50 MW WIND FARM NEAR EREYMENTAU (Interdisciplinary Design Project)
Transcript of 50 MW WIND FARM NEAR EREYMENTAU (Interdisciplinary Design Project)
50 MW WIND FARM NEAR EREYMENTAU (Interdisciplinary Design Project)
Bachelor of Engineering
(Electrical, Civil, Mechanical)
Yntymak Abukhanov
Sanzhar Korganbayev
Yelaman Serik
Yerkebulan Saparov
Shakarim Irmukhametov
2015
ii
DECLARATION
We hereby declare that this report entitled “title of report” is the result of our own
project work except for quotations and citations which have been duly acknowledged.
We also declare that it has not been previously or concurrently submitted for any other
degree at Nazarbayev University.
Names:
Yntymak Abukhanov
Sanzhar Korganbayev
Yelaman Serik
Yerkebulan Saparov
Shakarim Irmukhametov
Due date: 20.04.2015
iii
Acknowledgement
We would like to express our special thanks of gratitude to our Professor
Alexander Ruderman whose advising was very helpful for this project.
iv
ABSTRACT
Increase of energy consumption in the world and importance of CO2 reduction
stimulate development of alternative sources of energy. Kazakhstan territory has high
potential for wind energy industry development. As a result, Republic of Kazakhstan
increases energy production from wind, solar and other renewable resources.
This purpose of the Project is Feasibility Report for construction of 50 MW wind farm
station near Ereymentau, Akomla region. Initially, current wind industry situation is
investigated in Chapter 1. After that, Ereymentau’ wind potential assessment is done in order
to calculate possible energy production. Then, turbine type is chosen and technical details of
wind park is analyzed. Afterward, detailed economy analysis of the project is given in
Chapter 6. Safety and Risk assessment are covered in Chapters 7 and 8. Next, environmental
impact is discussed in Chapter 9. Project Management is given in the last Chapter.
Summary of Final Feasibility of the wind park Project near Ereymentau and
recommendations are given in Chapter 11.
LITERATURE REVIEW
Copious amount of literature has been reviewed during wind farm project.
Nevertheless, several main sources of information can be described below. The main sources
of data related to site analysis and current wind industry condition in Kazakhstan are The
Kazakhstan electricity association Committee on renewable energy sources official site and
Samruk-Energy Report on Ereymentau wind farm. In addition, main source of wind theory is
Ali Sayigh’s “Comprehensive renewable energy: Volume 2-Wind Energy” issued in
Nazarbayev University library. Danish wind industry association official site and WindFarm
software tutorials from ReSoft company were intensively used for calculations of technical
aspects for this project.
v
Table of content List of tables: .......................................................................................................................................................................vii
List of figures: .....................................................................................................................................................................vii
GLOSSARY .......................................................................................................................................................................... viii
ACRONYMS ........................................................................................................................................................................... ix
CHAPTER 1. INTRODUCTION ............................................................................................................................................... 1
1.1 Purpose and vision of project ........................................................................................................................... 1
1.2 Wind energy development trend in the world.......................................................................................... 1
1.3 Origin and main characteristics of wind ...................................................................................................... 2
1.4 Energy industry in Kazakhstan ........................................................................................................................ 4
1.5 Promising wind farm constructions in Ereymentau region ................................................................ 6
CHAPTER 2. SITE SELECTION ................................................................................................................................................ 7
CHAPTER 3. SITE ANALYSIS................................................................................................................................................... 8
3.1 Ereymentau’s wind potential assessment................................................................................................... 8
3.2 Electricity consumption and load in Akmola region ............................................................................11
3.3 Climate of the region...........................................................................................................................................13
3.4 Wind energy development Law Regulations ...........................................................................................13
CHAPTER 4. TURBINE CHOOSE ...........................................................................................................................................14
4.1Wind turbine technologies and properties ................................................................................................14
4.2 Defining criteria for wind turbine choose .................................................................................................14
4.3 Wind turbine power curve, comparing alternatives over Weibull- power curve graphs...15
4.4 Power losses ...........................................................................................................................................................18
CHAPTER 5. PROJECT DETAILS............................................................................................................................................20
5.1 State authorities’ approval ...............................................................................................................................20
5.2 Project Location Details.....................................................................................................................................20
5.3 Internal roads and electrical grid..................................................................................................................21
5.4 Noise, shadow and aesthetic aspects...........................................................................................................21
5.5 Wake effect..............................................................................................................................................................22
5.6 Electrical characteristics of wind farm .......................................................................................................23
5.7 Power balance .......................................................................................................................................................24
5.8 Foundation ..............................................................................................................................................................25
CHAPTER 6. ECONOMY .........................................................................................................................................................28
6.1 Cost Estimation .....................................................................................................................................................28
6.2. Financial Costs. IRR. Payback Period..........................................................................................................31
CHAPTER 7: P ROFESSIONAL ETHICS. COMMUNITY HEALTH&SAFETY ..................................................................32
vi
7.1 Professional ethics ...............................................................................................................................................32
7.2 Community health & Safety .............................................................................................................................33
7.2.1 Ice throw ......................................................................................................................................................33
7.2.2 Electromagnetic interference .............................................................................................................33
7.2.3 Public Access ..............................................................................................................................................34
7.2.4 Shadow flicker ...........................................................................................................................................34
7.3 Effect on local population .................................................................................................................................34
CHAPTER 8. RISK ASSESSMENT .........................................................................................................................................36
CHAPTER 9: ENVIRONMENT ................................................................................................................................................44
9.1 Soil and groundwater .............................................................................................................................44
9.2 Surface water .............................................................................................................................................44
9.3 Biodiversity and plant impact.............................................................................................................45
9.4 Cultural heritage aspects and plant impact .....................................................................................45
9.5 Landscape and visual aspects and plant impact .........................................................................45
CHAPTER 10. PROJECT MANAGEMENT ..............................................................................................................................46
RESULTS AND DISCUSSION ................................................................................................................................................49
CONCLUSION ..........................................................................................................................................................................50
REFERENCE LIST ..................................................................................................................................................................... 1
APPENDIX ................................................................................................................................................................................. A
vii
List of tables: Table 1.3.1 Hellmann exponent and roughness length for different types of terrain
Table 1.3.2 Variation of Monin-Obukhov length L
Table 3.1.1 Wind data
Table 3.2.1 Electricity consumption and electrical load in numbers for Akmola region in 2010
Table 3.2.2 Electric energy consumption and generation for a period of 2012- 2021
Table 4.1.1 Comparison between HAWT and VAWT
Table 4.3.1 Results of capacity factor calculations for individual turbine
Table 4.3.2 Wind farm energy output data
Table 4.3.3 Final wind plant output parameters
Table 5.8.1 Power balance for Akmola oblast
Table 5.9.1 Main parameters for Terzaghi equation
Table 5.9.2 Additional parameters for General equation
Table 5.9.3 Obtained values for Terzaghi equation
Table 8.1 Identified risks of the project and their risk indexes
Table 8.2 General risk matrix
Table 8.3 Risk indexes’ criteria
Table 8.4 Risk frequency indexes’ definitions
Table 8.5 Risk matrix of the wind farm project
Table 10.1 Project management plan
List of figures: Figure 1.4.1 Energy resource use in Kazakhstan
Figure 3.1.1 Wind and energy roses for the site
Figure 3.1.2 Seasonal pattern of wind speed
Figure 3.2.1 Electric energy consumption by industry in Akmola region in 2010
Figure 4.3.1 Power curves for alternative considered.
Figure 4.3.2 Comparison of annual electric energy production by alternatives.
Figure 4.3.3 Comparison of power output for summer and winter seasons
Figure 5.3.1 Site layout map by Samruk-Green Energy
Figure 5.5.2 Shadow plot
Figure 5.7.1 Schematic diagram of wind farm connection to national grid.
Figure 5.9.1 The foundation
Figure 6.1.1 Declining Cost of Wind Energy over Time
Figure 6.1.2 Kazakhstan inflation rate, 2009-2015
Figure 10.1 Project organization
viii
GLOSSARY Capacity factor- ratio of actual energy production of the machine for a given time period to
the energy production of the same machine if it had operated at its rated power output
Feed-in tariff- policy mechanism developed for the support of renewable energy
technologies, through the award of a certain payment per kWh for electricity produced by
renewable resource and fed into the grid
Technical availability- time of actual operation of machine without scheduled maintenance,
unforeseen faults, etc
Wind farm-wind park- a group of wind turbines installed within the boundaries of a given
area
Betz limit- the maximum theoretical value that the aerodynamic coefficient may get=0.59
Cut- in speed- the wind speed at which a given wind turbine starts to operate
Cut-out speed- the wind speed at which a given wind turbine ceases to operate
Rated power speed – the minimum wind speed at which a given wind turbine operated at its
rated power
Hub- the center of a wind generator rotor, which holds the blades in place and attaches to the
shaft
Yaw- rotation parallel to the ground. A wind generator yaws to face winds coming from
different directions
Grid-connected- a wind turbine is grid-connected when its output is channeled directly into a
national grid
Social benefits- benefits for the society in terms of development, job positions, environmental
behavior and income increase
ix
ACRONYMS EBRD European Bank for Reconstruction and Development
KWh kilowatt-hour
UNDP United Nations Development Program
KEGOC Kazakhstan Electricity Grid Operating Company
CC Capital Costs (Initial Investments, Capital Investments)
CIF Cash- in-flows
COF Cash-out-flows
EUR Euro
FV Future Worth
GW Gigawatt
KEGOC Kazakhstan Energy Generation and Operation Company
kW Kilowatt
kWh kilowatt hour
KZT Kazakhstani Tenge
LCOE Levelised cost of energy
m/s metres per second
MW Megawatt
MWh Megawatt hour
NCF Net-Cash-Flows
NPV Net Present Value
O&M Operating and maintenance
PV Present Worth
UNDP United Nations Development Program
USD United States dollar
1
CHAPTER 1. INTRODUCTION
1.1 Purpose and vision of project For a last few decades, the high interest on renewable energy sources was shown by
companies and government. Consequently, it is important to analyse the perspective
construction sites. As a one kind of renewable energy sources, wind energy influences the
energy production industry. The aim of this paper is to analyse Ereymentau region,
Kazakhstan, and provide technical- economic justification for building wind power plant in
mentioned area. Other aspects considered include: environmental and social impacts, risk and
safety assessments. Results of individual aspect assessment will be analysed and used to
decide whether construction of wind farm is suggested or not.
1.2 Wind energy development trend in the world Wind energy is attractive renewable energy source that is under intense investigation
around the world. By definition, wind is a flow of air from high pressure area to low pressure.
In another words, wind flow is consequence of uneven sun energy distribution on plant’s
surface, which heats air up to different temperatures. Therefore, as far as earth will receive
sun radiation, wind will proceed blowing and wind energy will be used by humanity.
From ancient times, people were actively using the wind power. For instance, marine rs
using sails travelled long distances, farmers used wind mills to pump water or convert wind
energy into useful mechanical work. Modern world, moving towards sustainable and
renewable energy generation, utilizes wind resources to generate electricity since the first two
decades of XX and currently attempts to increase the green energy share in the overall energy
generation industry.
Ali Sayigh (2012) reports that wind energy, which generating 1 kilowatt of energy
replace use of 300-350 grams of coal in thermal power plants, is assumed to be the solution
for a greenhouse gas emission problem.
According to the world wind energy association (2014), the total wind energy capacity
has reached 336GW by the end of June 2014. Moreover, general trend shows that wind
capacity added energy year is becoming higher. For instance, the additional power generated
by introducing new wind farms in 2014 resulted in 17, 613MW more wind energy produced
and this number is substantially higher than in 2013 (13.9GW) and 2012 (16.4GW) (ibid).
Generally speaking, wind power generation constitutes the 4% of world’s electricity
consumption (ibid). The leading countries in wind energy utilization are China (98, 588
2
MW), USA (61, 946 MW), Germany (36, 488 MW), Spain (22, 970 MW), and India (21, 262
MW) (ibid). As a result, collectively these countries produce 72% of total wind energy
generated in the world (ibid). Apart from listed, around 80 countries are implementing wind
energy development programs and planning to construct wind farms that will generate
millions of MW energy. Moreover, those programs include development of wind machinery
industry, which illustrates long term perspectives and importance of field to future energy
system of country.
To conclude, wind energy is attractive due to the following factors:
Renewable energy source that doesn’t depend on fuel cost
Absence of negative emissions, e.g. greenhouse gasses, hazardous waste
Presence of developed wind energy generation technologies
Competitiveness of generated electricity cost, which has no dependence on
current fuel cost
Short construction period of wind farms and its flexibility in terms of local climate
and load characteristics
Opportunity to decentralize the energy generation system (Kaldellis, 2012).
1.3 Origin and main characteristics of wind Pressure differences, which are caused by temperature differences within the air layer,
centripetal and Coriolis forces induce winds- large-scale movements of air masses in the
atmosphere (Ali Sayigh, 2012). Due to the fact that pressure differences caused by
differential solar heating of the atmosphere, wind energy can be thought of as an indirect
form of solar energy.
