code, provided
(a) the supply of power is technically feasible,
(b) the applicant has observed the procedure specified in this Code; and
(c) the applicant agrees to bear the cost of supply and services as specified in the
Code.
4.2 The system of supply and voltage shall depend on the category of the consumer and
the load as per details given in Chapter 3.
Licensee’s obligation to extend the Distribution System and Consumer’s share in
the Cost
4.3 The Licensee is responsible for ensuring that its distribution system is upgraded,
extended and strengthened to meet the demand for electricity in its area of supply.
4.4 The Licensee shall meet the cost for strengthening / up gradation of the system to
meet the enhanced demand of the existing consumers through its annual revenues and
this cost shall be recovered from the consumers through tariff.
4.5 The cost of extension and up-gradation of the system for meeting demand of new
consumers shall be recovered from the new consumers through system loading
charges as approved by the Commission. In areas where distribution mains do not
exist, the costs for installation of new distribution mains shall normally be covered by
grant from State Government or the local body or any collective body of the
consumers or a consumer. The Licensee may also install new Distribution Mains
from the surplus available with the Licensee after meeting all expenditure. The
Licensee shall submit a policy regarding the utilization of surplus funds and the
installation of Distribution Mains to the Commission for approval. The
(a) responsibility of construction of the required distribution network in case of a
new residential, commercial or an industrial complex with load exceeding 25
KW shall be that of the body or the agency (public or private) that constructs
such complex and
Deleted: all out standing arrears related to electricity for the premises have been paid.
Deleted: case of rural
Deleted: system
Deleted: es
Deleted: cost
Deleted: shall b
Deleted: the
Deleted: g
16
(b) responsibility for laying the distribution network for street lights on any new
road /street shall be that of the concerned local authority.
4.6 In all cases the applicant shall bear the cost of the extension of service line
from the Distribution Mains to the point of supply. There shall be no refund
towards free length of service line/cable either overhead or underground
chargeable to the Licensee, as the same shall be adjusted towards supervision
charges payable to the Licensee by the consumer.
Application for Supply
4.7 Application form for obtaining new connection and for enhancement /reduction of
load shall be made available to the consumer free of charge at all offices of the
Licensee. Licensee shall also put them on its website (www.uppcl.org) for
downloading. The application form can be downloaded from the web site of UPERC
also (www.uperc.org). Photocopies of a blank form may be made by the consumer
and shall be accepted by the Licensee.
For Loads up to 25 KW Where Distribution mains Exists within 0.9 Km
4.8 Application for new connections, in prescribed form (Annex 4.1) and complete in all
respects and accompanied by the prescribed Registration-cum-processing fee, shall be
filed in duplicate in the office of the Sub Divisional officer along with attested true
copies of the following documents:
(a) Proof of ownership of the premises in the form of registered sale deed or
partition deed or succession or heir ship certificate or deed of last will
OR
Proof of occupancy such as valid power of attorney or latest rent paid receipt
or valid lease deed along with an indemnity form as per Annex 4.2.
(b) Approval / permission of the local authority, if required under any law
/statute.
(c) In case of a partnership firm, partnership deed.
(d) In case of a Limited Company, Memorandum and articles of Association and
Certificate of incorporation.
(e) Work completion and Test certificate, on the prescribed format (Annex- 4.3),
given by the licensed electrical contractor.
4.9 Licensee shall arrange to assist the applicants, if required, in completing the
application form.
Deleted: The Licensee shall prepare a long-term plan for laying down the distribution system within next 10 years in the entire rural area of his area of supply. The plan including annual physical and financial targets shall be submitted to the Commission within 6 months of the notification of the code and shall be prepared in consultation with the state government. The Commission expects that the government would provide funds for this purpose to the Licensee.¶
Deleted: areas where Distribution mains exist within 0.9 Km of the point where supply is requested to be given and the application is for load not exceeding 25 KW,
Deleted: as approved by the Commission from time to time.
Deleted: In areas where Distribution mains do not exist within 0.9 Km of the point of supply or the applied load is more than 25 KW the applicant would bear the cost of extension / up gradation of the distribution network that may include setting up a new transformer or a substation and other related works. However:¶Responsibility of construction of the requisite distribution network in case of a new residential, commercial or an industrial complex with a load exceeding 25 KW would be that of the body or the agency (public or private) that constructs such complex.¶(b) Responsibility for laying the distribution network for street lights on any new road /street would be that of the concerned local authority.
17
4.10 The Licensee shall verify the application and the enclosed documents at the time of
receipt of application. A written acknowledgement shall be issued on the spot. The
acknowledgement shall contain the date of proposed inspection (not later than 7
days), if the application is complete or the shortcomings if the application is
incomplete.
4.11 The applicant along with the licensed contractor or his representative shall be present
during the inspection. During the inspection, the Licensee shall:
(a) Satisfy himself regarding the Work completion certificate and the test report
submitted by the applicant.
(b) In consultation with the consumer, fix the point of supply and the place where
meter and the MCB etc. shall be fixed.
(c) Estimate the distance between the point of supply and the nearest Distribution
mains from where supply could be given.
(d) Determine if the supply line is to go over any property belonging to a third
party.
(e) Verify other particulars mentioned in the application form, if required.
4.12 If Licensee is satisfied and no new pole is to be erected and underground cable is not
to be laid for giving the supply, the Licensee shall intimate at the spot, in writing the
charges that need to be deposited for obtaining the supply. In other cases, the estimate
of the work and other charges shall be intimated to the applicant within 7 days of the
site inspection. The charges shall include security deposit, charges for laying the
service line and system loading charges etc. as determined by the Licensee with the
approval of the Commission.
4.13 If the Licensee is not satisfied, he shall intimate to the applicant shortcomings on the
spot. The applicant shall be required to get the defects removed. Inspection shall
again be conducted as per Clause 4.12 and a fee, as prescribed, may be charged for
such subsequent inspections.
4.14 The applicant shall deposit the requisite charges, the requisite way-leave permission if
the supply line is to go over the property not belonging to the applicant. If the
consumer desires to procure the meter and MCB himself, the same shall also be
deposited with the Licensee who shall satisfy himself about the accuracy of the meter
and MCB.
Deleted: spot
18
4.15 The applicant shall provide a board at the point of supply where meter and MCB shall
be installed.
4.16 The Licensee shall, upon completion of formalities as indicated in Clause 4.14,
intimate the date when the meter shall be installed. The meter and MCBs etc. shall be
installed and sealed in the presence of the applicant on the appointed date and the
connection shall be energized immediately thereafter.
4.17 The supply shall be given within 7 days after deposit of charges; meter etc. as per
Clause 4.16, if no new pole is to be erected. In other cases, the supply shall be given
within 30 days.
For Loads Exceeding 25 KW and / or Where Distribution Mains do not Exist
4.18 Application in prescribed form shall be filed with the local office of the Licensee
along with the documents detailed in Clause 4.8 excepting that the work-completion
certificate may not be attached, if the wiring has not been completed. The applicant
may also indicate in the application if he desires that load be released in a phased
manner along with the time schedule.
4.19 The Licensee shall communicate to the applicant whether the supply is technically
feasible and, in case of feasibility, the financial estimate for the works required to be
done to give supply and the estimated time to execute these works, after site
inspection and within:
(a) 15 days in case of load up to 50 KW.
(b) 30 days for request for supply on HT.
(c) 60 days for request for supply on EHT.
The date of site inspection shall be notified to the applicant at least 7 days in advance
when he or his authorized representative shall be required to be present.
4.20 Along with the estimate the Licensee shall also intimate the security deposit, the point
where meter is to be installed and the civil /other works that are to be completed by
the applicant for installation of meter cubicles and other electrical apparatus.
4.21 The applicant shall be required to deposit the estimate amount in the local office of
the Licensee within 60 days, failing which the application shall be considered
withdrawn and a fresh application shall need to be filed subsequently.
4.22 The Licensee shall execute the work expeditiously and definitely within:
(a) 60 days for loads up to 5 MW
(b) 150 days for loads between 5 to 10 MW
Deleted: 15
Deleted: 5
19
(c) 300 days for loads exceeding 10 MW
from the date of deposit of the estimate money.
4.23 The applicant shall have the option to execute these works himself through LEC
under the supervision of the Licensee for which supervision charges shall be payable
to the Licensee.
4.24 The applicant shall be responsible for getting the electrical works on his site inspected
by the Electrical Inspector if required, preferably 2 weeks prior to the scheduled date
of completion of works relating to the distribution system and submit the same to the
Licensee. The consumer shall, up on demand of the Licensee shall submit the test
results of the manufactures of the apparatus in case of HT and EHT consumers.
4.25 Upon satisfactory verification of the work completion certificate and test results,
submission of security by the applicant and completion of the distribution system
related works; the Licensee shall intimate the date (not later than 7 days) when the
connection shall be energized. The applicant or his authorized representative shall be
present at the time of sealing of meter and energizing of the connection.
Application for Temporary Supply
4.26 Licensee may grant temporary supply for a period not exceeding 2 years for building
construction and 3 months for other purposes.
4.27 Application for temporary supply shall be given in the format prescribed in Annex 4.4
to the local office of the Licensee at least 15 days before the day when supply is
required for load up to 50 KW and 30 days for loads exceeding 50 KW along with the
following documents:
(a) No objection certificate from the local authority if the supply is required at a
place owned by the local authority.
(b) Proof of ownership in case applicant is not a consumer of the Licensee for the
premises where temporary connection is to be given or copy of the latest paid
bill of the Licensee in other cases.
4.28 The Licensee shall examine the technical feasibility and if feasible shall send to the
applicant an estimate of the cost of the service line and other charges within a week of
the receipt of application.
4.29 The Licensee shall also intimate the charges towards electricity consumption for the
period for which supply is requested, as per tariff approved by the Commission from
time to time.
Rule 63 to 69 of 1956
Deleted: 15
20
4.30 After deposit of the estimated cost and the advance charge for electricity as intimated
above, the load shall be released within 3 days for load up to 50 KW and within 21
days for loads exceeding 50 KW. However, the load shall be released only after
receipt of approval in writing from the electrical inspector in cases where 100 or
more people are expected to gather at a place.
4.31 The date of availment of the temporary supply may be got amended, to a date not
later than 90 days of the date in the original sanction, by the Consumer, by applying
to the authority who sanctioned the load, at least three days before the
commencement date indicated in the order.
4.32 In case any permit / licence / NOC is withdrawn by the competent authority after the
connection is energized, the supply shall be disconnected forthwith and shall be
reconnected only after the permit / licence / NOC is restored. Further, Licensee shall
not be liable for any damages. Reduction of any charges or refund shall not be
permissible on this account.
4.33 For further extension of the period of temporary supply, the Consumer shall apply to
the Licensee at least one week before the date of expiry of temporary supply. The
Licensee may grant extension subject to provisions of clause 4.26 and deposit by the
consumer of the advance tariff, for the period of extension.
Tatkal Yojana
4.34 Licensee may give temporary supply at a notice of 24 hours, if it is technically
feasible, on payment of an additional fee as fixed by the Licensee with the approval
of the Commission.
General Conditions of Supply
Connected Load
4.35 The prevailing method of determination of connected load is given in Annex 4.5.
Contracted Load
LT Consumers without MDI
4.36 The Contracted load shall be equal to the connected load excepting that in domestic
and commercial categories the Licensee shall sanction contracted load less than the
connected load subject to the condition that in domestic category it shall not be less
than 50% of the connected load and in commercial category not less than 75% of the
connected load.
Deleted: certificate
21
LT Consumers with MDI and all HT and EHT Loads
4.37 Contracted load shall be as mutually agreed between the consumer and the Licensee
having regard to the requirement of the consumer installation.
Agreement
4.38 An agreement, on stamp paper of a prescribed value, shall be executed by the applicant
for getting a new connection and for enhancement of load in all cases other than
contracted loads of less than 25 KW. For contracted loads of less than 25 KW the
application form itself shall serve the purpose of the agreement. A copy of the
agreement shall be given to the consumer after the supply is commenced.
4.39 The agreement shall be for a minimum period of 2 years and shall remain valid till it
is terminated by either party, after following the procedure detailed subsequently.
4.40 The standard agreement format can be amended with the approval of the
Commission.
4.41 After permanent disconnection the agreement shall be deemed to be terminated.
4.42 A consumer may terminate the agreement after giving a notice in the specified format
(Annex 4.6). The notice period shall be 15 days for all consumers in domestic
category and for loads up to 7.5 KW and 30 days in other cases. However, if the
agreement is to be terminated before completion of 2 years:
(a) Consumer shall be liable to pay the minimum charges (or the demand /fixed
charges, if no minimum charges are prescribed for that category) for a period
of 6 months or the period by which the total duration of the agreement falls
short of 2 years, whichever is lower and
(b) The HT/EHT consumers shall bear the estimated expenditure on the removal
of the apparatus and line.
4.43 The service line shall be dismantled on the termination of the agreement and the Licensee
may take necessary steps for recovery of balance dues.
4.44 Whenever, an agreement is terminated the Licensee shall give a written intimation to
the consumer as per format in Annex 4.7.
