Africa Dialogues- NAIROBI - Global Sustainable Electricity ...
ITy - UoN Repository - University of Nairobi
-
Upload
khangminh22 -
Category
Documents
-
view
1 -
download
0
Transcript of ITy - UoN Repository - University of Nairobi
CONTRACTORS OFFACTORS INFLUENCING PERFORMANCE OF
GOVERNMENT-FUNDED BUILDING PROJECTS IN KIRINYAGA COUNTY,
KENYA.
%ITy
* os
BY
MUGUIY1 MAUREEN WANJIKU
A RESEARCH PROJECT REPORT SUBMITTED IN PARTIAL FULFILMENT OF
THE AWARD OF A MASTER OF ARTS DEGREE IN PROJECT PLANNING AND
MANAGEMENT, THE UNIVERSITY OF NAIROBI
2012
DECLARATION
This Research Project Report is my original work and has not been presented for a degree in this
university or any other institution o f higher learning.
MUGUIY1 MAUREEN WANJIKU
1.50/ 63941/2010
Date °.s.)..
This Research Project Report has been submitted for examination with my approval as the
University supervisor.
DR. CHRISTOPHER M. GAKUO
D ate.............?. .fi'. Lh®.!. frT.
Senior Lecturer, Department of Extra-Mural Studies
University of Nairobi
u
DEDICATION
1 dedicate this study to my father Gerald Muguiyi Muchiri for his support and encouragement
throughout my life and academic journey.
in
ACKNOWLEDGEMENT
1 wish to extend my gratitude to the University of Nairobi for offering me the study opportunity
which has opened wider avenues o f knowledge and self-discovery both in my professional and
personal endeavours. Special thanks go to my supervisor Dr. C. Gakuo for his guidance in
developing this study, Dr. L. Otieno for ensuring unwavering focus on the academic programme
and Prof. Macharia for his enthusiastic ability and encouragement o f ‘outside the box’ perception
of issues. I further wish to thank the non-teaching staff at the Nyeri Extra-Mural Centre for their
encouragement and support.
I am thankful to my colleagues for their support and knowledge-sharing especially Group Five
members with whom we have acquired deeper insight into project management issues. I also
acknowledge the support of Arch. Muli, Arch. Munano and Arch. Kafuna of Min. of Public
Works and Prof. C. Ochieng of Jomo Kenyattta University of Agriculture and Technology for
their mentoring.
Finally, 1 wish to thank my son, siblings and friends for their support, with a special mention of
my sister Wambui whose support has been immeasurable.
IV
TABLE OF CONTENTS
DECLARATION............................................................................DEDICATION................................................................................ACKNOWLEDGEMENT............................................................TABLE OF CONTENTS.............................................................LIST OF TABLES.........................................................................LIST OF FIGURES......................................................................ABBREVIATIONS AND ACRONYMS..................................ABSTRACT...................................................................................
CHAPTER ONE: INTRODUCTION Ok}fi/r.
1.1 Background of the Study............................ ,vr,'.. .' ”*(Jy ,'*r' .
1.2 Statement o f the Problem...........................^
1.3 Purpose of the Study......... ........................... yo4......1.4 Research Objectives................................................................................
1.5 Research Questions................................................................................
1.6 Significance of the Study........................................................................
1.7 Delimitation of the Study......................................................................
1.8 Limitations of the Study.........................................................................
1.9 Assumptions of the Study......................................................................
1.10 Definition of Significant Terms............................................................
1.11 Organisation of the Study Report.........................................................
CHAPTER TWO: LITERATURE REVIEW
2.1 Introduction.............................................................................................
2.2 Project Management and Government-funded Building Projects....
2.3 The Building Project Process................................................................
2.4 Measurement of Contractors’ Performance........................................
2.5 Financial Issues and Contractors’ Performance.................................
2.6 Human Resources Conditions and Contractors’ Performance..........
2.7 Site Characteristics and Contractors’ Performance...........................
2.8 Design Quality Aspects and Contractors’ Performance...................
2.9 Legal and Regulatory Environment and Contractors’ Performance.
2.10 Organisational Culture and Contractors’ Performance.....................
Pageiiiiiivvixxxixii
1
3
3
3
4
4
4
4
4
5
6
7
7
8
9
12
13
14
15
15
16
v
2.11 Conceptual Framework.................................................................................................. 17
2.12 Summary.......................................................................................................................... 18
CHAPTER 3: RESEARCH DESIGN AND METHODOLOGY
3.1 Introduction...................................................................................................................... 19
3.2 Research Design.............................................................................................................. 19
3.3 Target Population............................................................................................................ 19
3.4 Sample Size and Sampling Procedure........................................................................... 20
3.5 Research Instruments...................................................................................................... 20
3.6 Pilot Study........................................................................................................................ 20
3.6.1 Reliability............................................................................................................. 21
3.6.2 Validity.................................................................................................................. 21
3.7 Data Collection Procedure............................................................................................... 21
3.8 Data Analysis Procedure................................................................................................. 22
3.9 Ethical Considerations..................................................................................................... 22
3.10 Operationalisation of Variables...................................................................................... 22
3.11 Summary............................................................................................................................ 27
CHAPTER 4: DATA ANALYSIS, PRESENTATION AND INTERPRETATION
4.1 Introduction...................................................................................................................... 28
4.2 Response Rate.................................................................................................................. 28
4.3 General Information........................................................................................................ 28
4.3.1 Age Bracket......................................................................................................... 28
4.3.2 Gender.................................................................................................................. 29
4.3.3 Education Level.................................................................................................. 29
4.3.4 Company’s Registration Category.................................................................... 30
4.3.5 Years of Operation.............................................................................................. 30
4.4 Project Performance........................................................................................................... 31
4.4.1 Descriptive Statistics............................................................................................. 31
4.4.2 Project Performance Issues.................................................................................. 31
4.5 Financial Issues’ influence on Contractors’ Performance............................................. 32
4.5.1 Descriptive Statistics............................................................................................ 32
4.5.2 Specific Financial Issues’ influence.................................................................... 32
vi
4.5.3 Financial Issues and Successful Completion of Projects................................. 33
4.6 Human Resources Conditions’ influence on Contractors’ Performance.................... 35
4.6.1 Descriptive Statistics........................................................................................... 35
4.6.2 Specific Human Resources Conditions’ influence........................................... 35
4.6.3 Human Resources Conditions and Successful Completion of Projects........ 36
4.7 Site Characteristics’ influence on Contractors’ Performance...................................... 37
4.7.1 Descriptive Statistics............................................................................................ 37
4.7.2 Specific Site Characteristics’ influence.............................................................. 38
4.7.3 Site Characteristics and Successful Completion of Projects........................... 38
4.8 Design Quality Aspects’ influence on Contractors’ Performance............................... 40
4.8.1 Descriptive statistics............................................................................................ 40
4.8.2 Specific Design Quality Aspects’ influence...................................................... 40
4.8.3 Design Quality Aspects and Successful Completion of Projects.................... 41
4.9 Relationship between Factors and Contractors’ Performance...................................... 43
4.9.1 Correlation between Financial Issues and Contractors’ Performance......... 43
4.9.2 Correlation between Human Resources Conditions and 43
Contractors’ Performance.................................................................................
4.9.3 Correlation between Site Characteristics and Contractors’ Performance... 43
4.9.1 Correlation between Design Quality Aspects and 43
Contractors’ Performance...................................................................................
4.9.5 Correlation between Factors............................................................................... 43
4.10 Summary.......................................................................................................................... 45
CHAPTER 5: SUMMARY OF FINDINGS, DISCUSSIONS, CONCLUSIONS
AND RECOMMENDATIONS
5.1 Introduction....................................................................................................................... 46
5 2 Summary o f Major Findings........................................................................................... 46
| 5.3 Discussions........................................................................................................................ 48
5.4 Conclusion......................................................................................................................... 50
5-5 Recommendations.............................................................................................................. 51
I 5.6 Suggestions for Further Study.......................................................................................... 51
REFERENCES:.......................................................................................................................... 52
vii
APPENDICES:
Appendix 1: Confirmation Letter from the University....................................................... 57
Appendix 2: Letter o f Introduction to the Ministry of Public Works, Kirinyaga 58
County..............................................................................................................
Appendix 3: Sample Letter of Introduction to Respondents.............................................. 59
Appendix 4: Sample Questionnaire.........................................................................................
Appendix 5: Frequency Tables o f Questionnaire Responses on Variables......................... 63
Appendix 6: Raw data.............................................................................................................. 69
Appendix 7: Reliability and Validation Statistics.................................................................. 71
Appendix 8: Classification of Building Contractors in Kenya............................................. 72
viii
23
28
29
29
29
30
30
31
31
32
33
34
35
36
36
37
38
39
40
41
41
44
47
48
48
Operational T able........................................................................................
Response Rate..............................................................................................
Age Bracket.................................................................................................
Gender..........................................................................................................
Education Level...........................................................................................
Company’s Registration Category............................................................
Years of Operation......................................................................................
Descriptive Statistics- Project Performance.............................................
Project Performance Issues.......................................................................
Descriptive Statistics- Financial Issues....................................................
Financial issues and Successful Completion of Projects.......................
Ways in which Financial Issues influence Successful Completion
of Projects....................................................................................................
Descriptive Statistics- Human Resources Conditions............................
Human Resources Conditions and Successful Completion o f Projects
Ways in which Human Resources Conditions influence
Successful Completion of Projects...........................................................
Descriptive Statistics- Site Characteristics..............................................
Site Characteristics and Successful Completion of Projects.................
Ways in which Site Characteristics influence Successful Completion
of Projects....................................................................................................
Descriptive Statistics- Design Quality Aspects......................................
Design Quality Aspects and Successful Completion o f Projects.........
Ways in which Design Quality Aspects influence Successful
Completion of Projects.............................................................................
Correlation Analysis..................................................................................
General Findings with respect to the Objectives....................................
Summary o f Correlation between the Independent and
Dependent Variables..................................................................................
Summary of Significant Correlation between Independent Variables.
LIST OF TABLES
ix
BS
CDF
GDP
GOK
KSh
MOF
MOPW
MTEF
NCAPD
OECD
P\11
SPSS
USD
ABBREV IATIONS AND ACRONYMS
British Standards
Constituency Development Fund
Gross Domestic Product
Government of the Republic of Kenya
Kenya shillings
Ministry of Finance, Government of Kenya
Ministry of Public Works, Government o f Kenya
Medium Term Expenditure Framework
National Coordinating Agency for Population and Development
Organization for Economic Co-operation and Development
Project Management Institute
Statistical Package for Social Sciences
US dollars
xi
ABSTRACT
Building projects, a component o f infrastructure development, are key drivers of economic growth o f a country. Governments globally thus invest heavily in this sector. Their contribution however, can only be determined by their performance, with the ultimate goal being project success. The concept o f project success has remained ambiguously defined in the building industry although time, cost and quality are considered to be the predominant criteria. In Kenya, government-funded building projects are implemented through a tri-party endeavour consisting of the financier/client, the project manager, and the contractor, who must work harmoniously to ensure project success. The implementing entity that carries out the actual construction is the contractor. This study focuses on this third party. Whereas the performance of contractors undertaking such projects in Kirinyaga County and in Kenya in general, is influenced by specific factors that impact on project success, very little reliable information is available on what these factors are and their influence. As such, this study sought to investigate the influences of the factors identified as financial issues, human resources conditions, site characteristics and design quality aspects, derived from relevant literature review and as conceptualized. The research design of choice was descriptive survey, which utilizes elements of both quantitative and qualitative research methodologies thereby addressing the objectives and research questions, and ensuring coherence and rigour. Data was gathered through written questionnaires having closed and open-ended structured questions; the latter to give deeper insight into the study problem. Respondents for the study were contractors undertaking government-funded building projects in Kirinyaga County. The study was a census with the resultant descriptive statistics presenting inferential findings on the target population of contractors who are considered to be a homogeneous group. A pilot study was carried out to test reliability and ascertain validity of the data collection instrument. Data was analyzed with reference to the research objectives through use of SPSS. Major findings of the research reflect the propositions contained in various studies and models as reviewed from literature sources that basically, the factors identified influence project performance. The study further reveals the relative influence of each o f the factors, o f greatest significance being human resources conditions and design quality aspects. A key derivative o f this study is the distinctive emergence o f the human resources element as the prime factor influencing the performance of contractors o f government-funded building projects in Kirinyaga County. Essentially, the research findings suggest that addressing all the factors identified, with particular focus on the human resources and design quality elements, would enhance the contractors’ performance of the projects and ensure higher rates of projects success. Suggestions are put forth for further study on interest areas that may have a significant influence on building projects performance.
Xll
CHAPTER ONE
INTRODUCTION
1.1 Background of the Study
The annual value o f the construction sector cannot be understated. It is in the order of USD 1.5
trillion, constituting about 8% of GDP, 60% of fixed capital formation and represents 7% of total
employment in world economy (Njuguna H., 2008). In Kenya, on average the construction
industry is projected to grow annually at a rate of 16.7% (GOK, 2009) and the government has
adopted it as an engine o f stimulating economic growth by enhancing funding towards it. This is
further underscored in key development blueprints such as the Constitution of Kenya (GOK,
2010) and the long-term national planning strategy, Vision 2030 (GOK, 2007).
Governments and non-government agencies have been changing trends from ad hoc
development activities to projects and programmes in all development sectors, premised on the
conception o f projects as primary drivers of economic growth as they contribute significantly to
a nation’s Gross Domestic Product (Omar O., 2006). However, their level of contribution
towards this end can only be reasonably determined by their performance. Results from studies
on performance however point to a general trend o f non-successful delivery of projects.
Examples o f such results include: a study of over 250 organizations across the globe found that
successful delivery of projects was 30% for respondents from UK and Europe, 40% for those of
USA, and 18% for delivery on time and 23% for delivery on budget for those of Asia Pacific
(PIPC, 2006); and of the 1035 infrastructure sector projects completed during April 1992 and
March 2009 in India. 41% faced cost over-runs and 82% witnessed time over-runs (PMI-KPMG,
2010).
This study focused on an aspect o f governments’ funding of development projects. One of the
key investment sectors for governments is infrastructure development. Building projects are a
component o f this. These are capital intensive ventures which require proper management to
ensure efficient use of input resources and ensure intended effectiveness (OECD, 2006). A
policy research working paper on the success of infrastructure projects in low-income countries
1
(Limodio N„ 2011) supports this by quoting World Bank figures that every year more than USD
200 billion is spent on this sector in developing countries, roughly a fifth o f total investment.
