Minutes of 228 SEAC Meeting Date 23/07/2015 - Enviroment ...

52
Page 1 of 52 Minutes of 228 th SEAC Meeting Date 23/07/2015 The 228 th meeting of SEAC was held in Directorate of Environment, U.P. on 23/07/2015. Following members were present in the meeting along with Secretary, SEAC: 1. Dr. M. S. Khan Chairman 2. Dr. S.N. Singh Member 3. Dr. Asheesh Kumar Singh Member 4. Shri S.C. Bramhchari Member 5. Shri Surendra Singh Secretary The Chairman welcomed the members to the 228 th SEAC meeting. The minutes of 227 th SEAC meeting dated 11/07/2015 were confirmed. The Members of SEAC unanimously taken following decisions on the agenda points discussed: 1. Industrial Project at Plont No-A-006, Sector-87, Noida. Sri Navin Rajvanshi, Sr. GM,(F&A), Kent RO System Pvt. Ltd., A-2, Sector-59, Noda. File No. 2549/DD-Y The project proponent did not appear. The committee discussed and deliberated that project fie should be closed and should be opened only after request from the project proponent. The file shall not be treated as pending at SEIAA/SEAC. 2. Group Housing Project "Express Eternity" at Plot No-GH-06A, Sector-01, Greater Noida, U.P. M/s Express Projects Pvt. Ltd. Sri S. Raghavan, VP, Express Highway, 810, Surya Kiran Building,Cannaught Place, New Delhi. File No. 2552/SPO-V The committee noted that an application dated 18/02/2014 was made by the project proponent for environmental clearance of Group Housing Project "Express Eternity" at Plot No. GH-06A, Sector-01, Greater Noida, U.P. M/s Express Projects Pvt. Ltd. A presentation was made by Shri Rajeev Pandey, authorized representative of project proponent alongwith their consultant M/s Grass Roots Research & Creation India (P) Ltd. The proponent, through the documents submitted and the presentation made, informed the committee that:- 1. The environmental clearance is sought for Group Housing Project "Express Eternity" at Plot No-GH-06A, Sector-01, Greater Noida, U.P. M/s Express Projects Pvt. Ltd. 2. Area details of the project is as follows: S. No. Particulars Area (in m 2 ) Percentage (in %) 1. Plot Area 23,912.5 100 2. Permissible Ground Coverage (@ 35% of the plot area) 8,369.375 3. Proposed Ground Coverage (@ 23.81% of the plot area) 5,692.658 23.81 4. Total Permissible FAR (@ 3.5 of the plot area) (a + b) a. Permissible FAR (@ 2.75 of plot area) 83,693.750 65,759.375

Transcript of Minutes of 228 SEAC Meeting Date 23/07/2015 - Enviroment ...

Page 1 of 52

Minutes of 228th

SEAC Meeting Date 23/07/2015

The 228th

meeting of SEAC was held in Directorate of Environment, U.P. on

23/07/2015. Following members were present in the meeting along with Secretary,

SEAC:

1. Dr. M. S. Khan Chairman

2. Dr. S.N. Singh Member

3. Dr. Asheesh Kumar Singh Member

4. Shri S.C. Bramhchari Member

5. Shri Surendra Singh Secretary

The Chairman welcomed the members to the 228th

SEAC meeting.

The minutes of 227th SEAC meeting dated 11/07/2015 were confirmed.

The Members of SEAC unanimously taken following decisions on the agenda

points discussed:

1. Industrial Project at Plont No-A-006, Sector-87, Noida. Sri Navin Rajvanshi, Sr.

GM,(F&A), Kent RO System Pvt. Ltd., A-2, Sector-59, Noda. File No. 2549/DD-Y

The project proponent did not appear. The committee discussed and deliberated that

project fie should be closed and should be opened only after request from the project proponent. The file shall not be treated as pending at SEIAA/SEAC.

2. Group Housing Project "Express Eternity" at Plot No-GH-06A, Sector-01, Greater

Noida, U.P. M/s Express Projects Pvt. Ltd. Sri S. Raghavan, VP, Express Highway,

810, Surya Kiran Building,Cannaught Place, New Delhi. File No. 2552/SPO-V

The committee noted that an application dated 18/02/2014 was made by the project

proponent for environmental clearance of Group Housing Project "Express Eternity" at Plot

No. GH-06A, Sector-01, Greater Noida, U.P. M/s Express Projects Pvt. Ltd.

A presentation was made by Shri Rajeev Pandey, authorized representative of project

proponent alongwith their consultant M/s Grass Roots Research & Creation India (P) Ltd.

The proponent, through the documents submitted and the presentation made, informed the

committee that:-

1. The environmental clearance is sought for Group Housing Project "Express Eternity" at

Plot No-GH-06A, Sector-01, Greater Noida, U.P. M/s Express Projects Pvt. Ltd.

2. Area details of the project is as follows:

S.

No.

Particulars Area (in m2

) Percentage

(in %)

1. Plot Area 23,912.5 100

2. Permissible Ground Coverage (@ 35% of the plot area) 8,369.375

3. Proposed Ground Coverage (@ 23.81% of the plot area) 5,692.658 23.81

4. Total Permissible FAR (@ 3.5 of the plot area) (a + b)

a. Permissible FAR (@ 2.75 of plot area)

83,693.750

65,759.375

Minutes of 228th

SEAC Meeting Dated 23/07/2015

Page 2 of 52

b. Purchasable FAR (@ 0.75 of plot area) 17,934.375

5. Proposed FAR (@ 3.49 of the plot area)

a. Residential FAR

b. Commercial FAR

83,689.975

82,855.41

834.565

6. Ancillary Area (@ 15% of the permissible FAR) 12,554.063

7 Proposed Ancillary Area (@ 14.99% of the permissible FAR) 12,552.55

8. Built Up Area 1,28,630.55

9. Open Area 18,219.842

10. Green Area (@ 51.95% of the open area) 9,464.601 39.58

11. Basement area (1 No.) 20,152.675

12. Stilt Parking Area 12,235.35

13. Surface Parking area 2,203.5 9.21

14. Road & remaining open area 6,551.741 27.4

15. Maximum Height of Building (till Mumty Terrace) 88.8 m

3. Built-up area calculation details is as follows:

S. No. Particulars Area (in m

2

)

1. Proposed FAR 83,689.975

2. Ancillary Area 12,552.550

3. Basement Area 20,152.675

4. Stilt Parking Area 12,235.35

Built-up Area 1,28,630.55

4. Salient features details of the project is as follows:

S.NO. PROJECT FEATURES DESCRIPTION

1. Plot Area 23,912.5 m2

2. Built Up Area 1,28,630.55 m2

3. Proposed Ground Coverage 5,692.658 m2

4. Proposed FAR 83,689.975 m2

5. Basement Area 20,152.675 m2

6. Green Area 9,464.601 m2

7. Height of the building 88.8 m (till Mumty Terrace)

8. Estimated Population

Total no. of D.U.

5,758 Nos. (5,008 General, Staff 250 & Visitors 500)

1,113

9. Estimated Water Requirement

Construction Phase

Operation Phase

643 ML (Agency: Treated water from STP of GNIDA)

489 KLD (Fresh water = 332 KLD) (Agency: GNIDA)

10. Estimated Wastewater Generation 404 KLD

11. Power Demand

Power Back-up

4,490 kVA

2,520 kVA (4*630 KVA)

12. Agency of Power Noida Power Corporation Limited (NPCL)

13. No. of RWH Structures 3 Pits and 3 Tanks

14. Solid Waste Generation 2,662 kg/day

15. Parking Facilities Required

Proposed

As per MoEF norms: 846 ECS As per Greater Noida Bye Laws : 1,046 ECS

1,053 ECS

5. Ground coverage details are as follows:

SI. No Tower Dwelling

Units

Ancillary Area

(in m2

)

Ground Coverage

(in m2

)

Height

1. A 98 1,061.450 392.392 S+25

2. B 99 1,065.390 392.392 S+25

3. C 99 1,072.970 392.392 S+26

4. D 99 1,072.970 392.392 S+26

5. E 99 1,072.970 392.392 S+26

6. F 99 1,023.728 453.809 S+26

7. G 104 1,052.851 453.809 S+26

8. H 104 1,105.186 392.392 S+26

9. I 104 1,105.186 392.392 S+26

10. J 104 1,105.186 392.392 S+26

11. K 104 1,105.186 392.392 S+26

Minutes of 228th

SEAC Meeting Dated 23/07/2015

Page 3 of 52

12. Community Building 369.977 369.977

13. Commercial - 834.565

14. U.G Water Tank/STP 312.500

15. Misc. Area 21.970

Total 1,113 12,552.55 m2

5,692.658 m2

6. Population details are as follows:

S. No. Unit Type Nos. PPU Total Population

1. Residents 1,113 4.5 5008.5 say 5008

2. Staff 250

3. Visitors 500

Grand Total 5,758

7. Water requirement details of the project are as follows:

S.

No.

Description Area

(in m2

)

Total

Occupancy

Rate of water

demand (lpcd)

Total Water

Requirement

(KLD)

A. Domestic Water

A)Residential Development

• Residents 5008 86 430.688

• Visitors 500 15 7.5

• Staff 250 30 7.5

Total domestic water demand (A) 445.688 KLD

Say 446 KLD

B. Horticulture and Landscape

development 9,464.601 m

2

1 lt./sqm/day 9.4 or 9 KLD

C. Filter Backwash 10

D. Make-up water for swimming

pool

10

E. DG Sets Cooling (4 X 630

kVA)*

0.9 lt./KVA/hr 13.61

Grand Total (A+B+C+D+E) = 488.61 KLD Say 489 KLD

8. Waste water calculation details are as follows:

Domestic Water Requirement 446 KLD

• Fresh (@ 70% of domestic) 312.2 or 312 KLD

• Flushing (@ 30% of domestic) 133.8 KLD say 134 KLD

Wastewater Generated

(@ 80% fresh + 100% flushing +100% filter back wash +

100% make up water for swimming pool)

249.6+134+10+10= 403.6 or 404 KLD

9. Water and waste water management are as follows:

SOURCE MANAGEMENT / MITIGATIVE MEASURES

A) DURING CONSTRUCTION PHASE

1. Agency: Treated water from STP of GNIDA

2. Approx. Water Demand: 643 ML

3. Wastewater Generation: 4.5 KLD

(@ 80% of domestic water requirement of

construction workers)

1. The site drainage is planned in such a way that there is

no accumulation of wastewater within the project

premises or in the vicinity of the site.

2. Mobile type sulabh shauchalayas to be provided for

construction laborers.

B) DURING OPERATION PHASE

1. Agency: GNIDA

2. Total Water Demand = 489 KLD

Domestic water = 446 KLD

Horticulture = 9 KLD

3. Wastewater Generation = 404 KLD

1. STP of 20% higher capacity is proposed to maximum

usable treated wastewater & rest of wastewater is

directly discharge to CSTP.

2. Treated sewage to be used for Horticulture, DG cooling

& flushing.

3. Use of Water efficient fixtures to conserve water.

10. Solid waste generation details are as follows:

S. No. Category Waste Generated

(kg per capita per day)

Waste generated (kg/day)

1. Residents 5,008 @ 0.50 kg/day 2,504

2. Staff 250 @ 0.25 kg/day 62.5

3. Visitors 500 @ 0.15 kg/day 75

4. Landscape waste @ 0.2 kg/acre/day 0.466

Minutes of 228th

SEAC Meeting Dated 23/07/2015

Page 4 of 52

(2.33acres)

5. STP Sludge 19.2

TOTAL SOLID WASTE GENERATED 2,661.166 kg/day

Say 2,662 kg/day

11. The project proposals are covered under category 8"a" of EIA Notification, 2006.

The committee discussed the matter and directed the project proponent to submit

following information:

1. Physical features within 30 m of the project sites with their ownership.

2. Area details showing proposed uses as residential, commercial, parks, parking,

roads, other services, facilities of the project also in percentage.

3. Location of approach road alongwith width should be shown on map.

4. Set back on all sides. 5. Internal road width with RoW/carriage way/cross section of all roads. Also

showing drainage, plantation etc. 6. Details of community facilities as per bye-laws.

7. 03 m peripheral green shall be provided around the project inside the project boundary.

8. Copy of all approved layout plan/maps/services plans/letters submitted to Development Authority.

9. The structure design certificate by qualified structure engineer should be

submitted. The structural design certificate should preferably be vetted by

IITs/CBRI. Provision of alarm system, to timely notify the employees/residents,

in case of occurrence of earthquake/other natural disasters/fire should be

provided.

10. Provision should be made for underground water tank for storing water for

distribution/supply to resident. Plans with details/dimensions should be

submitted.

11. Dimensions of swimming pool with commensurate water requirement and

requirement of makeup water.

12. Details of area required for installation and functioning of Organic waste

converter. Consumption rate within the premises should be submitted. Plan for

use of manure outside the premises, if reproduction of manure is more than its consumption within the premises.

13. Environmental Corporate Responsibility (ECR) plan along with budgetary provision amounting to 2% of project cost shall be prepared and approved by

Board of Directors of the company. A copy of resolution as above shall be submitted to the authority alongwith list of beneficiaries with their mobile

nos./address. 14. Revised parking plan.

15. Fire NOC to be submitted.

16. Load calculation for solar provisions as proposed by the proponent with area

requirement for the purposes.

The project proponent submitted replies to the queries alongwith soft copy through

letter dated 23/07/2015 in the meeting. The committee noted that the project proponent has submitted calculation details of solar demand/area required, revised basement parking plan

showing entry and exit with colour codes, location of kaccha pond according to slope of the area, provision of chute system, community facility details alongwith plan, evacuation route

plan with floor/basement /stilt evacuation plan, structural stability certificate, physical features within 30 m of the project alongwith ownership, area chart with their proposed uses

as residential commercial, community, green area, road area and open area, approach road

Minutes of 228th

SEAC Meeting Dated 23/07/2015

Page 5 of 52

plan, copy of plan submissions to GNIDA Authority, Fire NOC, section details of all roads

and landscape plan.

The committee discussed the matter and recommended grant of environmental clearance on the project proposals alongwith general conditions as earlier prescribed by the

authority for construction project and following specific conditions:

1. Provision of setback on all sides should be made as per GNIDA bye-laws.

2. Municipal solid waste shall be disposed/managed as per Municipal Solid Waste (Management and Handling) Rules, 2000 (as amended).

3. 03 m peripheral green shall be provided around the project inside the project boundary. Add Astonia in list of trees.

4. 15% area of the total plot area shall be compulsorily made available for the green belt development including the peripheral green belt.

5. Project falling with in 10 Km. area of Wild Life Sanctuary is to obtain a clearance from National Board Wild Life (NBWL) even if the eco- sensitive zone is not earmarked.

6. Criteria/ norms provided by competent Authority regarding the seismic zone be followed for construction work. Provision of alarm system, to timely notify the

residents, in case of occurrence of earthquake/other natural disasters/fire should be

provided. A well defined evacuation plan should also be prepared and regular mock

drills should be arranged for the residents. Rise of stairs should be constructed in a way,

so that it should provide smooth movement.

7. For the treatment for total sewage, a full-fledged STP is to be provided with 20% more

capacity than waste water generated during operation phase.100% waste water is to be

treated in captive STP conforming to prescribed standards of receiving body for

designated use. Monitoring of STP to be done daily till its stabilization.

8. Dual plumbing should be adopted. Recycling of water as proposed shall be undertaken

with regular testing and monitoring of treated water.

9. Dedicated power supply for STPs is to be ensured during operation. Sludge of STP is to be used in-house as manure and surplus manure should be managed by giving it to end

users. STP shall be suitably located nearest to back side boundary with shortest out let. Operation and the maintenance cost of the STP shall also be informed along with the

compliance of the E-waste and municipal solid waste disposal. 10. Environmental Corporate Responsibility (ECR) plan along with budgetary provision

amounting to 2% of total project cost shall be prepared and approved by Board of Directors of the company. A copy of resolution as above shall be submitted to the

authority. A list of beneficiaries with their mobile nos./address should be submitted alongwith six monthly compliance reports.

11. LEDs should be used in all common areas and corridors. 100% solar lighting is to be

provided in the open areas/ stairs cases.

12. Parking guideline as per Greater Noida Development Authority should be followed.

Parking for disabled persons should be explored.

13. All entry/exit point should be bell mouth shaped.

14. To discharge excess treated waste water into public drainage system, permission from

the competent authority to be taken prior to any discharge.

15. 100 % provision of Rain Water Harvesting is to be made. RWH shall be initially done

only from the roof top. RWH from green and other open areas shall be done only after

permission from CGWB.

16. An underground Pucca tank for collection/reuse of rain water may be constructed. 17. Height of the stack should be provided based on combined DG sets capacity and be 6mt

higher than the tallest building. 18. Post project monitoring for air, water (surface + ground), Stack noise of D.G. sets, STP

to be carried out as CPCB Guidelines. 19. Crèche to be provided during the construction/operation phase.

Minutes of 228th

SEAC Meeting Dated 23/07/2015

Page 6 of 52

20. Provision of separate room for senior citizen with proper amenities shall be made.

21. EWS/LIG housing provisions shall be made as per development authority bye-laws.

22. Protection shall be provided on the windows of the high rise flats for security of

residents.

23. Unless and until all the environmental issues are sorted out the occupancy will be

restricted and would be only allowed after achieving the Permission from the competent

authority.

24. The project proponent shall ensure that the project site does not attract/infringe any buffer zone of no activity identified/declared under law.

25. For any extraction of ground water, prior permission from CGWB shall be taken. 26. Sprinkler to be used for curing and quenching and ready mix concrete may be used for

construction. 27. Possibilities of use of treated waste water for irrigation purposes should be explored.

Drip irrigation should be tried upto extent possible. No fresh water will be used for irrigation purpose.

28. Mobile toilets, safe drinking water facility, sanitation facility and eco friendly fuels etc. Shall be made available to the temporary residents/workers at the project site including

the proper treatment and the disposal of the wastes.

3. Group Housing Project “Panchsheel Green-II” at Plot No. GH-01A, Sector-16,

Greater Noida. Sri Gulshan Kumar, H-169, Sector-63, Noida. File No. 2560/AD-H

The project proponent did not appear. The committee noted that the applicant has

submitted a request letter for including the matter in next meeting. The committee directed to

defer the matter for next meeting.

4. Group Housing Project at Plot No-SC-01/B-7, Sports City, Sector-150, Noida. Sri

Rajeev Sharma, director, IInd Floor, F-32, Sector-18, Noida. File No. 2562/SPO-V

The project proponent did not appear. The committee discussed and deliberated that project fie should be closed and should be opened only after request from the project

proponent. The file shall not be treated as pending at SEIAA/SEAC.