Estimate
4.45 The estimate shall be prepared as per the provisions of the Indian Electricity Act,
1910 and on the basis of charges approved by the Commission. The Licensee shall
submit once in two years a proposal to the Commission for approval of various
charges to be charged by the Licensee from the consumer in the estimate. The
Formatted: Bullets and Numbering
Formatted: Bullets and Numbering
Deleted: The Licensee may make amendments in the standard agreement format after taking approval from the Commission and giving at least one -month notice to the consumers.applicant.¶
22
estimate shall be valid for two months. If the work is to be done by the applicant,
Licensee shall charge 15% of the estimate as supervision charges that shall need to be
deposited before work begins. In other cases, Licensee shall commence the work after
the applicant, has deposited the full amount of the estimate.
4.46 Disputes regarding the estimate may be referred to the Electrical Inspector for
adjudication as per the provisions of clause VI (3) of the Schedule of the Indian
Electricity Act, 1910.
4.47 A final bill shall be prepared after completion of the work by the Licensee. If the final
bill exceeds the value of the estimate, the difference shall be deposited by the
applicant before connection is energized. If it were less, the difference shall be
adjusted in subsequent electricity bills.
Point of Supply
4.48 Supply shall be given at a single point in a premises at the outgoing terminal of the
Licensee. The point of supply shall be determined by the Licensee such that the
meters and other equipment are always accessible to the Licensee for inspection
without infringing the privacy of the consumer. All EHT & HT consumers shall
provide independent entry to the meter or metering cubical. However, in special cases
Licensee may agree to give supply at more than one point in the installation of the
consumer having regard to the physical layout of the installation and the requirements
of the consumer.
4.49.1 At the point of commencement of supply, the consumer shall provide a main
switch/circuit breaker. In addition, HT/EHT consumers shall also provide suitable
protective devices as per the provisions of Rule 56 and 64 of the Indian Electricity
Rules 1956. The system of protection shall be got approved by the Licensee before
commencement of supply. Meter and the MCB or, in case of HT /EHT consumers,
circuit breakers and its associated equipment shall be installed by the Licensee at the
point (s) of supply.
4.49.2 HT /EHT consumers shall install step down transformers with a vector group with
delta winding on the high voltage side and star winding on the low voltage side, with
the neutral terminal brought out and solidly earthed.
4.50 The meter, meter boards, service mains, MCB/CB, load limiters etc., must on no
account be handled or removed by any one who is not an authorized
employee/representative of the Licensee. The seals, which are fixed on the meters
Deleted: ion
Deleted: is
Deleted: featuring
Deleted: suitably
Deleted: The consumer shall be responsible for the safe custody of meters, MCB/CB etc. The installations in his premises shall be maintained in a safe condition as provided by rule 31 of the Indian Electricity Rules, 1956.
23
/metering equipments, load limiters and the Licensee’s apparatus, must on no account
be tampered, damaged and broken. The responsibility for the safe custody of
Licensee’s equipments and seals on the meters/metering equipments within the
Consumer’s premises shall be on the Consumer.
4.51 In the event of any damage caused to the Licensee’s equipments in the Consumer’s
premises by reason of any act, neglect or default of the Consumer or his employees,
the cost thereof as claimed by the Licensee shall be payable by the consumer. If the
consumer fails to do so after demand, it shall be treated as a contravention of the
terms and conditions of supply agreement and the supply is liable to be disconnected.
4.52 The Licensee shall maintain a waiting list of applicants seeking connections, which
shall be granted on the basis of first cum first served. Area vise information about the
current status of connections released and the up to date position of the waiting list,
shall be displayed on the Notice board, or on a Blackboard kept at a prominent place
in the SDO’S office to be updated weekly.
Charges to be Levied for Connection, Reconnection and Disconnection etc.
4.53 The schedule of charges for connection, reconnection and disconnection shall be
fixed by the Licensee with the approval of the Commission and may include:
Registration-cum Processing fee
4.54.1 All applications for new connection, for enhancement or reduction of load, for
reconnection and for seeking disconnection shall be accompanied by a non-
refundable fee as prescribed. Applications without fee shall not be accepted.
4.54.2 Security Deposit
(a) A security deposit to cover the estimated power consumption for two months
shall be made by all consumers. The estimated consumption and security
deposit amount for different categories shall be determined by the Licensee
with the approval of the Commission. In case of enhancement of load, only
additional security to cover the additional consumption shall need to be
deposited.
(b) The security amount shall be revised as per the tariff order.
(c) The Licensee may give notice to any consumer for deposit of additional
deposit if:
Formatted: Bullets and Numbering
Deleted: 4.54
24
(i) The security deposit falls short of covering the estimated power
consumption bill for 2 months based on his average monthly consumption
for the preceding financial year.
(ii) The security deposit is reduced due to adjustment of outstanding dues.
The consumer shall deposit the additional sum within 15 days of the notice
failing which the Licensee may take steps for disconnection.
(d) The security deposit shall be returned to consumer, upon termination of the
agreement and after adjustment of all dues, within 30 days. In case of delay,
interest @12% p.a. shall be payable to the consumer.
(e) The Licensee shall pay interest @3% p.a., or as approved by the Commission
from time to time, by way of a credit in the bill of the consumer in the months
of April, May or June as per the applicable billing cycle. However, no interest
shall be payable if the deposit is made by way of a Bank Guarantee.
(f) The amount of security deposit shall be phased out according to the time
schedule agreed for release of load in case of “Phased Contract Demand”. The
additional security shall be deposited at least 30 days prior to the scheduled
release of additional load.
(g) The Licensee shall energise no Connection until the requisite security amount
has been deposited by the applicant/consumer.
Cost of Servicing a New Connection/ Enhancement of Load
4.54.3 The consumer shall pay the cost of service line etc. and system loading charges.
These charges shall be either on the basis of the schedule of standard charges
approved by the Commission or actual cost of works as given in the estimate prepared
by the Licensee.
Mode of Payment of Charges
4.55 All payments shall be made by way of Cash (up to Rs 20000), Banker’s Cheque,
Demand Draft. The Cheques and demand drafts shall be payable at any branch of a
scheduled commercial bank that is a member of the clearing house for the area where
the concerned Sub Divisional Office is located. However, for new connections for
contracted load exceeding 10 MW, consumer may have the option of making the
security deposit by way of a bank guarantee, valid for an initial period of 3 years,
drawn on a branch of a scheduled bank, situated in the district. It shall be the
25
responsibility of the consumer to get the guarantee renewed for further periods of five
year at least 3 months prior to the date of the expiry of the guarantee.
Wiring on Consumer’s Premises
4.56 The work of wiring at the premises of the consumer shall be carried out by a licensed
electrical contractor and conform to the standards specified in and Chapter VII of the
Indian Electricity Rules 1956. The material used for wiring shall comply with or be
superior to the standards laid down by the Bureau of Indian Standards. All high-rise
buildings, having a height of more than 15 meters from ground level, shall also
comply with Rule 50-A of the Indian Electricity Rules, 1956. The wiring shall be
tested as per provisions of Section 47 to 49 of the Indian Electricity Rules, 1956.
Installation of AC Motors
4.57.1 No AC motor shall be connected to the low or medium voltage system of the
Licensee unless the motor and the installation thereof has a suitable device to limit the
starting current in accordance with the requirement indicated below.
(a) Power supply shall not be given to any applicant at low or medium voltage for
utilizing induction motors of 3 HP capacity or above or welding transformers
of 1 KVA capacity or above, unless shunt capacitors of appropriate rating are
installed by the consumer across the terminal of such motors and welding
transformers to achieve an average monthly power factor that is specified in
this Code.
(b) Motors of low or medium voltage shall be provided with control gear to
satisfactorily prevent the maximum current demand from the consumer’s
installation exceeding the limits given in the following schedule under all
possible conditions:
Nature of Supply Size of Installation Max. Current
Demand
Single phase/ three
phase
(a) Up to and including 1 BHP.
(b) Above 1 BHP and up to and
including 10 BHP
(c) Above 10BHP and up to and
including 15 BHP
(d) Above 15 BHP
Six times full load
current.
Three times full load
current.
Two times the full
load current
One and a half times
the full load current.
26
Failure to comply with these requirements shall render the consumer liable to
be disconnected. The Licensee may, depending on the location and condition
of working, relax the starting current limit.
(c) A triple pole linked switch protected by a no-volt release shall control the
motor circuit and triple pole fuses (or overload release). It is important that
the release shall be maintained in good working order. Wiring for motors shall
be run with all three-phase wire bunches in a metallic conduit, which shall be
effectively earthed throughout and shall be connected to the frame of the
motor from which two separate earth wires shall run. The minimum
permissible size of the earth wire permitted shall be No. 14 SWG. Indian
Electricity Rules, as amended from time to time, shall be complied with in
every respect.
(d) Total harmonic voltage distortion shall not exceed the limits mentioned
below:
EHT = 4%
HT = 10%
LT = 15%
(e) In addition, synchronous motors shall also be provided with an apparatus to
control watt-less current.
Installation of Irrigation/Agriculture Pump Set
4.57.2 All new pumping set connection/reconnections shall have the following :-
(a) Friction less foot valve (b) HDPE piping suction and delivery (c) ISI marked energy efficient monobloc pump set. (d) Capacitor of adequate rating for the pump set.
Parallel Operation with the Supply System of Licensee
4.58 The consumer shall arrange the plant, machinery and apparatus of his generating
units, including an extension of or addition to the same, to operate in an isolated
mode, with the consent of the Commission, for capacity above 50 KW. Where
consent has been given for parallel operation, the consumer shall arrange his
installation to protect it from disturbances in the Licensees system. The Licensee shall
not be liable for any damage caused to the consumer’s plant, machinery and apparatus
on account of such parallel operation, or any adverse consequence arising thereof. For
Deleted: efficiently
27
parallel operation with the grid, the consumer shall have to follow the provisions of
the UP Electricity Grid Code and other relevant regulations and shall pay
synchronizing charges as approved by the Commission. The actual operations shall be
carried out in coordination with the STU and the Licensee.
Protective Load
4.59 The Licensee may grant protective load in exceptional cases to those consumers, who
have opted for use of power during restricted hours on the following terms and
conditions: -
(a) An additional charge as specified in the latest Tariff Schedule shall be
recovered each month through regular billing.
(b) The protective load may be subjected to any emergency rostering.
(c) The charges for protective load shall not count towards minimum charge for
the main supply.
(d) Protective load may also be utilised for lights & fans and drinking water
purposes.
(e) The consumer availing the facility of protective load shall, however, not be
subjected to scheduled power cut imposed from time to time by the State
Government or the Licensee. During the period of scheduled power cut, the
protective load shall not exceed the sanctioned protective load.
(f) Protective load shall be sanctioned only to such consumers, who are given
supply through an independent feeder from a grid sub-station.
(g) Protective load shall not be released or continued to such consumer, against
whom there are arrears towards the Licensee.
4.60 If it is brought to the notice of the SLDC/Licensee that a particular consumer is using
electricity during emergency load shedding by unauthorized or irregular means, the
feeder feeding such a consumer shall be opened to disenergize it from the source grid
sub-station, on instructions from the SLDC, for which the consumer shall be solely
responsible.
General Provisions Regarding Service Line and Apparatus
4.61 The consumer shall provide space of requisite dimensions and at convenient location
as mutually agreed between the consumer and the Licensee, free of charge, for
erection / installation of that part of service line that falls within his premises,
transformers, switch gear, meter and all other apparatus up to the point of
Formatted: Bullets and Numbering
Deleted: not
Deleted: <#>¶
Deleted: not
Deleted: not
28
commencement of supply. The whole of service line and other apparatus shall be
deemed to be the property of the Licensee and shall remain under his control.
4.62 The Licensee may use the service line and other apparatus to give supply to other
consumers provided that the supply to the consumer who has paid for them is not
affected adversely. Further, even if the supply to the consumer who has paid for the
line / apparatus is disconnected for whatever reason, the consumer shall permit the
Licensee continued access to the service line and other apparatus if they are required
to give supply to other consumers, and no payment shall be due to the consumer for
such access / facility, until alternate arrangements are made. However, it is expressly
provided that the Licensee shall make all possible efforts to make alternate
arrangements as early as may be practicably possible. For this purpose, the Licensee
may explore a mutually acceptable arrangement for continuation of the installation at
the existing place.
Access to Consumer’s Premises
4.63.1 The Licensee or his authorised staff shall be entitled to enter the premises
immediately after informing the consumer, for checking unauthorized additions and
alterations to equipment, theft and misappropriation of energy, diversion of power,
by-passing of the meter, or for general inspection and testing:
Provided no inspection, testing or checking of any domestic places or domestic
premises shall be carried out between sunset and sunrise except in the presence of an
adult male member occupying such premises.
4.63.2 If the consumer refuses to allow access, the Licensee or his authorised staff shall,
without prejudice to other actions available in the law, disconnect the supply of power
to the premises in accordance with section 20 of the Indian Electricity Act, 1910 after
giving 24 hours notice.
