Design Basis Memorandum for Secondary Clarifier #3
-
Upload
khangminh22 -
Category
Documents
-
view
1 -
download
0
Transcript of Design Basis Memorandum for Secondary Clarifier #3
Report:
Design Basis Memorandum for Secondary Clarifier #3
Project SC403 Secondary Clarifier Weir Structure
Removal and Replacement
(RMOW Wastewater Treatment Plant Upgrade)
Client:
Prepared by:
200 – 896 Cambie Street Vancouver, BC, V6B 2P6
Contact Person:
Ali Taleb P.Eng.
Email: [email protected] Tel: 604-681 0901
August 17, 2021
MidSea Engineering Ltd. 2
200-896 Cambie Street Vancouver, BC, V6B 2P6
PROJECT NO. 200135
DESIGN BASIS MEMORANDUM FOR SECONDARY
CLARIFIER #3
Contents 1. SCOPE OF WORK ........................................................................................................ 3
2. INTRODUCTION .......................................................................................................... 3
3. KWL CONDITION ASSESSMENT OF SECONDARY CLARIFIERS ........................................ 5
4. DESIGN CRITERIA ........................................................................................................ 5
4.1. Background information ..................................................................................................... 5
4.2. WASTEWATER CHARACTERIZATION PROGRAM ................................................................. 6
4.3. DESIGN LOADS .................................................................................................................... 6
4.4. EFFLUENT DISCHARGE PERMIT ........................................................................................... 7
5. SECONDARY CLARIFIER#3 ........................................................................................... 8
6. SITE SPECIFIC CONDITIONS ......................................................................................... 9
7. DESIGN STANDARDS ................................................................................................. 10
Steel Related Reference Standards: ................................................................................. 10
8. REFERENCES ............................................................................................................. 11
9. APPENDICES ............................................................................................................. 12
9.1. Technical Memorandum, KWL Consulting Engineers ....................................................... 13
9.2. Clarifier#3 Drawings .......................................................................................................... 14
MidSea Engineering Ltd. 3
200-896 Cambie Street Vancouver, BC, V6B 2P6
PROJECT NO. 200135
DESIGN BASIS MEMORANDUM FOR SECONDARY
CLARIFIER #3
1. SCOPE OF WORK
MidSea Engineering is retained by Maven to prepare a Design Basis Memorandum for refurbishment of
the Secondary Clarifier#3 for Whistler Wastewater Treatment Plant (WWTP). The current memorandum
aims to present details regarding the current condition of the Secondary Clarifier#3 and the scope of
work and operations requirements for restoration, the design criteria including design loads and a brief
list of design codes and standards. At the end As-Constructed drawing will be enclosed.
2. INTRODUCTION
The Resort Municipality of Whistler (RMOW) operates a trickling filter/solid contact secondary
wastewater treatment plant (WWTP). The RMOW’s WWTP uses a sophisticated, enhanced biological
phosphorus removal (EBPR) process. This system builds on the carbon and nutrient loads entering the
plant to grow a specialized biomass able to withdraw phosphate from the water. The removal of
phosphate from the water relies on a food source “bugs” that comes from the system’s fermenter.
Currently the fermenter at the WWTP is offline and it has become necessary to introduce acetic acid into
the bioreactor as a food source. The fermenter is scheduled to come back online in 2023.
WWTP is located between the Sea to Sky Highway (Highway 99) and the north bank of the Cheakamus
River approximately 100m southwest of the intersection of Highway 99 and Cheakamus Lake Road at
the south entrance to Whistler.
The plant was last upgraded in 2007/2008. In 2006, Stantec was awarded an assignment to design the
upgrade of the Whistler WWTP and the project was completed on an accelerated schedule to enable
commissioning prior to the 2010 Olympics. The project upgraded the wastewater facility to meet the
projected community build out population of 62,125 bed units (as was expected to be reached in the year
2016). The design implemented biological phosphorus and nitrogen removal.
The following objectives were identified and followed in the design process for the upgrade of the
Whistler WWTP by Stantec:
• The RMOW developed and adopted a community vision on sustainability -Whistler 2030 Vision
(Currently RMOW adopts Whistler 2030 Vision) based on the principals of The Natural Step
Framework. Sustainable design is a key driver in this project. All aspects of the design from
initial process selection to detailed design decisions strive to meet the principles outlined in the
Whistler 2030 vision.
MidSea Engineering Ltd. 4
200-896 Cambie Street Vancouver, BC, V6B 2P6
PROJECT NO. 200135
DESIGN BASIS MEMORANDUM FOR SECONDARY
CLARIFIER #3
• Odour control was a significant issue. Minimizing odours was an objective in design and
upgrade by Stantec. Odour is no longer an issue, the plant utilized a carbon filtration system to
treat the foul air.
• The plant is intended to meet the wastewater treatment needs of the RMOW. Hence, design
input from operations and engineering staff should be accommodated to the maximum extent
possible.
• Training of municipal staff should be provided throughout the project.
• The plant must continuously provide a favorable operational environment for plant operators.
• Operational issues and improvements to existing facilities will be addressed in this upgrade.
• Life cycle costs and provision of quality facilities must be considered in the overall project
assessment and operation.
• Where practical and feasible, consideration should be given to incorporating existing
equipment and facilities into the upgrade.
The upgrade plan performed by Stantec in 2007/2008 included following items:
• Septage receiving station improvement, DAF and biosolids dewatering building.
• Two train Modified Johannesburg Biological Nutrient Removal (BNR) bioreactor system.
• Primary Sludge Fermenter (currently out of service; this food source is currently supplemented
with acetic acid).
• New administration building.
• A new secondary clarifier (Clarifier#404).
• A new blower building with a room to house equipment for the District Energy System
• Construction of a UV disinfection building.
• Conversion of ATAD tanks to waste activated sludge and fermented primary sludge storage
tanks (currently the tanks are only being utilized for WAS storage).
• Soda Ash silo for alkalinity addition (currently this is out of service, and not required for the
operation at this time).
