National Broadband Network - A risk assessment and cost-effectiveness analysis

136
NATIONAL BROADBAND NETWORK A RISK ASSESSMENT AND COST-EFFECTIVENESS ANALYSIS by DARRYN MCCLELAND The School of Information Technology and Electrical Engineering, University of Queensland Submitted for the degree of Bachelor of Engineering (Honours) in the division of Mechatronic Engineering OCTOBER 2010

Transcript of National Broadband Network - A risk assessment and cost-effectiveness analysis

 

NATIONAL BROADBAND NETWORK

A RISK ASSESSMENT AND COST-EFFECTIVENESS ANALYSIS

by

DARRYN MCCLELAND

The School of Information Technology and Electrical Engineering,

University of Queensland

Submitted for the degree of

Bachelor of Engineering (Honours)

in the division of Mechatronic Engineering

OCTOBER 2010

School of Information Technology and Electrical Engineering,

The University of Queensland,

St Lucia QLD 4072

Dear Professor Paul Strooper,

In accordance with the requirements for the degree of Bachelor of Engineering (Honours) in

the School of Information Technology and Electrical Engineering, I submit the following

thesis entitled

“National Broadband Network: A Risk Assessment and Cost-Effectiveness Analysis”.

This thesis was performed under the supervision of Professor David A. Williams. I declare

that the work submitted in this thesis is my own, except where acknowledged in the text, and

has not been previously submitted for a degree at The University of Queensland or any other

institution.

Yours sincerely,

Darryn McCleland

i

ABSTRACT The rollout of the new $43bn National Broadband Network is the largest ever infrastructure

project in Australia. This thesis conducts a thorough risk assessment and cost-effectiveness

analysis on the numerous hazards facing the NBN project. The risk assessment identifies 59

hazards under 7 main failure modes of: Construction, Operation, Demand, Network,

Technology, Financing and Regulation. The most significant contributors to the overall risk

ranking are the Regulatory hazards due to the political sensitivity and lack of regulation

surrounding the NBN Co and telecommunication implementation policies. This is closely

followed by Financial hazards due to the high cost of the $43bn project and the lack of

interest from private investors due to the extended return on investment period. The

underlying key hazards include, scope creep, increased demand for high speed broadband,

increased demand for mobility/wireless connectivity, overseas bottlenecks in network design,

high prices charged by Wholesaler/ISPs, lack of private investment, lack of

telecommunication and market competition policies, and political instability.

Several remedial actions are suggested to address the key hazards and reduce the overall risk.

These include: Liberal Party’s broadband plan, NBN 3.0, NBN 3.1, NBN 3.2, domestic

caching and regulatory reform policies. The most cost-effective remedial option is a

combination of the NBN 3.0 and domestic caching, which resulted in a 61.8% reduction in

risk. This option provides a purely 4G wireless network with domestic caching relocating key

static media to domestic servers to avoid overseas bottleneck data rates. While this option is

the most cost-effective due to its low price, it still doesn’t address some key concerns for

Australia’s broadband future. The NBN 3.2 plan, which is a combination of the Liberal’s

broadband plan and NBN 3.0 wireless network, focuses on sufficient fibre infrastructure

upgrades and the demand for mobile connectivity options. When combined with domestic

caching and regulatory reform, it results in a risk reduction of 62.4%, the lowest overall risk

ranking for the NBN Risk Model. While not the most cost-effective solution due to its slightly

higher construction costs, this plan is recommended for the inherent benefits that both

wireless and fixed HFC connection options provide to the public.

ii

ACKNOWLEDGMENTS 

Firstly I would to thank Professor David Williams who not only presented me with the

opportunity to undertake a thesis that I found genuine interest in, but also provided support

and guidance in completing such a demanding thesis. His insight and ideas helped lead me

down new and exciting paths of research.

I would also like to thank my family for providing me with the opportunity to attend the

highly regarded and acclaimed University of Queensland. The knowledge and skills I have

gained whilst studying at the University of Queensland will continue to foster my career

aspirations.

iii

Table of Contents Abstract......................................................................................................................................i Acknowledgments ....................................................................................................................ii List of Tables ............................................................................................................................v List of Figures..........................................................................................................................vi List of Abbreviations ........................................................................................................... viii Definitions................................................................................................................................ix 1.  Introduction.......................................................................................................................1 

1.1.  Aims.............................................................................................................................1 1.2.  Scope............................................................................................................................1 1.3.  Limitations ..................................................................................................................2 

2.  Literature Review .............................................................................................................5 2.1.  Risk ..............................................................................................................................5 2.2.  Risk Assessment .........................................................................................................5 2.3.  Acceptable Risk ..........................................................................................................7 2.4.  Fault/Event Tree Analysis .........................................................................................8 

3.  Theory ................................................................................................................................9 3.1.  Background.................................................................................................................9 

3.1.1.  Australia’s Current Broadband Situation ..............................................................9 3.1.2.  Importance of Broadband ....................................................................................11 

3.2.  Construction Hazards..............................................................................................15 3.2.1.  Labour Shortage ..................................................................................................15 3.2.2.  Scope Creep.........................................................................................................17 3.2.3.  Latent Grounds ....................................................................................................19 

3.3.  Operational Hazards................................................................................................21 3.3.1.  Contention ratio ...................................................................................................21 3.3.2.  Maintenance and Equipment (Fibre) Failure.......................................................22 3.3.3.  Security – Cyber Crime, Spam and Intellectual Property ...................................23 

3.4.  Demand Hazards......................................................................................................25 3.4.1.  Decreased Demand..............................................................................................25 3.4.2.  Increased Demand ...............................................................................................32 

3.5.  Network Hazard .......................................................................................................37 3.5.1.  Design Bottlenecks..............................................................................................37 

3.6.  Technological Hazards.............................................................................................41 3.6.1.  Wireless Technologies.........................................................................................41 

3.7.  Financial Hazards ....................................................................................................49 3.7.1.  Financing Vehicles ..............................................................................................50 3.7.2.  Private Investment ...............................................................................................53 3.7.3.  Operating Revenue ..............................................................................................55 

3.8.  Regulatory Hazard...................................................................................................57 3.8.1.  Regulatory Policies..............................................................................................57 3.8.2.  Telstra’s Fibre Network and Customer Base.......................................................59 3.8.3.  Political Instability...............................................................................................59

iv

4.  Methodology ....................................................................................................................63 4.1.  Risk Assessment .......................................................................................................63 4.2.  Sensitivity Analysis...................................................................................................65 4.3.  Cost-Effectiveness Analysis (CEA).........................................................................65 

5.  Results ..............................................................................................................................67 5.1.  Fault Tree Analysis (FTA).......................................................................................70 5.2.  Key Hazards .............................................................................................................79 5.3.  Sensitivity Analysis...................................................................................................82 5.4.  Remedial Actions......................................................................................................83 

5.4.1.  Liberal’s national broadband plan .......................................................................83 5.4.2.  NBN 3.0...............................................................................................................85 5.4.3.  Domestic Caching ...............................................................................................87 5.4.4.  Regulatory Reform: .............................................................................................90 

5.5.  Cost-Effectiveness Analysis .....................................................................................93 6.  Discussion ........................................................................................................................97 

6.1.  Sensitivity analysis ...................................................................................................97 6.2.  Cost-Effectiveness ....................................................................................................99 6.3.  Financial Concerns.................................................................................................103 

6.3.1.  How much should an NBN cost? ......................................................................103 6.3.2.  Demand Concerns .............................................................................................106 

6.4.  Limitations and recommendations for further work..........................................107 7.  Conclusion and Recommendations .............................................................................109 Appendices............................................................................................................................113 

Appendix A - Labour Shortages .....................................................................................113 Appendix B - Telstra Case Study....................................................................................114 

Method 1.........................................................................................................................114 Method 2.........................................................................................................................115 

Appendix C – Companion Disk (NBN Risk Model)......................................................116 References.............................................................................................................................117  

v

LIST OF TABLES Table 2.1 Risk Matrix Example .................................................................................................7 

Table 3.1 NBN Estimated Construction Costs [12].................................................................19 

Table 3.2 ISP’s Fibre Prices ....................................................................................................29 

Table 3.3 List of submarine fibre optic cables connecting Australia [36]...............................38 

Table 3.4 Advancements in mobile communication data rates [42], [43], [44], [45], [41] .....42 

Table 3.5 Wireless Technology Fit for Market Needs [41] .....................................................43 

Table 3.6 FTTP versus Wireless last mile connection.............................................................47 

Table 3.7 ABS Internet Activity, December 2009 [47] ...........................................................56 

Table 3.8 Labour’s NBN versus Liberal’s proposed broadband network ...............................59 

Table 4.1 Likelihood Ratings...................................................................................................63 

Table 4.2 Consequence Ratings...............................................................................................64 

Table 5.1 Identified Hazards and Likelihoods of Failure ........................................................68 

Table 5.1 Technological Hazards FTA....................................................................................71 

Table 5.2 Risk Assessment Results .........................................................................................79 

Table 5.3 Sensitivity Analysis Results ....................................................................................82 

Table 5.4 Current NBN plan versus NBN 3.0 .........................................................................85 

Table 5.5 Consumer Internet Traffic Forecast by Sub-Segments [31] ....................................87 

Table 5.6 Remedial Action Costs ............................................................................................93 

Table 5.7 Cost-Effectiveness Analysis of combination of remedial actions ...........................94 

Table 6.1 Percentage of Risk Reduction................................................................................101 

Table A.1 Forecasted BAU ICT Labour vs. NBN Demand for Labour ................................113 

vi

LIST OF FIGURES Figure 3.1 Average monthly subscription price for broadband, 2009 [9] ...............................10 

Figure 3.2 Fastest residential broadband download speed advertised, 2009 [9] .....................10 

Figure 3.3 Percentage of fibre connections in total broadband subscriptions, 2009 [9]..........11 

Figure 3.4 Contributions of ICT investment to GDP growth [10]...........................................12 

Figure 3.5 OECD correlation between broadband penetration and GDP per capita [10]........13 

Figure 3.6 Forecasted BAU ICT Labour vs. NBN Demand for Labour .................................16 

Figure 3.7 Price Floor’s Surplus Effect ...................................................................................26 

Figure 3.8 Average monthly subscription price for very high-speed connections ..................26 

Figure 3.9 Average monthly subscription price for medium-speed connections ....................27 

Figure 3.10 Range of broadband prices per Mbps by country [10] .........................................28 

Figure 3.11 Diffusion of Innovations ......................................................................................30 

Figure 3.12 Cisco’s Forecasted Global IP Traffic Growth Rate [31] ......................................32 

Figure 3.13 Access speeds required by applications [32]........................................................33 

Figure 3.14 Fixed Bandwidth Demand [33] ............................................................................34 

Figure 3.15 The three stages of broadband user experience [32] ............................................34 

Figure 3.17 Australia’s submarine cable connections [1]........................................................39 

Figure 3.17 Advancements in mobile communication data rates (log graph) .........................45 

Figure 3.18 4th Generation wireless speed tests for multiple users [33] ..................................46 

Figure 3.19 Indicative shares of public infrastructure investment by financing vehicle in

Australia and the United Kingdom (2006-2007) [2] .......................................................51 

Figure 3.20 NBN Project IRR versus required returns for private sector equity [17] .............53 

Figure 3.21 Aggregate fibre take-up scenarios [17] ................................................................55 

vii

Figure 3.22 Priority release sites across Australia [58] ...........................................................61 

Figure 5.1 Construction Hazards FTA.....................................................................................70 

Figure 5.2 Operational Hazards FTA ......................................................................................71 

Figure 5.3 Demand Hazards FTA............................................................................................72 

Figure 5.4 Network Hazards FTA ...........................................................................................73 

Figure 5.5 Technological Hazards FTA ..................................................................................74 

Figure 5.6 Financial Hazards FTA ..........................................................................................75 

Figure 5.7 Regulatory Hazard FTA .........................................................................................76 

Figure 5.8 Combination of individual FTAs leading to Top Event.........................................77 

Figure 5.9 Risk ranking results for various hazards to the NBN.............................................80 

Figure 5.10 Consumer Internet Traffic Forecast by Sub-Segments [31].................................88 

Figure 6.1 Sensitivity Analysis ................................................................................................97 

Figure 6.2 Telstra’s five-year share price, September 2006-2010 [66] .................................104 

Figure 6.3 Telstra versus ASX 200, September 2006-2010 [66]...........................................105 

Figure B.1 Telstra’s Revenue and product profitability [67].................................................114 

viii

LIST OF ABBREVIATIONS AAB Alliance for Affordable Broadband

BAU Business As Usual

CAGR Compound Annual Growth Rate

CDN Content Delivery Network

CEA Cost-Effectiveness Analysis

DSL Digital Subscriber Line

FTA Fault Tree Analysis

FTTN Fibre to the Node

FTTP Fibre to the Premises

Gbps Gigabits per second

GTEs Government Trading Enterprises

HFC Hybrid Fibre Copper

ICT Information Communication Technology

IP Internet Protocol

IPTV Internet Protocol Television

Kbps Kilobits per second

LTE Long Term Evolution

Mbps Megabits per second

MIMO Multiple Input Multiple Output

NBN National Broadband Network

OECD Organisation for Economic Co-operation and Development

OLT Optical Line Terminal

ONT Optical Networking Terminal

PAYGO Pay As You Go

PB Petabyte

PFI Private Financing Initiative

PPP Private Public Partnership

RBBP Regional Backbone Blackspot Priority

RRR Required Rate of Return

TCO Total Cost of Ownership

WACC Weighted Average Cost of Capital

Wi-Fi Wireless Fidelity

Wi-Max Worldwide Interoperability Microwave Access

ix

DEFINITIONS 

1. Broadband – download data transfer rates equal to or greater or greater than 256kbps

in accordance with OECD standards

2. Harm – Physical injury or damage to health, property or the environment

3. Hazard – Source of potential harm or a situation with a potential for harm

4. Hazardous event – Event which can cause harm

5. Hazard identification – Process of recognising that a hazard exists and defining its

characteristics

6. High speed Broadband – download data transfer rates equal to or greater than 10Mbps

7. Infrastructure bonds - A financial instrument by which the bond holder loans money

to the government for a fixed term and receives periodic interest payments. On

maturity, loan money is returned to the bond holder.

8. Last mile - is the final leg of delivering connectivity from a communications provider

to a customer

9. Latency – is a measure of the time delay experience in a system.

10. PAYGO - is the practice of financing expenditures with funds that are currently

available rather than borrowed.

11. Public good - is a good that is non-rivalrous and non-excludable, which results in

positive externalities that are not remunerated.

12. Risk – Combination of the frequency, or probability, of occurrence and the

consequence of a specified hazardous event

13. Risk analysis – Systematic use of available information to identify hazards and to

estimate the risk to individuals or populations, property or the environment

14. Risk assessment – Overall process of risk analysis and risk evaluation

15. Risk control – Process of decision-making for managing and/or reducing risk; its

implementation, enforcement and re-evaluation from time to time, using the results of

risk assessment as one input

16. Risk estimation – Process used to produce a measure of the level of risk being

analysed. Risk estimation consists of the following steps: frequency analysis,

consequence analysis and their integration.

17. Risk evaluation – Process in which judgements are made on the tolerability of the risk

on the basis of risk analysis and taking into account factors such as socio-economic

and environmental aspects.

x

18. Risk management – Systematic application of management policies, procedures and

practices to the tasks of analysing, evaluating and controlling risk.

19. RRR - The minimum rate of return that an investment must provide or must be

expected to provide in order to justify its acquisition.

20. System – Composite entity, at any level of complexity, of personnel, procedures,

materials, tools, equipment, facilities and software. The elements of this composite

entity are used together in the intended operational or support environment to perform

a given task or achieve a specific objective.

21. WACC – The calculation of a firm's cost of capital in which each category of capital

is proportionately weighted.

1

1. INTRODUCTION The National Broadband Network (NBN) is Australia’s largest ever infrastructure project,

costing $43 billion to construct over 9 years. It is a Labour government initiative undertaken

to provide high speed broadband to all Australians. Fibre optic connections will be provided

to 90% of Australian premises, providing speeds of 100Mbps, while the remaining rural and

remote areas will be serviced by a combination of wireless or satellite technologies providing

speeds of at least 12Mbps. The following introductory section establishes the aims, scope and

limitations of the following risk assessment and cost-effectiveness analysis of the NBN.

1.1. AIMS  

This thesis seeks to identify the inherent risks associated with undertaking the NBN project,

provides remedial actions to address the most severe risks and analyses the cost effectiveness

of the remedial actions. The risk assessment identifies relevant hazards and through

quantitative analysis assigns likelihoods (probabilities of failure) of hazards occurring along

with the respective consequence ratings of such hazards. A sensitivity analysis helps to

identify the effect of the inputs of likelihood and consequence on the overall risk ranking

output. Remedial actions are then identified to address the most severe hazards and to either

target the likelihood or consequence based on the sensitivity analysis results. The cost-

effectiveness analysis compares the relative costs and outcomes of the various remedial

actions. The most cost-effective solution can then be suggested to minimise risks of the NBN

project.

1.2.  SCOPE  

This risk assessment identifies risks associated with the NBN project as of 2010. The

proposed remedial actions are designed to target the current foreseeable risks of the project.

As the NBN project’s rollout is over a 9 year period, there will be another election during the

construction phase. The immediate effects of this election on risk will be considered,

however the resulting effect on the NBN project should a change of ruling party come about

2

cannot be accurately foreseen and is beyond the scope of this thesis. As such, risks and

remedial actions have been identified based on the following assumptions:

• The Australian Labour Party is the ruling political party.

• The NBN plan incorporates a $43 billion investment, with FTTP for 10% of Australians

and remaining premises being serviced by a combination of wireless and satellite

technologies. The project is expected to take 9 years to rollout and commenced in 2010.

In order to conduct the risk assessment and assign likelihood ratings, the modes of failure for

the NBN must be fully understood. The following factors will act as performance measures

for the project:

• Financial - exceeding the budgetary constraint of $43 billion by 10%,

• Project delivery - exceeding the build time of 9 years by 10 months,

• Project life span – failure to remain operational for 20 years from first build without the

need for significant upgrades,

• Geographic - failure to reach at least 90% of the Australian population with high speed

broadband (i.e. above 10Mbps), and

• Geographic – failure to provide at least 99% of the Australian population with broadband

services (i.e. above 256Kbps).

Likelihood ratings are assigned to the various hazards with these performance measures in

mind.

1.3. LIMITATIONS  

Any risk analysis should be comprehensive, but it must remain feasible given the available

time and resources. A $25 million preliminary implementation study into the National

Broadband Network by KPMG McKinsey provides an indication of the amount of time and

financial resources this $43 billion infrastructure project requires.

3

A Risk assessment is a process that does not result in a fixed final answer. Due to the nature

of the NBN project and the duration of the risk assessment being conducted over a 10-month

period, certain contributing factors were in a state of transition.

These include:

• Political instability due to the Federal election

• Recovering economic climate post global financial crisis

• Initial stage 1 testing and installation of fibre network in Tasmania

The risk assessment and cost-effectiveness analysis has been conducted with the above

factors in mind.

4

5

2. LITERATURE REVIEW The following literature review highlights prior research and risk assessment methods. The

Fault/Event Tree Analysis method is also discussed as a hazard identification and causal

relationship tool.

