Government of India Ministry of New & Renewable Energy National Workshop on Review of Implementation of Rooftop Solar Phase II Programme 12 th June 2021 Proceedings Opening Remarks: Mr Amitesh K Sinha Joint Secretary MNRE gave the opening remarks. He provided an overview on India’s 175 GW target under the National Solar Mission including rooftop solar (40 GW), challenges faced by the rooftop solar sector, achievements and progress under the MNRE Phase-II program, engagement of DISCOMs in rooftop solar implementation and with various Technical assistance programs for creating the enabling environment towards accelerating rooftop solar implementation. Despite various challenges, the rooftop solar sector holds promise to both the consumers and DISCOMs and assured that MNRE will continue to address and to overcome the challenges. He requested DISCOMs to discover prices for allocated capacities on a fast-tracking basis. As regards Ease of Doing Business, he emphasized DISCOMs to disburse the subsidy to vendors timely and publish all information for facilitating consumers to apply for approvals and implement rooftop solar projects. He further emphasized taking appropriate action who has agreed to implement the projects at L1 price through tender and suitable penalty clauses should be incorporated in the tender. He encouraged DISCOMs to promote rooftop solar in sectors other than residential sector and implement new and innovative business models. Overall Summary - Phase-2 Rooftop Solar Program: Mr J K Jethani, Director, MNRE presented and elaborated on the implementation aspects of Grid Connected Rooftop Solar for Phase II Programme issued on 20th Aug 2019. As of date, MNRE has allocated app. 3 GW of rooftop solar capacity to DISCOMs and released Central Financial Assistance amount of INR 266 Crs, resulting in an installed capacity of 699 MW in the residential sector. He informed that as of date, 61 DISCOMs have reported a cumulative installed rooftop solar capacity of 4.32 GW. He further updated on various clarifications issued by MNRE towards implementing the Phase II program including the blanket extension provided due to pandemic and the procedures for claiming incentives. Finally, Mr Jethani touched upon the various challenges faced by the DISCOMs and vendors in rooftop solar implementation related to the pandemic, increase in components’ price, tender timings and extensions, DISCOM reduced uptake due to RPO compliant status etc., Presentations by States on sharing of successful experience in rooftop solar implementation Four presentations were made on sharing the key enablers and factors for successful implementation of rooftop solar by GUVNL, KSEB, BRPL and CREST. The summary of the presentations is provided below: Gujarat Urja Vikas Nigam (GUVNL) made a comprehensive presentation on the key success factors of large-scale rooftop solar implementation in the residential sector in Gujarat. The success elements included but not limited to (i) empanelment of large number of vendors (app. 550), (ii) effective implementation plan, (iii) effective use of digital platform, (iv) deployment of dedicated DISCOM officials for overall support (incl. pre-dispatch inspection of modules, follow-up with consumers’ interest, approvals, inspection etc.,) (v) extensive state level awareness creation program (vi) Ease of Doing Business and (vii) wide spread media and outreach initiatives. As a result of these, Gujarat alone has achieved installation of 634 MW.

Transcript of 115_notification.pdf - Solar Rooftop

Government of India Ministry of New & Renewable Energy

National Workshop on Review of Implementation of Rooftop Solar Phase II Programme

12th June 2021

Proceedings

Opening Remarks: Mr Amitesh K Sinha Joint Secretary MNRE gave the opening

remarks. He provided an overview on India’s 175 GW target under the National Solar

Mission including rooftop solar (40 GW), challenges faced by the rooftop solar sector,

achievements and progress under the MNRE Phase-II program, engagement of

DISCOMs in rooftop solar implementation and with various Technical assistance

programs for creating the enabling environment towards accelerating rooftop solar

implementation. Despite various challenges, the rooftop solar sector holds promise to

both the consumers and DISCOMs and assured that MNRE will continue to address and

to overcome the challenges. He requested DISCOMs to discover prices for allocated

capacities on a fast-tracking basis. As regards Ease of Doing Business, he emphasized

DISCOMs to disburse the subsidy to vendors timely and publish all information for

facilitating consumers to apply for approvals and implement rooftop solar projects. He

further emphasized taking appropriate action who has agreed to implement the projects

at L1 price through tender and suitable penalty clauses should be incorporated in the

tender. He encouraged DISCOMs to promote rooftop solar in sectors other than

residential sector and implement new and innovative business models.

Overall Summary - Phase-2 Rooftop Solar Program: Mr J K Jethani, Director, MNRE

presented and elaborated on the implementation aspects of Grid Connected Rooftop

Solar for Phase – II Programme issued on 20th Aug 2019. As of date, MNRE has

allocated app. 3 GW of rooftop solar capacity to DISCOMs and released Central

Financial Assistance amount of INR 266 Crs, resulting in an installed capacity of 699

MW in the residential sector. He informed that as of date, 61 DISCOMs have reported a

cumulative installed rooftop solar capacity of 4.32 GW. He further updated on various

clarifications issued by MNRE towards implementing the Phase II program including the

blanket extension provided due to pandemic and the procedures for claiming incentives.

Finally, Mr Jethani touched upon the various challenges faced by the DISCOMs and

vendors in rooftop solar implementation related to the pandemic, increase in

components’ price, tender timings and extensions, DISCOM reduced uptake due to

RPO compliant status etc.,

Presentations by States on sharing of successful experience in rooftop solar

implementation

Four presentations were made on sharing the key enablers and factors for successful

implementation of rooftop solar by GUVNL, KSEB, BRPL and CREST. The summary of the

presentations is provided below:

Gujarat Urja Vikas Nigam (GUVNL) made a comprehensive presentation on the key

success factors of large-scale rooftop solar implementation in the residential sector in

Gujarat. The success elements included but not limited to (i) empanelment of large

number of vendors (app. 550), (ii) effective implementation plan, (iii) effective use of

digital platform, (iv) deployment of dedicated DISCOM officials for overall support (incl.

pre-dispatch inspection of modules, follow-up with consumers’ interest, approvals,

inspection etc.,) (v) extensive state level awareness creation program (vi) Ease of Doing

Business and (vii) wide spread media and outreach initiatives. As a result of these,

Gujarat alone has achieved installation of 634 MW.

Government of India Ministry of New & Renewable Energy

Mr Abhishek Ranjan AVP, System Operation from BSES Rajdhani Power Ltd., (BRPL)

BRPL presented on the digitalisation of / online management of rooftop solar

implementation in Delhi. He explained the aspects of digitalization of (i) unified web

portal, (ii) consumer awareness and knowledge dissemination, (iii) overall management

of the workflow including internal fleet view of the progress and impact and (iv) Internal

review of online monitoring of the rooftop solar systems in Delhi. The workflow

management along with design & analytics module provides BRPL a comprehensive

understanding of consumer needs (leads generation and deal conversions) and

requirements and enables BRPL to devise service solutions accordingly including

consumer’s view of benchmarking their performance with the rest of consumers.

Abhishek further updated that BRPL has modified the existing rooftop solar app

developed under EU India TA program and will be launched soon. Currently BRPL is

working on establishing an internal dashboard for reviewing the generation Vs forecast

trends besides others and is engaging with inverters to develop APIs to achieve real

time monitoring of rooftop solar systems. He also touched upon the portable rooftop

solar systems being implemented on pilot basis in Delhi and its analysis with and

without battery storage.

Ms R Deepa, Assistant Executive Engineer, SOURA Project, Kerala State Electricity

Board made the presentation as regards the implementation of innovative business

models for large scale deployment of RTS in Kerala. The presentation outlined the

unique features of three business models with and without Utility investment combined

with annuity payments and levelized tariff for vendors and capital investment by

consumers (after subsidy). Despite unique business models and overwhelming

responses from the consumer for RESCO model, the tenders weren’t successfully

implemented due to apprehensions by vendors in implementing RESCO models for low

capacity consumers, minimum bid capacity, low ceiling bidding tariff etc., MNRE

emphasised that vendors should be onboarded on upfront basis for implementing such

business models which should be simple with low number of control parameters and

combined with ease of doing business. Further it was suggested by MNRE that vendors

should be provided 80-90% of their system costs to enable them to support the 5 years

AMC without any challenges. DISCOMs can always consult with MNRE for simplifying

the tendering processes where need, relevant and applicable.

Mr Sukhwinder Abhrol, Project Director, Chandigarh Renewable Energy and Science &

Technology (CREST) presented on the key features of the RESCO based Build Own

Operate and Transfer model for implementing residential rooftop solar systems in

Chandigarh. He informed that the consumers are looking forward to such a model and a

demand aggregation of over 2.5 MW has already been garnered. This may have slowed

down the implementation of the ongoing CAPEX tender with the discovered L1 price. He

explained the benefits offered by this model to all the key stakeholders involved

(consumer, developer, DISCOM and CREST) basis which a quadripartite agreement

has been proposed for execution. The bidding parameter will be the number of days the

vendor would operate the rooftop solar system and then transfer the ownership to the

consumer. JERC had convened the first hearing following which CREST is updating the

documents incorporating JERC’s comments. The revised submission to JERC will be

done soon by CREST for subsequent hearing.

Government of India Ministry of New & Renewable Energy

Presentation by Donors on TA and DISCOMs on Overall progress on Rooftop Solar

implementation in States

The World Bank TA Program

Dr. Amit Jain from The World Bank discussed about the SUPRABHA program, its

interventions, achievements and key aspects from DISCOM’s perspective for

streamlining and scaling rooftop solar implementation.

o Subsequently, Dinesh Babu, EY PMC presented on the overall progress and

current status of operationalization of the rooftop solar projects under the

MNRE Phase II Program by the DISCOMs from 17 States

o Nagaland : JS MNRE will be talking to Principal Secretary, Nagaland for

expediting development on Rooftop Solar

o UHBVN requested for additional capacity under the existing first allocation,

and requested MNRE for time extension for submission of PCRs

o DHBVN to resolve claims by ZunRoof and keep MNRE in the communication

loop

ADB TA Program

Mr Jigar Bhatt from ADB introduced the TA Program following which Mr Ajit Pandit, from

IDAM Infrastructure presented on the overall progress and achievements on TA

activities implemented in 8 States allocated by MNRE.

o Subsequently, Mr Abhishek Shah from KPMG presented on the overall

progress and current status of operationalization of the rooftop solar projects

under the MNRE Phase II Program by the DISCOMs from 8 States.

o All states agencies (except LED & MESCOM) participated and presented the

status update and challenges encountered by them.

o TA Program also highlighted difficulties regarding progress in Lakshadweep

and MESCOM, as presented during MNRE review meeting from time to time.

o Telangana DISCOM to resolve claims by ZunRoof and keep MNRE in the

communication loop.

GIZ TA Program

Mr Abhinav Jain from GIZ India presented the activities implemented by GIZ’s TA

Program (IGSEP RTPV 2.0) for rooftop solar in 11 States and UTs. He further

presented on the overall progress and current status of operationalization of the rooftop

solar projects under the MNRE Phase II Program in these States/UTs. MNRE and GIZ

observed that while the Gujarat has demonstrated an overwhelming success, Uttar

Pradesh still had inherent coordination issues between DISCOMs and State Nodal

Agency.

Key officer from DISCOMs from all the partner States of the above Donor TA Programs also

provided their updates, shared their challenges and success factors and sought clarifications

from MNRE.

Presentation by Bankers and Financing Institutions on financing Rooftop Solar

Mr Sanjay Haider, AGM, (CPPD), SBI presented on SBI’s role in financing renewable

energy and the success achieved in the financing over INR 32,000 crores for 752

projects, as of 31st March 2021. He explained the various efforts in providing attractive

features to consumers for securing loan for implementing renewable energy projects. In

specific, he updated the financing of rooftop solar projects under the World Bank line of

Government of India Ministry of New & Renewable Energy

credit to the tune of $625 Mn. SBI, as on 32st March 2021, has disbursed $220 Mn

against a sanctioned portfolio of $290 Mn and 550MW.

Mr Piyush Kumar Arora, Manager (technical Services) IREDA presented on the 5

lending schemes of financing rooftop solar projects in India including line of credit facility

and loans against securitization of future cash flows. He further said eligible borrowers

include RE suppliers, developers, contractors, DISCOMs, TRANSCOs, Government

Agencies and State owned trading companies. He shared the financing norms, checklist

for appraisal and risk assessment, challenges faced during appraisal, sanction and

disbursement along with a case study.

Mr Mudit Jain, Head- Research, TCCL, presented on the financing of rooftop solar

projects under the Green Climate Fund’s Line of Credit of $100 Mn. He further

elaborated on the key risk and challenges which TCCL review and analyse during

financing of such rooftop solar projects. He further emphasized on the need for a first

loss guarantee for further scaling the rooftop solar implementation for the SME segment.

Launch of Online Training Platform:

Mr Pulkit Dhingra, AHA Solar, engaged by GIZ facilitated the launch of the online

training platform developed under the GIZ TA Program and presented on the details

of the functionalities of the platform. Mr Abhinav Jain from GIZ mentioned that the

access details will be shared with MNRE for further circulation to all the DISCOMs to

access and benefit from the online training. Currently a module on “Inspection of

Rooftop Solar System” is available for online training

(https://dev.teksun.com/projects/ahasolar/login/index.php).

Vote of Thanks

Mr. Hiren Borah, Scientist D, MNRE delivered the vote of thanks to all the participants.

Key Outcomes including Action Points:

Rooftop Solar Phase II Program

MNRE is making all efforts to release of incentives and DISCOMs are requested to

submit the request and also ensure that the data is aligned, data duplicity and

discrepancy in data collection are avoided and ensure syncing with the data previously

submitted

MNRE will issue a clarification that Benchmark Price published on an annual basis need

not be taken as the ceiling price for discovering L1 from tenders by DISCOMs

Gujarat Success Story will be shared with all the DISCOMs in other States for

implementing the key aspects of Media & Outreach activities adopted by GUVNL

SBI requested to design and launch financing product for financing renewable energy

including residential rooftop solar under the RBI’s Priority Sector Lending (PSL) scheme

MNRE will be releasing the new benchmark price for FY 21-22

TA programs to share development of any unique and additional models under the

Unified Web Portal (UWP) changes to other DISCOMs / States for adoption

DISCOMs to develop and finalize business models in consultation with vendors to

achievement efficacy in tendering

DISCOMs who are unable to tender their allocations sanctioned during 2019 and 2020

should consider surrendering the capacity and request for revised capacity (e.g)

Southern AP DISCOM, Karnataka, Nagaland etc.,

Government of India Ministry of New & Renewable Energy

MNRE is currently working on developing specifications and guidelines for remote / real-

time monitoring of rooftop solar

DISCOMs uniformly requested MNRE for training of officers on Rooftop Solar on various

aspects (Inspection, Subsidy Disbursement, Technical Aspects etc.,) through TA

Programs besides online training

Assam may explore solutions to re-allocate the 400 kW due to withdrawal of one vendor

MNRE to launch national media and outreach program soon

MNRE may consider release of the withheld 25% of 3% service fee to DISCOMs subject

to internal deliberations

MNRE will expedite release of advance subsidy to Private DISCOMs

DISCOMs should avail the services of Technical Assistance programs for completing

the development of Unified Web Portals

DISCOM should independently engage agencies for AMC of UWP as TA programs

could provide only 3 months of handholding after handover the portal

All the DISCOMs who haven’t submitted the target capacity were requested to submit

the same at the earliest.

Agenda

Date: 12th June 2021

Venue: Online Event Time: 10:00 am – 02:00 pm

Time Topic Speaker

10:00 AM – 10:10 AM Welcome & Opening Remarks Joint Secretary, MNRE

10:10 AM – 10:20 AM Overall Summary : Phase-2 Rooftop Solar Programme

Director, MNRE

10:20 AM – 11:30 AM Sharing of Experience

Large Scale Deployment of Residential Rooftop Solar through Tenders – Gujarat

Online Management of Rooftop Solar – BRPL

Innovative Business Models by KSEB

RESCO BOT Scheme – CREST

Gujarat Urja Vikas Nigam Ltd.,

BSES Rajdhani Power Limited

KSEB, Kerala

CREST, Chandigarh

11:30 PM – 4:00 PM Presentation by Donors on TA on Rooftop Solar implemented in States

and

Review of progress with DISCOMs

The World Bank

Asian Development Bank

GIZ

04:00 PM – 5:30 PM Presentation by Bankers and Financing Institutions on financing Rooftop Solar

SBI

TCCL

IREDA

05:30 PM – 05:45 PM Launch of Online Rooftop Solar Training Portal

MNRE and GIZ

05:45 PM Vote of Thanks MNRE

Rooftop Solar Programme : Phase-II

• Component-A : Residential sector with subsidy - 4 GW

• 40% subsidy for capacity up to 3 kWp

• 20% subsidy for capacity beyond 3 kWp and up to 10 kWp

• 20% subsidy for GHS/RWA capacity up to 500 kWp

• Component-B : Incentive to DISCOMs for achievements above

baseline:

• No incentives for capacity addition up to 10%

• 5% incentives for addition beyond 10% and up to 15%

• 10% incentives for addition beyond 15%

• Incentive limited to 18 GW capacity

• Implementation Guideline notified on 20.08.2019

RTS Ph-II : Status of Implementation (Updated on 15-06-2021)

FY Capacity allocated Rate

discovered

CFA released Capacity installed

19-20 882.96 MW to 54

DISCOMs in 27

States/UTs

10 States ₹ 12.55 crore

released to 4

DISCOMs of

Gujarat

So far Around 700 MW

capacity installed in residential

sector

(Gujarat 634.33 MW,

Haryana 14.20 MW,

Punjab 9 MW,

Rajasthan 13.29 MW,

Telangana 9.59 MW )

20-21 2099.3 MW to 36

DISCOMs in 24

States

18 States ₹ 91.67 crore

released to 26

DISCOMs

21-22 -- 3 States ₹ 161.81 crore

released to 9

DISCOMs

Out of 65 DISCOMs (31 States/UTs) = 55 DISCOMs have live portal

RTS Ph-II : Status of Implementation

• Toll Free IVRS helpline No 1800 180 3333 launched in February

2020

• Support to Discoms available under Technical Assistance programme

of WB, ADB and GIZ.

• Issued amendments of Phase-II guidelines dated 19-Feb-2021 and 4-

May-2021

• L1 bidder to execute 10%

• Pvt. Discoms to get advance CFA without bank guarantee

• Reduction in CFA in case of extension of timeline

• MNRE retaining 25% of service charges for IEC activities

• As on date around 4.315 GW of cumulative installed capacity

Rooftop solar capacity has been reported by 61 DISCOMs

RTS Ph-II : Incentive to DISCOMs

• Detailed procedure for claiming incentives issued on

19.2.2021

• All documents to be uploaded on SPIN Portal

• Details of all types of Grid connected RTS plants to be included

• RTS plants not connected to grid to be reported separately

• Timeline fixed for submitting claims for 2019-20 was

30.4.2021 and for 2020-21 is 30.6.2021

• 29 DISCOMs have submitted their request for release of

incentives of FY 19-20 and 5 DISCOMs have submitted their

request for FY 20-21.

RTS Ph-II : Implementation Issues

• Lack of awareness and capacity building

• Delay in finalizing tenders

• Low L1 Rate

• Vendors reluctant due to increase in price of RTS components

• Delay in payment of CFA to vendors by DISCOMs

• Delay in submission of PCRs/monthly status in the SPIN portal

• Non-Release of CFA due to pending UCs /EAT implementation

• No capacity demanded for RTS by few DISCOMs

• Web Portal not yet functional in few DISCOMs

• Multiple sanctions at same time (Punjab, Tamil Nadu, Kerala etc..)

• Slow progress due to COVID-19

• Limitation of Net metering up to 10 kW in case of RWA/GHS

• Non implementation of RTS programme : RPO achieved

RTS Ph-II : Issues while claiming the incentives

• Capacity variation in the RTS capacity declared by DISCOMs

• Typographical error in the data/unit while entering in to the SPIN

portal.

• Duplicate entry of commissioned projects in FY 2019-20 and FY

2020-21.

• Instead of capacity addition in a particular FY, all projects included.

• Mismatch in base capacity data in excel sheet and in the covering

letter

• Discrepancy in data of calculating next year base capacity

• Mismatch in rate discovery data reported

• Behind the meter installations included for claiming incentives.

National Workshop on Review of pImplementation of Rooftop Solar Phase II 

ProgrammeProgrammeOnline Management of Rooftop Solar

12th J 2021

g p

12th June, 2021

Abhishek RanjanVP ‐ System Operation & Head – Renewable & DSM

BSES Rajdhani Power Ltd, New Delhi , IndiaBSES Rajdhani Power Ltd, New Delhi , India

BSES is a JV of Reliance Infrastructure (51%) and Govt. of Delhi (49%)1

Presentation Flow• BRPL – Brief Overview• RE Transition & RTS at BRPL• Online initiatives

• Online Portal – NM Application & Knowledge• Online Portal – NM Application & Knowledge• Customer Outreach – Digital means

W kfl M t f RTS j t & Fl t i• Workflow Management of RTS projects & Fleet view• Mobile app – Insights on yield & comparison • Real time monitoring (In House) 

• Submission to MNRE

2

BRPL at a glanceDistribution Area 750 sq KmDistribution Area  750 sq. KmNo. of customers    2.55 Mln. 

