Bheemdatta Municipality Resettlement Plan
-
Upload
khangminh22 -
Category
Documents
-
view
3 -
download
0
Transcript of Bheemdatta Municipality Resettlement Plan
Resettlement Plan
Project Number: 47252-002
December 2020
NEPAL: Regional Urban Development Project
Upgrading and Rehabilitation of Urban Road and Drainage in Bheemdatta
Municipality
Prepared by the Government of Nepal for the Asian Development Bank.
This resettlement plan is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature.
Your attention is directed to the “terms of use” section of this website.
In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.
i
Table of Contents ABBREVIATIONS ................................................................................................... iii
WEIGHTS AND MEASURES ................................................................................. iv
GLOSSARY OF NEPALI TERMS............................................................................ iv
Glossary of Terms .................................................................................................... v
EXECUTIVE SUMMARY.......................................................................................... 1
I. PROJECT DESCRIPTION ........................................................................... 6 A. Introduction ..................... ....................................................... ........ 6 B. Sub-project Description and Proposed Components .............................. 7 C. Measures to Avoid or Minimize Impact ................................................... 13 D. Scope and Objectives of RP.............................................................. 17
II. SCOPE OF LAND ACQUISTION AND RESETTLEMENT IMPACTS ................ 21
A. Beneficial Impact of the Sub-project ........................................................ 21
B. Scope of Land Acquisition....................................................................... 21 C. Summary of Impact .................................................................................. 30 D. Indigenous Peoples ......................................................................... 32 E. Impact Category of the Subproject ................................................... 33
III. SOCIO-ECONOMIC INFORMATION AND PROFILE ....................................... 34
IV. INFORMATION DISCLOSURE, CONSULTATION AND PARTICIPATION ..... 40
A. Community & Stakeholder Consultations ............................................. 40 B. Information Disclosure and Dissemination ........................................... 42 C. Future Consultations and Participation ................................................ 43
V. GRIEVANCE REDRESS MECHANISMS ........................................................ 45
VI. LEGAL FRAMEWORK .................................................................................... 47
A. The Constitution ................................................................................... 47 B. Land Acquisition Act, 2034 (1977) ....................................................... 47 C. Land Reform Act 2021 (1964) .............................................................. 48
D. Local Government Operation Act, 2074................................................. 48 E. Land Acquisition, Rehabilitation and Resettlement Policy (LARRP) .. 49 F. Policies and Act related to Indigenous Peoples ..................................... 51 G. ADB’s Safeguard Policy Statement 2009 ............................................ 52 H. ADB’s Policy on Indigenous Peoples (SPS 2009) ............................ 53 I. Measures for Bridging Gaps between ADB and GON Policies ............ 53
VII. ENTITLEMENT, ASSISTANCE AND BENEFITS.................................... 55 A. Entitlement Policy................................................................................. 55 B. Entitlement Matrix ................................................................................ 56
ii
VIII. RESETTLEMENT BUDGET AND FINANCING PLAN ...................... 62
A. Dismantling, Rehabilitation / Maintenance Cost....................................... 62 B. Reinstatement / Protection for Public / Community Properties .................. 62 C. Rehabilitation Allowances.................................................................. 62 D. RP Implementation and Management Cost ......................................... 62 E. Contingencies ....................................................................................... 63 F. Total Cost Estimate ............................................................................. 63 G. Financing Plan ......................................................................................... 63
IX. INSTITUTIONAL ARRANGEMENTS......................................................... 64 X. IMPLEMENTATION SCHEDULE................................................................. 66 XI. MONITORING AND REPORTING............................................................. 67
Annexes ..................................................................................................... 70 Annex-1: List of Consulted Persons and Inventory of Loss Annex-2: Demographic and Economic Information of Affected Households Annex-3 (A): Land Ownership and Impact on Land Annex-3 (B): Minimum Land Rate and Current Market Price of Land Annex 4: Minutes of Meeting Annex-5(A): Third Party Verification Letter Annex-5(B): Individual Consent of Affected Owners
iii
ABBREVIATIONS
ADB Asian Development Bank AH Affected Household AP Affected Person BPL Below Poverty Level CBO Community Based Organizations CDC Compensation Determination Committee CDO Chief District Officer CFC Compensation Fixation Committee CPR Community Property Resource CRIPP Combined Resettlement and Indigenous Peoples Plan DDC / DCC District Development Committee / District Coordination Committee DoR Department of Roads DSC Design and Supervision Consultants DUDBC Department of Urban Development and Building Construction EA Executing Agency GoN Government of Nepal GRC Grievance Redress Committee HA Hectares HH s Households IA Implementing Agency IP Indigenous People IR Involuntary Resettlement LA Land Acquisition LA Act Land Acquisition Act NGO Non-Government Organization NRs Nepalese Rupees PCO Project Coordination Office PD Project Director PISU Project Implementation Support Unit PIU Project Implementation Unit PMC Project Management Consultant PM Project Manager PPTA Project Preparatory Technical Assistance RoW Right of Way RP/IPP Resettlement Plan / Indigenous Peoples Plan R-PIU Regional Project Implementation Unit R&R Resettlement and Rehabilitation TA Technical Assistance ToR Terms of Reference WHH Women Headed Households
iv
WEIGHTS AND MEASURES
Sq.m Square meter cum Cubic meter Km Kilometer mm Millimeter
GLOSSARY OF NEPALI TERMS
Ropani Size of land parcel; 1 ropani= 16 anna (0.509ha)-508.72 sq.m Anna Size of land parcel; 1 anna= 4 paisa (0.0509ha) Paisa Size of land parcel; 1 paisa= 4 dam = 31.80 sq.m Dam Size of land parcel; 1 dam= 1.99 sq.m Bigha Size of land parcel; 1 bigha= 20 katha (0.678ha) Crore 10 million (= 100lakh) Dhur Size of land parcel; 1dhur= 0.0017ha Katha Size of land parcel; 1 katha= 20 paisa (0.0339ha) Kucchi Temporary structure e.g a rural hut made of wood, bamboo or
stone with Mud mortar and a thatched roof Lakh, lac 100,000 Pukka Structure (house/ building) with permanent roofing made of RCC/
RBC Semi- Pukka
House or building made of stone with mud mortar and clay, timber, slate or corrugated iron roofing
v
Glossary of Terms
Affected Person: In the context of involuntary resettlement, displaced persons are those who displaced physically (relocation, loss of residential land, or loss of shelter) and/or economically (loss of land, assets, access to assets, income sources, or means of livelihood) as a result of (i) involuntary acquisition of land, or (ii) involuntary restrictions on land use or on access to legally designated parks and protected areas; (iii).or any other moveable or fixed assets acquired, possessed, restricted, or otherwise adversely affected, in full or in part, permanently or temporarily
Census: Census is 100% enumeration of affected persons and to document the socio-economic status of potentially affected persons within the project footprint. The census will provide a demographic overview of the population, households' assets, source of incomes, and means of livelihood.
Compensation Determination Committee (CDC): The committee established as per Land Acquisition Act 2034 (1977) for the determination of compensation rate.
Compensation: Payment in cash or in kind in lieu of acquisition of an asset or a resource that is acquired or affected by a project.
Cut-off date: The completion date of the census that establishes the eligibility for receiving compensation and resettlement assistance by the project affected persons. For land, the cut-of date will be the date of notice published by the CDC.
Dalits: The group of people defined and recognized by National Dalit Commission. The word is usually designated for a group of people belonging to the so-called lower castes, many of whom are traditionally regarded as 'untouchable'.
Grievance Redress Committee (GRC):The committee established under the projects to document, hear, and resolve the project related grievances/concerns.
Indigenous peoples: The ethnic groups and communities having distinct social and cultural characteristics such as distinct language/mother tongue, traditional customs, cultural identity, social structure from those of dominant populations and culture. The National Foundation for Upliftment of Aadibasi/Janjati Act, 2058 (2002) has identified 59 groups as Adivasi/Janajati (or indigenous peoples or nationalities) in Nepal.
Land acquisition: The approaches (voluntary offer, negotiation, inter-agencies transfer, and expropriation) adopted to acquire land for the project components.
Rehabilitation: The allowances/assistance provided as described in the resettlement plan other than compensation of the acquired property.
Relocation: Physical relocation of APs permanently from their shelter.
Replacement cost: The sum of market value of the affected assets plus any transaction costs such as administrative charges, taxes, registration, and titling costs to replace the affected assets.
vi
Restoration: All the measures taken to mitigate all or any adverse impacts of the project on the APs' property and/or livelihoods including enhancement measures.
Severely affected households: The affected households (i) losing 10% or more of their total productive assets and/or income sources; (ii) requiring relocation due to the Project.
Socio-economic survey: The survey conducted to establish monitoring and evaluation parameters and establish a benchmark of socio-economic status of APs.
Vulnerable group: The vulnerable a r e individuals or groups who may experience differential adverse impacts from the proposed project more severely than dominant population because of their unique and inherit socio-economic characteristics. Typically, those households falling below poverty line 1 , the landless, household head with disability, single women headed households, Dalits, and endangered indigenous peoples.
1 NPR 31,134 person / year in 2019 (socio-economic survey year) and NPR 33,223 person / year in 2020.
This figure has been derived from per capita income NPR 19,262 person / year estimated by Nepal Living Standards Survey (CBS, 2010/2011) adjusting Nepal Rastra Bank’s annual inflation rate from 2012 to 2020
1
EXECUTIVE SUMMARY
1. Regional Urban Development Project (RUDP) has been implemented to develop urban infrastructure as well as to strengthen urban sector institutions. The broader goal of the project is to uplift the standard of living of the people; and the objective is to achieve socio-economic transformation in the project municipalities through managed urbanization. The 8 Project Municipalities are Dhangadhi, Bheemdutta, Godawari & Suklaphanta of P7 (now Sudurpaschim) and Biratnagar, Birgunj, Siddarthanagar & Nepalgunj of non P7. The project will improve infrastructure and service delivery in urban roads, drainage and integrated waste management in project municipalities; as well as construction of municipal office building in Suklaphnata and Godawari municipalities. For implementation of the project Government of Nepal (GoN) has received financial assistance from the Asian Development Bank (ADB). Loan No. 3566 for US$ 150 million was approved on 22 September 2017, signed on 27 November 2017 and became effective on 8 December 2017. 2. This document is a Resettlement Plan (RP) for Urban Roads and Drainage component in Bheemdatta municipality under RUDP. This sub-project includes rehabilitation and upgrading of existing road and drainage. The main objective of the RP is to identify impacts and to propose suitable mitigation measures to address the various losses due to the subproject activities. The RP has been prepared based on the detailed engineering design. The major components of the sub-project are urban road, drainage, foot path and road furniture. The RP follows Combined Resettlement and Indigenous People Planning Framework (CRIPPF) prepared by ADB for RUDP and guided by the ADB Safeguard Policy Statement 2009 and other relevant policies and guidelines of Nepal. 3. Considering the budget constraint and magnitude of impacts on public and private structures, the municipality has prioritized the road and drainage improvement works. Meeting held among Bheemdatt Municipality official, R-PIU, PMC and DSC on 30th April, 2019 has selected the most prioritized road that will go under construction. Accordingly out of total 36.6 km road recommended by PPTA, 14.014 km will go under construction in phase-I under the project scope. Therefore, this RP has been prepared for improvement of Phase-I road and drainage in Bhamdatta under RUDP. 4. The loss inventory prepared during project screening stage reveals that there would be severe impacts on the public and private properties, if road and drainage are designed based on the RoW recommended by municipal transportation master plan (MTMP). Therefore, magnitude of the impact was tested out with different road width options and appropriate design width was chosen with proper consultation with municipality in order to avoid or minimize the losses. Different alternatives were discussed and agreed to adopt design width based on the actual available width of existing roads so that the major construction activities could be carried out without impacting the structural element of the houses. Accordingly the detailed design of the road finalized based on alternative agreed to avoid loss and with minimum impact. 5. This Resettlement Plan (RP) aims to explore the measures to avoid or minimize the losses of private and public properties as far as possible. The likely affected local people/ families and communities residing along the proposed road alignment were consulted during socio-economic household survey so that they can have informed choice of the
2
project design. The affected person have chosen the design option resulting partial impact on their structures without affecting structural element of their house and they agreed for offering donation voluntary in case of unavoidable minor loss of land and structures. This RP therefore, focuses on the assessment of eligibility criteria for voluntary donation and ensure willingness of affected owners. 6. Altogether 628 structures will be affected, which include the projected temporary shed in front part of the house locally known as Chhaja, house peti (apron) or boundary wall of 619 private houses, 1 school, 4 Government offices and 4 public/community properties (temple, chautara). As such total 3740 individuals living in 619 households are identified as affected persons due to the sub-project. Out of them 1965 (52.54 %) are male and 1777 (47.46 %) are female with sex ratio 1.11. The average household size of the affected owners is 6.25. The findings of field survey and loss inventory signify that there would not be physical displacement and the affected persons would loss less than 10 % of their productive asset. Hence, none of them are severely affected persons. 7. Based on eligibility criteria for voluntary donation as specified in CRIPPF, the project will accept self-declaration of voluntary donation of partial structures and clearance of municipal right of way. The offer has been considered in condition of; i) the voluntary offer is of small strips of land, ii) it will not result in permanent and significant loss/impact on income and livelihood of the owner, iii) road improvement and other project activities will directly benefit the owners, iv) meaningful consultation was carried out to finalize the design, v) land owners agree and their voluntary offer without coercion is documented, and vi) the donor is not categorized as poor or vulnerable. Based on these criteria, the affected owners are eligible for voluntary offer and also are willing for voluntary donation of affected minor structures or lands located within the adopted design width. The Individual consent of the affected owners has been collected and attached in Annex-5. 8. Since there will be partial dismantling of the projected structures located within the adopted design width and main structures remain unaffected, there would not be relocation impacts (displacement of residential houses). There would be nominal economic displacement as the affected parts primarily include apron (peti), temporary shed ( chhaja), boundary wall which are not contributing to the household's income. The affected owners are operating their business in main building and the land being used by affected projected structures viz. chhajja or peti is not used for business purpose. Most of the proposed roads are in city core area, which is town planning area. The Nagar Vikas Samiti has prepared Mahendranagar Town Development Master Plan in B.S 2029 (1973) and also fixed the road RoW. After fixing the road width (50 ft for North-South gully roads and 30 ft for East-West gully roads) residential plots were sold beyond this road width on both sides. The local residents have built peti (apron) and temporary shed (Chhaja) on the free space between edge of black topped (mostly drain) and their houses. Since the lands covered by the affected structures are located within the width of public road, the affected owners will loss no land. The inventory of loss indicates that the loss of land outside the town planning areas is less than 10 percent of total land owned by the affected individual household (Annex-3). The implementation of the sub-project will have more positive impacts rather than adverse impacts to the owners because the upgraded road will increase their income by expanding market as well as increase in their rental value and land price. Therefore, the
3
voluntary donation of affected minor structures and small strips of land was accepted following the provision of CRIPPF. 9. The cost for dismantling and minor maintenance works of affected structures within the design width (formation width) has been provisioned and included in BoQ. This cost primarily covers the dismantling, repair and maintenance of public and community structures. The useable material will be used for reinstatement of demolished structures. Transportation cost for disposal of unusable materials of demolished structures has also been included in BoQ. The inventory of loss prepared during design stage includes the information on type of house and current status of building along the road alignment. This information will be verified and updated during the construction, if required in order to avoid grievance particularly effect to the building due to use of heavy equipment and vibration. Some temporary impacts may arise during the construction period, and shall be addressed by the contractor complying with the combined resettlement and indigenous people planning framework (CRIPPF) prepared for the RUDP. As the proposed roads pass mostly through built up area, some temporary disturbances to businesses are anticipated for a few hours per 100-200 m section during construction of roads (preparation of base course, premix and pavement) and drainages. However, full road closure is not anticipated and these temporary disturbances will not result in physical or restriction to access to business and resources. In order to avoid and limit the disturbance to the extent possible, consultations with stakeholders will be undertaken at different locations. 10. Field consultations were undertaken especially during household survey at different locations, in particular with affected persons, and municipality representatives. Consultations with community people along the alignment of proposed road sections were carried out to get feedback on people’s perceptions of the project and suggestions. More than 600 persons were consulted during census survey of affected households and the list of them is given in Annex-1. In addition formal meetings / interactions with stakeholders including affected persons were conducted in different locations and dates. Summary such consultations is given in Table- 14 and minutes are attached in Annex-4. 11. A summary of RP including sub-project's design alternative, impacts, entitlement, budget, grievance redress mechanism and contact information will be made accessible to the affected people and stakeholders through the respective Ward Offices, Bheemdatta Municipality Office and office of R-PIU. Different design options (viz road width recommended by PPTA or municipality / MTMP, within the existing width, including no project choice) were shared with the affected local people and communities so that they can have informed choice of the project design. The detailed design of the road sections have been finalized based on the alternative agreed to avoid loss and with minimum impact. As the affected persons have chosen design option resulting partial loss of structures, the project accepts self-declaration of voluntary donation of structures and clearance of municipal right of way. Such offer has been considered only after assessment of eligibility criteria as stated in CRIPPF and willingness of affected owners for donation voluntarily. As stated in entitlement matrix there is no compensation for the donated land and self-demolition of affected structures. However, there are some provisions to mitigate the impacts such as provision of exemption of registration fees or other municipal charges, repair allowances to structure owner based on per unit rate (sq.m) as decided by municipal
4
board, exemption of 3 years’ housing tax (only for demolished building), waiver of building permission fees and taxes to rebuild affected house. 12. To keep more transparency and for further active involvement of APs and other stakeholders, the subproject information will be disseminated through disclosure of safeguard planning documents. The EA will provide relevant information (final RP endorsed by the EA and other relevant information, if required) in a timely manner. 13. The grievance redress mechanism (GRM) as proposed in CRIPPF has been established for this project. The project has established two tiers of GRM at the local (project municipality) & central (PCO) levels respectively. A municipal level GRC has been formed in Bheemdatta Municipality on 2074/10/14 BS (2018 Jan 28). The composition of the GRC is in line with PAM and CRIPPF; headed by Mayor of the municipality. The committee consists of following members:
I. Chairperson : Mr. Surendra Bista , Mayor II. Member : Project Manager, RPIU/DUDBC Dhangadhi, Kailali III. Member : to be nominated , representing Affected Person IV. Member : to be nominated , representing Affected Person V. Member Secretary: Mr. Hari Singh Dhami, Social Development Unit, Bheemdatta
Municipality.
14. The GRC will meet as needed to determine the merit of each grievance, and resolve grievances within 7 working days of receiving the complaint. Similarly, at the central level a GRC has been formed under the chairmanship of Project Director (PD) comprising of Deputy Project Director and chief of social development unit of MoUD as members. The unresolved or major issues forwarded by the Municipality level GRC will be reviewed at PCO level GRC for final solution. Decision must be made within 15 days of receipt of complaint at this level. The PCO level GRC shall refer the complaints registered at the PCO to the concerned municipality level GRC for initial hearing within 7 days of registration.
15. An aggrieved person shall have access to the country's legal system at any stage, and accessing the country's legal system can run parallel to accessing the project GRM and is not dependent on the negative outcome of the GRM. People who are, or may in the future be, adversely affected by the project and not satisfied with the established GRM may submit complaints to ADB’s Accountability Mechanism.
16. An entitlement matrix has been prepared in line with the requirements of GON and ADB’s Safeguard Policy Statement (2009) on involuntary resettlement. The entitlement matrix (EM) has provisions of self-declaration of voluntary demolition of building and clearance of municipal Right of Way (ROW). The CRIPPF explains that voluntary donation is a choice of affected person who meets all eligibility criteria. As stated earlier the affected persons have chosen design option resulting partial impact on their temporary structures and they also meets all eligibility criteria. Thus the subproject will adopt voluntary donation approach for dismantling of projected structures that fall within the municipal Right of Way (ROW) as well as adopted design width without affecting the main buildings. EM has also provisions to ensure that the owners are the direct beneficiaries of the project and are willing for voluntary donation.
5
17. The total estimated resettlement budget for the implementation of this RP is NRs. 55,411,492. This cost includes all costs related to dismantling, rehabilitation and minor maintenance of affected structures within RoW, reinstatement / maintenance / protection of the affected public / community properties, RP implementation, monitoring and contingencies. The major cost related to the dismantling, reinstatement and protection of affected structures including public / community properties is included in BoQ. All the budget for implementation of the RP will be borne by the government. The MOUD, the executing agency, will ensure that adequate funds are delivered on time for timely implementation of the RP.
18. The MOUD working through its Department of Urban Development and Building Construction (DUDBC), has established a project coordination office (PCO) for the RUDP headed by a project director. The PCO is staffed with a social development/ safeguard expert under the Project Management Consultant (PMC) to ensure smooth implementation of the RP and take corrective actions if necessary. The R-PIU established in DUDBC divisional office Kailali, along with the DSC is the Implementing Agencies (IAs) for the sub-projects. The municipality has also established a project implementation support unit (PISU) for smooth implementation of the projects. The R-PIU headed by Project Manager and staffed with a social development officer is responsible for further updating and implementation of this RP. 19. A design and supervision consultant (DSC) is engaged to support the R-PIU in all its activities; and will make sure that the relevant conditions formulated in the CRIPPF and RP will be included in the tender documents, to allow the bidders to include these measures and conditions in their bids. The DSC has qualified personnel to carry out this task. The DSC will assist with any rehabilitation and resettlement to ensure that affected persons are aware of their entitlements and to ensure conformity with the project RP.
20. The project will be implemented over six years (2017-2023). Construction activities are expected to start from the first quarter of 2020. The voluntary dismantling of structures will be completed prior to handing over of subproject site and the start of civil works. This RP includes individual consent of affected owners offering voluntary donation of affected structures and land. The voluntary donation process and eligibility criteria as specified in CRIPPF have been review and verified by Municipality, RPIU and Nagarik Samaj viz Citizen Forum nominated by municipality as an independent third party. So, individual consents in this regard have been collected prior to contract award to ensure there is no outstanding issue.
21. The RP implementation will be monitored through internal monitoring systems. Internal monitoring will be the regular activity of the R-PIU and DSC, which is also in charge of implementing the RP. The R-PIU will maintain a record of all transactions in the resettlement database. The project office will be responsible to keep the record of the baseline, socio-economic and census data for field level monitoring. The PCO/DUDBC will submit semiannual internal monitoring reports of the RP implementation to ADB.
6
I. PROJECT DESCRIPTION A. Introduction
22. Regional Urban Development Project (RUDP) aims to develop urban infrastructure and to strengthen urban sector institutions. The broader goals are to uplift the standard of living of the people, reduce poverty and capitalize on the benefits of urbanization to support economic growth based on a sustainable development track. The services are proposed to deliver in four Municipalities of Province 7 (now Far-western Province) namely i) Dhangadhi, ii) Godavari, iii) Shuklaphanta and iv) Bheemdatta; as well as in the non-provience-7 municipalities of Biratnagar, Birgunj, Nepalgunj and Siddharthanagar. The project will improve infrastructure and service delivery in urban roads, drainage and integrated waste management in project municipalities; as well as construction of municipal office building in Suklaphnata and Godawari municipalities. For implementation of the project Government of Nepal (GoN) has received financial assistance from the Asian Development Bank (ADB). Loan No. 3566 for US$ 150 million was approved on 22 September 2017, signed on 27 November 2017 and became effective on 8 December 2017. 23. This document is a Resettlement Plan (RP) for Urban Roads and Drainage component in Bheemdatta municipality under RUDP. This sub-project includes rehabilitation and upgrading of existing road and drainage. The main objective of the RP is to identify impacts and to propose suitable mitigation measures to address the various losses due to the subproject activities. The RP has been prepared based on the detailed engineering design. The technical, financial and social feasibility of road alignment of proposed urban road and drain were assessed and it was agreed with the municipality.
7
Figure- 1: Location of Project Area
B Sub-project Description and Proposed Components
24. Bheemdatta Municipality is one of major urban centers of the Kanchanpur District of the Far-Western region as a part of Mahakali region in Terai-Madhesh plain. It lies in southern-west part of Nepal and covers an area of 171.24 square kilometer within 28015’ to 29008’ North Latitude; and 80006’ to 80015.5’ East Longitude. This municipality stands at the elevation of approximately 229 m from sea level. 25. The Project will implement urban environmental improvement, on an integrated basis, in the areas of municipal road, drainage, waste water management and solid waste management. The following table summarizes the components of urban infrastructures in Bheemdatta municipality.
8
Table 1 : Priority Urban Infrastructure Components in Bheemdatta Municipality Municipality Sector Description
Bheemdatta
Waste Water Management
Improvements of existing on-site waste water management New small bore sewerage and decentralized WWTP sites. Serving households approximately 2,000 (as per PPTA).
Solid Waste Management
Strategic waste prevention plus reduce, reuse and recycle (3R). Integrated solid waste management (ISWM) system with landfill site. Serving households approximately 10,700 (as per PPTA).
Urban Roads and Drainage
Roads and Drainage works length approximately 36.19 km (as per PPTA)
26. Among the four sub-project components under RUDP, this report covers only road and drainage sub-project in Bheemdatta municipality. The Road and Drainage improvement works initially proposed by the municipality based on PPTA recommendation is given in Table below. Table 2: Roads proposed under the project
SN Name of the Roads Length of road (Km) as per PPTA
Municipal RoW (m)
1 M1 Bhasi-Rautela Road 5 15
2 M2 Bhanuchowk-Bishnudham Road 5 15
3 M3 Shukla Phanta Marg 4 20 4 M4 Airport-Airighat Road 2.8 20 5 M5 Gaddachauki(H14)- Airighat Road 4 20
6 M6 Tintara(H14)-Ring Road-Ghadighach Road 5.5 15
7 M8 Municipal Ring Road(North-West Section) 1.5 15
8 Hospital Chowk-Traffic, SP Office
8.8 15
9 Gully No. 1, 2, 3, 4, & 5
10 Parba to 1 No. Galli-eye hospital road
11 Katan Chhetra road
12 Janaki tole Katan Chhetra road
13 Ban Karyala to Uttar Sadak
14 Campus road to Melpot road Total 36.6
9
27. Prioritized Road and Storm Water Drains: Even though the PPTA has proposed nearly 36.6 km road ( Table-2), considering the budget constraint and magnitude of impacts on private and public structures, the municipality has prioritized the road and drainage improvement works in two phases as described below. 28. The total estimated cost for road and drain as presented in Draft Detailed Design Report is about NRs. 4203.7 million but the allocated budget for Bheemdatt Municipality as per PAM is about NRs. 1770 million. Meeting held among Bheemdatta Municipality official, R-PIU, PMC and DSC to find the way out on 30th April, 2019. The meeting decided to select the most prioritized road that will go under construction. The minute of meeting is attached in Annex-4 for reference. Based on that decision, the total road and drain has been divided into two phase, Phase I and Phase II (Table-3). Road and drain under Phase I will go under construction, while the Phase II roads and drains will be constructed in future only after the management of budget. Table - 3: Phasing of Road and Drain
S.N Road Name Road Length (m) Drain Length (m)
Phase I Phase II Total Phase I Phase II Total
1 M1:Bhasi - Rautela Road 560.00 3,081.00 3,641.00
- 3,910.00 3,910.00
2 M2: Bhanuchowk - Bishnudham Road 210.00
4,675.00 4,885.00 451.00 8,247.36
8,698.36
3 M3: Shukla Phata Marga (Bhanuchowk-Madan chowk-Airport Road)
3,756.48 - 3,756.48 7,264.50 -
7,264.50
4 M4: Airport - Airighat Road 652.56
1,659.44 2,312.00 851.50 3,054.00
3,905.50 5 M5: Gaddachauki (H14) -
Airighat Road - 4,004.00 4,004.00
- 7,719.00 7,719.00
6 Tintara (H14) - Ring Road - Ghadighach Road (M6)
- 5,587.00 5,587.00
- 10,085.00 10,085.00
7 Municipal Ring Road (North-West Section) (M8)
- 1,137.00 1,137.00
- 2,229.23 2,229.23
8 Madan Chowk- Dasrat Chowk- Napi karalaya- Bhagatpur Chowk Road
1,149.70 - 1,149.70 2,165.00 -
2,165.00
9 Traffic Chowk- Dasrat Chowk- BP Chowk Road (Hospital Link Road)
596.84 - 596.84 1,170.00 -
1,170.00
10 Hotel Opera Road 190.00 90.00 280.00
380.00 154.00 534.00
11 V1: Gully No. 1 Road - Shalgadhi Road 1,102.04 - 1,102.04
1,331.00 - 1,331.00
12 V2: Gully No. 2 Road 407.92 - 407.92 392.00 -
392.00 13 V3: Gully No. 3 Road 407.37 - 407.37
389.00 - 389.00
14 V4: Gully No. 4 Road 404.75 - 404.75 387.00 -
387.00 15 V5: Gully No. 5 Road -
Campus Road 674.77 - 674.77 1,109.00 -
1,109.00 16 H1: Gully Road -1(East
West section) 298.26 - 298.26 - - -
10
S.N Road Name Road Length (m) Drain Length (m)
Phase I Phase II Total Phase I Phase II Total
17 H2: Gully Road-2 (East West section ) 297.88 - 297.88
- - -
18 H3: Hospital Road (Gully 6 to Gully 1) 290.08 - 290.08
580.00 - 580.00
19 H4: Campus Road (Janki tole) to Gully 1 284.40
195.60 480.00 580.00 380.00
960.00
20 Sarswati Tole Road 1 (East West section, Katan Area), (H5)
300.99 - 300.99 593.00 -
593.00
21 H6: Sarswati Tole Road 2 (East West section, Katan Area)
149.85 200.15 350.00
- 688.00 688.00
22 H7: Sarswati Tole Road 3 (East West section, Katan Area)
392.41 - 392.41 774.00 -
774.00
23 H8: Sarswati Tole Road 4 (East West section, Katan Area)
372.22 - 372.22 719.00 -
719.00
24 H9: Eye Hospital Road 429.83 - 429.83 838.00 -
838.00
25 H10: Hospital Road (Gully 1 to Bhagatpur Marg)
738.03 - 738.03 1,444.00 -
1,444.00
26 V6: Krishi Vikash Road (Malpot/Napi karalaya-E/W highway)
347.58 - 347.58 665.00 -
665.00
Total 14,013.96 20,629.19 34,643.15
22,083.0 36,466.59
58,549.59
29. Minor rehabilitation and improvement of first priority (Phase I) roads of total 14.014 km length (23 road sections) includes construction of urban standard road with both side drain, footpath, road furniture and street lamp. The pavement is proposed for all 14.014 km roads.
13
(C) Measures to Avoid or Minimize Impact 30. Attentions had been given during the project preparatory and detailed design phases of the subproject to minimize the adverse impacts due to land acquisition and resettlement. Initially preliminary design was guided by municipal RoW (based on MTMP) and other design parameters recommended by PPTA team. However, considering the magnitude of impacts on private and public structures different options were discussed in consultation with municipality and R-PIU. During the design phase technical and engineering constraints were one of the major concerns during exploration of various alternative design options. Before finalizing the design different design options (within the existing width, including no project choice) were shared with the stakeholders. The affected local individuals/ families and communities were also consulted during socio-economic household survey so that they can have informed choice of the project design. Following are the general criteria adopted for the selection of the design to avoid IR impacts : Initially attempt was made in designing the urban road within municipal RoW and length
recommended by PPTA as far as possible. Where the resettlement impacts are severe then attempts have been made designing project within existing RoW and accommodate all proposed facilities within it as far as possible with proper consultation with the municipality.
The loss inventory prepared during project screening stage reveals that there would be severe impacts on the public and private properties, if road and drainage are designed based on the RoW recommended by municipal transportation master plan (MTMP). Therefore, magnitude of the impact was tested out with different road width options and appropriate design width was chosen with proper consultation with municipality in order to avoid or minimize the losses. Different alternatives were discussed and agreed to adopt design width based on the available width so that the major construction activities could be confined within the designed width without impacting the major part of the structures. Accordingly the detailed design of the road finalized based on alternative agreed to avoid loss and with minimum impact. The road section wise details of road width options and impacts are presented in Annex-4 of this report. The comparison between the impacts between municipal RoW and adopted design width as well as the measures taken to mitigate the impacts are given in Table-4 below.
Table-4: Comparison of Impacts between Municipal RoW and Adopted Design Width
S. No. Road Name
Municipal RoW and Likely Impacts
Adopted Design Width to avoid or minimize the losses
Measures taken to avoid or minimize Impacts Width
(m) Impacts Design
Width (m)Impacts
1
M1: (Bhasi Rautela Road), Total Length=3641 m, Phase I Construction Length=560 m (Chainage 0 +00 - 0+560 m)
24 Major part of 37 houses will be affected.
12 Total 5 minor structures (peti and boundary wall) of houses including one temple will be affected, but structural element of
Considering the magnitude of impact and budget constraint 12 m wide road of length 560 m road out of total 3641 m proposed length will be constructed
14
S. No. Road Name
Municipal RoW and Likely Impacts
Adopted Design Width to avoid or minimize the losses
Measures taken to avoid or minimize Impacts Width
(m) Impacts Design
Width (m)Impacts
houses will remain unaffected.
in phase I to avoid / minimize losses.
2
M2: (Bhanuchowk -Bishnudham Road), Total Length=4885 m, Phase I Construction Length= 210 m (Chainage 0+00 - 0+210)
10 Major part of 5 houses including 9 minor structures will be affected.
10 Total 9 minor structures will be affected and major part of houses will remain unaffected.
Considering the magnitude of impact and budget constraint 210 m out of total 4885 m road will be constructed.
3
M3 :Shukla Phata Marga (Bhanuchowk-Madan chowk-Airport Road), Total length=3,756.5 m, Phase I construction length=3,756.5 m
20 Total 60 houses (major part) will be affected.
34.5 m from ch. 0+00 to 0+540.39 & 12 m from ch. 0+540.39 to 0+3,756.5
19 minor structures will be affected.
Design width of the road has been reduced to 12 m to avoid or minimize the impact.
4
M4: (Airport-Airighat Road), Total Length = 2312 m, Phase I Construction Length = 652.56 m (Chainage 1+660 - 2+312)
20 Total 41 structures will be affected including major part of houses.
12 Only 4 minor structures will be affected and structural element of houses will remain unaffected.
Considering the magnitude of impact and budget constraint o652.56 m out of 2312 m road will be constructed reducing design width to 12 m.
5
V5: Gully No-5 Road(Campus Road, North-South section), Total Length = 674.77 m, Phase I Construction Length = 674.77 m
15 Total 46 houses (major part) including 103 minor structures will be affected.
12 Total 103 minor structures (Chhaja & Peti) will be affected and major element of houses will remain unaffected.
Design width has been reduced to 12 in order to minimize possible loses of private / public properties.
6
V-4: Gully No-4 Road (North-South section), Total Length = 404.75 m, Phase I Construction Length = 404.75 m
15 Major part of 39 houses including 76 minor structures will be affected.
12 Total 74 minor structures (Chhaja & Peti) will be affected and major part of houses will remain unaffected.
Considering the magnitude of impact 12 m design width of the road has been adopted.
7 V-3: Gully No-3 Road (North-South section),
15 Major part of 36 houses including 64
12 Total 64 minor part (Chhaja & peti) will be
Considering the magnitude of impact 12 m
15
S. No. Road Name
Municipal RoW and Likely Impacts
Adopted Design Width to avoid or minimize the losses
Measures taken to avoid or minimize Impacts Width
(m) Impacts Design
Width (m)Impacts
Total Length=407.37m, Phase I Construction Length=407.37 m
minor structures will be affected.
affected and major part of houses will remain unaffected.
design width of the road has been adopted.
8
V-2 :Gully No-2 Road(North-south section), Total Length = 407.92 m, Phase I Construction Length = 407.92 m
15 Major part of 31 houses including 89 minor structures will be affected.
12 Total 89 minor part (Chhaja & peti) will be affected and major part of houses will remain unaffected.
Considering the magnitude of impact 12 m design width of the road has been adopted.
9
V-1: Gully No-1 Road (North-South section), Total Length = 1,102.04 m, Phase I (Construction Length =1,102.04 m
15 Total 31 houses including 98 minor structures will be affected.
12 Total 98 minor part (Chhaja & peti) will be affected and major part of houses will remain unaffected.
Considering the magnitude of impact 12 m design width of the road has been adopted.
10
V6: Krishi Vikash Road (Malpot/Napi-Highway), Length=347.58 m
15 Minor part of 4 houses will be affected
12 Minor part of 4 houses will be affected
Considering the magnitude of impact 12 m design width of the road section has been adopted.
11
H1:(East-West Gully-1), Total Length = 298.26 m, Phase I Construction Length=298.26 m
10 21 houses (major part) including 23 minor parts will be affected.
9 Minor part of 23 houses (Chhaja & Peti) will be affected.
In order to avoid or minimize the loss 9 m design width has been adopted.
12
H2: (East-West Gully-2), Total Length = 297.88 m, Phase I Construction Length=297.88 m
10 27 houses (major part) will be affected
9 16 houses (minor part) will be affected
In order to avoid or minimize the loss 9 m design width has been adopted.
13
H-3: Hospital road ( East-West Gully-3), Total Length = 290 m, Phase I Construction Length =290 m
15 16 houses (major part) will be affected.
10 None In order to avoid the loss 10 m design width has been adopted.
14
H-4: East –West Gully-4 (Campus Road/Janiki Tole – Gully No-1) Total Length = 480 m, Phase I Construction
15 11 houses (major part) will be affected.
10 None In order to avoid the loss 10 m design width has been adopted.
16
S. No. Road Name
Municipal RoW and Likely Impacts
Adopted Design Width to avoid or minimize the losses
Measures taken to avoid or minimize Impacts Width
(m) Impacts Design
Width (m)Impacts
length = 284.4 m
15
H-5: Saraswoti Tole Road-1 (East- West Section, Katan Area), Total Length = 300.99 m, Phase I Construction Length=300.99 m
15 Major part of 7 houses along with 28 minor structures will be affected.
10 28 minor structures (boundary wall) will be affected.
In order to avoid or minimize the impact 10 m design width has been adopted.
16
H-6: Sarswoti Tole Road 2 (East-West section, Katan Area) , Total Length = 350 m, Phase I construction Length=150 m (ch 200-350)
15 4 houses (major part) will along with 11 minor structures be affected.
10 11 minor structures (boundary wall) will be affected.
In order to avoid or minimize the impact 150 m out of 350 m length and 10 m design width has been adopted.
17
H-7: Sarswati Tole Road 3 (East West section, Katan Area), Total Length = 392.41m, Phase I Construction length=392.41 m
15 13 houses along with 29 minor structures will be affected.
10 29 minor structures (boundary wall) will be affected.
In order to avoid or minimize the impact 10 m design width has been adopted.
18
H-8: Sarswati Tole Road 4 (East West section, Katan Area), Total length= 372.22m, Phase I Construction Length= 372.22m
15 3 houses along with 26 minor structures will be affected.
10 26 minor structures (boundary wall) will be affected.
In order to avoid or minimize the impact 10 m design width has been adopted.
19
H-9: Eye Hospital Road, East-west Section), Total Length= 429.83 m, Phase I Construction length=429.83 m
15 3 houses including 1 boundary wall will be affected.
10 1 boundary wall will be affected.
In order to avoid or minimize the impact 10 m design width has been adopted.
20
H-10: (Galli 1- BP Chowk - Bhagatpur Marga), Total Length= 738.03m, Phase I Construction Width=738.03 m
15 10 houses with 13 minor structures will be affected.
10 13 minor structures (boundary wall & peti) will be affected.
In order to avoid or minimize the impact 10 m design width has been adopted.
21 Hotel Opera 15 18 houses 15 6 structures In order to avoid or
17
S. No. Road Name
Municipal RoW and Likely Impacts
Adopted Design Width to avoid or minimize the losses
Measures taken to avoid or minimize Impacts Width
(m) Impacts Design
Width (m)Impacts
road, Total length=280 m, Phase I construction length= 190 m (ch. 0+00 - 0+190)
and 6 other structures will be affected.
(peti & shed/shutter) will be affected.
minimize the impact 190 m out of total length 280 m road will be constructed.
22
Madan Chowk-Dashrath Chowk – Napi Kralaya - Bhagatpur Chowk Road, Total Length 1150m
15
25 houses and 6 other structures will be affected.
15 m from Dashrath Chowk to Nani Karalaya (ch: 0+00-0+750) & 12 m from Napi Karalaya to Bhagatpur (ch:0+751- 1+150)
6 structures (peti and boundary wall) will be affected.
Considering the severity of impact the design width has been reduced to 12 m for 400 m long section (Napi karalaya – Bhagatpur).
23
Traffic Chowk- Dashrat - BP Chowk Road (Hospital link Road), Length = 596.84 m
15 None 15 None
Source: Field survey, 2019
During the household census survey for socio-economic information field consultations
were made at various places along the alignment of the proposed road sections and based on people’s concerns and suggestions the design was adjusted to minimize the resettlement impacts.
(D) Scope and Objectives of RP 31. This sub-project includes rehabilitation and upgrading of existing road and drainage. The main objective of the RP is to identify impacts and to propose suitable mitigation measures to address the various losses due to the subproject activities. The RP has been prepared based on the detailed engineering design. The major components of the sub-project are urban road, drainage, foot path and road furniture. The process and methodology followed for this RP preparation include topographic field survey for obtaining screening level data i.e affected structures, field measurement and observation as well as socio-economic household survey of the affected households in order to obtain detailed information on resettlement impacts and to prepare loss inventory. Field verification and consultations with affected persons / communities residing along the alignment of proposed roads and with government line agencies were carried out and different design options were discussed. The RP follows Combined Resettlement and Indigenous People
18
Planning Framework (CRIPPF) prepared by ADB for RUDP and guided by the ADB Safeguard Policy Statement 2009, and other relevant policies and guidelines of Nepal. 32. This Resettlement Plan (RP) aims to explore the measures to avoid or minimize the losses of private and public properties as far as possible. The likely affected local people/ families and communities residing along the proposed road alignment were consulted during socio-economic household survey so that they can have informed choice of the project design. The affected persons have chosen the design option resulting partial impact on their structures without affecting structural element of their houses, and they agreed for offering donation voluntary in case of unavoidable minor loss of land and structures. This RP therefore, focuses on the assessment of eligibility criteria for voluntary donation and ensure willingness of affected owners. In this regard individual consent of affected owners has been collected and attached in Annex-5. 33. The census survey of households residing within the design width of proposed road section was carried out. Altogether 619 households were surveyed, who have built permanent or temporary structures within design width. However, only extended structures such as chhaja (shed in front part of the house), peti (apron) or boundary wall etc need to be dismantled for site clearance during construction. Road section wise details of affected structures within adopted design width to avoid or minimize the impacts are given in table below. Table -5: Summary of Impact within Design Width Adopted to Avoid or Minimize the Impact.
S. No. Road Name Number of Affected structures as per design width
Remarks
1
M1: (Bhasi Rautela Road), design width=12 m, Length=560 m (Chainage 0 +00 - 0+560 m)
Total 5 minor structures (peti and boundary wall) of houses including one temple will be affected, but structural element of houses will remain unaffected.
Considering the magnitude of impact and budget constraint 12 m wide road of length 560 m road (out of total 3641 m proposed length) will be constructed.
2
M2: (Bhanuchowk -Bishnudham Road), Design width=10m, Length= 210 m (Chainage 0+00 - 0+210)
Total 9 minor structures will be affected and major part (structural element) of houses will remain unaffected.
Considering the magnitude of impact and budget constraint 210 m out of total 4885 m road will be constructed.
3
M3 :Shukla Phata Marga (Bhanuchowk-Madan chowk-Airport Road), Design width=34.5 m from ch. 0+00 to 0+540.39 & 12 m from ch. 0+540.39 to 0+3,756.5, Length=3,756.5 m
20 minor structures will be affected.
Design width of the road has been reduced to 12 m to avoid or minimize the impact.
4 M4 (Airport-Airighat), Design width=12 m, Length = 652.56 m (Chainage 1+660 - 2+312)
Only 4 minor structures will be affected and major part of houses will remain unaffected.
Considering the magnitude of impact and budget constraint 652.56 m out of 2312 m road will be constructed reducing design width to 12 m.
5 V5: Gully No-5 (Campus Total 103 minor Design width has been
19
S. No. Road Name Number of Affected structures as per design width
Remarks
Road, North-South section), Design width=12m, Length = 674.77 m
structures (Chhaja & peti) will be affected and major part of houses will remain unaffected.
reduced to 12 in order to minimize possible losses of private / public properties.
6 V-4: Gully No-4 (North-South), Design width=12m, Length = 404.75 m
Total 76 minor structures (Chhaja & Peti) will be affected and major part of houses will remain unaffected.
Considering the magnitude of impact 12 m design width of the road has been adopted.
7 V-3: Gully No-3, Design width=12m, Length=407.37 m
Total 64 minor part (Chhaja & peti) will be affected and major part of houses will remain unaffected.
Considering the magnitude of impact 12 m design width of the road has been adopted.
8 V-2 :Gully No-2, Design width=12m, Length = 407.92 m
Total 89 minor part (Chhaja & peti) will be affected and major part of houses will remain unaffected.
Considering the magnitude of impact 12 m design width of the road has been adopted.
9 V-1: Gully No-1, design width=12m, Length =1,102.04 m
Total 98 minor part (Chhaja & peti) will be affected and major part of houses will remain unaffected.
Considering the magnitude of impact 12 m design width of the road has been adopted.
10
V6: Krishi Vikash Road (Malpot/Napi-Highway), Design width=12m, Length = 347.58 m
Minor part of 4 houses will be affected
Considering the magnitude of impact 12 m design width of the road section has been adopted.
11 H1:(East-West Gully-1), Design width=9m, Length=298.26 m
4 houses (minor part) will be affected.
In order to avoid or minimize the loss 9 m design width has been adopted.
12 H2: (East-West Gully-2), Design width=9m, Length = 297.88 m
4 houses (minor part) will be affected
In order to avoid or minimize the loss 9 m design width has been adopted.
