PROGRAM : PROGRAM PENGADAAN, PENINGKATAN SARANA DAN PRASARANA RUMAH SAKIT/ RUMAH SAKIT JIWA RUMAG SAKIT PARU-PARU/ RUMAH SAKIT MATA NAMA KEGIATAN : PEMBANGUNAN RUMAH SAKIT REKAPITULASI RENCANA ANGGARAN BIAYA NAMA KEGIATAN : PEMBANGUNAN RUMAH SAKIT PEKERJAAN : PEMAGARAN RUMAH SAKIT PRATAMA LOKASI : KEC. NARMADA KAB. LOMBOK BARAT TAHUN ANGGARAN : 2015 1 3 I PEKERJAAN PERSIAPAN - Rp 2 NO URAIAN PEKERJAAN JUMLAH HARGA (RP) I PEKERJAAN PERSIAPAN - Rp II PEKERJAAN TANAH - Rp III PEKERJAAN PASANGAN DAN BETON - Rp IV PEKERJAAN BESI - Rp V PEKERJAAN PENUTUP LANTAI DAN DINDING - Rp VI PEKERJAAN PENGECATAN - Rp VII PEKERJAAN INSTALASI LISTRIK - Rp REAL COST - Rp PPN 10% - Rp JUMLAH - Rp JUMLAH - Rp PEMBULATAN - Rp TERBILANG : ..................,............,2015 Penawar CV./PT.,................................. ............................................... Jabatan

Transcript of 03 BOQ.pdf

  • PROGRAM : PROGRAM PENGADAAN, PENINGKATAN SARANA DAN PRASARANA RUMAH SAKIT/ RUMAH SAKIT JIWA/RUMAG SAKIT PARU-PARU/ RUMAH SAKIT MATA

    NAMA KEGIATAN : PEMBANGUNAN RUMAH SAKIT

    REKAPITULASI RENCANA ANGGARAN BIAYA

    NAMA KEGIATAN : PEMBANGUNAN RUMAH SAKITPEKERJAAN : PEMAGARAN RUMAH SAKIT PRATAMA LOKASI : KEC. NARMADA

    KAB. LOMBOK BARATTAHUN ANGGARAN : 2015

    1 3I PEKERJAAN PERSIAPAN -Rp

    2

    NO URAIAN PEKERJAAN JUMLAH HARGA (RP)

    I PEKERJAAN PERSIAPAN -Rp II PEKERJAAN TANAH -Rp III PEKERJAAN PASANGAN DAN BETON -Rp IV PEKERJAAN BESI -Rp V PEKERJAAN PENUTUP LANTAI DAN DINDING -Rp VI PEKERJAAN PENGECATAN -Rp VII PEKERJAAN INSTALASI LISTRIK -Rp

    REAL COST -Rp PPN 10% -Rp JUMLAH -Rp JUMLAH -Rp PEMBULATAN -Rp

    TERBILANG :

    ..................,............,2015Penawar

    CV./PT.,.................................

    ...............................................Jabatan

  • PROGRAM : PROGRAM PENGADAAN, PENINGKATAN SARANA DAN PRASARANA RUMAH SAKIT/ RUMAH SAKIT JIWA/RUMAG SAKIT PARU-PARU/ RUMAH SAKIT MATA

    KEGIATAN : PEMBANGUNAN RUMAH SAKITPEKERJAAN : PEMAGARAN RUMAH SAKIT PRATAMA LOKASI : KEC. NARMADA

    KAB. LOMBOK BARATTAHUN ANGGARAN : 2015

    1 3 4 5 6 7I PEKERJAAN PERSIAPAN -Rp

    1 Uitzet & Bouplank 36,60 M 1.4. -Rp -Rp 2 Papan Nama Proyek 1,08 M2 1.4.a. -Rp -Rp

    II PEKERJAAN TANAH -Rp 1 Galian tanah pondasi Kurang 1 m 356,92 M 2.1. -Rp -Rp 2 Urugan tanah kembali 118,97 M 2.9. -Rp -Rp 3 Urugan tanah 84,37 M 2.11.a.1. -Rp -Rp 4 Urugan pasir 17,77 M 2.11.1. -Rp -Rp

    III PEKERJAAN PASANGAN DAN BETON -Rp 1 Pasangan pondasi batu Kosong 71,08 M3 3.9.c.1. -Rp -Rp 2 Pas. Batu Kali 1 Pc : 5 Ps 394,81 M3 3.3.1 -Rp -Rp 3 Pas. Bata 1/2 Bata 1 Pc : 5 Ps 539,20 M 4.12.1. -Rp -Rp 4 Pas. Bata 1/2 Bata 1 Pc : 5 Ps, Penebalan Kolom5 Plesteran dinding 1 Pc : 5 Ps (Tebal 15 mm) 1.565,29 M 5.5. -Rp -Rp 6 Plesteran Ciprat 1 PC : 2 Ps 492,94 M 5.23. -Rp -Rp 7 Pek. Siaran Pas. batu kali 177,70 M 5.26. -Rp -Rp 8 Acian dinding 1.565,29 M 5.27. -Rp -Rp 9 Roster bali 12,32 M 4.24.1.a -Rp -Rp

    10 Pas. Koloma. Kolom 10 x 10, (K175) 4,92 M3 7.5.c.1. -Rp -Rp

    11 Pas. Sloofa. Sloof 15 x 20, (K175) 16,50 M3 7.5.b.1. -Rp -Rp

    12 Pas. Baloka. Balok ring 10 x 15, (K175) 10,66 M3 7.5.d.1. -Rp -Rp

    13 Pas. Plata. Plat beton kepala kolom t = 12 cm, (K175) 4,72 M3 7.5.e.2. -Rp -Rp

    IV PEKERJAAN BESI -Rp 1 Pek. Pagar besi 77,03 m2 11.15.d.1.a -Rp -Rp

    V PEKERJAAN PENUTUP LANTAI DAN DINDING -Rp 1 Pes. Batu Candi 158,53 M2 13.58.1. -Rp -Rp