Kenya is rated as a low-income country (World Bank, 2011). Similar to other such countries, the
construction industry is very important for the Kenyan economy. It accounts for 5% of the
country’s GDP and employs about 1 million people with an estimated annual wage bill of
KSh3.2 billion. According to recent findings by the Kenya National Bureau of Statistics,
Kenya’s economy grew by 4.9% in the first quarter o f 2011 thanks to the improved productivity
in the construction industry thereby contributing KSh. 12.6 billion to Kenya’s GDP (Njihia M.,
2011).
In Kenya, planning and implementing of government-funded building projects is a tri-party
endeavour consisting of three key players: the financier or client being the government through
its various agencies, the project manager being the Ministry o f Public Works which is mandated
to provide technical expertise in implementing the projects in close liaison with other relevant
ministries and departments of government, and the contractor, an independent entity that carries
out the actual construction (MOPW, 2006).
This study was premised on the acknowledgement that for building projects to succeed, there is
need to understand and ensure harmonious working o f all the key players. The focus on the
contractor is based on the fact that full realisation of the built product is critically reliant on this
party. The study therefore sought to address factors that influence this third player’s
performance. It further strove to add to the body of knowledge to enhance development in the
construction project management discipline and subsequent improvement of performance o f
government-funded building projects.
2
1.2 Statement of the Problem
The performance of contractors of government-funded building projects in Kirinyaga County
and Kenya in general is poor. The success rate of government-funded construction projects in
Kenya, in which building projects are inclusive, stands at 15% (GOK, 2009). Information
garnered from the Kirinyaga County Works Office, Ministry of Public Works which is the office
managing such projects in the study area presented a similar scenario, with successful project
delivery rates o f about 25% every financial year.
Having noted that the contractors’ performance is fundamental to realising government-funded
building projects success, it was imperative thus to identify and critically study key factors
influencing their performance with a view to gaining deeper insight o f the scenario and the
evident problem of poor performance.
1.3 Purpose of the Study
The purpose o f this study was to investigate the factors influencing performance of contractors of
government-funded building projects in Kirinyaga County, Kenya.
This was to be achieved by identifying key factors through conceptualisation and from relevant
literature and subsequently establishing their influence on performance from the contractors’
own perspective and experiences.
1.4 Research Objectives
The study was guided by the following objectives:
1. To establish the influence o f financial issues on contractors’ performance of government-
funded building projects in Kirinyaga County, Kenya.
2. To determine the influence of human resources conditions on contractors’ performance of
government-funded building projects in Kirinyaga County, Kenya.
3. To establish the influence of site characteristics on contractors’ performance of
government-funded building projects in Kirinyaga County, Kenya.
4. To determine the influence of design quality aspects on contractors’ performance o f
government-funded building projects in Kirinyaga County, Kenya.
3
1.5 Research Questions
The study sought to answer the following questions derived from the research objectives:
1. How do financial issues influence contractors’ performance o f government-funded
building projects in Kirinyaga County, Kenya?
2. How do human resources conditions influence contractors’ performance of government-
funded building projects in Kirinyaga County, Kenya?
3 How do site characteristics influence contractors’ performance o f government-funded
building projects in Kirinyaga County, Kenya?
4. How do design quality aspects influence contractors’ performance o f government-funded
building projects in Kirinyaga County, Kenya?
1.6 Significance of the Study
The study was aimed at adding value to government’s investment in building projects in Kenya.
It is expected to contribute to planning, evolution o f practical and sustainable responses,
synthesis o f risk management strategies, and quality development that will enhance the
perfonnance o f the contractors and overall projects’ performance.
1.7 Delimitation of the Study
The study was carried out within Kirinyaga County, Kenya. Target respondents were contractors
executing government-funded building projects managed by the Ministry of Public Works,
within this county. This provided a specific project management environment that has stipulated
operations and procedures. The field study was undertaken within the month of June 2012.
1.8 Limitations of the Study
Limitations o f the study were minimal as the study was carried out in a relatively small area and
the target respondents were few. However, this thus required a high response rate that was
achieved through intense follow up for returns.
1.9 Assumptions of the Study
The study assumptions were that the target contractors are reflective and adequately
representative of similar contractors in Kenya thus adding value to the results, and that the
4
respondents answered questions truthfully and objectively, they were knowledgeable and
cooperated willingly.
1.10 Definition of Significant Terms
Contractor: Refers to a person or firm who deploys material and human resource inputs to carry
out project works as per the stipulated scope, budget and timelines. For government-funded
building projects in Kenya, such entities must be appropriately registered to carry out the type
and scope o f projects they undertake.
Design quality aspects: Matters related to translation of a building project’s design into physical
reality by constructing it on a site.
Financial issues: Aspects related to the cost and funding o f the building projects.
Human resources conditions: Issues related to the diversity, knowledge and skills of the
workforce planning and executing building projects works.
Legal and regulatory environment: The policy, legal and institutional framework that governs
building projects.
Organisational culture: The sum total of a contractor firm’s past and current assumptions,
experiences, philosophy and values expressed in its inner workings, interactions with the outside
world, and future expectations.
Performance: Refers to execution of government- funded building projects in accordance with
planned project scope and specifications, work programming and completion schedules and
budget.
Site characteristics: Unique features of a site on which a building project is undertaken.
5
1.11 Organisation of the Study Report
Chapter One provides an overall introduction of the study. It comprises of the background of the
study, statement o f the problem, research objectives, research questions and significance of the
study It is also inclusive o f delimitation and limitations and of the study, assumptions, definition
of significant terms and the outline of the organisation o f the study report.
Chapter Two presents the literature review, with sub-topics containing the introduction, review
of relevant literature material fomiing the theoretical framework base, the conceptual framework
and the summary.
Chapter Three covers the research methodology. It consists of the research design, target
population, sample size and sampling procedure, research instrument and its reliability and
validity, data collection procedure, methods of data analysis, the operational definitions of the
variables and a summary.
Chapter Four covers data analysis and presentation of results. The chapter analyses the data that
was collected and offers interpretation of the results from the findings collected from the
respondents.
Chapter Five consists of the summary of major findings, discussions of the findings vis-a-vis the
literature review, conclusions and recommendations o f the study.
The report also contains a list o f references of the study’s scholarly literature sources and
appendices relevant to the study.
6
CHAPTER TWO
LITERATURE REVIEW
2.1 Introduction
This chapter delves into identifying and critically analysing key factors that influence the
performance o f contractors of government-funded building projects. It outlines the discipline of
project management in relation to government-funded building projects and expounds on the
building project process for deeper insight. This is followed by an analysis of measurement o f
contractors’ performance of building projects from relevant studies and models. Subsequent sub
sections address the key factors thus identified. Finally, it contains the conceptual framework
derived from the preceding theoretical analysis.
2.2 Project Management and Government-funded Building Projects
Projects are carried out to meet a specific objective and they can be initiated by any entity
ranging from individuals to institutions. Fundamental to this initiation is the resources aspect that
determines the proponents of the project. Since building projects are resource-intensive,
governments are major project initiators as they usually have or can access resources required.
Government-funded building projects which are the focus of this study generally have a project
cycle consisting of concept, design, tendering, pre-construction, construction and commissioning
stages. Management of the projects is normally in a tri-party form with the government as the
financier, a project manager to administer resources and activities, and the implementing entity
in form of a contractor (Uher T. and Davenport P., 2009).
Project management which is a discipline that has had rapid development in the last few decades
(Cleland D. and Gareis R., 2006) a compound term consisting of two elements: ‘project’ and
‘management’. A project is defined as a temporary endeavour that has a definite beginning and
end, undertaken to create a unique product or service. Management in general is a term referring
to planning, organising, staffing, directing and controlling operations and processes (Nokes S.
and Kelly S., 2007). The compound term of project management is therefore the application o f
7
knowledge, skills, tools and techniques to project activities in order to meet or exceed
stakeholder needs and expectations from a project. This requires balancing o f competing needs
of scope, time, cost and quality, and also of stakeholders with differing needs and expectations.
Scope and quality specify what is to be achieved. The time aspect is established with specified
start and end dates, whereas the cost element is in regard to the limited financial resources to be
expended. These factors determine project performance. Although all these elements are
interrelated, it is important to note that for building projects, delay has a major impact on a
project’s cost (Assaf S. and Al-Hejji S., 2006).
2.3 The Building Project Process
Hendrickson C., (2008) provides a detailed analysis o f the process. Design and construction
process for building projects is a complex integrated system. ‘Design’ is defined as the process
of creating the description of a new facility, usually represented by detailed plans and
specifications; while ‘construction’ refers to employment o f activities and resources required to
make the design a physical reality.
Building projects are unique in a number of aspects. First, nearly every facility is custom
designed and constructed with the facility satisfying conditions peculiar to a specific site
location, pre-determined functional requirements, legal and regulatory controls, budgetary
constraints, and implementation time-lines. Secondly, because of technological complexity and
market demands, changes of design and implementation plans during construction are not
uncommon.
He further explains the design process as involving the following integrated actions: formulation
of the problem; analysis and interpretation to refine the problem; search for a set of potential
solutions to fulfill the specified functional requirements; decision based on evaluation of each o f
the potential alternatives to obtain the best solution; specification of the chosen solution in
enough detail for implementation; and finally, modification if required based on if the solution is
found to be wanting or if new information is discovered in the process o f design. This process
holds true from conceptualisation to detail design while becoming increasingly more formalised.
The construction process on the other hand consists of identification and utilization of the
primary inputs of labour, material and equipment which must be efficiently and effectively
8
coordinated. The design and construction processes are non-independent with information and
actions transmitted back and forth, thereby compounding the complexity issue.
2.4 Measurement of Contractors’ Performance
The traditionally-accepted measure o f project performance is the basic cost-quality-time triangle
(Ali A. and Rahmat I., 2009). However, there are differences between various types of projects
in determination o f performance since measurement is carried out against pre-determined
success factors. For building projects, there have been studies carried out and attempts made
towards development of evaluation models aimed at determining performance factors. However,
there is no universally accepted basis due to the differing complexity, inherent nature and unique
characteristics o f such projects (Hendrickson C., 2008).
According to Muir B„ (2006), eight factors affect performance of construction projects: nature o f
the work; work force considerations; safety; time constraints; environmental issues; legal issues;
governmental regulation; and socio-political pressures. Omar O., (2006) suggested another basic
model of using the broader context o f client satisfaction as a measure, expanding the traditionally
accepted project performance measurement model, which would normally centre on the basic
cost-quality-time triangle.
Examples drawn from actual construction projects’ performance further underline the complexity
issue. An article on projects’ performance based on energy and utilities projects in Alberta,
Canada (Amalraj J., Hernani C., Ladouceur K.. and Verma A., 2007) identifies key performance
issues as quality assurance and quality control; project controls and project accounting;
availability o f appropriate labour resources; stretch targets; weather conditions; and possible
opposition from local communities. Saqib M., Farooqui R. and Lodi S., (2008) identified six
critical success factors for construction projects in Pakistan, namely contractor experience; site
management; supervision and involvement of subcontracting; contractor’s cash flow;
effectiveness o f cost control system; and speed of information flow.
In another study of project performance in terms of the cost element for building construction
projects in Klang Valley, Malaysia, causes o f problems that essentially affect overall project
9
performance were identified as: inaccurate or poor estimation o f original cost; inflation of project
costs; improper planning; fluctuation in price of raw materials; poor project management; lack o f
experience; obsolete or unsuitable construction equipments and methods; unforeseen site
conditions; mistakes in design; insufficient funds; poor contract management; high cost o f
machineries; and construction cost underestimation (Ali A. and Kamaruzzaman S., 2010).
A study on India’s infrastructure projects (PMI-KPMG, 2010) identified drivers for success as
resource planning and utilisation; prior feasibility analysis to ensure soundness of investment;
ensuring compliance to regulatory agencies requirements; and identification and prioritisation of
risks in planning and monitoring, resource utilisation and skilled project management talent.
Another study undertaken by the Project Management Institute (PMI, 2010) on U.S. Federal
Government programmes to uncover thematic “success factors” found that excellence had a firm
grounding in the fundamentals: people, processes, and the resources to support both.
A World Bank policy research paper (Limodio N., 2011) based on 1912 infrastructure projects
financed by the World Bank between 1979 and 2008 attributed success of infrastructure projects
in low-income countries to three key factors: the quality of project implementers; the
performance o f the supervising agent; and proper design of the projects. Further, in a recent
paper that analyzed project-level variables, Denizer, Cevit, Kaufmann and Kraay A., (2011)
found out that micro variables such as project early-warning indicators, supervision and
evaluation lags are all significantly correlated with project outcomes. Khosravi S. and Afshari
H., (2011) also developed another performance measurement model for construction projects
with the model’s output being a project success index calculated based on five project success
factors: time performance; cost perfomiance; quality performance; health, safety and
environment o f the project; and client satisfaction.
A review of the Kenyan construction industry revealed similar factors as those identified in
models and studies above. The review identified twenty three factors influencing contractors’
performance in Kenya: staffing and competence; access to finance; statutory requirements;
absence of a unified legal and regulatory framework; poor or non-maintenance of structures;
inadequate supervision; improperly designed projects; weak judicial links; prevalence of stalled
10
projects; political interference; community interference with staffing; undue harassment by local
authorities; emergence of militia groups; absence of established and published work
specifications; non-implementation o f the National Planning and Building Authority Regulations
2010; absence o f a rationalized consultancy legislative framework; absence of a binding
framework uniting all consultants in the industry; restructuring of the consultancy registration
and regulatory regime; absence of a strong Contractors Association; prevalence of corruption and
graft in the industry; absence of strong links with relevant university departments; multiplicity of
uncoordinated legislative instruments in the industry; and lack of sound project and financial
management skills on the part of many contractors (Moramati-Proinvest, 2011 (a)).
These models and studies as outlined attempt to address the ‘complexity’ o f building projects
which emanate from issues such as the procurement selection, traditional separation of design
from construction, integration/ organization o f project members, communication channels,
uncertainties in design and construction, changing internal and external environment, project
complexity and characteristics and contractual and commercial matters (Ong H., 2007).
The factors cited in the models and studies seem to encapsulate a view postulated in a recent
review on construction project success. Al-Tmeemy S., Abdul-Rahman H. and Harun Z.,(2010)
postulated on success criteria for building projects as comprising of three aspects: project
management success, product success and market success. Project management success was
conceived as consisting of adherence to quality targets, adherence to schedule and adherence to
budget. Product success consists of customer satisfaction, functional requirements and technical
specifications. Market success was conceived as consisting of revenue and profit, market share,
reputation and competitive advantage. This model conceived project success in terms of factors
relating to both the immediate end product and longer term effects. Studies on all three aspects
require both objective and subjective measurements. Objective measures can be obtained using
mathematical formulae, whereas measurement of project psychosocial outcomes would be
subjective (Manana M., van Waveren C. and Chan K., 2011).
