Madhya Pradesh Energy Efficiency Improvement Investment ...
-
Upload
khangminh22 -
Category
Documents
-
view
0 -
download
0
Transcript of Madhya Pradesh Energy Efficiency Improvement Investment ...
Safeguards Due Diligence Report
This social safeguards due diligence report has been prepared by the Madhya Pradesh Paschim Kshetra Vidyut Vitaran Co. Ltd. (DISCOM-W), Indore for the Asian Development Bank and is made publicly available in accordance with ADB’s Public Communications Policy (2011). It does not necessarily reflect the views of ADB. This social safeguards due diligence report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.
Project Number: 43467-016 May 2018
IND: Madhya Pradesh Energy Efficiency Improvement Investment Program - Tranche 2
Submitted by
Madhya Pradesh Paschim Kshetra Vidyut Vitaran Co. Ltd. (DISCOM-W), Indore
Due Diligence Report April 2018
Madhya Pradesh Paschim Keshtra Vidyut Vitaran Co.
Limited- DISCOM-WEST,
GPH, Compound, Pologround, INDORE (MP)
Feeder Separation Project
(M.P. Energy Efficiency Improvement Investment
Program-Trench-2) Under ADB Loan-2830-IND
PREPARED BY:
SMS Envocare Limited Vijay Nagar, Indore, M.P.
2
CURRENCY EQUIVQLENT
((As of 1 April 2018)
Currency Unit – Indian Rupee (Rs)
Rs 1.00 = $0.015
$1.00 = Rs 65.08
ABBREVIATIONS
ADB : Asian Development Bank
AH : Affected Household
AP : Affected Person
DISCOM : Distribution Company
DISCOM-W : Distribution Company-West
DPR : Detailed Project Report
DCDS : Double Circuit Double (circuit) Stringing
DCSS : Double Circuit Single (circuit) Stringing
EA : Executing Agency
FGD : Focus Group Discussions
GOMP : Government of Madhya Pradesh
GoI : Government of India
GRC : Grievance Redress Committee
HVDS : High-Voltage Distribution System
IA : Implementing Agency
INR : Indian Rupee
LA : Land Acquisition
LVC : Land Valuation Committee
MP : Madhya Pradesh
MPPKVVCL : Madhya Pradesh Paschim Keshtra Vidyut Vitaran Co. Limited
PMU : Project Management Unit
NRRP : National Resettlement & Rehabilitation Policy
ROW : Right of Way
RP : Resettlement Plan
SOR : Schedule of Rates
ST : Scheduled Tribe
T&D : Transmission and Distribution
3
WEIGHTS AND MEASURES
Ha (hectare) =10,000m2 =2.47105 Acre
Km (Kilometer) =1,000m
kV = Kilo Volt (1,000 Volt)
kW =Kilowatt (1,000 watt)
kWh =Kilowatt-hour
mG = Milli Gauss
MVA = Megavolt-Amperes
MW = Megawatt
GWh/MU = Gigawatt-hour or Million kVh
NOTES:
(i) The financial year (FY) of the government of India and its agencies begins on 1
April. “FY” before a calendar year denotes the year in which the fiscal year starts,
e.g, FY2016 begins on 1 April 2016 and ends on 31 March 2017.
(ii) In this report “$” refers to U.S dollars
4
TABLE OF CONTENTS
DESCRIPTION PAGE NO.
EXECUTIVE SUMMARY
1. PROJECT DESCRIPTION
6
1.1 Need for Due Diligence Update 9
2. SCOPE OF LAND ACQUISTION AND RESETTELMENT IMPACTS 10
3. INFORMATION DISCLOSURE CONSULTATION AND
PARTICIPATION
3.1. Consultation 3.2. Finding of Consultation during DDR Presentation 3.3. Plan for Further Consultation in the Project 3.4. Disclosure
4. GRIEVANCE REDRASSEL MECHANISM
4.1. Introduction
4.2. Grievance Redressal Committee
14
14
15
16
16
17
17
17
5. CONCLUSION 18
5
LIST OF TABLES PAGE NO.
Table 1.1 Updated Scope of Project as Implemented under DISCOM-West
8
Table 2.1 Summary of Land Acquisition and Resettlement Impacts 10
Table 2.2 Detailed Impacts of each Project Components 11
Table 3.1 Public Consultation & Disclosure 14
Table 3.2 Public Consultation Summary of PPR-41,Lot-I of ABD Loan - 3066 - IEE & RP Update
15
LIST OF ANNEXURE PAGE NO.
Annex 1 Details of Sub Project Components of DISCOM-West under ADB Loan- 3066
20
Annex 2 Govt of MP Circulars for Land Allotments 23
Annex 3 Public Consultation Attendance Sheets 29
6
1. PROJECT DESCRIPTION
1. Government of Madhya Pradesh (GoMP) has requested the Asian Development Bank
(ADB) through the Government of India (GoI) for a Multi-Tranche Financing Facility
(MFF) to part finance the feeder separation investment program. The key aspect of the
feeder separation project is separation of the irrigation and residential/commercial loads
in rural areas and to adopt measures to check pilferage of electricity.
