INTERNATIONAL ADR MOOTING COMPETITION, 2016 5th July
-
Upload
khangminh22 -
Category
Documents
-
view
1 -
download
0
Transcript of INTERNATIONAL ADR MOOTING COMPETITION, 2016 5th July
INTERNATIONAL ADR MOOTING COMPETITION, 2016
5th July- 9th July 2016
HONG KONG
ON BEHALF OF AGAINST
CLAIMANT RESPONDENT
Albas Watchstraps Mfg. Co. Ltd., Gamma Celltech Co. Ltd.,
241 Nathan Drive, 17 Rodeo Lane,
Yanyu City, Yanyu, Mulaba, Wulaba
MEMORANDUM FOR CLAIMANT
TEAM NUMBER 872 C
LIST OF ABBREVIATIONS
ABBREVIATION
CONTENT
& And
AAA Rules International Arbitration Rules of the
American Arbitration Association
Art. Article
CIETAC China International Economic and Trade
Arbitration Commission
CIETAC Rules China International Economic and Trade
Arbitration Commission CIETAC Arbitration
Rules
CISG United Nations Convention on Contracts for
the International Sale of Goods
Clarification ADR International Mooting Competition,
Request for Clarifications
Claimant Albas Watchstraps Mfg. Co. Ltd.
Co. Company
DDP Delivery Duty Paid
Ex. Exhibit
FTCA Serbia The Foreign Trade Court of Arbitration with
the Chamber of Commerce and Industry of
Serbia
ICC Rules International Chamber of Commerce Rules
of Arbitration
ICSID Convention Convention on the Settlement of Investment
Disputes between States and Nationals of
Other States
Incoterms 2010 International Commercial Terms 2010
Japan CAA Rules Commercial Arbitration Rules of the Japan
Commercial Arbitration Association
No. Number
p. Page
Parties Albas Watchstraps Mfg. Co. Ltd. and
Gamma Celltech Co. Ltd.
PCA Croatia The Permanent Court of Arbitration with the
Croatian Chamber of Commerce
Respondent Gamma Celltech Co. Ltd.
S. Section
SoD Statement of Defense
SPA Sale and Purchase Agreement
The Agreement The Sale and Purchase Agreement between
Albas Watchstraps Mfg. Co. Ltd. and
Gamma Celltech Co. Ltd.
The Tribunal Ms. Felicity Chan, Dr. Anne Descartes and
Mr. Martin Mayfair (presiding arbitrator)
UNCITRAL Rules United Nations Commission on International
Trade Law Arbitration Rules
VAC Rules Rules of Arbitration and Conciliation of the
Vienna Arbitration Centre
TABLE OF AUTHORITIES
BOOKS
Cited As Content Citing
Footnotes
Chap. 5.4(c) Redfern &
Hunter
REDFERN A. & HUNTER M., LAW AND PRACTICE OF
INTERNATIONAL COMMERCIAL ARBITRATION, 1999,
Chap. 5.4(c)
1
Redfern &
Hunter(2004), p. 295
REDFERN A. & HUNTER M., LAW AND PRACTICE OF
INTERNATIONAL COMMERCIAL ARBITRATION, (4th
ed., London 2004), p. 295
12
BORN(2001), p. 298 BORN G., INTERNATIONAL COMMERCIAL
ARBITRATION, (2nd ed.. Hague 2001), p. 298
12
FOUCHARD(1999), p.
1222
FOUCHARD GAILLARD GOLDMAN, INTERNATIONAL
COMMERCIAL ARBITRATION (ed. Gaillard E., Savage
J., The Hague 1999) p. 1222.
12
Honnold(2009) UNIFORM LAW FOR INTERNATIONAL SALES UNDER
THE 1980 UNITED NATIONS CONVENTION, Harry M.