2.1. RISK 

Risks in infrastructure projects are usually broken down into seven main failure modes of;

Construction, Operation, Demand, Network, Technology, Financial and Regulation [2]. Risk

can be further classified into two categories; voluntary and involuntary. Voluntary risks are

those willingly undertaken by an individual having control over their actions. Normal risks

associated with living in society, such as those incurred through exposure to crime, aircraft

crash on housing, domestic gas explosions etc. are usually considered to be of the involuntary

type [3]. Risk is said to exist if there are potential sources of damage or hazard and risk is the

combination of damage plus uncertainty of the hazard occurring. In engineering applications,

risk is formally defined as the product of the probability of failure and consequences [4]:

Risk = (Probability of failure) x (Consequences of failure)

2.2. RISK ASSESSMENT 

Risk assessments are able to address multiple failure modes. It is a diagnostic tool that

accounts for all components of uncertainty and the factors affecting the risk, be it technical,

human or otherwise. [4]. Vick (2002) explains the process of adverse events occurring as

having three parts: (1) an Initiator that begins it, (2) the Response of the structure to the

initiator, and (3) the consequences if inadequate response results in failure.

A risk assessment is primarily a scenario development tool that seeks to understand the risk

contribution from each possible scenario that leads to the hazardous outcome or event of

interest [5]. Once hazards have been identified it is essential to prioritise them so that action

can be taken and so that they can be dealt with in a suitable way [6]. Each of the identified

6

hazards must be examined to determine all the barriers that contain it or intervene to prevent

or minimize exposure to the hazard. The steps needed to maintain the integrity of the barrier

represents the challenges to barriers. The probability or frequency of exposure to the hazard

should also be identified for each scenario. Finally, the consequences of being exposed to the

hazard should be understood. The process can be formalized through the following steps [5]:

1. Identification of Hazards

2. Identification of Barriers

3. Identification of Challenges to Barriers

4. Estimation of Hazard Exposure

5. Consequences evaluation

Risk assessments are continuous and should not be regarded as a one-off exercise. There are

three types of risk assessment that all form part of a safety management system [4]:

• Baseline risk assessment – which assesses where a company is in terms of risk,

identifying major risks and thereby establishing their priorities and a program for

future risk control.

• Issue based risk assessment – as circumstances and needs arise, separate risk

assessment studies need to be conducted. An additional risk assessment will need to

be carried out when, for instance, a new machine is installed, a system of work is

changed or operations alter, after an accident or ‘near-miss’ has occurred, as new

knowledge comes to light and information is received which may influence the level

of risk to employees.

• Continuous risk assessment – This is the most important form of risk assessment that

should take place continually, as integral part of day-to-day management. This

includes audits, general hazard awareness linked to a suggestion theme, pre-work

assessments using checklists.

There are several approaches that can be used for the measurement of risk. The Risk Matrix

type approach categorises the consequences of the hazard and their likelihood separately.

They are then combined in a matrix to represent priority, as shown below [6].

7

Table 2.1 Risk Matrix Example

Multiple Fatalities 1 2 3 4

Fatality 2 3 4 5

Reportable Accident 3 4 5 6

Con

sequ

ence

s

Loss Time Accident 4 5 6 7

Once a

month

Once a

year

Once every

10 years

Once in a

Lifetime

Likelihood

A risk matrix can be used to accurately identify key hazards by combing the likelihood of

occurrence and consequence rating of the hazard occurring.

2.3. ACCEPTABLE RISK 

The results of risk assessments can be used in a relative manner to methodically rank risk-

exposure levels. De facto levels of socially tolerated (acceptable) levels of risk exposure can

define acceptable risk thresholds. For example, the risk of death from Car accidents is 1 in

5300. There are similar risks related to other major causes of death from cardiovascular

disease through to homicide, which are tolerated by society [5]. The level of risk that is

tolerated depends greatly on the values, beliefs and attitudes of society, thus varying from

community to community [3].

Although regulators often strive to assess absolute levels of risk, the relative ranking of risks

is a better risk management strategy for allocating resources towards regulatory control.

Ensuring system risks are below regulatory safety targets is often an important criterion in the

decision-making process. A risk may be tolerable if the benefits appear to exceed the risk [3].

Cost-benefit analysis is often required as an adjunct to formulating risk-control strategies to

socially acceptable levels [5]. Cost-benefit analysis is effectively a measure of the

willingness to live with a risk in order to secure the benefits, and in the confidence that the

risk is being properly controlled [3].

8

Another form of risk ranking is to use odds or the probability of hazard exposure per unit of

time. Another more objective method of risk comparison examines the duration of the

exposure and is used for comparison purposes using consistent units such as dollars lost per

year. The societal benefits and the cost trade-offs for risk reduction are widely used guides to

set and justify risk acceptability limits. By comparing the risks and benefits associated with

certain activities, fair, balanced and consistent limits for risk acceptability can be set and

institutional controls on risk can be established [5].

2.4. FAULT/EVENT TREE ANALYSIS 

Fault Tree analysis is a systematic, deductive technique which allows the development of

causal relations leading to a given undesired event, called the Top Event [7]. It accounts for

the interaction of many events to produce other events. Simple logical relationships such as

intersection and union are used to methodically build a logical structure, which represents the

system.

Event trees follow a similar method to that of Fault Tree Analysis. They use logic methods

for identifying the various accident sequences which can generate from a single initiating

event. An event tree begins with a defined accident-initiating event. It follows that there is

one tree for each different accident-initiating event considered. Once an initiating event is

defined, all the safety functions that are required to mitigate the accident must be defined and

organised according to their time of intervention [8]. In the case of the NBN, the seven failure

modes identified before are the initiating events.

9

3. THEORY This section discusses the main underlying hazards that could lead to the seven failure modes

of Construction, Operation, Demand, Network, Technology, Finance and Regulation. A brief

background of Australia’s current broadband situation is also provided to help understand

some of the reasons for undertaking the NBN and the effect it will have on Australia.

3.1. BACKGROUND 

The NBN will be a wholesale only, open access network. The Government has established a

new company, NBN Co. Ltd, to design, build and operate the new NBN. Australia’s current

aging broadband network has prompted the government initiative to maintain Australia’s

strong economic growth and to gain various broadband and online benefits that are discussed

below.

3.1.1.  Australia’s Current Broadband Situation 

The NBN project was commissioned to address Australia’s aging broadband infrastructure.

The NBN seeks to provide Australians with high speed broadband at reasonable prices. In

2009, Australia’s broadband was ranked the fifth most expensive out of the 30 OECD

Countries, as shown in Figure 3.1 below.

10

Figure 3.1 Average monthly subscription price for broadband, 2009 [9]

The speed of Australia’s broadband is falling behind technology leaders like Japan, Korea,

Germany and the USA as shown in Figure 3.2. Australia’s fastest advertised broadband

speeds in 2009 were 30Mbps. This may have increased since to speeds around 50Mbps, but

the relative position of Australia’s broadband situation still remains the same.

Figure 3.2 Fastest residential broadband download speed advertised, 2009 [9]

55.64 

10 

20 

30 

40 

50 

60 

70 

80 

90 

100 USD

 PPP

 per m

onth  

30000

 10 000  20 000  30 000  40 000  50 000  60 000  70 000  80 000  90 000  100 000  110 000 

Kbps 

11

Figure 3.3 Percentage of fibre connections in total broadband subscriptions, 2009 [9]

In terms of technology, fibre is yet to be offered to Australian residential broadband users. A

number of other OECD countries already have a significant penetration of fibre connections

into their broadband market, as shown in Figure 3.3 above.

3.1.2.  Importance of Broadband 

One of the main reasons stipulated by the Australian government for the construction of the

NBN project is the positive impact that ICT investment and broadband has on the economy.

Broadband has the ability to accelerate and enhance economic growth, improve social and

cultural developments and facilitate innovation. Widespread and affordable broadband access

can contribute to productivity and growth through applications that promote efficiency,

network effects and positive externalities, with benefits for business, the public sector and

consumers. As shown in Figure 3.4 below, Australia shows the highest correlation between

ICT investment and GDP growth amongst OECD nations.

0%  10%  20%  30%  40%  50%  60% 

Australia Ireland 

Switzerland Italy 

Netherlands Iceland 

Czech Republic Hungary 

United States OECD 

Norway Denmark 

Slovak Republic Sweden Korea Japan 

12

Figure 3.4 Contributions of ICT investment to GDP growth [10]

The private sector benefits from broadband in the form of e-business and new market

opportunities, allowing small and medium sized enterprises to realise growth through

productivity increases [11]. Broadband enables the emergence of new business models, new

processes, new inventions, new and improved goods and services. It increases competition in

markets and flexibility in the economy, for example by the increased diffusion of information

at lower cost, by improving access to increasingly larger markers, by allowing people to work

from multiple locations with flexible hours and by generally speeding up procedures and

processes [10]. The public sector such as health, education and government services, also

benefit from the productive efficiencies that broadband has to offer. Broadband can enhance

quality of life for residential consumers through economic, social and cultural development.

Broadband access allows rural and remote communities to experience economic and social

inclusion. It can facilitate access to new and advanced goods and services, as well as

opportunities to participate in the digital economy and information society [11]. There is also

believed to be a correlation between broadband penetration and GDP Capita as shown in

Figure 3.5 below. If this correlation is correct, then the introduction of high speed broadband

through the NBN project will hopefully lead to an increase in broadband penetration, which

in turn may lead to higher GDP per Capita and better standards of living.

0.0

0.1

0.2

0.3

0.4

0.5

0.6

0.7

0.8

0.9

1.0 Percen

tage 

1990‐95 

1995‐2003 (1) 

13

Figure 3.5 OECD correlation between broadband penetration and GDP per capita [10]

Another reason for the NBN is the health care benefits it will provide. People living in rural

and remote areas will have improved access to specialist doctors without having to travel

long distances. All Australians will benefit from better-informed diagnosis, targeted treatment

and patient management enabled by online collaboration between health professionals and

the instant transmission of diagnostic images, such as x-rays.

20,000 

40,000 

60,000 

80,000 

100,000 

120,000 

10 

15 

20 

25 

30 

35 

40 

GDP pe

r Capita 

Broadb

and pe

netraX

on percentage 

Broadband penetraXon (%) 

GDP per capita (USD PPP) 

14

15

3.2.  CONSTRUCTION HAZARDS 

The NBN project is being built over a 9-year period, starting with fibre rollout to 100,000

premises in Tasmania. There are a number of hazards, which will become evident during the

design and construction phase of the project. For example, a shortage of materials and

hardware such as OLTs (Optical Line Terminals), ONTs (Optical Networking Terminals) and

fibre optic cable may affect the project at some stage in the construction lifespan. There may

also be operational security issues determined by the amount of fibre placed along power

lines (aerial), therefore making the cable more accessible than ducted or buried fibre. The

enormous scale of the NBN provides the hazard of third party integration, where the various

contractors building the network run the risk of using different standards for construction and

operation. NBN Co’s coordination of contractors during the construction phase will be of

utmost importance. The hazards of labour shortage, scope creep and latent grounds are

determined to present the highest likelihood of occurrence and are discussed in more detail

below.

3.2.1.  Labour Shortage 

The NBN project will require a peak labour force of around 18 000 during years 4 to 7 of

construction [12]. This is based on 15% of the project being completed per year during this

period and will therefore require the peak number of personnel. This labour force will be

required in addition to the existing labour force employed in the Information and

Communication Technology sector. Strong growth in the Australian economy has led to a

dramatic drop in unemployment rates over the last decade. This decline in unemployment

rates has seen the pool of surplus labour disappear [13]. There are a number of factors that

could influence the shortage of skills such as:

• Growth of new industries with few ready-skilled trades people available

• Lack of interest in particular industries among job seekers

• Technology changes within an industry, especially production, resulting in new methods

and therefore new skills needs which are not being successfully incorporated in existing

training

• Growth in demand for new skills or work practices, associated with the pressure of

globalisation, international competition and structural change

16

There is a risk of a shortage of labour supply for the NBN project. Utilising Australian

Bureau of Statistics (ABS) data on ICT labour supply [14], a trended growth was forecasted

in Microsoft excel to predict the Business As Usual (BAU) labour force supply for future

years of the NBN project. The NBN’s labour requirement was then added to this to establish

the possible resource gap in the labour market. The findings are displayed in Appendix A and

graphically represented in Figure 3.6 below.

Figure 3.6 Forecasted BAU ICT Labour vs. NBN Demand for Labour

If current ICT labour force levels continue to decline there will be a peak resource gap of

approximately 18 027. The risk of a skills shortage for the construction of the NBN should

not be dismissed, as the resource gap may be formidable. The focus on the initial construction

of the rural backbone (see 3.8 Regulatory Hazard) also provides the hazard of a wage

blowout due to the shortage of skilled workers in rural areas [15]. However, there is scope to

redirect labour from other construction-based sectors to the NBN project when the skill sets

are similar, such as piping and tunnel engineering. The resource gap could also be filled with

professionals from overseas during periods when there is a spike in local demand in Australia

for ICT skills.

 ‐  

 5,000  

 10,000  

 15,000  

 20,000  

 25,000  

 30,000  

 35,000  

 40,000  

1996  1998  2000  2002  2004  2006  2008  2010  2012  2014  2016  2018  2020 

Resources (FTEs) 

Year 

Resource Gap 

Historical/Current workforce (Retained) NBN Plus Forecast BAU Reuirements Forecast BAU Requirement 

17

3.2.2.  Scope Creep 

Every project should have a set of deliverables, an assigned budget and an expected closure

time. These constitute the scope of the project. Any variation in the scope of a project can

affect the schedule, budget and in turn, the ultimate success of the project. If requirements

originally excluded are later included and constitute a variation, the project scope will extend.

The NBN’s project scope is set to deliver fibre to 90% of Australian premises at a cost of $43

billion over a 9-year project rollout. Scope creep can occur when this line is moved, usually

outwards, to extend current features or include additional features.

Scope creep can be classified as Technical or Business scope creep [16]. The technical scope

creep can show up when the project team wants to please the customer and is not able to

reject the customer's request for a change in the requirements during project execution. Gold

plating is another reason, which can cause technical scope creep. In this case, the project team

or design team adds additional features and functionality that are not part of original

requirements in order to please the customer. The NBN project has already seen a form of

technical scope creep in the form of fibre being extended from 90% to 93% coverage of

Australian premises. This scope creep came as a result of the implementation study

conducted by McKinsey & Company and KPMG which suggested an extension of coverage

to 93% of Australian premises [17]. However, the additional coverage still remains within the

existing budgetary constraints.

Business scope creep occurs due to external forces that may be beyond the control of a

project manager. An example might be the continual changes in market trends, which makes

previously defined requirements now obsolete. The NBN may be prone to business scope

creep in the form of wireless being opted for instead of fibre for the “last mile” connection. In

this case, the market demand for wireless mobility may lead to a change in design to discard

FTTP (Fibre to the premises) and instead implement a FTTN (Fibre to the Node) network

with wireless communications used for the last mile connection (see section 3.6.1 Wireless

Technologies).

18

One can avoid scope creep by managing the scope of the project effectively. There are a

number of ways to control or avoid scope creep [16]:

• Involve the customer and/or the end users early in the project.

• Thoroughly analyse and gather requirements during the initial stages of the project.

• Introduce a Change Control Board (CCB) team that would evaluate the risk of

implementing the changes.

• Make sure to involve critical stakeholders throughout the project phases (especially

during the planning phase).

• Avoid gold-plating and gain the ability to refuse changes in requirements with proper

reasons and support.

• In extreme cases, stop the project so that new additional requirements can be properly

scoped and integrated rather than tacked on.

The NBN project evidently follows and breaks a number of the above rules for controlling

and/or avoiding scope creep. Firstly, the lack of a preliminary cost benefit analysis started the

project on unsteady grounds, as the exact benefits from such a large infrastructure investment

have not been clearly articulated. Since then, an implementation study conducted by KPMG

& McKinsey has made suggestions to alter certain aspects, although most of these do not

affect the construction of the project. There has also been discussion and suggestions by a

group of telco chiefs, namely the Alliance for Affordable Broadband (AAB), that the NBN

plan should be amended to a FTTN network with 4G wireless technology used for the last

mile connection. A form of “gold plating” scope creep could occur if wireless last mile

connections were provided, in addition to FTTP.

Scope creep can lead to projects exceeding budgets and/or taking longer to complete. The

NBN project has already undergone minor changes to design, such as the extent of fibre

coverage and the planned release sites, but this has not led to any increase in costs or change

on the project completion date. The lack of a cost-benefit analysis may result in a number of

changes to the NBN as certain aspects of the fibre network may be found to be more essential

to certain parts of the Australia than others. For example, since the recent 2010 Federal

elections there has been an amendment to the priority release sites to gain access to the fibre

network in addition to hospitals, schools and rural areas priority release sites (see section 3.8

Regulatory Hazard).

19

3.2.3. Latent Grounds  

Latent grounds refer to unforseen circumstances that may alter or affect the construction and

progress of the NBN project. The lack of an in depth preliminary study is often a precursor to

the delay of works and exceeding budgets due to latent grounds. One of the major causes for

concern for the NBN project in terms of latent grounds is the amount of hard rock that will be

encountered during tunnelling operations. The amount of hard rock has an affect both on the

time and cost that it takes to tunnel through as opposed to soil. The geological consistency of

the land over the entire NBN network is difficult to predict and uncertainty exists as to the

delays that may be caused by rocky outcrops. Table 3.1 below shows approximate

construction costs associated with the NBN project [12].

Table 3.1 NBN Estimated Construction Costs [12]

Total Capex excl. GST (Millions)

Construction - Underground $11,800

Construction - Aerial $1,500

Construction Rural Plough $370

Splicing $6,800

Technicians $130

Splicing, Fibre Termination, Testing $6,900

Pole Make Ready Works $1,000

Designers $730

Data-entry $130

Material - Fibre $1,000

Total $30,360

20

The underground construction represents the greatest cost in the construction phase, totalling

$11.8 billion. This figure is based on 50% of fibre requiring underground construction such

as ducts and pits to house the cable. This means that the total construction costs are highly

sensitive to any fluctuations caused by delays in tunnelling and underground construction.

The risk of latent grounds is considerable due to the large cost placed on underground

construction. However, the percentage of aerial works, which is the amount of fibre placed

along power and telephone lines, has the opportunity to decrease construction costs and the

time delay compared to underground construction. The greater the percentage of fibre aerial

works, the less risk there is from latent grounds due to underground construction. There is

however an increase in risk for Operational hazards, as aerial works allows easier access to

the fibre cable and therefore increased security hazards. This does not go without saying that

aerial works doesn’t carry its own inherent risk and can be affected by latent grounds too, but

the sensitivity of overall costs to a slight change in construction costs means that there is less

cause for concern with a greater percentage of aerial works.

21

3.3. OPERATIONAL HAZARDS 

Operational risk is commonly associated with unexpected problems in staff management,

maintenance and other elements of operating the infrastructure and is usually present from

the commencement of operations [2]. Operational risk could arise if the planned level of

service availability from the NBN network does not eventuate. One of the main reasons for

the construction of the NBN project is to provide economic benefit to Australia through

productivity enhancements [18]. There is a risk that large-scale power, network and hardware

outages could cause a major loss in productivity for businesses dependent on ICT services.

Such hazards can be addressed through the introduction of design redundancies, which

takeover operation from failed nodes in the network. There are also operational hazards when

the network is fully functioning. Security of the content transferred over the NBN also

threatens to affect the productivity benefits that the network could offer to the economy.

3.3.1. Contention ratio 

The contention ratio is the ratio of the potential maximum demand to the actual bandwidth.

The higher the contention ratio, the lower the effective bandwidth as a large number of users

may place demand on the bandwidth at the same time, especially during peak usage times

[19]. Generally, ISP’s offer business broadband services with a contention ratio of 20:1,

while some residential ratios can be as high as 150:1. A ratio of 20:1 means that the

broadband users share their broadband speed, of say 20Mbps, with 20 other premises. If each

user was accessing their connections equally at the same time then they could expect speeds

of around 1Mbps. In the case of the NBN, a contention ratio of 32:1 can be expected [20]. It

is for this reason that we can expect that constant actual download speeds of 100Mbps for the

NBN will not materialise as the 100Mbps bandwidth will be shared amongst the various users

accessing the same exchange point. Even if 100Mbps was possible for all users on the same

exchange point, then the actual network and fibre backbone would struggle to cope with the

broadband demand. The 20 users accessing 100Mbps would have a total download

bandwidth of 2Gbps. If this scenario was to eventuate over a number of exchange points

simultaneously, then there would be a network overload and the speed would have to slow

down at some point. This clearly illustrates that a hazard exists that the 100Mbps of the NBN

will not eventuate. This will depend on the final decisions in design of the network to

accommodate design redundancies in order to cope with peak network demands.

