    PROGRAM : PEMBANGUNAN JALAN DAN JEMBATAN

    KEGIATAN : PEMBANGUNAN JALAN DENGAN LAPIS PERMUKAAN ASPAL

    NAMA PEKERJAAN : LAPEN JALAN TAMBAN LINGK. II KELURAHAN BUNUT BARAT

    KEC. KISARAN BARAT

    UNIT KERJA : DINAS PEKERJAAN UMUM KABUPATEN ASAHAN

    TAHUN ANGGARAN : 2012

    No.JUMLAH HARGA

    ( Rp )

    1 6

    I PEKERJAAN PERSIAPAN 9,332,000.00

    II PEKERJAAN LAPEN SEPANJANG 450 X 3 M' 186,718,842.27

    III PEKERJAAN LAIN-LAIN 1,000,000.00

    JUMLAH TOTAL 196,050,842.27

    DIBULATKAN 196,050,000.00

    TERBILANG : Seratus Sembilan Puluh Enam Juta Lima Puluh Ribu Rupiah

    Kisaran, 11 Juli 2012Penawar,

    CV. DUA WARNA Dibuat Oleh,

    FERRY SYAHPUTRA NASUTION SARIA GINTINGDirektur Tenaga Teknis

    URAIAN KEGIATAN

    2

    REKAPITULASI ANGGARAN BIAYA

  • 7/22/2019 Lapen Jalan Tamban

    2/34

    PROGRAM : PEMBANGUNAN JALAN DAN JEMBATAN

    KEGIATAN : PEMBANGUNAN JALAN DENGAN LAPIS PERMUKAAN ASPAL

    NAMA PEKERJAAN : LAPEN JALAN TAMBAN LINGK. II KELURAHAN BUNUT BARAT

    KEC. KISARAN BARAT

    UNIT KERJA : DINAS PEKERJAAN UMUM KABUPATEN ASAHAN

    TAHUN ANGGARAN : 2012

    No.KODE

    ANALISAHARGA SATUAN

    (Rp.)HARGA TOTAL

    (Rp.)

    1 3 6 7

    I PEKERJAAN PERSIAPAN1. Pembuatan / Sewa Kantor Direksi Keet + Gudang Ls - 2,000,000.00 2,000,000.00

    2. Pengukuran dan Pemasangan Patok Kembali Ls - 1,200,000.00 1,200,000.00 3. Tanda Pengaman Lalu Lintas Ls - 850,000.00 850,000.00 4. Mobilisasi dan Demobilisasi Ls - 5,282,000.00 5,282,000.00

    9,332,000.00

    II PEKERJAAN LAPEN SEPANJANG 450 X 3 M'1. Pengupasan Tanah dan Pembersihan Semak K 210 450.00 M2 3,125.00 1,406,250.00 2. Perbaikan Existing dengan Telford / Penambahan Lebar K 516 85.69 M3 365,479.19 31,317,911.58 3. Lapisan Penetrasi Macadam ( Lapen ) K 618 1,350.00 M2 114,070.13 153,994,680.69

    186,718,842.27

    III PEKERJAAN LAIN-LAIN1. Foto Dokumentasi Ls - 400,000.00 400,000.00

    2. Plank Nama Proyek Ls 1.00 Bh 600,000.00 600,000.00 1,000,000.00

    197,050,842.27

    197,050,000.00

    SARIA GINTING

    Kisaran, 11 Juli 2012

    Dibuat Oleh

    ANGGARAN BIAYA

    URAIAN KEGIATAN

    2

    SUB JUMLAH

    KUANTITAS

    Terbilang : Seratus Sembilan Puluh Tujuh Juta Lima Puluh Ribu Rupiah

    Tenaga Teknis

    4

    SUB JUMLAH

    Penawar;CV. DUA WARNA

    FERRY SYAHPUTRA NASUTIONDirektur

    DIBULATKAN

    JUMLAH TOTAL

    SUB JUMLAH

  • 7/22/2019 Lapen Jalan Tamban

    3/34

    199,250,000

    197,950,000

  • 7/22/2019 Lapen Jalan Tamban

    4/34

    PEKERJAAN : LAPEN JALAN TAMBAN LINGK. II KELURAHAN BUNUT BARATKECAMATAN : KISARAN BARATKABUPATEN : ASAHAN

    NO. SATUAN KODESATUAN UPAHPer Hari ( Rp )

    KET

    A. HARGA SATUAN UPAH1 Mandor Orang L061 102,000.00 2 Mekanik Orang L071 93,000.00 3 Pembantu Mekanik Orang L072 78,000.00 4 Kepala Tukang Orang L073 95,000.00 5 Tukang Orang L079 90,000.00 6 Operator Terlatih Orang L081 110,000.00 7 Operator Kurang Terlatih Orang L082 87,500.00

    8 Pembantu Operator Orang L083 80,000.00 9 Sopir Terampil Orang L091 85,000.00

    10 Sopir Personil / Kernect Orang L092 80,000.00 11 Buruh Tak Terampil Orang L101 70,000.00 12 Buruh Semi Terlatih Orang L103 81,500.00 13 Buruh Terampil ( Pekerja ) Orang L106 82,000.00 14 Masinis Orang 117,000.00 15 Jaga Malam Orang 68,000.00