Flechtmer ed., (Wolters Kluwer, 4th ed., 2009)
44,47
Schwenzer(2010) INGEBORG & SCHWENZER, COMMENTARY ON THE UN
CONVENTION ON THE INTERNATIONAL SALE OF
GOODS (3rd ed., 2010)
36, 41, 46,
51, 52
CASES
Cited As Content Citing
Footnotes
ARAMCO Case Saudi Arabia v. Arabian American Oil Co. Ltd
(ARAMCO)ILR 1963, at 117
4
Joc Oil Case Sojuznefteexport (SNE) v. Joc Oil Ltd.
translated in (1990) 6 Arbitration International 79
4
Texaco Case Texaco Overseas Petroleum Co./California Asiatic
Oil Co. v. Government of Libya YCA 1979
4
JA Apparel Case
(2010)
JA Apparel Corp. v. Aboud 682 F.Supp 2d 294 2010
U.S. Dist. LEXIS 2151 (S.D.N.Y. 2010)
5
Reyes Case (2012) Reyes v. Metromedia Software Inc. 840 F.Supp.2d
752, 2012 WL 13935 S.D.N.Y., January 04, 2012
5,9
MBIA Case (2012) MBIA Ins. Corp. v. Patriarch Partners VIII, LLC
2012 WL 382921 S.D.N.Y., February 06, 2012
5, 10
Dan Dong Dong Jin
case (2012)
Dan Dong Dong Jin Garment Co. Ltd. v. KIK
Fashions Inc.
2012 WL 2433530 S.D.N.Y.,2012, June 27, 2012
5
Hirshenson
case(2001)
Hirshenson v. Spaccio 800 So. 2d 670, 674 (Fla. 5th
DCA 2001)
6
Mercury Construction Moses H. Cone v. Mercury Constr. Corp. 460 U.S. 1, 6
case (1983) 24-25 (1983)
Maguire v. King
(2005)
Maguire v. King
917 So.2d 263, 266 (Fla.App. 2005)
6
Owens-Brockway
case (1996)
Austin v. Owens-Brockway Glass Container, Inc.
78 F.3d 875, 879 (4th Cir. 1996)
6
Ziegler case (1982) Ziegler v. Knuck 419 So. 2d 818 (Fla. 3rd DCA 1982 6
Conax Florida
case(2007)
Conax Florida Corp. v. Astrium Ltd.
499 F. Supp. 2d 1287 (M.D. Fla. 2007)
6
Bharat Engineering
Corp case (1977)
Union of India v. Bharat Engineering Corp.
(1977) 11 ILR Delhi 57
7
Canadian National
Railway case(1999)
Canadian National Railway and Others v. Lovat
Tunnel Equipment Inc (1999)174 DLR (4th) 385
7
WSG Nimbus case
(2002)
WSG Nimbus Pte Ltd v. Board of Control for Cricket
in Sri Lanka [2002] 3 SLR 603
7
NB Three Shipping
case (2004)
NB Three Shipping Ltd v. Harebell Shipping Ltd.
[2004] EWHC (Comm) 2001
7
South India Shipping
case (1981)
Bremer Vulkan Schiffbau und Maschinenefabrik v.
South India Shipping Corp. Ltd. [1981] AC 909
8`
Corral case (2012) Corral v. Outer Marker LLC
2012 WL 243318 E.D.N.Y., January 24, 2012
9
Convergent Wealth
Advisors case (2012)
Convergent Wealth Advisors LLC v. Lydian Holding
Co. 2012 WL 2148221 S.D.N.Y.,2012, June 13, 2012
9
Homeward
Residential case
(2014)
Homeward Residential, Inc. v. Sand Canyon Corp.
2014 WL 2510809 S.D.N.Y.,2014. May 28, 2014
9
Carolina Power &
Light Co. case (1983)
John Hancock Mut. Life Ins. Co. v. Carolina Power &
Light Co. 717 F.2d 664, 669 n.8 (2d Cir. 1983)
10
Ajax Tool Works
case(2003)
Ajax Tool Works, Inc. v. Can.-Eng Manufacturing
Ltd. Available at: http://cisgw3.law.pace.edu/
case/30129ul.html
15
Easom Automatom
Systems case(2007)
Easom Automation Systems, Inc. v. Thyssenkrupp
Fabco Corp. 2007 U.S. Dist. LEXIS 72461 (E.D.