Customer Density  3400 /sq Km

Consumer MixConsumer Mix

About 86% residential contributing to ~70%

BRPL

Max Demand  met (Till Date) 3211 MW

Annual Billed energy  12,194 MU

contributing to  70% consumption

BYPL

RE ~ 29% of portfolioFY19 12,194 MU

AT&C Loss FY 20 7.22 %EHV capacity 5559 MVA

portfolio             ( 1300MW+)   by ‘21‐22

> 43% reduction since  

Year ‘02

Peak Demand Met

3

RE Transition at BRPL2019 20 (E b k ) 2021 22 (E b k ) RE P f li (‘21 22) (MU)

13%

3%3%

2019‐20 (Energy breakup)

18%

2021‐22 (Energy breakup)

1,572 , 54%1,164 , 

163 , 6%RE Portfolio (‘21‐22) (MU)

MU

64%17%

13%

53%

14%

12%3%

54%1,164 , 40%

RE Portfolio (‘21‐22) (MW)2019‐20 (Power breakup) 2021‐22 (Power breakup)

771, 64%400, 34%

28, 2%RE Portfolio ( 21 22) (MW)

377 , 13%

50 , 2% 95 , 3%2019 20 (Power breakup)

1,199 , 29%

2021‐22 (Power breakup)

MW, 6 %

1,609 , 54%815 , 28%

1,609 ,40%

815 , 408 , 10%

50 , 1%

20%

4

BRPL’s Rooftop Journey till 31 March 2021

81.86 MWp till 31.05.21

Solar tenders supported by WB Suprabha Program 5 5

BRPL’s Rooftop Journey

Capacity of RTS installations

6

Benefits of RTS for Discoms

7

Online InitiativesOnline Initiatives

1. Online Portal – NM Application & Knowledge2. Customer Outreach – Digital means3 Workflo Management of RTS projects & fleet ie3. Workflow Management of RTS projects & fleet view4. Mobile app – Insights on yield & comparison 5 Real time monitoring (In House)5. Real time monitoring (In House)

8

Online Portal (www.solarbses.com) – Customer view

9 9

Online Portal – Discom view

10

Online Portal (www.solarbses.com) – Discom view

Lead managementg

11 11

SPIN Portal Integration

12

Online InitiativesOnline Initiatives

1. Online Portal – NM Application & Knowledge2. Customer Outreach – Digital means3 Workflo Management of RTS projects & fleet ie3. Workflow Management of RTS projects & fleet view4. Mobile app – Insights on yield & comparison 5 Real time monitoring (In House)5. Real time monitoring (In House)

13

Webinars – A convenient digital means

Weekly / Fortnightly Webinars being held with consumer groups 14

Consumer Outreach Activities

15

Online InitiativesOnline Initiatives

1. Online Portal – NM Application & Knowledge2. Customer Outreach – Digital means3 Workflo Management of RTS projects & fleet ie3. Workflow Management of RTS projects & fleet view4. Mobile app – Insights on yield & comparison 5 Real time monitoring (In House)5. Real time monitoring (In House)

16

RTS Projects – Portfolio Management

17

Workflow Management of RTS Projects

18

BRPL Solar Dashboard – Fleet View

Indicative for Illustration onlyy

19

Individual Consumer performance benchmarkingIndicative for Illustration onlyIndicative for Illustration only

Adopting Behavioral insights from Energy Efficiency to Rooftop Solar

20

Individual Consumer performance benchmarkingIndicative for Illustration only

Inverter Make based performance

21

Individual Consumer performance benchmarking

Solar Panel Make based performance

Indicative for Illustration only

p

22

Online InitiativesOnline Initiatives

1. Online Portal – NM Application & Knowledge2. Customer Outreach – Digital means3 Workflo Management of RTS projects & Fleet ie3. Workflow Management of RTS projects & Fleet view4. Mobile app – Insights on yield & comparison 5 Real time monitoring (In House)5. Real time monitoring (In House)

23

Solar Mobile App • Initially developed under EU India TCP EnergyProgram

• Revamped and integrated with BRPL Business MobileAppApp

• Launch under progress

24

Solar Mobile App 

25

Online InitiativesOnline Initiatives

1. Online Portal – NM Application & Knowledge2. Customer Outreach – Digital means3 Workflo Management of RTS projects & Fleet ie3. Workflow Management of RTS projects & Fleet view4. Mobile app – Insights on yield & comparison 5 Real time monitoring (In House)5. Real time monitoring (In House) 

26

BRPL Solar Rooftop Dashboard (In‐house ‐ POC)

27

BRPL Solar Rooftop Dashboard

28

Discom Solar Rooftop Dashboard – Key points• Standard technical specifications for smart solar inverters needed for DSO operation

• Mandate and modifications in Grid Code to that effect neededeffect needed

• Draft NEP ‘21 has introduced the concept of DSO – A l twelcome step

• Discom owned / controlled RTS model (VPP) will be essential for DSO  

29

BTM Storage – An example

• Plug and Play system which is portable and can be plugged to 16 Amp socket• Upto 2 kWp solar PV modules  and 4.8 kWh BESS (Li ion). BESS life up to 10 years• Generates upto 10 kWh per day• The inverter has Utility interface capability (Useful for DSM & Automated DR)The inverter  has Utility interface capability (Useful for DSM & Automated DR)• Complies with safety norms of CEA, MNRE

Very useful for Discoms with day as well Night peak demand – Provides FlexibilityFlexibility

30

BTM Storage – An example

Version 1 – No Storage 31

BTM Storage – An example

Version 5 – With Li‐ion Storage 32

Submission to MNRE• Strong interest amongst consumers – especially residential

consumers

• Continuity in tender validity is essential to convert

• Past experience shows, break in continuity of scheme leads to fallin interest & conversion

• Request to extend the validity of current sanction till 31 March20222022

• (Majority existing vendors have agreed to stick to current tender)rates)

33

Thank YouGo Solar

Contact Information:bh h k d d bl

Go Solar Abhishek Ranjan, VP and Head Renewable InitiativesEmail: [email protected]

34

National Workshop on

Review of Implementation of Rooftop Solar Phase II Programme

Presentation on Innovative Business Modelsby

KSEBL

Supported by:

Idam Infrastructure Advisory Pvt. Ltd.

&KPMG Advisory Services Pvt. Ltd.

Need of Rooftop in Kerala

Meeting RPO compliance from sources within the State

Utility driven

program

Scarcity of land for ground mounted solar

Retaining Consumer base

Reduction in T&D loss

Helps in managing day demand

Improved tail end voltage

Urja Kerala Mission

3

Vision to develop the energy sector to global standards

FILAMENT FREE KERALA

SOURA

E - SAFE

TRANSGRID 2.0DYUTHI 2021

1000 MW of solar by 2022

Replace all lamps & tubes lights by LEDs

Modernise the distribution gridReduce losses and constraints in transmission networks

Publicity campaign to sensitise users on safety

Soura Program & Business Models

4

500 MW Rooftop

200 MW Ground Mounted

Phase I:

200 MW

Phase II:

50 MW

Phase II: (Retender):

50 MW

Phase III:

200 MW

Roof Lease ModelMaster RESCO ModelConsumer Owned Model

EPC RESCO Hybrid Model & Consumer Owned Model

EPC Annuity PayoutModel & Consumer Owned Model

EPC Mode

300 MW Floating, Solar Park & Canal Top

Soura Key Activities (Phase I – Without CFA)

5

November, 2018Launch of Soura Program

February, 2019Consumer Acquisition▪ Launched web portal

for registrations.▪ Received 2.78 Lacs

Applications

May, 2019Physical survey of Roofs

▪Trained 770 Solar coordinators for physical survey▪Developed Mobile App for

physical survey▪Surveyed 2.78 Lacs roofs

June, 2019

▪ Identify 42,000 Feasible roofs▪ Total capacity of more than

270MW

August, 2019

Identification of Roofs

Received in principle approval, for Soura rooftop program

September, 2019Release of RFP

Regulatory Approval from KSERC

January, 2019

Vendor Meet

Implementation Models (Phase I)

• KSEBL avails roof from

consumers on ‘Right to

Use’ basis.

• KSEBL invests cost of

solar rooftop plant

• Roof owners get a

energy rebate of 10%

of solar generation

• Entire solar generation

to KSEBL

Model 1

• KSEBL invests & develops

solar rooftop plant

through EPC developers

• Energy generated will

be sold to consumers of

respective roofs

• Tariff includes cost of

generation plus margin

and is less than the grid

tariff . The tariff is fixed

for 25 years

Model 2

• Consumers own solar

rooftop plant

• KSEBL build solar

rooftop plant through

EPC developer and

transfer to consumers

Model 3

Phase I: 200MW - All consumer categories (2/2)

7

Tender Outcome

• EPC 50 MW capacity

46.5 MW awarded to three vendors.

• RESCO 150 MW Capacity

No Participation

Consultation with local and major PV project developers of Kerala to understand low participations.

Key issued identified:

• Minimum bid capacity of 5 MW was too high. • Labour cost is higher in Kerala leading to higher overall cost of

installation.• Ceiling prices defined for RESCO Projects are too low • Not viable case for RESCO players, specially when majority of

rooftop were small in size (LT consumers).• Requirement of solvency certificate is a challenge.

Learnings were incorporated in next tenders.

Phase II subsidy scheme – Innovative Models

• Capacity Allocated by MNRE to KSEBL:

✓ FY 2020 – 50 MW &

✓ FY 2021 – 200 MW

• DISCOMS can devise suitable business models:

✓ Subsidy to be targeted towards low end domestic consumers. Should benefit low consumption consumers with monthly consumption upto 200 units per month

✓ All stakeholders should contribute & should have stake in development of RTPV Projects for it to be sustainable business model.

✓ Interest of Utility/ Consumers/ Developer should be protected with proper sharing of risks and rewards.

✓ Recent experience of Bidders participation (RESCO/EPC) of Phase I Soura Tender is considered while devising subsidy based model catering to Domestic Category Consumers.

8

STAKEHOLDERS

9

Risk Sharing among all stakeholders

KSEB

Developer

Consumer

•Quality systems, reliable developer•Assured offtake•Minimal initial investment Funding support

•Retention of consumers• Standardised systems•Balanced growth• Long term sustainable Biz model

•Assured market access/offtake• Clarity of process/systems•Assured payment track

GOK GR – RTPV for Residential under Ph-II

10

• Government of Kerala has issued order and approved:

➢ Three Business Models for Domestic Categories with monthly consumption up to 200 Units.

➢ Financial Contribution by all Consumers + KSEBL+MNRE CFA + Solar Power Developer

➢ Consumer Owned Business Model – Consumer + MNRE CFA.

PHASE II- SUBSIDY SCHEME- Business Models

• Kerala Model - G O dated 13.1.2020 ✓2 and 3 kW capacity plants✓ Stakeholders: KSEBL + Consumer+ MNRE CFA

• Share of stakeholders

• Consumer Model – Consumer + MNRE CFA

✓Netmetering arrangement

Monthly

consumption uptoMNRE CFA Consumer

contribution

Energy Share - consumer

120 40% 12% 25 %

150 40% 20 % 40%

200 40% 25 % 50%

PHASE II- SUBSIDY SCHEME- Business Models

• EPC RESCO Model ✓2 and 3 kW capacity plants;✓ Stakeholders: KSEBL + Consumer + MNRE CFA + Developer

• Share of stakeholders

• Payment : The developer is paid 2/3rd plant cost upon commissioning and balance investment as levelised tariff for 25 years. The levelised tariff will be discovered in bidding. (Rs.2.25 to Rs.1.67 per unit)

MODEL Monthly

consumption

upto, kWh

MNRE CFA Consumer

contribution

KSEBL investment Energy Share -

consumer

IA 120 40% 12% 14.67% + levelised tarifffor generation from plant

25 %

IB 150 40% 20 % 6.67%+ levelised tariff for generation from plant

40%

IC 200 40% 25 % 1.67%+ levelised tariff for generation from plant

50%

EPC RESCO Tender

13

• Tender Outcome✓ Seven bids were received✓ Only two offers received for 2 and 3 kW plants

• Learnings✓ 25 years of O&M for small rooftops is not feasible.✓ Generation based tariff for small rooftops is not attractive for RESCOs✓ RESCO arrangement is not economically viable in cases of small individual

residential rooftop solar projects.

• Since there were not enough bidders in the 2 and 3 kW plant capacitiesand notification of new benchmark rates from MNRE , it was decided tocancel and retender.

PHASE II- SUBSIDY SCHEME- Business Models

• EPC Annuity Payout Model✓2 and 3 kW capacity plants✓ Stakeholders: KSEBL + Consumer + MNRE CFA + Developer

• Share of Stakeholders:

• Payment : 2/3rd plant cost upon commissioning ,Remaining 1/3rd of Capital Cost and O&M for 6th and 7th year -annuity payout basis for7 years. After 7 years O &M by KSEBL

MODEL Monthly

consumption

upto, kWh

MNRE CFA Consumer

contribution

KSEBL investment Energy Share -

consumer

IA 120 40% 12% 14.67% + annuity payout for 7 years

25 %

IB 150 40% 20 % 6.67% + annuity payout for 7 years

40%

IC 200 40% 25 % 1.67% + annuity payout for 7 years

50%

PHASE II- SUBSIDY SCHEME- Business Models

15

• Tender Outcome✓ Only 3 vendors were empanelled and allocated 50MW capacity.

• Learnings: ✓ Limited response received as MNRE benchmark was considered as

upper ceiling limit.✓ Deferred payment of 1/3rd plant cost as annuity payout is not attractive

for developers.

Supported by:

THANK-YOU

KPMG Advisory Services Pvt. Ltd.

Idam Infrastructure Advisory Pvt. Ltd.

&

CRESTChandigarh RESCO BOT Model – Utility Anchored RESCO Model

National Workshop on Review of Implementation of Rooftop Solar Phase II Program

12 Jun 2021

Page 2

Challenges in Conventional RESCO Model

Consumers

Hesitance with long term PPA contract with private party for 25 years

Access to roof blocked for 25 years

RESCO O&M uncertainty for 25 years

Lack of consumer awareness of contractual provisions

RESCO

Payment Uncertainty from consumer

Unfeasibility for small project size

Lack of contract provisions enforcement over a period of time

Contractual uncertainty in addressing defaults and termination during PPA tenure (25 years).

Other operational challenges

Page 3

RESCO

Installs, Operates and Maintains RTS for BOT period

(GRPV Power @ APPC)

Residential Consumers

Residential ConsumersDISCOMS

Rs. 0.07/kWh

APPC – Trading

Margin

APPC

Energy Flow

Contract Flow

Quadripartite

Agreement

CREST

Retains trading margin

Overall Project MonitoringG

ros

s M

ete

rin

g

Net Metering

RESCO BOT Model – Schematics Diagram

Features

❑ CREST / DISCOM aggregates the residential consumers

❑ RESCOs selected by CREST / DISCOM based on competitive

bidding process (Bidding Parameter - No.of days)

❑ RESCO, DISCOM, Nodal Agency & Consumer sign a

quadripartite agreement for overall arrangement

❑ RESCOs own the assets and transfer the ownership after

competitively determined BOT period (days)

❑ DISCOM executes PPA with RESCO for payments @ APPC

for that FY

❑ Residential Consumers pay :

o APPC rate plus Utility trading margin (INR 0.07 per unit) as

Cost of Power for solar units consumed

o this DISCOM determined tariff for balance of grid power

imported from grid

❑ DISCOM issues electricity bill with two part tariff payments

❑ CREST have applied to JERC for approval for under other

business models of Net Metering Regulation

Advantages

Consumer : No investment, no PPA with RESCO and reduced electricity bill

RESCO : Demand Aggregation by DISCOM, reduced transaction cost, and

secured payments from DISCOM

Page 4

Way Forward

• CREST has aggregated residential consumer demand of 2.5 MW equivalent capacities to be taken up

under the scheme

• CREST has undertaken market consultations and understood the viability of the scheme from

RESCO’s perspective

• CREST has obtained approval from CED’s for fixed APPC rate (2020), as procurement cost from this

model, with CERC approved trading margin of INR 0.07 per unit.

• However, due to new APPC rate issued for FY20-21, CREST will reapply to CED with APPC (for current

FY)

• First petition hearing with JERC held on 12th Oct 2020.

• All comments during petition hearing have been addressed and revised petition will be reapplied.

UWPActivities for Installation of RTS

SUPRABHA

Rooftop Solar TA Program

Progress Review

SBI - The World Bank Initiative

12 June 2021

SUPRABHA Rooftop Solar TA Program

Coverage : 17 Indian states

Long Term Concessional Loan: USD 625 Million https://www.sbi.co.in/webfiles/uploads/files/SBI_WORLD_BANK.pdf

Technical Assistance : USD 13 Million

www.suprabha.org

► Odisha

► Jharkhand

► Bihar

► Chhattisgarh

► Rajasthan

► Haryana

► Madhya Pradesh

► Delhi

► Chandigarh

► Assam

► Nagaland

► Manipur

► Mizoram

► Tripura

► Meghalaya

► Sikkim

► Andhra Pradesh

v

- Live UWP

Ground Presence: 17 States

► Odisha

► Jharkhand

► Bihar

► Chhattisgarh

► Rajasthan

► Haryana

► Madhya Pradesh

► Delhi

► Chandigarh

► Assam

► Nagaland

► Manipur

► Mizoram

► Tripura

► Meghalaya

► Sikkim

► Andhra Pradesh

Data Room Sites 4429

Capacity Mobilized 830

MW

MSME Financing Framework

$100

Mn

CGM

UWP Developed 15

Model NEM RegulationsFOR /

CERC

Stakeholders Trained 2282

National Renewable Energy Data

Centre

One Sun One World One Grid

Flagship Programs

Four Years of SUPRABHA

2000

CGM : Credit Guarantee Mechanism

Newsletter, Advertisements,

National and State Media

Collaterals, MNRE Outreach

strategy

Policy & Regulation

Capacity Building

Unified Web Portal

Media & Outreach

States – 17

Live UWPs – 13

UWPs Developed – 2

Yet to be Initiated - 2

Achievements at a Glance - SUPRABHA

MNRE DISCOM Phase II Allocation

Capacity Tendered

DISCOMs published tender

15 States

30 DISCOMs

445.5 MW Total

230.7

28

Summary

In MW

Demand Aggregation

Program (4429 Sites & 381.72 MW)

State – 1

Sites – 465

Capacity – 18.23

Tendered*– 65

States – 11

Sites – 3964

Capacity – 363.7

Tendered* – 250

Residential GovernmentIn MW In MW

2282

Stakeholders Trained(SBI, DISCOMs, Developers,

Entrepreneurs & Trainers)

RTS Policy-2 States

CERC/FOR – NEM2019 (Net Metering Regulations)

*Total Demand Tendered in MW may include capacities which

are not covered under Data Room

14 June 2021

Unified Web Portal

Digital

Interventions

by TA

• Interconnection Module and Subsidy Module

• Vendor Management Module

• Consumer Grievance Redressal Module

• Bank Guarantee Monitoring, Performance Ratio

based penalty assessment

Vendor Mgmt. Portal

• Project management including milestone tracking,

status updates and performance reports

• Power Purchase Agreement automation

• Grievance redressal through time based escalation

features

NORS-DMC @ NISE

• Framework for national level data monitoring of RTS

plants through Advance Metering Infrastructure (AMI)

and Smart Meters / Inverters / Data Logger

Data Room• Solar capacity assessment of site

• Annual solar power generation estimation

• Estimation of solar power losses incurred due to

various factors (e.g shadow analysis)

• Generation of site feasibility assessment and

shadow analysis report

FOR NEM Regulation

• Updated FOR Model NEM Regulation includes

stipulation of installation of Advanced Metering

Infrastructure (AMI) facility with RS 485 (or

higher) communication port

National RE Data Centre

• An integrated RE Data Centre with central data

repository for intelligent monitoring and verification

of RE systems installed across states in India

Digital Interventions by SUPRABHA TA program

Page 5SUPRABHA Progress Review

Achievements: Unified Web Portal

6

Ready to be Launched –

2 StatesLive – 13 States

To be Initiated – 2 States

*Development for APSPDCL is yet to be initiated

Carried out detailed analysis and

provided extensive comments on

Rooftop Solar clauses in the Rights for

Consumers (Electricity Rules 2020)

Analysis and

Comments on

Rights for

Consumers

(Electricity

Rules 2020)

• Engagement with IREDA and MSME Ministry

– working on CGM structure

• Organized MSME Event on RTS–Event for

sharing financing of RTS for MSMEs by SBI

• MSMEs in MP – transaction structure,

engagement with MSME Dept in MP

• Support MSME event in Kerala

MSME CGM & Outreach

Assistance to MNRE

Developed and submitted concept note

and RFP for NREDC

Supported MNRE Progress Review meeting

with DISCOMs on 2nd September 2020

Supporting “Fortnightly Progress Review

Meetings” for DISCOMs in 17 States by

MNRE on RTS Progress

Weekly Progress Review Meeting by

MNRE for Donor TA Programs

Knowledge Portal, FAQs, TOR for

Verification MNRE funded sites -shortlisting,

consolidation of price discovered from

tenders, engagement with vendors for price

benchmark, coordination for remote

monitoring workshop, National workshop on

progress review of DISCOMs, review of GIZ

online training materials, etc.,Engaged with EESL to explore

implementation of their Annuity

Business Model for RTS in Chhattisgarh

EESL Business ModelExecuted key activities viz., selection of

implementing agency for OWOSOG initiative,

inception workshop and technical support and

overall coordination to ISA, WB, SBI and MNRE

OSOWOG Inception Workshop

Key Activities : September 2020 till date (1/2)

Developed online training materials for

Bankers and delivered the first online

training to SBI officers in three batches

Online Training

of SBI Officers

on Evaluation of

Rooftop Solar

Projects

Proposals for

Lending

Developed online training materials for

DISCOM officers for carrying out onsite

inspection of installed RTS systems.

