Engineering and Technical Feasibility Study for Proposed ...
pre-feasibility report for proposed pesticide technical and ...
-
Upload
khangminh22 -
Category
Documents
-
view
3 -
download
0
Transcript of pre-feasibility report for proposed pesticide technical and ...
1
PRE-FEASIBILITY REPORT
FOR
PROPOSED PESTICIDE TECHNICAL AND
SPECIALTY CHEMICALS
Of
M/s. H M INDUSTRIES
Plot No. A2/2115,
Phase-III, G.I.D.C., Vapi-396 195,
Di: Valsad, State: Gujarat
2
CONTENTS
Sr. No. Description Page No.
1. Executive Summary 3
2. Introduction of the Project/Background information 7
3. Project Description 9
4. Site Analysis 15
5. Planning Brief 18
6. Proposed Infrastructure 19
7. Rehabilitation and resettlement (R & R) Plan 22
8. Project Schedule & Cost Estimates 22
9. Analysis of Proposal (Final Recommendations) 23
3
1.0 EXECUTIVE SUMMARY 1.1 Company Profile
M/s. H M Industries proposes pesticide technical and specialty chemicals at plot No.
A2/2115, Phase-III, GIDC Vapi, Dist: Valsad, Gujarat.
1.2 Project Details
No. PRODUCTS CAS No. QTY
MT/MONTH End Use
LD50 (mg/Kg)
Group I: FUNGICIDE
100
1 Hexaconazole 79983-71-4
Crop care
Chemical of Fungicide
Category with varied
application
6071 2 Tebuconazole 107534-96-3 1700 3 Tricyclazole 41814-78-2 2000 4 Metalaxyl 57837-19-1 3100 5 Thiophenate Methyl 23564-05-8 5000 6 Azoxystrobin 131860-33-8 2000 7 Picoxystrobin 117428-22-5 5000 8 Trifloxystrobin 141517-21-7 5000 GROUP II - HERBICIDE
100
9 2,4 D Sodium / 2,4 D Acid/ 2,4 D Amine/2,4 D Ester Crop care
Chemical of Herbicide Category with varied application
1500
2,4 D Sodium 7084-86-8 2,4 D Acid 94-75-7 2,4 D Amine 2008-39-1 2,4 Ester 533-23-3
10 Atrazine 1912-24-9 2200 11 Metribuzin 21087-64-9 1100 12 Pretilachlor 51218-49-6 2200 GROUP III - INSECTICIDE
100
13 Acetamiprid 135410-20-7 Crop care
Chemical of Insecticide
Category with varied
application
2000 14 Imidacloprid 138261-41-3 5000 15 Thiamethoxam 153719-23-4 1563 16 Bifenthrin 82657-04-3 2000 17 Cypermethrin 52315-07-8 1600 18 Permethrin 52645-53-1 2000
GROUP IV - SPEACILTY CHEM
100
19 Triethylbenzylammonium chloride (TEBA) 56-37-1
Phase Transfer Catalyst
2219
TOTAL OF PRODUCTS 400
4
1.3 Green Belt Development
M/s. H M Industries has develop an effective green belt within the factory and on periphery
of the factory. In addition to this, majority of the vacant land is planted with trees, shrubs
and grasses.
1.4 Power & Fuel Requirement
Power requirement:
Proposed: 90 KVA 1 DG Set – 125 KVA (In case of Emergency) Fuel requirement: Proposed: Natural gas @ 150 SCM/Hour Diesel @ 20 lit/Hour.
1.5 Water Requirement and Wastewater Generation & Treatment
Total water requirement – 91.5 m3/day will be met through GIDC, Vapi. Total
wastewater generation will be 57.13 m3/day. The Low COD effluent (9.8 m3/day) shall be
treated in proposed effluent treatment plant consisting of primary treatment and
secondary treatment & send it to CETP for treatment and disposal.
The High COD & High TDS-effluent (42.33 m3/day) shall be treated in proposed effluent
treatment plant consisting of primary treatment and then evaporate in MEE and MEE
Condensate will be reused in plant premises.
Domestic Effluent (5.0 m3/day) is disposed through septic tank & soak pit.
1.6 Air Pollution Source and Control Management
The company will install one steam boiler of 2000 kg/hr, D G Set and 5 Nos. of process gas
emission. Company will install the Scrubber system to control process gas emission.
Natural Gas will be used as fuel in proposed utilities. Diesel will be used as fuel in D.G.Set.
