general principles of contract management and fidic - Driver ...

131
www.drivertrett.com GENERAL PRINCIPLES OF CONTRACT MANAGEMENT AND FIDIC (Day 1) Hugo-Frans Bol - Managing Director [email protected] Ernst Jan de Jong – Senior Consultant [email protected]

Transcript of general principles of contract management and fidic - Driver ...

www.drivertrett.com

GENERAL PRINCIPLES OF CONTRACT MANAGEMENT AND FIDIC

(Day 1)

Hugo-Frans Bol - Managing Director [email protected]

Ernst Jan de Jong – Senior [email protected]

www.drivertrett.com

DRIVER TRETT, WHO ARE WE?

Global construction consultancy

Established in 1978

Stock exchange listed plc. – AIM (2005)

Market leader in expert witness,

planning, commercial and disputes

Network of offices across Africa,

Americas, Asia Pacific, Europe, and the

Middle East

Global reach with projects

undertaken worldwide

www.drivertrett.com

www.drivertrett.com

WHERE WE ARE

Our worldwide locations – A partner to clients all around the world

A worldwide Presence

is the heart of the Driver Group brand – and that goes for us as well!

This presence enables us to quickly offer targeted solutions that are tailored to regional requirements.

UAEDubaiAbu Dhabi

www.drivertrett.com

www.drivertrett.com

Dispute

resolution

Support

services

Commercial

and contract

management

Planning,

scheduling

programming

Provides multi-disciplinary consultancy services:

www.drivertrett.com

OUR SERVICES

www.drivertrett.com

The Group’s Expert Witness support service provider.

DIALES

Internationally experienced adjudicators,

arbitrators and mediators

World-class quantum, delay,

and technical experts for litigation

www.drivertrett.com

THE TRAINERS…

Hugo-Frans BolManaging Director

Driver Trett and Diales

in Mainland Europe.

Ernst Jan de JongSenior Consultant

Driver Trett Netherlands.

www.drivertrett.com

GOAL OF TRAINING

The goal of this training…

‘General Principles ofContract Management and FIDIC’

And yes, we will be starting from scratch!

www.drivertrett.com

08.45 – 09.00 Informal walk / dial in…

09.00 – 09.30 Training introduction

09.30 – 10.30 FIDIC introduction 1

10.30 – 10.45 Break

10.45 - 12.30 FIDIC introduction 2

12.30 - 13.30 Lunch Break

13.30 - 14.15 Theme 1: Tendering

14.15 - 15.15 Theme 2: Procurement and Subcontracting

15.15 - 15.30 Break

15.30 - 16.00 Theme 3: Setting up the Project

16.00 - 16.30 Questions and wrap up day one

www.drivertrett.com

AGENDADAY ONE

www.drivertrett.com

08.45 – 09.00 Start and conclusions Day 1...

09.00 – 10.00 Theme 4: The Engineer

10.00 – 10.15 Break

10.15 – 11:15 Theme 5: Time, Reporting

11.15 – 12.30 Theme 6: Valuation, payment

12.30 – 13.30 Lunch Break

13.30 – 14.45 Theme 7: Change!

14.45 – 15.00 Break

15.00 – 15.45 Theme 8: Trouble, claims and dispute avoidance!

15.45 – 16.15 Summary and close

AGENDADAY TWO

www.drivertrett.com

www.drivertrett.com

INTRODUCTION TO FIDIC (PART 1)

www.drivertrett.com

FIDIC

Federation of national associations of consulting engineers in the

construction business

Based in Geneva

Founded in 1913 with original founding members from France,

Belgium and Switzerland

UK joined 1949, USA joined 1958

Seen as international from 1970s and members from about 70

countries

FÉDÉRATION INTERNATIONALE DES INGÉNIEURS-CONSEILS

www.drivertrett.com

www.drivertrett.com

www.drivertrett.com

FIDIC Ambitions

High ethical standards

High professional standards

Development of engineering

profession in developing countries

FIDIC Documents

Standard Forms of Contracts –

since 1957

Guides to Standard Forms of

Contracts

Tendering procedures

Model Agreements

FIDIC

www.drivertrett.com

BASIC UNDERSTANDING

FIDIC or not?

www.drivertrett.com

STANDARD FORMS OF CONTRACT

www.drivertrett.com

GENERAL PRINCIPLES: 1

Often known by their colour i.e. red, yellow, silver, blue, gold etc.

Hence the name ‘Rainbow suite’;

Historically based on Anglo Saxon type of contracts.

So, more reliance on documentation as part of contract itself;

Drafted for general use on an international basis.

So, applicable law and ruling language needs to be agreed / stated;

Modifications may be required in some jurisdictions.

These should be included as revisions (in PCCs);

Generally accepted to be well-written, capable of being understood by users and…

They have, in principle, a balanced risk/reward allocation.

www.drivertrett.com

GENERAL PRINCIPLES: 2

Further….

They recognise there will be problems and potential for conflict

and dispute on projects but set out processes to (avoid and)

resolve them including:

Placing a significant administrative burden on the parties

with clear timelines and

Require the parties to deal with issues the moment

they occur or when they are foreseen to happen (SC 8.4).

www.drivertrett.com

FORM FOLLOWS FUNCTION

FORM FUNCTION

General Conditions of Contract (“GCCs”) Define standard terms for each of the forms of contract

Set out

the parties’ obligations,

how the contract is to be administered

Create fair and reasonable risk/reward allocation– according to FIDIC.

Price, payment Separate schedule, part of GCCs

Particular Conditions

of Contract (“PCCs”)

Formulate amendments (to be) agreed by the parties,

Tailor the GCCs to:

project requirements and

governing law requirements.

Note: refer to ‘Guidance’ for PCC-preparation

Appendix to tender Numbers and (calendar) data for this particular Contract

www.drivertrett.com

DECEMBER 5th 2017

New editions of red, yellow and silver book:

Operational experience since 1999 as a basis

‘Golden rules’ (enhanced and new in 2017 FIDIC)

More detailed contractual provisions

(Even) more emphasis on ‘notices’ and reciprocity

More importance to the engineer’s role

‘General provisions’ (→ definitions) in alphabetical order (1999-edition: thematically ordered)

www.drivertrett.com

FYI: FIDIC’S FIVE GOLDEN PRINCIPLES

The duties, rights, obligations, roles and responsibilities of all theContract Participants must be generally as implied in the GeneralConditions, and appropriate to the requirements of the Project.

The Particular Conditions must be drafted clearly andunambiguously.

The PCs must not change the balance of risk/reward allocationprovided for in the GCs.

All time periods specified in the Contract for Contract Participantsto perform their obligations must be of reasonable duration.