For the purpose o f this study, project performance which translates into the contractors’
performance was addressed in terms of only one aspect: project management success. It assessed
11
and measured identified factors influencing the contractors’ performance during the construction
phase. The choice of this paradigm was based on ensuring focus on objective measurement, for
reliability and validity.
From the above premise, and from the reviewed models and studies, it was possible to identify
general cross-cutting broad factors that are fundamental to contractors’ performance of building
projects namely, financial issues, human resources conditions, site characteristics, and design
quality aspects. Evident also was that the legal and regulatory environment is a consideration as
it would have a contingent effect on the relationship between these four major factors and the
performance. Another emergent aspect relates to the contractors’ “way o f doing things”- the
organisational culture of the construction entity, which would also have an effect. The following
sub-sections delve in more detail on these issues.
2.5 Financial Issues and Contractors’ Performance
Financial issues relate to cost and funding of a project which has an overall effect on
performance. According to Amalraj et. al., (2007) key aspects for consideration in this include
initial accuracy o f project estimates and subsequent project controls and project accounting in
relation to scope and schedule. Abdul-Rahman H., Wang C., Takim R. and Wong S., (2010)
provide a more comprehensive analysis of these issues, categorised as payment, cash flow,
financial resource and market issues based on previous relevant studies from diverse countries
such as Saudi Arabia, Hong Kong, Nigeria, Indonesia, United Kingdom, Ghana, Turkey and
USA, and with specific research on the Malaysian experience (Abdul-Rahman H., Berawi M.A.,
Berawi A.R., Mohamed O., Othman M. and Yahya I., 2006).
For government-funded building projects in Kenya, the main source of funding is the yearly
budgetary allocations. The annual budget is prepared under the Medium Term Expenditure
Framework (MTEF) which is a planning and budget formulation process that attempts to
improve decision making by linking policies, priorities and requirements within limited resource
constraints (GOK-MOF, 2011). The funds are then channeled through government ministries and
other service agencies. Costing for the works is done by Ministry of Public Works personnel who
also carry out periodic valuations and payments certification. Payments are made only for
12
certified works. The contractors are therefore required to have their own financial resources to
undertake works. This is usually established during the bids evaluation process with the basis
being their qualifications, equipment, experience, and audited company accounts, among other
criteria (Moramati- Proinvest, 2011(b)).
2.6 Human Resources Conditions and Contractors’ Performance
The building industry involves a diverse workforce with operations dependent on the knowledge
and skills of people planning and executing the work. According to Muir B., (2006) it is crucial
to have both talented management in place to guide and direct operations and also an adequate
number of skilled and unskilled workers to perform the work. However, it is difficult to find and
recruit sufficient numbers o f skilled and talented people. He cites the reason for this challenge as
being that construction is typically viewed as being one o f the least desirable industries in which
to work due its inherent nature: dangerous, dirty, hard work. Kaur P., (2006) reinforces this
perspective by stating that construction is considered a least lucrative profession due to the
fragmented structure of the sector, nature of the work and the terms o f labour recruitment.
ABTEC, (2006) submits the same line of thought with human resources issues in projects
identified as training, certification, apprenticeship, demographics and wage levels.
Amalraj et. al., (2007) present additional influences to the human resources element of a project
as inclusive o f the quality and quantity o f available workforce in a particular area, union or other
labour agreements, and a project site’s location. A related consideration to this is construction
equipment operation. The quality and quantity o f plant and equipment operators, their
availability, skills and productivity influence a building project’s performance. Ong H., (2007)
and Saqib et. al., (2008) offer a dimension on the human resources issue based specifically on
project management in relation to both design and construction. They highlight that project
success is dependent the project team’s competence: education, training and experience.
The issues above are collaborated by specific cases. For instance, based on the Malaysian
experience Wong P., (2007) drew attention to the need for sufficient manpower of proper skills
and experience to ensure successfully completion o f projects. He also called for perception
change of construction related careers, unjustly branded as “dirty, dangerous and demanding”
13
and reserved for only school "drop-outs". Veronika A., (2011) on the Indonesian experience
underlined the need to manage and develop human resources with regard to education levels,
demand fluctuations and personnel motivation. Aniekwu N. and Ozochi C., (2010) also present a
similar argument on the Nigerian scenario.
In Kenya, contractors undertaking government-funded building projects determine their own
human resources needs and employ the required workforce accordingly. The design and
supervision o f works is undertaken by Ministry of Public Works personnel deployed to the local
office or sourced from neighbouring areas (Source: County Works Office- Kirinyaga).
2.7 Site Characteristics and Contractors’ Performance
Site location in terms of geographical, political and functional context fixes the site in relation to
climate conditions, adjacent land uses, utilities and infrastructure availability, and the socio
cultural environment. The topography and slope determine drainage patterns and problems, on
site and off-site views, erosion and sedimentation, and suitability for different uses and activities.
The geology and soils have a bearing on the required engineering characteristics of structures to
be built in relation to stability, suitability for structural foundations, erosion susceptibility,
surface drainage, and soil fertility to support plant growth. Vegetation is also considered in terms
of climate modification and conservation value. The general climate of the location determines
the design form and also implementation scheduling. Another consideration is the availability o f
essential utilities such as water, sanitary sewer, storm sewer, electric and telephone mains, which
affect the costs o f development (McBride S., 2008).
Site characteristics for government-funded building projects in Kenya vary, with some of the
issues such as foundation soil conditions only evident on excavation. This subsequently has an
effect on the contractors’ performance. For instance, the study area of Kirinyaga County has
varied characteristics ranging from the cool, hilly, red soil regions on the lower slopes of Mt.
Kenya, to the hot, dry, flat, clay soil Mwea region (Source: County Works Office- Kirinyaga).
14
2.8 Design Quality Aspects and Contractors’ Performance
The documented design, materials specifications for functional and aesthetic reasons, actual site
conditions, in conjunction with pre-planned work schedules merge during implementation. This
may present another set of issues that are influence the contractors’ performance. Saqib et. al.,
(2008) categorised a number of these key issues. Among the issues they noted were the clear and
precise definition o f project scope and objectives, timely decision-making, risk attitude and
emphasis on low construction cost/ high quality of construction/ quick construction. Other
aspects include project design complexity, mistakes/delays in producing design documents,
adequacy of plans and specifications, project planning, scheduling, communication and speed of
information flow, and supervision. Alarcon L. and Mardones D.,(2009) presented the factors in
three categories: design quality related to design drawings and specifications, design standards
coupled with suitability for the existing technology, and constructability o f the designs. Another
major concern is the availability o f materials required for the built product. This encompasses
types and specification, delivery, special manufacturing, selection and procurement lead times
(Amalraj et. al., 2007).
The above design quality aspects o f completeness, complexity, changes, information flow,
supervision and specifications manifest in government-funded building projects in Kenya and
influence the contractors’ performance (Source: County Works Office- Kirinyaga).
2.9 Legal and Regulatory Environment and Contractors’ Performance
The legal and regulatory framework has an influence on building projects in form of exerting
control over the operations of the sector in a country. Laws and regulation should express the
policy o f the government; define the scope and functions of the building sector; regulate the
requirements o f practice for building projects and the working conditions; provide guidance and
standards that need to be followed; and regulate the distribution of responsibility of various
governing authorities of the sector (Moghram M., 2010). These are not standard but differ from
country to country and in levels o f development and enforcement. For instance, in USA the
building sector and construction in general is heavily regulated with laws and regulations based
on policies from diverse public agencies. These govern a wide range of aspects such as business
structure, licensing, contracts, bonding, insurance, safety building codes, labour, employee
15
relations, environment, taxes, import o f materials, foreign investment and immigration (O’Neal
S and Beming P., 2007).
The legal and regulatory environment governing all building projects in Kenya is largely
unharmonised. In terms of policy, currently all development efforts in Kenya are anchored in
Vision 2030, the blue print for Kenya’s long term national development which is implemented
through a series o f five year medium term rolling plans. The legal framework consists of a
multiplicity of statutes that are not harmonized (Moramati- Proinvest, 2011(b)). The institutional
framework also has multiple actors. However, the Ministry of Public Works is charged with
managing all government and public institutions building works, in liaison with other relevant
bodies such as the Ministry of Public Health (Kimani M. and Musungu T., 2010). The
contractors’ operations are also not harmonized despite the establishment of their umbrella body
of Kenya Federation of Master Builders in 2010 which does not have a legislative mandate
(Moramati- Proinvest, 2011 (a)). British Standards (BS) has been the safety guide for Kenya’s
building sector. The government intends to replace these with Eurocodes which are harmonized
Europe’s technical rules for the design o f buildings and structures, by 2013. Kenya will develop
is own national annexes to accommodate the local conditions (Njihia M., 2012).
2.10 Organisational Culture and Contractors’ Performance
According to Oyewabi L., Ibrahim A., Ganiyu B. and Okwori I., (2011) researches into building
projects’ performance have largely focused on the projects themselves rather than on the
organisations responsible for the projects. In their research paper, they conclusively
demonstrated that organisational culture is a powerful management instrument that can be
employed to enhance building projects’ performance. This view is shared by Ankrah N.,
Proverbs D. and Debrah Y., (2009) and expanded to include organisational learning by Opoku A.
and Fortune C., (2011).
Contractors carrying out government-funded building projects in Kenya comprise of independent
firms, each with its own management structure and organisational culture.
16
2.11 Conceptual Framework
The conceptual framework for the study as illustrated in Fig.2 indicates the relationship between
the variables. The defining premise for the framework as derived from the literature review is
that manipulation o f the independent (predictor) variables consisting of financial issue, human
resources conditions, site characteristics and design quality aspects influences the contactors’
perfonnance o f government-funded building projects. The framework further illustrates the
moderating and intervening variables identified as legal and regulatory environment and
organizational culture, respectively. It also includes indicators of the variables that would be
used to measure the levels of influence.
Independent variables Moderating variable
Financial Issues:
• Funding system• Financial management
system• Progress payments
process
Human Resources
Conditions:
• Availability o f appropriate human resources
• Productivity levels of the workforce
Site Characteristics:• Unique site features
and conditions
Design Quality Aspects:
• Design quality issues• Materials
specifications
Intervening variable
figure 1: Conceptual Framework
17
2.12 Summary
The literature review revealed key factors influencing performance o f contractors of
government-funded building projects. These were identified as financial issues, human resources
conditions, site characteristics and design quality aspects. The legal and regulatory environment
was identified as a moderating variable in the relationship between the independent and
dependent variables. Organisational culture was similarly identified as an intervening variable in
the same relationship.
The literature review thus formed the theoretical framework and subsequent development of the
conceptual framework, providing concrete grounding for carrying out the research study’s field
work.
18
CHAPTER THREE
RESEARCH DESIGN AND METHODOLOGY
3.1 Introduction
This chapter presents and justifies the research approach and methodology selection used in the
study. It consists of the research design, sampling, data collection and data analysis procedures
that were be used to achieve the set research objectives.
3.2 Research Design
With reference to the objectives and research questions o f the proposed study, the research
design o f choice was descriptive survey. This utilises elements of both quantitative and
qualitative research methodologies thereby seeking to provide a complete and accurate picture o f
the situation being studied (Given L., 2007).
The choice was based on the challenge posed by the construction engineering and management
sector, due to the interdisciplinary project-based nature of the work, industry fragmentation, one-
of-a-kind end products, site-based production, and other factors (Panas A. and Pantouvakis J.,
2010). To resolve this, a reasonable basis for choosing an appropriate methodology is an
appreciation o f the human resource clement in building projects. Since people play key roles in
nearly all aspects o f construction, an effective construction research calls for proper application
of social science research methods. This can be achieved by combining quantitative and
qualitative approaches in research design and data collection (Abowitz D. and Toole T., 2010).
3.3 Target Population
The target population was the 38 building contractors currently undertaking government-funded
building projects managed by the Ministry of Public Works in Kirinyaga County, Kenya. Their
projects consist o f public buildings such as educational, health services, offices, recreational and
market facilities.
19
The rationale for this was that the target population of contractors could be considered to be a
homogenous group since the basic criteria for undertaking the government-funded building
projects is simply registration with MOPW. Minimum qualifications for bidding for projects are
stipulated for each specific project. A point of note is that in relation to the focus projects, the
Ministry o f Public Works only manages building projects funded through mainstream
government ministries and departments in the county, and those funded through the Constituency
Development Fund (CDF) in Mwea and Gichugu constituencies which are two of the four
constituencies making up Kirinyaga County (Source: County Works Office- Kirinyaga).
3.4 Sample Size and Sampling Procedure
The study was a census due to the small population size o f 38 building contractors. Thus, no
sampling was carried out. The respondents were managing directors o f these construction firms.
This facilitated gathering o f the necessary data from persons in authority who have full
understanding of, and involvement in, the building projects’ process.
3.5 Research Instruments
The data collection instrument used in the study was a self-administered questionnaire
comprising o f both closed- and open- ended questions. This has advantages o f collecting the
required information at a low cost per respondent, the respondents may give more honest
answers in the absence of the researcher, the answers are more standardized for closed-ended
questions, and they can fill the questionnaire at their convenience. Closed- ended questions
provide objective quantitative data whereas the open-ended questions, provide general subjective
insight into the study subject (Cargan L., 2007).
3.6 Pilot Study
The questionnaire was piloted to test if it yielded the required information. The pilot study was
carried out in Nyeri County which neighbours Kirinyaga County, Kenya. Seven respondents with
similar characteristics as the target population were chosen on convenience. They were asked to
respond on any ambiguities and also to give comments about the length, structure and wording of
the questionnaire. This facilitated altering and refining the questions accordingly to meet
research objectives so as to achieve the ultimate aim of obtaining reliable and valid survey data
( Fink A., 2006).
20
3.61 Reliability
The pilot study was a critical exercise in testing for reliability. Reliability was also tested through
lest-retest technique, whereby the same questionnaire was administered to the same 13
respondents at two separate points in time. Calculating the correlation between the two scores
yielded the reliability coefficient. ‘Internal consistency’ or homogeneity was measured using a
statistical package to derive Cronbach’s alpha, which is a coefficient that measures the
consistency of results across items. With an acceptable reliability o f 0.7 and above
(Thanasegaran G., 2009), the test result of 0.783 indicated that the tool was reliable.
3.62 Validity
The pilot study was also used to ascertain validity. Validity was ensured on the following
criteria. The instrument at face value had to seem to be a reasonable way to gain the information
required and was well designed. This also established criterion-related validity. It satisfied the
content criterion through inclusion of adequately representative indicators of the concepts
measured. This was checked by evaluating inter-item correlations. Peer evaluation of inferences
based on the instrument was also incorporated to further enhance reliability and validity.