In the update project by Stantec, the Secondary Clarifiers # 1 and #2 were refitted, the Secondary
Clarifier#4 was newly added; however, the secondary clarifier# 3 was untouched. In April 2020, Kerr
Wood Leidal (KWL) performed a condition assessment of the four circular secondary clarifiers at the
Whistler Wastewater Treatment Plant (WWTP). The report identified critical action items for each
MidSea Engineering Ltd. 5
200-896 Cambie Street Vancouver, BC, V6B 2P6
PROJECT NO. 200135
DESIGN BASIS MEMORANDUM FOR SECONDARY
CLARIFIER #3
clarifier. Need for major restoration has been identified for the Secondary Clarifier#3 which is reaching
end-of-life and shows significant corrosion and rust of steel works. The location of Secondary Clarifier#3
with respect to other clarifiers is presented in drawing number P403 of Stantec’s as-constructed
drawings. This memorandum intends to specify design basis criteria for the restoration of the
Secondary Clarifier#3.
3. KWL CONDITION ASSESSMENT OF SECONDARY CLARIFIERS
The Whistler Wastewater Treatment Plant (WWTP) operates two smaller clarifiers (#1 and #2), each 16m
in diameter, and two larger units (#3 and #4) each 22.5 m in diameter. Clarifiers #1 and #2 combined
have the same capacity as one larger clarifier.
In the Condition Assessment performed by KWL Consulting Engineers dated April 2020, the Secondary
Clarifiers were evaluated on a scale of one to five, where one is excellent and five represents failure, or
not working.
Clarifier #3 was given an overall Assessment Rating of four.
Critical Action Items:
1. The launders and weirs are close to end-of-life and require replacement, preferably within the next 12- 24 months. The submerged supports were not inspected but should be assessed structurally when the tank is empty.
2. The drive mechanism is 24 years old and considered near the end-of-life for this type of rotating equipment, although the supplier (WesTech) noted that some of their units have lasted 40 years with good maintenance. The motor was replaced in 2019, and it is reported that the electrical control panel is no longer working.
3. The submerged items were not inspected, but to guarantee continued performance and long-term operation, replacement of all internal equipment is recommended.
4. DESIGN CRITERIA
The design criteria presented in this chapter is from Stantec Pre-Design Report in March 2007 for a peak
of load in 2010 Olympics. RMOW is currently working on updating design criteria for 2040 build out. This
revised design criteria (Table 1, 2, & 3) will be available August 2021.
4.1. BACKGROUND INFORMATION
The design parameters outlined for the build out year (2016), based on 90% occupied Bed unit occupancy
projections are summarized in Table 1.
MidSea Engineering Ltd. 6
200-896 Cambie Street Vancouver, BC, V6B 2P6
PROJECT NO. 200135
DESIGN BASIS MEMORANDUM FOR SECONDARY
CLARIFIER #3
Table 1 -Flow and Load Projections (Adopted from Table 4.1 Stantec Pre-Design Report, March 2007)
Flow Value Notes
2016 Annual Average Flow
(m3/d)
14,00
2016 Maximum Month Flow
(m3/d)
20,000 Based upon a maximum (m3/d)
month factor of 1.35 (reference
AE Technical Memorandum
2.2b)
2016 Peak Hour Flow (m3/d) 53,600
Total occupied bed units 55,935 Assumes 90% occupancy
TSS load (kg/d) 6,153 @0.11 kg/d per BU
BOD load (kg/d) 6,647 @0.10 kg/d per BU
Total P load (kg/d) 145 @ 0.0026 kg/d per BU
For process design purposes, a maximum monthly flow of 20,000 m3/d should be selected for the
refurbishment of Secondary Clarifier#3. Results from the waste characterization program shall be used
to adjust the design parameters for the detailed design.
4.2. WASTEWATER CHARACTERIZATION PROGRAM
Two sampling periods shall be employed, each one month in duration to characterize wastewater. In
absence of such sampling program, Appendix A of the Pre-Design Report by Stantec in March 2007 can
be used which includes sampling program data obtained from November 2006 to January 2007.
4.3. DESIGN LOADS
Secondary clarifiers shall be designed for the maximum monthly loads while maintained to be
hydraulically suitable for peak hour flows presented in Table 2. The data in this table was obtained from
sampling program data acquired by Stantec from November 2006 to January 2007.
MidSea Engineering Ltd. 7
200-896 Cambie Street Vancouver, BC, V6B 2P6
PROJECT NO. 200135
DESIGN BASIS MEMORANDUM FOR SECONDARY
CLARIFIER #3
Table 2 -Maximum Month Design Loads Using Measured Concentrations November 2006 -January 2007
(Adopted from Table 4.3 Stantec Pre-Design Report, March 2007)
Parameter Design Concentration
(mg/L)
Avg day Load
(kg/d)
Max Month Load
(kg/d)
CBOD 250 3,675 5,000
TSS 250 3,675 5,000
TKN 40 588 800
NH3-N 25 368 500
TP 5 74 100
The design concentrations including safety factors because of the limited sampling period employed by
Stantec are presented in Table 3:
Table 3 -Selected Plant Design Loads (Adopted from Table 4.4 Stantec Pre-Design Report, March 2007)
Parameter Design Concentration
(mg/L)
Avg day Load
(kg/d)
Max Month Load
(kg/d)
CBOD 290 4,263 5,800
TSS 290 4,263 5,800
TKN 40 588 800
NH3-N 25 367 500
TP 7 103 140
Flow (m3/d) - 14,700 20,000
4.4. EFFLUENT DISCHARGE PERMIT
The RMOW’s effluent quality requirements are covered under Operational Certificate ME-01452. The
operational certificate parameters are summarized in Table 4.5 of Stantec Pre-Design Report and in
MidSea Engineering Ltd. 8
200-896 Cambie Street Vancouver, BC, V6B 2P6
PROJECT NO. 200135
DESIGN BASIS MEMORANDUM FOR SECONDARY
CLARIFIER #3
Table 4 below. The certificate set limits on CBOD, TSS, soluble orthophosphorus and effluent toxicity.
All parameters shall never exceed values, except for orthophosphate loading which is monthly mass
loading from May 15th to September 15th.
