Vermont Yankee - Defueled Safety Analysis Report, Revision 1
-
Upload
khangminh22 -
Category
Documents
-
view
3 -
download
0
Transcript of Vermont Yankee - Defueled Safety Analysis Report, Revision 1
DEFUELED SAFETY ANALYSIS REPORT
TABLE OF CONTENTS
VYNPS DSAR Revision 1 TOC-1 of 2
SECTION 1 UFSAR, REV 17, TOC
1.0 INTRODUCTION AND SUMMARY 1.1 INTRODUCTION 1.2 DESIGN CRITERIA 1.3 FACILITY DESCRIPTION 1.4 SUMMARY OF RADIATION EFFECTS 1.5 GENERAL CONCLUSIONS SECTION 2 2.0 STATION SITE AND ENVIRONS 2.1 SUMMARY DESCRIPTION 2.2 SITE DESCRIPTION 2.3 METEOROLOGY 2.4 HYDROLOGY AND BIOLOGY 2.5 GEOLOGY AND SEISMOLOGY 2.6 RADIOLOGICAL ENVIRONMENTAL MONITORING PROGRAM SECTION 3 3.0 FACILITY DESIGN AND OPERATION 3.1 DESIGN CRITERIA 3.2 FACILITY STRUCTURES 3.3 SYSTEMS SECTION 4 4.0 RADIOACTIVE WASTE MANAGEMENT 4.1 SOURCE TERMS 4.2 RADIATION SHIELDING 4.3 HEALTH PHYSICS INSTRUMENTATION 4.4 RADIATION PROTECTION PROGRAM 4.5 LIQUID WASTE MANAGEMENT SYSTEMS 4.6 SOLID WASTE MANAGEMENT 4.7 EFFLUENT RADIOLOGICAL MONITORING AND SAMPLING
DEFUELED SAFETY ANALYSIS REPORT TABLE OF CONTENTS (Continued)
VYNPS DSAR Revision 1 TOC-2 of 2
SECTION 5 5.0 CONDUCT OF OPERATIONS 5.1 ORGANIZATION AND RESPONSIBILITY 5.2 TRAINING 5.3 EMERGENCY PLAN 5.4 QUALITY ASSURANCE PROGRAM 5.5 REVIEW AND AUDIT OF OPERATIONS 5.6 TECHNICAL REQUIREMENTS MANUAL SECTION 6 6.0 SAFETY ANALYSIS 6.1 INTRODUCTION 6.2 ACCEPTANCE CRITERIA 6.3 ACCIDENTS EVALUATED 6.4 SITE EVENTS EVALUATED 6.5 REFERENCES 6.6 APPENDICES SECTION 7 7.0 AGING MANAGEMENT 7.1 SUPPLEMENT FOR RENEWED OPERATING LICENSE 7.2 AGING MANAGEMENT PROGRAMS AND ACTIVITIES 7.3 REFERENCES 7.4 LIST OF LICENSE RENEWAL COMMITMENTS APPENDICES G.2 CURRENT ON-SITE METEOROLOGICAL PROGRAM
VYNPS DSAR Revision 1 1.0-1 of 17
INTRODUCTION AND SUMMARY TABLE OF CONTENTS
Section Title Page
1.1 INTRODUCTION .......................................................... 3
1.2 DESIGN CRITERIA ....................................................... 5
1.3 FACILITY DESCRIPTION .................................................. 7
1.3.1 General ...................................................... 7
1.3.1.1 Site and Environs ............................... 7
1.3.1.2 Facility Arrangement ............................ 9
1.3.2 Fuel Storage and Handling .................................... 9
1.3.2.1 Nuclear Fuel .................................... 9
1.3.2.2 Deleted ......................................... 9
1.3.2.3 Standby Fuel Pool Cooling and Demineralizer System ............................ 9
1.3.3 Radioactive Waste Management ................................. 9
1.3.3.1 Equipment and Floor Drainage Systems ........... 10
1.3.3.2 Liquid Radwaste System ......................... 10
1.3.3.3 Solid Radwaste System .......................... 10
1.3.4 Radiation Monitoring and Control ............................ 11
1.3.4.1 Reactor Building Ventilation Radiation Monitoring System .............................. 11
1.3.4.2 Process Radiation Monitoring ................... 11
1.3.4.3 Area Radiation Monitors ........................ 11
1.3.5 Auxiliary Systems ........................................... 12
1.3.5.1 Electrical Power Systems ....................... 12
1.3.5.2 Service Water System ........................... 12
1.3.5.3 Fire Protection System ......................... 13
1.3.5.4 Heating, Ventilating, and Air Conditioning Systems ........................... 13
1.3.5.5 Service and Instrument Air Systems ............. 13
1.3.5.6 Process Sampling System ........................ 14
VYNPS DSAR Revision 1 1.0-2 of 17
1.3.6 Communications Systems ...................................... 14
1.3.6.1 Facility Communications System ................. 14
1.3.7 Station Water Purification, Treatment and Storage ........... 14
1.3.7.1 Deleted ........................................ 14
1.3.7.2 Potable and Sanitary Water System .............. 15
1.3.8 Shielding, Access Control, and Radiation Protection Procedures .................................................. 15
1.3.8.1 General ........................................ 15
1.3.9 Structural Loading Criteria ................................. 16
1.4 SUMMARY OF RADIATION EFFECTS ......................................... 17
1.4.1 Fuel Storage and Handling and Waste Management .............. 17
1.4.2 Accidents and Events ........................................ 17
1.5 GENERAL CONCLUSIONS .................................................. 17
VYNPS DSAR Revision 1 1.0-3 of 17
1.1 INTRODUCTION
On January 12, 2015, Entergy Nuclear Operations (ENO) certified to the Nuclear
Regulatory Commission (NRC) that a determination to permanently cease operation
at the Vermont Yankee Nuclear Power Station (VYNPS) was made on December 29, 2014
which was the date on which operation ceased at VYNPS. ENO also certified that
the fuel has been permanently removed from the VYNPS reactor vessel and placed in
the spent fuel pool. ENO acknowledged that, following docketing, the VYNPS
license no longer authorized operation of the reactor or emplacement or retention
of fuel into the reactor vessel.
This Defueled Safety Analysis Report (DSAR) is derived from Revision 26 of the
VYNPS Updated Final Safety Analysis Report (UFSAR). The DSAR has been developed
as a licensing basis document that reflects the permanently defueled condition of
VYNPS. The DSAR serves the same function during SAFSTOR and decommissioning that
the UFSAR served during operation of the facility. An evaluation of the systems,
structures and components (SSCs) described in the UFSAR was performed to
determine the function, if any, these SSCs would perform in a defueled condition.
The criteria used to evaluate the major SSCs and the conclusions of the
evaluations are provided in appropriate station documents.
ENO acknowledged that the 10CFR50 operating license continues to remain in effect
until the Nuclear Regulatory Commission terminates the license.
The Vermont Yankee Nuclear Power Corporation was originally organized by ten New
England utilities in August, 1966, for the purpose of building and operating a
nuclear generating station in Vermont. At the time of application, Vermont
Yankee was similar in organization to the Yankee Atomic Electric Co. and the
Connecticut Yankee Atomic Power Co. Nine of the twelve Vermont Yankee sponsors
were also sponsors of Yankee and Connecticut Yankee. Thus, Vermont Yankee had
the benefit of the experience gained from the operation of these two plants.
The Vermont Yankee Nuclear Power Corporation was the sole applicant for an
operating license for a nuclear power station, located at the Vernon site in
Windham County, Vermont, for initial power levels up to 1593 MWt under Section
104(b) of the Atomic Energy Act of 1954, as amended, and the regulations of the
NRC set forth in Part 50 of Title 10 of the Code and Federal Regulations
(10CFR50).
The facility was designated as the Vermont Yankee Nuclear Power Station.
The Vermont Yankee Nuclear Power Corporation, as owner, was responsible for the
design, construction, operation and decommissioning of the station.
VYNPS DSAR Revision 1 1.0-4 of 17
EBASCO Services, Inc. designed and constructed the station exclusive of the
nuclear steam supply system.
General Electric Company was awarded a contract to design, fabricate, and deliver
the nuclear steam supply system and nuclear fuel for the station, as well as to
provide technical direction for installation and startup of this equipment.
General Electric Company was also contracted to design, fabricate, deliver, and
install the turbine generator as well as to provide technical assistance for the
startup of this equipment.
In July 2002, the operating license was transferred to Entergy Nuclear Vermont
Yankee, LLC, a limited liability company and wholly owned subsidiary of Entergy
Nuclear Operations, Inc.
VYNPS DSAR Revision 1 1.0-5 of 17
1.2 DESIGN CRITERIA
The principal architectural and engineering criteria for the design and
construction of the station, applicable in the permanently defueled state, are
summarized below.
General
The station design shall be in accordance with applicable codes and
regulations.
The station shall be designed in such a way that the release of radioactive
materials to the environment is limited so that the limits and guideline values
of Title 10 of the Code of Federal Regulations pertaining to the release of
radioactive materials are not exceeded.
Structural
Adequate strength and stiffness with appropriate safety factors shall be
provided so that a hazardous release of radioactive material shall not occur.
Nuclear Fuel
The fuel cladding shall be designed to retain integrity as a radioactive
material barrier.
The fuel cladding shall be designed to accommodate without loss of integrity
the pressures generated by the fission gases released from the fuel material
throughout the design life of the fuel.
The fuel cladding, in conjunction with other facility systems, shall be
designed to retain integrity throughout any abnormal operational transient.
Fuel Handling and Storage
Fuel handling and storage facilities shall be designed to maintain adequate
shielding and cooling for spent fuel.
Fuel handling and storage facilities shall be designed to preclude inadvertent
criticality.
VYNPS DSAR Revision 1 1.0-6 of 17
Electrical Power Systems
The electric power system shall be designed to provide sufficient normal and
standby electrical power to assure proper operation of the spent fuel pool
cooling and support systems.
Transformers, switchgear, buses, and cables shall be designed to have adequate
current carrying capacity without exceeding the acceptable voltage drop of the
electrical loads.
Switchgear protective devices shall be provided to detect and interrupt
electrical malfunctions.
The rated capacity of interrupting devices shall exceed the maximum available
fault current.
Radioactive Waste Disposal Systems
Liquid and solid waste disposal facilities shall be designed so that the
discharge and off-site shipment of radioactive effluents can be made in
accordance with applicable regulations.
The design shall provide means to inform station operating personnel of an
approach to limits on the release of radioactive material.
Shielding and Access Control Radiation shielding shall be provided and access control patterns shall be
established to allow the staff to control radiation doses within the limits of
10CFR20.
VYNPS DSAR Revision 1 1.0-7 of 17
1.3 FACILITY DESCRIPTION
1.3.1 General
1.3.1.1 Site and Environs
1.3.1.1.1 Location and Size of Site
The site is located on the west shore of the Connecticut River immediately
upstream of the Vernon Hydroelectric Station, in the town of Vernon, Vermont,
which is in Windham County. Site coordinates are approximately 4247' north,
7231' west. The facility is located on about 125 acres which are bounded by
privately owned land on the north, south, and west and by the Connecticut River
on the east. The site plot plan is shown on Drawing 5920-6245.
1.3.1.1.2 Site Ownership
Entergy Nuclear Vermont Yankee, LLC is the owner of the site, with the
exception of a narrow strip of land between the Connecticut River and the VYNPS
property for which it has perpetual rights and easements from its owner.
1.3.1.1.3 Activities at Site
All activities at the facility site will be under the control of Entergy
Nuclear Vermont Yankee, LLC and Entergy Nuclear Operations, Inc. at all times.
1.3.1.1.4 Access to the Site
The immediate area around the facility is completely enclosed by a fence with
access to the facility controlled at a security gate. Access to the site is
possible from either Governor Hunt Road, a local road, or from a spur of the
Central Vermont Railroad. Site boundaries are posted.
1.3.1.1.5 Description of Environs
The area adjacent to the facility is primarily farm and pasture land. Downstream
of the facility are the Vernon Hydroelectric Station and the town of Vernon,
Vermont. The area within a 5-mile radius is predominantly rural with the
exception of a portion of the city of Brattleboro, Vermont and the town of
Hinsdale, New Hampshire. Between 75% and 80% of the area within 5 miles of the
facility is wooded. The remainder is occupied by farms and small industries.
VYNPS DSAR Revision 1 1.0-8 of 17
1.3.1.1.6 Geology
The major structures at the site are supported by bedrock. Compression tests
indicated minimum failure of the bedrock to be 16,000 psi (1,152 tons per
square foot). An allowable bearing pressure has been established at 50 tons
per square foot; however, actual loadings do not exceed 20 tons per square
foot.
1.3.1.1.7 Seismology
Based on a three-fold seismic evaluation, the site was found to be relatively
quiescent from a seismic standpoint. From these studies the design earthquake
has been established at 0.07g horizontal ground acceleration and the maximum
hypothetical earthquake at 0.14g horizontal ground acceleration. The seismic
evaluation consisted of a review of historical data from the New England area,
an analysis of instrument and historical records for the Vermont area, and a
study of earthquake intensity attenuation with distance for the northeast
United States.
1.3.1.1.8 Hydrology
The facility is on the Connecticut River in Vernon, Vermont, some 138.3 miles
from the river mouth. The river in the vicinity of the facility is comprised
of a series of ponds formed by dams constructed for the generation of
hydroelectric power. All local surface streams drain to the Connecticut River,
and the site is in the direct path of natural drainage to the east of the local
watershed. In the vicinity of the site there is also a considerable amount of
groundwater which several municipalities utilize as one source of water supply.
1.3.1.1.9 Regional and Site Meteorology
The general climatic regime is that of a continental type with some
modification from the maritime climate which prevails nearer the coast. For
the one-year period between August 1967 and July 1968, temperature inversions
occurred 39% of the total time. Seasonal inversion frequencies ranged between
36% and 42%. Wind distribution is biased in the direction of the river due to
the channeling effect of the valley.
Historical records show that annual snowfall varies between 30 inches and
118 inches. Temperature range is about 133F. Occasional heavy rains and ice
storms occur in the area.
VYNPS DSAR Revision 1 1.0-9 of 17
1.3.1.2 Facility Arrangement
The facility arrangement is shown on Drawing 5920-6245. The principal
structures of the station are the reactor building and primary containment,
turbine building, control building, radwaste building, intake structure,
cooling towers, main stack, and an Independent Spent Fuel Storage Installation
(ISFSI) storage pad.
1.3.2 Fuel Storage and Handling
1.3.2.1 Nuclear Fuel
Nuclear fuel previously used for power generation consists of slightly enriched
uranium dioxide pellets contained in sealed Zircaloy tubes. These fuel rods
are assembled into individual fuel assemblies. On January 12, 2015, VYNPS
certified to the NRC that all nuclear fuel had been permanently removed from
the reactor vessel and placed in the spent fuel pool. Therefore, all nuclear
fuel is stored either in the Spent Fuel Pool (SFP) or at the Independent Spent
Fuel Storage Installation (ISFSI) Facility.
1.3.2.2 Deleted
1.3.2.3 Standby Fuel Pool Cooling and Demineralizer System
The Standby Fuel Pool Cooling (SFPCS) removes decay heat released from the
spent fuel to maintain fuel pool temperature within specified limits. The Fuel
Pool Demineralizer System (FPDS) maintains water clarity.
1.3.3 Radioactive Waste Management
The Radioactive Waste Systems are designed to control the release of
radioactive material to within the limits specified in 10CFR20 and within the
limits specified in technical specifications and the Off-Site Dose Calculation
Manual (ODCM). The methods employed for the controlled release of these
contaminants depends primarily upon the state of the material.
VYNPS DSAR Revision 1 1.0-10 of 17
1.3.3.1 Equipment and Floor Drainage Systems
Drains and sumps are provided to ensure proper drainage and collection of all
reject liquids throughout the facility. The drain systems are:
1. The chemical waste sump and equipment and floor sumps in the Radwaste
Building and Reactor Building that contain or potentially contain
radioactive liquids are routed to the Torus.
2. Uncontaminated liquids are drained to storm sewers or other areas where
they can be discharged to the river.
1.3.3.2 Liquid Radwaste System
The Liquid Radwaste System is no longer in service. The system has been drained to the extent practical. The Torus-as-CST System processes water collected from the chemical waste sump and equipment and floor drains in the Radwaste Building and Reactor Building. This water is stored in the Torus and is normally used to control spent fuel pool inventory. Water stored in the torus may be disposed of offsite or discharged to the environs in accordance with applicable permits and regulatory approvals.
1.3.3.3 Solid Radwaste System
Solid radioactive wastes are collected, processed, and packaged for storage and subsequent off-site burial. Generally, these wastes are stored on-site until the short half-lived activities are insignificant. Solid wastes from equipment originating in the Nuclear System are stored for radioactive decay in the fuel storage pool and prepared for reprocessing or off-site burial in approved shipping containers. Examples of these wastes are spent fuel, spent control rods, in-core ion chambers, etc. Process solid wastes, such as resins or filter material, are collected, dewatered, and prepared for storage in shielded casks. Dry active waste such as paper, air filters, and used clothing is collected and temporarily stored in large shipping containers before being sent to a disposal site or to an off-site waste processor for volume reduction prior to disposal. The processed waste may be returned to VYNPS in strong tight packages, or sent directly to burial.
VYNPS DSAR Revision 1 1.0-11 of 17
1.3.4 Radiation Monitoring and Control
1.3.4.1 Reactor Building Ventilation Radiation Monitoring System
The Reactor Building Ventilation Radiation Monitoring System consists of
radiation monitors arranged to monitor the activity level of the ventilation
exhaust from the Reactor Building.
1.3.4.2 Process Radiation Monitoring
Radiation monitors and monitoring systems are provided on process liquid and
gas lines that may serve as discharge routes for radioactive materials. The
monitors include the following:
Plant Stack Radiation Monitoring System
Process Liquid Radiation Monitoring System
Reactor Building Ventilation Radiation Monitoring System
1.3.4.3 Area Radiation Monitors
Radiation monitors are provided to monitor for abnormal radiation at various
locations. These monitors annunciate alarms when abnormal radiation levels are
detected.
VYNPS DSAR Revision 1 1.0-12 of 17
1.3.5 Auxiliary Systems
1.3.5.1 Electrical Power Systems
At the 345 kV switchyard, a ring bus arrangement supplies the 115 kV switchyard
through a 345 kV/115 kV autotransformer. A line from the 115 kV switchyard also
interconnects with 115 kV transmission systems in New Hampshire. Off-site
power is supplied to the facility from the 115 kV switchyard via two startup
transformers.
The Auxiliary AC Power System provides adequate power for the safe storage and
handling of irradiated fuel and support activities.
Backup power is available from the Vernon Hydroelectric Station and the Station
Blackout Diesel.
The Main Battery System provides a reliable source of dc power for control
power to selected breakers and power to selected lighting systems.
1.3.5.2 Service Water System
The Service Water System supplies cooling water from the Connecticut River
directly to auxiliary equipment. Pumps supply the systems and equipment through
a dual header arrangement.
VYNPS DSAR Revision 1 1.0-13 of 17
1.3.5.3 Fire Protection System
Water for the Fire Protection System is supplied by two vertical turbine-type
pumps, one diesel driven and one electric-motor driven, both located in the
intake structure. These pumps supply water to the facility fire loop with its
various hydrants and subsequently to the standpipe connections, sprinklers, and
deluge systems throughout portions of the facility. Supplementing these water
systems are a CO2 Fire Protection System for the cable vault and Switchgear
Rooms and portable fire extinguishers located throughout the facility.