Online Training : UHBVN

Other Activities

SECI :

Initiated Demand Aggregation Activities

MSME MP Demand Aggregation Program :

Initiated engagement with MSME

Department for Demand Aggregation for

RTS implementation

Advisory Committee :

Established for guiding on

legacy activitiesNewsletters, Video Snippets, Social

Media Postings, Articles, MP Hospitals

M&O, MSME Outreach, OSOWOG

M&O etc.,

Media&Outreach / REINVEST

Submitted comprehensive progress report

on activities implemented since Aug 2017

till date and shared for Lighthouse Case

Study preparation as well

MoEFCC – Progress Report

Key Activities : September 2020 till date (2/2)

Solarization of E-Mobility :

Initiated activities on solarization of E-

Mobility (Delhi)

Activities till Nov 2021

Overall PMC Coordination

Activities

Prioritization of 5 States for DPC engagement

(delayed-COVID)

OSOWOG

(full swing)

REINVEST 2020

(completed)

Solar City

(on hold)

100% Solarization of Govt. Buildings (on hold other than Data

Room)

Digitization of RTS Processes

NREDC

(preliminary stage / lacks clarity)

SECI Solarization of Govt. Buildings & Consolidated RTS

Portal

(100-150 MW)

MSME CGM

(MSME Ministry)

(Initiated)

Vendor Management Portal

(completed / to explore replication)

Residential RTS WB Line of Credit

(need update from WB)

Policy & Regulatory Activities / Evidence

Based Policy

Knowledge Management

Quality Assurance & Compliance –

MNRE

(initiated)

MSME MP DAP

(initiated)

Any other activities from White Paper / WB / SBI / MNRE

Page 10 14 June 2021

MNRE PHASE – II Capacity AllocationWorld Bank Partner States

20th Aug,2019 – 24th Nov,2020

In MW

Summary

15 States

30 Discoms

445.5 MW Total

State

Capacity

Allocated

(MW)

Capacity

Tendered

(MW)

Chhattisgarh 5 5

Chandigarh 85 3

Haryana 40 15

Delhi 31.5 31.5

Madhya

Pradesh45 45

Odisha 4 4

Rajasthan 45 45

Andhra

Pradesh25 8

State

Capacity

Allocated

(MW)

Capacity

Tendered

(MW)

Jharkhand 60.7 35.7

Bihar 25 25

Meghalaya 70 10

Assam 2 2

Nagaland 4.8 0

Mizoram 1.5 0.5

Manipur 1 1

World Bank Partner States UWP RTS Applications Received Vs Installed Capacity(kW)

as of April/May 2021

Bihar Rajasthan HaryanaMadhyaPradesh

Chandigarh Jharkhand Delhi Assam Odisha Meghalaya Chhattisgarh

No. of applications received 6673 4537 2819 1547 780 508 252 134 90 32 29

Capacity of the systems Installed (kW) 804 19132 14452.3 3248 3209 300 842 0 0 0 171

6673

4537

2819

1547

780 508252

134 90 32 29804 kW

19,132 kW

14,452 kW

3,248 kW

3,209 kW

300 kW842 kW

0 kW 0 kW 0 kW 171 kW0

1000

2000

3000

4000

5000

6000

7000

8000

0

5000

10000

15000

20000

25000

No

. o

f A

pp

licati

on

s

Insta

lled

Cap

acit

y (

kW

)

No. of applications received Capacity of the systems Installed (kW)

Capacity Tendered

230.7 MW

Capacity of

Applications

Received

76.320 MW

Capacity of Systems

Installed

42.158 MW

No. of Applications

Received

17401

Moving Forward with DISCOMs

• Availability of a dedicated IT team for successful

handover of the portal for its smooth operation

• Implementation strategy Post-nCOVID19

• Revised Timelines for ongoing and new capacities

• SOP for subsidy claim with standard timelines

• Business Continuity Plan

• Beyond Tenders – business plan

• Capacity assessment for implementation across segments – Government /

C&I / Residential

• Road Map

o Impact Assessment and Business Models

• Transitioning to Need Based Digitization

o RTS Digital Platform

o Streamlining / Smoothening offline processes

• Consumer outreach - sustaining engagement with clients for assuring vendors

Key Requirements from DISCOMs for MNRE Phase II RTSUWP

DAP

14 June 2021 SUPRABHA Progress Review 13

Leading questions for Discussions

Streamlining release of “Incentives and Subsidies”2

Extension on the deadlines due to nCOVID19 (blanket and DISCOM specific)1

Benchmark Price 3

Efficient methods of tendering4

National level Media & Outreach5

Training of DISCOM Officers6

Concurrent monitoring of performance and quality of Resi GRPV Systems7

Andhra Pradesh

Andhra Pradesh Eastern Power Distribution

SUPRABHA Progress Review 142 June 2021

MNRE Phase-II Capacity Allocation / Implementation Status

0

0

Additional Comments on Allocation / Implementation: Empanelled 16 vendors for the

capacity ranges from 1-10kWp and 3 vendors (2 are same from the 1-10kWp range) for above

10-500kWp RTS systems

Applications Capacity

(MW)

Status: Live

http://onlineapp.apeasternpower.com , tested working fine.

SPIN Integration Status: Integrated

UWP Progress

Sanctioned Capacity (MW) 0

TA Support Needed: Training programme for DISCOM Officials & empanelled

vendors on SPIN portal/ web portal and CFA disbursement

Other Unique Aspects on Aggregation, Marketing etc.,

/ TA Support Request Areas

Deployed :CAPEX

Envisaged : NA

Business Models Deployed or Envisaged

Year 19-20 20-21

Sanctioned

Capacity(MW)

8 (Later

surrendered)

8

Tendered Yes (tender

cancelled due

to court case)

Yes

No. of

Vendors

0 17

Cumulative

Resi-Installed

Capacity(MW)

1.01 2.136

Year 19-20 20-21 21-22

Baseline

Capacity

(MW)

31.828

(As of

Mar-

2019)

48.825

(As of

Mar-

2020)

60.685

(As of

Mar-

2021)

Overall

Installed

Capacity

(MW)

48.825 60.685 61.775

* As of May 2021

MNRE Phase-II Subsidy / Incentive Status

0

0

Subsidy /

Year19-20 20-21

Availed

Advance

No No

Availed 2nd

Instalment

No No

Availed 3rd

Instalment

No No

Incentives/

Year19-20 20-21

Submitted

for

Incentives

Yes No

Availed

Incentives

No No

Additional Comments on Subsidy & Incentives :Submitted all the documents in

connection with Incentive FY2019-20

Additional Comments on Unified Web Portal : 129 kW applications registered in

other than domestic category in web portal

0.129

Andhra Pradesh

Andhra Pradesh Southern Power Distribution

SUPRABHA Progress Review 15

MNRE Phase-II Capacity Allocation / Implementation Status

0

0

Additional Comments on Allocation / Implementation: APSPDCL awaiting approval from

Govt. of AP to implement the scheme.

Applications Capacity

(MW)

Status: To be Initiated

SPIN Integration Status: To be

Initiated

UWP Progress

Sanctioned Capacity (MW) 0

TA Support Needed: -

Other Unique Aspects on Aggregation, Marketing etc.,

/ TA Support Request Areas

Deployed : CAPEX and RESCO

Envisaged : NA

Business Models Deployed or Envisaged

Year 19-20 20-21

Sanctioned

Capacity(MW)

17 0

Tendered No No

No. of

Vendors

0 0

Cumulative

Resi-Installed

Capacity(MW)

0 0

Year 19-20 20-21 21-22

Baseline

Capacity

(MW)

50.57

(As of

Mar-

2019)

77.15

(As of

Mar-

2020)

Overall

Installed

Capacity

(MW)

77.15

* As of May 2021

MNRE Phase-II Subsidy / Incentive Status

0

0

Subsidy /

Year19-20 20-21

Availed

Advance

No No

Availed 2nd

Instalment

No No

Availed 3rd

Instalment

No No

Incentives/

Year19-20 20-21

Submitted for

Incentives

No No

Availed

Incentives

No No

Additional Comments on Subsidy & Incentives :

Additional Comments on Unified Web Portal : At Sept 2020 workshop, MNRE

suggested APEPDCL to share UWP with APSPDCL. This activity is yet to be

initiated.

0

Assam

Assam Power Distribution Company Limited (APDCL)

SUPRABHA Progress Review 16

MNRE Phase-II Capacity Allocation / Implementation Status

0

0

Additional Comments on Allocation / Implementation: COVID-19 has impacted on the deployment

of RTS systems on consumer premises, Timeline extension will be required for implementation.

Applications Capacity

(MW)

Status: http://www.rodalee.com/

SPIN Integration Status: Integrated

UWP Progress

Sanctioned Capacity

(MW) 0.112

TA Support Needed: SUPRABHA may conduct the training Programme for APDCL

Officials and empanelled Vendors.

Other Unique Aspects on Aggregation, Marketing etc.,

/ TA Support Request Areas

Deployed : CAPEX (for Residential)

Envisaged : NA

Business Models Deployed or Envisaged

Year 19-20 20-21

Sanctioned

Capacity(MW)

Nil 2

Tendered NA Yes

No. of Vendors NA 6

Resi-Installed

Capacity(MW)

NA 0

Year 19-20 20-21 21-22

Baseline

Capacity

(MW)

8.9880

(As of

Mar-

2019)

20.446

(As of

Mar-

2020)

29.73

(As of

Mar-

2021)

Overall

Installed

Capacity

(MW)

20.446 29.73 29.73*

* As of May 2021

MNRE Phase-II Subsidy / Incentive Status

0

0

Subsidy / Year 19-20 20-21

Availed Advance NA No

Availed 2nd

Instalment

NA No

Availed 3rd

Instalment

NA No

Incentives/ Year 19-20 20-21

Submitted for

Incentives

Yes No

Availed

Incentives

No No

Additional Comments on Subsidy & Incentives : APDCL had submitted requisition for

Incentive (FY 2019-20) and CFA Disbursement request to MNRE.

Additional Comments on Unified Web Portal : Portal is up and running for

Consumer’s application.

Bihar

North Bihar Power Distribution Company Limited (NBPDCL)

SUPRABHA Progress Review 1714 June 2021

Year 19-20 20-21

Sanctioned

Capacity(MW)2 10

Tendered Yes Yes

No. of

Vendors11

Yet to be

Finalized

Resi-Installed

Capacity(MW)- 0.217

Year 19-20 20-21 21-22

Baseline

Capacity

(MW)

0.679

(As

of Mar-

2019)

3.149

(As

of Mar-

2020)

6.895(As

of Mar-

2021)

Overall

Installed

Capacity

(MW)

3.149 6.895 *

Subsidy /

Year19-

20

20-21

Availed

AdvanceYes No

Availed 2nd

Instalment No No

Availed 3rd

InstalmentNo No

Incentives/

Year19-20 20-21

Submitted for

Incentives No No

Availed

Incentives No No

Additional Comments on Subsidy & Incentives : Request for extension for

submission of incentives submitted to MNRE

MNRE Phase-II Capacity Allocation / Implementation Status

0

0

Additional Comments on Allocation / Implementation: Tender floated and

technical analysis completed for 10 MW allocation. Financial analysis put on hold.

Applications Capacity (MW) 7.18Status: Live (http://solarbihar.bsphcl.co.in/)

SPIN Integration Status: Integrated

UWP Progress

Sanctioned Capacity (MW) 02

Unique Aspects :

State Subsidy available in addition to MNRE Subsidy.

TA Support Needed :-

Other Unique Aspects on Aggregation, Marketing etc.,

/ TA Support Request Areas

Deployed : CAPEX

Envisaged :

Business Models Deployed or Envisaged

* As of Mar 2021

MNRE Phase-II Subsidy / Incentive Status

0

0

Additional Comments on Unified Web Portal : To finalize the new process module

for modifying the UWP.

Bihar

South Bihar Power Distribution Company Limited (SBPDCL)

SUPRABHA Progress Review 1814 June 2021

MNRE Phase-II Capacity Allocation / Implementation Status

0

0

Additional Comments on Allocation / Implementation: Tender floated and

technical analysis completed for 10 MW allocation. Financial analysis put on hold.

Applications Capacity (MW) 5.2Status: Live (http://solarbihar.bsphcl.co.in/)

SPIN Integration Status: Integrated

UWP Progress

Sanctioned Capacity (MW) 03

Unique Aspects :

State subsidy available in addition to MNRE subsidy

TA Support Needed :-

Other Unique Aspects on Aggregation, Marketing etc.,

/ TA Support Request Areas

Deployed : CAPEX

Envisaged :

Business Models Deployed or Envisaged

Year 19-20 20-21

Sanctioned

Capacity(MW)3 10

Tendered Yes Yes

No. of

Vendors11

Yet to be

Finalized

Resi-Installed

Capacity(MW)- 0.587

Year 19-20 20-21 21-22

Baseline

Capacity

(MW)

0.689

(As

of Mar-

2019)

2.10

(As

of Mar-

2020)

*

(As of Mar-

2021)

Overall

Installed

Capacity

(MW)

0.689 2.10 7.462

* As of Mar 2021

MNRE Phase-II Subsidy / Incentive Status

0

0

Subsidy /

Year19-

20

20-21

Availed

AdvanceYes

No

Availed 2nd

Instalment No No

Availed 3rd

InstalmentNo No

Incentives/

Year19-20 20-21

Submitted for

Incentives No No

Availed

Incentives No No

Additional Comments on Subsidy & Incentives : Request for extension for

submission of incentives submitted to MNRE

Additional Comments on Unified Web Portal : Finalized the new process module

for modifying the UWP.

ChandigarhCREST

SUPRABHA Progress Review19

Chhattisgarh

Chhattisgarh State Power Distribution Company Limited

20

Delhi

BRPL

SUPRABHA Progress Review 2114 June 2021

MNRE Phase-II Capacity Allocation / Implementation Status

0

0

Additional Comments on Allocation / Implementation:

Applications Capacity (MW) 1.34Status: Live (http://solarbses.com)

SPIN Integration Status: Integrated

UWP Progress

Sanctioned Capacity (MW) 1.32

Other Unique Aspects on Aggregation, Marketing etc.,

/ TA Support Request Areas

Deployed : CAPEX and RESCO; GNM & VNM

Envisaged : Utility anchored RESCO model (Hybrid PPA Model)

Business Models Deployed or Envisaged

Year 19-20 20-21

Sanctioned

Capacity(MW)

10 NA

Tendered Yes No

No. of Unique

Vendors

30 NA

Resi-Installed

Capacity(MW)

NA 0.512

Year 19-20 20-21 21-22

Baseline

Capacity

(MW)

44.43

(As of

Mar 19)

63.98

(As of

Mar 20)

80.38

(As of Mar

21)

Overall

Installed

Capacity

(MW)

63.98 80.38 81.85*

* As of May 2021

MNRE Phase-II Subsidy / Incentive Status

0

0

Subsidy /

Year19-20 20-21

Availed

Advance

No* No

Availed 2nd

Instalment

No No

Availed 3rd

Instalment

No No

Incentives/

Year19-20 20-21

Submitted

for

Incentives

Yes Yes

Availed

Incentives

No No

Additional Comments on Subsidy & Incentives: : The requests for advance

subsidy and incentives are already submitted to MNRE. Yet to receive the same.

Additional Comments on Unified Web Portal :

Unique Aspects TA Support Needed

TA support may be provided in checking the

compliances in line with tender requirements

for disbursal of CFA to empanelled vendors.

14 June 2021 SUPRABHA Progress Review 22

Delhi

BYPL

14 June 2021 SUPRABHA Progress Review 23

TPDDL

Delhi

Haryana

Uttar Haryana Bijli Vitran Nigam (UHBVN)

SUPRABHA Progress Review 24

14 June 2021

MNRE Phase-II Capacity Allocation / Implementation Status

0

0

Additional Comments on Allocation / Implementation:

Applications Capacity (MW) 4.94

Status: Launchedsolarconnection.uhbvn.org.in

SPIN Integration Status:

Fully Integrated

UWP Progress

Sanctioned Capacity (MW) 4.27

TA Support Needed :-

Training of DISCOM officers for (a)Inspection of RTS systems and (b)Subsidy disbursement

Unique Aspects :-

Other Unique Aspects on Aggregation, Marketing etc.,

/ TA Support Request Areas

Deployed : Net-Metering (CAPEX)

Envisaged : N.A

Business Models Deployed or Envisaged

Year 19-20 20-21

Sanctioned

Capacity(MW)5.0 10

Tendered Yes No

No. of Vendors 9 -

Resi-Installed

Capacity(MW)3.90 -

Year 19-20 20-21 21-22

Baseline

Capacity (MW)

32.02(As

of Mar-

2019)

77.45(As

of Mar-

2020)

120.04(As

of Mar-

2021)

Overall

Installed

Capacity (MW)

77.45 120.04 *

* As of May 2021

MNRE Phase-II Subsidy / Incentive Status

0

0

Subsidy / Year 19-20 20-21

Availed

AdvanceYes

-

Availed 2nd

Instalment No -

Availed 3rd

InstalmentNo -

Incentives/ Year 19-20 20-21

Submitted for

IncentivesYes No

Availed

IncentivesNo No

Additional Comments on Subsidy & Incentives :

Additional Comments on Unified Web Portal :

Haryana

Dakshin Haryana Bijli Vitran Nigam (DHBVN)

SUPRABHA Progress Review 25

MNRE Phase-II Capacity Allocation / Implementation Status

0

0

Additional Comments on Allocation / Implementation:

Applications Capacity (MW) 30.55

Status: Launched

esolarconn.dhbvn.org.in

SPIN Integration Status:

Fully Integrated

UWP Progress

Sanctioned Capacity (MW) 27.04

Unique Aspects TA Support Needed

Other Unique Aspects on Aggregation, Marketing etc.,

/ TA Support Request Areas

Deployed : Net-Metering (CAPEX)

Envisaged : N.A

Business Models Deployed or Envisaged

Year 19-20 20-21

Sanctioned

Capacity(MW)10.0 15.0

Tendered Yes No

No. of Vendors 17 -

Resi-Installed

Capacity(MW)10.55 -

Year 19-20 20-21 21-22

Baseline

Capacity (MW)

43.37(As

of Mar-

2019)

165.72(As

of Mar-

2020)

213.80(As

of Mar-

2021)

Overall

Installed

Capacity (MW)

165.72 213.80 222.57*

* As of May 2021

MNRE Phase-II Subsidy / Incentive Status

0

0

Subsidy / Year 19-20 20-21

Availed

AdvanceYes

-

Availed 2nd

Instalment No -

Availed 3rd

InstalmentNo -

Incentives/ Year 19-20 20-21

Submitted for

IncentivesNo No

Availed

IncentivesNo No

Additional Comments on Subsidy & Incentives :

Additional Comments on Unified Web Portal :

14 June 2021

14 June 2021 SUPRABHA Progress Review 26

Jharkhand

Jharkhand Bijli Vitran Nigam Ltd. (JBVNL)

SUPRABHA Progress Review 26

14 June 2021

MNRE Phase-II Capacity Allocation / Implementation Status

0

0

Additional Comments on Allocation / Implementation: Floated the 25MW RESCO residential (Gross

metering), Bid Submission deadline is extended due to COVID lockdown.

Applications Capacity (MW) 3.504Status: Live (https://suvidha.jbvnl.co.in/ )

SPIN Integration Status: Integrated

UWP Progress

Sanctioned Capacity (MW) 0.470

Unique Aspects: JBVNL engaged with MP and MLAs for better outreach amongst the consumers on

RTS adoption.

TA Support Needed1. Need training for ( a) sub-divisional officials on the use of UWP and (b) MNRE Phase II Program and

its process flow.

2. Need TA support for Net-billing software development and integration with current billing software.

3. Need TA for the implementation of 25MW RESCO tender.

Other Unique Aspects on Aggregation, Marketing etc.,

/ TA Support Request Areas

Deployed : 1. CAPEX Model

2.RESCO( gross metering) model based residential RTS tender launched.