13 H-3: Hospital road ( East-West Gully-3), Design width=10m, Length =290 m
None In order to avoid the loss 10 m design width has been adopted.
14
H-4: East –West Gully-4 (Campus Road/Janiki Tole to Gully No-1), Design width=10m, Length = 284.4 m
None In order to avoid the loss 10 m design width has been adopted.
15
H-5: Saraswoti Tole Road-1 (East- West Section, Katan Area), Design width=10m, Length = 300.99 m
28 minor structures (boundary wall) will be affected.
In order to avoid or minimize the impact 10 m design width has been adopted.
16
H-6: Sarswoti Tole Road 2 (East-West section, Katan Area) , Design width=10m, Length=150 m (ch 200-350)
11 minor structures (boundary wall) will be affected.
In order to avoid or minimize the impact 150 m out of 350 m length and 10 m design width has been adopted.
17
H-7: Sarswati Tole Road 3 (East West section, Katan Area), Design width=10m, Length=392.41 m
29 minor structures (boundary wall) will be affected.
In order to avoid or minimize the impact 10 m design width has been adopted.
18 H-8: Sarswati Tole Road (East West section, Katan
26 minor structures (boundary wall) will be
To avoid or minimize the impact 10 m design width has
20
S. No. Road Name Number of Affected structures as per design width
Remarks
Area), Design width=10m, Length= 372.22m
affected. been adopted.
19 H-9: Eye Hospital Road, East-west Section), Design width=10m, Length=429.83 m
1 boundary wall will be affected.
In order to avoid or minimize the impact 10 m design width has been adopted.
20 H-10: (Gully 1- BP Chowk - Bhagatpur Marga), Design width=10m, Length=738.03 m
13 minor structures (boundary wall & peti) will be affected.
In order to avoid or minimize the impact 10 m design width has been adopted.
21 Hotel Opera road, Length= 190 m (ch. 0+00 - 0+190)
6 minor structures (peti & shed/shutter) will be affected.
In order to avoid or minimize the impact 190 m out of total length 280 m road will be constructed.
22
Madan Chowk-Dashrath Chowk – Napi Kralaya - Bhagatpur Chowk road, Design Width=15 m from Dashrath Chowk to Nani Karalaya (ch: 0+00-0+750) & 12 m from Napi Karalaya to Bhagatpur (ch:0+751- 1+150),Total Length 1150m
6 minor structures (peti and boundary wall) will be affected.
Considering the severity of impact the design width has been reduced to 12 m for 400 m long section (Napi karalaya – Bhagatpur).
23
Traffic Chowk- Dashrat - BP Chowk Road (Hospital link Road), Design width =15m,Length= 596.84 m
None
Source: Field survey, 2019
34. The objective of this RP is to assess the resettlement impacts as well as develop mitigation measures exploring possible alternatives. The loss inventory prepared during project screening stage reveals that there would be severe impacts on the public and private properties, if road and drainage are designed based on the RoW recommended by municipal transportation master plan (MTMP). Therefore, magnitude of the impact was tested out with different road width options and appropriate design width was chosen with proper consultation with municipality in order to avoid or minimize the losses. Different alternatives were discussed and agreed to adopt design width based on the actual available width of existing roads so that the major construction activities could be confined within the designed width without impacting the structural element of the houses. Accordingly the detailed design of the road finalized based on alternative agreed to avoid loss and with minimum impact.
21
II. SCOPE OF LAND ACQUISTION AND RESETTLEMENT IMPACTS
A. Beneficial Impact of the Sub-project
35. The urban road and drainage improvement will have overall positive impacts for all residents of the Bheemdatta municipality irrespective of caste/ethnicity, economic status and socio-political backgrounds. The proposed subproject can be viewed as a means to enhance quality of living in Bheemdatta municipality. It is expected that it will boost economic growth and contribute in poverty reduction bringing substantial economic opportunities in the city. The social benefits arising due to the subproject will be triggered off due to improved accessibility to various services such as easy access to markets, health facilities, schools, workplace etc. which in turn increases the income of the locals, and ultimately uplifting their standard of living. Besides, improved road and drain network will encourage entrepreneurs to invest more in commercial enterprises and industrial activities which ultimately generate employment opportunities for city dwellers. Improved road will also enhance essential and emergency services like schools, health services, public distribution system etc. making them available faster.
B. Scope of Land Acquisition and Likely IR and IP Impacts:
36. The assessment of likely impacts of involuntary resettlement with respect to physical displacement (relocation, loss of residential land, or loss of shelter) and economic displacement (loss of land, assets, access to assets, income sources, or means of livelihoods) as a result of (i) involuntary acquisition of land, or (ii) involuntary restrictions on land use or on access to legally designated parks and protected areas for the proposed components are given below. 37. Bheemdatta has prepared its Municipal Transport Master Plan (MTMP), which indicates road right-of-ways (RoW). Based on the MTMP, Bheemdatta municipality has declared RoWs for all roads within its jurisdiction. The PPTA has initially proposed total 36.6 km length under the project scope. During design phase however, the municipality has prioritized through phasing of the recommended road sections considering budget constraint and magnitude of impact on private and public properties. Now it has been decided to construct 23 roads sections including city core area road (16 road sections) with total length of 14.014 km in phase-I under scope of RUDP. In addition considering the severity of impacts within the municipal RoW, the magnitude of impacts was tested out with different road width options of the roads, and appropriate width was chosen in order to avoid or minimize the impacts. 38. Different alternatives were discussed and agreed to adopt design width based on the actual available width of existing roads so that the major construction activities could be carried out without impacting the major part of the structures. Accordingly the detailed design of the road finalized based on alternative agreed to avoid loss and with minimum impact. Hence, there would not have involuntary resettlement impact resulting physical displacement. There will be nominal economic impact due to loss of minor structures and less than 10 percent of productive assets. Since the minor structures are not contributing to the household’s income, loss of such minor structures will not result adverse impact to
22
the owners; rather the upgraded road will increase their income by expanding the market as well as increasing their rental value and land price. Annex-3 (B) shows the land rate fixed by District Revenue Office and current market price of land to compare results of expanded market and increased land price after the improvement of the roads. Some temporary impacts may arise during the construction period, and shall be addressed by the contractor complying with the CRIPPF prepared for the RUDP. 39. Most of the proposed roads are in city core area, which is town planning area. The Nagar Vikas Samiti has prepared Mahendranagar Town Development Master Plan in B.S 2029 (1973) and also fixed the road RoW. After fixing the road width (50 ft for North-South gully roads and 30 ft for East-West gully roads) residential plots were sold beyond this road width on both sides. The local residents have built peti (apron) and temporary shed (Chhaja) on the free space between edge of carriage way / black topped (mostly drain) and their houses. Since the lands occupied by the affected structures are located within the width of public road, the affected owners will loss no land. The inventory of loss indicates that the loss of land outside the town planning areas is less than 10 percent of total land owned by the affected individual household as shown in Annex-3. 40. The typical cross-sections of proposed roads of different width ranging from 10 m to 34.5 m are shown in Figures 4 to 7 below. The typical cross section for 10 m width road (Figure-4, left) represents the typical design of four city core area road sections namely gully roads (4 East-West sections H1 to H4). The roads consist of 5.5 m carriageway (black topped), 0.85 m side drain and 0.40 m footpath on both side of the road. Hence, 10 m site clearance is required to carry out construction activities and any structures located beyond 5 m from the centre of the road will not be affected under this project. 41. Figure 4 (right-hand) represents the typical cross section of city core area road viz. H-5: Saraswoti Tole Road-1 (East- West Section, Katan Area), H-6: Sarswoti Tole Road 2 (East-West section, Katan Area), H-7: Sarswati Tole Road 3 (East West section, Katan Area), H-8: Sarswati Tole Road 4 (East West section, Katan Area), H-9: Eye Hospital Road, East-west Section), H-10: (Galli 1- BP Chowk - Bhagatpur Marga) and V6: Krishi Vikash Road. The roads consist of 5.5 m carriageway (black topped), 0.50 m side drain and 1.75m storm water drain on both side of the road. Closed drain has been designed and the foot path and street light will be accommodated within the same space (1.75 m) in either side. Hence, 10 m site clearance is required to carry out construction activities and any structures located beyond 5 m from the centre of the road will not be impacted.
23
Figure 4: Typical Cross Section of Road for 10 m width (10 City Core Area Roads, East West Sections)
42. The city core area North South road sections (Gully No.1 - 5) and Airport - Airighat Road (M4) have been designed as urban road standard road of 12 m width as shown in Figure-5 below. The road consists of 7 m carriageway (black topped), 0.85 m side drain, 1.65 m foot path on both side of the road and street light. Hence, 12 m site clearance is required to carry out construction activities and any structures located beyond 6 m from the centre of the road will not be dismantled under this project, even though they fall within the municipal RoW (15m).
Figure 5: Typical Cross Section of Road for 12 m width (5 City core Area Road, North
South Sections, Gully No.1-5)
43. As Figure-6 shows, an urban road standard (double lane) 15 m wide road is designed for Madan Chowk- Dasrat Chowk- Napi Karalaya- Bhagatpur Chowk Road, Traffic Chowk- Dasrat Chowk- BP Chowk Road (Hospital Link Road and Hotel Opera Road. The road consists of 7 m carriageway (black topped), 0.5 m side drain, 1.5 m cycle
24
track and 2 m storm water drain on both sides. Closed drain has been designed and the foot path and street lamp will be accommodated within the 15 m width. Hence, 15 m site clearance is required to carry out construction activities and any structures located beyond 7.5 m from the centre of the road will not be affected under this project. Figure 6: Typical Cross Section of Road for 15 m width (Madan Chowk- Dasrat Chowk-
Napi karalaya- Bhagatpur Chowk Road, Traffic Chowk- Dasrat Chowk- BP Chowk Road (Hospital Link Road and Hotel Opera Road)
44. An urban road standard (four lane) road of 34.5 m width has been designed for 450 m segment of M-3 (Suklaphanta Marga) as shown in Figure-7, which consists of 7 m carriageway (black topped) on either side with provision of deriver at the centre, side drain, storm water drain, cycle track and greenery area. Closed drain has been designed and the foot path, street light and road furniture will be accommodated within the 34.5 m width. Hence, 34.5 m site clearance is required to carry out construction activities and any structures located beyond 17.75 m from the centre of the road will not be impacted under this project.
Figure 7: Typical Cross Section of Road for 34.5 m width (450 m segment of
M3:Suklaphanta Marga)
25
45. The proposed road and drainage construction works will be carried out within the adopted design width which has been fixed based on the actual available width of the existing roads in order to avoid losses as far as possible. The road section wise details of existing situation are given below in Table-6. Table-6: The road section wise details of existing situation S.N. Name of Road Existing Situation Remarks
M1: (Bhasi Rautela Road), design width=12 m, Length=560 m (Chainage 0 +00 - 0+560 m)
The road M1 under this project starts from East West Highway at Bhasi towards North direction and ends at Mahakali canal crossing site. It is also known as Bhasi-Rautela Road. The road alignment lies in open area with scattered settlement on both sides of the road. Within the adopted design width total 5 minor structures of the houses (2 Chhaja + Peti) and 3 boundary wall) will be affected, which require to dismantle for site clearance during construction. Of the total affected structures 4 are private house and 1 temple. Regarding land loss the affected owners will loss than 10 percent of total land (Annex-3).
The affected households agree for offering donation voluntary and dismantling the affected structures. Individual consent of affected households has been taken and included in Annex-5. The site is clear and no any other issue regarding land acquisition.
M2: (Bhanuchowk -Bishnudham Road), Total Length=4885 m, Phase I Construction Length= 210 m (Chainage 0+00 - 0+210)
The road M2 under this project starts from Bhanuchowk towards North direction to Bishnudham. Out of total 4.8 km only 0.21 km road will be constructed under phase -I. This section of road passes through built up area. Total 9 minor structures i.e Peti and Chhaja of the houses will be affected; but major part of the houses will remain unaffected. The affected owners will loss less than 10 % of total land. Additional vacant land acquisition i.e the land not occupied by the structure is not required as this section of road is in built up area.
There will be minor impact on 9 private structures. They are ready for voluntary dismantle the structures. Individual consent has been taken from them (Annex-5). Except this the site is clear and no any issue regarding land acquisition.
M3 :Shukla Phata Marga (Bhanuchowk-Madan chowk-Airport Road), Total length=3,756.5 m, Phase I construction length=3,756.5 m
The proposed road M3 starts from Bhanuchowk (E/W highway) passing through Madan Chowk ends at airport. The road is the main gateway to Mahendranager town. 34.5 m wide road has been designed from Bhabu Chowk to Madan Chowk (540m) and from Madan Chowk to Airport 12 m road width has been adopted. Storm water drain are proposed on the both sides of the road. A total of 19 minor structures (3 hut/shed, 4 Peti & Chhaja, 11 boundary wall and 1 kitchen shed) will be affected due to sub project; of them 18 are private house and 1 is temple. From Bhanu Chowk to Madan Chowk there is compact settlement, whereas from Madan Chowk towards airport the settlement is scattered. Land loss due to the project is less than 10 % of total land of affected owners.
They are willing to donate voluntary the affected structures or lands. Individual consent in this regard is taken from them before dismantling the structures. Besides this the site is clear and no any issue regarding land acquisition.
26
S.N. Name of Road Existing Situation Remarks
M4: (Airport-Airighat Road), Total Length = 2312 m, Phase I Construction Length = 652.56 m
The proposed road M4 starts from Airport (Majgaun) towards South direction ends at Banskeda. The road is known as Airport-Arighat road has 2.3 km total length, of that only 0.65 km road will be constructed under this project. The road passes through open land. Total 4 structures (3 boundary wall and 1 shed) will be affected due to construction of 12 m wide road. Only small strip of land covered by these structures will be lost by affected owner (less than 10% of total land). Additional land in open area is not required as the available width of existing road is sufficient.
They are willing to donate voluntarily structure and land. Individual consent in this regard is taken them and are attached in Annex-5. The site is clear and no any other issue regarding land acquisition.
V5: Gully No-5 Road(Campus Road, North-South section), Length = 674.77 m
Gully No-5 road starts from Madan Chowk towards South direction. Since the road is in city core area, passes through built up area with dense settlement. Total 103 Peti (apron) and Chhaja (temporary shed) of the houses will be affected due to construction of the road. However, major part (structural element) of the houses will remain unaffected. This area is town planning area, where the Nagar Vikas Samiti after fixing 50 ft road width sold residential plots beyond this road width on both sides. The local residents have built peti (apron) and temporary shed (Chhaja) on the free space available between edge of black topped or drain and their houses. The affected land i.e covered by structures is public road (within RoW); hence the affected owners will loss no land due to the sub project.
The affected owners are ready for voluntary dismantling the structures. Individual consent from them has been taken and attached in Annex-5. The site is clear and no any issue regarding land acquisition.
V-4: Gully No-4 Road (North-South section), Length = 404.75 m
Gully No-4 road passes through built up area with dense settlement. A total of 74 Peti (apron) and Chhaja (temporary shed) of the houses will be affected due to construction of the road. However, major part (structural element) of the houses will remain unaffected. This area is town planning area, where the Nagar Vikas Samiti after fixing 50 ft road width sold residential plots beyond this road width on both sides. The local residents have built peti (apron) and temporary shed (Chhaja) on the free space available between edge of black topped or drain and their houses. Hence, the affected owners will loss no land due to the sub project.
The affected owners are ready for voluntary dismantling the structures. Individual consent from them has been taken and attached in Annex-5. The site is clear and no any issue regarding land acquisition.
V-3: Gully No-3 Road (North-South section), Length=407.37m
Gully No-3 road is in city core area. It passes through built up area with dense settlement. Total 64 Peti (apron) and Chhaja (temporary shed) of the houses will be affected due to construction of the road. However, major part (structural element) of the houses will remain unaffected. This area is town planning area, where the
The affected owners are ready for voluntary donation. Individual consent from them has been taken and attached in Annex-5. The site is clear and no any issue regarding land
27
S.N. Name of Road Existing Situation Remarks
Nagar Vikas Samiti after fixing 50 ft road width sold residential plots beyond this road width on both sides. The local residents have built peti (apron) and temporary shed (Chhaja) on the free space available between edge of black topped or drain and their houses. Hence, the affected owners will loss no land due to the sub project.
acquisition.
V-2 :Gully No-2 Road(North-south section), Length = 407.92 m
Gully No-2 road is in city core area. It passes through built up area with dense settlement. Total 89 Peti (apron) and Chhaja (temporary shed) of the houses will be affected due to construction of the road. However, major part (structural element) of the houses will remain unaffected. This area is town planning area, where the Nagar Vikas Samiti after fixing 50 ft road width sold residential plots beyond this road width on both sides. The local residents have built peti (apron) and temporary shed (Chhaja) on the free space available between edge of black topped (or drain) and their houses. Hence, the affected owners will loss no land due to the sub project.
The affected owners are ready for voluntary dismantling the structures. Individual consent from them has been taken and attached in Annex-5. The site is clear and no any issue regarding land acquisition.
V-1: Gully No-1 Road (North-South section), Length = 1,102.04 m
Gully No-2 road passes through built up area with dense settlement. Total 98 Peti (apron) and Chhaja (temporary shed) of the houses will be affected due to construction of the road. However, major part (structural element) of the houses will remain unaffected. This area is town planning area, where the Nagar Vikas Samiti after fixing 50 ft road width sold residential plots beyond this road width on both sides. The local residents have built peti (apron) and temporary shed (Chhaja) on the free space available between edge of black topped (or drain) and their houses. Hence, the affected owners will loss no land due to the sub project.
The affected owners are ready for voluntary dismantling the structures. Individual consent from them has been taken and attached in Annex-5. The site is clear and no any issue regarding land acquisition.
V6: Krishi Vikash Road (Malpot/Napi-Highway), Length = 347.58 m
V6: Krishi Vikas Road starts from East-West Highway and end at Napi Karalaya. It passes through open area with some structures along the alignment. Total 4 (3 Peti (apron) & Chhaja (temporary shed) and 1 boundary wall) , but major part (structural element) of the houses will remain unaffected. Small strip of land (less than 10 %) of the affected owner will be impacted.
The affected owners are ready for voluntary donation. Individual consent from them has been taken and attached in Annex-5. The site is clear and no any issue regarding land acquisition.
H1:(East-West Gully-1), Length = 298.26 m
H1 (East-West Gully 1) is in city core (town planning area), which intersects the North-South Gully Roads. It passes through built up area with dense settlement. Total 23 Peti (apron) and Chhaja (temporary shed) of the houses will be affected due to
The affected owners are ready for voluntary dismantling the structures. Individual consent from them has been taken and
28
S.N. Name of Road Existing Situation Remarks
construction of the road. However, major part (structural element) of the houses will remain unaffected. This area is town planning area, where the Nagar Vikas Samiti after fixing 30 ft road width sold residential plots beyond this road width on both sides. The local residents have built peti (apron) and temporary shed (Chhaja) within the space of public road (30 ft) on both sides. Hence, the affected owners will loss no land due to the sub project.
attached in Annex-5. The site is clear and no any issue regarding land acquisition.
H2: (East-West Gully-2), Total Length = 297.88 m.
H2 (East-West Gully 2) is in city core (town planning area), which intersects the North-South Gully Roads. It passes through built up area with dense settlement. Total 16 Peti (apron) and Chhaja (temporary shed) of the houses will be affected due to construction of the road. However, major part (structural element) of the houses will remain unaffected. This area is town planning area, where the Nagar Vikas Samiti after fixing 30 ft road width sold residential plots beyond this road width on both sides. The local residents have built peti (apron) and temporary shed (Chhaja) within the space of public road (30 ft) on both sides. Hence, the affected owners will loss no land due to the sub project.
The affected owners are ready for voluntary donation. Individual consent from them has been taken and attached in Annex-5. The site is clear and no any issue regarding land acquisition.
H-3: Hospital road ( East-West Gully-3), Total Length = 290 m
H3 (East-West Gully 3) is in city core (town planning area), which intersects the North-South Gully Roads. It passes through built up area with dense settlement. The available width of the existing road (10 m) is sufficient for road improvement; hence no structure and land will be affected due to the sub-project.
The site is clear and no any issue regarding land acquisition.
H-4: East –West Gully-4 (Campus Road/Janiki Tole – Gully No-1) Length = 480 m
H4 (East-West Gully 4) is in city core (town planning area), which intersects the North-South Gully Roads. It passes through built up area with dense settlement. The available width of the existing road (10 m) is sufficient for road improvement; hence no structure and land will be affected due to the sub-project.
The site is clear and no any issue regarding land acquisition.
H-5: Saraswoti Tole Road-1 (East- West Section, Katan Area), Length = 300.99 m
H5 (East-West section) is in Saraswoti Tole, Katan area. Total 28 structures (23 boundary wall, 2 Peti (apron) / Chhaja and 3 shed/shutter) will be affected due to construction of the road. However, major part (structural element) of the houses will remain unaffected. The local residents have built peti (apron) and temporary shed (Chhaja) within the space of public road (30 ft) on both sides. Hence, the affected owners will loss no land due to the sub project.
The affected owners are ready for voluntary donation of affected structure. Individual consent from them has been taken and attached in Annex-5. The site is clear and no any issue regarding land acquisition.
H-6: Sarswoti Tole Road 2 (East-West
H6 (East-West section) is in Saraswoti Tole, Katan area. Total 11 boundary wall
The affected owners are ready for voluntary
29
S.N. Name of Road Existing Situation Remarks
section, Katan Area) , Total Length = 350 m
will be affected due to construction of the road. However, major part (structural element) of the houses will remain unaffected.
donation of affected structure. Individual consent from them has been taken and attached in Annex-5. The site is clear and no any issue regarding land acquisition.
H-7: Sarswati Tole Road 3 (East West section, Katan Area), Length = 392.41m
H7 (East-West section) is in Saraswoti Tole, Katan area. Total 29 structures ( 22 boundary wall and 7 hut/shed) will be affected due to construction of the road. However, major part (structural element) of the houses will remain unaffected.
The affected owners are ready for voluntary donation of affected structure. Individual consent in this regard has been taken and attached in Annex-5. The site is clear and no any issue regarding land acquisition.
H-8: Sarswati Tole Road 4 (East West section, Katan Area), Length= 372.22m
H8 (East-West section) is in Saraswoti Tole, Katan area. Total 26 structures ( 24 boundary wall and 2 hut/shed) will be affected due to construction of the road. However, major part (structural element) of the houses will remain unaffected.
The affected owners are ready for voluntary donation of affected structure/land. Individual consent in this regard has been taken and attached in Annex-5. The site is clear and no any issue regarding land acquisition.
H-9: Eye Hospital Road, East-west Section), Length=429.83 m
The road H9 known as Eye Hospital Road. The road passes through open area. Only one boundary will be affected due to construction of the road. The available width of the existing road is sufficient for improvement of the road; hence land acquisition is not required.
The affected owner is ready for voluntary donation of affected structure. Individual consent in this regard has been taken and attached in Annex-5. The site is clear and no any issue regarding land acquisition.
H-10: (Gully 1- BP Chowk - Bhagatpur Marga), Length =738.03 m
The road H 10 starts from Gully No-1 and ends at Bhagalpur Chowk. The road passes through the open area with scattered settlement. Total 13 structures (12 boundary wall and 1 peti) will be affected due to construction of the road. Major part (structural element) of the houses will remain unaffected.
The affected owners are ready for voluntary donation of affected structure/land. Individual consent in this regard has been taken and attached in Annex-5. The site is clear and no any issue regarding land acquisition.
Hotel Opera road, Length= 190 m
The Hotel Opera road under this project is in city core area. It passes through built up area. Considering the severity impact 190 m road of 15 m width will be constructed out of total 280 m length. Total 6 structures ( peti and shed/shutter) will be affected. However, major part of the house will remain unaffected.
The affected owners are ready for voluntary donation of affected structure. Individual consent in this regard has been taken and attached in Annex-5. The site is clear and no any issue regarding land acquisition.
30
S.N. Name of Road Existing Situation Remarks
Madan Chowk-Dashrath Chowk – Napi Kralaya - Bhagatpur Chowk Road, Total Length 1150m
This road under this project starts from Madan Chowk passing through Dashrath Chowk and Napi Karalaya ends at Bhagatpur Chowk. Total 6 structures will be affected due to the construction of road.
The affected owners are ready for voluntary donation of affected structure/land. Individual consent in this regard has been taken (Annex-5). The site is clear and no any issue regarding land acquisition.
Traffic Chowk- Dashrat - BP Chowk Road (Hospital link Road), Length = 596.84 m
This section of road under the project also known as hospital link road. It starts from Traffic Chowk passing through Dashrath Chowk ends at BP Chowk. The available width of the existing road (10 m) is sufficient for road improvement; hence no structure and land will be affected due to the sub-project.
The site is clear and no any issue regarding land acquisition.
Source: Field measurement and observation, 2019
C. Summary of Impact
46. Impact on Private and Public Structures: Overall 628 minor structures i.e Chhaja, Peti, boundary wall etc. of 619 private houses, 1 schools, 4 Government offices, 4 public/community structures (temple/chautara) will be affected. The road section wise number of affected structure is given in Table-7 below, and further details of loss inventory along with list of affected persons / owners are presented in Annexes-, 2 and 3 of this report. Table-7: The road section wise details of affected structures
S.N Name of the Road
Number of structures affecting Chhaja, Peti, Boundary Wall etc.
Private house School Gov.
Office
Public structure (Temple /Chautara)
Total
1 M1: (Bhasi Rautela Road) 4 1 5
2 M2: (Bhanuchowk -Bishnudham Road) 9 9
3 M3 :Shukla Phata Marga (Bhanuchowk-Madan chowk-Airport Road)
18 1 19
4 M4: (Airport-Airighat Road) 4 4
5 V5: Gully No-5 Road (Campus Road, North-South section), 103 103
6 V-4: Gully No-4 Road (North-South section) 74 74
7 V-3: Gully No-3 Road (North-South section) 64 64
8 V-2 :Gully No-2 Road(North-south section) 89 89
9 V-1: Gully No-1 Road (North-South section), 97 1 98
31
S.N Name of the Road
Number of structures affecting Chhaja, Peti, Boundary Wall etc.
Private house School Gov.
Office
Public structure (Temple /Chautara)
Total
10 V6: Krishi Vikash Road (Malpot/Napi-Highway) 3 1 4
11 H1:(East-West Gully-1) 23 23 12 H2: (East-West Gully-2) 16 16
13 H-3: Hospital road ( East-West Gully-3)
0
14 H-4: East –West Gully-4 (Campus Road/Janiki Tole – Gully No-1)
0
15 H-5: Saraswoti Tole Road-1 (East- West Section, Katan Area)
28 28
16 H-6: Sarswoti Tole Road 2 (East-West section, Katan Area) 11 11
17 H-7: Sarswati Tole Road 3 (East West section, Katan Area), 29 29
18 H-8: Sarswati Tole Road 4 (East West section, Katan Area) 26 26
19 H-9: Eye Hospital Road, East-west Section) 1 1
20 H-10: (Gully 1- BP Chowk - Bhagatpur Marga) 10 2 1 13
21 Hotel Opera road 4 2 6
22 Madan Chowk-Dashrath Chowk – Napi Kralaya - Bhagatpur Chowk Road
6 6
23 Traffic Chowk- Dashrat - BP Chowk Road (Hospital link Road),
0
Total 619 1 4 4 628Source: Field survey, 2019
47. Affected Persons: Total 3740 individuals living in 619 households were identified as affected persons due to the sub-project. Out of them 1965 (52.54 %) are male and 1777 (47.46 %) are female with sex ratio 1.11. The average household size of the affected owners is 6.25. The findings of field survey and loss inventory signify that there will be nominal economic impact without physical displacement and the affected persons would loss less than 10 % of their productive asset; hence none of them are severely affected persons. The social assessment signifies that the affected households do not fall under the below poverty line and other venerability criteria. All of them are direct beneficiaries of the sub-project and they have chosen the design option resulting partial impact on their temporary/projected structures. Based on eligibility criteria for voluntary donation as specified in CRIPPF, the affected owners are eligible for offering donation voluntarily and also are willing for voluntary donation of affected minor structures or lands located within the adopted design width. Individual consent of the affected owners in this regard has been taken and attached in Annex-5 of this report and the further detail information of affected households are given in Annexes 1,2 and 3.
32
48. During construction of roads (preparation of base course, premix and pavement) and drainages some temporary disturbances to businesses are anticipated for a few hours per 100-200 m section. However, full road closure is not anticipated and these temporary disturbances will not result in physical or restriction to access to business and resources. In order to avoid and limit the disturbance to the extent possible, consultations with stakeholders will be undertaken at different locations. Different options of avoidance /or minimization of disturbance will be discussed. Different measures will be adopted such as alternative traffic management in coordination with city traffic authority, provision of night works in high-traffic and commercial areas, avoidance of drainage construction during evening hours (5:00- 7:00 pm) when moving venders are coming to the streets and provision of walkways and metal sheets where required to maintain access to shops will ensure continued access to businesses and limited disruption to business activity. To avoid such disruptions all the construction activities will comply with a work schedule that ensures completion of particular activity on the same day. Such action shortens disruption timings of the business and vending. The construction workforce will take maximum care of the private and public structures and utility services while doing excavation works. The disturbance related to environment like, noise, dust etc. will be covered by the project specific EMP. 49. The project will also establish close coordination with the residents and business owners of the area to minimize construction related disturbances. For efficient work progress and people’s support in project activities, RPIU along with Municipality, Construction Supervision Consultant (CSC) and the contractor will disseminate information on commencement of works through public announcements, billboards/signage and other form of notice to the residents, businesses owners and tenants, and other sensitive receptors (schools, places of worship, hospitals/clinics, etc.) along construction alignment 7 days, and again 2 days, prior to commencement of works. D. Indigenous Peoples
50. According to the ADB’s safeguard policy the indigenous people safeguards are triggered if a project directly or indirectly affects the dignity, human rights, livelihood systems, or culture of indigenous peoples or affects the territories or natural or cultural resources that indigenous peoples own, use, occupy, or claim as an ancestral domain or asset. The term indigenous peoples is used in a generic sense to refer to a distinct, vulnerable, social and cultural group possessing the characteristics such as self-identification as members of distinct indigenous cultural group, geographically distinct habitats or ancestral territories; distinct customary cultural, economic, social, or political institutions and a distinct language. 51. The subproject activities are confined within a linear distance with defined width along the alignment of proposed road and drainage. The construction will be undertaken following the existing road and drainage alignment. It has been observed that the indigenous people in the subproject area share a similar economic and political system with the mainstream society. The indigenous people are not significantly different from the non-indigenous households and other local families living in the project areas in terms of livelihood patterns, and access to economic, health and educational opportunities. The indigenous people in general do not display any significant social or economic traits that
33
would distinguish them from non-indigenous people communities, except in their cultural identity and national identification as indigenous people or Janajati/Adhibasi (in Nepali language). The field observation reveals that all the settlements/clusters in Bheemdatta are heterogeneous in terms of caste/ethnicity and no specific territory of indigenous people has been observed. The lands owned or occupied by indigenous people in sub-project site are not considered as ancestral/tribal value. Individual ownership of lands has been in practice among indigenous people for many generations. Hence, it is expected that the project will have no impact on their cultural identity, survival and cultural resources. 52. The improved road services and drainage system will have overall beneficial effects. However, the improved road conditions may increase vehicle speed and requires awareness among the indigenous people about the road safety and traffic rules. With municipal facility improvements, subprojects are expected to result in improved health and quality of lives of both indigenous people and non-indigenous people. Considering the facilities proposed under this subproject, the adverse impact of the project on indigenous peoples along the road alignment is not expected. No physical displacement of indigenous people is anticipated as a result of implementation of the subprojects. On the other hands, the project will create short-term employment opportunities in infrastructure construction and maintenance where indigenous groups will be given first priority for employment. The project design has included activities, which will address requirements in behavioral changes to be habitual with improved road and traffic management system. The gender equality and social inclusion (GESI) action plan and performance-based socio-economic development program (PBSEDP) includes specific actions favorable to indigenous people to enhance beneficial impacts. Therefore, indigenous people plan is not required for this subproject.
E. Impact Category of the Subproject
53. In Bheemdatta the resettlement impacts of the proposed components are found to be minor as land acquisition and resettlement has been avoided and/or minimized to the extent possible by exploring alternative design of the subproject. Improvement of roads and drainages will be carried out avoiding realignment and widening wherever feasible. For example, project will try to limit formation width of the road within the available width of existing road in order to minimize losses of structures and land acquisition. In unavoidable circumstances, voluntary donation of affected structures for road widening works will be accepted only by following the approach of community-driven development and process as defined in the CRIPPF prepared for RUDP. Thus, the resettlement impacts will be of small scale, consistent with Category B as per SPS -2009.
34
III. SOCIO-ECONOMIC INFORMATION AND PROFILE 54. This section provides an overview of brief socio-economic information and profile of the affected households residing along the alignment of proposed road sections and the findings are based on the census survey. The census survey of the households who have permanent or temporary structures within the adopted design width was conducted in order to access the socio-economic status and magnitude of likely impacts on them. The household survey was conducted from January to February 2019 and covers the demographic and economic status of affected households. As stated in earlier section out of total 628 affected structures 619 are private houses and other 9 belong to government office/institution or public/community structures. Hence the profile provides the socio-economic information of 619 affected households.
55. Both field physical survey and household survey were carried out in order to acquire the information regarding location of house and type of loss and socio-economic status of the households. The households were interviewed using the structured questionnaire, which includes questions about family composition, age, gender, education, employment, livelihood activities, income and expenditure of household and possession of the land etc. The census for collection of socio-economic and demography data were conducted by visiting each household. The list and further detail information of the surveyed households are given in Annexes- 1and 2. 56. Demography: During the household census survey socio-economic information of 598 out of total 619 affected households was collected because 21 house owners are living in other area and could not be met during the survey. The total population of the surveyed households is 3740 with 52.54 percent male and 47.46 percent female. The average household size is 6.25 and sex ratio 1.11. The road section wise distribution of affected households and population are given in table below.
Table 8: Household and Population of Affected Households
S.N Name of Road Surveyed HH Population Average
HH Size Sex
Ratio Male Female Total 1 M1 : Bhasi- Rautela Road 4 14 9 23 5.75 1.56
2 M2 : Bhanuchowk -Bishnudham Road 9 25 26 51 5.67 0.96
3 M3: Suklaphanta Marga(Bhanuchowk-Madan chowk-Airport Road)
18 66 52 115 6.39 1.27
4 M4: Airport-Airighat Road 4 19 14 33 8.25 1.36
5 V5: Gully No-5 Road (Campus Road, North-South section) 99 314 297 611 6.17 1.06
6 V-4: Gully No-4 Road (North-South section) 72 203 200 403 5.60 1.02
7 V-3 : Gully No-3 Road (North-South Section) 62 216 193 408 6.58 1.12
8 V-2: Gully No-2 Road (North-South section) 89 285 282 568 6.38 1.01
35
S.N Name of Road Surveyed HH Population Average
HH Size Sex
Ratio Male Female Total
9 V-1: Gully No-1(Shalgadhi Road, North-South Section) 89 329 291 622 6.99 1.13
10 V6: Malpot/Napi Karalaya-E/W Highway) 3 8 8 16 5.33 1.00
11 H1: East-West Gully-1 23 76 75 150 6.52 1.01 12 H2: East-West Gully-2 16 54 50 104 6.50 1.08
13 H-3: Hospital Road (Gully 6 to Gully 1/ East-West Gully-3) 0
14 H-4: Campus Road (Janki tole) to Gully 1( East-West Gully-4) 0
15 H-5: Sarswati Tole Road 1 (East West Gully-5, Katan Area)
28 88 78 166 5.93 1.13
16 H-6:Sarswati Tole Road 2 (East West Gully-6, Katan Area)
11 34 33 67 6.09 1.03
17 H-7: Sarswati Tole Road 3 (East West Gully-7, Katan Area)
28 96 69 165 5.89 1.39
18 H-8: Sarswati Tole Road 4 (East West section, Katan Area)
24 78 55 133 5.54 1.42
19 H-9: Eye Hospital Road (East-West) 1 6 5 11 11.00 1.20
20 H-10 : Hospital Road (Gully 1 to Bhagatpur Marg) 9 23 17 40 4.44 1.35
21 Hotel Opera road, E-W) 3 10 7 17 5.67 1.43
22 Madan chowk-Dashrath Chowk - Napi - Bhagatpur Chowk Road 6 21 16 37 6.17 1.31
23 Traffic Chowk- Dashrat - BP Chowk Road 0
Total 598 1965 1777 3740 6.25 1.11 Source: Census Survey, 2019
57. Caste / Ethnicity: The project service area comprises multi caste / ethnic groups. Each caste and ethnicity is characterized by its own customs, traditions, culture and nature of occupation with which they are associated. Among the affected households, Hill Brahmin and Chhettri, comprising 95.8 percent of total families, are the most prevailing group in the service area. Janagati are the next major indigenous group with 1.94 percent , followed by Dalit group constituting 1.62 percent of total affected households. It was learnt that Brahmin and Chhettri were migrated from different hill districts of western region and settled in the project area especially after development of east-west highway and town planning in Mahendranager. The Janjati refers to the indigenous group and here basically represents Tharu community. The western Terai region including the project service area is considered as original homeland of Tharu people. Tharu are the indigenous people with
36
their own culture, social and political institutions and distinct language. Table 9: Distribution of surveyed households by Caste and Ethnicity S.N. Ethnicity / Caste No. of HH Percent
1 Brahmin /Chhettri 593 95.802 Janajati 12 1.943 Dalit 10 1.624 Muslim 1 0.165 Others (Yogi) 3 0.48
Total 619 100.00Source: Field survey, 2019
58. Family Structure: Two types of family structures were reported among the surveyed households; nuclear and joint family. A nuclear family is a family that consists only of parents and their unmarried children sharing a common kitchen. Whereas, joint family consists of grandparents, parents and their children who share a common kitchen. The finding of the household survey reveals that 54.35 percent have a nuclear family structure and 45.65 percent households have a joint family structure (Table 10). The joint family structure was reported particularly in Tharu community which has traditionally been in practice. Table 10: Surveyed households by types of family structure Family Type Number of Households Percent (%)
Nuclear family 325 54.35 Joint family 273 45.65 Total 598 100.00
Source: Field survey, 2019
59. Literacy and Education: Out of total household surveyed, 34.95 percent of household head reported that they have completed intermediate level education, 20.57 percent have secondary school level education and 32.11 percent are literate with or without formal education. Nearly 11.20 percent of them have attended higher education; whereas only 1.17 percent are illiterate who could not read and write. Table 11: Educational Status of the Head of Household Educational Status No. of HH Head Percent Illiterate 7 1.17 Literate / Elementary 192 32.11
Secondary school level 123 20.57
Intermediate level 209 34.95 Higher Education 67 11.20 Total 598 100.00
Source: Field survey, 2019
37
60. Household economy and modes of livelihood: With urbanization the economy of the area has gradually been shifted from rural agricultural economy to business and service based; hence the major sources of income for majority of the households are nonfarm activities. However, the overall livelihood strategy of the surveyed households is characterized by a mixture of farm and nonfarm activities. Farm activities are carried out for food supply, whereas other requirements of the household are fulfilled through nonfarm activities. The surveyed households are largely relying on more than one source of income for the fulfillment of their livelihood needs. Non-agriculture activities like business & jobs are the main contributors for household economy. The main source of income for a large majority of surveyed households (80.27 %) is business. Service which includes both government and private sector jobs is the primary source of income for 17.89 percent of the households, whereas agriculture is the major source of income for only 1.51 percent households. As in other part of the country remittance / foreign employment has also been playing important role in household economy of the area, which is contributing as secondary source of income for many households. Table 12: Main sources of income of the surveyed households
S.N. Occupation No. of HH Percent 1 Agriculture 9 1.51 2 Business 480 80.273 Service 107 17.894 Wage Labor 1 0.17 5 Remittance 1 0.17 6 Other 0.00
Total 598 100.00Source: Field survey, 2019
61. Income Level: It is indeed a difficult task to calculate the income and expenditure patterns of the surveyed households because generally income and expenditure data might not be very reliable as most of the respondents either grossly underestimate their income or overestimate their expenditure patterns. Besides, the surveyed households do not keep records of their family’s income and expenditures. Even though the surveyed households own lands and are involved in farm activities, agriculture is not a significant contributor to the household economy. The major part of the household income is derived from nonfarm activities. The surveyed household’s monthly average income is estimated as NRs 53123 with an average per capita income of NRs 114606 per person per year. This is significantly higher income as compared with per capita NRs 19,262 person/year estimated by the Nepal Living Standards Survey 2010/2011 and Nepal Rastra Bank’s annual inflation rate adjusted per capita income NRs 31,134 per person per annum in survey year 2019. Further details of occupation, monthly income and per capita income of individual affected household are presented in Annex-2, which signifies that none of the affected households fall under below poverty line.
38
Table 13: Average household income and per capita income
S.N Name of Road No. of
HH
Average Monthly
Income (Rs)
Average Per Capita
Income (Rs)1 M1 : Bhasi- Rautela Road 4 26250 547832 M2 : Bhanuchowk -Bishnudham Road 9 43889 92941
3 M3: Suklaphanta Marga(Bhanuchowk-Madan Chowk-Airport Road) 18 48944 91930
4 M4: Airport-Airighat Road 4 345250 502182
5 V5: Gully No-5 Road (Campus Road, North-South section) 99 51515 100164
6 V-4: Gully No-4 Road (North-South section) 72 55556 1191077 V-3 : Gully No-3 Road (North-South Section) 62 56855 1036768 V-2: Gully No-2 Road (North-South section) 89 57618 108338
9 V-1: Gully No-1(Shalgadhi Road, North-South Section) 89 57674 99029
10 V6: Malpot/Napi Karalaya-E/W Highway) 3 23333 5250011 H1: East-West Gully-1 23 60217 11080012 H2: East-West Gully-2 16 58313 107654
13 H-3: Hospital Road (Gully 6 to Gully 1/ East-West Gully-3)
14 H-4: Campus Road (Janki tole) to Gully 1( East-West Gully-4)
15 H-5: Sarswati Tole Road 1 (East West Gully-5, Katan Area) 28 47036 95205
16 H-6:Sarswati Tole Road 2 (East West Gully-6, Katan Area) 11 39091 77015
17 H-7: Sarswati Tole Road 3 (East West Gully-7, Katan Area) 28 40357 82182
18 H-8: Sarswati Tole Road 4 (East West section, Katan Area) 24 52708 114135
19 H-9: Eye Hospital Road (East-West) 1 80000 87273
20 H-10 : Hospital Road (Gully 1 to Bhagatpur Marg) 9 34444 93000
21 Hotel Opera road, E-W) 3 38333 81176
22 Madan chowk-Dashrath Chowk - Napi - Bhagatpur Chowk Road 6 35000 68108
23 Traffic Chowk- Dashrat - BP Chowk Road Total 598 55005 105539
Source: Field survey, 2019
39
62. Vulnerability and Differential Impacts Assessment: The vulnerable are individuals or groups who may experience differential adverse impacts from the proposed project more severely than dominant population because of their unique and inherit socio-economic characteristics. Those households falling below poverty line, the landless, household head with disability, single women headed households, marginalized Dalits, and endangered indigenous peoples (Mukta Kamaiya) are considered here as vulnerable groups. Per capita income NRs 31,134 in 2019 (socio economic survey year) is considered here as poverty threshold, which is derived from per capita income NRs 19,262 person/year estimated by the Nepal Living Standards Survey 2010/2011 adjusting Nepal Rastra Bank’s annual inflation rate from 2012 to 2019. The socio-economic census survey of affected households signifies that per capita income of affected individual household is higher than NRs 31,134 per person per year which details are shown in Annex-2 of this report; hence none of the affected household falls under below poverty line. 63. The Janjati refers to the indigenous group and here basically represents the Tharu community. The western Terai region is considered as original homeland of Tharu people. Tharu are the indigenous people with their own culture, social and political institutions and distinct language. Among the Tharu people Mukta Kamaiya (freed labor) could be considered as vulnerable group. The census survey of affected households signifies that among the total affected households there are 12 of indigenous people including Tharu. However, none of them were reported as Mukta Kamaiya. Out of total affected households 10 are reported as Dalit. All of them are involving in business and their income level is satisfactory with per capita income above NRs. 31,134. Either Peti (apron), temporary chhaja (shed) or boundary wall will be affected without impacting the major part (i.e structural element) of the house. Such affected minor structures are not contributing for household's income; thus there would not be economic and physical displacement due to dismantling the affected part. Regarding land loss the affected area i.e area covered by affected structure is public land (within RoW of existing road); hence the affected owners would loss no land. 64. It has been observed that the Indigenous and Dalit people in the subproject area share a similar economic and political system with the mainstream society. The indigenous and Dalit people are not significantly different from the non-indigenous households and other local families living in the project areas in terms of livelihood patterns, and access to economic, health and educational opportunities. The indigenous people in general do not display any significant social or economic traits that would distinguish them from non-indigenous people communities. Therefore, considering the economic status and nature or scale of impacts on Indigenous and Delit groups differential impact on their livelihood may not applicable for this sub-project.
40
IV. INFORMATION DISCLOSURE, CONSULTATION AND PARTICIPATION
A. Community & Stakeholder Consultations
65. Field consultations were undertaken especially during household survey at different locations, in particular with affected persons, and municipality representatives. More than 600 persons were consulted during census survey of affected households and the list of them is given in Annex-1. In addition meetings / interactions with stakeholders including affected persons were conducted in different locations and dates. Summary such consultations is given in Table- 14 below and minutes are attached in Annex-4. 66. The general objective of the consultations was to share project related information with project affected local communities and stakeholders as well as to assess the project’s likely impacts (both positive and negative) on them. These consultations organized during household survey also fulfilled dual objectives to assess and acquire socio-economic information required for this RP as well as to disseminate information on the likely impacts of the project. The consultations were also instrumental to understand the perceptions of affected persons, local residents, expectations and feedback of affected people. Most of such consultations were carried out along the alignment of the proposed section of road during socio-economic survey. Different design options viz. road width recommended by PPTA and municipality / MTPM, within the existing width, including no project choice were shared with the affected local people and communities so that they can have informed choice of the project design. Among the different alternatives discussed they agreed to adopt design width based on the actual available width so that the major construction activities could be carried out without impacting the major part of the structures. The detailed design of the road sections have been finalized based on the alternative agreed to avoid loss and with minimum impact. 67. The major concerns and perceptions of the participants about the subproject during the consultations are as follows:
• Most of the consulted persons particularly affected persons were positive towards the project and they even willing for voluntary demolish the minor structures and donate land if required for the road and drainage improvement.