    VI PEKERJAAN PENGECATAN -Rp 1 Pek. Cat dinding 1.565,29 M2 14.6. -Rp -Rp 2 Pek. Cat penutup 2 lapis pada permukaan baja/kayu 146,83 M2 14.15. -Rp -Rp

    VII PEKERJAAN INSTALASI LISTRIK -Rp 1 Titik Lampu + Instalasi 41,00 Bh 15.1. -Rp -Rp

    HARGA SATUAN (RP) TOTAL HARGA (RP) TOTAL SUB ITEM (RP)

    2

    RENCANA ANGGARAN BIAYA

    NO URAIAN PEKERJAAN VOLUME SAT KODE ANALISA

  • 4. PEKERJAAN SIPIL

    4.1. Upah Pekerjaan Sipil/Bangunan

    NO. URAIAN SATUAN HARGA KET.

    1 2 3 4 51 Buruh Semi Terlatih OH2 Buruh Tak terlatih OH3 Buruh Terlatih OH4 Kepala Pemasak Aspal OH5 Kepala Penganyam Bronjong OH6 Kepala Tukang OH7 Mandor OH8 Mekanik OH9 Operator Kurang Terlatih OH10 Operator Terlatih OH11 Pekerja OH12 Pemasak Aspal/Tukang Aspal OH13 Pembantu Sopir OH14 Pembantu Mekanik OH15 Pembantu Operator OH16 Pemecah Batu OH17 Penganyam Bronjong OH18 Penggergaji OH19 Penggosok Tegel OH20 Penjaga Malam OH21 Sopir OH22 Tukang Aluminium/Kaca OH23 Tukang Batu OH24 Tukang Besi OH25 Tukang Bor OH26 Tukang Cat OH27 Rapat dan sejenisnya OH28 Tukang Kayu OH29 Tukang Las OH30 Tukang Listrik OH31 Tukang Pipa OH32 Tukang Politur OH33 Tukang Ukur OH34 Team Leader :

    - Pengalaman 10 Tahun OB- Pengalaman 9 Tahun OB- Pengalaman 8 Tahun OB- Pengalaman 7 Tahun OB- Pengalaman 6 Tahun OB- Pengalaman 5 Tahun OB

    4.3. Bahan Pekerjaan Sipil/Bangunan4.3.1. Bahan pasangan dan Tanah

    NO. URAIAN SATUAN HARGA KET.

    1 2 3 4 51 Bata Merah Kelas I bh2 Bata Merah Kelas II bh

    3 Batu Gunung Kualitas Baik m3

    4 Batu Kali m3

    5 Batu Kali Keping/Tempel m3

    6 Batu Belah 10-15 cm m3

    7 Batu Belah 15-20 cm m3

    HARGA SATUAN UPAH DAN BAHAN

  • 8 Batu Pecah 0,5-1 cm m3

    9 Batu Pecah 1-2 cm m3

    10 Batu Pecah 2-3 cm m3

    11 Batu Pecah 3-5 cm m3

    12 Batu Pecah 5-7 cm m3

    13 Gebalan Rumput m2

    14 Kapur Gamping/Labur m3

    15 Kapur Pasang m3

    16 Kerikil Alam - Royalti m3

    17 Kerikil Beton (maks. 30 mm) m3

    18 Kerikil Sungai m3

    19 Pasir Galian m3

    20 Pasir Pasang m3

    21 Pasir Beton m3

    22 Pasir Urug m3

    23 PC ( 50 kg ) Kg

    24 Semen Merah m3

    25 Semen Warna kg26 Mill kg

    27 Sirtu m3

    28 Tanah Liat m3

    29 Tanah Urug Biasa m3

    30 Tanah Urug Pilihan m3

    4.3.3. Bahan Kayu

    NO. URAIAN SATUAN HARGA KET.

    1 2 3 4 5

    1 Balok Kayu Begisting m3

    2 Balok Kayu Kelas I m3

    3 Balok Kayu Kelas II m3

    4 Balok Kayu Kelas III m3

    5 Dolken kayu 8 - 10 / 4 m batang6 Kayu list plapond 4 x 4 cm m'

    7 Lumbersearing Kelas I m2

    8 Lumbersearing Kelas II m2

    9 Papan Kayu Begisting m3

    10 Papan Kayu Kelas I m3

    11 Papan Kayu Kelas II m3

    12 Papan Kayu Kelas III m3

    4.3.6. Bahan Lantai

    NO. URAIAN SATUAN HARGA KET.

    1 2 3 4 5

    1 Batu Candi m2

    2 Batu Candi Garis m2

    3 Batu Granit (Kerikil Sikat) kg4 Batu Hias bh

    5 Batu Marino m2

    6 Batu Paras m2

    7 Batu Teraso (Kerikil Sikat) kg8 Granit 40 x 40 m9 Granit 30 x 60 m10 Granit 60 x 60 m11 Gymfloor (Lantai Kayu) m12 Karpet m

