Solutions of Multivariate Polynomial Systems using Macaulay Resultant Expressions
RAJASTHAN ELECTRICITY REGULATORY COMMISSION, JAIPUR In the matter of Determination of Benchmark...
-
Upload
independent -
Category
Documents
-
view
4 -
download
0
Transcript of RAJASTHAN ELECTRICITY REGULATORY COMMISSION, JAIPUR In the matter of Determination of Benchmark...
Page 1 of 23
RAJASTHAN ELECTRICITY REGULATORY COMMISSION, JAIPUR
Suo-Motu
In the matter of Determination of Benchmark Capital Cost for Solar PV
and Solar Thermal Power Projects and resultant Generic Levellised Tariff.
Coram :
Shri D.C. Samant, Chairman
Shri S.K. Mittal, Member
Shri S. Dhawan, Member
Date of hearing: 13.03.2012
Date of Order: 30.05.2012
ORDER
BACKGROUND
1. In accordance with the provisions of Electricity Act, 2003 and
National Tariff Policy notified by Govt. of India (GoI), the
Commission under its RERC (Terms and Conditions for
Determination of Tariff) Regulations, 2009 had incorporated the
enabling provisions for determination of tariff of solar power
projects.
2. Commission has issued the last tariff order on 25.05.2010 after
taking into account the comments received from the stakeholders
on the draft tariff order dt. 10.03.2010 wherein the Commission has
determined generic tariff for solar power. This tariff was applicable
for solar plants (SPV) to be commissioned by 31.03.2012 and solar
thermal plants to be commissioned by 31.03.2013 wherein PPAs
have been signed by 31.03.2011. The commission as per its order
dt 29.09.2010 has amended the tariff order dt 25.5.2010 to extend
the tariff as applicable for MW scale solar thermal plants to small
solar thermal plants covered under GoI’s subsidy scheme. The
tariffs as per the orders dt 25.05.2010 and 29.09.2010 are given in
the following Table-1.
Page 2 of 23
Table-1: Solar Tariffs in Rajasthan as per orders dt. 25.05.2010 and
29.09.2010
3. CERC had issued tariff order dt 26.04.2010, applicable for projects
where the PPAs were to get signed by 31.03.2011 and
commissioned by 31.03.2012 for SPV projects and by 31.03.2013 for
solar thermal projects and the levellised tariff for solar PV was
`17.91 per kWh and for solar thermal it was `15.31 per kWh.
4. There has been a steady decline in the tariffs due to lower cost of
solar modules and components and the emerging competitive
scenario in the country. This is best exemplified by the reverse
bidding process that was adopted for allotment of projects in the
1st Batch of Phase 1 of JNNSM, by NTPC Vidyut Vyapar Nigam Ltd
(NVVN), the nodal agency under JNNSM Phase-1 for purchase of
solar power, which has resulted in substantial discounts on the
benchmark tariffs, given in para 3 above, that were determined
by CERC.
5. CERC has, subsequently, issued order dt. 09.11.2010 (255/2010 suo-
motu) for Determination of benchmark capital cost norms for Solar
PV power projects and Solar Thermal power projects applicable
S.No. Particulars
Tariff (in `/kWh)
without AD
benefit
Tariff (in `/kWh)
if AD benefit is
availed
1 2 3 4
1 Solar Thermal Power Plants
commissioned by 31.3.2013
12.58 10.99
2 Solar Photo Voltaic (PV)
Power Plants commissioned
by 31.3.2012
15.32 13.19
3 Roof Top Solar PV Installations
and other small solar power
generation plants covered in
GoI’s subsidy scheme
commissioned by 31.3.2012
15.32 13.19
4 Small Solar Thermal Power
generation plants covered in
GoI’s subsidy scheme
commissioned by 31.03.2013
12.58 10.99
Page 3 of 23
during FY 2011-12. The revised benchmark capital cost for solar PV
was determined as `14.42cr per MW and `15cr per MW for solar
thermal projects for the FY 2011-12. Further, CERC has issued final
order dt 09.11.2010 (256/2010 suo-motu) for determination of
generic levellised generation tariff. The generic tariff was
determined as `15.39 per kWh for Solar PV and `15.04 per kWh for
Solar Thermal and would be applicable for projects wherein the
PPAs would be signed by 31.03.2012 and the plants would get
commissioned by 31.03.2013 in case of solar PV and by 31.03.2014
in case of solar thermal.
6. The final tariffs that resulted in selection of solar PV projects for the
2nd Batch of Phase-1 of JNNSM in December, 2011 through
bidding, were again substantially lower than the benchmark CERC
tariff i.e. `15.39 per kWh consequent to lower capital costs on
account of sharp drop in solar PV module prices.
7. Government of Rajasthan has issued Rajasthan Solar Energy Policy,
2011 vide Notification No. F. 20 (6) Energy /2010 dated 19.04.2011
for promoting solar energy in Rajasthan. Some of the key
objectives of the policy are
Developing a global hub of solar power of 10000-12000 MW
capacity in next 10 to 12 years to meet energy requirements of
Rajasthan and India.
Contributing to long term energy security of Rajasthan as well
as ecological security by reduction of carbon emissions and
dependence on fossil fuel resources.
Productive use of abundant wastelands, thereby utilizing the
non-industrialized desert area for creation of an industrial hub.
Creating conditions favourable to solar manufacturing
capabilities by providing fiscal incentives. Generating large
direct and indirect employment opportunities in solar and
allied industries
Page 4 of 23
To achieve the grid parity in next 7 to 8 years, the State will
encourage the Solar Power Developers to establish their
manufacturing plants in Rajasthan.
8. Commission vide its earlier order dated 2.04.2008 has prescribed
an obligation on the distribution licensees to buy 50 MW of solar
power and the same was increased to 100MW vide the
Commission’s order dt 25.05.2010. RERC notification No.
RERC/Secy./Regulation-85 dtd. 24th May, 2011, gives the
Renewable Purchase Obligation in respect of various sources
expressed as percentage of energy consumption1 and in respect
of solar, the obligation for FY 2011-12, FY 2012-13 & FY 2013-14
being 0.5%, 0.75% and 1.00% respectively.