22

3.3.2. Maintenance and Equipment (Fibre) Failure 

The estimation of the life span of a project is essential for economic practices to determine

whether a project is economically viable. A capital-intensive project like the NBN will

require sufficient operating lifespan in order to financially recover the capital investment in

the project. Lower than expected equipment life and the resulting diminished operational

lifespan is a hazard to the NBN project.

The NBN project places utmost importance on the use of fibre optic cable to provide FTTP

connections to over 90% of Australian premises. There is concern that the lifespan of the

fibre optic cable may be lower than expected. The varying environmental conditions from the

fibre cable either being placed in ducts or along power lines will impact the life span of the

fibre cable. Manufacturers calculate an expected life of around 60 years for fibre optic cables

[21]. The calculation takes into consideration fatigue and stress corrosion susceptibility,

which accounts for environmental factors such as water, wind and heat. The 60 year

prediction can be applied to a relatively stable environment such as an underground duct.

Australia’s temperate climate favours underground fibre cable. Cable exposed to water and

extreme cold temperatures can lead to ice formation and stress cracking of the fibre cables.

The harsh Australian sun can be detrimental to aerial fibre optic cables placed along power

lines and exposed to the elements. Modern fibre cables utilise UV protective shielding that

protects the cable. Aerial fibre cables will also be susceptible to increased mechanical

stressing from winds. As a result, a 25% decrease in lifespan to approximately 45 years is

predicted for aerial fibre cables due to environmental stresses. This figure is backed up by the

KPMG McKinsey Implementation study, which confirms 40 years or more lifespan for fibre

cabling [17].

As is the case with any infrastructure, adequate maintenance of the NBN will be essential.

The breakdown of equipment is an expected occurrence but the success of the operation of

the network will be dependent on the ability to control breaks in transmission. Australia

already has in place a successful “Dial Before You Dig” referral service for information on

underground pipes and cables. This campaign reduces the likelihood of fibre cable being

damaged by digging.

23

Maintenance and equipment failure is always a considerable concern for infrastructure

projects like the NBN. The inert nature of fibre compared to copper cabling, which is prone

to corrosion and fibre’s relatively long lifespan presents less of a maintenance hazard than a

copper network. The NBN will require maintenance as is the case with any project but these

costs should be relative to the size of the network.

3.3.3. Security – Cyber Crime, Spam and Intellectual Property 

As is the case with any infrastructure project, the safety and security of customers using the

end product is of utmost importance. If an asset is deemed to be unsafe or insecure for

customers to use then it is deemed a failure in providing a service to the customer. The NBN

is unlikely to present any physical safety concerns to the average user, however users will be

susceptible to online security attacks in one way or another. A recent survey of Internet and

email users indicates the current scale of security threats present.

• The number of people who received phishing attacks doubled between 2004 and 2006,

from 57 million to 109 million [22].

• It is estimated that between 50% and 65% of all e-mail is spam. While some 80% of

organizations have some form of anti-spam technology in place, even protected

employees will spend as much as 80 minutes per 1,000 e-mails (about 2.4 work days a

year) dealing with spam [23].

Strategies to prevent spam are proving costly, because of the need to involve governments

and ISPs as no standard approach exists [24]. While spam poses a serious threat to offsetting

some of the productivity benefits that the NBN will provide, there are also concerns about

malicious viruses and spyware that affect computer performance and can lead to identity

theft. If online security threats are not sufficiently addressed, then the inherent benefits

provided by the NBN could be diminished. Some of the benefits such as remote access for

daily tasks, like Internet banking, could be discarded as an option for some users. The

monetary losses for victim from credit card and identity fraud have more than quadrupled

since 2005. A survey found that 23 percent of online banking consumers have reverted back

to offline methods because of security concerns [22].

24

As the Internet is a global access platform, governments need to collaborate in order to

control cybercrime through consistent policy making. This will prevent online criminals from

hiding behind a wall of bureaucracy in a country which may have Internet laws that

essentially protect criminals and assist criminal activities. In order to press down on

cybercrime, police will need to have real-time access to network traffic, and new powers to

rapidly secure evidence held on computer systems. [25] Australia has signed up to a global

treaty aimed at fighting fraud and other offences committed using the internet such as

computer hacking, child pornography and copyright infringement [25]. The convention,

which provides a standard framework for investigating and prosecuting crimes involving the

internet across national borders, has been adopted by more than 45 countries, including the

US, Canada and Japan, since it began in 2004. This is a step in the right direction for securing

NBN customers from malicious cyber attacks.

The security hazard from cybercrime, spam and intellectual property is present on current

broadband networks. There is no indication that a high-speed broadband network will

facilitate these criminal activities further, but there is cause for concern over the reduction in

economic productivity due to this security hazard.

25

3.4. DEMAND HAZARDS 

The demand hazards facing the NBN arise because the demand for the NBN services might

not meet expectations. This risk is present throughout the life of the project, both during

construction and operation. An unanticipated decline in customer demand for the NBN

services would lead to a reduction in the value of the infrastructure as an asset. A sufficient

level of demand will be required in order to provide high speed broadband services and to

generate sufficient revenue to cover construction and operation costs of the project. Similarly,

if there is excessive demand, it may result in network congestion and users failing to achieve

data rates of 100Mbps.

3.4.1. Decreased Demand 

The economics of supply and demand lead to price setting in accordance with the supply

available and the demand for the product or service. The NBN Co. will be supplying a service

to customers across Australia, offering high speed broadband. The large cost for the

construction of the fibre infrastructure should ideally be recovered through the wholesale

rates offered by the NBN Co. Early predictions indicated that the top-tier 100Mbps

broadband service would be priced around $200 a month in order to cover the costs and

required rates of return for the project [26]. This rate has since been revised down to around

$130 per month as offered by iiNet and iPrimus. However, this price is still more than double

the current cost of the average broadband plan with similar download quota. The high prices

for fibre broadband could act as a price floor and effect demand, as shown in Figure 3.7. A

price floor results in a surplus or excess supply as consumers either cut back their demand or

drop out of the market entirely and suppliers increase production due to the increase in price

equilibrium.

26

Figure 3.7 Price Floor’s Surplus Effect

The NBN’s supply of high speed broadband at a fixed price F = $130, could result in a supply

surplus as less customers are able to afford the price. However, when the fibre subscription

rates are compared with countries with similar geographic conditions and population density

such as the USA, the proposed fibre prices appear acceptable (Figure 3.8 below).

Figure 3.8 Average monthly subscription price for very high-speed connections

(Greater than 35Mbps advertised) [9]

139.95 152.68 

20 

40 

60 

80 

100 

120 

140 

160 

180 

USD

 per m

onth  

27

Prices for very high-speed broadband services in other parts of the world indicate a maximum

of $150 USD in Norway. Again, the more densely populated countries such as Korea,

Sweden and Japan fall privy to lower broadband prices, as their costs for infrastructure over a

smaller area are lower. The more comparable USA advertises near NBN broadband speeds at

approximately $170 AUD. Recent data collected by the OECD indicate that average

broadband subscription rates were around $60 AUD in Australia in 2009, shown in Figure 3.9

below.

Figure 3.9 Average monthly subscription price for medium-speed connections

(2.5Mbps to 10Mbps advertised) [9]

Australia’s broadband subscription rates are already among the highest in the OECD group of

countries. This has mainly been accredited to geographic reasons, as Australia is a large and

sparsely populated country, with cities established along the coast. The large distances

between cities presents a high fixed cost for building telecommunication infrastructure.

However, countries like the USA share a similar problem of having a vast geographic area to

connect, but they are still able to achieve reasonable broadband prices, which are on average

approximately $17 USD lower than Australia. This falls back to one of the main objectives of

the NBN project to deliver “affordable” high speed broadband to 90% of Australians.

38.66 

55.64 

10 

20 

30 

40 

50 

60 

70 

80 

90 

100 

USD

 PPP

 per m

onth  

28

Figure 3.10 Range of broadband prices per Mbps by country [10]

Figure 3.10 indicates that Australia has the highest priced subscription rates per Mbps out of

the OECD countries. This is due to the lack of competition in the Australian broadband

market and Telstra’s control of major ICT infrastructure. Wholesalers who follow a Bertrand

competition strategy compete on price and are able to reduce competition in the downstream

retail market but increasing their wholesale fee [27]. This is evident in the Australian market,

whereby the high wholesale fee is passed on to the consumer. The high price in Figure 3.10

may also account for the expensive satellite connections, which are used to connect remote

areas of Australia.

18.46 4.95

3.85 3.56

3.22 3.16

2.82 2.65

2.44 2.27 2.10

1.92 1.74 1.72

1.58 1.51 1.44 1.42

1.16 1.15 1.11

1.03 1.02

0.95 0.92

0.41 0.35 0.34

0.25

Mexico Turkey

Canada Poland

Hungary Belgium

Czech Republic United States

Slovak Republic Portugal Norway

Austria Spain Switzerland

Ireland Luxembourg Germany Italy

United Kingdom Netherlands Iceland

Greece Denmark

New Zealand Australia

Finland Sweden Korea

France Japan

115.01 41.42

110.51 73.83

46.31 22.07 15.60 26.66

54.18 13.35

20.99 22.73

43.27 74.60

22.28 16.51 19.17 22.24

13.16 45.20

37.29 46.70

26.07 86.02

160.96 68.76

98.80 4.48

27.91 86.00

0.10 1.00 10.00 100.00 1000.00

Mexico Turkey

Canada Poland

Hungary Belgium

Czech Republic United States

Slovak Republic Portugal Norway Austria Spain

Switzerland Ireland

Luxembourg Germany

Italy United Kingdom

Netherlands Iceland Greece

Denmark New Zealand

Australia Finland

Sweden Korea

France Japan

USD PPP

29

Recently released pricing by iiNet and iPrimus (Table 3.2) show a slightly improved pricing

structure for fibre access to the NBN since the initial $200/month estimate.

Table 3.2 ISP’s Fibre Prices

Cost (Peak/Off-peak quota) Plans Down/Up speed iPrimus iiNet

Fibre 1 25 / 2 Mbps $49.95 (5/10GB) $49.95 (5/5GB)

Fibre 2 25 / 2 Mbps $59.95 (20/20GB) $59.95 (10/10GB) Fibre 3 25 / 2 Mbps $119.95 (80/220GB) $69.95 (30/30GB)

Fibre 4 50 / 4 Mbps $79.95 (20/20GB) $89.95 (30/30GB) Fibre 5 50 / 4 Mbps $99.95 (65/65GB) $99.95 (50/50GB)

Fibre 6 100 / 8 Mbps $109.95 (65/65GB) $129.95 (60/60GB)

Fibre 7 100 / 8 Mbps $139.95 (80GB/220GB) $159.95 (90/90GB)

However pricing still remains at more than double the price of the equivalent ADSL2+

speeds with similar download quota. In comparison, iiNet also offer broadband ADSL2+

speeds (24Mbps) with 50GB/50GB peak and off-peak download quota for $59.95 per month.

The equivalent fibre 5 plan, with slightly higher download speeds, is priced at $100, which is

$40 (40%) more. Lack of demand for NBN high-speed broadband services will be

predominately result from elevated prices. The indicative price of around $200 a month may

not be too far off international standards for similar broadband and factoring in Australia’s

geographic predicament. However, it is unlikely that the average subscriber will initially

switch to a subscription plan that is more than double the current rate. The adoption of

innovations can be explained by the Diffusion of Innovations Theory, which categorises

customers into different rates of adoption (see Figure 3.11 on following page)

30

Figure 3.11 Diffusion of Innovations

This rate of adoption may explain the statement by NBN Co. Chief Mike Quigley, that the

NBN project will only see returns in 20 years [28]. As consumer confidence grows through

positive feedback from early adopters, more and more consumers will adopt high-speed

broadband and the price will come down as a result. However, this process may take up to 20

years before the majority of potential customers realise the benefits of high-speed broadband.

Greater household penetration of NBN broadband services would be better achieved by

setting reasonable prices that encourage initial take-up by customers. The McKinsey

implementation study estimates that 75 - 90% of premises within the fibre network will be

activated by 2035 as shown in Figure 3.21 below. The blue region in Figure 3.21, shows the

estimated number of premises with fibre activated over time, corresponds closely to the shape

of the innovation adoption curve.

31

Figure 3.21 Aggregate fibre take-up scenarios [17]

The broad region of premises activated with fibre by 2035 represents between 10 and 12.5

million premises, which would constitute a large variance in operating revenue. The risk of a

lower take-up of fibre by premises translates not only into lower operating revenue but also

lower returns for investors and relates back to the financial hazards discussed in section 3.7

Financial Hazards.

The risk of the decrease in demand has up until now focused on high prices discouraging

customers from switching to the NBN. However, the probability of a lack of demand based

on the need for such high broadband speeds in place of current ADSL2+ services should also

be acknowledged. Although evidence in section 3.4.2 covering Increased Demand shows that

there is a growing trend towards increased IP traffic, in the short term the NBN’s high speed

broadband services could be deemed an unnecessary upgrade for the average customer.

Demand for high-speed broadband will also be driven by applications and digital content that

require high data rates [29]. Such applications will likely emerge during the latter years of the

9 year NBN rollout.

32

3.4.2. Increased Demand 

The NBN project faces the risk of greater than expected demand for high-speed broadband

services. Factors such as increases in fuel and travel costs means more people are looking

towards alternatives such as video conferencing and online shopping. An ever-increasing

population also increases the total demand for broadband services. Increased demand for the

NBN could lead to poor service levels and congested fibre networks as the networks were

designed for fewer users. This presents less of a risk to the overall NBN project, than below

expected demand, as the increased demand would fund infrastructure upgrades. NBN Co.

have also released, after testing in first release sites in Tasmania, that the network will be able

to provide users with data rates up to 1Gbps [30]. However, the longevity of the project

would be in question if the design did not account for adequate expansion of the network

required by exceeding the expected number of users and an increase in data rate

requirements.

The growth of electronic file sizes and digital applications that require greater bandwidths has

steadily increased over the past two decades. There is an exponentially growing trend in

global IP traffic as indicated by Figure 3.12 below.

Figure 3.12 Cisco’s Forecasted Global IP Traffic Growth Rate [31]

10000 

20000 

30000 

40000 

50000 

60000 

1990  1995  2000  2005  2010  2015 

Petra By

tes (PB) 

Year 

33

If predictions by Cisco materialise, Global IP traffic will double from 21 000 PB (Petabytes)

in 2010 to 42 000 PB by the end of 2012. The growth in traffic is largely attributable to

emergence of online high definition video viewing such as IPTV, video on demand and

YouTube which are expected to account for 90% of IP traffic in 2014 [31]. As demand for

applications and uses such as video streaming, multi-channel tv, 3d tv etc grow, so will the

demand for high speed broadband as shown in Figure 3.13 below.

Figure 3.13 Access speeds required by applications [32]

The NBN Co. has recognised the growing demand for higher speed broadband by extending

the NBN service levels to speeds of up to 1Gbps. This is a reaction to the realisation that by

the end of the rollout of the fibre network, speeds of 1Gbps will be standard globally.

34

Figure 3.14 Fixed Bandwidth Demand [33]

Figure 3.14 shows the predicated growth of speeds to 1Gbps by 2020. The increase in global

IP traffic driven by video is stimulating demand for higher speed broadband services. As

more and more Australian ISPs provide IPTV services, demand for improved broadband

services will grow. There is also the scenario of supply creating demand as the provision of a

1Gbps fibre network would provide incentives for application developers to utilise the excess

bandwidth. Figure 3.15 below shows the key drivers of users’ broadband experience.

Figure 3.15 The three stages of broadband user experience [32]

The provision of broadband results in creativity for application development and emergence

of new digital content. The speed of access determined by broadband speed enhances the

broadband experience as internet browsing and online interaction is more enjoyable [32].

35

Application development and online video will increase the demand for high-speed

broadband. The forecasted growth in global IP traffic shows an exponential trend, which

could see the demand for high-speed broadband far exceeding original expectations. The

NBN could face the hazard of an above-expected demand for take-up of lead-ins. If the

network is not designed with excess capacity or the ability to accommodate extra users, then

the network could suffer serious congestion and data rates will fall well below the advertised

100Mbps. However, the choice of fibre optic cabling has the potential to be upgraded over

time as the demand for high-speed broadband grows and exchange technology progresses to

allow for faster speeds.

36

37

3.5. NETWORK HAZARD 

The network hazard arises as the use of the NBN infrastructure depends on decisions made in

relation to other elements of the network. This risk is present throughout the life of the

project. For instance, the NBN may be subject to a relative shift in demand for other

broadband services such as wireless (see section 3.4 Demand Hazards). Other hazards such as

poor service levels provided by ISPs, poor integration between the fibre and wireless/satellite

network and the risk of Telstra operating their own last mile fibre connection also add to the

overall Network failure mode. In addition, the NBN’s 100Mbps speeds are dependent on all

connection links, both domestically and internationally. This leaves the network susceptible

to overseas bottlenecks where information offshore is accessed via communication cables

that cannot provide NBN speeds.

3.5.1. Design Bottlenecks 

Currently 80% of Australia’s international Internet traffic is to the US. Considering current

trends, this looks unlikely to change in the short to medium term [34]. Email accounts for

about 10% of Internet traffic, with the majority of traffic (approximately 80%) from file

transfer and web browsing/downloads. This further indicates the level of Internet traffic that

would leave Australia’s local high-speed fibre optic network and that would require access to

servers abroad. There is evidence supporting the concern that the 100mbps speeds supported

within Australia would be dramatically reduced to a few Mbps when accessing overseas

servers.

Tests conducted on overseas networks in the USA, privy to high-speed broadband

connections (100Mbps maximum speeds), show the extent of the bottleneck situation

between the USA and Australia. The test indicated that a maximum speed of only 4.06Mbps

was attainable when connected to a server in Melbourne [35]. This highlights the effect of the

bottleneck caused by only a handful of submarine fibre cables connecting Australia. Table

3.3 on the following page highlights this lack of international connectivity.

38

Table 3.3 List of submarine fibre optic cables connecting Australia [36]

Submarine Cable Name Submarine Cable Connections

AIS Australia-Indonesia-Singapore

AJC Australia-Japan Cable

ANZCAN Australia, New Zealand, Canada

APCN (Asia-Pacific Cable Network) Japan, Korea, Philippines, Taiwan, Hong Kong, Malaysia, Singapore, Thailand, Indonesia, Australia

APNG Australia-Papua New Guinea

APNG-2 Australia-Papua New Guinea

Gondwana-1 New Caledonia, Australia

JASURAUS Jakarta - Surabaya - Australia

PacRimWest Australia-Guam

PPC-1 (Pipe Pacific Cable) Australia, Papua New Guinea, Guam

SX (Southern Cross) Australia, New Zealand, United States

TASMAN 2 Australia-New Zealand

Telstra Endeavour Australia-Hawaii-United States

The shortage of external connections presents a digital divide between Australia and the rest

of the world. Currently, the only direct submarine connections to the USA are the Southern

Cross Cable and the Telstra Endeavour. Other connections such as the PacRimWest and PPC-

1 cables can connect with the USA through the Asia America Gateway [37], but are then

susceptible to increased data traffic from the Asia-Pacific region. Together these four cables

form the major transit routes carrying the majority of Australia’s internet traffic [38]. These

four main cables are highlighted in green and the Telstra Endeavour cable in red in Figure

3.16 on the following page.

