Design Solution for Ingot Handling and Machining - DiVA-Portal
-
Upload
khangminh22 -
Category
Documents
-
view
0 -
download
0
Transcript of Design Solution for Ingot Handling and Machining - DiVA-Portal
Design Solution for Ingot Handling and Machining
Konceptstudie för hantering och bearbetning av göt
Johan Jönsson
Faculty of Health, Science and Technology
Degree Project for Master of Science in Engineering, Mechanical Engineering
30hp
Supervisor: Mohamed Sadek
Examiner: Jens Bergström
7/9/2021
Abstract
At the electro remelting slag (ESR) facility at Uddeholm, cylindrical steel ingots are produced
in several different sizes. The ESR process requires a “starting step” that consist of a 20mm
thick steel plate and is a little larger than the diameter of the ingot. During casting the steel
plate is inevitably welded to the ingot, also a protective slag layer is also present and flows on
top of the melt when the ingot is produced. This layer is sacrificial and is removed before
forging. The plate consists of a different and unwanted material composition and must be
removed at some point to ensure the best material properties of the ingot. Current process
steps at Uddeholm causes the steel plate to be smeared out on the high-quality ingot. The
“impure” part of the ingot leads to extra waste and costs after forging. The ingots are cast
vertically but needs to be positioned horizontally to be transported to the forge, this is done
using an overhead crane and a clamp. This maneuver exerts excessive stress that damages the
crane and the clamp sometimes fails and drops the ingot. Because of the high-risk steps during
ingot handling as well as the extra waste that is created due to the starting step, the purpose
of this thesis is to develop a solution that can: move the ingots from a vertical to a horizontal
position in a controlled manner, a method to remove the starting step before forging and
reduce the overall risks during ingot handling. The goal is to develop a complete concept that
solves the problems mentioned so that the solution can later be realized.
To get a deeper understanding of the current procedures and problems, visits and meetings at
Uddeholm were carried out. This master thesis builds on the principle of the product
development process. Interviews with operators, managers, and other impacted employees at
Uddeholm were conducted in order to specify a product specification. To make the project
more fathomable, six sub functions were defined. Later a concept generation session using
the principles of brainstorming was held with engineers and managers at Uddeholm to find
new, plausible solutions to the problems. The results from the session were reviewed and some
solutions were discarded directly. Solutions that passed the screening was scored using a
weighted decision matrix based on a Kesselring matrix.
The chosen concepts were: milling to remove the starting step, “rotary axis grab” to rotate the
ingots, a conveyor belt to transport slag, a vacuum and conveyor belt to remove chips, a roll
bed with V-pallets to handle and transport the ingots, and let the slag fall of naturally when
horizontal. These solutions fulfill almost all of Uddeholm’s requirements and will significantly
increase the safety and profitability. The new solutions also bring in high flexibility for
production and will free up time for the operators.
The lifting tool of the solution needed to be structurally verified to prove it is a valid option.
This was done by analyzing the maximum stress in one part of the tool. The results gave that
it was indeed a feasible solution.
The whole product development process has proven helpful for this machine system. It has
especially proven useful for documenting all decisions made throughout the project. This
makes it easier for Uddeholm to adopt the solution and develop it further and later realize it.
Sammanfattning
På ESR-anläggningen i Uddeholm tillverkas cylindriska stålgöt i flera olika storlekar. ESR-
processen kräver ett "startsteg" som består av en 20 mm tjock stålplåt som är lite större än
götets diameter. Under gjutning svetsas oundvikligen stålplattan ihop med götet, förutom
detta finns det ett skyddande slaggskikt som flyter ovanpå smältan när götet produceras. Detta
lager är temporärt och tas bort innan smide. Plattan består av en annan, oönskad,
materialkomposition och måste tas bort någon gång för att säkerställa bästa
materialegenskaperna på götet. Nuvarande processteg vid Uddeholm gör att stålplattan
smetas ut på det högkvalitativa götet. Den "orena" delen av götet leder till extra spill och
kostnader efter smide. Göten är gjutna vertikalt men måste placeras horisontellt för att
transporteras till presssmedjan, detta görs med en travers och en klämma. Denna manöver
utövar överdriven stress som skadar traversen och klämman kan förlora greppet och tappa
götet. På grund av högriskoperationerna vid hantering av göt samt det extra spillet som skapas
på grund av startsteget, är syftet med detta examensarbete att utveckla en lösning som kan:
Flytta göten från en vertikal till en horisontell position på ett kontrollerat sätt, en metod för
att ta bort startsteget före smide och minska de totala riskerna vid hantering av göt. Målet är
att utveckla ett komplett koncept som löser de nämnda problemen så att lösningen senare kan
realiseras.
För att få en djupare förståelse för nuvarande rutiner och problem, hölls besök och möten på
Uddeholm. Det här examensarbetet bygger på principen för produktutvecklingsprocessen.
Intervjuer med operatörer, chefer och andra berörda medarbetare på Uddeholm genomfördes
för att specificera en produktspecifikation. För att göra projektet mer hanterbart definierades
sex underfunktioner. Senare hölls en konceptgenereringssession styrt av principerna för
brainstorming med ingenjörer och chefer på Uddeholm för att hitta nya, troliga lösningar på
problemen. Resultaten från sessionen granskades och vissa lösningar kasserades direkt.
Lösningar som klarade utsållningen gick vidare och rankades med hjälp av en beslutsmatris
baserad på en Kesselring-matris.
De vinnande koncepten var: fräsning för att ta bort startsteget, En “rotating axis grab” för att
rotera göten, ett transportband för att transportera slagg, en dammsugare- och transportband
för att ta bort spån, en rullbotten med tillhörande V-pallar för att hantera och transportera göt
samt att låt slaggen falla av naturligt när götet är horisontellt. Dessa lösningar uppfyller nästan
alla Uddeholms krav och kommer att signifikant öka säkerheten och lönsamheten. De nya
lösningarna ger också hög flexibilitet för produktionen och frigör tid för operatörerna.
En del av lösningen behövde verifieras strukturellt för att bevisa att det är en giltig lösning.
Detta gjordes genom att analysera maximal spänning i en del av verktyget. Resultaten visade
att det var en realiserbar lösning.
Hela produktutvecklingsprocessen har visat sig vara användbar för detta maskinsystem. Det
har visat sig användbart för att dokumentera alla beslut som tagits under hela projektet. Detta
gör det lättare för Uddeholm att ta sig an projektet och utveckla det vidare och senare
förverkliga det.
