TO: Red Wing Port Authority Board
FROM: Shari Chorney, Port Authority Manager
Agenda Item No.: 11. A. Little River Dredging Payment Amendment
Meeting Date: November 4, 2020
ACTION REQUESTED:
Motion to Approve a Revised Payment to LSM Marine and Riverview Tug Servicesfor $59, 185 for the Little River Bulkhead Dredging Project.
ATTACHMENTS:
LSM Marine Contractors invoice dated October 26, 2020
Riverview Tug Service invoice dated October 1, 2020Voigt Consultants Proposal and Scope of Services dated September 24, 2020
BACKGROUND:
At our October 6th meeting, the board authorization payment of up to $46, 000 to LSM
Marine and Riverview Tug for the Little River Bulkhead dredge. Staff included a caveat
that at the time of the meeting, we did not have the final invoice. Since our last meeting, we have received the final invoices from both LSM Marine Contractors and Riverview
Tug Service for a total of $59, 185. LSM Marine ended up removing 6, 000 cubic yards.
Why Two Companies
Because this was an " emergency" dredge, LSM Marine, who was booked out until mid- November was unable to completely service a dredge, specifically providing a tugboatand associated crew. Thanks to the creativity and relationships that CD Corporationour bulkhead operator) has, they quickly coordinated efforts between LSM Marine and
Riverview Tug to mobilize and demobilize equipment and provide tug boat service withLSM Marine performing the actual dredge.
In addition, Public Works needed an emergency dredge at Colvill Marina. Public Works
reached out to LSM Marine to see if they could accommodate their dredge at the sametime. Typically mobilization costs are shared between the Port Authority and PublicWorks. The hope is that we will share in the mobilization cost of $ 30, 235.
315 West 4th St
Red Wing, MN 55066Website:
www.redwingportauthority.orgPhone: 651. 385. 3638
DISCUSSION:
Staff is asking the Port Board to approve the actual invoiced expenditure of $59, 285,
and staff will further review a cost sharing for mobilization with Public Works.
Due to the ongoing challenges of dredging costs, the Harbor Commission LeaseCommittee met on October 20th with Rick Voigt of Voigt Consultants. In addition to
discussion around his proposal for dock repairs, Rick discussed an evaluation of the
river channel. This would include Sediment Modeling of the river's reach near the dockand the Colvill Marina entrance. See Voigt Consultants Proposal dated September 24,
2020. Public Works will be responsible for the services related to Colvill Marina.
Rick will be presenting his proposal at the November 23, 2020 Harbor CommissionBoard. Staff will provide an update at the Port Authority meeting.
In addition, our bulkhead operator is looking into dredging equipment to assist withfuture maintenance dredging issues.
BUDGET:
The monies for this project will come from Improvements other than Buildings 236-
46600-54150, which has a current unspent balance of $220, 000. This was intended to
be used for possible bulkhead repairs in 2020, but it can be used for dredging as well.
RECOMMENDATION:
Staff recommends that the Port Authority Board authorize the payment to LSM MarineContractors and Riverview Tug Services for the authorized dredging services at a totalcost of $59, 185.
315 West 4th St
Red Wing, MN 55066Website:
www.redwingportauthority.orgPhone: 651. 385. 3638
E3E 0Marine Contractors
LS MARINE
3000 Centerville Road, Suite D
St. Paul, Minnesota 55117
651) 653- 6307 phone
CUSTOMER
Red Wing Port Authority419 Bush Street
Red Wing, Minnesota 55066
Project: Little River Bulkhead Dredging
ITEM DESCRIPTION
1 Little River Bulkhead DredgingSee Attached Payment Voucher for Breakdown
If you have any questions regarding this Invoice, please contact
INVOICE
INVOICE NO.: 20046
DATE: 10/ 26/2020
PROJECT NO: 20910
ACCOUNT NO: RWPA
PO/ CONTRACT NO.:
QTY UNIT PRICE TOTAL
1 36,610. 00 36, 610. 00
SUBTOTAL 36, 610. 00
SALES TAX N/ A
INVOICE TOTAL $ 36.610. 00
Taylor Luke
612) 554- 9764
taylorl@lsmarine. com
To: Red Wing Port Authority
419 Bush Street
Red Wing, Minnesota 55066
ATTN: Shari Chorney
FROM: LS Marine, Inc.