5. Group Housing Project “Dinesh Nagar” at Pabla Modinagar Road, Pilkhuwa, NH-

24, Hapur, U.P. M/s Platina Real Estate Pvt Ltd. Sri Vipin Kumar Mittal, C-22, 3rd

Floor, D C, Raj Nagar, Ghaziabad. File No. 2569/DD-Y

The committee noted that an undated application received on 24/09/2014 was made

by the project proponent for environmental clearance of Group Housing Project “Dinesh

Nagar” at Pabla Modinagar Road, Pilkhuwa, NH-24, Hapur, U.P. M/s Platina Real Estate Pvt.

Ltd.

A presentation was made by Shri Madhur Mittal, authorized representative of project

proponent alongwith their consultant M/s Prakriti Consultants Services. The proponent,

through the documents submitted and the presentation made, informed the committee that:-

1. The environmental clearance is sought for Group Housing Project “Dinesh Nagar” at

Pabla Modinagar Road, Pilkhuwa, NH-24, Hapur, U.P. M/s Platina Real Estate Pvt Ltd.

2. Area details of the project is as follows:

S. No. Items Details (sq m)

A Total plot area 80165.55

B Area under road widening 8362.92

C Area for Agriculture land 7122.92

D Area of Less lands 1901.85

Minutes of 228th

SEAC Meeting Dated 23/07/2015

Page 7 of 52

A-(B+C+D)=E Plot Area 62,777.86

3. Area under plotted development:

Plotted Development – A Area 17659.11

Plotted Development – B Area 1035.00

4. Area under group housing:

1 Net Area under GH 44083.75

2 Commercial area 1938.77

3 Area under parks 6638.97

4 Jr. High School 2000.00

5 Parking area 2696.50

6=[1-(2+3+4+5)] Area under net GH 30809.51

Open area 17338.01

Permissible FAR 1.750

Achieved FAR 53916.6 (1.749)

Permissible Ground Coverage 45%

Achieved Ground Coverage 13469.91 (43.72%)

Blocks 42 & G+3

Total Proposed Units 1344 (@303 units/Ha)

Permissible Units 1548

Population 6720

5. Green area of the project is as follows:

S.No. Particulars Area (sqm)

1 Group Housing 6638.97

2 Plotted Development-A 2649.14

3 Plotted Development-B 155.26

Total 9443.37

6. Population details are as follows:

S.No Particulars Details

1 Group Housing 6720

2 Plotted Development 645

3 Commercial Centre 650

4 Jr. High School 400

5 Total Population 8415

6 Maximum Height 12 m

7. Block breakup details are as follows:

Residential/ Commercial/Jr. High School Units/Plots Description

Residential

Group Housing No of Blocks- 42

(one floor having 8 units ,1 Block having 32

units)

1344 Ground + 3 Floors

Plotted

Development

Plotted-A and B

(Plot A having 121 No. of plots and Plot B

having 7 No. plots)

129 Plotted

Commercial Area

Comm.-A 6 -

Comm.-B 4 -

Comm.-C 4 -

Jr. High School 1 1 -

8. Land use breakup details are as follows:

S.No. Particulars Area (sqm) Percentage

1 Group Housing 13471.5 21.46%

2 Plotted Development 8750.52 13.94%

3 Commercial Area 2533.5 4.04%

4 Jr. High School 2000 3.19%

5 Green / parks 9443.37 15.04%

6 Parking area 2696.5 4.30%

7 Area under road/path/open 23882.47 38.04%

Total 62,777.86 100%

Minutes of 228th

SEAC Meeting Dated 23/07/2015

Page 8 of 52

9. Water and power requirement details are as follows:

PARTICULARS PROPOSAL

Fresh water 503 KLD

Flushing 180 KLD

Horticulture/Landscape 10 KLD

Cooling Water for DG set 13 KLD

Total water requirement 706 KLD

Waste water 550 KLD

STP Capacity 650 KLD

Source of Water Supply Ground Water

Power Requirement 1800kVA

Power Source From state (UP) Grid Supply

Backup Power

(DG Sets in Construction Phase)

600*3 kVA

10. Water calculation details are as follows: S.

No.

Description unit/Area

(in m2

)

Total

Occupancy (@ 5/unit)

Rate of fresh

water demand (lpcd)

Total Fresh

Water (KD)

Total

Flushing/Recycled water

(KLD)

Total Water

Requirement (KLD)

1. Group Housing

1344 6720 Fresh Water @ 65 LPCD

Flushing Water

@ 21 LPCD

437 142 579

2. Plotted

development

129 645 Fresh Water

@ 65 LPCD Flushing Water

@ 21 LPCD

42 4 56

3. Commercial Centres

2533.5 450 Fresh Water @ 5 LPCD

Flushing Water @ 10 LPCD

2.5 4.5 7

4. Jr. High

School

2000 200 Fresh Water

@ 5 LPCD Flushing Water @

10 LPCD

1 2 3

5. Staff 5%of total

population

500 Fresh Water

@ 30 LPCD

Flushing Water @ 15 LPCD

15 7.5 23

6. Visitors 10%of total population

1000 Fresh Water @ 5 LPCD

Flushing Water @

10 LPCD

5 10 15

(A) Total water 503 180 683

5 Horticulture and

Landscape development

9443

sqm

1 l/sqm 10 10

6 Cooling water for DG sets

600*3 kVA

0.9 l/KVA/Hr

(@ 8 hrs)

13 13

(B) 23 KLD

Grand Total (A+B) = 706 KLD

12. Waste water details are as follows:

Water/ Waste Water Details

Fresh water 503 KLD

Flushing 180 KLD

Horticulture / Landscape 10 KLD

Diesel generator sets cooling 13 KLD

Total water requirement 706 KLD

Waste water 550 KLD

Source of water - Municipal Water

STP Capacity – 650 KLD (~ 20% extra for future expansion)

STP Sludge – 130 KLD

The total quantity of fresh water requirement for the proposed project will be 503 KLD which will be met

from municipal supply. 550 KLD waste water will be generated from the project which will be treated in STP

Minutes of 228th

SEAC Meeting Dated 23/07/2015

Page 9 of 52

(650 KLD) and recycled within premises for flushing, horticulture, DG sets cooling and other low end uses.

13. Solid waste generation details are as follows:

S. No. Particulars Population Waste generated(Kg/day)

1 Group Housing (@ 0.5 Kg/day) 6720 3360

2 Plotted development (@ 0.5 Kg/day) 645 322

3 Commercial Centers (@ 0.15

Kg/day)

650 98

4 Jr. High School (@ 0.15 Kg/day) 400 60

2 Visitors (@ 0.15 Kg/day) 421 63

3 Staff (@ 0.15 Kg/day) 841 126

Total Solid Waste Generated 4TPD

Horticulture Waste 34 KLD

E-Waste (0.15 Kg/C/Yr) 3 Kg/year

STP Sludge 194 KLD

14. The project proposals are covered under category 8"a" of EIA Notification, 2006.

The committee discussed the matter and directed the project proponent to submit following information:

1. Scheme boundary should be clearly mentioned on map. 2. Physical features within 30 m of the project sites with their ownership.

3. Registry papers of ownership (including all khasras) should be submitted. 4. Land use proposed should be as per Pilakhua Master Plan and should be shown on the

map. 5. Net plot area under scheme should be mentioned separately.

6. Area details showing proposed uses as residential, commercial, parks, parking, roads,

other services, facilities of the project also in percentage.

7. Population calculation as per plot size/no. of housing units as per provisions of bye-

laws should be submitted (for polloted development as well as group housing). Water

calculations should be revised accordingly.

8. Internal road width with RoW/carriage way/cross section of all roads. Also showing

drainage, plantation etc.

9. In case of borewell, permission from Ground Water Authority should be taken.

10. Copy of all approved layout plan/maps/services plans/letters submitted to Development

Authority.

11. Parking details alongwith requirement to be submitted.

12. Proposed 30 m wide road in Master Plan to be constructed by project proponent for

getting approach in colony, if the same is not constructed by Authority.

13. Provision of Kauccha tank for surface water collection.

14. Show the outlet of internal storm water drainage. Appropriate disposal of storm water

shall be responsibility of the builder. Plan in this regard should be submitted.

15. G.O. regarding no EWS/LIG housing is needed in affordable housing is to be

submitted.

16. Plan of STP and location on map.

17. Plan for municipal solid waste management alongwith identification of service provider

as approved/authorized by SPCB. Site of ultimate disposal and rate of manure

production and consumption within the site. 18. Sanction letter from Power Corporation for Power supply to the project.

19. Distance of project from Common Municipal Solid Waste disposal site, Pilakhua. 20. The structure design certificate by qualified structure engineer should be submitted. The

structural design certificate should preferably be vetted by IITs/CBRI. Provision of alarm system, to timely notify the employees/residents, in case of occurrence of

earthquake/other natural disasters/fire should be provided. . 21. Area statement with block wise/tower wise/floor wise details alongwith no. of units.

The matter shall be discussed after submission of information as above.

Minutes of 228th

SEAC Meeting Dated 23/07/2015

Page 10 of 52

6. Proposed Cement Grinding Unit of KLK Cement Pvt. Ltd., at Plot N0-E-18,19,20,

UPSIDC Sidhwan, Jaunpur, U.P. Sri Pradeep Kumar, Naya Chowk, Balia. File No.

2335/DD-DS

The committee noted that an undated application received on 23/05/2014 was made

by the project proponent for environmental clearance of Proposed Cement Grinding Unit of

KLK Cement Pvt. Ltd., at Plot N0-E-18,19,20, UPSIDC Sidhwan, Jaunpur, U.P. Terms of

reference in the matter were issued through letter dated 19/11/2014. The project proponent

submitted final EIA through letter dated 27/04/2015.

A presentation was made by Shri Pradeep Kumar, project proponent along with their

consultant M/s Prakriti Consultants Services. The proponent, through the documents

submitted and the presentation made, informed the committee that:-

1. The environmental clearance is sought for Proposed Cement Grinding Unit at Plot

N0-E-18, 19, 20, UPSIDC Sidhwan, Jaunpur, U.P. M/s KLK Cement Pvt. Ltd.

2. Salient features of the project are as follows: � Land Area 3510 sqm in Industrial Area, Rampur Sidhwan, Jaunpur

� Type of unit Cement Grinding Unit

� Capacity 30,000 TPA ( 100 TPD) (300 Working day)

� CoveredArea 1029.0 sqm

� OpenArea 2298.53 sqm

� Factory Area 1212.28 sqm

� Lab & Office Area 109.00 sqm

� Raw Material Store Area 131.09 sqm

� Green Area 1158.3 sqm

� Raw Material Clinker - Reeva, MP, Gypsum – Rajasthan,Fly Ash- Renukoot

� Variety of Cement OPC (Ordinary Portland Cement), PPC (Portland Pozzolona Cement)

� Water requirement 1 KLD (Only for Domestic Use)

� Source of water Bore Well (Ground Water)

� Electric requirement 400 KVA for 100 TPD Cement Plant

� Worker & Staff 17 nos.

3. Land use breakup details are as follows: Type Area (sqm)

Total Area 3510.8 sqm

Covered Area 1029.0 sqm

Open Area 2298.53 sqm

Factory Area 1212.28 sqm

Lab & Office Area 109.00 sqm

Raw Material Store Area 131.09 sqm

Green Area 1158.3 sqm

4. Raw material details are as follows: Raw Material Percentage (%) Proposed requirement for 100 TPD PPC

(Approx)

Clinker 65-70% 20000 TPA

Fly ash 25-30% 7500 TPA

Gypsum 5% 2500 TPA

Total 30000 TPA

5. The project proposals are covered under category 3”b” of EIA Notification, 2006.

The committee discussed the matter and directed the project proponent to submit following information:

1. Location of proposed site in UPSDIC map. 2. Approved plan of the project by UPSDIC.

3. Setback left on all sides. 4. Plantation plan with physical features within 30 m of the project sites with their

ownership. 5. Provision of trees @ 1tree per 80, Sq Mt. of area to be provided.

Minutes of 228th

SEAC Meeting Dated 23/07/2015

Page 11 of 52

6. Traffic study on highway in vicinity of the project alongwith air quality study.

7. Rain water harvesting potential should be calculated on the basis of rooftop area.

Revised calculation should be submitted.

8. Environmental Corporate Responsibility (ECR) plan along with budgetary

provision amounting to 2% of project cost (Rs. 10 Lac) shall be prepared and

approved by Board of Directors of the company. A copy of resolution as above

shall be submitted to the authority alongwith list of beneficiaries with their

mobile nos./address.

The matter shall be discussed after submission of information as above.

7. Expansion of Group Housing Project at Plot No-SC-02/A, Sector-150, Noida, U.P. S

Lotus Greens Constructions Pvt. Ltd Sri Manmeet Singh Batra File No. 2901/AD(H)

The committee noted that an application dated 12/03/2015 was made by the project

proponent for environmental clearance of Expansion of Group Housing Project at Plot No-

SC-02/A, Sector-150, Noida, U.P. M/s Lotus Greens Constructions Pvt. Ltd. Terms of

reference in the matter were prescribed in SEAC meeting dated 19/06/2015. The project

proponent through letter dated 16/05/2015 have submitted REIA report. Again, through letter

dated 21/07/2015 a point wise compliance was submitted by the project proponent.

A presentation was made by Shri Manmeet Singh Batra, project proponent along with

their consultant M/s Ind Tech House Consult, Delhi. The proponent, through the documents

submitted and the presentation made, informed the committee that:-

1. The environmental clearance is sought for proposed Expansion of Group Housing Project

at Plot No-SC-02/A, Sector-150, Noida, Gautam Budh Nagar, U.P.

2. Salient features of the project are as follows: S.n

o

Description Details Unit

AREA DETAILS

1. Plot Area 647600 SQM

2. Proposed Built Up Area 1986644 SQM

3. Cost of The Project 3207 CR

4. Height of Tallest Tower 96 M

5. No. of Floors B+ST/28 NOS

6. Total Permissible Ground Coverage (28% Residl. + 2%

Facility)

194280 SQM

7. Total Proposed Ground Coverage (13.9%) 90066 SQM

8. Permissible FAR Area 210 (200+ 5% for green rating) 1359960 SQM

9. Proposed FAR Area (200.44) 1298051 SQM

10. Green Area Required (43.04% of Plot Area) 278767 SQM

11. Green Area Proposed (54.95% of Plot Area) 355887 SQM

POPULATION & WATER REQUIREMENT

12. Total No. of DU’s including villas 9314 NOS

13. Expected Population (Res.-46755 + N.Res.-1057+ vis. 8430) 56242 PERSONS

14. Total Water Requirement 5162 KLD

15. Fresh Water Requirement (61.28% of total water req) 3164 KLD

16. Waste Water Generation 3574 KLD

17. STP Capacity 4290 KLD

18. Treated Water Available for Reuse/Used 2859 KLD

19. Surplus Treated Water 822 KLD

RAIN WATER HARVESTING PIT DETAILS

20. Proposed quantity of rainwater to be harvested 170089.85 CUM

21. No. of RWH Pits Proposed 160 NOS

PARKING

Minutes of 228th

SEAC Meeting Dated 23/07/2015

Page 12 of 52

22. Parking required as /bylaws 16359 ECS

23. Parking Proposed (incl. Visitors) 20794 ECS

24. Proposed Parking on Surface 4315 ECS

25. Proposed Parking in Stilt + Podium 3630 ECS

26. Proposed Parking in Basement 12580 ECS

27. Proposed Parking in Sport Club Basement 269 ECS

WASTE GENERATION

28. Municipal Solid Waste Generation 24.48 TPD

29. Quantity of e-waste generation 160 KG/DAY

30. Quantity of Hazardous Waste Generation 6060 LTS/ANNUM

31. Quantity of Sludge generated from STP 1286.6 KG/DAY

POWER REQUIREMENT

32. Total Power Requirement 42000 KW

33. DG sets Backup 30300 KVA

LAND UTILIZATION DETAIL

Use Area % w.r.t total plot area

Plot 647600 100

34. Residential 76815.57 11.862

35. Commercial 2857.27 0.44

36. Sports 10393.04 1.60

37. Roads and Parking 171874.5 26.5

38. Green Area 355887.49 55

39. Other Open and Paved Area 29772 4.6

Total 647600 100

POPULATION & WATER REQUIREMENT DETAILS

Residential

Domestic

Flushing

46755 65 3039 2431 - 28

59 46755 21 982 982 982

Non Residential

Domestic

Flushing

1057 15 16 13 -

1057 30 31 31 31

Visitors

Domestic

Flushing

8430 6 51 41 -

8430 9 76 76 76

Gardening Area 243522 1 243 - 243

DG Cooling water for

6 hrs

30300 0.9 82 - 82

Golf course 112365 5 562 - 562

Air conditioning 600 10 60 - 60

Filter backwash LS LS 50

Swimming pool 1 LS 8

Total - - 5200 3574 2037

Surplus treated waste water available for construction use 822 KLD

Fire Fighting Water Requirement Prop in UG Tank and

OH Tank

3525 KL (5x200000)+(25000x101)

1% of Total Water Requirement = 52

KL

GREEN AREA

• Total Plot Area- 647600 sq.m. , Ground Coverage Area- 90066 sq.m.

• A total of 355887 sq m green area will be developed to enhance the beauty of the site and combat air and

noise pollution.

Landscape Area Schedule

Total plot area 647600 sq. m.

Required Green Area (43.04% of Plot Area) 278767 sq. m.

Proposed Green Area (54.95% of Plot Area)

355887 sq. m. Peripheral plantation and Golf Course green area = 160980

sq.m.(24.85% of the plot area)

SURFACE, STILT/PODIUM PARKING PLAN

Parking required as /bylaws 16359 ECS

Parking Proposed incl. visitors parking 20794 ECS

Proposed Parking on Surface (Visitors parking) 4315 ECS

Minutes of 228th

SEAC Meeting Dated 23/07/2015

Page 13 of 52

Proposed Parking in Stilt + Podium 3630 ECS

Proposed Parking in Basement 12580 ECS

Proposed Parking in Sport Club Basement 269 ECS

Basement

Parking

@

30sq.m./ECS

Net Basement

Area (Sq.m.)

Service Area

(Sq.m.)

Net Area Available

for Parking (Sq.m.)

ECS

399614.973 22193.437 377421.53 12580

WASTE GENERATION

Total Waste Generation 24.48 TPD

Organic Waste Generation 14.69 TPD

E- Waste Generation 160 KG/Day

Sludge Generation 1286.58 KG/Day

Hazardous Waste Generation (DG Waste

Oil)

6060 Lts/ Annum

DG SETS & POWER BACKUP

Power load 42000 KW

Source of Power Supply Uttar Pradesh State Electricity Board.

Power Backup • DG sets of total capacity 30300 KVA will be provided as backup during power failure

• Inbuilt acoustic enclosure of DG sets as per EP rules.