The Heating Boiler Room is protected by automatic fire detection devices which
alarm in the Main Control Room.
Consideration has been given to the use of noncombustible and fire-resistant
materials throughout the facility.
1.3.5.4 Heating, Ventilating, and Air Conditioning Systems
The Heating, Ventilating, and Air Conditioning (HVAC) Systems normally provide
filtered air to the facility structures.
This air provides the appropriate temperature and humidity conditions as
required in these structures for personnel and equipment protection. It
provides for the effective protection of personnel against possible airborne
radioactive contaminants by maintaining flow direction and rate so that the
gaseous or particulate contaminants are effectively prevented from entering the
cleaner zones.
1.3.5.5 Service and Instrument Air Systems
The Instrument Air System provides the facility with a continuous supply of
dry, oil-free air for pneumatic instruments and controls through a dual header
system.
The Service Air System provides the facility with a continuous supply of air
where the air quality of the Instrument Air System is not required. Four 100%
capacity air compressors and two air receiver tanks comprise the pieces of
equipment for the two systems. Additionally, the Instrument Air System has a
filter and drier in each header to ensure air quality.
VYNPS DSAR Revision 1 1.0-14 of 17
1.3.5.6 Process Sampling System
The Process Sampling System provides a means for sampling and testing various
process fluids in centralized locations, from which the performance of the
facility, items of equipment, and systems may be determined.
1.3.6 Communications Systems
1.3.6.1 Facility Communications System
The Communications System provides adequate means of communication throughout
the facility and from the facility to off-site locations. The on-site means of
communication are:
1. Intrasite dial telephone system
2. Intrastation public address system
3. Sound-powered telephone system
4. Intrastation radio communications system
Communications to off-site locations can be accomplished by means of:
1. Public telephones
2. Off-site radio communications system
3. Intersite microwave communications system
1.3.7 Station Water Purification, Treatment and Storage
1.3.7.1 Deleted
VYNPS DSAR Revision 1 1.0-15 of 17
1.3.7.2 Potable and Sanitary Water System
Potable and sanitary water, filtered and treated as necessary, is provided in
sufficient quantity by this system to supply all facility drinking and sanitary
water requirements.
1.3.8 Shielding, Access Control, and Radiation Protection Procedures
1.3.8.1 General
Control of radiation exposure of facility personnel and people external to the
facility exclusion area is accomplished by a combination of radiation
shielding, control of access into certain areas, and administrative procedures.
The requirements of 10CFR20 are used as a basis for establishing the basic
criteria and objectives.
Shielding is used to reduce radiation dose rates in various parts of the
facility to acceptable limits. Access control and administrative procedure are
used to limit the integrated dose received by facility personnel to less than
that set forth in 10CFR20. Access control and procedures are also used to
limit the potential spread of contamination from various areas, particularly
areas where maintenance occurs.
Shielding is also used as necessary to protect equipment from radiation damage.
Of principal concern are organic materials such as insulation, linings, and
gaskets. The design levels are adjusted to accommodate the radiation damage
resistance of specific materials.
VYNPS DSAR Revision 1 1.0-16 of 17
1.3.9 Structural Loading Criteria
Structures and equipment are designed to substantially resist mechanical damage
due to loads produced by mechanical and thermal forces. For the purpose of
categorizing mechanical strength designs for these loads, the following
definitions were established:
1. Class I
Class I includes those structures, equipment, and components whose failure
or malfunction might cause or increase the severity of an accident which
would endanger the public health and safety.
2. Class II
Class II includes those structures, and components which are important to
the safe storage and handling of irradiated fuel and radioactive waste, but
are not essential for preventing or mitigating the consequences of an
accident which would endanger the public health and safety.
The loading categories are generically described and their meaning is expanded
in Section 3.
VYNPS DSAR Revision 1 1.0-17 of 17
1.4 SUMMARY OF RADIATION EFFECTS
1.4.1 Fuel Storage and Handling and Waste Management
Spent fuel storage and handling and waste management operations will be
conducted so that the dose to any off-site person, from external or internal
sources, will not exceed that permitted by 10 CFR 20.1301. It is expected that
during fuel storage and handling and waste management operations the dose to
any off-site person from gaseous waste discharge will not average more than
about 1% of the permissible dose, and that concentrations of liquid waste at
the point of discharge will average less than the concentrations permitted by
10 CFR 20. Both effects are only a small fraction of the effect of natural
background radiation.
For ISFSI operations, 10 CFR 72.106(b) defines the dose that any individual
located on or beyond the nearest boundary of the controlled area may receive
from any design basis accident associated with the ISFSI. For additional
information, see the VYNPS 10 CFR 72.212 Evaluation Report.
1.4.2 Accidents and Events
The ability of the station to withstand the consequences of accidents and
events without posing a hazard to the health and safety of the public is
evaluated by analyzing a fuel handling accident in the spent fuel pool and a
radwaste transfer cask drop event. The calculated consequences are
substantially below the dose limits given in 10 CFR 50.67 for the fuel handling
accident and 10CFR100 for the transfer cask drop event. A further description
is provided in Section 6.
1.5 GENERAL CONCLUSIONS
Based on the design of the facility and the analysis of credible events, there
is reasonable assurance that the facility can safely manage irradiated fuel and
radioactive waste without endangering the health and safety of the public.
VYNPS DSAR Revision 0
2.0-1 of 108
SITE AND ENVIRONS
TABLE OF CONTENTS Section Title Page
2.1 SUMMARY DESCRIPTION .................................................. 9
2.2 SITE DESCRIPTION ..................................................... 9
2.2.1 Location and Area ........................................... 9
2.2.2 Population ................................................. 10
2.2.3 Land Use ................................................... 10
2.2.4 Site Area Boundaries, Exclusion Area, and Low Population Zone ........................................ 12
2.2.5 Conclusions ................................................ 15
2.3 METEOROLOGY ......................................................... 22
2.3.1 General .................................................... 22
2.3.2 On-site Meteorological Programs ............................ 22
2.3.3 Diffusion Climatology ...................................... 22
2.3.4 Winds and Wind Loading ..................................... 23
2.3.5 Temperature and Precipitation .............................. 23
2.3.5.1 Temperature .................................... 23
2.3.5.2 Precipitation .................................. 24
2.3.5.3 Snowfall, Snow and Ice Loading ................. 24
2.3.6 Storms ..................................................... 26
2.3.6.1 Thunderstorms .................................. 26
2.3.6.2 Hurricanes ..................................... 27
2.3.6.3 Tornadoes ...................................... 27
2.3.7 Conclusions ................................................ 28
2.3.8 References ................................................. 29
2.4 HYDROLOGY AND BIOLOGY ............................................... 37
2.4.1 General .................................................... 37
2.4.2 Land Area Ground Hydrology ................................. 37
VYNPS DSAR Revision 0
2.0-2 of 108
2.4.2.1 Introduction ................................... 37
2.4.2.2 Surface Water .................................. 37
2.4.2.3 Groundwater .................................... 37
2.4.3 Hydrology .................................................. 38
2.4.3.1 Introduction ................................... 38
2.4.3.2 Stream Flow .................................... 38
2.4.3.3 Temperature .................................... 39
2.4.3.4 Floods ......................................... 39
2.4.4 Uses of River .............................................. 46
2.4.4.1 Introduction ................................... 46
2.4.4.2 Industrial Use ................................. 46
2.4.4.3 Public Use ..................................... 46
2.4.5 Biology .................................................... 47
2.4.5.1 Commercial Fisheries ........................... 47
2.4.5.2 Sport Fisheries ................................ 48
2.4.5.3 Bottom Fauna ................................... 48
2.4.5.4 Aquatic Plants ................................. 49
2.4.5.5 Conclusions .................................... 49
2.4.6 Chemical and Bacteriological Quality of Water ...................................................... 49
2.4.7 River Field Program ........................................ 50
2.4.8 Conclusions ................................................ 50
2.4.9 References ................................................. 52
2.5 GEOLOGY AND SEISMOLOGY .............................................. 76
2.5.1 General .................................................... 76
2.5.2 Geology .................................................... 76
2.5.2.1 Introduction ................................... 76
2.5.2.2 Geological Investigation Program ............... 76
2.5.2.3 Regional Geology ............................... 77
2.5.2.4 Site Geology ................................... 79
VYNPS DSAR Revision 0
2.0-3 of 108
2.5.2.5 River Geology .................................. 81
2.5.3 Seismology ................................................. 83
2.5.3.1 Introduction ................................... 83
2.5.3.2 Seismic Investigation Program .................. 83
2.5.3.3 Geologic and Tectonic Background ............... 83
2.5.3.4 Seismic History ................................ 83
2.5.3.5 Seismicity of Area ............................. 85
2.5.4 Conclusions ................................................ 86
2.6 RADIOLOGICAL ENVIRONMENTAL MONITORING PROGRAM ...................... 104
2.6.1 Objectives ................................................ 104
2.6.2 Monitoring Network ........................................ 105
2.6.2.1 Direct Radiation .............................. 105
2.6.2.2 Airborne ...................................... 106
2.6.2.3 Waterborne .................................... 106
2.6.2.4 Ingestion ..................................... 107
2.6.3 Land Use Census ........................................... 107
2.6.4 Emergency Surveillance .................................... 107
2.6.5 Reports ................................................... 108
VYNPS DSAR Revision 0
2.0-4 of 108
STATION SITE AND ENVIRONS LIST OF TABLES Table No. Title 2.2.4 Urban Centers Within 30 Miles of Site 2.2.7 Hazardous Materials Railroad Traffic Through Vernon,
Vermont 2.3.1 Meteorology Record 2.3.4 Winds During Thunderstorms 2.3.5 Rainfall Data from Hurricane Connie 2.4.1 Average and Extreme Values of Stream Flow Connecticut
River at Vernon, Vermont Water Years 1944-1988 2.4.2 Vermont Yankee Nuclear Power Station, Daily Stream Flow
for October 1964 to September 1965, Connecticut River at Vernon, Vermont
2.4.3 Municipal and Industrial Groundwater Usage Within a
10-Mile Radius of the Vernon Site 2.4.4 Public Water Supplies Within a 10-Mile Radius of the
Vernon Site 2.4.5 Water Supplies Within a l-Mile Radius of the Site 2.4.6 Six-Hour PMP and Runoff Increments - Connecticut River
Basin above Vernon, Vermont 2.4.7 Maximum Annual Floods on Connecticut River at Vernon,
Vermont - Arranged in Descending Order (1927, 1936, 1938, 1945-1973)
2.4.8 Time - Varying PMF Stage - Discharge Table Vermont Yankee
Nuclear Plant Site 2.4.9 Time - Varying Modified PMF Stage - Discharge Table
Vermont Yankee Nuclear Plant Site 2.4.10 Checklist of Connecticut River Fishes Found Near Vernon,
Vermont 2.4.11 Fishes of the Connecticut River in the Vicinity of Vernon,
Vermont - All Collections, 1980
VYNPS DSAR Revision 0
2.0-5 of 108
STATION SITE AND ENVIRONS LIST OF TABLES (Cont'd) Table No. Title 2.5.1 Available Information Concerning Geology and Seismic
Activity Related to the Vermont Yankee Nuclear Power Station Site
2.5.2 Vernon Pluton: Estimated Mode of the Oliverian Magma
Series
VYNPS DSAR Revision 0
2.0-6 of 108
STATION SITE AND ENVIRONS LIST OF FIGURES Reference Figure No. Drawing No. Title 2.2-1 Location Map - 2-Mile Radius 2.2-2 Location Map - 10-Mile Radius 2.2-3 Location Map - 25-Mile Radius 2.2-5 5920-6245 Plan Showing Exclusion Area and
Restricted Area Boundaries 2.3-1 Station Site - Westover AFB,
Massachusetts Area - Annual Surface Windrose
2.3-2 Station Site - Westover AFB, Massachusetts Area - Seasonal Surface Windroses – (Winter, Spring, Summer, Fall)
2.3-3 Station Site - Concord, NH Area - Return Period of Rainfall (for extremely short intervals)
2.4-1 Station Site - Area Public Water
Supplies - 10-Mile Radius 2.4-2 Station Site - Area Private Water
Supplies - 1-Mile Radius 2.4-3 Enveloping Depth-Duration-Area Values
of PMP for Susquehannna River Basin 2.4-4 6-Hour Unit Hydrograph 2.4-5 Total SPF Hydrograph 2.4-6 Total PMF Hydrograph (Natural and
Modified) 2.4-8 Vermont Yankee Nuclear Plant - Location
of River Cross-Sections 2.4-9 Stage-Discharge Curve at the Vermont
Yankee Nuclear Plant
VYNPS DSAR Revision 0
2.0-7 of 108
STATION SITE AND ENVIRONS LIST OF FIGURES (Cont’d) Reference Figure No. Drawing No. Title 2.4-10 Cross Section of the Critical Fetch
2.4-11 Vermont Yankee Sample Stations on
Connecticut River 2.5-1 Not Used 2.5-2 Station Site - Geological Survey -
General Plan - Location of Test Borings 2.5-3 Station Site - Geological Survey -
Subsurface Profile - Log of Test Borings (1A, 2A, 3A, 4, 5, 8)
2.5-4 Station Site - Tectonic Map - State of
Vermont 2.5-5 Station Site - Tectonic Map - State of
New Hampshire 2.5-6 Station Site - Geological Survey - Area
Bedrock Geology 2.5-7 Station Site - Geological Survey - Area
Geological Section 2.5-8 Station Site - Geological Survey -
Subsurface Profile (Section AA) - Log of Test Borings (5, 8, S9, 11, and 21)
2.5-9 Station Site - Geological Survey -
Subsurface Profile (Section BB) - Log of Test Borings (2A, 3A, ST6-1/2, and S9)
2.5-10 Station Site - Geological Survey - Subsurface Profile (Section CC) - Log of Test Borings (2, 2A, 5, 7, 7A, 13, and 15)
VYNPS DSAR Revision 0
2.0-8 of 108
STATION SITE AND ENVIRONS LIST OF FIGURES (Cont’d) Reference Figure No. Drawing No. Title 2.5-11 Station Site - Geological Survey -
Subsurface Profile (Section DD) - Log of Test Borings (3, 3A, 4, 8, 8A, 12, and 16)
2.5-12 Station Site - Tectonic Map - New
England Area 2.5-13 Station Site - Compilation of
Earthquakes - New England Area 2.5-14 Station Site - Earthquake Intensity -
Modified Mercalli and Rossi - Forel Scales
2.5-15 Station Site - Compilation of
Earthquakes - Central New England Area
VYNPS DSAR Revision 0
2.0-9 of 108
2.1 SUMMARY DESCRIPTION
HISTORICAL INFORMATION BELOW NOT REQUIRED TO BE REVISED.
This section provides information about the site and environs of the
Vermont Yankee Nuclear Power Station (VYNPS) and summarizes the analyses
and studies which confirm the suitability of the site
The site of the VYNPS at Vernon, Vermont, was thoroughly investigated and
found to be suitable in 1967 when the construction permit was issued.
Since the issuance of the construction permit, further review has been
pursued in the areas of meteorology, hydrology, and marine ecology, geology
and seismology, and environmental radiation monitoring. The results of
this additional review confirmed the suitability of Vernon as a nuclear
power plant site.
2.2 SITE DESCRIPTION
2.2.1 Location and Area
The site is located in the town of Vernon, Vermont in Windham County on the
west shore of the Connecticut River immediately upstream of the Vernon
Hydroelectric Station. The site contains about 125 acres owned by Entergy
Nuclear Vermont Yankee, LLC and a narrow strip of land between the
Connecticut River and the east boundary of the VYNPS property to which
Entergy Nuclear Vermont Yankee, LLC has perpetual rights and easements from
its owner. This land is bounded on the north, south, and west by
privately-owned land and on the east by the Connecticut River. Site
coordinates are approximately 42o 47' north latitude and 72o 31' west
longitude. Figures 2.2-1 through 2.2-3 locate the site. The site plot
plan, exclusion area boundary and site area boundaries for both gaseous and
liquid effluents are shown on Drawing 5920-6245.
VYNPS DSAR Revision 0
2.0-10 of 108
2.2.2 Population
HISTORICAL INFORMATION BELOW NOT REQUIRED TO BE REVISED.
The population density for 1990 was estimated to be about 121 people per
square mile within a five-mile radius of the site. The population density
in this same area was estimated to be 126 people per square mile in 2000,
and projected to be about 131 people per square mile by 2010. In 1990, the
total population within 25 miles was estimated to be 189,038, or an average
density of 96 people per square mile. For 2000, the 25-mile radius
population has been estimated to be about 193,746, or an average density of
99 people per square mile. This represents a growth factor of about 2.5%
for 2000 area over the ten-year period 1990 to 2000. The total resident
population within 50 miles for 2000 is estimated to be about 1,467,343.
Based on this region's projected growth rate of 4% over the next 10 years,
the estimated 50-mile population for the year 2010 is 1,526,037.
The nearest towns with populations of 25,000 or more are Northampton,
Massachusetts (2000 population 28,978) at about 30 miles to the south; and
Amherst, Massachusetts (2000 population 34,874) at about 28 miles south.
Accordingly, 28 miles is the population center distance.
2.2.3 Land Use
HISTORICAL INFORMATION BELOW NOT REQUIRED TO BE REVISED.
About 80% of the land within a 25-mile radius of the site is undeveloped.
Most of the developed land is used for agriculture and dairying, with homes
scattered or grouped in small villages.
The primary agricultural crop in the immediate site area is silage corn
which is stored for year-round feed for milk cows.
The area within 10 miles of the site has only one urban area, the city of
Brattleboro, Vermont (2000 population 12,005), which is located about 5
miles upriver. The remainder of this area is rural and contains several
small villages with populations between 1,000 and 3,000. The area between
10 and 25 miles has only three urban centers with 2000 populations between
11,299 and 22,563 (see Table 2.2.4).
VYNPS DSAR Revision 0
2.0-11 of 108
The closest site boundary is 910 feet west of the Reactor Building. The
nearest homes are situated along the Governor Hunt Road just west of the
site. An annual land use census checks on the location of the nearest
resident and reports this finding as part of the Annual Radiological
Environmental Operating Report. The Vernon Elementary School, which has a
pupil enrollment of about 250 is on the other side of the road (Highway No.
4) about 1,500 feet from the Reactor Building.
The nearest hospital, Brattleboro Memorial, is approximately five (5) miles
from the site. The nearest dairy farm is approximately 1/2-mile
west-northwest of the site and there are several others within a 5-mile
radius of the plant. The nearest railroad line runs north-south through
the site area, and is approximately 0.5 miles west of the plant at its
closest approach. Table 2.2.7 lists the approximate quantities of
hazardous materials which are annually shipped past the site by the
Springfield Terminal Railway and the Central Vermont Railway which utilize
this track. No other significant off-site sources of hazardous materials
have been identified within five (5) miles of the site.
The land within a 1-mile radius of the site is occupied by rural homes and
is used for dairy feed products and pasture, except for a residential area
of about 75 houses located about 0.8 miles across the Connecticut River.
About 30% of this area consists of the river and undeveloped land adjacent
to it.
VYNPS DSAR Revision 0
2.0-12 of 108
2.2.4 Site Area Boundaries, Exclusion Area, and Low Population Zone
As defined in 10 CFR 20 and 10 CFR 100, the terms "unrestricted area,"
"controlled area," "restricted area," "exclusion area," and "low population
zone" each refer to a specific area about the site as a result of applying
different radiological health constraints. The "unrestricted area" refers
to all areas beyond the site's outer security fence access to which is
neither limited nor controlled by the licensee. The "controlled area"
refers to all plant areas inside the site boundary, but outside of any
restricted area, access to which is limited by the licensee for any reason.
