Rab

14
REKAPITULASI BILL OF QUANTITY ( B O Q ) Pekerjaan : Inventarisasi penginderaan jarak jauh Danau tempe kabupaten wajo Tahun Anggaran : 2015 NO. URAIAN JUMLAH BIAYA (Rp.) I BIAYA PERSONIL 406,000,000.00 1.1. TENAGA AHLI 208,000,000.00 1.2. TENAGA SUB PROFESIONAL 152,000,000.00 1.3. TENAGA PENUNJANG 46,000,000.00 II BIAYA TRANSPORTASI 28,000,000.00 2.1. SEWA KENDARAAN 28,000,000.00 2.2. BIAYA PERJALANAN DINAS 61,500,000.00 III KANTOR DAN PERALATAN 127,900,000.00 3.1. BIAYA KANTOR 25,000,000.00 3.2. PERALATAN KANTOR 18,900,000.00 3.3. PERALATAN LAPANGAN 84,000,000.00 IV BAHAN-BAHAN HABIS PAKAI 15,125,000.00 4.1. BAHAN-BAHAN KANTOR 13,800,000.00 4.2. BAHAN-BAHAN LAPANGAN 1,325,000.00 V BIAYA PENGADAAN CITRA DAN RBI 100,550,000.00 5.1. PENGADAAN FOTO UDARA 100,000,000.00 5.2. PETA RUPA BUMI (BAKOSURTANAL) 550,000.00 VI BIAYA REPRODUKSI DOKUMEN 4,250,000.00 SUB TOTAL 681,825,000.00 PPN 10% 68,182,500.00 TOTAL 750,007,500.00 DIBULATKAN 750,000,000.00 Terbilang : TUJUH RATUS LIMA PULUH JUTA RUPIAH

description

ok

Transcript of Rab

Page 1: Rab

REKAPITULASI BILL OF QUANTITY

( B O Q )

Pekerjaan : Inventarisasi penginderaan jarak jauh Danau tempe kabupaten wajo

Tahun Anggara : 2015

NO. URAIAN JUMLAH BIAYA (Rp.)

I BIAYA PERSONIL 406,000,000.00

1.1. TENAGA AHLI 208,000,000.00

1.2. TENAGA SUB PROFESIONAL 152,000,000.00

1.3. TENAGA PENUNJANG 46,000,000.00

II BIAYA TRANSPORTASI 28,000,000.00

2.1. SEWA KENDARAAN 28,000,000.00

2.2. BIAYA PERJALANAN DINAS 61,500,000.00

III KANTOR DAN PERALATAN 127,900,000.00

3.1. BIAYA KANTOR 25,000,000.00

3.2. PERALATAN KANTOR 18,900,000.00

3.3. PERALATAN LAPANGAN 84,000,000.00

IV BAHAN-BAHAN HABIS PAKAI 15,125,000.00

4.1. BAHAN-BAHAN KANTOR 13,800,000.00

4.2. BAHAN-BAHAN LAPANGAN 1,325,000.00

V BIAYA PENGADAAN CITRA DAN RBI 100,550,000.00

5.1. PENGADAAN FOTO UDARA 100,000,000.00

5.2. PETA RUPA BUMI (BAKOSURTANAL) 550,000.00

VI BIAYA REPRODUKSI DOKUMEN 4,250,000.00

SUB TOTAL 681,825,000.00

PPN 10% 68,182,500.00

TOTAL 750,007,500.00

DIBULATKAN 750,000,000.00

Terbilang :

TUJUH RATUS LIMA PULUH JUTA RUPIAH

Page 2: Rab

BILL OF QUANTITY

( B O Q )

Pekerjaan : Inventarisasi penginderaan jarak jauh Danau tempe kabupaten wajo

Tahun Anggaran : 2015

I. BIAYA PERSONIL

JUMLAH LAMA BEBAN BIAYA JUMLAH

NO. POSISI PERSONIL SATUAN PENUGASAN PERSONIL BIAYA

(ORANG) (BULAN) (Rp.) (Rp.)

