Evaluating critical lines and stations considering the impact of the consequence using transit...
Transcript of Evaluating critical lines and stations considering the impact of the consequence using transit...
Hiroshi Shimamoto, Hiroshima University, Japan
Fumitaka Kurauchi, Kyoto University, Japan Jan-Dirk Schmöcker, Tokyo Institute Of Technology, Japan
Michael G H Bell, Imperial College London, UK Received: October 2007 Accepted: January 2008
Evaluating Critical Lines and Stations Considering
the Impact of the Consequence Using Transit
Assignment Model -Case Study of London’s
Underground Network
Hiroshi Shimamoto
Fumitaka Kurauchi
Jan-Dirk Schmöcker
Michael G H Bell
As the problem of full transit vehicles is encountered daily by
passengers in most of the big cities, previous research evaluated the
consequence of overcrowding in terms of on-board crowding and
passengers not being able to board with full vehicles. The impact of
overcrowding in the real world is, however, not necessarily
proportional to these numbers. This paper attempts to specify the
critical lines and stations of a network by considering the number of
passengers failing to board and attempting to evaluate its impact on
service quality and safety risks. The hypothesis is that larger stations
with wider platforms can often cope better with overcrowding than
smaller stations. Therefore a station size dependent satisfaction function is proposed, which takes values from 0 to 1. The method is
applied to London’s underground network with a number of scenarios
which show critical stations in the network if delays occur.
1. Introduction
The problem of full transit vehicles is encountered daily by
passengers in most of the big cities of the world. For example, many commuters during the morning peak-hours fail to board the transits in
London’s underground. This overcrowding leads not only to journey
unreliability through having to wait for emptier services but also to stress,
delays through passengers trying to push on overcrowded trains and even health and safety risks. The costs related to crowding and delays of its
2
public transportation network are estimated at £230m per year for the
City of London alone (Oxford Economic Forecasting, 2003). In London crowding will occur during the morning peak-hour at any working day
even if all services run as scheduled, however extreme congestion
leading to significant numbers of passengers not being able to board will
only occur if transits are delayed. This is however frequently the case; London Underground Limited publishes on their homepage that they
cancel in average 5 % of all service almost every day and the rate is even
higher during the morning peak period (London Underground Limited, 2006). Moreover, more than half of the services are cancelled if a major
accident occurred.
The U.K.’s Rail Safety and Standards Board (RSSB, 2005) discussed how to control the crowding on the platform and recommended to take
measures with following steps; (1) measures to exclude passengers from
certain parts of the stations, (2) closing pedestrian access to the station,
(3) keep trains away from busy platforms, (4) keep trains away from stations which are overcrowded, (5) suspension of trains services, and (6)
evacuation of station. However, if the service frequency is reduced or the
station is closed, there is a possibility that passengers change their route choice behaviour and therefore that the location of overcrowding
stations/platforms varies. Hence, it is very important for operators to
comprehend the influence of reducing frequency of a certain line or that of closing a certain station: i.e. which line or station is critical against
reduction of service level.
The authors have evaluated the effect of overcrowding on public
transit and its mitigation measures using the transit assignment model described in for example, Shimamoto et al, 2006. In this and other papers,
only the consequence (for example, how many passengers failed to
board) is evaluated. The impact of overcrowding in the real world is, however, not necessarily proportional to the number of passengers who
fail to board. For instance, suppose the same number of passengers fail to
board at a major station with a large platform and at a minor station with
a small platform. Then, even if those who fail to board affect the service little (in terms of safety hazard or delay) at the major station, they might
affect the service much more at the minor station. Lam et al (1999)
investigated the effects of crowding at the Light Rail Transit (LRT) station platforms in Hong Kong. They classified five Levels of Service
(LOS) on LRT platform crowding and examine the crowding effects of
passengers discomfort at the vehicles and the platforms throughout the SP survey. They focused on how passengers perceive the congested level,
3
but the transit operators would also concern the congestion level since
they have to take some measures as congestion gets worse. Based on these backgrounds, this paper evaluates the effect of
congestion using the reliability analysis technique, in which the critical
lines and stations are specified considering the scenarios with reduction
of service frequency of each line. In the context of network reliability, several researches have been carried out to address several concerns over
the reliability of the transportation network. In particular, in the field of
network analysis against disasters the main aim has been to evaluate the robustness/vulnerability of the network or identify critical components of
the network. For instance, Du and Nicholson (1997) evaluated the
connectivity reliability of degradable transport networks in which the connectivity reliability is inferred to the probability of all OD pairs to
still be connected after different possible road closure patterns. Bell
(1999) proposed a game theoretic based approach between the “evil
entity” aiming to degrade the network so as to maximise the total travel time and the travellers re-routing to minimise their travel time. The result
of this game will be the most critical link in the network. D’Este and
Taylor (2003) defined the concept of node vulnerability whose accessibility index decreases significantly with a small number of links
degraded. Kurauchi et al. (2007) evaluated the road network and
identified the critical link from the network capacity indicator; i.e. the network is vulnerable if a minor link degradation reduces the network
capacity, and such links are defined as critical.