    B HARGA BAHAN / MATERIAL

    1 Pasir Pasang / Beton M3 M 041 55,000.00 2 Pasir Urug M3 M 040 50,000.00 3 Semen Zak M 080 55,000.00 4 Tanah Timbun M3 M 040 60,000.00 5 Kayu Bekisting M3 M 180 3,000,000.00 6 Paku Kg M 166 52,000.00 7 Batu Padas 10 - 15 cm M3 M 020 230,000.00 8 Batu Padas 5 - 7 cm M3 M 022 389,000.00 9 Batu Padas 3 - 5 cm M3 M 023 442,000.00

    10 Batu Padas 2 - 3 cm M3 M 024 481,000.00 11 Batu Padas 1 - 2 cm M3 M 025 502,000.00 12 Solar / Minyak Diesel Ltr M 065 5,000.00 13 Bensin Ltr 4,500.00 14 Pelumas Btl 30,000.00 15 Aspal Kg 14,080.00

    C ALAT BANTU DAN LAINNYA1 Alat-alat Kerja ( 3 set ) set M 170 150,000.00

    DAFTAR HARGA UPAH DAN BAHAN

    URAIAN

  • 7/22/2019 Lapen Jalan Tamban

    5/34

    Kisaran, 11 Juli 2012

    Dibuat Oleh :

    SARIA GINTING

    Tenaga TeknisDirektur

    CV. DUA WARNAPenawar

    FERRY SYAHPUTRA NASUTION

  • 7/22/2019 Lapen Jalan Tamban

    6/34

    KODE

    K 2 1 0

    URAIAN : ANGGAPAN / ASUMSI : 1. Mengupas dan Membuang semak-semak 1. Menggunakan tenaga manusia (1200 M2/hari) dengan tenaga manusia pada damija 2. Tidak ada pohon besar pada damija ( hanya semak ) (Daerah Milik Jalan) 3. Bakar sampah pada pekerjaan

    4. Hasil kerja 25 m2 / orang - hari 2. Lebar pengupasan dan pembersihan = damija-lebar 5. Umur alat bantu rata-rata 1 bulan / orang / set @ 3 alat badan jalan

    JUMLAHORANG

    HARI KODEJUMLAH

    HARI-KERJAUPAH

    (Rp/org/hari)B I A Y A

    ( Rp )SUB TOTAL

    ( Rp )

    Mandor 1.00 1 L061 1.00 102,000.00 102,000.00

    Buruh tak terlatih 48.00 1 L101 48.00 70,000.00 3,360,000.00

    PEKERJA 3,462,000.00

    JUMLAHBAHAN

    VOLUMESATUAN

    KODEHARGASATUAN

    ( Rp )

    BIAYA( Rp )

    SUB TOTAL( Rp )

    Alat Bantu 1.92 Set M170 150,000.00 288,000.00

    MATERIAL 288,000.00

    JUMLAH ALAT

    HARIKERJA

    KODEJAM

    KERJAHARGA

    ( Rp / Jam )B I A Y A

    ( Rp )SUB TOTAL

    PERALATAN -

    TOTAL Rp 3,750,000.00

    VOLUME : 1200 SATUAN M2 HARGA SATUAN Rp. 3,125.00 per M2

    P E K E R J A

    P

    ER AL

    AT

    AN

    PEKERJ

    A

    MATERIAL

    M ATERI

    AL

    P E R A L A T A N

    PROPINSI :SUMATERA

    ANALISA BIAYA PEKERJAAN

    PENGUPASAN & PEMBERSIHAN SEMAK PADA DAMIJA

    ( MENGGUNAKAN BURUH )

    DINAS PEKERJAAN UMUMKABUPATEN ASAHAN

    TAHUN ANGGARAN 2012

    KABUPATEN : ASAHAN

    KODE :DISIAPKAN OLEH :TANGGAL :

  • 7/22/2019 Lapen Jalan Tamban

    7/34

  • 7/22/2019 Lapen Jalan Tamban

    8/34

    KODE

    K 5 1 6

    URAIAN : ANGGAPAN / ASUMSI :1. Material disiapkan di lokasi pekerjaan 1. Menggunakan tenaga manusia (400 M2/hari)2. Pasir dihampar setebal 5 cm 2. Material ditimbun di sepanjang jalan oleh pemasok3. Batu Pecah Ukuran besar (10-15) di susun berdiri 3. Batu sudah dipecah (50% berat ukuran 10-15, 20% ukuran 5-7 dsb 30% pada hamparan pasir 5 cm Berat pasir urug4. Batu pecah ukuran lebih kecil dihampar di atasnya sehingga 4. Tanah dasar jalan sudah disiapkan rata kemudian dipadatkan / digilas dengan mesin gilas 5. Dipadatkan sampai tebal 20 cm

    6. Koefisien pemadatan = 1,2 7. Umur alat bantu rata-rata 1 bulan

    JUMLAH

    ORANGHARI KODE

    JUMLAH

    HARI-ORANG

    UPAH

    (Rp/org/hari)

    B I A Y A

    ( Rp )

    SUB TOTAL

    ( Rp )