Conditions When Supply Shall not be Given
4.64 If there are arrears of electricity dues in respect of any premises, new connection
shall not be released if the applicant is an associate or relative (as defined in Section 2
and 6 respectively of the Companies Act, 1956) of the defaulting consumer.
However, if the Licensee refuses electric connection on this ground, orders shall be
passed by the Dy. General Manager and only after the applicant has been given an
opportunity to present his case.
Deleted: The Licensee or a person duly authorised by the Licensee may, at any reasonable time and on informing the occupier of his intention, enter any premises or land, under, over, along, across, in or upon which electric supply has been given by the Licensee and undertake inspection and/or testing of the electric supply lines, meters, fittings, works and apparatus for the supply of energy belonging to the Licensee and where it is considered necessary to ascertain the amount of energy supplied or the electrical quantity contained in the supply.¶4.65 Where the consumer refuses to allow the Licensee or any person authorised by it to enter into the premises or refuses to allow the Licensee or the authorised person to undertake inspection, testing, repairing and altering the supply lines, meters, fittings, works and apparatus as aforesaid, the Licensee may, after expiry of 24 hours from the service of a notice in writing on the consumer, cut off the supply to the consumer for so long as such refusal or failure continues but for no longer.
Deleted: no
29
Conditions when Supply may be Disconnected
4.65 The supply may be disconnected temporarily or on a permanent basis as per the
procedure described below. The Licensee shall remove service line, meter etc after
permanent disconnection. However, the Licensee may not remove service line, meter
etc in case of temporary disconnection.
Temporary Disconnection
4.66.1 The supply may be disconnected temporarily in following cases:
(a) If electricity bills are not paid by the disconnection date indicated on the bill.
(b) If conduct/continuance of a particular business/industry/activity is being
carried out in any premises becomes unlawful due to lack of necessary
permission or withdrawal of permission from the authority competent in law.
(c) If the power factor of consumer’s installation other than the following
categories of consumer is less than 0.70 during any billing period
(i) Domestic having connected load up to10 KW
(ii) Commercial having connected load up to 5 KW
(d) If the wiring, apparatus, equipment or installation at the premises of any
consumer is found to be defective or there is leakage of electricity or if the
consumer is found to have altered the position of the meter and related
apparatus or if the consumer uses any apparatus or appliance or uses the
energy in such manner as to endanger the service lines, equipment, electric
supply mains and other works of the Licensee, or is found to be using it in any
manner which unduly or improperly interferes with the efficient supply of
energy to any other consumer.
(e) If at any time the consumer is found to be using energy for a purpose other
than for which it was intended/provided or tampers with the meter and /or
other apparatus of the Licensee on his premises or extends / allows supply of
energy to any other premises from his connection.
The supply shall be disconnected without any notice for cases covered by clause (a)
and (e). However, a notice of minimum period of 7 days in cases covered by clause
(b) and (c) and 48 hours in cases covered under clause (d) shall be served on the
consumer by the Licensee. The supply shall be disconnected only if the cause of the
disconnection is not removed within the notice period.
Deleted: of the premises in the period for which the arrears are due. ¶
30
4.66.2 The Licensee shall, after a connection is temporarily disconnected issue a notice, as
per format given in Annex 4.8, to the consumer, to remove the cause of disconnection
within 45 days failing which the supply shall be disconnected permanently.
Permanent Disconnection
4.67 The supply shall be disconnected permanently in following cases:
(a) On the termination of the agreement.
(b) If the cause for which the supply was temporarily disconnected is not removed
within the notice period.
Procedure for Reconnection
4.68.1 A connection that is disconnected permanently shall not be reconnected and the
consumer shall have to apply for a new connection.
4.68.2 In case of temporary disconnection, supply shall be reconnected after the cause of
disconnection has been removed.
4.68.3 If the disconnection was on account of non-payment of bill, the connection shall be
reconnected on an application of the consumer accompanied by the copy of the
notice, receipt of payment of dues along with the prescribed reconnection fee. Supply
shall be reconnected within 24 hours of the submission of the complete application.
However, if payment is made by Cheque (other than Banker’s Cheque) supply may
be reconnected after realisation of the Cheque.
4.68.4 In other cases, the applicant shallapply for reconnection after removal of the cause
along with the prescribed reconnection fee and the following documents:
(a) Receipt of payment .
(b) Test report by a LEC, if the disconnection was made under clause 4.66.1(c),
(d) and (e).
(c) Documentary evidence of removal of cause if disconnection was made under
clause 4.66.1 (b).
(d) An affidavit in cases covered under clause 4.66.1 (e).
The Licensee shall inspect the premises within 48 Hrs. and if he is satisfied that the
cause of disconnection has been removed the supply shall be reconnected within 24
hours of the inspection.
Reduction in Contracted load
4.69.1 Every application for reduction of contracted load shall be made in duplicate to the
concerned Sub division officer on prescribed form (Annex-4.9) along with the
Deleted: all dues are paid. ¶
Deleted: ,
Deleted: if any was due
31
prescribed processing fee and charges for reduction of load along with the following
documents:
(a) Work completion certificate and test report from a licensed electrical
contractor (where alteration of the installation is involved).
(b) Meter reading of the previous three months.
(c) Letter of approval from the Electrical Inspector, wherever applicable.
(d) Copy of the latest paid electricity bill.
4.69.2 The designated authority of the Licensee shall communicate to the consumer the
decision on his application within thirty days of receipt of the duly completed
application.
4.69.3 A fresh agreement for reduced load shall be executed for two years.
4.69.4 No refund shall be allowed for the deposited cost of the line and substation. However,
if the security deposited earlier is in excess of the requirement for the reduced load,
the excess shall be adjusted in future bills.
4.69.5 The effective date of such reduction shall be reckoned from the first day of the month
following the month in which the Licensee received the application, complete in all
respects.
4.69.6 The reduction in load shall not be permitted in following cases:
(a) If electricity dues are outstanding or a case relating to payment of electricity
bill is pending in a court of law.
(b) Arc/Induction furnaces, rolling and re-rolling mills and mini steel plants shall
not be allowed to reduce the load below the total rating of machines and
furnaces installed in the premises. Auxiliary load shall be excluded.
(c) Contracted load shall not be reduced below the total rating of installed
machines in case of Small & Medium industrial consumers having no MDI
meter and in case of private tube wells.
(d) Load shall not be reduced within 24 months of the date of commencement of
supply. However, if the consumer is willing to pay the fixed / minimum
charge applicable for the unreduced contracted load for the balance of the 24
month period or six months, whichever is less, reduction may be allowed.
No application for reduction of load shall be rejected without recording reasons and
the decision shall be communicated to the applicant.
Deleted: .
32
Procedure for Enhancement of Load
For Public Lighting
4.70 In notified areas and in public places belonging to the Development/Authorities/Trust
Boards/Municipal Corporations/City Municipalities/Housing Boards and such other
Authorities/ Bodies as may be approved by the Licensee, power supply to additional
public lamps or change in type of fitting shall be arranged subject to the following
conditions:
(a) The applicant shall apply in the prescribed form at the Sub-Division Office of
the Licensee on payment of prescribed registration cum processing fee.
(b) Licensee shall intimate the cost of arranging power supply within fifteen days.
(c) The applicant shall pay the estimated cost of the supply including the cost of
the security within one month of intimation.
(d) The applicant shall execute an Agreement in the prescribed form.
(e) The Licensee shall arrange to supply enhanced demand within fifteen days of
the amount deposited by the applicant.
(f) A suitable metal waterproof box to house the meter and street control M.C.B
as per Licensee’s approved design shall be provided.
For Cases other than Public Lighting
4.71.1 Applications for enhancement of load shall be filed in duplicate to the concerned sub-
divisional officer of the Licensee in the prescribed form (Annex 4.9) along with the
following:
(a) Prescribed Registration-cum-processing fee as approved by the Commission
from time to time.
(b) Work completion certificate and Test report from a Licensed Electrical
contractor.
(c) Letter of approval from the Electrical inspector, if required.
(d) Copy of the latest paid electricity bill.
471.2 If the system and voltage of supply do not change as a result of requested
enhancement and:
(a) The metering and related apparatus is not to be changed, enhancement shall be
sanctioned within 7 days and the consumer shall be required to deposit
additional security and system loading charges to cover the enhanced load and
enhancement shall be effected from the day security is deposited.
Rule 63 of 1956
33
(b) The metering and related apparatus needs to be changed, the load shall be
sanctioned within 7 days and consumer shall be (a) required to deposit the
additional security and (b) either deposit the cost for new meter and other
apparatus or procure it himself and supply to the Licensee. Licensee shall
inspect the premises of the consumer, after giving notice to the consumer to be
present along with the LEC or his representative, and if he is satisfied with the
wiring, shall fix the meter and related apparatus and seal it. The enhancement
shall be effective immediately thereafter.
4.71.3 If there is a change in the system or voltage of supply the procedure for sanction of
enhanced load shall be the same as for a new connection as detailed in clause 4.8 and
4.18.
4.71.4 A fresh agreement for enhanced load shall be executed for a minimum period of two
years.
Transfer of Connection and Mutation of Names
4.72 A connection may be transferred in the name of another person upon the death of the
consumer or in case of transfer of ownership or occupancy of the premises, upon an
application of the consumer.
4.72.1 Application for mutation is to be filed, in the prescribed format (Annex 4.10), along
with prescribed fee by the transferee or the legal heir or successor of the deceased
consumer with the local office of the Licensee. The application shall be accompanied
by documentary evidence of transfer or legal heir ship or succession and proof of no
arrears on account of electricity charges on that connection. The Licensee shall decide
the mutation case within 21 days. If the mutation application is allowed, intimation
shall be sent to the applicant along with information regarding pending dues against
the connection and the formalities that are to be completed for transfer to take effect.
However, if the mutation application is to be disallowed and mutation is to be refused
the orders shall be passed only after the applicant has been given an opportunity to
present and to hear him about his case, by an speaking order.
4.72.2 The transferee or the legal heir shall submit a fresh agreement, in the prescribed
format, along with pending dues, if any, within 30 days. The transfer shall be affected
and a copy of the agreement shall be sent to the consumer within 7 days.
34
Procedure in Case of Change in Wiring and /or Apparatus or Shifting of Service
Line in the Premises of the Consumer
4.73.1 The consumer shall get all work relating to wiring on his premises only by or under
the supervision of a Licensed Electrical Contractor and obtain a Work Completion
certificate and Test report, as prescribed by Indian Electricity Rules, 1956.
4.73.2 No reference shall be made to the Licensee if the change in wiring of LT loads does
not result in dislocation of the meter or other related apparatus and there is no change
in the load. However, the consumer shall produce the test report if required by the
Licensee in future.
4.73.3 In other cases, if the consumer desires to alter the wiring on his premises, or change
the location of meter or other related apparatus or shift the service line on his
premises notice thereof shall be sent in writing with the modified wiring diagram and
other necessary details to the Licensee. The Licensee shall after due enquiry grant
approval, with or without modification to the proposal, or reject the request stating
reasons thereof, in writing, within 15 days.
4.73.4 The work relating to change in wiring shall be done by the consumer through a
licensed electrical contractor and the Work completion certificate along with test
results shall be provided to the Licensee. The Licensee shall, within one week, inspect
the premises to confirm that the alteration/s are in accordance with the approval given
by him and the Indian Electricity Rules 1956.
4.73.5 The work of change in position of point of supply, meter or related apparatus and
shifting of service line shall be done by the Licensee at the cost of the consumer. The
estimate for this work shall be sent to the consumer along with the approval and work
shall be completed within 15 days of the money being deposited.
Resale of Energy
4.74 The Consumer shall not supply any energy supplied to him by the Licensee to another
person or other premises unless he holds a suitable sanction or licence for distribution
and sale of energy granted by the Commission/State Government or has been
exempted by the Commission from holding license for sale.
4.75 In case of Commercial, office or residential complexes, where Power supply is
availed originally in the name of the builder or promoter of the complex and who
subsequently transfers the ownership of the complex, either entirely, to different
Deleted: For LT loads,
Deleted: any
Deleted: , no reference is to be made to the Licensee.
35
individuals or partly to different individuals retaining the balance for lease, the power
supply may be continued in the following methods.
(a) The builder or promoter of the complex in whose name the supply continues,
is permitted to extend power supply to the individual owners of the flats etc.
or to the lessee by installing sub-meters and to collect the cost of consumption
of power from them on no profit or no loss basis (i.e. sharing of expenses of
consumption of electricity) and this shall not be treated as unauthorized
extension of supply or resale of energy.
(b) In case, the promoter or builder of the complex does not wish to have any
stake in the complex after promoting the complex, the service connection
originally availed may be permitted to be transferred in the name of an
Association or Society that may be formed in the complex and registered and
the service agency so formed is permitted to extend supply to the individual
owners of the flats etc. or lessees by installing sub-meters and to collect the
cost for consumption of power from them on no profit or no loss basis (i.e.,
sharing of expenses of consumption of electricity) and this shall not be treated
as unauthorized extension or resale of energy.
