œ涪 #376; 桨 ˆ脚 ‹ #8217;ˆ鸥娇 ˆ批 粛跟

75

Transcript of œ涪 #376; 桨 ˆ脚 ‹ #8217;ˆ鸥娇 ˆ批 粛跟

œ¸¢©�¸Ÿ¸ ®¸½°¸ ˆ½Å ‹¸’ˆÅ¸½¿ ˆÅú ¬¸»�¸ú: 1. ‚š¡¸®¸, œ¸®¸½¢¨¸¬¸¢Ÿ¸¢÷¸ ‡¨¸¿ Š¸º�¸£¸¢¨¸¢›¸¢¥¸¢Ÿ¸, ¨¸”¸½™£¸ 2. ¬¸™¬¡¸ (¢ŠÏ œÏ¤¸¿ ‡¨¸¿ ¢¨¸÷¸), ˆ½Å¢¨¸œÏ¸, ›¸ƒÄ ¢™¥¥¸ú 3. œÏ¤¸¿š¸ ¢›¸™½©¸ˆÅ, Žî¸ú£¸¢¨¸œ¸¸£½ˆ¿Å¢¥¸¢Ÿ¸., £¸¡¸œ¸º£ 4. œÏ¤¸¿‹¸ ¢›¸™½©¸ˆÅ, Žî¸ú£¸¢¨¸¢¨¸÷¸ˆ¿Å¢¥¸¢Ÿ¸., £¸¡¸œ¸º£ 5. œÏ¤¸¿‹¸ ¢›¸™½©¸ˆÅ, Žî¸ú£¸¢¨¸„÷œ¸¸ˆ¿Å¢¥¸¢Ÿ¸., £¸¡¸œ¸º£ 6. Ÿ¸º‰¡¸ ‚¢ž¸¡¸¿÷¸¸ (ž¸¸.œÏ½.), Žî¸ú£¸¢¨¸œ¸¸£½ˆ¿Å¢¥¸¢Ÿ¸. ‰¸½”¸Ÿ¸¸£¸, ¢ž¸¥¸¸ƒÄ 7. œÏ¤¸¿š¸ ¢›¸™½©¸ˆÅ, Š¸½’ˆÅ¸½, ¨¸”¸½™£¸ 8. œÏ¤¸¿š¸ ¢›¸™½©¸ˆÅ, œ¸¢ä¸Ÿ¸ Š¸º�¸£¸÷¸ ¢¨¸�¸ ˆÅŸœ¸›¸ú ¢¥¸¢Ÿ¸., £¸�¸ˆÅ¸½’ 9. Ÿ¸º‰¡¸ ‚¢ž¸¡¸¿÷¸¸ (ž¸¸.œÏ½.), Š¸º�¸¢¨¸œ¸¸£½ˆÅŸœ¸›¸ú¢¥¸¢Ÿ¸., ¨¸”¸½™£¸ 10. ‚š¡¸®¸ ¨¸ œÏ¤¸¿š¸ ¢›¸™½©¸ˆÅÅ, Ÿ¸œÏ¢¨¸œ¸¸£½ˆÅŸœ¸›¸ú ¢¥¸¢Ÿ¸., �¸¤¸¥¸œ¸º£ 11. ‚š¡¸®¸ ¨¸ œÏ¤¸¿š¸ ¢›¸™½©¸ˆÅÅ, Ÿ¸œÏ¢¨¸„÷œ¸¸ˆÅŸœ¸›¸ú ¢¥¸¢Ÿ¸’½”, �¸¤¸¥¸œ¸º£ 12. ‚š¡¸®¸ ¨¸ œÏ¤¸¿š¸ ¢›¸™½©¸ˆÅÅ, œ¸¢©�¸Ÿ¸ ®¸½°¸ ¢¨¸Ô¸º÷¸ ¢¨¸÷¸£μ¸ ˆÅŸœ¸›¸ú ¢¥¸¢Ÿ¸., ƒ›™¸¾£ 13. ¢¨¸©¸½«¸ ˆÅ¸¡¸Ä ‚¢š¸ˆÅ¸£ú (ž¸¸£ œÏ½«¸μ¸), £¸ž¸¸œÏ½ˆ½Å›Í, Ÿ¸œÏ¢¨¸œ¸¸£½ˆ¿Å¢¥¸¢Ÿ¸., �¸¤¸¥¸œ¸º£ 14. œÏ¤¸¿š¸ ¢›¸™½©¸ˆÅÅ, Ÿ¸í¸£¸¢¨¸œ¸¸£½ˆ Ÿœ¸›¸ú ¢¥¸¢Ÿ¸., Ÿ¸º¿¤¸ƒÄ 15. œÏ¤¸¿š¸ ¢›¸™½©¸ˆÅ , Ÿ¸í¸£¸¢¨¸„÷œ¸¸ˆÅŸœ¸›¸ú ¢¥¸¢Ÿ¸., Ÿ¸º¿¤¸¿ƒÄ 16. œÏ¤¸¿š¸ ¢›¸™½©¸ˆÅ , Ÿ¸í¸£¸¢¨¸¢¨¸÷¸ˆÅŸœ¸›¸ú ¢¥¸¢Ÿ¸., Ÿ¸º¿¤¸¿ƒÄ 17. Ÿ¸º‰¡¸ ‚¢ž¸¡¸¿÷¸¸ (ž¸¸œÏ½), £¸ž¸¸œÏ½ˆ½Å›Í, Ÿ¸í¸£¸¢¨¸œ¸¸£½ˆ¿Å¢¥¸¢Ÿ¸., ˆÅ¥¸¨¸¸ 18. Ÿ¸º‰¡¸ ¢¨¸Ô¸º÷¸ ‚¢ž¸¡¸¿÷¸¸, ¢¨¸Ô¸º÷¸ ¢¨¸ž¸¸Š¸, Š¸¸½¨¸¸ 19. ¢›¸™½©¸ˆÅ (¨¸¸¢μ¸�¡¸), ‡›¸œ¸ú’ú¬¸ú ¢¥¸¢Ÿ¸., ›¸ƒÄ ¢™¥¥¸ú 20. ¢›¸™½©¸ˆÅ (œÏ�¸¸¥¸›¸), œ¸ú�¸ú¬¸ú‚¸ƒÄ‡¥¸, Š¸º”õŠ¸¸Â¨¸ 21. ¢›¸™½©¸ˆÅ (œÏ�¸¸¥¸›¸), ‡›¸œ¸ú¬¸ú‚¸ƒÄ‡¥¸, Ÿ¸º¿¤¸ƒÄ 22. ¬¸¢�¸¨¸ (¢¨¸Ô¸º÷¸), ¬¸¿‹¸ ©¸¸¢¬¸÷¸ ®¸½°¸ ™Ÿ¸›¸ ‡¨¸¿ ™ú¨¸, Ÿ¸¸½÷¸ú ™Ÿ¸›¸ 23. ¬¸¢�¸¨¸ (¢¨¸Ô¸º÷¸),¬¸¿‹¸ ©¸¸¢¬¸÷¸ ®¸½°¸, ™¸™£¸ ›¸¸Š¸£ í¨¸½¥¸ú, ¢¬¸¥¸¨¸¸¬¸¸ 24. ˆÅ¸¡¸ÄˆÅ¸£ú ¢›¸™½©¸ˆ , ‡›¸‡¥¸”ú¬¸ú, ›¸ƒÄ ¢™¥¥¸ú 25. ˆÅ¸¡¸ÄˆÅ¸£ú ¢›¸™½©¸ˆ , œ¸®¸½ž¸¸œÏ½ˆ½Å›Í, Ÿ¸º¿¤¸ƒÄ 26. ˆÅ¸¡¸ÄˆÅ¸£ú ¢›¸™½©¸ˆ , ’¸’¸ œ¸¸¨¸£ ˆ¿ÅŸœ¸›¸ú, Ÿ¸º¿¤¸ƒÄ 27. Ÿ¸í¸œÏ¤¸¿š¸ˆÅ, ‚¸£�¸úœ¸úœ¸ú‡¥¸, ›¸¸½¡¸”¸ 28. Ÿ¸º‰¡¸ ˆÅ¸¡¸Ä.¢›¸™½., ‡›¸‡�¸”ú¬¸ú ¢¥¸¢Ÿ¸.,ž¸¸½œ¸¸¥¸ 29. ¬¸™¬¡¸ (¢¨¸Ô¸º÷¸), ›¸.¢›¸.œÏ¸¢š¸., ƒ¿™¸¾£ 30. ¢›¸™½©¸ˆÅ, ƒ¬¬¸¸£ œ¸¸¨¸£ ¢¥¸¢Ÿ¸., ¬¸»£÷¸ 31. ¢›¸™½©¸ˆÅ, œ¸ú’ú¬¸ú ƒ¿¢”¡¸¸ ¢¥¸¢Ÿ¸., ›¸ƒÄ ¢™¥¥¸ú 32. Ÿ¸í¸œÏ¤¸¿š¸ˆÅ, ¤¸½¬’ „œ¸ÇÅŸ¸, Ÿ¸º¿¤¸ƒÄ 33. ¬¸™¬¡¸ ¬¸¢�¸¨¸, œ¸®¸½¢¨¸¬¸¢Ÿ¸¢÷¸, Ÿ¸º¿¤¸ƒÄ

¢¨¸©¸½«¸ ‚¸Ÿ¸¿¢°¸÷¸ ¬¸™¬¡¸ 1. ¬¸™¬¡¸ (¢¨¸Ô¸º÷¸ œÏμ¸¸¥¸ú), ˆ½Å¢¨¸œÏ¸, ›¸ƒÄ ¢™¥¥¸ú 2. œÏ¤¸¿š¸ ¢›¸™½©¸ˆÅ, ‡Ÿ¸‡¬¸ƒÄ¤¸ú í¸½¢¥”¿Š¸ ˆ¿Å.¢¥¸¢Ÿ¸., Ÿ¸º¿¤¸ƒÄ 3. ‚š¡¸®¸ ‡¨¸¿ œÏ¤¸¿š¸ ¢›¸™½©¸ˆÅ, Ÿ¸.œÏ.¢¨¸.’ï½”ˆÅ¸½, �¸¤¸¥¸œ¸º£ 4. œÏ¤¸¿š¸ ¢›¸™½©¸ˆÅ, Žî¸ú £¸ œ¸¸¨¸£ í¸½¢¥”¿Š¸ ˆÅŸœ¸›¸ú ¢¥¸¢Ÿ¸., £¸¡¸œ¸º£ 5. œÏ¤¸¿š¸ ¢›¸™½©¸ˆÅ, Š¸º�¸…¢¨¸¢›¸¢¥¸¢Ÿ¸., ¨¸”¸½™£¸ ‚›¡¸ 1. œÏ¤¸¿‹¸ ¢›¸™½©¸ˆÅ, Žî¸ú£¸¢¨¸„÷œ¸¸ˆ¿Å¢¥¸¢Ÿ¸., £¸¡¸œ¸º£ 2. Ÿ¸º‰¡¸ ‚¢ž¸¡¸¿÷¸¸ (¨¸¸¢μ¸�¡¸), Žî¸ú£¸¢¨¸¢¨¸÷¸ˆ¿Å¢¥¸¢Ÿ¸., £¸¡¸œ¸º£ 3. œÏ¤¸¿š¸ ¢›¸™½©¸ˆÅ, Š¸º�¸£¸¢¨¸¢›¸¢¥¸¢Ÿ¸., ¨¸”¸½™£¸ 4. Ÿ¸º‰¡¸ ‚¢ž¸¡¸¿÷¸¸ (‚¸£. ‡¿” ¬¸ú), Š¸º�¸¢¨¸œ¸¸£½¢›¸¢¥¸¢Ÿ¸., ¨¸”¸½™£¸ 5. ˆÅ¸¡¸ÄˆÅ¸£ú ¢›¸™½©¸ˆÅ (¢¨¸î¸), Š¸º�¸…�¸¸Ä¢¨¸¢›¸¢¥¸¢Ÿ¸., ¨¸”¸½™£¸ 6. ˆÅ¸¡¸ÄˆÅ¸£ú ¢›¸™½©¸ˆÅ (‚¸½ ‡¿” ‡Ÿ¸ ‡¿” �¸½›¸.), Ÿ¸œÏ¢¨¸„÷œ¸¸ˆ¿Å¢¥¸¢Ÿ¸., �¸¤¸¥¸œ¸º£ 7. ¢¨¸©¸½«¸ ˆÅ¸¡¸Ä ‚¢š¸ˆÅ¸£úÅ (‡¥¸ ‡¿” ‚¸£ ‡), ‡Ÿ¸.œ¸ú.’ï½”ˆÅ¸½, �¸¤¸¥¸œ¸º£ 8. ¢›¸™½©¸ˆÅ (œÏ�¸¸.), Ÿ¸í¸£¸¢¨¸¢¨¸÷¸ˆÅŸœ¸›¸ú ¢¥¸¢Ÿ¸., Ÿ¸º¿¤¸ƒÄ 9. ¢›¸™½©¸ˆÅ (œÏ�¸¸.), Ÿ¸í¸£¸¢¨¸„÷œ¸¸ˆ Ÿœ¸›¸ú ¢¥¸¢Ÿ¸., Ÿ¸º¿¤¸ƒÄ 10. ¢›¸™½©¸ˆÅ (œÏ�¸¸¥¸›¸), Ÿ¸í¸£¸¢¨¸œ¸¸£½ˆ¿Å¢¥¸¢Ÿ¸., Ÿ¸º¿¤¸ƒÄ 11. Ÿ¸º‰¡¸ ‚¢ž¸¡¸¿÷¸¸ (œ¸úœ¸ú), Ÿ¸í¸£¸¢¨¸¢¨¸÷¸ˆÅŸœ¸›¸ú ¢¥¸¢Ÿ¸., Ÿ¸º¿¤¸ƒÄ 12. Ÿ¸º‰¡¸ ‚¢ž¸¡¸¿÷¸¸ (¢ŠÏ” œÏ¤¸¿.), ˆ½Å¢¨¸œÏ¸, ›¸ƒÄ ¢™¥¥¸ú 13. Ÿ¸º‰¡¸ ‚¢ž¸¡¸¿÷¸¸ (’︿¬¸.), ‡›¸œ¸ú¬¸ú‚¸ƒÄ‡¥¸, Ÿ¸º¿¤¸ƒÄ 14. ®¸½°¸ú¡¸ ˆÅ¸¡¸ÄˆÅ¸£ú ¢›¸™½©¸ˆÅ, ‡›¸œ¸ú’ú¬¸ú¢¥¸¢Ÿ¸., œ¸®¸½Ÿ¸º‰¡¸¸¥¸¡¸, Ÿ¸º¿¤¸ƒÄ 15. ˆÅ¸¡¸ÄˆÅ¸£ú ¢›¸™½©¸ˆÅ (¨¸¸¢μ¸�¡¸), ‡›¸’úœ¸ú¬¸ú ¢¥¸¢Ÿ¸., ›¸ƒÄ ¢™¥¥¸ú 16. ˆÅ¸¡¸ÄˆÅ¸£ú ¢›¸™½©¸ˆÅ (¨¸¸¢μ¸�¡¸), œ¸ú�¸ú¬¸ú‚¸ƒÄ‡¥¸, Š¸º”õŠ¸¸¿¨¸ 17. ˆÅ¸¡¸ÄˆÅ¸£ú ¢›¸™½©¸ˆÅ (”¤¥¡¸»‚¸£’ú‡¬¸-I), œ¸ú�¸ú¬¸ú‚¸ƒÄ‡¥¸, ›¸¸Š¸œ¸º£ 18. ˆÅ¸¡¸ÄˆÅ¸£ú ¢›¸™½©¸ˆÅ (”¤¥¡¸»‚¸£’ú‡¬¸-II), œ¸ú�¸ú¬¸ú‚¸ƒÄ‡¥¸, ¨¸”¸½™£¸ 19. ˆÅ¸¡¸Äœ¸¸¥¸ˆÅ ‚¢ž¸¡¸¿÷¸¸ , ™Ÿ¸›¸ ™ú¨¸, ›¸¸›¸ú ™Ÿ¸›¸ 20. ˆÅ¸¡¸Äœ¸¸¥¸ˆÅ ‚¢ž¸¡¸¿÷¸¸, ™¸™£¸ ›¸¸Š¸£ í¨¸½¥¸ú, ¢¬¸¥¸¨¸¸¬¸¸ 21. ˆÅ¸¡¸ÄˆÅ¸£ú „œ¸¸š¡¸®¸, œ¸ú’ú¬¸ú ƒ¿¢”¡¸¸ ¢¥¸¢Ÿ¸., ›¸ƒÄ ¢™¥¥¸ú 22. Ÿ¸í¸œÏ¤¸¿š¸ˆÅ (¢¨¸Ô¸º÷¸), ‚¸£�¸úœ¸úœ¸ú‡¥¸, £÷›¸¸¢Š¸£ú 23. Ÿ¸º‰¡¸ ‚¢ž¸¡¸¿÷¸¸ (£½Š¸º¥¸½’£ú ‡¨¸¿ ¨¸¸¢μ¸�¡¸), ¤¸½¬’, Ÿ¸º¿¤¸ƒÄ 24. Ÿ¸í¸œÏ¤¸¿š¸ˆÅ, ‚¸ƒÄ‡¬¸œ¸ú, ‡›¸‡�¸”ú¬¸ú ¢¥¸¢Ÿ¸., Ÿ¸š¡¸ œÏ™½©¸ 25. ¨¸¢£.Ÿ¸í¸œÏ¤¸¿š¸ˆÅ, ’¸’¸ œ¸¸¨¸£ ˆÅŸœ¸›¸ú, Ÿ¸º¿¤¸ƒÄ 26. ¨¸¢£. „œ¸¸š¡¸®¸,. ƒ¬¬¸¸£ œ¸¸¨¸£ ¢¥¸¢Ÿ¸., ¬¸»£÷¸ 27 ¬¸™¬¡¸ ¬¸¢�¸¨¸, œ¸»¨¸Ä®¸½¢¨¸¬¸¢Ÿ¸¢÷¸, ˆÅ¸½¥¸ˆÅ¸÷¸¸ 28. ¬¸™¬¡¸ ¬¸¢�¸¨¸, ™®¸½¢¨¸¬¸¢Ÿ¸¢÷¸, ¤¸¿Š¸¥¸º³ 29. ¬¸™¬¡¸ ¬¸¢�¸¨¸, „œ¸»¨¸Ä®¸½¢¨¸¬¸¢Ÿ¸¢÷¸, ¢©¸¥¸¿¸Š¸ 30. ¬¸™¬¡¸ ¬¸¢�¸¨¸, „®¸½¢¨¸¬¸¢Ÿ¸¢÷¸, ›¸ƒÄ ¢™¥¥¸ú

ž¸¸£÷¸ ¬¸£ˆÅ¸£

Government of India ˆ ½›Íú¡¸ ¢¨¸Ô¸º÷¸ œÏ¸¢š¸ˆÅ£μ¸

Central Electricity Authority

œ¸¢©�¸Ÿ¸ ®¸½°¸ú¡¸ ¢¨¸Ô¸º÷¸ ¬¸¢Ÿ¸¢÷¸ WESTERN REGIONAL POWER COMMITTEE

œ¸®¸½¢¨¸¬¸ ˆÅú ¢™›¸¸¿ˆÅ 25 isatMbar 2009 ˆÅ¸½ rayapur Ÿ¸½¿ ‚¸¡¸¸½¢�¸÷¸ 11 ¨¸ú¿ ¤¸¾“ˆÅ ˆÅa ˆÅ¸¡¸ÄvaR%t

 

MINUTES OF 11TH MEETING OF WRPC HELD ON 25TH SEPTEMBER 2009 AT RAIPUR

Ÿ¸º¿¤¸ƒÄ  

MUMBAI

 

 

C O N T E N T S Item No. Particulars

Page No.

