R E K A P I T U L A S I DAFTAR KUANTITAS DAN HARGA
KEGIATAN : PEMBANGUNAN RKB
PEKERJAAN : PEMBANGUNAN RKB MDT NURUL IKHLAS DESA xxxxxxxxxx KEC. Xxxxxxx
LOKASI : KECAMATAN xxxxxxxxxxxxx KABUPATEN xxxxxxxxxxx
TAHUN : 2013
NO URAIAN PEKERJAAN JUMLAH HARGA
I. PEKERJAAN PENDAHULUAN 7,544,440.00
II. PEKERJAAN TANAH DAN PASIR 8,216,832.96
III. PEKERJAAN BETON DAN PASANGAN 84,314,124.41
IV. PEK. KAYU DAN KUNSEN 12,883,352.25
V. PEK. RANGKA KAP DAN ATAP 85,616,735.88
VI. PEKERJAAN INSTALASI LISTRIK 3,463,575.00
VII. PEKERJAAN GANTUNGAN DAN KUNCI 2,544,489.00
VIII. PEKERJAAN PENGECATAN 9,522,044.58
IX. PEKERJAAN PEMBUATAN KM/WC 24,016,055.80
JUMLAH 238,121,649.87
PPn 10 % 23,812,164.99
JUMLAH TOTAL 261,933,814.86
DIBULATKAN 261,933,000.00
xxxxxxxxxxxxxxxxxxxx
xxxxxxxxxxx, 29 Juli 2013
Dibuat Oleh,Kontraktor Pelaksana :
xxxxxxxxxxxxxxxxxxxx
xxxxxxxxxxxxxxxxxxxDirektur
Terbilang :
DAFTAR HARGA SATUAN JADI
### #REF!KEGIATAN : PEMBANGUNAN RKB PEKERJAAN : PEMBANGUNAN RKB MDT NURUL IKHLAS DESA xxxxxxxxxx KEC. Xxxxxxx
NO URAIAN PEKERJAAN SATUAN
1. #REF! #REF! #REF!
2. #REF! #REF! #REF!
3. #REF! #REF! #REF!
4. #REF! #REF! #REF!
5. #REF! #REF! #REF!
6. #REF! #REF! #REF!
7. #REF! #REF! #REF!
8. #REF! #REF! #REF!
9. #REF! #REF! #REF!
10. #REF! #REF! #REF!
11. #REF! #REF! #REF!
12. #REF! #REF! #REF!
13. #REF! #REF! #REF!
14. #REF! #REF! #REF!
15. #REF! #REF! #REF!
16. #REF! #REF! #REF!
xxxxxxxxxxx, 29 Juli 2013
0 Dibuat Oleh,0
0 xxxxxxxxxxxxxxxxxxx0 Direktur
HARGA SATUAN
(Rp.)
DAFTAR KUANTITAS DAN HARGA
KEGIATAN : PEMBANGUNAN RKB PEKERJAAN : PEMBANGUNAN RKB MDT NURUL IKHLAS DESA xxxxxxxxxx KEC. XxxxxxxLOKASI : KECAMATAN xxxxxxxxxxxxx KABUPATEN xxxxxxxxxxxTAHUN : 2013
NO URAIAN PEKERJAAN SAT
1 2 3 4 5 6
I. PEKERJAAN PENDAHULUAN
1 Pek. Persiapan, Pembersihan Awal Dan Akhir Pekerjaan 1.00 Ls 1,000,000.00 1,000,000.00
2 Pek. Pasangan Bowplank 58.00 M' 48,180.00 2,794,440.00
3 Pek. Papan Nama Proyek 1.00 Ls 250,000.00 250,000.00
4 Pek. Dokumentasi 1.00 Ls 1,000,000.00 1,000,000.00
5 Pek. Barak Kerja Sementara 1.00 Ls 2,000,000.00 2,000,000.00
6 Air Kerja 1.00 Ls 500,000.00 500,000.00
JUMLAH I 7,544,440.00
II. PEKERJAAN TANAH DAN PASIR
1 Pek. Galian Tanah Pondasi 20.952 M3 22,400.00 469,324.80
2 Pek. Urugan Kembali Tanah Pondasi 6.984 M3 10,740.00 75,008.16
3 Pek. Pasir Urug Dibawah Lantai Dan Pondasi 13.750 M3 111,600.00 1,534,500.00
4 Pek. Timbunan Tanah Didatangkan ( Bawah lantai ) 49.500 M3 124,000.00 6,138,000.00
JUMLAH II 8,216,832.96
III. PEKERJAAN BETON DAN PASANGAN
1 Pek. Pasangan Pondasi Beton Cor 1 : 2 : 3 9.030 M3 814,305.00 7,353,174.15
2 Pek. Pasangan Pondasi Tapak Beton Btl. 1 : 2 : 3 ( Besi 150 Kg ) 0.835 M3 3,268,395.00 2,729,109.82
3 Pek. Balok Sloof 15 / 20 Beton Btl. 1 : 2 : 3 ( Besi 200 Kg ) 1.638 M3 4,362,505.00 7,145,783.19
4 Pek. Tiang Kolom 20 X 20 cm Beton Btl. 1 : 2 : 3 ( Besi 150 Kg ) 1.264 M3 4,264,555.00 5,390,397.52
5 Pek. Pasangan Batu Alam Tiang Teras 3.360 M2 224,860.00 755,529.60
6 Pek. Profil Tiang Kolom Teras 1.000 Ls 300,000.00 300,000.00
7 Pek. Tiang Kolom Praktis Beton Bertulang Uk. 11 x 11 cm 36.300 M' 83,355.59 3,025,807.83
8 Pek. Ring Balok Beton Beton Bertulang Uk. 10 x 15 cm 92.500 M' 71,031.32 6,570,396.95
9 Pek. Pasangan Dinding 1/2 Bata 1 : 4 ### M2 92,220.00 14,663,902.20
10 Pek. Plesteran Dinding 1 : 4 ### M2 44,335.00 13,257,096.04
11 Pek. Cor Lantai Selasar Dan Teras Beton 1 : 3 : 5 Tebal 7 cm Diaci 6.300 M3 591,450.00 3,726,135.00
12 Pek. Pasangan Lantai Dalam Dan Teras ( Keramik 30 x 30 cm ) ### M2 118,900.00 16,324,256.60
13 Pek. Pasangan Dinding 1/2 Bata 1 : 3 ( Saluran Air ) 14.500 M2 98,755.00 1,431,947.50
14 Pek. Plesteran 1 : 3 ( Saluran Air ) 29.000 M2 56,572.00 1,640,588.00
JUMLAH III 84,314,124.41
IV. PEK. KAYU DAN KUSEN
1 Pek. Konsen Pintu, Jendela, (Kayu Kulim ) 0.711 M3 5,770,750.00 4,103,003.25
2 Pek. Pas. Konsen Ventilasi Silang ( Kayu Kulim ) 40.000 Unit 43,280.63 1,731,225.00
3 Pek. Daun Pintu Panil 5.100 M2 390,500.00 1,991,550.00
4 Pek. Daun Jendela Kaca 15.000 M2 319,600.00 4,794,000.00
5 Pek. Pas Ram Jalusi Kayu Klass II 1.080 M2 244,050.00 263,574.00
JUMLAH IV 12,883,352.25
V. PEK. RANGKA KAP DAN ATAP
1 Pek. Pasangan Rangka Atap Baja Ringan ### M2 183,759.50 45,021,077.50
2 Pek. Pasangan Atap Genteng Metal ### M2 54,860.00 13,440,700.00
3 Pek. Bumbungan Genteng Metal 18.250 M' 30,250.00 552,062.50
4 Pek. Listplang 76.000 M' 62,850.00 4,776,600.00
5 Pek. Rangka Plapond ### M2 64,650.00 12,340,133.40
6 Pek. Plapond GRC T = 4 mm ### M2 34,980.00 6,676,842.48
7 Pek. List Plapond Kayu Profil L = 3 cm ### M' 17,130.00 2,809,320.00
VOLUME
HARGA SATUAN
(Rp.)
JUMLAH HARGA
(Rp.)
JUMLAH V 85,616,735.88
VI. PEKERJAAN INSTALASI LISTRIK
1 Pek. Instalasi Listrik dan Cahaya 17.000 Ttk 155,250.00 2,639,250.00
2 Pek. Lampu XL 20 Watt ( Lampu Hemat Energi ) 10.000 Bh 50,600.00 506,000.00
3 Pek. Stop Kontak 2.000 Bh 37,450.00 74,900.00
4 Pek. Saklar Ganda 2.000 Bh 37,450.00 74,900.00
5 Pek. Saklar Tunggal 2.000 Bh 32,450.00 64,900.00
6 Pek. MCB 1.000 Bh 103,625.00 103,625.00
JUMLAH VI 3,463,575.00
VII. PEKERJAAN GANTUNGAN DAN KUNCI
1 Pek. Kunci Pintu 2 Slaag 3.000 Bh 119,475.00 358,425.00
2 Pek. Engsel Pintu 4 " 9.000 Bh 31,248.00 281,232.00
3 Pek. Engsel Jendela 3 " 24.000 Bh 28,248.00 677,952.00
4 Hak Angin 24.000 Bh 20,748.00 497,952.00
5 Pek. Grendel Jendela 24.000 Bh 21,248.00 509,952.00
6 Tarikan Jendela 12.000 Bh 18,248.00 218,976.00
JUMLAH VII 2,544,489.00
VIII. PEKERJAAN PENGECATAN
1 Pek. Cat Tembok ### M2 13,975.00 4,500,802.48
2 Pek. Cat Plapond ### M2 13,975.00 2,667,492.10
3 Pek. Cat Kilat ( Pintu,Jendela, Kunsen, dan Listplang ) 62.500 M2 37,660.00 2,353,750.00
JUMLAH VIII 9,522,044.58
NO URAIAN PEKERJAAN SAT
1 2 3 4 5 6
IX. PEKERJAAN PEMBUATAN KM/WC
1 Pek. Galian Tanah Pondasi 2.800 M3 22,400.00 62,720.00
2 Pek. Urugan Kembali Tanah Pondasi 1.440 M3 10,740.00 15,465.60
3 Pek. Pasangan Pondasi Beton Cor 1 : 2 : 3 0.960 M3 814,305.00 781,732.80
4 Pek. Tiang Kolom Praktis 11 x 11 cm 12.250 M' 83,355.59 1,021,105.95
5 Pek. Pasangan Dinding Bata 1 : 4 22.900 M2 92,220.00 2,111,838.00
6 Pek. Plesteran 1 : 4 36.600 M2 44,335.00 1,622,661.00
7 Pek. Konsen Pintu 0.072 M3 5,770,750.00 415,494.00
8 Pek. Daun Pintu Panil 2.800 M2 390,500.00 1,093,400.00
9 Pek. Pas. Kunci Pintu 2.000 Unit 119,475.00 238,950.00
10 Pek. Pas. Engsel Pintu 6.000 Unit 31,248.00 187,488.00
11 Pek. Pas. Rangka Atap Baja Ringan 15.600 M2 183,759.50 2,866,648.20
12 Pek. Pasangan Atap Genteng Metal 15.600 M2 54,860.00 855,816.00
13 Pek. Bumbungan Genteng Metal 4.000 M' 30,250.00 121,000.00
14 Pek. Listplang 15.000 M' 62,850.00 942,750.00
15 Pek. Rangka Plapond 8.750 M2 64,650.00 565,687.50
16 Pek. Plapond 18.250 M2 34,980.00 638,385.00
17 Pek. Kaca Es T = 5 mm Utk. Ventilasi 0.490 M2 123,245.00 60,390.05
18 Pek. Pas. Lantai Beton Cor 1 : 3 : 5 Diaci Tebal 10 cm 0.650 M3 591,450.00 384,442.50
19 Pek. Pas. Dinding Keramik 20 x 20 cm T = 120 cm 7.637 M2 113,900.00 869,854.30
20 Pek. Pasangan Lantai Keramik WC 20 x 20 cm 4.488 M2 138,370.00 621,004.56
21 Pek. Pas. Bak Air Fibber 2.000 Unit 666,800.00 1,333,600.00
22 Pek. Pas. Closet Jongkok 2.000 Unit 369,100.00 738,200.00
23 Pek. Pas. Kran Air 2.000 Unit 44,162.50 88,325.00
24 Pas. Floor Drain 2.000 Unit 24,100.00 48,200.00
25 Pek. Pas. Pipa Paralon, Sambungan, Lem + Upah 1.000 Ls 150,000.00 150,000.00
26 Pek. Pembuatan Septic tank 1.000 Ls 1,591,017.14 1,591,017.14
27 Pek. Pembutan Sumur Gali Dalam 6 M + ( Beton Gorong Dia + 80 1.000 Ls 1,250,000.00 1,250,000.00
28 Pek. Pas. Pompa Air ( Upah Pasang ) 1.000 Ls 2,500,000.00 2,500,000.00
29 Pek. Cat Tembok 36.600 M2 13,975.00 511,485.00
30 Pek. Cat Kilat 8.720 M2 37,660.00 328,395.20
JUMLAH IX 24,016,055.80
xxxxxxxxxxx, 29 Juli 2013
Dibuat Oleh,
Kontraktor Pelaksana :
xxxxxxxxxxxxxxxxxxxx
xxxxxxxxxxxxxxxxxxx
Direktur
VOLUME
HARGA SATUAN
(Rp.)
JUMLAH HARGA
(Rp.)
R E K A P I T U L A S I
KEGIATAN : PENGADAAN SARANA DAN PRASARANA PUSKESMAS PEKERJAAN : REVITALISASI PUSKESMAS PERAWATAN KWANDANGLOKASI : KECAMATAN KWANDANG KABUPATEN GORONTALO UTARASUMBER DANA : DAK/DAUTAHUN ANGGARAN : 2009
NO JENIS PEKERJAAN
A. PEKERJAAN PERSIAPAN
B. PEMBANGUNAN GEDUNG RAWAT JALAN
C. PEMBANGUNAN GEDUNG RAWAT INAP
D. PEKERJAAN KORIDOR PENGHUBUNG
E. PEKERJAAN LAIN - LAIN
A. SUB TOTAL
B. PPN 10 %
C. IMB
( A + B + C) TOTAL
DIBULATKAN
Terbilang : " Satu Milyar Enam Ratus Satu Juta Enam Ratus Ribu Rupiah "
Kwandang, 23 Maret 2009Mengetahui
PT. PERDANA PUTRA BAJATAMA Dibuat Oleh
ABDUL RASYID ABAS xxxxxxxxxxxxxDirektur Pimpinan Teknik
R E K A P I T U L A S I
: PENGADAAN SARANA DAN PRASARANA PUSKESMAS : REVITALISASI PUSKESMAS PERAWATAN KWANDANG: KECAMATAN KWANDANG KABUPATEN GORONTALO UTARA
HARGA (Rp)
14,850,000.00
#REF!
#REF!
12,000,000.00
4,500,000.00
#REF!
#REF!
13,410,000.00
#REF!
#REF!
Terbilang : " Satu Milyar Enam Ratus Satu Juta Enam Ratus Ribu Rupiah "
Kwandang, 23 Maret 2009
Dibuat Oleh
xxxxxxxxxxxxxPimpinan Teknik
RENCANA ANGGARAN BIAYA (RAB)
KEGIATAN : PENGADAAN SARANA DAN PRASARANA PUSKESMAS PEKERJAAN : REVITALISASI PUSKESMAS PERAWATAN KWANDANGLOKASI : KECAMATAN KWANDANG KABUPATEN GORONTALO UTARASUMBER DANA : DAK/DAUTAHUN ANGGARA: 2009
NO URAIAN PEKERJAAN SATUAN VOL HARGASATUAN
( Rp.)
A. PEKERJAAN PERSIAPAN1 Pekerjaan Pembuatan Papan Nama Proyek Ls 1.00 500,000.00 2 Pembersihan awal Ls 1.00 1,000,000.00 3 Pembongkaran Bangunan Lama Ls 1.00 6,000,000.00 4 Biaya administrasi / dokumentasi Ls 1.00 1,500,000.00 5 Pekerjaan Penyediaan Air Kerja Ls 1.00 2,000,000.00 6 Biaya Pemindahan/Pasang Meteran PLN Lama Ls 1.00 350,000.00 7 Direksi Keet Ls 1.00 3,000,000.00
B. PEMBANGUNAN GEDUNG RAWAT JALAN I PEKERJAAN TANAH DAN URUGAN1 Galian tanah untuk pondasi M³ 103.68 22,400.00 2 Urugan tanah kembali M³ 34.56 - 3 Pekerjaan Timbunan lantai M³ 79.65 #REF!4 Urugan pasir dibawah Pondasi dan lantai M³ 23.90 #REF!
II PEKERJAAN PONDASI 1 Pasangan batu kosong / aanstamping M³ 13.30 #REF!2 Pas. pondasi batu kali camp 1 : 4 M³ 61.66 #REF!
III PEKERJAAN BETON 1 Pekerjaan Cor Lantai Kerja 1 : 3 : 5 M³ 12.39 - 2 Pekerjaan Beton Pondasi Tapak M³ 7.88 #REF!3 Pek. Lantai Beton Bertulang 1:2:3 M³ 18.72 #REF!4 Pek. Beton Sloof 20/25 M³ 6.20 #REF!5 Pek. Beton Kolom K1 30/30 M³ 5.26 #REF!6 Pek. Beton Kolom K2 20/30 M³ 0.46 #REF!7 Pek. Beton Kolom K3 20/20 M³ 2.34 #REF!8 Pek. Beton Kolom K4 11/20 M³ 0.10 #REF!9 Pek. Beton Kolom Praktis 12/12 M³ 3.57 #REF!10 Pek. Beton Balok B1 25/40 M³ 10.80 #REF!11 Pek. Beton Balok B2 20/30 M³ 0.24 #REF!12 Pek. Beton Balok B3 15/20 M³ 2.55 #REF!13 Pek. Beton Balok Ring 15/20 M³ 5.58 #REF!14 Pek. Beton Balok Bordes 25/20 M³ 0.25 #REF!15 Pek. Beton Balok Latei 12/15 M³ 2.84 #REF!16 Pek. Lisplank Beton M³ 31.53 #REF!17 Pek. Tangga/Bordes Beton M³ 1.33 #REF!18 Pekerjaan Beton Plat Level M³ 1.72 #REF!19 Pekerjaan Beton Plat Meja M³ 0.12 #REF!
IV PEKERJAAN PAS. DINDING DAN PLESTERAN1 Pas. Tembok bt. Bata trasram camp. 1Pc : 3Ps M² 67.89 #REF!2 Pas. Tembok bt. Bata camp. 1Pc : 5Ps M² 583.69 #REF!3 Plesteran tembok trasram camp. 1Pc : 3Ps M² 135.78 #REF!4 Plesteran tembok biasa camp. 1Pc : 5Ps M² 1,109.01 #REF!5 Pekerjaan Acian M² 1,244.79 #REF!6 Pek. Papan Nama Stainless Steel Ls 1.00 1,000,000.00
V PEKERJAAN PINTU JENDELA DAN VENTILASI1 Pek. Kusen pintu dan jendela Aluminium M' 741.64 #REF!
NO URAIAN PEKERJAAN SATUAN VOL HARGASATUAN
( Rp.)
2 Pek. Bingkai Jendela Aluminium M' 582.88 #REF!3 Pas. Pintu Panel Aluminium/Kaca M² 31.74 #REF!4 Pas. Sekat Multipleks 5 mm M² 31.50 #REF!5 Pas. Pintu PVC Set 5.00 #REF!6 Pas. Kaca polos t = 4,5 mm M² 73.15 #REF!7 Pas. Railling Stainless Balkon M' 22.00 375,000.00
VI PEKERJAAN ATAP1 Pekerjaan Kuda-Kuda Kayu Kelas II M³ 6.79 #REF!2 Pekerjaan Rangka Atap Kayu Kelas II M² 172.90 #REF!3 Pekerjaan Atap Genteng Sakura Roof M² 172.90 #REF!4 Pekerjaan Nok Genteng Sakura Roof M' 64.74 #REF!5 Pekerjaan Lisplank Kayu M' 9.00 #REF!
VII PEKERJAAN PLAFOND1 Pekerjaan Pasangan rangka Plafond M² 409.94 #REF!2 Pekerjaan Plafond Tripleks 3 mm M² 409.94 #REF!3 Pekerjaan Lis Plafon Sp. 3 M' 388.00 -
VIII PEKERJAAN KERAMIK 1 Pas. Keramik 40 x 40 cm polos M² 324.20 #REF!2 Pas. Keramik 20 x 20 cm KM/WC M² 9.50 #REF!3 Pas. Keramik Dinding 20 x 25 cm KM/WC/Meja Beton M² 27.90 #REF!
IX PEKERJAAN GANTUNGAN DAN KUNCI 1 Pas. Engsel Pintu Psg 22.00 #REF!2 Pas. Engsel Jendela Psg 150.00 #REF!3 Pas. Kunci 3 Lever Bh 22.00 #REF!4 Pas. Grendel Tanam Bh 150.00 #REF!5 Pas. Hak Angin Psg 150.00 #REF!6 Pas. Ekspagnyolet Stainless Psg 10.00 #REF!7 Pas. Door Closer Psg 22.00 #REF!
X PEKERJAAN PERLENGKAPAN DALAM Pekerjaan Instalasi Listrik
1 Pasang MCB 6 grup Bh 6.00 #REF!2 Penyambungan Kabel Listrik Ls 1.00 350,000.00 3 Pasangan Lampu Pijar 25 Watt Unit 6.00 #REF!4 Pasangan Lampu SL Philips 18 Watt + Downlight Unit 18.00 #REF!5 Pasangan Lampu SL Philips 18 Watt Unit 25.00 #REF!6 Lampu TL Armateur 2 x 36 Watt Unit 26.00 #REF!7 Pasangan Saklar Doubel Unit 24.00 #REF!8 Pasangan Saklar Tunggal Unit 10.00 #REF!9 Pasangan Stop Kontak Unit 38.00 #REF!10 Pasangan Instalasi Titik Lampu Ttk 75.00 #REF!
