Sydney Metro Train Facility (SMTF) SSI-5931 Operational ...
-
Upload
khangminh22 -
Category
Documents
-
view
1 -
download
0
Transcript of Sydney Metro Train Facility (SMTF) SSI-5931 Operational ...
Acoustics
Vibration
Structural Dynamics
Sydney Melbourne Brisbane Kuwait
Renzo Tonin & Associates (NSW) Pty Ltd ABN 29 117 462 861
Level 1/418A Elizabeth St SURRY HILLS NSW 2010 | PO Box 877 STRAWBERRY HILLS NSW 2012
P (02) 8218 0500 F (02) 8218 0501 [email protected] www.renzotonin.com.au
SYDNEY METRO TRAIN FACILITY (SMTF)
SSI-5931 OPERATIONAL NOISE AND
VIBRATION REVIEW (ONVR)
REF: NWRLOTS-NRT-RTF-AV-RPT-105005-E
July 2016
Northwest Rapid Transit
RENZO TONIN & ASSOCIATES 18 JULY 2016
NORTHWEST RAPID TRANSIT
TG264-05 8F01 (R7) SSI 5931 ONVR [NWRLOTS-NRT-RTF-AV-RPT-
105005-E] iii
SYDNEY METRO TRAIN FACILITY (SMTF) - SSI 5931 ONVR
NWRLOTS-NRT-RTF-AV-RPT-105005-E
Executive Summary
Renzo Tonin & Associates (NSW) Pty Ltd, on behalf of Northwest Rapid Transit (NRT) has prepared this
Operational Noise and Vibration Review (ONVR) for the final design stage of the Sydney Metro
Northwest project (the 'Project'). This report addresses noise and vibration for the Sydney Metro Train
Facility (SMTF, formerly Rapid Transit Rail Facility - RTRF) as approved under State Significant
Infrastructure (SSI) 5931 [1]. The ONVR is a requirement of SSI 5931 Condition F4, and forms a key
element of the operational management documents for the Project.
Separate ONVR's will be prepared for train operations between Epping Station and Cudgegong Road
Station and other fixed facilities (in accordance with Project Approval SSI 5414 [2]) at a later date.
The Project Environmental Assessment [3], associated Submissions Report and Preferred Project Report
[4] included detailed operational noise and vibration assessments which were reviewed by the NSW
Department of Planning and Infrastructure (now NSW Department of Planning and Environment -
DP&E) prior to the Minister for Planning and Infrastructure granting the Project Approval [1]. This ONVR
builds on these previous environmental assessments of noise (air and ground-borne) and vibration
including:
Confirming the operational noise (air and ground-borne) and vibration objectives to manage
noise and vibration impacts on adjoining development and other noise-sensitive receivers,
Predicting the operational noise and vibration impacts at adjoining development based on
the final design of the project,
Identifying mitigation measures for controlling operational noise and vibration at source and
at nearby sensitive receivers,
Describing the procedures for operational noise and vibration complaints management once
the Project is operational.
SMTF overview
The SMTF is located at the western most end of the Project, west of Tallawong Road and north of
Schofields Road, Schofields.
The SMTF provides for the stabling, cleaning and maintenance of trains that will operate on the Sydney
Metro Northwest including the operations control centre (OCC) and administration facilities. Bulk
electrical supply equipment and substations are also located within the SMTF site.
Noise and vibration objectives
All operations and equipment associated with the SMTF are categorised as fixed facilities and in
accordance with Condition F2 of SSI 5931, noise emissions are required to be assessed against the NSW
Industrial Noise Policy (INP) [5].
RENZO TONIN & ASSOCIATES 18 JULY 2016
NORTHWEST RAPID TRANSIT
TG264-05 8F01 (R7) SSI 5931 ONVR [NWRLOTS-NRT-RTF-AV-RPT-
105005-E] iv
SYDNEY METRO TRAIN FACILITY (SMTF) - SSI 5931 ONVR
NWRLOTS-NRT-RTF-AV-RPT-105005-E
Condition F3 of SSI 5931 requires vibration objectives for human exposure to be set in accordance with
Department of Environment and Climate Changes (DECC) ‘Assessing Vibration – A technical guideline’
[6].
While Condition F1 of SSI 5931 requires assessment of rail line components against the RING [7], in
accordance with the RING, maintenance facilities and stabling yards are excluded and are to be assessed
against the NSW Industrial Noise Policy (INP) [5] as per Condition C5 of SSI 5931.
There are no rail line components as part of the SMTF that are assessable against the Rail Infrastructure
Noise Guideline (RING) [7] in accordance with Condition F1 of SSI 5931.
With regard to ground-borne noise, the SMTF does not include underground or in-tunnel rail
infrastructure and subsequently ground-borne (internal) noise is not assessed within this ONVR.
Operational noise and vibration impact predictions
Noise and vibration impact predictions have been carried out for each facility and activity in accordance
with the requirements of the applicable noise and vibration criteria.
Noise from the SMTF was carried out using 3D noise prediction software, incorporating all relevant
design aspects, such as buildings, surrounding land topography, noise source locations and
characteristics, operational procedures, and location of sensitive receiver locations etc. The noise model
was used to establish where noise mitigation was required for the Project, and evaluate the
effectiveness of noise mitigation measures.
Mitigation measures
Noise and vibration mitigation measures have been implemented into the design of SMTF with its
associated buildings. In accordance with the relevant criteria, all feasible and reasonable measures have
been implemented at source, or within the rail corridor so as to satisfy the noise and vibration
objectives. Such mitigation measures include noise barriers around plant and equipment, low noise
plant and equipment selection, acoustic attenuators, siting and positioning of noise sources away from
sensitive receivers, and building envelope design considerations. In some cases, residual noise
exceedances have required the consideration of at-property noise mitigation treatment of existing
receiver properties and for future noise sensitive development surrounding the SMTF to incorporate
noise mitigation measures. The specific at-property noise mitigation treatments will require consultation
with the relevant property owners, and may include local barrier fences, provision of mechanical
ventilation to allow windows/doors to remain closed and/or upgrade of some windows/doors.
The process of determining the feasible and reasonable noise mitigation treatment options is set out in
this ONVR, along with the details of the final noise mitigation design for the Project.
RENZO TONIN & ASSOCIATES 18 JULY 2016
NORTHWEST RAPID TRANSIT
TG264-05 8F01 (R7) SSI 5931 ONVR [NWRLOTS-NRT-RTF-AV-RPT-
105005-E] v
SYDNEY METRO TRAIN FACILITY (SMTF) - SSI 5931 ONVR
NWRLOTS-NRT-RTF-AV-RPT-105005-E
Consultation and Independent verification
This ONVR is to be reviewed by relevant Government agencies and independently verified, as required
by the conditions of approval set out in SSI-5931.
Next steps
Once the ONVR has been independently verified and submitted to DP&E, NRT will commence one-on-
one consultation with property owners of existing dwellings that may be eligible for at-property noise
mitigation treatments. Subject to a detailed property inspection, one or more of the following options
will be offered based on the noise reduction required for individual properties:
Property boundary fencing or other external screen walls, and/or
Fresh air ventilation systems that allow existing windows and doors to be kept shut, sealing
wall vents and upgrading window and door seals, and/or
Upgraded windows and glazing, and solid core doors, on the exposed facade/s of masonry
structures.
Further consultation between NRT, DP&E and TfNSW is also expected to be required to determine the
expected noise exposure at any future development sites surrounding the SMTF, in order to permit
others to assess and design for noise exposure upon the future uses.
RENZO TONIN & ASSOCIATES 18 JULY 2016
NORTHWEST RAPID TRANSIT
TG264-05 8F01 (R7) SSI 5931 ONVR [NWRLOTS-NRT-RTF-AV-RPT-
105005-E] vi
SYDNEY METRO TRAIN FACILITY (SMTF) - SSI 5931 ONVR
NWRLOTS-NRT-RTF-AV-RPT-105005-E
Contents
Executive Summary iii
SMTF overview iii
Noise and vibration objectives iii
Operational noise and vibration impact predictions iv
Mitigation measures iv
Consultation and Independent verification v
Next steps v
1 Operational noise and vibration overview 1
1.1 Introduction 1
1.2 Project overview 2
1.3 Purpose 3
1.4 Operational noise and vibration assessment process 6
1.5 Consultation and review 8
1.6 Operational noise and vibration aspects of the SMTF 9
1.6.1 Fixed facilities 9
1.6.2 Railway operations 9
1.7 Terminology 9
1.7.1 Noise and vibration terminology 9
1.7.2 Track chainage and directions 9
1.7.3 Types of noise and vibration 10
1.8 Structure of this report 10
2 Land use survey surrounding SMTF 11
2.1 Overview 11
2.2 Receiver ID nomenclature and methodology 11
2.3 Land uses 13
2.3.1 Existing development 13
2.3.2 Future development 13
2.3.3 Noise Catchment Areas (NCAs) 13
2.4 Baseline noise monitoring 14
2.4.1 Measurement locations 14
2.4.2 Measured noise levels 15
3 Noise and vibration criteria 17
3.1 NSW Industrial Noise Policy (INP) 17
3.1.1 Intrusive noise criteria 18
3.1.2 Amenity noise criteria 18
3.1.3 Sleep disturbance 19
RENZO TONIN & ASSOCIATES 18 JULY 2016
NORTHWEST RAPID TRANSIT
TG264-05 8F01 (R7) SSI 5931 ONVR [NWRLOTS-NRT-RTF-AV-RPT-
105005-E] vii
SYDNEY METRO TRAIN FACILITY (SMTF) - SSI 5931 ONVR
NWRLOTS-NRT-RTF-AV-RPT-105005-E
3.1.4 Established noise goals 20
3.1.5 SMTF Emergency equipment 21
3.2 Assessing Vibration: a Technical Guideline 22
3.3 Rail infrastructure noise guideline (RING) 23
4 Noise assessment inputs and procedures 24
4.1 Overview 24
4.2 Design year 24
4.3 SMTF Operations 25
4.3.1 Stabling yard 25
4.3.2 Rolling stock 26
4.3.3 Rail track 27
4.3.4 Maintenance building 27
4.3.5 Administration building 28
4.3.6 Car park 29
4.3.7 Train Wash Plant 29
4.3.8 Under Floor Wheel Lathe 30
4.3.9 Infrastructure Workshop and Rail Store 30
4.3.10 Distribution and Traction building 30
4.3.11 Bulk Supply building 30
4.3.12 Fire pump room 31
4.4 Noise modelling 31
4.4.1 Environmental noise predictions 31
4.4.2 Noise generation within buildings 31
4.4.3 Meteorological conditions 31
4.4.4 Temperature profiles 32
5 Acoustic design outcomes 35
5.1 Summary of predicted noise levels 35
5.2 Feasible and reasonable design measures 35
5.3 At-property treatment 38
5.4 Future development surrounding the SMTF 40
6 Consultation with affected property owners 42
7 Operational noise monitoring program 44
7.1 Monitoring of noise emissions from the SMTF 44
7.2 Operational noise complaint response procedures 44
8 Independent verification of noise and vibration study 46
9 Conclusion 47
References 48
APPENDIX A Glossary of terminology 51
RENZO TONIN & ASSOCIATES 18 JULY 2016
NORTHWEST RAPID TRANSIT
TG264-05 8F01 (R7) SSI 5931 ONVR [NWRLOTS-NRT-RTF-AV-RPT-
105005-E] viii
SYDNEY METRO TRAIN FACILITY (SMTF) - SSI 5931 ONVR
NWRLOTS-NRT-RTF-AV-RPT-105005-E
APPENDIX B Land use survey and receiver locations 53
APPENDIX C Long-term noise monitoring methodology 61
C.1 Noise monitoring equipment 61
C.2 Meteorology during monitoring 61
C.3 Noise vs time graphs 61
APPENDIX D Noise logger graphs 62
APPENDIX E SMTF noise and vibration design measures 63
APPENDIX F Predicted noise levels from SMTF operations 64
APPENDIX G Independent verifier statement 65
List of tables
Table 1-1: ONVR conditional requirements 4
Table 2-1: SMTF Noise Catchment Areas (NCAs) 14
Table 2-2: Baseline noise monitoring locations 15
Table 2-3: Long-term noise monitoring results, dB(A) 16
Table 3-1: INP Amenity Criteria - Recommended LAeq Noise Levels from Industrial Noise Sources [NSW INP
Table 2.1] 18
Table 3-2: SMTF operational noise targets, dB(A) 21
Table 3-3: Preferred / maximum weighted RMS values for continuous vibration acceleration (m/s2) 1-80Hz 22
Table 4-1: SMTF Employment type mode share and parking provision estimates 29
Table 4-2: Detailed morning temperature profile information 32
Table 4-3: Temperature profile information 34
Table 5-1: Summary of noise mitigation options for SMTF 36
Table 5-2: At-property noise mitigation options 39
Table 5-3: Properties considered for at-property noise mitigation treatment 40
Table B-9-1: Land use survey summary 59
List of figures
Figure 1-1: Sydney Metro Northwest project overview 2
Figure 1-2: SMTF ONVR project boundary 3
Figure 1-3: SMTF noise and vibration management process 7
Figure 1-4: Noise and vibration assessment and design review process 8
Figure B.1: Rapid Transit Rail Facility & NCA Locations 54
Figure B.2: Riverstone East Draft Indicative Layout Plan [9] 55
Figure B.3: Alex Avenue Indicative Layout Plan [10] 56
Figure B.4: Riverstone Precinct Indicative Layout Plan [11] 57
Figure B.5: Area 20 Precinct Indicative Layout Plan [21] 58
RENZO TONIN & ASSOCIATES 18 JULY 2016
NORTHWEST RAPID TRANSIT
TG264-05 8F01 (R7) SSI 5931 ONVR [NWRLOTS-NRT-RTF-AV-RPT-
105005-E] 1
SYDNEY METRO TRAIN FACILITY (SMTF) - SSI 5931 ONVR
NWRLOTS-NRT-RTF-AV-RPT-105005-E
1 Operational noise and vibration overview
This Section of the ONVR provides an overview of this document and its purpose, the consultation process
undertaken during the design process and lists the different environmental noise and vibration aspects
associated with the Project.
1.1 Introduction
Renzo Tonin & Associates (NSW) Pty Ltd, on behalf of Northwest Rapid Transit (NRT) has prepared this
Operational Noise and Vibration Review (ONVR) for the final design stage of the Sydney Metro
Northwest ('Project'). This ONVR addressees SSI-5931, relating to the Sydney Metro Train Facility (SMTF,
formerly the Rapid Transit Rail Facility - RTRF). This report forms a key element of the operational
management documents for the Project.
Separate ONVR's will be prepared for train operations between Epping Station and Cudgegong Road
Station and other fixed facilities at a later date.
The Project, which has been the subject of three State Significant Infrastructure (SSI) approvals, will
deliver a new rapid transit high frequency single deck train system between the existing Chatswood
Station and new Cudgegong Road Station. The Project as a whole includes eight new stations, a four
kilometre elevated ‘Skytrain’ (viaduct) between Rouse Hill and Bella Vista, approximately 15.5 kilometres
of tunnels from Bella Vista to Epping and conversion of the existing Epping to Chatswood Rail Link
(ECRL). The SSI application for Stage 1 (SSI-5100) related to major civil construction works (EIS1) and
was approved on 25 September 2012. The Stage 2 SSI application (SSI-5414) related to the new stations,
rail infrastructure and systems works (EIS2) and was approved on 8 May 2013. The Stage 3 SSI
Application (SSI-5931), for which this ONVR relates, applied to the Sydney Metro Train Facility (EIS3) and
was approved on 15 January 2014.
The Project Environmental Assessments [8], associated Submissions Reports and Preferred Project
Reports [4] included detailed operational noise and vibration assessments which were reviewed by the
Department of Planning and Infrastructure (now Department of Planning & Environment - DP&E) prior
to the Minister for Planning and Infrastructure granting the Project Approval. This ONVR builds on these
previous environmental assessments and seeks to confirm the noise and vibration control measures that
would be implemented for the Project in accordance with the requirements of the Minister for
Planning’s Conditions of Approval [1].
This ONVR outlines the operational noise and vibration objectives and project specific criteria, noise-
modelling results, discussion of feasible and reasonable noise and vibration mitigation measures; and
the location, type and timing of noise mitigation measures. In addition, the ONVR outlines the
consultation strategy for seeking feedback from directly affected property owners and the procedures
for operational noise and vibration complaints management following the completion and opening of
the Project.
RENZO TONIN & ASSOCIATES 18 JULY 2016
NORTHWEST RAPID TRANSIT
TG264-05 8F01 (R7) SSI 5931 ONVR [NWRLOTS-NRT-RTF-AV-RPT-
105005-E] 3
SYDNEY METRO TRAIN FACILITY (SMTF) - SSI 5931 ONVR
NWRLOTS-NRT-RTF-AV-RPT-105005-E
Figure 1-2: SMTF ONVR project boundary
1.3 Purpose
Broadly, the purpose of the ONVR is to:
identify the operational noise (air and ground-borne) and vibration objectives to manage
noise and vibration impacts on adjoining development and other noise-sensitive receivers,
predict the operational noise and vibration impacts at adjoining development based on the
final design of the project,
identify mitigation measures for controlling operational noise and vibration at source and at
nearby sensitive receivers,
outline the consultation strategy that will be adopted for directly affected property owners,
and
describe the procedures for operational noise and vibration complaints management once
the Project is operational.
More specifically, the ONVR has been prepared in accordance with the requirements of the SSI-5931
Approval. Additional requirements for the ONVR were also stipulated in Appendix 44 of the Project's
Scope and Performance Requirements (SPR). The following table outlines the relevant requirements and
identifies where in the ONVR they have been addressed.
RENZO TONIN & ASSOCIATES 18 JULY 2016
NORTHWEST RAPID TRANSIT
TG264-05 8F01 (R7) SSI 5931 ONVR [NWRLOTS-NRT-RTF-AV-RPT-
105005-E] 9
SYDNEY METRO TRAIN FACILITY (SMTF) - SSI 5931 ONVR
NWRLOTS-NRT-RTF-AV-RPT-105005-E
1.6 Operational noise and vibration aspects of the SMTF
1.6.1 Fixed facilities
The noise generating equipment and operations associated with the SMTF are categorised as fixed
facilities, and in accordance with Condition F2 of SSI 5931, noise emission are required to be assessed
against the NSW Industrial Noise Policy (INP) [5]. The SMTF includes:
Maintenance operations,
Stabling roads and associated train movements within the SMTF,
train wash,
wheel lathe,
administration building mechanical equipment
car park,
bulk supply substation and traction substation.
1.6.2 Railway operations
In accordance with Condition F1 of SSI 5931, the rail line components are to be designed and operated
with the objective of not exceeding the airborne and ground-borne noise trigger levels at existing
development. Condition C5 of SSI 5931 however defines the SMTF as a fixed facility and therefore
requires assessment against the NSW Industrial Noise Policy (INP) [5] only, and not the RING [7]. A
separate ONVR will be prepared at a later date which will assess rail operations in accordance with SSI-
5414.
1.7 Terminology
1.7.1 Noise and vibration terminology
A Glossary of the acoustic terminology used within this report is presented within APPENDIX A.
1.7.2 Track chainage and directions
Consistent with normal rail terminology, track chainages for the main alignment are referenced to 0 km
at Central Station. Down and Up directions refer to trains travelling away from and towards Central
Station, respectively. For the Sydney Metro Northwest the Down and Up sides of the corridor are the
left-hand and right-hand sides, respectively, when facing towards the SMTF from Cudgegong Road
Station.
The track chainages are illustrated on the Location Maps in APPENDIX B.