Access to the controlled area can be limited to minimize exposures to
members of the public from routine radioactive releases from the plant and
fixed radiation sources. "Restricted area" refers to the inner most areas
of the plant site and facilities, access to which is limited by the
licensee for the purpose of protecting occupationally exposed individuals
against undue risks from radiation and radioactive materials. Exclusion
area means that area surrounding the reactor, as measured from the reactor
center line, in which the reactor licensee has the authority to determine
all activities including exclusion or removal of personnel and property
from the area. This area may be traversed by a highway, railroad, or
waterway, provided those are not so close to the facility as to interfere
with normal operations of the facility and provided appropriate and
effective arrangements are made to control traffic on the highway,
railroad, or waterway, in case of an emergency, to protect the public
health and safety. The exclusion area also includes part of the adjacent
waterway (Connecticut River) extending across to the opposite shoreline.
Finally, the low population zone is delineated by an area about the plant
which includes residential, farming, industrial, etc., activities to some
extent, but is not so large or populated to prevent orderly, effective
radiological control or evacuation in the event of an accident of an
environmentally significant nature.
Thus, these areas and zones are delineated for different purposes and vary
in the degree of control that the licensee can exercise from a radiation
protection standpoint. The following discussion presents an analysis of
each area in relation to the plant and its operations.
VYNPS DSAR Revision 0
2.0-13 of 108
1. Controlled Area
The controlled area for the VYNPS site consists of a significant portion
of the 125-acre property area owned by Entergy Nuclear Vermont Yankee,
LLC. The fenced boundaries of this area are delineated on Drawing 5920-
6245. The fence is a 6-foot high security fence topped by l foot of
barbed wire. In addition to the fence, signs are posted clearly
informing an individual that the area is private property and
unauthorized entry is strictly prohibited. Access to and activities
within this area are under the direct control of Entergy Nuclear Vermont
Yankee, LLC and Entergy Nuclear Operations, Inc. Access to the area is
from the Governor Hunt Road through the main gate. The fence and
location combine to afford access and activity control to the VYNPS
site.
Two normally locked gates exist in the northern corners of the
Controlled Area for access by Security Officers from the Controlled Area
into the Exclusion Area on the northern part of the property. One gate
is located along the east fence line and one gate is located along the
west fence line. The gate on the west fence may also be used for
alternate access to the site for fire trucks.
For ISFSI operations, 10 CFR 72.106(b) defines the dose that any
individual located on or beyond the nearest boundary of the controlled
area may receive from any design basis accident associated with the
ISFSI. For additional information, see the VYNPS 10 CFR 72.212
Evaluation Report.
2. Effluent Boundaries
In addition to the land area within the site's outer security fence,
VYNPS includes the river water area between the northern and southern
boundary fences, and extending out to the state border near the middle
of the river, as part of the site boundary for control of gaseous
effluents as regulated under the dose objectives of 10 CFR 50, Appendix
I. The low exposure rates involved and the zero or near zero occupancy
factor applicable to individuals in the river area combine to allow
VYNPS to include this region for the purpose of controlling plant
releases to levels as-low-as-reasonably achievable. The restricted area
boundary for liquid discharge concentration limits (10 CFR 20) is set at
the point of discharge from the plant to the river (see Drawing 5920-
6245). Thus, the overall boundary area for the plant is as shown on
Drawing 5920-6245.
VYNPS DSAR Revision 0
2.0-14 of 108
To ensure compliance with the constraints applicable to the unrestricted
and controlled areas as described, area dosimeter stations are provided
at strategic locations around the site. Measurements of integrated
gamma exposure are made to alert VYNPS to any condition that may produce
a greater exposure than necessary.
3. Exclusion Area
The exclusion area for the VYNPS site is also shown on Drawing 5920-6245
and includes the controlled area defined above. The minimum distance to
the boundary of the exclusion area, as measured from the reactor center
line, is 910 feet. In addition, the Connecticut River water area
between Vernon Dam and the northern VYNPS property line is included in
the exclusion area since it will be a controlled access region during an
accident condition. The means of controlling access on the river, and
evacuating it if necessary, have been worked out with the State of New
Hampshire officials who will coordinate control activities over the
river.
Passage on the Connecticut River to Vernon Pond is possible. The
licensee will at all times retain the complete authority to determine
and maintain sufficient control of all activities through ownership,
easement, contract and/or other legal instruments on property which is
closer to the reactor center line than 910 feet. This includes the
authority to exclude or remove personnel and property within the
exclusion area. Only facility related activities are permitted in the
exclusion area. No residences will be permitted in the exclusion area.
Control over activities within, and access to, the exclusion area assume
an entirely different form immediately following a condition that
produces, or threatens to produce, a radiological hazard to the site.
The VYNPS Emergency Plan describes the types and level of emergency
action that will be initiated at the plant in order to minimize
radiation exposure following an accidental release. The only addition
to that discussion is that, as previously mentioned, evacuation and
access control will be placed into effect for the Connecticut River area
included in the exclusion zone.
A normally locked gate on the northwest corner of the Exclusion Area
fence is used for access by Vermont Electric Power Co for access to
their switchyards, and is also used by VYNPS as an alternate access to
the site for fire trucks and emergency equipment.
VYNPS DSAR Revision 0
2.0-15 of 108
4. Low Population Zone
The low population zone for the VYNPS is the area included within a
5-mile radius of the site. It is outlined on Figure 2.2-2.
5. General
The boundaries for the unrestricted area, controlled area, restricted
area, exclusion area, and low population zone, as well as for control of
effluents to levels as-low-as-reasonably achievable, as described, are
fully consistent with the principles involved in ensuring the health and
safety of the public, together with the plant personnel. In addition,
the delineation yields an effective arrangement with regard to efficient
facility operation.
The complete perimeter fence described for the protected area, together
with the fact that the only facility access point is maintained by the
security force, afford the licensee with complete, continuous access and
activity control for every component of the facility. In addition,
fencing is provided for the 115 kV and 345 kV switchyards.
Thus, the responsibilities of the licensee are met from both
radiological protection and plant security standpoints.
2.2.5 Conclusions
HISTORICAL INFORMATION BELOW NOT REQUIRED TO BE REVISED.
About 80% of the land within 25 miles of the site is undeveloped. The 2000
census shows that about 489 people live within 1 mile of the site and about
9,919 live within 5 miles. The 2000 data also show that population density
in the vicinity is light, about 126 persons per square mile within a 5-mile
radius and 99 persons per square mile within a 25-mile radius. Population
projections to 2010 predict about a 4% increase above the 2000 figures.
However, the average population density is expected to remain low. The
location of the site provides good local isolation with light population
density in the surrounding area.
In summary, the site is suitable for the facility as designed from
population distribution and land usage considerations.
VYNPS DSAR Revision 0
2.0-16 of 108
TABLE 2.2.4
Urban Centers Within 30 Miles of Site
City Approximate Distance
From Site - Miles
1960 1970 1980 1990 2000
Brattleboro, VT 4 9,315 12,239 11,886 12,241 12,005
Greenfield, MA 12 14,389
18,116 18,415 18,666 18,168
Keene, NH 13 17,562
20,467 21,449 22,430 22,563
Athol, MA 19 10,161
11,185 10,619 11,451 11,299
Amherst, MA 28 13,718
26,331 33,210 35,228 34,874
Northampton, MA 30 30,058
29,669 29,128 29,289 28,978
VYNPS DSAR Revision 1
2.0-17 of 108
TABLE 2.2.7
Hazardous Materials Railroad Traffic Through Vernon, Vermont
Chemical(1) Central Vermont(2)
Springfield Track(2)
Total Per Year
Carbon Dioxide 395 96 491
Nitrogen 248 -- 248
Propane (LPG) 60 162 222
Chlorine 60 -- 60
Sulfuric Acid -- 24 24
Anhydrous Ammonia 1 6 7
Methyl Alcohol -- 4 4
Xylene -- 2 2
(1) Listed in either Regulatory Guide 1.78 or EPA's Extremely Hazardous
Substance List.
(2) Railcars per year.
VYNPS DSAR Revision 1 2.0-18 of 108
Vermont Yankee Defueled Safety Analysis Report
Location Map – 2-Mile Radius
Figure 2.2-1
VYNPS DSAR Revision 1 2.0-19 of 108
Vermont Yankee
Defueled Safety Analysis Report
Location Map – 10-Mile Radius
Figure 2.2-2
VYNPS DSAR Revision 1 2.0-20 of 108
Vermont Yankee
Defueled Safety Analysis Report
Location Map – 25-Mile Radius Figure 2.2-3
VYNPS DSAR Revision 1
2.0-22 of 108
2.3 METEOROLOGY
HISTORICAL INFORMATION BELOW NOT REQUIRED TO BE REVISED.
2.3.1 General
The general climatic regime of the site area is that of a continental type
with some modification from the maritime climate which prevails nearer the
coast. Of special importance from an engineering standpoint is a temperature
range of 133oF for the period of record; extremes in annual snowfall, which
may be as little as 30 inches or as much as 118 inches; occasional ice storms;
occasional severe thunderstorms; occasional heavy rains due to hurricane
influences; and the possibility of an occasional tornado. These and other
pertinent meteorological data are presented in the following subsections.
Table 2.3.1 indicates the elements, station of record and lengths of record
that were utilized in the analyses.
The site meteorological monitoring program is the most important source of
additional information obtained since the submittal of the Plant Design and
Analysis Report (PDAR).
2.3.2 On-site Meteorological Programs
An initial data collection program was undertaken at the site of the Vermont
Yankee Atomic Power Station to provide information on meteorological
conditions for dispersion analysis for the PDAR. Data from one year, from
August 1, 1967 through July 31, 1968, were evaluated and formed the basis for
those analyses. Appendix G contains a discussion of the August 1967 - July
1968 data collected from the initial monitoring program.
An upgraded on-site monitoring program which meets the intent of Revision 0 to
Regulatory Guide 1.23 was installed in early 1976 and is currently in
operation. A description of this upgraded system is also presented in
Appendix G, along with wind and stability data summaries for one year of
operation.
2.3.3 Diffusion Climatology
The river valley location of the site exerts a strong influence on wind
distribution. As seen in the various wind roses of Appendix G, the channeling
effect of the valley is readily apparent. However, there is no appreciable
difference in wind distribution during poorer dispersion conditions.
VYNPS DSAR Revision 1
2.0-23 of 108
The PDAR stated inversion frequency estimates on the basis of C. R. Hosler's
tabulations(1). These are repeated below together with the corresponding
values determined from the site preoperational meteorological program. As
shown, the maximum difference occurred in the spring season.
Inversion Frequency (% of total hours)
Hosler's
Estimates
Site Meteorological
Program
Winter 33 37
Spring 26 42
Summer 31 37
Fall 36 36
2.3.4 Winds and Wind Loading
At the time the PDAR was submitted, no continuous wind records were available
for the Vernon area. Due to the similarity in terrain, the relatively close
location, and ready availability of information, wind data from Westover,
Massachusetts, was presented at that time. The annual and seasonal surface
wind roses from Westover are shown in Figures 2.3-1 and 2.3-2. The annual and
seasonal wind roses are based upon the total possible hours for each time
interval specified and, in each case, add to 100%.
The corresponding annual and seasonal wind roses obtained from the site
monitoring programs are shown in Appendix G. The several sets of wind roses
show the same channeling effect due to topographical similarities.
The minimum allowable resultant wind pressure(2) at 30 feet suggested by the
National Bureau of Standards for the Vernon area is 25 lb-ft-2. This value
was used as the general facility design basis.
2.3.5 Temperature and Precipitation
2.3.5.1 Temperature
Temperature data(3,4,5) from the records of Vernon (one-half mile south) and
Brattleboro (6 miles north) should be representative of the values for the
site.
VYNPS DSAR Revision 1
2.0-24 of 108
The mean number of days with temperatures greater than 90°F or less than 32°F
for Vernon (1951-1960) are as follows:
2.3.5.2 Precipitation
Precipitation(6) at the site averages 43 inches per year and is distributed
rather evenly throughout the 12-month period. Snowfall is moderately heavy on
the average; but there is considerable variation in amounts from season to
season. Nearly all winter precipitation is in frozen form, although not
entirely as snow. Sleet and freezing rain are not uncommon.
Intense rainfall will be produced by the occasional severe thunderstorm or
modified hurricane. The maximum (8,9) recorded rainfall (inches) for short
time intervals at Concord, New Hampshire, is given below:
Minutes Hours
5 10 15 30 60 2 3 6 12 24
0.66 1.12 1.60 2.53 2.71 2.73 3.56 3.82 5.53 5.97
The return period of extreme short-interval rainfall is a useful
design-and-planning guide. The nearest location for which return data are
available and which should be reasonably representative for the Vernon area is
Concord, New Hampshire. These data are shown in Figure 2.3-3.
2.3.5.3 Snowfall, Snow and Ice Loading
The site being located in the northeastern part of the United States is
subjected to a wide range of snowfall, which may be as little as 30 inches or
as much as 118 inches(5,10). Average snowfall statistics for Vernon (25 years
of record) are considered to be representative of the site.
* More than 0 but less than 0.5
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Ann
>90° 0 0 0 0 * 3 6 3 1 0 0 0 13
<32° 30 28 29 14 6 * 0 0 2 13 23 30 175
VYNPS DSAR Revision 1
2.0-25 of 108
The most significant departure from the historical values occurred in the
amount of snowfall at Vernon between November 1968 and February 1969.
Snowfall during this period amounted to 80.2 inches compared with an average
for this period of 45.9 inches. The heaviest monthly snowfall was 42.7 inches
and occurred in February. This compares with a historical average value of
15.7 inches. However, the maximum annual snowfall of 118 inches was not
exceeded.
Average Monthly Snowfall (inches) for Vernon
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Ann
16.4 15.7 12.1 2.1 0.1 0.0 0.0 0.0 0.0 T 3.3 10.5 60.0
T = Trace
Snow load data(11) available from a Housing and Home Finance Agency (HHFA)
study conducted in 1952 is as follows:
Weight of Seasonal Weight of Maximum Weight of Estimated
Snowpack Equaled or Snowpack Maximum Accumulation on Ground Plus
Exceeded 1 year in 10 of Record Weight of Maximum Possible Snowstorm
30 lb-ft-2 50 lb-ft-2 70 lb-ft-2
Data relating to freezing rain and resultant formation of glaze ice(12) on
highways and utility lines are available from the following studies:
American Telephone and Telegraph Company, 1917-18 to 1924-25
Edison Electric Institute, 1926-27 to 1937-38
Association of American Railroads, 1928-29 to 1936-37
Quartermaster Research and Engineering Command, U.S. Army, 1959
The U.S. Weather Bureau also maintains annual summaries. The conclusions
reached from these several sources are sometimes contradictory, but the
following is probably a fairly accurate description of the glaze-ice
climatology of southern Vermont.
VYNPS DSAR Revision 1
2.0-26 of 108
The most typical synoptic condition for glaze formation or freezing rain in
the northeastern United States is a polar front wave with an active warm front
moving in the north or northeasterly direction toward the region. A high
pressure area almost always is found north of New England, with the center of
the ridge or high pressure cell usually located somewhere northeast of
Newfoundland. This distribution causes a flow of cold continental-polar air
over the area from the north or east, and warm maritime-tropical air up from
the south behind the warm front.
In this situation, the over-running maritime-tropical air is frequently warmer
than 32oF, while the cold continental-polar air beneath the front has
temperatures from 20o to 30oF, and a situation almost ideal for the formation
of freezing rain or drizzle results. The Vermont site is situated on the
northern edge of the "glaze belt" which extends from southern New England
west-southwest to Ohio and then curving down into Texas. The following data
will apply:
1. Times of occurrence - November through April,
2. Average frequency without regard to ice thickness - 0-10 storms per year,
3. Duration of ice on utility lines - 20 hours (mean) to 55 hours (maximum
of record),
4. Return periods for freezing rain storms producing ice of various
thicknesses are:
Ice 0.25 inch every year
0.50 inch every year
0.75 inch at least every 3 years
A U.S. Weather Bureau summary for the years 1939-48 give the actual number of
days with freezing rain (without regard to ice formation) for Concord, New
Hampshire, as follows:
Total Days in
Nov Dec Jan Feb Mar Apr 10 Years
2 24 29 23 16 1 95
2.3.6 Storms
2.3.6.1 Thunderstorms
Some localized wind damage occurring with the passage of thunderstorm line
squalls may be experienced each year. Extreme wind data(13) for Westover,
Massachusetts, is shown in Table 2.3.4.
VYNPS DSAR Revision 1
2.0-27 of 108
The "Index of Wind Damage Potential" (excluding tornado, hurricane, and
tropical storm and hail)(defined in units of 1000ths of 1% of residential
property value per year) for the Vernon area is 12 compared to a value of 16
for the Oklahoma-Kansas area.
Heavy precipitation is usually associated with severe thunderstorms and
modified hurricanes. The maximum in 24 hours for Vernon (62 years of record)
is listed below.(8)
Maximum in 24 Hours (inches)
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
2.21 2.89 4.35 2.49 3.23 3.50 3.80 4.35 3.99 3.57 3.13 2.21
2.3.6.2 Hurricanes
Unusual heavy precipitation(14) was associated with hurricane Connie (August
11-14, 1955) and Diane (August 17-20, 1955). Mass rainfall tables for Birch
Hills, Massachusetts (approximately 28 miles south) are in Table 2.3.5.
In "Index of Hurricane and Tropical Storm Damage Potential" (defined in units
of 1000ths of 1% of residential property value per year) for the Vernon area
is 140 as compared to 337 for the Cape Cod area, 606 for the Cape Hatteras,
North Carolina area, and 633 for the Miami, Florida area. The decrease in the
index of hurricane potential as one moves northward is indicative of the
decreased intensity of the hurricane due to several physical reasons. Being
cut off from the major source of energy (the ocean) as a hurricane proceeds
northward, it diminishes in intensity. Topography also causes frictional drag
the farther the storm travels over land, thereby reducing the storm's
magnitude.
2.3.6.3 Tornadoes
Severe storms such as tornadoes(15) are not numerous, but they do occur
occasionally. Most tornadoes that occur in New England occur in
Massachusetts.
Massachusetts Vermont New Hampshire
Total Number of
Tornadoes (1916-1958) 56 11 15
(1959-1965) 23 12 22
VYNPS DSAR Revision 1
2.0-28 of 108
The apparent increase in tornado activity is probably due to increased
population and more and better observing and reporting facilities and
techniques.
The monthly distribution (1916-1965) of tornadoes for the tri-state area is as
follows:
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Total
Massachusetts 12 15 26 9 6 6 3 2 79
Vermont 1 1 3 7 8 2 1 23
New Hampshire 6 8 14 6 2 1 37
In the period 1916 through 1965, Bennington County, Vermont, has reported only
2 tornadoes. Cheshire County, New Hampshire, reported 8, and Franklin County,
Massachusetts reported 9 for a total of 19 tornadoes for the immediate area.
The "Index of Tornado Damage Potential" (defined in units of 1000ths of 1%
residential property values per year) for the tri-county area is 1 as compared
to a value of 33 in "tornado alley" (Oklahoma-Kansas-Nebraska).