4.76 A panchayat/cooperative or a registered association of consumers may apply for
supply of electricity to a group of consumers at a single point. In such cases, the body
that has taken the connection shall be responsible for all payments of electrical
charges to the Licensee and for collection from the consumers.
Deleted: village panchayat
Deleted: s
Deleted: end
36
Chapter 5
Metering
Requirement of Meters
5.1 No new connection shall be given with out a Meter and Miniature Circuit Breaker
(MCB) or Circuit Breaker (CB) of appropriate specification from the date of issue of
this code.
5.2 The Licensee shall not supply electricity to any person, after expiry of three years
from the date of issue of this code, except through a meter, provided the Commission
may, by notification, extend the said period of three years for a class or classes of
persons or for such area as may be specified in that notification.
5.3 The Meters for new connections shall be of following type (s):
(a) For load up to 1 KW in urban areas - Electromechanical or Static meters
and all domestic and Commercial
loads in Rural areas
(b) For load more than 1KW in urban areas - Static Meters
(c) For HT / EHT consumers - 3 Phase Tri-vector meters with MDI.
The meters shall have a facility
for “Time of the Day Metering”
and storage of at least 45 days.
The consumer shall have the
option to install meter having
facility to record peak hours MDI
in addition to above features.
In situation where the Licensee is having a problem in collection of energy dues, the
Licensee may install pre-paid meters. The meters shall conform to the technical
requirements as prescribed by Rule 57 of the Indian Electricity Rules, 1956.
5.4 If supply is provided by the Licensee to different categories of consumers in the same
premises, separate meter(s) shall be installed for measurement of energy for each
such category.
5.5 For LT loads MCBs and for HT/ EHT loads CB of appropriate, rating and
specifications as approved by the Licensee shall be installed along with the meter.
Deleted: <#>¶
37
5.6 In case of HT loads up to 250 KW, metering may be made at the LT end, at the
option of the Licensee. In such cases, HT reading for billing purposes shall be
computed by adding 2 percent to the Maximum Demand reading and 3 percent to the
KWh reading recorded on the LT meters.
5.7 If supply to a HT / EHT consumer is given on an independent feeder for his exclusive
use the metering arrangement shall be installed at the consumer’s premises or, if
mutually agreed the metering arrangement at the Sub station of the Licensee may be
used for billing and no meter need be installed at the premises of the consumer.
5.8 The group of consumers may opt for metering at distribution transformer in place of
individual metering in low-density areas. The Licensee may submit a detailed
proposal for such metering to the Commission for approval.
Supply and Installation of Meters and MCBs / CBs
5.9 At the time of seeking a new connection the consumer shall have the option to either:
(a) Purchase the meter, MCB/CB and associated equipment himself from a
vendor(s) and of a make and specification approved by the Licensee from
time-to-time
OR
(b) To require that the meter, MCB/CB and associated equipment be supplied by
the Licensee.
The Consumer shall indicate this option in the application form and Licensee shall
supply him with the list of approved vendor(s) and Make(s).
5.10 HT and LT consumers, if they opt for procurement of meter and related apparatus,
shall provide a locked and weatherproof enclosure of a design approved by the
Licensee to house the metering equipment including CTs and PTs. In other cases,
these shall be included in the estimate and provided by the Licensee.
5.11 If meter is supplied by the Licensee, the recovery of the cost of the meter and
associated equipment shall be made in one or more installments as per the terms
approved by the Commission.
Note: Sub-section (3) of section 26 of the 1910 Act, covers the cases where meter is
provided by the consumer. Sub-section (1) thereof provides that in case a consumer
so requires, the Licensee shall cause the consumer to be supplied with a meter but in
that case the consumer will have to give security for the price of the meter and also
agree to pay hire charges for the meter by means of an agreement to be entered into.
Deleted:
38
As per the experience and for the benefit/convenience of the consumer, it has been
considered expedient that, normally speaking, the consumer may be required to
arrange his own meter, more so when he has otherwise also to deposit the security
amount equal to the price of the meter in addition to the liability of payment of hire
charges.
It is accordingly provided that the cost of the meter shall be provided by the
consumer.
5.12 In case of connections where cost of the meter has been borne by the consumer, no
meter rental shall be charged from the consumer.
5.13 Meter shall be installed by the Licensee at the point of supply in such a manner that it
is always accessible to the Licensee for meter reading and other purposes. In case of
multi-storied buildings, it shall be fixed preferably on the ground floor/rising mains.
5.14 Whenever a new meter is installed (as a replacement or for a new connection) it shall
be sealed in the presence of the consumer and a Meter History card shall be prepared
in two copies. The Licensee shall retain a copy and the second copy shall be tagged to
the meter. Subsequently, details of any faults in the meter, repairs etc. shall be entered
into this card by the Licensee. The seal, name plates and distinguishing numbers or
marks affixed on the said equipment or apparatus shall not in any way be broken,
erased or altered by the consumer.
5.15 The consumer shall be responsible for safe custody of Meter(s), MCB/CB etc. except
in cases where such Meter(s), MCB/CB etc. are installed in the premises of the
Licensee.
5.16 A consumer may install a check meter of appropriate make and conforming to the
technical specifications as laid down in Rule 57 of the Indian Electricity Rules, 1956.
These check meters may be calibrated by the Licensee upon payment of prescribed
fee. However, check meter readings shall not be used for billing purpose by the
Licensee.
5.17 Testing of Meters
(a) It shall be the responsibility of the Licensee to satisfy himself regarding the
accuracy of the meter before it is installed and may test them for this purpose.
(b) Licensee shall conduct periodical inspection/testing of the meters as per the
following schedule:
(i) Single phase meters Once every five years
Rule 56 of 1956
Rule 46 of 1956
Formatted: Bullets and Numbering
Deleted: defective meters replaced
Deleted: <#>The responsibility of keeping the meter under safe custody lies with the consumer. The Licensee may charge appropriate fee for replacing or repairing the meter parts that are damaged.¶
39
(ii) LT 3 phase meters Once every 3 years
(iii) HT meters including MDI Yearly.
Wherever applicable, CT and PT shall also be tested along with meters
(c) The test results shall be maintained in accordance with Rule 57 of Indian
Electricity Rules, 1956.
Defective Meters
5.18 The Licensee shall have the right to test any meter and related apparatus if there is a
reasonable doubt about the accuracy of the meter and the consumer shall provide the
Licensee necessary assistance in conduct of test. However, the consumer shall be
allowed to be present during the testing.
5.19 A consumer may request the Licensee to test the meter on his premises if he doubts
its accuracy, by applying to the Licensee in prescribed format (Annex 5.1) along with
the requisite testing fee. Licensee shall test the meter within 30 days of the receipt of
the application.
5.20 In all cases of testing of a meter in the laboratory, consumer shall be informed of the
proposed date of testing at least 7 days in advance so that he may be present at the
time of testing, personally or through an authorized representative. The signature of
the consumer or his authorized representative, if any present, be obtained on the Test
Result Sheet.
5.21 If the meter is tested as defective (slow or fast) and the test results are not disputed by
the consumer, the meter shall be replaced after repairs or with a new meter within 10
days and bills of previous three months prior to the month in which the dispute has
arisen shall be adjusted as per the test results. In case the meter is found to be fast,
the refund shall be adjusted in the next bill. In case meter is found to be slow,
additional charges shall be recovered along with the next bill. However, upon a
request of the consumer, these charges may be recovered in installments not
exceeding three.
5.22 If a consumer disputes the results of testing, he may appeal to the Electrical Inspector
who shall adjudicate upon the matter and give his decision within one month of the
application. The decision of the Inspector shall be binding on both the Licensee and
the consumer.
Formatted: Bullets and Numbering
Deleted: cycles
40
Meter (Including MDI) Not Recording
5.23 The consumer is expected to intimate the Licensee, as soon as he notices that meter
has stopped/not recording.
5.24 If during periodic or other inspection any meter is found to be not recording by the
Licensee or a consumer makes a complaint in this regard, the Licensee shall arrange
to test the meter within 15 days and the procedure detailed in clause 5.20 shall be
followed.
5.25 If the meter is actually found to be not recording it shall be replaced within 15 days of
the test.
5.26.1 The Consumer shall be billed, for the period between the date of last reading and the
date of replacement of the defective meter, on the basis of average consumption and
maximum demand of previous three billing cycles. The provisional bills, if any
issued, shall be accordingly adjusted.
5.26.2 In cases where the recorded consumption of past three billing cycles prior to the date
meter became defective is either not available or partially available, the consumption
pattern as obtained from such lesser period along with the above mentioned
subsequent three billing cycles shall be deemed sufficient for estimation of
consumption.
5.26.3 In calculation of average consumption, due consideration of seasonality of load shall
be made and in such cases consumption of previous year for same period shall be
taken.
Burnt Meters
5.27 In case a meter is found burnt either on consumer’s complaint or upon the inspection
of the Licensee:
(a) The Licensee shall restore the supply immediately by passing the burnt meter
after ensuring that necessary preventive action at site is taken to avoid future
damage.
(b) A new meter shall be installed by the Licensee within 5 days.
5.28 If possible, the Licensee shall test the burnt meter removed from the consumer
premises and the procedure detailed in clause 5.20 shall be followed. If it is not
possible to test the meter, the consumer shall be billed as per the procedure specified
in clause 5.26.
Formatted: Bullets and Numbering
Deleted: 7
Deleted: 7
Deleted: 10
41
5.29 The Consumer shall be billed, for the period between the date of last reading and the
date of replacement of the burnt meter, on the basis of the average consumption of
previous three billing cycles and the provisional bills, if any issued, shall be
accordingly adjusted.
Cost of Replacement of Defective / Burnt Meters
5.30 If the cost of the meter was not borne by the consumer initially the cost of replacement
shall be borne by the consumer and thereafter no meter rental shall be charged from
him.
5.31 If the initial cost of the meter was borne by the consumer and the meter is less than 15
years old the cost of replacing the meter shall be borne by the Licensee and otherwise
by the consumer subject to following exceptions:
(a) If, as a result of testing, it is established that the meter was burnt due to
technical reasons viz. voltage fluctuation, transients etc. attributable to the
Licensee the cost of the meter shall be borne by the Licensee. However, if it is
established that the meter was burnt due to reasons attributable to the
consumer viz. defect in consumer’s installation, connection of unauthorized
load by the consumer etc. the cost shall be borne by the consumer.
(b) If it is established, as a result of testing, that the meter was rendered defective
due to tampering or any other deliberate act by consumer to interfere with the
meter the cost of the meter shall be borne by the consumer. The consumer
shall be assessed as per clause 6.17. In addition, action as permissible under
law shall be taken against the consumer for pilferage and tampering.
5.32 In all cases of replacement of a meter, where cost is to be borne by the consumer, he
shall have the option to procure the meter and associated equipment himself and
action shall be taken as per clause 5.3 and 5.9.
Lost Meters
5.33.1 Complaints regarding lost meters shall be entertained by the Licensee only if they are
accompanied by a copy of the FIR lodged by the consumer with the police station. In
all such cases, an officer authorized by the Licensee shall also conduct an inquiry.
5.33.2 Supply in these cases shall be restored after installation of a new meter, payment of,
electricity charges for the period in which meter was not available and any other
prescribed charges that may be approved by the Commission. The electricity charges
for the period in which meter was not available shall be assessed as below:
42
(a) As per clause 6.17 of the Code, if it is established in the Licensee’s enquiry that
the loss of meter was due to a deliberate act of the consumer and / or with his
connivance.
(b) As per clause 5.26 of the Code, in other cases.
5.33.3 In all cases of loss of meter, cost of new meter and other apparatus shall be borne by
the consumer.
43
Chapter 6
Billing
Bills
6.1 The Licensee shall notify the Billing cycle and the date by which consumer shall
receive the bill, for different categories of consumers after approval of the
Commission.
6.2 The Licensee may give an option of “Spot Billing” system to the domestic and
commercial consumers in a notified distribution area.
6.3 If a consumer opts for “Spot Billing” system, he shall be responsible for taking the
correct reading of the meter within a week (before or after) of the meter reading date
mentioned on the last bill and obtain his bill from the notified billing office of the
Licensee.
6.4 In other areas, meter shall be read by an authorised representative of the Licensee
once every billing cycle. The Licensee shall issue proper identity cards to the meter
readers. The meter reader shall also record the meter reading in the meter card at the
consumer’s premises.
6.5 The Licensee shall dispatch the bills at least 15 days prior to the Due date of payment.
The Bill shall contain details of the energy consumption, various charges, due date of
payment, disconnection date etc. as given in Annex 6.1.
6.6 In cases of unmetered consumers having fixed monthly bill the Licensee may issue a
Passbook in which payments made by the consumer shall be recorded.
6.7 If a consumer does not receive the bill within 15 days of the Next Meter Reading
Date mentioned on the previous bill, he may obtain a duplicate bill from the
concerned billing office of the Licensee.
Bills when Meter Reading not Available
6.8 In all cases not covered by the “Spot Billing System”, if Licensee is not able to read
the meter, a provisional bill may be issued on the basis of the average consumption of
the previous 3 billing cycles. However, the Licensee shall ensure that such
provisional billing does not extend to more than two billing cycles at a stretch. The
provisional bills shall be adjusted on the basis of the subsequent actual meter reading.