RENZO TONIN & ASSOCIATES 18 JULY 2016
NORTHWEST RAPID TRANSIT
TG264-05 8F01 (R7) SSI 5931 ONVR [NWRLOTS-NRT-RTF-AV-RPT-
105005-E] 10
SYDNEY METRO TRAIN FACILITY (SMTF) - SSI 5931 ONVR
NWRLOTS-NRT-RTF-AV-RPT-105005-E
1.7.3 Types of noise and vibration
The most common form of noise experienced by people is termed ‘airborne noise’, indicating that it
propagates between the source and receiver primarily through the air. This is the primary form of noise
that occurs adjacent to surface railway tracks, roads and construction sites.
Ground-borne noise is the term used to describe the process where vibrational energy from the railway
propagates through the ground, which transfers into the building walls and floors and re-radiates as
noise which can be heard by occupants. Ground-borne noise has the potential to be evident where
railway tracks are underground or in deep cuttings, where the air-borne noise path is not present or
negligible.
In some cases, ground-borne vibration from a railway line can be felt by building occupants. Without
appropriate controls, the vibration may also induce secondary effects such as the rattling of crockery
and other loose fittings and furnishings, but is rarely of sufficient magnitude to cause direct damage to
buildings.
1.8 Structure of this report
This report is structured as follows:
Section 2 provides an overview of sensitive receivers including residences and other land
uses considered in this noise and vibration study.
Section 3 presents the Project specific criteria relevant to the surrounding sensitive receivers.
The SMTF design and operational inputs relevant to the noise and vibration assessment are
outlined in Section 4.
The results of noise modelling and assessment of reasonable and feasible mitigation
measures in outlined in Section 5.
Consultation with property owners being considered for at-property treatments is detailed in
Section 6.
The operational noise monitoring program is set out in Section 7.
The independent verification process is outlined in Section 8.
RENZO TONIN & ASSOCIATES 18 JULY 2016
NORTHWEST RAPID TRANSIT
TG264-05 8F01 (R7) SSI 5931 ONVR [NWRLOTS-NRT-RTF-AV-RPT-
105005-E] 11
SYDNEY METRO TRAIN FACILITY (SMTF) - SSI 5931 ONVR
NWRLOTS-NRT-RTF-AV-RPT-105005-E
2 Land use survey surrounding SMTF
2.1 Overview
A land use survey has been undertaken to confirm the location of sensitive receivers that are potentially
impacted by noise and vibration from the Project.
In accordance with SPR Appendix 44 Clause 3.2 a. i), and as relevant to the SMTF, the following
information has been established:
A detailed land use survey carried out to identify potentially critical areas that are sensitive to
operational noise (air and ground-borne) and vibration impacts, having regard to the type of
land use.
The land use report identifies the land use category and the associated operational noise and
vibration criteria at all sensitive receivers potentially impacted by the Project.
All receivers located within 200 m of the stationary facility are to be tabulated.
The tabulation must include a unique identification nomenclature for each receiver, with its
planned distance to the nearest track (or stationary facility), receiver type and applicable
criteria.
2.2 Receiver ID nomenclature and methodology
Receivers were identified via a range of methods described below:
Rail Alignment – The three-dimensional rail alignment of each track was provided by the NRT
project team. Each track was converted into 5 m segments with the relevant track chainage
assigned as a unique identifier for the start of each segment.
A Cadastral Boundary layer, identifying the property boundaries of all parcels of land within
the project area was provided by NRT.
The most recent Aerial Photography from NearMap and/or Google Earth was utilised to
locate buildings on each parcel of land. For the airborne noise modelling, the aerial imagery
was utilised to digitise the buildings and locate them within the three-dimensional GIS
database and noise modelling software. These resources were utilised to determine the
number of floor levels for each building and the approximate building heights.
Additional land use information was sourced from the EIS, discussions with local Councils,
site visits from members of the project team and other information available in the public
domain.
The following nomenclature has been adopted for receivers located within the database.
RENZO TONIN & ASSOCIATES 18 JULY 2016
NORTHWEST RAPID TRANSIT
TG264-05 8F01 (R7) SSI 5931 ONVR [NWRLOTS-NRT-RTF-AV-RPT-
105005-E] 12
SYDNEY METRO TRAIN FACILITY (SMTF) - SSI 5931 ONVR
NWRLOTS-NRT-RTF-AV-RPT-105005-E
Example Receiver ID: 25010-121U-OFF
where
25010 represents the location of the centre of the building (track chainage), based on the
down track
121 represents the distance from the centre of the building to the nearest track centreline
(in metres)
U represents the direction of the nearest track (U for Up track and D for Down track)
OFF represents the land use category (see below for receiver types)
The above nomenclature has been undertaken to generate a unique Receiver ID for each sensitive
building, based on the coordinates of the geometric centre of the building. The following land use
categories (receiver types) have been identified within the Project area:
CHC - Child Care
CIN - Cinema
HOS - Hospital
IND - Industrial
OFF - Office (Commercial)
PoW - Place of Worship
RES - Residential
RET - Retail
SCH - School
Maps showing the various receivers and future land uses surrounding the SMTF are presented in
APPENDIX B. An extract of the database identifying the sensitive receivers applicable to the current
assessment are also provided in APPENDIX B. The table provides a summary of the following
information:
The table provides a summary of the following information:
Building ID
Address / Lot Plan
Land Use (Receiver Type)
Nearest track and distance
Noise and/or vibration assessment criteria
The predicted noise and/or vibration levels are presented in Appendix F.
RENZO TONIN & ASSOCIATES 18 JULY 2016
NORTHWEST RAPID TRANSIT
TG264-05 8F01 (R7) SSI 5931 ONVR [NWRLOTS-NRT-RTF-AV-RPT-
105005-E] 13
SYDNEY METRO TRAIN FACILITY (SMTF) - SSI 5931 ONVR
NWRLOTS-NRT-RTF-AV-RPT-105005-E
2.3 Land uses
2.3.1 Existing development
The existing land use survey has found that the SMTF is surrounding by predominately residential land.
2.3.2 Future development
While future development sites are required to be considered in the assessment of environmental noise
and vibration, the assessment is not strictly for the requirement of compliance via control at source, but
to assist development of, and inform land use planning controls.
As outlined in the noise and vibration assessment carried out during the EIS stage [8], it was
recommended that where possible, noise sensitive development such as residential development, be
removed from the immediate vicinity of the SMTF. However, with the land surrounding the SMTF,
particularly the eastern side of Tallawong Road being in close proximity to Cudgegong Road Station,
many other positive planning outcomes are addressed by locating residential development in proximity
to the SMTF.
While the acoustic design of the SMTF has been informed by the existing residential development, and
all feasible and reasonable mitigation and maintenance measures have been adopted to minimise the
source levels of noise and vibration, there are fewer options to control noise to the upper levels of
multi-level residential developments, being above noise barriers and less shielded by intervening
structures. Consultation with DP&E and TfNSW has therefore occurred in order to develop appropriate
design responses for future noise sensitive development proposed around the SMTF, particularly with
regard to Riverstone East North West Growth Centre [9].
Where residual noise impacts may result, particularly at upper levels of future development, NRT will
consult further with DP&E, TfNSW and Blacktown Council to assist with the identification of any
mitigation measures required by future development surrounding the SMTF.
2.3.3 Noise Catchment Areas (NCAs)
For the purpose of assessing noise, the residential areas surrounding the SMTF have been divided into
Noise Catchment Areas (NCAs) to north, east, south and west, which describe areas of similar
topographical and acoustic features. Figure B.1 in Appendix B presents the nominated NCAs used in the
noise design along with other noise sensitive receivers that have been identified in the land use survey.
Table 2-1 below summarises the NCAs identified for the SMTF design and provides a description of the
typical land uses and dwelling types found in each catchment.
RENZO TONIN & ASSOCIATES 18 JULY 2016
NORTHWEST RAPID TRANSIT
TG264-05 8F01 (R7) SSI 5931 ONVR [NWRLOTS-NRT-RTF-AV-RPT-
105005-E] 17
SYDNEY METRO TRAIN FACILITY (SMTF) - SSI 5931 ONVR
NWRLOTS-NRT-RTF-AV-RPT-105005-E
3 Noise and vibration criteria
This Section of the ONVR outlines the noise and vibration criteria for operation of the SMTF.
3.1 NSW Industrial Noise Policy (INP)
The noise generating equipment and operations associated with the SMTF are categorised as fixed
facilities, and in accordance with Condition F2 of SSI 5931, noise emissions are required to be assessed
against the NSW Industrial Noise Policy (INP) [5]. The Project Approval conditions require that
operational noise targets for fixed facilities and associated activities be identified in the ONVR.
The noise targets in the INP have been selected to protect at least 90 per cent of the population living in
the vicinity of industrial noise sources from the adverse effects of noise for at least 90 per cent of the
time. Provided the noise targets in the INP are achieved, then it is unlikely that most people would
consider the resultant noise levels excessive. In those cases where the noise targets are not, or cannot
be, achieved it does not automatically follow that those people affected by the noise would find the
noise unacceptable.
The INP sets two separate noise targets to meet environmental noise objectives: one to account for
‘intrusive’ noise and the other to protect the acoustic ‘amenity’ of particular land uses (e.g. residential).
The Intrusive Noise Target allows for controlled increases above the background noise levels and
manages intrusive noise impacts in the short-term for residences. The Amenity Target is specific to land
use and associated activities. It is designed to limit continuing increases in industrial noise sources and
maintain noise level amenity for particular land uses, for example residential, educational, and
recreational.
The INP defines three standard time periods for assessment being:
Day 7am to 6pm,
Evening 6pm to 10pm, and
Night time 10pm to 7am.
However Section 3.3 of the INP, details situations where different assessment periods or ‘shoulder’
periods may be established. The example provided in the INP is that of early morning operations (5am
to 7am), which may be proposed that occur during a period when the background noise level may be
steadily rising. In such a case, it may not be considered reasonable to assess the early morning
operations against a potentially more stringent night time noise criteria.
The Sleep Disturbance Targets specifically for night operations, have been determined in accordance
with the Application Notes of the INP [13] and the NSW Environmental Criteria for Road Traffic Noise
(‘ECRTN’) [14].
RENZO TONIN & ASSOCIATES 18 JULY 2016
NORTHWEST RAPID TRANSIT
TG264-05 8F01 (R7) SSI 5931 ONVR [NWRLOTS-NRT-RTF-AV-RPT-
105005-E] 20
SYDNEY METRO TRAIN FACILITY (SMTF) - SSI 5931 ONVR
NWRLOTS-NRT-RTF-AV-RPT-105005-E
whether there are times of day when there is a clear change in the noise environment
(such as during early morning shoulder periods).
The LA1, (1 minute) descriptor is meant to represent a maximum noise level measured under 'fast'
time response. The EPA will accept analysis based on either LA1, (1 minute) or LA, (Max).
In addition, reference is made to Appendix B of the NSW ECRTN [14], which summarises the findings of
international research undertaken on sleep disturbance from noise (up until 2009) and concludes:
“Considering all of the foregoing information the following conclusions can be drawn:
Maximum internal noise levels below 50-55dB(A) are unlikely to cause awakening
reactions.
One or two noise events per night, with maximum internal noise levels of 65-70dB(A), are
not likely to affect health and wellbeing significantly.”
In regard to external noise levels, the maximum internal noise level 55dB(A) referenced in the ECRTN is
equivalent to 65dB(A) outside an open window. It is noted that a 10dB(A) reduction from outside to
inside is common and typical noise reduction via an open window. The 65dB(A) external noise limit is
consistent with the findings of Griefahn [15].
In summary, the sleep disturbance criteria of LA1(1min) ≤ LA90(15min) + 15dB(A) is to be used for initial
assessment, however consideration is also given to the ‘upper’ limit criteria of 65dB(A) in accordance
with the ECRTN. It is noted that the background LA90(15minute) noise level used for establishing the sleep
disturbance criteria does not need to exclude other noise from the subject premise.
3.1.4 Established noise goals
Table 3-2 summarises the single Rating Background Levels (RBL) and relevant INP intrusiveness, amenity
and sleep disturbance noise criteria applicable at land uses surrounding the SMTF. In regard to the noise
amenity criteria, it is noted that no existing industrial noise contribution was identified at the nearest
most potentially affected receiver locations and therefore no modification to the amenity targets as per
Table 2.2 of the INP were required.
The established noise goals are based on the existing noise levels measured for the area, as described in
APPENDIX C. Any change in noise level as a result of future growth in the area cannot be readily
quantified. Therefore, these noise goals may be conservative, in particular for the day and evening
periods in NCAs RTF-03 and RTF-04.
RENZO TONIN & ASSOCIATES 18 JULY 2016
NORTHWEST RAPID TRANSIT
TG264-05 8F01 (R7) SSI 5931 ONVR [NWRLOTS-NRT-RTF-AV-RPT-
105005-E] 23
SYDNEY METRO TRAIN FACILITY (SMTF) - SSI 5931 ONVR
NWRLOTS-NRT-RTF-AV-RPT-105005-E
3.3 Rail infrastructure noise guideline (RING)
In accordance with Condition F1 of SSI 5931, the rail line components are to be designed and operated
with the objective of not exceeding the airborne and ground-borne noise trigger levels at existing
development. Condition C5 of SSI 5931 however defines the SMTF as a fixed facility and therefore
requires assessment against the NSW Industrial Noise Policy (INP) [5] only, and not the RING [7].
RENZO TONIN & ASSOCIATES 18 JULY 2016
NORTHWEST RAPID TRANSIT
TG264-05 8F01 (R7) SSI 5931 ONVR [NWRLOTS-NRT-RTF-AV-RPT-
105005-E] 24
SYDNEY METRO TRAIN FACILITY (SMTF) - SSI 5931 ONVR
NWRLOTS-NRT-RTF-AV-RPT-105005-E
4 Noise assessment inputs and procedures
4.1 Overview
The noise and vibration sources associated with normal operations of the SMTF include:
Trains in stabling area including preparation for service, arrival and departure movements
and internal cleaning,
Maintenance and cleaning activity within the maintenance building,
Train wash plant
Wheel reprofiling using a double headed underfloor wheel lathe (UFWL)
Mechanical equipment serving the Administration building, Maintenance building and
Infrastructure Workshop,
Electrical equipment, including substations and bulk supply.
External graffiti cleaning and biological cleaning, as well as intermittent use of the low speed
test track (535m) have not been included in the standard operational noise assessment of the
SMTF. Where practical, it is recommended that use of these facilities not occur during the
night time or early morning shoulder periods (10pm to 7am) for the purpose of noise
management.
4.2 Design year
Condition F4(b) of SSI-5931 states that the ONVR shall 'predict the operational noise and vibration
impacts at receiving existing development based on the final design and operation of the SSI (this should
include consideration of rail movements associated with future Tier 1 rail operations)'. It is noted that Tier
1 rail operations relate to single-deck rapid transit services, rather than Tier 2 (double-deck suburban
train services) or Tier 3 (double-deck intercity train services) [18, pp. 1-7].
The capacity of the SMTF will expand over time, to accommodate additional trains that are forecast to
operate on the Sydney Metro Northwest line, as well maintain metro trains that are proposed to operate
on the expanded metro rail network. The current design of the SMTF is to provide stabling and
maintenance for up to 37 sets of six-car trains. This is referred to as the 'Ultimate Design' year, being the
ultimate capacity of the current design. The SMTF will however initially operate with a fleet size of 22
sets of six-car trains ('Initial design year,').
Future design augmentation within the current site boundary will be required to provide for the
maintenance of up to 76 eight-car trains and stabling of up to 46 eight-car trains ('safeguarded
capacity'). In addition, on-site car parking requirements will increase from 121 spaces to 228.
Consideration of this 'Augmentation' scenario has been considered in-principle. Under operations for
RENZO TONIN & ASSOCIATES 18 JULY 2016
NORTHWEST RAPID TRANSIT
TG264-05 8F01 (R7) SSI 5931 ONVR [NWRLOTS-NRT-RTF-AV-RPT-
105005-E] 25
SYDNEY METRO TRAIN FACILITY (SMTF) - SSI 5931 ONVR
NWRLOTS-NRT-RTF-AV-RPT-105005-E
Augmentation, the increase in LAeq noise levels is predicted to be between 2-3dB(A), assuming a
proportional increase in train activity, car park movements and general operations.
We understand that Augmentation may also require 24-hour operation of the Train Wash Plant and
extended operation of the Wheel Lathe. The assessment presented herein indicates that the Train Wash
Plant is not dominant in comparison to other major sources, and while the Wheel Lathe is a primary
contributor at , its operation would result in only marginal increases in the night
time predicted noise level (less than 2dB(A)).
The land use planning changes proposed for the area surrounding the SMTF will result in a very
different acoustic environment by Augmentation, compared with Ultimate design year. So as not to
impose unfairly stringent noise mitigation and operational management measures on the SMTF, the
assessment and design outcomes detailed in this report are based on Ultimate design year operations.
It is noted that as the timing for expansion between Initial and Ultimate design year is not known, the
acoustic design of the SMTF is conservatively based on existing background noise levels and Ultimate
design year operations.
4.3 SMTF Operations
Noise emission from the SMTF will vary throughout the daytime, evening and night-time periods on the
basis of train movements and operations, loads on mechanical equipment, and types of activities such
as cleaning, maintenance and wheel lathe operation. For noise assessment and design purposes, it is
necessary to develop noise modelling scenarios that accurately represent the proposed operations
during the relevant assessment periods.
Typical worst-case scenarios have been established for the range of assessment time periods and key
operational variations. Table E1 in Appendix E summarises the operational assumptions used for the
purpose of noise mitigation design. The following discusses the basis of specific operating assumptions.
4.3.1 Stabling yard
1. The SMTF has been designed to stable up to 37 six-car train sets.
2. It has been conservatively assumed that all 37 train are stabled at the SMTF overnight. In
practice, there is potential for some trains to be stabled overnight at underground stations.
This has an acoustic benefit in that it reduces the number of trains requiring preparation in
the early morning period.
3. While stabled at the yard, pantographs will be lowered and trains powered down.
4. Prior to trains departing for service, trains are powered and run through a series of test
procedures to ensure they are ready for service. This process takes approximately 20 minutes
per train, and is to occur in batches of 5 trains (for redundancy). The procedure involves:
a. Raising of pantographs and operation of auxiliary converter (Constant Voltage Source -
CVS)
RENZO TONIN & ASSOCIATES 18 JULY 2016
NORTHWEST RAPID TRANSIT
TG264-05 8F01 (R7) SSI 5931 ONVR [NWRLOTS-NRT-RTF-AV-RPT-
105005-E] 26
SYDNEY METRO TRAIN FACILITY (SMTF) - SSI 5931 ONVR
NWRLOTS-NRT-RTF-AV-RPT-105005-E
b. Testing of electrical systems
c. Operation of air compressor
d. Operation of Heating, Ventilation and Air-conditioning (HVAC) (ventilation mode in
morning / medium cooling in afternoon)
5. Once trains are prepared and ready for departure systems will remain on and idle.
6. Interior cleaning of trains will occur in the stabling yard and be carried out on a daily basis, 2
hours following morning peak, 2 hours following evening peak and 2 hours once all trains
have returned from service at night [19].
7. Appendix E outlines the noise sources and modelling assumptions for the stabling yard.
4.3.2 Rolling stock
1. Noise from trains within the SMTF will predominately relate to auxiliary systems on the train,
including HVAC, CVS and air compressors. Air compressors will typically operate only during
start-up preparations, for a short period, until air reservoirs are full.
2. In accordance with Condition C5 of SSI-5931 silencers have been incorporated into the
compressed air lines of the rolling stock to reduce noise from brake air release events. The
noise level at 1m from the brake pipe is to be less than 85dB(A), which is a significant
reduction when compared to current Sydney trains fleet. In addition, unlike the Sydney Trains
fleet, brake pipe noise events will be limited as the brake pipe is not required to be vented
during start-up procedures. The air reservoirs are required to be drained during preventative
maintenance (PM03) [19], however this is to occur within the maintenance building.