Pekerjaan Sanitasi Dan Instalasi Air 1 Pasangan Floor Drain Bh 5.00 #REF!2 Pasangan Pipa VE 0,5" (Air Bersih) M1 102.00 #REF!3 Pasangan Pipa VE 2" (Air Kotor) M1 94.00 #REF!4 Pasangan Pipa VE 3" (Air Hujan) M1 211.50 #REF!5 Pasangan Pipa VE 4" (Air Kotor) M1 40.00 #REF!6 Pasangan Kran Air Bh 11.00 #REF!7 Pasangan Kloset Duduk Bh 5.00 #REF!8 Pasangan Wastafel Bh 6.00 #REF!9 Pasang Septic tank dan peresapan Unit 1.00 #REF!10 Pasang Saluran Air Hujan M' 58.00 #REF!
XI PEKERJAAN PENGECATAN1 Pek. Pengecatan Tembok Dan Plafond M² 1,654.73 #REF!2 Pek. Pengecatan Lisplank Kayu M² 4.50 #REF!3 Pek. Pengecatan Waterproofing Lisplank Beton M² 192.20 #REF!
C. PEMBANGUNAN GEDUNG RAWAT INAP
NO URAIAN PEKERJAAN SATUAN VOL HARGASATUAN
( Rp.)
I PEKERJAAN TANAH DAN URUGAN1 Galian tanah untuk pondasi M³ 120.62 22,400.00 2 Urugan tanah kembali M³ 40.21 - 3 Pekerjaan Timbunan lantai M³ 135.90 #REF!4 Urugan pasir dibawah Pondasi dan lantai M³ 36.36 #REF!
II PEKERJAAN PONDASI 1 Pasangan batu kosong / aanstamping M³ 20.27 #REF!2 Pas. pondasi batu kali camp 1 : 4 M³ 94.85 #REF!
III PEKERJAAN BETON 1 Pekerjaan Cor Lantai Kerja 1 : 3 : 5 M³ 21.14 - 2 Pekerjaan Beton Pondasi Tapak M³ 2.63 #REF!3 Pekerjaan Sloef Beton 15/20 M³ 5.91 #REF!4 Pekerjaan Sloef Beton 20/30 M³ 0.96 #REF!5 Pekerjaan Kolom K1 40/40 M³ 2.78 #REF!6 Pekerjaan Kolom K3 25/25 M³ 2.74 #REF!7 Pekerjaan Kolom K2 30/30 M³ 0.66 #REF!8 Pekerjaan Kolom Praktis 12/12 M³ 2.05 #REF!9 Pekerjaan Balok Latei 12/15 M³ 2.20 #REF!10 Pekerjaan Ring Balok 15/20 M³ 5.37 #REF!11 Pekerjaan Ring Balok 20/30 M³ 1.08 #REF!12 Pekerjaan Beton Plat Level M³ 1.19 #REF!13 Pekerjaan Beton Plat Meja M³ 0.21 #REF!14 Pekerjaan Lisplank Beton M³ 21.39 #REF!
IV PEKERJAAN PAS. DINDING DAN PLESTERAN1 Pas. Tembok bt. Bata trasram camp. 1Pc : 3Ps M² 118.77 #REF!2 Pas. Tembok bt. Bata camp. 1Pc : 5Ps M² 454.67 #REF!3 Plesteran tembok trasram camp. 1Pc : 3Ps M² 237.54 #REF!4 Plesteran tembok biasa camp. 1Pc : 5Ps M² 863.86 #REF!5 Pekerjaan Acian M² 1,101.40 #REF!6 Pekerjaan Profil Semen M' 86.92 #REF!
V PEKERJAAN PINTU JENDELA DAN VENTILASI1 Pek. Kusen pintu dan jendela Aluminium M' 293.08 #REF!2 Pek. Bingkai Jendela Aluminium M' 202.70 #REF!3 Pas. Pintu Panel Aluminium/Kaca M² 31.74 #REF!4 Pas. Pintu PVC Set 6.00 #REF!5 Pas. Kaca polos t = 4,5 mm M² 28.24 #REF!
VI PEKERJAAN ATAP1 Pekerjaan Kuda-Kuda Kayu Kelas II M³ 8.15 #REF!2 Pekerjaan Rangka Atap Kayu Kelas II M² 421.78 #REF!3 Pekerjaan Atap Genteng Sakura Roof M² 421.78 #REF!4 Pekerjaan Nok Genteng Sakura Roof M' 60.47 #REF!
VII PEKERJAAN PLAFOND1 Pekerjaan Pasangan rangka Plafond M² 384.00 #REF!2 Pekerjaan Plafond Tripleks 3 mm M² 384.00 #REF!3 Pekerjaan Lis Plafon Sp. 3 M' 361.00 -
VIII PEKERJAAN KERAMIK 1 Pas. Keramik 40 x 40 cm polos M² 253.00 #REF!2 Pas. Keramik 20 x 20 cm KM/WC M² 16.50 #REF!3 Pas. Keramik Dinding 20 x 25 cm KM/WC/Meja Beton M² 15.00 #REF!
IX PEKERJAAN GANTUNGAN DAN KUNCI 1 Pas. Engsel Pintu Psg 18.00 #REF!2 Pas. Engsel Jendela Psg 80.00 #REF!3 Pas. Kunci 3 Lever Bh 4.00 #REF!
NO URAIAN PEKERJAAN SATUAN VOL HARGASATUAN
( Rp.)
4 Pas. Kunci 2 Lever Bh 10.00 #REF!5 Pas. Grendel Tanam Bh 80.00 #REF!6 Pas. Hak Angin Psg 80.00 #REF!7 Pas. Ekspagnyolet Stainless Psg 8.00 #REF!8 Pas. Door Closer Psg 17.00 #REF!
X PEKERJAAN PERLENGKAPAN DALAM Pekerjaan Instalasi Listrik
1 Pasang MCB 5 grup Bh 5.00 #REF!2 Pasangan Lampu Pijar 25 Watt Unit 8.00 #REF!3 Pasangan Lampu SL Philips 18 Watt Unit 17.00 #REF!4 Lampu TL Armateur 2 x 36 Watt Unit 26.00 #REF!5 Pasangan Saklar Doubel Unit 16.00 #REF!6 Pasangan Saklar Tunggal Unit 7.00 #REF!7 Pasangan Stop Kontak Unit 29.00 #REF!8 Pasangan Instalasi Titik Lampu Ttk 51.00 #REF!
Pekerjaan Sanitasi Dan Instalasi Air 1 Pasangan Floor Drain Bh 6.00 #REF!2 Pasangan Pipa VE 0,5" (Air Bersih) M1 65.00 #REF!3 Pasangan Pipa VE 2" (Air Kotor) M1 40.00 #REF!4 Pasangan Pipa VE 4" (Air Kotor) M1 23.00 #REF!5 Pasangan Pipa VE 3" (Air Hujan) M1 122.85 #REF!6 Pasangan Kran Air Bh 9.00 #REF!7 Pasangan Shower Bh 2.00 #REF!8 Pasangan Kran Shower Bh 2.00 #REF!9 Pasangan Kloset Jongkok Bh 4.00 #REF!10 Pasangan Kloset Duduk Bh 2.00 #REF!11 Pasangan Wastafel Bh 4.00 #REF!12 Pasangan Kitchen Zink Bh 1.00 #REF!13 Pasangan Bak Fiberglass Bh 4.00 #REF!14 Pasang Septic tank dan peresapan Unit 3.00 #REF!15 Pasang Saluran Air Hujan M' 66.00 #REF!
XI PEKERJAAN PENGECATAN1 Pek. Pengecatan Tembok Dan Plafond M² 1,485.40 #REF!2 Pek. Pengecatan Waterproofing Lisplank Beton M² 130.38 #REF!
D. PEKERJAAN KORIDOR PENGHUBUNG 1 Selasar Rangka Stainless Steel Atap Polykarbonat Ls 1.00 12,000,000.00
E. PEKERJAAN LAIN - LAIN1 Pembersihan Akhir Ls 1.00 1,000,000.00 2 Asbuilt Drawing Ls 1.00 3,500,000.00
xxxxxxxxxxx, 29 Juli 20130 #REF!0
0 xxxxxxxxxxxxx0 Pimpinan Teknik
RENCANA ANGGARAN BIAYA (RAB)
JUMLAHHARGA( Rp. )
14,850,000.00 500,000.00 1,000,000.00 6,000,000.00 1,500,000.00 2,000,000.00 350,000.00 3,500,000.00
#REF!
2,322,432.00 -
#REF!#REF!
#REF!#REF!
===
- #REF!#REF!#REF!#REF!#REF!#REF!#REF!#REF!#REF!#REF!#REF!#REF!#REF!#REF!#REF!#REF!#REF!#REF!
===
#REF!#REF!#REF!#REF!#REF!
1,000,000.00 =
=#REF!
JUMLAHHARGA( Rp. )
#REF!#REF!#REF!#REF!#REF!
8,250,000.00 =
###=
#REF!#REF!#REF!#REF!#REF!
===
#REF!#REF!
- ===
#REF!#REF!#REF!
==
#REF!#REF!#REF!#REF!#REF!#REF!#REF!
====
#REF! 350,000.00
#REF!#REF!#REF!#REF!#REF!#REF!#REF!#REF!
=#REF!#REF!#REF!#REF!#REF!#REF!#REF!#REF!#REF!#REF!
==
#REF!#REF!#REF!
=
#REF!
JUMLAHHARGA( Rp. )
2,701,888.00 -
#REF!#REF!
#REF!#REF!
==
- #REF!#REF!#REF!#REF!#REF!#REF!#REF!#REF!#REF!#REF!#REF!#REF!#REF!
===
#REF!#REF!#REF!#REF!#REF!#REF!
=
=#REF!#REF!#REF!#REF!#REF!
=###
=#REF!#REF!#REF!#REF!
===
#REF!#REF!
- ===
#REF!#REF!#REF!
==
#REF!#REF!#REF!
JUMLAHHARGA( Rp. )
#REF!#REF!#REF!#REF!#REF!
====
#REF!#REF!#REF!#REF!#REF!#REF!#REF!#REF!
=#REF!#REF!#REF!#REF!#REF!#REF!#REF!#REF!#REF!#REF!#REF!#REF!#REF!#REF!#REF!
==
#REF!#REF!
12,000,000.00 12,000,000.00
4,500,000.00 1,000,000.00 3,500,000.00
=
xxxxxxxxxxx, 29 Juli 2013
ANALISA TEKNIK
I. PEKERJAAN PENDAHULUAN
* Pek. Persiapan, Pembersihan Awal Dan Akhir Pekerjaan 12.0000 Hari
* Pek. Pasangan Bowplank 4.0000 Hari
* Pek. Papan Nama Proyek 1.0000 Hari
* Pek. Dokumentasi Selama Pelaksanaan
* Pek. Barak Kerja Sementara 4.0000 Hari
* Air Kerja 2.0000 Hari
II. PEKERJAAN TANAH DAN PASIR* Pek. Galian Tanah Pondasi
- Volume Pekerjaan = 20.9520 M3- Koefisien Pekerja
- Pekerja = 0.4000 O/H- Mandor = 0.0400 O/H
0.4400
- Jumlah Pekerja- Pekerja = 4.0000 Org - Mandor = 0.0200 Org
4.0200 Org
- Waktu yang diperlukan 20.9520 x 0.4400 = 2.2933 Hari 4.0200
- Peralatan- Mesin Air- Waterpass- Alat Bantu
* Pek. Urugan Kembali Tanah Pondasi - Volume Pekerjaan = 6.9840 M3- Koefisien Pekerja
- Pekerja = 0.1920 O/H- Mandor = 0.0190 O/H
0.2110
- Jumlah Pekerja- Pekerja = 4.0000 Org - Mandor = 0.0200 Org
4.0200 Org
- Waktu yang diperlukan 6.9840 x 0.2110 = 0.3666 Hari 4.0200
- Peralatan- Mesin Air- Waterpass- Alat Bantu
* Pek. Pasir Urug Dibawah Lantai Dan Pondasi- Volume Pekerjaan = 13.7500 M3- Koefisien Pekerja
- Pekerja = 0.3000 O/H- Mandor = 0.0100 O/H
0.3100
- Jumlah Pekerja- Pekerja = 4.0000 Org - Mandor = 0.0200 Org
4.0200 Org
- Waktu yang diperlukan 13.7500 x 0.3100 = 1.0603 Hari 4.0200
- Bahan yang diperlukan- Pasir Urug 13.7500 x 1.2000 = 16.5000 M3
- Peralatan- Mesin Air- Waterpass- Dump Truck- Alat Bantu
* Pek. Timbunan Tanah Didatangkan ( Bawah lantai )- Volume Pekerjaan = 49.5000 M3- Koefisien Pekerja
- Pekerja = 0.5000 O/H- Mandor = 0.0500 O/H
0.5500
- Jumlah Pekerja- Pekerja = 4.0000 Org - Mandor = 0.0200 Org
4.0200 Org
- Waktu yang diperlukan 49.5000 x 0.5500 = 6.7724 Hari 4.0200
- Bahan yang diperlukan- Tanah Timbunan 49.5000 x 1.2000 = 59.4000 M3
- Peralatan- Mesin Air- Waterpass- Dump Truck- Alat Bantu
Jumlah Hari Kerja = 10.4925 Hari Dalam Mingguan 1.4989 Minggu
III. PEKERJAAN BETON DAN PASANGAN* Pek. Pasangan Pondasi Beton Cor 1 : 2 : 3
- Volume Pekerjaan = 9.0300 M3- Koefisien Pekerja
- Tukang = 0.2500 O/H- Kepala Tukang = 0.0250 O/H- Pekerja = 1.6500 O/H- Mandor = 0.0800 O/H
2.0050 - Jumlah Pekerja
- Tukang = 4.0000 Org - Kepala Tukang = 0.2000 Org - Pekerja = 8.0000 Org - Mandor = 0.0400 Org
12.2400
- Waktu yang diperlukan 9.0300 x 2.0050 = 1.4792 Hari 12.2400
- Bahan yang diperlukan- Kerikil 9.0300 x 0.8700 = 7.8561 M3
Pasir Pasang 9.0300 x 0.5200 = 4.6956 M3 Semen 9.0300 x ### = 1,968.5400 Kg
- Peralatan- Mesin Air- Dump Truk- Concrete Mixer- Concrete Vibrator- Alat Bantu
* Beton Bertulang 1 : 2 : 3- Volume Pekerjaan = 1.0000 M3- Koefisien Pekerja
- Tukang = 0.2750 O/H- Kepala Tukang = 0.0280 O/H- Pekerja = 1.6500 O/H- Mandor = 0.0830 O/H
2.0360 - Jumlah Pekerja
- Tukang = 0.5000 Org - Kepala Tukang = 0.0500 Org - Pekerja = 1.0000 Org - Mandor = 0.5000 Org
2.0500
- Waktu yang diperlukan 1.0000 x 2.0360 = 0.9932 Hari 2.0500
- Bahan yang diperlukan- Kerikil 1.0000 x 0.7530 = 0.7530 M3
Pasir Pasang 1.0000 x 0.5710 = 0.5710 M3 Semen 1.0000 x ### = 371.0000 Kg
- Peralatan- Sekop- Cangkul- Dump Truck- Concrete Mixer- Dll
* Pembesian- Volume Pekerjaan = 1.0000 M3- Koefisien Pekerja
- Tukang = 0.0070 O/H- Kepala Tukang = 0.0007 O/H- Pekerja = 0.0070 O/H- Mandor = 0.0003 O/H
0.0150 - Jumlah Pekerja
- Tukang = 0.5000 Org - Kepala Tukang = 0.0500 Org - Pekerja = 1.0000 Org - Mandor = 0.5000 Org
2.0500
- Waktu yang diperlukan 1.0000 x 0.0150 = 0.0073 Hari 2.0500
- Bahan yang diperlukan- Besi beton 1.0000 x 1.0500 = 1.0500 Kg
Kawat Beton 1.0000 x 0.0150 = 0.0150 Kg
- Peralatan- Alat Bantu
* Bekisting- Volume Pekerjaan = 1.0000 M3- Koefisien Pekerja
- Tukang = 0.2600 O/H- Kepala Tukang = 0.0260 O/H- Pekerja = 0.5200 O/H- Mandor = 0.0260 O/H
0.8320 - Jumlah Pekerja
- Tukang = 0.5000 Org - Kepala Tukang = 0.0500 Org - Pekerja = 1.0000 Org - Mandor = 0.5000 Org
2.0500
- Waktu yang diperlukan 1.0000 x 0.8320 = 0.4059 Hari 2.0500
- Bahan yang diperlukan- Kayu Bekisting 1.0000 x 0.0450 = 0.0450 M3
Paku campuran 1.0000 x 0.3000 = 0.3000 Kg
- Peralatan- Alat Bantu
* Membongkar / Menyiram Beton- Volume Pekerjaan = 1.0000 M3- Koefisien Pekerja
- Pekerja = 2.0000 O/H- = O/H- = O/H- = O/H
2.0000 - Jumlah Pekerja
- Pekerja = 1.0000 Org - = Org - = Org - = Org
1.0000
- Waktu yang diperlukan 1.0000 x 2.0000 = 2.0000 Hari 1.0000
- Bahan yang diperlukan-
- Peralatan- Alat Bantu
* Pek. Pasangan Pondasi Tapak Beton Btl. 1 : 2 : 3 ( Besi 150 Kg ) - Volume Pekerjaan = 0.8350 M3- Waktu Pelaksanaan
- Beton Bertulang 0.9932 x 0.8350 = 0.8293 Hari- Pembesian 0.0073 x 0.8350 = 0.0061 Hari- Bekisting 0.4059 x 0.8350 = 0.3389 Hari- Membongkar / Menyiram Beton 2.0000 x 0.8350 = 1.6700 Hari
2.8443 - Bahan yang diperlukan
- Beton Bertulang 0.8350 x 1.0000 = 0.8350 M3 - Pembesian 0.8350 x ### = 125.2500 Kg - Bekisting 0.8350 x 2.6667 = 2.2267 M2 - Membongkar / Menyiram Beton 0.8350 x 1.0000 = 0.8350 M3
* Pek. Balok Sloof 15 / 20 Beton Btl. 1 : 2 : 3 ( Besi 200 Kg ) - Volume Pekerjaan = 1.6380 M3- Koefisien
- Beton Bertulang 0.9932 x 1.6380 = 1.6268 O/H- Pembesian 0.0073 x 1.6380 = 0.0120 O/H- Bekisting 0.4059 x 1.6380 = 0.6648 O/H- Membongkar / Menyiram Beton 2.0000 x 1.6380 = 3.2760 O/H
5.5796 - Bahan yang diperlukan
- Beton Bertulang 1.6380 x 1.0000 = 1.6380 M3 - Pembesian 1.6380 x ### = 327.6000 Kg - Bekisting 1.6380 x 5.8333 = 9.5550 M2 - Membongkar / Menyiram Beton 1.6380 x 1.0000 = 1.6380 M3
* Pek. Tiang Kolom 20 X 20 cm Beton Btl. 1 : 2 : 3 ( Besi 150 Kg ) - Volume Pekerjaan = 1.2640 M'- Koefisien
- Beton Bertulang 0.9932 x 1.2640 = 1.2554 O/H- Pembesian 0.0073 x 1.2640 = 0.0092 O/H- Bekisting 0.4059 x 1.2640 = 0.5130 O/H- Membongkar / Menyiram Beton 2.0000 x 1.2640 = 2.5280 O/H
4.3056 - Bahan yang diperlukan
- Beton Bertulang 1.2640 x 1.0000 = 1.2640 M3 - Pembesian 1.2640 x ### = 189.6000 Kg - Bekisting 1.2640 x 10.0000 = 12.6400 M2 - Membongkar / Menyiram Beton 1.2640 x 1.0000 = 1.2640 M3
* Pek. Tiang Kolom Praktis Beton Bertulang Uk. 11 x 11 cm - Volume Pekerjaan = 36.3000 M'- Koefisien
- Beton Bertulang 0.9932 x 36.3000 = 36.0521 O/H- Pembesian 0.0073 x 36.3000 = 0.2656 O/H- Bekisting 0.4059 x 36.3000 = 14.7325 O/H- Membongkar / Menyiram Beton 2.0000 x 36.3000 = 72.6000 O/H
123.6502 Dalam M'= 0.0121 x ### = 1.4962
- Bahan yang diperlukan dalam M'- Beton Bertulang 36.3000 x 0.0121 = 0.4392 M3 - Pembesian 36.3000 x 4.3189 = 156.7745 Kg - Bekisting 36.3000 x 0.1100 = 3.9930 M2 - Membongkar / Menyiram Beton 36.3000 x 0.0121 = 0.4392 M3
* Pek. Ring Balok Beton Beton Bertulang Uk. 10 x 15 cm - Volume Pekerjaan = 92.5000 M'- Koefisien
- Beton Bertulang 0.9932 x 92.5000 = 91.8683 O/H- Pembesian 0.0073 x 92.5000 = 0.6768 O/H- Bekisting 0.4059 x 92.5000 = 37.5415 O/H- Membongkar / Menyiram Beton 2.0000 x 92.5000 = 185.0000 O/H
315.0866 Dalam M'= 0.0150 x ### = 4.7263
- Bahan yang diperlukan dalam M'- Beton Bertulang 92.5000 x 0.0150 = 1.3875 M3 - Pembesian 92.5000 x 4.3197 = 399.5686 Kg - Bekisting 92.5000 x 0.1250 = 11.5625 M2 - Membongkar / Menyiram Beton 92.5000 x 0.0150 = 1.3875 M3
* Pek. Pasangan Dinding 1/2 Bata 1 : 4- Volume Pekerjaan = 159.0100 M2- Koefisien Pekerja
- Tukang = 0.1000 O/H- Kepala Tukang = 0.0100 O/H- Pekerja = 0.3000 O/H- Mandor = 0.0150 O/H
0.4250 - Jumlah Pekerja
- Tukang = 4.0000 Org - Kepala Tukang = 0.4000 Org - Pekerja = 8.0000 Org - Mandor = 0.0400 Org
12.4400
- Waktu yang diperlukan ### x 0.4250 = 5.4324 Hari 12.4400
- Bahan yang diperlukan- Batu Bata ### x 70.0000 = 11,130.7000 Bh
Pasir Pasangan ### x 0.0450 = 7.1554 M3 Semen ### x 9.6800 = 1,539.2168 Kg
- Peralatan- Mesin Air- Dump Truck- Concrete Mixer- Waterpass- Alat Bantu
* Pek. Pasangan Dinding 1/2 Bata 1 : 3 ( Saluran Air )- Volume Pekerjaan = 14.5000 M2- Koefisien Pekerja
- Tukang = 0.1000 O/H- Kepala Tukang = 0.0100 O/H- Pekerja = 0.3000 O/H- Mandor = 0.0150 O/H
0.4250 - Jumlah Pekerja
- Tukang = 4.0000 Org - Kepala Tukang = 0.4000 Org - Pekerja = 8.0000 Org - Mandor = 0.0400 Org
12.4400
- Waktu yang diperlukan 14.5000 x 0.4250 = 0.4954 Hari 12.4400
- Bahan yang diperlukan- Batu Bata 14.5000 x 70.0000 = 1,015.0000 Bh
Pasir Pasang 14.5000 x 0.0400 = 0.5800 M3 Semen 14.5000 x 14.3700 = 208.3650 Kg
- Peralatan- Mesin Air- Dump Truck- Concrete Mixer- Waterpass- Alat Bantu
* Pek. Plesteran Dinding 1 : 4- Volume Pekerjaan = 299.0210 M2- Koefisien Pekerja
- Tukang = 0.2000 O/H- Kepala Tukang = 0.0200 O/H- Pekerja = 0.2500 O/H- Mandor = 0.0250 O/H
0.4950 - Jumlah Pekerja
- Tukang = 4.0000 Org - Kepala Tukang = 0.4000 Org - Pekerja = 8.0000 Org - Mandor = 0.0400 Org
12.4400
- Waktu yang diperlukan ### x 0.4950 = 11.8983 Hari 12.4400
- Bahan yang diperlukan- Pasir Pasangan ### x 0.0280 = 8.3726 M3
Semen ### x 7.2900 = 2,179.8631 Kg
- Peralatan- Mesin Air- Dump Truck- Concrete Mixer- Waterpass- Alat Bantu
* Pek. Plesteran 1 : 3 ( Saluran Air )- Volume Pekerjaan = 29.0000 M2- Koefisien Pekerja
- Tukang = 0.2000 O/H- Kepala Tukang = 0.0200 O/H- Pekerja = 0.4000 O/H- Mandor = 0.0220 O/H
0.6420 - Jumlah Pekerja
- Tukang = 4.0000 Org - Kepala Tukang = 0.4000 Org - Pekerja = 8.0000 Org - Mandor = 0.0400 Org
12.4400
- Waktu yang diperlukan 29.0000 x 0.6420 = 1.4966 Hari 12.4400
- Bahan yang diperlukan- Pasir Pasangan 29.0000 x 0.0310 = 0.8990 M3
Semen 29.0000 x 10.3680 = 300.6720 Kg
- Peralatan- Mesin Air- Dump Truck- Concrete Mixer- Waterpass- Alat Bantu
* Pek. Cor Lantai Selasar Dan Teras Beton 1 : 3 : 5 Tebal 7 cm Diaci - Volume Pekerjaan = 6.3000 M3- Koefisien Pekerja
- Tukang = 0.2500 O/H- Kepala Tukang = 0.0250 O/H- Pekerja = 1.6500 O/H- Mandor = 0.0800 O/H