Table 4 -Summary of Current Operational Certificates (never to exceed, except as noted) (Adopted from Table
4.5 Stantec Pre-Design Report, March 2007)
Parameter Concentration
CBOD 30 mg/L
Total Suspended Solids (TSS) 40 mg/L
96 hr LC50 (Fish bioassay) 100% effluent strength
Orthophosphate concentration (as phosphorus) 1.75 mg/L
Orthophosphate loading (as phosphorus) 36.6 kg/mth (May 15 to Sept 15)
5. SECONDARY CLARIFIER#3
Design criteria for Secondary Clarifier #3 are summarized in Table 6.2 of the Stantec Report, presented
in Table 5 as follows, assuming that all four clarifiers are in operation. Table 5 will be updated August
2021.
Table 5 - Secondary Clarifier Design Criteria (Adopted from Table 6.2 Stantec Pre-Design Report, March
2007)
Description Peak Hydraulic Flow Maximum Month Flow
Design Flow (Ml/d) 53.6 20
Design MLSS (mg/L) 3700 3700
RAZ Rate 0.7Q 0.7Q
Surface Overflow Rate (m3/m2/d) 44.8 16.7
Solids Loading Rate (kg/m2/d) 11.7 4.4
Total Clarifier Area (m2) 1197 1197
#of Units / Diameter (m) 2@16m, [email protected] 2@16m, [email protected]
MidSea Engineering Ltd. 9
200-896 Cambie Street Vancouver, BC, V6B 2P6
PROJECT NO. 200135
DESIGN BASIS MEMORANDUM FOR SECONDARY
CLARIFIER #3
6. SITE SPECIFIC CONDITIONS
Table 6 - Climatic Design Data for the City of Whistler based on BC Building Code 2018
Feature Value
January 2.5% design dry bulb temperature °C -17
January 1% design dry bulb temperature °C -20
July 2.5% design dry bulb temperature °C 30
July 2.5% design wet bulb temperature °C 20
Annual total degree days below 18 °C 4180
Maximum 15-minute rainfall (mm) 10
One Day Rain, 1/50, (mm) 85
Annual rainfall (mm) 845
Moisture Index 0.99
Annual total precipitation (mm) 1215
Driving Rain wind pressure 1/5 years (Pa) 160
Ground snow load, snow component Ss (50 years) (kPa) 9.5
Ground snow load, rain component Sr (50 years) (kPa) 0.9
Hourly wind pressure 1/10 (kPa) 0.25
Hourly wind pressure 1/50 years (kPa) 0.32
MidSea Engineering Ltd. 10
200-896 Cambie Street Vancouver, BC, V6B 2P6
PROJECT NO. 200135
DESIGN BASIS MEMORANDUM FOR SECONDARY
CLARIFIER #3
Table 7- Seismic Hazard 2% probability of exceedance in 50 years for City of Whistler
Sa (0.2) Sa (0.5) Sa (1.0) Sa (2.0) Sa (5.0) Sa (10.0) PGA (g) PGV (m/s)
0.438 0.357 0.233 0.152 0.058 0.02 0.203 0.296
7. DESIGN STANDARDS
Relevant analyses and design standards include but not limited to :
• British Columbia Building Code
• National Building Code of Canada
• ACI 350.3-06
STEEL RELATED REFERENCE STANDARDS:
CSA S16, Limit State Design of Steel Structures
CSA G40.21, Structural Quality Steel
ASTM A53, Standard Specification for Pipe
ASTM F3125 Grade A325, Standard Specification for Structural Steel Bolts
ASTM A563 GR DH, Standard Specification for NUTs
ASTM F436, Standard Specification for Washers
CISC Handbook of Steel Construction
ASTM 153, Standard Specification for Galvanization of hardware products
ASTM 123, Standard Specification for Zinc (Hot-Dip Galvanized) Coatings on Iron and Steel
Products
CSA W48 E49XX electrode classification for Arc Welding Electrodes
CSA W59M for welding
Steel Fabricators and operators approved by Canadian Welding Bureau to the requirements
of CSA W47.1.
MidSea Engineering Ltd. 11
200-896 Cambie Street Vancouver, BC, V6B 2P6
PROJECT NO. 200135
DESIGN BASIS MEMORANDUM FOR SECONDARY
CLARIFIER #3
8. REFERENCES
[1] Associated Engineering Technical Memorandum (2006-2007)
[2] RMOW Wastewater Treatment Plant Upgrade- PRE-DESIGN REPORT, Stantec, March 2007.
[3] Technical Memorandum, KWL Consulting Engineers, April 2020.
[4] AS CONSTRUCTED DRAWINGS FOR RMOW Wastewater Treatment Plant, Knight LTD
MidSea Engineering Ltd. 12
200-896 Cambie Street Vancouver, BC, V6B 2P6
PROJECT NO. 200135
DESIGN BASIS MEMORANDUM FOR SECONDARY
CLARIFIER #3
9. APPENDICES
MidSea Engineering Ltd. 13
200-896 Cambie Street Vancouver, BC, V6B 2P6
PROJECT NO. 200135
DESIGN BASIS MEMORANDUM FOR SECONDARY
CLARIFIER #3
9.1. TECHNICAL MEMORANDUM, KWL CONSULTING ENGINEERS
Technical Memorandum
DATE: April 16, 2020
TO: Chelsey Roberts, AScT
Resort Municipality of Whistler FROM: Nigel Slater, P. Eng.
Don Nash, P.Eng. RE: SECONDARY CLARIFIER CONDITION ASSESSMENT
Resort Municipality of Whistler Our File 0029.326-300
1. Introduction KWL was retained to undertake a condition assessment of the four circular secondary clarifiers at the Whistler wastewater treatment plant (WWTP). There are two smaller clarifiers (#1 and #2) each 16 m in diameter, and two larger units (#3 and #4) each 22.5 m in diameter. Clarifiers #1 and #2 combined have the same capacity as one large clarifier.
2
TECHNICAL MEMORANDUMResort Municipality of Whistler
April 16, 2020
Clarifiers #1 and #2 were re-fitted around 2007/2008 with new mechanical/electrical equipment, along with construction of the new Clarifier #4, prior to the Olympics.