Table of Contents Abstract ...................................................................................................................................... 2
Sammanfattning ........................................................................................................................ 4
1. Introduction ........................................................................................................................... 1
1.1 Background ....................................................................................................................... 1
1.2 About Uddeholm .............................................................................................................. 1
1.3 Current Procedures ........................................................................................................... 1
1.3.1 ESR ............................................................................................................................. 1
1.3.2 Forging press .............................................................................................................. 4
1.4 Problem formulation ........................................................................................................ 4
1.5 Purpose and Goal .............................................................................................................. 4
1.6 Limitations ........................................................................................................................ 5
2. Theory .................................................................................................................................... 5
2.1 The Generic Product Development Process ..................................................................... 5
2.1.1 Planning ...................................................................................................................... 5
2.1.2 Concept Development ................................................................................................ 5
2.1.3 PFMEA ....................................................................................................................... 8
2.1.4 Concept Selection ....................................................................................................... 8
3. Method ................................................................................................................................... 9
3.1 Planning ............................................................................................................................ 9
3.2 PFMEA ............................................................................................................................. 9
3.3 Identifying Customer Needs ............................................................................................ 9
3.4 Product Specification ....................................................................................................... 9
3.5 Concept Generation .......................................................................................................... 9
3.6 Concept Selection ........................................................................................................... 10
3.7 Further Development ..................................................................................................... 10
3.8 Structural Verification .................................................................................................... 11
4. Results .................................................................................................................................. 12
4.1 Planning .......................................................................................................................... 12
4.2 PFMEA ........................................................................................................................... 12
4.3 Analysis of Current Procedures ...................................................................................... 12
4.3 Product Specification ..................................................................................................... 13
4.4 Concept Generation ....................................................................................................... 13
4.4.1 Search Externally ..................................................................................................... 13
4.4.2 Search Internally ..................................................................................................... 13
4.5 Concept Selection ........................................................................................................... 14
4.5.1 Removal of Starting step .......................................................................................... 14
4.5.2 Tipping Mechanism ................................................................................................. 16
4.5.3 Slag Removal ........................................................................................................... 18
4.5.4 Slag Handling .......................................................................................................... 19
4.5.5 Chip Removal ........................................................................................................... 19
4.5.6 Handling and Transport of Ingots ........................................................................... 20
4.5.7 Structural Verification of Rotary Axis Grab ............................................................ 22
4.5.8 Combined Concepts ................................................................................................. 25
5. Discussion ............................................................................................................................ 27
5.1 Further Development ..................................................................................................... 28
6. Conclusion ........................................................................................................................... 29
7. Acknowledgements .............................................................................................................. 30
8.References ............................................................................................................................. 31
9. Appendixes ........................................................................................................................... 32
Appendix A- Explanation of Concepts ................................................................................. 32
Appendix B- Preliminary Gantt Schedule ............................................................................ 38
Appendix C- Project FMEA .................................................................................................. 38
Appendix D- PFMEA ............................................................................................................ 39
Appendix E- Product Specification Tipping Mechanism .....................................................40
Appendix F-Product Specification Machining ..................................................................... 41
1
1. Introduction
1.1 Background
Electro slag remelting (ESR) is an important step when creating high quality steel. ESR has
been used in the industry since the 1960s because of solidification and chemical homogeneity
control. The process starts with an electrode that is suspended in a mast assembly with vertical
translation control. The electrode is put inside a water-cooled mold with a so-called starting
step at the bottom. The starting step consists of a steel plate and a reactive slag bath. A strong
electric current is passed through the mold and the electrode and an electric arc is formed at
the bottom of the electrode. The electrode starts to melt due to the high temperature and it
starts to drip droplets of molten metal to fill the mold. The molten metal falls through the slag
layer and the mold slowly fills and solidifies. Since the metal is passing through the reactive
slag bath, the material purity is increased and inclusions become very small and evenly
distributed. The slag continuously floats on top of the melt and is later removed once the ingot
solidifies. The remelting of the electrode creates a new ingot [1].
The steel plate that is the starting step is still attached to the ingot. It consists of a different
and unwanted material composition and must be removed at some point to ensure the best
material properties of the ingot. Current process steps at Uddeholm causes the steel plate to
be smeared out on the high-quality ingot. The “impure” part of the ingot leads to extra waste
and costs after forging. Apart from the extra waste material, there are several high-risk actions
during ingot handling, especially the “tipping” of the ingot. During tipping the ingot might fall
and hot slag might fall off and hit nearby operators.
1.2 About Uddeholm
Uddeholm is a global provider and manufacturer of tool steels situated in Hagfors, Sweden.
The history of ironmaking at or near Uddeholm is old, ironmaking started in 1640 and has
continued ever since. Uddeholm has a large plant with several departments such as: steel mill,
ESR, forge, rolling mills, heat treatment facilities, machining, an extensive research and
development department and more [2].
1.3 Current Procedures
At the ESR facility there are several ESR furnaces operating full time. The ingots that are
produced vary depending on customer needs and what furnace is used. Below is a description
of the current standard procedures that Uddeholm is following at the moment.
1.3.1 ESR
ESR is a process where an electrode of the specified composition is remelted using electricity
[1]. A thick slag layer is present at the top of this melt and protects the steel against oxidation.
This produces a higher quality ingot that can later be forged to the right shape and dimensions
[3]. In more detail, ESR uses a two-piece water-cooled casting form that is removable. The
whole ESR process is built upon a starting step. The starting step consists of a round steel plate
that is 20mm thick and has a diameter that is a bit larger than the final cast ingot. The diameter
2
of the starting step is in the range of 400-1500mm. A schematic figure of the ESR setup is
shown in Figure 1.
Figure 1. A schematic figure of the ESR process
After the remelting process, the casting mold is removed and a hot ingot with the thick slag
top becomes exposed. At this stage, the ingot is picked up using a clamp operated by an
overhead crane. The ingot is placed on a cutting table and a cooling hood is placed over it. The
cooling hood protects workers against heat radiation and spatter and falling debris from the
slag top. When the ingot is cooling the differential heat expansion makes the slag top unstable
and it might even spontaneously crack and fall off. Slag and debris around the bottom of the
ingot is scraped off by an operator into the cutting table, which also works as a waste bin. When
the waste bin is filled it is sent away for reconditioning since waste gets trapped and stuck. The
starting step steel plate is oversized and the extra part of the starting step is removed using a
cutting torch. This produces steel rings that are discarded. These steps are shown in Figure 2.
3
Figure 2. The figure illustrates how the ingot is picked up and later processed under the cooling hood
After the cutting operation, the ingot is cool enough to remove the cooling hood. The next step
is to remove the slag top, this is done using the clamp and overhead crane. The clamp picks up
the slag top and lifts it to a waste container, this is done after the cooling hood is removed.
There are several risks present during this step: the slag top might be unstable and crack
during the lift, it might fall out of the clamp etc. After the slag top removal, there is just the
ingot and the starting step left. The next step is to pick up the ingot and put it on a pallet for
transportation. This lift is also done with the clamp. The operator grabs the top of the ingot,
places it on the ground and moves it sideways to make it fall over. This operation puts
damaging stresses on the overhead crane and on several occasions, the ingot is accidentally
released from the clamp and falls to the ground. The ingot is placed on a pallet and transported
to the forge. Figure 3 shows the last two steps done in the ESR facility.
Figure 3. Removal of the slag top and the tipping of the ingot
4
1.3.2 Forging press
At the forge the ingot is preheated and forged. When the ingot is forged, the starting step is
smeared out on the “good” material. This leads to large cutoffs, since all material containing
the starting step must be removed, costing a lot of money. Uddeholm created a “knife” that
can be used to scrape off the starting step to minimize waste. This solution has been working
quite well but it is hard to use according to the operators and there is always some
contamination left leading to some spill material. On average, only 20-40% of the starting step
is removed by the knife. Forging is time critical since materials properties change with
temperature. There is a small temperature interval where forging can be done and since time
is lost when using the knife this step can lead to problems. It takes on average 1-2 minutes to
remove 20-40% of the starting step. Figure 4 below illustrates these steps.
Figure 4. Press forging process steps with starting step removal using the knife
1.4 Problem formulation
Due to the high-risk steps during ingot handling, a new, safer, procedure is needed. A solution
that can move the ingots from vertical to a horizontal orientation with greater control to reduce
the risks is to be developed. In addition, a solution that can remove the unwanted material
before forging to reduce the extra wastage and costs due to material loss is also meant to be
found. Uddeholm needs a highly reliable solution that can cooperate with all the different
types, compositions, and quantities of ingots currently and in future production. Both
solutions, i.e., a material handling solution and a material removal solution, are to be packaged
in a module that will be installed in a specific area in the ESR-facility at Uddeholm.
1.5 Purpose and Goal
The purpose of this project is to increase safety, efficiency and reliability when handling ESR
ingots at the ESR facility at Uddeholm due to the facts stated in section 1.2.
The goal is to present a finished concept and a model for Uddeholm so that they can later
realize the machine.
5
1.6 Limitations
To make this problem more fathomable and feasible, there are some limitations:
● It will be a concept study; the thesis will not include complete drawings and
manufacturing specifications.
● The space and location where the machine are supposed to be installed is defined.
● The machine must be able to be CE marked.
● The thesis is limited to be made on 800hrs of work, this corresponds to 30hp.