2.0050 - Jumlah Pekerja
- Tukang = 4.0000 Org - Kepala Tukang = 0.4000 Org - Pekerja = 8.0000 Org - Mandor = 0.0400 Org
12.4400
- Waktu yang diperlukan 6.3000 x 2.0050 = 1.0154 Hari 12.4400
- Bahan yang diperlukan- Kerikil 6.3000 x 0.8700 = 5.4810 M3
Pasir Pasang 6.3000 x 0.5200 = 3.2760 M3 Semen 6.3000 x ### = 1,373.4000 Kg
- Peralatan- Mesin Air- Dump Truck- Concrete Mixer- Waterpass- Alat Bantu
* Pek. Pasangan Lantai Dalam Dan Teras ( Keramik 30 x 30 cm )- Volume Pekerjaan = 137.2940 M2- Koefisien Pekerja
- Tukang = 0.1000 O/H- Kepala Tukang = 0.0450 O/H- Pekerja = 0.6000 O/H- Mandor = 0.0300 O/H
0.7750 - Jumlah Pekerja
- Tukang = 4.0000 Org - Kepala Tukang = 0.4000 Org - Pekerja = 8.0000 Org - Mandor = 0.0400 Org
12.4400
- Waktu yang diperlukan ### x 0.7750 = 8.5533 Hari 12.4400
- Bahan yang diperlukan- Keramik Lantai 30 x 30 ### x 1.0000 = 137.2940 M2
Semen ### x 9.3000 = 1,276.8342 Kg Pasir Pasang ### x 0.0180 = 2.4713 M3 Semen Warna ### x 1.5000 = 205.9410 Kg
- Peralatan- Mesin Air- Dump Truck- Concrete Mixer- Waterpass- Alat Bantu
* Pek. Pasangan Batu Alam Tiang Teras- Volume Pekerjaan = 3.3600 M2- Koefisien Pekerja
- Tukang = 0.1100 O/H- Kepala Tukang = 0.0110 O/H- Pekerja = 0.6600 O/H- Mandor = 0.0330 O/H
0.8140 - Jumlah Pekerja
- Tukang = 4.0000 Org - Kepala Tukang = 0.4000 Org - Pekerja = 8.0000 Org - Mandor = 0.0400 Org
12.4400
- Waktu yang diperlukan 3.3600 x 0.8140 = 0.2199 Hari 12.4400
- Bahan yang diperlukan- Batu alam 3.3600 x 1.1000 = 3.6960 M2
Semen Portland 3.3600 x 9.3000 = 31.2480 Kg Pasir pasang 3.3600 x 0.0180 = 0.0605 M3
- Peralatan- Mesin Air- Dump Truck- Concrete Mixer- Waterpass- Alat Bantu
Jumlah Hari Kerja = 49.5424 Hari Dalam Mingguan 7.0775 Minggu
V. PEK. KAYU DAN KUSEN* Pek. Konsen Pintu, Jendela, (Kayu Kulim )
- Volume Pekerjaan = 0.7110 M3- Koefisien Pekerja
- Tukang = 18.0000 O/H- Kepala Tukang = 1.8000 O/H- Pekerja = 6.0000 O/H- Mandor = 0.3000 O/H
26.1000 - Jumlah Pekerja
- Tukang = 4.0000 Org - Kepala Tukang = 0.4000 Org - Pekerja = 8.0000 Org - Mandor = 0.0400 Org
12.4400
- Waktu yang diperlukan 0.7110 x 26.1000 = 1.4917 Hari 12.4400
- Bahan yang diperlukan- Kayu Kulim 0.7110 x 1.2000 = 0.8532 M3
Lem Kayu 0.7110 x 1.0000 = 0.7110 Kg Paku 0.7110 x 1.2500 = 0.8887 Kg
- Peralatan- Alat Bantu
* Pek. Pas. Konsen Ventilasi Silang ( Kayu Kulim )- Volume Pekerjaan = 40.0000 Unit- Koefisien Pekerja
- Tukang = 18.0000 O/H- Kepala Tukang = 1.8000 O/H- Pekerja = 6.0000 O/H- Mandor = 0.3000 O/H
26.1000 - Jumlah Pekerja
- Tukang = 4.0000 Org - Kepala Tukang = 0.4000 Org - Pekerja = 8.0000 Org - Mandor = 0.0400 Org
12.4400
- Waktu yang diperlukan 40.0000 x 26.1000 = 83.9228 Hari 12.4400
Dalam Unit = 0.0075 x ### = 0.6294 Hari
- Bahan yang diperlukan- Kayu Kulim 40.0000 x 1.2000 = 48.0000 M3
Lem Kayu 40.0000 x 1.0000 = 40.0000 Kg Paku 40.0000 x 1.2500 = 50.0000 Kg
- Peralatan- Alat Bantu
* Pek. Daun Pintu Panil - Volume Pekerjaan = 5.1000 M2- Koefisien Pekerja
- Tukang = 2.5000 O/H- Kepala Tukang = 0.2500 O/H- Pekerja = 1.0000 O/H- Mandor = 0.0500 O/H
3.8000 - Jumlah Pekerja
- Tukang = 4.0000 Org - Kepala Tukang = 0.4000 Org - Pekerja = 8.0000 Org - Mandor = 0.0400 Org
12.4400
- Waktu yang diperlukan 5.1000 x 3.8000 = 1.5579 Hari 12.4400
- Bahan yang diperlukan- Kayu Kulim 5.1000 x 0.0400 = 0.2040 M3
- Peralatan- Alat Bantu
* Pek. Daun Jendela Kaca- Volume Pekerjaan = 15.0000 M2- Koefisien Pekerja
- Tukang = 2.4000 O/H- Kepala Tukang = 0.2400 O/H- Pekerja = 0.8000 O/H- Mandor = 0.0400 O/H
3.4800 - Jumlah Pekerja
- Tukang = 4.0000 Org - Kepala Tukang = 0.4000 Org - Pekerja = 8.0000 Org - Mandor = 0.0400 Org
12.4400
- Waktu yang diperlukan 15.0000 x 3.4800 = 4.1961 Hari 12.4400
- Bahan yang diperlukan- Kayu Kulim 15.0000 x 0.0240 = 0.3600 M3
- Peralatan- Alat Bantu
* Pek. Pas Ram Jalusi Kayu Klass II- Volume Pekerjaan = 1.0800 M2- Koefisien Pekerja
- Tukang = 0.1500 O/H- Kepala Tukang = 0.0150 O/H- Pekerja = 0.0150 O/H- Mandor = 0.0008 O/H
0.1808 - Jumlah Pekerja
- Tukang = 4.0000 Org - Kepala Tukang = 0.4000 Org - Pekerja = 8.0000 Org - Mandor = 0.0400 Org
12.4400
- Waktu yang diperlukan 1.0800 x 0.1808 = 0.0157 Hari 12.4400
- Bahan yang diperlukan- Kaca 5 mm 1.0800 x 1.1000 = 1.1880 M2
- Peralatan- Alat Bantu
Jumlah Hari Kerja = 7.8752 Hari Dalam Mingguan 1.1250 Minggu
V. PEK. RANGKA KAP DAN ATAPPek. Pasangan Rangka Atap Baja Ringan- Volume Pekerjaan = 245.0000 M2- Koefisien Pekerja
- Tukang = 0.8000 O/H- Kepala Tukang = 0.0800 O/H- Pekerja = 0.0800 O/H- Mandor = 0.1000 O/H
1.0600 - Jumlah Pekerja
- Tukang = 4.0000 Org - Kepala Tukang = 0.4000 Org - Pekerja = 8.0000 Org - Mandor = 0.0400 Org
12.4400
- Waktu yang diperlukan ### x 1.0600 = 20.8762 Hari 12.4400
- Bahan yang diperlukan- Smar Truss C75.100 ### x 2.8510 = 698.4950 M
Web C75.75 ### x 1.7290 = 423.6050 M Top Span 40 ### x 1.1220 = 274.8900 M ZA, G550 ### x 4.8890 = 1,197.8050 M Main Truss 1.05 TCT ### x 8.8650 = 2,171.9250 M Web 0,8 TCT ### x 12.2070 = 2,990.7150 M Ancor / Seng Pelapis Genteng ### x 0.0400 = 9.8000 Rol
- Peralatan- Alat Bantu
Pek. Pasangan Atap Genteng Metal- Volume Pekerjaan = 245.0000 M2- Koefisien Pekerja
- Tukang = 0.1000 O/H- Kepala Tukang = 0.0100 O/H- Pekerja = 0.2000 O/H- Mandor = 0.0010 O/H
0.3110 - Jumlah Pekerja
- Tukang = 4.0000 Org - Kepala Tukang = 0.4000 Org - Pekerja = 8.0000 Org - Mandor = 0.0400 Org
12.4400
- Waktu yang diperlukan ### x 0.3110 = 6.1250 Hari 12.4400
- Bahan yang diperlukan- Atap Genteng Metal ### x 1.2000 = 294.0000 Lbr
Paku Genteng ### x 0.0200 = 4.9000 Kg
- Peralatan- Alat Bantu
Pek. Bumbungan Genteng Metal- Volume Pekerjaan = 18.2500 M'- Koefisien Pekerja
- Tukang = 0.0700 O/H- Kepala Tukang = 0.0080 O/H- Pekerja = 0.1500 O/H- Mandor = 0.0060 O/H
0.2340 - Jumlah Pekerja
- Tukang = 4.0000 Org - Kepala Tukang = 0.4000 Org - Pekerja = 8.0000 Org - Mandor = 0.0400 Org
12.4400
- Waktu yang diperlukan 18.2500 x 0.2340 = 0.3433 Hari 12.4400
- Bahan yang diperlukan- Bubungan Genteng Metal 18.2500 x 1.1000 = 20.0750 M'
- Peralatan- Alat Bantu
Pek. Listplang- Volume Pekerjaan = 76.0000 M'- Koefisien Pekerja
- Tukang = 0.2000 O/H- Kepala Tukang = 0.0200 O/H- Pekerja = 0.1000 O/H- Mandor = 0.0050 O/H
0.3250 - Jumlah Pekerja
- Tukang = 4.0000 Org - Kepala Tukang = 0.4000 Org - Pekerja = 8.0000 Org - Mandor = 0.0400 Org
12.4400
- Waktu yang diperlukan 76.0000 x 0.3250 = 1.9855 Hari 12.4400
- Bahan yang diperlukan- Kayu Kelas II 76.0000 x 0.0160 = 1.2160 M3
Paku Campuran 76.0000 x 0.0500 = 3.8000 Kg
- Peralatan- Alat Bantu
Pek. Rangka Plapond- Volume Pekerjaan = 190.8760 M2- Koefisien Pekerja
- Tukang = 0.2500 O/H- Kepala Tukang = 0.0250 O/H- Pekerja = 0.1500 O/H- Mandor = 0.0750 O/H
0.5000 - Jumlah Pekerja
- Tukang = 4.0000 Org - Kepala Tukang = 0.4000 Org - Pekerja = 8.0000 Org - Mandor = 0.0400 Org
12.4400
- Waktu yang diperlukan ### x 0.5000 = 7.6719 Hari 12.4400
- Bahan yang diperlukan- Kayu Kls. II ### x 0.0120 = 2.2905 M3
Paku Campuran ### x 0.1000 = 19.0876 Kg
- Peralatan- Alat Bantu
Pek. Plapond GRC T = 4 mm- Volume Pekerjaan = 190.8760 M2- Koefisien Pekerja
- Tukang = 0.0500 O/H- Kepala Tukang = 0.0050 O/H- Pekerja = 0.1000 O/H- Mandor = 0.0050 O/H
0.1600 - Jumlah Pekerja
- Tukang = 4.0000 Org - Kepala Tukang = 0.4000 Org - Pekerja = 8.0000 Org - Mandor = 0.0400 Org
12.4400
- Waktu yang diperlukan ### x 0.1600 = 2.4550 Hari 12.4400
- Bahan yang diperlukan- GRC ### x 0.3640 = 69.4789 Lbr
Paku Sekrup ### x 0.1100 = 20.9964 Kg
- Peralatan- Alat Bantu
Pek. List Plapond Kayu Profil L = 3 cm - Volume Pekerjaan = 164.0000 M'- Koefisien Pekerja
- Tukang = 0.0500 O/H- Kepala Tukang = 0.0050 O/H- Pekerja = 0.0500 O/H- Mandor = 0.0030 O/H
0.1080 - Jumlah Pekerja
- Tukang = 4.0000 Org - Kepala Tukang = 0.4000 Org - Pekerja = 8.0000 Org - Mandor = 0.0400 Org
12.4400
- Waktu yang diperlukan ### x 0.1080 = 1.4238 Hari 12.4400
- Bahan yang diperlukan- List Profil Sp. 3 ### x 1.0500 = 172.2000 M'
Paku Campuran ### x 0.1000 = 16.4000 Kg
- Peralatan- Alat Bantu
Jumlah Hari Kerja = 40.8807 Hari Dalam Mingguan 5.8401 Minggu
VI. PEKERJAAN INSTALASI LISTRIKPek. Instalasi Listrik dan Cahaya- Volume Pekerjaan = 17.0000 Ttk- Koefisien Pekerja
- Tukang = 0.7500 O/H- Kepala Tukang = 0.0750 O/H- Pekerja = 0.4000 O/H- Mandor = - O/H
1.2250 - Jumlah Pekerja
- Tukang = 1.0000 Org - Kepala Tukang = 0.1000 Org - Pekerja = 2.0000 Org - Mandor = 0.0100 Org
3.1100
- Waktu yang diperlukan 17.0000 x 1.2250 = 6.6961 Hari 3.1100
- Bahan yang diperlukan- Kawat NYYM 2 x 2.5 mm 17.0000 x 6.0000 = 102.0000 M'
Klem PVC 1/2" 17.0000 x 0.5000 = 8.5000 Lot T.Dos PVC 17.0000 x 4.0000 = 68.0000 Bh Bok PVC 17.0000 x 2.0000 = 34.0000 Bh Isolatip 17.0000 x 2.0000 34.0000 Bh
- Peralatan- Alat Bantu
* Pek. Lampu XL 20 Watt ( Lampu Hemat Energi )- Volume Pekerjaan = 10.0000 Bh- Koefisien Pekerja
- Tukang = - O/H- Kepala Tukang = - O/H- Pekerja = 0.1000 O/H- Mandor = 0.0100 O/H
0.1100 - Jumlah Pekerja
- Tukang = - Org - Kepala Tukang = - Org - Pekerja = 2.0000 Org - Mandor = 0.0100 Org
2.0100
- Waktu yang diperlukan 10.0000 x 0.1100 = 0.5473 Hari 2.0100
- Bahan yang diperlukan- Lampu XL 20 Watt 10.0000 x 1.0000 = 10.0000 Bh
- Peralatan- Alat Bantu
* Pek. Stop Kontak- Volume Pekerjaan = 2.0000 Bh- Koefisien Pekerja
- Tukang = 0.1500 O/H- Kepala Tukang = 0.0150 O/H- Pekerja = 0.1000 O/H- Mandor = - O/H
0.2650 - Jumlah Pekerja
- Tukang = 1.0000 Org - Kepala Tukang = 0.1000 Org - Pekerja = 2.0000 Org - Mandor = - Org
3.1000
- Waktu yang diperlukan 2.0000 x 0.2650 = 0.1710 Hari 3.1000
- Bahan yang diperlukan- Stop Kontak 2.0000 x 1.0000 = 2.0000 Bh
- Peralatan- Alat Bantu
* Pek. Saklar Ganda- Volume Pekerjaan = 2.0000 Bh- Koefisien Pekerja
- Tukang = 0.1500 O/H- Kepala Tukang = 0.0150 O/H- Pekerja = 0.1000 O/H- Mandor = - O/H
0.2650 - Jumlah Pekerja
- Tukang = 1.0000 Org - Kepala Tukang = 0.1000 Org - Pekerja = 2.0000 Org - Mandor = - Org
3.1000
- Waktu yang diperlukan 2.0000 x 0.2650 = 0.1710 Hari 3.1000
- Bahan yang diperlukan- Saklar Ganda 2.0000 x 1.0000 = 2.0000 Bh
- Peralatan- Alat Bantu
* Pek. MCB - Volume Pekerjaan = 1.0000 Bh- Koefisien Pekerja
- Tukang = 0.3750 O/H- Kepala Tukang = 0.0375 O/H- Pekerja = 0.2500 O/H- Mandor = - O/H
0.6625 - Jumlah Pekerja
- Tukang = 1.0000 Org - Kepala Tukang = 0.1000 Org - Pekerja = 2.0000 Org - Mandor = - Org
3.1000
- Waktu yang diperlukan 1.0000 x 0.6625 = 0.2137 Hari 3.1000
- Bahan yang diperlukan- MCB 1.0000 x 1.0000 = 1.0000 Bh
- Peralatan- Alat Bantu
Jumlah Hari Kerja = 7.7991 Hari Dalam Mingguan 1.1142 Minggu
VII. PEKERJAAN GANTUNGAN DAN KUNCI* Pek. Kunci Pintu 2 Slaag
- Volume Pekerjaan = 3.0000 Bh- Koefisien Pekerja
- Tukang = 0.2250 O/H- Kepala Tukang = 0.0225 O/H- Pekerja = 0.0100 O/H- Mandor = 0.0050 O/H
0.2625 - Jumlah Pekerja
- Tukang = 1.0000 Org - Kepala Tukang = 0.0500 Org - Pekerja = 2.0000 Org - Mandor = 0.0100 Org
3.0600
- Waktu yang diperlukan 3.0000 x 0.2625 = 0.2574 Hari 3.0600
- Bahan yang diperlukan- Kunci Tanam 2 Slaag 3.0000 x 1.0000 = 3.0000 Bh
- Peralatan- Alat Bantu
* Pek. Engsel Pintu 4 "- Volume Pekerjaan = 9.0000 Bh- Koefisien Pekerja
- Tukang = 0.1500 O/H- Kepala Tukang = 0.0150 O/H- Pekerja = 0.0150 O/H- Mandor = 0.0008 O/H
0.1808 - Jumlah Pekerja
- Tukang = 1.0000 Org - Kepala Tukang = 0.0500 Org - Pekerja = 2.0000 Org - Mandor = 0.0100 Org
3.0600
- Waktu yang diperlukan 9.0000 x 0.1808 = 0.5318 Hari 3.0600
- Bahan yang diperlukan- Engsel Pintu Lengkap 4" 9.0000 x 1.0000 = 9.0000 M2
- Peralatan- Alat Bantu
* Pek. Engsel Jendela 3 "- Volume Pekerjaan = 24.0000 Bh- Koefisien Pekerja
- Tukang = 0.1500 O/H- Kepala Tukang = 0.0150 O/H- Pekerja = 0.0150 O/H- Mandor = 0.0008 O/H
0.1808 - Jumlah Pekerja
- Tukang = 1.0000 Org - Kepala Tukang = 0.0500 Org - Pekerja = 2.0000 Org - Mandor = 0.0100 Org
3.0600
- Waktu yang diperlukan 24.0000 x 0.1808 = 1.4180 Hari 3.0600
- Bahan yang diperlukan- Engsel Jendela Lengkap 3" 24.0000 x 1.0000 = 24.0000 Bh
- Peralatan- Alat Bantu
* Hak Angin- Volume Pekerjaan = 24.0000 Bh- Koefisien Pekerja
- Tukang = 0.1500 O/H- Kepala Tukang = 0.0150 O/H- Pekerja = 0.0150 O/H- Mandor = 0.0008 O/H
0.1808 - Jumlah Pekerja
- Tukang = 1.0000 Org - Kepala Tukang = 0.0500 Org - Pekerja = 2.0000 Org - Mandor = 0.0100 Org
3.0600
- Waktu yang diperlukan 24.0000 x 0.1808 = 1.4180 Hari 3.0600
- Bahan yang diperlukan- Hak Angin 24.0000 x 1.0000 = 24.0000 Bh
- Peralatan- Alat Bantu
* Pek. Grendel Jendela- Volume Pekerjaan = 24.0000 Bh- Koefisien Pekerja
- Tukang = 0.1500 O/H- Kepala Tukang = 0.0150 O/H- Pekerja = 0.0150 O/H- Mandor = 0.0008 O/H
0.1808 - Jumlah Pekerja
- Tukang = 1.0000 Org - Kepala Tukang = 0.0500 Org - Pekerja = 2.0000 Org - Mandor = 0.0100 Org
3.0600
- Waktu yang diperlukan 24.0000 x 0.1808 = 1.4180 Hari 3.0600
- Bahan yang diperlukan- Grendel Jendela 24.0000 x 1.0000 = 24.0000 Bh
- Peralatan- Alat Bantu
* Tarikan Jendela- Volume Pekerjaan = 12.0000 Bh- Koefisien Pekerja
- Tukang = 0.1500 O/H- Kepala Tukang = 0.0150 O/H- Pekerja = 0.0150 O/H- Mandor = 0.0008 O/H
0.1808 - Jumlah Pekerja
- Tukang = 1.0000 Org - Kepala Tukang = 0.0500 Org - Pekerja = 2.0000 Org - Mandor = 0.0100 Org
3.0600
- Waktu yang diperlukan 12.0000 x 0.1808 = 0.7090 Hari 3.0600
- Bahan yang diperlukan- Tarikan Jendela 12.0000 x 1.0000 = 12.0000 Bh
- Peralatan- Alat Bantu
Jumlah Hari Kerja = 5.7523 Hari Dalam Mingguan 0.8218 Minggu
VIII. PEKERJAAN PENGECATAN* Pengecatan Dinding & Plafond
- Volume Pekerjaan = 512.9370 M2- Koefisien Pekerja
- Tukang = 0.0630 O/H- Kepala Tukang = 0.0060 O/H- Pekerja = 0.0200 O/H- Mandor = 0.0020 O/H
0.0910 - Jumlah Pekerja
- Tukang = 1.0000 Org - Kepala Tukang = 0.0500 Org - Pekerja = 2.0000 Org - Mandor = 0.0100 Org
3.0600
- Waktu yang diperlukan ### x 0.0910 = 15.2540 Hari 3.0600
- Bahan yang diperlukan- Plamir Dinding ### x 0.1000 = 51.2937 Kg - Cat Dasar ### x 0.1000 = 51.2937 Kg - Cat Penutup 2x ### x 0.2600 = 133.3636 Kg
- Peralatan- Alat Bantu
* Mengecat Mengkilap- Volume Pekerjaan = 62.5000 M2- Koefisien Pekerja
- Tukang = 0.0090 O/H- Kepala Tukang = 0.0060 O/H- Pekerja = 0.0700 O/H- Mandor = 0.0030 O/H
0.0880 - Jumlah Pekerja
- Tukang = 1.0000 Org - Kepala Tukang = 0.0500 Org - Pekerja = 2.0000 Org - Mandor = 0.0100 Org
3.0600
- Waktu yang diperlukan 62.5000 x 0.0880 = 1.7974 Hari 3.0600
- Bahan yang diperlukan- Plamir kayu 62.5000 x 0.1500 = 9.3750 Kg - Cat Dasar 62.5000 x 0.2600 = 16.2500 Kg - Cat Mengkilap 62.5000 x 0.1700 = 10.6250 Kg
Menie 62.5000 x 0.2000 = 12.5000 Kg
- Peralatan- Alat Bantu
Jumlah Hari Kerja = 17.0514 Hari Dalam Mingguan 2.4359 Minggu
IX. PEKERJAAN PEMBUATAN KM/WC* Pek. Galian Tanah Pondasi = 1.0000 Hari
Pek. Urugan Kembali Tanah Pondasi = 1.0000 Hari
Pek. Pasangan Pondasi Beton Cor 1 : 2 : 3 = 1.0000 Hari
Pek. Tiang Kolom Praktis 11 x 11 cm = 1.0000 Hari
Pek. Pasangan Dinding Bata 1 : 4 = 1.0000 Hari
Pek. Plesteran 1 : 4 = 2.0000 Hari
Pek. Konsen Pintu = 2.0000 Hari
Pek. Daun Pintu Panil = 2.0000 Hari
Pek. Pas. Kunci Pintu = 2.0000 Hari
Pek. Pas. Engsel Pintu = 2.0000 Hari
Pek. Pas. Rangka Atap Baja Ringan = 2.0000 Hari
Pek. Pasangan Atap Genteng Metal = 2.0000 Hari
Pek. Bumbungan Genteng Metal = 2.0000 Hari
Jumlah Hari Kerja = 21.0000 Hari Dalam Mingguan 3.0000 Minggu
xxxxxxxxxxx, 29 Juli 2013
Dibuat Oleh,Kontraktor Pelaksana :
xxxxxxxxxxxxxxxxxxxx
xxxxxxxxxxxxxxxxxxxDirektur
Demikian tahapan-tahapan pelaksanaan pekerjaan Pemb. RKB MDT Nurul Ikhlas Desa xxxxxxxxxxx Kec. xxxxxxxxx kami buat untuk menjadi acuan dalam pelaksanaan pekerjaan.
