HPS Perencanaan Ja_lin 2013Edit

Post on 06-Dec-2015

490 views 31 download

description

contoh HPS

Transcript of HPS Perencanaan Ja_lin 2013Edit

LAMPIRAN BERITA ACARA KLARIFIKASI DAN NEGOSIASI

NOMOR

TANGGAL

PEKERJAAN

KEGIATAN

TAHUN ANGGARAN

No. Posisi/Keahlian

HARGA PENAWARAN

Jumlah Jumlah Biaya Personil Jumlah

Orang Bulan Org/BulanOrg/Bulan

( Rp. ) ( Rp. )

I. Biaya Langsung Personil

I.1 Biaya Tenaga Ahli

1 Tenaga Team Leader (S1 Teknik Sipil) 1.00 0.50 0.50 6,250,000.00 3,125,000.00

2 Tenaga Ahli Transportasi (S1 Teknik Sipil) 1.00 0.50 0.50 4,800,000.00 2,400,000.00

3 Tenaga Ahli Drainase (S1 Teknik Sipil) 1.00 0.50 0.50 4,800,000.00 2,400,000.00

4 Tenaga Ahli Cost Estimator (S1 Teknik Sipil) 1.00 0.50 0.50 4,800,000.00 2,400,000.00

5 Chief Surveyor (S1 geodesi) 1.00 0.50 0.50 4,800,000.00 2,400,000.00

Jumlah 12,725,000.00 I.2 Biaya Tenaga Pendukung

1 Surveyor (D3) 4.00 0.50 2.00 2,200,000.00 4,400,000.00

2 Drafter (D3) 2.00 0.50 1.00 2,200,000.00 2,200,000.00

3 Operator Komputer (D3) 2.00 0.50 1.00 1,950,000.00 1,950,000.00

4 Administrasi & Keuangan (D3) 1.00 0.50 0.50 700,000.00 350,000.00

Jumlah 8,900,000.00

NO U R A I A N SAT. VOL.Waktu HARGA JUMLAH

( bln ) SATUAN HARGA

II. Biaya Langsung Non Personil

II.1 Biaya Kendaraan (sewa)1 Mobil (Kendaraan Roda Empat) Unit 1.00 0.50 7,250,000.00 3,625,000.00

Jumlah 3,625,000.00

II.2 Biaya Peralatan (sewa)1 Komputer Unit 2.00 0.50 4,400,000.00 4,400,000.00

2 Alat Ukur Theodoliet Set 2.00 0.50 7,250,000.00 7,250,000.00

Jumlah 11,650,000.00

II. 3 Biaya Bahan

1 Alat Tulis dan Bahan Habis Pakai ls 1.00 900,000.00 900,000.00

Jumlah 900,000.00 II. 4 Biaya Pelaporan

1 Laporan Pendahuluan Buku 5.00 90,000.00 450,000.00

2 Laporan Akhir Buku 5.00 150,000.00 750,000.00

Jumlah 1,200,000.00

Jumlah 39,000,000.00

PPN 10 % 3,900,000.00

Jumlah 42,900,000.00

Dibulatkan 42,900,000.00

Terbilang : Tiga puluh empat juta empat ratus tiga puluh ribu rupiah

Menyetujui,

CV. KONSULTAN

......................................................................... .....................................................................Direktur

LAMPIRAN BERITA ACARA KLARIFIKASI DAN NEGOSIASI

NOMOR :

TANGGAL :

PEKERJAAN : Perencanaan Peningkatan Jalan Lingkungan

KEGIATAN : Perencanaan Pemeliharaan Sarana Dan Prasaran rumah Sederhana Sehat

TAHUN ANGGARAN : 2013

No. Posisi/Keahlian

HARGA PERKIRAAN SENDIRI (HPS)

Jumlah Jumlah Biaya Personil Jumlah

Orang Bulan Org/BulanOrg/Bulan

( Rp. ) ( Rp. )