2. Theory
2.1 The Generic Product Development Process
The generic product development process can be divided into six different phases [4]:
1. Planning
2. Concept Development
3. System Level Design
4. Detail Design
5. Testing and Refinement
6. Production Ramp-Up
These steps help the product developer work in a systematic way. The reasons for working in
this way is that it can ensure that the project can stay controlled and ensure higher quality in
the end. The systematic approach also leads to good documentation which can help future
development. As stated in section 1.6, only phase 1 and 2 will be in the scope of this project.
2.1.1 Planning
The purpose of the planning phase is to give the whole project an overall aim. The planning
phase will result in a project plan that will work as a contract between the different parties.
The project plan is an essential document since it can become a guideline for the remaining
process. The plan will help to estimate and visualize the efforts that are necessary for
completion. It usually contains a background, goals, time plan and a project risk analysis. The
project risk analysis helps the product developer understand what risks are present, and help
reduce them before they become a problem [4].
2.1.2 Concept Development
A product concept is an abstract idea that contains the fundamental form, function and
technology of a final product. According to the book Product Design and Development [4], the
quality of the underlying concepts has a major impact on the final product. The concepts are
based on the product specification, this requires that the product specification is complete and
meets the customer’s needs well.
6
The book also introduces a 5-step process for concept development:
1. Clarify the problem. Understand the issue and decompose it into simpler subproblems.
2. Search externally. Gather information from lead users, experts, patents, published
literature and related products.
3. Search internally. Use individual and group methods to retrieve and adapt the
knowledge of the team.
4. Explore systematically. Use classification trees and combination tables to organize
the thinking of the team and to synthesize solution fragments.
5. Reflect on the solutions and the process. Identify opportunities for improvement in
subsequent iterations or future projects.
2.1.2.1 Step 1. Clarify the Problem
In the first step, the main problem is made simpler and perhaps broken down into
subproblems that are easier to comprehend. This decomposition of the problem can be done
with different perspectives such as: Decomposition by sequence of user actions or
decomposition by key customer needs [4].
2.1.2.1.1 Identifying Customer Needs
David Dunne [6] writes about the importance of customer centered needs. A good relation and
communication between the customer and the project are important to ensure the greatest
outcome that benefits both parties. A systematic approach is important so that the developer
does not miss any information that might be vital for the project. This includes both obvious
needs and latent needs that the customer has a hard time communicating or sometimes
doesn't even know [6]. To understand what the customer wants, the book suggested these
steps [4]:
1. Gather raw data from customers.
2. Interpret the raw data in terms of customer needs.
3. Organize the needs into a hierarchy of primary, secondary, and (if necessary) tertiary
needs.
4. Establish the relative importance of the needs.
5. Reflect on the results and the process.
In short, all of these steps are done so that nothing is missed. It is crucial to understand the
application of the product and listen to what the customer wants and reflect on that result.
After gathering information, it should be analyzed in a positive and systematic manner to
ensure that the customer is in focus.
2.1.2.1.2 Product Specification
When the customer needs are identified and documented, it leads to the product specification.
The product specification allows the project to evaluate precise targets, tell if the product is a
success or failure and understand how different choices will affect the product´s performance.
This is done by taking the perhaps unclear customer needs and transforming them into
measurable and precise specifications. The product specifications tell the project what the
product must do [5]. This document will also become the starting point for the concept
development phase.
7
The specifications can be divided into two main categories. They can be related to the final
product’s assumed function or they can set limitations on what design solutions are possible.
Functional properties are treats that are associated with the function of the product.
Limitations could for example be size and cost of the product, i.e., criteria that limits the
product development opportunities. Furthermore, the product specifications can be divided
into demands and wishes. Demands are specifications that the product must fulfill and wishes
are specifications that are not essential to complete. The wishes should be graded based on
how much the customer would want them to be fulfilled. To call the product complete all
demands must be fulfilled and the wishes may be partly met [4].
In order to visualize and analyze the specifications, they are put in checklists. The lists should
also contain a metric by which the specification can be compared with. Some specifications
are not easily measured but it is favorable to have some metrics. By doing this, the project
team will be able to systematically approach the criteria and what aspects that will be taken
into consideration during the development [4].
2.1.2.2 Step 2. Search Externally
To search externally is the process of finding already existing solutions and adapting them to
the project. This should be done continuously since it can greatly speed up development. If
there already are reasonable solutions, there is no need to spend unnecessary time on that
area. The effort should be focused on other parts of the project that preexisting solutions can’t
solve. Sources for these kinds of solutions can be found in competitive products as well as
technologies with similar functions as the developed product [4].
2.1.2.3 Step 3. Search Internally
Internal search is personal or project group information gathering. All of the knowledge,
competence and ideas of the project members themselves are used in this step. Usually this
becomes a creative process with different methods to explore and produce lots of ideas. One
of these methods could be brainstorming or something similar [4].
2.1.2.3.1 Brainstorming
Brainstorming is a creative internal concept generation process. It was developed in the 1960s
by Alex Osborn. Brainstorming can be done both individually as well as in a group with
different benefits. This method is considered to be good at generating a large number of ideas
in an open-minded way. The large number of ideas may result in several ideas that are non-
relevant and impossible but some might be good ideas worth developing. In order to get an
effective and productive brainstorming session, a good mix of different people with different
backgrounds are desirable [7].
There are some rules that need to be followed according to Osborn:
● No criticism, the ideas that are generated should not be analyzed or rejected during the
session.
● All ideas are welcome no matter how different they may be. All participants should feel
secure to propose any idea that they find relevant.
● To improve and build on other participants ideas are welcome.
● The main objective is to generate as many ideas as possible.
8
Before the session begins, the participants should be informed of the rules and the background
of the problem. Ideas from the participants are passed through the leader of the session that
documents everything. After the session, all of the ideas are looked at again and may be
discarded if they are found to be irrelevant [7].
2.1.2.4 Step 4. Explore Systematically
From step 2 and 3, the project will have several “concept fragments”. These concept fragments
must now be sorted and systematically chosen to create complete concepts. There are several
methods to help organize the number of generated concepts, often several hundred are created
but many of them can be discarded right away [4].
2.1.2.5 Step 5. Reflect on the Solutions and the Process
The last step is supposed to be done continuously throughout the development process.
Questions that the project group should ask themselves could be: Is this relevant? Is it
feasible? Are all possibilities explored? Etc. [4].
2.1.3 PFMEA
PFMEA (Process Failure Mode and Effect Analysis) is a risk analysis of a process and the
equivalent of an FMEA for a product. The method builds upon identifying what risks can occur
during a process, rank the risks, and give proposals for preventions. The first step is to identify
what types of risks that can occur during the process. After that, the risks are given a score
based on the severity of the risk, how often it could happen and how easy it is to discover.
These scores are multiplied and the risk is given a risk score. 1-100 is considered a low risk
(green), 101-300 high risk (yellow) and 301-1000 is the highest risk (red). The yellow and red
risks are given more consideration and solutions to reduce the risk should be proposed. After
the review the risks are reevaluated and given a new risk score [5].
2.1.4 Concept Selection
Concept selection is the process of evaluating concepts. This is done with respect to customer
needs and other criteria, comparing the relative strengths and weaknesses of the concepts, and
selecting one or more concepts for further investigation or development [4].
2.1.4.1 Weighted Decision Matrix
In this decision process all of the relevant criteria are used to decide which concept to use. The
criteria are weighted from 1-5 where 5 is the most important. After the concepts are scored
according to the requirements, the score ranges from 1-5 where 5 is the highest. Then the
weight and scores are multiplied and summarized and the concept with the highest score is
chosen. This type of matrix is based on a Kesselring matrix but with some minor adjustments
to better suit the application [5].
9
3. Method
3.1 Planning
The background, problem formulation and goals are already stated in the beginning of this
report. But, to aid the planning of the entire project a project FMEA and a GANTT- schedule
was made to minimize risk and give a rough time span of the different stages of the project. A
GANTT-schedule is a good method of visually represent a timeline with several different tasks.
3.2 PFMEA
A PFMEA was developed by analyzing each process step separately and identifying as many
risks as possible. The document was updated throughout the project as more and more
solutions were implemented. All solutions and improvements were developed through
discussions and brainstorming.