Thom(16) divides the United States into 1-degree squares and determines the
tornado frequency for each square. Using data from 1953-62, Thom records 12
tornadoes occurring within a 1-degree square (about 3 million acres)
encompassing the Vernon site. A mean recurrence interval for a tornado
striking a point within this 1-degree square was calculated to be 1040 years.
This seems reasonable if one considers that only 12 tornadoes were reported in
about 3 million acres in a 10-year period.
Even though the probability of a tornado at the site is small, all structures
and equipment necessary for the safe storage of irradiated fuel are designed
to withstand short-term loadings resulting from 300 mph tornadic winds and an
external pressure drop of 3 psi in 5 seconds.
2.3.7 Conclusions
The meteorology of the site is basically that of a continental type with some
modification from the maritime climate which prevails nearer the coast. The
annual frequency of inversion was determined to be 39%, within the 30% to 40%
range predicted in the PDAR.
The average annual wind speed for the site is 7.5 mph and the most frequent
direction is NNW, the downriver direction. The river valley location leads to
a channeling of the winds.
VYNPS DSAR Revision 1
2.0-29 of 108
In summary, the site meteorological program substantiates the preliminary
conclusions. No changes in the previously described protection features were
necessary as a result of meteorological considerations.
2.3.8 References
1. "Low-Level Inversion Frequency in the Contiguous United States," Charles
R. Hosler, Monthly Weather Review, Vol. 89, No. 9, September 1961, pp.
319-339.
2. "Wind Pressures in Various Areas of the United States," Building
Materials and Structures, Report 152. National Bureau of Standards,
1959.
3. Climatological Data, New England, July Issue for 1962-1965 (four
publications), U.S. Weather Bureau.
4. Climatic Summary of the United States - Supplement for 1931 through 1952,
New England, U.S. Weather Bureau.
5. Climatic Summary of the United States - Supplement for 1951 through 1960,
New England, U.S. Weather Bureau.
6. "Rainfall Intensity - Duration - Frequency Curves", Technical Paper No.
25, U.S. Weather Bureau, 1955.
7. Deleted
8. "Maximum 24-Hour Precipitation in the United States," Technical Paper No.
16, U.S. Weather Bureau.
9. "Maximum Recorded United States Point Rainfall for 5 Minutes to 24
Hours," Technical Paper No. 2, U.S. Weather Bureau.
10. Climatological Data, New England, July Issues 1961-1965, U.S. Weather
Bureau (five publications).
11. "Snow Load Studies," Housing Research Paper 19, Housing and Home Finance
Agency, 1952.
12. "Glaze, Its Meteorology and Climatology, Geographical Distribution, and
Economic Effects," Quartermaster Research and Engineering Center, 1959.
VYNPS DSAR Revision 1
2.0-30 of 108
13. Climatological Data, National Summaries (1959-60-61-62-63-64-65), U.S.
Weather Bureau.
14. "Hurricane Rains and Floods of August 1955, Carolinas to New England,"
Technical Paper No. 26, U.S. Weather Bureau.
15. "Tornado Occurrences in the United States," Technical Paper No. 20, U.S.
Weather Bureau.
16. "Tornado Probabilities," H.C.S. Thom, Monthly Weather Review, U.S.
Weather Bureau, Washington, D.C., October-December 1963, pp. 730-736
VYNPS DSAR Revision 1
2.0-31 of 108
TABLE 2.3.1 METEOROLOGY RECORD Weather Element Station Record Period Temperature Brattleboro 11 years Vernon 10 years Precipitation Vernon 62 years Snowfall Vernon 25 years Surface Wind Westover, MA 22 years Surface Wind Vernon 1 year Stability Class Vernon 1 year
VYNPS DSAR Revision 1
2.0-32 of 108
TABLE 2.3.4
WINDS DURING THUNDERSTORMS Westover, MA Max. Winds(1) Peak Gusts(2) (from hourly obs.) (from daily obs.) Speed Speed Month Direction (knots) Direction (knots) Jan S 52 NW 55 Feb NNW 40 S 58 Mar NE 63 NNW 50 Apr S 36 ENE 61 May SSE 38 NNW 48 June S 28 NNW 49 July NNW 28 W 47 Aug NNE 47 NNE 62 Sept NNE 52 N 60 Oct NW 37 SSE 49 Nov N 39 ENE 69 Dec N 39 NNW 54
(1) For period Apr 1941 through Dec 1963. (One minute sustained wind) (2) For period Jan-Apr 1946, Jan, Feb, Apr, June, July 1949, Jan, Apr 1950 through
Dec 1963
VYNPS DSAR Revision 1 2.0-33 of 108
TABLE 2.3.5 RAINFALL DATA FROM HURRICANE CONNIE Birch Hill, MA Amherst, MA Time (Accumulative Inches) (Accumulative Inches) Aug. 11 - 6 AM 0.05 12 N 0.06 6 PM 0.14 2.15 12 M 0.24 2.25 Aug. 12 - 6 AM 1.00 3.35 12 N 1.40 3.90 6 PM 1.45 4.07 12 M 1.60 4.40 Aug. 13 - 6 AM 2.15 4.90 12 N 2.30 5.91 6 PM 4.30 7.65 12 M 6.30 7.70 Aug. 14 - 6 AM 6.39 7.70 12 N 6.40 7.70 6 PM 6.48 7.70 12 M 6.48 7.70 Aug. 15 - 6 AM 7.72 12 N 7.72 6 PM 7.72 12 M 7.73
VYNPS DSAR Revision 1 2.0-34 of 108
Vermont Yankee
Defueled Safety Analysis Report
Station Site - Westover AFB,
Massachusetts Area- Annual Surface Windrose
i 2 3 1
VYNPS DSAR Revision 1 2.0-35 of 108
Vermont Yankee
Defueled Safety Analysis Report
Station Site - Westover AFB,Massachusetts Area- Seasonal Surface Windroses (Winter – Spring – Summer – Fall)
Figure 2.3-2
VYNPS DSAR Revision 1 2.0-36 of 108
Vermont Yankee Defueled Safety Analysis Report
Station Site – Concord, New Hampshire Area- Return Seasonal Surface Windroses
Period of Rainfall – (For extremely short intervals)
Figure 2.3-3
VYNPS DSAR Revision 1 2.0-37 of 108
2.4 HYDROLOGY AND BIOLOGY
HISTORICAL INFORMATION BELOW NOT REQUIRED TO BE REVISED.
2.4.1 General
The site is at mile 138.3 above the mouth of the Connecticut River, located on
the west bank of the river, on the pond formed by the Vernon Dam and
Hydroelectric Station, licensed by the Federal Energy Regulatory Commission as
Project No. 1094. The site is about 3,500 feet upstream from the Vernon
Hydroelectric Station, on the same side of the river. The Vernon
Hydroelectric Station is the furthest downstream of a series of six
hydroelectric projects totaling over 456,000 kW on the river. Storage
reservoirs, whose contents total over 330,000 acre-feet, are also usable for
power generation.
Three of the dams, at 32, 75, and 132 miles above the site, are relatively low
structures developing heads of from 29 to 62 feet, with small amounts of
pondage. The large storage reservoirs are from 150 to 260 miles upstream from
Vernon.
2.4.2 Land Area Ground Hydrology
2.4.2.1 Introduction
The river in this general reach comprises a series of ponds formed by several
dams constructed for the generation of hydroelectric power.
There is sufficient groundwater in the area to provide wells for public as
well as private use.
2.4.2.2 Surface Water
All local streams in the area drain to the Connecticut River, and the site is
in the direct path of natural drainage to the east from the local watershed.
Surface drainage will flow toward the river.
2.4.2.3 Groundwater
2.4.2.3.1 Regional Area
There are several municipalities in the vicinity in which groundwater is
utilized as one source of water supply. These are listed in Tables 2.4.3 and
2.4.4 and shown in Figure 2.4-1. Private wells in the vicinity of the site
are listed in Table 2.4.5 and shown in Figure 2.4-2.
VYNPS DSAR Revision 1 2.0-38 of 108
2.4.2.3.2 Site Area
The local water table level fluctuates differentially depending on the amount
of precipitation. It is affected by level changes in the Connecticut River.
River flooding will cause a temporary reversal in the flow direction of
groundwater, so that the local water table will be considerably higher than
usual during periods when the river level is high. Natural subsurface
drainage is over the rock surface.
In 1988 and 1989, groundwater monitoring wells were established throughout the
site area. Groundwater levels varied between about 5 feet to 18 feet below
ground surface in the northern portion of the site. In the vicinity of the
major plant structures, groundwater was determined to be about 20 feet below
ground surface. Along the southern portion of the site, depth to groundwater
was about 30 feet. Although these levels do vary throughout the year, they do
provide a general indication of site area groundwater levels.
Hydraulic gradients, as computed from water level elevations measured in
monitoring wells, bedrock water supply wells and the river, demonstrate that
groundwater flow in the overburden and bedrock is from west to east. Vertical
hydraulic gradients indicate vertically downward groundwater flow from the
shallow soils to the underlying lower sand deposit, and vertically upward flow
from the bedrock to the overlying lower sand deposit. These data indicate
that groundwater discharges into the river.
Current groundwater monitoring requirements are specified by the VYNPS
Radiological and Non-Radiological Environmental Monitoring Programs and
associated implementing procedures.
2.4.3 Hydrology
2.4.3.1 Introduction
Under normal conditions, the flow of river water is largely determined by
operation of the hydroelectric stations and by the upstream reservoirs and
lakes.
2.4.3.2 Stream Flow
Connecticut River flow is monitored at Vernon Dam. Records were published by
the United States Geological Survey from 1944 to 1973 when their gage at
Vernon was discontinued. Drainage area at Vernon Dam is 6,266 square miles.
Nearby gages on the Connecticut River include N. Walpole, New Hampshire and
Turners Falls, Massachusetts. Their continuous periods of record are from
1942 and 1915 to the present at N. Walpole and Turners Falls, respectively.
The drainage areas at these two gages are 5,493 and 7,163 square miles.
VYNPS DSAR Revision 1 2.0-39 of 108
Table 2.4.1 shows average and extreme values of monthly stream flow plus
minimum weekly flows for the Connecticut River below Vernon Dam for a 44-year
period of record (1944-1988). These stream flows were compiled using the
measured stream flows at Vernon from 1944 to 1973 and the generated stream
flows for Vernon using stream flow data from the two nearby gages for the
period 1973 to 1988.
Table 2.4.2 shows daily stream flows measured below Vernon for the period
October 1964 through September 1965.
2.4.3.3 Temperature
River temperatures have been measured along the river at six sampling
stations. The uppermost is at a point just downstream from Brattleboro, some
4-1/2 miles above the site, and the farthest downstream is at a point just
upstream of the Schell Bridge in Northfield, Massachusetts, some 6-1/2 miles
below the site.
Temperature measurements were made below Vernon Dam, in the general area of
the permanent monitoring Station 3, to determine how and where best to
establish this station for reliable, consistent results. A similar
temperature monitoring station (Station 7) has been established upstream of
the station circulating water intake. Continual records from these two
temperature monitoring stations are submitted annually to the Vermont Agency
of Natural Resources. The locations of these monitoring stations are
presented in Section 2.4.5.
In addition to the records presently being obtained at the site, temperature
records have been kept for a number of years at the Bellows Falls
Hydroelectric Station, some 32 miles upstream. River temperatures also have
been recorded over a period of several years at the Cabot Hydroelectric
Station, a unit of the Turners Falls Hydroelectric Project, downstream from
the site.
2.4.3.4 Floods
The flood of March 19, 1936, was the greatest and most destructive flood on
this reach of the river. The discharge on that day was 176,000 cfs, reaching
a river stage at Vernon of 231.4 feet MSL. Other major floods were those of
November 5, 1927, 155,000 cfs at elevation 229.0 feet MSL; and
September 22, 1938, 132,500 cfs at elevation 226.6 feet MSL.
Since the floods of 1936-1938, extensive flood control works, consisting of
some five projects with 247,800 acre-feet of flood storage, have been designed
and constructed by the Corps of Engineers in the Connecticut River Basin
upstream from the Vernon Dam.
VYNPS DSAR Revision 1 2.0-40 of 108
The Probable Maximum Flood (PMF) on the Connecticut River Basin above Vernon,
Vermont (drainage area of 6,266 square miles) was determined using procedures
and information contained in the analytical studies for the Susquehanna River
(1). In addition, a stage-discharge curve was developed through step
backwater computations to determine the PMF elevation at the site.
In this study, the major emphasis was in the direction of conservatism. The
following conservative assumptions were made:
1. The maximum persisting 12-hour, 1000-millibar (mb) dew point temperature
of record is used as an index of the maximum precipitable water.
Furthermore, the 12-hour maximum persisting dew point was used throughout
the 72-hour rainfall period.
2. The unit of time selected for the unit hydrograph is 6 hours, although for
a basin area of 6,266 square miles and a lag time of 75 hours,
characteristic of the Connecticut River at Vernon, a more realistic unit
of time for the unit hydrograph would be 12 hours.
3. An infiltration rate of 0.05 inches per hour is assumed throughout the
rainfall period, although the recorded range for this particular basin is
0.05-0.10 inches per hour.
4. A baseflow of 58,800 cfs, which is about 5.7 times the average discharge
and greater than the annual peak discharge recorded in four of the 29-year
period of record, and about twice the value which is normally used.
Enveloping curves of PMP for 6, 12, 24, 48, and 72 hours were obtained by
adjustment of the depth-area-duration curves for the Susquehanna River Basin
(Figure 2.4-3). The adjustment is based on the precipitable water in the
1,000-200-mb air column (2) for the maximum persisting 12-hour, 1,000-mb dew
point of record (3). By applying the maximum persisting 12-hour, 1,000-mb dew
point of record and assuming this condition persists for an additional
60 hours (the PMP duration is 72 hours), there is a considerable amount of
conservatism in deriving the PMP for the basin.
At Harrisburg, Pennsylvania, the record maximum persisting 12-hour, 1,000-mb
dew point of 75.3F is equivalent to 2.93 inches of precipitable water, while
at Vernon, Vermont, it is 73.3F or 2.62 inches of precipitable water.
The 6-hour increments of PMP and runoff amounts, based on an infiltration rate
of 0.05 inches per hour, are presented in Table 2.4.6.
The 6-hour unit hydrograph (Figure 2.4-4) was derived from the Standard
Project Flood (SPF) hydrograph developed by the New England District of the
Corps of Engineers (Figure 2.4-5) by:
VYNPS DSAR Revision 1 2.0-41 of 108
1. Separating the base flow and snowmelt from the total flow to obtain the
flood flow due to rainfall runoff.
2. Computation of the rainfall runoff (4.5 inches).
3. Dividing the ordinates of the SPF net flow by the rainfall runoff.
4. Conversion of the resulting 24-hour unit hydrograph to a six-hour unit
hydrograph by the S-curve technique (4).
The resulting hydrograph is a 6-hour unit hydrograph for the entire
6,266-square mile basin. The natural PMF hydrograph was then derived by
multiplying the ordinates of the 6-hour unit hydrograph and the 6-hour values
of rainfall runoff, summing the subtotals, and adding back the base flow
(58,800 cfs). The resulting natural PMF hydrograph is presented in
Figure 2.4-6.
There are five flood control storage reservoirs in the Connecticut River Basin
above Vernon. The total storage capacity of the reservoirs is
247,800 acre-feet, which represents a rainfall runoff over the total basin of
0.74 inches. The storage capacity of each reservoir is:
1. Union Village 38,000 acre-feet
2. North Hartland 71,400 acre-feet
3. North Springfield 50,600 acre-feet
4. Ball Mountain 54,600 acre-feet
5. Townshend 33,200 acre-feet
The operation of these flood control facilities has reduced the flood threat
in the basin. For instance, the Corps of Engineers estimates that the SPF
natural peak discharge of 263,700 cfs at Vernon has been reduced to
225,000 cfs for a net reduction of 38,700 cfs.
As stated above, the operation of current flood control facilities has reduced
the SPF at Vernon from a natural peak of 263,700 cfs to 225,000 cfs, or a
reduction of 38,700 cfs. If this same reduction were applied to the PMF, the
peak discharge would be decreased from 506,400 cfs to 469,700 cfs.
However, for conservatism, it is assumed that due to antecedent conditions,
the entire 247,800 acre-feet of storage capacity upstream is not available for
regulation of the PMF. Therefore, assuming that about 68% of the SPF
reduction would go into storage, the modified PMF discharge becomes
480,100 cfs. The resulting modified PMF hydrograph is shown in Figure 2.4-6.
VYNPS DSAR Revision 1 2.0-42 of 108
The stage-discharge curve at the VYNPS site at Vernon was determined by the
standard step backwater method as described by Chow (5) utilizing the Ebasco
Backwater Calculation with Bridge Loss programmed for implementation on a
Burroughs 5500 computer. The recorded water surface profiles for applicable
floods of record (Table 2.4.7) were used as a basis for selecting roughness
coefficients, "n". The following "n" values were found to yield excellent
agreement with recorded flood profiles:
River Reach Low High Channel Overbank Above Vernon Dam 0.030 0.033 0.040 At Vernon Dam 0.013 0.013 0.013 Below Vernon Dam 0.030 0.033 0.050 River and valley cross sections upstream from Vernon Dam to the plant site and
downstream to the Central Vermont Railroad Bridge at Northfield,
Massachusetts, which were used for the step backwater computation are located
in Figure 2.4-8. The final rating curve for the plant site is shown in
Figure 2.4-9.
The time-varying PMF stage-discharge relationships are listed in Table 2.4.8
for the natural flood hydrograph and in Table 2.4.9 for the hydrograph as
modified by existing flood storage. Based on the PMF hydrograph modified for
existing flood storage, the PMF stillwater level at the site is
252.5 feet MSL.
As a check on the design flood for the site, failure of the largest upstream
flood control reservoir, Townshend Reservoir, was postulated to occur as a
result of an earthquake, which, in turn, occurs simultaneously with the SPF.
For conservatism, the maximum inflow of 71,000 cfs for this reservoir, which
is located about 22 miles upstream from Vernon, was considered to be
translated downstream and directly added onto the SPF peak discharge. This
coincident dam failure with the SPF modified peak discharge of 225,000 cfs
would produce a peak discharge of 296,000 cfs. From Figure 2.4-9, a peak
discharge of 296,000 cfs would produce a maximum stillwater elevation at the
site of 240.8 feet MSL.
The dam failure analysis described above was originally developed as a check
to ensure that the controlling flood for the site was the
precipitation-induced PMF. Since completion of the above upstream dam failure
analysis, additional information on flooding at the site due to failure of
upstream flood control and hydropower dams has been developed by the dam
owners and is summarized below. These more recent studies are based on
different criteria and analysis techniques than the previously described
analysis.
VYNPS DSAR Revision 1 2.0-43 of 108
There are several large dams on the Connecticut River upstream of the VYNPS
site. The owners of these dams are required by the Federal Energy Regulatory
Commission to perform dam failure analysis as input to the development of
Emergency Action Plans. The only upstream dam failure flood that reaches the
VYNPS site for these Connecticut River dams is that for the Moore Dam. The
impacts for the other dam failures terminate well upstream of the site.
The hypothetical failure of Moore Dam was assumed to coincide with the peak of
the PMF inflow hydrograph. The dam is about 145 miles upstream from the VYNPS
site. Four downstream dams, Comerford, McIndoes, Dodge Falls and Wilder, were
assumed to fail in cascade. The results of the Moore Dam failure analyses at
Vernon Dam are a peak inflow of 305,600 cfs and a peak flood elevation of
240.1 feet MSL. The VYNPS site is subject to the same flood elevation as the
Vernon Dam. The arrival time at the site for the leading edge of the Moore
Dam failure flood wave is about 22 hours after the postulated failure of the
dam. The time of the peak flood at the site is about 47 hours after the
postulated dam failure.