Mich. 2007). Available at:
http://www.cisg.law.pace.edu/cisg/biblio/zoccolillo1.h
tml
16
Atlarex case(2000) Rheinland Versicherungen v. Atlarex
Italy 12 July 2000 District Court Vigevano
Available at:
http://cisg3.law.pace.edu/cases/000712i3.html.
18
Assante Technologies
case (2001)
Assante Technologies, Inc. v. PMC-Sierra, Inc.
2001, 164 F.Supp. 2d 1142.
21
Società X v. Società
Y (1994).
Società X v. Società Y,
Arbitration 19 April 1994 Ad Hoc Arbitral Tribunal -
Florence
23
Lalaosa case (1995) Société Ytong v Lalaosa, Grenoble
16 June 1993, unreported but translated in English in
(1995) 14 J L & Comm 109 and abstracted as CLOUT
Case 25.
25
Adamfi Video (1992) Adamfi Video v. Alkotok Studiosa Kisszovetkezet
Hungary 24 March, 1992 Metropolitan Court
Available at:
http://cisgw3.law.pace.edu/cases/920324h1.html
27
BP Oil case (2003) BP Oil International Ltd. v. Empresa Estatal
Petroleos de Ecuador 332 F.3d 333,337(S.D.Texas
2003) Available at:
http://cisgw3.law.pace.edu/cases/030611u1.html
27
Bulletproof vest case Multi-Member Court of First Instance of Athens
4505/2009
Available at:
http://cisgw3.law.pace.edu/cases/094505gr.html
34
Fiberglass Materials
Case
Tribunal cantonal [Higher Cantonal Court] du Valais
C1 08 45
Available at:
http://cisgw3.law.pace.edu/cases/090128s1.html
35
Oberlandesgericht
Koblenz
Oberlandesgericht Koblenz, Germany
Case No: 2 U 580/96. Decided on: 11.09.1998
Available at:
http://www.unilex.info/case.cfm?id=300
49
G v. S case Tribunal Cantonal de Sion, Switzerland
Available at:
50
http://cisgw3.law.pace.edu/cases/980629s1.html
ARTICLES
Cited as Content Citing
Footnotes
Graves(2011) Jack M Graves ‘CISG Article 6 and Issues of Formation:
The Problem of Circularity’ Annals of the Faculty of Law
in Belgrade, Belgrade Law Review, University of
Belgrade, Year LIX, 2011, No. 3.
14
Drago &
Zoccolillo, Esq.
(2002)
Thomas J. Drago,Esq. and Alan F. Zoccolillo, ‘Be Explicit:
Drafting Choice of Law Clauses in International Sale of
Goods Contracts, Esq.’ Available at:
http://www.cisg.law.pace.edu/cisg/biblio/zoccolillo1.html
17
Holdsworth,
deKieffer &
Horgan (2001)
Judith L. Holdsworth, ‘Practical Applications of the
United Nations Convention on Contracts for the
International Sale of Goods (“CISG”), 2001’, DEKIEFFER
& HORGAN Available at:
http://www.cisg.law.pace.edu/cisg/biblio/holdsworth.html
19
CISG-AC
Opinion No. 16
(2014).