3.3 Identifying Customer Needs
In order to get the information necessary, a visit to Uddeholm was made. The visit was planned
carefully according to previously written section 2.1.3 so that nothing would get missed.
During the visit, several meetings and interviews with managers, operators and other involved
employees were held to understand their experiences and vision of the problems. All of the
collected data was used to analyze the current procedures and to formulate a requirement
specification.
3.4 Product Specification
With the information given from Uddeholm, visits at the plant and interviews with affected
employees, an idea of what the solution had to solve was formed. The idea was refined using
the methodology of Ulrich [4]. An online meeting was carried out with the supervisor at
Uddeholm to set the first version of the product specification. The product specifications were
divided into two sub functions, the tipping operation and the machining operation. For each
sub function, criterions were set. They were divided into demands, wishes, limitations and
functions. The wishes were weighted according to how important they were to fulfill.
3.5 Concept Generation
The first step in the concept generation phase is to clarify the problem. The problem was
decomposed mainly by the sequence of user actions, but also key customer needs. It was
quickly concluded that no real equivalent applications that are at least publicly accessible that
can give hints of ready-made solutions. The problem spans several fields and is complex with
a lot of underlying functions. Therefore, a brainstorming session was carried out to give a quick
understanding of the different sub functions and their sub problems.
A concept for the tipping mechanism had already been developed by Uddeholm several years
ago. There are drawings and some calculations but according to Uddeholm this information is
to be seen as inspiration and not a complete solution.
10
The literature states the importance of both individual and group concept generation sessions,
therefore a session with four employees at Uddeholm was planned and performed. The group
members came from different backgrounds, such as mechanical designers as well as
operational managers. The session started with a presentation of the main problem and the
rules of the session. All of the sub problems that were found during the functional analysis
were used as topics for the discussion. All the participants were also given papers to write or
sketch ideas for themselves or present the to the other participants.
Discussion topics that were presented:
● Tipping Mechanism
● Slag Removal
● Slag Handling
● Chip Removal
● Removal of Starting Step
● Handling and Transport of Ingots
All useful and discussed ideas generated were compiled and documented afterward. A lot of
ideas were generated and therefore quick screening with the concept group was done to
eliminate impossible ideas to minimize the total number of solutions.
3.6 Concept Selection
With that many ideas several thousand combinations of total solutions were possible. To solve
this problem, the sub concepts for each sub function were put into a weighted decision matrix
in order to minimize the number of total solutions. Criteria were taken from the relevant
product specification. However, some of the requirements in the specification were not
directly applicable to each function. Therefore, additional aspects connected to these functions
were added to the chart to keep relevance. Scoring decisions were supported by relevant
knowledge as well as relativity to the other concepts. For example: if one solution is clearly
more expensive than another, that solution will get a lower score compared to the cheaper
option from a cost perspective. After scoring, the winners from the weighted decision matrices
were combined into a complete solution.
Some of the concepts were sketched to better visualize and remember the vital elements
correctly. These visualizations can be seen in appendix A.
3.7 Further Development
The best concept was roughly constructed in SOLIDWORKS in order to visualize the most
important features. The overall layout and positioning of the functions within the machine was
the most important aspect that needed to be analyzed. It is important that the machine system
can fit within the prescribed area and give a good workflow for the rest of production.
11
3.8 Structural Verification
When the concept had been visualized and put into context with the rest of the system, a size
estimate of the machine could be made. The overall size scaled the dimensions of the
individual components, these dimensions were used when calculating critical stresses in one
of the components and altered using the trial and error method [8].
12
4. Results
4.1 Planning
The Gantt-schedule and project FMEA can be found in appendixes B and C. The most critical
risk that was identified was “Bad results”. This refers to results that would require more work
later in the project leading to delays, bad results, etc. Actions to reduce this risk were taken in
the form of a “front heavy” project planning and good communication with people
surrounding the project. Those actions would decrease the risk of miss steps early on and give
confidence that the methods are correct.
4.2 PFMEA
The PFMEA can be seen in Appendix D. The most considerable risk was “slip and fall” with a
score of 560 due to the high-risk effect, high occurrence rate and difficult to detect. Measures
suggested to lower the risk were: clean work floor, fences and railing. After those measures,
the score dropped to 60, which became the highest risk score of all identified risks after
reevaluation.
4.3 Analysis of Current Procedures
To understand and justify the need for a change, an analysis of the current procedures was
made. The analysis was based on the interviews and data that were collected during meetings
and visits at Uddeholm.
The most important aspect that is brought from the current procedures is hazards. Several
steps in the ingot handling in the ESR facility can be classified as highly dangerous. When the
ingots first come out of the mold, they are still 200-600°C and because of their relatively large
thermal mass the heat remains for a long time. The slag that sits on top of the ingot becomes
more and more unstable and has a higher chance of breaking and spalling as the ingot cools.
Since the operators are working so close to the ingot this is not as safe as possible. The most
dangerous moment is the tipping of the ingot, the clamp that is carrying the whole weight of
the ingot requires a good grip that can sometimes be unpredictable. The overhead crane is not
designed to take loads other than vertical. When the operator is tipping the ingot, the crane is
driven sideways to initiate the tipping. This puts lots of stress on the guide ways and
mechanical components of the crane. Which lead to mechanical failures and a shorter service
life. The most serious hazard is that the ingot can fall and roll away, leading to fatal accidents.
Other important factors are the economic benefits Uddeholm can obtain by solving the
starting step problem. High quality tool steel is expensive and waste is supposed to be
minimized. After discussions with one of the managers at the forge it was clear that the waste
problem needed to be fixed. The current procedure with the knife is not favored by the
operators. The operators already have time pressure and do not want to struggle with the knife
tool. It is not uncommon that the knife operation takes too long so that the work piece needs
to be reheated during forging and increases the cost. Also, the knife gets worn very quickly
reducing its performance. The forging press is manual meaning that the operators must
maneuver the work pieces by sight whilst sitting several meters away. This is hard to do and
13
requires skill. Finally, how hard the starting step has been welded to the ingot is dependent on
the ingot material. Sometimes the starting step falls off easily, while other times only a few
percent can be removed giving very little to no benefit to the final result. In summary, several
benefits can be achieved by removing the starting step before forging.
Production states that they would like a solution with a buffer where several ingots can sit and
wait for processing. Right now, there is no certain time interval at which the ingots are
finished. There might be several ingots that are finished at more or less the same time and
creating bottlenecks in production. A solution that can handle several ingots at the same time
would be advantageous since the production volume is expected to rise in the future.
Interviews also gave information on lead times. According to the forging shop manager, the
time between the ingot leaving ESR and arrives at the forge is insignificant. This is because the
forging shop cannot assure that the ingots get put in the preheating ovens immediately and
may rest for several hours before they do so. This implies that the speed at which the ingot
must arrive is non crucial.
4.3 Product Specification
The product specification can be found in appendixes E and F.
4.4 Concept Generation
4.4.1 Search Externally
Extensive searches for already existing solutions were done during the whole concept
development phase. Literature, articles, videos, study visits etc. were analyzed to find ideas or
solutions that could aid the design process. It was quickly discovered that some parts of the
problem formulation involved machinery that is not readily used in other industries, or at least
not publicly accessible information regarding those applications. Instead, a lot of information
was gathered from study visits at Uddeholm, who has been developing unique solutions for
their own problems throughout the years. Solutions regarding chip handling, milling,
clamping methods, pallet systems etc., was found at the machining facility at Uddeholm.
Equipment made to rotate objects were found when searching on the internet. The most
promising solution that was found is a lifting tool called “rotating axis grabs”. Rotating axis
grabs are manufactured by several manufacturers and can be customized for special
applications. Several versions are present with motorized functions and different loading
capacities.
Numerous manufactures that construct and sell rotating axis grabs were found and they were
subsequently contacted on behalf of Uddeholm.
4.4.2 Search Internally
The Brainstorming session was creative and successful, it generated several ideas and aspects
for every single topic. Excluded solutions were excluded before scoring since they were deemed
improbable and might not fulfill the customer demands.