The inspection took place on Thursday, March 12, 2020. Items are rated on a scale of one to five, where one is excellent and five represents failed, or not working.
A visual inspection of all above grade and above water components to assess its condition and operational function was completed. Plant operational input and comments were collected from site staff. Each asset condition was scored, and recommendations were made for monitor, repair or replace.
Improvements and considerations are also noted.
2. Condition Assessment Overview A condition assessment of each clarifier is tabulated in Attachment A.
Photos of the inspection items of concern are provided in Attachment B.
The outcome of the condition assessment can be summarized as follows:
• In general, the clarifiers operate well with no major issues.
• There is heavy algae growth in the clarifiers which requires operations and maintenance attention in the summer months, including shut-downs for manual cleaning.
• The secondary release of Phosphorous can be an issue under low-flow seasons due to the long hydraulic retention time in the clarifiers, and the limitations of the RAS flowrate.
• Typically, one large clarifier is used in summer months, with an additional small clarifier brought into service on weekends to deal with the increased flow.
• The WWTP has an excess of capacity based on current flow and loadings (plant was designed for a peak during the 2010 Olympics).
• The mechanical equipment in Clarifier #3 is 24 years old and is reaching the end-of-life and requires refurbishment to guarantee continued performance for the long term. If a refurbishment is undertaken, there would be opportunities to update the design to modern standards and incorporate alternative equipment and components to increase the capacity and performance of the clarifier.
2.1 Clarifier #1
Overall Assessment Results
The overall rating is two.
Critical Action Items
Painted steelwork is corroding. Undertake remedial renovation work in the next 12 months to prevent further corrosion, and deterioration. Sandblasting, priming and epoxy painting will be required.
The building for Clarifier #1 and #2 requires repair and restoration work to the heating and ventilation system.
3
TECHNICAL MEMORANDUMResort Municipality of Whistler
April 16, 2020
Other Considerations
Consider covering the open-mesh grating to reduce moisture within the building.
2.2 Clarifier #2
Overall Assessment Results
The overall rating is two.
Critical Action Items
The painted steelwork is corroding. Undertake remedial renovation work in the next 12 months to prevent further corrosion, and deterioration. Sandblasting, priming and epoxy painting will be required.
The building for Clarifiers #1 and #2 requires repair and restoration work, heating and ventilation system.
Other Considerations
Consider covering the open-mesh grating to reduce moisture within the building.
2.3 Clarifier #3
Overall Assessment Results
The overall rating is four.
Critical Action Items
The launders and weirs are close to end-of-life and require replacement, preferably within the next 12 – 24 months. The submerged supports were not inspected but should be assessed structurally when the tank is empty.
The drive mechanism is 24 years old and considered near the end-of-life for this type of rotating equipment, although the supplier (WesTech) noted that some of their units have lasted 40 years with good maintenance. The motor was replaced in 2019, and it is reported that the electrical control panel is no longer working.
The submerged items were not inspected, but to guarantee continued performance and long-term operation, replacement of all internal equipment is recommended. From photos supplied post-inspection, there is corrosion, but some of the internal steelwork appears to be in reasonable condition and it may be possible to repair or refurbish. However, any in-place cleaning and painting on-site for refurbishment work will need to be carefully monitored and supervised.
Other Considerations
Algae cleaning is an ongoing maintenance issue especially during the summer, and it is recommended to add spray washing or covers to the clarifier.
4
TECHNICAL MEMORANDUMResort Municipality of Whistler
April 16, 2020
2.4 Clarifier #4
Overall Assessment Results
The overall rating is three.
Critical Action Items
The clarifier has problems with algae in the summer and consideration should be given to improving launder cleaning equipment, or to providing covers for launders.
Some maintenance is required on the launder V-notch weirs for levelling and equalizing the flow around the clarifier. Also, some general corrosion protection (sand blasting and painting) is required to prevent steelwork deterioration. It is recommended to complete this work during the next 12 months.
Other Considerations
Inspect the submerged items when the tank is empty.
3. Main Items of Concern 1. Maintenance – Plant operation is generally “unplanned maintenance” with no specific maintenance
program at present. Typically, only the oil is changed. However, there should be other planned maintenance taking place including a weekly oil check, a yearly oil change, draining the condensate weekly, and lubrication per the O&M.
2. Algae – The growth of algae on the launder troughs and weirs is a constant maintenance and operational issue, especially during the summer when algae can be discharged into the discharge pipework and downstream UV system. Algae also increases TSS and BOD in the treated effluent. The brush cleaning system is not very effective on sectional weir segments, requires frequent adjustment, and does not keep up with the growth of algae and slime in the V-notches and launder troughs.
There are “touchless” alternatives including washer and jet sprays, which have demonstrated good performance and would provide a viable option for cleaning. Winter could be an issue with spray and freezing, but algae growth is lower in winter and less cleaning is required. Spray systems can operate continuously or intermittently, use wash-water (or potable water), at 20 US gpm and a pressure of 65 psi, and have a filter/strainer.
The most proven and effective long-term solution is to provide covers to prevent sunlight accessing the launders, which drastically reduces the growth of algae. There are several suppliers including Nefco and IEC Covers, and they can be made from HDPE, stainless steel or FRP. Covers are a passive system and require little maintenance. The main disadvantage of covers is that the treated effluent discharge over the weirs is no longer visible to the operator.
3. Instrumentation – Installation of sludge blanket detectors on each clarifier to provide real-time sludge blanket level monitoring should be considered. These units give an early warning of potential TSS carry-over from a high blanket or washout. The units would be linked to the WWTP SCADA for monitoring and alarms.