‘CISG-AC Opinion No. 16, Exclusion of the CISG under
Article 6’, Rapporteur: Doctor Lisa Spagnolo, Monash
University, Australia. Adopted by the CISG Advisory
Council following its 19th meeting, in Pretoria, South
20
Africa on 30 May 2014. Available at:
http://www.cisg.law.pace.edu/cisg/CISG-AC-op16.html
CISG
Explanatory Note
United Nations Convention on Contracts for the
International Sale of Goods (Vienna,1980) (CISG),
Explanatory Note. Available at:
http://www.uncitral.org/uncitral/en/uncitral_texts/sale_goo
ds/1980CISG.html
22, 28
Manz, Bappenr,
Witz and Selbhen
(1991)
Gerhard Manz, Susan Padmann-Reich Bappenr, Witz and
Selbhen ,‘Introduction of the UN Convention on
International Sale of Goods in Germany’ (Freiburg,
Germany/Brussels, Belgium) 19 Int'l Bus. Law. 300 1991
26
Callaghan(1994) James J. Callaghan ‘U.N. Convention On Contracts For
The International Sale Of Goods: Examining The Gap-
Filling Role Of CISG In Two French Decisions’
14 J.L. & Com. 183 1994-1995
27
Zeller (2006) Dr. Bruno Zeller ‘The Unidroit Principles Of Contract
Law; Is There Room For Their Inclusion Into Domestic
Contracts?’ 26 J.L. & Com. 115 2006-2007
29
Volken (1986) Paul Volken ‘The Vienna Convention:
Scope,Interpretation, and Gap-Filling,In International Sale
of Goods: Dubrovnik Lectures’ p. 19, 21 (Peter Sarcevc &
Paul Volken eds., 1986)
30
TABLE OF CONTENTS
ARGUMENTS ADVANCED ................................................................................................... 1
I. The tribunal has the jurisdiction to adjudicate on the claims presented before it. ............... 1
i. The Tribunal has the power to decide on its own jurisdiction. ............................. 1
ii. The dispute resolution clause reflects the intention of the parties to arbitrate. ..... 2
iii. The dispute resolution clause constitutes a valid and binding arbitration
agreement. ..................................................................................................................... 3
iv. The tribunal has the power to adjudicate with regard to all claims. .................. 4
v. The tribunal does not have the power to address the counterclaims of the
Respondent. ................................................................................................................... 4
II. The CISG governs the claims arising under SPA No.1 and SPA No.2. .............................. 5
i. The choice of law clause must expressly exclude application of the CISG .......... 6
ii. CISG is a part of the domestic law of the state. .................................................... 7
III. The Claimant is entitled to payment under SPA No.2. ........................................................ 8
i. The Claimant was not responsible for insuring the goods. ................................... 8
ii. The Claimant complied with the deadline for delivery of the prototype .............. 8
iii. The watchstraps were in conformity with SPA No.2. ....................................... 9
iv. The Claimant is entitled to payment for goods delivered. ............................... 12
REQUEST FOR RELIEF ........................................................................................................ 13
1
ARGUMENTS ADVANCED
I. THE TRIBUNAL HAS THE JURISDICTION TO ADJUDICATE ON THE CLAIMS PRESENTED
BEFORE IT.
The claims presented before this tribunal have been objected to by the Respondent on the
grounds of jurisdiction, in the first instance. Therefore, it becomes essential to prove that (i) The
tribunal has the power to decide on its own jurisdiction, (ii) The dispute resolution clause reflects
the intention of the parties to refer the matter to arbitration, (iii) The dispute resolution clause
constitutes a valid and binding arbitration agreement, (iv) The tribunal has the power to
adjudicate in the matter of all claims raised before it, (v) The tribunal cannot hear the matter of
the Respondent’s counterclaim.
i. The Tribunal has the power to decide on its own jurisdiction.
The question relates to whether the tribunal has the jurisdiction to hear the claims raised by the
Claimant. The applicable principle here is that of competence-competence which states that an
arbitral tribunal has the power to decide its own competence to hear a matter, as does this
tribunal.1 It is generally accepted in international commercial arbitration practice. It overcomes
an issue that could arise in the future where the tribunal finds the arbitration agreement to be
invalid prima facie and does not have the authority to make that finding in the first place.