9. CERC vide notification No. L-1/94/CERC/2011 dt 06.02.2012 has
determined the benchmark capital cost for solar PV projects at
`10.00 crores/MW with the CUF of 19% ( deration of modules has
been considered as nil and auxiliary consumption as nil) and
`13.00 crores/MW for solar thermal projects with a CUF of 23% (
deration has been considered as nil and auxiliary consumption as
10%). The interest rate for term loan was taken as 300 basis points
over the average of the Base Rate of SBI for the first six months of
the previous year and for working capital the interest rate was
considered as 350 basis points over the average of the Base Rate
of SBI for the first six months of the previous year.
10. CERC has issued final order on 27.03.2012 (Petition No. 35/2012
(Suo-Motu) in respect of the above and has determined a generic
tariff of `10.39 per unit (`9.35 per unit if AD benefit is availed) in
respect of solar PV projects and has determined a generic tariff of
1 energy consumption shall mean ‘consumption of obligated entity’ as defined in regulation 3(g) of RERC
(Renewable Energy Certificate and Renewable Purchase Obligation Compliance Framework) Regulations,
2010.
Page 5 of 23
`12.46 per unit (`11.22 per unit if AD benefit is availed) for solar
thermal projects whose PPAs would be signed by 31.03.2013 and
to be commissioned by 31.03.2014 in the case of solar PV projects
and by 31.03.2015 in the case of solar thermal projects.
11. The RERC tariff orders for solar plants dated 25.5.2010 and dated
29.9.2010 were applicable for the projects that have signed PPA
by 31.03.2011 and to be commissioned by 31.03.2012 the case of
solar PV and by 31.03.2013 in the case of solar thermal.
Draft Tariff Order
12. The Commission undertook an exercise to determine Benchmark
Capital Costs for Solar PV and Solar Thermal Power Projects and
resultant Generic Levellised Tariff for the MW scale solar plants
where PPAs would be signed by 31.03.2013 and to be
commissioned by 31.03.2014 in the case of solar PV plants and to
be commissioned by 31.03.2015 in the case of solar thermal plants.
13. In the draft tariff order issued on 23.01.2012, Commission
considered it appropriate to retain the financial norms, as
stipulated in Part – III of RERC Tariff Regulations, 2009 i.e. debt :
equity ratio, RoE, O&M escalation etc, that are applicable for the
tariff determination of other RE sources like wind/bio-mass and
were used for tariff order dt 25.05.2010 for solar projects. All the
parameters, for both solar PV and solar thermal projects, were
retained as per the tariff order dt 25.05.2010 except for capital
cost, CUF, interest rate and O&M expenses. The summary of Norms
and Parameters considered in the draft order are as under:
Page 6 of 23
Table-2: Summary of key normative parameters for solar PV (as in draft
order)
S.No. Parameter Value
1 2 3
1 Capital cost `10 crore per MW for FY 2012-13
2 Capacity Utilization Factor
(CUF)
20% with a deration of 0.5% every
year after second year.
3 Interest on term loan 12% p.a
4 Interest on working capital 12.5%
5 O&M Expenses
`11 lakhs/MW for FY 2012-13 with
an escalation of 5.72% p.a. Plus
0.3% of depreciated project cost
in each year towards insurance.
6 Auxiliary consumption 0.25%
Table-3: Summary of key normative parameters for solar thermal (as in
draft order)
S.No. Parameter Value
1 2 3
1 Capital cost ` 13 crore per MW for FY 2012-13
2 Capacity Utilization Factor
(CUF)
23% with a deration of 0.25%
every year after fourth year.
3 Interest on term loan 12% p.a
4 Interest on working capital 12.5%
5 O&M Expenses ` 15 lakhs /MW for FY 2012-13 with
an escalation of 5.72% p.a. Plus
0.3% of depreciated project cost
in each year towards insurance.
6 Auxiliary consumption 6.5%
14. Applicable Tariff for Solar PV and Solar Thermal Projects (as in draft
order)
The generic tariff levellised for 25 years for two different
technologies (solar PV & solar thermal) and for Roof Top and small
solar plants worked out as per the said norms is summarized as
follows:
Page 7 of 23
Table- 4: Summary of Solar PV and Solar Thermal Tariffs (as in draft order)
S.
No. Particulars
Tariff (`/kWh) if
AD benefit is
not availed
Tariff (`/kWh) if
AD benefit is
availed
1 2 3 4
1 Solar Photo Voltaic (PV) Power Plants
commissioned by 31.3.2014
10.12 8.85
2 Solar Thermal Power Plants
commissioned by 31.3.2015
12.08 10.57
3 Roof Top Solar PV installations and
other small solar PV power
generation plants covered in MNRE’s
scheme or Rajasthan Solar Policy to
be commissioned by 31.3.2014
10.12 8.85
4 Small Solar Thermal Power
generation plants covered in MNRE’s
scheme or Rajasthan Solar Policy to
be commissioned by 31.03.2015
12.08 10.57
Publication of draft order and stakeholder’s comments/suggestions
15. A public notice was published in the following newspapers inviting
comments on the Draft order and was also placed on
Commission’s website:
(1) The Times of India published on 25.01.2012
(2) Rajasthan Patrika published on 25.01.2012
(3) Rashtradoot published on 25.01.2012
16. Objections and suggestions were received from the following
stakeholders:
1. Shri. Shanti Prasad
2. Shri D S Agarwal, Rudraksh Energy
3. Shri. Bal Mukund Sanadhya
17. Public hearing on the Draft Order was held on 13.03.2012, in which
persons mentioned in Annexure-I participated.
Stakeholders Comments/Suggestions
18. The comments/suggestions received from the stakeholders are
mainly in respect of Capital cost, Capacity Utilisation Factor (CUF),
interest rate, Auxiliary Consumption, Depreciation and other issues
Page 8 of 23
relating to approval of bid documents, power evacuation
arrangement and public awareness. These comments have been
dealt with in the following paras.
(1) Capital Cost
Stakeholder’s Comments/Suggestions
19. Shri DS Agarwal has suggested that the capital cost of `10 Crores
per MW for Solar PV Projects appears reasonable. However,
looking to the decreasing trend it can be considered as `9.60
crores per MW for the years 2012-13 & 2013-14 provided higher
interest rate and depreciation are considered. For solar thermal
projects also he suggested that if higher Interest Rate &
Depreciation are considered then the capital cost per MW could
be reduced from `13 Crores per MW to about `12.5 crores per
MW.