There are also five flood control reservoirs on Connecticut River tributaries,
upstream of the VYNPS site. The owners have developed dam breach profiles for
each of the five dams. A review of these analyses showed that the impacts of
dam failure for three of the dams, Union Village, North Hartland, and North
Springfield do not reach the VYNPS site. Two of the dams, Townshend and Ball
Mountain, do produce flood levels downstream that reach the site. Both of
these dams are located on the West River, which is a tributary of the
Connecticut River.
For an assumed failure of Townshend Dam, the peak stage at Vernon Dam is
elevation 230 feet MSL. The time from the start of dam failure until the peak
stage is reached at the VYNPS site is 9.2 hours. The time from the start of
dam failure until the initial rise at the site is 5.2 hours. This analysis
used assumed pre-breach high flows in both the West and Connecticut Rivers.
For an assumed failure of Ball Mountain Dam, the peak stage at Vernon Dam is
elevation 235 feet MSL. The Ball Mountain Dam is upstream of the Townshend
Dam. The Townshend Dam fails as a result of the assumed failure of the Ball
Mountain Dam. The time from the start of dam failure until the peak stage is
reached at the VYNPS site is 10.0 hours. The time from the start of dam
failure until the initial rise at the site is 7.6 hours. This analysis also
assumed pre-breach high flows in both the West and Connecticut Rivers.
In summary, the flood levels at the VYNPS site due to upstream dam failures
are well below the PMF level at the site.
VYNPS DSAR Revision 1 2.0-44 of 108
The maximum PMF stillwater level at the VYNPS site at Vernon, Vermont was
computed to be 252.5 feet MSL occurring 96 hours after the beginning of the
72-hour probable maximum precipitation period. Additional consideration is
now given to the problem of wave runup.
Atomic Energy Commission Safety Evaluation Docket No. 50-271 dated
June 1, 1971 has been reviewed during the NEI 12-07 Fukushima Flooding
evaluation and is considered the governing document. Page 12 of this document
concludes, “The PMF will produce a maximum discharge of 480,000 cfs at the
site and a corresponding stage of 252 feet 6 inches MSL. This maximum occurs
eight days after the start of the rainfall causing the flood. We consider it
possible that another storm or synoptic weather system with sustained winds of
at least 45 mph could follow the original storm and be at the site at the same
time that the peak discharge occurs. If the winds came from the most
effective direction, waves two to four feet high could result. These waves
would break at the river bank, but could produce plant flooding at elevations
as high as 254 feet MSL.
Nominal plant grade is 252.0 feet MSL. Accesses to the Turbine, Reactor,
Radwaste, and Control Buildings from out of doors are at grade 252.5 feet MSL.
In addition, direct access to the Reactor Building from out of doors is
through a pair of leak-tight doors.
Fuel pool cooling will be maintained during a maximum probable flood until
service water is lost due to river water leakage into the intake structure or
normal power is lost.
If normal electrical power is unavailable, the Vernon Hydroelectric Station
and the Station Blackout Diesel Generator are available to supply back-up
power.
If fuel pool cooling cannot be maintained during a maximum probable flood,
alternate fuel cooling strategies are available and will be implemented in
accordance with applicable facility procedures.
The PMF stillwater level is essentially equal to the top of most yard
electrical manholes. A potential avenue of water intrusion into the
Switchgear Room, Elevation 248.5 feet MSL exists through underground conduits
routed from manholes and handholes to the Switchgear Room floor. Should water
enter these manholes, the underground conduits could provide a path for water
to enter the Switchgear Room manholes. If the water level gets high enough,
flooding in the Switchgear Room and lower levels of the administration and
Turbine Building could occur. This flooding could affect the operability of
switchgear.
VYNPS DSAR Revision 1 2.0-45 of 108
To preclude, or reduce the amount of water entering the Switchgear Room
manholes through the underground conduits which extend from the yard manholes,
these conduits have been sealed. In conjunction with the conduit sealing,
portable pumping capacity is available on-site to remove water which may enter
the Switchgear Room manholes. Additionally, facility procedures direct
personnel to remove this water as part of the site flood procedures.
Based on our review of these results of the flood analysis, we conclude that
acceptable measures will and can be taken to assure safe storage of irradiated
fuel even in the unlikely event that floods as large as the PMP should occur.”
The facility is, therefore, suitably protected against the maximum probable
flood and all lesser floods, including those due to the failure of upstream
dams.
VYNPS DSAR Revision 1 2.0-46 of 108
2.4.4 Uses of River
2.4.4.1 Introduction
The Connecticut River and its ponds are used by industry, chiefly for
hydroelectric power generation, and to some extent, by the public for
recreational purposes.
2.4.4.2 Industrial Use
The series of hydroelectric stations and their associated reservoirs on the
Connecticut River have been operated for many years to obtain maximum power
benefits for the power consumers of the New England region. This has required
operation of the river's hydroelectric stations as peak load facilities which
were shut down during the low load hours of each day and on weekends.
When river flow rates are less than 10,000 cfs, the Vernon Hydroelectric
Station is operated as a peak load facility. Often at such times, only one
hydroelectric unit is utilized during off-peak hours.
VYNPS's NPDES permit defines the maximum allowable thermal limits on the
Connecticut River.
Turners Falls Hydroelectric Project, FERC License No. 1889, is located
19.8 miles below Vernon Dam. This project, which utilizes water released from
the Vernon project, is owned and operated by the Western Massachusetts
Electric Company.
2.4.4.3 Public Use
Both Vernon Pond and Turners Falls Pond, next downstream, are used to some
extent for canoeing, boating, water skiing, and fishing. The utilization of
fishes resident in the Connecticut River has grown over the past few years.
Finfish have been studied in the Connecticut River in the area near VYNPS
since 1967. Fish were collected by various methods, including seining, gill
netting, minnow traps, fish traps (fyke nets), and electrofishing.
Table 2.4.10 lists, by scientific and common names, all of the species of
finfish taken through 1980 at Stations 2, 3, 4, and 5 on Figure 2.4-11. With
few exceptions, all specimens collected were identified, weighed, measured,
and released. Scale samples were taken from selected species for age-growth
studies. During the open cycle testing programs, similar data were collected
on all fish impinged on the traveling screens at the cooling water intake.
Fish data are presented in VYNPS's preoperational report (9), in subsequent
annual reports and in the reports of the open cycle testing programs.
A fish passage facility became operational at the Vernon Hydroelectric Station
in May 1981.
VYNPS DSAR Revision 1 2.0-47 of 108
There are no direct municipal water intakes downstream of the VYNPS site.
Northeast Utilities operates a 1,000,000 kW pumped storage hydroelectric
generating plant at Northfield and Erving, Massachusetts. This plant obtains
water from the Connecticut River at a point 14 miles downstream from the
Vermont Hydroelectric Station and pumps the water to an upper reservoir.
During hours of peak electrical demand, this water is allowed to return to the
river through the reversible turbine pump units to provide peaking electrical
generating capacity.
The Metropolitan District Commission of Massachusetts has investigated the
feasibility of taking water from the Northfield Mountain Reservoir and
diverting it through a penstock and canal system to the Quabbin Reservoir,
approximately 10 miles distant. This reservoir supplies water to Metropolitan
Boston, Clinton, Marlboro, Southboro, Worcester, and other communities in
Massachusetts. No action has been taken on this proposal to date.
2.4.5 Biology
The location of VYNPS biological monitoring stations in the Connecticut River
are depicted in Figure 2.4-11. The approximate location of the eight
monitoring stations in river miles north and south of Vernon Dam are shown
below:
Station No. Location Relative to Vernon Dam
1 6.45 miles south 2 4.70 miles south 3 0.65 miles south 4 0.55 miles north 5 1.25 miles north 6 4.10 miles north 7 4.25 miles north 8 8.70 miles north
NOTE: Only Stations 3 and 8 are monitored subsequent to the permanent
cessation of power operation. 2.4.5.1 Commercial Fisheries
There are no commercial fisheries in the Connecticut River in the Vernon Pool
area.
VYNPS DSAR Revision 1 2.0-48 of 108
2.4.5.2 Sport Fisheries
Thirty-three species of fishes have been found in the Connecticut River in the
vicinity of Vernon Dam. Some of the species, such as smallmouth bass and
yellow perch, are generally considered to be game fishes. Two anadromous
species, the Atlantic salmon and the American shad, have recently been
reintroduced into the Vernon area, as a direct result of the construction of
fish ladders at the Turners Falls and Vernon Dams. Successful passage of
these and other species have been recorded over the last few years. Other
species in the Connecticut River are either forage, coarse food, or "trash"
fish and are not generally sought by anglers. These species include the white
sucker and carp. Nearly all of the fish species present are warm-water
tolerant.
A 1980 survey shows that perch (both white and yellow), minnows, white sucker,
and bass are the most abundant fish species in the vicinity of the Vernon Dam
as seen in Table 2.4.11. These species comprised about 89% of the fish
population. The average weight of the smallmouth bass captured was
approximately 0.5 pounds, while the weight of the average sucker was nearly
1.5 pounds. Carp, white suckers, and minnows were shown to comprise
approximately 1/3 of the total number of all fishes caught, but accounted for
over 1/2 of the total weight.
2.4.5.3 Bottom Fauna
Monthly samples of Connecticut River benthic fauna were collected at
Stations 2, 3, 4, and 5 of Figure 2.4-11, from May through November with a
9-inch Ekman dredge and Henson traps (wire cages filled with 2 to 3-inch
diameter rocks). The following compares the number of samples and number of
genera of benthos collected by Ekman dredges over the years.
COMPARISON OF NUMBER OF SAMPLES AND NUMBER OF GENERA OF BENTHOS COLLECTED BY EKMAN DREDGE Station Number of Samples/Number of Genera Number 1969 1977 1978 1979 1980 2 6/33 8/20 8/22 7/27 7/36 3 6/24 8/25 8/13 7/26 7/39 4 7/16 8/19 8/17 7/26 7/30 5 8/18 8/20 6/14 7/28 7/25
VYNPS DSAR Revision 1 2.0-49 of 108
As has been found in earlier years, caddis fly and chironomid larvae were the
predominant organisms in most of the spring and summer samples. Fall samples
showed a greater variety of dominant forms - fingernail clams, planarians,
oligochaetes. Chironomids and caddis flies were again dominant in the
November Henson trap samples. The very low Station 2 and 3 diversity indices
in that sample set were attributable to large percentages of a single
chironomid species, Tanytarsus sp., which accounted for 90% of the Station 2
sample and 94% of the Station 3 sample. Large percentages of the chironomid,
Glyptotendipes sp., in all three Henson trap samples of July and the Station 5
sample of September are evidenced in the relatively low diversity indices of
those samples.
2.4.5.4 Aquatic Plants
Few species of aquatic plants are found in the waters of the Connecticut River
in the Vernon Pool area. Marshes adjacent to the river are, however, rich in
vegetation. Cattails are the predominate vascular plant found in these
wetlands; other abundant species are rushes, sedges, grasses, horsetails, and
sweetflag.
2.4.5.5 Conclusions
The waters of the Connecticut River in the Vernon Pool area support a variety
of aquatic organisms. The fishes found in these waters are predominantly
those generally referred to as "warm-water" species. The benthic fauna are
generally sparse due to the silty nature of the river bottom. Marshes
adjacent to the river are rich in aquatic vegetation. Safe storage and
handling of irradiated fuel and radwaste management at the VYNPS does not
adversely affect the ecology of the Vernon Pool adjacent to the site.
2.4.6 Chemical and Bacteriological Quality of Water
Water quality monitoring requirements are established by the current National
Pollutant Discharge Elimination System (NPDES) Permit.
The water above Vernon Dam, as determined by the Vermont Water Resources Board
(effective July 2, 2000), has been classified as Class B waters and can be
described as follows:
Class B: The designated uses of Class B waters include aquatic biota,
wildlife, aquatic habitat, aesthetics, public water supply, irrigation of
crops and other agricultural uses, swimming and other primary contact
recreation, boating, fishing and other recreational uses.
VYNPS DSAR Revision 1 2.0-50 of 108
2.4.7 River Field Program
Water quality parameters were monitored continuously from 1968 at Station 3,
downstream of VYNPS, and from 1970 at Station 7, upstream of the plant
(station locations are described in Section 2.4.5). In February 1980, the
requirement that conductivity and turbidity be monitored continuously was
deleted. The current ecological monitoring program is set forth in the NPDES
Permit which is issued every 5 years. Parameters to be monitored and
associated limits are ultimately established by the State of Vermont and may
be subject to revision within the course of each 5-year period. Data and
analysis from this monitoring program are presented in annual ecological
studies reports.
Biological studies, both qualitative and quantitative, are made to establish
the presence and amount of fish and benthic fauna. A comprehensive
environmental assessment is presented in Reference 11.
2.4.8 Conclusions
The station site nominal grade level is at elevation 252 feet Mean Sea Level
(MSL). The maximum river level that has occurred at the site was
elevation 231.4 feet MSL. The maximum Probable Maximum Flood Level at the
site is 252.5 feet MSL.
The PMF stillwater level is 6 inches above most yard electrical manholes. If
flood waters enter these manholes, potential flood pathways through conduits
which extend from the manholes into the Switchgear Room exist. This potential
water pathway through conduits is significantly reduced by the inclusion and
inspection of seals in conduits entering the Switchgear Room in addition to
measures in the flooding procedure which monitor and address any in-leakage.
Because the river is the natural low point and drainage channel for the
region, the groundwater table can be expected to slope toward the river.
Surface drainage also will flow toward the river. Thus, it is unlikely that
any liquids discharged to the river from the site would mix with domestic
water supplies in the area.
VYNPS DSAR Revision 1 2.0-51 of 108
The Federal Energy Regulatory Commission (FERC) requires, under Order No. 122,
issued January 21, 1981, that the dams and related structures of all Licensed
Projects be inspected once every five years by an independent consulting
engineer and that they be certified as safe in their construction and
operation. In the event unsafe conditions of any nature are found, under the
order they must be called to the attention of the owner and the FERC and
necessary corrective measures must be carried out. In response to an
exception request dated June 26, 1997, FERC issued an exemption from filing an
Independent Consultant's Safety Inspection Report pursuant to the above
regulation for the Vernon, VT and Bellows Falls, VT dams by FERC letter dated
August 6, 1997, on the basis that those projects are "low hazard potential"
facilities. The dam owner retains the responsibility to provide an emergency
action plan and an inspection by an independent consultant in the event the
upstream or downstream circumstances of either project change such that
failure of a project structure would present a hazard to the public. The dams
operated by the Corps of Engineers are also subject to periodic safety
inspections. It is believed that these actions will assure the safety of all
dams on the river.
VYNPS DSAR Revision 1 2.0-52 of 108
2.4.9 References
1. Probable Maximum Precipitation Susquehanna River Drainage above
Harrisburg, Pennsylvania, Hydrometeorological Report No. 40, U.S. Weather
Bureau, Washington, D.C., May 1965.
2. Seasonal Variation of the Probable Maximum Precipitation East of the
105th Meridian for Areas from 10 to 1,000 Square Miles and Durations of
6, 12, 24, and 48 hours, Hydrometeorological Report No. 33, U.S. Weather
Bureau, Washington, D.C., 1956.
3. Climatic Atlas of the United States, ESSA, U.S. Department of Commerce,
1968.
4. Flood Hydrograph Analysis and Computations, EM 1110-2-1405, U.S. Army
Corps of Engineers, 1959.
5. Chow, Ven Te, Open-Channel Hydraulics, Civil Engineering Series,
McGraw-Hill, 1959.
6. Technical Paper No. 55, Tropical Cyclones of the North Atlantic Ocean,
U.S. Department of Commerce, U.S. Weather Bureau, Washington, D.C., 1965.
7. Shore Protection, Planning and Design, Technical Report No. 4, Third
Edition, U.S. Army Coastal Engineering Research Center, Department of
Army, Corps of Engineers.
8. Computing Freeboard Allowances for Waves in Reservoirs, ETL No. 1210-2-8,
Department of Army, Corps of Engineers.
9. Webster-Martin, Incorporated, 1971. Ecological Studies of the
Connecticut River, Vernon, Vermont. Preoperational Report. Report
prepared for Vermont Yankee Nuclear Power Corporation.
10. U.S. Department of Commerce, 1978. "Tropical Cyclones of the North
Atlantic Ocean, 1871-1977," National Climatic Center, NOAA,
Asheville, N.C.
11. Aquatec, Incorporated, 1978. "316 Demonstration - Engineering,
Hydrological and Biological Information."
12. Aquatec, Incorporated, 1981. Ecological Studies of the Connecticut
River, Vernon, Vermont. Report X, January-December 1980. Report
prepared for Vermont Yankee Nuclear Power Corporation.
13. GZA GeoEnvironmental, Inc., 2011. Hydrogeologic Investigation of Tritium
in Groundwater, Vermont Yankee Nuclear Power Station Vernon, VT. Report
Prepared for Entergy Nuclear Operations, Vermont Yankee Nuclear Power
Station.
VYNPS DSAR Revision 1 2.0-53 of 108
TABLE 2.4.1
Average and Extreme Values of Stream Flow Connecticut River at Vernon, Vermont Water Years 1944 - 1988 Highest Lowest Lowest Average Average Average Average Monthly Monthly Monthly Weekly Flow Flow Flow Flow Cfs Cfs Cfs Cfs October 6,571 20,201 1,646 1,475 November 9,033 20,450 3,366 2,159 December 9,486 24,326 2,934 2,494 January 7,655 17,338 2,589 2,283 February 8,187 24,428 2,935 2,135 March 15,544 36,245 5,308 4,373 April 30,799 51,210 14,980 11,523 May 18,047 38,790 7,262 3,118 June 8,768 21,890 3,387 2,424 July 4,911 21,790 1,841 1,033 August 4,005 13,615 1,805 1,223 September 4,159 15,610 1,650 1,138 NOTES: 1. All flows reflect regulation of upstream reservoirs for power purposes. 2. Flows measured at Vernon for 1944 - 1973, flows generated for Vernon from
United States Geological Survey gages at N. Walpole, New Hampshire, and Turners Falls, Massachusetts for 1973 - 1988.
VYNPS DSAR Revision 1 2.0-54 of 108
TABLE 2.4.2 Vermont Yankee Nuclear Power Station, Daily Stream Flow for October 1964 to September 1965, Connecticut River at Vernon, Vermont Connecticut River Basin 1-1565. Connecticut River at Vernon, Vermont Location
Lat 4246'10", long 7230'50", on right bank just downstream from Vernon Dam at Vernon, Windham County, and 2 miles upstream from Ashuelot River. Drainage area 6,266 sq mi. Records available February to April 1936 (in WSP 798). September and October 1938 (in WSP 867), October 1944 to September 1965. Gage Water-stage recorder (digital). Datum of gage is at mean sea level, datum of 1929. Prior to January 20, 1948, at datum 94.13 ft higher. Average discharge 21 years (1944-65), 10,170 cfs (adjusted for storage). Extremes Maximum discharge during year, 32,000 cfs April 17 (gage height, 190.94 ft): minimum daily, 108 cfs September 6, 1936, 1938, 1944-65: Maximum discharge, 176,000 cfs March 19, 20, 1936 (gage height, 128.8 ft. datum then in use), from rating curve extended above 86,000 cfs: minimum daily, 99 cfs October 8, 1944. Remarks Records good except those below 1,000 cfs, which are fair. Flow regulated by powerplants and by First Connecticut and Second Connecticut Lakes, Lake Francis. Moore Reservoir and Comerford Station Pond (see Page 196), and other reservoirs (combined usable capacity, about 29 billion cubic feet).
