Instructions to Bidders (ITB) July 2018 VOLUME – III - AWS
-
Upload
khangminh22 -
Category
Documents
-
view
0 -
download
0
Transcript of Instructions to Bidders (ITB) July 2018 VOLUME – III - AWS
MAHARASHTRA STATE ROAD DEVELOPMENT CORPORATION
LTD. (MSRDC) [GOVERNMENT OF MAHARASHTRA UNDERTAKING]
for
Construction of Access Controlled Nagpur-Mumbai Super Communication Expressway
(Maharashtra Samruddhi Mahamarg) in the State of Maharashtra on EPC mode
for Construction Package 16, from Km. 664.479 to Km. 701.479
(Section - Village Birwadi to Village Amne) in District Thane.
Instructions to Bidders (ITB)
July 2018
Corporate Office: Maharashtra State Road Development Corporation (MSRDC) Limited, Bandra Worli (Rajeev Gandhi) Sea Link Project Office,
K.C. Marg, Opposite Bandra Reclamation Bus Depot, Bandra (West), Mumbai-400050, Maharashtra State, INDIA
VOLUME – III
SCHEDULES
Request for Proposal (RFP)
MSRDC Schedules
Construction of Nagpur- Mumbai Super Communication Expressway (Package-16) from Km
664.479 to Km 701.479 on EPC mode 1
SCHEDULE-A
(See Clauses 2.1 and 8.1)
SITE OF THE PROJECT EXPRESSWAY
1 The Site
1.1 Site of the Six-Lane Project Expressway shall include the land, buildings, structures and
road works as described in Annex-I of this Schedule-A.
1.2 The dates of handing over the Right of Way to the Contractor are specified in Annex-II
of this Schedule-A.
1.3 An inventory of the Site including the land, buildings, structures, road works, trees and
any other immovable property on, or attached to, the Site shall be prepared jointly by
the Authority Representative and the Contractor, and such inventory shall form part of
the memorandum referred to in Clause 8.2.1 of this Agreement.
1.4 The alignment plans of the Project Highway are specified in Annex-III. The proposed
profile of the project highways shall be followed by the Contractor with minimum FRL as
indicated in the alignment plan. The Contractor, however, improves / upgrade the Road
Profile as indicated in Annex-III based on site/design requirement.
1.5 The status of the environment clearances obtained or awaited is given in Annex IV.
MSRDC Schedules
Construction of Nagpur- Mumbai Super Communication Expressway (Package-16) from Km
664.479 to Km 701.479 on EPC mode 2
Annex – I
(Schedule-A)
Site
1. Site
2 The site of the Six-Lane Project Expressway is forming part (package-16) of Nagpur- Mumbai
Super Communication Expressway commencing from Khutadi village at Km 664.479 and ends at
Amne village at Km 701.362 passing through green field area (refer Index Map given at
Appendix A-1) in the state of Maharashtra. The land, carriageway and structures comprising the
Site are described below:
2. Land
The Site of the Project Expressway comprises the land (sum total of land already in
possession and land to be possessed as described below:
Sr.
No. Village
Chainage (km) Total
Right of
Way
(ROW)
(m)
Remark From To
1 Ratandhle, Lahe, Birwadi,
Saralambe, Khutadi 664.379 666.642 120.0
2 Khutadi, Saralambe,
Kasgaon, Arjunali 666.642 668.877 60.0
3 Kasgaon, Shelwali 668.877 671.100 120.0
4 Shelwali, Sapgaon,
Khutghar 671.100 674.360 120.0
5 Khutghar, Andad, Hiv 674.360 678.110 90.0
6 Hiv 678.110 678.323 120.0
7 Hiv 678.323 678.884 90.0
8 Hiv, Ras, Shere, Shei,
Ambarje, Hal, Ushid, 678.884 694.260 120.0
MSRDC Schedules
Construction of Nagpur- Mumbai Super Communication Expressway (Package-16) from Km
664.479 to Km 701.479 on EPC mode 3
Sr.
No. Village
Chainage (km) Total
Right of
Way
(ROW)
(m)
Remark From To
Dabav, Phalegaon,
Nadgaon, Utane,
Pitambare Nagre
9 Nadgaon, Chinchwali,
Raye, Gurawali, Nimbavali 694.260 696.745 120.0
10 Nimbavali 696.745 697.654 120.0
11 Chiradpada 697.654 699.054 60.0
12 Chiradpada, Pise, Vashere,
Amne 698.504 701.362 120.0
3. Carriageway
The proposed Expressway is green field area where no carriageway exists.
4. Major Bridges
The Site includes the following Major Bridges:
Sr. No. Proposed Chainage (km) Length of Structure Remarks
Nil
5. Road over-bridges (ROB)/ Road under-bridges (RUB)
The Site includes the following ROB (road over railway line)/RUB (road under railway
line
Sr. No. Chainage (km) Length of Structure Remarks
Nil
6. Grade Separator
The Site includes the following grade separators:
Sr. No. Chainage (km) Length of Structure Remarks
Nil
MSRDC Schedules
Construction of Nagpur- Mumbai Super Communication Expressway (Package-16) from Km
664.479 to Km 701.479 on EPC mode 4
7. Minor Bridges
The Site includes the following minor bridges:
Sr. No. Chainage (km) Length of Structure Remarks
Nil
8. Railway Level Crossings
The Site includes the following railway level crossings:
Sr. No. Chainage (km) Remarks
Nil
9. Underpasses/ Overpasses (Vehicular/Non-vehicular)
The Site includes the following underpasses/Overpasses:
Sr. No. Chainage (km) Length of Structure Remarks
Nil
10. Culverts
The Site has the following culverts:
Sr. No. Chainage (km) Length of Structure Remarks
Nil
11. Bus Bays
The details of bus bays on the Site are as follows:
Sr. No. Chainage (km) Dimension Location (Left/Right)
Nil
12. Truck Bays
The details of truck lay byes are as follows:
Sr. No. Chainage (km) Dimension Location (Left/Right)
Nil
MSRDC Schedules
Construction of Nagpur- Mumbai Super Communication Expressway (Package-16) from Km
664.479 to Km 701.479 on EPC mode 5
13. Road Side Drains
The details of the roadside drains are as follows:
Sr. No. Chainage (km)
Length of Structure Dimension From To
Nil
14. Major Junctions
The details of major cross roads on the Site are as follows:
Sr. No. Road Type Chainage (km)
1 ODR 670.678
2 SH – 44 672.072
3 SH - 79 674.234
4 ODR 677.769
5 ODR 682.761
6 MDR 62 683.690
7 MDR 69 689.384
8 MDR 70 690.580
9 ODR 692.673
15. Minor Junctions
The details of minor cross roads on the Site are as follows:
Sr. No. Road Type Chainage (km)
1 Village Road 666.768
2 Village Road 690.123
3 Village Road 690.375
4 Village Road 694.115
5 Village Road 696.421
6 Village Road 698.931
MSRDC Schedules
Construction of Nagpur- Mumbai Super Communication Expressway (Package-16) from Km
664.479 to Km 701.479 on EPC mode 6
Annex II
(Schedule-A)
DATES FOR PROVIDING RIGHT OF WAY
The dates on which the Authority shall provide Right of Way to the Contractor on different
parts of the Site are stated below:
Sl. No From Km to Km (Design
Chainage)
Design
Length
(Km)
Width
(m)
Date of providing
ROW
1 2 3 4 5
(i) Full Right of Way
(full width) RoW for 90% of project length shall be handed over on Appointed Date.
(ii) Balance Right of
Way (width)
RoW for balance 10% of project length shall be handed over within 150
days from Appointed Date.
MSRDC Schedules
Construction of Nagpur- Mumbai Super Communication Expressway (Package-16) from Km
664.479 to Km 701.479 on EPC mode 7
Annex – III
(Schedule-A)
ALIGNMENT PLANS
The plan and profile is available on e-portal of MSRDC website.
MSRDC Schedules
Construction of Nagpur- Mumbai Super Communication Expressway (Package-16) from Km
664.479 to Km 701.479 on EPC mode 8
Annex - IV
(Schedule-A)
Environment Clearances
I. Tansa and Kalsubai Wildlife Sanctuary clearance is in process
II. Forest Clearance is in process
III. Environmental Clearance as per EIA Notification 2006 is in process.
MSRDC Schedules
Construction of Nagpur Mumbai Super Communication Expressway (Package 16) from km 664.479 to km 701.479 on EPC Mode 10
Appendix A-I
Index map of Project Expressway
MSRDC Schedules
Construction of Nagpur Mumbai Super Communication Expressway (Package 16) from km
664.479 to km 701.479 on EPC Mode 10
SCHEDULE – B
(See Clause 2.1)
DEVELOPMENT OF THE PROJECT EXPRESSWAY
1. Development of the Project Expressway
Development of the Project Expressway shall include design and construction of the six
lanes (divided carriageway) expressway as described in this Schedule-B and in
Schedule-C.
General description of the Project Expressway is given at Annex-I of this Schedule-B
2. Specifications and Standards
(i) The Project Expressway shall be designed and constructed in conformity with
the Specifications and Standards specified in Annex-I of Schedule-D.
(ii) The alignment plan of the Project Expressway is specified in Annex III of
Schedule A. The proposed profile of the Project Expressway shall be followed by
the Contractor with minimum FRL as indicated in alignment plan. The Contractor
however, improve\upgrade the road profile as indicated in Annex – III based on
site/design requirement.
MSRDC Schedules
Construction of Nagpur Mumbai Super Communication Expressway (Package 16) from km
664.479 to km 701.479 on EPC Mode 11
ANNEX - I
(Schedule-B)
Description of Project Expressway
The Project Expressway is forming part (package-16) of Nagpur - Mumbai Super
Communication Expressway and shall be Six Lane divided carriageway with fully access
controlled. It is commencing from Khutadi village at Km 664.479 and ends at Amne
village at Km 701.362 passing through Green Field area in the state of Maharashtra. The
design length of the project Expressway (package-16) is 36.883 km.
1. Width of Carriageway
Paved carriageway including paved shoulders and edge strips of Six lane Project
Expressway shall be 30 m (carriageway width – 2 x 11.25 m, paved shoulders - 2x 3.00
m and edge strip – 2 x 0.75 m) wide in entire stretch. The paved carriageway in the
approaches shall match with carriageway width of structures.
2. Geometric design and general features
2.1. General
Geometric design and general features of the Project Expressway shall be in accordance
with Section 2 of the Manual and Schedule D.
2.2. Design speed
The design speed shall be minimum design speed of 150 km/hr.
Acceleration and deceleration lengths proposed for entry/exit ramps on interchanges
shall be as per Schedule B.
2.3. Improvement of the existing road geometrics:
The Project Expressway follows new alignment through Green Field area in entire
stretch. There is no requirement of improving existing road.
2.4. Right of Way
Details of the Right of Way are given in Annex II of Schedule-A.
MSRDC Schedules
Construction of Nagpur Mumbai Super Communication Expressway (Package 16) from km
664.479 to km 701.479 on EPC Mode 12
2.5. Type of Shoulder
Type of shoulder will be as per Paragraph 2.6 of the Manual and Paragraph 2.10 of
Annexure-I of Schedule B.
2.6. Lateral and vertical clearances at underpasses
Lateral and vertical clearances at underpasses and provision of guardrails/crash barriers
shall be as per the Paragraph 2.10 of the Manual.
2.7. Lateral and vertical clearance at overpasses
Lateral and vertical clearances at over passes shall be as per Paragraph 2.11 of the
Manual.
2.8. Connecting Roads / Service roads
Service roads shall be constructed at the locations and of the lengths indicated below:
Sr. No. Chainage
Length (m) Width (m) Side From To
1 668.880 670.680 1800 5.5 LHS
2 668.880 670.680 1800 5.5 RHS
3 671.000 671.500 500 5.5 LHS
4 671.000 672.500 1000 5.5 RHS
5 674.300 677.900 3600 5.5 LHS
6 674.300 677.900 3600 5.5 RHS
7 678.930 680.380 1450 5.5 LHS
8 678.930 680.380 1450 5.5 RHS
9 680.920 686.000 5080 5.5 LHS
10 680.920 685.920 5000 5.5 RHS
11 687.550 689.410 1860 5.5 LHS
12 687.450 689.397 1947 5.5 RHS
13 690.120 695.430 5310 5.5 LHS
14 690.120 695.430 5310 5.5 RHS
15 695.650 696.820 1170 5.5 LHS
16 695.650 696.820 1170 5.5 RHS
17 698.520 698.930 410 5.5 LHS
18 698.520 698.930 410 5.5 RHS
Note: Length of service road /cart track given in above table excluding length of service
road /cart track across the project expressway for proper connectivity of cross roads on
either side of project expressway which shall be deemed to be included in the scope of
work.
MSRDC Schedules
Construction of Nagpur Mumbai Super Communication Expressway (Package 16) from km
664.479 to km 701.479 on EPC Mode 13
2.9. Grade separated structures
Grade separated structures shall be provided as per paragraph 2.13 of the Manual. The
requisite particulars are given below:
2.9.1. Flyover / Viaduct and Tunnel
A. Flyover / Viaduct shall be constructed as follow:
B. Tunnels shall be constructed as follows:
Sr.
No. Location
Start
(Km)
End
(Km) Length (M)
Type of
Structures
1 Khutadi 665.086 666.014 928 Bored Tunnel
2 Ambarje 686.652 687.115 463 Bored Tunnel
2.9.2. Interchanges
Interchanges shall be constructed as follow:
Detailed layouts of interchanges are given in Appendix B-I
Sr.
No
.
Location
Centre
Chainage
(Km)
Length
(m) Span (m)
Width
(m)
Rem
arks
1 Khutadi,
Saralambe 667.763 2260
2x65+10x80
+38x35 2X17.5
2 Hiv 677.632 245 7x35 2X25.0
3 Ras, Shere 680.647 595 17x35 2X17.5
4 Nimbavali,
Chiradpada 698.120 1400 40x35 2X17.5
5 Pise, vashere 700.167 175 5x35 2X17.5
MSRDC Schedules
Construction of Nagpur Mumbai Super Communication Expressway (Package 16) from km 664.479 to km 701.479 on EPC Mode 14
Sr. No.
Location/Chainage
Type of Interchange
Structure Chainage
(Km) Structure Type
Proposed span arrangement (Span Length x Clearance
ht.)
Total width(m)
Remarks
Main Expressway
1 Kusgaon/672.072
and 674.234
Elongated
Roundabout
671.500 RCC Box 3x3 53.50 Box culvert
672.580 RCC Box 3x3 100.84 Box culvert
674.445 RCC Box 3x3 113.52 Box culvert
670.910 PSC-I Girder 1 x35.0 17.50& 25.0 Minor Bridge
673.174 RCC Box 12x5.75 48.00 Vehicular under pass
673.633 RCC Box 12x5.75 52.00 Vehicular under pass
672.072 PSC-I Girder 34.20+34.20 16.00 Vehicular over pass
674.234 PSC-I Girder 2 x 30 17.5 Flyover
2 Hiv/678.200 Roundabout
678.150 PSC-I Girder 37.00+37.00 40.00 Vehicular over pass
678.300 PSC-I Girder 37.00+37.00 40.00 Vehicular over pass
MSRDC Schedules
Construction of Nagpur Mumbai Super Communication Expressway (Package 16) from km 664.479 to km 701.479 on EPC Mode 15
Sr. No.
Location/Chainage
Type of Interchange
Structure Chainage
(Km) Structure Type
Proposed span arrangement (Span Length x Clearance
ht.)
Total width(m)
Remarks
3 Amne/700.800 Directional
Ramp 2 RCC Solid slab 21.00+21.00 12.50 Terminal Point on Mumbai
Ramp 4 PSC-I
Girder+RCC
Solid slab
4x34.885+4x20+5x34.885 12.50 Terminal Point on Mumbai
MSRDC Schedules
Construction of Nagpur- Mumbai Super Communication Expressway (Package-14) from Km
623.379 to Km 636.479 on EPC Mode 16
2.9.3. VUP (Vehicular Underpass)
VUP shall be constructed as follow:
Sr. No.
Design Chainage
Category of Road
Start of Road
End of Road
Proposed span
arrangement
(Span Length x
Clearance ht.)
Width (m)
1 670.678 ODR Kasgaon Shelwali 12x5.75 52.00
2 683.680 MDR 62 Ambarje Shere 12x6.435 52.00
3 694.876
GAIL Utility Crossing
with portal frame
5x5.5 46.00
4 696.421 ODR 12x5.75 46.00
5 696.827 ODR 12x5.50 79.00
Note: The location and design of VUP for GAIL Utility crossing shall be done in consultation with concerned authorities.
2.9.4. Light Vehicular Underpasses (LVUP
Light Vehicular Underpasses (LVUP) shall be constructed as follow:
Sr. No. Design
Chainage
Category
of Road
Start of
Road
End of
Road
Proposed span
arrangement
(Span Length x
Clearance ht.)
Width
(m)
Nil
2.9.5. VOP (Vehicular Overpass)
VOP shall be constructed as follow;
Sr.
No
.
Design
Chainage
(km) Structure
Category of
Road
Proposed
Span
Arrangeme
nt(m)
Height
of Mid
Pier (m)
Widt
h (m)
1 681.772 FOB/VOP 18 Village Road 32.76+32.76 8.673 13.00
2 682.761 FOB/VOP 19 Village Road 32.70+32.70 16.085 13.00
3 689.388 VOP20 MDR 37.00+37.00 13.469 13.00
4 690.123 VOP21 Village Road 32.70+32.70 8.699 13.00
5 690.375 VOP22 Village Road 35.00+35.00 8.511 13.00
6 690.580 VOP23 MDR 52.50+52.50 30.630 13.00
MSRDC Schedules
Construction of Nagpur- Mumbai Super Communication Expressway (Package-14) from Km
623.379 to Km 636.479 on EPC Mode 17
Sr.
No
.
Design
Chainage
(km) Structure
Category of
Road
Proposed
Span
Arrangeme
nt(m)
Height
of Mid
Pier (m)
Widt
h (m)
7 690.866 FOB/VOP24 Village Road 43.00+43.00 17.858 13.00
8 692.673 VOP25 Village Road 32.76+32.76 8.640 13.00
9 698.931 VOP27 Village Road 40.00+40.00 11.631 13.00
2.9.6. Cattle and Pedestrian under pass
Cattle and pedestrian underpass shall be provided as per Paragraph 2.10 of the Manual
the requisite particulars are given below;
Sr. No.
Design
Chainage
(Km)
Category of
Road
Start
of
Road
End of
Road
Proposed
span
arrangement
(m)
Width
(m)
1 675.760 Cart track - - 7x3 45.00
2 676.602 Cart track - - 7x3 45.00
3 678.951 Cart track - - 7x6 57.653
4 680.020 Cart track - - 7x3 45.00
5 685.928 Cart track - - 7x6 65.78
6 691.935 Cart track - - 7x6 57.85
7 695.803 Cart track - - 7x6 64.90
2.9.7. Road over-bridges
Road over bridges (road over rail) shall be provided at the following locations:
Sr. No.
Design
Chainage
(Km)
District
Proposed
Structure
type
Proposed Length (m) Width
(m)
1 695.538 Thane Composite 48.525 2X17.5
Note: Construction of ROB shall be as per design of drawings approval by Railways;
however proposed GAD is enclosed herewith for reference
MSRDC Schedules
Construction of Nagpur- Mumbai Super Communication Expressway (Package-14) from Km
623.379 to Km 636.479 on EPC Mode 18
2.10. Typical cross-sections of the Project Expressway –
A. Applicable Typical Cross Sections are indicated in the Table below.
Sr. no. Start
Chainage (Km)
End Chainage
(Km)
Length (Km)
TCS no. Remarks
1 664.479 665.086 0.607 TCS 02
2 665.086 666.014 0.928 TCS 03
3 666.014 666.155 0.141 TCS 02
4 666.155 666.365 0.210 TCS 01
5 666.365 666.546 0.181 TCS 02
6 666.546 666.598 0.052 TCS 01
7 666.598 668.928 2.330 TCS 05 Viaduct – 2260m
8 668.928 670.892 1.964 TCS 01 VUP at 670.678
9 670.892 670.927 0.035 TCS 07 Minor Bridge – 35m
10 670.927 671.825 0.898 TCS 01 Box culvert at 671.500
11 671.825 672.543 0.718 TCS 02 VOP at 672.072
12 672.543 674.204 1.661 TCS 01
Box culvert at 672.580, VUP at 673.174, VUP at 673.633
13 674.204 674.264 0.060 TCS 06 Flyover – 60m
14 674.264 677.510 3.246 TCS 01
Box culvert at 674.445, PUP at 675.760, Box culvert at 676.345, PUP at 676.602, Box culvert at 677.020
15 677.510 677.755 0.245 TCS 05 Viaduct – 245m
16 677.755 677.818 0.063 TCS 01
17 677.818 678.878 1.060 TCS 02
18 678.878 679.220 0.342 TCS 01 PUP at 678.951
19 679.220 679.400 0.180 TCS 02
20 679.400 680.350 0.950 TCS 01 PUP at 680.020
MSRDC Schedules
Construction of Nagpur- Mumbai Super Communication Expressway (Package-14) from Km
623.379 to Km 636.479 on EPC Mode 19
Sr. no. Start
Chainage (Km)
End Chainage
(Km)
Length (Km)
TCS no. Remarks
21 680.350 680.945 0.595 TCS 05 Viaduct – 595m
22 680.945 681.005 0.060 TCS 01
23 681.005 681.188 0.183 TCS 02
24 681.188 681.270 0.082 TCS 01
25 681.270 681.607 0.337 TCS 01
26 681.607 681.623 0.016 TCS 02 Box culvert a 681.620
27 681.623 681.983 0.360 TCS 02 VOP at 681.772
28 681.983 682.644 0.661 TCS 01 Box culvert at 682.300
29 682.644 683.162 0.518 TCS 02 VOP at 682.761
30 683.162 683.232 0.070 TCS 01
31 683.232 683.263 0.031 TCS 02
32 683.263 683.755 0.492 TCS 01 VUP at 683.680
33 683.755 684.108 0.353 TCS 02
34 684.108 684.347 0.239 TCS 01 Box culvert at 684.235
35 684.347 684.578 0.231 TCS 02
36 684.578 685.738 1.160 TCS 01
Box culvert at 684.880, Box culvert at 685.280
37 685.738 685.807 0.069 TCS 02
38 685.807 686.470 0.663 TCS 01
PUP at 685.928, Box culvert 686.300
39 686.470 686.652 0.182 TCS 02
40 686.652 687.115 0.463 TCS 03
41 687.115 687.596 0.481 TCS 02
42 687.596 688.635 1.039 TCS 01 Box culvert at 688.300
43 688.635 689.560 0.925 TCS 02 VOP at 689.388
44 689.560 689.735 0.175 TCS 01 Box culvert at 689.680
45 689.735 691.150 1.415 TCS 02
VOP at 690.123, VOP at 690.375, VOP at
MSRDC Schedules
Construction of Nagpur- Mumbai Super Communication Expressway (Package-14) from Km
623.379 to Km 636.479 on EPC Mode 20
Sr. no. Start
Chainage (Km)
End Chainage
(Km)
Length (Km)
TCS no. Remarks
690.580, VOP at 690.866
46 691.150 692.660 1.510 TCS 01
Box culvert at 691.368, Box culvert 691.800, PUP at 691.935, Box culvert at 691.988, Box culvert at 692.333, Box culvert at 692.628
47 692.660 693.115 0.455 TCS 02 VOP at 692.673
48 693.115 693.125 0.010 TCS 01
49 693.125 693.190 0.065 TCS 02
50 693.190 693.845 0.655 TCS 01 Box culvert at 693.563
51 693.845 693.933 0.088 TCS 02
52 693.933 693.950 0.017 TCS 01
53 693.950 694.028 0.078 TCS 01
54 694.028 694.227 0.199 TCS 02
55 694.227 694.390 0.163 TCS 01
56 694.390 694.617 0.227 TCS 02
57 694.617 694.742 0.125 TCS 01
58 694.742 694.790 0.048 TCS 02
59 694.790 695.520 0.730 TCS 01 Box culvert at 695.115
60 695.520 695.567 0.047 TCS 08 ROB
61 695.567 696+700 2.087 TCS 01
PUP at 695.803, Box culvert at 696.082, VUP at 696.421,
62 696.700 697.420 0.720 TCS 09 Toll Plaza at 696.980, VUP at 696.827
63 697.420 698.820 1.400 TCS 05 Viaduct – 1400m
64 698.820 698.840 0.020 TCS 01
MSRDC Schedules
Construction of Nagpur- Mumbai Super Communication Expressway (Package-14) from Km
623.379 to Km 636.479 on EPC Mode 21
Sr. no. Start
Chainage (Km)
End Chainage
(Km)
Length (Km)
TCS no. Remarks
65 698.840 699.011 0.171 TCS 02 VOP at 698.931
66 699.011 699.140 0.129 TCS 01
67 699.140 699.560 0.420 TCS 02
68 699.560 700.080 0.520 TCS 01
69 700.080 700.255 0.175 TCS 05 Viaduct – 175m
70 700.255 701.000 0.745 TCS 01
B. Interchanges
Sr.
no.