All formal disputes must be referred to a DisputeAvoidance/Adjudication Board (or DAB, if applicable) for aprovisionally binding decision as a condition precedent toarbitration.

1

2

3

4

5

www.drivertrett.com

THE CURRENT FIDIC STANDARD FORMS OF CONTRACT

www.drivertrett.com

CURRENT FIDIC MAIN STANDARD FORMS OF CONTRACT

Green(1999)

Blue-Green (2016)

Red (2017)

Pink (2010)

Yellow(2017)

Silver(2017)

Gold(2008)

www.drivertrett.com

PURPOSE (BLUE , RED, GREEN, PINK)

Green book:Short Form

Blue book:Dredging and Reclamation Contract

Red book:Construction Contract

Pink book:MDB Construction Contract (= Red amended for MDBs)

www.drivertrett.com

PURPOSE (YELLOW, SILVER AND GOLD)

Yellow book:Plant and Design-Build Contract

Silver book:EPC/Turnkey Contract

Gold book:DBO Contract

www.drivertrett.com

Straightforward project?

<€ 500K or <6 months

Employer Design?

Contractor design

All types of projectswith high unforeseen

risks

Little employer involvement, no major unforeseen risks

nonoyes

WHICH CONTRACT FOR WHAT SITUATION?

yes

yes

Ongoingoperation? no

no

yesyes

www.drivertrett.com

CONFIRM YOUR UNDERSTANDING: 1

www.drivertrett.com

Low High

Arrange in the order of risk to Contractor (low to high).

EXERCISE

Risk to Contractor

www.drivertrett.com

Low High

Q: But, where should the Blue Book be placed?

SOLUTION

A: It depends on the specific project

Burden of risk on Contractor

www.drivertrett.com28

CONFIRM YOUR UNDERSTANDING: 2

www.drivertrett.com

Low High

Q for each book:

1. Who has design responsibility?

2. What is the basis of valuation?

3. Who supervises the Works?

4. Where do you find the project specific data?

5. Arrange in the order of risk to Contractor

(low to high).

EXERCISE

Risk to Contractor

Employer design

Contractor design

Re-measurable

Lump Sum

Engineer

Employer’s Representative

Contract Data

Appendix to Tender

Particular Conditions

www.drivertrett.com

ANSWERS TO Q 1 - 4

Employer design

Re-measurable

Engineer

Appendix to Tender

Particular Conditions anticipated

Design responsibility project specific

Engineer

Valuation project specific

Particular Conditionsproject specific

Contract Data

Contractor design

Lump Sum

Engineer

Appendix to Tender

Particular Conditions anticipated

Employer’s Representative

Appendix to Tender

Particular Conditions anticipated

Contractor design

Lump Sum

www.drivertrett.com

CONFIRM YOUR UNDERSTANDING 3

www.drivertrett.com

EXERCISE (YELLOW BOOK 2017)

Under FIDIC contracts time and timing is very important…

1. The documents that the Contractor should expect to submit within a

period of say 28 days of Contract Award

2. The ‘things’ that the Contractor should expect to receive from the

Employer and/or his representative within say 28 days of Contract Award

www.drivertrett.com

EXERCISE – ANSWERS – 1

SC CONTENT/DELIVERABLE1.6 [Contract Agreement] says the Employer and Contractor shall enter into a Contract

Agreement within 35 (YB 1999: 28) days of the Contractor receiving the Letter of Acceptance.

4.2 [Performance Security] states that the Contractor shall provide to the Employer Performance Security.

4.3 [Contractor’s Representative] provides for the Contractor to appoint a Representative who will have the authority to act for the Contractor (including issuing and receiving communications).

8.3 [Programme] A detailed time programme (and separate report).14.4 If SC 14.4 [Schedule of Payments] applies and the Contract does not contain a

schedule of payments, the Contractor shall submit to the Engineer within 42 days of the Commencement Date, non-binding estimates of the expected payments during each quarterly period

14.2.1

If SC 14.2 [Advance Payment] applies, the Contractor shall provide to the Employer an advance payment guarantee.

19.1 [General Requirements for Insurances] requires that the relevant insuring Party shall provide to the other Party evidence that the insurances have been effected, copies of policies and evidence of payment of premiums; and give notice of such to the Engineer.

The documents that the Contractor should expect to submit within a period of say 28 days of Contract Award:

www.drivertrett.com

EXERCISE – ANSWERS - 2

The ‘things’ that the Contractor should expect to receive from the Employer and/or

his representative within say 28 days of Contract Award:

SC CONTENT/DELIVERABLE

1.6 [Contract Agreement] says that the Employer and Contractor shall enter into aContract Agreement within 35 (YB 1999: 28) days of the Contractor receiving theLetter of Acceptance.

2.1 [Right of Access to Site] says that the Employer shall give the Contractor right ofaccess to, and possession of parts of the Site as stated in the Appendix to Tender.

3.4 [Delegation by the Engineer] allows the Engineer to assign duties and / ordelegate authority to Assistants; this would include authority to communicate withthe Contractor on certain matters.

8.1 Not less than 14 (YB 1999: 7) days Employer to submit Notice of theCommencement Date

14.2 If SC 14.2 [Advance Payment] applies, the Employer shall pay the advancepayment in accordance with SC 14.7 [Payment].

19.1 [General Requirements for Insurances] requires that the relevant insuring Partyshall provide to the other Party evidence that the insurances have been effected,copies of policies and evidence of payment of premiums; and give notice of suchto the Engineer.

www.drivertrett.com

BREAK

www.drivertrett.com

INTRODUCTION TO FIDIC (PART 2)

www.drivertrett.com

OVERVIEW OF CURRENT FIDIC STANDARD FORMS OF CONTRACT

www.drivertrett.com

THE YELLOW BOOK

www.drivertrett.com

YELLOW BOOK: 1

FIDIC produces the General Conditions (21 clauses) and anticipates

separate Particular Conditions to be used (notes for guidance are

included)

Tenders issued with Employer’s Requirements (‘ER’, SC 1.1.33)

ERs must specify (cannot imply) for each part of the works:

the purpose

the scope

the design

other technical criteria

www.drivertrett.com

YELLOW BOOK: 2

Tenders issued with site data

SC 4.10 Employer to provide “all relevant data in Employer’s

possession…”

Appendix to Tender used to contain project-specific information

Forms of Letter of Tender, Contract Agreement (including Appendix to

Tender), Dispute Adjudication Agreement and Forms of Securities are

included

Letter of Acceptance signifies a contract has been entered into, or the

Contract Agreement, if no Letter of Acceptance

www.drivertrett.com

CLAUSE TITLE

1 General Provisions

2-4 The Employer, the Engineer and the Contractor

5 Design

6,7 Staff, labour, plant, materials and workmanship

8 Commencement, Delays and Suspension

9 & 10 Tests on Completion and Employer’s Taking Over

11 Defects after Taking Over

12 Tests after Completion

13 Variations and Adjustments

14 Contract Price and Payment

15 Termination by Employer

16 Suspension and Termination by Contractor

17 Care of the Works and Indemnities

18 & 19 Exceptional Events, Insurance

20 Employer’s and Contractor’s Claims

21 Disputes and Arbitration

YELLOW BOOK, GENERAL CONDITIONS

www.drivertrett.com

GENERALLY – YELLOW BOOK – 1(AS RED BOOK)

Clause 1 includes:

Definitions (Sub-Clause 1.1)

Communications shall be in writing, transmitted using specific

methods and to the addresses stated in Appendix to Tender.

