ENVIRONMENTAL AUDIT REPORT OF LARABEE ENTERPRISES LIMITED Plot 62, Phase 3, Sharada Industrial...
Transcript of ENVIRONMENTAL AUDIT REPORT OF LARABEE ENTERPRISES LIMITED Plot 62, Phase 3, Sharada Industrial...
Prepra nig ltd October 1, 2014
1
ENVIRONMENTAL AUDIT REPORT
Of
LARABEE ENTERPRISES LIMITED Plot 62, Phase 3, Sharada Industrial Estate, Kano
BY
PREPRA NIGERIA
31/32BELLO ROAD, KANO
Email: [email protected]
OCTOBER, 2014
Prepra nig ltd October 1, 2014
2
AUDIT PREPARERS
ALIYU BABA NABEGU, PhD, MWMS, mni
Lead Consultant, Prepra Nig. Ltd
SULAIMAN MUHAMMAD B. Eng
Civil Engineer, Prepra Nig. Ltd
ALIYU M GAMU
Head, Human Resources, Larrabee Ent ltd
PHILLIP MONDAY SHUAIBU
Head, Engineer, Larrabee Ent. Ltd
HARUNA UMAR SANI
Laboratory Technologist, Prepra Nig. Ltd
BELLAMKONDA SREENIVASARAO
Production Manager, Larrabee Ent.ltd
AMINU ALIYU
Technical Department, Prepra Nig.ltd
Prepra nig ltd October 1, 2014
3
LIST OF FIGURES
Figure 1 : Location of Sharada Industrial Estate within Kano metropolis
Prepra nig ltd October 1, 2014
4
LIST OF TABLES
Table 1: Profile of Larrabee enterprises Limited
Table 2: Comparison of Larrabee effluent analysis with NESREA standards
Table 3: Soil Analysis within Larrabee factory
Table 4: Noise level in some sections of Larrabee factory
Table 5: Air quality in the Larrabee factory
Prepra nig ltd October 1, 2014
5
TABLE OF CONTENT
Title Page i
List of Prepares ii
List of figures iii
List of Tables iv
Table of contents v – ix
Acknowledgement x
Exclusive Summery xi - xii
CHAPTER ONE: 1.0 INTRODUCTION
1
1.1 Background 1 - 3
1.2 Objectives of the Environment Audit 3 - 4
1.3 Terms of Reference of the EA 4
1.4 The Audit Criteria 5
1.5 Scope of the Audit 6
1.6 Approach and Methods 6
1.6.1 Pre - Audit phase 6 - 8
1.6.2 On site - Phase 8
1.6.2.1Conducting Opening Meeting with Factory Manager and Sites
Personnel
8
1.6.2.2 Undertaking review of relevant documents 8 - 9
1.6.2.3 Conducting Staff Interview to obtain Information on Actual
Practices
9
1.6.2.4 Conducting on Site Inspection with relevant Audit Checklist 9
1.6.2.5 Collecting Sample for Analysis 10
1.6.2.5.1 Procedure for Collection of Water Samples 10
1.6.2.5.2 Evaluation of the quality of waste water 10
1.6.2.5.3 Measurement of Temperature, pH and Conductivity 10 - 11
1.6.2.5.4 Determination of total solids, suspended, Dissolved solids and
Total ash
11
1.6.2.5.5 Conducting Material balance 11 -12
1.6.2.5.6 Debriefing of the management on audit findings,
recommended corrective actions
12 -13
1.6.2.5.7 Environmental Monitoring data 13
1.6.3 Post Audit Activities 13
1.6.3.1 Actions in post Audit phase 13-14
1.6.3.2 Evaluation of Findings 15
Prepra nig ltd October 1, 2014
6
1.6.3.3 Steps after analyzing the findings 15
1.6.3.4. Implementation of the Action plan 15
1.6.4 Audit period 15
CHAPTER TWO: 2.0 OVERVIEW OF LARRABEE ENTERPRISES LTD
16
2.1 Company Profile 16
2.2 Location of Larrablee Factory 17 - 18
2.3 The Process Technology 18
2.3.1 Raw Material for the Tanning industry 18 -19
2.3.2 The tanning Process 19
2.3.2.1 Currying 19 -20
2.3.2.2 Beam House operations 20
2.3.2.3 Soaking 20
2.3.2.4 Liming 20 - 21
2.3.2.5 De-liming and Bating 21
2.3.2.6 Pickling 21 - 22
2.3.2.7 Retanning 22 -23
CHAPTER THREE: 3.0 BASELINE ENVIRONMENTAL ASSESSMENT
24
3.1 Description of the Surrounding Environment 24
3.2. Existing Environmental management system 24
3.2.1Environmental Policy of Larrabee Enterprises Limited 24 - 26
3.2.2 Implementation of the EMP 26 - 27
3.2.3 Compliance with Environmental laws and regulations in Larrabee 27 - 29
CHAPTER FOUR: 4.0 AUDIT FINDINGS
30
4.1 Observation and Evaluation of General housekeeping 30
4.1.1Waste generation from Larrabee 30 – 31
4.1.2 Impact valuation 31
4.1.2.1. Waste Water Disposal 31- 33
4.1.1.2 Solid Water disposal 33- 34
4.1.2.3 Compatibility 34
4.1.2.4 Fuel Dump 34
4.1.2.5 Cloakroom/Conveniences 34
4.1.2.6 Safety signs 35
4.1.2.7 Soil Analysis 35
4.1.2.8 Muster point 35
4.1.2.9 Fire Extinguisher 36
Prepra nig ltd October 1, 2014
7
4.1.2.10 Illumination 36
4.1.2.11Noise level 36
4.1.2. 12 Air Quality 36- 37
4.1.3 Compliance with extant regulations 37
4.1.3.1Compliance with Environmental Regulations 37 - 38
4.2.1.2 Compliance to other regulations 38
4.1.2 Socio- Economic Impact 38-39
CHAPTER FIVE: 5.0 RECOMENDATIONS
40
5.1 General Recommendations 40
5.2 Specific Recommendations 41
5.2.1 Elimination of Waste 41
5.2.2 Reuse of waste 41
5.2.3 Recycling of Waste 41
5.2.4 Disposal after compaction, drying or other treatment 42
5.2.5 R Retention /Redirect 42
5.2.6 Separation/concentration 43
5.2.7 Determination of specific water consumption 43
5.2.8 Produce by products from waste generated 43- 44
5.2.9 Reducing Noise level and Gaseous pollutants 44
5.2.10 Compliance to all extant regulations 44
5.2.11 Compliance to all extant regulations 44
CHAPTER SIX: 6.0 FOLLOW UP PLAN
45
6.1 Completion and Submission of EA 45
6.1.1 Submission of EA report 45
6.1.2 Monthly effluent monitoring and sending results to NESREA and
Kano state Ministry of Environment
45
6.1.3 Implementation Follow up on the management of the company’s
EMP
43
6.1.4 Provision of adequate safety equipment 45
6.1.5 Provision of firefighting equipment in strategic locations of the
factory identified
45
6.1.7 Awareness training for staff 45
6.1.7 Quarterly inspection 45
Prepra nig ltd October 1, 2014
8
6.1.8 Establishment of quality assurance unit to ensure timely repairs to
leaking oil/water pipes
45
CHAPTER SEVEN: 7.0 CONCLUSION 46
Prepra nig ltd October 1, 2014
9
ACKNOWLEDGEMENT
Prepra Nigeria acknowledges the full cooperation and support of the
management and staff of Larrabee Enterprises limited. In particular, the support
and disposition of the chairman/CEO Mustapha Shour has been invaluable to
the success of this report. We also recognize and immensely appreciate the
assistance from the heads of Engineering and Human resources as well as the
production Manager.
Prepra Nig. Ltd is also grateful to Larrabee Enterprises limited for its patronage
and the opportunity to be involved in the company’s quest towards the
environmental sustainability.
Prepra Nigeria ltd wishes to stress that in line with its policy, all information
obtained in the course of this Audi exercise as well as those contained in this
report will be accorded the strictest confidentiality.