JADWAL WAKTU PELAKSANAAN (KURVA "S")
KEGIATAN : PEMBANGUNAN RKB
PEKERJAAN : PEMBANGUNAN RKB MDT NURUL IKHLAS DESA xxxxxxxxxx KEC. Xxxxxxx
LOKASI : KECAMATAN xxxxxxxxxxxxx KABUPATEN xxxxxxxxxxx
TAHUN : 2013
NO. U R A I A N
WAKTU PELAKSANAAN MINGGU KE -
Keterangan1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 17.14
WAKTU PELAKSANAAN HARI KE -1-7 8-14 15-21 22-28 29-35 36-42 43-49 50-56 57-63 64-70 71-77 78-84 85-91 92-98 99-105 106-112 113-119 120
I PEKERJAAN PENDAHULUAN 3.168 0.158 0.317 0.317 0.158 0.158 0.158 0.158 0.158 0.158 0.158 0.158 0.158 0.158 0.158 0.158 0.158 0.158 0.158
II PEKERJAAN TANAH DAN PASIR 3.451 1.725 1.725
III PEKERJAAN BETON DAN PASANGAN ### 1.770 5.311 5.311 5.311 7.082 7.082 1.770 1.770
IV PEK. KAYU DAN KUNSEN 5.410 1.082 4.328
V PEK. RANGKA KAP DAN ATAP ### 1.798 7.191 ### ### 3.596 1.798
VI PEKERJAAN INSTALASI LISTRIK 1.455 0.727 0.727
VII PEKERJAAN GANTUNGAN DAN KUNCI 1.069 1.069
VIII PEKERJAAN PENGECATAN 3.999 2.399 1.200 0.400
IX PEKERJAAN PEMBUATAN KM/WC ### 4.539 4.539 1.009
JUMAH ###
I RENCANA KEMAJUAN MINGGUAN 0.158 2.042 3.813 5.470 5.470 5.470 7.240 8.322 6.257 4.795 8.077 ### ### 8.292 2.965 2.558 1.358 0.558
II RENCANA KOMULATIF MINGGUAN - 0.158 2.201 6.013 ### ### ### ### ### ### ### ### ### ### ### ### ### ### ###
III REALISASI
IV DEVIASI
xxxxxxxxxxx, 29 Juli 2013
#REF! Dibuat Oleh,
### Kontraktor Pelaksana :
xxxxxxxxxxxxxxxxxxxx
xxxxxxxxxxxxxxxxxxxDirektur
BOBOT
(%)
Jangka Waktu Pelaksanaan 120 (Seratus Dua Puluh)
Hari Kalender
0
10
20
30
40
50
60
70
80
90
100
40
ANALISA HARGA SATUAN
KEGIATAN : PEMBANGUNAN RKB
PEKERJAAN : PEMBANGUNAN RKB MDT NURUL IKHLAS DESA xxxxxxxxxx KEC. Xxxxxxx
LOKASI : KECAMATAN xxxxxxxxxxxxx KABUPATEN xxxxxxxxxxx
TAHUN : 2013
JENIS PEKERJAAN : PENGUKURAN DAN PEMASANGAN BOWPLANK
SATUAN : M1
NO U R A I A N SATUAN KUANTITASHARGA SATUAN
(Rp.)
A. BAHAN - - -
Papan Bouwplank M3 0.0070 1,800,000 12,600.00
Balok Bouwplank M3 0.0120 1,800,000 21,600.00
Paku Kg 0.0200 19,000 380.00
Sub Total A 34,580.00
B. UPAH
Tukang O/H 0.1000 75,000.00 7,500.00
Kepala Tukang O/H 0.0100 80,000.00 800.00
Pekerja O/H 0.1000 50,000.00 5,000.00
Mandor O/H 0.0050 60,000.00 300.00
Sub Total B 13,600.00
C. PERALATAN
Sub Total C -
D. Jumlah Harga ( A + B + C ) 48,180.00
JENIS PEKERJAAN : GALIAN TANAH BIASA
SATUAN : M3
NO U R A I A N SATUAN KUANTITASHARGA SATUAN
(Rp.)
A. BAHAN - - -
Sub Total A
B. UPAH
Pekerja O/H 0.4000 50,000.00 20,000.00
Mandor O/H 0.0400 60,000.00 2,400.00
Sub Total B 22,400.00
C. PERALATAN
Sub Total C -
D. Jumlah Harga ( A + B + C ) 22,400.00
HARGA PEKERJAAN (Rp.)
HARGA PEKERJAAN (Rp.)
41
JENIS PEKERJAAN : URUGAN TANAH KEMBALI
SATUAN : M3
NO U R A I A N SATUAN KUANTITASHARGA SATUAN
(Rp.)
A. BAHAN - - -
- - -
Sub Total A
B. UPAH
Pekerja O/H 0.1920 50,000.00 9,600.00
Mandor O/H 0.0190 60,000.00 1,140.00
Sub Total B 10,740.00
C. PERALATAN
Sub Total C -
D. Jumlah Harga ( A + B + C ) 10,740.00
JENIS PEKERJAAN : URUGAN PASIR DIBAWAH LANTAI & PONDASI
SATUAN : M3
NO U R A I A N SATUAN KUANTITASHARGA SATUAN
(Rp.)
A. BAHAN
Pasir Urug M3 1.2000 80,000.00 96,000.00
Sub Total A 96,000
B. UPAH
Pekerja O/H 0.3000 50,000.00 15,000.00
Mandor O/H 0.0100 60,000.00 600.00
Sub Total B 15,600.00
C. PERALATAN
Sub Total C -
D. Jumlah Harga ( A + B + C ) 111,600.00
JENIS PEKERJAAN : TIMBUNAN TANAH
SATUAN : M3
NO U R A I A N SATUAN KUANTITASHARGA SATUAN
(Rp.)
A. BAHAN
Tanah Timbunan M3 1.2000 80,000.00 96,000.00
Sub Total A 96,000
B. UPAH
Pekerja O/H 0.5000 50,000.00 25,000.00
Mandor O/H 0.0500 60,000.00 3,000.00
Sub Total B 28,000.00
C. PERALATAN
Sub Total C -
D. Jumlah Harga ( A + B + C ) 124,000.00
HARGA PEKERJAAN (Rp.)
HARGA PEKERJAAN (Rp.)
HARGA PEKERJAAN (Rp.)
42
JENIS PEKERJAAN : BETON TUMBUK 1 : 3 : 5
SATUAN : M3
NO U R A I A N SATUAN KUANTITASHARGA SATUAN
(Rp.)
A. BAHAN
Kerikil M3 0.8700 120,000.00 104,400.00
Pasir Pasang M3 0.5200 100,000.00 52,000.00
Semen Kg 218.0000 1,500.00 327,000.00
Sub Total A 483,400.00
B. UPAH
Tukang O/H 0.2500 75,000.00 18,750.00
Kepala Tukang O/H 0.0250 80,000.00 2,000.00
Pekerja O/H 1.6500 50,000.00 82,500.00
Mandor O/H 0.0800 60,000.00 4,800.00
Sub Total B 108,050.00
C. PERALATAN
Sub Total C -
D. Jumlah Harga ( A + B + C ) 591,450.00
JENIS PEKERJAAN : COR BETON BERTULANG 1 : 2 : 3
SATUAN : M3
NO U R A I A N SATUAN KUANTITASHARGA SATUAN
(Rp.)
A. BAHAN
Kerikil M3 0.7530 120,000.00 90,360.00
Pasir Pasang M3 0.5710 100,000.00 57,100.00
Semen Kg 371.0000 1,500.00 556,500.00
Sub Total A 703,960.00
UPAH
Tukang O/H 0.2750 75,000.00 20,625.00
Kepala Tukang O/H 0.0280 80,000.00 2,240.00
Pekerja O/H 1.6500 50,000.00 82,500.00
Mandor O/H 0.0830 60,000.00 4,980.00
Sub Total B 110,345.00
C. PERALATAN
Sub Total C -
D. Jumlah Harga ( A + B + C ) 814,305.00
HARGA PEKERJAAN (Rp.)
HARGA PEKERJAAN (Rp.)
43
JENIS PEKERJAAN : PEMBESIAN
SATUAN : Kg
NO U R A I A N SATUAN KUANTITASHARGA SATUAN
(Rp.)
A. BAHAN
Besi beton Kg 1.0500 11,500.00 12,075.00
Kawat Beton Kg 0.0150 17,000.00 255.00
Sub Total A 12,330.00
B. UPAH
Tukang O/H 0.0070 75,000.00 525.00
Kepala Tukang O/H 0.0007 80,000.00 56.00
Pekerja O/H 0.0070 50,000.00 350.00
Mandor O/H 0.0003 60,000.00 18.00
Sub Total B 949.00
C. PERALATAN
Sub Total C -
D Jumlah Harga ( A + B + C ) 13,279.00
JENIS PEKERJAAN : CETAKAN BETON / BEKISTING
SATUAN : M2
NO U R A I A N SATUAN KUANTITASHARGA SATUAN
(Rp.)
A. BAHAN
Kayu Bekisting 0.0450 1,800,000.00 81,000.00
Paku campuran Kg 0.3000 19,000.00 5,700.00
Sub Total A 86,700.00
B. UPAH
Tukang O/H 0.2600 75,000.00 19,500.00
Kepala Tukang O/H 0.0260 80,000.00 2,080.00
Pekerja O/H 0.5200 50,000.00 26,000.00
Mandor O/H 0.0260 60,000.00 1,560.00
Sub Total B 49,140.00
C. PERALATAN
-
Sub Total C -
D Jumlah Harga ( A + B + C ) 135,840.00
JENIS PEKERJAAN : MEMBONGKAR & MENYIRAM BETON
SATUAN : M3
NO U R A I A N SATUAN KUANTITASHARGA SATUAN
(Rp.)
A. BAHAN
Sub Total A -
B. UPAH
Pekerja O/H 2.0000 50,000.00 100,000.00
Sub Total B 100,000.00
C. PERALATAN
-
Sub Total C -
D Jumlah Harga ( A + B + C ) 100,000.00
HARGA PEKERJAAN (Rp.)
HARGA PEKERJAAN (Rp.)
M3
HARGA PEKERJAAN (Rp.)
44
JENIS PEKERJAAN : Pek. Balok Sloof 15 / 20 Beton Btl. 1 : 2 : 3 ( Besi 200 Kg )
SATUAN : M3
NO U R A I A N SATUAN KUANTITASHARGA SATUAN
(Rp.)
A. Beton Bertulang 1 : 2 : 3 M³ 1.0000 814,305.00 814,305.00
B. Pembesian Kg 200.0000 13,279.00 2,655,800.00
C. Cetakan Bekisting M² 5.8333 135,840.00 792,400.00
D. Membongkar & Menyiram M³ 1.0000 100,000.00 100,000.00
E. Jumlah Harga ( A + B + C ) 4,362,505.00
JENIS PEKERJAAN : Pek. Tiang Kolom 20 X 20 cm Beton Btl. 1 : 2 : 3 ( Besi 150 Kg )
SATUAN : M3
NO U R A I A N SATUAN KUANTITASHARGA SATUAN
(Rp.)
A. Beton Bertulang 1 : 2 : 3 M³ 1.0000 814,305.00 814,305.00
B. Pembesian Kg 150.0000 13,279.00 1,991,850.00
C. Cetakan Bekisting M² 10.0000 135,840.00 1,358,400.00
D. Membongkar & Menyiram M³ 1.0000 100,000.00 100,000.00
E. Jumlah Harga ( A + B + C ) 4,264,555.00
JENIS PEKERJAAN : Pek. Tiang Kolom Praktis Beton Bertulang Uk. 11 x 11 cm
SATUAN : M3
NO U R A I A N SATUAN KUANTITASHARGA SATUAN
(Rp.)
A. Beton Bertulang 1 : 2 : 3 M³ 1.0000 814,305.00 814,305.00
B. Pembesian Kg 356.9303 13,279.00 4,739,677.45
C. Cetakan Bekisting M² 9.0909 135,840.00 1,234,909.09
D. Membongkar & Menyiram M³ 1.0000 100,000.00 100,000.00
E. Jumlah Harga ( A + B + C ) 6,888,891.54
F. Jumlah Harga Kolom Praktis / M' ### x 0.0121 83,355.59
JENIS PEKERJAAN : Pek. Ring Balok Beton Beton Bertulang Uk. 10 x 15 cm
SATUAN : M3
NO U R A I A N SATUAN KUANTITASHARGA SATUAN
(Rp.)
A. Beton Bertulang 1 : 2 : 3 M³ 1.0000 814,305.00 814,305.00
B. Pembesian Kg 287.9774 13,279.00 3,824,051.89
C. Cetakan Bekisting M² 8.3333 135,840.00 1,132,000.00
D. Membongkar & Menyiram M³ 1.0000 100,000.00 100,000.00
E. Jumlah Harga ( A + B + C ) 5,870,356.89
F. Jumlah Harga Ring Balok / M' ### x 0.0121 71,031.32
JENIS PEKERJAAN : Pek. Pasangan Pondasi Tapak Beton Btl. 1 : 2 : 3 ( Besi 150 Kg )
SATUAN : M3
NO U R A I A N SATUAN KUANTITASHARGA SATUAN
(Rp.)
A. Beton Bertulang 1 : 2 : 3 M³ 1.0000 814,305.00 814,305.00
B. Pembesian Kg 150.0000 13,279.00 1,991,850.00
C. Cetakan Bekisting M² 2.6667 135,840.00 362,240.00
D. Membongkar & Menyiram M³ 1.0000 100,000.00 100,000.00
E. Jumlah Harga ( A + B + C ) 3,268,395.00
HARGA PEKERJAAN (Rp.)
HARGA PEKERJAAN (Rp.)
HARGA PEKERJAAN (Rp.)
HARGA PEKERJAAN (Rp.)
HARGA PEKERJAAN (Rp.)
45
JENIS PEKERJAAN : PAS. DINDING BATA 1/2 BT. SP. 1 : 3
SATUAN : M2
NO U R A I A N SATUAN KUANTITASHARGA SATUAN
(Rp.)
A. BAHAN
1 Batu Bata Bh 70.0000 700.00 49,000.00
2 Pasir Pasang M3 0.0400 100,000.00 4,000.00
3 Semen Kg 14.3700 1,500.00 21,555.00
Sub Total A 74,555.00
B. UPAH
1 Tukang O/H 0.1000 75,000.00 7,500.00
2 Kepala Tukang O/H 0.0100 80,000.00 800.00
3 Pekerja O/H 0.3000 50,000.00 15,000.00
4 Mandor O/H 0.0150 60,000.00 900.00
Sub Total B 24,200.00
C. PERALATAN
Sub Total C -
D. Jumlah Harga ( A + B + C ) 98,755.00
JENIS PEKERJAAN : PAS. DINDING BATA 1/2 BT. SP. 1 : 4
SATUAN : M2
NO U R A I A N SATUAN KUANTITASHARGA SATUAN
(Rp.)
A. BAHAN
1 Batu Bata Bh 70.0000 700.00 49,000.00
2 Pasir Pasangan M3 0.0450 100,000.00 4,500.00
3 Semen Kg 9.6800 1,500.00 14,520.00
Sub Total A 68,020.00
B. UPAH
1 Tukang O/H 0.1000 75,000.00 7,500.00
2 Kepala Tukang O/H 0.0100 80,000.00 800.00
3 Pekerja O/H 0.3000 50,000.00 15,000.00
4 Mandor O/H 0.0150 60,000.00 900.00
Sub Total B 24,200.00
C. PERALATAN
Sub Total C -
D. Jumlah Harga ( A + B + C ) 92,220.00
HARGA PEKERJAAN (Rp.)
HARGA PEKERJAAN (Rp.)
46
JENIS PEKERJAAN : PLESTERAN Sp. 1 : 3
SATUAN : M2
NO U R A I A N SATUAN KUANTITASHARGA SATUAN
(Rp.)