5
TECHNICAL MEMORANDUMResort Municipality of Whistler
April 16, 2020
4. Other Site Observations and Recommendations 1. Assuming Clarifier #3 will be completely re-fitted with new internal mechanical/electrical equipment,
consider the following recommendations:
a. Evaluate the option of installing the launders and weirs around the edge of the tank wall, having a single weir and scum baffle, and providing launder covers to prevent algae growth. In addition, having a single peripheral weir allows the entire surface of the tank to be skimmed, which is a definite improvement on the current design. In addition, Stamford baffles (or equivalent) could be installed inside the tank to reduce density currents and improve performance.
b. If double-sided weirs and launders are used, specify circular weirs and troughs without bracing, instead of the sectional lengths of straight weirs. Circular weirs are inherently easier to clean.
c. A larger diameter inlet dissipation well / stilling baffle to improve flocculation of the mixed liquor entering the clarifier.
d. A dipping scum box and beach and dual scraper arms to improve surface scum removal.
e. Investigate options for increasing return activated sludge (RAS) flowrate.
f. Specify stainless steel for items which are partially submerged in liquid to reduce steel corrosion at the liquid-air interface.
g. Alternative materials for construction, such as aluminum or fibre reinforced plastic (FRP) for stilling baffles.
2. Investigate options to increase the RAS flowrate for all clarifiers, and hydraulic modelling to optimize clarifier performance.
3. It is recommended to implement an asset management program with equipment and component numbering, maintenance requirements/servicing and a schedule of routine inspection and planned servicing.
5. Cost Opinion The following budgetary pricing is provided for estimating capital expenditure required to maintain the existing process equipment in the secondary clarifiers.
5.1 Clarifier #1 and #2
The Table 5-1 below summarizes the work required for Clarifiers #1 and #2, which could be undertaken by a local (Sea to Sky) contractor:
6
TECHNICAL MEMORANDUMResort Municipality of Whistler
April 16, 2020
Table 5-1: Estimated Costs
Clarifier #1 and #2 Items Clarifier #1 Clarifier #2 Building
Cleaning and painting $20,000 $20,000 $10,000
Heating and ventilation $0 $0 $15,000
Sludge blanket level detectors (optional) $10,000 $10,000 $0
Column totals $30,000 $30,000 $25,000
Sub total $85,000
Contingency (30%) $25,500
Engineering (15%) $12,750
Total $123,250
5.2 Clarifier #3
The following cost estimates were obtained from WesTech (Clarifier #3 original manufacturer), and Envirodyne (Manufacturer of equipment installed in clarifiers #1, #2 and #4).
There are several other suppliers of this equipment, typically in the USA.
Table 5-2 summarizes the quotes by WesTech and Envirodyne for the clarifier mechanical and electrical (M&E) replacements, and Table 5-3 summarizes the costs for optional items.
Table 5-2: Estimated Costs
Clarifier #3 WesTech Envirodyne
Clarifier internals $182,000
Launder and baffles $171,000
Launder washer $69,000
Dive replacement $63,000
Shipping from USA $25,000 Included below
Lump sum price for total system Included above $441,000
Installation $102,000 $88,200
Total Supplier Costs $612,000 $529,200
Contingency (30%) $183,600 $158,760
Engineering (15%) $91,800 $79,380
Total $887,400 $767,340
Notes: Exchange rate 1 USD = 1.4 CAD. Installation 20% of capital, engineering 15%, and contingency 30%. Fabrication of equipment was stated at 16 – 24 weeks.
7
TECHNICAL MEMORANDUMResort Municipality of Whistler
April 16, 2020
Table 5-3: Optional Items
Items Cost
Covers $120,000
Sludge blanket level detectors $10,000
Total Supplier Costs $130,000
Contingency (30%) $39,000
Engineering (15%) $19,500
Total $188,500
Note: a spray system can be used instead of covers which would reduce the cost by $72,500 including engineering and contingency.
5.3 Clarifier #4
Table 5-4 summarizes the costs for Clarifier #4, which could be undertaken by a local (Sea to Sky) contractor and Table 5-5 summarizes the optional work items.
Table 5-4: Estimated Costs
Items Cost
Cleaning and painting $20,000
Sub total $20,000
Contingency (30%) $6,000
Engineering (15%) $3,000
Total $29,000
Table 5-5: Optional Items
Items Cost
Covers $120,000
Sludge blanket level detectors $10,000
Total Supplier Costs $130,000
Contingency (30%) $39,000
Engineering (15%) $19,500
Total $188,500
Note: a spray system can be used instead of covers which would reduce the cost by $72,500 including engineering and contingency.
8
TECHNICAL MEMORANDUMResort Municipality of Whistler
April 16, 2020
5.4 Cost Summary
Table 5-6 summarizes the costs for each clarifier including optional items.
Table 5-6: Cost Summary
Cost Summary Including Optional Items
Cost
Clarifier #1, #2, and building $123,250
Clarifier #3 (Envirodyne price) $955,840
Clarifier #4 $217,500
Total $1,296,590
6. Closing We would like to thank the Resort Municipality of Whistler for the opportunity to support the condition assessment work. KWL would be pleased to provide additional support moving forward as needed for design, asset management planning, developing standard operating procedures, maintenance schedules, tendering, and construction support.
Client: Regional Municipality of Whistler Comments Rating
Project Title Whistler Secondary Clarifier Condition Assessment
Description of Work Inspection of secondary clarifiers and associated equipment.
Date 12 March 2020
KWL Project No 0029.326
Item Clarifier # 1
Diameter, area etc. 16 m diameter, 201 m2, 4.75 m side-water depth, volume ~950 m3
Year built Year built unknown. Internals completely refurbished in 2008
Description
Concrete circular clarifier, center feed with stilling baffle and dissipation well, double-sided launder at 12 m
diameter with cross bracing, scum removal, two spiral sludge scrapers, center drive (Envirodyne, PA),
access bridge, 1:12 floor slope, 0.75m freeboard
Status Off-line (on standby)
Operational Issues and
comments
No major issues
No planned maintenance program, change oil as required. Not aware of other maintenance / O&M
No algae control, brushes etc., clean manually.
Issue with influent ML flow splitting between 1 and 2 due to pipework configuration, but controlled by
throttling #2. Flow is measured in a flowmeter before the flow split.
Check Envirodyne O&M and
maintenance program for the drive
system
2
Average Flows Rated for 5,000 m3/d (208 m3/h, 58 L/s)
Peak FlowExpected 10,000 m3/d (2 m/h up flow rate) but may have hydraulic or process restrictions from solids carry-
over or under-capacity of RAS
Flow would need to be shared between
clarifiers at this flowrate.