2. The Madhya Pradesh Paschim Keshtra Vidyut Vitaran Co. Limited (MPPKVVCL) as
power distribution company-DISCOM-W serves as the executing agency (EA) for the
projects under DISCOM-West for distribution system improvement for Indore & Ujjain
circle. DISCOM-W currently serves about 3.75 million customers within an area of
77,021 km2 in the rural and urban areas.
3. All feeder separation project activities are being carried out within the 14 districts in
phase-2 of DISCOM-West. There are about 900,000 agricultural pumps in the project
area, along with over 2.9 million household customers in the project area. The objective
is to create feeder separation network.
4. The Feeder Separation Project was a continuation of the on-going distribution
improvements and it has enabled 24 reaping the full benefits of power sector reforms
undertaken with the help of ADB program loan (IND – 2830- Tranche-2) that created an
enabling policy framework. Government of Madhya Pradesh (GoMP) launched Feeder
Separation Programme (FSP) (hereinafter referred as FSP Project) to separate
domestic load from agricultural load in rural areas.
5. The main objective of the programme were to provide continuous 24 hours power
supply to households and continuous 10 hours power supply to agriculture pumps in
rural areas and to reduce the T&D losses of the distribution system from eight per cent
to 22 per cent in the rural areas.
6. To implement this project district wise sub projects are prepared for strengthening and
modification of present electrical network and work is planned to be awarded to different
competent vendors so that entire project can be completed within the time limit.
7. The main project activities includes (i) erection of 11 kV additional bays along with VCB,
control relay panel; (ii) Laying of 11 kV lines on PCC poles with (rabbit) AAA conductor;
(iii) Installation of 25 KVA 11/0.433 kV distribution transformers; (iv) HVDS System
(Conversion of existing LT to HT line);(v) 33 kV bays at EHV substations, 33 kV new
substations and 33 kV lines; (vi) Replacement of bare conductor of LT lines by AB
cables; (vi) replacement of damaged lines by armored PVC cable; (viii) provision of
meters for un-metered consumers; and(vii) GIS based consumer indexing and asset
mapping.
8. The Resettlement Plan (RP) has been prepared for the Tranche-2 components of the
Madhya Pradesh Energy Efficiency Improvement Project (The Program). The RP based
on Detailed Project Report (DPR). Tranche-2 components has been categorized as „B‟
for Involuntary Resettlement (IR) impact according to ADB‟s Safeguard Policy
Statement, 2009 (SPS). A combined RP report for all distribution companies were
submitted for ADB‟s approval in September, 2011. As per ADB approved resettlement
plan in September,2011 scope of work of DISCOM-West was planned as per following:
7
Component-1- Feeder Separation comprising construction of new 11 KV lines and
rehabilitation and upgrades of existing 11 KV lines, so as to separate power supply to
irrigation pumps & households.
Components-2- Installation of HVDS comprising installation of new distribution
transformers and conversion of bare conductor LV lines to aerial bundled cables.
Component-3- Supply of Quality Improvement & Metering comprising mapping of
distribution assets & associated global positioned system (GPS) surveys, installation
of meters, network management improvement of systems at 11 KV & below.
Component-4- Upstream 33 KV Network Strengthening comprising construction of
new 33 KV bays at EHV substations, construction of new 33 KV lines, upgrading
existing 33/11 KV substations, construction of new 33/11 KV substations and
installation of new 33/11 KV transformers.
9. During the progress of subproject implementation, original scope of work has been
updated on quantity of subproject components based on actual surveys & site
conditions. Updated scope of work has been described in following subprojects going
on as under:
Extra quantity had executed under feeder separation based on survey, which
quantity was not covered in original ADB approved RP September 2011.Updated
scope of project, comprises, increased extra quantity of 85 KM of 11 KV line, which
now updated total 11 KV lines has length of 3708 KM in place of earlier length 3623
KM.
In support to increased quantum of 11 KV lines, 11 KV DP structure on 8 m PCC
pole increased 1010 nos, which now updated quantity is 3798 nos in place of earlier
2788 nos of original ADB approved RP September 2011.
Under this component 2, Updated scope of project, comprises, increased extra
quantity of 22.12 KM of Replacement of AAAC/ACSR conductor by AB cable XLPE
25 sqmm on existing 3-phase LV Line, which now updated total length of 1886.22
KM in place of earlier length 1864 KM.
Extra quantity had installed under quality improvement metering plan based on
GPS survey, which quantity was not covered in original ADB approved RP
September 2011.Updated scope of project, comprises, increased extra quantity of
72177 nos of meters, which now updated total quantity is 162719 nos in place of
earlier quantity 90542 nos for new & existing connections with renovation of service
lines.