In addition, this paper not only considers the consequence of
overcrowding in terms of failing-to board but also attempts to evaluate its impact on service quality and safety risks. The transit assignment
model is outlined in the next section. Section 3 proposes the idea of
identifying critical lines and stations and shows their evaluation criterion. Then, using these criteria, two types of concept of reliability for the
urban public transit are proposed. The method is then applied to
London’s Underground network in Section 4. Finally, Section 5
concludes this paper.
2. Outline of the Transit Assignment Model
2.1. Common lines problem
One of the key differences between road transport and
(frequency-based) public transit is the waiting time at each platform.
4
Therefore, passengers might wait a long time to get on a line of the
shortest travel time: i.e. they cannot always get to their destination earliest when they take a line of the shortest travel time. In case of no
information on the platform as to the arrival of the next vehicle comes,
the fastest way to get to their destination is known to take the first
vehicle to come among their “attractive” lines. This issue is referred as the common lines problem, which is defined as the problem to find the
set of optimal attractive lines among all lines bringing the travellers
closer to their destination (Chiriqui and Robilland, 1975). Suppose passengers arrive randomly and vehicles also arrive statistically
independent with given exponentially distributed headways, the
probability that passengers choose line i, pi, and the expected travel time, T, are calculated as follows:
Kk k
ii
f
fp (1)
Kk k
Kk kk
f
tfT
1 (2)
where K, tk and fk respectively represent the set of attractive lines,
in-vehicle time on transit line k and frequency on transit line k.
As a result, the optimal route between origin and destination is not a single route any more. Nguyen and Pallottino (1988) defined attractive
lines as hyperpath. The hyperpath connecting an origin r to a destination
s is defined as sets of stops, arcs and arc transition probabilities Hp=(Ip, Ap, p), where Hp is a hyperpath connecting r to s, if:
Hp is acyclic with at least one arc;
node r has no predecessors and s no successors;
for every node iIp-{r,s}, there is a path from r to s traversing i, and if i is not a destination, then i has at most one immediate successor;
the vector, p, contains the arc split probabilities, which satisfies
1 iOUTa
ap , pIi (3)
And
5
0ap , pAa . (4)
where OUT(i) are the sets of arcs leading out of node i. The arc split
probabilities are discussed in Section 2.3 after the introduction of the
fail-to-board probabilities.
2.2. Fail-to-board probability
In public transit, the number of passengers on board cannot exceed
the capacity of vehicles and passengers already on board have an
absolute priority over passengers who want to board. To reflect this, Bell et al.(2002) proposed a Capacity-Constrained transit assignment
model(CapCon), introducing the “fail-to-board probability”, qkl, which is
the probability that passengers who want to board at platform k to line l
can not get onto the vehicle due to overcrowding. The number of passengers travelling between stations can be represented as below:
klklkl demandboardingklboardonline xqxx 1 , LlUk l , (5)
where xa denotes the flow of arc a. linekl, on-boardkl, boarding-demandkl respectively denote the line arc, on-board arc, boarding arc of platform k
of line l. L and Ul represent the set of transit lines and set of platforms on
line l, respectively.