Weir Length 78m, weir overflow rate 0.75 L/m/s Normal Design
Capacity Surface Loading Rate (up flow rate) ~1m/h at 5,000 m3/d Normal Design
Solids loading Rate Calculated at 3.6kgMLSS/m2.h at 3,500mg/L MLSS Normal Design
Solids liquid separation Tank empty, no comment
Scum and scum box Moving surface scraper/collector, and beach. 2
Scum removal Discharge to sump/drain, collected by suction tanker
Scum sprayers None.
Weir trough Double-sided launders are ~900mm deep with cross bar bracing. V-notch weirs Access difficult 2
Algae None, tank empty
Cleaning Manual Labor intensive 2
Stilling Baffle Dissipation well and stilling baffle with scum outlets Standard design 2
Scrapers Two spiral sludge scrapers, across full width of tank, some rust/corrosion Repair/renovate 2
Bridge Fixed bridge access to drive, safe access 2
Bridge mechanism/drive Some oil leakage reported. Envirodyne drive mechanism from 2007/8, life expectancy 15-20 years Investigate maintenance 3
RAS flow RAS submersible pumps located inside the building in a wet well 2
Equipment5 HP / 3.7 kW 1,745rpm.
Flygt 3102.181 pumps.
Condition unknown, pumps are more
than 10 years old. 2
Flow measurement Yes
Control Variable speed
Standby capability Spare pump, one unit shared for Clarifiers #1 and #2.
WAS system Not applicable - Waste from Bioreactor based on sludge age
Flow splitting Issue with ML flow splitting between 1 and 2 but controlled by throttling #2 2
Outlet valves / gates 450 mm dia outlet pipework, then flowmeter and UV system
CorrosionSome corrosion starting on effluent launder and feed distribution baffle. Rusty fittings. Requires touch
up/painting maintenanceRepair/renovate 3
Safety Good, light, handrails, missing life float 2
Grating / handrails Generally good condition 2
Electrical Good condition 2
Valves and pipework Pipework in-tank in good condition. 2
BuildingsGenerally workable condition, steel framing shows corrosion. Requires heating and ventilation. Door needs
sealing. Cover open mesh wet wells to reduce moisture.Repair, building-mechanical work 4
Client: Regional Municipality of Whistler Comments Rating
Project Title: Whistler Secondary Clarifier Condition Assessment
Description of Work Inspection of secondary clarifiers and associated equipment.
Date 12 March 2020
KWL Project No: 0029.326
Item Clarifier # 2
Diameter, area etc. 16m diameter, 201 m2, 4.75 m side-water depth, volume ~950 m3
Year built Year built unknown. Internals completely refurbished in 2008
Description
Concrete circular clarifier, center feed with stilling baffle and dissipation well, double-sided launder at 12 m
diameter with cross bracing, scum removal, two spiral sludge scrapers, center drive (Envirodyne, PA),
access bridge, 1:12 floor slope, 0.75 m freeboard
Status Off-line (on standby)
Operational Issues and
comments
No major issues
No planned maintenance program, change oil as required. Not aware of other maintenance / O&M
Small crack in wall of #2 near building - needs review by structural/civil.
No algae control, brushes etc., clean manually.
Issue with influent ML flow splitting between 1 and 2 due to pipework configuration, but controlled by
throttling #2, Flow is measured by flowmeter before the flow split.
Civil inspection required
Check Envirodyne O&M and
maintenance program for the drive
system.
2
Average Flows Rated for 5,000m3/d (208m3/h, 58 L/s)
Peak FlowExpected 10,000 m3/d (2m/h up flow rate) but may have hydraulic or process restrictions from solids carry-
over or under-capacity of RAS
Operations would split flow between
clarifiers of this flowrate.
Weir Length 78 m, weir overflow rate 0.75 L/m/s Normal Design
Capacity Surface Loading Rate (up flow rate) ~1 m/h at 5,000 m3/d Normal Design
Solids loading Rate Calculated at 3.6kgMLSS/m2.h at 3,500mg/L MLSS Normal Design
Solids liquid separation Tank empty, no comment
Scum and scum box Moving surface scraper/collector, and beach. 2
Scum removal Discharge to sump/drain, collected by suction tanker
Scum sprayers None.
Weir trough Double sided launder ~900 mm deep trough without cross baffles. V-notch weirs. Access difficult 2
Algae None, tank empty
Cleaning Manual Labor intensive 2
Stilling Baffle Dissipation well and stilling baffle with scum outlets Standard design 2
Scrapers Two spiral sludge scrapers, across full width of tank, some rust/corrosion Repair/renovate 2
Bridge Fixed bridge access to drive, safe access
Bridge mechanism/drive No reported issues. Envirodyne drive mechanism from 2007/8, life expectancy 15-20 years 2
RAS flow RAS submersible pumps located inside the building in a wet well 2
Equipment5 HP / 3.7 kW 1,745rpm.
Flygt 3102.181 pumps.
Condition unknown, pumps are more
than 10 years old. 2
Flow measurement Yes
Control Variable speed
Standby capability Spare pump, one unit shared for Clarifiers #1 and #2
WAS system Not applicable - Waste from Bioreactor based on sludge age
Flow splitting Issue with ML flow splitting between 1 and 2 but controlled by throttling #2 2
Outlet valves / gates 450 mm dia outlet pipework, then flowmeter and UV system
CorrosionSome corrosion starting on effluent launder and feed distribution baffle. Rusty fittings. Requires touch
up/painting maintenanceRepair/renovate 3
Safety Good, light, handrails, missing life float 2
Grating / handrails Generally good condition 2
Electrical Good condition 2
Valves and pipework Pipework in-tank in good condition. 2
Buildings Same comments as Clarifier #1 Repair, building-mechanical work 4
Client: Regional Municipality of Whistler Comments Rating
Project Title: Whistler Secondary Clarifier Condition Assessment
Description of Work Inspection of secondary clarifiers and associated equipment.