    Mandor 2.00 1 L 061 2.00 102,000.00 204,000.00

    Operator Terlatih 1.00 1 L 081 1.00 110,000.00 110,000.00

    Pembantu Operator 1.00 1 L 089 1.00 80,000.00 80,000.00

    Sopir 1.00 1 L 091 1.00 85,000.00 85,000.00

    Pembantu Sopir 1.00 1 L 099 1.00 80,000.00 80,000.00

    Buruh Tak Terampil 80.00 1 L 101 80.00 70,000.00 5,600,000.00

    PEKERJA 6,159,000.00

    JUMLAHBAHAN

    VOLUMESATUAN KODE

    HARGA

    SATUAN( Rp )

    BIAYA( Rp )

    SUB TOTAL( Rp )

    Batu Padas 10 - 15 cm 50.00 M3 M 020 230,000.00 11,500,000.00 Batu Pecah 5 - 7 cm 20.00 M3 M 022 389,000.00 7,780,000.00 Pasir Urug 30.00 M3 M 040 50,000.00 1,500,000.00 Alat Bantu ( set@3 alat ) 3.20 set M 170 150,000.00 480,000.00

    MATERIAL 21,260,000.00

    JUMLAH ALAT

    HARIKERJA

    KODEJAM

    KERJAHARGA

    ( Rp / Jam )B I A Y A

    ( Rp )SUB TOTAL

    Mesin Gilas Roda Besi 8-10 Ton 1.00 1.00 E 080 5.00 172,137.00 860,685.00

    Truck Tangki Air 115 HP 1.00 1.00 E 182 5.00 191,730.00 958,650.00

    PERALATAN 1,819,335.00

    TOTAL Rp 29,238,335.00

    P E R A L A T A N

    PER AL

    AT

    AN

    P E K E R J A

    PEKERJ

    A

    MATERIAL

    M ATERI

    AL

    KODE :KABUPATEN :

    ASAHAN

    DISIAPKAN OLEH :

    TANGGAL :

    PROPINSI :

    SUMATERA

    DINAS PEKERJAAN UMUMKABUPATEN ASAHAN

    TAHUN ANGGARAN 2012

    ANALISA BIAYA PEKERJAAN

    PENGUPASAN & PEMBERSIHAN SEMAK PADA DAMIJA

    ( MENGGUNAKAN BURUH )

  • 7/22/2019 Lapen Jalan Tamban

    9/34

    VOLUME : 80 SATUAN M3 HARGA SATUAN Rp. 365,479.19 per M3

  • 7/22/2019 Lapen Jalan Tamban

    10/34

    #VALUE!

  • 7/22/2019 Lapen Jalan Tamban

    11/34

    KODE

    K 6 1 8

    KODE( 12 )

    KODE

    URAIAN : ANGGAPAN / ASUMSI : 1. Hampar agregat kasar 20 m2 / m3 1. Menggunakan Tenaga Buruh 2. Digilas & dipadatkan dengan mesin gilas roda tiga 2. Agregat pecah tersaring dikirim ke lokasi pekerjaan oleh pemasok 6 - 8 ton 3. Digunakan agregat pecah tersaring yang termurah3. Semprotkan aspal pengunci 64 m2 / m3 4. Agregat dihampar dengan tenaga manusia 4. Semprotkan aspal binder 2,5 kg / m2 5. Tebal padat perkerasan 5 cm 5. Hamparkan lapis seal dengan 12,5 mm 6. Permac sesuai rev. Spek. Umum B.M. Maret '89 - Buku chip 80 m2 / m3 & aspal 1,5 kg / m2

    JUMLAHORANG

    HARI KODE JUMLAHHARI-ORANGUPAH

    (Rp/org/hari)B I A Y A

    ( Rp )SUB TOTAL

    ( Rp )

    Mandor 6.00 3 L061 6.00 102,000.00 612,000.00

    Operator Terlatih 6.00 3 L061 6.00 110,000.00 660,000.00 Supir Terampil 3.00 3 L091 3.00 85,000.00 255,000.00

    Pembantu Supir 3.00 3 L101 3.00 80,000.00 240,000.00

    Pekerja Tak Terampil 174.00 3 L101 174.00 70,000.00 12,180,000.00 Pekerja Terampil 6.00 3 L106 6.00 82,000.00 492,000.00

    PEKERJA 13,947,000.00

    JUMLAHVOLUMESATUAN

    KODEHARGASATUAN

    ( Rp )

    BIAYA( Rp )

    SUB TOTAL( Rp )

    Batu Pecah 3 - 5 cm 56.00 M3 M 023 442,000.00 24,752,000.00 Batu Pecah 2 - 3 cm 31.11 M3 M 024 481,000.00 14,963,910.00 Batu Pecah 1 - 2 cm 15.55 M3 M 025 502,000.00 7,806,100.00 Pasir Beton 3.50 M3 M 041 55,000.00 192,500.00 Aspal 6,160.00 Kg M 061 14,080.00 86,732,800.00 Minyak Bakar 450.00 Ltr M 065 4,500.00 2,025,000.00 Alat Bantu 8.16 Set M 170 150,000.00 1,224,000.00