14
4.5 Concept Selection
Here are the results from the concept generation session and the results from the concept
selections (table 1-14).
4.5.1 Removal of Starting step
Table 1. Results from the concept generation session of Removal of starting step and reasons for exclusions
Removal of starting step Reason for exclusion
Milling
Thermal Oxygen Lance
Cutting Torch
Turning Will take too much time
Plasma Cutter Material thickness too great
Laser Material Thickness too great
EDM Will take too much time
Bandsaw Will take too much time
Freeze and break
Would require improbable cooling,
uncontrollable
Acid Bath High risk, steam formation
Slag Bath High risk and uncontrollable
Induction Heater Uncontrollable
The reason “uncontrollable” refers to that it is not obvious that all of the starting step is
removed and without taking other material with it. “High risk” refers to excessive danger with
toxic and hot substances that might harm operators. “Improbable cooling” refers to the fact
that the largest ingots weigh more than 26 metric tons and have a temperature of 300°C
cannot be cooled rapidly enough.
15
Table 2. Results from the weighted decision matrix
Concept 1 Concept 2 Concept 3
Project
description:
Milling Thermal Lance Cutting Torch Removal of
Starting Step
Criteria:
Weig
ht
1....... 5
Po
int
1 ....... 3
V x
P
Co
mm
ent
Po
int
1 ....... 3
V x
P
Co
mm
ent
Po
int
1 ....... 3
V x
P
Co
mm
ent
User Friendly 5 3 15 1 5
Requires
manual
operation 3 15
Easy
Maintenance 5 2 10
Requires
some
maintenance 3 15 3 15
Simple/few
parts
Easy
Installation 5 2 10
Requires
rebuilds 3 15 3 15
Easier than
concept 1
Cost 5 2 10
Quite
expensive
initially and
running 3 15 Cheap 2 10
Requires
machinery
CE-Marking 5 3 15 Possible 3 15 Possible 3 15 Possible
Cycle Time 5 3 15 Fast 1 5 Slow 1 5 Slow
Automatic
Operation 4 3 12 Possible 1 4 Not possible 3 12 Possible
87 74 87
The concepts with the highest scores are Milling and Cutting torch. Thermal lance scores the
lowest since it requires manual operation and is not automatable. Milling requires expensive
machinery and high running cost relative to concept 2 and 3. But it offers high controllability
and is the fastest of the three. According to a supplier the cycle time for the milling operation
is less than 5 minutes and the noise level will be lower compared to concept 2 and 3. A specific
cycle time is not determined for concept 2 and 3 but it will be significantly longer compared to
concept 1. Therefore, concept 1 is the chosen concept.
16
4.5.2 Tipping Mechanism
Table 3. Results from the concept generation session of Tipping mechanism and reasons for exclusions
Tipping mechanism Reason for exclusion
"Tipp Chair"
"Seesaw"
"Manipulator"
Rotary Axis Grab
"Flip Truck" Requires extra operators
Details on the concepts are shown in appendix A. The “flip truck” was deemed improbable
because it would most likely require an additional employee to man the truck which is not
necessary for the other concepts. Table 4. Results from the weighted decision matrix
Concept 1 Concept 2 Concept 3
Project description: Tipping Chair Seesaw Rotary Axis Grab Manipulator
Tipping Mechanism
Criteria: Weig
ht 1....... 5
Po
int 1 ....... 3
V x
P
Co
mm
ent
Po
int 1 ....... 3
V x
P
Co
mm
ent
Po
int 1 ....... 3
V x
P
Co
mm
ent
Po
int 1.......3
V x
P
Co
mm
ent
User Friendly 5 3 15 3 15 2 10
Requires
manual
input 3 15
Easy Maintenance 5 2 10
Several
mechanical
systems 2 10
Several
mechanical
systems 2 10
Several
mechanical
systems 2 10
Several
mechanical
systems
Easy Installation 5 2 10
Large
construction 2 10
Large
construction 3 15
No
installation 2 10
Large
construction
Cost 5 2 10
Large
construction 2 10
Large
construction 2 10 2 10
Large
construction
CE-Marking 5 3 15 Possible 3 15 Possible 3 15 Possible 3 15 Possible
Able to Handle Pallet
system 3 2 6
Would be
difficult 2 6
Would be
difficult 3 9 Compatible 2 6
Would be
difficult
Side Motion for
Tipped Ingots 4 2 8
Would be
difficult 2 8
Would be
difficult 3 12 Possible 2 8
Would be
difficult
Slag Removal System
Compatibility 5 2 10
Could be
difficult 2 10
Could be
Difficult 3 15
Does not
matter what
system 3 15
Does not
matter
Automatic Operation 4 3 12 Possible 3 12 Possible 2 8
Would be
difficult 3 12 Possible
96 96 104 101
17
Concept 3 is the winner of the selection. Concept 3 scores highest on easy installation
compared to the other concepts, this is because it is a standalone tool that does not require
foundations or other permanent installations. All of the concepts are given the same score on
cost since no estimation has been determined. Concept 3 is the only concept that is deemed to
be able to use the pallet system. No other concept will easily implement a function that involves
loading pallets. Side motion is graded on the same basis as “be able to use the pallet system”.
“Slag removal system compatibility” refers to the integration with a slag removal system.
Concept 1 and 2 scores lower since they are deemed free access of the slag top, concept 4 gives
free slag end access and concept 3 would transport the ingot further to some other solution
that would handle the slag. Automatic operation could be possible for concept 3 but is deemed
difficult since it utilizes the existing manual overhead crane. More details about the different
concepts can be seen in Appendix A.
The winning concept was concept 3. More details can be seen in Figure 5 below.
Figure 5. "Rotary axis grab"
The rotary axis grab is a lifting tool that can grab and then rotate the grabbed object around
an axis. An overhead crane is used to move and operate the tool and the grabbing and rotating
motion is powered by electric motors that are controlled by the operators remotely. The
moveable arms makes it possible to grab different sized ingots quickly without different sized
jaws. The ingots are supposed to be grabbed around their center of gravity. The grabbing
movement is controlled by a motor that turns a lead screw that moves the grabbing arms. The
clamps are then rotated 90 degrees to make the vertical ingots horizontal. The rotating motion
is made with one motor on each grabbing arm. The rotation is passed through an angled
gearbox that is self-locking for increased safety. When the ingot is rotated, it can then be placed
in a pallet that is loaded onto the next machine for further operations. This tool leaves both
ends of the ingot free, making the rest of the processing easier. Another benefit is that the tool
can be stored away from the rest of the machine and takes up little floor space compared to
the other concept solutions.
18
4.5.3 Slag Removal
Table 5. Results from the concept generation session of Slag removal and reasons for exclusions
Slag Removal Reason for exclusion
Air Jack Hammer
Spike
"Over Rotation"
Fall off Naturally when horizontal
Remove When Liquid Would compromise steel quality
“Remove when liquid” is not an option since the slag forms a protective layer that is necessary
to keep high steel quality.
Table 6. Results from the weighted decision matrix
Concept 1 Concept 2 Concept 3 Concept 4
Project description:
Air Jack Hammer Spike Over Rotation Fall Off Naturally When
Horizontal Slag Removal System
Criteria:
Weig
ht 1....... 5
Po
int 1 ....... 3
V x
P
Co
mm
ent
Po
int 1 ....... 3
V x
P
Co
mm
ent
Po
int 1 ....... 3
V x
P
Co
mm
ent
Po
int 1.......3
V x
P
Co
mm
ent
User Friendly 5 2 10 High Noise 3 15 2 10
Unpredict
able 3 15
Easy Maintenance 5 2 10
Mechanical
Systems 2 10
Mechanical
Systems 3 15
No extra
equipment 3 15 No maintenance
Easy Installation 5 2 10 2 10 3 15
No extra
equipment 3 15 No installation
Cost 5 2 10
Mechanical
Systems 2 10
Mechanical
Systems 3 15
No extra
equipment 3 15
No extra
equipment
CE-Marking 5 3 15 Possible 3 15 Possible 3 15 Possible 3 15 Possible
Automatic Operation 4 3 12 Possible 3 12 Possible 3 12 Possible 3 12 Naturally
67 72 82 87
The winner is concept 4 “Falls of Naturally When Horizontal”. Concept 1 scores lower on the
user-friendly criteria due to the loud noise produced when operating an air jack hammer. This
would impede with the comfort and deteriorate the work environment for the operators.