• Low Sulphur Diesel will be used in D.G. sets

• Height of DG Stack – 102 m from GL (6 m above tallest tower of the project)

3. The project is covered under category 8 "b" of EIA notification, 2006.

The committee noted that the project proponent has submitted copy of allotment

letter, all approved plans from Noida Development Authority, Section of all roads, Structural

safety certificate vetted by Jamia Millia University. The project proponent also submitted that

all excavated earth shall be used within the proposed project for infrastructure development

works and no earth shall be taken out of the premises. The project proponent also submitted

that 2% of project cost (Rs. 65-70 crores) shall be utilized on CSR activities.

The committee discussed the matter and recommended grant of environmental

clearance on the project proposals alongwith general conditions as earlier prescribed by the

authority for construction project and following specific conditions:

1. 03 m peripheral green shall be provided around the project inside the project boundary.

Add Astonia in list of trees.

2. 15% area of the total plot area shall be compulsorily made available for the green belt

development including the peripheral green belt.

3. Project falling with in 10 Km. area of Wild Life Sanctuary is to obtain a clearance from

National Board Wild Life (NBWL) even if the eco- sensitive zone is not earmarked.

4. Criteria/ norms provided by competent Authority regarding the seismic zone be

followed for construction work. Provision of alarm system, to timely notify the

residents, in case of occurrence of earthquake/other natural disasters/fire should be

provided. A well defined evacuation plan should also be prepared and regular mock

drills should be arranged for the residents. Rise of stairs should be constructed in a way, so that it should provide smooth movement.

5. For the treatment for total sewage, a full-fledged STP is to be provided with 20% more capacity than waste water generated during operation phase.100% waste water is to be

treated in captive STP conforming to prescribed standards of receiving body for designated use. Monitoring of STP to be done daily till its stabilization.

6. Dual plumbing should be adopted. Recycling of water as proposed shall be undertaken with regular testing and monitoring of treated water.

7. Dedicated power supply for STPs is to be ensured during operation. Sludge of STP is to

be used in-house as manure and surplus manure should be managed by giving it to end

users. STP shall be suitably located nearest to back side boundary with shortest out let.

Operation and the maintenance cost of the STP shall also be informed along with the

compliance of the E-waste and municipal solid waste disposal.

Minutes of 228th

SEAC Meeting Dated 23/07/2015

Page 14 of 52

8. Environmental Corporate Responsibility (ECR) plan along with budgetary provision

amounting to 2% of total project cost (Rs. 65-70 crores) shall be prepared and approved

by Board of Directors of the company. A copy of resolution as above shall be submitted

to the authority. A list of beneficiaries with their mobile nos./address should be

submitted alongwith six monthly compliance reports.

9. LEDs should be used in all common areas and corridors. 100% solar lighting is to be

provided in the open areas/ stairs cases.

10. Parking guideline as per Noida Development Authority should be followed. Parking for disabled persons should be explored.

11. All entry/exit point should be bell mouth shaped. 12. To discharge excess treated waste water into public drainage system, permission from

the competent authority to be taken prior to any discharge. 13. 100 % provision of Rain Water Harvesting is to be made. RWH shall be initially done

only from the roof top. RWH from green and other open areas shall be done only after permission from CGWB.

14. An underground Pucca tank for collection/reuse of rain water may be constructed. 15. Height of the stack should be provided based on combined DG sets capacity and be 6mt

higher than the tallest building.

16. Post project monitoring for air, water (surface + ground), Stack noise of D.G. sets, STP

to be carried out as CPCB Guidelines.

17. Crèche to be provided during the construction/operation phase.

18. Provision of separate room for senior citizen with proper amenities shall be made.

19. Protection shall be provided on the windows of the high rise flats for security of

residents.

20. Unless and until all the environmental issues are sorted out the occupancy will be

restricted and would be only allowed after achieving the Permission from the competent

authority.

21. The project proponent shall ensure that the project site does not attract/infringe any buffer zone of no activity identified/declared under law.

22. For any extraction of ground water, prior permission from CGWB shall be taken. 23. Sprinkler to be used for curing and quenching and ready mix concrete may be used for

construction. 24. Possibilities of use of treated waste water for irrigation purposes should be explored.

Drip irrigation should be tried upto extent possible. No fresh water will be used for irrigation purpose.

25. Mobile toilets, safe drinking water facility, sanitation facility and eco friendly fuels etc. Shall be made available to the temporary residents/workers at the project site including

the proper treatment and the disposal of the wastes.

8. Jubilant Agri & Consumer Products Ltd, at Bhartiagram, Gajraula, Amroha, Sri

Indrish Saxena. File No. 2537/SPO-V

The project proponent did not appear. The committee noted that the applicant has

submitted a request letter for including the matter in next meeting. The committee directed to

defer the matter for next meeting.

9. Group Housing Project “Gulshan Bellina”, at Plot No-GH-02A, Sector-16, Greater

Noida- Sri Uma Shanker Sharma, Sr. G M, 4, Dyanand Vihar, New Delhi File No.

2633/OSD-T

The committee noted that an undated application received on 31/10/2014 was made

by the project proponent for environmental clearance of Group Housing Project “Gulshan

Bellina” at Plot No-GH-02A, Sector-16, Greater Noida, M/s Gulshan Homz Pvt. Ltd. Terms

Minutes of 228th

SEAC Meeting Dated 23/07/2015

Page 15 of 52

of reference in the matter were prescribed in SEAC meeting dated 29/04/2015. Final EIA was

submitted through letter dated 26/06/2015.

A presentation was made by Shri Rajesh Sohal, authorized representative of project

proponent along with their consultant M/s Grass Roots Research & Creation India (P) Ltd.

The proponent, through the documents submitted and the presentation made, informed the

committee that:-

1. The environmental clearance is sought for Group Housing Project “Gulshan Bellina”

at Plot No-GH-02A, Sector-16, Greater Noida, M/s Gulshan Homz Pvt. Ltd.

2. Area details of the project is as follows:

S.

NO.

PARTICULARS AREA (IN M2

) % WISE DETAILS

1. Plot Area 28,374.22 100

2. Permissible Ground Coverage (@ 35% of

plot area)

9930.997

3. Proposed Ground Coverage (@ 30.51% of

plot area)

8656.343 30.51

4. Total Permissible FAR

• Permissible FAR (@ 2.75)

• Purchasable FAR (@ 0.75)

99309.770

78029.105

21280.665

5. Proposed FAR (@ 3.493)

• Residential

• Convenient shopping

• Community

99106.090

97274.944

982.584

848.362

6. Podium Area 12,333.850

7. Ancillary Area 14790.016

8. Total Basement Area

• Area for Parking

• Services Area

24,248.554

22,354.280

1,894.274

9. Stilt Area 4191.321

10. Total Built-up Area 1,54,669.83

11. Landscape Area (@ 51.37% of Open Area) 10,120.975

12. Height of the Building 65.68 m

13. Open Area 19717.877 69.49

3. Area break up details is as follows: S.NO. DESCRIPTION AREA IN SQ.M. % wise area

1 Area under residential facility (GC) 7369.266 26

2 Area under commercial (GC) 983.697 3

3 Area under community (GC) 303.38 1

4 Area Under Landscaping 10,120.98 36

5 Area under road & remaining open area 9,596.90 34

TOTAL PLOT AREA 28374.22 100%

4. Salient features details is as follows: PROJECT FEATURES DESCRIPTION

Estimated Population 5,605 Nos. (Residents, staffs and visitors)

Estimated Water Requirement

Construction Phase

Operation Phase

773 ML (Agency: Treated water from GNIDA)

477 KLD (Fresh water = 316 KLD) (Agency: Municipal Supply)

Estimated wastewater Generation 386 KLD

Power Demand 4,496 KVA

Power Backup 2 x 1010 kVA & 2 x 500 kVA (Considering diversity factor)

Source of Power Noida Power Company Limited (NPCL)

Rain Water Harvesting Pits 6 Pits

Solid Waste Generation 2,654 kg/day

Parking Facilities

Required

Proposed

As per MoEF norms: 991ECS

As per Greater Noida Bye Laws: 1,241 ECS

1,276 ECS

Minutes of 228th

SEAC Meeting Dated 23/07/2015

Page 16 of 52

5. Built up area break-up details is as follows: S. No. Particulars

Area (in m2

)

1. FAR 99,106.090

2. Basement Area 24,248.554

3. Stilt Area 4,191.321

4. Podium Area 12,333.850

5. Ancillary Area 14,790.016

Total Built-up area 1,54,669.83

6. Population details is as follows: S.

No.

Unit Type DUs/Area PPU Total Population % wise

1. General 1124 4.5 5,058 90.2

2. Convenient shopping

Staff

983 (3 m

2

/person)

10% of the

population

33 0.59

3. Community Staff 848.56 (10 m

2

/person)

10% of the

population

8 0.14

4. Visitors @ 10% of population 506 9.02

Grand Total 5,605 100

7. Water requirement details is as follows: S.

No.

Description

Area

(in m2

)

Total

Occupancy

Rate of water

demand (lpcd)

Total Water

Requirement

(KLD)

A. Residential

Dwelling Units 5,058 86 435

B. Convenient shopping Staff 33 30 0.99

C. Community Staff 8 30 0.24

D. Visitors 506 15 7.59

Total Domestic Water Demand (B) = 443.82 Say 444 KLD

E. Horticulture and

Landscape development

10,120.975

m2

12.73

F. Swimming Pool 5

G. STP Filter Backwash

15

Grand Total = 476.73 Say 477 KLD

8. Waste water calculation details is as follows: Domestic Water Requirement 444 KLD

• Fresh (70% of domestic) 311 KLD

• Flushing (30% of domestic) 133 KLD

Waste Water Generated

(80% fresh + 100% flushing + 80% Swimming pool)

249 + 133 + 4 = 386 KLD

9. The project proposals are covered under category 8"b" of EIA Notification, 2006.

The committee noted that all sanctioned map have been submitted. Structural safety

certificate vetted by Jamia Milia University has been submitted. Source of water supply is

Municipal Authority. Copy of letter submitted to Municipal Authority in this regard has been

submitted. Plan for community facilities and details regarding solar power provisions/area

required has been submitted. The committee discussed the matter and recommended grant of

environmental clearance on the project proposals alongwith general conditions as earlier

prescribed by the authority for construction project and following specific conditions:

1. 03 m peripheral green shall be provided around the project inside the project boundary. Provision of trees @ 01tree per 80 Sq mt. should be undertaken.

2. Kuchha water tank shall be provided for storage of storm water. 3. Load sanctioned from Greater Noida Power Supply should be submitted.

Minutes of 228th

SEAC Meeting Dated 23/07/2015

Page 17 of 52

4. 15% area of the total plot area shall be compulsorily made available for the green belt

development including the peripheral green belt.

5. Project falling with in 10 Km. area of Wild Life Sanctuary is to obtain a clearance from

National Board Wild Life (NBWL) even if the eco- sensitive zone is not earmarked.

6. Criteria/ norms provided by competent Authority regarding the seismic zone be

followed for construction work. Provision of alarm system, to timely notify the

residents, in case of occurrence of earthquake/other natural disasters/fire should be

provided. A well defined evacuation plan should also be prepared and regular mock drills should be arranged for the residents. Rise of stairs should be constructed in a way,

so that it should provide smooth movement. 7. For the treatment for total sewage, a full-fledged STP is to be provided with 20% more

capacity than waste water generated during operation phase.100% waste water is to be treated in captive STP conforming to prescribed standards of receiving body for

designated use. Monitoring of STP to be done daily till its stabilization. 8. Dual plumbing should be adopted. Recycling of water as proposed shall be undertaken

with regular testing and monitoring of treated water. 9. Dedicated power supply for STPs is to be ensured during operation. Sludge of STP is to

be used in-house as manure and surplus manure should be managed by giving it to end

users. STP shall be suitably located nearest to back side boundary with shortest out let.

Operation and the maintenance cost of the STP shall also be informed along with the

compliance of the E-waste and municipal solid waste disposal.

10. Environmental Corporate Responsibility (ECR) plan along with budgetary provision

amounting to 2% of total project cost (Rs. 7.5 crores) shall be prepared and approved by

Board of Directors of the company. A copy of resolution as above shall be submitted to

the authority. A list of beneficiaries with their mobile nos./address should be submitted

alongwith six monthly compliance reports.

11. LEDs should be used in all common areas and corridors. 100% solar lighting is to be

provided in the open areas/ stairs cases. 12. Parking guideline as per Greater Noida Development Authority should be followed.

Parking for disabled persons should be explored. 13. All entry/exit point should be bell mouth shaped.

14. To discharge excess treated waste water into public drainage system, permission from the competent authority to be taken prior to any discharge.

15. 100 % provision of Rain Water Harvesting is to be made. RWH shall be initially done only from the roof top. RWH from green and other open areas shall be done only after

permission from CGWB. 16. An underground Pucca tank for collection/reuse of rain water may be constructed.

17. Height of the stack should be provided based on combined DG sets capacity and be 6mt

higher than the tallest building.

18. Post project monitoring for air, water (surface + ground), Stack noise of D.G. sets, STP

to be carried out as CPCB Guidelines.

19. Crèche to be provided during the construction/operation phase.

20. Provision of separate room for senior citizen with proper amenities shall be made.

21. Protection shall be provided on the windows of the high rise flats for security of

residents.

22. Unless and until all the environmental issues are sorted out the occupancy will be

restricted and would be only allowed after achieving the Permission from the competent

authority. 23. The project proponent shall ensure that the project site does not attract/infringe any

buffer zone of no activity identified/declared under law. 24. For any extraction of ground water, prior permission from CGWB shall be taken.

25. Sprinkler to be used for curing and quenching and ready mix concrete may be used for construction.

Minutes of 228th

SEAC Meeting Dated 23/07/2015

Page 18 of 52

26. Possibilities of use of treated waste water for irrigation purposes should be explored.

Drip irrigation should be tried upto extent possible. No fresh water will be used for

irrigation purpose.

27. Mobile toilets, safe drinking water facility, sanitation facility and eco friendly fuels etc.

Shall be made available to the temporary residents/workers at the project site including

the proper treatment and the disposal of the wastes.

10. Establishment of new Power Plant capacity 20 MW at Vill-Simbhaoli, Distt-Hapur.

Sri A P Singh, MD, C-11, Inner Circle,Cannaught Place,New Dehli File No.

2660/SPO-V

The project proponent did not appear. The committee noted that the applicant has

submitted a request letter for including the matter in next meeting. The committee directed to

defer the matter for next meeting.

11. Conversion of Existing FO Tank of 4700 KL to HSD at our Mugalsarai Installation-

Sri Rajesh L. Kumbhare, Sr. Manager, Bharat Petrolium Corp. Ltd. Mugalsarai

Installation, Alampur, Mugalsarai, Chandauli File No. 2545/AD(H)

The committee noted that the matter was earlier discussed in SEAC meeting dated 01/06/2015 wherein following recommendations were made:

"The committee noted that the project proponent through their letter received on 04/09/2014 applied for environmental clearance in respect of propose change in product mix

at POL Depot of BPCL located at Mughalsarai. The project proponent through his letter

informed that due to heavy demand of HSD in the surrounding area of Mughalsarai,

conversion of existing FO Tank (above ground of 4700 KL capacity is proposed to be

converted to HSD). The committee noted that existing POL installation has storage capacity 45205 KL.

Tank no. 17 is presently use for storage of furnace oil (FO) which is proposed to be change for storage of HSD. Capacity of the installation will remain unaltered after proposed

conversion. No capacity augmentation is proposed. Only change in product mix in 01 tank is proposed.

The committee observed that activity of isolated storage and handling of hazardous chemicals is covered under category 6"b" of EIA Notification. Also, the prior environmental

clearance is required for any change in product mix in an existing manufacturing unit

included in scheduled beyond the specified range.

The committee discussed the MSIHC rules and its schedule-2 and observed that the

threshold quantity for storage of highly flammable liquids as defined in schedule -1 is 10,000

tons. The proposed change in product mix is 4700 KL of HSD. The committee directed that

the project proponent should submit details of change in product mix in view of provisions

made under category 6"b" of schedule of EIA Notification, 2006. The calculations regarding

change in product mix should be submitted in tonnes also.

The matter shall be taken on priority as soon as the information from BPCL is

received."

22. The project proponent submitted replies through letter dated 01/07/2015 through which

it was submitted that :

• The proposed project is as renovation project in the existing POL installation

with existing storage capacity 45205 KL.

• Tank no. 17 used presently for storage of FO will be changed for storage of

HSD.

Minutes of 228th

SEAC Meeting Dated 23/07/2015

Page 19 of 52

• Capacity of the installation will remain unaltered after proposed conversion.

• No capacity augmentation is proposed. Only one (1) existing FO tank will be

converted to store HSD.

• Pollution load will remain unaltered

• All statutory approvals for the existing capacity of the Installation are obtained.

• Installation is built, operated as per Best Practices / OISD Standards with

highest priority to HSSE.

• Total Land is under possession of BPCL. No Resettlement and Rehabilitation (R

& R) issues are involved.

The committee discussed the matter and observed that environmental clearance for

existing installation/project has not been taken as it was established prior to EIA Notification,

2006. The committee also noted the provisions of EIA Notification, 2006 that environmental

clearance would be required in case of, all new projects/expansion and modernization of

existing projects or activities listed in the schedule with addition of capacity beyond the limits

of specified for the concerned sectors /any change in product mix. The committee deliberated

that in view of provisions of EIA Notification and inclusion of proposed activity under

category 6"b" of Notification, environmental clearance is required to be obtained by the

project proponent. The committee also noted as proposal is covered under category 6"b", it

requires scoping. The committee decided that EIA should strictly follow the guidelines

prescribed in annexure-III to the EIA notification of 2006. The proponents may prepare an

EIA including existing and proposed facilities based on following terms of reference /general

guidelines:

1. Executive Summary.

2. Introduction:

(i) Details of the EIA Consultant including NABET accreditation.

(ii) Information about the project proponent.

(iii)Importance and benefits of the project.

3. Project Description:

(i) Cost of project and time of completion.

(ii) Products with capacities for the proposed project.

(iii) If expansion project, details of existing products with capacities and whether

adequate land is available for expansion, reference of earlier EC if any.

(iv) List of raw materials required and their source along with mode of transportation

(quantity should be given in tonnage).

(v) Other chemicals and materials required with quantities and storage capacities.

(vi) Details of Emission, effluents, hazardous waste generation and their management.

(vii) Requirement of water, power, with source of supply, status of approval, water balance

diagram, man-power requirement (regular and contract).

(viii) Process description along with major equipments and machineries, process flow sheet

(quantative) from raw material to products to be provided.

(ix) Hazard identification and details of proposed safety systems.