Commission’s Analysis and Decision
20. As discussed later, the Commission has agreed for increase in
interest rate for long term loan. It may be mentioned that CERC’s
capital cost is in the all India context and situation varies from
State to State. The State Govt. through Rajasthan Solar Energy
Policy, 2011 is extending support for setting up solar plants in the
State, including land at concessional rate. Considering the said
position and also the declining trend in the prices of solar modules,
the Commission considers it appropriate to adopt capital cost of
9.40 Cr./MW for solar PV projects, including connectivity charges.
Similarly, in case of solar thermal, the capital cost of 12.75
Cr./MW, including connectivity charges, as against 13 Cr./MW
proposed in the draft order seems appropriate and the same is
being adopted.
Page 9 of 23
(2) Capacity Utilization Factor (CUF)
Stakeholders Comments/Suggestions
21. Shri D.S. Agarwal has suggested that The CUF of 20% for solar PV
considered by the Commission appears reasonable for Western
Rajasthan where the Solar Radiation is high but for the other parts
of Rajasthan, a lower CUF of 19% could be considered.
Commission’s Analysis and Decision
22. The Commission acknowledges that with vast geographical area
and varied climatic conditions, the solar radiation will vary. As per
the Electricity Act, 2003 the Commission has to develop regulatory
framework in such a manner so as to promote Renewable Energy
generation and at the same time protect the interests of the
consumers. In order to reduce the price burden of solar power on
consumers, it would be desirable to encourage the plants to be
located in the places which receive higher solar radiation until
there is saturation from a power evacuation point of view. At a
later stage, CUFs which are appropriate to the different
geographical regions in the State may be considered. Therefore,
Commission considers it appropriate to continue with the
proposed norm of 20% for the CUF for State as a whole and no
change is required for this parameter.
(3) Interest Rate
Stakeholders Comments/Suggestions
23. Shri Shanti Prasad submitted that Commission may consider
specifying at least mean value i.e. long term loan interest rate as
300 basis point above base rate and effecting similar changes in
interest on debt and working capital loan in respect of other
renewable energy power plants through amendment in the tariff
Regulations.
Page 10 of 23
24. Shri D.S. Agarwal of Rudrakash Energy submitted that Interest Rate
on term loans adopted as SBI Base Rate + 200 basis points appears
to be on lower side and suggested that it should be SBI Base Rate
+ 300 basis points. Similarly, the interest rate on short term loan
should be SBI Base Rate + 300 basis points.
Commission’s Analysis and Decision
25. It may be mentioned that Commission, in the draft Order , has
proposed to consider the SBI base rate as on 31st January,2012 plus
200 basis points for long term loans and SBI base rate as on 31st
January 2012 plus 250 basis points for interest on working capital
loans. However, recently Commission has finalised the fourth
amendment in RERC Tariff Regulations, 2009 where Commission
has considered average of SBI base rate for first six months of
previous financial year as the benchmark for interest rate as the
same period has been considered by CERC. In view of this
Commission considers it appropriate to take average SBI base rate
for first six months of previous financial year as bench mark for the
purpose of interest rate.
26. The Commission has taken note of the interest rate charged by
IREDA and PFC for various renewable energy projects and Interest
rate norm adopted by CERC for Solar projects as well as
suggestions of stakeholders to increase interest rate and considers
it appropriate to adopt the interest rate on long term loans as SBI
base rate (average of the base rate of the first six months of the
previous year) + 300 basis points as against 200 basis points above
the SBI Base Rate on 31st January, 2012.
27. As regards interest rate on working capital, since the loan
requirement is for shorter duration with lower associated risk, the
Page 11 of 23
interest rate would normally be lower than that of long term loan.
Commission, therefore, considers it appropriate to adopt interest
rate norm of average SBI base rate for first six months of previous
financial year plus 250 bps for working capital requirement, being
50 base points lower than that of long-term loan.
(4) Auxiliary Consumption
Stakeholders Comments/Suggestions
28. Shri D.S. Agarwal has suggested that for solar thermal plants
auxilliary consumption @ 6.5% appears to be on lower side.
Commission’s Analysis and Decision
29. Commission is of the view that the Auxiliary Consumption norm for
solar thermal projects was arrived at after detailed deliberations.
Further, the practical experience relating to solar thermal projects
so far is limited. It would, therefore, be inappropriate to change
the auxiliary consumption norm. The proposed auxiliary
consumption norm of 6.50% for solar thermal projects is, therefore ,
being retained.
(5) Depreciation
Stakeholders Comments/Suggestions
30. Shri Shanti Prasad has commented that in the calculations of tariff,
Depreciation has been considered at the rate of 5.28% p.a. for 12
years and 2.05% thereafter. RERC Tariff Regulations, 2009 specifies
depreciation to be calculated for renewable power plants as per
Regulation 23 and Appendix-1. Different rates of depreciation as
per asset categories (e.g. land, office buildings, power plant, self
propelled vehicles, communication equipments , IT equipments /
softwares, etc) have been specified at Appendix-1 of the
Regulations. Commission may clearly specify whether
depreciation will be determined category wise as per Appendix-1
or at flat rate(s) as per assumptions in the calculations of tariff and
Page 12 of 23
may, if required, accordingly amend the regulations. Similarly,
Written Down Value (WDV) method does not consider salvage
value (vide CERC ‘s calculations on RE power plant tariffs) and on
this account there is conflict between WDV method and
regulation 23.
31. Shri D.S. Agarwal has suggested that the rate of depreciation
should be 5.83% instead of 5.28% considered by the Commission.
Commission’s Analysis and Decision
32. In generic tariff determination, the Regulations have specified
lump sum capital-cost without assets-wise break-up. In view of this,
while item-wise depreciation rate can be applied for project
specific tariff, wherein different items of the project cost are
approved based on prudent check; the same is not applicable for
RE projects under generic tariff due to the lumpsum project cost
adopted. CERC also, as far as RE projects are concerned, has
been applying depreciation at a uniform rate on the adopted
project cost. The said position has been suitably incorporated in
Appendix-I of regulation 23 vide Fourth Amendment finalized
recently.
33. As regards the suggestion of conflict between WDV method and
regulation 23, it is stated that the issue raised, prima facie, seems
to relate with methodology of calculation of Accelerated
Depreciation benefit. The methodology has been revisited and AD
benefit has been reworked by following the method adopted by
CERC in applying depreciation on notional basis to calculate the
gain in Income Tax on Availing Accelerated Depreciation.
Depreciation of 5.28% as per straight line method (Book
depreciation as per Companies Act,1956) has been compared
with depreciation allowable as per Income Tax Act 1962 i.e. 80% of
written down value. For the purpose of calculations, it has been
Page 13 of 23
considered that the project would capitalized during second half
of the relevant Financial Year (i.e. Project getting commissioned
after 180 days of the Financial Year), as is being followed by CERC.