• Some likely affected people who have houses within the municipal RoW worried about the possibilities of demolishing of their houses and also raised queries regarding the provision of compensation .
• Few of them worried about losing their small strip of lands along the alignment of the proposed road.
• Some participants expressed positive opinions about the proposed subproject and encouraged municipality to start the proposed subproject as soon as possible.
• In general the landowners along the road alignment were willing to give their land if required for road extension for the benefit of the community welfare.
41
Table-14: Summary of Consultation
S.N Date Location No. of Participants
Participants Topics Discussed Issues Raised Action Taken
1
2077-3-12 (26 Jun 2020)
Ward Nos-17,16 &12
14 (m-12, F-2)
Ward Chairperson, Ward members and affected persons
Ward /Tole level discussion regarding road width and impact on structures; consent and commitment of beneficiaries/affected owners for construction of road; formation of committee.
Queries on compensation and benefit for affected persons. Issues of land loss and structures
Width of road has been reduced and finalized based on actual available RoW of existing roads to avoid or mitigate impacts
2
2077-3-11 (25 Jun 2020)
Ward No-1
12 (m-10, F-2)
Ward Chairperson, Ward members and affected persons
Ward/Tole level discussion regarding road width and impact on structures; consent and commitment of beneficiaries/affected owners for construction of road; formation of committee.
. concern of land loss and structures Queries on compensation and benefit for affected persons.
Width of road has been reduced and finalized based on actual available RoW of existing roads to avoid or mitigate impacts
3
2077-3-12 (26 Jun 2020)
Ward No-18
13 (m-10, F-2)
Ward Chairperson, Ward members and affected persons
Ward level discussion regarding road width and impact on structures; consent and commitment of beneficiaries/affected owners for construction of road
. concern of land loss and structures
Width of road has been reduced and finalized based on actual available RoW of existing roads to avoid or mitigate impacts
4
2077-3-12 (26 Jun 2020)
Ward Nos-15 & 4
12 (m-11, F-1)
Ward Chairperson, Ward members and affected persons
Ward level discussion regarding road width and impact on structures; consent and commitment of beneficiaries/affected owners for construction of road
. concern of land loss and structures Queries on compensation and benefit for affected persons.
Width of road has been reduced and finalized based on actual available RoW of existing roads to avoid or mitigate impacts,
5
2076-1-17 BS (30 April 2019)
Bheemdatta Municipality
14 (M-13, F-1)
Municipality (Mayor, Chief Admin Officer, Engineer), RPIU (Deputy Project Manager), PMC expert, DSC experts
Road prioritization and selection of road to be constructed under phase-1, request for implementation of surveyed roads not included in phase-I, regarding individual consent of affected households for dismantling of affected structures and nomination of third party.
Budget constraint and delay in design works Maintenance /protection of public/ cultural property to be done during construction
Road prioritization based on available budget For protection / maintenance of public/cultural property budget has been included in BoQ.
42
S.N Date Location No. of Participants
Participants Topics Discussed Issues Raised Action Taken
6
2075-9-18 (2 Jan 2019)
Bheemdatta Municipality
21 (M-18, F-3)
Municipality (Mayor, Deputy Mayor, Chief Admin Officer, Engineer, Ward Chairpersons), RPIU (Deputy Project Manager), DSC experts and beneficiaries
Road prioritization based on budget and severity of impact and recommendation for design and estimate of prioritized roads, request for phase II roads design and estimate.
7
2075-8-8 (24 Nov 2018)
Ward No-3
44 (m-39, F-5)
Ward Chairperson, Ward members, secretary and affected persons
Ward level discussion regarding road width and impact on structures; consent and commitment of beneficiaries/affected owners for construction of road; formation of road width demarcation committee.
Queries on compensation and benefit for affected persons. Issues of land loss and structures
Width of road has been reduced and finalized based on actual available RoW of existing roads to avoid or mitigate impacts,
8
2075-4-30 ( 15 Aug 2018)
Ward No-6
78 (m-68, F-10)
Ward Chairperson, Ward members, Municipality officials and affected persons
Ward level discussion regarding road width, impact on structures and commitment of beneficiaries/affected owners for construction of road; formation of road width demarcation committee.
Issues of land loss and structures. Queries on compensation and benefit for affected persons.
Width of road has been reduced and finalized based on actual available RoW of existing roads
9
2075-5-6 (22 Aug 2018)
Ward No-6
11 (M-9, F-2)
Ward Chairperson, Ward members, member of road measurement/ demarcation committee.
Discussion regarding road width, affected structures and formation of road measurement/width demarcation committee.
10
2075-1-3 (6 Apr 2018)
Bheemdatta Municipality
5 (M-3, F-2)
Mayor, Deputy Mayor, Member, Engineer
Topographical survey of recommended roads
11
2075-3-24 (8 July 2018)
Bheemdatta Municipality
5 (M-3, F-2)
Mayor, Deputy Mayor, Member, Engineer
Road selection and topographical survey of recommended roads
B. Information Disclosure and Dissemination
68. Information disclosure and public consultation are important and necessary during project preparation as well as implementation. A summary of RP will be made accessible to the affected people and stakeholders through the respective Ward Offices, Bheemdatta Municipality Office, R-PIU Office.
43
69. Similarly, during project implementation, meaningful consultation, including with project affected persons as described in the CRIPPF will be continued. These enable project affected people, IPs, vulnerable groups, and other stakeholders to participate in and contribute to the project planning and implementation, and thereby help minimize adverse impacts and maximize the benefits. The information to be disclosed will include, information related to works progress, potential temporary disruptions to access during construction, grievance redress process, employment and other benefits available under the project and procedures for access etc. The mode of disclosure could vary, but may include booklets, newspapers, the internet, and community meetings related to the project and subprojects. Potential disclosure places could include: Ward Office, Municipality Office, DUDBC Divisional Office/RPIU, NGO, club etc. C. Future Consultations and Participation
70. In order to keep more transparency in planning and for further active involvement of APs and other stakeholders, the subproject information will be disseminated through disclosure of safeguard planning documents. The EA will provide relevant information (final RP endorsed by the EA, an updated RP, if required) in a timely manner, in an accessible place.
71. For effective implementation of the RP, additional consultative meetings with the affected persons will be carried out during project implementation. Such consultations will be carried out by the social development officer at R-PIU & social safeguards focal person at the municipality with the support of Social Expert under the PMC and DSC. Based on stakeholder analysis and consultation, following consultation and communication plan has been proposed for this sub-project.
Table-15 : Consultation and Communication Plan Activity Target
Stakeholders Type of Participation
Objective Responsible Time Frame
1. Project orientation focusing on construction modality for local community groups targeting affected persons (one time in each affected ward)
At least 650 community members focusing affected persons (619HHs) in each project ward of the municipality. The members to include head of the affected families, FHHs, TLO representatives and community leaders and at least 33% women.
Information sharing Consultation Shared responsibilities and expectations
Through presentations and discussion introduce the project construction modality, impact and benefits
Gather concerns and views related to project design and implementation
Explain grievance mechanism Explain ADB’s and the government’s
safeguards measures; grievance redress mechanism to the affected persons
Explain initiatives to promote GESI under the project; increased representation in decision-making and employment opportunities
Build awareness on the need to protect and keep clean public spaces and entities
PMC, DSC, IDC
Just before start of civil work
44
Activity Target Stakeholders
Type of Participation
Objective Responsible Time Frame
2. Project orientation workshop for contractors
Management staff, field supervisors and laborers.
Information sharing
Orient on safeguard provisions Sensitize on avoiding public
nuisances, minimizing public inconveniences, and avoiding disruption to the public activities/mobility
Awareness creation on health and hygiene, HIV/AIDS, other communicable diseases and core labor standards and gender issues
Best construction practices for safety during construction activities and EMP compliance
PMC, IDC, DSC
Upon contractor mobiliza-tion
3. Consultation on project‘s resettlement plan and framework (minimum 3 meetings) with identified APs
Affected persons Information sharing Consultation Negotiation
Introduce the project’s safeguard provision
Mitigate potential conflict Solicit the views of affected persons on
resettlement and compensation Agree on resettlement processes,
location, timing and compensation Disseminate/share about the likely
impacts of the subproject, summary of the RP including entitlements, grievance redress mechanism and contact information
R-PIU/PISU,PMC DSC, IDC
Years 1-3
45
V. GRIEVANCE REDRESS MECHANISMS 72. A project municipality specific grievance redress mechanism (GRM) has been established to hear grievances and concern raised from affected persons and project beneficiaries. According to PAM and CRIPPF each project municipality has to establish two tiers of grievance redress mechanism (GRM) at the local (project municipality) & central (PCO) level respectively.
73. Municipality level Grievance Redress Committee (GRC): As mentioned in CRIPPF the GRC has been formed comprising five members headed by mayor of Municipality. Members of the GRC include RPIU chief, representatives of affected persons with one male and one female (a representative of Indigenous people, in case of indigenous people related issues), social safeguard focal person. The social safeguard focal person representing project municipality is the member secretary of the GRC. The GRC will meet as needed to determine the merit of each grievance, and resolve it within 7 days of receiving the complaint. The committee thus appointed should be sanctioned by the municipal board. The responsibilities of the GRC at municipality will be:
to conduct subproject level public awareness campaign regarding grievance redress mechanism of the project. The social safeguards experts of the PMC will support the GRC by preparing and providing information/awareness material etc. to conduct the awareness campaign. The campaign will ensure participation of poor and vulnerable groups in the awareness campaign. The campaigns also cover information on entitlements policy provisions and their application.
to hear complaints and grievances at local level. The local people can approach the committee with their grievances related to the project which will be registered, categorized and discussed in the committee with the aim of amicable settlement. It is expected that the committee will provide an accessible forum for receiving and facilitating resolution grievances related to the project and grievances will be redressed within one week from the date of lodging the complaints. The social safeguard focal person representing project municipality in each municipality assisted by the DSC social expert will be responsible for processing and placing all papers before the GRC, recording decisions, issuing minutes of the meetings and taking follow up action to see that formal orders are issued and the decisions carried out. Any unresolved or major issues at municipality level will be referred to the PCO level GRC for resolution.
74. A municipal level GRC has been formed in Bheemdatta Municipality on 2074/10/14 BS (2018 Jan 28). The composition of the GRC is in line with PAM and CRIPPF; headed by Mayor of the municipality. The committee consists of following members: I. Chairperson : Mr. Surendra Bista , Mayor II. Member : Project Manager, RPIU/DUDBC Dhangadhi, Kailali III. Member : to be nominated , representing Affected Person IV. Member : to be nominated , representing Affected Person V. Member Secretary: Mr. Hari Singh Dhami, Social Development Unit, Bheemdatta Municipality.
75. The PCO Level GRC: A GRC has been formed at PCO under the chair of Project Director (PD) comprising of Deputy Project Director and chief of social development unit of MoUD as members. The Social Development Expert of Project
46
Management Consultant (PMC) under PCO is acting as member secretary of the GRC and responsible for processing and placing all papers before the GRC, recording decisions, issuing minutes of the meetings and taking follow up action to see that formal orders are issued and the decisions carried out. 76. The unresolved or major issues forwarded by the Municipality level GRC will be reviewed at PCO level GRC for final solution. Decision must be made within 15 days of receipt of complaint at this level. The PCO level GRC shall refer the complaints registered at the PCO to the concerned municipality level GRC for initial hearing within 7 days of registration. 77. Despite the project GRM, an aggrieved person shall have access to the country's legal system at any stage, and accessing the country's legal system can run parallel to accessing the GRM and is not dependent on the negative outcome of the GRM. 78. People who are, or may in the future be, adversely affected by the project and not satisfied with the established GRM may submit complaints to ADB’s Accountability Mechanism3. The Accountability Mechanism provides an independent forum and process whereby people adversely affected by ADB-assisted projects can voice, and seek a resolution of their problems, as well as report alleged violations of ADB’s operational policies and procedures. Before submitting a complaint to the Accountability Mechanism, affected people should make a good faith effort to solve their problems by working with the concerned ADB operations department. Only after doing that, and if they are still dissatisfied, should they approach the Accountability Mechanism. 3For further information see: http://www.adb.org/Accountability-Mechanism/default.asp
47
VI. LEGAL FRAMEWORK
79. In principle, Nepal has an established policy framework to implement social safeguard measures in development activities. The safeguard policies and regulation related to infrastructure development mainly reflected in the constitution, policies and regulations related to land acquisition and compensation; Indigenous Peoples (IPs); good governance, social accountability and public consultation.
A. The Constitution 80. The Constitution of Republic of Nepal (2015), Article 25 (1) guarantees the fundamental right of a citizen, i.e. right to acquire, own, sell and dispose of the property. Article 25 (2) describe that the state cannot acquire the property of any person except in case of public interest. Article 25 (3) also state that compensation shall be provided for any loss of individual property for public interest.
B. Land Acquisition Act, 2034 (1977) 81. The Land Acquisition Act (1977) specifies the procedures for land acquisition and compensation. The Act empowers the government to acquire any land for public interest or for the execution of any development works. There is a provision of Compensation Determination Committee (CDC) under the leadership of Chief District Officer (CDO), which will fix the rate of compensation for the affected property. The other members in the committee are the Chief of Land Revenue Officer, representative from District Development Committee (now District Coordination Committee), concerned Project Director/Manager. The committee can also invite representatives from among the affected persons, representative from affected Rural/Municipality. 82. The basic function of the CDC is to review the verification of lands to be acquired, review and determine the compensation rate, identify the proper owners, distribution of compensation and address the issues related to land acquisition and compensation distribution. District Administrative Office (DAO) under CDO is also responsible to notify the public regarding the details of the land area, structure affected and other assets affected in the concerned Rural/Municipality for project purposes. The typical process of land acquisition under this act is indicated in Table 16. Table 16: Process for land Acquisition as per Land Acquisition Act
S.N. Steps outlined in the Land Acquisition Act 1 Sectorial agency decides to execute a development project at a certain location 2 Sectorial agency requests the Government to acquire land specifying objectives and
committing payments of compensation and other expenses 3 GON approves and orders the initiation process and CDC is formed 4 Public notification is made at public places in the project area, Rural / Municipality
offices and to the affected households 5 Necessary preliminary survey including boundary demarcation, agricultural
production valuation and social census of affected families takes place 6 Land Revenue Office report on the area and location of land to be acquired
including likely compensation and amount of loss
48
7 The local officer (CDO) issues notices including purpose of acquisition and detail of land to be acquired
8 Land transactions are banned within the notified area 9 Owner can file complaints within 7 days through the local officer 10 Resolution of grievance within 15 days of complaint 11 Acquisition of land and payment of compensation Source: Land Acquisition Act, 2034(1977)
C. Land Reform Act 2021 (1964)
83. Another key legislation in Nepal related to land acquisition is the Land Reform Act 2021 (1964). The Land Reform Act (1964) is relevant in the compensation distribution modality. It specifies the compensation entitlements for the registered tenant. Where the tenancy right is legally established, the owner and tenant each will be entitled to 50% of the total compensation amount. Section 42 of the Land Reform Act states that Guthi (religious/trust) land acquired for development work must be replaced with another land.
D. Local Government Operation Act 2074
84. The new Local Government Operation Act enacted in 2017 has superseded all provisions of Local Self Governance Act 1999 in line with state restructuring of Nepal. The local government as Municipalities and Rural Municipalities has definite roles and rights in public land conservation and ownership as depicted in Clause 11 (g). Clause 11 (n-4) articulates the roles of local government in facilitation of land acquisition, compensation determination and distribution for public purpose. Similarly, the sub clause (n-5 and 6) articulates the roles of local government in facilitation and coordination for determination of land ownership and cadastral mapping. Other role in land ownership certificate distribution is also defined in these sub clauses.
85. The Local Government Operation Act 2074 Chapter -7 has building construction and road related provision. The clause 45 (1) states that Municipality or Rural Municipality may declare (fix) RoW of road within its area. According to clause (2) the municipality or Rural Municipality should obey the norms / standard of RoW of national or provincial level road. The clause 45(3) has given the power to local government over RoW and states that Municipality or Rural Municipality can order anytime to demolish or remove structures erected within RoW as mentioned in clause 45 (1 & 2). Further the clause 45(4) states that in case any person, organization or institution do not demolish or remove structures as ordered clause 45 (3), Municipality or Rural Municipality can demolish or remove such structures itself and the demolition or removal cost will be charged from concerned person, organization or institution.
86. Moreover, the clause 45 (5) states that after the enactment of this Act, once the RoW has been declared as per sub-section 1; if the RoW is changed again - then in such case if any land or structure falls under the new RoW (extended portion), then compensation shall be provided for acquisition of such land, or for demolition or/and removal of such structures. The Clause 27 in the Chapter 7 has provision of prohibition on construction of building without obtaining approval from concerned Municipality or Rural Municipality. House map registration and approval is mandatory for house construction. Clause 27 (3) mentions that fragmentation or plotting of land for housing purpose should not be done without prior approval from Municipality or Rural Municipality.
49
E. Land Acquisition, Rehabilitation and Resettlement Policy (LARRP), 2015
87. The Government of Nepal has formulated Land Acquisition, Rehabilitation and Resettlement Policy 2071 (2015) to facilitate the land acquisition process for infrastructure project. The policy outlines the need to conduct an economic and social impact assessment (SIA) of the development project, which was not a requirement under the Land Acquisition Act 1977. Based on this assessment, projects will be categorized as high, medium and low-risk5. The policy also provisioned for the project affected families to be entitled to compensation if works like installation of transmission, telephone and underground drinking water pipe lines affect livelihood. And in case the projects affect yields of registered commercial crop, fruit or flower producers, compensation equivalent to five years of revenue must be given in cash. 88. The policy adds that all expenses related to land acquisition, compensation and the implementation of resettlement and rehabilitation plans should be considered as project cost and interest should be paid on compensation amount depending on the days it took to release funds to those affected by the project. The interest calculation begins from the day a formal decision was taken to operate the project, says the policy. 89. The compensation amount for those affected by the project will be fixed by a five- member compensation committee formed under the chief district officer. The committee can form a technical team to determine the compensation amount. This team should derive the compensation amount as close as possible to the minimum market rate by working closely with members of families that are likely to be displaced. 90. Those not satisfied with land acquisition, resettlement and rehabilitation processes can lodge complaints at a body formed at the project office and complaint hearing offices at district and regional levels. If verdict issued by the regional level complaint hearing office is also deemed unsatisfactory, the person can knock on the doors of court.
5 High-risk projects refer to those which displace 50 or more households in the mountainous region, 75 or more households in the hilly region and 100 or more households in the Tarai. Medium-risk projects, on the other hand, are those that force relocation of less than 50 households in the mountainous region, less than 75 households in the hilly region and less than 100 households in the Tarai. Likewise, low-risk projects refer to those which cause productive property to shrink by up to 10 per cent.
50
91. The Land Acquisition, Resettlement and Rehabilitation Policy for the Infrastructure Development Projects has following key provisions regarding land acquisition:
Recognizes the need of resettlement and rehabilitation plan to ensure the livelihood of the project affected persons or households at least above the pre- project conditions;
Emphasize that the project development agency conduct meaningful consultation with the project affected persons including all vulnerable groups viz women, children, indigenous/Janajati groups, disabled, helpless and persons having no legal rights on the operated land;
Requires to accomplish compensation payment, resettlement and rehabilitation efforts to the project affected person/households including non- title holders;
Emphasize land acquisition through negotiation with the project affected person/households through transparent, free, fair and justifiable process;
Requires land based compensation and resettlement to persons/households who lose all the property or whose livelihood is agriculture based;
Requires relocation and resettlement of the affected persons/households close to the current place of residence until and otherwise he/she willingly prefer to relocate him/herself;
Requires inclusive programs for the enhancement of their socio- economic development of disadvantageous groups such as facility less groups (Dalit, Indigenous or Janajati groups and single women etc.);
Requires compensation of the built properties including resettlement and rehabilitation benefits for persons/households who do not have land or legal right for the currently operated land;
Requires access on project benefit (share allocations) to the affected persons/households for projects where return on investment is potential;
Requires provisioning of subsidized rates to the project affected persons/households for projects providing services;
Requires following additional project assistance on the top of the compensation and resettlement to the physically displaced groups.
1. Residential facilities 2. Goods transportation assistance 3. Relocation assistance 4. Relocation for business assistance 5. House Rental assistance
Additional assistance as recommended by plan to seriously project affected households and vulnerable groups (Dalit, Janajati or marginalized Indigenous, single women, helpless, disabled, senior citizen etc.)
Employment opportunity and livelihood restoration to the seriously project affected households and Vulnerable groups (Dalit, Janajati or marginalized Indigenous, single women, helpless, disabled, senior citizen etc.) based on their skills and capabilities.
Requires project development agency to ensure the allocation of resources required for resettlement /rehabilitation and livelihood restoration of the project affected persons/households.
51
F. Policies and Act Related to Indigenous Peoples 92. Nepal does not have a standalone policy on Indigenous Peoples to safeguard them from specific policy, planning initiatives and development projects. The Constitution of Nepal 2072 (2015), NFDIN Act 2002, Local Government Operation guideline, 2074, Forest Act (1993) and Forest Regulation (1995) and periodic Five Year Plans have been placed significant emphasis on delivering basic services to the indigenous people. Besides, there are some provisions for the protection and promotion of Janajatis' traditional knowledge and cultural heritage. 93. The Constitution of Nepal 2072 (2015), Article 18, Right to Equality, states that all citizens shall be equal before law. No person shall be denied the equal protection of law. However, the article also mentioned that nothing shall be deemed to bar the making of special provisions by law for the protection, empowerment or advancement of the women lagging behind socially and culturally, Dalits, Adibasi, Madhesi, Tharus, Muslims, oppressed class, backward communities, minorities, marginalized groups, peasants, laborers, youths, children, senior citizens, sexual minorities, persons with disability, pregnant, incapacitated and the helpless persons, and of the citizens who belong to backward regions and financially deprived citizens including the Khas Arya. 94. Specific policy initiatives for the welfare and advancement of IPs (Adivasi/Janajati) were initiated in 1997, when a National Committee for Development of Nationalities (NCDN) was set up. In 2002, the Nepal Parliament passed a bill for the establishment of an autonomous foundation named “National Foundation for Upliftment / Development of Indigenous Nationalities (NFDIN),” which came into existence in 2003 replacing the NCDN. The NFDIN Act 2002 established the first comprehensive policy and institutional framework pertaining to Adivasis/Janajatis. The act defines indigenous groups or Adivasi / Janajati in Nepali as "a group or community having its own territory, own mother tongue, traditional rites and customs, distinct cultural identity, distinct social structure and written or unwritten history". The government, through NFDIN, has identified and officially recognized 59 such indigenous communities. This list was updated in 2009 to include 81 groups for official recognition but yet to be approved by the GON. 95. The Local Government Operation Act, 2074 commits municipalities for the promotion, preservation, and protection of language, religion, culture of indigenous people and their welfare in the municipal area. The Act empowers municipalities to formulate policy / regulation, by-laws and guideline regarding project implementation, monitoring and evaluation within their own jurisdiction. The act also emphasis on the formulation, implementation and monitoring of the plan required for economic, social, environmental, cultural, technology and infrastructure development. Under the jurisdiction of provincial and state law, the act has given the authority to municipality formulate urban development plan and policy, law and standard related to building construction as well as planning, study, project identification, implementation and monitoring. The Act provides municipalities to follow planned development programs and prioritized programs that can increase productivity, contribute to upgrading living standards, and generate income and employment opportunities for indigenous people and other vulnerable groups. The Act also provisions on social security and poverty alleviation and focuses on formulation and execution of target group plan and policy benefiting to women and disadvantaged groups.
52
96. These constitutional, legal and policy provisions are supplemented with the provisions under the United Nations Declaration on the Rights of Indigenous Peoples (2007) and International Labor Organization (ILO) Convention (169), 1989 in 2007 since Nepal is a signatory to these international legal instruments. The ILO Convention no. 169 of 1989 is the most comprehensive legally binding treaty on the rights of indigenous peoples. The Convention includes provisions on cultural integrity, land and resource rights and non-discrimination, and instructs states to consult indigenous peoples in all decisions affecting them. Articles 1-4 of the United Nations Declaration on the Rights of Indigenous Peoples (2007) ensures the individual and collective rights of indigenous peoples, as well as their rights to culture, identity, language, employment, health, education and other issues while implementing any development activities in the traditional territory of the IP. G. ADB’s Safeguard Policy Statement 2009
97. According to the ADB Safeguard Policy Statement (2009), the basic objectives of the safeguards requirements are to avoid involuntary resettlement wherever possible; to minimize involuntary resettlement by exploring project and design alternatives; to enhance, or at least restore, the livelihoods of all affected persons in real terms relative to pre-project levels; and to improve the standards of living of the affected poor and other vulnerable groups. ADB’s main safeguard policy guidelines are:
Involuntary Resettlement (IR) should be avoided wherever possible; Where IR is unavoidable, minimize involuntary resettlement by exploring project
and design alternatives; Enhance or at least restore the livelihoods of all affected persons in real terms
relative to pre-project levels; Improve the standards of living of the affected poor and other vulnerable groups; Gender analysis is required to identify related resettlement impacts and risks; Resettlement Plans (RP) should be prepared in full consultation with affected
persons (APs), host communities, and concerned nongovernment organizations (NGOs) including disclosure of the RP and project related information;
Preference will be given to land-based resettlement for affected persons whose livelihoods are land-based. However, if the land is not the preferred option or the land is not available at reasonable price, the Displaced Person (DPs) will be provided opportunities for employment, or self-employment, in addition to the reasonable cash compensation for land and other assets lost;
Cash compensations for the loss of structures, other assets and incomes should be based on full replacement cost;
Absence of formal legal title to land or non-recognized or recognizable claims to such land by the affected persons should not be a bar to compensation;
The rate of compensation for land, structures and other assets should be calculated at full replacement cost based on fair market value; transaction cost; interest accrued; transitional and restoration cost, and other applicable payments, if any.
All compensation payments and related activities must be completed prior to the commencement of the civil work;
Special attention to be paid to the needs of vulnerable groups especially those below the poverty line, the landless, the elderly, women and children and indigenous people and those without legal title to land.
53
H. ADB’s Policy on Indigenous Peoples (SPS 2009)
98. It states that the borrower/client will ensure (i) that affected Indigenous Peoples receive culturally appropriate social and economic benefits; and (ii) that when potential adverse impacts on Indigenous Peoples are identified, these will be avoided to the maximum extent possible. Where this avoidance is proven to be impossible, based on meaningful consultation with indigenous communities, the Indigenous Peoples Plan6 will outline measures to minimize, mitigate, and compensate for the adverse impacts.
I. Measures for Bridging Gaps between ADB and GON Policies
99. The Table 17 summarizes the main differences between ADB and Government of Nepal’s legislation in terms of involuntary resettlement and the measures included in this resettlement plan to bridge the gaps.
Table 17: Differences between ADB Policy and GON Legal Framework and measures recommended for bridging gaps Key issues GON Regulation ADB SPS Measures
recommended in the RIPPF
Loss of more than 10% of the total landholdings and income
Do not consider thepercentage loss of income or total land holdings The LARRP (2015) has provision of social impact assessment ( 7.2.1)
Income restoration programs such as training and other measures to restore and improve the standard of living of the affected households
Provision has been madeto provide skill training and income generating measures in theEntitlement Matrix
Squatters/illegal occupants/nontitle land users
Do not consider squatters/ encroachers/ nontitle land users for compensation The LARRP (2015) has provision of compensation for affected non-land assets and assistance for rehabilitation ( 7.3.8)
Non-title holders are not entitled for the compensation of land but for replacement cost of assets on land and resettlement assistance business and other assistance
Provision has been made to provide compensation for the affected structures /houses/ business in the EM
Valuation of affected land, houses & other structures and trees
Compensation rate is determined by CDC, consisting of (i) CDO (ii) representative from DDC (iii) Chief of Land Revenue Office (iv)
All compensation is based on the principle of replacement cost
Provision has been made for the replacement value for the loss of land, houses/structures. APs can take salvagedmaterials. CDC will make final
6 If the impact on indigenous people is significant an Indigenous People’s Plan would be prepared for this project with a set out actions to addressing how IPs will benefit from this project and negative impacts will be avoided/mitigated. However, the impact on IP is very limited and no separate IPP is not justified at the stage of the project preparation and detained design.
54
Project Manager
The LARRP (2015) has provision of following scientific procedures while determining the compensation for the lands acquired and lossesincurred by individuals/families so that minimum market-value of the property must be maintained and the compensation should be given to the affected families within the given time (7.3.2).
decision on the rates in the presence of representativesfrom DPs, Municipality, civilsociety, who will attend themeeting as an observer(details are provided inSection VIII)
Other assistance For relocation of the houses
No provisions in LAA(1977) The LARRP (2015) hasprovision that projectproponent will ensure the resources required torehabilitate the livelihoodof the affected individuals/families (7.1.3)
All the eligible DPsincluding tenants, employees are entitled to receive financial assistance to cover physical andeconomical displacement
Provision has been madefor the transitionalallowances, transportallowances and one timefinancial assistance to thetenants, employees
Vulnerable groups No Provisions in LAA (1977) The LARRP (2015) hasprovision of additionalassistance and inclusive programs targeting these groups to uplift their socio-economic status (7.2.7).
Focused on the poor and vulnerable group to avoid future impoverishment and create new opportunities
Provision has been made for income restoration programs and other financial assistance
Voluntary land donation
No provision in LAA (1977) The LARRP (2015) hasprovision of Third-partyvalidation of consultationrelated to land donationsis required
The borrower is required to engage an independentthird-party to document thenegotiation and settlementprocesses to openlyaddress the risks ofasymmetry of informationand bargaining power ofthe parties involved insuch transactions.
A mechanism will be established ensuring transparent process is followed, and there is no coercion for donation of land and building demolition. The verification will be done by an independent third party.
55
VII. ENTITLEMENT, ASSISTANCE AND BENEFITS
A. Entitlement Policy
100. An entitlement matrix has been given in Table 17, which summarizes the main types of losses and corresponding entitlements proposed under this subproject. The entitlements listed in the entitlement matrix are based on standards and practices adopted by GON for similar projects funded by ADB. Principally the key entitlements include voluntary donation of partial loss of land and structures at minor repair cost and provisional exemption of tax and fees. 101. Voluntary Donation of Land & Structures: As provisioned in CRIPPF for RUDP the project accepts self-declaration of voluntary demolition of building and clearance of municipal right of way. Such offer would be considered only if (i) the voluntary offer is for small strips of land7, (ii) it will not result in permanent and significant loss/impact on income and livelihood of the land donor or causing any third party displacement8, (iii) road improvements and other project activities will directly benefit the owners, (iv) meaningful consultation was carried out to finalize the design, (v) land owners agree and their voluntary offer without coercion is documented, and (vi) the donor is not categorized as poor or vulnerable. 102. The affected person have chosen the design option resulting partial loss of structures and lands without affecting main part (i.e structural element) of their house and they agreed for offering donation voluntary. As stated in entitlement matrix there is no compensation for the donated land and self-demolition of affected structures. However, there are some provisions to mitigate the impacts such as provision of exemption of registration fees or other municipal charges, repair allowances to structure owner based on per unit rate (sq.m) as decided by municipal board, exemption of 3 years’ housing tax (only for demolished building), waiver of building permission fees and taxes to rebuild affected house. 103. The house owners who have built the projected structures within the municipal RoW as well as design width are mostly involving in business operating in their main building and the likely impacts due to demolition of the extended structures without disturbing the main buildings/structures are very marginal (based on percentage of loss and minimum size of remaining assets). The dismantling of extended structures such as chhaja (temporary shed in front part of the house), house peti (apron), boundary wall etc. do not result in displacement of households or cause loss of household’s incomes and livelihood. On the other hands, the households making voluntary donations are the direct beneficiaries of the project and they have chosen the proposed project design based on their informed choice among the various design options prepared by the project.
7 For example, less than 10% of the total area and not affecting the main structure 8 The donated land/assets should be free of third party impacts (current user of the land/ assets, either by
formal or informal arrangement). If there will be third party impacts, some assistance need to be provided to them.
56
104. While preparing individual voluntary donation consent paper, a mechanism has been established to ensure transparent process was followed and coercion was not used during accepting the voluntary demolition of building and clearance of municipal right of way. The whole process of offering voluntary donation of structures or lands has been verified and validated by R-PIU/PISU, Municipality with the help of Citizen Forum Bheemdatta as an independent third party prior to contract award. The individual consent papers in this regard are attached in Annex-5 for reference.
B. Entitlement Matrix
105. An entitlement matrix has been given in Table 18, which summarizes the main types of losses and corresponding entitlements proposed under this subproject. The entitlements listed in the entitlement matrix are based on standards and practices adopted by GON for similar projects funded by ADB. Principally the key entitlements include voluntary donation of partial loss of land and structures at minor repair cost and provisional exemption of tax and fees.
Table 18: Entitlement Matrix
Type of Loss Scope Who is entitled Entitlements
Responsible for the Delivery of the
Entitlement
Comments
A1. Loss of Lands/Impact on Lands 1. Self-declaration
of Voluntary demolition of building and clearance of municipal Right of Way (ROW)
Loss of land and structures on the donated land
Land and structure owner.
No compensation for the donated land and self-demolition of affected structures.
Exemption of any transfer costs, registration fees or other municipal charges.
Repair allowances to structure owner based on per unit rate (sft) as decided by municipal board.
Exemption of 3 years’ housing tax (only for demolished building).
Waiver of building permission fees and taxes to rebuild affected house.
The EA (concerned municipality & PIU)
1.1 Voluntary donor households. Donation is accepted only if the donor: Is project beneficiary and fully consulted and
informed about their rights and design options; Doesn’t fall below poverty line after land
donation; Donating up to 10% land holding without or no
impact on structural element of the building; Is unforced or freely willing to donate, Has chosen the design option for road widening. 1.2 Donation should be verified by PCO/RPIU to ensure integrity and impartiality. 1.3 The entitlement may not be applicable if the building owner has built the structure violating approved design of the building and building construction certificate issued by the municipality. 1.4 The municipality will provide all entitlement for any building constructed prior to declaration of RoW of particular road sections.
A2. Temporary Impacts on Land 2. Temporary
impacts during construction
2.1 Damage to adjacent parcel of land due to movement of machinery and spoil generated during construction 2.2 Land used by the contractor for labor
Land and business owner
15 days prior notice will be given to protect crops or business Reinstatement of the damaged property to the original form. Cash or kind compensation at replacement value by contractor, if the loss is non-revocable (that cannot be restored or reestablished). Lease fee at
Contractor Design supervision consultant will verify the loss and facilitate to negotiate the rates. Contractor to negotiate a contract agreement on a rental rate with the owner or user of the land that will be temporarily used for construction activities. Project and the contractor to ensure that persons other than the owner affected as a result of temporary acquisition are also compensated for loss of at least 3 months income.
58
Type of Loss Scope Who is entitled Entitlements
Responsible for the Delivery of the
Entitlement
Comments
camp, construction yard and stores.
replacement value will be provided to the land or building owner or user of the land or building if rented out. Land should be returned to the owner/user at the end of temporary acquisition period after fully restoring it to its original condition or improved as agreed with the AP.
B. Loss of Residential and Commercial Structures 3. Loss of
residential and commercial structures
Marginal impact (i.e., unaffected portion of the house is still viable for use and no relocation required)
3.1 Owners of the structures with or without acceptable proof of ownership over the land; with or without building permit
Cash compensation at replacement cost for the affected portion. Repair allowance equivalent to not less than 20% of replacement cost of the affected portion, or equivalent to the actual cost of repair. The affected households have right to take salvaged materials without deduction to compensation.
EA, Concerned municipality, PIU, and CDC
This entitlement only applies if someone denied for voluntary donation and impact on major structure due to construction activities with genuine causes verified by a technical team of DSC/PIU. Payment will be made, in full, to the AP before taking possession of the structure. Technical team of (IA or municipality or DSC consultant) will assess and confirm viability of use of the building and concurred with by the affected household.
59
Type of Loss Scope Who is entitled Entitlements
Responsible for the Delivery of the
Entitlement
Comments
Severe impact (i.e., house is no longer viable for continued use and the entire structure is to be acquired
3.2 Owners of the structures with or without acceptable proof of ownership over the land; with or without building permit
Cash compensation at replacement cost for the entire structure.
Materials transport allowance equivalent to 1.5 month minimum wage for the household if relocating in the same ward/village; 2 month minimum wage for the household if relocating elsewhere in the municipality/district.
One time assistance allowance of 1 month minimum wage for the household for those who will move to another plot of land and 1/2 month minimum wage for the household for those who will move within the same plot of land.
The affected household have right to take salvaged materials without deduction to compensation
EA, Concerned municipality, PIU, and CDC
This entitlement only applies when loss of residential/ commercial structures happened while demolishing extended slab/structure and compound wall with genuine causes verified by a technical team of DSC/PIU Payment will be made, in full, to the AP before taking possession of the structure. Technical team of (IA or municipality or DSC consultant) will assess and confirm viability of use of the building and concurred with by the affected household.
60
Type of Loss Scope Who is entitled Entitlements
Responsible for the Delivery of the
Entitlement
Comments
C. Loss of Income Generating Sources and Assets 4. Loss of income
of small vendors
Business affected temporarily during project construction
4.1 Non-mobile business operators on footpaths of road extension/upgrade projects
Affected Venders will be notified at least 1 month in advance of the construction date by the Project. One time assistance allowance of 15 days minimum wage for the vender. A lump sum shifting allowance (transport plus load un loading charges) of NRs 2500.00 will be paid to affected vender/shop/business owner
Supervision consultant/contractor to deliver short term compensation for loss of income.
The EA and project supervision consultant will ensure payment is made prior to physical displacement.
D. Loss of common property resources 5. Loss of cultural
and community structures/ public facilities/community forests
Common property resources such as community forests, monasteries, temples, irrigation cannel, water supply pipes, electricity poles etc. affected by the Project.
5.1 Affected community/ Institution/user group responsible for the administration of the property.
Replacement or restoration of the affected community facilities (including temples, shrines, public water stand posts etc.) in consultation with the affected community. Or cash compensation for restoring the affected cultural/community structures to the recognized institution/ patron/ custodian of the affected structure.
Design supervision consultant/contractor to deliver replacement/ restoration of structure/facility
The EA, and design supervision consultant
61
Type of Loss Scope Who is entitled Entitlements
Responsible for the Delivery of the
Entitlement
Comments
Project Assistance to move the structure to a new location
F. Other unanticipated impacts 6. Unanticipated
adverse impacts due to project intervention or associated activity.
Unanticipated involuntary and other impacts of the subprojects will be documented during the implementation phase and mitigated based on provision made in the CRIPPF. The EA and project implementation authorities will finalize the entitlements in line with GoN legal provisions and ADB’s SPS, 2009.
DSC= Design Supervision Consultants, CDC= Compensation Determination Committee, PIU= Project Implementation Unit.
62
VIII. RESETTLEMENT BUDGET AND FINANCING PLAN 106. This chapter provides the details of cost estimates regarding the resettlement activities described in preceding chapters under the following headings:
A. Dismantling, Rehabilitation and Minor Maintenance Cost for Affected Structures Within Design Width: 107. Cost for dismantling, rehabilitation and minor maintenance of private structures within the adopted design width has been provisioned and included in BoQ. The projected structures of private houses such as Chhaja (temporary shed in front part of the house), house peti (apron) and other minor structures including compound wall, temporary shed ect. need to be dismantled for site clearance during construction. Transportation cost for disposal of unusable materials of demolished structures has also been included. Total NRs 36,072,854 has been proposed for dismantling and minor maintenance of affected private structures and included in BoQ. B. Reinstatement / Maintenance / Protection of the Affected Public / Community Properties (Chautara, Temple etc.):
108. During socio-economic survey some public / community properties were identified located within RoW that will be affected during site clearance for construction. The cost has been provisioned for reinstatement / maintenance / protection of affected public / community properties such as temple, compound wall of public school, Government office etc. The Entitlement Matrix (EM:5.1) states the replacement or restoration of the affected community facilities (including temples, shrines, public water stand posts etc.) in consultation with the affected community. Total cost of NRs 2,481,521 has been proposed for this and included in BoQ.
C. Rehabilitation Allowance for Affected Venders 109. A rehabilitation allowance has been provisioned to cover loss of income or livelihood strategy due to temporary disturbance to income generating activities of mobile hawkers/vendors during Drainage and Road Improvement works. The entitlement Matrix (EM: 4.1) proposes one time assistance allowance of 15 days minimum wage(as per established rate of Kanchanpur district) plus a lump sum shifting allowance (transport plus load un loading charges) of NRs 2500.00 for the affected venders. The contractors will enumerate and Municipality / PISU will verify the exact numbers of the affected venders during construction period. The verified affected venders will be compensated using budget allocated either under provisional sum of the subproject or using contingency budget heading of the RP. D. RP Implementation and Management Cost: 110. A number of RP implementation activities need to be carried out at the subproject level by R-PIU in collaboration with PISU. Some of such activities include: (i) public consultation, and information dissemination, (ii) organizing stakeholder meetings, and implementing the decision, field verification, and updating RP, (iii) organizing and mobilizing local grievance redress committee meetings so on. In order to ensure such expenses, RP implementation cost also been calculated and incorporated in the resettlement budget as given in Table-18
63
E. Contingencies: 111. A contingency amount including price contingency, material, work change and other as per GoN rule (25%) of the total cost estimated for implementation of the resettlement activities is proposed to cover cost of likelihood expenses including cost of some private structures that might be affected during the implementation of road and drainage improvement works. F. Total Cost Estimate
112. The tentative total cost estimate for implementation of resettlement activities is as follows: Table 19: Budgetary Cost Estimate for Implementation of Resettlement Activities
S.N Description of the Task Quantity Rate (NRs) Estimated Cost (NRs)
1
Dismantling, Rehabilitation and Minor Maintenance of Affected Structures Within RoW/adopted design width.
As per BoQ As per BoQ 36,072,854
2
Reinstatement / Maintenance / Protection of the Affected Public / Community Properties (Chautara, Temple etc.)
As per BoQ As per BoQ 2,481,521
3
Information dissemination about the project, organizing stakeholder meeting and follow up activities.
6 25,000 150,000
4 Organizing GRC meetings and follow-up activities. 15 5,000 75,000
5
Mobilization of Surveyor/Amin / Malpot for Field Verification plus social safeguard related orientation/training
LS 300,000 300,000
6 Monitoring LS 150,000 150,000 Total(1-6) - 39,229,375
13% VAT 5,099,819 Sub-total including VAT 44,329,194 25% contingency 11,082,298 Total 55,411,492
G. Financing Plan
113. All costs related to RP implementation would be borne by the Government. The EA will ensure that adequate funds are delivered on time to the R-PIU for timely implementation of resettlement activities.
64
IX. INSTITUTIONAL ARRANGEMENTS
114. The Ministry of Urban Development (MoUD) through its Department of Urban Development and Building Construction (DUDBC) is the Executing Agency (EA) of the project. EA has established a Project Coordination Office (PCO) headed by a Project Director (PD). The PCO is staffed with a social development expert under project management consultant to confirm smooth implementation of the RP and take corrective actions if necessary. The R-PIU established in DUDBC divisional office Kailali, along with the project municipalities (Dhangadhi, Godawari, Suklaphanta and Bheemdatta) will be the Implementing Agencies (IAs) for the subprojects. The project municipalities have also established a project implementation support unit (PISU) in each municipality. The R-PIU headed by project manager and staffed with a social development officer / sociologist is responsible for the preparation of the SIA and the subsequent Resettlement and IPP Planning documents. Besides preparation of RAPs and related documents, R-PIU will also be responsible for the public participation process as outlined above, and for the grievance redress mechanism
115. A Design Supervision Consultant (DSC) is engaged to support the R-PIU in all its activities; and will make sure that the relevant conditions formulated in the CRIPPF and RP will be included in the scheme construction Tender Documents, in order to allow the bidders to include these measures and conditions in their bids. The DSC has qualified personnel to carry out this task. The DSC will assist with any rehabilitation and resettlement to ensure that affected persons are aware of their entitlements and to ensure conformity with the project Resettlement Plan.
116. The R-PIU and PISU in the municipality will implement resettlement activities. The Project Management Consultant (PMC) under PCO will also monitor the smooth implementation of RP. The R-PIU and PISU will work closely with the DSC- Resettlement Specialist /consultant during detailed design and construction phase to verify APs and corresponding mitigation measures and assistance proposed in this RP. The R-PIU and PISU will continue further consultation with APs during project implementation and solicit views regarding compensation, and relocation options. The PCO will verify the implementation of resettlement requirements and confirm whether APs received entitlements as per the RP prior to the award of civil work contracts. The municipal project implementation support unit (PISU) will facilitate linking APs to relevant government programs related to social and economic rehabilitation. 117. The R-PIU will submit quarterly progress reports on RP implementation to the PCO, who will then review and take corrective actions if necessary. The PCO with assistance from the PMC consultants will consolidate their reports into semiannual monitoring reports and submit to ADB. These reports are to describe the progress of the implementation of resettlement activities and any compliance issues and corrective actions. In cases where the municipality and plot owner negotiate directly, the DSC-consultant and R-PIU will verify the satisfaction of the plot owner with the agreed compensation amount, if applicable. The R- PIU and PISU with support of social development expert of DSC are to ensure all the activities specified in RP are implemented and ensure all entitlements are paid accordingly before commencement of civil works.