A. BAHAN
1 Pasir Pasangan M3 0.0310 100,000.00 3,100.00
2 Semen Kg 10.3680 1,500.00 15,552.00
Sub Total A 18,652.00
B. UPAH
1 Tukang O/H 0.2000 75,000.00 15,000.00
2 Kepala Tukang O/H 0.0200 80,000.00 1,600.00
3 Pekerja O/H 0.4000 50,000.00 20,000.00
4 Mandor O/H 0.0220 60,000.00 1,320.00
Sub Total B 37,920.00
C. PERALATAN
Sub Total C -
D. Jumlah Harga ( A + B + C ) 56,572.00
JENIS PEKERJAAN : PLESTERAN Sp. 1 : 4
SATUAN : M2
NO U R A I A N SATUAN KUANTITASHARGA SATUAN
(Rp.)
A. BAHAN
1 Pasir Pasangan M3 0.0280 100,000.00 2,800.00
2 Semen Kg 7.2900 1,500.00 10,935.00
Sub Total A 13,735.00
B. UPAH
1 Tukang O/H 0.2000 75,000.00 15,000.00
2 Kepala Tukang O/H 0.0200 80,000.00 1,600.00
3 Pekerja O/H 0.2500 50,000.00 12,500.00
4 Mandor O/H 0.0250 60,000.00 1,500.00
Sub Total B 30,600.00
C. PERALATAN
Sub Total C -
D. Jumlah Harga ( A + B + C ) 44,335.00
HARGA PEKERJAAN (Rp.)
HARGA PEKERJAAN (Rp.)
47
JENIS PEKERJAAN : PAS. BATU ALAM
SATUAN : M2
NO U R A I A N SATUAN KUANTITASHARGA SATUAN
(Rp.)
A. BAHAN
1 Batu alam M2 1.1000 150,000.00 165,000.00
2 Semen Portland Kg 9.3000 1,500.00 13,950.00
3 Pasir pasang M3 0.0180 100,000.00 1,800.00
Sub Total A 180,750.00
B. UPAH
1 Tukang O/H 0.1100 75,000.00 8,250.00
2 Kepala Tukang O/H 0.0110 80,000.00 880.00
3 Pekerja O/H 0.6600 50,000.00 33,000.00
4 Mandor O/H 0.0330 60,000.00 1,980.00
Sub Total B 44,110.00
C. PERALATAN
Sub Total C -
D. Jumlah Harga ( A + B + C ) 224,860.00
JENIS PEKERJAAN : KUSEN PINTU KAYU KULIM
SATUAN : M3
NO U R A I A N SATUAN KUANTITASHARGA SATUAN
(Rp.)
A. BAHAN
Kayu Kulim M3 1.2000 3,250,000.00 3,900,000.00
Lem Kayu Kg 1.0000 35,000.00 35,000.00
Paku Kg 1.2500 19,000.00 23,750.00
Sub Total A 3,958,750.00
B. UPAH
Tukang O/H 18.0000 75,000.00 1,350,000.00
Kepala Tukang O/H 1.8000 80,000.00 144,000.00
Pekerja O/H 6.0000 50,000.00 300,000.00
Mandor O/H 0.3000 60,000.00 18,000.00
Sub Total B 1,812,000.00
C. PERALATAN
Sub Total C -
D. Jumlah Harga ( A + B + C ) 5,770,750.00
E. I Unit Kusen Ventilasi Silang = ### x 0.0075 43,280.63
HARGA PEKERJAAN (Rp.)
HARGA PEKERJAAN (Rp.)
48
JENIS PEKERJAAN : DAUN PINTU PANEL KAYU KULIM
SATUAN : M2
NO U R A I A N SATUAN KUANTITASHARGA SATUAN
(Rp.)
A. BAHAN
1 Kayu Kulim M3 0.0400 3,250,000.00 130,000.00
Sub Total A 130,000.00
B. UPAH
1 Tukang O/H 2.5000 75,000.00 187,500.00
2 Kepala Tukang O/H 0.2500 80,000.00 20,000.00
3 Pekerja O/H 1.0000 50,000.00 50,000.00
4 Mandor O/H 0.0500 60,000.00 3,000.00
Sub Total B 260,500.00
C. ALAT
Sub Total C -
D. Jumlah Harga ( A + B + C ) 390,500.00
JENIS PEKERJAAN : PAS. BINGKAI DAUN JENDELA
SATUAN : M2
NO U R A I A N SATUAN KUANTITASHARGA SATUAN
(Rp.)
A. BAHAN
1 Kayu Kulim M3 0.0240 3,250,000.00 78,000.00
Sub Total A 78,000.00
B. UPAH
1 Tukang O/H 2.4000 75,000.00 180,000.00
2 Kepala Tukang O/H 0.2400 80,000.00 19,200.00
3 Pekerja O/H 0.8000 50,000.00 40,000.00
4 Mandor O/H 0.0400 60,000.00 2,400.00
Sub Total B 241,600.00
C. ALAT
Sub Total C -
D. Jumlah Harga ( A + B + C ) 319,600.00
JENIS PEKERJAAN : PAS. JALUSI VENTILASI
SATUAN : M2
NO U R A I A N SATUAN KUANTITASHARGA SATUAN
(Rp.)
A. BAHAN
1 Kayu Kls. II M3 0.0240 2,500,000.00 60,000.00
2 Paku Campuran Kg 0.1500 19,000.00 2,850.00
Sub Total A 62,850.00
B. UPAH
1 Tukang O/H 1.8000 75,000.00 135,000.00
2 Kepala Tukang O/H 0.1800 80,000.00 14,400.00
3 Pekerja O/H 0.6000 50,000.00 30,000.00
4 Mandor O/H 0.0300 60,000.00 1,800.00
Sub Total B 181,200.00
C. ALAT
Sub Total C -
D. Jumlah Harga ( A + B + C ) 244,050.00
HARGA PEKERJAAN (Rp.)
HARGA PEKERJAAN (Rp.)
HARGA PEKERJAAN (Rp.)
49
JENIS PEKERJAAN : PAS. KACA POLOS
SATUAN : M2
NO U R A I A N SATUAN KUANTITASHARGA SATUAN
(Rp.)
A. BAHAN
1 Kaca 5 mm M3 1.1000 100,000.00 110,000.00
Sub Total A 110,000.00
B. UPAH
1 Tukang O/H 0.1500 75,000.00 11,250.00
2 Kepala Tukang O/H 0.0150 80,000.00 1,200.00
3 Pekerja O/H 0.0150 50,000.00 750.00
4 Mandor O/H 0.00075 60,000.00 45.00
Sub Total B 13,245.00
C. ALAT
Sub Total C -
D. Jumlah Harga ( A + B + C ) 123,245.00
JENIS PEKERJAAN : PAS. ENGSEL PINTU LENGKAP 4"
SATUAN : Bh
NO U R A I A N SATUAN KUANTITASHARGA SATUAN
(Rp.)
A. BAHAN
1 Engsel Pintu Lengkap 4" Bh 1.0000 18,000.00 18,000.00
Sub Total A 18,000.00
B. UPAH
1 Tukang O/H 0.1500 75,000.00 11,250.00
2 Kepala Tukang O/H 0.0150 80,000.00 1,200.00
3 Pekerja O/H 0.0150 50,000.00 750.00
4 Mandor O/H 0.0008 60,000.00 48.00
Sub Total B 13,248.00
C. PERALATAN
Sub Total C -
D. Jumlah Harga ( A + B + C ) 31,248.00
JENIS PEKERJAAN : PAS. ENGSEL JENDELA LENGKAP 3"
SATUAN : Bh
NO U R A I A N SATUAN KUANTITASHARGA SATUAN
(Rp.)
A. BAHAN
1 Engsel Jendela Lengkap 3" Bh 1.0000 15,000.00 15,000.00
Sub Total A 15,000.00
B. UPAH
1 Tukang O/H 0.1500 75,000.00 11,250.00
2 Kepala Tukang O/H 0.0150 80,000.00 1,200.00
3 Pekerja O/H 0.0150 50,000.00 750.00
4 Mandor O/H 0.0008 60,000.00 48.00
Sub Total B 13,248.00
C. PERALATAN
Sub Total C -
D. Jumlah Harga ( A + B + C ) 28,248.00
HARGA PEKERJAAN (Rp.)
HARGA PEKERJAAN (Rp.)
HARGA PEKERJAAN (Rp.)
50
JENIS PEKERJAAN : PAS. KUNCI TANAM 2 SLAAG
SATUAN : Bh
NO U R A I A N SATUAN KUANTITASHARGA SATUAN
(Rp.)
A. BAHAN
Kunci Tanam 2 Slaag Bh 1.0000 100,000.00 100,000.00
Sub Total A 100,000.00
B. UPAH
Tukang O/H 0.2250 75,000.00 16,875.00
Kepala Tukang O/H 0.0225 80,000.00 1,800.00
Pekerja O/H 0.0100 50,000.00 500.00
Mandor O/H 0.0050 60,000.00 300.00
Sub Total B 19,475.00
C. PERALATAN
Sub Total C -
D. Jumlah Harga ( A + B + C ) 119,475.00
JENIS PEKERJAAN : PAS. GRENDEL JENDELA
SATUAN : Bh
NO U R A I A N SATUAN KUANTITASHARGA SATUAN
(Rp.)
A. BAHAN
1 Grendel Jendela Bh 1.0000 8,000.00 8,000.00
Sub Total A 8,000.00
B. UPAH
1 Tukang O/H 0.1500 75,000.00 11,250.00
2 Kepala Tukang O/H 0.0150 80,000.00 1,200.00
3 Pekerja O/H 0.0150 50,000.00 750.00
4 Mandor O/H 0.0008 60,000.00 48.00
Sub Total B 13,248.00
C. ALAT
Sub Total C -
D. Jumlah Harga ( A + B + C ) 21,248.00
JENIS PEKERJAAN : PAS. HAK ANGIN
SATUAN : Bh
NO U R A I A N SATUAN KUANTITASHARGA SATUAN
(Rp.)
A. BAHAN
1 Hak Angin Bh 1.0000 7,500.00 7,500.00
Sub Total A 7,500.00
B. UPAH
1 Tukang O/H 0.1500 75,000.00 11,250.00
2 Kepala Tukang O/H 0.0150 80,000.00 1,200.00
3 Pekerja O/H 0.0150 50,000.00 750.00
4 Mandor O/H 0.0008 60,000.00 48.00
Sub Total B 13,248.00
C. PERALATAN
Sub Total C -
D. Jumlah Harga ( A + B + C ) 20,748.00
HARGA PEKERJAAN (Rp.)
HARGA PEKERJAAN (Rp.)
HARGA PEKERJAAN (Rp.)
51
JENIS PEKERJAAN : PAS. TARIKAN JENDELA
SATUAN : Bh
NO U R A I A N SATUAN KUANTITASHARGA SATUAN
(Rp.)
A. BAHAN
1 Tarikan Jendela Bh 1.0000 5,000.00 5,000.00
Sub Total A 5,000.00
B. UPAH
1 Tukang O/H 0.1500 75,000.00 11,250.00
2 Kepala Tukang O/H 0.0150 80,000.00 1,200.00
3 Pekerja O/H 0.0150 50,000.00 750.00
4 Mandor O/H 0.0008 60,000.00 48.00
Sub Total B 13,248.00
C. PERALATAN
Sub Total C -
D. Jumlah Harga ( A + B + C ) 18,248.00
JENIS PEKERJAAN : MEMBUAT RANGKA ATAP BAJA RINGAN
SATUAN : M2
NO U R A I A N SATUAN KUANTITASHARGA SATUAN
(Rp.)
A. BAHAN
Smar Truss C75.100 M 2.8510 10,000.00 28,510.00
Web C75.75 M 1.7290 10,000.00 17,290.00
Top Span 40 M 1.1220 2,000.00 2,244.00
ZA, G550 M 4.8890 3,500.00 17,111.50
Main Truss 1.05 TCT M 8.8650 2,000.00 17,730.00
Web 0,8 TCT M 12.2070 2,000.00 24,414.00
Ancor / Seng Pelapis Genteng Rol 0.0400 1,500.00 60.00
Sub Total A 107,359.50
B UPAH
Tukang O/H 0.8000 75,000.00 60,000.00
Kepala Tukang O/H 0.0800 80,000.00 6,400.00
Pekerja O/H 0.0800 50,000.00 4,000.00
Mandor O/H 0.1000 60,000.00 6,000.00
Sub Total B 76,400.00
C. PERALATAN
Sub Total C -
D. Jumlah Harga ( A + B + C ) 183,759.50
HARGA PEKERJAAN (Rp.)
HARGA PEKERJAAN (Rp.)
52
JENIS PEKERJAAN : PAS. ATAP GENTENG METAL
SATUAN : M2
NO U R A I A N SATUAN KUANTITASHARGA SATUAN
(Rp.)
A. BAHAN
1 Atap Genteng Metal Lbr 1.2000 30,000.00 36,000.00
2 Paku Genteng Kg 0.0200 25,000.00 500.00
Sub Total A 36,500.00
B. UPAH
1 Tukang O/H 0.1000 75,000.00 7,500.00
2 Kepala Tukang O/H 0.0100 80,000.00 800.00
3 Pekerja O/H 0.2000 50,000.00 10,000.00
4 Mandor O/H 0.0010 60,000.00 60.00
Sub Total B 18,360.00
C. PERALATAN
Sub Total C -
D. Jumlah Harga ( A + B + C ) 54,860.00
JENIS PEKERJAAN : PAS. BUBUNGAN GENTENG METAL
SATUAN : M'
NO U R A I A N SATUAN KUANTITASHARGA SATUAN
(Rp.)
A. BAHAN
1 Bubungan Genteng Metal M' 1.1000 15,000.00 16,500.00
Sub Total A 16,500.00
B. UPAH
1 Tukang O/H 0.0700 75,000.00 5,250.00
2 Kepala Tukang O/H 0.0080 80,000.00 640.00
3 Pekerja O/H 0.1500 50,000.00 7,500.00
4 Mandor O/H 0.0060 60,000.00 360.00
Sub Total B 13,750.00
C. PERALATAN
Sub Total C -
D. Jumlah Harga ( A + B + C ) 30,250.00
JENIS PEKERJAAN : RANGKA PLAFOND KAYU KLS. II
SATUAN : M2
NO U R A I A N SATUAN KUANTITASHARGA SATUAN
(Rp.)
A. BAHAN
1 Kayu Kls. II M3 0.0120 2,500,000.00 30,000.00
Paku Campuran Kg 0.1000 19,000.00 1,900.00
Sub Total A 31,900.00
B UPAH
1 Tukang O/H 0.2500 75,000.00 18,750.00
2 Kepala Tukang O/H 0.0250 80,000.00 2,000.00
3 Pekerja O/H 0.1500 50,000.00 7,500.00
4 Mandor O/H 0.0750 60,000.00 4,500.00
Sub Total B 32,750.00
C. PERALATAN
Sub Total C -
D. Jumlah Harga ( A + B + C ) 64,650.00
HARGA PEKERJAAN (Rp.)
HARGA PEKERJAAN (Rp.)
HARGA PEKERJAAN (Rp.)
53
JENIS PEKERJAAN : PLAFOND GRC
SATUAN : M2
NO U R A I A N SATUAN KUANTITASHARGA SATUAN
(Rp.)
A. BAHAN
1 GRC Lbr 0.3640 65,000.00 23,660.00
2 Paku Sekrup Kg 0.1100 17,000.00 1,870.00
Sub Total A 25,530.00
B UPAH
1 Tukang O/H 0.0500 75,000.00 3,750.00
2 Kepala Tukang O/H 0.0050 80,000.00 400.00
3 Pekerja O/H 0.1000 50,000.00 5,000.00
4 Mandor O/H 0.0050 60,000.00 300.00
Sub Total B 9,450.00
C. ALAT
Sub Total C -
D. Jumlah Harga ( A + B + C ) 34,980.00
JENIS PEKERJAAN : LIST PROFIL SP. 3
SATUAN : M'
NO U R A I A N SATUAN KUANTITASHARGA SATUAN
(Rp.)
A. BAHAN
1 List Profil Sp. 3 M' 1.0500 8,000.00 8,400.00
2 Paku Campuran Kg 0.1000 19,000.00 1,900.00
Sub Total A 10,300.00
B UPAH
1 Tukang O/H 0.0500 75,000.00 3,750.00
2 Kepala Tukang O/H 0.0050 80,000.00 400.00
3 Pekerja O/H 0.0500 50,000.00 2,500.00
4 Mandor O/H 0.0030 60,000.00 180.00
Sub Total B 6,830.00
C. PERALATAN
Sub Total C -
D. Jumlah Harga ( A + B + C ) 17,130.00
JENIS PEKERJAAN : PAS. LIST PLANK PAPAN
SATUAN : M'
NO U R A I A N SATUAN KUANTITASHARGA SATUAN
(Rp.)
A. BAHAN
1 Kayu Kelas II M3 0.0160 2,500,000.00 40,000.00
2 Paku Campuran Kg 0.0500 19,000.00 950.00
Sub Total A 40,950.00
B. UPAH
1 Tukang O/H 0.2000 75,000.00 15,000.00
2 Kepala Tukang O/H 0.0200 80,000.00 1,600.00
3 Pekerja O/H 0.1000 50,000.00 5,000.00
4 Mandor O/H 0.0050 60,000.00 300.00
Sub Total B 21,900.00
C. PERALATAN
Sub Total C -
D. Jumlah Harga ( A + B + C ) 62,850.00
HARGA PEKERJAAN (Rp.)
HARGA PEKERJAAN (Rp.)
HARGA PEKERJAAN (Rp.)
54
JENIS PEKERJAAN : MEMASANG KERAMIK LANTAI 20 x 20 CM
SATUAN : M2
NO U R A I A N SATUAN KUANTITASHARGA SATUAN
(Rp.)
A. BAHAN
1 Keramik Lantai 20 x 20 M2 1.0000 50,000.00 50,000.00
2 Semen Kg 11.3800 1,500.00 17,070.00
3 Pasir Pasang M3 0.0420 100,000.00 4,200.00
4 Semen Warna Kg 1.5000 3,500.00 5,250.00
Sub Total A 76,520.00
B. UPAH
1 Tukang O/H 0.3500 75,000.00 26,250.00
2 Kepala Tukang O/H 0.0350 80,000.00 2,800.00
3 Pekerja O/H 0.6200 50,000.00 31,000.00
4 Mandor O/H 0.0300 60,000.00 1,800.00
Sub Total B 61,850.00
C. PERALATAN
Sub Total C -
D. Jumlah Harga ( A + B + C ) 138,370.00
JENIS PEKERJAAN : MEMASANG KERAMIK DINDING 20 x 20 CM
SATUAN : M2
NO U R A I A N SATUAN KUANTITASHARGA SATUAN
(Rp.)
A. BAHAN
1 Keramik Dinding 20 x 20 M2 1.0000 50,000.00 50,000.00
2 Semen Kg 9.3000 1,500.00 13,950.00
3 Pasir Pasang M3 0.0180 100,000.00 1,800.00
4 Semen Warna Kg 1.5000 3,500.00 5,250.00
Sub Total A 71,000.00
B. UPAH
1 Tukang O/H 0.1000 75,000.00 7,500.00
2 Kepala Tukang O/H 0.0450 80,000.00 3,600.00
3 Pekerja O/H 0.6000 50,000.00 30,000.00
4 Mandor O/H 0.0300 60,000.00 1,800.00
Sub Total B 42,900.00
C. PERALATAN
Sub Total C -
D. Jumlah Harga ( A + B + C ) 113,900.00
HARGA PEKERJAAN (Rp.)
HARGA PEKERJAAN (Rp.)
55
JENIS PEKERJAAN : MEMASANG LANTAI KERAMIK 30 x 30 CM
SATUAN : M2
NO U R A I A N SATUAN KUANTITASHARGA SATUAN
(Rp.)
A. BAHAN
1 Keramik Lantai 30 x 30 M2 1.0000 55,000.00 55,000.00
2 Semen Kg 9.3000 1,500.00 13,950.00
3 Pasir Pasang M3 0.0180 100,000.00 1,800.00
4 Semen Warna Kg 1.5000 3,500.00 5,250.00
Sub Total A 76,000.00
B. UPAH
1 Tukang O/H 0.1000 75,000.00 7,500.00
2 Kepala Tukang O/H 0.0450 80,000.00 3,600.00
3 Pekerja O/H 0.6000 50,000.00 30,000.00
4 Mandor O/H 0.0300 60,000.00 1,800.00
Sub Total B 42,900.00
C. PERALATAN
Sub Total C -
D. Jumlah Harga ( A + B + C ) 118,900.00
JENIS PEKERJAAN : PAS. MATA KRAN AIR
SATUAN : Bh
NO U R A I A N SATUAN KUANTITASHARGA SATUAN
(Rp.)
A. BAHAN
1 Mata Kran 1/2" Bh 1.0000 35,000.00 35,000.00
2 Seal Tape Bh 0.0250 2,500.00 62.50
Sub Total A 35,062.50
B. UPAH
1 Tukang O/H 0.1000 75,000.00 7,500.00
2 Kepala Tukang O/H 0.0100 80,000.00 800.00
3 Pekerja O/H 0.0100 50,000.00 500.00
4 Mandor O/H 0.0050 60,000.00 300.00
Sub Total B 9,100.00
C. PERALATAN
Sub Total C -
D. Jumlah Harga ( A + B + C ) 44,162.50
JENIS PEKERJAAN : PAS. FLOOR DRAIN
SATUAN : Bh
NO U R A I A N SATUAN KUANTITASHARGA SATUAN
(Rp.)
A. BAHAN
1 Floor Drain Besi Bh 1.0000 15,000.00 15,000.00
Sub Total A 15,000.00
B. UPAH
1 Tukang O/H 0.1000 75,000.00 7,500.00
2 Kepala Tukang O/H 0.0100 80,000.00 800.00
3 Pekerja O/H 0.0100 50,000.00 500.00
4 Mandor O/H 0.0050 60,000.00 300.00
Sub Total B 9,100.00
C. PERALATAN
Sub Total C -
HARGA PEKERJAAN (Rp.)
HARGA PEKERJAAN (Rp.)
HARGA PEKERJAAN (Rp.)
56
D. Jumlah Harga ( A + B + C ) 24,100.00
57
JENIS PEKERJAAN : PAS. KLOSET JONGKOK
SATUAN : Bh
NO U R A I A N SATUAN KUANTITASHARGA SATUAN
(Rp.)