1 Chap.5.4(c), REDFERN & HUNTER (1999); Arts.6(1), 6(3), CIETAC Rules; Art.41(1), ICSID
Convention; Art.21, UNCITRAL Rules; Article 6(2), ICC Rules.
2
The principle has been incorporated into the domestic laws of many countries,2international
adjudicating institutions,3 as well as case law.4 These clearly show that an arbitration tribunal has
the competence to decide the matter of its jurisdiction.
ii. The dispute resolution clause reflects the intention of the parties to arbitrate.
The validity of the arbitration agreement can be ascertained from the intention reflected in the
clause as arbitration is a consensual process. Language providing that a party “may” submit a
dispute to arbitration entails mandatory arbitration, otherwise it would render the clause
meaningless since parties could always voluntarily submit to arbitration. Therefore, the clause
does not provide a choice between arbitration and litigation, but between arbitration and doing
nothing at all which also implies that the agreement becomes binding once the option is
exercised. Provisions should not be interpreted in a way that renders them superfluous.5
Thus, arbitration is mandatory once demanded by either party even though the clause uses the
word “may” instead of “shall”.6 Since the option can be exercised by either party, the
Respondent has shown strong intention to submit disputes to arbitration and it is distinct from the
2 S.30, English Arbitration Act, 1996; S.2, Swedish Arbitration Act, 1999.
3Art.36(6), ICJ Statute; see supra note 1.
4 ARAMCO case at 117; Joc Oil Case; Texaco case.
5 JA Apparel case (2010); Reyes case (2012); MBIA case (2012); Dan Dong Dong Jin case
(2012).
6 Hirshenson case(2001); Mercury Constructioncase (1983); Maguire v. King (2005); Owens-
Brockway case (1996); Ziegler case (1982); Conax Florida case(2007).
3
mere mention of arbitration as an idea. Thus, the arbitration agreement reflects a valid consensus
to arbitrate.
In any case, exercise of the option of arbitration by the Claimant is sufficient to constitute a
binding arbitration agreement.
When a dispute resolution clause creates an option to arbitrate, exercisable by either party, once
the option is exercised, a binding arbitration agreement comes into existence.7 This is pursuant to
the intention shown by the parties to do the same with regard to disputes arising out of their
present contractual relationship. An analysis whereby notice will trigger the mutual agreement to
arbitrate fits better into the consensual scheme of arbitration than one which requires artificial
construction.8
iii. The dispute resolution clause constitutes a valid and binding arbitration agreement.
The clause provides the seat, venue, language and binding nature of arbitral award and this is
enough to constitute certainty. It is unreasonable to assume that despite all the effort made to
flesh out the arbitration clause, there is still ambiguity. Art.20(c) of the dispute resolution clause
allows for it to be interpreted as per the position of law in the State of New York according to
which, a contract cannot be deemed to be ambiguous or in dispute simply because parties do not
agree on its construction.9 The only ambiguity could be with regard to whether the parties are
7Bharat Engineering Corp case (1977); Canadian National Railway case(1999); WSG Nimbus
case (2002); NB Three Shipping case (2004).
8 South India Shipping case (1981).
9 Reyes case (2012); Corral case (2012); Convergent Wealth Advisors case (2012); Homeward
Residential case (2014).
4
excluded from referring payment disputes to litigation. This does not affect the operation of the
clause in constituting a valid agreement because it is certain that the clause becomes binding
once the option is exercised. Since there is no dispute regarding the certainty of the clause itself,
it constitutes a valid arbitration agreement.
In any case, the specific prevails over the general10
The specificity of Art.19(a) overrides the generality of 19(b) and even if the parties are entitled
to refer any dispute to litigation, 19(a) ensures that the parties can still refer payment disputes to
arbitration.
iv. The tribunal has the power to adjudicate with regard to all claims.