39

Figu

re 3

.16

Aus

tral

ia’s

subm

arin

e ca

ble

conn

ectio

ns [1

]

40

There are plans under way by Pacific Fibre to build a new submarine fibre connection from

Sydney to Auckland to Los Angeles. The project is estimated to cost around $400 million and

the fibre will have 5 times the current capacity of the existing Southern Cross fibre

connection to the USA. The cable will provide up to 5.12 Terabits/s and will effectively

double the current capacity of Australia’s access to overseas servers [39].

Poor data overseas rates cannot be fully explained by the lack of fibre infrastructure. This is

also attributed to the long distance connection between Australia and the USA. The great

continental divide translates into a “round-trip delay” as data accessed in the USA has to be

transferred back across the pacific. The speed of light and delay caused by communications

equipment factors, such as signal boosters/repeaters, will not be overcome through an

increase in bandwidth. The lead to lag times in data access can be solved through data

architecture, rather than infrastructure [38]. The idea is to relocate static media, such as video,

locally within Australia. This would allow the full utilisation of the 100Mbps NBN speeds

and exclude slower international connections. As long as Australians have to regularly access

content from overseas, there will be a compromise to the maximum attainable data rates.

Network architecture needs to be addressed to solve the lag time experienced by overseas

connections.

41

3.6. TECHNOLOGICAL HAZARDS 

Technological hazard facing the NBN arise because the risk of the fibre, wireless and satellite

network infrastructure might become obsolete or stranded if users choose to switch to a new

form of broadband service delivery. This technological risk is present throughout the life of

the project. Hazards such as security risks also arise with the ability to tap fibre lines and

access users’ information. The greater the amount of aerial works, the higher this risk is as

aerial fibre cables are more accessible than fibre cable placed in ducts or buried. Due to the

fast and progressive nature of technology development, the NBN is susceptible to technology

improvements during the relatively long rollout over 9 years. Considering the Internet was

born as recently as 1982, less than3 decades ago, the NBN project, which will take nearly a

decade to complete, will be at risk of becoming outdated before it is fully operational. There

is the extended risk that the NBN will become outdated before the projected 15-year project

life is reached. Wireless technologies present the greatest risk of outdating the FTTP network

delivery, offering a more mobile and convenient last mile connection. The increasing demand

for mobile connectivity and improvements in wireless technology is discussed below.

3.6.1.  Wireless Technologies 

The advancement of wireless technologies over the past decade has led to a significant

increase in download speeds, making it possible to provide services such as high speed

internet access and to receive broadcast television programs [40]. The upcoming 4th

Generation (4G) wireless network was being contested by 3 main standards. These included

Ultra Mobile Broadband (UMB), Worldwide Interoperability Microwave Access (WiMAX

Mobile) and Long Term Evolution (LTE). However, development of UMB ceased in

November 2008 in favour of LTE. Plans for the introduction of LTE as a 4G network indicate

that it will complement current 3G and even 2G networks [41]. A related trend is the growth

in use of Wi-Fi (Wireless Fidelity) and WiMAX. Wi-Fi uses local wireless networks for

high-speed mobile access to the Internet. WiMAX has a broader range of distance compared

to Wi-Fi. WiMAX’s main application is to attempt to alleviate network congestion from

cellular providers in urban areas. Metro Wi-Fi systems are becoming increasingly popular in

handling data services in dense urban areas. 3G, and soon 4G LTE, could be described as

bringing Internet capabilities to wireless mobile phones; Wi-Fi as providing wireless Internet

42

access for laptop computers; and WiMAX as expanding networks with wireless links to fixed

locations. The technologies are seen by some as competing for customers, and by others as

complementary providing a broader base and greater choice of devices for wireless

communications and networking [41]. There is scope and cost saving benefits to use a

combination of these wireless technologies as a “last mile” connection in a FTTN network.

Table 3.4 below summarises the relative performances of competing and complementary

wireless standards that have emerged over the last two decades. Most importantly, it shows

the rapid progression of data rates since the inception of mobile communication technology.

Table 3.4 Advancements in mobile communication data rates [42], [43], [44], [45], [41]

Generation Mobile Technology Year Introduced

Downlink Peak Network Speed

1G NMT/AMPS (Analogue) 1982 1 kbps

GSM (CDMA/TDMA) 1992 13 kbps

GPRS 2000 80 kbps

CDMA2000 1x 2000 144 kbps 2G

EDGE 2001 236.8 kbps

UMTS 2002 384 kbps

EDGE Evolution 2005 1.9 Mbps

UMTS WCDMA 2005 2.048 Mbps

HSDPA 2006 14.4 Mbps

CDMA2000 EV-DO 2006 14.7 Mbps

HSPA+ 2008 42 Mbps

3G

LTE 2009 100 Mbps

802.16m WiMAX (2x2 MIMO) 2010 144 Mbps 4G

LTE Advanced (4x4 MIMO) 2011 326 Mbps

1 Note: The above download speeds only account for a single user and the speeds will decrease when multiple users connect to a cell.

43

Table 3.5 below is an adaptation of a Market needs analysis carried out in 2007 on 3G and

emerging wireless technologies. It has been updated to account for the emergence of 4G as a

replacement for 3G, and the use of fibre fixed lines in the NBN. It clearly indicates the

market’s demand for wireless. It is apparent that wireless technologies can coexist and

supplement the faster fixed line fibre optic broadband connections. However, as wireless

technology advances so will the data rates. Essentially, wireless and fixed fibre optic lines

will find themselves competing in the same market segment. In this case, wireless will

possess an obvious advantage over fixed lines due to the mobile nature of the connection. A

fixed fibre backbone will always be required to support wireless communications as current

4G has an absolute maximum range of 50km. The use of WiMAX and LTE is ideally suited

to the “last-mile” connection, supporting a FTTN network setup. At distances under 2km

there would be near identical data rates achieved by a FTTN network with 4G wireless last-

mile connections compared to a FTTP network.

Table 3.5 Wireless Technology Fit for Market Needs [41]

Segmentation

Variable Wireless Data Market

Needs Wireless Technology Fit

Fixed Broadband capability must compete against fibre options. Continuous coverage not required.

3G not intended to compete against fibre approaches. 4G will compete in this area, though mostly in regions where fibre is not available. Fibre networks are evolving toward 1Gbps, which make it difficult for wireless systems to compete directly.

Fixe

d ve

rsus

Mob

ile

Mobile Good throughput is necessary, but it does not have to meet fixed line performance. Continuous coverage in coverage areas. Nationwide service offerings.

3G is now available in most major markets, with fallback to 2.5G services in other areas.

44

Segmentation

Variable

Wireless Data Market

Needs Wireless Technology Fit

Enterprise Nationwide service offerings. Unlimited usage service plans. Choice in devices, including modem cards, smartphones, and data capable mobile phones.

3G, and eventually 4G, technologies provide coverage in top markets, with fallback to 2.5G for other areas. Mobile WiMAX will potentially offer service in densely populated areas. All technologies will likely have unlimited usage service plans. 3G/4G technologies will have the widest device selection and strongest economies of scale.

Ente

rpris

e ve

rsus

Con

sum

er

Consumer Wide range of feature phones with multimedia capabilities.

3G/4G technologies will have the greatest selection of multimedia feature phones.

Urban High capacity to serve large numbers of subscribers. Broadband speeds desirable.

3G, municipal Wi-Fi, and eventually 4G will all provide broadband services in urban areas.

Urb

an v

ersu

s Rur

al

Rural Good coverage in low-density areas achieved through large radius cells. High data throughputs are a lesser priority.

These areas are to be serviced by 4G technologies under the NBN plan.

Developed Value-added services such as broadband data and wireless e-mail. Mobile applications constantly emerging.

3G networks can provide broadband data. 4G networks will eventually be able to offer broadband services. 3G operators are likely to provide the greatest number of value-added services.

Dev

elop

ed v

ersu

s Em

ergi

ng

Mar

kets

Emerging Basic telephony services supporting high-density populations. Data is a lower priority.

UMTS, CDMA2000, and WiMAX can all provide basic telephony services with data options.

Laptop High data throughputs. .

4G can deliver high data throughputs and is available in PC Card and USB dongle formats.

Smartphone Medium data throughputs and wide coverage areas.

2.5/3G is the best choice because of data support and wide coverage areas.

App

licat

ion

Type

Feature phone

for multimedia

High data throughputs and wide coverage areas.

4G is the best choice because of data support and wide coverage areas.

45

It is estimated that the future cost per megabyte for 4G Wireless services will be 83% lower

than current radio technology W- CDMA and 66% lower than HSDPA [46]. This is crucial as

there is a projected six-fold increase in global IP traffic between 2007 and 2012 (driven

mainly by video) with mobile data projected to double every year from 2008 to 2013. Figure

3.17 below is a graphical representation of Table 3.4. It shows the exponential trend in the

advancements of mobile communication data rates over time. Current experimental data rates

for 4G wireless communications have reached speeds of 326Mbps in the downlink [41],

which comfortably surpasses the 100Mbps landmark speed the NBN is offering to home

users.

Figure 3.17 Advancements in mobile communication data rates (log graph)

However, recent testing of 4G compliant wireless technologies has revealed that although the

peak data rates may far exceed 100Mbps, as the number of users per cell is increased, the

achievable data rates drops dramatically as shown in Figure 3.18 below.

0.001 

0.01 

0.1 

10 

100 

1000 

1980  1985  1990  1995  2000  2005  2010  2015 

Peak Dow

nlink Speed  

(Log scale ‐ Mbp

s) 

46

Figure 3.18 4th Generation wireless speed tests for multiple users [33]

Any wireless network wireless network used to provide the last mile connection should be

designed so that anyone tower does not service too many users. This problem is synonymous

to fixed line contention ratios, which can reach upwards of 150:1 and result in a similar drop

off in data rates (refer to section 3.3.1 Contention ratio). There is a growing demand in

Australia for mobile communications, which is evidenced by the rise in the number of

wireless subscribers over the past few years. Recently collected data by the Australian Bureau

of Statistics (ABS) shows the number of wireless broadband subscribers has risen from

approximately 2% in 2006 to around 33% by the end of 2009 [47]. Whether the wireless

subscribers are using a wireless connection to complement or replace a fixed line connection

is difficult to distinguish as the overall number of broadband subscribers increases each year.

However, it could be reasonably assumed that there is an emerging trend of broadband users

switching from fixed line broadband to wireless as the demand for the convenience of mobile

Internet increases. The switchover from analogue to digital television signals will free up a

large portion of the RF spectrum for broadcasting. This presents even more of an opportunity

for wireless technologies to advance (see section 3.8 Regulatory Hazard). The Risk involved

with the emergence of superior wireless technologies and the demand for mobile Internet

means that a FTTP network would be deemed unnecessary, as fixed lines become redundant.

Table 3.6 below summarises the various advantages and disadvantages of a fibre versus

wireless last mile connection for the NBN.

47

Table 3.6 FTTP versus Wireless last mile connection

Arguments for Fibre last mile connection

Arguments for Wireless last mile connection

• Fibre offers better security, reliability and

privacy

• Wireless is susceptible to interruptions

caused by changing environmental

conditions such as storms

• Wireless networks are more expensive

than fibre networks to maintain in the

long run

• Spectrum for transmitting wireless data is

a scarce resource

• Cheaper initial setup costs as there is no

physical connection required to each home

• Benefits of mobility and ability to utilise

broadband subscription anywhere within the

NBN

• Strong market forces resulting in Telcos

supplying the demand for wireless

infrastructure

• Freed up spectrum from switchover from

analogue to digital TV provides opportunity

for greater range and improved signal

integrity for wireless

The emergence of wireless technologies that can compete with fixed line service data rates

and also offer mobility threatens to outdate the fixed fibre network. As discussed earlier in

section 3.4 Demand Hazards, the effect of wireless technologies dominating the market

would also have a detrimental effect on the demand risk for the NBN’s FTTP network.

48

49

3.7. FINANCIAL HAZARDS 

It is estimated that $43 billion will be required to fund the NBN project. The financial hazard

present to the NBN arises as the expected availability and cost of finance might not

materialise. This can occur, for example, as interest rates and exchange rates change over

time. The most obvious financial hazard is due to scope creep and latent grounds, which

would occur during the construction phase. The impacts of these hazards have already been

discussed in section 3.2 Construction Hazards. The NBN project has already fallen privy to a

form of scope creep after a recommendation by the joint McKinsey & KPMG study [17] to

extend fibre coverage from 90% to 93% of Australian premises. This however has not had

any further financial implications and holds to the same budgetary constraints. Similarly,

latent grounds during the construction of the NBN may contribute to rising costs.

Financial hazards are apparent over the entire life of the project, not just during the

construction phase. Demand and take-up of the broadband services also has an effect on

financial risk, as a decrease in demand would lead to lower revenue levels for the project, as

discussed in section 3.4 Demand Hazards. There are already concerns about the high priced

entry-level 100Mbps plans being offered by iiNet and iPrimus.

Interest rates and exchange rates can contribute to the financial hazards. A variability in

interest rates can affect a company’s ability, in this case the NBN Co, to meet its debt

commitments [48]. The exchange rate risk for the project will be minimal as capital raised

and the revenues accrued both occur domestically. However, due to Australia’s dependence

on its primary activities such as mining exports, exchange rates can affect the price of raw

materials and therefore pass on the costs to other aspects of the Australian economy. This

may manifest itself in the form of wage increases and therefore contribute to an increase in

construction costs (see section 3.2 Construction Hazards). A decrease in sales and revenue for

the resources sector due to unfavourable exchange rates (strengthening Australian dollar),

would also affect the governments collection of taxes, most notably the mining and resource

super profit tax. This would place a strain on government funding of the NBN and affect the

choice of financing vehicle.

50

3.7.1. Financing Vehicles 

The NBN project will be financed through a combination of government and private

initiatives. The government will fund the bulk of its share of the $43 billion through

infrastructure bonds offered to the public. The peak government funding requirement will be

approximately $26 billion in year 6 [17]. The government has pledged up to $4.7 billion

directly to the NBN Co. from the Building Australia Fund. Infrastructure bonds will supply

up to $17 billion, leaving the public sector to contribute the remaining $21 billion [28].

The choice of an efficient financing vehicle can minimise the total cost of finance and reduce

risk and uncertainty. This cost of finance is made up of the return on the funds, the cost of

contingent liabilities and transaction costs. The choice of the appropriate financing vehicle

can lower the total cost of financing by [2]:

• Allocating non-diversifiable project risks to those who have the capability to better

manage this risk (i.e. the private sector).

• Improving the portfolio balance for the investors, reducing the market risk through

diversification, which lowers the return required to hold the asset.

• Reducing the lifetime transaction costs of financing and/or the costs of delay.

There are typically two broad types of financing vehicles used by governments:

1. Pay-As-You-Go (PAYGO), which involves various current revenues and fund sources

within the public sector, and

2. Capital-Market financing, which requires borrowing or equity contribution from

private sources.

The government has pledged up to $4.7 billion directly to the NBN Co. that will essentially

be funded by taxpayers’ money, a PAYGO financing vehicle. The risk with funding

government projects through PAYGO is the final total cost of financing, in most cases

resulting in a deadweight loss associated with the collection of taxes. There is an inherent

opportunity cost as these funds raised to pay for the NBN could be used to support other

programs or alternatively left with the taxpayer. As can be seen in Figure 3.19 below, the

United Kingdom’s public infrastructure financing choices differ from Australia’s in the

greater percentage of Public-Private-Partnerships (PPPs). 

51

 

Figure 3.19 Indicative shares of public infrastructure investment by financing vehicle in

Australia and the United Kingdom (2006-2007) [2]

The greater percentage of PPPs in the UK could be attributed to the full utilisation of their

Private Finance Panel. The lack of private investment in Australian infrastructure projects is

discussed in the subsequent section 3.7.2 Private Investment. The reasons for the variation in

financing practices adopted by governments can be attributed to the following common

reasons [49]:

• Infrastructure characteristics affect the user profiles and revenue-raising capacities of

particular assets

• Fiscal and macroeconomic conditions can restrict the use of particular financing vehicles

because of their budgetary consequences

• Institutional arrangements define the legal and regulatory framework as well as the

intergovernmental relationship within which public infrastructure assets are operated and

financed

• Perceptions of the role of government underlie voters’ expectations for the involvement

of government in delivering specific services and managing the economy.

These varied reasons for the choice of financing vehicles also contribute to the financial

hazard faced by the NBN. For instance, the current political climate in Australia with neither

party holding an outright majority, might lead to a choice of a financing vehicle which might

not be the most suitable for the NBN project, but would be aligned with voters’ expectations

52

in order to win voter confidence in the political party. This hazard also ties in with the

political hazard facing the NBN, as discussed in 3.8 Regulatory Hazard. Nonetheless,

whatever the choice for the particular financing vehicle to fund the NBN, there will be an

inherent risk involved that can negatively impact other unrelated infrastructure projects due

the opportunity cost involved in undertaking the NBN.

53

3.7.2. Private Investment 

Government investment is required in large-scale infrastructure projects such as the NBN in

order to regulate a natural monopoly and ensure the provision of public goods and services

whose benefits cannot be captured by market forces, for example the inherent productivity

and economic benefits provided by the NBN. However, public provision of infrastructure and

services is privy to a number of problems arising from immunity to market signals. This can

result in high costs, poor quality service levels, a lack of innovation and sub-optimal

investments [2].

The lack of capital market financing (private investment) for the NBN is caused by

uncertainty of market risk and indecision towards regulatory policies (discussed in 3.8

Regulatory Hazard). The return required by private investors increases with risk and

uncertainty [2]. There are obvious issues with the high rates of return that private sector

investors seek. Figure 3.20 below shows the gap between the desired rate of return for private

sector investment and the NBN project’s rate of return. At least for the initial years, the

project appears uninviting from a private investor’s point of view due to the 7 – 18%

difference in required rates of return.

Figure 3.20 NBN Project IRR versus required returns for private sector equity [17]

54

Figure 3.20 indicates equity investors in infrastructure projects require a 15-22 percent return

when investing prior to construction commencement, indicated by “Early roll-out” on the

graph. This required rate of return (RRR) has increased significantly from a rate of 14-15% in

mid 2009, as a result of the global financial downturn, as investors demand higher rates of

return due to the perceived increase in investment risk [17]. The WACC is based on the cost

of private sector debt and private sector equity, post tax. The high initial WACC curve is a

result of the large financial investment required to raise capital. The WACC is a good

indicator of the inherent risk involved in the NBN project. The early rollout phase presents a

high cost of equity and limited liquidity [17]. The risk premium demanded by private sector

equity should decline towards the NBN’s rollout completion as uncertainties surrounding

construction costs, business establishment and customer migration decline. The decreasing

WACC also relates to the increasing stability of the project as regulatory and policy

safeguards are implemented. The “Operations” phase of the NBN project relates to the

premium required of 5-10 percent over the return generated by a mature infrastructure asset.

The technological nature of the NBN also provides increased risk for private investors. The

NBN project could be described as more of venture capital investment, as opposed to an

infrastructure investment. Venture capital investments present greater risks but provide

greater returns. Venture capital investments typically have a shorter investment horizon with

returns usually realised within 7 years. The inherent problem with the NBN is the timeline of

the project. The high risk of returns of the NBN is further impacted by the relatively long

project rollout. As mentioned before, NBN Co.’s Mike Quigley only expects capital returns

in 20 years [28]. However, there is hope for future private investments as Brisbane’s Lord

Mayor Campbell Newman announced recently that i3 Group will rollout Brisbane’s own

fibre network using sewer cable laying methods, which is expected to cost 60% less than

NBN methods [50]. This venture poses no cost to Brisbane ratepayers as the venture is

funded purely by the i3 Group. Overall, the financial risk of the NBN for private investors is

a result of a high-risk project providing opportunity for high-returns, but over a longer than

desired timeframe.

