RP702 V2 - World Bank Documents
-
Upload
khangminh22 -
Category
Documents
-
view
1 -
download
0
Transcript of RP702 V2 - World Bank Documents
The World Bank Financed Taiyuan Urban Transport Project
Resettlement Action Plan
The World Bank Financed Taiyuan Urban Transport Project Resettlement Office
RP702 V2
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
i
Contents Contents.........................................................................................................................i
Contents of Tables.........................................................................................................v
1 Project Overview.....................................................................................................1
1.1 Brief Introduction to the Project................................................................................................. 1 1.2 linked Projects............................................................................................................................ 2 1.3 Regions Benefiting from the Project .......................................................................................... 3 1.4 Regions Affected by the Project................................................................................................. 5 1.5 Measures to Minimize Resettlement .......................................................................................... 7
1.5.1 Measures adopted in the project design stage..................................................................... 7 1.5.2 Measures to be adopted during implementation ............................................................... 10 1.5.3 Measures to be adopted during the construction .............................................................. 10
1.6 Preparation and Progress of the Project.................................................................................... 11 1.7 Ownership of the Project.......................................................................................................... 12 1.8 Implementation Schedule of the Project................................................................................... 12 1.9 Approval for Land Use and Relocation.................................................................................... 12 1.10 Laws Related to Compensation Rate..................................................................................... 12
2 Project Impact Analysis .........................................................................................14
2.1 Definition of Project Impact..................................................................................................... 14 2.2 Project Socioeconomic Survey................................................................................................. 16 2.3 Impact of Land Acquisition and Relocation............................................................................. 18 2.4 Impact of Land Acquisition for the Project .............................................................................. 22
2.4.1 Acquisition of rural collectively-owned land..................................................................... 23 2.4.2 Acquisition of state-owned land ........................................................................................ 26
2.5 Relocation ................................................................................................................................ 26 2.5.1 Relocation of private houses ............................................................................................. 26 2.5.2 Relocation of buildings of enterprises and institutions ..................................................... 27 2.5.3 Illegal buildings affected by the project ............................................................................ 28 2.5.4 Affected attachments.......................................................................................................... 28 2.5.5 Affected shops.................................................................................................................... 29 2.5.6 Affected smallware market ................................................................................................ 29
2.6 Affected Vulnerable Groups..................................................................................................... 29 2.6.1 Determination of affected vulnerable groups .................................................................... 29 2.6.2 Affected families of vulnerable groups .............................................................................. 30
2.7 Affected Infrastructures............................................................................................................ 31 2.8 Impact of Land Acquisition and Relocation for linked Projects ............................................. 31
2.8.1 Impact of land acquisition for linked projects................................................................... 31 2.8.2 Impact of relocation for linked projects ............................................................................ 32
3. Analysis on Socioeconomic Impact of Project .........................................................34
3.1 General Introduction to Socioeconomic Development of the Regions Affected by the Project34 3.2 General Situation of Affected Villages..................................................................................... 37 3.3 Analysis on Basic Information of Affected Families................................................................ 40 3.4 Analysis on Family Information of Affected Vulnerable Groups............................................. 44 3.5 Impact on Ethnic Minorities and Social Gender ...................................................................... 44
4. Law Framework and Policies...................................................................................46
4.1 Main Law Framework and Policies of Resettlement................................................................ 46 4.1.1 Relevant laws and provisions enacted By the Central Government.................................. 46 4.1.2 Statues and policies enacted by the People’s Government of Shanxi Province and related departments ................................................................................................................................ 46 4.1.3 Statues and policies enacted by the People’s Government of Taiyuan City and related
ii
departments ................................................................................................................................ 47 4.1.4 The World Bank’s policies on involuntary resettlement..................................................... 47
4.2 Summary of Main Law Framework and Policies..................................................................... 47 4.2.1 Summary of relevant national law framework................................................................... 47 4.2.2 Summary of relevant statues and policies in Shanxi Province .......................................... 50 4.2.3 Summary of relevant statues and policies in Taiyuan City ................................................ 61 4.2.4 The World Bank’s relevant policies on involuntary resettlement ....................................... 63
4.3 Polices on Resettlement for This Project.................................................................................. 65 4.3.1 Methods for the acquisition of state-owned land............................................................... 65 4.3.2 Compensation methods for the acquisition of collectively-owned land ............................ 66 4.3.3 Compensation and resettlement for the relocation on state-owned land........................... 66 4.3.3.1 Monetary compensation ................................................................................................. 66 4.3.3.2 Exchange of property right............................................................................................. 68 4.3.4 Compensation and resettlement for the relocation on collectively-owned land ................ 69 4.3.4.1 Monetary resettlement .................................................................................................... 69 4.3.4.2 Exchange of property right............................................................................................. 69 4.3.5 Resettlement of affected houses and shops of enterprises and institutions........................ 70 4.3.6 Moving subsidy and transition subsidy ............................................................................. 71 4.3.7 Resettlement of vulnerable groups .................................................................................... 72 4.3.8 Resettlement for the relocation of illegal structures.......................................................... 72 4.3.9 Compensation for affected infrastructures and attachments to the ground....................... 73
4.4 Policies on the Resettlement of linked projects........................................................................ 74 5. Resettlement Compensation Rates...........................................................................75
5.1 Basis of Establishment of Compensation Rates ....................................................................... 75 5.1.1 Basis of establishment of land compensation rates ........................................................... 75 5.1.2 Basis of establishment of compensation rates for buildings.............................................. 77 5.1.3 Basis of establishment of compensation rates of other kinds ............................................ 80
5.2 Compensation Rates................................................................................................................. 80 5.2.1 Compensation rates for land acquisition .......................................................................... 81 5.2.2 Compensation rates for relocated houses.......................................................................... 81 5.2.3 Rates for moving subsidy and transition subsidy .............................................................. 82 5.2.4 Compensation rates for affected infrastructures and attachments to the ground.............. 83
6 Resettlement and Rehabilitation ............................................................................85
6.1 Objective, Mode and Principle of the Resettlement and Rehabilitation................................... 85 6.1.1 Objective of the resettlement and rehabilitation................................................................ 85 6.1.2 Mode of the resettlement and rehabilitation...................................................................... 85 6.1.3 Principle of the resettlement and rehabilitation ................................................................ 86
6.2 Resettlement for Relocated Households................................................................................... 87 6.3 Rehabilitation of Peasants Affected by Land Acquisition ........................................................ 90 6.4 Rehabilitation of Affected Enterprises and Institutions............................................................ 91
6.4.1 Compensation and rehabilitation of enterprises whose production and business are affected ....................................................................................................................................... 91 6.4.2 Resettlement and rehabilitation of other enterprises and institutions ............................... 96 6.4.3 Reconstruction of affected schools .................................................................................. 100 6.4.4 Resettlement and rehabilitation of affected shops ........................................................... 101
6.5 Rehabilitation of Professional Facilities................................................................................. 103 6.6 Resettlement and Rehabilitation of Affected Vulnerable Groups........................................... 103 6.7 Schedule of Resettlement and Rehabilitation......................................................................... 104
7 Budget and Management of Resettlement Fund ...................................................107
7.1 Constitution of Resettlement Fund......................................................................................... 107 7.1.1 Land compensation ......................................................................................................... 107 7.1.2 Compensation for relocation........................................................................................... 107 7.1.3 Compensation for attachments to the ground and common facilities.............................. 108
iii
7.1.4 Management costs of resettlement................................................................................... 108 7.1.5 Other costs and contingency ........................................................................................... 108
7.2 Budget of Resettlement Fund................................................................................................. 108 7.3 Allocation and Flow of Resettlement Funds .......................................................................... 110
7.3.1 Allocation of resettlement funds .......................................................................................110 7.3.2 Sources and flow of resettlement funds.............................................................................111
7.4 Payment, Management and Monitoring of Resettlement Funds ............................................ 112 7.4.1 Payment of resettlement funds..........................................................................................112 7.4.2 Management and monitoring of resettlement funds .........................................................112
8. Organizational Framework of Resettlement ........................................................... 114
8.1 Organizational Establishment................................................................................................. 114 8.2 Responsibilities of All Organizations..................................................................................... 115
8.2.1 Project Leading Group Office ..........................................................................................115 8.2.2 Project Resettlement Office ..............................................................................................115 8.2.3 Resettlement Offices of Districts ......................................................................................116 8.2.4 Resettlement Office of Towns (Offices).............................................................................116 8.2.5 Resettlement Group of Villages (Communities)................................................................117 8.2.6 Design Institute ................................................................................................................117 8.2.7 Independent Monitoring Organization.............................................................................117
8.3 Personnel and Equipments of Resettlement Organizations at all Levels................................ 118 8.4 Measures for the Strengthening of Organizational Capacity.................................................. 120 8.5 Plans for the Strengthening of Organizational Capacity in the Future................................... 121
9 Public Participation and Consultation ..................................................................124
9.1 Activities Carried out up to Now............................................................................................ 124 9.2 Feedback on Public Participation and Consultation............................................................... 129 9.3 Next Consultation Plan with Affected Population.................................................................. 133 9.4 Consultation Modes of Affected Population during Project Implementation Period ............. 135 9.5 Policy Disclosure and Resettlement Information Booklet...................................................... 135
10. Complaint and Appeal .........................................................................................137
10.1 Means of Collecting Dissatisfaction and Complaints........................................................... 137 10.2 Procedure of Complaining and Appealing ........................................................................... 137 10.3 The Principles of Handling Complaints ............................................................................... 138 10.4 Contents of the Reply and Ways of Replying to Complaints ............................................... 139
10.4.1 Contents of the reply...................................................................................................... 139 10.4.2 Replying to complaints .................................................................................................. 139
10.5 Record of Complaints and Appeals and Relevant Feedback................................................ 139 10.6 Contact Information for Expressing Complaints and Appeals ............................................. 140
11. Resettlement Monitoring .....................................................................................142
11.1 Internal Monitoring .............................................................................................................. 142 11.1.1 Purpose and principles.................................................................................................. 142 11.1.2 Procedure of internal monitoring .................................................................................. 143 11.1.3 Contents of internal monitoring..................................................................................... 144 11.1.4 Means of internal monitoring ........................................................................................ 146 11.1.5 Internal monitoring agency and personnel assignment................................................. 149 11.1.6 Assignments of internal monitoring agency................................................................... 150 11.1.7 Reporting period of internal monitoring ....................................................................... 150
11.2 Independent Monitoring ....................................................................................................... 151 11.2.1 Purpose of independent monitoring............................................................................... 151 11.2.2 Independent monitoring organization and monitoring personnel ................................. 151 11.2.3 Assignments of the independent monitoring organization ............................................. 153 11.2.4 Means and procedures of independent monitoring........................................................ 153 11.2.5 Contents of independent monitoring.............................................................................. 154 11.2.6 Reporting system of independent monitoring ................................................................ 159
iv
12 Matrix of Entitlement ........................................................................................160
Attached Table 1 Quantity of private houses affected by relocation for Taiyuan Urban Transport Project ...................................................................................................................................... 164 Attached Table 2 Relocated households and population living in dormitories of enterprises and institutions................................................................................................................................ 166 Attached Table 3 Area and structures of houses of enterprises and institutions to be relocated for Taiyuan Urban Transport Project....................................................................................... 168 Attached Table 4 illegal buildings of private households......................................................... 178 Attached Table 5 Illegal buildings of enterprises and institutions(m2).................................... 179 Attached Table 6 Affected attachments of private family households....................................... 182 Attached Table 7 Affected attachements of enterprises and institutions................................... 183 Attached Table 8 Shops affected by Taiyuan Urban Transport Project .................................... 184 Attached Table 9 List of affected families of vulnerable groups............................................... 190 Attachment 1: ........................................................................................................................... 192 Resettlement Comparison between Direct Line and Circuitous Line of North Mid Ring Road192 Attachment 2: ........................................................................................................................... 198 Methods for the Use and Management of the Funds for Vulnerable Groups Affected by the Resettlement for the World Bank Financed Taiyuan Urban Transport Project ........................ 198 Attachment 3: ........................................................................................................................... 202 Resettlement Information Booklet for the World Bank Financed Taiyuan Urban Transport Project ...................................................................................................................................... 202
v
Contents of Tables Table 1-1 Composition of the World Bank Financed Taiyuan Urban Transport Project ..1
Table 1-2 Areas affected by Taiyuan Urban Transport Project........................................5
Table 1-3 Comparison of line schemes for North Mid Ring Road ..................................8
Table 1-4 Schedule for the preparation and implementation of the project ...................12
Table 1-5 Schedule for applying for approval for land use and relocation ....................12
Table2-1 Summary of the impacts of land acquisition and relocation of Taiyuan Urban
Transport Project.........................................................................................................20
Table 2-2 Types and quantity of collectively-owned land requisitioned for Taiyuan
Urban Transport Project ..............................................................................................24
Table 2-3 Buildings of enterprises and institutions to be relocated ...............................27
Table 2-4 Distribution of affected vulnerable groups ...................................................30
Table 2-5 Types and quantities of affected infrastructures............................................31
Table 2-6 Quantities of buildings of enterprises and institutions to be relocated for
linked projects.............................................................................................................32
Table 2-7 Shops affected by linked projects.................................................................33
Table 3-1 General situation of socioeconomic development of the regions affected by
Taiyuan Urban Transport Project (2006)......................................................................36
Table 3-2 General situation of villages affected by land acquisition and relocation for
Taiyuan Urban Transport Project .................................................................................39
Table 3-3 Basic characteristics of displaced persons of Taiyuan Urban Transport Project
....................................................................................................................................40
Table 3-4 Dwelling situation of affected families of Taiyuan Urban Transport Project .41
Table 3-5 Incomes of affected families ........................................................................42
Table 3-6 Proportion of dwelling spaces of affected families .......................................43
Table 5-1 Compensation rates for land acquisition calculated as per the highest times
(30 times) of average annual output value ...................................................................75
Table 5-2 Compensation rates of typical projects relocation in Taiyuan .......................78
Table 5-3 Base prices of various lands of Taiyuan .......................................................79
Table 5-4 Compensation prices of dwelling houses on state-owned land......................81
Table 5-5 Compensation prices of non-domestic houses on state-owned land ..............82
Table 5-6 Compensation prices of houses on collectively-owned land .........................82
Table 6-1 Construction plan of resettlement spots of Taiyuan urban transport project ..88
Table 6-2 Resettlement and recovery methods for enterprises whose production and
business operations are affected...................................................................................92
Table 6-3 Resettlement and rehabilitation methods of affected enterprises and
vi
institutions ..................................................................................................................96
Table 6-4 Schedule of resettlement activities .............................................................105
Table 7-1 Allocation object of resettlement funds ...................................................... 111
Table 8-1 Member list of all levels of resettlement offices for Taiyuan Urban Transport
Project....................................................................................................................... 118
Table 8-2 Personnel placement of all levels of resettlement organizations.................. 119
Table 8-3 Equipments of all levels of resettlement organizations ............................... 119
Table 8-4 Operational training plan table of resettlement personnel ...........................120
Table 8-5 Next operational training plan table of resettlement organizations..............122
Table 9-1 Main activities of resettlement information disclosure and consultation .....124
Table 9-2 Summarized table of public opinions and advices ......................................126
Table 9-3 Feedback on public participation and consultation of World Bank Financed
Taiyuan Urban Transport Project ...............................................................................129
Table 9-4 Time arrangement for consultative meetings with displaced persons ..........134
Table 10-1 Record form of complaints and appeals on the resettlement of the World
Bank Financed Taiyuan Urban Transport Project .......................................................140
Table 10-2 Information of the machinery and persons for receiving the complaints and
appeals of displaced persons......................................................................................140
Table 11-1 Land acquisition and resettlement progress ..............................................148
Table 11-2 Progress of using the compensation fund..................................................149
Table 11-3 Personnel of internal monitoring in resettlement agency...........................149
Table 11-4 Personnel of the Independent Monitoring Organization of the World Bank
Financed Taiyuan Urban Transport Project ................................................................152
Table 1 Comparison of affected families, persons and building areas between two lines
..................................................................................................................................193
Table 2 Compensation funds for private families affected by relocation in two lines..193
Table 3 Comparison of area of relocated enterprises and institutions between two lines
..................................................................................................................................194
Table 4 Comparison of compensation funds for affected enterprises and institutions
between two lines......................................................................................................195
Table 5 Comparison on the impact and cost of the land acquisition for two different
lines ..........................................................................................................................196
Table 6 Comparison on resettlement influences and cost between two lines...............196
Table 7 Comparison conclusions of two line programs for North Mid Ring ...............197
1
1�Project Overview
1.1 Brief Introduction to the Project
The World Bank Financed Taiyuan Urban Transport Project includes the following
four subprojects: improvement or road network, public transport, traffic management
and road safety, and strengthening of organizations.
The road network improvement subproject includes the construction of north
middle ring road and Taihang Road.
Traffic management and road safety subproject include the expansion of traffic
signal system and improvement of traffic arrangement at some sections and junctions,
facilities for non-motor vehicles and pedestrians, traffic guidance system, education on
traffic law and road safety, technological research and training, etc.
The subproject of public transport includes one exclusive bus lane from the south
to the north, construction of harbor-like bus stops at main lines, construction of two bus
parking & maintenance lots in Nanhan and Beiying, construction of four initial and
terminal Stations including Helaowan, Beiyan, Yingxin Street and Wohushan,
intelligent dispatching system, etc.
Technological research and consulting carried out for part of the abovementioned 3
subprojects constitutes the 4th subproject of this project.
Table 1-1 Composition of the World Bank Financed Taiyuan Urban Transport Project
No. Subproject
name Project description land
acquisition relocation
I Improvement of road network
1North Mid Ring Road North Mid Ring Street
Urban speedy way, with bi-directional 6 lanes for main lines, bi-directional 4 lanes for subsidiary road, construction of non-motor vehicle road. Starting from the junction of Waliu Road and North Mid Ring Road Street and ending at the junction of Taihang Road and Shenglidong Street, totaling 9.95 km.
�
2 Taihang Road
Urban main trunk road, with planned red line of 50 m in width. Bi-directional 8 lanes for main lines, some parts with subsidiary roads and non-motor vehicle road. Starting from the junction of Taihang Road and Shenglidong Street, and ending at the junction of Taihang Road and Xutan East Street, totaling 10.3 km.
�
II Improvement of public transport
1Public transport priority
2
1
Pingyang Road- Xinjian Road exclusive bus lane
Pingyang Road- Xinjian Road exclusive bus lane to be listed in the north-south road planning (the project includes improving and reconstructing road facilities, setting up signs and marking lines, reconstructing bus stops and signals). It starts from Shengli Street to Xuefu Street, totaling 11.4 km.
2Bus parking lot and maintenance lot
Two depots: Beiying and Nanhan ��
3Initial and terminal Stations
It is planned to build 4 initial and terminal Stations in Beiyan, Zoo, Helao Wan, and Yingxin Street.
� �
4Intelligent bus dispatching system
It is planned to construct the intelligent dispatching system in three stages, including inquiry system, bus-dispatching system, vehicle on-board data transmission system.
5Technological research
(1) Research on the optimizing of public transport network and public transport priority;
(2) Research on computer-based management and operation of public transport;
(3) Reformation of public transport system
III Traffic management and road safety
IV Strengthening of organization
VConstruction of resettlement spot
Five plots of land with total area of 59.61ha is requisitioned additionally for building resettlement houses and resettling the displaced persons affected by the project
��
Source: Proposal for the World Bank Financed Urban Transport Project, Leading Group Office of the World Bank
Financed Taiyuan Urban Transport Project, October 2006
1.2 Linked Projects
As is mentioned in the 4th article of Operational Policies for Involuntary
Resettlement, the policy applies to all components of the project that result in
involuntary resettlement, regardless of the source of financing. It also applies to other
activities resulting in involuntary resettlement, that in the judgment of the Bank, are (a)
directly and significantly related to the Bank-assisted project, (b) necessary to achieve
its objectives as set forth in the project documents; and (c) carried out, or planned to be
carried out, contemporaneously with the project.
According to the abovementioned principles, there are three linked projects: 1)
extension line of Waliu Road connected with North Mid Ring Road; 2) extension line of
Taihang Road connected with South Mid ring Road; 3) the bridge crossing Fenhe River.
Waliu Road and the North Mid Ring Road is 1.4 km away from each other. The
construction of extension line of Waliu Road to the north can connect Waliu Road and
North Mid Ring Road, and bring into full play the function of North Mid Ring Road as
the urban expressway. In the World Bank financed project under planning, Taihang
3
Road intersects Xutan East Street at Shenglidong Street towards the south, totaling 10.3
km, extending the Taihang Road northward for 1.7 km, connecting with North Mid
Ring Road, forming a complete urban trunk road network, which can bring the function
of Taihang Road as urban trunk road into full play. The bridge crossing Fenhe River
itself is one section of North Mid Ring Road and connects two secons of North Mid
Ring on the east and west banks of Fenhe River.
Considering that the abovementioned three subprojects are closely connected to this
project, this Resettlement Action Plan list these three subprojects in the related projects
of the World Bank Financed Urban Transport Project and brings the resettlement for
them into this plan.
1.3 Regions Benefiting from the Project
The implementation of the World Bank Financed Urban Transport Project will
optimize the transport system of Taiyuan city, the political, economical, cultural and
transport center of Shanxi Province, make it more convenient for the outing of urban
inhabitants, and enhance the functions of Taiyuan City in an all round way.
Great progresses have been made in city construction and transport in the 50 years
since the founding of the P.R. China. But there are still some problems with urban
transport that do not meet the demand for the development of the city. These problems
are:
First, urban transport lags behind the development of the city: (1) the development
of the city from the north to the south lacks the support of a backbone road; (2) the
development of the east part of the city lacks the support of road network; (3) the city
itself is still of a multi-circle structure with a single center, with many concentric circles,
which result in the serious traffic problems in the central area. Second, the demand and
supply of transport is imbalanced: (1) the capacity of road network in the city center
cannot adapt to the fast development trend of motor vehicles; (2) the road network in
the peripheral region still needs improvement; it is urgently needed to guide the
development of land through construction of road network; (3) the traffic is more and
more crowded in roads crossing Fen River; (4) static transport is seriously lagging
behind.
4
Third, public transport is developing at a low speed: (1) the buses for public
transportation is old, the distribution of bus stops and bus stations are not reasonable,
the measures for public transport priority are not enough, it takes a long time for
passengers to walk to the bus stops, and to wait for the buses, and the distance of travel
for most passengers doesn’t reach the ideal service distance for buses. All these lead to
the low service level and the unpopularity of public transportation, which only account
for 11% for all the outings of the citizens. (2) The road network is imperfect, which
reduce the coverage of service. The public transportation in Taiyuan (excluding taxi)
only has regular over-ground roads. There is no systematic planning for public transport
lines. The lines are excessively concentrated in the trunk roads in the center area. (3)
The facilities for bus stops are not reasonably arranged, the development of which is
restricted by policies and insufficiency of fund. The maintenance for buses is of low
level. All these lead to the small number and low quality of buses. Averagely, each
10,000 permanent population in the urban area only have 6.8 buses. The bus stations of
different kinds only cover an area of about 356,400 � , which could only meet the demand of parking for only 1, 153 buses.
Fourth, there are not enough routes for freight: (1) the flow of freight traffic
brings huge pressure to central areas; (2) there is a lack of highly sufficient ways form
the peripheral supply depots of goods to the city center.
Fifth, the traffic management level is low: (1) the unidirectional transport is lack
of systematic planning; (2) the land for junctions is not enough; (3) the markings are not
timely renewed; (4) slow traffic is not attached enough attention to, and the transport
facilities are simple and unsophisticated, and small in number; (5) the intelligent
facilities are of low levels; (6) the management of parking of buses need improvement.
Sixth, the connection to the outside is insufficient: (1) the roads are of low
radiating capacity to the outside; (2) the connection with the outside transport should be
improved.
Considering the above-mentioned problems, the authority of Taiyuan city
conceived the idea of improving the transport with the loan from the World Bank, and
has made an overall plan for the project (including 4 subprojects) after consultation with
the experts of the World Bank. The following can be realized through the World Bank
Financed Taiyuan Urban Transport Project: (1) the construction of North Ring Road and
5
Taihang Road will reduce the pressure on the central area, and reduce traffic jams in the
central area; (2) the construction of the two roads would promote the development of
the east and north parts of the city; (3) it will alleviate the crowded traffic of the north
part of the city that crosses the Fen River. (4) It will increase the number of people
taking buses and improve the transport conditions. (5) It will facilitate the outing of
vulnerable groups, improving the traffic management and improving the efficiency of
roads.
1.4 Regions Affected by the Project
The impact of the World Bank Financed Taiyuan Urban Transport Project is limited
within Taiyuan City. The road network improvement project and public transport
improvement project involve Bolin District, Jiancaoping District, Xinghualing District,
Yingze District, Xiaodian District and Jinyuan District. The road network improvement
project that leads to most relocation involves 5 districts, 10 sub-district offices
(townships), and 31 villages (communities)�For the project of public transport, four bus stations and two parking and
maintenance lost are distributed in five districts, six streets and six villages.
Among related project, the relocation for the extension line of Taihang Road
involves Xiaodian District, Beiying Sub-district Office, two villages (Xudong Village
and Xutan Village) and a community (Community of Chinese Academy of Agricultural
Sciences); the extension of Waliu Road involves Dongshe Village of Dongshe
Community in Wanbolin District.
The impact scope of the resettlement of Taiyuan Urban Transport Project is as
shown in Table 1-2.
Table 1-2 Areas affected by Taiyuan Urban Transport Project
Lines Affected districts Sub-district
offices(Town) Communities (Villages)
North Mid Ring Road
Wanbolin District Wanbolin Sub-district
Office Jinjixi Community
North Mid Ring Road
Wanbolin District Wanbolin Sub-district
Office Anguang Community
North Mid Ring Road
Jiancaoping District Huifeng Sub-district
Office Huifeng Community
North Mid Ring Road
Jiancaoping District Huifeng Sub-district
Office Xiliu Village
North Mid Ring Road
Jiancaoping District Huifeng Sub-district
Office Xiaodongliu Village
North Mid Ring Road
Jiancaoping District Huifeng Sub-district
Office Dadongliu Village
6
North Mid Ring Road
Jiancaoping District Gucheng Sub-district
Office Senyuannan Community
North Mid Ring Road
Xinghualing District
Julun Sub-district Office Xishengli Community
North Mid Ring Road
Xinghualing District
Julun Sub-district Office Shangbeiguan Community
North Mid Ring Road
Xinghualing District
Dunhuafang Sub-district Office
Jin’anxi Street Community
North Mid Ring Road
Xinghualing District
Dunhuafang Sub-district Office
Kuangji Community
North Mid Ring Road
Xinghualing District
Dunhuafang Sub-district Office
Wohushan Community
North Mid Ring Road
Xinghualing District
Yangjiayu Sub-district Office
Xiangtang Village
Taihang Road Xinghualing
District Yangjiayu Sub-district
Office Xiaozaogou Village
Taihang Road Xinghualing
District Yangjiayu Sub-district
Office Daochanggou Village
Taihang Road Xinghualing
District Yangjiayu Sub-district
Office Baergou Village
Taihang Road Xinghualing
District Yangjiayu Sub-district
Office Sanershu Village
Taihang Road Xinghualing
District Xinjie Sub-district
Office Xincun Community
Taihang Road Xinghualing
District Xinjie Sub-district
Office Taihang Road Community
Taihang Road Xinghualing
District Dadongguan Sub-district
Office Xinbei Community
Taihang Road Xinghualing
District Dadongguan Sub-district
Office Xinnan Community
Taihang Road Xinghualing
District Dadongguan Sub-district
Office Honggou Community
Taihang Road Xinghualing
District Dadongguan Sub-district
Office Wulongkou Community
Taihang Road Xinghualing
District Dadongguan Sub-district
Office Bailong Garden Community
Taihang Road Yingze District Haozhuang Town Haojiagou Village
Taihang Road Yingze District Haozhuang Town Haozhuang Village
Taihang Road Yingze District Haozhuang Town Wangjiafeng Village
Taihang Road Yingze District Haozhuang Town Dongtaibao Village
Taihang Road Yingze District Haozhuang Town Dianpo Village
Taihang Road Xiaodian District Beiying Sub-district
Office Longbao Village
Taihang Road Xiaodian District Beiying Sub-district
Office Xudong Village
Taihang Road Xiaodian District Beiying Sub-district
Office Xudong Village
Extension line of Waliu Road
Wanbolin Dongshe Dongshe Village
Extension line of Taihang Road
Xiaodian District Beiying Xudong Village, Xutan Village,
Community of Chinese Academy of Agricultural Sciences
Helaowan Initial and Terminal
Station Wanbolin District
Duerping Sub-district Office
Helaowan Village
Beiyan Initial and Terminal
Station Jinyuan District
Yijing Sub-district Office
Yijing Village
7
Wohushan Initial and Terminal
Station
Xinghualing District
Yangjiayu Sub-district Office
Zhongjianhe Village
Yingxin Street Initial and
Terminal Station Jiancaoping District
Yingxin Street Sub-district Office
Nangunian Village
Beiying Depot Xiaodian District Beiying Sub-district
Office Base of Stud Plot of the provincial
Forestry Department
Nanhan Depot Wanbolin District Xiaojingyu Sub-district
Office Jiuzhou Village
1.5 Measures to Minimize Resettlement
1.5.1 Measures adopted in the project design stage
In the planning and design stage, to mitigate the impact on local economy, the
leading group of the World Bank Financed Taiyuan Urban Transport Project has several
meetings together with the consulting and design departments to discuss how to
optimize the design and how to mitigate impact.
Picture 1-1 Personnel of the Resettlement Office, design and consulting units are
surveying the site to optimize the alignment
Shanghai Municipal Engineering Design General Institute, responsible for the
design of the project, East China Investigation and Design Institute, responsible for
environmental impact assessment, Research Center for Involuntary Resettlement,
Wuhan University, responsible for resettlement consulting, Liaoning Academy of Social
Sciences, responsible for public participation and collecting of complaints give their
suggestions for optimization of the project. The suggestions are reported to the project
8
office by Shanghai Municipal Engineering Design General Institute. In the project
design stage, the principles agreed upon to reduce impact are as follows:
First, compare different schemes, take the impact on local society and economy into
consideration, minimize the use of cultivated land.
Second, minimize relocation, and take this as the major factor when choosing
schemes. Leave reasonable space for other public utilities.
Third, for reconstruction and expansion of roads, when deciding the length of the
red line, take the relocation into consideration, and maintain the original length of red
line to reduce relocation.
For example, at the east section of North Mid Ring Road, there are two design
schemes. One is the circuitous line scheme and the other is direct line scheme. Based on
the initial design by Shanghai Municipal Engineering Design General Institute, East
China Investigation and Design Institute and Research Center for Involuntary
Resettlement, Wuhan University compare the two schemes from the aspect of
environmental impact and resettlement. The environmental assessment indicates, the
circuitous line scheme brings huge impact on the Zoo, and the disadvantages outweigh
the advantages. The resettlement research indicates the direct line has more advantages
in terms of the amount of displaced persons and relocation, and resettlement cost.
What’s more, the direct line scheme makes it possible to combine this transport project
with the old city reconstruction project and “village within the city” reconstruction
project. Therefore, it is suggested to adopt the direct line scheme. See Attachment 1 for
detailed demonstration of direct line and circuitous line schemes for North Mid Ring.
Table 1-3 Comparison of line schemes for North Mid Ring Road
Scheme Line design Length Transport capacity
Connection with road network
Impact on environment
Circuitous line
Going along the north side of Jian River, crossing Jiefang Road, Jian River Road, Railway Beitongpu line, passing the entrance of the Zoo, going round Wohu Mountain, turning from the north to the east side, and connecting with Taihang Road under planning
11.75km
The section along Wohu Mountain is of low linear is standard, the nodes are difficult to cope with, and the pressure
It can be connected with expressway passing Dongshan through Zhangzitou Overpass. It is about 1.9~3.0km away from Beida Street, of low capacity to diffluence the traffic on Beida Street, of long distance to Taihang Road.
The section along the Jian River is of great impact on environment of Wohu Mountain Park, and residents of Wohu Mountain. It is of great difficulty in
9
on pre-Zoo Road is increased.
land acquisition.
Direct line
Going along the north side of Jian River, crossing the Jian River at the river bend, crossing Taiyuan Mine Machine Factory, Fire Proof Material Factory, etc, going northward along one side of Taiyuan Carshop in Xiangtang East Street, crossing Xiangtang Village, crossing Jianhe Road, Railway Beitongpu Line, going northward in the direction of Beigedong Street, passing Jin’an Chemical Plan, and connecting with Taihang Road under planning.
9.95km� 1.8km shorter than the
circuitous line
It is of high linearis standard, of great attraction to traffic along the road, and the road capacity is increased.
It can be connected with expressway passing Dongshan through Yingchun Street and Yangjia Yu Overpass. It is suggested to extend northward to the expressway to facilitate the connection between the speedway and the expressway. It is 1.2~1.6km from Beida Street. The distance between roads is reasonable, it is of obvious impact to diffluence traffic in Beida Street, and there is no circumambulation.
It mainly involves the relocation of plants and factories, and the reconstruction of “village within the city”. It is easier for relocation, and it will promote the development of Donggou.
As well, in the process of site selection for initial and terminal Stations and parking
and maintenance lost, the design institution puts forward two or three programs for each
initial and terminal Station and parking and maintenance and submits them to the
resettlement department and the environmental assessment department for field
exploration and physical survey. The site selection program will be determined
ultimately through comprehensive evaluation based on the opinions of different
departments.
For example, For Wohushan Initial and Terminal Station, the site in the original
program is located in Zhongjianhe Village in Xinghualing District, 70m away from the
main entrance of the zoo and 400m away from Jianhe Road, with superior geographic
location. However, this plot involves a large area of relocation. It is estimated that the
area of the buildings to be relocated is 8500� and 140 households with 430 members need to be resettled. Besides, this plot has a complicated property right, involving the
dwelling land of the staff of Taiyuan Iron and Steel, the dwelling land of the villagers of
Zhongjianhe Village, the dormitory of Taiyuan Earthquake Bureau and the staff quarter
of Taiyuan Slaughterhouse. After field exploration, the resettlement department
suggests adopting the comparative program. The site in the comparative program is
located in Zhongjianhe Village in Xinghualing District, 1500m away from the north
10
entrance of the Zoo and bordering on the streets on both sides, with superior location.
The land occupies is the collective land of Zhongjianhe Village, and now its use right is
held by Hengyihua Co., Ltd. and the refractory material plant. The land acquisition and
relocation involves the above-mentioned two companies and Zhongjianhe Village, and
the communication will be easier. It is estimated that the houses of 2238.8� will be relocated and no relocation of private houses is involved. The optimized program
reduces the quantity of resettlement to a great extent.
1.5.2 Measures to be adopted during implementation
When relocation cannot be avoided, to mitigate impact of the construction, the
following measures shall be adopted:
Collect basic information, make an in-depth analysis of local socio-economic
status, make feasible Resettlement Action Plan to ensure that that the displaced persons
would not suffer from loss due to the implementation of the project.
Encourage the participation and supervision of the public. Strength internal and external monitoring, set up highly efficient feedback
mechanism and channels, minimize the period for the disposal of information to ensure
the timely solution of problems occurring in the construction. Notify in advance
displaced persons, arrange sites for relocation, compensate the loss of displaced persons,
minimize the idling period, and provide jobs for employees of affected enterprises.
During the relocation, get help and support from local governmental authorities to ensure the smooth implementation of resettlement, and to reduce the pressure and loss
of displaced persons, institutions and enterprises.
1.5.3 Measures to be adopted during the construction
The following measures are to be adopted during the construction to mitigate
impact:
Reasonably make construction plan and arrange traffic. For example, when reconstructing or expanding road, when possible, the construction is carried out on one
half of the road, the other half is reserved for traffic, and adjust the traffic within a small
area, minimizing the impact of construction on the surrounding environment and traffic
order. When excavating, all the factors shall be taken into full consideration. The
excavation, laying of pipelines and backfilling shall be finished in the shortest time
11
possible. For road crossing road with heavy traffic, the construction shall not be carried
out in rush hours (for example the construction is carried out during the night to ensure
smooth traffic flow in the day). Barbarian work manner is to be avoided. It is forbidden
to destroy existing pipelines. Warning signs, signals and leading marks shall be set up
for vehicles and pedestrians. After the completion of the construction, the site shall be
cleared and opened to the traffic.
Dredged spoil shall be timely carried out, and over loading is forbidden. Measures shall be taken to avoid spilling along the road. Before driving out, the tires of vehicles
shall be flushed by high pressure water to avoid pollution of roads. The entrance of the
construction site shall be timely cleaned.
In the area within 200 m away from residences of the civilians, the construction is forbidden from 22 o’clock in the evening to 8 o’clock the next morning. And equipment
with low noise shall be chosen for construction. For construction at night that affects
citizens, measures shall be taken to eliminate or control noises, and temporary sound
barrier equipment shall be set up around the construction site or near the residences of
the civilians.
The construction unit shall timely contact with local environmental sanitation
department to clear and clean the wastes in the construction sites to make it clean and
tidy.
1.6 Preparation and Progress of the Project
According to the demand of the preparation of resettlement work, the deadline of
the construction of North Mid Ring, Taihang Road and related projects is the 20th day of
December in 2006, and the deadline of the construction of parking and maintenance lots
and initial and terminal stations involved in the project of public transport is the 20th day
of July in 2007. The status quo of the construction deadline is taken as the reference of
resettlement survey. The Resettlement Action Plan for Taiyuan Urban Transport Project
is prepared according to inventory of properties for relocation, socioeconomic
investigation of displaced persons, data of technical feasibility report. The economic
and technical feasibility report was finished in May 2008 and approved in August 2008,
and estimated to be appraised and approved by the World Bank in September 2009. The
loan agreement with the World Bank is to be signed in March 2009, the initial design is
12
to be finished in December 2008, and the detailed construction design is to be finished
and the project is to be started in March 2009.
1.7 Ownership of the Project
The owner of the project is Taiyuan Municipal People’s Government.
1.8 Implementation Schedule of the Project
See table 1-4 for project preparation and implementation schedule.
Table 1-4 Schedule for the preparation and implementation of the project
Items Time
Approval of Feasibility Report August 2008
Passing the project appraisal September 2008
Finishing initial design December 2008
Finishing detailed design for construction
March 2009
Implementation of the project March 2008 – March 2011
1.9 Approval for Land Use and Relocation
See table 1-5 for the schedule for applying approval for land use and relocation
Table 1-5 Schedule for applying for approval for land use and relocation
Items Time Examined and approved by
Initiation of the project November 2007 Shanxi Provincial
Development and Reform Commission
Applying for land use December 2008 State Council
Approving the Resettlement Action Plan
February 2009 Shanxi Provincial
People’s Government
1.10 Laws Related to Compensation Rate
This Resettlement Action Plan is formulated by the Project Resettlement Office
after fully negotiating with resettlement office of each district in Taiyuan and affected
households and institutions based on intensive investigation and research, and the
13
resettlement policies therein are recognized by each relevant government department of
Taiyuan City. After the Resettlement Action Plan passes the appraisal of the World
Bank and is approved by the people’s government of Shanxi Province and Taiyuan City,
the policies and standards therein will be strictly conformed to during the
implementation. Taiyuan Municipal People’s Government acknowledges that all
policies and standards stated in this Resettlement Actions Plan will be in conformity
with the policies of the World Bank concerning involuntary resettlement as well as with
relevant laws and regulations of the People’s Republic of China and Shanxi Province
and keep in line with relevant local policies and standards of Taiyuan City.
14
2�Project Impact Analysis
2.1 Definition of Project Impact
Physical survey scope of project impact is the red line scope of road planning
determined according to design organization of project planning, generally with 25m of
both sides of road center, namely, all affected things within the range of 50m width
belong to survey scope. In some regions, design organization of project planning carried
out local optimization and slightly adjusted project impact scope according to
topographic characteristics, engineering requirements and actual situation. Because the
project is still in the process of optimization design while the physical survey for the
resettlement is carried out, design organization of the project may carry out optimization
design to the route and the date on land acquisition and relocation may be further
adjusted. Resettlement office will modify and perfect Resettlement Action Plan
according to adjustment data. Meanwhile, any significant change of project impact will
be reported to the World Bank prior to implementation and the reasons for the change
will be explained. This resettlement plan also applies to the extra displaced persons,
affected enterprises and institutions, affected villages and others.
Project impact is defined as follows:
(1) Permanent occupied land: all varieties of cultivated land and uncultivated land
to be used permanently within the red line range of the project. Cultivated land mainly
includes paddy field, dry land, vegetable land, pond, fruit and tea garden, nursery, and
so on; uncultivated land mainly includes barren hill, barren land, economic forest,
timber line, housing site, and so on.
(2) Temporary land acquisition: all varieties of land to be used temporarily during
construction period, which may be recovered after construction.
(3) Relocated buildings: all buildings within the red line range of the project,
mainly including brick and concrete house, brick and wood house, simple house, etc.
According to the proprietary rights of the buildings, they may be classified as private
buildings and buildings of enterprises institutions. According the purposes of the
buildings, they may be classified as private dwelling, houses used by enterprises and
institutions, shops, and etc.
15
(4) Affected attachments to the ground: attachments to the ground within the red
line range of the project, mainly including pool, fence, well, tomb, fruit tree, terrace, etc.
(5) Affected public facilities: public facilities and public service facilities within
the range of project impact.
(6) Affected family households: any family household with land, buildings and
attachments to the ground within the red line range of the project or affected directly.
(7) Affected communities: any community with land, buildings and attachments to
the ground within the red line range of the project or affected directly.
(8) Affected enterprises and institutions: any enterprise or institution with land,
buildings and attachments to the ground within the red line range of the project or
affected directly.
(9) Displaced persons of the project: all the members of affected family households
and affected enterprises and institutions form displaced persons of the project.
(10) House with title: house having total or part of house property rights or having
no formal certificate on house property rights but having construction documents and
credence issued by governments or relevant governments of all levels.
(11) Illegal Constructure: constructures having no relevant certificates issued by
any house property department or land department and being built without permission,
and temporary building being built with the approval of relevant department but
exceeding service period specified in the document.
(12) Affected labor: labors working in affected shops, enterprises or institutions or
engaging in agricultural production on the land for acquisition.
(13) Affected renter: all the persons leasing affected buildings for living or
business operation, based on the contracts.
(14) Vulnerable groups: vulnerable groups refer to social groups in the residents
that are easy to be harmed, lack of capability of responding social change, and stand in
the unfavorable status due to their weak social participation capability, social security,
disability, poverty and others, mainly including: solitary and widowed elder, female
single-parent family, orphan, poor family, handicapped person and patent, and etc.
16
2.2 Project Socioeconomic Survey
From December 2006 to January 2007, displaced persons of The World Bank
Financed Taiyuan Urban Transport Project and environment evaluation department and
Center for Resettlement Research of Wuhan University successfully made the
resettlement survey in the regions affected by North Mid Ring, Taihang Toad and
related projects together with the great help of resettlement offices of Yingze District,
Xinghualing District, Jiancaoping District, Wanbolin District and Xiaodian District. The
resettlement survey consisted of two parts: one was survey of objects in land acquisition
and relocation that maybe involved in project construction; the other was survey of
social economy of the displaced persons and enterprises and institutions.
