METHOD STATEMENT
1. INTRODUCTION
This Method Statement describes the specific safe working methods which will be used
by ------------------ to carry out the construction new storage facilities.
2. SCOPE
This document covers the scope of work required for the execution of the tank
construction. The method statement is in the following sequence as the work will be
carried out.
Tank specific design and drawings
Construction of new tank foundation
Plate, structural steel and tank component procurement
Floor, shell and roof plate fabrication
Installation of new floor plate and double deck roof
Fire protection system
Instrumentation and electrical works
Demolition of tank foundation, floor and roof
Tank decommissioning
Tank isolation
Tank cleaning
Tank conditional inspection survey
Blasting and painting works
Hydro-testing
Calibration
Hook up to existing process line, commissioning and demobilisation
3. REFERENCES
API 650: Welded steel storage tanks for Oil Storage
API MPMS 3.1B: Manual of Petroleum Measurement Standards Chapter 3 – Tank
Gauging (Section 1B: Standard Practice for Level measurement of Liquid
Hydrocarbons in Stationery Tanks by Automatic Tank Gauging)
Method Statement 1 of 17
Recommended Practice 14FZ: Recommended practice for Design and Installation of
Electrical Systems for Fixed and Floating Offshore Petroleum Facilities for
Unclassified and Class1, Zone 0, Zone 1 and Zone 2 Locations
NFPA 30: Flammable and Combustible Liquid Code-2000 Edition
BS 8110: Structural use of Concrete in Building
4. LIST OF EQUIPMENT
30 ton mobile crane
Flat deck/low bed trailer
Semi automatic welding machine
DC welding machines (400A)
Air compressor
Sand blasting set
Spray painting set
Wheel loader
Tipper truck
Mini dumper truck
Fuel tanker
Power generating set (30kVA, 50kVA, 60kVA, 100kVA)
NDT Equipment
Man Lifting Equipment (25m Boom height)
Dewatering pumps
Pneumatic power winch
Pneumatic air winch
5. SITE PERSONNEL
Construction Manager 1
Site Engineer 2
HSE Officer 1
QA/QC Officer 1
QA Engineer 2
QC Inspector 2
Site Supervisor 1
Pipe/Plate Welders 6
Method Statement 2 of 17
Pipe/Plate Fitter 6
Structural Welders 4
Rigger 6
Grit Blasters 4
Operators 8
6. WORK SEQUENCE AND METHOD
6.1. Tank Specific Design And Drawings
The following elements design shall be considered for adequacy in accordance with the
relevant codes and standards as may be applicable and any findings communicated to the
COMPANY for review and approval before changes will be effected.
The tank foundation shall be verified in accordance with appendix B of API
650:2005 and BS 8110
The floor and annular plates shall be verified in accordance with the requirements of
clauses 4.4 and 4.5 of API 650:2005
The shell plates shall be verified in accordance with the requirements of clauses 4.6
of API 650:2005
Roof and other roof accessories shall be verified to meet the requirement of Clause
4.10 of API 650:2005
Nozzles shall be verified to meet the requirement of clauses 4.7.6 for shell and 4.8.5
for roof of API 650:2005
The piping system shall be verified to meet the requirement of ASME B31.3
6.2.Plates, Structural Steel And Diesel Storage Tank Components Procurement
Steel plate and sections procured shall be accompanied with their mill certificates
Samples shall be taken from the procured materials to confirm that the chemical and
mechanical materials conform with the requirement of clause 4 of API 650: 2005
6.3. Cutting, Forming and Fabrication
Plate material shall be straight and/or flattened by pressing or rolling audtties shall be
done before the material is processed in any way.
Marking
To enable the various fabricated components to be assembled together
correctly on site, each part shall be marked with unique numbering system as
showed on the “Approved for Construction” drawings.
Method Statement 3 of 17
The erection marks shall be clearly written in paints and shall be at least
50mm high
Plate Edge Preparation
The edge of the tank plates shall be sheared, machine cut or bevelled with a
machine operated gas-cutting torch. Shearing shall be limited to plates less
than or equal to 10mm thick used for butt-welded joints and to plates less than
16mm thick used for lap-welded joints.
All shell plates shall be profiled to tolerance of ±2mm in length and ±1mm in
width. In addition, to ensure that plates are truly rectangular, the diagonals,
measured across the rectangle formed by scrubbing lines 50mm from each
edge, shall not differ by more than 3mm for lapped welded roof and bottom
plates, normally mill tolerances are acceptable.