ITEMS FOR DISCUSSION

ITEM No.1 CONFIRMATION OF THE MINUTES OF THE 10th MEETING OF WRP COMMITTEE

3

ITEM No.2 PERFORMANCE OF WR GRID DURING JUNE 09 TO AUG. 09 4

ITEM No.3 ISSUES CONCERNING TO THE DISSCUSSION HELD IN THE 29TH MEETING OF POWER SYSTEM PLANNING OF WESTERN REGION HELD ON 10TH SEPTEMBER 2009 AT AHMEDABAD

7

ITEM No.4 FREE GOVERNOR MODE OF OPERATION ON ALL GENERATING UNITS INSTALLED

17

ITEM No.5 WIDE AREA MEASUREMENT SYSTEM (WAMS) IN WR 17

ITEM No.6 PGCIL PROPOSAL FOR REPLACEMENT OF OLD PLCC PANELS 20

ITEM No.7 TRANSMISSION CHARGES FOR WHEELING OF CENTRAL SECTOR POWER TO DD & DNH THROUGH GETCO TRANSMISSION SYSTEM AND THE BILLING MECHANISM

21

ITEMS FOR INFORMATION

ITEM No.8 ANTICIPATED POWER SUPPLY POSITION IN WESTERN REGION FOR THE PERIOD FROM SEPT. 09 TO NOV. 09

23

ITEM No.9 SIGNING OF PPA WITH RGPPL AND ITS SCHEDULING 23

ITEM No.10 LTSA ARRANGEMENT FOR SCADA / EMS UNDER WR ULDC SCHEME

24

ITEM No.11 INVESTIGATION ON FAILURE OF 400KV TRANSMISSION LINES OF PGCIL DURING MAY-JUNE – 2009 BY THE STANDING COMMITTEE OF EXPERTS

25

ITEM No.12 SCHEDULE OF REVIEW OF CRISIS MANAGEMENT PLAN OF CENTRAL NODAL MINISTRIES / DEPARTMENTS FOR 2009-10

26

ITEM No.13 PAYMENTS OF UI AND REACTIVE ENERGY CHARGES 26

ITEM No.14 COMMISSIONING OF TRANSMISSION LINES AND GENERATING UNITS

27

ITEM No.15 ONGOING TRANSMISSION SCHEMES IN WESTERN REGION 27

ITEM No.16 ONGOING GENERATION SCHEMES IN WESTERN REGION 27

Agenda Notes of 11th WRPC meeting to be held on 25th Sept. 09

ITEM No.17 DISBURSEMENT OF INTEREST CALCUALATED ON LATE PAYMENT OF UI CHARGES AND THE INTEREST EARNED ON DEPOSIT AMOUNT FOR UI IN IDBI BANK

28

ITEM No.18 AUTOMATIC METER READING SOLUTIONS BY M/S BPL 29

ITEM No.19 ALLOCATION OF POWER FROM SUBANSIRI HEP (2000 MW) OF NHPC AND KAMENG HEP (600 MW) IN ARUNACHAL PRADESH

30

ITEM No.20 PROCUREMENT OF ONE SPARE UNIT OF 50 MVAR SHUNT REACTOR FOR WR

30

ITEM No.21 OPGW CONNECTIVITY TO SUB-STATIONS OF PGCIL 31

ITEM No.22 STATUS OF LTOA APPLICATIOS IN WR 32

ITEM No.23 EVACUATION OF POWER FROM GENERATION PROJECTS COMING UP IN SIKKIM AND BHUTAN

37

ITEM No.24 OPEN ACCESS APPLICATIONS PERTAINING TO NEW GENERATION PROJECTS IN SOUTHERN REGION WITH TARGET BENEFICIARIES IN WESTERN/ NORTHERN/ SOUTHERN REGION

39

ITEM No.25 PSS TUNING ACTIVITY IN WR 40

ITEM No.26 DATE AND VENUE OF NEXT WRPC MEETING 41

Agenda Notes of 11th WRPC meeting to be held on 25th Sept. 09

ANNEXURES

Annexure

Particulars

Annexure-1 (A) Participants attending TCC meeting held on 24.09.2009

Annexure-1 (B) Participants attending 11th WRPC meeting held on 25.09.2009

Annexure-2.1(a) The details of frequency profile during the period from June 2009 to August 2009

Annexure-2.1(b) Power supply position in WR for the period from June 2009 to August 2009

Annexure-2.2 The month wise detail of voltages at 400 kV and 765 kV sub-stations during the month of June 2009 to August 2009

Annexure-2.4 UFR operation in various constituents of WR during June 2009 to August 2009

Annexure-3.1.2 Details of the projects in Chhattisgarh

Annexure-5.2 GM I/c (LD & C), PGCIL letter dated 8th Sept. 09

Annexure-15 Details of ongoing transmission schemes in WR

Annexure-16 Details of on going generation schemes in WR both under State

as well as Central Sector

Agenda Notes of 11th WRPC meeting to be held on 25th Sept. 09

MINUTES OF 11th MEETING OF WESTERN REGIONAL POWER COMMITTEE HELD ON 25TH SEPTEMBER 2009 AT RAIPUR

The TCC and 11th WRPC meetings were held on 24th & 25th September 2009 respectively at Raipur. The list of the participants are at Annexure-I (A) & I (B) respectively. Shri V. K. Verma, Managing Directror, CSPHCL, Shri S. P. Chaturvedi, Managing Directror, CSPGCL, Shri S. N. Chauhan, MD, CSPTCL and Shri G. S. Deshpande, Managing Directror, CSPDCL extended warm welcome to Hon'ble Chief Minister, Chhattisgarh State, Dr. Raman Singh, Shri P. Joy Ommen, Chief Secretary (Power), Govt. of Chattisgarh, & Chairman, Chhattisgarh Power Companies, Shri Aman Singh, Special Secretary (Power), Govt. of Chhattisgarh, Shri S. Jagadeesan, Chairman, WRPC and Chairman, GSECL, Shri S.K. Negi, Managing Directror, GETCO and Chairman TCC, Shri V.Ramakrishna, Member (Power Systems), CEA and all members of WR Power Committee, special invitees and participants attending the meeting. During the address, Shri S. P. Chaturvedi, Managing Director, CSPGCL stated that the State of Chhattisgarh State has historical relevance and is famous for its traditional culture. The State is known as 'Dhan Ka Katora' being blessed with highly fertile land. It also has abundant natural resources, which are helping in development of Power, Cement and Steel industry on large scale in the State. He added that after the formation of Chhattisgarh State Electricity Board (CSEB) w.e.f. 1.11.2000, Chhattisgarh State has developed in terms of quantum of power generation capacity with participation from NTPC Ltd., BSP, BALCO & other IPPs. He further stated that though some of the operating thermal power plants in Chhattisgarh State are old, an overall increase of PLF in the State has been achieved from 65 % to 86 % during their operation period since the formation of CSEB. Chhattisgarh State has also been implementing zero power cut continuously for past 21 months, which is an added achievement. Shri Aman Singh, Special Secretary (Power) during his address stated that Chhattisgarh State is emerging as power hub of the country and it has tremendous responsibility on its shoulders to arrange coal/fuel linkages for the upcoming thermal power projects in the State for capacity addition programme of 48000 MW, for which the MOUs have already been signed with the power developers. The issues relating to redressal of R&R problems, land acquisition and arranging environmental clearances will be addressed appropriately under the leadership and guidance of the Hon'ble Chief Minister himself who also holds charge of State Urja Minister. Shri S. Jagadeesan, Chairman, WRPC and Chairman, GSECL welcomed Hon’ble Chief Minister, Dr. Raman Singh, Shri Aman Singh, Special Secretary (Power), Shri P. Joy Ommen, Secretary (Power) & Chairman, Chhattisgarh Power Companies, all members, special invitees and participants attending the meeting of WR Power Committee. He specially thanked Dr. Raman Singh, Hon'ble Chief Minister, Chhattisgarh State for sparing his valuable time from most busy schedule during visit of Shri P. Chidambaram, Hon’ble Home Minister to BALCO plant due to very sad incidence of Chimney collapse at BALCO and to attend law & order problem. He

Minutes of 11th WRPC meeting held on 25th September 2009 at Raipur

1

narrated about his close association with him in the past at the Centre, when Dr. Raman Singh was Minister of State for Commerce and Industry and about keen interest taken by him in promoting Power Sector development in the State. He further stated that Chhattisgarh State is one of the backward states but in the contrary is blessed with huge natural resources. The reason behind the growth of Chhattisgarh state is the best utilization of GoI schemes from time to time under his guidance. During his address he intimated that Western Region is the largest region in country in terms of Installed capacity and power consumption. During the period June 2009 to August 2009, Regional Grid operated at system frequency within IEGC range of 49.2 Hz to 50.3 Hz on the average for about 83% of the time. However on account of prolonged dry spell, despite efforts to maximize availability in August 2009 from 17000 MUs to 19200 MUs, the highest regional peak shortfall of 6950 MW i.e. 19% and the energy shortfall of 12% had resulted in the Western Region. The situation had been getting aggravated on account of drawls from this region by other regions, above the schedules at low frequency. The unrestricted demand of the region varied from 32,450 MW to 37,050 MW against 33360 MW to 35500 during last year. Western Region continues to experience huge demand-supply gap and the same is likely to aggravate further in the coming months. The peak deficit is estimated to be around 13 to 19 %. It is expected that additional capacity of nearly 35000 MW to be added in the next 5 – 6 years by number of IPPs out of which 19350 MW capacity is to come up in the Western Region. Against 19350 MW capacity in the western region, already open access for 17300 MW is under process of approval. Therefore it becomes imperative that the evacuation system need to be completed as per the plan keeping pace with the commissioning of the generating capacities. In this context, the role of the Chhattisgarh State is of paramount importance in terms of facilitating the continued coal supply, early completion of generating units, implementation of the associated evacuation system. He hoped that the deliberations in this meeting would be fruitful for all the stakeholders and the discussions would take place in the context of facilitating quality power supply to the participant States/ utilities. He thanked the Chhattisgarh State Government and the power utilities of the State for hosting this meeting and making excellent arrangements for the same. Dr. Raman Singh, Hon'ble Chief Minister, Chhattisgarh State during his address stated that during this holy period of NAVRATRI every body is worshipping Maa Shakti (Maa DURGA) and URJA (Power) is one form of Maa Shakti. He further stated that in coming 5 years around 15000 MW power is going to be added in the state and Rs 15000 Cr. would also be required for transmission schemes for evacuation as well as strengthening for transfer of this additional power. He said that with the huge generation capacity which is expected to come up in the in near future, there would be consequential development in other Sectors too in the State. The steps are therefore on way to arrange necessary infrastructure for the same. He stated that we should plan generation and transmission both for much longer period such as upto 2015-20. He stated that coal/fuel for future can be tied up and imported from other countries as cost difference in indigenous and imported coal would be very less in future as the coal linkage for long-term generation projects would need to be supplemented from the imported coal.

Minutes of 11th WRPC meeting held on 25th September 2009 at Raipur

2

Shri V. K. Verma, Managing Director, CSPHCL specially thanked the Hon'ble Chief Minister, Chhattisgarh State for sparing time out of his busy schedule to address this forum and giving his valuable guidance. He thanked Shri S. Jagadeesan, Chairman, WRPC and Chairman, GSECL, all Senior officials from the Western Regional States, CEA and all other WR Power Committee members for sparing time to attend the meeting and deliberate on issues slated for the discussion. Shri S. Jagadeesan, Chairman, WRPC and Chairman, GSECL, thereafter requested Member Secretary, WRPC to take up agenda items for the meeting. ITEM No.1: CONFIRMATION OF THE MINUTES OF THE 10th MEETING OF WRP

COMMITTEE 1.1 Member Secretary, WRPC stated that the minutes of 10th meeting of WR Power Committee held on 30th May 2009 at Diu were sent to the members vide letter No. WRPC/Minutes/AS/2009/6239 dated 15th June 2009. He stated that comments have been received from GM (Comml.), NTPC on Item No. 4, “transmission system connected with Vindhyachal pooling station and phasing of transmission work” requesting amendment in Para 4.3 and Para 4.4 of the minutes of the meeting as give below:

Para 4.3: GM(Commercial), NTPC stated that Vindhyachal-IV and Rihand-III Projects of NTPC are being developed as Regional Power Stations and as such the transmission system associated with these projects such as Vindhyachal-IV-Vindhyachal pooling 400 kV quad D/C line and Rihand-Vindhyachal pooling 2xS/C 765kV lines operated at 400 kV will be developed and owned by CTU (PGCIL). He further stated that NTPC has taken up with CEA the issue of amendment of the minutes of the SCPSP of WR to reflect the NTPC views as above and accordingly this agenda item may be confirmed after the issuance of the amendment by CEA.

Para 4.4: In response to a clarification, NTPC stated that Vindhayachal-IV and Rihand-III projects are being developed for the beneficiaries of WR and NR respectively. It was further clarified that allocation of power from power stations shall be as decided by GoI.

1.2 The WR Power Committee discussed the matter. It was noted that this matter was included in the agenda of 29th SCPSP of WR held on 10th September 2009 at Ahmedabad, wherein clarification to above was made as is reflected in subject minutes of the 10th WRPC meeting and hence no modification was required to be made in the same. In view of above, the WR Power Committee confirmed the minutes of 10th WRPC meeting without any modification.

Minutes of 11th WRPC meeting held on 25th September 2009 at Raipur

3

ITEM No.2: PERFORMANCE OF WR GRID DURING JUNE 09 TO AUG. 09 2.1 System Performance Member Secretary, WRPC stated that during the period June 2009 to August 2009, the grid operated in the frequency range of 49.2 Hz to 50.3 Hz for 83 % of time. The percentage time when frequency was within this range varied between 73.98 % to 94.74%. During this period, frequency remained below 49.2 Hz for 16.59 % of time. The frequency profile during the period was not much satisfactory except in July, 2009. During the period there was generally overdrawal by NR and ER due to prolonged dry spell/ generating unit outages. An improved system performance during the period was attributed to the synchronization of new generating units at Sugen, NSPCL-Bhilai, LANCO and APL. The details of frequency profile during the period from June 2009 to August 2009 are furnished at Annexure 2.1(a).

He said that the unrestricted demand of Western Region during the period varied between 32500 MW to 37100 MW. The corresponding figures for the previous year were between 33360 MW to 35500 MW. The maximum demand met during the period was 30115 MW and the region faced capacity shortage in the range of 4800 MW to 7000 MW. The details of Unrestricted Demand vs. Demand Met and Energy Requirement vs. Availability are furnished at Annexure-2.1(b).

Member Secretary, WRPC stated that during TCC meeting held on 24th September 2009, Gujarat, MP, Chhattisgarh and Maharashtra had suggested that planned outages of 500 MW units should not be taken in the months of October to March of the year and for the current year. It was also suggested that NTPC may plan outage of 500 MW units only after Diwali period and that the simultaneous outage of two 500 MW units of NTPC in the month of February 2010 viz KSTPS#4 from 03.02.10 to 27.02.10 and VSTPS#9 from 09.02.10 to 10.03.10 may be rescheduled. In this context, NTPC had intimated that they may not be availing simultaneous outage of two 500 MW units of NTPC in the month of February 2010 and for taking planned outage only after Diwali period they would revert back. The Committee noted the same. 2.2.1 The month-wise detail of voltages at 400 kV and 765 kV sub-stations during the month of June 2009 to August 2009 is placed at Annexure- 2.2. During the period low voltage was observed at Jetpur 400 kV touching to 352 kV on 27.08.2009 & 376 kV on 18.07.2009 and at Gwalior 400 kV touching to 365 kV on 20.07.2009, 372 kV on 13.08.2009 and 375kV on 27.06.2009. High voltage was recorded at 400 kV throughout the period at Dhule and Karad S/s in the order of 426 kV to 440 kV. To contain high voltages WRLDC had to resort to opening of 5 to 6 lines on many days. In order to control incidences of high voltages during low load periods, installation of reactors at following locations has been planned by various utilities:-

Minutes of 11th WRPC meeting held on 25th September 2009 at Raipur

4

S.No. 400 kV

Substation Size (MVAR) Implementing

Agency Expected date of Commissioning

1. Khandwa 1x125 PGCIL June 2010 2 Dhule 2x50 MSETCL Dec. 2009 3. Dehgam 1x125 PGCIL June 2010 4. Kasor 1x125 GETCO Feb. 2010 5 Karad 1x80 MSETCL Oct. 2009 6 Nardipur( Soja) 1x80 GETCO Feb. 2010

The progress achieved on above and expected date of installation and commissioning of reactors at the above locations as above was confirmed by the concerned utilities. The implementing utilities were requested that timely commissioning of these reactors may be ensured, as this would help in smoothening of high voltage profile in Western Regional Grid. 2.2.2 The issue regarding high voltage in Dhule area was also discussed in the meeting. It was pointed out that even after taking all other actions, including opening of number of lines, high voltage problem was still persisting. PGCIL was therefore, requested to conduct fresh studies for installation of reactors at Nagda or Rajgarh. PGCIL intimated that according to studies carried by them, installation of 1X125 MVAR bus reactor at Rajgarh would be beneficial to control over voltages. Member Secretary, WRPC stated that during TCC meeting POWERGRID intimated that installation and commissioning of 1X125 MVAR bus reactor at Rajgarh sub-station would take two years of time i.e. the reactor would be commissioned by September 2011.

The Committee noted the same.

2.3 Operational Discipline

Member Secretary, WRPC stated that there had been occasions of overdrawal by NR and ER from the WR grid under low frequency regime during the period June 2009 to August 2009. Over drawl by NR grid was to the extent of 1041 MW and that by ER grid to the extent of 876 MW during the month of August 2009. The large quantum of overdrawal had been resulting in low system frequency of the interconnected grid and operation of relays under AUFLS in Western Region. The overdrawal by NR and ER had been cause of concern during the month. The subject matter of overdrawal by neighboring region from WR had been taken up by WRPC with WRLDC and NLDC. WRLDC had intimated that they had been taking up the subject matter of overdrawal by NR and ER systems from WR grid in the real-time operation at number of occasions and it further intimated that NRLDC had filed two petitions with Hon'ble CERC on 09.07.2009 and 07.08.2009 against NR constituents on the same subject. He said that overdrawal during low frequency regime from WR grid by the neighboring regions was attributing largely in causing the system frequency below 49.2 Hz thereby forcing commercial deterrent to the constituents of Western Region who were either under drawing or limitedly/marginally over drawing. It is therefore

Minutes of 11th WRPC meeting held on 25th September 2009 at Raipur

5

essential that such instances of over drawal by the neighboring regional grids from the WR grid of N-E-W grid are contained in the interest of secured operation of the grid. Member Secretary, WRPC stated that TCC deliberated the issue and suggested that CEA may a convene joint meeting between WRLDC, NRLDC, NLDC, NRPC, WRPC, NR and WR constituents and CEA in Mumbai to resolve the issue and also in view of the ensuing Rabi peak demand period when high shortage conditions would yet continue to prevail/ aggravate. Further an effective administrative mechanism to control flows on major inter-regional links in the real time does not seem to exist at present. TCC suggested that CEA may be requested to address the issue concerning this aspect at an appropriate level and so as to have suitable remedial provisions for the same. CMD, MPPTCL stated that NR grid had been consistently overdrawing power from the grid. Also due to heavy overdrawal by NR, 220 kV Ujjain - Kota line and 220 kV Ujjain - Badod section of 220 kV Ujjain-Kota line which were synchronized with NR grid are getting over loaded. He said that this is a matter of serious concern and necessary corrective action has to be taken by NR to control the loading. He further suggested that information about performance of AUFLS in ER / NR systems and load relief obtained through the AUFLS operation should also be available to WR Constituents in similar manner as is being done by WR constituents.

Member (Power System), CEA stated that it is prudent for any overdrawing utility(ies) to restrict drawl at low frequency by effecting adequate load shedding. He added that matter regarding overdrawl by NR constituents from the grid has also been addressed by the Hon'ble CERC and penalty was also imposed on the defaulting constituent. He however suggested that to contain overloading of the interconnected link on account of overdrawl of NR the appropriate corrective action needs to be initiated by NRLDC. Director (O), MSETCL stated that Maharashtra Government has brought to the notice of Central Government the subject matter of overdrawal by other utilities from the interconnected grid, which is causing undue AUFLS operations in Maharashtra grid at low frequency, even though the State has been underdrawing after implementing large quantum of load shedding. During WRPC meeting, Chairman, WRPC suggested that subject matter of over drawal by neighboring region may be brought to the notice of CEA/Ministry of Power so that matter is taken up with Chairman, NRPC / concerned State authority. He also suggested that a joint meeting of WR/NR may also be arranged to be convened to address the issue. He said that he would also personally appraise Secretary (Power), Ministry of Power about the matter during a meeting in the coming week. After detailed discussion it was agreed that CEA would be requested to convene a joint meeting between WRLDC, NRLDC, NLDC, NRPC, WRPC, NR and WR constituents and CEA preferably at Delhi to discuss the issue and evolve a solution.

Minutes of 11th WRPC meeting held on 25th September 2009 at Raipur

6

2.4 AUFLS Performance in WR

The month-wise details relating to performance of AUFLS scheme in Western Region during the period June 2009 to August 2009 in terms of quantum of load relief obtained and number of occasions the UFR operated was noted by the Committee. The detail is at Annexure-2.4.

Member Secretary, WRPC stated that the AUFLS scheme, which is operational in Western Region, is essentially a defense mechanism for safeguarding the secured operation of the interconnected grid in the event of occurrence of any type of grid disturbance. It is therefore, requested that the WR beneficiaries may ensure to always keep the above scheme in operational readiness.

The Committee noted the same. ITEM No.3: TRANSMISSION SYSTEM ASSOCIATED WITH IPPS LOCATED IN

ORISSA, JHARKHAND, WEST BENGAL, MADHYA PRADESH AND CHATTISHGARH, MAUDA (2X500 MW), VINDHYACHAL-IV (1000MW) & RIHAND-III (1000MW) GENERATION PROJECTS OF NTPC

3.1 Transmission system associated with IPPs located in Orissa,

Jharkhand, West Bengal, Madhya Pradesh and Chattishgarh 3.1.1 Member Secretary stated that during the 28th meeting of the SCM of WR held on 6th December 2008, comprehensive transmission system associated with Tilaiya UMPP (4000 MW), Nabinahgar (1000 MW) of Railways and NTPC, Barh-II (1320 MW), Rihand-III (1000 MW) Vindhyachal-IV (1000 MW) and Mauda (1000 MW) of NTPC and IPPs in Jharkhand, Orrissa, Madhya Pradesh, Chhattisgarh and Maharashtra was deliberated and generation specific , System Strengthening Common to WR and NR and System Strengthening for WR were evolved and agreed. From the evolved transmission system, transmission elements to be associated with Vindhyachal-IV and Rihand-III were subsequently agreed along with its phasing during the Special meeting of the SCM held on 18th April 2009. It was also decided that based on latest status of various IPP projects, phasing of transmission works would be worked out. The above matter was deliberated in the TCC of WR held on 29th May 2009, the members had agreed to the scheme and stressed that the actual programme with each of the projects, once finalized, will be brought forth in the Standing Committee meeting and to WRPC meeting. Also, change in the transmission scheme, if any, subsequent to discussion in other region, will have to be brought to the notice of WRP Committee for its approval. It was also stressed that as discussed in the Special SCM, held on 18th April 2009, the details of cost of transmission scheme should be sent to all the constituents by PGCIL. The WRP Committee further discussed the matter in its 10th meeting held on 30th May 2009 at Diu and endorsed the views of the TCC. PGCIL representative had stated that the details of the transmission cost will be furnished to all the concerned by 5th June 2009.