In the calculation, qkl is determined so that kllinex does not exceed
the vehicle capacity;
LlUk
x
xcapq l
demandboarding
boardonl
kl
kl
kl
, 1,min,0max1: (6)
Where
lll zfcap (7)
and capl and zl respectively denotes the capacity of line l and that of
vehicle on line l. Then, Kurauchi et. al.(2003) proposed a transit
assignment model (CapCon-CL) by incorporating the idea of “Common Lines” into the CapCon model. In CapCon-CL, a fail-to-board node is
6
introduced between stop node (platform) and boarding node (see Figure
1). At this node, passengers may fail to board with the probability of qkl, and those who can not board the vehicle are hypothetically transferred to
their destination through a dummy arc.
Platform 1
Platform 2
O
Alight
Stop
Fail(B)
Fail(B) Board
Board
Access D
emand
Alight
Alight
Alight
Boardin
g
Demand
Boarding
Dem
and
Boarding
Boarding
D
Line
Line
Line
Line
On-Board Wait
On-Board Wait
Egress
Egress
WalkFailure
Failure
Failure
Figure 1. Network Description
2.3. Arc Split Probability
Arc split probability at stop nodes and fail-to-board nodes (see Figure
1) are defined as below:
1. Stop nodes
Arc split probability at stop nodes is proportionate to the line frequency
as below:
)(,,)( iOUTaSiFf ppipalap (8)
where,
7
)(
)(
iOUTa
alip
p
fF (9)
and fl(a), Sp represents for a frequency of line l and sets of stop nodes on hyperpath p, respectively.
2. Fail-to-board nodes
Passengers are split according to the fail to board probability at fail-to-board nodes as below:
si
si
apDaifq
Daifq1 , pEi (10)
where Ep and Ds are the sets of fail-to-board nodes and sets of failure arcs
destined to s, respectively.
2.4. The Cost of Hyperpath
Passengers might consider not only the travel time but also how crowded the vehicle or platform is when they determine their routes: i.e.
they might take longer but less congested routes instead of the shortest
but heavily crowded route. To reflect this, the cost of hyperpath p is assumed as below.
p
kp
pp Fk
k
Sk
kpkp
Aa
aapap qWTcg
1ln (11)
)(0
)(
)(
)(1
otherwise
BAa
WAa
LAa
a
(12)
where LA, WA and BA represents for Line arc, Walking arc and Boarding demand arc respectively (see Figure 1).
The first and the second terms represent the travel time for the arcs
and the expected waiting time at stop nodes respectively. ap and ap denote the probabilities that traffic traverses arc a and the probability of
traversing node i respectively. and denote ratios of the value of waiting and walking time to the value of in-vehicle time, respectively.
Further denotes the boarding resistance which is added every time
8
passengers board. WTip is the expected waiting time at stop node i of
hyperpath p, which can be calculated as follows:
ipip FWT 1 (13)
iOUTa
alip
p
fF (9)
The third term in Equation (11) represents the cost associated with
the risk of failing to board. is the user’s risk averseness and with this parameter, probability of delay through failing to board is converted into
a time value. If passengers are absolutely risk averse, and are not
considering normal expected travel time and waiting time; when =0 passengers do not care about the risk of failing to board or failing to
access the platform. Note that because Equation (11) is separable with
given fail-to-board probabilities, Bellman’s principle can be applied to find the minimum-cost hyperpath (see Appendix A).