In order to predict performance of a wind farm it is important to have data about wind
characteristics in selected site. According to WindFarm data, height, turbulence, roughness,
atmospheric stability, direction, topography and frequency distribution of speed are main
characteristics of wind speed (WindFarm software Tutorial). They will be briefly introduced
in this part of the report; detailed information for Ereymentau wind characteristics will be
given in part 3: Ereymentau’s wind potential assessment.
Height At heights lower than 100m, wind is strongly dependent on surface through
friction (roughness) which lows wind speed. Moreover, density and temperature of air
changes with height.
Two main equations (Bañuelos-Ruedas et al.,2011) describe wind shear:
3
Where, u1 is wind velocity at reference height h1, u2 is wind velocity at h2
is Hellmann exponent, depends on the nature of the surface
z0 is roughness length, depends on the nature of the surface
is wind speed at a reference height
Turbulence Rapid changes of wind speed and direction, which decreases power output and
create unwanted vibrations in the turbine
Roughness Surface frictional effect upon wind speed near surface (Equations 1.3.1, 1.3.2)
Table 1.3.1: Hellmann exponent and roughness length for different types of terrain
(WindFarm software Tutorial, 2015)
Atmospheric Stability
Parcel of air is displaced vertically and stable (highest speed) – tends to return to its original
position.
for h/L>0 neutral– stays at displaced location.
for h/L~0 unstable (lowest speed)– continue to move by reason of buoyancy forces.
for h/L<0 unstable conditions create greater
mixing of air and lower gradient of speed.
Equation 2 is modified to:
Where , L is Monin-Obukhov length from Table 2, h is height
under study.
4
Table 1.3.2 Variation of Monin-Obukhov length L
Atmospheric conditions L
Strongly convective days -10
Windy days with some solar heating -100
Windy days with little sunshine -150
No vertical turbulence 0
Purely mechanical turbulence infinity
Nights where temp stratification slightly
dampens mechanical turbulence generation
>0
Nights where temp stratification severely
suppresses mechanical turbulence generation
>>0
(Ali Sayigh, p 142)
Abovementioned equations will be used in Ereymentau’s wind potential assessment to
show the fact that even in best-scenario with stable conditions and higher speed at hub height
wind production is not paid back during life time of the wind farm.
Wind Direction- direction from which wind blows; it is measured from true north. Wind
rose will be used in the report to make micro site selection.
Topography- hills and hollows significantly affect wind shear. Ereymentau case will be
discussed in part 3.
Frequency distribution of speed Weibull distribution will be used to describe wind
regimes. Two main parameters of the distribution are scale factor “c” and shape factor “k”.
Detailed discussion is provided in part 3. Formula is given below:
1.4 Energy industry in Kazakhstan Republic of Kazakhstan is wealthy to natural resources that constitute 4% of total
global natural resource stock (KazEnergy, 2014). Following pie chart shows that most of
energy produced in Kazakhstan is from coal. Ministry of Energy of Republic of Kazakhstan
(2014) reports that most of the resource consumption is done by electricity and heat
generation industry and reaches 25 millions of tons in oil equivalent.
5
Figure 1.4.1 Energy resource use in Kazakhstan
Consequently, nearly 70% of electricity generated in Kazakhstan is produced out of coal,
14.6% of hydropower resources, 10.6% of natural gas, 4.9% of oil products, and less than 1%
of other energy sources (ibid). The total rated capacity of a ll power stations in Kazakhstan is
20, 844.2 MW (KEGOC, 2014). However, actual effective power is 16, 945.5MW (ibid). It’s
worth mentioning that most of the power plants have lifetime more than 25 years and require
capital reconstruction in order to satisfy future growth in energy consumption.
In general, the development of renewable energy sources in Kazakhstan depends on the
amount of coal and hydrocarbons. For instance, it’s been estimated that the amount of coal in
the region suffice to more than a century, whereas oil and gas resources will last for 40- 50
years (ibid). Another factor, influencing the rate of renewable energy resources mastering is
emissions affecting environment and being the reason for a global climate change issue.
Kazakhstan possesses vast areas of deserts and land that currently being used as
pastures or ores, but ready to be converted under renewable energy plants, such as solar-
wind farms. In case of presence of progressive technological and economical strategies of
renewable energy resources development, energy produced on these lands can be used to
decentralize energy system and satisfy local energy consumption. Kazenergy association
(2013) claims that potential of Kazakhstani renewable energy sources is:
Wind potential- 1820 MW*h/year
Solar energy- 1300- 1800 kW*h/m2/year
Hydropower- 170 MW*h/year
Geothermal energy- 520 MW.
6
Therefore, it’s easy notice that Kazakhstan has strong wind potential across the country,
which is shown in the Figure (Map of the Republic of Kazakhstan with distribution of wind
speed value at height of 80 m above ground level and a resolution of 9 km, can be found in
appendix).
Taking into account statements above, it can be concluded that for the country with
well wind energy development perspectives one of the main task is to detailed wind data
acquisition and analysis. This task is performed through use of meteorological mast that
usually collects wind data in 10- 50 m height during the long period of time. One of the
examples of such data collection is UNDP wind energy development program conducted in
Kazakhstan, to be precise, Ereymentau, Shelek, Zhongarian gates, port Shevchenko and
others regions. Thus, analyzing collected data it is possible to construct renewable energy
plants that will provide locals, which are usually live in the countryside and lack of constant
electricity supply, with green energy.
1.5 Promising wind farm constructions in Ereymentau region Currently, the Ereymetau region is becoming intensively involved in the wind farm
constructions and plans. Wind farm Project is located at south-east of Ereymentau town, 156
km north-east of Astana, in Akmola region. Coordinates of the town are
51° 37′ 0″ N, 73° 6′ 0″ E (Samruk-Green Energy, 2014). Following list shows the ongoing
projects:
Chevron Company is developing 30- 50MW wind farm plant project. The location of
project is planned to be to north- west of Ereymentau city. The estimated cost of
project- 30, 000 million tenge (162 million $) (Samruk- Green Energy, 2014). The
construction dates are unknown (ibid).
First wind power plant LLP company that is daughter company of Samruk Green
Energy LLP. Company is working on the 300 MW wind power station project. The
first stage that considers construction of 45MW wind farm has already started (ibid).
The location of the 45MW wind farm is 2.5 km away in south- west direction from
city. First stage is 17, 709 million tenge worth (95.7 million $) (ibid).
7
CHAPTER 2. SITE SELECTION
The site selection was the main issue during the project development. Several areas
located in different regions of Kazakhstan were considered:
- Port Shevchenko
- Dzhongar gates
- Ereymentau
In order to choose the most appropriate location, criteria had to be determined. Thus,
several factors were mentioned as area, landscape, wind capacity, demand of local population
and perspectives for the future development. The area is an important factor due to the lack of
installation experience in Kazakhstan. Thus, large area is required in order to have
opportunity for future expansion and stable wind energy development in region. Despite the
fact that Dzhongar gates have high wind velocity due to the concentrated wind flow, this
region was denied due to the presence of small area, which means that the project cannot
increase its capacity and no additional turbines can be installed. However, other two options
still appropriate for the wind farm.
The construction of wind farm in Port Shevchenko seems to be suitable for mentioned
criteria due to the presence of big area, which allow the expansion of the project, it has
appropriate landscape which means that the soil is appropriate to sustain the load of wind
towers and it has the opportunity to plug in central network. However, this location is not
desirable for investors as it is far from political and financial centers of the Republic.
Thus, it was decided to construct the project in Ereymentau, which has good capacity
for the project expansion and appropriate value of wind velocity. Moreover, this location is
attractive for investors as it can be demonstrated in EXPO 2017 exhibition. The main theme
of exhibition is “Future Energy”, which will be based on current innovations in this field.
8
CHAPTER 3. SITE ANALYSIS
3.1 Ereymentau’s wind potential assessment A. Wind Monitoring Equipment
Main source of wind data in Kazakhstan is information collected during the project between
the Government of the Republic of Kazakhstan and UNDP/GEF “Kazakhstan — Wind Power
Market Development Initiative”. According to this project 50 meter meteorological mast was
constructed near Ereymentau. Wind data was collected during 2006-2007 period with
availability 75.3%. Incorrect data (due to icing of sensors) was not used (Ermentau Wind
Farm, 2008). Wind data collected will be given in part 3.1 C of the report. During the report
higher data (speed, Hellman exponent) will be considered (best scenario) in order to show
that even in this case project need to be supported by the government of Kazakhstan in order
to improve wind energy development in the region.
B. Long-term Correlation
Due to the fact that amount of wind speed data is limited (for 1 year) Measure-
Correlate-Predict method is used to predict long-term speed at the site. UNDP Project used
long-term wind speed data from National Center for Atmospheric Research for place near the
wind farm site. Thus, it was calculated that long-term speed in the site for 50 m is 7.79 ms-1.
As a result, measured data during 2006-2007 period (7.89 ms-1) and long-term speed (7.79
ms-1) for 50 m are similar. Therefore, probability of wind speed volatility (decrease) in long-
term is very low.
C. Collected Information
UNDP collected data is given below in Table 3.1.
Table 3.1.1: Wind data
Wind statistics Level
1
Level
2
Level
3
Height 50.9 49.0 26.5
Minimal wind speed (ms-1) 0.0 0.0 0.0
Average wind speed (ms-1) 7.89 7.83 7.34
Maximal wind speed (ms-1) 29.8 29.9 27.3
Gust speed (ms-1)
IEC (15 ms-1) turbulence intensity
37
7.7%
38
7.6%
35
9.0%
(Wind station near Ereymentau, p 6)
9
It was calculated by UNDP that Weibull scale factor is equal to 8.82 ms-1 and shape
factor is 1.86. Measured air density is equal to 1.197 kgm-3, measured roughness length is
z0=0.03m (Wind station near Ereymentau, p 9). In addition, according to meteomast data
wind rose was created. It is shown in Figure 3.1.1.
According UNDP, territory in the wind farm site is an open area with rolling hills
covered with short grass. Therefore, according Table 1: Hellmann exponent and roughness
length for different types of terrain, it can be classified as featureless land, smooth bare soil,
mown grass or level country with low vegetation, heather, moor and tundra. As a result,
roughness length and Hellman exponent values can be found in Table 3.1.1.
Figure 3.1.1: Wind and energy roses for the site
(ibid, p 6)
Figure 3.1.2: Seasonal pattern of wind speed
(ibid, p 8)
D. Wind Data Analysis
All UNDP Data is measured in 50 m height. Thus, it is needed to correlate all values
with wind turbine hub height. 80 m height was chosen due to the fact that most of 2-3 MW
10
turbines have approximately this height. The main parameters for correlation are roughness
length z0 and Hellman exponent α.
It was found by UNDP that z0=0.03. It is possible to find α from equation 3.1.1 (Ali
Sayigh, 2012, p 78). Thus, α=0.1001
α value can be checked by Equation 11. Where u1= 7.89ms-1, u2=7.34ms-1, h1= 50.9m and
h2=26.5m. Thus, α=0.1107. Value is similar to previous and related to same type of terrain
mentioned in Table 3.1.2. Higher value of α will be used as best scenario case.
Height
Equation 3.1.1 is used to calculate speed at 80 m height, u2=8.295 ms-1
Turbulence
According to Table 3.1.1, turbulence intensity (15 ms-1) is 7.7% at 50 m height. This value is
not high and does not affect wind farm significantly.
Atmospheric Stability
Stability is related to speed of wind through Equation 3.1.2. Thus, different speeds can be
found for different atmospheric conditions.
According to formula, speed at stable conditions with z0 is 9.3509 ms-1, neutral is 8.295 ms-1
and for unstable is 8.2195 ms-1. Again, best scenario can be considered in the report to prove
the need of support from the government.
Wind Direction
As can be seen in Figure 3.1.1, prevailed wind direction is from South-West.
Therefore, it is necessary to construct wind farm on SW site of the Ereymentau in order to
have the highest possible winds.
Topography
As mentioned above, territory is rolling hills covered with short grass which have
highest efficiency for wind farm site (Ali Sayigh, 2012).
Frequency distribution of wind
UNDP shape and scale factors are given for 50m height. Thus, equations 3.1.2 and
3.1.3 (Ali Sayigh, p 144) are used.
11
For 80 m k=1.95059 and c=9.2727 ms-1
3.2 Electricity consumption and load in Akmola region According to the annual electricity consumption report provided by KEGOC
(Kazakhstan Electricity Grid Operation Company) in 2013, the electricity consumption and
electrical load in Akmola oblast is as in the table below.