Formatted: Bullets and Numbering
Deleted: Page Break
44
6.9 If the meter is not read as it was not accessible in two consecutive billing cycles,
provisional bills shall be issued on the basis of the average consumption of previous 3
bills and a notice shall be issued to consumer to keep the meter accessible for reading
on a date (at least 7 days after the date of notice) and time specified in the notice.
6.10 If meter is not made accessible even on the due date, a notice shall be served on the
consumer, if available, or affixed near the main entrance of the premises, to either get
the meter read by the Licensee, after payment of a penalty charge as laid down by the
Commission within next 7 days, failing which the supply shall be disconnected.
6.11 The provisions of clause 6.9 and 6.10 shall not apply in case of a domestic consumer
who has given an advance intimation to the Licensee of the inaccessibility of the
meter for reading due to the consumer being out of station and if he has deposited an
amount that covers the minimum/ fixed charges for the duration of the proposed
absence. Such provisional payment shall be adjusted when subsequent bill is issued
on the basis of actual meter reading. If, however, the consumer is found to be actually
using electricity during the period when he was away, the Licensee may impose a
penalty for mis-declaration.
Special Reading of Meters in cases of Change of Occupancy / Vacancy of
Premises for Domestic Consumers
6.12 It shall be the responsibility of the consumer to get his connection disconnected if he
vacates the premises as otherwise he shall continue to remain liable for all charges.
6.13 Notice and request for disconnection is to be given at least 15 days before the
proposed date of vacation. However, the Licensee may accept a notice of shorter
period. The Licensee shall arrange to take a special reading of the meter after
intimating the consumer. The special bill shall also include a payment for three days
following the meter reading date on a pro-rata basis. The connection shall be
disconnected on the 3rd day after the day meter was read and the consumer shall be
required to settle all dues within this period.
Advance Payment of Bills
6.14 A consumer may make advance payment of electricity bills for a period not
exceeding 12 months. Upon receipt of a request in the prescribed format (Annex 6.2),
the concerned AE, Revenue (AE (R)) shall prepare a provisional bill based on the
average consumption of previous one year and the consumer shall make payment
against this bill. No interest shall be paid on the unadjusted balance amount lying
45
with the Licensee. The advance payment shall be applied against the future bills
based on actual meter readings. The Bills shall reflect the balance in the account and
the customer shall be required to pay the amount due, in the usual manner, whenever
the bill shows a debit balance and all consequences of non-payment of bill shall
follow.
Disputed Bills
6.15 If there is an error of a non-pecuniary nature (incorrect name, address etc.) in the bill
the complaint shall be registered with the concerned AE(R) or Executive Engineer,
Revenue (EE(R)). Corrections, if any required, shall be made in the next bill. The
consumer shall be required to make the payment before due date.
6.16 If the consumer disputes the accuracy of any bill he may either make the payment
under protest and file a complaint with the AE(R) or EE(R), as the case may be, or
file a complaint before the due date for payment. The complaint shall be decided
within 7 days and consumer shall be informed.
(a) If the Complaint is found to be correct by AE(R)/ EE(R) a revised bill shall be
issued within 7 days of the complaint and consumer shall be given 7 days to
make the payment. The Consumer shall not be charged any late payment
surcharge (and he shall be eligible for timely payment rebate, if any
applicable) if the payment is made by the revised date. If payment has already
been made, excess amount shall be adjusted in subsequent bills.
(b) If the complaint was found to be incorrect the consumer shall be notified and
directed to make the payment, if not already paid, as per the original bill
immediately and the consumer shall be liable to pay the late payment
surcharge.
Billing in case of Theft of Electricity / Tempering of Meter
6.17.1 In case of theft of electricity the consumer shall be liable to pay a sum towards penalty /
compensation to the Licensee as per assessment made, in addition to any other action that
may be taken against him under any other law
The units of the electricity consumed shall be assessed in the following manner:
Units Assessed = L * F * D*H.
Where L = is the connected load in kW.
Deleted: 6.17
46
H = is the average number of hours per day the supply is made
available in the Distribution mains, feeding the consumer.
D = If the number of days for which the theft took place can be
ascertained on the basis of satisfactory evidence then actual
number or days. In other cases, this factor be taken equivalent
to 180.
F = for different types of supply as given below:
(a) For L & F and domestic power consumes F = 0.30
(b) For Commercial L & F and power consumers F = 0.50
(c) For Small and Medium power consumers
(up to 50 kW) F = 0.50
(d) For large and heavy power consumer
(With load above 50 KW) F = 0.75
(e) In case of large and heavy power consumers
for the purpose of assessment, the demand
for the month shall be taken as contracted
demand of the consumer or 75 per cent of the
connected load at the time of inspection,
which- ever is less.
(f) Categories not covered above F= 0.50
6.17.2 The consumption so assessed shall be charged at thrice the rate per unit of the tariff
applicable to the consumer category excluding the consumption recorded by the
meter that shall be charged at the appropriate tariff rates. The amount billed at this
rate (thrice the tariff rate) shall not be taken into consideration for the purpose of
computing consumer’s liability to pay monthly/annually minimum charges, wherever
applicable.
Billing in Case of Excess Load
6.18 In cases where MDI is installed the assessment shall be made as per the provisions of
the Tariff order. In cases where no MDI is installed, the excess load shall be billed as
per the formula given in clause 6.17 but at two times the rate applicable in the tariff
order. The ‘L’ in the formula shall be computed as per below:
Deleted: s
Deleted: excluding
Deleted: t
47
(a) In Domestic category, 50% of the difference between the actual connected
load and two times the contracted load
(b) In commercial category, 75% of the difference between the actual load and
1.33 times the contracted load.
(c) In other cases difference between the connected load and the contracted load.
6.19 In case the consumer exceeds the sanctioned protective load during scheduled
rostering, he shall be liable to pay double the prescribed charges, as provided in the
Tariff Schedule, for the load exceeding the sanctioned protective load.
Billing in case of Unauthorized, Supply /Sale or Use of Electricity
6.20 If at any time energy supplied to a Consumer / premises is found extended
unauthorizedly to some other person / premises, the Licensee shall assess the
quantum of energy and excess load so extended and charge for that quantum for such
period as may be deemed justified in the circumstances of any given case subject to a
maximum period of 6 months, at thrice the normal rate of Tariff applicable for the
purpose for which the energy is so extended.
6.21 If it is found at any time that the energy supplied is used for a purpose on which
higher tariff is applicable, the total energy consumed in the previous 3 (Three) months
from the date of detection shall be charged at twice the rate applicable for the
category for which load was found to have been used. This shall not relieve the
consumer from any penalty imposed by law or under any other provisions of the
Code.
6.22 A consumer aggrieved by the order of AE (R) or EE (R), as the case may be, may file
an application as per procedure detailed in clause 7.18.
Mode of Payment
6.23.1 The Consumer may make payment of the bill by Cash (up to Rs 20000), Cheque,
Demand Draft or Money Order. Payment by Cheque shall be accepted only if it has
been drawn on a Bank located at the Headquarters of the Divisional office. The date
of payment by cheque shall be deemed to be the date on which the cheque is received
in the office of the Licensee, provided that the cheque is encashed within 7 days of
presentation to the Bank and is not dishonored. In case a cheque is not encashed
within 7 days of presentation to the bank, the consumer shall forfeit rebate and the
Licensee may levy surcharge and also withdraw the facility of payment by cheque.
6.23.2 The Payment may be made:
Formatted: Bullets and Numbering
Deleted: .20
48
(a) In person at the designated collection offices of the Licensee during specified
times or
(b) By post or courier or.
(c) By deposit in the Drop-boxes maintained by the Licensee at designated
locations.
6.24 In case a cheque is dishonoured or a draft is not realized within the period prescribed
in Clause 6.23.1, the Licensee shall inform the consumer and require him to pay the
bill within 7 days in cash. The consumer shall be liable to pay the late payment
surcharge, as applicable, as well as a charge on account of the dishonour of the
cheque/non realization of the draft. If there are two instances of dishonour of
cheques/draft of a consumer in a financial year, the consumer shall be required to
make all payments in cash till the end of the following financial year. In addition the
Licensee may initiate action against the consumer under sections 138 and 142 of The
Negotiable Instruments Act.
6.25 In addition to the mode of payments specified in clause 6.23, the Licensee may notify
schemes for acceptance of Bill payment through Electronic Clearing System or at
designated counters of a bank or through credit /debit cards or through any other
means in a specified area and / or for a specified category of consumers, after due
notice is given to the consumers. However, any change in the Mode of Payment shall
be more friendly for the consumers than the prevailing system.
6.26 Where the due date indicated for payment on the bill falls on a Sunday or a public
holiday, the payment shall be due on the next working day.
Receipt
6.27 Receipt shall be given to the consumer for payment of bills made in person. In all
cases, payments shall be acknowledged in the next bill.
Application of the Amount Received
6.28 The amount paid by the consumer shall be first adjusted towards electricity duty
provided that in case of part payment by the consumer, the proportionate share of the
duty from the total collection shall be adjusted first. Out of the balance, adjustments
shall be made in the following order of priority: -
(a) Arrear of electricity charges
(b) Arrear of electricity duty
(c) Late payment surcharge
Formatted: Bullets and Numbering
Formatted: Bullets and Numbering
Deleted: for a period of 3
Deleted: s
Deleted: ¶
49
(d) Current Electricity charges
(e) Current electricity duty
(f) Miscellaneous charges
Rebate and Late Payment Surcharge
6.29 Rebate and Surcharge for delayed payment shall be levied as per the tariff order.
Installment Facility
6.30 The Licensee may frame a scheme, with the approval of the Commission, for
providing facility of payment of bills in installments, for consumers who are for the
time being under financial distress.
Recovery of Arrears
6.31.1 The payments due to the Licensee shall be recovered as arrears of land revenue as per
the provisions of the U.P. Government Electrical Undertaking (Dues Recovery) Act,
1958, as amended from time to time.
6.31.2 No sum due from any consumer, on account of default in payment shall be
recoverable after the period of two years from the date when such sum became first
due unless such sum has been shown continuously as recoverable as arrear of charges
for electricity supplied.
Deleted: ¶¶¶
50
Chapter 7
Standards of Service and
Procedure for Redressal of Consumer Grievances
7.1 The Licensee shall organize its systems and work processes so as to achieve the
standards of performance of customer service as subsequently detailed in this chapter.
7.2 The Licensee shall ensure that wide publicity is made of all the procedures that relate
to consumers by way of brochures, pamphlets, publication in newspapers (wherever
so required by rules or regulations) as well as electronic media. Copies of these
procedures shall be sent to all Panchayat offices free of cost and shall be available for
public through the local offices of the Licensee on payment of nominal charges.
These procedures shall also be posted on the website of the Licensee. Changes /
amendments in these rules are also to be widely publicized.
7.3 The Licensee shall always endeavour that the consumers are adequately and timely
briefed about their rights and responsibilities and about action taken on their
complaints / grievances.
7.4 The standards of customer service for
(a) new connections/disconnections/re-connections and related matters,
(b) metering,
(c) billing and
(d) availability of supply and its quality
shall not fall short of the details given in Chapter 4, 5, 6 and 7 respectively.
Availability of Supply and its Quality
7.5 All complaints regarding availability of supply and /or the quality of supply shall be
lodged with the concerned substation in writing or by telephone or through Internet
wherever such facility is available. The Licensee shall arrange to receive supply
related complaints 24 hours on all days of the week. Complaints shall be recorded in
a register and the complaint number shall be given to the consumer.
7.6 Licensee shall also set up Central Control Rooms (CCRs) in phases in all cities with
population exceeding 5 lakh. CCRs shall be provided telephones with adequate
number of lines and shall be connected to all the substations in the city by telephone
as well as an alternative mode such as wireless / Paging System. If, for some reason, a
consumer is unable to contact the substation, he may complain at the CCR who shall
51
be responsible to lodge the complaint with the concerned substation. The CCRs shall
also operate an automatic answering service that shall give updated information about
scheduled outages/rostering in the city area as well as details of unscheduled outage
in a large area (a substation) and the likely time by which the supply is likely to be
restored.
7.7 The Licensee shall give notice of all scheduled outages (including rostering)
exceeding 60 minutes in any area by way of notices published in the newspaper at
least 24 hours prior to the outage schedule and through CCRs. The Licensee shall also
display scheduled rostering on the notice board of the concerned 33/11 KV Sub
station. Licensee shall make all efforts to ensure that the scheduled outages are
planned in a manner that causes least inconvenience to the consumers and preferably
supply shall be restored before nightfall.
7.8 In case, there is an unscheduled disruption of supply in a large area and the disruption
is likely to last for more than 60 minutes, the Licensee shall inform the time when
supply is likely to be restored through all available means such as radio/cable TV etc
to the consumers of the affected area .
7.9 The supply related complaints shall be attended to within following time limits:
1. In case of blown fuse from distribution mains/
service pole
a. Within 4 hours in towns and cities.
b. Within 8 Hours in rural areas.