Date 12 March 2020
KWL Project No: 0029.326
Item Clarifier # 3
Diameter, area etc. 22.5m diameter, 398 m2, 4.75m side-water depth, volume ~1,891m3
Year built Year built 1996/7
Description
Large concrete circular clarifier, center feed with stilling baffle and dissipation well, double-sided launder at
17m dia without cross bracing, scum removal, two spiral scrapers, center drive (Westech, UT), access
bridge, 1:12 floor slope, 0.75m freeboard
4
Status In-service, above liquid inspection only.
Operational Issues and
comments
Usually operate 1 large clarifier (#3 or #4) and bring on a small clarifier (#1 or #2) at weekends in summer.
No planned maintenance program, only change oil as required
Effluent launder channels have deteriorated and showing signs of leaking and are close to end-of-life.
Algae control, brushes etc. and not very effective and usually the tank is fully drained and manually cleaned
two or three times in the summer.
Concrete in good condition
Inspect wetted components when tank
is empty, especially structural elements.4
Average Flows Rated for 10,000m3/d (416m3/h, 116 L/s) - estimate.
Peak FlowExpected 20,000 m3/d (2m/h up flow rate) but may have hydraulic or process restrictions, solids carry-over
from blanket due to under-capacity of RAS.
Operate more tanks at this flowrate to
share the flow.
Weir Length 106m, weir overflow rate 1.1 L/m/s Normal Design
Capacity Surface Loading Rate (up flow rate) ~1m/h at 10,000m3/d Normal Design
Solids loading Rate Calculated at 3.6 kgMLSS/m2.h at 3,500mg/L MLSS Normal Design
TSS carry-over Minimal. Effluent quality excellent, and good clarity 1
Flow distributionGood, no apparent short-circuiting, weir overflow reasonably uniform around the launder, but some v-
notches blinded3
Scum and scum box Moving surface scraper/collector, and beach. 3
Scum removal Discharge to sump/drain adjacent to clarifier #3, collected by suction tanker
Scum sprayers None.
Floatables None. Minor floating scum (FOG) on the surface of the tank, but retained by weir baffle.
Weir trough
Double sided launder trough without cross baffles. V-notch weirs.
Lauders at end of life and show deterioration. Leaking in places, missing bolts, some bending etc.
Deposits of Ferric and/or corrosion of launder and supporting steelwork. Some V-notches are almost
blocked.
Replace 4
Algae Minimal on the surface
CleaningBrushes provided (Weir-Wolf, or similar system) around the weir and wall, but not very effective and require
maintenance and adjustment. Manual cleaning required, drain the tank and clean, 2 or 3 times in summer.
Remove and implement cleaning
program or covers3
Stilling Baffle Dissipation well and stilling baffle with scum outlets Structure 3
Scrapers Two spiral scrapers, across full width of tank Inspect when empty 3
Bridge Fixed bridge access to drive, safe access. 2
Bridge mechanism/drive
WesTech Mechanism, 72ft diameter (Dated December 1996, WesTech job 4870A). Westech supplied the
clarifier tank internals except the launder troughs. All equipment/baffles manufactured from mild steel,
painted.
The above water steel looks in reasonable condition, but with some evidence of surface corrosion/rusting
especially at the liquid-air interface.
No torque issues, scraper moves smoothly with no obvious jerkiness.
Generally unplanned maintenance – no specific maintenance program at present. Oil changes only.
(Westech nameplate states Check oil weekly, change yearly. Drain condensate weekly, lubricate per O&M)
Motor was replaced in 2019 with 1 HP, 1,750 rpm, TEFC premium motor.
The unit is variable speed and runs at 75%.
System is 24 years old, and considered
at the end-of-life. Dependent on how the
system has been maintained and what
(if anything) has been replaced etc. The
units were manufactured to a high
standard from cast iron (probably more
robust than modern equipment).
Westech states they have them in
operation over 40 years!
3
RAS flowRAS submersible pumps located in a wet well adjacent to clarifier #4.
Wet wells have covers and pump lifting hoist2
Equipment7.5 HP / 5.6 kW 1,740rpm.
Flygt 3127.181 pumps.
Condition unknown. Shelf spare
required as pumps are more than 10
years old.
2
Flow measurement Yes
Control
Variable speed
Pump generally runs at 100% max RAS rate. RAS pipe is 250mm diameter, whereas clarifier #4 has
300mm diameter, so RAS maybe restricted from clarifier #3.
Standby capability Spare pump provided to share between Clarifier #3 and #4
WAS system Not applicable - Waste from Bioreactor based on sludge age
Flow splitting No issues with ML flow split - 3-way inlet flow-splitter with motorized valves. All in good condition. 2
Outlet valves / gates 600 mm dia outlet pipework, then flowmeter and UV system. Below grade, no inspection
Corrosion
Corrosion on effluent launder and support steelwork. Rusty fittings.
When tank is drained, it is reported that there is rust in the tank from steelwork.
Corrosion/rusting around the drive mechanism and torque box requires painting/protection.
Corrosion of dissimilar metals in wet well for RAS pump hoist anchor bolts.
Replace launders and steelwork.
Inspect steelwork and underwater
components for corrosion/structural
issues, replace if necessary
4
Safety Good, light, handrails, life float 2
Grating / handrails Generally good condition 2
ElectricalGenerally good condition, some electrical cables from the local panel need to be tied up to cable trays.
Local control panel with stainless steel enclosure and alarm light reported as not working.Replace/refurbish 4
Valves and pipework Submerged or below-grade, no inspection. Inspect when empty.
Buildings No buildings
Client: Regional Municipality of Whistler Comments Rating
Project Title: Whistler Secondary Clarifier Condition Assessment
Description of Work Inspection of secondary clarifiers and associated equipment.
Date 12 March 2020
KWL Project No: 0029.326
Item Clarifier # 4
Diameter, area etc. 22.5m diameter, 398 m2, 4.75m side-water depth, volume ~1,891m3
Year built Year built 2007
Description
Large concrete circular clarifier, center feed with stilling baffle and dissipation well, double-sided launder at
17m diameter with cross bracing, scum removal, two spiral sludge scrapers, center drive (Envirodyne, PA),
access bridge, 1:12 floor slope, 0.75m freeboard
2
Status In-service, above liquid inspection only.