Table 3.2.1 Electricity consumption and electrical load in numbers for Akmola region in 2010
Parameter Quantity
Electricity consumption, kW*h 7.5 millions
Maximum electrical load(including Unified
Energy system of Kazakhstan), MW
1313
Nominal power plant output, MW 562
Effective power plant output, MW 517
Electricity produced , kW*h 3.1 millions
Also, following table illustrates electric energy consumption and generation (in the past,
current, and prediction for future years) for a period of 2012- 2021 years. Additionally,
difference of these two will result in energy deficiency. Lack of energy is compensated on
account of extra energy generated in other regions through Unified Energy System of
Kazakhstan. The main reasons for restrictions on energy generation increase include
unsatisfactory technical condition of turbo generators, deficiency of boiler capacity, and
issues with insulation. Prediction analysis has been done according to the general economic
development trends, taking into account future population expansion, industrial constructions,
technical condition of energy generation facilities, and energy saving technologies.
Table 3.2.2 Electric energy consumption and generation for a period of 2012- 2021
Parameter,
billion kW*h
Fact Prediction
2012 2013 2014 2015 2016 2017 2018 2019 2020 2021
1. Consumption 7.5 7.5 7.7 7.8 7.9 8.1 8.2 8.3 8.6 8.8
2. Generation 3.1 3.1 3.0 3.2 4.8 4.6 4.8 4.8 4.6 4.6
Existing 3.1 3.1 3.0 3.0 3.1 3.1 3.1 3.1 2.9 2.9
TPP1-1
Astana-Energy
LLP
0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1
12
TTP-2 Astana-
Energy LLP
2.3 2.3 2.3 2.1 2.3 2.3 2.3 2.3 2.1 2.1
TPP Jet-7 LLP 0.7 0.7 0.6 0.8 0.7 0.7 0.7 0.7 0.7 0.7
Planning 0 0 0 0.2 1.7 1.5 1.7 1.7 1.7 1.7
New
constructions
0 0 0 0.2 0.3 0.3 0.3 0.3 0.3 0.3
45MW WPP2
Ereymentau
city
0 0 0 0.2 0.3 0.3 0.3 0.3 0.3 0.3
WPP near
Ereymentau
0 0 0 0 0.1 0.1 0.1 0.1 0.1 0.1
Expansion of
existing PPs
0 0 0 0 1.4 1.2 1.4 1.4 1.4 1.4
TTP-2 Astana-
Energy LLP
0 0 0 0 1.4 1.2 1.4 1.4 1.4 1.4
3. Deficiency 4.4 4.4 4.7 4.6 3.1 3.5 3.4 3.5 4.0 4.2
1TPP- thermal power plant
2WPP- wind power plant (KEGOC, 2013).
Analyzing data above, it’s easy to come into conclusion that the electric energy consumption
and generation in the Akmola oblast increases by around 1.3% and 4% respectively. This
trend might be due to the rise in local population and construction of new buildings, factories,
and industry.
Moreover, table provides information about existing power plants: TPP1 Astana-
energy LPP, TPP-2 Astana- energy LPP, and TPP Jet-7 LPP. 74.2% of all electric energy
produced is belongs to TPP-2 share (KEGOC, 2014). Also, influence of future construction
as wind farms and extension of existing ones is can be found. To be precise, 45MW
Ereymentau wind power plant produces 0.2 billion kW*h energy and starting from next year
additional wind plant begins operation (ibid).
As reported by Kazakhstan Electricity Grid Operation Company in 2013, the e lectric
energy consumption by industry is given below.
13
Figure 3.2.1 Electric energy consumption by industry in Akmola region in 2010
Generally speaking, 30% of energy was consumed by municipal buildings and little less
(27%) by industry (ibid).
3.3 Climate of the region The main characteristics of climate were measured by UNDP and mentioned before.
However, it should be mentioned that Baltabayeva and Bogolyubova (2012) states that
Ereymentau and wind farm site are located in intermountain basin and accumulate cold air
during winter. As a result, temperature in Ereymentau is colder than average temperature in
Akmola region. This cause higher air density and higher power production at winter.
3.4 Wind energy development Law Regulations After gaining independence Kazakhstan has started to pay attention to wind industry.
In 1995 Kazakhstan had committed United Nations Framework Convention on Climate
Change (Government Regulation of Republic of Kazakhstan, 2003). According to National
Program of wind energy development in Republic of Kazakhstan in 2007-2015 with
perspective to 2024 year (Ministry of Energy and Mineral Resources of Republic of
Kazakhstan, 2007), the main aim for wind industry is production of 900 million KW/hour of
electricity in 2015 year and 5 billion KW/hour in 2024 year. Moreover, Law of the Republic
of Kazakhstan “About support of use of renewable sources of energy” (2003) and “Rules of
definition of the nearest point of connection to the grid or thermal networks and connections
of the objects on use of renewable” (2009) declare support and regulations for wind energy
sector from the government.
In general, Kazakhstan government has developed many wind energy related laws in
2000-2015 period which solve legislation problems and improve wind energy development in
the region (The Kazakhstan Electricity Association Committee on Renewable Energy
Sources, 2015).
14
CHAPTER 4. TURBINE CHOOSE
4.1Wind turbine technologies and properties Wind turbine is machine that converts kinetic energy of wind into electrical energy. As
it’s been mentioned previously, ancestor of wind turbines is wind mills. However,
technological progress changes wind mills in many ways and currently two types of wind
turbines differentiated: horizontal and vertical axis. Wind turbine that has vertical axis of
rotation is said to be vertical- axis wind turbine (VAWT), and machine with horizontal axis
of rotation is horizontal- axis wind turbine (HAWT). Last one is used from ancient times and
implemented more often. Table below demonstrates characteristics of two types of machinery
(Kaldellis, 2014).
Table 4.1.1 Comparison between HAWT and VAWT
HAWT VAWT
Axis of rotation Horizontal Vertical
Pointing direction Into the wind (sensors are
used)
Any
Efficiency High Lower
Ripple torque Low High
Integration into a building No Yes
Accessibility to maintenance Medium High
Although, vertical axis turbines have several advantages that include better reliability due to
the less components involved, convenience during installation, universal wind capture
direction, less maintenance; there are also major drawbacks behind. For instance, efficiency,
which is one of the most important parameter, problems in design: low ability to handle
stress. Therefore, horizontal axis wind turbines are further considered as a power generation
machine appropriate in wind farm design.
4.2 Defining criteria for wind turbine choose However, there are even more turbine selection criteria that should be considered.
Following list most important ones:
Presence of pitch control mechanism
Presence of variable speed mode
Implementation of direct drive technology
Presence of 3 blades
15
Satisfactory cost/quality relation.
Pitch control- power control technology that implemented by means of adjusting the angle of
attack of individual blade, thereby controlling driving lift force (ibid).
The advantage of variable speed mode over fixed is in the better power capture, which is
achieved by designing the turbine so that it have peak performance at a wide range of wind
speeds (ibid).
Direct drive technology is replacement to most failure- prone component of wind turbine-
gearboxes (ibid).
4.3 Wind turbine power curve, comparing alternatives over Weibull- power curve graphs. Graph below illustrates the power curves for all turbines considered. General Electric,
Siemens and Vestas wind turbine manufacturers were considered, as they are major
companies in the world. In total, 5 turbines satisfied criteria stated above and preceded to the
power output calculation stage.
Figure 4.3.1 Power curves for alternative considered.
According to turbine manufacturers, the highest rated power among alternatives belongs to
Siemense SWT- 107 turbine and constitutes 3.6MW (Siemens, 2011). In a range of 1- 1.5
MW turbines, the General Electrics 1.5xle turbine was chosen as it satisfied turbine choose
criteria stated above. As a result, following graph was obtained (General Electric, 2009).
16
Figure 4.3.2 Comparison of annual electric energy production by alternatives.
The calculations were performed based on the wind turbine power curve and the wind
velocity Weibull probability density distribution. According to method used, specific wind
speed corresponds to one Weibull probability density value and power output value. Weib ull
probability density value illustrates how long specific wind blows per year. The wind
turbine’s power curve implies a specific power output during these hours. The product of
total hours per year to power output results in total annual electricity production by each
turbine. Therefore, figure N shows the annual energy generation by turbines relative to each
other. The highest energy generation belongs to Siemens SWT- 107 3.6MW turbines,
whereas others nearly the same, except GE turbine. Calculation included in appendix.
Table 4.3.1. Results of capacity factor calculations for individual turbine
Turbine GE 1.5xle Siemens SWT-
108
Siemens SWT-
107
Vestas V117 Vestas V126
Capacity factor,
%
56 60.9 42.4 41.5 41.2
Analyzing annual energy output, it is possible to obtain important parameter- capacity
factor. Capacity factor represents ratio of effective annual energy produced by turbine to
energy produced at rated power output during the same period of time. Capacity factor of
Siemens SWT- 108 is the highest among others and constitutes 60.9%. However, during the
calculations different losses that occur during the operation are not included.
17
To sum up, even if Siemens SWT- 107 turbine gives the highest annual energy generation, its
capacity factor is lowest, which mean turbine is not used efficiently. However, turbine SWT-
108 2.5MW from the same manufacturer shows relatively high output and has the highest
capacity factor value (60.9%). Therefore, team decided to use Siemens SWT- 108 wind
turbine and further in the design this turbine is used.
Table 4.3.2 Wind farm energy output data
Parameters Per turbine Wind farm
Number of turb ines 1 22
Rated power, MW 2.3 50
Annual rated energy generate,
MW*h
20,148 443,256
Annual effective energy
generation,
MW*h
12,285.69 270,285. 33
Table above suggests that total number of Siemens SWT-108 used in the design is 22, so that
rated power of plant will constitute 50MW and effective energy generation per year is 270
GW*h.
Another important output characteristic of wind power plant is seasonal dependence.
This happens due to the seasonal fluctuations of wind speed mentioned in Chapter 3. Figure
4.3.3 illustrates numerical difference between winter and summer seasons in terms of power
output by wind farm. It is obvious that Ereymentau wind farm will generate far more energy
during winter. Generally speaking, seasonal dependence of power generation has both
positive and negative effect on plant’s energy production.
Figure 4.3.3 Comparison of power output for summer and winter seasons
18
4.4 Power losses It was calculated that power output of SWT-108 turbine is 12.3 GWh per year through
use of Weibull distribution, power curve and Excel software. It is know that total nominal
energy output per year is 20.2 GWh. Thus, capacity factor is equal to 0.610=cf.
However, different losses should be added to calculate real power output of the farm.
1) Cut- in and cut-out losses
These losses occur due to the fact that SWT-108 produce power when speed is more than
3 ms-1 and less than 25 ms-1 (to prevent mechanical damage). These losses are included in
initial calculation (cf)
2) Wake effect losses
Wake losses are calculated in Chapter 5 of the report and equal to 10 percent (with
distance between turbines equal to 7D in wind direction). Thus, new capacity factor is
0.9*cf
3) Electromechanical and transformer losses
According to Ali Sayigh (2012), electromechanical losses are usually equal to 3-10%.
However, it is possible to state that electromechanical losses are taken into account in power
curve calculation. Nevertheless, wind farm transformer losses (5-10%) can be added to
these losses. As a result, new capacity factor is equal to 0.9*0.9*cf
4) Technical availability
Ali Sayigh (ibid) states that technical availability of a wind park varies from 95-98%.
Therefore, technical availability is taken as 95% due to the fact that after 10 years of wind
farm operation technical availability decreases. New capacity factor is 0.9*0.9*0.95*cf
5) Hysteresis losses
As mentioned before, wind farm stops operation when speed is lower than 3 ms-1 and higher
than 25 ms-1. When wind speed is decreased from cut-out region to normal conditions, the
wind turbine does not continue work immediately. Some time is necessary to start operation
again. Thus, hysteresis loss is occurred. Approximate hysteresis losses are 4-5 percents (ibid).
Thus, new capacity factor is 0.96*0.9*0.9*0.95*cf
6) Electricity transmission losses
Internal electricity load has loss of energy due to transmission from turbines to transformer
station. Approximate value was chosen 97% (ibid). New capacity factor is 0.97*
0.96*0.9*0.9*0.95*cf
7) Network rejection losses
19
Some restrictions introduced in the regional electrical grid system’s operation by KEGOC
(Kazakhstan Electricity Grid Operation Company) can affect wind farm operation. Thus,
losses are approximated as 98 percent. Final capacity factor of the wind farm is 0.98*0.97*
0.96*0.9*0.9*0.95*cf. By substituting corresponding values we obtain final capacity factor, cf
= 0.428=42.8%
Taking into account above statements, following can be produced:
Table 4.3.3 Final wind plant output parameters
Parameter Numeric value
Capacitor factor, cf, % 42.8
Annual effective energy generation,
MW*h
190 GWh
20
CHAPTER 5. PROJECT DETAILS
In this part of the report number and position of wind turbines will be defined. Noise,
shadow and aesthetical aspects will be considered. In addition, other different aspects related
to micro-siting will be discussed.
5.1 State authorities’ approval According to Samruk-Green Energy (2014), approval for 20 Wind turbine generators
of 2.5 MW capacity each (Fuhrlaender FL 2500) was given. However, capacity of the wind
turbines is 2.3 MW for this project. Thus, it is needed to increase number of turbines to 22
turbines. Differences between turbine model and number in abovementioned report and this
project is not crucial due to the fact that according to a technical diligence performed in the
“Supplementary environmental and social impact assessment informat ion addendum to
Project Pre-IEA Report” alternative wind turbines can be used to improve efficiency (ibid).