(x) Expansion/modernization proposals:

a. Copy of all the Environmental Clearance(s) including Amendments thereto obtained

for the project from MOEF/SEIAA shall be attached as an Annexure. A certified copy

of the latest Monitoring Report of the Regional Office of the Ministry of Environment

Minutes of 228th

SEAC Meeting Dated 23/07/2015

Page 20 of 52

and Forests as per circular dated 30th May, 2012 on the status of compliance of

conditions stipulated in all the existing environmental clearances including

Amendments shall be provided. In addition, status of compliance of Consent to

Operate for the ongoing Existing operation of the project from SPCB shall be attached

with the EIA-EMP report.

b. In case the existing project has not obtained environmental clearance, reasons for not

taking EC under the provisions of the EIA Notification 1994 and/or EIA Notification

2006 shall be provided. Copies of Consent to Establish/No Objection Certificate and

Consent to Operate (in case of units operating prior to EIA Notification 2006, CTE

and CTO of FY 2005-2006) obtained from the SPCB shall be submitted. Further,

compliance report to the conditions of consents from the SPCB shall be submitted.

4. Site Details:

(i) Location of the project site covering village, Taluka/Tehsil, District and State,

Justification for selecting the site, whether other sites were considered.

(ii) A toposheet of the study area of radius of 10km and site location on

1:50,000/1:25,000 scale on an A3/A2 sheet. (Including all eco-sensitive areas and

environmentally sensitive places).

(iii) Details w.r.t. option analysis for selection of site.

(iv) Co-ordinates (lat-long) of all four corners of the site.

(v) Google map-Earth downloaded of the project site.

(vi) Layout maps indicating existing unit as well as proposed unit indicating storage area,

plant area, greenbelt area, utilities etc. If located within an Industrial

area/Estate/Complex, layout of Industrial Area indicating location of unit within the

Industrial area/Estate.

(vii) Photographs of the proposed and existing (if applicable) plant site. If existing, show

photographs of plantation/greenbelt, in particular.

(viii) Landuse break-up of total land of the project site (identified and acquired),

government/ private - agricultural, forest, wasteland, water bodies, settlements, etc

shall be included. (not required for industrial area).

(ix) A list of major industries with name and type within study area (10km radius) shall be

incorporated. Land use details of the study area.

(x) Geological features and Geo-hydrological status of the study area shall be included.

(xi) Details of Drainage of the project upto 5km radius of study area. If the site is within 1

km radius of any major river, peak and lean season river discharge as well as flood

occurrence frequency based on peak rainfall data of the past 30 years. Details of

Flood Level of the project site and maximum Flood Level of the river shall also be

provided. (Mega green field projects).

(xii) Status of acquisition of land. If acquisition is not complete, stage of the acquisition

process and expected time of complete possession of the land.

(xiii) R&R details in respect of land in line with state Government policy.

5. Forest and wildlife related issues (if applicable):

(i) Permission and approval for the use of forest land (forestry clearance), if any, and

recommendations of the State Forest Department. (if applicable).

(ii) Landuse map based on High resolution satellite imagery (GPS) of the proposed site

delineating the forestland (in case of projects involving forest land more than 40 ha).

Minutes of 228th

SEAC Meeting Dated 23/07/2015

Page 21 of 52

(iii) Status of Application submitted for obtaining the stage I forestry clearance along with

latest status shall be submitted.

(iv) The projects to be located within 10 km of the National Parks, Sanctuaries, Biosphere

Reserves, Migratory Corridors of Wild Animals, the project proponent shall submit

the map duly authenticated by Chief Wildlife Warden showing these features vis-à-vis

the project location and the recommendations or comments of the Chief Wildlife

Warden-thereon.

(v) Wildlife Conservation Plan duly authenticated by the Chief Wildlife Warden of the

State Government for conservation of Schedule I fauna, if any exists in the study area.

(vi) Copy of application submitted for clearance under the Wildlife (Protection) Act,

1972, to the Standing Committee of the National Board for Wildlife.

6. Environmental Status:

(i) Determination of atmospheric inversion level at the project site and site-specific

micrometeorological data using temperature, relative humidity, hourly wind speed

and direction and rainfall.

(ii) AAQ data (except monsoon) at 8 locations for PM10, PM2.5, SO2, NOX, CO and

other parameters relevant to the project shall be collected. The monitoring stations

shall be based CPCB guidelines and take into account the pre-dominant wind

direction, population zone and sensitive receptors including reserved forests.

(iii) Raw data of all AAQ measurement for 12 weeks of all stations as per frequency given

in the NAQQM Notification of Nov. 2009 along with - min., max., average and 98%

values for each of the AAQ parameters from data of all AAQ stations should be

provided as an annexure to the EIA Report.

(iv) Surface water quality of nearby River (100 m upstream and downstream of discharge

point) and other surface drains at eight locations as per CPCB/MoEF&CC guidelines.

(v) Whether the site falls near to polluted stretch of river identified by the

CPCB/MoEF&CC, if yes give details.

(vi) Ground water monitoring at minimum at 8 locations shall be included.

(vii) Noise levels monitoring at 8 locations within the study area.

(viii) Soil Characteristic as per CPCB guidelines.

(ix) Traffic study of the area, type of vehicles, frequency of vehicles for transportation of

materials, additional traffic due to proposed project, parking arrangement etc.

(x) Detailed description of flora and fauna (terrestrial and aquatic) existing in the study

area shall be given with special reference to rare, endemic and endangered species. If

ScheduleI fauna are found within the study area, a Wildlife Conservation Plan shall be

prepared and furnished.

(xi) Socio-economic status of the study area.

7. Impact and Environment Management Plan:

(i) Assessment of ground level concentration of pollutants from the stack emission based

on site-specific meteorological features. In case the project is located on a hilly

terrain, the AQIP Modelling shall be done using inputs of the specific terrain

characteristics for determining the potential impacts of the project on the AAQ.

Cumulative impact of all sources of emissions (including transportation) on the AAQ

of the area shall be assessed. Details of the model used and the input data used for

modelling shall also be provided. The air quality contours shall be plotted on a

Minutes of 228th

SEAC Meeting Dated 23/07/2015

Page 22 of 52

location map showing the location of project site, habitation nearby, sensitive

receptors, if any.

(ii) Water Quality modelling - in case of discharge in water body

(iii) Impact of the transport of the raw materials and end products on the surrounding

environment shall be assessed and provided. In this regard, options for transport of

raw materials and finished products and wastes (large quantities) by rail or rail-cum

road transport or conveyorcum-rail transport shall be examined.

(iv) A note on treatment of wastewater from different plant operations, extent recycled

and reused for different purposes shall be included. Complete scheme of effluent

treatment. Characteristics of untreated and treated effluent to meet the prescribed

standards of discharge under E(P) Rules.

(v) Details of stack emission and action plan for control of emissions to meet standards.

(vi) Measures for fugitive emission control

(vii) Details of hazardous waste generation and their storage, utilization and management.

Copies of MOU regarding utilization of solid and hazardous waste in cement plant

shall also be included. EMP shall include the concept of waste-minimization,

recycle/reuse/recover techniques, Energy conservation, and natural resource

conservation.

(viii) Proper utilization of fly ash shall be ensured as per Fly Ash Notification, 2009. A

detailed plan of action shall be provided.

(ix) Action plan for the green belt development plan in 33 % area i.e. land with not less

than 1,500 trees per ha. Giving details of species, width of plantation, planning

schedule etc. shall be included. The green belt shall be around the project boundary

and a scheme for greening of the roads used for the project shall also be incorporated.

(x) Action plan for rainwater harvesting measures at plant site shall be submitted to

harvest rainwater from the roof tops and storm water drains to recharge the ground

water and also to use for the various activities at the project site to conserve fresh

water and reduce the water requirement from other sources.

(xi) Total capital cost and recurring cost/annum for environmental pollution control

measures shall be included.

(xii) Action plan for post-project environmental monitoring shall be submitted.

(xiii) Onsite and Offsite Disaster (natural and Man-made) Preparedness and Emergency

Management Plan including Risk Assessment and damage control. Disaster

management plan should be linked with District Disaster Management Plan.

8. Occupational health:

(i) Plan and fund allocation to ensure the occupational health & safety of all contract and

casual workers

(ii) Details of exposure specific health status evaluation of worker. If the workers' health

is being evaluated by pre designed format, chest x rays, Audiometry, Spirometry,

Vision testing (Far & Near vision, colour vision and any other ocular defect) ECG,

during pre placement and periodical examinations give the details of the same. Details

regarding last month analyzed data of above mentioned parameters as per age, sex,

duration of exposure and department wise.

(iii) Details of existing Occupational & Safety Hazards. What are the exposure levels of

hazards and whether they are within Permissible Exposure level (PEL). If these are

Minutes of 228th

SEAC Meeting Dated 23/07/2015

Page 23 of 52

not within PEL, what measures the company has adopted to keep them within PEL so

that health of the workers can be preserved,

(iv) Annual report of heath status of workers with special reference to Occupational

Health and Safety.

9. Corporate Environment Policy:

(i) Does the company have a well laid down Environment Policy approved by its Board

of Directors? If so, it may be detailed in the EIA report.

(ii) Does the Environment Policy prescribe for standard operating process / procedures to

bring into focus any infringement / deviation / violation of the environmental or forest

norms / conditions? If so, it may be detailed in the EIA.

(iii) What is the hierarchical system or Administrative order of the company to deal with

the environmental issues and for ensuring compliance with the environmental

clearance conditions? Details of this system may be given.

(iv) Does the company have system of reporting of non compliances / violations of

environmental norms to the Board of Directors of the company and / or shareholders

or stakeholders at large? This reporting mechanism shall be detailed in the EIA report

10. Details regarding infrastructure facilities such as sanitation, fuel, restroom etc. to be

provided to the labour force during construction as well as to the casual workers including

truck drivers during operation phase.

11. Enterprise Social Commitment (ESC):

• Adequate funds (at least 2% of the project cost) shall be earmarked towards the

Enterprise Social Commitment based on Public Hearing issues and item-wise details

along with time bound action plan shall be included. Socio-economic development

activities need to be elaborated upon.

12. Any litigation pending against the project and/or any direction/order passed by any Court

of Law against the project, if so, details thereof shall also be included. Has the unit

received any notice under the Section 5 of Environment (Protection) Act, 1986 or relevant

Sections of Air and Water Acts? If so, details thereof and compliance/ATR to the

notice(s) and present status of the case.

13. A tabular chart with index for point wise compliance of above TOR.

14. Details on list of hazardous chemicals to be stored alongwith storage quantities at the

facility, their category (as per MSIHC Rules), MSDS.

15. Mode of receiving hazardous chemicals in isolated storages and mode of their dispatch.

16. Layout plan of the storage tanks and other associated facilities.

17. Details on types and specifications of the storage facilities including tanks, pumps,

piping, valves, flanges, pumps, monitoring equipments, systems for emissions control

safety controls including relief systems.

18. Arrangements to control loss/leakage of chemicals and management system in case of

leakage.

19. Risk Assessment & Disaster Management Plan:

• Identification of hazards

• Consequence Analysis

• Details of domino effect of the storage tanks and respective preventive measures including distance between storage units in an isolated storage facility.

• Onsite and offsite emergency preparedness plan.

The matter shall be discussed after submission of final EIA report with incorporation

of public hearing comments/observations.

Minutes of 228th

SEAC Meeting Dated 23/07/2015

Page 24 of 52

12. Solid Waste Management, Bhadohi Cluster (Pipris) Project at ARaji No-11139,

1257, 1258, 1283, 1284, 1289, 1290-1297 & 1299, Vill-Piprish, Bhadohi (Area-7.603

Hac)- Sri Brij Mohan Varma, Project Manager, Unit-38, C & DS, UP Jal Nigam,

Raj Vill, Chandi Tiraha, Robertsganj, Sonbhadra. File No. 2897/AD-Sub.

The project proponent did not appear. The committee discussed and deliberated that

project fie should be closed and should be opened only after request from the project proponent. The file shall not be treated as pending at SEIAA/SEAC.

13. “Tannery Unit (Raw Hides/Skins to Finished Leather)” At Plot No.-F-15, H-67, H-

68, H-69, H-70, H-71, Village Jhajhri, UPSIDC Industrial Area, Site-Ii, District

Unnao, U.P. M/s Swastik Bone & Gelations Pvt. Ltd. Sri Rajeev Mehrotra, MD, C-

5/2, Moti Nagar, Guttaiya, Kanpur. File No. 2990/DD-Sh.

The committee noted that an application dated 31/03/2015 was made by the project

proponent for environmental clearance of “Tannery Unit (Raw Hides/Skins to Finished

Leather)” at Plot No.-F-15, H-67, H-68, H-69, H-70, H-71, Village Jhajhri, UPSIDC

Industrial Area, Site-II, District Unnao, U.P. M/S Swastik Bone & Gelations Pvt. Ltd.

A presentation was made by Shri Rajeev Mehrotra, Managing Director, project

proponent along with their consultant M/s Perfact Enviro Solutions Pvt. Ltd. The proponent,

through the documents submitted and the presentation made, informed the committee that:-

1. The environmental clearance is sought for “Tannery Unit (Raw Hides/Skins To

Finished Leather)” at Plot No.-F-15, H-67, H-68, H-69, H-70, H-71, Village Jhajhri,

UPSIDC Industrial Area, Site-Ii, District Unnao, U.P. M/S Swastik Bone & Gelations

Pvt. Ltd.

2. Leather requirement is increasing gradually and different variety of the finished

leather is in demand. To fulfil this demand M/s Swastik bone & Gelatines Pvt. Ltd. is

proposed to develop Tannery unit (raw hides/skins to finished leather) .

3. The proposed “Tannery Unit” is proposed to be at Plot No. F-15, H-67, H-68, H-69,

H-70, H-71, UPSIDC Industrial area, Site-II, Village-Jhajhari, Unnao, U.P.The land

has been allotted by U.P. State Industrial Development Corporation (UPSIDC). 4. The land of 5392.75 sqm has been allotted on lease to M/s Swastik bone & gelatines

Pvt. Ltd. 5. A tannery unit having capacity of 300 hides/skins per day i.e 7.2 TPD (raw

hides/skins to finished leather) has been proposed to meet with the increased demand of the finished leather.

6. Land use details of the project is as follows: Land Use Area in sq. m. %

Total Plot area 5392.75 100

Ground Coverage 2157.10 40

Green Spaces 1617.83 30

Road & Parking 1617.82 30

7. Salient features details are as follows; Description Details

Proposed Project Proposed Tannery Unit (Raw hides & skins to finished Leather)

Capacity 300 Hides/Skins per day i.e. 7.2 TPD (raw hides & skins to finished

leather)

Total Plot Area 5392.75 sq. meter

Manpower 100 persons

Water Requirement (KLD) 335 KLD

Waste Water Discharge 212 KLD

fresh water Requirement 163 KLD

ETP Capacity 230 KLD

Power Requirement (KW) 250 KVA

Source of Power U.P. Electricity Board

Minutes of 228th

SEAC Meeting Dated 23/07/2015

Page 25 of 52

Power Backup 1 x 250 KVA

Fuel: Low Sulphur Diesel of 6-8 Lt/Hr shall be used for D.G. Sets.

Boiler: The multi fueled Boiler of 3.0 TPH capacity shall be installed.

Fuel: Steam Coke of 1.5 TPD shall be used for boiler.

Capacity of boiler 3 TPH

No. of Rain water harvesting pits 1 nos.

8. Raw material details with daily consumption: S. No. Item Per hide/skin in kg Total (tons/day)

1 Raw Hides/skins 24 7.2 (300 Hides/Skins)

2 Hydrated lime 1.2 0.36

3 Sodium sulphide 0.54 0.162

4 Basic chrome sulphate 1.44 0.432

5 Sulphuric acid 0.54 0.162

6 Common salt 1.68 0.504

7 Sodium Bicarbonate 0.54 0.162

8 Ammonium Sulphate 0.72 0.216

9 Sodium Format 0.24 0.072

9. Product details are as follows: Particular Hides/Skins per day weight of Hides/Skins in

Kg per day

Weight of Hides/Skins in

Tons per day

Product-

Finished

Leather

300 hides/skins per day

(raw hide to finished leather)

(Average weight 20 Kg/hide)

6000 kg/day 6.0 TPD

10. Machinery details are as follows: S.NO QTY DESCRIPTION

1. 4 WOODEN DRUMS FOR TANNING

2. 2 LIMING FLESHING

3. 1 SAMMYING

4. 1 SPLITTING

5 1 SHAVER

6. 1 BUFFING

7 1 TROGGLING 100 PLATES

8 1 MEASURING

9 ETP AND OTHERS

11. Water management details are as follows:

• Total water requirement : 335 KLD (22.6 KL/tonne of hides/skins)

• Source : UPSIDC Supply

• Fresh water requirement : 163 KLD

• Treated Water requirement : 172 KLD

• Waste Water Discharge : 212 KLD (28 KL/tonne of hides/skins)

• ETP Capacity : 230 KLD

Usage Population Factor in

LPCD

Total Water requirement in

KLD

Waste Water

Discharge in KLD

Domestic

Staff 100 45 5

Visitor 10 15 1

Sub-Total 6 5

Process 245 202

Boiler 70 5

Gardening 4 Nil

Cooling 10 Nil

Total 480 335 KLD 212 KLD

12. Waste generation and its management details are as follows; Municipal solid waste

Category Type of Waste Color of Bins Disposal Method Total Waste

(Kg/day)

Bio Degradable Organic Waste Green Vermi-composting site 12

Minutes of 228th

SEAC Meeting Dated 23/07/2015

Page 26 of 52

within the project site

Non-Biodegradable Recyclable Waste Blue Authorized Recycler 4

Non-Biodegradable Inert Waste Black Nearby Landfill Site 1

Total 17 Kg/day

Process waste

Process

Waste

Waste In

kg/Hide

Total

Waste

(In Kg/day)

Total

Waste

(In

TPD)

Disposal method

Fleshing 2 600 0.6 Fleshing will be sold to glue manufacturers and dog

chew

Shaving 1 300 0.3 Shaver dust will be sold to leather board

manufacturer

Trimming 1 300 0.3 Trimming of splitting will be sold to lower quality

of leather goods manufacture

Total 1200

Kg/day

1.2 TPD

Hazardous Waste

Process Waste Proposed Disposal method

Used Oil 5 ltr/month Used oil generated from machineries/D.G. Set will be carefully stored

in HDPE drums in isolated covered facility. The used oil will be sold to

vendors authorized by Central Pollution Control Board for the treatment of the same. Suitable care will be taken so that spills / leaks

of used oil from storage could be avoided.

ETP Sludge 340 Kg/day Sludge from ETP covered under hazardous waste. It will be stored in the

impervious pit and finally disposed off at secured land fill.

MEE Residue 175 Kg/day Salts from the MEE shall be generated & disposed of at Secured land

fill at TSDF at Unnao, U.P.