55

3.7.3. Operating Revenue 

The main financial risk facing the operational phase of the NBN is from the unknown take-up

rate of fibre connections. Lower demand, and therefore a lower take-up of fibre connections

would adversely affect the revenue generated by the NBN. The McKinsey implementation

study estimates that 75% - 90% of premises within the fibre network will be activated by

2035 as shown in Figure 3.21 below.

Figure 3.21 Aggregate fibre take-up scenarios [17]

It has been broadly estimated that between 10 and 12.5 million premises would take up fibre

connections by 2035. The difference between the upper and lower estimates represents a

variance of 20% in projected operating revenue. In December 2009 there were 9.1 million

premises that subscribed to some form of internet connection [47] as shown in Table 3.7

below. If all 9.1 million current Internet subscribers in Australia were to switch over to fibre,

this would equate to 90% of current premises within the proposed fibre footprint.

56

Table 3.7 ABS Internet Activity, December 2009 [47]

Subscriber type Number (000) Proportion (%)

Dial-up

Analog 925 10

Other 2 0

Total dial-up 927 10

Non dial-up

DSL 4,193 46

Cable and fibre 935 10

Satellite 107 1

Wireless

Fixed 107 1

Mobile 2,838 31

Total fixed and mobile

wireless 2,945 32

Other 5 0

Total non dial-up 8,184 90

Total all subscribers 9,112 100

It should be duly noted that the number of premises within the fibre footprint is expected to

grow from 10 million to approximately 13.5 million by year 2035. The risk of a lower take-

up of fibre by premises also translates into a lower return for project investors and relates

back to the risk to private investment as mentioned in section 3.7.2. Projects with high fixed

costs require higher operating revenues in order to achieve economies of scale. The NBN

presents a large sunk cost of $43 billion as well as high operating costs.

57

3.8. REGULATORY HAZARD 

Regulatory risks can occur in infrastructure projects when government regulations potentially

affect the project’s profitability. Successful regulation can improve efficiency and provide a

stable investment environment. However, regulation uncertainty can affect stakeholder

expectations about the regulatory outcomes achievable, thereby creating stronger incentives

for disagreement, uncertainty and a higher probability of inconsistency in the application of

regulation [2]. Such risk arises, for example, due to a change in planning and environmental

requirements, pricing determination and regulatory conditions governing the entry of new

service providers. Government regulations generally address the following two areas:

• Price regulation, and

• Access regulation

NBN Co. will be provided on a wholesale basis and ISPs will set their price accordingly. The

task of price determination can affect the demand for take up of the NBN by customers. If the

access price is set too high, then the initial number of customers will be too low (see section

3.4 Demand Hazards). On the other hand, setting the price too low over the long term will

lead to the NBN being unable to generate the revenue necessary to operate and maintain

existing infrastructure (see section 3.7 Financial Hazards). Price regulation, or the threat of

such regulation, can be a deterrent to private investment in public infrastructure. Regulatory

uncertainty can also result in delays to investment as investors attempt to minimise the cost of

regulatory risk and retain a range of options.

3.8.1. Regulatory Policies 

NBN Co. was established as a publicly owned body under the understanding that it would be

privatised at the completion of the NBN project. However, recent political instability as a

result of the 2010 federal election has lead to discussions about the final public or private

ownership of the NBN. From the early 1990s there has been a trend towards the commercial

or private provision and ownership of public infrastructure [2]. Privatisation promotes

productive efficiencies, better-valued service levels and innovation. Private companies can

react more quickly to challenges and opportunities without going through a bureaucratic

decision making processes. In a technologically focused project like the NBN, the ability to

58

adapt quickly to changing market conditions will be key to survival. However, privatisation

does lead to the hazard of monopolistic behaviour by any one firm who possesses a greater

market share and can therefore assert dominance on other telcos. A decision needs to be made

as to the maximum share ownership of the NBN Co. by any one private entity. There have

been discussions by leading telcos about whether ownership should be limited to 20% or just

5% in order to promote better market competition [51]. Effective policymaking will ensure

there is sufficient competition by limiting majority ownership. However, share ownership

must still allow for competent decision-making by a few major private stakeholders.

There is an opportunity for the government to promote future generation wireless

technologies through effective policymaking with regards to spectrum usage. The current

switch over from analogue to digital television will have the effect of freeing up wireless

spectrum due to digital signals being more efficient users of the radio-frequency spectrum.

The USA’s Federal Communications Commission (FCC) has recently instigated such a

policy to allow for private mobile and television companies to purchase the now unused

spectrum. The most desired and important frequency for Mobile phone companies is the

700Mhz range. This frequency allows signals to travel for kilometres while unaffected by

weather, foliage and able to travel through buildings. They will allow mobile carriers to

cover, from a single tower, up to ten times the area possible from a tower using existing

frequencies [52]. The freeing up of this spectrum provides real opportunities for the

advancement of wireless technologies and the development of wireless infrastructure by

private telcos. The Australian government needs to realise the potential of the freed up

spectrum and set policies accordingly to maximise its benefit to private and public users.

An effective policy framework will promote innovation and application development that

fully utilises the NBN’s capabilities. Application development and innovation relates back to

one of the main reasons for the undertaking of the NBN, to facilitate economic growth. In

addition, an adequate reform of the telecommunications framework and reform of existing

consumer safeguards in the telecommunications sector will complement the NBN network

and ensure efficient use of resources [53]. There is, however, the hazard that inappropriate

policy setting will result in constrictive regulations on the NBN and the full potential and

benefits of the NBN will not be realised.

59

3.8.2. Telstra’s Fibre Network and Customer Base 

At the commencement of this thesis, an issue existed surrounding the cooperation of Telstra

with the NBN Co. The design of the new fibre optic network across Australia accounted for

Telstra’s existing fibre-optic cabling which covers around 150 000 kilometres across

Australia [54]. In the worst-case scenario, the NBN faced laying thousands of kilometres of

fibre, already covered by Telstra. This would represent a significant cost to the NBN project

and be seen as a waste of materials and resources on what would essentially be a duplicated

network already covered by Telstra. On the 20th June 2010, Telstra and the NBN Co. entered

into a Financial Heads of Agreement, which essentially would lead to a faster, cheaper and

more efficient rollout of the NBN. The agreement, worth an expected $11 billion, provides

for the use of existing Telstra infrastructure, including pits, ducts and backhaul fibre. The

agreement also covers the progressive migration of customers from Telstra’s copper and pay-

tv cable networks to NBN Co.’s new fibre network [55]. This agreement effectively lowers

the significant financial risk that faced the NBN Co. due to the excessive costs that would

have been involved in duplicating Telstra’s existing fibre network. It also accounts for the

concerns of sufficient demand for the new fibre network by including the migration of part of

Telstra’s broadband customer base across to NBN Co.

3.8.3. Political Instability 

The federal election in 2010 led to an even greater focus on the NBN, which was originally

proposed by the Australian Labour Party. The opposition Liberal Party have different views

on a NBN and proposed an alternative solution, which is summarised and compared against

the Labour’s NBN plan in Table 3.8 below:

Table 3.8 Labour’s NBN versus Liberal’s proposed broadband network

Australian Labour Party - NBN 2.0 Liberal Party of Australia – NBN 3.0

• FTTP network • HFC, DSL and wireless network

• $43 billion investment • $6.3 billion investment

• Broadband speeds of 100Mbps • Broadband speeds of at least 12Mbps

• 9 year rollout • 7 year rollout

• 99% Coverage • 97% Coverage

60

The two most significant differences are ultimately the capital expenditure and the expected

broadband speeds provided by the two projects. The Liberal party’s NBN proposal

represented a large cost saving for “reasonable” speeds. A few days before the federal

election, NBN Co Chief Mike Quigley announced that the NBN project would deliver 10

times initial predicted speeds, up to 1Gbps [30]. The timing of the statement acted to

reinforce the Labour Party’s commitment to a high-speed broadband network, even though

there are doubts as to whether such speeds are necessary for the home. The Alliance for

Affordable Broadband (AAB), which consists of a number of top Australian telco chief

executives, suggested that speeds of up to 1Gbps would not be required by homes in the short

to medium term [56]. The Liberal Party’s NBN plan focuses more on the importance of

market powers (private investment) to deliver the “last mile” service. The AAB also firmly

believes that the “last mile” connection would be better serviced by emerging wireless

technologies such as 4G LTE and Wi-Max which would address increasing demand for

mobile connectivity [56].

Early release sites for the NBN are focussed on remote areas that don’t have access to

broadband services. There is also a focus on establishing the fibre backbone, which will act to

connect rural and urban areas across Australia. The six regional backbone blackspot priority

(RBBP) locations that are of importance are [57]:

1. Geraldton, Western Australia

2. Darwin, Northern Territory

3. Emerald and Longreach, Queensland

4. Broken Hill, New South Wales

5. Victor Harbor, South Australia

6. South West Gippsland, Victoria

The above RBBPs are displayed in Figure 3.22 below. The NBN implementation plan is set

to upgrade metropolitan areas and other areas with existing high speed broadband in the final

release. Therefore it could be argued that the first part of the NBN rollout is similar to the

Liberal Party’s backhaul backbone fibre network proposal.

61

Figure 3.22 Priority release sites across Australia [58]

62

The recent federal election has already had an effect on the proposed rollout. The rollout has

been redesigned to address more regional areas first. This decision came as a result of the

political pressure on the Labour Party to win marginal independent seats after the recent 2010

federal election resulted in a hung parliament. There will also be an accelerated rollout of

wireless and satellite solutions, which will aid to connect more rural areas sooner. This late

change of rollout to oblige a few key politicians demonstrates the regulatory hazard present in

the high stakes NBN project. It also identifies possible future hazards that the NBN’s project

rollout and operation can be affected by political instability.

In summary, the recent federal election of 2010 presented a significant political risk to the

NBN project. If the Liberal party had formed a coalition government, Labour’s $43 billion

NBN would have be abandoned in favour of a lower cost but slower broadband network. The

9 year life span of the NBN project means that there is still continuing risk for political

instability until at least the next federal election. However, due to the similarities between the

fibre backbone focus by both the Labour and Liberal Party’s NBN plans, the initial 4 year

rollout of either project would be similar. In the case that the Labour Party loses power in the

next election, the NBN would not become redundant and necessarily disbanded. The fibre

backbone established would be able to be incorporated into the Liberal’s plans to revert to a

FTTN network instead of FTTP and leave the “last mile” connection to the telcos and market

powers. There is also considerable risk that the Labour Party will continue to adapt its

original NBN plan to win the support of voters. If the NBN is used as a tool to sway the

public’s political opinion, then there is serious concern that the NBN could be designed to

look good only on paper and appealing to voters instead of being practical, functional and in

the best interests of future generations.

63

4. METHODOLOGY This section sets out the method that this thesis follows in performing the risk assessment,

sensitivity analysis and cost-effectiveness analysis.

4.1. RISK ASSESSMENT 

The risk assessment is structured using the Fault/Event Tree Analysis (FTA/ETA) method

which conforms to Australian Standard IEC 61025 – 2008 [7]. The FTA is used to develop a

graphical representation of the hazards that lead to the Top Event, failure of the NBN. The

first step in the risk assessment involves identifying hazards that may lead to the failure of the

NBN. Using the FTA method, the multiple modes of failure, such as financial, regulatory etc,

are investigated to determine the possible underlying root causes. Likelihoods and

consequences are then assigned to the various hazards. A logarithmic, five-point scale is used

to assign the relative probabilities of failure (Pf) and consequences of the hazards occurring

[59]. Risk estimation involves predicting the expected frequency of the undesired event

occurring. Similarly, consequence analysis is used to estimate the impact should the

undesired event occur. The following tables outline the criteria used to assign the values.

Table 4.1 Likelihood Ratings

Value Pf Rating Description

1 1/1000 Rare May occur in exceptional circumstances, once in 100 years

2 1/333 Unlikely Could occur at some time

3 1/100 Moderate Moderate likelihood of occurrence, once in 50 years

4 1/33 Likely Will probably occur

5 1/10 Almost

Certain Expected to occur during life of the NBN, once in 25 years

64

Table 4.2 Consequence Ratings

Value Rating Description

1 Negligible Dealt with routinely

2 Low Threatens efficiency of effectiveness

3 Medium Requires significant review of or change to the operation

4 High Threatens the survival of the project

5 Severe Critical to the operation of the project

Following the hazard identification, risk estimation and consequence analysis, a number of

key hazards are identified as high-risk scenarios. Remedial actions are then developed to

address the key hazards in order to intervene or simply mitigate the possible effects of the

hazards to the NBN.

The risk assessment is conducted using a custom excel spreadsheet model, named NBN Risk

Model. The various hazards are assigned values according to the tables above. The hazards

are given a likelihood rating (Pf) for the current NBN, called the ‘Base Case’. The likelihood

of these failures are transferred up the Fault Tree through a combination of OR and AND

gates, using the following equations as used by Williams (2001) [59].

For the AND gates:

Pf AND = Pi × Pi+1 × ...× Pn Equation 1

For the OR gates:

PfOR =1− (1− Pi) × (1− Pi+1) × ...× (1− Pn ) Equation 2

Users of the NBN Risk Model can also enter their own likelihoods for the hazards in the

respective input cell. Only the highlighted cells on the inputs page can be altered as some of

the hazard’s values are linked to other hazards. Alternatively, users could set the likelihood

for all hazards to a number between 1 and 5 using the macro buttons. The resulting reductions

of likelihoods from remedial actions are also provided in the spreadsheet. A number of macro

buttons are available to ‘apply’ the remedial actions, which in turn would indicate the risk

reduction through numerical and graphical representation on the results worksheet.

65

The process of risk estimation and consequence analysis is a subjective process. However,

wherever possible, research was conducted to formulate better predictions for probability of

failure and consequences. The research data that aided the estimation process is included in

the previous section 3 Theory.

 

4.2. SENSITIVITY ANALYSIS 

The sensitivity analysis investigates how a variation in inputs to the NBN Risk Model affects

the outputs to the model. By varying the input parameters of consequence and probability of

failure between 1 and 5, the dynamic behaviour of the risk model is observed. Effectively,

this involves assigning all hazards a value of 1 and assigning the consequences of the failure

modes a value of 1. The hazards are then assigned a value of 2 while holding consequences

constant at a value of 1. This is carried out for all values up till 5 and then repeated by

holding the hazards constant and varying the consequence values. A graphic representation of

the results will clearly indicate the degree of sensitivity of the risk model to the variation of

probability of failure and consequence.

4.3. COST­EFFECTIVENESS ANALYSIS (CEA) 

A CEA acts as a means for comparison of different remedial options under consideration.

The remedial actions generated by the risk assessment are used to determine their relative

costs with respect to the cost of the NBN. The forecasted cost of $43 billion for the

construction of the NBN is used to calculate the relative costs. Similarly, the relative failure

for the remedial actions is determined with respect to the base case NBN, by setting the base

case to a relative failure ranking of 5. A calculation of relative risk versus relative cost is then

determined by the product of the relative cost and the relative failure, where the lower the

score, the better the outcome. A cost-benefit analysis was deemed unsuitable for this analysis

due to numerous intangible benefits and costs associated with the NBN project. Placing a

monetary value on such costs and benefits would be too subjective to be credible for this

study. As such, any costs or benefits were given a relative ranking so that they may still be

quantitatively analysed.

66

67

5. RESULTS  The following Table 5.1 Identified Hazards and Likelihoods of Failure, shows the various

hazards identified in the NBN risk assessment along with their probability of failure (Pf). A

total of 59 hazards were identified as having a possible affect on the NBN. The pages

following Table 5.1 show the FTA performed using the identfied hazards. The FTA

graphically shows the relationships between the identified hazards and how they contribute to

the overall risk ranking of the NBN. The FTA has been split into the seven failure modes as

addressed under section 3 Theory, namely:

1. Construction Hazards

2. Operational Hazards

3. Demand Hazards

4. Network Hazards

5. Technological Hazards

6. Financial Hazards

7. Regulatory Hazards

The final FTA diagram showing the Top Event, Failure of the NBN, is a combination of these

seven failure modes, resulting in an overall risk ranking.

68

Table 5.1 Identified Hazards and Likelihoods of Failure

Hazards Description  Likelihood  Pf Construction Hazards

Delay of Works Shortage of ICT Labour - Splicing Technicians 3 0.0100

Delay of Works Shortage of ICT Labour - Other ICT Labour 3 0.0100

Delay of Works People (Organisational, Disputes resolution, Political) 3 0.0100

Delay of Works Bankruptcy of Contractors 2 0.0033

Delay of Works Materials - Shortage of SATs, OLTs, ONTs, 1 0.0010

Delay of Works Materials - Design (ISO drawings) 2 0.0033 Delay of Works Materials - Shortage of Fibre Supply 2 0.0033 Delay of Works Latent Ground 4 0.0333 Design problems Security - % Aerial Works 3 0.0100

Design problems Security - Protocol and Communication standards used 3 0.0100

Design problems Scope Creep - % of Australian Premises Supplied with Fibre >90% 4 0.0333

Design problems Third party Integration of Alliances 3 0.0100

Budget Exceed Underground construction (% Existing Ducts available) 3 0.0100

Budget Exceed Latent Ground 4 0.0333 Budget Exceed Labour Costs Increase 2 0.0033 Budget Exceed Materials Supply & Demand 2 0.0033 Operational Hazards

Cyber Crime, Spam & Intellectual Property 4 0.0333

Less than 90% Australia reached by Fibre 1 0.0010

Required 100Mbps data rates Current ability of technology to obtain 100Mbps 3 0.0100

Maintenance and Equipment Failure Lack of redundancy in design 3 0.0100

Maintenance and Equipment Failure Reduced equipment/project lifespan 2 0.0033

Demand Hazards

Increased Demand Government Incentives - Above expected take-up of lead-ins 2 0.0033

Increased Demand Increased demand for high speed broadband 3 0.0100

Increased Demand Increase in Travel Costs 4 0.0333 Increased Demand Increase in population 4 0.0333 Increased Demand Innovation and Application development 3 0.0100 Decreased Demand High price Charged by Wholesaler/ISPs 4 0.0333 Decreased Demand Fibre Technology superseded 4 0.0333 Decreased Demand Negative NBN publicity 3 0.0100 Decreased Demand Below average take-up of lead-ins 3 0.0100 Decreased Demand Reliability issues 3 0.0100

69

Hazards Description  Likelihood  Pf Network Hazards

Retailers vs Wholesalers High price Charged by Wholesaler/Service Providers 4 0.0333

Retailers vs Wholesalers Poor service levels 2 0.0033

Telstras FTTP Network Telstra operating own last mile FTTP connection 1 0.0010

Maintenance & lack of Redundancy in design 3 0.0100

New & Competing technologies 4G & Future Generation Wireless 4 0.0333

New & Competing technologies

Poor integration of fibre (90%) and wireless/satellite 2 0.0033

Slow Data Rates Increased demand for high speed broadband 3 0.0100

Slow Data Rates Above expected take-up of lead-ins (Government Incentives) 2 0.0033

Slow Data Rates Bottlenecks in network design 5 0.1000 Technological Hazards Fibre Superseded 4G & Future Generation Wireless 4 0.0333

Fibre Superseded Increased demand for wireless broadband - Demand for mobility 5 0.1000

Fibre Superseded New broadband technologies 4 0.0333 Security Accessibility to Fibre - % Aerial Works 3 0.0100 Security Ability to tap fibre lines 3 0.0100 Data Rates Ability to provide 100Mbps data rates 3 0.0100 Financial Hazards

Scope creep % of Australian Premises Supplied with Fibre >90% 4 0.0333

Scope creep Integration of new community technologies 2 0.0033

Global Financial Downturn Exchange Rate - Expensive imported materials and equipment 2 0.0033

Global Financial Downturn Government Revenue downturn 3 0.0100

Project Financing Government Investment - 10% ($4.7bn) Capital requirements 4 0.0333

Project Financing Government Investment - Infrastructure bonds 4 0.0333

Project Financing Lack of Private Investment 5 0.1000 Project Revenue Below average take-up of lead-ins 3 0.0100 Regulatory Hazards

Lack of telecommunication and competition policies

NBN Co. Natural Monopoly, competition policy, RF spectrum assignment

5 0.1000

High price Charged by Wholesaler/Service Providers 4 0.0333

Telstra's Co-operation Telstra not sharing customer base with NBN Co. 2 0.0033

Telstra's Co-operation Telstra operating own last mile FTTP connection 1 0.0010

Political Instability Labour vs Liberal broadband plans 5 0.1000

 

70

5.1. FAULT TREE ANALYSIS (FTA) 

Figure 5.1 Construction Hazards FTA

71

Figure 5.2 Operational Hazards FTA

72

Figure 5.3 Demand Hazards FTA

73

Figure 5.4 Network Hazards FTA

74

Figure 5.5 Technological Hazards FTA

75

 

 

 

 

 

 

 

 

 

 

 

 

 

Figure 5.6 Financial Hazards FTA

76

Figure 5.7 Regulatory Hazard FTA

77

 

Figure 5.8 Combination of individual FTAs leading to Top Event

78

 

79

5.2. KEY HAZARDS 

The combination of the seven failure modes and 59 hazards identified in Table 5.1 generate

the following results:

Table 5.2 Risk Assessment Results

Likelihood Consequence Risk Ranking

Construction Hazards 0.173 3 0.519

Operational Hazards 0.057 3 0.170

Demand Hazards 0.172 4 0.690

Network Hazards 0.185 3 0.554

Technological Hazards 0.167 4 0.670

Financial Hazards 0.209 5 1.043

Regulatory Hazards 0.220 5 1.102

Total Risk Ranking for the NBN 4.747

A total risk ranking of 4.74 is calculated for the NBN.