2.5. Mathematical Formulation
Let us assume that passengers use a hyperpath of minimum cost as
defined in Equation (11) where the cost of a hyperpath is a function of
the failure-to-board probability for each transit line on each platform. The fail-to-board probability depends on boarding demand, passengers
already on board, and the transit line capacity, which in turn depends on
the fail-to-board probability. Therefore, the transit assignment model can
be formulated as a following fixed point problem which defines the equilibrium hyperpath flow vector y* and fail-to-board probability vector
q*:
0, *** qyuy , 0qyu **, , y (14)
0, *** qyvq , 0qyv **, , 1q0 (15)
Where
***** ,, rspp mgu qyqy (16)
9
klklkl demandboardinghboardonlkl xqxcapv 1, **
qy ,
LlUk l , (17)
and and hkl respectively denotes set of feasible hyperpath and
fail-to-board node of line l on platform k. As u denotes a vector of cost difference between gp(y*,q*) and
the minimum cost from the origin of the hyperpath p(r) to the destination
(s), *
rsm , Equation (14) represents the user equilibrium condition. Also,
as v denotes the vector of vacancies on the line arc on line l from
platform k, Equation (15) represents the capacity constraint condition. The existence of a fixed point is intuitive since any excess
demand simply implies non-zero failures to board. However, because of
the non-linear relationship in Equation (15), there is a possibility of
multiple fix points. This fixed point problem can be solved by combining the Method of Successive Averages (MSA) and absorbing Markov chains
(Kurauchi et.al. , 2003).
3. Method of Evaluation
3.1. Concept of the Critical Lines and the Critical Stations
In this study, the critical lines are defined as lines whose frequency
reduction causes a severe impact on the whole network. Firstly, the
impact is measured in terms of total number of passengers failing to board in the whole network. Therefore, the critical lines are formulated
as below where NF are the number of passengers failing to board and s is
the scenario indicator:
Find s such that )(max sNFtotals
(18)
Ll Uk
kltotal
l
sNFsNF )()( (19)
)()()( sqsxsNF kldemandboardingkl kl , LlUk l , (20)
As will be explained in the case study in Section 4, the frequency of
10
only one line is reduced in each scenario. Equation (19) shows the
number of passengers failing to board in the network and Equation (20) the number of passengers failing-to-board at each platform.
The critical stations are defined as stations whose platforms are
overcrowded due to the reduction of a certain line frequency. However, since our analysis is based on platform-overcrowding, the criticality of a
certain station is defined not as the sum of the fail-to-board passengers at
each platform belonging to the station but as the maximum among all platforms at this station:
)(max)( sNFsNF iPi
mm
(21)
where Pm represents the set of platforms at station m. Then, the critical
stations based on consequence are formulated as below:
For each scenario s, find m such that )(max sNFmm
(22)
where m is the station indicator. Note that critical stations are defined with each scenario (reduction of a certain line), and may not lie on the
line of reduced frequency.
3.2. Alternative criterion for the Impact of Overcrowding
Since the impact of overcrowding is not necessarily equal to the
number of passengers failing-to-board as described in Section 1 an alternative impact measure is developed in this paper. The impact of
overcrowding might also depend on for example (1) the size of platforms
or stations, (2) the number of exits or entrances and where they are, (3)
the potential impact on anther interchange line, and (4) the congestion mitigation possibilities provided through platform assistants, platform
markings and platform screen doors.
To consider these matters, a satisfaction function for the service operation is proposed. This satisfaction function will take the value of 1
when there is no congestion (fully satisfied), and should converge to 0 as
the number of passenger failing-to-board increases (not at all satisfied). The satisfaction criteria should be determined according to the above
four criteria. If the operator wants to emphasise the impact of crowding
on network delays one might give a higher weight to stations with large
11
interchanges to emphasise that the overcrowding of one line potential
also leads to overcrowding on other lines serving the same station. Similarly, if one wants to evaluate health and safety risks through
overcrowding the traffic engineer will be less concerned about some
overcrowding at large stations with several exits and large number of
station staff than if the same amount of overcrowding would occur at a small station. This second evaluation scenario considering health and
safety risks is taken as a case study in the following. Equation (23) and
Figure 2 express that the same amount of overcrowding is less acceptable at a smaller station than at a larger station.
0)(
10)(exp01.01
1
15)(exp01.01
1
0)(1
sNF
MSmsNF
MSmsNF
sNF
sIm
m
m
m
m
(23)
where MS stands for the set of major stations (definition of major stations
will be explained in Section 4). The relationship between the number of
fail-to-board passengers (NFm(s)) and the satisfaction function is then illustrated in Figure 2. Using the satisfaction function, the critical stations
based on the impact is formulated as below:
For each scenario s, find m such that )(min sImm
(24)
where m represents for a station indicator. Of course this example is used
to show the proposed methodology, and careful calibration of parameters should be made for the actual application.