    13 Keramik Dinding 10 x 20 m2

  • 14 Keramik Dinding 20 x 20 m2

    15 Keramik Dinding 20 x 25 m2

    16 Keramik Dinding 25 x 40 m2

    17 Keramik Lantai KW I 20 x 20 m2

    18 Keramik Lantai KW I 30 x 30 m2

    19 Keramik Lantai KW I 40 x 40 m2

    20 Keramik Lantai KW I 60 x 60 m2

    21 Keramik Lantai KW II 30 x 30 m2

    22 Keramik Lantai KW II 40 x 40 m2

    23 Keramik Lantai KW II 60 x 60 m2

    24 Keramik Artistik 10/20 m25 Keramik Artistik 5/20 m26 Marmer 100 x 100 cm m27 Mozaik 30/30 m28 Parquet m29 Plint Internal Cove artistik 5 x 5/20 m30 Plint Keramik artistik 10/10 m31 Plint Keramik artistik 10/20 m32 Plint Keramik artistik 5/20 m33 Plint Ubin Abu-abu 10/40 m34 Plint Ubin Abu-abu 15/20 m35 Plint Ubin Abu-abu 15/30 m36 Plint Ubin Granit 10/30 m37 Plint Ubin Granit 10/40 m38 Plint Ubin Teralux Kerang 10/30 m39 Plint Ubin Teralux Kerang 10/40 m40 Plint Ubin Teralux Marmer 10/30 m41 Plint Ubin Teralux Marmer 10/40 m42 Plint Ubin Teralux Marmer 10/60 m43 Plint Ubin Teraso 10/30 m44 Plint Ubin Teraso 10/40 m45 Plint Ubin Warna 10/20 m46 Plint Ubin Warna 10/30 m47 Plint Ubin Warna 10/40 m48 Porselin 10/20 m49 Porselin 11/11 m50 Porselin 20/20 m

    51 Roster Bali m2

    52 Tegel Abu-abu 20/20 cm m2

    53 Tegel Teraso Klas I 30/30 cm m2

    54 Tegel Teraso Klas II 30/30 cm m2

    55 Tegel Wapel 20/20 cm m2

    56 Tegel Warna 20/20 cm m2

    57 Tegel Warna Wapel 20/20 cm m2

    58 Teraso Cor m59 Ubin Abu-abu 20/20 m60 Ubin Abu-abu 30/30 m61 Ubin Abu-abu 40/40 m62 Ubin Granit 30/30 m63 Ubin Granit 40/40 m64 Ubin Keramik 10/33 m65 Ubin Keramik 20/20 m66 Ubin Keramik 30/30 m67 Ubin Keramik 33/33 m68 Ubin Keramik 40/40 m69 Ubin Keramik artistik 10/10 m

  • 70 Ubin Keramik artistik 10/20 m71 Ubin Teralux Kerang 30/30 m72 Ubin Teralux Kerang 40/40 m73 Ubin Teralux Marmer 30/30 m74 Ubin Teralux Marmer 40/40 m75 Ubin Teralux Marmer 60/60 m76 Ubin Teraso 30/30 m77 Ubin Teraso 40/40 m78 Ubin Warna 20/20 m79 Ubin Warna 30/30 m80 Ubin Warna 40/40 m81 Underlayer / rubber corrugated m82 Vinyl 30/30 m83 Vinyl karet 30/30 m84 Wall Paper m'85 Marmer Palimanan

    10 x 20 m2

    15 x 30 m2

    20 x 20 m2

    20 x 30 m2

    30 x 30 m2

    30 x 40 m2

    85 Marmerta

    40 x 60 m2

    20 x 40 m2

    30 x 30 m2

    40 x 40 m2

    86 Marmer Tengger

    30 x 30 m2

    40 x 60 m2

    40 x 40 m2

    87 Marmer Batik

    30 x 30 m2

    40 x 40 m2

    60 x 60 m2

    88 Marmer Lampung

    30 x 30 m2

    40 x 40 m2

    60 x 60 m2

    89 Marmer Bandung

    15 x 30 m2

    20 x 30 m2

    30 x 30 m2

    40 x 40 m2

    40 x 60 m2

    60 x 60 m2

    4.3.7. Bahan Besi

    NO. URAIAN SATUAN HARGA KET.

    1 2 3 4 51 Akustik ukuran 30 x 30 cm lembar2 Akustik ukuran 30 x 60 cm lembar3 Akustik ukuran 60 x 120 cm lembar4 Alumunium Profil T m'

    5 Aluminium Vertical Blinds 0,2 mm m2

    6 Rangka kusen aluminium silver t = 2 mm 4" m'7 Rangka kusen aluminium warna t = 2 mm 4" m'8 Angker Dock bh

  • 9 Baja Ringan setara KST. 10000-SS m2

    10 Baja Ringan setara KST. 12000-SS m2

    11 Baja Ringan setara KST. 12500-PC m2

    12 Baja Ringan setara KST. 4000-DS m2

    13 Baja Ringan setara KST. 6000-DS m2

    14 Baja Ringan setara KST. 6000-PC m2

    15 Baja Ringan setara KST. 7000-SS m2

    16 Baja Ringan setara KST. 8000-SS m2

    17 Baja Ringan setara KST. 8500-PC m2

    18 Baja Ringan C75.75 kg18 Baut Mour bh19 Besi angkur 8 mm kg20 Besi Beton Polos kg21 Besi Beton Ulir kg22 Besi Beugel/Baut Kuda-kuda Bh23 Besi Kuningan kg24 Besi plat kg25 Besi Profil kg26 Besi Profil Black Steel kg27 Besi baja I Beam kg28 Besi baja H Beam kg29 Besi Strip 30 x 3 mm kg30 Besi Ulir Pintu Air 2" - 2,5" kg31 Holllow 2x3 cm t=0,3 m'32 Beugel Komplit kg33 Bout Mata Bor untuk Trimdeck bh34 CSP 10 - 16 X 16 HGS bh35 CTEKS 12-14 X 45 HGS bh36 Jaring kawat baja dilas kg37 Kawat Berduri kg38 Kawat Bronjong 3 mm kg39 Kawat Bronjong 4 mm kg