3.7 Data Collection Procedure
Data to be used in the study was from both primary and secondary sources. The first stage
consisted o f examination of previous research reports and other relevant literature. This
facilitated identification of major concepts, their correlation and the knowledge gaps related to
the field of interest. The review o f this secondary data provided knowledge on how these
concepts may be operationalised thereby assisting in developing an appropriate research design
and methodology. The second stage comprised of collection of primary data. Prior to data
collection from the sample population, a pilot survey was conducted to verify the quality and
effectiveness o f the data collection instrument. On refinement of the instrument, the actual field
study was carried out. This was closely monitored, evaluated and appropriate adjustments made
to constrain the exercise within the projected work plan and resources.
The questionnaires were distributed personally by the researcher and research assistants to
respondents. The basis for this was that the alternative distribution method of mailing is
unreliable and could have taken too much time. The distribution points were MOPW county
21
offices in Kerugoya, and CDF offices for Mwea and Gichugu located in Ngurubani and
Kianyaga towns, respectively. This ensured access to respondents as project management
procedures require that the contractors visit these offices frequently. They were returned to the
same points or collected by the research personnel from locations convenient to the respondents.
The purpose of this was to enhance the response rate, and in consideration o f the fact that the
geographical area o f study was not extensive and the study units were few.
3.8 Data Analysis Procedure
The data analysis method involved the use of descriptive and inferential statistical analysis
derived through . The results are presented in form of frequency tables, proportions and means
analysis. Inferential statistics such as correlation analysis were done to determine the degree of
association between the variables, resulting in Pearson’s correlation coefficient. Validity o f the
measurement models was tested using SPSS. The results o f ANOVA, of SPSS helped answer the
question as to how the dependent variable is influenced by the independent variables.
3.9 Ethical Considerations
Before commencing the field study, permission was sought from relevant authorities. In
recruitment of respondents, they were fully informed on the study’s activities and purpose so that
their consent was freely granted and without prejudice. The structure of the data collection
instrument which yielded anonymous information was aimed at assuring respondents of
confidentiality and privacy. With respect to data collection, analysis and interpretation, all
references were cited and the source credited and the study was devoid of plagiarism, fabrication
or falsification. Honesty was observed in all interpersonal communication and in the analysis of
literature.
3.10 Operationalisation of Variables
Table 3.1 is a summary of the systematic process of operationalisation of the independent and
dependent variables that was undertaken: from the basis of the set objectives, through to
indicators, measures and measurement. It further indicates the data collection method,
measurement scale and the level of analysis.
22
Table 3.1: Operational table
Item Objectives
1 To establish the influence of financial issues on contractors’ performance of government-funded building projects in Kenya
Independent Indicatorsvariables
Financial issues Fundingsystem
Measures Measurement Data
-Adequacy of funds
-Access to finance
Ratio of contract sum (work awarded) to tender sum (work bid for) Amount of time taken to process a
collectionmethodQuestionnaire
Measurementscale
Interval/Ratio
Analysis
Correlation
loanFinancialmanagementsystem
-Cost control andaccounting
Level of effectiveness of cost control system
-Capital base Level of capital base in relation to works undertaken
Progresspaymentsprocess
-Timeliness of valuations andcertification
Amount of time taken to value and certify works
-Accuracy of valuations
Level of discrepancy between technical valuation for payment and the contractor’s claim
-Timeliness of honouring certificates
Amount of time taken to honour certificates
23
Item Objectives Independentvariables
2 To determine the influence of human resources conditions on contractors’ performance of government-funded building projects in Kenya
Humanresourcesconditions
Indicators Measures M easurem ent Datacollectionmethod
Measurementscale
\nal> \is
Availabilityofappropriatehumanresources
-Quantity of available appropriate workforce
Number of available personnel as required at a specific time
Questionnaire
Interval/Ratio
Corrclation
-Level of competence of available personnel
Education, training and experience levels of available personnel as required at a specific time
-Demandfluctuations
Differences in availability of personnel required over different periods of time
Productivity levels of the workforce
-Terms of employment
Production per time period
-Motivationstrategies
Number of ways employed to motivate personnel towards higher productivity
-Jobassignment
Level ofassignment of jobs based on specialization
24
Item O b jec tiv e s Independentvariables
Indicators M e a s u re s M e a s u re m e n t D a tacollectionmethod
M e a s u re me nt scale
A n a ly s is
3 To determine the influence o f site characteristics on contractors’ performance of government-funded building projects in Kenya
Sitecharacteristics
Unique site features and conditions
-AccessibilityTopographyand slopeeffects-Availabilityof utilities(such aswater,electricity,sewer mains)-Actual soilconditions onexcavation-Existingvegetation-Climaticconditions
Unit cost of production ( cost per nr of floor area) andTime taken to execute the works
Questionn a ire
Interval/Ratio
Correlation
4 To establish the influence of design quality aspects on contractors’ performance of government-funded building projects in Kenya
Design quality aspects
Design quality issues
-Completeness
Level of design andspecificationscompleteness
Questionnaire
Interval/Ratio
Correlation
-Complexityofspecifications
Level ofspecificationscomplexity
-Changes in design and specifications
Net cost of modifications
-Speed ofinformationflow
Time taken to communicate necessary information
25
Item Objectives I n d e p e n d e n tvariables
In d ic a to r s Measures M easurement Datacoliectionmethod
Measurementscale
Analysis
Materialsspecifications
-Availability of specified materials
Unit cost of production ( cost per m: of floor area)
-Procurement lead times
Amount of time taken to procure the specified materials
-Supervisionlevel
Level of daily works supervision Number of periodic project team site inspections and meetings
Item Objectives Dependentvariable
Indicators Measures Measurement Datacoliectionmethod
Measurementscale
Analysis
1 To establish the influence of- financial issues,- human resources issues- site characteristics and- design implementation issues on contractors’ performance of government- funded building projects in Kenya
Contractors’performance
Budget(Cost)
-Contractsum
Percentage of contract sum
Questionnaire
Interval/Ratio
Correlation
Contractperiod(Time)
-Contractduration
Percentage of contact period
Adherence to specifications (Quality)
-Specifications details
Level of adherence to specifications
26
3.11 Summary
This chapter on the research design and methodology is centered on the overall objectives o f the
study. It facilitated collection o f valid and reliable data that was objectively interpretable, thereby
yielding practical conclusions and recommendations, which must be the fundamental outcome
for any research.
27
CHAPTER FOUR
DATA ANALYSIS, PRESENTATION AND INTERPRETATION
4.1 Introduction
This chapter analyses the data that was collected and offers the interpretation o f the results from
the findings collected from the sampled respondents. The purpose of the study was to investigate
the factors influencing the performance o f contractors o f government-funded building projects in
Kirinyaga County, Kenya.
4.2 Response Rate
A total of 38 questionnaires were distributed to the selected respondents in Kirinyaga County. A
total of 36 questionnaires were duly filled and collected; a resultant 94.74% response rate. This
was an acceptable rate and could be attributed to the fact that the questionnaires were physically
given to the respondents and collected from specific collection points at an agreed date. Table
4.1 shows the response rate;
Table 4.1: Response Rate
Category Targeted Sample Response Rate % Response Rate
Size
Building contractors 38 36 94.74
Total 38 36 94.74
N=36
4.3 General Information
This section provides results and discussions o f characteristics of the building contractors in
Kirinyaga County.
4.3.1 Age Bracket
Hie study sought to establish the age bracket of the managing directors of building construction
firms and the responses are as provided in Table 4.2.
28
Table 4.2: Age Bracket
Frequency(N) Percent
31-40 11 30.6
41-50 15 41.7
Above 50 10 27.7
Total 36 100.0
The study found that majority of the respondents, 41.7% were aged 41-50 years, 30.6% of the
respondents were aged 31-40 years, and 27.7% o f the respondents were aged above 50 years.
This analysis indicates that all respondents were above 31 years of age with a majority within the
31-50 years age range. Persons in this age group tend to be generally well-established in their
careers.
4.3.2 Gender
Table 4.3 indicates the gender composition of the respondents.
Table 4.3: Gender
Frequency(N) Percent
Female 1 2.8
Male 35 97.2
Total 36 100.0
The study found that, majority of the respondents, 97.2% were male while 2.8% were female.
This implies a lack o f gender balance among the building contractors within Kirinyaga County.
4.3.3 Education Level
The research further attempted to establish the level of education o f the respondents and the
responses are as shown in Table 4.4.
Table 4.4: Education Level
Frequency(N) Percent
Certificate 10 27.8
Diploma 13 36.1
Degree 12 33.3
Masters and above 1 2.8
Total 36 100.0
29
Table 4.4 shows that o f the respondents, 36.1% were diploma holders and 33.3% were degree
holders. 27.8% of the respondents had certificate qualification. Only 1 or 2.8% of the respondent
had masters’ qualification. This analysis suggests that the majority of respondents hold high
qualifications o f diploma and above and could be having reasonable management capabilities.
4.3.4 Company’s Registration Category
The research emphasized on the categories of the building construction company registration and
the responses are provided in Table 4.5.
Table 4.5: Company’s Registration Category
Frequency(N) Percent
C o r D 6 \6H
E or F 23 63.9
G o rH 7 19.4
Total 36 100.0
The finding revealed that the majority of companies at 63.9% were registered in category E or F,
16.7% were registered in category C or D, and 19.4% in category G or H. This implies that the
majority are mid-level firms with the capability to undertake reasonably big works.
4.3.5 Years of Operation
The study sought to establish the period that each company had been in operation and the
findings are provided in Table 4.6.
Table 4.6: Years of Operation
Frequency(N) Percent
Less than 5 4 11.1
5 - 10 22 61.1
11 - 15 9 25.0
Above 20 1 2.8
Total 36 100.0
The finding revealed that 61.1% of the respondents have been in operations for 5-10 years and
25% o f the sample had been in operations for 11-15 years. About 11.1% o f the respondents had
been in operation for less the 5 years. Only one company has been in operations for more than 20
years. This reveals that there could be factors that have resulted in more building firms being
established and starting operations in the preceding 10 years.
30
4.4 Project Performance
This section provides results and discussions o f the projects’ performance equated to the
contractors’ performance, according to the building contractors in Kirinyaga County.
4.4.1 Descriptive Statistics
The research attempted to establish the level of project performance and general opinion is
provided in Table 4.7.
Table 4.7: Descriptive Statistics
N Minimum Maximum Mean Std. Deviation
project performance 36 1.33 4.33 2.6204 .54716
Table 4.7 indicates that, the average score o f project performance was 2.62. In the likert scale
measuring interval data, any score below 3 represents agree. The score thus implies that based on
on project performance statements, the majority of respondents agree that projects undertaken
are successful. Others statistics are also provided in the same table.
4.4.2 Project Performance Issues
The study sought to establish the views o f the respondents on project performance and the results
are given Table 4.8.
Table 4.8: Project Performance Issues
Stro
ngly
agr
ee
Agr
ee
Neu
tral
Dis
agre
eSt
rong
ly
Dis
agre
e
Tot
al
% % % % % %
Projects are done within the budget 2.8 27.8 61.1 5.6 2.8 100
Projects are completed within the 5.6 22.2 47.2 25.0i 0 100
contract period
Projects meet set standards 8.3 72.2 13.9 5.6 0 100
31
The study found that of the respondents, 30.6% agree, 61.1% neither agree nor disagree, while
8.3% disagree that projects are done within the budget. In response to the statement that projects
are completed within the contract period, 27.8% agree, 47.2% neither agree nor disagree, and
25.0% disagree. Finally, 80.5% of the respondents agree, 13.9% neither agree nor disagree, while
5.6% disagree that projects meet standards.
The above revealed the average response to all the project performance statements as follows:
46.3% agree, 40.7% neither agree nor disagree, and 13.0% disagree. This suggests that the
majority o f respondents at 46.3% agree that projects undertaken are successful. However, 53.7%
of the respondents are either neutral or disagree. This could be attributed to individual
experiences since no information on other projects’ performance was provided to the
respondents.
4.5 Financial Issues’ intluence on Contractors’ Performance
This section provides results and discussions of financial issues’ influence on the performance of
contractors o f government-funded building projects according to the building contractors in
Kirinyaga County.
4.5.1 Descriptive Statistics
The research attempted to establish the level at which financial issues influence contractors
performance and the general opinion is provided in Table 4.9.
Table 4.9: Descriptive Statistics
N Minimum Maximum Mean Std. Deviation
Financial issues 36 1.57 3.71 2.8611 .47868
Table 4.9 indicates that, the score average of financial issues was 2.86. In the likert scale, the
score represents agree. It thus implies that the majority of respondents agree that financial issues
influence the contractors’ performance.
4.5.2 Specific Financial Issues’ influence
This research attempted to establish the views of the respondents on the stated financial issues
and the results are given in Appendix 5. For each o f the statements, there was a view held by the
32
majority of respondents. On the contract sum being usually equivalent to the tender sum, 47.2%
agree. In response to the statement that loans are usually quickly processed by banks and other
financial institution, 44.4% agree. On whether respondents update plans and records of income
and expenditure on a weekly basis the majority was 52.7% disagree. In response to contractors
only bidding for projects for which they have the capacity to undertake 38.9% disagree. About
valuation and certification o f work being completed within the stipulated two weeks period,
55.6% of the respondents agree. In addition, the response was 69.4% agree on valuations for
payment being a source of disputes. Finally, responses to payment certificates being honoured
within the stipulated two weeks period, 44.4% disagree.
From the indicators of financial issues, the above reveals average responses related to the
funding system o f 45.8% agree, those related to financial management system of 45.8% disagree
and in relation to progress payments process, 44.4% disagree. This suggests that financial issues
have a major influence on the contractors’ performance. It also reveals that the major positive
influence on the contractors’ performance is issues related to the funding system, while negative
influences are issues related to their financial management system and the progress payments
process.
4.5.3 Financial Issues and Successful Completion of Projects
The study attempted to find out whether financial issues had any influence on successful
completion of projects as shown in the Table 4.10.
Table 4.10: Financial issues and successful completion of projects
Frequency(N) Percent
No 1 2.8
Yes 35 97.2
Total 36 100.0
The analysis found that majority o f the respondents, 97.2% said that financial issues had an
influence on successful completion o f projects.
The respondents’ views were further sought through open-ended questions to acquire deeper
insight into financial issues’ influence on successful completion of projects. The responses are
33
given in Table 4.11.Notably, 44.7% o f the respondents said that delays in payment leads to
delays in the projects and contractors sometimes bid for projects that they cannot complete.