1.1. TENAGA AHLI

1. Team Leader 1 Bln/Org 4 12,000,000.00 48,000,000.00

2. Sistem Analisis GIS 1 Bln/Org 4 10,000,000.00 40,000,000.00

3. Geodetic Engineer 1 Bln/Org 4 10,000,000.00 40,000,000.00

4. Ahli Penginderaan Jauh/Remote Sensing 1 Bln/Org 4 10,000,000.00 40,000,000.00

5. Ahli Pengolahan Citra Digital 1 Bln/Org 4 10,000,000.00 40,000,000.00

SUB TOTAL 1.1. 208,000,000.00

1.2. TENAGA SUB PROFESIONAL

1. Assisten Analisis GIS 1 Bln/Org 4 8,000,000.00 32,000,000.00

2. Asisten Geodetic Engineer 1 Bln/Org 4 8,000,000.00 32,000,000.00

3. Assisten Penginderaan Jauh/Remote Sensing 1 Bln/Org 4 8,000,000.00 32,000,000.00

4. Asisten Pengolahan Citra Digital 1 Bln/Org 4 8,000,000.00 32,000,000.00

5. Surveyor 1 Bln/Org 4 3,000,000.00 12,000,000.00

6. Draftman 1 Bln/Org 4 3,000,000.00 12,000,000.00

SUB TOTAL 1.2. 152,000,000.00

JUMLAH LAMA BEBAN BIAYA JUMLAH

NO. POSISI PERSONIL SATUAN PENUGASAN PERSONIL BIAYA

(ORANG) (BULAN) (Rp.) (Rp.)

1.3. TENAGA PENUNJANG

1. Office Manager 1 Bln/Org 4 3,500,000.00 14,000,000.00

4. Administrasi 1 Bln/Org 4 3,500,000.00 14,000,000.00

5. Driver 1 Bln/Org 4 1,500,000.00 6,000,000.00

6. Tenaga Lokal 6 Bln/Org 2 1,000,000.00 12,000,000.00

SUB TOTAL 1.3. 46,000,000.00

Page 3: Rab

II. BIAYA TRANSPORTASI

HARGA JUMLAH

NO. URAIAN JUMLAH SATUAN VOLUME SATUAN BIAYA

(Bulan) (Rp.) (Rp.)

2.1. SEWA KENDARAAN

1. Kendaraan Roda 4 1 Unit 4 5,000,000.00 20,000,000.00

2. Kendaraan Roda 2 2 Unit 4 1,000,000.00 8,000,000.00

SUB TOTAL 2.1. 28,000,000.00

HARGA JUMLAH

NO. URAIAN SATUAN VOLUME SATUAN BIAYA

(Rp.) (Rp.)

2.2. BIAYA PERJALANAN DINAS

1. Team Leader Hari 30 250,000.00 7,500,000.00

2. Sistem Analisis GIS Hari 30 200,000.00 6,000,000.00

3. Geodetic Engineer Hari 30 200,000.00 6,000,000.00

4. Ahli Penginderaan Jauh/Remote Sensing Hari 30 200,000.00 6,000,000.00

5. Ahli Pengolahan Citra Digital Hari 30 200,000.00 6,000,000.00

6. Assisten Analisis GIS Hari 30 150,000.00 4,500,000.00

7. Asisten Geodetic Engineer Hari 30 150,000.00 4,500,000.00

8. Assisten Penginderaan Jauh/Remote Sensing Hari 30 150,000.00 4,500,000.00

9. Asisten Pengolahan Citra Digital Hari 30 150,000.00 4,500,000.00

10. Surveyor Hari 60 100,000.00 6,000,000.00

11. Draftman Hari 60 100,000.00 6,000,000.00

SUB TOTAL 2.2. 61,500,000.00

III. KANTOR DAN PERALATAN

LAMA BIAYA JUMLAH

NO. URAIAN JUMLAH SATUAN SEWA SEWA BIAYA

(BULAN) (Rp.) (Rp.)

3.1. BIAYA KANTOR

1. Sewa Basecamp 1 Bulan 4 4,000,000.00 16,000,000.00

2. Telpon/Fax 1 Bulan 4 750,000.00 3,000,000.00

3. Biaya Listrik, Air dan Perawatan 1 Bulan 4 1,000,000.00 4,000,000.00

4. Biaya Komunikasi dan surat 1 Bulan 4 500,000.00 2,000,000.00

SUB TOTAL 3.1. 25,000,000.00

LAMA BIAYA JUMLAH

NO. URAIAN JUMLAH SATUAN SEWA SEWA BIAYA

(BULAN) (Rp.) (Rp.)

3.2. PERALATAN KANTOR

1. Meja Tulis + Kursi 3 Set 4 250,000.00 3,000,000.00

2. Komputer + Printer 4 Unit 4 500,000.00 8,000,000.00

3. Plotter 1 Unit 4 1,250,000.00 5,000,000.00

4. Roll Meter 4 buah 4 75,000.00 1,200,000.00

5. Kompas 3 buah 4 75,000.00 900,000.00

6. Kamera Digital 2 buah 4 100,000.00 800,000.00

SUB TOTAL 3.2. 18,900,000.00

Page 4: Rab

LAMA BIAYA JUMLAH

NO. URAIAN JUMLAH SATUAN SEWA SEWA BIAYA

(Hari) (Rp.) (Rp.)