Operational Issues and
comments
Large clarifier with Envirodyne equipment built around 2007 before the Olympics.
Usually operate 1 large clarifier (#3 or #4) and bring on a small clarifier (#1 or #2) at weekends in summer.
No planned maintenance program, only change oil as required.
Some algae control, brushes etc. on the outside but not very effective. Clarifier is drained 2 or 3 times in
summer for manual cleaning.
Concrete in good condition.
Recommend inspection when tank is drained.
Inspect wetted components when tank
is empty.3
Average Flows Rated for 10,000m3/d (416m3/h, 116 L/s).
Peak FlowExpected 20,000 m3/d (2m/h up flow rate) but may have hydraulic or process restrictions, solids carry-over
from blanket due to under-capacity of RAS.
Operate more tanks at this flowrate to
share the flow.
Weir Length 106m, weir overflow rate 1.1 L/m/s Normal Design
Capacity Surface Loading Rate (up flow rate) ~1m/h at 10,000m3/d Normal Design
Solids loading Rate Calculated at 3.6 kgMLSS/m2.h at 3,500mg/L MLSS Normal Design
TSS carry-over Minimal. Effluent quality excellent, and good clarity 1
Flow distributionGood, no apparent short-circuiting.
Weir overflow not uniform around the launder - requires levelling of v-notch weirsLevelling required. 3
Scum and scum box Moving surface scraper/collector, and beach.
Scum removal Discharge to sump/drain adjacent to clarifier #3, collected by suction tanker
Scum sprayers None.
Floatables Scum and floatables in the feed well and on the surface of the tank. Skim off to avoid build up 3
Weir troughDouble sided launder trough with cross baffles. V-notch weirs. Access difficult.
Launder v-notch weirs uneven and leaking - needs some maintenance.
Leveling and general maintenance
required.3
Algae Algae on the surface of the tank, walls and launders.
CleaningSome brushes provided around the weir and wall, but not very effective and require maintenance.
Manual cleaning required, drain the tank and clean, 2 or 3 times in summer.
Remove equipment and implement
cleaning program or covers3
Stilling Baffle Dissipation well and stilling baffle with scum outlets Inspect when empty 2
Scrapers Two spiral sludge scrapers, across full width of tank Inspect when empty 2
Bridge Fixed bridge access to drive, safe access. 2
Bridge mechanism/drive
Envirodyne Mechanism, All equipment/baffles mild steel painted.
Above water components in reasonable condition, some evidence of surface corrosion/rusting at liquid-air
interface..
No torque issues, scraper moves smoothly with no obvious jerkiness
Generally unplanned maintenance – no specific maintenance program at present. Oil changes only.
Motor was replaced with 0.5 HP, 1,725 rpm, Baldor/Reliance motor.
The unit is variable, but operates at a fixed speed.
Envirodyne drive mechanism from
2007/8, life expectancy 15-20 years
RAS flowRAS submersible pumps located in a wet well closer to clarifier #4 than #3.
Wet wells have covers and pump lifting hoist2
Equipment7.5 HP / 5.6 kW 1,740rpm.
Flygt 3127.181 pumps.
Condition unknown, pumps are more
than 10 years old. 2
Flow measurement Yes
ControlVariable speed
Pump generally runs at 100% max RAS rate. RAS pipe is 300mm diameter from #4 and 250mm from #3
Standby capability Spare pump provided to share between Clarifier #3 and #4.
WAS system Not applicable - Waste from Bioreactor based on sludge age
Flow splitting No issues with ML flow split - 3-way inlet flow-splitter with motorized valves. All in good condition. 2
Outlet valves / gates 600 mm dia outlet pipework, then flowmeter and UV system. Below grade, no inspection
Corrosion Some corrosion starting on effluent launder supports at the water-air interface.
Paint and undertake general
maintenance during summer to prevent
further corrosion
3
Safety Good, light, handrails, missing life float 2
Grating / handrails Generally good condition 2
Electrical Good condition 2
Valves and pipework Submersed or below-grade, no inspection. Inspect when empty.
Buildings No buildings
RESORT MUNICIPALITY OF WHISTLER Secondary Clarifier Assessment
Technical Memorandum April 2020
PrefixClient
Photo 1: Clarifier 1&2 Corrosion Photo 2: Clarifier 1&2 Corrosion
Photo 3: Clarifier 1&2 Launder Trough Corrosion & Rusting
Photo 4: Clarifier 1&2 Envirodyne Drive Mechanism
Photo 5: Clarifier 1&2 Corrosion & Rusting
Photo 6: Clarifier 1&2 Building Frame Corrosion
Inspection Photos
2
0029.236-300
RESORT MUNICIPALITY OF WHISTLER Secondary Clarifier Assessment
Technical Memorandum April 2020
Prefix Client
Photo 7: Clarifier #2 Concrete
Photo 8: Clarifier 1&2 Steelwork Corrosion
Photo 9: Clarifier #3
Photo 10: Clarifier #3 Scum Scraper, Brushes & Launder
Photo 11: Clarifier #3 Brush Cleaning Photo 12: Clarifier #3 Launder Corrosion
Inspection Photos
3
0029.236-300
RESORT MUNICIPALITY OF WHISTLER Secondary Clarifier Assessment
Technical Memorandum April 2020
Prefix Client
Photo 13: Clarifier #3 Drive Mechanism Photo 14: Clarifier #3 Launder
Photo 15: Clarifier #3 Brush System
Photo 16: Clarifier #3 Drive & New Motor
Photo 17: Clarifier #4 Photo 18: Clarifier #4 Launder Corrosion
Inspection Photos
4
0029.236-300
RESORT MUNICIPALITY OF WHISTLER Secondary Clarifier Assessment
Technical Memorandum April 2020
Prefix Client
Photo 19: Clarifier #4 Uneven Overflow Photo 20: Clarifier #4 Wall Brush
Photo 21: Clarifier #4 Beach Photo 22: Clarifier 3&4 RAS
Photo 23: Clarifier #4 Algae/floatables