3. In addition to the above, and in accordance with Condition C5 of SSI-5931, methods to
minimise rolling stock auxiliary noise levels have been investigated. This has resulted in
enclosure of the compressor and provision of attenuators to the compressor air dryer and
HVAC supply air fan. Furthermore, the HVAC system has been design with multiple modes of
operation, which vary in noise level, to ensure noise levels are minimised as far as practical
according to operating load requirements. For example, the highest noise levels, associated
with the 'High Cooling' mode, are unlikely to result in the SMTF, due to ambient temperature
conditions and no internal heat load within the carriages (no passengers).
4. Door test procedures, required during start-up of trains, have also been modified to reduce
noise emission from the SMTF, with the chimes and automated announcements not being
sounded.
5. The HVAC operation will automatically adjust to external ambient temperatures and to meet
Project specifications for customer comfort and internal temperature conditions of the train.
These are considered as part of the noise modelling scenarios. The key assumptions are
outlined:
RENZO TONIN & ASSOCIATES 18 JULY 2016
NORTHWEST RAPID TRANSIT
TG264-05 8F01 (R7) SSI 5931 ONVR [NWRLOTS-NRT-RTF-AV-RPT-
105005-E] 27
SYDNEY METRO TRAIN FACILITY (SMTF) - SSI 5931 ONVR
NWRLOTS-NRT-RTF-AV-RPT-105005-E
a. External ambient temperatures are based on meteorological data for BOM Station
067105 Richmond RAAF for 1993 to 2015, as presented in Section 4.3.4,
b. For morning start up and departure (03:40 to 07:05), HVAC will operate in ventilation
mode only – Mean 9am temperature all below 23 degrees.
c. For afternoon departures (15:20 to 16:55) HVAC may operate at medium cooling -
Mean max temp and Mean 3pm temp. Temperatures above 30deg being 61 days
(mean) annually. Note only 1dB increase for high cooling.
d. On trains return to the SMTF following service, HVAC will be in ventilation mode only
(no passengers or staff)
e. For internal cleaning during the night period, HVAC will operate in ventilation mode
only based on mean 9am temperature all below 23 degrees. Staff cannot override the
programmed operation of the HVAC.
6. Trains will be predominately controlled automatically from the operations control centre and
their speed will not exceed 25km/h (includes departure and arrival from the SMTF) [19].
Trains under manual control will be limited to 10km/h, with entry into maintenance building
limited to 6km/h.
7. Appendix E outlines the noise sources and modelling assumptions for the rolling stock.
4.3.3 Rail track
1. The majority of rail track within the SMTF is to be formed on ballast
2. To reduce potential increase in noise caused flanging at the wheel-rail interface, wheel flange
lubricators are fitted to the rolling stock.
3. Trackside lubricators are also installed at two locations, at the main branches accessing the
stabling roads (~47+414) and maintenance building (~47+357).
4.3.4 Maintenance building
1. The Maintenance building includes:
a. Five stabling roads including one for heavy cleaning, and one train lift.
b. Train lift
c. Loading area - Three overhead cranes for the lifting of train equipment such as HVAC,
pantographs and bogie handling [19].
2. First line maintenance of trains including preventive, corrective maintenance, roof and
underframe equipment change out will be carried out by MTS’s in-house staff [19].
RENZO TONIN & ASSOCIATES 18 JULY 2016
NORTHWEST RAPID TRANSIT
TG264-05 8F01 (R7) SSI 5931 ONVR [NWRLOTS-NRT-RTF-AV-RPT-
105005-E] 28
SYDNEY METRO TRAIN FACILITY (SMTF) - SSI 5931 ONVR
NWRLOTS-NRT-RTF-AV-RPT-105005-E
3. The scheduled and unscheduled maintenance of trains will be carried out on the service
roads and lifting road in the Maintenance Building service roads and lifting road in the
Maintenance Building [19].
4. Overhaul of trains including second line maintenance, remove and reinstall of major
equipment, major repairs of on train equipment and overhaul of removed equipment and
components will be contracted out [19].
5. Failure repair of major equipment such as bogies, traction motors, pantograph and air
compressors etc. will be outsourced. Failure repairs of minor equipment or components
which involve specific knowledge, tools and equipment will be outsourced to Original
Equipment Manufacturers or their maintenance contractors [19].
6. Should heavy maintenance be proposed in the Maintenance building in the future, provision
has been made for noisier works to be contained within bays along the northern side of the
Maintenance building which can be readily upgraded through construction of internal
partition walls, including additions to the external building envelope (internal skin), secondary
roof and doors if required. Modification of the intake louvres may be required to
accommodate the changes.
7. Heavy cleaning for each set will occur on an approximate monthly basis on the heavy
cleaning road inside the Maintenance building [19]. Cleaning is proposed to take place
between 10:00 to 14:00 and 19:00 to 23:00 with an average of 1.32 jobs per day [19]. Lighting
and air-conditioning units may be turned on for the cleaning team [19].
8. The Maintenance building will accept deliveries to the loading dock between 7:00am and
10:00pm only. Delivery truck movements are not proposed to occur between 10:00pm and
7:00am in accordance with Minister's Condition C5 (SSI 5931).
9. The Maintenance building will be ventilated using assisted natural ventilation. A combination
of smoke and ventilation fans on the roof, along with louvred ventilation openings along the
sides of the building will assist in moving air through the building. These features have been
incorporated into the noise model and form part of the acoustic design.
10. Heating and cooling to specific work areas will also be provided with the associated external
mechanical equipment located on the rooftop of the Maintenance building. The locations
have been positioned so as they are away from building edges and acoustically shielded as
far as practical by the sawtooth roof form.
11. Appendix E outlines the noise sources and modelling assumptions for the Maintenance
building.
4.3.5 Administration building
1. The Administration building will operate 24 hours per day, 7 days per week. For design
purposes the only environmental noise sources associated with this building are mechanical
plant and noise generated by car parking activities on site (mainly during shift changes).
RENZO TONIN & ASSOCIATES 18 JULY 2016
NORTHWEST RAPID TRANSIT
TG264-05 8F01 (R7) SSI 5931 ONVR [NWRLOTS-NRT-RTF-AV-RPT-
105005-E] 30
SYDNEY METRO TRAIN FACILITY (SMTF) - SSI 5931 ONVR
NWRLOTS-NRT-RTF-AV-RPT-105005-E
4.3.8 Under Floor Wheel Lathe
1. A double headed underfloor wheel lathe is to be installed within the Wheel Lathe building.
2. For the Ultimate design year scenario the wheel lathe is proposed to operate 8 hours per day,
7 days a week. The production rate is 5 passenger train wheelsets per 8-hour shift [19].
3. Use may extend to 16 hours per day when expanded to 46 eight car sets and (07:00 to 23:00),
and 24-hour work days for full Augmentation.
4. The train is not operational during the lathing process and the train is moved using an
electric train shunter.
5. Appendix E outlines the noise sources and modelling assumptions for the Wheel Lathe.
4.3.9 Infrastructure Workshop and Rail Store
1. The Infrastructure Workshop is proposed to be used during the 07:00 to 18:00 daytime
period only.
2. General operational noise sources from the buildings are limited to mechanical plant
equipment as detailed in Appendix E.
4.3.10 Distribution and Traction building
1. The Distribution and Traction building equipment will operate 24 hours per day, 7 days per
week.
2. For acoustic design purposes the only environmental noise emission sources identified for
this building are the transformers and reactor. Harmonic Filters form part of the DC
Switchboard and are installed indoors in a purpose built switch room. Noise emission will
therefore not be significant and has not been included in the noise model.
3. Noise emission from circuit breakers has not been included in the operational noise
assessment as they occur under fault conditions, which are highly irregular events.
4. Appendix E outlines the noise sources and modelling assumptions for the Distribution and
Traction building.
4.3.11 Bulk Supply building
1. The Bulk Supply equipment will operate 24 hours per day, 7 days per week.
2. For design purposes the only environmental noise emission source identified for this building
is the bulk supply transformer. Harmonic Filters may be required and are yet to be confirmed.
3. Appendix E outlines the noise sources and modelling assumptions for the Bulk Supply
building.
RENZO TONIN & ASSOCIATES 18 JULY 2016
NORTHWEST RAPID TRANSIT
TG264-05 8F01 (R7) SSI 5931 ONVR [NWRLOTS-NRT-RTF-AV-RPT-
105005-E] 31
SYDNEY METRO TRAIN FACILITY (SMTF) - SSI 5931 ONVR
NWRLOTS-NRT-RTF-AV-RPT-105005-E
4.3.12 Fire pump room
1. On the basis of the specified equipment and building design outlined in Appendix E, noise
levels are predicted to comply with the emergency noise requirements for the full perimeter
of the building excluding louvre locations where noise levels are predicted to exceed the
requirement by 3dB(A). The exceedance is predicted only for the operation of the diesel
pump.
2. It is noted that the pump only operates in emergencies and is not part of the environmental
noise model.
3. While a diesel pump with lower sound power will be sought during procurement, additional
acoustic treatment of the building envelope is not considered reasonable or feasible for the
limited operation of the pump. It is noted that the louvres have been positioned on the
western and southern sides of the building so as to direct noise away from the most sensitive
locations. It is understood that during operation, personnel will not be in close proximity to
the building, particularly the facades comprising acoustic louvres.
4.4 Noise modelling
4.4.1 Environmental noise predictions
Environmental noise predictions were carried out using the CONCAWE [21] noise prediction algorithm
as implemented within the CadnaA 3D noise modelling software (version 4.5.151). The CONCAWE
algorithm predicts noise levels that take into account noise attenuation due to distance, ground
topography, acoustic shielding from intervening elements, noise reduction of building envelope
components, atmospheric absorption and meteorological conditions.
Predicted noise emissions are based on the sources and assumptions in Appendix E to ensure that
cumulative noise impact from all sources within the SMTF has been taken into account. Results of noise
predictions are presented in Appendix F, incorporating all noise mitigation and management design
measures contained in this report.
4.4.2 Noise generation within buildings
Noise generation within buildings, including the Maintenance building, Wheel Lathe, Train Wash and
components of the Administration Building roof top plant room were modelled within CadnaR 3D noise
modelling software (version 2.2.105) prior to being incorporated into the CadnaA environmental noise
model.
4.4.3 Meteorological conditions
In accordance with the INP, the noise assessment considers the effects of adverse meteorological
conditions such as wind and temperature inversions. The noise enhancement from temperature
inversion is required to be assessed when temperature inversions are predicted to occur more than 30%
RENZO TONIN & ASSOCIATES 18 JULY 2016
NORTHWEST RAPID TRANSIT
TG264-05 8F01 (R7) SSI 5931 ONVR [NWRLOTS-NRT-RTF-AV-RPT-
105005-E] 35
SYDNEY METRO TRAIN FACILITY (SMTF) - SSI 5931 ONVR
NWRLOTS-NRT-RTF-AV-RPT-105005-E
5 Acoustic design outcomes
The noise mitigation and management measures recommended for incorporation into the SMTF design
are presented in Appendix E. The advice provided is in respect of acoustics only.
5.1 Summary of predicted noise levels
Table F1 in Appendix F presents a summary of the predicted noise levels for the various operating
scenarios outlined in Table E1.
The primary noise sources contributing to each of the predicted exceedances have also been identified
in Tables F2 to F4 for the Shoulder, Day and Evening periods respectively for the locations where non-
compliance is predicted.
In all cases, the primary contributors to predicted exceedances are noise sources not readily controlled
through design of the SMTF buildings, including trains in the stabling area, truck movements, door
openings (Maintenance building) and open ends of buildings (wheel lathe) etc.
5.2 Feasible and reasonable design measures
The assessment of feasible and reasonable mitigation measures is based on the guidance in
Sections 1.4.5 and 7 of the NSW INP.
In this context feasibility relates to engineering considerations and what can practically be built, and
reasonableness relates to the application of judgement in arriving at a decision, taking into account the
following factors:
noise mitigation benefits - amount of noise reduction provided, number of people protected
cost of mitigation - cost of mitigation versus benefit provided
community views - aesthetic impacts and community wishes
noise levels for affected land uses – existing and future levels, and changes in noise levels
A range of noise mitigation measures have been considered as part of the noise mitigation design to
protect noise sensitive receivers surrounding the SMTF. There are three categories into which these
noise mitigation measures can fall:
In-Corridor Treatment (at source);
In-Corridor Treatment (between source and receiver); and
At Property Treatment (at receiver).
The preferred noise mitigation treatment option is ‘In-Corridor Treatment (at source)’, such as building
HVAC treatment, architectural attenuation measures, train subsystem noise control or changes to work
RENZO TONIN & ASSOCIATES 18 JULY 2016
NORTHWEST RAPID TRANSIT
TG264-05 8F01 (R7) SSI 5931 ONVR [NWRLOTS-NRT-RTF-AV-RPT-
105005-E] 41
SYDNEY METRO TRAIN FACILITY (SMTF) - SSI 5931 ONVR
NWRLOTS-NRT-RTF-AV-RPT-105005-E
of higher density development, may be exposed to noise levels above those recommended in the NSW
INP. However, it is considered that the likely noise exposure, even after future expansion of the SMTF,
will be acceptable, provided that some mitigation measures and controls are incorporated into the
design of the residential development. Accordingly, objectives and controls have been incorporated into
the Riverstone East Growth Centre DCP to require consideration of noise emission from the SMTF in the
design of the future development. Similar controls would also be required for development within the
Area 20 Growth Centre that are located in proximity to the SMTF.
Notwithstanding the controls outlined, further consultation between NRT, DP&E and TfNSW will be
required to determine the expected noise exposure at any future development site, in order to permit
assessment and design of the future uses.
RENZO TONIN & ASSOCIATES 18 JULY 2016
NORTHWEST RAPID TRANSIT
TG264-05 8F01 (R7) SSI 5931 ONVR [NWRLOTS-NRT-RTF-AV-RPT-
105005-E] 42
SYDNEY METRO TRAIN FACILITY (SMTF) - SSI 5931 ONVR
NWRLOTS-NRT-RTF-AV-RPT-105005-E
6 Consultation with affected property owners
6.1 Existing dwellings
Once the ONVR has been submitted to DP&E, consultation with owners of existing structures that
require at-property noise mitigation treatment (as identified in Table 5-3) will commence.
As set out in Section 5.3, at-property treatments may comprise:
Property boundary fencing or other external screen walls, and / or
Fresh air ventilation systems, that allow existing windows and doors to be shut to all
habitable rooms identified as potentially impacted by noise.
[Note: The above is dependent on advice from mechanical ventilation contractor for rooms
requiring windows/doors to be closed for noise mitigation. Air conditioning will not be
provided by the Project in this case.]
Habitable rooms potentially impacted by noise may also require:
Sealing of any wall vents,
Replacement of existing weather seals on doors and windows with acoustic seals,
Upgrade of doors and windows,
[Note: Shall only be conducted on buildings with masonry construction because light frame
structures will not achieve a significant noise benefit.]
It is noted that the above described treatments will only be offered to residences with rooms defined as
‘habitable’ (eligible for eg. bedrooms, living rooms, dining rooms etc.) having facades that are identified
as potentially impacted by noise from the Project. The level of treatment to be offered to individual
residences will depend on the noise reduction required and the location of habitable rooms.
It is also noted, that for a building to be eligible for upgraded windows, glazing and solid core doors, as
described above in Item 4, it must be of masonry construction (eg brick or block work etc), because this
higher level of noise mitigation treatment will not achieve a significant noise benefit for buildings of
light frame construction.
Based on the approved ONVR, specific residences for treatment and the noise reduction required for
each residence will be confirmed. Consultation with these property owners will involve:
An initial letter sent to affected property owners, outlining the requirements of the property
treatment, the level of treatment required for the subject property and next steps.
A phone call to discuss whether the property owner will initially agree to a property
inspection, which is required to determine the exact scope of the treatment to be provided.
RENZO TONIN & ASSOCIATES 18 JULY 2016
NORTHWEST RAPID TRANSIT
TG264-05 8F01 (R7) SSI 5931 ONVR [NWRLOTS-NRT-RTF-AV-RPT-
105005-E] 43
SYDNEY METRO TRAIN FACILITY (SMTF) - SSI 5931 ONVR
NWRLOTS-NRT-RTF-AV-RPT-105005-E
If the owner agrees to the inspection, NRT will arrange a time to measure up and record
internal layouts.
Specific property information will then be utilised to determine the most appropriate form of
acoustic treatment for each eligible property, with input from NRT’s acoustic consultant,
Renzo Tonin and Associates, where required. Only treatments that are required to meet
relevant noise criteria will be offered.
A schedule of the designed treatment would be provided to the property owner. Should the
owner agree to this treatment, the owner will be asked to sign a Deed of Release.
Following receipt of the signed Deed of Release, NRT will liaise with the property owner to
arrange a suitable time for the specific treatment to be installed.
Alternatively, if the property owner would like to arrange for the purchase and installation of the
required treatment(s), NRT will provide a one off payment to cover the reasonable cost of the works (as
estimated by NRT) following receipt of the signed Deed of Release.
Any queries relating to operational noise from residents that are not eligible to receive at-property
treatments will be responded to through the Project complaints management process in accordance
with the Community Liaison Plan.
6.2 Future development
As outlined in Section 5.4, further consultation between NRT, DP&E and TfNSW is expected to be
required to determine the expected noise exposure at any future development sites surrounding the
SMTF, in order to permit others to assess and design for noise exposure upon the future uses.
RENZO TONIN & ASSOCIATES 18 JULY 2016
NORTHWEST RAPID TRANSIT
TG264-05 8F01 (R7) SSI 5931 ONVR [NWRLOTS-NRT-RTF-AV-RPT-
105005-E] 44
SYDNEY METRO TRAIN FACILITY (SMTF) - SSI 5931 ONVR
NWRLOTS-NRT-RTF-AV-RPT-105005-E
7 Operational noise monitoring program
7.1 Monitoring of noise emissions from the SMTF
In accordance with Minster for Planning and Infrastructure's Conditions of Approval Condition F2,
operational noise levels shall be reviewed within two years of commencement of operations and at any
subsequent time as required by the Director General. The review shall have regard to the status of land
use planning, any land use changes and the background noise environment within areas adjacent to the
fixed facilities at the time of the relevant review. NRT shall submit the results of the review to the
Director General. Any proposed changes to the operational noise levels as a result of the review shall be
included in a revised ONVR.
7.2 Operational noise complaint response procedures
The operator is committed to a strong program of customer engagement will be developed to
encourage ongoing feedback that will be used in the continual improvement of the Sydney Metro
Northwest services. As part of the Project requirements, the operator is to prepare an "Operational
Phase Environmental and Sustainable Plan", which is to be provided 120 days prior to trial running. This
document will provide further detail around the complaints management procedures, however the
following principles are to be adopted:
The public will be able to make enquiries and complaints through a number of channels,
including:
phone lines operated by TfNSW on behalf of the NSW Government
website operated by TfNSW on behalf of the NSW Government using feedback
mechanisms such as online forms, and
Operator email, for example [email protected]
Enquiries and complaints received by TfNSW in relation to the operation of Sydney
Metro Northwest will be directed to the operator for response and action.
All complaints are to be recorded and follow up actions documented
All complaints will be investigated in order to establish the nature of the noise and vibration
disturbance. At the discretion of the complainant(s) the operator shall contact the complaint,
Following initial investigation of the complaint, an appropriate course of action will be
determined and communicated with the complainant. This may involve:
Direct and prompt rectification of the cause of complaint where it is identified that the
source of noise or vibration is not operating in accordance with the Project
requirements,
Further investigation by a qualified acoustic consultant to quantify and assess the
source of noise and/or vibration against the Project requirements,
RENZO TONIN & ASSOCIATES 18 JULY 2016
NORTHWEST RAPID TRANSIT
TG264-05 8F01 (R7) SSI 5931 ONVR [NWRLOTS-NRT-RTF-AV-RPT-
105005-E] 45
SYDNEY METRO TRAIN FACILITY (SMTF) - SSI 5931 ONVR
NWRLOTS-NRT-RTF-AV-RPT-105005-E
If the source is found to be non-compliant with the Project requirements, feasible and
reasonable mitigation measures will be investigated.