In accordance with the involuntary resettlement policies of the World Bank, the
land acquisition and relocation caused by the resettlement spots used for building
resettlement houses for the families relocated due to the project will be brought into the
impact scope of the project and the unified resettlement policies will be implemented.
With respect to the resettlement spots, because at present only the written proposal of
location is completed and the approximate location is determined, the accurate position
needs to be detailed and the conditions for carrying out detailed survey on land
acquisition and relocation have not been equipped with. Therefore, the Project
Resettlement Office works out specific Resettlement Framework for the resettlement of
resettlement spots in accordance with the policies and standards in line with this project,
and will prepare the detailed Resettlement Plan for the resettlement spots after the
conditions are equipped with.
The resettlement survey may be divided into three parts as follows:
1�Literature survey
a. Statistic of social economy of Taiyuan city and the project area;
b. Local laws and regulations of the state, Shanxi province and Taiyuan city related
to land acquisition and resettlement.
2�Social economy background survey
a. Survey of basic circumstances of affected families and vulnerable families in the
area;
b. Public opinions and suggestions;
17
c. Survey of basic circumstances of affected villages in the area: population, labour
force, industrial structure, and plantation and etc.
3�Survey of affected objects in land acquisition and relocation
a. Circumstance of land acquisition: position, category and area;
b. Relocated buildings and other attachments to the land: position, category, and
quantity and property rights;
c. Category and quantity of various public facilities;
d. Basic circumstances and affected situation of enterprises and institutions.
The survey gathered the impact situation of 2193 affected families, 112 affected
enterprises and institutions, 114 shops and one smallware market, carried out sampling
survey on the basic situation of 347 families, initially knew basic impact resulted from
the project and provided information for compiling of Resettlement Action Plan.
Meanwhile, the survey also gathered statistical information of social and economic
development of affected areas in recent years, relevant policies and local laws and
regulations relating to land acquisition and house relocation in affected areas, important
cases about land acquisition and relocation in recent years and basic information about
market exchange of Taiyuan estate. The information can be regarded as the reference to
establishment of the compensation policy.
Towards the end of July 2007, after the design program for initial and terminal
stations and parking and maintenance lots of the project of public transport was put
forward, the Project Resettlement Office organized the personnel of the resettlement
consulting organization and the public transport company to carry out resettlement
survey on four initial and terminal stations and two parking and maintenance lots,
holding complete resettlement information and laying the foundation of perfecting the
Resettlement Action Plan.
18
Picture 2-1 Survey personnel explore requisitioned land on the spot.
Picture 2� 2 Survey personnel measure the relocated houses on the spot.
2.3 Impact of Land Acquisition and Relocation
According to physical survey data and statistics for the resettlement implemented by
Leadership Office of Taiyuan Urban Transport Project and Center for Involuntary
Resettlement Research, Wuhan University together, the basic data of the impact of land
acquisition and relocation for the project are as follows:
Affected administrative units: as to Taiyuan urban transport project, there are six
affected districts, i.e. Wanbolin District, Jiancaoping District, Xinghualing District,
Yingze District, Xiaodian District and Jinyuan District, 15 affected offices(township
ships) and 37 villages (communities) in Taiyuan City.
Affected by relocation:
Total area of relocated buildings: 423508.92.1�Households and persons affected by relocation: 2193 households and 7752
persons, including 606 rural households with 2518 persons, and 1587 urban households
with 5234 persons.
Relocated private houses: 1208 households and 4407 persons, including 606 rural
households with 2518 persons, and 602 urban households with 1889 persons. Total area
of relocated private houses is 154784.82� . And there are 985 urban households with
3345 persons who live in enterprise or unit-owned dormitories will also be relocated.
Affected enterprises and institutions:total number is 112 and the area is
266563.4� .
19
114 shops and one small ware market with 652 employees will be affected. The
area of relocation is 19351.2� , including 2160.7� for private shops and 17190.5 for
enterprises and units.
Affected by land acquisition:
Acquired collectively-owned land: 795.47mu, including cultivated land of
93.75mu.
Persons affected by the acquisition of collectively-owned cultivated land
acquisition: 11 households, 48 persons and 25 labors.
Acquired collectively-owned uncultivated land: 701.73mu.
Acquired state-owned land: 1320mu including 144mu of state-owned agricultural
land and 1176mu of state-owned land for construction.
Detailed impacts see 2-1a and 2-1b.
20
Table2-1a Summary of the impacts of land acquisition and relocation of Taiyuan Urban Transport Project
No. item name involved arealandrequisitioned(mu)
area ofrelocation(� )
Number of affectedenterprisesandinstitutions
number ofaffectedshops
householdsrelocated/persons
I. North Mid Ring
JiaocaopingDistrict,XinghualingDistrict
104.41 262838.89 55 38 1652/5660
II. Taihang Road
XinghualingDistrict, YingzeDistrict, XiaodianDistrict
508.56 144909.03 53 69 536/2071
III. Project of publictransport 182.5 15961 4 7 5/21
1Beiying Parking andMaintenanceLot
Xiaodian District 2356 0 0 0
2Nanhan Parking andMaintenanceLot
Wanbolin District 121.5 4500 1 4 0
3Beiyan Initial andTerminal Station
Jinyuan District 15.7 1190 0 0 0
4Zoo Initial andTerminal Station
XinghualingDistrict
21 4580 0 0 0
5Helaowan Initial andTerminalStation
Wanbolin District 10.8 3335 3 3 5/21
6Yingxin StreetInitial andTerminal Station
JiancaopingDistrict
13.5 0 0 0 0
22
Table 2-1b Taiyuan Urban Transport Project Land Acquisition and Resettlement
impacts
Detailed list of impacts Total amount
of land(mu) Total HH affected by land Acqu.
Total HH/persons displaced
businesses affected
Shops affected
Roads Network component 1RUWK�0LGGOH�5LQJ�5RDG�Jiaocaoping district 82.71 2 120/546 29 10 Xinghualing district 21.7 0 845/2766 6 19 Wanbolin district 0 0 0 20 07DLKDQJ�5RDG�Xinghualing district 157.29 2 67/332 21 39 Yingze district 292.24 2 145/616 30 39 Xiaodian district 59.03 1 26/126 2 0Public Transport component ;LQMLDQ�6WUHHW�%XV�ODQH�6 interchanges 0 0 0 0 0Street construction 0 0 0 0 0%XV�GHSRWV�Nanhan 121.5 0 0 1 4Beiying 90 0 0 0 0%XV�WHUPLQDOV�Yingxin 13.5 2 0 0 0He Lao Bay 10.8 0 5/21 3 3Zoo 21 0 0 0 0Beiyan 15.7 2 0 0 0Automated vehicle location and dispatching system Bus bays stops (10 proposed, including Xinjiang Street Busbay) Traffic Safety and Management component (impacts for these addressed under roads network component) Resettlement Sites Market 0 0 0 0 0Schools 3 0 0 0 0
Enterprises (112 total) 0 0 0 0 0Private shops (114 total) 0 0 0 0 0Linked Roads
Waliu road connection 75 1 57/314 2 0Fen River Bridge and interchanges 200 0 0 5 0Taihang Road Connection 40.5 0 0 3 0Dump Sites
5 existing dump sites will be used, there will be no relocation and land acquisition
The impacts of this table are permanent land acqusition and relocation, and the impacts of tempoary land use are not available at present stage,they will be provided with the progress of design.
23
2.4 Impact of Land Acquisition for the Project
According to the survey and statistics, total area of the land requisitioned for the
project is 2124.77mu, including 795.47mu of collective land and 1320mu of state-
owned land. Among the collective land requisitioned, cultivated land is 93.74mu, and
non-cultivated land is 701.73mu; among the state-owned land requisitioned, the land
used for construction is 1176mu, and the state-owned agricultural land and wood land is
144mu.
2.4.1 Acquisition of rural collectively-owned land
North Mid Ring
North Mid Ring Road is involved in the acquisition of rural collectively-owned
land in two districts (Jiancaoping and Xinghualing) and four villages (Dadongliu,
Xiaodongliu, Xiliu and Xiangtang). The total area of land acquired is 104.41mu,
including 35.1mu of cultivated land and 69.31mu of uncultivated land.
Taihang Road
Taihang Road is involved in the acquisition of rural collectively-owned land in
three districts (Xinghualing District, Yingze District and Xiaodian District). The total
area of land acquired is 508.56 mu, including 29.44 mu of cultivated land, 5.79%, and
69.31mu of uncultivated land, 94.21%. See Table 2-2 for the details of the acquisition of
collectively-owned land of each affected village.
Analysis on survey data shows that, cultivated land affected by Taiyuan urban
transport project mainly is housing site and three-barren land, and the area of cultivated
land is 93.74mu. According to the field survey of survey personnel of Center for
Involuntary Resettlement Research, Wuhan University, for this, there are two reasons as
follows:
Firstly, the scope of project impact is peri urban, around which less cultivated land
exists.
Secondly, on Taihang Road, where acquisition of collectively-owned land centers,
the land acquired has been controlled in Xiaozaogou, Daochanggou, San’ergou,
Baergou in Xinghualing District according to Taiyuan urban planning. The land used
for construction on Taihang Road has been controlled for many years.
24
64.54mu of cultivated land acquired for the project mainly is fruit garden and
greenhouse, contracted by seven peasant family households, among which, two are in
Dadongliu Village in Jiancaoping District, two in Xiaozaogou Village in Xinghualing
District, one in Longbao Village in Xiaodian District and two in Dianpo Village
inYingze District. Property rights of 1.46mu and 0.8mu green houses belong to Baergou
Village and Daochanggou Village in Xinghualing District, but at present, one is used by
a military organization (490 Army). There are 30 members and 16 labors in these seven
households.
Project of public transport
In the project of public transport, Helaowan Initial and Terminal Station occupies
the land of 10.8mu, all of which is non-cultivated land; Nanhan Depot occupies the land
of 121.5mu, all of which is non-cultivated land; Beiying Depot occupies the land of
90mu, which is the wood land of the Base of Stud Plot of the Provincial Forestry
Department; Beiyan Initial and Terminal Station occupies the cultivated land of 15.7mu,
involving 2 contracting households; Yingxin Street Initial and Terminal Station
occupies the land of 13.5mu, which is the fruit garden contracted by two households;
Zoo Initial and Terminal Station occupies the land 21mu, all of which is non-cultivated
land. Total area of the cultivated land requisitioned for the project of public transport
is29.2mu, involving 4 families, 18 persons and 9 labors.
Table 2-2 Types and quantity of collectively-owned land requisitioned for Taiyuan
Urban Transport Project
Cultivated Land (mu) Uncultivated Land (mu)
District
Office Village
Fruit Garden
GreenHouse
Total Hosing Site
Three-barren Land
Total Total
I. North Mid Ring Dadongliu
35.1 0 35.1 0 0 0 35.1
Xiliu 0 0 0 14.85 0 14.85 14.85 Xiaodongliu
0 0 0 32.76 0 32.76 32.76 Jingcaoping
Huifeng
Sub-total
35.1 0 35.1 47.61 0 47.61 82.71
Xingh Yangji Xiangt 0 0 0 21.7 0 21.7 21.7
25
ualing ayu ang Village
Subtotal of North Mid Ring 35.1 0 35.1 69.31 0 69.31 104.4
1II. Taihang Road Xiaodian
Beiying
Longbao
2.03 0 2.03 21.75 35.25 57 59.03
Daochanggou
0 0.8 0.8 5.13 5.02 10.15 10.95
Baergou
0 1.46 1.46 4.48 54.22 58.7 60.16
San’ergou
0 0 0 17.7 28.2 45.9 45.9
Xiaozaogou
10.2 7.2 17.4 11.25 11.63 22.88 40.28
Xinghualing
Yangjiayu
Sub-total
10.2 9.46 19.66 38.56 99.07 137.63157.29
Dianpo 7.75 0 7.75 18.75 2.94 21.69 29.44
Dongtaibao
0 0 0 0 16.5 16.5 16.5
Haojiagou
0 0 0 40 20 60 60
Haozhuang
0 0 0 66.3 25.2 91.5 91.5
Wangjiafeng
0 0 0 42 52.8 94.8 94.8
Yingze Haozhuang
Sub-total
7.75 0 7.75 167.05 117.44 284.49292.24
Subtotal of Taihang Road
19.98 9.46 29.44 227.36 251.76 479.12 508.5
6III. Project of public transport 13.5 15.7 29.2 0 153.3 153.3 182.5
Beiying Parking and Maintenance Lot
0 0 0 0 0 0 0
Nanhan Parking and Maintenance Lot
0 0 0 0 121.5 121.5 121.5
Beiyan Initial and Terminal Station
0 15.7 15.7 0 0 0 15.7
Zoo Initial and Terminal Station
0 0 0 0 21 21 21
Helaowan Initial and Terminal Station
0 0 0 0 10.8 10.8 10.8
Yingxin Street Initial and Terminal Station
13.5 0 13.5 0 0 0 13.5
Total 68.58
25.16
93.74 296.67 405.06 701.73 795.47
Data Source: Survey on Land Acquisition and Relocation of Taiyuan Urban Transport
26
Project.
2.4.2 Acquisition of state-owned land
Besides 795.47mu of rural collectively-owned land, 1320mu of state-owned land
will also be requisitioned for the construction of the project, including 1176mu of the
stated-owned land used for construction and 144mu of state-owned agricultural land and
wood land. The state-owned agricultural land and wood to be requisitioned now belongs
to Horticultural Research Institute of Shanxi Academy of Agricultural Science and the
Base of Stud Plot of the Provincial Forestry Department.
2.5 Relocation
According to the resettlement survey, total area of various buildings to e relocated
for Taiyuan Urban Transport Project is 423508.92� , including: 1) 154784.82� of private houses, 2) 266563.4� of the buildings of enterprises and institutions, and 3) 2160.7� of various private shops.
2.5.1 Relocation of private houses
According to the survey date, the private houses to be relocated for Taiyuan Urban
Transport Project involve 1208 households and 4407 persons. Total area of the houses
to be relocated is 154784.82, including 97.44 of steel-concrete structure,
118357.3 of brick-concrete structure, 23893.95of brick-wood structure, 3832.79
of earth-wood structure and 10763.3of simple structure. See Attached Table 1 for the
details of area and structure distribution of private houses to be relocated.
North Mid Ring
Total area of private houses to be relocated for the subproject of North Mid Ring is
89953.19 , including 63404.14 of brick-concrete structure, 20500.04of brick-
wood structure and 6049.01of simple structure. On North Mid Ring Road, affected
families include rural families and community residents, 965 households with 3312
persons, including 602 households of community residents with 1889 persons and 363
rural households with 1423 persons.
Taihang Road
Total area of private houses to be relocated for the subproject of Taihang Road is
63656.63 , including 97.44 of steel-concrete structure, 54190of brick-concrete
27
structure, 2982.11 of brick-wood structure, 3832.79 of earth-wood structure and
2554.29 of simple structure. All of the private houses to be relocated for the
subproject of Taihang Road belong to rural families, involving 238 households and
1074 persons.
Project of public transport
Total area of private houses to be relocated for the project of public transport is
3335 , including 763.2 of brick-concrete structure, 411.8of brick-wood structure
and 2160 of simple structure. All of the private houses to be relocated for the project
of public transport belong to rural families, involving 5 households and 21 persons.
It is needed to be pointed out that, the private houses to be relocated for the
projects of North Mid Ring, Taihang Road and public transport involve 1208
households and 4407 persons, the abovementioned data doesn’t include the houses
belonging to enterprises and institutes to be relocated which are occupied by 985
households and 3345 persons, among which, North Mid Ring involves 687 households
and 2384 persons and Taihang Road involves 298 households and 997 persons. See
Attached Table 2 for the details of the distribution. The number of such houses to be
relocated is included in their institutions. Therefore, in total, there are 2193 households
with 7752 persons affected by the relocation for Taiyuan urban transport project.
2.5.2 Relocation of buildings of enterprises and institutions
According to resettlement survey data, 112 enterprises and institutions are involved
in relocation of buildings of 2266563.4� for Taiyuan Urban Transport Project. Seen from the distribution of these enterprises and institutions, North Mid Ring Road affects
55 ones, Taihang Road affects 53 ones, and the project of public transport affects 4
ones, among which, 24 ones are in Wanbolin District, 29 in Jiancaoping District, 30 in
Yingze District, 27 in Xinghualing District, and 2 in Xiaodian District. See Table 2-3
for quantity and distribution of buildings of enterprises and institutions to be relocated.
See Attached Table 3 for quantity of buildings of each enterprise or institution to be
relocated.
Table 2-3 Buildings of enterprises and institutions to be relocated( )
House Total
28
Steel and concrete
Brick and concrete
Brick and wood
Simple
Jiancaoping (29 enterprises and institutions)
422.8 65069.1 2089.3 10563 78144.2
Wanbolin (20 enterprises and institutions)
2511 18348 3291.1 1079 25229.1
Xinghualing (6 enterprises and institutions)
0 62962 4632.4 1918 69512.4
56 enterprises and institutions on North Mid Ring
2933.8 146379.1 10012.8 13560 172885.7
Xinghualing (21 enterprises and institutions)
8776.2 9366.1 14.1 669.8 18826.2
Yingze (30 enterprises and institutions)
44874.8 2026.3 186 8767.2 55854.3
Xiaodian (2 enterprises and institutions)
1537.2 4966 0 68 6571.2
53 enterprises and institutions on Taihang Road
55188.2 16358.4 200.1 9505 81251.7
4 enterprises for the project of public transport
0 4500 4876 3050 12426
4 enterprises in Wanbolin District
0 4500 4876 3050 12426
Total: 112 enterprises and institutions
58122 167237.5 15088.9 26115 266563.4
2.5.3 Illegal buildings affected by the project
According to the survey, the area of illegal buildings to be relocated for Taiyuan
Urban Transport Project is 50619.61� , including 5697.85� of private unlicensed buildings and 44921.76� of unlicensed buildings owned by enterprises and institutions. According to the survey data, among the 5697.85� illegal private buildings, 2800 � are
used by 54 households as residential houses who have no other places to live.See
Attached Tables 4 and 5 for the distribution of unlicensed buildings.
2.5.4 Affected attachments
The physical survey for the resettlement shows that attachments affected by land
acquisition for Taiyuan Urban Transport Project mainly include:
29
fence, well, tree, greenhouse, terrace, etc.; those affected by relocation mainly
include electricity meter, water meter, telephone, air-conditioner, screen wall and
others. According to the survey data, all the attachments affected by the project mainly
are: 1763 telephones, 1711 closed circuit televisions, 14 air-conditioners, 3485
electricity meters, 2766 water meters, 291 screen walls, fence of 28280.2� , 2950 big timber trees, 119 small timber trees, 573 fruit trees with fruit, 358 fruit trees without
fruit, greenhouse of 19304.05� , 20 wells, 74 pools, and terrace of 12165� . See Attached Tables 6 and 7 for attachments of private family households and enterprises
and institutions affected by Taiyuan Urban Transport Project.
2.5.5 Affected shops
According to the survey, there are 114 shops with 297 empolyees will be affected
and the area of the buildings to be relocated is 3511.2� . Among the affected shops, 32
shops with1350.5� of buildings belongs to enterprises and collective institutions, and 82
shops with 2160.7� of buildings are private.107 shops will be affected for North Mid
Ring and Taihang Road,. For public transport project, 3 shops in Helaowan are
affected, and 4 shops are affected by Nanhan Depot and leased from Waliu Village and
there are 8 employees.See Attached Table 8 for the shops affected by Taiyuan Urban
Transport Project..
2.5.6 Affected smallware market
There is on smallware market to be relocated for the project of Taihang Road. The
market is located in Haojiagou Village, Haozhuang Townshipship, Yingze District, and
is divided into two rows, named Yiwu Street and Baogou Street, respectively. The
building area is 4500� . There are 180 shops and 360 employees totally, and daily smallwares are mostly sold.
2.6 Affected Vulnerable Groups
2.6.1 Determination of affected vulnerable groups
Disadvantaged groups refer to ones of displaced persons of the project that are
easiest to be hurt and have no ability of adapting to the changes brought by the project
construction. Disadvantaged groups are mainly divided as follows:
30
Lonely elderly: the single elderly over 65 years old and without the person fulfilling statutory duty of maintenance.
Single-parent family: the household of the family is single and has under aged
child.
Orphan: the children without parents and are lower than 16 years old.
Poor family: the urban families with Collecting Certificate of Lowest Living Security of Taiyuan Urban Residents, and rural poor households that have been
specially determined.
The disabled: the persons, in psychology, physiology or body constitution,
having some tissue or function lost or off-normal, or the ability of participating some
activity in the normal way lost totally or partially (subject to the holding of Disabled
Person Certificate of the People’s Republic of China).
The poor family only having one dwelling house and with dwelling area per capita less than 11.2� .
The determination of vulnerable groups is carried out in accordance with relevant
policies and regulations and on the basis of field survey. In the implementation process,
resettlement office will confirm it through door-to-door interview, neighboring
interview and proving of community resident committee.
2.6.2 Affected families of vulnerable groups
According to the survey, among displaced persons, there are 109 families with
vulnerable groups and 364 members. Vulnerable groups mainly in Yangjiayu and
Huifeng, and the total number is 104 households with 342 members. See Table 2-4 for
the distribution of affected vulnerable groups.
Table 2-4 Distribution of affected vulnerable groups
District Office Community (Village)
Number of Households
Population
Xinghualing Yangjiayu Xiangtang Village 46 111
Yingze Haozhuang Haojiagou 3 7
Jiancaoping Gucheng Senyuannan Street 2 15
Jiancaoping Huifeng Dadongliu 11 37
Jiancaoping Huifeng Xiaodongliu 23 92
Jiancaoping Huifeng Xiliu 24 102
31
Total 109 364 Data Source: Survey on Land Acquisition and Relocation for Taiyuan Urban Transport
Project
2.7 Affected Infrastructures
The infrastructures affected by the project mainly include low-voltage illumination
electric pole, high-voltage power transmission electric pole, transformer, and etc. See
Table 2-5 for the types and quantities of affected infrastructures of each district and
county.
Table 2-5 Types and quantities of affected infrastructures
District High-voltage electric pole
Low-voltage electric pole
PHS signal tower
Transformer
Jiancaoping 0 114 0 3
Xinghualing 14 397 0 2
Wanbolin 2 61 0 1
Yingze 1 114 0 6
Xiaodian 0 28 1 1
Total 17 714 1 13 Data Source: Survey on Land Acquisition and Relocation of Taiyuan Urban Transport Project.
2.8 Impact of Land Acquisition and Relocation for linked
Projects
2.8.1 Impact of land acquisition for linked projects
According to the survey, the land of 75mu will be acquired for extension line of
Waliu Road, including 2.18mu nursery, 2.94mu uncultivated land and 69.88mu housing
sites.
For the project of the bridge crossing Fenhe River, state-owned land of 200mu will
be requisitioned.
State-owned agricultural land of 40.5mu will be acquired for extension line of
Taihang Road.
32
2.8.2 Impact of relocation for linked projects
According to the survey, the total area of buildings to the relocated for two linked
projects is 56604.55� , including 52173� brick and concrete structure, 3638.55� brick and wood structure, 601� earth and wood structure and 192 � simple structure.
Between two linked projects, only Waliu Road is involved in the relocation of
private houses. According to the survey, the houses of 57 households in Dongshe
Village need to be relocated for Waliu Road, and the total area is 20767.55� , including 18153 brick and concrete structure, 2432.55� brick and wood structure and 182� earth and wood structure.
The buildings of ten enterprises and institutions need to be relocated for two linked
projects, and the total area is 35418� .
Table 2-6 Quantities of buildings of enterprises and institutions to be relocated for
linked projects(m2)
Line Institution
Brick &Concrete
Brick &Wood
Earth &Concrete
Simple
Total
Shanxi Academy of Agricultural Science
0 48 0 0 48
Xudong Village Collectivity
5057 22 0 80 5159 Extension line of Taihang Road
Shannxi Material Storage & Transportation and Distribution Corporation
1400 1136 0 112 2648
Dongshe Villager Committee
1328 0 0 0 1328 Extension line
of Waliu Road
Aluminium Industry Company
0 0 0 0 0
Forest Park of Jiancaoping District 10728 0 144 0 1087
2Housing Company of Taiyuan Iron and Steel
3208 0 0 0 3208
Fazhong Farm 2475 0 265 0 2740
Shanxi Fodder Supervision Institute 7849 0 10 0 7859
Bridge crossing
Fenhe River
Taiyuan Binxi Gass Reinforced Plastics Plant
1975 0 0 0 1975
33
Total 34020 1206 419 192 35873
Note: the extension line of Waliu Road is only involved in the terrace of 570� of Dongshe Aluminium Industry Company and doesn’t affect other buildings.
Three commercial shops changed from dwelling houses at the start point of the
extension line of Waliu Road is affected, and their property rights belong to the private.
See Table 2-7 for details.
Table 2-7 Shops affected by linked projects
No.
Address Shop name Owner name
Building structure
Area (� )
1Start point of Walu Road in Dongshe Village
Meiling Kitchen Ware
Lv Junsheng
Brick & Concrete
832
2Start point of Walu Road in Dongshe Village
Jinlongmen Chaffy Dish
Li Jianli Brick & Concrete
448
3Start point of Walu Road in Dongshe Village
Ruiyun Auto Repair
Jia Xishou Brick & Concrete
144
Besides, other attachments affected by the linked projects include 807.5� fense, 15 big timers, 18 small timers, 13 tombs, 334� greenhouse and 570� terrace.
34
3. Analysis on Socioeconomic Impact of Project
3.1 General Introduction to Socioeconomic Development of
the Regions Affected by the Project
Taiyuan City, as the provincial capital of Shanxi province, is the core city of energy
and heavy chemical industry of China and has been a city with perfect infrastructures,
abundant economic foundation and convenient and developed traffic and
communication through over fifty-year development after the establishment of new
China. In 2006, gross value of production of the whole city was 89.3 billion yuan, local
fiscal revenue was 5.695 billion yuan, and per-capita GDP was 26107 yuan. Per-capita
net income of peasants was 4402 yuan, and per-capita disposable income of town
dwellers was 10476 yuan.
By the end of 2006, gross population of Taiyuan city is 3716 thousand, including
permanent population of 3403.8 thousand with domicile and provisional flow and
temporary resident population of 312. Permanent populations include agricultural
population 1015 thousand, 29.81%, and nonagricultural population of 2389 thousand,
70.19%. Population density is 491 persons/k� , and the population per household is 3.7. Wanbolin is the west gate of urban area of Taiyuan City and is one of core urban
areas of Taiyuan, with the area of 305k� , population of 532 thousand, rural population of 76 thousand and population density of 1871/k� . There are 13 sub-district offices, 84
community resident committees, 3 townships, 63 villager committees and 79 natural
villages under the government of Wanbolin District. In 2006, gross value of local
production was 15.108 billion yuan including added value of the first industry of
533030 thousand yuan, that of the second industry of 10440 million yuan, and that of
the third industry of 4620 million yuan; financial revenue was 530 million yuan and per-
capita net income of the peasants was 5852 yuan.
Jiancaoping District is at the north end of Taiyuan City, with the largest west-east
width of 26km and the largest north-south distance of 22km. Fenhe River passes
through the district from south to north. The total area is 285.6k� , including urban construction area of 32.4k� . There are 9 sub-district offices, 53 community resident
committee, 5 townships, 90 villager committees and 101 natural villages under the
35
government of Jiancaoping District. At the end of 2006, the gross population of
Jiancaoping District is 346 thousand, including rural population of 101 thousand. In
2006, gross value of local production was 12.51 billion yuan including added value of
the first industry of 109850 thousand yuan, that of the second industry of 10080 million
yuan, and that of the third industry of 2337 million yuan; financial revenue was 397
million yuan and per-capita net income of the peasants was 3920 yuan.
Xinghualing District is in the northeast of Taiyuan City, and is the political center
of Taiyuan, the provincial capital of Shanxi Province, and many provincial and
municipal party, political and military institutions, such as the People’s Government of
Shanxi Province, Political Consultative Commission of Shanxi Province, Military Area
Command of Shanxi Province, Municipal Committee of the C.P.C of Taiyuan City, the
People’s Government of Taiyuan City and so on, are set in this district. The total area is
170k� , including urban construction area of 32k� . There are 10 sub-district offices, 99
community resident committees, 2 townships, 44 villager committees and 54 natural
villages under the government of Jiancaoping District. At the end of 2006, the gross
population of Xinghualing District is 546 thousand, including rural population of 33
thousand. In 2006, gross value of local production was 11.79 billion yuan including
added value of the first industry of 16950 thousand yuan, that of the second industry of
4058 million yuan, and that of the third industry of 7716 million yuan; financial revenue
was 606 million yuan and per-capita net income of the peasants was 5381 yuan.
Yingze District is on the east bank of Fenhe River and in the center of urban area.
The district connects to Xiaodian District in the south and Xinghualing District in the
north, borders upon Yuci City and Shouyang County in the east and lies across Fenhe
River from Wanbolin District. With the superior geographic location, Yingze District
becomes the political center, traffic hinge and the window for external communication
as well as the commercial center of the provincial capital of Shanxi Province. The total
area is 117k� . There are 6 sub-district offices, 89 community resident committees, 1
town, 29 villager committees and 54 natural villages under the government of Yingze
District. At the end of 2006, the gross population of Yingze District is 504 thousand,
including rural population of 19 thousand. In 2006, gross value of local production was
15.89 billion yuan including added value of the first industry of 11000 thousand yuan,
that of the second industry of 2680 million yuan, and that of the third industry of 13210
36
million yuan; financial revenue was 714 million yuan and per-capita net income of the
peasants was 5081 yuan.
Xiaodian District is in the southeast of Taiyuan City and at the north end of
Jinzhong Basin. It marches with Yuci District of Jinzhong City in the east, connects to
Qingxu County in the south, lies across Fenhe River from Jinyuan District in the west
and borders upon Yingze District at Nanneihuan Street. The total area is 295k� , including built-up area of 24.7k� . There are 6 sub-district offices, 63 community
resident committee, 3 townships, 86 administrative villages and 98 natural villages
under the government of Yingze District. At the end of 2006, the gross population of
Xiaodian District is 509 thousand, including rural population of 131 thousand. In 2006,
gross value of local production was 12.19 billion yuan including added value of the first
industry of 241220 thousand yuan, that of the second industry of 4185 million yuan, and
that of the third industry of 7631 million yuan; financial revenue was 609 million yuan
and per-capita net income of the peasants was 5780 yuan.
Jinyuan District is in the southwest of Taiyuan City. It starts from Yijingdong
Street and marches with Wanbolin District in the north, connects to Gaojiabao Village,
Yaocun Townshipshop in the south, borders upon Qingxu County and Gujiao City in
the southwest and lies across Fenhe River from Xiaodian District in the east. The total
area is 287k� , 20.6% of total area of Taiyuan City. At the end of 2006, the gross population of Jinyuan District is 650 thousand, including nonagricultural population of
184.6 thousand and agricultural population of 113 thousand. There are 3 townshipships,
3 sub-districts and 18 community resident committees under the government of Jinyuan
District. In 2007, gross value of local production was 4.497 billion yuan , financial
revenue was 290 million yuan and per-capita net income of the peasants was 5782 yuan.
Table 3-1 General situation of socioeconomic development of the regions affected by
Taiyuan Urban Transport Project (2006)
Affected regions
Land area
Population (10000)
Gross value of
1st industry
2nd industry
3rd industry
Annual average
Per-capita net
37
(km1) local production (100million yuan)
(%) (%) (%) wage of town employee (yuan)
income of rural resident (yuan)
Xiaodian 295 50.6 121.9 1.98 34.33 63.69 12042 5780
Yingze 117 47.97 158.9 0.07 16.87 83.06 10684 5081
Xinghualing 170 53.01 117.9 0.14 34.42 65.44 10048 5381
Jiancaoping 285 35.54 125.1 0.88 80.58 18.55 11304 3920
Wanbolin 305 57.05 151.08 0.35 69.10 30.55 10998 5852
Jinyuan 288 18.46 31.45 6.30 67.06 26.65 14232 4776
Data source: Calculated according to Taiyuan Socioeconomic statistical yearbook 2006.
3.2 General Situation of Affected Villages
The resettlement survey is carried out on the general situation of the affected
villages. Except for Longbao Village and Xudong Village of Beiying Office in Xiaodian
District that are affected slightly and survey data of which are not collected, the general
situations of other thirteen villages are as shown in Table 3-2.
According to survey data as shown in Table 3-2, the following analysis is carried
out on the socioeconomic development of affected villages:
Firstly, except for San’ershu village and Xiaozaogou Village in Xinghualing
District, living standard of villagers in other affected villages is relatively high, higher
than average level of net income of peasants of Xinghualing District.
Secondly, for villagers in these villages, basic income sources are second and third
industries. Agricultural production has a quite low proportion in total income. Social
labors also have a low proportion of agricultural production.
Thirdly, because here belongs to outskirt, per capita cultivated area of these
villages is small, and some villages even have no agricultural land. Therefore, land
acquisition for the project has no substantial impact on agricultural production.
According to the survey, cultivated land acquired for the project mainly is
distributed in Xiaozaogou Village and Dadongliu Village, 17.4m for the former and
35.1mu for the latter.
17.4mu cultivated land acquired in Xiaozaogou village includes 10.2mu fruit
garden and 7.2mu green house, separately contracted by families of Mr. Zhang and Mr.
Li. Totally, there are 165mu fruit garden and green house in Xiaozaogou Village,
38
occupying little cultivated land. In the opinions of Mr. Zhang and Mr. Li, if land
compensation can be paid to them, there is no great negative impact on their incomes.
In name, two families contract 35.1mu fruit garden in Dadongliu Village, but the
garden has been desolated for recent years. The survey finds that the fruit garden has
almost been a dumping place, and the contractor hardly has any incomes from it.
Therefore, the acquisition of the fruit garden has no substantial impact on actual
incomes of these two families.
39
Table 3-2 General situation of villages affected by land acquisition and relocation for Taiyuan Urban Transport Project
District Office Village Number ofHouseholds Population Per-capita
net income
Gross socialproduction value(10000 Yuan)
1st Industry(10000 Yuan)
2nd Industry(10000 Yuan)
3rd Industry(10000 Yuan)
Persons engagedof social labors
1st
Industry2nd
Industry Tertiary Cultivatedland (mu)
Xinghualing Yangjiayu Xiaozaogou 337 916 4857 4070 NA NA NA 613 NA NA NA 165
Xinghualing Yangjiayu Daochanggou 348 876 6350 3540 NA NA NA 630 NA NA NA 0
Xinghualing Yangjiayu Baergou 306 804 6500 2800 0 1920 880 549 0 150 399 0
Xinghualing Yangjiayu San’ershu 355 908 3650 4500 0 2050 2450 580 0 120 460 36
Xinghualing Yangjiayu XiangtangVillage
3680 10847 6800 4990 0 0 4990 8672 0 0 3586 0
Yingze Haozhuang Dongtaibao 892 2690 6000 NA NA NA NA 1357 NA NA NA 0
Yingze Haozhuang Haozhuang 586 1563 7283 66000 0.3 6026 59974 6201 1 584 5616 0
Yingze Haozhuang Wangjiafeng 815 2156 5364 4677 329.6 3450 900 800 60 300 440 700
Yingze Haozhuang Dianpo 383 1276 5345 3190 230 2990 970 783 83 460 240 804.99
Yingze Haozhuang Haojiagou 516 1400 6252 19000 5.9 2500 16494 893 30 260 603 55.8
Jiancaoping Huifeng Dadongliu 546 1708 4066 5700 110 1380 4210 1170 210 230 730 80
Jiancaoping Huifeng Xiliu 690 2122 4328 902 0 835 11486 895 NA NA NA 0
Jiancaoping Huifeng Xiaodongliu 556 1883 5235 2430 250 1960 220 1046 400 546 100 720
Data source: survey of social economy for Taiyuan Urban Transport Project, 2007
40
3.3 Analysis on Basic Information of Affected Families
In order to deeply understand basic information of affected families and provide
reasonable resettlement program with reference, during the process of resettlement
survey, for affected private households, sampling survey is carried out by the proportion
of 20%, and survey form of family information is to be completed (see Attachment for
survey from). Survey results involve basic information of 347 families with 1465
members in Jiancaoping District, Xinghualing District and Yingze District with
concentrated displaced persons. See Table 3-3 for basic characteristics of the
investigated.
Table 3-3 Basic characteristics of displaced persons of Taiyuan Urban Transport
Project
Unit: household, person, %
Characteristics Jiancaoping District
Xinghualing District
Yingze District
Total
Households 74 198 75 347 Population 378 751 336 1465 Sex Male 54.37 50 51.34 51.43 Female 45.63 50 48.66 48.56 Total 100 100 100 100 Age 0-16 18.65 16.94 25.89 19.4 16-60 75.79 68.75 62.05 69.0 60- 5.56 14.31 12.05 11.5 Total 100.00 100.00 100.00 100.0 Average Age 32.96 37.54 33.2 35.37 Nationality Han 100 99.6 98.36 99.49 Hui 0 0.2 1.34 0.41 Man 0 0.2 0 0.1 Total 100 100 100 100 Education level Illiteracy 4.74 8.49 5.88 6.96 Primary school 14.22 10.14 19.41 13.17 Junior middle school 48.82 42.45 49.41 45.59 Senior middle school 22.75 25 20.59 23.48 College and above 9.48 13.21 4.71 10.43 Other 0 0.71 0 0.37
Total 100 100 100 100 Marital status Unmarried 24.17 17.92 15.88 19.13
41
Currently married 72.99 72.17 77.65 73.54 Bereft of spouse 1.42 4.95 4.71 3.98 Divorced 0 0.94 0.59 0.62 Others 1.42 4.01 1.18 2.73 Total 100 100 100 100 Occupation status Worker 22.73 23.64 21.90 22.89 Agriculture 7.27 0.00 17.14 6.84 Cult., edu. and sanitation
40.00 13.94 31.43 26.32
Institutions 6.36 4.24 5.71 5.26 Others 23.64 58.18 23.81 38.68
Total 100.00 100.00 100.00 100.00
Unemployed Student at school 29.90 17.14 9.43 18.08 Doing the housework 36.08 21.63 29.25 26.56 Doing nothing 25.77 22.04 25.47 23.66 Retired 3.09 19.18 2.83 11.83 No working ability 5.15 7.35 4.72 6.25 Others 0 12.65 28.30 13.62
Total 100.00 100.00 100.00 100.00
In order to understand dwelling situation of affected families, the survey on types,
building time, property rights, sanitary condition and energy utilization of dwelling
houses of affected families is carried out. See Table 4-4 for results.
Table 3-4 Dwelling situation of affected families of Taiyuan Urban Transport Project
Unit: %
Type Jiancaoping
Xinghualing
Yingze Total
Building 83.67 7.63 56.00 34.35 Single story building 16.33 91.60 44.00 65.22 Others 0 0.76 0 0.43 Total 100.00 100.00 100.00 100.00
Buildingup time Jiancaoping
Xinghualing
Yingze Total
15 years ago 4.08 82.44 26.00 53.48 10-15 years ago 67.35 16.03 10.00 25.65 5-10 years ago 10.20 0.76 16.00 6.09 Recent five years 18.37 0.76 48.00 14.78 Total 100.00 100.00 100.00 100.00
House property Jiancaoping
Xinghualing
Yingze Total
Self-owned 97.96 46.56 96.00 68.26
42
Leasing the public or the institution
2.04 53.43 4.00 31.73
Total 100.00 100.00 100.00 100.00
Having separate toilet or not Jiancaoping
Xinghualing
Yingze Total
Yes 93.88 12.21 78.00 43.91 No 6.12 87.78 22.00 56.08 Total 100.00 100.00 100.00 100.00
Kitchen Jiancaoping
Xinghualing
Yingze Total
Exclusive use 100.00 94.66 94.00 95.65 Sharing 0 1.53 0 0.87 No 0 3.82 6.00 3.48 Total 0 100.00 100.00 100.00
Energy Jiancaoping
Xinghualing
Yingze Total
Coal 75.51 87.02 68.00 80.43 Oil liquefied gas 24.49 10.69 28.00 17.39 Piping coal gas 0 0.76 4.00 1.30 Others 0 1.53 0 0.87 Total 100.00 100.00 100.00 100.00
Seen from survey results, dwelling condition of affected families in Xinghualing
District is weaker, which is expressed in the following three aspects: firstly, 91.6% of
families live in single story buildings; secondly, 82% of houses were built 15 years ago;
thirdly, 50% of families have no property rights of the houses they live in. In
consideration of the large quantity of affected families in Xinghualing District and most
samples for survey in Xinghualing District, Xinghualing needs special attention for
dwelling houses of future resettlement.
For household income of rural residents, nonagricultural incomes are their main
sources. Among Jiaocaoping District, Xinghualing District and Yingze District with
concentrated displaced persons, the peasants in Xinghualing District have low incomes.
Urban residents mainly rely on salary incomes. Seen from the districts, incomes of
urban residents in Jiancaoping District are higher than that in Xinghualing District and
Yingze District, main reason for which is that some affected urban residents in
Jiancaoping District are working in Taiyuan Iron & Steel (Group) Co., Ltd. and this
company is an enterprise with outstanding economic benefits in Taiyuan.
Table 3-5 Incomes of affected families
Unit: Yuan
43
Jiancaoping District
Xinghualing District
Yingze District
� �
Rural residents Farming income 163.27 7.63 200 82.6358 Local non-farm income
10967.35 6772.76 14353 9321.277
Outland non-farm income
204.08 1913.74 784 1306.169
Other incomes 3408.16 2566.65 3196 2881.824 Total 14742.86 11260.78 18533 13591.91 Urban residents Wage income 16956 15072 16026 15677.52 Operating income
816 970 305 791.36
Other incomes 1004 229 240 394.17 Total 18776 16271 16571 16863.05
As to dwelling space, according the data supplied by Taiyuan Bureau of Statistics,
at the end of 2006, per capita dwelling space in urban area is 12� . Rural residents have larger dwelling spaces. In 2006, per capita dwelling space of rural residents in
Jiancaoping District is 25� , in Wanbolin District 28� , in Xinghualing District 31� , in Yingze District 30� , and in Xiaodian District 31� . The results of resettlement survey are generally in line with the above data. According to survey results, dwelling spaces
of over 80% of rural residents are more than 80� , while that of 24% of urban residents are less than 402. The resettlement of these families is a key of future resettlement.
Table 3-6 Proportion of dwelling spaces of affected families
Unit: % Area Rural residents Urban residents
� 30 0 23.96
30� 60 2.16 24.32
60� 80 15.14 39.43
� 80 82.70 12.29
Total 100 100.00
44
3.4 Analysis on Family Information of Affected Vulnerable
Groups
Seen from special information of families of vulnerable groups, family members
may be disabled, weak and sickly or have no regular income sources. See Attached
Table 9 for special information of 109 vulnerable families.