Curved edges of roof, bottom sketch plates and annular plates shall be cut to
shape by the machine operated gas torch. Various radius templates will be
used for marking and cutting. The resulting surface shall be uniform, smooth
and free from scale or slag accumulations. The bevelled edges shall be ground
to remove all the above accumulations.
Underside of tank bottom plates shall be blasted and coated as per procedure
on blasting and painting
Rolling of Shell Plate
Shell plates shall be shaped to the correct curvature of the tank. Rolling will be
developed in place, in a fabrication shop designed and built for this purpose.
Plate bending machine having rolling capacity 16mm thick and 2500mm wide
size shall be used. Pre-bend 200mm of both ends, of shell plate edges to the
required radius.
Plate shall be rolled within permissible localized variations as specified in
ASTM A6 & A20 and shall be free from buckling, dents, excessive drawing,
distortion or obvious imperfections. Templates shall be used to measure the
rolled plate’s curvature. Rolling of shell plate giving required load stage by
stage on rolling direction. Check radius using the above template stage by
stage until the required radius is obtained. Rolled shell plates shall be stacked
Method Statement 4 of 17
on radius saddles, which is same to that of the rolled plates for further
process.
Plates dimension shall be verified prior to the start of edge preparation or
rolling operations.
Clean-out Door
Clean out door plate cutting and marking shall be as per “Approved for
Construction” drawings
Machining of clean out door flange and cover shall be as per drawings
Stress relief shall be carried out according to API 650 and Approved post
weld heat treatment (PWHT)
Nozzles, Manhole and other Appurtenances
All nozzles, manholes and other appurtenances shall be fabricated & PWHT
in the shop, in accordance with the approved construction drawings.
A protective shelter shall be used.
Pipe shall be pre-heated around its circumference and maintained on 12''
sections on either side of the weld.
Each weld shall be started (root pass) and finished while the preheat
temperature is maintained without interruption.
Pipe shall be covered immediately after welding and be permitted to cool at
uniform rate.
6.4. Tank Erection
Foundation tolerances
Before installation of the bottom plate, the tank foundation shall be inspected
visually for evidence of cracks, damage etc
A check of the dimension, level, reference point and foundation profile
accuracy shall be carried out prior to commencement of tank bottom plate
installation
Spot level of the foundations shall be verified and tolerances shall be as per
the limits specified in clause 4.3.1 and Appendix B API 650: 2005
Method Statement 5 of 17
Exact centre point and orientation (0˚, 90˚, 180˚, 270˚) shall be marked
Laying of Annular plates
The underside of the plates shall be painted with black bituminous paint
before laying
A backing plate shall be fixed to each annular plate
Each annular plate shall be placed in accordance with the “Approved for
Construction” drawings in correct orientation
The radius of each annular plate outer edge shall be measured to ensure that
the outer edges are the correct distance from the centre of foundation
Fit-up between annular plates shall be adjusted as required
Upon completion of installation and prior to welding of annular plates, a final
check of the joint fit-up welding gaps and radius shall be made
The weld area upon which the shell plates are to be erected shall be ground
flush
All welds shall be inspected by vacuum box technique and penetration
method
Laying of Bottom Plates
The bottom plates, starting from the centre plate shall be laid progressively
towards the annular plates in accordance with the project drawings
Water draw-off sump shall be installed and welded according to “Approved
for Construction” drawing
Floor welding shall start from the centre of floor with the short transverse lap
joints working outwards each side of the centre to the periphery of the floor.
This sequence shall be repeated for the strakes of plate each side of the centre
strake
This shall be repeated for the strake adjacent to the last welded until the
transverse weld are completed
The longitudinal joints shall now be welded starting at the centre of the floor
and working outwards to the periphery from each side of the floor centre line
which is transverse to the setting out line
Where three plate thicknesses occur in the floor lap joints, the upper plate
shall be joggled, or cut and joggled.
Method Statement 6 of 17
Tank Shell Assembling
Preparation before Assembling
The shell plates shall be placed around the tank foundation.
All required fixtures shall be installed on the inside of the shell plates.
All required fixtures shall be installed on the inside and outside of the annular
plates to ensure that the shell plates are aligned with the scribed line.
Bracket hooks shall be fitted inside and outside each shell plate before it is
lifted into position.
Assembling
Each shell plate shall be secured on the annular plate and aligned by using
guides and wedges.
The first shell plate with its edge on the start mark shall be erected upright
using a 100 mm channel support.
Strong back plates shall be employed to secure adjacent shell plates. An
alignment and width check of joint gaps shall be carried out before tack
welding the vertical seams.
The alignment fixtures shall be removed, all tacks cleaned and all vertical
joints of the first shell course welded.