Extra quantity had construction of 10 nos new 33/11 KV substations, which quantity
was not covered in original ADB approved RP September 2011.Updated scope of
project, comprises, increased quantity of 10 nos 33/11 KV new substations, which
now updated total quantity is 31 nos in place of earlier quantity 21 nos for 33/11 KV
substation
10. Status of feeder separation project had 100% completed by June 2017.Updated scope
of work in totality has been summarized based on actual survey & executed and also
shown in table no-1.1 & detailed supporting in Annexure-1.
8
TABLE NO-1.1
Updated Scope of Project as Implemented under DISCOM-West
Sr. No
Description of Project/ Sub-projects under Feeder Separation
Project- MFF-Trench-2 Unit
Quantity as per ADB approved
Original RP September 2011
Extra Quantity Executed
Total Updated Quantity as
actual executed based on Survey
Component-1- Feeder Separation
1 Extension of 11 kV bay in existing
33/11 kV substation Nos 328 0 328
2 11 kV line on 140 kg 8 m PCC pole
with DP KM 3623 85 3708
3 25 kVA, 11/0.433 kV, 3-phase
distribution transformer substation
with metering
Nos 4836 0 4836
4 11 kV DP structure on 8 m PCC pole Nos 2788 1010 3798
5 Four pole structure nos 141 0 141
6 Road/river/railway crossings Nos NA NA NA
Component 2: HVDS and associated LV lines
7 LV to HV conversion (HVDS) km 1792 0 1792
8 LV line 3-phase 5-wire overhead
using AB cable XLPE 50 sqmm on
PCC pole 140 kg, 8 m
km 222 0 222
9 Replacement of AAAC/ACSR
conductor by AB cable XLPE 50
sqmm on existing 3-phase LV line.
km 1242 0 1242
10 Replacement of AAAC/ACSR
conductor by AB cable XLPE 25
sqmm on existing 3-phase LV Line
km 1864 22.12 1886.12
Component 3: Quality improvement and metering
11 Cost of providing meters for new &
existing connections with renovation
of service lines
Nos 90542 72177 162719
Component 4: Upstream 33 kV network strengthening
11 33 kV line on H Beam (152x152
mm), 33 kV bay power transformer
augmentation & new power
substation
km 343 0 343
12 33 kV line with DOG conductor Nos 8 0 8
13 33 kV Bay at EHV substation
0 0
14 33 kV guard for road /river /line km 673 0 673
9
crossing
15 33 kV DP structure on PCC pole Nos 357 0 357
16 New 33/11 kV substations (from temporary to permanent )
1.6 MVA Nos 1 0 1
3.15 MVA Nos 22 1 23
5 MVA Nos 2 0 2
17 New 3.15 MVA, 33/11 kV substations Nos 21 10 31
18 Augmentation of power transformer
From 1.6 to 3.15 MVA Nos 4 0 4
From 3.15 to 5 MVA Nos 76 0 76
19 Additional 3.15 MVA power
transformer in existing substation Nos 21 0 21
1.1 Need for due diligence update
11. The Due diligence has been conducted to examine the social safeguard issues of the
sub projects implemented by the executing authority (DISCOM-West) under ADB loan -
2830-IND.The DDR exercise has been conducted with respect to the requirement of
ADB safeguard policy statement 2009 as well as with other national regulation and
policies are as relevant .This report provide the findings, based on review of documents
available with respect to the resettlement impacts, verification on site through field visits
and consultation with the relevant stakeholders.
10
2. SCOPE OF LAND ACQUISITION AND RESETTLEMENT IMPACTS
12. All the new 31 nos substations are located on government land and the land allotment
approvals received by the MPPKVVCL. Through Govt circular no-F-6-25/2010/7/Nazul,
Bhopal, dated 18th August 2010 & department of energy, Govt of MP circular no. F-6-
2/2009/13, dated 26th August 2010. The copy of circular is attached Annexure-2.All
project activities have been carried out within the existing facilities of DISCOM-West for
a rural agricultural feeder separation program.
13. The feeder separation distribution lines of 11 kV (total KM-3708) & LV to HV conversion
(HVDS) line (total KM-2694) is single pole based and feeder separation lines mainly
follow the road right of way. Additionally, wherever the distribution lines passes through
the agriculture land care has been taken to place the pole on the plot edges to avoid
impacts on the land. Therefore the project has no resettlement impacts due to the
implementation of its components. Land area requirement for 3.15 MVA capacity 33/11
KV new substations are 30 mt x 40 mt each as per standard. Originally 21 new
substations were proposed & after completion of project 10 nos extra new substation
constructed. The summary of impacts is given in table 2.1, and component wise details
are given in table 2.2.