The impact of land acquisition and relocation on vulnerable families faces two
difficulties: firstly, the capital for buying new houses is not enough; secondly, house
relocation and transition needs the support of manpower. This needs special attention
during the process of resettlement.
3.5 Impact on Ethnic Minorities and Social Gender
According to census information supplied by Taiyuan Bureau of Statistics, there
are 46 nationalities including Han, Man, Hui, Yi and others, among which, the
population of Han nationality is over 99%. According to socioeconomic survey for
resettlement, 99.49% of displaced persons belong to Han nationality, and there is no
community with concentrated ethnic minorities within impact scope of Taiyuan Urban
Transport Project. Therefore, the problem about the impact on ethnic minorities doesn’t
exist.
According to sampling survey of resettlement organization, 48.5% of displaced
persons are female. Generally speaking, educational level of women in affected regions
is relatively low. Education level of most rural women is below junior high school, and
illiterate and semi-illiterate women have a higher proportion. According to sampling
survey, 8% of women are illiterate or semi-illiterate; 24% have accepted education in
primary school, 54% have studied in junior high school, 11% graduated from senior
high school or secondary technical school, and only 23% have accepted higher
education.
The impact on employment of displaced persons is mainly in affected enterprises
and institutions. In the enterprises and institutions with production and business being
not affected, the employment of women is not affected by the project. For the
enterprises with production and business being affected, resettlement office will give
45
priority to the benefits of female employees during the recovery and resettlement of
these enterprises.
As to the impact of relocation, 1834 households will obtain better dwelling
conditions. For the women bearing most of labor service of the families, improvement
of dwelling condition and environment may reduce their labor burden.
Seen from overall impact of the project, the construction of the project will
significantly improve urban transport situation of Taiyuan. For the women more relying
on urban public transport, the project will provide convenience for the transport of
women and improve the quality of women’s life and this is a positive impact.
46
4. Law Framework and Policies The plan and implementation of the settlement for Taiyuan urban transport project
will strictly follow relevant law framework and policies of the People’s Republic of
China, Shanxi province and Taiyuan city (as site of the project), and also will
completely comply with the World Bank’s policies about involuntary resettlement.
4.1 Main Law Framework and Policies of Resettlement
4.1.1 Relevant laws and provisions enacted By the Central Government
Land Administration Law of the People’s Republic of China implemented in Jan.,
1999, revised and put in force on the 28th in Aug., 2004.
Law of the Peoples Republic of China on the Administration of the Urban Real
Estate put in force on the 1st in Jan., 1995.
Administrative Regulations on the Urban Houses Relocation put in force on the
1st in Nov., 2001.
Guiding Comments on the Estimate for Urban Houses Relocation put in force on
the 1st in Jan., 2004.
The State Council's Decision on Deepening Reform and Managing Strictly Land,
issued by the State Council on the 21st, Oct., 2004.
Notice of the State Council on Relevant Issues about Intensifying Land Control,
issued by the State Council on the 31st in Aug., 2006.
Real Right Law of the People’s Republic of China put in force on the 1st of Oct.,
2007
4.1.2 Statues and policies enacted by the People’s Government of Shanxi Province and
related departments
Implementation Measures for Land Administration Law of the People’s Republic
of China in Shanxi Province, put in force on the 26th in Sept., 1999.
Statues for Urban Houses Relocation in Shanxi Province passed on the 27th in
Sept. 2003 and put in force on the 1st in Jan., 2004.
Management Approaches for Transforming Collectively-owned Land of ‘Urban
Villages’ into State-owned Land in Shanxi Province, put in force on the 28th in Aug.,
47
2003.
Appraisal Approaches to Compensation Price for Urban Houses Relocation in
Shanxi Province, issued on the 11th in Dec., 2004.
Temporary Approaches to Assistance and Compensation Rate for Urban Houses
Relocation in Shanxi Province, issued on the 11th in Dec., 2004.
4.1.3 Statues and policies enacted by the People’s Government of Taiyuan City and
related departments
Management Approaches for Urban Houses Relocation in Taiyuan City put in
force on the 1st in Nov., 2002.
Opinions on Accelerating Reconstruction of ‘Urban Villages’ in Taiyuan City put
in force on the 1st in Apr., 2004.
Measures on the Registration of Urban House Title passed on the 2nd in Apr.,
2003.
Notice on Relevant Problems as Short-term Resettlement Allowances and Moving
subsidy for Urban Houses Relocation put in force on the 1st in May, 2001.
Implementing Opinions on Base Price of Urban Storage Houses Exchange in
Taiyuan City put in force on Oct. 1, 2006.
4.1.4 The World Bank’s policies on involuntary resettlement
The World Bank’s OP4.12 of Involuntary Resettlement and Annex put in force on
the 1st in Jan., 2002.
The World Bank’s BP4.12 of Involuntary Resettlement and Annex put in force on
the 1st in Jan., 2002.
4.2 Summary of Main Law Framework and Policies
4.2.1 Summary of relevant national law framework
4.2.1.1 Summary of law framework on land acquisition
Land compensation belongs to the rural collective economic organization. However, compensation for attachments and young crops on the requisitioned land shall
be paid to their owners.
Resettlement subsidies for requisitioned land should adhere to be special fund for
48
special use and must not be diverted for others. Resettlement subsidies will be paid to
and managed by the rural collective economic organization or other units which take
charge of resettlement of displaced persons. However, as for those displaced persons
who don’t need unified resettlement, their resettlement subsidies will be paid
individually or used for insurance under their agreement. (Implementation Details of Land
Laws, No. 26 article.)
In requisitioning land, compensation should be paid according to original
purposes of the land requisitioned.
Compensation for requisitioned cultivated land includes compensation for land,
resettlement subsidies and compensation for attachments and young crops on the land.
Therein to, the compensation for land shall be 6-10 times of the average output
value of the three years preceding the requisition of the cultivated land. The resettlement
subsidies shall be calculated according to the number of agricultural population to be
resettled, which shall be counted by dividing the amount of cultivated land requisitioned
by the per capital land occupied of the unit whose land is requisitioned. The
resettlement subsidies for each agricultural person to be resettled shall be 4-6 times of
the average annual output value of the three years preceding the requisition of the
cultivated land. But the maximum resettlement subsidies per hectare of land
requisitioned shall not exceed 15 times of the average annual output value of the three
years prior to the requisition.
The standards for land compensation and resettlement subsidies for land
requisitioned shall be determined by various provinces, autonomous regions and
municipalities in reference to the land compensation and resettlement subsidies for
cultivated land requisitioned.
The compensation rate for attachments and young crops on the land requisitioned
shall be determined by various provinces, autonomous regions and municipalities.
Whereas the land compensation and resettlement subsidies paid according to the
provisions of the second paragraph of this article are not enough to maintain the original
level of living, the resettlement subsidies may be increased with the approval of the
people's governments of provinces, autonomous regions and municipalities. But the
combined total of land compensation and resettlement subsidies shall not exceed 30
times of the average output value of the three years prior to the requisition. (Land
49
Administration Law of the People’s Republic of China, No. 47 article)
Rural collective economic organizations shall make public to its members the receipts and expenditures of the land compensation for land requisitioned and accept
their supervision.
It is forbidden to embezzle or divert the land compensation and other related
expenses. (Land Administration Law of the People’s Republic of China, No. 49 article)
The term for the short-term use of land shall not usually exceed two years. (Land
Administration Law of the People’s Republic of China, No. 57 Article)
One rural household can own one housing site, with the area not exceeding the
standards provided for by provinces, autonomous regions and municipalities.
Construction of rural houses should conform to the general plans for the utilization
of land of townships (towns) and the original housing site and open spaces of villages
should be used as much as possible for building houses. (Land Administration Law of
the People’s Republic of China, No. 62 Article)
4.2.1.2 Summary of law framework on house relocation
Relocation households should be compensated and resettled by removers, and fulfill physical relocation within the prescribed term. (Administrative Regulations on the
Urban Houses Relocation, No. 4 Article)
Removers should implement house relocation within the scope and term
determined by the house relocation license. (Administrative Regulations on the Urban
Houses Relocation, No. 9 Article)
Compensation should be paid to the relocation households according to this statue unless removers dismantle unauthorized constructions and short-term buildings that
have passed the approval term. Appropriate compensation should be given if short-term
buildings are within the approval term. (Administrative Regulations on the Urban
Houses Relocation, No. 22 Article)
The way of compensating for relocation can be monetary compensation or
exchange of the property right. (Administrative Regulations on the Urban Houses
Relocation, No. 23 Article)
The sum of monetary compensation shall be determined by the appraisal price of real estate market on the basis of location, purpose and building area of relocated
houses. The specific measures shall be established by the people’s governments of
50
various provinces, autonomous regions and municipalities. (Administrative Regulations
on the Urban Houses Relocation, No. 24 Article)
As for the exchange of property right, removers and relocation households should calculate the compensation for relocated houses and the price of the exchanged houses,
and settle the price difference in term of the 24th article of this statue. (Administrative
Regulations on the Urban Houses Relocation, No. 25 Article)
With respect to relocation of houses for public utility, removers should rebuild them in the light of relevant law framework as well as requirements of city planning, or
pay monetary compensation. (Administrative Regulations on the Urban Houses
Relocation, No. 26 Article)
Removers should pay appropriate subsidies if the relocation of non-residential
houses causes production halts and business cessation. (Administrative Regulations on
the Urban Houses Relocation, No. 33 Article)
4.2.2 Summary of relevant statues and policies in Shanxi Province
4.2.2.1 Summary of statues and policies on land acquisition
Land administration departments of the people’s governments of cities and counties together with related departments shall draw out a specific plan on
compensating for requisitioned land and resettlement on the basis of the approved
scheme of land acquisition. Moreover, this plan shall be proclaimed at townships and villages as
sites of requisitioned land in order to hear opinions of the rural collective economic
organizations and peasants whose land has been requisitioned. And then this plan shall
be submitted to and obtain approval of the people’s governments of cities and counties,
and finally shall be implemented by land administration departments of the people’s
governments of cities and counties. The people’s governments at or above county level
shall mediate disputations on compensation rate, if failed; the people’s government that
approves land acquisition shall be the arbitration agency. The implementation of land
acquisition plan shall not be influenced by disputations on compensation for
requisitioned land and resettlement.
The units using the land should pay the sum of requisitioning land within three
months starting from the approval date of plan on compensation for requisitioned land
and resettlement. (Implementation Measures for Land Administration Law of the
People’s Republic of China in Shanxi Province, No. 26 article)
51
For the requisition of land, the units using land should pay compensation for land
in term of following standards.
(Error! Reference source not found.) For the requisition of capital farmland
(such as garden, pound, lotus pool), the compensation shall be 6-8 times of the average
output value of the three years prior to the requisition;
(Error! Reference source not found.) For the requisition of cultivated land
except for capital farmland, the compensation shall be 6-9 times of the average output
value of the three years prior to the requisition;
(Error! Reference source not found.) For the requisition of pasture, grassland
and so on, the compensation shall be 7 times of the average output value of the three
years prior to the requisition;
(Error! Reference source not found.) For the requisition of woodland, the
compensation shall be paid according to relevant regulations;
(Error! Reference source not found.) For the requisition of housing site, the
compensation shall be paid according to compensation rate for cultivated land;
(Error! Reference source not found.) For the requisition of leisure area,
wasteland, badlands, waste tidal land, the compensation shall be 3-6 times of the
cultivated land’s average output value of the three years prior to the requisition in the
village;
(Error! Reference source not found.) For the requisition of collectively owned
land for productive use, such as threshing floor and drying yard, the compensation shall
be paid according to compensation rate of their original purposes. (Implementation
Measures for Land Administration Law of the People’s Republic of China in Shanxi
Province, No. 27 article)
For the requisition of land, the units using land should pay resettlement subsidies in term of following standards.
(Error! Reference source not found.) For the requisition of capital farmland
(such as gardens, pounds, and lotus pools), the subsidies shall be 5-6 times of the
average output value of the three years prior to the requisition;
(Error! Reference source not found.) For the requisition of cultivated land
except for capital farmland, the subsidies shall be 4-5 times of the average output value
of the three years prior to the requisition;
52
(Error! Reference source not found.) For the requisition of pasture, grassland
and so on, the subsidies shall be 5 times of the average output value of the three years
prior to the requisition;
(Error! Reference source not found.) For the requisition of woodland, the
compensation shall be paid according to relevant regulations;
The maximum resettlement subsidies per hectare of land requisitioned prescribed
by preceding paragraphs shall not exceed 15 times of the average annual output value of
the three years prior to the requisition.
As for the requisition of housing site, leisure area, wasteland, badlands, waste
tidal land and threshing floor, no resettlement subsidies shall be paid. (Implementation
Measures for Land Administration Law of the People’s Republic of China in Shanxi
Province, No. 28 article)
The cultivated land’s average annual output value of the three years prior to the land requisition should be calculated according to following methods:
(Error! Reference source not found.) Persons whose land has been requisitioned
shall report planting conditions of the past three years to the villagers committee;
(Error! Reference source not found.) The people’s government of townships and
the villagers committee at the site or villages where lands have been requisitioned shall
make an announcement about the reported planting conditions and hear peasants’
opinions;
(Error! Reference source not found.) The people’s government of townships and
the villagers committee shall verify reports according to opinions of peasants;
(Error! Reference source not found.) The land administration department of the
people’s government at or above the county level at the site where lands have been
requisitioned, shall calculate the output, production value and average annual output
value of the three years prior to the land requisition on the basis of verified planting
conditions, the corresponding statistical forms of the statistical department at same
level, and the corresponding prices of crops.
As for other types of land, the calculation for average annual output value of the
three years prior to the land requisition shall refer to the preceding paragraph.
(Implementation Measures for Land Administration Law of the People’s Republic of
China in Shanxi Province, No. 29 article)
53
According to the 27th and 28th articles under this measure, resettlement subsidies
can be increased for displaced peasants whose living standard can’t be kept as before
even though they are provided with land compensation and resettlement subsidies upon
approval of the people’s government of Shanxi province. However, the maximum sum
of land compensation and resettlement subsidies shall not exceed 30 times of the
average annual output value of the three years prior to the requisition. (Implementation
Measures for Land Administration Law of the People’s Republic of China in Shanxi
Province, No. 30 article)
For the requisition of land, the units using land should pay compensation for attachments and young crops on the requisitioned land in term of following standards.
(Error! Reference source not found.) For attachments like buildings and
constructions, the compensation shall be converted into money, or attachments with
same quantity and quality;
(Error! Reference source not found.) For young crops, the compensation shall
not exceed the production of one season;
(Error! Reference source not found.) For transplanted trees, the compensation
shall include labor cost and expense for seeding loss; for irremovable trees, the
compensation shall be evaluated according to relevant regulations.
(Error! Reference source not found.) For fish, lotus root and pasturage, and etc.,
the compensation shall be evaluated according to relevant regulations.
No compensation shall be paid for trees and other attachments which are planted
and built in a rush after the announcement of compensation plan, as well as for
buildings and other facilities on the unlawfully occupied land. (Implementation
Measures for Land Administration Law of the People’s Republic of China in Shanxi
Province, No. 31 article)
4.2.2.2 Summary of statues and policies on house relocation
Removers are entitled to carry out relocation only on the condition of obtaining the license of houses relocation in accordance with the law. (Statues for Urban Houses
Relocation in Shanxi Province, No. 7 Article)
Removers should sign a written contract onhouses relocation, compensation and
resettlement with relocation households in accordance with the law.
54
As for the relocation of rented houses, removers should sign a written contract on
houses relocation, compensation and resettlement with relocation households and
renters.
Removers should put on records at houses relocation administration within 15 days
from the date on which the contract on houses relocation, compensation and
resettlement is signed. (Statues for Urban Houses Relocation in Shanxi Province, No.
14 Article)
In carrying out monetary compensation, the contract on houses relocation, compensation and resettlement should expressly specify the following�
(Error! Reference source not found.) Some basic conditions like the site,
building area, structural type, story, type, direction, and the way of obtaining the right to
the use of land;
(Error! Reference source not found.) Sum of the monetary compensation, the
payment method and term;
(Error! Reference source not found.) Term of physical relocation�(Error! Reference source not found.) Moving subsidy and other compensation
as well as payment method and term;
(Error! Reference source not found.) Solutions to breach of contract and
controversy;
(Error! Reference source not found.) Other items considered to be specified by
parties. (Statues for Urban Houses Relocation in Shanxi Province, No. 15 Article)
In carrying out exchanging the property right, except for the foregoing 6 items, the contract on houses relocation, compensation and resettlement should expressly
specify the following�(Error! Reference source not found.) The site, building area, structural type,
story, type, direction, and other conditions of houses of resettlement�(Error! Reference source not found.) Measures of physical relocation and
transition as well as term of transition period;
(Error! Reference source not found.) The site, building area, structural type,
story, water, electricity, gas, heater and other living facilities of houses during transition
period;
55
(Error! Reference source not found.).The way and time of calculating the price
difference of property right exchange;
(Error! Reference source not found.) Payment method and term of temporary
resettlement subsidies; (Statues for Urban Houses Relocation in Shanxi Province, No.
16 article)
The removers should carry out compensation and resettlement for relocation
households, whereas, who should fulfill physical relocation within the prescribed
period.
The compensation for relocation can be monetary compensation or the exchange of
property right. Relocation households can choose other ways of compensation in
accordance with the law unless otherwise stipulated by the state.
The sum of monetary compensation and the price of the exchanged house shall be
negotiated and determined by removers and relocation households on the basis of
location, usage, structural type, building area, decoration and fitment, and so on, if
failed; they shall be determined by the appraisal price of real estate market. The
evaluating method of price for houses relocation shall be established by the people’s
government of Shanxi province. (Statues for Urban Houses Relocation in Shanxi
Province, No. 20 Article)
No compensation for the following cases:
(Error! Reference source not found.) Unauthorized constructions and the short-
term buildings that have passed the approval term.
(Error! Reference source not found.) Newly-built houses, expanding and
rebuilding parts of houses after the confirmation and announcement of relocation scope.
(Statues for Urban Houses Relocation in Shanxi Province, No. 21 Article)
The building area and usage of the relocated house shall be affirmed by the ownership certificate, if which has no records about houses’ usage, which then shall be
determined by the house ownership registration administration department of city and
county (township) according to legal and effective documents provided by city planning
administration department. (Statues for Urban Houses Relocation in Shanxi Province,
No. 22 Article)
Removers should pay appropriate compensation for proprietors if the relocation
of non-residential houses causes production halts and business cessation, or for
56
relocation households, who have obtained business license in accordance with law
before the issue of relocation license for their residential houses in the scope of
relocation, on the basis of the running term of business and actual taxpaying. (Statues
for Urban Houses Relocation in Shanxi Province, No. 23 Article)
For the exchange of the property right of relocation households who enjoy the subsistence allowances for the urban poor and only have one relocated residential house
with the size of less than 45 � , removers should provide them with separate flats
exceeding 45 � as houses for resettlement. Price difference shall not be settled for the
area within 45 � of the house for resettlement. With respect to the price of left areas, it
will be settled by the price of real estate market. (Statues for Urban Houses Relocation
in Shanxi Province, No. 28 Article)
In carrying out monetary compensation for relocated houses, removers should pay relocation households resettlement compensation as well as moving subsidy, or
compensate moving subsidy for renters of relocated houses.
In carrying out the exchange of the property right of relocated houses, removers
should pay moving subsidy for relocation households or renters, who will be paid
moving subsidy again when moving from temporary houses to houses for resettlement.
(Statues for Urban Houses Relocation in Shanxi Province, No. 32 Article)
Standards for moving subsidy and temporary resettlement subsidies shall be prescribed by the people’s government of Shanxi province. (Statues for Urban Houses
Relocation in Shanxi Province, No. 33 Article)
Relocated houses shall be evaluated by institutions qualified for evaluating real
estate price according to guiding price of houses relocation. (Statues for Urban Houses
Relocation in Shanxi Province, No. 36 Article)
After signing the contract on relocation, compensation and resettlement, if relocation households or renters refuse physical relocation within the prescribed period,
removers shall apply for arbitrage to arbitration commission, or go to the People’s Court
and apply for carrying out relocation in advance during the period of lawsuit in
accordance with the law. (Statues for Urban Houses Relocation in Shanxi Province, No.
42 Article)
In case that removers cannot make an agreement on relocation, compensation and resettlement with relocation households, or with relocation households as well as
57
renters, parties concerned can apply for arbitrage to houses relocation administration at
the site where houses are relocated, or apply for arbitrage to the people’s government of
city, county (township) if the houses relocation administrative department is the
relocation household. (Statues for Urban Houses Relocation in Shanxi Province, No. 43
Article)
The people’s government of city, county (township) should make an announcement about guiding price for the appraisal of relocated house at different
locations at least once a year on the basis of the local replacement cost for various
houses and the real estate market’s price.
The construction (real estate) department together with the price department under
the people’s government of city, county (township) work out the guiding price for
evaluating relocated houses, and then proclaim in public after getting approval from the
people’s government of city, county (township). (Appraisal Approaches to
Compensation Price for Urban Houses Relocation in Shanxi Province, No. 8 Article)
Evaluation of the relocated houses includes classification appraisal and individual household appraisal.
Classification appraisal is firstly classifying relocated houses in the relocation
scope based on factors like location, structure and usage, and then determining the
average market price according to the classification.
Individual household appraisal is determining the market price of relocated houses
on the basis of location, usage, structure and building area, together with story, direction
and the brand-new degree, etc. (Appraisal Approaches to Compensation Price for
Urban Houses Relocation in Shanxi Province, No. 9 article)
Payment of moving subsidy and temporary resettlement subsidies is based on the building area recorded in the house ownership certificate and documents of relocated
houses. (Temporary Approaches to Assistance and Compensation Rate for Urban
Houses Relocation in Shanxi Province, No. 3 Article)
In carrying out monetary compensation for relocated houses, subsidies of 6-
month for temporary resettlement shall be paid in one-time; in carrying out the
accelerated resettlement, subsidies for temporary resettlement shall be paid according to
the contract. (Temporary Approaches to Assistance and Compensation Rate for Urban
Houses Relocation in Shanxi Province, No. 4 Article)
58
In carrying out the relocation of rented houses, moving subsidy and temporary resettlement subsidies shall be paid to relocation households, if who have terminated the
leasehold relationship with renters, or have resettled the renters. Otherwise, moving
subsidy and temporary resettlement subsidies shall be paid to renters if relocation
households cannot make an agreement on ending leasehold relationship with renters.
(Temporary Approaches to Assistance and Compensation Rate for Urban Houses
Relocation in Shanxi Province, No. 5 Article)
For the relocation of residential houses, standards for paying moving subsidy in one-time shall be as followings:
(Error! Reference source not found.) For the relocated house with building area
of less than or exceeding 30 � (including 30 � , same as follows) in the city, moving
subsidy of 200-300 Yuan or 7-10 Yuan per square meter shall be paid in one-time
respectively;
(Error! Reference source not found.) For the relocated house with building area
of less than or exceeding 30 � at the county (township), moving subsidy of 150-200
Yuan or 5-7 Yuan per square meter shall be paid in one-time respectively;
(Error! Reference source not found.) For the relocated house with building area
of less than or exceeding 30 � at the town, moving subsidy of 90-200 Yuan or 3-5
Yuan per square meter shall be paid in one-time respectively; (Temporary Approaches
to Assistance and Compensation Rate for Urban Houses Relocation in Shanxi Province,
No 6 Article)
For the relocation of non-residential houses, standards for paying moving subsidy
in one-time shall be as followings:
(Error! Reference source not found.) Subsidies of 15-20 Yuan/� , 20-25
Yuan/� , 10-12 Yuan/� and 15-20 Yuan/� shall be paid for relocated houses for commercial business, workshop, offices and storages respectively in the city.
(Error! Reference source not found.) Subsidies of 10-15 Yuan/� , 15-20
Yuan/� , 7-10 Yuan/� and 10-15 Yuan/� shall be paid for relocated houses for commercial business, workshop, offices and storages respectively at the county
(township).
(Error! Reference source not found.) Subsidies of 7-10 Yuan/� , 10-15 Yuan/� , 5-7 Yuan/� and 7-10 Yuan/� shall be paid for relocated houses for commercial
59
business, workshop, offices and storages respectively at the town. (Temporary
Approaches to Assistance and Compensation Rate for Urban Houses Relocation in
Shanxi Province, No. 7 Article)
In carrying out monetary compensation and the exchange of the property right of the complete department, moving subsidy shall be paid according to the 6th and the 7th
articles under this approach; In carrying out the exchange of the property right of the
forward delivery housing, relocation subsidies shall be paid twice according to the 6th
and the 7th articles under this approach. (Temporary Approaches to Assistance and
Compensation Rate for Urban Houses Relocation in Shanxi Province, No. 8 Article)
In case of relocation households who spend the transition period for themselves,
standards for paying short-term resettlement subsidies (transition subsidy) shall be as
followings:
(Error! Reference source not found.) For relocated houses with the building
area of less than or exceeding 30 � in the city, subsidies of 120-200 MRB or 4-6 Yuan /
� for short-term resettlement shall be paid monthly respectively.
(Error! Reference source not found.) For relocated houses with the building
area of less than or exceeding 30 � at the county (township), subsidies of 90-150 MRB
or 3-4 Yuan/� for short-term resettlement shall be paid monthly respectively.
(Error! Reference source not found.) For relocated houses with the building
area of less than or exceeding 30 � at the town, subsidies of 60-100 MRB or 2-4 Yuan /
� for short-term resettlement shall be paid monthly respectively. (Temporary
Approaches to Assistance and Compensation Rate for Urban Houses Relocation in
Shanxi Province, No. 9 Article)
As for the relocation of non-residential houses for business and production, or
residential houses which have got business licenses before the issue of relocation license
in accordance with the law, removers should pay economic compensation for relocation
households on the basis of last year’s rate-paying after the announcement of relocation,
which includes compensation for wage and business. The sum of business compensation
is calculated according to actual rental. No compensation shall be given if relocation
households pay no tax.
No compensation shall be paid to relocation households who have already obtained
business license, but still haven’t paid tax, or have ended operation and business before
60
the announcement of relocation. (Temporary Approaches to Assistance and
Compensation Rate for Urban Houses Relocation in Shanxi Province, No. 10 Article)
For the relocation of non-residential houses for business, which causes business
halts, the compensation rate shall be:
Wage compensation shall be paid to employees in one-time according to contracts
of labor, which are put on records at employment and social security departments, and
the standard of last year’s per capita monthly wage of this enterprise. Business
compensation shall be paid in one-time based on the last year’s monthly rate paying.
The term of compensation shall not exceed 6 months if the relocation completely
leads to business halts; the term of compensation shall not exceed 3 months if the
relocation partly leads to business halts. (Temporary Approaches to Assistance and
Compensation Rate for Urban Houses Relocation in Shanxi Province, No. 11 Article)
For the relocation of non-residential houses of production, which causes
production stop, the compensation rate shall be:
Wage compensation shall be paid to employees in one-time according to contracts
of labor, which are put on records at employment and social security departments, and
the standard of last year’s per capita monthly wage of this enterprise. Business
compensation shall be paid in one-time based on the last year’s monthly rate paying.
The term of compensation shall not exceed 6 months if the relocation completely
leads to business halts; the term of compensation shall not exceed 3 months if the
relocation partly leads to business halts; the term of compensation shall not exceed 6
months and the wage compensation shall be paid according to the half sum prescribed in
the No. 11 article if the relocation households are enterprises with unusual production.
(Temporary Approaches to Assistance and Compensation Rate for Urban Houses
Relocation in Shanxi Province, No. 12 Article)
For the relocation of residential houses which have obtained business licenses in
accordance with the law before the issue of relocation license, the compensation rate
shall be:
Wage compensation shall be paid to employees in one-time according to contracts
of labor, which are put on records at employment and social security departments, and
the standard of last year’s per capita monthly wage of this enterprise. No wage
compensation shall be given to those who haven’t signed labor contracts.
61
Business compensation shall be paid in one-time based on the last year’s monthly
rate-paying. No compensation shall be paid if relocation households haven’t pay tax.
The term of compensation shall not exceed 6 months if the relocation completely
leads to business halts; the term of compensation shall not exceed 3 months if the
relocation partly leads to business halts. (Temporary Approaches to Assistance and
Compensation Rate for Urban Houses Relocation in Shanxi Province, No. 13 Article)
For the relocation of non-residential houses for rent, which are under a contract
for rent and put on records at real estate management department at the site where
houses are relocated, the compensation rate for relocation households or renters shall
be:
(Error! Reference source not found.) The economic compensation equivalent to
3-month rent determined in the contract shall be paid to relocation households in one-
time.
(Error! Reference source not found.) The economic compensation shall be paid
to renters according to the compensation rate prescribed by No. 7, 10, 11 and 12 articles
under this method.
No compensation shall be given to relocation households and renters if they
haven’t signed a contract or put on records at real estate management department.
(Temporary Approaches to Assistance and Compensation Rate for Urban Houses
Relocation in Shanxi Province, No. 14 article)
4.2.3 Summary of relevant statues and policies in Taiyuan City
Compensation should be paid to the relocation households according to this statue unless removers relocate unauthorized constructions and short-term buildings that
have passed the approval term. Appropriate compensation should be given if short-term
buildings are within the approval term. (Administrative Regulations on the Urban
Houses Relocation in Taiyuan City, No. 20 article)
The compensation for relocation shall mainly be monetary compensation or the exchange of property right. Removers shall pay monetary compensation for the
relocation of attachments of houses which are not used for public utility.
(Administrative Regulations on the Urban Houses Relocation in Taiyuan City, No. 21
article)
62
The building area and usage of the relocated house shall be affirmed by records of the ownership certificate issued by the city’s real estate management department , if
which hasn’t indicated or recorded the usage, which then shall be determined by the
house property right records or planning department respectively. (Administrative
Regulations on the Urban Houses Relocation in Taiyuan City, No. 22 article)
The sum of monetary compensation shall be determined by the appraisal price of
real estate market according to location, usage, structure, and building area of relocated
houses. (Administrative Regulations on the Urban Houses Relocation in Taiyuan City,
No. 23 article)
The appraisal of houses relocation should be carried out by real estate appraisal
institutes at the corresponding levels. Removers should submit appraisal reports to
city’s real estate management department for records.
The time for the price appraisal shall be determined by the date on which the
relocation license shall be approved and issued. (Administrative Regulations on the
Urban Houses Relocation in Taiyuan City, No. 24 article)
As for the relocation of state-owned houses directly managed by governments or
voluntarily operated by units, renters enjoy the priority to purchase houses, and also
shall be compensated and resettled if they have already paid to property owners of
houses. Property owners who carry out the exchange of property right can resettle
renters in other places within planed cities, and also provide them with residential
houses that are not smaller than former houses. Renters who enjoy subsistence
allowances for the poor and cannot settle residential problem by themselves should be
resettled appropriately. (Administrative Regulations on the Urban Houses Relocation in
Taiyuan City, No. 28 article)
Removers should pay moving subsidy to relocation households or renters. During
the transition period, removers should pay short-term resettlement subsides for
relocation households or renters who arrange dwellings for themselves, but no subsidies
shall be paid if they accept the houses for turnover offered by removers. (Administrative
Regulations on the Urban Houses Relocation in Taiyuan City, No. 34 article)
Removers should pay removal subsides calculated by the building area of houses
with licenses for relocation households who have to move from the relocated houses.
For residential houses, the compensation shall be 10 YUAN per square meter. For non-
63
residential houses such as offices, houses for business as well as storage for production
and business, the compensation shall be 10 Yuan/, 20 Yuan/ , and 25 Yuan/
respectively. Notice on Relevant Problems as Short-term Resettlement Allowances and
Moving subsidy for Urban Houses Relocation, shall be put in force on the 1st in May,
2001.
4.2.4 The World Bank’s relevant policies on involuntary resettlement
Policies of involuntary resettlement are specified by OP4.12 and BP4.12 which are
operational polices and procedures of World Bank on involuntary resettlement, of which
main articles related to this project include:
Policy Objectives for Resettlement
1. Involuntary resettlement should be avoided where feasible, or minimized,
exploring all viable alternative project designs.
2. Where it is not feasible to avoid resettlement, resettlement activities should be
conceived and executed as sustainable development programs, providing sufficient
investment resources to enable the persons displaced by the project to share in project
benefits. Displaced persons should be meaningfully consulted and should have
opportunities to participate in planning and implementing resettlement programs.
Measures to Achieve Objectives
3. The resettlement plan or resettlement policy framework includes measures to
ensure that the displaced persons are:
(i) Informed about their options and rights pertaining to resettlement;
(ii) Consulted on, offered choices among, and provided with technically and
economically feasible resettlement alternatives; and
(iii) Provided prompt and effective compensation at full replacement cost for
losses of assets attributable directly to the project.
4. If it includes physical relocation, the resettlement plan or resettlement policy
framework includes measures to ensure that the displaced persons are:
(i) Provided assistance (such as moving subsidy) during physical relocation; and
(ii) Provided with residential housing, or housing sites, or, as required, agricultural
sites for which a combination of productive potential, advantages of location, and other
factors is at least equivalent to the advantages of the old site.
64
5. Where necessary to achieve the objectives of the policy, the resettlement plan or
resettlement policy framework also includes measures to ensure that displaced persons
are:
(i) Offered support after displacement, for a transition period, based on a
reasonable estimate of the time likely to be needed to restore their livelihood and
standards of living; and
(ii) Provided with development assistance such as land preparation, credit
facilities, training, or job opportunities.
Particular attention is paid to the needs of vulnerable groups among those
displaced, especially those below the poverty line, the landless, the elderly, women and
children, indigenous peoples, ethnic minorities, or other displaced persons who may not
be protected through national land compensation legislation.
Preference should be given to land-based resettlement strategies for displaced
persons whose livelihoods are land-based. These strategies may include resettlement on
public land, or on private land acquired or purchased for resettlement. Whenever
replacement land is offered, displaced persons are provided with land for which a
combination of productive potential, advantages of location, and other factors is at least
equivalent to the advantages of the land taken. If land is not the preferred option of the
displaced persons, the provision of land would adversely affect the sustainability of a
park or protected area, or sufficient land is not available at a reasonable price, non-land-
based options built around opportunities for employment or self-employment should be
provided in addition to cash compensation for land and other assets lost. The lack of
adequate land must be demonstrated and documented to the satisfaction of the Bank.
Payment of cash compensation for lost assets may be appropriate where (a)
livelihoods are land-based but the land taken for the project is a small fraction of the
affected asset and the residual is economically viable; or (b) active markets for land,
housing, and labor exist, displaced persons use such markets, and there is sufficient
supply of land and housing; or (c) livelihoods are not land-based. Cash compensation
levels should be sufficient to replace the lost land and other assets at full replacement
cost in local markets.
Displaced persons and their communities, and any host communities receiving
them, are provided timely and relevant information, consulted on resettlement options,
65
and offered opportunities to participate in planning, implementing, and monitoring
resettlement. Appropriate and accessible grievance mechanisms are established for these
groups.
In new resettlement sites or host communities, infrastructure and public services
are provided as necessary to improve, restore, or maintain accessibility and levels of
service for the displaced persons and host communities. Alternative or similar resources
are provided to compensate for the loss of access to community resources (such as
fishing areas, grazing areas, fuel, or fodder).
Patterns of community organization appropriate to the new circumstances are
based on choices made by the displaced persons. To the extent possible, the existing
social and cultural institutions of displaced persons and any host communities are
preserved and displaced persons’ preferences with respect to relocating in preexisting
communities and groups are honored.
4.3 Polices on Resettlement for This Project
According to the above mentioned national and local law framework as well as
related policies of the World Bank, and by considering the practical situation of areas
affected by the Urban Transport Project in Taiyuan city, and based on completely
negotiating with the affected masses, the resettlement office establish following policies
suited for this project on resettlement of displaced persons. After obtaining authorization
from the World Bank and approval from the People’s Government of Shanxi Province
and that of Taiyuan city, Resettlement Action Plan shall be implemented in the light of
following policies.
4.3.1 Methods for the acquisition of state-owned land
The compensation will be provided for the acquisition of the state-owned land used
for construction and state-owned agricultural land. The special methods are as follows:
with respect to the state-owned land used for construction, the compensation for the
land with buildings will be included in the compensation price of buildings and the land
compensation will not be listed separately; with respect to the state-owned land used for
construction obtained with compensation, the compensation for the land without
building will be provided at RMB 240 Yuan per square meter. The compensation for
66
state-owned agricultural land will be referenced to the compensation price of
collectively-owned land and be provided at RMB 50,000 Yuan per mu.
4.3.2 Compensation methods for the acquisition of collectively-owned land
With respect to the acquisition of collectively-owned land used for construction
obtained with compensation, the compensation for the land without building will be
provided at RMB 75 Yuan per square meter.
With respect to the acquisition of collectively-owned cultivated land, the
compensation for the land and young crops will be provided at RMB 50,000 Yuan per
mu. If the village collectivity exchanges land for the contractor of agricultural land
requisitioned, the compensation funds will be subject to the unified use of the village
collectivity. If no land is exchanged, 70% of the compensation funds will be paid to the
contractor of agricultural land requisitioned.
4.3.3 Compensation and resettlement for the relocation on state-owned land
In the relocation scope of the project, the person with valid and effective license
suffering from relocation may freely select the resettlement mode from monetary
compensation and exchange of property right. If monetary compensation is selected, no
house will be arranged.
Determination of use property and area of the house to be relocated: private
property will be subject to the certificate for housing ownership issued by relevant
administration; public property and institution property will be subject to the properties
and areas indicated in the certificates for the lease of house.
Determination of non-domestic house: refer to the house purpose stated in the
certificate for house ownership. If the house purpose is not stated in the certificate for
house ownership, be subject to the record in property right archives or the planning
permits of urban planning administration and local administration.
4.3.3.1 Monetary compensation
Monetary compensation rate and reference
In order to determine the amount of monetary compensation for the house to be
relocated, Taiyuan Financial Assessment Center and Taiyuan Construction Budget and
Settlement Auditing Center undertake evaluation of dwelling houses in the relocation
67
scope according to relevant national policies and codes concerning real estate valuation
and determine compensations prices of various building to the relocated for the project
under the principle of replacement cost.
Compensation prices: 2300 Yuan/� for frame construction, 1800 Yuan/� for brick-
concrete storied building, 1600 Yuan/� for single-story brick-concrete building, 1500
Yuan/� for brick-wood structure, and 1300 Yuan/� for earth-wood structure.
Amount and calculation formula of monetary compensation
1) Private dwelling house
Amount of monetary compensation = Property building area of house to be
relocated ×Unit price of market evaluation (Yuan/� ) 2) If monetary compensation is provided for public-property dwelling house
(public-property dwelling house under the direct administration of the municipality and
that under the administration of the institution itself), 30% of monetary compensation
will be paid to the relocate (property owner), and 70% will be paid to the leaseholder
(user).
Amount of monetary compensation = Property building area of house to be
relocated ×Unit price of market evaluation×70%
3) Non-domestic house
The calculation formula of the amount of monetary compensation for non-domestic
house is the same as the above.
If the property owner and the user of non-domestic house are different persons,
60% of monetary compensation will be paid to the user (leaseholder), and 40% will be
paid to the property owner (relocatee).
4) For the relocation of leased house, if the agreement between the relocatee and the
leaseholder cannot be achieved on canceling leasehold relation or the house involves
dispute, monetary compensation will not be provided, and the exchange of property
right will be carried out by the relocater for the relocatee.
5) For the relocation of the house with unclear property, the relocation will be
implemented upon the examination and approval of the house relocation administration.
Before the relocation, proof preserving should be handled in the notary department.
6) For the relocation of the house with mortgage rights, follow national laws and
regulations concerning guarantee.
68
7) For the relocation of the house used for public-welfare undertaking,
reconstruction will be carried out in accordance with relevant laws and regulations and
the requirements of urban planning, or monetary compensation will be provided. The
compensation price is subject to the evaluation.
4.3.3.2 Exchange of property right
The high-rise building subject to the exchange of property right is of frame
construction, and the multi-storied building is of brick-concrete structure. The types of
resettlement houses include 50� , 60� , 70� , 80� , 90� and 100� . If the exchange of property right is carried out for the relocation of private
dwelling house, provided that the building area of resettlement house equals the
building area of property right of relocated house, the price of structural difference will
not be settled if the structures are the same, and the price difference may be settled
according to individual evaluation price if the structures are different.
The preference of 10% will be provided for the resettlement house on the basis of property building area of the house to be relocated, and the relocatee pays expenses at
1800 Yuan/� for high-rise building and 1500 Yuan/� for multi-storied building.
If the relocatee require increasing resettlement area, the area increased less than
10� (including 10� ) will be settled at 2000 Yuan/� ; if the area increased is more than 10� and less than 20� (including 20� ), the construction cost will be settled at 2300 Yuan/� ; the extra part more than 20� will be settled as per the price of commercial housing at 3200 Yuan/� .
That is, building area of the house to be resettled = property building area of the
house to be relocated ×110%.
For the relocation of public-property and institutional-property dwelling houses,
in principle, the property right will be bought out. That is, for the part of property
building area of the original house, after the leaseholder buys the property right of the
house at 30% of market evaluation price, the exchange of property right will be carried
out. For the other part, the method for the expense settlement is the same as private
dwelling house.
For the relocation of non-domestic house, the resettlement will be carried out by
means of one relocation and one return. The exchange of property right may be carried
69
out for the right owner. The settlement between the prices of relocated house and
resettlement house should be subject to the individual evaluation price. The part
exceeding the resettlement area will be settled at the price of commercial housing, 6000
Yuan/� .
4.3.4 Compensation and resettlement for the relocation on collectively-owned land
For the relocation household on collectively-owned land, both resettlement modes
of monetary resettlement and exchange of property right are provided for free selection.
4.3.4.1 Monetary resettlement
In order to determine the amount of monetary compensation for the house to be
relocated on collectively-owned land, Taiyuan Financial Assessment Center and
Taiyuan Construction Budget and Settlement Auditing Center undertake evaluation of
dwelling houses in the relocation scope according to relevant national policies and
codes concerning real estate valuation and obtain evaluation prices as follows:
1800 Yuan/� for brick-concrete storied building, 1600 Yuan/� for single-story
brick-concrete building, 1500 Yuan/� for brick-wood structure, and 1300 Yuan/� for
earth-wood structure, and 300 Yuan/� for basement. The amount of monetary compensation is calculated according to the following
formula:
Amount of monetary compensation = Property building area of house to be
relocated ×Unit price of market evaluation (Yuan/� )
4.3.4.2 Exchange of property right
According to the documents provided by the office of Coordination and Leading
Group for the Reform of Village in City of Taiyuan, 14 villages (Dadongliu Village,
Xiliu Village, Xiaodongliu Village, Xiangtang Village, Xiaozaogou Village,
Daochanggou Village, Baergou Village, involved in land acquisition and relocation for
the project, San’ershu Village, Haojiagou Village, Haozhuang Village, Wangjiafeng
Village, Dianpo Village, Longbao Village and Dongtaibao Village) and Xudong
Village and Dongshe Village affected by linked projects have been brought into the
reform plan of village in city of Taiyuan. For the relocation of the houses in these
70
villages, except monetary resettlement freely selected by the villages, unified planning
and the construction of resettlement houses will be carried out.