    MATERIAL 137,696,310.00

    JUMLAH ALAT

    HARIKERJA

    KODEJAM

    KERJAHARGA

    ( Rp / Jam )B I A Y A

    ( Rp )SUB TOTAL

    Mesin Gilas 3 Roda 8 - 10 T 1.00 3.00 E080 15.00 160,599.79 2,408,996.88 Aspal Sprayer 200 L 1.00 3.00 E154 15.00 203,676.54 3,055,148.06 Dump Truck 3,5 T 1.00 3.00 E211 15.00 172,715.50 2,590,732.44

    KABUPATEN ASAHAN DISIAPKAN OLEH : TANGGAL :

    P E K E R J A

    DIREKTORAT JENDERAL BINA MARGADIREKTORAT BINA PROGRAM JALAN

    SUB DIT. PERENCANAAN JALAN LOKAL &KABUPATEN

    ANALISA BIAYA PEKERJAAN

    LAPIS PENETRASI MACADAM

    ( MENGGUNAKAN BURUH )

    PER AL

    AT A

    PEKERJ

    A

    MATERIAL

    M ATERI

    AL

    P E R A L A T A N

    PROPINSISUMATERA

  • 7/22/2019 Lapen Jalan Tamban

    12/34

    PERALATAN 8,054,877.38

    TOTAL Rp 159,698,187.38

    VOLUME : 1400 SATUAN M2 HARGA SATUAN Rp. 114,070.13 per M3

    N

  • 7/22/2019 Lapen Jalan Tamban

    13/34

    KODE

    E 080

    0 6

    JENIS ALAT : ROLLER 3 WHEEL 6 - 8 TON TENAGA 37 HP

    HARGA :

    UMUR KERJA : 10 Year : Jam

    1 Thn : Hari Kerja

    Atau : 5 Jam Kerja : 1,500 jam FAKTOR (CRF) :

    A. BIAYA PEMILIKAN (OWNERSHIP COST) : ( Rp. / Jam )

    1. Despresiasi : 90 % x (CRF) x 1Jam /Tahun

    x x x 1

    2. Lain-lain :

    Asuransi 3% Thn + PPN 10% % x Harga

    Jam/Tahun

    x

    SUB TOTAL =

    B. BIAYA OPERASI (OPERATING COST) ( Rp / Jam )

    Kebutuhan Bahan Bakar dan Pelumas tiap HP :

    Diesel = Liter/HP/Jam

    Bensin = Liter/HP/Jam

    Pelumas = Liter/HP/Jam

    Harga : Solar / Minyak Diesel = Rp. / Liter Bensin = Rp. / Liter

    Pelumas = Rp. / Liter

    Bahan Bakar = x 51 x =

    Pelumas = x 51 x =

    Perbaikan dan Pareparts = x x =

    ( 60 % x depresiasi )

    SUB TOTAL =

    30,000.00

    DIREKTORAT BINA PROGRAM JALAN BIAYA ALAT UNTUK PERHITUNGAN

    SUBDIT. PERENC. JALAN LOKAL ANALISA BIAYA PEKERJAAN

    DAN KABUPATEN

    PROPINSI KODE

    SUMATERA UTARA 1 DISIAPKAN TANGGAL

    571,988,300.00

    2 ASAHAN

    1 Hari 0.18062

    15,000

    300

    Alat

    =0.90 571,988,300.00

    KABUPATEN KODE

    61,987.516Rp1,500.00

    3.3

    0.03 571,988,300.00= 11,439.766Rp

    1,500.00

    0.18062=

    87,172.510Rp

    73,427.282Rp

    0.160

    1.170

    0.006

    0.160 5,000.00Rp 40,800.000Rp

    5,000.00

    4,500.00

    0.006 30,000.00Rp 9,180.000Rp

    0.6 61,987.52Rp 37,192.51Rp

  • 7/22/2019 Lapen Jalan Tamban

    14/34

    TOTAL BIAYA PEMILIKAN DAN BIAYA OPERASIONAL

    A + B = + = / Jam

    KODE

    E 182

    0 6

    JENIS ALAT : WATER TANK TRUCK TENAGA 115 HP

    HARGA :

    UMUR KERJA : 8 Year : Jam

    1 Thn : Hari Kerja

    Atau : 5 Jam Kerja : 1,200 jam FAKTOR (CRF) :

    A. BIAYA PEMILIKAN (OWNERSHIP COST) : ( Rp. / Jam )

    1. Despresiasi : 90 % x (CRF) x 1

    Jam /Tahun

    x x x 1

    2. Lain-lain :

    Asuransi 3% Thn + PPN 10% % x Harga

    Jam/Tahun

    x

    SUB TOTAL =

    B. BIAYA OPERASI (OPERATING COST) : ( Rp / Jam )

    Kebutuhan Bahan Bakar dan Pelumas tiap :