Allowable electronic systems of transmission also stated in

Appendix to Tender (SC 1.3, ‘Notices and other Communications’)

Applicable law and ruling language stated in Appendix to Tender

(SC 1.4, ‘Law and Language’)

Priority of documents provisions (SC 1.5, ‘Priority of Documents’)

www.drivertrett.com

GENERALLY – YELLOW BOOK – 2(AS RED BOOK)

Employer’s role is defined in Clause 2 (‘The Employer’). This role is limited after

contract is signed. Employer is to:

provide Right of Access and possession of Site (SC 2.1),

provide reasonable assistance to the Contractor at the request of the

Contractor, for the Contractor’s application of any permits etc. (SC 2.2) and

can pursue financial claims against the Contractor (SC 20.1-a)

Engineer appointed as representative of Employer acting after contract is signed

to “carry out the duties assigned to him in the Contract” (SC 3.1, ‘The Engineer’)

SC 3.2 (‘Engineer’s Duties and Authority’) states:

“Except as otherwise stated in these conditions, whenever carrying out duties or

exercising authority, specified in or implied by the Contract, the Engineer [-]

shall be deemed to act for the Employer.”

www.drivertrett.com

GENERALLY – YELLOW BOOK – 3(AS RED BOOK)

Clause 3.7 gives the exception …

“Whenever these Conditions provide that the Engineer shall proceed under

this Sub-Clause to agree or determine any matter or Claim, the following

procedure shall apply:

SC 3.7.1 (‘Consultation to reach agreement’): “The Engineer shall consult

with both Parties [-] in an endeavour to reach agreement.”

If no timely agreement is (or can be) reached:

SC 3.7.2 (‘Engineer’s Determination’): “The Engineer shall make a fair

determination of the matter or Claim, in accordance with the Contract,

taking due regard of all relevant circumstances.”

www.drivertrett.com

GENERALLY – YELLOW BOOK – 4(AS RED BOOK)

Engineer can delegate specific duties and authority to assistants (SC 3.4, ‘Delegation

by Engineer’).

Contractor shall comply with instructions in respect of the Works given by the Engineer

(SC 3.5, ‘Engineer’s Instructions’).

Contractor appoints and communicates Contractor’s Representative who is the only

person authorised to receive instructions (SC 4.3, ‘Contractor’s Representative’).

Note: do not forget the communications rules

SC 1.3 - ‘Notices and Other Communications’,

SC 1.4 - ‘Law and Language’.

Contractor is responsible for interpreting Site Data, inspecting and examining Site and

“to the extent which was practicable (taking account of cost and time) shall be deemed

to have obtained all necessary information as to risks, contingencies and other

circumstances which may affect the Tender or Works” (SC 4.10, ‘Use of Site Data’)

www.drivertrett.com

YELLOW BOOKCONTRACTOR’S DESIGN RESPONSIBILITY

Contractor to design the Works (SC 5.1) and execute the Works [-] so the

Works shall be fit for the purposes for which they are intended (SC 4.1) as

defined and described in Employer’s Requirements

Intended purpose must be specified in the Employer’s Requirements as per

SC 1.1.33

Treatment of Errors in the Employer’s Requirements (SC 1.9) (after Contract

Award that is !) provided for by the ‘experienced contractor test’ (SC 5.1)

Resolution could be as a Variation or a claim

Procedure for the Engineer to review and / or approve submitted documents

(SC 5.2.2)

www.drivertrett.com

YELLOW BOOK – TIME AND PROGRESS: 1 (AS RED BOOK)

Contractor to commence Works on the Commencement Date and complete

within the Time for Completion (SC 8.1 and 8.2)

Contractor to submit a “detailed time programme” to the Engineer within 28

days of the notice of commencement showing all stages (SC 8.3)

Revised programmes to be submitted “whenever the Programme fails [-] to

comply with the Contract [-] the Contractor shall within 14 days [-] submit a

revised Programme” (SC 8.3)

Engineer has 21/14 days to respond to initial/revised programme and give

notice that it does not comply with the Contract (SC 8.3). No timely response:

no objection assumed

Contractor to proceed in accordance with it (SC 8.3)

www.drivertrett.com

YELLOW BOOK – TIME AND PROGRESS: 2 (AS RED BOOK)

Rate of progress provisions at SC 8.7 state:

“If, at any time:

a) actual progress is too slow to complete the Work or a Section (if any)

within the relevant Time for Completion; and / or

b) progress has fallen (or will fall) behind the Programme [-] under SC 8.3,

other than as a result of a cause listed in Sub-Clause 8.5 [Extension of

Time for Completion] ….

www.drivertrett.com

YELLOW BOOK – TIME AND PROGRESS: 3 (AS RED BOOK)

(SC 8.7 cont’d):

…then the Engineer may instruct the Contractor to submit [-]

a revised programme [-].

Unless the Engineer gives a Notice to the Contractor stating otherwise, the

Contract shall adopt these revised methods [-] at the Contractor’s risk and cost.