If the building area of resettlement house equals the building area of licensed house
to be relocated, the price of difference will not be settled; the part exceeding the original
building area will be settled at the market price.
4.3.5 Resettlement of affected houses and shops of enterprises and institutions
For the compensation and resettlement of houses and shops of enterprises and
institutions to be relocated, multiple measures will be provided for free selection.
Resettlement modes include: monetary compensation and rehabilitation nearby; using
compensation funds for purchasing land freely and overall moving; the government
assists in providing land for building, and the enterprise recovers itself independently.
The monetary compensation rate for the relocated houses of enterprises and
institutions as well as shops shall be evaluated and put forward by the qualified real
estate appraisal company, and then shall be determined by the resettlement office after
negotiating with affected enterprises and institutions.
Evaluation price of non-domestic office occupancy: 1100 Yuan/� for frame construction, 900 Yuan/� for brick-concrete structure, 800 Yuan/� for brick-wood
structure, and 600 Yuan/� for earth-wood structure.
Evaluation price of business occupancy: 2680 Yuan/� for framed storied building, 2380 Yuan/� for brick-concrete storied building, 2030 Yuan/� for single-story brick-
concrete building, 1930 Yuan/� for brick-wood structure, and 1700 Yuan/� for earth-
wood structure.
Storage occupancy for production and business: 1100 Yuan/� for frame construction, 900 Yuan/� for brick-concrete structure, and 800 Yuan/� for brick-wood
structure.
Loss of salary and business caused by the relocation of enterprises and institutions
as well as shops shall be determined by the resettlement office after negotiating with the
displaced. Wage compensation shall be determined according to personnel scroll which
is about the enrolled workers (at work and paying labor insurance) of the relocated units
and is offered by the employment and social security departments. Business
compensation shall be paid based on the last year’s monthly rate-paying. The term of
71
compensation shall not exceed 6 months if the relocation completely leads to business
halts; the term of compensation shall not exceed 3 months if the relocation partly leads
to business halts.
The changed compensation caused by housing decoration or other factor should be
appraised and determined by the real estate appraisal company on the basis of market’s
principles.
Houses, which are registered as residential houses on the property right certificate,
but are used for business, shall be compensated according to the compensation standard
of residential houses, and also shall be paid 3-month business loss compensation on the
basis of rate paying attestation.
4.3.6 Moving subsidy and transition subsidy
1. Moving subsidy
1) Moving expenses for dwelling house shall be paid to the relocatee at 10 Yuan/�according to the property building area of the house to be relocated;
2) Moving subsidy for non-domestic house: 10 Yuan/� for office occupancy; 20 Yuan/� for business occupancy, and 25 Yuan/� for storage occupancy for production and business.
3) If the house to be relocated accepts monetary compensation, moving subsidy will
be paid once; if the house to be relocated accepts independent transition, moving
subsidy will be paid twice.
2. Transition subsidy
1) If the dwelling house to be relocated accepts exchange of property right, during
the transition period, the transition subsidy will be paid at 10 Yuan/� /month according to the property building area of the house to be relocated. If the transition period excel
24 months, the rate will be 20 Yuan/� /month.
2) If the non-domestic house to be relocated accepts exchange of property right,
during the transition period, the salary compensation for the employees will be
determined according to the personnel on the payroll recorded in labor and social
security department, and six-month salary compensation will be paid once as per
monthly salary per capita of the institution in the previous year.
72
3) Business compensation: if the relocation causes production and business
suspension, six-month business compensation will be paid once as per monthly average
taxes in the previous year; if partial production and business suspension is caused, three-
month business compensation will be paid once; if the production has stopped before
issuing the relocation notice, no compensation will be provided.
4) For monetary compensation, six-month temporary resettlement allowance will
be paid once, 10 Yuan/� for dwelling house and 20 Yuan/� for non-domestic house.
5) The shop leaseholder may obtain moving subsidy and finishing compensation
determined after evaluation. For the shop newly finished after relocation, under the
same condition, the original leaseholder enjoys the priority of accepting lease.
4.3.7 Resettlement of vulnerable groups
With respect to the vulnerable groups determined, the project office will provide the
security measures as follows:
According to the survey, if the family only has one dwelling house, the life is poor
indeed, and the public has no objection after issuing public announcement, the dwelling
house with building area not less than 50� will be provided. If the building area of resettlement house is less than 50� , the price of structure difference and the expenses for exceeding resettlement area will not be settled, and the charging rate of the expenses
for exceeding 50� is the same as private dwelling house. The resettlement office sets up the funds of RMB 2 million Yuan for helping
vulnerable groups according to specific needs during the resettlement course
For area, type and location of resettlement house, the family of vulnerable group has priority in selection.
Resettlement organizations at all levels are responsible for organization manpower
to assist in the moving of the families of vulnerable groups.
4.3.8 Resettlement for the relocation of illegal structures
The requirements of involuntary resettlement policies of the World Bank are taken
into full consideration, and for illegal structures to be dismantled, classified
compensation will be provided according to different situations. The concrete methods
are as follows:
73
If buildings without licenses are used as residential houses and relocation households have no other places for living, the relocation compensation shall be paid
according to that of buildings with license.
For the buildings other than the previous clause, the compensation will be
provided as per construction costs, and the concrete standards are: 600 Yuan/� for brick-concrete structure, 400 Yuan/2 for brick-concrete structure, 400 Yuan/� for brick-
wood structure and 200 Yuan/� for simple structure.
4.3.9 Compensation for affected infrastructures and attachments to the ground
As for public facilities and attachments to the ground involved in relocation and
moving, the appraisal shall be carried out according to replacement cost. Besides,
removers and the affected people should negotiate about and reach an agreement on the
compensation rate with reference to that of similar projects. The specific compensation
rate is�1. For the basement with the height more than 2.2m (including 2.2m), the
compensation will be provide as per 1/2 of compensation rate of the house of the same
structure; for the basement with the height less than 2.2m, the compensation will be
provided at 500 Yuan/� , and its area will not be brought into the area of resettlement
house.
2. Compensation for house finishing: the graded compensation will be provided
according to finishing degree and aging degree. For grade-one brand-new house, the
compensation will be provided at 200 Yuan/� ; for grade-two ninety percent new house,
the compensation will be provided at 180 Yuan/� , by parity of reasoning.
3. RMB 1000 Yuan for each cave house, 50 Yuan/� for brick wall, and 30 Yuan/� for adobe brick wall.
4. W.C.: RMB 100 Yuan for each brick-wood adobe brick W.C. with cover, RMB
300 Yuan for each simple W.C. without cover, and RMB 200 Yuan for other kind of
W.C.
5. RMB 500 Yuan for each gate tower, RMB 300 Yuan for each screen wall, and 15
Yuan/� for terrace. 6. 1000 Yuan/m for well.
74
7. 30 Yuan/� for greenhouse, RMB 30 Yuan for each timber tree with diameter of 10cm, by parity of reasoning; RMB 20 Yuan for each young tree, RMB 200 Yuan for
fruit tree that can bear fruit, and RMB 60 Yuan for fruit tree that cannot bear fruit.
8. RMB 150 Yuan for each telephone, RMB 600 Yuan for each internet accession,
and RMB 500 Yuan for each closed circuit.
4.4 Policies on the Resettlement of linked projects
Determined by the Taiyuan Urban Transport Project office, resettlement policies
and various compensation rates for extending sections of Waliu road and Taihang road
will be implemented completely according to that of the subprojects of North Mid Ring,
Taihang Road and public transport.
75
5. Resettlement Compensation Rates On the basis of deep survey and research, various kinds of compensation rates listed
in the Resettlement Action Plan, were established after full negotiation with the affected
units, persons and relevant local governmental departments of Taiyuan City according
to relevant laws and regulations in the People’s Republic of China and Shanxi Province
and involuntary resettlement policy of the World Bank, aiming to make the displaced
persons to retrieve and improve their living standard after resettlement in a short period.
5.1 Basis of Establishment of Compensation Rates
5.1.1 Basis of establishment of land compensation rates
According to Land Law of the People’s Republic of China and Regulations for the
Implementation of Land Law, compensation rates of requisition land constitute three
sections, namely, land compensation, resettlement subsidy and compensation for young
crops. According to relevant laws and regulations in Land Management Law of the
People’s Republic of China and Methods of Land Management Law of the People’s
Republic of China Implemented by Shanxi Province of Shanxi province, the first three
compensations need to be made sure the average production value of previous three
years at first and then decide a reasonable compensation multiple to calculate.
According to the abovementioned policies, the Resettlement Office selects the
cultivated land with the highest output value in affected region, refers to per unit area
yield publicized by Taiyuan Statistics Bureau and grain price in the market, and
calculates compensation rates for land acquisition as per the highest multiple (30 times)
of annual output value in each region.
Table 5-1 Compensation rates for land acquisition calculated as per the highest
multiples (30 times) of average annual output value
Affected region Per unit
area yield (kg)
Unit price (Yuan/kg)
Output value (Yuan)
Times Compensation amount
(Yuan)
76
Xiaodian District
388.00 2.1 814.8 30 24444
Yingze District 335.20 2.1 703.92 30 21117.6
Xinghualing District
346.73 2.1 728.14 30 21844.2
Jiancaoping District
359.13 2.1 754.18 30 22625.4
Wanbolin District
371.40 2.1 779.94 30 23398.2
Jinyuan District
393.27 2.1 825.86 30 24775.8
Seen from the results in Table 5-1, among compensation rates for land acquisition
calculated according to the regulations of the current land law, the highest is RMB
24776 Yuan.
No. 28 Document issued by the State Council on Oct 21st, 2004states that the
peoples government of each province, autonomous region and municipality directly
under the Central Government should stipulate and publicize unified annual output
value standard and district comprehensive land price for land acquisition of each city or
county. The Resettlement office of Taiyuan Urban Transport Project knows that the
Land and Resources Departments of Shanxi Province and Taiyuan City have measured
and established unified annual output value of the land or district land price in
accordance with No.28 File and directions of the Ministry of Land and Resources of
P.R.C., and determined that the unified district price for land acquisition in affected
region is 50,000 Yuan/mu, 25,000 Yuan higher than compensation rate worked out as
per the highest times of annual output value. The up-to-date unified annual output value
standard and district comprehensive land price have been formulated and reported, but
have not been formally publicized or implemented.
Although the unified district price for land acquisition in Taiyuan City has not
been publicized, in order to maintain the interests of the persons suffering from land
acquisition and provide conditions for recovering and improving their living level, the
Resettlement Office and the land department of each district agree to provide
compensation as per the unified district price, i.e. 50,000 Yuan/mu, after full
consultation. Among the 50000yuan ,1000yuan is compensation for young crops, and
49000 is for land acquisition. If the village provide cultivated land for the affected
77
family, the land compensation will be use by village , otherwise, 70% of it(34300yuan
per mu) will be paid to the family directly.
5.1.2 Basis of establishment of compensation rates for buildings
All the affected buildings will be compensated according to the replacement costs. In
order to know replacement costs of all the affected buildings exactly, the Project
Resettlement Office, local resettlement office and the survey and consultation unit
Center for Resettlement Research of Wuhan University did the ad hoc survey through
following methods to know the replacement costs of affected buildings and the feasible
compensation rates from December 2006 to March 2007:
First, know price index of various exchanges of estates at present through exchange
information of Taiyuan estate held by Taiyuan Real Estate Bureau. In particular, know
information about current second-hand houses exchange through price change of
existential estate to offer basis for resettlement rates and establishing policies. See the
information shown in block diagram 5-1.
According to Measuring and Calculating Methods of Base Price of Urban Existential
Houses Exchange in Taiyuan City, the scope of land acquisition and relocation in
Taiyuan Urban Transport Project locates in D-level district. Usually, reference price for
exchange of frame structure houses is RMB 1700 Yuan and price for exchange of brick
and concrete houses is RMB 1300 Yuan.
Box Methods of Establishing Reference price for Exchange of Current Estate in Taiyuan
1. Formula: Base price for exchange of existential houses in urban area of Taiyuan=location value of existential
houses ×(1+ correction factor of floor)×(1� correction factor of quality) ×(1+correction factor of facilities direction)×(1� correction factor of comprehensive environment)
2 Location value of existential houses:
Residence type A-level district B-level district C-level district D-level district E-level district
Multilayer residence 2100 1900 1700 1300 1000
High-layer residence 2600 2300 2000 1700 ——
Duplex residence 2800 2500 2200 1900 ——
Note: (1) As for existential houses in area of tract development with complete supporting facilities, good realty
management, implement the price according to location value in the higher-level district. (2) As for existential houses of special level, structure, function and floor in special district, real estate evaluation
organization possessed qualification of state second grade evaluates, and the tax will be levied according to this evaluated price.
78
(3) Location value of brick and wood house can be decreased by 5% according to multi-floor residence of
the same level.
3 . G e o g r a p h i c d i v i s i o n According to practical exchange of existential houses in past years, considering urban development planning,
transport and environment of the residences, it can be divided into five levels A, B, C, D, E. A-level district: North to Hanxiguan Street, Hanximen Street, Dongjihuying and Xinmin Middle Street, West to
Binhe East Road, South to Changfeng Street, East to Bingzhou North-south Road, Wuyi Road, South Inner Ring Street, Jianshe Road and Fudong Street;
B-level district: North to Beida Street, Xinghua Street, West to Qianfeng North-south Road, South to Nan Inner
Ring West Street, Changfeng West Street, Xuefu Street and Nan Middle Ring Street, East to Wucheng Road, Jianshe South Road, Chaoyang Street, Jingyuan Road and Wulongkou Street�
C-level district: North to Shengli Street, North Alley of Heping North Road, west to Heping North-south Road and Qianjin Road, East to Jianshe North Road, Bailongmiao Street and East Street of Xiaogoupo;
D-level street: North to north Paihongqu, Jiancaoping Street, West to Chengjiacun, West Trunk Railway, South to
Yijing Street, East to South street of Shuangta, Taihangnan North Road, Beihewan Road, Jianhe Road, Urban Area of Xiaodian District, Yingxinjie District, Jinyuan Town and Luocheng;
E-level district: except above plats.
Second, know compensation rates of similar projects recently in Taiyuan as reference
basis of establishing compensation rates of this project through survey.
Table 5-1 Compensation rates of typical projects relocation in Taiyuan
Unit: Yuan/�
Projects Use of the houses FrameBrick and
concrete
Brick and
wood
Earth and wood, simple houses
Private residence 1800 1600 1500 Airport avenue
Unit’s residence 1800 1600 1500
Residence 2172 1732 1505 560 Shi-Tai railway
Housing for business 2800 2400 2200
Cellular residence 1130 985
One-floor house 865 819 560
Housing for business 2260 1712 1628
Housing for office 1074 936 778 Residence on the collectively-owned land
700 600 550 300
Reforming the first phase dilapidated houses in Xiaodian District
Housing for business on the collectively-owned land
1400 1200 1100
House on state-owned land
1710 1680 1610 Reforming Yingchun Street House on collectively-
owned land 1000 1000
79
Third, know prices of the newly-built commercial buildings near affected area and
price of villagers’ rebuilt houses during reforming of “villages in Taiyuan city” recently.
In the vicinity of Xiangtang Village and Xiangtang Community of north middle ring
with most displaced persons, large-scale residential districts are being built with
reforming of “villages in the city”. The staff of the Resettlement Office and the staff of
Center for Resettlement Research of Wuhan University know the prices of the newly-
built buildings after survey on the spot. For a building named “Xiangtang Youth Town”,
the price of building under selling is 1700 to 1900 Yuan/� . For Xiaozaogou that is at the crossing of Taihang Road and Shenglidong Street, the staff responsible for survey
find that price of large-scale Zaoyuan District is 1350 ~1500 Yuan/� . Fourth, according to base price of land in different areas of Taiyuan and constructing
and installation costs of various buildings, determine reference prices of various
buildings in affected areas of this project.
In accordance with the information offered by Taiyuan Real Estate Bureau, the
districts of this project are 3 or 4 districts in Taiyuan. See base prices of various lands in
this district as shown in Table 5-3.
Table 5-3 Base prices of various lands of Taiyuan
Land levels Land types Base price Upper limit Lower limit
Land for industrial purposes 242 300 170
Land for business purposes 1229 1334 1125 3-level
Land for residence 949 1162 719
Land for industrial purposes NA NA NA
Land for business purposes 908 1125 690 4-level
Land for residence 579 719 450
Moreover, according to costs of building materials and labors without consideration
of price of the land, constructing and installation costs of frame-structure house, brick
and concrete house, brick and wood house are respectively RMB 800 Yuan, RMB 600
Yuan and RMB 400 Yuan at present in Taiyuan. Therefore, considering constructing
and installation costs of land types and various buildings in this project, reasonable
replacement prices of the frame-structure house, brick and concrete house, brick and
wood house in the areas of this project should respectively be about RMB 1750 Yuan,
RMB 1550 Yuan and RMB 1350 Yuan.
80
In order to work out relatively feasible compensation rates for the houses on rural
collective-owned land, the personnel of the Resettlement Office go deep into
Xiaozaogou Village, Yangjiyu Street, Xinghualing District and Xiaodongliu Village,
Huifeng Street, Jiancaoping District with more affected houses on collectively-owned
land, find residents newly building houses in recent years, collect various information
on costs and expenditures of building construction, analyze the costs, and obtain the
first-hand data concerning the costs of house construction on rural collectively-owned
land in affected region. The analysis of these typical cases lay the solid foundation for
working out compensation rates for the relocation of the houses on rural collectively-
owned land.
By the four approaches above, the Resettlement Office know current real estate
development in Taiyuan and market conditions clearly, which lays a firm foundation for
establishing compensation rates of relocated houses of this project.
5.1.3 Basis of establishment of compensation rates of other kinds
Besides compensation rates of requisitioned lands and buildings, compensation
rates of various attachments to the land, various specialized facilities, moving and
transition costs of affected families and etc will be established by the Resettlement
Office when they negotiate with displaced persons and combine with local market price
and compensation rates of the similar projects. Taking telecommunication facilities as
an example, according to affected situation from survey, department responsible for the
facilities puts forward the compensation report concerning resuming facilities, and then
the Resettlement Office employs specialized departments to check and evaluate the
report and agrees with department responsible for the facilities in accordance with
results of check and evaluation to determine compensation rates of this infrastructure.
5.2 Compensation Rates
By consultation with administrative department of the real estate, enterprises and
institutions and displaced persons’ representatives in the affected areas, the
Resettlement Office puts forward compensation rates as follows according to some
opinions and suggestions from the real estate evaluation company consulted:
81
5.2.1 Compensation rates for land acquisition
According to relevant policies and the results of survey, on the basis of the
suggestions of relevant departments, the Resettlement Office determines the
compensation rates for the acquisition of collectively-owned land as follows: for the
acquisition of collectively-owned land used for construction obtained with
compensation, if there is no building on the land, the compensation will be provided at
75 Yuan/� ; for the acquisition of collectively-owned cultivated land, the compensation
will be provided at 50,000 Yuan/mu.
As for the acquisition of state-owned land used for construction and with buildings,
its compensation will be included in the compensation price of the building, and land
compensation will not be listed separately; for the acquisition of collectively-owned
land used for construction obtained with compensation, if there is no building on the
land, the compensation will be provided at 240 Yuan/� ; for the acquisition of state-
owned agricultural land, the compensation will be provided at the compensation price of
collectively-owned land, 50,000 Yuan/mu.
5.2.2 Compensation rates for relocated houses
Through repeated survey and consultation, the Resettlement Office organizes
Taiyuan Financial Assessment Center and Taiyuan Construction Budget and Settlement
Auditing Center to carry out the evaluation of houses in the relocation scope and
determine compensation rates. See Table 5-4 through Table 5-6 for compensation rates
for various buildings.
Table 5-4 Compensation prices of dwelling houses on state-owned land
Unit: Yuan/�District
Structure Wanbolin District
Jiancaoping District
Xinghualing District
Yingze District
Xiaodian District
Frame 2300 2300 2300 2300 2300 Storied buildin
g1800 1800 1800
1800 1800
Brick- concret
eSingle story
building
1600 1600 1600
1600 1600
Brick-wood 1500 1500 1500 1500 1500 Simple two-story 1750 1750 1750 1750 1750
82
building Earth-wood 1300 1300 1300 1300 1300
Table 5-5 Compensation prices of non-domestic houses on state-owned land
Unit: Yuan/�Structure Wanboli
nDistrict
Jiancaoping District
Xinghualing District
Yingze District
Xiaodian District
Frame 1100 1100 1100 1100 1100 Brick-concrete 900 900 900 900 900
Brick-wood 800 800 800 800 800
Office
occupancy
Earth-wood 600 600 600 600 600 Frame 2680 2680 2680 2680 2680
Storied buildin
g2380 2380 2380 2380 2380
Brick- concret
eSingle story
building
2030 2030 2030 2030 2030
Brick-wood 1930 1930 1930 1930 1930
businessoccupancy
Earth-wood 1700 1700 1700 1700 1700 Frame 1100 1100 1100 1100 1100
Brick-concrete 900 900 900 900 900
Storageoccupancy
for
Brick-wood 800 800 800 800 800
Table 5-6 Compensation prices of houses on collectively-owned land
Unit: Yuan/�
Structure Wanbolin District
Jiancaoping District
Xinghualing District
Yingze District
Xiaodian District
Frame 1800 1800 1800 1800 1800 Brick-
concrete 1600 1600 1600
1600 1600
Brick-wood 1500 1500 1500 1500 1500 Earth-wood 1300 1300 1300 1300 1300 Basement 300 300 300 300 300
5.2.3 Rates for moving subsidy and transition subsidy
1. Moving subsidy
1) Moving expenses for dwelling house shall be paid to the relocatee at 10 Yuan/�according to the property building area of the house to be relocated;
83
2) Moving subsidy for non-domestic house: 10 Yuan/� for office occupancy; 20 Yuan/� for business occupancy, and 25 Yuan/� for storage occupancy for production and business.
3) If the house to be relocated accepts monetary compensation, moving subsidy will
be paid once; if the house to be relocated accepts independent transition, moving
subsidy will be paid twice.
2. Transition subsidy
1) If the dwelling house to be relocated accepts exchange of property right, during
the transition period, the transition subsidy will be paid at 10 Yuan/� /month according to the property building area of the house to be relocated, and the rate will be 20
Yuan/� /month after the transition period excel 24 months.
2) If the non-domestic house to be relocated accepts exchange of property right,
during the transition period, the salary compensation for the employees will be
determined according to the personnel on the payroll recorded in labor and social
security department, and six-month salary compensation will be paid once as per
monthly salary per capita of the institution in the previous year.
3) Business compensation: if the relocation causes production and business
suspension, six-month business compensation will be paid once as per monthly average
taxes in the previous year; if partial production and business suspension is caused, three-
month business compensation will be paid once; if the production has stopped before
issuing the relocation notice, no compensation will be provided.
4) For monetary compensation, six-month temporary resettlement allowance will
be paid once, 10 Yuan/� for dwelling house and 20 Yuan/� for non-domestic house.
5.2.4 Compensation rates for affected infrastructures and attachments to the ground
According to the compensation rates provided by other projects in Taiyuan City for
affected infrastructures and attachments to the ground, after full consultation, the
compensation rates for affected infrastructures and attachments to the ground in this
project are determined ultimately as follows:
1. For the basement with the height more than 2.2m (including 2.2m), the
compensation will be provide as per 1/2 of compensation rate of the house of the same
structure; for the basement with the height less than 2.2m, the compensation will be
84
provided at 500 Yuan/� , and its area will not be brought into the area of resettlement
house.
2. Compensation for house finishing: the graded compensation will be provided
according to finishing degree and aging degree. For grade-one brand-new house, the
compensation will be provided at 200 Yuan/� ; for grade-two ninety percent new house,
the compensation will be provided at 180 Yuan/� , by parity of reasoning. 3. RMB 1000 Yuan for each cave house, 50 Yuan/� for brick wall, and 30 Yuan/�
for adobe brick wall.
4. W.C.: RMB 100 Yuan for each brick-wood adobe brick W.C. with cover, RMB
300 Yuan for each simple W.C. without cover, and RMB 200 Yuan for other kind of
W.C.
5. RMB 500 Yuan for each gate tower, RMB 300 Yuan for each screen wall, and 15
Yuan/� for terrace. 6. 1000 Yuan/m for well.
7. 30 Yuan/� for greenhouse, RMB 30 Yuan for each timber tree with diameter of 10cm, by parity of reasoning; RMB 20 Yuan for each young tree, RMB 200 Yuan for
fruit tree that can bear fruit, and RMB 60 Yuan for fruit tree that cannot bear fruit.
8. RMB 150 Yuan for each telephone, RMB 600 Yuan for each wide band, and
RMB 500 Yuan for each closed circuit.
85
6�Resettlement and Rehabilitation
6.1 Objective, Mode and Principle of the Resettlement and
Rehabilitation
6.1.1 Objective of the resettlement and rehabilitation
According to the requirement of World Bank’s implementing policy about
involuntary resettlement and relative laws and regulations of the country, the general
aim of the World Bank financed Taiyuan Urban Transport Project is to make the living
and production of displaced persons, enterprises and institutions rehabilitate as soon as
possible and improve as much as possible. Specific aims are:
Affected households will be compensated according to the standard of replacement cost and ensured that the floor space, structure and inhabited environment
of their reconstructed houses at least reach the level before the relocation or have
improvement;
All manner of affected attachments to the ground will be compensated according
to the replacement cost price;
Resettled labor force will be resettled appropriately, and ensured that their income will retain and increase. No peasants will lose their job permanently because of
the land acquisition;
Public buildings and special facilities will be compensated according to the replacement price and rehabilitated according to primary standard;
After the reconstruction of enterprises, their production scale, capacity and
employment of staff will not be affected. No affected labor force will lose his job
permanently because his work unit is affected;
The public facilities and environment of affected communities will rehabilitate to the level before the relocation, and improve as much as possible.
6.1.2 Mode of the resettlement and rehabilitation
The resettlement and rehabilitation of the living of the affected population and the
resettlement and rehabilitation of the production will proceed at the same time.
86
The resettlement and rehabilitation of living, mostly resettlement and
reconstruction of houses and rehabilitation of living supporting facilities, mainly
include:
Residential houses of affected households. Residential buildings of production organizations. Facilities of domestic water supply, power supply and heating, etc.
The resettlement and rehabilitation of production, mostly the job arrangement of
labor force and reconstruction and rehabilitation of production facilities, include:
Agricultural resettlement of affected agricultural population. Rehabilitation of production facilities of production organizations. Production
facilities of production organizations will be compensated according to replacement
price, so the production scale and capacity will not diminish because of the project.
Former staff will be reemployed by new-constructed organizations.
The resettlement and rehabilitation will carry on mainly by fund compensation,
labor force resettlement, living and production conditions rehabilitation, etc.
6.1.3 Principle of the resettlement and rehabilitation
The affected population participate in the overall process of the resettlement. Issues like the compensation rate of houses and facilities, the selection of
resettlement location, the time arrangement of relocation and rehabilitation, the transfer
of fund and resettlement measures of labor force, etc. must be negotiated and agreed
with the participation of displaced persons or delegates. The consultation with displaced
persons shall carry on by delegate symposium, villager conference, etc.
All classes of compensation will be wholly and directly paid to property owners,
no unit or individual including committees of districts, townships (streets),villages
(communities) of all levels is allowed to use the compensation for property on behalf of
others.
Compensation for houses, special facilities and attachments shall be calculated at
replacement price. Compensation amount should not be detained, depreciated or tax-
borne; the compensation property owners get shall be calculated at public compensation
rate. All properties of former buildings belong to former owners, no organizations and
individuals have the rights of domination and disposition. The calculating of
87
compensation price should not be deducted with salvage value of materials of relocated
parts and depreciation of former properties.
Use land reasonably. Because the project affects many structures, land use for reconstructions shall be
planned well and land shall be used reasonably on the basis of consultation with
affected population.
Help and care for vulnerable groups. In respects of the selection of resettlement location, the supply of information of
resettlement house sources, endeavor for purchase opportunities for affordable housing,
etc. priority should be given to families of vulnerable groups; In respects of the supply
of employment opportunities created in the process of the implement of the project,
distribution of service network in resettlement locations, etc. preference should be given
to families of vulnerable groups.
6.2 Resettlement for Relocated Households
Well resettlement of relocated households is one of most important contents
regarded by Project Resettlement Office as well as a subject repeatedly negotiated with
displaced persons. Prior to Aug 2007, Project Resettlement Office worked out currency
resettlement as the preliminary policy in principle. However, during consultation with
displaced persons, the Project Resettlement Office found that market price of
commercial residential buildings in Taiyuan had greatly fluctuated recently and over
95% of relocated households were apt to obtaining houses rather than currency. In
particular, some relocated households with smaller living space said that they were
unable to get basic housing condition after currency resettlement, so they strongly held
that resettlement should be done through exchange of property rights.
To guarantee basic housing condition of affected families, the Project Resettlement
Office, under the precondition of fully knowing displaced persons’ resettlement will,
reported to the People’s Government of Taiyuan Municipality for approval of
amendment of the relocation policy. It was changed from currency resettlement to two
modes including exchange of property rights and currency resettlement for affected
families to make a self choice. This significant amendment was warmly supported by
affected families.
88
To accelerate successful construction of resettlement houses, the Project
Resettlement Office, after the World Bank Project Delegation visiting Taiyuan in Sep
2007, authorized Taiyuan Urban Planning and Design Research Institute to proceed in
planning of land use and site selection and design of construction plan of resettlement
residential buildings. The design plan has been approved by the People’s Government
of Taiyuan Municipality, the construction of resettlement houses will be developed step
by step with the progress of the project so that the relocated families can move to their
new houses successfully.
According to construction plan of resettlement houses, selection of new
resettlement spots will adhere to three principles as below:
First, “to focus on the people”, try to choose a site with smaller impact of land
requisition and relocation to construct resettlement houses, and resettle the land
requisition and relocation generated by construction of resettlement spots completely
in accordance with the resettlement policy for this project.
Second, “settlement in vicinity”, try to choose resettlement spots along North Mid
Ring Road and Taihang Road for the convenience of relocated households’ study and
work, and try to maintain their activity scope of daily life;
Third, “to improve citizens’ quality of life and environment”, completely change
the dirty, disorderly and bad environment during construction of resettlement spots.
According to aforesaid principles, Taiyuan Urban Planning and Design Research
Institute determines construction plan of five resettlement spots. It is estimated 11247
sets of resettlement houses will be offered. Besides meeting the resettlement
requirement of this project, moving-back resettlement buildings can also be offered to
other key projects to facilitate improvement of residents’ housing condition in Taiyuan.
See Table 6-1 for construction of resettlement spots.
Table 6-1 Construction plan of resettlement spots of Taiyuan urban transport project
No.
Name of resettlement spot
Area of land used (hectare)
Volume ratio
Resettlement area (� )
Number of households can be resettled
1Land 1 of Xinghualing transit expressway
17 1� 2 204000 2040
2Land 2 of Xinghualing transit expressway
11 2� 8 308000 3080
3 Shenglidong Street 13 1� 8 228700 2287
89
4 Chengjia Village 2 5 120000 1200
5 Wohu Mountain 17 1� 6 264000 2640
Total 60 1124700 11247
The construction plan of above resettlement spots has started. In May 2008, written
proposal of location presented by Taiyuan Urban Planning and Design Research
Institute was approved by Taiyuan Urban Planning Administration, and directions of
resettlement spots were determined. However, detailed positions of resettlement spots
are under final determination. Resettlement survey is unavailable now due to immature
conditions. Therefore, the Project Resettlement Office decides to formulate
Resettlement Policy Framework for land acquisition and relocation before formal
evaluation of Taiyuan Urban Transport Project and to formulate Resettlement Action
Plan when resettlement survey is available. The land acquisition and relocation policy
for resettlement spots will be consistent with that for resettlement spots at North Mid
Ring Road and Taihang Road.
According to its schedule, the Project Resettlement Office will determine the final
construction plan for resettlement spots during Aug.-Sept. 2008, arrange house building
in Oct. 2008 and provide new houses for relocation households who move back to live
in at the end of 2009. At the same time, the construction of project will be implemented
in several stages as much as possible. Construction will be commenced from the work
section for which relocation is not necessary or a small number of households need to
be relocated, so as to minimize the transition period of relocation households. The
longest transition period will not exceed 24 months. All relocation households will be
given a housing subsidy by 10 Yuan/� per month.
In May 2008, the Project Resettlement Office learnt from the coordination office
for reformation of villages in Taiyuan City that, according to the city’s development
plan, 14 villages including Dadongliu, Xiliu, Xiaodongliu, Xiangtang, Xiaozaogou,
Daochanggou, Ba’ergou, Can’ershu, Haojiagou, Haozhuang, Wangjiafeng, Dianpo,
Longbao and Dongtaibao villages involved in this project and Xudong and Dongshe
villages involved in related projects were all covered by the “Village in City” reform
plan of Taiyuan City. And Dadongliu, Xiliu, Xiaodongliu, Xiangtang, Xiaozaogou,
Daochanggou, Haojiagou, Dianpo and Longbao villages were listed in the 2008 “village
in city” reform plan. Based on the consultations with villagers, the Project Resettlement
90
Office has considered resettlement of relocation households and construction of
resettlement spots in the construction plan of resettlement spots. And the above
“villages in city” will also be reformed in combination with the construction of
resettlement spots. The compensation rates of the World Bank financed project is higher
than those of “the reformation of villages in city”, especially much more favorite
policies are adopted for the vulnerable groups and owner of illegal buildings.
Meanwhile, since real estate market has developed to some extent in recent years,
some relocation households have bought houses elsewhere. So monetary compensation
and physical resettlement are alternatives for relocation households to choose. If they
choose monetary compensation and buy houses themselves, they will be given funds at
the compensation rates.
6.3 Rehabilitation of Peasants Affected by Land Acquisition
According to the survey, totally 93.74 mu of collective land is requisitioned for this
project, in which 35.1 mu is from North Mid Ring Road, 29.44 mu from Taihang Road,
13.5 mu from Starting and Ending Stations of Yingxin Street, and 15.7 mu from
Starting and Ending Stations of Beiyan. The above requisitioned land is orchards and
vegetable greenhouses, respectively managed by 11 peasant households under contracts,
among which 2 households are from Dadongliu Village in Jiancaoping District; 2 from
Nangunian Village; 2 from Xiaozaogou Village in Xinghualing District; 1 from
Longbao Village in Xiaodian District; 2 from Dianpo Village in Yingze District; and 2
from Yijing Village in Jinyuan District. These 11 households have 42 persons including
23 labors.
The survey also shows that the above requisitioned orchards and greenhouses are
only a part of their land and other non-agricultural incomes are their main sources of
incomes.
According to the survey among the above 11 households and resettlement methods
of previous similar projects, the final resettlement methods are determined based on
consultation with the villages they live in:
The compensations for attachments to ground including young groups should be given to affected households. compensation for young crops is 1000yuan per mu.
91
70% of land compensation fees(34300yuan per mu) will be directly given to
affected households.
The use of land compensation funds collectively managed by villages should be
determined at villager representative meetings and should be used mainly for public
utilities.
6.4 Rehabilitation of Affected Enterprises and Institutions
The World Bank Financed Taiyuan Urban Transport Project affects 112 enterprises
and institutions, among which 55 are at North Mid Ring Road, 53 at Taihang Road, and
4 are affected by the project of public transport. The relocated parts of these enterprises
and institutions include some production and business places, some enclosing walls or
office buildings, or accommodations owned by units. Resettlement offices at all levels
conducted investigations and learnt the desires of all units, consulted with them on the
methods of resettlement and recovery, and preliminarily formed the relevant plan of
resettlement and rehabilitation of enterprises and institutions.
6.4.1 Compensation and rehabilitation of enterprises whose production and business are
affected
The production and business operations of 18 enterprises among the
abovementioned 112 enterprises and institutions will be affected directly. According to
the preliminary resettlement intentions agreed between resettlement offices and these
enterprises, except one enterprise, the rest may change their production layouts at the
original sites and continue their production and business operations. As the project
office has notified the project alignment in advance, the enterprises may have enough
time to conduct adjustment of production layouts so as to minimize the losses of
operations. Besides compensations for affected substances at standard rates,
professional evaluation agents will be employed to finally determine loss from
suspension.
92
Table 6-2 Resettlement and rehabilitation methods for enterprises whose production and business operations are affected
No.
Unit Description of influence Degree of influence Resettlementmethod
1Duxiaozi Lubricating OilProcessing Plant, Taiyuan
Two oil tanks in the oil depot, gatehouse and
enclosing wall will be affected.
Slight influence; normalproduction will not be
affected
Use compensationfunds to change the
location ofproduction
2Fengquan Rainmaker Plant,Taiyuan
The office building and a manufacturing shopwill beaffected, about 1200 � of brick andconcrete.
slight influence; moveproduction shop nearby
Use compensationfunds to change the
location ofproduction
3Chengruida Iron TowerManufacture Co., Ltd, Shanxi
Gatehouse, enclosing wall and a workshop willbe affected, 25 � of brick and concrete, 476.6 �of brick and wood.
Reconstruct enclosingwall; move workshop
nearby; slight influence
Use compensationfunds to change the
location ofproduction
4Guangju Industry Co., Ltd,Shanxi
A workshop will beaffected, 492 � of brick andconcrete.
Move workshop nearby;slight influence
Use compensationfunds to change the
location ofproduction
5Petroleum Drilling Tool Plant,Jinxi
Brick-concrete structureof 4041 � , and simplestructureof 3275�
The affected generallyis spare building and
officeoccupancy; slightinfluence.
Use compensationfunds to change the
location ofproduction
6Jinbao New-Type BuildingMaterialsCo., Ltd, Taiyuan
Two workshops will beaffected, 719 � of brick-concrete structure.
Medium influence;reconstruct workshop
nearby
Use compensationfunds to change the
location ofproduction
7Xinhua Machine Works,Taiyuan
The part will beaffected, and steel-concretestructureof3100� and brick-concrete structure
Medium influence,move the production
Use compensationfunds to change the
93
No.
Unit Description of influence Degree of influence Resettlementmethod
of 1500� will be relocated. shop to the buildingnearby
location ofproduction
8Shanxi Luweibao TaiyuanSteel Refractory MaterialsCo., Ltd
Just change to China-Germany joint venture inJuly 2006. Both two major workshopsand onein-construction workshop will be relocated.
Severe influenceIntegral moving
9TheWarehouse of Taiyuan 3rd
Construction CompanyA warehouse of 186 � of brick and concretewillbe affected.
Slight influence Change the locationof production
10 Xinglong Garage Brick-concrete structureof 3200�Slight influence Use compensation
funds to adjust thelocation ofproduction
11 ThePlasticine FactoryOne workshop will beaffected, brick-concretestructureof 77� .
Slight influence Use compensationfunds to adjust the
location ofproduction
12Jingdong Automobile DrivingSchool
The parking lot and part of the training field willbe affected, 498 � of brick and concretestructure.
Slight influence Use compensationfunds to adjust the
location
13Shanxi Huaqi MachineryCompany
A transformer and asmall part of workshopswill beaffected, 560 � of brick and concreteand 210 � of brick and wood. No materialaffection to the production.
Slight influence Use compensationfunds to adjust the
location ofproduction
14Xinhui Metal FormingMachinery Works
Brick-concrete structureof 1524.62�Slight influence Use compensation
funds to adjust thelocation ofproduction
152nd Brick Yard ofWangjiafeng Village
A part of the factory buildings need removing,24 � of brick and concrete, 248.6 � of brick and
Production of the brickfactory will not be
Use compensationfunds to adjust the
94
No.
Unit Description of influence Degree of influence Resettlementmethod
wood and 24 � of cabanas. affected location ofproduction
16 Taiyuan Air PipeFactoryPartial production yard will beaffected, 1326.5� of brick and concrete.
Slight influence Use compensationfunds to adjust the
location ofproduction
17Taiyuan Mining MachineryGroup Co., Ltd.
A production shop will be affected, 12948 � ofbrick and concrete, 826.4 � of brick and woodand 892 � of cabanas.
Medium influence;move the production
shop nearby
Use compensationfunds to adjust the
location ofproduction
18ThePlasticine Factory ofDianpo Village
A workshop of 77 � of brick and concretewillbe affected.
Slight influence Use compensationfunds to adjust the
location ofproduction
95
As for the enterprises with production and business affected, once the project is
commenced, the corresponding expenses will be paid six month in advance according to
the progress of engineering construction, in order that the enterprises may do
preparation in advance. Make reasonable arrangement of land acquisition and relocation
and normal production and business of the enterprises, so as not to affect the
construction and to ensure the successful production and business of the enterprise.
Box Resettlement of Shanxi Luweibao Taiyuan Steel Refractory Materials
Co., Ltd. affected most severely
Shanxi Luweibao Taiyuan Steel Refractory Materials Co., Ltd. is a large-scale enterprise and became a Chinese –Germany joint venture in July 2006. The refractory materials produced by the company are mainly supplied to Taiyuan Iron and Steel Group. The North Mid Ring passes across the enterprise, and two major workshops and one in-construction workshop have to be relocated. The whole enterprise almost losses its basic production function completely.
In order to solve the resettlement problem of this enterprise, from December 2006 to May 2005, the Resettlement Office has made efforts from different angles:
1) Probe into the possibility of line optimization with the design department together. Avoid the core part of the enterprise as best as possible and minimize losses.
2) Negotiate with the enterprises on the compensation program and the methods for proper resettlement and rehabilitation when the line arrangement has been determined.
3) Communicate and coordinate with the municipal government and relevant organizations, and try for preferential policy for integral moving of the enterprise. Through full consultation, in May 2008, the Resettlement Office and Shanxi Luweibao Taiyuan Steel Refractory Materials Co., Ltd. achieved the following agreement on resettlement: 1) Integrally move the enterprise, and resettle it in Taiyuan Stainless Steel Ecological Industrial Park. The Stainless Ecological Industrial Park is located in Jiancaoping District in Taiyuan City. The area of the park is 100 square kilometers, and there are exclusive market zone, industrial processing zone, sales center, resource allocation center, logistics and distribution center and corresponding technical development center and information center in the park. The park borders upon National Highway 108 and Xinlan Road, is 3km away from the entry of Dayun Expressway, 5km away from Binhe East Road and 2.5km away from material base, Taiyuan Iron and Steel Group, and has two railway sidings, which provides convenient traffic for the park. The park is successfully opened on August 28, 2004. 2) For the mechanical equipment which may be used normally after moving, the Project Office will afford the expenses of equipment dismounting and transportation; for the equipment which may not be used after moving, the Project Office will provide compensation as per the original purchasing price of the
96
equipment; 3) The determination of property and area of the house to be relocated should be subject to the ownership certificate issued by the relevant administration;
4) The compensation for mechanical equipment should be subject to the determination of the professional evaluation organization; 5) The Resettlement Office should actively communicate and coordination with the department related to enterprise moving, providing convenience for the successful moving of the enterprise. 6) On the basis of consultation and evaluation, resettlement compensation for the enterprise is RMB 211,335,514.59 Yuan. The enterprise will finish the moving within two years after the project commencement.