Where noise and/or vibration measures are determined to be required, a program for
rectification works will be established and communication with the complainant.
RENZO TONIN & ASSOCIATES 18 JULY 2016
NORTHWEST RAPID TRANSIT
TG264-05 8F01 (R7) SSI 5931 ONVR [NWRLOTS-NRT-RTF-AV-RPT-
105005-E] 46
SYDNEY METRO TRAIN FACILITY (SMTF) - SSI 5931 ONVR
NWRLOTS-NRT-RTF-AV-RPT-105005-E
8 Independent verification of noise and vibration study
This Section of the ONVR outlines the independent verification of the operational noise and vibration
impact assessment undertaken by a noise and vibration expert approved by the Director-General of the
Department of Planning and Infrastructure
In accordance with the Minister for Planning and Infrastructures' Conditions of Approval the ONVR has
been independently reviewed by a noise and vibration expert approved by the Director-General.
AECOM were engaged to undertake this independent verification role. The AECOM team consists of:
- Principal Acoustic Engineer
The Director-General granted approval for AECOM to undertake this role on 10 February 2016.
The verification scope was developed in consultation with the EPA on 9 February 2016 as required by
Condition F4 of SSI-5931. The scope includes:
Review of background noise monitoring results and fixed facilities targets.
Review of adopted noise and vibration criteria.
Review of the adequacy of the methodology utilised.
Review of modelling inputs and outputs.
Review of the adequacy of the conclusions in relation to the potential extent of noise and
vibration impact and the required mitigation.
A statement of verification has been prepared by AECOM and is attached in APPENDIX G.
RENZO TONIN & ASSOCIATES 18 JULY 2016
NORTHWEST RAPID TRANSIT
TG264-05 8F01 (R7) SSI 5931 ONVR [NWRLOTS-NRT-RTF-AV-RPT-
105005-E] 47
SYDNEY METRO TRAIN FACILITY (SMTF) - SSI 5931 ONVR
NWRLOTS-NRT-RTF-AV-RPT-105005-E
9 Conclusion
This Operational Noise and Vibration Review (ONVR) has been prepared in accordance with the
requirements of the Ministers Conditions Approval for State Significant Infrastructure SSI-5931, and
additional requirements of the Project’s Scope and Performance Requirements (SPRs) Appendix 44. The
ONVR has been prepared in consultation with relevant the government agencies and has been
independently peer reviewed.
This ONVR confirms the proposed noise and vibration mitigation measures that are to be implemented
into the design and operation of the Sydney Metro Train Facility (SMTF) and discusses when these will
be implemented and how they will be verified once the Project is operational. A complaints
management procedure is also outlined for the ongoing management of noise and vibration from the
SMTF.
RENZO TONIN & ASSOCIATES 18 JULY 2016
NORTHWEST RAPID TRANSIT
TG264-05 8F01 (R7) SSI 5931 ONVR [NWRLOTS-NRT-RTF-AV-RPT-
105005-E] 48
SYDNEY METRO TRAIN FACILITY (SMTF) - SSI 5931 ONVR
NWRLOTS-NRT-RTF-AV-RPT-105005-E
References
[1] Minister for Planning and Infrastructure, “SSI-5931 Infrastructure Approval,” NSW Government,
2014.
[2] Minister for Planning and Infrastructure, “SSI-5414 Infrastructure Approval,” NSW Government,
2013.
[3] Department of Planning, “Stage 3 Project Assessment,” 2013.
[4] NSW Department of Planning, “Stage 3 Submissions report”.
[5] NSW EPA, NSW Industrial Noise Policy, Sydney: Environmental Protection Authority, 2000.
[6] Department of Environment and Conservation (NSW), “Assessing Vibration: A technical guideline,”
Department of Environment and Conservation (NSW), Sydney, 2006.
[7] NSW EPA, Rail Infrastructure Noise Guideline, Sydney: Environment Protection Authority, 2013.
[8] SLR Consulting Australia Pty Ltd, “North west Rail Link Rapid Transit Rail Facilty Noise Assessment
(Appendix F of EIS),” NSW Transport for NSW, Sydney, 2013.
[9] NSW Planning & Environment, “Riverstone East ILP Draft,” June 2015. [Online]. Available:
http://growthcentres.planning.nsw.gov.au/Portals/0/Riverstone%20East/
Riverstone%20East%20exhibition%20documents/Riverstone%20Simplified%20ILP.pdf. [Accessed
14 September 2015].
[10] NSW Planning & Environment, “Alex Avenue Precinct: Indicative Layout Schedule,” April 2010.
[Online]. Available: http://growthcentres.planning.nsw.gov.au/Portals/0/docs/Alex%20Avenue
/Alex%20Ave%20ILP.pdf. [Accessed 2 March 2015].
[11] NSW Planning & Environment, “Riverstone Precinct: Indicative Layout Schedule,” May 2010.
[Online]. Available:
RENZO TONIN & ASSOCIATES 18 JULY 2016
NORTHWEST RAPID TRANSIT
TG264-05 8F01 (R7) SSI 5931 ONVR [NWRLOTS-NRT-RTF-AV-RPT-
105005-E] 49
SYDNEY METRO TRAIN FACILITY (SMTF) - SSI 5931 ONVR
NWRLOTS-NRT-RTF-AV-RPT-105005-E
http://growthcentres.planning.nsw.gov.au/Portals/0/docs/Riverstone/Riverstone_ILP.pdf. [Accessed
2 March 2015].
[12] NSW Planning & Environment, “Draft Plans and Policies: Changes to planning controls in the Area
20 Precinct,” Department of Planning & Infrastructure, 19 December 2014. [Online]. Available:
http://planspolicies.planning.nsw.gov.au/index.pl?action=view_job&job_id=6795. [Accessed 29
April 2015].
[13] NSW EPA, “Application notes - NSW Industrial Noise Policy,” 12 June 2013. [Online]. Available:
http://www.epa.nsw.gov.au/noise/applicnotesindustnoise.htm. [Accessed 4 December 2014].
[14] NSW EPA, Environmental Criteria for Road Traffic Noise, Chatswood: Environmental Protection
Authority, 1999.
[15] B. Griefahn, “Noise control during night,” Acoustics Australia, vol. 20, no. 2, pp. 43-47, 1992.
[16] DEC, “Assessing Vibration: A technical guideline”.
[17] Bristish Standard, “BS6472,” 1992.
[18] Transport for NSW, “Environmental Impact Statement Stage 2-Stations, Rail Infratructure and
Systems,” Transport for NSW, Sydney, 2012.
[19] Northwest Rapid Transit, “NWRLOTS-NRT-RTF-GN-PLN-720100-D RTRF Operation Plan,” NRT,
2015.
[20] German Federal Ministry of Transport, Dept. for Road Construction, “Guidelines for Noise Control
at Roads (RLS-90),” German Federal Ministry of Transport, Dept. for Road Construction, 1990.
[21] CONCAWE, “The propagation of noise from petroleum and petrochemical complexes to
neighbouring communities,” 1981.
[22] NSW Planning & Environment, “Area 20 Precinct: Indicative Layout Schedule,” August 2011.
[Online]. Available:
http://growthcentres.planning.nsw.gov.au/Portals/0/docs/Area%2020/A20_FINAL_ILP.pdf.
[Accessed 2 March 2015].
RENZO TONIN & ASSOCIATES 18 JULY 2016
NORTHWEST RAPID TRANSIT
TG264-05 8F01 (R7) SSI 5931 ONVR [NWRLOTS-NRT-RTF-AV-RPT-
105005-E] 50
SYDNEY METRO TRAIN FACILITY (SMTF) - SSI 5931 ONVR
NWRLOTS-NRT-RTF-AV-RPT-105005-E
[23] NSW Department of Planning, “Development near Rail Corridors and Busy Roads – Interim
Guideline,” NSW Department of Planning, Sydney, 2008.
[24] NSW Government, “State Environmental Planning Policy (Infrastructure),” Sydney, 2007.
[25] NSW Department of Planning & Infrastructure, “Director General's Environmental Assessment
Report SSI13-5931,” NSW Department of Planning & Infrastructure, 2014.
[26] R. Hoover and R. Keith, “Noise Control for Mechanical and Ventilations Systems,” in Encyclopedia
of Acoustics V3 ed. Malcom J. Croker, New York, John Wiley & Sons, Inc., 1997, pp. 1219-1241.
RENZO TONIN & ASSOCIATES 18 JULY 2016
NORTHWEST RAPID TRANSIT
TG264-05 8F01 (R7) SSI 5931 ONVR [NWRLOTS-NRT-RTF-AV-RPT-
105005-E] 53
SYDNEY METRO TRAIN FACILITY (SMTF) - SSI 5931 ONVR
NWRLOTS-NRT-RTF-AV-RPT-105005-E
APPENDIX B Land use survey and receiver locations
RENZO TONIN & ASSOCIATES 18 JULY 2016
NORTHWEST RAPID TRANSIT
TG264-05 8F01 (R7) SSI 5931 ONVR [NWRLOTS-NRT-RTF-AV-RPT-
105005-E] 55
SYDNEY METRO TRAIN FACILITY (SMTF) - SSI 5931 ONVR
NWRLOTS-NRT-RTF-AV-RPT-105005-E
Figure B.2: Riverstone East Draft Indicative Layout Plan [9]
RENZO TONIN & ASSOCIATES 18 JULY 2016
NORTHWEST RAPID TRANSIT
TG264-05 8F01 (R7) SSI 5931 ONVR [NWRLOTS-NRT-RTF-AV-RPT-
105005-E] 56
SYDNEY METRO TRAIN FACILITY (SMTF) - SSI 5931 ONVR
NWRLOTS-NRT-RTF-AV-RPT-105005-E
Figure B.3: Alex Avenue Indicative Layout Plan [10]
RENZO TONIN & ASSOCIATES 18 JULY 2016
NORTHWEST RAPID TRANSIT
TG264-05 8F01 (R7) SSI 5931 ONVR [NWRLOTS-NRT-RTF-AV-RPT-
105005-E] 58
SYDNEY METRO TRAIN FACILITY (SMTF) - SSI 5931 ONVR
NWRLOTS-NRT-RTF-AV-RPT-105005-E
Figure B.5: Area 20 Precinct Indicative Layout Plan [22]
RENZO TONIN & ASSOCIATES 18 JULY 2016
NORTHWEST RAPID TRANSIT
TG264-05 8F01 (R7) SSI 5931 ONVR [NWRLOTS-NRT-RTF-AV-RPT-
105005-E] 62
SYDNEY METRO TRAIN FACILITY (SMTF) - SSI 5931 ONVR
NWRLOTS-NRT-RTF-AV-RPT-105005-E
APPENDIX D Noise logger graphs
Date Day Evening Night Day Evening Night
Tuesday-25-November-2014 - 43.1 33.0 - 56.1 50.6
Wednesday-26-November-2014 44.0 42.6 36.1 58.3 56.1 49.9
Thursday-27-November-2014 46.9 45.2 30.6 57.8 57.3 50.7
Friday-28-November-2014 41.5 45.6 26.8 59.4 57.1 50.1
Saturday-29-November-2014 39.0 43.5 30.3 55.8 55.7 50.0
Sunday-30-November-2014 - - - - - -
Monday-01-December-2014 41.6 44.2 - 57.2 55.6 -
Tuesday-02-December-2014 43.5 43.6 42.3 57.3 54.4 51.7
Wednesday-03-December-2014 - - - - - -
Representative Weekday 43.5 43.9 33.0 58.1 56.2 50.6
Representative Weekend 39.0 43.5 30.3 55.8 55.7 50.0Representative Week 42.6 43.6 31.8 57.8 56.1 50.5
Notes:
1. Day is taken to be 7:00am to 6:00pm 4. Rating Background Level (RBL) for L90 and logarithmic average for Leq
2. Evening is taken to be 6:00pm to 10:00pm. 5. Assessment Background Level (ABL)
3. Night is taken to be the remaining periods. 6. Rating Background Level (RBL) for L90 and logarithmic average for Leq
Template QTE-05B (rev 109) Sydney Logger Graphs TG264-05 4 1 1S0X (r0) M_RT01 - 88 Amarco Cct
LA90 Background Noise Levels5 LAeq Ambient Noise Levels
, The Ponds
Background & Ambient Noise Monitoring Results - NSW 'Industrial Noise Policy', 2000
AcousticsVibration
Structural Dynamics
Date Day Evening Night Day Evening Night
Monday-03-November-2014 - 32.8 30.5 - 46.0 40.4
Tuesday-04-November-2014 32.7 32.7 32.1 57.0 47.8 45.3
Wednesday-05-November-2014 - 33.0 32.3 - 42.6 43.5
Thursday-06-November-2014 33.7 36.0 32.8 45.8 48.9 44.1
Friday-07-November-2014 32.6 37.5 32.9 45.6 49.0 46.1
Saturday-08-November-2014 32.8 33.3 32.7 45.7 48.0 45.8
Sunday-09-November-2014 - - 33.1 - - 48.0
Monday-10-November-2014 - 35.1 33.2 - 46.2 45.8
Tuesday-11-November-2014 - - - - - -
Representative Weekday 32.7 34.1 32.6 52.9 47.2 44.6
Representative Weekend 32.8 33.3 32.9 45.7 48.0 47.0Representative Week 32.7 33.3 32.8 51.9 47.3 45.3
Notes:
1. Day is taken to be 7:00am to 6:00pm 4. Rating Background Level (RBL) for L90 and logarithmic average for Leq
2. Evening is taken to be 6:00pm to 10:00pm. 5. Assessment Background Level (ABL)
3. Night is taken to be the remaining periods. 6. Rating Background Level (RBL) for L90 and logarithmic average for Leq
Template QTE-05B (rev 109) Sydney Logger Graphs TG264-05 4 1 1S0X (r0) M_RT03 - 67 Tallawong Rd
Rouse Hill
Background & Ambient Noise Monitoring Results - NSW 'Industrial Noise Policy', 2000
LA90 Background Noise Levels5 LAeq Ambient Noise Levels
AcousticsVibration
Structural Dynamics
RENZO TONIN & ASSOCIATES 18 JULY 2016
NORTHWEST RAPID TRANSIT
TG264-05 8F01 (R7) SSI 5931 ONVR [NWRLOTS-NRT-RTF-AV-RPT-
105005-E] 63
SYDNEY METRO TRAIN FACILITY (SMTF) - SSI 5931 ONVR
NWRLOTS-NRT-RTF-AV-RPT-105005-E
APPENDIX E SMTF noise and vibration design measures
Table E1: SMTF Operations
Early morning Shoulder Day Evening Night
Area Operation Details / Source location 4am to 5am 5am to 7am 7am - 10am 10am - 12pm 12pm-6pm 6pm-8pm 8pm to 10pm 10pm-2am 2am to 4amStabling Train preparation • Commences approx. 20 minutes prior to departure.
• Conducted by remote control from the Administration Building.
• Compressor on 5min for first 15min
• HVAC on med cooling during day and vent/heating at other times
• Door tests with chimes disabled - will not generate noise
• Air reservoir pipe (not vented)
5 trains 5 trains - - 5 trains - - - 2 trains (in TMF)
Stabling Train awaiting departure • Following 20 minute departure.
• Compressor off
• HVAC on low cooling during day and vent/heating at other times
No additional
trains from
startup
2 trains 2 trains
Stabling Train departing Train travelling at slow speed/ Stabling Yard neck (average 15km/h)
Controlled by train systems sources
2 5 - - 5 - - - 2
Stabling Train arriving Train travelling at slow speed/ Stabling Yard neck (average 15km/h)
Controlled by train systems sources
- - 5 - - 6 - 2 -
Stabling Train cleaning (internal) • Services take up to one hour per train set
• Trains will be cleaned:
- At the end of the morning peak;
- At the end of the evening peak;
- Once all trains have returned at night
• Up to nine trains being cleaned at one time.
• HVAC on low cooling during day and heat/vent other times.
- - - 9 trains - - 9 trains - 9 trains
Stabling Horn sounding • Provided for emergency use only. Not used for standard operations. 0 0 0 0 0 0 0 0 0
Graffiti and Biocleaning Cleaning • Irregular and intermitent activity.
• Limit to day and evening period.
0 0 1 1 1 1 1 0 0
Maintenance Corrective & Preventative • 4 roads occupied, no compressor, HVAC on vent
• All eastern doors open during the day period (7am to 6pm), otherwise
doors closed except during train entry/egress. Single door open during other
periods.
• It is recommended that doors remain closed wherever practical for noise
management.
- 4 trains 4 trains 4 trains 4 trains 4 trains 4 trains 4 trains 4 trains
Maintenance Corrective & Preventative Impact wrench
- Ingersoll-Rand 8049 operating in maintenance area
- 2 2 2 2 2 2 2 2
Maintenance Train moving • Train Warning Alarm
- 2 x BBS-107 per road (1 train entering in 15 min period)
- Ambient noise sensing. Noise level no more than 15dB(A) above ambient
noise level.
- On 5min in 15min period while train arriving/ departing shed
2 2 2 2 2 2 2 2 2
Maintenance Heavy cleaning • One road only
• Door to cleaning road closed
- - 1 1 1 1 1 - -
Maintenance Internal loading general • Forklift
- Maximum 5 tonne, operating in maintenance area
- Broadband reverse alarm (quacker)
1 1 1 1 1 1 1 1 1
Maintenance Train Lifting Equipment
(TLE)
• 1 per road (assumed 1 operating in 15 min period) 1 1 1 1 1 1 1 1 1
Maintenance Loading dock truck Loading dock sources identified below:
• Truck (semi-trailer) delivery
- External movements between gate and Maintenance building
• Truck park inside building
- - 1 1 1 1 1 - -
Maintenance Loading dock forklift • Forklift
- Maximum 5 tonne, operating in maintenance area
- Broadband reverse alarm (quacker)
- - 1 1 1 1 1 - -
Maintenance General lifting • Crane (electric)
- Flashing light warning only, no alarm siren
1 1 1 1 1 1 1 1 1
No. of source events/items per typical worst-case 15-minute period
Report ref: NWRLOTS-NRT-RTF-AV-RPT-105005-E
18/07/2016 E1 - Operations: Page 1 of 19 TG264-05 5 2 01 (r21b) RTRF Design Matrices (SMTF ONVR E)
Early morning Shoulder Day Evening Night
Area Operation Details / Source location 4am to 5am 5am to 7am 7am - 10am 10am - 12pm 12pm-6pm 6pm-8pm 8pm to 10pm 10pm-2am 2am to 4am
No. of source events/items per typical worst-case 15-minute period
Maintenance Roof chiller/VRVs/CRAC
Noise reduction based on
50*log relationship with
conservative correction
For a design day the typical loads peaking at up to 100% at 2PM and minimum
of 30% at 6 AM are :
- 0-20% zero
- 20-40% 11hrs
- 40-60%6hrs
- 60-80% 8hrs
- 80-100% 2 hrs
40% (-15dB) 40% (-15dB) 60% (-8dB) 80% (-3dB) 80-100% 80% (-3dB) 60% (-8dB) 40% (-15dB) 40% (-15dB)
Train wash Train wash plant • In use 7:00am to 3:00pm; 7:00pm to 10:00pm, 7 days/ week
• Train Wash specification: the noise level emitted from the TWP while
operating under the worst conditions shall not exceed 75 dB(A) when measured
at a distance of 1 metre from any part of the Train Wash. This includes blowers
to dry train after washing and does not include the noise reduction provided by
the enclosure.