12
00.10.20.30.40.50.60.70.80.9
1
0 10 20 30 40 50 60 70 80 90 100110120130140150
I m(s
)
NFm(s)
Major Station Minor Station
Figure 2. Satisfaction function
4. Case Study with London Underground Network
4.1. Study Area and Data Collection
The proposed method is applied to the central part of London
Underground network as shown in Figure 3, which consists of 56 stations
and 14 lines. Following data were made available from Transport for London: travel time between stations, estimated walking time between
different platforms, service frequency and the capacity of each line. The
major stations are marked with red circle in Figure 3. The OD matrix of the whole network from 7:45 am to 8:45 am for passengers entering the
inner zone estimated by Schmöcker (2006) is used. The parameters ,
and , in the hyperpath cost function (Eq. 3), are calibrated to minimise
RMS errors from observed passengers’ flow of each line to =2.5, =1,
=3, =150 (Shimamoto et al., 2006).
13
Northern North Picadilly North
Victoria North
Central East
District,
Hammersmith &
City East
Jubilee East
Northern (Bank)
SouthBakerloo South
Northern (Waterloo)
SouthVictoria South
District South
District West
Picadilly West
Central West
Hammersmith &
City West
Bakerloo WestMetropolitan
North
Jubilee North
Figure 3. Underground network of central London
Only one line is assumed to be delayed in each scenario. Therefore,
total 28 scenarios are considered as shown in Table 1. In each scenario, two types of case studies are conducted. In the first case, the impact of
minor delays in the service headway (10% increases) is estimated. Given
the statistics on LUL’s homepage this might well correspond to delays experienced daily during the morning peak. In the second case, major
delays corresponding to a reduction of 50% in line frequency are
considered.
4.2. Discussion
Table 1 summarises the result of calculation. First of all, the critical lines are identified based by the total number of passengers who failed to
board (NFtotal). From the table, Westbound Central Line (4/CeW) and
Southbound Victoria Line (26/ViS) seems to have a larger impact in the
case of minor delay. For the major delay, the relatively large values of NFtotal were obtained for scenarios 4/CeW, 10/DiW, 15/JuE, 16/JuN,
19/NoNL, 23/PiN, 24/PiS, 25/ViN and 26/ViN. Since the two lines which
were found to be critical in the minor delay scenarios were also critical in the case of major delay, these lines should be carefully managed and
monitored so as to maintain a good level of service.
The most critical station in each scenario is specified by the minimum
14
value of the evaluation criteria. It was found that the same station is
identified to be critical from both NFmax( )(max sNFmm
) as well as
Imin( )(min sImm
), as shown in the Table 1. Note that Victoria Station
was critical in the base case without delay (Scenario 0), and is generally
critical in most of the scenarios. There are very few scenarios in which the most critical station is neither Victoria nor along the delayed line (for
these cases the relevant stations are written in bold in Table 1). For
example, in Scenario 13/HCE (major delay on east-bound Hammersmith
& City Line) Tower Hill is the critical station even though it is not on the Hammersmith & City Line. As seen in Table 2, this is because the delay
encourages passengers at Liverpool and Aldgate to take the Circle Line.
This result implies the importance of evaluating the critical lines/ stations using network analysis techniques. Note further the complex network
impacts of delays on line loads. In Scenario 1 the minor delay scenario in
fact leads to more passengers failing to board than in the major delay scenario. The reason is that in the case of large delays more passengers
are encouraged to travel on different routes whereas the expectation of
only a minor frequency reduction is not enough to deter passengers from
their nominally shortest route.