Minutes of 11th WRPC meeting held on 25th September 2009 at Raipur

7

3.1.2 In this meeting, Member (Power System), CEA stated that based on the review of progress of various IPPs in Chhattisgarh a list of 12 nos IPPS in Chhattisgarh who had made some progress which were likely to materialize during 11th plan / early 12th plan programme for which was drawn. The total installed capacity of these twelve (12) nos IPPs is 15485 MW out of which 7 no. IPPs with capacity 8540 MW are located near Raigarh complex and 5 no. IPPs with capacity 6945 MW are located near Jhangir-Champa complex. The target beneficiaries as indicated by these IPPs are 11143 MW to WR and 3742 MW to NR. For Orissa IPPs based on review with the project developers, OPTCL, CEA and POWERGRID had assessed and drawn a list of seven (7) projects with total capacity 10,090 MW which are likely to materialize by end of 11th Plan/ early 12th plan. The target beneficiaries indicated by these IPPs is 2340 MW to WR and 3315 MW to NR and balance to ER/SR. For Jharkhand and West Bengal (WBSEDCL) generation projects based on review the total installed capacity works to about 5465 MW. The target beneficiaries indicated by these IPPs is 1470 MW for WR and 2964 MW for NR and balance to ER. For IPP projects of Madhya Pradesh and Chhattisgarh (connected to Bilaspur pooling station) the total installed capacity is 3870 MW and the target beneficiaries indicated by these IPPs was 2375 MW for WR and 1095 for NR. Thus the total capacity of IPP projects in Chhatisgarh, Madhya Pradesh, Orissa, Jharkhand and West Bengal for which transmission system was considered during the 29th SCM of WR was of the order of 35,000 MW. Details of the projects is at Annex-3.1.2 He further stated that the transmission system associated with the various IPP projects located in different states was discussed during the 29th meeting of the Standing Committee on Power System Planning and the transmission system was evolved. Details of the evolved transmission are:

i) For evacuating power from 12 no. of IPPs projects in Chattishgarh it was agreed to pool power at 3 nos 765/400 kV pooling stations at Raigarh (Kotra), Raigarh (Tanmar) and Champa. Two pooling stations Raigarh (Kotra) and Raigarh (Tanmar) pooling stations have been have been planned and interconnected to reduce the ROW requirements as there is difficulty in laying lines for projects located northern part of Raigarh . At present only Jindal Power project is connected to Raigarh (Tanmar). It is understood that Jindal Power is yet to get coal linkage. Therefore the implementation of Raigarh(Tanmar) pooling station should be linked with the progress of works at Jindal power. These three pooling stations would be interconnected through Raigarh (Kotra)- Champa 765 kV S/C and Raigarh (Kotra)- Raigarh(Tamnar) 765 kV D/C line. For onward transfer of power it was agreed to further pool power at another intermediate Raipur pooling station. Raigarh Pooling station (Kotra) would be connected to Raipur pooling station through 765 kV D/C line. Similarly Champa would be connected to Raipur through 765 kV D/C lines. To provide an alternate path Champa pooling station would also be connected to Dharamjaygarh where power from other IPP projects in Orrisa, Jharkhand and W.Bengal would also be injected. For transfer of power beyond Raipur within WR, Raipur-Wardha- Aurangabad 765 kV 2xD/c lines were agreed to. Beyond Aurangabad power is proposed to be transferred through 765 kV Aurangabad-Padghe 765 kV D/C and Aurangabad- Dhule-Vadodra 765 kV S/C. For further dispersal of power at 400 kV, Aurangabad-Khargar 400 kV D/C (quad), Vadodra-Asoj 400 kV D/C

Minutes of 11th WRPC meeting held on 25th September 2009 at Raipur

8

(quad), Dhule – Nasik 400 kV D/C (quad), Dhule – Malegaon 400 kV D/C (quad) were proposed. Also interconnection at 400 kV between the proposed 765 kV substations at Dhule, Padghe, Vadodara, Raipur pooling stations, Raigarh (Kotra) Pooling Stations to the existing substations was agreed. Also for bulk transfer of power from eastern part of Western Region to western part of Western Region a + 600 kV, 4000 MW HVDC bipole between Raigarh pooling station (Kotra) to Dhule was agreed and for bulk transfer of power to NR + 800 kV, 6000 MW HVDC bipole between Champa pooling station and around Kurushetra in Haryana was agreed with 3000 MW, 800 kV HVDC terminals at Champa and Kurushetra with provision to upgrade the terminals to 6000 MW.

ii) For evacuation of power from IPP projects in Orissa it was agreed to pool power from various IPPs located in Orissa at three number 765/400 kV pooling stations at Jharsuguda, Dhenkanal and Angul. The proposed pooling stations would be interconnected through 765 kV 2xS/C ring network and for onward transfer of power to NR and WR it was proposed to inject power at new pooling station at Dharamjaygarh in Chhattisgarh through Jharsuguda pooling- Dharamjaygarh 765 kV 2x D/c lines. In the phased development of transmission pooling stations at Jharsuguda and Angul were agreed to be set up with the initial set of 7 no IPPs likely to materialise in Orissa, which are located near to these two pooling stations. These two pooling stations are initially proposed to be interconnected through 765 kV, 2x S/C line. For evacuation of power 2 no. 765 kV D/C lines from Jharsuguda to Dharamjaygarh were agreed, one D/C line is proposed to be associated with Orrisa IPP projects who have sought open access for transfer to WR/NR and the 2nd D/C line is proposed with IPP projects in SR who have sought open access for selling power to NR/WR. From Dhramjaygarh power will be transferred to Jabalpur pooling station through 765 kV 2xD/C lines. Of the two D/c lines one D/C is associated with Orrissa IPPs and the 2nd D/C line is proposed part of transmission system associated with Jharkhand IPPs and West Bengal projects who have sought open access for transfer of power to NR/WR. From Jabalpur pooling station power would be transferred to NR through the Jabalpur-Bina- Gwalior- Jaipur- Bhiwani 765 kV line. For transfer within WR Jabalpur-Bhopal-Indore- Vadodra 765 kV 1x S/C lines were agreed. The 765 kV Jabalpur-Bhopal-Indore section of line is covered with Orissa IPPs and 765 kV Indore-Vadodra section and Vadodra- Pirana 400 kV quad is covered with Madhya Pardesh generation projects and Chhattisgarh generation projects (pooled at Bilaspur). For IPP projects in Jharkhand and West Bengal in addition to the existing Ranchi-Sipat 400 kV and Ranchi-Sipat 765 kV S/c under construction a 765 kV Ranchi- Dharamjaygarh S/C line and a 765 kV Dharamjaygarh-Jabalpur 765 kV D/C line was agreed for transfer of power to NR/WR. For MP IPPs and Chhattisgarh IPPs (pooled at Bilaspur pooling station), Indore-Vadodra 765 kV S/C and Vadodra –Pirana 400 kV D/C quad lines were agreed to.

Accordingly, the transmission system evolved and agreed in the 29th SCM of WR held at Ahmedabad on 10th Sept 2009 associated with various IPP projects is as under:

Minutes of 11th WRPC meeting held on 25th September 2009 at Raipur

9

A. New IPP projects in Chattishgarh and the associated transmission system

Transmission System within WR associated with New IPP projects in

Chattishgarh

(i) Raipur Pooling station- Wardha 765 kV 2x D/C ( initially 1st D/c line to be operated at 400 kV)

(ii) Wardha- Aurangabad (PG) 765 kV 2X D/C (initially 1st D/c to be operated at 400 kV)

(iii) Aurangabad- Padge(PG) 765 kV D/C (iv) Aurangabad- Dhule (New) (PG) 765 kV S/C (Implementation by private

sector through tariff based competitive bidding route) (v) Dhule (New) – Vadodara (PG) 765 kV S/C (Implementation by private

sector through tariff based competitive bidding route) (vi) Establishment of 765/400 kV 2x1500 MVA substations at Dhule (New)

(Implementation by private sector through tariff based competitive bidding route)

(vii) Dhule (New) – Dhule (MSETCL) 400 kV D/C (quad) (Implementation by private sector through tariff based competitive bidding route)

(viii) Establishment of 765/400 kV 2x1500 MVA substations at Aurangabad and Padghe (GIS)

(ix) Aurangabad(PG)-Khargar 400 kV D/C (quad) (x) Padghe(PG)- Padghe 400 kV D/C (Quad) (xi) Vadodra-Asoj (GETCO) 400 kV D/C (Quad) (xii) Dhule (New) – Nasik (MSETCL) 400 kV D/C (quad) (Implemented by

private sector through tariff based competitive bidding route). (xiii) Dhule (New) – Malegaon (MSETCL) 400 kV D/C (quad) (Implemented by

private sector through tariff based competitive bidding route) (xiv) + 600 kV 4000 MW HVDC bipole between Raigarh pooling station (Kotra) –

Dhule (xv) 4000 MW , 600 kV HVDC bipole terminal each at Raigarh pooling station

(Kotra) and Dhule

Transmission System proposed for NR associated with New IPP projects in Chattishgarh

(i) + 800 kV 6000 MW HVDC bipole between Champa Pooling Station –

Around Kurushetra (NR) ( initially to be operated at 3000 MW) (ii) 3000 MW , 800 kV HVDC bipole terminal at Champa pooling station and

Around Kurushetra with provision to upgrade the terminals to 6000 MW (iii) Kurushetra- Jallandhar 400 kV D/C (Quad) ( one ckt via Nakodar S/S) (iv) LILO of Abdullapur- Sonepat 400 kV D/C (triple) at Kurushetra (v) Establishment of 400/220 kV , 2x500 MVA substation at Kurushetra

Pooling Stations along with their interconnections for New IPP projects in Chattishgarh

(i) Raigarh Pooling Station (Kotra)- Raipur Pooling station 765 kV D/C ( intially

to be operated at 400 kV) (ii) Raigarh Pooling Station (Kotra)- Champa Pooling station 765 kV S/C

Minutes of 11th WRPC meeting held on 25th September 2009 at Raipur

10

(iii) Champa Pooling station- Raipur Pooling station 765 kV D/C ( initially to be operated at 400 kV

(iv) Raigarh Pooling station (Kotra)- Raigarh Pooling station (Tamnar) 765 kV D/C (initially to be operated at 400 kV )

(v) Champa Pooling station – Dharamjaygarh 765 kV S/C (vi) Establishment of 765/400 kV pooling stations at Raigarh (near Kotra),

Raigarh (near Tamnar), Champa, and at Raipur (the pooling stations will be initially at 400 kV and later upgraded to 765/400 kV).

(vii) Raigarh Pooling Station (Kotra) - Raigarh existing 400 kV D/C (to be kept open at a later date).

(viii) Raipur Pooling Station – Raipur existing 400 kV D/C (to be kept open at a later date)

Note: At present only Jindal Power project is connected to Raigarh (Tanmar). Jindal Power is yet to get coal linkage. Therefore the implementation of Raigarh(Tanmar) pooling station will be linked with the progress of works at Jindal power.

Dedicated transmission System up to pooling point under the scope of Project Developer for generation projects in Raigarh Complex

RKM Powergen Ltd.(4x360MW)

(i) RKM Powergen – Raigarh Pooling Station (near Kotra) 400kV D/c(Quad)

Athena Chhattisgarh Power Ltd. (2x600MW)

(i) Athena Chhattisgarh – Raigarh Pooling Station (near Kotra) 400kV D/c(Quad)

Jindal Power Ltd.(4x600MW + 1x500MW)

(i) Jindal Power – Raigarh Pooling Station (near Tamnar) 400kV 2xD/c (Quad) along with 765/400kV 3x1500MVA transformers at Raigarh Pooling station (Tamnar)

SKS Ispat & Power Ltd.(4x300MW)

(i) SKS Ispat - Raigarh Pooling Station (near Kotra) 400kV D/c(Quad/Triple)

Korba(West) Power Ltd.(1x600MW)

(i) LILO of Athena Chhattisgarh – Raigarh Pooling Station 400kV D/c at Korba(W)

DB Power Ltd.(2x600MW) (i) DB Power – Raigarh Pooling Station (near Kotra) 400kV D/c (Quad/Triple)

Dedicated transmission System up to pooling point under the scope of Project Developer for generation projects in Champa Complex

Wardha Power Ltd.(6x600MW)

(i) Wardha Power – Champa Pooling Station 400kV 2xD/c (Quad) along with 765/400kV 3x1500MVA transformers at Champa Pooling Station.

Balco Ltd.(4x300MW)

(i) Balco – Champa Pooling Station 400kV D/c (Quad/Triple)

Vandana Vidyut Ltd. (2x135 + 1x270MW)

(i) Vandana Vidyut – Champa Pooling Station 400kV D/c

Lanco Amarkantak Power(2x660MW)

(i) Lanco - Champa Pooling Station 400kV D/c (Quad)

Chhattisgarh Steel & Power Ltd. (1x35+1x250MW)

(i) LILO of Vandana Vidyut – Champa Pooling Station 400kV D/c at CSPL

Interim arrangement for connectivity of projects coming prior to

availability of transmission*

Minutes of 11th WRPC meeting held on 25th September 2009 at Raipur

11

Balco Ltd. (i) LILO of both circuits of Korba - Birsinghpur 400kV D/c at Balco

RKM Powergen Ltd. (i) LILO of Rourkela- Raigarh 400kV D/c at RKM Powergen Vandana Vidyut Ltd (i) LILO of one ckt of Korba – Birsingpur 400kV D/c at

Vandana Vidyut

*Above arrangement is temporary till the corresponding generation project gets interconnected at the identified pooling station.

B. Madhya Pradesh Generation Projects and Chattishgarh Generation Projects (pooled at Bilaspur Pooling Point)

System strengthening common for WR associated with above

generation projects

(i) Indore - Vadodara 765kV S/c (ii) Vadodara – Pirana 400kV D/c(Quad) (iii) Establishment of 765/400kV 2x1500MVA Vadodara substation

Dedicated transmission System up to pooling point under the scope of Project Developer

Maruti Clean Coal & Power Ltd. (300 MW)

(i) Maruti – WR Pooling Station(Bilaspur) 400 kV D/c (ii) Two nos of 400kV bays at WR Pooling Station ( Bilaspur)

Dheeru Powergen (450MW) and PTC India(600MW)

(i) Dheeru Power Gen – WR Pooling Station (Bilaspur) 400 kV D/c (high capacity)

(ii) Two nos of 400kV bays each at WR Pooling Station (Bilaspur) Jaiprakash Power Ventures Ltd. (1320MW)

(i) Jaiprakash – Satna 400kV D/c (high capacity) (ii) Two nos of 400kV bays at Satna(POWERGRID)

Aryan Coal Benefications Pvt. Ltd. (1200MW)

(i) Aryan Coal – Vindhyachal Pooling Station 400kV D/c (high capacity)

(ii) Two nos of 400kV bays at Vindhyachal Pooling Station (iii) 1X 1500 MVA, 765/400 KV transformer at Vindhyachal

Pooling Station ( to be reviewed in light of 400 kV D/C interconnection between Vindhyachal pool and Sasan)

C. Orissa IPP Projects

System strengthening common for WR and NR associated with Orissa IPPs

(i) Establishment of 765kV switching substation at Dharamjaygarh (ii) Establishment of 2x1500 MVA, 765/400kV Jabalpur Pooling Station (iii) Jharsuguda Pooling Station – Dharamjaygarh (WR) 765kV D/c (iv) LILO of Ranchi – Sipat (Bilaspur) PS 765kV S/c line at Dharamjaygarh (v) Dharamjaygarh – Jabalpur Pool 765kV D/c line (vi) Jabalpur Pooling station – Jabalpur 400 kV D/c (high capacity) (vii) Jabalpur Pooling station – Bina 765kV D/c line (viii) Bina – Gwalior 765kV S/c (3rd circuit)

Minutes of 11th WRPC meeting held on 25th September 2009 at Raipur

12

System strengthening in WR associated with Orissa IPPs.

(i) Establishment of 2x1500MVA, 765/400kV Bhopal Pooling Station ( Implementation by private sector through tariff based competitive bidding route)

(ii) Jabalpur Pooling station – Bhopal 765kV S/c ( Implementation by private sector through tariff based competitive bidding route)

(iii) Bhopal – Indore 765kV S/c (Implementation by private sector through tariff based competitive bidding route)

(iv) Bhopal New substation – Bhopal (M.P.) 400kV D/c (high capacity) (Implementation by private sector through tariff based competitive bidding route)

System strengthening in NR associated with Orissa IPP. (i) Gwalior - Jaipur 765kV S/c line (ii) Jaipur - Bhiwani 765kV S/c line

Pooling Stations along with their interconnections for IPPs in Orissa (i) Establishment of 765/400kV Pooling Station at Jharsuguda (ii) Establishment of 765/400kV Pooling Station at Angul (iii) Angul Pooling Station – Jharsuguda Pooling Station 765kV 2xS/c (iv) LILO of Rourkela – Raigarh 400kV 1xD/c at Jharsuguda Pooling station (v) *LILO of Meramundali – Jeypore 400kV S/c line at Angul pooling station (vi) *LILO of one ckt of Talcher - Meramundali 400kV D/c line at Angul pooling

station. * Interim arrangement. LILO to be removed after establishment of 765 kV pooling station at Angul

Dedicated transmission System up to pooling point under the scope of Project Developer for Orissa IPPs

Sterlite (2400 MW) (i) Sterlite- Jharsuguda Pooling station 400 kV D/C line

with associated bays Ind- Barath(700 MW)

(i) Ind-Barath- Jharsuguda Pooling station 400 kV D/C line with associated bays

Jindal Thermal (1200 MW)

(i) Jindal Thermal- Angul Pooling station 400 kV D/C line with associated bays

Monnet (1050 MW)

(i) Monet- Angul Pooling station 400 kV D/C line with associated bays

GMR (1050 MW) (i) GMR- Angul Pooling station 400 kV D/C line with associated bays

Lanco Babandh (2640 MW)

(i) Lanco Babandh- Angul Pooling station 400 kV 2XD/C line with associated bays

(ii) 3X1500 MVA, 765/400 kV transformers at Angul along with associated bays

Navbharat Phase-I (1050 MW)

(i) Navbharatl- Angul Pooling station 400 kV D/C line with associated bays

Minutes of 11th WRPC meeting held on 25th September 2009 at Raipur

13

D. Jharkhand and West Bengal IPP Projects System strengthening, common for WR and NR associated with IPP

Projects in Jharkhand and West Bengal Generation projects

(i) Ranchi - Dharamjayagarh 765kV S/c (ii) Dharamjaygarh – Jabalpur 765kV D/c (2nd line) ( Implementation by

private sector through tariff based competitive bidding route)

Member (PS), CEA stated that the above transmission system is to be built in phases depending upon the progress of various IPPs. The interim arrangement of providing of LILOs of the existing lines is a temporary transmission arrangement for power transfer on short term basis. The corresponding LILO shall be removed and the line shall be restored to its original configuration by the respective developer, after interconnection of the generation project at the identified Pooling Station. He further stated that till the generators identify the beneficiaries; the risk of payment of transmission charges will be borne by the generators for which they will have to open LC. He further stated that there were certain modifications with respect to the network earlier evolved and the modifications mainly were 765 kV 2xD/c lines instead of 400 kV links upgradable to 1200 kV in future between Raipur- Wardha-Aurangabad interlinking of Champa pooling station in Chhattisgarh with Dharamjaygarh instead of Bilaspur pooling Station. In regards to the query regarding the change in earlier proposal of ±600 kV, 4000 MW HVDC from Raigarh to Vadodara to now from Raigarh to Dhule, Member (PS), CEA stated that based on the discussions and inter action with GETCO, it is understood that Gujarat had signed MOU with number of IPPs for setting up of generation projects in the State and accordingly the same was reviewed and therefore is now proposed at Dhule which is a major load centre. In regard to proposal connectivity with 400 kV D/c line to Kharghar, Member (PS) requested MSETCL to expedite to intimate change/ modification if any at the earliest. He requested the WRP Committee to concur the schemes as proposed associated with various IPPs listed under A, B, C & D. Chairman, WRPC/GSECL while stressing for a broader approach in the interest of building up of strong National grid network said that minor modifications may become necessary in the proposed transmission schemes under the finalization stages while carrying out finer adjustments so as to evolve optimum system without constraints. He therefore, requested to ensure that the transmission schemes are in place for power evacuation of various upcoming IPPs. The matter was discussed and WR Power Committee gave the concurrence for implementation of the above proposed transmission schemes accordingly.

Minutes of 11th WRPC meeting held on 25th September 2009 at Raipur

14

3.2 Transmission system associated with Mauda (2X500 MW) generation project of NTPC

Member (PS), CEA stated that during the 29th Standing Committee Meeting on Power System Planning of WR held on 10th Sept. 2009 at Ahmedabad, the transmission system earlier proposed for this project in the 28th SCM held on 6.12.2008 was reviewed and it was decided that Mauda- Nagpur South line could be directly taken to Wardha instead of via Naqpur thus eliminating the need for Nagpur South substation. The revised associated Transmission system for Mauda generation project as agreed during the 29th SCM is as under: Mauda – Wardha 400kV D/C (Quad) Mauda – Khaperkheda (MSETCL) 400kV D/C (Quad)

WRP Committee concurred with the above transmission system.