2. In case of line break down:
a. Within 8 hours in towns and cities.
b. Within 48 hours in rural areas.
3. In case of distribution Transformer failure:
a. Within 24 hours in towns and cities
b. Within 72 hours in rural areas.
A. Interruption/Failure of
Power Supply
4. In case of major failure involving Power
Transformers (33 KV and above):
Within 15 days. (Alternative supply to be restored as
early as possible)
B. Voltage Variation 1. Within 24 hours in case of local problems.
Deleted: 6
Deleted: may
Deleted: to use the medium of radio / cable etc. to announce the disruption and
52
2. Within 3 months in case of inadequacy of LT
distribution system.
3. Within 9 months in case of deficiency in the HT
distribution system.
7.10 The time limits indicated above are the outer limits and the Licensee shall endeavour
to restore the supply in the least possible time. In all cases, the Licensee shall also
endeavour to inform the complainant of the time by when the proper supply is likely
to be restored.
Procedure for Redressal of Consumer Grievances
7.11 The redressal of the consumer grievances arising out of failure of the Licensee to
meet the standards of service shall be done in the following manner:
New Connection/Re-connection/Disconnection
7.12 In case a new connection is not released or disconnection is not made upon the
request of the consumer or supply is not reconnected within the time limits specified
above consumer may either approach the EE of the division in person or send a
written complaint in the prescribed format (Annex 7.1)..
7.13 The EE shall inquire into the grievance and:
(a) Get the supply reconnected or disconnected, as the case may be, within 24
hours if the consumer has completed all the necessary formalities.
(b) In case of a grievance regarding new connections, within 3 days in urban and
7 days in rural areas, inform the consumer of the reasons for the delay and
likely date by which the supply shall be given.
Supply Interruptions
7.14 In case of a complaint regarding supply interruption, if supply is not restored within
the time limit specified above, the consumer may approach the Sub Divisional officer
(SDO). The SDO shall immediately inquire into the reasons for the delay and inform
the consumer and also intimate the likely time by which the supply shall be restored.
All such cases shall be brought to the notice of the EE of the division who shall
ensure that the supply is restored at the earliest. The names, address and phone nos. of
the concerned officials/officers shall be displayed in the sub-station.
Deleted: The EE shall be available in his office on all working days, during notified hours, to meet with the consumers
53
7.15 All cases of interruption of supply exceeding 48 hours in urban areas and 5 days in
rural areas shall be reported to the Commission by the Licensee in a report to be sent
monthly in the prescribed format.
Meter
7.16 In case a meter complaint is not attended to and resolved within the specified time
limit the consumer may approach the EE (Meter) concerned who shall ensure that the
complaint is attended to within 7 days of the grievance.
7.17 If a consumer disputes the result of a meter testing, he may appeal to the Electrical
Inspector who shall adjudicate upon the matter and give his decision within one
month. An appeal from the order of the Electrical Inspector lies with the Commission
as per section 35 of the Act.
Billing
7.18 If a billing complaint is not attended to and resolved within the specified time limit
the consumer may approach EE (Distribution) or DGM (in case original complaint
was lodged with EE (revenue)) who shall ensure that the complaint is resolved within
7 days.
7.19 If a consumer is aggrieved by the decision of the AE (Revenue) or EE (Revenue) he
may appeal to the EE (Distribution) or DGM respectively, within 30 days who shall
dispose off the appeal within 30 days. However, no such appeal shall be admitted
unless the consumer has paid the full amount as adjudicated upon by EE / AE
(Revenue).
7.20 An appeal from the order of the EE or DGM shall lie to the Appellate committee as
per the procedure detailed in Annex 7.2.
Monitoring of Redressal of Grievances
7.21 The Licensee shall set up systems for monitoring by senior management of
performance against service standards.
7.22 The EE shall be available in his office on all working days, during notified hours, to
meet with the consumers. The Superintending Engineer /DGM of the circle and the
Chief Engineer /GM of the Zone shall schedule at least one day per week to meet
with the public and listen to their grievances during notified hours. This shall be
widely publicized.
7.23.1 The Licensee shall constitute Electricity Advisory Committees at the district levels.
These committees shall have representation of the important district officials, the
Deleted: two days in a month
54
Executive Engineers of all the divisions in the district, representatives of consumers
and District Panchayat. The number of members may be fixed by the Licensee, which
shall not exceed 15.
7.23.2 The Licensee shall constitute Local Electricity Advisory Committee also at the
substation level. This committee shall have representation of the concerned local,
district officials, Sub-divisional officer, Executive Engineer, Gram Pradhans and
representative of the consumers. The number of members of Local Electricity
Advisory Committee may be decided by the Licensee. However, the number of
members shall not be more than 15.
7.23.3 These committees shall meet once every quarter and review the general condition of
supply in the district and also the status of compliance with the standards of
performance as detailed in this code.
7.24 A quarterly report shall be sent to the Commission detailing the number of grievances
received and their disposal, in the prescribed format.
Complaints before the Electrical Inspector
7.25 A consumer not satisfied with the decision of the Licensee after exhausting the
channels for redressal of grievance setup by the Licensee, may approach to the
Electrical Inspector for grievances related to accuracy of meter, as per section 26 of
the Indian Electricity Act, 1910.
Complaints before the Commission
7.26 In case of grievance related to accuracy of meter the Commission may be approached,
only if the consumer is not satisfied with the decision of Electrical Inspector. In other
cases, the Commission may be approached only after a consumer has exhausted the
channels for redressal of grievance set up by the Licensee, as specified above.
7.27 Complaints to the Commission shall fall into two categories:
(a) Cases where the Licensee has failed to respond to a service complaint within the
prescribed time limit and;
(b) Cases where the consumer is aggrieved by the decision of the
Licensee/Electrical Inspector about a complaint or a grievance.
7.28 Complaints regarding ‘failure to respond’ to a service complaint may be sent to the
“Consumer Affairs” section of the Commission in writing in Hindi/Urdu/English. The
complaint shall contain the evidence that the consumer has exhausted the channel of
the Licensee before approaching the Commission. In all cases, the complaint shall be
55
acknowledged and a copy sent to the Licensee requiring him to respond to the
complaint within specified time. The Commission shall monitor such complaints and
consumer shall be informed about the action taken.
7.29 If a consumer is aggrieved by the decision of the Licensee/Electrical Inspector as
specified in clause 7.26, he may file a petition to the Commission under Section 34/
35 of the Act, as per the procedure specified in the Conduct of Business Regulation,
2000 of the Commission. In addition to meeting the requirements laid down in the
Business Regulations, such petitions shall be accompanied by the following:
(a) Documentary evidence that the procedure for redressal of grievance of the
Licensee, as detailed above has been fully complied.
(b) Statement regarding any complaint/suit filed with the Consumer Court or any
other court on the same issue.
Complaints shall not be admitted by the Commission for hearing unless they are
accompanied by the above two documents.
56
Chapter 8
General Provisions
Force Majure and Restrictions on Supply of Power
8.1 The Licensee may direct the consumer to curtail, stagger or altogether stop using
supply in any of the following conditions and the Licensee shall not be liable for any
claim on account of loss or damage arising out of failure of supply in such conditions.
(a) When such failure is due, either directly or indirectly, to war, mutiny, civil
commotion, riot, strike, lockout, fire, flood, tempest, lightning, earthquake or
other forced incidents such as break down of equipment, overhead lines and
cables or causes beyond the control of the Licensee.
(b) In the event of restriction on power supply imposed by the State Government
under section 22-B of the Indian Electricity Act, 1910, or by the Commission in
exercise of powers under the Act.
(c) In case of a major breakdown in the supply system of the Licensee such as Grid
Failure that warrants curtailment of load.
Demand Side Management
8.2 It shall be the duty of every consumer to stop wastage and inefficient use of
electricity and to extend necessary cooperation to the Licensee in implementation of
the programs for Demand Side Management that may be launched by the Licensee.
Compensation for Damage
8.3 A Licensee shall, in exercise of any of the powers conferred by or under IE Act,
1910, and by or under this Code cause as little damage, detriment and inconvenience
as may be, and shall make full compensation for any damage, detriment or
inconvenience caused by him or by any one employed by him.
Arbitration and Appeals
8.4 The provisions for appeal in different cases have been mentioned in the Code. The
Commission may be approached under Section 34 of the Act after the consumer has
exhausted the channels of appeal and grievance redressal established by the Licensee.
Service of Notices
8.5 Service of any notice on the consumer may be effected either by delivering the notice
to the consumer in person by an official of the Licensee or by dispatching the notice
by registered post or Courier post or by publication in daily newspaper commonly
Deleted: normal
57
read in the concerned locality to be kept on the record by the Licensee. In the case of
an individual consumer, service of notice to the consumer’s spouse or his
representative, and in the case of a firm, company or corporation, on the Managing
Director, Director or Principal Officer or an authorised person of such a concern,
shall be taken as sufficient service for the purposes of this code.
8.6 If a consumer refuses or avoids receiving the notice, the service may be effected by
affixing the notice at a conspicuous place on the premises of the consumer, in the
presence of two witness or by publication in daily newspaper commonly read in the
concerned locality, and in such cases an endorsement shall be made on the copy of
the notice. This affixture or publication shall be deemed as sufficient for service of
notice.
Power to Remove Difficulties
8.7 If any difficulty arises in giving effect to any of the provisions of this Code or there is
a dispute regarding interpretation of any provision, the matter may be expeditiously
referred to the Commission who shall pass necessary orders after consulting the
parties concerned, provided the Commission may refuse to entertain the reference
filed beyond 3 months delay without sufficient cause.
58
Annexure: - 3.1 (Ref. Clause 3.10)
Existing Consumer Categories
LMV-1 - Domestic Light, Fan & Power.
LMV-2 - Non-Domestic Light, Fan & Power.
LMV-3 - Public Lamps.
LMV-4 - Public Institutions.
LMV-4 (A) - Light, Fan & Power for Public Institutions
LMV-4 (B) - Light, Fan & Power for Private Institutions
LMV-5 - Small Power for Private Tube Wells/Pumping Sets for
Irrigation Purposes.
LMV-6 - Small and Medium Power.
LMV-7 - Public Water Works
LMV-8 - State Tube Wells, World Bank Tube Wells & Pumped Canals.
LMV-9 - Temporary Supply.
LMV-10 - Departmental Employees
HV-2 - Large and Heavy Power
HV-3 - Railways
Formatted
59
Annexure-4.1 (Ref. Clause 4.8)
This form is available free of cost
Application Form For Requisition Of Supply Of Energy
1. Name of the Applicant:
2. Father/Husband’s Name:
3. Occupation:
4. Address:
(a) For Communication
(b) Where Connection is Required: (Indicate land makes to identify the location)
5. Plot size______ sq.feet covered Area________ sq. feet.
6. Total Connected Load:
7. Purpose of Supply: ______________
8. Details of Processing Fee:
(a) Amount
(b) Mode_____ cheque/draft/cash
i. No Date
ii. Bank Name
(Following Information is to be Furnished by Applicants Requisiting Electric Supply more than 50 KW and for Industrial Purposes)
9. Type of unit firm (Viz: ownership :-------------------------------------- /Partnership/ Private Ltd./Public Ltd.
/Society/Govt.Deptt./Govt undertaking 10. Name of Institution developing Industrial Premises :------------------------------------ (e.g. UPSIDC/self/industries deptt. etc.) 11. Possession Letter or No. Objection Certificate :------------------------------------------ Issued by the Institution (copy enclosed.) No.--------------date----------
12. Whether supply is needed through an independent feeders :----------------------- 13. Whether the above unit ever operated at some other place or applied for connection ? (If yes, pl. furnish the following)
(a) Sanction load: :----------------------- (b) Service Connection No. :-------------- (c) Arrears of payment (in any) :----------------------- (d) Address
14. If electricity connection for the premises
60
is being requested in the past. If yes details of electricity connection.
(a) Name of unit :-------------- (a) Service connection no. :-------- (b) Arrears of payment (if any) :--------
15. Purpose or process for which Electricity load is required. :--------------------------
16. Nature of process :--------------------------
17. (a) Registration No. from Deptt. of Industries U.P. Govt. :-------------------------- (b) No objection certification from Pollution Control
Board (Copy to be enclosed.) :-------------------------- 18. Name of the Agency Financing the unit
(UPFC/PICUP/BANK/SELF/Any other) :-------------------------- 19. Proposed date of start of Production :-------------------------- 20. Is there any other industrial unit operating in the vicinity If yes, please given name and address -------------------------- 21. Pl. specify voltage ratio & capacity of the nearest Electricity sub-station and its distance from the unit :--------------------------
Enclosures :
1. Work Completion Certificate and Test Report (B & L form)
2. Documentary evidence in support of lawful occupation of the premises. If the
applicant is not the owner of the premises, indemnity bond as specified by the
Licensee shall be enclosed.
3. Factory/Industry/Premises/Eastablishment/House map, where supply is desired,
indicating tentative position of the meter box.
4. Receipt for payment, if cash/cheque/draft.
1. In case of consumers without MDI meter, the connected load can be 200% of the contracted load in the domestic category and 133 % of the contracted load in the commercial category.