5
1.7 Hazardous Waste Management
Hazardous wastes generated are in the form of ETP sludge, spent solvent, iron sludge,
organic residue, process waste, inorganic salts, spent carbon and discarded containers.
Company has provided adequate storage area for proper storage of wastes.
No. Name of waste Category Qty /
Month Unit Mode of Disposal
1 Used/Spent oil 5.1 25 Liters Reused for Machine Lubrication / Given to GPCB registered reprocessor
2 Used Filters/Filter Cloths & Materials
… 50 KG
Collection, Storage transportation for co-processing in cement industry or incineration in common incineration facility.
3 Used Hy-Flow Material … 100 KG
4 Solvent Distillation Residue
20.3 1 MT
5 Process Residue 29.1 2 MT
6 Expired Pesticides 29.3 What So
Ever Generates
KG
7 Spent Solvent 29.4 20 MT
Collection, Storage, recovery within premises or recovery at outside facility or transportation & disposal by co-processing in cement industry or sent to common incineration facility.
8 Residual Salts from MEE / Sludge from ETP
35.3 200 MT To Landfill at TSDF
9 Sludge from Scrubbers 37.1 0.1 MT To Landfill at TSDF 10 Used Containers Drums 33.1 500 Nos. Sold to GPCB authorized dealer
after decontamination Bags and Liners 33.1 5000 Nos. 11 Potassium Sulfate … 900 MT
Collection, Storage and sell to end user/s having permission of Rule-9.
12 Hydrochloric Acid Solution
… 190 MT
13 Sodium Sulfite Solution … 162 MT
6
INTRODUCTION OF THE PROJECT/BACKGROUND INFORMATION 2.1 Identification of the project and project proponent. In case of mining project, a copy
of mining lease/letter of intent should be given.
Identification of the project
Proposed pesticide technical and specialty Chemical manufacturing unit
Identification of the project proponent
No. Name Designation Qualification Contact Details 1 K N Madhukurup Partner DEE 28 / A, Aavishkar Co-Operative
Society, Near Sardar Park, GIDC, Ankleshwar 393 002 Mobile: +91 9662539447
2 Omankuttan R Pillai
Partner DEE B/203, Sunbright Apartment, Charwada Road, Vapi 396 191 Mobile: +91 9662539449
2.2 Brief description of nature of the Project
The proposed project involves the production of pesticide technical and specialty Chemical
which falls under item no 5(b) i.e. pesticide technical and pesticide intermediates as per the
EIA notification, Sept. 14, 2006 (as amended time to time), it is to be treated as Category 'A',
and needs to obtain the prior Environmental Clearance from MoEFCC, New Delhi.
2.3 Need for the project and its importance to the country and or region
The proposed products range having good demand in the Market & as per market survey by
the company there is a less supply of the products against its demand, to overcome this
shortage & to bridge demand-supply gap, the company proposed to have this expansion.
2.4 Demand-Supply Gap
Based on our informal survey of the market with our current customers and various
traders, we have found that there is a big potential for the range of the products we are
planning. These products are versatile products as far as pesticide application is concerned.
7
2.5 Imports vs. Indigenous production
Based on the current cost of indigenous raw materials, it will make us very competitive
against imported finished products and we will be able to increase the export of our
finished products.
2.6 Export possibility
As per market survey by the company, these proposed products are having a domestic as
well as export market due to its application in various types of Printing Inks, Coatings &
Adhesives Industries.
2.7 Domestic/Export Markets
According to the global perception, there is very good possibility of export of the products.
2.8 Employment Generation (Direct and Indirect) due to project.
Employment would be as per prevailing norms of state government for skilled and unskilled
people (30 Nos.) for the proposed expansion project.
3.0 Project Description
3.1 Type of Project including interlinked and interdependent projects, if any.
Proposed pesticide technical and specialty chemical manufacturing unit
Category: 'A'-5(b).
8
3.2 Location (map showing general location, specific location and project boundary &
project site layout) with coordinates.
Map showing general location
11
3.3 Details of alternate sites considered and the basis of selecting the proposed site,
particularly the environmental considerations gone into should be highlighted.
Major factors involved in the selection of site are listed below:
Site is very well connected by road
Proximity to Raw Material suppliers
Availability of sufficient land free from cultivation
Availability of power evacuation facilities
Availability of abundant water for industrial use
Modern infrastructure support and amenities at par with industrial estates in other global
markets, including:
Efficient transport facilities within the industrial estate.