Prepra nig ltd October 1, 2014
10
EXECUTIVE SUMMARY
This environmental audit (EA) was carried out with strict adherence to the
guidelines and regulation of the National Environmental Standards and
Regulations Enforcement Agency (NESREA) in particular, NESREA Act, Section 7
(a) which vests in the Agency the responsibility to enforce compliance with laws,
guidelines, policies and standards on environmental matters; Section 7 (j), that
empowers the Agency to enforce environmental control measures through
registration, licensing and permitting systems; Section 7 (k) of the Act that
empowers NESREA to conduct environmental audit and establish data bank on
regulatory and enforcement mechanisms of environmental standards other
than in the oil and gas sector; Section 8 (k) of the Act also empowers the
Agency to make Regulations, one of which is the Regulations S. I No 29, that
requires existing industries to undertake environmental audit and submit reports
of such every three (3) years.
Desirous of complying with extant environmental laws and regulations Larrabee
enterprises appointed MESSR PREPRA NIGERIA LTD – a NESREA accredited
consultant to conduct the audit.
In order to evaluate the impact of the activities of Larrabee, an assessment of
the location in terms of compatibility and of the processes and housekeeping of
the factory was undertaken. This initial contact ensured management consent
and selection of audit team from the company.
Standard questionnaire was administered to the management and key staff to
obtain information that was used in the facility inspection as well as examination
of records and documents of the company.
The main activity in Larrabee enterprises limited is the conversion of animal hides
and skins into leather which results in considerable quantities of several varieties
of waste products and the tanning industry has the unenviable reputation of
being one of the evil-smelling industries. With the expansion of settlements in the
fringes of industrial layouts the problem is becoming more acute. Thus efforts
are being made especially through vigorous enforcement of laws by NESREA to
limit or eliminate as much as possible the discharge of polluting materials into
the atmosphere.
Tanning of hides and skins involve considerable use of water, either to cleanse
them or in the form of process liquors during the various unit processes.
Generally, a tannery can contribute to problems of health hazard by (i) causing
depleting of oxygen in water where it is discharged, thereby removing the
dissolved oxygen required by fish and other aquatic organisms for respiration, (ii)
leading to high concentration of salts and possible formation of metal sulphides
which are very harmful to both human beings and animal (iii) causing
bacteriological pollution by pathogenic organism.
Prepra nig ltd October 1, 2014
11
This Audit exercise indicated that the operation of Larrabee tannery will result in
short and long term adverse impact to the environment as well as nuisance to
the community especially from waste water which is by far the most dominant
waste product. Thus various strategies for treating the wastewater have been
proffered as well as to minimize the generation instead of concentrating
treating them. Further measures in which the wastewater can be reused directly
subject to the guidelines of NESREA have also been suggested. In addition,
suggestion were made in the report that will ensure that resources are used
appropriately and efficiently; informed decision making; encourage and
provide opportunities for public participation; a basis for ongoing environmental
management through the use of monitoring; protection of human health and
safety; avoiding irreversible changes and serious damage to the environment;
safeguarding valued resources, natural areas and ecosystem components
among others.
Prepra nig ltd October 1, 2014
12
1.0 CHAPTER ONE: INTRODUCTION
1.1 BACKGROUND
Environmental protection is considered the most important consideration for
sustainable development. Consequently, globally, environmental regulatory
agencies now embrace comprehensive, multi-statute solutions to facility
permitting, compliance and regulatory development issues. In relation to
organization’s activities, sustainable development involves meeting the current
need of the organization while protecting recourses so that future generations
are able to meet their needs.
Environmental Audit (EA) is a systematic, documented, periodic and objective
evaluation of how well organizations, management and equipment are
performing with the aim of safeguarding the environment and human health in
order to meet the requirements for sustainable development. It is designed to
protect the environment with the aim of:
Assessing performance against a set of requirements or targets related to
specific issues
Evaluating compliance with environmental legislation and corporate
policies
Measuring performance against the requirements of an environmental
management system standard
Prepra nig ltd October 1, 2014
13
Exploring the potential economic, social and environmental benefits that
an improved performance can achieve.
The National Environmental Standards and Regulations Enforcement Agency
(NESREA) is responsible for ensuring that all businesses and organizations comply
with environmental laws that protect the environment and public health in
Nigeria through;
The NESREA Act, Section 7 (a) vests in the Agency the responsibility to
enforce compliance with laws, guidelines, policies and standards on
environmental matters
Section 7 (j), empowers the Agency to enforce environmental control
measures through registration, licensing and permitting systems.
Section 7 (k) of the NESREA Act empowers NESREA to conduct
environmental audit and establish data bank on regulatory and
enforcement mechanisms of environmental standards other than in the oil
and gas sector
Section 8 (k) of the NESREA establishment Act also empowers the Agency
to make Regulations. One of such made is the “National Environmental
(Permitting and Licensing System) Regulations, 2009; S. I No. 29”
All the extant national sectorial environmental regulations require existing
industries to undertake environmental audit and submit reports every
three (3) years.
Prepra nig ltd October 1, 2014
14
Organizations that conduct environmental audit clearly demonstrate to its
employees that it is committed to improving its environmental performances. In
addition, it portends that the professionals within the organization are interested
in environment issues and wishes to maintain environmental governance.
Environmental Audit addresses regulators’ problem of obtaining effective day-
to-day monitoring of regulatory compliance with limited resources. In addition,
it aids in targeting enforcement actions because it more reliable differentiates
between compliers and non-compilers. Environmental auditing has the long-
term potential for improving relations between the regulators and regulated.
Besides pursuing sanctions, NESREA can acknowledge and encourage
corporations that demonstrate innovative approaches to environmental
management through its NESREA GREEN MARK.
1.2 OBJECTIVES OF THE ENVIRONMENTAL AUDIT (EA)
The objectives of this EA include: -
Generation of adequate environmental information assessment of
facilities for the potential environmental risks that are likely to be caused
by the operations to the facilities and immediate environs.
Achieving resources optimization and improved process performance.
Encouraging organizations to self- regulate their environmental practices
and to increase their responsibilities to stakeholders and society.
Prepra nig ltd October 1, 2014
15
Ensuring compliance, not only with laws, regulations and standards, but
also with company policies the requirements of the approved NESREA
endorsed Environmental Management Plan of the organization as
standard.
Enabling environmental problems and risks to be anticipated and
responses planned.
Minimizing human exposure to risks from environmental health and safety
problems.
1.3 TERMS OF REFERENCE OF THE EA
For the purpose of the mandatory Compliance Audit due every three (3) years;
this audit assesses compliance of the Larrabee with criteria derived from:
National Environmental standards and Regulations enforcement Agency
provided in sections 21 of the S.I.9 regulations of 1991 on National
Environmental protection (pollution abatement in Industries and facilities
generating wastes), EA Act No 86 of 1992 and 7 (a) and 7 (k) of the
NESREA Act No 25 of 2007 and those that will come into force from time to
time
Corporate or management policy of Larrabee
NESREA Approved facility Environmental management plan of Larrabee
Prepra nig ltd October 1, 2014
16
1.4 THE AUDIT CRITERIA
The criteria used in environmental audits vary depending on the objectives of
the audit process. Audit criteria considered in this study included but are not
limited to:
Industry codes of practice
Specified organizational requirements (e.g. compliance with company
environmental policy)
Environment protection Act
Environment protection regulations
Conditions of licenses, workers approvals and exemptions
Other applicable Federal/State / Local government -environment
legislations
Standards, rules, orders, etc made under an act and having the force of
law
International agreement such as, convention, protocol, and treaties
which have been ratified by the government.