As per Income Tax Act, the depreciation rate applicable for the
first year would be 40% (50% of 80%). The income tax benefit, likely
to be so availed , has been worked out considering income tax
rate of 32.445% (=30% Income Tax Rate + 5% Surcharge+ 3%
Education Cess) for first year and 30.90%(=30% Income Tax Rate +
3% Education Cess) for subsequent years on the net depreciation
benefit. The per unit levelised AD benefit has been computed by
discounting the net depreciation benefit considering weighted
average cost of capital (WACC) as the discount factor i.e. 13.41%
(= 0.7x12.30% + 0.3 x16%).
34. In addition to above, Commission would like to clarify that
presently parameters for determination of tariff for sale of power
from solar power projects are not governed by the existing RERC
Tariff Regulations, 2009. For the purpose of determination of
generic tariff, depreciation is being applied at the general rate of
5.28% for first 12 years and remaining depreciable value spread
over the balance useful life based on norms adopted in this order.
(6) Other Comments
(a) Regulatory Approval for the Bid Documents under Competitive Bidding
Process
Stakeholders Comments/Suggestions
35. Shri Shanti Prasad has commented that Para 42 of draft order
specifies competitive tariff bidding in respect of new renewable
energy generating stations to be commissioned during Control
Period. Reg. 87 of RERC Tariff regulations specifies that the
Commission shall adopt the tariff for RE power projects as
envisaged under Section 63 of the Act and for the purpose of
competitive bidding process, until the Central Government notifies
Page 14 of 23
the competitive bidding guidelines including the Standard Bid
Documents as applicable for RE projects, the Commission shall
approve the bid documents or deviations applicable for
conventional power plant under case-2 for each type of RE
sources separately. However, for competitive bidding by Discoms
or by any agency on their behalf, the procedures need regulatory
scrutiny under section 63 and aforesaid reg. 87. The Guidelines for
Determination of Tariff by Bidding Process for Procurement of
Power by Distribution Licensees issued by the Govt. of India vide
notification of 19.1.2005, provides vide para 5.15 that the bidder
who has quoted lowest levellised tariff as per evaluation
procedure, shall be considered for the award. Thus these
guidelines do not provide for selection of bidders other than lowest
tariff. Award(s) on L1, L2, L3, etc offers till capacity requirement is
fulfilled, as has been done by NVVNL, is a major deviation requiring
regulatory commission’s approval. Commission , while considering
such deviation, may consider strictly following Govt. of India’s
guidelines with rebidding for balance quantity or following
NVVNL’s methodology or not considering different rates for the
same bidder or restricting selection within a percentage range
above L1 offer and rebidding for balance capacity or to modify
penalty and BG requirement so that it may lead to further lower
tariff or to adopt both competitive bidding as well as generic tariff
route with weighted average competitive bid price plus margin
(as determined by overall success rate) as one of the guiding
factor to determine generic tariff.
36. Shri D S Agarwal has commented on Clauses 41 & 42 that for the
projects to be selected through Competitive Bidding, the bidder
should offer discount on the Bench Mark tariff proposed at para 39
i.e, `10.12 for Solar PV & ` 12.08 for Solar thermal instead of final
tariff to be determined by the commission, so as to avoid delay.
Page 15 of 23
Commission’s Analysis and Decision
37. Commission has taken note of the suggestion /comments.
Commission would like to state that the existing competitive
bidding guidelines issued by Ministry of Power (MoP) under Section
63 of the Electricity Act 2003 do not cover the procurement of
power from RE sources and a committee has recently been
constituted to, inter-alia, evolve guidelines for competitive bidding
for procurement of power from such sources.
38. The Commission has recently examined the question of specifying
Regulations/ guidelines for introduction of competitive bidding in
the State. In the draft 4th amendment in RERC (Terms and
Conditions for determination of Tariff) Regulation, 2012 placed in
public domain and which was subsequently dropped vide order
dated 10.5.2011, the Commission came to the following
conclusion, as given in para 13 of the said order:
“In the light of the fact that Hon’ble Supreme Court has stayed
the directions of Hon’ble Tribunal in respect of issue of
guidelines by KERC to introduce competitive bidding process
and considering the stand taken by the Central Government in
the Delhi High Court, it emerges that the Commission through
Regulation or otherwise cannot frame guidelines for
transparent bidding under Sec. 63 or any other provision of the
Electricity Act and Sec. 62 is the only available option for tariff
determination in the circumstances prevailing as on date. “
39. Accordingly, the competitive bidding stipulated in draft order
would not be applicable and instead generic tariff under Section
62 of the Electricity Act 2003 is being determined through this
order.
(b) Other Comments – Power Evacuation Arrangement
Stakeholders Comments/Suggestions
40. Shri Shanti Prasad has commented that with number of solar
projects coming in and around the same substation, RVPN/
Page 16 of 23
Discoms will find it difficult to allocate one bay for each project
due to space constraints or to create additional substations due to
resources constraints. It would be appropriate that regulatory
commission considers creation of such substations and their
locations, approved by RVPN/Discoms (after considering, interalia,
no interference with Right of Way of future transmission /
Distribution system) by the private sector so that there is common
transmission line for number of power stations created by
developer of solar park or transmission licensee. It is suggested
that Commission may cover such cases by specifying that in such
cases losses and wheeling charges will be separately determined
from generating station to pooling station and for common
transmission system at pooling station and from pooling station to
substation of RVPN/Discoms on actual cost or benchmark cost
whichever is less.
Commission’s Analysis and Decision
41. Commission is of the view that the scope of present regulatory
exercise is limited to the determination tariff for sale of power from
solar power projects to the Discoms of the State and therefore,
issues relating to transmission of such power fall outside the
purview of the present order.
(c) Other Comments - General
Stakeholders Comments/Suggestions
42. Shri Bal Mukund Sanadhya has given various general comments
pertaining to public awareness of the regulatory process,
determination of tariff parameters, need for discussions on the
draft order at various state and national level fora etc.,
Page 17 of 23
Commission’s Analysis and Decision
43. The Commission is following the Electricity (Procedure for Previous
Publication) Rules, 2005 as provided under the Electricity Act, 2003
which is fair and adequate.