Locati
on
Interc
hang
e
Ramps
From
(Km) To
(Km)
Lengt
h (m)
TCS Remar
ks
1 Kusgao
n
Elong
ated
Round
About
SH-44 0+000 2+900 2900 TCS 21
Detaile
d
layouts
of
interch
anges
are
given in
Append
ix B-I
Ramp 1 0+000 1+266 1266 TCS 12
Ramp 2 0+000 1+141 1141 TCS 12
Ramp 3 0+000 1+585 1585 TCS 12
Ramp 4 0+000 1+348 1348 TCS 12
Ramp 5 0+000 0+784 784 TCS 12
Ramp 6 0+000 0+651 651 TCS 12
Ramp 7 0+000 0+972 972 TCS 12
Ramp 8 0+000 1+005 1005 TCS 12
Ramp 9 0+000 0+997 997 TCS 12
Ramp 10 0+000 1+082 1082 TCS 12
Ramp 11 0+000 0+480 480 TCS 12
Ramp 12 0+000 0+512 512 TCS 12
SH-79 0+000 1+320 1320 TCS 21
Round
About 0+000 1+049 1049 TCS 19
2 Hiv-Ras Round
about
Ramp 1 0+000 0+744 744 TCS 12
Ramp 2
0+000 0+360 360 TCS 12
0+360 0+906 546 TCS 21
Ramp3
0+000 0+380 380 TCS 12
0+380 0+743 363 TCS 21
Round
About 0+000 0+399 399 TCS 19
3 Amne Directi
onal
Ramp1 0+000 1+232 1232
TCS 12 Ramp2 0+000 1+812 1812
Ramp3 0+000 1+241 1241
Ramp4 0+000 2+672 2672
MSRDC Schedules
Construction of Nagpur- Mumbai Super Communication Expressway (Package-14) from Km
623.379 to Km 636.479 on EPC Mode 22
3. Intersections and Grade Separators
All intersections and grade separators shall be as per Section 3 of the Manual. Existing
intersections which are deficient shall be improved to the prescribed standards.
Properly designed intersections shall be provided at the locations and of types and
features given in the tables below:
A. At-grade intersections
Major Intersections:
Sr. No. Chainage (km) Location Type of Junction
NIL
Minor Intersections:
Sr. No. Chainage (km) Location Existing Cross-road type
NIL
B. Grade separated intersection with / without ramps
The grade separated structures shall be constructed as specified in paragraph
2.9 of Annex-I of Schedule B.
MSRDC Schedules
Construction of Nagpur- Mumbai Super Communication Expressway (Package-14) from Km
623.379 to Km 636.479 on EPC Mode 23
4. Road embankment and cut section
Construction of new road embankment / cuttings shall conform to the standards and
specifications given in Section 4 of the Manual and the specified cross sectional details.
5. Pavement Design
Pavement design shall be carried out in accordance with section – 5 of the Manual.
5.1. Type of pavement
Rigid pavement shall be provided on entire project length except on service/
Connecting roads/ slip roads/ access roads where flexible pavement is to be provided.
5.2. Design requirements
Design requirement for the rigid pavement shall be in accordance with the Manual
subject to a minimum crust thickness of rigid pavement as given below:
Sr. No. Chainage (km) Thickness (mm)
1 Pavement Quality Concrete (PQC) 300
2 Dry Lean Concrete (DLC) 150
3 Granular Sub Base (GSB) 200
5.2.1. Design Period and strategy
Rigid pavement for new pavement shall be designed for a minimum design period of 30
years.
5.2.2. Design Traffic
Notwithstanding anything to the contrary contained in this Agreement or the Manual,
the Contractor shall design the pavement of main carriageway for minimum Design as
per the Manual. Pavement design of connecting / service road shall be done for
minimum design traffic of 10 MSA.
5.3. Reconstruction of Sections
Nil
6. Roadside drainage
Drainage system including surface and subsurface drains for the Project Expressway
shall be provided as per section 9 of the Manual.
Sr. No. Side Chainage Length
(m) Type
LHS RHS Start (Km) End (Km)
1
RHS 666050 666719 669 LINED
MSRDC Schedules
Construction of Nagpur- Mumbai Super Communication Expressway (Package-14) from Km
623.379 to Km 636.479 on EPC Mode 24
Sr. No. Side Chainage Length
(m) Type
LHS RHS Start (Km) End (Km)
2 LHS
666050 666680 630 LINED
3
RHS 668954 670919 1965 LINED
4 LHS
668954 670869 1915 LINED
5 RHS
670474 671059 585 EARTHEN
6
670940 671518 578 LINED
7 LHS
671540 672580 1040 EARTHEN
8
RHS 671540 672570 1030 EARTHEN
9 LHS
672590 674202 1612 EARTHEN
10 LHS
672590 674189 1599 EARTHEN
11
674280 674447 167 LINED
12
LHS
674300 674453 153 LINED
13
674450 676359 1909 EARTHEN
14
674470 676361 1891 LINED
15
676380 677052 672 EARTHEN
16
676390 677047 657 LINED
17 LHS
677050 677521 471 LINED
18 LHS LHS
677060 677521 461 LINED
19
677550 680376 2826 EARTHEN
20
677550 677830 280 LINED
21
LHS
677830 680402 2572 LINED
22
678900 680413 1513 EARTHEN
23
678920 680375 1455 LINED
24
680930 681619 689 EARTHEN
25 LHS
680940 681626 686 LINED
26 LHS
680940 681640 700 LINED
27 LHS
680950 681630 680 LINED
28 LHS
681030 681612 582 LINED
29 LHS
681260 681597 337 EARTHEN
30 LHS
681630 682020 390 EARTHEN
31 LHS
681630 682320 690 EARTHEN
32 LHS
681640 682050 410 EARTHEN
33 LHS
681640 682032 392 EARTHEN
34 LHS
682020 682302 282 EARTHEN
35
RHS 682050 682311 261 LINED
36
RHS
682320 682690 370 EARTHEN
37 682320 682900 580 LINED
38
RHS
682320 684273 1953 LINED
39 682340 684247 1907 EARTHEN
40 682690 683170 480 LINED
41 682700 683251 551 EARTHEN
MSRDC Schedules
Construction of Nagpur- Mumbai Super Communication Expressway (Package-14) from Km
623.379 to Km 636.479 on EPC Mode 25
Sr. No. Side Chainage Length
(m) Type
LHS RHS Start (Km) End (Km)
42 682750 683220 470 LINED
43
RHS 682900 683186 286 LINED
44
RHS 683170 683770 600 LINED
45
RHS 683186 683790 604 LINED
46
RHS 683770 683940 170 LINED
47
RHS 683780 684259 479 LINED
48
RHS 683790 683934 144 EARTHEN
49
RHS 683790 684050 260 EARTHEN
50
RHS 683940 684262 322 EARTHEN
51
RHS 684050 684266 216 EARTHEN
52
RHS 684250 684892 642 EARTHEN
53
RHS 684250 684513 263 EARTHEN
54
RHS 684270 685285 1015 EARTHEN
55
RHS 684270 684875 605 EARTHEN
56
RHS 684290 684883 593 EARTHEN
57 LHS
684880 685014 134 LINED
58 LHS
684890 684960 70 EARTHEN
59 LHS
684910 685270 360 EARTHEN
60
RHS 684920 685295 375 LINED
61
RHS 684960 685120 160 EARTHEN
62
RHS 685120 685278 158 EARTHEN
63 LHS
685280 686278 998 EARTHEN
64
RHS 685300 685342 42 EARTHEN
65
RHS 685300 686291 991 EARTHEN
66 LHS
685310 686342 1032 EARTHEN
67 LHS
685342 685448 106 EARTHEN
68
685448 685600 152 LINED
69 LHS
685600 685856 256 LINED
70
685640 686279 639 EARTHEN
71 LHS
685700 686325 625 LINED
72 RHS
687440 688330 890 EARTHEN
73
687440 687990 550 LINED
74 RHS
687440 687962 522 LINED
75
687962 688315 353 EARTHEN
76
RHS 687990 688330 340 EARTHEN
77 LHS
688340 689450 1110 LINED
78
LHS
688350 688620 270 EARTHEN
79
688600 689680 1080 LINED
80
688620 689714 1094 EARTHEN
81
RHS 688640 689716 1076 EARTHEN
MSRDC Schedules
Construction of Nagpur- Mumbai Super Communication Expressway (Package-14) from Km
623.379 to Km 636.479 on EPC Mode 26
Sr. No. Side Chainage Length
(m) Type
LHS RHS Start (Km) End (Km)
82
689450 689681 231 LINED
83 LHS
689705 689920 215 LINED
84
RHS 689710 691411 1701 LINED
85 LHS
689920 691816 1896 LINED
86
RHS 691390 691460 70 LINED
87 LHS
691460 691630 170 LINED
88
RHS 691630 691808 178 LINED
89 LHS
691830 692341 511 LINED
90
RHS 691830 692334 504 LINED
91 LHS
692340 692634 294 LINED
92
RHS 692350 692627 277 LINED
93 LHS
692640 693554 914 LINED
94
RHS 692650 693588 938 LINED
95 LHS
693580 694393 813 LINED
96
RHS 693580 694380 800 LINED
97 LHS
694580 695131 551
98
RHS 694610 695134 524
99 RHS
695150 695552 402 LINED
100
695150 695534 384 EARTHEN
101
RHS 695610 696110 500 EARTHEN
102
RHS 695610 696093 483 EARTHEN
103
RHS 696090 696689 599 EARTHEN
104 LHS
696110 696695 585 EARTHEN
105 RHS
698020 699562 1542 EARTHEN
106
698030 700010 1980 LINED
107
RHS 698040 699031 991 LINED
108
RHS 698090 700117 2027 LINED
109
RHS 698850 699566 716 EARTHEN
110
RHS 698870 699029 159 EARTHEN
111
RHS 700130 700982 852 EARTHEN
112
RHS 700130 700993 863 EARTHEN
113
RHS 700150 700992 842 EARTHEN
7. Design of Structures
7.1. General
7.1.1. All bridges, culverts and structures shall be designed and constructed in accordance
with section 6 of the Manual and shall conform to the cross-sectional features and
other details specified therein.
MSRDC Schedules
Construction of Nagpur- Mumbai Super Communication Expressway (Package-14) from Km
623.379 to Km 636.479 on EPC Mode 27
7.2. Culverts
7.2.1. Overall width of all culverts shall be provided as specified in Paragraph 2.10 of
Annexure-I of Schedule B and clause 6.3 of the Manual.
7.2.2. Reconstruction of existing culverts: Nil
7.2.3. Widening of existing culverts: Nil
7.2.4. New culverts shall be constructed as per particulars given in the table below:
Sr. No.
Design
Chainage
(Km)
Proposed
Structure type
Proposed span
arrangement
(Span Length x
Clearance ht.)
Width
(m)
1 676.345 Box Culvert 3x3 57.513
2 677.020 Box Culvert 3x3 57.947
3 681.620 Box Culvert 3x3 46.00
4 682.300 Box Culvert 3x3 46.00
5 684.235 Box Culvert 3x3 55.424
6 684.880 Box Culvert 3x3 58.335
7 685.280 Box Culvert 3x3 71.99
8 686.300 Box Culvert 3x3 69.711
9 688.300 Box Culvert 3x3 75.871
10 689.680 Box Culvert 3x3 46.00
11 691.368 Box Culvert 3x3 60.225
12 691.800 Box Culvert 3x3 54.957
13 691.988 Box Culvert 3x3 74.610
14 692.333 Box Culvert 3x3 105.769
15 692.628 Box Culvert 3x3 50.903
16 693.563 Box Culvert 3x3 99.914
17 695.115 Box Culvert 3x3 53.477
18 696.082 Box Culvert 3x3 117.42
7.2.5. New Box /Pipe Culverts shall be constructed on Service Road / Cart Track are given
below
Sr. No.
Design Chainage(k
m)
Proposed Structure type
Total length of pipe culvert(m)
Remarks
1 671.500 1.2 m φ Pipe culvert
12.125 Pipe culvert below RHS & LHS service road
MSRDC Schedules
Construction of Nagpur- Mumbai Super Communication Expressway (Package-14) from Km
623.379 to Km 636.479 on EPC Mode 28
Sr. No.
Design Chainage(k
m)
Proposed Structure type
Total length of pipe culvert(m)
Remarks
2 672.580 Box Culvert -- Refer drawing MSRDC-MPC-P-5-D-BC-GA-0011
3 674.445 Box Culvert -- Refer drawing MSRDC-MPC-P-5-D-BC-GA-0012
4 676.345 1.2 m φ Pipe culvert
23.79 Pipe culvert below RHS & LHS service road
5 677.020 1.2 m φ Pipe culvert
26.44 Pipe culvert below RHS & LHS service road
6 681.620 1.2 m φ Pipe culvert
57.287 Pipe culvert below RHS & LHS service road
7 682.300 1.2 m φ Pipe culvert
35.465 Pipe culvert below RHS & LHS service road
8 684.235 1.2 m φ Pipe culvert
23.79 Pipe culvert below RHS & LHS service road
9 684.880 1.2 m φ Pipe culvert
23.79 Pipe culvert below RHS & LHS service road
10 685.280 Box Culvert Refer drawing MSRDC-MPC-P-5-D-BC-GA-0012
11 691.368 1.2 m φ Pipe culvert
32.685 Pipe culvert below RHS & LHS service road
12 691.800 1.2 m φ Pipe culvert
23.79 Pipe culvert below RHS & LHS service road
13 692.628 1.2 m φ Pipe culvert
57.287 Pipe culvert below RHS & LHS service road
14 693.563 1.2 m φ Pipe culvert
18.27 Pipe culvert below RHS & LHS service road
15 695.115 1.2 m φ Pipe culvert
26.44 Pipe culvert below RHS & LHS service road
MSRDC Schedules
Construction of Nagpur- Mumbai Super Communication Expressway (Package-14) from Km
623.379 to Km 636.479 on EPC Mode 29
Sr. No.
Design Chainage(k
m)
Proposed Structure type
Total length of pipe culvert(m)
Remarks
16 696.082 1.2 m φ Pipe culvert
10.67 Pipe culvert below RHS & LHS service road
Cross culverts shall be provided in continuation with Main C/W cross culverts as per Appendix B-I
7.2.6. Repairs/replacements of railing/parapets, flooring and protection works of the existing
culverts shall be undertaken as follows: Nil
7.2.7. Flood protection works shall be as specified in the relevant IRC Codes and
Specifications
7.3. Bridges
7.3.1. Existing bridges to be re-constructed/widened: Nil
7.3.2. New bridges
New bridges at the following locations on the Project Expressway shall be constructed.
GADs for the new bridges are attached in the drawings folder.
A. New Major Bridges on Main Carriageway:
Sr. No. Design
Chainage Proposed Length (m)
Width (m)
NIL
B. New Major Bridges on Service Road:
New major bridges shall be constructed on service road as per particulars given in the
table below:
Sr. No. Design Chainage Proposed Length (m) Width
(m)
Nil
C. New Minor Bridges on Main Carriageway:
New minor bridges shall be constructed as per particulars given in the table below:
Sr. No. Design
Chainage Proposed Length (m)
Width (m)
D. New Minor Bridges on Service Road:
MSRDC Schedules
Construction of Nagpur- Mumbai Super Communication Expressway (Package-14) from Km
623.379 to Km 636.479 on EPC Mode 30
New minor bridges shall be constructed on service road as per particulars given in the
table below:
Sr. No. Design
Chainage Proposed Length (m)
Width (m)
NIL
7.3.3. The railings of existing bridges shall be replaced by crash barriers at the following
locations: Nil
7.3.4. Repairs/replacements of railing/parapets of the existing bridges shall be undertaken as
follows: Nil
7.3.5. Drainage system for bridge decks
An effective drainage system for bridge decks shall be provided as specified in Section 6
of the Manual.
7.3.6. Structures in marine environment: Nil
7.4. Rail-road bridges
Design, construction and detailing of ROB/RUB shall be as specified in Section 6 of the
Manual.
7.4.1. Road over-bridges
Road over bridges (road over rail) shall be provided at the following locations:
Sr. No. Design
Chainage District
Proposed Structure type
Proposed Length (m)
Width (m)
1 695.538 Thane ROB 1x48.525 2X17.5
Note: Construction of ROB shall be as per design of drawings approval by Railways,
however, proposed GAD is enclosed herewith for reference.
7.4.2. Road under bridges: Nil
7.5. Grade separated structures
The grade separated structures shall be provided at the locations and of the type and
length specified in paragraphs 2.9 and 3 of this Annex-I
7.6. Repair and Strengthening of Bridges and Structures: NIL
7.7. List of Major Bridges and Structures
MSRDC Schedules
Construction of Nagpur- Mumbai Super Communication Expressway (Package-14) from Km
623.379 to Km 636.479 on EPC Mode 31
Sr. No. Location
Nil
8. Retaining wall
The retaining wall shall be provided at following locations;
Sr.
No.
Start
Chainage(Km)
End
Chainage
(Km)
Total
Length (m)
Remarks
1 674.340 674.897 454.684 LHS - Drawing No. MSRDC-
MPC- P5- D- GN- RW- 0001
2 674.392 674.898 408.362 RHS - Drawing No. MSRDC-
MPC- P5- D- GN- RW- 0001
3 685.850 685.998 149.950 LHS - Drawing No. MSRDC-
MPC- P5- D- GN- RW- 0001
4 685.850 685.919 66.240 RHS - Drawing No. MSRDC-
MPC- P5- D- GN- RW- 0001
5 691.950 692.070 120.000
Both Sides - Drawing No.
MSRDC-MPC- P5- D- GN-
RW- 0001
6 692.235 692.415 180.000
Both Sides - Drawing No.
MSRDC-MPC- P5- D- GN-
RW- 0001
7 670880.2 670885.8 6.0
Both Sides -Drawing No.
MSRDC-MPC- P5- D- MN-
GA- 0003
8 670934.3 670940.1 6.0
Both Sides -Drawing No.
MSRDC-MPC- P5- D- MN-
GA- 0003
9 666575.7 666589 13.0
Both Sides -Drawing No.
MSRDC-MPC- P5- D- GN-
GA- 0079
10 668936.9 668940.6 4.0 Both Sides -Drawing No.
MSRDC Schedules
Construction of Nagpur- Mumbai Super Communication Expressway (Package-14) from Km
623.379 to Km 636.479 on EPC Mode 32
Sr.
No.
Start
Chainage(Km)
End
Chainage
(Km)
Total
Length (m)
Remarks
MSRDC-MPC- P5- D- GN-
GA- 0079
11 677488.8 677501.1 12.0
Both Sides -Drawing No.
MSRDC-MPC- P5- D- GN-
GA- 0069
12 677764 677776.7 13.0
Both Sides -Drawing No.
MSRDC-MPC- P5- D- GN-
GA- 0069
13 680328.1 680341.1 13.0
Both Sides -Drawing No.
MSRDC-MPC- P5- D- GN-
GA- 0068
14 680954 680967.1 13.0
Both Sides -Drawing No.
MSRDC-MPC- P5- D- GN-
GA- 0068
15 697398.5 697411 13.0
Both Sides -Drawing No.
MSRDC-MPC- P5- D- GN-
GA- 0076
16 700058.5 700071.1 13.0
Both Sides -Drawing No.
MSRDC-MPC- P5- D- GN-
GA- 0075
17 700264 700276.2 12.0
Both Sides -Drawing No.
MSRDC-MPC- P5- D- GN-
GA- 0075
18 695500.4 695511.7 11.0 Both Sides - MSRDC-MPC-
P5-D-RB-GA-0001
19 695575.3 695585.5 10.0 Both Sides - MSRDC-MPC-
P5-D-RB-GA-0001
MSRDC Schedules
Construction of Nagpur- Mumbai Super Communication Expressway (Package-14) from Km
623.379 to Km 636.479 on EPC Mode 33
9. Traffic control devices and road safety works
Traffic control devices and road safety works shall be provided in accordance with
Section 10 of the Manual.
Necessary Berms and soil stabilization, rock bolting etc shall be provided wherever
necessary and as per the manual.
9.1. Specifications of the reflecting sheeting
As specified in Paragraph 10.2.5 of the Manual.
9.2. Crash barriers detail is provided in the table below:
Sr. No.