Conditions contained in facility permits
Codes of professional practice/ international code of conduct
Good environmental management
Prepra nig ltd October 1, 2014
17
1.5 SCOPE OF THE AUDIT
The scope of this Audit exercise covers the following:
Evaluation of Larrabee existing Environmental management system
The existing environmental policy and objectives
Housekeeping and records
Existing strategies for environmental improvement
Larrabee compliance status with statutory laws and regulations
1.6 APPROACH AND METHODS
This environmental audit was undertaken in three phases:
Pre – audit
On – site audit
Post – audit
1.6.1 PRE – AUDIT PHASE
This is the audit preparation phase prior to visit by an audit team. It entailed.
Obtaining full management commitment for PREPRA NIG LTD to embark
on the audit
Setting overall goals, objectives, scope and priorities for the audit
Selecting a team to ensure objectivity and professional competence
Sending out prepared pre-audit questionnaire to management and staff
of Larrabee (see appendix1)
Prepra nig ltd October 1, 2014
18
Reviewing background and operational information with the
management of Larrabee.
Conducting initial site visit at the Larrabee facility
Reviewing audit plan and arranging logistics.
i) Management commitment
A letter from the management of Larrabee to Prepra Nigeria to conduct the
audit was duly signed by the CEO. This signaled the commencement of the
audit.
ii) Team selection
The audit team was carefully selected and includes employees of the Larrabee
and Prepra Nigeria. The team leader was a NESREA accredited consultant while
the other team members have skills and knowledge relevant to the audit
process. Each member of the team was assigned his/her role and responsibilities
and pre-audit training was done to ensure that all the team members are
adequately prepared for the task.
In addition to other relevant information requested for in the questionnaire used
(Appendix1), the following information were also collected by the team
members:
Identifying types of pollutants and waste generation, storage,
transportation, treatment and disposal as well as the general practice:
Prepra nig ltd October 1, 2014
19
Identifying requirements, regulations and limitations as applicable in the
form of Permits and Licenses
Federal and State database relevant to Larrabee, such as, any nearby
abandoned, inactive or uncontrolled hazardous waste sites; Industrial
landfill; Municipal landfill; Solid waste sites and Drinking water sources
1.6.2 On site audit phase
The purpose of the on-site audit phase was to collect verifiable evidence to
determine whether audit criteria are being complied with. This entailed well
defined and systematic use of checklists which started with:
1.6.2.1 Conducting opening meeting with factory manager and site personnel
to:
Identify areas to be inspected
Outline procedures
Outline schedules
Identify records and documents to be reviewed during audit
Review health and safety requirement
Review how confidential data will be handled
1.6.2.2 Undertaking a review of relevant documents such as:
Corporate or/and management policy
NESREA endorsed Environmental Management Plan (EMP)
Management system documentation
Prepra nig ltd October 1, 2014
20
Operational procedures and records
Records (inventory, utility, monitoring, transportation, training)
Environmental monitoring/quality records
Correspondence on environmental committee/team meeting minutes
Previous environmental audit report (if available)
1.6.2.3 Conducting staff interview to obtain information on actual practices;
awareness level; expectations and possible suggestions through :
Identifying key facility personnel
Scheduling ahead of time, meeting in work areas
Confirming interview time
1.6.2.3 Conducting detailed on - site inspections with the relevant audit
checklist
This exercise was conducted to investigate the presence of sensitive sites within
or n the neighborhood of the Larrabee factory that are capable of impacting
on the data collected such as the nature of the past and present usage of the
factory; nature and operations in adjourning properties - type and use past and
present; above ground storage tanks ;Air sources mobile and stationary;
Presence of Asbestos; Boilers usage; Contaminated sites; Drinking water quality
cross connections; Discharges to groundwater; Neighboring wetlands and
waterways protection; PCB containing transformers and/or other PCB regulated
equipment; Sewage and septic system discharges etc.
Prepra nig ltd October 1, 2014
21
1.6.2.5 Collecting samples for Analysis
1.6.2.5.1 Procedure for collection of water samples
Samples of wastewater representing the existing conditions in the Larrabee
tannery were collected from effluent pit every day, over a period of seven days
in suitable polythene containers with screw cap and stored in a refrigerator
where immediate analysis was not possible.
Samples (250ml) meant for the estimations of biochemical oxygen demand
(BOD) sulphide were collected separately in two glass bottles stoppers. The
dissolved oxygen and sulphide were fixed on the spot by the addition of winker
reagent (MnSO4 followed by alkine-iodide-azide) and zinc acetate respectively.
Since the components of the liquor undergo significant and unavoidable
changes on storage, composite samples could not be used.
1.6.2.5.2 Evaluation of the quality of waste water
Due to the complex nature of the wastewater and in view of the specific
requirements relating to NESREA guidelines, the present work is based on the
examination of different parameters as follows:
1.6.2.5.3 Measurement of temperature, pH and conductivity
Wherever possible the temperature and pH of the samples were determined on
the spot, the measurements of pH were conducted using the PH Meter (Philips
Prepra nig ltd October 1, 2014
22
PW 9418). The electrical conductivity was measured with the Griffin conductivity
bridge.
1.6.2.5.4 Determination of total solids, suspended , Dissolved solids and Total ash
The methods for the determination of solid used is that of Hanson (Hanson,1973).
The term’ Total ash’ is a measure of the total mineral content and was
determined by the method prescribed by the society of leather technologists
and chemists(Soc. Leath,Tech.Chem.,1965).
Other characteristics were estimated on the aliquots of the samples (100ml)
obtained after removing the suspended solids by filtration. Estimation or chloride
and total nitrogen were carried out using the argentimetric and ‘kjeldahl’
methods respectively. The amount of BOD was determined using the dilution
method. Estimation of metals was carried out by using perkin-Elmer Model 306
Atomic Absorption Spectrophotometer and EEL Model A Flame Photometer.
1.6.2.5.5 .Conducting a material balance
In the mass balance approach that was used in this study, each process
needed to be clearly understood in terms of inputs and outputs. This was
achieved by carrying out a mass balance assessment based on the simple
principle that the total mass of material going into the process should equal the
total mass going out i.e. Input – Losses = Outputs
Prepra nig ltd October 1, 2014
23
EXAMPLE OF INPUTS: raw materials – skins and various chemicals, packaging e.g
pallets, plastic drums and containers, polythene, sacking and cardboards,
consumable - e.g. gloves, aprons and ear defenders and utilities or services
servicing each process e.g. water, steam, cooling water and compressed air.
EXAMPLES OF LOSSES: waste materials such as packaging, liquids such as
effluent or lubricants, air emissions and waste generated by the utilities or
services
OUTPUTS: the final product(s).
The mass of inputs to the process in Larrabee should balance the mass of
outputs as products, emissions and wastes, plus any change in stocks. This
simply entailed the following steps.
Assembling unit process input and output information
Deriving a preliminary material balance for unit processes
Evaluating the material balance
Refining the material balance
1.6.2.6 Debriefing of the management on audit findings, recommended
corrective actions
This exercise involved meeting with the management in order to assess the
observations made with a view to Identifying actual and/or imminent threats to
health and the environments; Identifying actual noncompliance; Identifying
Prepra nig ltd October 1, 2014
24
potential noncompliance; Identifying and discussing information gaps
Identifying and discussing unclear audit findings
1.6.2.7 Environmental monitoring data
In evaluating environmental monitoring data the following amongst others were
considered:
That the sampling analysis and procedures are appropriate and that
results comply with relevant national guidelines
That the steps taken to collect, review evaluate or verify data are
consistent with accepted best practices
That management of data obtained in the course of audit process such
as: index, facility records, correspondence, include date, time, what,
when etc.
1.6.3 Post audit activities
The objectives are to produce an environmental audit report with audit findings
and recommendations and to contribute toward formulation of an action plan
for continuous improvement of operations of Larrabee.
1.6.3.1 Actions in post audit phase
Collation of information and follow up on outstanding issues
Evaluation of findings including outcome of material balance and impact
evaluation of Larrabee process on the environment.
Prepra nig ltd October 1, 2014
25
Preparation of the draft audit report in the approved presentation format
Circulating draft audit report for comments to managements and audit
team
Incorporating or resolving all comments
Preparation of an action plan with consultation with the management of
Larrabee to incorporate the following:
A list of recommended actions in terms of increasing cost effectiveness in
addressing the facility’s critical environmental issues.