Additionally, 36.3% said that many contractors fail to complete their projects in time due to
financial problems. This reflects the suggestions in 4.5.2 above.
Table 4.11: Ways in which financial issues influence successful completion of projects
No. Ways Frequency %
1 Contractor will be able to plan for two phase simultaneously
since he/she has capability o f purchasing materials required in
advance, i.e. while on site, one with power of purchase can be
fabricating roof structure
1 2.8
2 Delay in payment delays the project, contractors sometimes bid
for projects that they cannot complete
16 44.7
3 Enables contractor to start the project immediately and work
continuously
1 2.8
4 Facilitate work to move faster 2 5.6
5 Inadequate funds delayed and late payments usually lead to
delayed completion or total abandonment of projects
2 5.6
6 It ensures all departments o f a project are going together, e.g
delivery o f materials, payment of labour, hiring of skilled
personnel, etc
1 2.8
7 Less money less work and poor one 1 2.8
8 Many contractors fail to complete their projects in time due to
financial problems
13 36.3
9 The contractors are able to plan and work within the time given 1 2.8
10 The contractors are able to purchase and honour suppliers
invoices
1 2.8
11 Finances fully disabused gives a contractor and workers
confidence and encourage them to complete their work
1 2.8
34
4.6 Human Resources Conditions’ influence on Contractors’ Performance
This section provides results and discussions on human resources conditions’ influence on the
performance of contractors o f government-funded building projects according to the building
contractors in Kirinyaga County.
4.6.1 Descriptive Statistics
The study attempted to establish the level at which human resources conditions influence
performance o f contractors and the general opinion is provided in Table 4.12.
Table 4.12: Descriptive Statistics
N Minimum Maximum Mean Std. Deviation
Human resources
conditions
36 1.17 2.50 1.8843 .38999
Table 4.12 indicates that the average score of human resources conditions was 1.88. In the likert
scale, the score represents agree. It thus implies that the majority of respondents agree that
human resources conditions influence the contractors’ performance.
4.6.2 Specific Human Resources Conditions’ influence
The study attempted to establish the views of the respondents on the listed human resources
conditions and the results are given in Appendix 5. For each of the statements, there was a view
held by the majority of respondents. On that personnel (skilled, semi-skilled, unskilled and
management) is available when required, 69.4% agree. In response to the statement that
recruitment o f personnel on the basis of education, training and experience ensures quality o f
work, 100.0% agree. On whether sometimes there is excess or shortage o f labour available in a
particular area, 80.6% agree. In response to terms of employment (such as daily wages, piece
work) affect the work output of personnel, 94.4% agree. On the statement that ways used to
motivate personnel (such as bonuses, time-off, training opportunities) affect productivity levels,
91.7% of the respondents agree. Finally, in response to the statement that assignments are
allocated to personnel based on their specialized skills, 66.7% agree.
From the indicators o f human resources conditions, the above reveals average responses related
to the availability of appropriate human resources of 83.3% agree, and in relation to productivitySMrt
•<
■J p-, A f t r
levels of the workforce, 84.3% agree. This suggests that human resources conditions have a
maior influence on the contractors’ performance.
4.6.3 Human Resources Conditions and Successful Completion of Projects
The study attempted to find out whether human resources conditions had any influence on
successful completion o f projects as shown in Table 4.13.
Table 4.13: Human resources conditions and successful completion of projects
Frequency(N) Percent
No 2 5.6
Yes 34 94.4
Total 36 100.0
The analysis found that, majority of the respondents, 94.4% said that human resource conditions
had an influence on successful completion of projects.
The respondents’ views were further sought through open-ended questions to acquire deeper
insight into human resources conditions’ influence on successful completion of projects. The
responses are given in Table 4.14. Notably, 22.4% of the respondents said that better personnel
results in quick and timely completion of projects and 19.6% said that labour used should have
the right skills. Additionally, 14.0% said that availability o f personnel is important for good work
and 14.0% said it affects the quality o f work, time of completion and also profit to the company.
This reflects the suggestion in 4.6.2 above.
Table 4.14: Ways in which human resources conditions influence successful completion of
projects
No. Ways Frequency %
1 As a measure for proper collection and guidance towards work
and other status of work
1 2.8
2 As humans, when well guided, well managed, well paid, the
absolute is a satisfactory performance
2 5.6
3 At times you lack local skilled labour and you have to import 3 8.4
36
from other areas
4 Availability of personnel is important for good work 5 14.0
5 Better personnel leads to quick and timely completion
projects
of 8 22.4
6 Depends on who does the work; without their input,
foundation and nature o f the work will fail
the 1 2.8
7 It affects the quality o f work, time of completion and also profit
to the company
5 14.0
8 Labour used should have the right skills 7 19.6
9 Source o f job creation and human input is the pillar to
development o f a society
any 1 2.8
4.7 Site Characteristics’ influence on Contractors’ Performance
This section provides results and discussions of site characteristics’ influence on the performance
of contractors o f government-funded building projects according to the building contractors in
Kirinyaga County.
4.7.1 Descriptive Statistics
The research attempted to establish the level at which site characteristics influence performance
of contractors and the descriptive statistics are provided in Table 4.15.
Table 4.15: Descriptive Statistics
N Minimum Maximum Mean Std. Deviation
site characteristics 36 1.00 2.60 1.6722 .40328
Table 4.15 indicates that the average score of site characteristics was 1.67. In the likert scale, the
score represents agree. It thus implies that the majority of respondents agree that site
characteristics influence the contractors’ performance.
37
4.7.2 Specific Site Characteristics’ influence
The study sought to establish the views of the respondents on the listed site characteristics and
the results are given in Appendix 5. For each o f the statements, there was a view held by the
majority of respondents. On that means o f accessing a site affect the cost and duration of a
project, 94.4% agree. In response to the statement that the topography and slope affect the cost
and duration o f a project, 100.0% agree. On that availability o f utilities (such as water,
electricity, sewer) on or near site affect the cost and duration of a project, 100,0% agree. In
response to the statement that soil condition and existing vegetation affect the cost and duration
of a project, 100,0% agree. Finally, in response to the statement that climatic conditions in an
area affect the cost and duration of a project, 94.4% agree.
From the indicator o f site characteristics, namely unique site features, the above reveals the
average of responses of 97.8% agree. This suggests that site characteristics have a major
influence on the contractors’ performance.
4.7.3 Site Characteristics and Successful Completion of Projects
The study sought to find out whether site characteristics had any influence on successful
completion o f projects as shown in the Table 4.16.
Table 4.16: Site characteristics and successful completion of projects
Frequency(N) Percent
No 2 5.6
Yes 34 94.4
Total 36 100.0
The study found that, majority of the respondents, 94.4% said that site characteristics had
influence on successful completion of projects.
fhe respondents’ views were further sought through open-ended questions to acquire deeper
insight into site characteristics’ influence on successful completion o f projects. The responses are
given in table 4.17. Notably, 28.0% of the respondents said that actual site conditions should be
considered in project planning. Additionally, 28.0% said that all the factors listed affect the cost
and duration o f a project because if any of the factors is not favourable, more materials and
38
intensive labour is required, hence raising costs and duration. This reflects the suggestion in 4.7.2
above.
Table 4.17: Ways in which site characteristics influence successful completion of projects
No. Ways Frequency %
1 A good site (easily accessible, with utilities and stable soil)
makes the construction works economical
2 5.6
2 Accessibility does determine the type of transportation used and
hence the cost
3 8.4
3 Actual site conditions should be considered in project planning 10 28.0
4 All above factors affect the cost and duration o f a project
because if any o f the factors is not favourable more materials
and intensive labour is required hence raising costs and duration
10 28.0
5 Bad sites will definitely affect 2 5.6
6 Weather conditions affect project implementation activities e.g.
concreting, excavation etc
3 8.4
7 Some sites are very steep, others have bad soils 1 2.8
8 For good sites, the project is easily completed and money spent
is less
1 2.8
! 9 Tough sites are hard to build on and costly 1 2.8
1 io When there is electricity, good access road, may lead to 24hrs
working for project to move faster
2 5.6
11 Distance to dispose off cleared and excavated also leads to
delayed completion if its far off
1 2.8
12 Type of site determines the amount of materials to cast away
and backfill
2 5.6
13 Soil condition and type also affect and determine the depth of
excavation
1 2.8
14 They determine time frame, accessibility cost and viability 1 2.8
39
4.8 Design Quality Aspects’ influence on Contractors’ Performance
This section provides results and discussions o f design quality aspects’ influence on the
performance o f contractors of government-funded building projects according to the building
contractors in Kirinyaga County.
4.8.1 Descriptive Statistics
The research attempted to establish the level at which design quality aspects influence
performance of contractors and the descriptive statistics are provided in Table 4.18.
Table 4.18: Descriptive Statistics
N Minimum Maximum Mean Std. Deviation
design quality aspects 36 1.25 2.75 2.1181 .32036
Table 4.18 indicates that, the average score o f design quality aspects was 2.11. In the likert scale,
the score represents agree. It thus implies that the majority o f respondents agree that design
quality aspects influence the contractors’ perfonnance.
4.8.2 Specific Design Quality Aspects’ influence
The study sought to establish the views of the respondents on the listed design quality aspects
and the results are given in Appendix 5. For each o f the statements, there was a view held by the
majority o f respondents. In response to the statement that project documentation (drawings and
bills of quantities) is usually accurate and complete, 27.8% agree. However, 50% of the
respondents had a neutral view. On the statement that projects undertaken can usually be done to
completion using available skilled personnel and machinery, 91.7% agree. In response to the
statement that design changes affect the work programme and costs o f a project, 100.0% agree.
On that cost o f materials is dependent on their availability, 91.7% agree. In response to the
statement that the types of materials specified detennine the amount of time taken for their
procurement and delivery, 94.4% agree. Response to the statement that relevant information is
usually communicated within a reasonable period o f time was 47.2% agree. On that a qualified
overall supervisor must be on site at all times, 97.2% agree. Finally, in response to the statement
that project team site inspections are held bi-weekly and site meetings are held monthly as
stipulated.27.8% agree. However, 47.2% were neutral.
40
From the indicators of design quality aspects, the above reveals average responses related to
design quality issues of 66.7% agree, those related to materials specifications 93.1% agree and in
relation to supervision level, 62.5% agree. This suggests that design quality aspects have a major
influence on the contractors’ performance.
4.8.3 Design Quality Aspects and Successful Completion of Projects
The study sought to find out whether design quality aspects had any influence on successful
completion of projects as shown in the Table 4.19.
Table 4.19: Design quality aspects and successful completion of projects
Frequency(N) Percent
No 2 5.6
Yes 34 94.4
Total 36 100.0
The study found that, majority of the respondents, 94.4% said that design quality aspects had
influence on successful completion o f projects.
The respondents’ views were further sought through open-ended questions to acquire deeper
insight into design quality aspects’ influence on successful completion of projects. The responses
are given in Table 4.20. Notably, 22.4% of the respondents said that bad designs destroy projects
while good quality design makes good projects. In addition 16.8% said that a change of design
causes demolitions if not timely done which effectively increases the cost o f the project and at
times loses to the contractor due to lack of payment. Further, 11.2% said that good design quality
equals well produced and finished projects. This reflects the suggestion in 4.8.2 above.
Table 4.20: Ways in which design quality issues influence successful completion of projects
No. Ways Frequency %
1 Bad designs destroy projects, good quality design makes good
projects
8 22.4
2 Because most of the design are not done by qualified personnel
or are borrowed from other projects
1 2.8
41
3 BQs should be well done and changes avoided 3 8.4
4 A change o f design causes demolitions if not timely done. This
effectively increases the cost of the project and at times loses for
the contractor due to lack o f payment
6 16.8
5 Design and how it is built on site affect completion o f projects 1 2.8
6 Documentation should be complete and supervision constant 1 2.8
7 Good design quality equals well produced and finished projectsc
4 11.2
8 No changes are effected 1 2.8
9 Sophisticated designs cost more 1 2.8
10 Supervision is important 2 5.6
11 The more accurate the design, the less time it takes to complete
the projects as less clarification and consultation between
projects managers and contractor are required
1 2.8
12 They help in proper work programme 1 2.8
13 When the designs are constant, construction moves faster unlike
when they are changed regularly, since any change commands
whether you demolish, hence affect duration of completion
1 2.8
42
4.9 Relationship between Factors and Contractors’ Performance
This section provides results and discussions of the correlation analysis o f the study as shown in
Table 4.21. Correlation measures the degree/strength o f association between two variables.
4.9.1 Correlation between Financial Issues and Contractors’ Performance
There exists a correlation between financial issues and contractors’ perfonnance although the
Pearson correlation = 0.318 is marginally significant. Employing 0.05 significance level, this was
supported by a significance value o f 0.059 > 0.05.
4.9.2 Correlation between Human Resources Conditions and Contractors’ Performance
A fairly strong correlation exists between human resources conditions and contractors’
perfonnance. Employing 0.05 significance levels, the result indicate that there was relationship
between contractors’ perfonnance and human resources conditions. The results are statistically
significant with a significance value of 0.034 < 0.05. The Pearson correlation value is 0.354. This
implies that use of adequate, motivated, well trained and skilled human resources influences
contractors’ perfonnance, hence successful completion of projects.
4.9.3 Correlation between Site Characteristics and Contractors’ Performance
There exists a correlation between site characteristics and contractors’ performance although the
Pearson correlation = 0.214 is not statistically significant at all. Employing 0.05 significance
levels, this was supported by a significance value of 0.210 > 0.05.
4.9.4 Correlation between Design Quality Aspects and Contractors’ Performance
A fairly strong correlation exists between design quality aspects and contractors’ performance
with a Pearson correlation value o f 0.535. Employing 0.01 significance levels, the results are
highly statistically significant with a significance value of 0 .0010.01 . This implies that the use
of quality design and a high level of supervision influence contractors’ performance.
4-9.5 Correlation between Factors
Funher to the above, there exists fair correlation between human resources conditions and
financial issues and design quality aspects, employing a 5% significance level. The association
between them is statistically significant with a significance value of 0.022 < 0.05 and 0.021 <
9.05 respectively.
43
Table 4.21: Correlation analysis
Human
Contractors’ Financial resources Site Design quality
performance issues conditions characteristics aspects
Contractors’ Pearson 1
performance Correlation
Sig. (2-tailed)
N 36
Financial Pearson .318 1
issues Correlation
Sig. (2-tailed) .059
N 36 36
Human Pearson .354’ .382’ 1
resources Correlation
conditions Sig. (2-tailed) .034 .022
N 36 36 36
Site Pearson .214 1 OO 00 .121 1
characteristics Correlation
Sig. (2-tailed) .210 .273 .481
N 36 36 36 36
Design quality Pearson .535” .286 .384* .258 1
aspects Correlation
Sig. (2-tailed) .001 .090 .021 .128
N 36 36 36 36 36
*• Correlation is significant at the 0.05 level (2-tailed).