Design Chainage in Km Length Side
Start End
1 666.100 666.140 40 LEFT
2 668.970 671.290 2320 LEFT
3 672.560 672.850 290 LEFT
4 673.020 675.010 1990 LEFT
5 675.050 675.360 310 LEFT
6 675.760 676.140 380 LEFT
7 676.180 677.810 1630 LEFT
8 678.870 678.960 90 LEFT
9 678.980 679.040 60 LEFT
10 679.520 679.560 40 LEFT
11 679.720 681.000 1280 LEFT
12 683.390 683.720 330 LEFT
13 684.240 684.300 60 LEFT
14 684.820 685.640 820 LEFT
15 685.820 686.290 470 LEFT
16 691.180 691.460 280 LEFT
17 691.620 692.500 880 LEFT
18 692.570 692.640 70 LEFT
19 693.240 693.810 570 LEFT
20 699.070 699.110 40 LEFT
21 671.500 671.530 30 RIGHT
22 672.550 675.260 2710 RIGHT
23 675.350 675.380 30 RIGHT
24 675.630 675.800 170 RIGHT
25 675.900 676.540 640 RIGHT
26 676.720 676.800 80 RIGHT
27 676.890 677.810 920 RIGHT
28 678.890 679.200 310 RIGHT
29 679.510 679.580 70 RIGHT
MSRDC Schedules
Construction of Nagpur- Mumbai Super Communication Expressway (Package-14) from Km
623.379 to Km 636.479 on EPC Mode 34
Sr. No.
Design Chainage in Km Length Side
Start End
30 679.730 679.800 70 RIGHT
31 679.930 680.970 1040 RIGHT
32 681.090 681.140 50 RIGHT
33 681.170 681.250 80 RIGHT
34 683.320 683.630 310 RIGHT
35 684.140 684.186 46 RIGHT
36 684.660 684.730 70 RIGHT
37 684.780 684.880 100 RIGHT
38 684.990 685.740 750 RIGHT
39 691.210 691.450 240 RIGHT
40 691.720 692.090 370 RIGHT
41 692.150 692.450 300 RIGHT
42 692.560 692.630 70 RIGHT
43 693.086 693.130 43 RIGHT
44 693.250 693.830 580 RIGHT
45 701.180 701.363 183 RIGHT
Note: Terminals at start and end of the safety barrier shall be provided at each location
in addition to the lengths in the table above. Crash barriers shall be provided in addition
to the list provided in Clause 9.2 above at locations warranted as per the manual.
10. Roadside furniture
Roadside furniture shall be provided in accordance with the provisions of section 10 of
the Manual.
Sr. No.
Project Facility Location Design
Requirements
Other Essential Details
1 Traffic Signs and Pavement Markings
Entire length As per Schedule D
2 Road Boundary Stones Entire length As per Schedule D
3 Kilometer and 200m stones Entire length As per Schedule D
4 Road side Delineators
Horizontal curves As per Schedule D
10.1. Overhead signs
Locations and size of overhead signs shall be as specified in the table given below;
Overhead signs shall be provided at project terminal and interchanges
Sr. No. Location (Km) Size Side
LXH in m
MSRDC Schedules
Construction of Nagpur- Mumbai Super Communication Expressway (Package-14) from Km
623.379 to Km 636.479 on EPC Mode 35
Sr. No. Location (Km) Size Side
LXH in m
1 669.500 5.55 X 5.235 LHS
2 670.100 11.25 X 3.8 LHS
3 670.200 7.5 X 3.8 LHS
4 675.200 7.5 X 3.8 RHS
5 675.400 11.25 X 3.8 RHS
6 675.800 5.55 X 5.235 LHS
7 675.900 5.55 X 5.235 RHS
8 676.800 5.55 X 5.236 LHS
9 677.900 5.55 X 5.237 RHS
10 677.300 11.25 X 3.8 LHS
11 677.600 7.5 X 3.8 LHS
12 679.000 7.5 X 3.8 RHS
13 679.200 11.25 X 3.8 RHS
14 679.700 5.55 X 5.235 RHS
15 680.200 5.55 X 5.236 RHS
16 691.800 5.55 X 5.237 LHS
17 692.800 5.55 X 5.237 LHS
18 693.300 11.25 X 3.8 LHS
19 693.800 7.5 X 3.8 LHS
20 695.300 7.5 X 3.9 RHS
21 695.700 11.25 X 3.8 RHS
22 696.200 5.55 X 5.237 RHS
23 696.700 5.55 X 5.237 RHS
24 700.500 5.55 X 4.00 LHS
11. Compulsory Afforestation
Deleted
12. Hazardous locations
Road Side safety barriers shall be provided at all locations of hazards such as high
embankment, road side obstacles, sharp curves, VUP and bridge approaches,
overpasses, ROB and any other locations identified in consultation with Independent
Engineer during the execution of the Project Expressway.
13. Change of Scope
The length of Structures and bridges specified herein above shall be treated as an
approximate assessment. The actual lengths as required on the basis of detailed
investigations shall be determined by the Contractor in accordance with the
Specifications and Standards. Any variations in the lengths specified in this Schedule-B
shall not constitute a Change of Scope, and except any variations in the length arising
MSRDC Schedules
Construction of Nagpur- Mumbai Super Communication Expressway (Package-14) from Km
623.379 to Km 636.479 on EPC Mode 36
out of a Change of Scope expressly undertaken in accordance with the provisions of
Article 13.
14. Rainwater Harvesting
The construction of rain water harvesting structure is mandatory in and around water
crisis area and structures shall be constructed at 1.0km interval on both side of the
carriageway. Which shall be planned and executed as per the requirement stated by
Ground Water Surveys Development Agency, Government of Maharashtra vide letter
number GSDA/DDN/TECH/2639/2017 dated 14 November 2017.
15. Innovative materials to be used in Trial stretch:
An innovative material to be used in Trial stretches of pavement to be finalized in
consultation with MSRDC and Authority Engineer.
Use of waste plastic in Road Construction
Location of use: Service Road
Material
Plastic confirming to Low Density Polyethylene (LDPE), High Density
Polyethylene (HDPE), PET and Polyurethane shall be used in pavement construction.
Warm Mix Asphalt
Location of use: Service Road
IRC: SP: 101-2014 “Interim Guidelines for Warm Mix Asphalt” shall be used along with
MORT&H specifications for construction.
16. Utilities:
Provisions for crossing utilities across Project Expressway and its locations shall be
finalized as per good industry practice and in consultation with Authority’s Engineer/
Authority.
17. Durability of structures
All structural concrete shall be provided with non-nitrite based migrating corrosion
inhibiting admixtures. The admixtures should protect both cathodic and anodic sides
and only admixtures recommended by MORTH/IRC shall be used. All exposed concrete
surfaces above ground shall be coated with anti-carbonation coating recommended by
MORTH/IRC. All bridge decks shall be provided with water proofing membrane.
MSRDC Schedules
Construction of Nagpur- Mumbai Super Communication Expressway (Package-14) from Km
623.379 to Km 636.479 on EPC Mode 37
18. Fencing
Fencing shall be provided all along the Project Expressway at 3.0 m inside the ROW
boundary and as shown in the schematic drawing and specifications as given in
Schedule D.
Schematic Drawing of Row Fencing/Wall Precast Panel (All dimensions are in mm)
Sketch – Elevation of Typical Fencing Wall
900
2400
200 - 300
3300 3300
65
100
600
Cross Section of Precast Panel
PANEL
PANEL
PANEL
PANEL
4 Nos. 3 mm Ø MS bars
MSRDC Schedules
Construction of Nagpur- Mumbai Super Communication Expressway (Package-16) from Km 664.479 to Km 701.479 on EPC Mode 38
MSRDC Schedules
Construction of Nagpur- Mumbai Super Communication Expressway (Package-16) from Km 664.479 to Km 701.479 on EPC Mode 39
MSRDC Schedules
Construction of Nagpur- Mumbai Super Communication Expressway (Package-16) from Km 664.479 to Km 701.479 on EPC Mode 40
MSRDC Schedules
Construction of Nagpur- Mumbai Super Communication Expressway (Package-16) from Km 664.479 to Km 701.479 on EPC Mode 41
MSRDC Schedules
Construction of Nagpur- Mumbai Super Communication Expressway (Package-16) from Km 664.479 to Km 701.479 on EPC Mode 42
MSRDC Schedules
Construction of Nagpur- Mumbai Super Communication Expressway (Package-16) from Km 664.479 to Km 701.479 on EPC Mode 43
MSRDC Schedules
Construction of Nagpur- Mumbai Super Communication Expressway (Package-16) from Km 664.479 to Km 701.479 on EPC Mode 44
MSRDC Schedules
Construction of Nagpur- Mumbai Super Communication Expressway (Package-16) from Km 664.479 to Km 701.479 on EPC Mode 45
MSRDC Schedules
Construction of Nagpur- Mumbai Super Communication Expressway (Package-16) from Km 664.479 to Km 701.479 on EPC Mode 46
MSRDC Schedules
Construction of Nagpur- Mumbai Super Communication Expressway (Package-16) from Km 664.479 to Km 701.479 on EPC Mode 47
MSRDC Schedules
Construction of Nagpur- Mumbai Super Communication Expressway (Package-16) from Km 664.479 to Km 701.479 on EPC Mode 48
MSRDC Schedules
Construction of Nagpur- Mumbai Super Communication Expressway (Package-16) from Km 664.479 to Km 701.479 on EPC Mode 49
MSRDC Schedules
Construction of Nagpur Mumbai Super Communication Expressway (Package 16) from km
664.479 to km 701.479 on EPC Mode 50
SCHEDULE – C
(See Clause 2.1)
PROJECT FACILITIES
1 Project Facilities
The Concessionaire shall construct the Project Facilities in accordance with the
provisions of this agreement. Such Project Facilities shall include:
a. Toll Plazas;
b. Roadside Furniture;
c. Street Lighting;
d. Landscaping And Tree Plantation;
e. Service Areas (Way Side Amenities)
f. Emergency Medical Aid Posts;
g. Vehicle Rescue Posts;
h. Highway Patrol Unit
i. Tunnel Facilities
2 Project Facilities for Six-Laning
Project Facilities forming part of expressway and to be completed on or before the
Project Completion Date have been described in Annex-I of this Schedule-C.
MSRDC Schedules
Construction of Nagpur Mumbai Super Communication Expressway (Package 16) from km
664.479 to km 701.479 on EPC Mode 51
3 Utilities
One utility duct of 2m x 2m shall be provided at the rate on 1 no per kilometer where
ever necessary. The location of utility ducts shall be identified and certified by the
Authority’s Engineer. Provisions for crossing utilities across Project Expressway and its
locations shall be finalised as per good industry practice and in consultation with
Authority’s Engineer/Authority. Number of utility ducts to be provided in project length
shall not be less than 5 Nos. Refer Drawing Volume IX for structural design details.
Note: In Case of any discrepancy in numbers or location of any of the project facilities
mentioned in this Schedule C, shall be provided in consultation with the Authority’s
Engineer as per Site/Design requirement.
MSRDC Schedules
Construction of Nagpur Mumbai Super Communication Expressway (Package 16) from km
664.479 to km 701.479 on EPC Mode 52
Annex - I
(Schedule-C)
1 Project Facilities
The Concessionaire shall construct the Project Facilities described in this Annex-I to
form part of the Project. The Project Facilities shall include:
a. Toll Plazas;
b. Roadside Furniture;
c. Street Lighting;
d. Landscaping And Tree Plantation;
e. Service Areas;
f. Emergency Medical Aid Posts;
g. Vehicle Rescue Posts;
h. Highway Patrol Unit
i. Tunnel Facilities
2 Description of Project Facilities
Each of the Project Facilities is briefly described below:
(a) Toll Plazas
The location of Toll Plazas is as under:
Sr. No. Location of Toll Plaza at Km
1
Toll plazas (8 no’s- 1 for each ramp) shall be provided on
interchange 3 at Ramp 1 Ch. 0+675 (TCS -14)Ramp 2 Ch.
0+567(TCS -14) ramp 3 Ch. 0+026 (TCS -14)ramp 4 Ch. 0+850 (TCS
-14)Ramp 7 Ch. 0+480 (TCS -14)Ramp 8 Ch. 0+548 (TCS -14)Ramp
9 Ch. 0+480 (TCS -14)Ramp 10 Ch. 0+510 (TCS -14)Sapgaon as
specified in Schedule B
MSRDC Schedules
Construction of Nagpur Mumbai Super Communication Expressway (Package 16) from km
664.479 to km 701.479 on EPC Mode 53
2
Toll Plaza (4 No’s- 1 for each ramp) shall be provided on
interchange 4 at Ramp 1 Ch. 0+160 (TCS -24)Ramp 2 Ch.
0+583(TCS -24) Hiv-Ras as specified in Schedule B
3 Toll Plaza at Km Ch. 697.000 (TCS -09)on Main Carriageway of the
Expressway as specified in Schedule B
Toll Plaza shall be provided in accordance with the Manual and Standards as referred in
Schedule-D.
(b) Road side Furniture
Road side furniture shall be provided in accordance with Section 13 of the Manual. The
Concrete / Metal Crash Barriers shall be provided in accordance with the Manual.
The provision of road side furniture shall be finalised as per the Manual and in consultation
with the Authority Engineer.
(i) Traffic Signs and Pavement Markings
Traffic signs and pavement markings shall include roadside signs, overhead signs as
per relevant IRC standard including; curb mounted signs and road markings along
the Project Expressway. The design and marking for the Project Expressway shall be
as per the design standard indicated in Schedule-D and the location for various
treatments shall be finalised in consultation with the Authority Engineer. Adequate
Number of Cat’s eyes reflector and delineators demarcating the edge lines, lane
markings and junctions shall be provided to ensure safety of pedestrians and
traffic.
Traffic signs for the Tunnel locations include Variable Messages Signs inside the
Tunnel, traffic lights above each lane at entry portal end and inside.
(ii) The cat’s eyes or road studs shall be provided to improve the visibility in night-time
and wet-weather conditions. These shall be prismatic retro-reflective type,
conforming to ASTM D4280.
(iii) Concrete Crash Barrier, Metal beam crash barrier, Separators (MS Railing)/Wire
rope barrier as per the Manual
(iv) Boundary fencing for the entire length of the Expressway on both sides (Chain link
fencing)
(v) Traffic Safety Devices, as required
(vi) Boundary Stones
MSRDC Schedules
Construction of Nagpur Mumbai Super Communication Expressway (Package 16) from km
664.479 to km 701.479 on EPC Mode 54
(vii) Hectometer / Kilometer Stones
(viii) Traffic Blinker Signals (LED) at intersections
(ix) Any other item given in Manual
(c) Street Lighting
Street lighting shall be provided in accordance with the Manual of Specifications and
Standards as referred in Schedule-D but not limited to, the following:
1. Toll Plaza areas
2. Service areas
3. Top and underside of grade separated structures including flyovers as well as
underpasses
4. All service roads
5. Approaches to the Tunnel shall be provided in accordance with Section 12.3 of
the Manual
6. Inside Tunnels as per the Section 14.8 of the Schedule-D
(d) Landscaping and Plantation
Landscaping of the highway shall be provided as per provisions of Manual
(e) Service /Rest Area:
Sr. No. Location (Design Chainage ) Area (Hec) Remark
Nil
Note: In case of any discrepancy in numbers or location of any of the project facilities
mentioned in this Annex-I, the Authority's Engineer shall finalize the number/location of
these facilities as per site requirement.
(f) Emergency Medical Aid Posts
These services shall include setting up medical aid posts by the Concessionaire.
The Concessionaire shall provide ambulance(s) at the Toll Plaza locations manned by at
least two trained and certified paramedics so that the response time is not more than
20 minutes of call. Each ambulance shall be equipped with first aid, life saving medical
services and support system implements for transporting the victims to the nearest
trauma care hospitals, and providing emergency medical aid during transportation of
victims from accident site to the nearest trauma care hospital. It shall also be fitted with
MSRDC Schedules
Construction of Nagpur Mumbai Super Communication Expressway (Package 16) from km
664.479 to km 701.479 on EPC Mode 55
a GPS based Vehicle Tracking System to monitor its movement on 24 hrs x 7 days of a
week basis.
The vehicle shall be Matador Vani Swaraj Mazda Tempo Traveler or equivalent
of white colour with the provision of two stretchers, fitted with rotating light for easy
recognition, with control center helpline numbers painted prominently on all sides. The
ambulance is required to have the following medicines and equipments and also the
paramedical staff:
A) General Ambulance
Folding Doctor Seat with Belt with adequate height in relation to the stretcher,
Antistatic , water proof ply board vinyl flooring, Channel, Locking system for rolling
stretcher, High intensity blinkers/light barlsiren / beacon, Electronic siren with Public
Addressing System, Internal lighting with three spot light embedded in ceiling, AC/DC
connection and outlet points, Wash basin with Stainless Steel Tank, 58 Trash bin
Cabinet integrated with interiors , Head racks and cupboard, Attendant seat with seat
belt to double as second stretcher for stable patients, Provision for communication
system where the location of ambulance can be located, Provision for fog light on
sides, Cool/Warm boxes, Provision of Fire Extinguishers, Handheld Spotlight, Inverter
with the facility re-charging from 220V AC and Vehicle's alternative, Oxygen delivery
system comprising of Cylinder Trolley, pressure tubing with regulators, Roof mounted
Air-conditioner with appropriate cooling capacity with additional blower for Patient
Cabin, Extrication equipment and Good Suspension to cater for smooth transportation.
B) Basic Life Support System
Automatic loading stretcher, Scoop stretcher, Folding stretcher, Spine board full,
Vacuum splint kit/foldable splints, C-Collars, Oxygen Cylinder with accessories
mounted/with manifold and pressure indicators, Oxygen Cylinder (aluminum portable),
BP Instruments (Wall mounted-Aneroid), Stethoscope, Automatic defibrillator,
Resuscitation bag (ambu bag, laryngoscope, airways and masks of different size
including pediatric). Manual foot operated suction pump. I. V. Fluid and I.V. Sets,
Tourniquet, First Aid Box (Dressing material/ Antiseptic lotion/Analgesic etc.),
Linen/Blanket, Laryngeal mask airway of all sizes.
C) The following paramedical staff are required with proper uniform and name of the
person written on the uniform:
i. Trained Paramedical Staff 1
ii. Nursing staff with knowledge of first aid 1
MSRDC Schedules
Construction of Nagpur Mumbai Super Communication Expressway (Package 16) from km
664.479 to km 701.479 on EPC Mode 56
iii. Driver for ambulance 1
(g) Vehicle rescue posts
The Concessionaire shall provide a carne of adequate capacity (minimum 30
MT) at each Toll Plaza location (s) with all necessary equipment so that it can reach the
site of the incident within 30 minutes of call and clear the disabled/ accidented vehicles.
If shall also be fitted with a GPS based Vehicle Tracking system to monitor its movement
on 24 hours x 7 days of a week basis.
(h) Highway Patrol Unit(s)
The Concessionaire shall establish and operate Highway Patrol Unit(s) at the Toll
Plaza Locations, which shall continuously patrol the highway in a stretch not exceeding
50 km and shall remain in contact with the Control Room on a real time basis. The
patrol shall render assistance to users in distress and disabled vehicles through own
intervention or by calling for assistance from Control Room, Crane operators or
ambulance as required. The patrol shall promptly clear the road of any obstruction.
Where the obstructions take time to be cleared, the section shall be cordoned off by
placing traffic cones, which shall be illuminated during night. The patrol vehicle shall be
large enough for seating atleast four personnel besides the driver and space to carry
essential traffic and incidence management and safety tools. It shall also have a light on
its top and a siren on board. It shall also be filled with a GPS based Vehicle Tracking
System to monitor its movement on 24 hrs x 7 days of a week basis.
Each Patrol Vehicle should carry the following
equipment:
a) Fire extinguisher (1 no.)
b) Gas culler with protective glass (2 nos.)
c) Liquid container (2 nos.), Water container with fresh water (1 no.) and Funnel.
d) Rubber Gloves, Leather Gloves (1 pair each)
e) Brooms one hard bristle, other soft (2 nos.)
f) Gum boot (4 pairs), Rain coat (4 pairs), Blanket (1 no.)
g) Torch light (4 no.), Spare Batterie, Flashing light (1 nos.)
h) Hydraulic jack, towing chain, Animal hook, rope.
i) Tool set (with standard set of spanners, pliers, hammers etc.), shovels.
j) Digital Camera, measuring tape.
k) Paper pad, Forms, pens/pencils, folders.
MSRDC Schedules
Construction of Nagpur Mumbai Super Communication Expressway (Package 16) from km
664.479 to km 701.479 on EPC Mode 57
l) First Aid kit, Rain Coat, water proof sheets, stretchers (2 nos.)
m) List of Hospitals in the area.
Each vehicle should also carry the following Traffic Management Equipment,
(used/worn out items shall be replaced forthwith with new ones)
a) Sign boards- "Accident ahead"- 3 nos., "Lane merging"- 3 nos., "Direction Arrows"-
3 nos., "Speed Limit" (80/60/40)- 3 nos., "Keep left/right"- 2 nos. (all signs 1200
mm size and of retro-reflective type (micro prismatic cube comer).
b) Sign Stand set (one for triangular and other for circular sign)-6 sets.
c) Flags, whistle, reflective hand signal.
d) Traffic cones 500 mm size with solar bulb mounted on top 20 nos.
e) Barricades-4 nos. reflective type (100 m), tape , stands, flags of 600 mm by 600
mm made of good red cloth secured to a staff at 1 m length, paddles all east 600
mm wide and provided with rigid handle with markings SLOW , STOP.
f) Reflective jackets - 12 nos .
As a minimum, each patrol vehicle should carry sufficient communication equipment
to render its staff capable of direct communication with the Control Room.
Manpower:
The team which is to be deployed with each patrol vehicle, needs adequate training
for their tasks, especially in first aid, vehicle maintenance and minor repairs. The
Concessionaire must employ sufficient manpower to work in shifts for each patrol
vehicle. Typical staffing shall be: ·
a) Route Patrol ln charge
b) Route Patrol Assistant
c) Driver, with knowledge of vehicle repairs
(i) Tunnel facilities
The Contractor is required to design, install, operate and maintain Tunnel
Facilities as part of project facilities which are in addition to the Highway Traffic
management System specified elsewhere in the Manual.
The components to be deployed shall inter alia include:
(A) Video Surveillance System (CCTV PTZ Dome/ Fixed Camera)
(B) Video Incidence Detection System
(C) Emergency Roadside Telephones
(D) Variable Messages Signs
MSRDC Schedules
Construction of Nagpur Mumbai Super Communication Expressway (Package 16) from km
664.479 to km 701.479 on EPC Mode 58
(E) Meteorological Sensors inside and outside of the Tunnel
(F) Tunnel Operation and Maintenance Centers on each end of Tunnels (Total 2
Numbers) equipped with Integrated Supervisory Control and Data Acquisition
(SCADA) Control System with Anti-Hacking provisions and conforming to the
section 14 of the Manual and Schedule -D.