    40 Kawat Harmonika Gas (HG) m2

    41 Kawat Ikat Beton kg42 Kawat las kg

    43 Kawat Nyamuk Alumunium m2

    44 Kawat Nyamuk Plastik m2

    45 Klip-Lok MTEKS 10-16 X WAF bh46 Kontra Mur 12 mm bh47 Nok Zingkalum T=0,35 mm Color m'48 Paku 1 - 3 cm kg49 Paku 4 - 6 cm kg50 Paku 7 - 12 cm kg51 Paku Asbes kg52 Paku Eternit kg53 Paku Kait Bh54 Paku Sekrup 10 cm bh55 Paku Sekrup 5 cm bh56 Paku Seng kg57 Paku Sumbat kg58 Paku Tahan Karat kg59 Paku Tripleks kg60 Plat Strip Klem talang 4 mm bh61 Sekrup Fixer Bh62 Sekrup/Piles 1,5 cm kotak63 Sekrup/Piles 2 cm kotak

  • 64 Screw Spandek 7 cm bh65 Screw Fixer/Ripeat bh66 Topspan C75 Hi-Ten Tebal 0.6 TCT m'67 Zilcalume C75 Hi-Ten Tebal 0.8 TCT m'68 Zilcalume C75 Hi-Ten Tebal 1.05 TCT m'69 Zingkalum 0,30 mm Color L. 0,75M m'70 Zingkalum 0,35 mm Color L. 0,75M m'71 Zingkalum 0,40 mm Color L. 0,75M m'72 Zingkalum 0,45 mm Color L. 0,75M m'

    4.3.8. Bahan Plafond

    NO. URAIAN SATUAN HARGA KET.

    1 2 3 4 51 Calsiboard 120 x 240 x 3 mm lembar2 Calsiboard 120 x 240 x 6 mm lembar3 Eternit 100 x 100 cm lembar4 Formika Putih 120 x 240 cm lembar5 Formika Warna 120 x 240 cm lembar6 GRC 12 mm lembar7 GRC 6 mm lembar8 GRC 9 mm lembar9 Gypsum Board 120 x 240 x 9 mm lembar10 Lem Kayu kg11 List Gypsum C7 m'12 Plywood 120 x 240 x 3 mm lembar13 Teak Block 120 x 240 x 12 mm lembar14 Teak Block 120 x 240 x 18 mm lembar15 Teak Block 120 x 240 x 6 mm lembar16 Teak Block 120 x 240 x 9 mm lembar17 Teakwoods 210 x 240 x 2 mm lembar18 Teakwoods 90 x 210 x 3 mm lembar19 Tepung Gypsum kg20 Tripleks 120 x 240 x 12 mm lembar21 Tripleks 120 x 240 x 18 mm lembar22 Tripleks 120 x 240 x 2 mm lembar23 Tripleks 120 x 240 x 3 mm lembar24 Tripleks 120 x 240 x 6 mm lembar25 Tripleks 120 x 240 x 9 mm lembar26 Tripleks lapis alumunium lembar27 Wood Plank 1/20 lembar28 Wood Plank 1/30 lembar

    4.3.10. Bahan Cat dan Finishing

    NO. URAIAN SATUAN HARGA KET.

    1 2 3 4 51 Alkali Liter2 Ampelas lembar3 Aqua Proof kg4 Cairan Pengeras Cat (Hardner) kg5 Cairan Pengupas Cat kg6 Cat Besi kg7 Cat Corak Batu kg8 Cat Genteng kg9 Cat Halus kg10 Cat Kayu Mutu Menengah kg11 Cat Kayu Mutu Tinggi kg12 Cat Marka Jalan Biasa kg13 Cat Marka Jalan Scalato kg14 Cat Tembok Mutu Menengah kg

  • 15 Cat Tembok Mutu Tinggi kg16 Dempul Isamo kg17 Dempul Kayu kg18 Kapek bh19 Kuas bh20 Melamin lembar21 Meni Besi kg22 Meni Kayu kg23 Minyak Cat/Abtiner Liter24 Plamir Kayu kg25 Plamir Tembok kg26 Politur Liter27 Residu Liter28 Roll Cat bh29 Sabun Kg30 Sikat Baja bh31 Spirtus Liter32 Sprayer bh33 Teak Oil Liter34 Teer kg35 Tiner A Spesial kg36 Vernis Liter37 Wood Filler Liter

    4.3.10. Bahan Pipa

    NO. URAIAN SATUAN HARGA KET.

    1 2 3 4 53. PIPA PVC SC S 10

    DIA. 20 mm (0,7874 Inc) m'DIA. 25 mm (0,98425 Inc) m'DIA. 32 mm (1,25984 Inc) m'DIA. 40 mm (1,5748 Inc) m'DIA. 50 mm (1,9685 Inc) m'DIA. 63 mm (2,48031 Inc) m'DIA. 75 mm (2,95276 Inc) m'DIA. 90 mm (3,54331 Inc) m'DIA. 110 mm (4,33071 Inc) m'DIA. 160 mm (6,29921 Inc) m'

    4.3.13. Bahan Lampu

    NO. URAIAN SATUAN HARGA KET.

    1 2 3 4 51 Bok Zekering Dua Group bh2 Bok Zekering Satu Group bh3 Bok Zekering Tiga Group bh4 Fitting Gantung bh5 Fitting Kombinasi bh6 Fitting Plafon bh7 KWH Listrik KWh8 Lampu Down Light bh9 Lampu Hias set10 Lampu Kapal bh11 Lampu LED bh12 Lampu Pijar bh13 Lampu SL bh14 Lampu Tanam SL bh15 Lampu TL bh16 Saklar Engkel Inbow bh

  • 17 Saklar Engkel Outbow bh18 Saklar Engkel Stop Inbow bh19 Saklar Engkel Stop Outbow bh20 Saklar Seri Inbow bh21 Saklar Seri Outbow bh22 Spot Light Halogen set23 Stop Contack + Instalasi bh24 Stop Kontak Inbow bh25 Stop Kontak Outbow bh26 Titik Lampu Pijar + Instalasi bh27 Titik Lampu TL bh28 Kabel NYA 3x2,5mm2 m'

    4.3.15. Bahan Lain - Lain

    NO. URAIAN SATUAN HARGA KET.