An arbitration agreement confers a mandate upon an arbitral tribunal to decide any and all
disputes that are within the ambit of that agreement. The claims presented before the tribunal are
with regard to money due to the Claimant as a result of the Respondent withholding payment for
goods delivered. This is clearly a “payment dispute” under the SPA No.2 and is arbitrable.
v. The tribunal does not have the power to address the counterclaims of the Respondent.
If institutional rules only state that a counter claim is allowed, as the CIETAC Rules do,
reference may be made to other institutional rules to determine the extent of a counter claim.
These provide that jurisdiction whenever it is based ‘on the same agreement to arbitrate’, or on
10 MBIA case (2012); Carolina Power & Light Co. case (1983).
5
the ‘same relationship’.11 The relief sought by the Respondent does not pertain to the present
contractual relationship between them and is thus outside the jurisdiction of the tribunal.
A counterclaim may be raised only if it falls within reach of the arbitration clause. This follows
from the basic principle that arbitral jurisdiction is based on the will of the parties, and that
arbitral tribunal may decide only on the issues which fall under the scope of the arbitration
clause.12 Here, intention is paramount and it is evident from the exchange of emails between the
parties that they terminated the contractual relationship set out in SPA No.1. Thus, the
Respondent’s counterclaim, which is based on the earlier transaction, does not fall under the
ambit of the arbitration agreement that confers power on the tribunal in the present matter.
II. THE CISG GOVERNS THE CLAIMS ARISING UNDER SPA NO.1 AND SPA NO.2.
The CISG governs both the agreements as Yanyu and Wulaba are parties to it, (i) The choice of
law clause must expressly exclude the application of the CISG and (ii) As CISG forms a part of
the domestic law of the Contracting States, it continues to be applicable notwithstanding the
clause.
11Art.23, FTCA Serbia, Art.15,PCA Croatia; Art.3(2), AAA Rules; Art.7(a),VAC Rules;
Art.19(1),Japan CAA Rules. Similarly, with regard to ICC arbitration, Derains &Schwartz,
(1998) at 72.
12REDFERN & HUNTER (2004), p.295; BORN (2001), p. 298; FOUCHARD (1999), p.1222.
6
i. The choice of law clause must expressly exclude application of the CISG
CISG allows the parties to completely or partially exclude the provisions of the Convention13
i.e., they may “opt out” of CISG.14 However, a standard choice of law clause that does not
mention CISG is insufficient15 to opt out of CISG merely because it specifies the law of a
particular jurisdiction to govern the contract.16 The choice of law provision must expressly
exclude application of the CISG17 i.e., being aware that CISG applies to the contract, the Parties
should intend to exclude it.18 This is because an express choice of law of a specific domestic law
of a Contracting State does not mean an implied exclusion.19
The clear intent to exclude can be inferred from an express exclusion of the CISG or the choice
of the law of a non-contracting State or the choice of an expressly specified domestic statute or
Code where that would otherwise be displaced by the CISG’s application.20 Mere specification
of the general law of a Contracting State does not exclude the application of the Convention.21As
13 Art.6, CISG.
14 Graves (2011).
15Ajax Tool Works case (2003).
16Easom Automation Systems case (2007).
17Drago & Zoccolillo, Esq. (2002).
18Atlarex case (2000).
19Holdsworth, deKieffer & Horgan (2001).
20CISG-AC Opinion No. 16 (2014).
21Assante Technologies case (2001).
7
certainty is essential in commercial exchanges22, in the absence of clear language indicating that
the parties intend to opt out of the CISG, it will continue to be applicable.23
The clause specifying the choice of governing law in this case states that the contract shall be
governed by the national law of Wulaba.24 No express exclusion of the CISG can be found in the
clause, thus making the CISG applicable to both the SPAs.
ii. CISG is a part of the domestic law of the state.