2. In your own interest, please ensure permanent disconnection of your electric supply before vacating the premises
3. Electric Connection shall not be treated as a proof of ownership of the Premises
DECLARATION
I/we, ……………………………………………………., solemnly assure and undertake that
61
A. I/We hereby declare that I/we desire to have and agree with the Licensee to take a
supply of energy for the above mentioned purposes, for a period of not less than 2
years from the date of commencement of supply and to pay for the energy so supplied
and all other charges at the rates set out in the Tariff Order.
B. I/We also agree to be bound by the Licensee’s Distribution Code as approved by the
Commission including any modifications thereof and the provisions of Indian
Electricity Act, 1910 together with the Rules framed there under and Electricity
(Supply) Act, 1948 in so far as they are applicable.
C. I/We also declare that in the event of my/our failure to comply with the above
provisions, it shall be lawful for the Licensee to discontinue the supply in terms of the
aforesaid Distribution Code.
D. I/We further declare that the Licensee shall not be held responsible for any
interruption/diminution of supply for reasons beyond its control.
E. I/We understand that this declaration can be cancelled after two years by either party
giving notice as per the procedure described in this code.
F. I/We further agree that this declaration given by me/us shall be construed as an
Agreement with the Licensee to the above effect.
G. I/We declare that all details furnished in the Application Form are true to my/our
knowledge. If any information is found incorrect at a later date, then the Licensee
shall have the right to withhold/ disconnect supply, as the case may be.
H. It shall be ensured by me/us that there is no unauthorized addition/alteration to the
equipment or theft or misappropriation or by-passing of or tempering of the meter. In
other words, it shall be ensured by me/us that the energy provided to me/us by the
Licensee is utilized as per law and authorization. In case the Licensee has reasonable
basis to understand or apprehend that there is in any way whatsoever unauthorized
addition/alteration to the equipment or theft or misappropriation or diversion of the
energy or by-passing of or tampering with the meter, it shall be open to the designated
authority of the Licensee to enter upon the premises for general inspection and testing
of the equipment, meter and wiring etc.
I. I undertake to intimate the Licensee as per the procedure described in the “Electricity
Supply Code” whenever I intend to vacate the premises for which the electric
connection is being taken.
Formatted: Bullets and Numbering
62
Date: ________________ Applicant’s Signature
Place:
(To be Filled by the Licensee)
1. Date of application received:
2. Contracted Load Sanctioned:
3. Date of commencement of Supply:
4. Consumer No/connection No:
5. Meter No:
Signature of Applicant Signature of Representative of the Licensee
Acknowledgement
Application form of Sh./Smt. -----------------------, complete in all respects/has following
shortcomings, for requisition of supply is hereby received on -------------------. In this
connection, the applicant is given a reference No.---------- to be used in all future
correspondence.
Signature of Representative of the Licensee
63
Annexure 4.2(Ref. Clause 4.8)
INDEMNITY BOND
(if the intending consumer is not the owner of the premises)
To:
……………..Engineer, From…………………
………………………… ………………………….
Whereas the land/premises detailed hereunder, belongs to Sri/Smt……………and I am only
lessee/tenant/occupier of the said land/premises where I have applied for the electricity
connection the said/premises and I am not able to obtain the consent of Sri /
Smt………………….but produced the proof of occupancy, i.e. valid power of attorney/latest
rent paid receipt/registered lease deed.
Thereto I, in consideration of the grant of electricity connection to me on the conditions of supply for which I have executed the Agreement, further agree to indemnify and keep harmless the Licensee from all damages and claims whatsoever, including costs of suit, original petitions and all manner of legal or other proceedings that the Licensee may incur or likely to incur on account of any action of threat by or at the instance of the owner of the said land/premises (whether such owner be the said Sri/Smt……………or any other). I also further agree that such loss, damages and any other claim resulting out of the electricity connection being given to me without the consent of the owner of the land/premises are also recoverable from me and my properties under the provisions of the Revenue Recovery Act, in force at the time of such recovery, or by such other proceedings as the Licensee may deem fit to initiate.
I hold myself answerable to costs of such recoveries and proceedings also.
Place :
Date:
Witnessee:- Signature of lessee/tenant/occupier
1)
2)
64
Annexure-4.3 (Ref. Clause 4.8)
Format For Work Completion Certificate and Test Results
fo|qr lqj{kk funs'kky; dk;Ziwjd izek.k&i=
¼jkT; ljdkj ls vuqKfIr ¼ykblsUl½ izkIr Bsdsnkj }kjk Hkjk tk;sxk½
miHkskDrk@ Lokeh dk uke %
firk @ ifr dk uke % irk % ifjlj dh vofLFkfr %
oksYVrk vkSj iznk; dh iz.kkyh & % ¼1½ oksYVrk %
¼2½ dykvksa ¼ Qstksa½ dh la[;k % ¼3½ ,0lh0 @ Mh0 lh0 % ok;fjax dk iz;kstu& %
ok;fjax ds izdkj ¼cSVu] dUMwV bR;kfn½ % laLFkkiuk dh fof'kf"V;ka %&
220 @ 230 oksYV~l
Qst 1 Qst 2 Qst 3
400 @440 oksYV~l
mPp @vfr mPp oksYVrk laLFkkiu
la[;k dqy okV~l
la[;k dqy okV~l
la[;k dqy okV~l
la[;k dqy {kerk
la[;k dqy {kerk
I- ¼1½ cfRr;ksa ds IokbUV ¼2½ ia[kksa ds IokbaV ¼3½ Iyx IokbaV ¼4½ eksVj @tsujsVlZ ¼iw.kZ C;ksjk fn;k tk;½
&2&
65
&&&&&&&&&&&&&&&&&&&&&&&&&&&&&&&&&&&&&&&&&&&&&&&&&&&& ;ksx &&&&&&&&&&&&&&&&&&&&&&&&&&&&&&&&&&&&&&&&&&&&&&&&&&&&&&&&&&&
II& vU; miLdj ¼iwjk C;ksjk fn;k tk;½
¼1½ ¼2½
dqy la;kstu Hkkj fdyksokV esa&
vf/kdre djsaV ekax] ,fEi;j esa & ¼dqy la;ksftr Hkkj ds vk/kkj ij½
fo|qr dk fjlko ¼fo|qrjks/kh izfrjks/kh de ls de ,d esxkvkse gksxk vFkok mruk gksxk ftruk Hkkjrh; ekud laLFkku }kjk le; le; ij fofufn"V fd;k tk;½ A Vsdsnkj }kjk fo|qrjks/kh izfrjks/kh ds ijh{k.k dk ifj.kke&
Qst& 1 o vFkZ Qst&2 o vFkZ Qst&3 o vFkZ &&&&&&&&& &&&&&&&& &&&&&&&&
¼I½ Qst ,oa vFkZ ds chp &
¼II½ U;wVzy ,oa vFkZ ds chp&
¼III½ rkjksa ds e/; & fu;e &29 %&
¼I½ crk;as fd ok;fjax dk dk;Z] iz;qDr lkexzh rFkk midj.k Hkkjrh; ekud laLFkku dh O;ogkj lafgr ds vuqlkj gS A
¼II½ crk;sa fd izR;sd lfdZV vyx&vyx fLopksa }kjk fu;af=r gSa A
¼III½ crk;sa fd lelr fLop fo|qeU; ¼thoUr½ pkydksa ij yxk;s x;s gSa A
fu;e& 32 %& crk;sa fd nks rkj iz.kkyh dk vFkZok;j rFkk cgqrkj iz.kkyh ds HkwlEifdZr U;wVzy ok;j ij LFkk;h izd`fr dk lwpd yxk;k x;k gS ftlls fd ,sls pkyd dks fo|qre; ¼thoUr½ pkyd ls lqfHkUu fd;k tk lds A
&3&
66
¼lR;kiu izek.k&i=½
eS @ ge &&&&&&&&&&&&&ykblsUl izkIr fo|qr Bsdsnkj] ykblsUl la[;k &&&&&&&&&& fuEu dk lR;kiu djrs gq, /kks"k.kk djrs gSa &
¼v½ fd iwoZksDr fo|qr laLfkkiu dk;Z esjs }kjk fd;k x;k gS A
¼c½ iwoksZDr vafdr laLFkkiu dk fo|qrjks/kh dk ijh{k.k esjs @ esjs lqijokbtj }kjk fd;k x;k gS ,oa mldk ijh{k.k ifj.kke esjs@ esjs lqijokbtj }kjk vafdr fd;s x;s gS A
¼l½ laLFkkiu dk;Z Hkkjrh; fo|qr fu;e] 1956 ,oa Hkkjrh; ekud laLFkku dh O;ogkj lafgrk ds izkfo/kkuksa ds vuq:i fd;k x;k gS A ¼n½ mijksDr dk;Z esjs @ gekjs fuEukafdr LVkQ }kjk fd;k x;k gS &
ok;jeSu dk uke &&&&&&&&&&ijfeV la0 &&&&&&&&&oS/krk dh frfFk &&&&&&&& gLrk{kj
i;Zos{kd dk uke &&&&&&&&&&&&&izek.k i-= la0 &&&&&&&&& oS/krk dh frfFk &&&&&
gLrk{kj
vizafUVl dk uke ,oa gLrk{kj &&&&&&&&&&&&&&&&&&&&&&&
fnukad %&&&&&&&&&&&& fo|qr Bsdsnkj dh QqeZ dk uke ykblsal la[;k &&&&&&&&&&&&&&&
ykblsal Js.kh &&&&&&&&&&&&&&& oS/krk dk fnukad &&&&&&&&&&&&&&&
Bsdsnkj ds gLrk{kj
&4&
67
/kks"k.kk ¼ miHkksDrk }kjk dh tk;½
eS izekf.kr djrk gwa fd jkT; fo|qr ifj"kn ykblsalh }kjk fo|qr ÅtkZ ds iznk; gsrq fu/kkZfjr 'krksZ ,oa Hkkjrh; fo|qr fu;e] 1956 ds izkfo/kkuksa dk vuqikyu esjs }kjk Bhd izdkj fd;k x;k gS
A A eq[; Q~;wt dh vf/kdre {kerk &&&&&,Eih;j ls vf/kd ugha gS rFkk laLFkkiu esa fdlh izdkj dh c<kSrjh vFkok vksojyksfMax jkT; fo|qr ifj"kn ykblsalh }kjk vuqKk izkIr gksus ij gh dh tk;sxh A
fnukad &&&&&&&&&& miHkksDrk dk uke ,oa gLrk{kj
ijh{k.k fjiksVZ
¼lIyk;j ds izfrfuf/k }kjk Hkjh tk;sxh½
fo|qrjks/kh izfrjks.kh dk ifj.kke& Qst& 1 o vFkZ Qst&2 o vFkZ Qst&3 o vFkZ &&&&&&&&& &&&&&&&& &&&&&&&&
¼1½ Qst ,oa vFkZ ds chp &
Qst& 1 o 2 Qst&2 o 3 Qst&3 o 1 &&&&&&&&& &&&&&&&& &&&&&&&&
¼2½ rkj ds chp &
fo|qr laLFkkiu esa ik;h x;h dfe;ksa ¼ ;fn dksbZ gksa½ ,oa dfe;ksa dks nwj djkus gsrq d`r dk;Zokgh%& 1&
2&
&5&
68
3& 4& fnukad &&&&&&&&&&& iznk;drkZ ¼ lIyk;j½ ds fujh{k.kdrkZ
dk uke ,oa gLrk{kj inuke
fo|qr lqj{kk funs'kky; dk izek.kd
fujh{k.k dk ifj.kke fujh{k.k vf/kdkjh ds gLrk{kj vkSj ¼fooj.k layXu fd;k tk;s½ in uke fujh{k.k frfFk
69
Annexure-4. 4(Ref. Clause 4.27)
This form is available free of cost
Application Form for Requisition of Temporary Supply of Energy
1. Name of the Applicant:
2. Occupation:
3. Address of the Applicant:
4. Address where connection is required:
a. (Indicate land marks to identify the location)
5. Total Connected Load
6. Purpose of Supply: ______________
7. (a) Date from which supply is required
(b) Duration for which supply is required
8. Details of Fee
(a) Amount
(b) Mode_____ cheque/draft/cash
(i) No Date
(ii) Bank Name
DECLARATION
I/we, ……………………………………………………., solemnly assure and undertake that
a. I/We also agree to be bound by the Licensee Distribution Code as approved by the
Commission including any modifications thereof and the provisions of Indian
Electricity Act, 1910 together with the Rules framed hereunder and Electricity
(Supply) Act, 1948 in so far as they are applicable.
70
b. I/We also declare that in the event of my/our failure to comply with the relevant
provisions of the Code, it shall be lawful for the Licensee to discontinue the supply.
c. I/We further declare that the Licensee shall not be held responsible for any
interruption/diminution of supply for reasons beyond its control.
d. I/We further agree that this declaration given by me/us shall be construed as an
Agreement with the Licensee to the above effect.
e. I/We declare that all details furnished in the Requisition Form are true to my/our
knowledge. If any information is found incorrect at a later date, then the Licensee
shall have the right to withhold/ disconnect supply, as the case may be.