I. Biaya Langsung Personil

I.1 Biaya Tenaga Ahli

1 Tenaga Team Leader (S1 Teknik Sipil) 1.00 0.50 0.50 6,500,000.00 3,250,000.00

2 Tenaga Ahli Transportasi (S1 Teknik Sipil) 1.00 0.50 0.50 5,000,000.00 2,500,000.00

3 Tenaga Ahli Drainase (S1 Teknik Sipil) 1.00 0.50 0.50 5,000,000.00 2,500,000.00

4 Tenaga Ahli Cost Estimator (S1 Teknik Sipil) 1.00 0.50 0.50 5,000,000.00 2,500,000.00

5 Chief Surveyor (S1 geodesi) 1.00 0.50 0.50 5,000,000.00 2,500,000.00

Jumlah 13,250,000.00 I.2 Biaya Tenaga Pendukung

1 Surveyor (D3) 4.00 0.50 2.00 2,250,000.00 4,500,000.00

2 Drafter (D3) 2.00 0.50 1.00 2,250,000.00 2,250,000.00

3 Operator Komputer (D3) 2.00 0.50 1.00 2,000,000.00 2,000,000.00

4 Administrasi & Keuangan (D3) 1.00 0.50 0.50 750,000.00 375,000.00

Jumlah 9,125,000.00

NO U R A I A N SAT. VOL.Waktu HARGA JUMLAH

( bln ) SATUAN HARGA

II. Biaya Langsung Non Personil

II.1 Biaya Kendaraan (sewa)1 Mobil (Kendaraan Roda Empat) Unit 1.00 0.50 7,500,000.00 3,750,000.00

Jumlah 3,750,000.00

II.2 Biaya Peralatan (sewa)1 Komputer Unit 2.00 0.50 4,500,000 4,500,000.00

2 Alat Ukur Theodoliet Set 2.00 0.50 7,500,000 7,500,000.00

Jumlah 12,000,000.00

II. 3 Biaya Bahan

1 Alat Tulis dan Bahan Habis Pakai ls 1.00 1,000,000.00 1,000,000.00

Jumlah 1,000,000.00 II. 4 Biaya Pelaporan

1 Laporan Pendahuluan Buku 5.00 100,000.00 500,000.00

2 Laporan Akhir Buku 5.00 200,000.00 1,000,000.00

Jumlah 1,500,000.00

Jumlah 40,625,000.00

PPN 10 % 4,062,500.00

Jumlah 44,687,500.00

Dibulatkan 44,687,000.00

Terbilang : Tiga puluh empat juta empat ratus tiga puluh ribu rupiah

Menyetujui,

CV. KONSULTAN

.........................................................................

Direktur

DAFTAR SATUAN TENAGA AHLI DAN TENAGA PENDUKUNG

No. Posisi/Keahlian 7 tahun 5 tahun1 hari 1 bulan 1 hari 1 bulan

1 Tenaga Team Leader (S1 Teknik Sipil) 216,666.67 6,500,000.00

2 Tenaga Ahli Transportasi (S1 Teknik Sipil) 166,666.67 5,000,000.00

3 Tenaga Ahli Drainase (S1 Teknik Sipil) 166,666.67 5,000,000.00

4 Tenaga Ahli Cost Estimator (S1 Teknik Sipil) 166,666.67 5,000,000.00

5 Chief Surveyor (S1 geodesi) 166,666.67 5,000,000.00

6 Surveyor (D3)

7 Drafter (D3)

8 Operator Komputer (D3)

9 Administrasi & Keuangan (D3)

DAFTAR SATUAN TENAGA AHLI DAN TENAGA PENDUKUNG

Satuan 3 tahun

Orang

Orang

Orang

Orang

Orang 75,000.00 2,250,000.00 Orang 75,000.00 2,250,000.00 Orang 66,666.67 2,000,000.00 Orang 25,000.00 750,000.00 Orang