The CISG is a “self-executing treaty”25 implying that no additional legislation is required to be
enacted to enforce its provisions.26 On a signatory’s assent to the CISG, it automatically becomes
part of the domestic law of that State27 and its application prevails over other regulations that fall
within its scope.28 This is because it forms part of the municipal law of the State.29 All persons
residing in such a State can assert their rights or demand the fulfilment of another party’s duty by
referring directly to the treaty itself.30
22 CISG Explanatory Note.
23Società X v. Società Y (1994).
24 Art.20, SPA No.2.
25Lalaosa case (1995).
26 Manz, Bappenr, Witz and Selbhen(1991).
27Adamfi Video (1992), BP Oil case (2003), Callaghan(1994)
28 Supra note 22.
29Zeller (2006).
30Volken(1986).
8
Therefore, the exclusion in Art.20 of SPA No.2 is nullified with regard to the CISG.31 Hence, the
CISG governs both the agreements.
III. THE CLAIMANT IS ENTITLED TO PAYMENT UNDER SPA NO.2.
Assuming the counterclaims are admitted by the tribunal and the CISG applies, it is submitted
that (i)the responsibility for insurance was not on the Claimant, (ii)the deadline for delivery of
the prototypes was complied with, (iii)the watchstraps were in conformity with the contract, and
therefore, (iv)the claimant is entitled to payment for the goods delivered.
i. The Claimant was not responsible for insuring the goods.
In consideration of the concerns of the Respondent, Incoterms 2010 (DDP) was incorporated.
Consequently, it was responsible for all costs of customs formalities as well as all duties, taxes
and other charges and for cost of transit through any country prior to delivery.32 However, the
Claimant had no obligation to insure the goods as DDP does not include insurance.33
ii. The Claimant complied with the deadline for delivery of the prototype
The prototypes were delivered within the time stipulated by the contract. The initial deposit was
received on 31st July, 2014. This is the day of the triggering event. There is a general assumption
31Supra note 12.
32S.A6, DDP, Incoterms 2010.
33Id at S.A3.
9
that this is excluded in the calculation.34 The number of days is calculated after exclusion of the
day of performance of obligation by the other party.35 Since the payment was deposited on
31stJuly, 2014 the contractual deadline of fourteen days would therefore start from 1st August,
2014. The prototypes were delivered on 14th August, 2014 which was the fourteenth day and was
within the deadline. In a period of time fixed for delivery, the seller can, in principle, choose
when he wishes to deliver: on the first day, on the last day, or sometime in between.36
iii. The watchstraps were in conformity with SPA No.2.
The Respondent is withholding payment alleging that the goods were not in conformity with the
agreed terms of quality. However, (a)conformity with the prototype implies fulfilment of the
terms of the contract,(b)The Claimant has not committed any fundamental breach of the contract
by using tools to mass produce the final goods
a. Conformity with the prototype implies fulfilment of the contract.
The transaction between the Parties was a sale by sample. Therefore, the goods will be held to
not conform to the contract only if they do not possess qualities of the goods which the seller
held out as a sample or model.37 On 14th August 2014, the prototypes were manufactured and
sent for approval to the Respondent. First, the Respondent failed to raise an objection as to the
size of the watchstrap while approving the prototypes.38 Since the final goods were produced in
34Bulletproof Vest case.
35Fiber glass materials case.
36 Schwenzer(2010), p.552-553.
37Article 35(2)(c) CISG.
38 Claimant’s Ex. No.4.
10
conformity with the approved prototype, the Respondent is not entitled to refuse them on these
grounds. Further, the objection with regard to the quality of leather and method of production is
not justified. The contract required that the watchstraps be made of soft genuine Yanyu leather39
and the same was followed in producing the final goods. Leather is not consistent in terms of
grain or colour therefore it is inevitable that goods made of even the same roll of leather are
prone to differences.40 The existence of any discrepancy as permitted in various trade sectors,
that are usual in the particular trade concerned, is not to be regarded as constituting a lack of
conformity.41
b. The Claimant has not committed any fundamental breach of the contract by using tools to
mass produce the final goods
There is a distinction between the sampling stage and mass production. The prototypes were
handmade because it has been the Claimant’s policy to invest in necessary tooling for mass
production only after approval of the buyer in case of customized orders. This policy is not
inconsistent with business custom.42 The Respondent was aware of the history and reputation of
the Claimant.43 Even a preliminary research by a prospective buyer would reveal the common
customs of business and so the Claimant reasonably presumed that the Respondent ought to have
known the common policy adopted by the Claimant in manufacturing the goods.