A. BAHAN
1 Kloset Jongkok Bh 1.0000 175,000.00 175,000.00
2 Semen Kg 6.0000 1,500.00 9,000.00
3 Pasir Pasang M3 0.0100 100,000.00 1,000.00
Sub Total A 185,000.00
B. UPAH
1 Tukang O/H 1.5000 75,000.00 112,500.00
2 Kepala Tukang O/H 0.1500 80,000.00 12,000.00
3 Pekerja O/H 1.0000 50,000.00 50,000.00
4 Mandor O/H 0.1600 60,000.00 9,600.00
Sub Total B 184,100.00
C. PERALATAN
Sub Total C -
D. Jumlah Harga ( A + B + C ) 369,100.00
JENIS PEKERJAAN : PAS. BAK AIR FIBBER
SATUAN : Unit
NO U R A I A N SATUAN KUANTITASHARGA SATUAN
(Rp.)
A. BAHAN
1 Bak Air Fibber Unit 1.0000 275,000.00 275,000.00
2 Perlengkapan (18% x Harga Fibbe Ls 0.1800 275,000.00 49,500.00
Sub Total A 324,500.00
B. UPAH
1 Tukang O/H 2.7000 75,000.00 202,500.00
2 Kepala Tukang O/H 0.5400 80,000.00 43,200.00
3 Pekerja O/H 1.8000 50,000.00 90,000.00
4 Mandor O/H 0.1100 60,000.00 6,600.00
Sub Total B 342,300.00
C. PERALATAN
Sub Total C -
D. Jumlah Harga ( A + B + C ) 666,800.00
JENIS PEKERJAAN : SEPTICTANK + PERESAPAN
SATUAN : UNIT
NO U R A I A N SATUAN KUANTITASHARGA SATUAN
(Rp.)
1 Pek. Galian Tanah M3 2.7500 22,400.00 61,600.00
2 Pek. Urugan Pasir Alas M3 0.1500 111,600.00 16,740.00
3 Ijuk M2 3.6000 25,000.00 90,000.00
4 Batu Karang M3 0.9000 160,000.00 144,000.00
5 Pas. Batu Bata 1/2 ad. 1:3 M2 5.5000 98,755.00 543,152.50
6 Pas. Plester ad. 1:3 M2 6.6000 56,572.00 373,375.20
7 Cor Beton Bertulang 1 : 2 : 3 M3 0.1080 814,305.00 87,944.94
8 Cor Beton ad. 1:3:5 M3 0.2100 591,450.00 124,204.50
9 Pipa PVC 4" + Accessories M' 4.0000 35,000.00 140,000.00
10 Pipa Penguapan Galv. 2 " M' 0.2500 40,000.00 10,000.00
Jumlah Harga 1,591,017.14
HARGA PEKERJAAN (Rp.)
HARGA PEKERJAAN (Rp.)
HARGA PEKERJAAN (Rp.)
58
JENIS PEKERJAAN : MEMASANG INSTALASI LISTRIK
SATUAN : TTK
NO U R A I A N SATUAN KUANTITASHARGA SATUAN
(Rp.)
A. BAHAN
1 Kawat NYYM 2 x 2.5 mm M' 6.0000 7,500.00 45,000.00
2 Klem PVC 1/2" Lot 0.5000 4,000.00 2,000.00
3 T.Dos PVC Bh 4.0000 3,000.00 12,000.00
4 Bok PVC Bh 2.0000 3,000.00 6,000.00
5 Isolatip Bh 2.0000 4,000.00 8,000.00
Sub Total A 73,000.00
B. UPAH
1 Tukang O/H 0.7500 75,000.00 56,250.00
2 Kepala Tukang O/H 0.0750 80,000.00 6,000.00
3 Pekerja O/H 0.4000 50,000.00 20,000.00
4 Mandor O/H - 60,000.00 -
Sub Total B 82,250.00
C. PERALATAN
Sub Total C -
D. Jumlah Harga ( A + B + C ) 155,250.00
JENIS PEKERJAAN : MEMASANG SAKLAR GANDA
SATUAN : Bh
NO U R A I A N SATUAN KUANTITASHARGA SATUAN
(Rp.)
A. BAHAN
1 Saklar Ganda Bh 1.0000 20,000.00 20,000.00
Sub Total A 20,000.00
B. UPAH
1 Tukang O/H 0.1500 75,000.00 11,250.00
2 Kepala Tukang O/H 0.0150 80,000.00 1,200.00
3 Pekerja O/H 0.1000 50,000.00 5,000.00
4 Mandor O/H - 60,000.00 -
Sub Total B 17,450.00
C. PERALATAN
Sub Total C -
D. Jumlah Harga ( A + B + C ) 37,450.00
JENIS PEKERJAAN : MEMASANG SAKLAR TUNGGAL
SATUAN : Bh
NO U R A I A N SATUAN KUANTITASHARGA SATUAN
(Rp.)
A. BAHAN
1 Saklar Tunggal Bh 1.0000 15,000.00 15,000.00
Sub Total A 15,000.00
B. UPAH
1 Tukang O/H 0.1500 75,000.00 11,250.00
2 Kepala Tukang O/H 0.0150 80,000.00 1,200.00
3 Pekerja O/H 0.1000 50,000.00 5,000.00
4 Mandor O/H - 60,000.00 -
Sub Total B 17,450.00
C. PERALATAN
Sub Total C -
D. Jumlah Harga ( A + B + C ) 32,450.00
HARGA PEKERJAAN (Rp.)
HARGA PEKERJAAN (Rp.)
HARGA PEKERJAAN (Rp.)
59
JENIS PEKERJAAN : MEMASANG MCB
SATUAN : Bh
NO U R A I A N SATUAN KUANTITASHARGA SATUAN
(Rp.)
A. BAHAN
1 MCB Unit 1.0000 60,000.00 60,000.00
Sub Total A 60,000.00
B. UPAH
1 Tukang O/H 0.3750 75,000.00 28,125.00
2 Kepala Tukang O/H 0.0375 80,000.00 3,000.00
3 Pekerja O/H 0.2500 50,000.00 12,500.00
4 Mandor O/H - 60,000.00 -
Sub Total B 43,625.00
C. PERALATAN
Sub Total C -
D. Jumlah Harga ( A + B + C ) 103,625.00
JENIS PEKERJAAN : MEMASANG STOP KONTAK
SATUAN : Bh
NO U R A I A N SATUAN KUANTITASHARGA SATUAN
(Rp.)
A. BAHAN
1 Stop Kontak Bh 1.0000 20,000.00 20,000.00
Sub Total A 20,000.00
B. UPAH
1 Tukang O/H 0.1500 75,000.00 11,250.00
2 Kepala Tukang O/H 0.0150 80,000.00 1,200.00
3 Pekerja O/H 0.1000 50,000.00 5,000.00
4 Mandor O/H - 60,000.00 -
Sub Total B 17,450.00
C. PERALATAN
Sub Total C -
D. Jumlah Harga ( A + B + C ) 37,450.00
JENIS PEKERJAAN : MEMASANG LAMPU XL 20 WATT
SATUAN : Bh
NO U R A I A N SATUAN KUANTITASHARGA SATUAN
(Rp.)
A. BAHAN
1 Lampu XL 20 Watt Bh 1.0000 45,000.00 45,000.00
Sub Total A 45,000.00
B. UPAH
1 Tukang O/H
2 Kepala Tukang O/H
3 Pekerja O/H 0.1000 50,000.00 5,000.00
4 Mandor O/H 0.0100 60,000.00 600.00
Sub Total B 5,600.00
C. PERALATAN
Sub Total C -
D. Jumlah Harga ( A + B + C ) 50,600.00
HARGA PEKERJAAN (Rp.)
HARGA PEKERJAAN (Rp.)
HARGA PEKERJAAN (Rp.)
60
JENIS PEKERJAAN : PENGECATAN DINDING & PLAFOND
SATUAN : M2
NO U R A I A N SATUAN KUANTITASHARGA SATUAN
(Rp.)
A. BAHAN
Plamir Dinding Kg 0.1000 12,000.00 1,200.00
Cat Dasar Kg 0.1000 12,500.00 1,250.00
Cat Penutup 2x Kg 0.2600 20,000.00 5,200.00
Sub Total A 7,650.00
B. Upah
Tukang O/H 0.0630 75,000.00 4,725.00
Kepala Tukang O/H 0.0060 80,000.00 480.00
Pekerja O/H 0.0200 50,000.00 1,000.00
Mandor O/H 0.0020 60,000.00 120.00
Sub Total B 6,325.00
C. PERALATAN
Sub Total C -
D. Jumlah Harga ( A + B + C ) 13,975.00
JENIS PEKERJAAN : MENGECAT KAYU + PLAMIR
SATUAN : M2
NO U R A I A N SATUAN KUANTITASHARGA SATUAN
(Rp.)
A. BAHAN
Plamir kayu Kg 0.1500 17,500.00 2,625.00
Cat Dasar Kg 0.2600 45,000.00 11,700.00
Cat Mengkilap Kg 0.1700 50,000.00 8,500.00
Menie Kg 0.2000 50,000.00 10,000.00
Sub Total A 32,825.00
B. UPAH
Tukang O/H 0.0090 75,000.00 675.00
Kepala Tukang O/H 0.0060 80,000.00 480.00
Pekerja O/H 0.0700 50,000.00 3,500.00
Mandor O/H 0.0030 60,000.00 180.00
Sub Total B 4,835.00
C. PERALATAN
Sub Total C -
Jumlah Harga ( A + B + C ) 37,660.00
xxxxxxxxxxx, 29 Juli 2013
Dibuat Oleh,
Kontraktor Pelaksana :
xxxxxxxxxxxxxxxxxxxx
xxxxxxxxxxxxxxxxxxx
Direktur
HARGA PEKERJAAN (Rp.)
HARGA PEKERJAAN (Rp.)
DAFTAR HARGA SATUAN BAHAN
KEGIATAN : PEMBANGUNAN RKB
PEKERJAAN : PEMBANGUNAN RKB MDT NURUL IKHLAS DESA xxxxxxxxxx KEC. Xxxxxxx
LOKASI : KECAMATAN xxxxxxxxxxxxx KABUPATEN xxxxxxxxxxx
TAHUN : 2013
NO. U R A I A N SATUAN
1. Kayu Kulim M3 3,250,000.00
2. Kayu Kls. II M3 2,500,000.00
3. Kayu Kls. III M3 1,800,000.00
4. Batu Bata Bh 700.00
5. Batu Alam M2 150,000.00
6. Kerikil M3 120,000.00
7. Pasir Pasang M3 100,000.00
8. Pasir Urug M3 80,000.00
9. Tanah Timbunan M3 80,000.00
10. Semen Kg 1,500.00
11. Semen Warna Kg 3,500.00
12. Lem Kayu Kg 35,000.00
13. Keramik Lantai 20 x 20 Cm M2 50,000.00
14. Keramik Dinding 20 x 20 Cm M2 50,000.00
15. Keramik Lantai 30 x 30 Cm M2 55,000.00
16. Besi Beton Polos Kg 11,500.00
17. Kawat Beton Kg 17,000.00
18. Smar Truss C75.100 M 10,000.00
19. Web C75.75 M 10,000.00
20. Top Span 40 M 2,000.00
21. ZA, G550 M 3,500.00
22. Main Truss 1.05 TCT M 2,000.00
23. Web 0,8 TCT M 2,000.00
24. Ancor / Seng Pelapis Genteng Rol 1,500.00
25. Genteng Metal M2 30,000.00
26. Bubungan Genteng Metal M' 15,000.00
27. Baut Scrup Kg 17,000.00
28. GRC Lbr 65,000.00
29. List Profil Sp. 3 M' 8,000.00
30. Kaca 5 mm (Bening) M2 100,000.00
31. Paku Campuran Kg 19,000.00
32. Paku Ulir Kg 25,000.00
33. Plamir Tembok Kg 12,000.00
HARGA SATUAN
(Rp.)
NO. U R A I A N SATUAN
34. Kunci Tanam 2 Levers Bh 100,000.00
35. Engsel Pintu 4 Inchi Bh 18,000.00
36. Engsel Jendela 3 Inchi Bh 15,000.00
37. Grendel Jendela Bh 8,000.00
38. Hak Angin Bh 7,500.00
39. Tarikan Jendela Bh 5,000.00
40. Pipa PVC Dia. 4" M' 35,000.00
41. Pipa Galvanis 2" M' 40,000.00
42. Mata Kran Air 1/2" Bh 35,000.00
43. Seal Tape Bh 2,500.00
44. Fluor drain (Avour) Bh 15,000.00
45. Kloset Jongkok Bh 175,000.00
46. Bak Air Fibber Unit 275,000.00
47. Ijuk M2 25,000.00
48. Batu Karang M3 160,000.00
49. Cat tembok Penutup Kg 20,000.00
50. Cat Dasar Tembok Kg 12,500.00
51. Plamur Kayu Kg 17,500.00
52. Cat Dasar Minyak Kg 45,000.00
53. Cat Kayu Kg 50,000.00
54. Saklar Ganda Bh 20,000.00
55. Saklar Tunggal Bh 15,000.00
56. MCB Unit 60,000.00
57. Stop Kontak Bh 20,000.00
58. Lampu XL 20 Watt Bh 45,000.00
59. Kawat NYYM 2 x 2.5 mm M' 7,500.00
60. Klem PVC 1/2" Lot 4,000.00
61. T.Dos PVC Bh 3,000.00
62. Bok PVC Bh 3,000.00
63. Isolatip Bh 4,000.00
xxxxxxxxxxx, 29 Juli 2013
Dibuat Oleh,
Kontraktor Pelaksana :
xxxxxxxxxxxxxxxxxxxx
xxxxxxxxxxxxxxxxxxx
Direktur
HARGA SATUAN
(Rp.)
DAFTAR HARGA SATUAN UPAH
KEGIATAN : PEMBANGUNAN RKB
PEKERJAAN : PEMBANGUNAN RKB MDT NURUL IKHLAS DESA xxxxxxxxxx KEC. Xxxxxxx
LOKASI : KECAMATAN xxxxxxxxxxxxx KABUPATEN xxxxxxxxxxx
TAHUN : 2013
NO. U R A I A N SATUAN
1. Tukang Hari 75,000.00
2. Kepala Tukang Hari 80,000.00
3. Pekerja Hari 50,000.00
4. Mandor Hari 60,000.00
xxxxxxxxxxx, 29 Juli 2013
Dibuat Oleh,Kontraktor Pelaksana :
xxxxxxxxxxxxxxxxxxxx
xxxxxxxxxxxxxxxxxxxDirektur
HARGA (Rp.)
DAFTAR HARGA SATUAN PERALATAN
KEGIATAN : PEMBANGUNAN RKB
PEKERJAAN : PEMBANGUNAN RKB MDT NURUL IKHLAS DESA xxxxxxxxxx KEC. Xxxxxxx
LOKASI : KECAMATAN xxxxxxxxxxxxx KABUPATEN xxxxxxxxxxx
TAHUN : 2013
NO. U R A I A N SATUAN
1 Dump Truck Hari 500,000.00
2 Mesin Air Hari 150,000.00
3 Waterpass Hari 200,000.00
4 Concrete Mixer/Concrete Vibrator Hari 250,000.00
xxxxxxxxxxx, 29 Juli 2013
Dibuat Oleh,Kontraktor Pelaksana :
xxxxxxxxxxxxxxxxxxxx
xxxxxxxxxxxxxxxxxxxDirektur
HARGA (Rp.)
ASLI
DOKUMEN PENAWARAN
0
PEKERJAANPEMBANGUNAN BALAI NIKAH 2 (DUA) UNIT
KANTOR KEMENTRIAN AGAMA KABUPATEN BONE BOLANGO
LOKASIKABUPATEN BONE BOLANGO
TAHUN ANGGARAN 2011
DOKUMEN KUALIFIKASI
0
#REF! #REF!
#REF! #REF!
#REF! #REF!
LOKASI 0
0 0
ANALISA HARGA SATUAN PEKERJAAN PINTU, JENDELA & VENTILASI
KEGIATAN : PENGADAAN SARANA DAN PRASARANA PUSKESMAS PEKERJAAN : REVITALISASI PUSKESMAS PERAWATAN KWANDANGLOKASI : KECAMATAN KWANDANG KABUPATEN GORONTALO UTARASUMBER DANA : DAK/DAUTAHUN ANGGARAN : 2009
NO TYPE PINTU & JENDELA VOLUME SATHARGA SATUAN
(Rp)
1 pj1Bahan + upah
- Kusen 18.7000 m1 #REF!- Bingkai 23.9000 m1 #REF!- Kaca 3.8880 M2 #REF!- Pintu 3.6800 M2 1,500.00 - #REF!- #REF!
Jumlah harga sat. bahan + upah =
1 pj2Bahan + upah
- Kusen 20.1600 m1 #REF!- Bingkai 19.8200 m1 #REF!- Kaca 2.4960 M2 #REF!- Pintu 2.0700 1,500.00 - #REF!- #REF!
Jumlah harga sat. bahan + upah =
2 pj3Bahan + upah
- Kusen 16.4200 m1 #REF!- Bingkai 6.7000 m1 #REF!- Kaca 2.3540 M2 #REF!- Pintu 2.0700 1,500.00 - #REF!- #REF!
Jumlah harga sat. bahan + upah =
3 p3Bahan + upah
- Kusen m1 #REF!- Bingkai m1 #REF!- Kaca M2 #REF!- 1,500.00 - #REF!- #REF!
4 p1Bahan + upah
- Kusen 11.3000 m1 #REF!
- Bingkai m1 #REF!- Kaca 0.3900 M2 #REF!- Pintu 3.6800 1,500.00 - #REF!- - #REF!
Jumlah harga sat. bahan + upah =
5 p2Bahan + upah
- Kusen 8.7000 m1 #REF!- Bingkai m1 #REF!- Kaca 0.1976 M2 #REF!- Pintu 2.0700 1,500.00 - #REF!- - #REF!
Jumlah harga sat. bahan + upah =
6 j1Bahan + upah
- Kusen 15.2800 m1 #REF!- Bingkai 16.9200 m1 #REF!- Kaca 1.8492 M2 #REF!- 1,500.00 - #REF!- - #REF!
Jumlah harga sat. bahan + upah = 7 j2
Bahan + upah- Kusen 10.8600 m1 #REF!- Bingkai 11.2800 m1 #REF!- Kaca 1.2328 M2 #REF!- 1,500.00 - #REF!- - #REF!
Jumlah harga sat. bahan + upah = 7 j3
Bahan + upah- Kusen 6.3400 m1 #REF!- Bingkai 5.6400 m1 #REF!- Kaca 0.6164 M2 #REF!- 1,500.00 - #REF!- - #REF!
Jumlah harga sat. bahan + upah = 7 v1
Bahan + upah- Kusen 2.1200 m1 #REF!- Bingkai m1 #REF!- Kaca 0.2500 M2 #REF!- 1,500.00 - #REF!- - #REF!
Jumlah harga sat. bahan + upah =
xxxxxxxxxxx, 29 Juli 2013
0 #REF!0
0 xxxxxxxxxxxxx#REF! Pimpinan Teknik
ANALISA HARGA SATUAN PEKERJAAN PINTU, JENDELA & VENTILASI
JUMLAH(Rp)
#REF!#REF!#REF!
5,520.00 #REF!#REF!#REF!
#REF!#REF!#REF!
3,105.00 #REF!#REF!#REF!
#REF!#REF!#REF!
3,105.00 #REF!#REF!#REF!
#REF!#REF!#REF!
- #REF!#REF!#REF!
#REF!
#REF!#REF!
5,520.00 #REF!#REF!#REF!
#REF!#REF!#REF!
3,105.00 #REF!#REF!#REF!
#REF!#REF!#REF!
- #REF!#REF!#REF!
#REF!#REF!#REF!
- #REF!#REF!#REF!
#REF!#REF!#REF!
- #REF!#REF!#REF!
#REF!#REF!#REF!
- #REF!#REF!#REF!
xxxxxxxxxxx, 29 Juli 2013
#REF!
xxxxxxxxxxxxxPimpinan Teknik
ANALISA HARGA SATUAN PEKERJAAN PINTU, JENDELA & VENTILASI
KEGIATAN : PENGADAAN SARANA DAN PRASARANA PUSKESMAS PEKERJAAN : REVITALISASI PUSKESMAS PERAWATAN KWANDANGLOKASI : KECAMATAN KWANDANG KABUPATEN GORONTALO UTARASUMBER DANA : DAK/DAUTAHUN ANGGARAN : 2009
NO TYPE PINTU & JENDELA VOLUME SATHARGA SATUAN
(Rp)
1 pj1Bahan + upah
- Kusen 18.7000 m1 #REF!- Bingkai 23.9000 m1 #REF!- Kaca 3.8880 M2 #REF!- Pintu 3.6800 M2 1,500.00 - #REF!- #REF!
Jumlah harga sat. bahan + upah =
1 pj2Bahan + upah
- Kusen 11.3000 m1 #REF!- Bingkai 4.7000 m1 #REF!- Kaca 0.3276 M2 #REF!- Pintu 3.6800 1,500.00 - #REF!- #REF!
Jumlah harga sat. bahan + upah =
2 pj3Bahan + upah
- Kusen 19.6600 m1 #REF!- Bingkai 11.9000 m1 #REF!- Kaca 1.9220 M2 #REF!- Pintu 4.6575 1,500.00 - #REF!- #REF!
Jumlah harga sat. bahan + upah =
3 p3Bahan + upah
- Kusen m1 #REF!- Bingkai m1 #REF!- Kaca M2 #REF!- 1,500.00 - #REF!- #REF!
4 p1Bahan + upah
- Kusen m1 #REF!
- Bingkai m1 #REF!- Kaca M2 #REF!- Pintu 1,500.00 - #REF!- - #REF!
Jumlah harga sat. bahan + upah =
5 p2Bahan + upah
- Kusen m1 #REF!- Bingkai m1 #REF!- Kaca M2 #REF!- Pintu 1,500.00 - #REF!- #REF!
Jumlah harga sat. bahan + upah =
6 j1Bahan + upah
- Kusen 15.2800 m1 #REF!- Bingkai 16.9200 m1 #REF!- Kaca 1.8492 M2 #REF!- 1,500.00 - #REF!- - #REF!