Table 5.2 above shows the breakdown of risk by failure modes. Regulatory hazards are

determined to be the highest risk to the NBN with a risk ranking of 1.102. This was followed

by financial hazards and demand hazards. The graph below is a graphical representation of

the risk ranking results.

80

Figure 5.9 Risk ranking results for various hazards to the NBN

In order to address the key hazards of Regulatory, Financial and Demand, the underlying

hazards that contribute to these top-level failure modes will have to be addressed. From Table

5.1, the main underlying hazards are:

• Construction hazards:

o Delay of works due to latent grounds

o Exceeds budget due to latent grounds

o Scope creep through greater than 90% coverage

• Operational Hazards:

o Cyber crime, spam and intellectual property

• Demand Hazards:

o Increased in demand for high speed broadband

o Increased in travel costs

o Increase in population

o High price charged by wholesaler/ISPs

o Fibre technology superseded

• Network Hazards:

o High price charged by Wholesaler/ISPs

o 4G and Future generation wireless technologies

o Increase in demand for high speed broadband

o Bottlenecks in network design

0.519 

0.170 

0.690 

0.554 0.670 

1.043  1.102 

0.0 

0.2 

0.4 

0.6 

0.8 

1.0 

1.2 Risk Ran

king 

81

• Technological Hazards:

o Increase in demand for wireless broadband

o Increase in demand for mobility

o New emerging broadband technologies

• Financial Hazards:

o Lack of private investment

o Scope creep through greater than 90% coverage

o Project Financing – capital requirements and infrastructure bonds

• Regulatory Hazards:

o Lack of telecommunication and market competition policies

o Political instability - Labour vs. Liberal NBN plans

o High price charged by Wholesaler/ISPs

A number of the above hazards crossover within the seven failure modes. For example, scope

creep relates both to construction and financial hazards as it will increase construction time

and lead to an increase in costs. By dealing with the one hazard, both failure modes of

construction and financial will benefit from hazard reduction. Addressing these hazards will

lead to the greatest risk reduction through remedial actions. The above list of hazards is

summarised to form the following eight key hazards.

1. Scope creep

2. Increase in demand for high speed broadband

3. Increase in demand for mobility/wireless connectivity

4. Bottlenecks in network design

5. High prices charged by Wholesaler/ISPs

6. Lack of private investment

7. Lack of telecommunication and market competition policies

8. Political instability

82

5.3. SENSITIVITY ANALYSIS 

A sensitivity analysis was conducted on the overall risk ranking, by systematically varying

the inputs of construction, operation, demand, network, technology, financial and regulatory

hazards. The likelihood ratings for all hazards were varied from 1 to 5, while the consequence

ratings were also varied on the 1 to 5 scale. The overall risk ranking for the combined failure

modes is displayed below.

Table 5.3 Sensitivity Analysis Results

CONSEQUENCE

LIKELIHOOD Negligible Low Medium High Extreme

Rare 0.057 0.113 0.170 0.227 0.284

Unlikely 0.187 0.374 0.562 0.749 0.936

Moderate 0.545 1.091 1.636 2.182 2.727

Likely 1.646 3.293 4.939 6.585 8.232

Almost Certain 3.818 7.635 11.453 15.270 19.088

83

5.4. REMEDIAL ACTIONS 

Four remedial actions to address the Key Hazards have been evaluated. Each action addresses

a combination of hazards, which exist across the 7 different failure modes, but are targeted

towards addressing Regulatory and Financial risk. The actions suggested and investigated

are:

1. The Liberal’s broadband plan with wireless last mile connection

2. NBN 3.0

3. Domestic caching

4. Regulatory reform

Domestic caching and regulatory reform will require the existence of a broadband network in

order for the benefits of risk reduction to be realised. The Liberal’s broadband plan and NBN

3.0 are proposed to act as replacements for the current NBN. A combination of the broadband

plans and domestic and/or regulatory reform could be found to be the most effective plan of

action. This will be addressed in the results of 5.5 Cost-Effectiveness Analysis.

5.4.1. Liberal’s national broadband plan 

A big focus of the recent 2010 federal elections was the different broadband plans put

forward by the two major parties; the Labour and the Liberal Parties. The liberals contested

the election by providing campaign promises to disband the current $43 billion NBN and

instead rollout a cheaper $6.3 billion fibre backbone network with upgrades to the existing

copper network to a HFC and wireless connectivity. This plan covers 97% of Australian

premises with speeds of 100Mbps down to at minimum of 12Mbps. The cost structure of the

Liberals $6.3 billion NBN plan is split amongst the following actions [60]:

• $2.75 billion investment in a national fibre backbone

• $1 billion investment in fixed-wireless networks in rural and remote Australia

• $1 billion investment on metro wireless networks

• $750 million on increasing access to upgraded broadband via the old copper network

• $700 million on satellite services for the remote 3% of the country

84

A risk assessment conducted on the Liberal’s plan using the NBN Risk Model highlights a

number of risk reductions and risk increases in certain areas. The likelihoods of hazards

occurring were reduced in the following areas:

• Private investment - as costs are lower and the broadband plan is focused on private

sector development of the network and wireless technologies

• Lower wholesale price setting by NBN Co. - as construction costs will be lower than the

NBN and therefore required returns and operating revenues will be lower

The Liberal’s plan presented higher likelihoods of hazards occurring in the following areas:

• Percentage of Australian’s reached by fibre connections will be less than the NBN

• Lack of redundancy in design, due to less fibre construction, leading to possible

maintenance and equipment failure

• Increased risk in demand for high speed broadband as network will be slower than NBN

• Telstra operating own last mile connection

• Telstra not sharing their previously negotiated customer base and existing fibre

infrastructure.

Overall, the Liberal’s broadband plan presents a higher risk ranking than the current NBN

plan. However, a cost-effectiveness analysis will most likely show that the Liberal’s plan is

more cost-effective due to its cost of construction being projected at 15% of the NBN.

However, the risk assessment of the Liberal’s plan did highlight the shortcomings of a

cheaper network, which may become technologically outdated sooner and ultimately result in

slower data rates.

85

5.4.2. NBN 3.0 

The Alliance for Affordable Broadband (AAB) was formed by a group of Telco chiefs and

experts. They put forward suggestions for amendments to the current NBN, calling their

version NBN 3.0. The AAB propose that NBN 3.0 should service 98% of Australians using

4G wireless technology for the last mile connection instead of FTTP. The following table

highlights the key similarities and differences between the NBN and NBN 3.0

Table 5.4 Current NBN plan versus NBN 3.0

Similarities Differences

• NBN 3.0 will operate off a National Fibre

Backhaul Network

• Speeds of 100Mbps

• Fibre for schools, hospitals and most

businesses providing speeds up to 1Gbps

• Satellite for remote areas at speeds up to

12Mbps

• Fibre backbone and 4G Wireless

technologies used for last mile

connection

• Project rollout over 4 years

• Public/private model utilising existing

private fibre and wireless infrastructure in

conjunction with new national wholesale

4G network.

• 4G Wireless network costing $3.5 billion

The NBN 3.0 plan emphasises the importance of private competition. Competition based on

infrastructure provision is preferential over the current NBN’s plan for infrastructure

monopolies with retail competition. The NBN 3.0 also prioritises providing broadband to

those who don’t have access, rather than providing up to 1Gbps connections to premises in

urban areas that already have access to broadband. The focus on 4G wireless technologies for

connecting 98% of Australians is highly dependent on government’s policymaking decision

with respect to the freeing up of spectrum with the switch over to digital television signals

(see section 3.8.1 Regulatory Policies). The opening up of the 700Mhz spectrum will allow

wireless to become a plausible alternative to fibre connections. At this frequency, wireless

signals are able to carry higher data rates with less attenuation over large distances. The

signal is also less affected in built up areas by buildings and other obstructions that may

affect line of sight connection. As a result, required data rates of 100Mbps will be achievable

and the greater signal range will allow a single wireless tower to cover a greater region and

therefore lower the fixed infrastructure cost.

86

NBN 3.0 is projected to cost US$3 billion. A similar national 4G wireless network in the

USA is projected to cost US$7 billion, which includes operational costs for the first 7 years

[56]. The network will cover 93% of 300 million people in the USA, over an area roughly the

same landmass of Australia. Considering Australia’s lower population of 22 million and that

75% of the population is located along the coastal region, leads to approximating half the cost

of the US 4G wireless network. For the purpose of this thesis, NBN 3.0 will be costed at AU$

3.5 billion, rounding up after currency conversion rate of around US$0.90 to one Australian

dollar. It must be noted that the above costing only includes plans for provision of 4G

wireless technology to 98% of Australian premises. The AAB provided no further cost

structure for the fibre backbone, fibre to schools, hospitals and businesses and satellite

connections for rural areas. Therefore, the analysis will only consider the 4G wireless

network in assessing its risks and benefits as a remedial action.

The NBN 3.0 will be suggested as a three-part remedial action for the current NBN. The first

option will consider the NBN 3.0 as a standalone plan, providing 98% wireless coverage,

which will be referred to as NBN 3.0. The second option will consider NBN 3.0 as an

addition to the existing NBN, by providing both FTTP and the 98% wireless coverage, which

will be referred to as NBN 3.1. The cost of the two plans combined will simply be their

summation. The final and third option will combine the Liberal Party’s broadband plan with

the NBN 3.0 to provide a plan similar to that suggested by the AAB, which will be referred to

as NBN 3.2. This will include the fibre backbone, fibre to schools, hospitals and businesses

providing speeds up to 1Gbps and satellite connections for rural areas at speeds up to 12Mbps

and extending 4G wireless from just rural and metropolitan areas to 98% coverage. The cost

of these two plans combined will be added together, less the Liberal Party’s included costing

of $1bn worth on fixed wireless for rural and remote Australia, and $1bn for metro wireless.

The costing of these three plans is shown below:

NBN 3.0 = $3.5

NBN 3.1 = $43bn + $3.5bn = $46.5bn

NBN 3.2 = $6.5bn + $3.5bn - $2bn = $8bn

87

5.4.3. Domestic Caching  

The problem of slow overseas data rates is due to a combination of sheer distance and to a

lesser extent, the number of access paths via submarine cables to countries such as the USA.

The emergence over the past decade of dynamic websites, which continuously update, meant

that access for that website content was stored in one location (ie a server in the USA). Rather

than accessing a local cache, which is possibly out of date, the original overseas cache is

accessed through international submarine fibre links. However, there has been a vast growth

in demand for video content, which is classified as static media because the file does not

change after creation. The figure below shows the forecasted growth for video and other

media.

Table 5.5 Consumer Internet Traffic Forecast by Sub-Segments [31]

The predicted Compound Annual Growth Rate (CAGR) for each sub-segment is indicated in

the last column of the above table. It is clear that Internet video to TV is expected to have the

highest growth rate at around 107%. This can be attributed to the increasing demand for iPTV

services. Internet video also poses high growth of around 48% due to popular media forums

such as YouTube. A graphical representation of the above data is shown on the following

page.

.

88

Figure 5.10 Consumer Internet Traffic Forecast by Sub-Segments [31]

Figure 5.10 above indicates that there will most likely be a large growth in static media

represented by File sharing, Internet video and Internet Video to TV. Video traffic is data

heavy and will continue to be with the increasing popularity of high definition and 3D video.

Australian ISPs already pay up to 17.5 times more for IP transit over international submarine

cables than their international counterparts [38]. The idea is to reduce costs while

simultaneously improving quality of service by relocating static media locally within

Australia. This would allow the full utilization of the 100mbps FTTP connection speeds, as

data would be located domestically and users would not fall privy to sub NBN data transfer

rates due to slower international connections.

Domestic caching forms part of a Content Delivery Network (CDN). In a CDN, servers store

popular media at strategically placed server points in a network so as to maximise bandwidth

for access to the data. A client (Australian user) will access a copy of the data near to the

client (domestically), as opposed to all clients (all international users) accessing the same

central server (for example a server in the USA) so as to avoid a bottleneck near that server.

The strategically placed server locations can free up network capacity and lower packet

delivery costs paid by ISPs. A well implemented CDN can introduce network redundancy

which is vital during large scale power, network or hardware outages [61].

2000 

4000 

6000 

8000 

10000 

12000 

14000 

16000 

18000 

20000 

2009  2010  2011  2012  2013  2014 

Petrab

ytes per m

onth (P

B) 

Years Forecasted 

File Sharing 

Internet Video 

Internet Video to TV 

Web/Data 

Video Calling 

Onlne Gaming 

VoIP 

89

There has been a trend of multi-billion dollar investments in local data-centres in recent

years, notably by NextDC, who have purchased land for $15 million for data-centres in

Brisbane and Melbourne [62]. Fujitsu’s new Perth based data centre spans some 8,000 square

metres. At an average cost of construction and fitting out around $10,000 per square metre,

this equates to a cost of construction of approximately $80 million [63]. There are plans to

build a $1 billion data centre in Canberra, which will generate an expected $31 million for the

Australian economy each year [64]. In order to maximise data efficiency in the network, a

small percentage of the capacity at one of these data centres would be used at various

locations around the country. This approach would allow users to access data from servers

with a low latency. Telstra plans to fit out 12 small data centres across Australia as part of its

CDN at a cost of $14 million [65]. These network media centres, being rolled out over the

course of 5 years, will be located at Ethernet aggregation points within existing telephone

exchanges. There are a further 147 aggregation points across Australia’s major cities.

For this analysis we will consider all of these 147 aggregation points as necessary for a

comprehensive CDN, accessible by all Australian ISPs. Using an upper average cost of $1.25

million to fit out the telephone exchanges with the necessary hardware, it will cost of a total

of $183.75 million. It is also suggested that an additional 5 data centres will be required for

each state and territory capital to future proof the expected growth in data requirements that

will be evident by the end of the NBN rollout in 2020. This would entail the construction of

additional 40 data centres at a cost of approximately $80 million each, leading to a total cost

of $3.38 billion for this remedial action. The beneficial reduction of risk from such a CDN

will affect the risk assessment in the following areas:

• Network Hazards and

• Operational Hazards

The network hazards will be reduced by mitigating the data rate bottleneck effect caused by

overseas access. This will allow the NBN to fully utilise its projected 100Mbps and allow for

the full economic benefits of high-speed broadband to be realised. Similarly, a CDN will

reduce operational hazards by introducing redundancy of data and access in the network. As

previously mentioned, a user will not be simply cut off from accessing data as the multiple

storage points allow other paths within the network to be utilised if there is a large-scale

power, network or hardware outage.

90

5.4.4. Regulatory Reform: 

Regulatory reform and efficient policymaking will address the obvious regulatory risks but

not political instability. A number of telecommunication-based policies could be introduced

to address the following:

• Improving productivity across the economy

• Management of government owned resources - NBN Co. and RF spectrum

• Competition amongst ICT and ISP operators

• Consumer protection

• Rural, regional and remote Australia access

• Reducing unnecessary regulation, and

• Community safety and national security

Policies in these areas will lead to a reduction in risk for regulatory, financial, demand and

operational hazards. The first act should address private ownership of the NBN Co. following

the completion of the NBN. Private ownership of the network is necessary to promote

efficiency and survival of the NBN. The private sector normally prevails over government in

striving for cost reductions and operating efficiencies in the search for profit maximization. A

balance between the maximum percentage ownership by anyone private investor is necessary

to facilitate competition, while still allowing a large enough ownership, say 25%, for concise

decision making by a few major owners. This will reduce regulatory risk and also instill

investor confidence within the NBN to allow for lower risk private investments.

Following on from the previous point, the financial hazards of the NBN could be addressed

by the actual development of up to date communication based policies. The act of

policymaking would mitigate perceived market risk for potential private investors. A

reduction in perceived market risk would mean investors require lower rates of return, which

would be closer to the rates of return offered by the NBN project (see section 3.7.2 Private

Investment). This would lead to greater private investment, earlier on in the project timeline,

rather than later when the risks of construction have been mitigated.

91

The magnitude of the NBN project provides an inherent risk of a natural monopoly

developing. Sufficient competition based policy could provide protection for consumers and

adequate competition would lead to a lowering of demand risk. Competition leads to more

socially efficient price setting (lower prices) in exchange for more quantity. This would result

in a lower price for access to NBN services and hence greater take-up of fibre, wireless and

satellite lead-ins. This increased take-up of NBN services will lead to greater operating

revenues and provide financial stability for the NBN.

The switchover from analogue to digital television signals will free up a significant portion of

RF spectrum. This provides the opportunity for further development and utilization of

wireless technologies (see section 3.8.1 Regulatory Policies). Successful policymaking by

opening up this freed spectrum to offers from the market will allow innovation and the

advancement of wireless technology, which would contribute to overall broadband access

options and hence competition within Australia. 4G Wireless will also benefit from lower

frequency spectrum assignment (around 700Mhz), as there is less attenuation over distance

for lower frequency signals. This will allow wireless to become even more competitive as

fewer 4G towers would have to be installed with the increased range of a single tower.

Finally, community safety and national security policies would help reduce operational

hazards. Sufficient policy making to empower police would provide protection against cyber

crime, spam and intellectual property. However, such policy making would be more difficult

to administer as it requires international involvement so cyber criminals cannot hide behind

the defence of their international borders and differing domestic cyber policies (see section

3.3 Operational Hazards).

The costing of such a regulatory reform is beyond the scope of this thesis. However, costs can

also be perceived as a benefit foregone. In the case of regulatory reform, if sufficient policies

are not set in place then the NBN will certainly become inefficient and lead to lower levels of

productivity in the economy than initially expected. Costing the productivity benefits of the

NBN is again, a subjective and difficult task. The case for efficient wireless spectrum usage

does however provide a means to cost regulatory reform as a benefit foregone. If sufficient

92

policy is not in place for the newly freed up RF spectrum, then wireless technologies will not

be given the same opportunity to develop as in other parts of the world. The cost of $3.5

billion for the NBN 3.0 would be foregone and along with the benefits. It is therefore decided

to attach the cost for the NBN 3.0 of $3.5 million to the cost of the remedial action of the

regulatory reform. Again, note that this costing is beyond the scope of this thesis and so the

dollar amount of $3.5 million will be used simply for the academic exercise of comparing

remediation actions in the cost-effectiveness analysis.