Roof top and small solar PV and thermal systems: Applicable Tariff (as
in Draft Order)
44. The Commission is of the considered view that the generic tariff as
applicable for MW scale solar plants be extended to roof top and
small solar power generation systems covered under MNRE /
JNNSM schemes and Rajasthan Solar Energy Policy, 2011.
Stakeholders Comments/Suggestions
45. Shri D.S. Agarwal has commented that Tariff for Roof Top & Small
Solar PV & Thermal Systems should be higher than that of MW
scale plants, since there will be a higher Capital cost per MW &
higher O & M charges for small projects.
Commission’s Analysis and Decision
46. Commission would like to state that setting up of a MW scale
power plant a set of preliminary works are required to be done
which also include land acquisition and development etc. For a
typical green field grid connected solar PV MW scale project, the
cost component towards land, civil and general works, preliminary
and preoperative expenses comes in the vicinity of 17-19% . For
Roof Top Solar PV systems such expenses would be lower.
However, CUF for roof top PV systems would be lower as such
systems may be located predominantly in the areas having lesser
solar radiation when compared with western Rajasthan which has
better solar radiation potential and also due to impact of shading
of trees/adjoining buildings.
47. Considering the above position, Commission at present finds no
merit in specifying different tariff for such systems. Similarly,
Page 18 of 23
Commission would like to continue with the earlier practice of
having same tariff for small solar projects i.e. up to 2 MW covered
in MNRE guidelines for rooftop and other small solar power plants.
Summary of final key normative parameters
48. Considering the stakeholder comments and the Commission’s
decisions on the same, the summary of the final main parameters
for solar PV and solar thermal tariff determination are given below
and other parameters are as per Annexure- II & III.
Table-5: Summary of final main normative parameters for solar PV
S.No. Parameter Value
1 2 3
1 Capital cost `9.40 crore per MW for FY 2012-13
2 Capacity Utilization Factor
(CUF)
20% with a deration of 0.5% every
year after second year.
3 Interest on term loan 12.3% p.a
4 Interest on working capital 11.8% p.a
5 O&M Expenses
`11 lakhs/MW for FY 2012-13 with
an escalation of 5.72% p.a. Plus
0.3% of depreciated project cost
in each year towards insurance.
6 Auxiliary consumption 0.25%
Table-6: Summary of final main normative parameters for solar thermal
S.No. Parameter Value
1 2 3
1 Capital cost ` 12.75 crore per MW for FY 2012-
13
2 Capacity Utilization Factor
(CUF)
23% with a deration of 0.25%
every year after fourth year.
3 Interest on term loan 12.3% p.a
4 Interest on working capital 11.8% p.a
5 O&M Expenses ` 15 lakhs /MW for FY 2012-13 with
an escalation of 5.72% p.a. Plus
0.3% of depreciated project cost
in each year towards insurance.
6 Auxiliary consumption 6.5%
Applicable Tariff for Solar PV
Page 19 of 23
49. Considering the parameters discussed above, the generic tariff for
the solar PV plants is being determined as ` 9.63/kWh, as per
calculation sheet placed at Annnexure-II. This tariff is levellised
tariff for 25 years and applicable for plants commissioned without
availing benefit of Accelerated Depreciation. With AD benefit, the
tariff would be lower by `1.21/kWh i.e. ` 8.42/kWh. This tariff would
be applicable for solar PV plants where PPA is signed on or before
31.03.2013 and which get commissioned on or before 31.03.2014.
Applicable Tariff for Solar Thermal
50. Considering the parameters discussed above, the generic tariff for
the solar thermal power plants is being determined as `11.95/kWh,
as per calculation sheet given in Annexure-III. This tariff is levellised
tariff for 25 years and applicable for plants commissioned without
availing benefit of Accelerated Depreciation. The tariff would be
lower by ` 1.50/kWh if accelerated depreciation is availed i.e. the
tariff would be `10.45/kWh. This tariff would be applicable for solar
thermal plants where PPA is signed on or before 31.03.2013 and
which get commissioned on or before 31.03.2015.
Guidelines for Metering, Billing and other Requirements
51. The guidelines laid down as per order dt 25.05.2010 as regards (i)
Metering and Billing arrangement; (ii) Technical requirements; and
(iii) General Terms and Conditions are being retained and would
be suitably incorporated in the PPA.
Conclusion
52. The generic tariff levellised for 25 years for two different
technologies (solar PV & solar thermal) and for Roof Top and small
solar plants is summarized as under:
Table- 7: Summary of Solar PV and Solar Thermal Tariffs
Page 20 of 23
S.
No. Particulars
Tariff (`/kWh) if
AD benefit is
not availed
Tariff (`/kWh) if
AD benefit is
availed
1 2 3 4
1 Solar Photo Voltaic (PV) Power
Plants commissioned by 31.3.2014
9.63 8.42
2 Solar Thermal Power Plants
commissioned by 31.3.2015
11.95 10.45
3 Roof Top Solar PV installations and
other small solar PV power
generation plants covered in
MNRE’s scheme or Rajasthan Solar
Energy Policy to be commissioned
by 31.3.2014
9.63 8.42
4 Small Solar Thermal Power
generation plants covered in
MNRE’s scheme or Rajasthan Solar
Energy Policy to be commissioned
by 31.03.2015
11.95 10.45
53. Considering that considerable capacity of the solar projects
already stands commissioned in the State as against virtually nil
capacity upto 25.05.2010 when the earlier solar tariff order was
issued, the Distribution licensees, in the interest of the consumers,
must strive to procure solar energy at a generic tariff being lower
of the two streams namely, with or without AD benefit by giving
preference, while finalising/signing PPA, to developers/generators
offering the lower rate among the said two tariff streams. However,
if capacity in excess of RPO is to be contracted, the licensee must
obtain prior approval of the Commission based on reasons and full
justification before contracting for capacity in excess of RPO
requirement.
54. The tariff for roof top solar installations and other small solar systems
is inclusive of the incentive/subsidy component to be received by
the purchasing utility/distribution licensee from Govt. of India.
Capital subsidy, from GoI or other sources, received by the roof
top solar developer / installer, shall be passed on to the consumer
/ owner of the roof top solar installation.
Page 21 of 23
55. A generator claiming the higher tariff worked out for projects
without AD benefit would have to furnish an undertaking in
advance to the buyer regarding AD benefit not being availed
and this would have to be followed for each financial year by a
certificate of the Chief Executive or the person responsible for filing
Income Tax return of the generating unit to the effect that AD
benefit has not been claimed/availed in that financial year.