- - 1 1 1 1 1 - -
Wheel lathe Under floor wheel lathe
(UFWL) (8 hours per day)
• 8 hours, 7 days during Initial operations (7am - 11pm at Ultimate design)
• Wheel Lathe specification: the noise level emitted from the Wheel Lathe
under all working conditions shall not exceed 80 dB(A) when measured at a
level of 1.5 m above floor level and at any point 3 m away from the Wheel Lathe
- - 1 1 1 1 1 - -
Wheel lathe Train Shunter • Electric Locomotive Train Shunter (details to be provided) - - 1 1 1 1 1 1 -
Infra Workshop and Rail
Store
Intermittent sources • Assumed day use only - - Y Y Y - - - -
Admin building Car park • Light vehicles arriving or departing car park 30 30 30 30 30 30 30 30 30
Admin building Mechanical - ac related
equip.
For a design day the typical loads peaking at up to 100% at 2PM and minimum
of 30% at 6 AM are :
- 0-20% zero
- 20-40% 11hrs
- 40-60%6hrs
- 60-80% 8hrs
- 80-100% 2 hrs
40% (-15dB) 40% (-15dB) 60% (-8dB) 80% (-3dB) 80-100% 80% (-3dB) 60% (-8dB) 40% (-15dB) 40% (-15dB)
Bulk supply point Transformer 60MVA power transformer 1 1 1 1 1 1 1 1 1Bulk supply point Harmonic filters TBC TBC TBC TBC TBC TBC TBC TBC TBC TBCDist and traction sub Power transformers Traction substation external bay 2 2 2 2 2 2 2 2 2Dist and traction sub 15MVA 33/11kV
Transformer
Traction substation external bay 1 1 1 1 1 1 1 1 1
Dist and traction sub 0.65kVA 11/400V
Transformer
Traction substation external bay 1 1 1 1 1 1 1 1 1
Dist and traction sub Reactor Traction substation external bay 1 1 1 1 1 1 1 1 1Dist and traction sub Harmonic filters Located inside substation building. - - - - - - - - -Pad mount substations LWA BLG Kiosk K3 • 11/0.4kV
• Located north of Maintenance building
1 1 1 1 1 1 1 1 1
Pad mount substations WORKSHOP Kiosk K4 • 11/0.4kV
• Located east of Workshop building
1 1 1 1 1 1 1 1 1
Pad mount substations ADMIN SERVICES Kiosk K1 • 11/0.4kV
• Located in Administration Services
2 2 2 2 2 2 2 2 2
Pad mount substations ADMIN SERVICES Isolating
transformer
• Located in Administration Services area 1 1 1 1 1 1 1 1 1
18/07/2016 E1 - Operations: Page 2 of 19 TG264-05 5 2 01 (r21b) RTRF Design Matrices (SMTF ONVR E)
Table E2: SMTF MEP Equipment Data
MEP SPECIFICATION NOISE LEVEL REQUIREMENTS
MEP Design ID Item DescriptionAir flow
L/sStatic pressure Pa
Duty/
StandbyLocation Serving Brand Model No.
Sound level
descriptionLp dB(A)*
Maximum LW
dB(A)
63Hz
(LwZ)
125Hz
(LwZ)
250Hz
(LwZ)
500Hz
(LwZ)
1kHz
(LwZ)
2kHz
(LwZ)
4kHz
(LwZ)
8kHz
(LwZ)
CH-RTF-AD2-01 Air Cooled Chiller - Screw
compressor
Full Load Duty 01L2001 PLANT Carrier 30XA0352-A 75 @ 1m 95 96 95 92 91 84 79
HP-RTF-AD2-01 Hot Water Heat Pump Full Load @ 160 Duty 01L2001 PLANT Carrier 30RQSY160A Outlet Ducted 90 94 93 87 85 81 73
Radiated + Inlet 73 @ 1m 90 91 90 88 85 82 75
CHWP-RTF-AD2-01&02 Chilled Water Pump 14 300000 1 x Duty,
1 x Standby
01L2001 PLANT CH-RTF-AD2-01 Grundfos CUE 5.5kW Motor fan 65 @ xm
HHWP-RTF-AD2-01&02 Hot Water Pump 3.5 300000 1 x Duty,
1 x Standby
01L2001 PLANT HP-RTF-AD2-01 Grundfos CUE 3kW Motor fan 60 @ xm
TEF-RTF-AD2-01 Main Toilet Exhaust Fan 1495 100 Duty 01L2001 PLANT 01GL042 WCM
01GL043 WCF
01GL044 AWC
01GL047 CLNRS CPD.
01L1046 WCM
01L1047 WCF
01L1048 AWC
01L1054 CLNRS CPD
Fantech AP series ducted fan
AP0564AP5/14
Inlet 57 @ 3m 78 79 81 76 75 73 70 67 56
Outlet 60 @ 3m 80 78 85 76 76 75 73 70 63
EF-RTF-AD2-03 Minor Exhaust Fans 200 70 Duty 01L2001 PLANT 01GL038 RECYCLABLES Fantech TD-800/200SIL Inlet 40 @ 3m 61 50 51 57 55 58 53 48 43
Outlet 40 @ 3m 61 63 61 63 56 55 53 49 43
EF-RTF-AD1-05 Minor Exhaust Fans 400 70 Duty 01L1028 UTILITY 01L1028 UTILITY Fantech MMD356/2 Inlet 45 @ 3m 65 67 69 64 61 60 58 55 45
Outlet As inlet
EF-RTF-AD1-06 Minor Exhaust Fans 400 70 Duty 01L1029 UTILITY 01L1029 UTILITY Fantech MMD356/2 Inlet 45 @ 3m 65 67 69 64 61 60 58 55 45
Outlet As inlet
EF-RTF-AD2-07 Minor Exhaust Fans 40 70 Duty 01L2001 PLANT 01L1059 CLEANER Fantech JCE152-3SJK Inlet 29 @ 3m 50 0 48 46 42 44 46 31 17
Outlet As inlet
AHU-RTF-AD2-01 Air Handling Unit 1150 250 Duty 01L2001 PLANT Carrier 39CQM In-duct INLET 87 76 82 81 83 84 80 75 70
In-duct OUTLET 88 87 87 83 83 84 80 75 70
AIRBORNE 78 76 77 70 74 75 69 47 70
AHU-RTF-AD2-02 Air Handling Unit 2850 250 Duty 01L2001 PLANT Carrier 39CQM In-duct INLET 90 83 86 85 89 85 81 75 68
In-duct OUTLET 90 94 91 87 89 85 81 75 68
AIRBORNE 81 83 81 74 80 76 70 47 68
AHU-RTF-AD2-03 Air Handling Unit 2400 250 Duty 01L2001 PLANT Carrier 39CQM In-duct INLET 88 82 84 83 88 83 78 72 66
In-duct OUTLET 88 93 89 85 88 83 78 72 66
AIRBORNE 79 82 79 72 79 74 67 44 66
OU-RTF-AD2-01 DX split Outdoor Units Duty 01GL054 CONDENSERS ROOM CA-RTF-ADG-01 Daikin RXS25 DX split outdoor unit
RKS25K3V1B
Cooling 46 @ 1m 63 63 64 64 61 58 52 46 47
Heating 47 @ 1m 64 67 68 65 62 60 54 47 39
VOU-RTF-ADG-01 Duty 01GL054 CONDENSERS ROOM CA-RTF-ADG-02
CA-RTF-ADG-03
CA-RTF-ADG-04
CA-RTF-ADG-05
FCU RTF ADG 24
Daikin REYQ10PY1 Cooling 58 @ 1m 74 77 78 76 73 68 62 59 52
EF-RTF-AD2-01&02 System Equipment Gas
Suppression Exhaust Fan
1145 100 1 x Duty,
1 x Standby
01L2001 PLANT 01GL052 SYSTEMS EQUIP Fantech AP series ducted fan
AP0504AP5/16
Inlet 59 @ 3m 80 75 79 73 76 75 73 68 59
Outlet 60 @ 3m 81 74 76 80 74 77 73 68 64
TEF-RTF-ADG-02 Minor Toilet Exhaust Fan 120 70 Duty 01GL012 CORR 01GL009 WC
01GL010 AWC
Fantech TD-500/150SIL Inlet 40 @ 3m 60 51 49 57 59 55 53 45 43
Outlet 41 @ 3m 62 61 51 62 61 57 49 43 39
EF-RTF-ADG-10&11 Minor Exhaust Fans 2640-530 150 1 x Duty,
1 x Standby
01GL017 CORR 01GL025 UPS
01GL027 SWITCHROOM
Fantech AP0564GP6/25 Inlet 56 @ 3m 76 77 79 71 72 72 69 66 58
Outlet 57 @ 3m 78 77 80 72 74 74 69 67 60
EF-RTF-ADG-12&13 Minor Exhaust Fans 100 100 1 x Duty,
1 x Standby
01GL019 GAS SUPPRESS 01GL019 GAS SUPPRESS Fantech TD-500/150 Inlet 39 @ 3m 59 0 48 56 57 54 53 45 38
Outlet As inlet
OAF-RTF-ADG-05 Outside air fans 20 Duty 01GL007 OCC MAN. CA-RTF-ADG-04 Fantech JCE152-3SJK Inlet 29 @ 3m 50 0 48 46 42 44 46 31 17
Outlet As inlet
OAF-RTF-ADG-06 Outside air fans 40 Duty 01GL006 INCIDENT MAN. CA-RTF-ADG-05 Fantech TD-800/200N Inlet 40 @ 3m 60 0 51 63 54 54 54 49 40
Outlet As inlet
OAF-RTF-ADG-07 Outside air fans 100 Duty 01GL014 OCC MEET FCU-RTF-ADG-24 Fantech TD-800/200N Inlet 40 @ 3m 60 0 51 63 54 54 54 49 40
Outlet As inlet
OAF-RTF-ADG-08 Outside air fans 20 Duty 01GL013 OCC OFFICE CA-RTF-ADG-02 Fantech JCE152-3SJK Inlet 29 @ 3m 50 0 48 46 42 44 46 31 17
Outlet As inlet
OAF-RTF-ADG-09 Outside air fans 50 Duty 01GL008 OCC STAFF KITCHEN CA-RTF-ADG-03 Fantech TD-500/150 Inlet 39 @ 3m 59 0 48 56 57 54 53 45 38
Outlet As inlet
SAF-RTF-ADG-01&02 Lift ventilation 0.26m3/s 100 1 x Duty,
1 x Standby
01GL041 TRAINING 1 01GL045 LIFT
01L1049 LIFT
Fantech PCE356ER Inlet 44 @ 3m 64 67 65 64 62 57 57 53 45
SAF-RTF-ADG-03&04 UPS & Switchroom ventilation 2640-530 50 1 x Duty,
1 x Standby
In the corridor outside
01GL016 CALL CENTRE
01GL025 UPS
01GL027 SWITCHROOM
Fantech AP0564GP6/25 Inlet 56 @ 3m 76 77 79 71 72 72 69 66 58
Outlet 57 @ 3m 78 77 80 72 74 74 69 67 60
MAINTENANCE BUILDING (MB)VOU-RTF-MB-01 VRF OUTDOOR UNIT Duty ROOF PLATFORM GRIDS 04 TO
06
CA-RTF-MB-01, 02, 03, 04, 05, 06
& 07
Daikin REYQ8PY1 58 @ 1m 74 76 78 77 72 68 61 59 53
VOU-RTF-MB-02 VRF OUTDOOR UNIT Duty ROOF PLATFORM GRIDS 04 TO
06
FCU-RTF-MB-01, 02 & 03 Daikin REYQ14PY1 62 @ 1m 78 82 80 79 75 73 69 62 60
VOU-RTF-MB-03 VRF OUTDOOR UNIT Duty ROOF PLATFORM GRIDS 04 TO
06
FCU-RTF-MB-04, 05, 06, 07, 08,
09 & 10
Daikin REYQ34PY1 63 @ 1m 83 80 80 79 73 68 62 55 49
Report ref: NWRLOTS-NRT-RTF-AV-RPT-105005-E
18/07/2016 E2 - MEP Equipment: Page 3 of 19 TG264-05 5 2 01 (r21b) RTRF Design Matrices (SMTF ONVR E)
MEP SPECIFICATION NOISE LEVEL REQUIREMENTS
MEP Design ID Item DescriptionAir flow
L/sStatic pressure Pa
Duty/
StandbyLocation Serving Brand Model No.
Sound level
descriptionLp dB(A)*
Maximum LW
dB(A)
63Hz
(LwZ)
125Hz
(LwZ)
250Hz
(LwZ)
500Hz
(LwZ)
1kHz
(LwZ)
2kHz
(LwZ)
4kHz
(LwZ)
8kHz
(LwZ)
VOU-RTF-MB-04 VRF OUTDOOR UNIT Duty GRD FLR ELECTRICAL
WORKSHOP PLANT
CA-RTF-MB-09 & 10 Daikin RXYMQ4AV4A Cooling 50 @ 1m 78 82 80 79 75 73 69 62 60
Heating 52 @ 1m 74 76 78 77 72 68 61 59 53
VOU-RTF-MB-05 VRF OUTDOOR UNIT Duty GRD FLR ELECTRICAL
WORKSHOP PLANT
FCU-RTF-MB-11, 12 & 13 Daikin RXYQ10TY1A 57 @ 1m 59 62 63 61 58 53 47 40 31
VOU-RTF-MB-06 VRF OUTDOOR UNIT Duty ROOF PLATFORM GRIDS 04 TO
06
Daikin REYQ8PY1 58 @ 1m 74 76 78 77 72 68 61 59 53
VOU-RTF-MB-07 VRF OUTDOOR UNIT Duty ROOF PLATFORM GRIDS 04 TO
06
Daikin REYQ8PY1 58 @ 1m 74 76 78 77 72 68 61 59 53
OU-RTF-MB-01&02 DX Outdoor Unit 1 x Duty,
1 x Standby
IU-RTF-MB-01 Daikin RXM46PVMA P-Series Cooling (H/SL) 47/44 @ 1m
Heating (H/SL) 48/45 @ 1mOU-RTF-MB-03&04 DX Outdoor Unit 1 x Duty,
1 x Standby
IU-RTF-MB-03 Daikin RXM50PVMA P-Series Cooling (H/SL) 47/44 @ 1m
Heating (H/SL) 48/45 @ 1mCOU-RTF-MB-01&02 Data Room Air Conditioner 99.8 1 x Duty,
1 x Standby
ROOF PLATFORM GRIDS 04 TO
06
CRAC-RF-MB-01 &02 Liebert LDF76 1 off Vmax setting 81 86 84 85 87 82 80 77 74 72
AHU-RTF-MB-01 Air Handling Unit 4000 Duty Main Depot Carrier 39 G Galaxy 1319 85RCHP-RTF-MB-01 Air Cooled Reverse Cycle Duty AHU-RTF-MB-01 AHI Carrier 30RQSY160A Outlet Ducted 90 94 93 87 85 81 73
Radiated + Inlet 73 @ 1m 90 91 90 88 85 82 75OAF-RTF-MB-01 Outdoor Air Supply Fan 90 100 Duty 4006 DUTY AND SUPERVISOR
OFFICE
Fantech TD-800/200N Inlet 40 @ 3m 60 51 63 54 54 54 49 40
OAF-RTF-MB-02 Outdoor Air Supply Fan 145 100 Duty 4007 DCC Fantech TD-800/200SIL Lo speed Inlet 40 @ 3m 61 50 51 57 55 58 53 48 43Outlet 40 @3m 61 63 61 63 56 55 53 49 43Outlet 41 @ 3m 62 61 51 62 61 57 49 43 39
OAF-RTF-MB-05 Outdoor Air Supply Fan 20 100 Duty 4004 FIRST AID Fantech JCE152-3SJK Lo speed Inlet 29 @ 3m 50 48 46 42 44 46 31 17OAF-RTF-MB-06 Outdoor Air Supply Fan 120 100 Duty 4112 MEET 1 Fantech TD-500/150SIL Hi speed Inlet 40 @ 3m 60 51 49 57 59 55 53 45 43
Outlet 41 @ 3m 62 61 51 62 61 57 49 43 39OAF-RTF-MB-07 Outdoor Air Supply Fan 120 100 Duty 4111 MEET 2 Fantech TD-500/150SIL Hi speed Inlet 40 @ 3m 60 51 49 57 59 55 53 45 43
Outlet 41 @ 3m 62 61 51 62 61 57 49 43 39OAF-RTF-MB-08 Outdoor Air Supply Fan 50 100 Duty 4119 KITCHEN Fantech TD-500/150 Lo speed Inlet 39 @ 3m 59 48 56 57 54 53 45 38OAF-RTF-MB-09 Outdoor Air Supply Fan 300 100 Duty 4120 DINING Fantech TD-1300/250SIL Hispeed Inlet 47 @ 3m 67 58 59 71 63 61 59 55 52
Outlet 53 @ 3m 74 56 62 70 72 71 62 51 48Breakout 35 @ 3m 56 54 48 57 46 54 46 36 38
OAF-RTF-MB-10 Outdoor Air Supply Fan 80 100 Duty 4117 OFFICE 7P Fantech TD-800/200N Lo speed Inlet 40 @ 3m 60 51 63 54 54 54 49 40OAF-RTF-MB-11 Outdoor Air Supply Fan 240 100 Duty 4118 MAINTENANCE OFFICE Fantech TD-1300/250SIL Lo speed Inlet 42 @ 3m 63 61 56 66 59 56 54 50 47
Outlet 49 @ 3m 69 55 60 66 68 66 56 46 42Breakout 31 @ 3m 52 55 48 51 43 50 41 31 33
OAF-RTF-MB-12 Outdoor Air Supply Fan 100 100 Duty 4110 CORRIDOR Fantech TD-500/150SIL Hi speed Inlet 40 @ 3m 60 51 49 57 59 55 53 45 43Outlet 41 @ 3m 62 61 51 62 61 57 49 43 39
OAF-RTF-MB-13 Outdoor Air Supply Fan 50 100 Duty 4040 RS & STC ELEC WKS Fantech TD-500/150 Lo speed Inlet 39 @ 3m 59 48 56 57 54 53 45 38OAF-RTF-MB-14 Outdoor Air Supply Fan 50 100 Duty 4043 OH & POW WK Fantech TD-500/150 Lo speed Inlet 39 @ 3m 59 48 56 57 54 53 45 38OAF-RTF-MB-15 Outdoor Air Supply Fan 50 100 Duty 4044 ST & TUN WK/ST Fantech TD-500/150 Lo speed Inlet 39 @ 3m 59 48 56 57 54 53 45 38OAF-RTF-MB-18 Outdoor Air Supply Fan 20 100 Duty 4113 ROLLING STOCK
MANAGER
Fantech JCE152-3SJK Lo speed Inlet 29 @ 3m 50 48 46 42 44 46 31 17
OAF-RTF-MB-19 Outdoor Air Supply Fan 20 100 Duty 4114 POWER SUPPLY
MANAGER
Fantech JCE152-3SJK Lo speed Inlet 29 @ 3m 50 48 46 42 44 46 31 17
OAF-RTF-MB-20 Outdoor Air Supply Fan 20 100 Duty 4115 SIGNALS & COMMS
MANAGER
Fantech JCE152-3SJK Lo speed Inlet 29 @ 3m 50 48 46 42 44 46 31 17
OAF-RTF-MB-21 Outdoor Air Supply Fan 20 100 Duty 4116 STATION BASE MANAGER Fantech JCE152-3SJK Lo speed Inlet 29 @ 3m 50 48 46 42 44 46 31 17
OAF-RTF-MB-22 Outdoor Air Supply Fan 20 100 Duty 4170 EMU Fantech JCE152-3SJK Lo speed Inlet 29 @ 3m 50 48 46 42 44 46 31 17OAF-RTF-MB-23 Outdoor Air Supply Fan 20 100 Duty 4009 OFF IP Fantech JCE152-3SJK Lo speed Inlet 29 @ 3m 50 48 46 42 44 46 31 17OAF-RTF-MB-24 Outdoor Air Supply Fan 80 100 Duty 4010 OFF 8 SIGNALS Fantech TD-800/200N Lo speed Inlet 40 @ 3m 60 51 63 54 54 54 49 40OAF-RTF-MB-25 Outdoor Air Supply Fan 80 100 Duty 4011 OFF 8 P OH&P Fantech TD-800/200N Lo speed Inlet 40 @ 3m 60 51 63 54 54 54 49 40OAF-RTF-MB-26&27 Outdoor Air Supply Fan 120 100 1 x Duty,
1 x Standby
4057 SIGNAL
COMMUNICATIONS
Fantech TD-500/150SIL Hi speed Inlet 40 @ 3m 60 51 49 57 59 55 53 45 43
Outlet 41 @ 3m 62 61 51 62 61 57 49 43 39TEF-RTF-MB-01 EXHAUST FAN 350 70 Duty GL WCF AWC WCM Fantech TD2P800/200N Inlet 51 @ 3m 72 63 74 65 65 67 60 52TEF-RTF-MB-02 EXHAUST FAN 1730 70 Duty L1 F CH RM, M CH RM, CLN ST Fantech AP0504AP5B003 Inlet 58 @ 3m 79 78 77 74 75 74 72 69 57
Outlet 57 @ 3m 78 78 75 74 71 74 71 68 58TEF-RTF-MB-03 EXHAUST FAN 70 70 Duty 02GL025 UNISEX Fantech TD-500/150 Lo speed Inlet 39 @ 3m 59 48 56 57 54 53 45 38EF-RTF-MB-01 EXHAUST FAN 720 70 Duty 02GL057 SIGNALS
COMMUNICATION (FIRE
SUPPRESS)
Fantech APS0404AA5H005
APS0404AA5/19
Inlet 49 @ 3m 70 67 71 68 66 65 62 57 46
Outlet 50 @ 3m 71 69 72 68 67 66 64 60 52EF-RTF-MB-02 & 03 EXHAUST FAN 1320-265 150 1 x Duty,
1 x Standby
02GL048 MSB (OVER HEAT) Fantech AP0564GP6/10 Inlet 55 @ 3m 76 72 76 73 71 72 69 64 57
EF-RTF-MB-05 EXHAUST FAN 120 70 Duty 02GL043 CLEANERS STORE Fantech Unknown
(most likely TD-2000/315SIL)
Lo speed
Inlet 43 @ 3m 64 60 63 68 59 58 55 52 48
Outlet 48 @ 3m 69 60 69 69 65 66 57 43 42Breakout 33 @ 3m 54 50 56 52 47 50 46 43 37
EF-RTF-MB-06 EXHAUST FAN 40 70 Duty 02L1050 STORE Fantech TD-350/125 Lo speed Inlet 40 @ 3m 60 50 55 58 57 52 46 39EF-RTF-MB-07&08 EXHAUST FAN 60 70 1 x Duty,
1 x Standby
02GL091 GAS BOTTLE STORE Fantech TD-800/200 Lo speed Inlet 45 @ 3m 66 52 56 65 58 59 54 47
EF-RTF-MB-09&10 EXHAUST FAN 50 70 1 x Duty,
1 x Standby
02GL080 BATTERY
MAINTENANCE
02GL080 BATTERY
MAINTENANCE
Fantech TD-800/200N Lo speed Inlet 45 @ 3m 66 52 56 65 58 59 54 47
EF-RTF-MB-11 EXHAUST FAN 5180 70 Duty 02GL066 WELD SHOP EXHAUST HOOD Fantech AP0714AP5/25 Outlet 67 @ 3m 88 88 89 84 83 83 81 79 73EF-RTF-MB-12 EXHAUST FAN 360 70 Duty 02GL066 WELD SHOP WELDING FUME EXTRACTION
ARM
Fantech AP0314AP5/25 Outlet 48 @ 3m 68 71 64 63 62 65 61 56 52
EF-RTF-MB-13 EXHAUST FAN 360 70 Duty 02GL066 WELD SHOP WELDING FUME EXTRACTION
ARM
Fantech AP0314AP5/25 Outlet 48 @ 3m 68 71 64 63 62 65 61 56 52
EF-RTF-MB-15 EXHAUST FAN 1420 100 Duty 02GL082 PAINTING &
EQUIPMENT AREA
SPRAY PAINT BOOTH MN
Spraybooths
Industrial open face spray
booth
83 @ 1m 89 83 84 92 85 83 80 77 74
18/07/2016 E2 - MEP Equipment: Page 4 of 19 TG264-05 5 2 01 (r21b) RTRF Design Matrices (SMTF ONVR E)
MEP SPECIFICATION NOISE LEVEL REQUIREMENTS
MEP Design ID Item DescriptionAir flow
L/sStatic pressure Pa
Duty/
StandbyLocation Serving Brand Model No.