    1 2 3 4 51 Air Liter2 Alat Bantu Bina Marga set3 Angkutan Lokal GIP keg.4 Angkutan Lokal PVC keg.5 Aspal Buton kg6 Aspal Emulsi kg7 Aspal (Aspal Concrete/AC) kg8 Elastomer bh9 Filler/Kapur kg10 Floor Hardener kg11 Flux Oil Liter12 HCL/Pembersih Lantai Liter13 Karung Plastik lembar

    14 Kayu Bakar m3

    15 Minyak Tanah Liter16 Minyak Rem Liter17 Modifier Liter18 Olie SAE 140 Liter19 Olie SAE 90 Liter20 Olie SAE 40 Liter21 Olie SAE 10 (Hydraulic) Liter22 Premium Liter23 Soda Api kg24 Solar Liter25 Strorox-100 kg26 Waterstop PVC lebar 150 mm m'27 Waterstop PVC lebar 200 mm m'28 Waterstop PVC lebar 230 mm - 320 mm m'29 Roda Pintu Dorong R 10 cm bh30 Engsel 1,5" (Bubut) bh31 Alat bantu set32 Cetakan Huruf Bahan Vynil m233 Isolasi bh34 Sewa alat Jam

  • 1. PEKERJAAN PERSIAPAN

    1.4. 1 m' Pengukuran dan pemasangan bouwplank -Rp HARGA SATUANBAHAN/ UPAH

    (Rp.) (Rp.)Kayu Usuk Kelas III. 5/7 m

    30,012 -Rp -Rp

    Paku 7 - 12 cm kg 0,020 -Rp -Rp

    Papan Kayu Kelas III. 3/20 m3

    0,006 -Rp -Rp

    Pekerja OH 0,100 -Rp -Rp Tukang Kayu OH 0,100 -Rp -Rp Kepala Tukang OH 0,010 -Rp -Rp

    Mandor OH 0,005 -Rp -Rp -Rp

    1.4.a. 1 m Pasang Papan Nama Proyek -Rp HARGA SATUANBAHAN/ UPAH

    (Rp.) (Rp.)Kayu Usuk Kelas III. 5/7 m

    30,012 -Rp -Rp

    Paku 7 - 12 cm kg 0,020 -Rp -Rp

    Tripleks 120/240/3 mm m2

    0,350 -Rp -Rp

    Cetakan Huruf Bahan Vynil m3

    1,050 -Rp -Rp

    Pekerja OH 0,100 -Rp -Rp Tukang Kayu OH 0,100 -Rp -Rp Kepala Tukang OH 0,010 -Rp -Rp

    Mandor OH 0,005 -Rp -Rp -Rp

    2. PEKERJAAN TANAH

    2.1. 1 m3 Galian tanah biasa kedalaman 1 m -Rp HARGA SATUANBAHAN/ UPAH

    (Rp.) (Rp.)Pekerja OH 0,750 -Rp -Rp

    Mandor OH 0,025 -Rp -Rp -Rp

    2.9. 1 m3 Urugan kembali (1/3 kali indeks pekerjaan galian) -Rp HARGA SATUANBAHAN/ UPAH

    (Rp.) (Rp.)Pekerja OH 0,250 -Rp -Rp

    Mandor OH 0,008 -Rp -Rp -Rp

    2.11.1. 1 m3 Urugan pasir -Rp HARGA SATUANBAHAN/ UPAH

    (Rp.) (Rp.)Bahan Pasir urug m

    31,050 -Rp -Rp

    Pekerja OH 0,300 -Rp -Rp

    Mandor OH 0,010 -Rp -Rp -Rp

    JUMLAHKEBUTUHAN SATUAN INDEKS

    Bahan

    Tenaga kerja

    Jumlah Harga per Satuan Pekerjaan

    KEBUTUHAN SATUAN INDEKS

    JUMLAH

    Tenaga Kerja

    Jumlah Harga per Satuan Pekerjaan

    JUMLAH

    Bahan

    Tenaga kerja

    Jumlah Harga per Satuan Pekerjaan

    SATUAN

    Tenaga Kerja

    KEBUTUHAN SATUAN INDEKS

    INDEKS

    Jumlah Harga per Satuan Pekerjaan

    KEBUTUHAN SATUAN INDEKSJUMLAH

    KEBUTUHAN

    Tenaga Kerja

    Jumlah Harga per Satuan Pekerjaan

    ANALISA BIAYA PEKERJAAN

    JUMLAH

  • 2.11.a.1. 1 m3 Urugan tanah -Rp HARGA SATUANBAHAN/ UPAH

    (Rp.) (Rp.)Bahan Tanah Urug Biasa m

    31,050 -Rp -Rp

    Pekerja OH 0,300 -Rp -Rp

    Mandor OH 0,010 -Rp -Rp -Rp

    3. PEKERJAAN PONDASI

    3.3.1 1 m3 Pasangan Batu Kali 1 PC : 5 PS -Rp HARGA SATUANBAHAN/ UPAH

    (Rp.) (Rp.)Batu Kali m3 1,050 -Rp -Rp

    PC ( 50 kg ) kg 136,000 -Rp -Rp

    Pasir Pasang m3 0,544 -Rp -Rp

    Pekerja OH 1,500 -Rp -Rp Tukang batu OH 0,750 -Rp -Rp Kepala tukang OH 0,075 -Rp -Rp Mandor OH 0,075 -Rp -Rp

    -Rp

    3.9.c.1. 1 m3 Pasangan Batu Kosong (aanstamping) untuk Rumah Sederhana -Rp HARGA SATUANBAHAN/ UPAH