TABLE- 2.1
Summary of Land Acquisition and Resettlement Impacts
S.N. Impacts Quantity ( As per ADB
approved RP) Quantity ( Revised/
Updated)
1. Total area of private land to be acquired
Nil Nil
2. Total area of Government land Transferred
2.52 Hectare (1200 Sq mt each x 21
nos substation)
3.72 Hectare (1200 Sq Mt each x 31
nos substation)
3. Total area for crop compensation for temporary Impact
Nil Nil
4. Total number of private fruit trees
Nil Nil
5. Total number of affected households for crop compensation
Nil Nil
6. Total number of titleholders Nil Nil
7. Total number of non-title holders
Nil Nil
8 Total Number of vulnerable households
Nil Nil
11
TABLE- 2.2
Detailed impact of Each Project Component
Description of Subprojects
Number of subproject
components / Line length in km ( Original
Scope of Work)
Actual Executed
as per Survey
Transfer of Govt. Land
(ha)
Permanent IR
Impact: Land
Acquisition (ha)
Temporary IR Impact:
(Crops)/ Area (ha)
Remarks
Component-1 –Feeder Separation
Extension of 11 KV bay in
existing 33/11 KV Sub-
Station
328 nos 290 nos NA No No
All the existing sub stations are located in Government land. There were no encroachment, no squatter on the existing land. Total 11 KV distribution line for feeder separation under the subproject is 3708 km. The single-pole for 11 KV line and four pole for 11 KV DP structure will not have any impact on land. The distribution lines mainly follow the road ROW for which obtains permission has been obtained from the concerned department. Wherever the distribution lines passes through the agriculture land care has been taken to place the pole on the plot edges to avoid impacts on the land. To finalize the distribution line network, walkover surveys, were held with the participation of local communities and representatives of local rural bodies.
11 KV line on 140 KG 8 M
PCC Pole with DP 3,623 km 3708 km NA No No
25 KVA, 11/0.433 KV, 3 PH
Distribution Transformer
Sub-Station with Metering
4,836 nos 4358 nos NA No No
11 KV DP Structure on 8 M
PCC Pole 2,788 nos 3798 nos NA No No
Four Pole Structure 141 nos 141 nos NA No No
12
Description of Subprojects
Number of subproject
components / Line length in km ( Original
Scope of Work)
Actual Executed
as per Survey
Transfer of Govt. Land
(ha)
Permanent IR
Impact: Land
Acquisition (ha)
Temporary IR Impact:
(Crops)/ Area (ha)
Remarks
Component-2- HVDS and Associated LV Lines
LV to HV Conversion HVDS) 1,792 km 267 km NA No No Planned quantity of HVDS & associated Lines was total 5120 KM, while it had reduced by high difference of 47% as actual executed quantity 2694 KM after project executed based on survey. The single/double-pole distribution line had not any impact on land. The distribution lines for feeder separation project mainly follow the road/canal ROW for which they obtain permission. Wherever it passes through agricultural land there is no impact on the land. The DISCOM defines the ROW for distribution on the basis of a walk-over survey. The local communities, representatives of rural local body are present in the walk-over survey.
LV Line 3 PH 5 Wire
overhead using AB cable
XLPE 50 sqmm on PCC Pole
140 KG 8 M
222 km 40 km NA No No
Replacement of
AAAC/ACSR conductor by
AB cable XLPE 50 sqmm on
existing 3 PH LV Line
1,242 km 501.08 km NA No No
Replacement of
AAAC/ACSR conductor by
AB cable XLPE 25 sqmm on
existing 3 PH LV Line
1,864 km 1886.12 km NA No No
Component 3: Quality improvement and metering
Cost of providing meters for new & existing connections with renovation of Service Lines
90,542 no 162719 no NA No No
Subproject component of providing metering for new & existing connection with renovation of service lines does not concern with land acquisition & resettlement impact.
Component 4: Upstream 33 KV Network Strengthening
33 KV Line on H-Beam (152x152mm) 33 KV bay power
transformer augmentation & new power substation NA No No
13
Description of Subprojects
Number of subproject
components / Line length in km ( Original
Scope of Work)
Actual Executed
as per Survey
Transfer of Govt. Land
(ha)
Permanent IR
Impact: Land
Acquisition (ha)
Temporary IR Impact:
(Crops)/ Area (ha)
Remarks
33 KV Line with DOG
conductor 343 km 147.3 km NA No No
All the existing sub stations temporary to permanent are located in Government land. There were no encroachment, no squatter on the existing land All the proposed new sub stations are located in Government land. There were no encroachment, no squatter on the allotted land
33 KV Bay at EHV
Substation 8 no 0 no NA No No
33 KV Guard for Road/
River/ Line Crossing 673 km 11 km NA No No
33 KV DP Structure on PCC
Pole 357 no 151 no NA No No
New 33/11 KV Substation (From temporary to permanent) NA No No
1.6MVA 1 no 1 no NA No No
3.15MVA 22 no 23 no NA No No
5MVA 2 no 2 no NA No No
New 3.15 MVA, 33/11 KV
Substation 21 no 31 no NA No No
Augmentation of Power Transformer NA No No
From 1.6 to 3.15 MVA 4 no 4 no NA No No
From 3.15 to 5 MVA 76 76 no NA No No
Additional 3.15 MVA Power
Transformer in existing
substation
21 no 21 no NA No No
14
3. INFORMATION DISCLOSURE, CONSULTATION AND PARTICIPATION
3.1 Consultations
14. Public participation and community consultation has been taken up as an integral part of
the project social and environmental assessment process. Consultation was used as a
tool to inform and educate stakeholders about the project. The participatory process
helped in involving the local people in project activities. Initial public consultation has
been carried out in the project areas by project authority through transact walk/walk over
survey with the objectives of minimizing probable adverse impacts of the project through
alternate design solutions and to achieve speedy implementation of the project through
bringing awareness among the community on the benefits of the project. Consultations
were held during project preparation stage with project beneficiaries, elected
representatives of the local body and officials of the DISCOM-West (MPPKVVCL).