Jumlah harga sat. bahan + upah = 7 j2
Bahan + upah- Kusen 10.8600 m1 #REF!- Bingkai 11.2800 m1 #REF!- Kaca 1.2328 M2 #REF!- 1,500.00 - #REF!- - #REF!
Jumlah harga sat. bahan + upah = 7 j3
Bahan + upah- Kusen 6.3400 m1 #REF!- Bingkai 5.6400 m1 #REF!- Kaca 0.6164 M2 #REF!- 1,500.00 - #REF!- - #REF!
Jumlah harga sat. bahan + upah = 7 v1
Bahan + upah- Kusen 2.1200 m1 #REF!- Bingkai m1 #REF!- Kaca 0.2500 M2 #REF!- 1,500.00 - #REF!- - #REF!
Jumlah harga sat. bahan + upah =
7 v2Bahan + upah
- Kusen 4.2000 m1 #REF!- Bingkai 4.0000 m1 #REF!- Kaca 0.2392 M2 #REF!- 1,500.00 - #REF!- - #REF!
Jumlah harga sat. bahan + upah =
xxxxxxxxxxx, 29 Juli 2013
0 #REF!0
0 xxxxxxxxxxxxx#REF! Pimpinan Teknik
ANALISA HARGA SATUAN PEKERJAAN PINTU, JENDELA & VENTILASI
JUMLAH(Rp)
#REF!#REF!#REF!
5,520.00 #REF!#REF!#REF!
#REF!#REF!#REF!
5,520.00 #REF!#REF!#REF!
#REF!#REF!#REF!
6,986.25 #REF!#REF!#REF!
#REF!#REF!#REF!
- #REF!#REF!#REF!
#REF!
#REF!#REF!
- #REF!#REF!#REF!
#REF!#REF!#REF!
- #REF!#REF!#REF!
#REF!#REF!#REF!
- #REF!#REF!#REF!
#REF!#REF!#REF!
- #REF!#REF!#REF!
#REF!#REF!#REF!
- #REF!#REF!#REF!
#REF!#REF!#REF!
- #REF!#REF!#REF!
#REF!#REF!#REF!
- #REF!#REF!#REF!
xxxxxxxxxxx, 29 Juli 2013
#REF!
xxxxxxxxxxxxxPimpinan Teknik
SPESIFIKASI TEKNIS
### #REF!KEGIATAN : PEMBANGUNAN RKB PEKERJAAN : PEMBANGUNAN RKB MDT NURUL IKHLAS DESA xxxxxxxxxx KEC. Xxxxxxx
1.
2. Semaksimal mungkin diupayakan menggunakan standar nasional (SNI);3. Metode Pelaksanaan harus logis, realistik dan dapat dilaksanakan;4. Jadwal waktu pelaksanaan harus sesuai dengan metoda pelaksanaan;5.
6. Mencantumkan syarat-syarat bahan yang dipergunakan dalam pelaksanaan pekerjaan;7. Mencantumkan syarat-syarat pengujian bahan dan hasil produk;8. Mencantumkan kriteria kinerja produk yang diinginkan;9. Mencantumkan tatacara pengukuran dan tata cara pemabayaran;10. Spesifikasi Teknis Bahan Bangunan Konstruksi :
a.
b.
c.
d.
11. Spesifikasi Teknis Peralatan Konstruksi dan Peralatan Bangunan;a. Mengindentifikasi bahaya setiap jenis alat yang digunakan;b.
c.
12. Spesifikasi Teknis Proses / Kegiatana.
b.
c.
Spesifikasi Terknis ditetapkan dalam dokumen pelalangan berdasarkan jenis pekerjaan yang akan dilelangkan, dengan ketentuan :
Tidak mengarah kepada merk/produk tertentu, tidak menutup kemungkinan digunakannya produksi dalam negeri;
Mencantumkan macam, jenis, kapasitas dan jumlah peralatan utama minimal yang diperlukan dalam pelaksanaan pekerjaan;
Mengidentifikasi setiap jenis bahan bangunan konstruksi yang akan digunakan untuk pekerjaan permanen maupun untuk pekerjaan sementara atau penunjang, dan menetapkan spesifikasi teknis setiap jenis bahan yang boleh digunakan;
Setiap bahan bangunan konstruksi yang digunakan sedaspat mungkin dipilih yang paling kecil bahay dan resikonya, dan diberi penjelasan cara penggunaan yang benar dan selamat;
Memberi penjelasan atas bahan bangunan yang berbahaya atau beracun dan menjelaskan cara pengangkutan dan pembuangan limbahnya sesuai dengan prosedur perundang-undangan yang berlaku;
Informasi tentang bahan bangunan dan beracun yang diterbitkan oleh pabrik pembuatnya atau dari sumber-sumber yang berkompeten.
Memilih setiap jenis alat yang paling kecil bahaya dan resikonya serta lebih mudah penggunaan dan perawatnnya dan memberi penjelasan singkat cara penggunaan dan perawatnnya.
Memastikan setiap jenis alat yang digunakan telah diberi perlindungan atau kelengkapan pengaman untuk mencegah bahaya secara langsung terhadap tubuh pekerja;
Mengidentifikasi setiap bahay dari jenis proses ataua tahapan kegiatan pekerjaan konstruksi
Setiap jenis proses/kegiatan sedapat mungkin dipilih yang paling kecil bahay dan resikonya
Melengkapi dengan prosedur kerja, sistem perlindungan terhadap pekerja, perlengkapan pengaman dan rambu-rambu peringatan dan kewajiban pekerja.
13. Spesifikasi Teknis Metode Konstruksi/Metode Pelaksanaan/Metode Kerjaa.
b.
14. Spesifikasi Jabatan Kerja Konstruksi
a.
b.
LINGKUP PEKERJAANA. PEKERJAAN PERSIAPAN
Mengadakan sumber air bersih untuk keperluan pelaksanaan pekerjaan
- Meja / Kursi Kerja- Lemari Arsip- Meja Rapat- Kursi Rapat- Papan White Board- Dispenser- KM/WC sementara- Komputer dan Printer
Menyediakan obat-obatan untuk pertolongan pertama pada kecelakaan.Memperhitunkan biaya untuk keamanan.
B PEKERJAAN KONSTRUKSIPekerjaan Galian Tanah
Mengukur Elevasi permukaan tanah asli dibeberapa tempat sesuai petunjuk direksi
Identifikasi bahaya harus dilakukan terhadap setiap metode konstruksi/metode pelaksanaan pekerjaan, dan persyaratan teknis yang ditetapkan
Melaksanakan pekerjaan dengan menggunakan peralatan, material dan konstruksi semnetara sesuai dengan kondisi lokasi/tanah/cuaca dan dapat dikerjakan oleh pekerja dan operator terlatih
Penetapan Spesifikasi teknis serta metode pelaksanaan/konstruksi/kerja harus dilakukan oleh tenaga ahli yang mempunyai kompetensi yang dipersyaratkan.
Memastikan bahwa semua potensi bahaya dan resiko yang terkait pada bentuk rancangan, spesifikasi teknis dan metode kerja/konstruksi.
Sebelum memulai pelaksanaan pekerjaan lokasi harus dibersihkan dari sisa-sisa bangunan, rumput, semak, akar, pohon, tanah humus dan segala sesuatu yang tidak diperlukan
Mengadakan pengukuran kembali dengan teliti dengan disaksikan oleh pengawas lapangan untyuk mengetahui batas-batas, ketinggian bangunan dengan menggunakan alat ukur
Membuat Direksi Keet atau barak kerja yang dilengkapi dengan fasilitas untuk direksi dan tamu-tamu antara lain :
Memperhitungkan biaya dokumentasi berupa foto-foto yang diambil secara berkala dari seluruh pelaksanaan pekerjaan
Mengupas seluruh daerah yang akan terletak di bawah lantai bangunan dari lapisan humusnya. Hasil kupasan dibuang ketempat yang akan jauh dari lokasi pekerjaan agar tidak mengganggu kelancaran pekerjaan.
Galian harus mencapai kedalaman dan lubang galian harus cukup lebar sehingga waktu mengerjakan pasangan atau pengecoran tidak akan terganggu dan dasar lubang pondasi rata.
Menyingkirkan dan membuang hasil galian yang tidak dipergunanakan sebagai urugan tanah kemabli agar tidak terjadi penumpukan tanah disekitar lokasi
Jika terdapat genangan air dalam galian maka air tersebut harus dipompa keluar dengan menggunakan Pompa Air.
d. Jika terdapat tempat yang gembur pada dasar galian, maka harus digali dan ditimbun kembali dengan pasir urug kemudian disiram air dan dipadatkan.
Pekerjaan Urugan Tanah Kembali Bekas Galian
Pekerjaan Urugan Pasir Dibawah Lantai dan Pondasi
Pekerjaan Urugan Tanah
Pekerjaan Timbrisan Batu Kali / Belah
Batu kali yang digunakan harus batu yang keras dan baik.Pasir urug untuk lapisan dasar pondasi harus memenuhi ketentuan
Pekerjaan Pasangan Batu Kali / Belah
Pekerjaan pasangan batu harus didasarkan sesuai ukuran minimal pada gambar kerja.
Pasangan batu kali/batu belah dilaksanakan dengan campuran 1 pc : 4 pasir
Pasir Pasang untuk adukan harus terdiri dari butir-butir yang bersih dari segala kotoran
Pekerjaan Beton Bertulang, pembesian dan bekisting
Pasir Pasang untuk adukan harus terdiri dari butir-butir yang bersih dari segala kotoran
Air harus bersih dan tidak boleh mengandung endapan lumpur, minyak dan garam, asam,
Menggunakan alat pengaduk yang disetujui direksi
Menganyam besi beton sesuai dengan dimensi dan ukuran yang ditentukan dalam gambar.
Tanah bekas galian setelah dibersihkan dari kotoran-kotoran dan apabila dipandang cukup baik dapat dipergunakan untuk menimbun kembali pondasi dan membuang tanah hasil galian yang tidak dapat dipergunakan keluar dari lokasi pekerjaan.
Urugan pasir harus dilaksanakan di bawah lantai pada bangunan minimal setebal 10 cm padat dan di bawah rabat minimal setebal 10 cm.
Lapisan pasir urug harus ditimbun / dipadatkan dengan diairi sebelum lantai ubin atau pondasi dipasang, pasir urug harus bersih dari akar-akar dan kotoran lain.
Urugan tanah dilaksanakan lapis demi lapis, dan harus ditumbuk serta diairi sampai padat sebelum lapisan berikutnya dikerjakan.
Batu kali/batu belah yang dipakai adalah jenis keras, batu karang tidak boleh dipakai.
Semen yang digunakan adalah Portland Cemen (PC) produk dalam negeri yang memnuhi persyaratan
Semua tahapan pembuatan beton harus mengikuti standar dan memenuhi persyaratan yang berlaku di Indonesia dengan perbandingan 1Semen : 2 Pasir : 3 Kerikil
Pekerjaan pengecoran beton harus dilakukan sekaligus dan harus dihindarkan adanya penghentian pengecoran dan segera setelah adukan dituangkan ke dalam bekisting, adukan harus dipadatkan
Kubus beton yang dipakai selama pengecoran harus diuji kekuatan tekan karakteristiknya dilaboratorium yang dapat disetujui Direksi dan hasilnya dilaporkan secara tertulis kepada Direksi untuk dievaluasi. Apabila hasil pemeriksaan menunjukkan bahwa mutu beton kurang dari nilai yang disyaratkan, pemborong harus mengambil core sample dari bagian – bagian Konstruksi yang diragukan. Jumlah core sample untuk tiap pemeriksaan adalah tiga buah, dan selanjutnya akan diperiksa di laboratorium dengan persetujuan Direksi. Hasilnya akan dievaluasi Direksi dan bila nilai yang diperoleh membahayakan konstruksi, harus dilakukan perbaikan konstruksi tersebut atas biaya pemborong.
Semen yang digunakan adalah Portland Cemen (PC) produk dalam negeri yang memnuhi persyaratn
Kerikil harus kuat, padat tahan lama dan bersih dari segala bentuk kotoran yang dapat menurunkan mutu beton
Pekerjaan Beton Tidak Bertulang
Pekerjaan Pasangan Dinding Batu Bata
Pekerjaan Plesteran dan Acian
Semua pembengkokan tulangan harus dilakukan sebelum penyetelan/penempatan dan diperkenankan membengkokkan tulangan bila sudah ditempatkan kecuali apabila hal itu terpaksa dan sudah mendapat persetujuan direksi.
Tulangan harus ditempatkan secara teliti pada poisi sesuai rencan dan harus dijaga jarak antara tulangan dengan bekisting untuk mendapatkan tebal selimut beton minimal sesuai dengan gambar rencana. Sebelum melakukan pengecoran, semua tulangan harus terlebih dahulu diperiksa untuk memastikan ketelitian penempatannya, kebersihannya, dan untuk mendapatkan perbaikan bila diperlukan. Tulangan yang berkarat harus segera dibersihakan atau diganti bilamana dianggap dapat melemahkan konstruksi. Pengecoran tidak dapat dilakukan apabila belum mendapatkan persetujuan direksi.
Membuat cetakan (bekisting) dari bahan yang bagus yang mempunyai permukaan yang rata dan kedap air.
Untuk mendapatkan bentuk penampang dan ukuran dari beton seperti dalam gambar kerja (konstruksi), maka bekisting harus dikerjakan dengan baik, lurus, rata, teliti dan kokoh.
Pekerjaan bekisting harus sedemikian rupa sehingga hubungan-hubungan antara papan bekisting terjamin rapat dan adukan tidak akan merembes keluar.
Melindungi beton selama proses pengeringan dari cuaca dengan cara menyiram, menutup dengan karung, atau dengan cara lain yang dibenarkan
Pembongkaran bekisting beton tidak boleh dilakukan sebelum waktu pengerasan menurut PBI 1991 dipenuhi dan pembongkarannya dilakukan hati-hati dan tidak merusak beton yang sudah mengeras.
Beton Tidak bertulang dengan campuran 1 semen : 3 pasir : 5 kerikil, dilaksanakan untuk pekerjaan lain-lain dimana dianggap perlu menurut syarat-syarat pelaksanaan yang baik dan sempurna
Sebelum dipasang batu bata harus direndam lebih dahulu dengan air. Dalam hari yang sama setelah pemasangan batu bata selesai dikerjakan, siar – siar dikeruk sedalam 1 cm agar plesteran dapat melekat dengan baik.
Sebelum melakukan pekerjaan pasangan dinding, harus dipastikan bahwa pekerjaan pondasi telah benar-benar selesai dan balok sloof telah mencapai umur kering dan kekuatan yang diharpkan, dan semua tembok harus dipasang tegak lurus dan rata,
Pada bagian + 1,00 m dari permukaan balok sloof digunakan campuran spesi pengikat dengan perbandingan 1 pc : 3 pasir untuk lapisan kedap air atau dikenal dengan lapisan transram
Perbandingan campuran pada kegiatan adalah campran 1 semen : 3 pasir (trasram) dan campuran 1 semen : 5 pasir.
Semua permukaan dinding sebelah luar dan dalam harus diplester dengan adukan yang sesuai dengan perekat yang dipergunakan oleh pasangan dinding.
Pada pasangan batu bata, sebelum diplester bidang tembok harus dibasahi dahulu sampai jenuh. Begitu selesai memasang batu bata siar – siar dikeruk sedalam 1 cm untuk tujuan supaya plesteran dapat lebih kokoh menempel pada pasangan bata. Permukaan beton yang akan di plester sebelumnya harus diberap dahulu dengan air semen, kemudian dilakukan pemelesteran.
Tebal plesteran tembok bata diambil maksimum 2 cm dengan perbandingan 1 semen : 3 pasir dan 1 semen : 5 pasir. Plesteran tembok boleh dilakukan apabila selesai dengan pemasangan pipa – pipa saluran air dan listrik, Pembobokan plesteran untuk instalasi tersebut tidak diperkenankan. Setelah pekerjaan – pekerjaan plesteran selesai maka dilanjuntukan dengan acian dinding menggunakan semen.
Pekerjaan Pintu dan Jendela Aluminium
Pekerjaan Atap
Pekerjaan Plafond
Pekerjaan Lantai
Pekerjaan Instalasi Listrik
Jenis lampu (baik lampu TL maupun lampu pijar) harus berspesifikasi hemat energi.
Pekerjaan ini meliputi pengadaan tenaga kerja, bahan-bahan dan peralatan yang dipergunakan untuk melaksanakan pekerjaan pembuatan dan pemasangan Kusen Pintu dan Jendela Aluminium pada seluruh bangunan seperti yang ditunjukkan dalam gambar dan berdasarkan spesifikasi yang ada.
Rangka atap menggunakan kuda-kuda kayu kelas II dengan dimensi dan ukuran sesuai dengan gambar kerja/bestek dengan memperhatikan sambungan ataupun pertemuan kayu yang lain dengan kayu lainnya.
Penutup atap dipsersyaratkan menggunakan bahan aluminium gelombang dan bubungan aluminium.
Kemiringan atap dibuat sedemikian sehingga air hujan yang jatuh dapat segera mengalir turun tanpa terjadi rembesan di sela-sela sambungan atau susunan penutup atap.
Rangka plafond menggunakan kuda-kuda kayu kelas II dengan dimensi dan ukuran sesuai dengan gambar kerja/bestek dengan memperhatikan sambungan ataupun pertemuan kayu yang lain dengan kayu lainnya.
Dipergunakan triplex tebal minimum 3 mm, ukuran sesuai gambar rencana untuk semua ruangan dalam/luar gedung, bagian lain disesuaikan dan langit-langit dari triplex dipasang tepat waterpass.
List plafond kayu profil Sp.4 di pasang pada bagian pertemuan antara plafond dengan dinding dicat minyak, warna akan ditentukan kemudian oleh pemberi tugas.
Sebelum memulai pekerjaan, harus dipastikan bahwa permukaan timbunan telah benar-benar padat dan kuat serta siap untuk dikerjakan.
Lantai dicor dengan campuran cor beton 1 pc : 3 pasir : 5 kerikil dengan ketebalan sesuai dengan gambar kerja/bestek.
Pekerjaan lantai ruangan-ruangan (selain kamar mandi) menggunakan bahan keramik ukuran 30 x 30 cm dan plint keramik 10 x 30
Lantai toilet (kamar mandi / wc) dengan kemiringan cukup + 5 % kearah lubang pembuangan (floor drain). Siar-siar harus membentuk satu garis lurus dan diisi dengan semen kental sampai penuh, kemudian dibersihkan sampai noda-nodanya hilang.
Keramik lantai toilet (km / wc) ukuran 20 x 20 cm (anti slip) dan Keramik ukuran 20 x 25 cm dipergunakan untuk pelapis dinding km / wc (toilet) setinggi 1,50 cm, dan tempat-tempat lainnya sesuai gambar bestek/detail.
Semua keramik yang digunakan berkualitas KW. 1 mempunyai ukuran yang tepat dan pinggiran-pinggiran yang tajam dan utuh dan tidak retak.
Kabel, Stop Kontak, Saklar dan lampu harus disesuaikan dengan persyaratan dan Setiap sambungan kabel harus dibungkus dengan isolatip
Kabel yang digunakan dalam kegiatan ini adalah kabel 2,5 mm digunakan untuk semua pekerjaan jaringan instalasi listrik gedung, baik untuk instalasi penerang maupun instalasi stop kontak / saklar.
Sesuai dengan persyaratan dalam gambar, untuk lampu pijar harus memakai lampu holder, floursent harus dari jenis daylight dilengkapi dengan kapasitas lampu TL 1 x 40 watt dan TL 1 x 20 watt dengan armateur. Semua komponen didalam rumahan/housing (built in) lengkap.
Pekerjaan Sanitair
- Menggunakan Pipa-pipa PVC ydengan diameter yang ditentukan.
- Sedapat menugkin menghindari keboran pada sambungan pipa.
- Jaringan pipa air bersih untuk diluar dan didalam bangunan.
-
- Jaringan pipa-pipa vent untuk sistem pembuangan air kotor/air hujan.
- Jaringan pipa-pipa air kotor didalam bangunan.
- Penyambungan pipa air bersih dari jalur pipa air bersih utama.
- Unit pengolahan air kotor, berupa tangki septic yang dilengkapi dengan resapan.
13. PEKERJAAN LAIN-LAIN
xxxxxxxxxxx, 29 Juli 2013
0 Dibuat Oleh,0 0
Meliputi pelaksanaan pengadaan dan pemasangan Kloset, Kran Air, Floor Drain, serta perlengkapan-perlengkapan sanitair lainnya.
Semua kran yang dipakai adalah dengan chromed finish. Kran-kran tembok dipakai yang berleher panjang dan mempunyai ring kedudukan yang harus dipasang menempel pada dinding. Kran-kran yang dipasang dihalaman harus mempunyai ulir sink dan dapat disambung dengan pipa leher angsa (extension).
Floor drain dan clean out dengan bahan dasar kuningan finishing verchroom type bulat ukuran 3" dan atau ∅ 4” dilengkapi dengan siphon.
Pada tempat-tempat yang akan dipasang floor drain penutup lantai harus dilobangi dengan rapi, menggunakan pahat kecil dengan bentuk dan ukuran sesuai ukuran floor drain tersebut.
Pelaksanaan lnstalasi Air Bersih, Air Kotor, Air Buangan harus dilaksanakan dengan Pedoman Plumbing Indonesia 1979 dan Peraturan standar air buangan.
Penyediaan instalasi air bersih, pengelolaan air kotor dan drainase air hujan, termasuk pemilihan dan pengadaan material, pemasangan, pembangunan, pengujian material dan sistem, trial run, untuk seluruh sistem sehingga dapat berjalan dengan baik sesuai gambar rencana dan persyaratan ini. Sistem dan unit-unitnya meliputi :
Jaringan pipa-pipa dan saluran, talang tegak, talang datar untuk pembuangan air hujan dari atap serta halaman dan menyalurkan menuju drainase utama.
Membuat gambar-gambar persyaratan revisi pada gambar bestek/gambar detail yang telah dilaksanakan. Gambar tersebut dibuat dalam 3 (tiga) rangkap dan diserahkan kepada Direksi / PTP dan Pengguna Jasa pada saat penyerahan pertama pekerjaan, satu copy gambar tersebut diserahkan pada perencana pada waktu yang sama.
