  • SATUAN KERJA : Satuan Kerja Bandara Rembele

    PEKERJAAN : Pelapisan Landasan Pacu Existing (30 x 700 M'), Taxiway Existing (23 x 187m)

    Apron Existing (80 x 107 M'), Pemenuhan Standart Runway Strip 24.000 M2 dan

    Perluasan Turning (650 M2) dan Marking

    LOKASI : Bandara Rembele Kabupaten Bener Meriah

    TAHUN ANGGARAN : APBN 2014

    PENAWAR : PT. Flamboyant Huma Arta

    Perkiraan Harga Jumlah

    Kuantitas Satuan Harga

    ( Rp ) ( Rp )

    a b c d e f = ( d x e )

    A. PEKERJAAN PERSIAPAN

    1 Pembuatan barak kerja M2 36.00 1,500,000.00 54,000,000.00

    2 Mobilisasi dan Demobilisasi Paket 1.00 74,250,000.00 74,250,000.00

    3 Pengukuran awal dan akhir M2 34,695.00 821.43 28,499,464.29

    Sub Jumlah 156,749,464.29

    B. OVERLAY RUNWAY EXISTING 30 X 700 METER

    1 Tack Coat (Lapis Pengikat 1 Kg/M2) M2 12,600.00 20,271.15 255,416,435.93

    2 Leveling landasan Aspal ATBL M3 152.00 3,703,498.35 562,931,748.54

    3 Tack Coat (Lapis Pengikat 1 Kg/M2) M2 21,000.00 20,271.15 425,694,059.88

    4 Overlay dengan Aspal AC tebal 5 Cm M2 21,000.00 190,014.29 3,990,300,194.68

    5 Marka Landasan M2 960.00 86,367.23 82,912,539.23

    Sub Jumlah 5,317,254,978.27

    C. OVERLAY TAXI WAY EXISTING TERMASUK FILLET 23 X 187 METER

    1 Tack Coat (Lapis Pengikat 1 Kg/M2) M2 3,444.00 20,271.15 69,813,825.82

    2 Leveling landasan Aspal ATBL Tone 67.32 3,703,498.35 249,319,508.63

    3 Tack Coat (Lapis Pengikat 1 Kg/M2) M2 4,485.00 20,271.15 90,916,088.50

    4 Overlay dengan Aspal AC tebal 5 Cm M2 4,485.00 190,014.29 852,214,113.01

    5 Marka Taxiway M2 189.00 86,367.23 16,323,406.16

    Sub Jumlah 1,278,586,942.12

    D. OVERLAY APRON EXISTING 107 X 80 METER

    1 Tack Coat (Lapis Pengikat 1 Kg/M2) M2 8,560.00 20,271.15 173,521,007.27

    2 Leveling Apron Aspal ATBL Tone 140.00 3,703,498.35 518,489,768.40

    3 Tack Coat (Lapis Pengikat 1 Kg/M2) M2 8,560.00 20,271.15 173,521,007.27

    4 Overlay dengan Aspal AC tebal 5 Cm M2 8,560.00 190,014.29 1,626,522,365.07

    5 Marka Landasan M2 151.67 86,367.23 13,099,317.53

    Sub Jumlah 2,505,153,465.53

    E. PERLUASAN TURNING AREA 650 M2

    1 Galian tanah dan pembuangan M3 390.00 39,913.21 15,566,153.82

    2 Pemadatan tanah dasar M2 650.00 3,876.88 2,519,969.33

    3 Sub Base course tebal 40 Cm M3 260.00 271,788.61 70,665,039.64

    4 Base course tebal 25 Cm M3 97.50 545,669.76 53,202,802.01

    5 Prime Coat M2 650.00 37,216.61 24,190,794.48

    6 Aspalt ATB tebal 7,5 Cm M3 48.75 3,669,680.45 178,896,921.84

    7 Tack Coat (Lapis Pengikat 1 Kg/M2) M2 650.00 20,271.15 13,176,244.71

    8 AC 5 Cm M2 650.00 190,014.29 123,509,291.74

    9 Marka Landasan M2 54.00 86,367.23 4,663,830.33

    Sub Jumlah 486,391,047.91

    Ke halaman 2

    BILL OF QUANTITY

    No. Uraian Satuan

  • 03. Bill Of Quantityboq hal2