SATUAN KERJA : Satuan Kerja Bandara Rembele
PEKERJAAN : Pelapisan Landasan Pacu Existing (30 x 700 M'), Taxiway Existing (23 x 187m)
Apron Existing (80 x 107 M'), Pemenuhan Standart Runway Strip 24.000 M2 dan
Perluasan Turning (650 M2) dan Marking
LOKASI : Bandara Rembele Kabupaten Bener Meriah
TAHUN ANGGARAN : APBN 2014
PENAWAR : PT. Flamboyant Huma Arta
Perkiraan Harga Jumlah
Kuantitas Satuan Harga
( Rp ) ( Rp )
a b c d e f = ( d x e )
A. PEKERJAAN PERSIAPAN
1 Pembuatan barak kerja M2 36.00 1,500,000.00 54,000,000.00
2 Mobilisasi dan Demobilisasi Paket 1.00 74,250,000.00 74,250,000.00
3 Pengukuran awal dan akhir M2 34,695.00 821.43 28,499,464.29
Sub Jumlah 156,749,464.29
B. OVERLAY RUNWAY EXISTING 30 X 700 METER
1 Tack Coat (Lapis Pengikat 1 Kg/M2) M2 12,600.00 20,271.15 255,416,435.93
2 Leveling landasan Aspal ATBL M3 152.00 3,703,498.35 562,931,748.54
3 Tack Coat (Lapis Pengikat 1 Kg/M2) M2 21,000.00 20,271.15 425,694,059.88
4 Overlay dengan Aspal AC tebal 5 Cm M2 21,000.00 190,014.29 3,990,300,194.68
5 Marka Landasan M2 960.00 86,367.23 82,912,539.23
Sub Jumlah 5,317,254,978.27
C. OVERLAY TAXI WAY EXISTING TERMASUK FILLET 23 X 187 METER
1 Tack Coat (Lapis Pengikat 1 Kg/M2) M2 3,444.00 20,271.15 69,813,825.82
2 Leveling landasan Aspal ATBL Tone 67.32 3,703,498.35 249,319,508.63
3 Tack Coat (Lapis Pengikat 1 Kg/M2) M2 4,485.00 20,271.15 90,916,088.50
4 Overlay dengan Aspal AC tebal 5 Cm M2 4,485.00 190,014.29 852,214,113.01
5 Marka Taxiway M2 189.00 86,367.23 16,323,406.16
Sub Jumlah 1,278,586,942.12
D. OVERLAY APRON EXISTING 107 X 80 METER
1 Tack Coat (Lapis Pengikat 1 Kg/M2) M2 8,560.00 20,271.15 173,521,007.27
2 Leveling Apron Aspal ATBL Tone 140.00 3,703,498.35 518,489,768.40
3 Tack Coat (Lapis Pengikat 1 Kg/M2) M2 8,560.00 20,271.15 173,521,007.27
4 Overlay dengan Aspal AC tebal 5 Cm M2 8,560.00 190,014.29 1,626,522,365.07
5 Marka Landasan M2 151.67 86,367.23 13,099,317.53
Sub Jumlah 2,505,153,465.53
E. PERLUASAN TURNING AREA 650 M2
1 Galian tanah dan pembuangan M3 390.00 39,913.21 15,566,153.82
2 Pemadatan tanah dasar M2 650.00 3,876.88 2,519,969.33
3 Sub Base course tebal 40 Cm M3 260.00 271,788.61 70,665,039.64
4 Base course tebal 25 Cm M3 97.50 545,669.76 53,202,802.01
5 Prime Coat M2 650.00 37,216.61 24,190,794.48
6 Aspalt ATB tebal 7,5 Cm M3 48.75 3,669,680.45 178,896,921.84
7 Tack Coat (Lapis Pengikat 1 Kg/M2) M2 650.00 20,271.15 13,176,244.71
8 AC 5 Cm M2 650.00 190,014.29 123,509,291.74
9 Marka Landasan M2 54.00 86,367.23 4,663,830.33
Sub Jumlah 486,391,047.91
Ke halaman 2
BILL OF QUANTITY
No. Uraian Satuan
-
03. Bill Of Quantityboq hal2