VYNPS DSAR Revision 1
2.0-55 of 108
TABLE 2.4.2
(Continued) DISCHARGE IN CUBIC FEET PER SECOND. WATER YEAR OCTOBER 1964 TO SEPTEMBER 1965 DAY OCT. NOV. DEC. JAN. FEB. MAR. APR. MAY JUNE JULY AUG. SEPT. 1. 1,220 164 10,900 6,730 4,500 7,000 *4,700 15,000 4,560 2,950 125 5,790 2. 1,900 3,070 5,580 5,450 3,500 6,600 4,390 13,600 7,620 2,830 1,710 8,810 3. 167 3,140 4,610 1,180 3,300 7,000 3,290 13,500 4,530 128 1,780 11,100 4. 157 3,050 6,740 4,890 3,400 7,400 826 13,000 *4,370 125 1,320 2,790 5. 3,270 2,210 1,760 7,300 4,900 8,000 4,970 12,300 1,100 125 1,900 134 6. 3,420 2,890 196 6,950 1,100 8,700 7,410 11,900 125 4,120 1,320 108 7. 3,720 725 4,150 6,420 1,000 9,800 8,910 10,200 4,650 2,650 296 3,760 8. 2,550 167 3,840 5,560 7,600 12,500 7,830 9,710 4,790 3,070 128 4,220 9. 2,620 3,400 4,190 5,250 6,800 13,000 10,200 4,630 5,600 3,270 2,640 2,860 10. 167 3,570 3,840 2,850 7,600 13,700 9,650 8,560 5,110 917 3,460 3,470 11. 160 811 3,990 6,770 8,400 13,800 11,900 9,660 4,890 567 3,460 2,210 12. 157 3,820 2,060 *6,760 9,000 12,800 14,300 10,400 1,060 2,290 2,390 628 13. 2,800 3,580 194 7,010 7,800 11,500 24,800 10,700 2,440 1,910 1,920 5,740 14. 2,850 2,920 4,340 6,960 7,400 9,650 23,600 8,840 10,800 2,390 125 6,540 15. 2,900 654 5,100 7,000 6,000 7,670 21,300 4,130 6,310 2,770 125 3,680 16. 2,200 4,990 5,330 2,800 6,300 9,260 24,100 2,400 7,400 2,720 3,900 2,270 17. 759 4,750 5,100 131 6,000 6,870 29,900 7,400 5,310 128 3,020 1,780 18. 737 4,750 5,630 4,300 6,500 7,500 25,400 8,730 5,300 125 4,690 125 19. 2,720 4,790 1,500 4,000 7,000 7,990 20,800 7,870 880 4,030 3,580 125 20. 3,550 5,250 174 3,700 3,500 7,250 19,400 7,050 2,550 3,810 3,080 1,940 21. 5,320 1,080 6,870 3,000 1,750 894 19,400 6,870 4,960 3,670 125 2,530 22. 3,580 167 5,120 3,800 5,000 7,320 *21,000 1,060 5,180 2,300 125 2,850 23. 5,470 5,260 6,980 2,000 5,900 6,610 24,400 134 5,450 2,530 2,280 3,050 24. 174 4,050 3,650 1,500 5,900 6,960 23,600 5,300 5,730 128 1,100 2,900 25. 167 4,460 3,660 4,600 7,000 6,440 19,100 4,910 4,450 125 1,430 9,360 26. 3,440 5,030 7,990 5,000 6,600 6,500 14,000 5,610 1,660 2,200 1,760 5,010 27. 3,620 8,580 15,500 4,100 1,850 3,920 15,400 5,960 759 1,730 1,740 7,960 28. 4,140 11,900 20,000 4,200 800 872 16,800 4,320 5,410 1,450 973 8,410 29. *3,870 12,100 17,400 4,500 ------ 6,770 16,300 1,120 4,940 859 885 7,040 30. 3,970 8,670 13,900 2,100 ------ 6,190 16,700 128 3,740 1,010 2,150 6,960 31. 969 ------ 12,400 600 ------ 5,530 ------ 125 ------ 131 2,420 ------ TOTAL 72,744 119,998 192,694 137,411 146,400 245,996 464,446 225,117 131,674 57,058 55,957 124,150 MEAN 2,347 4,000 6,216 4,433 5,229 7,935 15,480 7,262 4,389 1,841 1,805 4,138 MEAN** 1,942 4,335 6,040 3,867 3,834 6,385 16,490 8,924 4,518 1,809 2,174 4,383 CFSM** .310 .692 .964 .617 .612 1.02 2.63 1.42 .721 .289 .347 .699 IN** .36 .77 1.11 .71 .64 1.17 2.94 1.64 .80 .33 .40 .78 CALENDAR YEAR 1964 MAX 63,200 MIN 143 MEAN 7,840 MEAN** 7,822 CFSM** 1.25 IN 17.00 WATER YEAR 1964-65 MAX 29,900 MIN 108 MEAN 5,407 MEAN** 5,382 CFSM** .859 IN 11.65 Peak discharge (base, 50,000 cfs). - No peak above base. Note: Stage-discharge relation affected by ice January 15, 16, January 18 to March 9.
3* Discharge measurement made on this day. ** Adjusted for change in contents in all reservoirs from First Connecticut and Second Connecticut Lakes to reservoirs in West River basin listed on Page 196.
VYNPS DSAR Revision 1 2.0-56 of 108
TABLE 2.4.3 Municipal and Industrial Groundwater Usage Within a 10-Mile Radius of the Vernon Site Minimum and Minimum and Static Number Maximum Depth Maximum Yield Level Town of Wells Feet GPM Feet Brattleboro, VT 49 10-540 1-40 9-35 Guilford, VT 30 50-540 1-50 8-41 Halifax, VT 12 34-345 1-30 8-10 Vernon, VT 14 36-565 1-75 25-115 Chesterfield, NH 26 41-470 0.2-25 12-50 Hinsdale, NH 5 72-280 3-30 -30 Winchester, NH 3 155-473 1.5-20 - Bernardston, MA 3 29-145 0.5-20 - Gill, MA 15 40-345 0.5-15 10-20 Leyden, MA 4 95-208 3-100 - Northfield, MA 19 52-345 0.3-40 14-85 Warwick, MA 5 52-372 1-9 - This information was obtained from records of the Green Mountain Well Company, Putney, Vermont.
VYNPS DSAR Revision 1 2.0-57 of 108
TABLE 2.4.4
Public Water Supplies Within a 10-Mile Radius of the Vernon Site Location Town on Map Source Treatment Capacity Brattleboro, VT A Lake and Reservoir Filtration 3 MGD Plant Brattleboro B 3 Gravel-Packed Wells Filtration 970 GPM Supplementary 30 feet deep Plant 465 GPM 800 GPM Hinsdale, NH C-1 2 Gravel-Packed Wells Chlorine 220 GPM 74 feet and Sodium Phosphate 68 feet deep Sodium Hydroxide C-2 2 Gravel-Packed Wells Chlorine 500 GPM 47 feet and Sodium Phosphate 64 feet deep Sodium Hydroxide Winchester, NH D 3 Gravel-Packed Wells Phosphate 0.6 MGD Approx. 60 feet deep Northfield, MA No. 1 E 1 Gravel-Packed Well Sodium Hydroxide 100 GPM
No. 2 F Reservoir Chlorine 0.1 MGD Bernardston, MA G 2 Gravel-Packed Wells Potassium Hydroxide 480 GPM 69 feet and 74 feet 250 GPM deep G Sand and Gravel Well Chlorine 0.07 MGD 24 feet deep Sodium Hydroxide From 1963 Inventory of Municipal Water Facilities, U.S. Department of HEW, updated by local municipal water departments/town offices (2000).
VYNPS DSAR Revision 1 2.0-58 of 108
TABLE 2.4.5 Water Supplies Within a 1-Mile Radius of the Site HINSDALE, NEW HAMPSHIRE Ground Feet Yield Elevation (ft) No. Depth GPM U.S.G.S. Use 1. 200 5 300 Domestic 2. 72 30 280 Domestic VERNON, VERMONT 1 198 15 295 Domestic 2 189 5.5 295 Domestic 3 368 11.5 275 School 4 356 25 208 Domestic & Homes 5 Spring Fed Supply Miller Farm Spring 6 125 30 320 Domestic 7 288 3.75 360 Domestic 8 19 275 Domestic & Farm 8A 18 Now Dry 275 9 17 3-4 275 Domestic 9A 25 Now Dry 275 Domestic 10 20 - 275 Domestic & Farm 10A 18 275 Domestic 11 30.5 4-5 275 Domestic 12 18 6 275 Domestic 13 16 275 Domestic 14 16 275 Domestic 15 14 275 Domestic 16 275 17 Spring 275 18 28 275 Domestic 19 20 15 275 Domestic 20 Spring 275 21 23 10 270 Domestic 22 19 270 Domestic 23 Spring 270 24 Spring 270 25 Spring 270 26 Spring 240 27 Spring 240 28 Spring 220 29 Spring 230 30 Going to 240 Drill 31 17 10 240 Domestic 32 20 240 Domestic 33 165 4 270 Domestic 34 70 20 270 Domestic 35 20 270 Domestic 36 31 270 Domestic & Farm 37 235 16.5 270 Domestic 38 23 275 Domestic 39 12 270 Domestic 40 18 270 Domestic 41 30 280 Domestic 42 20 280 Domestic 43 24 6 280 Domestic 44 35 Dry 280
VYNPS DSAR Revision 1 2.0-59 of 108
Table 2.4.5 (Continued) Water Supplies Within a 1-Mile Radius of the Site Ground Feet Yield Elevation (ft) No. Depth GPM U.S.G.S. Use 45 275 Domestic 46 270 47 24 270 Domestic 48 23 275 Domestic 49 24 275 Domestic 50 22 275 Domestic 51 23 275 Domestic 52 20 275 Grange & Domestic 53 175 6 270 Domestic 54 18 270
VYNPS DSAR Revision 1 2.0-60 of 108
TABLE 2.4.6 Six-Hour PMP and Runoff Increments Connecticut River Basin Above Vernon, Vermont Basin Arranged Shape Cumulative Incremental in PMP Time PMS Red. PMP PMP Critical Losses Runoff (hrs) (ins) Factor (ins) (ins) Order .05"/hr (ins) 6 6.1 .95 5.8 5.8 0.3 0.3 0.0 12 8.3 .95 7.9 2.1 0.7 0.3 0.4 18 9.7 .95 9.2 1.3 0.7 0.3 0.4 24 10.7 .95 10.2 1.0 0.9 0.3 0.6 30 11.7 .95 11.1 0.9 1.0 0.3 0.7 36 12.4 .95 11.8 0.7 2.1 0.3 1.8 42 13.2 .95 12.5 0.7 5.8 0.3 5.5 48 13.5 .95 12.8 0.3 1.3 0.3 1.0 54 13.8 .95 13.1 0.3 0.3 0.3 0.0 60 14.0 .95 13.3 0.2 0.2 0.3 0.0 66 14.2 .95 13.5 0.2 0.2 0.3 0.0 72 14.4 .95 13.7 0.2 0.2 0.3 0.0 TOTAL = 13.7 TOTAL = 10.4
VYNPS DSAR Revision 1 2.0-61 of 108
TABLE 2.4.7 Maximum Annual Floods on Connecticut River at Vernon, Vermont Arranged in Descending Order (1927, 1936, 1938, 1945-1973) Year Peak Discharge, CFS Stage, Ft MSL 1936 176,000 222.9 1927 155,000 220.5 1938 132,500 214.8 1960 107,000 209.6 1973 102,000 - 1948 101,000 208.5 1953 98,800 208.0 1949 88,600 205.4 1968 88,100 205.3 1952 86,600 204.9 1958 84,200 204.3 1951 81,200 203.6 1969 81,200 203.5 1959 80,600 203.4 1947 79,600 203.3 1956 79,600 203.1 1972 78,600 201.7 1962 73,900 201.7 1955 70,500 200.9 1945 69,700 200.8 1950 68,300 200.3 1967 66,800 200.0 1964 66,100 199.8 1971 65,500 199.6 1954 65,000 199.5 1970 63,400 199.1 1946 62,700 198.8 1963 61,600 198.6 1961 57,900 197.7 1966 46,700 194.8 1965 32,000 190.9 1957 30,000 190.1
VYNPS DSAR Revision 1 2.0-62 of 108
TABLE 2.4.8 Time-Varying PMF Stage-Discharge Table Vermont Yankee Nuclear Plant Site Time Discharge Stage Time Discharge Stage (hrs) (cfs) (ft MSL) (hrs) (cfs) (ft MSL) 0 58,800 221.3 156 247,000 237.0 6 58,800 221.3 162 231,000 235.8 12 58,900 221.4 168 217,000 234.7 18 59,000 221.5 174 205,300 233.8 24 59,300 221.5 180 192,300 233.0 30 59,800 221.6 186 182,000 232.1 36 60,800 221.8 192 172,000 231.4 42 66,300 222.0 198 162,400 230.7 48 78,300 223.4 204 154,000 230.1 54 95,200 225.0 210 146,000 229.4 60 117,500 227.2 216 139,400 229.0 66 158,200 230.4 222 133,000 228.5 72 255,000 237.5 228 128,400 228.1 78 367,000 245.7 234 122,000 227.5 84 417,000 248.8 240 117,300 227.2 90 464,000 251.5 246 112,000 226.6 96 506,400 253.9 252 107,500 226.2 102 465,000 251.6 258 104,000 226.0 108 430,000 249.5 264 100,000 225.5 114 403,000 248.0 270 97,000 225.2 120 380,000 246.5 276 93,700 225.0 126 351,000 244.8 282 91,400 224.7 132 321,000 242.7 288 88,500 224.5 138 294,000 240.8 294 86,000 224.2 144 283,000 239.6 300 83,700 224.0 150 265,000 238.3
VYNPS DSAR Revision 1 2.0-63 of 108
TABLE 2.4.9 Time-Varying Modified PMF Stage-Discharge Table Vermont Yankee Nuclear Plant Site Time Discharge Stage Time Discharge Stage (hrs) (cfs) (ft MSL) (hrs) (cfs) (ft MSL) 0 58,800 221.3 156 235,100 236.1 6 58,800 221.3 162 220,600 235.0 12 58,900 221.4 168 207,400 234.1 18 59,000 221.5 174 196,500 233.2 24 59,200 221.5 180 184,200 232.4 30 59,600 221.6 186 174,300 231.5 36 60,500 221.9 192 164,900 230.9 42 65,900 222.3 198 156,000 230.3 48 74,100 223.0 204 148,200 229.6 54 87,900 224.4 210 140,600 229.1 60 106,400 226.3 216 134,500 228.6 66 142,300 229.2 222 128,200 228.1 72 235,000 236.1 228 122,300 227.5 78 343,800 244.1 234 118,100 227.2 84 390,700 247.2 240 113,800 226.8 90 437,700 250.0 246 108,800 226.4 96 480,100 252.5 252 104,500 226.0 102 439,700 250.1 258 101,200 225.6 108 407,300 248.2 264 97,700 225.3 114 381,900 246.8 270 94,500 225.0 120 360,500 245.5 276 91,500 224.6 126 333,500 243.5 282 89,460 224.4 132 305,100 241.4 288 86,630 224.2 138 283,900 239.6 294 84,280 224.0 144 269,000 238.5 300 82,140 223.9 150 252,900 237.4
VYNPS DSAR Revision 1 2.0-64 of 108
TABLE 2.4.10 Checklist of Connecticut River Fishes Found Near Vernon, Vermont* Salmonidae - Trouts Salmo salar Linnaeus Atlantic Salmon Salmo trutta Linnaeus Brown Trout Salmo gairdneri Richardson Rainbow Trout Salvelinus fontinalis (Mitchill) Brook Trout Osmeridae - Smelts Osmerus mordax (Mitchill) Rainbow Smelt Catostomidae - Suckers Catostomus commersoni (Lacepede) White Sucker Catostomus catostomus (Forster) Longnose Sucker Cyprinidae - Minnows and Carps Cyprinus carpio Linnaeus Carp Semotilus corporalis (Mitchill) Fallfish Semotilus atromaculatus (Mitchill) Creek Chub Couesius plumbeus (Agassiz) Lake Chub Notemigonus crysoleucas (Mitchill) Golden Shiner Notropis cornutus (Mitchill) Common Shiner Notropis hudsonius (Clinton) Spottail Shiner Hybognathus nuchalis Agassiz Silvery Minnow Ictaluridae - Freshwater Catfishes Ictalurus nebulosus (LeSueur) Brown Bullhead Ictalurus natalis (LeSueur) Yellow Bullhead Esocidae - Pikes Esox lucius Linnaeus Northern Pike Esox niger LeSueur Chain Pickerel Anguillidae - Freshwater Eels Anguilla rostrata (LeSueur) American Eel Cyprinodontidae - Killifishes Fundulus diaphanus (LeSueur) Banded Killifish Percichthyidae - Temperate Basses Morone americana (Gmelin) White Perch
* Common names used in this checklist are those proposed by Bailey, Reeve M., et
al., 1970. "A List of Common Scientific Names of Fishes from the United States and Canada." Special Publication No. 6, American Fisheries Society, Washington.
VYNPS DSAR Revision 1 2.0-65 of 108
TABLE 2.4.11 Fishes of the Connecticut River in the Vicinity of Vernon, Vermont All Collections - 1980 Total Total Weight Length Number Weight Extremes Extremes in Species Captured In Grams In Grams Millimeters Catostomus commersoni (Lacepede) White Sucker 190 129,514 0.5-1408 33-507 Cyprinus carpio Linnaeus Carp 19 91,765 138-8500 195-740 Semotilus corporalis (Mitchill) Fallfish 1 473 473 332 Notemigonus crysoleucas (Mitchill) Golden Shiner 12 913 35-170 137-225 Notropis hudsonius (Clinton) Spottail Shiner 195 2,062 7-15 73-128 Hybognathus nuchalis Agassiz Silvery Minnow 1 16 16 112 Juvenile Cyprinidae 133 208 0.05-2.6 17-68 Ictalurus nebulosus (LeSueur) Brown Bullhead 20 6,500 32-733 140-375 Ictalurus natalis (LeSueur) Yellow Bullhead 1 76 76 180 Esox lucius Linnaeus Northern Pike 1 400 400 400 Esox niger LeSueur Chain Pickerel 12 5,818 162-846 282-508 Anguilla rostrata (LeSueur) American Eel 1 1,360 1,360 750 Morone americana (Gmelin) White Perch 494 58,551 4-410 64-308 Perca flavescens (Mitchill) Yellow Perch 229 25,338 7-350 90-290 Stizostedion vitreum (Mitchill) Walleye 48 30,522 51-1156 185-490 Micropterus dolomieui Lacepede Smallmouth Bass 70 16,693 4-1470 70-490 Micropterus salmoides (Lacepede) Largemouth Bass 8 3,457 23-2040 110-507 Lepomis gibbosus (Linnaeus) Pumpkinseed 48 4,490 2.7-843 57-420 Lepomis macrochirus Rafinesque Bluegill 16 3,585 3-383 56-240 Ambloplites rupestris (Rafinesque) Rock Bass 103 13,246 2.1-302 51-250 TOTALS 1602 394,987 Source: See Reference 12.