3.3 Transmission System associated with Vindhyachal-IV (1000MW) and

Rihand-III (1000MW) generation projects of NTPC Member (PS), CEA stated that the transmission system associated with Vindhyachal-IV and Rihand-III was agreed during the 28th SCM and Special meeting of the SCM held on 18th April 2009. During the Special SCM it was decided that connectivity with Sasan both at 400 kV and 765 kV would be reviewed based on studies. During the 29th the same was discussed and connectivity both at 765 kV and 400 kV was agreed. The revised transmission system associated with Vindhyachal- IV and Rihand-III is as under:

Part-I: Generation specific transmission system (to be implemented by PGCIL)

A : Rihand-III: For NR only Rihand-III – Vindhyachal Pooling Station 765kV 2xS/c (initially to be

operated at 400kV) B : Vindhyachal-IV: For WR only

Vindhyachal-IV – Vindhyachal Pooling Station 400kV D/c (Quad)

Part-II: Common System: For both WR and NR Vindhyachal Pooling Station – Satna 765kV 2xS/c(initially to be operated at

400kV) Satna – Gwalior 765kV 2xS/c Sasan – Vindhyachal Pooling Station 765kV S/c Sasan – Vindhyachal Pooling Station 400kV D/c Establishment of 765/400kV 2x1500MVA S/s at Vindhyachal Pooling Station

Note: In order to reduce the short circuit levels, under Sasan transmission it has been decided to delete the LILO of Vindhayachal STPP – Jabalpur 400 kV D/C at Sasan subsequent to development of 765 kV system from Sasan. One of the LILO line would be retained at Sasan with suitable switching arrangements at Sasan 400 kV switchyard to meet its starting power requirements in future. The LILO of the other ckt would be bypassed

Minutes of 11th WRPC meeting held on 25th September 2009 at Raipur

15

and the 400 kV bays at Sasan would be utilized for Vindhyachal Pool-Sasan 400 kV D/C line to be terminated at Sasan.

Part-III: NR Strengthening in Regional pool Gwalior – Jaipur 765/400 kV S/c. Jaipur (RVPN)-Jaipur (Bassi) 400 kV D/c (Quad)

WRP Committee concurred with the above transmission scheme.

3.4 Connectivity of proposed 220/132 kV substations at Raigarh and Kumhari of Indian Rlys with existing Raigarh S/s of PGCIL for wheeling of power from Nabinagar generation project in ER to their traction substation in Chhatisgarh

GUVNL representative raised the issue concerning granting connectivity of proposed 220/132 kV substations at Raigarh and Kumhari of Indian Railways with existing Raigarh S/s of PGCIL for wheeling of power from Nabinagar generation project in ER to their traction substation in Chhattisgarh during 29th SCM held at Ahmedabad on 10th Sept. 2009. PGCIL informed that Railway Electrification, Bhubaneshwar has proposed to wheel power from Railways 1000 MW generation project at Nabinagar in ER, being developed by Bharat Rail Bijli Co. Ltd. (BRBCL) to Chhattisgarh through ISTS network. The power supply would be availed at 220 kV level by constructing 220/132 kV substations one each at Raigarh and Raipur and connecting these to PGCIL 220kV Raigarh and Kumahari(Raipur) S/s respectively. The Long term open access has been granted to Bharat Rail Bijli Co. Ltd. (Nabinagar generation project) for transfer of 990 MW. Target beneficiaries Indian Railways (ER: 355 MW, WR: 485 MW, NR: 50 MW) and BSEB (100 MW). The target drawal of 130 MW in Maharashtra, 95 MW in Chhattisgarh, 185 MW in Madhya Pradesh and 75 MW in Gujarat has been indicated by Indian Railways in WR. Member (PS), stated that the above matter was discussed During the 29th meeting of Standing Committee and as a special case the proposal of for connectivity to proposed 220/132 kV at Raigarh and Kumhari of Indian Rlys with existing Raigarh S/s of PGCIL has been agreed. GUVNL representative stated that if the Railways draws the power through State transmission network it would be in order. However, agreeing to the above proposal of Railways will amount to direct connectivity with CTU and might set an improper precedence and may involve payment of cross subsidy surcharge to the concerned State by the above utility. Chairman, WRPC/GESCL remarked whether allowing the connectivity to the Railways as a special case mentioned above would be feasible contrary to the CERC regulations. He, therefore, suggested that Railways might approach CERC and based on the outcome their proposal for connectivity of 220/132 kV at Raigarh and Kumhari of Indian Rlys with existing Raigarh S/s of PGCIL for wheeling of power from Nabinagar generation project in ER to their traction

Minutes of 11th WRPC meeting held on 25th September 2009 at Raipur

16

substation in Chhatisgarh may be examined. He requested PGCIL to take the needful action. PGCIL agreed to the same. ITEM No. 4: FREE GOVERNOR MODE OF OPERATION ON ALL GENERATING

UNITS INSTALLED Having specific regard to the prevailing condition of shortage, the Hon’ble CERC in Petition No.-66/2003 in the matter of free governor mode of operation of generating units etc. have directed the implementation of only restricted governor operation in various types of thermal and hydro units: The schedule for implementation is

Type Category To be implemented by Software based EHG system

1.03.2010 KWU & LMZ turbines for thermal sets of 200 MW and above Hardware based EHG

system where boiler controls are in “ Auto”

1.06.2010

Hydro units of 10 MW and above

- 1.03.2010

• All the generating companies are directed by Hon'ble CERC to place before the

Commission, within a month, their action plan in line with the above schedule and furnish monthly progress reports to the Commission in this regard.

• The Staff shall initiate suitable amendment to para 1.6 of IEGC and submit the

same for Commission’s approval within a month.

The Committee noted as above. ITEM No.5: WIDE AREA MEASUREMENT SYSTEM (WAMS) IN WR 5.1 Member Secretary, WRPC stated that In the TCC meeting of WR held on 29th May 2009 at Diu the matter regarding implementation of Wide Area Measurement System (WAMS) in WR was discussed, wherein PGCIL had made a presentation on CSIR approved project under their New Millennium India Technology Leadership Initiative programme namely, “Intelligent monitoring & Control of the interconnected Power Grid using Wide Area Measurements (WAM)”. As this project is of high/new technology area, the TCC had recommended therein that the technical details etc. of the project may be discussed in a meeting of all the constituents of WR at working level and thereafter the matter should be put up to TCC/ WRPC for further direction. The matter was further deliberated in detail in the 10th meeting of WRP Committee held on 30th May 2009. The WRP Committee had agreed to the above recommendation of TCC. It was decided that technical details of the project may be discussed in the Regional Protection Committee meeting and hereafter the matter will be put up to TCC / WRPC for further direction.

Minutes of 11th WRPC meeting held on 25th September 2009 at Raipur

17

5.2 He stated that accordingly, the matter was deliberated in the 105th meeting of Protection sub-Committee of WRPC held on 18th June 2009. In the meeting the features of the WAMS project proposed by PGCIL and IIT –B were presented. The members expressed that they would go through to examine the details and would intimate their observations and views on the same. The comments on the above proposal submitted were received from MPPTCL, GETCO and MSETCL. In this regard, CEA had held a separate meeting in New Delhi on 21.7.2009, which was attended by representatives from CSIR, CPRI, PGCIL and CEA. The record note of the proceedings of the same received by WRPC was circulated to WR constituents for information. The matter was further discussed in 106th meeting of Protection sub-Committee of WR held on 1st & 2nd September 2009, wherein MSETCL also made presentation regarding the WAMS project already taken up by them in MSETCL Grid on pilot basis in association with CPRI - Bangalore and IIT- Kanpur. The Protection sub-Committee members felt that the WAMS project proposed by PGCIL might require inclusion in the scheme a facility to enable availability of PMU data to the WR constituents, which is presently not envisaged in the pilot project proposal of PGCIL. After discussions in the meeting, the Protection sub-Committee suggested PGCIL to provide clarifications to certain queries relating to data routing, extent of data sharing by the participating agencies and their role, technical capability and locations identified for the proposed 25-30 PMUs to be installed under existing scope of the above Pilot project and detailed break up of the total cost estimates on the project. In the above context, GM I/c (LD&C) vide letter dated 8th September 2009, furnished the information in respect of the queries raised by the WR constituents as above. The financial details, break-up of cost of PGCIL portion location of PMUs intimated by PGCIL etc. has been furnished by PGCIL vide above referred letter dated 8.9.09 which is enclosed at Annexure- 5.2.

a) Financial Details- Total Cost of project is Rs. 16.75 Crs.: PCGIL – 8.76 Crs; TCS- 3.77 Crs.; Tata Power, 1.44 Crs. and IIT-B- 2.77 Crs. through grant.

b) Break up of PGCIL Rs. 8.76 Cr. portion - Phasor Measurement Units

(PMUs)- 3.24 Crs.; Control Center Hardware, Software & Communication System- 3.47 Crs.; Installation, Testing & Commissioning Services – 0.93 Crs.; Miscellaneous including Field Trials 1.12 Cr.

c) PMU Locations (indicative) – MP, Maharashtra and Gujarat – 6 each; Chhatisgarh-4, Goa -2 and DNH-1

5.3 He said that as further desired by the constituents, a Special Meeting was held for discussions on WAMS on 17th September 2009 at Mumbai. Representatives from constituents of GETCO, MSETCL, MPPTCL, CSPTCL, POWERGRID, Torrent Power, Tata Power, Reliance Energy, WRLDC and WRPC attended the meeting. The technical details of WAMS were discussed in detail and the brief outcome of the discussions are as follows:

a) MSETCL representative stated that Maharashtra is already implementing a project of installing PMU / WAMS in their system.

Minutes of 11th WRPC meeting held on 25th September 2009 at Raipur

18

b) GETCO, MPPTCL and CSTCL representatives were of the view that the implementation of WAMS should be done at a regional level as proposed by POWERGRID.

c) So far as the proportionate sharing of the cost of Rs 8.76 cr by Maharshtra is

concerned, Maharashtra stated that they will not be able to share the same as they are already implementing the WAMS project in their system.

d) Regarding installation of PMUs in MSETCL system under the proposed regional

WAMS project and utilization of the MSETCL installed WAMS PMU data in Maharashtra system, MSETCL representative had stated that they would revert back.

e) Constituents suggested that the expenditure of Rs 8.76 cr for the above project may

be met from the UI cap fund as the project is for system improvement. WRLDC clarified that this will be subject to the approval of CERC.

f) It was suggested to form a PMU group at the RPC level comprising of

representatives of Protection groups from all the constituents of WR, that will look into the analysis of correct/incorrect operation of protection relays during line trippings and other grid disturbances using input from WAMS data which is in milliseconds time frame, study of stability related issues by study group etc. At present the data routing was envisaged at RLDC levels. Hence the data routing should be such that the WAMS PMU data is available to the Protection and Study groups both at the State as well as RPC level. The necessary details of data routing to the SLDC / WRLDC/ Protection and Study PMU groups can be finalized accordingly.

g) It was also suggested that Task Force from the representatives of WR constituents

may be formed which would monitor the progress of the implementation of the proposed WAMS project.

h) Constituents felt that the continuous real time data (24 x 7) should not be provided in

view of the commercial implications. POWERGRID representative agreed to discuss the same with IIT-B and revert back. The data sharing by IIT-B in the above pattern may be during the project implementation duration period only.

5.4 Member Secretary, WRPC stated that the TCC in its meeting held on on 24th Sept. 09 discussed the matter and was agreed that WAMS in WR will be implemented on integrated regional basis. MSETCL will also be the part of this regional WAMS. Above recommendations were further discussed by the WR Power Committee. GM I/C(LD&C), PGCIL informed that the POWERGRID proposed project is a Regional Project. This WAMS project is approved by CSIR (Council of Scientific & Industrial Research) under New Millennium India Technology Leader Initiative (NMITLI), which is a step to promote development of indigenous technology. In this project around 25 no. of PMUs shall be installed at substations/generating stations in the Western Region. The location of PMUs shall be decided in consultation with IIT Bombay who is one of the partners of the consortium. Other consortium partners are TCS and Tata Power. The estimated cost of the project is Rs. 16.75 Crores. POWERGRID share of total estimated cost of the project is Rs. 8.76 Crores. The POWERGRID Share of project

Minutes of 11th WRPC meeting held on 25th September 2009 at Raipur

19

cost is for installation of PMUs, Hardware/software at WRLDC etc. The data generated by PMUs shall be available at WRLDC and shall be used by the WRLDC for grid operation as and when they are commissioned. CSIR shall provide soft loan at an interest rate of 3% for implementation of the project, which shall be repaid over a period of ten years in annual installments. The Project completion time has been envisaged as two years for development followed by one year for performance monitoring. Balance amount of the project cost (Rs 7.99 Crs) would be given by CSIR to IITB as grant and as loan to TCS and Tata Power. Tata Power shall be responsible for providing five no of PMUs in Western region. The responsibility for development of software analytics is with IITB and TCS. Developed software shall be used by WRLDC for grid operation. The developed software also has the potential to generate the revenue through IPR, which shall be shared among the Project partners and CSIR. ED (WRLDC) informed that the proposed project is a regional project like any other transmission project of POWERGRID and the benefit would be to all the constituents by way of improved grid operation, and therefore all the constituents should agree for its implementation by POWERGRID. ED (WRLDC) proposed that the UI cap fund can be utilized for repayment of POWERGRID portion of CSIR loan. Chairman, WRPC suggested MSETCL to join the POWERGRID proposed CSIR approved WAMS project as this being a Regional Project and cost of funding is also very low (@3% interest). Member (Power System), CEA informed that the MSETCL project is in the proposal stage only in the National perspective plan for R&D in power sector. The fund under National perspective plan is limited, which is allotted to projects on first come first serve basis. The MSETCL proposal is at 33rd position in the priority list of the projects already proposed for funding under National perspective plan. Member (Power System), CEA also suggested MSETCL to join the POWERGRID proposed Regional WAMS project. After deliberations the WR Power Committee agreed to the above recommendations of the Special meeting held o 17th Sept 2009. Regarding points (a) to (d) of the recommendations above it was agreed that MSETCL shall join POWERGRID proposed Regional WAMS Project. MSETCL however requested that participation of their officials should be ensured in the proposed WAM project at regional level, which was agreed. It was therefore agreed to form a PMU group at RPC level comprising of representatives of Protection groups from all the constituents & WRPC. Under the project proposal the data routing is envisaged only at RLDC level. During deliberations it was further agreed that WAMS PMU data shall be made available at SLDCs, RPC and PMU study groups also. Any additional expenditure incurred to make the PMU data available at SLDC/RPC, shall be separately put up for approval.

In view of above the WR Power Committee approved the implementation of WAMS Project in WR proposed by POWERGRID with consortium partners TCS, IIT Bombay & Tata Power Company limited and repayment of the loan from CSIR shall be through UI cap fund. WRLDC shall approach CERC for necessary approval. In case of non-approval from CERC, the matter will be placed before WRP Committee for further direction. PGCIL/WRLDC may proceed accordingly.

(Action: PGCIL/WRLDC)

Minutes of 11th WRPC meeting held on 25th September 2009 at Raipur

20

ITEM No. 6: PGCIL PROPOSAL FOR REPLACEMENT OF OLD PLCC PANELS

Member Secretary, WRPC stated that the proposal made by WRTS-I, PGCIL vide letter dated 19th June 2009 for (a) replacement of old PLCC Panels type ETI, NSD 60 (30 Nos.), (b) replacement of battery bank at Raipur (4 Nos.), Bhadrawati both AC and DC (10 Nos.), Mapusa (4 Nos.), Boisar (4 Nos.), (c) replacement of switchyard equipment due to higher fault level, (d) replacement of transformer oil of 13 No. converter transformers at HVDC Bhadrawati, (e) procurement of long term HVDC spares & (f) procurement of insulator washing equipments was discussed in 106th meeting of Protection sub-Committee of WRPC held on 1st & 2nd Sept., 2009 at WRPC, Mumbai. The Protection sub-Committee suggested that all utilities including PGCIL may replace the old PLCC Panel (make ABB type ETI, NSD 60) as a number of mal-operations are reported due to poor performance of these panels and ABB is not giving the required service support. The Protection sub-committee also recommended replacement of old PLCC Panels type ETI, NSD 60 (30 Nos.) proposed by PGCIL at an estimated cost of Rs. 1.5 Crores. and suggested that the same may be placed before WR Power Committee in this TCC/WRPC meeting for approval The matter was deliberated in the TCC meeting held on 24th Sept. 09 and the TCC suggested that as the procurement of above equipment is to be considered under additional capital expenditure, PGCIL may approach CERC directly for necessary approval of the same accordingly. WRP Committee agreed to the suggestion of the TCC and requested PGCIL to approach CERC.

(Action: PGCIL)

ITEM No.7: TRANSMISSION CHARGES FOR WHEELING OF CENTRAL SECTOR POWER TO DD & DNH THROUGH GETCO TRANSMISSION SYSTEM AND THE BILLING MECHANISM

7.1 Member Secretary, WRPC intimated that on Petition No. 64/2008 and No. 67 / 2008 in the matter of fixation of and adjudication on the transmission charges for use of the Gujarat transmission system for conveyance of Central Sector power to UT of DD & DNH under sections 62 and 79 of the Electricity Act, 2003 and in the matter of Gujarat Energy Transmission Corporation Ltd., the Hon’ble CERC issued final order on 31st July 2009. The Commission directed that the charges applicable for the period 01.04.2004 to 31.03.2009 in accordance with the above order shall be shared in the manner decided in Commission’s order dated 03.02.2009 i.e. as per the existing practice. WRPC Secretariat had accordingly revised the concerned statement of monthly REAs for the year 2004-05 to 2008-09 based on above directions of CERC. The Commission also directed that w.e.f. 01.04.2009 Member Secretary, WRPC shall calculate the charges payable for use of GETCO System in the same manner and shall be shared by WR Constituents as decided earlier by order-dated

Minutes of 11th WRPC meeting held on 25th September 2009 at Raipur

21

03.02.2009. The parties are at liberty to approach the Commission for resolving disputes, if any regarding calculation / payment of charges in accordance with law. In the TCC meeting held on 24th Sept. 09, GETCO informed that they are in the process of filing a petition with the Appellate Tribunal for reviewing of CERC order. TCC suggested that since there is no direction from ATE as of now, the fixation of the transmission charges for use of the Gujarat transmission system for conveyance of Central Sector power to UT of DD & DNH, should be done as per the CERC order dated 31.7.2009. WRP Committee noted the same.

7.2 Member Secretary, WRPC stated that during the 10th Meeting of WR Power Committee held on 30th May 2009 the matter regarding billing of transmission charges for wheeling the C.S. Power to UTs of DD & DNH was discussed and it was decided that till such time, any order is issued by the Hon’ble CERC in respect of determination of transmission charges for GETCO System for wheeling the C.S. power to DD & DNH, the present methodology of billing the transmission charges through PGCIL should be continued and the same would facilitate adjustment / recovery of transmission charges due, if any, as the entire record and billing details are available with PGCIL. Subsequently on issue of specific orders by Hon'ble CERC in the matter, the billing of transmission charges in respect of above might be done by GETCO / MSETCL directly, as per REA issued by WRPC.

As the Hon'ble CERC have now issued order dated 31st July 2009 in respect of determination of transmission charges for GETCO System for wheeling the C.S. power to DD & DNH, the matter regarding billing the wheeling charge came up for discussion in 53rd meeting of Commercial sub-Committee of WRPC held on 8th Sept. 09. Representative of MSETCL in the meeting had opined that mechanism for payment of charges towards wheeling the C.S. power to Goa and UTs of DD & DNH was earlier agreed on account of non- connectivity of their respective systems with CTU network because it is the responsibility of CTU to arrange connectivity of the beneficiaries' systems to the ISTS to transmit C.S. power to the beneficiary States. Therefore, the present arrangement of billing of transmission charges in respect of MSETCL / GETCO for transmitting of C.S. power to Goa/DD&DNH through PGCIL, should be continued. GETCO/GUVNL and rest of WR constituents including Goa had also endorsed the above opinion of continuing with the present arrangement. However, PGCIL representative stated that for continuing the existing practice of billing, some working arrangement along with necessary agreement with MSETCL and GETCO would be required to be in place. It was therefore suggested by the Commercial sub-Committee that the matter may to be discussed in the TCC / WRPC for further directions.

The matter was deliberated in the TCC meeting held on 24th Sept. 09 and TCC opined that existing arrangement. of billing of transmission charges in respect of MSETCL / GETCO for transmitting of C.S. power to Goa/DD&DNH through PGCIL monthly billing system should be continued. However, PGCIL representative stressed that for continuing the existing practice of billing, some working arrangement along with necessary agreement with MSETCL and GETCO would be required to be in place.

Minutes of 11th WRPC meeting held on 25th September 2009 at Raipur

22

The matter was deliberated and WRP Committee agreed to the above suggestion of TCC and requested PGCIL to continue with the present arrangement.