Interim and long term targets/objectives and a time-table for achieving
them for environmental improvement in the operation of Larrabee
An indication of investments and other resources (human and
information) that would be required at Larrabee without compromising
commercial confidential information
Produce report for use of Larrabee and NESREA
Facilitate the implementation of action plan at the management level of
Larrabee
Prepra nig ltd October 1, 2014
26
1.6.3.2 Evaluation of findings
The information gathered and data collected together with the overall findings
of this Audit report will be reviewed in line with the extant regulations with the
Larrabee management. The key rules in discussing the findings are: -
The exact nature of the problems should be clearly stated.
Communicating the extent of the problem fully stating whether there is
compliance or noncompliance.
Providing good management practices suitable to Larrabee.
1.6.3.3 Steps After analyzing the result of findings :
Prioritizing the problems/impacts and Allocating responsibilities/roles
Developing a plan of action and Assessing the effectiveness of plan and
effect a change if it is not effective
Making all necessary agreed changes with facility management and
Documenting and communicating the changes to the management of
Larrabee
1.6.3.4 Implementation of the action plan
Responsibilities needed to be undertaken according to unit and timeline for
completion within the environmental action plan framework will be stated.
1.6.4 AUDIT PERIOD
The audit was conducted between 14th September and 3rd October 2014.
Prepra nig ltd October 1, 2014
27
2.0 CHAPTER TWO: OVERVIEW OF LARRABEE ENTERPRISES
2.1 COMPANY PROFILE
Table 1 Profile of Larrabee enterprises Limited
The Company LARABEE ENTERPRISES LIMITED
RC. NO. 196655
Date of Incorporation 26/5/1992
Registered office Plot 62, SHARADA INDUSTRIAL ESTATE,
PHASE 111, Mailing Address P.O.BOX, 11344 KANO, KANO STATE.
Telephone No 234 (0) 934400 and 978446
Email [email protected]
Ownership Structure 75% owned by Shour Family
Nature of Activity TANNING
Installed Capacity 10,000 SKINS/DAY (WET BLUE)
Raw Materials RAW ANIMAL SKINS, CHEMICALS AND
WATER Consumables DIESEL,PETROL,LUBRICANTS, GREASE etc
Manpower: Skilled 34
Semi skilled 68
Prepra nig ltd October 1, 2014
28
2.2 LOCATION OF LARRABEE FACTORY
Larrabee enterprises Limited’s tannery is located in Sharada Industrial estate
phase 111, Kano, the most important and largest center of manufacturing
activity in Northern Nigeria. The location of the Industrial estate within Kano
metropolis is shown in Figure 1.
Figure 1 : Location of Sharada Industrial Estate within Kano metropolis
The factory is sited between latitude 110. 56` 457and longitude 80. 29` 049. Based
on the coordinates, the exact position of the factory is shown in Plate 1 as
extracted from Google earth. The site of the land in which the factory is located
consists of two plots of land covered by C of O No. LKN/1ND/82/36 covering an
area of 0.735 hectares and C of O No LKN/IND/82/3 covering 0.733 hectares,
thus the factory occupies a total area of 1.468 hectares. More 70% of the area
Prepra nig ltd October 1, 2014
29
of the factory is built up. All structures on the premises have been approved by
Kano urban planning development authority (KNUPDA).
2. 3 THE PROCESS TECHNOLOGY
Tanning is the process of treating animal’s skins to produce leather, which is
more durable and less susceptible to decomposition. A tannery is the term for a
place where the skins of animals are processed. It can be performed with either
vegetable or mineral methods.
2. 3.1 Raw materials for the Tanning industry
Animal skins
a) Wet – salted Goat skins
b) Wet – salted Sheep skins
Chemicals
a) Sodium chloride
b) Sodium sulphide
c) Chrome
d) Sulfuric Acid
e) Ammonium sulphate
f) Caustic soda
g) Soda Ash
h) Ammonium liquor
i) Dyes
Prepra nig ltd October 1, 2014
30
j) Bactericides
k) Fungicides
l) Formic Acid
m) Enzymes
n) Syntans
o) Synthetic oils
p) Vegetable oils
q) Lacquers
r) Pigments
s) Binders (acrylic and non-acrylic)
2.3.2 The tanning process
The first stage of the leather production begins with the collection and sorting of
raw skins – normally supplied by designated agents to the companies
warehouse. Plate 2 shows sorted raw sheep skins in the company’s warehouse
Tanning involves four stages as indicated below:
2.3.2.1 Curing
Preparing the skins begins by curing them with salt. Thus the skins form the
abattoirs are wet-salted before being transported to the company. Curing is
employed to prevent putrefaction of the protein substance [collagen] from
bacterial growth during the time lag that might occur from procuring the skins to
Prepra nig ltd October 1, 2014
31
when it is processed. Curing removes excess water from the skins using a
difference in osmotic pressure. The moisture content of skin is greatly reduced. In
wet- salting, skins are heavily salted, then pressed into packs for about 30 days.
In brine-curing, the skins are agitated in a salt water bath for about 16 hours.
Generally, curing substantially reduces the chance of spoilage by bacteria.
Curing can also be done by preserving the skins at a very low temperature. In
Nigeria the only form of curing is wet-salting.
2.3.2.2 Beam-house operations
The steps in the production of leather between curing and tanning are
collectively referred to as beam-house operations. They include: soaking liming,
removal of extraneous tissues (un-hairing, scudding, and fleshing), de-liming,
bating, drenching and picking
2.3.2.3 Soaking
In the process known as soaking, the hides are soaked in clean water to remove
the salt left over from curing and increase the moisture so that the hide or skin
can be further treated.
2.3.2.4 Liming
After soaking, the hides and skins are taken for liming which is a treatment that
involves the addition of sharpening agents like sodium sulfide, cyanides, amines
etc. The objectives of this operation are mainly to:
Prepra nig ltd October 1, 2014
32
Remove the hairs, nails and other keratinous matter.
Remove some of the inter-fibrillary soluble proteins like mucins.
Swell and split up the fibers to the desired extent.
Remove the natural grease and fats to some extent
Bring the collagen in the hide to a proper condition for satisfactory
tannage.
The weakening of the hair on the breakdown of the disulfide link of the amino
acid is called cystine, which is the characteristic of the ketarin class of protein
that gives strength to hair and wools (ketarin makes up 90% of the dry weight
hair). The hydrogen atoms supplied by the sharpening agent weaken the
cystine. To some extent, sharpening also contributes to un-hairing as it tends to
break down the hair protein.
2.3.2.5 De-liming and Bating
The pH of the collagen is brought down to a lower level so that enzymes may
act on it in a process called de-liming. Depending on the end use of the leather,
skins may be treated with enzymes to soften them, a process called bating.
2.3.2.6 Pickling
Once bating is completed, the hides and skins are treated with a mixture of
common table salt and sulfuric acid, in a case a mineral tanning is to be done.
This is done to bring down pH of collagen to a very low level so as to facilitate
the penetration of mineral tanning agent into the substance. This process is
called picking. The common salt penetrates the skins twice as fast as the acid
Prepra nig ltd October 1, 2014
33
and checks the ill effect of sudden drop of pH. The pH is very acidic when the
chromium is introduced to ensure that the chromium complexes are small
enough to fit between the fibers and residues of the collagen. Once the desired
level of penetration of chrome into substance is achieved, the pH of the mineral
is raised again to facilitate the process. This step is known as Basification. In the
raw state chrome tanned skins are blue in appearance and are therefore
referred to as Wet Blue. Chemicals used in tanning include chrome, salts, sulfuric
acid, ammonium sulphate and bactericides.
2.3.2.7 Retanning
The wet blue is selected and shaved to specified thickness often determined by
the final product to be used and subsequently moved back to the drum for re-
tanning. Re-tanning is the process of using oils and vegetable extract to convert
the skin into leather.
