PRESENTASI PROPOSAL SINGKAT PROYEK PERUMAHAN "BHUMI BINTAN RESIDENCE " PROYEKSI PERHITUNGAN - CASH FLOW (ARUS KAS) < 1 # BL. 1. TAHUN 1. TAHUN 2. TAHUN 3. TAHUN 4. ( BULAN 0 ) TRIWULAN 1 TRIWULAN 2 TRIWULAN 3 TRIWULAN 4 SEMESTER 1 SEMESTER 2 SEMESTER 1 SEMESTER 2 SEMESTER 1 SEMESTER 2 A. SUMBER DANA : 1 PENDAPATAN USAHA : - BOOKING FEE - 64,500,000 64,500,000 64,500,000 64,500,000 86,000,000 86,000,000 - - - - 430,000,000 - DOWN PAYMENT - 1,701,750,000 1,701,750,000 1,701,750,000 1,701,750,000 2,269,000,000 2,269,000,000 - - - - 11,345,000,000 - KPR - - - - - 8,242,500,000 8,242,500,000 4,121,250,000 4,121,250,000 1,373,750,000 1,373,750,000 27,475,000,000 - KELEBIHAN TANAH - - - - - 151,200,000 151,200,000 75,600,000 75,600,000 25,200,000 25,200,000 504,000,000 2 MODAL AWAL - - - - - - - - - - - - 3 PINJAMAN INVESTASI & MODAL KERJA 9,745,250,000 - - - - - - - - - - 9,745,250,000 9,745,250,000 1,766,250,000 1,766,250,000 1,766,250,000 1,766,250,000 10,748,700,000 10,748,700,000 4,196,850,000 4,196,850,000 1,398,950,000 1,398,950,000 49,499,250,000 B. PENGGUNAAN DANA : 1 INVESTASI / DEPOSIT - - - - - - - - - - - - 2 BIAYA OPERASIONAL a. MANAGEMENT PROYEK Biaya Konsultan Perencana - 202,500,000 - - - - - - - - - 202,500,000 Biaya Pembelian Lahan - 2,700,000,000 - - - - - - - - - 2,700,000,000 Biaya IMB dan SPMB - 168,750,000 - - - - - - - - - 168,750,000 Biaya Legalitas PBB dan Sertifikat Induk - 39,375,000 - - - - - - - - - 39,375,000 Biaya Pemasaran Rumah - - - - - 477,048,000 477,048,000 238,524,000 238,524,000 79,508,000 79,508,000 1,590,160,000 Biaya Entertainment - 9,000,000 9,000,000 9,000,000 9,000,000 13,500,000 13,500,000 9,000,000 9,000,000 4,500,000 4,500,000 90,000,000 Biaya Overhead Kantor/Manajemen - 39,375,000 39,375,000 39,375,000 39,375,000 78,750,000 78,750,000 78,750,000 78,750,000 78,750,000 78,750,000 630,000,000 Pajak Penjualan 5 % - - - - - - - - - - - - b. PEKERJAAN TANAH Cut and Fill - 189,000,000 - - - - - - - - - 189,000,000 c. PEKERJAAN KONSTRUKSI Rumah Type 36 / 72 - 1,170,000,000 1,170,000,000 1,170,000,000 1,170,000,000 - - - - - - 4,680,000,000 Rumah Type 45 / 90 - - - - - 1,687,500,000 1,687,500,000 - - - - 3,375,000,000 Rumah Type 60 / 120 - - - - - 1,350,000,000 1,350,000,000 - - - - 2,700,000,000 Rumah Toko (Ruko) Type 90 / 54 - 1,260,000,000 1,260,000,000 1,260,000,000 1,260,000,000 - - - - - - 5,040,000,000 NO. KETERANGAN TOTAL JHY - 08/05/2012

description

Presentasi Proposal Singkat pada Proyek Perumahan Bhumi Bintan Residence, Tg. Pinang

Transcript of Proyeksi Cashfow BhumiBIntanResidence_2

Page 1: Proyeksi Cashfow BhumiBIntanResidence_2

PRESENTASI PROPOSAL SINGKATPROYEK PERUMAHAN "BHUMI BINTAN RESIDENCE " PROYEKSI PERHITUNGAN - CASH FLOW (ARUS KAS)

< 1 # BL. 1. TAHUN 1. TAHUN 2. TAHUN 3. TAHUN 4.

( BULAN 0 ) TRIWULAN 1 TRIWULAN 2 TRIWULAN 3 TRIWULAN 4 SEMESTER 1 SEMESTER 2 SEMESTER 1 SEMESTER 2 SEMESTER 1 SEMESTER 2

A. SUMBER DANA :1 PENDAPATAN USAHA :

- BOOKING FEE - 64,500,000 64,500,000 64,500,000 64,500,000 86,000,000 86,000,000 - - - - 430,000,000 - DOWN PAYMENT - 1,701,750,000 1,701,750,000 1,701,750,000 1,701,750,000 2,269,000,000 2,269,000,000 - - - - 11,345,000,000 - KPR - - - - - 8,242,500,000 8,242,500,000 4,121,250,000 4,121,250,000 1,373,750,000 1,373,750,000 27,475,000,000 - KELEBIHAN TANAH - - - - - 151,200,000 151,200,000 75,600,000 75,600,000 25,200,000 25,200,000 504,000,000

2 MODAL AWAL - - - - - - - - - - - - 3 PINJAMAN INVESTASI & MODAL KERJA 9,745,250,000 - - - - - - - - - - 9,745,250,000

9,745,250,000 1,766,250,000 1,766,250,000 1,766,250,000 1,766,250,000 10,748,700,000 10,748,700,000 4,196,850,000 4,196,850,000 1,398,950,000 1,398,950,000 49,499,250,000