ITEMS FOR INFORMATION ITEM No.8: ANTICIPATED POWER SUPPLY POSITION IN WESTERN

REGION FOR THE PERIOD FROM SEPT. 09 TO NOV. 09 The anticipated power supply position in the region for the period from September, 2009 to November, 2009 commences with the onset of Rabi season. During this period the regional demand is likely to be rise considerably. As per estimates, the unrestricted regional demand would vary from 36400 MW to 40220 MW and deficit will vary from 12.79 % to 18.80 %. In terms of energy, the unrestricted requirement would vary ranging from 22870 MUs to 25670 MUs with regional deficit remaining in the order of 9.39% to 13.80%. The anticipated Peak demand shortage of 870 to 1500 MW in Gujarat, 130 to 210 MW in Chhattisgarh, 3550 to 5020 MW in Maharashtra, 1190 to 1660 MW in Madhya Pradesh, 30 to 40 MW in Goa, 30 to 35 MW in DD&DNH is likely to prevail. All WR constituent states shall have to ensure maximum availability of transmission system by taking necessary steps to minimize frequent tripping of EHV lines. Also, monthly programme for maintenance of the generating units shall require to be scheduled appropriately so as to ensure maximum availability of online generation capacity considering the regional demand and diversity in demand of NR and ER in an integrated combined N-E-W grid.

The Committee noted the same. ITEM No.9: SIGNING OF PPA WITH RGPPL AND ITS SCHEDULING Member Secretary, WRPC stated that this issue had earlier been discussed in Commercial Committee Meeting and WRP Committee meeting in the past and RGPPL were accordingly requested to take the matter with their management in expediting early signing of PPA, to enable scheduling of 5% capacity of RGPPL power, to the concerned beneficiaries as per MoP order i.e. 1.5 % each to DD & DNH and 1% each to Goa and Madhya Pradesh. During the last TCC meeting held on 29th May 2009 at Diu, Special Secretary (P), UTs of DD & DNH expressed their concern and again raised the above matter. This was also deliberated in the 10th meeting of WRP Committee held on 30th May 2009 wherein RGPPL were requested to take urgent steps for scheduling of the above allocated power immediately. Representative of RGPPL in the meeting stated that they would look into the matter and revert back. In the Commercial Committee Meeting held on 8th September 2009, RGPPL representative stated that this matter is put up to their Board, which is meeting shortly.

Minutes of 11th WRPC meeting held on 25th September 2009 at Raipur

23

RGPPL representative stated that they would intimate the position for expediting the signing of PPAs with beneficiaries in this regard in a week’s time within which RGPPL’s Board meeting is likely to be held. ITEM No. 10: LTSA ARRANGEMENT FOR SCADA / EMS UNDER WR ULDC

SCHEME 10.1 Member Secretary, WRPC stated that the matter regarding the need for going in for a comprehensive Long Term Service Agreement (LTSA) for the ULDC project broadly covering the scope of SCADA / EMS / DTS software as well as hardware at ten control centers commissioned under the ULDC project has been discussed in earlier meetings of WRP Committee. During the last 10th meeting of WRPC the matter was deliberated in detail. The WRP Committee agreed for LTSA through OEM route and decided that senior level officers of WR constituents would also interact with M/s GE for further negotiation, if any. It was tentatively proposed to have the meeting of WR constituents with M/s GE on 9th June, 2009 and Member Secretary, WRPC would coordinate the same. It was also agreed that after the negotiation with M/s GE at the senior level, WRLDC/PGCIL would go ahead with awarding of maintenance of SCADA/EMS system in Western Region to M/s GE and LTSA arrangements with them. The WR constituents further opined that replacement action for the new system should be initiated before the end of three year period so that the new system could be in place by the end of the LTSA period. PGCIL agreed to take necessary action in this matter. 10.2 As directed by the WRP Committee, the discussions regarding LTSA arrangement for SCADA / EMS of WR were held on 9th June 2009 and after prolong discussions and two rounds of negotiations with M/s. GE, the OEM, the following was agreed:-

i) M/s. GE would submit an offer on 10th June, 2009 for five years LTSA with exit option after three years. M/s GE stated that in case of exit option extra payment for demobilization at 10% on the remaining two-year cost of LTSA may have to be paid.

ii) M/s. GE would provide necessary support and technical assistance in replacing the existing system with system supplied by any other vendor including M/s. GE during the contract period.

iii) M/s. GE agreed for (1) and (2) above. iv) As the present SCADA / EMS system is unattended so far as

maintenance is concerned, PGCIL was requested to take urgent steps in placement of the order so as to ensure secured and uninterrupted monitoring / operation of the system. PGCIL agreed to take necessary action.

10.3 Accordingly, WRLDC vide letter dated 2.09.09 confirmed that the LTSA arrangement for the WR SCADA / EMS systems installed under ULDC project have been concluded and the works of Long Term Support Arrangements for all ten control centers have been awarded to M/s. GE as below and is effective from August 14, 2009:

i) Vide LOA No. WRLDC/CON/WC-835 (off shore)/09-1556 dated August 13, 2009 for the Off shore portion of the services at an award value of US $ 21,42,857 for 05 years.

Minutes of 11th WRPC meeting held on 25th September 2009 at Raipur

24

ii) Vide LOA No. WRLDC/CON/WC-834 (On-shore)/09-1556 dated August 13, 2009 for the On-Shore portion of the services at an award value of INR 22, 00, 00,000/- for 05 years.

10.4 In the TCC meeting held on 24th Sept. 09, upon query by TCC members, ED, WRLDC stated that as per the arrangement, the preparation for the replacement of the existing ULDC scheme shall be taken up after three years and in this activity PGCIL will involve the constituents for preparation of specifications etc. WRLDC further indicated that in the next RPC meeting they would propose suitably the modalities for this activity for discussion and concurrence by the WRPC forum. The issue regarding of levying of 15 % PGCIL service charges, upon query by MPPTCL, on the value of the LTSA contract had come up for discussion in the TCC meeting. PGCIL pointed out this is being done as per their policy. However WR constituents unanimously stressed that since the WRLDC expenditure is borne by them, the above proposed service charges should not be charged. The matter was deliberated by WRP Committee and the Committee did not agree with the proposal of PGCIL for levy service charge in respect of above LTSA. ITEM No. 11: INVESTIGATION ON FAILURE OF 400 KV TRANSMISSION LINES

OF PGCIL DURING MAY-JUNE – 2009 BY THE STANDING COMMITTEE OF EXPERTS

The Standing Committee of Experts on investigation on failure of 400 kV transmission lines of PGCIL has submitted its report, in it’s finding the Committee has finally concluded that the following lines of PGCIL in respect of WR failed due to heavy wind except 400 kV Korba – Bhilai-Ckt-I S/C line:

(i) 400kV Jabalpur-Itarsi D/C line (18 No. of towers) (ii) 400kV Vindhyachal-Jabalpur Ckt-I & II D/C Line (3 No. of towers) (iii) 400kV Korba-Bhilai Ckt-I S/C Line (3 No. of towers) (iv) 400kV Khandwa-Dhule D/C Line (5 No. of towers)

The 400kV Korba-Bhilai Ckt-I S/C Line failed due to action of heavy wind velocity on towers but the main reason was missing of the redundant members due to theft. The Standing Committee of experts to investigate failure of 400 kV transmission lines of PGCIL decided that:

(i) PGCIL will provide hip bracings on all the suspension towers on all transmission lines up to bottom cross arm, keeping in view the priority & importance of the lines.

(ii) PGCIL should also obtain the services of SERC regarding installation of wind measure system as well as downloading of data remotely & its analysis.

The WR Power Committee noted the same.

Minutes of 11th WRPC meeting held on 25th September 2009 at Raipur

25

ITEM No. 12: SCHEDULE OF REVIEW OF CRISIS MANAGEMENT PLAN OF CENTRAL NODAL MINISTRIES / DEPARTMENTS FOR 2009-10

Member Secretary, WRPC stated that as per intimation received from CEA that the Cabinet Secretariat had requested Central Nodal Ministries / Departments to draw up a schedule of mock drills to verify preparedness for crises management plan, an action taken in this regard is to be reviewed during the meeting to be taken by Secretary (security), Cabinet Secretariat in November 2009. In this context, it requested that the disaster Management Plan along with detailed action plan available/drawn-up by WR utilities to conduct the mock drills and communicated to CEA. WRLDC intimated about having sent nominations of officers designated for associating themselves in this activity to their management for the needful. The plan could also be discussed in case any review/modification needed in the suggested plan. In view of the above requirement, all Members from WR utilities/LDCs agreed to send the details of plans to CEA/WRPC at the earliest. ITEM No.13: PAYMENTS OF UI AND REACTIVE ENERGY CHARGES

As per the information received from WRLDC, the status of payment to UI pool account and Reactive Energy Pool account as on 8.09.2009 i.e. upto week 17.08.09 to 23.08.09 of the current financial year is given below: -

(All figures in Rupees) UI Pool Account Reactive Energy Pool Account Constituents Dues Constituents Dues

CHHATTISGARH (35,440,538) CHHATTISGARH (6,326,286) MADHYA PRADESH (46,927,023) MADHYA PRADESH 1,307,206 GUJARAT (22,063,221) GUJARAT 5,773,988MAHARASHTRA (187,728,964) MAHARASHTRA (3,055,300)GOA 17,621,998 GOA (2,450,199)DD 28,621,807 DD 211,925 DNH 491,550 DNH 717,232 NTPC (168,180,380) NR Exchange 470,250,105 SR Exchange (253,798,843) ER Exchange 717,850,562 Jindal Power (176,196,911) HVDC Vindhyachal (879,270) HVDC Bhadravati (5,036,201) Lanco Amarkantak (910,073,864) Mundra APL 220,845,175 Diff. due to capping (1,869,347,230) Diff. due to Additional UI (454,031,455)

Net Total (2,674,022,703) (3,821,434)

Figures in bracket ( ) are receivables from pool Committee noted the same.

Minutes of 11th WRPC meeting held on 25th September 2009 at Raipur

26

ITEM No.14: COMMISSIONING OF TRANSMISSION LINES AND GENERATING UNITS

14.1 Commissioning of transmission elements by PGCIL NIL 14.2 Commissioning of generating units

S.No State/Agency Name of

Project Unit No.

Capacity in MW

Date of Synchronization

1 Gujarat Mundra (APL) 1 330 23.05.09

2 Chhattisgarh Pathadi TPP (LANCO)

1 300 13.05.09

3 Bhilai TPP (Joint venture with SAIL)

NSPCL 2 250 Full load operation on 12.07.09

The Committee noted as above. ITEM No.15: ONGOING TRANSMISSION SCHEMES IN WESTERN REGION The details of ongoing transmission schemes in WR is enclosed at Annexure-15. The important EHV lines, which are expected to be commissioned during the current year, are as below: S.No. Name of transmission element Expected date of

commissioning 1 400 kV D/C Akola-Aurangabad Oct. 2009 2 765 kV S/C Seoni - Bina line (to be charged at 400kV) Dec. 2009 3 400 kV D/c Ranchi - Rourkela Mar-2010 4 400 kV D/c Rourkela - Raigarh Mar-2010 5 400 kV D/c Raigarh – Raipur Mar-2010 6 765 kV Seoni – Wardha Ckt-II (initially to be charged on

400 kV) Mar.-2011

7 LILO of Kankroli-Zerda at Bhinmal Oct-2009

The Committee noted as above ITEM No. 16: ONGOING GENERATION SCHEMES IN WESTERN REGION

The details of on going generation schemes in WR both under State as well as Central Sector are enclosed at Annexure-16. The generating units expected to be commissioned during the next one year are as follows: Name of the Power Projects Unit No. Capacity

(MW) Schedule Date of Commissioning

GUJARAT (i) Surat Llignite expansion-PH-I GIPCL 1 125 Nov. 2009

Minutes of 11th WRPC meeting held on 25th September 2009 at Raipur

27

Name of the Power Projects Unit No. Capacity (MW)

Schedule Date of Commissioning

2 125 Mar. 2010 (ii) Utran GPP GT+ST 374 GT syncd. On 10.7.09 (iii) Mundra TPP Ph-I, APL 1 330 Syncd. on 23.05.09 2 330 Oct. 2009 3 330 Feb. 2010 4 330 May. 2010 (iv) Hazira CCPP (GSECL) GT+ST 350 Apr. 2010

CHHATTISGARH (i) Pathadi TPP (Lanco) 2 300 Aug 2010

MAHARASHTRA (i) New Parli TPS Extn. 2 250 Nov 2009 (ii) Paras TPS Extn. 2 250 Dec 2009 (iii) JSW Energy, Ratnagiri (4x300) 1 300 Feb. 2010 CENTRAL SECTOR – NTPC (i) Sipat-I, TPP 1 660 Nov. 2010 2 660 May 2011 3 660 Nov 2011 (ii) Korba STPP Stage-III 7 500 May. 2010 The Committee noted the same. ITEM No. 17: DISBURSEMENT OF INTEREST CALCULATED ON LATE

PAYMENT OF UI CHARGES AND THE INTEREST EARNED ON DEPOSIT AMOUNT FOR UI IN IDBI BANK.

17.1 WRLDC in the 53rd CCM held on 8th Sept. 09 stated that presently, the residual interest with UI pool account, after payment to the interest receivable members, is distributed to the UI interest receivable members as per their UI receivables for the period for which interest is calculated. Also as decided in the 43rd CCM, interest earned on deposit amount for UI in IDBI bank is distributed to all the UI receivable members of UI pool accounts in proportion to their total receivables for the period during which interest is earned. 17.2 As per the clause 9 of Central Electricity Regulatory Commission (Unscheduled Interchange charges and related matters) Regulations, 2009 the Commission directed that all payments on account of UI charges including additional UI charges levied under the above Regulations and the interest received on late payment thereof shall be credited to a Fund called the “Unscheduled Interchange Pool Account Fund”, which shall be maintained and operated in accordance with provisions of the Grid Code. Further, as per clause 11 of the Regulation, all the amount left after final settlement of claims of Unscheduled Interchange charges of

Minutes of 11th WRPC meeting held on 25th September 2009 at Raipur

28

the generating station and the beneficiaries, shall be utilized, with the prior approval of the Commission. The relevant Clause-11 of the Regulation is reproduce below: “11. Application of fund collected through UI- (1) The amount left after final settlement of claims of Unscheduled Interchange charges of the generating station and the beneficiaries shall be utilised, with the prior approval of the Commission, for either or both of the following activities:

(a) Servicing of investment for transmission schemes of strategic importance, Provided that the Central Transmission Utility in consultation with Central Electricity Authority shall identify the inter-State transmission schemes of strategic importance, not being utilised up to optimum level and seek prior approval of the Commission for servicing of capital costs during the initial years from amount left in the “Unscheduled Interchange Pool Fund” after settlement of claims of Unscheduled InterchangeCharges.

Provided further that when utilisation of such transmission line or transmission system included in the transmission schemes of strategic importance reaches the optimum level of utilisation, the cost of such scheme shall be recovered from the users of the scheme in accordance with the methodology specified by the Commission.

(b) Providing ancillary services including but not limited to ‘load generation balancing’ during low grid frequency as identified by the Regional Load Despatch Centre, in accordance with the procedure prepared by it, to ensure grid security and safety:

(2) The amount of fund, allocable for the purposes specified under clause (1), shall be decided by the Commission from time to time.” In the above context, WRLDC during 53rd meeting of Commercial Committee meeting of WRPC held on 8th Sept. 09 proposed that from 1st April’2009 onwards the surplus amount generated through the interest earned through deposit amount for UI in IDBI bank and the residual interest after payment to UI interest receivables will be kept in the “Unscheduled Interchange Pool Fund”. WRP Committee noted as above.

ITEM No. 18: AUTOMATIC METER READING SOLUTIONS BY M/S BPL 18.1 WRLDC in the 53rd meeting of Commercial Committee held on 8th Sept. 2009 stated that M/s BPL has developed an Automatic Meter Reading (AMR) solution for downloading and transmitting the data from remote locations to RLDCs. The main feature of this solution is that the data will be automatically read from the meter and transmitted to RLDC. WRLDC added that M/s BPL have developed the output text file exactly similar to one created by M/s SML and M/s L&T using their software “SMARTGRID and “VINCOM” respectively and have given three different types of architectures to download and transmit the data from remote location to respective RLDC. WRLDC further stated that a pilot project has been given to M/s BPL by WRTS-I, PGCIL, Nagpur, to connect few meters at 400 kV Seoni S/s for one month with required interface unit so that complete system can be verified for few weeks

Minutes of 11th WRPC meeting held on 25th September 2009 at Raipur

29

before it can be accepted completely. WRTS-I, PGCIL agreed to take up the responsibility. As per the detailed budgetary proposal received from M/s BPL, the total cost for 531 Nos. SEMs (405 SML make and 126 L&T make), spread over 92 locations, comes out to Rs. 77.73 Lakhs assuming that dedicated PCs are available in all these locations. In addition to above, cost of TA/DA of PGCIL employee will also have to be borne by the constituents. WRLDC proposed to share the cost of this project in the same manner the cost of SEMs are shared. WRLDC also stated that M/s BPL have agreed to take up this project at few 3 or 4 locations free of cost. 18.2 The above matter was deliberated in detail and the Commercial Committee members unanimously opined that the above project may be initially taken at few 3 or 4 locations at free of cost and based on the experience the decision for implementing the same for all locations will be taken later on. WRLDC suggested Asoj, Koradi or Kolhapur, Korba(W) and Bina or Bhopal locations can be initially taken up by M/s BPL start the project, Constituents agreed to the same. The Committee also suggested WRLDC to other developers also in this project. Chairman, WRPC / GSECL suggested that WRLDC may look for 3-4 vendors for development of the project so as to get better option. ITEM No. 19: ALLOCATION OF POWER FROM SUBANSIRI HEP (2000 MW) OF

NHPC AND KAMENG HEP (600 MW) IN ARUNACHAL PRADESH MoP vide letter No. 11/1/2002/DO(NHPC) dated 14th July 2009 intimated that allocation of Subansiri, HEP (2000 MW) and Kameng, HEP (600 MW) to the constituents of NER, NR and WR. From Subansiri, HEP Western Region allocation is 25% equivalent to 500 MW whereas, the allocation from Kameng, HEP is 25% equivalent to 150 MW. The details are as under:-

S.No. States Allocation in %

Equivalent Power in MW from

Subansiri HEP

Equivalent Power in MW from Kameng

HEP 1. Gujarat 32.39 162 48 2. M.P. 21.10 105 32 3. Chhattisgarh 8.44 42 13 4. Maharashtra 36.55 183 15 5. Goa 1.52 8 2

Total 100.00 500 150 WRP Committee noted as above.

ITEM No. 20: PROCUREMENT OF ONE SPARE UNIT OF 50 MVAR SHUNT

REACTOR FOR WR PGCIL representative stated that in view of the system ageing and the failures being experienced, it is proposed to procure one no. 50 MVAR reactor for WR and keep it in a strategic location so that in case of any failure, immediate replacement is possible. The location has been decided based on the critical requirement e.g. State

Minutes of 11th WRPC meeting held on 25th September 2009 at Raipur

30

capitals or major load centre and critical operation, based on various condition monitoring techniques or ageing factor.

In view of the criticality of the location in Western Region and number of existing reactors under operation, it is proposed to keep one spare reactor at Itarsi S/S to meet any eventuality, as at present eleven (11) nos. of shunt reactors are under operation at Itarsi S/S (largest no. of reactors in a particular S/S) and four (04) of them are more than seventeen (17) years old. The availability of spare reactor in the region will help in restoration of the failed equipment within minimum possible period and ensuring reliable power supply without over voltage problem, as the reactos are not readily available and repair of a reactor after failure, generally takes around 12 months time due to pre occupation of manufactures with supply of new equipments. The estimated cost of one 50 MVAR Shunt Reactor is approx. Rs 3.25 Crores. The matter was deliberated in the TCC meeting held on 24th Sept. 09 and the TCC suggested that as the procurement of above equipment is to be considered under additional capital expenditure or through O&M expenses. PGCIL may approach CERC directly for necessary approval of the same accordingly. WRP Committee agreed to the suggestion of the TCC and requested PGCIL to approach CERC.

(Action: PGCIL) ITEM No. 21: OPGW CONNECTIVITY TO SUB-STATIONS OF PGCIL 21.1 PGCIL stated that under ULDC project, Fibre Optic (FO) based Wideband communication network has been established. Subsequently, backup communication links on certain sections have also been established. This wideband network of ULDC is available at only selected locations (Total – 25 nodes & Central Sector - 6 nodes) and therefore huge no. of RTUs are still communicating on PLCC. The performance of SCADA system at WRLDC and SLDC is largely dependent on the performance of the communication links. The SCADA committee of Western Region consisting of the members of all the constituents of Western Region and WRLDC reviews the performance and maintenance issue periodically. The committee in their meeting held on 30th June 2009 has recommended that (a) all future transmission lines would have to be equipped with OPGW link as part of construction package and (b) the important and critical lines commissioned subsequent to commissioning of ULDC scheme in WR to be provided with OPGW communication link. Accordingly, POWERGRID proposes to extend the FO connectivity to all its substations in the region. POWERGRID also mentioned that upcoming WAMS technology can be implemented only with FO based communication network. GM I/C (LD&C) POWERGRID mentioned that in case constituents’ substations are also to be provided with wide band connectivity the requirement can be finalized on regional basis. The matter was deliberated by the constituents in the TCC meeting held on 24th Sept. 09 and it was concluded that requirement of FO connectivity is to be examined on case-to-case basis. However, the future transmission lines should be equipped

Minutes of 11th WRPC meeting held on 25th September 2009 at Raipur

31

with OPGW link as part of construction package. It was decided that the FO connectivity network for the region shall be finalized by the SCADA committee and thereafter the same shall be put up for the approval of the TCC/WRPC. WRP Committee endorsed the recommendation of the TCC. ITEM No. 22: STATUS OF LTOA APPLICATIOS IN WR

22.1 PGCIL representative stated that in the 11th meeting of WR constituents regarding Long-term Open Access(LTOA) applications in WR was held on 10.09.2009 at Ahmedabad. IPPs who have shown substantial progress for the project as well as scheduled commissioning of the unit as informed by the applicants as well as by CSPTCL/CSPGL were considered for grant of LTOA. Further, IPPs have indicated only target region/beneficiaries, however, they need to firm-up the beneficiaries at the earliest. However, based on the target beneficiaries/regions suitable system strengthening as well as dedicated transmission system have been identified and transmission charges for the system strengthening shall be borne by the respective IPP/applicant till firming-up of the beneficiaries. It was informed that some of the LTOA applicants applied for open access for full capacity and some for net injection. In line with the discussion held during the 28th Standing Committee meeting of WR, since the sharing of pooled regional transmission charges was on the basis of gross generation capacity, therefore, the LTOA applicants would also share the transmission charges accordingly. Wherever, the applicant has applied for part capacity with balance to be supplied through STU system or own consumption, LTOA would be for capacity applied for. However, such applicants would need to account for their full generation capacity with respect to LTOA (STU) + LTOA (CTU) + own consumption. The owing long-term open access applications were discussed and agreed in the 11th meeting of WR constituents regarding Long-term Open Access(LTOA) applications in WR was held on 10.09.2009 at Ahmedabad. 22.2 Bina Power Supply Co. Ltd. Bina Power Supply Co. Ltd. has submitted application to POWERGRID for grant of “Long term Open Access” for transfer of 500MW power from their proposed generation project [2x250 MW] in Distt Sagar, MP to Madhya Pradesh [210 MW] and target region WR [145 MW] & NR [145 MW]. Expected date of commencement of above open access as informed by M/s Bina Power is Sep’2011.