93

5.5. COST­EFFECTIVENESS ANALYSIS 

The suggested remedial actions have the effect of either reducing or increasing the likelihood

of some hazards at varying costs. The following table summarises the projected costs of each

remedial action:

Table 5.6 Remedial Action Costs

Remedial Action Cost (Billions)

Liberal’s NBN $6.5

NBN 3.0 $3.5

NBN 3.1 $46.5

NBN 3.2 $9

Domestic Caching $3.38

Regulatory Reform $3.5

Various combinations of the above remedial actions are assessed when calculating the most

cost-effective plan of action. As mentioned before, the Liberal’s NBN and NBN 3.0/1/2 are

stand-alone broadband plans as alternatives to the current NBN. Therefore, the cost of $43

billion for the current NBN will be withdrawn when assessing these remedial actions.

Domestic caching and regulatory reform provide additional costs to whatever broadband

network option is chosen. The following Table 5.7 summarises the various costs and risk

reductions of all remedial options. The last column on the right shows the cost-effectiveness

results, where the lower the value is, the better the outcome. The remedial actions have been

numbered from 1 to 5 (shown in brackets) for easier referencing in the table.

94

Table 5.7 Cost-Effectiveness Analysis of combination of remedial actions

Cost (billions)

Relative cost

Risk Ranking

Relative Risk

(Relative Cost) x

(Relative Failure)

Base Case NBN (1) $43.00 1.00 4.740 5.000 5.000

Liberal's NBN (2) $6.50 0.15 4.764 5.025 0.760

NBN 3.0 (3.0) $3.50 0.08 5.704 6.017 0.490

NBN 3.1 (3.1) $46.50 1.08 4.260 4.494 4.859

NBN 3.2 (3.2) $8.00 0.19 4.013 4.233 0.788

Domestic Caching (4) $3.38 0.08 3.912 4.127 0.324

Regulatory Reform (5) $3.50 0.08 2.933 3.094 0.252

1 + 4 $46.38 1.08 3.912 4.127 4.451

1 + 5 $46.50 1.08 2.933 3.094 3.346

1 + 4 + 5 $49.88 1.16 2.416 2.549 2.956

2 + 4 $9.88 0.23 2.254 2.378 0.546

2 + 5 $10.00 0.23 2.398 2.530 0.588

2+ 4 + 5 $13.38 0.31 1.879 1.982 0.617

3.0 + 4 $6.88 0.16 2.184 2.304 0.369

3.0 + 5 $7.00 0.16 2.331 2.459 0.400

3.0 + 4 + 5 $10.38 0.24 1.809 1.908 0.461

3.1 + 4 $49.88 1.16 2.942 3.103 3.600

3.1 + 5 $50.00 1.16 2.383 2.514 2.923

3.1 + 4 + 5 $53.38 1.24 2.015 2.126 2.639

3.2 + 4 $11.38 0.26 2.156 2.274 0.602

3.2 + 5 $11.50 0.27 2.302 2.428 0.649

3.2 + 4 + 5 $14.88 0.35 1.780 1.878 0.650

From the results in Table 5.7 above, the most cost-effective option is a combination of the

NBN 3.0 and domestic caching. The top five most cost-effective options can be ranked as:

1. NBN 3.0 and domestic caching

2. NBN 3.0 and regulatory reform

3. NBN 3.0 and domestic regulatory reform

4. Liberal’s NBN and domestic caching

5. Liberal’s NBN and regulatory reform

95

It should also be noted the combination of the NBN 3.2 plan with domestic caching and

regulatory reform results in the greatest risk reduction and lowest overall risk ranking for the

NBN Risk Model. This combination of plans requires a greater extent of spending for this risk

reduction and therefore does not result in the most cost-effective combination of remedial

actions.

96

97

6. DISCUSSION The following section interprets the results from the risk assessment, sensitivity analysis and

cot-effectiveness analysis. The significance of these results are discussed and compared in

light of the supporting theory.

6.1. SENSITIVITY ANALYSIS 

Figure 6.1 below is a graphical representation of Table 5.3, the results of the sensitivity

analysis. The figure shows the effect of a variation of inputs of risk and consequence on the

NBN Risk Model.

Figure 6.1 Sensitivity Analysis

There is a clear indication that lowering the likelihood of hazards is a high priority. The

overall risk ranking from a medium consequence (3) and almost certain likelihood (5) results

in an overall risk ranking of approximately 11.5. However, extreme consequence (5) and

moderate risk (3) results in an overall risk ranking of approximately 2.5. These results

indicate the likelihood of hazards have more of an effect on the overall risk ranking. The

NBN Risk model is therefore more sensitive to a change in the likelihood of hazards occurring

compared to a change in consequence of the failure modes. Risk management can be used to

implement a number of strategies to reduce or minimise risk.

10 

12 

14 

16 

18 

20 

Negligible  Low  Medium  High  Extreme 

Risk Ran

king 

Consequence 

Rare 

Unlikely 

Moderate 

Likely 

Almost Certain 

98

Such risk management strategies include:

• Transferring the risk to another party

• Avoiding the risk

• Reducing the negative effect of the risk

• Accepting some or all of the consequences of a particular risk.

From the sensitivity results, it is logical for the remediation options to target the reduction in

likelihood as opposed to consequence management. For this reason the remedial actions were

specifically designed to reduce the likelihood of hazards occurring rather than addressing the

negative effects or consequences of the hazards occurring.

99

6.2. COST­EFFECTIVENESS  

The summarised results in Table 5.7 from the cost-effectiveness analysis indicate a

combination of the NBN 3.0 and domestic caching would result in the most cost-effective

option. The current NBN being rolled out is the least cost–effective course of action,

presenting a combination of high risk and high costs.

The NBN 3.0, which provides wireless coverage to 98% of Australian premises, addresses

the concern for the increasing demand for mobility and wireless broadband solutions. The

NBN 3.0 plan would mitigate a large amount of the financial hazards as it focuses on private

investment and the development of wireless networks. The lower construction cost, and

resultant lower financial risk facing investors, would be more attractive to private investors

than the current NBN. The shorter rollout over 4 years would also provide quicker returns for

investors than the NBN’s 9 year rollout. Private telcos have also shown significant interest in

mobile communications over the past decade. It could be safely assumed that a wireless

broadband network would therefore be more attractive to private investors as they can realise

the competitive nature such a network would provide.

The NBN 3.0 has some inherent risks. Although wireless data rates are catching up to those

provided by fibre, some premises within the 4G tower’s range may not be privy to the same

connection speeds others achieve. As is the case today with copper networks and to a lesser

extent, fibre networks, the further a user is away from an exchange, the slower the data rates.

This is caused by the relationship between attenuation of a signal and distance. The further a

user is from the exchange, the greater the attenuation of the signal (signal gets weaker) and

data rates are reduced as a result. Fibre has the lowest attenuation rate over distance with

wireless usually most severely impacted. A number of factors contribute to the severity of

wireless’ attenuation over distance, namely environmental. Hills and valleys can act to either

weaken or strengthen the signal in those areas. Weather conditions and the nature of

surrounding surfaces such as buildings and foliage can also attenuate the signal or provide

interference through reflected signals. Fibre and copper communication mediums enjoy the

benefit of a closed-in environment, protected from external factors. It is likely that while

some premises close to a 4G tower will experience adequate data rates, there is the chance

100

that other premises will be less than satisfied with the data rates provided. Densely populated

areas will also require more towers per area, as there is a decrease in the tower’s data rates

with an increase in the number of users. The NBN 3.1 plan would address this problem by

providing FTTP, so that premises can choose fixed broadband if their wireless reception is

not suitable. The Liberal’s NBN plan also provides the option of utilising upgraded

fibre/copper services in such areas. Alternatively, the high demand for wireless connectivity

may be sufficient for the market to manage the provision of 4G Wireless alone. A purely

fixed line broadband network, either HFC or fibre, may therefore be a viable option, leaving

the market to provide the more profitable wireless network. It is usually the responsibility of

government to provide public goods, as they provide positive externalities, which are not

remunerated. In this case, fibre connectivity to 90% of Australians could be perceived as a

public good as the market cannot recover the full benefits, such as productivity increases,

through service fees.

Table 6.1 on the following page provides additional information on the percentage of risk

reduction by each remedial action.

101

Table 6.1 Percentage of Risk Reduction

Cost (billions)

Risk Ranking

(Relative Cost) x (Relative Failure)

Reduction in Risk (%)

Base Case NBN (1) $43.00 4.740 5.000 0.0% Liberal's NBN (2) $6.50 4.764 0.760 -0.5% NBN 3.0 (3.0) $3.50 5.704 0.490 -20.3% NBN 3.1 (3.1) $46.50 4.260 4.859 10.1% NBN 3.2 (3.2) $8.00 4.013 0.788 15.3% Domestic Caching (4) $3.38 3.912 0.324 17.5% Regulatory Reform (5) $3.50 2.933 0.252 38.1%

1 + 4 $46.38 3.912 4.451 17.5%

1 + 5 $46.50 2.933 3.346 38.1%

1 + 4 + 5 $49.88 2.416 2.956 49.0%

2 + 4 $9.88 2.254 0.546 52.4%

2 + 5 $10.00 2.398 0.588 49.4%

2+ 4 + 5 $13.38 1.879 0.617 60.4%

3.0 + 4 $6.88 2.184 0.369 53.9%

3.0 + 5 $7.00 2.331 0.400 50.8%

3.0 + 4 + 5 $10.38 1.809 0.461 61.8%

3.1 + 4 $49.88 2.942 3.600 37.9%

3.1 + 5 $50.00 2.383 2.923 49.7%

3.1 + 4 + 5 $53.38 2.015 2.639 57.5%

3.2 + 4 $11.38 2.156 0.602 54.5%

3.2 + 5 $11.50 2.302 0.649 51.4%

3.2 + 4 + 5 $14.88 1.780 0.650 62.4%

The NBN 3.0 as a standalone option actually results in a 20.3% increase in risk. It is the

addition of domestic caching, which reduces the overall plans risk significantly. The NBN 3.2

plan, combined with the remedial actions of domestic caching and regulatory reform, presents

the lowest overall risk ranking option (greatest risk reduction at 62.4%). However, it is not

the most cost-effective option. It should be kept in mind that a Cost-Effectiveness Analysis

simply compares relative risk reduction against cost. So a remedial option may reduce the

risk slightly but for a negligible cost will appear more cost effective than a remedial action

that reduces the risk substantially but incurs a significant cost. A remedial action’s main

purpose is to reduce risk. Taking this into consideration, the greater risk reduction by the

remedial action of the NBN 3.2, combined with domestic caching and regulatory reform, may

present a more worthwhile course of action. A cost-benefit analysis may be better suited to

102

fully assess the benefits of the suggested remedial actions. It is likely the benefits of offering

both the mobile connectivity aspect of 4G wireless along with fixed line HFC network would

surpass the benefits of a wireless or fibre only network. The NBN 3.2 addresses similar

aspects to the current NBN, but on a smaller scale. There is significant focus on providing

broadband to rural and remote areas of Australia and construction of an Australian fibre

backbone. The plan does not provide fibre to 90% of homes but would instead upgrade

existing copper networks to an HFC network for a fraction of the cost of FTTP. Another

notable remedial option is the combination of the Liberals broadband plan with domestic

caching and regulatory reform, which results in a 60.4% reduction in risk.

It must be noted that none of the proposed standalone broadband plans can offset the slow

overseas data rates. The remedial action of domestic data caching serves the purpose of

excluding the bottleneck speeds of the overseas submarine fibre from the equation. A well-

designed CDN will allow the full speed potential of any national broadband network to be

realised.

103

6.3. FINANCIAL CONCERNS 

The financial burden of the NBN project has presented two debatable questions; how much

should an NBN cost, and do we need such high speeds at high prices at this stage in time?

The question of the cost of an NBN is discussed further in the following section.

6.3.1. How much should an NBN cost? 

The NBN has attracted a lot of attention from the media and public, primarily due to the

financial burden of $43 billion it will take to construct. This thesis has placed emphasis on

analysing the financial hazards and designed remedial actions to reduce the high cost of

construction through presenting various cheaper national broadband network options.

In a country like Australia, with a large landmass that is sparsely populated, it is difficult to

determine exactly how much a customised broadband solution should cost. One way is to

utilise the market’s current valuation of the cost of a national broadband network. Appendix

A - Labour Shortages contains two methods for calculating the current value the market

places on a NBN. Both methods utilise Telstra as a case study with its dominant 65% market

share in the telecommunications industry. Method 1 uses Telstra’s share price and sales

revenues from broadband services to determine the market value of a NBN. Method 2 uses

Telstra’s current assets of Property, Plant and Equipment to extend this cost of infrastructure

from 65% market share to a national infrastructure cost and confirms Method 1’s results.

Both methods return a value of around $36 billion. This value could indicate that the current

NBN solution being rolled out nationally is approximately $7 billion overpriced. However,

this figure of $36 billion is closer to the NBN’s cost of $43 billion than the cost of the

Liberal’s broadband plan and NBN 3.0. It could be argued that the current NBN represents a

cost closer to what the current market value is for a NBN. However, if Method 1 is repeated

and the share price for Telstra is taken from July 2007, prior to the NBN plan announcement

and the Labour Party entering power (see Figure 6.2 below), then again a there would be

different value for the a national broadband network.

104

Figure 6.2 Telstra’s five-year share price, September 2006-2010 [66]

Telstra’s share price averaged over July 2007 was $4.75, giving a total share value of

approximately $59 billion. However, three years later in July 2010 the share price had

dropped to $3.20 and approximately $40 billion in shareholder value. This drop in value can

be attributed to external factors such as the global financial crisis, as indicated by a similar

drop in the ASX200 over the same period as shown below.

105

Figure 6.3 Telstra versus ASX 200, September 2006-2010 [66]

The resemblance between the ASX200 (green line) and Telstra (blue line) indicates that up

till around July 2009, Telstra’s share fluctuations were in accordance with the Australian

market. However, post July 2009 there was a decline in Telstra’s share value and this could

be attributed to an effect from the NBN announcement and project commencement. The 2007

value of Telstra’s shares would certainly offer a higher valuation of a national broadband

network, surpassing the current $43 billion price tag. Overall, irrespective of Telstra’s share

price, the above two methods of valuing what a national broadband network should cost

indicate a figure upwards of $36 billion. This however does not account for existing

telecommunication infrastructure, for example Telstra’s fibre network, which is being

incorporated into the NBN. The value of existing infrastructure being incorporated into the

NBN should be deducted from the $36 billion price estimate to ascertain the required cost of

newly constructed infrastructure to form a NBN.

106

6.4. DEMAND CONCERNS 

Pricing options by iiNet and iPrimus, as discussed in section 3.4.1 Decreased Demand,

indicate lower than initially expected pricing for fibre connections. The various fibre plan

options are repeated below:

Table 3.2 ISP’s Fibre Prices

Cost (Peak/Off-peak quota) Plans Down/Up speed iPrimus iiNet

Fibre 1 25 / 2 Mbps $49.95 (5/10GB) $49.95 (5/5GB)

Fibre 2 25 / 2 Mbps $59.95 (20/20GB) $59.95 (10/10GB)

Fibre 3 25 / 2 Mbps $119.95 (80/220GB) $69.95 (30/30GB) Fibre 4 50 / 4 Mbps $79.95 (20/20GB) $89.95 (30/30GB)

Fibre 5 50 / 4 Mbps $99.95 (65/65GB) $99.95 (50/50GB)

Fibre 6 100 / 8 Mbps $109.95 (65/65GB) $129.95 (60/60GB) Fibre 7 100 / 8 Mbps $139.95 (80GB/220GB) $159.95 (90/90GB)

The early adopters who will take up the fibre broadband plans are most likely to be heavy

users of the Internet and various online content. The attraction of the faster download speeds

fibre offers allows users to download more content in a shorter time. However, the top plan

above only offers a total of 180GB of data by iiNet and 300GB by iPrimus (although only

80GB is available during peak times). For a user with an above average connection speed this

will be the limiting factor for their online usage. It is concerning to see ISPs offering

ADSL2+ data plans with up to 1TB of download quota for $100, whereas the faster fibre

plans have considerably less data allowances included.

There is also concern that fibre users will not see much improvement over ADSL2+ speeds as

users are still susceptible to the overseas bottlenecks. Domestic caching will be required to

solve the problem of not being able to fully utilise the 100Mbps download speeds. These low

data allowances will certainly act as a limiting factor and deter even early adopters from fibre

connections. However, data plan allowances are constantly changing and the data allowances

could increase in the near future. It would be unwise for ISP’s to offer the improved speeds

that a fibre connection offers without a suitably higher data allowance to attract more demand

for the fibre connections.

107

6.5. LIMITATIONS AND RECOMMENDATIONS FOR FURTHER WORK 

The nature of the five scale ranking system used to determine the likelihood and consequence

of hazards has some limitations. The simplicity of the scale does help to reduce subjectivity

when assigning a likelihood or consequence to a hazard. However, when assessing some

hazards, such as the financial and regulatory hazards, a larger ranking scale could have lead

to a greater emphasis of the consequence of such hazards on the overall risk ranking of the

NBN. The scale was effective though in indicating that these hazards were the most

pronounced, but it is questionable as whether a larger scale could have contributed to more

accurate and dispersed results. Future studies could assign a larger 10 point scale which

would provide more variety in defining the likelihood and the consequence of hazards.

The accuracy of costing the various remedial actions could be argued. The Liberal party

presented their broadband plan with a cost breakdown for the various aspects of the network.

There could, however, be discrepancies in the costing for the various works that would not be

known unless a more in depth cost assessment was carried out. Similarly for the NBN 3.0

plan, the cost structure presented by the AAB was based on an estimate for a similar wireless

plan presented by a USA firm. A number of inaccuracies could arise from simply scaling the

costs based on land mass size and population density. Future studies could incorporate an in

depth cost model for these two broadband plans.

The costing of the regulatory reform was purely an academic exercise in order to be able to

assess its validity in the cost-effectiveness analysis. The domestic caching remedial action

was based on an estimate of the number and cost of building data centres in strategic

locations around the country. It would be advisable for future work on the topic to include

study into Australia’s current CDN situation and whether certain regions may require more or

less data capacity in the form of data centres.

The NBN Risk Model is designed to account for the perceived likelihoods of hazards to the

NBN occurring and the relative consequences of those hazards. For the purpose of comparing

the remedial actions in the cost-effectiveness, it is merely the risks that can be accounted for

108

and how certain remedial actions present less risk (benefits) over other options. This model

however, cannot fully account for all benefits that some remedial actions offer. For instance,

the NBN 3.2 provides the benefit of both wireless and fixed HFC connectivity options, but

these benefits are not realised to the full extent through a simple risk model. A cost-benefit

analysis would be better suited to assessing the benefits of the NBN 3.2 combined with

domestic caching and regulatory reform, the lowest risk scenario. A cost-benefit analysis

would most likely find that the benefits (risk reduction) are under estimated by the NBN Risk

Model. Future work should look at applying a cost-benefit analysis to the remedial actions.

Finally, the nature of the cost-effectiveness analysis is to deduce which remedial action

reduces risk for the lowest cost. The method does fall short when a small reduction in risk is

accomplished for a negligible cost. This option may come out the most cost-effective but will

have missed the main objective of a remedial action; to reduce risk. A cost-benefit analysis in

this case may be better suited as it would account for intangible benefits and costs, which

would otherwise be missed by a cost-effectiveness analysis. Alternatively, a threshold can be

established for the minimal risk reduction that a remedial action can contribute. If a remedial

action does not reduce risk sufficiently passed the threshold, then it is disregarded as a viable

option.