SATUAN BIAYA NON PERSONIL

Nama Sewa Alat dan Bahan lumpsum harga/hari harga/bln

Kendaraan Roda 4 250,000.00 7,500,000.00 Komputer dan Printer 150,000.00 4,500,000.00 Theodoliet 250,000.00 7,500,000.00 Alat Tulis/pakai habis 1,000,000.00 1,000,000.00 Bahan Lap Pendahuluan 100,000.00 100,000.00 Bahan Lap Akhir 200,000.00 200,000.00

I. BIAYA LANGSUNG PERSONIL

1. Biaya Tenaga Ahli

No. Posisi/Keahlian

Jumlah Jumlah Biaya Personil

Orang Bulan Org/Bulan

Org/Bulan

( Rp. )

1 Tenaga Team Leader (S1 Teknik Sipil) 1.00 0.50 0.50 6,500,000.00

2 Tenaga Ahli Transportasi (S1 Teknik Sipil) 1.00 0.50 0.50 5,000,000.00

3 Tenaga Ahli Drainase (S1 Teknik Sipil) 1.00 0.50 0.50 5,000,000.00

4 Tenaga Ahli Cost Estimator (S1 Teknik Sipil) 1.00 0.50 0.50 5,000,000.00

5 Chief Surveyor (S1 geodesi) 1.00 0.50 0.50 5,000,000.00

JUMLAH

2. Biaya Tenaga Pendukung

No. Posisi/Keahlian

JumlahJumlah Biaya Personil

Orang Bulan Org/BulanOrg/Bulan

( Rp. )

1 Surveyor (D3) 4.00 0.50 2.00 2,250,000.00

2 Drafter (D3) 2.00 0.50 1.00 2,250,000.00

3 Operator Komputer (D3) 2.00 0.50 1.00 2,000,000.00

4 Administrasi & Keuangan (D3) 1.00 0.50 0.50 750,000.00

JUMLAH

Jumlah

( Rp. )

3,250,000.00

2,500,000.00

2,500,000.00

2,500,000.00

2,500,000.00

13,250,000.00

Jumlah

( Rp. )

4,500,000.00

2,250,000.00

2,000,000.00

375,000.00

9,125,000.00

II. BIAYA LANGSUNG NON PERSONIL

1. BIAYA KENDARAAN (SEWA)

NO U R A I A N SAT. VOL.Waktu HARGA

( bln ) SATUAN

1 Mobil (Kendaraan Roda Empat) Unit 1.00 0.50 7,500,000.00

Jumlah

2. BIAYA PERALATAN (Sewa)

NO U R A I A N SAT. VOL.Waktu HARGA

( bln ) SATUAN

1 Komputer Unit 2.00 0.50 4,500,000.00

2 Alat Ukur Theodoliet Set 2.00 0.33 7,500,000.00

Jumlah

3. BIAYA BAHAN

NO U R A I A N SAT. VOL.HARGA

SATUAN

1 Alat Tulis dan Bahan Habis Pakai Ls 1.00 1,000,000.00

Jumlah

4. BIAYA PELAPORAN

NO U R A I A N SAT. VOL.HARGA

SATUAN

1 Laporan Pendahuluan Buku 5.00 100,000.00

2 Laporan Akhir Buku 5.00 200,000.00

Jumlah

JUMLAH

HARGA

3,750,000.00

3,750,000.00

JUMLAH

HARGA

4,500,000.00

4,950,000.00

9,450,000.00

JUMLAH

HARGA

1,000,000.00

1,000,000.00

JUMLAH

HARGA

500,000.00

1,000,000.00

1,500,000.00

LAMPIRAN BERITA ACARA KLARIFIKASI DAN NEGOSIASI

NOMOR :

TANGGAL :