Concept 3 also scores lower on user friendliness since the time it takes for the slag to be
loosened from the ingot varies. It would be difficult to estimate the time the ingot must be in
the over rotated position. This would in turn require an operator's attention and therefore
scores lower than concept 2 and 4. Concept 1 and 2 score lower on maintenance, installation
and cost since the required extra machinery. More parts equal a higher risk of failure, are more
19
complex to install and cost more. CE-marking as well as automatic operation is seen to be
possible for all concepts.
4.5.4 Slag Handling
Table 7. Results from the concept generation session of Slag handling and reasons for exclusions
Slag Handling Reasons for exclusion
Container
Conveyor Belt
Leave on ground Unsustainable
Leaving the slag on the ground is not sustainable.
Table 8. Results from the weighted decision matrix
Concept 1 Concept 2
Project description: Container Conveyor Belt
Slag Handling
Criteria:
Weig
ht 1....... 5
Po
int 1...... 3
V x
P
Co
mm
ent
Po
int 1 ....... 3
V x
P
Co
mm
ent
User Friendly 5 2 10 Requires manual emptying 3 15
Easy Maintenance 5 2 10 2 10 Mechanical System
Easy Installation 5 3 15 2 10 Mechanical System
Cost 5 3 15 2 10 Mechanical System
CE-Marking 5 3 15 Possible 3 15 Possible
Automatic
Operation 4 1 4 Not Possible 3 12 Possible
69 72
The winner is concept 2 “conveyor belt”. Concept 1 scores lower on User friendly and therefore
Automatic operation since a container would require an operator to replace it in some way.
Concept 2 scores lower than concept 1 on maintenance, installation and cost since it requires
extra machinery.
4.5.5 Chip Removal
Table 9. Results from the concept generation session of Chip removal and reasons for exclusions
Chip Removal Reason for exclusion
Screw Transport
Conveyor Belt
Vacuum
20
Table 10. Results from the weighted decision matrix
Concept 1 Concept 2 Concept 3
Project description: Screw Transport Conveyor Belt Vacuum
Chip Removal
Criteria:
Weig
ht 1....... 5
Po
int 1....... 3
V x
P
Co
mm
ent
Po
int 1....... 3
V x
P
Co
mm
ent
Po
int 1....... 3
V x
P
Co
mm
ent
User Friendly 5 3 15 3 15 3 15
Easy Maintenance 5 2 10 Not as well tested 3 15 3 15
Easy Installation 5 2 10 2 10 2 10
Cost 5 2 10 2 10 2 10
CE-Marking 5 3 15 3 15 3 15
Automatic
Operation 4 3 12
Can be
automated 3 12
Can be
automated 3 12 Can be Automated
72 77 77
The winning concept for chip handling is concept 2 and 3.
Concept 1 scores lower on maintenance since Uddeholm already have existing production
systems using based on concept 2 and 3.
4.5.6 Handling and Transport of Ingots
Table 11. Results from the concept generation session of Handling and transport of ingots and reasons for exclusions
Handling and Transport of ingots Reasons for exclusion
V-pallet system
Rails
Walking Beam
21
Table 12. Results from the weighted decision matrix
Concept 1 Concept 2 Concept 3
Project description: V-Pallet System and Roll
Bed Rails "Walking Beam" Handling and
Transport of Ingots
Criteria:
Weig
ht 1....... 5
Po
int 1....... 3
V x
P
Co
mm
ent
Po
int 1....... 3
V x
P
Co
mm
ent
Po
int 1....... 3
V x
P
Co
mm
ent
User Friendly 5 2 10
Requires loading
of pallets 3 15 3 15
Easy Maintenance 5 3 15
Proven
technology 2 10 Heavy wear 2 10
Heavy
machinery
Easy Installation 5 2 10 2 10 2 10
Cost 5 2 10
Mechanical
systems 3 15 Simple 2 10
Mechanical
Systems
Be able to handle
pallet system 4 3 12 Possible 1 Not possible 1 Not possible
CE-Marking 5 3 15 Possible 3 15 Possible 3 15 Possible
Automatic Operation 4 2 8
Requires loading
of pallets 3 12 Possible 3 12 Possible
80 77 72
22
The winner of table 12 is concept 1. Concept 3 scores the lowest of the three in user friendliness
and automatic operation because it requires some loading of the pallets onto the roll bed. Both
concept 2 and 3 score lower on maintenance compared to concept 1 since it is expected to have
heavier wear on machinery since the ingots are in direct contact with the transport system.
Concept 1 is on the other hand an already existing solution at Uddeholm. Concept 1 and 3 score
lower on cost compared to concept 2 since it is a more complex construction with more moving
parts. Concept 2 and 3 does not utilize the existing pallet system and therefore score 1.
4.5.7 Structural Verification of Rotary Axis Grab
The lifting tool has one critical part that requires verification to determine if the concept is
feasible. The stress levels in the grabbing arms must be at a reasonable level so that the tool´s
lifespan will be adequate.
The trial and error-method [5] is a method that involves trying until a final solution. If the
solution does not reach the approved value, the design is modified and tested again. The
iteration continues until the solution is approved. The changed parameters in this case are the
dimensions.
4.5.7.1 Load Case
One of the concept solutions for tipping the ingots is the rotary axis grab. One specific load
case in that tool is presented in figure 5.
Figure 6. The load case in the lifting tool
The clamping force required to grab the ingot is calculated using the following equations:
Force equilibrium:
∑ ↑: 𝑚𝑔 = 2 𝐹𝑓
𝛴 →: 2𝑁 = 2 𝐹𝑐𝑙𝑎𝑚𝑝
Friction force: 𝐹𝑓 = 𝑁 ∗ 𝜇
23
Where:
• m is the mass of the ingot (kg)
• g is the acceleration of gravity (m/s^2)
• µ is the coefficient of friction
Solving for the normal force: ⇒ 𝑁 =𝑚𝑔
2𝜇
The load case [9] can be simplified as a cantilever beam with a force applied on the end of the
beam as can be seen in Figure 7. Cantilever beamFigure 7.
Figure 7. Cantilever beam
Where L is the length and F is the force.
4.5.7.2 Moment of Inertia
The cross section in the lifting arms is a hollow square as can be seen in Figure 8.
Figure 8. Lift arm cross section
The moment of inertia is calculated using the equation below:
𝐼𝑧 =𝑡1𝑏3
6+
1
2𝑡2𝑏2ℎ
24
The maximum stress can be calculated using the equation below:
𝜎𝑚𝑎𝑥 =𝐹𝐿 ∗ ℎ/2
𝐼𝑧
Structural verification using the data from Table 13, gave a maximum stress of 209MPa
Table 13. Structural data
m (kg) 30000
Coefficient of friction 0.5
h (m) 0.3
b (m) 0.3
t1 (m) 0.04
t2 (m) 0.04
Length of beam (m) 1.7
25
4.5.8 Combined Concepts
The winners of the different concept selections were combined into a final concept. The chosen
concepts are presented in table 14. Table 14. The winners of the concept selections
Sub-Functions Winner
Tipping Mechanism Rotary Axis Grab
Slag Removal Fall of Naturally When Horizontal
Slag handling Conveyor Belt
Removal of Starting Step Milling
Chip Removal Vacuum and Conveyor Belt
Handling and Transport of Ingots V-Pallet system with Roll Bed
The visualized final concept can be seen in Figure 9:
Figure 9. Visualization of the final concept
26
This final combined concept is meant to be used in a workflow as can be seen in Figure 10.