    (Rp.) (Rp.)Batu Gunung Kualitas Baik m3 1,050 -Rp -Rp

    Pasir Pasang m3 0,432 -Rp -Rp

    Pekerja OH 0,780 -Rp -Rp Tukang batu OH 0,390 -Rp -Rp Kepala tukang OH 0,039 -Rp -Rp Mandor OH 0,039 -Rp -Rp

    -Rp

    4. PEKERJAAN DINDING

    4.12.1. 1 m2 Pasangan bata merah tebal 1/2 bata, 1 PC : 5 PS -Rp HARGA SATUANBAHAN/ UPAH

    (Rp.) (Rp.)Bata Merah Kelas I bh 74,000 -Rp -Rp

    PC ( 50 kg ) kg 9,680 -Rp -Rp

    Pasir Pasang m3

    0,045 -Rp -Rp

    Pekerja OH 0,300 -Rp -Rp

    Tukang batu OH 0,100 -Rp -Rp

    Kepala tukang OH 0,010 -Rp -Rp

    Mandor OH 0,015 -Rp -Rp -Rp

    4.24.1.a 1 m2 Pasangan dinding roster bali, campuran spesi 1 PC : 3 PS -Rp HARGA SATUANBAHAN/ UPAH

    (Rp.) (Rp.)Roster Bali m2 1,000 -Rp -

    PC ( 50 kg ) kg 14,000 -Rp -

    Pasir Pasang m3

    0,032 -Rp -

    Pekerja OH 0,300 -Rp -

    Tukang batu OH 0,100 -Rp -

    Kepala tukang OH 0,010 -Rp -

    Mandor OH 0,015 -Rp - -

    Bahan

    SATUAN INDEKSJUMLAH

    KEBUTUHAN

    Tenaga Kerja

    Jumlah Harga per Satuan Pekerjaan

    KEBUTUHAN SATUAN INDEKSJUMLAH

    Tenaga Kerja

    Jumlah Harga per Satuan Pekerjaan

    KEBUTUHAN SATUAN INDEKS

    KEBUTUHAN

    JUMLAH

    Bahan

    Tenaga Kerja

    Jumlah Harga per Satuan Pekerjaan

    KEBUTUHAN SATUAN INDEKSJUMLAH

    Bahan

    Tenaga Kerja

    Jumlah Harga per Satuan Pekerjaan

    SATUAN INDEKSJUMLAH

    Bahan

    Tenaga Kerja

    Jumlah Harga per Satuan Pekerjaan

  • 5. PEKERJAAN PLESTERAN

    5.5. 1 m2 Plesteran Campuran 1 PC : 5 PS (15 mm) -Rp HARGA SATUANBAHAN/ UPAH

    (Rp.) (Rp.)PC ( 50 kg ) kg 5,184 - -Rp

    Pasir Pasang m3

    0,026 - -Rp

    Pekerja OH 0,300 - -Rp

    Tukang batu OH 0,150 - -Rp

    Kepala tukang OH 0,015 - -Rp

    Mandor OH 0,015 - -Rp -Rp

    5.23. 1 m2 Plesteran Ciprat 1 PC : 2 PS -Rp HARGA SATUANBAHAN/ UPAH

    (Rp.) (Rp.)PC ( 50 kg ) kg 4,320 - -Rp

    Pasir Pasang m3

    0,006 - -Rp

    Pekerja OH 0,300 - -Rp

    Tukang batu OH 0,100 - -Rp

    Kepala tukang OH 0,010 - -Rp

    Mandor OH 0,015 - -Rp -Rp

    5.26. 1 m2 Finishing siar pasangan batu kali adukan 1 PC : 2 PS -Rp HARGA SATUANBAHAN/ UPAH

    (Rp.) (Rp.)PC ( 50 kg ) kg 6,340 - -Rp

    Pasir Pasang m3

    0,012 - -Rp

    Pekerja OH 0,300 - -Rp

    Tukang batu OH 0,150 - -Rp

    Kepala tukang OH 0,015 - -Rp

    Mandor OH 0,015 - -Rp -Rp

    5.27. 1 m2 Acian -Rp HARGA SATUANBAHAN/ UPAH

    (Rp.) (Rp.)Bahan PC ( 50 kg ) kg 3,250 - -Rp

    Pekerja OH 0,200 - -Rp

    Tukang batu OH 0,100 - -Rp

    Kepala tukang OH 0,010 - -Rp

    Mandor OH 0,010 - -Rp -Rp

    7. PEKERJAAN BETON

    7.5. Membuat 1 m3 beton mutu fc = 14,5 MPa (K 175), slump (12 2) cm, w/c = 0,66 -Rp HARGA SATUANBAHAN/ UPAH

    (Rp.) (Rp.)PC ( 50 kg ) kg 326,000 -Rp -Rp

    Pasir Beton m3 0,543 -Rp -Rp

    Kerikil Beton (maks. 30 mm) m3 0,762 -Rp -Rp

    Air liter 215,000 -Rp -Rp Pekerja OH 1,650 -Rp -Rp Tukang batu OH 0,275 -Rp -Rp Kepala tukang OH 0,028 -Rp -Rp Mandor OH 0,083 -Rp -Rp