The re-tanned leather is referred to as crust and it is often colored depending on
the requirement. The crust is now complete leather and can be finished to
various formats by the spray of pigments and lacquers. Chemicals used in re-
tanning includes, dyes, formic and sulfuric acids, fatliqours and Syntans
For finishing the main chemicals are binders of different make i.e. acrylic and
non-acrylic, pigments and lacquers
The stages can be summarized as follows:-
Prepra nig ltd October 1, 2014
34
Preparation for Tanning => Tanning => Re-tanning => Finishing
In addition to skins and chemicals other materials that are required in a tannery
like Larrabbe include water, lubricants, fuel, diesel, packaging materials and
auxiliary facilities such as power supply etc.
Prepra nig ltd October 1, 2014
35
3.0 CHAPTER THREE: BASELINE ENVIRONMENTAL ASSESSMENT
3.1 DESCRIPTION OF SURROUNDING ENVIRONMENT
The factory site is very firm, relatively level and well drained. Larrabee enterprises
limited is bounded by Gongoni Industrial Enterprises, to the east, to the west by
Dangote flour mills, to the north by Sani Brothers Wire industries and to the south
by Northern plastics. The factory is located about 45 meters off- the main trunk A
road that links Kano city with Challawa Industrial estate. Across the trunk C road
are Angel spinning as well as loquat tannery. It is also located a few meters from
the main rail line that connects Kano to the south is at the eastern part of the
factory making it very accessible. The factory is sited within an area
demarcated for medium to heavy industrial operation. The factory covers
an area about 1.468 hectares of land.
3.2 EXISTING ENVIERONMENTAL MANAGEMENT SYSTEM
3.2.1 Environmental Policy of Larrabee Enterprises Limited
The realization of the legal requirement to protect the environmental as well as
the consciousness of the company to protect the health of its employees as well
as the community in its vicinity led the company to initiate a company –
community relation in order to come up with an enduring environmental policy.
To ensure the actualization, the company engaged a NESREA accredited
Prepra nig ltd October 1, 2014
36
environmental consultant Messr- PREPRA NIGERIA LIMITED to lead the committee
and come up with an environmental policy.
The result of these consultation resulted in the adoption of an environmental
policy by Larraabee enterprise limited with the vision and mission as :
Vision
------ to be a producer of high quality leather products with an enduring
commitment to preserving and protecting the environment -----------
Mission
-------- protecting and preserving the environment for future generation through
commitment to training, creating awareness to staff and community and
deploying the best technologies at all times to meet the challenges of a great
changing world ---------------
The main objectives of the environmental policy adopted by Larrabee are:
i) To maximize resource utilization and reduce waste
ii) Fully comply with all applicable environmental protection regulations
iii) Minimize damage to the environments from its operation
iv)To use the best technology at all times
The environmental policy of the company is implemented through the
environmental monitoring plan of the company that was submitted to
Prepra nig ltd October 1, 2014
37
NESREA. The EMP structured the implementation of the company
environmental plan through the following plans:
1) Development of a company environmental policy
2) Environmental Management Implementation plan
3) Environmental Monitoring plan
4) Contingency plan
5) Safety plan
6) Risk assessment and Emergency response plan
7) Environmental management plan review
8) Reporting plan
3.2.2 IMPLEMENTATION OF THE EMP
Larrabee enterprises limited have established an environmental and social
monitoring unit that ensures implementation of the environmental management
plan. The unit is led by a project manager and consists of staff members of
Larrabee enterprises limited and a representation of the community. The unit is
responsible for ensuring that the overall environmental targets are achieved and
that the environmental responsibilities and obligation of the EMP is satisfied. Also
the unit coordinates the day-to-day monitoring of regulatory bodies.
Because liquid effluent forms a great proportion of the waste generated and to
comply fully with the legal requirement to have a primary treatment plant,
Prepra nig ltd October 1, 2014
38
Larrabbe enterprises established a waste water primary treatment plant with the
waste water collection pond.
As a practical demonstration of compliance to environmental regulation and
care to the health and well-being of staff, Larrabee makes it mandatory for all
staff to wear protective clothing at all times based on the recommendations.
To ensure smooth implementation of the EMP environmental, the following plans
are put in place;
Environmental Reporting
Staff training Plan
Emergency Response Plan
Emergency Response plan
Contingency plan
Safety plan
Plan Review
Environmental monitoring plan
3.2.3 COMPLIANCE WITH ENVIRONMENTAL LAWS AND REGULATIONS IN
LARRABEE
The following among others are laws and regulations that are applicable to
the Larrabee enterprises limited
Prepra nig ltd October 1, 2014
39
Laws of the Federation of Nigeria 1990, Labor ACT CAP 198 Relating
to general welfare to staff – Changing rooms, toilet facilities,
compensation, safety and protective wares, pre-employment
medical examination, casualization of labor, workplace policy on
AIDS/HIV
Business premises registration LAW (CAP, 18) 1992 section 4(1) of
Kano state Government
Hides and Skins premises license
Hides and skins buyers license
The hides and skins (Northern states)Regulations 1958 - Exporters
license
Billboard fees local government edict section 40 (t)chapter
84,vol.01.2 of laws of Kano state of Nigeria 1991, as harmonized by
(JIB) decree 21, 1998section 7 (5)
Public health act
Polluter fee
Section 1 (1) of Regulation S.I.8 of 1991
Section 3 (1) of Regulation S.I.8
Prepra nig ltd October 1, 2014
41
4.0 CHAPTER FOUR: AUDIT FINDINGS
4.1 OBSERVATIONS AND EVALUATION OF GENERAL HOUSE KEEPING
The following are the results of observations and data collected in respect of the
operations of Larrabee enterprises.
4.1.1 Waste Generation from Larrabee operation
The following are the wastes that are generated from the manufacturing
process in Larrabee:
Liquid waste
Waste water – effluent
Oil and greases
Solid waste
Trimmings
Fleshings
Dust from buffing
Plastic and cartons from packaging
Spent chemical residues
General sweepings
Gaseous waste
Ancillary dust and compounds from boiler and generators
Prepra nig ltd October 1, 2014
42
Noise
Sound from generators and machinery
In addition to the wastes generated from operation of Larrabee, other issues
considered for evaluation include level of compliance to regulations, safety and
welfare provision to workers.
4.1.2 IMPACT EVALUATION
4.1.2.1 Waste water disposal
Wastewater effluent is the dominant waste generated and data collected
indicated about 600,000 litres is generated at full capacity. The existing methods
of waste water disposal presently being followed in Larrabee is by discharging
waste water after primary treatment through the main drainage outlet and
ultimately into Salanta river . This method of disposal has its attendant problems
and much pollution is caused by uncontrolled discharges. Table 1 shows the
analysis of wastewater of Larrabee and its comparison with NESREA standard for
waste water from tanneries, showing clearly it is not up to 100% in compliance.
Although a small volume of waste discharge into rivers is eventually broken
down by micro-organisms especially if nitrogenous organic substances are
present, many of the substances in the wastewater from Larrabee are resistant
to bacterial action and the breakdown may be very slow. Consequently
remedial measures must be put in place to comply with NESREA guidelines.