5.2 Project Location Details Location is placed on south-east and its total area is 2.242 ha. The main advantages of
location are availability of public roads, near railway, grid 35, 110 and 220kV. Location of
wind turbines and roads in abovementioned report is shown in Figure 5.3.1.
Figure 5.3.1: Site layout map by Samruk-Green Energy (ibid, p 10)
21
5.3 Internal roads and electrical grid Internal roads should have adjacent trenches for storm water drainage. Moreover, according
to “Technical and commercial aspects in wind project development” (p18, 2014), minimal width of
roads, turning radius, ride height should be declared by wind turbine manufacturer.
Internal electrical grid will be underground cables within radial display to connect wind
turbines. This is common practice in wind industry (Samruk-Green Energy, 2014).
5.4 Noise, shadow and aesthetic aspects Parameters which affect population of Ereymentau are important for this project. The nearest
residence to a wind farm is located within a distance of 700m (ibid). Thus, abovementioned effect
can be calculated.
Ali Sayigh (2012) states that distance for acceptable noise level is equal to 4 t imes the total
height (hub height+0.5 rotor diameter). Therefore, acceptable distance is 532 m, which has not
negative effect to local residents.
Danish Wind Industry software is used for turbine proposed in this project in order to measure
shadow effect. Moreover, it is important to notice the fact that residents are placed only in North,
North-East direction from wind turbines. Whereas maximum shadow effect distance from Figure
5.5.2 in this direction is 360m, while closest resident is at distance 700m. Therefore, shadow effect
does not influence local residents. In addition to abovementioned calculations it is worth to
mentioned noise modeling which was done by Samruk-Green Energy (2014). In this modeling
worst-scenario was considered and it was concluded that there is no noise disturbance for local
residents.
Aesthetic aspect is not very important for this project due to the fact that wind farm is placed at
distance from the town. Nevertheless, Ali Sayigh (2012) states that three-bladed wind turbine has
higher aesthetic value than other types of turbine.
22
Figure 5.5.2: shadow plot
5.5 Wake effect Wake effect significantly decreases wind speed and affects to power output of turbine.
The main equation for wake speed is given below
Where v is wind speed x meters behind the motor, u is initial speed, R is radius of rotor
and α is wake decay constant and equal to 0.075 m. Moreover, normal power loss due to
wake is approximately 10 percent (ibid). Speed-power relation is cubic relation. Thus, if
normal power loss is 10% then wake speed- initial speed ratio is
Therefore, X distance can be found from equation X as
X distance equal to 2444.5 meters. With this distance between two turbines in wind
direction loss of power available in wind will be 10 percent. However, according to
23
calculation and comparison of energy available in wind and energy produced by power
available in wind is equal to 5.952*Betz limit MW=3.51MW; while turbine can produce only
2.3 MW. Thus, 2444.5 meters between turbines is very high and inefficient value.
As a result, for this project common thumb rule (7 D in wind direction, 5 D
perpendicular in direction) can be used. Distance of seven turbine diameters is equal to 756
m. With u=7.89 ms-1 ratio between velocities after X meters and initial velocity will be
0.841364 from Equation 5.6.1. From cubic power-speed relation power ratio will be
0.595596. Thus, possible power output in 7 D distance will be
5.952MW*0.59=2.0905 MW
And park efficiency will be equal to
As a result wake losses of the project are equal to 10 % of power production. According
to Ali Sayigh (2012, p 402) 10% is optimal wake loss for wind park design.
5.6 Electrical characteristics of wind farm Connection of the wind farm to existing national grid depends on total power output. In
considered case it is 50MW, thus 220kV high voltage transmission line was chosen. There is
a reason to eliminate connection to existing 35kV, 110kV transmission lines. According to
technical specification of electrical substation, 110/35 kV Ereymentau substation’s maximum
transformer power output possible to transmit into the grid 30MW and 18MW respectively
(Yakovenko, 2014). These amounts are insufficient to transmit 50MW of wind farm power.
Thus, additional reconstruction is required, which results in extra expenditures. Therefore,
it’s suggested to connect wind farm to 220kV transmission lines.
Wind farm substation will consist of 220kV switchgear with power transformer
(35/220kV, 63kVA) installed (ibid). Also, 4 km transmission line construction is required
that will connect switchgear to Erkinshilik- Ereymentau transmission line with use of AC-300
high voltage cable (ibid).
24
Figure 5.7.1 Schematic diagram of wind farm connection to national grid.
5.7 Power balance Table 5.8.1 illustrates power balance conducted for Akmola region that considers
period between 2017 to 2021. The objective of table is to show the influence of wind farm in
case of project will be implemented. It is observable that electric load in the region will
increase, as so energy deficiency does. Therefore, this power will be compensated from
Unified energy system of Kazakhstan.
Table 5.8.1 Power balance for Akmola oblast
Parameter
2017 2019 2021
1. Consumption
Max electrical load, MW 1485 1575 1680
2. Power generated
Rated, MW 897 897 897
Effective, MW 839 839 839
Construction of new capacities
45MW Wind power plant 45 45 45
50MW wind power plant 50 50 50
Reconstruction of existing
plants, MW
244
244
244
3. Introduction of wind farm considered in this paper
Rated power, MW 50
50
50
Power deficiency, MW
257
347
502
25
Share of wind energy in total
regional electricity
generation, %
8.3
5.8 Foundation The main objective of wind turbines is to produce green energy. Thus, electrical
engineers deal with problems that are related to the production of energy, while the
construction of the whole plant is the responsibility of civil engineers. Due to the reason that
wind energy turbines are located on places, which are characterized by high wind speed, it is
necessary to keep the whole structure stable under high wind load. Therefore, the main
objective of civil engineers is to provide stable foundation for such construction. There are
several types of foundations:
Spread foundation
Shallow foundation
Pile foundation
The Terzaghi equation is the main equation for foundation design in geotechnical
engineering which is shown in equation 5.9.1. The bearing design is one of the main steps in
foundation design, which allow sustaining the required load.
Qu = c Nc + qDNq + 0.5 γ B Nγ
Table 5.9.1. Main parameters for Terzaghi equation
Term Description
C cohesion of soil (has to be determined experimentally from the site)
Nc cohesion bearing capacity factor
Nq load bearing capacity factor
Ny unit weight bearing capacity factor
Q load
D depth of foundation
Γ Unit weight of soil
B width of foundation
This formula is not sufficient to consider aggregate exposure to the structure. Thus it was
suggested to use general equation, which is similar to Terzaghi equation.
Qu = c NcFcsFcdFci + qDNqFqsFqdFqi + 0.5 γ B NγFγsFγdFγi
26
Second formula introduces next parameters:
Table 5.9.2. Additional parameters for General equation
Factor Parameter Description
Shape Fcs cohesion shape factor
Fqs load shape factor
F γs unit weight shape factor
Depth F cd cohesion depth factor
F qd load depth factor
F γd unit weight depth factor
Inclination F ci cohesion inclination factor
F qi load inclination factor
F γ i unit weight inclination factor
Table 5.9.3. Obtained values for Terzaghi equation
C(kN/m2) Nc Nq Ny phi Fcs Fqs Fys Fqd Fcd
20 20.72 10.66 10.88 25 1.514 1.466 0.6 1+0.466/B 1+0.514/B
Fyd Fyi Fci Fqi Q FS d
1 1 1 1 4000 4 2
By substituting values from table 5.9.3 to equation 2 it is possible to find the value
for dimensions of foundation. As a result, from table 1 and equation 2 B=L=3,5. Table 5.9.3
represents the values which were used during the calculation. The average for medium stiff
clays is about 20-40 kN/m2. Thus, in order to provide most safe design the minimum value
for cohesion was taken into account. Moreover, the maximum value for safety factor for
foundation design is 4, which was used in calculations in order to provide save structure. This
means that when the required load is 4000kN, the foundation was designed for 16000 kN in
order to sustain all possible loads as wind, transport and the structure load. Moreover, the
friction angle was also chosen as 250 in order to ensure the stability. The next parameter
which was taken into account was unit weight of soil. Due to the fact that water table located
at the depth of 10 m below the ground, the dry unit weight was used for the construction.
Moreover, this value was taken by considering safety issues. However, all these safety issues
influenced the cost for foundation, so it could be said that it is better to make some
27
investigation in the field to obtain actual values for required parameters which can minimize
the cost of project. The foundation is shown on figure 5.9.1.
Figure 5.9.1. The foundation
Due to the reason that the construction of foundations depends on the ground and the
load, so types of piles would be defined. Actually, there are two types of piling: friction piles
and cohesion piles. Due to the presence of strong clay in the field, cohesion piles will be used
with a length less than 10 m. These piles are driven piles, which will be penetrated into the
soil layers by hydraulic machine, which use heavy hummers and penetrate piles in specific
frequency. Therefore, piles can be penetrated without any break along the length. Moreover,
it is necessary to use well covered piles to avoid corrosion. Due to the fact that the ground
water level is located at depth of 10m, 6 m and 8 m length piles could be sufficient in order to
support the load. Pile types are made of wood, concrete and steel. Reinforced concrete piles
will be used due to its advantages as durability and strength.
28
CHAPTER 6. ECONOMY
6.1 Cost Estimation Wind energy has no fuel costs related with the electricity generation process.
Therefore, all costs are associated with initial investments. Initial investments consist of the
connection to the grid, construction of a foundation, purchase and installation of turbines,
land rent (if it is a commercial, non-governmental project), electric installations, consultancy,
financial cost, road construction(in places where there is no road near the construction site)
and control systems (International Renewable Energy Agency, 2015). More detailed cost
constituents are listed below:
Total costs of initial investment consist of (The European Wind Energy Association, 2009):
Turbine Cost – 75.6% (of the total capital costs)
Grid Connection – 8.9%
Foundation – 6.5%
Land Rent – 3.9%
Electric Installation – 1.5%
Consultancy – 1.2%
Financial Costs – 1.2%
Road Construction – 0.9%
Control Systems – 0.3%
Operations and maintenance costs are associated with the cost elements that emerge after the
start of wind farm operation (Windustry, 2015). Some are fixed and some may alter with the
capacity of the farm. They consist of raw materials, operation personnel, tax payments and
insurance, land lease, access fee (cost of the access to connect to the grid), preventive
maintenance (system check-ups), and repair works.
There are also some financial costs associated with the project, depending on the type of
project investment. In this project, interest rate of bank loan was taken as 3% per annum,
which is an average interest rate for funding wind energy projects in Europe according to
Yoursri.com, 2013.
Three main elements drive the cost of electricity in wind energy according to Awea.org:
capital costs, capacity factor and operation costs. Figure 6.1.1 describes the global trends in
wind energy prices, which are constantly falling from the beginning of 1980s.
29
Figure 6.1.1. Declining Cost of Wind Energy Over Time (Awea.org)
In order to access the cost of the electricity of the wind project, we should find LCOE
(levelized cost of energy). LCOE is a main source of metrics for cost of the electricity
produced by the generator, in this case wind generators (Renewable Energy Advisors, 2011).
Levelised cost of electricity generation (LCOE) is the electricity price required for
project revenues to be equal to costs (International Renewable Energy Agency, 2012).
Therefore, the price for electricity greater than LCOE, will result in the greater return of
investments.
;
Figure 6.1.1 shows that cost of wind energy is declining each year, and at year 2013, its
average value reached $0.05/kW of installed turbine power. This means that wind energy has
become more accessible and profitable.
Modern wind turbines are supposed to operate for 120,000 hours over 20 years, which is
68% of time operating and the rest staying still (Windmeasurementinternational.com, 2015).
Maintenance cost increases as turbines ages. It also varies with the number of generation of
the turbines, where newer generations have lower maintenance costs. Modern turbines
maintenance cost ranges from 1% to 5% of the initial cost of the turbine per year, depending
30
on the operation time, the older the wind farm, more operation works are necessary. Moving
turbine parts will have more frequent breakages rather than static parts. The fastest wearing
out parts are the gearbox and the rotor blades. Total O&M cost have been calculated by
UNDP in 2008 year as 1.665 KZT/kW*h, with the inflation rate taken into account in Figure
6.1.2, it becomes 2.63 KZT/kW*h ($0.0142) in year 2015 (Government of Kazakhstan and
UNDP Kazakhstan, 2015). However, in order to give more accurate cost estimations another
method was used. According to this method, average annual O&M costs are (Ali Sayigh,
2012):
1% of CC at years 1-2
1.9% of CC at years 3-5
2.2% of CC at years 6-10
3.5% of CC at years 11-15
4.5% of CC at years 16-20
Figure 6.1.2, shows that according to the trend of inflation rate from 2009 to 2015,
average inflation rate is 6.75% which is the average of the highest rate and lowest inflation
rates in that period.