    Diesel = Liter/HP/Jam

    Bensin = Liter/HP/Jam

    Pelumas = Liter/HP/Jam

    4,249.57Rp

    30,362.75Rp

    0.160

    1.170

    3.3

    0.03 169,982,800.00=1,200.00

    0.006

    0.20483

    Alat

    =0.9 169,982,800.00 0.20483

    = 26,113.18Rp1,200.00

    1 Hari

    DISIAPKAN TANGGAL

    169,982,800.00

    9,600

    300

    KODE

    SUMATERA UTARA 1 2 ASAHAN

    KODE KABUPATEN

    DIREKTORAT BINA PROGRAM JALAN BIAYA ALAT UNTUK PERHITUNGAN

    SUBDIT. PERENC. JALAN LOKAL ANALISA BIAYA PEKERJAAN

    73,427.282Rp 87,172.510Rp 160,599.79Rp

    DAN KABUPATEN

    PROPINSI

  • 7/22/2019 Lapen Jalan Tamban

    15/34

    Harga : Solar / Minyak Diesel = Rp. / Liter

    Bensin = Rp. / Liter

    Pelumas = Rp. / Liter

    Bahan Bakar = x 115 x =

    Pelumas = x 115 x =

    Perbaikan dan Pareparts = x =

    ( 60 % x depresiasi ) =

    SUB TOTAL =

    TOTAL BIAYA PEMILIKAN DAN BIAYA OPERASIONAL

    A + B = + = / Jam

    KODE

    E 153

    0 9

    JENIS ALAT : ASPHALT SPRAYER TOWED 200 L TENAGA 25 HPHARGA :

    UMUR KERJA : 6 Year : Jam

    1 Thn : Hari Kerja

    Atau : 5 Jam Kerja : 1,200 jam FAKTOR (CRF) :

    A. BIAYA PEMILIKAN (OWNERSHIP COST) : ( Rp. / Jam )

    1. Despresiasi : 90 % x (CRF) x 1Jam /Tahun

    x x x 1

    2. Lain-lain :

    Asuransi 3% Thn + PPN 10% % x Harga

    Jam/Tahun

    x

    30,362.75Rp 128,367.91Rp 158,730.66Rp

    0.6 26,113.18 15,667.91Rp

    128,367.910Rp

    0.160 5,000.00Rp 92,000.000Rp

    0.006 30,000.00Rp 20,700.000Rp

    5,000.00

    4,500.00

    30,000.00

    DIREKTORAT BINA PROGRAM JALAN BIAYA ALAT UNTUK PERHITUNGAN

    SUMATERA UTARA 1 2

    SUBDIT. PERENC. JALAN LOKAL ANALISA BIAYA PEKERJAAN

    DAN KABUPATEN

    ASAHAN DISIAPKAN TANGGAL

    396,000,000.00

    7,200

    300

    3.3

    0.033 396,000,000.00=

    750.00

    PROPINSI KODE KABUPATEN KODE

    1 Hari 0.23668

    Alat

    =0.9 396,000,000.00 0.23668

    = 112,470Rp

  • 7/22/2019 Lapen Jalan Tamban

    16/34

    SUB TOTAL =

    B. BIAYA OPERASI (OPERATING COST) : ( Rp / Jam )

    Kebutuhan Bahan Bakar dan Pelumas tiap :

    Diesel = Liter/HP/Jam

    Bensin = Liter/HP/Jam

    Pelumas = Liter/HP/Jam

    Harga : Solar / Minyak Diesel = Rp. / Liter

    Bensin = Rp. / Liter

    Pelumas = Rp. / Liter

    Bahan Bakar = x 7 x =

    Pelumas = x 7 x =

    Perbaikan dan Pareparts = x =

    ( 60 % x depresiasi ) =SUB TOTAL =

    TOTAL BIAYA PEMILIKAN DAN BIAYA OPERASIONAL

    A + B = + = / Jam

    KODE

    E 211

    0 9

    JENIS ALAT : DUMP TRUCK TENAGA 115 HP

    HARGA :UMUR KERJA : 6 Year : Jam

    1 Thn : Hari Kerja

    Atau : 5 Jam Kerja : 1300 jam FAKTOR (CRF) :

    A. BIAYA PEMILIKAN (OWNERSHIP COST) : ( Rp. / Jam )

    1. Despresiasi : 90 % x (CRF) x 1

    , 750.00

    129,894Rp

    4,500.00

    0.160

    1.170

    0.006

    5,000.00

    0.006 30,000.00Rp 1,260.000Rp

    30,000.00

    0.160 4,500.00Rp 5,040.000Rp

    DIREKTORAT BINA PROGRAM JALAN BIAYA ALAT UNTUK PERHITUNGAN

    73,782.202Rp

    129,894Rp 73,782.202Rp 203,676.54Rp

    SUMATERA UTARA 1 2

    SUBDIT. PERENC. JALAN LOKAL ANALISA BIAYA PEKERJAAN

    DAN KABUPATEN

    ASAHAN DISIAPKAN TANGGAL

    258,900,500.00

    7,800

    300

    67,482.20Rp

    PROPINSI KODE KABUPATEN KODE

    0.6 112,470.34Rp

    1 Hari 0.24668

    Alat

  • 7/22/2019 Lapen Jalan Tamban

    17/34

    Jam /Tahun

    x x x 1

    2. Lain-lain :

    Asuransi 3% Thn + PPN 10% % x Harga

    Jam/Tahun

    x

    SUB TOTAL =

    B. BIAYA OPERASI (OPERATING COST) ( Rp / Jam )

    Kebutuhan Bahan Bakar dan Pelumas tiap :