Point of injection and drawl details for the purpose of open access is as

under:

S.N

Gen Capacity (MW) Point of injection [Quantum (MW) to be transferred]

Point /Quantum of drawal

1. Bina Power Supply TPS– 2x250 MW (500MW) Village- Sirchopi, Tehsil – Bina, Dist- Sagar (M.P)

400kV Bina (PG) 500 MW

Quantum: Long term Sale: M.P – 210 MW at MPSEB S/s Bina

Minutes of 11th WRPC meeting held on 25th September 2009 at Raipur

32

S.N

Gen Capacity (MW) Point of injection [Quantum (MW) to be transferred]

Point /Quantum of drawal

Generation step-up voltage: 400kV

Merchant Power – 290 MW WR : 145 MW NR : 145 MW Point of drawal: The State Utilities interface with POWERGRID system

MPPTCL informed that drawal of 210MW allocation of M.P shall be at Bina TPS generation switchyard. Therefore, LTOA in ISTS can be provided to M/s Bina Power Supply Co. corresponding to balance 290MW.

After detailed deliberations, following was agreed in LTOA meeting:

After detailed deliberations, following was agreed:

i) Long-term open access to M/s Bina Power for transfer of 290MW power from their proposed 500MW generation project at Bina, Dist. Sagar, M.P to target beneficiaries in WR (145 MW)/NR (145 MW) may be provided.

ii) LILO portion of 400kV Bina(M.P) – Bina(PG) D/c line at Bina TPS shall be

the dedicated transmission system for the generation project which shall be built, owned, operated and maintained by M/s Bina Power to interconnect the generation project with WR grid.

iii) M/s Bina Power shall sign BPTA with POWERGRID for sharing of WR

regional transmission charges corresponding to 290MW, NR transmission charges corresponding to 145MW as per CERC norms as well as shall need to share the transmission charges towards following common transmission corridors beyond Bina(PG) in WR/NR proposed for IPPs in Orissa/Bilaspur Pooling Station

Common Transmission system to shared by Maruti Clean Coal & Power Ltd.(300MW), PTC India(600MW), Dheeru Powergen (450MW), Jaiprakash Power Ventures Ltd(1320MW), Aryan Coal Benefications Pvt. Ltd.(1200MW), Bina Power(290MW) and Indiabulls Power(390 MW) to be shared along with IPPs in Orissa(6080MW) in proportion to allocation to NR

a) Bina – Gwalior 765 kV S/c (3rd) b) Gwalior – Jaipur 765kV S/c(2nd) c) Jaipur – Bhiwani 765kV S/c

Common Transmission system to shared by Maruti Clean Coal & Power Ltd. (300MW), PTC India(600MW), Dheeru Powergen(450MW), Jaiprakash Power Ventures Ltd, (1320MW), Aryan Coal Benefications Pvt. Ltd. (1200MW) and Bina Power(290MW) in proportion to allocation to WR

a) Indore - Vadodara 765 kV S/c b) Vadodara – Pirana 400kV D/c(Quad)

Minutes of 11th WRPC meeting held on 25th September 2009 at Raipur

33

c) Establishment of 765/400kV 2x1500MVA Pooling station at Vadodara

WRP Committee noted the same. 22.3 Indiabulls Power Ltd. M/s Indiabulls Power Ltd. has submitted application to POWERGRID for grant of “Long term Open Access” for transfer of 1230MW power from their proposed Nandgaon peth generation project [2x660 MW] in Distt Amravati, Maharashtra to Maharashtra [930 MW] and target regions: WR [200 MW] & NR [100 MW]. Expected date of commencement of above open access as informed by M/s Indiabulls Power Ltd is Dec’2011. Point of injection and drawl details for the purpose of open access is as

under:

S.N Gen Capacity (MW) Point of injection [Quantum (MW) to be transferred]

Point /Quantum of drawal

1. Amravati TPS – 2x660 MW (1320MW) Nandgaon Pet, Dist – Amravati (Maharashtra) Generation step-up voltage: 400kV

Nearest POWERGRID S/s in Maharashtra 1230 MW

Quantum: Maharashtra – 930 MW Capacity for Sale to Other States – 300 MW WR : 200 MW NR : 100 MW Point of drawal: Interconnection of CTU system with the STU system of target States

Common Transmission system to shared by Maruti Clean Coal & Power

Ltd.(300MW), PTC India(600MW), Dheeru Powergen (450MW), Jaiprakash Power Ventures Ltd(1320MW), Aryan Coal Benefications Pvt. Ltd.(1200MW), Bina Power(290MW) and Indiabulls Power (390 MW) to be shared along with IPPs in Orissa(6080MW) in proportion to allocation to NR

a) Bina – Gwalior 765 kV S/c (3rd) b) Gwalior – Jaipur 765kV S/c(2nd) c) Jaipur – Bhiwani 765kV S/c After detailed deliberations, following was agreed in the LTOA meeting:

a) Long-term open access to M/s Indiabulls Power for transfer of 390MW (WR-

260 MW, NR-130 MW) power from their proposed 1320MW generation project at Dist. Amravati, Maharashtra to target beneficiaries in WR/NR may be provided.

b) Following dedicated transmission system for the generation project shall be built, owned, operated and maintained by M/s Indiabulls Power to interconnect the generation project with MSTECL network:

Minutes of 11th WRPC meeting held on 25th September 2009 at Raipur

34

• Nandgaonpeth (Indiabulls) – Akola II (MSETCL) 400kV D/c(Quad) • LILO of Akola-I – Koradi I 400kV S/c at Nandgaonpeth (Indiabulls)

c) M/s Indiabulls Power shall sign BPTA with POWERGRID for sharing of WR

transmission charges corresponding to 390MW and NR transmission charges corresponding to 130MW as per CERC norms. In addition, transmission charges for the proposed strengthening scheme shall also need to be shared by M/s Indiabulls along with other IPPs in proportion to their quantum of LTOA.

i) Strengthening Scheme – Transmission charges to be shared along

with other IPPs in Chhattisgarh • Aurangabad(PG) – Khargar 400kV D/c (Quad)

ii) Common Transmission system to shared by Maruti Clean Coal & Power

Ltd.(300MW), PTC India(600MW), Dheeru Powergen (450MW), Jaiprakash Power Ventures Ltd(1320MW), Aryan Coal Benefications Pvt. Ltd.(1200MW), Bina Power(290MW) and Indiabulls Power (390 MW) to be shared along with IPPs in Orissa(6080MW) in proportion to allocation to NR

a) Bina – Gwalior 765 kV S/c (3rd) b) Gwalior – Jaipur 765kV S/c(2nd) c) Jaipur – Bhiwani 765kV S/c

It was informed that M/s Indiabulls needs to submit bank guarantee equivalent to 10% of the total transmission system strengthening project cost at (i) above to be shared along with IPPs in proportion to their LTOA quantum along with signing of BPTA as construction phase bank guarantee.

d) Date of commencement of above open access is from the date of

commissioning of above identified system strengthening scheme indicated at para (c) and dedicated line, scheduled for implementation by that time frame. Further, M/s Indiabulls Power shall take necessary action to fulfill the terms and conditions of open access application.

WRP Committee noted the same. 22.4 Pipavav Energy Pvt Ltd. M/s Pipavav Energy Ltd has submitted application to POWERGRID for grant of “Long term Open Access” for transfer of 555MW power from their proposed generation project [1x600 MW] in Distt Amreli, Gujarat. Subsequently, Pipavav Energy Ltd revised their generation capacity to 1200 MW (2x600 MW) and transfer requirement to 1110 MW (WR [555 MW] & NR [555 MW]). Expected date of commencement of above open access as informed by M/s Pipavav Energy Ltd is Mar’2013.

Minutes of 11th WRPC meeting held on 25th September 2009 at Raipur

35

Point of injection and drawl details for the purpose of open access is as under:

S.N Gen Capacity (MW) Point of injection [Quantum (MW) to be

transferred]

Point /Quantum of drawal

1. Pipavav Energy TPS – 2x600 MW (1200 MW) Pipavav port, Dist – Amreli (Gujarat) Generation step-up voltage: 400kV

Nearest POWERGRID S/s in Gujarat 1110 MW

Quantum: WR : 555MW NR : 555 MW Point of drawal: Interconnection of CTU system with the STU system of target States

After detailed deliberations, following was agreed in the LTOA meeting:

a) Long-term Open access to M/s Pipavav Energy Ltd for transfer of power

from their 1200 MW generation project at Dist. Amreli, Gujarat to target beneficiaries in WR (600 MW)/NR(600 MW) may be provided.

b) Following dedicated transmission system for the generation project shall be

built, owned, operated and maintained by M/s Pipavav Energy Ltd to interconnect the generation project with WR grid, subject to response from GETCO regarding suitability of connectivity elsewhere:

i) Pipavav TPS – Pirana(PG) 400kV D/c (Triple/Quad) ii) 2 nos. 400kV line bays at Pirana(PG) to terminate above line

GETCO informed that they would explore the possibility of connectivity at nearby S/s in Saurashtra region in a week’s time and in case connectivity is not available, direct connection to 400kV Pirana may be provided.

c) M/s Pipavav Energy Ltd shall sign BPTA with POWERGRID for sharing of

WR regional transmission charges corresponding to 1200MW and NR transmission charges corresponding to LTOA quantum to NR as per CERC norms and as well as shall need to share the transmission charges towards following transmission system strengthening scheme backed by suitable bank guarantee. It was informed that M/s Pipavav Energy needs to submit bank guarantee equivalent to 10% of the total transmission system strengthening cost along with signing of BPTA as construction phase bank guarantee.

Strengthening Scheme a) Bhachau – Versana(GETCO) 400kV D/c

In case, generation project is interconnected at suitable location in Saurashtra area, above system strengthening needs to be reviewed.

WRP Committee noted the above.

Minutes of 11th WRPC meeting held on 25th September 2009 at Raipur

36

ITEM No. 23: Evacuation of power from generation projects coming up in Sikkim and Bhutan

23.1 Member (PS), CEA informed that a review of the generation projects in Sikkim, Bhutan and NER along with comprehensive transmission system was informed during the 29th meeting of SCM held on 10th September 2009. The latest schedule of generation projects envisaged to come by the year 2014 is as under:

(a) NER : About 4000 MW ( Lower Subansisri HEP: 2000MW, Kameng HEP: 600 MW, Bongaigaon TPS: 750 MW, Pallatana GBPP: 726 MW)

(b) Sikkim : About 2400 MW ( Chujachen: 99 MW, Teesta-III: 1200 MW,

Jorethang: 96 MW, Tingting: 99 MW, Rongnichu: 96 MW, Bhasmey: 51 MW, Tashiding: 97 MW, Rangit-II*: 66 MW, Teesta-VI: 500 MW, Rangit-IV: 120 MW)

(c) Bhutan : About 1200 MW (Punatsangchu-I HEP),

Other future projects in Bhutan like Mangdechu (670MW) and Punatsangchu-II (990 MW) are expected to be commissioned by 2016

23.2 In order to evacuate the power from the generation projects in NER, Sikkim and Bhutan, a comprehensive transmission scheme has been evolved which consisted of Bishwanath Chariyali(NER) - Agra(NR), +/-800kV, 6000MW HVDC bipole line with 3000MW HVDC converter stations at Bishwanath Charyiali and Agra proposed under “NER – NR/WR Interconnector-I” initially, which has already been concurred by the constituents of NR and WR.. Earlier it was proposed to evacuate power from Sikkim projects by pooling it at Kishenganj and onward transmission to Agra was to be through HVDC. However, now there was change in the proposal and Sikkim power is now proposed to be evacuated through AC network from Kishenganj onward. The location of the proposed HVDC terminal is proposed to be brought to Alipurduar nearer to Bhutan for evacuation of power from projects in Bhutan. The balance portion of the scheme now consists of 3000MW converter station each at Alipurduar and Agra along with loop-in & loop-out of 6000MW HVDC bipole line at Alipurduar. 23.3 The transmission system for evacuation of the above projects had been divided into three parts. The first part is for evacuation of power from the first two projects in Sikkim i.e. Chujachen (99 MW) and Teesta-III (1200 MW). The 2nd part is for evacuation of the next 1100MW of power i.e. total 2400MW from Sikkim generation projects. The 3rd part is for providing the corridor towards NR/WR with adequate reliability and security for the above generation projects in Sikkim as well as help in evacuation of power from Phunatsangchu-I generation project in Bhutan and also initial evacuation of future generation projects in Bhutan like Punatsangchu-II, Mangdechu etc.

Minutes of 11th WRPC meeting held on 25th September 2009 at Raipur

37

The details of the transmission system are as under:

(i) By 2011-12, for evacuation of 1300 MW from Sikkim Part-A: Transmission System for development of pooling station at Kishanganj in Northern part of West Bengal/Bihar

Establishment of new 2x315 MVA, 400/220kV sub-station at Kishanganj LILO of Siliguri (Existing) – Purnea 400kV D/c line(quad) at new pooling

station Kishanganj LILO of Siliguri (Existing) – Purnea 400kV D/c line(on which

reconductoring is being carried out) at Kishanganj with the higher capacity(HTLS) conductor LILO of Siliguri – Dalkhola 220kV D/c line at new pooling station at

Kishanganj LILO of Gangtok-Melli 132kV S/c line upto Rangpo, where Chuzachen-

Rangpo 132kV D/c would be connected so as to form Chuzachen-Gangtok and Chuzachen-Melli 132kV S/c lines.

(ii) By 2012-13, when additional 1100 MW materializes in Sikkim

Part-B: Transmission System for development of pooling substations within Sikkim and transfer of power to a new pooling station Kishanganj in northern Part of West Bengal/Bihar Establishment of 220/132kV, 3x100MVA Gas Insulated Substation at

Rangpo Establishment of 10x167MVA, 1 phase, 400/220kV Gas Insulated

substation at New Melli LILO of Teesta III – Kishanganj 400kV D/c line at New Melli Rangpo – New Melli 220kV D/c line (with twin Moose conductor) LILO of Gangtok-Rangit 132kV S/c line at Rangpo and termination of

Gangtok-Rangpo and Melli – Rangpo 132kV lines (constructed under part-A through LILO of Gangtok-Melli 132kV S/c line upto Rangpo) at Rangpo LILO of Teesta V – Siliguri 400kV D/c line at New Melli Kishanganj – Patna 400kV D/c (quad) line

(iii) By 2014-15, when Punatsangchu-I (1200 MW) comes up in Bhutan

Part-C: Transmission System for development of pooling station in Northern part of West Bengal and transfer of power from Bhutan to NR/WR. New 400kV AC & HVDC sub-station with + 800kV, 3000MW converter

module at new pooling station in Alipurduar Extension of + 800 kV HVDC station with 3000 MW inverter module at

Agra LILO of Bishwanath Chariali – Agra HVDC line at new pooling station in

Alipurduar for parallel operation of the HVDC station LILO of Bongaigaon – Siliguri 400kV D/c line at new pooling station in

Alipurduar LILO of Tala-Siliguri 400kV D/c line at new pooling station in Alipurduar LILO of Birpara-Salakati 220 kV D/C line at New Pooling station in

Alipurduar Punatsangchu-I (generation project in Bhutan)-Alipurduar 400 kV D/C with

HTLS conductor (Indian portion)

Minutes of 11th WRPC meeting held on 25th September 2009 at Raipur

38

23.4 The transmission charges for Part ‘A’ & ‘B’ of the above transmission scheme would be initially borne by the generation developers. The transmission charges for Part ‘C’ of the transmission scheme shall be borne by beneficiaries of Bhutan power. Northern Region Constituents had already agreed to share the transmission charges of Part-C of the scheme subject to the allocation of power from Bhutan projects to Northern Region. During the 29th meeting of SCM held on 10th September 2009 WR constituents agreed to share transmission charges for Part ‘C’ of the transmission scheme subject to the allocation of power to Western Region from Bhutan projects. The WR Power Committee noted the same. ITEM No. 24: OPEN ACCESS APPLICATIONS PERTAINING TO NEW

GENERATION PROJECTS IN SOUTHERN REGION WITH TARGET BENEFICIARIES IN WESTERN/ NORTHERN/ SOUTHERN REGION

24.1 Member (PS), CEA informed that the Long Term Open access applications pertaining to New Generation Projects in Southern Region with target beneficiaries in Western/Northern/Southern Region was discussed during the Special meeting of the Standing Committee on Power System Planning in WR held on 18th April 2009 and also during the 29th meeting of Standing Committee on Power System Planning in WR held on 10th Sept 2009. The open access applications received in Southern Region with target beneficiaries in WR/NR/SR was as under:

LTOA Applied

Allocation of Power(MW) LTOA Applicant

SR WR NR

Krishnapatnam Area Simhapuri Energy Private Ltd. 491 311 135 PTC India Ltd. (Meenakshi) 600 205 195 200 APPDCL 175 175 Krishnapatnam Power (Navayuga) 1860 360 600 900 Total 3126 876 930 1275

Tuticorin Area

Coastal Energen Pvt. Ltd. 1100 820 280 Ind-Barath Power (Madras) Ltd. 945 284 236 425 Total 2045 1104 516 425

Srikakkulam Area

East-Coast Energy 2440 1940 500 NCC Vamshadara 1320 500 500 320 Total 3760 2440 1000 320

Grand Total 8931 4420 2446 2020 24.2 During the Special meeting of the SCM held on 18th April 2009 it was decided that the inter-state transmission system strengthening in WR and NR as well as

Minutes of 11th WRPC meeting held on 25th September 2009 at Raipur

39

inter-regional system strengthening between NR and WR shall be identified later on. During the 29th meeting of SCM in WR the transmission system for transfer of power to WR and NR beneficiaries was discussed and the following transmission system strengthening within WR/NR and between WR and NR had been identified.

(i) Sholapur – Pune 765 kV 2nd S/c. (ii) Jabalpur Pooling station – Orai 765 kV S/c line. (iii) Orai – Bulandshahar 765 kV S/c line. (iv) Bulandshahar – Sonipat 765 kV S/c line (v) Establishment of 765/400 kV 2X1000 MVA substation at Orai by LILO of

one circuit of Satna – Gwalior 765 kV line (vi) Establishment of 765/400 kV 2X1500 MVA substation at Bulandshahar by

LILO of Agra – Meerut 765 kV line. (vii) Establishment of 765/400 kV 2X1500 MVA substation station at Sonepat

by LILO of Bhiwani – Meerut 765 kV line. 24.3 The above system strengthening scheme had been agreed by the constituents of SR during the 29th SCM of SR. The Sholapur – Pune 765 kV 2nd S/C line would be a common strengthening scheme for WR and NR for IPP projects in SR. Balance elements would be system strengthening in NR. The transmission charges of the above system strengthening scheme shall be borne by the generation project developers till the finalization of their beneficiaries. The WR Power Committee noted the same.

ITEM No.25: PSS TUNING ACTIVITY IN WR Member Secretary, WRPC stated that in the 114th WRE Board had approved that PSS Tuning exercise in WR (Phase One), which had identified 12 units for PSS Tuning, namely two units each at Dahanu, Wanakbori, Nasik, Korba West, Satpura and NTPC Korba. The first phase was successfully completed. In the 128th WRE Board meeting held on 2.9.2005, the PSS Tuning for Phase II was identified and in the first part of Phase II, 14 units were identified, namely three units at Parli, three at NTPC Korba, four at SGTPS Birsingpur, one at Chhattisgarh and three at Gandhinagar. An initial contribution of Rs 11 Lakh for Part I was taken. At present PSS Tuning for six units is already completed (three each at Parli and NTPC Korba) and Rs 673927/- has been so far spent. In the PSS Tuning Core group meeting held on 17.9.2009 at WRPC, it was proposed that Part I of this PSS Tuning activity has to be completed by December 2009. It was estimated that an additional amount Rs 3.0 Lakh is required to complete the balance activity under phase-II of Part I. Accordingly it was recommended to request a contribution of Rs 60000/- each from MSPGCL, GSECL, CSPGCL, NTPC and MPPGCL to complete this part-I. Upon completion of this part, the accounts may be finalized in line with the decision taken in 128th WRE Board meeting. The matter was discussed in the TCC meeting held on 24th Sept. 09 and the TCC recommended that a contribution of Rs 60000/- each from MAHAGENCO, GSECL, CSPGCL, NTPC and MPPGCL to meet balance expenses for Part I of Phase II of the project may be made. WR Power Committee agreed to this recommendation of TCC and approved the additional expenditure for proceeding with the balance work of PSS tuning process as above.