B. PENGGUNAAN DANA :

1 INVESTASI / DEPOSIT - - - - - - - - - - - -

2 BIAYA OPERASIONAL

a. MANAGEMENT PROYEK Biaya Konsultan Perencana - 202,500,000 - - - - - - - - - 202,500,000

Biaya Pembelian Lahan - 2,700,000,000 - - - - - - - - - 2,700,000,000

Biaya IMB dan SPMB - 168,750,000 - - - - - - - - - 168,750,000

Biaya Legalitas PBB dan Sertifikat Induk - 39,375,000 - - - - - - - - - 39,375,000

Biaya Pemasaran Rumah - - - - - 477,048,000 477,048,000 238,524,000 238,524,000 79,508,000 79,508,000 1,590,160,000

Biaya Entertainment - 9,000,000 9,000,000 9,000,000 9,000,000 13,500,000 13,500,000 9,000,000 9,000,000 4,500,000 4,500,000 90,000,000

Biaya Overhead Kantor/Manajemen - 39,375,000 39,375,000 39,375,000 39,375,000 78,750,000 78,750,000 78,750,000 78,750,000 78,750,000 78,750,000 630,000,000

Pajak Penjualan 5 % - - - - - - - - - - - -

b. PEKERJAAN TANAH Cut and Fill - 189,000,000 - - - - - - - - - 189,000,000

c. PEKERJAAN KONSTRUKSI Rumah Type 36 / 72 - 1,170,000,000 1,170,000,000 1,170,000,000 1,170,000,000 - - - - - - 4,680,000,000

Rumah Type 45 / 90 - - - - - 1,687,500,000 1,687,500,000 - - - - 3,375,000,000

Rumah Type 60 / 120 - - - - - 1,350,000,000 1,350,000,000 - - - - 2,700,000,000

Rumah Toko (Ruko) Type 90 / 54 - 1,260,000,000 1,260,000,000 1,260,000,000 1,260,000,000 - - - - - - 5,040,000,000

NO. KETERANGAN TOTAL

JHY - 08/05/2012

Page 2: Proyeksi Cashfow BhumiBIntanResidence_2

PRESENTASI PROPOSAL SINGKATPROYEK PERUMAHAN "BHUMI BINTAN RESIDENCE " PROYEKSI PERHITUNGAN - CASH FLOW (ARUS KAS)

< 1 # BL. 1. TAHUN 1. TAHUN 2. TAHUN 3. TAHUN 4.( BULAN 0 ) TRIWULAN 1 TRIWULAN 2 TRIWULAN 3 TRIWULAN 4 SEMESTER 1 SEMESTER 2 SEMESTER 1 SEMESTER 2 SEMESTER 1 SEMESTER 2

d. BIAYA PEMASANGAN AIR KE PDAM Rumah Type 36 / 72 - 50,000,000 50,000,000 50,000,000 50,000,000 - - - - - - 200,000,000

Rumah Type 45 / 90 - - - - - 50,000,000 50,000,000 - - - - 100,000,000

Rumah Type 60 / 120 - - - - - 30,000,000 30,000,000 - - - - 60,000,000

Rumah Toko (Ruko) Type 90 / 54 - 20,000,000 20,000,000 20,000,000 20,000,000 - - - - - - 80,000,000

e. BIAYA PEMASANGAN LISTRIK KE PLN Rumah Type 36 / 72 - 62,500,000 62,500,000 62,500,000 62,500,000 - - - - - - 250,000,000

Rumah Type 45 / 90 - - - - - 62,500,000 62,500,000 - - - - 125,000,000

Rumah Type 60 / 120 - - - - - 37,500,000 37,500,000 - - - - 75,000,000

Rumah Toko (Ruko) Type 90 / 54 - 25,000,000 25,000,000 25,000,000 25,000,000 - - - - - - 100,000,000

f. PEKERJAAN EXTERNAL Jalan Aspal, termasuk bouxite, duststone

Saluran/Drainase

Landscaping - 60,750,000 60,750,000 60,750,000 60,750,000 - - - - - - 243,000,000

Pagar Lokasi

Pintu Gerbang Utama

3 PENGEMBALIAN PINJAMAN INVESTASI - - - - - - - - - - - -

4 PENGEMBALIAN PINJAMAN MODAL KERJA - - - - - - - - - - 9,745,250,000 9,745,250,000

5 PAJAK PENGHASILAN - - - - - - - - - - - -

- 6,546,500,000 3,246,875,000 3,246,875,000 3,246,875,000 3,786,798,000 3,786,798,000 326,274,000 326,274,000 162,758,000 9,908,008,000 34,584,035,000

C. CASH SURPLUS (DEFISIT) 9,745,250,000 (4,780,250,000) (1,480,625,000) (1,480,625,000) (1,480,625,000) 6,961,902,000 6,961,902,000 3,870,576,000 3,870,576,000 1,236,192,000 (8,509,058,000) 14,915,215,000

BEGINNING BALANCE (SALDO AWAL KAS) - 9,745,250,000 4,965,000,000 3,484,375,000 2,003,750,000 523,125,000 7,485,027,000 14,446,929,000 18,317,505,000 22,188,081,000 23,424,273,000 -

ENDING BALANCE (SALDO AKHIR KAS) 9,745,250,000 4,965,000,000 3,484,375,000 2,003,750,000 523,125,000 7,485,027,000 14,446,929,000 18,317,505,000 22,188,081,000 23,424,273,000 14,915,215,000 14,915,215,000

NO. KETERANGAN TOTAL

- 425,250,000 425,250,000 425,250,000 425,250,000 - - - - - - 1,701,000,000

- 125,000,000 125,000,000 125,000,000 125,000,000 - - - - - - 500,000,000

JHY - 08/05/2012