56. The benefit availed by the solar project developer under the clean
development mechanism shall be shared between the distribution
licensee and project developer in the ratio of 25:75 as provided
under the regulation 42 of RERC Tariff Regulations, 2009.
57. This is also to clarify that the project developer to the extent of
capacity contracted by signing PPA with distribution licensee
would not be availing benefit of REC and such an undertaking
would be incorporated in PPA.
58. As regards grid connectivity charges, this is to state that charges
would be governed as per Regulation 89(2) of current MYT
Regulations. Connectivity charges for capacity exceeding 50 MW
are payable @ 2.00 lac/MW whereas no charges are payable
upto 50 MW. Since the Regulations are valid upto FY 13-14, any
separate order for this period is neither required nor would be
effective to the extent of its variance with the Regulations. When
the earlier order dated 25.5.2010 was issued, not a single MW scale
project had been commissioned in the State. However, the
situation has undergone sea change in past two years after
success of bidding conducted by NVVN under National Solar
Mission. The observation of the Commission in the earlier order
dated 25.5.2010 comes in conflict with the said Regulation once
total installed capacity in the State exceeds 50 MW and
Page 22 of 23
connectivity charges as per Regulation are payable for capacity
getting commissioned beyond the said limit of 50 MW.
59. The metering shall be at the generator premises as provided in
CEA Metering Regulations. However, in case where the injection of
power to the grid is agreed to be at the premises/ (substation) of
the licensee, then tariff shall be calculated after considering losses
and wheeling charges in line with Regulation 83(6)(b) of RERC
Tariff Regulations, 2009.
60. Copy of this order be sent to the State Government, Central
Electricity Authority (CEA), MNRE , RREC, Distribution Licensees,
stakeholders and be also placed on the Commission’s website
(S. Dhawan)
Member
(S.K. Mittal)
Member
(D.C. Samant)
Chairman
Page 23 of 23
List of Participants in the Public Hearing on 13.03.2012
S. No Name Designation Organisation
1 D.S. Agarwal Consultant Rudraksh Energy
2 V K Gupta Consultant Rudraksh Energy
3 J K Agarwal Consultant SSAEL
4 Aditya Jandhyala Consultant SSAEL
5 Anil Patni Project Manager RREC
6 K K Purohit SE(Commercial) JVVNL
Annexure-I
TARIFF DETERMINATION FOR SOLAR PHOTO VOLTAIC POWER PLANTS LOCATED IN RAJASTHAN
Levelised Tariff (Rs/kWh) without AD 9.63
Accelerated Depreciation benefit(Rs/kWh) 1.21
Levelised Tariff (Rs/kWh) with AD 8.42
S. No.Assumption
HeadSub-Head Sub-Head (2) Unit
Base Case
(SPV)
1 Power Generation
Capacity
Installed Power Generation Capacity MW 1
CUF % 20.00%
Deration p.a. after 2nd year % 0.50%
Auxiliary Consumption % 0.25%
Tariff Period Years 25
Life of Power Plant Years 25
2 Project Cost
Capital Cost/MW Including Land & Connectivity charges Rs Lacs/MW 940Project Cost Power Plant Cost Rs Lacs 940
3 Sources of Fund
Debt: Equity
Debt % 70.00%
Equity % 30.00%
Total Debt Amount Rs Lacs 658
Total Equity Amout Rs Lacs 282
Funding Options-1 (Domestic Loan Source-1)
Loan Amount Rs Lacs 658
Moratorium Period years 0
Repayment Period(incld Moratorium) years 12
Intrest Rate % 12.30%
Funding Options-2 ( Equity Finance )
Equity amount Rs Lacs 282
Return on Equity for first 10 yrs % p.a 16.00%
Return on Equity from 11th yr onwards % p.a 16.00%
Discount Rate (equiv. to WACC) 13.41%
4 Financial Assumptions
Fiscal Assumptions
Income Tax % 30.90%
MAT Rate (for yr-1) % 20.01%MAT Rate (for yr-2 ) % 19.06%
MAT Rate (for yr-2 to yr-10) 19.06%
80 IA benefits Yes/No Yes
Depreciation
Depreciation Rate(upto 12-yrs) % 5.28%
Depreciation Rate(after 12-yrs) % 2.05%
Years for 5.28% SLM rate years 12
5 Working Capital
For Fixed Charges
O&M Charges Months 1
Maintenance Spare (% of O&M expenses) 15.00%
Receivables for Debtors Months 1.5
Intrest On Working Capital % 11.80%
6 Operation & Maintenance
power plant Rs Lacs per MW Rs Lacs 11.00
Insurance % of depreciated capital cost % 0.30%
Total O & M Expenses Escalation % 5.72%No. of Days Days 365
Total No. of Hours Hrs 8760
Annexure-II
TARIFF DETERMINATION FOR SOLAR PHOTO VOLTAIC POWER PLANTS LOCATED IN RAJASTHAN
Units Generation Unit Year---> 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25
Aux Consumption % 0.25% 0.25% 0.25% 0.25% 0.25% 0.25% 0.25% 0.25% 0.25% 0.25% 0.25% 0.25% 0.25% 0.25% 0.25% 0.25% 0.25% 0.25% 0.25% 0.25% 0.25% 0.25% 0.25% 0.25% 0.25%
Installed Capacity MW 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Deration factor % 0.50% 1 1.000 0.995 0.990 0.985 0.980 0.975 0.970 0.966 0.961 0.956 0.951 0.946 0.942 0.937 0.932 0.928 0.923 0.918 0.914 0.909 0.905 0.900 0.896 0.891
Generation MU 1.75 1.75 1.74 1.73 1.72 1.71 1.70 1.70 1.69 1.68 1.67 1.66 1.65 1.65 1.64 1.63 1.62 1.61 1.60 1.60 1.59 1.58 1.57 1.57 1.56