13. The project proposals are covered under category 4"f" of EIA Notification, 2006.

The Committee discussed the matter and recommended following terms of reference

for preparation of EIA. The Committee also directed that EIA should strictly follow the methods of monitoring and analysis, Annexure-IV: guidance for assessment of the

representativeness and reliability of baseline environmental attributes detailed under EIA manual January, 2001 and the other guidelines in the matter.

1. Approved layout plan of the project by UPSIDC. 2. Compliance of the conditions a stipulated under charter on "Corporate Responsibility

for Environmental Protection (CREP). 3. Greenbelt plan showing 33% of total plot area and pattern.

4. Sources of water and its availability alongwith permission from competent authority. 5. Water Conservation measures proposed in the project.

6. Plans for effluent treatment and disposal including Chrome recovery. Plans for zero liquid discharge.

7. Emergency Plan for effluent management during process disturbances.

8. Plans for Hazardous and solid waste management/disposal and authorization.

9. Plans for rooftop rain water harvesting.

10. Ground water Quality around ETP. Guard pond, solar evaporation pond and landfill

site.

11. Plans for annual environmental auditing.

12. Plans for infrastructure facilities such as water supply, fuel, sanitation etc for

construction workers so as to avoid felling of trees and pollution of water.

13. Noise levels in and around the plant area.

14. Occupational health surveillance plan for the workers.

15. Environmental Corporate Responsibility (ECR) plan along with budgetary provision

amounting to 2% of project cost (Rs. 12 Lac) shall be prepared and approved by

Board of Directors of the company. A copy of resolution as above shall be submitted to the authority alongwith list of beneficiaries with their mobile nos./address.

Minutes of 228th

SEAC Meeting Dated 23/07/2015

Page 27 of 52

14. 20 MW Co-generation Power Plant at Vill-Sujanpur, Tehsil & Distt-Badaun- Sri K

K Sharma, Vill-Sujanpur, Tehsil & Distt-Badaun. File No. 3002/AD-H

The project proponent did not appear. The committee discussed and deliberated that

project fie should be closed and should be opened only after request from the project

proponent. The file shall not be treated as pending at SEIAA/SEAC.

15. Proposed “Revamping of HPCL” Meerut Oil Installation. Sri Satish Kumar, Sr.

Instt. Manager, HPCL, Meerut IRD. File No. 3196/OSD-T

The committee noted that an application dated 01/06/2015 was made by the project

proponent for environmental clearance of Proposed “Revamping of HPCL” Meerut Oil

Installation, U.P. M/s Hindustan Petroleum Corp. Ltd.

A presentation was made by Shri Satish Kumar, Sr. Instt. Manager, HPCL, project

proponent along with their consultant M/s Mantec Consultants Pvt. Ltd., Noida. The

proponent, through the documents submitted and the presentation made, informed the

committee that:-

1. The environmental clearance is sought for Proposed “Revamping of HPCL” Meerut

Oil Installation, U.P. M/s Hindustan Petroleum Corp. Ltd.

2. HPCL Meerut Oil Terminal was constructed in Aug-1994 and supplying Petroleum

products to 8 districts from last 20 years.

3. HPCL is planning to augment and revamp the existing Meerut (UP) Oil terminal to

meet the increasing demand of petroleum products in the National Capital Region

(NCR) and UP west of India.

4. HPCL Meerut Terminal after augmentation and revamp shall be energy efficient,

environment- friendly and shall meet the increasing requirement of MS (Motor Sprit),

HSD (High Speed Diesel) and SKO (Superior Kerosene Oil) of 9 cities in UP west.

5. The company intends to establish storage and distribution facilities for 29625 KL

petroleum product (MS, HSD, SKO and Ethanol) at Village- Vedvyaspuri, Pootha

Partapur industrial area in Meerut district of Uttar-Pradesh.

6. Projected details of the project is as follows:

ACTUAL PROJECTED (KL)

2013-14 2016-17 2017-18 2018-19 2019-20 2020-21

MS 73036 144306 156572 169881 184320 199988

HSD 141495 377374 401903 428027 455849 485479

TMF 214531 521680 558475 597908 640169 685467

ACTUAL PROJECTED (KL)

2013-14 2016-17 2017-18 2018-19 2019-20 2020-21

Vol/Month 17878 43473 46540 49826 53347 57122

Vol/Day 715 1739 1862 1993 2134 2285

TT/Day 45 109 116 125 133 143

Peak Demand 30 % 58 141 151 162 173 186

65% mixed Loads 38 92 98 105 113 121

30% Full HSD 17 42 45 49 52 56

5 % Full MS 3 7 8 8 9 9

Mixed Bay 3 8 8 9 9 10

HSD 1 4 4 4 4 5

MS 0 1 1 1 1 1

Total 4 13 13 14 14 16

Minutes of 228th

SEAC Meeting Dated 23/07/2015

Page 28 of 52

Bays Required considering 2 TTs / Hr / Bay

7. The proposed project having storage and distribution facilities of petroleum products

(MS, HSD, SKO and Ethanol).

8. Located at Villages- Vedvyaspuri, Pootha Partapur Industrial area in Meerut district

of Uttar-Pradesh, adjacent to NH-119 and NH-58. The area of the terminal 12.57

Acres (5.07 Hectare).

9. This project will consist of the following facilities:

� Total storage capacity of petroleum products- 29625 KL

(MS-13245KL, HSD-13545 KL, SKO-1845KL and Ethenol-990KL)

� 2 Nos. of 8 Bay TT Gantry.

� ETP, Fire fighting system, Electrical system, Pump house, pipeline, Boundary walls,

Internal roads, Truck Parking, TLF pump house, TWD pump house, Admin building,

First-Aid post, Bore-well, DG Sets etc.

10. Salient features of the project are as follows: PARTICULARS DETAILS

Name of Project Revamping of HPCL Meerut oil Installation.

Proposed Capacity Class A-14235 KL, Class B-15390 KL

Category of Project Category B

Location Village- Vedvyaspuri, Pootha Partapur industrial area, District–Meerut, U.P.

Corner

Co-ordinates (1)28⁰57’1.40”N 77⁰39’31.02” (2)28⁰56’57.08”N 77⁰39’37.03”

(3)28⁰56’54.44”N 77⁰39’26.58” (4)28⁰56’50.91”N 77⁰39’33.82”

Toposheet No (SoI) Study Area : Toposheet No 53G12, 53H9, 53H13,

Land Requirement 12.57 Acres (5.07 Hectare)

Raw Water Requirement No raw water required for the storage and distribution of Petroleum product,

Water stored for firefighting purpose only.

Power supply UPSEB Maliyana (Partapur, Meerut) Substation through 250 KVA, 11KV/415V

transformer.

11. Existing and proposed capacity are as follows: S. No. Product Existing Capacity

(KL)

Increased Capacity (KL) Capacity After Revamp

(KL)

1. Class A 1940 12295 KL 14235 KL

2. Class B 7532 7858 KL 15390 KL

Total 9472 20153 29625

12. Area around the project site: PARTICULARS DETAILS

North MDA green belt (RAF Campus)

East Agriculture land

South Tank Wagon unloading siding ,Railway track and Agriculture land

West IOCL terminal

13. Terminal operation process is as follows:

• RECEIPT: Petroleum Products are received thru Tank wagons from Tank wagon

loading locations Bahadurgarh , HMEL as per monthly distribution plan .

• STORAGE: Petroleum Products are stored in closed storage tanks ( Internal

floating Roof, fixed cone roof, Underground tanks) . All the storage tanks are

connected to Tank wagon decantation Pumps and tank trucks loading pumps

through MS pipelines.

• DELIVERY: Delivery to retail outlets are done by tank trucks of capacity

12KL/18KL/20KL which are filled at Automated Tank truck loading gantry thru

centrifugal product pumps.

14. Water Sources:

Minutes of 228th

SEAC Meeting Dated 23/07/2015

Page 29 of 52

• The source of water supply will be met from existing underground water source

through bore wells, there are three numbers of bore wells provided within the

premises of terminal. The water is utilized for drinking and as well as fire fighting

purpose.

• Water is stored in above ground water tanks for fire fighting.

• Fire water line is kept pressurized by jockey pumps.

• Separate borewell for drinking and service water with water meters.

15. The project proposals are covered under category 6"b" of EIA notification, 2006, as

amended.

The committee noted that the proposal are covered under category 6"b" and it requires

scoping. The committee decided that EIA should strictly follow the guidelines prescribed in

annexure-III to the EIA notification of 2006. The proponents may prepare an EIA including

existing and proposed facilities based on following terms of reference /general guidelines:

1. Approved maps/plans by PASO and MDA.

2. Executive Summary.

3. Introduction:

(i) Details of the EIA Consultant including NABET accreditation.

(ii) Information about the project proponent.

(iii)Importance and benefits of the project.

4. Project Description:

(i) Cost of project and time of completion.

(ii) Products with capacities for the proposed project.

(iii) If expansion project, details of existing products with capacities and whether adequate

land is available for expansion, reference of earlier EC if any.

(iv) List of raw materials required and their source along with mode of transportation.

(v) Other chemicals and materials required with quantities and storage capacities.

(vi) Details of Emission, effluents, hazardous waste generation and their management.

(vii) Requirement of water, power, with source of supply, status of approval, water balance

diagram, man-power requirement (regular and contract).

(viii) Process description along with major equipments and machineries, process flow sheet

(quantative) from raw material to products to be provided.

(ix) Hazard identification and details of proposed safety systems.

(x) Expansion/modernization proposals:

a. Copy of all the Environmental Clearance(s) including Amendments thereto obtained

for the project from MOEF/SEIAA shall be attached as an Annexure. A certified copy

of the latest Monitoring Report of the Regional Office of the Ministry of Environment

and Forests as per circular dated 30th May, 2012 on the status of compliance of

conditions stipulated in all the existing environmental clearances including

Amendments shall be provided. In addition, status of compliance of Consent to

Operate for the ongoing Existing operation of the project from SPCB shall be attached

with the EIA-EMP report.

b. In case the existing project has not obtained environmental clearance, reasons for not

taking EC under the provisions of the EIA Notification 1994 and/or EIA Notification

2006 shall be provided. Copies of Consent to Establish/No Objection Certificate and

Consent to Operate (in case of units operating prior to EIA Notification 2006, CTE

Minutes of 228th

SEAC Meeting Dated 23/07/2015

Page 30 of 52

and CTO of FY 2005-2006) obtained from the SPCB shall be submitted. Further,

compliance report to the conditions of consents from the SPCB shall be submitted.

5. Site Details:

(i) Location of the project site covering village, Taluka/Tehsil, District and State,

Justification for selecting the site, whether other sites were considered.

(ii) A toposheet of the study area of radius of 10km and site location on

1:50,000/1:25,000 scale on an A3/A2 sheet. (including all eco-sensitive areas and

environmentally sensitive places).

(iii) Details w.r.t. option analysis for selection of site.

(iv) Co-ordinates (lat-long) of all four corners of the site.

(v) Google map-Earth downloaded of the project site.

(vi) Layout maps indicating existing unit as well as proposed unit indicating storage area,

plant area, greenbelt area, utilities etc. If located within an Industrial

area/Estate/Complex, layout of Industrial Area indicating location of unit within the

Industrial area/Estate.

(vii) Photographs of the proposed and existing (if applicable) plant site. If existing, show

photographs of plantation/greenbelt, in particular.

(viii) Landuse break-up of total land of the project site (identified and acquired),

government/ private - agricultural, forest, wasteland, water bodies, settlements, etc

shall be included. (not required for industrial area).

(ix) A list of major industries with name and type within study area (10km radius) shall be

incorporated. Land use details of the study area.

(x) Geological features and Geo-hydrological status of the study area shall be included.

(xi) Details of Drainage of the project upto 5km radius of study area. If the site is within 1

km radius of any major river, peak and lean season river discharge as well as flood

occurrence frequency based on peak rainfall data of the past 30 years. Details of

Flood Level of the project site and maximum Flood Level of the river shall also be

provided. (Mega green field projects).

(xii) Status of acquisition of land. If acquisition is not complete, stage of the acquisition

process and expected time of complete possession of the land.

(xiii) R&R details in respect of land in line with state Government policy.

6. Forest and wildlife related issues (if applicable):

(i) Permission and approval for the use of forest land (forestry clearance), if any, and

recommendations of the State Forest Department. (if applicable).

(ii) Landuse map based on High resolution satellite imagery (GPS) of the proposed site

delineating the forestland (in case of projects involving forest land more than 40 ha).

(iii) Status of Application submitted for obtaining the stage I forestry clearance along with

latest status shall be submitted.

(iv) The projects to be located within 10 km of the National Parks, Sanctuaries, Biosphere

Reserves, Migratory Corridors of Wild Animals, the project proponent shall submit

the map duly authenticated by Chief Wildlife Warden showing these features vis-à-vis

the project location and the recommendations or comments of the Chief Wildlife

Warden-thereon.

(v) Wildlife Conservation Plan duly authenticated by the Chief Wildlife Warden of the

State Government for conservation of Schedule I fauna, if any exists in the study area.

Minutes of 228th

SEAC Meeting Dated 23/07/2015

Page 31 of 52

(vi) Copy of application submitted for clearance under the Wildlife (Protection) Act,

1972, to the Standing Committee of the National Board for Wildlife.

7. Environmental Status:

(i) Determination of atmospheric inversion level at the project site and site-specific

micrometeorological data using temperature, relative humidity, hourly wind speed

and direction and rainfall.

(ii) AAQ data (except monsoon) at 8 locations for PM10, PM2.5, SO2, NOX, CO and

other parameters relevant to the project shall be collected. The monitoring stations

shall be based CPCB guidelines and take into account the pre-dominant wind

direction, population zone and sensitive receptors including reserved forests.

(iii) Raw data of all AAQ measurement for 12 weeks of all stations as per frequency given

in the NAQQM Notification of Nov. 2009 along with - min., max., average and 98%

values for each of the AAQ parameters from data of all AAQ stations should be

provided as an annexure to the EIA Report.

(iv) Surface water quality of nearby River (100 m upstream and downstream of discharge

point) and other surface drains at eight locations as per CPCB/MoEF&CC guidelines.

(v) Whether the site falls near to polluted stretch of river identified by the

CPCB/MoEF&CC, if yes give details.

(vi) Ground water monitoring at minimum at 8 locations shall be included.

(vii) Noise levels monitoring at 8 locations within the study area.

(viii) Soil Characteristic as per CPCB guidelines.

(ix) Traffic study of the area, type of vehicles, frequency of vehicles for transportation of

materials, additional traffic due to proposed project, parking arrangement etc.

(x) Detailed description of flora and fauna (terrestrial and aquatic) existing in the study

area shall be given with special reference to rare, endemic and endangered species. If

ScheduleI fauna are found within the study area, a Wildlife Conservation Plan shall be

prepared and furnished.

(xi) Socio-economic status of the study area.

8. Impact and Environment Management Plan:

(i) Assessment of ground level concentration of pollutants from the stack emission based

on site-specific meteorological features. In case the project is located on a hilly

terrain, the AQIP Modelling shall be done using inputs of the specific terrain

characteristics for determining the potential impacts of the project on the AAQ.

Cumulative impact of all sources of emissions (including transportation) on the AAQ

of the area shall be assessed. Details of the model used and the input data used for

modelling shall also be provided. The air quality contours shall be plotted on a

location map showing the location of project site, habitation nearby, sensitive

receptors, if any.

(ii) Water Quality modelling - in case of discharge in water body

(iii) Impact of the transport of the raw materials and end products on the surrounding

environment shall be assessed and provided. In this regard, options for transport of

raw materials and finished products and wastes (large quantities) by rail or rail-cum

road transport or conveyorcum-rail transport shall be examined.

(iv) A note on treatment of wastewater from different plant operations, extent recycled

and reused for different purposes shall be included. Complete scheme of effluent

Minutes of 228th

SEAC Meeting Dated 23/07/2015

Page 32 of 52

treatment. Characteristics of untreated and treated effluent to meet the prescribed

standards of discharge under E(P) Rules.

(v) Details of stack emission and action plan for control of emissions to meet standards.

(vi) Measures for fugitive emission control

(vii) Details of hazardous waste generation and their storage, utilization and management.

Copies of MOU regarding utilization of solid and hazardous waste in cement plant

shall also be included. EMP shall include the concept of waste-minimization,

recycle/reuse/recover techniques, Energy conservation, and natural resource

conservation.

(viii) Proper utilization of fly ash shall be ensured as per Fly Ash Notification, 2009. A

detailed plan of action shall be provided.

(ix) Action plan for the green belt development plan in 33 % area i.e. land with not less

than 1,500 trees per ha. Giving details of species, width of plantation, planning

schedule etc. shall be included. The green belt shall be around the project boundary

and a scheme for greening of the roads used for the project shall also be incorporated.

(x) Action plan for rainwater harvesting measures at plant site shall be submitted to

harvest rainwater from the roof tops and storm water drains to recharge the ground

water and also to use for the various activities at the project site to conserve fresh

water and reduce the water requirement from other sources.

(xi) Total capital cost and recurring cost/annum for environmental pollution control

measures shall be included.

(xii) Action plan for post-project environmental monitoring shall be submitted.

(xiii) Onsite and Offsite Disaster (natural and Man-made) Preparedness and Emergency

Management Plan including Risk Assessment and damage control. Disaster

management plan should be linked with District Disaster Management Plan.

9. Occupational health:

(i) Plan and fund allocation to ensure the occupational health & safety of all contract and

casual workers

(ii) Details of exposure specific health status evaluation of worker. If the workers' health

is being evaluated by pre designed format, chest x rays, Audiometry, Spirometry,

Vision testing (Far & Near vision, colour vision and any other ocular defect) ECG,

during pre placement and periodical examinations give the details of the same. Details

regarding last month analyzed data of above mentioned parameters as per age, sex,

duration of exposure and department wise.

(iii) Details of existing Occupational & Safety Hazards. What are the exposure levels of

hazards and whether they are within Permissible Exposure level (PEL). If these are

not within PEL, what measures the company has adopted to keep them within PEL so

that health of the workers can be preserved,

(iv) Annual report of heath status of workers with special reference to Occupational

Health and Safety.

10. Corporate Environment Policy:

(v) Does the company have a well laid down Environment Policy approved by its Board

of Directors? If so, it may be detailed in the EIA report.

(vi) Does the Environment Policy prescribe for standard operating process / procedures to

bring into focus any infringement / deviation / violation of the environmental or forest

norms / conditions? If so, it may be detailed in the EIA.

Minutes of 228th

SEAC Meeting Dated 23/07/2015

Page 33 of 52

(vii) What is the hierarchical system or Administrative order of the company to deal with

the environmental issues and for ensuring compliance with the environmental

clearance conditions? Details of this system may be given.