Figure 6.1.2. Kazakhstan inflation rate, 2009-2015 (Tradingeconomics.com)
Capital cost for the project was taken as an average cost for European project in 2006
(The European Wind Energy Association, 2009). These prices are given in euros. They were
converted to USD using data for USD/EUR rates in 2006 (X-rates.com, 2015). Then, Future
worth of these numbers was obtained for year 2015 using the formula:
where PV – present worth, FV – future worth, i –price indexation (6.75%), n – time from
year 2006 to year 2015. Therefore, value of $140 368 506 was obtained as a capital
investments of the whole project. Using actual power 1.395675 MW, total power output of
the plant was calculated as 242.242 GW*h. Using online calculator at Figure 6.1.3 (Nrel.gov,
31
2015) (see Appendix), LCOE was calculated as $0.083/kW*h (15.355KZT/kW*h). This
number is much smaller than the price for wind energy set by KEGOC in 2014, which is
$0.130/kW*h (24.211 KZT/kW*h) (Rfc.kegoc.kz, 2014).
6.2. Financial Costs. IRR. Payback Period There are two scenarios applied to this project in order to show the alternative way of
developing of project. First scenario in Figure 6.5(see Appendix), applies a feed- in-tariff,
which was implemented by the government in year 2014, and according to this incentives,
cost for wind energy is $0.130/kWh, which is quite high. Second scenario in Figure 6.2.3(see
Appendix), was done without governmental incentives, and the average price for electricity in
Astana region, $0.0746 was taken.
In scenario 1, (Table 6.2.1(see Appendix)) Project is to be funded by taking a bank
loan for 20 years with an interest rate of 3%. Each year, $7 228 978 will be paid to bank,
which 5.15% of overall money that should be paid to bank. Project can be profitable in this
case, because of the feed-in-tariff, which allow to sell electricity to KEGOC at a level higher
than LCOE. Payback period is calculated as 9-10 years, after that project will give profits to
investors. Internal Rate of Return (IRR) in this scenario is 8%. IRR can be calculated by the
formula below:
Cash- in-flow were estimated to be $24 827 815, which is high enough to pay off bank
loan and O&M costs. Positive balance is achieved at the year 14, and keeping this tendency at
the end of year 20 net revenue of $129 211 913 was obtained.
Scenario 2 (Figure 6.2.2(see Appendix)) has a bank loan for 20 year with an interest
rate of 3%. Figure 6.2.2 shows that project will not be efficient. Net Cash Flows in each year
is negative, giving no profit to investors at all. IRR is zero, because NPV is negative.
Figure 6.7 (see Appendix) shows how the total revenue increases each year. There is a
steady grow in scenario 1, and a long term debt left in scenario 2. Figure 6.8 (see Appendix)
shows how O&M costs changes over time. A gradual increase can be noticed in this graph.
Figure 6.9 (see Appendix) represents all cash flows in scenario 1 over 20 years.
32
CHAPTER 7: PROFESSIONAL ETHICS. COMMUNITY
HEALTH&SAFETY
7.1 Professional ethics Professional ethics are professionally accepted standards of personal and business
behavior, values and guiding principles. Codes of professional ethics are often established by
professional organizations to help guide members in performing their job functions according
to sound and consistent ethical principles.
The construction of a wind farm, as nearly all engineering-related endeavors, raises
the question of several ethical concerns, each of which should be addressed objectively and
appropriately as required by the codes of ethics an engineer is bound by.
Wind turbines can pose a certain threat level to bird life because of mid-air collisions with
large rotating blades of a turbine, or even a tower and non-rotating blades. Therefore, as
engineers, bounded by ethical standards, we should address a concern of danger to wildlife.
One of the solutions of this problem is constructing the wind farm outside of known
migratory patterns to minimize the chance of collisions. Another solution could be shutting
down of the wind turbines during peak times of migration.
Also, an engineer should consider environmental impact and sustainable development.
Environmentally conscious engineers should recognize that the process of producing
alternative energy at the cost of a direct and negative effect on a region’s ecosystem does not
reflect the moral standards expected of an engineer.
Wind turbines, while considered renewable and clean sources of energy, can pose some
health threats to humans that should be addressed. Large wind turbines can produce
infrasound that can cause significant sound-related hearing loss as well as more immediate
health problems. One such possible risk, usually considered minor as the symptoms include
mainly headaches or high stress levels, is caused by the interference between audible noises
and infrasound, resulting in a slightly pulsating frequency known as a beat.
Human health and safety must be a first priority for engineers regardless of field. In
terms of the wind farm, an ethically appropriate response would include addressing of
potential health risks to humans as well as research aimed at reducing the generation of
dangerous infrasound.
The wellbeing of both life and property should be addressed to inform the public of all
possible dangers, regardless of how likely or serious they may be. Doing so, which may at
first stir opposition, would maintain the integrity of the engineering profession.
33
7.2 Community health & Safety
7.2.1 Ice throw Wind turbines operating during cold weather may have the risk of throw and shedding of
ice formed on the blades. Accumulated icing can be shed from the turbine due to both the
mechanical forces of the rotating blades and gravity. A change in conditions, such as increase
in ambient temperature, wind, or solar radiation can result in falling of sheets or fragments of
ice, making the area near the turbine subject to a great risk. Furthermore, rotating blades of a
turbine can throw ice fragments some distance from a turbine, up to several hundred meters
under right conditions. It may cause injuries to people and damage to structures and vehicles;
therefore, some prevention measures should be made to avoid the risk.
To mitigate the risk several actions should be considered:
Turbine siting.
Wind Energy Production in Cold Climate gives the following formula for calculating a safe
distance from the turbine:
1.5 * (hub height + rotor diameter)
The residential houses and other buildings in Yerementau are situated at a distance far from
the wind farm, where ice throw is not considered.
Also, area of the wind farm will be used only for grazing, which is not possible during cold
weather; therefore, public traffic during winter will be minimized and as a result the risk
associated with ice throw.
Turbine deactivation.
If ice accumulation is detected, the turbine is remotely switched off. In addition, some
scenarios can cause an automatic shutdown of the turbine:
Detection of ice by an ice sensor placed in nacelle of the turbine
Detection of rotor imbalance by a shaft vibration sensor due to formed ice in blades
Anemometer icing that result in a measured wind speed below cut- in
Restriction of public access.
While ice remains on the turbine, restrict access to the wind farm by site personnel.
7.2.2 Electromagnetic interference Another effect from wind turbines is electromagnetic interference (EMI) with
radiocommunications links, aviation and meteorological radar, wireless internet, emergency
services etc.
Since there are no airports in the area aviation radar interference risks are not considered.
34
Interference to radiocommunication signals can be caused by the reflection or obstruction of
the signal by blades of the turbine. It will be minimized by usage of glass reinforced plastic
blades.
7.2.3 Public Access The area of the project is used for grazing by individuals. Measures to provide safe access
for them will be determined and applied after discussion with local authorities and land users.
Mitigation will include cogitable instructions to be followed by contractors, comprising
Construction and Traffic Management Planning.
Measures that will be employed for safety reasons:
Proper public communication to allow timely announcement of local land users
before construction operations or traffic in area open to public access
Appropriate training of security service to avert unauthorized access to project area
Usage of appropriate warning signs to prevent access to unsafe, hazardous place
7.2.4 Shadow flicker Shadow flicker is the flickering effect caused when rotating blades of a wind turbine
periodically cast shadows through constrained openings. The scale of this problem depends
on several factors, such as wind direction and speed, the position of the sun and cloud iness.
For example, it is worse during winter periods since wind speed is high or when she sun is
low in the sky.
7.3 Effect on local population It is important to investigate in details effect of the wind farm to local population. It is
important to notice the fact that wind farm in Astana region are classified as “Category A” by
European Bank for Reconstruction and Development (EBRD). Thus, this project has
potentially significant and diverse social and environmental impacts which need to be
carefully analyzed (Samruk-Green Energy, 2014).
CO2 emission aspect
Operation of a wind farm does not have carbon dioxide emissions. Moreover, it
significantly reduces CO2 emissions in the region due to the fact that it replaces electricity
produced by conventional power plant. Kaldellis (2012) states that approximately 300-350
grams of coal in thermal power plants produce 1 kWh of electricity. While project wind farm
produces about 190 GWh per year which results to 57000 tons of coal savings in one year
and decreasing of CO2 emissions.
35
Involuntary Resettlement and Land Aspects
Project territory does not belong to individual owners, it is state-owned. Thus, there is
no resettlement or physical displacement of people during this project.
Area near the project is used by local residents for open range grazing. Main grazing
area is placed on south and cattle are grazing by moving through project territory. Moreover,
there is huge are near wind farm for grazing and project does not create problem in this
aspect. In addition, after construction phase wind farm area can be used for grazing, while
area near wind turbines will be fenced (Samruk-Green Energy, 2014).
Economic aspect
Taxes paid by the wind farm company to the government of Republic of Kazakhstan
can be classified as indirect economical effect to local residents and can be not considered in
details due to the fact that it is unknown what part from taxes will go to Ereymentau region’s
budget.
In addition, wind farm creates additional jobs for local residents. In construction phase
25-50 unskilled and semi-skilled can be created, for operation phase only security positions
can be necessary to the wind farm. Moreover, it is possible to consider indirect economical
aspect as business, transport services for Project employees. In general, job creation is not
significant for local residents in long-term.
Effect from technical aspects
Shadow flicker, noise effects and aesthetic aspects are considered in Chapter 5.
Literature review and appropriate calculations have shown that wind farm operation does not
affect local residents. However, it is important to consider construction phase which has high
noise. Nevertheless, construction works are planned to be performed during day time. It is
important to notice the fact that constructions phase does not take long time comparing with
life period of the project. In addition, Figure 5.1 shows that most of turbines are placed in
distance from town and noise from their construction will not affect local residents.
Summary of effects on population
In general, there is no huge impact on local society. Negative effects are not significant and
mainly include technical noise and shadow flicker effect which were calculated as not
causing disturbance during operational phase. As shown above, disturbance during
construction phase is not significant too. Positive effects are mainly small economic growth
and CO2 reduction. However, CO2 reduction does not have strong effect on Ereymentau
residents in short-term period due to the fact that there is no huge coal power plant in the
36
town. Nevertheless, the wind farm project is a huge step in wind energy development in
region which is important for CO2 emission reduction in Kazakhstan.
CHAPTER 8. RISK ASSESSMENT
Wind farm managers are under the pressure to minimize the life cycle costs whilst
maintaining reliability or availability aims, and to operate within safety regulation. In this
section a risk based decision-making methodology for undertaking run-repair-replace
decisions with the ultimate target of maximizing the Net Present Value (NPV) of the
investment in maintenance.
The risks cover the three main phases of the project:
Planning and development;
Building, testing, putting into operation;
Operation of the project.
Different stages of the project have distinct risk profiles and concerns for lenders and
financiers. All the risks associated with the project are described below.
Planning and development stage:
Contract bankability
This is the risk of the project being incapable of providing security of bankable offtaker
contracts. Offtaker contract, actually, is one of the conditions to receive financing. It is the
most significant contractual risk. It can effectively terminate the project. So, the severity of
this risk is 5 out of 5. However, with proper control and track of the process the probability of
this risk is very rear and its value is 2 out of 5.
Planning delays
This relates to the risk of delay caused by failure to obtain planning, building permission, and
other necessary authorizations. It can lead to the delay of the project’s start and revision of
permission processes. Since it can increase the cost and timeliness of the project the value
severity level of this risk is set to be 3. Value of probability level is set to be equal to 3 since
delays happen often enough.
Risk of possible prohibition by government
This is the risk of prohibition of the project by the federal government being approved by
local and state administration, though. Severity level of this risk is set to be equal to 4 since it
37
is necessary for the project to obtain an agreement from government. However, having
extensive community consultation probability of this risk reduces significantly and becomes
rare so that probability level is equal to 2.
Environmental impact assessment
Environmental impact assessment is the method used by permission committees to check if
the environmental impact is justified by the approval of the process. The Environmental
Impact Assessment process includes different studies concerning influence on flora and
fauna, noise, cultural heritage and electromagnetic interference. Usually this assessment
requires commitment of subject specialists and can be tedious and expensive. The conclusion
of the EIA will show the probability of successful approval of the project, but it is not always
the case. Severity of this event is relatively big and set to be 4 since it is necessary to obtain a
successful approval from environmental site; however, such assessments are not usual and
therefore, probability level of this risk is set to be equal to 1.
Construction agreement
The construction contract is the formal agreement for construction, alteration, or repair of
structures. It should include all details from the beginning of the performance until
completion of the project. Since lack of this agreement or presence of shortcomings in it put
the construction of the project into the risk severity level is set to be equal to 4 out of 5.
However, with appropriate control measures during signing the agreement probability level
becomes very rare and corresponds to 1 out of 5.
Public opinion
Adverse public opinion is considered a risk to the project, because even a small number of
protests can stop the proceeding of the project. Public judgement in opposition of wind farms
is usually the greatest during the development and construction phases. After the
construction, number of protests tends to reduce. There are various factors that affect public
opinion; however, they are not always reasonable. Severity of negative public opinion risk is
set to be equal to 3 since it can affect the development process and increase cost of the
project. Probability is set to be equal to 2, because with governmental agreement public
opinion rarely becomes negative.