Figure 10. The workflow of the machine
The process starts immediately when the mold is removed from the ingot. Then the rotary
axis grab tool lifts and flips the ingots horizontally and places them in a waiting V-pallet that
sits on the roll bed. When on the roll bed, the ingots are incrementally rolled forward in order
to make room for succeeding ingots. The roll bed can hold several ingots at a time and let them
cool without any supervision or danger. A conveyor belt runs on the “slag side” of the roll bed
and transports the slag that will eventually fall off from the ingots as they cool and frees the
slag top. On the end of the roll bed there is a milling station. The ingots are lifted using
hydraulic cylinders to position them more accurately for the machining phase. When lifted, an
automatically, numerically controlled mill moves towards the ingot and machines away the
starting step. Close to the milling head runs a vacuum that sucks away most chips. Underneath
the milling machine runs a conveyor belt that transports away the chips that drops down. After
the milling process the ingots are lowered down onto the pallet and rolled away and awaits
transport to the forging shop.
27
5. Discussion
The final concept almost fulfills all requirements set by Uddeholm. The solution will reduce
manual work by: combining the lifting and the tipping in one step, diminishing the need for
an operator to remove slag and the need for an operator to manually cut off a part of the
starting step. It also provides increased capacity by holding several ingots at a time. Manual
operation will be needed when lifting and rotating the ingots. The possibility of utilizing the
existing milling machine is not yet clear, future work will need to determine if it will be
adequate for the application. A hold down mechanism is also unclear if it will be necessary and
is therefore left out in this thesis.
The system will be able to handle all dimensions and current production volumes and will have
good serviceability.
The cost of the new machine will certainly be higher than the current equipment. Several new
machines must be obtained and installed fetching a larger initial cost for Uddeholm. On the
other hand, the material waste costs each year and therefore the investment will have a short
payback period. A real cost estimate is to be determined and quotes from different
manufacturers must be asked for. Another factor will be that there will be less wear on the
overhead cranes in the ESR facility. This will lead to lower maintenance costs and less
downtime. The time saved during forging will also be significant. The need for ingots to be re-
heated before forging will be diminished, this leads to savings in natural gas to heat the ovens
and shorten the lead time. The overall yield for each ingot will be increased and more
predictable, therefore production planning will be easier. Also, the operators have stated a
higher level of stress because of the extra steps and time it takes to use the “knife” in the forge
today. The new solution will certainly reduce the stress of the operators and make their job
easier.
The overall risk of the ingot handling will be reduced. The new method and tool for tipping the
ingots will significantly reduce the risk during the rotation of the ingots. The need for operators
to get close to the ingot and remove slag and cut away the starting step will be eliminated.
While this machine will change the way Uddeholm handles ESR ingots there are some
obstacles that has to be overcome. Milling will be a complex component of the machine and
will require tests in order to find the correct parameters. Some of the operators may also need
to get special training to run the milling machine. Changing tools and general maintenance
that are special for milling machines are not part of the standard requirements for working at
the ESR facility at Uddeholm. Discussions have started with a cutting tool company that is
already present at Uddeholm to develop the process, but this is out of the scope of this thesis.
The pallets that are thought to be used in this machine are nonstandard in order to
accommodate the different sized ingots since Uddeholm is using different pallets right now.
Creating a new standard of pallets is not ideal but necessary for this machine to work
seamlessly, but Uddeholm has stated that this will be a tradeoff that they are willing to make.
The number of pallets that must be produced is still to be determined.
Structural verification of the rotary axis grab arms gave reasonable results in both stress levels
and dimensions for a steel construction. This is seemed like an adequate verification to prove
that the concept will work. Although a much more thorough analysis of the design must be
28
done to further to verify the construction. The grabbing arms were seen as a critical part of the
tool. The verification also gave an estimate of the tool dimensions and they were also within
reasonable limits. A full FEM-model should be made and evaluated to find the critical points
of the design.
5.1 Further Development
To further develop and make the concept feasible for Uddeholm, detailed construction and
certification must be made of the different components. This includes detailed CAD-drawings,
structural analysis of the rotary axis grab, milling machine and roll bed. A cost estimation
would also be necessary for it to be implemented. A lot of the components are to be outsourced
according to Uddeholm; this means that the details for each component must be specified.
Control systems for hydraulics, roll bed and milling machine are to be programmed. A
specifications list for the milling machine needs to be made and in addition, machining
parameters and programming of a control system for the mill must be made. The rotary axis
grab must be specified and built by a manufacturer. Conveyor system capacities and
dimensions are to be specified. Since the machine is to be installed in an already active
workplace the overall layout and changes that must be done within the ESR-facility must be
determined. That could be moving machinery, making foundations, installing electrics and
more. All machinery must also be CE-certified. The PFMEA identified several risks that could
be minimized using fencing and guards. This should also be installed around the machine and
around critical safety components such as the milling machine, roll bed, hydraulics lifts etc.
Another vital aspect is the production planning and logistics that will surround the new
machine. The installation will disturb the production flow and measures to minimize this
impact should be taken into consideration.
29
6. Conclusion
The challenges that Uddeholm has with ESR ingots are set to be solved with the concept
solutions found in this thesis. The result of the concept development and selection resulted
in sub solutions that:
• Reduced the risk during ingot handling
The need for operators to get close the ingot is reduced. A purpose-built tool will
make the tipping operation safer.
• Increases material yield
Since the starting step is completely removed before forging extra waste is
eliminated.
• Increased ingot capacity
The roll bed will be able to carry several ingots at a time, freeing floorspace and
reduces extra tools.
• Decreases manual work
More operations will be automated and the need for extra work in the forge will be
unnecessary.
• Decreases strain on operators
The time critical operations at the forge will be reduced, making it easier for the
operators and minimizes cycle time.
More work is needed to be able to make the concepts feisable. For example: do detailed
design and construction for the different sub functions, get quotas from manufacturers,
perform more extensive structural verifications, find process parameters for the milling
operation, CE-mark the solution, etcetera.
The product development process proved useful and easy to follow and applicable even for
more complex products such as a large machine system like this. It provides a clear
documentation which, for instance, makes it easy to go back for more info regarding previous
decisions. This will be especially useful when Uddeholm is ready to realize this project in the
future. Thus, it can be concluded that the product development process is a useful and well-
established method for generating and selecting new solutions.
30
7. Acknowledgements
A great thanks to Uddeholm and their employees for making this master thesis possible. A
special thanks to Ludvig Lundberg for his guidance and support patience throughout the
project. I would also like to thank the Uddeholm employees for participating in meetings and
answering my questions.
Thanks to my supervisor Mohamed Sadek for the guidance and frequent meetings.
31
8.References
1. Electroslag Remelting Process: Part One :: Total Materia Article. [cited 4 May 2021]. Available: https://www.totalmateria.com/page.aspx?ID=CheckArticle&site=kts&NM=226
2. History - Uddeholm Global. [cited 4 May 2021]. Available: https://www.uddeholm.com/en/history/
3. Crouch IG, Cimpoeru SJ, Li H, Shanmugam D. 2 - Armour steels. In: Crouch IG, editor. The Science of Armour Materials. Woodhead Publishing; 2017. pp. 55–115. doi:10.1016/B978-0-08-100704-4.00002-5
4. Ulrich KT, Eppinger SD, Yang MC. Product design and development. Seventh edition (international student edition). McGraw-Hill Education; 2020.
5. Johannesson H, Persson J-G, Pettersson D. Produktutveckling : effektiva metoder för konstruktion och design. 2. uppl. Liber; 2013.
6. Cooper R. The handbook of design management. Berg; 2011.
7. Anil Mital, Anoop Desai, Anand Subramanian, Aashi Mital. Product Development : A Structured Approach to Design and Manufacture. Amsterdam: Butterworth-Heinemann; 2008.
8. Hippel E von. Democratizing innovation. MIT Press; 2005.
9. Sundström B. Handbok och formelsamling i hållfasthetslära. KTH; 1998.
32
9. Appendixes
Appendix A- Explanation of Concepts
Tipping mechanisms
Concept 1: “Tipping Chair”
The ingots are placed in the
“tipping chair” with an
overhead crane when it is
nearly vertical (approx.