15. The tools used for consultations were individual discussions and focused group
discussions (FGD). These consultations provided insights into the present energy
situation and needs of the communities, their expectations and cooperation with officials
of the energy department in identifying sites for substations.
16. The project has conducted public consultation and disclosure of safe guard documents
as per the schedule given in table 3.1.
TABLE- 3.1
Public Consultation and Disclosure
Activity Task Period Stakeholder Identification
Mapping of the project area Feb-March 2011
Consultative meetings on resettlement mitigation measures
Discuss entitlements, compensation rates, grievance redress mechanisms
Feb-March 2011
Project information dissemination
Distribution of information Feb-March 2011
Disclosure of RP Disclosed AT PROJECT SITE OFFICES
March- April 2011
Web disclosure of the RP
RP posted on ADB and EA website
September 2011
Impact identification for change of site locations of sub station
Mapping of the project area to identify resettlement impacts , if any
December 2017 to January 2018
15
3.2 Findings of Consultation during DDR preparation
17. Focused group discussions were held at 6 no‟s for subproject components for DDR
preparation. Informal discussions were conducted with the villagers in and around the
substations sites. These discussions were held between the periods ofDecember-
2017 to January 2018. Local community from the villages where substations and/or
distribution lines have been executed participated in the discussions and information‟s
about the project was provided. Further, the local community accompanied the
consultants and officials during the respective site inspection and explained why the
particular location was chosen from the alternatives considered.
18. The public consultation summery is presented in Table 3.2 for Feeder Separation
Project areas & sample attendance lists of FGDs are presented in Annexure 3.
TABLE-3.2. Public Consultation Summary of FSP of ADB Loan-2830- Update
S. N. Site
Location Site Status
Date of Consultation
No. of Participants
Feedback Response
1 Lohari,
Dewas Operational 09-01-2018 5
No major concerns
expressed by project
surrounding people
Best practices are
incorporated as per
EMP
2 Karanj,
Ujjain Operational 09-01-2018 8
People were apprehensive
about construction activities
and if they would cause
nuisance. Assured that best
practices are incorporated
as per EMP
Construction
activities will be
stopped during
cultivation period to
avoid crop
damages
3 Ujjaini,
Dhar Operational 09-01-2018 3
No major concerns
expressed by project
surrounding people
Local People were
supportive.
4
Bori
Buzurg,
Burhanpur
Operational 12-01-2018 5
Some people wanted to
know if construction can be
carried out during non-
cultivation season. Assured
that it is followed by EPC
contractor
Best practices are
incorporated as per
EMP
5
Jadwasa
Kala,
Ratlam
Operational 12-01-2018 4
People are aware of the
project. No major concerns
were expressed except
related to compensation for
crop damaged during
project activity
Local People were
supportive
6
Badiya
Mandu,
Dewas
Operational 12-01-2018 6
People were apprehensive
about construction activities
and if they would cause
nuisance. Assured that best
practices are incorporated
as per EMP
Best practices are
incorporated as per
EMP
16
7 Malgaon,
Khandwa Operational 12-01-2018 3
Some people wanted to
know if construction can be
carried out during non-
cultivation season. Assured
that it is followed by EPC
contractor
Construction
activities will be
stopped during
cultivation period to
avoid crop
damages
3.3 Plan for further Consultation in the Project
19. The consultation process will be continued under the project as necessary. The PMU
will be responsible for conducting the consultation as envisaged for the project:
(i) In case of any change in the site for substations and/or distribution line alignments,
the APs and other stakeholders will be consulted regarding the factors that
necessitated the change, efforts taken to minimize resettlement impacts and
mitigation measures available in accordance with the principles of the RP.
(ii) The PMU will carry out information dissemination sessions in the project area and
solicit the help of the local Panchayat/community leaders and encourage the
participation of the APs in plan implementation.
(iii) During the implementation of RP, PMU will organize public meetings, and will
appraise the communities about the progress in the implementation of project
works.
(iv) Consultation and focus group discussions will be conducted with the vulnerable
groups such as women, to ensure that the vulnerable groups understand the
process and their needs are specifically taken into consideration in the
implementation.