VYNPS DSAR Revision 1 2.0-66 of 108
Vermont Yankee
Defueled Safety Analysis Report
Station Site – Area Public Water Supplies 10 Mile Radius
Figure 2.4-1
VYNPS DSAR Revision 1 2.0-67 of 108
Vermont Yankee
Defueled Safety Analysis Report
Station Site – Area Private Water Supplies
1 Mile Radius
Figure 2.4-2
VYNPS DSAR Revision 1 2.0-68 of 108
Vermont Yankee
Defueled Safety Analysis Report
Enveloping Depth-Duration-Area ValuesOf PMP for Susquehanna River Basin
Figure 2.4-3
VYNPS DSAR Revision 1 2.0-69 of 108
Vermont Yankee
Defueled Safety Analysis Report
6-Hour Unit Hydrograph
Figure 2.4-4
VYNPS DSAR Revision 1 2.0-70 of 108
Vermont Yankee
Defueled Safety Analysis Report
Total SPF Hydrograph Figure 2.4-5
VYNPS DSAR Revision 1 2.0-71 of 108
Vermont Yankee
Defueled Safety Analysis Report
Total PMF Hydrograph (Natural and Modified)
Figure 2.4-6
VYNPS DSAR Revision 1 2.0-72 of 108
Vermont Yankee
Defueled Safety Analysis Report
Vermont Yankee Nuclear Plant
Location of River Cross-Sections Figure 2.4-8
VYNPS DSAR Revision 1 2.0-73 of 108
Vermont Yankee
Defueled Safety Analysis Report
Stage Discharge Curve at The Vermont Yankee Nuclear Plant
Figure 2.4-9
VYNPS DSAR Revision 1 2.0-74 of 108
Vermont Yankee
Defueled Safety Analysis Report
Cross Section of the Critical Fetch
Figure 2.4-10
VYNPS DSAR Revision 1 2.0-75 of 108
Vermont Yankee
Defueled Safety Analysis Report
Vermont Yankee Sample StationsConn. River
Figure 2.4-11
VYNPS DSAR Revision 1 2.0-76 of 108
2.5 GEOLOGY AND SEISMOLOGY
HISTORICAL INFORMATION BELOW NOT REQUIRED TO BE REVISED.
2.5.1 General
This subsection provides information related to geological and seismological
considerations at the site. Detailed site and laboratory investigations were
undertaken by independent consulting firms to obtain necessary design data
contained in this section. The consulting firms were Goldberg-Zoino and
Associates, Cambridge, Massachusetts, and Weston Geophysical Research, Inc., in
conjunction with the Vermont Yankee Nuclear Power Corporation and Ebasco Services
Incorporated. Evaluations of the investigations indicate that the proposed site
was adequate from the geological and seismological viewpoints and could safely
support the nuclear station installation.
2.5.2 Geology
The site is located on the west bank of the Connecticut River in the town of
Vernon, Vermont, which is in Windham County. Site coordinates are approximately
42 47' north latitude and 72 31' west longitude, in the extreme southeastern
corner of the state of Vermont.
2.5.2.1 Introduction
All but one of the major structures of the facility, including the reactor
building and turbine building, are supported on rock. The storage pad for the
Independent Spent Fuel Storage Installation (ISFSI) is supported on engineered
fill placed on existing soils. Sixteen of the 93 borings at the site were made in
the immediate vicinity of the reactor building (see Figure 2.5-2). These borings
show that the area is overlaid by glacial deposits from the Pleistocene Age, with
an average 30 feet of glacial overburden above the local bedrock, which consists
of hard biotite gneiss. Rock outcroppings near the site are found along the river
bank. Bedrock exists at or near the foundation grades for the structures, namely
elevation 206 feet MSL for the reactor building, elevation 217 feet MSL for the
turbine building, elevation 227 feet MSL for the radwaste building, and elevation
187 feet MSL for the circulating water intake structure.
2.5.2.2 Geological Investigation Program
Standard geologic procedures were employed during the site investigation,
beginning with a complete search of available literature concerning geology and
seismic activity in the area including unpublished and published material (refer
to Table 2.5.1). A complete geologic field reconnaissance of the general area and
the immediate site was performed, employing United States Geodetic Survey
topographic maps, aerial photographs, and the state of Vermont geologic and
tectonic maps.
VYNPS DSAR Revision 1 2.0-77 of 108
An extensive subsurface exploration project was undertaken at the site.
Ninety-three borings were made, 35 of which were from 32 to 100 feet in depth.
Thirty of these borings were AX (1-3/8 in. cores) and 5 were NX (2-1/8 in.
cores)(see Figure 2.5-2). All NX-size holes were logged in detail (see NX core
logs in Figure 2.5-3). The other cores were examined carefully to determine
general features and characteristics. Representative cores were taken at and
immediately below foundation grade in all NX core holes, and were submitted to
intense laboratory testing for determination of specific physical properties of
bedrock at the site. Several petrographic sections were made and analyzed to
ascertain the mineral composition and structure of bedrock.
A thorough seismic survey program was carried out to determine several of the
in-place physical properties of the site bedrock as it relates to earthquake
criteria for design of structures - such as compressional wave velocities (Vc),
shear wave velocities (Vs), subsurface rock contours, and the possibility of
extensive faulting and jointing.
The results of this investigation program are summarized in the following
paragraphs.
2.5.2.3 Regional Geology
Geologic structure of the region is complex, in that there are several sequences
of anticlinoria and synclinoria trending essentially in a northerly direction (see
Figures 2.5-4 and 2.5-5). The site is located geologically within the so-called
Brattleboro syncline, which is part of the Connecticut Valley-Gaspe Synclinorium.
Most of the region is underlain by Paleozoic metamorphic rocks and by a narrow
band of Triassic sedimentary rocks south of the site. The general outcrop pattern
of local Paleozoic formations indicates the presence of a major recumbent fold,
overturned to the west. The entire region has undergone extensive metamorphism
(mostly of the regional type) which apparently ranges from low-grade west of the
Vernon area to relatively high-grade east of the Vernon area.
Foliated igneous rocks of middle- and late-Devonian age underlie a large portion
of the region. These include three fairly large plutons of the Oliverian Magma
Series (Billings, 1935; Skehan, 1961), one of which is below the site, in the
towns of Vernon, Vermont and Hinsdale, New Hampshire - the Vernon Dome.
VYNPS DSAR Revision 1 2.0-78 of 108
2.5.2.3.1 Regional and Local Stratigraphy
The Vernon pluton is a narrow elongate mass approximately 8 miles long and 2 miles
wide, striking approximately 10 degrees to the northwest and dipping steeply to
the east (see Figures 2.5-6 and 2.5-7). The Connecticut River flows southeasterly
across its central portion. Gneisses of the Oliverian Plutonic Series
(middle-Devonian) make up the pluton core (Billings, 1935)(see Figure 2.5-7).
Both the Vernon Dome and the Westmoreland Dome north of Brattleboro (see Figure
2.5-5), are part of the Bronson Hill Anticlinorium, a series of echelon gneissic
domes that extend northward into northern New Hampshire and southward into the
State of Connecticut. Except where the Connecticut River crosses the Vernon Dome,
the local topography reveals strikingly the distribution of the lithologic units.
2.5.2.3.2 Geological History
There appears to have been at least two distinct tectonic periods of folding after
formation of the Vernon Dome (late Paleozoic to pre-Triassic - over 70 million
years ago). Most normal faults on the flanks of the domes strike N30E. The two
faults at the northern terminus strike N10W. In all cases, the faults dip
steeply, and appear to be Triassic or younger in age. The Clough Quartzite and
the Littleton Formation have been intensely folded at the northern end of the
domal structure. Folds in the immediate area indicate differential movement with
reverse drag folds occurring along with recumbent structures (see Figure 2.5-4).
Faulting took place over 70 million years ago along the southeastern boundary of
the Vernon-Chesterfield area, particularly in the state of New Hampshire. The
Triassic Border Fault (see Figure 2.5-4) is the only fault structure of major
significance related to the site and there has been no apparent movement in it
during the last several million years. Rocks of the Oliverian Plutonic Series and
the mantle of a gneiss dome comprising the Ammonoosuc, Clough, and Littleton
Formations adjoin the fault on the east (Robinson, 1963). There has been relative
movement down on the west side of the fault. A crushed zone in gneiss on the east
side of the fault near Gill Station at the southern end of the Vernon area may be
associated with the fault (Bolk, 1956). The fault is exposed 4 miles south of the
Vernon-Chesterfield area where it dips steeply to the west (Keller and Brainard,
1940). It is difficult to match structures across the fault, and this prevents an
accurate estimate of throw on the fault. Recent movement along the fault is not
indicated. All minor faults in the region appear to be high-angle and Triassic or
younger in age.
VYNPS DSAR Revision 1 2.0-79 of 108
2.5.2.3.3 Regional Structure
The three main structural features at the site are a relatively large, heavily
mantled gneissic dome, a major recumbent fold (Bernardson Nappe), and the eastern
margin of a regional syncline (Brattleboro Syncline).
The Bernardson Nappe apparently first formed during the main sequence of
deformation. No minor folds or lineations can be ascribed specifically to
movements that produced the nappe. The tectonic transport direction of the nappe
was generally from east to west. Formation of the gneissic domes followed
emplacement of the nappe and produced an early set of minor folds and lineations
on the mantle of the domes and on the rocks of the nappe (Trask, 1964). Early
folds at the north end of the Vernon Dome are overturned to the northeast and
northwest, with an apparent reverse drag. These early folds and lineations were
deformed then by still later folding in the synclinal area between the two domes.
Local isograds are essentially parallel to the regional structural trend. The
development of slip-cleavage in the Brattleboro Syncline, adjacent to the Vernon
Dome, was accompanied by extensive retrograde metamorphism (Moore, 1949).
Rocks of the Oliverian Plutonic Series, intrusive into the surrounding metamorphic
rocks, form the cores of elongate domes uplifts (Billings, 1935). The Vernon Dome
represents a southern counterpart of the Oliverian Magma Series. Foliation is
well developed around the margins of the Vernon pluton, but decreases slightly
toward its central portion. According to Moore (1949) and Skehan (1961), the
foliation is essentially parallel to the contact between the gneiss and the
overlying Ammonoosuc Volcanics. Available data (Moore, 1949), indicate that the
contact between the gneiss and the overlying Ammonoosuc Volcanics is concordant.
2.5.2.4 Site Geology
2.5.2.4.1 Physiography
The Connecticut River traverses the area near the site from north to south, along
the eastern side of the Vernon, Vermont area, geographically separating the states
of Vermont and New Hampshire at this point.
A strip of lowlands and terraces, about 1 mile in width, borders the river in the
area. There are naturally dissected uplands with an average local relief of
several hundred feet east and west of the lowlands. Wantastiguet Mountain, 0.5
mile east of Brattleboro, is the highest point in the area with an elevation of
1351 feet MSL. The lowest point is on the Connecticut River near Northfield,
Massachusetts, with an elevation of 175 feet MSL.
VYNPS DSAR Revision 1 2.0-80 of 108
Rock composition of Vernon pluton is essentially a gneiss, grading from a
granodiorite (quartz-diorite) to granite. It is essentially light-gray to
pink-gray, slightly to moderately foliated, medium-grained, subporphyritic
quartz-diorite with hypidiomorphic to granoblastic texture. As tabulated in Table
2.5.2, the gneiss contains plagioclase feldspar (An12 to An44), quartz and biotite
mica, as essential minerals. Epidote, muscovite mica, K-feldspar, hornblende,
garnet, and magnetite are included as accessory minerals. Sericite, some
chlorite, and calcite are present also, as alteration products. Granulated and
flattened "quartz eyes" are present, and individual grains of these aggregates
show sutured and mortar textures. The quartz eyes and strings of biotite flakes
produce prominent lineation. As much as 1% zircon has been found in rocks of the
central region of the Vernon Dome.
An extensive subsurface exploration project was undertaken at the site. The
drilling program was carried out by the Raymond Concrete Pile Company during the
fall of 1966. Subsurface profiles of the borings in the vicinity of the station
structures are illustrated in Figures 2.5-8, 2.5-9, 2.5-10 and 2.5-11. Detailed
logs of deep borings in the reactor building area are provided in Figure 2.5-3.
During formation of the metamorphic plutonic body, various joints and minor
slippages occurred. Many of these joints served as avenues for solutions to
travel with subsequent mineralized fillings. Visual examination of rock cores
indicates that many joints were filled by hydrothermal solutions. A few joint
surfaces have a drusy appearance, some with crystal growth, and others with
mineral stainings left by ground water. Some fractures of joint surfaces appeared
weathered to highly weathered.
Pegmatitic quartzite veins were encountered in borings 1 at elevation 198 feet
MSL, 4 at elevation 208 feet MSL, and 5 at elevation 169 feet MSL. The
approximate strike of this vein is N60E and it dips 40NW. Apparent thickness of
this vein is 1-1/2 feet. Pegmatitic veins were encountered also in borings 6 and
21.
Dike or sill-like bodies of a dark green, fine grain diorite were found in boring
6 at elevation 194.5 feet MSL and elevation 191.7 feet MSL. They were found also
in boring 2A at elevation 210.1 feet MSL. Both units are approximately 5 inches
thick. Hard milky quartzite bands or veinlets with accessory magnetite were found
in many of the borings at various depths. Geologic relationships of these bands
have not been made, but it may be determined that they belong to a particular
joint set.
The rock is extensively jointed. Three or more joint sets may be present. These
joint sets appear reasonably tight.
VYNPS DSAR Revision 1 2.0-81 of 108
2.5.2.4.2 Bedrock
Bedrock, although extremely hard and structurally competent, appears to be
fractured sufficiently to present occasional hydrostatic conditions in zones of
fracturing, as was observed in several of the drill holes. Water pressure tests
at the site were conducted to determine the "tightness" or permeability of certain
fractured zones. Tests proved that the formation is very tight.
2.5.2.4.3 Surficial Deposits
Rock types at the site are considered to be a metamorphosed igneous intrusive of
the Oliverian Plutonic Series. Generally, the rock is a quartzofeld
spathic-biotite gneiss, with variable amounts of orthoclase and plagioclase
feldspar. The attitude of this gneissic plutonic body is considered to trend
slightly west of north and dip to the east near the site.
At the site, the exposed outcrops along the edge of the river are massive, in some
instances intensively jointed due to mechanical weathering, and without any
visible gneissic structure. Foliation and lineation of the rock has been obscured
due to surface weathering. Rock cores reveal the gneissic structure. Foliation
is fairly well developed. The attitude of the rocks can be determined from the
cores by noting dip of foliation planes.
The gneiss is medium-grained, light-gray to slightly pinkish-gray rock, and its
texture somewhat approaches granoblastic. It is slightly subporphyritic and
rarely has a flaser fabric. Grains of white to gray glassy quartz, white to pink
feldspar, black biotite, with some muscovite and amphibole can be recognized.
Feldspar is quite variable. Minor constituents noted in the rock types are
magnetite, garnet, and possibly zircon and sphene.
2.5.2.5 River Geology
2.5.2.5.1 General
The Connecticut River at site lies within the New England upland. The basin is
maturely dissected with the river flowing throughout most of its course in an open
valley with well-developed flood plains above which rise glacial terraces tiered
on the valley walls. The main river in the upland section winds between rounded,
irregular hills and ridges.
VYNPS DSAR Revision 1 2.0-82 of 108
The topography of the entire basin has been modified by glaciation which scraped
the tops from the bedrock hills and filled the valleys with glacial detritus with,
however, little actual diversion of drainage. The major effect of the glacial
fill was to raise the streams from their old beds, thereby permitting the
development of present channels which may or may not be related to the underlying
configuration of the old valleys in the bedrock.
2.5.2.5.2 Seismic Survey
The seismic tests resulted in conclusions as follows:
1. Seismic velocity measurements in boreholes and from surface studies are high
and indicate hard massive bedrock. Deeply weathered zones or faults were not
detected.
2. Bedrock surface is slightly irregular as evidenced by the borings and the
lines of seismic refraction investigations.
3. Elastic moduli values, based on seismic velocities, are high values of
approximately 4.16 x 106 lb/in2 for Young's Modulus and 1.53 x 106 lb/in2 for
the shear or rigidity modulus. Poisson's ratio is 0.347.
4. Compressional wave velocity was found to be 13,800 fps and the shear wave
velocity 6,500 fps.
2.5.2.5.3 Shoreline Retreat
The presence of natural outcrops of the bedrock at the various dam-sites such as
Vernon, Turners Falls, and Bellows Falls, coupled with the construction of dams at
these sites, have restricted the river's velocity and concentrated its potential
erosion at the sites themselves. The river banks, as a result, are relatively
stable, with erosion, if any, manifest only as a result of major floods. The long
intervening periods of placid flows provide ample opportunity for inspection and
stabilization of the river banks, should this be required.
At the site, the natural river banks have become well stabilized during the
60-year existence of the Vernon Hydroelectic Project immediately downstream.
There is little evidence of bank erosion.
VYNPS DSAR Revision 1 2.0-83 of 108
2.5.3 Seismology
2.5.3.1 Introduction
The evaluation of a nuclear power station site from a seismic standpoint is based
upon a combination of historical and instrumental data. Historical records before
1900 are somewhat misleading since observations are limited to population centers
and the untrained observer appears to sometimes exaggerate. Later historical
records, such as those of the early 1900's, appear to be more reliable.
Instrumentation for the detection of local earthquakes, which may or may not be
felt, has been operating in the New England area since the mid-1930's.
2.5.3.2 Seismic Investigation Program
The seismic evaluation of the station is a threefold study consisting of a review
of historical data from the New England area, an analysis of instrumental and
historical records for the Vernon area, and a study of earthquake intensity
attenuation with distance for northeastern United States.
2.5.3.3 Geologic and Tectonic Background
As described in detail in Subsection 2.5.2, "Geology", the southern parts of
Vermont and New Hampshire are composed of early Paleozoic sediments which have
been metamorphosed through intense folding. Some middle and late Paleozoic
igneous intrusives and extrusives are also present. The site itself is located on
the Vernon Dome, a middle Ordovician intrusive body of quartz-diorite gneiss. The
only post-Paleozoic tectonic feature present in the area is the eastern border
fault of the Triassic Basin of Massachusetts. The fault is present in extreme
southwestern New Hampshire where it strikes in a northeasterly direction passing
about 6 miles to the southwest of the station site. A tectonic map of the New
England area is shown in Figure 2.5-12.
2.5.3.4 Seismic History
Those earthquakes which have been strongly felt or have produced some damage in
the New England area are shown in Figure 2.5-13. Areas of some seismic activity
are noted in the vicinity of the following locations: Lake George, New York;
Concord, New Hampshire; Ossipee Mountains, New Hampshire; southeastern New
Hampshire and northeastern Massachusetts; and Haddam Connecticut. All of these
areas lie between 50 and 100 miles from the plant site and have experienced at
least one historical earthquake which has produced some minor damage (Modified
Mercalli Intensity VI or greater).
VYNPS DSAR Revision 1 2.0-84 of 108
The nearest of these areas to the site is the Concord, New Hampshire area, about
50 miles to the northeast of the site. The earthquake of November 23, 1884, of
Intensity VI on the Modified Mercalli Scale, is the largest to have occurred at
Concord. This earthquake was felt over an 8000-square mile area which did not
include the Vernon, Vermont area.