Table 1. List of scenarios with the most critical station
Impact-based Impact-based
Scenario Line Name Remarks NF total NF max I min NF total NF max I min
1 Bakerloo NB 5694 143.7 0.007 Victoria 5541 150.3 0.004 Euston
2 Bakerloo SB 5614 122.3 0.028 Kings Cross 6428 127.4 0.020 Victoria
3 Central EB 5767 157.3 0.003 Victoria 7626 161.4 9.83×10-6 Queensway
4 Central WB 10464 215.4 4.43×10-8 Liverpool Street 16244 229.4 1.08×10
-8 Liverpool Street
5 Circle EB 5596 134.1 0.013 Victoria 5921 198.4 1.81×10-4 Victoria
6 Circle WB 5923 163.2 0.002 Victoria 6098 219.2 4.51×10-5 Victoria
7 District EB 5960 162.2 0.002 Victoria 9742 179.0 0.001 Victoria
8 District NB to Edgware Road 5674 146.2 0.006 Victoria 5686 143.2 0.007 Victoria
9 District WB from Temple 5694 146.7 0.006 Victoria 5715 160.4 0.002 Victoria
10 District WB 6390 174.3 0.001 Euston 12131 651.5 1.37×10-17 Bank-Monument
11 District SB to Edgware Road 6083 139.4 0.009 Victoria 7979 135.3 0.012 Victoria
12 District EB to Temple 6035 139.6 0.009 Euston 8159 157.1 0.003 Victoria
13 H & C EB 6074 136.2 0.011 Victoria 8445 148.9 3.40×10-5 Tower Hill
14 H & C WB 5685 134.8 0.012 Victoria 6757 141.3 0.008 Victoria
15 Jubilee EB 5560 142.3 0.008 Victoria 11318 151.9 0.004 Victoria
16 Jubilee NB 5675 148.6 0.005 Victoria 13653 337.2 1.72×10-17 London Bridge
17 Metropolitan EB 5681 142.8 0.007 Victoria 7184 132.2 0.015 Victoria
18 Metropolitan NB 5618 135.8 0.012 Victoria 5628 142.1 0.008 Victoria
19 Northern NB via London Bridge 6107 158.8 0.003 London Bridge 10038 240.9 1.06×10-5 London Bridge
20 Northern SB via London Bridge 5786 142.0 0.008 Victoria 9245 144.2 0.007 Victoria
21 Northern NB via Waterloo 5689 140.8 0.008 Victoria 5734 143.6 0.007 Victoria
22 Northern SB via Waterloo 6051 149.4 0.005 Kings Cross 9863 310.3 1.39×10-7 Euston
23 Piccadilly NB 5965 161.0 0.002 Victoria 11166 154.1 0.003 Victoria
24 Piccadilly SB 6458 159.5 0.002 Euston 12552 240.5 1.08×10-5 Euston
25 Victoria NB 6382 229.7 2.24×10-5 Victoria 13382 319.7 5.52×10
-8 Victoria
26 Victoria SB 7597 166.3 0.002 Euston 15119 146.8 0.006 Kings Cross
27 W & C From Waterloo to Bank 5715 167.8 0.001 Waterloo 5760 143.1 0.007 Victoria
28 W & C From Bank to Waterloo 5699 140.8 0.008 Victoria 5699 140.8 0.008 Victoria
- 5699 140.8 0.008 Victoria
Notations
H & C: Hammersmith & City EB: East bound NB: North bound
W & C: Waterloo & City EB: East bound SB: South bound
Consequence-based
Major delay
Critical Station
No Delay
Consequence-basedCritical Station
Minor delay
15
Table 2. Number of passengers travelling between stations
Line Scenario Kings Cross Farringdon Barbican Moorgate LiverpoolSt Aldgate
H & C delay 2798.87 2299.96 2114.22 2094.79 2603.35 2224.76
No delay 2850.78 2361.27 2178.76 2164.62 2510.21 2131.64
Difference -51.91 -61.31 -64.55 -69.84 93.14 93.12
H & C delay 10646.39 7694.86 6593.56 5238.39 1761.33
No delay 10592.38 7661.88 6562.45 5225.36 1761.33
Difference 54.01 32.98 31.11 13.03 0.00
Circle
Metropoltan
Finally, Figure 4 shows the number of failing passengers and the
evaluation criterion (based on satisfaction function) at Scenario 10/DiW (major delay on westbound District Line). Generally speaking, as the
number of passengers failing-to-board increase, the evaluation criterion
decreases. However, the evaluation criterion on Westminster station,
which is classified as a minor station, is relatively low even though only a few passengers are failing to board. This fact implies the importance of
evaluating the critical stations using proposed evaluation criteria
depending on the station size.