Prepra nig ltd October 1, 2014
43
Table 2: Comparison of Larrabee effluent analysis with NESREA standards
Parameter NESREA permissible limits Larrabee Effluent
Analysis Results Temperature Less than 40(0C) 28.0
Colour Colourless colorless
pH 6-7 8- 9.5
BOD5 at 20(0C) 50 1956
Total suspended solids 25 40
Total dissolved solids 2,000 3077
Chloride (as Cl-) 600 1090
Sulphate (as SO42-) 500 130
Sulphide (as S-2) 0.2 3.3
Cyanide (as CN-) 0.1 nil
Detergents (linear alkylate sulphonate as
methylene
15 31.5
Oil and grease 10 6.9
Nitrate (as N03-) 20 21
Phosphate (as PO43-) 5 50.7
Arsenic (as AS) 0.1 nil
Barium (as BA) 5 1.6
Turbidity 10 3
Iron (as Fe) 20 3.5
Manganese (as Mn) 5 0.20
Phenolic compounds (as phenol) 0.2 1.12
Chlorine (free) 1.0 16.3
Cadmium (Cd) Less than 1 0.1
Chromium Trivalent and hexavalent Less than 1 N/A
Copper Less than 1 N/A
Lead Less than 1 N/A
Mercury Less than 1 N/A
Nickel 0.5 N/A
Selenium Less than 1 N/A
Prepra nig ltd October 1, 2014
44
Silver 0.1 N/A
Zinc Less than 1 N/A
Total metals 3 N/A
Calcium (as Ca2+) 200 N/A
Magnesium (as Mg2+) 200 N/A
Boron (as B) 5 N/A
Alkyl mercury compounds Not Detectable N/A
Polychlorinated Biphenyls (PCBs) 0.003 N/A
Pesticides (Total) Less than 0.01 N/A
Beta emitters (µc/ml) 10-6 N/A
Coliform (daily average) 400 MPN/100ml N/A
4.1.2.2 Solid Waste disposal
A substantial amount of sludge consisting of fleshing and solid residue from the
liming made up of broken hair and other ancillary product such as plastic and
paper from packaging, residue of various chemical and greases are the major
constituents. A further component of the solid is dust from the buffing operation
as well as general sweepings. Data indicated that about 1200kg of these wastes
are generated daily from Larrabee operations. This is presently deposited on
land surface within the factory and is eventually evacuated after the box made
up of block is filled up. It is expected that when the waste slowly percolate
through the soil and gradually undergo oxidation by soil bacteria it would result
in the formation of harmless end products. However, it was observed that this
practice requires large areas of land that the company currently does not have;
it leads to bad smell; may contaminate underground water and can ultimately
Prepra nig ltd October 1, 2014
45
lead to poor agricultural productivity of the land. Also the polluted groundwater
eventually flows into a drinking water well or river resulting in the spreading of
waterborne diseases in the long run. Therefore remedial measures are required
immediately
4.1.2.3 Compatibility
The factory is located in Sharada industrial estate and is thus compatible with
the existing approved land use of section 3.2 of the National policy on
environment and Kano urban planning development authority requirement.
4.1.2.4 Fuel dump
Larrabee has 11,000 and 5,000 litres capacity surface storages for diesel.
Observation indicated that there is no oil/water separator. There is also no
mechanism to prevent leakages from the tanks and no contingency plan
against rupture of the tanks.
4.1.2.5 Cloakroom/Conveniences
There is no cloak room especially for the female employees who are about 9 or
15% of the total work force. More serious is the fact that there is no separate
toilet for women.
4.1.2.7 Safety signs
There are no safety signs to warn staff and visitors within the factory.
Prepra nig ltd October 1, 2014
46
4.1.2.8 Soil Analysis
Soil samples in six different process areas of the factory to get a
representative sample were analyzed in the laboratory to determine the
characteristics of the soil. The analysis is shown in Table 3. The purpose is to
use the data as baseline data for control/monitoring. Any change in the
parameter determined to be caused by the operation will have to be
ameliorated.
Table 3: Soil Analysis within Larrabee factory
Parameters Values measured
Ph 8.0
Temperature(°c) 23.9
Moisture content (%) 1.9
Base saturation (%) 85
Organic matter (%) 1.3
Oil and grease(mg/kg) 0
Total hydro carbon(mg/kg) 0
Nitrate(mg/kg) 63.1
Phosphate(mg/kg) 3.6
Chromium(mg/kg) 0
4.1.2.9 Muster point
There is no muster point within the factory
4.1.2.10 Fire extinguishes
No Fire extinguishers and where they exist they have expired
Prepra nig ltd October 1, 2014
47
4.1.2.11 Illumination
Illumination especially within the beam house is poor
4.1.2.12 Noise levels
Noise level within identified units of the Larrabee plant were measured and
compared with the NESREA permissible limits is shown in Table 4. Most units of the
Larrabee factory is within the limit but the area in the vicinity of the generating
room which also houses, the workshop and ETP are well above the limit and
considering the presence of workers all the time in the area constitute a risk to
the long term health of the workers.
Table 4 Noise level in some sections of Larrabee factory
Sites within Larrabee Noise level
NEAR THE GENERATOR HOUSE 108dB
AVERAGE WITHIN THE FACTORY 70dB
NEAR THE OFFICES 40dB
NESREA STANDARD FOR INDUSTRY 90dB
4.1.2.13Air Quality
Air qualities within identified units of the Larrabee plant were measured as shown
in Table 5. Most areas of the Larrabee factory has emission of gases within the
limit but the observed variation not only indicated differences in the levels of air
quality, but also potential problem that require attention especially the area in
the vicinity of the generating room and the Boiler.
Prepra nig ltd October 1, 2014
48
Table 5 :Air quality in the Larrabee factory
Sites within Larrabee CO N02 S02 H2S CH4
Near the generator/effluent
plant
2 3 0.67 1.81 0.11
Near the offices 0.2 0.3 0 0.1 0.0
4.1.3COMPLIACE WITH EXTANT REGULATIONS
4.1.3.1 Environmental Regulations
Section 7 (k) of the NESREA Act empowers NESREA to conduct
environmental audit and establish data bank on regulatory and
enforcement mechanisms of environmental standards other than in the oil
and gas sector
Section 8 (k) of the NESREA establishment Act also empowers the Agency
to make Regulations. One of such made is the “National Environmental
(Permitting and Licensing System) Regulations, 2009; S. I No. 29”
All the extant national sectorial environmental regulations require existing
industries to undertake environmental audit and submit reports every
three (3) years.
Section 1 (1) of Regulation S.I.8 of 1991
Section 3 (1) of Regulation S.I.8
Section 17 of Regulation S.I.9l
Prepra nig ltd October 1, 2014
49
Larrabee is in compliance with the existing regulations as enumerated
above by establishing a functioning effluent treatment plant and
engaging a NESREA accredited consultant to prepare an Environmental
Management plan (EMP) which has been submitted to NESREA and now
an Environmental Audit.
4.1.3.2 Compliance to other regulations
Larrabee is in partial compliance to most of the regulations, but needs to
be aware of the laws currently in place that require adherence to.
4.1.4 SOCIO-ECONOMIC IMPACT
Kano is known for its traditional leather and is famous in the tanning sub-sector
with international reputation. The bulk of leathers produced in Kano are
exported to Europe and Asia. Also, the artisanal producers convert finished
leather for domestic finished leather goods markets. Kano state has abundant
supply of skilled labor in the Tanning sector. This is obvious as commercial
production for leather and leather products existed for many years in Kano.
Leather and leather products are among the most widely traded and universally
used commodities in the world. Already, the total value of annual trade is
estimated at 1.5 times the value of the meat trade, more than five times that of
coffee and more than eight times that of rice. In Nigeria, according to the
Federal Ministry of Industry, Trade and Investment, leather has overtaken Cocoa
Prepra nig ltd October 1, 2014
50
as the second biggest foreign exchange earner for the country. A study by
Chemonics International Inc. prepared for the United States Agency for
International Development (USAID) in 2012 disclosed that Nigeria’s huge leather
industry export worth $43.4 billion is begging for investors. According to the
Report filed by Business Day, the industry is believed to be worth about $4.4
Billion for raw hides and skins, $14 billion in rough-tanned and finished leathers of
all types and $25 billion for footwear with leather uppers. This indicates high
exports potentials from the products. However, according to FAO current
production in Nigeria is still less than 40% of the potentials that exist in the tanning
sector. The aforementioned facts informed the decision of the Share-holders of
Larrabee enterprises limited to launch themselves into the leather processing
business.