6.4.2 Resettlement and rehabilitation of other enterprises and institutions
The Project Resettlement Office will compensate enterprises and institutions
whose production and operation is not materially affected according to these
organizations’ actual amount of affected structures and the compensation rate. As to
these organizations, in general, only parts of unproductive and non-operative structures
are affected, which can be simply rehabilitated on the spot and will not cause loss of
production suspension. See Table 6-3 for impact situations and resettlement methods of
these organizations.
Table 6-3 Resettlement and rehabilitation methods of affected enterprises and
institutions
Organization Relocated Area
Description of affection Resettlement and rehabilitation methods
Beichen Development Company
1504
A part of temporary structures are affected. When the resettlement plan was concluded, this organization was removing some structures within the red line by itself.
Remove the temporary structures; pay adequate compensation.
Shanxi Laboratory 8228 Removing of sewage treatment facilities is involved.
Pay compensation according to the rate; rehabilitate hand reconstruct at nearest place.
Beijianhe River Administrative Station
298 The watercourse drainage facilities of Beijian River will be all removed.
Pay compensation according to the rate; rehabilitate hand reconstruct at nearest place.
Bolang Shirt Factory 4312 Idle houses were rented to Xinhua School, 1/3 will be relocated.
Pay compensation according to the rate.
The 9th Architechtural Engineering Company of Linzhou City
6952 Shop fronts of the front row are removed.
Remove the temporary structures; pay adequate compensation.
Taiyuan Iron and Steel (Group) Co., Ltd. (main plant side)
5874 2 gates, water tower, gatehouse. The affection is comparatively small.
Reconstruct at the same place.
Taiyuan Botong Culture and Education Training School
100 enclosing wall Pay compensation according to the rate, rebuild enclosing wall.
97
Dashun Industry Co., Ltd
300 Gatehouse and enclosing wall. No affection to its production.
Pay compensation according to the rate; rebuild enclosing wall and gatehouse.
Long’ao Electricity Administrative Station of Galiaogou River
367.2 The office building is affected and need removing.
Pay compensation according to the rate; rebuild office building.
Huifeng Community 1345 Some scattered old houses, no material affection.
Pay compensation according to the rate.
Sanwei Steel Structural Engineering Co., Ltd.
278.75 The office building is affected and need relocating. Production is not affected.
Pay compensation according to the rate; choose another office building.
Taiyuan Fruit Plant Field
907.3 Some old houses, no material affection.
Pay compensation according to the rate; rebuild enclosing wall and gatehouse.
The Concrete Division of Taiyuan Lionhead (Group) Co., Ltd.
2929.44
Only gatehouse, enclosing wall and a row of shopfronts for rent are affected. No affection to the production.
Pay compensation according to the rate; rebuild enclosing wall and gatehouse.
Taiyuan 2nd Rainmaker Factory
371 Gatehouse and enclosing wall are affected.
Pay compensation according to the rate; rebuild enclosing wall and gatehouse.
Yinhe Aluminium Alloy Material Factory
145 Gatehouse and enclosing wall are affected.
Pay compensation according to the rate; rebuild enclosing wall and gatehouse.
Huifeng Sub-district Office
6239
A three-storeys building of which the 2nd and 3rd floors is the action center of the community, 1st floor is the property sales office of the Civil Administration Bureau.
Pay compensation according to the rate.
Penghong Real Eatate Company
2666 A few cabanas. No material affection to the company.
Pay compensation according to the rate.
Shanxi Frozen Poultry Semen and Breeding Center
84 Gatehouse and enclosing wall are affected.
Pay compensation according to the rate; rebuild enclosing wall and gatehouse.
Shanxi Yuanli Science and Technology Development Co., Ltd
1306 A half of the main office building is affected.
Pay compensation according to the rate; rebuild an office building at the nearest place.
Shuangqin Honeycomb Briquet Factory
96 enclosing wall and cabanas Pay compensation according to the rate, rebuild enclosing wall.
Fruit Plant Center of Jiancaoping District, Taiyuan
870 some old houses for rent Pay compensation according to the rate, rebuild backwardly.
Villagers’ Committee of Xiliu Village
1610 2 two-storeys buildings Pay compensation according to the rate.
Villagers’ Committee of Xiaodongliu Village
2284 the village police station, need wholly removing
Pay compensation according to the rate.
Property Company of Anguang Quarter
65.75 Gatehouse and enclosing wall are affected.
Pay compensation according to the rate; rebuild enclosing wall and gatehouse.
Haodong Physical Distribution Co., Ltd.
30 a carport Pay compensation according to the rate.
Jinji Xinyouyi Quarter 1490 enclosing wall Pay compensation according to the rate; rebuild enclosing wall and gatehouse.
Shanxi National Defence Fleet Operation
911.5 gatehouse, gate and a transformer Rebuild a gatehouse and remove the transformer.
Wansha Real Estate Development Company
270
Several temporary living houses of building workers are involved, which will probably be dismantled by the organization itself before this project starts.
Pay compensation according to the rate.
Dongshe Waste and Old Materials Market
40 enclosing wall Rebuild enclosing wall.
Jinxi Machinery Building and Repairing Plant
467 Only houses close to the enclosing wall and a boiler are affected.
Pay compensation according to the rate; rebuild a boilerhouse.
Jinxi Rubber and Plastic Products
503 The land is station owned. Only a few like the gatehouse are
Pay compensation according to the rate; b ild enclosing wall and gatehouse.
98
Plastic Products Factory
structures like the gatehouse are affected.
rebuild enclosing wall and gatehouse.
Jinxi Prefab Frame Factory
1288 Some unproductional houses are affected. No material affection.
Pay compensation according to the rate.
Taiyuan Fruit Plant Field
495.2
The field crosses over Wanbolin District and Jiancaoping District. A part of abandoned hog houses are affected.
Pay compensation according to the rate.
Taiyuan Maoxinsheng Goods and Materials Trade Center
160 Gatehouse and enclosing wall are affected.
Pay compensation according to the rate; rebuild enclosing wall and gatehouse.
Taiyuan Ruigang Erection Work Co., Ltd
2520 It is in the range of the crossing inter section, almost need entirely dismantling.
Pay compensation according to the rate, and wholly relocate.
Taiyuan Wanbolin Fruit Plant Field
930
Some scattered old houses of which some have already broken down and some are abandoned. No material affection.
Pay compensation according to the rate.
West Xinghua Street Elementary School of Wanbolin District, Taiyuan City
0Station owned. A playground is affected, but may cause traffic safety issues in the future for the students.
Pay compensation according to the rate, construct a new playground and traffic aisle.
Wanbolin Fruit Plant Field
250 Abandoned old houses Pay compensation according to the rate.
Shanxi Jinan Chemical Plant
12884 It is in the state of off production or half off production. The affection is small.
Pay compensation according to the rate; Organizations that rented its houses must rent other abounding idle houses.
Environmental Health Team of Xinghualing District, Taiyuan
3037 Almost half of the structures are affected. The affection is comparatively big.
Pay compensation according to the rate, rebuild at the nearest place.
Chuangxin Embellishment Work Company of Bailong Garden
540 No more production is seen; houses are abandoned.
Pay compensation according to the rate.
Dongshan Heat Source Factory
292 gate and gatehouse Rebuild enclosing wall and gatehouse.
Yada Corperation 1423 rented to others Pay compensation according to the rate.
Civil Defense 838 of Shanxi Province
1082 the Office of Civil Defense Pay compensation according to the rate.
Taiyuan Slide Fastener Factory
1004 A workshop house that is rented to others by the owner is involved.
Pay compensation according to the rate.
Daochanggou Village, Subject Office of Yangjiayu, Xinghualing District
1130 shopfronts and temporary structures on the edge of the village
Pay compensation according to the rate.
Hongchao Company 105.8 Private-owned, hiring collective land. A small 2-story building is affected. No material affection to production.
Pay compensation according to the rate.
Baiyun Flower Center 495.5
Private-owned, hiring station owned land of the mental hospital. 3 greenhouses, a warehouse, gatehouse, houses, etc. are affected. About half the center will be relocated.
Pay compensation according to the rate.
Mental Health Center of Taiyuan City
1542
In the hospital area, only the gatehouse and carport are affected, the main building is not affected. On the land oof the hospital across, a big pool, a 300m-deep well, and some houses are affected. The water supply system needs reconstruction.
Pay compensation according to the rate; reconstruct a pool and water supply system at the nearest place. Consider constructing an underground passage to ensure the safety of staff on the way to work.
The refrigerated warehouse of Taiyuan Bingfeng Emporium
255 This area belongs to the warehouse of the emporium; only a corner of the warehouse, a toilet and a cabana are
Pay compensation according to the rate.
99
affected.
Taiyuan Jianyuan Industry and Trade Co., Ltd
640.3 Only the enclosing wall and two small houses are affected. No material affection to production.
Pay compensation according to the rate; rebuild enclosing wall and gatehouse.
The Professional Trading Academy of Radio, Film and TV
879.5
No material affection to structures like school buildings, only 800 � of brick and concrete and 79.52 � of cabanas are affected. But during the construction period, regular teaching may be affected. The completed project will separate the academy into 2 parts.
Pay compensation according to the rate; Consider construct an underground passage or a pedestrian overcrossing to give convenience to the traffic.
Haojiagou Village (2# wellhouse)
45.4 Removing the wellhouse may affect the water supply of the village. Need rebuilding at somewhere nearby.
Pay compensation according to the rate; Rebuild at the nearest place.
Shanxi Sanjin Pharmaceuticals Co., Ltd.
459 Only gatehouse, enclosing wall and garage are affected. No material affection.
Pay compensation according to the rate; rebuild the enclosing wall and the gatehouse.
The Switch Factory of Shanxi Power Company
1838
A few workshops, storerooms and garage are involved, no significant affection to production. But a water tower and a water storage pond need removing; domestic water of the staff is affected.
Pay compensation according to the rate; Rebuild at the nearest place.
Betrochemistry Branch Factory
814.3 A few non-productive structures; no material affection to production.
Pay compensation according to the rate.
Small Commodities Market
4500 All 180 shops need relocating. Construct a new market; whole relocation.
Shanxi Archives Bureau
13418 Station owned land. Office building and dormitory are affected.
Pay compensation according to the rate; rebuild at the nearest place.
Warehouse of Overseas Chinese Friendship Company
195 Station owned. A few cabanas are affected, no material affection.
Pay compensation according to the rate.
Taiyuan Asbestos Factory (Jierui Building Materials Company)
2467
Office building. Half the office building is within the range of the red line, need removing and reconstruction.
Pay compensation according to the rate; Rebuild at the nearest place.
Taiyuan Zhaoyang Carbon Factory
790.5 Non-productive structures, little affection.
Pay compensation according to the rate.
Taiyuan Salvation Administer Station
1320
Station owned. Some farms or simple factories for employment of salvaged people are affected; positions need adjusting.
Pay compensation according to the rate; Rebuild at the nearest place.
Taiyuan Railway Prison
1020 Station owned. Half of the office building is affected. There is material affection. Need wholly relocating.
Pay compensation according to the rate; Rebuild at the nearest place.
1st Brick Yard of Wangjiafeng Village
174.1 No material affection. Pay compensation according to the rate.
Villagers’ Committee of Wangjiafeng Village
2485 1/3 of the office building is affected; the auditorium will be completely removed.
Pay compensation according to the rate; Rebuild at the nearest place.
Wangjiafeng Elementary School
9120 Station owned. Need wholly removing and rebuilding.
Pay compensation according to the rate; select another place to rebuild.
The Horticulture Institute of the Academy of Agricultural Sciences
5727 A number of greenhouses and test field are affected.
Pay compensation according to the rate.
Village Collective of Longbao Village
844.2 The pool of the village collective and collective owned houses.
Pay compensation according to the rate.
100
6.4.3 Reconstruction of affected schools
Among all kinds of affected organizations, the Resettlement Office pays special
attention to the resettlement of affected schools. According to field survey, 4 schools
that will be affected by the project respectively are: West Xinghua Street Elementary
School in Jinjixi Community, Wanbolin Sub-district Office, Wanbolin District; Xincun
Elementary School (and dormitory) in Xincun Community, Xincun Sub-district Office,
Xinghualing District; The Professional Trading Academy of Radio, Film and TV in
Haozhuang Township, Yingze District and Wangjiafeng Elementary School (and
kindergarten) in Haozhuang Township, Yingze District.
Among these 4 schools, as to Xincun Elementary School, only its staff quarters are
affected, the teaching area is not affected; The Professional Trading Academy of Radio,
Film and TV and West Xinghua Street Elementary School are both separated by the
highway into two parts, however, their teaching buildings are not affected. Considering
the safety issue of the students on their way to school after the project finishes, the
Resettlement Office communicated with the principles of the two schools, they all hope
the Office will consider add pedestrian over-crossing or underground passage for the
convenience of students’ crossing the street. The Resettlement Office delivered this
demand to the design organization, and will give consideration to it during the
construction process of the project.
So, the only school that needs wholly removing along the line of this project is
Wangjiafeng Elementary School (and kindergarten). The floor space of this school is
9120 � , among which 1664 � are brick and concrete, 7456 � are cabanas. Because this project needs to remove most of the school buildings, considering the need of the safety
of students and normal teaching environment, the Office decided to rebuild the school at
another place. In December 2006, workers of the Project Resettlement Office, together
with workers of The Resettlement Office of Haozhuang Township, and local office
workers in charge of education negotiated on the reconstruction with village cadres and
the masses. The agreed opinion is that the Resettlement Office will choose a proper site
within the village and requisition land to reconstruct. The compensation for affected
structures will be paid once for all 6 months before the relocation, and the Villagers’
Committee will organize the reconstruction. Before the new school is completed, the old
101
school should not be dismantled to ensure normal teaching activities. The moving from
the old school to the new school will proceed during vacation.
Picture 6-1 Wangjiafeng Elementary School to be relocated
6.4.4 Resettlement and rehabilitation of affected shops
According to the resettlement survey, there are 114 shops to be relocated along the
line. Besides, a smallware market with 180 shops had to be relocated, all the affected
employees are 657. These shops may be divided into three groups:
Group 1: 82 shops are rebuilt by rural or community people in their houses, which
are defined as residential houses on their licenses. Shops of this kind concentrate in
Huifeng Community of Jiancaoping District and Haozhuang Village of Yingze District.
Group 2: 22 shops are temporary structures built by some enterprises for rent.
Shops of this kind concentrate along Madaopo Street of Dongshan Coal Mine and
Kaixuan Street of Daochanggou Village, and in the Haojiagou Smallware market.
Group 10 shops are sites of failed enterprises or idle sites for rent. Shops of this
kind mainly concentrate in Jin’an Chemical Plant (Yangjiayu Office of Xinghualing
District).
The resettlement measures for the 82 private shops are:
For shops rebuilt by individuals or households from residential houses, besides compensation according to the compensation rate, their operating loss of 3 months will
be compensated according to their duty-aid certificates.
Some shop fronts will be built in resettlement plots, those whose shop had been
dismantled will take precedence to lease them.
The resettlement measures for the 32 shops built by enterprises and institutions are:
102
For new shop fronts and mercantile occupancy rebuilt by enterprises and institutions backwardly at nearest places after current shops are dismantled, on an equal
footing, the former tenants have preferential tenant right.
Moving cost, transition cost and compensation for fitments determined by evaluation belong to the tenant; the compensation for the construction belongs to the
owner of property right.
The operating losses caused by relocation of shops of enterprises and institutions shall be determined after the Resettlement Office negotiates with the displaced persons.
In order to properly resettle the shops in Yiwu Street and Baigou Street smallware
market, several smallware markets has been newly built in Haojiagou Village,
Haozhuang Township, Yingze District, such as Jinyang Smallware Market, Meiji
Market, and so on. These markets are close to the existing smallware market and have
convenient traffic. After the smallware market is relocated, the existing shop operators
may move the new places for business according to the current leasing area and price.
Their businesses will not be affected, and benefit from the improvement of traffic
conditions after the construction of Taihang Road.
Picture 6-2 Jinyang Smallware Market for resettling the shops to be relocated
103
Picture 6-3 Meiji Smallware Market for resettling the shops to be relocated
6.5 Rehabilitation of Professional Facilities
Affected professional facilities mainly mean power facilities and
telecommunication facilities. As to these facilities, on basis of sufficient consultation
with power and telecommunication organizations, the resettlement organization will
compensate according to the replacement prices of these facilities. Rehabilitation and
reconstruction of these facilities will complete before requisition to ensure the normal
requirement for production and living of population along the line of the project.
6.6 Resettlement and Rehabilitation of Affected Vulnerable
Groups
As for relocated families of vulnerable groups, resettlement offices at all levels and
primary government will provide special help and care. Main measures are:
With respect to the vulnerable groups determined, the project office will provide the
security measures as follows:
According to the survey, if the family only has one dwelling house, the life is poor indeed, and the public has no objection after issuing public announcement, the dwelling
house with building area not less than 50� will be provided. If the building area of
104
resettlement house is less than 50� , the price of structure difference and the expenses for exceeding resettlement area will not be settled.
The resettlement office sets up the funds of RMB 2 million Yuan for helping vulnerable groups according to specific needs during the resettlement course. The funds
will be used strictly conforming to public and transparent management articles. See
Attachment 2 for use method of the funds for helping vulnerable groups.
For area, type and location of resettlement house, the family of vulnerable group has priority in selection.
Resettlement organizations at all levels are responsible for organization manpower
to assist in the moving of the families of vulnerable groups.
6.7 Schedule of Resettlement and Rehabilitation
It is planned that the civil works of this project would start in January 2009. In
order that the affected population and organizations will be appropriately and well
resettled, all land requisition and resettlement activities will be finished before the civil
works starts. See table 6-4 for time arrangement for each resettlement activity.
105
Table 6-4 Schedule of resettlement activities
2006 2007 2008 2009 20102012
Activity2 4 6 8
10
12
2 4 6 810
12
3 6 912
3 6 912
3 6 912
12
Establishment of the ProjectResettlement OfficeEstablishment ofresettlement officesat alllevelsSurvey for land requisitionand relocationPreliminary consultation ofthe resettlement planDraft of theaction plan ofresettlement
Complementary surveys
Modification of theactionplan of resettlementSecond consultation of theresettlement planPerfecting of resettlementplanApproval of the resettlementplanImplementation of theresettlement planInternal monitoring
107
7�Budget and Management of Resettlement Fund
7.1 Constitution of Resettlement Fund
Resettlement fund of this project mainly consists of four parts, namely: land
compensation, compensation rates for relocation, compensation rates for attachments to
the ground and common facilities, management costs for resettlement and contingency.
7.1.1 Land compensation
Land compensation includes compensation rates for land and various expenses of
taxation.
(1)Compensation rates for land
Calculate according to integrated land price in land acquisition area.
(2)Compensation rates for newly-added land used for building
According to regulations in state document, Taiyuan City belongs to the fifth region,
so applicable compensation rate for newly-added land used for building is 64yuan/� . (3)Farmland use tax
Farmland use tax is calculated by virtue of actual area of occupied farmland.
According to relevant regulations of China, Shanxi Province and Taiyuan City, rate for
farmland use tax is 10yuan/� . (4)Management expenses of land acquisition
Management expenses of land acquisition paid to the Ministry of Land and
Resources of P.R.C is 1.5% of compensation rates for land.
7.1.2 Compensation for relocation
Compensation for relocation includes:
(1)Compensation for relocated private houses
Calculate according to area and compensation rates of relocated rural and urban
private houses.
(2)Compensation rates for relocated buildings of enterprises and institutions.
Calculate according to types and areas of relocated buildings of enterprises and
institutions.
(3)Moving costs, transition costs and operating losses
108
Moving costs and transition costs for private houses as well as moving costs for
enterprises and institutions are calculated according to compensation rates, but
transition costs and operating losses of enterprises and institutions are paid according to
consultation.
7.1.3 Compensation for attachments to the ground and common facilities
Compensation for attachments to the ground and common facilities of private
houses and enterprises and institutions is calculated according to actual quantity
investigated and compensation rates.
7.1.4 Management costs of resettlement
Management costs of resettlement include: funds established to help vulnerable
families, administrative costs of resettlement organizations of all levels and resettlement
monitoring costs. According to actuality of Taiyuan Urban Transport Project, fund with
total amount of 2,000,000 is specially established to help vulnerable groups. Moreover,
according to similar projects, administrative costs of resettlement are 5% of resettlement
costs, while resettlement monitoring costs are 0.4% of resettlement costs.
7.1.5 Other costs and contingency
Contingency includes contingency of substances and contingency of prices that are
calculated by 10% of basic costs.
7.2 Budget of Resettlement Fund
According to compensation rates and statistical magnitude of various affected
items, resettlement costs of the World Bank Financed Taiyuan Urban Transport Project
are RMB1,171,806,183 yuan. See Table 7-1 for detailed cost estimate.
Item Unit Qty Compensation rates Sum
I Land compensation 83191761.03
109
Compensation rates for land
(calculate according to
different districts)
Mu 795.47 50000 39773500
Compensation rates for newly-added land used
for building � 536781.
664 33941750.34
Farmland reclamation costs
Mu 93.74 4500 421830
Farmland use tax � 62524.58
10 625245.8
State-owned farmland and forest land
Mu 144 50000 7200000
Management costs of land (1.5% of land costs)
1242593.97
� Compensation for relocated houses Yuan 923865353
Rural private houses 156944.
8257319866
Frame � 97.4 2300 224112
Brick and concrete � 118357.3
1800 213043212
Brick and wood � 23894 1500 35840925Earth and wood � 3832.8 1300 4982627 Simple house � 10763.3 300 3228990
Enterprises and institutions’ houses
266563.4
627309287�
Frame � 58122 2680 155766960
Brick and concrete � 191991.5
2380 398025250�
Brick and wood � 15088.9 1930 29121577�Earth and wood � 26115 1700 44395500
Moving costs 156944.
810 1569448
Transition costs 156944.
8240 37666752
� Compensation for attachments and
facilities 6639751.5
Cave Pore 22 1000 22000 Fence � 23399.2 50 1169960
Timber tree� �10cm 2747 30 82410 Terrace � 12165 30 364950
110
Timber tree <10cm
119 20 2380
Fruit tree with fruits 570 200 114000 Fruit tree without fruits 358 60 21480
Screen wall Piece 291 300 87300
Greenhouse � 19304.05
30 579121.5
Air conditioner Piece 14 200 2800 Telephone Piece 1763 150 264450
Piped television Piece 1711 500 855500 Water well 20 1500 30000
High-voltage line 17 150000 2550000 Low tension wire 714 600 428400
Transformer Piece 13 5000 65000 Management costs of
resettlement 158109317.3
Fund to assist vulnerable group
2000000
Administrative costs of resettlement (5% of basic resettlement
costs)
50684843.28
Resettlement monitoring costs (0.4% of basic resettlement costs)
4054787.462
Contingency (10% of basic resettlement
costs) 101369686.6
Total Yuan 1171806183
7.3 Allocation and Flow of Resettlement Funds
7.3.1 Allocation of resettlement funds
According to property rights of various affected items, resettlement funds of this
project will be allocated to different objects, and see details in Table 7-2. In order to
ensure that sufficient funds will be allocated to displaced persons and units in time, on
one hand, give full play to functions of external monitoring organization, inner
monitoring organization and national auditing organization, on the other hand, try to
reduce middle links, grant resettlement funds to individuals and units directly by easy
and feasible mode.
111
Table 7-1 Allocation object of resettlement funds
Object Types of Costs
Institutions Compensations for relocation, moving, transition and attachments to the ground.
Enterprises Compensations for relocation, moving, transition and attachments to the ground and operating losses.
Collectivity of village
Compensations for land, attachments and collectivity-owned facilities
Families Compensations for relocated houses, attachments, young crops (for the families which young crops are levied), moving and transition.
Other departments
Vairous tax on requisitioned land
7.3.2 Sources and flow of resettlement funds
Resettlement costs of the World Bank Financed Taiyuan Urban Transport Project
are allocated by Project Resettlement Office through resettlement office of each level,
monitored by national auditing organization and external monitoring organization. Flow
of resettlement funds is shown in Chart 7-1.
Taiyuan Municipal Construction and Managment Committee,Taiyuan Municipal Finance Bureau
Taiyuan Urban Transport Project Lead Group Office
Taiyuan Municipal Adminstration Bureau
Taiyuan Municipal Construction and Managment Committee
Trans. ManagementOffice
Taihang Road Office
PT Sub-project Office
NMR Road Office
Resettlement Offices at All Affected District
Affected Households,Collective Units,Enterprises and Shops and Institutions
112
Flow of Resettlement Fund
Fund Planing and Supervising
Figure 7-1 Flow Graph of Resettlement Funds of Taiyuan Urban Transport Project
7.4 Payment, Management and Monitoring of Resettlement
Funds
7.4.1 Payment of resettlement funds
Payment of resettlement funds of this project will adhere to following principles:
All costs relating to land acquisition and relocation will be calculated into general estimate of the project, compensation of land acquisition and relocation and other costs
will be paid to relevant units and persons by project office through coordinating project
office of each level;
Various compensations for private families will be granted to affected families in cash or bankbook directly before relocation by district resettlement office and bank;
Compensation for land will be paid before requisition;
In order to guarantee successful implementation of resettlement, project offices must set up different levels of finance and monitoring organizations to ensure payment
on time.
7.4.2 Management and monitoring of resettlement funds
Budget control is carried out for resettlement funds, special account is set up in
the bank by project office, in which sum of money may only be used as designated and
be paid unifiedly.
Disbursing of resettlement funds must be carried out strictly in accordance with policies in relevant national laws and regulations of land acquisition and relocation and
Resettlement Action Plan, which cannot be lower than or smaller than compensation
rates and scopes determinated by Resettlement Action Plan.
113
As for resettlement funds and relevant costs, enforcement organization of land
acquisition and relocation puts forward application of payment, reports to finance
economic analysis team to unifiedly compile payment plan of funds. Annual payment
plan will be finished compiling before Dec 20th every year and monthly payment plan
will be finished compiling before 25th of every month. Then project office gathers
relevant plans and reports to municipal financial fund management department.
When paying the funds, enforcement team of relocation will be responsible for approval of relocation scope, area and price, but finance economic analysis team will
recheck and gather the data and then submit the report form.
Compensation costs for land, houses, attachments and moving (including inside
facilities transition, moving, transition, rewards for moving in advance, losses of
individual business operators and enterprises and institutions) are approved by
enforcement team of relocation, and then are rechecked by financial personnel in
financial economic analysis team. Then project office authorizes special bank to effect
payment directly to affected individuals and families.
Municipal financial and auditing departments are entitled to monitor and audit usage of the special funds.
Project office makes an internal check of usage of resettlement funds every half year.
Resettlement external monitoring organization specially follows and monitors
payment of compensation for affected families and enterprises and institutions during
independent monitoring.
114
8. Organizational Framework of Resettlement
8.1 Organizational Establishment
In order to get done with the resettlement for the Urban Transport Project of
Taiyuan City, all levels of governments of Taiyuan City guarantee the smooth
implementation of preparation for the project and resettlement beginning with the
establishment of organizational framework and the strengthening of capacity. In January
2006, Taiyuan Urban Transport Project Leading Group Office was established
officially; in March 2006, Taiyuan Urban Transport Project Resettlement Office was
established officially. In October 2006, under the organization of Taiyuan Development
and Reform Commission and the support of all levels of governments, Taiyuan Urban
Transport Project Resettlement Office and the resettlement organizations at districts and
towns (offices) levels along the lines were established officially. In December, Taiyuan
Municipal Government officially confirmed that the Project Resettlement Office is
under the administration of Taiyuan Administration Bureau of Municipal Construction.
Therefore, the main organizations relevant to the resettlement of the project include:
·Taiyuan Urban Transport Project Leading Group Office
·Taiyuan Urban Transport Project Resettlement Office
·Resettlement offices of all districts within affected range
·Resettlement offices of all offices (towns) within affected range
·Resettlement groups of all communities (villages)
·Independent monitoring organization of resettlement—Center for Resettlement
Research, Wuhan University
The network of organizational framework of resettlement is shown in Figure 8-1.
115
Figure 8-1 Organizational Framework of Taiyuan Urban Transport Project
Resettlement
8.2 Responsibilities of All Organizations
8.2.1 Project Leading Group Office
·Leading the preparation and implementation of the project completely
·Making decisions on important policies of resettlement
·Coordinating the relationship of resettlement organizations and relevant
governmental departments
8.2.2 Project Resettlement Office
·Commissioning survey and design institutes and participating in the determination
of impact of resettlement, implementing population statistics, keeping data and training
resettlement personnel who are responsible for data use
·Applying to relevant departments for land-use planning license and land-use
construction license
·Formulating all policies of resettlement action plan
·Training resettlement office personnel of all districts
·Coordinating implementation progress of construction of the project and
resettlement action plan
Leading Group Office of Taiyuan Urban Transport Project
Taiyuan Urban Transport Project Resettlement Office
Center for Resettlement Research, Wuhan
Resettle-ment Office of Wanbolin
Resettle-ment Office of Jiancaoping
Resettle-ment Office of Xinghualing
Resettle-ment Office of Yingze
Resettle-ment Office of Xiaodian
Resettle-ment Office of Jinyuan
Resettlement offices of all affected towns (streets, offices)
Resettlement groups of all affected communities (villages)
116
·Signing resettlement contracts with land administrative departments and people’s
government of all districts
·Supervising the appropriation of fund
·Directing and supervising the implementation of resettlement
·Coordinating the work of relevant organizations of resettlement
·Supervising resettlement
·Inspecting supervision report
·Supplying the budget of resettlement
·Dealing with complaints of migrants in the process of resettlement.
8.2.3 Resettlement Offices of Districts
Resettlement Offices of Districts are the major departments that implement
resettlement concretely, whose main responsibilities are:
·Formulating resettlement implementation plan of the district according to data
offered by survey and design institutes and resettlement policies
·Organizing resettlement implementation work concretely
·Directing and supervising the work of resettlement offices of towns (offices)
·Accepting and managing resettlement fund appropriated by Project Resettlement
Office
·Distributing resettlement fund to towns (offices) and villages (communities)
resettlement groups and supervising its use
·Training resettlement office personnel of towns (offices)
·Reporting work to Project Resettlement Office
·Dealing with problems in the process of resettlement and reporting complaints of
migrants to superior resettlement organizations
8.2.4 Resettlement Office of Towns (Offices)
·Inspecting, supervising and recording all resettlement activities within its
administrative region
117
·Supervising and implementing land requisition, reconstruction and relocation of other
structures, enterprises as well as buildings
·Arranging the employment and training of affected population in township
enterprises
·Dealing with problems in the process of resettlement and reporting complaints of
migrants to superior resettlement organizations
8.2.5 Resettlement Group of Villages (Communities)
·Reporting and verifying relocation data of the village
·Participating in survey and other necessary resettlement organization work
·Organizing public participation and resettlement consultation work within the
administrative region
·Assisting superior resettlement organization to implement resettlement plan
·Helping affected population within the administrative region to report problems
and advices
·Reporting resettlement progress
8.2.6 Design Institute
·Determining affected region of the project and offering detailed drawings
·Assisting project office and survey organization to survey
·Consulting opinions and advices of multiple parties, optimizing the design of the
project and reducing resettlement
·Supply technical assistance for the preparation and implementation of
Resettlement Action Plan of Project Resettlement Office
8.2.7 Independent Monitoring Organization
In the process of the planning and implementation of resettlement, it is responsible
for the independent monitoring of resettlement work, and supplies resettlement progress
report and supervision report for Project Settlement Office and World Bank. The
responsibilities of the organization are shown in the chapter independent monitoring in
details
118
8.3 Personnel and Equipments of Resettlement Organizations
at all Levels
Presently, there are five personnel in Project Resettlement Office, all of which have
strong organization and coordination abilities, resettlement experience and computer
skills. The resettlement organization of all districts and towns (offices) are also
composed of personnel with high caliber and rich experience who are perfectly
competent for the requirement of resettlement work. Personnel list is shown in table 8-1.
Project Resettlement Office has equipped resettlement offices of all districts with
equipments like computers, etc. Personnel and equipments of resettlement organizations
at all levels are shown in table 8-2 and table 8-3 respectively.
Table 8-1 Member list of all levels of resettlement offices for Taiyuan Urban
Transport Project
Resettlement offices of districts and offices
Principal of the office � Personnel
Project Resettlement Office Liu Xiaojun Zhao Wenhui, Hao Jianpin, Qu Xiaolan
Resettlement Office of Wanbolin District
Li Longxi Li Xiaochu, Sui Yan, Wu Xiaojun
Resettlement Office of Wanbolin Office
Li Bo Wang Hongfeng
Resettlement Office of Jiancaoping District
Niu Dongquan
Guo Bianfang, Miao Changqing, Xing Liang
Resettlement Office of Huifeng Office
Liang Binglong Yang Erdong, Yuan Quan
Resettlement Office of Gucheng Office
Liu Jianxin Zhang Rong, Wang Jianfa
Resettlement Office of Xinghualing District
Zhao Lin Li Jianghong, Hu Biansheng,
Wang Sufang
Resettlement Office of Julun Office Ye Jianping Wang Baoqin, Zhao Xiaobin, Li Chunling
Resettlement Office of Dunhuafang Office
Yan DongmeiWang Zhimin, Jiang Liping, Wang Fengxian
Resettlement Office of Yangjiayu Office
Xiao Chun’e Zhang Yonghong, Yang Junping
Resettlement Office of Xinjie Office Chen Hongbin
Zhao Wei, Zhang Gaixiang, Ren Zhongman
Resettlement Office of Dadongguan Office
Yao Jingzhong
Liu Guizhen, Hu Haiyu
Resettlement Office of Yingze District
Yang Congjie Wu Jianping, Zhang Yi
119
Resettlement Office of Haozhuang Town
Wang Dongde
Jiao Yan, Gao Hong
Resettlement Office of Xiaodian District
Wang Jianjun Zhao Shiliang, Wang Jianmin
Resettlement Office of Beiying Office
Ma Ming Zhap Futang, Zhao Huping
Resettlement Office of Jinyuan District
Liu Hui Huo Yanchao, Xie Chunbao
Table 8-2 Personnel placement of all levels of resettlement organizations
Resettlement organization
Basic personnel
Total personne
lPersonnel and qualification
Time for working and operation
Project Resettlement Office
3 5
Personnel are familiar with foreign languages, computer, engineering and resettlement.
From January 2006 to the end of resettlement work
Resettlement offices of districts
5 7
Leaders of development and reform commissions of districts are in command. Personnel own educational attainments above junior college.
From October 2006 to the end of resettlement work
Resettlement offices of towns (offices)
3 5
Major leaders of towns (offices) are in command. Personnel own educational attainments above technical secondary school.
From October 2006 to the end of resettlement work
Resettlement groups of villages (communities)
2 3Major leaders of villages (communities) participate in personally.
From November 2006 to the end of resettlement work
Independent monitoring organization
3 5
With long experience of similar jobs and educational attainments above master
From January 2006 to the completion of the evaluation of resettlement work
Table 8-3 Equipments of all levels of resettlement organizations
Operating organization Comput
er
Telephone (mobile phone)
Camera Operatio
nvehicle
Office (� )
Project Resettlement Office
3 3 1 1 200
120
Resettlement offices of districts
1 5 1 1 100
Resettlement offices of towns (offices)
0 3 1 0 100
Independent monitoring organization
3 3 1 0 40
8.4 Measures for the Strengthening of Organizational
Capacity
In order to enhance the quality of personnel of all levels of resettlement
organizations, strengthen the capacity of resettlement organizations, make personnel of
resettlement organizations get familiar with relevant resettlement laws and regulations,
understand more requirements of World Bank as to involuntary resettlement and
guarantee the smooth implementation of resettlement work in the project, Project
Resettlement Office has trained personnel who have learned relevant resettlement
policies and regulations of China and the operational policy of involuntary resettlement
of World Bank OP4.12/BP4.12. The training that has been completed is shown in Table
8-4.
Table 8-4 Operational training plan table of resettlement personnel
Responsible training organization
Training content Trainee Training
time No.
A B C D
1Project Resettlement Office
Having learned and surveyed the experience of project resettlement of other provinces and visited projects in Shanghai, Nanchang, Wuhan, Liaoyang, Shijiazhuang
Project Resettlement Office
2006.1�2006.12
2Project Resettlement Office
Training on procedure, arrangement and survey of resettlement
Project Resettlement Office, resettlement office of districts
2006.11
3Project Resettlement Office
Computer operation and data processing
Project Resettlement Office
2006.6�12
4Project Resettlement Office
Learning of relevant migration regulations of China and operational policies of World
Project Resettlement Office
2006.6�12
121
Bank
5Project Resettlement Office
Procedure, management and supervision of appropriation of fund
Resettlement office of districts
2006.12
6Project Resettlement Office
Processing methods of resettlement information
Project Resettlement Office
2006.11
7Resettlement offices of districts
Procedure and policies of resettlement
Resettlement offices of offices (towns), resettlement groups of villages
2006.12
8Project Resettlement Office
Resettlement policies of World Bank
Project Resettlement Office
2007.3
9Project Resettlement Office
Newest land requisition and relocation policies of China
Project Resettlement Office
2007.9
10 Project Resettlement Office
Experience of resettlement of other cities in China
Project Resettlement Office
2008.3
8.5 Plans for the Strengthening of Organizational Capacity in
the Future
To implement Resettlement Action Plan all the better, guarantee benefits of
affected population and satisfy the general planning of project progress, Project
Resettlement Office will take following measures to strengthen the organizational
capacity and increase efficiency.
1. Leader’s responsibility system: The forceful leadership groups that are in the
charge of branch leaders of all the district government and are composed of leaders of
relevant departments like development and reform commissions will be founded.
2. Arranging high caliber personnel: all levels of personnel of resettlement
organizations are required to have strong overall ideas, understanding of policy and
special capacity, especially for experience of mass service
3. Definition of responsibility: The responsibilities of all levels of resettlement
offices will be defined according to the requirements of World Bank and relevant laws
and regulation of China.
122
4. Training of resettlement personnel: According to requirements of resettlement
work, personnel will receive training on resettlement policies and information
management, etc. at irregular intervals
5. Making use of supervision of the mass and public opinions: All the resettlement
materials will be disclosed to the mass and society and can be supervised by the mass
and public opinions anytime
6. Resettlement report meeting presided by provincial resettlement office will be
held at irregular intervals and the report will be distributed to all districts in the form of
briefing.
7. Project Resettlement Office will equip all levels of resettlement organizations
with necessary vehicles and relevant office facilities to meet the requirements of the
work.
The strengthening of organizations and training plans for the future are shown in
Table 8-5.
Table 8-5 Next operational training plan table of resettlement organizations
Responsible training organization
Training content Trainee Training time No.
A B C D
1Project Resettlement Office
To learn and survey the experience of project resettlement of World Bank from other provinces
Personnel from Project Resettlement Office, resettlement office of districts
2008� 2009
2
Center for Resettlement Research, Wuhan University
Resettlement policies of World Bank
Personnel from Project Resettlement Office, resettlement office of districts
2008.7
3
Center for Resettlement Research, Wuhan University
Newest changes of land requisition and relocation policies of China
Personnel from Project Resettlement Office, resettlement office of districts
2008.8
123
4Project Resettlement Office
Experience of resettlement of other places
Personnel from Project Resettlement Office, resettlement office of districts
2008.9
5Project Resettlement Office
Computer operation and data processing
Project Resettlement Office, resettlement office of districts
2008.11� 12
6Resettlement offices of all districts
Procedure and policies of World Bank financed project resettlement
Resettlement offices of offices (towns), resettlement groups of villages
2009.1
7Resettlement offices of all districts
Policy and practice of resettlement
Resettlement offices of offices (towns), resettlement groups of villages
2009.2
8Resettlement offices of all districts
Survey of international experience of resettlement
Personnel from Project Resettlement Office, resettlement office of districts
2009� 2011
124
9�Public Participation and Consultation
In order to make the resettlement work of World Bank financed Taiyuan Urban
Transport Project base on a feasible and reliable foundation, ensure the lawful rights and
interests of migrants and relocated enterprises and reduce dissatisfaction and dispute,
the project attaches great importance to the participation and consultation of migrants.
Resettlement Action Plan is prepared on the basis of full negotiation and information
disclosure of affected population. Therefore, in the decision process of the planning,
design and implementation of the project, Resettlement Office of Taiyuan World Bank
Financed Project and all levels of resettlement offices together with all the consultant
institutions make use of opportunities like socioeconomic surveys and social impact
evaluation to propagandize the background of the project in various ways, take counsel
with all kinds of affected population and negotiate about common concerns. Public
participation and consultation provide basis for the improvement of resettlement plan.
9.1 Activities Carried out up to Now
As to all significant topics for discussion involved in the planning stage of
resettlement, Project Resettlement Office has organized design organizations, consultant
organizations, local resettlement departments and affected population to disclose
information and conduct consultation in various ways. Main disclosure and consultation
activities so far are shown in Table 9-1.
Table 9-1 Main activities of resettlement information disclosure and consultation
No. Time Content of disclosure and consultation
Participant Organizer
12006.5�2007.3
Optimation of project design scheme
The design institute, Project Resettlement Office, resettlement offices of all districts, representatives of village collectives and affected population
Project Resettlement Office and resettlement offices of all districts
32006.12� 2007.1
Amount of land requisition and relocation
Wuhan University, Project Resettlement Office, resettlement offices of all districts, affected enterprises, affected population
Project Resettlement Office and resettlement offices of all districts
125
42006.11—2007.3
Compensation rate for land requisition
Project Resettlement Office, resettlement offices of all districts, representatives of local village, group collectives and affected population
Project Resettlement Office and resettlement offices of all districts
52006.11—2007.3
Compensation rate for houses
Project Resettlement Office, resettlement offices of all districts, representatives of local village, group collectives and affected population
Project Resettlement Office and resettlement offices of all districts
62006.12� 2007.3
Social impact of the project
Liaoning Academy of Social Sciences, Project Resettlement Office, resettlement offices of all districts, affected population, affected enterprises and institutions
Project Resettlement Office and resettlement offices of all districts
72006.12� 2007.1
Resettlement mode and desire
Wuhan University, Project Resettlement Office, resettlement offices of all districts, affected enterprises, affected population
Project Resettlement Office and resettlement offices of all districts
82006 12� 2007 1
Resettlement policies
Project Resettlement Office, resettlement offices of all districts, affected enterprises and institutions
Project Resettlement Office and resettlement offices of all districts
92007 5� 8
Consultation on resettlement locations
Project Resettlement Office, resettlement offices of all districts, affected enterprises, affected population
Project Resettlement Office and resettlement offices of all districts
82007 12� 20085
Resettlement of enterprises and institutions
Project Resettlement Office, resettlement offices of all districts, affected enterprises
Project Resettlement Office and resettlement offices of all districts
In September 2006, the delegation of World Bank evaluated the content of the
project. From December 2006 to January 2007, according to the result of evaluation,
Center for Resettlement Research, Wuhan University carried out a relatively large-scale
126
questionnaire about opinion and advice of public participation for affected areas. It
selected a family member above 15 years old from 347 affected households on whom
the questionnaire survey was conducted. The summarized results of the survey are
shown in Table 9.2.