65
118. Civil works contracts and contractors: RP and EMP are to be included in bidding and contract documents and verified by the R-PIU and PCO. The contractor will be required to designate an Environment, Health and Safety (EHS) supervisor to ensure implementation of social safeguard provisions in this RP during civil works, who will also have the responsibility for communication with the public under the guidance of R- PIU/PSIU and grievance registration. Contractors are to carry out all mitigation and monitoring measures outlined in their contract.
119. The PCO and R-PIU will ensure that bidding and contract documents include specific provisions requiring contractors to comply with: (i) all applicable labor laws and core labor standards on (a) prohibition of child labor as defined in national legislation for construction and maintenance activities; (b) equal pay for equal work of equal value regardless of gender, ethnicity, or caste; and (c) elimination of forced labor; and with (ii) the requirement to disseminate information on sexually transmitted diseases, including HIV/AIDS, to employees and local communities surrounding the project sites.
66
X IMPLEMENTATION SCHEDULE
120. The project will be implemented over five years (2016-2021). Construction activities are expected to start from the first quarter of 2020 and be completed at the end of 2021. RUDP-CRIPPF (2016) and ADB SPS (2009) require that consent of affected persons for voluntary donation of affected land and structures within the municipal RoW to be provided before the loss is incurred. Accordingly the consents of affected owners in this regard have been collected before construction and attached in this RP, and other entitlements will commence as soon as the RP has been approved by ADB. All land required will be provided free of encumbrances to the contractor prior to handing over of subproject site and the start of civil works. APs will be given sufficient notice to vacate their property before civil works begins.
Table-20: Time Bound Schedule for RP Implementation S.N RP Implementation
Activities 2018 2019 2020 2021
1Q
2Q
3Q
4Q
1Q
2Q
3Q
4Q
1Q
2Q
3Q
4Q
1Q
2Q
3Q
4Q
1 Topographic Survey of proposed road section
2 Loss Inventory preparation based on topographic survey
3 Project Screening and Categorization
4 Field measurement and Socio-economic survey of Affected Households
5 Inventory of Affected Households
6 Draft RP preparation
7 Final RP preparation
8 Approval of RP by ADB 9 Disclosure of RP and
Distribution of RP summary
10 Consent / Agreement with Affected households for voluntary donation of affected land and structure
11 Establish Grievance Redress Mechanism (GRM) and form Grievance Redress Committee (GRC)
12 Contract Bidding 13 Award for civil works
contracts
14 RP implementation, monitoring and Reporting
15 Internal monitoring by RPIU/PCO
67
XI. MONITORING AND REPORTING
121. Need for Monitoring: Monitoring is a major part of the resettlement management system to ensure its goals are met. The RP implementation activities will be closely monitored internally by the R-PIU, PISU and PCO. This will involve: (i) administrative monitoring to ensure that implementation is on schedule and problems are dealt with on a timely basis; (ii) socio-economic monitoring during and after any resettlement impact utilizing baseline information from sub-project preparation; (iii) overall monitoring to assess AP status; and (iv) preparation of quarterly progress reports to be submitted to PCO by the R-PIU, reporting actual achievements against the targets fixed and reasons for shortfalls, if any.
122. Internal Monitoring: The DUDBC through its PCO will be responsible for internal monitoring. The R-PIU will provide necessary oversight and monitor the RP implementation at the ground level and submit quarterly progress reports to PCO. Internal monitoring will ensure all land acquisition and resettlements activities are implemented according to the approved Resettlement Plans are in accordance with this Resettlement Framework.
123. The R-PIU in coordination with the PISU and technical support of social development expert of DSC will maintain a record of all transactions in their resettlement database, followed by entitlement records signed by AP and survey based monitoring of resettlement / land acquisition progress on a monthly basis. Monitoring will ensure that:
All internal training of relevant safeguards staff occurred; Verification that there are no outstanding or unresolved land acquisition
issues with respect to the project and that property valuation and economic rehabilitation has been carried out in accordance with the provisions of the plan;
Information campaign and consultation has been carried out with APs; Status of land acquisition and payments on land compensation; Value of entitlement received is equal to that of original structure or land
acquired; Effective utilization of entitlements received; Compensation for affected structures and other assets; Relocation of APs; if applicable; Payments for loss of income; That all economic rehabilitation measures are implemented, as approved; Effective operation of both the Grievance Committees; Funds for implementing land acquisition and economic rehabilitation
activities are available in a timely manner, are sufficient for the purposes, and are spent in accordance with the plan.
124. PCO through R-PIU and PISU will also be responsible for carrying out field level monitoring through:
Review of census information for all APs; Consultation and informal interviews with APs; In-depth case studies; Informal sample survey of APs; Key informant interviews; and Community public meetings.
68
125. Monitoring Indicators: The most crucial components/indicators to be monitored are specific contents of the activities and entitlement matrix. Some of the indicative monitoring indicators are as following:
1. Delivery of entitlement
Entitlements disbursed, compared with number and category of losses set out in the entitlement matrix.
Disbursements against timelines. Timely disbursements of the agreed transport costs, relocation costs, income
restoration support, and any resettlement allowances, according to schedule.
2. Consultation and Grievances
Consultations organized as scheduled including meetings, groups, and community discussions.
Knowledge of entitlements by the displaced persons. Use of the grievance redresses mechanism by the displaced persons. Information on the resolution of the grievances. Implementation of special measures for Indigenous Peoples.
3. Communications and Participation
Number of general meetings (for both men and women). Percentage of women out of total participants. Number of meetings exclusively with women. Number of meetings exclusively with vulnerable groups. Number of meetings exclusively with IPs.
4. Budget and Time Frame
Land acquisition and resettlement staff appointed and mobilized on schedule for
the field and office work. Capacity building and training activities completed on schedule. Achieving resettlement implementation activities against the agreed
implementation plan. Funds allocation for resettlement to resettlement agencies on time. Receipt of scheduled funds by resettlement offices. Funds disbursement according to the resettlement plan.
69
5. Livelihood and Income Restoration
Progress on income and livelihood restoration activities being implemented as set out in the income restoration plan
Number of affected persons who received vocational training (women, men, and vulnerable groups).
Types of training and number of participants in each. Number and percentage of affected persons covered under livelihood
programs (women, men, and vulnerable groups). Number of affected persons who have restored their income and livelihood
patterns (women, men, and vulnerable groups). Number of new employment activities created by the project.
6. Benefit Monitoring
Noticeable changes in patterns of occupation, production, and
resource use compared to the pre-project situation. Noticeable changes in income and expenditure patterns compared to the
pre-project situation. Changes in cost of living compared to the pre-project situation. Changes in key social and cultural parameters relating to living standards. Changes occurred for IPs and vulnerable groups. Benefiting from the project by the affected persons
126. Reporting Requirement: The R-PIU will submit quarterly9 progress reports on resettlement activities and submit to PCO to the PCO, who will then review and take corrective actions if necessary. The R-PIU will prepare quarterly progress reports. The PCO with assistance from the PMC consultants will consolidate their reports into semiannual monitoring and submit to ADB. These reports are to describe the progress of the implementation of resettlement activities and any compliance issues and corrective actions. Reports to ADB should clarify whether or not resettlement goals have been achieved, more importantly analysis of whether livelihoods and living standards have been restored/enhanced (especially for vulnerable APs) along with appropriate recommendations for improvement need to include in monitoring reports. Any problems or issues identified are followed-up (including recommendation of mitigation measures and supplementary budget); and learning from such issues must be recorded which would help to deal with issues such as these more effectively.
9DSC to submit monthly reports to R-PIU; R-PIU submits quarterly reports to PCO; PCO submits semi-annual reports to ADB.
Annex ‐ Page 1
ANNEX-1 List of Consulted Persons and Inventory of Loss
S.N Name of HH Head Side Available ROW
Required Width
Chainage
Type of Structure Affected Part Individual
Consent
M1 (Bhasi- Rautela Road), Design Width=12 m, Total Length=3641 m, Phase I Construction Length=560 m (Chainage 0 +00 - 0+560 m)
1 Chanak Lal Chaudhary R 5 1 0+010 BM House 1.0m peti+ T.Chhaja Yes
2 Asha Chaudhary R 4.5 1.5 0+060 BM House 1.50m peti+T.Chhaja Yes
3 Shiva Mandir R 2.5 3.5 0+250 BM House 2.5mBW+1m T.Store
4 Hira Devi Thagunna R 4.6 1.4 0+362 BM House 1.40m BW Yes
5 Ghungra Khatri R 4.7 1.3 0+420 BM House 1.30m BW Yes M2 (Bhanuchowk -Bishnudham Road), Design Width= 10m, Total Length=4885 m, Phase I Construction Length= 210 m (Chainage 0+00 - 0+210)
1 Binod Rawal L 4.6 0.4 0+015 RCC House 0.4m Chhaja Yes
2 Bhupendra Rawal R 4.3 0.7 0+015 BM House 0.7mT-Chhja Yes
3 Debu Devi Bista L 4.6 0.4 0+031 BM House 0.4m peti Yes
4 Kalyan Singh Thakuriya R 4.6 0.4 0+031 BM House 0.4m peti
5 Madhavi Bhatta L 4.4 0.6 0+077 RCC House 0.6m Chhaja+Peti Yes
6 Deependra Rawal R 4.5 0.5 0+145 RCC House 0.5m peti Yes
7 Prem Thalal R 4.4 0.6 0+145 RCC House 0.6m Chhaja+Peti
8 Navaraj Khadka R 4.5 0.5 0+166 RCC House 0.5m Peti Yes9 Kishor Pandey L 4.6 0.4 0+189 RCC House 0.4m Peti
M3: Suklaphanta Marga(Bhanuchowk-Madan chowk-Airport Road) , Design Width=34.5m for 540.39 m and 12 m for 3216.09 m, Total Length=3756.48 m, Phase I construction Length=3756.48m
1 D.D Pandey R 5 1 1+515 BM House 1m Peti+T-Chhaja Yes
2 Sabitri Rawat L 5.4 0.6 1+530 RCC House 0.60m Chhaja Yes
3 Kalawati Chand R 5.4 0.6 1+555 BM House 0.60nm Peti Yes
4 Kamala Devi Dhami R 4 2 1+572 BM House 2mPeti Yes
5 Gopal Chand L 4.75 1.25 1+572 RCC House 1.25m Wall+2.6m BW Yes
6 Dabala Dhami R 5.1 0.9 1+600 BM House 1.9BW+0.9m Shed
7 Kalu Chand L 4.6 1.4 1+635 RCC House 1.4m BW Yes
8 Rami Chand L 5.3 0.7 1+655 BM House 0.70mBW Yes
9 Gangadatt Joshi L 4.5 1.5 1+710 BM House 1.5mBW Yes
10 Ran Bdr. Chand L 5.1 0.9 1+669 BM House 0.9m BW
11 Arjun Chand L 4.3 1.7 1+935 BM House 1.7m BW
12 Nglasaini Mandir L 5.3 0.7 2+020 BM House 0.7m Kitchen hut
13 Puskar Bdr. Chand L 5.5 0.5 2+520 BM House 0.50m BW Yes
14 Lal Singh Bista R 5.6 0.4 2+602 BM House 0.40m BW Yes
15 Bahadur Nath L 5.2 0.8 2+668 BM House 0.80m Shed
16 Dhan Bdr. Bista R 5.4 0.6 3+470 BM House 0.60m BW Yes
17 Bhim Bdr. Chand R 5.2 0.8 3+550 BM House 0.80m BW Yes
Annex ‐ Page 2
S.N Name of HH Head Side Available ROW
Required Width
Chainage
Type of Structure Affected Part Individual
Consent
18 Kausilla Khatri R 5.3 0.7 3+560 BM House 0.70m BW Yes
19 Mohan Dev Bhatta R 5 1 3+600 RCC House 1m Septic Tank YesM4: Airport-Airighat Road, Design Width= 12 m, Total Length = 2313 m, Phase I Construction Length = 652 m (Chainage 0+00 - 0+652 as per social survey)
1 Mohan Singh Bhjandari L 5.5 0.95 0+005 BM 0.95 m Shed Yes
2 Haridatt Joshi L 3.8 2.2 0+090 BM 2.2m BW Yes
3 Man Bdr. Chand R 3.7 2.3 0+418 BM House 2.3m BW Yes
4 Bishna Devi Dhami L 3.3 2.7 0+418 BM House 2.7m BW Yes V5: Gully No-5 Road (Campus Road, North-South section), Design Width = 12 m, Total Length = 674.77 m, Phase I Construction Length = 674.77m
1 Deepak Rawat R 4.5 1.5 0+000 RCC House 1.50m Peti+T-Chhaja
2 Tej Singh K.C R 4.5 1.5 0+013 RCC House 1.50m Peti+ T-Chhaja Yes
3 Hiikmat Thaurathi R 4.5 1.5 0+023 RCC House 1.50m Peti+ T-Chhaja Yes
4 Padam Bharati R 4.5 1.5 0+029 RCC House 1.50m Peti+ T-Chhaja Yes
5 Tek Raj Bharati R 4.5 1.5 0+032 RCC House 1.50m Peti+ T-Chhaja Yes
6 Ghanashyam Joshi R 4.5 1.5 0+035 RCC House 1.50m Peti+ T-Chhaja Yes
7 Raju Chand R 4.5 1.5 0+046 RCC House 1.50m Peti+ T-Chhaja Yes
8 Lal Bdr. Chand R 4.5 1.5 0+050 RCC House 1.50m Peti+ T-Chhaja
9 Bharat Chand R 4.5 1.5 0+055 RCC House 1.50m Peti+ T-Chhaja
10 Megh Raj Bohora R 4.5 1.5 0+077 RCC House 1.50m Peti+ T-Chhaja Yes
11 Ganesh Chand R 4.5 1.5 0+085 RCC House 1.50m Peti
12 Chhetrapal Mehera R 4.5 1.5 0+088 RCC House 1.50m Peti+ T-Chhaja Yes
13 Madhav Parshad Bhatta R 4.5 1.5 0+089 RCC House 1.50m Peti Yes
14 Uddhav Dev Joshi R 4.5 1.5 0+100 RCC House 1.50m Peti+ T-Chhaja Yes
15 Chandra Dev Joshi R 4.5 1.5 0+104 RCC House 1.50m Peti+ T-Chhaja Yes
16 Mahadev Bohora R 4.5 1.5 0+108 RCC House 1.50m Peti+ T-Chhaja Yes
17 Laxmi Devi Joshi R 4.5 1.5 0+115 RCC House 1.50m Peti+ T-Chhaja Yes
18 Prem parkash Pathak R 4.5 1.5 0+122 RCC House 1.50m Peti+ T-Chhaja
19 Bijaya Nanda Joshi R 4.5 1.5 0+125 RCC House 1.50m Peti+ T-Chhaja Yes
20 Hansa Devi Chand R 4.5 1.5 0+128 RCC House 1.50m Peti
21 Lok Raj Bharati R 4.5 1.5 0+163 RCC House 1.50m Peti Yes
22 Devraj Mishra R 4.5 1.5 0+150 RCC House 1.50m Peti+ T-Chhaja Yes
23 Keshav Raj Joshi R 4.5 1.5 0+162 RCC House 1.50m Peti+ T-Chhaja Yes
24 Dilananda Giri R 4.5 1.5 0+175 RCC House 1.50m Peti+ T-Chhaja Yes
25 Bisna Devi Palpali R 4.5 1.5 0+183 RCC House 1.50m Peti+ T-Chhaja Yes
26 Khem palpali R 4.5 1.5 0+185 RCC House 1.50m Peti+ T-Chhaja Yes
27 Raghubir Bhatta R 4.5 1.5 0+188 RCC House 1.50m Peti+ T-Chhaja
28 Chandra Devi Rawal R 4.5 1.5 0+193 RCC House 1.50m Peti+ T-Chhaja Yes
Annex ‐ Page 3
S.N Name of HH Head Side Available ROW
Required Width
Chainage
Type of Structure Affected Part Individual
Consent
29 Sushila Vevi Rawal R 4.5 1.5 0+200 RCC House 1.50m Peti+ T-Chhaja Yes
30 santos Aitwal R 4.5 1.5 0+206 RCC House 1.50m Peti+ T-Chhaja Yes
31 Parbesh Partap Aitwal R 4.5 1.5 0+216 RCC House 1.50m Peti+ T-Chhaja Yes
32 Bhupendra Aitwal R 4.5 1.5 0+226 RCC House 1.50m Peti+ T-Chhaja Yes
33 Gyanendra Pd. Joshi R 4.5 1.5 0+250 RCC House 1.50m Peti+ T-Chhaja Yes
34 Mahesh Parshad Joshi R 4.5 1.5 0+256 RCC House 1.50m Peti+ T-Chhaja Yes
35 Ganesh Joshi R 4.5 1.5 0+260 RCC House 1.50m Peti+ T-Chhaja Yes
36 Tribhuwan Kumar Bhatta R 4.5 1.5 0+263 RCC House 1.50m Peti+ T-Chhaja Yes
37 Gunakar Bhatta R 4.5 1.5 0+267 RCC House 1.50m Peti+ T-Chhaja Yes
38 Hari Parshad pandey R 4.5 1.5 0+274 RCC House 1.50m Peti+ T-Chhaja Yes
39 Uma Chand R 4.5 1.5 0+278 RCC House 1.50m Peti+ T-Chhaja Yes
40 Kedar Nath Pandey R 4.5 1.5 0+286 RCC House 1.50m Peti+ T-Chhaja Yes
41 Krishna Parshad Aryal R 4.6 1.4 0+304 RCC House 1.40m Peti+T-Chhaja Yes
42 Laxmi Devi Aryal R 4.5 1.4 0+308 RCC House 1.40m Peti+T-Chhaja Yes
43 Gopal Sing Bohora R 4.5 1.4 0+317 RCC House 1.40m Peti Yes
44 Suraj Kharel R 4.5 1.4 0+323 RCC House 1.40m Peti+T-Chhaja Yes
45 Gyan Parshad Dumre R 4.5 1.4 0+329 RCC House 1.40m Peti+T-Chhaja Yes
46 Parbatman Khanal R 4.5 1.4 0+339 RCC House 1.40m Peti+T-Chhaja Yes
47 Tika Devi Kadel R 4.5 1.4 0+349 RCC House 1.40m Peti+T-Chhaja Yes
48 Duhurba Parshad Aryal R 4.5 1.4 0+357 RCC House 1.40m Peti+T-Chhaja Yes
49 Khagimaya Bhandari R 4.5 1.4 0+360 RCC House 1.40m Peti+T-Chhaja Yes
50 Chandra Bdr. Malla R 5 1 0+364 RCC House 1.00m Peti+ T-Chhaja Yes
51 Harka Bdr. Malla R 5 1 0+370 RCC House 1.00m Peti+ T-Chhaja Yes
52 Gopal Datt Joshi R 5 1 0+390 RCC House 1.00m Peti+ T-Chhaja Yes
53 Saraswati Rawal L 4.5 1.5 0+000 RCC House 1.50m Peti+ T-Chhaja
54 Upendr Bdr. Khadka L 4.5 1.5 0+004 RCC House 1.50m Peti+ T-Chhaja Yes
55 Jayaraj Saran Bhatta L 4.5 1.5 0+008 RCC House 1.50m Peti+ T-Chhaja Yes
56 Dinesh Chandra Bhatta L 4.5 1.5 0+011 RCC House 1.50m Peti+ T-Chhaja Yes
57 Devraj Saran Bhatta L 4.5 1.5 0+022 RCC House 1.50m Peti+ T-Chhaja Yes
58 Manoj Gupta L 4.5 1.5 0+028 RCC House 1.50m Peti+ T-Chhaja Yes
59 Dev Raj Panta L 4.5 1.5 0+034 RCC House 1.50m Peti+ T-Chhaja Yes
60 Sivraj saran Bhatta L 4.5 1.5 0+040 RCC House 1.50m Peti+ T-Chhaja
61 Gyanendra Bdr. Shah L 4.5 1.5 0+055 RCC House 1.50m Peti+ T-Chhaja
62 Sambhu Bharati L 4.5 1.5 0+070 RCC House 1.50m Peti+ T-Chhaja Yes
63 Kalawati Joshi L 4.5 1.5 0+075 RCC House 1.50m Peti+ T-Chhaja Yes
64 Dan Bdr. Kunuwar L 4.5 1.5 0+080 RCC House 1.50m Peti+ T-Chhaja
65 Bhakta Joshi L 4.5 1.5 0+084 RCC House 1.50m Peti+ T-Chhaja
Annex ‐ Page 4
S.N Name of HH Head Side Available ROW
Required Width
Chainage
Type of Structure Affected Part Individual
Consent
66 Hari Shngh Bista L 4.5 1.5 0+091 RCC House 1.50m Peti+ T-Chhaja Yes
67 Janki Raiswal L 4.5 1.5 0+095 RCC House 1.50m Peti+ T-Chhaja
68 Parbati Chataut L 4.5 1.5 0+098 RCC House 1.50m Peti+ T-Chhaja Yes
69 Tarani Datt Chataut L 4.5 1.5 0+107 RCC House 1.50m Peti Yes
70 Bijayanand Joshi L 4.5 1.5 0+122 RCC House 1.50m Peti Yes
71 Nanda Dhami L 4.5 1.5 0+136 RCC House 1.50m Peti+ T-Chhaja Yes
72 Mohan Singh Dhami L 4.5 1.5 0+140 RCC House 1.50m Peti Yes
73 Jayakisan Bhatta L 4.5 1.5 0+145 RCC House 1.50m Peti+ T-Chhaja Yes
74 Dilliraj Joshi L 4.5 1.5 0+152 RCC House 1.50m Peti Yes
75 Dharma Devi Rana L 4.5 1.5 0+158 RCC House 1.50m Peti+ T-Chhaja Yes
76 Gopal Datt Joshi L 4.5 1.5 0+163 RCC House 1.50m Peti+ T-Chhaja Yes
77 Tej Bdr. Bam L 4.5 1.5 0+170 RCC House 1.50m Peti+ T-Chhaja Yes
78 Kisan Singh Thapa L 4.5 1.5 0+176 RCC House 1.50m Peti Yes
79 Laxmi Datt Pandey L 4.5 1.5 0+187 RCC House 1.50m Peti+ T-Chhaja Yes
80 Lov Dev Pandey L 4.5 1.5 0+198 RCC House 1.50m Peti+ T-Chhaja Yes
81 Basudev Bohora L 4.5 1.5 0+209 RCC House 1.50m Peti+ T-Chhaja Yes
82 Karna Bdr. Chand L 4.5 1.5 0+215 RCC House 1.50m Peti+ T-Chhaja Yes
83 Deelip Singh Bhandari L 4.5 1.5 0+221 RCC House 1.50m Peti+ T-Chhaja Yes
84 Manoj Parshad Joshi L 4.5 1.5 0+228 RCC House 1.50m Peti Yes
85 lov Dev Pandey L 4.5 1.5 0+238 RCC House 1.50m Peti Yes
86 Chandra Maya karki L 4.5 1.5 0+248 RCC House 1.50m Peti+ T-Chhaja Yes
87 Tara Devi Bhatta L 4.5 1.5 0+256 RCC House 1.50m Peti+ T-Chhaja Yes
88 Gangaram Giri L 4.5 1.5 0+264 RCC House 1.50m Peti+ T-Chhaja Yes
89 Netra Chataut L 4.5 1.5 0+286 RCC House 1.50m Peti+ T-Chhaja Yes
90 Balaram Ghimire L 4.5 1.5 0+290 RCC House 1.50m Peti+ T-Chhaja Yes
91 Jayadatt Paudyal L 4.5 1.5 0+300 RCC House 1.50m Peti+ T-Chhaja Yes
92 Bidhya Devi Kharel L 4.5 1.5 0+309 RCC House 1.50m Peti+ T-Chhaja Yes
93 Tikaram Aryal L 4.5 1.5 0+315 RCC House 1.50m Peti+ T-Chhaja Yes
94 Chintamani Kharel L 4.5 1.5 0+323 RCC House 1.50m Peti+ T-Chhaja Yes
95 Ranbir Saran Bhatta L 4.5 1.5 0+330 RCC House 1.50m Peti+ T-Chhaja Yes
96 Narain Datt Bhatta L 4.5 1.5 0+337 RCC House 1.50m Peti Yes
97 Raju Sharma L 4.5 1.5 0+345 RCC House 1.50m Peti+ T-Chhaja Yes
98 Gokarna Bdr. Chand L 4.5 1.5 0+352 RCC House 1.50m Peti+ T-Chhaja Yes
99 Amita Aryal L 4.5 1.5 0+360 RCC House 1.50m Peti+ T-Chhaja Yes100 Pabi Kafle L 4.5 1.5 0+364 RCC House 1.50m Peti+ T-Chhaja Yes
101 Hema Devi Gurung L 4.5 1.5 0+367 RCC House 1.50m Peti+ T-Chhaja Yes
10 Hom Bdr. Kunuwar L 4.5 1.5 0+387 RCC House 1.50m Peti+ Metal Ladder Yes
Annex ‐ Page 5
S.N Name of HH Head Side Available ROW
Required Width
Chainage
Type of Structure Affected Part Individual
Consent
2
103 Khadak Bdr. Kunuwar L 4.5 1.5 0+388 RCC House 1.50m Peti+ T-Chhaja Yes
V-4: Gully No-4 Road (North-South section) , Design Width = 12 m, Total Langth = 404.75 m, Phase I Construction Length = 404.75 m
1 L.B Bista R 4.6 1.4 0+000 RCC House 1.40m Peti+T-Chhaja
2 Tara Singh Bohora R 4.6 1.4 0+013 RCC House 1.40m Peti+T-Chhaja Yes
3 Mohan Khatri R 4.6 1.4 0+020 RCC House 1.40m Peti+T-Chhaja Yes
4 Hariram Chaudhari R 4.6 1.4 0+026 RCC House 1.40m Peti+T-Chhaja Yes
5 Chet Raj Joshi R 4.6 1.4 0+031 RCC House 1.40m Peti+T-Chhaja Yes
6 Dhan Bdr.Ayer R 4.6 1.4 0+037 RCC House 1.40m Peti+T-Chhaja Yes
7 Khadak Singh Saud R 4.6 1.4 0+044 RCC House 1.40m Peti+T-Chhaja
8 Hira Devi Thagunna R 4.6 1.4 0+050 RCC House 1.40m Peti+T-Chhaja Yes
9 Shankardatt Joshi R 4.6 1.4 0+075 RCC House 1.40m Peti+T-Chhaja Yes
10 Chitramani Joshi R 4.6 1.4 0+078 RCC House 1.40m Peti+T-Chhaja Yes
11 Manju Bhatta R 4.8 1.2 0+083 RCC House 1.40m Peti+T-Chhaja
12 Haridatt Bhatta R 4.8 1.2 0+087 RCC House 1.40m Peti+T-Chhaja
13 Mamta Awasti R 4.6 1.4 0+092 RCC House 1.40m Peti+T-Chhaja Yes
14 Dhan Bdr. Bom R 4.6 1.4 0+100 RCC House 1.40m Peti+T-Chhaja Yes
15 Kiran Khadka R 4.6 1.4 0+108 RCC House 1.40m Peti+T-Chhaja Yes
16 Gajadhar Joshi R 4.6 1.4 0+112 RCC House 1.40m Peti+T-Chhaja Yes
17 Manorath Bhatta R 4.6 1.4 0+116 RCC House 1.40m Peti+T-Chhaja Yes
18 Girija Shankar Parsad R 4.6 1.4 0+120 RCC House 1.40m Peti+T-Chhaja
19 Harish Chandra Bhatta R 4.6 1.4 0+150 RCC House 1.40m Peti Yes
20 Naina Ojha R 4.6 1.4 0+175 RCC House 1.40m Peti+T-Chhaja
21 Deependra Bista R 4.6 1.4 0+180 RCC House 1.40m Peti+T-Chhaja Yes
22 Ganga Kharel R 4.6 1.4 0+186 RCC House 1.40m Peti+T-Chhaja
23 Devidatt Bhatta R 4.6 1.4 0+192 RCC House 1.40m Peti
24 Devaki Joshi R 4.6 1.4 0+196 RCC House 1.40m Peti
25 Chandrakala Panta R 4.6 1.4 0+204 RCC House 1.40m Peti
26 Jaya Bdr. Pal R 4.6 1.4 0+210 RCC House 1.40m Peti Yes
27 Dambar Bdr. Pal R 4.6 1.4 0+219 RCC House 1.40m Peti Yes
28 Hari Parsad Bhatta R 4.6 1.4 0+228 RCC House 1.40m Peti+T-Chhaja Yes
29 Laxman Singh Bista R 4.6 1.4 0+234 RCC House 1.40m Peti+T-Chhaja
30 Narendra Khatri R 4.6 1.4 0+250 RCC House 1.40m Peti+T-Chhaja
31 Dhirendra Bdr. Chand R 4.6 1.4 0+255 RCC House 1.40m Peti+T-Chhaja
32 Saligram Kharel R 4.6 1.4 0+258 RCC House 1.40m Peti+T-Chhaja Yes
33 Narayan Baral R 4.8 1.2 0+265 RCC House 1.40m Peti+T-Chhaja Yes
Annex ‐ Page 6
S.N Name of HH Head Side Available ROW
Required Width
Chainage
Type of Structure Affected Part Individual
Consent
34 Dhan Bdr. Chand R 4.6 1.4 0+273 RCC House 1.40m Peti Yes
35 Bamayanti Joshi R 4.6 1.4 0+280 RCC House 1.40m Peti Yes
36 Durga Bhandari R 5 1 0+310 RCC House1.40m RCC House Chhaja Yes
37 Parbati Devi Damai R 5 1 0+318 RCC House 1.40m Peti+T-Chhaja Yes
38 Tila Devi Damai R 5 1 0+322 RCC House 1.40m Peti+T-Chhaja Yes
39 P.K Shrestha R 5 1 0+325 RCC House 1.0mPeti Yes
40 Dammari Bhatta R 5 1 0+332 RCC House 1.40m Peti+T-Chhaja
41 Rama Shrestha R 5 1 0+340 RCC House 1.40m Peti+T-Chhaja
42 Deepa Devi Shrestha R 5 1 0+352 RCC House 1.40m Peti Yes
43 Hripriya Pant L 4.6 1.4 0+000 RCC House 1.40m Peti+T-Chhaja
44 Premdatt Joshi L 4.6 1.4 0+012 RCC House 1.40m Peti+T-Chhaja
45 Prajapati Bista L 4.6 1.4 0+019 RCC House 1.40m Peti Yes
46 Dal Bdr.Bista L 4.6 1.4 0+032 RCC House 1.60m Peti+T-Chhaja Yes
47 Harka Bdr. Bista L 4.6 1.4 0+036 RCC House 1.60m Peti+T-Chhaja Yes
48 Jahar Singh Pwali L 4.6 1.4 0+040 RCC House 1.60m Peti+T-Chhaja Yes
49 Madhav Joshi L 4.6 1.4 0+045 RCC House 1.60m Peti+T-Chhaja
50 Shreeram Chataut L 4.6 1.4 0+055 RCC House 1.60m Peti+T-Chhaja Yes
51 Hajari Singh Pujara L 4.6 1.6 0+065 RCC House 1.60m Peti Yes
52 Dharma Singh Rawal L 4.6 1.4 0+072 RCC House 1.60m Peti+T-Chhaja
53 Dhana Devi Bhatta L 4.6 1.4 0+080 RCC House 1.60m Peti+T-Chhaja Yes
54 Niraj Saud L 4.6 1.4 0+093 RCC House 1.60m Peti Yes
55 Padam Thakurathi L 4.6 1.4 0+100 RCC House 1.60m Peti+T-Chhaja Yes
56 Godawari Bhatta L 4.6 1.4 0+108 RCC House 1.60m Peti+T-Chhaja Yes
57 Sunil Panta L 4.6 1.4 0+150 RCC House 1.60m Peti+T-Chhaja Yes
58 Tek Bdr. Kunuwar L 4.6 1.4 0+156 RCC House 1.60m Peti+T-Chhaja Yes
59 Madan Singh Thagunna L 4.6 1.4 0+162 RCC House 1.60m Peti+T-Chhaja
60 Sova Karki L 4.6 1.4 0+168 RCC House 1.60m Peti+T-Chhaja Yes
61 Kalu Bohora L 4.6 1.4 0+173 RCC House 1.60m Peti+T-Chhaja Yes
62 Gorakh Bdr. Bista L 4.6 1.4 0+180 RCC House 1.60m Peti+T-Chhaja Yes
63 Lalit Bdr. Bohora L 4.6 1.4 0+205 RCC House 1.40m Peti+T-Chhaja Yes
64 Lalit Parsad Bhatta L 4.6 1.4 0+215 RCC House 1.40m Peti+T-Chhaja Yes
65 Laxman Chand L 4.6 1.4 0+260 RCC House 1.40m Peti+T-Chhaja Yes
66 Kashi Singh Karki L 4.6 1.4 0+267 RCC House 1.20m Peti+T-Chhaja Yes
67 Gyanu Bohara L 4.6 1.4 0+278 RCC House 1.30m Peti+T-Chhaja Yes
68 Parkash Chand L 4.6 1.4 0+282 RCC House 1.30m Peti+T-Chhaja Yes
69 Padama devi Bhatta L 4 2 0+331 RCC House 2m Peti+0.20m H/Chhaja Yes
70 Rudra Parsad Bhatrai L 4 2 0+335 RCC House 2m Peti+0.20m H/Chhaja Yes
Annex ‐ Page 7
S.N Name of HH Head Side Available ROW
Required Width
Chainage
Type of Structure Affected Part Individual
Consent
71 Mina Baral L 4.9 1.1 0+350 RCC House 1.10m Peti Yes
72 Padam Raj Pandey L 5.4 0.6 0+372 RCC House 0.60m Peti Yes
73 Mahesh Pandey L 5.4 0.6 0+375 RCC House 0.60m Peti Yes
74 Dhan Bdr. Chand L 4.9 1.1 0+390 RCC House 1.10m Peti+T-Chhaja Yes V-3 : Gully No-3 Road (North-South Section), Design Width= 12m, Total Length=407.37m, Phase I Construction Langth=407.37 m
1 Basanti Devi Pandey R 5.5 0.5 0+000 RCC House 0.50m Peti+T-Chhaja Yes
2 Ambika devi Bhandari R 5.5 0.5 0+015 RCC House 0.50m House Peti Yes
3 Parmananda Bhandari R 5.5 0.5 0+026 RCC House 0.50m House Peti Yes
4 Top Bdr. K.C R 4.5 1.5 0+037 RCC House 1.50m Peti+T-Chhaja
5 Bhim Pandey R 4.5 1.5 0+048 RCC House 1.50m Peti+T-Chhaja Yes
6 Bhuwan Pandey R 4.5 1.5 0+052 RCC House 1.50m Peti+T-Chhaja Yes
7 Devraj Mishra R 4.6 1.4 0+065 RCC House 1.40m Peti+T-Chhaja Yes
8 Prem Singh Bhatta R 4.5 1.5 0+074 RCC House 1.50m Peti+T-Chhaja
9 Hikmat Saud R 4.5 1.5 0+079 RCC House 1.50m Peti Yes
10 Ganesh Saud R 4.5 1.5 0+085 RCC House 1.50m Peti Yes
11 Tej Bdr. Bhandari R 4.5 1.5 0+090 RCC House 1.50m Peti+T-Chhaja Yes
12 Sundara Dev Bhandari R 4.5 1.5 0+094 RCC House 1.50m Peti Yes
13 Chandra Bdr. Chand R 4.5 1.5 0+100 RCC House 1.50m Peti+T-Chhaja Yes
14 Bhan Bdr. Chand R 4.5 1.5 0+108 RCC House 1.50m Peti+T-Chhaja Yes
15 Bashu Dev Deuba R 4.5 1.5 0+115 RCC House 1.50m Peti+T-Chhaja
16 Nara Bdr. Bista R 4.5 1.5 0+119 RCC House 1.50m Peti+T-Chhaja
17 Kamala Devi Kathayat R 4.5 1.5 0+124 RCC House 1.50m Peti+T-Chhaja Yes
18 Dal Bdr. Shah R 4.5 1.5 0+128 RCC House 1.50m Peti+T-Chhaja
19 Gorakh Bdr. Khati R 4.5 1.5 0+132 RCC House 1.50m Peti+T-Chhaja
20 Bhim Datta Bhatta R 4.5 1.5 0+139 RCC House 1.50m Peti+T-Chhaja Yes
21 Yagyaraj Paudyal/Madan R 4.5 1.5 0+141 RCC House 1.50m Peti+T-Chhaja Yes
22 Rupkiswor Gupta R 4.5 1.5 0+165 RCC House 1.50m Peti
23 Bharat Nepal R 4.5 1.5 0+175 RCC House 1.50m Peti+T-Chhaja Yes
24 Nar Bdr. Pal R 4.5 1.5 0+180 RCC House 1.50m Peti+T-Chhaja Yes
25 Kailap Bhatta R 4.5 1.5 0+185 RCC House 1.50m Peti
26 Ghanashyam Kalauni R 4.5 1.5 0+195 RCC House 1.50m Peti Yes
27 Dhan Bdr. Bom R 4.5 1.5 0+200 RCC House 1.50m Peti+T-Chhaja
28 Anil Dhungana/Joshi R 4.5 1.5 0+260 RCC House 1.50m Peti Yes
29 Yasoda Pathak/ Tiwari R 4.5 1.5 0+267 RCC House 1.50m Peti Yes
30 Jeetendra Parsad Bhatta R 4.5 1.5 0+300 RCC House 1.50m Peti+T-Chhaja Yes
31 Mahendra Bdr Kunwor L 4.7 1.3 0+000 RCC House 1.30m Peti+T-Chhaja
Annex ‐ Page 8
S.N Name of HH Head Side Available ROW
Required Width
Chainage
Type of Structure Affected Part Individual
Consent
32 Ram Singh Ter L 4.7 1.3 0+012 RCC House 1.30m Peti+T-Chhaja Yes
33 Ram Pd Sapkota L 4.7 1.3 0+023 RCC House 1.30m Peti Yes
34 Arjun Prakash Upreti L 4.7 1.3 0+033 RCC House 1.30m Peti+T-Chhaja
35 Min Raj Bhatta L 4.7 1.3 0+044 RCC House 1.30m Peti+T-Chhaja
36 Karan Shah L 4.7 1.3 0+065 RCC House 1.30m Peti+T-Chhaja
37 Narendra Raj Bohora L 4.7 1.3 0+070 RCC House 1.30m Peti+T-Chhaja Yes
38 Jagdish Upreti L 4.7 1.3 0+074 RCC House 1.30m Peti+T-Chhaja Yes
39 Ratan Saud L 4.7 1.3 0+084 RCC House 1.30m Peti Yes
40 Karan Bdr Singh L 4.7 1.3 0+088 RCC House 1.30m Peti+T-Chhaja Yes
41 Ashok Kumar Dewal L 4.7 1.3 0+104 RCC House 1.30m Peti+T-Chhaja Yes
42 Dhawal Bdr Chand L 4.7 1.3 0+112 RCC House 1.30m Peti
43 Kalpana KC L 4.7 1.3 0+121 RCC House 1.30m Peti+T-Chhaja Yes
44 Jayamati Devi Bhatta L 4.7 1.3 0+129 RCC House 1.30m Peti+T-Chhaja Yes
45 Madan Panta L 4.6 1.4 0+164 RCC House 1.40m Peti+T-Chhaja
46 Dhan Singh Rawal L 4.6 1.4 0+170 RCC House 1.40m Peti+T-Chhaja Yes
47 Belu Devi Bhata L 4.6 1.4 0+186 RCC House 1.40m Peti+T-Chhaja Yes
48 Kunti Bohora L 4.6 1.4 0+192 RCC House 1.40m Peti+T-Chhaja Yes
49 Harish Chand L 4.6 1.4 0+199 RCC House 1.40m Peti+T-Chhaja Yes
50 Jamunaganga Devi Joshi L 4.6 1.4 0+205 RCC House 1.40m Peti+T-Chhaja
51 Tanka Pd. Bhatta L 4.6 1.4 0+220 RCC House 1.40m Peti
52 Radhika Devi Bhatta L 4.6 1.4 0+228 RCC House 1.40m Peti+T-Chhaja Yes
53 D.r Rajendra Bhatta L 4.6 1.4 0+234 RCC House 1.40m Peti+T-Chhaja Yes
54 Deepak Kharel L 4.6 1.4 0+241 RCC House 1.40m Peti Yes
55 Rishi Kharel L 4.6 1.4 0+250 RCC House 1.40m Peti Yes
56 Yadu Raj Joshi L 4.6 1.4 0+310 RCC House 1.40m Peti+T-Chhaja Yes
57 Nar Singh Dhami L 4.6 1.4 0+317 RCC House 1.40m Peti+T-Chhaja Yes
58 Tarun Lakhera L 4.6 1.4 0+324 RCC House 1.40m Peti Yes
59 Padama Saud Bhandari L 4.6 1.4 0+330 RCC House 1.40m Peti Yes
60 Furua Kalauni L 5.1 0.9 0+350 RCC House 0.90mPeti+Metal ladder Yes
61 Megh Raj Bhatta L 5 1 0+357 RCC House 1m Peti Yes
62 Kashidatt Bhatta L 5 1 0+365 RCC House 1m Peti Yes
63 Panchadev Multipurpose Office L 5 1 0+373 RCC House 1m Peti+T-Chhaja Yes
64 Kalpana Karki L 5.1 0.9 0+380 RCC House 0.90mPeti+Greel ladder Yes V-2: Gully No-2 Road (North-South section) , Design Width = 12 m, Total Length = 407.92 m, Phase I Construction Length = 407.92 m
1 Ramesh Pandey R 4.4 1.6 0+000 RCC House 1.60m Peti Yes
2 Laxi Pandey R 4.4 1.6 0+007 RCC House 1.60m Peti+T-Chhaja Yes
Annex ‐ Page 9
S.N Name of HH Head Side Available ROW
Required Width
Chainage
Type of Structure Affected Part Individual
Consent
3 Arjundatt Pandey R 4.4 1.6 0+016 RCC House 1.60m Peti+T-Chhaja Yes
4 Gopaldatt Bhatta R 4.4 1.6 0+023 RCC House 1.60m Peti+T-Chhaja Yes
5 Jamuna Devi Bhatta R 4.4 1.6 0+027 RCC House 1.60m Peti+T-Chhaja Yes
6 Bhojraj Bhatta R 4.4 1.6 0+030 RCC House 1.60m Peti+T-Chhaja
7 Rameswor Upreti R 4.4 1.6 0+040 RCC House 1.60m Peti+T-Chhaja Yes
8 Neha Singh Pal R 4.4 1.6 0+047 RCC House 1.60m Peti
9 Tikadatt Paneru R 4.4 1.6 0+053 RCC House 1.60m Peti+T-Chhaja Yes
10 Rajesh Gupta R 4.4 1.6 0+060 RCC House 1.60m Peti+T-Chhaja Yes
11 Parmananda Paneru R 4.4 1.6 0+064 RCC House 1.60m Peti+T-Chhaja Yes
12 Karunakar Paneru R 4.4 1.6 0+070 RCC House 1.60m Peti+T-Chhaja Yes
13 Laxmi Devi Bhatta R 4.4 1.6 0+075 RCC House 1.60m Peti Yes
14 Tek Khadka R 4.4 1.6 0+082 RCC House 1.60m Peti+T-Chhaja
15 Ram Parshad Pandey R 4.4 1.6 0+087 RCC House 1.60m Peti+T-Chhaja
16 Sher Singh Ter R 4.4 1.6 0+091 RCC House 1.60m Peti+T-Chhaja
17 Shankar Bdr. Bista R 4.4 1.6 0+095 RCC House 1.60m Peti+T-Chhaja Yes
18 Madan Singh Aiyar R 4.4 1.6 0+100 RCC House 1.60m Peti+T-Chhaja
19 Dharma Raj Bhatta R 4.4 1.6 0+103 RCC House 1.60m Peti Yes
20 Dev Raj Bhatta R 4.4 1.6 0+107 RCC House 1.60m Peti Yes
21 Jayalal Bhatta R 4.4 1.6 0+110 RCC House 1.60m Peti Yes
22 Bhoj Raj Bhatta R 4.4 1.6 0+114 RCC House 1.60m Peti+T-Chhaja Yes
23 Uddhav Singh Bista R 4.4 1.6 0+120 RCC House 1.60m Peti+T-Chhaja Yes
24 Nar Bdr. Bista R 4.4 1.6 0+123 RCC House 1.60m Peti+T-Chhaja Yes
25 Kiswar Jairu R 4.4 1.6 0+126 RCC House 1.60m Peti+T-Chhaja Yes
26 Nandalal Bohora R 4.4 1.6 0+130 RCC House 1.60m Peti Yes
27 Motilal Bohora R 4.4 1.6 0+134 RCC House 1.60m Peti Yes