    Diesel = Liter/HP/Jam

    Bensin = Liter/HP/JamPelumas = Liter/HP/Jam

    Harga : Solar / Minyak Diesel = Rp. / Liter

    Bensin = Rp. / Liter

    Pelumas = Rp. / Liter

    Bahan Bakar = x 106 x =

    Pelumas = x 106 x =

    Perbaikan dan Pareparts = x =

    ( 60 % x depresiasi ) =

    SUB TOTAL =

    TOTAL BIAYA PEMILIKAN DAN BIAYA OPERASIONAL

    A + B = + = / Jam

    1.170

    0.006

    5,000.00

    6,572Rp1,300.00

    0.160 4,500.00Rp 76,320.000Rp

    50,787Rp

    3.3

    4,500.00

    0.033 258,900,500.00=

    0.160

    172,715.50Rp

    0.006 30,000.00Rp 19,080.000Rp

    30,000.00

    =0.9 258,900,500.00 0.24668

    = 44,215Rp1,300.00

    0.6 44,214.63Rp 26,528.78Rp

    121,928.777Rp

    50,787Rp 121,928.777Rp

  • 7/22/2019 Lapen Jalan Tamban

    18/34

  • 7/22/2019 Lapen Jalan Tamban

    19/34

    160,599.79Rp

  • 7/22/2019 Lapen Jalan Tamban

    20/34

    158,730.66Rp

  • 7/22/2019 Lapen Jalan Tamban

    21/34

    203,676.54Rp

  • 7/22/2019 Lapen Jalan Tamban

    22/34

    172,715.50Rp

  • 7/22/2019 Lapen Jalan Tamban

    23/34

    TOTALTAHUN

    JAM PERTAHUN

    TOTALJAM

    1 Grader 115 HP E 010 1,200,000,000 8 1,500 12,000 100 0.2048 2 Roller 3 Wheel 8-10 ton E 080 571,988,300 10 1,500 15,000 37 0.1806

    3 Roller Tandem 6-8 ton E 081 532,200,000 10 1,500 15,000 40 0.1806

    4 Roller Preumatic 8-15 ton E 084 1,056,000,000 10 1,500 15,000 95 0.1806 5 Concrete Vibrator E 089 55,200,000 5 600 3,000 4 0.2808

    6 Asphalt Finisher 1,820 mm/ 30 HP E 157 481,000,000 7 1,200 8,400 30 0.2260

    7 Asphall Sprayer Towed 200 ltr E 154 94,434,200 6 1,200 7,200 25 0.2366

    8 Water Tank Truck E 182 169,982,800 8 700 5,600 115 0.2048 9 Truck Picp Up 39 HP E 222 196,400,000 8 700 5,600 115 0.2048

    10 Concrete Mixer 125 L E 251 73,700,000 4 1,500 6,000 6 0.3327 11 Compressor 210 m3 / jam E 301 126,000,000 8 750 6,000 35 0.2048

    12 Water Pump 5 cm E 341 37,380,000 4 750 3,000 8 0.2048 13 Dump Truck 3,5 T / 115 HP E 211 258,900,500 6 1,300 7,800 115 0.2366

    Kisaran, 11Penawar,CV. DUA W

    FERRY SYDirektur

    DAFTAR HARGA DASAR PERALATANPEKERJAAN JALAN

    KABUPATEN ASAHANTAHUN ANGGARAN 2012

    KAPASITAS ALAT(HORSE POWER)

    No NAMA ALAT DAN KAPASITAS KODETOTAL BIAYAMODAL ( Rp )

    UMUR DAN KAFASITAS ALATCRF

  • 7/22/2019 Lapen Jalan Tamban

    24/34

    Rp / Jam Rp / Hari

    372,665.00 1,863,325.00

    160,599.79 802,998.96

    146,926.00 734,630.00

    308,726.00 1,543,630.00

    44,366.00 88,732.00

    173,510.00 694,040.00

    203,676.54 1,018,382.69

    158,730.66 793,653.31

    191,730.00 440,979.00

    30,893.00 154,465.00

    76,592.00 191,480.00

    33,213.00 83,032.50

    172,715.50 863,577.48

    li 2012

    NA

    PUTRA NASUTION

    HARGA ALAT

  • 7/22/2019 Lapen Jalan Tamban

    25/34

    PEKERJAAN : LAPEN JALAN TAMBAN LINGK. II KELURAHAN BUNUT BARATKECAMATAN : KISARAN BARATKABUPATEN : ASAHAN

    M1 M2 M3 M4 M1 M2 M3 M4 M1

    I PEKERJAAN PERSIAPAN1 Pembuatan / Sewa Kantor Direksi Keet + Gudang 2,000,000.00 1.01 1.01

    2 Pengukuran dan Pemasangan Patok Kembali 1,200,000.00 0.61 0.61

    3 Tanda Pengaman Lalu Lintas 850,000.00 0.43 0.43

    4 Mobilisasi dan Demobilisasi 5,282,000.00 2.68 1.34

    II PEKERJAAN LAPEN SEPANJANG 450 M X 3 M'