Sound level
descriptionLp dB(A)*
Maximum LW
dB(A)
63Hz
(LwZ)
125Hz
(LwZ)
250Hz
(LwZ)
500Hz
(LwZ)
1kHz
(LwZ)
2kHz
(LwZ)
4kHz
(LwZ)
8kHz
(LwZ)
VEF-RTF-MB-01 to 08 Ventilation Exhaust Fan (Smoke
Rated)
12500 152 Emergency use MAIN WORKSHOP Fantech RSS1006CA12/35 Inlet 68 @ 3m 89 89 84 88 87 83 80 76 70
Outlet 69 @ 3m 90 92 87 89 88 84 81 78 73VEF-RTF-MB-01 to 08 Ventilation Exhaust Fan (Smoke
Rated)
6287 38 Duty MAIN WORKSHOP Fantech RSS1006CA12/35 (25Hz) Inlet 54 @ 3m 74 73 74 77 70 68 66 63 56
Outlet 54 @ 3m 75 76 76 77 72 68 67 64 59ACFD-RTF-MB-01 AIR COMPRESSOR FILTER &
DRYER
Duty 02L1071 PLANT ROOM Champion CSF30 74 @ 1m +/- 3dBA
SAF-RTF-MB-01 & 02 SUPPLY AIR FAN 260 70 1 x Duty,
1 x Standby
CORRIDOR LIFT SHAFT Fantech AP0314AP5/17 Outlet 45 @ 3m 65 65 64 68 60 58 57 53 48
SAF-RTF-MB-03 & 04 SUPPLY AIR FAN 1320 - 265 150 1 x Duty,
1 x Standby
MSB Fantech AP0564GP6/10 Outlet 55 @ 3m 76 72 76 73 71 72 69 64 57
DANGEROUS GOODS (DG)EF-RTF-DG-01&02 EXHAUST FAN (DG RATED) 220 70 1 x Duty,
1 x Standby
DANGEROUS GOODS STORE
CHEM
DANGEROUS GOODS STORE
CHEM
Fantech AP0314AP5/14 Inlet 45 @ 3m 66 60 62 68 63 60 57 50 40
Outlet 44 @ 3m 65 65 64 68 60 58 57 53 48EF-RTF-DG-03&04 EXHAUST FAN (DG RATED) 540 70 1 x Duty,
1 x Standby
DANGEROUS GOODS STORE
NO. 1
DANGEROUS GOODS STORE NO.
1
Fantech AP0404AP5/13 Inlet 50 @ 3m 71 68 72 69 67 66 63 58 47
Outlet 51 @ 3m 72 70 73 69 68 67 65 61 53EF-RTF-DG-05&06 EXHAUST FAN (DG RATED) 220 70 1 x Duty,
1 x Standby
DANGEROUS GOODS STORE
NO. 2
DANGEROUS GOODS STORE NO.
2
Fantech AP0314AP5/14 Inlet 45 @ 3m 66 60 62 68 63 60 57 50 40
Outlet 44 @ 3m 65 65 64 68 60 58 57 53 48
INFRASTRUCTURE WORKSHOP (IW)VOU-RTF-IW-01 VRV AIR CONDITIONING UNITS
(OUTDOORS)
Duty 03GL013 AC PLANT FCU-RTF-IW-01 TO 05 Daikin RXYQ30TSY1A Combination of
RXYQ14 and 16TY1A
64 @ 1m 62 64 64 63 60 57 51 44 37
OU-RTF-IW-01 OUTDOOR UNIT (HOLD) Duty IU-RTF-IW-01 Daikin RXM46PVMA Heating 48 @ 1m 63 71 68 63 60 59 52 45 37TEF-RTF-IW-01 EXHAUST FAN 805 100 Duty 03GL009 WC/SH/CH-M 03GL005 AWC
03GL007 WC/SH/CH-F
03GL009 WC/SH/CH-M
Fantech PCD456ER Inlet 46 @ 3m 67 77 76 67 64 59 57 55 51
EF-RTF-IW-01&02 EXHAUST FAN (DG RATED) 100 50 1 x Duty,
1 x Standby
03GL022 DNGR GOODS 1 03GL022 DNGR GOODS 1 Fantech AP0314AP5/10 Inlet 45 @ 3m 66 60 62 68 63 60 57 50 40
Outlet 44 @ 3m 65 65 64 68 60 58 57 53 48ACFD-RTF-IW-01 AIR COMPRESSOR FILTER &
DRYER
Duty 03GL019 MAIN STR 03GL019 MAIN STR Champion CSF15 67 @ 1m
RAIL STORE (RS)EF-RTF-RS-01&02 EXHAUST FAN (DG RATED) 100 50 Duty 04GL003 DANGEROUS GOODS
STORE
04GL003 DANGEROUS GOODS
STORE
Fantech AP0314AP5/14 Inlet 45 @ 3m 66 60 62 68 63 60 57 50 40
Outlet 44 @ 3m 65 65 64 68 60 58 57 53 48
SECURITY BUILDING (SB)OAF-RTF-SB-01 OUTDOOR AIR FAN 20 70 Duty Fantech JCE152-3SJK (Lo speed) Inlet 29 @ 3m 50 48 46 42 44 46 31 17OAF-RTF-SB-02&03 OUTDOOR AIR FAN 30 70 1 x Duty,
1 x Standby
Fantech JCE152-3SJK (Lo speed) Inlet 29 @ 3m 50 48 46 42 44 46 31 17
TEF-RTF-SB-01 TOILET EXHAUST FAN 40 20 Duty Fantech HV-150AE Inlet 37 @ 3mOU-RTF-SB-01 SPLIT OUTDOOR UNIT Duty Daikin RZQ100KCV4A Heating 53 @ 1m 68 65 72 70 65 61 56 51 45
Cooling 51 @ 1m 66 66 70 68 63 59 55 50 44OU-RTF-SB-02&03 SPLIT OUTDOOR UNIT 1 x Duty,
1 x Standby
Daikin RXM20PVMA Heating 47 @ 1m 73 77 79 75 71 67 60 58 51
Cooling 46 @ 1m 76 82 80 79 75 70 66 61 60
WHEEL LATHE (WL)OAF-RTF-WL-01 OUTDOOR AIR FAN 20 70 Duty 10GL003 OFFICE 10GL003 OFFICE Fantech JCE152-3SJK (Lo speed) Inlet 29 @ 3m 50 0 48 46 42 44 46 31 17TEF-RTF-WL-01 TOILET EXHAUST FAN 40 20 Duty 10GL004 WC 10GL004 WC Fantech HV-150AE Inlet 37 @ 3mEF-RTF-WL-01 EXHAUST FAN 1000 150 Duty 10GL001 WHEEL LATHE 10GL002 PIT Fantech AP0564AP5/14 Inlet 61 @ 3m 82 75 82 79 79 78 74 66 59
Outlet 62 @ 3m 83 77 79 79 82 76 75 72 68OU-RTF-WL-01 SPLIT OUTDOOR UNIT Duty Outside 10GL003 OFFICE to the
south
CA-RTF-WL-01 Daikin RXS25K3V1B Heating 43 @ 1m 62 68 67 64 60 57 48 44 39
Cooling 42 @ 1m 60 60 60 61 59 54 46 40 36ACFD-RTF-WL-01 AIR COMPRESSOR FILTER &
DRYER
Duty 10GL001 WHEEL LATHE 10GL001 WHEEL LATHE Champion CSF11 67 @ 1m
* - Details and conditions of sound pressure level measurements vary by manufacturer. Refer to manufacturers details.7
MEP Design ID Item DescriptionAir flow
L/s
Static pressure
Pa
Duty/
StandbyLocation Serving Brand Model No.
INSERTION LOSSno detail no detail2 63Hz 125Hz 250Hz 500Hz 1kHz 2kHz 4kHz 8kHz
Acoustic louvre Admin plant room Walls Sound
Attenuators
Australia/IAC
Acoust c
AL1H 3 7 9 13 15 16 15 14
Acoustic louvre Fire pump room pump room Sound
Attenuators
Australia/IAC
Acoustic
AL2H 8 11 16 22 27 29 27 24
18/07/2016 E2 - MEP Equipment: Page 5 of 19 TG264-05 5 2 01 (r21b) RTRF Design Matrices (SMTF ONVR E)
Table E3: SMTF Additional noise sources
SPECIFICATION DETAIL NOISE LEVEL REQUIREMENTS
Item/Area Sub Item DetailsSound level
descriptionMax Lp dB(A)*
Maximum Lw
dB(A)
63Hz
(LwZ)
125Hz
(LwZ)
250Hz
(LwZ)
500Hz
(LwZ)
1kHz
(LwZ)
2kHz
(LwZ)
4kHz
(LwZ)
8kHz
(LwZ)Train HVAC High cooling 2 x every car.
Operates 30 deg ambient and above.
External 86 83 86 88 84 81 77 71 64
Train HVAC Medium Cooling 2 x every car.
Operates 24 deg to 29 deg ambient
External 85 82 85 87 83 80 76 70 63
Train HVAC Half Cooling 2 x every car External 82 79 82 84 80 77 73 67 60
Train HVAC Low Cooling 2 x every car External 81 78 81 83 79 76 72 66 59
Train HVAC Ventilation 2 x every car.
Operates ambient temp up to 23 deg
External 78 75 78 80 76 73 69 63 56
Train HVAC Heating 2 x every car.
No louder than ventiliation mode
External 78 75 78 80 76 73 69 63 56
Train CVS 2 x set, car 1 and 6 External 83 82 80 80 78 75 66
Train APU Compressor 2 x set, car 1 and 6.
Noise level when operating
Operating for 5min in 15min period.
Spectra from A-Sets
External 92 97 91 84 90 89 82 77 76
Train Total train on MED COOLING -
No comp
96 93 97 98 94 91 87 81 74
Train Total train in VENTILATION - No
comp
91 86 91 91 88 86 82 75 67
Train Brake Pipe venting 2 x set, car 1 and 6
Venting occurs during maintenance only in
Maintenance building
External 85dB(A) @ 1m 93
Train Door tests during preparation Electonic test only
Do not generate noise
- -
Train Horn Used for emergency purpose only.
Not used for general operations and movement in the
RTRF
- -
Maintenance building Train lift When operating
To operate for 120 sec in any 15 minute period
Per lift on lifting road
75dB(A) @ 1m 83
Maintenance building Impact wrench 2 x Ingersoll -Rand 8049 90
Maintenance building Train warning alarm 2 x BBS-107 per road
Ambient noise sensing
110
Maintenance building Forklift 2 x Maximum 5 tonne with Broadband reverse alarm
(quacker)
90
Maintenance building Truck idling Steady state source - no correction for duration 96
Maintenance building Truck moving Per m/ Lw - 10km/h, LAeq15minute 68
Train wash Wash plant When operating
The noise level emitted from the TWP while operating
under the worst conditions shall not exceed 75 dB(A)
when measured at a distance of 1m from any part of
the Train Wash. This includes blowers to dry train
after washing and does not include the noise
reduction provided by the enclosure.
Reverberant field 75dB(A) @ 1m
Report ref: NWRLOTS-NRT-RTF-AV-RPT-105005-E
18/07/2016 E3 - Noise sources: Page 6 of 19 TG264-05 5 2 01 (r21b) RTRF Design Matrices (SMTF ONVR E)
SPECIFICATION DETAIL NOISE LEVEL REQUIREMENTS
Item/Area Sub Item DetailsSound level
descriptionMax Lp dB(A)*
Maximum Lw
dB(A)
63Hz
(LwZ)
125Hz
(LwZ)
250Hz
(LwZ)
500Hz
(LwZ)
1kHz
(LwZ)
2kHz
(LwZ)
4kHz
(LwZ)
8kHz
(LwZ)Wheel lathe Single head underfloor lathe The noise level emitted from the Wheel Lathe under
all working conditions shall not exceed 80 dB(A) when
measured at a level of 1.5m above floor level and at
any point 3 m away from the Wheel Lathe
Reverberant field 80dB(A) @ 3m 98
Wheel lathe Shunter Electric shunter Electric shunter
Electrical ADMIN SERVICES Kiosk K1 11/0.4kV 65 68 70 65 65 59 54 49 42
Electrical LWA BLG Kiosk K3 11/0.4kV 70 73 75 70 70 64 59 54 47
Electrical Workshop Kiosk K4 11/0.4kV 75 78 80 75 75 69 64 59 52
Electrical Admin services isolating
transformer
70 73 75 70 70 64 59 54 47
Traction substation Power transformers 2 off in external bay 62 65 67 62 62 56 51 46 39
Traction substation Transformer 1 x 15MVA 33/11kV in external bay 70 73 75 70 70 64 59 54 47
Traction substation Transformer 1 x 0.65kVA 11/400V in external bay 60 63 65 60 60 54 49 44 37
Traction substation Reactor 1 in external bay 63 66 68 63 63 57 52 47 40
Traction substation Harmonic Filters TBC
Bulk supply Transformer 60MVA power transformer
Sound power level will be 85dB (A) at no-load, 100%
Ur volts. Assumed 88 dB(A) under load.
88 91 93 88 88 82 77 72 65
Bulk supply Harmonic Filters TBC TBC
Fire pump room Electric Pump and
motor((mergency use)
45kW, IE2, 2 pole motor
NK 65-250/251 A2-F-B-E-BQQE
Case radiated 78dB(A) @ 1m 94
Fire pump room Diesel pump and motor
(Emergency use)
Motor - 43kW @ 2700RPM
Pump - NK 65-250/270 Y1-F-B-E-BQQE
Case radiated 110dB(A) @ 1m 126
Motor - 43kW @ 2700RPM
Pump - NK 65-250/270 Y1-F-B-E-BQQE
Exhaust with
attenuator
85dB(A) @ 1m 93
Backup generator Noise level specification 1m from unit 85dB(A) @ 1m
18/07/2016 E3 - Noise sources: Page 7 of 19 TG264-05 5 2 01 (r21b) RTRF Design Matrices (SMTF ONVR E)
Table E5: Noise and Vibration Requirements and Verification - SMTF MEP Mitigation measures Report ref: NWRLOTS-NRT-RTF-AV-RPT-105005-E
MEP Specification MEP NV RequirementsRelevant equipment Location Serving Case radiated noise Discharge side of unit Intake side of unitADMINISTRATION BUILDING (AD)
CH-RTF-AD2-01 01L2001 PLANT FCUs Acoustic louvres to plantroom - Refer Table E5 2.5m long, 100mm lined circular duct on each fan to roof
discharge
Acoustic louvres to plantroom - Refer Table E5
HP-RTF-AD2-01 01L2001 PLANT FCUs Acoustic louvres to plantroom - Refer Table E5 3m long, 50mm lined rectangular duct on each fan to roof
discharge
Acoustic louvres to plantroom - Refer Table E5
CHWP-RTF-AD2-01 01L2001 PLANT CH-RTF-AD2-01 Acoustic louvres to plantroom - Refer Table E5 Acoustic louvres to plantroom - Refer Table E5 Acoustic louvres to plantroom - Refer Table E5CHWP-RTF-AD2-02 (Standby) 01L2001 PLANT CH-RTF-AD2-01 Acoustic louvres to plantroom - Refer Table E5 Acoustic louvres to plantroom - Refer Table E5 Acoustic louvres to plantroom - Refer Table E5HHWP-RTF-AD2-01 01L2001 PLANT HP-RTF-AD2-01 Acoustic louvres to plantroom - Refer Table E5 Acoustic louvres to plantroom - Refer Table E5 Acoustic louvres to plantroom - Refer Table E5HHWP-RTF-AD2-02 (Standby) 01L2001 PLANT HP-RTF-AD2-01 Acoustic louvres to plantroom - Refer Table E5 Acoustic louvres to plantroom - Refer Table E5 Acoustic louvres to plantroom - Refer Table E5TEF-RTF-AD2-01 01L2001 PLANT 01GL042 WCM
01GL043 WCF
01GL044 AWC
01GL047 CLNRS CPD.