Environment-friendly zone.
Uninterrupted power supply.
3.4 Size or Magnitude of Operation
Please refer section 1.2 of PFR.
3.5 Project Description with process details (a schematic diagram/flow chart showing the
project layout, components of the project etc. should be given)
Please refer Annexure-III in Form-I.
3.6 Raw material required along with estimated quantity, likely source, marketing area of
final products. Mode of transport of raw materials and finished products.
Please refer Annexure-II in Form-I.
3.7 Resource optimization/recycling and reuse envisaged in the project, if any, should be
briefly outlined.
There will not resource optimization/recycling and reuse envisaged in the proposed project.
12
3.8 Availability of water its source, energy/power requirement and source should be
given.
Water Source
Quantity of water consumption will be 91.5 KL/Day. The entire water requirement will be
met through GIDC Water Supply.
Power & Fuel Requirement
Power requirement: Proposed: 90 KVA 1 DG Set – 125 KVA (In case of Emergency) Fuel requirement: Proposed: Natural gas @ 75 SCM/Hour Diesel @ 20 lit/hr.
3.9 Quantity of wastes to be generated (liquid and solid) and scheme for their
management/disposal.
Total water requirement – 91.5 m3/day will be met through GIDC, Vapi. Total
wastewater generation will be 57.13 m3/day. The Low COD effluent (9.8 m3/day) shall be
treated in proposed effluent treatment plant consisting of primary treatment and send it
to CETP for treatment and disposal.
The High COD & High TDS-effluent (42.33 m3/day) shall be treated in proposed effluent
treatment plant consisting of primary treatment and then evaporate in MEE and MEE
Condensate will be reused in plant premises.
Domestic Effluent (5.0 m3/day) is disposed through septic tank & soak pit.
13
3.10 Schematic representations of the feasibility drawing which give information of EIA
purpose.
RECONNAISSANCE SURVEY OF EXISTING PLANT ANNUAL REPORT MARKET ASSESSMENT FINANCIAL REPORT PROJECT REPORT
INTRODUCTION
MONITORING OF AIR, WATER & SOIL QUALITY & NOISE LEVELS. DATA ON METEOROLOGY SOCIO-ECONOMIC STATUS & BASIC AMENITIES. SITE VISITS BY AND INTERVIEWS WITH LOCALS
BASELINE ENVIRONMENTAL
STATUS
ENVIRONMENTAL INFORMATION CENTRE CENTRAL GROUND WATER BOARD GUJARAT POLLUTION CONTROL BOARD (GPCB) PUBLIC HEALTH ENGINEERING DEPT. AGRICULTURE DEPARTMENT FOREST DEPARTMENT IRRIGATION DEPARTMENT EMPLOYMENT EXCHANGE HEALTH CENTER CENSUS DEPT. INDIAN METEOROLOGICAL DEPT.
SOCIOECONOMIC STATUS &
INFRASTRUCTURE
PROPOSED PLANT
FACILITY DESCRIPTION
IMPACTS METHODOLOGY OF
IMPACT ASSESSMENT
IDENTIFICATION & ASSESSMENT OF IMPACTS EVALUATION OF IMPACTS BY MATRIX METHOD
SOURCE OF INFORMATION OVERVIEW OF E. I. A. STUDIES
ACTIVITIES
ENVIRONMENTAL MANAGEMENT PLAN
DESCRIPTION OF EFFLUENT TREATMENT PLAN, AIR POLLUTION CONTROL, HAZARDOUS WASTE MANAGEMENT, GREEN BELT DEVELOPMENT MONITORING PROGRAM
RISK ANALYSIS STUDIES & DISASTER
MANAGEMENT PLAN
SAFETY, HEALTH & ENVIRONMENTAL POLICY, GUIDELINES BY DIRECTOR GENERAL OF FACTORY SAFETY, MINISTRY OF LABOR. CONSEQUENCE ANALYSIS
PREPARATION OF DISASTER MANAGEMENT PLAN
14
4.0 Site Analysis
4.1 Connectivity
Site is very well connected by road
Availability of power evacuation facilities
Availability of abundant water for industrial use
4.2 Land Form, Land Use and Land Ownership
16
4.4 Existing land use pattern (agriculture, non-agriculture, forest, water bodies (including
area under CRZ)), shortest distances from the periphery of the project to periphery of the
forests, national park, wild life sanctuary, eco sensitive areas, water bodies (distance from
HFL of the river), CRZ. In case of the notified industrial area, a copy of the Gazette
notification should be given.