PEKERJAAN : Perencanaan Peningkatan Jalan Lingkungan

KEGIATAN : Perencanaan Pemeliharaan Sarana Dan Prasaran rumah Sederhana Sehat

TAHUN ANGGARAN : 2013

No. Posisi/Keahlian

HARGA PERKIRAAN SENDIRI (HPS) HARGA PENAWARAN KLARIFIKASI DAN NEGOSIASI

Jumlah Jumlah Biaya Personil JumlahJumlah Jumlah Biaya Personil Jumlah

Jumlah Jumlah Biaya Personil Jumlah

Orang Bulan Org/BulanOrg/Bulan

Orang Bulan Org/BulanOrg/Bulan

Orang Bulan Org/BulanOrg/Bulan

( Rp. ) ( Rp. ) ( Rp. ) ( Rp. ) ( Rp. ) ( Rp. )

I. Biaya Langsung Personil

I.1 Biaya Tenaga Ahli

1 Tenaga Team Leader (S1 Teknik Sipil) 1.00 0.50 0.50 6,500,000.00 3,250,000.00 1.00 0.50 0.50 6,250,000.00 3,125,000.00 1.00 0.50 0.50 6,250,000.00 3,125,000.00

2 Tenaga Ahli Transportasi (S1 Teknik Sipil) 1.00 0.50 0.50 5,000,000.00 2,500,000.00 1.00 0.50 0.50 4,800,000.00 2,400,000.00 1.00 0.50 0.50 4,800,000.00 2,400,000.00

3 Tenaga Ahli Drainase (S1 Teknik Sipil) 1.00 0.50 0.50 5,000,000.00 2,500,000.00 1.00 0.50 0.50 4,800,000.00 2,400,000.00 1.00 0.50 0.50 4,800,000.00 2,400,000.00

4 Tenaga Ahli Cost Estimator (S1 Teknik Sipil) 1.00 0.50 0.50 5,000,000.00 2,500,000.00 1.00 0.50 0.50 4,800,000.00 2,400,000.00 1.00 0.50 0.50 4,800,000.00 2,400,000.00

5 Chief Surveyor (S1 geodesi) 1.00 0.50 0.50 5,000,000.00 2,500,000.00 1.00 0.50 0.50 4,800,000.00 2,400,000.00 1.00 0.50 0.50 4,800,000.00 2,400,000.00

Jumlah 13,250,000.00 12,725,000.00 12,725,000.00 I.2 Biaya Tenaga Pendukung

1 Surveyor (D3) 4.00 0.50 2.00 2,250,000.00 4,500,000.00 4.00 0.50 2.00 2,200,000.00 4,400,000.00 4.00 0.50 2.00 2,200,000.00 4,400,000.00

2 Drafter (D3) 2.00 0.50 1.00 2,250,000.00 2,250,000.00 2.00 0.50 1.00 2,200,000.00 2,200,000.00 2.00 0.50 1.00 2,200,000.00 2,200,000.00

3 Operator Komputer (D3) 2.00 0.50 1.00 2,000,000.00 2,000,000.00 2.00 0.50 1.00 1,950,000.00 1,950,000.00 2.00 0.50 1.00 1,950,000.00 1,950,000.00

4 Administrasi & Keuangan (D3) 1.00 0.50 0.50 750,000.00 375,000.00 1.00 0.50 0.50 700,000.00 350,000.00 1.00 0.50 0.50 700,000.00 350,000.00

Jumlah 9,125,000.00 8,900,000.00 8,900,000.00

NO U R A I A N SAT. VOL.Waktu HARGA JUMLAH

SAT. VOL.Waktu HARGA JUMLAH

SAT. VOL.Waktu HARGA JUMLAH

( bln ) SATUAN HARGA ( bln ) SATUAN HARGA ( bln ) SATUAN HARGA

II. Biaya Langsung Non Personil

II.1 Biaya Kendaraan (sewa)1 Mobil (Kendaraan Roda Empat) Unit 1.00 0.50 7,500,000.00 3,750,000.00 Unit 1.00 0.50 7,250,000.00 3,625,000.00 Unit 1.00 0.50 7,250,000.00 3,625,000.00