01L1046 WCM
01L1047 WCF
01L1048 AWC
01L1054 CLNRS CPD
Acoustic louvres to plantroom - Refer Table E5 Acoustic louvres to plantroom - Refer Table E5 Acoustic louvres to plantroom - Refer Table E5
EF-RTF-AD2-03 01L2001 PLANT 01GL038 RECYCLABLES Acoustic louvres to plantroom - Refer Table E5 Acoustic louvres to plantroom - Refer Table E5 Acoustic louvres to plantroom - Refer Table E5EF-RTF-AD1-05 01L1028 UTILITY 01L1028 UTILITY Locate the fan above the CAC39 ceiling tiles Provide acoustically insulated ductwork (50mm insulation)
for a minimum length of 1m
Provide acoustically insulated ductwork (50mm insulation)
for a minimum length of 1m. Provide acoustically
insulated return air plenum and cushion head. Provide
acoustically insulated circular flexible ductwork for a
minimum length of 1m.
EF-RTF-AD1-06 01L1029 UTILITY 01L1029 UTILITY Locate the fan above the CAC39 ceiling tiles Provide acoustically insulated ductwork (50mm insulation)
for a minimum length of 1m
Provide acoustically insulated ductwork (50mm insulation)
for a minimum length of 1m. Provide acoustically
insulated return air plenum and cushion head. Provide
acoustically insulated circular flexible ductwork for a
minimum length of 1m.
EF-RTF-AD2-07 01L2001 PLANT 01L1059 CLEANER Acoustic louvres to plantroom - Refer Table E5 No acoustic treatment required No acoustic treatment requiredAHU-RTF-AD2-01 01L2001 PLANT 01L1032 OFFICE SOUTH ZONE Acoustic louvres to plantroom - Refer Table E5 ATT-RTF-AD2-01 - Acoustic attenuator equivalent to
Fantech RT17E (1800mm long with 47% free area) within
the plant room. Provide acoustically insulated ductwork
(50mm insulation) for the entire length of the supply air
ductwork after the attenuator.
Install a false ceiling (solid plasterboard) above 01L1042
OFFICE. REASON: duct breakout noise in 01L1042 OFFICE.
Provide acoustically insulated ductwork (50mm insulation)
for the entire length. Provide acoustically insulated
cushion head. Provide acoustically insulated circular
flexible ductwork for a minimum length of 1m.
AHU-RTF-AD2-02 01L2001 PLANT 01L1032 OFFICE CENTRAL ZONE Acoustic louvres to plantroom - Refer Table E5 ATT-RTF-AD2-02 - acoustic attenuator equivalent to
Fantech RT22F (2100mm long with 53% free area) within
radial bend inside the plant room. Provide acoustically
insulated ductwork (50mm insulation) for the entire
length of the supply air ductwork after the attenuator.
Provide acoustically insulated circular flexible ductwork
for a minimum length of 2m.
A solid plasterboard is to be added with a gap of a
minimum 100mm from the secondary ceiling type CL-306.
REASON: duct breakout noise in 01L1001 LOBBY. (refer
Table E5)
Provide acoustically insulated ductwork (50mm insulation)
for the entire length. Provide acoustically insulated
cushion head. Provide acoustically insulated circular
flexible ductwork for a minimum length of 1m.
Encase return air ductwork above Boardroom with 13mm
plasterboard, independant from duct and internally lined
with bulk insulation.
18/07/2016 E4 - MEP mitigation: Page 8 of 19 TG264-05 5 2 01 (r21b) RTRF Design Matrices (SMTF ONVR E)
MEP Specification MEP NV RequirementsRelevant equipment Location Serving Case radiated noise Discharge side of unit Intake side of unitAHU-RTF-AD2-03 01L2001 PLANT 01L1032 OFFICE NORTH ZONE Acoustic louvres to plantroom - Refer Table E5 Install acoustic attenuator Fantech RT17D (1500mm long
with 47% free area) within the plant room. Provide
acoustically insulated ductwork (50mm insulation) for the
entire length of the supply air ductwork after the
attenuator. Install second ceiling (solid plasterboard) to
cover all services above 01L1044 INT 1. Minimum 100mm
above finished ceiling. REASON: duct breakout noise in
01L1044 INT 1. (refer Table E5)
Provide acoustically insulated ductwork (50mm insulation)
for the entire length. Provide acoustically insulated
cushion head. Provide acoustically insulated circular
flexible ductwork for a minimum length of 1m.
COU-RTF-ADG-01 01GL054 CONDENSERS ROOM CRAC-RTF-ADG-01
CRAC-RTF-ADG-02
Refer ARCH details in Table E5 Refer ARCH details in Table E5 Refer ARCH details in Table E5
COU-RTF-ADG-02 01GL054 CONDENSERS ROOM CRAC-RTF-ADG-01
CRAC-RTF-ADG-02
Refer ARCH details in Table E5 Refer ARCH details in Table E5 Refer ARCH details in Table E5
COU-RTF-ADG-03 01GL054 CONDENSERS ROOM CRAC-RTF-ADG-03
CRAC-RTF-ADG-04
Refer ARCH details in Table E5 Refer ARCH details in Table E5 Refer ARCH details in Table E5
COU-RTF-ADG-04 01GL054 CONDENSERS ROOM CRAC-RTF-ADG-03
CRAC-RTF-ADG-04
Refer ARCH details in Table E5 Refer ARCH details in Table E5 Refer ARCH details in Table E5
OU-RTF-AD2-01 01GL054 CONDENSERS ROOM CA-RTF-ADG-01 Refer ARCH details in Table E5 Refer ARCH details in Table E5 Refer ARCH details in Table E5VOU-RTF-ADG-01 01GL054 CONDENSERS ROOM CA-RTF-ADG-02
CA-RTF-ADG-03
CA-RTF-ADG-04
CA-RTF-ADG-05
FCU RTF ADG 24
Refer ARCH details in Table E5 Refer ARCH details in Table E5 Refer ARCH details in Table E5
EF-RTF-AD2-01 01L2001 PLANT 01GL052 SYSTEMS EQUIP Locate the fan above the CAC39 ceiling tiles Provide acoustically insulated ductwork (50mm insulation)
for a minimum length of 2m
Provide acoustically insulated ductwork (50mm insulation)
for a minimum length of 2mEF-RTF-AD2-02 (Standby) 01L2001 PLANT 01GL052 SYSTEMS EQUIP Locate the fan above the CAC39 ceiling tiles Provide acoustically insulated ductwork (50mm insulation)
for a minimum length of 2m
Provide acoustically insulated ductwork (50mm insulation)
for a minimum length of 2mTEF-RTF-ADG-02 01GL012 CORR 01GL009 WC
01GL010 AWC
Locate the fan above the CAC39 ceiling tiles No acoustic treatment required Provide acoustically insulated ductwork (50mm insulation)
for a minimum length of 1m to each air grilles
EF-RTF-ADG-10 01GL017 CORR 01GL025 UPS
01GL027 SWITCHROOM
Locate the fan inside swithroom. Operate on VSD. Provide 1m of 50mm internaly lined duct
to intake side before lined plenum.
Operate on VSD. Provide acoustically insulated ductwork
(50mm insulation) from fan to first inlet (2m).
EF-RTF-ADG-11 (Standby) 01GL017 CORR 01GL025 UPS
01GL027 SWITCHROOM
Locate the fan inside swithroom. Operate on VSD. Provide 1m of 50mm internaly lined duct
to intake side before lined plenum.
Operate on VSD. Provide acoustically insulated ductwork
(50mm insulation) from fan to first inlet (2m).
EF-RTF-ADG-12 01L1019 GAS SUPPRESS 01L1019 GAS SUPPRESS No acoustic treatment required No acoustic treatment required No acoustic treatment requiredEF-RTF-ADG-13 (Standby) 01L1019 GAS SUPPRESS 01L1019 GAS SUPPRESS No acoustic treatment required No acoustic treatment required No acoustic treatment requiredOAF-RTF-ADG-01 01GL022 OCC MECH CRAC-RTF-ADG-01 No acoustic treatment required No acoustic treatment required No acoustic treatment requiredOAF-RTF-ADG-02 (Standby) 01GL022 OCC MECH CRAC-RTF-ADG-02 No acoustic treatment required No acoustic treatment required No acoustic treatment requiredOAF-RTF-ADG-05 01GL007 OCC MAN. CA-RTF-ADG-04 Locate the fan above the CAC39 ceiling tiles Provide acoustically insulated circular flexible ductwork
for a minimum length of 1m
No acoustic treatment required
OAF-RTF-ADG-06 01GL006 INCIDENT MAN. CA-RTF-ADG-05 Locate the fan above the CAC39 ceiling tiles Provide acoustically insulated ductwork (50mm insulation)
for a minimum length of 1m. Provide acoustically
insulated circular flexible ductwork for a minimum length
of 2m
No acoustic treatment required
OAF-RTF-ADG-07 01GL014 OCC MEET FCU-RTF-ADG-24 Locate the fan inside OCC MECH No acoustic treatment required No acoustic treatment requiredOAF-RTF-ADG-08 01GL013 OCC OFFICE CA-RTF-ADG-02 Locate the fan above the CAC39 ceiling tiles Provide acoustically insulated circular flexible ductwork
for a minimum length of 1m
No acoustic treatment required
OAF-RTF-ADG-09 01GL008 OCC STAFF KITCHEN CA-RTF-ADG-03 Locate the fan above the CAC39 ceiling tiles Provide acoustically insulated circular flexible ductwork
for a minimum length of 1m
No acoustic treatment required
SAF-RTF-ADG-01 & 02 01GL041 TRAINING 1 01GL045 LIFT
01L1049 LIFT
Locate the fan above the CAC39 ceiling tiles. Provide acoustically insulated ductwork (50mm insulation)
to all duct work from fan to lift shaft.
Provide acoustically insulated ductwork (50mm insulation)
to all duct work and return plenum.
SAF-RTF-ADG-03 In the corridor outside 01GL016 CALL
CENTRE
01GL025 UPS
01GL027 SWITCHROOM
Locate the fan above the CAC39 ceiling tiles Operate on VSD. Provide acoustically insulated ductwork
(50mm insulation) from fan to first supply grill (4m).
Operate on VSD. Provide 1m of 50mm internaly lined duct
to intake side before lined plenum.
SAF-RTF-ADG-04 (Standby) In the corridor outside 01GL016 CALL
CENTRE
01GL025 UPS
01GL027 SWITCHROOM
Locate the fan above the CAC39 ceiling tiles Operate on VSD. Provide acoustically insulated ductwork
(50mm insulation) from fan to first supply grill (4m).
Operate on VSD. Provide 1m of 50mm internaly lined duct
to intake side before lined plenum.
LIFT SHAFT RELIEF AIR GRILLES PLANT ROOM LIFT SHAFT N/A Provide 50mm internally lined duct from grille to
plantroom external louvre
N/A
MAINTENANCE BUILDING (MB)
VOU-RTF-MB-01 ROOF PLATFORM GRIDS 04 TO 06 Operate on VSD Operate on VSD Operate on VSD
18/07/2016 E4 - MEP mitigation: Page 9 of 19 TG264-05 5 2 01 (r21b) RTRF Design Matrices (SMTF ONVR E)
MEP Specification MEP NV RequirementsRelevant equipment Location Serving Case radiated noise Discharge side of unit Intake side of unitVOU-RTF-MB-02 ROOF PLATFORM GRIDS 04 TO 06 Operate on VSD Operate on VSD Operate on VSDVOU-RTF-MB-03 ROOF PLATFORM GRIDS 04 TO 06 Operate on VSD Operate on VSD Operate on VSDVOU-RTF-MB-06 ROOF PLATFORM GRIDS 04 TO 06 Operate on VSD Operate on VSD Operate on VSDVOU-RTF-MB-07 ROOF PLATFORM GRIDS 04 TO 06 Operate on VSD Operate on VSD Operate on VSDVOU-RTF-MB-04 02GL059 A/C PLANT 02GL059 A/C PLANT No acoustic treatment required Min 50mm acoustically lining to disharge ductwork. No acoustic treatment requiredVOU-RTF-MB-05 02GL059 A/C PLANT 02GL059 A/C PLANT No acoustic treatment required Min 50mm acoustically lining to disharge ductwork. No acoustic treatment requiredAHU-RTF-MB-01 Rooftop btw Grids 11-12 and B-C Main Depot Operate on VSD Provide acoustically insulated ductwork (50mm insulation)
for a minimum length of 5m from the fan
Provide acoustically insulated ductwork (50mm insulation)
for a minimum length of 5m from the fanOAF-RTF-MB-01 02GL006 DUTY AND SUPERVISOR 02GL006 DUTY AND SUPERVISOR CAC39 ceiling tiles provided. See ARCH. Provide acoustically insulated circular flexible ductwork
for a minimum length of 2m
Min 1m lined duct to inlet side.
OAF-RTF-MB-02 02GL007 DCC 02GL007 DCC CAC39 ceiling tiles provided. See ARCH. Provide acoustically insulated circular flexible ductwork
for a minimum length of 2m
Min 1m lined duct to inlet side.
OAF-RTF-MB-03 02GL008 1ST LINE MAINTENANCE
OFFICE
02GL008 1ST LINE MAINTENANCE
OFFICE
CAC39 ceiling tiles provided. See ARCH. Provide acoustically insulated circular flexible ductwork
for a minimum length of 2m
Min 1m lined duct to inlet side.
OAF-RTF-MB-04 02GL005 OFFICE 1P 02GL005 OFFICE 1P CAC39 ceiling tiles provided. See ARCH. Provide acoustically insulated circular flexible ductwork
for a minimum length of 1m
No acoustic treatment
OAF-RTF-MB-05 02GL004 FIRST AID 02GL004 FIRST AID CAC39 ceiling tiles provided. See ARCH. Provide acoustically insulated circular flexible ductwork
for a minimum length of 1m
No acoustic treatment
OAF-RTF-MB-06 02GL012 MEET 1 02GL012 MEET 1 CAC39 ceiling tiles provided. See ARCH. No acoustic treatment required Min 1m lined duct to inlet side.OAF-RTF-MB-07 02GL011 MEET 2 02GL011 MEET 2 CAC39 ceiling tiles provided. See ARCH. No acoustic treatment required Min 1m lined duct to inlet side.OAF-RTF-MB-08 02GL019 KITCHEN 02GL019 KITCHEN CAC39 ceiling tiles provided. See ARCH. No acoustic treatment required Min 1m lined duct to inlet side.OAF-RTF-MB-09 02GL020 DINING 02GL020 DINING CAC39 ceiling tiles provided. See ARCH. No acoustic treatment required Min 1m lined duct to inlet side.OAF-RTF-MB-10 02L1017 OFFICE 7P 02L1017 OFFICE 7P CAC39 ceiling tiles provided. See ARCH. No acoustic treatment required Min 1m lined duct to inlet side.OAF-RTF-MB-11 02L1018 MAINTENANCE OFFICE 02L1018 MAINTENANCE OFFICE CAC39 ceiling tiles provided. See ARCH. No acoustic treatment required Min 1m lined duct to inlet side.OAF-RTF-MB-12 02GL010 CORRIDOR 02GL010 CORRIDOR CAC39 ceiling tiles provided. See ARCH. No acoustic treatment required Min 1m lined duct to inlet side.OAF-RTF-MB-13 02GL040 RS & STC ELEC WKS 02GL040 RS & STC ELEC WKS Installed above plasterboard or fibre cement ceiling - CL-
302/CL-303
No acoustic treatment required Min 1m lined duct to inlet side.
OAF-RTF-MB-14 02GL041 OH & POW WK 02GL041 OH & POW WK Installed above plasterboard or fibre cement ceiling - CL-
302/CL-303
No acoustic treatment required Min 1m lined duct to inlet side.
OAF-RTF-MB-15 02GL042 ST & TUN WK/ST 02GL042 ST & TUN WK/ST Installed above plasterboard or fibre cement ceiling - CL-
302/CL-303
No acoustic treatment required Min 1m lined duct to inlet side.
OAF-RTF-MB-18 02L1013 ROLLING STOCK MANAGER 02L1013 ROLLING STOCK MANAGER CAC39 ceiling tiles provided. See ARCH. Provide acoustically insulated circular flexible ductwork
for a minimum length of 1m
No acoustic treatment
OAF-RTF-MB-19 02L1014 POWER SUPPLY MANAGER 02L1014 POWER SUPPLY MANAGER CAC39 ceiling tiles provided. See ARCH. Provide acoustically insulated circular flexible ductwork
for a minimum length of 1m
No acoustic treatment
OAF-RTF-MB-20 02L1015 SIGNAL & COMMS
MANAGER
02L1015 SIGNAL & COMMS
MANAGER
CAC39 ceiling tiles provided. See ARCH. Provide acoustically insulated circular flexible ductwork
for a minimum length of 1m
No acoustic treatment
OAF-RTF-MB-21 02L1016 STATION BASE MANAGER 02L1016 STATION BASE MANAGER CAC39 ceiling tiles provided. See ARCH. Provide acoustically insulated circular flexible ductwork
for a minimum length of 1m
No acoustic treatment
OAF-RTF-MB-22 02L1070 EMU 02L1070 EMU CAC39 ceiling tiles provided. See ARCH. Provide acoustically insulated circular flexible ductwork
for a minimum length of 1m
No acoustic treatment
OAF-RTF-MB-23 02GL058 COMMS 02GL058 COMMS CAC39 ceiling tiles provided. See ARCH. Provide acoustically insulated circular flexible ductwork
for a minimum length of 1m
No acoustic treatment
OAF-RTF-MB-24 02GL010 OFF 8P -SIGNALS 02GL010 OFF 8P -SIGNALS CAC39 ceiling tiles provided. See ARCH. Provide acoustically insulated ductwork (50mm insulation)
for a minimum length of 1m from the fan. Provide
acoustically insulated circular flexible ductwork for a
minimum length of 2m
Min 1m lined duct to inlet side.
OAF-RTF-MB-25 02GL011 OFF 8P -OH&P 02GL011 OFF 8P -OH&P CAC39 ceiling tiles provided. See ARCH. Provide acoustically insulated ductwork (50mm insulation)
for a minimum length of 1m from the fan. Provide
acoustically insulated circular flexible ductwork for a
minimum length of 2m
Min 1m lined duct to inlet side.
TEF-RTF-MB-01 02GL002 CORRIDOR outside 02GL024
LOBBY
02GL020 AWC
02GL021 LOBBY
02GL022 WCM
02GL023 WCF
02GL024 LOBBY
CAC39 ceiling tiles provided. See ARCH. Provide minimum 2m of acoustically lined 50mm duct
from fan.
Provide acoustically insulated ductwork (50mm insulation)
for a minimum length of 1m from the fan. Provide
acoustically insulated circular flexible ductwork for a
minimum length of 1m to each of the air grilles.
TEF-RTF-MB-02 02L1029 MALE CHANGE 02L1025 AWC
02L1026 WCF
02L1027 FEMALE CHANGE
02L1028 WCM
02L1029 MALE CHANGE
CAC39 ceiling tiles provided. See ARCH. Provide minimum 2m of acoustically lined 50mm duct
from fan.