(viii) Does the company have system of reporting of non compliances / violations of

environmental norms to the Board of Directors of the company and / or shareholders

or stakeholders at large? This reporting mechanism shall be detailed in the EIA report

11. Details regarding infrastructure facilities such as sanitation, fuel, restroom etc. to be

provided to the labour force during construction as well as to the casual workers including

truck drivers during operation phase.

12. Enterprise Social Commitment (ESC):

• Adequate funds (at least 2 % of the project cost) shall be earmarked towards the

Enterprise Social Commitment based on Public Hearing issues and item-wise details

along with time bound action plan shall be included. Socio-economic development

activities need to be elaborated upon.

13. Any litigation pending against the project and/or any direction/order passed by any Court

of Law against the project, if so, details thereof shall also be included. Has the unit

received any notice under the Section 5 of Environment (Protection) Act, 1986 or relevant

Sections of Air and Water Acts? If so, details thereof and compliance/ATR to the

notice(s) and present status of the case.

14. A tabular chart with index for point wise compliance of above TOR.

15. Details on list of hazardous chemicals to be stored alongwith storage quantities at the

facility, their category (as per MSIHC Rules), MSDS.

16. Mode of receiving hazardous chemicals in isolated storages and mode of their dispatch.

17. Layout plan of the storage tanks and other associated facilities.

18. Details on types and specifications of the storage facilities including tanks, pumps,

piping, valves, flanges, pumps, monitoring equipments, systems for emissions control

safety controls including relief systems.

19. Arrangements to control loss/leakage of chemicals and management system in case of

leakage.

20. Risk Assessment & Disaster Management Plan:

• Identification of hazards

• Consequence Analysis

• Details of domino effect of the storage tanks and respective preventive measures

including distance between storage units in an isolated storage facility.

• Onsite and offsite emergency preparedness plan.

The matter shall be discussed after submission of final EIA report with incorporation of public hearing comments/observations.

16. Up-Gradation of Baitalpur LPG Plant (OISD-169) to full-fledged OISD-144 Plant

inclusive of all facilities Sri Rajwinder Singh , BPCL. File No. 3200/AD-Sub.

The project proponent did not appear. The committee noted that the applicant has

submitted a request letter for including the matter in next meeting. The committee directed to

defer the matter for next meeting.

Minutes of 228th

SEAC Meeting Dated 23/07/2015

Page 34 of 52

17. Group Housing Project, Located at Plot No-07, Sector-P-4, Builders Area, Greater

Noida, U.P. Sri Gagan Gupta, Astt. Director, (Tech), Central Government

Employees Welfare Housing Organisation, 6th Floor, A Wing, Janpath Bhawan,

Janpath, Lucknow. File No. 2257/AD-H

The committee noted that the matter was earlier discussed in SEAC meting dated

23/03/2015 wherein the project proponent was directed to submit following information:

1. Copy of layout plan alongwith covering letter submitted to GNIDA.

2. All building plans/Services plans/sewerage plan/drainage plan alongwith certificate

from architect that the plans have been prepared in accordance to Development

Authority Bye-laws.

3. Physical features within 30 m of the project sites with their ownership.

4. Details of approach roads be submitted with width on map.

5. Structural stability certificate duly signed by structural engineer.

6. Area details showing proposed uses as residential, commercial, parks, parking, roads,

other services, facilities of the project also in percentage.

7. Provision of 10% EWS/LIG in the project.

8. Roof top water only to be harvested in rain water harvesting pits. Plan should be

submitted.

9. Solid waste disposal to be done at site. Plan should be submitted.

10. NOC from AAI.

11. Plan for discharge of storm water.

12. Provision of 10% EWS/LIG in the project.

13. Provision for organic waste convertor shall be made and an undertaking shall be

submitted in the regards.

14. Project cost and corresponding CSR cost (2% of project cost) with details under

commitment from Board of Directors.

The project proponent submitted their replies through letter dated 12/05/2015. The

project proponent submitted layout plan alongwith copy of building permit fee submitted to

Greater Noida Authority. Copy of all building plans alongwith certificate from Architect and

undertaking for same, physical features within 30 m of the project, details of approach road,

structural stability certificate, area details showing various proposed uses as residential,

commercial, parks, parking roads and other services, rooftop water harvesting plan, solid

waste disposal plan, NOC from AAI, plan for discharge of storm water, provision from

organic waste convertor has been submitted. The project proponent also informed that

provision for EWS is not mentioned in Greater Noida bye-laws and also this project is for

Govt. employees, not for profit generation. The committee deliberated that above statement

regarding provision for EWS should be supported with documents endorsed by GNIDA.

A presentation was made by Shri Gagan Gupta, authorized representative of project

proponent along with their consultant M/s Grass Roots Research & Creation India (P) Ltd.

The proponent, through the documents submitted and the presentation made, informed the

committee that:-

1. The environmental clearance is sought for Group Housing Project Group Housing

Located at plot No-07, Sector-P-4, Builders Area, Greater Noida, U.P. M/s Central

Govt. Employees Welfare Housing Organization.

2. Salient features of the project is as follows:

Minutes of 228th

SEAC Meeting Dated 23/07/2015

Page 35 of 52

Project Features Description

Plot Area 1,53,832.00 m

2

Built Up Area 4,02,030.44 m

2

Estimated Population

Total no. of D.U.

11,048 Nos. (9,608 General, Staff 480 & Visitors

960)

2,135

Estimated Water Requirement

Construction Phase

Operation Phase

2010 ML (Agency: Private Water Tanker)

954 KLD (Fresh water = 598 KLD)

(Agency: Municipal Water Supply)

Estimated Wastewater Generation 734 KLD

Power Demand

Power Back-up

6,650 kVA

4,510 kVA (2*1500 KVA+ 1010 KVA+ 500

KVA)

Source of Power UPPCL (Uttar Pradesh Power Corporation Limited )

Total no. of RWH pits 25

Solid Waste Generation Approx 5,071 kg/day

Parking Facilities

Required

Proposed

As per MoEF norms: 2,913 ECS

As per Greater Noida Bye Laws : 5,288 ECS

5310 ECS

3. Area details of the project is as follows:

S. No. Particulars Area (in m2

)

1. Plot Area 1,53,832.00

2. Permissible Ground Coverage (@ 35% of the Plot Area) 53,841.20

3. Proposed Ground Coverage (@ 10.84% of the Plot Area) 16,669.81

4. Ground Coverage for Future Expansion (@ 22.98% of the Plot Area) 35,351.28

5. Proposed Ground coverage for Facilities

• Community Hall

• Nursing Home

• Nursery School

• Conv. Shopping

• Religious Building

1,820

300

300

400

600

220

6. Total Permissible FAR

• Permissible FAR (@ 2.75 of the Plot Area)

• Additional FAR (@ 15% of the Permissible Area)

4,86,493.7

4,23,038.00

63,455.70

7. Proposed FAR

• Residential Towers (@1.63 of the Plot Area)

• Additional FAR

2,81,552.9

2,51,031.94

30,520.96

8. Proposed FAR for Facilities

• Community Hall

• Nursing Home

• Nursery School

• Conv. Shopping

• Religious Building

9,800

2,000

2,750

1,500

3,000

550

9. Basement (1 ) 94,007.73

10. Stilt area 16,669.81

11. Open area 99,990.80

12. Landscape area (@ 67% of the Open area) 67,597.41

13. Built up Area 4,02,030.44

14. Maximum Height of Building 51.15 m

4. Water requirement of the project is as follows:

SI.

No.

Description Area

(in m2

)

Total

Occupancy

Rate of

water

demand

(lpcd)

Total Water

Requirement

(KLD)

Minutes of 228th

SEAC Meeting Dated 23/07/2015

Page 36 of 52

A. Domestic Water

1. Group Housing

• Residents

• Staff (5%)

• Visitors (10%)

2,91,352.9 9608

480

960

86

30

15

826

14

14

Total Domestic Water Requirement (A) 854 KLD

B. Horticulture and Landscape

development

67,597.41 1

lt./sqm/da

y

68

C. DG Sets Cooling (2 x 1500 KVA+

1010 KVA+ 500 KVA)

0.9

lt./KVA/h

r*

32

Grand Total (A+B+C) 954 KLD

5. A waste water calculation detail is as follows:

Domestic Water Requirement 854 KLD

• Fresh (@ 70% of domestic) 598 KLD

• Flushing (@ 30% of domestic) 256 KLD

Waste Water Generated

(@ 80% fresh + 100% flushing)

478 +256 =734 KLD

6. The Project proposal falls under Category 8(b) of EIA Notification, 2006 (as

amended).

The committee discussed the matter and recommended grant of environmental

clearance on the project proposals alongwith general conditions as earlier prescribed by the authority for construction project and following specific conditions subject to submission of

provisions of GNIDA regarding EWS and submission of all maps/services plans approved by

GNIDA:

1. If there will be any change in map and plan as from approved map, fresh EC will have to be obtained as per rule.

2. 03 m peripheral green shall be provided around the project inside the project boundary. 3. 15% area of the total plot area shall be compulsorily made available for the green belt

development including the peripheral green belt. 4. Project falling with in 10 Km. area of Wild Life Sanctuary is to obtain a clearance from

National Board Wild Life (NBWL) even if the eco- sensitive zone is not earmarked.

5. Criteria/ norms provided by competent Authority regarding the seismic zone be

followed for construction work. Provision of alarm system, to timely notify the

residents, in case of occurrence of earthquake/other natural disasters/fire should be

provided. A well defined evacuation plan should also be prepared and regular mock

drills should be arranged for the residents. Rise of stairs should be constructed in a way,

so that it should provide smooth movement.

6. For the treatment for total sewage, a full-fledged STP is to be provided with 20% more

capacity than waste water generated during operation phase.100% waste water is to be

treated in captive STP conforming to prescribed standards of receiving body for

designated use. Monitoring of STP to be done daily till its stabilization.

7. Dual plumbing should be adopted. Recycling of water as proposed shall be undertaken

with regular testing and monitoring of treated water. 8. Dedicated power supply for STPs is to be ensured during operation. Sludge of STP is to

be used in-house as manure and surplus manure should be managed by giving it to end users. STP shall be suitably located nearest to back side boundary with shortest out let.

Minutes of 228th

SEAC Meeting Dated 23/07/2015

Page 37 of 52

Operation and the maintenance cost of the STP shall also be informed along with the

compliance of the E-waste and municipal solid waste disposal.

9. Environmental Corporate Responsibility (ECR) plan along with budgetary provision

amounting to 2% of total project cost shall be prepared and approved by Board of

Directors of the company. A copy of resolution as above shall be submitted to the

authority. A list of beneficiaries with their mobile nos./address should be submitted

alongwith six monthly compliance reports.

10. LEDs should be used in all common areas and corridors. 100% solar lighting is to be provided in the open areas/ stairs cases.

11. Parking guideline as per GNIDA Authority should be followed. Parking for disabled persons should be explored.

12. All entry/exit point should be bell mouth shaped. 13. To discharge excess treated waste water into public drainage system, permission from

the competent authority to be taken prior to any discharge. 14. 100 % provision of Rain Water Harvesting is to be made. RWH shall be initially done

only from the roof top. RWH from green and other open areas shall be done only after permission from CGWB.

15. An underground Pucca tank for collection/reuse of rain water may be constructed.

16. Height of the stack should be provided based on combined DG sets capacity and be 6mt

higher than the tallest building.

17. Post project monitoring for air, water (surface + ground), Stack noise of D.G. sets, STP

to be carried out as CPCB Guidelines.

18. Crèche to be provided during the construction/operation phase.

19. Provision of separate room for senior citizen with proper amenities shall be made.

20. Protection shall be provided on the windows of the high rise flats for security of

residents.

21. EWS/LIG housing provisions shall be made as per development authority bye-laws.

22. Unless and until all the environmental issues are sorted out the occupancy will be restricted and would be only allowed after achieving the Permission from the competent

authority. 23. The project proponent shall ensure that the project site does not attract/infringe any

buffer zone of no activity identified/declared under law. 24. For any extraction of ground water, prior permission from CGWB shall be taken.

25. Sprinkler to be used for curing and quenching and ready mix concrete may be used for construction.

26. Possibilities of use of treated waste water for irrigation purposes should be explored. Drip irrigation should be tried upto extent possible. No fresh water will be used for

irrigation purpose.

27. Mobile toilets, safe drinking water facility, sanitation facility and eco friendly fuels etc.

Shall be made available to the temporary residents/workers at the project site including

the proper treatment and the disposal of the wastes.

18. Group Housing Project at at Plot No.GH-P4, Sector 25 , Jaypee Greens Sports City,

District- Gautam Budh Nagar, Uttar Pradesh, Sri Pramood Goel, MD, D-1, Sector-

3, Noida. File No. 2382/SPO-V

The committee noted that the matter was earlier discussed in SEAC meting dated

23/03/2015 wherein the project proponent was directed to submit following information;

1. Approved layout plan of Jaypee Project showing proposed project alongwith

Environmental clearance issued to the Jaypee project.

2. Structural stability plan alongwith certificate of architect.

Minutes of 228th

SEAC Meeting Dated 23/07/2015

Page 38 of 52

3. List of basic facilities committed by Jaypee in favour of proposed project alongwith

agreement made in this regard.

4. Area details showing proposed uses as residential, commercial, parks, parking,

roads, other services, facilities of the project also in percentage.

5. Apart from rain water harvesting from roof tops, other rain water may be collected

in pond/water body and may be used for grading or other necessary purposes. Plan

in this regard should be submitted.

6. Project cost and corresponding CSR cost (Rs. 3.0 crore) with details under

commitment from Board of Directors.

7. Use of reflecting paints on rooftops and side walls of the buildings.

8. Provision of play school/crèche is to be made as per population requirement.

The project proponent submitted their replies thorugh letter dated 28/052015. A

presentation was made by Shri Ashwani Mittal, authorized representative of project

proponent along with their consultant M/s Ascenso Enviro Private Limited. The proponent,

through the documents submitted and the presentation made, informed the committee that:-

1. The environmental clearance is sought for Group Housing Project at at Plot No.GH-

P4, Sector 25, Jaypee Greens Sports City, District- Gautam Budh Nagar, Uttar Pradesh, M/s VGA Developers Pvt. Ltd.

2. Area details are as follows: S. No. Particulars Area in

Sq.m.

In percentage (%)

1 Plot area 20,071.00 ……

2 Permissible Ground Coverage 5,017.75 25% of Plot area

3 Proposed Ground Coverage

• Residential Ground Coverage

• Community Ground Coverage

4,946.15

4,679.75

266.40

24.64% of Plot area

94.61% of Proposed Gr. Coverage

5.38% of Proposed Gr. Coverage

4 Permissible FAR 60,213.00 300 % of Plot area

5 Proposed FAR

• Residential FAR

• Community FAR

59,305.72

59,039.32

266.40

295.47% of Plot area

99.55% of Proposed FAR

0.45% of Proposed FAR

6 Permissible service Area 9,031.95 15% of Permissible FAR

7 Proposed Service Area 5,809.26 9.64% of Permissible FAR

8 ESS Area 250.00 ……

9 Stilt area 743.63 ……

10 Total Basement Area

• Upper Basement Area

• Lower Basement Area

32,278.96

16,139.48

16,139.48

…….

50% of total Basement Area

50% of total Basement Area

11 Open area (Plot Area – Proposed Ground Coverage)

15,124.85 75.35% of Plot Area

12 Landscape required 50% of open area 7,562.426 37.67 % of Plot area

13 Landscape provided @50.53% of open area 7,643.215 38.08 % of Plot area

14 Built up area

(FAR + Basement + Stilt + Permissible FAR)

98,137.57 ……

3. Facility wise area details are as follows: S.no. Category Area as per approved

Jaypee Sports City Plan

(in sq. m.)

Area as per Site layout of Project

Site

(in sq. m.)

1 Residential 3131700 (31.3%) 59,305.72

2 Commercial 1227100 (12.3%) ….

3 Recreational green(parks) 771200 (7.7%) …..

4 Open and Green 526700 (5.3%) 7,643.215(38.08%) : green area

15,124.85 (75.53%): open area

5 Roads and Transportation 858800 (8.6%) 7,481.64 (37.27%)

6 Roads and other circulation 350200 (3.5%)

Minutes of 228th

SEAC Meeting Dated 23/07/2015

Page 39 of 52

7 Others(educational facility,

community, health facility,

utility)

500100 (5.4%) …..

4. Salient features of the project is as follows: Name and Location of the Project Group Housing Project at Plot No-GH-P4, Jaypee Greens Sports

City District-Gautam Budh Nagar, Uttar Pradesh

Developers of the project M/s VGA Developers Pvt. Ltd.

Total Plot Area 20,071.00 m

2

Built-up Area(Proposed FAR + Basement

area + Services area) 98,137.57 m

2

.

Total Water Consumption 278 KLD

Total Freshwater Requirement 198 KLD Source: Municipal Supply

Power Requirement 1932.30 kW

Source: NPCL

Power Backup 2 DG Sets of total capacity of 1760 KVA

(1x1010 + 1x750 KVA )

Total Parking provided 762 ECS

Solid Waste to be Generated 1407.3 kg / day

No. of RWH Pits 5 pits

5. Building blocks details are as follows;

S. No. Type of Building Storey

1. Tower-A G+17

2. Tower-B

3. Tower-C

4. Tower-D

5. Tower-E

6. Tower-F

7 Villas (V-1 to V-16) G+2

6. Population details are as follows

S. No. Types No of unit / Area

in sq.m.

Person Per

Unit

Population

1 Residential population

• Dwelling Units

• Villas

608 nos.

16 nos

4.5 2,808

2 Community Population 266.401 1 person/1.5 sq. m

of FAR

177

3 Visitor (10 % of Residential Population) 280

Total Population 3,265

7. Water calculation details are as follows:

S.

No.

Description Area /

Population

Unit water

consumption

(liters)

Total Water

required

(KLD)

Water for

domestic

use (KLD)

Flushing/

Recycled

water (KLD)

1 Residential

Population

2,808 86 241.4880 182.520 58.968

2 Community Population

177 15 2.6550 1.062 1.593

3 Visitors 280 15 4.2120 1.685 2.527

4 Horticulture 7,556.453 1ltrs./sq.m 7.6432 …… ….

5 DG Cooling 1,760 … 9.5 … …

6 Swimming Pool … … 10 … …

Total water requirement 275.5087 185.267 63.088

7 Firefighting Tank 1% of total water requirement 2.75 … …

Sub Total water requirement 278.5 … …

says 278 185 63

8. Waste water calculation details are as follows:

Details Water (KLD)

Water requirement for domestic purpose 185

Minutes of 228th

SEAC Meeting Dated 23/07/2015

Page 40 of 52

Wastewater to be generated from domestic use (@ 80% of domestic

requirement)

148

Water requirement for Flushing Purpose 63

Wastewater to be generated from Flushing

(@ 100% of flushing requirement)

63

Waste water from Swimming Pool 8

Total waste water generated (148+63+8) = 219

9. Parking calculation details are as follows:

Description As Per YEIDA Building Byelaws Parking

(E.C.S.)