(G) Communication System
(H) Leaky Feeder Cable for mobile signals
(I) Fire Fighting System
(J) Tunnel Ventilation
(K) Over Head Maintenance passage with access arrangement from footpath at
every 100m
(L) Power supplies from 2 alternative sources including substation supported
with back up to facilitate 24x7 operation and maintenance of Tunnel and
control center. Back up shall be provided by Uninterrupted Power Supply
(UPS) and Diesel Generators of adequate capacity with storage of Fuel (80%
of peak load for two hours) shall be provided at each Tunnel operation and
control center.
(M) Linear Heat Detection
3. Utilities
Provision of accommodating utilities has been made over as well as underground
within utility corridor on either side of the Project Highway.
4. Rainwater Harvesting
As per Ministry of Environment and Forests Notification, New Delhi dated 14.01.1997
(as amended on 13.01.1998, 05.01.1999 & 6.11.2000), the construction of Rain water,
harvesting structure is mandatory in and around Water Crisis area, notified by the
Central Ground Water Board.
MSRDC Schedules
Construction of Nagpur Mumbai Super Communication Expressway (Package 16) from km
656.479 to km 701.479 on EPC Mode 59
SCHEDULE – D
(See Clause 2.1)
SPECIFICATIONS AND STANDARDS
1. Construction
The Contractor shall comply with the Specifications and Standards set forth in Annex-I
of this Schedule-D for construction of the six Lane Project Highway.
1.1 Design Standards
The Project Highway including Project Facilities shall conform to design requirements
set out in the following documents:
The Contractor shall comply with the Specifications and Standards set forth in Annex-I
of this Schedule-D for construction of the Project Highway.
MSRDC Schedules
Construction of Nagpur Mumbai Super Communication Expressway (Package 16) from km
656.479 to km 701.479 on EPC Mode 60
Annex - I (Schedule-D)
SPECIFICATIONS AND STANDARDS FOR EXPRESSWAYS
1. Specifications and Standards
All Materials, works and construction operations shall conform to the Manual of
Specifications and Standards for Expressways (IRC: SP: 99-2013) published by IRC
(referred to as “Manual” in Schedules) and MORTH Specifications for Road and Bridge
Works.
Where the specification for a work is not given, Good Industry Practice shall be adopted
to the satisfaction of the Authority’s Engineer.
2. Deviations from the Specifications and Standards
2.1 The terms "Contractor", "Independent Engineer" and "Concession Agreement" used in
the Manual shall be deemed to be substituted by the terms "Contractor", "Authority's
Engineer" and "Agreement" respectively.
2.2 Notwithstanding anything to the contrary contained in the aforesaid Manual, the
following Specifications and Standards shall apply to the Project Highway, and for
purposes of this Agreement, the aforesaid Manual shall be deemed to be amended to
the extent set forth below:
S. No.
Clause
referred in
Manual
Detail of Item
Modified Provision
1 2.2.1 Design Speed
Design speed adopted for entire project is 150kmph
2 2.3.3
No service roads shall be provided within the ROW of the Expressway
Service roads shall be provided as per Plan and Profile throughout the Expressway
2 2.9.3 Desirable Speed 120 Kmph 150 Kmph
MSRDC Schedules
Construction of Nagpur Mumbai Super Communication Expressway (Package 16) from km
656.479 to km 701.479 on EPC Mode 61
and minimum Radii
Absolute Minimum Radius
670 m 1050 m
Desirable Minimum radius
1000 m 1500 m
3 2.9.3 Sight distances
Speed 120 Kmph 150 Kmph
Safe Stopping sight distance
250 m 360 m
desirable minimum sight distance
500 m 720 m
4
5.7.5
IRC
SP
23
Minimum K value for vertical curve for SSD
100 Kmph 120 Kmph 150 Kmph
73.6 137 295
5 10.10 Fencing As shown in Schedule B (RC Panel with Barbed
wire)
In addition to clause 1.4 of Manual following provision shall be followed:
List of other Acceptable Codes, Standards, Guidelines and Technical Specifications.
i) Road Traffic and Work Zone Safety Manual published NHAI
ii) Quality Assurance Manual published NHAI
iii) Draft Green Highway Project issued by MoRTH
2.3 Modified highway geometric desıgn parameters -
The Manual provides the required guidelines for expressways of design speed 120kmph
in plain and 100 kmph in rolling terrain. However, the design speed of Nagpur-Mumbai
Super Communication Expressway is expected to be 150kmph. ıt would require certain
deviations from the Manual specified design parameters to accommodate the higher
design speed. These deviations are discussed as follows:
The Manual Clause 2.2 Design Speed:
The Expressway should be designed for 150 kmph in plain and rolling terrain. However,
for hilly/mountainous terrain, lower design speed consistent with the topography may
be considered with prior approval. Adequate signage and other traffic engineering
MSRDC Schedules
Construction of Nagpur Mumbai Super Communication Expressway (Package 16) from km
656.479 to km 701.479 on EPC Mode 62
measures should be adopted at the transition sections to make road users aware of the
change.
IRC: SP: 99-2013 Clause 2. 5. 3 Edge Strip:
There is no deviation in the width and construction specification of the edge strip.
However, additional 1.0 m to 1.25 m stabilized granular shoulder may be considered on
the median side for safe stoppage of vehicles travelling in the right most lane during
emergency.
The Manual Clause 2.5.4 Median Transition
In addition to the details provided in the Manual, sections with different median widths
should have harmonious transition. A parabolic transition is preferred over the linear
transition. The transition rate of 1 in 75 may be adopted for the purpose. It may be
developed using the equations given below:
Where,
T is total desired transition in width of median (m),
R is transition rate (i. e., 1 in 75),
x is the interval along length of road (say, every 5 m) and varies from 0 to T/R (m).
Tx is the transition at x m interval.
The Manual Clause 2. 9. 2: Horizontal Alignment
In addition to the details provided in the Manual, following particulars may be adopted:
Short straight sections (typically less than 400m) between two curve sections in the
same direction shall be avoided. It would help to mitigate the effect of broken back
curve configuration.
Maximum length of straight or tangent section is recommended to be 2500 m. It
would help to break monotony in driving.
MSRDC Schedules
Construction of Nagpur Mumbai Super Communication Expressway (Package 16) from km
656.479 to km 701.479 on EPC Mode 63
Alignments with larger transition and circular curves flanked by longer straight or
tangent section on either side of the curve section should be preferred while
developing the alignment.
The Manual Clause 2, 9. 2. 3: Radii of horizontal curves
For design speed of 150 kmph, the desirable minimum radius shall be 2000 m, and
absolute minimum radius in unavoidable circumstances shall be 1050 m, The
minimum radius shall be measured for the centre of innermost lane of the
carriageway.
Further, horizontal curves should not be too short,
The Manual Clause 2.9,2.4: Transition curves
For design speed of 150 kmph, the minimum transition curve length should be 180
m.
The transition curve shall be equally distributed between tangent and curved
section.
The Manual Clause 2.9.3.1: Safe stopping sight distance
The table below (Table 1) provides the safe stopping sight distance and desirable
minimum sight distance (i.e., Intermediate sight distance) for various downward
gradients. Sight distances for 0% gradient maybe adopted for upward gradients.
Table 1: Safe stopping sight distance and desirable minimum sight distance
Gradient 0% -0.5% -1.0% -1.5% -2.0%
Safe Stopping Sight Distance (m 360 362 365 370 375
Desirable Minimum Sight Distance
(m)
(Intermediate sight distance)
720 725 730 740 750
The Manual Clause 2.9.3.2: Decision sight distances
In addition to the critical location indicated in the Manual, following locations may be
considered for the decision sight distance:
MSRDC Schedules
Construction of Nagpur Mumbai Super Communication Expressway (Package 16) from km
656.479 to km 701.479 on EPC Mode 64
At exits and merging sections, including exits to roadway facilities;
Sections with change in speed limit,
Sections with frequent vertical and horizontal curves.
The drivers of fast moving vehicles are required to make decisions while overtaking the
slow moving vehicles. Hence, if considerable number of slow moving vehicles (slower by
20kmph or more) are anticipated, it is advisable to adopt decision sight distance instead
of stopping sight distance for designing the geometric features of the expressway.
Appropriate advisory traffic signs such as "Look out for slow-moving vehicles" and other
appropriate traffic engineering measures may be considered wherever the decision
sight distance is not available. The decision sight distances may be separately calculated
for urban, suburban and rural sections through which the expressway is expected to
pass. For a design speed of 150 kmph, the minimum decision sight distance of 470 m
maybe recommended for rural areas, 540 m for suburban areas and 610 m for urban
areas.
The Manual Clause 2. 9. 4. 1 Vertical Alignment
In addition to the details provided in the Manual, following particulars may be adopted.
If the vertical gradient exceeds 3%, appropriate limits on the maximum length of
longitudinal section may be considered after field studies. It would depend on the
maximum desired speed drop of heavy vehicles and the adopted gradient.
Separate climbing lanes may be considered for longer stretches of roadway with
steeper gradients. In these sections, it is expected that heavier vehicles would
considerably slow down. The length of the stretch and its gradient may be
ascertained from field studies.
Minimum longitudinal gradient on bridges and tunnels may be considered for
drainage.
It is advisable to provide emergency escape ramps on hilly terrain where the
alignment has longer sections with steep downward gradient. Such ramps
maybe placed preferably before any sharp horizontal curve.
The Manual Clause 2.9.4.2: Gradients
There is no deviation in the minimum, ruling and limiting gradients for design speed of
150 kmph. However, the minimum longitudinal gradient shall be ascertained at sections
where consecutive horizontal curves in opposite direction are expected with zero
crossfall in-between. Further, vertical curve is not required for minimum grade change
MSRDC Schedules
Construction of Nagpur Mumbai Super Communication Expressway (Package 16) from km
656.479 to km 701.479 on EPC Mode 65
of 0. 5%. However, when provided, vertical curves with minimum length of 130 m
should be considered.
The Manual Clause 2.9.5: Coordination of Horizontal and Vertical Alignment
In addition to the details provided in the Manual, following particulars may be adopted:
Avoid short sags between two straights or short straights between sags.
Tangent length in horizontal and vertical alignments shall be equal.
Avoid flat, straight-board effect (especially on bridges)
Disjointed effect (bottom of a horizontal curve hidden due to preceding sag-
curve) should be avoided.
The Manual Cause 3. 3. 8: Acceleration/Deceleration Lanes
The acceleration lane length depends on vehicle speed at the entry point of the ramp,
prevailing vehicle speed in the adjacent lane of the expressway and acceleration rate.
Whereas, the deceleration lane length depends on the vehicle speed at the time of
entering the ramp, minimum vehicle speed at the end of the ramp and deceleration
rate. The acceleration and deceleration rate varies with vehicle speed and depends on
its engine characteristics. Considering the acceleration/deceleration and speed
characteristics of vehicles adopted in USA, the estimated acceleration and deceleration
lane length are as follows:
Table 2 Minimum acceleration and deceleration lengths for grades of 2 percent or less
speed on entry/exit curve of ramp
(kmph)
60 80 100 120
Length of acceleration lane (m) 930 820 450 350
Length of deceleration lane (m) 240 180 140 110
The left most lane is generally occupied by slow moving heavy vehicles traveling at
80kmph or less speed. In this case, the acceleration lane lengths based on the prevailing
vehicle speed in the left most lane are as follows:
Table 3 Acceleration lengths based on prevailing speed in the left most lane
MSRDC Schedules
Construction of Nagpur Mumbai Super Communication Expressway (Package 16) from km
656.479 to km 701.479 on EPC Mode 66
Prevailing vehicle speed in
left most lane (kmph)
Acceleration Length L (m)
Speed on entry curve (km/h)
60 80
80 305 -
100 620 470
Tunnel:
Tunnel facilities provisions shall be as per category applicable as per Table 7.1 of the
Manual.
MSRDC Schedules
Construction of Nagpur Mumbai Super Communication Expressway (Package 16) from km
664.479to km 701.479 on EPC Mode 67
SCHEDULE – E (See Clauses 2.1 and 14.2)
MAINTENANCE REQUIREMENTS
1. Maintenance Requirements
1.1. The Contractor shall at all times maintain the Project Expressway in accordance
with the provisions of this Agreement, Applicable Laws, and Applicable Permits.
1.2. The Contractor shall repair or rectify any defect or deficiency set forth in Paragraph 2 of
Schedule - E within the time limit specified therein and any failure in this behalf shall
constitute non-fulfillment of the Maintenance obligations by the Contractor. Upon
occurrence of any breach hereunder, the authority shall be entitled to effect reduction
in monthly lump sum payment as set forth in Clause 14.6 of this Agreement, without
prejudice to the rights of the Authority under this Agreement, including termination
thereof.
1.3. All materials, works, and construction operations shall conform to the MORT&H
Specifications for Road and Bridge Works, and the relevant IRC publications. Where the
specifications for a work are not given, Good Industry Practice shall be adopted.
2. Repair/Rectification of Defects and Deficiencies
The obligations of the Contractor in respect of Maintenance Requirements shall include
repair and rectification of the defects and deficiencies specified in Annex-I of this Schedule-
E within the time limit set forth therein.
3. Other Defects and Deficiencies
In respect of any defect or deficiency not specified in Annex-I of this Schedule-E, the
Authority’s Engineer may, in conformity with Good Industry Practice, specify the
permissible limit of deviation or deterioration with reference to the Specifications and
Standards, and any deviation or deterioration beyond the permissible limit shall be
repaired or rectified by the Contractor within the time limit specified by the Authority’s
Engineer.
4. Extension of Time Limit
Notwithstanding anything to the contrary specified in this Schedule-E, if the nature and
extent of any defect or deficiency justifies more time for its repair or rectification than the
time specified herein, the Contractor shall be entitled to additional time in conformity with
MSRDC Schedules
Construction of Nagpur Mumbai Super Communication Expressway (Package 16) from km
664.479to km 701.479 on EPC Mode 68
Good Industry Practice.Such additional time shall be determined by the Authority’s
Engineer and conveyed to the Contractor and the Authority with reasons thereof.
5. Emergency Repairs/Restoration
Notwithstanding anything to the contrary contained in this Schedule-E, if any Defect,
deficiency or deterioration in the Project Expressway poses a hazard to safety or risk of
damage to property, the Contractor shall promptly take all reasonable measures for
eliminating or minimizing such danger.
6. Daily Inspection by the Contractor
The Contractor shall, through its engineer, undertake a daily visual inspection of the Project
Expressway and maintain a record thereof in a register to be kept in such form and manner
as the Authority’s Engineer may specify. Such record shall be kept in safe custody of the
Contractor and shall be open to inspection by the Authority and the Authority’s Engineer at
any time during office hours.
7. Pre-monsoon / Post-monsoon Inspection
The Contractor shall carry out a detailed pre-monsoon inspection of the Expressway, and its
drainage system before 1st June every year in accordance with the guidelines contained in
IRC: SP: 35. Report of this inspection together with details of proposed maintenance works
as required on the basis of this inspection shall be sent to the Authority’s Engineer before
the 10th June every year. The Contractor shall complete the required repairs before the
onset of the monsoon and send to the Authority’s Engineer a compliance report. Post
monsoon inspection shall be done by the 30th September and the inspection report
together with details of any damages observed and proposed action to remedy the same
shall be sent to the Authority’s Engineer.
8. Repairs on Account of Natural Calamities
All damages occurring to the Project Expressway on account of a Force Majeure Event of
default or neglect of the Authority shall be undertaken by the Authority at its own cost. The
Authority may instruct the Contractor to undertake the repairs at the rates agreed between
the Parties.
MSRDC Schedules
Construction of Nagpur Mumbai Super Communication Expressway (Package 16) from km
664.479to km 701.479 on EPC Mode 69
Annex – I
(Schedule-E)
REPAIR/RECTIFICATION OF DEFECTS AND DEFICIENCIES
The Contractor shall repair and rectify the Defects and Deficiencies specified in this Annex-I of
Schedule-E within the time limit set forth in the table below.
Nature of Defect or Deficiency Time Limit for Repair/ Rectification
Road
(a) Carriageway and paved shoulders
(i) Breach or blockade
Temporary restoration of traffic
within 24 hours; permanent
restoration within 15 (fifteen) days
(ii)
Roughness value exceeding 2000mm in
a stretch of 1km (asmeasured by a laser
profilometer)
120 (one hundred and twenty) days
(iii) Pot holes 24 hours
(iv) Any cracks in road surface 15 (fifteen) days
(v) Any depressions, rutting exceeding
10mm in road surface
30 (thirty) days
(vi) Bleeding/skidding 7 (seven ) days
(vii) Routing and sealing random transverse
cracks that are larger in width than 5mm 15 (fifteen) days
MSRDC Schedules
Construction of Nagpur Mumbai Super Communication Expressway (Package 16) from km
664.479to km 701.479 on EPC Mode 70
Nature of Defect or Deficiency Time Limit for Repair/ Rectification
(viii) Routing and sealing random longitudinal
cracks that are larger in width than 5mm 15 (fifteen) days
(ix) Any other defect/distress on the road 15 (fifteen) days
(x) Damage to pavement edges 15 (fifteen) days
(xi) Removal of debris, dead animals 6 hours
(b) Granular earth shoulders, side slopes, and drains
(i)
Variation by more than 1% in the
prescribed slope of camber/cross fall
(shall not be less than the camber on the
main carriageway)
7 (seven) days
(ii) Edge drop at shoulders exceeding 40mm 7 (seven) days
(iii) Variation by more than 15% in the
prescribed side (embankment) slopes 30 (thirty) days
(iv) Rain cuts/gullies in slope 7 (seven) days
(v) Damage to or silting of side drains 7 (seven) days
(vi) Desilting of drains in urban/semi-urban
areas 24 hours
(vii) Railing, parapets, crash barriers 7 (seven) days (Restore immediately
if causing safety hazard)
(c) Road side furniture including road sign and pavement marking
(i) Damage to shape or position, poor 48 hours
MSRDC Schedules
Construction of Nagpur Mumbai Super Communication Expressway (Package 16) from km
664.479to km 701.479 on EPC Mode 71
Nature of Defect or Deficiency Time Limit for Repair/ Rectification
visibility or loss of retro-reflectivity
(ii) Painting of KM stone, railing, parapets,
crash barriers
As and when required/Once every
year
(iii) Damaged/missing road signs requiring
replacement 7 (seven) days
(iv) Damage to road mark ups 7 (seven) days
(d) Road lighting
(i) Any major failure of the system 24 hours
(ii) Faults and minor failures 8 hours
(iii)
Any other defects/deficiency not covered
above but pointed out by Authority’s
Engineer
3 (three) days
(e) Trees and plantation
(i)
Obstruction in a minimum head-room of
5m above carriageway or obstruction in
visibility of road signs
24 hours
(ii) Removal of fallen trees from carriageway 4 hours
(iii) Deterioration in health of trees and
bushes Timely watering and treatment
(iv) Trees and bushes requiring replacement 30 (thirty) days
(v) Removal of vegetation affecting sight line
and road structures 15 (fifteen) days
MSRDC Schedules
Construction of Nagpur Mumbai Super Communication Expressway (Package 16) from km
664.479to km 701.479 on EPC Mode 72
Nature of Defect or Deficiency Time Limit for Repair/ Rectification
(vi)
Any other defects/deficiency not covered
above but pointed out by Authority’s
Engineer
3 (three) days
(f) Other Project Facilities and Service roads
(i) Damage in service roads, pedestrian
facilities, stairs, and Medical Aid Posts. 15 (fifteen) days
(ii) Damaged vehicles or debris
on the road 4 (four) hours
(iii) Malfunctioning of the mobilecrane 4 (four) hours
(g) Rest area
(i) Cleaning of toilets Every 4 hours
(ii) Defects in electrical, water and sanitary
installation
24 hours
(h) Toll Plaza Not Applicable
Bridges
(a) Superstructure
(i)
Any damage, cracks, spalling / scaling
Temporary measures
Permanent measures
Within 48 hours
Within 15 (fifteen) days or as
specified by the Authority’s Engineer
(b) Foundations
MSRDC Schedules
Construction of Nagpur Mumbai Super Communication Expressway (Package 16) from km
664.479to km 701.479 on EPC Mode 73
Nature of Defect or Deficiency Time Limit for Repair/ Rectification
(i) cavitation’s ( if any) 15 (fifteen) days
(c) Piers, abutments, return walls, and wing walls
(i) Cracks and damages including settlement
and tilting, spalling, scaling 30 (thirty) days
(d) Bearings (metallic/POT PTFE ) of flyover
(i) Deformation, damages, tilting or shifting
of bearings
15 (fifteen) days
Greasing of metallic bearings once in
a year
(e) Joints
(i) Malfunctioning of joints 15 (fifteen) days
(f) Other items
(i) Deforming of pads in elastomeric bearings 7 (seven) days
(ii)
Gathering of dirt in bearings and joints; or
clogging of spouts, weep holes, and vent-
holes
3 (three) days
(iii) Damage or deterioration in kerbs,
parapets, handrails, and crash barriers
3 (three) days
(immediately within 24 hours if
posing danger of safety)
(iv) Rain-cuts or erosion of banks of the side
slopes of approaches 15 (fifteen) days
(v) Damage to wearing coat 15 (fifteen) days
MSRDC Schedules
Construction of Nagpur Mumbai Super Communication Expressway (Package 16) from km
664.479to km 701.479 on EPC Mode 74
Nature of Defect or Deficiency Time Limit for Repair/ Rectification
(vi)
Damage or deterioration in approach
slabs, pitching, apron, toes, floor, or guide
bunds
30 (thirty) days
(vii) Growth of vegetation affecting the
structure or obstructing the waterway 15 (fifteen) days
Hill Roads
(i) Damage to retaining wall/breast wall 7 (seven) days
(ii) Landslides requiring clearance 12 (twelve) hours
(iii) Snow requiring clearance 24 (twenty four) hours
Note: For rigid pavement, maintenance manual and maintenance schedule shall be finalised by
Authority Engineer as per good industry practice and shall be included as part of this schedule.
179
MSRDC Schedules
Construction of Nagpur Mumbai Super Communication Expressway (Package 16) from km
664.479to km 701.479 on EPC Mode 75
SCHEDULE- F
(See Clause 3.1.7(a))
APPLICABLE PERMITS
1. Applicable Permits
1.1. The Contractor shall obtain, as required under the Applicable Laws, the following
Applicable Permits:
(a) Permission of the State Government for extraction of boulders / stones from
quarry;
(b) Permission of Village Panchayats and Pollution Control Board for installation of
crushers;
(c) License for use of explosives;
(d) Permission of the State Government for drawing water from river/reservoir;
(e) License from inspector of factories or other competent Authority for setting up
batching plant;
(f) Clearance of Pollution Control Board for setting up batching plant;
(g) Clearance of Village Panchayats and Pollution Control Board for setting up
asphalt plant;
(h) Permission of Village Panchayats and State Government for borrow earth, and
any other permits or clearances required under Applicable Laws.