    1 Pengupasan Tanah dan Pembersihan Semak 1,406,250.00 0.71 0.36 0.35

    2 Perbaikan Existing dengan Telford / Penambahan Lebar 31,317,911.58 15.89 1.99 1.99 1.99 1.99 1.99 1.98

    3 Lapisan Penetrasi Macadam ( Lapen ) 153,994,680.69 78.15

    III PEKERJAAN LAIN-LAIN

    1 Photo Dokumentasi 400,000.00 0.20 0.07

    2 Plank Proyek 600,000.00 0.30 0.30

    JUMLAH 197,050,842.27 100.00

    RENCANA MINGGUAN 3.76 0.36 0.35 1.99 1.99 1.99 1.99 1.99 1.98

    RENCANA KUMULATIF MINGGUAN 0 3.76 4.12 4.47 6.46 8.45 10.44 12.43 14.42 16.40 1

    PENAWAR,CV. DUA WARNA

    FERRY SYAHPUTRA NASUTIONDirektur

    JADWAL WAKTU PELAKSANAAN ( TIME S

    NO URAIAN KEGIATAN HARGA TOTAL( Rp ) BOBOT( % )BULAN I BULAN II

    0

    3.76

    4.12

    4.47

    6.46

    8.45

    10.44

    12.43

    14.42

    16.4

  • 7/22/2019 Lapen Jalan Tamban

    26/34

    M1 M2 M3 M4

    1.34

    8.68 8.68 8.68 8.68

    0.06

    8.68 8.68 8.68 10.08

    72.56 81.24 89.92 100.00

    n, 11 Juli 2012

    Oleh,

    GINTINGa Teknis

    BULAN V KEMAJUANPEKERJAAN KET

    -

    20

    40

    60

    80

    100

    72.56

    81.2489.92

    100.00

  • 7/22/2019 Lapen Jalan Tamban

    27/34

    PEKERJAAN : LAPEN JALAN TAMBAN LINGK. II KELURAHAN BUNUT BARATKECAMATAN : KISARAN BARATKABUPATEN : ASAHAN

    M1 M2 M3 M4 M1 M2 M3 M4 M1

    II PEKERJAAN LAPEN SEPANJANG 450 M X 3 M'

    1 Perbaikan Existing dengan Telford / Penambahan Lebar Batu Padas 10 - 15 cm 53.56 M3 6.69 6.69 6.69 6.69 6.70 6.70 6

    Batu Pecah 5 - 7 cm 21.42 M3 2.68 2.68 2.68 2.68 2.68 2.68 2

    Pasir Urug 32.13 M3 4.02 4.02 4.02 4.02 4.02 4.01 4

    2 Lapisan Penetrasi Macadam ( Lapen )Batu Pecah 3 - 5 cm 54.00 M3Batu Pecah 2 - 3 cm 30.00 M3

    Batu Pecah 1 - 2 cm 14.99 M3Pasir Beton 3.38 M3 Aspal 5,940.00 KgMinyak Bakar 433.93 Ltr

    PENAWAR,CV. DUA WARNA

    FERRY SYAHPUTRA NASUTIONDirektur

    JADWAL PENGGUNAAN BAHAN

    NO URAIAN KEGIATAN VOL SAT BULAN I BULAN II

  • 7/22/2019 Lapen Jalan Tamban

    28/34

    M4 M1 M2 M3 M4

    6.00 6.00 6.00 6.00 6.00

    3.33 3.33 3.34 3.34 3.34

    1.67 1.66 1.66 1.66 1.66 0.38 0.37 0.37 0.37 0.37

    660.00 660.00 660.00 660.00 660.00

    48.21 48.21 48.21 48.21 48.21

    Kisaran, 11 Juli 2012

    Dibuat Oleh,

    SARIA GINTINGTenaga Teknis

    BULAN V KET

  • 7/22/2019 Lapen Jalan Tamban

    29/34

    PEKERJAAN : LAPEN JALAN TAMBAN LINGK. II KELURAHAN BUNUT BARAT

    KECAMATAN : KISARAN BARAT

    KABUPATEN : ASAHAN

    M1 M2 M3 M4 M1 M2 M3 M4 M1 M2 M

    II PEKERJAAN LAPEN SEPANJANG 450 X 3 M'1 Pengupasan Tanah dan Pembersihan Semak

    Alat Bantu 0.72 set 0.36 0.36

    2 Perbaikan Existing dengan Telford / Penambahan Lebar Mesin Gilas 3 Roda 6 - 8 T 5.36 jam 0.67 0.67 0.67 0.67 0.67 0.67 0.67 0.67

    Truck Tangki Air 5.36 jam 0.67 0.67 0.67 0.67 0.67 0.67 0.67 0.67

    Alat Bantu 3.43 set 0.43 0.43 0.43 0.43 0.43 0.43 0.43 0.42

    3 Lapisan Penetrasi Macadam ( Lapen )Mesin Gilas 3 Roda 6 - 8 T 14.46 jam

    Aspal Sprayer 200 L 14.46 jam

    Dump Truck 3,5 T 14.46 jam

    Alat Bantu 7.87 set

    PENAWAR,CV. DUA WARNA

    FERRY SYAHPUTRA NASUTIONDirektur

    JADWAL PENGGUNAAN ALAT

    NO URAIAN KEGIATAN

    TOTAL

    WAKTU(JAM)