If these revised methods cause the Employer to incur additional costs, the

Employer shall be entitled subject to SC 20.2 [Claims for Payment and EoT] to

payment of these costs by the Contractor, in addition to Delay Damages (if any)”.

www.drivertrett.com

YELLOW BOOK – REPORTING(MAINLY AS RED BOOK)

Contractor to submit progress report (SC 4.20):

To be submitted monthly until completion of all work

Comprehensive - shall include:

a) Charts & descriptions of progress for each stage including design

b) Photographs

c) Manufacture report

d) Contractor’s personnel and equipment

e) QA documents, test results etc

f) Notices of claims

g) Safety statistics

h) Comparisons planned versus actual progress, risks and mitigation measures

www.drivertrett.com

YELLOW BOOK – COMPLETION(MAINLY AS RED BOOK)

Contractor entitled to an extension of the Time for Completion if completion

is or will be delayed for any of the stated reasons (SC 8.5)

Contractor liable for delay damages if it fails to complete within the Time for

Completion (SC 8.2)

Sum stated in the Appendix and the Contractor’s only liability for delay (SC

8.8)

Provision for Tests on Completion (Clause 9) and Tests after Completion

(Clause 12)

www.drivertrett.com

YELLOW BOOK – TAKING OVER AND DEFECTS

Employer issues Taking-Over Certificate to signify Works (or a Section) are

ready for taking over. This does not necessarily mean they are complete (SC

10.1)

Provision for Taking Over for any completed part of the Works “The

Employer shall not use any part of the Works [-] unless and until the

Engineer has issued a Taking-Over Certificate for this part” (SC 10.2)

Period for undertaking outstanding work and remedying defects (Defects

Notification Period, DNP) stated in the Appendix to Tender (SC 11.1)

Performance Certificate issued at the end of DNP confirms Employer’s

acceptance of the Works (SC 11.9)

(AS RED BOOK)

www.drivertrett.com

YELLOW BOOK – VARIATIONS

Only the Engineer (or his delegated assistants) can vary the

Works (SC 13.1).

Variations is a defined term, procedure at SC 13.3.

Value Engineering provisions are at SC 13.2.

(AS RED BOOK)

www.drivertrett.com

YELLOW BOOK – VALUATION AND PAYMENT - 1

Works to be valued on a lump sum basis (SC 14.1 (a)).

Contractor to submit a Statement to the Engineer after the end of thepayment period in the Contract data or at the end of each month.

This Statement needs to:

have a form acceptable to the Engineer,

be in hard and soft copy (and as many hard copies as stated in the

Contract Data) and

show details to substantiate the amount the Contractor deems itself to

be entitled to.

Payment at intervals stated in the Appendix.

Per 14.6, The Engineer issues Interim Payment Certificate (‘IPC’) within 28days after receipt of Statement per SC 14.3, thus certifying the monthlyinterim payments to be paid to the Contractor.

Can be withheld until Performance Security received (SC 14.6)

www.drivertrett.com

YELLOW BOOK – VALUATION AND PAYMENT - 2

The Employer pays at certain timescales (SC 14.7),

Retention rules apply (SC 14.9),

Any advance payment is subject to a guarantee and is progressively

reduced as works proceeds (SC 14.2),

Contractor entitled to financing charges for late payment (SC 14.8),

Remedies available to Contractor for failure of Engineer to certify or

Employer to pay (SC 16.1, ‘Suspension by Contractor’).

(AS RED BOOK)

www.drivertrett.com

YELLOW BOOK – EXTENSION OF TIME, COMPENSATION OF COSTS

Contractor to issue Notice whenever he considers to be entitled to more

time and / or money and within 28 days of being aware (or should have

been aware) of the cause to this entitlement. Failure to issue Notice

according to Contract in timely manner means a loss of rights to claim (SC

20.2),

Subsequent procedure for submission of any claims and Engineer’s

response also subject to timescales (SC 20.2.1 - 4),

DAAB appointed to avoid and eventually resolve disputes with subsequent

recourse to Arbitration if needed (Clause 21).

(AS RED BOOK)

www.drivertrett.com

THE SILVER BOOK

www.drivertrett.com

SILVER BOOK, GENERALLY – 1(AS YELLOW BOOK)

FIDIC produces the General Conditions (21 clauses) and anticipates separate

Particular Conditions to be used (notes for guidance are included).

Tender issued with Employer’s Requirements (‘ER’)

According to Sub-clause 1.1.31, ERs must specify (cannot imply) for each part

of the works:

The purpose

The scope

The design

Other technical criteria

www.drivertrett.com

SILVER BOOK, GENERALLY – 2(MAINLY AS YELLOW BOOK)

Tenders issued with all data for information:

Sub-clause 2.5 Employer to provide “all relevant data in the Employer’s

possession on the topography of the Site [-]” and Contractor responsible

for verification and interpretation (SC 4.10)

Appendix to Tender used to contain project-specific information.

Forms of Letter of Tender, Contract Agreement (including Appendix to Tender),

Dispute Adjudication Agreement and Forms of Securities are included.

Letter of Acceptance signifies a contract has been entered into, or the Contract

Agreement if no Letter of Acceptance.

www.drivertrett.com

CLAUSE TITLE

1 General Provisions2-4 The Employer, the Employer’s Administration and

the Contractor5 Design6-7 Staff and Labour - Plant, Materials and Workmanship8 Commencement, Delays and Suspension9-10 Tests on Completion - Employer’s Taking Over11 Defects after Taking Over12 Tests after Completion13 Variations and Adjustments14 Contract Price and Payment15 Termination by Employer16 Suspension and Termination by Contractor17 Care of the Works and Indemnities18-19 Exceptional Events - Insurance20 Employer’s and Contractor’s Claims21 Disputes and Arbitration

SILVER BOOK, GENERAL CONDITIONS

www.drivertrett.com

SILVER BOOK, GENERALLY - 1(AS YELLOW BOOK)

Clause 1 includes:

Definitions (SC 1.1),

Communications shall be in writing, transmitted using specific methods

and to the addresses stated in Appendix to Tender. Allowable electronic

systems of transmission also stated in Appendix to Tender (SC 1.3,

‘Notices and other Communications’),

Applicable law and ruling language stated in Appendix to Tender (SC

1.4, ‘Law and Language’),

Priority of documents provisions (SC 1.5).

www.drivertrett.com

SILVER BOOK, GENERALLY - 2(DIFFERENT TO YELLOW BOOK)

Employer has a limited role after contract is signed (Clause 2):

Provide right of access to and possession of Site (SC 2.1),

Provide reasonable assistance to the Contractor at the request of the

Contractor, for the Contractor’s application of any permits etc (SC 2.2),

Can pursue financial claims against the Contractor (SC 20.1).

Employer’s Representative may be appointed to act on Employer’s behalf

after contract is signed (sub-clause 3.1).

Note: prime duties restricted to monitoring progress, quality and testing.

www.drivertrett.com

SILVER BOOK, GENERALLY - 3(DIFFERENT TO YELLOW BOOK)

Sub-Clause 3.5 is formulated:

“Whenever these Conditions provide that the Employer’s Representative shall

proceed under this Sub-Clause to agree or determine any matter or Claim, the

following procedure shall apply:

SC 3.5.1 (‘Consultation to reach agreement’): “The Employer’s Representative

shall consult with both Parties [-] in an endeavour to reach agreement.”