Parking

Required

Residential ECS required @1 ECS/80 sq m FAR area

FAR Area = 59,305.72 sq m

= 741.32 ECS

Says 742 ECS

Total ECS Required 742 ECS

Parking

Proposed

In Lower Basement Area @ 1ECS/30m2

Lower Basement Area (15,164.847 m2

)

371 ECS

In Upper Basement Area @ 1ECS/30 m2

Upper Basement Area (15,670.958 m2

)

393 ECS

Total ECS provided 393+371 = 762

10. Solid waste generation details are as follows: S. No. Category of

Solid Waste

Waste

Generation

Rate

Total Population Waste Generated

1 Residential Refuse

(Residents + visitors)

0.3 to 0.6

kg/cap/day

3,088 1389.6

2 Community 0.1 to 0.2

kg/cap/day

177 17.7

Total 3,388 1,407.3 kg/day

11. The project proposals are covered under category 8"a" of EIA notification, 2006, as

amended.

The committee discussed the matter and recommended grant of environmental

clearance on the project proposals alongwith general conditions as earlier prescribed by the

authority for construction project and following specific conditions:

1. 03 m peripheral green shall be provided around the project inside the project boundary. 2. 15% area of the total plot area shall be compulsorily made available for the green belt

development including the peripheral green belt.

3. Project falling with in 10 Km. area of Wild Life Sanctuary is to obtain a clearance from

National Board Wild Life (NBWL) even if the eco- sensitive zone is not earmarked.

4. Criteria/ norms provided by competent Authority regarding the seismic zone be

followed for construction work. Provision of alarm system, to timely notify the

residents, in case of occurrence of earthquake/other natural disasters/fire should be

provided. A well defined evacuation plan should also be prepared and regular mock

drills should be arranged for the residents. Rise of stairs should be constructed in a way,

so that it should provide smooth movement.

5. For the treatment for total sewage, a full-fledged STP is to be provided with 20% more

capacity than waste water generated during operation phase.100% waste water is to be

treated in captive STP conforming to prescribed standards of receiving body for

designated use. Monitoring of STP to be done daily till its stabilization.

6. Dual plumbing should be adopted. Recycling of water as proposed shall be undertaken

with regular testing and monitoring of treated water.

7. Dedicated power supply for STPs is to be ensured during operation. Sludge of STP is to

be used in-house as manure and surplus manure should be managed by giving it to end

users. STP shall be suitably located nearest to back side boundary with shortest out let.

Minutes of 228th

SEAC Meeting Dated 23/07/2015

Page 41 of 52

Operation and the maintenance cost of the STP shall also be informed along with the

compliance of the E-waste and municipal solid waste disposal.

8. Environmental Corporate Responsibility (ECR) plan along with budgetary provision

amounting to 2% of total project cost (Rs. 2.5 crores) shall be prepared and approved by

Board of Directors of the company. A copy of resolution as above shall be submitted to

the authority. A list of beneficiaries with their mobile nos./address should be submitted

alongwith six monthly compliance reports.

9. LEDs should be used in all common areas and corridors. 100% solar lighting is to be provided in the open areas/ stairs cases.

10. Parking guideline as per YEIDA should be followed. Parking for disabled persons should be explored.

11. All entry/exit point should be bell mouth shaped. 12. To discharge excess treated waste water into public drainage system, permission from

the competent authority to be taken prior to any discharge. 13. 100 % provision of Rain Water Harvesting is to be made. RWH shall be initially done

only from the roof top. RWH from green and other open areas shall be done only after permission from CGWB.

14. An underground Pucca tank for collection/reuse of rain water may be constructed.

15. Height of the stack should be provided based on combined DG sets capacity and be 6mt

higher than the tallest building.

16. Post project monitoring for air, water (surface + ground), Stack noise of D.G. sets, STP

to be carried out as CPCB Guidelines.

17. Crèche to be provided during the construction/operation phase.

18. Provision of separate room for senior citizen with proper amenities shall be made.

19. Protection shall be provided on the windows of the high rise flats for security of

residents.

20. Unless and until all the environmental issues are sorted out the occupancy will be

restricted and would be only allowed after achieving the Permission from the competent authority.

21. The project proponent shall ensure that the project site does not attract/infringe any buffer zone of no activity identified/declared under law.

22. For any extraction of ground water, prior permission from CGWB shall be taken. 23. Sprinkler to be used for curing and quenching and ready mix concrete may be used for

construction. 24. Possibilities of use of treated waste water for irrigation purposes should be explored.

Drip irrigation should be tried upto extent possible. No fresh water will be used for irrigation purpose.

25. Mobile toilets, safe drinking water facility, sanitation facility and eco friendly fuels etc.

Shall be made available to the temporary residents/workers at the project site including

the proper treatment and the disposal of the wastes.

19. Expansion of “Supreme Court Bar Association” at plot No- GH-4 & 5, Sector-99,

Noida, U.P. Sri G.K. Sinha, CEO, Supreme Court Bar Association, Multi-State Co-

Opp. Group Housing Society Ltd., New Delhi. File No. 2233/AD-Sub.

The committee noted that:

1. Environmental clearance for Residential Project “Supreme Court Bar Association”

at plot No- GH-4 & 5, Sector-99, Noida, U.P. was issued bythe State Level

Environment Impact Assessment Authority, U.P. (SEIAA, U.P.) vide letter no.

943 dated 09/06/2009.

2. The project proponent informed that a fresh application for environmental

clearance for the expansion of Group Housing Project “Supreme Court Bar

Minutes of 228th

SEAC Meeting Dated 23/07/2015

Page 42 of 52

Association” at plot No- GH-4 & 5, Sector-99, Noida, U.P. was submitted on

14/09/2013 vide letter dated 11/03/2014 for the inclusion of 36 apartments in the

project

3. The tenure of erstwhile SEIAA was completed on 11/10/2013 and reconstituted

through MoEF notification dated 25/02/2014 and the first meeting was organized

on 10/03/2014.

4. The aforesaid application dated 11/03/2014 was considered in State Level Expert

Appraisal Committee, UP (SEAC, UP) meeting dated 05/08/2014 in chronological

order wherein the proponent informed that 98% construction work has already

been undertaken. Therefore, SEAC deliberated as follows:

a. Submit the Compliance of SEIAA letter no. 943/SEAC/DDS/80, dated

09/06/2009 through which environmental clearance was accorded to the

original project.

b. Statement regarding sanctioned map and added area as increased after revision

of the plan is to be submitted.

c. Comparative detail of previous and proposed expansion.

d. Approved map from Noida Authority should be submitted.

e. An affidavit regarding the discharge/reuse of the domestic effluent along with

clear cut plan to be submitted.

f. An inspection report made by Deputy Director, Regional Office, Meerut

regarding compliance to earlier E.C. and status of proposed expansion should

be submitted.

5. As per the direction of the SEAC the site inspection was undertaken by Shri

Devendra Singh, Deputy Director, Regional Office, Directorate of Environment,

Meerut regarding the matter. The case was again discussed in SEAC meeting

dated 14/09/2014 and the SEAC gone through the inspection report and noted that

construction work on the proposed expansion of the project has been started

without obtaining prior environmental clearance. The committee directed the

project proponent to submit compliance of MoEF OM dated 12/12/2012 for

violation of EP Act, 1986. List of Board of Directors with their address and details

of year wise construction without obtaining environmental clearance should be

submitted and also directed that Secretary, SEAC to make necessary

communication to State Govt. for initiation of legal action in this regards. The

matter shall be discussed by the committee after receipt of information regarding

initiation of credible legal action.

6. In this regard Hon'ble Justice Deepak Verma, Former Judge, Hon'ble Supreme

Court of India, Administrator through his letter dated 07/10/2014 (Copy

enclosed)informed to Chairman, SEIAA that:

a. Environment Clearance from SEIAA vide letter dated 09/06/2009 was issued

for the Residential Project “Supreme Court Bar Association” at plot No- GH-4

& 5, Sector-99, Noida, U.P. and the work was initiated after approval of

drawings from NOIDA Authority on 25/08/2009 as per prevailing FAR at that

time.

b. Gazette notification dated 20/02/2010 issued by the Government of Uttar

Pradesh, for the purchase of additional FAR. Accordingly Society applied for

Minutes of 228th

SEAC Meeting Dated 23/07/2015

Page 43 of 52

the same to the NOIDA to accommodate more members in it considering the

objective/mission of the cooperative.

c. Initially it was proposed to purchase 17,100 sq. mt. as per the Board decision.

NOIDA Authority agreed the same vide letter dated 14/06/2012. In the Annual

General Meeting it was also approved to purchase the additional FAR on

12/03/2011, later on 28/01/2012 purchasable FAR was reduced to the tune of

8800 sq.mt.

d. In the meanwhile the Board was rendered defunct due to expiry of the term of

the Board and thereafter the Hon'ble Supreme Court appointed the

undersigned as the Administrator of the Society on 12/07/2013.

e. After vetting of the drawings from IIT, Bombay (as per provision of the

Gazette notification clause 83.2 (iv) Society applied the same to NOIDA

Authority and your good office on 14/11/2013 and again on 27/03/2014 for

Environmental Clearance. Since it is prestigious project for the members of

the Society, who are practicing Advocates in Supreme Court of India and

considering the rising cost, all efforts are being made to complete the project

as early as possible.

f. In anticipation of Environmental clearance/approval, Society has constructed

flats, keeping in mind all compliances/conditions required for such

Environment Clearance.

g. In view of the above facts and circumstances, it is requested that the

Environment Clearance be accorded at the earliest, for which society and its

member shall remain obliged.

7. In the above context the SEAC discussed the issue in its meeting dated

13/12/2014. Shri G.K. Sinha, CEO, appeared in the meeting with his consultant

ShriMahendraPandey, M/s EKO Pro Engineers Pvt. Ltd. The project proponent

informed that structural stability of the proposed project has been conducted

through IIT, Bombay which shows that the expansion project is safe and also the

compounding fee is submitted in the Noida Authority. Now, Noida Authority has

directed to submit environmental clearance prior to issuance of completion

certificate. Shri Sinha further submitted that all environmental safeguards and

stipulation shall be dully followed and this violation shall not be repeated and

requested for exemption from initiation of legal action under E.P. Act, 1986. The

committee discussed the matter and deliberated that the matter should be

forwarded to Authority for seeking legal opinion in the matter in view of above

situation.

Subsequently the recommendations of the SEAC meeting dated 13/12/2014 regarding

the project was considered by the State Level Environment Impact Assessment Authority

(SEIAA) in its meeting dated 12/01/2015. The SEIAA decided to seek the opinion of the

Ministry of Environment, Forests and Climate Change regarding the matter and sent a

communication to Director, IA Division, MoEFCC, Govt. of India through letter no.

2666/Parya/SEAC/2233/AD(S)/2014, dated 13/03/2015 in this context.

The SEAC was informed by the secretariat that a representation from Aishwarya Bhati,

Convener, Supreme Court Bar Association dated 01/06/2015 was received to the Directorate

Minutes of 228th

SEAC Meeting Dated 23/07/2015

Page 44 of 52

regarding the title project. The SEAC directed to put up the matter in next SEAC meeting

along with all the documents and a brief note.

The committee discussed the situation as above and representation of Shri Aishwarya

Bhati, Convener, Supreme Court Bar Association dated 01/06/2015. The committee also

noted that MoEFCC, Govt. of India has not given any opinion in the matter on the

communication dated 13/03/2015 made as per decision of SEIAA. The committee further

noted that Hon'ble NGT in its order dated 07/07/2015 in the matter of S.P. Muthuraman V/s

Union of India and Ors. (Original Application No. 37 of 2015 (M.A. No. 291, 293 & 294 of

2015) and Original Application No. 213 of 2014 (Ma 755 of 2014 & M.A. No. 177 of 2015)

has quashed the MoEF OMs dated 12/12/2012 and 27/06/2013 related to provisions for

dealing the violation matters. In this situation, the matter may again be forwarded to SEIAA

for taking necessary action in view of Hon'ble NGT decision dated 07/07/2015 and

recommendations of SEAC made in meeting dated 13/12/2014.

20. Group Housing project “Raj Garden City” Vill- Noornagar, Ghazibad. Sri Deepak

Rawat, 3/114 Sector- 5, Rajendra nagar, Sahibabad, Ghizabad. File No. 1716/DD-Y

The committee noted that the matter was earlier discussed in SEAC meeting dated

07/10/2014 wherein the project proponent was directed to submit following information:

1. Document regarding Ownership of land & change of land use.

2. Copy of development authority's documents through which FAR has been allowed.

3. Specify the permitted uses of the proposed project site as per zoning of Noida Master

Plan.

4. Area statement with block wise, floor wise details should be submitted.

5. On scale map showing approach road with reference to project site.

6. Site layout plan with dimensions should be submitted. All road widths should be

clearly mentioned in the layout plan.

7. Structural design map along with certificate for structural safety.

8. All services maps i.e. sewage, drainage, external electrification, rain water harvesting,

parking, uses of solar energy etc. 9. Solar energy provisions for street lighting and stair case lighting should be made and

plans submitted. 10. Plan for zero discharge. Scenario for monsoon period should also be considered while

proposing for zero discharge. 11. Detailed plan for STP.

12. Section drawing for roads showing all services i.e. footpath/parking/sewage/drainage. 13. Parking entry and exit have been proposed on same road. Provision for separate

entry/exit roads may be explored. 14. Detailed plan for CSR.

15. Affidavit regarding wild life sanctuary within 5 KM to be given.

16. Provision for facilities like convenient shops, play school, community Hall etc.

The SEIAA in its meeting dated 30/10/2014 agreed with the recommendations of

committee and also directed for a site visit. A site visit was undertaken by the Officials of

Directorate of Environment, Regional Office, Meerut and UPPCB, Regional Office,

Ghaziabad. As per inspection report, it was reported that no construction work has been

undertaken. The committee again scheduled the matter in its meeting dated 27/06/2015

wherein the project proponent did not appear. The matter was again scheduled in SEAC

meeting dated 23/07/2015. A presentation was made by the project proponent alongwith

their consultant Shri A.K. Gupta, M/s Shri Environment Technology Institute. The proponent, through the documents submitted and the presentation made, informed the committee that:-

Minutes of 228th

SEAC Meeting Dated 23/07/2015

Page 45 of 52

1. The Environmental Clearance is sought for Group Housing Project “Raj Garden City”

at Plot No/Khasra No. 1085, 1086, 1088, 1089 and 1135, Noor Nagar, Ghaziabad,

U.P.

2. The total plot area and proposed built up area of project are respectively 39371.25

sqm and 179902.85 sqm.

3. The permissible and achieved FAR are respectively 114989.63 sqm and 114851.66

sqm. 4. Parking facility is required for 1722 ECS and proposed for 1781 ECS.

5. The total water requirement is proposed as 1228 KLD which will be sourced from municipal supply. Total fresh water requirement is proposed 593 KLD.

6. The total waste water generation is proposed as 706 KLD and treated in 847 KLD capacity.

7. Total power requirement is proposed as 4500 KVA from UPPCL/Concern authority. 8. 5 nos. of DG Sets of (4x1050 KVA+1x500 KVA) are proposed for power back up.

9. Total green area of the proposed project is 5640.00 sqm. 10. Quantity of MSW to be generated is proposed is 6373kg/day.

11. The proposed number of rain water harvesting pits 5 will be provided.

12. The total no. of towers and floor are respectively 05 and (G+15).

13. Highest tower of the project is 50 m.

14. The total excavated earth is 1,20,000 m3

15. The Project proposal falls under category 8"b" of EIA Notification, 2006 (as

amended).

The committee discussed the replies of project proponent and inspection report made

by the Officials of Environment Department and recommended grant of environmental clearance on the project proposals alongwith general conditions as earlier prescribed by the

authority for construction project and following specific conditions:

1. 03 m peripheral green shall be provided around the project inside the project boundary. 2. 15% area of the total plot area shall be compulsorily made available for the green belt

development including the peripheral green belt. 3. Project falling with in 10 Km. area of Wild Life Sanctuary is to obtain a clearance from

National Board Wild Life (NBWL) even if the eco- sensitive zone is not earmarked.

4. Criteria/ norms provided by competent Authority regarding the seismic zone be

followed for construction work. Provision of alarm system, to timely notify the

residents, in case of occurrence of earthquake/other natural disasters/fire should be

provided. A well defined evacuation plan should also be prepared and regular mock

drills should be arranged for the residents. Rise of stairs should be constructed in a way,

so that it should provide smooth movement.

5. For the treatment for total sewage, a full-fledged STP is to be provided with 20% more

capacity than waste water generated during operation phase.100% waste water is to be

treated in captive STP conforming to prescribed standards of receiving body for

designated use. Monitoring of STP to be done daily till its stabilization.

6. Dual plumbing should be adopted. Recycling of water as proposed shall be undertaken

with regular testing and monitoring of treated water. 7. Dedicated power supply for STPs is to be ensured during operation. Sludge of STP is to

be used in-house as manure and surplus manure should be managed by giving it to end users. STP shall be suitably located nearest to back side boundary with shortest out let.

Operation and the maintenance cost of the STP shall also be informed along with the compliance of the E-waste and municipal solid waste disposal.

8. Environmental Corporate Responsibility (ECR) plan along with budgetary provision amounting to 2% of total project cost shall be prepared and approved by Board of

Directors of the company. A copy of resolution as above shall be submitted to the

Minutes of 228th

SEAC Meeting Dated 23/07/2015

Page 46 of 52

authority. A list of beneficiaries with their mobile nos./address should be submitted

alongwith six monthly compliance reports.

9. LEDs should be used in all common areas and corridors. 100% solar lighting is to be

provided in the open areas/stairs cases.

10. Parking guideline as per Ghaziabad Development Authority should be followed.

Parking for disabled persons should be explored.

11. All entry/exit point should be bell mouth shaped.

12. To discharge excess treated waste water into public drainage system, permission from the competent authority to be taken prior to any discharge.

13. 100 % provision of Rain Water Harvesting is to be made. RWH shall be initially done only from the roof top. RWH from green and other open areas shall be done only after

permission from CGWB. 14. An underground Pucca tank for collection/reuse of rain water may be constructed.

15. Height of the stack should be provided based on combined DG sets capacity and be 6mt higher than the tallest building.

16. Post project monitoring for air, water (surface + ground), Stack noise of D.G. sets, STP to be carried out as CPCB Guidelines.

17. Crèche to be provided during the construction/operation phase.

18. Provision of separate room for senior citizen with proper amenities shall be made.

19. Protection shall be provided on the windows of the high rise flats for security of

residents.

20. Unless and until all the environmental issues are sorted out the occupancy will be

restricted and would be only allowed after achieving the Permission from the competent

authority.