Jumlah 3,750,000.00 3,625,000.00 3,625,000.00

II.2 Biaya Peralatan (sewa)1 Komputer Unit 2.00 0.50 4,500,000 4,500,000.00 Unit 2.00 0.50 4,400,000.00 4,400,000.00 Unit 2.00 0.50 4,400,000.00 4,400,000.00

2 Alat Ukur Theodoliet Set 2.00 0.50 7,500,000 7,500,000.00 Set 2.00 0.50 7,250,000.00 7,250,000.00 Set 2.00 0.50 7,250,000.00 7,250,000.00

Jumlah 12,000,000.00 11,650,000.00 11,650,000.00

II. 3 Biaya Bahan

1 Alat Tulis dan Bahan Habis Pakai ls 1.00 1,000,000.00 1,000,000.00 ls 1.00 900,000.00 900,000.00 ls 1.00 900,000.00 900,000.00

Jumlah 1,000,000.00 900,000.00 900,000.00 II. 4 Biaya Pelaporan

1 Laporan Pendahuluan Buku 5.00 100,000.00 500,000.00 Buku 5.00 90,000.00 450,000.00 Buku 5.00 90,000.00 450,000.00

2 Laporan Akhir Buku 5.00 200,000.00 1,000,000.00 Buku 5.00 150,000.00 750,000.00 Buku 5.00 150,000.00 750,000.00

Jumlah 1,500,000.00 1,200,000.00 1,200,000.00

Jumlah 40,625,000.00 39,000,000.00 39,000,000.00

PPN 10 % 4,062,500.00 3,900,000.00 3,900,000.00

Jumlah 44,687,500.00 42,900,000.00 42,900,000.00

Dibulatkan 44,687,000.00 42,900,000.00 42,900,000.00

Terbilang : Tiga puluh empat juta empat ratus tiga puluh ribu rupiah

PEJABAT PENGADAAN BARANG/ JASA

Menyetujui,

CV. KONSULTAN DINAS TATA RUANG DAN CIPTA KARYA KOTA BANDUNG

......................................................................... .....................................................................Direktur

HARGA PERKIRAAN SENDIRI (HPS)

KEGIATAN : Perencanaan Pemeliharaan Sarana Dan Prasaran rumah Sederhana SehatPEKERJAAN : Perencanaan Peningkatan Jalan LingkunganLOKASI : TersebarSKPD : Dinas Tata Ruang Dan cipta karya kota bandungTAHUN ANGGARAN : 2013

REKAPITULASI

No. Uraian

I. Biaya Langsung Personil

II. Biaya Langsung Non Personil

J u m l a hP P N 10 %Jumlah BiayaDibulatkan

Terbilang : Tiga Puluh Dua Juta Enam Ratus Sembilan Puluh Tujuh Ribu Rupiah

Bandung, Nopember 2013Disayahkan Disusun Oleh :

Kuasa Pengguna Anggaran Pejabat Pengadaan Barang/Jasa

....................................... ...........................................

HARGA PERKIRAAN SENDIRI (HPS)

: Perencanaan Pemeliharaan Sarana Dan Prasaran rumah Sederhana Sehat

REKAPITULASI

Jumlah Biaya (Rp.)

21,625,000.00

17,375,000.00

39,000,000.00 3,900,000.00 42,900,000.00 42,900,000.00

Terbilang : Tiga Puluh Dua Juta Enam Ratus Sembilan Puluh Tujuh Ribu Rupiah

Bandung, Nopember 2013

Pejabat Pengadaan Barang/Jasa

...........................................