3.3. PERALATAN LAPANGAN

1. GPS GEODETIK 1 Set 60 1,200,000.00 72,000,000.00

EPOCH L1

2. GPS HAND (GARMIN) 2 unit 60 100,000.00 12,000,000.00

SUB TOTAL 3.3. 84,000,000.00

A68
ANDIRA:
Page 5: Rab

IV. BAHAN-BAHAN HABIS PAKAI

HARGA JUMLAH

NO. URAIAN JUMLAH SATUAN SATUAN BIAYA

(Rp.) (Rp.)

4.1. BAHAN-BAHAN KANTOR

1. Kertas HVS 10 Rim 40,000.00 400,000.00

2. Kertas Milimeter 5 Roll 80,000.00 400,000.00

3. Kertas Kalkir 5 Roll 600,000.00 3,000,000.00

4. Tinta Printer A0 6 Buah 400,000.00 2,400,000.00

5. Tinta Printer Photo warna 12 Buah 300,000.00 3,600,000.00

6. Hardisk 2 Buah 1,000,000.00 2,000,000.00

7. ATK Ls - 2,000,000.00 2,000,000.00

SUB TOTAL 4.1. 13,800,000.00

HARGA JUMLAH

NO. URAIAN JUMLAH SATUAN SATUAN BIAYA

(Rp.) (Rp.)

4.2. BAHAN-BAHAN LAPANGAN

1. Patok Beton (BM) 4 buah 300,000.00 1,200,000.00

2. Buku Ukur 5 buah 25,000.00 125,000.00

SUB TOTAL 4.2. 1,325,000.00

V. BIAYA PENGADAAN

HARGA JUMLAH

NO. URAIAN JUMLAH SATUAN VOLUME SATUAN BIAYA

(Rp.) (Rp.)

5.1. PENGADAAN FOTO UDARA

Pengadaan Foto Udara 1 ls 1 100,000,000.00 100,000,000.00

SUB TOTAL 5.1 100,000,000.00

HARGA JUMLAH

NO. URAIAN JUMLAH SATUAN VOLUME SATUAN BIAYA

(Rp.) (Rp.)

5.2. PETA RUPA BUMI (BAKOSURTANAL)

Peta Skala 1 : 50.000 Hardcopy 1 Sheet 2 50,000.00 100,000.00

Peta Skala 1 : 50.000 Softcopy 1 Sheet 1 450,000.00 450,000.00

SUB TOTAL 5.2 550,000.00

VI. BIAYA REPRODUKSI LAPORAN

HARGA JUMLAH

NO. URAIAN SATUAN VOLUME SATUAN BIAYA

(Rp.) (Rp.)

6.1. BIAYA REPRODUKSI DOKUMEN

1. Laporan Pendahuluan Eksam. 5 150,000.00 750,000.00

2. Laporan Bulanan Eksam. 5 150,000.00 750,000.00

3. Laporan Antara Eksam. 5 150,000.00 750,000.00

5. Laporan Final Eksam. 10 200,000.00 2,000,000.00

Page 6: Rab

SUB TOTAL 6.1 4,250,000.00

Page 7: Rab

Kurva - S"Inventarisasi penginderaan jarak jauh Danau tempe kabupaten wajo"

NO KEGIATAN

BULAN KE-

KETERANGANI II

1 2 3 4 1 2 3 4I. PERSIAPAN

I.1 Mobilisasi 8.00 8.00 8.00 8.00

I.2 Pengumpulan data Sekunder 12.00 12.00 12.00 12.00

II. PEKERJAAN SURVEY dan PENGUKURAN II.1 Orientasi Lapangan 7.00 7.00

7.00 7.00 II.2 Pemangan BM 10.00 5.00 5.00

10.00 4.00 4.00 2.00 II.3 Survey DGPS dan Pengukuran Profil Lintasan 15.00 7.50 7.50

15.00 5.00 5.00 5.00 III. ANALISA & PENGOLAHAN DATA III.1 Analisa Data Dasar 8.00 8.00