Cost of generation Unit Year---> 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25
O&M Expenses Rs Lacs 13.82 14.30 14.82 15.37 15.97 16.60 17.28 18.01 18.79 19.63 20.52 21.46 22.48 23.64 24.88 26.20 27.59 29.06 30.62 32.28 34.03 35.89 37.85 39.93 42.14
Depreciation Rs Lacs 49.63 49.63 49.63 49.63 49.63 49.63 49.63 49.63 49.63 49.63 49.63 49.63 19.26 19.26 19.26 19.26 19.26 19.26 19.26 19.26 19.26 19.26 19.26 19.26 19.26
Interest on term loan Rs Lacs 77.56 70.82 64.07 57.33 50.58 43.84 37.09 30.35 23.61 16.86 10.12 3.37 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Interest on working Capital Rs Lacs 3.26 3.18 3.10 3.03 2.96 2.89 2.82 2.76 2.69 2.63 2.72 2.66 2.20 2.25 2.31 2.37 2.43 2.49 2.56 2.63 2.71 2.79 2.88 2.97 3.06
Return on Equity Rs Lacs 56.41 55.74 55.74 55.74 55.74 55.74 55.74 55.74 55.74 55.74 65.30 65.30 65.30 65.30 65.30 65.30 65.30 65.30 65.30 65.30 65.30 65.30 65.30 65.30 65.30
Total Cost of generation Rs Lacs 200.68 193.67 187.37 181.10 174.88 168.70 162.57 156.49 150.47 144.49 148.28 142.42 109.24 110.46 111.75 113.12 114.57 116.11 117.74 119.47 121.30 123.24 125.29 127.46 129.76
Per unit Cost of generation Rs/kWh 11.48 11.08 10.78 10.47 10.16 9.85 9.54 9.23 8.92 8.61 8.88 8.57 6.60 6.71 6.83 6.94 7.07 7.20 7.34 7.48 7.63 7.80 7.97 8.14 8.33
200.68 193.67 187.37 181.10 174.88 168.70 162.57 156.49 150.47 144.49 148.28 142.42 109.24 110.46 111.75 113.12 114.57 116.11 117.74 119.47 121.30 123.24 125.29 127.46 129.76
Levellised cost of generation (Rs/kWh) (25 yrs) 9.63
Annexure-II…contd…
Determination of Accelerated Depreciation Benefit for Solar PV Power Projects
Depreciation amount 90%
Book Depreciation rate 5.28%
Tax Depreciation rate 80%
Income Tax 32.45% 30.90% Yr-2 onwards
Capital Cost 940.0 Rs Lacs/MW
Years -----------------> Unit 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25
Book Depreciation % 2.64% 5.28% 5.28% 5.28% 5.28% 5.28% 5.28% 5.28% 5.28% 5.28% 5.28% 5.28% 5.28% 5.28% 5.28% 5.28% 5.28% 2.88% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
Book Depreciation Rs Lacs 24.82 49.63 49.63 49.63 49.63 49.63 49.63 49.63 49.63 49.63 49.63 49.63 49.63 49.63 49.63 49.63 49.63 27.07 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Accelerated Depreciation
Opening % 100.00% 60.00% 12.00% 2.40% 0.48% 0.10% 0.02% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
Allowed during the year % 40% 48.00% 9.60% 1.92% 0.38% 0.08% 0.02% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
Closing % 60% 12% 2.40% 0.48% 0.10% 0.02% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
Accelrated Deprn. Rs Lacs 376.00 451.20 90.24 18.05 3.61 0.72 0.14 0.03 0.01 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Net Depreciation Benefit Rs Lacs 351.18 401.57 40.61 -31.58 -46.02 -48.91 -49.49 -49.60 -49.63 -49.63 -49.63 -49.63 -49.63 -49.63 -49.63 -49.63 -49.63 -27.07 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Tax Benefit Rs Lacs 113.94 124.08 12.55 -9.76 -14.22 -15.11 -15.29 -15.33 -15.33 -15.34 -15.34 -15.34 -15.34 -15.34 -15.34 -15.34 -15.34 -8.37 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Energy generation MU 0.87 1.75 1.74 1.73 1.72 1.71 1.70 1.70 1.69 1.68 1.67 1.66 1.65 1.65 1.64 1.63 1.62 1.61 1.60 1.60 1.59 1.58 1.57 1.57 1.56
Per unit benefit Rs/Unit 13.04 7.10 0.72 (0.56) (0.83) (0.88) (0.90) (0.90) (0.91) (0.91) (0.92) (0.92) (0.93) (0.93) (0.94) (0.94) (0.95) (0.52) 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Discounting Factor,DF 1.00 0.88 0.78 0.69 0.60 0.53 0.47 0.41 0.37 0.32 0.28 0.25 0.22 0.19 0.17 0.15 0.13 0.12 0.10 0.09 0.08 0.07 0.06 0.06 0.05
Applicable DF 1.00 0.94 0.83 0.73 0.65 0.57 0.50 0.44 0.39 0.34 0.30 0.27 0.24 0.21 0.18 0.16 0.14 0.13 0.11 0.10 0.09 0.08 0.07 0.06 0.05
Levellised benefit 1.21 Rs/kWh
Annexure-II…contd…
TARIFF DETERMINATION FOR SOLAR THERMAL POWER PLANTS LOCATED IN RAJASTHAN
Levelised Tariff (Rs/kWh) without AD 11.95
Accelerated Depreciation benefit (Rs/kWh) 1.50
Levelised Tariff (Rs/kWh) with AD 10.45
S. No.Assumption
HeadSub-Head Sub-Head (2) Unit
Base
Case
(CSP)
1 Power Generation
Capacity
Installed Power Generation Capacity MW 1
CUF % 23.00%
Deration p.a. after 4th year % 0.25%
Auxiliary Consumption % 6.50%
Tariff Period Years 25
Life of Power Plant Years 25
2 Project Cost
Capital Cost/MW Including Land & Connectivity charges Rs Lacs/MW 1275
3 Sources of Fund
Debt: Equity
Debt % 70.00%
Equity % 30.00%
Total Debt Amount Rs Lacs 892.5
Total Equity Amout Rs Lacs 382.5
Funding Options-1 (Domestic Loan Source-1)
Loan Amount Rs Lacs 892.5
Moratorium Period years 0
Repayment Period(incld Moratorium) years 12
Interest Rate % 12.30%
Funding Options-2 ( Equity Finance )
Equity amount Rs Lacs 382.5
Return on Equity for first 10 yrs % p.a 16.00%
Return on Equity from 11th yr onwards % p.a 16.00%
Discount Rate (equiv. to WACC) 13.41%
4 Financial Assumptions
Fiscal Assumptions
Income Tax % 30.90%