If no timely agreement is (or can be) reached:

SC 3.5.2 (‘Determination’): “The Employer’s Representative shall make a fair

determination of the matter or Claim, in accordance with the Contract,

taking due regard of all relevant circumstances.”

www.drivertrett.com

SILVER BOOK, GENERALLY - 4(DIFFERENT TO YELLOW BOOK)

Employer or Employer’s Representative can delegate specific duties and

authority to assistants (SC 3.2, ‘Other Employer’s Personel’),

Contractor shall take instructions from the Employer or Employer’s

Representative (SC 3.4, ‘Instructions’),

Contractor to appoint Contractor’s Representative who is the only person

authorised to receive instructions on behalf of Contractor (SC 4.3,

‘Contractor’s Representative’),

Note: do not forget the communications rules:

SC 1.3 ‘Notices and Other Communications’ and

SC 1.4 ‘Law and Language’,

Contractor responsible for verifying and interpreting (site) data made

available by Employer (SC 4.10, ’Use of Site Data’).

www.drivertrett.com

SILVER BOOK, GENERALLY - 5(DIFFERENT TO YELLOW BOOK)

Contractor to execute (= design and construct) the Works so they will be fit

for the purposes for which they are intended, as defined and described in

the Employer’s Requirements (SC 4.1, ‘Contractor’s General Obligations’),

Intended purpose must be specified in the Employer’s Requirements as

defined in SC 1.1.31,

Contractor generally responsible for the accuracy and completeness of

Employer’s Requirements (SC 5.1: “The Employer shall not be responsible

for any error, inaccuracy or omission in the Employer’s Requirements [-]”),

Procedure for the Employer to review submitted documents (SC 5.2,

‘Contractor’s Documents’, SC 5.2.2, Review by Employer’).

www.drivertrett.com

SILVER BOOK - TIME AND COMPLETION(SIMILAR TO YELLOW BOOK)

Contractor to commence Works on the Commencement Date (SC 8.1) and

complete within the Time for Completion (SC 8.2),

Contractor to submit:

- an ‘initial programme’ to the Employer within 28 days of the Notice of Commencement

under SC 8.1, using programming software according to ER or acceptable to Employer

(SC 8.3),

- a ‘revised programme’ according to ‘actual progress of the Works’ when a delta occurs

between planning and progress or in case of other inconsistencies between reality and

Contracor’s obligations (SC 8.3),

Employer has 21/14 days (to initial/revised programme) to respond and

give Notice that it does not comply with the Contract (SC 8.3). Without

timely Notice: Notice of No-objection assumed,

Contractor to proceed in accordance with such Notice (SC 8.3).

www.drivertrett.com

SILVER BOOK - REPORTING(SIMILAR TO YELLOW BOOK)

Contractor to submit progress report (SC 4.20):

To be submitted monthly until completion of all work

Comprehensive - shall include:

a) Charts & descriptions of progress for each stage including design,

b) Photographs,

c) Manufacture report,

d) Contractor’s personnel & equipment,

e) QA documents, test results etc.,

f) Notices of claims,

g) Safety statistics,

h) Comparisons planned versus actual progress, risks and mitigationmeasures.

www.drivertrett.com

SILVER BOOK – PROGRAMME SLIPPAGE - 1(AS YELLOW BOOK)

Rate of progress provisions at SC 8.7 state:

“If, at any time:

a) actual progress is too slow to complete the Works or a Section (if any)

within the relevant Time for Completion; and / or

b) progress has fallen (or will fall) behind the Programme under Sub-Clause

8.3…

other than as a result of a cause listed in Sub-Clause 8.5 [‘Extension of Time

for Completion’] …

www.drivertrett.com

SILVER BOOK – PROGRAMME SLIPPAGE - 2(AS YELLOW BOOK)

SC 8.7 continued:

…then the Employer may instruct the Contractor to submit , under Sub-Clause

8.3 [‘Programme’] a revised programme describing the revised methods [-] …

Unless the Employer gives a Notice to the Contractor stating otherwise, the

Contractor shall adopt these revised methods, which may require increases in

the working hours and / or in the numbers of Contractor’s Personnel or

Goods, at the Contractor’s risk and cost.

If these revised methods cause the Employer to incur additional costs, the

Contractor shall subject to Sub-Clause 20.2 [Claims for Payment and/or EOT]

to payment of these costs by the Contractor, in addition to Delay Damages.”

www.drivertrett.com

SILVER BOOK – COMPLETION, DELAY(AS YELLOW BOOK)

Contractor entitled to an extension of the Time for Completion if

completion is or will be delayed for any of the stated causes (SC 8.5),

Contractor liable for Delay Damages if it fails to complete within the Time

for Completion (SC 8.8),

Sum stated in the Appendix and the Contractor’s only liability for delay

(SC 8.8),

Provision for Tests on Completion (Clause 9) and Tests after Completion

(Clause 12).

www.drivertrett.com

SILVER BOOK – EMPLOYER’S TAKING-OVER(AS YELLOW BOOK)

Contractor may apply for Taking-Over Certificate by giving a Notice to the Employer,

Employer shall within 28 days after Contractor’s Notice:

- (i) issue Taking-Over Certificate to signify Works (or a Section) are ready for taking

over (and minor outstanding work and defects may still be needed – not affecting the

safe use nor purpose) or

- (ii) reject application by means of a Notice (SC 10.1).

Taking over of Parts of the Works is not permitted unless agreed by the Parties (sub-

clause 10.2),

Period for undertaking outstanding work (‘DNP’) and remedying defects stated in the

Appendix to Tender (sub-clause 11.1),

Performance Certificate issued at the end of DNP confirms Employer’s acceptance of the

Works (SC 11.9).

www.drivertrett.com

SILVER BOOK – VARIATIONS(DIFFERENT TO YELLOW BOOK)

Variations is a defined term - please refer to Clause 13 ‘Variations and Adjustments’,

Only the Employer (or delegated assistants) can vary the Works (SC 13.1),

Contractor will be bound by an Instruction under SC 13.3.1 (‘Variation by Instruction’)

even in absence of consent over conditions except under conditions (SC 13.1 sub a – e),

Value Engineering is Contractor’s initiative here - if so (SC 13.2),

Condition is Employer’s benefit of the engineering proposed:

accelaration,

cost reduction,

efficiency improvement,

other benefits.

www.drivertrett.com

SILVER BOOK – VALUATION, PAYMENT - 2(DIFFERENT TO YELLOW BOOK)

Contract Price is an agreed amount of money for the execution of the

Works, eventually adjusted according to Contract (SC 1.1.10),

Works to be valued on a lump sum basis (SC 14.1 (a)),

Contractor to submit a Statement to the Employer after the end of the

payment period in the Contract data or at the end of each month.