Minutes of 11th WRPC meeting held on 25th September 2009 at Raipur

40

ITEM No.26: DATE AND VENUE OF NEXT WRPC MEETING The next meeting i.e. 12th WRP Committee meeting will be held in Dec 09 /Jan 2010. Gujarat agreed to host the meeting.

* * * * *

Minutes of 11th WRPC meeting held on 25th September 2009 at Raipur

41

ANNEXURE

Agenda Notes of 11th WRPC meeting to be held on 25th Sept. 09

Annexure-1(A)

LIST OF PARTICIPANTS OF TCC MEETING HELD ON 24.09.2009 AT RAIPUR

A. TECHNICAL COORDINATION COMMITTEE

MEMBERS

1. Shri S. K. Negi, MD, GETCO & Chairman, TCC 2. Shri M. B. Mendhekar, ED(O), CSPGCL 3. Shri Vijay Singh, CE(Trans), CSPTCL 4. Shri R. K. Pandey, CE(O&M), CSPDCL 5. Shri A. K. Roy, CE(LD), CSPTCL 6. Shri N. H. Suthar, CE (LD), SLDC, GETCO 7. Shri R. K. Verma, CMD, MPPTCL 8. Shri R. P. Sharma, OSD (LD), MPPTCL 9. Shri G. S. Limaye, Dir(O), MSETCL 10. Shri S. G. Kelkar, CE (LD), MSETCL 11. Shri S. B. Agrawal, Regional ED(W) 12. Shri M. L. Jadhav, CE (Trans.), NPCIL 13. Shri R. K. Grover, CE(GM), CEA 14. Shri R. K. Bhatnagar, GM(Power), RGPPL 15. Shri T. S. Bhatt, Sr. VP, PTC India Ltd. 16. Shri R. B. Mathur, GM(ISP), NHDC Ltd. 17. Shri Atul G. Patil, CE, BEST Undertaking 18. Shri Sanjeev Mehra, EVP, PTC India Ltd. 19. Shri M. G. Raoot, ED, WRLDC 20. Shri Manjit Singh, Member Secretary, WRPC

B. OTHERS I. CHHATTISGARH

1. Shri S. N. Chauhan, MD, CSPTCL 2. Shri G. S. Deshpande, MD, CSPDCL 3. Shri Vinod Shrivastava, MD, CSP Tradco. 4. Shri V. K. Verma, MD, CSPHCL 5. Shri S. P. Chaturvedi, MD(Gen.), CSPGCL 6. Shri V. K. Khare, CE(T&C), CSPTCL 7. Shri P. N. Singh, CE(EHT), CSPTCL 8. Shri L. S. Chawla, CE(Comml), CSPDCL 9. Shri C. P. Pandey, CE(O&M-gen), CSPGCL 10. Shri A. K. Garg, CE(PT), CSP Tradco. 11. Shri Shiv Raj Singh, Advisor, CSPTCL

II. GUJARAT

1. Shri P. J. Jani, EE(CSP), GUVNL

III. MADHYA PRADESH

1. Shri D. Khandelwal, OSD (L & RA), MP Tradco IV. MAHARASHTRA

1. Shri S. D. Shrouty, ED (STU), MSETCL 2. Shri N.R. Sonkavday, SE (STU), MSETCL 3. Shri A. B. Shayamkul, GM, MAHAGENCO 4. Shri B. F. Dongre, CE(LM), MSEDCL

V. GOA ELECTRICITY DEPT.

1. Shri Nirmal Braganza, CEE 2. Shri B. Nigalye, AEE

VI. POWERGRID CORPN. OF INDIA LTD.

1. Shri N. S. Sodha, GM (I/C), LD & C, CC 2. Shri N. Ravi Kumar, GM(O&M), POWERGRID, WRTS-I 3. Shri S. K. Gupta, GM(Pr.), WRTS-II 4. Shri P. Pentayya, AGM (OS), WRLDC 5. Shri Prashant Sharma, AGM (Comml.), CC 6. Shri A. S. Kushwaha, AGM, LD&C, CC 7. Shri D. K. Dave, AGM(O&M), WRTS-II 8. Shri S. K. Mishra, DGM, WRTS-I 9. Shri C.A. Bhat, CM(SS), WRLDC

VII. NTPC LTD.

1. Shri Guryog Singh, AGM(Comml.) 2. Shri P. A. Pande, DGM(Comml.)

VIII. TATA POWER COMPANY

1. Shri V.R. Shrikhande, DGM, TPC

IX. NARMADA CONTROL AUTHORITY

1. Shri Hemant Pandey, AD(Power) X. WESTERN REGIONAL POWER COMMITTEE

1. Shri S. G. Tenpe, SE (Comml.) , WRPC 2. Shri O. P. Singh, SE (Opn.), WRPC 3. Shri M. M. Dhakate, AS, WRPC 4. Shri S. Satyanarayan, EE(Prot.), WRPC 5. Shri V. K. Gupta, EE (Opn.) , WRPC

Annexure-1(B)

LIST OF PARTICIPANTS OF 11th WRPC MEETING HELD ON 25.09.2009 AT RAIPUR

A. WESTERN REGIONAL POWER COMMITTEE

MEMBERS

1. Shri S. Jagadeesan, Chairman, GSECL & WRPC 2. Shri S.N. Chauhan, MD, CSPTCL 3. Shri G. S. Deshpande, MD, CSPDCL 4. Shri S. P. Chaturvedi, MD(Gen.), CSPGCL 5. Shri A. K. Roy, CE(LD), CSPTCL 6. Shri S. K. Negi, MD, GETCO 7. Shri N. H. Suthar, CE (LD), SLDC, GETCO 8. Shri R. K. Verma, CMD, MPPTCL 9. Shri R. P. Sharma, OSD (LD), MPPTCL 10. Shri S. G. Kelkar, CE (LD), MSETCL 11. Shri Nirmal Braganza, CEE, ED, Goa 12. Shri R. N. Nayak, Dir.(Opn.), Powergrid 13. Shri M. G. Raoot, ED, WRLDC 14. Shri Manjit Singh, Member Secretary, WRPC

B. OTHERS I. CHHATTISGARH

1. Shri V. K. Verma, MD. CSPHCL 2. Shri V. K. Shrivastava, MD, CSP Tradco. 3. Shri M. B. Mendhekar, ED(O), CSPGCL 4. Shri C. P. Pandey, CE(O&M-gen), CSPGCL 5. Shri L. S. Chawla, CE(Comml), CSPDCL 6. Shri R. K. Pandey, CE(O&M), CSPDCL 7. Shri A. K. Garg, CE(PT), CSP Tradco 8. Shri Vijay Singh, CE(Trans.), CSPTCL 9. Shri P. N. Singh, CE(EHT), CSPTCL 10. Shri Shiv Raj Singh, Advisor, CSPTCL

II GUJARAT

1. Shri S. B. Khyalia, ED(Finance), GUVNL 2. Shri P. J. Jani, EE(CSP), GUVNL

III. MADHYA PRADESH

1. Shri D. Khandelwal, OSD (L & RA), MP Tradco IV. MAHARASHTRA

1. Shri G. S. Limaye, Dir.(Opn.), MSETCL 2. Shri S. D. Shrouty, ED (STU), MSETCL 3. Shri N.R. Sonkavday, SE (STU), MSETCL 4. Shri A. B. Shayamkul, GM, MAHAGENCO 5. Shri B. F. Dongre, CE(LM), MSEDCL

V. GOA ELECTRICITY DEPT.

1. Shri B. Nigalye, AEE

VI. CENTRAL ELECTRICITY AUTHORITY

1. Shri V. Ramakrishna, Member(PS) 2. Shri R. K. Grover, CE(GM)

VII. POWERGRID CORPN. OF INDIA LTD.

1. Shri Y. K. Sehgal, ED(SEF), CC 2. Shri R. G. Yadav, ED(OS), CC 3. Shri N. S. Sodha, GM (I/C), LD & C, CC 4. Shri N. Ravi Kumar, GM(O&M), WRTS-I 5. Shri S. K. Gupta, GM(Pr.), WRTS-II 6. Shri P. Pentayya, AGM (OS), WRLDC 7. Shri Prashant Sharma, AGM (Comml.), CC 8. Shri A. S. Kushwaha, AGM(LD&C), CC 9. Shri D. K. Dave, AGM(O&M), WRTS-II 10. Shri S. K. Mishra, DGM, WRTS-I 11. Shri Kamal Sarkar, DGM, CC 12. Dr. Subir Sen, DGM (Engg.), CC 13. Shri C.A. Bhat, CM(SS), WRLDC

VIII. NTPC LTD.

1. Shri S. N. Goel, GM, CC 2. Shri Guryog Singh, AGM(Comml.), CC 3. Shri B. P. Parida, AGM, CC 4. Shri P. A. Pande, DGM(Comml.)

IX. NUCLEAR POWER CORPORATION OF INDIA LTD.

1. Shri M. L. Jadhav, CE (Trans.), NPCIL X. TATA POWER COMPANY

1. Shri V.R. Shrikhande, DGM, TPC XI. RATNAGIRI GAS AND POWER PRIVATE LTD.

1. Shri R. K. Bhatnagar, GM(Power), RGPPL XII. ESSAR POWER LTD.

1. Shri T. S. Bhatt, Sr. VP, PTC India Ltd. XIII. NATIONAL HYDROELECTRIC DEVELOPMENT CORPORATION

1. Shri R. B. Mathur, GM (ISP), NHDC

XIV. PTC INDIA LTD.

1. Shri Sanjeev Mehra, EVP

XV. BEST UNDERTAKING

1. Shri Atul G. Patil, CE XVI. NARMADA CONTROL AUTHORITY

1. Shri Hemant Pandey, AD(Power)

XVII. WESTERN REGIONAL POWER COMMITTEE

1. Shri S. G. Tenpe, SE (Comml.) 2. Shri O. P. Singh, SE (Opn.) 3. Shri M. M. Dhakate, AS 4. Shri S. Satyanarayan, EE (Prot.) 5. Shri V. K. Gupta, EE (Opn.)

Sr.No. PARTICULARS Jun-09 Jul-09 Aug-09

1 MAXIMUM FREQUENCY (Hz)

1.1 Integrated over an hour 50.25 50.40 50.14

1.2 Instantaneous 50.59 50.56 50.46

2 MINIMUM FREQUENCY (Hz)

2.1 Integrated over an hour 48.86 48.98 48.89

2.2 Instantaneous 48.69 48.74 48.62

3 AVERAGE FREQUENCY (Hz) 49.52 49.67 49.41

4.1 48.6 Hz 0 0 0

4.2 48.8 Hz 1144 82 855

4.3 51.0 Hz 0 0 0

5.1 Above 50.2 Hz 1.64 1.97 0.65

5.2 Above 50.3 Hz 0.52 0.56 0.14

5.3 Between 50.2 Hz & 49.5 Hz 49.40 71.19 37.57

5.4 Between 50.2 Hz & 49.2 Hz 79.17 93.33 73.47

5.5 Below 49.2 Hz 19.19 4.70 25.88

5.6 Below 49.8 Hz 77.82 66.30 87.07

5.7 Between 49.2 Hz & 50.3 Hz 80.29 94.74 73.98

5.8 Between 50.3 Hz & 48.5 Hz 99.48 99.44 99.86

Annexure-2.1(a)

FREQUENCY PARTICULARS OF WESTERN REGION FOR THE PERIOD JUNE 2009 TO AUGUST 2009

5

PERCENTAGE TIME WHEN FREQUENCY WAS

4

NUMBER OF TIMES FREQUENCY TOUCHED

ANNEX -2.1(b) (1/2)

June July August June July August June July August June July August

Availability (MW) 2558 2551 2795 8739 8206 9586 4668 4229 4508 13931 12847 13822

Unrestricted demand (MW)

2644 2637 2934 9098 8475 10179 5936 5358 5506 17586 16083 19555

Deficit(-)/Surplus(+)

(i) MW -86 -86 -139 -359 -269 -593 -1268 -1129 -998 -3655 -3236 -5733

( ii) % -3.25 -3.26 -4.74 -3.95 -3.17 -5.83 -21.36 -21.07 -18.13 -20.78 -20.12 -29.32

June July August June July August June July August June July August

Availability (MW) 377 379 378 220 222 223 451 454 460 29370 27629 30113

Unrestricted demand (MW)

420 421 449 245 247 248 488 454 499 34839 32455 37060

Deficit(-)/Surplus(+)

(i) MW -43 -42 -71 -25 -25 -25 -37 0 -39 -5469 -4826 -6947

(ii) % -10.24 -9.98 -15.81 -10.20 -10.12 -10.08 -7.58 0.00 -7.82 -15.70 -14.87 -18.75

POWER SUPPLY POSITION IN WR FOR PERIOD FROM JUNE 2009 TO AUGUST 2009 (IN MW)

MaharashtraDetails 

Chhatisgarh Gujarat Madhya Pradesh

Details Western RegionGoa Daman & Diu Dadra & Nagar Haveli

ANNEX -2.1(b) (2/2)

June July August June July August June July August June July August

Availability (MUs) 1038 1106 1248 5674 4860 5958 2632 2478 2629 8856 7957 8737

Unrestricted Requirement (MUs)

1066 1124 1297 5748 4892 6082 3427 2982 3225 10711 8947 10570

Deficit(-)/Surplus(+)

(i) MUs -28 -18 -49 -74 -32 -124 -795 -504 -596 -1855 -990 -1833

(ii) % -2.61 -1.62 -3.78 -1.28 -0.65 -2.04 -23.20 -16.92 -18.48 -17.32 -11.07 -17.34

June July August June July August June July August June July August

Availability (MUs) 240.39 223.16 227.24 144.09 152.98 150.85 297.95 341.92 331.02 18883 17118 19255

Unrestricted Requirement (MUs)

263.66 225.94 234.78 157.62 171.58 169.45 317.97 341.92 350.22 21691 18684 21902

Deficit(-)/Surplus(+)

(i) MUs -23.27 -2.78 -7.54 -13.53 -18.6 -18.6 -20.02 0 -19.2 -2809 -1566 -2647

(ii) % -8.83 -1.23 -3.21 -8.58 -10.84 -10.98 -6.30 0.00 -5.48 -12.95 -8.38 -12.09

Maharashtra

POWER SUPPLY POSITION IN WR FOR PERIOD FROM JUNE 2009 TO AUGUST 2009 (IN MUs)

Details Chhatisgarh Gujarat Madhya Pradesh

Details Western RegionGoa Daman & Diu Dadra & Nagar Haveli

Annexure - 3.1.2

A. New IPP projects in Chattishgarh

S.N Developer Capacity (MW)

LTOA (MW)

Unitwise comm schedule

Target Allocation-Region (MW)

RAIGARH COMPLEX WR* NR SR TOTAL 1 RKM Powergen Ltd.(4x360)

1440 1440 Mar'11,Jun'11,Sep'11,Dec'11 840 300 300 1440

2 Athena Chhattisgarh Power Ltd.(2x600) 1200 1200 Mar'12, Aug'12 823 377 1200

3 Jindal Power Ltd.(4x600) 2400 2400

Mar'12,Jul'12,Nov'12,Mar'13 1610 790 2400

4 Jindal Power Ltd.(1x500) 500 500 Existing 500 500 5 SKS Ispat & Power Ltd.(4x300)

1200 1200 Nov'11,Dec'11,Mar'12,Mar'12 800 400 1200

6 Korba West Power Co. Ltd.(1x600) 600 600 Jul'12 600 600

7 DB Power Ltd.(2x600) 1200 1200 Nov'11,Feb'12 818 382 1200 sub-total 8540 8540 5991 2249 300 8540 JANJGIR-CHAMPA COMPLEX 1 Wardha Power Co. Ltd (6x600) 3600 3600 Feb'12,Jun'12,Oct'

12,Feb'13, Jun'13,Oct'13

3600 3600

2 BALCO(4x300)

1200 900 Jun'10, Sep'10,

Dec'10, Mar'11 450 450 900

3 Vandana Vidyut Ltd.(2x135+1x270) 540

540 Apr'11,Dec'11,Mar'12

440 100 540

4 Lanco Amarkantak Power Pvt. Ltd.(2x660) 1320

1320 Mar'12,Jun'12

462 858 1320

5 Chhattisgarh Steel & Power Ltd.(1x35+1x250)

285 285 Existing, Dec'11 200 85 285

sub-total 6945 6645 5152 1493 0 6645 Total 15485 15185 11143 3742 300 15185 ** WR allocation also includes Chhattisgarh Share (3600 MW) @35% on a/c of FRR

B. Madhya Pradesh Generation Projects and Chattishgarh Generation Projects (pooled at Bilaspur Pooling Point)

a. IPPs near Bilaspur Pooling Station (Chhatisgarh)

Sl. No.

Applicant Gen. Project Capacity

(MW)

LTOA Applied for (MW)

Location Time Frame Quantum allocated in the region

WR NR 1. Maruti Clean Coal 300(1x300) 300 Near Bilaspur Jun’12 222 78 2. PTC (Dheeru) 600(3x350) -

part 600 Near Bilaspur Sep’12,

Dec’12, Mar’13 300 300

3. Dheeru Power Gen 450(3x350) - part

450 Near Bilaspur Sep’12, Dec’12, Mar’13

367.5 82.5

Total 1350 1350 889.5 460.5

Minutes of 11th WRPC meeting held on 25th September 2009 at Raipur

1

b. IPPs in M.P.

Sl. No.

Applicant Gen. Project Capacity

(MW)

LTOA Applied for (MW)

Location Time Frame Quantum allocated in the region

WR NR 1. Jaiprakash Power

Ventures Ltd. 1320(2x660) 1320 Near Nigri May’13,

Nov’13 908 412

2. Aryan Coal Benefications

1200(4x300) 1200 Near Sidhi Mar’13, Mar’14, Dec’14, Mar’15

900 300

Total 2520 2520 1808 712 C. Orissa Generation Projects:

LTOA Required (MW) Sl

noProjects

Generation Developer/ Open Access Applicant

Date of Commissi

oning

Installed Capacity

(MW) NR WR ER SR Total

1 Sterlite Sterlite Energy Ltd Jun-09 2400 200 200 - - 400 2 GMR GMR Kamalanga Energy

Ltd Sept -11 1050 600 - - 200 800

3 Navbharat Navabharat Power Pvt. Ltd Jul - 11 1050 465 255 - - 720 4 Monnet Monet Power Company

Ltd June-12 1050 300 375 225 - 900

5 Jindal Jindal India Thermal Power Ltd

March-11 1200 834 210 - - 1044

6 Lanco Babandh

Lanco Babandh Power Pvt Ltd

Dec-13 2640 650 950 - - 1600

7 Ind Barath

Ind Barath Energy(Utkal) Ltd

Sept-11 700 266 350 - - 616

Subtotal(Orissa) 10090 3315 2340 225 200 6080

D. Jharkhand and West Bengal (WBSEDCL) Generation Projects Allocation Sl

No Projects Developer/Applicant Time

Frame Ins. Cap

LTOA NR WR ER Total

A Jharkhand Projects 1 Adhunik Adhunik Thermal

Energy Ltd Mar-12 1005 910 500 350 850

2 Corporate Corporate Power Ltd Mar-12 660 594 594 594 3 ESSAR Essar Power

(Jharkhand) Ltd. Dec-11 1200 1100 400 400 300 1100

5 Dumka CESC Ltd.(Dumka) Jun-12 600 540 270 270 0 540

Subtotal 3465 3144 1764 670 650 3084 B West Bengal

Projects WBPDCL/WBSEDCL 2011-12 2000 2000 1200 800 - 2000

Total 5465 5144 2964 1470 650 5084

Minutes of 11th WRPC meeting held on 25th September 2009 at Raipur

2

HP_Owner
Text Box
Annexure - 5.2

Annexure-15 (1/3)

PROGRESS OF TRANSMISSION LINES UNDER CONSTRUCTION IN WESTERN REGIONSr.No.

Name of transmission line Length in Ckt. Km

Anticipated Completion

REMARKS

Target

A GUJARAT (July 2009)

I. 400 400 kV Lines

1 400 KV D/C Mundra (Adani) - Varsana D/C line 166.00 Feb-10 Work under Progress. ROW problems.2 400 KV Tappar( Varsana)-Hadala line 299.88 Feb-10 Work under Progress. ROW problems.3 400 KV Essar-Hadala line 232.00 Nov-09 Work under Progress. ROW problems.4 400 KV LILO to Kosamba from Asoj-Ukai 64.00 Foundation Work under Progress

II. 220 220 kV Lines1 200 kV LILO at Mota (Bardoli) S/S from 2nd Ckt. of Ukai (T)-Vav 9.60 Sept. 08 Line work complted. Feeder bay work

completed.LILO point jumper work pending.

2 200 kV D/C Utran-Kosambaat Kosamba S/S from Vav-Zagadia line 172.00 Oct-09 Check survey, foundation and Erection work under progress.

3 200 kV LILO Mangrol-Mobha D/C line 218.00 Jun-09 Foundation, erection & stringing work inprogress.ROW problem

4 220 KV D/C Chorania - Bala 59.12 Feb-09 Line charged on 29.04.095 220 KV D/C Rajpur-Dudhrej 19.16 Dec-08 Work completed.6 200 kV LILO at Dinod S/S (Kosamba) from Vav-Zagadia line 10.20 Mar.09 Line charged on 08.07.09

7 200 kV LILO at Chitrod from Deodar-Anjar 2.10 Line is ready. Feeder bay Work under progress.