Envisaged : NA

Business Models Deployed or Envisaged

Year 19-20 20-21

Sanctioned

Capacity(MW)

10 50

Tendered Yes Yes (25MW)

No. of Vendors 11 -

Resi-Installed

Capacity(MW)

0.300 -

Year 19-20 20-21 21-22

Baseline

Capacity

(MW)

19.750(A

s of Mar-

2019)

24.949(A

s of Mar-

2020)

25.249(A

s of Mar-

2021)

Overall

Installed

Capacity

(MW)

24.949 25.249 25.249

*

* As of May 2021

Subsidy /

Year19-20 20-21

Availed

Advance

No No

Availed 2nd

Instalment

No No

Availed 3rd

Instalment

No No

Incentives/

Year19-20 20-21

Submitted for

Incentives

Yes No

Availed

Incentives

No No

Additional Comments on Subsidy & Incentives :

Additional Comments on Unified Web Portal :

MNRE Phase-II Subsidy / Incentive Status

0

0

Jharkhand

TATA STEEL Utilities and Infrastructure Services Ltd

SUPRABHA Progress Review 27

14 June 2021

MNRE Phase-II Capacity Allocation / Implementation Status

0

0

Additional Comments on Allocation / Implementation:

Slow progress in domestic sector due to already existing low domestic tariff

Applications Capacity (MW) 0.0

Status: Live (https://services.tatasteel.co.in/rts/Login.aspx)

SPIN Integration Status: Integrated

UWP Progress

Sanctioned Capacity (MW) 0.0

Unique Aspects:

TA Support Needed: Assistance required in creating consumer awareness and explaining benefits to low domestic

tariff area.

Other Unique Aspects on Aggregation, Marketing etc.,

/ TA Support Request Areas

Deployed :CAPEX Model

Envisaged :

Business Models Deployed or Envisaged

Year 19-20 20-21

Sanctioned

Capacity(MW)

0.100 NA

Tendered No No

No. of Vendors 12 NA

Resi-Installed

Capacity(MW)

- NA

Year 19-20 20-21 21-22

Baseline

Capacity

(MW)

0.135(

As of

Mar-

2019)

1.481

(As of

Mar-

2020)

2.041

(As of

Mar-

2021)

Overall

Installed

Capacity

(MW)

1.481 2.041 2.041*

* As of May 2021

MNRE Phase-II Subsidy / Incentive Status

0

0

Subsidy /

Year19-20 20-21

Availed

Advance

No No

Availed 2nd

Instalment

No No

Availed 3rd

Instalment

No No

Incentives/

Year19-20 20-21

Submitted

for

Incentives

Yes Yes

Availed

Incentives

No No

Additional Comments on Subsidy & Incentives :

Additional Comments on Unified Web Portal :

Jharkhand

TATA Steel Ltd.

SUPRABHA Progress Review 28

14 June 2021

Year 19-20 20-21

Sanctioned

Capacity(MW)

0.600 NA

Tendered No No

No. of

Vendors

12 NA

Resi-Installed

Capacity(MW)

0.013

Year 19-20 20-21 21-22

Baseline

Capacity

(MW)

0.548(

As of

Mar-

2019)

5.035(

As of

Mar-

2020)

7.267

(As of

Mar-

2021)

Overall

Installed

Capacity

(MW)

5.035 7.267 7.267*

* As of May 2021

MNRE Phase-II Capacity Allocation / Implementation Status

0

Additional Comments on Allocation / Implementation:

Slow progress in domestic sector due to already existing low domestic tariff

Applications Capacity (MW) 0.013

Status: Live

(https://services.tatasteel.co.in/rts/Login.aspx) SPIN

Integration Status: Integrated

UWP Progress

Sanctioned Capacity (MW) 0.013

Unique Aspects:

TA Support Needed: 1.Assistance required in creating consumer awareness and explaining benefits to

low domestic tariff area.

Other Unique Aspects on Aggregation, Marketing etc.,

/ TA Support Request Areas

Deployed :CAPEX Model

Envisaged : NA

Business Models Deployed or Envisaged

MNRE Phase-II Subsidy / Incentive Status

0

0

Subsidy /

Year19-20 20-21

Availed

Advance

No No

Availed 2nd

Instalment

No No

Availed 3rd

Instalment

No No

Incentives/ Year 19-20 20-21

Submitted for

Incentives

Yes Yes

Availed

Incentives

No No

Additional Comments on Subsidy & Incentives :

Additional Comments on Unified Web Portal :

* As of May 2021

Madhya Pradesh

Madhya Pradesh Madhya Kshetra Vidyut Vitaran Co. Ltd (MPCZ)

SUPRABHA Progress Review 29

Madhya Pradesh

Madhya Pradesh Poorv Kshetra Vidyut Vitaran Co. Ltd (MPEZ)

SUPRABHA Progress Review 30

Madhya Pradesh Paschim Kshetra Vidyut Vitaran Co. Ltd (MPWZ)

SUPRABHA Progress Review 31

Madhya Pradesh

Manipur

Manipur State Power Distribution Company Limited (MSPDCL)

SUPRABHA Progress Review 3214 June 2021

MNRE Phase-II Capacity Allocation / Implementation Status

0

0

Additional Comments on Allocation / Implementation: MSPDCL will seek the

timeline extension on the grounds of COVID-19 pandemic and subsequent lockdown

imposed by the State Government.

Applications Capacity (MW) 0.059Status: https://solar.mspdcl.info/

SPIN Integration Status: Integrated

UWP Progress

Sanctioned Capacity (MW) 0.059

TA Support Needed: SUPRABHA may conduct the training Programme for MSPDCL

Officials and empanelled Vendors for early deployment of Systems.

Other Unique Aspects on Aggregation, Marketing etc.,

/ TA Support Request Areas

Deployed : RESCO (for Government) and CAPEX (for Residential)

Envisaged : NA

Business Models Deployed or Envisaged

Year 20-21

Sanctioned

Capacity(MW)

1

Tendered Yes

No. of Vendors 12

Resi-Installed

Capacity(MW)

Year 19-20 20-21 21-22

Baseline

Capacity

(MW)

1.882

(As of

March

2019)

4.765

(As

of Marc

h 2020)

4.765

(As

of Marc

h 2021)

Overall

Installed

Capacity

(MW)

4.765 4.765 4.765

* As of May 2021

MNRE Phase-II Subsidy / Incentive Status

0

0

Subsidy /

Year19-20 20-21

Availed

Advance

No NA

Availed 2nd

Instalment

No NA

Availed 3rd

Instalment

No NA

Incentives/

Year19-20 20-21

Submitted

for

Incentives

Yes No

Availed

Incentives

No No

Additional Comments on Subsidy & Incentives : MSPDCL had submitted

requisition for Incentive (FY 2019-20), Advance CFA release request is yet to be

submitted to MNRE.

Additional Comments on Unified Web Portal : Portal is up and running for

Consumer’s application.

MeghalayaMeghalaya Power Distribution Corporation Limited (MePDCL)

SUPRABHA Progress Review 3314 June 2021

MNRE Phase-II Capacity Allocation / Implementation Status

0

0

Additional Comments on Allocation / Implementation: MePDCL has tendered 10

MWp Phase-II RTS Capacity, 60 MWp Tender Document is prepared and ready to float.

Applications Capacity (MW) 2187

Status: https://meghsolar.meghalaya.gov.in/

SPIN Integration Status: Integrated

UWP Progress

Sanctioned Capacity (MW) 0

Unique Aspects TA Support Needed1. Rent-a-Roof Model for Residential Sector 1. Training Programme for AEE/EEs on RTS

2. Utility Owned Business Model 2. Training Programme on UWP Portal.

Other Unique Aspects on Aggregation, Marketing etc.,

/ Technical Assistance (TA) Support Request Areas

Deployed: RESCO (for Government Departments) and CAPEX Model (Residential

Sector)

Envisaged: Rent-a-Roof Model for Residential Sector

Business Models Deployed or Envisaged

Year 19-20 20-21

Sanctioned

Capacity(MW)

70 Nil

Tendered Yes No

No. of

Vendors

7 Nil

Resi-Installed

Capacity(MW)

Nil Nil

Year 19-20 20-21 21-22

Baseline

Capacity

(MW)

0.006

(As

of Marc

h 2019)

0.198

(As

of Marc

h 2020)

0.198

(As

of Marc

h 2021)

Overall

Installed

Capacity

(MW)

0.006 0.198 0.198*

* As of May 2021

MNRE Phase-II Subsidy / Incentive Status

0

0

Subsidy /

Year19-20 20-21

Availed

Advance

No NA

Availed 2nd

Instalment

No NA

Availed 3rd

Instalment

No NA

Incentives/

Year19-20 20-21

Submitted

for

Incentives

Yes No

Availed

Incentives

No No

Additional Comments on Subsidy & Incentives : MePDCL has no progress for the

FY 2020-21, so may not be able to submit the incentive disbursement request for the

FY 2020-21.

Additional Comments on Unified Web Portal : MePDCL has desired a

demonstration and training programme for the field officials.

Mizoram

Power & Electricity Department

SUPRABHA Progress Review 3414 June 2021

MNRE Phase-II Capacity Allocation / Implementation Status

0

0

Additional Comments on Allocation / Implementation:

Applications Capacity (MW) 0.015Status: Under Development (Tentative by

20.06.2021)

SPIN Integration Status: Under

Development (Tentative by 31.06.2021)

UWP Progress

Sanctioned Capacity (MW) 0

Unique Aspects: P&E Department has initiated Media Outreach activity through electricity

bill.

TA Support Needed: SUPRABHA may provide training to P&E Department Official and

empanelled vendors.

Other Unique Aspects on Aggregation, Marketing etc.,

/ TA Support Request Areas

Deployed : CAPEX (for Non-Government) and RESCO (for Government)

Envisaged : NA

Business Models Deployed or Envisaged

Year 19-20 20-21

Sanctioned

Capacity(MW)

0.500 1.0

Tendered Yes No

No. of

Vendors

3 NA

Resi-Installed

Capacity(MW)

0 0

Year 19-20 20-21 21-22

Baseline

Capacity

(MW)

0.498

(As

of Marc

h 2019)

1.365

(As

of Marc

h 2020)

1.365

(As

of Marc

h 2021)

Overall

Installed

Capacity

(MW)

0.498 1.365 1.365

*

* As of May 2021

MNRE Phase-II Subsidy / Incentive Status

0

0

Subsidy /

Year19-20 20-21

Availed

Advance

No No

Availed 2nd

Instalment

No No

Availed 3rd

Instalment

No No

Incentives/

Year19-20 20-21

Submitted

for

Incentives

No No

Availed

Incentives

No No

Additional Comments on Subsidy & Incentives :

Additional Comments on Unified Web Portal : Portal has been migrated on Server,

there was some challenge on software compatibility, which has been successfully

resolved.

Nagaland

Department of Power, Nagaland

SUPRABHA Progress Review 3514 June 2021

MNRE Phase-II Capacity Allocation / Implementation Status

0

0

Additional Comments on Allocation / Implementation:MNRE had sanctioned cumulative 4.8 MWp, Entire Tender Capacity will be tendered post

concurrence and approval of Department of Power.

Applications Capacity (MW) 0Status: To be Initiated (Subject to the

concurrence of Department)

SPIN Integration Status: To be

Integrated (subject to the concurrence of

Implementation of Department)

UWP Progress

Sanctioned Capacity (MW) 0

TA Support Needed: SUPRABHA may support in Bid Management Activities and Unified

Web Portal Development for Rooftop Solar Application. There Assistance may also be

required in Media Outreach activities.

Other Unique Aspects on Aggregation, Marketing etc.,

/ TA Support Request Areas

Deployed : RESCO and CAPEX (in General)

Envisaged : NA

Business Models Deployed or Envisaged

Year 19-20 20-21

Sanctioned

Capacity(MW)

1 3.8

Tendered No No

No. of

Vendors

NA NA

Resi-Installed

Capacity(MW)

Year 19-20 20-21 21-22

Baseline

Capacity

(MW)

Overall

Installed

Capacity

(MW)

*

* As of May 2021

MNRE Phase-II Subsidy / Incentive Status

0

0

Subsidy /

Year19-20 20-21

Availed

Advance

No No

Availed 2nd

Instalment

No No

Availed 3rd

Instalment

No No

Incentives/

Year19-20 20-21

Submitted

for

Incentives

No No

Availed

Incentives

No No

Additional Comments on Subsidy & Incentives :

Additional Comments on Unified Web Portal :Unified Web Portal (UWP) is yet to be initiated, concurrence and approval from Department of

Power is yet to be provided.

14 June 2021 36

Odisha

TP Central Odisha Distribution Limited (TPCODL)

SUPRABHA Progress Review 36

Additional Comments on Allocation / Implementation: 1. Vendor Empanelment finalization by OREDA was completed on 29/01/2021. 2. Due to pandemic condition implementation is getting delayed.

Deployed : CAPEX Model

Envisaged : NA

Business Models Deployed or Envisaged

Year 19-20 20-21

Sanctioned

Capacity(MW)

1 Nil

Tendered Yes(Execu

ted by OR

EDA)

No

No. of Vendors 7 -

Resi-Installed

Capacity(MW)

Nil Nil

Year 19-20 20-21 21-22

Baseline

Capacity

(MW)

13.293(A

s of Mar-

2019)

14.674(A

s of Mar-

2020)

17.601(As

of Mar-

2021)

Overall

Installed

Capacity

(MW)

14.674 17.601 17.601*

* As of May 2021

Subsidy /

Year19-20 20-21

Availed

Advance

No -

Availed 2nd

Instalment

No No

Availed 3rd

Instalment

No No

Incentives/

Year19-20 20-21

Submitted

for

Incentives

Yes No

Availed

Incentives

No No

MNRE Phase-II Capacity Allocation / Implementation Status

MNRE Phase-II Subsidy / Incentive Status

Additional Comments on Subsidy & Incentives :

Applications Capacity (MW) 0.581Status: Live

(http://portal.tpcentralodisha.com:8080/TpcodlSolarRegistrati

on/ )

SPIN Integration Status: To be Integrated (to

be integrated by July 2021)

UWP Progress

Sanctioned Capacity (MW) 0

Unique Aspects :

TA Support Needed:• Knowledge and learnings from other DISCOMS needs to be shared.

• Training of DISCOM officers (Inspection of RTS systems and Subsidy disbursement)

Other Unique Aspects on Aggregation, Marketing etc.,

/ TA Support Request Areas

Additional Comments on Unified Web Portal :

Odisha

TP Northern Odisha Distribution Limited (TPNODL)

SUPRABHA Progress Review 3714 June 2021

Year 19-20 20-21

Sanctioned

Capacity(MW)

1 MW NIL

Tendered Yes(Exec

uted by O

REDA)

No

No. of Vendors 8

Resi-Installed

Capacity(MW)

NIL NIL

Year 19-20 20-21 21-22

Baseline

Capacity

(MW)

0.367(As

of Mar-

2019)

0.613(As

of Mar-

2020)

0.675(As

of Mar-

2021)

Overall

Installed

Capacity

(MW)

0.613 0.676 Nil

* As of May 2021

MNRE Phase-II Capacity Allocation / Implementation Status

0

0

Additional Comments on Allocation / Implementation: The vendors empanelment process is under progress.

Delayed due to privatization of DISCOM. To be complete by end of June 2021.

Applications Capacity (MW) 0.16

Status: Live (http://rts.odisha.gov.in/ )

SPIN Integration Status: Integrated

UWP Progress

Sanctioned Capacity (MW) 0

Unique Aspects :-

TA Support Needed:-

1. Need training for ( a) sub-divisional officials on the use of UWP and (b) MNRE Phase II Program and its process

flow.

2. Need a dedicated state level nodal officer from SUPRABHA TA Program

Other Unique Aspects on Aggregation, Marketing etc.,

/ TA Support Request Areas

Deployed : CAPEX Model

Envisaged : NA

Business Models Deployed or Envisaged

MNRE Phase-II Subsidy / Incentive Status

0

0

Subsidy /

Year19-20 20-21

Availed

Advance

No No

Availed 2nd

Instalment

No No

Availed 3rd

Instalment

No No

Incentives/

Year19-20 20-21

Submitted

for

Incentives

No No

Availed

Incentives

No No

Additional Comments on Subsidy & Incentives :

Additional Comments on Unified Web Portal :

Odisha

TP Southern Odisha Distribution Limited (TPSODL)

SUPRABHA Progress Review 38

Year 19-20 20-21

Sanctioned

Capacity(MW)

1 No

Tendered Yes(Executed

by OREDA)No

No. of Vendors 7 Nos No

Resi-Installed

Capacity(MW)

Nil Nil

Year 19-20 20-21 21-22

Baseline

Capacity

(MW)

0.519(As

of Mar-

2019)

0.850(As

of Mar-

2020)…5

0.947(As

of Mar-

2021)

Overall

Installed

Capacity

(MW)

0.850 0.947 0.947*

* As of May 2021

MNRE Phase-II Capacity Allocation / Implementation Status

0

0

Additional Comments on Allocation / Implementation: The vendors empanelment process is under

progress. Delayed due to privatization of DISCOM. To be complete by end of June 2021.

Applications Capacity (MW) 0

Status: Live (http://rts.odisha.gov.in/ )

SPIN Integration Status: Integrated

UWP Progress

Sanctioned Capacity (MW) 0

Unique Aspects:-

TA Support Needed:-

1. Need training for ( a) sub-divisional officials on the use of UWP and (b) MNRE Phase II

Program and its process flow.

Other Unique Aspects on Aggregation, Marketing etc.,

/ TA Support Request Areas

Deployed : CAPEX Model

Envisaged : NA

Business Models Deployed or Envisaged

MNRE Phase-II Subsidy / Incentive Status

0

0

Subsidy /

Year19-20 20-21

Availed

Advance

No No

Availed 2nd

Instalment

No No

Availed 3rd

Instalment

No No

Incentives/

Year19-20 20-21

Submitted

for

Incentives

No No

Availed

Incentives

No No

Additional Comments on Subsidy & Incentives :

Additional Comments on Unified Web Portal :Required a common login i.d. at H.Q. level to track online

application request status.

Odisha

TP Western Odisha Distribution Limited (TPWODL)

SUPRABHA Progress Review 39

Year 19-20 20-21

Sanctioned

Capacity(MW)

1 -

Tendered Yes

(Executed

by OREDA)

-

No. of

Vendors

8 -

Resi-Installed

Capacity(MW)

- --

Year 19-20 20-21 21-22

Baseline

Capacity

(MW)

0.835(As

of Mar-

2019)

0.952(As

of Mar-

2020) `

NIL

Overall

Installed

Capacity

(MW)

0.952 NIL Nil*

Subsidy /

Year19-20 20-21

Availed

Advance

No No

Availed 2nd

Instalment

N0 No

Availed 3rd

Instalment

No No

Incentives/

Year19-20 20-21

Submitted

for

Incentives

No No

Availed

Incentives

No No

MNRE Phase-II Capacity Allocation / Implementation Status

0

Additional Comments on Allocation / Implementation: The vendors empanelment process is under

progress. Delayed due to privatization of DISCOM. To be complete by end of June 2021.

Applications Capacity (MW) 1.25

Status: Live (http://rts.odisha.gov.in/ )

SPIN Integration Status: Integrated

UWP Progress

Sanctioned Capacity (MW) 0

Unique Aspects :-TA Support Needed:- 1. Need training for ( a) sub-divisional officials on the use of UWP and

(b) MNRE Phase II Program and its process flow.

2. Need a dedicated state level nodal officer from SUPRABHA TA Program.

Other Unique Aspects on Aggregation, Marketing etc.,

/ TA Support Request Areas

Deployed : CAPEX Model

Envisaged : NA

Business Models Deployed or Envisaged

* As of May 2021

MNRE Phase-II Subsidy / Incentive Status

0

0

Additional Comments on Subsidy & Incentives :

Additional Comments on Unified Web Portal : Required a common login i.d. at H.Q. level to track online

application request status.

Rajasthan

AVVNL

SUPRABHA Progress Review 40

Rajasthan

JVVNL

SUPRABHA Progress Review 41

Rajasthan

JdVVNL

SUPRABHA Progress Review 42

Sikkim

Energy & Power Department, Government of Sikkim

SUPRABHA Progress Review 4314 June 2021

MNRE Phase-II Capacity Allocation / Implementation Status

0

0

Additional Comments on Allocation / Implementation: Energy & Power Department had

surrendered allocated 5 MWp Sanctioned capacity, fresh demand of 2 MWp had been submitted to

MNRE for Sanction.

Applications Capacity (MW) 0 Status: https://usrp.sikkim.gov.in/

SPIN Integration Status: Integrated

UWP Progress

Sanctioned Capacity (MW) 0

TA Support Needed: SUPRABHA may provide training to E&P Department Official on

demand aggregation.

Other Unique Aspects on Aggregation, Marketing etc.,

/ TA Support Request Areas

Deployed : CAPEX (for Residential) and RESCO (for Government)

Envisaged : NA

Business Models Deployed or Envisaged

Year 19-20 20-21

Sanctioned

Capacity(MW)

5 Nil

Tendered No NA

No. of

Vendors

Nil NA

Resi-Installed

Capacity(MW)

Year 19-20 20-21 21-22

Baseline

Capacity

(MW)

Overall

Installed

Capacity

(MW)

*

* As of May 2021

MNRE Phase-II Subsidy / Incentive Status

0

0

Subsidy /

Year19-20 20-21

Availed

Advance

No No

Availed 2nd

Instalment

No No

Availed 3rd

Instalment

No No

Incentives/

Year19-20 20-21

Submitted

for

Incentives

No No

Availed

Incentives

No No

Additional Comments on Subsidy & Incentives : Energy & Power Department has

surrendered allocated 5 MWp sanctioned capacity and request of CFA does not arise at the

moment.

Additional Comments on Unified Web Portal : Sikkim UWP is up and running,

ready to accept the consumer application for RTS installation.