3.4 Disclosure
20. DISCOM-west provided relevant information in a timely manner, in an accessible place,
and in a form and language (Hindi/ English) understandable to stakeholders. Notification
as per the electricity act, 2003 on project information disclosed in the local newspaper. A
summary of the draft RP has been made available in local at relevant local government
offices and at the PMU and site offices. This DDR will be disclosed on ADB website and
MP Discom- west. Information dissemination and consultation will continue throughout
the project implementation, and especially during the implementation of the project.
17
4. GRIVANCE REDRASSAL MECHANISM
4.1 Introduction
21. A grievance redressal mechanism (GRM) has been established to receive, evaluate and
facilitate the resolution of displaced people‟s concerns, complaints, and grievances
about the social issues arising out of the project and RP implementation. The GRM is
aimed to provide a trusted way to voice and resolve concerns linked to the project, and
to be an effective way to address displaced people‟s concerns without allowing it to
escalate resulting in delays in project implementation.
4.2 Grievance Redressal Committees
22. The EA has establish a mechanism to receive and facilitate the resolution of affected
persons‟ concerns and grievances about physical and economic displacement and other
project impacts, paying particular attention to the impacts on vulnerable groups. The
grievance redress mechanism will address affected persons‟ concerns and complaints
promptly, using an understandable and transparent process that is gender responsive,
culturally appropriate, and readily accessible to the affected persons at no costs and
without retribution.
23. A Grievance Redress Committee (GRC) has been formed as provided in annexure-4, to
ensure APs grievances are addressed and facilitate timely project implementation.
Minor grievance will be redressed at the site level through the concerned project
engineer and contractor failing which the case will be referred to the GRC.
24. The GRC have representatives from, EA, the officer in PMU designated for safeguards
compliance comprising Project Director, Environmental Specialist, SE level officers. The
GRC generally have meeting once in a month or as and when required by EA. The main
responsibilities of the GRC are to:
i) provide support to APs on problems arising from land/property acquisition and
crop/tree compensation; if any
ii) record AP grievances, categorize, and prioritize grievances and resolve them within
4 weeks; if any.
18
iii) immediately inform the EA of serious cases; and
iv) Report to APs on developments regarding their grievances and decisions of the
GRC and the EA. Other than disputes relating to ownership rights and
apportionment issues, GRC will review grievances involving all resettlement
benefits, compensation, relocation, replacement cost and other assistance.
Grievances will be redressed within 4 weeks from the date of lodging the
complaints. The GRCs will continue to function during the life of the Project
including the defects liability period.
19
5. CONCLUSION
25. All new substation sites had constructed in Govt land & barren land only. There is no any
encroachment of acquired land for all substations.
26. All subproject components had constructed in existing facilities on Govt land & barren land
only. There is no any encroachment of acquired land for all existing facilities.
27. There are no grievances recorded during project / subprojects implementation.
28. Aside from best engineering practice and survey approaches of project planning, where land
acquisition was one of the primary considerations in selecting the sites for the distribution
lines to minimize social impacts on surrounding community.
29. The distribution lines mainly follow the road ROW for which obtains permission has been
obtained from the concerned department. Wherever the distribution lines passes through the
agriculture land care has been taken to place the pole on the plot edges to avoid impacts on
the land.
30. To finalize the distribution line network, walkover surveys, were held with the participation of
local communities and representatives of local rural bodies.
31. All project components do not affect / damage vegetation, crops. Also project activates are
stopped during cultivation/ harvesting season to avoid any loss of crops. Also going on
project components / activities do not effect to indigenous people & any settlements.
32. Based on due diligence survey & field visits, it is concluded that DISCOM-West subproject
does not adverse social impact.
33. Outcome of project implementation will be positive social impact to community for direct &
indirect employment & local area development as well as fulfillment of power demand on
rural level.
34. Project is 100% completed on June 2017 by conforming all social safeguard polices &
applicable National & Local laws under PMU of DISCOM-West.
35. DISCOM-West has ensured contractor‟s on bid contract document for ADB social safe guard
policies for employed staff/ local labor for project implementation going on.
36. Execute agency is closely monitoring and coordinating with respective departments to
expedite RP activities implementation and resolving of any social issues, if any.
20
ANNEXURE-I DETAILS OF PROJECT COMPONENTS OF DISCOM-WEST UNDER ADB LOAN-2830
Detailed Scope of work with Division wise under ADB Loan-2830-Ind
Sr.
No.