1.2. Applicable Permits, as required, relating to environmental protection and
conservation shall have been procured by the Authority in accordance with the
provisions of this Agreement.
MSRDC Schedules
Construction of Nagpur Mumbai Super Communication Expressway (Package 16) from km 656.479
to km 701.362 on EPC Mode. 76
SCHEDULE-G
(See Clauses 7.1.1, 7.5.3 and 19.2)
FORM OF BANK GUARANTEE
Annex-I
(See Clause 7.1.1)
PERFORMANCE SECURITY
Executive Engineer,
MSRDC (Ltd.)
Opp. Bandra Reclamation Bus Depot,
Near Lilavati Hospital,
K. C. Marg, Bandra (West)
Mumbai 400 050
WHEREAS:
_______________________________ (Hereinafter called the “Contractor”) has executed an
agreement (Hereinafter called the “Agreement”) with the “ Chief Engineer, MSRDC, Bandra,
Mumbai, Maharashtra”(Hereinafter called the “Authority”) have entered into an agreement for
the “Construction of Nagpur-Mumbai Super Communication Expressway, Package V with
construction package 16 on EPC mode.”, subject to and in accordance with the provisions of the
Agreement.
(A) The Agreement requires the Contractor to furnish a Performance Security for due and
faithful performance of its obligations, under and in accordance with the Agreement,
during the {Construction Period/ Defects Liability Period and Maintenance Period} (as
defined in the Agreement) in a sum of Rs. _____________ Cr. (Rupees
________________________________________ crore) (the “Guarantee Amount”).
MSRDC Schedules
Construction of Nagpur Mumbai Super Communication Expressway (Package 16) from km 656.479
to km 701.362 on EPC Mode. 77
(B) We, _________________ through our branch at _________________ (the “Bank”) have
agreed to furnish this bank guarantee (hereinafter called the “Guarantee”) by way of
Performance Security.
NOW, THEREFORE, the Bank hereby, unconditionally and irrevocably, guarantees and affirms as
follows:
1. The Bank hereby unconditionally and irrevocably guarantees the due and faithful
performance of the Contractor’s obligations during the {Construction period /Defects
Liability Period and maintenance period} under and in accordance with the Agreement, and
agrees and undertakes to pay to the Authority, upon its mere first written demand, and
without any demur, reservation, recourse, contest or protest, and without any reference to
the Contractor, such sum or sums up to an aggregate sum of the Guarantee Amount as the
Authority shall claim, without the Authority being required to prove or to show grounds or
reasons for its demand and/or for the sum specified therein.
2. A letter from the Authority, under the hand of an officer not below the rank of Executive
Engineer in the NH, MSRDC that the Contractor has committed default in the due and
faithful performance of all or any of its obligations under and in accordance with the
Agreement shall be conclusive, final and binding on the Bank. The Bank further agrees that
the Authority shall be the sole judge as to whether the Contractor is in default in due and
faithful performance of its obligations during and under the Agreement and its decision that
the Contractor is in default shall be final and binding on the Bank, notwithstanding any
difference between the Authority and the Contractor, or any dispute between them pending
before any court, tribunal, arbitrators or any other Authority or body, or by the discharge of
the Contractor for any reason whatsoever.
3. In order to give effect to this Guarantee, the Authority shall be entitled to act as if the Bank
were the principal debtor and any change in the constitution of the Contractor and/or the
Bank, whether by their absorption with any other body or corporation or otherwise, shall not
in any way or manner affect the liability or obligation of the Bank under this Guarantee.
MSRDC Schedules
Construction of Nagpur Mumbai Super Communication Expressway (Package 16) from km 656.479
to km 701.362 on EPC Mode. 78
4. It shall not be necessary, and the Bank hereby waives any necessity, for the Authority to
proceed against the Contractor before presenting to the Bank its demand under this
Guarantee.
5. The Authority shall have the liberty, without affecting in any manner the liability of the Bank
under this Guarantee, to vary at any time, the terms and conditions of the Agreement or to
extend the time or period for the compliance with, fulfillment and/or performance of all or
any of the obligations of the Contractor contained in the Agreement or to postpone for any
time, and from time to time, any of the rights and powers exercisable by the Authority
against the Contractor, and either to enforce or forbear from enforcing any of the terms and
conditions contained in the Agreement and/or the securities available to the Authority, and
the Bank shall not be released from its liability and obligation under these presents by any
exercise by the Authority of the liberty with reference to the matters aforesaid or by reason
of time being given to the Contractor or any other forbearance, indulgence, act or omission
on the part of the Authority or of any other matter or thing whatsoever which under any law
relating to sureties and guarantors would but for this provision have the effect of releasing
the Bank from its liability and obligation under this Guarantee and the Bank hereby waives
all of its rights under any such law.
6. This Guarantee is in addition to and not in substitution of any other guarantee or security
now or which may hereafter be held by the Authority in respect of or relating to the
Agreement or for the fulfillment, compliance and/or performance of all or any of the
obligations of the Contractor under the Agreement.
7. Notwithstanding anything contained hereinbefore, the liability of the Bank under this
Guarantee is restricted to the Guarantee amount and this Guarantee will remain in force for
the period specified in paragraph 8 below and unless a demand or claim in writing is made
by the Authority on the Bank under this Guarantee all rights of the Authority under this
Guarantee shall be forfeited and the Bank shall be relieved from its liabilities hereunder.
8. The Guarantee shall cease to be in force and effect on Rs. _________ unless a demand or
claim under this Guarantee is made in writing before expiry of the Guarantee, the Bank shall
be discharged from its liabilities hereunder.
9. The Bank undertakes not to revoke this Guarantee during its currency, except with the
previous express consent of the Authority in writing, and declares and warrants that it has
MSRDC Schedules
Construction of Nagpur Mumbai Super Communication Expressway (Package 16) from km 656.479
to km 701.362 on EPC Mode. 79
the power to issue this Guarantee and the undersigned has full powers to do so on behalf of
the Bank.
10. Any notice by way of request, demand or otherwise hereunder may be sent by post
addressed to the Bank at its above referred branch, which shall be deemed to have been
duly authorized to receive such notice and to effect payment thereof forthwith, and if sent
by post it shall be deemed to have been given at the time when it ought to have been
delivered in due course of post and in proving such notice, when given by post, it shall be
sufficient to prove that the envelope containing the notice was posted and a certificate
signed by an officer of the Authority that the envelope was so posted shall be conclusive.
11. This Guarantee shall come into force with immediate effect and shall remain in force and
effect for up to the date specified in paragraph 8 above or unit it is released earlier by the
Authority pursuant to the provisions of the Agreement.
Signed and sealed this ____ Day of ____________ 20__ at ___________________.
SIGNED, SEALED AND DELIVERED
For and on behalf of the Bank by:
(Signature)
(Name)
(Designation)
(Code Number)
MSRDC Schedules
Construction of Nagpur Mumbai Super Communication Expressway (Package 16) from km 656.479
to km 701.362 on EPC Mode. 80
(Address)
NOTES:
(i) The bank guarantee should contain the name, designation and code number of the
officer(s) signing the guarantee.
(ii) The address, telephone number and other details of the head office of the Bank as well as
of issuing branch should be mentioned on the covering letter of issuing branch.
MSRDC Schedules
Construction of Nagpur Mumbai Super Communication Expressway (Package 16) from km 656.479
to km 701.362 on EPC Mode. 81
Annex - II
(Schedule-G)
(See Clause 7.5.3)
FORM FOR GUARANTEE FOR WITHDRAWAL OF RETENTION MONEY
Executive Engineer,
MSRDC (Ltd.)
Opp. Bandra Reclamation Bus Depot,
Near Lilavati Hospital,
K. C. Marg, Bandra (West)
Mumbai 400 050
WHEREAS:
_______________________________ (Hereinafter called the “Contractor”) has executed an
agreement (Hereinafter called the “Agreement”) with the “Chief Engineer, MSRDC, Mumbai,
Maharashtra”(Hereinafter called the “Authority”) have entered into an agreement for the
“Construction of Nagpur-Mumbai Super Communication Expressway, Package V with construction
package 16 on EPC mode.”, subject to and in accordance with the provisions of the Agreement.
(A) In accordance with the Clause 7.5.3 of the Agreement, the Contractor may withdraw the
retention money (hereinafter called the “Retention Money”) after furnishing to the
Authority a bank guarantee for an amount equal to the proposed withdrawal.
(B) We, __________________ through our branch at _______________________ (the “Bank”)
have agreed to furnish this bank guarantee (hereinafter called the “Guarantee”) for the
amount of Rs. ________ cr. (Rupees _______________________________________) (the
“Guarantee Amount”).
MSRDC Schedules
Construction of Nagpur Mumbai Super Communication Expressway (Package 16) from km 656.479
to km 701.362 on EPC Mode. 82
NOW, THEREFORE, the Bank hereby, unconditionally and irrevocably, guarantees and affirms as
follows:
1. The Bank hereby unconditionally and irrevocably undertakes to pay to the Authority, upon
its mere first written demand, and without any demur, reservation, recourse, contest or
protest, and without any reference to the Contractor, such sum or sums up to an aggregate
sum of the Guarantee Amount as the Authority shall claim, without the Authority being
required to prove or to show grounds or reasons for its demand and/or for the sum specified
therein.
2. A letter from the Authority, under the hand of an officer not below the rank of Executive
Engineer in the MSRDC, Nagpur that the Contractor has committed default in the due and
faithful performance of all or any of its obligations under and in accordance with the
Agreement shall be conclusive, final and binding on the Bank. The Bank further agrees that
the Authority shall be the sole judge as to whether the Contractor is in default in due and
faithful performance of its obligations during and under the Agreement and its decision that
the Contractor is in default shall be final, and binding on the Bank, notwithstanding any
difference between the Authority and the Contractor, or any dispute between them pending
before any court, tribunal, arbitrators or any other Authority or body, or by the discharge of
the Contractor for any reason whatsoever.
3. In order to give effect to this Guarantee, the Authority shall be entitled to act as if the Bank
were the principal debtor and any change in the constitution of the Contractor and/or the
Bank, whether by their absorption with any other body or corporation or otherwise, shall not
in any way or manner affect the liability or obligation of the Bank under this Guarantee.
4. It shall not be necessary, and the Bank hereby waives any necessity, for the Authority to
proceed against the Contractor before presenting to the Bank its demand under this
Guarantee.
5. The Authority shall have the liberty, without affecting in any manner the liability of the
Bank under this Guarantee, to vary at any time, the terms and conditions of the Retention
Money and any of the rights and powers exercisable by the Authority against the Contractor,
and either to enforce or forbear from enforcing any of the terms and conditions contained in
MSRDC Schedules
Construction of Nagpur Mumbai Super Communication Expressway (Package 16) from km 656.479
to km 701.362 on EPC Mode. 83
the Agreement and/or the securities available to the Authority, and the Bank shall not be
released from its liability and obligation under these presents by any exercise by the
Authority of the liberty with reference to the matters aforesaid or by reason of time being
given to the Contractor or any other forbearance, indulgence, act or omission on the part of
the Authority or of any other matter or thing whatsoever which under any law relating to
sureties and guarantors would but for this provision have the effect of releasing the Bank
from its liability and obligation under this Guarantee and the Bank hereby waives all of its
rights under any such law.
6. This Guarantee is in addition to and not in substitution of any other guarantee or security
now or which may hereafter be held by the Authority in respect of or relating to the
Retention Money.
7. Notwithstanding anything contained hereinbefore, the liability of the Bank under this
Guarantee is restricted to the Guarantee amount and this Guarantee will remain in force for
the period specified in paragraph 8 below and unless a demand or claim in writing is made
by the Authority on the Bank under this Guarantee all rights of the Authority under this
Guarantee shall be forfeited and the Bank shall be relieved from its liabilities hereunder.
8. The Guarantee shall cease to be in force and effect 90 (ninety) days after the end of the
Defects Liability Period specified in Clauses 12.4 of the Agreement.
9. The Bank undertakes not to revoke this Guarantee during its currency, except with the
previous express consent of the Authority in writing, and declares and warrants that it has
the power to issue this Guarantee and the undersigned has full powers to do so on behalf of
the Bank.
10. Any notice by way of request, demand or otherwise hereunder may be sent by post
addressed to the Bank at its above referred branch, which shall be deemed to have been
duly authorized to receive such notice and to effect payment thereof forthwith, and if sent
by post it shall be deemed to have been given at the time when it ought to have been
delivered in due course of post and in proving such notice, when given by post, it shall be
sufficient to prove that the envelope containing the notice was posted and a certificate
signed by an officer of the Authority that the envelope was so posted shall be conclusive.
MSRDC Schedules
Construction of Nagpur Mumbai Super Communication Expressway (Package 16) from km 656.479
to km 701.362 on EPC Mode. 84
11. This Guarantee shall come into force with immediate effect and shall remain in force and
effect for up to the date specified in paragraph 8 above or until it is released earlier by the
Authority pursuant to the provisions of the Agreement.
Signed and sealed this ____Day of ____________ 20__ at ___________________.
SIGNED, SEALED AND DELIVERED
For and on behalf of the Bank by:
(Signature)
(Name)
(Designation)
(Code Number)
(Address)
NOTES:
(i) The bank guarantee should contain the name, designation and code number of the
officer(s) signing the guarantee.
(ii) The address, telephone number and other details of the head office of the Bank as well as
of issuing branch should be mentioned on the covering letter of issuing branch.
MSRDC Schedules
Construction of Nagpur Mumbai Super Communication Expressway (Package 16) from km 656.479
to km 701.362 on EPC Mode. 85
Annex - III
(Schedule-G)
(See Clause 19.2)
FORM FOR GUARANTEE FOR ADVANCE PAYMENT
Executive Engineer,
MSRDC (Ltd.)
Opp. Bandra Reclamation Bus Depot,
Near Lilavati Hospital,
K. C. Marg, Bandra (West)
Mumbai 400 050
WHEREAS:
_______________________________ (Hereinafter called the “Contractor”) has executed an
agreement (Hereinafter called the “Agreement”) with the “Chief Engineer, MSRDC, Mumbai,
Maharashtra”(Hereinafter called the “Authority”) have entered into an agreement for the
“Construction of Nagpur-Mumbai Super Communication Expressway, Package V with construction
package 16 on EPC mode.”, subject to and in accordance with the provisions of the Agreement.
(A) In accordance with the Clause 19.2 of the Agreement the Authority shall make to the
Contractor an interest free advance payment (hereinafter called the“Advance Payment”)
equal to 10% (ten per cent) of the Contract Price; and that the advance payment shall be
made in three installments subject to the Contractor furnishing an irrevocable and
unconditional guarantee by a scheduled bank for an amount equal to 110% (One hundred
and ten percent) of such installment to remain effective till the complete and full
repayment of the installment of the Advance Payment as security for compliance with its
MSRDC Schedules
Construction of Nagpur Mumbai Super Communication Expressway (Package 16) from km 656.479
to km 701.362 on EPC Mode. 86
obligations in accordance with the Agreement. The amount of {first/second/third}
installment of the Advance Payment
(B) We, ____________________________ through our branch at ______________________
(the“Bank”) have agreed to furnish this bank guarantee (hereinafter called the
“Guarantee”) for the Guarantee Amount.
NOW, THEREFORE, the Bank hereby, unconditionally and irrevocably, guarantees and affirms as
follows:
1. The Bank hereby unconditionally and irrevocably guarantees the due and faithful
repayment on time of the aforesaid installment of the Advance Payment under and in
accordance with the Agreement, and agrees and undertakes to pay to the Authority, upon
its mere first written demand, and without any demur, reservation, recourse, contest or
protest, and without any reference to the Contractor, such sum or sums up to an aggregate
sum of the guarantee amount as the Authority shall claim, without the Authority being
required to prove or to show grounds or reasons for its demand and/or for the sum
specified therein.
2. A letter from the Authority, under the hand of an officer not below the rank of Executive
Engineer in the MSRDC, Nagpur, that the Contractor has committed default in the due and
faithful performance of all or any of its obligations for the repayment of the installment of
the Advance Payment under and in accordance with the Agreement shall be conclusive,
final and binding on the Bank. The Bank further agrees that the Authority shall be the sole
judge as to whether the Contractor is in default in due and faithful performance of its
obligations during and under the Agreement and its decision that the Contractor is in
default shall be final, and binding on the Bank, notwithstanding any difference between
the Authority and the Contractor, or any dispute between them pending before any court,
tribunal, arbitrators or any other Authority or body, or by the discharge of the Contractor
for any reason whatsoever.
3. In order to give effect to this Guarantee, the Authority shall be entitled to act as if the Bank
were the principal debtor and any change in the constitution of the Contractor and/or the
MSRDC Schedules
Construction of Nagpur Mumbai Super Communication Expressway (Package 16) from km 656.479
to km 701.362 on EPC Mode. 87
Bank, whether by their absorption with any other body or corporation or otherwise, shall
not in any way or manner affect the liability or obligation of the Bank under this
Guarantee.
4. It shall not be necessary, and the Bank hereby waives any necessity, for the Authority to
proceed against the Contractor before presenting to the Bank its demand under this
Guarantee.
5. The Authority shall have the liberty, without affecting in any manner the liability of the
Bank under this Guarantee, to vary at any time, the terms and conditions of the Advance
Payment or to extend the time or period of its repayment or to postpone for any time, and
from time to time, any of the rights and powers exercisable by the Authority against the
Contractor, and either to enforce or forbear from enforcing any of the terms and
conditions contained in the Agreement and/or the securities available to the Authority,
and the Bank shall not be released from its liability and obligation under these presents by
any exercise by the Authority of the liberty with reference to the matters aforesaid or by
reason of time being given to the Contractor or any other forbearance, indulgence, act or
omission on the part of the Authority or of any other matter or thing whatsoever which
under any law relating to sureties and guarantors would but for this provision have the
effect of releasing the Bank from its liability and obligation under this Guarantee and the
Bank hereby waives all of its rights under any such law.
6. This Guarantee is in addition to and not in substitution of any other guarantee or security
now or which may hereafter be held by the Authority in respect of or relating to the
Advance Payment.
7. Notwithstanding anything contained hereinbefore, the liability of the Bank under this
Guarantee is restricted to the Guarantee amount and this Guarantee will remain in force
for the period specified in paragraph 8 below and unless a demand or claim in writing is
made by the Authority on the Bank under this Guarantee all rights of the Authority under
this Guarantee shall be forfeited and the Bank shall be relieved from its liabilities
hereunder.
MSRDC Schedules
Construction of Nagpur Mumbai Super Communication Expressway (Package 16) from km 656.479
to km 701.362 on EPC Mode. 88
8. The Guarantee shall cease to be in force and effect on****. Unless a demand or claim
under this Guarantee is made in writing on or before the aforesaid date, the Bank shall be
discharges from its liabilities hereunder.
9. The Bank undertakes not to revoke this Guarantee during its currency, except with the
previous express consent of the Authority in writing, and declares and warrants that it has
the power to issue this Guarantee and the undersigned has full powers to do so on behalf
of the Bank.
10. Any notice by way of request, demand or otherwise hereunder may be sent by post
addressed to the Bank at its above referred branch, which shall be deemed to have been
duly authorized to receive such notice and to effect payment thereof forthwith, and if sent
by post it shall be deemed to have been given at the time when it ought to have been
delivered in due course of post and in proving such notice, when given by post, it shall be
sufficient to prove that the envelope containing the notice was posted and a certificate
signed by an officer of the Authority that the envelope was so posted shall be conclusive.
11. This Guarantee shall come into force with immediate effect and shall remain in force and
effect for up to the date specified in paragraph 8 above or until it is released earlier by the
Authority pursuant to the provisions of the Agreement.
Signed and sealed this ______Day of _________________ 20____ at ___________.
SIGNED, SEALED AND DELIVERED
For and on behalf of the Bank by:
(Signature)
(Name)
MSRDC Schedules
Construction of Nagpur Mumbai Super Communication Expressway (Package 16) from km 656.479
to km 701.362 on EPC Mode. 89
(Designation)
(Code Number)
(Address)
NOTES:
(i) The bank guarantee should contain the name, designation and code number of the
officer(s) signing the guarantee.
(ii) The address, telephone number and other details of the head office of the Bank as
well as of issuing branch should be mentioned on the covering letter of issuing branch.
MSRDC, Maharashtra Schedules to Concession Agreement
Construction of Nagpur- Mumbai Super Communication Expressway (Package-16) from Km 664.479
to Km 701.479 on EPC mode 90
H. SCHEDULE-H
(SeeClauses10.1.4 and19.3)
Contract Price Weightages
1.1 The Contract Price for this Agreement is Rs. 2,716.19 Crores
1.2 Proportions of the Contract Price for different stages of Construction of the Project Expressway shall be as specified below:
Item Weightage in
percentage to the
Contract Price
Stage for Payment
Percentage weightage
1 2 3 4
Road works including culverts, widening and
repair of culverts.
24.93%
A- Deleted
B.1- Construction of 6-lane+Paved shoulder Pavement (Rigid pavement)
(1) Earthwork up to top of the sub-grade 45.24%
(2) Sub Base Course 5.91%
(3) Dry Lean Concrete(DLC) Course 6.99%
(4) Pavement Quality Control (PQC) Course
31.59%
C.1- Construction of Service road (Flexible pavement)
(1) Earthwork up to top of the sub-grade 1.98%
(2) Sub Base Course 1.32%
(3) Non-Bituminous Base Course 1.06%
(4) Bituminous Base Course 1.91%
(5) Wearing Coat 0.29%
C.2- Construction of Service road (Rigid Pavement)
(1) Earthwork up to top of the sub-grade
(2) Sub Base Course
(3) Dry Lean Concrete(DLC) Course
(4) Pavement Quality Control (PQC) Course
D- Re-Construction and New culverts on existing road, realignments, bypasses:
Culverts (length < 6 m) 3.70%
Minor Bridges/ Underpasses/ Overpasses 1.87%
A.I- Deleted
Minor bridges
A.2- New Minor bridges (length >6 and
MSRDC, Maharashtra Schedules to Concession Agreement
Construction of Nagpur- Mumbai Super Communication Expressway (Package-16) from Km 664.479
to Km 701.479 on EPC mode 91
<60 m.)
a)Minor Bridges
(1) Foundation +Sub- structure: On completion of the foundation work including foundations for wing and return walls, abutments, piers upto the abutment/pier cap.
23.81%
(2) Super-structure: On completion of the super- structure in all respects including wearing coat, bearings, expansion joints, hand rails, crash barriers, road signs & markings, tests on completion etc. complete in all respect.
6.61%
(3) Approaches: On completion of approaches including Retaining walls, stone pitching, protection works complete in all respect and fit for use.