    -Rp

    JUMLAH

    Bahan

    Tenaga kerja

    Jumlah Harga per Satuan Pekerjaan

    INDEKS

    Bahan

    Tenaga kerja

    Jumlah Harga per Satuan Pekerjaan

    JUMLAH

    Tenaga kerja

    Jumlah Harga per Satuan Pekerjaan

    KEBUTUHAN SATUAN INDEKSJUMLAH

    KEBUTUHAN SATUAN

    SATUAN INDEKS

    Jumlah Harga per Satuan Pekerjaan

    Tenaga kerja

    Bahan

    KEBUTUHAN SATUAN INDEKSJUMLAH

    Bahan

    Tenaga kerja

    Jumlah Harga per Satuan Pekerjaan

    JUMLAHKEBUTUHAN

    KEBUTUHAN SATUAN INDEKS

  • 7.5.b.1. -Rp

    HARGA SATUANBAHAN/ UPAH

    (Rp.) (Rp.)Beton Mutu K175 m3 0,982 -Rp -Rp

    Begisting Sloof m2 13,333 -Rp -Rp

    Pembesian dengan Besi Beton Polos kg 143,292 -Rp -Rp -Rp

    7.5.c.1. Membuat 1 m3 Kolom 10 x 10 dengan beton mutu fc = 14,5 MPa (K 175), slump (12 2) cm, w/c = 0,66 -Rp HARGA SATUANBAHAN/ UPAH

    (Rp.) (Rp.)Beton Mutu K175 m3 1,000 -Rp -Rp

    Begisting Kolom m2 20,000 -Rp -Rp

    Pembesian dengan Besi Beton Polos kg 268,449 -Rp -Rp -Rp

    7.5.d.1. -Rp

    HARGA SATUANBAHAN/ UPAH

    (Rp.) (Rp.)Beton Mutu K175 m3 0,977 -Rp -Rp

    Begisting Balok m2 20,000 -Rp -Rp

    Pembesian dengan Besi Beton Polos kg 182,328 -Rp -Rp -Rp

    7.5.e.2. Membuat 1 m3 Plat Lantai t = 12 cm dengan beton mutu fc = 14,5 MPa (K 175), slump (12 2) cm, w/c = 0,66-Rp HARGA SATUANBAHAN/ UPAH

    (Rp.) (Rp.)Beton Mutu K175 m3 1,000 -Rp -Rp

    Begisting Plat Lantai m2 8,333 -Rp -Rp

    Pembesian dengan Besi Beton Polos kg 82,247 -Rp -Rp -Rp

    7.17.a. Pembesian 1 kg dengan besi beton polos -Rp HARGA SATUANBAHAN/ UPAH

    (Rp.) (Rp.)Besi Beton Polos kg 1,0500 -Rp -Rp Kawat Ikat Beton kg 0,0150 -Rp -Rp Pekerja OH 0,0070 -Rp -Rp Tukang besi OH 0,0070 -Rp -Rp Kepala tukang OH 0,0007 -Rp -Rp Mandor OH 0,0004 -Rp -Rp

    -Rp

    7.21.a.1. Memasang 1 m2 bekisting untuk sloof 15 x 20 (2x pakai) -Rp HARGA SATUANBAHAN/ UPAH

    (Rp.) (Rp.)Papan Kayu Kelas III. Tebal 3 cm m3 0,016 -Rp -Rp

    Paku 7 - 12 cm kg 0,300 -Rp -Rp Flux Oil liter - -Rp -Rp Pekerja OH 0,520 -Rp -Rp Tukang besi OH 0,260 -Rp -Rp Kepala tukang OH 0,026 -Rp -Rp Mandor OH 0,026 -Rp -Rp

    -Rp

    Jumlah Harga per Satuan Pekerjaan

    Tenaga kerja

    Jumlah Harga per Satuan Pekerjaan

    KEBUTUHAN SATUAN INDEKS

    Bahan

    Jumlah Harga per Satuan Pekerjaan

    JUMLAH

    Bahan

    Jumlah Harga per Satuan Pekerjaan

    KEBUTUHAN SATUAN

    KEBUTUHAN SATUAN INDEKSJUMLAH

    Membuat 1 m3 Balok Ring 10 x 15 dengan beton mutu fc = 14,5 MPa (K 175), slump (12 2) cm, w/c = 0,66

    INDEKSJUMLAH

    Bahan

    INDEKSJUMLAH

    Bahan

    Tenaga kerja

    Jumlah Harga per Satuan Pekerjaan

    Bahan

    KEBUTUHAN

    Membuat 1 m3 Sloof 15 x 20 dengan beton mutu fc = 14,5 MPa (K 175), slump (12 2) cm, w/c = 0,66

    KEBUTUHAN SATUAN INDEKS

    KEBUTUHAN SATUANJUMLAH

    Bahan

    Jumlah Harga per Satuan Pekerjaan

    INDEKS

    JUMLAH

    SATUAN

  • 7.22.a.1. Memasang 1 m2 bekisting untuk kolom praktis 10 x 10 (2x pakai) -Rp HARGA SATUANBAHAN/ UPAH

    (Rp.) (Rp.)Teak Block 120 x 240 x 9 mm lembar 0,184 -Rp -Rp Paku 7 - 12 cm kg 0,400 -Rp -Rp Dolken kayu 8 - 10 / 4 m batang 1,050 -Rp -Rp Pekerja OH 0,660 -Rp -Rp Tukang besi OH 0,330 -Rp -Rp Kepala tukang OH 0,033 -Rp -Rp Mandor OH 0,033 -Rp -Rp

    -Rp

    7.23.a.1. Memasang 1 m2 bekisting untuk balok ring 10 x 15 (2x pakai) -Rp HARGA SATUANBAHAN/ UPAH

    (Rp.) (Rp.)Teak Block 120 x 240 x 9 mm lembar 0,184 -Rp -Rp

    Bahan Balok Kayu Kelas III. 5/7 m3 0,009 -Rp -Rp

    Paku 7 - 12 cm kg 0,400 -Rp -Rp Pekerja OH 0,660 -Rp -Rp Tukang besi OH 0,330 -Rp -Rp Kepala tukang OH 0,033 -Rp -Rp Mandor OH 0,033 -Rp -Rp