Des
crip
tio
n o
f P
roje
ct /
Su
b-p
roje
cts
un
der
fee
der
sep
ara
tion
Pro
ject
-MF
F-
Tre
nch
-2
Un
it
Tota
l u
pd
ate
d q
uan
tity
exec
ute
d b
ase
d o
n S
urv
ey
as
on
Ju
ne-1
7
Sh
aja
pu
r
Dis
tric
t
Man
dsa
ur
Dis
tric
t
Nee
mu
ch
Dis
tric
t
Ind
ore
Dis
tric
t
Dh
ar
Dis
tric
t
Kh
arg
on
e
Dis
tric
t
Kh
an
dw
a
Dis
tric
t
Barw
an
i
Dis
tric
t
Bu
rhan
pu
r
Dis
tric
t
Ratl
am
Dis
tric
t
Dew
as
Dis
tric
t
Ujj
ain
Dis
tric
t
Jh
ab
ua
Dis
tric
t
Tota
l
Sh
uja
lpu
r
Garo
th
Malh
ar-
garh
Man
dsa
ur
Sit
am
ou
Nee
mu
ch
Man
asa
Jaw
ad
Ind
ore
Dh
ar
kh
arg
on
e
kh
an
dw
a
Barw
an
i
Bu
rhan
pu
r
Ratl
am
Dew
as
Ujj
ain
Jh
ab
ua
Component-1- Feeder Separation
1
Extension of 11
KV bay in existing
33/11 KV sub-
station
Nos 328 48 36 32 34 36 26 30 48 - - - - - - - - - - 290
2
11 KV line on 140
KG 8 m PCC Pole
with DP KM 3708 327.2 650 460.06 540 590 318.44 399.3 423 - - - - - - - - - - 3708
3
25 KV, 11/0.433
KV, 3 Phase Dist.
Transformer S/s
with Metering
Nos 4836 482 755 531 610 733 325 370 552 - - - - - - - - - - 4358
4
11 KV DP
Structure on 8m
PCC Pole Nos 5850 331 680 461 551 610 319 410 436 - - - - - - - - - - 3798
5 Four Pole
Structure Nos 141 12 26 18 24 17 16 12 16 - - - - - - - - - - 141
6 Road/River/
Railway Crossings Nos NA NA NA NA NA NA NA NA NA NA NA NA NA NA NA NA NA NA NA 0
Component-2- HVDS and Associated LV Lines 0
21
7
LV to HV
Conversion
(HVDS) KM 1792 26 48 35 41 37 32 26 22 - - - - - - - - - - 267
8
LV line 3 Phase 5
wire overhead
using AB Cable
XLPE 50 Sq.mm
on PCC pole140
KG 8 M
KM 222 2 7 7 5 6 4 5 4 - - - - - - - - - - 40
9
Replacement of
AAAC/ ACSR
conductor by AB
cable XLPE 50
Sqmm on existing
3 Phase LV line
KM 1242 27.62 82.26 66.23 63.05 76.11 43.08 62.71 80.37 - - - - - - - - - - 501.43
10
Replacement of
AAAC/ ACSR
conductor by AB
cable XLPE 25
Sqmm on existing
3 Phase LV line
KM 1886.12 81.81 341.56 211.69 290.16 295.8 198.02 211.9 255.46 - - - - - - - - - - 1886.4
Component-3-Quality improvement and metering 0
11
Cost of providing
meters for new &
existing
connections with
renovation of
Service lines
(Installation of
Energy Meter)
Nos 162719 15050 22416 31167 21656 23883 15644 18799 14104 - - - - - - - - - - 162719
Component-4-Upstream 33 KV New work strengthening 0
12
33 KV Line on
H-beam
(152x152mm), 33
KV bay power
transformer
augmentation &
NA 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
22
new power
substation
13 33 KV line with
DOG Conductor KM 343 - - - 12 12 0.5 - - 21 27 8 12.5 1.3 12 14 12 15 - 147.3
14 33 KV bay at EHV
S/s Nos. 8 - - - - - - - - - - - - - - - - - - 0
15
33 KV Guard for
road/river/line
crossing KM 673 - - - 1 1 0 - - 2 2 - 1 - 1 1 1 1 - 11
16
33 KV DP
structure on PCC
Pole Nos. 357 - - - 12 12 1 - - 20 30 8 13 2 12 14 12 15 - 151
17
New 33/11 KV S/s
(from temporary
to permanent) - 0
1.6 MVA Nos. 1 - - - - 1 - - - - - - - - - - - - - 1
3.15 MVA Nos. 23 - - - 1 0 2 - - - 3 1 - 3 - 1 - 12 - 23
5 MVA Nos. 2 - - - - - - - - - 1 - - - - 1 - - - 2
18 New 3.15 MVA,
33/11 KV S/s Nos. 31 - - - 2 1 1 - - 3 4 1 6 2 3 2 3 3 - 31
19 Augmentation of
power transformer - - - - - - - - - - - - - - - - - - 0
from 1.6 to 3.15
MVA Nos. 4 - - - - - 1 - - - - - - - - 2 - 1 - 4
from 3.15 to 5
MVA Nos. 76 0 - - 1 1 - 1 1 5 10 11 12 2 7 5 12 4 4 76
20
Addl. 3.15 MVA
power transformer
in existing S/s Nos. 21 2 1 - 1 1 1 1 1 2 3 2 - - 1 1 3 - 1 21
24
GOVERNMENT OF MADHYA PRADESH
MINISTRY OF REVENUE DEPARTMENT