109

7. CONCLUSION AND RECOMMENDATIONS The risk assessment identified 59 hazards under the 6 main failure modes of: Construction,

Operation, Demand, Network, Technology, Financing and Regulation. Six remedial actions

were investigated to address the key hazards. A cost-effectiveness analysis was then used to

determine the most cost-effective combination of remedial actions to reduce risk. All stated

goals of the risk assessment were successfully completed.

The construction hazards present in the NBN were found to be most effected by the risk of a

shortage of ICT labour, latent grounds causing an increase in construction costs and time, and

scope creep leading to greater than 90% of Australian premises covered by fibre connectivity.

The construction failure mode presents a relatively low risk compared to the other failure

modes. As a result, no remedial actions were designed to address the construction phase of

the project.

Operational hazards highlight the risk of cyber crime, spam and intellectual property and to a

lesser extent the affect ISP’s contention ratios would have on the ability for fibre connections

to reach the claimed 100Mbps. The lifespan of fibre optic cable was also discussed and found

in general to have a sufficient operational life of at least 40 years. Suitable maintenance

procedures would also ensure that the fibre network remained operational for longer.

Demand hazards addressed both issues of increased and decreased demand for the NBN.

Decreased demand may eventuate due to fibre technology being superseded, for instance by

wireless, or through a decreased uptake of fibre connections due to high prices charged by the

Wholesaler and/or ISPs. Increased demand for high-speed broadband was deemed likely due

to increasing Internet traffic and the growing demand for online video and IPTV services.

The increased demand hazard was assigned a lower probability of failure in comparison to

decreased demand due to fibre’s capacity to handle higher data loads.

110

Network hazards are affected by the demand for NBN services and also the choices in design

with regards to other aspects of the network. The overseas bottleneck issue is of serious

concern as 70% of Australian Internet traffic is directed towards accessing websites and

servers in the USA. The shear distance and design bottleneck of these undersea fibre optic

cables leads to slow data rates. If this hazard is not addressed the full potential of the NBN

high-speed network will never be fully realised.

Technological hazards identified the concern that fibre could be superseded as technology

advances rapidly. This is attributed to the increasing demand for mobile connectivity which is

being helped along by the progress of 4G and future generation wireless technologies.

Financial hazards are an obvious risk due to the $43 billion cost of construction of the NBN,

Australia’s largest infrastructure project. Decreased demand for fibre connections again

presents itself as a hazard as operating revenues for the NBN are dependent on the take-up of

fibre lead-ins. The lack of private investment is also of serious concern, as the government’s

financing vehicles will find it difficult to cover the full cost of the project.

The most significant contributors to the overall risk ranking are the Regulatory hazards,

caused by political sensitivity and lack of regulation surrounding the NBN Co and

telecommunication implementation policies. Regulation of NBN Co, the RF spectrum,

consumer protection through competition policy and national security will lower the project’s

overall market risk and lead to an increase in investor confidence which relates back to the

financial hazards.

The remedial actions of the Liberal Party’s broadband plan, NBN 3.0/3.1/3.2, Domestic

caching and Regulatory reform are designed to address and reduce the likelihood of the key

hazards occurring. The most cost-effective broadband network option was the NBN 3.0 plan

to provide high speed broadband through last mile 4G wireless connectivity to 98% of

Australian premises. When combined with the remedial action of domestic caching, it

presented the most cost-effective plan, reducing risk by 61.8%.

111

The NBN 3.2 plan, combined with the remedial actions of domestic caching and regulatory

reform, presents the lowest overall risk ranking option, reducing risk by 62.4%. The greater

risk reduction by the NBN 3.2 remedial action compared to an increase in risk by the NBN

3.0, may present the NBN 3.2 as a more worthwhile course of action. A cost-benefit analysis

may be better suited to fully assess the benefits of the suggested remedial actions. It is

possible that the benefits of offering both the mobile connectivity aspect of 4G wireless

connections along with fixed line HFC network would surpass the benefits of a wireless or

fibre only network. Future studies should look at using the cost-benefit analysis method to

better assess the benefits that the two styles of fixed and wireless connectivity would offer

over a choice of only one connection type.

It is also recommended that pricing for the current NBN should be reviewed and possibly

lowered in order to encourage take-up of the fibre connections. This will allow more users to

initially benefit from the NBN and encourage greater take-up by other Australians as

consumer confidence in the network grows. Current pricing for fibre plans is more than

double the price of an ADSL2+ broadband plan with similar data allowance. There is still the

risk that early fibre users will not be able to utilise the higher data rates until the overseas

bottleneck issues are addressed. A well-designed CDN is required to address these slow

overseas data rate concerns and to equip the NBN with the means to deal with infrastructure

outages and equipment failures.

112

113

APPENDICES 

APPENDIX A ­ LABOUR SHORTAGES 

Table A.1 Forecasted BAU ICT Labour vs. NBN Demand for Labour

Year ABS Data

Expected Workforce

Forecast BAU

NBN Requirement

Total ICT Labour Force

Required

Resource Gap

1996 31,100 30,259 1997 34,400 29,541 1998 28,800 28,840 1999 29,900 28,156 2000 25,500 27,488 2001 23,800 26,835 2002 24,900 26,199 2003 26,600 25,577 2004 23,300 24,970 2005 22,300 24,378 2006 25,000 23,800 2007 26,900 23,235 2008 20,000 20,000 22,684 2009 20,000 22,684 2010 20,000 21,620 21,620 1,620 2011 20,000 21,107 140 21,247 1,247 2012 20,000 20,606 8,680 29,287 9,287 2013 20,000 20,117 14,769 34,887 14,887 2014 20,000 19,640 18,386 38,027 18,027 2015 20,000 19,174 18,386 37,561 17,561 2016 20,000 18,719 18,386 37,106 17,106 2017 20,000 18,275 18,386 36,662 16,662 2018 20,000 17,842 18,206 36,048 16,048 2019 20,000 17,418 7,234 24,653 4,653

114

APPENDIX B ­ TELSTRA CASE STUDY 

Telstra can be used as a case study to estimate the current value of what the market values a

national broadband network. Two different methods are used below.

Method 1  

Method 1 uses Telstra’s share price, prior to the effect of the NBN Co. deal announcement in

July 2010, to calculate the market value of the business. Telstra’s sales revenue figures are

then utilised to calculate the percentage of business activity attributed to broadband products.

This then gives a percentage of their total value attributed to broadband activities.

Figure B.1 Telstra’s Revenue and product profitability [67]

All relevant data service revenues were summed from the above table, while other services

such as PSTN products were excluded. This summed amount was then used in conjunction

with the total sales revenue to calculate the percentage of Telstra’s operations that are

broadband relevant (data services).

115

Total Data Service Revenue ÷ Total Sales Revenue x 100%

= $14.465 ÷ $24.183 x 100% = 59.81%

This figure was then used in conjunction with Telstra’s share price averaged over June/July

($3.20), number of shares (12 443 074 357) and 65% market share to calculate the overall

market value of a NBN.

NBN Market value = No. of Telstra Shares x Total Data Service Revenue % x Market Share

= 12 443 074 357 x $3.20 x 59.81% ÷ 65%

= $36.639 billion

Telstra can also be valued pre-Labour government using the above method with a share price

of $4.75 (July 2007) and 12.407 billion shares on offer against the July 2010 price of $3.20

giving:

2010 = 12.443bn x $3.20 = $39.818 billion

2007 = 12.407bn x $4.75 = $58.933 billion

We can see a significant drop in capital and the value of Telstra from July 2007 to 2010.

Method 2 

From Telstra’s 2010 full year financial results [67], assets including Property, Plant &

Equipment are valued at $22.894 billion. Using an expected market share of 65% this would

lead to a total market value of a broadband network equating to:

Total NBN market value of infrastructure = $22.894 ÷ 65% = $35.221 billion

This $35 billion worth of broadband infrastructure is consistent with Method 1 when a share

price of $3.20 (June/July 2010) is used, which gives $36.639 billion. It can be concluded that

the market value of the current NBN is approximately $36 billion.

116

APPENDIX C – COMPANION DISK (NBN RISK MODEL) 

The companion disk contains the following files:

• NBN Risk Model (Excel)

• NBN Fault Tree Analysis (Visio)

• ITEE Expo presentation (Powerpoint)

• ITEE Expo poster (Powerpoint)

• Progress seminar presentation slides (Powerpoint)

• Research Proposal (PDF)

• Research Material (Various file types)

117

  REFERENCES [1]  Telstra. (2008, Next Generation Cable Systems ‐ Endeavour. Telstra Wholesale.  

[2]  C. Chan,  et al.,  "Public  Infrastructure Financing: An  International Perspective," Productivity 

Commission Staff Working PaperMarch 2009. 

[3]  M.  G.  Stewart  and  R.  E.  Melchers,  Probabilistic  risk  assessment  of  engineering  systems. 

London ; New York: Chapman & Hall, 1997. 

[4]  S. G. Vick and A. S. o. C. Engineers, Degrees of belief : subjective probability and engineering 

judgment. Reston, Va.: ASCE Press, 2002. 

[5]  M. Modarres,  et al., Reliability engineering and  risk analysis  : a practical guide. New York: 

Marcel Dekker, 1999. 

[6]  E.  a.  S.  International  Symposium  on  Risk,  Failure  Minimisation  and  Analysis  Pilanesberg, 

South Africa) and R. K. Penny, Risk, economy and safety, failure minimisation and analysis : 

failures  '96  :  proceedings  of  the  Second  International  Symposium  on  Risk,  Economy  and 

Safety,  Failure  Minimisation  and  Analysis,  Pilanesberg,  South  Africa,  22‐26  July  1996. 

Rotterdam: A.A. Balkema, 1996. 

[7]  Standards Australia, "AS IEC 61025‐2008 Fault Tree Analysis (FTA)," ed, 2008. 

[8]  E.  Zio,  An  introduction  to  the  basics  of  reliability  and  risk  analysis.  Singapore:  World 

Scientific, 2007. 

[9]  OECD.  (2009,  OECD  Communications  Outlook  2009.  Information  and  Communication 

Technologies, 350.  

[10]  OECD. (2008, OECD Information Technology Outlook 2008. Information and Communication 

Technologies, 350.  

[11]  P. Lindroos and M. Pinkhasov, "Broadband Driving Growth: Policy Response," O. f. E. C.‐o. a. 

Development, Ed., ed, 2003. 

[12]  Evans  &  Peck,  "Capital  Budgets  and  Resource  Gap  Analysis  for  FTTP  Access  Network  ‐ 

Preliminary Study," 18 January 2010. 

[13]  CCIQ. (2005, Skills and Labour Shortages: A Critical Issue for Queensland Business. Chamber 

of Commerce & Industry Queensland.  

[14]  Australian  Bureau  of  Statistics.  8126.0  ‐  Information  and  Communication  Technology 

[Online].  

[15]  M. Bingemann and A. Hepworth,  "Wage blowot  threat  to NBN rollout," The Australian, 10 

September 2010. 

118

[16]  K.  Thakore.  (2010,  2  June).  How  Should  the  Project  Manager  Deal  with  Scope  Creep? 

Available:  http://www.projectsmart.co.uk/how‐should‐the‐project‐manager‐deal‐with‐

scope‐creep.html 

[17]  McKinsey  &  Company  and  KPMG,  "National  Broadband  Network  Implementation  Study," 

2010. 

[18]  National  Broadband  Network.  (2010,  9  September).  How  will  it  benefit  the  Australian 

economy?  Available:  http://www.nbn.gov.au/content/how‐will‐it‐benefit‐australian‐

economy 

[19]  ServiceSat.  (2010, 11 October).  Internet Speeds and Contention Ratios Explained. Available: 

http://www.servicesat.net/internetspeedsan.html 

[20]  NBN  Co.  (2009,  What  is  Optical  Fibre?  NBN  Co.  Fact  Sheet.  Available: 

http://www.nbnco.com.au/wps/wcm/connect/d09d300043a207508ddbfdc5166da634/NBN

Co_FactSheet_Fibre.pdf?MOD=AJPERES 

[21]  Sterlite.  (2006,  Optical  Fibre  Lifetime  Calculation.  Available: 

http://www.sterlitetechnologies.com/pdf/KnowledgeCenter/AN0001%20‐

%20Optical%20Fiber%20Lifetime.pdf 

[22]  C. Koch. (2007, June 11, 2007). How You Can Fight Cybercrime. CIO.com.  

[23]  A.  C.  Trembly,  "Spam  is  a  productivity  killer," National Underwriter,  vol.  107,  8 December 

2003. 

[24]  "Study reveals spam's true cost to global productivity," Precision Marketing, May 27 2005. 

[25]  K. Dearne, "Australia to sign global traty to combat cybercrime," in The Australian, ed, 2010. 

[26]  N. Cochrane. (2009, 2 September). NBN cost debate picks up steam. CRN, 3.  

[27]  M.  Motta,  Competition  policy  :  theory  and  practice.  Cambridge  ;  New  York  ::  Cambridge 

University Press, 2004. 

[28]  M. Bingemann, "No return on NBN  for 'up to 30 years'," The Australian, 16 April 2010. 

[29]  OECD,  "The  Future  Digital  Economy:  Digital  content  creation,  distribution  and  access," 

Committee for Information, Computer and Communications Policy, p. 84, 22 May 2006. 

[30]  E. Rodgers, "Big gig: NBN to be 10 times faster," ABC News, 12 August 2010. 

[31]  Cisco, "CiscoVisual Networking Index: Forecast and Methodology, 2009 ‐2014," ed, 2010, p. 

17. 

[32]  M. Alder and K. Kilraine, "Leaders of Laggards? Australia's Broadband Future," KPMG, p. 56, 

2004. 

[33]  M. Kaiser, "NBN Co. Presentation," in Western Corridor Luncheon, 2010. 

119

[34]  J.  Hibbard,  et  al.,  "International  Internet  Connectivity  and  its  Impact  on  Australia," 

Department of Communication Information Technology and the Arts, 2004. 

[35]  J.  Gans.  (2010,  The  overseas  broadband  bottleneck.  Core  Economics.  Available: 

http://economics.com.au/?p=6073 

[36]  Wikipedia.  (2010,  List  of  international  submarine  communications  cables.  Available: 

http://en.wikipedia.org/wiki/List_of_international_submarine_communications_cables 

[37]  Telstra.  (2008,  2  September).  Telstra's  new  submarine  cable  lands  in  Sydney.  Available: 

http://www.telstraenterprise.com/newsevents/news/Pages/Telstra’snewsubmarinecablelan

dsinSydney.aspx 

[38]  T. Clarke. (2010, NBN 101: Floating the Submarine cable question. Computerworld. Available: 

http://www.computerworld.com.au/article/358578/nbn_101_floating_submarine_cable_qu

estion/ 

[39]  Pacific  Fibre.  (2010,  2  September).  Why  is  Pacific  Fibre  needed?  Available: 

www.pacificfibre.net/why.php 

[40]  L. K. Moore, "Wireless Technology and Spectrum Demand," CRS Report for Congress, 2006. 

[41]  Rysavy_Research,  "EDGE,  HSPA  and  LTE  ‐  The  Mobile  Broadband  Advantage,"  Rysavy 

Research and 3G Americas, September 2007. 

[42]  Wikipedia. (2009, 6 September). 3G. Available: http://en.wikipedia.org/wiki/3G#Evolution 

[43]  Wikipedia. (2010, 6 September). 1G. Available: http://en.wikipedia.org/wiki/1G 

[44]  Wikipedia.  (2010,  6  September).  Enhanced  Data  Rates  for  GSM  Evolution.  Available: 

http://en.wikipedia.org/wiki/Enhanced_Data_Rates_for_GSM_Evolution 

[45]  Wikipedia. (2010, 6 September). 3GPP. Available: http://en.wikipedia.org/wiki/3GPP 

[46]  S.  Rodriguez,  et  al.,  "4G  CMOS  Nanometer  Receivers  for Mobile  Systems:  Challenges  and 

Solutions," International Symposium on Signals, Circuits and Systems, pp. 1‐4, 2009. 

[47]  Australian Bureau of Statistics, "Internet Activity, Australia," ed. Canberra, 2009. 

[48]  F. K. Crundwell, "Financing Engineering Projects," ed London: Springer London, 2008, p. 531. 

[49]  A. Merna and C. Njiru, Financing infrastructure projects. London: Thomas Telford Ltd, 2009. 

[50]  M. Bingemann, "Brisbane plans own fibre network," The Australian, 15 October 2010. 

[51]  B.  Grubb.  (2009,  21  September).  Telcos  call  for  NBN  ownership  cap.  iTnews.  Available: 

http://www.itnews.com.au/Tools/Print.aspx?CIID=155063 

[52]  Economist.com.  (2010,  The Difference  Engine:  Bigger  than Wi‐Fi The  Economist.  Available: 

http://www.economist.com/blogs/babbage/2010/09/white‐space_wireless/ 

[53]  S. Conroy, "National Broadband Network: Regulatory Reform for 21st Century Broadband," 

presented at the Discussion Paper, 2009. 

120

[54]  J. Campbell, "Broadband big waste risk," Herald Sun, April 18 2010. 

[55]  S.  Conroy,  "Agreement  between  NBN  Co  and  Telstra  on  the  rollout  of  the  National 

Broadband Network," Department of Brodband, Communications and the Digitial Economy, 

20 June 2010. 

[56]  Computerworld,  "NBN  3.0  from  the  Alliance  for  Affordable  Broadband:  Open  Letter," 

Computerworld Australia, 31 August 2010. 

[57]  National_Broadband_Network.  (2010,  3  September).  Fixing  regional  backbone  blackspots. 

Available: http://www.nbn.gov.au/content/fixing‐regional‐backbone‐blackspots 

[58]  National_Broadband_Network.  (2010,  3  September).  Geographical  Rollout.  Available: 

http://www.nbn.gov.au/content/geographical‐rollout#australia 

[59]  D. Williams, et al., "ACARP C8039 ‐ Risk Assessment & Cost Effectiveness Analysis," ed, 2001. 

[60]  Liberal  Party  of  Australia.  (2010,  The  Coalition's  plan  for  real  action  on  Broadband  and 

Telecommunications.  Available: 

http://www.liberal.org.au/~/media/Files/Policies%20and%20Media/Infrastructure/Broadba

nd%20and%20Telecommunications%20Policy.ashx 

[61]  Wikipedia.  (2010,  27  September).  Content  delivery  network.  Available: 

http://en.wikipedia.org/wiki/Content_delivery_network 

[62]  T. Clarke. (2010, NextDC buys up Melbourne and Brisbane data centre land. Computerworld. 

Available: 

http://www.computerworld.com.au/article/351903/nextdc_buys_up_melbourne_brisbane_

data_centre_land/ 

[63]  Computerworld.  (2010,  Top  10  new  data  centre  considerations.  Available: 

http://www.computerworld.com.au/article/print/343890/top_10_new_data_centre_consid

erations/ 

[64]  F.  Foo.  (2010,  Green  light  for  $1bn  Canberra  data  centre.  The  Australian.  Available: 

http://www.theaustralian.com.au/australian‐it/green‐light‐for‐1bn‐canberra‐data‐

centre/story‐e6frgakx‐1225856083935 

[65]  B. Winterford. (2010, 27 September). Telstra reveals homegrown content delivery network. 

iTnews.  Available:  http://www.itnews.com.au/News/213885,telstra‐reveals‐homegrown‐

content‐delivery‐network.aspx 

[66]  (2010,  Telstra  Coporation  Limited  Share  Price.  Yahoo!7  Finance.  Available: 

http://au.finance.yahoo.com/q/bc?t=5y&s=TLS.AX&l=on&z=l&q=l&c=&c=%5EAXJO 

[67]  (2010, Annual Report Telstra. Available: www.telstra.com.au/abouttelstra/investor