This Statement needs to:

have a form acceptable to the Employer,

be in hard and soft copy (and as many hard copies as stated in the

Contract Data) and

show details to substantiate the amount the Contractor deems

itself to be entitled to (SC 14.3 ‘Application for Interim Payment’).

Payment at intervals (if so, SC 14.4) stated in the Appendix.

www.drivertrett.com

SILVER BOOK – VALUATION, PAYMENT - 3(DIFFERENT TO YELLOW BOOK)

Per SC 14.6, The Employer issues Interim Payment Certificate (‘IPC’)

within 28 days after receipt of Statement per SC 14.3, thus certifying

the monthly interim payments to be paid to the Contractor.

Can be withheld until Performance Security received (SC 14.6) and

retention rules apply (SC 14.9).

Any advance payment is subject to a guarantee and is progressively

reduced as works proceeds (SC 14.2).

Payment procedure is different after Taking Over Certificate is issued

(SC 14.10 to 14.13), including Final Payment Certificate.

Contractor entitled to financing charges for late payment (SC 14.8) and

remedy available to Contractor for failure of Employer to pay (SC 16.1,

‘Suspension by Contractor’): Notice + 21 days → suspension.

www.drivertrett.com

SILVER BOOK – EXTRA TIME AND MONEY(DIFFERENT TO YELLOW BOOK)

Notice of Claim shall be issued by Contractor to Employer whenever it

considers it to be entitled to more time and / or money and within 28

days of being aware (or should have been aware). Failure to comply

means a loss of rights to claim (SC 20.2.1, ‘Notice of Claim’),

Subsequent procedure for submission of any claims also subject to

timescales (SC 20.2.2, ‘Initial response’),

DAAB appointed to resolve disputes with subsequent recourse to

Arbitration if needed (Clause 21).

Conclusion under Silver Book:

Responsibility for nearly all risk with the Contractor

www.drivertrett.com

LUNCH BREAK

www.drivertrett.com

Theme 1: Tendering

www.drivertrett.com

1. TENDER STAGE (PREPARATION)

What is its main purpose?

www.drivertrett.com

PRIORITY FOR A TENDERER

The priority is for a tenderer to understand what will beexpected of all the parties involved

This includes:

Technical requirements Type and scope of works (i.e. dredging, design and build – or not) Timing and timescale

Legal considerations Type of contractual relationship (i.e. main contract, sub contract) Applicable terms and conditions (influence during tender – if so !)

Commercial aspects Method of valuing works (i.e. lump sum, re-measurable) Guarantees and payment conditions (financial stability of parties)

www.drivertrett.com

HOW IS THIS ACHIEVED?

Studying all parts of the RFQ or tender documents.

Verify all documents have been received

Verify the correct documents have been received

DEME practice:

Involve:

supporting departments (larger projects);

area personnel (small/medium sized projects) and in any case:

Legal and insurance - analysis of legal risks – LICRA

Planning engineering – variance analysis of different scenarios

Incorporating Opportunity and Risk Management (ORM).

O & R register populated during tender phase

www.drivertrett.com

ORM – DEME PRACTICE

• Main ORM tool that is used to manage O&R during tender and execution phase

O&R Register

O & R (Opportunity and Risk) REGISTER

www.drivertrett.com

What Opportunities exist at tender stage?

To understand the customer’s needs

To see whether the proposed contract describes the same thing

To influence the customer’s way of thinking

To influence the provisions of the contract (terms and conditions)

To influence the allocation of risk and/or compensation of risk

To agree the duration for undertaking the works

To agree the price for undertaking the works

To agree security of payment

Et cetera

OPPOORMOPPORTUNITIES

www.drivertrett.com

The client will have considered Risk allocation.

Remember: Risk should be allocated to the party best able to manage it.

Standard Forms of Contract (such as one of the FIDIC or BIMCO forms)

generally allocate risk reasonably and fairly.

What type of risks should be considered?

ORMRISK ALLOCATION

www.drivertrett.com

Contracting Risks (1 of 2)

1. Extent of the scope of work

2. Safety provisions

3. Provision of bonds, guarantees

4. Security for payment

5. Liabilities

6. Physical conditions and access

7. Practicality of schedule dates

8. Use of specialist suppliers/sub contractors/ third parties

9. Dispute resolution provisions

ORMMANAGEMENT OF RISK

www.drivertrett.com

Contracting Risks (2 of 2)

1. Clarity of the contract wording and provisions (no discrepancies)

2. Wording and provisions that can be easily understand by all concerned

3. Document submittals at, or just after commencement

4. Condition precedent clauses (‘ontbindende voorwaarden’)

5. Notice requirements

6. Requirement for record keeping

7. Change process

8. Claims process

ORMMANAGEMENT OF RISK

www.drivertrett.com

Contracting Risks are often indicated by:

Manner in which contract was secured (‘binnen gehaald’)

The consultants and their roles

The level of definition of the works

Feasibility (‘haalbaarheid’)

The procurement status

Financial circumstances

Political aspects

Legal / contractual

New concept

ORMMANAGEMENT OF RISK

www.drivertrett.com

Tendering contractors should consider revisions to Standard

Forms of Contract carefully:

the revisions may prevent the contract from

working in certain circumstances.

links between clauses may be broken.

ORMMANAGEMENT OF THE TENDER STAGE

www.drivertrett.com

MANAGEMENT OF THE TENDER STAGE

Other requirements:

Clarifying the responsibilities during tender:

− Document control essential – single point of communication ?

− Register of questions and answers – summarises status during negotiations

− Records of any verbal discussions and meetings – how ?

− Results of negotiations – properly captured in the contract ?

Establishing a commercial strategy for the project

www.drivertrett.com

THEME 2: PROCUREMENT AND SUBCONTRACTING

www.drivertrett.com

PROCUREMENT AND SUB-CONTRACTING (PREPARATION)

www.drivertrett.com

BE AWARE!

www.drivertrett.com

Risk should be allocated to the party best able to manage it.

In sub-contract relationships, risk that is passed on should be

stepped down.

Should opportunities be passed down too?

Sometimes opportunities and risk must be retained at main

contractor level and especially on EPC/EPCI projects.

OPPORTUNITY AND RISK SHARING

www.drivertrett.com

EXAMPLES OF TYPICAL OPPORTUNITIES AND RISKS

Extent of scope of work (includes design?) and interfaces

Safety provisions

Provision of bonds and guarantees

Practicality of programme dates within overall duration

Notice and reporting provisions

If we are main contractor, what do we want to happen with these in our subcontracts?