CRZ Clearance is not applicable to our industry.
17
4.5 Existing Infrastructure
Major factors involved in the selection of site are listed below:
Site is very well connected by road
Proximity to Raw Material suppliers
Availability of sufficient land free form cultivation
Availability of power evacuation facilities
4.6 Soil Classification
It will be incorporated in EIA Studies.
4.7 Climatic data from secondary sources. Primary source: our own weather station & Secondary Source: Indian Meteorological
Department.
4.8 Social infrastructure available.
Depending on the growth of the company the required social infrastructure will be
provided.
5.0 Planning Brief
5.1 Planning Concept (type of industries, facilities, transportation etc) Town and Country
planning/Development authority classification.
Type of Industry: Proposed pesticide technical and pesticide intermediates manufacturing
unit
5.2 Population Projection
It will be incorporated in EIA Studies.
5.3 Land use planning (breakup along with green belt etc.)
Total Plot Area: 1809 m2
18
5.4 Assessment of Infrastructure Demand (Physical & Social)
Employment would be as per prevailing norms of state government for skilled and unskilled people for the proposed expansion project.
Social Welfare
Cordial relation with the industry shall be established and representation shall be made to villagers for help for creation of facilities related to health, education, etc.
5.5 Amenities/Facilities
It will be incorporated in EIA Studies.
6.0 Proposed Infrastructure
6.1 Industrial Area (Processing Area)
Processing Area (Processing Zone, ETP Area and Utility Area): 786 m2
6.2 Residential Area (Non Processing Area)
Non Processing Area (Green belt, Raw material storage area, finished storage area and open
area): 1000 m2
6.3 Green Belt
M/s. H M Industries has developed an effective green belt within the factory and on
periphery of the factory. In addition to this, majority of the vacant land is planted with
trees, shrubs and grasses.
6.4 Social Infrastructure
Depending on the growth of the company the required social infrastructure will be
provided.
6.5 Connectivity (Traffic and Transportation Road/ Rail/Metro/ Water ways etc)
Major factors involved in the selection of site are listed below:
Site is very well connected by road
Proximity to Raw Material suppliers
Availability of sufficient land free from cultivation
19
Availability of power evacuation facilities
Availability of abundant water for industrial use
6.6 Drinking water Management (Source & Supply of water)
Water requirement will meet through GIDC Water Supply.
6.7 Sewerage System
Sewage pipes are laid in entire company for the removal and disposal of mainly non-
harmful liquid wastes from the offices, canteen and domestic waste coming from different
sections. These liquid wastes are treated and disposed of by septic tank & soak pit.
6.8 Solid Waste Management
Details of Hazardous Waste Generation & Disposal Please refer Topic No. 1.7 on Page no. 5. 6.9 Power Requirement & Supply/Source
Power requirement:
Power requirement: Proposed: 90 KVA 1 DG Set – 125 KVA (In case of Emergency) Fuel requirement: Proposed: Natural gas @ 75 SCM/Hour Diesel @ 20 lit/Hour.
7.0 Rehabilitation and Resettlement (R & R) Plan
7.1 Policy to be adopted (central/state) in respect of the project affected including home
oustees, land ouatees and landless laborers (a brief outline to be given)
There is no habitation on the proposed e project area, so that R & R policy is not applicable
to this project.
There shall be no displacement of any population in the project area. Any major activity that
may lead to resettlement of the people is considered as permanent impact. Hence, there is
no permanent impact on this account. The increasing industrial activity will boost the
commercial and economical status of the locality up to some extent.
20
8. Project Schedule & Cost Estimates
8.1 Likely date of start of construction and likely date of completion (Time schedule for
the project to be given).
Project can be implemented in 9 months after obtaining EC & CTE.
8.2 Estimated Project cost along with analysis in terms of economic viability of the
project.
Total costs of the project will Rs. 7.50 Crore. Capital cost of air & water pollution control
system and environmental monitoring equipments will be Rs. 1.5 Crore .
9. Analysis of Proposal (Final Recommendations)
9.1 Financial and social benefits with special emphasis on the benefit to be local people
including tribal population, if any, in the area.
Employment would be as per prevailing norms of state government for skilled and unskilled people for the proposed project.
Social Welfare shall be done.
Cordial relation with the industry shall be established and representation shall be made
to villagers for help for creation of facilities related to health, education, etc.