21. The project proponent shall ensure that the project site does not attract/infringe any

buffer zone of no activity identified/declared under law.

22. For any extraction of ground water, prior permission from CGWB shall be taken.

23. Sprinkler to be used for curing and quenching and ready mix concrete may be used for construction.

24. Possibilities of use of treated waste water for irrigation purposes should be explored. Drip irrigation should be tried upto extent possible. No fresh water will be used for

irrigation purpose. 25. Mobile toilets, safe drinking water facility, sanitation facility and eco friendly fuels etc.

Shall be made available to the temporary residents/workers at the project site including the proper treatment and the disposal of the wastes.

21. Group Housing “Bluemoon Homesat" at plot no- 1104, 1111, Vill-Noornagar,

Ghaziabad.Sri Vinod kumar Tyagi,124, Rajpur Khurd, New Delhi. File No.

1717/AD-H

The project proponent did not appear. The committee discussed and deliberated that

project fie should be closed and should be opened only after request from the project

proponent. The file shall not be treated as pending at SEIAA/SEAC.

22. Expansion of Group Housing Project “Earth Towne” at Plot No-GH-04, Sector-1,

Greater Noida, U.P. M/s Earth Towne Infrastructure Pvt. Ltd. Sri Vipin Gupta, 26,

Ist Floor, Pusa Road, New Delhi. File No. 3191/OSD(T)

The committee noted that an application dated 18/06/2015 was made by the project

proponent for environmental clearance of Expansion of Group Housing Project “Earth

Towne” at Plot No-GH-04, Sector-1, Greater Noida, U.P. M/s Earth Towne Infrastructure

Pvt. Ltd.

A presentation was made by Shri Nandgopal Maurya, authorized representative of

project proponent along with their consultant M/s Ascenso Enviro Private Limited. The

Minutes of 228th

SEAC Meeting Dated 23/07/2015

Page 47 of 52

proponent, through the documents submitted and the presentation made, informed the

committee that:-

1. The environmental clearance is sought for Expansion of Group Housing Project “Earth Towne” at Plot No-GH-04, Sector-1, Greater Noida, U.P. M/s Earth Towne Infrastructure

Pvt. Ltd. Environmental clearance was earlier issued through SEIAA letter no. 1275/Parya/SEAC/450/2010/TAJ dated 03/04/2011 for the project. Now, environmental

clearance for expansion of the project is proposed. 2. Area details of the project is as follows:

S.

No.

Description Total Area In percentage (%)

1 Total Plot Area 73,942.00 ….

2 Permissible Ground Coverage 25,879.70 35% of Plot area

3 Proposed Ground Coverage 15,953.37

21.58% of Plot area

4 Permissible FAR 2,03,340.50 2.75 % of Plot area

5 Purchasable FAR 55,456.50 0.75% of Plot area

6 Total Permissible FAR

(@ 3.5 of Plot Area)

2,58,797.00 3.5% of Plot area

7 Proposed FAR 2,58,775.37 3.49% of Plot area

8 Permissible

Shopping/Commercial Area

@1% of Permissible FAR

2,587.97 ….

9 Proposed Shopping

/Commercial FAR

2,585.00 0.99% of permissible FAR

10 Proposed School FAR 1500 ….

11 Permissible Ancillary Area

@15% of Permissible FAR

38,819.55 15% of permissible FAR

12 Proposed Ancillary Area 37,423.496 14.46% of permissible FAR

13 Basement Area 1,07,343.437 …

14 Stilt Area 3,053.114 …

15 Built up Area 4,06,595.42 …

16 Open Area 57,988.63 78.42% of Plot area

17 Landscape Area Provided 29,322.63 50.56% of Open area

3. Salient features details are as follows: Name and Location of the Project Modernization cum Expansion of Group Housing Project

“Earth Towne” at Plot No.GH-04, Sector-1, Greater Noida,

Uttar Pradesh

Developers of the project Earth Towne Infrastructure Pvt. Ltd

Total Plot Area 73,942.00 m2

Built-up Area 4,06,595.42 m2

Total Water Consumption 1,446 KLD

Total Freshwater Requirement 924 KLD

Source: Municipal Supply

Power Requirement 9650 kVA

Source: Noida Power Corporation Limited

Power Backup 12 DG sets of total capacity of 12,000 kVA

(6 x 1,500+ 6 x 500)

Total Parking provided 3235 ECS

Solid Waste to be Generated 7,025.55 kg / day

No. of RWH Pits 12 RWH Pits

4. Building blocks details are as follows: S. No. Type of building Story No. of Dwelling Units No. of Servants Units

1 Tower-1 G/S+19 79 00

2 Tower-2 G/S+19 78 00

3 Tower-3 G/S+19 79 00

4 Tower-4 G/S+19 79 00

5 Tower-5 G/S+19 79 00

6 Tower-6 G/S+19 78 00

7 Tower-7 G/S+19 79 00

Minutes of 228th

SEAC Meeting Dated 23/07/2015

Page 48 of 52

8 Tower-8 G/S+19 79 00

9 Tower-9 G/S+19 79 00

10 Tower-10 G/S+21 87 00

11 Tower-11 G/S+21 87 00

12 Tower-12 G/S+21 87 00

13 Tower-12 A G/S+21 87 00

14 Tower-14 G/S+21 87 00

15 Tower-15 G/S+21 87 00

16 Tower-15 A G/S+21 87 00

17 Tower-16 G/S+21 87 00

18 Tower-17 G/S+21 87 00

19 Tower-18 G/S+21 87 00

20 Tower-19 G/S+19 79 00

21 Tower-20 G/S+19 79 00

22 Tower-21 G/S+19 79 00

23 Tower-22 G/S+19 78 00

24 Tower-23 G/S+19 79 00

25 Tower-24 G/S+19 79 00

26 Tower-25 G/S+19 79 00

27 Tower-26 G/S+19 78 00

28 Tower-27 G/S+19 79 00

29 Tower-28 G/S/C+25 101 00

30 Tower-29 G/S/C+25 101 101

31 Tower-30 G/S/C+25 101 00

32 Tower-31 G/S/C+25 101 101

33 Tower-32 2C+19.5 156 00

34 Tower-33 2C+19.5 156 00

5. Population details are as follows: S.

No.

Types No of unit / Area in

sq.m.

Person Per

Unit

Population

1 Main Dwelling

Units

3,004 nos. 4.5 13,518

2 Servant Units 202 nos. 2.25 455

3 Commercial Area 2,585.00 sq.m 1 person/3 sq.m of FAR

for Ground floor

862

4 Visitor (10 % of DU Population) 1352

Total Population 16,187

6. Water requirement details are as follows: S.

No.

Description Population Unit water

consumption

(litres)

Total

water

required

(KLD)

water

requirement

for domestic

use (KLD)

Flushing/

Recycled

water

(KLD)

1 Residential Population

Main + Servants Units

13,973 86 1,201.67 908.24 293.43

2 Commercial 862 30 25.86 7.75 18.10

3 Visitors 1,352 15 20.28 8.11 12.16

4 Horticulture

(29,322.63 sq.m)

-- 3 ltrs./sq.m 87.96 -- --

5 DG Cooling

(12,000 KVA)

1ltrs./KVA/hrs. 96.00 -- --

6 Fire fighting Tank -- 1% of total

water requirement

14.00 -- --

Total Water

Requirement

-- -- 1,445.78 924.11 323.70

SAY 1,446.00 924.00 324.00

7. Solid waste generation details are as follows: S.

No.

Category of Solid Waste Waste

Generation

Rate

Formula Total

Population

Waste

Generated

1 Residential Refuse 0.3 to 0.6 Total 15,325 6,896.25

Minutes of 228th

SEAC Meeting Dated 23/07/2015

Page 49 of 52

(Residents+ servants +

Visitors)

kg/cap/day Population*0.45

2 Commercial + Community 0.1 to 0.2

kg/cap/day

Total

Population*0.15

862 129.3

Total 7,025.55

kg/day

8. The project is covered under category 8 "b" of EIA notification, 2006.

The committee discussed the matter and recommended following TORs and general

guidelines for conducting EIA studies regarding the proposals:

Additional TORs :

1. Comparative area and other environmental parameter statements showing values

earlier and proposed as expansion.

2. All approved revised drawings/maps alongwith all approved revised services plans.

3. The revised structure design certificate by qualified structure engineer should be

submitted. The structural design certificate should preferably be vetted by IITs/CBRI.

Provision of alarm system, to timely notify the employees/residents, in case of

occurrence of earthquake/other natural disasters/fire should be provided.

4. Status of construction undertaken till date (block wise/tower wise/floor wise).

5. Compliance of earlier EC dated 03/04/2011.

6. Master plan of the area showing proposed project.

7. Permissible uses of the proposed site as per zoning regulation.

8. Allotment letter from concerned development authority.

9. Physical features within 30 m of the project sites with their ownership.

10. Section details of all road.

11. Area details showing proposed uses as residential, commercial, parks, parking, roads,

other services, facilities of the project also in percentage.

12. Land use approved by the competent authority.

13. Complete Details of facilities to be developed by the project proponent i.e. for which

environment clearance is sought.

14. Use of reflecting paints on roof top and side walls.

15. Details of rain water harvesting are to be given.

16. Provision of 100% solar lighting along the road site, stair cases, common places.

17. A site plan showing the project site and its surroundings with physical features and

topographical details, such as land use, contours and drainage pattern, along with

photographs of the site from all four sides, should be included in the background

information.

18. 10% EWS / LIG housing provision shall be made as per Development Authority bye-laws.

19. Sanctioned plans/maps regarding the project with all services plans.

20. All plans and elevation sections/all service plan/landscape plan/standard

electrification plan/drainage/sewerage plan.

21. Structural plan is to be submitted signed by qualified structural designer.

22. All service plans like sewer drainage water supply rain water harvesting fire fighting

landscape plan is to be submitted.

23. Examine in detail the proposed site with reference to impact on infrastructure

covering water supply, storm water drainage, sewerage, power, etc., and the disposal

of treated/raw wastes from the complex on land/water body and into sewerage system.

Minutes of 228th

SEAC Meeting Dated 23/07/2015

Page 50 of 52

24. Water requirement and water management plan alongwith necessary permissions for

discharge.

25. Hydro-geological investigations be carried out and obtain permission from Central

Ground Water Authority for withdrawal of ground water.

26. Consider soil characteristics and permeability for rainwater harvesting proposals,

should be made to prevent ground water contamination. Maximize use of treated

water by recycling and utilization of rainwater.

27. Make provision for safety against failure in the operation of wastewater treatment

facilities. Identify acceptable outfall for treated effluent.

28. Details of green belt as a measure for mitigation of dust and noise and buffer between

habitation and proposed project.

29. Landscape plan, green belts and open spaces may be described separately.

30. Study the existing flora and fauna of the area and the impact of the project on them.

31. Examine existing crèche, education, health facilities, police, post Office, Banks and

other services and make adequate provisions in the proposal.

32. Assess soil erosion in view of the soil characteristics, topography and rainfall pattern.

33. Application of renewable energy/alternate energy, such as solar and wind energy may

be described including solar water heating in the guidelines for entrepreneurs.

34. Consider solid wastes, including e-waste in addition to other solid wastes and their

disposal.

35. Identification of recyclable wastes and waste utilization arrangements may be made.

36. Explore possibility of generating biogas from biodegradable wastes.

37. Arrangements for hazardous waste management may be described as also the

common facilities for waste collection, treatment, recycling and disposal of all

effluent, emission and refuse including MSW, biomedical and hazardous wastes.

Special attention should be made with respect to bird menace.

38. Provisions made for safety in storage of materials, products and wastes may be

described.

39. Disaster management plan should be prepared.

40. Traffic management plan including parking and loading/unloading areas may be

described. Traffic survey should be carried out both on weekdays and weekend.

41. Parking provision is to be made for higher ECS worked out either as per state bye-

laws or construction manual of the MoEF.

42. Exclusive Parking area in the basement (excluding other facilities) and surface is to be

clearly mentioned.

43. Provide service road for entry and exit to project site.

44. Use of local building materials should be described.

45. Consider provision of DG Flue Gas emissions to be treated in a scrubber. Stack

details with provisos of sampling port for monitoring be described.

46. Work out MGLC for the combined capacity of DG sets.

47. Provide for conservation of resources, energy efficiency and use of renewable sources

of energy in the light of ECBC code.

48. Application of resettlement and rehabilitation policy may be described. Project

affected persons should be identified and rehabilitation and resettlement plan should

be prepared.

49. Examine separately the details for construction and operation phases both for

Minutes of 228th

SEAC Meeting Dated 23/07/2015

Page 51 of 52

Environmental Management Plan and Environmental Monitoring Plan.

50. Environment Corporate Responsibility (ECR) plan along with budgetary provision of

minimum 2% of the project cost as discussed in meeting shall be submitted on need

base assessment study in the study area.

51. Details of all internal and peripheral roads width.

52. Source and quantity of required water during construction and management of

generated waste water.

53. Project falling with in 10 Km. area of Wild Life Sanctuary is to obtain a clearance from National Board Wild Life (NBWL) even if the eco- sensitive zone is not

earmarked. 54. Declare/submit the running cost of STP and other environmental management

services (e.g., Municipal Solid Waste Disposal, Green belt Maintenance, Water Management etc.) in the proposals which are to be including in the allotment letters.

55. The proponent will submit the schedule of monitoring/data collection programme to the Office of Directorate, Member Secretary, UP Pollution Control Board and District

Magistrate of related District.

General Guidelines:

a. A legal affidavit by the Project proponent on Rs. 100/- non-judicial Stamp Paper, duly attested by Public Notary, stating that:

I. “There is no litigation pending against the project and/or land in which the project is

proposed to be set up (please give name & ownership etc. of the project) and that for

any such litigation what so ever, the sole responsibility will be borne by the Project

proponent.”

II. “No activity relating to this project (i.e. name of the project) including civil

construction has been undertaken at site except fencing of the site to protect it from

getting encroached and construction of temporary shed(s) for the guard(s). (if fencing

has not been done, then the same may be deleted).

III. “I/We hereby give undertaking that the data and information given in the application,

enclosures and other documents are true to the best of my knowledge and belief and

I/We am/are aware that if any part of the data and information submitted is found to

be false or misleading at any stage, the project will be rejected and clearance given,

if any to the Project will be revoked at our risk and cost.” IV. Project does not fall under any buffer zone of no-development as declared /identified

under any law.

b. Another legal affidavit by the consultant stating “(a) that the prescribed TORs have been

complied with (to be deleted if not applicable) & (b) that details and the data presented

are factually correct”, as per MoEF circular dated 04.08.2009 is also to be submitted along with EIA.

c. Current, site photographs viewing towards the project area from four directions indicating date of photograph taken, direction from which taken, name of the project,

and signature of Project proponent along with consultant with seal should be submitted, so as to ensure that no construction has been started before the grant of EC.

d. EIA should strictly follow the guidelines prescribed in annexure-III to the EIA

notification of 2006 and the Methods of Monitoring and analysis (Annexure-IV):

Guidance for assessment of representativeness and reliability of baseline environmental

attributes detailed under EIA manual January, 2001 and other guidelines in the matter. e. The status of accreditation of the EIA consultant with NABET/QCI shall be specifically

mentioned. The consultant shall certify that his accreditation is for the sector for which this EIA is prepared.

f. On the front page of EIA/EMP reports, the name of the consultant/consultancy firm along with their complete details including their accreditation, if any shall be indicated.

g. While submitting the EIA/EMP reports, the name of the experts associated with/involved in the preparation of these reports and the Name of laboratory through

Minutes of 228th

SEAC Meeting Dated 23/07/2015

Page 52 of 52

which the samples have been got analysed should be stated in the report. It shall clearly

be indicated whether said laboratory is accredited by NABL or approved under the

Environment (Protection) Act, 1986 (Please refer MoEF office memorandum dated 4th

August, 2009). The name project leader of the EIA study shall also be mentioned.

h. The EIA document shall be printed on both sides, as for as possible.

The Information’s no (a I , II, III & c) asked under the general guidelines is to be

submitted within 15 days from the date of receipt of the letter and remaining of the

information’s is to be submitted along with the EIA.

23. Expansion of IIMT College of Engineering at Plot No-A-20, Knowledge Park-III,

Greater Noida. Sri Mayank Arawal, MD. File N0- 2529/DD-Y

The project proponent did not appear. The committee directed that the project

proponent should be directed to present their case in view of MoEF Notification dated

09/06/2015 alongwith plan for sustainable environmental management as provisioned in the

Notification.

24. Jh jJh jJh jJh jek jeu] lhek jeu] lhek jeu] lhek jeu] lh----bZbZbZbZ----vksvksvksvks----] xzsVj uks;M] xzsVj uks;M] xzsVj uks;M] xzsVj uks;Mk] b.MªfLVª;y MsoysiesaV vFkkfjVh ds i= fnukad 01k] b.MªfLVª;y MsoysiesaV vFkkfjVh ds i= fnukad 01k] b.MªfLVª;y MsoysiesaV vFkkfjVh ds i= fnukad 01k] b.MªfLVª;y MsoysiesaV vFkkfjVh ds i= fnukad 01----07070707----2015 ij lfefr }kjk fopkj&foe'kZ A2015 ij lfefr }kjk fopkj&foe'kZ A2015 ij lfefr }kjk fopkj&foe'kZ A2015 ij lfefr }kjk fopkj&foe'kZ A

The committee noted that environmental clearance for Municipal Solid Waste

Processing and disposal facility, Astauli, District-Gautam Budh Nagar was accorded through

SEIAA letter dated 20/09/2013.

Shri Ramaraman, CEO, GNIDA through his letter dated 01/07/2015 has submitted that a meeting was held on 24/12/2014 at Noida Office in presence of Noida and GNIDA

Officers on the site options for proposed MSW treatment and disposal facility for Noida waste. Noida has expressed interest to manage and treat their segregated waste at Astauli,

Greater Noida. Astauli Municipal Solid Waste processing and disposal facility site has been approved by both the authorities after mutual understanding on future development of a

common MSW facility. In this regard, a MOU has been signed between GNIDA and Noida to treat Municipal Solid Waste of Noida at Astauli site. Both Noida and GNIDA shall jointly

maintain 576.16 TPD MSW threshold limit with approved treatment technologies and other

EC conditions to treat their MSW.

The committee discussed the matter and deliberated that a complete plan should be

submitted with details of Municipal Solid Waste facility to be used as per above proposed

arrangement by both Noida and GNIDA for further discussion on the matter. The copies of

the project report should be communicated to all committee Members before meeting for

their appraisal.

(Dr. M. S. Khan)

Chairman, SEAC,UP (Dr. S.N. Singh)

Member, SEAC, UP (Dr. Asheesh Kumar Singh)

Member, SEAC, UP

(S. C. Brahmachari)

Member, SEAC, UP

(Surendra Singh)

Secretary, SEAC, UP