Competition risk
This type of risk is associated with the competition with other developers working in the
same place, searching the same network or grid connection or competing for finance from the
38
same organization. Since the wind power potential in the chosen place in Ereymentau is
strong competition in this place for land in place, where the grid has sufficient capacity for
extra generation can be strong. This aspect can moderately increase the development costs of
the project; thus, the severity of this risk is 3. Since competition in this field of study in the
country is very low, the probability of this risk is minimum and therefore, value of
probability is said to be equal to 1.
Construction stage:
Non-fulfilment of a contract
This jeopardy implies on the turnkey contractor being unable to bring the specifications on
arranged schedule and at the assigned cost. The contractor non-performance is considered to
be relatively low with a limited negative impact; therefore, severity of this risk is assigned to
be equal to 3. Probability level is set to be equal to 3, because likelihood of this event is
occasional.
Engineering risks
Engineering hazards come from imperfections in design, material and qualification. They can
cause a physical damage to the wind farm. Imperfections are usually found during the testing
and putting into operation phase, when the whole project’s productive capacity is being tested
under operating conditions. Defects observed at the late stage of construction can lead to
more expensive repair and replacement costs, can probably result in a considerable delay to
the start of operation of the wind farm. Severity of this risk is said to be equal to 4 out of 5
since imperfections in design as written before can increase the overall cost of the project and
cause a delay, which is undesirable. With appropriate control measures probability of this risk
can be reduced to rare level or level of 2 out of 5.
Physical hazard (caused by human or nature)
This risk involves natural hazards and human caused accidents or in other words
nontechnological nature failures resulting in a physical damage to the structure during the
construction stage. Natural hazards like ice storms, earthquakes and floods are of the most
concern. They can cause great harm to machinery even if they happen very rarely. Severity of
natural hazards is rated higher during the construction stage than during the operation stage.
Overall, severity of these natural hazards is very big and is set to be equal to 5; however, as
was written before probability of these events is very rare and is assigned to equal to 1 out of
5.
39
Offtaker contract failure
This is the risk of power offtakers to draw back from contract subsequent to financial closure
or after the financial closing date, but before the project is started to operate. This risk is
similar to offtaker default, but due to the shorter timeframe, this risk is less possible to occur.
Overall this risk is still considered to be of a high importance. These means that severity of
this risk is crucial and can be assigned to be equal to 4 out of 5, while probability of this
event is 2 out of 5
Grid connection agreement
Getting a grid connection contract for a wind farm requires invitation and approval by the
local network provider. This is commonly the result of expensive and tedious grid connection
studies, which are normally carried out by the network service provider and are able to show
that the project does not negatively affect the stability and reliability of the transmission line
to which it is connected. Severity of this risk is considerable since the costs associated with
connecting a wind farm are usually higher than required, because of the typical requirement
for over-engineering to provide the network service provider with a high degree of
confidence in the electrical stability systems employed. So, severity level is set to be equal to
3 and probability is set to be equal to 2.
Market risk
Market risk is the risk of the wind farm neither getting a power purchase agreement, nor
obtaining funding and is closely related to competitive risk. This risk also concerns the level
of investor confidence and the quantity and quality of investor funds available in the
marketplace for similar projects. Since it is important to obtain finance, severity of this event
is moderate.
Operation stage:
Natural hazards
It relates to the risk of physical damage to the structure and machinery due to natural during
the operation stage. Natural hazards during operating phase have the same impacts as during
construction phase, but with a slightly less pronounced financial impact. Severity of this risk
is set to be equal to 4 and probability is assigned to be equal to 1 due to rare likelihood of the
event.
40
Process Interruption
This risk considers a complete plant shutdown resulting in a overall process interruption at
any time due to unscheduled maintenance. A maintenance event could be triggered by design
imperfection, or other engineering hazards. Severity of this risk is not so significant, but the
probability is occasional.
Offtaker default
This risk concerns the electricity offtaker defaulting from contractual obligations under the
Power Purchasing Agreement after starting of operation of the project. Since this agreement
provides the long-term revenue assurance for the project, it is of an essential concern for the
lenders. Moreover, changes in the bidding proceedings for securing long-term electricity
tariffs for wind power projects in Kazakhstan must be taken into consideration.
Creditworthiness and reputation are also crucial factors of the risk related to Power
Purchasing Agreements.
Warranty non-fulfilment
Warranty non-fulfilment is related to the risk of the turbine fabricant failing to meet
contractual duties under the equipment warranty. This is usually of a significant concern for
wind farm projects. They commonly have a five-year manufacturing warranty to cover all the
equipment service and repair costs. Severity of this risk is set to be equal to 4 and probability
– 2 out of 5.
Wind volatility
This type concerns the risk that average wind speeds can drop below the required levels to
produce economically efficient power outputs and electricity. This risk is considered of
moderate importance and it value is set to be equal to 3 out of 5. Probability of this risk is
very rare and was calculated in part 3.1.
Legal liability
This risk relates to the legal liability caused by bodily injury or property damage to third
parties. It is of medium importance overall. Severity and probability levels of this event are
set to be equal to 2 out of 5 for both of them
Vandalism
The physical hazards caused by a third party to wind energy projects are not well understood,
nor documented. Such acts of vandalism have been known to comprise deliberate damage
41
like graffiti, damage from gun fire, and loosening of guy ropes from monitoring towers. Since
acts of vandalism have the potential to increase costs of maintenance and reduce returns from
energy production, due to turbine down-time severity of this risk is set to be equal to 3 out of
5. However, probability level can be reduced to a minimum level 1 out of 5 with
implementing increased security measures and insurances.
All considered risks and their risk indexes in this project are shown in the table below.
Table 8.1 Identified risks of the project and their risk indexes
№ Name of the risk Severity Probability Risk Index
1 Contract bankability A 2 1A
2 Planning delays C 3 3C
3 Planning issues B 2 2B
4 Environmental impact
assessment
B 1 1B
5 Construction agreement B 1 1B
6 Public opinion C 2 2C
7 Competition risk C 1 1C
8 Contractor non-performance B 2 2B
9 Engineering risks C 3 3C
10 Physical hazard (caused by
man or nature)
A 1 1A
11 Catastrophic design failure B 1 1B
12 Offtaker contract failure B 2 2B
13 Grid connection agreement C 2 2C
14 Market risk D 2 2D
15 Natural hazards B 1 1B
16 Process Interruption D 3 3D
17 Physical hazard (caused by
third party)
C 1 1C
18 Offtaker default A 1 1A
19 Warranty non-performance B 2 2B
20 Wind volatility C 1 1C
21 Legal liability D 2 2D
22 Vandalism C 1 1C
42
The qualitative risk matrix analysis was used to evaluate the risk level of the hazards of the project. To make the analysis 5 levels of severity and 5 levels of risk probability were
adopted in the risk matrix (Table 8.2) Table 8.2 General risk matrix
Risk probability Severity of the accident
Extreme
A=5
Crucial
B=4
Moderate
C=3
Insignificant
D=2
Negligible
E=1
5-Frequent 5A=25 5B=20 5C=15 5D=10 5E=5
4-Likely 4A=20 4B=16 4C=12 4D=8 4E=4
3- Occasional 3A=15 3B=12 3C=9 3D=6 3E=3
2-Rare 2A=10 2B=8 2C=6 2D=4 2E=2
1-Almost impossible 1A=5 1B=5 1C=3 1D=2 1E=1
Here in the table 8.3, 4 risk labels are described for the wind farm project
ordered by quantities of multiplication of risk probability with severity.
Table 8.3 Risk indexes’ criteria
Assessment Risk Index Criteria
5A, 5B, 5C, 4A, 4B, 3A
(15 25)
Unacceptable risk level
Requires immediate action under existing circumstances
5D, 4C, 4D, 3B, 3C, 2A, 2B
(8 12)
Unsatisfactory risk level
Manageable under risk control & mitigation. Requires Risk
Analysis Board & management decision
5E,4E, 3D, 2C, 1A, 1B
(4 6)
Acceptable after review of the operation.
Requires continued tracking and recorded action plans.
3E, 2D, 2E, 1C, 1D, 1E
(1 4)
Acceptable risk level
Acceptable with continued data collection and trending for
continuous improvement.
The frequency definitions are shown in the table 8.4.
Table 8.4 Risk frequency indexes’ defin itions
Frequency Definition
Frequent (5) > 1 in 10 years
Probable (4) 1 in 10 years to 1 in 100 years1
Occasional (3) 1 in 100 years to 1 in 1000 years
Remote (2) 1 in 1000 years to 1 in 10000 years
Improbable (1) < 1 in 10000 years
43
Severity of the risk is also divided on 5 parts, where severity of 5 implies high financial
losses and inability to continue the project and severity of 1 – negligible financial losses and project can be continued working as before.
Table 8.5 Risk matrix of the wind farm pro ject
Risk probability Severity of the accident
Extreme
A=5
Crucial
B=4
Moderate
C=3
Insignificant
D=2
Negligible
E=1
5-Frequent
4-Likely
3- Occasional 2
2-Rare 1 3,8,11,17 6,12,13 19
1-Almost impossible 10,16 4,5,14 7,18,20
As can be seen from the risk matrix no one risk lays on unacceptable levels. With appropriate
mitigation measures risks laying in the unsatisfactory risk level could be reduced to
acceptable levels.
44
CHAPTER 9: ENVIRONMENT
9.1 Soil and groundwater The land of the wind farm project is covered by a brownish humus-rich prairie soils
(Kastanozem). Therefore, the area is primarily utilized for grazing ra ther than agriculture.
Impacts of construction of the project on soil and groundwater will include disposal and
processing of topsoil, soil densification, and possible leakages of fuels and greases.
To minimize the impacts usage at the extent possible of the present roads with an eye
to reduce land take. Furthermore, good practice soil processing technology is to be introduced
comprising the following:
Topsoil will be separately conserved and used for revision of the damaged places after
the construction period;
Reducing topsoil dismantling to the footprint of the turbines, base, new access roads
parts;
Excess of soil will be conserved at special locations specified by local authorities for
future reuse.
To avoid leaks of fuel and greases the following measures should be done:
Every fuel leakages will be instantly cleaned up, and polluted areas will be recovered;
Limitation of facility service refueling at appointed impenetrable hard-standing
locations with introduction of leakage restraint and appropriate control measuresl
Introduction of actions for emergency response
No considerable impacts to groundwater and soil are expected at operation period of the
project.
9.2 Surface water Only little water streams are located in the lowlands on the area of the project.
Activities related to digging or excavation will be stopped during strong rainfall periods in
order to minimize the risk of precipitation, chemicals or oil spilled into natural draining
system. Complete recovery of water streams affected during construction will be
implemented.
During operation period, the project will not need water and therefore, no discharges
will occur. No considerable impacts are expected on the run-off rates and the draining
system throughout the operation period of the project.
45
9.3 Biodiversity and plant impact Possible impacts come from direct habitat loss and demolition of local flora and fauna
during construction, with impacts more probable for organisms that are less mobile like
plants and invertebrates. Damage to rarely met plants and invertebrates is likely if they live
on sites of construction. Furthermore, they can be affected by a dust coming from the
construction site or unexpected shedding of waste. The major operational hazards are
associated with collision and dislocation associated with work of wind turbine. They are
mostly associated with birds and bats.
To mitigate the risks land-take will be minimized where it is possible and land will be
recovered to its natural state. To regulate dust and waste appropriate constructio n practice
will be used. Also to minimize the chance of collisions the wind farm construction could be
outside of known migratory patterns or shutting down of the wind turbines during peak times
of migration will be done.
9.4 Cultural heritage aspects and plant impact In Yereymentau area 25 archaeological entities are registered, which comprise antique
graves, ancient settlements and fences etc. However, none of them are located on the site of
the Project. An archaeological field survey will be carried out to avoid potential impacts on
unfound cultural patrimony.
9.5 Landscape and visual aspects and plant impact The implementation of two dozens of wind turbines having maximum height of 140 m
to tip and maximum 80 m to hub will affect visual aspects and local landscape. They will
make artificial elements of significant scale comparing to the natural landscape setting a new
landmark in views from far apart. The wind farm means a clear, obvious and continuous shift
in landscape features involving a bigger area. But, the susceptibility of the landscape is not
high, which means that the landscape impact of the project is in medium.
To minimize impacts on the landscape several mitigation measures should be made:
Minimization of Vegetation removal;
Prohibit all advertising and brands on the turbines;
Removal of all signs that are not related to Health and Safety issues on turbine doors
Increase vegetation or planting of trees to minimize visual impacts
However, implementing these measures will not completely remove the visual impact on the
landscape. They can only mitigate it to a certain level.
46
CHAPTER 10. PROJECT MANAGEMENT
The project organization is to be described in perspective of project owner organization.