If we are a subcontractor, what do we want to happen with the contents of the main contract?

www.drivertrett.com

TERMS AND CONDITIONS FOR A SUB-CONTRACT - 1

Question: Which terms and conditions are to be used for a subcontract?

The ‘main’ contract conditions?

Revised ‘main’ contract conditions? If so, how to revise?

The DEME standard terms?

Revised DEME standard terms? If so, how to revise?

The phrase ‘back to back with the main contract’? If so, what

does it mean?

www.drivertrett.com

‘BACK TO BACK’

A commonly used phrase that can lead to practical problems

How can ‘applying the provisions of a main contract to a

subcontract’ work in practice? Some crucial elements:

Main Contract Price vs. Subcontract Price

Main contract conditions (timescales !, specs)

Approvals from Employer

Bonds and securities (contract price-related)

Insurance coverage

‘Back-to-back’:

no shortcut for proper drafting of sub-contracts

creates strong potential for disputes

www.drivertrett.com

EXAMPLES OF SUBCONTRACT WORDING…

• Article 3.1 says that ‘Subcontractor shall be deemed to have full knowledge

of the provisions of the Main Contract...

Contractor shall (if requested) make available a copy of the Main Contract.

Article 3.2 says ‘Subcontractor shall carry out and complete Subcontract

Works so that no act or omission of the Subcontractor shall result in

any breach of the Main Contract by the Contractor.

Article 3.3 says ‘to the extent that such obligations and liabilities relate to

the Subcontract Works, the Subcontractor shall perform the obligations

and assume the liabilities of the Contractor under the Main Contract.’

www.drivertrett.com

AN EXAMPLE OF MAIN CONTRACT WORDING…

• Article 3.4 says ‘Subcontractor shall indemnify (‘vrijwaren’) the Contractor

against any claim, arising from any breach or non observance of such

obligations or non compliance therewith.’

Article 15 (c) says that ‘Contractor must make all the terms and conditions

of Contract (as far as the same are applicable ) terms and conditions of

Subcontract and must not permit any alteration of the Subcontract without

the prior written consent of Company and must enter into a Subcontract

with the Subcontractor accordingly.’

www.drivertrett.com

TERMS AND CONDITIONS FOR A SUB-CONTRACT - 2

Again: Which terms and conditions are to be used for a subcontract?

The ‘main’ contract conditions?

Revised ‘main’ contract conditions? If so, how to revise?

The DEME standard terms?

Revised DEME standard terms? If so, how to revise?

All can work but:

in all cases, the parts of the main contract relevant to the subcontract need identifying (and possibly revising), and then be incorporated into the subcontract.

www.drivertrett.com

What if works are needed to start

prior to a contract being in place?

www.drivertrett.com

THE DILEMMA ...

Employers and Contractors are faced with time constraints in

negotiating full contract documentation;

Some work must start to meet (envisaged) milestones:

- procurement process (where there are long lead in times)

- engineering

- mobilisation

The alternative: ‘delaying contract commencement’ → envisaged

milestones will not be met

www.drivertrett.com

SOME FURTHER CONSIDERATIONS

What has caused the problem?

Did (future) Employer start its procurement process too late ?

Is it in (future) Contractor’s interest to start ?

What action needed to respect timescales ?

Create a basis (in writing) to start working to ensure

compensation for work and commitments, in both cases:

the contract will be closed as anticipated

the contract will not be closed as anticipated

www.drivertrett.com

VARIOUS OPTIONS

A mini contract for the works that are needed to start

Should be straight forward to agree and formalise

Should not need agreement of the full terms and conditions

May be standalone, or eventually merged into the full contract

A binding Letter Of Intent (‘LOI’)

This requires careful drafting

www.drivertrett.com

BE CAREFUL WITH LOI’S

LOI’s are:

often letters of comfort

(no agreement and no instruction or authorisation for any works – just

outlining intentions);

sometimes unclear or vague w.r.t. parties’ commitment

(what scope exactly?)

most likely non-binding

(not a complete offer, no acceptance, no intention to create a legal relation,

without names of legal entities)

www.drivertrett.com

Exercise 2Consider the following

Please refer to the next slides

Part 1 and Part 2

www.drivertrett.com

www.drivertrett.com

Example Letter of Intent sent by Main Contractor to Sub-Contractor

“As you know from our meeting this morning, we have just received a letter of intent from [X] for the [Y] project, which includes your [equipment].

In our turn, we are pleased to confirm that it is our intention to enter into a sub contract with [you] for your [equipment], this will be generally be on the basis of the Sub Contract document that we discussed this morning (ref…)

We also agreed that we would incorporate your final comments on the draft Sub Contract and that you would provide details of the Advance Payment Bond, on-demand Performance Bond and insurance that you can offer.

The main contract commencement date is…

Please acknowledge receipt.”

PART 1

www.drivertrett.com

Consider what this letter is saying and what your response would be

www.drivertrett.com

PART 2Consider what this letter is saying and what your response would be

www.drivertrett.com

Second example Letter of Intent sent by Main Contractor to Sub-Contractor

“This is to place a letter of intent (LOI) for [W] works to [X] ... by [Y] … strictly in accordance with the following terms and conditions and to give an authorisation to proceed immediately with the engineering, procurement and manufacturing in accordance with this requisition.”

Sections then cover matters including:

Scope and Price

Payments Terms

Delivery Terms and Date

Contract Documents

Etc.

www.drivertrett.com

BREAK

www.drivertrett.com

THEME 3: SETTING UP THE PROJECT

www.drivertrett.com

SETTING UP THE PROJECT (EXECUTION)

www.drivertrett.com

NOW, CONTRACT IS SIGNED – WE’RE IN A RISKY STADIUM !

All knowledge gained at tender stage must be transferred to project team

Strong tendency to re-do engineering process(no budget for this !)

Several urgent needs:

Baseline and SoW must be (made) clear Admin according to contracted requirements Insurance in place Procurement Project organisation aligned (resources, equipment,

subcontractors, suppliers, ….) Several deliverables due within ‘a month’ ….

www.drivertrett.com

The DEME procedure is for the O & R Register to be updated upon

contract award

Because:

the O & R profile is fixed with Contract Award (“sign off”)

contract as signed will most likely differ from first concept (as a

result of negotiations).