2.65%
(4) Guide Bunds and River Training Works: On completion of Guide Bunds and river Training Works complete in all respects
b)Canal Bridges
(1) Foundation +Sub- structure: On completion of the foundation work including foundations for wing and return walls, abutments, piers upto the abutment/pier cap.
0.00%
(2) Super-structure: On completion of the super- structure in all respects including wearing coat, bearings, expansion joints, hand rails, crash barriers, road signs & markings, tests on completion etc. complete in all respect.
0.00%
(3) Approaches: On completion of approaches including Retaining walls, stone pitching, protection works complete in all respect and fit for use.
0.00%
(4) Guide Bunds and River Training Works: On completion of Guide Bunds and river Training Works complete in all respects
B.1-Deleted
Underpasses/ Overpasses
B.2- Underpasses/ overpasses
a)PUP
(1) Foundation +Sub- Structure: On completion of the foundation work including foundations for wing and return walls, abutments, piers upto the abutment/pier cap.
19.14%
MSRDC, Maharashtra Schedules to Concession Agreement
Construction of Nagpur- Mumbai Super Communication Expressway (Package-16) from Km 664.479
to Km 701.479 on EPC mode 92
(2) Super-structure: On completion of the super- structure in all respects including wearing coat, bearings, expansion joints, hand rails, crash barriers, road signs Wearing Coat (a) in case of Overpass- wearing coat including expansion joints complete in all respects as specified and (b) in case of underpass- rigid pavement including drainage facility complete in all respects as specified as specified.completion etc. complete in all respect.& markings, tests on
11.73%
(3) Approaches: On completion of approaches including Retaining walls/ Reinforced Earth walls, stone pitching, protection works complete in all respect and fit for use.
b)VUP
(1) Foundation +Sub- Structure: On completion of the foundation work including foundations for wing and return walls, abutments, piers upto the abutment/pier cap.
22.36%
(2) Super-structure: On completion of the super- structure in all respects including wearing coat, bearings, expansion joints, hand rails, crash barriers, road signs Wearing Coat (a) in case of Overpass- wearing coat including expansion joints complete in all respects as specified and (b) in case of underpass- rigid pavement including drainage facility complete in all respects as specified as specified.completion etc. complete in all respect.& markings, tests on
13.70%
(3) Approaches: On completion of approaches including Retaining walls/ Reinforced Earth walls, stone pitching, protection works complete in all respect and fit for use.
0.00%
c)LVUP
(1) Foundation +Sub- Structure: On completion of the foundation work including foundations for wing and return walls, abutments, piers upto the abutment/pier cap.
0.00%
MSRDC, Maharashtra Schedules to Concession Agreement
Construction of Nagpur- Mumbai Super Communication Expressway (Package-16) from Km 664.479
to Km 701.479 on EPC mode 93
(2) Super-structure: On completion of the super- structure in all respects including wearing coat, bearings, expansion joints, hand rails, crash barriers, road signs Wearing Coat (a) in case of Overpass- wearing coat including expansion joints complete in all respects as specified and (b) in case of underpass- rigid pavement including drainage facility complete in all respects as specified as specified.completion etc. complete in all respect.& markings, tests on
0.00%
(3) Approaches: On completion of approaches including Retaining walls/ Reinforced Earth walls, stone pitching, protection works complete in all respect and fit for use.
0.00%
Major Bridge(length >60m.) works and
ROB/RUB/ elevated sections/flyov ers
including viaducts, if any
39.64%
A.1-Deleted
A. 2- Major Bridges
(1) Foundation 0.00%
(2) Sub-structure 0.00%
(3) Super-structure (including bearings) 0.00%
(4) Wearing Coat including expansion joints
0.00%
(5) Miscellaneous Items like hand rails, crash barriers, road markings etc.) 0.00%
(6) Wing walls/return walls 0.00%
(7) Guide Bunds, River Training works etc.
0.00%
(8) Approaches (including Retaining walls, stone pitching and protection works)
0.00%
B. 1- Deleted
B.2- Constrution of ROB/RUB
(a) ROB
(b) RUB
(1) Foundation 0.46%
(2) Sub-structure 0.32%
(3) Super-structure (including bearings) 0.45%
(4) Wearing Coat: (a) in case of ROB- wearing coat including expansion joints complete in all respects as specified and (b) in case of RUB- rigid pavement under RUB including drainage facility complete in all respects as specified as specified.
0.12%
(5) Miscellaneous Items like hand rails, crash barriers, road markings etc.) 0.02%
(6) Wing walls/return walls 0.02%
MSRDC, Maharashtra Schedules to Concession Agreement
Construction of Nagpur- Mumbai Super Communication Expressway (Package-16) from Km 664.479
to Km 701.479 on EPC mode 94
(7) Approaches (including Retaining walls/Reinforced Earth wall, stone pitching and protection works)
0.12%
C.1- Deleted
C.2-New Elevated Section/Flyovers/ Grade Separators
a)Flyover
(1) Foundation 0.44%
(2) Sub-structure 0.32%
(3) Super-structure (including bearings) 0.42%
(4) Wearing Coat including expansion joints
0.12%
(5) Miscellaneous Items like hand rails, crash barriers, road markings etc.) 0.02%
(6) Wing walls/return walls 0.03%
(7) Approaches (including Retaining walls/Reinforced Earth wall, stone pitching and protection works)
0.12%
b)Viaduct
(1) Foundation 24.40%
(2) Sub-structure 17.43%
(3) Super-structure (including bearings) 21.40%
(4) Wearing Coat including expansion joints
5.58%
(5) Miscellaneous Items like hand rails, crash barriers, road markings etc.) 0.91%
(6) Wing walls/return walls
(7) Approaches (including Retaining walls/Reinforced Earth wall, stone pitching and protection works)
c)Interchange
(1) Foundation 7.55%
(2) Sub-structure 5.39%
(3) Super-structure (including bearings) 6.62%
(4) Wearing Coat including expansion joints
1.73%
(5) Miscellaneous Items like hand rails, crash barriers, road markings etc.) 0.28%
(6) Wing walls/return walls
(7) Approaches (including Retaining walls/Reinforced Earth wall, stone pitching and protection works)
d)VOP
(1) Foundation 2.02%
(2) Sub-structure 1.44%
(3) Super-structure (including bearings) 1.77%
(4) Wearing Coat including expansion joints
0.46%
MSRDC, Maharashtra Schedules to Concession Agreement
Construction of Nagpur- Mumbai Super Communication Expressway (Package-16) from Km 664.479
to Km 701.479 on EPC mode 95
(5) Miscellaneous Items like hand rails, crash barriers, road markings etc.) 0.07%
(6) Wing walls/return walls 0.00%
(7) Approaches (including Retaining walls/Reinforced Earth wall, stone pitching and protection works)
0.00%
Tunnel Works
13.25%
Tunnel work including protection, pavement layers work and installing lighting system complete
(1) Excavation and Primary Lining 61.00%
(2) Final Lining 19.00%
(3) Pavement, Drainage, Lighting works etc.
11.00%
(4) Testing of Tunnels and final finishing 9.00%
Other works
20.32%
(1)Traffic Signs, Markings and Others Appurtenances
15.05%
(2) Drainage and Protection works 5.78%
(3)Toll Plaza 4.06%
(4) Utility Corridor 41.76%
(5) Administrative Building 0.44%
(6) Electrical work -Highway lighting 1.12%
(7) Rest Area 0.00%
(8) Site Clearance and Dismantling 1.17%
(9) Interchange
(i) Earthwork up to top of the sub-grade 4.59%
(ii) Sub Base Course 4.19%
(iii) Non-Bituminous Base Course 2.14%
(iv) Bituminous Base Course 3.67%
(v) Wearing Coat 0.40%
(vi) cement Concrete pavement 15.61%
MSRDC, Maharashtra Schedules to Concession Agreement
Construction of Nagpur- Mumbai Super Communication Expressway (Package-16) from Km 664.479
to Km 701.479 on EPC mode 96
1.3 Procedure of estimating the value of work done
1.3.1 Road works including approaches to minor bridges, Major Bridges and Structures (excluding service roads).
Procedure for estimating the value of road work done shall be as follows:
Stage of Payment Percentage - weightage
Payment Procedure
A-Deleted
B.1- Construction of 6-lane+Paved shoulder Pavement (Rigid pavement)
Unit of measurement is linear length. Payment of each stage shall be made on pro rata basis on completion of a stage in full length or 5(five)
km. length, whichever is less. (1) Earthwork up to top of the sub-grade 45.24%
(2) Sub Base Course 5.91%
(3) Dry Lean Concrete(DLC) Course 6.99%
(4) Pavement Quality Control (PQC) Course 31.59%
C.1- Reconstruction/ New service road (Flexible pavement)
Unit of measurement is linear length. Payment of each stage shall be made on pro rata basis on completion of a stage in full length or 5(five) km. length, whichever is less.. (1) Earthwork up to top of the
sub-grade 1.98%
(2) Sub Base Course 1.32%
(3) Non-Bituminous Course 1.06%
(4) Bituminous Base Course 1.91%
(5) Wearing Coat 0.29%
D- Re-Construction and New culverts on existing road, realignments, bypasses: (1) Culverts (length < 6m)
3.70%
Cost of each culvert shall be determined on pro rata basis with respect to the total number of culverts. Payment shall be made on the completion of at least five culverts.
@.For example, if the total length of bituminous work to bedoneis100km, the cost
per km of bituminous work shall be determined as follows:
Cost per km =P x Weightage for road work x Weightage for bituminous work (1/L)
Where, P= Contract Price
L =Total length in km
Similarly, the rates per km for stages (1), (2) and (4) above shall be worked out.
MSRDC, Maharashtra Schedules to Concession Agreement
Construction of Nagpur- Mumbai Super Communication Expressway (Package-16) from Km 664.479
to Km 701.479 on EPC mode 97
1.3.2 Minor Bridge works, Overpass and Underpass
Procedure for estimating the value of Minor Bridge work sand of Overpass and Underpass shall be as stated in table
Stage of Payment Weightage Payment Procedure
1 2 3
A.2- New minor bridges
Cost of each minor bridge shall be determined on pro rata basis with respect to the total linear length of the minor bridges. Payment shall be made on the completion of widening & repair works of a minor bridge.
a)Minor Bridges
(1) Foundation +Sub- structure: On completion of the foundation work including foundations for wing and return walls, abutments, piers upto the abutment/pier cap.
23.81%
(i) Foundation +Sub- Structure: sub-structure shall be made on pro-rata basis on completion of a stage i.e. not less than 25% of the scope of foundation +sub-structure of each bridge subject to completion of atleast two foundations along with substructure upto abutment/pier cap level of each bridge. In case where load testing is required for foundation, the trigger of first payment shall include load testing also where specified.
(2) Super-structure: On completion of the super- structure in all respects including wearing coat, bearings, expansion joints, hand rails, crash barriers, road signs & markings, tests on completion etc. complete in all respect.
6.61%
(ii) Super-structure: Payment shall be made on prorata basis on completion of a stage i.e. completion of superstructure of at least one span in all respects as specified in the column of “Stage of Payment” in this sub-clause.
(3) Approaches: On completion of approaches including Retaining walls, stone pitching, protection works complete in all respect and fit for use.
2.65%
(iii) Approaches: Payment shall be made on pro-rata basis on completion of a stage i.e. completion of approaches in all respect as specified in the column of “Stage of Payment” in this sub-clause.
(4) Guide Bunds and River Training Works: On completion of Guide Bunds and river Training Works complete in all respects
0.00%
(iv) Guide Bonds and River Training Works: Payment shall be made on prorata basis on completion of a stage i.e. completion of Guide Bunds and River training Works in all respects as specified.
b)Canal Bridges
(1) Foundation +Sub- structure: On completion of the foundation work including foundations for wing and return walls, abutments, piers upto the abutment/pier cap.
0.00%
(i) Foundation +Sub- Structure: sub-structure shall be made on pro-rata basis on completion of a stage i.e. not less than 25% of the scope of foundation +sub-structure of each bridge subject to completion of atleast two foundations along with substructure upto abutment/pier cap level of each bridge. In case where load testing is required for foundation, the trigger of first payment shall include load testing also where
MSRDC, Maharashtra Schedules to Concession Agreement
Construction of Nagpur- Mumbai Super Communication Expressway (Package-16) from Km 664.479
to Km 701.479 on EPC mode 98
specified.
(2) Super-structure: On completion of the super- structure in all respects including wearing coat, bearings, expansion joints, hand rails, crash barriers, road signs & markings, tests on completion etc. complete in all respect.
0.00%
(ii) Super-structure: Payment shall be made on prorata basis on completion of a stage i.e. completion of superstructure of at least one span in all respects as specified in the column of “Stage of Payment” in this sub-clause.
(3) Approaches: On completion of approaches including Retaining walls, stone pitching, protection works complete in all respect and fit for use.
0.00%
(iii) Approaches: Payment shall be made on pro-rata basis on completion of a stage i.e. completion of approaches in all respect as specified in the column of “Stage of Payment” in this sub-clause.
(4) Guide Bunds and River Training Works: On completion of Guide Bunds and river Training Works complete in all respects
0.00%
(iv) Guide Bunds and River Training Works: Payment shall be made on prorata basis on completion of a stage i.e. completion of Guide Bunds and River training Works in all respects as specified.
B.1-Deleted
0.00%
Underpasses/ Overpasses
0.00%
Cost of each underpass/overpass shall be determined on pro rata basis with respect to the total linear length of the underpasses/overpasses. Payment shall be made on the completion of widening & repair works of a underpass/overpass.
B.2- Underpasses/ overpasses
0.00%
a)PUP 0.00%
(1) Foundation +Sub- Structure: On completion of the foundation work including foundations for wing and return walls, abutments, piers upto the abutment/pier cap.
19.14%
(i) Foundation +Sub- structure: Cost of each Underpass/Overpass shall be determined on pro rata basis with respect to the total linear length (m) of the Underpasses/Overpasses. Payment against foundation + sub-stmcture shall be made on pro-rata basis on completion of a stage i.e. not less than 25% of the scope of foundation +sub- structure of each Underpasses/Overpasses subject to completion of atleast two foundations along with sub-structure upto abutment/pier cap level each underpass/overpass. In case where load testing is required for foundation, the trigger of first payment shall include load testing also where specified.
MSRDC, Maharashtra Schedules to Concession Agreement
Construction of Nagpur- Mumbai Super Communication Expressway (Package-16) from Km 664.479
to Km 701.479 on EPC mode 99
(2) Super-structure: On completion of the super- structure in all respects including wearing coat, bearings, expansion joints, hand rails, crash barriers, road signs Wearing Coat (a) in case of Overpass- wearing coat including expansion joints complete in all respects as specified and (b) in case of underpass- rigid pavement including drainage facility complete in all respects as specified as specified.completion etc. complete in all respect.& markings, tests on
11.73%
(ii) Super-structure: Payment shall be made on prorata basis on completion of a stage i.e. completion of superstructure of atleast one span in all respects as specified in the column of “Stage of Payment” in this sub-clause.
(3) Approaches: On completion of approaches including Retaining walls/ Reinforced Earth walls, stone pitching, protection works complete in all respect and fit for use.
0.00%
(iii) Approaches: Payment shall be made on pro-rata basis on completion of a stage i.e. completion of approaches in all respect as specified.
b)VUP
0.00%
(1) Foundation +Sub- Structure: On completion of the foundation work including foundations for wing and return walls, abutments, piers upto the abutment/pier cap.
22.36%
(i) Foundation +Sub- structure: Cost of each Underpass/Overpass shall be determined on pro rata basis with respect to the total linear length (m) of the Underpasses/Overpasses. Payment against foundation + sub-stmcture shall be made on pro-rata basis on completion of a stage i.e. not less than 25% of the scope of foundation +sub- structure of each Underpasses/Overpasses subject to completion of atleast two foundations along with sub-structure upto abutment/pier cap level each underpass/overpass. In case where load testing is required for foundation, the trigger of first payment shall include load testing also where specified.
MSRDC, Maharashtra Schedules to Concession Agreement
Construction of Nagpur- Mumbai Super Communication Expressway (Package-16) from Km 664.479
to Km 701.479 on EPC mode 100
(2) Super-structure: On completion of the super- structure in all respects including wearing coat, bearings, expansion joints, hand rails, crash barriers, road signs Wearing Coat (a) in case of Overpass- wearing coat including expansion joints complete in all respects as specified and (b) in case of underpass- rigid pavement including drainage facility complete in all respects as specified as specified.completion etc. complete in all respect.& markings, tests on
13.70%
(ii) Super-structure: Payment shall be made on prorata basis on completion of a stage i.e. completion of superstructure of atleast one span in all respects as specified in the column of “Stage of Payment” in this sub-clause.
(3) Approaches: On completion of approaches including Retaining walls/ Reinforced Earth walls, stone pitching, protection works complete in all respect and fit for use.
0.00%
(iii) Approaches: Payment shall be made on pro-rata basis on completion of a stage i.e. completion of approaches in all respect as specified.
c)LVUP
0.00%
(1) Foundation +Sub- Structure: On completion of the foundation work including foundations for wing and return walls, abutments, piers upto the abutment/pier cap.
0.00%
(i) Foundation +Sub- structure: Cost of each Underpass/Overpass shall be determined on pro rata basis with respect to the total linear length (m) of the Underpasses/Overpasses. Payment against foundation + sub-stmcture shall be made on pro-rata basis on completion of a stage i.e. not less than 25% of the scope of foundation +sub- structure of each Underpasses/Overpasses subject to completion of atleast two foundations along with sub-structure upto abutment/pier cap level each underpass/overpass. In case where load testing is required for foundation, the trigger of first payment shall include load testing also where specified.
MSRDC, Maharashtra Schedules to Concession Agreement
Construction of Nagpur- Mumbai Super Communication Expressway (Package-16) from Km 664.479
to Km 701.479 on EPC mode 101
(2) Super-structure: On completion of the super- structure in all respects including wearing coat, bearings, expansion joints, hand rails, crash barriers, road signs Wearing Coat (a) in case of Overpass- wearing coat including expansion joints complete in all respects as specified and (b) in case of underpass- rigid pavement including drainage facility complete in all respects as specified as specified.completion etc. complete in all respect.& markings, tests on
0.00%
(ii) Super-structure: Payment shall be made on prorata basis on completion of a stage i.e. completion of superstructure of atleast one span in all respects as specified in the column of “Stage of Payment” in this sub-clause.
(3) Approaches: On completion of approaches including Retaining walls/ Reinforced Earth walls, stone pitching, protection works complete in all respect and fit for use.
(iii) Approaches: Payment shall be made on pro-rata basis on completion of a stage i.e. completion of approaches in all respect as specified.
1.3.3 Major Bridge (length >60m.) works and ROB/RUB/ elevated sections/flyovers including viaducts
Procedure for estimating the value of major bridge works ROB/RUB/ elevated
sections/flyovers including viaducts shall be as stated in following table
Stage of Payment Weightage Payment Procedure
1 2 3
A.I- Deleted
A.2- New Major Bridges
(i) Foundation
0.00%
(i) Foundation: Cost of each Major Bridge shall be determined on pro rata basis with respect to the total linear length (m) of the Major Bridge. Payment against foundation shall be made on pro-rata basis on completion of a stage i.e. not less than 25% of the scope of foundation of the major Bridge subject to completion of atleast two foundations of the major Bridge.In case where load testing is required for foundation, the trigger of first payment shall include load testing also where specified.
MSRDC, Maharashtra Schedules to Concession Agreement
Construction of Nagpur- Mumbai Super Communication Expressway (Package-16) from Km 664.479
to Km 701.479 on EPC mode 102
(ii) Sub-structure
0.00%
(ii) Sub-Structure:. Payment against Sub-structure shall be made on pro-rata basis on completion of a stage i.e. not less than 25% of the scope of sub-structure of the major bridge subject to completion of atleast two sub-structures of abutments/piers upto abutment/pier cap level of the major bridge.
(iii) Super-structure (including bearings)
0.00%
(iii) Super-structure: Payment shall be made on pro- rata basis on completion of a stage i.e. completion of super- structure including bearings of atleast one span in all respects as specified.
(iv) Wearing Coat including expansion joints
0.00%
(iv) Wearing Coat: Payment shall be made on completion of wearing coat including expansionjoints complete in all respects as specified.
(v) Miscellaneous Items like hand rails, crash barriers, road markings etc. 0.00%
(v) Miscellaneous: Payments shall be made on completion of all miscellaneous works like hand rails, crash barriers, road markings etc. complete in all respects as specified.
(vi) Wing walls/return walls
0.00%
(vi) Wing walls/return walls: Payments shall be made on completion of all wing walls/return walls complete in all respects as specified.
(vii) Guide Bunds, River Training works etc.
0.00%
(vii) Guide Bunds, River Training works: Payments shall be made on completion of all guide bunds/river training works etc. complete in all respects as specified.
(viii) Approaches (including Retaining walls, stone pitching and protection works) 0.00%
(viii) Approaches: Payments shall be made on completion of both approaches including stone pitching, protection works, etc. complete in all respects as specified.
B.1-Deleted
(viii) Approaches (including Retaining walls, stone pitching and protection works) 0.00%
(viii) Approaches: Payments shall be made on completion of both approaches including stone pitching, protection works, etc. complete in all respects as specified.
B.2 - New (a) ROB (b) RUB
MSRDC, Maharashtra Schedules to Concession Agreement
Construction of Nagpur- Mumbai Super Communication Expressway (Package-16) from Km 664.479
to Km 701.479 on EPC mode 103
(i) Foundation
0.46%
(i) Foundation: Cost of each ROB/RUB shall be determined on pro rata basis with respect to the total linear length (m) of the ROBs/RUBs. Payment against foundation shall be made on pro-rata basis on completion of a stage i.e. not less than 25% of the scope of foundation of the ROB/RUB subject to completion of atleast two foundations of the ROB/RUB. In case where load testing is required for foundation, the trigger of first payment shall include load testing also where specified.
(ii) Sub-structure
0.32%
(ii) Sub-Structure:. Payment against Sub-structure shall be made on pro-rata basis on completion of a stage i.e. not less than 25% of the scope of sub-structure of the ROB/RUB subject to completion of atleast two sub-structures of abutments/piers upto abutment/pier cap level of the ROB/RUB.
(iii) Super-structure (including bearings)
0.45%
(iii) Super-structure: Payment shall be made on pro- rate basis on completion of a stage be. ecmpletion of super- structure including bearings of atleast one span in all respects as specified.
(iv) Wiring Coat including expansion joints in case of ROB. In case of RUB, rigid pavement under RUB including drainage facility as specified.