28 Madana Devi Bohora R 4.4 1.6 0+138 RCC House 1.60m Peti+T-Chhaja Yes
29 Hari Parshad Bohora R 4.4 1.6 0+142 RCC House 1.60m Peti Yes
30 Siddharaj Bohora R 4.4 1.6 0+146 RCC House 1.60m Peti+T-Chhaja Yes
31 Sita K.C R 4.4 1.6 0+158 RCC House 1.60m Peti Yes
32 Iswori Devi Bohora R 4.4 1.6 0+163 RCC House 1.60m Peti+T-Chhaja Yes
33 Urmila Kharel R 4.4 1.6 0+168 RCC House 1.60m Peti+T-Chhaja Yes
34 Tika Devi Kharel R 4.4 1.6 0+174 RCC House 1.60m Peti Yes
35 Ram Parshad Kharel R 4.4 1.6 0+180 RCC House 1.60m Peti
36 Navraj Kharel R 4.4 1.6 0+186 RCC House 1.60m Peti
37 Manmati Giri R 4.4 1.6 0+191 RCC House 1.60m Peti+T-Chhaja Yes
38 Nisha Shah R 4.4 1.6 0+195 RCC House 1.60m Peti
39 Rasmi Gupta R 4.4 1.6 0+201 RCC House 1.60m Peti+T-Chhaja Yes
Annex ‐ Page 10
S.N Name of HH Head Side Available ROW
Required Width
Chainage
Type of Structure Affected Part Individual
Consent
40 Pawan Kumar Sarwagi R 4.4 1.6 0+206 RCC House 1.60m Peti Yes
41 Birendra Kumar Sangai R 4.4 1.6 0+217 RCC House 1.60m Peti
42 Dhan Bdr. Chand R 4.4 1.6 0+230 RCC House 1.60m Peti
43 Hajari Chand R 4.4 1.6 0+280 RCC House 1.40m Peti+T-Chhaja
44 Ram Bdr. Kunuwar R 4.4 1.6 0+320 RCC House 1.40m Peti+BW Yes
45 Laxmi Bhatta R 4.4 1.6 0+342 RCC House 1.40m Peti Yes
46 Pratap Chand R 4.4 1.6 0+350 RCC House 1.40m Peti Yes
47 Ram Bdr. Kunuwar R 4.4 1.6 0+360 RCC House 1.40m Peti+T-Chhaja Yes
48 Narendra Paneru L 4.6 1.4 0+000 RCC House 1.40m Peti+T-Chhaja Yes
49 Damodar Athola Joshi L 4.6 1.4 0+013 RCC House 1.40m Peti+T-Chhaja Yes
50 Laxi Devi Paneru L 4.6 1.4 0+020 RCC House 1.40m Peti+T-Chhaja
51 Dwarika devi Bista L 4.6 1.4 0+025 RCC House 1.40m Peti Yes
52 Ramdular jaiswal L 4.6 1.4 0+031 RCC House 1.40m Peti Yes
53 Deep Raj Chataut L 4.6 1.4 0+037 RCC House 1.40m Peti Yes
54 Padam Bdr. Thakurathi L 4.6 1.4 0+047 RCC House 1.40m Peti Yes
55 Kalpana Thapa L 4.6 1.4 0+060 RCC House 1.40m Peti+T-Chhaja
56 Motimaya Sharma L 4.6 1.4 0+070 RCC House 1.40m Peti Yes
57 Ganga Kafle L 4.6 1.4 0+075 RCC House 1.40m Peti Yes
58 Narendra Khatri L 4.6 1.4 0+080 RCC House 1.40m Peti
59 Binod Joshi L 4.6 1.4 0+087 RCC House 1.40m Peti+T-Chhaja Yes
60 Srijana Rawal L 4.6 1.4 0+090 RCC House 1.40m Peti
61 Bir Bdr.Kunwor L 4.6 1.4 0+095 RCC House 1.40m Peti Yes
62 Nirmal Lamichhane L 4.6 1.4 0+100 RCC House 1.40m Peti Yes
63 Madan Sunar L 4.6 1.4 0+105 RCC House 1.40m Peti Yes
64 Shivlal Nyeupane L 4.6 1.4 0+109 RCC House 1.40m Peti
65 Naresh Agrawal L 4.6 1.4 0+113 RCC House 1.40m Peti Yes
66 Radhika Sunar L 4.6 1.4 0+118 RCC House 1.40m Peti Yes
67 Rameswor Bhatta L 4.6 1.4 0+122 RCC House 1.40m Peti Yes
68 Sushil Dewal L 4.6 1.4 0+132 RCC House 1.40m Peti+T-Chhaja
69 Megh Raj Bohora L 4.6 1.4 0+140 RCC House 1.40m Peti Yes
70 Ramchandra Bohora L 4.6 1.4 0+160 RCC House 1.40m Peti Yes
71 Kamala Devi Bohora L 4.6 1.4 0+166 RCC House 1.40m Peti+T-Chhaja Yes
72 Govinda Raj Joshi L 4.6 1.4 0+173 RCC House 1.40m Peti Yes
73 Mukesh Agrawal L 4.6 1.4 0+179 RCC House 1.40m Peti+T-Chhaja Yes
74 Kaviraj Bhatta L 4.6 1.4 0+185 RCC House 1.40m Peti+T-Chhaja Yes
75 Bhojraj Joshi L 4.6 1.4 0+191 RCC House 1.40m Peti Yes
76 Chitra Nepal L 4.6 1.4 0+202 RCC House 1.40m Peti+T-Chhaja Yes
Annex ‐ Page 11
S.N Name of HH Head Side Available ROW
Required Width
Chainage
Type of Structure Affected Part Individual
Consent
77 Iswori Devi Chilwal L 4.6 1.4 0+207 RCC House 1.40m Peti+T-Chhaja Yes
78 Laxmi devi Tiwari L 4.6 1.4 0+212 RCC House 1.40m Peti+T-Chhaja Yes
79 Ganesh Raj Bohora L 4.6 1.4 0+223 RCC House 1.40m Peti
80 Sunita Budha L 4.6 1.4 0+234 RCC House 1.40m Peti+T-Chhaja Yes
81 Chandra Datt Joshi L 4.6 1.4 0+249 RCC House 1.40m Peti+T-Chhaja
82 Madhusudan Aryal L 4.6 1.4 0+245 RCC House 1.40m Peti Yes
83 Gangaram Rawal L 4.6 1.4 0+252 RCC House 1.40m Peti
84 Somraj Aryal L 4.6 1.4 0+260 RCC House 1.40m Peti+T-Chhaja
85 Gopal Bhusal L 4.5 1.5 0+268 RCC House 1.40m Peti+T-Chhaja
86 Homlal Bhusal L 5.4 0.6 0+340 RCC House 0.60m P. Chhaja
87 Ishwori Devi Bhatta L 5.75 0.25 0+344 RCC House0.25m RCC House Chhaja
88 Tek Bdr. Sunar L 4.4 1.6 0+347 RCC House1.60m RCC House Chhaja
89 Min Bdr. Kathayat L 4.5 1.5 0+352 RCC House 1.50m Peti+T-Chhaja V-1: Gully No-1(Shalgadhi Road, North-South Section), Design Width = 12 m, Total Length = 1102 m, Phase I Construction Length =1102 m
1 Bhairav Bdr. Aiyar R 4.6 1.4 0+003 RCC House 1.40m Peti+T-Chhaja Yes
2 Suman Dewal R 4.5 1.5 0+011 RCC House 1.50m Peti+T-Chhaja Yes
3 Ashok Kumar Dewal R 4.6 1.4 0+013 RCC House 1.40m Peti+T-Chhaja Yes
4 Bhupendra Rawal R 4.5 1.5 0+016 RCC House 1.50m Peti+T-Chhaja Yes
5 Rajendra Rawal R 4.4 1.6 0+021 RCC House 1.60m Peti+T-Chhaja
6 Bhoj Raj bohora R 5 1 0+026 RCC House 1.00m Peti+T-Chhaja Yes
7 Padam Bdr. Aiyar R 5 1 0+032 RCC House 1.00m Peti+T-Chhaja Yes
8 Hariom Dewal R 5 1 0+037 RCC House 1.00m Peti+T-Chhaja Yes
9 Harinanda Pd.NirajKumar R 5 1 0+058 RCC House 1.00m Peti+T-Chhaja Yes
10 Nannelal Hariom R 5 1 0+054 RCC House 1.00m Peti+T-Chhaja Yes
11 Kailash Gupta R 4.6 1.4 0+061 RCC House 1.40m Peti Yes
12 Bijaya Dewal R 5 1 0+065 RCC House 1.00m Peti+T-Chhaja Yes
13 Padam Bdr. Thakurathi R 5 1 0+071 RCC House 1.00m Peti+T-Chhaja
14 Harilal Thakurathi R 5 1 0+076 RCC House 1.00m Peti+T-Chhaja Yes
15 Maheswor Chataut R 5 1 0+081 RCC House 1.00m Peti+T-Chhaja
16 Dansingh Thakurathi R 5 1 0+085 RCC House 1.00m Peti+T-Chhaja Yes
17 Omprakash Gupta R 4.5 1.5 0+091 RCC House 1.50m Peti+T-Chhaja Yes
18 Rajiv Dewal R 5 1 0+095 RCC House 1.00m Peti+T-Chhaja Yes
19 Rajeswori Devi Dewal R 5 1 0+100 RCC House 1.00m Peti+T-Chhaja Yes
20 Dharmendra Gupta R 5 1 0+106 RCC House 1.00m Peti+T-Chhaja
21 Parsuram Gautam R 5 1 0+111 RCC House 1.00m Peti+T-Chhaja Yes
22 Hira Devi Bohora R 5 1 0+115 RCC House 1.00m Peti+T-Chhaja
Annex ‐ Page 12
S.N Name of HH Head Side Available ROW
Required Width
Chainage
Type of Structure Affected Part Individual
Consent
23 Kanhyalal Dewal R 5 1 0+120 RCC House 1.00m Peti+T-Chhaja Yes
24 Gopal Dewal R 5 1 0+125 RCC House 1.00m Peti+T-Chhaja Yes
25 Dambar Datt Bhatta R 5 1 0+130 RCC House 1.00m Peti+T-Chhaja Yes
26 Balaram Chataut R 5 1 0+136 RCC House 1.00m Peti+T-Chhaja Yes
27 Kirta Bdr. Johra R 5 1 0+145 RCC House 1.00m Peti Yes
28 Dharma Raj Joshi R 5 1 0+149 RCC House 1.00m Peti+T-Chhaja Yes
29 Durga Devi Johra R 5 1 0+160 RCC House 1.00m Peti+T-Chhaja Yes
30 Dharma Singh Rawal R 5 1 0+168 RCC House 1.00m Peti Yes
31 Abdul Samim R 5 1 0+179 RCC House 1.00m Peti+T-Chhaja Yes
32 Maina Devi Bhandari R 5 1 0+185 RCC House 1.00m Peti+T-Chhaja Yes
33 Parbati Devi Khadayat R 5 1 0+190 RCC House 1.00m Peti+T-Chhaja Yes
34 Abdul Samim R 5 1 0+196 RCC House 1.00m Peti+T-Chhaja Yes
35 Masjeed R 5 1 0+200 RCC House 1.00m Peti+T-Chhaja Yes
36 Indra Singh Rawal R 5 1 0+204 RCC House 1.00m Peti+T-Chhaja
37 Lal Singh Thakurathi R 5 1 0+212 RCC House 1.00m Peti+T-Chhaja Yes
38 Padam Raj Bohora R 5 1 0+216 RCC House 1.00m Peti+T-Chhaja Yes
39 Bhubaneswori Kunwar R 5 1 0+220 RCC House 1.00m Peti Yes
40 Geeta Kharel R 4.7 1.3 0+232 RCC House 1.30m Peti+T-Chhaja Yes
41 Pabitra Aryal R 4.7 1.3 0+237 RCC House 1.30m Peti+T-Chhaja Yes
42 Harka Singh Aiyar R 5 1 0+248 RCC House 1.00m Peti+T-Chhaja
43 Bimal Khadayat R 5 1 0+255 RCC House 1.00m Peti
44 Bhubaneswori Bogati R 5 1 0+263 RCC House 1.00m Peti
45 Hem Raj Bohora R 5 1 0+270 RCC House 1.00m Peti
46 Dinesh Shrestha R 5 1 0+315 RCC House 1.00m Peti
47 Dev Singh Ter R 4.5 1.5 0+330 RCC House 1.50m Peti+T-Chhaja
48 Gagan Bdr Singh L 4.6 1.4 0+000 RCC House 1.40m Peti+T-Chhaja Yes
49 Khagesh Pd. Bhatta L 4.6 1.4 0+006 RCC House 1.40m Peti+T-Chhaja Yes
50 Siddha Raj Bhatta L 4.6 1.4 0+010 RCC House 1.40m Peti+T-Chhaja Yes
51 Deepu Budhayar L 4.6 1.4 0+013 RCC House 1.40m Peti+T-Chhaja Yes
52 Ammar Budharar L 4.6 1.4 0+019 RCC House 1.40m Peti+T-Chhaja Yes
53 Keshav Raj Panta L 4.6 1.4 0+025 RCC House 1.40m Peti+T-Chhaja Yes
54 Bimal Raj Panta L 4.6 1.4 0+030 RCC House 1.40m Peti+T-Chhaja Yes
55 Pawan Khadayat L 4.6 1.4 0+036 RCC House1.40m RCC House Chhaja
56 Lal Bdr. Khadayat L 4.6 1.4 0+041 RCC House 1.40m Peti+T-Chhaja Yes
57 Mukesh Rawal L 4.6 1.4 0+048 RCC House 1.40m Peti+T-Chhaja Yes
58 Megh Raj Bohora L 4.6 1.4 0+060 RCC House 1.40m Peti+T-Chhaja Yes
59 Dan Singh Thakurathi L 4.6 1.4 0+066 RCC House 1.40m Peti+T-Chhaja Yes
Annex ‐ Page 13
S.N Name of HH Head Side Available ROW
Required Width
Chainage
Type of Structure Affected Part Individual
Consent
60 Nawal Singh Saud L 4.6 1.4 0+070 RCC House 1.40m Peti+T-Chhaja
61 Krishna Datt Chataut L 4.6 1.4 0+075 RCC House 1.40m Peti+T-Chhaja Yes
62 Shiv Raj Bhatta L 4.6 1.4 0+080 RCC House 1.40m Peti+T-Chhaja Yes
63 Niraj Gupta L 4.6 1.4 0+085 RCC House 1.40m Peti+T-Chhaja Yes
64 Yagya Raj Bhatta L 4.6 1.4 0+090 RCC House 1.40m Peti+T-Chhaja Yes
65 Yagya Raj Bhatta L 4.6 1.4 0+094 RCC House 1.40m Peti+T-Chhaja Yes
66 Parkash Rawal L 4.6 1.4 0+097 RCC House 1.40m Peti+T-Chhaja Yes
67 Samser Rawal L 4.6 1.4 0+100 RCC House 1.40m Peti+T-Chhaja Yes
68 Lal Bdr. Rawal L 4.6 1.4 0+107 RCC House 1.40m Peti+T-Chhaja Yes
69 Amar Shingh Khadayat L 4.6 1.4 0+114 RCC House 1.40m Peti+T-Chhaja Yes
70 Tek Bdr. Saud L 4.6 1.4 0+117 RCC House 1.40m Peti+T-Chhaja Yes
71 Uday Saud L 4.6 1.4 0+120 RCC House 1.40m Peti+T-Chhaja Yes
72 Bam Dev Chataut L 4.6 1.4 0+124 RCC House1.40m RCC House Chhaja Yes
73 Chhotelal Batuwa L 4.6 1.4 0+127 RCC House 1.40m Peti+T-Chhaja Yes
74 Raj Kumar Dewal L 4.6 1.4 0+135 RCC House 1.40m Peti+T-Chhaja Yes
75 Umashankar Dewal L 4.6 1.4 0+138 RCC House 1.40m Peti+T-Chhaja Yes
76 Bhuwan Chataut L 4.6 1.4 0+150 RCC House 1.40m Peti
77 Ganesh Chataut L 4.6 1.4 0+155 RCC House 1.40m Peti Yes
78 Bal Devi Kharel L 4.9 1.1 0+158 RCC House 1.10m Peti+T-Chhaja Yes
79 Bashu Dev Bohora L 4.9 1.1 0+163 RCC House 1.10m Peti+T-Chhaja Yes
80 Mohan Singh Bista L 4.9 1.1 0+169 RCC House 1.10m Peti+T-Chhaja Yes
81 Kalpana Devi Bhusal L 4.9 1.1 0+175 RCC House 1.10m Peti+T-Chhaja Yes
82 Narayan Bhatta L 4.9 1.1 0+181 RCC House 1.10m Peti+T-Chhaja
83 Anita Joshi L 4.9 1.1 0+200 RCC House 1.10m Peti+T-Chhaja Yes
84 Bhuwan Kharel L 4.9 1.1 0+205 RCC House 1.10m Peti+T-Chhaja Yes
85 Poonam Bhatta L 4.9 1.1 0+210 RCC House 1.10m Peti Yes
86 Basanti Thagunna L 4.9 1.1 0+215 RCC House 1.10m Peti
87 Sova Dewal L 4.9 1.1 0+219 RCC House 1.40m Peti Yes
88 Mandhari Devi Giri L 5 1 0+226 RCC House 1.00m Peti+T-Chhaja
89 Laxman Singh Bista L 5 1 0+232 RCC House 1.00m Peti+T-Chhaja Yes
90 Hema Pandey L 4.2 1.8 0+260 RCC House 1.80m Peti+T-Chhaja
91 Rupa Aryal L 4.4 1.6 0+269 RCC House 1.60m Peti+T-Chhaja
92 Cholanath Bhandari L 4.4 1.6 0+275 RCC House 1.60m Peti+T-Chhaja
93 Man Singh Mahara L 4.4 1.6 0+280 RCC House 1.60m Peti+T-Chhaja
94 Sher Shingh Bhandari L 4.4 1.6 0+285 RCC House 1.60m Peti+T-Chhaja
95 Bir Bdr. Sunar L 4.4 1.6 0+290 RCC House 1.60m Peti+T-Chhaja
96 Omkar Panta L 4.4 1.6 0+305 RCC House 1.60m Peti+T-Chhaja
Annex ‐ Page 14
S.N Name of HH Head Side Available ROW
Required Width
Chainage
Type of Structure Affected Part Individual
Consent
97 Prakash Shah L 4.4 1.6 0+310 RCC House 1.60m Peti+T-Chhaja
98 Hari Datt Bhatta L 4.6 1.4 0+315 RCC House 1.40m Peti+T-Chhaja
V6: Malpot/Napi Karalaya-E/W Highway), Design Width=10 m, Length = 347.58 m
1 Little Buddha Academi R 4.4 0.6 0+228 BM House 0.60m BW Yes
2 Harilal Joshi R 4.9 0.1 0+240 RCC House 0.10m BW+ Chhaja
3 Patiram Chunara R 3.2 1.8 0+260 BM House 1.80m Peti+T-Chhaja Yes
4 Tek Raj Bhatta R 3.2 1.8 0+275 BM House 1.80m Peti+T-Chhaja H1: East-West Gully-1, Design Width=9 m, Rec. Width=9m, Total Length = 298.26 m, Phase I Construction Length=298.26 m
1 Gajendra Bdr. Shah L 2.6 1.9 0+005 RCC House 1.9m Peti Yes
2 Shambhu Bharati R 2.6 1.9 0+005 RCC House 1.9m Peti Yes
3 Chintamani Joshi L 2.6 1.9 0+030 RCC House 1.9m BW Yes
4 Manju Bhatta R 2.6 1.9 0+030 RCC House 1.9m Peti Yes
5 Shreeram Chataut L 2.6 1.9 0+063 RCC House 1.9m Peti Yes
6 Hajari Singh Pujara R 2.6 1.9 0+063 RCC House 1.9m Peti Yes
7 Gopal Singh Budha R 2.6 1.9 0+073 RCC House 1.9m Peti Yes
8 Bhuban Pandey L 2.6 1.9 0+082 RCC House 1.9m Peti Yes
9 Devraj Mishra R 2.6 1.9 0+082 RCC House 1.9m Peti+T.Chhaja Yes
10 Min Raj Bhatta L 2.6 1.9 0+115 RCC House 1.9m Peti + Chhaja Yes
11 Prem Shah R 2.6 1.9 0+115 RCC House 1.9m Peti + Chhaja Yes
12 Narendra Bohora R 2.6 1.9 0+119 RCC House 1.9m Peti + Chhaja Yes
13 Deepak Gupta R 2.6 1.9 0+123 RCC House 1.9m Peti + Chhaja Yes
14 Padam Bdr. Bhandari L 2.6 1.9 0+142 RCC House 1.9m Peti + Chhaja Yes
15 Laxmi Datt Bhatta R 2.6 1.9 0+150 RCC House 1.9m Peti + Chhaja Yes
16 Rudra Singh Bhandari L 2.6 1.9 0+159 RCC House 1.9m Peti + Chhaja
17 Karunakar Paneru L 2.6 1.9 0+162 RCC House 1.9m Peti + Chhaja Yes
18 Harilal Bhatta R 2.6 1.9 0+170 RCC House 1.9m Peti + Chhaja Yes
19 Kalpana Thapa R 2.6 1.9 0+195 RCC House 1.9m Peti + Chhaja
20 Padam Bdr. Thakurathi L 2.6 1.9 0+215 RCC House 1.9m Peti + Chhaja Yes
21 Shanti Damai L 2.6 1.9 0+225 RCC House 1.9m Peti + Chhaja Yes
22 kalu Singh+jagat Bhandari L 2.6 1.9 0+237 RCC House 1.9m Peti + Chhaja
23 Padam Bdr. Thakurathi R 2.6 1.9 0+245 RCC House 1.9m Peti + Chhaja Yes H2: East-West Gully-2, Design Width = 9 m, Rec Width = 9 m, Total Length = 297.88 m, Phase I Construction Length = 297.88m
1 Mohan Singh Dhami L 2.63 0.7 0+005 RCC House 1.77 m Peti Yes
2 Jaya Kisan Bhatta R 2.63 0.7 0+005 RCC House 1.77 m Peti+T.Chhaja Yes
3 Haris Chandra Bhatta R 2.63 0.5 0+024 RCC House 1.77 m Peti Yes
4 Laba Raj Bhatta L 2.63 0.5 0+024 RCC House 1.77 m Peti Yes
Annex ‐ Page 15
S.N Name of HH Head Side Available ROW
Required Width
Chainage
Type of Structure Affected Part Individual
Consent
5 Sunil Panta R 2.63 0.1 0+057 RCC House 1.77 m Peti Yes
6 Madan Paudyal L 2.61 0.45 0+084 RCC House 1.79 m Peti Yes
7 Tikaram Bohora R 2.61 0.45 0+091 RCC House 1.79 m Peti+T.Chhaja
8 Khem Raj Bohora R 2.61 0.45 0+103 RCC House 1.79 m Peti
9 Govinda Ballav Joshi R 2.61 0.6 0+137 RCC House 1.79 m Peti+Chhaja
10 Jaimati Devi Bhatta L 2.61 0.6 0+137 RCC House 1.79 m Peti+Chhaja Yes
11 Bashudev Bohora L 2.61 0.45 0+166 RCC House 1.79 m Peti Yes
12 Sita Devi K.C R 2.61 0.45 0+166 RCC House 1.79 m Peti Yes
13 Ganesh Bohora L 2.61 0.5 0+200 RCC House 1.79 m Peti
14 Kamala Devi Bohora R 2.61 0.5 0+200 RCC House 1.79 m Peti Yes
15 Durga Devi Bohara R 2.61 0.35 0+237 RCC House 1.79 m Peti
16 Dharma Raj joshi L 2.61 0.35 0+237 RCC House 1.79 m Peti Yes H-3: Hospital Road (Gully 6 to Gully 1/ East-West Gully-3), Design Width = 10 m, Total Length = 290 m, Phase I Construction Length =290 m
None H-4: Campus Road (Janki tole) to Gully 1( East-West Gully-4), Design Width = 10 m, Total Length = 480 m, Phase I Construction length = 284.40 m
None H-5: Sarswati Tole Road 1 (East West Gully-5, Katan Area) , Design Width = 10 m, Total Length = 300.99m, Phase I Construction Length = 300.99 m
1 Bisnudatt Bhatta R 4.45 0.55 0+000 BM House 0.55m BW Yes
2 Bajir Singh Aiyar L 4 1 0+038 BM House 1m BW Yes
3 Khagendra Chand R 4.7 0.3 0+038 BM House 0.30m BW
4 Ganga Datt Joshi L 4.15 0.85 0+054RCC House +BM House
0.85m BW+0.55m Shutter
5 Rajendra Chand R 4.8 0.2 0+054 BM House 0.20m BW Yes
6 Anandi Panta L 4.8 0.2 0+076 BM House 0.20m BW Yes
7 Parmeswori Pandey R 4.7 0.3 0+076RCC House+ BW 0.30m BW+0.20m Shutter Yes
8 Hom Bdr. Panthi L 4.7 0.3 0+100RCC House +BMM 0.30m BW+0.20m Shutter
9 Dharma Nanda Bhatta R 4.7 0.3 0+100 BM House 0.30m BW Yes
10 Sashi Ojha L 4.5 0.5 0+113 BM House 0.50m BW Yes
11 Laxman Singh Bhandari R 4.7 0.3 0+113 BM House 0.30m BW
12 Ganesh Bohora L 4.5 0.5 0+132 BM House 0.50m BW Yes
13 Narayan Singh Saud R 4.1 0.9 0+145 BM House 0.90m BW
14 Kamala Bohora L 4.1 0.9 0+145 BM House 0.90m BW Yes
15 Man Bdr. Sunar L 4.2 0.8 0+160 BM House 0.80m BW Yes
16 Tikaram Bhatta R 4.2 0.8 0+160 BM House 0.80m BW Yes
17 Tekendra Bhatta L 4.2 0.8 0+180 BM House 0.80m BW
18 Damodar Pandey R 4.1 0.9 0+200 BM House 0.90m BW Yes
19 Dr. Bhojraj Panta L 4.1 0.9 0+202 BM House 0.90m BW Yes
20 Bishnu Awasti R 4.1 0.9 0+220 BM House 0.90m BW Yes
Annex ‐ Page 16
S.N Name of HH Head Side Available ROW
Required Width
Chainage
Type of Structure Affected Part Individual
Consent
21 Puspamani Bhatta L 4.3 0.7 0+220 BM House 0.70m BW Yes
22 Keshav Nayak R 4.3 0.7 0+239 BM House 0.70m BW
23 Kamal Shrestha L 4.3 0.7 0+250 BM House 0.70m BW Yes
24 Gauri Datt Joshi R 4.3 0.7 0+250 BM House 0.70m BW
25 Lalitananda Joshi L 4.3 0.7 0+257 BM House 0.70m BW
26 Somraj Aryal L 4.3 0.7 0+270 BM House 0.70m BW Yes
27 Man Singh Rawat L 3.7 1.3 0+283RCC House +BM House
0.40m H Chhaja+1.30m BW
28 Purna Raj Bhatta R 3.7 1.3 0+300 BM House 1.30 Kucchi House H-6:Sarswati Tole Road 2 (East West Gully-6, Katan Area), Design Width= 10 m, Total Length = 350 m, Total Length =350 m, Phase I construction length=150m (ch 0+200- 0+350) Yes
1 Devaki Bam L 3.85 1.15 0+200 BM House 1.15m BW
2 Kapil Joshi R 3.85 1.15 0+200 BM House 1.15m BW
3 Shyam Chand L 3.85 1.15 0+225 BM House 1.15m BW Yes
4 Basant Bdr. Singh R 3.85 1.15 0+245 BM House 1.15m BW
5 Parwati Devi Chand L 3.85 1.15 0+265 BM House 1.15m BW Yes
6 Tara Joshi R 3.85 1.15 0+280 BM House 1.15m BW Yes
7 Siddharaj Bhatta L 3.85 1.15 0+295 BM House 1.15m BW
8 Mohandev Joshi R 3.85 1.15 0+315 BM House 1.15m BW
9 Dattaram Dasrath Bhatta L 3.85 1.15 0+325 BM House 1.15m BW
10 Manmati Chand R 3.85 1.15 0+325 BM House 1.15m BW Yes
11 Dal Bdr. Chand L 3.85 1.15 0+330 BM House 1.15M BW H-7: Sarswati Tole Road 3 (East West Gully-7, Katan Area), Design Width= 10 m, Total Length = 392.41m, Phase I Construction length=392.41 m
1 Pushkar Giri R 4.1 0.9 0+000RCC House +BM House
0.70m HW+0.90m BW/Shutter
2 Gagan Giri L 4.1 0.9 0+050 BM House 0.90m BW
3 Dilmaya Bhatta R 4.1 0.9 0+050RCC House +BM House
0.70m HW+0.90m BW/Shutter
4 Tek Raj Panta L 4.1 0.9 0+060 BM House 0.90m BW Yes
5 Sova Devi Joshi R 4.1 0.9 0+060 BM House 0.90m BW Yes
6 Kapil Panta L 4.1 0.9 0+080 BM House 0.90m BW+BM Shed
7 Karan Nath R 4.1 0.9 0+080 BM House 0.90m BW
8 Komala Devi Chand L 4.1 0.9 0+095 BM House 0.90m BW
9 Umadatt Bhatta R 4.1 0.9 0+095 BM House 0.90m BW
10 Ambika Joshi R 4.1 0.9 0+114 BM House 0.90m BW
11 Krishna P.d Bohora L 4.1 0.9 0+138 BM House 0.90m BW
12 Dhani Datt Panta R 3.75 1.25 0+158 BM House 1.25m BW Yes
13 Pramananda Joshi L 3.75 1.25 0+158 BM House 1.25m BW Yes
14 Kalpana K.C R 3.8 1.2 0+185 BM House 1.20m BW
15 Sitaram Joshi L 3.8 1.2 0+185 BM House 1.20m BW
Annex ‐ Page 17
S.N Name of HH Head Side Available ROW
Required Width
Chainage
Type of Structure Affected Part Individual
Consent
16 Prakash Bdr. Singh R 3.8 1.2 0+205 BM House 1.20m BW Yes
17 Rana singh Bhandari L 3.8 1.2 0+205 BM House 1.20m BW Yes
18 Gajendra Thapa R 3.8 1.2 0+225 BM House 1.20m BW Yes
19 Purnananda Bhatta L 3.8 1.2 0+225 BM House 1.20m BW Yes
20 Bhojraj Pandey L 3.8 1.2 0+240 BM House 1.20m BW
21 Jayanti Chand R 4 1 0+260 BM House 1m BW Yes
22 Bhanubhakta Joshi L 4 1 0+260 BM House 1m BW Yes
23 Shusila Pandey L 4 1 0+280 BM House 1m BW+BM Shed Yes
24 Mahadev Bhatta R 3.8 1.2 0+300 BM House 1.20m BW Yes
25 Tara Devi Bhatta L 3.8 1.2 0+300 BM House 1.20m BW+ BM Shed
26 Chandra Dev Upadhyay L 4 1 0+315 BM House 1m BW
27 G.K Bhat L 4 1 0+315 BM House 1m BW Yes
28 Narad Pandey R 4 1 0+335RCC House +BM House 1m HW+ BW Yes
29 Ran Bdr. Pal L 4 1 0+360RCC House +BM House 1m HW+BW
H-8: Sarswati Tole Road 4 (East West section, Katan Area) , Design Width=10m, total length= 372.22m, Phase I Construction Length= 372.22m Yes
1 Tara Devi Joshi R 4.35 0.65 0+000 BM House 0.65m BW Yes
2 Shanti Devi Bhandari L 4.35 0.65 0+030 BM House 0.65m BW Yes
3 Rajaya Swar R 4.15 0.85 0+030 BM House 0.85m BW
4 Laba Dev Pandey L 4.15 0.85 0+050 BM House 0.85m BW Yes
5 Bishnu Aryal R 3.85 1.15 0+086 BM House 1.15m BW Yes
6 Basanta Singh R 3.85 1.15 0+086 BM House 1.15m BW
7 Paradise Hotel L 3.85 1.15 0+100 BM House 1.15m BW Yes
8 Nepal Manav Dharma Sewa R 3.85 1.15 0+100 BM House 1.15m BW Yes
9 Kamala Nanda Joshi L 3.85 1.15 0+136 BM House 1.15m BW Yes
10 Hemlal Sapkota R 3.85 1.15 0+136 BM House 1.15m BW Yes11 Sita Devi Joshi L 3.85 1.15 0+154 BM House 1.15m BW
12 Ganesh Chand R 3.85 1.15 0+154 BM House 1.15m BW Yes13 Tika singh Dhami L 3.85 1.15 0+175 BM House 1.15m HW+ BW
14 Dr. Madan Singh Karki R 3.85 1.15 0+175 BM House 1.15m BW
15 Dharmanand Bhatta L 3.85 1.15 0+209 BM House 1.15m BW 16 Dashrath Joshi R 3.75 1.25 0+209 BM House 1.25m BW Yes
17 Uttara Chand L 3.75 1.25 0+227 BM House 1.25m BW Yes18 Maya Devi Joshi R 3.75 1.25 0+245 BM House 1.25m BW
19 Harsa Narain Upadhyay L 3.75 1.25 0+262 BM House 1.25m BW Yes
20 Bishnu Datt Awasti L 3.75 1.25 0+280 BM House 1.25m BW Yes21 Nirajan Gautam L 3.75 1.25 0+292 BM House 1.25m BW 22 Shavitri Devi Panta R 3.75 1.25 0+300 BM House 1.25m BW Yes23 Krishna Bdr. Chand L 3.75 1.25 0+318 BM House 1.25m BW Yes
Annex ‐ Page 18
S.N Name of HH Head Side Available ROW
Required Width
Chainage
Type of Structure Affected Part Individual
Consent
24 Janaki Devi Bam L 3.75 1.25 0+336 BM House 1.25m BW Yes25 Dammar Datt Bogati R 3.75 1.25 0+350 BM House 1.25m BW+ BM Shed Yes26 Hari Chand R 3.75 1.25 0+360 BM House 1.25m BW Yes
H-9: Eye Hospital Road (East-West), Design Width= 10m, Total Length= 430 m, Phase I Construction length=430m
1 Omprakash Dedwal R 3.5 1.5 0+015 BM House 4m BW+BM House Yes H-10 : Hospital Road (Gully 1 to Bhagatpur Marg), Design Width=10m, Total Length= 738 m, Phase I Construction Width=738 m
1 Siddhanath Tample L 4.4 0.6 0+650 BM House 0.60m BW
2 Krishna Prasad Bhandari R 4.4 0.6 0+694 BM House 0.60m Peti
3 Kedar Prasad Bhandari R 3.8 1.2 0+705 BM House 1.20m BW 4 Nandalal Joshi R 3.8 1.2 0+714 BM House 1.20m BW 5 Kamala Devi Bhatta R 4 1 0+720 BM House 1m BW
6 Ravi Joshi R 4 1 0+730 BM House 1m BW
7 Mina Panta R 4.2 0.8 0+750 BM House 0.80m BW Yes8 Lokraj Panta R 4.3 0.7 0+755 BM House 0.70m BW
9 District Election Office R 4.5 0.5 0+770 BM House 0.50m BW
10 Okil Karalaya/Mahesh Datta Joshi L 4.8 0.2 0+850 RCC House 0.20m HW
11 Lal Bdr.Thapa R 4.3 0.7 0+870 BM House 0.70m BW 12 Raji Chand L 3.4 1.6 0+888 BM House 1.60m BW
13 Dhir Samser Kunuwar R 4.4 0.6 0+922 BM House 0.60m BW Hotel Opera road, E-W), Design Width 15 m, Total length=280 m, Phase I construction length= 190m (ch. 0+00 - 0+190)
1 Binod Kumar Agrawal R 5.5 2 0+020 BM House 2m Peti+T.Chhaja Yes
2 Nagar Vikas House L 5.8 0.7 0+020 RCC House 0.70m Peti
3 Nagar Vikas Shutter-5nos L 7.35 0.15 0+037 RCC House 0.15m Peti+T.Chhaja 4 Krishna Prasad Bogati R 6.8 0.7 0+100 RCC House 0.70m Peti Yes
5 Harilal Paneru R 6.8 0.7 0+175 RCC House 0.70 m Peti Yes
6 Hotel Opera L 7.25 0.25 0+175 BW+Peti 0.25mBW+Peti Madan chowk-Dashrath Chowk - Napi - Bhagatpur Chowk Road, Design Width=15 m from Dashrath Chowk to Nani Karalaya (ch: 0+00-0+750) & 12 m from Napi Karalaya to Bhagatpur (ch:0+751- 1+150),Total Length 1150m
1 Duraga Datt Bohora L 5.8 0.2 0+880 RCC House 0.20m BW+Chhaja Yes
2 Ratna Singh Thakurathi L 5.7 0.3 0+935 RCC House 0.3m Peti+veranda Yes
3 Gorakh Bdr. Chand L 5.7 0.3 0+945 RCC House 0.3m BW Yes4 Omparkash Bhandari R 5.75 0.25 0+965 BM House 0.25m T.Chhaja Yes5 Krishna Datt Bhatta L 5.6 0.4 1+004 BM House 0.4m BW Yes
6 Damar Devi Kuwar R 5.1 0.9 1+060 BM House 0.9m T.shutter+Chhaja YesTraffic Chowk- Dashrat - BP Chowk Road, Design width =15m, Length = 600 m
None Note: BM House= Brick Masonry House, RCC House= Reinforced Concrete House, BW=Boundary Wall, T. Chhaja=Temporary Chhaja (shed)
Annex ‐ Page 19
ANNEX-2
Demographic and Economic Information of Affected Households
S.N Name of HH Head / Owner Ethnicity
Education
Population Economic Status
Male Female Total Occupation Monthly Income (Rs)
Per Capita Income (Rs)
M1 : Bhasi- Rautela Road 1 Chanak Lal Chaudhary Janjati S.L.C 5 2 7 Business 50000 85714
2 Asha Chaudhary Janjati Elementary 1 3 4 Business 25000 75000
3 Hira Devi Thagunna Chhettri Elementary 4 2 6 Agriculture 20000 40000
4 Ghungra Khatri Chhettri Elementary 4 2 6 Wage 16000 32000
M2 : Bhanuchowk -Bishnudham Road
1 Binod Rawal Chhettri Elementary 2 2 4 Business 50000 150000
2 Bhupendra Rawal Chhettri 3 3 6 Business 50000 100000
3 Debu Devi Bista Chhettri Elementary 2 4 6 Business 75000 150000
4 Kalyan Singh Thakuriya Chhettri Elementary 4 4 8 Business 40000 60000
5 Madhavi Bhatta Brahmin Elementary 2 3 5 Business 35000 84000
6 Deependra Rawal Chhettri B.A 4 3 7 Business 30000 51429
7 Prem Thalal Chhettri S.L.C 3 3 6 Business 45000 90000
8 Navaraj Khadka Chhettri Elementary 2 3 5 Business 40000 96000
9 Kishor Pandey Brahmin B.A 3 1 4 Service 30000 90000
M3: Suklaphanta Marga(Bhanuchowk-Madan chowk-Airport Road) 1 D.D Pandey Brahmin Elementary 4 3 7 Business 55000 94286
2 Sabitri Rawat Chhettri Elementary 2 2 4 Business 40000 120000
3 Kalawati Chand Chhettri Elementary 4 3 7 Business 50000 85714
4 Kamala Devi Dhami Chhettri S.L.C 6 3 4 Business 30000 90000
5 Gopal Chand Chhettri Inter 6 5 7 Service 45000 77143
6 Dalla Dhami Chhettri Elementary 4 3 9 Business 50000 66667
Annex ‐ Page 20
S.N Name of HH Head / Owner Ethnicity
Education
Population Economic Status
Male Female Total Occupation Monthly Income (Rs)
Per Capita Income (Rs)
7 Kalu Chand Chhettri Elementary 4 3 11 Service 150000 163636
8 Rami Chand Chhettri Elementary 4 3 7 Business 50000 85714
9 Gangadatt Joshi Brahmin * 6 6 12 Business+Service 40000 40000
10 Ran Bdr. Chand Chhettri 4 2 6 Business 39000 78000
11 Arjun Chand Chhettri Inter 2 2 4 Agriculture 30000 90000
12 Piuskar Bdr. Chand Chhettri B.A 1 2 3 Agriculture 25000 100000
13 Lal Singh Bista Chhettri Inter 3 3 6 Service 45000 90000
14 Bahadur Nath Chhettri Inter 3 3 6 Agriculture 52000 104000
15 Dhan Bdr. Bista Chhettri S.L.C 6 3 9 Service 65000 86667
16 Bhim Bdr. Chand Chhettri S.L.C 3 1 4 Service 40000 120000
17 Kausilla Khatri Chhettri Elementary 1 1 2 Business 35000 210000
18 Mohan Dev Bhatta Brahmin S.L.C 3 4 7 Business 40000 68571
M4: Airport-Airighat Road 1 Mohan Singh Bhjandari Chhettri Inter 6 3 9 Service 50000 66667
2 Haridatt Joshi Brahmin S.L.C 6 4 10 Service 70000 84000
3 Man Bdr. Chand Chhettri Inter 5 5 10 Remittance 60000 72000
4 Bishna Devi Dhami Chhettri Elementary 2 2 4 Business 35000 105000
V5: Gully No-5 Road (Campus Road, North-South section)1 Deepak Rawat Chhettri Inter 2 3 5 Business 50000 120000
2 Tej Singh K.C Chhettri S.L.C 2 4 6 Business 35000 70000
3 Hiikmat Thaurathi Chhettri Inter 5 5 10 Business 45000 54000
4 Padam Bharati Chhettri Elementary 3 4 7 Business 30000 51429
5 Tek Raj Bharati Chhettri Elementary 4 4 8 Business 25000 37500
6 Ghanashyam Joshi Brahmin Elementary 6 6 12 Business 32000 32000
7 Raju Chand Chhettri Elementary 1 4 5 Business 35000 84000
8 Lal Bdr. Chand Chhettri Elementary 1 2 3 Business 25000 100000
Annex ‐ Page 21
S.N Name of HH Head / Owner Ethnicity
Education
Population Economic Status
Male Female Total Occupation Monthly Income (Rs)
Per Capita Income (Rs)
9 Bharat Chand Chhettri Elementary 3 4 7 Business 45000 77143
10 Megh Raj Bohora Brahmin S.L.C 4 3 7 Business 50000 85714
11 Ganesh Chand Chhettri M.A 1 3 4 Service 50000 150000
12 Chhetrapal Mehera Chhettri Elementary 2 2 4 Business 50000 150000
13 Madhav Parshad Bhatta Brahmin Inter 4 3 7 Business 50000 85714
14 Uddhav Dev Joshi Brahmin Inter 3 2 5 Business 50000 120000
15 Chandra Dev Joshi Brahmin Elementary 2 3 5 Business 50000 120000
16 Mahadev Bohora Chhettri Inter 3 2 5 Business 50000 120000
17 Laxmi Devi Joshi Brahmin Elementary 4 4 8 Business 50000 75000
18 Prem parkash Pathak Brahmin Inter 10 8 18 Business 100000 66667
19 Bijaya Nanda Joshi Brahmin Inter 3 2 5 Business 25000 60000
20 Hansa Devi Chand Chhettri Inter 2 3 5 Business 50000 120000
21 Lok Raj Bharati Chhettri S.L.C 3 1 4 Business 50000 150000
22 Devraj Mishra Brahmin Inter 2 3 5 Business 30000 72000
23 Keshav Raj Joshi Brahmin Inter 2 3 5 Business 50000 120000
24 Dilananda Giri Chhettri Inter 4 1 5 Business 100000 240000
25 Bisna Devi Palpali Dalit Inter 5 6 11 Business 100000 109091
26 Khem Palpali Dalit S.L.C 6 3 9 Business 100000 133333
27 Raghubir Bhatta Brahmin Elementary 4 4 8 Business 50000 75000
28 Chandra Devi Rawal Chhettri Elementary 2 2 4 Business 50000 150000
29 Sushila Vevi Rawal Chhettri Inter 2 3 5 Business 100000 240000
30 santos Aitwal Chhettri Inter 3 2 5 Business 100000 240000
31 Parbesh Partap Aitwal Chhettri Inter 3 3 6 Business 50000 100000
32 Bhupendra Aitwal Chhettri Inter 2 2 4 Business 50000 150000
33 Gyanendra Parshad Joshi Brahmin Inter 2 3 5 Business 50000 120000
34 Mahesh Parshad Joshi Brahmin Inter 3 4 7 Business 50000 85714
Annex ‐ Page 22
S.N Name of HH Head / Owner Ethnicity
Education
Population Economic Status
Male Female Total Occupation Monthly Income (Rs)
Per Capita Income (Rs)
35 Ganesh Joshi Brahmin Inter 3 4 7 Business 50000 85714
36 Tribhuwan Kumar Bhatta Brahmin M.A 2 2 4 Business 50000 150000
37 Gunakar Bhatta Brahmin S.L.C 3 3 6 Business 50000 100000
38 Hari Parshad Pandey Brahmin B.A 2 2 4 Business 50000 150000
39 Uma Chand Chhettri B.A 3 1 4 Business 50000 150000
40 Kedar Nath Pandey Brahmin B.A 2 2 4 Business 50000 150000
41 Krishna Parshad Aryal Brahmin BBM 2 2 4 Business 50000 150000
42 Laxmi Devi Aryal Brahmin Inter 3 2 5 Business 50000 120000
43 Gopal Sing Bohora Chhettri Inter 2 2 4 Business 50000 150000
44 Suraj Kharel Brahmin Inter 3 3 6 Business 30000 60000
45 Gyan Parshad Dumre Chhettri Inter 4 5 9 Business 25000 33333
46 Parbatman Khanal Brahmin S.L.C 2 6 8 Business 23000 34500
47 Tika Devi Kadel Chhettri Inter 2 3 5 Business 20000 48000
48 Duhurba Parshad Aryal Brahmin S.L.C 2 3 5 Business 20000 48000
49 Khagimaya Bhandari Chhettri Elementary 1 4 5 Business 20000 48000
50 Chandra Bdr. Malla Chhettri Elementary 6 4 10 Business 70000 84000
51 Harka Bdr. Malla Chhettri S.L.C 4 3 7 Business 100000 171429
52 Gopal Datt Joshi Brahmin B.A 7 5 12 Service 35000 3500053 Saraswati Rawal Chhettri Elementary 2 3 5 Business 50000 120000
54 Upendr Bdr. Khadka Chhettri S.L.C 5 5 10 Business 50000 60000
55 Jayaraj Saran Bhatta Brahmin S.L.C 4 3 7 Business 50000 85714
56 Dinesh Chandra Bhatta Brahmin B.A 2 3 5 Business 50000 120000
57 Devraj Saran Bhatta Brahmin Inter 2 2 4 Business 50000 15000058 Manoj Gupta Brahmin B.A 2 2 4 Business 50000 150000
59 Dev Raj Panta Chhettri Elementary 3 3 6 Business 50000 100000
60 Sivraj saran Bhatta Brahmin B.A 3 3 6 Business 50000 100000
Annex ‐ Page 23
S.N Name of HH Head / Owner Ethnicity
Education
Population Economic Status
Male Female Total Occupation Monthly Income (Rs)
Per Capita Income (Rs)
61 Gyanendra Bdr. Shah Chhettri S.L.C 3 4 7 Business 50000 85714
62 Sambhu Bharati Chhettri Inter 1 3 4 Business 100000 300000
63 Kalawati Joshi Brahmin Elementary 5 4 9 Business 50000 66667
64 Dan Bdr. Kunuwar Chhettri Elementary 3 2 5 Service 50000 120000
65 Bhakta Joshi Brahmin Inter 4 4 8 Business 40000 60000
66 Hari Shngh Bista Chhettri Elementary * * * * *
67 Janki Raiswal Chhettri Inter * * * * *
68 Parbati Chataut Chhettri Elementary 6 3 9 Service 100000 133333
69 Tarani Datt Chataut Chhettri Inter 3 3 6 Service 100000 200000
70 Bijayanand Joshi Brahmin Inter 3 2 5 Business 60000 144000
71 Nanda Dhami Chhettri Inter 4 1 5 Service 20000 48000
72 Mohan Singh Dhami Chhettri S.L.C 4 3 7 Business 50000 85714
73 Jayakisan Bhatta Brahmin Elementary 3 2 5 Business 20000 48000
74 Dilliraj Joshi Brahmin Inter 4 3 7 Business 50000 85714
75 Dharma Devi Rana Janjati Elementary 1 1 2 Business 25000 150000
76 Gopal Datt Joshi Brahmin S.L.C 3 2 5 Business 20000 48000
77 Tej Bdr. Bam * * * * * * *
78 Kisan Singh Thapa Chhettri Inter 2 1 3 Business 50000 200000
79 Laxmi Datt Pandey Brahmin Inter 6 5 11 Service 150000 163636
80 Laba Dev Pandey Brahmin Inter 6 6 12 Service 200000 200000
81 Basudev Bohora Chhettri Inter 3 1 4 Business 55000 165000
82 Karna Bdr. Chand Chhettri Inter 2 2 4 Business 40000 120000
83 Deelip Singh Bhandari Chhettri Inter 3 2 5 Service 50000 120000
84 Manoj Parshad Joshi Brahmin Inter 3 4 7 Business 100000 171429
85 Chandra Maya karki Chhettri Elementary 4 6 10 Service 30000 36000
86 Tara Devi Bhatta Brahmin S.L.C 1 3 4 Business 50000 150000
Annex ‐ Page 24
S.N Name of HH Head / Owner Ethnicity
Education
Population Economic Status