Figure 10.1 illustrates the organization of project: owner will contract subcontractors. These
are tower/turbine supplier and project developer, which will manage majority of construction
processes. Apart from that owner is responsible for construction of power lines and
environmental aspect of project, e.g. obtaining environmental permission acts,
impact/mitigation measure analysis. Moreover, owner will be head of on-site project
management, quality control, and documentation during realization period.
Figure 10.1 Project organization
Tower/Turbine supplier has been chosen as Siemens Company, turbine to be supplied is
Siemens SWT- 2.3 108 and more detailed information can be found in chapter 4.
As you might notice from figure above, most of the construction work is performed by
developer. In practice, the developer is an organization that initially proposed the wind farm
design and informed about it in detail.
Project is divided into 5 phases that supposed to fulfill certain requirements during each
stage. Very first stage has been accomplished by team, which is mostly dedicated to the
feasibility analysis for construction. Next stage includes throughout analysis of wind in
Ereymentau area, test of soil, and simulation of preliminary farm layout along with start of
permission documentation issuing. Phases III and IV are strongly interconnected so that the
tasks done in 3rd stage will contribute to the efficient construction strategy in terms of time
and resource management in the upcoming stage. Finally, last phase of Ereymentau wind
farm project is dedicated to the commercial operation of plant as far as the testing and
finalization of construction is conducted. During last phase, crew training and safety related
tasks are held. As far as the all considered phases carried through, the Ereymentau wind farm
47
is ready to operated at its rated power and generate green energy. Table below, summarizes
the tasks to be conducted during each phase and specifies duration, current status.
Table 10.1 Project management plan
Phases Tasks Period or duration Current status
Phase I:
Preliminary studies
Site evaluation
Prefeasibility study
Wind resource
assessment
Preliminary
economics study
Wind turbine
choose
Stakeholders
engagement plan
preparation
Calculations on
chosen wind turbine
performance
Wind farm layout
1st
year Completed
Phase II:
Design preparation
Permitting
Technical details
Detailed wind data
collection
Begin collection of
permission
documentation
Preliminary farm
layout
Local soil testing
Layout optimization
1st
and 2nd
years Complete
Phase III:
Project finalizat ion
Complete permitting
Finalize budgeting
Order wind turbines
Road construction
completed
Foundation
construction begins
2nd
and 3rd
year Incomplete
Phase IV:
Construction
*Weather condition
Foundation
completed
Collection system
3rd
year Incomplete
48
might influence
duration
and cabling
completed
Turbines delivered
to construction site
Transmission lines
built
220/35 kV
substation with
63MVA transformer
completed
Relay protection
and automation
installed
Turbine erection
done
Service supervisory
control unit build
Inspection and
testing
Optimization and
maintenance
Phase V:
Commercial operation
Operation and
maintenance
Crew training
Safety issues
Incomplete
49
RESULTS AND DISCUSSION
Analytic and mathematical methods of assessment were used to conduct feasibility
analysis for Ereymentau wind farm construction. Therefore, the aim of the study is assumed
to be reached. To sum up, study determines current energy generation sector of Kazakhstan
and reveals that majority of energy produced is by use of coal- mine resource. Consequently,
the greenhouse gasses emission is high and as consumption of electricity rises it becomes
even higher. As a possible solution, use of renewable energy sources is suggested. To be
precise, one of the most attractive, in terms of energy output, the wind farm is proposed. As a
result of site selection study, the Ereymentau region was determined to be suitable for wind
power plant construction. Next, wind potential has been assessed, which reveals that
Ereymentau has strong wind energy potential. Therefore, wind turbine choose stage analysis
demonstrates that Siemens SWT- 108 2.3MW turbine performance is the highest among
other alternatives and 22 turbine will result in 190GW*h green energy annually with capacity
factor of 40%. Further development provides the results of detailed analysis of technical,
bureaucratic, strategic aspects result in the overall energy deficiency reduction in the region.
Additionally, economic analysis illustrates that total initial investment required is $140
million and with support of governmental policies project will bring revenue after 9-10 years.
The consideration of environmental, community health and safety, risk assessment
complements the study and shows that there are no drawbacks of this project on above
mentioned aspects. The project is planned to be implemented in 3 years and divided to 5
phases, which are described in the project management chapter of this paper.
Generally speaking, the study was conducted according to mathematical models and
supported by reliable sources. The information used in analysis is more or less up to date and
obtained results are realistic. Specific engineering solutions were provided and various
aspects, including engineering, social, and environmental, were taken into account in final
wind farm design and project management plan.
Chapter 4 mentions that wind farm energy production is seasonal. Therefore, it is
suggested to integrate PV panels into design that will result in higher energy output during
summer times. Such systems are well knows as hybrid and widely practiced in the world.
50
CONCLUSION
Technical and economical analyzes were done in the Project Report. According to technical
analysis, Ereymentau has high wind potential and developed infrastructure for electricity
production. Moreover, the most effective SWT-108 2.3MW turbine is chosen for the project.
Power calculation for wind park shows opportunity to have 40% capacity factor which is
higher than average capacity factor in industry. However, it must be stated from economical
analysis that support from Government of Kazakhstan is absolutely necessary due to the fact
that the wind farm is not profitable without support and greed tariffs. This is caused mainly
by extremely low prices for coal- main source of energy in the region. As a result, Project is
feasible only with support from Government of Kazakhstan. Nevertheless, importance of the
Project for wind industry development and CO2 emission reduction in Central Asia region is
significant.
1
REFERENCE LIST
1. Ali Sayigh, 2012. Comprehensive Renewable Energy (8 Volume Set) . Volume2: Wind Energy. 1st Edit ion.
Elsevier. ISBN: 978-0-08-087872-0
2. Awea.org. (2015). The Cost of Wind Energy in the U.S. [Online].
Available:http://www.awea.org/Resources/Content.aspx?ItemNumber=5547#Comparat iveCost . [Accessed:
8- Apr- 2015].
3. Baltabayeva D. B., Bogolyubova E.V. (2012). Analysis of statistical characteristics of climate parameters in
Central Kazakhstan, Aqmola region . Vestnik KazNU Journal. A lmaty, Kazakhstan. Retrieved at March, 1
from: http://articlekz.com/art icle/8635
4. Bañuelos-Ruedas F., Angeles-Camacho C. and Rios-Marcuello S. (2011). Methodologies Used in the
Extrapolation of W ind Speed Data at Different Heights and Its Impact in the Wind Energy Resource
Assessment in a Region, W ind Farm - Technical Regulations, Potential Es timation and Siting Assessment,
Dr. Gastón Orlando Suvire (Ed .), ISBN: 978-953-307-483-2, InTech, DOI: 10.5772/20669. Retrieved at
February, 24 from: http://www.intechopen.com/books/wind-farm-technical-regulat ions-potential-estimation-
and-siting-assessment/methodologies-used-in-the-extrapolation-of-wind-speed-data-at-different-heights-and-
its-impact-in -th
5. Ermentau Wind Farm.(2008). Pre-feasibility Study. UNDP
6. General Electric (2009) 1.5MW Wind Turbine, USA: General electric.
7. Government Regulation of Republic of Kazakhstan. (2003). O razvitii vetroenergetiki. Retrieved at March, 1
from: http://www.windenergy.kz/eng/pages/Legislation.html
8. Government of Kazakhstan and UNDP Kazakhstan. (2008). Vetrovaya elektrostantsiya vblizi g. Ereimentau.
Predinvestitsionnoe issledovanie, 1st ed. Almaty.
9. International Renewable Energy Agency. (2012). Renewable Energy Technologies: CostAnalysis Series,
IRENA. Bonn, Germany.
10. International Renewable Energy Agency (IRENA). (2014). Renewable Power Generation Costs in 2014.
IRENA, Bonn, Germany.
11. KazEnergy (2013) Green Energy of Kazakhstan, Available at:http://www.kazenergy.com/ru/5-49-
2011/3445-green-energy-of-kazakhstan.html(Accessed: 10th April 2015).
12. KEGOC (2015) Электроэнергетика Казахстана: ключевые факты, Availab le
at:http://www.kegoc.kz/elektroenergetika/elektroenergetika-kazakhstana-klyuchevye-fakty/(Accessed: 10th
April 2015).
13. Law of the Republic of Kazakhstan «ABOUT SUPPORT OF USE OF RENEWABLE SOURCES OF
ENERGY».(2003). Unofficial translation. Retrieved at March, 2 from:
http://www.windenergy.kz/files/1265263663_file.pdf
14. Ministry of Energy and Mineral Resources of Republic of Kazakhstan. (2007). Nacionalnaiya programma
razvitiya vetroenergetiki do 2015g s perspektivoi do 2024. Project of Republic of Kazakhstan Government
and United Nation Development Program. Retrieved at March, 2 from:
http://www.windenergy.kz/files/1213794277_file.pdf
2
15. Ministry of Energy of Republic Kazakhstan (5th November 2014) “GREEN BRIDGE” FOR
DEVELOPMENT OF COOPERATION, Available at : http://en.energo.gov.kz/index.php?id=1662 (Accessed:
12th April 2015).
16. Nrel.gov. (2013). NREL: Energy Analysis - Levelized Cost of Energy Calculator. [Online]. Availab le:
http://www.nrel.gov/analysis/tech_lcoe.html. [Accessed: 13- Apr- 2015].
17. Rules of definit ion of the nearest point of connection to the grid or thermal networks and connections of the
objects on use of renewable.(2009). Retrieved at March, 2 from:
http://www.windenergy.kz/files/1264479839_file.pdf
18. Renewable Energy Advisors. (2011) LCOE. [Online]. Available:http://www.renewable-energy-
advisors.com/learn -more-2/ levelized-cost-of-electricity/. [Accessed: 10- Mar- 2015].
19. Rfc.kegoc.kz. (2014). V Kazakhstane utverzhdeny tarify na “zelenuyu” elektroenergiyu | LLP “Raschetno -
finansovyi tsentr po podderzhke vozobnovlyaemyh istochnikov energii”. [Online]. Availab le:
http://www.rfc.kegoc.kz/v-kazaxstane-utverzhdeny-tarify-na-zelenuyu-elektroenergiyu/. [Accessed: 11-
Mar- 2015].
20. Samruk- Green Energy (July 28, 2014) http://samruk-
green.kz/project/possilke/preEIA_Addendum_Report_Yereymentau.pdf, Siemensstasse 9; 63263 Neu-
Isenburg Germany: ERM Frankfurt.
21. Schuller M. (2010). Technicheskie i kommercheskie aspekti razrabotki vetroenergeticheskih proektov,
abridged version. Ukrainian Sustainable Energy Lending Facility. FICHTNER GmbH & Co. K.
Sarweystraße 3, 70191 Stuttgart. Retrieved at February, 27 from:
http://www.uself.com.ua/fileadmin/documents/WS4_Wind_Markus_Schueller_rus.pdf
22. Siemens (2011) Siemens Wind Turbine SWT-2.3-108, Lindenplatz 2 20099 Hamburg, Germany: Siemens
Wind Power A/S.
23. The Kazakhstan Electricity Association Committee on Renewable Energy Sources.(2015). Retrieved at
February, 27 from: http://www.windenergy.kz/eng/pages/Legislation.html
24. The World wind energy association (2014) Half-year report, Charles-de-Gaulle- Str. 5; 53113 Bonn,
Germany: WWEA.
25. The European Wind Energy Association. (2009). The Economics of W ind Energy. EW EA, Belg ium.
26. Tradingeconomics.com. (2015). Kazakhstan Inflation Rate | 1992-2015 | Data | Chart | Calendar | Forecast.
[Online]. Availab le: http://www.tradingeconomics.com/kazakhstan/inflation-cpi. [Accessed: 17- Apr- 2015].
27. Vestas (2014) V126-3.3 MW™ at a Glance, Available at: V126-3.3 MW™ at a Glance(Accessed: 10th April
2015).
28. Vestas (2014) V117-3.3 MW™ at a Glance, Available at: V126-3.3 MW™ at a Glance(Accessed: 10th April
2015).
29. WindFarm software Tutorial.(2015).The Nature of Wind. Retrieved at February, 25 from
http://www.resoft.co.uk/English/index.htm
30. Windmeasurementinternational.com. (2015). W ind Turbines. [Online]. Availab le:
http://www.windmeasurementinternational.com/wind-turbines/om-turbines.php. [Accessed: 17- Apr- 2015].
31. Windustry. (2015). How much do wind turbines cost? [Online]. Available:
http://www.windustry.org/how_much_do_wind_turbines_cost . [Accessed: 17- Apr- 2015].
3
32. X-rates.com. (2015). Exchange Rate Average (Euro, US Dollar) - X-Rates. [Online]. Available:
http://www.x-rates.com/average/?from=EUR&to=USD&amount=1&year=2006. [Accessed: 17- Apr- 2015].
33. Yakovenko, O.V. (2014) Parallnaya rabota vetroelectrostancii v EES na primere Ereimentauskoi VES,
Almaty: Almaty university of energy and communication.