3000 Centerville Road, Suite D
St. Paul, Minnesota 55117
PAYMENT VOUCHER
PROJECT: Little River Bulkhead Dredging
Pay Application: 0001
APPLICATION DATE: 10/ 26/ 2020
PERIOD FROM: 9/ 28/ 2020
PERIOD TO: 9/ 30/ 2020
PROJECT NO: 20910
TOTALS $ $ $ 36, 610. 00 $ 36, 610. 00
CONTRACT INFORMATION QUANTITY COMPLETED WORK COMPLETED TOTAL
ITEM
NO. DESCRIPTION U/ M QUANTITY
UNIT CONTRACT
PRICE AMOUNT
PREV THIS TO FROM
QTY PERIOD DATE PREV. PERIOD
THIS
PERIOD
COMPLETED
TO DATE
01 Mobilization/ Demobilization LS $ 7, 660. 00 0. 000 1. 000 1. 000 7, 660.00 7, 660. 00
02 Dredging HR $ 965. 00 0. 000 30. 000 30. 000 28, 950.00 28, 950. 00
TOTALS $ $ $ 36, 610. 00 $ 36, 610. 00
RIVERVIEW TUG SERVICE, INC.
960 NORTH RIVERVIEW
BELLEVUE, IA 52031
Bill To:
RED WING PORT AUTHORITY
SHARICHORNEY
419 BUSH STREET
RED WING, MN 55066
Description
Invoice #:
Invoice Date:
Due Date:
Project:
P. O. Number:
Invoice
20200549
10/ 1/ 2020
10/ 29/ 2020
Hours/Qty Rate Amount
M/ V CAPT BOWE PICKED UP BARGES, LOAD EQUIPMENT AND 22. 5 350. 00 7, 875. 00
TRANSPORTED TO RED WING ( 22. 5 HOURS)
M/ V CAPT BOWE MOVE DREDGE BARGES ( 11 HOURS 09/28, 11 30 350. 00 10, 500. 00
HOURS 09/29, 8 HOURS 09/ 30
RETURN DREDGE EQUIPMENT TO ST PAUL 12 HOURS 12 350. 00 4, 200.00
We appreciate your business! Total $ 22, 575. 00
Payments/ Credits $ 0. 00
Balance Due $ 22, 575. 00
VOIGT • CONSULTANTS, LLC
September 24, 2020
Ms. Shari ChorneyPort Authority ManagerRed Wing Port Authority419 Bush Street
Red Wing, MN 55066
Re: Proposal and Scope of Services for Dock Evaluation, recommended Short -
and Long -Term Repairs for the Dock and Sediment Modeling of the River Reachnear the Dock and the Colvill Park Marina Entrance Downstream.
Dear Ms. Chorney:
This letter proposes a Scope of Services and cost estimates for the evaluation of the dock,
recommended short term repairs, recommended options for long term repairs intended toextend the life of the dock as well as the modeling of the sediment transport through theLittle River channel in which the dock is located with the intent of developing solutionscapable of reducing or eliminating the need for dredging in the future. As proposed, thesediment modeling will be extended downstream to also evaluate the sedimentationoccurring in the Colvill Park Marina entrance. Voigt Consultants is teaming withEngineering Partners International, LLC to include specialized structural expertise on theteam.
SCOPE OF WORK
The proposed work scope consists of the following items. Tasks 1, 2, 3 and 6 arerecommended for completion as soon as possible, tasks 4, 5 and 7 can be completed
following the first round of tasks:
Task 1— Design Short Term Slab Repairs
Design repairs with the anticipated repair scope:
Perform partial depth repairs at locations where concrete is spalling ordeteriorated. Remove concrete to a minimum depth of 2 inches to competent
concrete with small chipping hammers. Sawcut the perimeter. Sand blast
817 19th AVENUE NORTH, SOUTH ST. PAUL, MN 55075
952- 292- 8486, RICKVOIGT @VOIGTCONSULTANTS. COM
existing reinforcing to remove corrosion. If reinforcing is corroded more than 20percent, remove and replace bars. Enlarge opening as required for required splicelengths. Install sealer along edges of repair. Provide special inspection forcleaning, reinforcing placement, concrete placement, and concrete cylinder tests.