Tripura

Tripura State Electricity Corporation Limited (TSECL)

SUPRABHA Progress Review 4414 June 2021

MNRE Phase-II Capacity Allocation / Implementation Status

0

0

Additional Comments on Allocation / Implementation: TSECL vide Letter dated

2nd June 2021 has request an allocation of 1 MWp under Phase-II RTS Scheme.

Applications Capacity (MW) 0Status: To be Initiated (Tentatively by

Sept 2021 subject to availability of Server

and Security Audit)

SPIN Integration Status: To be

Integrated (one week from date of Server

Migration)

UWP Progress

Sanctioned Capacity (MW) 0

TA Support Needed: SUPRABHA may support in Bid Management Activities and

Unified Web Portal Development for Rooftop Solar Application. There Assistance may

also be required in Media Outreach activities.

Other Unique Aspects on Aggregation, Marketing etc.,

/ TA Support Request Areas

Deployed : CAPEX and RESCO (in General)

Envisaged : NA

Business Models Deployed or Envisaged

Year 19-20 20-21

Sanctioned

Capacity(MW)

Nil Nil

Tendered NA NA

No. of

Vendors

NA NA

Resi-Installed

Capacity(MW)

0.007 0.022

Year 19-20 20-21 21-22

Baseline

Capacity

(MW)

2.208

(As

of Marc

h 2019)

2.381

(As

of Marc

h 2020)

2.381

(As

of Marc

h 2021)

Overall

Installed

Capacity

(MW)

2.208 2.381 2.381

*

* As of May 2021

MNRE Phase-II Subsidy / Incentive Status

0

0

Subsidy /

Year19-20 20-21

Availed

Advance

NA NA

Availed 2nd

Instalment

NA NA

Availed 3rd

Instalment

NA NA

Incentives/

Year19-20 20-21

Submitted

for

Incentives

No No

Availed

Incentives

No No

Additional Comments on Subsidy & Incentives :

Additional Comments on Unified Web Portal :

Dr. Amit JainEnergy SpecialistEmail: [email protected]

Mani Khurana Senior Energy SpecialistEmail : [email protected]

Nithyanandam Yuvaraj Dinesh BabuTeam Leader, EY Consortium / Senior AdvisorEmail: [email protected]:9560719349

Thank You !

National Workshop on Review of Implementation of RTS Phase II Program

ADB TA Program

June 2021

About the ADB TA Programme

▪ Initiative under the able guidance of the Ministry of New and Renewable Energy (MNRE)▪ Aims to remove identified barriers to large-scale adoption of Rooftop Solar (RTS) through

enhancement of the institutional capacity of DISCOMs and other RTS stakeholders

▪ Review of policies/regulations and development of innovative business models▪ Streamline tendering and applications for RTPV systems▪ Demand aggregation▪ Capacity building▪ Marketing and Outreach▪ Development of DISCOM specific rooftop solar portals

TSSPDCL, TSNPDCL

TELANGANA

A&N ED

ANDAMAN

KSEBL

KERALA

PED

PUDUCHERRY

TANGEDCO, TEDA

TAMIL NADU

BESCOM,CESCOM, HESCOM, GESCOM, MESCOM

KARNATAKA

EDG, GEDA

GOA

LED, LEDA

LAKSHADWEEP

2

WHAT IS THE ADB TA PROGRAM?

SUPPORT PROVIDED

STATES SUPPORTED

8 STATES / UTs

❑ Tender issued for more than 625 MW SRT capacity, ❑ Deployed 7 USRP, - Ready for deployment : 3 USRP❑ Capacity building to 850+ state officials, ❑ Organized/ Supported 11 bidders meet ❑ Proposed business models across 8 States/ UTs.❑ Conceptualize and implementation of Project

Management Portal for KSEBL

Key Achievements of the ADB TA Programme

▪ 450 MW – Kerala Phase 1 & 2

▪ 5 MW – A&N

▪ 85.6MW – Goa

▪ 50 MW – Karnataka

▪ 30 MW – Puducherry

▪ 5 MW – Tamil Nadu

3

TRAININGS & STUDY TOURS

AWARDED (102 MW)

YET TO BE ISSUED (383 MW)

ISSUED (625 MW)

RO

OFT

OP

SO

LAR

TEN

DER

S

8 STATES / UTs

Developed animation videos, website design and bidders

meet

Supported in implementation of innovative Utility driven

business models

Deployed USRP in Telangana, Karnataka

(BESCOM), Puducherry, A&N, Tamil Nadu and Kerala

▪ GOA: SRT Training (130 Participants)

▪ KERALA – SRT training (150 Participants)

▪ PUDUCHERRY – SRT Training (30 Participants)

▪ TAMIL NADU – SRT Training (150 officials)

▪ TELANGANA – SRT Training (220 officials)

▪ KARNATAKA – SRT Training (175 officials)

▪ KARNATAKA: Study tour on Utility driven business models for SRT to multiple states

▪ KERALA - Study Tour to a Centralised monitoring centre

▪ 96.5MW – Kerala Phase 1 &2

▪ 605KW – Goa ▪ 5 MW – A&N

▪ 1 MW – Goa▪ 60 MW – Kerala RESCO▪ 312 MW – Karnataka▪ 10 MW – Lakshadweep

SUM

MA

RY

Online training on SRT for Telangana Discomofficials

Solar plus storagetender in A&N

Ekiransolar rooftopportal launchedin Kerala

Solarization of Goa University

Snapshots

4

CONTENTS

• About the ADB TA Programme and snapshot of key achievements• Updates from this quarter- This section captures key Programme activities carried out during the quarter • From the archives- Selected past initiatives are highlighted here. • Industry updates- Important updates relevant for the TA Programme covered in this section.

Programme Newsletter- Quarterly

5

*Disclaimer: This is still under development and will be completed in June 2021. 6

Programme Website

*Disclaimer: This is still under development and will be completed in June 2021. 7

Knowledge Products

This is a guide for implementing agencies in solarizing government buildings and provides:

• Methodology to solarize government buildings including feasibility assessment, demand aggregation and tendering.

• Recommendations for effective implementation using case studies

The Guidebook will assist utilities in undertaking Demand Aggregation (DA) program in their licence areas.

• It lists the important parameters that any utility should consider before designing DA program and

• Includes the steps and guidelines on how to undertake DA program.

This Guidebook describes four innovative rooftop solar business models such as

• Utility as a facilitator for the deployment of solar rooftop

• Roof leasing with utility investment• EPC-RESCO hybrid model with partial

stakeholder investment• Utility as master RESCO

TA progress inStates/ UTs

8

Kerala

Kerala State Electricity Board Limited

ADB TA Progress Review9

13 June 2021

MNRE Phase-II Capacity Allocation / Implementation Status

0

0

Additional Comments on Allocation / Implementation: List of Empanelled

Vendors for 200 MW SRPV Capacity will be published upon receipt of SD and

issuance of new benchmark cost by MNRE. (Tentatively in June 2021).

Applications Capacity (MW) 71Status: Developed & Live.

https://ekiran.kseb.in/

SPIN Integration Status: Integrated

UWP Progress

Sanctioned Capacity (MW) 6.6

MNRE TA Programme may exhibit the highlights of subsidy programme

(Advertisements) through regional TV channels to reach the programme among the

ordinary consumers.It is not possible to make other outreach programmes due to

COVID 19 pandemic.

Other Unique Aspects on Aggregation, Marketing etc.,

/ TA Support Request Areas

Deployed: Kerala Model & Consumer Owned Model.

Kerala model – In order to attract low consumption consumers, KSEBL devised a new

business model , wherein the plant cost excluding CFA from MNRE is jointly invested

by consumer and KSEBL. Energy generated from the plant is proportionately shared

based on the investment and consumer requirement.

Business Models Deployed or Envisaged

Year 19-20 20-21

Sanctioned

Capacity(MW)

50 200

Tendered Yes Yes

No. of

Vendors

3 7

Resi-Installed

Capacity(MW)

.088 -

Year 19-20 20-21 21-22

Baseline

Capacity

(MW)

27.96 62.55 113.00

Overall

Installed

Capacity

(MW)

62.55 113.00

* As of May 2021

MNRE Phase-II Subsidy / Incentive Status

0

0

Subsidy /

Year19-20 20-21

Availed

Advance

0

Availed 2nd

Instalment

Nil

Availed 3rd

Instalment

Nil

Incentives/

Year19-20 20-21

Submitted for

Incentives

Re-

submitted

on

19.5.2021

Under

preparatio

n

Availed

Incentives

Nil

Additional Comments on Subsidy & Incentives : Sanctioned Advance CFA for

Rs.10.48 Crores, but not released for want of approval for Utilisation certificates in

respect of previously sanctioned funds to KSEBL.

Additional Comments on Unified Web Portal : Additional Functionalities (migration

of 21000 applications, capturing business model details etc. is presently under

development. Remaining applications will be process upon empanelment of Vendors.

Telangana

Southern Power Distribution Company of Telangana Limited

ADB TA Progress Review 1013 June 2021

MNRE Phase-II Capacity Allocation / Implementation Status

0

0

Additional Comments on Allocation / Implementation: Vendor empanelment for

FY 20-21 allocations of 20 MW completed on 19 December 2020, by TSREDCO

Applications Capacity (MW) 13.5Status: Developed & Livehttps://www.tssouthernpower.com/

http://117.239.151.19:8080/

SPIN Integration Status: Integrated

UWP Progress

Sanctioned Capacity (MW) 13.3

Unique Aspects TA Support Needed

Online capacity building provided to 220 grid engineers.

Other Unique Aspects on Aggregation, Marketing etc.,

/ TA Support Request Areas

Capex: Net metering arrangement with consumer investment.

Business Models Deployed or Envisaged

Year 19-20 20-21

Sanctioned

Capacity(MW)

10.78 20

Tendered Yes Yes

No. of

Vendors

72 78

Resi-Installed

Capacity(MW)

9.15 0.07

Year 19-20 20-21 21-22

Baseline

Capacity

(MW)

70.04 104.29

0

153.08

Overall

Installed

Capacity

(MW)

104.29 153.08 164.84

* As of May 31 2021

MNRE Phase-II Subsidy / Incentive Status

0

0

Subsidy /

Year19-20 20-21

Availed

Advance

Yes Yes

Availed 2nd

Instalment

No No

Availed 3rd

Instalment

No No

Incentives/

Year19-20 20-21

Submitted

for

Incentives

Yes No

Availed

Incentives

No No

Additional Comments on Subsidy & Incentives :

Additional Comments on Unified Web Portal :

Telangana

Nnorthern Power Distribution Company of Telangana Limited

ADB TA Progress Review 1113 June 2021

MNRE Phase-II Capacity Allocation / Implementation Status

0

0

Additional Comments on Allocation / Implementation: Vendor empanelment for

FY 20-21 allocations of 5 MW completed on 19 December 2020, by TSREDCO

Applications Capacity (MW) 1.9Status: Developed & Live

http://210.212.223.83:7001/J2S/j2s/webs

iteLoginUsers.action

SPIN Integration Status: Integrated

UWP Progress

Sanctioned Capacity (MW) 1.8

Unique Aspects TA Support Needed

Other Unique Aspects on Aggregation, Marketing etc.,

/ TA Support Request Areas

Capex: Net metering arrangement with consumer investment.

Business Models Deployed or Envisaged

Year 19-20 20-21

Sanctioned

Capacity(MW)

1.5 5

Tendered Yes Yes

No. of

Vendors

72 78

Resi-Installed

Capacity(MW)

1.082 0.026

Year 19-20 20-21 21-22

Baseline

Capacity

(MW)

5.746 13.602

0

18.798

Overall

Installed

Capacity

(MW)

13.602 18.798 19.245

* As of May 31, 2021

MNRE Phase-II Subsidy / Incentive Status

0

0

Subsidy /

Year19-20 20-21

Availed

Advance

Yes Yes

Availed 2nd

Instalment

No No

Availed 3rd

Instalment

No No

Incentives/

Year19-20 20-21

Submitted

for

Incentives

Yes No

Availed

Incentives

No No

Additional Comments on Subsidy & Incentives :

Additional Comments on Unified Web Portal :

Goa

Electricity Department, Goa & Goa Energy Development Agency

ADB TA Progress Review 1213 June 2021

MNRE Phase-II Capacity Allocation / Implementation Status

0

0

Additional Comments on Allocation / Implementation: Empanelment process is

almost completed. 16 vendors shortlisted. Final list to be issued after vendors submit

SD. Delay in submission of SD due to covid restrictions.

Applications Capacity (MW) 1.5Status: Developed

SPIN Integration Status: To be

Integrated by June 30, 2021.

UWP Progress

Sanctioned Capacity (MW) 0

Unique Aspects TA Support Needed –Yes

• Prepared pamphlet for creating awareness & generating expression of interests.

• Tied up with local channels for creating awareness and propagation.

Other Unique Aspects on Aggregation, Marketing etc.,

/ TA Support Request Areas

Deployed: Consumer Owned Model with Net metering

Business Models Deployed or Envisaged

Year 19-20 20-21

Sanctioned

Capacity(MW)

5 80

Tendered Yes Yes

No. of

Vendors

16

Resi-Installed

Capacity(MW)

0

Year 19-20 20-21 21-22

Baseline

Capacity

(MW)

2.024 6.513

0

13.787

Overall

Installed

Capacity

(MW)

6.513 13.787

* As of May 2021

MNRE Phase-II Subsidy / Incentive Status

0

0

Subsidy /

Year19-20 20-21

Availed

Advance

No No

Availed 2nd

Instalment

No No

Availed 3rd

Instalment

No No

Incentives/

Year19-20 20-21

Submitted

for

Incentives

No No

Availed

Incentives

No No

Additional Comments on Subsidy & Incentives : Advance subsidy will be availed upon finalization of Vendors.

In the process of submitting documents for claiming the incentives.

Additional Comments on Unified Web Portal : Solar Rooftop Portal is developed.

Security Audit is completed. Server is arranged. Deployment of Portal is under

process.

Puducherry

Puducherry Electricity Department

ADB TA Progress Review 1313 June 2021

MNRE Phase-II Capacity Allocation / Implementation Status

0

0

Additional Comments on Allocation / Implementation: Tendering process for 30 MW

capacity almost complete. Finalization of empanelment of vendors is in process.

Applications Capacity (MW) 0Status: Deployed & Live

https://solarrooftop.py.gov.in/

SPIN Integration Status: Integrated

UWP Progress

Sanctioned Capacity (MW) 0

Unique Aspects TA Support Needed

Media publications used to elicit demand

Capacity building workshop conducted for 30 grid engineers

Other Unique Aspects on Aggregation, Marketing etc.,

/ TA Support Request Areas

Capex model deployed for 30 MW capacity (Combined tender for FY 19-

20 and FY 20-21 allocations)

Business Models Deployed or Envisaged

Year 19-20 20-21

Sanctioned

Capacity(MW)

5 MW 25 MW

Tendered Yes Yes

No. of

Vendors

NA NA

Resi-Installed

Capacity(MW)

NA NA

Year 19-20 20-21 21-22

Baseline

Capacity

(MW)

2.3 7.84

0

13.1

Overall

Installed

Capacity

(MW)

7.84 13.1 13.1

* As of May 2021

MNRE Phase-II Subsidy / Incentive Status

0

0

Subsidy /

Year19-20 20-21

Availed

Advance

No No

Availed 2nd

Instalment

No No

Availed 3rd

Instalment

No No

Incentives/

Year19-20 20-21

Submitted

for

Incentives

No No

Availed

Incentives

No No

Additional Comments on Subsidy & Incentives : Same will be availed on

finalization of vendors.

Additional Comments on Unified Web Portal :

Andaman and Nicobar Islands

Andaman and Nicobar Electricity Department

ADB TA Progress Review 1413 June 2021

MNRE Phase-II Capacity Allocation / Implementation Status

0

0

Additional Comments on Allocation / Implementation: Vendor empanelment for 5 MW capacity complete. (Residential: 1 MW, Commercial & Government: 2 MW, and Industrial: 2 MW)

Applications Capacity (MW) 0Status: Deployed & Live

https://usrp.andaman.gov.in/

SPIN Integration Status: Integrated

UWP Progress

Sanctioned Capacity (MW) 0

Unique Aspects TA Support Needed

Demand aggregation of 1000+ government buildings done

Online capacity building workshop conducted for ~30 grid engineers

Reduced electricity tariff for consumers who install solar rooftop

Other Unique Aspects on Aggregation, Marketing etc.,

/ TA Support Request Areas

Capex model with battery storage

Business Models Deployed or Envisaged

Year 19-20 20-21

Sanctioned

Capacity(MW)

1 MW -

Tendered Yes -

No. of

Vendors

1 NA

Resi-Installed

Capacity(MW)

0 NA

Year 19-20 20-21 21-22

Baseline

Capacity

(MW)

4.15 4.15

0

4.15

Overall

Installed

Capacity

(MW)

4.15

0

4.15 4.15

0

* As of May 2021

MNRE Phase-II Subsidy / Incentive Status

0

0

Subsidy /

Year19-20 20-21

Availed

Advance

Yes NA

Availed 2nd

Instalment

No NA

Availed 3rd

Instalment

No NA

Incentives/

Year19-20 20-21

Submitted

for

Incentives

No No

Availed

Incentives

No No

Additional Comments on Subsidy & Incentives : 2nd and 3rd instalments will be

availed post implementation of allocated capacity.

Additional Comments on Unified Web Portal :

Tamil Nadu

Tamil Nadu Generation and Distribution Company Limited

ADB TA Progress Review 1513 June 2021

MNRE Phase-II Capacity Allocation / Implementation Status

0

0

Additional Comments on Allocation / Implementation: TEDA/ TANGEDCO issued

the 5 MW tender on 10 September 2020. Bids are being evaluated and finalized.

Applications Capacity (MW) 0Status: Developed & Live

https://www.tnebltd.gov.in/usrp/

SPIN Integration Status: Integrated

UWP Progress

Sanctioned Capacity (MW) 0

Unique Aspects TA Support Needed

Online capacity building provided to 170+ grid engineers

Other Unique Aspects on Aggregation, Marketing etc.,

/ TA Support Request Areas

Capex: Net metering arrangement with consumer investment

Business Models Deployed or Envisaged

Year 19-20 20-21

Sanctioned

Capacity(MW)

5 MW 50 MW

Tendered Yes -

No. of

Vendors

NA NA

Resi-Installed

Capacity(MW)

NA NA

Year 19-20 20-21 21-22

Baseline

Capacity

(MW)

56.472 76.59

0

107.06

Overall

Installed

Capacity

(MW)

76.59 107.06 107.06

* As of May 2021

MNRE Phase-II Subsidy / Incentive Status

0

0

Subsidy /

Year19-20 20-21

Availed

Advance

No NA

Availed 2nd

Instalment

No NA

Availed 3rd

Instalment

No NA

Incentives/

Year19-20 20-21

Submitted

for

Incentives

Yes Yes

Availed

Incentives

No No

Additional Comments on Subsidy & Incentives :

Additional Comments on Unified Web Portal :

Karnataka

Bangalore Electricity Supply Company Limited

ADB TA Progress Review16

13 June 2021

MNRE Phase-II Capacity Allocation / Implementation Status

0

0

Additional Comments on Allocation / Implementation:

1. Bids opened for 30 MW capacity and KERC approval awaited

2. Approval for implementation of 300MW is requested before KERC and approval is awaited..

Applications Capacity (MW) 3.726Status: Developed & Live

http://srtpv.bescom.org/SRTPV/

SPIN Integration Status: Integrated.

UWP Progress

Sanctioned Capacity (MW) 3.726

1. Awareness created through distribution of pamphlets, paper notifications, SMS,

Facebook and Twitter .

2. Demand Aggregation initiated for implementation of 300 MW.

Other Unique Aspects on Aggregation, Marketing etc.,

/ TA Support Request Areas

Deployed: Net/Gross metering with consumer investment

Business Models Deployed or Envisaged

Year 19-20 20-21

Sanctioned

Capacity(MW)

30 300

Tendered Yes No

No. of

Vendors

-

Resi-Installed

Capacity(MW)

Year 19-20 20-21 21-22

Baseline

Capacity

(MW)

114.6920 136.1421 152.705

Overall

Installed

Capacity

(MW)

136.1421 152.705

* As of May 2021

MNRE Phase-II Subsidy / Incentive Status

0

0

Subsidy /

Year19-20 20-21

Availed

Advance

---- ----

Availed 2nd

Instalment

---- ----

Availed 3rd

Instalment

---- ----

Incentives/

Year19-20 20-21

Submitted for

Incentives Yes No

Availed

IncentivesNo

-------

Additional Comments on Subsidy & Incentives :

Advance subsidy will be availed upon finalization of Vendors.

Additional Comments on Unified Web Portal :

Empanelled Vendor list will be integrated on finalization of Empanelment process.

Karnataka

Gulbarga Electricity Supply Company Ltd.

ADB TA Progress Review17

13 June 2021

MNRE Phase-II Capacity Allocation / Implementation Status

0

0

Additional Comments on Allocation / Implementation: 5 Vendors submitted their

bids. TSC Committee is evaluating the bids.

Applications Capacity (MW) 1.925Status: Beta Version Developed

SPIN Integration Status: To be

integrated by June 2021.