Male Female Total Occupation Monthly Income (Rs)
Per Capita Income (Rs)
87 Gangaram Giri Yogi Elementary 3 3 6 Business 70000 140000
88 Netra Chataut Brahmin PHd 3 1 4 Business 60000 180000
89 Balaram Ghimire Brahmin S.L.C 2 2 4 Business 50000 150000
90 Jayadatt Paudyal Brahmin Inter 4 1 5 Business 50000 120000
91 Bidhya Devi Kharel Brahmin Inter 2 1 3 Business 40000 160000
92 Tikaram Aryal Brahmin Inter 4 3 7 Business 50000 85714
93 Chintamani Kharel Brahmin Inter 2 1 3 Business 50000 200000
94 Ranbir Saran Bhatta Brahmin S.L.C 3 3 6 Business 25000 50000
95 Narain Datt Bhatta Brahmin S.L.C 4 4 8 Business 25000 37500
96 Raju Sharma Brahmin S.L.C 7 6 13 Business 50000 46154
97 Gokarna Bdr. Chand Chhettri Inter 7 3 10 Service 40000 48000
98 Amita Aryal Brahmin S.L.C 2 3 5 Business 20000 48000
99 Pabi Kafle Brahmin Inter 2 2 4 Business 20000 60000
100 Hema Devi Gurung Janjati Elementary 2 2 4 Service 30000 90000
101 Hom Bdr. Kunuwar Chhettri S.L.C 3 3 6 Business 30000 60000
102 Khadak Bdr. Kunuwar Chhettri S.L.C 3 1 4 Business 35000 105000
V-4: Gully No-4 Road (North-South section)
1 L.B Bista Chhettri S.L.C 3 4 7 Business 100000 171429
2 Tara singh Bohora Chhettri S.L.C 2 3 5 Business 50000 120000
3 Mohan Khatri Chhettri S.L.C 3 3 6 Business 50000 100000
4 Hariram Chaudhari Janjati S.L.C 3 3 6 Business 50000 100000
5 Chet raj Joshi Brahmin B.A 8 5 13 Service 50000 46154
6 Dhan Bdr.Ayer Chhettri S.L.C 3 3 6 Business 50000 100000
7 Khadak Singh Saud
8 Hira Devi Thagunna Chhettri Elementary 3 3 6 Business 50000 100000
9 Shankardatt Joshi Brahmin Inter 2 3 5 Business 50000 120000
Annex ‐ Page 25
S.N Name of HH Head / Owner Ethnicity
Education
Population Economic Status
Male Female Total Occupation Monthly Income (Rs)
Per Capita Income (Rs)
10 Chitramani Joshi Brahmin Elementary 3 4 7 Business 50000 85714
11 Manju Bhatta Brahmin Inter 2 2 4 Business 50000 150000
12 Haridatt Bhatta Brahmin Elementary 3 4 7 Business 50000 85714
13 Mamta Awasti Brahmin Inter 4 7 11 Business 50000 54545
14 Dhan Bdr. Bom Chhettri Inter 4 3 7 Business 50000 85714
15 Kiran Khadka Chhettri Elementary 3 3 6 Business 50000 100000
16 Gajadhar Joshi Brahmin Elementary 7 7 14 Business 50000 42857
17 Manorath Bhatta Brahmin Elementary 4 2 6 Business 50000 100000
18 Girija Shankar Parsad Brahmin Elementary 3 3 6 Business 50000 100000
19 Harish Chandra Bhatta Brahmin S.L.C 6 6 12 Business 100000 100000
20 Naina Ojha Brahmin Inter 2 3 7 Business 50000 85714
21 Deependra Bista Chhettri Inter 2 3 5 Business 150000 360000
22 Ganga Kharel Brahmin Inter 3 5 8 Service 50000 75000
23 Devidatt Bhatta Brahmin Inter 2 * 2 Business 100000 600000
24 Devaki Joshi Brahmin Elementary 2 3 5 Business 50000 120000
25 Chandrakala Panta Brahmin Inter 2 2 4 Business 50000 150000
26 Jaya Bdr. Pal Chhettri S.L.C 3 3 6 Business 100000 200000
27 Dambar Bdr. Pal Chhettri S.L.C 3 3 6 Business 100000 200000
28 Hari parsad Bhatta Brahmin Inter 2 1 3 Business 100000 400000
29 Laxman Singh Bista Chhettri Inter 3 3 6 Business 50000 100000
30 Narendra Khatri Chhettri Inter 3 3 6 Service 20000 40000
31 Dhirendra Bdr. Chand Chhettri Inter 1 2 3 Business 10000 40000
32 Saligram Kharel Brahmin S.L.C 2 3 5 Business 50000 120000
33 Narayan Baral Brahmin Inter 1 1 2 Business 50000 300000
34 Dhan Bdr. Chand Chhettri Inter 4 1 5 Business 50000 120000
35 Bamayanti Joshi Brahmin Elementary 4 2 4 Business 100000 300000
Annex ‐ Page 26
S.N Name of HH Head / Owner Ethnicity
Education
Population Economic Status
Male Female Total Occupation Monthly Income (Rs)
Per Capita Income (Rs)
36 Durga Bhandari Chhettri Elementary 1 1 2 Business 50000 300000
37 Parbati Devi Damai Dalit Elementary 2 1 3 Business 50000 200000
38 Tila Devi Damai Dalit Elementary 3 3 6 Service 35000 70000
39 P.K Shrestha Janjati S.L.C 5 4 9 Business 100000 133333
40 Dammari Bhatta Brahmin S.L.C 2 2 4 Business 40000 120000
41 Rama Shrestha Janjati S.L.C 1 3 4 Business 40000 120000
42 Deepa Devi Shrestha Janjati S.L.C 2 2 4 Business 30000 90000
43 Hripriya Pant Brahmin S.L.C 2 2 4 Business 15000 45000
44 Premdatt Joshi Brahmin B.A 2 2 4 Business 50000 150000
45 Prajapati Bista Chhettri Inter 3 2 5 Business 15000 36000
46 Dal Bdr.Bista Chhettri S.L.C 3 3 6 Service 25000 50000
47 Harka Bdr. Bista Chhettri S.L.C 3 3 6 Service 25000 50000
48 Jahar Singh Pwali Chhettri Elementary 4 5 9 Business 25000 33333
49 Madhav Joshi Brahmin B.A 2 2 4 Business 70000 210000
50 Shreeram Chataut Chhettri Elementary 3 6 9 Business 100000 133333
51 Hajari Singh Pujara Brahmin Elementary 2 2 4 Business 50000 150000
52 Dharma Singh Rawal Chhettri Inter 2 2 4 Business 100000 300000
53 Dhana Devi Bhatta Brahmin Elementary 4 3 7 Business 50000 85714
54 Niraj Saud Chhettri Inter 1 3 4 Business 75000 225000
55 Padam Thakurathi Chhettri Elementary 3 1 4 Business 75000 225000
56 Godawari Bhatta Brahmin Elementary 5 3 8 Business 75000 112500
57 Sunil Panta Brahmin B.A 2 2 4 Business 75000 225000
58 Tek Bdr. Kunuwar Chhettri B.A 3 3 6 Business 75000 150000
59 Madan Singh Thagunna Chhettri S.L.C 3 1 4 Business 75000 225000
60 Sova Karki Chhettri MBBS 1 2 3 Business 75000 300000
61 Kalu Bohora Chhettri S.L.C 3 3 6 Business 30000 60000
Annex ‐ Page 27
S.N Name of HH Head / Owner Ethnicity
Education
Population Economic Status
Male Female Total Occupation Monthly Income (Rs)
Per Capita Income (Rs)
62 Gorakh Bdr. Bista Chhettri Elementary 4 4 8 Business 30000 45000
63 Lalit Bdr. Bohora Chhettri S.L.C 3 4 7 Business 75000 128571
64 Lalit Parsad Bhatta Brahmin Inter 2 3 5 Business 75000 180000
65 Laxman Chand Chhettri Inter 2 2 4 Business 40000 120000
66 Kashi Singh Karki Chhettri
67 Gyanu Bohara Chhettri Inter 2 2 4 Business 40000 120000
68 Parkash Chand Chhettri Inter 3 1 4 Business 50000 150000
69 Padama devi Bhatta Brahmin Inter 2 2 4 Business 50000 150000
70 Rudra Parsad Bhatrai Brahmin Inter 3 1 4 Business 50000 150000
71 Mina Baral Chhettri Elementary 2 2 4 Business 20000 60000
72 Padam Raj Pandey Brahmin Inter 2 2 4 Business 15000 45000
73 Mahesh Pandey Brahmin Inter 2 2 4 Service 30000 90000
74 Dhan Bdr. Chand Chhettri S.L.C 4 3 7 Business 20000 34286
V-3 : Gully No-3 Road (North-South Section)
1 Basanti Devi Pandey Brahmin Elementary 5 4 9 Business 100000 133333
2 Ambika devi Bhandari Chhettri S.L.C 6 3 9 Business 100000 133333
3 Parmananda Bhandari Chhettri B.A 6 3 9 Business 100000 133333
4 Top Bdr. K.C Chhettri Elementary 2 2 4 Business 80000 240000
5 Bhim Pandey Brahmin Elementary 3 4 7 Business 50000 85714
6 Bhuwan Pandey Brahmin B.A 3 4 7 Business 50000 85714
7 Devraj Mishra Brahmin 4 1 5 Service 20000 48000
8 Prem Singh Bhatta Brahmin 4 3 7 Business 50000 85714
9 Hikmat Saud Chhettri 3 2 5 Business 20000 48000
10 Ganesh Saud Chhettri 4 3 7 Business 50000 85714
11 Tej Bdr. Bhandari Chhettri Inter 3 2 5 Business 30000 72000
12 Sundara Dev Bhandari Chhettri Elementary 3 2 5 Business 30000 72000
Annex ‐ Page 28
S.N Name of HH Head / Owner Ethnicity
Education
Population Economic Status
Male Female Total Occupation Monthly Income (Rs)
Per Capita Income (Rs)
13 Chandra Bdr. Chand Chhettri Inter 5 3 8 Business 30000 45000
14 Bhan Bdr. Chand Chhettri Inter 6 6 12 Business 40000 40000
15 Bashu Dev Deuba Chhettri Elementary 2 2 4 Business 50000 150000
16 Nara Bdr. Bista Chhettri Elementary 4 2 6 Business 20000 40000
17 Kamala Devi Kathayat Chhettri Elementary 4 4 8 Business 22000 33000
18 Dal Bdr. Shah Chhettri S.L.C 4 3 7 Business 30000 51429
19 Gorakh Bdr. Khati Chhettri Elementary 3 4 7 Business 25000 42857
20 Bhim Datta Bhatta Brahmin S.L.C 3 3 6 Business 25000 50000
21 Yagyaraj Paudyal/Madan Brahmin Inter 3 3 6 Business 50000 100000
22 Rupkiswor Gupta Chhettri S.L.C 3 2 5 Business 100000 240000
23 Bharat Nepal Brahmin S.L.C 9 9 18 Business 100000 66667
24 Nar Bdr. Pal Chhettri Elementary 1 1 2 Business 50000 300000
25 Kailap Bhatta Brahmin Inter 2 2 4 Business 50000 150000
26 Ghanashyam Kalauni Brahmin B.A 3 2 5 Business 50000 120000
27 Dhan Bdr. Bom Chhettri Elementary 4 6 10 Business 50000 60000
28 Anil Dhungana/Joshi Brahmin Inter 3 4 7 Service 35000 60000
29 Yasoda Pathak/ Tiwari Brahmin M.A 3 2 5 Business 50000 120000
30 Jeetendra Parsad Bhatta Brahmin S.L.C 2 2 4 Business 50000 150000
31 Mahendra Bdr Kunwor Chhettri Inter 3 2 5 Business 30000 72000
32 Ram Singh Ter Chhettri Elementary 7 10 17 Business 100000 70588
33 Ram Pd Sapkota Brahmin S.L.C 5 4 9 Business 100000 133333
34 Arjun Prakash Upreti Brahmin S.L.C 4 3 7 Business 50000 85714
35 Min Raj Bhatta Brahmin S.L.C 4 6 10 Business 50000 60000 36 Karan Shah Chhettri Elementary 4 3 7 Business 50000 85714
37 Narendra Raj Bohora Brahmin S.L.C 3 3 6 Business 50000 100000
38 Jagdish Upreti Brahmin Elementary 3 3 6 Business 100000 200000
Annex ‐ Page 29
S.N Name of HH Head / Owner Ethnicity
Education
Population Economic Status
Male Female Total Occupation Monthly Income (Rs)
Per Capita Income (Rs)
39 Ratan Saud
40 Karan Bdr Singh Chhettri Elementary 2 3 5 Business 100000 240000
41 Ashok Kumar Dewal Chhettri S.L.C 4 3 7 Business 50000 85714
42 Dhawal Bdr Chand Chhettri Elementary 2 3 4 Business 100000 300000
43 Kalpana KC Chhettri Elementary 3 3 6 Business 50000 100000
44 Jayamati Devi Bhatta Brahmin Inter 2 2 4 Business 100000 300000
45 Madan Panta Brahmin Elementary 6 5 11 Business 50000 54545
46 Dhan Singh Rawal Chhettri Elementary 3 3 6 Business 50000 100000
47 Belu Devi Bhata Brahmin Elementary 3 3 6 Business 50000 100000
48 Kunti Bohora Chhettri Elementary 2 2 4 Business 50000 150000
49 Harish Chand Brahmin Elementary 5 4 9 Business 50000 66667
50 Jamunaganga Devi Joshi Brahmin Elementary 4 3 7 Business 50000 85714
51 Tanka Pd. Bhatta Brahmin Elementary 3 2 5 Business 50000 120000
52 Radhika Devi bhatta Brahmin Elementary 4 4 8 Business 50000 75000
53 D.r Rajendra Bhatta Brahmin PHD 3 2 5 Service 100000 240000
54 Deepak Kharel Brahmin 3 2 5 Business 40000 96000
55 Rishi Kharel Brahmin Inter 4 4 8 Business 50000 75000
56 Yadu Raj Joshi Brahmin Inter 3 3 6 Service 50000 100000
57 Nar Singh Dhami Chhettri S.L.C 2 3 5 Business 150000 360000
58 Tarun Lakhera Brahmin Inter 3 3 6 Business 50000 100000
59 Padama Saud Bhandari Chhettri PhD 2 2 4 Service 50000 150000
60 Furua Kalauni Chhettri Elementary 1 2 3 Business 15000 60000
61 Megh Raj Bhatta Brahmin S.L.C 3 2 5 Business 25000 60000
62 Kashidatt Bhatta Brahmin Elementary 3 1 4 Business 15000 45000
63 Kalpana Karki Chhettri Inter 3 2 5 Business 150000 360000
V-2: Gully No-2 Road (North-South section)
Annex ‐ Page 30
S.N Name of HH Head / Owner Ethnicity
Education
Population Economic Status
Male Female Total Occupation Monthly Income (Rs)
Per Capita Income (Rs)
1 Ramesh Pandey Brahmin M.A 2 2 4 Service 100000 300000
2 Laxi Pandey Brahmin Elementary 2 2 4 Business 50000 150000
3 Arjundatt Pandey Brahmin B.A 4 5 9 Business 50000 66667
4 Gopaldatt Bhatta Brahmin Elementary 7 8 15 Business 50000 40000
5 Jamuna Devi Bhatta Brahmin Elementary 6 6 12 Business 50000 50000
6 Bhojraj Bhatta Brahmin Elementary 4 2 6 Business 50000 100000
7 Rameswor Upreti Brahmin Elementary 3 4 7 Business 50000 85714
8 Neha Singh Pal Chhettri S.L.C 4 4 8 Business 50000 75000
9 Tikadatt Paneru Brahmin S.L.C 3 3 6 Business 50000 100000
10 Rajesh Gupta Chhettri S.L.C 2 2 4 Business 50000 150000
11 Parmananda Paneru Brahmin Elementary 4 3 7 Business 30000 51429
12 Karunakar Paneru Brahmin Elementary 4 3 7 Business 30000 51429
13 Laxmi Devi Bhatta Brahmin Elementary 3 3 6 Business 30000 60000
14 Tek Khadka Chhettri Inter 2 4 6 Business 30000 60000
15 Ram Parshad Pandey Brahmin S.L.C 4 4 8 Business 30000 45000
16 Sher Singh Ter Chhettri S.L.C 3 3 6 Business 30000 60000
17 Shankar Bdr. Bista Chhettri S.L.C 3 1 4 Business 30000 90000
18 Madan Singh Aiyar Chhettri Elementary 3 3 6 Business 30000 60000
19 Dharma Raj Bhatta Brahmin S.L.C 4 5 9 Business 30000 40000
20 Dev Raj Bhatta Brahmin Inter 4 5 9 Business 30000 40000
21 Jayalal Bhatta Brahmin Elementary 3 3 6 Business 50000 100000
22 Bhoj Raj Bhatta Brahmin Elementary 4 2 6 Business 50000 100000
23 Uddhav Singh Bista Chhettri Elementary 3 2 5 Business 50000 120000
24 Nar Bdr. Bista Chhettri Elementary 3 3 6 Business 50000 100000
25 Kiswar Jairu Chhettri Inter 2 3 5 Business 50000 120000
26 Nandalal Bohora Brahmin S.L.C 3 3 6 Business 50000 100000
Annex ‐ Page 31
S.N Name of HH Head / Owner Ethnicity
Education
Population Economic Status
Male Female Total Occupation Monthly Income (Rs)
Per Capita Income (Rs)
27 Motilal Bohora Brahmin S.L.C 5 3 8 Business 50000 75000
28 Madana Devi Bohora Brahmin Elementary 5 2 7 Business 50000 85714
29 Hari Parshad Bohora Brahmin B.A 2 3 5 Business 50000 120000
30 Siddharaj Bohora Brahmin Inter 3 2 5 Business 50000 120000
31 Sita K.C Chhettri Inter 5 5 10 Service 100000 120000
32 Iswori Devi Bohora Brahmin Elementary 5 5 10 Business 30000 36000
33 Urmila Kharel Brahmin Inter 2 2 4 Business 30000 90000
34 Tika Devi Kharel Brahmin Elementary 3 3 6 Business 60000 120000
35 Ram Parshad Kharel Brahmin Inter 3 3 6 Business 30000 60000
36 Navraj Kharel Brahmin Inter 2 2 4 Business 30000 90000
37 Manmati Giri Chhettri Elementary 3 1 4 Business 50000 150000
38 Nisha Shah Muslim Inter 2 3 5 Business 200000 480000
39 Rasmi Gupta Chhettri Inter 2 2 5 Business 15000 36000
40 Pawan Kumar Sarwagi Chhettri Inter 4 2 6 Business 100000 200000
41 Birendra Kumar Sangai Chhettri Inter 3 2 5 Business 150000 360000
42 Dhan Bdr. Chand Chhettri Inter 5 4 9 Business 25000 33333
43 Hajari Chand Chhettri Inter 2 3 5 Business 50000 120000
44 Ram Bdr. Kunuwar Chhettri Elementary 6 5 11 Business 200000 218182
45 Laxmi Bhatta Brahmin B.A 1 2 3 Service 50000 200000
46 Pratap Chand Chhettri Elementary 6 4 10 Service 50000 60000
47 Ram Bdr. Kunuwar Chhettri Inter 2 2 4 Service 50000 150000
48 Narendra Paneru Brahmin BBS 2 3 5 Business 50000 120000
49 Damodar Athola Joshi Brahmin Elementary 6 8 14 Business 100000 85714
50 Laxi Devi Paneru Brahmin Elementary 5 4 9 Business 100000 133333
51 Dwarika Devi Bista Chhettri Elementary 3 1 4 Business 100000 300000
52 Ramdular Jaiswal Chhettri Elementary 2 5 7 Business 50000 85714
Annex ‐ Page 32
S.N Name of HH Head / Owner Ethnicity
Education
Population Economic Status
Male Female Total Occupation Monthly Income (Rs)
Per Capita Income (Rs)
53 Deep Raj Chataut Chhettri 3 2 5 Business 75000 180000
54 Padam Bdr. Thakurathi Chhettri Inter 5 5 10 Business 28000 33600
55 Kalpana Thapa Chhettri BA 2 2 4 Business 20000 60000
56 Motimaya Sharma Brahmin Elementary 1 2 3 Service 50000 200000
57 Ganga Kafle Brahmin Elementary 2 2 4 Business 25000 75000
58 Narendra Khatri Chhettri Elementary 2 2 4 Business 50000 150000
59 Binod Joshi Brahmin S.L.C 2 3 5 Business 50000 120000
60 Srijana Rawal Chhettri Elementary 4 5 9 Business 50000 66667
61 Bir Bdr.Kunwor Chhettri Elementary 4 5 8 Business 30000 45000
62 Nirmal Lamichhane Dalit Elementary 4 4 9 Business 30000 40000
63 Madan Sunar Dalit Elementary 5 5 10 Business 30000 36000
64 Shivlal Nyeupane Brahmin Inter 3 3 6 Business 50000 100000
65 Naresh Agrawal Chhettri Inter 2 1 3 Business 100000 400000
66 Radhika Sunar Dalit Elementary 1 3 4 Business 40000 120000
67 Rameswor Bhatta Brahmin M.A 6 7 13 Service 100000 92308
68 Sushil Dewal Chhettri Inter 3 3 6 Business 200000 400000
69 Megh Raj Bohora Chhettri Elementary 3 2 5 Business 40000 96000
70 Ramchandra Bohora Chhettri Elementary 3 3 6 Business 40000 80000
71 Kamala Devi Bohora Chhettri Elementary 3 3 6 Business 50000 100000
72 Govinda Raj Joshi Brahmin Inter 2 1 3 Business 50000 200000
73 Mukesh Agrawal Chhettri Inter 1 4 5 Business 30000 72000
74 Kaviraj Bhatta Brahmin Inter 2 1 3 Business 40000 160000
75 Bhojraj Joshi Brahmin L.L.B 4 8 12 Business 200000 200000
76 Chitra Nepal Brahmin Inter 2 3 5 Service 100000 240000
77 Iswori Devi Chilwal Brahmin Inter 5 2 7 Business 40000 68571
78 Laxmi Devi Tiwari Brahmin S.L.C 3 3 6 Business 30000 60000
Annex ‐ Page 33
S.N Name of HH Head / Owner Ethnicity
Education
Population Economic Status
Male Female Total Occupation Monthly Income (Rs)
Per Capita Income (Rs)
79 Ganesh Raj Bohora Chhettri 2 3 5 Business 75000 180000
80 Sunita Budha Chhettri S.L.C 3 1 4 Business 50000 150000
81 Chandra Datt Joshi Brahmin Inter 3 2 5 Business 50000 120000
82 Madhusudan Aryal Brahmin Inter 2 2 4 Business 40000 120000
83 Gangaram Rawal Chhettri Elementary 3 4 7 Business 50000 85714
84 Somraj Aryal Brahmin Inter 4 2 6 Business 50000 100000
85 Gopal Bhusal Brahmin Inter 2 3 5 Business 50000 120000
86 Homlal Bhusal Brahmin Inter 3 3 6 Business 50000 100000
87 Ishwori Devi Bhatta Brahmin Inter * 2 2 Business 50000 300000
88 Tek Bdr. Sunar Dalit Inter 4 3 7 Business 100000 171429
89 Min Bdr. Kathayat Chhettri S.L.C 4 4 8 Business 50000 75000
V-1: Gully No-1(Shalgadhi Road, North-South Section)1 Bhairav Bdr. Aiyar Chhettri Elementary 6 9 15 Business 50000 40000
2 Suman Dewal Chhettri Elementary 1 1 2 Business 10000 60000
3 Ashok Kumar Dewal Chhettri Elementary 4 3 7 Business 19000 32571
4 Bhupendra Rawal Chhettri B.A 3 2 5 Business 35000 84000
5 Rajendra Rawal Chhettri B.A 2 2 4 Business 30000 90000
6 Bhoj Raj Bohora Chhettri Inter 3 1 4 Business 30000 90000
7 Padam Bdr. Aiyar Chhettri Inter 5 5 10 Service 30000 36000
8 Hariom Dewal Chhettri B.A 1 1 2 Business 40000 240000
9 Harinanda Pd.NirajKumar Chhettri Elementary 2 2 4 Business 40000 120000
10 Nannelal Hariom Chhettri Elementary 5 5 10 Service 50000 60000
11 Kailash Gupta Chhettri S.L.C 4 1 5 Business 19000 45600
12 Bijaya Dewal Chhettri S.L.C 3 3 6 Business 30000 60000
13 Padam Bdr. Thakurathi Chhettri S.L.C 4 2 6 Business 20000 40000
14 Harilal Thakurathi Chhettri S.L.C 4 5 9 Business 100000 133333
Annex ‐ Page 34
S.N Name of HH Head / Owner Ethnicity
Education
Population Economic Status
Male Female Total Occupation Monthly Income (Rs)
Per Capita Income (Rs)
15 Maheswor Chataut Brahmin S.L.C 3 2 5 Business 40000 96000
16 Dansingh Thakurathi Chhettri Inter 2 3 5 Business 20000 48000
17 Omprakash Gupta Chhettri Elementary 5 3 8 Business 40000 60000
18 Rajiv Dewal Chhettri Elementary 2 2 4 Business 40000 120000
19 Rajeswori Devi Dewal Chhettri Elementary 6 8 14 Business 40000 34286
20 Dharmendra Gupta Chhettri Inter 2 2 4 Business 100000 300000
21 Parsuram Gautam Chhettri Elementary 2 2 4 Business 30000 90000
22 Hira Devi Bohora Chhettri C.A 3 2 5 Business 25000 60000
23 Kanhyalal Dewal Chhettri Elementary 6 4 10 Business 27000 32400
24 Gopal Dewal Chhettri Elementary 2 3 5 Business 25000 60000
25 Dambar Datt Bhatta Chhettri S.L.C 4 1 5 Business 20000 48000
26 Balaram Chataut Brahmin S.L.C 5 3 8 Business 50000 75000
27 Kirta Bdr. Johra Chhettri Elementary 5 7 12 Service 100000 100000
28 Dharma Raj Joshi Brahmin Inter 4 4 8 Business 100000 150000
29 Durga Devi Johra Chhettri Elementary 4 7 12 Business 100000 100000
30 Dharma singh Rawal Chhettri Elementary 2 2 4 Business 30000 90000
31 Abdul Samim Janjati Elementary 2 5 7 Service 100000 171429
32 Maina Devi Bhandari Chhettri Elementary 5 6 11 Business 100000 109091
33 Parbati Devi Khadayat Chhettri Elementary 13 6 19 Business 100000 63158
34 Abdul Samim Janjati Elementary 2 5 7 Business 100000 171429
35 Indra Singh Rawal Chhettri S.L.C 2 4 6 Business 50000 100000
36 Lal Singh Thakurathi Chhettri S.L.C 3 3 6 Business 50000 100000
37 Padam Raj Bohora Brahmin S.L.C 2 4 6 Business 50000 100000
38 Bhubaneswori Kunwar Chhettri
39 Geeta Kharel Brahmin Elementary 9 6 15 Business 100000 80000
40 Pabitra Aryal Brahmin Elementary 4 4 8 Business 100000 150000
Annex ‐ Page 35
S.N Name of HH Head / Owner Ethnicity
Education
Population Economic Status
Male Female Total Occupation Monthly Income (Rs)
Per Capita Income (Rs)
41 Harka Singh Aiyar Chhettri S.L.C 9 6 15 Business 40000 32000
42 Bimal Khadayat Chhettri
43 Bhubaneswori Bogati Chhettri
44 Hem Raj Bohora Chhettri
45 Dinesh Shrestha Janjati Inter 2 3 5 Business 30000 72000
46 Dev Singh Ter Chhettri Inter 5 4 9 Business 30000 40000
47 Gagan Bdr Singh Chhettri
48 Khagesh Pd. Bhatta Brahmin Inter 5 2 7 Business 50000 85714
49 Siddha Raj Bhatta Brahmin Inter 7 6 13 Business 100000 92308
50 Deepu Budhayar Chhettri Inter 2 2 4 Business 30000 90000
51 Ammar Budharar Chhettri Inter 2 2 4 Business 30000 90000
52 Keshav Raj Panta Brahmin B.A 3 1 4 Business 100000 300000
53 Bimal Raj Panta Brahmin Inter 2 2 4 Business 50000 150000
54 Pawan Khadayat Chhettri B.A 4 6 10 Business 50000 60000
55 Lal Bdr. Khadayat Chhettri ISC 4 4 8 Business 50000 75000
56 Mukesh Rawal Chhettri BSC 2 2 4 Business 50000 150000
57 Megh Raj Bohora Chhettri S.L.C 4 4 8 Business 100000 150000
58 Dan Singh Thakurathi Chhettri Inter 3 3 6 Business 50000 100000
59 Nawal Singh Saud
60 Krishnadatt Chataut Brahmin S.L.C 4 5 9 Business 25000 33333
61 Shiv Raj Bhatta Brahmin B.A 2 3 5 Service 40000 96000
62 Niraj Gupta Brahmin B.A 2 2 4 Business 60000 180000
63 Yagya Raj Bhatta Brahmin B.A 3 1 4 Business 40000 120000
64 Yagya Raj Bhatta Chhettri Inter 2 2 4 Business 50000 150000
65 Parkash Rawal Chhettri Inter 3 2 5 Business 30000 72000
66 Samser rawal Chhettri B.A 4 1 5 Service 38000 91200
Annex ‐ Page 36
S.N Name of HH Head / Owner Ethnicity
Education
Population Economic Status
Male Female Total Occupation Monthly Income (Rs)
Per Capita Income (Rs)
67 Lal Bdr. Rawal Chhettri Inter 3 6 9 Business 100000 133333
68 Amar Shingh Khadayat Chhettri Elementary 2 2 4 Business 50000 150000
69 Tek Bdr. Saud Chhettri Elementary 3 4 7 Business 30000 51429
70 Uday Saud Chhettri Inter 3 2 5 Service 40000 96000
71 Bam Dev Chataut Brahmin Inter 4 2 6 Business 100000 200000
72 Chhotelal Batuwa Chhettri Elementary 9 4 13 Business 100000 92308
73 Raj Kumar Dewal Chhettri Inter 6 4 10 Business 50000 60000
74 Umashankar Dewal Chhettri Elementary 7 4 11 Business 50000 54545
75 Bhuwan Chataut Chhettri Elementary 10 4 14 Business 50000 42857
76 Ganesh Chataut Chhettri Inter 4 3 7 Business 50000 85714
77 Bal Devi Kharel Brahmin Elementary 1 2 3 Business 100000 400000
78 Bashu Dev Bohora Chhettri Inter 2 2 4 Bsiness 50000 150000
79 Mohan Singh Bista Chhettri Inter 3 3 6 Bsiness 50000 100000
80 Kalpana devi Bhusal Brahmin S.L.C 2 3 5 Bsiness 100000 240000
81 Narai Bhatta Brahmin Elementary 3 3 6 Bsiness 100000 200000
82 Anita Joshi Brahmin Elementary 2 4 6 Service 100000 200000
83 Bhuwan Kharel Brahmin Inter 2 3 5 Bsiness 100000 240000
84 Poonam Bhatta Brahmin S.L.C 3 3 6 Business 20000 40000
85 Basanti Thagunna Chhettri Elementary 2 3 5 Business 100000 240000
86 Sova Dewal Chhettri Elementary 1 2 Business 100000 600000
87 Mandhari Devi Giri Yogi Elementary 10 4 14 Business 50000 42857
88 Laxman Singh Bista Chhettri Inter 4 3 7 Business 50000 85714
89 Hema Pandey Brahmin S.L.C 2 2 4 Business 50000 150000
90 Rupa Aryal Brahmin S.L.C 4 1 5 Business 50000 120000
91 Cholanath Bhandari Chhettri S.L.C 2 3 5 Business 50000 120000
92 Man Singh Mahara Chhettri Inter 2 2 4 Business 50000 150000
Annex ‐ Page 37
S.N Name of HH Head / Owner Ethnicity
Education
Population Economic Status
Male Female Total Occupation Monthly Income (Rs)
Per Capita Income (Rs)
93 Sher Shingh Bhandari Brahmin
94 Bir Bdr. Sunar Chhettri Inter 3 3 6 Business 100000 200000
95 Omkar Panta Brahmin Inter 2 2 4 Business 100000 300000
96 Prakash Shah Chhettri B.Com 3 3 6 service 100000 200000
97 Hari Datt Bhatta Brahmin S.L.C 5 4 9 Business 50000 66667
V6: Malpot/Napi Karalaya-E/W Highway) 1 Harilal Joshi Brahmin M.A 3 2 5 Service 25000 60000
2 Patiram Chunara Dalit S.L.C 3 5 8 Business 20000 30000
3 Tek Raj Bhatta Brahmin Inter 2 1 3 Business 25000 100000
H1: East-West Gully-1 1 Gajendra Bdr. Shah Chhettri S.L.C 3 4 7 Business 50000 85714
2 Shambhu Bharati Yogi Inter 1 3 4 Business 100000 300000
3 Chintamani Joshi Brahmin Elementary 3 4 7 Business 50000 85714
4 Manju Bhatta Brahmin Inter 2 2 4 Business 50000 150000
5 Shreeram Chataut Brahmin Elementary 3 6 9 Business 100000 133333
6 Hajari Singh Pujara Chhettri Elementary 2 2 4 Business 50000 150000
7 Gopal Singh Budha Chhettri Elementary 3 4 7 Business 30000 51429
8 Bhuban Pandey Brahmin Inter 2 1 3 Business 50000 200000
9 Devraj Mishra Brahmin Inter 3 4 7 Business 50000 85714
10 Min Raj Bhatta Brahmin S.L.C 4 6 10 Business 50000 60000
11 Prem Shah Chhettri Elementary 4 3 7 Business 50000 85714
12 Narendra Bohora Brahmin Inter 3 3 6 Business 50000 100000
13 Deepak Gupta Chhettri Inter 4 5 9 Business 25000 33333
14 Padam Bdr. Bhandari Chhettri Elementary 2 3 5 Service 40000 96000
15 Laxmi Datt Bhatta Brahmin Elementary 2 2 4 Business 60000 180000
16 Rudra Singh Bhandari Chhettri Elementary 3 1 4 Business 40000 120000
Annex ‐ Page 38
S.N Name of HH Head / Owner Ethnicity
Education
Population Economic Status
Male Female Total Occupation Monthly Income (Rs)
Per Capita Income (Rs)
17 Karunakar Paneru Brahmin Elementary 3 1 4 Business 20000 60000
18 Harilal Bhatta Brahmin S.L.C 3 3 6 Business 20000 40000
19 Kalpana Thapa 3 2 5 Service 100000 240000
20 Padam Bdr. Thakurathi Chhettri S.L.C 4 2 6 Business 200000 400000
21 Shanti Damai Dalit Elementary 4 5 9 Business 50000 66667
22 kalu Singh+jagat Bhandari Chhettri Inter 9 5 13 Business 100000 92308
23 Padam Bdr. Thakurathi Chhettri S.L.C 6 4 10 Business 50000 60000
H2: East-West Gully-2
1 Mohan Singh Dhami Chhettri Inter 4 3 7 Business 50000 85714
2 Jaya Kisan Bhatta Brahmin Elementary 4 3 7 Business 100000 171429
3 Haris Chandra Bhatta Brahmin S.L.C 4 6 10 Business 100000 120000
4 Laba Raj Bhatta Brahmin Inter 3 1 4 Business 20000 60000
5 Sunil Panta Brahmin B.A 2 2 4 Business 75000 225000
6 Madan Paudyal Brahmin Elementary 5 5 10 Business 21000 25200
7 Tikaram Bohora Brahmin S.L.C 2 2 4 Business 20000 60000
8 Khem Raj Bohora Brahmin S.L.C 4 2 6 Business 20000 40000
9 Govinda Ballav Joshi Brahmin 3 4 7 Business 50000 85714
10 Jaimati Devi Bhatta Brahmin Inter 2 2 4 Business 100000 300000
11 Bashudev Bohora Chhettri Inter 2 2 4 Bsiness 50000 150000
12 Sita Devi K.C Chhettri Inter 5 5 10 Service 100000 120000
13 Ganesh Bohora Chhettri B.A 4 4 8 Service 50000 75000
14 Kamala Devi Bohora Chhettri Elementary 3 3 6 Business 40000 80000
15 Durga Devi Jora Chhettri Elementary 3 2 5 Business 40000 96000
16 Dharma Raj joshi Brahmin Inter 4 4 8 Business 100000 150000
H-3: Hospital Road (Gully 6 to Gully 1/ East-West Gully-3) None
Annex ‐ Page 39
S.N Name of HH Head / Owner Ethnicity
Education
Population Economic Status
Male Female Total Occupation Monthly Income (Rs)
Per Capita Income (Rs)
H-4: Campus Road (Janki tole) to Gully 1( East-West Gully-4) None
H-5: Sarswati Tole Road 1 (East West Gully-5, Katan Area)1 Bisnudatt Bhatta Brahmin B.A 3 2 5 Service 100000 240000
2 Bajir Singh Aiyar Chhettri Elementary 2 2 4 Business 45000 135000
3 Khagendra Chand Chhettri Inter 3 4 7 Service 35000 60000
4 Ganga Datt Joshi Brahmin B.A 3 2 5 Service 35000 84000
5 Rajendra Chand Chhettri Inter 3 3 6 Service 35000 70000
6 Anandi Panta Brahmin B.A 2 1 3 Service 30000 120000
7 Parmeswori Pandey Brahmin Elementary 5 7 12 Business 100000 100000
8 Hom Bdr. Panthi Chhettri S.L.C 4 1 5 Business 18000 43200
9 Dharma Nanda Bhatta Chhettri S.L.C 3 3 6 Business 30000 60000
10 Sashi Ojha Chhettri S.L.C 4 2 6 Business 20000 40000
11 Laxman Singh Bhandari Chhettri S.L.C 4 5 9 Business 100000 133333
12 Ganesh Bohora Brahmin S.L.C 3 2 5 Business 40000 96000
13 Narayan Singh Saud Chhettri Inter 5 3 8 Service 50000 75000
14 Kamala Bohora Chhettri Elementary 4 5 9 Business 25000 33333
15 Man Bdr. Sunar Dalit Elementary 2 3 5 Service 40000 96000
16 Tikaram Bhatta Brahmin Elementary 2 2 4 Business 60000 180000
17 Tekendra Bhatta Brahmin B.A 3 3 6 Business 40000 80000
18 Damodar Pandey Brahmin BSC 5 4 9 Service 50000 66667
19 Dr. Bhojraj Panta Chhettri 2 2 4 Business 50000 150000
20 Bishnu Awasti Chhettri Elementary 3 4 7 Business 30000 51429
21 Puspamani Bhatta Brahmin Inter 2 1 3 Business 50000 200000
22 Keshav Nayak Chhettri Elementary 2 1 3 Business 50000 200000
23 Kamal Shrestha Janjati S.L.C 3 4 7 Business 50000 85714
Annex ‐ Page 40
S.N Name of HH Head / Owner Ethnicity
Education
Population Economic Status
Male Female Total Occupation Monthly Income (Rs)
Per Capita Income (Rs)
24 Gauri Datt Joshi Brahmin Inter 2 2 4 Service 35000 105000
25 Lalitananda Joshi Brahmin S.L.C 4 2 6 Business 27000 54000
26 Somraj Aryal Brahmin 3 3 6 Service 40000 80000
27 Man Singh Rawat Chhettri S.L.C 3 4 7 Business 100000 171429
28 Purna Raj Bhatta Brahmin S.L.C 4 1 5 Business 40000 96000
H-6:Sarswati Tole Road 2 (East West Gully-6, Katan Area)1 Devaki Bam Chhettri Elementary 4 2 6 Business 50000 100000
2 Kapil Joshi Brahmin Inter 3 1 4 Business 100000 300000
3 Shyam Chand Chhettri Inter 3 3 6 Service 25000 50000
4 Basant Bdr. Singh Chhettri Inter 3 3 6 Service 25000 50000
5 Parwati Devi Chand Chhettri B.A 2 1 3 Service 30000 120000
6 Tara Joshi Brahmin B.A 3 2 5 Service 30000 72000
7 Siddharaj Bhatta Brahmin B.A 2 3 5 Service 30000 72000
8 Mohandev Joshi Brahmin B.A 3 6 9 Service 30000 40000
9 Dattaram Dasrath Bhatta Brahmin Elementary 3 3 6 Business 30000 60000
10 Manmati Chand Chhettri Elementary 2 4 6 Business 30000 60000
11 Dal Bdr. Chand Chhettri S.L.C 6 5 11 Business 50000 54545
H-7: Sarswati Tole Road 3 (East West Gully-7, Katan Area)1 Pushkar Giri Chhettri Inter 3 1 4 Service 25000 75000
2 Gagan Giri Chhettri Inter 3 1 4 Service 30000 90000
3 Dilmaya Bhatta Brahmin S.L.C 4 3 7 Service 50000 85714
4 Tek Raj Panta Brahmin PhD 3 2 5 Service 25000 60000
5 Sova Devi Joshi Brahmin S.L.C 2 1 3 Service 35000 140000
6 Kapil Panta Brahmin Inter 3 1 4 Service 40000 120000
7 Karan Nath Chhettri Inter 4 2 6 Service 25000 50000
8 Komala Devi Chand Chhettri Inter 2 2 4 Business 30000 90000
Annex ‐ Page 41
S.N Name of HH Head / Owner Ethnicity
Education
Population Economic Status
Male Female Total Occupation Monthly Income (Rs)
Per Capita Income (Rs)
9 Umadatt Bhatta Brahmin Inter 5 4 9 Service 40000 53333
10 Ambika Joshi Brahmin Elementary 6 3 9 Service 50000 66667
11 Krishna P.d Bohora Brahmin Inter 2 1 3 Business 30000 120000
12 Dhani Datt Panta Brahmin Elementary 3 4 7 Business 50000 85714
13 Pramananda Joshi Brahmin Inter 3 3 6 Business 45000 90000
14 Kalpana K.C Chhettri Elementary 5 4 9 Business 65000 86667
15 Sitaram Joshi Brahmin Elementary 2 3 5 Business 35000 84000
16 Prakash Bdr. Singh Chhettri Inter 4 3 7 Business 40000 68571
17 Rana singh Bhandari Chhettri Inter 5 5 10 Service 50000 60000
18 Gajendra Thapa Chhettri Inter 3 1 4 Business 50000 150000
19 Purnananda Bhatta Brahmin B.A 4 3 7 Service 50000 85714
20 Bhojraj Pandey Brahmin B.A 4 3 7 Service 50000 85714
21 Jayanti Chand
22 Bhanubhakta Joshi Brahmin B.A 5 2 7 Service 40000 68571
23 Shusila Pandey Brahmin B.A 1 1 2 Service 25000 150000
24 Mahadev Bhatta Brahmin Inter 3 3 6 Business 40000 80000
25 Tara Devi Bhatta Brahmin Inter 3 2 5 Service 35000 84000
26 Chandra Dev Upadhyay Brahmin Inter 2 2 4 Service 35000 105000
27 G.K Bhat Chhettri Inter 2 3 5 Service 40000 96000
28 Narad Pandey Brahmin Inter 6 3 9 Business 50000 66667
29 Ran Bdr. Pal Chhettri Inter 4 3 7 Service 50000 85714
H-8: Sarswati Tole Road 4 (East West section, Katan Area) 1 Tara Devi Joshi Brahmin Inter 3 2 5 Service 50000 120000
2 Shanti Devi Bhandari Chhettri Inter 6 3 9 service 60000 80000
3 Rajaya Swar Chhettri Inter 3 1 4 service 50000 150000
4 Laba Dev Pandey Brahmin Inter 6 6 12 Service 200000 200000
Annex ‐ Page 42
S.N Name of HH Head / Owner Ethnicity
Education
Population Economic Status
Male Female Total Occupation Monthly Income (Rs)
Per Capita Income (Rs)
5 Bishnu Aryal Brahmin S.L.C 4 2 6 Business 50000 100000
6 Basanta Singh Chhettri Inter 3 1 4 Service 50000 150000
7 Kamala Nanda Joshi Brahmin Elementary 3 2 5 Business 30000 72000
8 Hemlal Sapkota Brahmin Inter 2 2 4 Business 50000 150000
9 Sita Devi Joshi Brahmin Inter 3 1 4 Service 50000 150000
10 Ganesh Chand Chhettri Inter 4 1 5 Service 50000 120000
11 Tika singh Dhami Chhettri Inter 4 4 8 Service 50000 75000
12 Dr. Madan Singh Karki Chhettri M.A 5 3 8 Service 50000 75000
13 Dharmanand Bhatta Brahmin Elementary 3 3 6 Service 50000 100000