0.0
0.1
0.2
0.3
0.4
0.5
0.6
0.7
0.8
0.9
1.0
0
100
200
300
400
500
600
700
BM EB BF
CS
TE
MH VI
TH LB SK WA EC EU
WM SS KC SJ GR
Eval
uat
ion
Cri
teri
on
Nu
mb
er o
f Fa
ilin
g P
asse
nge
rs
Station Code
Number of Failing Passengers Evaluation Criterion
Figure 4. Number of failing passengers and the evaluation criterion
16
5. Conclusion
This paper proposed a method to identify critical transit lines against
reduction of their frequency using an afore-constructed transit
assignment model. The line criticality is measured with total number of
failing to board passengers and the station criticality is measured with both the consequence and the impact of overcrowding. A satisfaction
function is proposed to evaluate the impact of overcrowding at each
platform. In the case study evaluating scenarios with the satisfaction function or in terms of number of passengers failing to board leads to the
same critical station. However, it is proposed that the evaluation with a
satisfaction function adds flexibility to the operator to analyse the impact of overcrowding. For example overcrowding at refurbished stations with
wide spaces might be less severe than at old stations with less space for
waiting passengers.
The definition of such a satisfaction function obviously depends on a good knowledge of the system and its facilities. In further work the shape
of the satisfaction for single stations should be discussed in more detail
with Transport for London. One way to model the impact of overcrowding at different platforms might be through the use of a
detailed pedestrian simulation model. Further note that this paper
assesses the critical lines and stations using a user equilibrium model, which implicitly assumes that passengers have perfect information as to
the frequency of each line in each scenario; i.e. they know which line is
degraded. If these delays appear very irregular this is obviously a strong
assumption. However passengers in London often have fairly good information about the delay situation on all lines through information
displayed at all stations. The scenarios discussed in this paper could
further be of interest to the transport operator who might want to know the impact of a longer term frequency reduction for example due to
construction works. Our scenario based analysis further illustrated the
often complex networks effects of delays. In some cases it might be
better for the operator to announce the delays are major instead of only minor in order to deter passengers from already overcrowded lines.
Finally, another interesting extension may be to evaluate the effect of
train arrival information suggested by the authors (Shimamoto et. al, 2005).
17
Acknowledgements
We would like to thank Transport for London for the provision of the
data used in the case study. Further we would like to thank Robin C d’A
Hirsch from the Railway Technology Strategy Centre at Imperial College
London for the discussion on impact of overcrowding.
Appendix A: Separable of the Cost Function
The separability of the generalised cost function (Equation (11)) can
be proven in the same way as in Kurauchi et. al. (2003). Let Vp denote
the set of all elementary paths in Hp, and al is 1 if arc a is included in l,
otherwise 0. Further, using arc split probabilities ap and if lp denotes the probability of choosing any particular elementary path l of hyperpath p, then clearly:
p
al
Aa
aplp
, pVl (25)
1 pVl
lp (26)
Let il be defined as 1 if elementary path l traverses node i. Then, the
probability that hyperpath p traverse node i, ip, can be calculated from
lp as follows:
pVl
lpilip , pIi (27)
Similarly ap, probability that traffic traverses arc a, i.e., arc transition probability, can be calculated as follows:
pVl
lpalap , pAa (28)
Using node and arc transition probabilities, the cost of hyperpath p
(Equation (11)) can be expressed as follows:
18
p pppVl Ek
kkl
Sk
kpkl
Aa
aalalp qWTcg 1ln (29)
Above result suggests that the cost for hyperpath p is a sum of the costs of the elementary paths weighted by their choice probabilities. Let g
’ip
denote the cost of the sub-hyperpath from i to s on hyperpath p, and
define lp(i) as:
ip
al
Aa
aplp i (30)
1 pVl
lp i (31)
Then, clearly,
ajai lpaplp , ipAa (32)
where i(a) and j(a) respectively are a head node and a tail node of arc a.