Table 9-2 Summarized table of public opinions and advices
Content of survey Opinion or advice Proportion (%)
� . Be clear about the construction or not (single choice)
NA 0.87 1 Clear 25.76 2 Not so clear 32.31 3 Not clear 41.05
� . Support the construction of the project or not (single choice)
NA 2.18 1 Support 62.88 2 Don’t support 27.07 3 Don’t care 7.86
� . Potential advantages of the construction of the project (multiple choices)
1 Convenient traffic 75.65 2 Investment opportunity 21.30 3 Employment opportunity 16.09 4 Market information 12.23 5 Others 7.86
� . Potential disadvantages of the project (multiple choices)
1 Inconvenient 5.22 2 Environmental impact 19.57 3 Scarcity of land 30.43 4 Others 25.65
� . Be clear about land requisition or relocation compensation policies or not (single choice)
NA 3.91 1 Clear 7.83 2 Not so clear 20.43
127
3 Not clear 67.83 � . Opinions and advices on land requisition and relocation of the project (multiple choices)
1 Reduce relocation as much as possible33.91 2 Reduce land requisition as much as possible
13.60
3 Make traffic as convenient as possible 22.61 4 Take the convenience and safety of citizens’ traffic along the lines into full consideration
67.83
� . Desire for reconstruction of houses (only for rural households, multiple choices)
1 Unified planning and centralized construction
26.96
2 Freely select house site and submit to the village for approval
35.22
3 Be given money compensation and purchase house by oneself
30.43
� . Opinions on the use and allocation of land compensation funds and labor settlement fees (only for rural households, multiple choices)
1 All are allocated to affected households; cropland is not to be adjusted; and affected population seek jobs by themselves
47.83
2 All are controlled and used by the collectives and land is to be adjusted.
7.39
3 Part of them are allocated to directly or indirectly affected households and then land is to be adjusted
5.65
4 All are invested to develop enterprises and land is not to be adjusted.
0.87
5 Offer employment opportunities other than peasants
5.65
� . Desire for relocation of houses (only for urban households, multiple choices)
1 Implement relocation with material objects; and supply relocation houses
84.70
128
2 Implement money relocation 7.76 3 Implement the combined relocation of material objects and money; and relocated household choose by themselves.
17.35
4 Have no opinion of one’s own and obey to the arrangement of the government
3.20
Source of data: Socioeconomic survey data of World Bank Financed Taiyuan Urban
Transport Project
The following several conclusions can be drawn from the analysis of statistical
data:
Firstly, in the aspect of the extent of acquaintance with the project, survey data
show that affected population are not so acquainted with the background of the project
and relocation compensation policies. Only about 1/4 of the respondents is clear about
the background of the project while the other 3/4 of them are not clear or not so clear
about it, especially for the definite land requisition and relocation time; and in the aspect
of compensation policies, about 90% of them are not clear or not so clear about land
requisition or relocation policies. At the same time, it is also found that those who are
not clear are mainly peasants, since many of them haven’t received the information
relevant to the project through formal channels. This indicates that the project needs
improvement in the aspect of propaganda. It is advised to enhance propaganda, make
use of various propaganda methods like television, broadcast, etc., and transmit relevant
information of the project widely. Meanwhile, public participation needs to be
strengthened to give affected population profound understanding and sufficient
knowledge of the project.
Secondly, in the aspect of opinions of the project, most of affected population
supports the implementation of it. About 70% of respondents support or not oppose the
construction of the project. And when it comes to the advantages and disadvantages of
the project, 3/4 of them believe that the best advantage of the project is convenient
traffic and then comes employment opportunity. As to the disadvantages, the worst
disadvantage is considered to be the scarcity of land and about 1/3 of them holds this
opinion. The advices on the project focus on two aspects: the first one is taking the
129
convenience and safety of citizens’ traffic along the lines into full consideration; and the
other is reducing relocation.
Thirdly, as to desires for relocation of houses, villagers is more prone to free
selection of house sites and money compensation; then comes money compensation and
purchase of houses by themselves. They are not interested in the mode unified planning
and centralized construction by the government. However, urban residents are prone to
implementation of relocation with material objects and supply of relocation houses; the
combined relocation of material objects and money follows; and they are not interested
in the simple money relocation mode.
Fourthly, in the aspects of the use and allocation of land compensation funds and
labor settlement fees of villagers, respondents are more prone to all allocation of
compensation funds to affected population for free use rather than unified use by the
village. In the aspect of employment, residents are more prone to seek jobs by
themselves and are not interested in employment opportunities other than peasants.
9.2 Feedback on Public Participation and Consultation
From December 2006, Center for Resettlement Research, Wuhan University
carried out socioeconomic surveys for affected population, generalized and summarized
the opinions and advices put forward by them, timely fed back to engineering design
organizations, and fully considered and absorbed these opinions and advices when
formulating resettlement action plan. Feedback on public participation and consultation
up to now is shown in Table 9-3.
Table 9-3 Feedback on public participation and consultation of World Bank Financed
Taiyuan Urban Transport Project
Item Problem Reason and result Measures for improvement
Land requisition and relocation
The construction of urban traffic will occupy many houses.
It makes residents lose original houses. And part of residents with rent incomes as their main sources may lose original income sources.
Try to avoid or reduce the compact districts of houses passed through in the design of the project. Provide money resettlement and resettlement in material objects to be selected by the relocated households.
130
Item Problem Reason and result Measures for improvement
The construction of urban traffic will exert considerable impact on the production and operation of part of enterprises and institutions.
Some enterprises will be removed because their main workshops are within the red line, which leads to their failure to production and operation; and still some institutions will need whole relocation because their main office buildings are removed, which may affects their normal working.
Try to avoid or reduce the main workshops of enterprises and main office buildings of institutions passed through in the design of the project
The construction of urban traffic will affect teaching of individual schools and safety of students
Own to relocation, study of students of individual schools may be affected. And individual schools will be divided into two parts by the road. Parents worry about the safety of students.
Build new schools in advance and guarantee normal study of students. Increase underground passages where roads pass through schools to guarantee safety of students.
Badly informed. Most of residents, particularly for peasants, haven’t received relevant information of the project through formal channels, especially for definite land requisition and relocation time.
Relocated households and tenants will be affected and may not arrange their own living timely. Residents who live on rental will be confronted with the risk that tenants leave in advance and houses are vacant while tenants will also be confronted with the risk that living or operation can’t be arranged fully.
Determine the construction lines of roads as soon as possible and inform affected population of them timely. So relocated households can build new houses timely and tenants can arrange their living in advance. At the same time, it is advised that relevant information of the project should be widely spread to give affected population profound understanding and sufficient knowledge in popular ways, such as broadcast, television, local drama, play let, song, regular meeting, etc.
131
Item Problem Reason and result Measures for improvement Relocated households worry that the government may ask them to apply for house sites again.
It leads to the loss of money and time of relocated households.
The house sites for the reconstruction of relocated households will not undergo complex approval and approval procedures will be reduced.
Relocated households worry that they may be migrated to villages outside of their former residence.
In new residence, they may receive discrimination. Meanwhile, some residents worry that the new place may be unfit for rent. Original rental may decrease and they may loss living support.
Settlement in vicinity.
The masses are concerned about the compensation and allocation of the funds.
The compensation and allocation of the funds are related to living support of relocated households.
The government and road traffic departments should bulletin relevant compensation rate before the construction of roads and make the masses well-informed.
Compensation funds
Allocation mode of compensation funds.
Some residents worry that compensation funds won’t be allocated fully or will be held back.
It is advised that strict institutional and financial disclosure should be implemented, such as disclosure of compensation rate, measurement size, evaluation grade, etc. After the determination of compensation funds, they should be pasted for disclosure and subject to the participation and supervision of affected population. Compensation funds are directly allocated to the peasants in the form of bankbooks.
132
Item Problem Reason and result Measures for improvement
The construction of the Project will cause damage to infrastructure to different extents.
The lines will cause damage to original power and communication facilities (e.g. wire stands, transformers and communication transmission towers) to some extent. And water and heating facilities of some residents and enterprises are also involved (e.g. well house in villages; boilers and reservoirs of enterprises), which exerts negative influence to production and residents’ living.
Try to reduce damages to existing public facilities; maintain damaged public facilities or change their courses in the process of construction to avoid unnecessary conflicts. Try to repair and rebuild damaged water resource facilities like wells, boilers, reservoirs, etc. as well as power and communication facilities.
Public facilities and environment
Noise pollution
Because traffic on roads causes a lot of noise, normal work and rest of the residents living near to roads will be affected.
It is advised to enlarge relocation range reasonably. If relocation is hard to be implemented, sound-insulated wall may be set to reduce noise, or proper compensation may be paid.
Compensation for operating loss
Business operators’ wage and profit losses will not be compensated
Publicize the relocation information as early as possible, provide operators sufficient time to respond the impact of relocation; offer compensation for wage and profit losses according to tax payment records
Compensation for commercial stores
Handling of relationship between owner and renter
Compensation fund will all be retained by the owner, and the renter’s interests will not be secured.
The compensation fund will be distributed to different persons according to ownership: compensation for house will be given to the owner, and compensation for decoration, wage and profit losses will be given to the renter.
Auxiliary facilities
Some auxiliary facilities are to
Traffic facilities for crossing the road.
It is advised to build pedestrian bridges or
133
Item Problem Reason and result Measures for improvement be established. underground passages in
places where there are schools or the population is dense.
Mass participation
Let displaced persons take part in each link of the project.
Let displaced persons share project benefits and promote the enthusiasm of local governments at all levels and the masses.
To establish channels for complaints and feedback, for instance, hot line for complaints and suggestion boxes. To set up a consultative system. To hold as many as possible consultation meetings participated by project office, town government, street offices, representatives of village committees and displaced persons.
9.3 Next Consultation Plan with Affected Population
With the continual advance of the preparation and construction of the project,
Project Resettlement Office and local resettlement offices will carry out further
consultation activities. Main contents of consultation include:
Concrete opinions of affected population on engineering design
Before the construction, all local resettlement offices will inform the offices of
village collectives and streets along the lines of the structure designs of design
organizations. At the beginning of the construction, Project Resettlement Office will
implement exploratory survey along the lines and determine the concrete positions and
sizes and so on of structures. For places with which the masses aren’t very satisfied,
Project Resettlement Office will organize the design department again to revise the
design on the premise that engineering standards are met.
Location selection (at least twice) of residential building reconstruction and reconstruction method
Arrangement of compensation for relocated households and payment procedures
Employment modes of work force and production recovery measures
134
How to rehabilitate electricity and water supply functions affected during the
construction period
Other problems concerned by displaced persons, for instance, indirect influence on working and living conditions of residents who live outside the red line.
See Table 9-4 for time arrangement for further consultation meetings of
resettlement offices at all levels and displaced persons. According to work arrangement
of Project Resettlement Office, districts, towns (street offices) and villages
(communities) may hold consultation meetings and report relevant situations to Project
Resettlement Office. Besides participating in the consultation activities organized by
Project Resettlement Office, monitoring departments also should hold meetings on other
monitoring problems and collect the complaints and suggestions of affected people, and
then provide monitoring information to land acquisition departments at all levels.
Table 9-4 Time arrangement for consultative meetings with displaced persons
Content Time Attendee
Comments on engineering design
May to Jul., 2008
Project Resettlement Office, design
department, resettlement offices of
all districts, external monitoring
institution
Resettlement mode and concrete implementation plan
Jul. to Sept., 2008
Project Resettlement Office, design department, resettlement offices of all districts, external monitoring institution
Rehabilitation of electricity, water and heat supply
Sept. to Oct., 2008
Project Resettlement Office, district-level and town-level (street) resettlement offices, external monitoring institution
Indirect influence beyond the red line
The whole period of project implementation
Resettlement offices and external monitoring institutions at all levels
Collection of suggestions and complaints
Aug., 2008 to Dec., 2010
Monitoring department, resettlement office, district-level and town-level (street) resettlement offices
135
9.4 Consultation Modes of Affected Population during Project
Implementation Period
1. Direct mode
Displaced persons meeting
Meetings with representatives of displaced persons or village cadres should be held
to collect their key problems and ideas for which ideas from local government and
resettlement office should be obtained.
Enterprises and institutions consultative meeting
For relocation site, compensation ratio, etc. concerning enterprises and institutions,
agreements should be reached with their legal persons or representatives through
consultations.
District-level consultation meeting on land acquisition
Consultation meeting on land acquisition and relocation should be organized
jointly by resettlement offices at all levels and held separately. Organize displaced
persons to visit the resettlement location and auxiliary facilities for the convenience of
their selections. And collect their opinions to improve Resettlement Action Plan. After
the meeting, relevant personnel should visit displaced persons and the latter should sign
Resettlement Compensation Agreement through full consultation.
2. Indirect mode
Displaced persons may reflect their complaints, ideals and suggestions to village
(community) committee and resettlement and monitoring departments at all levels. The
resettlement offices should feedback relevant handling ideas.
9.5 Policy Disclosure and Resettlement Information Booklet
In order to let all affected population understand in time and thoroughly the
resettlement policy and implementation of the project so that resettlement can be carried
out openly and fairly, resettlement agencies at all levels will adopt the following
measures:
136
Before December 31, 2008, the resettlement policy and standard will be published in Taiyuan Evening News;
Each affected village/community should disclose its situation of affected population, compensation rates, resettlement measures, and complaint and appeal
channels, and so on in the presence of cadres of village/community, or in other public
places;
Before December 31, 2008, booklets are available at the public libraries or other public places of affected areas, to which all displaced population may refer at any
moment;
Provide one Resettlement Information Booklet for each household affected
The following will be listed in detail in the Resettlement Information Booklet: the
situations of various affected families, proper compensation policy and compensation
rates, project progress, procedures for solving dissatisfactions and complaints of
displaced persons. The booklet will be issued prior to the formal commencement of the
project, and its pattern is as Attachment-3.
137
10. Complaint and Appeal Since land acquisition and resettlement relate to various aspects, it is a complicated
work. It is inevitable that the displaced persons may be dissatisfied at some matters such
as resettlement and compensation and have some complaints during the implementation,
as it relates to the benefit of displaced persons. To ensure the complaints of displaced
persons can be handled smoothly and rapidly, the resettlement office of the World Bank
Financed Taiyuan Urban Transport Project will establish a transparent and feasible
collecting and handling procedure of dissatisfaction and complaints to deal with such
issues objectively and efficiently.
10.1 Means of Collecting Dissatisfaction and Complaints
(1) The report of local resettlement office, which includes complaints of the
masses, the progress of resettlement, working measures and existing problems
(2) The construction log faxed to the Employer by the construction organizer,
which show whether and how the masses affect the construction
(3) The site inspection of the Employ, during which the problems relating to the
land acquisition and resettlement may be found
(4) Relevant information provided by the independent monitoring organization
(5) Letters and visits of the displaced persons
(6) Information provided by the workstation of the Employer
(7) Relevant problems found by auditor and discipline inspection departments
(8) Information on payment of land compensation shown on the fund transfer list
provided by the bank
(9) Specific survey of internal monitoring agency
10.2 Procedure of Complaining and Appealing
Stage 1
The displaced persons give their oral or written complaints to the village
(community) committee or local resettlement office. In case of oral complaint, the
village (community) committee or local resettlement office must keep a written record
and give a clear reply within 2 weeks. If it is a big issue that shall be submitted to the
138
superior resettlement office, the village (community) committee or local resettlement
office shall try to get the comments of the superior resettlement office within 2 weeks.
Stage 2
If the reply given in the Stage 1 fails in satisfying the complainer, the complainer
may appeal to the district resettlement office within 1 month after receiving the decision
of Stage 1. The district resettlement office shall make a decision on the appeal within 3
weeks.
Stage 3
If the complainer is dissatisfied with the replay of the district resettlement office,
he or she may appeal to the Resettlement Office of the World Bank Financed Taiyuan
Urban Transport Project within 1 month after receiving the reply of stage 2. The Project
Resettlement Office will give its comment within 4 weeks.
Stage 4
If the complainer is still dissatisfied with the reply of Stage 3, he or she may appeal
to civil court within 15 days after receiving the reply.
10.3 The Principles of Handling Complaints
The resettlement offices at various levels must carry out site survey on the
complaints of the masses, collect the their opinions and negotiate with them patiently, in
accordance with the principles and standards stipulated in the rules and regulations of
the state and the Resettlement Action Plan, and give comments objectively and
reasonably. The resettlement office shall report those problems that cannot be handled
on its own to the superior resettlement office timely and assist the latter in carrying out
relevant survey.
If the resettlement office of the previous stage fails in giving a reply within the
specified period to the complaint, the complainer has the right of appeal.
During the resettlement, some special complaints and appeals of women may
appear, therefore the project office plans to hire at least 1 female employee for each
resettlement team to deal with women’s complaints. The local governmental and
non-governmental organizations, such as the Bureau of Civil Affairs and the Women's
Association will supervise the resettlement to ensure the rights and interests of the
displaced persons, especially that of affected women.
139
10.4 Contents of the Reply and Ways of Replying to
Complaints
10.4.1 Contents of the reply
Brief description of the complaint The result of survey
The principles and standards stipulated in the rules and regulations of the state and the Resettlement Action Plan
Comments on handling the complaint and its basis The complainer has the right of appealing to the superior settlement office and
the civil court and the charges shall be paid by the project organizer.
10.4.2 Replying to complaints
As to the individual complaint, written reply shall be sent to the complainer directly.
As to the common complaint, the reply shall be announced in the village
(community) meeting or shall be notified to the village or community in the form of
formal document.
Whatever way of replying is adopted, the replay shall be sent to the corresponding
resettlement office of the complainer.
10.5 Record of Complaints and Appeals and Relevant
Feedback
During the implementation of the Resettlement Action Plan, the resettlement office
shall keep a record of complaints and the results of handling and submit a written report
to the Project Resettlement Office, which will carry out a regular inspection on the
record of complaints handling.
To keep a complete record of the complaints of the displaced persons and the
handling of relevant issues, the Project Resettlement Office has designed a record form
for this purpose, shown as Table 10-1.
140
Table 10-1 Record form of complaints and appeals on the resettlement of the World
Bank Financed Taiyuan Urban Transport Project
Acceptor: Time: Place:
Complainer Content Demanded solution Planned solution
Actual handling
Complainer (Signature)
Recorder (signature)
Remarks: 1. The recorder shall register the actual complaint and demand of the complainer. 2. The complaining shall not be disturbed or hindered by any factor. 3. The planned solution shall be notified to the complainer in the specified period.
The main contents of this chapter will be publicized to the displaced persons and
delivered to each affected household, public institution and business in the form of
publicity material before the implementation of resettlement.
10.6 Contact Information for Expressing Complaints and
Appeals
The resettlement offices of the districts shall arrange the principles to collect and
receive the complaints and appeals of the displaced persons. See Table 10-2 for their
names, office addresses, and telephone numbers.
Table 10-2 Information of the machinery and persons for receiving the complaints and
appeals of displaced persons
Resettment office of districts and offices
Liaisons Address Telephone
Project Resettlement Office
Liu Xiaoj
No.38, Fuxi Street, T i
4152223
141
Office Xiaojun Taiyuan
Resettlement office of Wanbailin district
Li Longxi
No.35, Xikuang Street, Taiyuan
6060678
Resettlement office of Jiancaoping district
Niu Dongqua
n
Chai Village, Jiancaoping District, Taiyuan
5648860
Resettlement office of Xinghualing district
Zhao Lin No.232, Jiefang Road,
Taiyuan 3041595
Resettlement office of Yingze district
Yang Congjie
No.15, Yunlu Street, Taiyuan
4033472
Resettlement office of Xiaodian district
Wang Jianjun
No.16, Changsheng West Street, Taiyuan
7198299
Resettlement office of Jinyuan district
Liu Hui No. 221, Shuangta West
Street, Taiyuan 4633094
142
11. Resettlement Monitoring
11.1 Internal Monitoring
11.1.1 Purpose and principles
The internal monitoring indicates the continuous internal monitoring on the
implementation of the Resettlement Action Plan carried out by the Employer and the
resettlement offices throughout the management system. It aims at obtaining the
accurate progress of resettlement timely and integrally, finding and solving problems
and providing the basis of decision-making for the smooth implementation of
resettlement.
The purpose of internal monitoring provides a criteria and guidance for the internal
monitoring of resettlement carried out by the Employer, the resettlement offices and the
organizations relating to the resettlement to ensure that the implementation of
resettlement complies with the Resettlement Action Plan and the resettlement
monitoring and evaluation are carried out orderly, normally and efficiently, therefore
the relevant organizations may get to know the implementation of the resettlement
timely and the problems occurred may be found and eliminated early.
The principles of internal monitoring include: to conduct regular survey and
evaluation on the implementation of the Resettlement Action Plan, to collect data and
analyze information accurately to ensure the accuracy of the results of monitoring, to
conduct scientific and objective evaluation on the implementation of the Resettlement
Action Plan justly and to submit report to the Employer and the World Bank in time to
keep them informed of the progress of the project and able to make scientific decision.
The function of internal monitoring: The internal monitoring is an important
integral part of the internal management of the project; it directs to mastering the
implementation of resettlement; through the establishment and use of resettlement
information management system, the progress of the implementation of the resettlement
and the data and information of the relevant funds and quality are collected, analyzed
and shared and the existing and potential problems and the causes may be found and the
measures and suggestions on solving the problems may be proposed.
143
The internal monitoring of the resettlement shall be conducted by the Employer
and the resettlement offices and the Employer shall submit the internal monitoring
report to the World Bank regularly.
11.1.2 Procedure of internal monitoring
The internal monitoring can be divided into two phases, namely, preparation phase
and implementation phase. The preparation phase begins at project identification period,
through project preparation, project pre-assessment and project assessment, finally ends
at project approval period of the project cycle. The implementation phase begins at the
implementation of the resettlement and ends at the achievement of the aim of
resettlement.
1. Preparation phase of internal monitoring
The Employer and the local government shall establish the resettlement offices at
the early period of project preparation. The Employer shall establish an internal agency
for resettlement with capable personnel specialized in resettlement to ensure the
provision of complete and objective information and data, which also contributes to the
involvement of the organizations of other fields. The internal monitoring and evaluation
of the resettlement shall be arranged in the project preparation period.
Preparations of the Employer include:
——To organize the trainings on the resettlement policy of the World Bank and
relevant experiences, national resettlement policy, the design of the Resettlement Action
Plan, resettlement implementation and the monitoring and evaluation of resettlement for
the staff of the Employer and the resettlement offices;
——To invite professional agency and professionals who will assist in the design
of the Resettlement Action Plan as early as possible; to organize socioeconomic survey;
to design the Resettlement Action Plan with the help of the professional agency and
professionals;
——To establish resettlement information management system with the help of the
professional agency and professionals.
Preparations of the resettlement agency include:
——To sign the detailed resettlement implementation contract with the Employer;
144
——To establish the resettlement offices at various levels and arrange necessary
personnel for them.
——To organize resettlement staff trainings; to carry out socioeconomic survey
and the design of the Resettlement Action Plan together with the Employer and the
professional agency it invited;
——To establish the resettlement information management system.
2. Implementation phase of internal monitoring
During the implementation phase, the district resettlement office shall submit the
information on resettlement implementation of the sample households and sample
organizations drawn by the monitoring agency and up-to-date record of relevant
activities to the Project Resettlement Office to ensure the follow-up monitoring of the
resettlement. The Project Resettlement Office will carry out regular inspection on the
resettlement offices at town (street) level and village (community) level and verify the
progress of resettlement reported by them.
During the implementation phase of the internal monitoring, the Employer shall,
——In accordance with the Resettlement Action Plan, preside over the internal
monitoring of the resettlement;
——Submit a detailed internal monitoring report to the World Bank every half a
year;
——Update the statistics of the resettlement implementation in time and complete
the resettlement information management system.
11.1.3 Contents of internal monitoring
Generally, the internal monitoring shall include the followings:
Organization: The establishment and assignment of resettlement-implementing
agency and relevant organizations and their personnel assignment and capability
development;
Resettlement policy and compensation rate: The design and implementation of resettlement policy; the actual implementation of compensation rates of various losses
caused by the resettlement (permanent land acquisition, temporary land occupation,
house relocation, store relocation, the relocation of public institution and enterprise and
145
the relocation of specific facility) and specific identification of whether the rates in the
Resettlement Action Plan is implemented and the causes of any changes occurred;
Progress of relocation and resettlement: The general schedule and the yearly schedule, the progress of personnel assignment of the resettlement agency, the progress
of land acquisition and temporary occupation, the progress of adjustment, acquisition
(or transfer) and assignment of the land of resettlement area (including land for
production, residential building and public facility), the progress of house relocation, the
progress of the construction of resettlement house, the progress of the moving of
displaced persons, the progress of production development project, the progress of the
construction of public facility, the progress of the recovery, removal and reconstruction
of specific facilities, the progress of the removal and reconstruction of industrial and
mineral enterprises and public institutions, the progress of the employment-related
action and the progress of other resettlement activities. The sample form of the internal
monitoring report on the progress of land acquisition and resettlement is shown as Table
11-1;
Resettlement budget and implementation: The amount and time of payment of resettlement fund to various levels, the use and management of resettlement fund of
resettlement offices at various levels, the amount and time of payment of compensation
fund to the proprietor of affected property (house) and the proprietor (village and group)
and the user of affected land, the use and management of compensation fund of the
collective land at village level, the supervision and audit of the use of fund. The sample
form of the internal monitoring report on the progress of the use of compensation fund
is shown as Table 11-2;
Production and employment resettlement of displaced persons: The main measures for the resettlement of the displace persons (land adjustment resettlement, new
land development, enterprise and public institution, self-employment), the number of
persons, the employment resettlement of the staff of displaced enterprises, the
resettlement of vulnerable groups (household of women, household of old persons and
the disabled), the recovery of the land occupied temporarily and the impact of
resettlement;
Reconstruction of displaced houses and living resettlement: the means and areas
of the resettlement of rural displaced persons, the arrangement and allocation of the
146
residential area, the way of house reconstruction, the three accesses and one leveling of
the residential area, the payment of compensation fund, the relocation of the matching
public facilities (water supply, power supply, road and business area);
The reconstruction of the enterprises and public institutions and various specific facilities (power supply, heat supply, water supply, communication, traffic and
pipelines);
Complaint, appeal, public involvement, consultation, information publicity and
independent monitoring: The channel, procedure and responsible organization of
complaining and appealing, the main complaints and appeals and their handling, main
content and means of public involvement and consultation, the impact of public
involvement and consultation, resettlement information brochure and information
publicity, the activities and impact of independent monitoring organization;
Handling of the relevant issues stated in the inspection memorandum of the World Bank;
Existing problems and solutions.
11.1.4 Means of internal monitoring
The internal monitoring, as the from top to bottom monitoring on the
implementation of the resettlement within the resettlement system, shall establish
standard, smooth, from top to bottom resettlement information management system
among the Employer and resettlement offices at various levels and follow up the
progress of resettlement in various districts. The resettlement offices at various levels
shall report the progress of resettlement and the information about the compensation
fund and the impact of resettlement from the bottom to top, analyze and handle relevant
issues through the information management system.
The Project Resettlement Office has established a complete information
management system, which can save and manage various data and information relating
to the implementation of project comprehensively, timely and accurately.
The following means of internal monitoring may, in accordance with the
implementation status of the project, be adopted for this project:
1. Standard report forms
147
The Employer shall, in accordance with the requirements of resettlement
implementation, design uniform report forms, which show the progress of appropriation
of resettlement fund and the progress of land acquisition and resettlement. The report
forms shall be submitted at every end of month from lower level to superior level,
through which the Employer can master the progress of the project.
2. Regular and irregular communication
The resettlement offices of city, district and town level and the independent
monitoring organization shall discuss the problems occurred in the resettlement and
communicate relevant information and propose their comments on handling these
problems by a variety of means.
3. Regular coordination meeting
At every beginning of the month, the Project Resettlement Office will convene
resettlement coordination meeting and the staff of district resettlement office shall
report the progress of the implementation and existing problems, communicate the
working experience and seek for the solution of the problems.
4. Inspection
The Project Resettlement Office will carry out routine inspection and specific
inspection on the resettlement offices of lower levels and field survey, handle
resettlement problems on site and verify the progress of the resettlement and the
implementation of resettlement policy.
5. Information communication with independent monitoring organization
The Employer and the local resettlement offices shall keep in touch with the
independent monitoring organization and take their findings and comments as the basis
of internal monitoring.
6. Survey
The Employer will adopt questionnaire and door-to-door interview in the survey to
check the implementation of resettlement. Sampling survey shall be applied for
households. Some households or collective organizations will be drawn and the
questionnaires filled by them will show the payment of their compensation and moving
cost, and whether the resettlement is implemented strictly according to the Resettlement
Action Plan. And all the enterprises and the public institutions will be investigated.
148
The Project Resettlement Office will carry out the first survey after the displaced
persons get their compensation for the first time. After the first survey, the Project
Resettlement Office will take some improving measures based on the results of the
survey and the complaints of the displaced persons and follow up the implementation of
these improving measures. Questionnaire will be adopted for the irregular survey on the
labor force resettlement of the displaced persons, the land adjustment and the handling
of the complaints and it will also collect the comments and suggestions on the public
consultation and the house selection.
Table 11-1 Land acquisition and resettlement progress
Organization:________________________________ Date: ________/____/______ (Y/M/D)
Resettlement activity Unit Planned amount
Completed amount
Accumulated completed amount
Proportion(%)
Permanent land acquisition
Mu
Temporary land occupation
Mu
House relocation �
Including: Private house �
Store �
Premise of enterprise and public institution
�
Land compensation Ten
thousand yuan
Payment of house relocation fee
Ten thousand
yuan
Reconstruction of residential house
�
Reconstruction of store �
Reconstruction of premise of enterprise and public institution
�
149
Resettlement activity Unit Planned amount
Completed amount
Accumulated completed amount
Proportion(%)
Displaced persons moved to new houses
Person
Displaced persons trained Person
Provision of employment opportunity
Person
Land adjustment Mu
Filled by: Signature of Person in Charge: Seal:
Table 11-2 Progress of using the compensation fund
_____ District_____ Town(Street)_______ Village(Community) Date /____/___ (Y/ M/ D)
Affected organization Brief description
Qty (Organization)
Amount required (yuan)
Compensation acquired in the report period (yuan)
Accumulated acquired Compensation
Proportion(%)
Village collective
Village (Community)1
Household
Village collective
Village (Community)2
Household
Store
Enterprise and public institution
Public facility
Filled by: Signature of Person in Charge: Seal:
11.1.5 Internal monitoring agency and personnel assignment
The personnel of resettlement agency relating to internal monitoring are shown in
Table 11-3.
Table 11-3 Personnel of internal monitoring in resettlement agency
Resettlement agency Number of standing personnel
Number of personnel in peak period
Project Resettlement Office
2 3
District resettlement office
3 4
150
Resettlement office at town (street) level
2 4
Village committee(Community)
1 3
11.1.6 Assignments of internal monitoring agency
To investigate the affected area, establish resettlement office and train the staff. Assign the independent monitoring organizations.
Give guidance to the survey agency at the initial stage. Train the staff of resettlement office at district and town (street) level. Collect the materials required by the Resettlement Action Plan from resettlement
offices at district and town (street) level.
Check the resettlement policies of resettlement offices at district and town (street) level and keep them consistent with the Resettlement Action Plan.
Study the information collected from the displaced persons and prepare
resettlement manual.
The Project Resettlement Office shall design measures in time to solve the
problems found in the internal monitoring.
11.1.7 Reporting period of internal monitoring
The internal monitoring is a continuous process and its overall monitoring activity
shall be carried out at least once a quarter and its frequency will be increased during the
key period of the relocation of the displaced persons.
During the preparation period of the project, the internal monitoring agency will
make regular and irregular report, combining with the inspection of the World Bank.
The format of the report will be determined in accordance with the requirements of the
World Bank and different projects and stages. After the implementation begins, it is
required to make brief weekly and monthly report and detailed quarterly, half-yearly
and yearly report for major projects and make brief quarterly report and detailed half-
yearly and yearly report for minor projects. Specific report shall be made according to
the requirement of project management. After the implementation of the project, a final
report shall be made. The internal monitoring report shall be submitted to the People’s
Government at the same level, the resettlement office at superior level and the Employer
151
by the resettlement offices at various levels. And the Employer shall submit an internal
monitoring report to the World Bank every half a year.
11.2 Independent Monitoring
In accordance with the relevant requirements of the World Bank, Center for
Involuntary Resettlement Research, Wuhan University is committed to undertake the
independent monitoring of the resettlement of the World Bank Financed Taiyuan Urban
Transport Project upon the comparison of the Project Resettlement Office and it will
monitor and evaluate the resettlement and recovery activities to ensure the resettlement
is implemented in conformity to the Resettlement Action Plan.
11.2.1 Purpose of independent monitoring
In the independent monitoring and evaluation (M&E), the resettlement evaluation
shall be made by the organization independent of the governmental department. Its
purpose is to inspect the implementation of the Resettlement Action Plan from a broad
and long-term view, to monitor and evaluate whether the aims of land acquisition,
resettlement and relocation are reached, to propose comments and suggestions and to
take remedial measures and follow up their implementation and impacts to ensure the
result of the resettlement.
The independent monitoring shall follow up the land acquisition and resettlement
to monitor and evaluate the followings:
1. Whether the relevant rules and regulation of the state are observed in the
resettlement;
2. Whether relevant policies on involuntary settlement of the World Bank are
observed in the resettlement;
3. Whether the living conditions of the displaced persons is improved or recovered.
11.2.2 Independent monitoring organization and monitoring personnel
Center for Involuntary Resettlement Research, Wuhan University is an
organization with abundant experience in resettlement survey and research and
independent monitoring. The center is a comprehensive academic institution integrating
scientific research, teaching, consultancy and service, which has engaged in
152
socioeconomic survey and resettlement for a long time and accumulated rich
experience. In the recent 10 years, it has undertaken the resettlement consultancy or
independent monitoring of 20 key projects.
To carry out the independent monitoring of this project successfully, the center has
organized a project team for this project. The following factors have been taken into
consideration for the selection of the team members.
(1)The independent monitoring personnel shall have the experience of similar work
and abundant experience in socioeconomic survey, understand the involuntary
resettlement policies of the World Bank, master relevant rules and laws of the state and
local government on the resettlement.
(2)They shall be industrious and capable of carrying out social survey and research
independently and have communication ability.
(3)Some female staff shall be assigned according to a certain proportion.
In accordance with the above, 9 persons are selected and the name list of the
members of the independent monitoring organization is shown in Table 11-4.
Table 11-4 Personnel of the Independent Monitoring Organization of the World Bank
Financed Taiyuan Urban Transport Project
Name Se
xAge Similar Experience Assignments in this Project
Zhong
Shuiying M 40
Took charge of 9
similar projects.
To organize and be responsible for
independent monitoring.
Cheng Dening M 37 Took charge of 7
similar projects.
To investigate and research, make
monitoring report and translate the
report.
Wei Shan M 34 Took charge of 7
similar projects.
To investigate, research and process
the information acquired.
Wen Hui F 34 Took charge of 4
similar projects.
To investigate, research and make
monitoring report.
Yu Jiang M 29 Took charge of 4
similar projects.
To investigate, research and make
monitoring report.
He Zhiyang M 25 Took charge of 4
similar projects.
To take part in the survey and
research.
Li Kui M 23 Took charge of 4
similar projects.
To take part in the survey and
research.
153
Lou Feipeng M 23 Took charge of 4
similar projects.
To take part in the survey and
research.
Yan Honghong F 25 Took charge of 4
similar projects.
To take part in the survey and
research.
11.2.3 Assignments of the independent monitoring organization
The independent monitoring organization shall undertake the followings:
Before the resettlement, the living standard baseline survey shall be carried out to master the basic living and production conditions of the displaced persons.
In the process of the resettlement, the independent monitoring organization shall
follow up and monitor the implementation of the resettlement, collect the comments and
complaints of the displaced persons and report them to the Project Resettlement Office
and local resettlement office timely. And the independent monitoring organization shall
submit monitoring report to the Project Resettlement Office and the World Bank.
The independent monitoring organization shall investigate the living and production conditions of the displaced persons all the time and evaluate the resettlement
activities and relevant measures.
Upon survey, research and discussion with the displaced persons, the independent
monitoring organization shall propose constructive comments to the Project
Resettlement Office and local resettlement office to ensure the smooth implementation
of the resettlement and fast recovery of the living and production conditions of the
displaced persons.
11.2.4 Means and procedures of independent monitoring
The independent monitoring organization will adopt the following means to carry
out the monitoring of resettlement.
(1)On the basis of resettlement survey, the independent monitoring organization
will set up a database for the displaced persons and carry out door-to-door interview
constantly. The independent monitoring organization will fully make use of the
information acquired through socioeconomic survey and the resettlement information
management system of the Project Resettlement Office, carry out dynamic management
on the basic conditions of the displaced households, get to know the relevant
154
information of the displaced persons all the time. According to the information shown in
the database, the monitoring personnel will visit the displaced persons, get to know the
progress of the resettlement, collect their complaints and suggestions, and inform them
relevant policies of the state, relevant requirements of the World Bank and the
information on the construction of the project.
After the acquisition of the name list of the displaced persons and relevant
information from basic institution, the independent monitoring organization shall carry
out door-to-door interview independently, not accompanied by the staff of the local
resettlement office or local administrative personnel. The visiting persons shall be
relatively stable, which means a monitoring member shall try to visit the same affected
area from time to time, which is beneficial for the establishment of the trust between the
monitoring member and the displaced persons and the efficiency of the visits.
(2)The independent monitoring organization shall convene meetings irregularly in
the area with a large population to collect the comments on the importation issues
relating to the project of the displaced persons. The meeting may be formal or informal.
And the staff of the local resettlement office may be or may not be invited to the
meeting, which depends on the actual situation.
(3)Field survey. The staff of the independent monitoring organization shall visit the
resettlement area regularly and irregularly and observe the resettlement on site.
(4)Survey on individual case. The monitoring personnel shall put emphasis on the
special case occurred in the resettlement, analyze the causes of the problems, work out
solutions and propose suggestions.
(5)Questionnaire. The monitoring staff shall carry out sampling survey on the
recovery of the living and production conditions of the displaced persons and the
comments on the resettlement and analyze the result in time to solve the existing
problems. And the resettlement work of the next year may be carried out with reference
to the results of the survey and the solutions of the problems occurred.
11.2.5 Contents of independent monitoring
(1)The settlement of the affected enterprises and public institutions
Many enterprises and public institutions are involved in the land acquisition and
resettlement of the World Bank Financed Taiyuan Urban Transport Project. Generally,
155
these affected organizations are capable of negotiating with the resettlement office and
protecting their own benefits. The public institutions may build or rent new office
building with the compensation and complete the resettlement in a short period. The
enterprises whose affected parts are not important to the production shall adjust the
production layout and the production and operation may continue. The project may have
great influence on a few enterprises, but most of which are with large energy
consumption and severe pollution and the municipal government of Taiyuan City has
planned to remove these enterprises to other areas. They may carry out land exchange in
the project and move out of the downtown, seeking for new development opportunity.
The independent monitoring organization shall follow up the resettlement of the
enterprises and public institutions through phone call and the study on individual case.
The followings will be most concerned about:
Whether the time of land acquisition and the resettlement is arranged reasonably; Whether the losses of the affected enterprises are compensated; Whether the staff of the enterprises are resettled properly; Whether the production of the enterprises is resumed in time;
Whether the affected enterprise transfer their loss to their staff. (2)The resettlement of displaced persons
Many urban and rural residential houses are involved in this project. The
resettlement of displaced persons is the emphasis of the independent monitoring. As to
these displaced persons, the followings are the main concerns of the independent
monitoring organization.
Whether the compensation rates of houses and other attachments to the ground are determined in accordance with the replacement cost principle;
Whether the compensation is paid with full amount and in time; Whether the land of new residential houses is determined through consultation; Whether the time of relocation is arranged reasonably; Whether the transition subsidy and moving cost are paid;
Whether the physical losses are fully compensated; Whether the infrastructure (including water, power and heat supply and roads) of
the new resettlement area is completed and who is responsible for it;
156
Whether it is convenient to go to hospital and school from the new resettlement
area.
(3)The production resettlement of the displaced persons
In accordance with the features and the operation of the affected land, the
independent monitoring on the land acquisition and production resettlement shall be
focused on the followings:
Whether the compensation rates of various lands are determined in accordance with relevant laws of the state;
Whether the transfer procedure of land compensation fund can ensure the affected village and team acquire their deserved amount;
Whether the amount of land requisitioned, compensation rate, compensation
amount are publicized in the village and by which means they are publicized;
If the land compensation shall be paid to individuals directly, how the range of payment is determined and whether the readjustment of land is required;
If the readjustment of land is required, how the plan of readjustment is determined and whether it is determined upon the discussion and consultation with the
displaced persons;
Whether a definite and feasible plan ismade for the collective use of land
compensation;
Whether the plan of the use of land compensation is designed after the collection of the comments of related villagers and how the use plan is finally determined;
How the benefit brought by land compensation is distributed and how the actual
economic benefit of the displaced persons is guaranteed;
The implementation and impact of land reclamation plan. (4)Resettlement offices
Capable, specialized and efficient resettlement offices may assure the success of
resettlement. The monitoring on the operation of resettlement offices is an important
part of independent monitoring. The means of monitoring are mainly visits to the
resettlement offices and the inspection on the working data and record. The main
content of monitoring on resettlement offices includes:
Whether the personnel structure of the resettlement offices at various levels meets the requirements of the resettlement;
157
Whether necessary working conditions are provided for the resettlement offices at various levels;
Whether the quality of resettlement personnel meets the requirements of the
resettlement;
The resettlement staff training; The internal data and information management of the resettlement offices.
(5)The resettlement of vulnerable groups
The vulnerable groups shall be given special attention not only by the resettlement
offices but also by the independent monitoring organization. The independent
monitoring organization shall follow up and monitor the resettlement of vulnerable
groups by means of door-to-door interview, questionnaire, individual case analysis and
the main indicators of monitoring include:
Which preferential policies are enjoyed by vulnerable groups in the resettlement; Whether the affected poor household in the urban area can afford a new house; Whether any assistance has been offered to the affected poor household in the
rural area;
The measures for the production resettlement of affected poor households in rural
area;
Whether special requirements of affected women have been fully considered in the design of resettlement measures;
Whether vulnerable groups, especially women, can acquire employment
opportunity relating to the project and how many vulnerable persons are employed in
the construction of the project;
Whether there is a female staff member in each resettlement office to deal with the affairs of women.