Correlation is significant at the 0.01 level (2-tailed).
44
4.10 Summary
From the correlation analysis, only two independent variables namely, human resources
conditions and design quality aspects were statistically significant on contractors’ performance.
Financial issues had notable correlation but marginal significance at 0.05 significance level,
while site characteristics had notable correlation but not significant at 0.05 significance level,
hence insignificant.
The correlation analysis also revealed the existence o f fair correlation between human resources
conditions and, financial issues and design quality aspects.
45
CHAPTER FIVE
SUMMARY OF FINDINGS, DISCUSSIONS, CONCLUSIONS AND
RECOMMENDATIONS
5.1 Introduction
This chapter gives the summary of major Findings, discussions, conclusions and
recommendations of the study.
5.2 Summary of Major Findings
The study was aimed at investigating the factors influencing the performance of contractors
of government-funded building projects in Kirinyaga County, Kenya. In general, the study
revealed that based on the responses, the factors studied had influence on the contractors’
performance and consequently, on the successful completion of projects. The study also
revealed a 46.3% success rate of the projects.
The findings also presented within the factors, key critical aspects that affect performance,
from the respondents’ perspective. For financial issues, these were identified as payment
delays and the contractors’ financial capacity. On human resources conditions, these
consisted of the quality and availability of the necessary personnel. In relation to site
characteristics, the key critical aspect was noted as each unique site’s features and the
importance of factoring these in planning of the projects. Finally, in relation to design quality
aspects, critical aspects identified were quality of the design which relates to completeness
and complexity of, and modifications to the design, and efficiency of information flow on
these aspects.
The findings also revealed strong correlation between the contractors’ performance of
government-funded building projects and only two of the independent variables, namely,
human resources conditions and design quality aspects. This implies that changes in human
resources conditions and/ or design quality aspects significantly affect performance.
Further, the findings revealed an association between human resources conditions and two of
the other three independent variables, namely, financial issues and design quality aspects.
This implies that human resources conditions and financial issues mutually affect each other.
46
Similarly, human resources conditions and design quality aspects mutually affect each other.
However, these correlations are fairly weak.
Table 5.1, Table 5.2 and Table 5.3 provide summaries of the major findings of the study as
described above.
Objective Findings Remarks
1. To establish the influence
of financial issues on
Likert scale score:
2.86 (Agree)
Majority of respondents agree that financial
issues influence the contractors’ performance
contractors’ performance of
government-funded
building projects in
Kirinyaga County, Kenya.
97.2% of the
respondents
Majority of respondents said that financial
issues influence successful completion of
projects
2. To determine the influence
of human resources
conditions on contractors’
Likert scale score:
1.88 (Agree)
Majority of respondents agree that human
resources issues influence the contractors’
performance
performance of government-
funded building projects in
Kirinyaga County, Kenya.
94.4% of the
respondents
Majority of respondents said that human
resources issues influence successful
completion of projects
3. To establish the influence
of site characteristics on
contractors’ performance of
Likert scale score:
1.67 (Agree)
Majority of respondents agree that site
characteristics influence the contractors’
performance
government-funded
building projects in
Kirinyaga County, Kenya.
94.4% of the
respondents
Majority of respondents said that site
characteristics influence successful completion
of projects
4. To determine the influence
of design quality aspects on
contractors’ performance of
Likert scale score:
2.11 (Agree)
Majority of respondents agree that design
quality issues influence the contractors’
perfomiance
government-funded
building projects in
Kirinyaga County, Kenya.
94.4% of the
respondents
Majority of respondents said that design
quality issues influence successful completion
of projects
Table 5.1: General Findings with respect to the Objectives
47
Dependent variableContractors’ performance of government-
funded building projects
Independent
variables
Pearson’s
Correlation
Value, r
Significance
level
Significance
value Remarks
1. Financial issues 0318 0.05 0.059 > 0.05 Pearson correlation marginally
significant. Weak correlation.
2. Human resources 0.354 0.05 0.034 < 0.05 Statistically significant.
conditions Strong correlation.
3. Site 0.214 0.05 0.210 >0.05 Pearson correlation insignificant.
charactensticsSc- Weak correlation.
4. Design quality 0.535 0.01 0.001 <0.01 Statistically significant.
aspects Strong correlation.
Table 5.2: Summary of Correlation between the Independent and Dependent Variables.
Human resources issues
Pearson’s
Correlation
Value, r
Significance
level
Significance
value
Remarks
1. Financial issues 0.382 0.05 0.022 <0.05 Statistically significant.
Fairly weak correlation
2. Design quality
aspects
0.384 0.05 0.021 < 0.05 Statistically significant.
Fairly weak correlation.
Table 5.3: Summary of Significant Correlation between Independent Variables.
5.3 DiscussionsThe study was aimed at investigating the factors influencing the performance of contractors
of government-funded building projects in Kenya. The development of the research was
anchored on the basic viewpoint that government-funded building projects in Kenya may be
studied from the perspective of general projects, with additional focus on building projects.
The takeoff point was an outline literature review of general performance of projects. Results
reviewed exemplified a general trend of non-successful delivery of projects. The study results
48
present a similar scenario, with revelation of a 46.3% success rate of government-funded
building projects in Kirinyaga County, Kenya.
Project performance was determined on the traditionally-accepted measure of cost-time-
quality triangle. Project success was addressed in terms of only the project management
aspect as postulated in the Al-Tmeemy et. al.,(2010) model. This centered the study on issues
of project performance during the construction phase. This was further operationalised with
reference to government-funded building projects in Kenya. Factors influencing the
contractors’ performance were established through review of various models of, and studies
on, general building projects which provided the theoretical framework. The broad cross
cutting themes thereby identified as fundamentally influencing the contractors’ performance
were: financial issues, human resources conditions, site characteristics and design quality
aspects. These were accordingly, conceptualised as the independent variables in the study.
The study findings reflect the views of the studies and models in the literature review.
Majority of the respondents viewed the identified factors as highly influential on the
contractors’ performance. This is evidenced by the general findings of ‘agree’ and ‘yes’ of
between 1.67 and 2.86 on the likert scale and 94.4% to 97.2% of responses, respectively.
Correlation analysis of the association between the dependent variable and independent
variables provides deeper insight into the respondents’ views. Strong correlation is revealed
between the contractors’ performance of government-funded building projects and only two
of the independent variables, namely, human resources conditions and design quality aspects.
Most of the literature reviewed does not specifically isolate the factors in terms of their
relative importance. However, on the human resources aspect, Abowitz D. and Toole T.,
(2010) highlight the key role played by people in all activities of construction. The strong
correlation in relation to design quality aspects has a strong basis in the ‘complexity’ of
building projects. The explanation is strongly put forth by Hendrickson C., (2008) in his
analysis of the integrated design and construction processes, which are non-independent, with
information and actions transmitted back and forth.
Weak correlation was revealed between contractors’ performance of government-funded
building projects and the other independent variables, namely, financial issues and site
characteristics. This was despite the acknowledgement of these factors as fundamental to
49
building projects success in the literature review. Reasons for this situation may be attributed
to unique characteristics of each project. The respondents identified critical aspects in relation
to financial issues as, payment delays and the contractors’ financial capacity. With reference
site characteristics, they identified the key critical aspect as each unique site’s features. From
this premise both of these factors may significantly differ from project to project depending
on pre-construction phase planning actions.
Another key finding was the association, although fairly weak, between human resources
conditions and two of the other three independent variables, namely, financial issues and
design quality aspects. This again may be attributed to the key role played by people in all
processes of construction. This argument is reinforced by the absence of the fourth factor, site
characteristics, in this association. It is notable that this is the only factor that is independent
of people’s direct influence during the construction phase.
5.4 Conclusion
The study findings fulfill the research objectives and answers research questions on factors
influencing the performance of contractors of government-funded building projects in
Kirinyaga County, Kenya. The findings reflect the propositions contained in various studies
and models as reviewed from literature sources that basically, the factors identified influence
project performance. It further reveals the relative influence of each of the factors, of greatest
significance being human resources conditions and design quality aspects. The findings
further provide pointers to actual ways in which these effects are manifested.
A key derivative of this study is the distinctive emergence of the human resources element as
the prime factor influencing the performance of contractors of government-funded building
projects. This primacy is apparent as the findings also revealed its association with other
fundamental factors.
Essentially, the research findings suggest that addressing all the factors identified, with
particular focus on he human resources and design quality elements would enhance the
contractors’ performance of the projects and ensure higher rates of projects success.
50
5.5 Recommendations
On the basis o f this study, the following recommendations are made:
1. The study recommends that in order to enhance project success, the human resources
element should receive due consideration through ensuring adequacy, and prudent
utilization o f the necessary personnel. This would provide considerable positive
influence on overall project management which would result in higher project success
rates.
2. The study also recommends that design quality aspects in terms of completeness and
complexity of, and modifications to the design, efficiency o f information flow and
supervision should be addressed comprehensively to enhance project success.
3. Financial issues and site characteristics aspects should also be addressed thereby
facilitating higher project success rates. Critical to this is addressing these issues in
pre-construction phase planning actions thus reducing their potential negative effects.
4. Finally, the study recommends addressing and resolving o f the four aspects in an
integrated manner in response to the complexity o f the building project process, thus
ensuring better performance by contractors and enhancing success rates of the
projects.
5.6 Suggestions for Further Study
ITiis research focused on project management issues influencing performance o f contractors
o f building projects during the construction phase. Further research is recommended on
i. pre-construction planning issues
ii. human resources aspects in building projects and
iii. the management, structure and culture of construction firms.
51
R E F E R E N C E S
Abdul-Rahman, H., Berawi, M.A., Berawi, A.R., Mohamed, O., Othman, M., and Yahya, I.A.
(2006). Delay mitigation in the Malaysian construction industry. Journal of Construction Engineering & Management, 132(2):pp. 125-133.
Abdul-Rahman, H., Wang, C., Takim, R., and Wong, S. (2010). Project schedule influenced by
financial issues: Evidence in construction industry. Full length research paper available at
http://www.academicjoumals.org/SRE. Retrieved on March 2, 2012 at 9.46 pm.
Abowitz, D. A. and Toole, T. M. (2010). Mixed method research: fundamental issues of design,
validity, and reliability in construction research. Journal of Construction Engineering and Management, 136( 1): pp. 108-116.
ABTEC (2006). Human resource issues for energy project development. Presented to Provincial
Energy Plan Review Department o f Natural Resources by ABTEC of the Newfoundland
and Labrador Building and Construction Trades Council, February,8 2006, Comer Brook.
Alarcon, L.F. and Mardones D.A. (2009). Improving the design-construction interface.
http://www.ce.berkeley.edu/~tommelein/IGLC-6/ AlarconAndMardones.pdf. Retrieved
on March 5, 2012 at 9.46 pm.
Ali, A.S. and Rahmat, I. (2009). The performance measurement o f construction projects
managed by ISO-certified contractors in Malaysia- Journal of Retail & Leisure Property (2010). 9: pp. 25-35.
Ali. A.S. and Kamaruzzaman, S.N. (2010). Cost performance for building construction projects
in Klang valley. Journal of Building Performance. Volume 1 Issue 1 2010: pp. 110.
Al-Tmeemy, S.M.H.M., Abdul-Rahman, H., and Harun, Z. (2010). Future criteria for success of
building projects in Malaysia. International Journal of Project Management, 29(3):pp.
337-348.
Amalraj, J., Hemani C., Ladouceur, K., and Verma, A. (2007). Project Management: Challenges
& Lessons Learned. BUEC 663. Doucet, J. (ed). Retrieved on February 8, 2012.
Aniekwu, N. and Ozochi, C.A. (2010). Restructuring education, training and human-resource
development in the Nigerian construction industry. Journal of Science and Technology Education Research, Vol. 1(5), October 2010: pp. 92 — 98.
52
Ankrah,N. A, Proverbs, D. and Debrah, Y. (2009).Factors influencing the culture of a
construction project organization: An empirical investigation. Journal of Engineering, Construction and Architectural Management, 16(1): pp. 26-47.
Assaf, S.A. and Al-Hejji, S. (2006). Causes o f delay in large construction projects. International Journal of Project Management, 24: pp. 349-357.
Cargan, L. (2007). Doing Social Research. Rowman & Littlefield.
Cleland, D.I. and Gareis, R.(2006). The evolution of project management. Global project
management handbook, Chapter 1. McGraw-Hill Professional. ISBN 0-07-146045-4
Denizer, Cevit, Kaufmann and Kraay,A.(2011). “Good Countries or Good Projects? Macro and
Micro Correlates of World Bank Project Performance”, Policy Research Working Paper
No. 5646. The World Bank.
Fink. A. (2006). How To Conduct Surveys: A Step-by-Step Guide. SAGE.
Given L.M., (2007). Descriptive Research. Encyclopedia of Measurement and Statistics. Vol. 1. Thousand Oaks, CA: Sage Reference, 2007.
GOK (2007). Kenya Vision 2030: A Globally Competitive and Prosperous Kenya. Government
Printers.
GOK (2009). End Term Review (Terminal Report) of the Economic Recovery Strategy for
Wealth and Employment Creation, (ERS), 2003-2007. Office of the Prime Minister-
Ministry o f State for Planning, National Development, and Vision 2030. Government
Printers.
GOK (2010). The Constitution o f Kenya. Government Printers.
GOK- MOF (2011). MTEF Manual. Kenya Budget Process. Treasury. Government Printers.
Hendrickson, C. (2008). Management for Construction. Fundamental Concepts for Owners,
Engineers, Architects and Builders. Prentice Hall. available on
http://pmbook.ce.cmu.edu/Project. Retrieved on January 2, 2012.
Kaur, P. (2006). Human resource planning in the construction industry-can it ever work.
Retrieved from on March 5, 2012 at 7.42pm.from http://en.articlesgratuits.com/
Khosravi, S. and Afshari, H. (2011). A Success Measurement Model for Construction Projects. A
paper presented at the 2011 International Conference on Financial Management and
Economics. IPEDR vol.l 1 (2011). Singapore: 1ACSIT Press.
53
Kimani, M., and Musungu, T., (2010). Reforming and Restructuring Planning and Building Laws and Regulations in Kenya for Sustainable Urban Development. A paper presented
at the 46tn ISOCARP Congress 2010 in Nairobi, Kenya.
Limodio, N. (2011). The Success of Infrastructure Projects in Low-Income Countries and the
Role o f Selectivity. Policy Research Working Paper 5694. The World Bank.