No. F 6-25/2010/Seven/Nazool Bhopal/Dated: 18.08.2010 To, The Commissioner (All), Madhya Pradesh The Collector (All), Madhya Pradesh Sub: Allotment of Government Land free of cost to M.P. Electricity Transmission Company, M.P. Electricity Generating Company and M.P. Electricity Distribution Companies. The Revenue Department, Government of Madhya Pradesh Notification No. F-6-150/ 2003/Seven/Nazool, Dated: 02.08.2007, through which directives were issued that after 01.04.2008 the land allotted to the M.P. Electricity Board and it successor Companies will have to pay 50% of premium on market rate and as per law to pay annual lease rent is hereby cancelled. The Government of M.P. now decided that for Electricity Generation/Transmission and Distribution related projects, the Revenue Department will allot the land to Energy Department. Energy Department will allot these Govt. Land to M.P. Electricity Transmission Company, M.P. Electricity Generating Company and M.P. Electricity Distribution Companies without premium and @ Rs. 1/- as annual lease rent. Please ensure to take necessary action as per the above decision. -sd-
(N. S. Parmar) Deputy Secretary
Govt. of M.P. Revenue Deptt. Endorsement No.F-6-25/2010/VII/Nazool Bhopal/Dated 18 AUG 2010 Copy to: 1. Honr‟ble Chairman, M.P. Electricity Regulatory Commission, Ministry Bhopal. 2. The Principal Secretary Govt. of M.P., Finance Deptt., Bhopal. 3. The Secretary, Govt. of M.P., Energy Deptt., Bhopal. 4. The Accountant General, Madhya Pradesh, Gwalior. 5. The Commissioner, Land-Records and Settlement. M.P. Gwalior. – for information
and needful action please. 6. For Guard File -sd-
Deputy Secretary Govt. of M.P. Revenue Deptt.
26
GOVERNMENT OF MADHYA PRADESH
MINISTRY OF ENERGY DEPARTMENT
No. F 6-2/2009/13 Bhopal/Dated: 26 AUG 2010
To,
1. The Chairman & Managing Director,
M.P. East/Central/West Discom Vidyut Vitaran Company Limited,
Jabalpur/ Bhopal/ Indore
2. The Chairman & Managing Director
M.P. Power Generating/ Transmission Company Limited,
Jabalpur
3. The Managing Director
M.P. Power Trading Company Limited,
Jabalpur
4. The Secretary
M.P. State Electricity Board
Jabalpur
Sub: Allotment of Government Land free of cost to M.P. Electricity Transmission
Company, M.P. Electricity Generating Company and M.P. Electricity Distribution
Companies.
For the successor companies of M.P. State Electricity Board, viz. M.P. Power
Generating Limited, M.P. Power Transmission Company Limited and all the three
Electricity Distribution Companies for their Projects, the Government land will be
allotted without premium and @ Rs. 1/- as annual lease rent and related notification of
Revenue Department viz. F-6-25/2010/VII/Nazool, Bhopal/Dated 18 AUG 2010 copy
enclosed, for information and necessary action please as per the directives given.
-sd-
(K. C. Dubey)
Upper Secretary
Govt. of M.P. Energy Deptt.
28
OFFICE OF THE CHAIRMAN & MANAGING DIRECTOR
Madhya Pradesh Pashchim Kshetra Vidyut Vitran Company Limited, Indore
No. CMD/WZ/01/Estt-3/156/16956 Indore/Dated: 17 SEP 2010 To, The Chief Engineer (IR/UR) MPPKVVCL Indore/Ujjain Sub: Allotment of Government Land free of cost to M.P. Electricity Transmission Company, M.P. Electricity Generating Company and M.P. Electricity Distribution Companies. Ref: Upper Secretary, Government of M.P., Energy Department, Bhopal Letter No. F-6-2/2009/XIII, Bhopal/Dated 26 AUG 2010. With reference to above subjected matter, wherein it has been mentioned for the successor companies of M.P. State Electricity Board, viz. M.P. Power Generating Limited, M.P. Power Transmission Company Limited and all the three Electricity Distribution Companies for their Projects, the Government land will be allotted without premium and @ Rs. 1/- as annual lease rent and related notification of Revenue Department viz. F-6-25/2010/VII/Nazool, Bhopal/Dated 18 AUG 2010 copy enclosed, for information and necessary action please as per the directives given. Encl: As above -sd-
Addl. Secretary OFFICE OF THE CHIEF ENGINEER (IR)
Madhya Pradesh Pashchim Kshetra Vidyut Vitran Company Limited, Indore Endorsement No.13686/CE/IR/Works Indore/Dated 21 SEP 2010 Copy to: SE (City/O&M) Circle MPPKVVCL, Indore/ Khandwa/ Khargone/ Dhar/ Jhabua/ Barwani/ Burhanpur – please ensure necessary action as per above instructions. Encl: As above -sd-
Superintending Engineer O/o C.E. (I.R.) Indore