FORM OF DOMESTIC CONTENT CALCULATION (FORMULIR PERHITUNGAN TINGKAT KOMPONEN DALAM NEGERI) PT. OSSIANA SAKTI EKAMAJU Jumlah Nilai Penawaran USD Total Quoted Price : ITEM KDN Pen URAIAN (Quote Nilai per Item % (% Domestic Nilai (DESCRIPTION) (Item Value) Content / DC) (Value) a b c d = a x c A. GOODS I. Material Terpakai (Used Material) 5.55 41.11% 40.38% 2.24 II. Peralatan (Equipment) Sub Jumlah (Sub Total) A 5.55 41.11% 2.24 B, SERVICES III Personil/Konsultan (Personnel/Consultant) IV. Alat Kerja/Peralatan (Tools/Equipment) V. Konstruksi/Fabrikasi (Construction/Fabrication 2.89 21.41% 100.00% 2.89 VI. Jasa Umum, dll (Other Services) 5.06 37.48% 100.00% 5.06 Sub Jumlah (Sub Total) B 7.95 58.89% 7.95 C. JUMLAH (TOTAL) 13.50 100.00% 10.19 = Sub Jumlah (Sub Total) A + B Note : b = Value per item / Total Offered Value x 100% e = Value of the Offered DC / Total Offered Value x 100% - Personnel / Consultant - Tools/Equipment - Construction/Fabrication - General Service, etc - Used Material - Equipment - Form Lit II may be coppied in line with number of biders % Komponen Dalam Negeri / KDN

Transcript of Draft Tkdn

Page 1: Draft Tkdn

FORM OF DOMESTIC CONTENT CALCULATION(FORMULIR PERHITUNGAN TINGKAT KOMPONEN DALAM NEGERI)

PT. OSSIANA SAKTI EKAMAJUJumlah Nilai Penawaran

USD 13.50 Total Quoted Price :

ITEMKDN Penawaran

URAIAN(Quoted DC)

Nilai per Item%

(% Domestic Nilai%

(DESCRIPTION) (Item Value) Content / DC) (Value)

a b c d = a x c e

A. GOODS

I. Material Terpakai (Used Material) 5.55 41.11% 40.38% 2.24 16.60%

II. Peralatan (Equipment)

Sub Jumlah (Sub Total) A 5.55 41.11% 2.24 16.60%

B, SERVICES

III. Personil/Konsultan (Personnel/Consultant)

IV. Alat Kerja/Peralatan (Tools/Equipment)

V. Konstruksi/Fabrikasi (Construction/Fabrication) 2.89 21.41% 100.00% 2.89 21.41%

VI. Jasa Umum, dll (Other Services) 5.06 37.48% 100.00% 5.06 37.48%

Sub Jumlah (Sub Total) B 7.95 58.89% 7.95 58.89%

C. JUMLAH (TOTAL)13.50 100.00% 10.19 75.49%

= Sub Jumlah (Sub Total) A + B

Note :

b = Value per item / Total Offered Value x 100%

e = Value of the Offered DC / Total Offered Value x 100%

- Personnel / Consultant

- Tools/Equipment

- Construction/Fabrication

- General Service, etc

- Used Material

- Equipment

- Form Lit II may be coppied in line with number of biders

% Komponen Dalam Negeri / KDN