Membersihkan seluruh lapangan pekerjaan dari bekas bongkaran pekerjaan, bekas galian dan sisa-sisa material yang tidak digunakan lagi.
0 xxxxxxxxxxxxxxxxxxx0 Direktur
DAFTAR PERSONIL INTI
### #REF!### #REF!
KEGIATAN : PEMBANGUNAN RKB PEKERJAAN : PEMBANGUNAN RKB MDT NURUL IKHLAS DESA xxxxxxxxxx KEC. Xxxxxxx
No. N a m a POSISI DI PROYEK INI U M U R PENDIDIKAN TERAKHIR
1 2 3 4 5
1. Pimpinan Teknik 46 Tahun Sarjana Teknik Mesin
2. Pelaksana Lapangan 28 Tahun Sarjana Teknik Elektro
3. Logistik 27 Tahun Sarjana TekniK Sipil
4. Administrasi 35 Tahun S M A
xxxxxxxxxxx, 29 Juli 201300 Dibuat Oleh,
0 xxxxxxxxxxxxxxxxxxx0 Direktur
DAFTAR PERSONIL INTI
PENGALAMAN
6
19 Tahun
3 Tahun
2 Tahun
20 Tahun
xxxxxxxxxxx, 29 Juli 2013
Dibuat Oleh,
xxxxxxxxxxxxxxxxxxxDirektur
DAFTAR PERALATAN UTAMA
### #REF!### #REF!
KEGIATAN : PEMBANGUNAN RKB PEKERJAAN : PEMBANGUNAN RKB MDT NURUL IKHLAS DESA xxxxxxxxxx KEC. Xxxxxxx
No. Nama AlatJumlah Merk Tahun Ukuran /
DayaMilik
SewaAlat dan Type Pembuatan Kapasitas Sendiri
1 2 3 4 5 6 7 8 9
1 Genset Jiandiong 2002 15 KVA Sewa Gorontalo
2 Dump Truck Mitsubishi 2008 6 Ton Sewa Gorontalo
3 Molen (Concert Mixer) Goliath 2008 7,5 HP Sewa Gorontalo
4 Water Pump Honda 2008 5 HP Sewa Gorontalo
xxxxxxxxxxx, 29 Juli 201300 Dibuat Oleh,
0 xxxxxxxxxxxxxxxxxxx0 Direktur
Lokasi Alat Sekarang
PAKTA INTEGRITAS
Saya yang bertanda tangan dibawah ini :
1. N a m a : MUCHSIN BREKAT
J a b a t a n : Direktur
Bertindak untuk : CV. MARGA MULYADan atas nama
2. N a m a : xxxxxxxxxxxxxxxxxx
J a b a t a n : xxxxxxxxxxxxxxx
Bertindak untuk : xxxxxxxxxxxxDan atas nama
1. Tidak akan melakukan praktek Korupsi, Kolusi dan Nepotisme (KKN)
2.
3.
4.
xxxxxxxxxxx, 29 Juli 2013
CV. MARGA MULYA xxxxxxxxxxxx
Dalam rangka Pengadaan Pekerjaan Pembangunan Pabrik Es Kapasitas 15 Ton pada Pokja Pekerjaan Konstruksi ULP pada Dinas Perikanan dan Kelautan Provinsi Gorontalo Tahun Anggaran 2011, dengan ini menyatakan bahwa :
Akan melaporkan kepada pihak APIP Inspektorat Jenderal Kementrian Kelautan dan Perikanan yang bersangkutan dan/atau LKPP apabila mengetahui ada indikasi KKN di dalam proses pengadaan ini;
Akan mengikuti proses pengadaan secara bersih, transparan dan profesional untuk memberikan hasil kerja terbaik sesuai ketentuan peraturan perundang-undangan.
Apabila melanggar hal-hal yang dinyatakan dalam Pakta Integritas ini bersedia menerima sanksi administratif, menerima sanksi pencantuman dalam daftar hitam, digugat secara perdata dan atau dilaporkan secara pidana.
xxxxxxxxxxxxxxxxxxMUCHSIN BREKAT xxxxxxxxxxxxxxx
Direktur
PRA RENCANA K3 KONTRAK
KEGIATAN : PEMBANGUNAN RKB
PEKERJAAN : PEMBANGUNAN RKB MDT NURUL IKHLAS DESA xxxxxxxxxx KEC. Xxxxxxx
LOKASI : KECAMATAN xxxxxxxxxxxxx KABUPATEN xxxxxxxxxxx
TAHUN : 2013
1. Kebijakan xxxxxxxxxxxxxxxxxxxx
1.1 Visi dan Misi -
- Menyediakan lingkungan kerja yang aman -
-
1.2 Kebijakan Mutu dan K3L - Meningkatkan mutu cara kerja dan hasil kerja -
-
-
2. Manajemen Resiko K3
2.1 Prosedur Manajemen Resiko --
-
-
2.2 Resiko Bahaya
Memenuhi kebutuhan pelanggan dengan layanan yang baik dan produk yang berkualitas
Meningkatkan dan mengembangkan kemampuan sumberdaya manusia, terutama dibidang keteknikan, manajemen perusahaan dan proyek Memperkokoh posisi perusahaan di pasar global dengan pelayanan yang baik, produk berkualitas dan tenaga kerja yang terampil
Melaksanakan kegiatan sesuai dengan ketentuan dan mencegah ketidaksesuaian pada semua tahapan kerja Melaksanakan norma-norma perlindungan kerja dan lingkungan kerja serta menciptakan tempat kerja yang aman, sehat dan bebas resiko kecelakaan Melakukan perbaikan kinerja mutu dan K3L secara berkelanjutan, untuk memenuhi kepuasan pelanggan dan stakeholder lainnya
Mengidentifikasi tempat kerja dan proses tahapan pekerjaan yang akan Mengidentifikasi potensi bahaya pada setiap proses tahapan pekerjaan baik yang berjalan normal, abnormal, emergensi serta kondisi peralatan yang berjalan.Mengidentifikasi tingkat resiko bahaya, yang mungkin terjadi pada setiap ahapan pekerjaan Mengevaluasi besar kecilnya tingkat resiko bahaya untuk menentukan prioritas pengendalian terhadap resiko yang terjadi
Resiko bahaya lingkungan/manusia yang mungkin terjadi dari kegiatan pekerjaan dapat berupa kerugian, cidera/cacat/kematian dan pencemaran lingkungan. Contoh resiko bahaya yang mungkin terjadi pada setiap tahapan pekerjaan adalah terpeleset, jatuh dari ketinggian, tersengat listrik, tertimpa peralatan/bahan, penurunan pendengaran, kebakaran, pencemaran air, kontaninasi tanah dan pencemaran udara.
2.3 Identifikasi Potensi Bahaya
- Pendekatan data/dokumen masa lalu - Penggunaan check list - Pendekatan sistem proses kerja
2.4 Penilaian Tingkat Resiko -
-
-
2.5 Pengendalian Resiko - Eliminasi (modifikasi proses, metoda/materi untuk mengurangi dampak K3) - Subsitusi (mengganti materi zat atau proses dengan yang tidak/kurang berdampak) -
-
-
-
Identifikasi potensi bahaya dapat menggunakan pendekatan-pendekatan sebagai berikut :
Kemungkinan (tingkat keseringan) adalah variable yang mereflesikan seberapa sering suatu dampak terjadi dan berapa besar peluang terjadinya Konsekwensi (tingkat keparahan) adalah memprosentasikan besarnya dampak kerugian yang dialami akibat terjadinya resiko, aspek legal menjadi point tertinggi dalam penilaian aspek keparahan.
Resikonya dibagi dalam sistem peringkat, yaitu resiko rendah, resiko sedang dan resiko tinggi
Pemisahan (menyingkirkan atau memisahkan agar dampak yang mungkin terjadi minim dengan cara perlingdungan, penyimpanan ditempat, ruang tau waktu terpisah)
Administrasi (menyesuaikan waktu dan kondisi dengan proses administrasi misalnya dengan membuat standar prosedur) Pelatihan (meningkatkanpengetahuan dan keterampilan untuk mengurangi resiko terkena dampak K3) Alat pelindung diri (yang sesuai dan memadai guna menghindari dampak yang mungkin terjadi)
LEMBAR PENGESAHANxxxxxxxxxxxxxxxxxxxx
RENCANA K3 KONTRAK
PEKERJAAN : PEMBANGUNAN RKB LOKASI : PEMBANGUNAN RKB MDT NURUL IKHLAS DESA xxxxxxxxxx KEC. Xxxxxxx
KLASIFIKASI DOKUMENxxxxxxxxxxxxxxxxxxxx
Tanggal Terbit Pertama Tanggal Terbit Edisi Ini
Pihak Penyedia Jasa Pihak Pengguna Jasa
CV……………………… Disetujui Oleh
…………………………………. ………………………..Direktur Nip :
KEBIJAKAN K3xxxxxxxxxxxxxxxxxxxx
KEBIJAKAN MUTU DAN K3L
- Meningkatkan mutu cara kerja dan hasil kerja
-
-
-
xxxxxxxxxxxxxxxxxxxx
Nomor Dokumen Peraturan Perundang-undangan'UU No. 1/1970 Tentang Keselamatan KerjaUU No. 20/1992 Tentang KelistrikanUU No. 23/1992 Tentang KesehatanUU. No. 18/1999 Tentang Jasa KonstruksiUU No. 13/2003 Tentang KetenagakerjaanPermenaker No. 01/MEN/1980 Tentang K3 Konstruksi BangunanSKB Menaker & PU 1986 Tentang K3 Konstruksi Permenaker No. 5/1996 Tentang SMK3Ins. Menaker N0. 01/1992 Tentang Pemeriksaan Unit Organisasi K3SK. Dirjen PPK No. 20/DJPPK/VI/2004 Tentang Ahli Keselamatan dan Kesehatan Kerja
Melaksanakan norma-norma perlindungan kerja dan lingkungan kerja serta menciptakan tempat kerja yang aman, sehat dan bebas resiko kecelakaan
Melaksanakan norma-norma perlindungan kerja dan lingkungan kerja serta menciptakan tempat kerja yang aman, sehat dan bebas resiko kecelakaan
Melakukan perbaikan kinerja mutu dan K3L secara berkelanjutan, untuk memenuhi kepuasan pelanggan dan stakeholder lainnya
PEMENUHAN PERUNDANG-UNDANGAN DAN PERSYARATAN LAINNYA
SASARAN DAN PROGRAMxxxxxxxxxxxxxxxxxxxx
1. SasaranSasaran Mutu dan K3
2. Program Dalam Mencapai Sasaran* Adanya Program Kerja K3* Persyaratan Program Kerja K3
- Dibuat untuk mencapai sasaran K3- Uraian, wewenang dan tanggung jawab, sasaran, waktu- Indikator pencapaian program- Ditinjau secara regular
* Program kerja diuraikan secara jelas
Memberikan produk dan layanan kepada pelanggan dan stakeholder lainnya, sesuai dengan ketentuan dan spesifikasi yang diperjanjikan serta mencapai sasaran perusahaan tanpa kecelakaan atau zero accident
ORGANISASI KEGIATANxxxxxxxxxxxxxxxxxxxx
PENYEDIA JASA PENGGUNA JASA
KEPALA SATUAN KERJA
DIREKTUR PEJABAT PEMBUAT KOMITMEN
PIMPINAN TEKNIK DIREKSI
PELAKSANA LAPANGAN PENGAWAS LAPANGAN
LOGISTIK
ADMINISTRASI ASS. TEKNIK
ORGANISASI PENYEDIA JASAxxxxxxxxxxxxxxxxxxxx
Pimpinan TeknikPimpinan Teknik
DirekturDirektur
Juru UkurJuru Ukur LogistikLogistik
Administrasi Administrasi
URAIAN TUGAS, WEWENANG DAN TANGGUNG JAWABxxxxxxxxxxxxxxxxxxxx
NO N A M A JABATAN TUGAS WEWENANG TANGGUNG JAWAB
1 Direktur
2
3
Membuat Perjanjian Kontrak dengan Pengguna Jasa
Menetapkan harga satuan upah dan BTL maksimum sama-sama dengan RAPK
Bertanggung jawab langsung atas terlaksananya pekerjaan yang diberikan.
Melakukan Monitoring Proyek selama pelaksanaan pekerjaan
Mensahkan bukti-bukti pembayaran.
Melaksanakan rapat mingguan atau rapat bulanan internal dan eksternal.
Mewakili perusahaan berhubungan dengan pihak I sesuai tugas yang diatur dalam pasal-
Pimpinan Teknik
Membuat kegiatan perencanaan yang lain (Review Doc. Spec Hitung kembali dan Metode Pelaksanaan).
Mewakili perusahaan berhubungan dengan pihak I sesuai tugas yang diatur dalam pasal-
Bertanggung jawab langsung kepada Direktur atas terlaksananya dengan baik tugas yang diberikan.
Membuat rencana tidak lanjut / corrective action terhadap penyimpangan yang terjadi.
Pelaksana Lapangan
Melaksanakan Pekerjaan sesuai dengan mutu yang direncanakan.
Mewakili perusahaan berhubungan dengan pihak I sesuai tugas yang diatur dalam pasal-
Bertanggung jawab langsung kepada pelaksana utama atas terlaksananya dengan baik tugas yang diberikan
Mengadakan Pengecekan transaksi-transaksi pelaksanaan proyek, mengkompilasikan dan membandingkan dengan rencana semula.
NO N A M A JABATAN TUGAS WEWENANG TANGGUNG JAWAB
4 Administrasi Mengatur dan menyiapkan kebutuhan material yang dibutuhkan
Mewakili perusahaan berhubungan dengan pihak I sesuai tugas yang diatur dalam pasal-
Bertanggung jawab langsung kepada pelaksana utama atas terlaksananya dengan baik tugas yang diberikan
Melakukan penilitian kembali untuk meyakinkan kebenaran/ketepatan yang dilakukan.
Melakukan pencatatan berkas-berkas transaksi ke dalam media pembukuan (jurnal,dll) secara benar dan tepat waktu.
Penanggung jawab masalah-masalah keuangan,Akuntansi/Pembukuan dan unsur-unsur Umum dan SDM Proyek.
Bertanggung jawab langung kepada pelaksana utma atas terlaksananya dengan baik tugas yang diberikan
Melakukan penilitian kembali untuk meyakinkan kebenaran/ketepatan yang dilakukan.
Secara periodic membuat laporan-laporan yang telah ditetapkan, dimintakan pengesahannya kepada pejabat yang berwenang dan mengirimkannya kepada pihak-pihak yang memerlukan sesuai prosedur yang berlaku.Melaksanakan pengadministrasian keuangan dan melaksanakan pencatatan mutasi keuangan secara khusus.
Mengurus masalah kepegawaian seperti : kebutuhan tenaga kerja proyek, asuransi-asuransi lain yang diper-syratkan dalam proyek dan lain-lain.
NO N A M A JABATAN TUGAS WEWENANG TANGGUNG JAWAB
6 Teknisi Material Mengatur dan menyiapkan kebutuhan material yang dibutuhkan
Penanggung jawab masalah-masalah pengadaan bahan.
Bertanggung jawab langung kepada pelaksana utama atas terlaksananya dengan baik tugas yang diberikan
Melakukan penilitian kembali untuk meyakinkan kebenaran/ketepatan yang dilakukan.
Secara periodic membuat laporan-laporan yang telah ditetapkan, dimintakan pengesahannya kepada pejabat yang berwenang dan mengirimkannya kepada pihak-pihak yang memerlukan sesuai prosedur yang berlaku.Sebagai anggota tim yang melaksanakan opname kas dan sediaan secara periodic.Melakukan Verifiaksi seluruh dokumen transaksi pembayaran
xxxxxxxxxxxxxxxxxxxx
NO JENIS / TYPE PEKERJAAN PENGENDALI RESIKO K3
Pekerjaan Tanah Jenis Bahaya dan ResikoPengendalian resiko K31 Galian Tanah Biasa
2 Urugan Tanah
3 Urugan Pasir
Pekerjaan Pasangan Jenis Bahaya dan ResikoPengendalian resiko K31 Pek. Pondasi Batu Kali/Belah
2 Pek. Pas. Dinding Batu Bata
3 Pek. Plesteran
PRA - RENCANA KESELAMATAN DAN KESEHATAN KERJA KONTRAK ( PRA - RK3K)
IDENTIFIKASI JENIS BAHAYA & RESIKO K3
Terjadi Insiden Berupa Kaki Pekerja Terkena Peralatan Seperti Sekop dan Pacul Sehingga Terjadi Luka
Akan disediakan sepatu boat pelindung kaki
Terkena Material Hasil Galian sehingga terjadi luka dibagian kepala pekerja baik luka ringan maupun luka berat.
Akan disediakan helm pelindung kepala
Resiko bahaya lingkungan / manusia yang mungkin terjadi dari kegiatan pekerjaan dapat erupa kerugian, cidera, cacat/kematian dan pencemaran lingkungan
Mengindentifikasi potensi bahaya yang akan terjadi dengan menggunakan pendekatan data, penggunaan chek list dan pendekatan sistem proses kerja
Terjadi Insiden Berupa Kaki Pekerja Terkena Peralatan Seperti Sekop dan Pacul Sehingga Terjadi Luka
Akan disediakan sepatu boat pelindung kaki
Akan disediakan helm pelindung kepala
Terkena Material batu kali/belah & batu bata sehingga terjadi luka dibagian kepala pekerja sehingga terjadi luka baik luka ringan maupun luka berat.
Akan disediakan masker pelindung muka dan mataAkan disediakan sarung tangan pelindung tanganMengindentifikasi potensi bahaya yang akan terjadi dengan menggunakan pendekatan data,penggunaan chek list dan pendekatan sistem proses kerja
Terjadi Insiden berupa mata Pekerja Terkena material semen, pasir, pecahan batu dibagian muka dan mata sehingga mengakibatkan luka ringan maupun luka berat.
NO JENIS / TYPE PEKERJAAN PENGENDALI RESIKO K3
Pekerjaan Kayu Jenis Bahaya dan ResikoPengendalian resiko K31 Pek. Kusen Kayu
2 Pek. Daun Pintu Panel
3 Pek. Rangka Plafond
Pek. Rangka Atap
Pekerjaan Kusen Jenis Bahaya dan ResikoPengendalian resiko K31 Pek. Kusen Pintu & Jendela
IDENTIFIKASI JENIS BAHAYA & RESIKO K3
Terjadi Insiden berupa kaki pekerja kejatuhan perlatan seperti gergaji, palu dll sehingga terjadi luka.
Akan disediakan sepatu boat pelindung kaki
Akan disediakan helm pelindung kepala
Terkena sisa potongan kayu, paku, dan bahan lainnya sehingga terjadi luka dibagian kepala pekerja sehingga terjadi luka baik luka ringan maupun luka berat.
Akan disediakan masker pelindung muka dan mataAkan disediakan sarung tangan pelindung tanganAkan disediakan tali pelindung sehingga tidak langsung terjatuh dari ketinggian
Terjadi Insiden berupa mata Pekerja Terkena material kayu, paku, baut dan bahan lainnya dibagian muka dan mata sehingga mengakibatkan luka ringan maupun luka berat.
Mengindentifikasi potensi bahaya yang akan terjadi dengan menggunakan pendekatan data,penggunaan chek list dan pendekatan sistem proses kerjaTerjadi Insiden berupa
terjatuh dari ketinggian sehingga mengakibatkan luka ringan maupun luka berat.
Terjadi Insiden berupa kaki pekerja kejatuhan perlatan seperti sehingga terjadi luka.
Akan disediakan sepatu boat pelindung kaki
Akan disediakan helm pelindung kepala
Terkena sisa potongan aluminium, dan bahan lainnya sehingga terjadi luka dibagian kepala pekerja sehingga terjadi luka baik luka ringan maupun luka berat.
Akan disediakan masker pelindung muka dan mataAkan disediakan sarung tangan pelindung tanganAkan disediakan tali pelindung sehingga tidak langsung terjatuh dari ketinggian
Mengindentifikasi potensi bahaya yang akan terjadi dengan menggunakan pendekatan data,penggunaan chek list dan pendekatan sistem proses kerja
NO JENIS / TYPE PEKERJAAN PENGENDALI RESIKO K3
Pekerjaan Kaca Jenis Bahaya dan ResikoPengendalian resiko K31 Pas. Kaca
IDENTIFIKASI JENIS BAHAYA & RESIKO K3
Terjadi Insiden berupa kaki, tangan, mata dan badan pekerja terkena pecahan kaca sehingga menimbulkan luka baik luka ringan maupun luka berat.
Akan disediakan sepatu boat pelindung kaki
Akan disediakan helm pelindung kepala
Akan disediakan masker pelindung muka dan mataAkan disediakan sarung tangan pelindung tanganAkan disediakan tali pelindung sehingga tidak langsung terjatuh dari ketinggian
Mengindentifikasi potensi bahaya yang akan terjadi dengan menggunakan pendekatan data,penggunaan chek list dan pendekatan sistem proses kerja
Akan disediakan kotak P3K
NO JENIS / TYPE PEKERJAAN PENGENDALI RESIKO K3
Pekerjaan Lainnya Jenis Bahaya dan ResikoPengendalian resiko K31 Pek. Finishing
xxxxxxxxxxx, 29 Juli 2013
Dibuat Oleh,Kontraktor Pelaksana :xxxxxxxxxxxxxxxxxxxx
xxxxxxxxxxxxxxxxxxxDirektur
IDENTIFIKASI JENIS BAHAYA & RESIKO K3
Terjadi Insiden berupa kaki, tangan, mata dan badan pekerja terkena bahan/material sehingga menimbulkan luka baik luka ringan maupun luka berat.
Akan disediakan sepatu boat pelindung kaki
Akan disediakan helm pelindung kepala
Akan disediakan masker pelindung muka dan mataAkan disediakan sarung tangan pelindung tanganAkan disediakan tali pelindung sehingga tidak langsung terjatuh dari ketinggian
Mengindentifikasi potensi bahaya yang akan terjadi dengan menggunakan pendekatan data,penggunaan chek list dan pendekatan sistem proses kerja
Akan disediakan kotak P3K