14 Dashrath Joshi Brahmin MBBS 2 2 4 Business 50000 150000
15 Uttara Chand Chhettri S.L.C 1 3 4 Agriculture 50000 150000
16 Maya Devi Joshi Brahmin Elementary 4 2 6 Service 50000 100000
17 Harsa Narain Upadhyay Brahmin Elementary 4 4 8 Agriculture 50000 75000
18 Bishnu datt Awasti Brahmin Elementary 3 2 5 Business 50000 120000
19 Nirajan Gautam Brahmin S.L.C 2 2 4 Service 50000 150000
20 Shavitri Devi Panta Brahmin M.A 2 3 5 Business 40000 96000
21 Krishna Bdr. Chand Chhettri B.A 3 2 5 Service 40000 96000
22 Janaki Devi Bam Chhettri S.L.C 3 1 4 Business 35000 105000
23 Dammar Datt Bogati Chhettri S.L.C 3 1 4 Service 35000 105000
24 Hari Chand Chhettri Inter 2 2 4 Business 25000 75000
H-9: Eye Hospital Road (East-West) 1 Omprakash Dedwal Chhettri Elementary 6 5 11 Business 80000 87273
H-10 : Hospital Road (Gully 1 to Bhagatpur Marg)
1 Krishna Prasad Bhandari Brahmin Inter 2 1 3 Agriculture 25000 100000
2 Kedar Prasad Bhandari Brahmin S.L.C 2 1 3 Business 25000 100000
3 Nandalal Joshi Brahmin Inter 4 4 8 Business 50000 75000
Annex ‐ Page 43
S.N Name of HH Head / Owner Ethnicity
Education
Population Economic Status
Male Female Total Occupation Monthly Income (Rs)
Per Capita Income (Rs)
4 Kamala devi Bhatta Brahmin Elementary 4 2 6 Business 45000 90000
5 Ravi Joshi Brahmin S.L.C 2 1 3 Agriculture 25000 100000
6 Mina Panta Brahmin Inter 2 2 4 Service 25000 75000
7 Lokraj Panta Brahmin Inter 2 3 5 Agriculture 25000 60000
8 Lal Bdr.Thapa chhettri S.L.C 2 2 4 Service 50000 150000
9 Raji Chand chhettri
10 Dhir Samser Kunuwar chhettri Inter 3 1 4 Service 40000 120000
Hotel Opera road, E-W)
1 Binod Kumar Agrawal Brahmin Inter 3 2 5 Business 35000 84000
2 Krishna P.D Bogati Chhettri Inter 3 2 5 Business 40000 96000
3 Harilal Paneru Brahmin Inter 4 3 7 Business 40000 68571
Madan chowk-Dashrath Chowk - Napi - Bhagatpur Chowk Road1 Duraga Datt Bohora Brahmin Inter 4 1 5 Business 40000 96000
2 Ratna Singh Thakurathi Chhettri Elementary 3 3 6 Business 35000 70000
3 Gorakh Bdr. Chand Chhettri Inter 4 3 7 Service 25000 42857
4 Omparkash Bhandari Chhettri S.L.c 3 2 5 Business 25000 60000
5 Krishna Datt Bhatta Brahmin Inter 2 3 5 Service 35000 84000
6 Damar Devi Kuwar Chhettri Elementary 5 4 9 Business 50000 66667
Traffic Chowk- Dashrat - BP Chowk Road None
Annex ‐ Page 44
ANNEX-3 (A)
Land Ownership and Impact on Land
S.N Name of Owner Length of Affected Part /Area(m)
Width of Affected part/Area (m)
Approx. Area of Affected Part (sqm)
Area of Affected Kitta (Kattha)
Land in Other Area (Kattha)
Total Land Owned (kattha)
Total Land (sq.m)
% of Land Loss
Remaining Land after Donation (sq.m)
% of Remaining Land After Donation
Remarks
M1 : Bhasi- Rautela Road
1 Chanak Lal Chaudhary 8.5 1 8.5 0.7 10 10.7 3616.6 0.24 3608.1 99.76
2 Asha Chaudhary 5 1.5 7.5 4 10 14 4732 0.16 4724.5 99.84
3 Hira Devi Thagunna 8 1.4 11.2 4 0 4 1352 0.83 1340.8 99.17
4 Ghungra Khatri 7 1.3 9.1 0.5 0 0.5 169 5.38 159.9 94.62
M2 : Bhanuchowk -Bishnudham Road
1 Binod Rawal 15.8 0.4 6.32 0.75 15 15.75 5323.5 0.12 5317.2 99.88
2 Bhupendra Rawal 16.8 0.7 11.76 2 60 62 20956 0.06 20944.2 99.94
3 Debu Devi Bista 8.7 0.4 3.48 0.75 15 15.75 5323.5 0.07 5320.0 99.93
4 Kalyan Singh Thakuriya 8 0.4 3.2 0.75 40 40.75 13773.5 0.02 13770.3 99.98
5 Madhavi Bhatta 5.4 0.6 3.24 0.3 5 5.3 1791.4 0.18 1788.2 99.82
6 Deependra Rawal 11.5 0.5 5.75 0.9 60 60.9 20584.2 0.03 20578.5 99.97
7 Prem Thalal 5.5 0.6 3.3 0.75 0 0.75 253.5 1.3 250.2 98.7
8 Navaraj Khadka 5.3 0.5 2.65 0.275 20 20.275 6852.95 0.04 6850.3 99.96
9 Kishor Pandey 9.8 0.4 3.92 2 20 22 7436 0.05 7432.1 99.95
M3: Suklaphanta Marga(Bhanuchowk-Madan chowk-Airport Road)
1 D.D Pandey 20.8 1 20.8 2 0 2 676 3.08 655.2 96.92
2 Sabitri Rawat 3.8 0.6 2.28 2 0 2 676 0.34 673.7 99.66
3 Kalawati Chand 7.8 0.6 4.68 1 20 21 7098 0.07 7093.3 99.93
4 Kamala Devi Dhami 7.6 2 15.2 1 15 16 5408 0.28 5392.8 99.72
5 Gopal Chand 5 1.25 6.25 3 40 43 14534 0.04 14527.8 99.96 6 Dalla Dhami 6.35 0.9 5.715 2 20 22 7436 0.08 7430.3 99.92
Annex ‐ Page 45
S.N Name of Owner Length of Affected Part /Area(m)
Width of Affected part/Area (m)
Approx. Area of Affected Part (sqm)
Area of Affected Kitta (Kattha)
Land in Other Area (Kattha)
Total Land Owned (kattha)
Total Land (sq.m)
% of Land Loss
Remaining Land after Donation (sq.m)
% of Remaining Land After Donation
Remarks
7 Kalu Chand 7 1.4 9.8 2 35 37 12506 0.08 12496.2 99.92
8 Rami Chand 18.4 0.7 12.88 2 20 22 7436 0.17 7423.1 99.83
9 Gangadatt Joshi 35 1.5 52.5 10 20 30 10140 0.52 10087.5 99.48
10 Ran Bdr. Chand 18.3 0.9 16.47 3 12 15 5070 0.32 5053.5 99.68
11 Arjun Chand 6.5 1.7 11.05 0.7 10 10.7 3616.6 0.31 3605.6 99.69
12 Piuskar Bdr. Chand 4 0.7 2.8 1 0 1 338 0.31 335.2 99.69
13 Lal Singh Bista 11 0.5 5.5 1 0 1 338 1.63 332.5 98.37
14 Bahadur Nath 10.2 0.4 4.08 3 4 7 2366 0.17 2361.9 99.83
15 Dhan Bdr. Bista 28.3 0.8 22.64 3.5 40 43.5 14703 0.15 14680.4 99.85
16 Bhim Bdr. Chand 10.3 0.6 6.18 1.1 0 1.1 371.8 1.66 365.6 98.34
17 Kausilla Khatri 14 0.8 11.2 1.25 22 23.25 7858.5 0.14 7847.3 99.86
18 Mohan Dev Bhatta 5 0.7 3.5 5 4 9 3042 0.12 3038.5 99.88 M4: Airport-Airighat Road
1 Mohan Singh Bhjandari 10.7 0.95 10.165 1 18 19 6422 0.16 6411.8 99.84
2 Haridatt Joshi 3.2 2.2 7.04 1 25 26 8788 0.08 8781.0 99.92
3 Man Bdr. Chand 8.4 2.3 19.32 0.5 6 6.5 2197 0.88 2177.7 99.12
4 Bishna Devi Dhami 29.5 2.7 79.65 1 4 5 1690 4.71 1610.4 95.29
V5: Gully No-5 Road (Campus Road, North-South section)
1 Deepak Rawat 12.5 1.5 18.75 0.2 40 40.2 13587.6 0 13587.6 100
The
affe
cted
are
a i.e
are
a oc
cupi
ed b
y af
fect
ed s
truct
ure
is
publ
ic la
nd (w
ithin
RoW
of e
xist
ing
road
); he
nce
the
owne
r will
loss
no
land
2 Tej Singh K.C 10.6 1.5 15.9 0.2 50 50.2 16967.6 0 16967.6 100
3 Hiikmat Thaurathi 5.6 1.5 8.4 0.2 3 3.2 1081.6 0 1081.6 100
4 Padam Bharati 2.6 1.5 3.9 0.2 20 20.2 6827.6 0 6827.6 100
5 Tek Raj Bharati 2.6 1.5 3.9 0.2 30 30.2 10207.6 0 10207.6 100
6 Ghanashyam Joshi 10.3 1.5 15.45 0.2 40 40.2 13587.6 0 13587.6 100
7 Raju Chand 3.2 1.5 4.8 0.2 20 20.2 6827.6 0 6827.6 100
8 Lal Bdr. Chand 5.1 1.5 7.65 0.2 30 30.2 10207.6 0 10207.6 100
Annex ‐ Page 46
S.N Name of Owner Length of Affected Part /Area(m)
Width of Affected part/Area (m)
Approx. Area of Affected Part (sqm)
Area of Affected Kitta (Kattha)
Land in Other Area (Kattha)
Total Land Owned (kattha)
Total Land (sq.m)
% of Land Loss
Remaining Land after Donation (sq.m)
% of Remaining Land After Donation
Remarks
9 Bharat Chand 2.5 1.5 3.75 0.2 10 10.2 3447.6 0 3447.6 100
10 Megh Raj Bohora 7.1 1.5 10.65 0.2 30 30.2 10207.6 0 10207.6 100
11 Ganesh Chand 3.5 1.5 5.25 0.2 4 4.2 1419.6 0 1419.6 100
12 Chhetrapal Mehera 3.7 1.5 5.55 0.2 0 0.2 67.6 0 67.6 100
13 Madhav Parshad Bhatta 7.5 1.5 11.25 0.4 40 40.4 13655.2 0 13655.2 100
14 Uddhav Dev Joshi 3.7 1.5 5.55 0.2 40 40.2 13587.6 0 13587.6 100
15 Chandra Dev Joshi 3.7 1.5 5.55 0.2 20 20.2 6827.6 0 6827.6 100
16 Mahadev Bohora 6.8 1.5 10.2 0.4 10 10.4 3515.2 0 3515.2 100
17 Laxmi Devi Joshi 7.2 1.5 10.8 0.4 60 60.4 20415.2 0 20415.2 100
18 Prem parkash Pathak 3.8 1.5 5.7 0.2 20 20.2 6827.6 0 6827.6 100
19 Bijaya Nanda Joshi 3.2 1.5 4.8 0.2 10 10.2 3447.6 0 3447.6 100
20 Hansa Devi Chand 7.3 1.5 10.95 0.2 0 0.2 67.6 0 67.6 100
21 Lok Raj Bharati 7.5 1.5 11.25 0.4 10 10.4 3515.2 0 3515.2 100
22 Devraj Mishra 10.9 1.5 16.35 0.4 13 13.4 4529.2 0 4529.2 100
23 Keshav Raj Joshi 7.5 1.5 11.25 0.4 15 15.4 5205.2 0 5205.2 100
24 Dilananda Giri 7.5 1.5 11.25 0.2 20 20.2 6827.6 0 6827.6 100
25 Bisna Devi Palpali 2.7 1.5 4.05 0.2 10 10.2 3447.6 0 3447.6 100
26 Khem Palpali 2.7 1.5 4.05 0.2 10 10.2 3447.6 0 3447.6 100
27 Raghubir Bhatta 5.5 1.5 8.25 0.3 20 20.3 6861.4 0 6861.4 100
28 Chandra Devi Rawal 6.8 1.5 10.2 0.3 0 0.3 101.4 0 101.4 100
29 Sushila Vevi Rawal 5.5 1.5 8.25 0.3 0 0.3 101.4 0 101.4 100
30 santos Aitwal 9.1 1.5 13.65 0.6 44 44.6 15074.8 0 15074.8 100
31 Parbesh Partap Aitwal 10.8 1.5 16.2 0.6 35 35.6 12032.8 0 12032.8 100
32 Bhupendra Aitwal 1.3 1.5 1.95 0.4 35 35.4 11965.2 0 11965.2 100
33 Gyanendra Parshad Joshi 6 1.5 9 0.2 20 20.2 6827.6 0 6827.6 100
34 Mahesh Parshad Joshi 3.6 1.5 5.4 0.2 20 20.2 6827.6 0 6827.6 100
Annex ‐ Page 47
S.N Name of Owner Length of Affected Part /Area(m)
Width of Affected part/Area (m)
Approx. Area of Affected Part (sqm)
Area of Affected Kitta (Kattha)
Land in Other Area (Kattha)
Total Land Owned (kattha)
Total Land (sq.m)
% of Land Loss
Remaining Land after Donation (sq.m)
% of Remaining Land After Donation
Remarks
35 Ganesh Joshi 3.5 1.5 5.25 0.2 10 10.2 3447.6 0 3447.6 100
36 Tribhuwan Kumar Bhatta 3.9 1.5 5.85 0.2 1 1.2 405.6 0 405.6 100
37 Gunakar Bhatta 7.5 1.5 11.25 0.4 20 20.4 6895.2 0 6895.2 100
38 Hari Parshad Pandey 3.7 1.5 5.55 0.2 45 45.2 15277.6 0 15277.6 100
39 Uma Chand 3.7 1.5 5.55 0.3 5 5.3 1791.4 0 1791.4 100
40 Kedar Nath Pandey 4.2 1.5 6.3 0.4 10 10.4 3515.2 0 3515.2 100
41 Krishna Parshad Aryal 3.5 1.4 4.9 0.2 0.25 0.45 152.1 0 152.1 100
42 Laxmi Devi Aryal 5.5 1.4 7.7 0.3 20 20.3 6861.4 0 6861.4 100
43 Gopal Sing Bohora 5.5 1.4 7.7 0.3 0 0.3 101.4 0 101.4 100
44 Suraj Kharel 5.5 1.4 7.7 0.3 0 0.3 101.4 0 101.4 100
45 Gyan Parshad Dumre 9.6 1.4 13.44 0.53 0 0.53 179.14 0 179.14 100
46 Parbatman Khanal 9.2 1.4 12.88 0.5 0 0.5 169 0 169 100 47 Tika Devi Kadel 7.4 1.4 10.36 0.4 0.82 1.22 412.36 0 412.36 100 48 Duhurba Parshad Aryal 3.9 1.4 5.46 0.2 0.4 0.6 202.8 0 202.8 100 49 Khagimaya Bhandari 3.9 1.4 5.46 0.2 0 0.2 67.6 0 67.6 100
50 Chandra Bdr. Malla 4.5 1 4.5 0.49 20 20.49 6925.62 0 6925.62 100
51 Harka Bdr. Malla 4.5 1 4.5 0.49 20 20.49 6925.62 0 6925.62 100
52 Gopal Datt Joshi 10.5 1 10.5 0.56 0 0.56 189.28 0 189.28 100
53 Saraswati Rawal 3.5 1.5 5.25 0.2 0 0.2 67.6 0 67.6 100
54 Upendr Bdr. Khadka 3.5 1.5 5.25 0.2 40 40.2 13587.6 0 13587.6 100
55 Jayaraj Saran Bhatta 3.5 1.5 5.25 0.04 40 40.04 13533.52 0 13533.52 100
56 Dinesh Chandra Bhatta 5.5 1.5 8.25 0.58 20 20.58 6956.04 0 6956.04 100
57 Devraj Saran Bhatta 5.5 1.5 8.25 0.58 5 5.58 1886.04 0 1886.04 100
58 Manoj Gupta 5.2 1.5 7.8 0.3 20 20.3 6861.4 0 6861.4 100
59 Dev Raj Panta 2.7 1.5 4.05 0.15 20 20.15 6810.7 0 6810.7 100
60 Sivraj saran Bhatta 5.5 1.5 8.25 0.3 20 20.3 6861.4 0 6861.4 100
Annex ‐ Page 48
S.N Name of Owner Length of Affected Part /Area(m)
Width of Affected part/Area (m)
Approx. Area of Affected Part (sqm)
Area of Affected Kitta (Kattha)
Land in Other Area (Kattha)
Total Land Owned (kattha)
Total Land (sq.m)
% of Land Loss
Remaining Land after Donation (sq.m)
% of Remaining Land After Donation
Remarks
61 Gyanendra Bdr. Shah 6.7 1.5 10.05 0.3 30 30.3 10241.4 0 10241.4 100
62 Sambhu Bharati 7.5 1.5 11.25 0.4 30 30.4 10275.2 0 10275.2 100
63 Kalawati Joshi 4 1.5 6 0.2 20 20.2 6827.6 0 6827.6 100
64 Dan Bdr. Kunuwar 4 1.5 6 0.4 15 15.4 5205.2 0 5205.2 100
65 Bhakta Joshi 7.2 1.5 10.8 0.2 20 20.2 6827.6 0 6827.6 100
66 Hari Shngh Bista 3.5 1.5 5.25 0.2 12 12.2 4123.6 0 4123.6 100
67 Janki Raiswal 3.5 1.5 5.25 4 7 11 3718 0 3718 100
68 Parbati Chataut 7.2 1.5 10.8 0.4 10 10.4 3515.2 0 3515.2 100
69 Tarani Datt Chataut 14.6 1.5 21.9 0.79 20 20.79 7027.02 0 7027.02 100
70 Bijayanand Joshi 14.6 1.5 21.9 0.79 15 15.79 5337.02 0 5337.02 100
71 Nanda Dhami 3.7 1.5 5.55 0.2 0.2 67.6 0 67.6 100
72 Mohan Singh Dhami 4.9 1.5 7.35 0.4 80 80.4 27175.2 0 27175.2 100
73 Jayakisan Bhatta 6.5 1.5 9.75 0.3 0 0.3 101.4 0 101.4 100
74 Dilliraj Joshi 5.7 1.5 8.55 0.3 10 10.3 3481.4 0 3481.4 100
75 Dharma Devi Rana 5.5 1.5 8.25 0.3 0 0.3 101.4 0 101.4 100
76 Gopal Datt Joshi 6.9 1.5 10.35 0.4 20 20.4 6895.2 0 6895.2 100
77 Tej Bdr. Bam 5.5 1.5 8.25 0 0 0 0 100
78 Kisan Singh Thapa 10.5 1.5 15.75 1.65 0 1.65 557.7 0 557.7 100
79 Laxmi Datt Pandey 10.9 1.5 16.35 0.59 20 20.59 6959.42 0 6959.42 100
80 Laba Dev Pandey 10.9 1.5 16.35 0.5 50 50.5 17069 0 17069 100
81 Basudev Bohora 4.7 1.5 7.05 0.3 40 40.3 13621.4 0 13621.4 100
82 Karna Bdr. Chand 6.7 1.5 10.05 0.35 80 80.35 27158.3 0 27158.3 100
83 Deelip Singh Bhandari 5.6 1.5 8.4 0.3 10 10.3 3481.4 0 3481.4 100
84 Manoj Parshad Joshi 7 1.5 10.5 0.3 20 20.3 6861.4 0 6861.4 100
85 Chandra Maya karki 9.4 1.5 14.1 0.53 0 0.53 179.14 0 179.14 100
86 Tara Devi Bhatta 7.5 1.5 11.25 0.25 80 80.25 27124.5 0 27124.5 100
Annex ‐ Page 49
S.N Name of Owner Length of Affected Part /Area(m)
Width of Affected part/Area (m)
Approx. Area of Affected Part (sqm)
Area of Affected Kitta (Kattha)
Land in Other Area (Kattha)
Total Land Owned (kattha)
Total Land (sq.m)
% of Land Loss
Remaining Land after Donation (sq.m)
% of Remaining Land After Donation
Remarks
87 Gangaram Giri 7.5 1.5 11.25 0.25 30 30.25 10224.5 0 10224.5 100
88 Netra Chataut 18.2 1.5 27.3 0.4 20 20.4 6895.2 0 6895.2 100
89 Balaram Ghimire 3.5 1.5 5.25 0.2 10 10.2 3447.6 0 3447.6 100
90 Jayadatt Paudyal 8.5 1.5 12.75 0.59 20 20.59 6959.42 0 6959.42 100
91 Bidhya Devi Kharel 6.3 1.5 9.45 0.18 1 1.18 398.84 0 398.84 100
92 Tikaram Aryal 7.2 1.5 10.8 0.4 1 1.4 473.2 0 473.2 100
93 Chintamani Kharel 7.2 1.5 10.8 0.4 20 20.4 6895.2 0 6895.2 100
94 Ranbir Saran Bhatta 7.2 1.5 10.8 0.4 20 20.4 6895.2 0 6895.2 100
95 Narain Datt Bhatta 7.2 1.5 10.8 0.4 20 20.4 6895.2 0 6895.2 100
96 Raju Sharma 7.2 1.5 10.8 0.4 1 1.4 473.2 0 473.2 100
97 Gokarna Bdr. Chand 7.2 1.5 10.8 0.4 0 0.4 135.2 0 135.2 100
98 Amita Aryal 3.7 1.5 5.55 0.4 0 0.4 135.2 0 135.2 100
99 Pabi Kafle 3.7 1.5 5.55 0.4 0 0.4 135.2 0 135.2 100
100 Hema Devi Gurung 8.5 1.5 12.75 0.4 0 0.4 135.2 0 135.2 100
101 Hom Bdr. Kunuwar 9.6 1.5 14.4 0.495 40 40.495 13687.31 0 13687.31 100
102 Khadak Bdr. Kunuwar 4.5 1.5 6.75 0.17 10 10.17 3437.46 0 3437.46 100 V-4: Gully No-4 Road (North-South section)
1 L.B Bista 13 1.4 18.2 0.49 40 40.49 13685.62 0 13685.62 100
The
affe
cted
are
a i.e
are
a oc
cupi
ed b
y af
fect
ed s
truct
ure
is
publ
ic la
nd (w
ithin
RoW
of e
xist
ing
road
); he
nce
the
owne
r will
loss
no
land
2 Tara singh Bohora 6 1.4 8.4 0.49 1 1.49 503.62 0 503.62 100
3 Mohan Khatri 6 1.4 8.4 0.49 30 30.49 10305.62 0 10305.62 100
4 Hariram Chaudhari 5.5 1.4 7.7 0.49 60 60.49 20445.62 0 20445.62 100
5 Chet raj Joshi 5.3 1.4 7.42 0.49 15 15.49 5235.62 0 5235.62 100
6 Dhan Bdr.Ayer 5.3 1.4 7.42 0.49 20 20.49 6925.62 0 6925.62 100
7 Khadak Singh Saud 5.7 1.4 7.98 0.3 0.3 101.4 0 101.4 100
8 Hira Devi Thagunna 3.8 1.4 5.32 0.2 10 10.2 3447.6 0 3447.6 100
Annex ‐ Page 50
S.N Name of Owner Length of Affected Part /Area(m)
Width of Affected part/Area (m)
Approx. Area of Affected Part (sqm)
Area of Affected Kitta (Kattha)
Land in Other Area (Kattha)
Total Land Owned (kattha)
Total Land (sq.m)
% of Land Loss
Remaining Land after Donation (sq.m)
% of Remaining Land After Donation
Remarks
9 Shankardatt Joshi 3.5 1.4 4.9 0.2 15 15.2 5137.6 0 5137.6 100
10 Chitramani Joshi 5 1.4 7 0.2 6 6.2 2095.6 0 2095.6 100
11 Manju Bhatta 3.5 1.2 4.2 0.2 0.2 67.6 0 67.6 100
12 Haridatt Bhatta 3.5 1.2 4.2 0.2 6 6.2 2095.6 0 2095.6 100
13 Mamta Awasti 7.2 1.4 10.08 0.4 30 30.4 10275.2 0 10275.2 100
14 Dhan Bdr. Bom 7.2 1.4 10.08 0.4 20 20.4 6895.2 0 6895.2 100
15 Kiran Khadka 3.9 1.4 5.46 0.2 20 20.2 6827.6 0 6827.6 100
16 Gajadhar Joshi 3.9 1.4 5.46 0.2 40 40.2 13587.6 0 13587.6 100
17 Manorath Bhatta 3.2 1.4 4.48 0.2 20 20.2 6827.6 0 6827.6 100
18 Girija Shankar Parsad 3.2 1.4 4.48 0.4 0.4 135.2 0 135.2 100
19 Harish Chandra Bhatta 24 1.4 33.6 1.9 30 31.9 10782.2 0 10782.2 100
20 Naina Ojha 5.5 1.4 7.7 0.3 20 20.3 6861.4 0 6861.4 100
21 Deependra Bista 5.5 1.4 7.7 0.3 41 41.3 13959.4 0 13959.4 100
22 Ganga Kharel 5.5 1.4 7.7 0.3 20 20.3 6861.4 0 6861.4 100
23 Devidatt Bhatta 3.5 1.4 4.9 0.2 1 1.2 405.6 0 405.6 100
24 Devaki Joshi 7.4 1.4 10.36 0.3 0 0.3 101.4 0 101.4 100
25 Chandrakala Panta 4.5 1.4 6.3 0.3 0 0.3 101.4 0 101.4 100
26 Jaya Bdr. Pal 8.2 1.4 11.48 0.45 30 30.45 10292.1 0 10292.1 100
27 Dambar Bdr. Pal 8.2 1.4 11.48 0.45 10 10.45 3532.1 0 3532.1 100
28 Hari parsad Bhatta 5.5 1.4 7.7 0.3 0 0.3 101.4 0 101.4 100
29 Laxman Singh Bista 5.5 1.4 7.7 0.3 20 20.3 6861.4 0 6861.4 100
30 Narendra Khatri 3.7 1.4 5.18 0.2 10 10.2 3447.6 0 3447.6 100
31 Dhirendra Bdr. Chand 3.6 1.4 5.04 0.2 0 0.2 67.6 0 67.6 100
32 Saligram Kharel 7.8 1.4 10.92 0.4 1 1.4 473.2 0 473.2 100
33 Narayan Baral 7.4 1.2 8.88 0.4 0 0.4 135.2 0 135.2 100
34 Dhan Bdr. Chand 7.2 1.4 10.08 0.4 1 1.4 473.2 0 473.2 100
Annex ‐ Page 51
S.N Name of Owner Length of Affected Part /Area(m)
Width of Affected part/Area (m)
Approx. Area of Affected Part (sqm)
Area of Affected Kitta (Kattha)
Land in Other Area (Kattha)
Total Land Owned (kattha)
Total Land (sq.m)
% of Land Loss
Remaining Land after Donation (sq.m)
% of Remaining Land After Donation
Remarks
35 Bamayanti Joshi 7.5 1.4 10.5 0.4 25 25.4 8585.2 0 8585.2 100
36 Durga Bhandari 7.2 1 7.2 0.4 6 6.4 2163.2 0 2163.2 100
37 Parbati Devi Damai 3.6 1 3.6 0.2 1 1.2 405.6 0 405.6 100
38 Tila Devi Damai 3.6 1 3.6 0.2 1 1.2 405.6 0 405.6 100
39 P.K Shrestha 7.2 1 7.2 0.2 10 10.2 3447.6 0 3447.6 100
40 Dammari Bhatta 3.7 1 3.7 0.2 80 80.2 27107.6 0 27107.6 100
41 Rama Shrestha 3.7 1 3.7 0.2 0 0.2 67.6 0 67.6 100
42 Deepa Devi Shrestha 8 1 8 0.4 12 12.4 4191.2 0 4191.2 100
43 Hripriya Pant 12.1 1.4 16.94 0.49 10 10.49 3545.62 0 3545.62 100
44 Premdatt Joshi 5 1.4 7 0.3 14 14.3 4833.4 0 4833.4 100
45 Prajapati Bista 5 1.4 7 0.3 10 10.3 3481.4 0 3481.4 100
46 Dal Bdr.Bista 3.6 1.4 5.04 0.2 25 25.2 8517.6 0 8517.6 100
47 Harka Bdr. Bista 3.6 1.4 5.04 0.2 25 25.2 8517.6 0 8517.6 100
48 Jahar Singh Pwali 5.2 1.4 7.28 0.3 0 0.3 101.4 0 101.4 100
49 Madhav Joshi 4.8 1.4 6.72 0.2 10 10.2 3447.6 0 3447.6 100
50 Shreeram Chataut 12.7 1.4 17.78 0.49 30 30.49 10305.62 0 10305.62 100
51 Hajari Singh Pujara 8.7 1.6 13.92 0.165 10 10.165 3435.77 0 3435.77 100
52 Dharma Singh Rawal 3.6 1.4 5.04 0.2 60 60.2 20347.6 0 20347.6 100
53 Dhana Devi Bhatta 3.7 1.4 5.18 0.2 20 20.2 6827.6 0 6827.6 100
54 Niraj Saud 7 1.4 9.8 0.4 30 30.4 10275.2 0 10275.2 100
55 Padam Thakurathi 7 1.4 9.8 0.4 20 20.4 6895.2 0 6895.2 100
56 Godawari Bhatta 7 1.4 9.8 0.79 40 40.79 13787.02 0 13787.02 100
57 Sunil Panta 6.2 1.4 8.68 0.3 100 100.3 33901.4 0 33901.4 100
58 Tek Bdr. Kunuwar 5.4 1.4 7.56 0.49 10 10.49 3545.62 0 3545.62 100
59 Madan Singh Thagunna 5.3 1.4 7.42 0.3 0 0.3 101.4 0 101.4 100
60 Sova Karki 5.5 1.4 7.7 0.3 20 20.3 6861.4 0 6861.4 100
Annex ‐ Page 52
S.N Name of Owner Length of Affected Part /Area(m)
Width of Affected part/Area (m)
Approx. Area of Affected Part (sqm)
Area of Affected Kitta (Kattha)
Land in Other Area (Kattha)
Total Land Owned (kattha)
Total Land (sq.m)
% of Land Loss
Remaining Land after Donation (sq.m)
% of Remaining Land After Donation
Remarks
61 Kalu Bohora 5.5 1.4 7.7 0.3 0 0.3 101.4 0 101.4 100
62 Gorakh Bdr. Bista 5.5 1.4 7.7 0.3 30 30.3 10241.4 0 10241.4 100
63 Lalit Bdr. Bohora 10 1.4 14 0.49 20 20.49 6925.62 0 6925.62 100
64 Lalit Parsad Bhatta 5.5 1.4 7.7 0.49 10 10.49 3545.62 0 3545.62 100
65 Laxman Chand 7.2 1.4 10.08 0.49 0 0.49 165.62 0 165.62 100
66 Kashi Singh Karki 7.2 1.4 10.08 0.3 0 0.3 101.4 0 101.4 100
67 Gyanu Bohara 3.7 1.4 5.18 0.2 20 20.2 6827.6 0 6827.6 100
68 Parkash Chand 7.2 1.4 10.08 0.4 15 15.4 5205.2 0 5205.2 100
69 Padama devi Bhatta 3.5 2 7 0.2 4 4.2 1419.6 0 1419.6 100
70 Rudra Parsad Bhatrai 15 2 30 0.79 30 30.79 10407.02 0 10407.02 100
71 Mina Baral 7.2 1.1 7.92 0.4 0 0.4 135.2 0 135.2 100
72 Padam Raj Pandey 3.5 0.6 2.1 0.2 13.5 13.7 4630.6 0 4630.6 100
73 Mahesh Pandey 3.5 0.6 2.1 0.2 12 12.2 4123.6 0 4123.6 100
74 Dhan Bdr. Chand 5.2 1.1 5.72 0 0 0 0 0 100
V-3 : Gully No-3 Road (North-South Section)
1 Basanti Devi Pandey 11 0.5 5.5 0.58 40 40.58 13716.04 0 13716.04 100
The
affe
cted
are
a i.e
are
a oc
cupi
ed b
y af
fect
ed s
truct
ure
is p
ublic
land
(with
in
RoW
of e
xist
ing
road
); he
nce
the
owne
r w
ill lo
ss n
o la
nd
2 Ambika devi Bhandari 10.6 0.5 5.3 0.58 20 20.58 6956.04 0 6956.04 100
3 Parmananda Bhandari 10.6 0.5 5.3 0.58 20 20.58 6956.04 0 6956.04 100
4 Top Bdr. K.C 9.8 1.5 14.7 0.58 10 10.58 3576.04 0 3576.04 100
5 Bhim Pandey 3.25 1.5 4.875 0.29 20 20.29 6858.02 0 6858.02 100
6 Bhuwan Pandey 3.25 1.5 4.875 0.29 20 20.29 6858.02 0 6858.02 100
7 Devraj Mishra 8.5 1.4 11.9 0.29 0 0.29 98.02 0 98.02 100
8 Prem Singh Bhatta 4.2 1.5 6.3 0.29 0 0.29 98.02 0 98.02 100
9 Hikmat Saud 5.3 1.5 7.95 0.29 0 0.29 98.02 0 98.02 100
10 Ganesh Saud 5.3 1.5 7.95 0.58 0 0.58 196.04 0 196.04 100
11 Tej Bdr. Bhandari 3.5 1.5 5.25 0.4 7 7.4 2501.2 0 2501.2 100
Annex ‐ Page 53
S.N Name of Owner Length of Affected Part /Area(m)
Width of Affected part/Area (m)
Approx. Area of Affected Part (sqm)
Area of Affected Kitta (Kattha)
Land in Other Area (Kattha)
Total Land Owned (kattha)
Total Land (sq.m)
% of Land Loss
Remaining Land after Donation (sq.m)
% of Remaining Land After Donation
Remarks
12 Sundara Dev Bhandari 3.5 1.5 5.25 0.4 7 7.4 2501.2 0 2501.2 100
13 Chandra Bdr. Chand 7.5 1.5 11.25 0.4 20 20.4 6895.2 0 6895.2 100
14 Bhan Bdr. Chand 7.5 1.5 11.25 0.4 0 0.4 135.2 0 135.2 100
15 Bashu Dev Deuba 3.6 1.5 5.4 0.2 80 80.2 27107.6 0 27107.6 100
16 Nara Bdr. Bista 3.6 1.5 5.4 0.2 20 20.2 6827.6 0 6827.6 100
17 Kamala Devi Kathayat 3.6 1.5 5.4 0.2 0 0.2 67.6 0 67.6 100
18 Dal Bdr. Shah 3.6 1.5 5.4 0.2 0 0.2 67.6 0 67.6 100
19 Gorakh Bdr. Khati 7.5 1.5 11.25 0.4 30 30.4 10275.2 0 10275.2 100
20 Bhim Datta Bhatta 3.7 1.5 5.55 0.2 14 14.2 4799.6 0 4799.6 100
21 Yagyaraj Paudyal/Madan 4.2 1.5 6.3 0.2 0.2 67.6 0 67.6 100
22 Rupkiswor Gupta 106 1.5 159 0.49 0.49 165.62 0 165.62 100
23 Bharat Nepal 5.4 1.5 8.1 0.3 10 10.3 3481.4 0 3481.4 100
24 Nar Bdr. Pal 5.4 1.5 8.1 0.3 20 20.3 6861.4 0 6861.4 100
25 Kailap Bhatta 11 1.5 16.5 0.3 30 30.3 10241.4 0 10241.4 100
26 Ghanashyam Kalauni 5.5 1.5 8.25 0.3 25 25.3 8551.4 0 8551.4 100
27 Dhan Bdr. Bom 5.2 1.5 7.8 0.3 20 20.3 6861.4 0 6861.4 100
28 Anil Dhungana/Joshi 7.2 1.5 10.8 0.3 20 20.3 6861.4 0 6861.4 100
29 Yasoda Pathak/ Tiwari 11 1.5 16.5 0.4 0 0.4 135.2 0 135.2 100
30 Jeetendra Parsad Bhatta 6 1.5 9 0.4 0 0.4 135.2 0 135.2 100
31 Mahendra Bdr Kunwor 11.5 1.3 14.95 0.49 40 40.49 13685.62 0 13685.62 100
32 Ram Singh Ter 10.5 1.3 13.65 0.49 110 110.49 37345.62 0 37345.62 100
33 Ram Pd Sapkota 10.5 1.3 13.65 0.49 0 0.49 165.62 0 165.62 100
34 Arjun Prakash Upreti 11 1.3 14.3 0.59 0 0.59 199.42 0 199.42 100
35 Min Raj Bhatta 11.8 1.3 15.34 0.59 120 120.59 40759.42 0 40759.42 100
36 Karan Shah 4.6 1.3 5.98 0.04 10 10.04 3393.52 0 3393.52 100
37 Narendra Raj Bohora 3.6 1.3 4.68 0.15 34 34.15 11542.7 0 11542.7 100
Annex ‐ Page 54
S.N Name of Owner Length of Affected Part /Area(m)
Width of Affected part/Area (m)
Approx. Area of Affected Part (sqm)
Area of Affected Kitta (Kattha)
Land in Other Area (Kattha)
Total Land Owned (kattha)
Total Land (sq.m)
% of Land Loss
Remaining Land after Donation (sq.m)
% of Remaining Land After Donation
Remarks
38 Jagdish Upreti 11 1.3 14.3 0.49 20 20.49 6925.62 0 6925.62 100
39 Ratan Saud 3.7 1.3 4.81 0.2 0 0.2 67.6 0 67.6 100
40 Karan Bdr Singh 11 1.3 14.3 0.49 30 30.49 10305.62 0 10305.62 100
41 Ashok Kumar Dewal 7.2 1.3 9.36 0.4 0.25 0.65 219.7 0 219.7 100
42 Dhawal Bdr Chand 7.2 1.3 9.36 0.4 20 20.4 6895.2 0 6895.2 100
43 Kalpana KC 7.1 1.3 9.23 0.79 20 20.79 7027.02 0 7027.02 100
44 Jayamati Devi Bhatta 16.5 1.3 21.45 0.4 2 2.4 811.2 0 811.2 100
45 Madan Panta 7.7 1.4 10.78 0.4 30 30.4 10275.2 0 10275.2 100
46 Dhan Singh Rawal 5.5 1.4 7.7 0.4 40 40.4 13655.2 0 13655.2 100
47 Belu Devi Bhata 5.7 1.4 7.98 0.3 0 0.3 101.4 0 101.4 100
48 Kunti Bohora 5.7 1.4 7.98 0.3 2 2.3 777.4 0 777.4 100
49 Harish Chand 5.4 1.4 7.56 0.3 0 0.3 101.4 0 101.4 100
50 Jamunaganga Devi Joshi 5.7 1.4 7.98 0.3 20 20.3 6861.4 0 6861.4 100
51 Tanka Pd. Bhatta 7.2 1.4 10.08 0.3 20 20.3 6861.4 0 6861.4 100
52 Radhika Devi bhatta 7.5 1.4 10.5 0.3 30 30.3 10241.4 0 10241.4 100
53 D.r Rajendra Bhatta 7.5 1.4 10.5 0.3 30 30.3 10241.4 0 10241.4 100
54 Deepak Kharel 9 1.4 12.6 0.3 20 20.3 6861.4 0 6861.4 100
55 Rishi Kharel 6 1.4 8.4 0.3 20 20.3 6861.4 0 6861.4 100
56 Yadu Raj Joshi 7.2 1.4 10.08 0.3 2 2.3 777.4 0 777.4 100
57 Nar Singh Dhami 7 1.4 9.8 0.3 7 7.3 2467.4 0 2467.4 100
58 Tarun Lakhera 7.2 1.4 10.08 0.3 1 1.3 439.4 0 439.4 100
59 Padama Saud Bhandari 7.2 1.4 10.08 0.3 10 10.3 3481.4 0 3481.4 100
60 Furua Kalauni 7.2 0.9 6.48 0.3 0 0.3 101.4 0 101.4 100
61 Megh Raj Bhatta 7.2 1 7.2 0.4 1 1.4 473.2 0 473.2 100
62 Kashidatt Bhatta 7.2 1 7.2 0.22 10 10.22 3454.36 0 3454.36 100
63 Kalpana Karki 3.5 0.9 3.15 0.4 0.4 135.2 0 135.2 100
Annex ‐ Page 55
S.N Name of Owner Length of Affected Part /Area(m)
Width of Affected part/Area (m)
Approx. Area of Affected Part (sqm)
Area of Affected Kitta (Kattha)
Land in Other Area (Kattha)
Total Land Owned (kattha)
Total Land (sq.m)
% of Land Loss
Remaining Land after Donation (sq.m)
% of Remaining Land After Donation
Remarks
V-2: Gully No-2 Road (North-South section)
1 Ramesh Pandey 6.4 1.6 10.24 0.04 1 1.04 351.52 0 351.52 100
The
affe
cted
are
a i.e
are
a oc
cupi
ed b
y af
fect
ed s
truct
ure
is p
ublic
la
nd (w
ithin
RoW
of e
xist
ing
road
); he
nce
the
owne
r will
loss
no
land
2 Laxi Pandey 3.5 1.6 5.6 0.04 20 20.04 6773.52 0 6773.52 100
3 Arjundatt Pandey 3.5 1.6 5.6 0.04 20 20.04 6773.52 0 6773.52 100
4 Gopaldatt Bhatta 3.5 1.6 5.6 0.04 20 20.04 6773.52 0 6773.52 100
5 Jamuna Devi Bhatta 3.5 1.6 5.6 0.04 20 20.04 6773.52 0 6773.52 100
6 Bhojraj Bhatta 3.7 1.6 5.92 0.49 60 60.49 20445.62 0 20445.62 100
7 Rameswor Upreti 10.5 1.6 16.8 0.29 100 100.29 33898.02 0 33898.02 100
8 Neha Singh Pal 5.2 1.6 8.32 0.29 30 30.29 10238.02 0 10238.02 100
9 Tikadatt Paneru 3.6 1.6 5.76 5 5 1690 0 1690 100
10 Rajesh Gupta 3.2 1.6 5.12 0.2 30 30.2 10207.6 0 10207.6 100
11 Parmananda Paneru 3.2 1.6 5.12 0.2 10 10.2 3447.6 0 3447.6 100
12 Karunakar Paneru 5 1.6 8 0.2 20 20.2 6827.6 0 6827.6 100
13 Laxmi Devi Bhatta 6.2 1.6 9.92 0.3 30 30.3 10241.4 0 10241.4 100
14 Tek Khadka 5.5 1.6 8.8 0.3 20 20.3 6861.4 0 6861.4 100
15 Ram Parshad Pandey 3.8 1.6 6.08 0.2 10 10.2 3447.6 0 3447.6 100
16 Sher Singh Ter 3.7 1.6 5.92 0.2 30 30.2 10207.6 0 10207.6 100
17 Shankar Bdr. Bista 3.8 1.6 6.08 0.2 20 20.2 6827.6 0 6827.6 100
18 Madan Singh Aiyar 3.7 1.6 5.92 0.2 10 10.2 3447.6 0 3447.6 100
19 Dharma Raj Bhatta 3.4 1.6 5.44 0.2 20 20.2 6827.6 0 6827.6 100
20 Dev Raj Bhatta 3.8 1.6 6.08 0.2 20 20.2 6827.6 0 6827.6 100
21 Jayalal Bhatta 3.6 1.6 5.76 0.2 50 50.2 16967.6 0 16967.6 100
22 Bhoj Raj Bhatta 3.6 1.6 5.76 0.2 30 30.2 10207.6 0 10207.6 100
23 Uddhav Singh Bista 3.8 1.6 6.08 0.2 100 100.2 33867.6 0 33867.6 100
24 Nar Bdr. Bista 3.2 1.6 5.12 0.2 20 20.2 6827.6 0 6827.6 100
25 Kiswar Jairu 3.8 1.6 6.08 0.2 1 1.2 405.6 0 405.6 100
Annex ‐ Page 56
S.N Name of Owner Length of Affected Part /Area(m)
Width of Affected part/Area (m)
Approx. Area of Affected Part (sqm)
Area of Affected Kitta (Kattha)
Land in Other Area (Kattha)
Total Land Owned (kattha)
Total Land (sq.m)
% of Land Loss
Remaining Land after Donation (sq.m)
% of Remaining Land After Donation
Remarks
26 Nandalal Bohora 3.8 1.6 6.08 0.2 20 20.2 6827.6 0 6827.6 100
27 Motilal Bohora 3.8 1.6 6.08 0.2 50 50.2 16967.6 0 16967.6 100
28 Madana Devi Bohora 7.3 1.6 11.68 0.2 50 50.2 16967.6 0 16967.6 100
29 Hari Parshad Bohora 3.5 1.6 5.6 0.2 30 30.2 10207.6 0 10207.6 100
30 Siddharaj Bohora 8 1.6 12.8 0.2 30 30.2 10207.6 0 10207.6 100
31 Sita K.C 5.8 1.6 9.28 0.25 10 10.25 3464.5 0 3464.5 100
32 Iswori Devi Bohora 5.5 1.6 8.8 0.3 10 10.3 3481.4 0 3481.4 100
33 Urmila Kharel 5.7 1.6 9.12 0.3 20 20.3 6861.4 0 6861.4 100
34 Tika Devi Kharel 5.7 1.6 9.12 0.3 1.5 1.8 608.4 0 608.4 100
35 Ram Parshad Kharel 5.3 1.6 8.48 0.3 21 21.3 7199.4 0 7199.4 100
36 Navraj Kharel 5.5 1.6 8.8 0.3 20 20.3 6861.4 0 6861.4 100
37 Manmati Giri 4.7 1.6 7.52 0.25 1 1.25 422.5 0 422.5 100
38 Nisha Shah 6.2 1.6 9.92 0.3 0 0.3 101.4 0 101.4 100
39 Rasmi Gupta 5 1.6 8 0.3 0 0.3 101.4 0 101.4 100
40 Pawan Kumar Sarwagi 10.7 1.6 17.12 0.5 1 1.5 507 0 507 100
41 Birendra Kumar Sangai 10.7 1.6 17.12 0.5 5 5.5 1859 0 1859 100
42 Dhan Bdr. Chand 12.3 1.6 19.68 0.59 70 70.59 23859.42 0 23859.42 100
43 Hajari Chand 6.7 1.6 10.72 0.4 5 5.4 1825.2 0 1825.2 100
44 Ram Bdr. Kunuwar 18 1.6 28.8 0.49 50 50.49 17065.62 0 17065.62 100
45 Laxmi Bhatta 7.2 1.6 11.52 0.4 0 0.4 135.2 0 135.2 100
46 Pratap Chand 7.05 1.6 11.28 0.4 30 30.4 10275.2 0 10275.2 100
47 Ram Bdr. Kunuwar 5.5 1.6 8.8 0.4 20 20.4 6895.2 0 6895.2 100
48 Narendra Paneru 12.7 1.4 17.78 0.58 34 34.58 11688.04 0 11688.04 100
49 Damodar Athola Joshi 5.5 1.4 7.7 0.29 40 40.29 13618.02 0 13618.02 100
50 Laxi Devi Paneru 5.5 1.4 7.7 0.29 34 34.29 11590.02 0 11590.02 100
51 Dwarika Devi Bista 5.5 1.4 7.7 0.29 0 0.29 98.02 0 98.02 100
Annex ‐ Page 57
S.N Name of Owner Length of Affected Part /Area(m)
Width of Affected part/Area (m)
Approx. Area of Affected Part (sqm)
Area of Affected Kitta (Kattha)
Land in Other Area (Kattha)
Total Land Owned (kattha)
Total Land (sq.m)
% of Land Loss
Remaining Land after Donation (sq.m)
% of Remaining Land After Donation
Remarks
52 Ramdular Jaiswal 5.3 1.4 7.42 0.29 0 0.29 98.02 0 98.02 100
53 Deep Raj Chataut 10.3 1.4 14.42 0.58 40 40.58 13716.04 0 13716.04 100
54 Padam Bdr. Thakurathi 10.6 1.4 14.84 0.4 20 20.4 6895.2 0 6895.2 100
55 Kalpana Thapa 8.8 1.4 12.32 0.4 50 50.4 17035.2 0 17035.2 100
56 Motimaya Sharma 4 1.4 5.6 0.2 8 8.2 2771.6 0 2771.6 100
57 Ganga Kafle 4 1.4 5.6 0.2 3 3.2 1081.6 0 1081.6 100
58 Narendra Khatri 7 1.4 9.8 0.2 20 20.2 6827.6 0 6827.6 100
59 Binod Joshi 3.7 1.4 5.18 0.2 9 9.2 3109.6 0 3109.6 100
60 Srijana Rawal 4.2 1.4 5.88 0.2 40 40.2 13587.6 0 13587.6 100
61 Bir Bdr.Kunwor 4.2 1.4 5.88 0.2 20 20.2 6827.6 0 6827.6 100
62 Nirmal Lamichhane 4.2 1.4 5.88 0.2 20 20.2 6827.6 0 6827.6 100
63 Madan Sunar 4 1.4 5.6 0.2 5 5.2 1757.6 0 1757.6 100
64 Shivlal Nyeupane 4.2 1.4 5.88 0.2 20 20.2 6827.6 0 6827.6 100
65 Naresh Agrawal 4.2 1.4 5.88 0.2 12 12.2 4123.6 0 4123.6 100
66 Radhika Sunar 4 1.4 5.6 0.2 1 1.2 405.6 0 405.6 100
67 Rameswor Bhatta 7.2 1.4 10.08 0.4 60 60.4 20415.2 0 20415.2 100
68 Sushil Dewal 7.2 1.4 10.08 0.4 21 21.4 7233.2 0 7233.2 100
69 Megh Raj Bohora 7.2 1.4 10.08 0.2 40 40.2 13587.6 0 13587.6 100
70 Ramchandra Bohora 6.2 1.4 8.68 0.2 1 1.2 405.6 0 405.6 100
71 Kamala Devi Bohora 6.2 1.4 8.68 0.3 1 1.3 439.4 0 439.4 100
72 Govinda Raj Joshi 5.5 1.4 7.7 0.3 10 10.3 3481.4 0 3481.4 100
73 Mukesh Agrawal 6 1.4 8.4 0.3 0 0.3 101.4 0 101.4 100
74 Kaviraj Bhatta 6 1.4 8.4 0.3 0 0.3 101.4 0 101.4 100
75 Bhojraj Joshi 11 1.4 15.4 0.3 60 60.3 20381.4 0 20381.4 100
76 Chitra Nepal 4.3 1.4 6.02 0.3 100 100.3 33901.4 0 33901.4 100
77 Iswori Devi Chilwal 4.2 1.4 5.88 0.3 4 4.3 1453.4 0 1453.4 100
Annex ‐ Page 58
S.N Name of Owner Length of Affected Part /Area(m)
Width of Affected part/Area (m)
Approx. Area of Affected Part (sqm)
Area of Affected Kitta (Kattha)
Land in Other Area (Kattha)
Total Land Owned (kattha)
Total Land (sq.m)
% of Land Loss
Remaining Land after Donation (sq.m)
% of Remaining Land After Donation
Remarks
78 Laxmi Devi Tiwari 5.2 1.4 7.28 0.3 0 0.3 101.4 0 101.4 100
79 Ganesh Raj Bohora 11.2 1.4 15.68 0.3 10 10.3 3481.4 0 3481.4 100
80 Sunita Budha 5.5 1.4 7.7 0.3 1 1.3 439.4 0 439.4 100
81 Chandra Datt Joshi 5.5 1.4 7.7 0.3 1 1.3 439.4 0 439.4 100
82 Madhusudan Aryal 5.6 1.4 7.84 0.3 0 0.3 101.4 0 101.4 100
83 Gangaram Rawal 7.5 1.4 10.5 0.3 21 21.3 7199.4 0 7199.4 100
84 Somraj Aryal 8.8 1.4 12.32 0.4 50 50.4 17035.2 0 17035.2 100
85 Gopal Bhusal 3.6 1.5 5.4 0.2 20 20.2 6827.6 0 6827.6 100
86 Homlal Bhusal 3.6 0.6 2.16 0.2 20 20.2 6827.6 0 6827.6 100
87 Ishwori Devi Bhatta 3.5 0.25 0.875 0.2 0 0.2 67.6 0 67.6 100
88 Tek Bdr. Sunar 4.6 1.6 7.36 0.2 40 40.2 13587.6 0 13587.6 100
89 Min Bdr. Kathayat 3.5 1.5 5.25 0.2 10 10.2 3447.6 0 3447.6 100 V-1: Gully No-1(Shalgadhi Road, North-South Section)
1 Bhairav Bdr. Aiyar 8.6 1.4 12.04 0.3 60 60.3 20381.4 0 20381.4 100
2 Suman Dewal 2.25 1.5 3.375 0.3 0 0.3 101.4 0 101.4 100
3 Ashok Kumar Dewal 2.25 1.4 3.15 0.3 0 0.3 101.4 0 101.4 100
4 Bhupendra Rawal 5.2 1.5 7.8 0.3 60 60.3 20381.4 0 20381.4 100
5 Rajendra Rawal 5.2 1.6 8.32 0.3 60 60.3 20381.4 0 20381.4 100
6 Bhoj Raj Bohora 5.6 1 5.6 0.3 12 12.3 4157.4 0 4157.4 100
The
affe
cted
land
i.e.