Manana, M.M., van Waveren, C. C. and Chan, K.Y. (2011). The relationship between CIDB
grading and project perfonnance in South Africa. ISEM 2011 Proceedings, September
21-23, Stellenbosch, South Africa.
McBride, S.B. (2008). Site planning and design. Regional Research Institute, West Virginia
University. Retrieved from http://www.rri.wvu.edu/WebBook/McBride/section3.html on
March 10, 2012 at 11.17 pm.
MOPW (2006). Buildings Organization and Operations Manual. Ministry o f Works, Buildings
Department, Nairobi Kenya. Government Printers.
Moghram M. (2010). Regulatory Frameworks of the Construction Sector in Yemen: Legal Framework and Suggested Changes. Paper presented at construction workshop
September 28-29, 2010 Sana’a, Yemen Republic.
Moramati-Proinvest (2011 (a)). Modernizing construction: The Kenyan construction industry. Report dated 7/16/2011-Moramati Foundation in conjunction with Proinvest.
Moramati-Proinvest (2011 (b)). Modernizing construction: Upgrade the classification and licensing systems for road and building contractors & consultants. Report dated
7/16/2011-Moramati Foundation in conjunction with Proinvest.
Muir, B. (2006). Challenges Facing Today’s Construction Manager. Supplemental Reading for
CIEG 486-010. Construction Methods & Management. University of Delaware.
NACPD (2005). Kirinyaga District Strategic Plan 2005 - 2010 for implementation o f the national
population policy for sustainable development. NACPD, Ministry o f Planning and
National Development, Government of Kenya.
Njihia M. (2011). Overview o f the construction industry in Kenya. Construction Business /?ev/ew,September 14,2011. Retrieved on March 12, 2012 at 10.36 pm. from
http://wAvw.constructionkenya.com/999/major-opportunities-in-construction/
54
\jihia M. (2012). Kenya construction industry to adopt Eurocodes by 2013. Construction Business Review, February25,2012. Retrieved on March 12, 2012 at 10.48 pm. from
http://www.constructionkenya.com/999/major-opportunities-in-construction/.
Njuguna, H. B. (2008). The construction industry in Kenya and Tanzania: Understanding the mechanisms that promote growth. DBA assignment presentation. ESAM1, Tanzania.
Mokes, S. & Kelly, S. (2007). The definitive guide to project management: the fast track to
getting the job done on time and on budget. Prentice Hall.
O’Neal, S.V. and Beming P.W. (2007). U.S. construction, architecture and engineering industry: An overview for international investors. A paper presented to the Shanghai
Association o f International Economic and Technological Cooperation in Shanghai on
December 10, 2002, and to the China International Contractors’ Association on
December 12, 2002, in Beijing.
OECD (2006). Policy Framework for Investment. OECD Publishing.
Omar. 0 . (2006). Work environment factors and job performance: The construction manager’s
perspective. University o f Malaysia.
Ong, H.T. (2007). Effective project management - Essential elements for successful projects. A
conference paper presented at the Inaugural Construction Conference 2007 jointly
organized by CIOB Singapore and National University o f Singapore on January 25, 2007
in Singapore.
Opoku. A. and Fortune, C. (2011). Organizational learning and sustainability in the construction
industry. The Built & Human Environment Review, Vol. 4, Special Issue 1,2011: pp. 98
Oyewabi, L.O., Ibrahim, A.D., Ganiyu, B.O. & Okwori, I.G. (2011). Impact o f organizational
culture on the occurrence of rework in building project. Journal of Emerging Trends in Economics and Management Sciences JETEMS, 2 (5): pp. 426-435
Panas. A. and Pantouvakis, J.P. ( 2010). Evaluating research methodology in construction
productivity studies. The Built & Human Environment Review, Vol. 3, Special Issue 1,
2010: pp. 63
PIPC (2006). Global Project Management Survey: February, 2006. www.pipc.com
PMI (2010). Program Management 2010: A study o f program management in the U.S. Federal
Government. Project Management Institute.
55
PMI-KPMG (2010). PMI-KPMG Study on drivers for success in infrastructure projects 2010.
Managing for change. KPMG India.
Saqib, M., Farooqui, R.U. and Lodi S.H. (2008). Assessment of Critical Success Factors for Construction Projects in Pakistan. A paper presented at the First International
Conference on Construction In Developing Countries (ICCIDC-I) “Advancing and
Integrating Construction Education, Research & Practice” August 4-5, 2008, Karachi,
Pakistan.
Thanasegaran G. (2009). Reliability and validity issues in research. Univ. Putra Malaysia.
Retrieved on March 15, 2012 at 8.43 pm. from
http://econ.upm. edu.my/researchbulletin/artikel/Vol%204%20March%202009/35-40%20
Ganesh.pdf.
Uher, T.E. and Davenport, P. (2009). Fundamentals of building contract management. Univ. of
New South Wales Press Ltd.
Veronika, A. (2011). Factors in human resources management that influence construction
company’s performance in Indonesia, http://ui.academia.edu/. Retrieved on March 6,
2012 at 8.27 pm.
Wong, P. (2007). “Timely response needed to resolve human resources issues and brain drain affecting the construction A speech presented during the Master Builders Association
Malaysia (MBAM) 53rd Anniversary Dinner on 10th August 2007 (Friday) at Grand
Lagoon Ballroom, Sunway Resort Hotel & Spa (SRHS).
World Bank (2011). Africa Development Indicators 2011. Washington, D.C.: International Bank
for Reconstruction and Development/The World Bank.
56
APPfcNDIX 1
UNIVERSITY OF NAIROBICOLLEGE OF EDUCATION AND EXTERNAL STUDIES
SCHOOL OF CONTINUING AND DISTANCE EDUCATION DEPARTMENT OF EXTRA MURAL STUDIES P 0 Box 598 - NYERI: T e l: 061-2030460
TO WHOM IT MAY CONCERN12June 2012
SUBJECT : CONFIRMATION LETTER
MUGUIYI MAUREEN WANJIKU - REG. NO.L50/63941/2010
This is to confirm that the above named is a bona fide student of University of Nairobi
pursuing a Master of Arts Degree in Project Planning and Management - in the School of
Continuing and Distance Education - Department of Extra Mural Studies.
She has completed course work and is currently writing the Research Project which is a requirement
for the award of the Masters Degree.
Her topic is ‘‘Factors Influencing the performance of Contractors of Government-funded
Building Projects in Kenya; A case ofKirinyaga County, Kenya”
Any assistance accorded to her will be highly appreciated.
RESIDENT LECTURER MYEPJ & MT. KENYA REGION
57
APPENDIX 2-Muguiyi Maureen Wanjiku
P.O. Box 390l&J'JH 2(112. Kerueova.
Tel:^k
18 June 2012
I t -
Dear Sir,
iu:: LETTER OF INTRODUCTION'
IL Q l'E S T TO CARRY OUT AN ACADEMIC RESEARCH ON PROJECTS MANAGED BY
IKE MIN. OF PUBLIC WORKS- KIRIN YAGA COUNTY
management. I am carrying out an academic research on factors influencing the performance of
contractors o f government-funded building projects in Kenya, specifically the projects managed
by the Ministry of Public Works, Kirinyaga County.
I am kindly seeking your authority to collect data via questionnaires from contractors
undertaking such projects in your area o f jurisdiction. All information that will be collected will
i?e treated with utmost confidentiality.
attached herewith, please find a sample questionnaire for your records.
1 our support will be highly appreciated.
Vours faithfully,
- am a student at the University o f Nairobi pursuing a masters degree in project planning and
No. L50/63941/2010
58
A P P E N D I X 3: S A M P L E L E T T E R O F I N T R O D U C T I O N T O R E S P O N D E N T S
Muguiyi Maureen Wanjiku
P.O. Box 390
Kerugova.
T el:......................................
18 June 2012
The Managing Director
M/s.............................................................
Dear Sir/ Madam,
RE: L E T T E R O F I N T R O D U C T I O N
REQUEST FOR YOUR PARTICIPATION AS A RESPONDENT IN AN ACADEMIC
RESEARCH
1 am a student at the University of Nairobi pursuing a masters degree in project planning and
management. I am carrying out an academic research on factors influencing the performance of
contractors of government-funded building projects in Kenya, specifically the projects managed
by the Ministry of Public Works, Kirinyaga county.
In your position o f authority in a construction firm undertaking such projects, you have been
identified as a principal respondent in the study. Attached herewith is a questionnaire for your
responses. Please respond to the items honestly and completely, and do not include your name in
the questionnaire. All information that you may provide will be treated with utmost
confidentiality.
Kindly return the questionnaire to ............................................. by.......................... Alternatively,
you may call the telephone number above for it to be collected at a place convenient to you.
0ur support and co-operation will be highly appreciated.
Tours faithfully,
Maureen W. Muguiyi
Reg. No. L50/63941/201059
No.APPENDIX 4: SAMPLE QUESTIONNAIRE
Factors in f lu e n c in g th e p e r f o r m a n c e o f c o n t r a c to r s o f g o v e rn m e n t - fu n d e d b u i ld in g
projects in K e n y a : a e a se of K i r in y a g a C o u n ty , K en y a .
(Research conducted with the authority of the University of Nairobi, College of Education and External
Studies. School of Continuing and Distance Education, Department of Extra Mural Studies)
INSTRUCTIONS: The questionnaire has Six sections. Kindly respond to all questions.
All information will be treated with utmost confidentiality. Please tick (V ) in the appropriate
box. Where explanation is requested, kindly be concise.
S E C T IO N I: G E N E R A L I N F O R M A T I O N
1. Age bracket (years): 18-20 O 21-30 Q l - 4 0 D 1-50 I kbove 50 I I
Female2. Gender:
3. Education level:
Male
Certificate
□□ □□ QDiploma L J Degree I__ I Masters and above □
4. Company’s registration category: A or B C U c o r D □ E or F Q or H □
5. No. o f years of operation: less than 5! 1 5 - lo l 1 11-15 1 116-20 1 Lbove 20 I 1
S E C T IO N I I : F IN A N C IA L IS S U E S
6. Kindly respond appropriately to the statements below.
KEY: 1.Strongly Agree 2.Agree 3.Neither Agree nor Disagree 4.Disagree 5. Strongly Disagree
Statement 1 2 3 4 5
i The contract sum is usually equivalent to the tender sum
ii Loans are usually quickly processed by banks and other financial institutions
r We update plans and records o f income and expenditure on a weekly basis
iv Contractors only bid for projects for which they have the capacity to undertake
fv Valuation and certification o f work is completed within the stipulated two weeks period1 V* Valuations for payment are a source of disputes
r Payment certificates are honoured within the stipulated two weeks period
Do you think financial issues influence successful completion of projects? Yes l _ l No
IfYes, in what way......................................................................................................................
60
No.
SECTION I I I : H U M A N R E S O U R C E S C O N D I T I O N S
v Kindly respond appropriately to the statements below.
KEY: 1.Strongly Agree 2.Agree 3.Neither Agree nor Disagree 4.Disagree 5. Strongly Disagree
Statement 1 2 3 4 5
i Personnel (skilled, semi-skilled, unskilled and management) is available when required
ii Recruitment o f personnel on the basis of education, training and experience ensures quality of work
iii Sometimes there is excess or shortage of labour available in a particular area
iv Terms of employment (such as daily wages, piece work) affect the work output of personnel
v Ways used to motivate personnel (such as bonuses, time-off, training opportunities) affect productivity levels
vi Assignments are allocated to personnel based on their specialized skills
9. Do you think human resources conditions influence successful completion Yes
of projects?
If Yes, in what way
S E C T IO N IV : S I T E C H A R A C T E R I S T I C S
10. Kindly respond appropriately to the statements below.
KEY: 1 .Strongly Agree 2.Agree 3.Neither Agree nor Disagree 4.Disagree 5. Strongly Disagree
Statement 1 2 3 4 5
Means of accessing a site affect the cost and duration o f a project
i The topography and slope affect the cost and duration o f a project___
ii Availability o f utilities (such as water, electricity, sewer) on or near site affect the cost and duration of a project
v Actual soil condition and existing vegetation affect the cost and duration o f a project
v Climatic conditions in an area affect the cost and duration of a project
H Do you think site characteristics influence successful completion
of projects?
IfYes, in what w ay..............................................................................
Y es Q no □
61
No.
SECTION V : D E S I G N Q U A L I T Y A S P E C T S
12. Kindly respond appropriately to the statements below.
KEY: l.Strongly Agree 2.Agree 3.Neither Agree nor Disagree 4.Disagree 5. Strongly Disagree
Statement 1 2 3 4 5
i Project documentation (drawings and bills of quantities) is usually accurate and complete
ii Projects undertaken can usually be done to completion using skilled personnel and machinery
iii Design changes affect the work programme and cost of a project
iv The cost o f materials is dependent on their availability
V The types of materials specified determine the amount o f time taken for their procurement and delivery
vi Relevant information is usually communicated within a reasonable period of time
vii A qualified overall supervisor must be on site at all times
viii Project team site inspections are held bi-weekly and site meetings are held monthly as stipulated
13. Do you think design quality aspects influence successful completion
of projects?
If Yes, in what w ay....................................................................................
Yes ]no □
S E C T IO N V I : P R O J E C T P E R F O R M A N C E
14. Kindly respond appropriately to the statements below.
KEY: l.Strongly Agree 2.Agree 3.Neither Agree nor Disagree 4.Disagree 5. Strongly Disagree
Statement 1 2 3 4 5
' Projects are done within the approved cost
ii Projects are completed within the contract duration
' iii Projects executed conform to specifications
Thank you for your participation.