UWP Progress

Sanctioned Capacity (MW) --

Other Unique Aspects on Aggregation, Marketing etc.,

/ TA Support Request Areas

Deployed: Net metering with consumer investment

Business Models Deployed or Envisaged

Year 19-20 20-21

Sanctioned

Capacity(MW)

10 MW

Tendered Yes

No. of

Vendors

Resi-Installed

Capacity(MW)

-

Year 19-20 20-21 21-22

Baseline

Capacity

(MW)

13.473 13.476 15.306

Overall

Installed

Capacity

(MW)

13.476 15.306

* As of May 2021

MNRE Phase-II Subsidy / Incentive Status

0

0

Subsidy /

Year19-20 20-21

Availed

Advance

No No

Availed 2nd

Instalment

No No

Availed 3rd

Instalment

No No

Incentives/

Year19-20 20-21

Submitted for

Incentives

No No

Availed

Incentives

No No

Additional Comments on Subsidy & Incentives :

Prepared Claim for incentives for the FY19-20. Same will be submitted upon approval.

.Advance subsidy will be availed upon finalisation of Vendors.

Additional Comments on Unified Web Portal : Server License has expired.

GESCOM is in the process of renewing license. Subsidy Module will be activated

upon completion of Vendor Empanelment.

Unique Aspects TA Support Needed: yes

1. Circular issued to All Offices

2. Pamphlet/Advertisement issued in News paper

3. Jingles played in FM

4. TA Support needed for making Solar Rooftop Portal Live

Karnataka

Hubli Electricity Supply Company Limited

ADB TA Progress Review18

13 June 2021

MNRE Phase-II Capacity Allocation / Implementation Status

0

0

Additional Comments on Allocation / Implementation:

1) LOA is yet to be issued.

Applications Capacity (MW) -Status: Under Development (June 12,

2021)

SPIN Integration Status: To be

Integrated.

UWP Progress

Sanctioned Capacity (MW) -

Unique Aspects TA Support Needed

Awareness activities has been initiated 1) Technical support from ADB

1) SRTPV campaigning through News TA: Training/ Workshops for

paper, Radio FM, Pamphlets distribution, officials of HESCOM reg

Displaying banner in all HESCOM offices SRTPV phase-II scheme,

and public places has been proposed usage of web portal.

and got approved

2) LOI has been issued for printing

banner and pamphlet

Other Unique Aspects on Aggregation, Marketing etc.,

/ TA Support Request Areas

Deployed: Net metering with consumer investment

Business Models Deployed or Envisaged

Year 19-20 20-21

Sanctioned

Capacity(MW)

20 MW -

Tendered Yes -

No. of

Vendors5 -

Resi-Installed

Capacity(MW)

- -

Year 19-20 20-21 21-22

Baseline

Capacity

(MW)

24.985 32.118 38.759

Overall

Installed

Capacity

(MW)

32.118 38.759 39.298

* As of May 2021

MNRE Phase-II Subsidy / Incentive Status

0

0

Subsidy /

Year19-20 20-21

Availed

AdvanceNo No

Availed 2nd

Instalment No No

Availed 3rd

InstalmentNo No

Incentives/

Year19-20 20-21

Submitted for

IncentivesNo No

Availed

IncentivesNo No

Additional Comments on Subsidy & Incentives : Claim for incentives for the year 19-20 & 20-21 will be submitted shortly.

Advance subsidy will be availed upon finalisation of Vendors.

Additional Comments on Unified Web Portal : HESCOM has shared all IT

requirements with BESCOM IT Team. Customization of Solar Rooftop Portal for

HESCOM is ongoing. Tentative customisation date is June 12, 2021.

Karnataka

Chamundeshwari Electricity Supply Company Ltd.

ADB TA Progress Review19

13 June 2021

MNRE Phase-II Capacity Allocation / Implementation Status

0

0

Additional Comments on Allocation / Implementation: ADB TA Program has

prepared draft RFP document and shared. Tender document is under review with

PQR committee.

Applications Capacity (MW) 0.21Status: Initiated (June 30, 2021)

SPIN Integration Status: To be

Integrated.

UWP Progress

Sanctioned Capacity (MW)

Unique Aspects TA Support Needed

(a) Issue advertisement in Newspaper.

Other Unique Aspects on Aggregation, Marketing etc.,

/ TA Support Request Areas

Envisaged: Net metering with consumer investment

Business Models Deployed or Envisaged

Year 19-20 20-21

Sanctioned

Capacity(MW)

10 -

Tendered Under

Progress

No. of

Vendors

-

Resi-Installed

Capacity(MW)

Year 19-20 20-21 21-22

Baseline

Capacity

(MW)

3.3054 5.971 9.64

Overall

Installed

Capacity

(MW)

5.971 9.64

* As of May 2021

MNRE Phase-II Subsidy / Incentive Status

0

0

Subsidy /

Year19-20 20-21

Availed

Advance

No No

Availed 2nd

Instalment

No No

Availed 3rd

Instalment

No No

Incentives/

Year19-20 20-21

Submitted for

Incentives

Will

submit

Will submit

Availed

Incentives

No No

Additional Comments on Subsidy & Incentives :

Additional Comments on Unified Web Portal : CESC is in the process of

procurement of Server.

Karnataka

Mangalore Electricity Supply Company Ltd.

ADB TA Progress Review20

13 June 2021

MNRE Phase-II Capacity Allocation / Implementation Status

0

0

Additional Comments on Allocation / Implementation: MESCOM has surrender 2

MW capacity to MNRE.

Applications Capacity (MW) --Status: Under Development (June 30,

2021)

SPIN Integration Status: To be

initiated after completion of development.

UWP Progress

Sanctioned Capacity (MW) --

Unique Aspects TA Support Needed

Other Unique Aspects on Aggregation, Marketing etc.,

/ TA Support Request Areas

Envisaged: Net metering with consumer investment

Business Models Deployed or Envisaged

Year 19-20 20-21

Sanctioned

Capacity(MW)

- 2 MW

Tendered No

No. of

Vendors

-

Resi-Installed

Capacity(MW)

-

Year 19-20 20-21 21-22

Baseline

Capacity

(MW)

17.964 26.352 37.882

Overall

Installed

Capacity

(MW)

26.352 37.8820

* As of May 2021

MNRE Phase-II Subsidy / Incentive Status

0

0

Subsidy /

Year19-20 20-21

Availed

Advance

No No

Availed 2nd

Instalment

No No

Availed 3rd

Instalment

No No

Incentives/

Year19-20 20-21

Submitted for

Incentives

No No

Availed

Incentives

No No

Additional Comments on Subsidy & Incentives :

Additional Comments on Unified Web Portal : MESCOM has shared all IT

requirements with BESCOM IT Team. Customization of Solar Rooftop Portal for

MESCOM is ongoing. Tentative customisation date is June 30, 2021.

Lakshadweep

Lakshadweep Electricity Department & Lakshadweep Energy Development Agency

ADB TA Progress Review21

13 June 2021

MNRE Phase-II Capacity Allocation / Implementation Status

0

0

Additional Comments on Allocation / Implementation: ADB TA Program has

prepared draft RFP document for 10 MW of SRPV. LED is in the process of reviewing

and finalising the tender document.

Applications Capacity (MW) --Status: Developed.

SPIN Integration Status: To be

initiated after deployment. (July 2021)

UWP Progress

Sanctioned Capacity (MW) --

Unique Aspects TA Support Needed

Other Unique Aspects on Aggregation, Marketing etc.,

/ TA Support Request Areas

Envisaged: LED is in process of taking approval from Administration of

Lakshadweep for additional subsidy over and above available CFA to

implement rooftop solar in residential consumer category.

Business Models Deployed or Envisaged

Year 19-20 20-21

Sanctioned

Capacity(MW)

2 MW 8 MW

Tendered No No

No. of

Vendors

- -

Resi-Installed

Capacity(MW)

-

Year 19-20 20-21 21-22

Baseline

Capacity

(MW)

- - -

Overall

Installed

Capacity

(MW)

- - -

* As of May 2021

MNRE Phase-II Subsidy / Incentive Status

0

0

Subsidy /

Year19-20 20-21

Availed

Advance

No NO

Availed 2nd

Instalment

No No

Availed 3rd

Instalment

No No

Incentives/

Year19-20 20-21

Submitted for

Incentives

No No

Availed

Incentives

No No

Additional Comments on Subsidy & Incentives :

Additional Comments on Unified Web Portal : Portal is developed. Security Audit is

completed. LED is in the process of arranging server for deployment of USRP.

Thank You

Implemented by

National Workshop on Review of Implementation of Rooftop Solar Phase II Programme12 June 2021

IGEN Solar Technical Assistance Matrix 06/2021

I-RE (2 + 0.95 = 2.95 Mio. €)• GRID INTEGRATION STUDY 1 – capacity of RE with DISCOMS

• GRID INTEGRATION STUDY 2 – grid vervice with RE for DISCOMS

IGEN PVRT 1 (3 Mio. €)

• Capacity Building of min 10,000 people in the solar sector

• 10 policy recommendations

IGSEP RTPV 2 (5 + 1.5 + 2.5+1 = 10 Mio. €)

• Support to discoms

• Unified Single Clearance Window

• Capacity Building Int / Nat

• Study Tours

• IT Support / Digitilization

• Demand Agg in States and Smart Cities

• 1 GW in 5 to 11 States – iSMART

• Innovative business models for sector

• PV Port & Store – concept

• Upskilling and business models for Suyrmitra‘s

• Replacing GenSets – Pilot with Solar and Battery Storage of 100 KWp solar +450

kWh storage IGEN New Innovative Solar (4.9 Mio. €))- Addressing the Food-Water-Energy-Land Nexus

by finding New Solar areas and pilot

demonstration

- Supporting the Indian Goverment with domestic

manufacturing

BMZ

BMU

+ 3 Mio Solar

Recovery

2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024

BMZ

Präsentationstitel hier eintragen21.06.2021

3

http://ismartsolar.in/

•Demand aggregation for rooftop solar in the residential

•Supported by GIZ and MNRE

•Targeting 3500 MW of demand aggregated in 11 states

Demand Aggregation through I-SMART

What is ISMART program?

The Indian Solar Market Aggregation for Rooftops (I-SMART) Program is a GIZ and Ministry of Newand Renewable Energy (MNRE) supported initiative to increase uptake of rooftop solar in theresidential consumer segment.

Creating a pool of volunteer resources to educate and motivate the consumers for rooftop solar adoption

GIZ

Developing targeted content for effective knowledge dissemination and seamless outreach to diverse consumer base

Objectives

Creating a one-stop website for assisting the consumer in rooftop solar adoption journey

Technical Cooperation Supported By

MNRE

Technical Assistance(TA)

EY, AHA Solar will provide the technical assistance for the program

Support DISCOMs in portal development, floating the tender, SOP preparation, training, implementation, claiming subsidy and incentives from MNRE

Gujarat- Application Flow Chart

"Presentation on Subsidy Module of Unified RTPV Portal" for GUVNL; 6 June '21 5

21 June 2021 GIZ Progress Review 6

Surya Gujarat Portal Process Flow Chart

Gujarat

DGVCL

GIZ Progress Review 721 June 2021

MNRE Phase-II Capacity Allocation / Implementation Status

0

0

Additional Comments on Allocation / Implementation: Under the sanction year 2019-20 total 77.84 MW has been submitted to SPIN

Total baseline installed capacity as on 31.03.2019 as per MNRE SPIN was 53.764 MW

Applications Capacity (MW) 163Status: Live from 10 September

2019

http://suryagujarat.guvnl.in/

http://suryagujarat.ahasolar.in/

SPIN Integration Status: Integrated

(Integrated on 26 March 2020)

UWP Progress

Tender Capacity (MW) 193

Unique Aspects TA Support Needed

Other Unique Aspects on Aggregation, Marketing etc.,

/ TA Support Request Areas

Deployed :: Capex

Envisaged :

Business Models Deployed or Envisaged

Year 19-20 20-21

Sanctioned

Capacity(MW)

81 112

Tendered Yes Yes

No. of

Vendors

459 549

Resi-Installed

Capacity(MW)

80.996 36.134

Year 19-20 20-21 21-22

Baseline

Capacity

(MW)

47.186

(Additional to

FY18-19)

Overall

Installed

Capacity

(MW)

100.95 *

* As of May 2021

MNRE Phase-II Subsidy / Incentive Status

0

0

Subsidy /

Year19-20 20-21

Availed

Advance

Yes

Availed 2nd

Instalment

No No

Availed 3rd

Instalment

No No

Incentives/

Year19-20 20-21

Submitted

for

Incentives

Yes No

Availed

Incentives

No No

Additional Comments on Subsidy & Incentives : Partial advance received

Incentive amount of Rs. 14.56 Crs. has been sent for claim for the sanction year 2019-20.

Additional Comments on Unified Web Portal : The data from Unified Web Portal

are being synchronized with MNRE SPIN Portal on a real-time basis

• SURYA – Rath Yatra campaign planhas been prepared for Awareness

• Demand Aggregation portaldeveloped

• DISCOM support from AHASolar teamfor TA placed in DGVCL by GIZ

Gujarat

MGVCL

GIZ Progress Review 821 June 2021

MNRE Phase-II Capacity Allocation / Implementation Status

0

0

Additional Comments on Allocation / Implementation: Under the sanction year 2019-20 total 104.021 MW has been submitted to SPIN

Total baseline installed capacity as on 31.03.2019 as per MNRE SPIN was 68.80 MW

Applications Capacity (MW) 211Status: Live from 10 September

2019

http://suryagujarat.guvnl.in/

http://suryagujarat.ahasolar.in/

SPIN Integration Status: Integrated

(Integrated on 26 March 2020)

UWP Progress

Tender Capacity (MW) 208

Unique Aspects TA Support Needed

Other Unique Aspects on Aggregation, Marketing etc.,

/ TA Support Request Areas

Deployed :: Capex

Envisaged :

Business Models Deployed or Envisaged

Year 19-20 20-21

Sanctioned

Capacity(MW)

106 102

Tendered Yes Yes

No. of

Vendors

459 549

Resi-Installed

Capacity(MW)

106.383 50.842

Year 19-20 20-21 21-22

Baseline

Capacity

(MW)

50.086

(Additional to

FY18-19)

Overall

Installed

Capacity

(MW)

118.89 *

* As of May 2021

MNRE Phase-II Subsidy / Incentive Status

0

0

Subsidy /

Year19-20 20-21

Availed

Advance

Yes Yes

Availed 1st

Instalment

Yes No

Availed 2nd

Instalment

No No

Incentives/

Year19-20 20-21

Submitted

for

Incentives

Yes Yes / No

Availed

Incentives

No Yes / No

Additional Comments on Subsidy & Incentives : Rs. 20 Cr. has been received under 2019-20 scheme and Rs. 25.70 Cr. received as advance of

2020-21 scheme.

Incentive amount of Rs. 14.93 Crs. has been sent for claim for the sanction year 2019-20.

Additional Comments on Unified Web Portal : The data from Unified Web Portal

are being synchronized with MNRE SPIN Portal on a real-time basis

• DISCOM support from AHASolar teamfor TA placed in MGVCL by GIZ

Missed call system to invite consumers toknow about rooftop

Webinar to consumer

Demand Aggregation portal developed

Gujarat

UGVCL

GIZ Progress Review 921 June 2021

MNRE Phase-II Capacity Allocation / Implementation Status

0

0

Additional Comments on Allocation / Implementation: Under the sanction year 2019-20 total 51.006 MW has been submitted to SPIN

Total baseline installed capacity as on 31.03.2019 as per MNRE SPIN was 78.19 MW

Applications Capacity (MW) 107Status: Live from 10 September

2019

http://suryagujarat.guvnl.in/

http://suryagujarat.ahasolar.in/

SPIN Integration Status: Integrated

(Integrated on 26 March 2020)

UWP Progress

Tender Capacity (MW) 142

Unique Aspects TA Support Needed

Other Unique Aspects on Aggregation, Marketing etc.,

/ TA Support Request Areas

Deployed :: Capex

Envisaged :

Business Models Deployed or Envisaged

Year 19-20 20-21

Sanctioned

Capacity(MW)

53 89

Tendered Yes Yes

No. of

Vendors

459 549

Resi-Installed

Capacity(MW)

52.556 25.42

Year 19-20 20-21 21-22

Baseline

Capacity

(MW)

30.67

(Additional to

FY18-19)

Overall

Installed

Capacity

(MW)

108.86 *

* As of May 2021

MNRE Phase-II Subsidy / Incentive Status

0

0

Subsidy /

Year19-20 20-21

Availed

Advance

Yes

Availed 2nd

Instalment

No No

Availed 3rd

Instalment

No No

Incentives/

Year19-20 20-21

Submitted

for

Incentives

Yes No

Availed

Incentives

No No

Additional Comments on Subsidy & Incentives : Partial advance received

Incentive amount of Rs. 7.52 Crs. has been sent for claim for the sanction year 2019-20.

Additional Comments on Unified Web Portal : The data from Unified Web Portal

are being synchronized with MNRE SPIN Portal on a real-time basis

• DISCOM support from AHASolar teamfor TA placed in UGVCL by GIZ

Missed call system to invite consumers to knowabout rooftop

Webinar to consumer

Demand Aggregation portal developed

Gujarat

PGVCL

GIZ Progress Review 1021 June 2021

MNRE Phase-II Capacity Allocation / Implementation Status

0

0

Additional Comments on Allocation / Implementation: Under the sanction year 2019-20 total 117.035 MW has been submitted to SPIN

Total baseline installed capacity as on 31.03.2019 as per MNRE SPIN was 53.296 MW

Applications Capacity (MW) 228Status: Live from 10 September

2019

http://suryagujarat.guvnl.in/

http://suryagujarat.ahasolar.in/

SPIN Integration Status: Integrated

(Integrated on 26 March 2020)

UWP Progress

Tender Capacity (MW) 280

Unique Aspects TA Support Needed

Other Unique Aspects on Aggregation, Marketing etc.,

/ TA Support Request Areas

Deployed :: Capex

Envisaged :

Business Models Deployed or Envisaged

Year 19-20 20-21

Sanctioned

Capacity(MW)

121 159

Tendered Yes Yes

No. of

Vendors

459 549

Resi-Installed

Capacity(MW)

121.068 52.251

Year 19-20 20-21 21-22

Baseline

Capacity

(MW)

41.288

(Additional to

FY18-19)

Overall

Installed

Capacity

(MW)

94.584 *

* As of May 2021

MNRE Phase-II Subsidy / Incentive Status

0

0

Subsidy /

Year19-20 20-21

Availed

Advance

Yes

Availed 2nd

Instalment

No No

Availed 3rd

Instalment

No No

Incentives/

Year19-20 20-21

Submitted

for

Incentives

Yes No

Availed

Incentives

No No

Additional Comments on Subsidy & Incentives : Partial advance received

Incentive amount of Rs. 12 Crs. has been sent for claim for the sanction year 2019-20.

Additional Comments on Unified Web Portal : The data from Unified Web Portal

are being synchronized with MNRE SPIN Portal on a real-time basis

• DISCOM support from AHASolar teamfor TA placed in PGVCL by GIZ

Missed call system to invite consumers to knowabout rooftop

Webinar to consumer

Demand Aggregation portal developed

Gujarat

Torrent Power - Ahmedabad

GIZ Progress Review 1121 June 2021

MNRE Phase-II Capacity Allocation / Implementation Status

0

0

Additional Comments on Allocation / Implementation:Under the sanction year 2019-20 total 60.569 MW has been submitted to SPIN

Total baseline installed capacity as on 31.03.2019 as per MNRE SPIN was 44.925 MW

Applications Capacity (MW) 125Status: Live from 10 September

2019

http://suryagujarat.guvnl.in/

http://suryagujarat.ahasolar.in/

SPIN Integration Status: Integrated

(Integrated on 26 March 2020)

UWP Progress

Tender Capacity (MW) 82

Unique Aspects TA Support Needed

Other Unique Aspects on Aggregation, Marketing etc.,

/ TA Support Request Areas

Deployed :: Capex

Envisaged :

Business Models Deployed or Envisaged

Year 19-20 20-21

Sanctioned

Capacity(MW)

62 20

Tendered Yes Yes

No. of

Vendors

459 549

Resi-Installed

Capacity(MW)

62.942 27.175

Year 19-20 20-21 21-22

Baseline

Capacity

(MW)

25.170

(Additional

to FY18-19)

Overall

Installed

Capacity

(MW)

70.095 *

* As of May 2021

MNRE Phase-II Subsidy / Incentive Status

0

0

Subsidy /

Year19-20 20-21

Availed

Advance

No

Availed 1st

Instalment

Yes No

Availed 2nd

Instalment

No No

Incentives/

Year19-20 20-21

Submitted

for

Incentives

Yes No

Availed

Incentives

No No

Additional Comments on Subsidy & Incentives : Received First Instalments of CFA 7.57 Cr.(4.95 MW) for the year 2019-20

Incentive amount of Rs. 7.04 Cr. has been sent for claim for the sanction year 2019-20.