(6)The living standard baseline survey of displaced persons
Before the formal commencement of the resettlement, the independent monitoring
organization shall collect the basic information for the resettlement of the World Bank
Financed Taiyuan Urban Transport Project upon sampling survey. Structured
questionnaires are adopted for the sampling survey. Cluster sampling shall be carried
out, taking all the affected households involved in the socioeconomic survey at the
preparation phase of the project as the sample bank. The sampling proportion of the
158
households affected by land acquisition is preliminarily determined to be 10%, and that
of the households affected by relocation is 10%, and that of the households affected by
land acquisition and relocation is 15%.
The living standard baseline survey of the affected households covers: family
structure, production conditions, gross floor area of the houses, annual income of the
household, employment structure, annual expenditure of the household, traffic
conditions, water supply, power supply and heat supply conditions, living environment,
subjective appraisal of production and living conditions.
(7)The impact of resettlement
After the implementation of the resettlement, the independent monitoring
organization will follow up and monitor the impact of the resettlement continuously.
The independent monitoring organization will investigate the affected households
half a year after the resettlement. The follow-up survey is similar to the living standard
baseline survey of the affected households, adopting sampling survey by means of
structured questionnaires, to show the impact of resettlement on the production and
living of the persons investigated. And the impact of resettlement shall be evaluated on
the basis of the follow-up survey.
The principle of the selection of samples of the follow-up survey is the same as
that of living standard baseline survey. The independent monitoring organization shall
try to investigate the objects of living standard baseline survey. After the living standard
baseline survey, the independent monitoring personnel shall establish the database of
the samples of the survey, which will be the basis of the follow-up survey. As to the
survey objects that it is hard to investigate again due to various reasons, they shall be
replaced by similar affected households in the same community after referring to the
information bank established upon the earlier socioeconomic survey.
The contents of the follow-up survey shall be consistent with those of living
standard baseline survey, so as to carry out comparison analysis of the production and
living conditions of the affected households before and after the resettlement.
Meanwhile, the subjective comments on the resettlement of the displaced persons shall
be collected and they will be referred to in the evaluation of the impact of the
resettlement.
159
11.2.6 Reporting system of independent monitoring
The independent monitoring organization shall make independent monitoring
report in written form based on the information acquired through observation and
survey. The two purposes of reporting: one is to report the progress of the resettlement
and existing problems objectively to the World Bank and the Employer and the other is
to evaluate the social and economic impacts of the resettlement, propose constructive
comments and suggestions to improve and perfect the resettlement.
The independent monitoring organization shall submit reports to the World Bank
and the Employer and the periods of reporting are confirmed as follows:
Submit an interim monitoring report concerning the resettlement of the first half of the year to the World Bank and the Employer before July 31 of every year;
Submit a yearly monitoring report to the World Bank and the Employer before Jan. 31 of every year;
Submit a comprehensive evaluation report half a year after the completion of the resettlement.
A routine monitoring report shall at least include the followings: 1. monitoring
objects of the report; 2. the progress of the resettlement; 3. main findings of the
independent monitoring organization; 4. main existing problems; 5. basic appraisal,
comments and suggestions of independent monitoring organization.
The independent monitoring organization shall submit the report both in English
and in Chinese to the Project Office and the World Bank. Before submitting, the
independent monitoring organization shall inform relevant personnel of the resettlement
office of the contents of the report and collect their comments and they shall
communicate with each other on the contents and the form of the report.
160
12�Matrix of Entitlement
Type
Displacedpersonsandorganization
s
Resettlement and Recovery Policies Compensation Rate
VillageCommittee
The land requisitioned shall be compensated at theuniform land priceof thearea.As to the acquisition of collective cultivated land, young crops compensation(1000yuan per mu) and the
compensation for attachments to theground shall bepaid to thecontractor.If the village collective replaces the requisitioned land with another pieceof cultivated land for thecontractor, land
compensation shall bepaid to thevillagecollective.If the village collective cannot replace the requisitioned land with another piece of cultivated land for the contractor,
part of the land compensation shall bepaid to thecontractor and theproportion shall benegotiated and agreed by thevillagecollectiveand thecontractor.
As to the land acquisition of other collective land, the use of land compensation shall be negotiated among themembers of thevillagecollective.
The collective economic organization may spend the land compensation on the public enterprise of the collective.
Thecompensation for landacquisition will beprovided asper
theunified district land price,50,000 Yuan/mu.Land
acquisitionand
Landcontractors
The affected contractors shall obtain the compensation for young crops and various attachments to the ground on the land requisitioned.
If the village collective cannot replace the requisitioned land with another pieceof cultivated land for thecontractor,70% of the land compensation(34300yuan per mu) shall bepaid to thecontractor.
If the requisitioned land is replaced with another piece of cultivated land, the contractor shall acquire the newly assigned land.
Landrequisition
User ofstate-owned
land
As for state-owned land used for construction and state-owned agricultural land to be requisitioned for theproject,thecompensation will beprovided according to national policies;
As for the acquisition of state-owned land used for construction and with buildings, its compensation will beincluded in thecompensation priceof thebuilding, and land compensation will not be listed separately;
For the acquisition of collectively-owned land used for construction obtained with compensation, if there is nobuilding on the land, thecompensation will beprovided at 240 Yuan/� .
For the acquisition of state-owned agricultural land, thecompensation will beprovided at thecompensation priceofcollectively-owned land.
240 Yuan/� for state-owned landused for construction obtained with
compensation and withoutbuildings;
50,000 Yuan/mu for state-ownedagricultural land and wood land
Relocationof
residentialhouses inurban area
Displacedurban
residents
In the relocation scopeof theproject, theperson suffering from relocation may freely select the resettlement modefrom monetary compensation and exchange of property right. If monetary compensation isselected, no housewill bearranged.
Determination of useproperty and area of thehouse to be relocated: privateproperty will besubject to thecertificatefor housing ownership issued by relevant administration; public property and institution property will besubject to thepropertiesand areas indicated in thecertif icates for the lease of house.
Determination of non-domestic house: refer to thehousepurposestated in thecertificatefor houseownership. If thehousepurpose isnot stated in the certif icate for houseownership, besubject to therecord in property right archives ortheplanning permits of urban planning administration and local administration.
Calculation formula of monetary compensation for private dwelling house Amount of monetary compensation = Property building area of house to be relocated ×Unit price of market evaluation
(Yuan/� )
Frame construction: 1800Yuan/� Brick-concrete: 1600
Yuan/� Brick-wood: 1300 Yuan/�
Basement: 300 Yuan/�Moving subsidy: 10 Yuan/�
Transition subsidy: 10Yuan/� /month and 2 0
Yuan/� /month after transitionperiod excel 24 months
161
The high-risebuilding subject to theexchange of property right isof frameconstruction, and the multi-storiedbuilding is of brick-concretestructure. The types of resettlement houses include50� , 60� , 70� , 80� , 90� and 100� .
If the exchange of property right is carried out for therelocation of privatedwelling house, provided that thebuilding area of resettlement houseequals thebuilding area of property right of relocated house, thepriceof structuraldifferencewill not besettled if thestructuresare thesame, and thepricedifferencemay besettled according toindividual evaluation price if thestructuresaredifferent.
The preference of 10% will be provided for the resettlement house on the basis of property building area of the house to be relocated, and the relocateepays expensesat 1800 Yuan/� for high-risebuilding and 1500 Yuan/� for multi-storied building.
If the relocatee require increasing resettlement area, thearea increased less than 10� (including 10� ) will be settled at 2000 Yuan/� ; if the area increased is more than 10� and less than 20� (including 20� ), the construction cost will be settled at 2300 Yuan/� ; the extra part more than 20� will be settled as per the price of commercial housing at 3200 Yuan/� .
That is, building area of the house to be resettled = property building area of the house to be relocated ×110%.For the relocation of public-property and institutional-property dwelling houses, in principle, the property right will
be bought out. That is, for the part of property building area of the original house, after the leaseholder buys the propertyright of the house at 30% of market evaluation price, the exchange of property right will be carried out. For the otherpart, the method for the expense settlement is the same as private dwelling house.
For the relocation of non-domestic house, the resettlement will be carried out by means of one relocation and onereturn. The exchange of property right may be carried out for the right owner. The settlement between the prices ofrelocated house and resettlement house should be subject to the individual evaluation price. The part exceeding theresettlement area will be settled at the price of commercial housing, 6000 Yuan/� .
Moving expenses for dwelling house shall be paid to the relocatee according to the property building area of the house to be relocated;
If the house to be relocated accepts monetary compensation, moving subsidy will be paid once; if the house to berelocated accepts independent transition, moving subsidy will be paid twice.
If the dwelling house to be relocated accepts exchange of property right, during the transition period, the transitionsubsidy will be paid at 10 Yuan/� /month according to the property building area of the house to be relocated;
LeaseholdersThe leaseholder shall get moving cost, transition subsidy and compensation for affected facilities. The leaseholder shall have the priority to lease the premise under the same conditions.
Relocationof
collectivelands and
houses
Displacedrural
residents
For the relocation household on collectively-owned land, both resettlement modes of monetary resettlement andexchange of property right are provided for free selection.
Amount of monetary compensation = Property building area of house to be relocated ×Unit price of market evaluation (Yuan/� )
For the relocation of the houses in these villages, except monetary resettlement freely selected by the villages,unified planning and the construction of resettlement houses will be carried out.
If the building area of resettlement house equals the building area of licensed house to be relocated, the price of difference will not be settled; the part exceeding the original building area will be settled at the market price.
Vulnerablegroups
Vulnerablefamilies
According to the survey, if the family only has one dwelling house, the life is poor indeed, and the public has no objection after issuing public announcement, the dwelling house with building area not less than 50� will be provided. If the building area of resettlement house is less than 50� , the price of structure difference and the expenses for exceeding resettlement area will not be settled, and the charging rate of the expenses for exceeding 50� is the same as private dwelling house.
162
The resettlement office sets up the funds of RMB 2 million Yuan for helping vulnerable groups according to specific needsduring the resettlement course
For area, typeand location of resettlement house, the family of vulnerablegroup has priority in selection.Resettlement organizations at all levels are responsible for organization manpower to assist in the moving of the
families of vulnerablegroups.
Relocationof
enterprisesand publicinstitutions
Enterprisesand publicinstitutions
For the compensation and resettlement of houses and shops of enterprises and institutions to be relocated, multiple measureswill beprovided for freeselection. Resettlement modes include: monetary compensation and rehabilitationnearby; using compensation funds for purchasing land freely and overall moving; thegovernment assists in providingland for building, and theenterprise recovers itself independently.
The monetary compensation rate for the relocated houses of enterprisesand institutionsas well asshopsshall beevaluated and put forward by thequalified real estateappraisal company, and then shall bedetermined by theresettlement officeafter negotiating with affected enterprisesand institutions.
The salary loss and business loss due to the relocation of the enterprise, the public institution and the store shall be determined upon theconsultation between the resettlement officeand theaffected organization. Thecompensation forsalary shall, in accordancewith thename list of thestaff (fully employed staff and workerswho pay thepremium oflabor insurance) of thedisplaced organization provided by theLabor and Social Security AdministrativeDepartment, bedetermined. Thecompensation for business lossshall, in accordancewith theaveragemonthly amount of tax paid of theprevious year, bedetermined. As to the fully stop of theproduction, thecompensation period is6 months; as to thepartial stop of theproduction, thecompensation period is3 months.
Any change of compensation rate due to house decoration shall be confirmed by the real estate assessment company by theprincipleof market.
If the house is registered for residential use on the property right certificate, but has been used for businesspurpose,it shall becompensated as residential houseand thecompensation for business loss of 3 months shall, in accordancewithstateof operation, term of operation and the tax payment records, bemade.
Evaluation priceof non-domesticofficeoccupancy: 1100 Yuan/�
for frameconstruction, 900Yuan/� for brick-concrete
structure, 800 Yuan/� for brick-wood structure, and 600 Yuan/�
for earth-wood structure.Evaluation priceof businessoccupancy: 2680 Yuan/� for framed storied building, 2380
Yuan/� for brick-concretestoriedbuilding, 2030 Yuan/� for single-story brick-concretebuilding, 1930Yuan/� for brick-wood structure,and 1700 Yuan/� for earth-wood
structure.Storage occupancy for productionand business: 1100 Yuan/� for frameconstruction, 900 Yuan/�
for brick-concretestrcutre, and 800Yuan/� for brick-wood structure.
Relocationof shop
Propertyownersandleaseholders
If the house is registered for residential use on the property right certificate, but has been used for businesspurpose,it shall becompensated as residential houseand thecompensation for business loss of 3 months shall, in accordancewiththe tax payment certif icate, bemade.
thenew shop fronts in the resettlement plotswill bechoosen first by thosewhoseshop had been dismantled.As to the newly built stores and houses for business purpose of various enterprises and public institutions closely
behind thesites of thedisplaced stores, the leaseholders shall have thepriority to lease thehouses under thesameconditions.
The moving cost, transition subsidy, and the compensation for decoration confirmed upon assessment of the stores shall begiven to the leaseholder. Thecompensation for structuresshall bepaid to theproperty owner.
As to the business loss of enterprises and public institutions due to the relocation of their stores, the compensation shall bedetermined upon theconsultation between the resettlement officeand theaffected enterprises and publicinstitutions.
illegalbuildings
Buildingusers
If buildings are used as residential houses and relocation households have no other places for living, the relocation compensation shall bepaid according to that of buildingswith license.
For the buildings other than thepreviousclause, thecompensation will beprovided asper construction costs, and theconcretestandards are: 600 Yuan/� for brick-concretestructure, 400 Yuan/2 for brick-concretestructure, 400 Yuan/�
163
for brick-wood structureand 200 Yuan/� for simple structure.
Attachmentto the
ground
Propertyowner
Compensation will beprovided asper replacement price: RMB 1000 Yuan for each cavehouse, 50 Yuan/� for brick wall, and 30 Yuan/� for adobe brick wall.
W.C.: RMB 100 Yuan for each brick-wood adobebrick W.C. with cover, RMB 300 Yuan for each simple W.C.without cover, and RMB 200 Yuan for other kind of W.C.
RMB 500 Yuan for each gate tower, RMB 300 Yuan for each screen wall, and 15 Yuan/� for terrace. 1000 Yuan/m for well. 30 Yuan/� for greenhouse, RMB 30 Yuan for each timber tree with diameter of 10cm, by
parity of reasoning; RMB 20 Yuan for each young tree, RMB 200 Yuan for fruit tree that can bear fruit, and RMB 60Yuan for fruit tree that cannot bear fruit.
RMB 150 Yuan for each telephone, RMB 600 Yuan for each wideband, and RMB 500 Yuan for each closed circuit.Land
acquisitionand
relocationof relatedprojects
Displacedpersons
Thecompensation shall bemade in accordancewith the resettlement policy and compensation rateof North Mid RingRoad and Taihang Road.
164
Attached Table 1 Quantity of private houses affected by relocation for Taiyuan Urban TransportProject
House (� ) Population
District OfficeCommunity(village)
Steelandconcrete
Brick andconcrete
Brickandwood
Woodand earth
Simple Total
Numberofhouseholds
Number ofpersons
I. Taihang Road
Xiaodian Beiying LongbaoVillage
0 9283.2 376 0 289 9948.2 26 126
Daochanggou 0 2844.12 510.81 0 827 4181.93 32 173Baergou 0 360.95 401.9 0 172.6 935.45 4 20Xiaozaogou 0 3098.81 140.01 0 825.12 4063.94 31 139
Xianghualing
Yangjiayu
Sub-total 15587.08 1428.72 0 2113.72
9181.32 67 332
Dianpo 0 5745.7 74 3544 365.5 9729.2 11 52
Haojiagou 0 23672 41.25 0 22.0723735.32
55 261
Wangjiafeng 97.44 9185.22 1438.14 288.79 5311062.59
79 303Yingze
Haozhuang
Sub-total 97.44 38602.92 1553.39 3832.79 440.57 44527.11
145 616
Total of Tanghang Road 97.44 54190 2982.11 3832.79 2554.29
63656.63
238 1074
II. North Mid Ring RoadXiuliu 1105.04 0 0 0 1105.04 29 95
Xiaodongliu 24484.22 0 0 024484.22
75 379
Jiancaoping
Huifeng
Sub-total 25589.26 0 0 025589.26
104 474
165
Gucheng Senyuannan 13141 0 0 924 14065 16 72
Total 38730.26 0 0 924 39654.26 120 546
Dunhuafang
Jinjixi 8956.2817325.88
04331.47
30613.63
586 1817
YagjiayuXiangtangVillage
15717.6 3174.16 0 793.54 19685.3 259 949Xinghualing
Total 24673.88 20500.04
0 5125.01
50298.93
845 2766
Total of North Mid Ring Road 63404.14 20500.04
0 6049.01
89953.19
965 3312
III. Subproject of public transport 763.2 411.8 2160 3335 5 21
IV. Total 97.44 118357.3 23893.95
3832.79 10763.3
154784.8
1208 4407
166
Attached Table 2 Relocated households and population living in dormitories of enterprises and institutions
Organization Name District Office Community
Number of households
Number of persons
Total of North Mid Ring Road
727 2480
Municipal Forest Science Research Institute (dormitory)
Jiancaoping
Gucheng Senyuann
an 42 139
Raw Material Department of Taiyuan Steel Plant (dormitory)
Jiancaoping
Gucheng Senyuann
an 140 462
Concrete Branch of Taiyuan Lionhead Group
Jiancaoping
Huifeng Huifeng 25 83
Shanxi Fodder Supervision Institute (dormitory)
Xinghualing
Julun Xishengli
Taiyuan Locomotive Works
Xinghualing
Julun Jiche 400 1400
Kuangji Dormitory Xinghuali
ng Dunhuafa
ng Jinjixi 80 264
Total of Taihang Road 258 865
Dongshan Coal Mine (dormitory)
Xinghualing
Xinjie Taihang
Road 20 66
Dadongguan Building Materials Main Plant (dormitory)
Xinghualing
Xinjie Xincun 4 13
Shanxi Machine Manufacturing Co., Ltd. (dormitory)
Xinghualing
Xinjie Xincun 21 69
Shanxi Knitting Mill (dormitory)
Xinghualing
Xinjie Xincun 4 13
Tumor Hospital (dormitory)
Xinghualing
Xinjie Xincun 14 46
Fifth Company of Shanxi Construction Corporation (dormitory)
Xinghualing
Xinjie Xincun 3 11
167
Taiyuan Pressing Plant (dormitory)
Xinghualing
Xinjie Xincun 10 35
Taiyuan Forest Center (dormitory)
Xinghualing
Xinjie Xincun 11 36
Taoyuan No.1 Wool Spinning Plant (dormitory)
Xinghualing
Xinjie Xincun 72 238
Taiyuan Leather Plant (dormitory)
Xinghualing
Xinjie Xincun 65 215
Frozen Food Main Plant of Taiyuan Aquatic Product Company (dormitory)
Xinghualing
Xinjie Xincun 12 40
Taiyuan Transport Company (dormitory)
Xinghualing
Xinjie Xincun 22 73
Taiyuan Rolling Mill (dormitory)
Xinghualing
Xinjie Xincun 9 30
Xincun Primary School (dormitory)
Xinghualing
Xinjie Xincun 3 14
Taiyuan Hoist Plant (dormitory)
Yingze District
Haozhuang
Haozhuang
28 98
Total 985 3345
168
Attached Table 3 Area and structures of houses of enterprises and institutions to be relocated forTaiyuan Urban Transport Project
House� )
No. District OfficeCommunity
OrganizationSteelandconcrete
Brick andconcrete
Brick andwood
Simple
Total
1Jiancaopin
gGuchen
gSenyuanna
nBeichen DevelopmentCompany
0 700 84 720 1504
2Jiancaopin
gGuchen
gSenyuanna
nShanxi Chemical Plant 0 4712 1258 2258 8228
3Jiancaopin
gGuchen
gSenyuanna
nBeijianhe AdministrativeStation
0 298 0 0 298
4Jiancaopin
gGuchen
gSenyuanna
nBolang Shirt Plant 0 4144 0 168 4312
5Jiancaopin
gGuchen
gSenyuanna
nLinzhou Construction No.9Company
0 3152 0 3800 6952
6Jiancaopin
gGuchen
gSenyuanna
nTaiyuan Forest ScientificResearch Institute
0 5124 0 0 5124
7Jiancaopin
gGuchen
gSenyuanna
n
Taiyuan Irons& Steel (Group)Company Ltd. (Main PlantSite)
0 5874 0 0 5874
8Jiancaopin
gGuchen
gSenyuanna
nRaw Material Section ofTaiyuan Iron & Steel
0 13196 0 24 13220
9Jiancaopin
gGuchen
gSenyuanna
nTaiyuan Forest Center 0 4532 0 3056 7588
10Jiancaopin
gGuchen
gSenyuanna
nTaiyuan Botong CultureandEducation Training School
0 100 0 0 100
11Jiancaopin
gHuifeng Huifeng Dashun Industry Co., Ltd. 0 300 0 0 300
169
House� )
No. District OfficeCommunity
OrganizationSteelandconcrete
Brick andconcrete
Brick andwood
Simple
Total
12Jiancaopin
gHuifeng Huifeng
Galiaogou Long’ao PowerAdministrative Station
0 367.2 0 0 367.2
13Jiancaopin
gHuifeng Huifeng Huifeng Community 0 1345 0 0 1345
14Jiancaopin
gHuifeng Huifeng
Sanwei Steel StructuralEngineering Co., Ltd.
278.75 0 0 0 278.75
15Jiancaopin
gHuifeng Huifeng Taiyuan Fruit Tree Center 0 240 667.3 0 907.3
16Jiancaopin
gHuifeng Huifeng
Concrete Branch of TaiyuanLionhead Group
0 2929.44 0 0 2929.44
17Jiancaopin
gHuifeng Huifeng
Taiyuan Single-son LubrcatingOil Processing Plant
0 291 0 0 291
18Jiancaopin
gHuifeng Huifeng
Taiyuan Irrigation EquipmentSecond Plant
144 167 20 40 371
19Jiancaopin
gHuifeng Huifeng Galaxy Aluminum Plant 0 12 0 133 145
20Jiancaopin
gHuifeng
XiliuVillage
Dazhong Farm 0 6239 0 0 6239
21Jiancaopin
gHuifeng
XiliuVillage
Penghong Real EstateCompany
0 2666 0 0 2666
22Jiancaopin
gHuifeng
XiliuVillage
Shanxi Poultry Frozen SemenBreeding Center
0 84 0 0 84
23Jiancaopin
gHuifeng
XiliuVillage
Shanxi Yuanli ScientificDevelopment Co., Ltd.
0 1306 0 0 1306
24Jiancaopin
gHuifeng
XiliuVillage
Shuangqin Honeycomb BriquetPlant
0 0 60 36 96
170
House� )
No. District OfficeCommunity
OrganizationSteelandconcrete
Brick andconcrete
Brick andwood
Simple
Total
25Jiancaopin
gHuifeng
XiliuVillage
Taiyuan Fengquan IrrigationEquipment Plant
0 1200 0 0 1200
26Jiancaopin
gHuifeng
XiliuVillage
Taiyuan Jiancaoping Fruit TreeCenter
0 870 0 0 870
27Jiancaopin
gHuifeng
XiliuVillage
Taiyuan Air Tube Plant 0 1326.5 0 328 1654.5
28Jiancaopin
gHuifeng
XiliuVillage
Xiliu Villager Committee 0 1610 0 0 1610
29Jiancaopin
gHuifeng
Xiaodongliu
Xiaodongliu VillagerCommittee
0 2284 0 0 2284
Total of Jiancaoping(29 enterprises and institutions) 422.75 65069.14 2089.3 10563 78144.19
1Wanbolin Wanboli
nAnguang
Anguang Subzone PropertyCompany
0 65.75 0 0 65.75
2Wanbolin Wanboli
nAnguang
Haodong LogisticsCo., Ltd. 0 0 0 0 0
3Wanbolin Wanboli
nAnguang Shanxi Jixin Friendship
Subzone0 1490 0 0 1490
4Wanbolin Wanboli
nAnguang Shanxi Chengruida Pylon
Manufacturing Co., Ltd.0 25 467.6 0 492.6
5Wanbolin Wanboli
nAnguang Shanxi Guangjuye Industry
Co., Ltd.0 492 0 492
6Wanbolin Wanboli
nAnguang Shanxi Defense Industry Motor
Transport Company0 20.25 720.25 171 911.5
7Wanbolin Wanboli
nAnguang Wansha Real Estate
Development Company0 270 0 0 270
171
House� )
No. District OfficeCommunity
OrganizationSteelandconcrete
Brick andconcrete
Brick andwood
Simple
Total
8Wanbolin Wanboli
nJinjixi
Dongshe Wasted and OldMaterialsmarket
0 40 0 0 40
9Wanbolin Wanboli
nJinjixi Jinxi Machinery Manufacturing
Plant0 467 0 0 467
10Wanbolin Wanboli
nJinjixi
Jinxi Oil Drilling Tool Plant 0 4547 0 0 4547
11Wanbolin Wanboli
nJinjixi Jinxi Rubber and Plastic
Manufacturing Plant0 503 0 0 503
12Wanbolin Wanboli
nJinjixi Jinxi Prefabricated Structure
Plant0 1272 0 16 1288
13Wanbolin Wanboli
nJinjixi
Taiyuan Fruit Tree Center 0 0 483.2 12 495.2
14Wanbolin Wanboli
nJinjixi Taiyuan Jinbao New-type
Building MaterialsCo., Ltd.0 719 0 0 719
15Wanbolin Wanboli
nJinjixi Taiyuan Maoxinsheng Material
Trade Center0 160 0 0 160
16Wanbolin Wanboli
nJinjixi Taiyuan Ruigang Installation
Engineering Co., Ltd.0 2520 0 0 2520
17Wanbolin Wanboli
nJinjixi Taiyuan Wanbolin Fruit Tree
Center0 930 0 0 930
18Wanbolin Wanboli
nJinjixi Taiyuan Wanbolin Xinghuaxi
Street Primary School0 0 0 0 0
19Wanbolin Wanboli
nJinjixi Taiyuan Xinhua Machinery
Plant2511 4577 1620 880 9588
20Wanbolin Wanboli
nJinjixi Dormitory of Wanbolin Fruit
Tree Plant0 250 0 0 250
172
House� )
No. District OfficeCommunity
OrganizationSteelandconcrete
Brick andconcrete
Brick andwood
Simple
Total
Total of Wanbolin (20 enterprises and institutions) 2511 18348 3291.05 1079 25229.05
1Xinghualin
gDunhuaf
angWohushan Shanxi Jin’an Chemical Plant 0 8858 3806 220 12884
2Xinghualin
gJulun Xishengli
Taiyuan Kuangji Machine(Group) Co., Ltd.
0 12948 826.4 892 14666.4
3Xinghualin
gJulun Xishengli
Taiyuan Iron and Steel Plant(Single Dormitory)
0 3966 0 0 3966
4Xinghualin
gJulun
Shangbeiguan
Shanxi Luweibao TaigangFireproof Materials Co., Ltd.
0 13649 0 48 13697
5Xinghualin
gJulun
Shangbeiguan
Taiyuan Rolling Stock Plant 0 20504 0 758 21262
6Xinghualin
gJulun
Shangbeiguan
Xinghualing Environment andSanitation Group
0 3037 0 0 3037
Total of Xinghualing (6 enterprises and institutions) 0 62962 4632.4 1918 69512.4
Total of North Mid Ring (55 enterprises and institutions) 2933.8 146379.1 10012.81356
0172885.7
1Xinghualin
gDadongguan
BailongGarden
Bailong Garden ChuangxingDecoration Engineering Company
540 0 0 0 540
2Xinghualin
gDadongguan
Honggou Dongshan Hear Resource Plant 196 96 0 0 292
3Xinghualin
gDadongguan
Wulongkou Yada Enterprise 1176 246.86 0 0 1423
4Xinghualin
gDadongguan
Xinnan Shanxi People Defense 838 858 224 0 0 1082
5Xinghualin
gXinjie
TaihangRoad
490 1040.67 0 0 0 1041
173
House� )
No. District OfficeCommunity
OrganizationSteelandconcrete
Brick andconcrete
Brick andwood
Simple
Total
6Xinghualin
gXinjie Taihang
RoadDongshan Coal Mine(dormitory)
3026.85 507.48 0 0 3534
7Xinghualin
g
XinjieXincun
Dadongguan BuildingMaterialsMain Plant(dormitory)
0 97.68 0 0 97.68
8Xinghualin
gXinjie Xincun Shanxi Machine Manufacturing
Co., Ltd. (dormitory)0 739 0 10 749
9Xinghualin
gXinjie Xincun Shanxi Knitting Mill (Huangpi)
(dormitory)0 151.05 0 0 151.1
10Xinghualin
gXinjie Xincun
Tumor Hospital (dormitory) 0 495.11 0 8 503.1
11Xinghualin
g
Xinjie Xincun Fifth Company of ShanxiConstruction Corporation(dormitory)
0 99.16 0 0 99.16
12Xinghualin
gXinjie Xincun Taiyuan Pressing Plant
(dormitory)0 342.05 0 10.25 352.3
13Xinghualin
gXinjie Xincun Taiyuan Forest Center
(dormitory)0 371.26 0 12.2 383.5
14Xinghualin
gXinjie Xincun Taiyuan No.1 Wool Spinning
Plant (dormitory)330.12 2137.07 0 65.36 2533
15Xinghualin
gXinjie Xincun Taiyuan Leather Plant
(dormitory)265.1 1913.79 14.1 95.77 2289
16Xinghualin
g
Xinjie Xincun Frozen Food Main Plant ofTaiyuan Aquatic ProductCompany (dormitory)
0 401.89 0 23.2 425.1
17Xinghualin
gXinjie Xincun Taiyuan Transport Company
(dormitory)0 733.72 0 28.28 762
174
House� )
No. District OfficeCommunity
OrganizationSteelandconcrete
Brick andconcrete
Brick andwood
Simple
Total
18Xinghualin
gXinjie Xincun Taiyuan Rolling Mill
(dormitory)211.5 108 0 12.72 332.2
19Xinghualin
gXinjie Xincun Xincun Primary School
(dormitory)68 36 0 0 104
20Xinghualin
gYangjiayu
Baergou Taiyuan SlideFastener Plant 884 36 0 84 1004
21Xinghualin
gYangjiayu
BaergouXinghualing Yangjiayu Sub-
district Office, DaochanggouVillage
180 630 0 320 1130
Total of Xinghualing (21 enterprisesand institutions) 8776.24 9366.12 14.1 669.78 18826
1YingzeDistrict
Haozhuang
DianpoVillage
Dianpo Mould Material Plant 77 0 0 0 77
2YingzeDistrict
Haozhuang
DianpoHongchao Company 105.8 0 0 0 105.8
3YingzeDistrict
Haozhuang
Dianpo Warehouse of Taiyuan ThirdConstruction Company
186 0 186 0 372
4YingzeDistrict
Haozhuang
DianpoXinglong Auto Repair Plant 3200 0 0 0 3200
5YingzeDistrict
Haozhuang
DianpoMould Material Plant 77 0 0 0 77
6YingzeDistrict
Haozhuang
Dongtaibao Baiyun Garden 495.5 0 0 0 495.5
7YingzeDistrict
Haozhuang
Dongtaibao Jingdong Vehicle DrivingSchool
498 0 0 0 498
8YingzeDistrict
Haozhuang
DongtaibaoShanxi Mental Health Center 1440.7 101.26 0 0 1542
175
House� )
No. District OfficeCommunity
OrganizationSteelandconcrete
Brick andconcrete
Brick andwood
Simple
Total
9YingzeDistrict
Haozhuang
Dongtaibao Refrigerated WarehouseofTaiyuan Bingfeng Plaza
147 82 0 26 255
10YingzeDistrict
Haozhuang
DongtaibaoTaiyuan Psychiatric Hospital 293 101 0 30 424
11YingzeDistrict
Haozhuang
Dongtaibao Taiyuan Construction Industryand TradeCo., Ltd.
640.25 0 0 0 640.3
12YingzeDistrict
Haozhuang
HaojiagouThe Professional TrainingAcademy of Radio Film & TV
800 0 0 79.52 879.5
13YingzeDistrict
Haozhuang
Haojiagou Haojiagou Village (No.2 wellhouse)
0 30.4 0 15 45.4
14YingzeDistrict
Haozhuang
Haojiagou Shanxi Huaqi MachineryCompany
560 210 0 0 770
15YingzeDistrict
Haozhuang
Haojiagou Shanxi Sanjin MedicineIndustry
376.76 0 0 82.28 459
16YingzeDistrict
Haozhuang
Haojiagou Switch Plant of Shanxi PowerCorporation
1838 0 0 0 1838
17YingzeDistrict
Haozhuang
HaojiagouPetrochemistry Branch Factory 814.26 0 0 0 814.3
18YingzeDistrict
Haozhuang
HaozhuangVillage
Shanxi ArchivesBureau 13058.4 0 0 359.25 13418
19YingzeDistrict
Haozhuang
Haozhuang Warehouse of Shanxi HuaqiaoFriendship Company
195 0 0 0 195
20YingzeDistrict
Haozhuang
HaozhuangTaiyuan Hoist Plant 5836.68 0 0 5 5842
21YingzeDistrict
Haozhuang
Haozhuang Taiyuan AsbestosPlant (JieruiBuilding MaterialsCompany)
1318.71 969.66 0 179.03 2467
176
House� )
No. District OfficeCommunity
OrganizationSteelandconcrete
Brick andconcrete
Brick andwood
Simple
Total
22YingzeDistrict
Haozhuang
Haozhuang Taiyuan Zhaoyang CharcoalInk Plant
790.51 0 0 0 790.5
23YingzeDistrict
Haozhuang
Haozhuang Taiyuan RescueAdministrativeStation
973.8 95.4 0 250.5 1320
24YingzeDistrict
Haozhuang
HaozhuangTaiyuan Railway Prison 759.73 0 0 260.68 1020
25YingzeDistrict
Haozhuang
Haozhuang Xinhui Metal FormingMachinery Plant
1524.62 0 0 0 1525
26YingzeDistrict
Haozhuang
Wangjiafeng
Wangjiafeng No.2 Brick Plant 24 248.6 0 24 296.6
27YingzeDistrict
Haozhuang
Wangjiafeng
Wangjiafeng No. 1 Brick Plant 174.05 0 0 0 174.1
28YingzeDistrict
Haozhuang
Wangjiafeng
WangjiafengVillagerCommittee
2297.15 188.02 0 0 2485
29YingzeDistrict
Haozhuang
Wangjiafeng
Wangjiafeng Primary School 1664.22 0 0 7456 9120
Total of Yingze (30 enterprisesand institutions)44874.8
42026.34 186
8767.26
55854
1 Xiaodian Beiying XutanHorticultural Research Instituteof Shanxi Academy ofAgricultural Science
1013 4714 0 0 5727
2 Xiaodian BeiyingLongbaoVillage
Longbao Village Collectivity 524.2 252 0 68 844.2
Total of Xiaodian (2 enterprises and institutions) 1537.2 4966 0 68 6571Total of Taihang Road (53 enterprises and institutions) 55188 16358 200 9505 81252Subproject of public transport (4 enterprises and institutions) 0 4500 4876 3050 12426
177
House� )
No. District OfficeCommunity
OrganizationSteelandconcrete
Brick andconcrete
Brick andwood
Simple
Total
Total: 112 enterprises and institutions 58122 167237.5 15088.9 26115 266563.4Data source: Resettlement survey of Taiyuan Urban Transport Project........................................................................................................................................
178
Attached Table 4 illegal buildings of private households Unit
: �
Subproject
District Office Village
(community) )
Area of unlicensed buildings
Taihang Road Xiaodian Beiying Longbao 289
Taihang Road Xinghualing Yangjiayu Daochanggou 287.00
Taihang Road Xinghualing Yangjiayu Baergou 172.6
Taihang Road Xinghualing Yangjiayu Xiaozaogou 226.62
Taihang Road Yingze Haozhuang Dianpo 36.55
Taihang Road Yingze Haozhuang Haojiagou 22.07
Taihang Road Yingze Haozhuang Wangjiafeng 53.00
North Mid Ring Road
Xinghualing Dunhuafang Jinjixi 4331.47
North Mid Ring Road
Xinghualing Yangjiayu Xiangtang Village
79.54
North Mid Ring Road
Xinghualing Dunhuafang Kuangji 200.00
Total 5697.85
179
Attached Table 5 Illegal buildings of enterprises and institutions(m2)
District Office Community Organization Area Jiancaoping
Gucheng Senyuannan Beichen Development Company 804
Jiancaoping
Gucheng Senyuannan Shanxi Chemical Plant 3516
Jiancaoping
Gucheng Senyuannan Bolang Shirt Plant 168
Jiancaoping
Gucheng Senyuannan Linzhou Construction No.9 Company
3800
Jiancaoping
Gucheng Senyuannan Raw Material Section of Taiyuan Iron & Steel
24
Jiancaoping
Gucheng Senyuannan Taiyuan Forest Center 3056
Jiancaoping
Huifeng Huifeng Taiyuan Fruit Tree Center 667.3
Jiancaoping
Huifeng Huifeng Taiyuan Irrigation Equipment Second Plant
60
Jiancaoping
Huifeng Huifeng Galaxy Aluminum Plant 133
Jiancaoping
Huifeng Xiliu Shuangqin Honeycomb Briquet Plant
96
Jiancaoping
Huifeng Xiliu Taiyuan Air Tube Plant 328
Jiancaoping (total 14 enterprises and institutions) 12652.3
Wanbolin Wanbolin Anguang Shanxi Chengruida Pylon Manufacturing Co., Ltd.
467.6
Wanbolin Wanbolin Anguang Shanxi Guangjuye Industry Co., Ltd. 0
Wanbolin Wanbolin Anguang Shanxi Defense Industry Motor Transport Company
891.25
Wanbolin Wanbolin Jinjixi Jinxi Prefabricated Structure Plant 16 Wanbolin Wanbolin Jinjixi Taiyuan Fruit Tree Center 495.2 Wanbolin Wanbolin Jinjixi Taiyuan Xinhua Machinery Plant 2500 Wanbolin (total 6 enterprises and institutions) 4370.05 Xinghualing
Dunhuafang
Wohushan Shanxi Jin’an Chemical Plant 4026
Xinghualing
Julun Xishengli Taiyuan Kuangji Machine (Group) Co., Ltd.
1718.4
Xinghualing
Julun Shangbeiguan
Shanxi Luweibao Taigang Fireproof Materials Co., Ltd.