0.12%
Wearing Coat: Payment shaH be made on completion of (a) in case of ROB- wearing coat including expansion joints complete in all respects as specified and (b) in case of RUB- rigid pavement under RUB including drainage facility |complete in all respects as specified as specified
(v) Miscellaneous Items like hand rails, crash barriers, road markings etc. 0.02%
(v) Miscellaneous: Payments shall be made on completion of all miscellaneous works like hand rails, crash barriers, road markings etc. complete in all respects as specified
(vi) Wing walls/return walls
0.02%
(vi) Wing walls/return walls: Payments shall be made on completion of all wing walls/ret^ walls complete in all respects as specified.
(vii) Approaches (including Retaining walls, stone pitching and protection works) 0.02%
(vii) Approaches: Payments shall be made on completion of both approaches including stone pitching, protection works, etc. complete in all respects as specified.
C.1- Deleted
C2 -New Elevated Section / Flyovers/Grade Separators
a)Flyover
MSRDC, Maharashtra Schedules to Concession Agreement
Construction of Nagpur- Mumbai Super Communication Expressway (Package-16) from Km 664.479
to Km 701.479 on EPC mode 104
(i) Foundation
0.44%
(i) Foundation; Cost of each Structure shall be determination pro rata basis with respect to the total Linear length (m) of the structures. Payment against foundation shall be made on pro-rata basis on completion of a stage i.e. not less than 25% of the scope of foundation of the structure subject to completion of at least two foundations of the structure. In case where load testing is required for foundation, the trigger of first payment shall include load testing also where specified.
(ii) Sub-structure
0.32%
(ii) Sub-Structure: Payment against Sub-structure shall be made on pro-rata basis on completion of a stage i.e. not less than 25% of the scope of sub-structure of the structure subject to completion of at least two sub-structures of abutments/piers upt0 abutment/pier cap level of the structure
(iii) Super-structure (including bearings)
0.42%
(iii) Super-structure: Payment shall be made on pro- rata basis on completion of a stage i.e. completion of super- structure including bearings of at least one span in all respects as specified.
(iv) Wearing Coat including expansion joints
0.12%
(iv) Wearing Coat: Payment shall be made on comp1et«on of wearing coat includmg expansion Joints complete in all respects as specified.
(v) Miscellaneous Items like hand rails, crash barriers, road markings etc 0.02%
(v) Miscellaneous: Payments shall be made on completion of all miscellaneous works like hand rails, crash barriers, road markings etc. complete in all respects as specified.
(vi) Wing walls/return walls
0.03%
(vi) Wing walls/return walls: Payments shall be made on completion of all wing walls/return walls complete in all respects as specified.
(vii) Approaches (including Retaining walls/Reinforced Earth wall, stone pitching and protection works)
0.12%
(vii) Approaches: Payments shall be made on completion of both approaches including stone pitching, protection works, etc. complete in all respects as specified
b)Viaduct
(i) Foundation
24.40%
(i) Foundation; Cost of each Structure shall be determination pro rata basis with respect to the total Linear length (m) of the structures. Payment against foundation shall be made on pro-rata basis on completion of a stage i.e. not less than 25% of the scope of foundation of the structure subject to completion of at least two foundations of the structure. In case where load testing is required for foundation, the trigger of first payment shall include load testing also where specified.
MSRDC, Maharashtra Schedules to Concession Agreement
Construction of Nagpur- Mumbai Super Communication Expressway (Package-16) from Km 664.479
to Km 701.479 on EPC mode 105
(ii) Sub-structure
17.43%
(ii) Sub-Structure: Payment against Sub-structure shall be made on pro-rata basis on completion of a stage i.e. not less than 25% of the scope of sub-structure of the structure subject to completion of at least two sub-structures of abutments/piers upt0 abutment/pier cap level of the structure
(iii) Super-structure (including bearings)
21.40%
(iii) Super-structure: Payment shall be made on pro- rata basis on completion of a stage i.e. completion of super- structure including bearings of at least one span in all respects as specified.
(iv) Wearing Coat including expansion joints
5.58%
(iv) Wearing Coat: Payment shall be made on comp1et«on of wearing coat includmg expansion Joints complete in all respects as specified.
(v) Miscellaneous Items like hand rails, crash barriers, road markings etc 0.91%
(v) Miscellaneous: Payments shall be made on completion of all miscellaneous works like hand rails, crash barriers, road markings etc. complete in all respects as specified.
(vi) Wing walls/return walls
0.00%
(vi) Wing walls/return walls: Payments shall be made on completion of all wing walls/return walls complete in all respects as specified.
(vii) Approaches (including Retaining walls/Reinforced Earth wall, stone pitching and protection works)
0.00%
(vii) Approaches: Payments shall be made on completion of both approaches including stone pitching, protection works, etc. complete in all respects as specified
c)Interchange
(1) Foundation
7.55%
(i) Foundation; Cost of each Structure shall be determination pro rata basis with respect to the total Linear length (m) of the structures. Payment against foundation shall be made on pro-rata basis on completion of a stage i.e. not less than 25% of the scope of foundation of the structure subject to completion of at least two foundations of the structure. In case where load testing is required for foundation, the trigger of first payment shall include load testing also where specified.
(2) Sub-structure
5.39%
(ii) Sub-Structure: Payment against Sub-structure shall be made on pro-rata basis on completion of a stage i.e. not less than 25% of the scope of sub-structure of the structure subject to completion of at least two sub-structures of abutments/piers upt0 abutment/pier cap level of the structure
(3) Super-structure (including bearings)
6.62%
(iii) Super-structure: Payment shall be made on pro- rata basis on completion of a stage i.e. completion of super- structure including bearings of at least one span in all respects as specified.
MSRDC, Maharashtra Schedules to Concession Agreement
Construction of Nagpur- Mumbai Super Communication Expressway (Package-16) from Km 664.479
to Km 701.479 on EPC mode 106
(4) Wearing Coat including expansion joints
1.725%
(iv) Wearing Coat: Payment shall be made on comp1et«on of wearing coat includmg expansion Joints complete in all respects as specified.
(5) Miscellaneous Items like hand rails, crash barriers, road markings etc.) 0.280%
(v) Miscellaneous: Payments shall be made on completion of all miscellaneous works like hand rails, crash barriers, road markings etc. complete in all respects as specified.
(6) Wing walls/return walls
0.000%
(vi) Wing walls/return walls: Payments shall be made on completion of all wing walls/return walls complete in all respects as specified.
(7) Approaches (including Retaining walls/Reinforced Earth wall, stone pitching and protection works)
0.000%
(vii) Approaches: Payments shall be made on completion of both approaches including stone pitching, protection works, etc. complete in all respects as specified
d)VOP
(1) Foundation
2.02%
(i) Foundation; Cost of each Structure shall be determination pro rata basis with respect to the total Linear length (m) of the structures. Payment against foundation shall be made on pro-rata basis on completion of a stage i.e. not less than 25% of the scope of foundation of the structure subject to completion of at least two foundations of the structure. In case where load testing is required for foundation, the trigger of first payment shall include load testing also where specified.
(2) Sub-structure
1.44%
(ii) Sub-Structure: Payment against Sub-structure shall be made on pro-rata basis on completion of a stage i.e. not less than 25% of the scope of sub-structure of the structure subject to completion of at least two sub-structures of abutments/piers upt0 abutment/pier cap level of the structure
(3) Super-structure (including bearings)
1.77%
(iii) Super-structure: Payment shall be made on pro- rata basis on completion of a stage i.e. completion of super- structure including bearings of at least one span in all respects as specified.
(4) Wearing Coat including expansion joints
0.46%
(iv) Wearing Coat: Payment shall be made on completion of wearing coat including expansion Joints complete in all respects as specified.
(5) Miscellaneous Items like hand rails, crash barriers, road markings etc.)
0.07%
(v) Miscellaneous: Payments shall be made on completion of all miscellaneous works like hand rails, crash barriers, road markings etc. complete in all respects as specified.
(6) Wing walls/return walls
0.00%
(vi) Wing walls/return walls: Payments shall be made on completion of all wing walls/return walls complete in all respects as specified.
MSRDC, Maharashtra Schedules to Concession Agreement
Construction of Nagpur- Mumbai Super Communication Expressway (Package-16) from Km 664.479
to Km 701.479 on EPC mode 107
(7) Approaches (including Retaining walls/Reinforced Earth wall, stone pitching and protection works) 0.00%
(vii) Approaches: Payments shall be made on completion of both approaches including stone pitching, protection works, etc. complete in all respects as specified
1.3.4 Tunnel Work
Tunnel work including protection, pavement layers work and installing lighting system complete
Tunnel work including protection, pavement layers work and installing lighting system complete
(1) Excavation and Primary Lining 61.00%
Unit of measurement is linear length. Cost of each stage shall be determined on pro rata basis with respect to the total linear length of all the tunnels. Payment of each stage shall be made on pro rata basis on completion of a stage in continuous length of not less than 100 (hundred) meter.
(2) Final Lining 19.00%
(3) Pavement, Drainage, Lighting works etc. 11.00%
(4) Testing of Tunnels and final finishing 9.00%
Note: (1) In case of innovate Major Bridge projects like cable suspension/cable stayed/ Extra Dozed
and exceptionally long span bridges, the schedule may be modified as per site requirements before
bidding due approval of DG(RD)&SS, MoRT&H.
(2) The Schedule fo exclusive tunnel projects may be prepared as pe site requirements before
bidding with due approval of DG(RD)&SS, MoRT&H.
1.3.5 Other Works Stage of Payment Weightage Payment Procedure
(1)Traffic Signs, Markings and Others Appurtenances
15.05%
Unit of measurement is each completed toll plaza. Payment of each toll plaza shall be made on pro rata basis with respect to the total of all toll plazas.
(2) Drainage and Protection works
5.78% Unit of measurement is linear length in km. Payment shall be made on pro rata basis on completion of a stage in a length of not less than 10 % (ten per cent) of the total length.
(3)Toll Plaza
4.06%
(4) Utility Corridor 41.76% Payment shall be made on pro rata basis for completed facilities. (5) Administrative Building 0.44%
(6) Electrical work -Highway lighting
1.12%
(7) Rest Area 0.00%
(8) Site Clearance and Dismantling
1.17%
(9) Interchange
(i) Earthwork up to top of the sub-grade
4.59%
Unit of measurement is linear length. Payment of each stage shall be made on pro rata basis on completion of a stage in a length of not less than 10 (ten) percent of the total length.
(ii) Sub Base Course 4.19%
(iii) Non-Bituminous Base 2.14%
MSRDC, Maharashtra Schedules to Concession Agreement
Construction of Nagpur- Mumbai Super Communication Expressway (Package-16) from Km 664.479
to Km 701.479 on EPC mode 108
Course
(iv) Bituminous Base Course 3.67%
(v) Wearing Coat 0.40%
(vi) cement Concrete pavement
15.61%
Unit of measurement is linear length. Payment of each stage shall be made on pro rata basis on completion of a stage in a length of not less than 10 (ten) percent of the total length.
2 Procedure for payment for Maintenance
2.1 The cost for maintenance shall be as stated in Clause 14.1.1.
2.2 Payment for Maintenance shall be made in quarterly instalments in accordance with the provisions of Clause 19.7.
MSRDC Schedules
Construction of Nagpur Mumbai Super Communication Expressway (Package 16) from km
664.479to km 701.479 on EPC Mode 109
SCHEDULE-I (See Clause 10.2.4)
DRAWINGS
1. Drawings
In compliance of the obligations set forth in Clause 10.2 of this Agreement, the Contractor
shall furnish to the Authority’s Engineer, free of cost, all Drawings listed in Annex-I of this
Schedule-I.
2. Additional Drawings
If the Authority’s Engineer determines that for discharging its duties and functions under this
Agreement, it requires any drawings other than those listed in Annex-I, it may by notice
require the Contractor to prepare and furnish such drawings forthwith. Upon receiving a
requisition to this effect, the Contractor shall promptly prepare and furnish such drawings to
the Authority’s Engineer, as if such drawings formed part of Annex- I of Schedule-I.
MSRDC Schedules
Construction of Nagpur Mumbai Super Communication Expressway (Package 16) from km
664.479to km 701.479 on EPC Mode 110
Annex-I
(Schedule-I)
LIST OF DRAWINGS
[Note: The Authority shall describe in this Annex-I, all the Drawings that the Contractor is required to
furnish under Clause 10.2.]
1. TheProjectExpresswaydrawings,asdefinedinClause1.1,Definitions,Article1,DefinitionsandInte
rpretation,Part-I:Preliminary,oftheContractAgreement shall consist:
a) Working Drawings of all the components/elements of the Project Expressway as
determined by Authority Engineer, and
b) As-built drawings for the Project Expressway components/elements as
determined by AE. As-built drawings shall be duly certified by Authority
Engineer.
2. A broad list of the drawings of the various components/elements of the Project
Expressway, service road and project facilities required to be submitted by the Contractor
is given below:
a) Drawings of horizontal alignment, vertical profile, and cross sections
b) Drawings of cross drainage works including major and minor bridges and culverts.
c) Drawings of interchanges, major intersections, grade separators, Underpasses,
and ROB’s
d) Drawings of toll plaza layout, toll collection systems, and roadway near toll plaza
e) Drawings of Control Centre
f) Drawings of bus-bay, and bus shelters with furniture, and drainage system
g) Drawing of a truck parking lay bye with furniture, and drainage system
h) Drawings of road furniture items including traffic signage, markings, safety
barriers.
i) Drawings of traffic diversion plans, and traffic control measures
j) Drawings of road drainage measures
k) Drawings of typical details slope protection measures
l) Drawings of landscaping, and horticulture
m) Drawings of vehicular, and pedestrian crossings
MSRDC Schedules
Construction of Nagpur Mumbai Super Communication Expressway (Package 16) from km
664.479to km 701.479 on EPC Mode 111
n) Drawings of street lighting
o) Layout/Configuration of HTMS
p) General arrangement of Base camp and Administrative Block.
MSRDC Schedules
Construction of Nagpur Mumbai Super Communication Expressway (Package 16) from km
664.479to km 701.479 on EPC Mode 112
SCHEDULE- J (See Clause 10.3.2)
PROJECT COMPLETION SCHEDULE
1. Project Completion Schedule
During construction period, the Contractor shall comply with the requirements set forth in this
Schedule J for each of the Project Milestones and the Scheduled Completion Date. Within 15
(fifteen) days of the date of each Project Milestone, the Contractor shall notify the Authority of
such compliance along with necessary particulars thereof.
2. Project Milestone - I
2.1. Project Milestone - I shall occur on the date falling on the 360th (Three Hundred and Sixth)
day from the Appointed Date (the “Project Milestone - I”).
2.2. Prior to the occurrence of Project Milestone - I, the Contractor shall have commenced
construction of the Project Expressway and submitted to the Authority duly and validly
prepared Stage Payment Statements completion schedule in reference to Schedule - H
Items, Stages and Sub-stages payment statements for an amount not less than 10% (ten per
cent) of the Contract Price.
3. Project Milestone – II
3.1. Project Milestone - II shall occur on the date falling on the 540th (Five Hundred and Fortith)
day from the Appointment Date (the “Project Milestone - II”).
3.2. Prior to the occurrence of Project Milestone - II, the Contractor shall have continued with
construction of the Project Expressway and submitted to the Authority duly and validly
prepared Stage Payment Statements for an amount not less than 40% (Forty per cent) of the
Contract Price.
MSRDC Schedules
Construction of Nagpur Mumbai Super Communication Expressway (Package 16) from km
664.479to km 701.479 on EPC Mode 113
4. Project Milestone - III
4.1. Project Milestone - III shall occur on the date falling on the 730th (Seven Hundred Thirtieth)
day from the Appointed Date (the “Project Milestone - III”).
4.2. Prior to the occurrence of Project Milestone - III, the Contractor shall have continued with
construction of the Project Expressway and submitted to the Authority duly and validly
prepared Stage Payment Statements for an amount not less than 70% (Seventy percent) of
the Contract Price.
5. Schedule Completion Date
5.1. The Schedule Completion Date shall occur on the 910th (Nine Hundred and Tenth) day from
the Appointed Date.
5.2. On or before the Scheduled Completion Date, the Contractor shall have completed
construction in accordance with this Agreement.
MSRDC Schedules
Construction of Nagpur Mumbai Super Communication Expressway (Package 16) from km
664.479to km 701.479 on EPC Mode 114
6. Extension of Time
Upon extension of any or all of the aforesaid Project Milestones or the Scheduled Completion
Date, as the case may be, under and in accordance with the provisions of this Agreement, the
Project Completion Schedule shall be deemed to have been amended accordingly.
MSRDC Schedules
Construction of Nagpur Mumbai Super Communication Expressway (Package 16) from km
664.479to km 701.479 on EPC Mode 115
SCHEDULE-K (See Clause 12.1.2)
TESTS ON COMPLETION
1. Schedule for Tests
1.1. The Contractor shall, no later than 30 (thirty) days prior to the likely completion of
construction, notify the Authority’s Engineer and the Authority of its intent to subject the
Project Expressway to Tests, and no later than 10 (ten) days prior to the actual date of Tests,
furnish to the Authority’s Engineer and the Authority detailed inventory and particulars of
all works and equipment forming part of Works.
1.2. The Contractor shall notify the Authority’s Engineer of its readiness to subject the Project
Expressway to Tests at any time after 10 (ten) days from the date of such notice, and upon
receipt of such notice, the Authority’s Engineer shall, in consultation with the Contractor,
determine the date and time for each Test and notify the same to the Authority who may
designate its representative to witness the Tests. The Authority’s Engineer shall thereupon
conduct the Tests itself or cause any of the Tests to be conducted in accordance with Article
12 and Schedule K.
2. Tests
2.1. Visual and Physical Test: The Authority’s Engineer shall conduct a visual and physical check
of construction to determine that all works and equipment forming part thereof conform to
the provisions of this Agreement. The physical tests shall include tests (to be decided with
Authority’s Engineer at the time of physical tests as per relevant IRC/ Code Manual).
2.2. Riding Quality Test: Riding quality of each lane of the carriageway shall be checked with the
help of a calibrated bump integrator and the maximum permissible roughness for purposes
of this test shall be 2,000mm (two thousand) for each kilometer.
2.3. Tests for Bridges: All major and minor bridges shall be subjected to the rebound hammer
and ultrasonic pulse velocity tests, to be conducted in accordance with the procedure
described in Special Report No. 17: 1996 of the IRC Highway Research Board on
Nondestructive Testing Techniques, at two spots in every span, to be chosen at random by
the Authority’s Engineer. Road Overbridge with a span of 15m (fifteen) or more shall also be
subjected to load testing.
2.4. Other Tests: The Authority’s Engineer may require the Contractor to carry out or cause to be
carried additional tests, in accordance with Good Industry Practice, for determining the
compliance of the Project Road with Specifications and Standards.
MSRDC Schedules
Construction of Nagpur Mumbai Super Communication Expressway (Package 16) from km
664.479to km 701.479 on EPC Mode 116
2.5. Environmental Audit: The Authority’s Engineer shall carry out a check to determine
conformity of the Project section with the environmental requirements set forth in
Applicable Laws and Applicable Permits.
2.6. Safety Audit: The Authority’s Engineer shall carry out, or cause to be carried out, a safety
audit to determine conformity of the Project Road with the safety requirements and Good
Industry Practice.
3. Agency for conducting Tests
All Tests set forth in Schedule-K shall be conducted by the Authority’s Engineer or such
other agency or person as it may specify in consultation with the Authority.
4. Completion Certificate
Upon successful completion of Tests, the Authority’s Engineer shall issue the Completion
Certificate in accordance with the provisions of Article 12.
MSRDC Schedules
Construction of Nagpur Mumbai Super Communication Expressway (Package 16) from km
664.479to km 701.479 on EPC Mode 117
SCHEDULE - L
(See Clause 12.2 and 12.4)
PROVISIONAL CERTIFICATE
1. I, _____________________________ (Name of the Authority Engineer), acting as Authority
Engineer, under and in accordance with the Agreement Dated ______________ (the
“Agreement”), for Consultancy Services for Preparation of Feasibility Study and Detailed
Project Report of Access Controlled Nagpur-Mumbai Super Communication Expressway,
Package V with construction package 16 on EPC mode.,(the “Project Expressway”) on
Engineering, Procurement, and Construction (EPC) Basis Contract”, through
_________________________________ (Name of Contractor), hereby certify that the Tests
specified in Article 12 of the Agreement have been undertaken to determine compliance of
the Project Highway with the provisions of the Agreement.
2 Works that are incomplete on account of Time Extension have been specified in the Punch
List appended hereto, and the Contractor has agreed and accepted that it shall complete all
such works in the time and manner set forth in the Agreement. In addition, certain minor
works are incomplete and these are not likely to cause material inconvenience to the Users
of the Project Expressway or affect their safety. The Contractor has agreed and accepted
that as a condition of this Provisional Certificate, it shall complete such minor works within
30 (thirty) days hereof. These minor works have also been specified in the aforesaid Punch
List.
MSRDC Schedules
Construction of Nagpur Mumbai Super Communication Expressway (Package 16) from km
664.479to km 701.479 on EPC Mode 118
3 In view of the foregoing, I am satisfied that the Project Expressway from Km ________ to
Km _________ can be safely and reliably placed in service of the Users thereof, and in
terms of the Agreement, the Project Expressway is hereby provisionally declared fit for
entry into operation on this the ____day of _____________ 20___.
ACCEPTED, SIGNED, SEALED SIGNED, SEALED AND
AND DELIVERED DELIVERED
For and on behalf of For and on behalf of
CONTRACTOR by: AUTHORITY’s ENGINEER by:
(Signature) (Signature)
MSRDC Schedules
Construction of Nagpur Mumbai Super Communication Expressway (Package 16) from km
664.479to km 701.479 on EPC Mode 119
COMPLETION CERTIFICATE
1 I/, ____________________________(Name of the Authority Engineer),acting as Authority
Engineer, under and in accordance with the Agreement Dated _________________ (the
“Agreement”), for the Consultancy Services for Preparation of Feasibility Study and
Detailed Project Report of Access Controlled Nagpur-Mumbai Super Communication
Expressway, Package V with construction package 16 on EPC mode., through
___________________________ (Name of Contractor),here by certify that the Tests in
accordance with Article 12 of the Agreement have been successfully undertaken to
determine compliance of the Project Expressway with the provisions of the Agreement,
and I am satisfied that the Project Expressway can be safely and reliably placed in service
of the Users thereof.
2 It is certified that, in terms of the fore said Agreement, all works forming part of the
Project Expressway have been completed, and the Project Expressway is here by declared
fit for entry into operation on this the ____day of_______________ 20___.
SIGNED, SEALED AND DELIVERED
For and on behalf of
Authority’s Engineer by:
(Signature)
(Name)
(Designation)
(Address)
MSRDC Schedules
Construction of Nagpur Mumbai Super Communication Expressway (Package 16) from km
664.479to km 701.479 on EPC Mode 120
SCHEDULE- M (See Clauses 14.6, 15.2 and 19.7)
PAYMENT REDUCTION FOR NON-COMPLIANCE
1. Payment Reduction for Non-Compliance with the Maintenance Requirements
1.1 Monthly lump sum payments for maintenance shall be reduced in the case of non-
compliance with the Maintenance Requirements set forth in Schedule-E.