39 Claimant’s Ex. No.6, Article 2(1)(a), SPA No.2.
40 Clarification No.26.
41 Supra Note 36 at p.573.
42 Clarification No.71.
43 Claimant’s Ex. No.1.
11
Further, the Respondent pressed for an expedient production of 5,000,000 watchstraps within 60
days. Given that it takes 14 days to hand stitch eight pieces, it would be impossible to
manufacture the entire consignment in 60 days without using conventional methods of mass
production. There was no request made by the Respondent that the watchstrap should look
handmade. Where doubt exists concerning a party’s intention, or the other party’s awareness of
that intention, statements should be interpreted according to the understanding of a reasonable
person in the circumstances.44 It wouldn’t be unreasonable to expect the Respondent, as a
prospective buyer, to understand the practical problems of mass production and the common
business practices involved.
In any case, the Respondent is estopped from alleging non-conformity.
The buyer should notify the seller of the alleged non-conformity within a “reasonable time” after
it “knew or ought to have known” of the non-conformity.45 In case the buyer wishes to reject the
goods, a rapid notice should be given to the seller to provide him an opportunity to remedy the
defect.46 A buyer who fails to notify the seller loses his right to all remedies relating to non-
conformity.47
The Respondent failed to notify the Claimant of the alleged non-conformity within a reasonable
time and thus forfeited its right to rely on non-conformity of the watchstraps in accordance with
Articles 38 and 39 of the CISG. The Respondent received the goods on 29th January, 2015 and
44Article 8(2) CISG; Honnold(2009) Pg. 118.
45Art.39(1), CISG.
46 Supra Note 36 at p.631.
47 Supra Note 44 at p.259.
12
the Respondent’s employees had checked some pieces in every carton when the consignment
arrived at the warehouse.48 The examination of the goods by the buyer must be made “within as
short a period as is practicable in the circumstances”. Examination of the goods should occur
within a week after delivery and notice of non-conformity should be given in another week at the
most.49A period of fourteen days for examination and notice is to be considered reasonable in the
absence of any specific circumstances.50 The Claimant was notified of the alleged non-
conformity only on 27th February, 2015.Examination of the watch straps ought not to have taken
as long as it did and by notifying the Claimant only after 30 days of the receipt of the
watchstraps the Respondent failed to provide notice in accordance with Article 39(1) of CISG.
iv. The Claimant is entitled to payment for goods delivered.
In the event a buyer defaults on certain obligations under the contract or the CISG convention,
the seller may exercise his rights provided in Articles 62-65 of CISG. Requiring specific
performance from the defaulting party flows from the principle of pacta sunt servanda and is an
accepted principle of contractual and international law.51 Payment of price is the most important
contractual obligation in practice.52 From the above submissions, it is evident that the Claimant is
not in breach of any of the terms and conditions of the contract. It is entitled to receive payments
for goods delivered the Respondent.
48Clarification No. 19.
49Oberlandesgericht Koblenz.
50G v. S case.
51 Supra Note 36 at p.876.
52 Id at p.869.
13
REQUEST FOR RELIEF
In light of the arguments advanced, the Claimant respectfully requests the Tribunal to find that:
1. The Tribunal has the jurisdiction to adjudicate on the claims presented before it.
2. The CISG governs the claims arising under SPA No.1 and SPA No.2.
3. The Claimant is entitled to payment under SPA No.2 amounting to USD 9,600,000 plus
interest and costs i.e. RMB 61,152,000.