8.00 2.00 6.00 III.2 Analisa Hasil Data Pengukuran 8.00 4.00 4.00

8.00 2.00 3.00 3.00 III.3 Digitasi dan Penggambaran Topografi 10.00 5.00 5.00

10.00 5.00 5.00 IV. LAPORAN IV.1 Laporan Pendahuluan 4.00 4.00

4.00 4.00 IV.2 Laporan Bulanan 6.00 3.00 3.00

6.00 3.00 3.00 IV.3 Laporan Final 4.00 4.00

4.00 4.00 IV.4 Gambar 8.00 8.00

8.00 8.00 Rencana Kemajuan Pekerjaan % 100.00 8.00 12.00 19.50 19.50 12.00 9.00 5.00 15.00 Komulatif Rencana % 0 8.00 20.00 39.50 59.00 71.00 80.00 85.00 100.00 Realisasi Kemajuan Pekerjaan % 100.00 8.00 12.00 16.00 20.00 16.00 8.00 5.00 15.00 Komulatif Realisasi % 0 8.00 20.00 36.00 56.00 72.00 80.00 85.00 100.00 Deviasi % - - (3.50) (3.00) 1.00 - - -

Bobot Rencana (%)

Bobot Realisasi (%)

0

10

20

30

40

50

60

70

80

90

100

Page 8: Rab

RINCIAN BIAYA BEBAN PERSONIL

Pekerjaan : Pemetaan Batas Daerah Genangan Bendung Gerak Danau TempeNama Perusahaan : PT. Geomatik Consultant

No Nama Jabatan

Rincian Biaya Remunerasi

Gaji Dasar

1 2 3 4 5 6 7 8 9 10 PROFESIONAL STAFF

1 Ir. Muhammad Haris, MSc Team Leader 2,200,000.00 880,000.00 2,860,000.00 5,940,000.00 500,000.00 560,000.00 7,000,000.00 2 Ir. Reza Martani Surdia Sistem Analisis GIS 1,900,000.00 760,000.00 2,280,000.00 4,940,000.00 490,000.00 570,000.00 6,000,000.00 3 Ir. Ricky Rukmandar Geodetic Engineer 1,600,000.00 640,000.00 1,920,000.00 4,160,000.00 360,000.00 480,000.00 5,000,000.00 4 Ir. Agus Firmansyah Ahli Penginderaan Jauh/Remote Sensing 1,600,000.00 640,000.00 1,920,000.00 4,160,000.00 360,000.00 480,000.00 5,000,000.00 5 Rahmat Agus Nursamsi, S.Kom Ahli Pengolahan Citra Digital 1,600,000.00 640,000.00 1,920,000.00 4,160,000.00 360,000.00 480,000.00 5,000,000.00

Catatan :

Lajur 4 : Gaji Dasar (GD) meliputi gaji bruto yang senyatanya sebelum dipotng pajak pendapatan dan daftar gaji masing-masing personil yang diusulkan harus disertakanLajur 5 : Beban Biaya Sosial harus mencakup konstribusi perusahaan terhadap Asuransi Tenaga Kerja, tunjangan liburan yang dibayar, cuti sakit dan tunjangan standar lainnya yang dibayarkan oleh perusahaan konsultan kepada personil sebagai karyawan Rincian Biaya yang diusulkan harus diajukan dan didukung oleh penjelasan yang besarnya 0,3 s.d 0,4 kali (GD)Lajur 6 : Beban Biaya Umum (BBU) harus meliputi biaya administrasi umum biaya sewa kantor, biaya tata usaha, dan staf junior dan biaya Usaha untuk memperoleh pekerjaan dll. Rincian Biaya yang diusulkan harus diajukan dan didukung oleh penjelasan yang besarnya 0,5 s.d 1,3 kali (GD)Lajur 8 : Imbalan jasa mencakup keuntungan perusahaan termasuk pajak perusahaan, deviden bonus, dana cadangan dan investasi sebesar 0,1 kali (GD+BBS+BBU)Lajur 9 : Tunjangan Penugasan merupakan insentif yang senyatanya dibayarkan kepada personil yang tinggal ditempat tugas yang besarnya antara 0,1 s.d 0,3 (GD)Lajur 10 : Beban Biaya Personil perbulan antara 2,2 s.d 3,1 kali (GD) Pekerjaan lapangan meliputi semua lokasi di Indonesia Makassar, 24 Oktober 2011

Diaudit Oleh :AKUNTAN

PT. Geomatik Consultant HAKIM MURNI & REKAN

Ir. Anto BasriDirektur Utama Drs. AHMAD ALI, Ak

Reg. Neg. 710

Remunerasi Per-Bulan (7+8+9)

Beban Biaya Sosial (40% dari 4)

Beban Biaya Umum (130% dari 4)

Sub Total (4+5+6)

Imbalan Jasa (10%dari 7)

Tunjangan Proyek (30%

dari 4)