MAT Rate (for yr-1) % 20.01%
MAT Rate (for yr-2 to yr-10) % 19.06%
80 IA benefits Yes/No Yes
Depreciation
Depreciation Rate(upto 12-yrs) % 5.28%
Depreciation Rate(after 12-yrs) % 2.05%
Years for 5.28% SLM rate 12
5 Working Capital
For Fixed Charges
O&M Charges Months 1
Maintenance Spare (% of O&M expenses) 15.00%
Receivables for Debtors Months 1.5
Interest On Working Capital % 11.80%
6 Operation & Maintenance
power plant Rs lakhs per MW Rs Lakhs 15.00
Insurance % of depreciated capital cost % 0.30%
Total O & M Expenses Escalation % 5.72%
Final Order - Solar Tariff
Annexure - III
TARIFF DETERMINATION FOR SOLAR THERMAL POWER PLANTS LOCATED IN RAJASTHAN Annexure-III contd…
Units Generation Unit Year---> 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25
Aux Consumption % 6.5% 6.5% 6.5% 6.5% 6.5% 6.5% 6.5% 6.5% 6.5% 6.5% 6.5% 6.5% 6.50% 6.50% 6.50% 6.50% 6.50% 6.50% 6.50% 6.50% 6.50% 6.50% 6.50% 6.50% 6.50%
Deration factor % 1.000 1.000 1.000 1.000 0.998 0.995 0.993 0.990 0.988 0.985 0.983 0.980 0.978 0.975 0.973 0.970 0.968 0.966 0.963 0.961 0.958 0.956 0.954 0.951 0.949
Installed Capacity MW 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Generation MU 1.884 1.884 1.884 1.884 1.879 1.874 1.870 1.865 1.860 1.856 1.851 1.846 1.842 1.837 1.833 1.828 1.824 1.819 1.814 1.810 1.81 1.80 1.80 1.79 1.79
Cost of generation Unit Year---> 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25
O&M Expenses Rs Lakh 18.83 19.48 20.19 20.94 21.76 22.62 23.56 24.55 25.62 26.75 27.97 29.26 30.64 32.24 33.93 35.72 37.61 39.63 41.76 44.01 46.40 48.93 51.62 54.45 57.46
Depreciation Rs Lakh 67.32 67.32 67.32 67.32 67.32 67.32 67.32 67.32 67.32 67.32 67.32 67.32 26.13 26.13 26.13 26.13 26.13 26.13 26.13 26.13 26.13 26.13 26.13 26.13 26.13
Interest on term loan Rs Lakh 105.20 96.06 86.91 77.76 68.61 59.46 50.31 41.17 32.02 22.87 13.72 4.57 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Interest on working Capital Rs Lakh 4.43 4.31 4.21 4.11 4.02 3.92 3.83 3.74 3.66 3.57 3.69 3.61 2.99 3.06 3.14 3.22 3.30 3.39 3.48 3.58 3.69 3.80 3.91 4.04 4.17
Return on Equity Rs Lakh 76.51 75.61 75.61 75.61 75.61 75.61 75.61 75.61 75.61 75.61 88.57 88.57 88.57 88.57 88.57 88.57 88.57 88.57 88.57 88.57 88.57 88.57 88.57 88.57 88.57
Total Cost of generation Rs Lakh 272.29 262.78 254.23 245.74 237.31 228.94 220.63 212.39 204.22 196.12 201.27 193.34 148.33 149.99 151.76 153.63 155.61 157.71 159.93 162.29 164.78 167.43 170.23 173.19 176.32
Per unit Cost of generation Rs/kWh 14.45 13.95 13.50 13.04 12.63 12.21 11.80 11.39 10.98 10.57 10.87 10.47 8.05 8.16 8.28 8.40 8.53 8.67 8.81 8.97 9.13 9.30 9.48 9.67 9.87
Levellised Tariff (Rs/kWh) (25 yrs) 11.95
Determination of Accelerated Depreciation Benefit for Solar Thermal Power Projects
Depreciation amount 90% Annexure-III contd…
Book Depreciation rate 5.28%
Tax Depreciation rate 80%
Income Tax 32.45% 30.90%
Capital Cost 1275.0 Rs Lacs/MW
Years -----------------> Unit 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25
Book Depreciation % 2.64% 5.28% 5.28% 5.28% 5.28% 5.28% 5.28% 5.28% 5.28% 5.28% 5.28% 5.28% 5.28% 5.28% 5.28% 5.28% 5.28% 2.88% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
Book Depreciation Rs Lacs 33.66 67.32 67.32 67.32 67.32 67.32 67.32 67.32 67.32 67.32 67.32 67.32 67.32 67.32 67.32 67.32 67.32 36.72 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Accelerated Depreciation
Opening % 100.00% 60.00% 12.00% 2.40% 0.48% 0.10% 0.02% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
Allowed during the year % 40% 48.00% 9.60% 1.92% 0.38% 0.08% 0.02% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
Closing % 60% 12% 2.40% 0.48% 0.10% 0.02% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
Accelrated Deprn. Rs Lacs 510.00 612.00 122.40 24.48 4.90 0.98 0.20 0.04 0.01 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Net Depreciation Benefit Rs Lacs 476.34 544.68 55.08 -42.84 -62.42 -66.34 -67.12 -67.28 -67.31 -67.32 -67.32 -67.32 -67.32 -67.32 -67.32 -67.32 -67.32 -36.72 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Tax Benefit Rs Lacs 154.55 168.31 17.02 -13.24 -19.29 -20.50 -20.74 -20.79 -20.80 -20.80 -20.80 -20.80 -20.80 -20.80 -20.80 -20.80 -20.80 -11.35 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Energy generation MU 0.94 1.88 1.88 1.88 1.88 1.87 1.87 1.87 1.86 1.86 1.85 1.85 1.84 1.84 1.83 1.83 1.82 1.82 1.81 1.81 1.81 1.80 1.80 1.79 1.79
Per unit benefit Rs/Unit 16.41 8.93 0.90 (0.70) (1.03) (1.09) (1.11) (1.11) (1.12) (1.12) (1.12) (1.13) (1.13) (1.13) (1.14) (1.14) (1.14) (0.62) 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Discounting Factor,DF 1.00 0.88 0.78 0.69 0.60 0.53 0.47 0.41 0.37 0.32 0.28 0.25 0.22 0.19 0.17 0.15 0.13 0.12 0.10 0.09 0.08 0.07 0.06 0.06 0.05
Applicable DF 1.00 0.94 0.83 0.73 0.65 0.57 0.50 0.44 0.39 0.34 0.30 0.27 0.24 0.21 0.18 0.16 0.14 0.13 0.11 0.10 0.09 0.08 0.07 0.06 0.05
Levellised benefit 1.50 Rs/kWh