1.2 Any deduction made on account of non-compliance with the maintenance Requirements
shall not be paid even after compliance subsequently. The deduction shall continue to be
made every month until compliance is done.
1.3 The Authority’s Engineer shall calculate the amount of payment reduction on the basis of
weightage in percentage assigned to non-conforming items as given in Paragraph 2.
2. Percentage Reductions in Lump Sum Payments
2.1 The following percentages shall govern the payment reduction:
Sl. No. Item/Defect/Deficiency Percentage
(a) Carriageway/Pavement
(i) Pot holes, Cracks, other surface defects 15%
(ii) Repair of Edges, Rutting 5%
(b) Road, Embankment, Cuttings, Shoulders
(i) Edge drop, inadequate cross fall, undulations, settlement,
potholes,ponding, obstructions 10%
(ii) Deficient slopes, raincuts, disturbed pitching, vegetation 5%
MSRDC Schedules
Construction of Nagpur Mumbai Super Communication Expressway (Package 16) from km
664.479to km 701.479 on EPC Mode 121
Sl. No. Item/Defect/Deficiency Percentage
growth, pruning of trees
(c) Bridges and Culverts
(i)
Desilting, cleaningvegetation growth,damaged pitching,
flooring, parapets, wearing course, footpaths, any damage to
foundations
20%
(ii) Any Defects in superstructures, bearings, and sub-structures 10%
(iii) Painting, repairs/replacement kerbs, railings, parapets,
guideposts/crash barriers 5%
(d) Road side Drains
(i) Cleaning and repair of drains 5%
(e) Road Furniture
(i) Cleaning, painting, replacement of road signs, delineators,
roadmarkings, 200m/km/5thkm stones 5%
(f) Miscellaneous Items
(i) Removal of dead animals, broken down/accident vehicles,
fallen trees, road blockades 10%
(ii) Any other defects in accordance with paragraph 1 5%
(g) Defects in Other Project Facilities 5%
2.2 The amount to be deducted from monthly lump-sum payment for non-compliance of
particular item shall be calculated as under:
R= (P/100) * M * (L1/L)
Where,
MSRDC Schedules
Construction of Nagpur Mumbai Super Communication Expressway (Package 16) from km
664.479to km 701.479 on EPC Mode 122
P= Percentage of particular item/defect/deficiency for deduction
M = Monthly lump-sum payment in accordance with the Bid
L1 = Non-complying length
L = Total length of the road
R = Reduction (the amount to be deducted for non-compliance for a particular
item/defect/deficiency)
The total amount of reduction shall be arrived at by summation of reductions for such
items/defects/deficiency or non-compliance.
For any defect in a part of one kilometer, the non-conforming length shall be taken as one
kilometer.
MSRDC Schedules
Construction of Nagpur Mumbai Super Communication Expressway (Package 16) from km
664.479to km 701.479 on EPC Mode 123
SCHEDULE - N
(See Clause 18.1.1)
SELECTION OF AUTHORITY’S ENGINEER
1. Selection of Authority’s Engineer
1.1. The provisions of the Model Request for Proposal for Selection of Technical Consultants,
issued by the Ministry of Finance in May 2009, or any substitute thereof shall apply for
selection of an experienced firm to discharge the functions and duties of an Authority’s
Engineer.
1.2. In the event of termination of the Technical Consultants appointed in accordance with the
provisions of Paragraph 1.1, the Authority shall appoint another firm of Technical
Consultants forthwith and may engage a government owned entity in accordance with the
provisions of Paragraph 3 of this Schedule N.
2. Terms of Reference
The Terms of Reference for the Authority’s Engineer (the “TOR”) shall substantially conform
to Annex-I of Schedule N.
3. Appointment of Government entity as Authority’s Engineer
Notwithstanding anything to the contrary contained in this Schedule, the Authority may in
its discretion appoint a government-owned entity as the Authority’s Engineer; provided that
such entity shall be a body corporate having as one of its primary functions the provision of
consulting, advisory, and supervisory services for engineering projects; provided further that
a government-owned entity which is owned or controlled by the Authority shall not be
eligible for appointment as Authority’s Engineer.
MSRDC Schedules
Construction of Nagpur Mumbai Super Communication Expressway (Package 16) from km
664.479to km 701.479 on EPC Mode 124
Annex – I
(Schedule - N)
TERMS OF REFERENCE FOR AUTHORITY’S ENGINEER
1. Scope
1.1. These Terms of Reference (the “TOR”) for the Authority’s Engineer are being specified
pursuant to the EPC Agreement dated _________________ (the “Agreement”), which has
been entered into between the Chief Engineer, MSRDC, Mumbai (the “Authority”) and
_________________ (the “Contractor”) for Consultancy Services for Preparation of
Feasibility Study and Detailed Project Report of Access Controlled Nagpur-Mumbai Super
Communication Expressway, Package V with construction package 16 on EPC mode., and a
copy of which is annexed hereto and marked as Annex-I to form part of this TOR.
1.2. The TOR shall apply to construction and maintenance of the Project Expressway.
2. Definitions and Interpretation
2.1. The words and expressions beginning with or in capital letters and not defined herein but
defined in the Agreement shall have, unless repugnant to the context, the meaning
respectively assigned to them in the Agreement.
2.2. References to Articles, Clauses and Schedules in this TOR shall, except where the context
otherwise requires, be deemed to be references to the Articles, Clauses, and Schedules of
the Agreement, and references to Paragraphs shall be deemed to be references to
Paragraphs of this TOR.
2.3. The rules of interpretation stated in Clauses 1.2, 1.3 and 1.4 of the Agreement shall apply,
mutatis mutandis, to this TOR.
3. General
3.1. The Authority’s Engineer shall discharge its duties in a fair, impartial, and efficient manner,
consistent with the highest standards of professional integrity, and Good Industry Practice.
MSRDC Schedules
Construction of Nagpur Mumbai Super Communication Expressway (Package 16) from km
664.479to km 701.479 on EPC Mode 125
3.2. The Authority’s Engineer shall perform the duties and exercise the authorityin accordance
with the provisions of this Agreement, but subject to obtainingprior written approval of the
Authority before determining:
(a) AnyTime extension
(b) Any additional cost to be paid by the Authority to the Contractor
(c) The Termination Payment or
(d) Any other matter which is not specified in (a), (b), or (c) above and which creates an
obligation or liability on either Party for a sum exceeding Rs. 5,000,000 (Rs. fifty
lakh).
3.3. The Authority’s Engineer shall submit regular periodic reports, at least once every month, to
the Authority in respect of its duties and functions under this Agreement. Such reports shall
be submitted by the Authority’s Engineer within 10 (ten) days of the beginning of every
month.
3.4. The Authority’s Engineer shall inform the Contractor of any delegation of its duties and
responsibilities to its suitably qualified and experienced personnel; provided, however, that
it shall not delegate the authority to refer any matter for the Authority’s prior approval in
accordance with the provisions of Clause 18.2.
3.5. The Authority’s Engineer shall aid and advise the Authority on any proposal for Change of
Scope under Article 13.
3.6. In the event of any disagreement between the Parties regarding the meaning, scope, and
nature of Good Industry Practice, as set forth in any provision of the Agreement, the
authority’s Engineer shall specify such meaning, scope, and nature by issuing a reasoned
written statement relying on good industry practice and authentic literature.
4. Construction Period
4.1. During the Construction Period, the Authority’s Engineer shall review the Drawings
furnished by the Contractor along with supporting data, including the geo-technical and
hydrological investigations, characteristics of materials from borrow areas and quarry sites,
topographical surveys, and the recommendations of the Safety Consultant in accordance
with the provisions of Clause 10.1.6. The Authority’s Engineer shall complete such review
MSRDC Schedules
Construction of Nagpur Mumbai Super Communication Expressway (Package 16) from km
664.479to km 701.479 on EPC Mode 126
and send its observations to the Authority and the Contractor within 15 (fifteen) days of
receipt of such Drawings; provided, however that in case of a Road Overbridge or Structure,
the aforesaid period of 15 (fifteen) days may be extended upto 30 (thirty) days. In particular,
such comments shall specify the conformity or otherwise of such Drawings with the Scope
of the Project and Specifications and Standards.
4.2. The Authority’s Engineer shall review any revised Drawings sent to it by the Contractor and
furnish its comments within 10 (ten) days of receiving such Drawings.
4.3. The Authority’s Engineer shall review the Quality Assurance Plan submitted by the
Contractor and shall convey its comments to the Contractor within a period of 21 (twenty-
one) days stating the modifications, if any, required thereto.
4.4. The Authority’s Engineer shall complete the review of the methodology proposed to be
adopted by the Contractor for executing the Works, and convey its comments to the
Contractor within a period of 10 (ten) days from the date of receipt of the proposed
methodology from the Contractor.
4.5. The Authority’s Engineer shall grant written approval to the Contractor, where necessary,
for interruption and diversion of the flow of traffic in the existing lane(s) of the Project
Expressway for purposes of maintenance during the Construction Period in accordance with
the provisions of Clause 10.4.
4.6. The Authority’s Engineer shall review the monthly progress report furnished by the
Contractor and send its comments thereon to the Authority and the Contractor within 7
(seven) days of receipt of such report.
4.7. The Authority’s Engineer shall inspect the Construction Works and the Project Expressway
and shall submit a monthly Inspection Report bringing out the results of inspections and the
remedial action taken by the Contractor in respect of defects or deficiencies. In particular,
the Authority’s Engineer shall include in its Inspection Report, the compliance of the
recommendations made by the Safety Consultant.
MSRDC Schedules
Construction of Nagpur Mumbai Super Communication Expressway (Package 16) from km
664.479to km 701.479 on EPC Mode 127
4.8. The Authority’s Engineer shall conduct the pre-construction review of manufacturer's test
reports and standard samples of manufactured materials, and such other materials as the
Authority’s Engineer may require.
4.9. For determining that the Works conform to Specifications and Standards, theAuthority’s
Engineer shall require the Contractor to carry out, or cause to be carried out, tests at such
time and frequency and in such manner as specified in the Agreement and in accordance
with Good Industry Practice for quality assurance. For purposes of this Paragraph 4.9, the
tests specified in the IRC Special Publication-11 (Handbook of Quality Control for
Construction of Roads and Runways) and the Specifications for Road and Bridge Works
issued by MORTH (the “Quality Control Manuals”) or any modification/substitution thereof
shall be deemed to be tests conforming to Good Industry Practice for quality assurance.
4.10. The Authority’s Engineer shall test check at least 20 (twenty) percent of the quantity or
number of tests prescribed for each category or type of test for quality control by the
Contractor.
4.11. The timing of tests referred to in Paragraph 4.9, and the criteria for acceptance/ rejection of
their results shall be determined by the Authority’s Engineer in accordance with the Quality
Control Manuals. The tests shall be undertaken on a random sample basis and shall be in
addition to, and independent of, the tests that may be carried out by the Contractor for its
own quality assurance in accordance with Good Industry Practice.
4.12. In the event that results of any tests conducted under Clause 11.10 establish any defects or
deficiencies in the Works, the Authority’s Engineer shall require the Contractor to carry out
remedial measures.
4.13. The Authority’s Engineer may instruct the Contractor to execute any work which is urgently
required for the safety of the Project Expressway, whether because of an accident,
unforeseeable event or otherwise; provided that in case of any work required on account of
a Force Majeure Event, the provisions of Clause 21.6 shall apply.
4.14. In the event that the Contractor fails to achieve any of the Project Milestones, the
Authority’s Engineer shall undertake a review of the progress of construction and identify
potential delays, if any. If the Authority’s Engineer shall determine that completion of the
Project Expressway is not feasible within the time specified in the Agreement, it shall
MSRDC Schedules
Construction of Nagpur Mumbai Super Communication Expressway (Package 16) from km
664.479to km 701.479 on EPC Mode 128
require the Contractor to indicate within 15 (fifteen) days the steps proposed to be taken to
expedite progress, and the period within which the Project Completion Date shall be
achieved. Upon receipt of a report from the Contractor, the Authority’s Engineer shall
review the same and send its comments to the Authority and the Contractor forthwith.
4.15. The Authority’s Engineer shall obtain from the Contractor a copy of all the Contractor’s
quality control records and documents before the Completion Certificate is issued pursuant
to Clause 12.4.
4.16. Authority’s Engineer may recommend to the Authority suspension of the whole or part of
the Works if the work threatens the safety of the Users and pedestrians. After the
Contractor has carried out remedial measure, the Authority’s Engineer shall inspect such
remedial measures forthwith and make a report to the Authority recommending whether or
not the suspension hereunder may be revoked.
4.17. In the event that the Contractor carries out any remedial measures to secure the safety of
suspended works and Users, and requires the Authority’s Engineer to inspect such works,
the Authority’s Engineer shall inspect the suspended works within 3 (three) days of receiving
such notice, and make a report to the Authority forthwith, recommending whether or not
such suspension may be revoked by the Authority.
4.18. The Authority’s Engineer shall carry out, or cause to be carried out, all the Tests specified in
Schedule-K and issue a Completion Certificate or Provisional Certificate, as the case may be.
For carrying out its functions under this Paragraph 4.18and all matters incidental thereto,
the Authority’s Engineer shall act under and in accordance with the provisions of Article 12
and Schedule-K.
5. Maintenance Period
5.1. The Authority’s Engineer shall aid and advise the Contractor in the preparation of its
monthly Maintenance Programme and for this purpose carry out a joint monthly inspection
with the Contractor.
MSRDC Schedules
Construction of Nagpur Mumbai Super Communication Expressway (Package 16) from km
664.479to km 701.479 on EPC Mode 129
5.2. The Authority’s Engineer shall undertake regular inspections, at least once every month, to
evaluate compliance with the Maintenance Requirements, and submit a Maintenance
Inspection Report to the Authority and the Contractor.
5.3. The Authority’s Engineer shall specify the tests, if any, that the Contractor shall carry out, or
cause to be carried out, for the purpose of determining that the Project Expressway is in
conformity with the Maintenance Requirements. It shall monitor and review the results of
such tests and the remedial measures, if any, taken by the Contractor in this behalf.
5.4. In respect of any defect or deficiency referred to in Paragraph 3 of Schedule- E, the
Authority’s Engineer shall, in conformity with Good Industry Practice, specify the
permissible limit of deviation or deterioration with reference to the Specifications and
Standards and shall also specify the time limit for repair or rectification of any deviation or
deterioration beyond the permissible limit.
5.5. The Authority’s Engineer shall examine the request of the Contractor for closure of any
lane(s) of the Project Expressway for undertaking maintenance/repair thereof, and shall
grant permission with such modifications, as it may deem necessary, within 5 (five) days of
receiving a request from the Contractor. Upon expiry of the permitted period of closure, the
Authority’s Engineer shall monitor the reopening of such lane(s), and in case of delay,
determine the Damages payable by the Contractor to the Authority under Clause 14.5.
6. Determination of costs and time
6.1. The Authority’s Engineer shall determine the costs, and/or their reasonableness, that are
required to be determined by it under the Agreement.
6.2. The Authority’s Engineer shall determine the period of Time Extension that is required to be
determined by it under the Agreement.
6.3. The Authority’s Engineer shall consult each Party in every case of determination in
accordance with the provisions of Clause 18.5.
MSRDC Schedules
Construction of Nagpur Mumbai Super Communication Expressway (Package 16) from km
664.479to km 701.479 on EPC Mode 130
7. Payments
7.1. The Authority’s Engineer shall withhold payments for the affected works for which the
Contractor fails to revise and resubmit the Drawings to the Authority’s Engineer in
accordance with the provisions of Clause 10.2.4 (d).
7.2. Authority’s Engineer shall -
(a) within 10 (ten) days of receipt of the Stage Payment Statement from the Contractor
pursuant to Clause 19.4, determine the amount due to the Contractor and recommend
the release of 90 (ninety) percent of the amount so determined as part payment,
pending issue of the Interim Payment Certificate.
(b) within 15 (fifteen) days of the receipt of the Stage Payment Statement referred to in
Clause 19.4, deliver to the Authority and the Contractor an Interim Payment Certificate
certifying the amount due and payable to the Contractor, after adjustments in
accordance with the provisions of Clause 19.10.
7.3. The Authority’s Engineer shall, within 15 (fifteen) days of receipt of the Monthly
Maintenance Statement from the Contractor pursuant to Clause 19.6, verify the
Contractor’s monthly statement and certify the amount to be paid to the Contractor in
accordance with the provisions of the Agreement.
7.4. The Authority’s Engineer shall certify final payment within 30 (thirty) days of the receipt of
the final payment statement of Maintenance in accordance with the provisions of Clause
19.16.
8. Other duties and functions
The Authority’s Engineer shall perform all other duties and functions as specified in the
Agreement.
MSRDC Schedules
Construction of Nagpur Mumbai Super Communication Expressway (Package 16) from km
664.479to km 701.479 on EPC Mode 131
9. Miscellaneous
9.1. A copy of all communications, comments, instructions, Drawings or Documents sent by the
Authority's Engineer to the Contractor pursuant to this TOR, and a copy of all the test results
with comments of the Authority's Engineer thereon, shall be furnished by the Authority's
Engineer to the Authority forthwith.
9.2. The Authority's Engineer shall retain at least one copy each of all Drawings and Documents
received by it, including 'as-built' Drawings, and keep them in its safe custody.
9.3. Within 90 (ninety) days of the Project Completion Date, the Authority's Engineer shall
obtain a complete set of as-built Drawings, in 2 (two) hard copies and in micro film form or
in such other medium as may be acceptable to the Authority, reflecting the Project
Expressway as actually designed, engineered and constructed, including an as-built survey
illustrating the layout of the Project Expressway and setback lines, if any, of the buildings
and structures forming part of Project Facilities; and shall hand them over to the Authority
against receipt thereof.
9.4. The Authority's Engineer, if called upon by the Authority or the Contractor or both, shall
mediate and assist the Parties in arriving at an amicable settlement of any Dispute between
the Parties.
9.5. The Authority's Engineer shall inform the Authority and the Contractor of any event of
Contractor's Default within one week of its occurrence.
MSRDC Schedules
Construction of Nagpur Mumbai Super Communication Expressway (Package 16) from km
664.479to km 701.479 on EPC Mode. 132
SCHEDULE - O
(See Clauses 19.4.1, 19.6.1, and 19.8.1)
FORMS OF PAYMENT STATEMENTS
1. Stage Payment Statement for Works
The Stage Payment Statement for Works shall state:
(a) The estimated amount for the Works executed in accordance with Clause
19.3.1subsequent to the last claim
(b) Amounts reflecting adjustments in price for the aforesaid claim
(c) The estimated amount of each Change of Scope Order executed subsequent to the
last claim
(d) Amounts reflecting adjustment in price, if any, for (c) above in accordance with the
provisions of Clause 13.2.3 (a)
(e) Total of (a), (b), (c) and (d) above
(f) Deductions:
i. Any amount to be deducted in accordance with the provisions of the
Agreement except taxes
ii. Any amount towards deduction of taxes, and
iii. Total of (i) and (ii) above
(g) Net claim: (e) – (f) (iii)
(h) The amounts received by the Contractor upto the last claim:
i. For the Works executed (excluding Change of Scope orders)
ii. For Change of Scope Orders, and
iii. Taxes deducted
2. Monthly Maintenance Payment Statement
The monthly Statement for Maintenance Payment shall state:
(a) the monthly payment admissible in accordance with the provisions of the Agreement
(b) the deductions for maintenance work not done
MSRDC Schedules
Construction of Nagpur Mumbai Super Communication Expressway (Package 16) from km
664.479to km 701.479 on EPC Mode. 133
(c) net payment for maintenance due, (a) minus (b)
(d) amounts reflecting adjustments in price under Clause 19.12, and
(e) amount towards deduction of taxes
3. Contractor’s claim for Damages Note
The Contractor shall submit its claims in a form acceptable to the Authority.
MSRDC, Maharashtra Schedules to Concession Agreement
Construction of Nagpur- Mumbai Super Communication Expressway (Package-16) from Km
664.479 to Km 701.479 on EPC mode 134
SCHEDULE-P
(See Clause 20.1)
INSURANCE
1. Insurance during Construction Period
1.1. The Contractor shall effect and maintain at its own cost, from the Appointed Date till the
date of issue of the last Completion Certificate, the following insurances forany loss or
damage occurring on account of Non-political Event of Force Majeure, Malicious Act,
Accidental Damage, Explosion, Fire, and Terrorism:
(a) Insurance of Works, Plant, and Materials and an additional sum of 15 (fifteen) per cent
of such replacement cost to cover any additional costs of and incidental to the
rectification of loss or damage including professional fees and the cost of demolishing
and removing any part of the Works and of removing debris of whatsoever nature.
(b) Insurance for the Contractor’s Equipment, and Documents brought onto the Site by the
Contractor, for a sum sufficient to provide for their replacement at the Site.
1.2 The insurance under paragraph 1.1(a)and (b) above shall cover the Authority and the
Contractor against all loss or damage from whatsoever cause arising under paragraph 1.1
other than risks which are not insurable at commercial terms.
2. Insurance for Contractor's Defects Liability
2.1. The Contractor shall effect and maintain insurance cover for the Works from the date of
issue of the Completion Certificate until the end of the Defects Liability Period for any loss
or damage for which the Contractor is liable and which arises from a cause occurring prior
to the issue of the Completion Certificate. The Contractor shall also maintain other
insurances for maximum sums as may be required under the Applicable Laws and in
accordance with Good Industry Practice.
MSRDC, Maharashtra Schedules to Concession Agreement
Construction of Nagpur- Mumbai Super Communication Expressway (Package-16) from Km
664.479 to Km 701.479 on EPC mode 135
3. Insurance against Injury to Persons and Damage to Property
3.1. The Contractor shall insure against its liability for any loss, damage, death or bodily injury, or
damage to any property (except things insured under Paragraphs 1 and 2 of this Schedule,
or to any person except persons insured under Clause 20.9), which may arise out of the
Contractor's performance of this Agreement. This insurance shall be for a limit per
occurrence of not less than the amount stated below with no limit on the number of
occurrences.
The insurance cover shall be not less than the value of the Contract Price.
3.2. The insurance shall be extended to cover liability for all loss and damage to the Authority's
property arising out of the Contractor's performance of this Agreement excluding:
(a) the Authority's right to have the construction works executed on, over, under, in or
through any land, and to occupy this land for the Works.
(b) Damage which is an unavoidable result of the Contractor's obligations to execute
the Works.
4. Insurance to be in Joint Names
The insurance under paragraphs 1 to 3 above shall be in the joint names of the Contractor
and the Authority.