JADWAL PENUGASAN/ KETERLIBATAN PERSONIL

NO. POSISI/ KEAHLIANBULAN KE I T O T A L

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 Bln-Org Hr-Org

1 Tenaga Team Leader (S1 Teknik Sipil) 0.50 15.00

2 Tenaga Ahli Transportasi (S1 Teknik Sipil) 0.50 15.00

3 Tenaga Ahli Drainase (S1 Teknik Sipil) 0.50 15.00

4 Tenaga Ahli Cost Estimator (S1 Teknik Sipil) 0.50 15.00

5 Chief Surveyor (S1 geodesi) 0.50 15.00

6 Surveyor (D3) 2.00 15.00

7 Drafter (D3) 1.00 15.00

8 Operator Komputer (D3) 1.00 15.00

9 Administrasi & Keuangan (D3) 0.50 15.00

JADWAL PELAKSANAAN PEKERJAAN

NO. URAIAN PEKERJAANPERSONIL BULAN KE I

LELANGPOSISI JUMLAH 1 2 3

1 Survey dan Pengukuran

Team Ld. / Sipil 1

GeodesiSurveyor 4

Adm & Keu 1

2 Penggambaran/ Penyajian Kondisi Eksisting

Team Ld. / Sipil 1

Geodesi 1

Drafter 2

Surveyor 1

3 Perencanaan dan Penggambaran

Team Ld. / Sipil 1

Cost Estimator 1

Geodesi 1

Drafter 2

Op. Komputer 1

4 Penyusunan Rencana Kerja & Syarat-Syarat

Team Ld. / Arsitek 1

Ahli Sipil 1

Op. Komputer 1

Adm & Keu 1

5 Perhitungan Rencana Anggaran Biaya

Team Ld. / Sipil 1

Cost Estimator 1

Geodesi 1

Op. Komputer 1

6 Penyusunan Dokumen Lelang

Team Ld. / Sipil 1

Ahli Sipil 1

Op. Komputer 1

Cost Estimator 1

Adm & Keu 1

7 Aanwijzing

Team Ld. / Sipil 1

Ahli Sipil 1

Cost Estimator 1

8 Evaluasi Penawaran Hasil LelangTeam Ld. 1

Cost Estimator 1

9 Pre Construction MeetingTeam Ld. / Sipil 1

Ahli Sipil 1

10 Pengawasan BerkalaTeam Ld. / Surveyor 1

Ahli Sipil 1

JADWAL PELAKSANAAN PEKERJAAN

LELANG WAKTU PELAKSANAAN FISIK

JADWAL PELAKSANAAN PEKERJAAN

NO. URAIAN PEKERJAANPERSONIL BULAN KE I BULAN KE II

LELANG WAKTU PELAKSANAAN FISIKPOSISI JUMLAH 1 2 3 4 1 2 3 4

1 Survey dan Pengukuran

Team Ld. / Arsitek 1

Surveyor 2

Adm & Keu 1

2 Penggambaran/ Penyajian Kondisi Eksisting

Team Ld. / Arsitek 1

Drafter 2

Op. Komputer 2

Adm & Keu 1

3 Perencanaan dan Penggambaran

Team Ld. / Arsitek 1

Ahli Sipil 1

Drafter 2

Op. Komputer 1

Adm & Keu 1

4 Penyusunan Rencana Kerja & Syarat-Syarat

Team Ld. / Arsitek 1

Ahli Sipil 1

Op. Komputer 1

Adm & Keu 1

5 Perhitungan Rencana Anggaran Biaya

Team Ld. / Arsitek 1

Cost Estimator 1

Op. Komputer 1

Adm & Keu 1

6 Penyusunan Dokumen Lelang

Team Ld. / Arsitek 1

Ahli Sipil 1

Op. Komputer 1

Cost Estimator 1

Adm & Keu 1

7 Aanwijzing

Team Ld. / Arsitek 1

Ahli Sipil 1

Cost Estimator 1

8 Evaluasi Penawaran Hasil LelangTeam Ld. / Arsitek 1

Cost Estimator 1

9 Pre Construction MeetingTeam Ld. / Arsitek 1

Ahli Sipil 1

10 Pengawasan BerkalaTeam Ld. / Arsitek 1

Ahli Sipil 1