8 200 kV LILO of Shivlakha-Nanikhakhar at Varsana one ckt at Kukma s/s

34.00 Mar.09 Work under progress. Severe ROW problem

9 220 KV D/C Mundra (Adani) - Varsana D/C line 166.00 Jun-09 Erection work under progress. RIW problem

10 200 kV LILO at Lakhani S/S from both Ckt of Kansari- Tharad line 8.00 Mar-10 Price bid opened. Tender under acceptance.

11 200 kV LILO at Botad S/S from Kasor- Vartej line 38.80 Oct-09 Agency finalized, work to be started.12 220 KV Varsana-Morbi 214.00 Aug-09 Work under progress. Severe ROW problem13 220 KV D/C Viramgam-Salejada 124.00 Nov-09 Work under progress.14 220 KV M/C LILO to Bhat from Viramgam-Salejada line 36.00 Nov-09 Work under progress.15 220 KV D/C Utran-Kosamba 86.00 Oct-09 Check survey, foundation and Erection work

under progress.ROW Problem.

B MADHYA PRADESH (June 2009)

I. 400 kV Lines

NILSr.No.

Name of transmission line Length in Ckt. Km

Anticipated Completion

REMARKS

Target

II. 220 220 kV Lines1 LILO of 1st Ckt. DCDS 200 kV Gwalior- Malanpur at 400KV Gwalior

PGCIL S/S16.90 2009-10 Work in Progress

2 200 kV Satna-Chhatarpur 140.00 2009-10 Work in Progress.

3 200 kV Amarkantak-Birsinghpur DCDS at 400kV s/s SUKHA(PGCIL) 300.00 2008-09 In principle Forest approval for 0.95 Hactare received. Final approval awaited. Work in progress.

4 220 kV Chhindwara-400 kV PGCIL Seoni D/C 140.00 2008-09 Work completed.Line charged on 20.05.09

5 LILO of one Ckt of 200 kV Jabalpur-Itarsi at Piparia S/S 7.20 2009-10 Work almost completed.Line charged upto the gantry of 220 kV Pipariya S/S

6 220 kV Bhopal (400 kV) -Ashta for Ashta S/S 194.00 2009-10 Work stopped due to contracters problem.

7 SujalpurPGCIL (400kV)-220kV Rajgarh Biaora line 134.40 2008-09 Work completed.

8 Jabalpur-Narsingpur part line for 400 kV PGCIL Sukha 158.00 2009-10 Work in Progress.

9 Chhindwara-Betul 270.00 2009-10 Work in Progress.134.4 kms survey completed

10 Chegoan-Nimrani 220.00 2009-10 Work in Progress.

11 LILO of one circuit of 220kV Satpura-Itarsi for 220kV Handia 220.00 2009-10 Work in Progress & Line charged on 12.06.09

12 Rerouting of 220kV Makronia Traction Feeder through 220kV Sagar 10.18 2008-09 Work completed.

13 LILO of second circuit of 220kV Pithampur-Ratlam line for 220kV Badnagar

20.29 2008-09 Work completed exept termination of gantry

14 LILO of 2nd Ckt. of 220 kV Itarsi-Bhopal for 220 kV Hosangabad 10.75 2009-10 Line charged on 13.06.0915 Astha-Bercha line 45.00 2009-10 Work in Progress16 Maheshwar-Pithampur 108.00 2009-10 Survey completed in forest area. In principal

forest approval received on 01.01.0917 Maheshwar-Nimrani 54.00 2009-10 Work commenced.18 Maheshwar-Rajgarh 230.00 2009-10 Survey completed in forest area. In principal

forest approval received on 01.01.0919 LILO of one circuit of 220kV Bhopal-Bina for Vidisha new S/S 42.32 2009-10 Work stopped as Contractor has not deployed

gang. Notice served to the Contractor

20 Dewas-Astha Line 146.00 2009-10 Work in Progress

Annexure- 15 (2/3)Sr.No.

Name of transmission line Length in Km

Anticipated Completion

REMARKS

Target

C CHHATTISGARH (July 2009)I. 400 400 kV Lines

1 LILO of 400 kV Korba (West)-Bhilai to Raipur DCDS 25.00 2009-2010 Order placed. Work to be started shortly.2 400 kV Korba(West)- Khedamara DCDS 220.00 2009-2010 Order placed. Work to be started shortly.

II. 220 220 kV Lines

1 200 kV Korba -Bishrampur DCSS 153.00 2009-2010 Case submitted for 2nd phase approval from AIG(FC) Min. of Env & Forest, New Delhi

2 LILO of 220 kV Bhatapara-Raipur (PGCIL) at Doma 21.47 2009-2010 Work under Progress.3 220kV DCDS Suhela-PGCIL Bhatapara line 13.53 2009-2010 Work under Progress.4 I/C 220 kV Raigarh-PGCIL Raigarh DCDS 10.39 2008-2009 Charged on 15.04.095 LILO of 200 kV Korba-Siltara at Mopka DCDS 12.14 2009-2010 Work under Progress.6 220 KV DCSS lines between 400 KV S/S Bhilai& Rajnandgaon+ 1 No.

bay at Khedamara49.82 2009-2010 Work completed & line charged on 18.07.09

7 220 kV DCSS Khedamara-220 KV s/s Bemetara+ 1 No. bay at Khedamara & 1 No. at Bemetara

50.90 2009-2010 Work under Progress.

8 220 kV DCDS lines Chhuri-Mopka(Bilaspur) 90.00 2009-2010 Order placed9 220 kV I/C between New Power House at Korba(E) to prposed 220 kV

Chhuri30.00 2009-2010 Work to be taken up

10 Diversion of 200 kV line from Korba(E)-Bhilai line emanating from 200 MW PH-II to Korba(E) and 200 kV I/C in between Korba(E) PH-II

30.00 2009-2010 Work to be taken up

11 Diversion of 200 kV line from Korba-Bhatpara and 200 kV I/C in between Korba(W) and proposed 200 kV Chhuri S/S using section of Korba-Amarkantak - I & II DCSS

14.00 2009-2010 Work to be taken up

12 Diversion of 200 kV Korba-Amarkantak Ckt.I&II to proposed 200/132KV Chhuri S/S DCSS

4.00 2009-2010 Work to be taken up

D (MAHARASHTRA) (Jun 2009)

I. 400 400 kV Lines

1 400 kV Dabhol- Nagothane Ckt II 135.56 Dec-09 Severe ROW Problems in Vadvali village2 Diversion of 400 KV Chandrapur-Parli S/C line for WCL 7.50 Jun-09 Work is slow due to ROW problems3 Diversion of 400 KV Chandrapur-Parli D/C line for WCL 29.00 Jun-09 Work is slow due to ROW problems4 400 KV D/C line from Bhusawal II to A'bad(Loc. No. 1 to 270) 190.00 Mar-10 Work in progress5 400 KV D/C line from Bhusawal to A'bad(Loc. No. 270 -Waluj) 88.02 Mar-10 Work in progress6 400 KV Jaigad-New Koyana D/C line 114.00 Dec-09 Work in progress7 400 KV Jaigad-New Karad D/C line 224.00 Jun-10 Work in progress8 400 KV D/C line from Bhusawal II to existing 400 KV Khadka 15.00 Dec-09 Work in progress9 LILO on 400 KV Lonikhand-Padghe S/S line for 400 KV Chakan S/S 3.00 Jul-09 Work in progress10 400 KV S/C line from 400 KV New Khaerkheda-400 KV Koradi 5.00 Jul-09 Checked Survey Completed. Exccavation

work in progress

11 LILO on 400 KV Koradi-Chandrapur S/S line for 400 KV New Khaperkheda S/S

1.50 Jul-09 Checked Survey Completed. Exccavation work in progress

II. 220 220 kV Lines

1 LILO on 220 kV Tarapur-Borivali for 220 kV Boisar-II S/S 8.00 Mar-10 Forest proposal recommended by Dy. COF Dahanu to Chief Conservator Thane. Court case at Loc.No.11

2 220 kV line from PGCIL to 220 kV Wada S/S 57.00 Mar-10 Work held up due to Court cases & forest clearance approval requirement

3 LILO of 220 kV Nasik-Kalwa Ckt. 3&4(Padghe-Kalwa) for Bapgaon S/S 3.00 Mar-10 Work held up due to local problem. Written to Collector for protection.

4 220 KV Nagothane-Wadkhal D/C line 30.00 Mar-10 Severe ROW Problems. Extension of contract proposal is under process at C.O.

5 LILO on 220 kV Padghe-Kalwa for Temghar S/S 1.50 Jun-09 Work is delayed due to shifting of PT(Dt. 13.12.08) which involved outage.

6 LILO on 220 kV Mulund-Borivali of XLPE underground cable for Bhandup GIS S/S

3.00 Dec-09 Permission for Under ground cable duct is awaited from MCGM.

7 220 kV D/C from Phursungi S/S TO 400 kV Jejuri S/S 62.00 Mar-10 Check survey started from 23.12.08

8 LILO on 220 kV Chinchwad-Kandalgaon for Hinjewadi-II S/S 10.00 Jun-09 Stringing except single phase between Loc. No.6-8 is balance due to clearence of 22 kV

9 220 kV D/C on M/C tower from 400 kV PGCIL Talegaon to 220 kV Urse S/S

10.27 Dec-09 One ckt.commissioned on 21.08.08. Court case for 2nd ckt. Strg. Between Loc. No. 4-5 is carried out on 21.02.09.

10 Shifting of 220 kV Telco Bhosari interconnecting bay at Chinchwad S/S 0.50 Dec-09 Work stopped as S/S gantry is not erected& 22kV line shifting is to be done by MSEDCL.

11 220 kV D/C line from 400 kV Chakan to M/s Volks Wagen Chakan 4.68 Jun-09 Work in Progress.

12 220 kV D/C line on M/C towers LILO to 220 kV Bhosari-Chinchwad line at 400 kV Chakan S/S

18.00 Dec-09 Check survey under progress.

13 220 kV LILO on 2nd ckt. Kolhapur Phonda line 220 kV Mumewadi 2.00 Sep-08 Work in Progress.

14 220 kV LILO on 2nd ckt. Kolhapur Phonda line 220 kV Halkarni 20.00 Sep-08 Work in Progress.

15 220 kV LILO on Pusad-Girawali(Nanded) for Hingoli 44.00 Sep-09 Work in Progress.

16 220 kV Chitegaon-Shendra D/C line 43.10 Mar-10 Work not started

17 Reorientation of 220 kV Padegaon I&II, Babhaleshwar I&II, Chitegaon I&II and Jalna I&II at Aurangabad

3.00 Dec-09 Survey started

18 220kV D/C on D/C Tower from Jeurparanda 30.00 Jun-10 Work not started

19 220 kV D/C line BEED-PATODA 45.00 Jun-10 Work not started

20 220kV Parli TPS-Nanded M/C line(Waghala) 90.30 Jun-10 Work not started

21 220 kV D/CJalna-Chikhali 150.00 Dec-10 Work not started

22 220 kV D/C on D/C tower from 400 kV Bhusaval II to 220 kVAmalner S/S

182.00 Mar-10 Work in Progress.

23 220 kV D/C line on M/C towers from 400/220 kV new Bhusaval S/S to existing 400 kV Khadka

20.00 Nov-09 Work in Progress.

E POWERGRID (July 2009)

765 & 400 kV & 400 kV Lines

1 Sipat-II Supplimemtary Trans. System1.1 765 S/C Seoni-wardha (to be operated at 400kV) 268.0 Apr-09 Commercial Opn. w.e.f. 01.04.09

1.2 400 kV D/C Wardha-Akola 324.0 Apr-09 Commercial Opn. w.e.f. 01.04.09

1.3 400 kV D/C Akola-Aurangabad 482.0 Oct-09 Final checking under progress

Annexure- 15 (3/3)

Sr.No.

Name of transmission line Length in Ckt. Km

Anticipated Completion

REMARKS

Target

2 Western Region Stregthening Scheme-II2.1 SET-A: For absorbing import in eastern&central part of WR2.1.1 765 KV 2nd S/C Seoni(PG)-Wardha(PG) (initially to be operated at

400kV)270 Mar-11 Foundation commenced from Jun' 09

2.1.2 400 kV D/C Wardha (PG)-Parli (PG)(Quad.) 682 -2.1.3 400 kV D/C Raipur(PG)-Wardha(PG) 736 -2.1.4 400 kV D/C Bhadravati (PG)-Parli(PG) 776 -2.1.5 400 kV D/C Parli(MSEB)-Parli(PG) 14 - Engg. & survey under progress.2.2 SET-B: For Regional strengthening in southern Maharashtra (to be

implemented through IPTC route)- Awaiting approval from MOP under section

164. Phisical construction work to be initiated on receipt of this clearance.

2.2.1 400 kV D/C Parli(PG)-Pune 616 -2.2.2 400 kV D/C Pune(PG)-Aurangabad(MSEB) 450 -2.2.3 400 kV D/C Parli(PG)-Pandharpur/Solapur 392 -2.2.4 400 kV D/C Pandharpur/Solapur(PG)-Kolhapur(MSEB) 378 -2.2.5 LILO of Lonikhand(MSEB)-Kalwa(MSEB)400 kV D/C at Pune(PG) 48 -2.2.6 LILO of Solapur(MSEB)-Karad(MSEB)400 kV D/C at

Pandharpur/Solapur(PG)52 -

2.3 SET-C: For Regional strengthening in Gujarat (to be implemented through IPTC route)

- Awaiting approval from MOP under section 164. Phisical construction work to be initiated on receipt of this clearance.

2.3.1 400 kV D/C Rajgarh(PG)-Karamsad(GEB) 480 -2.3.2 400 kV D/C Limbdi(Chorania)(GEB)-Ranchodpura(Vadavi)(GEB) 190 -2.3.3 400 kV D/C Ranchodpura(Vadavi)(GEB)-Zerda(Kansari)(GEB) 310 -2.4 SET-D: For Regional strengthening in Northern Madhaya Pradesh

2.4.1 Bina(PG)-Gwalior(PG) 765 kV 2nd Ckt.to be operated at 400kV 233 Jul-102.4.2 400 kV D/C Korba(NTPC)-Birsighpur(MPGENCO) 453 Jul-102.4.3 400 kV D/C Birsighpur(MPGENCO)-Damoh(PG) 454 Jul-102.4.4 400 kV D/C Damoh(PG)-Bhopal(MPSEB) 430 Jul-102.5 Trans. Sy. Associated with Gandhar-II (GBPP) -2.5.1 400 kV D/C Gandhar-Kawas 190 * 33 months from investment approval or from2.5.2 400 kV D/C Gandhar-Rajkot 600 * date of tying up of FSA by NTPC whichever 2.5.3 LILO of 400 kV D/C Bina-Nagda at Shujalpur 60 * is later3 Western Region Stregthening Scheme-V3.1 400 kV Vapi(PG)-Navi Mumbai D/C line 277 Sep-10 Severe Row problem being faced in

Maharashtra&DNH on allmost all locations.3.2 220 kV Vapi-Khadoli(UT of DNH) D/C line 56 Sep-103.3 LILO of Lonikhand(MSEB)-Kalwa(MSEB) 400 kV S/C line at Navi

Mumbai 10 Sep-10 Engg. & survey in progress

4 Western Region Stregthening Scheme-VI4.1 400 kV D/C Dehgam - Pirana line 106 Nov-105 Western Region Stregthening Scheme-IX5.1 LILO of 400 kV D/C Bina-Nagda line 60 Jan-11 Tendering under progress

6 Inter-regional lines

6.1 East-West Transmission corridor strengthening scheme

6.1.1 400 kV D/C Ranchi - Rourkela286 Mar-10 Row problem being faced due to extremists in

Jharkhand6.1.2 400 kV D/C Rourkela - Raigarh 440 Mar-106.1.3 400 kV D/C Raigarh - Raipur 440 Mar-106.2 Transmission System associated with Barh Generation Project

6.2.1 765 kV S/C Seoni - Bina line (to be charged at 400kV) 293 Dec-096.3 Transmission System associated with North west Transmission

corridor strengthening scheme6.3.1 765 kV Agra - Gwalior 2nd S/C line (initially to be operated at 400kV) 128 Mar-09 Commercial Opn. w.e.f. 01.04.09

GENERATION SCHEMES UNDER CONSTRUCTION DURING 11th PLAN IN WESTERN REGION

Sr. No. Name of the Power Projects Unit No. Capacity (MW)

Schedule Date of Commissioning

A GUJARAT

Generation Schemes included in 11th Plan

1 Kutch Lignite TPS 4 75 Commissioned on 22.10.2008

2 Sugen CCPP (Torrent Power Gen. Ltd.) Block -1 382.5 Commissioned on 20.11.2008

Block-2 382.5 Synchronised on 29.01.09

Block-3 382.5 Synchronised on 27.03.09

3 Surat Lignite expansion- GIPCL 1 125 Nov. 2009

2 125 Mar. 2010

4 Utran GPP GT+ST 374 GT syncd. On 10.07.09

5 Sikka TPP Extn. 3 250 Jan. 2010

4 250 May. 2010

6 Ukkai TPS Extn. 6 490 Feb. 2011

7 Pipavav CCPP- GPCL & GSPC joint venture Block-1 350 Sep. 2010

Block-2 350 Mar. 2011

8 Mundra TPP Ph-1 (Adani Power Ltd.) 1 330 Syncd. On 23.5.09

2 330 Oct. 2009

9 Mundra TPP Ph-2 (Adani Power Ltd.) 3 330 Feb. 2010

4 330 May. 2010

10 Mundra Ultra Mega TPP (Tata Power Ltd.) 1 800 Sep. 2011

2 800 Mar. 1012

11 Hazira CCPP Expansion GSEG GT+ST 350 Apr. 2010

Other Projects

1 Gujarat Lignite-NLC & GPCL joint venture Stage-I 1500 2011-12

Stage-II 500 2012-13

2 Dhuvaran CCPP GSECL Stage-III 360 Mar. 2010

3 Pipavav TPP- Torrent Power 1000 2011-12

4 Bhavnagar Lignite TPP-joint venture 500 Apr. 2011

5 Mundra STPP (Adani Power Ltd.) 1 660 Jan. 2011

2 660 June. 2011

B MADHYA PRADESH

Generation Schemes included in 11th Plan

1 Amarkantak TPS 5 210 Commissioned on 15.06.2008

2 500 Apr. 2011

2 Satpura TPS Extn. 10 250 Nov. 2010

11 250 Mar.2011

Other Projects

1 Maheshwar HEP - 400 2010-11

2 Malwa TPP 1 500 Dec. 2010

Annexure-16 (1/2)

Sr. No. Name of the Power Projects Unit No. Capacity (MW)

Schedule Date of Commissioning

C CHHATTISGARH

Generation Schemes included in 11th Plan

1 Jindal PL 1 250 Commissioned on 08.12.07

2 250 Commissioned on 16.04.08

3 250 Commissioned on 15.06.08

4 250 Commissioned on 17.06.08

2 LANCO Amarkantak PL 1 300 Synchronised on 01.05.2009

2 300 Aug. 2010

3 Marwa TPP 1 500 Sept. 2012

2 500 Dec. 2012

4 Korba West-III TPP 1 500 Jun. 2012

Other Projects

1 Bhaiyathan TPP Phase-I 1 500 Dec. 2012

2 500 Aug. 2013

2 IFFCO 1 660 Aug.2012

2 660 Dec.2012

D MAHARASHTRA

Generation Schemes included in 11th Plan

1 New Parli TPS Extn. 2 250 Nov. 2009

2 Paras TPS Extn. 2 250 Dec. 2009

3 Khaperkheda TPP Extn. 1 500 Mar. 2010

4 Bhusawal Extn. TPP 1 500 May. 2010

2 500 Sep. 2010

5 Trombay TPS Extn. (Tata Power Co.) 8 250 Commissioned on 14.01.2009

6 Ghatghar HPS (Hydro) 1 125 Commissioned on 13.05.08

2 125 Commissioned on 01.07.08

7 JSW Ratnagiri TPP (JSW Energy (Ratnagiri) Ltd.) 1 300 Feb. 2010

2 300 Sep. 2010

3 300 Dec. 2010

4 300 Mar. 2011

Other Projects

1 Koradi TPS Extn. 1 800 Oct. 2012

2 Dhopawe TPP 1 800 Nov. 2011

2 800 May 2012

3 Uran CCPP Block-1 700 Feb. 2010

Block-2 340 May-10

4 Koradi TPS Extn. (Replacemet of 4 x 120) 1 800 Apr 2012

5 Parli TPS (Replacement of 2x30) 1 250 May. 2010

6 Paras TPS (Replacement of 1x62.5) 1 250 May. 2010

7 Bhusawal TPS (Replacement of 1x62.5) 1 250 May. 2010

8 Chandrapur TPS Extn. 1 500 Dec. 2011

2 500 May. 2012

E CENTRAL SECTOR - NTPC

Generation Schemes included in 11th Plan1 Sipat-II TPP 5 500 Commissioned on 27.12.08

2 Sipat-I TPP 1 660 Nov. 2010

2 660 May. 2011

3 660 Nov. 20113 Bhilai TPP (Joint venture with SAIL) 1 250 COD w.e.f 22.4.2009

2 250 Synchd. on 28.03.09

4 Korba STPS-III 7 500 May. 2010

5 Mauda TPP 1 500 2011-12

2 500 2012-12

Annexure-16 (2/2)