98°). Then the chair is slid
down the slot and on the
bottom rails to lower is to a
horizontal position. After
that the ingot is lifted to
another position for further
processing.
Concept 2: “Seesaw”
The ingot is placed with an
overhead crane in the nearly
vertical rotating platform.
The center of gravity of the
ingot is approx. at the
rotating axle of the platform.
Then the platform is rotated
to a horizontal position
where the ingot is moved to
another position for further
processing.
33
Concept 3: Rotating Axis
Grab
See explanation in 4.5.2
Tipping Mechanism
Concept 4: “Manipulator”
The ingot is placed or held in
front of the machine with an
overhead crane and is
grabbed with the gripping
claw. The gripping claw is
raised and then rotated and
lowered onto a pallet for
further processing.
Slag Removal System
Concept 1: “Air Jack Hammer”
An air powered jack hammer that is
automatically operated is moved to the slag
end of the ingot and starts hammering in the
center. The slag drops down on a slag
transportation system below.
34
Concept 2: “Spike”
Similar to the Air Jack Hammer but the spike
is simply driven into the center of the slag by
a linear actuator. The slag drops down on a
slag transportation system below.
Concept 3: “Over Rotation”
When the ingot is rotated in the tipping tool
it rotates the ingot end over end. Then the
slag falls off naturally down on a slag
transportation system below. This partial
solution is not compatible with all tipping
mechanism solutions.
Concept 4: “Falls Off Naturally When
Horizontal”
The ingot is left to cool and eventually the
slag will fall off naturally onto a slag
transportation system below.
35
Removal of Starting Step
Concept 1: Mill
The starting step is removed by a horizontal
milling machine that is numerically
controlled. The chips are transported away
with a chip transportation system.
Concept 2: Thermal Lance
A cutting thermal lance is manually operated
and cuts off the whole end of the ingot.
Concept 3: Cutting Torch
An automatically controlled cutting torch
cuts off the end of the whole ingot.
36
Chip Removal System
Concept 1: “Screw transport”
The chips fall down in a trough, in the
bottom there is a screw conveyor that
transports the chips.
Concept 2: Conveyor Belt
The chips fall down in a through and get
transported away with a conveyor belt.
Concept 3: Vacuum
A vacuum head is placed near the milling
head and sucks the chips. The chips are
moved through tubes to an external chip
collection area.
Slag Handling
Concept 1: Container
The slag falls directly down into a container
below.
37
Concept 2: Conveyor Belt
The slag falls down onto a heat resistant
conveyor belt. The conveyor belt transports
the slag to an external slag collection area.
Handling and Transportation of Ingots
Concept 1: “V-pallet System and Roll Bed”
The ingots are placed in standardized V-
pallets keeping them from rolling and
enabling forklifts to move them more easily.
The pallets are placed on a roll bed with space
for several pallets/ingots. The roll bed acts as
the transportation mean to the different
processing stations and an ingot holding
area.
Concept 2: Rails
The ingots are placed directly on a rail. The
ingots are rolled along the rail to the different
processing areas. The rail can accommodate
several ingots.
Concept 3: “Walking Beam”
The ingots are placed on the walking beam.
The walking beam incrementally “walks” the
ingots forward to the different processing
areas. The walking beam can accommodate
several ingots.
38
Appendix B- Preliminary Gantt Schedule
Appendix C- Project FMEA
Johan
Jönsson 2021-05-07 Risk Characteristic AS IS Nr Risk
Possibility Risk Effect Cause of Risk S O D RPN Recommended
action
1. Sickness Delayed work NA 5 1 1 5 Plan for redundancy
2.
Supervisor sick
Delayed work NA
5 1 1 5
Plan for
redundancy,
frequent
communication
3.
Uddeholm closes
Loss of information, not be able to visit
Corona
6 3 1 18
4.
Not passing
Not able to graduate
Bad work
9 2 3 54
Good
communication
with supervisors
5.
Bad results Take longer time, bad result
Lack of pre-study. bad methods. Lack of information
6 3 4 72
"Front heavy"
project, Extensive
literature search,
good
communication
6.
To complex Delays, hard to pass
Insufficient boundaries 6 3 3 54
Good
communication
with supervisors
7.
Takes too much time
Puts pressure on other things, not finishing in time
Bad planning, insufficient boundaries 5 3 3 45
Long term planning
and good
communication
with supervisors
8.
Delays Everything is delayed, more pressure on other aspects of life
Bad planning, lack of communication
5 3 3 45
Plan long term and
with redundancy
and good
communication
with supervisors
39
Appendix D- PFMEA
Johan
Jönsson 2021-05-07
Risk Characteristic AS IS
AFTER RE
EVAL.
Nr Risk
Possibility
Risk Effect Cause of Risk S O D RPN Recommended
action
S O D RPN
1.
Not stable Machine
falls over,
Injures
workers,
Fatality
Vibrations,
not fastened
10 1 4 40
Proper
fastening,
minimize
vibrations
10 1 1 10
2.
Slag falling Hit
workers,
fatality
No
protection 10 1 6 60
Shields, fence
10 1 4 40
3.
Metal chips
flying
Injures
workers
No
protection 4 7 3 84
Shields, fence
4 1 3 12
4.
Workers get
pinched
Injures
workers,
Fatality
No
protection,
no warning 10 1 5 50
Shields, fence,
light and
sound signals 10 1 2 20
5.
Machine total
breakdown
Injures
workers,
Fatality,
Downtime
Bad design,
wrong
calculations,
wrong
materials,
bad
maintenance
10 1 3 30
Competent
designers,
Structural
calculations 10 1 1 10
6.
Power loss Downtime,
Machine
fails,
Fatality
Bad electrics,
Non-Self-
locking
mechanisms
10 2 3 60
Self-locking
mechanisms,
reserve
generator
10 1 3 30
7.
Extreme
Temperatures
Machine
fails,
injures
workers
No heat
protection 6 2 2 24
Shields, fence
6 1 2 12
8.
Slip and fall Injures
workers,
fatality
No good
platforms,
slippery
surfaces, no
railings
10 7 8 560
Clean work
floor, fences,
railing 10 2 3 60
40
Appendix E- Product Specification Tipping Mechanism
Tipping
Machine
Criteria
number Criteria
Demands = D
Wish = W
Function= F
Limitation= L
Weighting
(1 min, 5 max) Comments:
1 CE Marking D L
2
All Wear Parts are to be
made from Uddeholm
steel
W L 2
3 Slag removal system D F
4 Be able to handle pallet
system W F 3
5 Fit in the prescribed
space D L 9000x4100 (mm)
6 Forklift accessible D L Accessible coming
from the outside
7
Be able to handle all
current ingot
dimensions
D L Min-max
dimensions
8 Heat resistant D L Temperature span
9 Operator protection D L
10 Automatic operation W F 4
11 Cycle time (tipping) W L 5 Max cycle time 10
minutes
12 Overhead crane
accessible D L
13 Side motion for finished
ingots W F 4
14 User Friendly D L
15 Easy Maintenance D L
16 Easy Installation D L
17 Cost Efficient
Construction D L
41
Appendix F-Product Specification Machining
Milling
machine
Criteria
number Criteria
Demands = D
Wish = W
Function= F
Limitation= L
Weighting
(1 min, 5 max) Comments:
1 CE Marking D L
2
All Wear Parts are to be
made from Uddeholm
steel
W L 2
3 Chip removal system D F
4
Be able to handle all
current base plate
dimensions
D L min-max
dimensions
5 Heat resistant D L Temperature span
6 Operator protection D L
7 Forklift accessible D L
8 Utilizing the existing
milling machine W L 5
9 Fit in the prescribed
space D L 9000x4100 (mm)
10 Automatic operation W F 4
11 Cycle time (milling) W L 5 max cycle time 5
minutes
12 Overhead crane
accessible D L
13 User Friendly D L
14 Easy Maintenance D L
15 Easy Installation D L
16 Cost Efficient
Construction D L