Additional Comments on Unified Web Portal : The data from Unified Web Portal

are being synchronized with MNRE SPIN Portal on a real-time basis

• DISCOM support from AHASolar teamfor TA placed in TPA by GIZ

Missed call system to invite consumers to knowabout rooftop

Webinar to consumer

Demand Aggregation portal developed

Gujarat

Torrent Power - Surat

GIZ Progress Review 1221 June 2021

MNRE Phase-II Capacity Allocation / Implementation Status

0

0

Additional Comments on Allocation / Implementation: Under the sanction year 2019-20 total 16.644 MW has been submitted to SPIN

Total baseline installed capacity as on 31.03.2019 as per MNRE SPIN was 9.031 MW

Applications Capacity (MW) 31.98Status: Live from 10 September

2019

http://suryagujarat.guvnl.in/

http://suryagujarat.ahasolar.in/

SPIN Integration Status: Integrated

(Integrated on 26 March 2020)

UWP Progress

Tender Capacity (MW) 27

Unique Aspects TA Support Needed

Other Unique Aspects on Aggregation, Marketing etc.,

/ TA Support Request Areas

Deployed :: Capex

Envisaged :

Business Models Deployed or Envisaged

Year 19-20 20-21

Sanctioned

Capacity (MW)

17 10

Tendered Yes Yes

No. of

Vendors

459 549

Resi-Installed

Capacity(MW)

17.144 7.158

Year 19-20 20-21 21-22

Baseline

Capacity

(MW)

6.369

(Additional

to FY18-19)

Overall

Installed

Capacity

(MW)

15.40 *

* As of May 2021

MNRE Phase-II Subsidy / Incentive Status

0

0

Subsidy /

Year19-20 20-21

Availed

Advance

No

Availed 1st

Instalment

Yes No

Availed 2nd

Instalment

No No

Incentives/

Year19-20 20-21

Submitted

for

Incentives

Yes No

Availed

Incentives

No No

Additional Comments on Subsidy & Incentives : Received First instalment of CFA-2.95 Cr. (1.98 MW) for 2019-20.

Claim has been sent for Incentive amount of Rs. 1.88 Crs. For the sanction year 2019-20.

Additional Comments on Unified Web Portal : The data from Unified Web Portal

are being synchronized with MNRE SPIN Portal on a real-time basis

• DISCOM support from AHASolar teamfor TA placed in TPS by GIZ

Missed call system to invite consumers to knowabout rooftop

Webinar to consumer

Demand Aggregation portal developed

PUNJAB (Residential and Non-residential)

Punjab State Power Corporation Limited (PSPCL)

GIZ Progress Review 1321 June 2021

MNRE Phase-II Capacity Allocation / Implementation Status

0

0

Additional Comments on Allocation / Implementation:

Applications Capacity (MW) 253.72Status: Live

https://distribution.pspcl.in/returns/module.

php?to=PSPCLRoofTopSolar

SPIN Integration Status: Integrated

UWP Progress

Sanctioned Capacity (MW) 181.23

Other Unique Aspects on Aggregation, Marketing etc.,

/ TA Support Request Areas

Deployed : CAPEX

Envisaged :

Business Models Deployed or Envisaged

Year 19-20 20-21

Sanctioned

Capacity(MW)

30 50

Tendered Yes Yes

No. of

Vendors

247 11

Resi-Installed

Capacity(MW)

10.052 Nil

Year 19-20 20-21 21-22

Baseline

Capacity

(MW)

44.821 111.573 140.046

Overall

Installed

Capacity

(MW)

111.573 140.046 146.450

*As of May 2021

MNRE Phase-II Subsidy / Incentive Status

0

0

Subsidy /

Year19-20 20-21

Availed

Advance

Yes No

Availed 2nd

Instalment

No No

Availed 3rd

Instalment

No No

Incentives/

Year19-20 20-21

Submitted

for

Incentives

No No

Availed

Incentives

No No

Additional Comments on Subsidy & Incentives : Half advance subsidy for 19-20

released

Additional Comments on Unified Web Portal : NA

Unique Aspects TA Support Needed

DISCOM coordinator is placed in Punjab

Uttar Pradesh

MVVNL

SUPRABHA Progress Review 1421 June 2021

MNRE Phase-II Capacity Allocation / Implementation Status

0

0

Additional Comments on Allocation / Implementation:

Applications Capacity (MW) 16.92Status: Live (upnedasolarrooftopportal.com)

SPIN Integration Status: Integrated

UWP Progress

Sanctioned Capacity (MW) 10.77

TA Support Needed

SOP for implementation and modification in UPNEDA portal

Other Unique Aspects on Aggregation, Marketing etc.,

/ TA Support Request Areas

Deployed: CAPEX

Envisaged:

Business Models Deployed or Envisaged

Year 19-20 20-21

Sanctioned

Capacity(MW)

19

Tendered Yes (By

UPNEDA)No

No. of

Vendors

71

Resi-Installed

Capacity(MW)

8.47

Year 19-20 20-21 21-22

Baseline

Capacity

(MW)

57.64 68.50 76.91

Overall

Installed

Capacity

(MW)

68.50 76.91 77.97*

* As of May 2021

MNRE Phase-II Subsidy / Incentive Status

0

0

Subsidy /

Year19-20 20-21

Availed

Advance

Yes No

Availed 2nd

Instalment

No No

Availed 3rd

Instalment

No No

Incentives/

Year19-20 20-21

Submitted

for

Incentives

No No

Availed

Incentives

No No

Additional Comments on Subsidy & Incentives :

Additional Comments on Unified Web Portal :

Uttar Pradesh

PVVNL

SUPRABHA Progress Review 1521 June 2021

MNRE Phase-II Capacity Allocation / Implementation Status

0

0

Additional Comments on Allocation / Implementation:

Applications Capacity (MW) 3.48Status: Live (upnedasolarrooftopportal.com)

SPIN Integration Status: Integrated

UWP Progress

Sanctioned Capacity (MW) 1.30

Other Unique Aspects on Aggregation, Marketing etc.,

/ TA Support Request Areas

Deployed: CAPEX

Envisaged:

Business Models Deployed or Envisaged

Year 19-20 20-21

Sanctioned

Capacity(MW)

12

Tendered Yes (By

UPNEDA)No

No. of

Vendors

71

Resi-Installed

Capacity(MW)

0.92

Year 19-20 20-21 21-22

Baseline

Capacity

(MW)

3.216 3.416 3.762

Overall

Installed

Capacity

(MW)

3.416 3.762 4.024*

* As of May 2021

MNRE Phase-II Subsidy / Incentive Status

0

0

Subsidy /

Year19-20 20-21

Availed

Advance

Yes No

Availed 2nd

Instalment

No No

Availed 3rd

Instalment

No No

Incentives/

Year19-20 20-21

Submitted

for

Incentives

No No

Availed

Incentives

No No

Additional Comments on Subsidy & Incentives :

Additional Comments on Unified Web Portal :

TA Support Needed

SOP for implementation and modification in UPNEDA portal

Uttar Pradesh

PuVVNL

SUPRABHA Progress Review 1621 June 2021

MNRE Phase-II Capacity Allocation / Implementation Status

0

0

Additional Comments on Allocation / Implementation:

Applications Capacity (MW) 2.48Status: Live (upnedasolarrooftopportal.com)

SPIN Integration Status: Integrated

UWP Progress

Sanctioned Capacity (MW) 0.87

Other Unique Aspects on Aggregation, Marketing etc.,

/ TA Support Request Areas

Deployed: CAPEX

Envisaged:

Business Models Deployed or Envisaged

Year 19-20 20-21

Sanctioned

Capacity(MW)

10

Tendered Yes (By

UPNEDA)No

No. of

Vendors

71

Resi-Installed

Capacity(MW)

0.68

Year 19-20 20-21 21-22

Baseline

Capacity

(MW)

6.986 11.487 11.958

Overall

Installed

Capacity

(MW)

11.958 11.958 12.533*

* As of May 2021

MNRE Phase-II Subsidy / Incentive Status

0

0

Subsidy /

Year19-20 20-21

Availed

Advance

Yes No

Availed 2nd

Instalment

No No

Availed 3rd

Instalment

No No

Incentives/

Year19-20 20-21

Submitted

for

Incentives

No No

Availed

Incentives

No No

Additional Comments on Subsidy & Incentives :

Additional Comments on Unified Web Portal :

TA Support Needed

SOP for implementation and modification in UPNEDA portal

Uttar Pradesh

DVVNL

SUPRABHA Progress Review 1721 June 2021

MNRE Phase-II Capacity Allocation / Implementation Status

0

0

Additional Comments on Allocation / Implementation:

Applications Capacity (MW) 2.06Status: Live (upnedasolarrooftopportal.com)

SPIN Integration Status: Integrated

UWP Progress

Sanctioned Capacity (MW) 0.77

Other Unique Aspects on Aggregation, Marketing etc.,

/ TA Support Request Areas

Deployed: CAPEX

Envisaged:

Business Models Deployed or Envisaged

Year 19-20 20-21

Sanctioned

Capacity(MW)

11

Tendered Yes (By

UPNEDA)No

No. of

Vendors

71

Resi-Installed

Capacity(MW)

0.43

Year 19-20 20-21 21-22

Baseline

Capacity

(MW)

0.18 0.30 0.85

Overall

Installed

Capacity

(MW)

0.30 0.85 0.89*

* As of May 2021

MNRE Phase-II Subsidy / Incentive Status

0

0

Subsidy /

Year19-20 20-21

Availed

Advance

Yes No

Availed 2nd

Instalment

No No

Availed 3rd

Instalment

No No

Incentives/

Year19-20 20-21

Submitted

for

Incentives

No No

Availed

Incentives

No No

Additional Comments on Subsidy & Incentives :

Additional Comments on Unified Web Portal :

TA Support Needed

SOP for implementation and modification in UPNEDA portal

Uttar Pradesh

KESCo

SUPRABHA Progress Review 1821 June 2021

MNRE Phase-II Capacity Allocation / Implementation Status

0

0

Additional Comments on Allocation / Implementation:

Applications Capacity (MW) 0.66Status: Live (upnedasolarrooftopportal.com)

SPIN Integration Status: Integrated

UWP Progress

Sanctioned Capacity (MW) 0.35

Other Unique Aspects on Aggregation, Marketing etc.,

/ TA Support Request Areas

Deployed: CAPEX

Envisaged:

Business Models Deployed or Envisaged

Year 19-20 20-21

Sanctioned

Capacity(MW)

4

Tendered Yes (By

UPNEDA)No

No. of

Vendors

71

Resi-Installed

Capacity(MW)

0.11

Year 19-20 20-21 21-22

Baseline

Capacity

(MW)

12.084 15.634 16.822

Overall

Installed

Capacity

(MW)

15.634 16.822 17.159*

* As of May 2021

MNRE Phase-II Subsidy / Incentive Status

0

0

Subsidy /

Year19-20 20-21

Availed

Advance

Yes No

Availed 2nd

Instalment

No No

Availed 3rd

Instalment

No No

Incentives/

Year19-20 20-21

Submitted

for

Incentives

No No

Availed

Incentives

No No

Additional Comments on Subsidy & Incentives :

Additional Comments on Unified Web Portal :

TA Support Needed

SOP for implementation and modification in UPNEDA portal

Uttar Pradesh

NPCL

SUPRABHA Progress Review 1921 June 2021

Applications Capacity (MW) 0.174Status: Live

(https://upnedasolarrooftopportal.com/Apply-

Online )

SPIN Integration Status: Integrated

UWP Progress

Sanctioned Capacity (MW) 0.174

Other Unique Aspects on Aggregation, Marketing etc.,

/ TA Support Request Areas

Deployed : CAPEX

Envisaged: None

Business Models Deployed or Envisaged

Additional Comments on Unified Web Portal :

MNRE Phase-II Capacity Allocation / Implementation Status

0

0

Additional Comments on Allocation / Implementation: We have received 28 no. of applications of 174KW

capacity under Phase-II of Rooftop Solar Program, out of which 120 kW against 19 applications has been

installed/commissioned. However, till date we have Residential installed capacity of 1.303 MW out of

23.478MW.

MNRE Phase-II Subsidy / Incentive Status

0

0

Additional Comments on Subsidy & Incentives :

Year 19-20 20-21

Sanctioned

Capacity(MW)2 MW -

Tendered Yes(UPNEDA)

-

No. of Vendors 71

Resi-Installed

Capacity(MW)0.061

Year 19-20 20-21 21-22

Baseline

Capacity

(MW)

22.51 23.22 23.40

Overall

Installed

Capacity

(MW)

23.22 23.40 23.48*

* As of May 2021

Subsidy /

Year19-20 20-21

Availed

Advance

No No

Availed 2nd

Instalment

No No

Availed 3rd

Instalment

No No

Incentives/

Year19-20 20-21

Submitted

for

Incentives

No No

Availed

Incentives

No No TA Support Needed

SOP for implementation and modification in UPNEDA portal

Uttar Pradesh

Torrent Power (Agra)

SUPRABHA Progress Review 2021 June 2021

MNRE Phase-II Capacity Allocation / Implementation Status

0

0

Additional Comments on Allocation / Implementation:

Applications Capacity (MW) 3.03Status: Live (upnedasolarrooftopportal.com)

SPIN Integration Status: Integrated

UWP Progress

Sanctioned Capacity (MW) 1.06

Other Unique Aspects on Aggregation, Marketing etc.,

/ TA Support Request Areas

Deployed: CAPEX

Envisaged:

Business Models Deployed or Envisaged

Year 19-20 20-21

Sanctioned

Capacity(MW)

2

Tendered Yes (By

UPNEDA)No

No. of Vendors 71

Resi-Installed

Capacity(MW)

0.738

Year 19-20 20-21 21-22

Baseline

Capacity

(MW)

4.179 5.350

5

7.465

Overall

Installed

Capacity

(MW)

5.350 7.465 7.696*

* As of May 2021

MNRE Phase-II Subsidy / Incentive Status

0

0

Subsidy /

Year19-20 20-21

Availed

Advance

No No

Availed 2nd

Instalment

No No

Availed 3rd

Instalment

No No

Incentives/

Year19-20 20-21

Submitted

for

Incentives

Yes Yes

Availed

Incentives

No No

Additional Comments on Subsidy & Incentives :

Additional Comments on Unified Web Portal:

TA Support Needed

SOP for implementation and modification in UPNEDA portal

Maharashtra

MSEDCL

GIZ Progress Review 2121 June 2021

MNRE Phase-II Capacity Allocation / Implementation Status

0

0

Additional Comments on Allocation / Implementation: Tender for 500 MW is

under preparation and shall be launched soon.

Applications Capacity (MW) 2.563Status: Live https://grouppaybill.mahadiscom.in/PayNCCharg

es/UI/ROOFTOP/PVNewApplication.aspx

SPIN Integration Status:

Integrated

UWP Progress

Sanctioned Capacity (MW) 1.165

Other Unique Aspects on Aggregation, Marketing etc.,

/ TA Support Request Areas

Deployed : CAPEX

Envisaged : NA

Business Models Deployed or Envisaged

Year 19-20 20-21

Sanctioned

Capacity(MW)25 500

Tendered Yes No

No. of

Vendors26 NA

Resi-Installed

Capacity(MW)0.251 NA

Year 19-20 20-21 21-22

Baseline

Capacity

(MW)

288.797 511.493 693.34

Overall

Installed

Capacity

(MW)

511.493 693.34 705.38

As of April 2021

MNRE Phase-II Subsidy / Incentive Status

0Subsidy /

Year19-20 20-21

Availed

AdvanceYes No

Availed 2nd

Instalment No No

Availed 3rd

InstalmentNo No

Incentives/

Year19-20 20-21

Submitted for

Incentives

Yes No

Availed

Incentives

No No

Additional Comments on Subsidy & Incentives : Request for Incentives for FY 19-

20 is submitted to MNRE.

Additional Comments on Unified Web Portal : NA

Unique Aspects TA Support Needed

Consumer Awareness through volunteer

initiative of GIZ TA program

Consumer Awareness, Development of

Media Collaterals

Maharashtra

The Brihanmumbai Electric Supply & Transport

GIZ Progress Review 2221 June 2021

MNRE Phase-II Capacity Allocation / Implementation Status

0

0

Additional Comments on Allocation / Implementation: NA

Applications Capacity (MW) 0Status: Live The Brihanmumbai Electric Supply

& Transport Undertaking (BEST) | of the Brihanmumbai Mahanagarpalika(bestundertaking.com)

SPIN Integration Status:

Integrated

UWP Progress

Sanctioned Capacity (MW) 0

Other Unique Aspects on Aggregation, Marketing etc.,

/ TA Support Request Areas

Deployed : CAPEX

Business Models Deployed or Envisaged

Year 19-20 20-21

Sanctioned

Capacity(MW)0.58 0

Tendered Yes No

No. of

Vendors3 NA

Resi-Installed

Capacity(MW)0 NA

Year 19-20 20-21 21-22

Baseline

Capacity

(MW)

2.86

MWp

0.606

MWp

0.151

MWp

Overall

Installed

Capacity

(MW)

8.996

MWp

9.600

MWp

9.751

MWp

As of April 2021

MNRE Phase-II Subsidy / Incentive Status

0Subsidy /

Year19-20 20-21

Availed

AdvanceNo No

Availed 2nd

Instalment No No

Availed 3rd

InstalmentNo No

Incentives/

Year19-20 20-21

Submitted for

Incentives

Yes No

Availed

Incentives

No No

Additional Comments on Subsidy & Incentives : Request for Incentives for FY

19-20 is submitted to MNRE.

Additional Comments on Unified Web Portal : NA

Unique Aspects TA Support Needed

MaharashtraAdani Electricity Mumbai Limited

SUPRABHA Progress Review 2321 June 2021

MNRE Phase-II Capacity Allocation / Implementation Status

0

0

Additional Comments on Allocation / Implementation:

Applications Capacity (MW) 0Status: Solar Portal Live

https://www.adanielectricity.com/RooftopSolarSPIN Integration Status:

To be integrated

UWP Progress

Sanctioned Capacity (MW) 0

Unique Aspects TA Support Needed- Dedicated RTS Cell - Training to Discom Officers & Vendors

- Scheme promotion on website - Tender Validity to be extended till Mar-22.

Other Unique Aspects on Aggregation, Marketing etc.,

/ TA Support Request Areas

Deployed : CAPEX

Envisaged : NA

Business Models Deployed or Envisaged

Year 19-20 20-21

Sanctioned

Capacity(MW)

3.5 0

Tendered Yes No

No. of

Vendors

4 0

Resi-Installed

Capacity(MW)

0 0

Year 19-20 20-21 21-22

Baseline

Capacity

(MW)

10.839 16.705 20.416

Overall

Installed

Capacity

(MW)

5.866 3.710 0.135

(WIP)

* As of 31 May 2021

MNRE Phase-II Subsidy / Incentive Status

0

0

Subsidy /

Year19-20 20-21

Availed

Advance

No No

Availed 2nd

Instalment

No No

Availed 3rd

Instalment

No No

Incentives/

Year19-20 20-21

Submitted

for

Incentives

Yes No

Availed

Incentives

No No

Additional Comments on Subsidy & Incentives : Claim for incentives for FY19-20

submitted to MNRE on April 29, 2021.

Additional Comments on Unified Web Portal : New Solar Portal is under development

and will be integrated with MNRE SPIN portal.

Maharashtra

Tata Power Mumbai

GIZ Progress Review 2421 June 2021

MNRE Phase-II Capacity Allocation / Implementation Status

0

0

Additional Comments on Allocation / Implementation: NA

Applications Capacity (MW) 0Status: Modification of the existing

net metering portal in progress

SPIN Integration Status: In –

Progress – Target – June 2021

UWP Progress

Sanctioned Capacity (MW) 0

Other Unique Aspects on Aggregation, Marketing etc.,

/ TA Support Request Areas

Deployed : CAPEX

Business Models Deployed or Envisaged

Year 19-20 20-21

Sanctioned

Capacity(MW)0.4 2

Tendered Yes Yes

No. of

Vendors8 8

Resi-Installed

Capacity(MW)0 0

Year 19-20 20-21 21-22

Baseline

Capacity

(MW)

5.3

MWp

2.1

MWp

0.1

MWp

Overall

Installed

Capacity

(MW)

9.4

MWp

11.5

MWp

11.6

MWp

As of April 2021

MNRE Phase-II Subsidy / Incentive Status

0Subsidy /

Year19-20 20-21

Availed

AdvanceNo No

Availed 2nd

Instalment No No

Availed 3rd

InstalmentNo No

Incentives/

Year19-20 20-21

Submitted for

Incentives

Yes No

Availed

Incentives

No No

Additional Comments on Subsidy & Incentives : Request for Incentives for FY

19-20 is submitted to MNRE.