34. Yoursri.com. (2013). Topic o f the month Summer 2013 (July/August): Onshore Wind Energy – A Case
Study — yourSRI - Socially Responsible Investments. [Online]. Available: https://yoursri.com/responsible-
investing/newsletter/Topic%20of%20the%20month%20July%202013. [Accessed: 17- Apr- 2015].
A
APPENDIX
Figure 6.1.3. Calculation of Simple Levelized Cost of Electricity (Nrel.gov, 2013)
Table 6.1.1 Cost estimations and IRR
Name Unit cost Quantity Cost
Turbine Cost $1 165 000/MW
50.6 MW
$58 949 000
Grid Connection $137 000/MW $6 932 200
Foundation $100 000/MW $5 060 000
Land Rent $60 000/MW $3 036 000
Electric Installation $23 000/MW $1 163 800
Consultancy $19 000/MW $961 400
Financial Costs $19 000/MW $961 400
Road Construction $14 000/MW $708 400
B
Control Systems $5 000/MW $253 000
Initial Investments
(as for 2006) $1 541 000/MW $77 975 600
Initial Investments, average
inflation rate 6.75% (2015) $2 774 046/MW $140 368 506
Rated Power of WF 0.984 MW
22 turbines
50.6 MW
Actual Power of WF 1.395675 MW 21.657 MW
Annual Power Output of WF 8 623 344 kWh 189 713 568 kWh
Average Annual O&M Costs
1% at years 1-2
1.9% at years 3-5
2.2% at years 6-10
3.5% at years 11-15
4.5% at years 16-20
Simple Levelised Cost of
Energy (LCOE)
15.355 KZT/kW*h
($0.083/kW*h)
Average Cost of Electricity
(Astana, January 2015)
13.80 KZT/kW*h
($0.0746/kW*h)
Cost for Wind Energy 24.2109 KZT/kW*h
($0.13087/kW*h)
Lifetime of the Project more than 20 years
Payback Period 9-10 years (feed- in-tarif)
20-21 year (no incentives)
Annual Average Price
Indexation 6.75%
Capacity Factor 42.8%
Loan Interest Rate 3%
Annual Return of Loan
(100+3)/20%=5.15%
Internal Rate of Return
(feed- in-tarif) 8%
Internal Rate of Return
(no incentives) 0%
Table 6.2.1. Scenario 1 Cash-flows
Cost of Wind
Energy
Annual Power
Output
Cash-in-
Flows
Capital
Costs Credit Operations &
Net-Cash-
Flows Revenue
feed-in-tarif,
2014 feed-in-tarif feed-in-tarif Management Costs feed-in-tarif feed-in-tarif
Year
Cost WE ($/kWh)
Power Out (kWh)
CIF FIT ($/year)
CC ($) Credit FIT
($) O$M Costs
($/year) NCF FIT ($)
Revenue FIT ($)
0 -140368506 -140368506
1 0,13087 189 713 568 24827815
-7228978 -1403685 16195152 -124173354
2 0,13087 189 713 568 24827815
-7228978 -1403685 16195152 -107978203
3 0,13087 189 713 568 24827815
-7228978 -2667002 14931835 -93046368
4 0,13087 189 713 568 24827815
-7228978 -2667002 14931835 -78114533
C
5 0,13087 189 713 568 24827815
-7228978 -2667002 14931835 -63182698
6 0,13087 189 713 568 24827815
-7228978 -3088107 14510729 -48671969
7 0,13087 189 713 568 24827815
-7228978 -3088107 14510729 -34161239
8 0,13087 189 713 568 24827815
-7228978 -3088107 14510729 -19650510
9 0,13087 189 713 568 24827815
-7228978 -3088107 14510729 -5139780
10 0,13087 189 713 568 24827815
-7228978 -3088107 14510729 9370949
11 0,13087 189 713 568 24827815
-7228978 -4912898 12685939 22056888
12 0,13087 189 713 568 24827815
-7228978 -4912898 12685939 34742827
13 0,13087 189 713 568 24827815
-7228978 -4912898 12685939 47428766
14 0,13087 189 713 568 24827815
-7228978 -4912898 12685939 60114705
15 0,13087 189 713 568 24827815
-7228978 -4912898 12685939 72800644
16 0,13087 189 713 568 24827815
-7228978 -6316583 11282254 84082897
17 0,13087 189 713 568 24827815
-7228978 -6316583 11282254 95365151
18 0,13087 189 713 568 24827815
-7228978 -6316583 11282254 106647405
19 0,13087 189 713 568 24827815
-7228978 -6316583 11282254 117929659
20 0,13087 189 713 568 24827815
-7228978 -6316583 11282254 129211913
Tota
l 3794271360 496556293
-182479058 -82396313 8%
Table 6.2.3 Cash Flows in Scenario 2
Cost of
Electricity Annual Power
Output Cash-in-
Flows Capital Costs
Credit Operations & Net-Cash-
Flows Revenue
Astana,
Jan 2015 no tarif
no tarif
Management
Costs no tarif no tarif
Year Cost EE
($/kWh)
Power Out
(kWh)
CIF
($/year) CC ($) Credit ($)
O$M Costs
($/year) NCF ($) Revenue ($)
0 -140368506 -140368506
1 0,0746 189 713 568 14152632
-7228978 -1403685 5519969 -134848537
2 0,0746 189 713 568 14152632
-7228978 -1403685 5519969 -129328568
3 0,0746 189 713 568 14152632
-7228978 -2667002 4256652 -125071915
4 0,0746 189 713 568 14152632
-7228978 -2667002 4256652 -120815263
5 0,0746 189 713 568 14152632
-7228978 -2667002 4256652 -116558610
6 0,0746 189 713 568 14152632
-7228978 -3088107 3835547 -112723063
7 0,0746 189 713 568 14152632
-7228978 -3088107 3835547 -108887516
8 0,0746 189 713 568 14152632
-7228978 -3088107 3835547 -105051969
9 0,0746 189 713 568 14152632
-7228978 -3088107 3835547 -101216422
10 0,0746 189 713 568 14152632
-7228978 -3088107 3835547 -97380875
11 0,0746 189 713 568 14152632
-7228978 -4912898 2010756 -95370119
12 0,0746 189 713 568 14152632
-7228978 -4912898 2010756 -93359363
13 0,0746 189 713 568 14152632
-7228978 -4912898 2010756 -91348606
14 0,0746 189 713 568 14152632
-7228978 -4912898 2010756 -89337850
15 0,0746 189 713 568 14152632
-7228978 -4912898 2010756 -87327093
16 0,0746 189 713 568 14152632
-7228978 -6316583 607071 -86720022
17 0,0746 189 713 568 14152632
-7228978 -6316583 607071 -86112951
18 0,0746 189 713 568 14152632
-7228978 -6316583 607071 -85505879
19 0,0746 189 713 568 14152632
-7228978 -6316583 607071 -84898808
20 0,0746 189 713 568 14152632
-7228978 -6316583 607071 -84291737
Total
3794271360 283052643
-144579561 -82396313 0
D
Figure 6.7. Total Revenue in two scenarios
Figure 6.8 Operations and Maintenance Costs
Figure 6.9 Cash flows
-$150 000 000
-$100 000 000
-$50 000 000
$0
$50 000 000
$100 000 000
$150 000 000
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
To
tal
Re
ve
nu
e
years
Total Revenue
Revenue (no tarif)
-$7 000 000
-$6 000 000
-$5 000 000
-$4 000 000
-$3 000 000
-$2 000 000
-$1 000 000
$0
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
O&
M C
ost
s
years
Operations and Mainetance Costs
O&M Costs
-$160 000 000
-$140 000 000
-$120 000 000
-$100 000 000
-$80 000 000
-$60 000 000
-$40 000 000
-$20 000 000
$0
$20 000 000
$40 000 000
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
Ca
sh F
low
s
years
Cash-in-flows and Cash-out-flows
CIF
CC
Credit
O&M
1
Team contract
Mission: The purpose of the mission definition is to provide an explanation of the team functions.
The mission of the NurlyZhel team is to conduct feasibility analysis for construction of 50 MW
wind farm near Ereymentau town
Section 1—Name
This organization shall be known as NurlyZhel.
Section 2—Membership
The purpose of this section is to define who is part of the team and the specific roles needed to
manage team business.
A. Members of the team include: Yntymak Abukhanov, Sanzhar Korganbayev, Yelaman Serik,
Yerkebulan Saparov, Shakarim Irmukhametov
B. No member shall purport to represent the team unless so authorized by the team.
C. Each member shall be provided a copy of the team bylaws.
D. Members of the team shall include those listed below with their designated responsibilities.
(spell out specific responsibilities of each officer position).
1. Team Chief: Yntymak
a. Call meetings
b. Facilitate meetings
c. Track Deadlines for Submissions
d. Set meetings with Adviser
2. Deputy Team Chief: Yerkebulan Saparov
a. Economical Aspect
b. Analysis of information from Lectures
c. Dealing with appropriate methodology
3. Secretary/Recorder: Sanzhar Korganbayev
a. Electrical Engineering Leader
b. Weekly Log
c. Evaluation of member’s activity
d. Involvement of each member in work
4. Deputy Team Chief of Civil and Mechanical Engineering: Yelaman Serik
a. Intercommunication of Mechanical and Civil Engineering Parts (construction and
materials)
b. External Communication
5. Mechanical Engineer: Shakarim Irmukhametov
a. Mechanical Part
b. Evaluation of Report Progress
c. Compromise in Conflict Situation
2
E. Removal of members
Uninterested in project, low attendance to meetings, negligence with completing allocated tasks,
conflicts with team members
Section 3—Decision Making
The purpose of this section is to explain how decisions are made by the team. The following
suggestions are offered.
Discussion among team members through providing reliable arguments is main decision making
method. Voting method of decision making has been omitted due to the fact that it may cause
conflict and misunderstanding within the group. Additionally, it negatively influences team spirit
and diminishes motivation of individuals. In order to resolve inconsistency of team members’
opinions discussion of details with team adviser is also assumed to influence decision making.
This method agreed to be reliable because of experience and knowledge of adviser in discussed
area. Among the other methods of decision making, further research is an option. To be precise,
each member familiarizes himself in the area of discussion by further reading and data analysis.
In the next meeting, group is more likely to come to single solution.
Section 4—Meetings
The purpose of this section is to make known to the team and others when meetings are held and
guidelines for meetings. The following suggestions are offered.
A. All affairs of the team shall be governed by Yntymak Abukhanov, unless otherwise specified.
B. Meetings shall be held each Monday and Thursday in order to provide time for each member
for research,the work is processing during the whole week, which maximize the efficiency of
team(when).
C. Unless otherwise noticed, all meetings will be held at the dormitory.
D. Special meetings of the team may be called by team Chief or by request of team
members(how).
E. Approved minutes of meetings and sign- in sheets to record attendance, must be kept for all
meetings.
F. Meeting discussions will be conducted in a conversational format with special regard for a
dialogue that is respectful and considerate of all members in attendance.
G. A meeting agenda, defined by Shakarim Irmukhametov, whose responsibilities include this
part, will guide meeting topics and timing.
H. The length of meetings is not limited in order to work effectively.
I. All meetings will be publicized to members using: phone calls, team websites, e-mail, and
texting.
J. Meetings are planned according to point B.
K. Failure to receive notice does not invalidate a meeting, but the efforts must be made in good
faith.
Section 5—Committees or Work Groups
The purpose of this section is to discuss the formation, responsibilities and disbanding of any
standing or special i.e. ad-hoc work groups. The following suggestions are offered.
3
A. The team lead, with other team members, may organize ad-hoc groups to facilitate specialized
tasks of the team, e.g. economic evaluation, establishing contact with external committee, and
others.
B. Work groups shall report to the team and these reports shall be entered into the minutes.
C. Committees can be permanent or temporary.
D. One team member can enroll to several committees.
E. Each committee have its leader who is responsible for tasks completion.
Section 6—Documentation and Communication
A. Individual members shall document project work as follows:
B. Project work shall be considered confidential, the exception is made for Academic staff
C. Communication with project clients will be held by Yelaman Serik, who is responsible for
external communication.
D. All meeting and ideas are documented by Sanzhar Korganbayev and shared by university
mail system.
F. The Documentation is analyzed and approved by adviser Alexander Ruderman.
D. Corrections which proposed by adviser are made by all group members
Section 7—Amendments
The purpose of this section is to define the process by which these by-laws can be amended. The
following suggestion is offered.
A. By-laws in the contract may be amended due to the demand of the team, such as
obsolescence of initial by- laws, or by the offer of one of the team member.
B. In order to change these by- laws, member who is offering to change a by-law should
prove its necessity and persuade all other team members to agree with him.
C. After that, team should design a new by- law and adopt it to entire team contract at the
meeting time where the voting on whether to change a specific by- law or not has been
done.
Section 8—Effective Date (Required)
The purpose of this section is to state the date of the initial adoption of these by-laws. Statement
of an effective date is required.
A. These by- laws of the “Nurly Zhel” team shall become effective on Monday, February 16,
2015.
B. Dates of amendment must be recorded in minutes of meetings at which amendments were
approved, together with a revised set of bylaws.