the
land
oc
cupi
ed b
y st
ruct
ure
is p
ublic
la
nd; h
ence
the
owne
r will
loss
no
land
7 Padam Bdr. Aiyar 5.5 1 5.5 0.3 26 26.3 8889.4 0 8889.4 100
8 Hariom Dewal 2.75 1 2.75 0.3 0 0.3 101.4 0 101.4 100
9 Harinanda Pd.NirajKumar 2.75 1 2.75 0.3 0 0.3 101.4 0 101.4 100
10 Nannelal Hariom 5.5 1 5.5 0.3 0 0.3 101.4 0 101.4 100
11 Kailash Gupta 5.3 1.4 7.42 0.2 20 20.2 6827.6 0 6827.6 100
12 Bijaya Dewal 3.6 1 3.6 0.2 0 0.2 67.6 0 67.6 100
Annex ‐ Page 59
S.N Name of Owner Length of Affected Part /Area(m)
Width of Affected part/Area (m)
Approx. Area of Affected Part (sqm)
Area of Affected Kitta (Kattha)
Land in Other Area (Kattha)
Total Land Owned (kattha)
Total Land (sq.m)
% of Land Loss
Remaining Land after Donation (sq.m)
% of Remaining Land After Donation
Remarks
13 Padam Bdr. Thakurathi 3.8 1 3.8 0.2 0 0.2 67.6 0 67.6 100
14 Harilal Thakurathi 3.5 1 3.5 0.2 40 40.2 13587.6 0 13587.6 100
15 Maheswor Chataut 3.5 1 3.5 0.2 0 0.2 67.6 0 67.6 100
16 Dansingh Thakurathi 3.55 1 3.55 0.79 0.79 267.02 0 267.02 100
17 Omprakash Gupta 3.6 1.5 5.4 0.2 0 0.2 67.6 0 67.6 100
18 Rajiv Dewal 3.5 1 3.5 0.2 0 0.2 67.6 0 67.6 100
19 Rajeswori Devi Dewal 3.6 1 3.6 0.2 0 0.2 67.6 0 67.6 100
20 Dharmendra Gupta 3.85 1 3.85 0.3 20 20.3 6861.4 0 6861.4 100
21 Parsuram Gautam 3.6 1 3.6 0.1 0 0.1 33.8 0 33.8 100
22 Hira Devi Bohora 3.8 1 3.8 0.2 10 10.2 3447.6 0 3447.6 100
23 Kanhyalal Dewal 3.5 1 3.5 0.2 18 18.2 6151.6 0 6151.6 100
24 Gopal Dewal 3.5 1 3.5 0.2 0 0.2 67.6 0 67.6 100
25 Dambar Datt Bhatta 3.55 1 3.55 0.2 20 20.2 6827.6 0 6827.6 100
26 Balaram Chataut 7.4 1 7.4 0.2 15 15.2 5137.6 0 5137.6 100
27 Kirta Bdr. Johra 4 1 4 0.2 80 80.2 27107.6 0 27107.6 100
28 Dharma Raj Joshi 7.6 1 7.6 0.4 20 20.4 6895.2 0 6895.2 100
29 Durga Devi Johra 5.6 1 5.6 0.3 60 60.3 20381.4 0 20381.4 100
30 Dharma singh Rawal 7.4 1 7.4 0.1 0 0.1 33.8 0 33.8 100
31 Abdul Samim 10.9 1 10.9 0.79 21 21.79 7365.02 0 7365.02 100
32 Maina Devi Bhandari 5.3 1 5.3 0.3 21 21.3 7199.4 0 7199.4 100
33 Parbati Devi Khadayat 5.5 1 5.5 0.3 80 80.3 27141.4 0 27141.4 100
34 Abdul Samim 5.5 1 5.5 0.3 0.3 101.4 0 101.4 100
35 Indra Singh Rawal 7.7 1 7.7 0.15 0 0.15 50.7 0 50.7 100
36 Lal Singh Thakurathi 3 1 3 0.15 10 10.15 3430.7 0 3430.7 100
37 Padam Raj Bohora 3.6 1 3.6 0.2 0 0.2 67.6 0 67.6 100
38 Bhubaneswori Kunwar 5.5 1 5.5 0 0 0 0 100
Annex ‐ Page 60
S.N Name of Owner Length of Affected Part /Area(m)
Width of Affected part/Area (m)
Approx. Area of Affected Part (sqm)
Area of Affected Kitta (Kattha)
Land in Other Area (Kattha)
Total Land Owned (kattha)
Total Land (sq.m)
% of Land Loss
Remaining Land after Donation (sq.m)
% of Remaining Land After Donation
Remarks
39 Geeta Kharel 11 1.3 14.3 0.3 40 40.3 13621.4 0 13621.4 100
40 Pabitra Aryal 5.5 1.3 7.15 0.3 1 1.3 439.4 0 439.4 100
41 Harka Singh Aiyar 7.4 1 7.4 0.3 30 30.3 10241.4 0 10241.4 100
42 Bimal Khadayat 7.4 1 7.4 0 100
43 Bhubaneswori Bogati 6.6 1 6.6 0 100
44 Hem Raj Bohora 7.4 1 7.4 0 100
45 Dinesh Shrestha 7 1 7 0.3 0.5 0.8 270.4 0 270.4 100
46 Dev Singh Ter 7.5 1.5 11.25 0.3 30 30.3 10241.4 0 10241.4 100
47 Gagan Bdr Singh 5.2 1.4 7.28 0.07 0 0.07 23.66 0 23.66 100
48 Khagesh Pd. Bhatta 3.5 1.4 4.9 0.07 1 1.07 361.66 0 361.66 100
49 Siddha Raj Bhatta 3.7 1.4 5.18 0.07 30 30.07 10163.66 0 10163.66 100
50 Deepu Budhayar 5.3 1.4 7.42 0.3 0 0.3 101.4 0 101.4 100
51 Ammar Budharar 5 1.4 7 0.3 0 0.3 101.4 0 101.4 100
52 Keshav Raj Panta 5 1.4 7 0.3 30 30.3 10241.4 0 10241.4 100
53 Bimal Raj Panta 5.8 1.4 8.12 0.3 20 20.3 6861.4 0 6861.4 100
54 Pawan Khadayat 4.4 1.4 6.16 0.3 20 20.3 6861.4 0 6861.4 100
55 Lal Bdr. Khadayat 6.3 1.4 8.82 0.3 20 20.3 6861.4 0 6861.4 100
56 Mukesh Rawal 6.6 1.4 9.24 0.35 20 20.35 6878.3 0 6878.3 100
57 Megh Raj Bohora 4.5 1.4 6.3 0.2 40 40.2 13587.6 0 13587.6 100
58 Dan Singh Thakurathi 4.5 1.4 6.3 0.2 20 20.2 6827.6 0 6827.6 100
59 Nawal Singh Saud 4.5 1.4 6.3 0
60 Krishnadatt Chataut 4.5 1.4 6.3 0.2 0 0.2 67.6 0 67.6 100
61 Shiv Raj Bhatta 3.6 1.4 5.04 0.2 0 0.2 67.6 0 67.6 100
62 Niraj Gupta 3.7 1.4 5.18 0.2 5 5.2 1757.6 0 1757.6 100
63 Yagya Raj Bhatta 3.5 1.4 4.9 0.2 5 5.2 1757.6 0 1757.6 100
64 Yagya Raj Bhatta 3.5 1.4 4.9 0.36 30 30.36 10261.68 0 10261.68 100
Annex ‐ Page 61
S.N Name of Owner Length of Affected Part /Area(m)
Width of Affected part/Area (m)
Approx. Area of Affected Part (sqm)
Area of Affected Kitta (Kattha)
Land in Other Area (Kattha)
Total Land Owned (kattha)
Total Land (sq.m)
% of Land Loss
Remaining Land after Donation (sq.m)
% of Remaining Land After Donation
Remarks
65 Parkash Rawal 3.5 1.4 4.9 0.2 20 20.2 6827.6 0 6827.6 100
66 Samser rawal 7 1.4 9.8 0.4 0 0.4 135.2 0 135.2 100
67 Lal Bdr. Rawal 7 1.4 9.8 0.4 30 30.4 10275.2 0 10275.2 100
68 Amar Shingh Khadayat 3.7 1.4 5.18 0.3 10 10.3 3481.4 0 3481.4 100
Area
occ
upie
d by
affe
cted
stru
ctur
e is
pub
lic la
nd (w
ithin
RoW
of e
xist
ing
road
); he
nce
the
owne
r will
loss
no
land
69 Tek Bdr. Saud 3.7 1.4 5.18 0.4 30 30.4 10275.2 0 10275.2 100
70 Uday Saud 3.7 1.4 5.18 0.2 2 2.2 743.6 0 743.6 100
71 Bam Dev Chataut 3.7 1.4 5.18 0.2 5 5.2 1757.6 0 1757.6 100
72 Chhotelal Batuwa 7 1.4 9.8 0.2 0.15 0.35 118.3 0 118.3 100
73 Raj Kumar Dewal 3 1.4 4.2 0.2 4 4.2 1419.6 0 1419.6 100
74 Umashankar Dewal 7 1.4 9.8 0.2 0.05 0.25 84.5 0 84.5 100
75 Bhuwan Chataut 2.8 1.4 3.92 0.3 40 40.3 13621.4 0 13621.4 100
76 Ganesh Chataut 3.1 1.4 4.34 0.3 30 30.3 10241.4 0 10241.4 100
77 Bal Devi Kharel 5.4 1.1 5.94 0.3 20 20.3 6861.4 0 6861.4 100
78 Bashu Dev Bohora 5.5 1.1 6.05 0.3 20 20.3 6861.4 0 6861.4 100
79 Mohan Singh Bista 6.2 1.1 6.82 0.3 20 20.3 6861.4 0 6861.4 100
80 Kalpana devi Bhusal 5.8 1.1 6.38 0.3 0 0.3 101.4 0 101.4 100
81 Narai Bhatta 4.4 1.1 4.84 0.3 40 40.3 13621.4 0 13621.4 100
82 Anita Joshi 6 1.1 6.6 0.3 20 20.3 6861.4 0 6861.4 100
83 Bhuwan Kharel 5.6 1.1 6.16 0.3 20 20.3 6861.4 0 6861.4 100
84 Poonam Bhatta 5.4 1.1 5.94 0.3 30 30.3 10241.4 0 10241.4 100
85 Basanti Thagunna 5.4 1.1 5.94 0.3 4 4.3 1453.4 0 1453.4 100
86 Sova Dewal 3 1.1 3.3 0.15 0.15 50.7 0 50.7 100
87 Mandhari Devi Giri 5.5 1 5.5 0.3 40 40.3 13621.4 0 13621.4 100
88 Laxman Singh Bista 7.8 1 7.8 0.3 30 30.3 10241.4 0 10241.4 100
89 Hema Pandey 4.2 1.8 7.56 0.12 40 40.12 13560.56 0 13560.56 100
90 Rupa Aryal 4 1.6 6.4 0.12 40 40.12 13560.56 0 13560.56 100
Annex ‐ Page 62
S.N Name of Owner Length of Affected Part /Area(m)
Width of Affected part/Area (m)
Approx. Area of Affected Part (sqm)
Area of Affected Kitta (Kattha)
Land in Other Area (Kattha)
Total Land Owned (kattha)
Total Land (sq.m)
% of Land Loss
Remaining Land after Donation (sq.m)
% of Remaining Land After Donation
Remarks
91 Cholanath Bhandari 4.1 1.6 6.56 0.12 0.5 0.62 209.56 0 209.56 100
92 Man Singh Mahara 4.1 1.6 6.56 0.12 14 14.12 4772.56 0 4772.56 100
93 Sher Shingh Bhandari 4.5 1.6 7.2 0 0 100
94 Bir Bdr. Sunar 4.5 1.6 7.2 0.12 30 30.12 10180.56 0 10180.56 100
95 Omkar Panta 4.4 1.6 7.04 0.12 5 5.12 1730.56 0 1730.56 100
96 Prakash Shah 4.4 1.6 7.04 0.12 6 6.12 2068.56 0 2068.56 100
97 Hari Datt Bhatta 4.6 1.4 6.44 23.78 23.78 8037.64 8037.64 100 V6: Malpot/Napi Karalaya-E/W Highway)
1 Harilal Joshi 9.9 0.1 0.99 0.49 20 20.49 6925.62 0.01 6925.62 99.992 Patiram Chunara 14.8 1.8 26.64 0.49 10 10.49 3545.62 0.75 3545.62 99.25
3 Tek Raj Bhatta 6.4 1.8 11.52 1 15 16 5408 0.21 5408 99.79
H1: East-West Gully-1 100
1 Gajendra Bdr. Shah 18.3 1.9 34.77 0.3 30 30.3 10241.4 0 10241.4 100
The
affe
cted
are
a i.e
are
a oc
cupi
ed b
y af
fect
ed
stru
ctur
e is
pub
lic la
nd (w
ithin
RoW
of e
xist
ing
road
); he
nce
the
owne
r will
loss
no
land
2 Shambhu Bharati 18.3 1.9 34.77 0.4 30 30.4 10275.2 0 10275.2 100
3 Chintamani Joshi 18.4 1.9 34.96 0.2 6 6.2 2095.6 0 2095.6 100
4 Manju Bhatta 18.3 1.9 34.77 0.2 0 0.2 67.6 0 67.6 100
5 Shreeram Chataut 18.3 1.9 34.77 0.59 30 30.59 10339.42 0 10339.42 100
6 Hajari Singh Pujara 10 1.9 19 0.3 10 10.3 3481.4 0 3481.4 100
7 Gopal Singh Budha 8.5 1.9 16.15 0.4 30 30.4 10275.2 0 10275.2 100
8 Bhuban Pandey 18.3 1.9 34.77 0.2 15 15.2 5137.6 0 5137.6 100
9 Devraj Mishra 18.3 1.9 34.77 0.29 20 20.29 6858.02 0 6858.02 100
10 Min Raj Bhatta 18.3 1.9 34.77 0.49 120 120.49 40725.62 0 40725.62 100
11 Prem Shah 4 1.9 7.6 0.2 10 10.2 3447.6 0 3447.6 100
12 Narendra Bohora 3.8 1.9 7.22 0.2 34 34.2 11559.6 0 11559.6 100
13 Deepak Gupta 10.7 1.9 20.33 0.2 0 0.2 67.6 0 67.6 100
14 Padam Bdr. Bhandari 7.6 1.9 14.44 0.2 2 2.2 743.6 0 743.6 100
Annex ‐ Page 63
S.N Name of Owner Length of Affected Part /Area(m)
Width of Affected part/Area (m)
Approx. Area of Affected Part (sqm)
Area of Affected Kitta (Kattha)
Land in Other Area (Kattha)
Total Land Owned (kattha)
Total Land (sq.m)
% of Land Loss
Remaining Land after Donation (sq.m)
% of Remaining Land After Donation
Remarks
15 Laxmi Datt Bhatta 9 1.9 17.1 0.2 5 5.2 1757.6 0 1757.6 100
16 Rudra Singh Bhandari 3.4 1.9 6.46 0.2 20 20.2 6827.6 0 6827.6 100
17 Karunakar Paneru 7.3 1.9 13.87 0.2 20 20.2 6827.6 0 6827.6 100
18 Harilal Bhatta 10 1.9 19 0.3 30 30.3 10241.4 0 10241.4 100
19 Kalpana Thapa 18.3 1.9 34.77 0.4 10 10.4 3515.2 0 3515.2 100
20 Padam Bdr. Thakurathi 18.3 1.9 34.77 0.4 18 18.4 6219.2 0 6219.2 100
21 Shanti Damai 12.5 1.9 23.75 0.46 10 10.46 3535.48 0 3535.48 100
22 kalu Singh+jagat Bhandari 6.6 1.9 12.54 0.2 0.15 0.35 118.3 0 118.3 100
23 Padam Bdr. Thakurathi 19.2 1.9 36.48 0.2 4 4.2 1419.6 0 1419.6 100
H2: East-West Gully-2 100
1 Mohan Singh Dhami 18.5 0.7 12.95 0.2 8 8.2 2771.6 0 2771.6 100
The
affe
cted
are
a i.e
are
a oc
cupi
ed b
y af
fect
ed s
truct
ure
is
publ
ic la
nd (w
ithin
RoW
of e
xist
ing
road
); he
nce
the
owne
r will
loss
no
land
2 Jaya Kisan Bhatta 18.5 0.7 12.95 0.3 0 0.3 101.4 0 101.4 100
3 Haris Chandra Bhatta 18.5 0.5 9.25 0.9 50 50.9 17204.2 0 17204.2 100
4 Laba Raj Bhatta 18.5 0.5 9.25 0.4 0 0.4 135.2 0 135.2 100
5 Sunil Panta 18.5 0.1 1.85 0.2 100 100.2 33867.6 0 33867.6 100
6 Madan Paudyal 19 0.45 8.55 0.4 0 0.4 135.2 0 135.2 100
7 Tikaram Bohora 12 0.45 5.4 0.3 50 50.3 17001.4 0 17001.4 100
8 Khem Raj Bohora 6.8 0.45 3.06 0.3 30 30.3 10241.4 0 10241.4 100
9 Govinda Ballav Joshi 20 0.6 12 0.3 40 40.3 13621.4 0 13621.4 100
10 Jaimati Devi Bhatta 18.5 0.6 11.1 0.4 2 2.4 811.2 0 811.2 100
11 Bashudev Bohora 18.5 0.45 8.325 0.3 20 20.3 6861.4 0 6861.4 100
12 Sita Devi K.C 18.5 0.45 8.325 0.25 10 10.25 3464.5 0 3464.5 100
13 Ganesh Bohora 18.5 0.5 9.25 0.4 10 10.4 3515.2 0 3515.2 100
14 Kamala Devi Bohora 18.5 0.5 9.25 0.2 1 1.2 405.6 0 405.6 100
15 Durga Devi Jora 18.5 0.35 6.475 0.2 40 40.2 13587.6 0 13587.6 100
16 Dharma Raj joshi 18.5 0.35 6.475 0.4 20 20.4 6895.2 0 6895.2 100
Annex ‐ Page 64
S.N Name of Owner Length of Affected Part /Area(m)
Width of Affected part/Area (m)
Approx. Area of Affected Part (sqm)
Area of Affected Kitta (Kattha)
Land in Other Area (Kattha)
Total Land Owned (kattha)
Total Land (sq.m)
% of Land Loss
Remaining Land after Donation (sq.m)
% of Remaining Land After Donation
Remarks
H-3: Hospital Road (Gully 6 to Gully 1/ East-West Gully-3)
None
H-4: Campus Road (Janki tole) to Gully 1( East-West Gully-4)
None
H-5: Sarswati Tole Road 1 (East West Gully-5, Katan Area)
1 Bisnudatt Bhatta 35 0.55 19.25 1.65 1.65 557.7 0 557.7 100
The
affe
cted
are
a i.e
are
a oc
cupi
ed b
y af
fect
ed s
truct
ure
is
publ
ic la
nd (w
ithin
RoW
of e
xist
ing
road
); he
nce
the
owne
r will
loss
no
land
2 Bajir Singh Aiyar 18.3 1 18.3 1.65 1.65 557.7 0 557.7 100
3 Khagendra Chand 18.3 0.3 5.49 1.65 30 31.65 10697.7 0 10697.7 100
4 Ganga Datt Joshi 21.7 0.85 18.445 1.65 10 11.65 3937.7 0 3937.7 100
5 Rajendra Chand 17.7 0.2 3.54 1.65 35 36.65 12387.7 0 12387.7 100
6 Anandi Panta 18.7 0.2 3.74 1.65 20 21.65 7317.7 0 7317.7 100
7 Parmeswori Pandey 18.3 0.3 5.49 1.65 20 21.65 7317.7 0 7317.7 100
8 Hom Bdr. Panthi 18.3 0.3 5.49 1.65 20 21.65 7317.7 0 7317.7 100
9 Dharma Nanda Bhatta 18.3 0.3 5.49 1.65 1.65 557.7 0 557.7 100
10 Sashi Ojha 18.3 0.5 9.15 1.65 10 11.65 3937.7 0 3937.7 100
11 Laxman Singh Bhandari 18.3 0.3 5.49 1.65 40 41.65 14077.7 0 14077.7 100
12 Ganesh Bohora 18.3 0.5 9.15 1.65 5 6.65 2247.7 0 2247.7 100
13 Narayan Singh Saud 19 0.9 17.1 1.65 0 1.65 557.7 0 557.7 100
14 Kamala Bohora 20 0.9 18 1.65 1.65 557.7 0 557.7 100
15 Man Bdr. Sunar 18.8 0.8 15.04 1.65 1.65 557.7 0 557.7 100
16 Tikaram Bhatta 18.3 0.8 14.64 1.65 5 6.65 2247.7 0 2247.7 100
17 Tekendra Bhatta 18.3 0.8 14.64 1.65 1.65 557.7 0 557.7 100
18 Damodar Pandey 18.3 0.9 16.47 1.65 18 19.65 6641.7 0 6641.7 100
19 Dr. Bhojraj Panta 18.3 0.9 16.47 1.65 10 11.65 3937.7 0 3937.7 100
20 Bishnu Awasti 18.3 0.9 16.47 1.65 30 31.65 10697.7 0 10697.7 100
21 Puspamani Bhatta 19 0.7 13.3 1.65 15 16.65 5627.7 0 5627.7 100
Annex ‐ Page 65
S.N Name of Owner Length of Affected Part /Area(m)
Width of Affected part/Area (m)
Approx. Area of Affected Part (sqm)
Area of Affected Kitta (Kattha)
Land in Other Area (Kattha)
Total Land Owned (kattha)
Total Land (sq.m)
% of Land Loss
Remaining Land after Donation (sq.m)
% of Remaining Land After Donation
Remarks
22 Keshav Nayak 9.6 0.7 6.72 1.65 6 7.65 2585.7 0 2585.7 100
23 Kamal Shrestha 18.3 0.7 12.81 1.65 20 21.65 7317.7 0 7317.7 100
24 Gauri Datt Joshi 27 0.7 18.9 1.65 10 11.65 3937.7 0 3937.7 100
25 Lalitananda Joshi 18.5 0.7 12.95 1.65 12 13.65 4613.7 0 4613.7 100
26 Somraj Aryal 12.3 0.7 8.61 1.65 15 16.65 5627.7 0 5627.7 100
27 Man Singh Rawat 20 1.3 26 1.65 25 26.65 9007.7 0 9007.7 100
28 Purna Raj Bhatta 7 1.3 9.1 1.65 17 18.65 6303.7 0 6303.7 100
H-6:Sarswati Tole Road 2 (East West Gully-6, Katan Area)
1 Devaki Bam 18.5 1.15 21.275 1.65 30 31.65 10697.7 0 10697.7 100
The
owne
r will
loss
no
land
2 Kapil Joshi 18.5 1.15 21.275 1.65 30 31.65 10697.7 0 10697.7 100
3 Shyam Chand 18.8 1.15 21.62 1.65 0 1.65 557.7 0 557.7 100
4 Basant Bdr. Singh 18.2 1.15 20.93 1.65 30 31.65 10697.7 0 10697.7 100
5 Parwati Devi Chand 18.3 1.15 21.045 1.65 30 31.65 10697.7 0 10697.7 100
6 Tara Joshi 18.5 1.15 21.275 1.65 27 28.65 9683.7 0 9683.7 100
7 Siddharaj Bhatta 18.3 1.15 21.045 1.65 20 21.65 7317.7 0 7317.7 100
8 Mohandev Joshi 18.3 1.15 21.045 1.65 12 13.65 4613.7 0 4613.7 100
9 Dattaram Dasrath Bhatta 18.5 1.15 21.275 1.65 20 21.65 7317.7 0 7317.7 100
10 Manmati Chand 18.3 1.15 21.045 1.65 0 1.65 557.7 0 557.7 100
11 Dal Bdr. Chand 23 1.15 26.45 1.65 20 21.65 7317.7 0 7317.7 100
H-7: Sarswati Tole Road 3 (East West Gully-7, Katan Area)
1 Pushkar Giri 38 0.9 34.2 1.65 2 3.65 1233.7 0 1233.7 100
Area
occ
upie
d by
af
fect
ed s
truct
ure
is
publ
ic la
nd; h
ence
the
owne
r will
loss
no
land
2 Gagan Giri 18.6 0.9 16.74 1.65 5 6.65 2247.7 0 2247.7 100
3 Dilmaya Bhatta 21.3 0.9 19.17 1.65 12 13.65 4613.7 0 4613.7 100
4 Tek Raj Panta 18.3 0.9 16.47 1.65 40 41.65 14077.7 0 14077.7 100
5 Sova Devi Joshi 18.3 0.9 16.47 1.65 15 16.65 5627.7 0 5627.7 100
6 Kapil Panta 18.3 0.9 16.47 1.65 0 1.65 557.7 0 557.7 100
Annex ‐ Page 66
S.N Name of Owner Length of Affected Part /Area(m)
Width of Affected part/Area (m)
Approx. Area of Affected Part (sqm)
Area of Affected Kitta (Kattha)
Land in Other Area (Kattha)
Total Land Owned (kattha)
Total Land (sq.m)
% of Land Loss
Remaining Land after Donation (sq.m)
% of Remaining Land After Donation
Remarks
7 Karan Nath 18.3 0.9 16.47 1.65 0 1.65 557.7 0 557.7 100
8 Komala Devi Chand 18.3 0.9 16.47 1.65 2 3.65 1233.7 0 1233.7 100
9 Umadatt Bhatta 11.9 0.9 10.71 1.65 0 1.65 557.7 0 557.7 100
10 Ambika Joshi 24.8 0.9 22.32 1.65 8 9.65 3261.7 0 3261.7 100
11 Krishna P.d Bohora 19.8 0.9 17.82 1.65 12 13.65 4613.7 0 4613.7 100
12 Dhani Datt Panta 22.3 1.25 27.875 1.65 30 31.65 10697.7 0 10697.7 100
13 Pramananda Joshi 24.1 1.25 30.125 1.65 13 14.65 4951.7 0 4951.7 100
14 Kalpana K.C 18.3 1.2 21.96 1.65 30 31.65 10697.7 0 10697.7 100
15 Sitaram Joshi 19.2 1.2 23.04 1.65 31 32.65 11035.7 0 11035.7 100
16 Prakash Bdr. Singh 18.5 1.2 22.2 1.65 30 31.65 10697.7 0 10697.7 100
17 Rana singh Bhandari 18.5 1.2 22.2 1.65 15 16.65 5627.7 0 5627.7 100
18 Gajendra Thapa 18.2 1.2 21.84 1.65 25 26.65 9007.7 0 9007.7 100
19 Purnananda Bhatta 18.2 1.2 21.84 1.65 25 26.65 9007.7 0 9007.7 100
20 Bhojraj Pandey 18.8 1.2 22.56 1.65 15 16.65 5627.7 0 5627.7 100
21 Jayanti Chand 36.8 1 36.8 30 30 10140 0 10140 100
22 Bhanubhakta Joshi 18.4 1 18.4 1.65 7 8.65 2923.7 0 2923.7 100
23 Shusila Pandey 18.4 1 18.4 1.65 5 6.65 2247.7 0 2247.7 100
24 Mahadev Bhatta 18.8 1.2 22.56 1.65 10 11.65 3937.7 0 3937.7 100
25 Tara Devi Bhatta 18.3 1.2 21.96 1.65 10 11.65 3937.7 0 3937.7 100
26 Chandra Dev Upadhyay 18.3 1 18.3 1.65 1 2.65 895.7 0 895.7 100
27 G.K Bhat 18.3 1 18.3 3.3 20 23.3 7875.4 0 7875.4 100
28 Narad Pandey 70 1 70 4.12 30 34.12 11532.56 0 11532.56 100
29 Ran Bdr. Pal 40 1 40 1.65 10 11.65 3937.7 0 3937.7 100
H-8: Sarswati Tole Road 4 (East West section, Katan Area) 1 Tara Devi Joshi 29.7 0.65 19.305 2.75 20 22.75 7689.5 0 7689.5 100
owne
r w
ill lo
ss
no
land
2 Shanti Devi Bhandari 18.3 0.65 11.895 1.65 0 1.65 557.7 0 557.7 100
Annex ‐ Page 67
S.N Name of Owner Length of Affected Part /Area(m)
Width of Affected part/Area (m)
Approx. Area of Affected Part (sqm)
Area of Affected Kitta (Kattha)
Land in Other Area (Kattha)
Total Land Owned (kattha)
Total Land (sq.m)
% of Land Loss
Remaining Land after Donation (sq.m)
% of Remaining Land After Donation
Remarks
3 Rajaya Swar 28.8 0.85 24.48 1.65 20 21.65 7317.7 0 7317.7 100
4 Laba Dev Pandey 36.6 0.85 31.11 1.98 20 21.98 7429.24 0 7429.24 100
5 Bishnu Aryal 18.3 1.15 21.045 1.65 0 1.65 557.7 0 557.7 100
6 Basanta Singh 18.3 1.15 21.045 1.65 5 6.65 2247.7 0 2247.7 100
7 Kamala Nanda Joshi 18.4 1.15 21.16 1.65 1.65 557.7 0 557.7 100
8 Hemlal Sapkota 36.6 1.15 42.09 3.3 3.3 1115.4 0 1115.4 100
9 Sita Devi Joshi 18.3 1.15 21.045 1.65 9 10.65 3599.7 0 3599.7 100
10 Ganesh Chand 18.6 1.15 21.39 1.65 0 1.65 557.7 0 557.7 100
11 Tika singh Dhami 18.3 1.15 21.045 1.65 5 6.65 2247.7 0 2247.7 100
12 Dr. Madan Singh Karki 18.4 1.15 21.16 1.65 5 6.65 2247.7 0 2247.7 100
13 Dharmanand Bhatta 26 1.15 29.9 2.34 30 32.34 10930.92 0 10930.92 100
14 Dashrath Joshi 26 1.25 32.5 2.34 18 20.34 6874.92 0 6874.92 100
15 Uttara Chand 18.3 1.25 22.875 1.65 15 16.65 5627.7 0 5627.7 100
16 Maya Devi Joshi 18.3 1.25 22.875 1.65 120 121.65 41117.7 0 41117.7 100
17 Harsa Narain Upadhyay 18.5 1.25 23.125 1.65 40 41.65 14077.7 0 14077.7 100
18 Bishnu datt Awasti 18 1.25 22.5 1.65 7 8.65 2923.7 0 2923.7 100
19 Nirajan Gautam 18.3 1.25 22.875 1.65 20 21.65 7317.7 0 7317.7 100
20 Shavitri Devi Panta 18.3 1.25 22.875 1.65 0 1.65 557.7 0 557.7 100
21 Krishna Bdr. Chand 18.6 1.25 23.25 1.65 0 1.65 557.7 0 557.7 100
22 Janaki Devi Bam 18.3 1.25 22.875 1.65 0 1.65 557.7 0 557.7 100
23 Dammar Datt Bogati 18.3 1.25 22.875 1.65 30 31.65 10697.7 0 10697.7 100
24 Hari Chand 19.3 1.25 24.125 1.65 20 21.65 7317.7 0 7317.7 100
H-9: Eye Hospital Road (East-West)
1 Omprakash Dedwal 14 1.5 21 1.65 0 100
H-10 : Hospital Road (Gully 1 to Bhagatpur Marg) 100
1 Krishna Prasad Bhandari 5.6 0.6 3.36 0.3 13 13.3 4495.4 0 4495.4 100
Annex ‐ Page 68
S.N Name of Owner Length of Affected Part /Area(m)
Width of Affected part/Area (m)
Approx. Area of Affected Part (sqm)
Area of Affected Kitta (Kattha)
Land in Other Area (Kattha)
Total Land Owned (kattha)
Total Land (sq.m)
% of Land Loss
Remaining Land after Donation (sq.m)
% of Remaining Land After Donation
Remarks
2 Kedar Prasad Bhandari 6.7 1.2 8.04 0.3 13 13.3 4495.4 0 4495.4 100
3 Nandalal Joshi 6.4 1.2 7.68 0.3 10 10.3 3481.4 0 3481.4 100
4 Kamala devi Bhatta 9.1 1 9.1 0.3 50 50.3 17001.4 0 17001.4 100
5 Ravi Joshi 16.3 1 16.3 0.43 0 0.43 145.34 0 145.34 100
6 Mina Panta 5 0.8 4 0.3 20 20.3 6861.4 0 6861.4 100
7 Lokraj Panta 16 0.7 11.2 1.43 20 21.43 7243.34 0 7243.34 100
8 Lal Bdr.Thapa 18.7 0.7 13.09 1.65 30 31.65 10697.7 0 10697.7 100
9 Raji Chand 24.7 1.6 39.52 1.65 1.65 557.7 0 557.7 100
10 Dhir Samser Kunuwar 8.65 0.6 5.19 1.65 5 6.65 2247.7 0 2247.7 100
Hotel Opera road, E-W)
1 Binod Kumar Agrawal 8.45 2 16.9 3.09 6 9.09 3072.42 0 3072.42 100
2 Krishna P.D Bogati 16.7 0.7 11.69 0.3 0 0.3 101.4 0 101.4 100
3 Harilal Paneru 15.3 0.7 10.71 0.34 20 20.34 6874.92 0 6874.92 100
Madan chowk-Dashrath Chowk - Napi - Bhagatpur Chowk Road
1 Duraga Datt Bohora 10.6 0.2 2.12 2 40 42 14196 0 14196 100
2 Ratna Singh Thakurathi 5.25 0.3 1.575 1.65 0.18 1.83 618.54 0 618.54 100
3 Gorakh Bdr. Chand 5.25 0.3 1.575 0.4 12 12.4 4191.2 0 4191.2 100
4 Omparkash Bhandari 10 0.25 2.5 1.65 10 11.65 3937.7 0 3937.7 100
5 Krishna Datt Bhatta 17.2 0.4 6.88 1.98 14 15.98 5401.24 0 5401.24 100
6 Damar Devi Kuwar 10 0.9 9 1.65 20 21.65 7317.7 0 7317.7 100
Traffic Chowk- Dashrat - BP Chowk Road
None Source: Field Measurement 2019
Annex ‐ Page 69
ANNEX- 3 (B): Minimum Land Rate and Current Market Price of Land
S.N
Name of Road
Ward No.
Minimum rate of land of FY 2077 / 078
fixed by Land Revenue Office
(NRs/Kattha)
Annual increment trend of minimum rate of
land
Current Market Rate (NRs / Kattha)
1 M1 : Bhasi- Rautela Road 1 2709040 10 % 4000000
2 M2 : Bhanuchowk -Bishnudham Road 3,6 8127120 10 % 5000000
3 M3: Suklaphanta Marga(Bhanuchowk-Madan Chowk-Airport Road)
Bhanu Chowk – Madan Chowk 4 8804380 10 % 29000000
Madan Chowk - Airport 4 6433970 10 % 10000000
4 M4: Airport-Airighat Road 17,12,16 2709040 10 % 5500000
5 V5: Gully No-5 Road (Campus Road, North-South section) 4,18 8973695 10 % 17600000
6 V-4: Gully No-4 Road (North-South section) 4,18 8973695 10 % 17600000
7 V-3 : Gully No-3 Road (North-South Section) 4,18 8973695 10 % 17600000
8 V-2: Gully No-2 Road (North-South section) 4,18 8973695 10 % 17600000
9 V-1: Gully No-1(Shalgadhi Road, North-South Section) 4 8973695 10 % 20000000
10 V6: Malpot/Napi Karalaya-E/W Highway) 4 8973695 10 % 9500000
11 H1: East-West Gully-1 4,18 8973695 10 % 12000000
12 H2: East-West Gully-2 4 8973695 10 % 12000000
13 H-3: Hospital Road (Gully 6 to Gully 1/ East-West Gully-3) 4,18 8973695 10 % 12000000
14 H-4: Campus Road (Janki tole) to Gully 1( East-West Gully-4) 18 2539725 10 % 7500000
15 H-5: Sarswati Tole Road 1 (East West Gully-5, Katan Area) 18 1523835 10 % 6000000
16 H-6:Sarswati Tole Road 2 (East West Gully-6, Katan Area) 18 1523835 10 % 6000000
17 H-7: Sarswati Tole Road 3 (East West Gully-7, 18 1523835 10 % 5500000
Annex ‐ Page 70
S.N
Name of Road
Ward No.
Minimum rate of land of FY 2077 / 078
fixed by Land Revenue Office
(NRs/Kattha)
Annual increment trend of minimum rate of
land
Current Market Rate (NRs / Kattha)
Katan Area)
18 H-8: Sarswati Tole Road 4 (East West section, Katan Area) 18 1523835 10 % 5500000
19 H-9: Eye Hospital Road (East-West) 18 2607451 10 % 10000000
20 H-10 : Hospital Road (Gully 1 to Bhagatpur Marg) 18 5587395 10 % 20000000
21 Hotel Opera road, E-W) 4 10158900 10 % 15000000
22 Madan chowk-Dashrath Chowk - Napi - Bhagatpur Chowk Road 4 5587395 10 % 29000000
23 Traffic Chowk- Dashrat - BP Chowk Road 4 4910135 10 % 11700000
Source: Land Reform and Land Revenue Office, Mahendranagar, Kanchanpur, 2020