Additional Comments on Unified Web Portal : NA

Unique Aspects TA Support Needed

West Bengal

Implementing Agency: WBSEDCL

SUPRABHA Progress Review 2521 June 2021

MNRE Phase-II Capacity Allocation / Implementation Status

0

0

Additional Comments on Allocation / Implementation:

Applications Capacity (MW) 0Status: Under Development (Estimated date

of completion: 30 June 2021)

SPIN Integration Status: To be

Integrated (Estimated date of completion: 9 July

2021)

UWP Progress

Sanctioned Capacity (MW) 0

TA Support Needed

Tender support is provided and DISCOM coordinator is placed

Other Unique Aspects on Aggregation, Marketing etc.,

/ TA Support Request Areas

Deployed :NA

Envisaged :NA

Business Models Deployed or Envisaged

Year 19-20 20-21

Sanctioned

Capacity(MW)

5 50

Tendered No In

Progress

No. of

Vendors

0 NA

Resi-Installed

Capacity(MW)

0 0

Year 19-20 20-21 21-22

Baseline

Capacity

(MW)

7.9

Overall

Installed

Capacity

(MW)

*

* As of May 2021

MNRE Phase-II Subsidy / Incentive Status

0

0

Subsidy /

Year19-20 20-21

Availed

Advance

No

Availed 2nd

Instalment

No No

Availed 3rd

Instalment

No No

Incentives/

Year19-20 20-21

Submitted

for

Incentives

No No

Availed

Incentives

No No

Additional Comments on Subsidy & Incentives :

Additional Comments on Unified Web Portal :

Uttarakhand

Implementing Agency: UPCL

SUPRABHA Progress Review 2621 June 2021

MNRE Phase-II Capacity Allocation / Implementation Status

0

0

Additional Comments on Allocation / Implementation:

Applications Capacity (MW) 7Status: Live (https://usrp.upcl.org)

SPIN Integration Status: Integrated

UWP Progress

Sanctioned Capacity (MW) 2

TA Support Needed

TA support ended from GIZ after development of portal, tender and

demand aggregation support

Other Unique Aspects on Aggregation, Marketing etc.,

/ TA Support Request Areas

Deployed : Capex

Envisaged :

Business Models Deployed or Envisaged

Year 19-20 20-21

Sanctioned

Capacity(MW)

2 20

Tendered Yes

No. of

Vendors

15

Resi-Installed

Capacity(MW)

7 0

Year 19-20 20-21 21-22

Baseline

Capacity

(MW)

Overall

Installed

Capacity

(MW)

*

* As of May 2021

MNRE Phase-II Subsidy / Incentive Status

0

0

Subsidy /

Year19-20 20-21

Availed

Advance

Availed 2nd

Instalment

Availed 3rd

Instalment

Incentives/

Year19-20 20-21

Submitted

for

Incentives

Availed

Incentives

Additional Comments on Subsidy & Incentives :

Additional Comments on Unified Web Portal :

Himachal Pradesh

Implementing Agency: HPSEBL

SUPRABHA Progress Review 2721 June 2021

MNRE Phase-II Capacity Allocation / Implementation Status

0

0

Additional Comments on Allocation / Implementation:

Applications Capacity (MW) 0Status: Live (http://www.rts.himurja.gov.in/)

SPIN Integration Status: Integrated

UWP Progress

Sanctioned Capacity (MW) 0

TA Support Needed

TA support ended from GIZ after development of portal, tender and

demand aggregation support

Other Unique Aspects on Aggregation, Marketing etc.,

/ TA Support Request Areas

Deployed :

Envisaged :

Business Models Deployed or Envisaged

Year 19-20 20-21

Sanctioned

Capacity(MW)

10

Tendered Yes No

No. of

Vendors

Resi-Installed

Capacity(MW)

Year 19-20 20-21 21-22

Baseline

Capacity

(MW)

Overall

Installed

Capacity

(MW)

*

* As of May 2021

MNRE Phase-II Subsidy / Incentive Status

0

0

Subsidy /

Year19-20 20-21

Availed

Advance

Yes /

No

Availed 2nd

Instalment

Yes /

No

Yes /

No

Availed 3rd

Instalment

Yes /

No

Yes /

No

Incentives/

Year19-20 20-21

Submitted

for

Incentives

Yes / No Yes / No

Availed

Incentives

Yes / No Yes / No

Additional Comments on Subsidy & Incentives :

Additional Comments on Unified Web Portal :

Jammu & Kashmir/Ladakh

Implementing Agency: JAKEDA

SUPRABHA Progress Review 2821 June 2021

MNRE Phase-II Capacity Allocation / Implementation Status

0

0

Additional Comments on Allocation / Implementation:

Applications Capacity (MW) 0Status: Live (https://jk.ahasolar.in/)

SPIN Integration Status: Integrated

UWP Progress

Sanctioned Capacity (MW) 0

TA Support Needed

TA support ended from GIZ after development of portal, tender and

demand aggregation support

Other Unique Aspects on Aggregation, Marketing etc.,

/ TA Support Request Areas

Deployed :

Envisaged :

Business Models Deployed or Envisaged

Year 19-20 20-21

Sanctioned

Capacity(MW)

Nil

Tendered No

No. of

Vendors

Resi-Installed

Capacity(MW)

Nil

Year 19-20 20-21 21-22

Baseline

Capacity

(MW)

Overall

Installed

Capacity

(MW)

*

* As of May 2021

MNRE Phase-II Subsidy / Incentive Status

0

0

Subsidy /

Year19-20 20-21

Availed

Advance

No

Availed 2nd

Instalment

No No

Availed 3rd

Instalment

No No

Incentives/

Year19-20 20-21

Submitted

for

Incentives

No No

Availed

Incentives

No No

Additional Comments on Subsidy & Incentives :

Additional Comments on Unified Web Portal :

Arunachal Pradesh

Implementing Agency: APEDA

SUPRABHA Progress Review 2921 June 2021

MNRE Phase-II Capacity Allocation / Implementation Status

0

0

Additional Comments on Allocation / Implementation:

Applications Capacity (MW) 0Status: Under Development (provide target

date of completion

SPIN Integration Status: To be

Integrated (provide target date of completion)

UWP Progress

Sanctioned Capacity (MW) 0

Unique Aspects TA Support Needed

Other Unique Aspects on Aggregation, Marketing etc.,

/ TA Support Request Areas

Deployed :

Envisaged :

Business Models Deployed or Envisaged

Year 19-20 20-21

Sanctioned

Capacity(MW)

Nil

Tendered No

No. of

Vendors

Resi-Installed

Capacity(MW)

Nil

Year 19-20 20-21 21-22

Baseline

Capacity

(MW)

Overall

Installed

Capacity

(MW)

*

* As of May 2021

MNRE Phase-II Subsidy / Incentive Status

0

0

Subsidy /

Year19-20 20-21

Availed

Advance

No

Availed 2nd

Instalment

No No

Availed 3rd

Instalment

No No

Incentives/

Year19-20 20-21

Submitted

for

Incentives

No No

Availed

Incentives

No No

Additional Comments on Subsidy & Incentives :

Additional Comments on Unified Web Portal :

Diu & Daman, Dadra And Nagar Haveli

Implementing Agency: DISCOM

21 June 2021 SUPRABHA Progress Review 30

MNRE Phase-II Capacity Allocation / Implementation Status

0

0

Additional Comments on Allocation / Implementation:

Applications Capacity (MW) 0Status: Live

(http://dnhpdcl.rooftopsolar.org.in/)

SPIN Integration Status: Integrated

UWP Progress

Sanctioned Capacity (MW) 0

TA Support Needed

Capacity of residential rooftop is not required. The cost of electricity is

very low for residential consumers

Other Unique Aspects on Aggregation, Marketing etc.,

/ TA Support Request Areas

Deployed :

Envisaged :

Business Models Deployed or Envisaged

Year 19-20 20-21

Sanctioned

Capacity(MW)

Nil

Tendered No

No. of

Vendors

0

Resi-Installed

Capacity(MW)

Nil

Year 19-20 20-21 21-22

Baseline

Capacity

(MW)

Overall

Installed

Capacity

(MW)

*

* As of May 2021

MNRE Phase-II Subsidy / Incentive Status

0

0

Subsidy /

Year19-20 20-21

Availed

Advance

No

Availed 2nd

Instalment

No No

Availed 3rd

Instalment

No No

Incentives/

Year19-20 20-21

Submitted

for

Incentives

No No

Availed

Incentives

No No

Additional Comments on Subsidy & Incentives :

Additional Comments on Unified Web Portal :

Learnings

• One vendor per MW of tender capacity – Gujarat experience shows that only 10-20 vendors were only able to installed 1-2 MW solar rooftop capacity in residential consumer

• Consumer friendly landing page for solar rooftop in DISCOMs website, Missed call number and SMS campaign from DISCOM is a must

• Awareness campaign through radio, TV and DISCOMs office

• Solar rooftop ambassador in DISCOM- Dedicated solar rooftop cell with officer in-charge shall be established in each DISCOMs

• Ownership of TA support- DISCOMs need to takeover the portals and other publicity and awareness material after the end of TA support

21 June 2021 SUPRABHA Progress Review 31

Thank You

In cooperation with:

Deutsche Gesellschaft für

Internationale Zusammenarbeit (GIZ) GmbH

GIZ Office (India), B – 5/2 Safdarjung Enclave, 1st Floor

New Delhi, 110029, India

T +91 11 49495353 Ext.

F +91 11 46036690

M +91 9810 511 138

Mr. Joerg GaeblerPrincipal Advisor, IGEN-solar

[email protected]

6/21/2021

Project Manager:

Mr. Abhinav JainAdvisor

[email protected]

Consultancy support by

-EY for UP, Punjab, Maharashtra and West Bengal -AHA Solar for Gujarat

12 June 2021

Presented By:

Mr. Piyush Kumar Arora

[email protected]

INDEX

2

About IREDA 3Major Schemes - Funding Rooftop Solar Projects 4Broad Policy Framework for funding Solar Rooftop Projects 5Appraisal Checklist for Appraisal and Risk Assessment 6Challenges faced during project appraisal, Loan sanction/ disbursements 7Case Study: 1.018 MWp Solar Rooftop Project 8

3

About IREDA

Established in 1987 as a Dedicated FI under Ministry of New &Renewable Energy, Govt. of India to promote RenewableSources of Energy

Catalyzed RE Market Development in India

100% Government owned company with total equitycontribution of Rs. 784.60 Cr.

Raised US$ 300 million rupee-denominated green masala bondat competitive pricing of 7.125% p.a. at London/ Singapore Stockexchanges

Financed more than 2500 RE projects - largest share in REProject Financing in India

Cumulative loan sanctions of more than Rs. 92000 Crores andCumulative loan disbursements of more than 54000 Crores

Paid up capital: Rs. 784.60Crs (As on 31.03.2020)- USD104.67 Mn

Reserves and Surplus: Rs.1736.71 Crs (As on31.03.2020)- USD 231.68 Mn

IREDA has already availedinternational assistanceequivalent to ~Rs. 8000 Crsfrom various Bilateral /Multilateral agencies.

Approval for Issue of 13.90crore fresh Equity shares offace Value Rs. 10 under IPO.

3

The annual financial highlights for the FY 2020-21 as against FY 2019-20 are as follows:

Profit Before Tax- Rs. 570 crores as against Rs. 241 crores, up by 136% (All-time high)

Profit After Tax- Rs. 346 crores as against Rs. 215 crores (up by 61%)

Loan Disbursement- Rs. 8827 crores as against Rs. 8785 crores, (2nd highest ever)

Loan Book- Rs. 27854 crores as against Rs. 23548 crores, (Annual growth: 2nd highest ever)

Net-worth- Rs. 2995 crore as against Rs. 2521 crore, (up by 19%)

Net NPA Reduction- 5.61% as against 7.18% (reduction by 22%)

Major Schemes - Funding Rooftop Solar Projects

Specific Schemes for SOLAR ROOFTOP

Loan Scheme for Financing Rooftop Solar PV Grid Connected/ Interactive Power Projects(Industrial, Commercial and Institutional)

IREDA Loan Scheme/Line of Credit for Financing Large Scale Roof Top Solar PV Grid Connected/Interacted Power Projects.

Loan against Securitization of Future Cash Flow of Renewable Energy Projects

Other Related Schemes

Short term loan assistance to RE Developers /Suppliers/ Contractors/ Energy Efficiency Projects

Short Term Loan Facility to Govt. Bodies/ Discoms/ Transcos /State Owned Trading Companies

17.0

0

14.4

8 26.1

8

32.8

6

21.5

0

76.9

2

61.2

2

82.2

5

89.1

9

46.7

4

67.2

3

7.85

43.5

9

1.62

33.8

2

0.0010.0020.0030.0040.0050.0060.0070.0080.0090.00

100.00

2016-17 2017-18 2018-19 2019-20 2020-21

IREDA Sanctions and Disbursements

Sanctioned Capacity (MW) Sanctioned Amount (INR Crores) Disbursed Amount (INR Crores)

4

Broad Policy Framework for funding Solar Rooftop Projects

Financing Schemes

• Project Financing

Quantum of Assistance

• 70%• or Upto 75% of the Project cost with

DSCR >=1.3 for new applicants + goodtrack record for repayments for oldborrowers

Minimum Promoter Contribution

• 25%-30% of the Project Cost. Further,generally a minimum of 70% promotercontribution is required to be brought-inupfront

Rate of Interest

• 9.20% - 10.15% per annum (dependingupon the Internal Grading of the Project– Grade I/II/III/IV/V)*

• Discount of 15 bps for Solar RTprojects on government/PSUbuildings

Mode of Application

• Single Or Aggregate Multiple Projects• Minimum project capacity - at least 1

MWp• Minimum capacity of sub projects not be

less than 20 kWp.

Upfront Fee • 1% of IREDA’s Loan Amount upto Rs.100 Cr. and 0.25% for loan amount overand above Rs. 100 Cr.

Moratorium Period

• 12 months from the date of COD

Repayment Period

• Upto 10 Years, 15 years for govt. rooftops• 15 years for projects having private off

takers, with at least 80% having a creditrating of “A- or above.”

Construction Period

• Maximum up to 12 months from firstdisbursement.

GeneralSecurity/Conditions On Case-to-case Basis

• Primary Securities• Hypothecation of Movable Assets, TRA,

Assignment of Project Documents,Pledge of Shares, Personal Guarantees,substitution rights for lease holdrooftops.

• Secondary Securities• Corporate Guarantee till Project

Stabilization, Collateral securities(minimum 10%-20% of loan amount) viamortgage of immovable non-agriculturalproperties in urban or rural areas(excluding waste/barren lands) and/orBank Guarantee/FD, DSRA for twoQuarters – P+I

• RPC and Cash Sweep conditions• Upfront Promoter Contribution with at

least 75% expenditure on project beforefirst disbursement

5

https://www.ireda.in/images/whatsnewpage/Annexure-I.pdfLink to IREDA’s FINANCING NORMS AND SCHEMES*https://www.ireda.in/interest-rate-matrix

6

Appraisal Checklist for Appraisal and Risk AssessmentTechnical Due Diligence – Major Areas:

Detailed project report (DPR)/ ResourceAssessment/ Energy yield report (Including thirdparty view if required from empaneledRA/Consultants)

RE Technology – Warranty, Performanceassessments

Policy and Regulatory Regime

PPA, LOI, Status of clearances/ approvals, Detailsof contracts (EPC, O&M, material Supply etc.),Lease Agreements

Project land details (Agricultural/Non-Agricultural/Purchase/Lease/Private/Government etc.),Environmental & Social assessment

Business Profiles and experience/Credentials

KYC Categorization of borrower and promotercompanies/directors / guarantors

Assessment w.r.t. similar projects in vicinity

Financial Due Diligence - – Major Areas:

Cashflows & financials to ascertain projectviability - Uncertainty Calculation, Probability AndSensitivity Analysis - DSCR, Project NPV,IRR, ACR, Cost of Generation

MNRE/Industry Benchmarking

Audited Annual reports for the past threeyears of company and promoters

Account status from existing Fis/Banks +Credit Information, CIBIL reports,Networths.

Income tax returns in respect of applicantcompany/ promoter(s)/Guarantor(s) for lastthree years.

Board resolution for setting up of project andborrowing of loan.

Source of promoters’ contribution along withnecessary supporting documents.

6

Mitigation - Sponsor/Promoter Risk, Permitting Risk , Execution Risk , Operating Risk, GenerationRisk , Offtaker Risk , Financial Risk.

Challenges faced during project appraisal, Loan sanction/ disbursements

• Untimely and incomplete submission of requested information from the Applicantcompany/Borrower

• Reliability of Resource Assessment data, Inputs to PV Syst Reports

• Promoters' contribution includes part equity, UNSECURED LOANS, Convertible Debentures etc.

• Performance and Payment Security Provisions in Agreements and related Contracts

• Offtaker Ratings and financials in case of Group Captive/Third Party Consumers

• Delay in Security Perfection on account of pending approvals

7

Case Study: 1.018 MWp Solar Rooftop Project

Project Capacity 1.018 MWpPPA Status 25-year PPA, @Rs. 3.70/kWh.Project Cost Rs. 3.87 CroresCost per MW Rs. 3.81 Crores (DC)Promoter Contribution Rs. 1.87 CroresLoan Proposed Rs. 2 CroresDebt (% of Project Cost) 51.56%Interest rate 10.40%Repayment period 48 structured quarterly instalments

PLF for appraisal 17.66% (AC)Key Financial Indicators Average DSCR – 1.30%, Average ACR –

2.43, Average Cost of Generation – 2.31

Securities proposed

Hypothecation of movable properties pertaining to the project both

present and future

Corporate and Personal Guarantees

Collateral Security of 15% of the loan amount

Deposit of Post-Dated Cheques/ECS for principal loan repayments

and interest

Debt Service Reserve (DSRA) equivalent to debt service obligations

for 2 quarters – P+I

Assignment of TRA, EPC, O&M and PPA contracts as applicable

51% Pledge of Shares of the borrower8

Thank You

Skill Council for Green Jobs

Indian Renewable Energy Development Agency Limited(A Government of India Enterprise)

Corporate Office Registered Office

3rd Floor, August Kranti Bhawan, India Habitat Centre, East Court

Bhikaji Cama Place, New Delhi – 110 066. Core-4A, 1st Floor, Lodhi Road, New Delhi - 11 00 03

Tel: +91 11 26717400 - 26717412 Tel: +91 11 24682206 - 24682219

Fax: +91 11 26717416 Fax: +91 11 24682202

Email: [email protected]

Tata Cleantech CapitalRooftop Solar

June 2021

Tata Cleantech Capital (TCCL): Introduction First of its kind Private Sector Green Investment Bank in emergingeconomies with focus on climate finance and advisory services

9.3 GW+Renewable capacity financed Projects financed Annual carbon emission averted

225+ 15.0 million tons

Project Finance Debt Syndication Advisory

Business activities

• First private entity globally to partner Green Climate Fund ('GCF') to developsolar rooftop market through USD 100 million credit line

• First Indian entity to join the Global Green Bank Network comprising NationalGreen Banks from across the world

• Globally acclaimed by Climate investors for its formidable work inmainstreaming Climate Finance in India

• “AAA” domestic rating in India by CRISIL (an S&P Global Company)

Key highlights

2

TCCL’s Induction into the Global “Green Bank Network”

Members of the coveted Green Bank Network

TCCL was inducted into the Green Bank Network in September 2019, in New York coinciding with United Nations meetings on Climate Change and New York Climate Week

TCCL is the first Private Sector Climate Finance Institution in the Green Banking Network

3

Challenges in rooftop solar financing: lower generation but higher cost

4

37%35%

34% 34% 33%

29%

23%

19%17% 16%

0%

10%

20%

30%

40%

0%

5%

10%

15%

20%

25%

30%

35%

40%

State1

State2

State3

State4

State5

State6

State7

State8

State9

State10

Ground Mounted Rooftop Difference

Irradiation assessment

• High mismatch losses• Higher possibility of Potential Induced Degradation (PID)• Significantly higher shading losses• Operations at comparatively higher temperatures

Lower generation

• The orientation of the modules (Tilt angle and azimuth angle of module) is often not in an ideal condition

• In rooftop projects, a compromise is required between maximizing the capacity and generation per kW

Roof orientation

• Rooftop solar projects are required to stop generation in case of grid failure unless it is synchronized with gen-sets

• Throttling of solar power to maintain spinning reserve for diesel load management in case of power failure

Curtailment & throttling

• Significantly higher levels of aerosols• Land use patterns

Average CUF in TCCL’s portfolio

Rooftop solar projects have higher cost as compared to that of utility scale projects because of lack of scale benefits

Financing solutions

Business model

Consumer segmentation

Challenges in rooftop solar financing: higher processing costs and credit issues

5

Government ResidentialC&I

RESCO CAPEX RESCO CAPEX CAPEX

• Significant proportion of reputed and credit worthy offtakers prefer OPEX model

• Higher system size

19%

17%64%

AA- and aboveA+ and BBB-Below BB+ or unrated

IT systems upgrades

Partnerships

TCCL is in advanced stages to launch a product

• Small system sizes• Requires NOC from existing lenders

significantly increasing the time and effort

Proposed framework for financing SME segment

6

Lender

Rooftop Solar System

SMEs

Designated government agencyMultilaterals

EPC/ O&M companies EPC1 EPC2 EPCi…………..

PlatformFintechs/ support agencies

Other support agencies (e.g.: legal)

Low cost funds

Equity

DebtFaster loan processing

Installation and O&M

Support in debt repayment/collection

Payments for services

Documentation

Documentation and support for system recovery

First loss guarantee

System rights handover support

Auction and selection of winner

System recovery

System buyback/ at fair market value arrived through auction process

Dismantling and reinstallation of system

https://seed.uno/articles/plcf-2020-india-tata-cleantech

TCCL is committed to be part of efforts in mainstreaming rooftop solar financing in India

9.6%

15.0%

22.0% 23.8%

FY'18 FY'19 FY'20 FY'21

TCCL’s share in addressable market

7

Rooftop solar is still largely untapped in India

0%

20%

40%

60%

80%

100%

Developedmarkets

China Indiacurrently

India target

Net-metering

DISCOMs suffer disproportionate losses

Gross metering

Little incentive for consumers to install rooftop solar plant