‘O&R register’ should further be:

kept up to date throughout contract life

incorporated into monthly reporting (both DEME policies)

ORM REVISITED

www.drivertrett.com

It’s essential to success, a good practice and a DEME policy…

‘KTP’ means a structured hand-over of knowledge gained at the

tender and pre-award stages, to the execution team

It involves: Knowledge Transfer Checklist to be populated

Knowledge Transfer Meeting to be held according to template

KNOWLEDGE TRANSFER PROCESS - 1

www.drivertrett.com

• Hand Over Checklistaims to structure the hand over between TM and PM

• Hand over checklist will be part of updated PMM

• Signed by AM/TM/PM

Tender-project transition

KNOWLEDGE TRANSFER MEETING - TEMPLATE

www.drivertrett.com

It’s essential to success, a good practice and a DEME policy

‘KTP’ means a structured hand-over of knowledge gained at the

tender and pre-award stages, to the execution team

It involves: Knowledge Transfer Checklist to be populated

Knowledge Transfer Meeting to be held according to template

Responsible, Accountable, Consulted, Informed (RACI) table to be

populated and kept up to date

KNOWLEDGE TRANSFER PROCESS - 2

www.drivertrett.com

Item Topic Description Responsible Accountable Consulted Informed

1Tender-Project Transition

1Project Responsible & Accountable

Assign ORM 'point of contact' for project Project Manager PM p.p.

Project Manager ORM department

Knowledge Transfer Meeting Define attendees Project Manager PM p.p.

Project Manager

Knowledge Transfer Meeting Sign Knowledge Transfer Checklist Project Manager Tender Manager

Project ManagerTender Manager

ORM department

O&R Register Update/manage O&R Register Project Manager PM p.p.

Project Manager ORM department (SC)

Work budget Create/update work budget Project Manager PM p.p.

Project Manager AD/BU/GMArea Controller

Contingency budget Create/update contingency budget Project Manager PM p.p.

Project Manager AD/BU/GMArea Controller

Primary Kick-Off Meeting Define attendees Project Manager PM p.p.

Project Manager DRIVE department

Primary Kick-Off Meeting Organize/prepare Primary Kick-Off meetings Project Manager PM p.p.

Project Manager

Primary Kick-Off Meeting Define mitigation strategies for O&R Project Manager PM p.p.

Project Manager DRIVE department

Operational Action log Create/update operational action log Works Manager Project Manager DRIVE department DRIVE (SC)All action holders (SC)Operational staff (SC)

Non-operational Action log Create/update non-operational action log Finance Manager Project Manager Relevant supporting departments

Core Project Management Team (SC)

RACI TABLE

www.drivertrett.com

Does this process repeat when more implementation

personnel join the project?

Does it repeat again prior to the offshore phase?

KNOWLEDGE TRANSFER PROCESS - 3

www.drivertrett.com

RELEVANCE OF THE CONTRACT

Contracts

Opportunity & Risk

Finance

Design & Engineering

Planning

Procurement and subcontracting

www.drivertrett.com

Review your contract to identify obligations and the need for project-specific

systems?

If so, what for?

Securities and guarantees; insurance requirements

Deliverables (‘tech’ and ‘non tech’)

Planning submittals

Discrepancies

Notices

Payments

Correspondence and reporting

SO, DO YOU ?

www.drivertrett.com

Have a kick off meeting with the Employer?

If so, what do you cover?

Confirmation and clarification of scope or uncertainties Agreement of formats/procedures for reporting and coordination Communication routes/details QHSE

How useful is a kick off meeting with the Employer when considering

commercial strategy for a project?

DO YOU ALSO?

www.drivertrett.com

(SNEAK PREVIEW TO TOMORROW’S:)

THEME 5:PLANNING, REPORTING

Part of Contract Management Training for DEME

Hugo-Frans Bol - Managing Director [email protected]

Ernst Jan de Jong – Senior [email protected]

www.drivertrett.com

PLANNING (EXECUTION)

www.drivertrett.com

THE PLANNING PROCESS

The Planning Process is a result of Contractor’s decision making:

What to do (scope)

How to do it (method)

When to do it (schedule)

What resources to use (staff, equipment, plant and material)

www.drivertrett.com

PLANNING AND PROGRAMMING

A programme is a project management tool used to monitor and control the project

It is not just a ‘picture’

www.drivertrett.com

CONSIDER….

Should the Contractor submit a programme (schedule) early in the

implementation stage?− Yes – to show how it intends to undertake the works

On what basis should this programme (schedule) be put together?

− It should show what was agreed in the Contract and serve as the

baseline (and: needed to substantiate any deviation → Variation)

Should the programme (schedule) be agreed?

− Contract mostly dictates: “Yes” (Baseline schedule = milestone)

but it generally shows Contractor's choices

www.drivertrett.com

THE BASELINE SCHEDULE

It should:

Reflect the contract requirements (the baseline)

Show contract milestones

Show intended sequence of works

Incorporate any resource constraints

Show the critical path

And remember:

No planning → no deviation → no variation → no compensation

www.drivertrett.com

CRITICAL PATH

The Critical Path – why is it important?

Determines the earliest completion date for the project;

Determines the earliest and latest completion dates for individual activities;

Calculates float;

Identifies which activities are important to the completion of the project;

Identifies areas of opportunity and risk;

Identifies areas where action should be taken to reduce the project

duration or recover from delays.

The Critical Path - Shortest route between work and the pub

www.drivertrett.com

PROGRESS REPORTING

Progress reporting involves:

Measuring actual progress (should mirror schedule);

Updating your plan or schedule for this actual progress;

Forecasting impact in the future;

Creates a record.

Please note:

Content and lay out defined in larger contracts (to be agreed for smaller contracts)

Content and lay out of subcontractor’s reporting needs to be in line with Main Contract

Obligations

Observe deadlines: Subcontractor → Main Contractor → Employer

www.drivertrett.com

CONTRACTOR’S PROGRESS RECORDS AND MONITORING

The need for progress records and monitoring:

Accurate assessment of status of project;

Contractual obligation;

‘Notices’ exchanged;

Record and keep result;

How deal with changes?;

Plot and compare results in a project with large scope;

Compare different trends;

Accurate and agreed records in case of dispute;

Major source of knowledge for Employer ‘at distance’ (under a Design and Build Contract).

In what situation would Contractor do not want to declare actual status ?

www.drivertrett.com

CONSIDER…

The items the Contractor has to include in its Progress Reports.

Should the Contractor prepare different Progress Reports for

internal circulation to that submitted to the Employer ?

If so, what would be the differences ?

www.drivertrett.com

OTHER REQUIRED RECORDS

These include, for example:

Correspondence exchanged;

As-built, it’s easier to do as the project progresses;

Daily reports including weather and numbers of resources;

The reasons for decisions to move resources;

Causes and effects of deviations (possibly: ‘Changes’);

And: check Contract (‘Admin requirements’) to know how and

where records need to be stored.

Remember: Subcontract in line with Main Contract activities.

www.drivertrett.com

THE END….OF DAY 1

THANK YOU!We hope you have enjoyed this presentation