Task 2 — Design Short Term Edge ofSlab Repair
Design repair with the anticipated repair scope:
Remove sections of the embedded angle where spalling, deterioration of theconcrete, or deterioration of the angle is present. Remove concrete to a minimum
depth of 2 inches to competent concrete with small chipping hammers. Sawcutthe perimeter. Sand blast existing reinforcing to remove corrosion. If reinforcingis corroded more than 20 percent, remove and replace bars. Enlarge opening asrequired for required splice lengths. Install sealer along edges of repair. Dowelreinforcing into adjacent competent slab to anchor new angle. Remove andreplace adjacent slab on grade as required, and repair subgrade where it has
washed away. Provide special inspection for cleaning, reinforcing placement, concrete placement, anchorage, and concrete cylinder tests.
Task 3 — Design Short Term Beam Repairs
Design repairs for ends of concrete beams along east edge of the structure. Anticipated repair scope to include:
Remove spalled or deteriorated concrete with small chipping hammers. Sandblast existing reinforcing to remove corrosion. Add bars and dowers as requiredto extend reinforcing into replaced concrete area. Form and place concrete. Provide special inspection for cleaning, reinforcing placement, concreteplacement, and concrete cylinder tests.
Task 4 — Develop comprehensive structural inspection proposal.
As more is learned about the structure in subsequent site visits and information
learned during the short-term repairs, develop a second phase proposal toinvestigate the current condition of the existing structure. Investigation to coverthe existing slab, concrete wall, and steel structure.
Task 5 - Develop a comprehensive structural upgrade plan based on the resultsofthe inspection.
Upon concurrence with the Port Authority regarding the long- term repairs, develop drawings to a level suitable for a preliminary cost estimate.
VOIGT CONSULTANTS LLC, 817 19" AVENUE NORTH, SOUTH ST. PAUL, MN 55075
952- 292- 8486, RICKVOIGT @VOIGTCONSULTANTS. COM
Task 6 —Evaluate hydrographic information ofthe reach from upstream ofthepoint where the Little River side channel begins downstream past the Colvill
Park Marina entrance. Evaluate the characteristics of the sediment near thedock and marina entrance.
Evaluate existing hydrographic information available for the river reach to bemodeled. If sufficient information is not adequate to develop a reliable model, recommend additional hydrographic survey be performed and coordinate dataacquisition performed by contractor.
Task 7 - Develop 2- d Model ofReach from the point where or just upstream ofthe Little River side channel begins downstream past the Colvill Park Marina
entrance.
Develop a 2- dimensional model of the reach of river extending from upstream ofthe point where the Little River side channel separates from the main channel
downstream of the Colvill Park Marina entrance.
Computational routines will be developed within the model analysis tools so that
the model data may also be used to compute bed shear and the corresponding sizeof the sediment subject to movement. This can be used to graphically show areasof the river bed that may be subject to changes in bed shear (potential scour ordeposition zones).
Prior to modeling discuss the modeling intent with USACE staff to develop anunderstanding of what sediment directing alternatives they would prefer as well asany initial concerns they may have.
Select river discharges for modeling that are representative of times of significantsediment transport in the Little River channel and the main river channel near the
Colvill Park Marina. Model the effectiveness of sediment directing alternativessuch as wing dams and vanes that may reduce the amount of sedimentationoccurring in front of the dock. The modeling will involve approximately fivedesign development runs evaluating and optimizing alternatives. Model two otherriver discharges with the proposed sediment directing alternatives in place toassess the general effectiveness at other river discharges.