62
APPENDIX 5: FREQUENCY TABLES OF QUESTIONNAIRE RESPONSES ONVARIABLES
1. Financial issues
Frequency Percent Valid Percent Cumulative PercentValid Strongly agree 5 13.9 13.9 13.9
Agree 12 33.3 33.3 47.2Neither agree nor disagree 13 36.1 36.1 83.3
Disagree 6 16.7 16.7 100.0Total 36 100.0 100.0
Loans are usually quickly processed by banks and other financial institutions
Frequency Percent Valid Percent Cumulative PercentValid Strongly agree 3 8.3 8.3 8.3
Agree 13 36.1 36.1 44.4Neither agree nor disagree 5 13.9 13.9 58.3
Disagree 12 33.3 33.3 91.7Strongly Disagree 3 8.3 8.3 100.0
Total 36 100.0 100.0
We update plans and records o f income and expenditure on a weekly basis
Frequency Percent Valid Percent Cumulative PercentValid Strongly agree 3 8.3 8.3 8.3
Agree 7 19.4 19.4 27.8Neither agree nor disagree 7 19.4 19.4 47.2
Disagree 16 44.4 44.4 91.7Strongly Disagree 3 8.3 8.3 100.0
Total 36 100.0 100.0
Contractors only bid for projects fo r which they have the capacity to undertake
Frequency Percent Valid Percent Cumulative PercentValid Strongly agree 1 2.8 2.8 2.8
Agree 8 22.2 22.2 25.0Neither agree nor disagree 13 36.1 36.1 61.1
Disagree 14 38.9 38.9 100.0Total 36 100.0 100.0
Valuation and certification of work is completed
Frequency Percent Valid Percent Cumulative PercentValid Strongly agree 3 8.3 8.3 8.3
Agree 17 47.2 47.2 55.6Neither agree nor disagree 11 30.6 30.6 86.1
Disagree 2 5.6 5.6 91.7Strongly Disagree 3 8.3 8.3 100.0
Total 36 100.0 100.0
63
The contract sum is usua : to the tender sumFrequency Percent Valid Percent Cumulative P
Strongly agree 5 13.9 13.9 13.9Agree 12 33.3 33.3 47.2
Neither agree nor disagree 13 36.1 36.1 83.3Disagree 6 16.7 16.7 100.0
Valuations for payment are a source of disputes
Frequency Percent Valid Percent Cumulative PercentValid Strongly agree 13 36.1 36.1 36.1
Agree 12 33.3 33.3 69.4Neither agree nor disagree 5 13.9 13.9 83.3
Disagree 4 11.1 11.1 94.4Strongly Disagree 2 5.6 5.6 100.0
Total 36 100.0 100.0
Payment certificates are honoured w ithin the stipulated two weeks period
Frequency Percent Valid Percent Cumulative PercentValid Strongly agree 2 5.6 5.6 5.6
Agree 2 5.6 5.6 11.1Neither agree nor disagree 16 44.4 44.4 55.6
Disagree 12 33.3 33.3 88.9Strongly Disagree 4 11.1 11.1 100.0
Total 36 100.0 100.0
2. Human resources issuesPersonnel (skilled, semi-skilled, unskilled and management) is available when required
Frequency Percent Valid Percent Cumulative PercentValid Strongly agree 10 27.8 27.8 27.8
Agree 15 41.7 41.7 69.4Neither agree nor disagree 10 27.8 27.8 97.2
Disagree 1 2.8 2.8 100.0Total 36 100.0 100.0
Frequency Percent Valid Percent Cumulative PercentValid Strongly agree 19 52.8 52.8 52.8
Agree 17 47.2 47.2 100.0Total 36 100.0 100.0
Sometimes there is excess or shortaq e of labour available in a particular area
Frequency Percent Valid Percent Cumulative PercentValid Strongly agree 6 16.7 16.7 16.7
Agree 23 63.9 63.9 80.6______ Neither agree nor disagree 7 19.4 19.4 100.0
64
r
Personnel (skilled, semi-skilled, unskilled and management) is available when required
Frequency Percent Valid Percent Cumulative PercentStrongly agree 10 27.8 27.8 27.8
Agree 15 41.7 41.7 69.4Neither agree nor disagree 10 27.8 27.8 97.2
Disagree 1 2.8 2.8 100.0Total 36 100.0 100.0
Terms of employment affect the work output o f personnel
Frequency Percent Valid Percent Cumulative PercentValid Strongly agree 10 27.8 27.8 27.8
. Agree 24 66.7 66.7 94.4Neither agree nor disagree 1 2.8 2.8 97.2
Disagree 1 2.8 2.8 100.0Total 36 100.0 100.0
Ways used to motivate personnel affect productiv ity levels
Frequency Percent Valid Percent Cumulative PercentValid Strongly agree 11 30.6 30.6 30.6
Agree 22 61.1 61.1 91.7Neither agree nor disagree 2 5.6 5.6 97.2
Disagree 1 2.8 2.8 100.0Total 36 100.0 100.0
Assignments are allocated to personnel based on the ir specialised skills
Frequency Percent Valid Percent Cumulative PercentValid Strongly agree 8 22.2 22.2 22.2
Agree 16 44.4 44.4 66.7Neither agree nor disagree 11 30.6 30.6 97.2
Disagree 1 2.8 2.8 100.0Total 36 100.0 100.0
3. Site characteristicsMeans of accessing a site affect the cost and duration of a project
Frequency Percent Valid Percent Cumulative Percent
Valid Strongly agree 10 27.8 27.8 27.8Agree 24 66.7 66.7 94.4
Neither agree nor disagree 1 2.8 2.8 97.2Strongly Disagree 1 2.8 2.8 100.0
Total 36 100.0 100.0
The topography and slope affect the cost and duration of a project
Frequency Percent Valid Percent Cumulative PercentValid Strongly agree 13 36.1 36.1 36.1
_ Agree 23 63.9 63.9 100.0
65
3. Site characteristicsMeans o f accessing a site affect the cost and duration of a project
Frequency Percent Valid Percent Cumulative PercentStrongly agree 10 27.8 27.8 27.8
Agree 24 66.7 66.7 94.4Neither agree nor disagree 1 2.8 2.8 97.2
Strongly Disagree 1 2.8 2.8 100.0Total | 36 100.0 100.0
Availab ility o f utilities on or near s ite affect the cost & duration of a project
Frequency Percent Valid Percent Cumulative PercentValid Strongly agree 15 41.7 41.7 41.7
Agree 21 58.3 58.3 100.0Total 36 100.0 100.0
Actual soil condition and existing vegetation affect the cost & duration of a project
Frequency Percent Valid Percent Cumulative PercentValid Strongly agree 19 52.8 52.8 52.8
Agree 17 47.2 47.2 100.0Total 36 100.0 100.0
Climatic conditions in an area affect the cost and duration of a project
Frequency Percent Valid Percent Cumulative PercentValid Strongly agree 10 27.8 27.8 27.8
Agree 24 66.7 66.7 94.4Neither agree nor disagree 1 2.8 2.8 97.2
Strongly Disagree 1 2.8 2.8 100.0Total 36 100.0 100.0
4. Design quality issuesProject documentation is usually accurate and complete
Frequency Percent Valid Percent Cumulative PercentValid Agree 10 27.8 27.8 27.8
Neither agree nor disagree 18 50.0 50.0 77.8Disagree 7 19.4 19.4 97.2
Strongly Disagree 1 2.8 2.8 100.0
Total 36 100.0 100.0
Projects undertaken can usually be done to completion using skilled personnel and machinery
Frequency Percent Valid Percent Cumulative PercentValid Strongly agree 10 27.8 27.8 27.8
Agree 23 63.9 63.9 91.7Neither agree nor disagree 3 8.3 8.3 100.0
Total 36 100.0 100.0
Design changes affect the work programme and cost of a project
Frequency Percent Valid Percent Cumulative PercentValid Strongly agree 22 61.1 61.1 61.1
____ Agree 14 38.9 38.9 100.0
66
Project documentation is usually accurate and complete
Frequency Percent Valid Percent Cumulative PercentAgree 10 27.8 27.8 27.8
Neither agree nor disagree 18 50.0 50.0 77.8Disagree 7 19.4 19.4 97.2
Strongly Disagree 1 2.8 2.8 100.0Total | 36 100.0 100.0 _ L
The cost of materials is dependent on their availability
Frequency Percent Valid Percent Cumulative PercentValid Strongly agree 9 25.0 25.0 25.0
Agree 24 66.7 66.7 91.7Neither agree nor disagree 1 2.8 2.8 94.4
Disagree 2 5.6 5.6 100.0Total 36 100.0 100.0
The types o f m ateria ls specified determine the amount of time taken o f their procurement and delivery
Frequency Percent Valid Percent Cumulative PercentValid Strongly agree 10 27.8 27.8 27.8
Agree 24 66.7 66.7 94.4Neither agree nor disagree 2 5.6 5.6 100.0
Total 36 100.0 100.0
Relevant information is usually communicated w ithin a reasonable period of time
Frequency Percent Valid Percent Cumulative PercentValid Strongly agree 2 5.6 5.6 5.6
Agree 15 41.7 41.7 47.2Neither agree nor disagree 16 44.4 44.4 91.7
Disagree 3 8.3 8.3 100.0Total 36 100.0 100.0
A qualified overall supervisor must be on site at all time
Frequency Percent Valid Percent Cumulative PercentValid Strongly agree 15 41.7 41.7 41.7
Agree 20 55.6 55.6 97.2Neither agree nor disagree 1 2.8 2.8 100.0
Total 36 100.0 100.0
Project team site inspections are held b i-wekly and site meetings are held m onthly as stipulated
Frequency Percent Valid Percent Cumulative PercentValid Strongly agree 3 8.3 8.3 8.3
Agree 7 19.4 19.4 27.8Neither agree nor disagree 17 47.2 47.2 75.0
Disagree 7 19.4 19.4 94.4Strongly Disagree 2 5.6 5.6 100.0
67
Relevant information is usually communicated w ithin a reasonable period o f time
Frequency Percent Valid Percent Cumulative PercentStrongly agree 2 5.6 5.6 5.6
Agree 15 41.7 41.7 47.2Neither agree nor disagree 16 44.4 44.4 91.7
Disagree 3 8.3 8.3 100.0Total 36 100.0 100.0
5. Project performanceProject are done within the approved cost
Frequency Percent Valid Percent Cumulative PercentValid Strongly agree 1 2.8 2.8 2.8
Agree 10 27.8 27.8 30.6Neither agree nor disagree 22 61.1 61.1 91.7
Disagree 2 5.6 5.6 97.2Strongly Disagree 1 2.8 2.8 100.0
Total 36 100.0 100.0
Projects are completed within the contract duration
Frequency Percent Valid Percent Cumulative PercentValid Strongly agree 2 5.6 5.6 5.6
Agree 8 22.2 22.2 27.8Neither agree nor disagree 17 47.2 47.2 75.0
Disagree 9 25.0 25.0 100.0Total 36 100.0 100.0
Projects executed conform to specifications
Frequency Percent Valid Percent Cumulative PercentValid Strongly agree 3 8.3 8.3 8.3
Agree 26 72.2 72.2 80.6Neither agree nor disagree 5 13.9 13.9 94.4
Disagree 2 5.6 5.6 100.0Total 36 100.0 100.0
68
APPENDIX 6: RAW DATA
X2 X4XI HUMAN X3 DESIGN Y
FINANCIAL RESOURCES SITE QUALITY CONTRACTORS’ISSUES CONDITIONS CHARACTERISTICS ASPECTS PERFORMANCE
3.57 1.83 1.2 2.25 2.673.14 1.83 1.2 1.88 23.29 1.33 1 1.88 22.57 2.17 2.2 2.75 2.672.57 1.67 1.4 1.63 23.71 2.17 1.2 2.25 3.333.71 1.67 1 2.13 2.332.29 1.67 1.6 1.88 1.672.71 1.67 1.6 1.5 2.333.57 1.67 1.4 2.5 2.672.86 1.83 1.6 1.88 2.331.57 1.33 1 2 23.14 2.17 1 2.63 33.14 2 1 1.25 2.333.14 1.67 2.6 1.88 1.332.43 1.67 1.8 2.25 2.673.14 1.33 2.2 2.25 4.33
3 2.33 1.6 2.25 2.672.57 1.17 2 2.13 2.332.57 2.17 1.8 2.25 2.67
3 2.33 2 2.13 2.672.43 1.67 1.8 2.25 2.672.29 1.5 2 2 2.672.86 2.17 1.6 2.25 2.673.29 2.33 2 2.63 3.332.43 1.5 1.6 2 2.672.57 2 2 2 2.673.0 2.33 2 2.13 2.67
2.14 1.5 2 1.75 2.672.71 2.5 1.6 1.88 32.71 1.5 1.8 2.25 2.672.29 1.5 1.8 2 2.332.86 2.33 1.6 2.13 2.673.43 2.5 2 2.5 3.333.29 2.33 2 2.5 3.673.0 2.5 2 2.5 2.67
69
SYNTAX OUTPUT
COMPUTE X l=m ean(v.6i,v.6 ii,v.6 iii,v .6 iv,v.6v,v.6vi,v.6vii).VARIABLE LABELS X I 'financial issues'.EXECUTE.
COMPUTE X2=m ean(v.8i,v.8ii,v.8iii,v.8iv,v.8v,v.8vi).VARIABLE LABELS X2 'Human resources conditions'.EXECUTE.
COMPUTE X 3 = m e a n (v .l0 i,v .l0 ii,v .l0 iii,v .l0 iv ,v .l0 v ).VARIABLE LABELS X3 'site characteristics'.EXECUTE.
COMPUTE X 4 = m e a n (v .l2 i,v .l2 ii,v .l2 iii,v .l2 iv ,v .l2 v ,v . l2 v i,v .l2 v ii,v .l2 v iii) . VARIABLE LABELS X4 'design qua lity aspects'.EXECUTE.
COMPUTE Y = m e a n (v .l4 i,v .l4 ii,v .l4 iii) .VARIABLE LABELS Y 'contractors ' perform ance'.EXECUTE.
70
APPENDIX 7: RELIABILITY AND VALIDATION STATISTICS
Reliability
Reliability Statistics
Cronbach’sAlpha
Cronbach’s Alpha Based
onStandardized
ItemsN of Itemsm00r- .815 43
Cronbach’s alpha-0.783. This indicates that the tool considered in this analysis was reliableenough.
- Validation
ANOVAb
Model
Sum of
Squares df
Mean
Square F Sig.
Regression 3.589 4 .897 4.037 .009a
Residual 6.890 31 .222
Total 10.478 35
a. Predictors: (Constant), Financial issues, Human resources conditions, Site
characteristics and Design quality aspects.
b. Dependent Variable: Project performance (Contractors’ performance)
71
C lass if ica tio n o f B u ild in g C o n t r a c t o r s in K e n y a
APPENDIX 8:
PROJECT COST Annual Experience FINANCIAL STATUS
CEILING (KSh Million) Registration
General Specialist (KSh) (Years) Annual Liquidity Fixed
Contractors Contractors Turnover Assets
% of % of % of
Class Class Class
S. limit limit limit
Class 5 1 1000 - N/A N/A N/A
H1 Class 10 2 1000 - N/A N/A N/A
G
Class 20 4 1000 2 75% 5% 20%
F
Class 50 10 3000 4 75% 5% 20%
E
Class 100 20 3000 4 75% 5% 20%
D
Class 150 30 3000 6 75% 5% 20%
C
Class 250 50 5000 8 75% 5% 20%
B
Class Unlimited Unlimited 5000 10 75% 5% 20%
! A1
Classification for registration and upgrading of building contractors in Kenya
(Source: Ministry o f Public Works, Republic of Kenya - December 2004)
72