Prepra nig ltd October 1, 2014
51
5.0 CHAPTER FIVE: RECOMMENDATIONS
5.1 GENERAL RECOMMENDATIONS
Larrabee needs to consider both the short and long term environmental
issues arising from its operations with a strong view to sustainable
development
Aesthetics and landscape of the frontage of the factory as well as the
areas surrounding the effluent treatment and waste water holding tanks
should be managed. A horticulturist should be engaged to enhance the
beauty of the surrounding by planting flowers and trees that could also
serve as a sink
There is the need to improve housekeeping especially around the effluent
plant and water holding tanks
The solid waste collection should be segregated through the provision of
bins of different colors with a view to recovery of such waste based on the
principles of cradle to grave or life cycle approach
The importance of the Materials safety data sheet for the different raw
materials especially chemicals should be made clear to the store keeper
And other production staff
Larrabee must integrate environmental issues in its operation by
introducing environmental accounting procedures to all its staff
Prepra nig ltd October 1, 2014
52
5.2 SPECIFIC RECOMMENDATIONS
5.2.1 Elimination of waste
Ensure constant monitoring to repair leaking hose/ pipe, a faulty
valve on a tanning drum, and from disconnected pipework. Minor
repairs can result in substantial water and effluent elimination.
Lights/Generators to be switched off during lunchtime (one hour)
and shift breaks. The lighting procedure can be a standard
practice by considering censor to control lighting in the toilets to
increase savings.
Steps be taken to ensure that empty cans are fully drained. This will
result in substantial reduction in spent chemical waste
Leaking oil from the bearings of drums and other equipment
should be monitored as well as the use of excess oil.
5.2.2 Reuse of waste on site
Collection of waste liquors from the soaking processes could
enable the recovery of, 260,000lites of water; 6900 liters of paraffin
for reuse (86% recovery) in subsequent batches.
5.2.3 Recycling of waste
Recycled polythene can be used as part of product packaging.
On average, 527kg of polythene are used each week.
Prepra nig ltd October 1, 2014
53
5.2.4 Disposal after compaction drying, or other treatment
Currently, Solid following coarse screening of effluent are collected
in open sumps. It is recommended now to transfer wet sludge to
slotted cages where it is left to drain for a week. The dried sludge
should then be transferred to a skip, which is sent to landfill. This will
reduce the chance of land pollution by 80%
1,300 kg fleshings/week are generated from typical processing of
50,000 skins/week. In the past, these fleshings were collected in skips
and disposed of to landfills. However, it is recommended that
through compaction, fleshings can be now handled as a solid
rather than a liquid waste eliminating hazard to soil and
groundwater.
5.2.5 Retention/redirection
This simply means determining uses for wastewater other than discharge.
Examples of redirection include using “clean” wastewater or using nitrogen-rich
wastewater as a fertilizer for plant grass areas. These approaches require close
attention to regulatory requirements.
Prepra nig ltd October 1, 2014
54
5.2.6 Separation/concentration
This should involve separating out solid or other materials from wastewater. Low-
technology options include installing drain screen, setting basins, or systems to
separate waste products out of wastewater before it is discharge.
5.2.7 Determination of specific water consumption
Specific water consumption is the volume of waster used per unit of production,
measured in m3 of product. Similarly, specific wastewater discharge is the
volume of wastewater discharge per unit of production, measured in m3 of
products. Establishing these figures will allow the industry to compare the
performance with benchmarks and that of other companies, regardless of
company size and variations in throughput. As well as measuring how much
water the industry is using, it is also useful to know how this consumption relates
to the industry’s levels of production and therefore pointer to whether Larrabee
is within industry limit or not. Above industry limit means the company is wasting
money in water bill and discharging more than is necessary.
5.2.8 Produce by products from the waste generated
Another best strategy that can be adopted in wastewater management is to
look for wealth from waste. For example because of the process by which
sewage collected, the solid content varies from 2-4%. They need to be pre-
processed before use in a digester (biomethanation) for energy production. The
Prepra nig ltd October 1, 2014
55
biogas so obtained can be used in engines. Clean sewage based biogas has
400-1500 ppm of hydrogen sulfide. Mixed sewage based biogas has 1-3%
hydrogen sulfide. Such a gas needs treatment before use in engines.
5.2.9 Reducing Noise level and Gaseous pollutants
Generators should be sound proof and provided with acoustic devices to
reduce high noise level. They should also be overhauled and serviced as at
when due to minimize the levels of SO2
5.2.10 Compliance to all extant regulations
Operations of establishments such as Larrabee are regulated and guided by
local, state and Federal legislations that are either in force now or will be
enacted from time to time. Larrabee enterprises limited must ensure that it is in
compliance with all extant laws and regulations at all times. Such compliance is
an indicator to integrity of the company.
5.2.11 General adherence to good management
Larrabee must put in place good cleanliness of its premises; ensure that all staff
are provided with appropriate uniforms and that they use them at all times;
illuminations in all sections of the factory; Explicit signs in strategic sections of the
factory; training of staff as enshrined in its EMP; Regular submission of effluent
analysis as at when due etc
Prepra nig ltd October 1, 2014
56
6.0 CHATER SIX; FOLLOW UP ACTION PLAN
6.1 Completion and submission of EA
6.1.1 Submission of EA report SEPTEMBER – 0CTOBER, 2014, to
i) NESREA NWZ, Kano
ii) NESREA Headquarters, Abuja
iii) Kano State Ministry of Environment
6.1.2 Monthly effluent monitoring and sending results to NESREA and
Kano state Ministry of Environment
6.1.3 Implementation follow on the management of the company’s
EMP
6.1.4 Provision of adequate safety equipment
6.1.5 Provision of firefighting equipment in strategic locations of the
factory identified
6.1.6 Awareness training for staff
6.1.7 Quarterly inspection
6.1.8 Establishment of quality assurance unit to ensure timely repairs to
leaking oil/water pipes
Prepra nig ltd October 1, 2014
57
7.0 CHAPTER SEVEN: CONCLUSION
This exercise examines the operations of Larrabee enterprises limited –
a tanning plant as well as the compliance status of the plant with
respect to environmental regulations and the contingency plans.
Relevant general and specific regulations in these regards were
proffered on the basis of the data collected during the exercise.
Prepra nig ltd October 1, 2014
58
APPENDIX 1
Environmental Audit Questionnaire
1.0 INDUSTRIAL IDENTIFICATION
1.1 Name and Address:
……………………………………………………………………………………………….
……………………………………………………………………………………………….
……………………………………………………………………………………………….
1.2 Type of Industry :
- Food, Beverages, Tobacco, Distilleries and Breweries
- Textile, Paint, Tanneries, Pulp and Paper
- Asbestos, Asphalt, Cement, Iron and Steel
- Petrochemicals, Plastics, Cosmetics, Chemicals/pharmaceuticals and Allied Products.
- Others (please state clearly).
………………………………………………………………………………………………
………………………………………………………………………………………………
1.3 Year of Establishment:
……………………………………………………………………………………………
……………………………………………………………………………………………
……………………………………………………………………………………………
1.4 Number of Employees
Total: ……………………………………………………………………………………
Plant employees: …………………………………………………………………………
- (indicate if you operate shift system) : Yes/No
If yes, specify shift periods:
…………………………………………………………………………………………………
………………………………………………………………………..
Prepra nig ltd October 1, 2014
59
1.5 Number of Working Days Per Week:
………………………………………………………………………………………………………
……………….
2.0 GENERAL SANITATION OF SURROUNDINGS:
2.1 How would you rate the general cleanliness of your surroundings?
- Above average
- Average
- Below average
2.2 How often do you clean your surroundings
- Once a week
- Fortnightly
- Monthly
- Other
2.3 Are there any beautification plans in place i.e planting of trees and/or shrubs? Yes/No
2.4 If yes, how frequent is the landscape managed.
- Once a week
- Fortnightly
- Monthly
- Yearly
- Other
2.5 How would you rate the conditions of your drains and pipes?
- Good
- Fair
- Poor
2.6 How do you keep the floors of your facility free from spent oil/grease and lubricants?
………………………………………………………………………………………………………
………………………………………………………………………………………………………
………………………………………………
Prepra nig ltd October 1, 2014
60
3.0 RAW MATERIALS:
Please list raw materials used and indicate quantities used per day.