The shell course dimensions shall be checked for roundness at the bottom and
top levels, vertically at a minimum of two points and for level at the shell plate
top-level line.
When checking is completed the second course of plates shall be placed into
position together with the first shell course.
For the erection of the second and subsequent courses, scaffold brackets and
plates shall be attached to the shell plates and secured with rope. The shell
plates shall then be lifted into position.
Method Statement 7 of 17
On completion of assembling the shell plates handrail shall be installed on the
inside of the scaffold
Wall ladders shall be attached on the inside wall of the tank.
The second course vertical joints shall be aligned and welded.
Aligning horizontal seam between 1st & 2nd courses, and fit up check shall be
carried out after tack welding.
The alignment fixtures shall be removed, all tacks cleaned and horizontal
joints shall be welded.
After completing welding of horizontal joint, 3rd shell course shall be erected.
The same sequence shall be followed to complete the assembly of the
remaining shell courses.
Vertical seams shall be located, as to clear all shell appurtenances and their
reinforcing pads.
** Guying system shall be used during shell courses erection from 4th. Course
and shall be moved up progressively.
Tank Shell Plumbness
To inspect the roundness of the first shell course, the distance from the auxiliary
line scribed on the tank bottom inside the tank shell, to each bottom shell plate,
shall be measured. If the distance is not within tolerance it shall be corrected by
means of the wedge guides and wedges.
The verticality of the first shell course shall be inspected by using an internal
plumb line suspended from the course top and the distance between the plumb line
and the inside of the tank shell at the bottom, measured at a minimum of two
positions for each plate.
If the tank shell is found to be titled in excess of the tolerance limit, the temporary
100mm channel supports shall be removed from the first shell course and the tank
shell verticality corrected by means of a hand lever block.
Method Statement 8 of 17
To inspect the level of the first shell course top line, a graduated level shall be
installed inside the tank at the centre of the tank bottom, with its top aligned with
the top of the shell course. The graduations shall be read at two or more positions
per shell plate
The level shall be corrected by driving wedges between the foundation and the
tank bottom where the tank shell is low. The space between the lifted tank bottom
and the foundation shall be filled with non-shrink grout
Shell Manholes
The manhole contour shall be marked on the shell plate in accordance with the
“Approved for construction drawing”. The COMPANY’s authorized inspector
shall inspect the scribed manhole lines before the manhole is cut out.
Tank Floating Roof
A grid formation of vertically adjustable scaffolds support (Acrows) shall be set to
suit the final level of the underside of the roof pontoons and deck.
The supports shall be held securely in place with scaffold poles and clips.
The roof shall be completely erected and welded on these supports and all the roof
support legs, nozzles, manholes and all other roof appurtenances shall be fitted to
the roof.
Once the legs are in place and pinned in position, the supports and scaffolding shall
be removed from the tank through the shell manholes.
The outer rim of the pontoons shall be supported off temporary brackets welded to
the tank shell.
Staircase
Staircase shall be prefabricated, erected and welded according to “approved for
construction drawing”
Top Hand-railing & Platform
Method Statement 9 of 17
Top hand-railing & platform shall be prefabricated, erected and welded according to
approved drawing
Welding
All welding of tank plates, steel framing, structural attachments and mountings in both
the fabrication shop and in the field shall conform to welding procedures and
qualifications per section IX of ASME BPVC.
Sequence of Welding
The sequence employed for tack welding and final welding of the bottom, shell and roof
plates shall be arranged to minimize distortion due to weld shrinkage.
Annular plate
All joints shall fit-up except one and welding shall start either odd or even joints first.
After that, welding shall start from any one joint to both directions i.e. clockwise and
anti-clockwise. Before welding of the final joint make sure the annular plate outer
diameter as required. Particular attention shall be given to the welding of butt-welded
seams for the annular plates where these pass under the shell plates, to ensure that full
penetration is obtained.
Necessary NDT shall be applied according to approved contract drawing & API
650
Bottom plate
Short seam joints fit-up and welding will starts first from bottom centre to side. After
welding of short seam joints the long seam fit-up and welding will starts from centre
to towards side. Complete the welding of both long joints adjacent to the centre point,
after that alternate joint. Finally complete all remaining long seam joints in the same
manner. Keep open at least 8'' from open ends of long seam with annular plates.
Annular plate to bottom sketch plates fit-up and welding shall start after completion
of shell to annular welding.
Three lap joints shall be rounded and bent using horse shoe and wedge with
hammering, direct hammering not allowed, and these joints shall be tested by DPI.
Method Statement 10 of 17