Date: ________________ Applicant’s Signature_____________
Place:
(To be Filled by the Licensee)
1. Date of application received:
2. Contracted Load Sanction
3. Date of commencement of Supply:
4. Reference No:
Acknowledgement
Application form of Sh./Smt. ----------------, complete in all respect, for requisition of
temporary supply is hereby received on -----------. In this connection, the applicant is given a
reference No.--------------- to be used in all future correspondence.
Signature of Representative of the Licensee
71
Annexure: - 4.5(Ref. Clause 4.35)
Procedure for Determination of Connected Load
1. Bulb/Fan - Actual rating or 60 Watt each, if it is not possible to read
the rating on the bulb/fan.
2. Tube Light - Actual rating or 40 Watt each
3. Light Plug - 60 Watt upto three plugs and extra 60 Watts for every
three plugs or less.
5. Television
(a) Colour
(b) Black & White
-
-
100 Watt
60 Watt
6. Power Plug - 500 Watt up to three plugs and extra 500 Watts for every
three plugs or less.
7. Fridge - 250 Watt
8. Dessert Cooler - 250 Watt
9. Geyser - 1500 Watt
10. Air-Conditioner 1/1.5
Ton
- 1500 Watt/2200 Watt
11. Water lifting pump - 180 Watt or 360 Watt (According to Pump) or according
to the equipment’s original rating (Name plate &
Specification).
Note:
1) If any equipment is connected with plug point equipment’s load or plug
point rating whichever is maximum shall be taken. In such case, load of
plug point shall not be counted separately.
2) For commercial light & fan consumer load of every bulb shall be taken
as100 Watt.
3) The load for Arc/induction furnace shall be worked out on the basis of
600 KVA per ton of the capacity of the furnace.
4) The higher rating of only one equipment shall be considered if both
Geyser and Air-conditioner (without heater) are installed
Formatted: Bullets and Numbering
Deleted: 85
72
Annexure – 4.6(Ref. Clause 4.42)
Format for Disconnection: Date: To The Executive Engineer ( EDD ) -------------------- -------------------- A connection, No. -------------------- for contracted load of ----------- kW/HP exists in the name of ------------------------ at ---------------------------------------------------------------------------------------------------------------------------------------------- ( address ). It is requested that the above connection may please be disconnected, and the relevant agreement with the Corporation be terminated forthwith. Following documents are enclosed herewith:
1. Copy of last bill. 2. Copy of payment reeipt of last bill.
Thanking you, ( Signatures ) Name, Address, Phone number of consumer ________________________________________________________________
ACKNOWLEDGEMENT
Application of Sh./Smt/M/s ---------------------- is, complete in all respects/has following shortcomings, for disconnection/termination of contract has been received in this office on ---------------- (date). In this connection, the applicant is given a reference number -------------------- to be used in all future correspondence.
( Signatures and seal of the rep. of the Licensee )
Formatted: Bullets and Numbering
73
Annexure 4.7(Ref. Clause 4.44) Format for intimation to consumer after termination of agreement
Office
Address
No.__________ Date
_________________(Name of Consumer) _________________(Address) _________________ _________________
This is to inform you that an agreement dated _____________________ against connection No __________ between yourself and _________(Name of Licensee) regarding supply of ________ KW/MW (Please indicate contracted load) in the ________________ consumer category has been terminated w.e.f____________________on account of: _______________________________________________
________________________________________________________________________________________________________________________________________________ Your supply has been disconnected permanently.
After final adjustment of all charges and energy bills an amount of: 1. Rs.____________ is payable to you for which a checque No.________________
is enclosed. 2. Rs.____________ is due from you. You are requested to pay the amount within a
week of receipt of this letter, failing which, action as prescribed under the law shall be initiated for recovery of the amount.
There is nothing outstanding against you towards this connection. This may be treated as no dues from ________________ (Name of Licensee) in respect of above referred agreement/connection.
Thanking you, Yours faithfully,
Name, Signature & Designation of the representative of the Licensee
74
Annexure 4.8(Ref. Clause 4.66.2)
Format for intimation to consumer after temporary disconnection of supply
Office Address
No.__________ Date:
_________________(Name of Consumer) _________________(Address) _________________ _________________ Reference
Connection No.____________________ Consumer Category_________________ Contracted Load ___________________
This is to inform you that your supply has been temporarily disconnected with effect from
___________________due to following reasons:
________________________________________________________________________ ________________________________________________________________________________________________________________________________________________ You are requested to remove the cause of disconnection and intimate
this office at the earliest. You are also requested to pay sum of Rs.______ towards
disconnection, re-connection charges and-------------(Pl. mention if any other dues is to be
deposited. Pl. also give break up of the total sum) If cause of disconnection is not removed to
the satisfaction of this office and above amount is not paid, within 45 days of this notice
(_______________ date) your supply shall be disconnected permanently without any further
notice.
Thanking you, Yours faithfully,
Name, Signature & Designation of the representative of the Licensee
75
Annexure – 4.9(Ref. Clause 4.71.1) Application Form for Enhancement/Reduction of Contract Demand
(Name of Licensee)
Application No. : Date:
consumer No. :
Name of consumer :
In view of revision of load requirement due to ---------------------------------------I / We
hereby request for enhancement/ reduction of our Contract Demand as detailed below as per
provisions of the Distribution Code.
1. Address at which enhancement/reduction of load/:
Desired Max. Demand
2. Existing Proposed
i) Connected Load KW/MW KW/MW
ii) Max. Demand KW/MW KW/MW
iii) Details of load added/ disconnected from supply
(Please attach list of equipments category-wise)
(a) Lighting
(b) Motive Power
(c) Agricultural
(d) Other (please specify)
Enclosures:
1) A work completion certificate & test report from licensed electrical contractor from
____________________________________ (name of licensed electrical contractor).
2) A copy of last paid energy bill.
3) The recorded meter readings for past three billing periods.
4) Approval letter from Electrical Inspector in view of change in H.T installation is
enclosed. (Applicable for HT consumers only).
5) No objection certificates from competent authorities as applicable.
Place: Signature of the Applicant
* Strike out which is not applicable.
Deleted:
Deleted: is desired
76
Annexure 4.10(Ref. Clause 4.72.1)
Format for transfer of connection/mutation of name To,
The Executive Engineer
___________________ ___________________
A connection No.____________________ for contracted load of
____________ exists in name of ______________________ at
______________________________________________________________ (address).
It is requested that above referred connection may please be transferred in name of ___________________________ at same address due to following reasons: ________________________________________________________________________________________________________________________________________________ Following documents for transfer of above connection is enclosed herewith.
1. Receipt of deposition of processing fee. 2. Registered deed/succession certificate/______________ . 3. Fresh application form duly filled in 4. No objection from the existing consumer if available/possible. 5.
Thanking you.
Name, Signature, Address, Phone No of the Applicant
Acknowledgement
Application of Sh./Smt. ----------------------- is, complete in all respect/has following
shortcomings, for transfer of connection/mutation of name against connection
No.____________________ in name of ___________________ is hereby received on --------
-----------. In this connection, the applicant is given a reference No.---------- to be used in all
future correspondence.
Signature of Representative of the Licensee
77
Annex 5.1 (Ref. Clause 5.19)
Meter Related Complaints or Testing of Meter
Complaint Ref. No.:
(To be given by Licensee)
1. Name, address and telephone No., if any of the complaint.
2. Book Number/Service Connection Number
3. Brief description of the complaint-Burnt out/completely stopped/Fast/Seal
broken/Testing of Meter
4. Initial cost of meter was borne by consumer/Licensee
5. Complainant desires to provide/has provided a new meter for replacement
(Yes/No)
6. Any other information
Date: (Signature of Applicant)
----------------------------------Cut From Here--------------------------------
(For Office Use)
1. Site verification report
Signature
(JMT/SMT)
2. Comments of AE (Meter)
Signature
E (Meter)
3. Reference of informing the consumer within seven days
----------------------------------Cut From Here--------------------------------
ACKNOWLEDGEMENT TO BE HANDED OVER TO THE CONSUMER
1. Complaint reference No.
(To be given by Licensee)
2. Complaint received by
(Name & Designation)
3. Complaint receiving date
4. Target time to resolve
Signature of Licensees
78
Annexure 6.1(Ref. Clause 6.5)
Minimum details to be indicated on electricity bill A. The Licensee at least must provide following information in the bill
Name of the Consumer Address of the Consumer Connection No Consumer Category Contracted Load Voltage of supply Meter No. Book No/Ledger No. Period/month of the Bill Address of bill issuing office Date Reading Previous reading (Multiplying factor, if any) Present reading Maximum demand Probable Next date for reading Last date for payment Date of disconnection, if payment is not made Rate Amount Fixed charges Energy charges Restricted hours penalty, if any Maximum demand charge, if any Meter rent, if any Load factor Higher consumption Electricity duty Arrears, if any Surcharge on arrears, if any Total amount payable within the due date Total amount payable after the due date B. Following information at least must be provided on the back of the bill
Appropriation of charges (As per clause 6.29) Address and working hours of Collection Centres
Address and location of drop Boxes
In Case of Cheque/Draft, payment may be drawn in favour of_________Payable (Place)___
In Case of wrong billing or any other difficulty, please contact
-Designation of the Authority, Address, Telephone No
Complaints regarding supply can be lodged
-Designation of the authority, address, telephone no.
79
Annexure 6.2(Ref. Clause 6.4)
Format for application of advance payment
To, The Executive Engineer
___________________ ___________________
Reference
Name of Consumer:___________________________________ Address of the Connection ______________________________
______________________________ ______________________________
Connection No _______________________________________ Consumer Category ___________________________________ Contracted Load ______________________________________
Dear Sir,
I wish to make advance payment for the period from _______________ to
__________________ against above referred connection. You are requested to kindly send me provisional advance bill for my
electricity consumption of above period, so that I can make payment. Thanking you.
Name, Signature, Address, Phone No of the Applicant
80
Annexure –7.1(Ref. Clause 7.12)
Complaint to The Executive Engineer
Complaint Ref. No.:
(To be given by Licensee)
1. Name
2. Address and telephone No. if any of the complaint.
3. Book Number/Service Connection Number
4. Consumer’s original Complaint Number & Date
5. Brief description of the present complaint Copies of the previous complaints filed
with sub station/AE(R)/AE (Meter) with copies of the reply received, if any
Date : (Signature of Applicant)
-------------------------------------Cut From Here-----------------------------
ACKNOWLEDGEMENT TO BE HANDED OVER TO THE CONSUMER
1. Complaint reference No
(To be given by Licensee)
2. Complaint received by
(Name & Designation)
3. Complaint receiving date
4. Target time to resolve
Signature
81
Annexure-7.2(Ref. Clause 7.20)
Procedure for Complaints To Appellate Committee
(Pertaining To Energy Bill)
(i) The memorandum of appeal shall be in legible writing, on fullscape paper in triplicate
duly signed by the consumer. All material on which the applicant (consumer) seeks to
rely for the purpose of his appeal shall be sent along with the memorandum of appeal.
(ii) The appellate Committee shall dispose off the appeal within a month after
considering the submission of the appellant in the memorandum of appeal; the
material placed before the Committee by the appellant and the enquiry records. It
shall not be obligatory for the appellate Committee to give a personal hearing, but if a
request is made in that behalf, it may grant such hearing to the appellant. The
appellant may be represented at such hearings by a legal practitioner or any person
duly authorised in that behalf.
(iii) The appellant committee may: -
(a) Confirm, reduce, enhance or annul the assessment or
(b) Set aside the assessment and order fresh disposal of the case with or without
further enquiry or
(c) Conduct a further enquiry itself or call for a report from the lower authority
and dispose off the appeal in the light of such further enquiry or report or
(d) Pass such other orders as it deems fit:
Provided that no order adverse to the consumer shall be passed with-out giving notice
and opportunity for a written representation to the consumer:
Provided further that if the consumer fails to turn up in spite of giving reasonable
opportunity of being heard, the appellate Committee may proceed ex-party and decide
the case on merits.
(iii) The appellate committee shall give reasons for their conclusions.
82
1. Committee at Circle level :/DGM
(a) Superintending Engineer/DGM
(b) Deputy Chief Accounts Officer or
Accounts Officer nominated by him.
(c) Executive Engineer (Test)
Chairman
Member
Member
Up to lacs Rs. 2.00 ,
2. Committee at Zone level/GM
(a) Chief Engineer (Zone)/GM
(b) Deputy Chief Accounts Officer or
where no Dy. C.A.O. is posted,
senior most Accounts Officer
(c) Senior most Superintending Engineer
Chairman
Member
Member
Above Rs.2.00 lacs and up
to 10.00 lacs.
3. Committee at Area level/CGM
(a) Chief Engineer (Distribution)
(b) Chief Accounts Officer & Financial
Advisor or Deputy Chief Accounts
Officer
(c) Senior most Chief Engineer (zone)
Chairman
Member
Member
All matters above Rs 10.00
lacs.