Provide acoustically insulated ductwork (50mm insulation)
for a minimum length of 2m from the fan before the
junction. Provide acoustically insulated circular flexible
ductwork for a minimum length of 1m to each of the air
grillesTEF-RTF-MB-03 02GL025 UNISEX 02GL025 UNISEX CAC39 ceiling tiles provided. See ARCH. No acoustic treatment required Provide acoustically insulated circular flexible ductwork
for a minimum length of 1m to the air grille
18/07/2016 E4 - MEP mitigation: Page 10 of 19 TG264-05 5 2 01 (r21b) RTRF Design Matrices (SMTF ONVR E)
MEP Specification MEP NV RequirementsRelevant equipment Location Serving Case radiated noise Discharge side of unit Intake side of unitSAF-RTF-MB-01 & 02 CORRIDOR LIFT SHAFT Locate the fan above the CAC39 ceiling tiles. Provide acoustically insulated ductwork (50mm insulation)
to all duct work from fan to lift shaft.
Provide acoustically insulated ductwork (50mm insulation)
to all duct work and return plenum.EF-RTF-MB-01 02GL057 SIGNAL COMMUNICATION 02GL057 SIGNAL COMMUNICATION No acoustic treatment required Provide acoustically insulated ductwork (50mm insulation)
for a minimum length of 1m from the fan
Provide acoustically insulated ductwork (50mm insulation)
for a minimum length of 2m from the fanEF-RTF-MB-02&03 02GL048 MSB 02GL048 MSB No acoustic treatment required Provide acoustically insulated ductwork (50mm insulation)
for a minimum length of 2m from the fan
Provide acoustically insulated ductwork (50mm insulation)
for a minimum length of 1m from the fan.SAF-RTF-MB-03&04 02GL048 MSB 02GL048 MSB No acoustic treatment required Provide acoustically insulated ductwork (50mm insulation)
for a minimum length of 1m from the fan.
Provide acoustically insulated ductwork (50mm insulation)
for a minimum length of 1m from the fan.EF-RTF-MB-05 02GL043 CLRNS STR 02GL043 CLRNS STR Installed above plasterboard ceiling CL-303. See Table E5 No acoustic treatment required Provide acoustically insulated circular flexible ductwork
for a minimum length of 1m to the air grille.
EF-RTF-MB-06 02L1050 STORE 02L1050 STORE Installed above plasterboard ceiling CL-303. See Table E5 No acoustic treatment required Provide acoustically insulated ductwork (50mm insulation)
for a minimum length of 1m from the fan.
EF-RTF-MB-07 & 08 02GL091GAS BOTTLE STORE 02GL057 COMMS No acoustic treatment required Provide acoustically insulated ductwork (50mm insulation)
for a minimum length of 1m from the fan.
Provide acoustically insulated ductwork (50mm insulation)
for a minimum length of 1m from the fan.EF-RTF-MB-09 & 10 02GL080 BATTERY MAINTENANCE 02GL080 BATTERY MAINTENANCE No acoustic treatment required Provide acoustically insulated ductwork (50mm insulation)
for a minimum length of 1m from the fan.
Provide acoustically insulated circular flexible ductwork
for a minimum length of 1m to the air grille
EF-RTF-MB-11 02GL066 WELD SHOP EXHAUST HOOD Fan located inside maintenance building, and to allow
lined duct either side.
Provide 4m of 50mm internally lined ductwork from fan to
roof discharge.
Internal criteria 70-75dB(A) for weld shop. Provide 2m of
50mm internally lined ductwork before intake to weld
shopEF-RTF-MB-12 & 13 02GL066 WELD SHOP WELDING FUME EXTRACTION ARM Fan located inside maintenance building, and to allow
lined duct either side.
Provide 2m of 50mm internally lined ductwork from fan to
roof discharge.
Internal criteria 70-75dB(A) for weld shop. Provide 1m of
50mm internally lined ductwork before intake to weld
shopEF-RTF-MB-15 02GL082 PAINTING & EQUIPMENT
AREA
SPRAY PAINT BOOTH Encase fan with 13mm plasterboard or 9mm FC sheet and
bulk insulation, independent of fan.
Provide 4m of 50mm internally lined ductwork from fan to
roof discharge.
Internal criteria 70-75dB(A) for weld shop. Provide 2m of
50mm internally lined ductwork before intake to weld
shopVEF-RTF-MB-01 Various locations on the roof of the
Maintenance Building
Cleaning and Maintenance Tracks No acoustic treatment required No acoustic treatment required No acoustic treatment required
VEF-RTF-MB-02 Various locations on the roof of the
Maintenance Building
Cleaning and Maintenance Tracks No acoustic treatment required No acoustic treatment required No acoustic treatment required
VEF-RTF-MB-03 Various locations on the roof of the
Maintenance Building
Cleaning and Maintenance Tracks No acoustic treatment required No acoustic treatment required No acoustic treatment required
VEF-RTF-MB-04 Various locations on the roof of the
Maintenance Building
Cleaning and Maintenance Tracks No acoustic treatment required No acoustic treatment required No acoustic treatment required
VEF-RTF-MB-05 Various locations on the roof of the
Maintenance Building
Cleaning and Maintenance Tracks No acoustic treatment required No acoustic treatment required No acoustic treatment required
VEF-RTF-MB-06 Various locations on the roof of the
Maintenance Building
Cleaning and Maintenance Tracks No acoustic treatment required No acoustic treatment required No acoustic treatment required
VEF-RTF-MB-07 Various locations on the roof of the
Maintenance Building
Cleaning and Maintenance Tracks No acoustic treatment required No acoustic treatment required No acoustic treatment required
VEF-RTF-MB-08 Various locations on the roof of the
Maintenance Building
Cleaning and Maintenance Tracks No acoustic treatment required No acoustic treatment required No acoustic treatment required
ACFD-RTF-MB-01 02L1071 PLANT ROOM Acoustic louvres AL1H. Louvres as per ARCH-701 Acoustically line exhaust ducts to roof cowl, with
minimum 2m of 50mm internally lined duct. Acoustic
enclosure around compressor required for environmental
noise control (as full height wall grille identified).
Acoustically line exhaust ducts to roof cowl, with
minimum 2m of 50mm internally lined duct. Acoustic
enclosure around compressor required for environmental
noise control (as full height wall grille identified).
COU-RTF-MB-01 ROOF PLATFORM GRIDS 04 TO 06 CRAC-RTF-MB-01 Equipment operate on VSD Equipment operate on VSD Equipment operate on VSDCOU-RTF-MB-02 ROOF PLATFORM GRIDS 04 TO 06 CRAC-RTF-MB-02 Equipment operate on VSD Equipment operate on VSD Equipment operate on VSDCH-RTF-MB-01 ROOF PLATFORM GRIDS 10 TO 12 Equipment operate on VSD Equipment operate on VSD Equipment operate on VSDDANGEROUS GOODS (DG)
EF-RTF-DG-01 & 02 11GL001 CHEM STR 11GL001 CHEM STR Criteria set as 65dB(A) for unoccupied storage area. No
acoustic treatment required
No acoustic treatment required No acoustic treatment required
EF-RTF-DG-03 & 04 11GL002 DG1 11GL002 DG1 Criteria set as 65dB(A) for unoccupied storage area. No
acoustic treatment required
No acoustic treatment required No acoustic treatment required
EF-RTF-DG-05 & 06 11GL003 DG2 11GL003 DG2 Criteria set as 65dB(A) for unoccupied storage area. No
acoustic treatment required
No acoustic treatment required No acoustic treatment required
INFRASTRUCTURE WORKSHOP (IW)
VOU-RTF-IW-01 03GL013 AC PLANT 03GL013 AC PLANT No acoustic treatment required No acoustic treatment required No acoustic treatment requiredOU-RTF-IW-01 03GL013 AC PLANT IU-RTF-IW-01 No acoustic treatment required No acoustic treatment required No acoustic treatment required
18/07/2016 E4 - MEP mitigation: Page 11 of 19 TG264-05 5 2 01 (r21b) RTRF Design Matrices (SMTF ONVR E)
MEP Specification MEP NV RequirementsRelevant equipment Location Serving Case radiated noise Discharge side of unit Intake side of unitTEF-RTF-IW-01 03GL009 WC/SH/CH-M 03GL005 AWC
03GL007 WC/SH/CH-F
03GL009 WC/SH/CH-M
Locate fan above flush plasterboard ceiling No acoustic treatment required No acoustic treatment required
EF-RTF-IW-02 & 03 03GL022 DNGR GOODS 1 03GL022 DNGR GOODS 1 Criteria set as 65dB(A) for unoccupied storage area. No
acoustic treatment required
1m lined duct. 1m lined duct.
ACFD-RTF-IW-01 03GL019 MAIN STR 03GL019 MAIN STR Intermittent use within building. AS2107:2000 not
applicable.
Intermittent use within building. AS2107:2000 not
applicable.
Intermittent use within building. AS2107:2000 not
applicable.RAIL STORE (RS)
EF-RTF-RS-01 & 02 04GL003 DANGEROUS GOODS STORE 04GL003 DANGEROUS GOODS STORE Criteria set as 65dB(A) for unoccupied storage area. No
acoustic treatment required
No acoustic treatment required No acoustic treatment required
SECURITY BUILDING (SB)
OAF-RTF-SB-01 12GL001 SEC 12GL001 SEC Locate fan above flush plasterboard ceiling Provide acoustically insulated circular flexible ductwork
for a minimum length of 1m to the split cassette indoor
unit
No acoustic treatment required
OAF-RTF-SB-02 12GL002 FIRE CONTROL ROOM 12GL002 FIRE CONTROL ROOM No acoustic treatment required Provide acoustically insulated circular flexible ductwork
for a minimum length of 1m to the split cassette indoor
unit
No acoustic treatment required
OAF-RTF-SB-03 (Standby) 12GL002 FIRE CONTROL ROOM 12GL002 FIRE CONTROL ROOM No acoustic treatment required Provide acoustically insulated circular flexible ductwork
for a minimum length of 1m to the split cassette indoor
unit
No acoustic treatment required
TEF-RTF-SB-01 12GL005 WC 12GL005 WC No acoustic treatment required No acoustic treatment required No acoustic treatment requiredOU-RTF-SB-01 Outside 12GL003 MESS ROOM to the
south
IU-RTF-SB-01 No acoustic treatment required No acoustic treatment required No acoustic treatment required
OU-RTF-SB-02 Outside 12GL002 FIRE CONTROL
ROOM to the south
IU-RTF-SB-02 No acoustic treatment required No acoustic treatment required No acoustic treatment required
OU-RTF-SB-03 (Standby) Outside 12GL002 FIRE CONTROL
ROOM to the south
IU-RTF-SB-03 No acoustic treatment required No acoustic treatment required No acoustic treatment required
WHEEL LATHE (WL)
OAF-RTF-WL-01 10GL003 OFFICE 10GL003 OFFICE Locate fan above CAC39 ceiling tiles Provide acoustically insulated circular flexible ductwork
for a minimum length of 1m to the split cassette indoor
unit
No acoustic treatment required
TEF-RTF-WL-01 10GL004 WC 10GL004 WC No acoustic treatment required No acoustic treatment required No acoustic treatment requiredEF-RTF-WL-01 10GL001 WHEEL LATHE 10GL002 PIT No acoustic treatment required Provide acoustically insulated ductwork (50mm insulation)
for a minimum length of 2m from the fan
Provide acoustically insulated ductwork (50mm insulation)
for a minimum length of 2m from the fanOU-RTF-WL-01 Outside 10GL003 OFFICE to the south CA-RTF-WL-01 No acoustic treatment required No acoustic treatment required No acoustic treatment required
ACFD-RTF-WL-01 10GL001 WHEEL LATHE 10GL001 WHEEL LATHE Intermittent use within building. AS2107:2000 not
applicable.
Intermittent use within building. AS2107:2000 not
applicable.
Intermittent use within building. AS2107:2000 not
applicable.
GENERAL - INTERNAL RIGID
DUCT INSULATION
ALL LOCATIONS Perf metal faced insulation (Non-mylar lined) Perf metal faced insulation (Non-mylar lined) Perf metal faced insulation (Non-mylar lined)
18/07/2016 E4 - MEP mitigation: Page 12 of 19 TG264-05 5 2 01 (r21b) RTRF Design Matrices (SMTF ONVR E)
Table E5: SMTF Architectural Mitigation Measures
ARCH SPECIFICATION NV RequirementBuilding Room ID Element Element ID Description RW (ctr) NRCMaintenance Main walls EL-207A Kingspan (KS1000 MR) 80mm 27(-3) -
Maintenance High Walls - Spandek 0.48 mm (1 layer) EL-211, 120mm airspace filled with bulk fibreglass insulation 14
kg/m3, Spandek 0.48 mm (1 layer) EL-211
27(-3) -
Maintenance Roof RF-003 RO-201 - Klip lok 700 0.48 mm (1 layer), 130mm airspace filled with bulk fibreglass insulation
14 kg/m3 (INS-301), EL-214-0.48 mm non-perf profiled metal(1 layer).
Underside lined with IN-105 (50mm acoustic insulation equivalent to Polymax Absorb HD50)
held in place open wire mesh.
27(-3) 0.85
Maintenance Doors EL-207B Kingspan (KS1000 MR) 80mm 22(-4) -Maintenance Glazing - north facade GL-210 Fixed framed - 6.38mm laminated glass 28(-3) -Maintenance Glazing - saw tooth light panels & south facade EL-301 12m Danpalon Multicell 20(-3) -Maintenance Wall Ventilator LV Air grills along northern and southern wall, as per architectural drawings.
1m x 2m louvres every second column (18m centres)
- -
Maintenance 02GL040 RS & STC ELEC WKS Ceiling CL-303 13mm plasterboard ceiling 25 -Maintenance 02GL041 OH & POW WK Ceiling CL-303 13mm plasterboard ceiling 25 -Maintenance 02GL042 ST & TUN WK/ST Ceiling CL-303 13mm plasterboard ceiling 25 -Maintenance 02GL043 CLRNS STR Ceiling CL-303 13mm plasterboard ceiling 25 -Maintenance 02L1050 STORE Ceiling CL-302 13mm plasterboard ceiling 25 -Maintenance 02L1071 PLANT ROOM Louvres LV-103 IAC Acoustic/Sound Attenuators Australia ALH1 300mm deep acoustic louvre See Table E4 -Administration Plant room External walls (above roof line) EL-206A Kingspan (KS1000 MR) 80mm 27(-3) -Administration Plant room Walls below roof line 1 x 13mm fire-rated plasterboard / 150mm steed stud with 75mm fibreglass ins (14kg/m3) /
1 x 13mm fire-rated PB / 1 x 9mm FC lining
55
Administration Plant room Roof RF-003 RO-201 - Klip lok 700 0.48 mm (1 layer), 130mm airspace filled with bulk fibreglass insulation
14 kg/m3 (INS-301), EL-214-0.48 mm non-perf profiled metal(1 layer).
Underside lined with IN-105 (50mm acoustic insulation equivalent to Polymax Absorb HD50)
held in place open wire mesh.
27(-3) 0.85
Administration Plant room Plant room louvres LV-103 IAC Acoustic/Sound Attenuators Australia ALH1 300mm deep acoustic louvre See Table E4 -
Administration CRAC External plant deck Barriers - 2.4m high walls
North and east perimeter wall of enclosure.
Blockwork walls with acoustically absorptive finish to internal face of plant enclosure walls
such as 50mm Pyrotech Reapor
27(-3) 0.85
Administration CRAC External plant deck CRAC units Mounted no higher than 450 above groundTrain wash Train wash Walls EL-207C & D
GL-210
Kingspan (KS1000 MR) 80mm
6 mm float glazing
27(-3) -
Train wash Train wash Roof EL-207A Kingspan (KS1000 MR) 80mm 27(-3) -Train wash Train wash Roof ventilators RO-301 4 x roof vents -Train wash Train wash East West openings - Opening minimised as far as practical. 4800 as per architectural drawings. - -Wheel lathe Building 10 Walls EL-207A Kingspan (KS1000 MR) 80mm 27(-3) -Wheel lathe Building 10 Roof RF-002 RO-201 Klip lok 700 0.48 mm (1 layer), 130mm airspace filled with bulk fibreglass insulation
14/kg/m3, RS-201 Klip lok 700 0.48 mm (1 layer).
Underside lined with 50mm acoustic insulation equivalent to Polymax Absorb HD50 - held in
place with acoustic retaining wire
27(-3) 0.85
Wheel lathe Building 10 Roof Ventilators - 3 x 900 throat vents - -Wheel lathe Building 10 Doors - Open, as per architectural drawings. - -Wheel lathe Building 10 Glazing EL-301 12m Danpalon Multicell 20(-3) -Wheel lathe Lathe Pit - 10GL002 Pit wall internal lining Acoustic lining of pit walls 50mm Pyrotek Reapor. 0.9Distribution and Traction Sub Transformer bays Transformer bay walls Acoustic lining of transformer bays with acoustic insulation equivalent to Polymax Absorb
HD50 or 50mm Pyrotech Reapor.
Where protective sheeting is required for the insulation, perforated metal having minimum
11% open area equivalent to Stramit Acoustic Panel System
- 0.85
Distribution and Traction Sub Transformer bays Roof over bays RS-201 Klip lok 700 0.48 mm (1 layer).
Underside underside lined with 50mm acoustic insulation equivalent to Polymax Absorb
HD50 - held in place with roof safety mesh
20(-3) 0.85
Distribution and Traction Sub Transformer bays Doors - Air grills along SE, NE and NW sides of transformer room - -Distribution and Traction Sub Transformer bays Louvres - Standard weather louvres - -Bulk Supply Wall surrounding Bulk Supply Blockwork wall as per architectural drawings 30 -
Report ref: NWRLOTS-NRT-RTF-AV-RPT-105005-E
18/07/2016 E5 - ARCH mitigation: Page 13 of 19 TG264-05 5 2 01 (r21b) RTRF Design Matrices (SMTF ONVR E)
ARCH SPECIFICATION NV RequirementBuilding Room ID Element Element ID Description RW (ctr) NRCFire pump room Fire pump room Doors GL-001, GL-001 32 -Fire pump room Fire pump room Louvres LV-01 15-GL, LV-02 15-GL ALH2 Acoustic louvre, 600 deep
1200 x 3000 on southern façade (western end)
1200 x 3000 on western façade (centre)
See Table E4 -
Fire pump room Fire pump room High sectiono fo walls EL211 High section of wall to be minimum 9mm fibre cement sheeting. 30 -Fire pump room Fire pump room Roof Vents RO-302B Standard roof ventilator,min 2.5m from building edge. - -
18/07/2016 E5 - ARCH mitigation: Page 14 of 19 TG264-05 5 2 01 (r21b) RTRF Design Matrices (SMTF ONVR E)
RENZO TONIN & ASSOCIATES 18 JULY 2016
NORTHWEST RAPID TRANSIT
TG264-05 8F01 (R7) SSI 5931 ONVR [NWRLOTS-NRT-RTF-AV-RPT-
105005-E] 64
SYDNEY METRO TRAIN FACILITY (SMTF) - SSI 5931 ONVR
NWRLOTS-NRT-RTF-AV-RPT-105005-E
APPENDIX F Predicted noise levels from SMTF operations
RENZO TONIN & ASSOCIATES 18 JULY 2016
NORTHWEST RAPID TRANSIT
TG264-05 8F01 (R7) SSI 5931 ONVR [NWRLOTS-NRT-RTF-AV-RPT-
105005-E] 65
SYDNEY METRO TRAIN FACILITY (SMTF) - SSI 5931 ONVR
NWRLOTS-NRT-RTF-AV-RPT-105005-E
APPENDIX G Independent verifier statement