    SATBULAN I BULAN II BULAN I

  • 7/22/2019 Lapen Jalan Tamban

    30/34

    M4 M1 M2 M3 M4

    1.61 1.61 1.60 1.60 1.60

    1.61 1.61 1.60 1.60 1.60

    1.61 1.61 1.60 1.60 1.60

    0.87 0.88 0.88 0.88 0.88

    n, 11 Juli 2012

    t Oleh,

    GINTINGa Teknis

    BULAN VKET

  • 7/22/2019 Lapen Jalan Tamban

    31/34

    PEKERJAAN : LAPEN JALAN TAMBAN LINGK. II KELURAHAN BUNUT BARAT

    KECAMATAN : KISARAN BARATKABUPATEN : ASAHAN

    NO VOLUME SATUAN KETERANGAN

    1 Batu Padas 10 - 15 cm 50.00 M3 Bahan dalam Negeri2 Batu Pecah 5 - 7 cm 20.00 M3 Bahan dalam Negeri3 Pasir Urug 30.00 M3 Bahan dalam Negeri4 Batu Pecah 3 - 5 cm 56.00 M3 Bahan dalam Negeri5 Batu Pecah 2 - 3 cm 31.11 M3 Bahan dalam Negeri6 Batu Pecah 1 - 2 cm 15.55 M3 Bahan dalam Negeri7 Pasir Beton 3.50 M3 Bahan dalam Negeri8 Aspal 6,160.00 Kg Bahan dalam Negeri9 Minyak Bakar 450.00 Ltr Bahan dalam Negeri

    Kisaran, 11 Juli 2012

    Dibuat Oleh;

    SARIA GINTINGTenaga Teknis

    FERRY SYAHPUTRA NASUTIONDirektur

    JENIS BAHAN KERJA YANG DIGUNAKAN

    JENIS BAHAN

    Diketahui Oleh;CV. DUA WARNA

  • 7/22/2019 Lapen Jalan Tamban

    32/34

    PEKERJAAN : LAPEN JALAN TAMBAN LINGK. II KELURAHAN BUNUT BARAT

    KECAMATAN : KISARAN BARATKABUPATEN : ASAHAN

    NOTAHUN

    PEMBUATANJUMLAH

    ALATMERK ALAT HARGA

    1 MESIN GILAS 3 RODA 6 - 8 Ton 2002 1 SAKAI R25-3 571,988,300

    2 WATER TANK TRUCK 2003 1 MITSUBISHI 169,982,800

    3 ASPAL SPRAYER 200 L 2000 1 SAKAI AS 155 94,434,200

    4 DUMP TRUCK 2007 5 MITSUBISHI 258,900,500

    Kisaran, 11 Juli 2012

    Dibuat Oleh;

    SARIA GINTINGTenaga Teknis

    FERRY SYAHPUTRA NASUTIONDirektur

    DAFTAR DAN HARGA PERALATAN UTAMA

    NAMA PERALATAN

    Diketahui Oleh;CV. DUA WARNA

  • 7/22/2019 Lapen Jalan Tamban

    33/34

    PEKERJAAN : LAPEN JALAN TAMBAN LINGK. II KELURAHAN BUNUT BARAT

    KECAMATAN : KISARAN BARATKABUPATEN : ASAHAN

    NOTAHUN

    PEMBUATANJUMLAH

    ALATMERK ALAT KETERANGAN

    1 MESIN GILAS 3 RODA 6 - 8 Ton 2002 1 SAKAI R25-3 DUKUNGA

    2 WATER TANK TRUCK 2003 1 MITSUBISHI DUKUNGA

    3 ASPAL SPRAYER 200 L 2000 1 SAKAI AS 155 DUKUNGAN

    4 DUMP TRUCK 2007 5 MITSUBISHI DUKUNGAN

    5 ALAT BANTU 2010 3 set variasi MILIK

    Kisaran, 11 Juli 2012

    Dibuat Oleh;

    SARIA GINTINGTenaga Teknis

    FERRY SYAHPUTRA NASUTIONDirektur

    NAMA PERALATAN

    DAFTAR PERALATAN YANG DIPAKAI / UTAMA

    Diketahui Oleh;CV. DUA WARNA

  • 7/22/2019 Lapen Jalan Tamban

    34/34

    PEKERJAAN : LAPEN JALAN TAMBAN LINGK. II KELURAHAN BUNUT BARAT

    KECAMATAN : KISARAN BARAT

    KABUPATEN : ASAHAN

    No. JABATAN PENDIDIKAN JUMLAH

    1 SARIA GINTING Tenaga Teknis STM 1 Orang

    2 TARWIDI Pel. Lapangan STM 1 Orang

    3 HENDRO LAKSMONO Logistik SMU 1 Orang

    4 FAHRANI DEWI NASUTION Administrasi Sarjana 1 Orang

    Diketahui Oleh;CV. DUA WARNA

    FERRY SYAHPUTRA NASUTIONDirektur

    SARIA GINTINGTenaga Teknis

    NAMA PERSONIL

    DAFTAR PERSONIL INTI

    Kisaran, 11 Juli 2012

    Dibuat Oleh;