48
Xinghualing
Julun Shangbeiguan
Taiyuan Rolling Stock Plant 758
Xinghualing (total 4 enterprises and institutions) 6550.4 North Mid Ring Road (21 enterprises and institutions) 23991.75
180
Xinghualing
Dadongguan
Honggou Dongshan Hear Resource Plant 96
Xinghualing
Dadongguan
Wulongkou Yada Enterprise 246.86
Xinghualing
Dadongguan
Xinnan Shanxi People Defense 838 224
Xinghualing
Xinjie Taihang Road
Dongshan Coal Mine (dormitory) 253.74
Xinghualing
Xinjie Xincun Dadongguan Building Materials
Main Plant (dormitory) 48.84
Xinghualing
Xinjie Xincun Shanxi Machine Manufacturing Co.,
Ltd. (dormitory) 374.5
Xinghualing
Xinjie Xincun Shanxi Knitting Mill (Huangpi) (dormitory)
75.525
Xinghualing
Xinjie Xincun Tumor Hospital (dormitory) 251.555
Xinghualing
Xinjie Xincun Fifth Company of Shanxi Construction Corporation (dormitory)
49.58
Xinghualing
Xinjie Xincun Taiyuan Pressing Plant (dormitory) 176.15
Xinghualing
Xinjie Xincun Taiyuan Forest Center (dormitory) 191.73
Xinghualing
Xinjie Xincun Taiyuan No.1 Wool Spinning Plant
(dormitory) 1101.215
Xinghualing
Xinjie Xincun Taiyuan Leather Plant (dormitory) 1011.83
Xinghualing
Xinjie Xincun Frozen Food Main Plant of Taiyuan Aquatic Product Company (dormitory)
212.545
Xinghualing
Xinjie Xincun Taiyuan Transport Company (dormitory)
381
Xinghualing
Xinjie Xincun Taiyuan Rolling Mill (dormitory) 60.36
Xinghualing
Xinjie Xincun Xincun Primary School (dormitory) 18
Xinghualing
Yangjiayu Baergou Taiyuan Slide Fastener Plant 120
Xinghualing
Yangjiayu Baergou Xinghualing Yangjiayu Sub-district
Office, Daochanggou Village 950
Xinghualing (19 enterprises and institutions) 5843.43
Yingze Haozhuang
Dianpo Village
Warehouse of Taiyuan Third Construction Company
186
Yingze Haozhuang
Dongtaibao Shanxi Mental Health Center 101.26
Yingze Haozhuang
Dongtaibao Refrigerated Warehouse of Taiyuan Bingfeng Plaza
108
181
Yingze Haozhuang
Dongtaibao Taiyuan Psychiatric Hospital 131
Yingze Haozhuang
Haojiagou The Professional Training Academy of Radio Film & TV
79.52
Yingze Haozhuang
Haojiagou Haojiagou Village (No.2 well house) 45.4
Yingze Haozhuang
Haojiagou Shanxi Huaqi Machinery Company 210
Yingze Haozhuang
Haojiagou Shanxi Sanjin Medicine Industry 82.28
Yingze Haozhuang
Haozhuang Village
Shanxi Aechives Bureau 359.25
Yingze Haozhuang
Haozhuang Village
Taiyuan Hoist Plant 5
Yingze Haozhuang
Haozhuang Village
Taiyuan Asbestos Plant (Jierui Building Materials Company)
1148.69
Yingze Haozhuang
Haozhuang Village
Taiyuan Rescue Administrative Station
345.9
Yingze Haozhuang
Haozhuang Village
Taiyuan Railway Prison 260.68
Yingze Haozhuang
Wangjiafeng
Wangjiafeng No.2 Brick Plant 272.6
Yingze Haozhuang
Wangjiafeng
Wangjiafeng Primary School 7456
Yingze (15 enterprises and institutions) 10791.58
Xiaodian Beiying Xutan Horticultural Research Institute of Shanxi Academy of Agricultural Science
4714
Xiaodian (1 institution) 4714 Taihang Road (35 enterprises and institutions) 21349.01 Total 44921.76
182
Attached Table 6 Affected attachments of private family households
District OfficeCommunity
Telephone
Closedcircuittelevision
Air-conditioner
Electricitymeter
Watermeter
Screenwall Fence
Bigtree
Fruittree
Fruittreewithout fruits
Greenhouse Well Pool
Terrace
I. North Mid Ring Road
Huifeng 25 20 25 25
Xiliu 51 51 3 64 64 29 100 2HuifengXiaodongliu
75 75 7 681 101 70 1 14 4 25Jiancaoping
GuchengSenyuannan
210 210 230 230 16
Julun Xishengli 28 28 28 28
Kuangji 80 80 80 80Dunhuafang Jinjixi 556 543 681 681
Xinghualing
YangjiayuXiangtangVillage
250 235 265 265
Subtotal of North Mid Ring 1275 1242 10 2054 1474 99 100 1 16 4 25
II. Taihang Road
Xiaodian Beiying Longbao 26 25 71 71 25 415 6 80 48 1 6 128
TaihangRoad
20 20 20 20Xinjie
Xincun 234 224 250 250
Daochanggou
32 32 51 51 20 576.8 36 8 1
Baergou 4 4 4 4 4 30 1
Xinghualing
Yangjiayu
Xiaozaogou
31 31 39 39 23 599.6 11 281 4 14
Dianpo 11 11 1 21 21 11 147.5 2 15 4 50 16
Haojiagou 55 55 3 830 691 55 686.1 19 5 168.9 2 7 491Yingze HaozhuangWangjiafeng
75 67 145 145 54 997.8 61 165 4 104 27 60
Subtotal of Taihang Road 488 469 4 1431 1292 192 3585 156 554 8 402.9 8 71 11
III. Subproject of pulic transport 0 0 0 0 0 4 2600 3 3 0 0 0 3 0
Total 1763 1711 14 3485 2766 295 6285 160 573 12 427.9 8 74 11
183
Attached Table 7 Affected attachements of enterprises and institutionsDistrict Office Community Fence (�) Well Big tree Small tree Greenhouse (�) Fruit tree Terrace (�)
I. North Mid Ring Road 7279.1 5 1079 8022.4 8832
Gucheng Senyuannan 1756 0 0 0 0
Huifeng 916.1 0 0 618 0JiancaopingHuifeng
Xiliu Village 1056 0 2 3280 0
Anguang 709 0 0 882 0Wanbolin Wanbolin
Jinjixi 1001 1 120 1185.4 8432
Dunhuafang Wohushan 357 4 513 445 400
Shangbeiguan 859 0 444 1612 0XinghualingJulun
Xishengli 625 0 0 0 0
II. Taihang Road 12435.1 7 1511 119 10853.75 346 3322
Honggou 297 0 0 0 0 0 0Dadongguan
Xinnan 443.1 0 0 0 0 0 0
Xinjie Taihang Road 15 0 87 0 360 0 2500
Xinjie Xincun 208.25 0 34 0 0 0 0
Xinghualing
Yangjiayu Baergou 323.5 0 100 0 0 0 0
Dianpo Village 99 0 0 0 1298 0 0
Dongtaibao village 6541 3 202 2 2572 6 0
Haojiagou 1998.7 2 666 12 2625.41 0 30
Haozhuang Village 1119 0 140 76 552.34 200 792
Yingze Haozhuang
Wangjiafeng 705.5 1 260 29 0 140 0
Xiaodian Beiying Xutan 685 1 22 0 3446 0 0
III. Subproject of public transport 2281 0 200 0 0 0 0
Total 29995.2 12 2790 119 18876.15 346 12154
184
Attached Table 8 Shops affected by Taiyuan Urban Transport Project
No. Shop Name Address Area Staff
1 Liangjie Daily Cosmetics Huifeng, Jiancaoping 25.5 2
2 Children’s Clothes Shop Xiliu, Huifeng, Jiancaoping
34 1
3 Par Merchandise Supermarket XiliuVillage, Huifeng, Jiancaoping
45 3
4 Xiaozhang Restaurant Xiliu Village, Huifeng, Jiancaoping
22.5 3
5Eighth Branch of Friendship
Convenience Store Xiliu Village, Huifeng, Jiancaoping
45 2
6 Xiaozhang Convenience Store Xiliu Village, Huifeng, Jiancaoping
32 1
7 Chengxin Grain & Oil Xiliu Village, Huifeng, Jiancaoping
45 2
8 Ruchun Bistro XiliuVillage, Huifeng, Jiancaoping 43 3
9 Hongye Cake House Xiliu Village, Huifeng, Jiancaoping
32 3
10 Baozi Shop Xiliu Village, Huifeng, Jiancaoping
27 2
11 China Netcom Xishengli, Julun, Xinghualing
24 10
12 Taiyuan Yili Trade Company Xishengli, Julun, Xinghualing
24 1
13 Cangzhou Marketing Company, Harbin Bearing Main Plant
Xishengli, Julun, Xinghualing
23 2
14 Taiyuan Xile Lubricating Hydraulic Equipment Co., Ltd.
Xishengli, Julun, Xinghualing
37 2
15 Taiyuan Xinyida Mechanical and Electrical Company
Xishengli, Julun, Xinghualing
23 2
16 Hairdressing House Xishengli, Julun, Xinghualing
21 2
17 Dongbei Dumpling Xinghualing Refractory Plant
25 2
18 Qinghua Xinliangdian Solar Water Heater
Xinghualing Refractory Plant
25 1
19 Longbao Auto Decoration Xinghualing Refractory Plant
50 5
20 Haina Hardware Electric and Chemical
Xinghualing Refractory Plant
50 2
21 Binbin Chess and Card Game Hall
Xinghualing Refractory Plant
25 4
22 Wreath and Grave Clothes Xiangtang Village, Yangjiayu, Xinghualing
20 1
23 Shunmei Auto Beautification Xiangtang Village, 50 3
185
No. Shop Name Address Area Staff Yangjiayu, Xinghualing
24 Shengwang Convenience Store Xiangtang Village, Yangjiayu, Xinghualing
25 2
25 Black and White Iron Processing
Xiangtang Village, Yangjiayu, Xinghualing
10 1
26 Lufa Tire Repair Xiangtang Village, Yangjiayu, Xinghualing
20 1
27 Xinglong Autocycle Repair Xiangtang Village, Yangjiayu, Xinghualing
19 2
28 Chengxinli Building Materials Xiangtang Village, Yangjiayu, Xinghualing
23 2
29 Haili Building Materials Agency
Xiangtang Village, Yangjiayu, Xinghualing
28 2
30 Daochanggou Vegetable Market
Daochanggou, Yangjiayu, Xinghualing
300 30
31 Xiaofeng Noodle Restaurant Daochanggou, Yangjiayu, Xinghualing
31 2
32 Clinic Daochanggou, Yangjiayu, Xinghualing
26 1
33 Muslem Meat Diet Shop Daochanggou, Yangjiayu, Xinghualing
28 2
34 Fangxin Meat Diet Shop Daochanggou, Yangjiayu, Xinghualing
32 2
35 Sanjin First Bowl Daochanggou, Yangjiayu, Xinghualing
35 3
36 Liquefied Gas Supply Station Daochanggou, Yangjiayu, Xinghualing
67 5
37 Yuli Daily Cosmetics Daochanggou, Yangjiayu, Xinghualing
25 2
38 Public Telephone Supermarket Daochanggou, Yangjiayu, Xinghualing
22 2
39 Chongqing Noodle Restaurant Daochanggou, Yangjiayu, Xinghualing
28 2
40 Yinzhong Clinic Daochanggou, Yangjiayu, Xinghualing
29 1
41 Public Telephone Supermarket Daochanggou, Yangjiayu, Xinghualing
18 1
42 Haisheng Restaurant Daochanggou, Yangjiayu, Xinghualing
48.5 5
43 Hotel Restaurant Daochanggou, Yangjiayu, Xinghualing
87.2 6
44 Fangxin Noodle Shop Daochanggou, Yangjiayu, Xinghualing
21.5 3
45 Video Disc Lending, Tobacco and Wine Shop
Dongshan Coal Mine,
Tanghang Community,
Xinghualing 32 1
186
No. Shop Name Address Area Staff
46 Linmin Fruit and Vegetable Shop
Dongshan Coal Mine, Tanghang Community, Xinghualing
32 3
47 Hongdong Restaurant Dongshan Coal Mine, Tanghang Community, Xinghualing
32 5
48 Vegetable Dongshan Coal Mine, Tanghang Community, Xinghualing
38 5
49 Hengsheng Trade Firm Dongshan Coal Mine, Tanghang Community, Xinghualing
32 3
50 Zhengzhou Mutton Noodle Dongshan Coal Mine, Tanghang Community, Xinghualing
32 4
51 Yiliya Cosmetics Shop Dongshan Coal Mine, Tanghang Community, Xinghualing
32 2
52 Binchang Auto Repair Dongshan Coal Mine, Tanghang Community, Xinghualing
32 3
53 Jiangsu Harware Painting Dongshan Coal Mine, Tanghang Community, Xinghualing
32 3
54 Dingxin Tobacco and Wine Shop
Dongshan Coal Mine, Tanghang Community, Xinghualing
32 1
55 Water Tank and Tire Repair Dongshan Coal Mine, Tanghang Community, Xinghualing
32 2
56 Dahe Auto Repair Wulongkou, Dadongguan, Xinghualing
24 3
57 Dabing Tire Wulongkou, Dadongguan, Xinghualing
20 2
58 Chuangxing Decoration Wulongkou, Dadongguan, Xinghualing
39.6 4
59 Public Telephone Supermarket Wohushan� Yangjiayu�Xinghualing
23 1
60 Tobacco, Wine and Nonstaple Food Shop
Wohushan, Yangjiayu, Xinghualing
23 1
61 Noodle Restaurant Wohushan, Yangjiayu, Xinghualing
32 3
62 Small Restaurant Wohushan, Yangjiayu, Xinghualing
42 3
63 Drinking Water Wholesale Wohushan, Yangjiayu, 47 3
187
No. Shop Name Address Area Staff Xinghualing
64 Nonstaple Fool Wholesale and Retailing
Wohushan, Yangjiayu, Xinghualing
23 3
65 Tobacco, Wine and Nonstaple Food Shop
Wohushan, Yangjiayu, Xinghualing
23 2
66 Retail Section Wohushan, Yangjiayu, Xinghualing
23 1
67 Convenience Store Wohushan, Yangjiayu, Xinghualing
31 2
68 Wheaten Food Restaurant Wohushan, Yangjiayu, Xinghualing
22 2
69 Tobacco, Wine and Nonstaple Food
Haozhuang Village, Haozhuang Town, Yingze
42 1
70 Supply and Marketing Cooperative Store
Haozhuang Village, Haozhuang Town, Yingze
37.4 7
71 Tobacco, Wine and Nonstaple Food
Haozhuang Village, Haozhuang Town, Yingze
21 1
72 Wheaten Food Restaurant Haozhuang Village, Haozhuang Town, Yingze
20 2
73 Chess and Card Game Room Haozhuang Village, Haozhuang Town, Yingze
26 1
74 Feilong Tea House Haozhuang Village, Haozhuang Town, Yingze
20 3
75 Public Telephone Supermarket Haojiagou, Haozhuang, Yingze
15 3
76 Xiaochou Hairdressing Haojiagou, Haozhuang, Yingze
16 2
77 Ershao Store Haojiagou, Haozhuang, Yingze
32 2
78 Qinyan Clinic Haojiagou, Haozhuang, Yingze
30 2
79 Ruilin Autobycle Repair Haojiagou, Haozhuang, Yingze
20 2
80 Black and White Iron Electric Welding
Haojiagou, Haozhuang, Yingze
20 2
81 Welfare Lottery Haojiagou, Haozhuang, Yingze
15 1
82 Xinya Cosmetics Haojiagou, Haozhuang, Yingze
25 3
83 Yingying Computer Operating Room
Haojiagou, Haozhuang, Yingze
10 2
84 Tianrui Technology Haojiagou, Haozhuang, Yingze
10 2
85 Sign-up Place of Driving School of Driver Association
Haojiagou, Haozhuang, Yingze
15 1
86 Guangtou Tobacco and Wine Shop
Haojiagou, Haozhuang, Yingze
15 1
188
No. Shop Name Address Area Staff
87 Weiye Advertising Haojiagou, Haozhuang, Yingze
15 2
88 Xinxin Restaurant Haojiagou, Haozhuang, Yingze
20 3
89 Yinhua Cosmetics Haojiagou, Haozhuang, Yingze
15 1
90 Mrizhongmei Daily Cosmetics Haojiagou, Haozhuang, Yingze
10 1
91 Xiaojin Knitting Haojiagou, Haozhuang, Yingze
10 1
92 Tengfei Auto Repair Haojiagou, Haozhuang, Yingze
10 2
93 Xingxing Driving School Training
Haojiagou, Haozhuang, Yingze
10 1
94 Wanbao Emerald House Haojiagou, Haozhuang, Yingze
10 1
95 Mobile Telephone Shop Haojiagou, Haozhuang, Yingze
10 1
96 Bed Clothes Shop Haojiagou, Haozhuang, Yingze
10 1
97 Xiaoxia Elaborative Gloves Haojiagou, Haozhuang, Yingze
10 1
98 Labor Protection Appliance Section 2
Haojiagou, Haozhuang, Yingze
20 2
99 Doudou Shoes and Hats Haojiagou, Haozhuang, Yingze
10 1
100 Xinxiang Daily Cosmetics Haojiagou, Haozhuang, Yingze
10 1
101 Changhong Battery Haojiagou, Haozhuang, Yingze
15 1
102 Buddhism Articles Haojiagou, Haozhuang, Yingze
15 1
103 Sanwei Hats Haojiagou, Haozhuang, Yingze
15 1
104 Yuanfang Electric Appliances Haojiagou, Haozhuang, Yingze
15 1
105 Shuanglu Battery Haojiagou, Haozhuang, Yingze
15 1
106 Nanfang Watch Haojiagou, Haozhuang, Yingze
15 1
107 Yiren Hospital Chaoyanggou, Haozhuang, Yingze
300 23
Subproject of public transport 4 Nanhandepot Waliu Village 80 8
Helaowan Initial and Terminal Station
Helaowan Village, Duerping Sub-district
Office 80 5
190
Attached Table 9 List of affected families of vulnerable groups
District Office Community Name of the head of the household
Population Description
Xinghualing Yangjiayu Xiangtang Village Wang Zhongyi 3 Low income
Xinghualing Yangjiayu Xiangtang Village Lin Shuanling 3 Low income
Xinghualing Yangjiayu Xiangtang Village Wang Yiling 3 Low income
Xinghualing Yangjiayu Xiangtang Village Li Gaixiang 2 Low income
Xinghualing Yangjiayu Xiangtang Village Tian Mixiang 1 Low income
Xinghualing Yangjiayu Xiangtang Village Li Changsheng 3 Low income
Xinghualing Yangjiayu Xiangtang Village Zhang Yuling 1 Low income
Xinghualing Yangjiayu Xiangtang Village Hao Gaixian 1 Low income
Xinghualing Yangjiayu Xiangtang Village Li Liang 4 Low income
Xinghualing Yangjiayu Xiangtang Village Li Ming 3 Low income
Xinghualing Yangjiayu Xiangtang Village Li Long 4 Low income
Xinghualing Yangjiayu Xiangtang Village Guo Jiuzhu 2 Low income
Xinghualing Yangjiayu Xiangtang Village Yan Cuihua 1 Low income
Xinghualing Yangjiayu Xiangtang Village Wang Tong 3 Low income
Xinghualing Yangjiayu Xiangtang Village Kou Fulong 4 Low income
Xinghualing Yangjiayu Xiangtang Village Ma Zhenping 2 Low income
Xinghualing Yangjiayu Xiangtang Village An Ruishan 2 Low income
Xinghualing Yangjiayu Xiangtang Village An Shuming 3 Low income
Xinghualing Yangjiayu Xiangtang Village Ren Xianrong 2 Low income
Xinghualing Yangjiayu Xiangtang Village Fang Xiuying 4 Low income
Xinghualing Yangjiayu Xiangtang Village Zhang Rui 4 Low income
Xinghualing Yangjiayu Xiangtang Village Kang Ji 2 Low income
Xinghualing Yangjiayu Xiangtang Village Kang Shushan 3 Low income
Xinghualing Yangjiayu Xiangtang Village Li Gaifang 3 Low income
Xinghualing Yangjiayu Xiangtang Village An Yinping 3 Low income
Xinghualing Yangjiayu Xiangtang Village Ling Ping 3 Low income
Xinghualing Yangjiayu Xiangtang Village Duo Genlai 4 Low income
Xinghualing Yangjiayu Xiangtang Village Hu Yongming 2 Low income
Xinghualing Yangjiayu Xiangtang Village Kou Bianmei 3 Low income
Xinghualing Yangjiayu Xiangtang Village Yang Zhijing 1 Low income
Xinghualing Yangjiayu Xiangtang Village Ma Cuihua 1 Low income
Xinghualing Yangjiayu Xiangtang Village Xing Guilin 3 Low income
Xinghualing Yangjiayu Xiangtang Village Ren Runmei 3 Low income
Xinghualing Yangjiayu Xiangtang Village Liu Ruilong 2 Low income
Xinghualing Yangjiayu Xiangtang Village Zheng Xiufang 1 Low income
Xinghualing Yangjiayu Xiangtang Village Yan Yuqing 1 Low income
Xinghualing Yangjiayu Xiangtang Village Xing Fanze 2 Low income
Xinghualing Yangjiayu Xiangtang Village Jiao Jinliang 1 Low income
Xinghualing Yangjiayu Xiangtang Village Ma Xianguo 2 Low income
Xinghualing Yangjiayu Xiangtang Village Guo Liansheng 2 Low income
Xinghualing Yangjiayu Xiangtang Village Guo Hugen 4 Low income
Xinghualing Yangjiayu Xiangtang Village Guo Hulin 4 Low income
191
District Office Community Name of the head of the household
Population Description
Xinghualing Yangjiayu Xiangtang Village Guo Hujin 4 Low income
Xinghualing Yangjiayu Xiangtang Village Pi Runxiang 1 Low income
Xinghualing Yangjiayu Xiangtang Village Fan Guilan 1 Low income
Jiancaoping Gucheng Senyuannan Street Wei Runsheng 11 Low income
Jiancaoping Gucheng Senyuannan Street Yan Lansheng 4 Low income
Yingze Haozhuang Haojiagou Hu Baolian 4 No regular income
Yingze Haozhuang Haojiagou Hao Xiu 2 No regular income
Yingze Haozhuang Haojiagou Zhang Sanni 1 No regular income
Jiancaoping Huifeng Dadongliu Xu Gaifeng 4 Disabled, no regular income
Jiancaoping Huifeng Dadongliu Xu Guilan 4 No regular income, disabled
Jiancaoping Huifeng Dadongliu Geng Erqing 4 No regular work, disabled
Jiancaoping Huifeng Dadongliu Li Jinlong 3 Disabled, no regular income
Jiancaoping Huifeng Dadongliu Duan Sansuo 3 Old and sickly, no regular income
Jiancaoping Huifeng Dadongliu Xu Gailing 4 With congenital disease, no regular income
Jiancaoping Huifeng Dadongliu Li Chun 3 Congenital disability
Jiancaoping Huifeng Dadongliu Li Meihua 4 Congenital disease
Jiancaoping Huifeng Dadongliu He Wanxi 4 Sickly, disablement
Jiancaoping Huifeng Dadongliu Xu Gaihua 3 No regular income
Jiancaoping Huifeng Dadongliu Hao Qizhi 1 Congenitalling weak in intelligence
Jiancaoping Huifeng Xiaodongliu Li Guizhong 3 Weak, no working ability
Jiancaoping Huifeng Xiaodongliu Li Guowen 4 Disabled
Jiancaoping Huifeng Xiaodongliu Wang Wenzhang 4 Unemployed
Jiancaoping Huifeng Xiaodongliu Li Haiyu 4 Unemployed and sickly
Jiancaoping Huifeng Xiaodongliu Ma Sanmao 4 Weak
Jiancaoping Huifeng Xiaodongliu Li Pingxi 5 No regular income, weak
Jiancaoping Huifeng Xiaodongliu Li Jindong 4 Weak and old
Jiancaoping Huifeng Xiaodongliu Li Sanlong 4 Weak and no regular income
Jiancaoping Huifeng Xiaodongliu Zhang Gaihua 1 Weak
Jiancaoping Huifeng Xiaodongliu Zhang Fusuo 4 Weak
Jiancaoping Huifeng Xiaodongliu Ma Ergui 3 No regular income
Jiancaoping Huifeng Xiaodongliu Ma Manping 3 Disabled
Jiancaoping Huifeng Xiaodongliu Gong Pingping 4 Weak and no regular income
Jiancaoping Huifeng Xiaodongliu Li Tianxi 6 Disabled and no regular income
Jiancaoping Huifeng Xiaodongliu Hao Xianglin 3 Old, weak and disabled
Jiancaoping Huifeng Xiaodongliu Feng Jinping 4 Weak in intelligence
Jiancaoping Huifeng Xiaodongliu Li Fuliang 4 No regular income
Jiancaoping Huifeng Xiaodongliu Zhang Fugui 5 Disabled
Jiancaoping Huifeng Xiaodongliu Fan Qingshan 4 Weak
Jiancaoping Huifeng Xiaodongliu Li Erhuo 3 Weak
Jiancaoping Huifeng Xiaodongliu Li Quanming 4 Weak
Jiancaoping Huifeng Xiaodongliu Ye meizhen 5 No regular income
Jiancaoping Huifeng Xiaodongliu Jia Jinhu 4 No regular income
Jiancaoping Huifeng Xiaodongliu Ma Shuangxi 3 Disabled and no income
Jiancaoping Huifeng Xiliu Zhao Zhiyong 4 Weak in intelligence and limbs
192
District Office Community Name of the head of the household
Population Description
Jiancaoping Huifeng Xiliu Zhao Yuquan 4 Weak in intelligence
Jiancaoping Huifeng Xiliu Wei Quanlin 4 Weak in intelligence
Jiancaoping Huifeng Xiliu Zhao Chunsheng 7 Weak in limbs
Jiancaoping Huifeng Xiliu Wang Yuying 3 Weak in limbs
Jiancaoping Huifeng Xiliu Gao Fengxiang 1 Weaked in fingers
Jiancaoping Huifeng Xiliu Zhao Fuzhu 4 Weak in limbs
Jiancaoping Huifeng Xiliu Xu Guoping 5 Weak in vision and limbs
Jiancaoping Huifeng Xiliu Lin Fulin 6 Weak in intelligence and limbs
Jiancaoping Huifeng Xiliu Li Yingxiang 3 Weak in intelligence and limbs
Jiancaoping Huifeng Xiliu Zhang Yanxia 3 Weak in limbs
Jiancaoping Huifeng Xiliu Zhang Changshou 4 Weak in limbs
Jiancaoping Huifeng Xiliu Li Tiansheng 2 Weak in vision and intelligence
Jiancaoping Huifeng Xiliu Zhang Quanlin 4 Weak in limbs
Jiancaoping Huifeng Xiliu Zhang Yinhai 6 Weak in intelligence
Jiancaoping Huifeng Xiliu Zhang Zhuhua 4 Weak in limbs
Jiancaoping Huifeng Xiliu Zhang Dongxi 3 Weak in intelligence and limbs
Jiancaoping Huifeng Xiliu Hao Fengjin 5 Weak in limbs
Jiancaoping Huifeng Xiliu Liu Xin 4 Weak in audition
Jiancaoping Huifeng Xiliu Liu Bin 4 Weak in audition
Jiancaoping Huifeng Xiliu Zhang Fenglin 5 Weak in intelligence
Jiancaoping Huifeng Xiliu Qin Xia 7 Weak in vision
Jiancaoping Huifeng Xiliu Wang Tiancai 5 Weak in limbs
Jiancaoping Huifeng Xiliu Hao Guanxi 5 Sickly
Total: 109 households, 364 persons
Attachment 1:
Resettlement Comparison between Direct Line and
Circuitous Line of North Mid Ring Road
1 Comparison between Families affected by Relocation
1.1 Comparison of Affected Families, Persons and Building Areas
Seen from survey data, for direct line, there are 925 families with 3030 persons affected by relocation, while for circuitous line, there are 1014 families with 3347 persons affected by relocation. The total area of private houses to be relocated in direct line is 52864.9� and that is circuitous line is 68217� . Families affected by relocation in direct line are fewer that in circuitous line by 89 households, displaced persons in direct line are fewer than that in rounding by 317, and the area of building to be relocated in direct line is fewer than that in circuitous line by 15353� .
193
Moreover, among buildings to be relocated in direct line, higher-quality ones of brick and concrete structure are 51%, and brick and wood structure 39%, while in circuitous line, affected buildings of brick and concrete structure are 62%, and brick and wood structure 37%. Therefore, seen from the degree of impact of relocation on private house, direct line is obviously higher than rounding.
Table 1 Comparison of affected families, persons and building areas
Brick & Concrete (� )
Brick & Wood (� )
Simple (� ) Total (� ) Househo
ld Person
Kuangji Dormitory
2366 0 200 2566 80 264
Jinxi Community
8956.28 17325.88 4331.5 30613.6 586 1817
Xiangtang Village
15717.6 3174.16 793.54 19685.3 259 949
Total of Direct line 27039.88 20500.04 5325.04 52864.9 925 3030
Dormitory of Shanxi Chemical Plant
9961.2 6374.4 0 16335.6 297 980
Xijianhe Village
29917 4268 0 34185 475 1567
Dongjianhe Village
2128 14402 1166 17696 242 800
Total of Circuitous line
42006 25044 1166 68217 1014 3347
1.2 Comparison of Compensation Funds for Private Buildings to be
Relocated
Analyzed from compensation amounts for private houses to be relocated, compensation funds for direct line is RMB 88394400 Yuan, and for circuitous line RMB 117198000 Yuan, RMB 28803600 Yuan les than the direct line.
Table 2 Compensation funds for private families affected by relocation in two lines
Item Brick & Concrete
Brick & wood Simple Total
Compensation rate 1800 1600 1300 Relocated area for direct line 27039.88 20500.04 5325.04 52864.96 Compensation funds for direct line
48671784 32800064 6922552 88394400
Relocated area for circuitous line 42006.2 25044.4 1166 68216.6 Compensation funds for circuitous 75611160 40071040 1515800 1171980
194
line 00
2 Comparison of Affected Enterprises and Institutions
2.1 Comparison of Quantities of Relocated Buildings of Affected
Enterprises and Institutions
According to results of investigation, 8 enterprises and institutions shall be
affected by the direct line, while 14 shall be affected by the circuitous line. Relocated
area of 786, 284� shall be for the direct line, which is 11, 541� larger than that of 67, 087� for the circuitous line. As for buildings to be relocated for the direct line, there is a relative larger proportion of brick-concrete structure, accounting for 87%.
Whereas, brick-concrete structure only accounts for 57% in the circuitous line.
Therefore, it can be regarded that the impact of the direct line on the relocation of
enterprises and institutions is larger.
Table 3 Comparison of area of relocated enterprises and institutions
Unit: �No. Name
Brick & concrete
Brick& wood
Simple Total
1Beichen Real Estate Development Co., Ltd
700 84 720 1504
2 Shanxi Chemistry Factory 4712 642 2258 7612
3 Mining Machinery Company 12948 826.4 892 14666.4
4 Taiyuan Steel Factory 3966 0 0 3966
5Shanxi Taigang Refractory Company Limited
13649 0 48 13697
6 Taiyuan Locomotive Factory 20504 0 758 21262
7Xinghualing District Environmental Sanitation Team
3037 0 0 3037
8 Shanxi Jin’an Chemical Plant 8858 3806 220 12884
Total of direct line 68374 5358.4 4896 78628.4
1Beichen Real Estate Development Co., Ltd
700 84 720 1504
2 Shanxi Chemistry Factory 3716 2112 3400 9228
3 Taiyuan Snack Wholesale Market 20178 0 980 21158
4Taiyuan Boiler and Donkey Engine Factory
4441 1215 132 5788
5Shanxi Environmental Monitoring Station
2882 899 0 3781
6 Taiyuan Zoo Administration 1300 1017 128 2445
195
7 Jianhe Meat Factory 1904 2312 624 4840
8Xincheng Construction and Decoration Company
0 1998 0 1998
9 Taiyu Auto Repair Factory 1072 1976 140 3188
10 Taiyuan Tube Casting Factory 680 2484 0 3164
11 Liquid Gas Station 0 1208 360 1570
12 Jin’an Farm 0 382 732 1114
13 Taigang Secondary Pump Room 0 262 0 262
14 Jin’an Chemical Factory 1164 3568 2315 7047
Total of circuitous line 38037 19519 9531 67087
2.2 Comparison of Compensation Funds for Relocated Buildings of
Affected Enterprises and Institutions
As for compensation funds for relocated buildings, the funds for the direct line is RMB 181395032 Yuan, and for circuitous line is RMB 144402430, RMB 36992602 Yuan less than the direct line.
Table 4 Comparison of compensation funds for affected enterprises and institutions
Brick & concrete
Brick & wood
Simple structure
Total
Compensation rate (Yuan/� ) 2380 1930 1700
Relocated area for the direct line (� ) 68374 5358.4 4896 78628.4
Compensation funds for the direct line (Yuan)
162730120
10341712 8323200 181395032
Relocated area for the circuitous line (� ) 38037 19519 9531 67087
Compensation funds for the circuitous line (Yuan) 90528060 37671670 16202700 14440243
0
3 Comparison on impact of land acquisition
According to the design plan, among the lands taken for Direct line, it is only
required to pay the compensation fund for 21.7 mu of non-cultivated land, other lands
are government-owned land used for construction, which can be used by way of land
allocation. The land acquisition for Circuitous line is relatively complicated. The area
of state-owned land not used for construction to be taken totals to 202.5mu and that of
collective lands totals to 140mu. Based on the compensation rate of this project and
the rates of various taxes and levies for land acquisition stipulated by the country, the
196
total cost for the land acquisition for Circuitous line is RMB 22,335,600 Yuan, while
that for Direct line is only RMB 2,011,300 Yuan.
Table 5 Comparison on the impact and cost of the land acquisition
Area of lands to be taken (mu)
Cost for land acquisition� 10,000
Yuan�Circuitous line 342.5 2233.56
Housing site of Xijianhe Village 60 300.00
Housing site of Dongjianhe Village
80 400.00
Cost for recovery of forest plantation
142.5� 5018 Yuan / mu� 71.50
Cost for newly-increased land used for construction
342.5� 64 Yuan/� � 1462.06
Direct line 21.7 201.13
Housing site of Xiangtang Village
21.7 108.50
Cost for newly-increased land used for construction
21.7� 64 Yuan/� � 92.63
4 Summary of comparison of various influences and expenses
Table 6 Comparison on resettlement influences and cost between two lines
Item Circuitous line Direct line Extra length of Circuitous line
Affected family (household) 1014 925 89
Affected population (person) 3347 3030 317
Relocated area (� ) 135303.6 131493.3 3810.3 Affected enterprises and
institutions 14 8 6
Total compensation (10, 000 Yuan)
28392.96 27179.53 1212.83
Compensation for relocation of private families
11719 8839.4 2880
Compensation for relocation of enterprises and institutions 14440.4 18139 -3699.6
Compensation for land requisition 2233.56 201.13 2032.43
Based on above-mentioned comparison and analysis from different angles, combining integrated estimation of designing institute, environmental impact assessment unit and resettlement consultation unit after field survey on Circuitous line and direct line, the project office finally chooses the direct line as the optimal plan with following reasons:
Circuitous line is not recommended due to its huge impact on Taiyuan Zoo according to the environmental impact assessment unit.
197
Relocation amount, number of affected population and households as well as enterprises and institutions of Circuitous line are larger.
Resettlement expense for circuitous line is RMB 12128300 Yuan more than that for direct line;
The buildings requisitioned for direct program mainly are enterprises, most of which are bankrupt enterprises, and the resettlement is relatively easier.
Although direct program has a great impact on the part of fireproof material plant and locomotive works, after partial optimization, the impact may be reduced; Besides, from the angle of development, these two enterprises have been listed in the plan of outward moving by the planning department. As to the loss due to production stopping, direct program is more economic.
Round-going program involves more enterprises and institutions than direct program, and it involves relocation and acquisition of Taiyuan non-staple food wholesale market and its construction may affect and involve the employment of many persons.
As to direct program, the relocation of Xiangtang Village may be combined with the reformation plan of village in town under planning and may improve living conditions of these residents.
Table 7 Comparison conclusions of two line programs for North Mid Ring
Item compared Direct program Round-going program Environment
impact No special sensitive point No major impact on Taiyuan
Zoo Affected families 925 households, 3030 persons 1014households, 3347 persons
Affected enterprises and
institutions
8 enterprises, except two enterprise, the others are
bankrupt enterprise.
14 enterprises, involving small-ware market, with large resettlement difficulty.
Land acquisition Mainly state-owned land used for construction
A great deal of collective land will be acquisitioned, and land acquisition expenses is increased by RMB 20000 thousand Yuan.
Benefit of poor persons
Greatly improving dwelling conditions of residents in the villages in city in combination with the reformation of Xiangtang Village
Cannot be combined with reformation of the village in village. The benefits of poor persons are limited.
Direct resettlement cost
RMB 12 million Yuan less than circuitous line
RMB 12 million Yuan more than direct line
Total construction cost
The mileage is shortened by 1800m, and construction cost is reduced by RMB 126 million Yuan.
The mileage is increased by 1800m, and construction cost is increased by RMB 126 million Yuan.
Basic conclusion With good economic, environmental and social benefits. The optimum program.
With worse economic, environmental and social benefits. The second optimum program.
198
Attachment 2:
Methods for the Use and Management of the Funds for
Vulnerable Groups Affected by the Resettlement for the
World Bank Financed Taiyuan Urban Transport Project
During the implementation of the resettlement for the World Bank financed
Taiyuan Urban Transport Project, the resettlement offices at all level will provide
special help to the vulnerable families among affected persons, in order to recover and
improve their living conditions and levels as soon as possible. Besides the general
assistance measures as stated in the Resettlement Action Plan, the Resettlement Office
also specially sets a sum of funds for vulnerable groups amounting to RMB 2,000,000
Yuan, assisting those families indeed needing help. In order to bring the funds into the
maximum benefits, the methods for the use and management of the funds are
specially formulated as follows:
I. Use objective of the funds
The setting and use of the funds for vulnerable groups is intended to provide
appropriate assistance to those especially poor affected families which need special
help to ensure basic subsistence and development conditions in the process of
resettlement, to eliminate adverse impact on them during the land acquisition and
relocation, to help them obtain basic conditions of subsistence and development, and
to create conditions for recovering and improving their living levels.
II. Principles of the use and management of the funds
The use and management of the funds should comply with the following
principles:
1) Strict examination. The person obtaining the support of the funds must pass the
strict qualification accreditation.
199
2) Openness and transparence: the granting and use of the funds will be put up on
the notice board in the communities of affected population and accept public
supervision.
3) Check and evaluation: the granting, use and use impact of the funds will be
audited by the auditing department of Taiyuan City. The internal monitoring
organization and independent monitoring organization will carry out follow-up
monitoring on its use process and impact.
III. Qualification accreditation of funds gainer
The gainer of the funds for vulnerable groups must meet the following basic
conditions:
The family affected by the land acquisition or relocation for the World Bank
financed Taiyuan Urban Transport Project;
In line with the definition of vulnerable group specified in the Resettlement
Action Plan;
Indeed severely affected by land acquisition or relocation and needing special
help;
Formal written documentary evidence issued by the community, street and
village.
IV. Regulations for the use of the funds
1) In principle, the funds for each affected family of vulnerable group should not
exceed RMB 500 Yuan;
2) The funds must be used for the following purposes: allowance for purchasing
dwelling house after relocation; allowance for leasing house during the transition
period; allowance for traffic and other adverse impact caused by relocation and
resettlement; allowance for other substantial impact caused by relocation.
3) The Resettlement Office and each primary resettlement office will carry out
daily monitoring on the use of the funds. In case that it is found that the funds are
used for unspecified purpose, the offices will stop granting the funds and are
responsible for colleting the funds that have been issued.
V. Procedures of applying for and granting funds
200
The procedures of applying for and granting special funds for vulnerable groups
are as follows:
1) The Resettlement Office and all the primary offices will publicize relevant
information and regulations concerning the funds for vulnerable groups to all affected
families during the period of propagation for land acquisition and relocation.
2) If the affected family considers itself qualified, it should present a written
application to the communication, street and village resettlement offices, and provide
documentary evidence.
3) After verifying the application documents, the primary resettlement office will
order the applicants according to the degree of assistance required and put forward the
preliminary opinions on whether the assistance will be provided, assistance form and
the amount of funds issued, which may be submitted to the Resettlement Office via.
the district resettlement office.
4) After reviewing and balancing the documents, the Resettlement Office will
present a preliminary list of granting funds.
5) The preliminary list will be publicized in the communities of affected persons
in two cycles, for collecting public suggestions and accepting public supervision.
6) Within two weeks after publicizing, each primary resettlement office will
collect and verify different opinions of affected persons and put forward resolutions
which may be submitted to the Resettlement Office via. the district resettlement
office.
7) The Resettlement Office will review the opinions obtained in the process of
publicizing and present the final assistance list.
VI. Granting and management of the funds
The granting and management of the funds for vulnerable groups will adopt the
following methods:
1) The funds for vulnerable groups shall be used exclusively for its designated
purpose, the Project Office will set special accounts for management, and the funds
shall not be used for other purposes.
201
2) According to the list of assistance families determined ultimately, the
Resettlement Office will directly grant the funds to the families of vulnerable groups
in bankbook.
3) In principle, the funds approved will be granted twice, 50% of the approved
amount for each time.
4) The Resettlement Office shall require the auditing department to audit the
management and use of the funds once every year. The internal monitoring
organization and independent monitoring organization shall carry out the monitoring
on the funds twice every year and reflect its use and management status in the
monitoring reports.
5) The Resettlement Office shall set a special complaint telephone and publicize
the telephone number in the process of publicizing, for receiving the complaints of
affected persons.
202
Attachment 3:
Resettlement Information Booklet for the World Bank
Financed Taiyuan Urban Transport Project
Respected ,
The World Bank Financed Taiyuan Urban Transport Project will cover the land
your family/working unit located, and this booklet is hereby issued in order to let you
understand the general situation of the project, relevant land relocation policy of the
country and affected family/working unit.
I. General situation of the project
The World Bank Financed Taiyuan Urban Transport Project mainly includes the
subprojects such as improvement of road network, traffic management and safety, and
public traffic, and so on. The improvement of road network mainly include the
construction of North Mid Ring Road (approx.12.4km long) and Taihang Road
(approx. 10.3km long); for traffic management and safety, there are capacity
enlarging of traffic signal system, traffic improvement of road sections and junctions,
facilities for non-motor vehicle and pedestrians, traffic induction system, traffic law
enforcement and road safety education, technical research and training, and others; for
public traffic, two bus lanes will be constructed respectively for east-west and south-
north directions, and there are bus bay, bus parking and maintenance lot, initial bus
station and terminal, and intelligent bus control system, and so on.
II. Laws and regulations and compensation rates in regard to land taking
(1) Major laws and regulations
Land Administration Law of the People’s Republic of China
Regulation on the Implementation of the Land Administration Law of the
People’s Republic of China
203
Regulations for the Management of Urban Housing Demolition and Relocation
Measures for the Implementation of Land Administration of Shanxi Province
Regulations on Urban Housing Demolition and Relocation of Shanxi Province
Measures for the Management of Urban Housing Demolition and Relocation of
Taiyuan City
The Operational Policy OP/BP4.12 for involuntary resettlement by WB
(2) Compensation policy for land taking of this Project
Category Compensation rates
1. Compensation for land taking
50,000 Yuan per mu
2. Housing
For residential housing: framed structure, 1900 Yuan /� ; brick-concrete structure, 1700 Yuan /� ; brick-wood structure, 1500 Yuan /� ; simple structure, 500 Yuan /� .
For commercial buildings: framed structure, 2400 Yuan /� ; brick-concrete structure, 2300 Yuan /� ; brick-wood structure, 2200 Yuan /� .
For office buildings: framed structure, 2300 Yuan /� ; brick-concrete structure, 2200 Yuan /� ; brick-wood structure, 2100 Yuan /� .
3.Land attachments
Cave-house, 1000 Yuan each; enclosing wall, 30 Yuan /� ; terrace, 15 Yuan /� ; large timber tree, 30 Yuan each. Small timber tree, 20 Yuan each; tree with fruits, 190 Yuan each; tree without fruits, 60 Yuan each; screen wall, 300 Yuan each; big shed, 30 Yuan /� ; cable television, 300 Yuan each; water well, 500 Yuan each.
4. Special infrastructure
The compensation should be made according to concrete replacement price or negotiated price of infrastructure.
This compensation rates is formulated on the basis of survey and investigation
and in accordance with the laws and regulations of China as well as the operational
policy of involuntary resettlement by the World Bank, in order to restore and improve
the standards of living of affected population after resettlement as soon as possible.
III. Affected family/work unit
Item Quantity Compensation rates
Compensation payable
Remark
1234
204
Total IV. Predicted implementation time
Item Time Land acquisition announcement
Capital payment Relocation for land taking Moving into new houses Preparation for the project Project construction
V. Rights and obligations of affected population
(1) Rights of displaced persons
They should obtain compensations completely according to the above
compensation rates and may reflect their ideas and suggestions to the resettlement
offices of village committees/communities, towns/streets, districts and the city.
Detailed contents are: Base compensation, compensation rates, time for paying
compensation, location for building reconstruction, and so on. Each resettlement
office must give its response within 15 days after receiving the complaints of
displaced persons or those reported by lower level of resettlement office.
(2) Obligations of affected population
They should actively cooperate with project construction.
New buildings should not be set up within the range of survey after it is
conducted, or there will be no compensation.
They should demolish the buildings within the range of land for transportation.
VI. Assistance to vulnerable households
Vulnerable households will be given the following assistance:
Financial assistance. In the process of relocation, villages/communities should
offer some subsidiaries to them.
Assistance in labor service. Villages/communities give assistance to labor
force responsible for relocation.
Vulnerable households should have priority to select locations for building
reconstruction and reallocated farmland.
VII. Land relocation agencies
205
City-level agency
Leadership Office of World Bank Funded Project of Taiyuan City
Address: No.38, Fuxi Street, Taiyuan City
Post code:030002
Tel: 4152223
District-level resettlement agencies
Resettlement Office, Wanbolin District
Address: No.35, Xikuang Street, Taiyuan
Tel: 6060678
Resettlement Office, Jiancaoping District
Address: Chai Village, Jiancaoping District, Taiyuan
Tel: 5648860
Resettlement Office, Xinghualing District
Address: No.232, Jiefang Road, Taiyuan
Tel: 3041595
Resettlement Office, Yingze District
Address: No.15, Yunlu Street, Taiyuan
Tel: 4033472
Resettlement Office, Xiaodian District
Address: No.16, Changsheng West Street, Taiyuan
Tel: 7198299
Resettlement Office, Jinyuan District
Address: No. 221, Shuangtaxi Street, Taiyuan City
Tel.: 4633094
Independent Monitoring Organization: Research Center for Involuntary
Resettlement, Wuhan University
Address: Luojia Hill, Wuchang District, Wuhan City
Post code: 430072
Tel: 027-68752611
VIII. Right to interpret the booklet