Use model to look at techniques such as wing dams and vanes that may reduce theamount of sedimentation occurring within the inlet of the Colvill Park Marina. The modeling will involve approximately five design development runsevaluating and optimizing alternatives. Model two other river discharges with theproposed sediment directing alternatives in place to assess the generaleffectiveness at other river discharges. Note, it is expected that, due to the
physical separation between the two locations, and assuming that the sediment is
VOIGT CONSULTANTS LLC, 817 19" AVENUE NORTH, SOUTH ST. PAUL, MN 55075
952- 292- 8486, RICKVOIGT @VOIGTCONSULTANTS. COM
relatively similar in nature at both locations it will be possible to evaluatealternatives at each location during a single run, minimizing the number of overallmodel runs.
Provide results and recommendations regarding possible sedimentation controlmeasures near the dock to the Red Wing Port Authority and regarding ColvillMarina to the City of Red Wing.
Task 8 - Develop preliminary design drawings suitablefor cost estimation forthe recommended alternative(s).
Upon concurrence with the Port Authority and City regarding the long-termalternatives to reduce sediment deposition in undesirable areas, develop drawingsto a level suitable for a preliminary cost estimate.
COMPENSATION
The estimated cost to complete the tasks listed above is provided below. It is proposed
that the actual costs be billed on a time and expenses basis according to the attached ratesheet, direct project expenses will be charged to the project without markup.
The estimated cost to complete the Scope of Work outlined in Tasks 1, 2 and 3
above is $ 8, 000 to $ 10, 000, this cost includes 3 anticipated site visits.
The estimated cost to complete the Scope of Work outlined in Task 6 above is
1, 500 to $3, 000.
The estimated cost to complete the Scope of Work outlined in Tasks 4, and 5
above is $ 15, 000 to $20,000, depending on the findings of the structuralinspection, this cost includes three anticipated site visits.
The estimated cost to complete the Scope of Work outlined in Task 7 and 8 above
is $ 28, 000 to $ 38, 000, depending on the complexity of the river bathymetry andflow patterns within each area, the nature of the sediment in both locations and
the alternative(s) chosen.
STAFF
Voigt Consultants LLC specializes in 1, 2 and 3- dimensional numerical modeling andriver engineering. Rick Voigt will be the primary staff member working on this projectfor Voigt Consultants. Mr. Voigt will be assisted by Dr. V. Ramanathan (Rama). Rick
and Rama respectively have over 35 -yrs and 40 -yrs experience in physical and numericalhydraulic analyses of complex river systems and hydrologic studies.
Engineering Partners International (EPI) is a specialized consulting engineering firm, andpractices primarily in the areas of structural, foundation, geotechnical, and constructionengineering. Greg Greenlee, P. E. has 25 years of experience working for manufacturing,
VOIGT CONSULTANTS LLC, 817 19" AVENUE NORTH, SOUTH ST. PAUL, MN 55075
952- 292- 8486, RICKVOIGT @VOIGTCONSULTANTS. COM
regional and national design firms performing structural design, specialty foundationdesign, shoring design, and earth retention design.
SCHEDULE
It is anticipated that the tasks can be undertaken simultaneously and they are expected totake approximately three to four months to complete the last of the tasks. The VoigtConsultants team is ready to start the project immediately upon authorization.
Sincerely,
Richard L. Voigt, Jr., PE
Voigt Consultants, LLC
VOIGT CONSULTANTS LLC, 817 19" AVENUE NORTH, SOUTH ST. PAUL, MN 55075
952- 292- 8486, RICKVOIGT @VOIGTCONSULTANTS. COM
VOIGT CONSULTANTS, LLC
2020 BILLING RATES
Principal Engineer 150-$ 190/ hr
Senior Engineer 95-$ 150/ hr
Engineer 85- 120/ hr
Technician 50-$ 105/ hr
Intern 20-$ 45/ hr
SMS Computational Program 20/hr
Direct project expenses are billed at cost
VOIGT CONSULTANTS LLC, 817 19"' AVENUE NORTH, SOUTH ST. PAUL, MN 55075
952- 292- 8486, RICKVOIGT @VOIGTCONSULTANTS. COM