    -Rp

    7.24.1. Memasang 1 m2 bekisting untuk plat (2x pakai) -Rp HARGA SATUANBAHAN/ UPAH

    (Rp.) (Rp.)Bahan Teak Block 120 x 240 x 9 mm lembar 0,184 -Rp -Rp

    Balok Kayu Kelas III. 5/7 m3 0,006 -Rp -Rp Paku 7 - 12 cm kg 0,400 -Rp -Rp Dolken kayu 8 - 10 / 4 m batang 1,050 -Rp -Rp Pekerja OH 0,660 -Rp -Rp Tukang besi OH 0,330 -Rp -Rp Kepala tukang OH 0,033 -Rp -Rp Mandor OH 0,033 -Rp -Rp

    -Rp

    11. PEKERJAAN BESI DAN ALUMINIUM

    11.5.1. Mengerjakan 1 cm pengelasan dengan elektroda 3,2 mm las listrik -Rp HARGA SATUANBAHAN/ UPAH

    (Rp.) (Rp.)Kawat las Kg 0,003 -Rp -Rp Solar liter 0,004 -Rp -Rp Flux Oil liter 0,004 -Rp -Rp Pekerja OH 0,001 -Rp -Rp Tukang Besi OH 0,000 -Rp -Rp Kepala tukang OH 0,000 -Rp -Rp Mandor OH 0,000 -Rp -Rp

    Alat Sewa alat jam 0,002 -Rp -Rp -Rp

    11.15.d.1.a Memasang 1 m2 pagar besi hollow rangka 50.50.1,6 dan 50.30.1,6 -Rp

    HARGA SATUANBAHAN/ UPAH

    (Rp.) (Rp.)Hollow 50.50.1,6 kg 3,161 -Rp -Rp Hollow 50.30.1,6 kg 12,642 -Rp -Rp Pengelasan cm 27,080 -Rp -Rp Pekerja OH 1,670 -Rp -Rp Tukang Las OH 1,670 -Rp -Rp Kepala tukang OH 0,167 -Rp -Rp Mandor OH 0,083 -Rp -Rp

    -Rp

    KEBUTUHAN SATUAN INDEKS

    Jumlah Harga per Satuan Pekerjaan

    Bahan

    Tenaga kerja

    JUMLAH

    Bahan

    Tenaga kerja

    Jumlah Harga per Satuan Pekerjaan

    JUMLAH

    KEBUTUHAN SATUAN INDEKS

    KEBUTUHAN SATUAN INDEKSJUMLAH

    KEBUTUHAN

    Tenaga kerja

    JUMLAHSATUAN INDEKS

    JUMLAH

    Tenaga kerja

    Jumlah Harga per Satuan Pekerjaan

    KEBUTUHAN SATUAN

    Bahan

    INDEKS

    Jumlah Harga per Satuan Pekerjaan

    Tenaga kerja

    Jumlah Harga per Satuan Pekerjaan

  • 13. PEKERJAAN PENUTUP LANTAI DAN DINDING

    13.58.1. 1 m2 Pasang dinding batu candi -Rp HARGA SATUANBAHAN/ UPAH

    (Rp.) (Rp.)Batu Candi m2 1,050 -Rp -

    PC ( 50 kg ) kg 11,750 -Rp -

    Pasir Pasang m3 0,035 -Rp -

    Pekerja OH 0,700 -Rp - Tukang batu OH 0,350 -Rp - Kepala tukang OH 0,035 -Rp - Mandor OH 0,035 -Rp -

    -

    14. PEKERJAAN PENGECATAN DAN FINISHING

    14.6. -Rp

    HARGA SATUANBAHAN/ UPAH

    (Rp.) (Rp.)Plamir tembok kg 0,100 -Rp -Rp Cat Tembok Mutu Tinggi kg 0,240 -Rp -Rp Ampelas Lembar 0,500 -Rp -Rp Kuas bh 0,015 -Rp -Rp Kapek bh 0,050 -Rp -Rp Pekerja OH 0,080 -Rp -Rp Tukang Cat OH 0,060 -Rp -Rp Kepala tukang OH 0,006 -Rp -Rp Mandor OH 0,004 -Rp -Rp

    -Rp

    14.15. 1 m2 Mengecat penutup 2 lapis pada permukaan baja secara manual -Rp HARGA SATUANBAHAN/ UPAH

    (Rp.) (Rp.)Cat Besi kg 0,200 -Rp -Rp Minyak Cat/Abtiner Liter 0,100 -Rp -Rp Kuas bh 0,020 -Rp -Rp Pekerja OH 0,150 -Rp -Rp Tukang Cat OH 0,150 -Rp -Rp Kepala tukang OH 0,015 -Rp -Rp Mandor OH 0,008 -Rp -Rp

    -Rp

    15. PEKERJAAN INSTALASI LISTRIK

    15.1. Pasang 1 Titik Lampu -Rp HARGA SATUANBAHAN/ UPAH

    (Rp.) (Rp.)Kabel NYA 3x2,5mm2 m' 3,000 -Rp -Rp Pipa PVC Dia. 5/8" Tipe AW m' 3,000 -Rp -Rp Isolasi bh 0,200 -Rp -Rp Tukang Listrik OH 1,000 -Rp -Rp Kepala Tukang OH 0,050 -Rp -Rp

    -Rp

    Tenaga kerja

    Jumlah Harga per Satuan Pekerjaan

    KEBUTUHAN SATUAN INDEKSJUMLAH

    Bahan

    Jumlah Harga per Satuan Pekerjaan

    1 m2 Pengecatan cat tembok, menggunakan kuas termasuk plamir

    KEBUTUHAN SATUAN INDEKS

    Bahan

    Tenaga kerja

    JUMLAH

    KEBUTUHAN SATUAN INDEKS

    Tenaga kerja

    Jumlah Harga per Satuan Pekerjaan

    KEBUTUHAN SATUAN INDEKS

    Tenaga kerja

    Jumlah Harga per Satuan Pekerjaan

    JUMLAH

    Bahan

    JUMLAH

    Bahan