(a)
List all raw materials including
industrial chemicals
(b)
Average quantities used per day
(Grms./ Kgs).
(c)
Storage conditions
……………………………………….
………………………………………..
……………………………………….
……………………………………….
……………………………………….
……………………………………….
………………………………….
………………………………….
………………………………….
………………………………….
………………………………….
………………………………….
………………………………
………………………………
………………………………
………………………………
………………………………
………………………………
4.0 PRODUCTS:
4.1 Please list your products and indicate quantities produced per day.
………………………………………………………………………………………………………
………………………………………………………………………………………………………
………………………………………………………………………………………………………
………………………………………………………………………………………………………
Prepra nig ltd October 1, 2014
61
5.0 INSTALLATION OF POLLUTION ABATEMENT EQUIPMENTS AND DATE
OF INSTALLATION
5.1 List all types of pollution abating equipment you have installed in your facility.
………………………………………………………………………………………………………
………………………………………………………………………………………………………
………………………………………………………………………………………………………
6.0 USE OF WATER
6.1 Please indicate source of water used in plant
- Well
- Municipal supply
- Surface water
- Borehole
- Other (specify)
…………………………………………………………………………………………………
6.2 How is the inlet water used and please specify volume used.
- Process ………………………………………………………………………… liters/day
- Cooling ……………………………………………………………………......... liters/day
- Boiler …………………………………………………………………………… liters/day
- Sanitation/ washing etc …………………………………………………………. liters/day
- Other (specify) ………………………………………………………………….. liters/day
- Total daily consumption …………………………………………… ………….. .liters/day
6.3 Please give a brief summary description of the processes involved in the use of
water
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
Prepra nig ltd October 1, 2014
62
………………………………………………………………………………………………
………………………………………………………………………………………………
6.3.1 Waste water
What are the means by which waste water is collected in your facility?
(Please indicate volume).
- Combined for all effluents……………………………………………. liters/day
- Separate for process water, domestic water,
Rain run-off …………………………………………………………… liters/day
- Other (specify) …………………………………………………………. liters/day
6.5.1 How many waste water outfalls are in your facility?
………………………………………………………………………………………………
6.5.2 Indicate volume discharge for each outfall……………………………. litres/day
6.6 TREATMENT
Do you treat your waste water Yes/No?
If yes
(specify)………………………………………………………………………………………
…………………………………………………………………………………………………
…………………………………………………………………………………………………
6.7 if yes (specify briefly summaries steps undertaken by your establishment in treatment of
waste-water before discharge)
………………………………………………………………………………………………………
………………………………………………………………………………………………………
………………………………………………………………………………………………….......
Prepra nig ltd October 1, 2014
63
If No, give reasons.
………………………………………………………………………………………………………
………………………………………………………………………………………………………
………………………………………………………………………………………………….......
6.8 Where do you discharge the treated/untreated water?
- Into general sewers (………………………….... liter/day)
- Into receiving waters (……………………………. liter/day)
- Recycle
-Reuse
6.9 What are your general observations on the quality of the receiving water (attach analysis log
sheet of the receiving water)
………………………………………………………………………………………………………
6.10 MONITORING
Are samples of the waste stream analyzed?
- Yes
- No
6.11 if yes please indicate frequency of sampling and analysis.
- Weekly
-Fortnightly
- Monthly
- Others (specify)
…………………………………………………………………………………………………..
Prepra nig ltd October 1, 2014
64
6.12 Please indicate which effluent monitoring methodology is used?
- USEPA
- UK Department of environment method
- NESREA (Nigeria Environmental Standards Regulations Enforcement agency)
- WHO/GEMS (World Health Organization/ Global Environmental Monitoring system)
- Others (Specify)
6.13 – Please attach your effluent analysis log sheet
7.0 SOLID WASTE
7.1 At what point along your production process do you generate solid wastes?
…………………………………………………………………………………………………..
…………………………………………………………………………………………………..
…………………………………………………………………………………………………..
…………………………………………………………………………………………………..
7.2 Do you have any waste segregation/sorting mechanisms or plans in place?
- Yes ……………………. No…………………………..
7.3 If Yes, how? / If No why?
…………………………………………………………………………………………………..
…………………………………………………………………………………………………..
…………………………………………………………………………………………………..
7.4 What is the total annual industrial solid waste generated by your firm……………….. kg/day
(give estimate)………………………………………….
Prepra nig ltd October 1, 2014
65
7.5 How do you manage your solid waste?
Compression/compaction:………………………………………………………………… kg
Recover from sorting:……………………………………………………………………. Kg
Incineration:………………………………………………………………………………. Kg
Store/bury in premises:…………………………………………………………………….. kg
Others (specify)……………………………………………………………………………. Kg
7.6 How do you dispose of your solid wastes?
………………………………………………………………………………………………………
………………………………………………………………………………………………………
7.7 Where is the final waste disposal site?
………………………………………………………………………………………………………
7.8 How do you treat and dispose of any corrosive, flammable or radioactive waste
materials?..........................................................................................................................................
7.9 How do you dispose of your expire raw materials and or products?
............................................................................................................................................................
............................................................................................................................................
8.0 GASEOUS WASTE:
8.1 List major air contaminants emitted by your facility.
......................................................................................................................................................
......................................................................................................................................................
......................................................................................................................................................
8.2 Indicate the type of gaseous emissions abatement equipment in place. (Filter,
scrubber, electrostatic precipitator, others).
.………………..…………………………………………………………………………
Prepra nig ltd October 1, 2014
66
…………………………………………………………………………………………….
……………………………………………………………………………………………..
8.3 What is the maintenance schedule if any?
……………………………………………………………………………………………..
11. ENVIRONMENTAL AUDIT
11.1 Do you have any in-house environmental pollution monitoring unit?
Yes ………………………………………. No…………………………………
11.2 Do you employ the services of a consultant to advice you on environmental issues from
time to time?
Yes ………………………………… No ………………………………….
11.3 Does your consultant have NESREA Accreditation?
…………………………………………………………………………………………………
…………………………………………………………………………………………………
11.4 When last did you carry out environmental audit on your facility?
…………………………………………………………………………………………………
…………………………………………………………………………………………………
11.5 Have you sent your audit report to NESREA office for review?
Yes ………………………………… No ………………………………….
11.6 Which of the recommendations in the audit report have you implemented?
Specify please……………………………………………………………………………
…………………………………………………………………………………………………
12.0 HEALTH AND SAFETY
12.1 Number of accidents recorded yearly within the last three years.
Year …………………………….. No. of accidents ……………………………….
Year …………………………….. No. of accidents ……………………………….
Year …………………………….. No. of accidents ……………………………….
12.2 Number of fatalities
Year …………………………….. No. of fatalities ……………………………….
Year …………………………….. No. of fatalities ……………………………….
Year …………………………….. No. of fatalities ……………………………….
Prepra nig ltd October 1, 2014
67
12.3 Number and type of illness reported by workers in the last three years
Type of illness ………………………. No. of staff………………………. Year ………
………………………. No. of staff………………………. Year ………
………………………. No. of staff………………………. Year ………
12.4 State the type of safety warning signs in place.
…………………………………………………………………………………………………
…………………………………………………………………………………………………
…………………………………………………………………………………………………
12.5 List the safety gears you provide for your staff
…………………………………………………………………………………………………
…………………………………………………………………………………………………
…………………………………………………………………………………………………
12.6 How do you enforce usage of these safety gears?
…………………………………………………………………………………………………
…………………………………………………………………………………………………
…………………………………………………………………………………………………
13.0 GENERAL
13.1 What impact do the activities of your facility have on the immediate environment?
…………………………………………………………………………………………………
…………………………………………………………………………………………………
…………………………………………………………………………………………………
…………………………………………………………………………………………………
13.2 Has there been any complaints from the public on the activity of your facility?
…………………………………………………………………………………………………
…………………………………………………………………………………………………