Using lp(i) , g’jp can be written as follows.
iOUTa
pajapiiFiiS
iOUTa
aapa
iOUTa
pajap
Ll
iiFiiSliaalp
Ll Ek
kkl
Sk
kkl
Aa
aalalpip
pp
pp
p ipipip
gqWTc
gqWTci
qWTcig
'1ln
'1ln
1ln'
,
(33)
where iS is 1 if node i is a stop node and 0 otherwise, iF is 1 if node i is a failure node and 0 otherwise, and a(i,l) denotes an arc on elementary
path l leading out from node i. Equation (33) gives the cost of hyperpath
from i to s as the sum of the cost at node i, which is either the expected
waiting time or the risk of failing to board, a cost for arcs connecting to other nodes weighted by the respective arc split probabilities, and a total
cost from node j to s also weighted by arc split probabilities. s the costs
of subsequent nodes are separable, Bellman’s principle shown by Equation (34) can be applied for finding the minimum cost hyperpath.
19
Eiifq
Siiff
f
sESIiifc
siif
saji
Ka
al
Ka
sajal
iOUTK
iOUTa
saja
is
i
*
*
*
*
1ln
1
min
min
0
(34)
Where I, S and E respectively denote set of nodes, set of stop nodes and set of fail-to-board nodes as illustrated in Figure 1.
Reference
Bell, M. G. H. 1999. Measuring network reliability: A game theoretic
approach, Journal of Advanced Transportation, 33(2), 135-146. Bell M.G.H., Schmöcker J.-D., Iida Y., and Lam W.H.K. 2002. Transit
Assignment: An Application of Absorbing Markov Chains,
Transportation and Traffic Theory in the 21st Century (Ed. Taylor,
M.A.P.), 43-62.
Chiriqui C., and Robilland P. 1975. Common Bus Lines, Transportation
Science, 9, 115-121.
D’Este, G. M. and Taylor, M. A. P. 2003. Network vulnerability: An approach to reliability analysis at the level of national strategic
transport networks, In Bell, M. G. H. and Iida, Y. eds., The Network
Reliability of Transport, Pergamon, Oxford. Du, Z. P. and Nicholson, A. J. 1997. Degradable transportation systems:
sensitivity and reliability analysis, Transportation Research B, 31(3),
225-237.
Kurauchi F, Bell M.G.H., and Schmöcker J.-D. 2003. Capacity-constrained Transit Assignment with Common Lines,
Journal of Mathematical Modelling and Algorithms, Vol.2, 309-327.
Kurauchi, F., Sumalee, A. Tamura, H. and Uno, N. 2007. Bilevel programming problem for analysing capacity vulnerability in a
transportation network under limited damage”, paper presented at
the Third International Symposium on Transportation Network Reliability, 19-20, July, 2007, The Netherlands.
Lam W.H.K, Cheung C.Y, and Lam C.F. 1999. A study of crowding
effects on Hong Kong light rail transit stations, Transportation
Research A 33, 401-415.
20
Nguyen S., and Pallotino S. 1988. Equilibrium Traffic Assignment for
Large Scale Transit Networks, European Journal for Operational Research, 37, 176-186
Oxford Economic Forecasting. 2003. The Economic Effects of Transport
Delays on the City of London, Published by the Cooperation of
London. Available form <www.cityoflondon.gov.uk/economicresearch/(Accessed October
2007).
RSSB. 2005. Health and safety effects of crowding – hazard identification. Rail Safety and Standards Board. Research Report
RAS/PR/04/12/01, Final version 09 February 2005. Available from
< http://www.rssb.co.uk/pdf/reports/(Accessed November 2005). Schmöcker J.-D. 2006. Dynamic Capacity Constrained Transit
Assignment. Ph.D. thesis, Imperial College London, U.K.
Shimamoto H., Kurauchi, F. and Iida, Y. 2005. Evaluation on Effect of
Arrival Time Information Provision Using Transit Assignment Model. International Journal of ITS Research, Vol. 3, 11-18.
Shimamoto H., Schmöcker J.-D, Kurauchi F. and Bell M.G.H. 2006.
Controlling Congestion On Platforms -A Case Study With London’s Underground Network. Proceedings of The 11
th Meeting of the
EURO Working Group on Transportation, CD-ROM.