The largest earthquake to have originated in the vicinity of Lake George, New
York, occurred on April 20, 1931. The epicenter of this earthquake is about 75
miles northwest of the site. It was reported to have been felt at Bellows Falls,
Vermont; Greenfield, Massachusetts; and Hinsdale, New Hampshire. The intensity at
Vernon can be estimated at about IV on the Modified Mercalli Scale (see Figure
2.5-14).
Modified Mercalli isoseismal lines for the Ossippe, New Hampshire, earthquakes of
December 20 and 24, 1940, which were of epicentral Intensity VII, show that the
intensity at Vernon, Vermont, was about IV. The epicenter of these earthquakes
was about 95 miles northeast of the site. Although the isoseismal lines show an
intensity of IV, reports from various localities in the area show that intensities
range from III to VI. In Keene, New Hampshire, a great part of which is located
on alluvium, an intensity of VI was noted, although just outside the town in the
surrounding highlands, the intensity was IV. Brattleboro, Vermont, reported an
Intensity V; Bellows Falls, Vermont, reported an Intensity IV; and Hinsdale, New
Hampshire across the Connecticut River from Vernon, reported an Intensity of III.
The earthquake of October 5, 1817, whose epicenter was near Woburn, Massachusetts,
was listed as Modified Mercalli Intensity VII by the United States Coast and
Geodetic Survey. The only report of damage is that "walls were thrown down at
Woburn". Since no other reports concerning this earthquake could be found, it is
doubtful that this earthquake had any effect on a site located 70 miles to the
west-northwest of Woburn, Massachusetts.
The earthquakes of November 9, 1727, at Newburyport, Massachusetts, and May 18,
1791, at East Haddam, Connecticut, are both listed by the United States Coast and
Geodetic Survey as Intensity VIII (Modified Mercalli). Both earthquakes occurred
between 85 and 90 miles from the plant site. Historical evidence shows that these
earthquakes were felt over wide areas of the northeastern United States, probably
including the Vernon, Vermont area. Although there is evidence that these
earthquakes were less than Intensity VIII, attenuation of earthquake intensity
with distance would probably have reduced these (even if they were of intensity
VIII) to Intensity IV or V at the plant site.
VYNPS DSAR Revision 1 2.0-85 of 108
2.5.3.5 Seismicity of Area
A more detailed picture of the seismicity of the central New England area
surrounding Vernon, Vermont, is shown in Figure 2.5-15. This figure shows the
approximate epicentral location of all the earthquakes of record.
The nearest earthquake to Vernon, Vermont, for which instrumental records were
obtained, took place on June 1, 1963. The epicenter of this earthquake was
located near Shelburne Falls, Massachusetts, about 15 to 20 miles southwest of
Vernon, Vermont. The intensity was listed as Modified Mercalli Intensity II or
less.
The earthquake catalogue of Henry Fielding Reid lists some local activity in the
Keene, New Hampshire area on October 10, 1854, and December 1, 1875. No newspaper
accounts of these earthquakes could be found in the New Hampshire Sentinel,
published in Keene.
A report of the earthquake which was observed in Vernon, Vermont, on June 11,
1898, appeared in the Monthly Weather Review of June 1898. "Vernon, Vermont,
reports an earthquake on the 11th, at 1:25 a.m., which was distinctly felt and
jarred the house. This seems to be quite an isolated case, and it is worth
inquiring whether this jar was not due to something else than a true earthquake".
Local newspapers were studied for any accounts of this earthquake. The earthquake
was observed in Brattleboro, but apparently not observed in Keene, or Hinsdale,
New Hampshire or Greenfield, Massachusetts. The newspaper account of the
earthquake which appeared in the Brattleboro Evening Phoenix of June 13, 1898, is
as follows: "An earthquake shock was felt distinctly in Brattleboro at 1:45
Saturday morning. People who were awake say that houses were shaken, and that
doors were slammed by the shock. The nervous shock which one woman sustained was
sufficient to cause illness. Mr. Pratt, the night watchman at S. A. Smith and
Company's factory, says that almost the same moment that the earthquake was felt,
a brilliant meteor flashed across the sky and exploded with a loud report. People
who felt the earthquake also heard the report, but few saw the meteor".
It is possible that this event was a meteor, but in evaluating the seismic
history, we must consider it as a local earthquake of Modified Mercalli Intensity
IV in the Vernon-Brattleboro area (see Figure 2.5-14).
VYNPS DSAR Revision 1 2.0-86 of 108
2.5.4 Conclusions
The nuclear installation is located on the west side of the Connecticut River near
Vernon, Vermont. The station is supported on rock at the site. Bedrock in the
area is hard, strong, competent gneiss with unconfined compressive strengths that
generally exceed 15,000 psi. The rock is moderately to highly jointed. The mass
of the rock has not been weakened structurally to any important degree by the
jointing. Seismic velocity measurements at the site verify the hard massive
nature of the bedrock. Deeply weathered or faulted zones were not detected at the
site. Geologic considerations do not preclude utilization of the site for a
nuclear station location.
The effects at the site resulting from a significant seismic disturbance have been
considered based upon local and regional geology, tectonics, and historical and
instrumental seismology.
It is indicated from geologic and tectonic history that the region is relatively
quiescent. Low magnitude seismic events can occur, but should be relatively
infrequent.
The seismic activity of the area is depicted on Figure 2.5-13. Some concentrated
areas of seismic activity may be noted 50 miles to the northeast of the site in
the Concord, New Hampshire area and at other localities 75 miles to 100 miles
distance from the site. The nearest earthquake to the site which produced damage
occurred near Concord, New Hampshire, and was of Intensity VI on the Modified
Mercalli Scale. Concord, New Hampshire, is 50 miles from the site.
Based on intensity attenuation with distance, the largest New England earthquakes,
which occurred some 85 to 90 miles from the site, would have been observed as
Modified Mercalli Intensity IV or V at the plant site.
The nearest earthquake to the site, which occurred during the instrumental
recordings of the last 30 years, had an epicentral location of approximately 15 to
20 miles from the site. The probable maximum intensity from an earthquake which
has been observed in the Vernon area is that of Intensity V on the Modified
Mercalli Scale. Based on extrapolated data from earthquakes which occurred on the
west coast of the United States, the maximum acceleration to be expected at the
bedrock surface of the plant site in Vernon, Vermont, would be from an earthquake
of Intensity V to low Intensity VI on the Modified Mercalli Scale. This
earthquake would produce an acceleration of approximately 0.03g to 0.04g.
VYNPS DSAR Revision 1 2.0-87 of 108
It is believed that the earthquake accelerations developed for this site are
conservative. They result from detailed studies of the site and region by
consultants knowledgeable in the field of seismology. However, for design
purposes, a minimum ground acceleration of 0.07g was used. In addition,
structures and equipment have been examined for an acceleration of 0.14g to
ascertain that no failure could occur that would prevent safe storage of
irradiated fuel.
VYNPS DSAR Revision 1 2.0-88 of 108
TABLE 2.5.1
AVAILABLE INFORMATION CONCERNING GEOLOGY AND SEISMIC ACTIVITY RELATED TO THE VERMONT YANKEE NUCLEAR POWER STATION SITE REFERENCES Balk, R., 1956. Bedrock Geology of the Massachusetts Portion of the
Northfield Quadrangle, Massachusetts - New Hampshire - Vermont: U.S. Geol. Survey, Geol. Quad. Map GQ92.
Billings, M.P., 1935. Geology of the Littleton - Moosilauke Quadrangles, New
Hampshire: New Hampshire State Planning and Development Comm., Concord, New Hampshire
Keeler, J., and Faulted Phyllite East of Greenfield, Brainard, C., 1940. Massachusetts: Am. Jour. Sci., V. 238, pp. 354-365. Moore, G. Em. Jr., 1949. Structure and Metamorphism of the Keene - Brattleboro
Area, New Hampshire - Vermont: Geol. Soc. Am., Bull., Vol. 60, pp. 1613-1670.
Robinson, P., 1963. Gneiss Domes of the Orange Area, Massachusetts and New
Hampshire: Doctoral Thesis, Harvard University. Skehan, J. W., 1961. The Green Mountain Anticlinorium in the Vicinity of
Wilmington and Woodford, Vermont: Bull: 17, Vermont Geol. Survey, Vermont Development Dept.
Trask, N.J., Jr., 1964. Stratigraphy and Structure in the Vernon -
Chesterfield Area, Massachusetts; New Hampshire; Vermont: Doctoral Thesis, Harvard University. Unpublished.
MAP REFERENCES 1. Centennial Geologic Map of Vermont, 1961, Compiled and Edited under the
direction of Dr. Charles G. Doll, State Geologist. 2. Geologic Map of New Hampshire, Marland P. Billings, Dept. of Geology, Harvard
University in cooperation with New Hampshire Planning and Development Commission and U.S. Geological Survey.
3. Geology Map of the Keene - Brattleboro Area; G.E. Moore, Jr., 1949, for New
Hampshire Planning and Development Commission.
VYNPS DSAR Revision 1 2.0-89 of 108
TABLE 2.5.2 VERNON PLUTON: ESTIMATED MODE OF THE OLIVERIAN MAGMA SERIES 1 2 3 4 5 Phenocrysts Quartz - 2 5 8 - Plagioclase - 2 - 2 - Hornblende - - - 5 - Groundmass Plagioclase 54 52 58 54 53 K-feldspar tr tr - - 7 Quartz 32 36 31 30 36 Biotite 5 3 - - 3 Chlorite 2 1 2 tr - Muscovite 3 2 4 - tr Epidote 4 1 - - 1 Magnetite - tr tr tr tr Garnet - tr tr - - Zircon tr tr tr tr tr Apatite tr tr tr tr tr Sphene - - - - tr Pyrite - - tr - - Hematite - - tr - - Leucoxene - - tr - - Tourmaline - - tr - - Carbonate tr 1 - - - % of Anorthite in Plagioclase 41 37 12 44 41 Size of Groundmass (mm) 0.25-1.0 0.1-0.25 0.05-0.2 0.15-0.3 0.05-0.5 Size of Phenocrysts (mm) - 2.0-3.0 2.0-4.0 1.0-4.0 - Texture Gr* Gr Gr Gr Gr Subp" Subp M** Por' M** 1. Quartz-diorite 4. Hornblende quartz diorite *GR = Granoblastic 2. Quartz-diorite 5. Granodiorite "Subp = Subporphyritic 3. Quartz-diorite **M = Mortar 'Por = Porphyritic (After Moore, 1949)
VYNPS DSAR Revision 1
2.0-90 of 108
Vermont YankeeDefueled Safety Analysis Report
Station Site - Geological Survey -
General Plan-Location of Test Borings Figure 2.5-2
VYNPS DSAR Revision 1
2.0-91 of 108
Vermont YankeeDefueled Safety Analysis Report
Station Site - Geological Survey -Subsurface Profile – Log of Test
Borings (1A, 2A, 3A, 4, 5, 8)
Figure 2.5-3
VYNPS DSAR Revision 1
2.0-92 of 108
Vermont Yankee
Defueled Safety Analysis Report
Station Site – Tectonic Map -
State of Vermont Figure 2.5-4
VYNPS DSAR Revision 1
2.0-93 of 108
Vermont Yankee
Defueled Safety Analysis Report
Station Site – Tectonic Map -
State of New Hampshire Figure 2.5-5
VYNPS DSAR Revision 1
2.0-94 of 108
Vermont Yankee
Defueled Safety Analysis Report
Station Site – Geological Survey Area Bedrock Geology
Figure 2.5-6
VYNPS DSAR Revision 1
2.0-95 of 108
Vermont Yankee
Defueled Safety Analysis Report
Station Site – Geological Survey
Area Geological Section Figure 2.5-7
VYNPS DSAR Revision 1
2.0-96 of 108
Vermont Yankee
Defueled Safety Analysis Report
Station Site – Geological Survey Subsurface Profile (Section AA)
Log of Test Borings (5, 8, S9, 11 and 21) Figure 2.5-8
VYNPS DSAR Revision 1
2.0-97 of 108
Vermont Yankee
Defueled Safety Analysis Report
Station Site – Geological Survey Subsurface Profile (Section BB)
Log of Test Borings (2A, 3A, ST6-1/2 and S9) Figure 2.5-9
VYNPS DSAR Revision 1
2.0-98 of 108
Vermont Yankee
Defueled Safety Analysis Report
Station Site – Geological Survey Subsurface Profile (Section CC)
Log of Test Borings (2, 2A, 5, 7, 7A, 13, 15)
Figure 2.5-10
VYNPS DSAR Revision 1
2.0-99 of 108
Vermont YankeeDefueled Safety Analysis Report
Station Site – Geological Survey
Subsurface Profile (Section BB)
Log of Test Borings (3, 3A, 4, 8, 8A, 12 and
16)
Figure 2.5-11
VYNPS DSAR Revision 1
2.0-100 of 108
Vermont Yankee
Defueled Safety Analysis Report
Station Site – Tectonic Map –
New England Area
Figure 2.5-12
VYNPS DSAR Revision 1
2.0-101 of 108
Vermont Yankee
Defueled Safety Analysis Report
Station Site – Compilation of
Earthquakes-New England Area
Figure 2.5-13
VYNPS DSAR Revision 1 2.0-102 of 108
Vermont Yankee
Defueled Safety Analysis Report
Station Site – Earthquake Intensity
Modified Mercalli and Rossi-Forel Scales
Figure 2.5-14
VYNPS DSAR Revision 1
2.0-103 of 108
Vermont Yankee
Defueled Safety Analysis Report
Station Site – Compilation of Earthquakes
Central New England Area
Figure 2.5-15
VYNPS DSAR Revision 1 2.0-104 of 108
2.6 RADIOLOGICAL ENVIRONMENTAL MONITORING PROGRAM
2.6.1 Objectives
The radiological environmental monitoring program is designed to demonstrate
the adequacy of environmental safeguards inherent in station design, the
effectiveness of the Process Radiation and Area Radiation Monitoring Systems
in measuring the controlled releases of low levels of radioactive materials
and the impact, if any, on the environment as a result of facility operation.
Emphasis is placed on control at the source with follow-up and confirmation by
environmental radiological surveillance.
The program consists of two phases, preoperational and operational, each
having specific objectives. The preoperational phase was conducted over the
two-year (approximate) period preceding station operation to establish
background radiation levels and radioactivity concentrations at selected
locations, to assess the variability between sample locations, and to observe
any cyclical or seasonal trends in the environmental sample media. Although
VYNPS has certified permanent cessation of operation and permanent defueling
in accordance with 10 CFR 50.82, the facility will continue in the operational
phase of the radiological environmental monitoring program. The operational
phase of the program has the following objectives:
1. To assure that radiation levels and radioactivity concentrations in the
environment resulting from facility operation meet the applicable
regulatory and license requirements.
2. To make possible the prompt recognition of any significant increase in
environmental radiation or radioactivity levels and to identify the cause
of the change, whether it be station effluents, effluents from other
nuclear facilities, fallout from atmospheric nuclear weapons tests,
seasonal changes in natural background, or other sources.
3. Obtain information on the critical radionuclides and pathways leading to
the quantitative evaluation of the dose to man resulting from the
operation of the station.
VYNPS DSAR Revision 1 2.0-105 of 108
2.6.2 Monitoring Network
The radiological environmental monitoring program compares measured radiation
levels and levels of radioactivity in samples from the area possibly
influenced by the station to levels found in areas not influenced by the
station. Sampling in both areas is done in accordance with the requirements
of Off-Site Dose Calculation Manual (ODCM) and Technical Specifications, with
the area outside the influence of the station serving as a background or
control for the area in the immediate vicinity of the station. A comparison
of survey data collected at control locations and locations within the range
of influence of the station (indicator locations) allows the determination of
any significant difference between the two areas. This method of
environmental sampling makes it possible to differentiate between facility
releases and other fluctuations in environmental radioactivity due to
atmospheric nuclear weapons test fallout, seasonal variations in natural
background, and other causes.
With the cessation of operations and reduced risk of radioactive releases from
the facility, the direct radiation monitoring network is reduced to each of
the 16 compass sectors around the facility with a land border with the state
of Vermont. Additional stations are situated at special interest and control
locations.
The types of sample media used for environmental surveillance are divided into
four categories, based on exposure pathways. These categories are direct
radiation, airborne, waterborne, and ingestion. Each of these is described
below. Specific and more detailed monitoring requirements may be found in
ODCM Section 3/4.5.1, and the identification of specific monitoring locations
may be found in Table 7.1 of the ODCM. The number of sampling locations and
the frequency of sampling discussed below reflect minimum ODCM requirements.
The actual sampling program may exceed these requirements.
2.6.2.1 Direct Radiation
Environmental direct radiation (gamma) measurements are continuously monitored
at approximately 40 locations. Either pressurized ion chambers or
Thermoluminescent Dosimeters (TLDs) are used to obtain an integrated gamma
radiation exposure at frequencies as prescribed in the ODCM. However, the
frequency of analysis readout is based upon the specific system used as
discussed in the ODCM.
VYNPS DSAR Revision 1 2.0-106 of 108
2.6.2.2 Airborne
Air is sampled for particulates at offsite locations as described in the ODCM
(including one control). The samples are collected by passing the air through
a glass fiber filter in series with a charcoal cartridge. The sampling pumps
operate continuously, and a meter is incorporated into the sampling stream to
measure the total volume of air sampled during a given interval.
The air particulate filters are collected and analyzed weekly for gross beta
radioactivity. These filters are composited for each sampling station and are
analyzed quarterly for gamma-emitting radionuclides.
Increased sampling frequency or additional analyses may be required on air
particulate filters or charcoal cartridges if conditions warrant, pursuant to
the footnotes to Off-Site Dose Calculation Manual Table 3.5.1.
2.6.2.3 Waterborne
2.6.2.3.1 Surface Water
River water samples are collected from one upstream and one downstream
location. At the upstream (control) location, a grab sample is collected
monthly. At the downstream location, an automatic compositing water sampler
collects an aliquot of river water at time intervals that are very short
relative to the compositing period (monthly). These composited samples are
collected monthly.
A gamma isotopic analysis is required on each monthly sample. These samples
are also composited, by station, for a quarterly tritium analysis.
2.6.2.3.2 Ground Water
Grab samples of ground water are collected and analyzed in accordance with the
requirements of the Off-Site Dose Calculation Manual.
2.6.2.3.3 Sediment from Shoreline
Sediment grab samples are collected semiannually from two locations, one
downstream from the station and one at the North Storm Drain Outfall. Each
sample is analyzed for gamma-emitting radionuclides.
VYNPS DSAR Revision 1 2.0-107 of 108
2.6.2.4 Ingestion
2.6.2.4.1 Deleted
2.6.2.4.2 Fish
Recreationally important species of fish are collected semiannually from two
locations, one upstream and one in the vicinity of the station discharge. The
edible portions of each sample are analyzed for gamma-emitting radionuclides.
2.6.2.4.3 Vegetation
A mixed grass sample is collected at each air sampling station on a quarterly
schedule, as available. Each sample is analyzed for gamma-emitting
radionuclides.
A silage sample is collected from each milk sampling station quarterly, as
available. Each sample is analyzed for gamma-emitting radionuclides.
2.6.3 Land Use Census
A Land Use Census is performed annually according to the Off-Site Dose
Calculation Manual 3/4.5.2. Analyses are done to ensure that the receptors
used for calculations done in accordance with the Off-Site Dose Calculation
Manual 3/4.3.3 are conservative.
2.6.4 Emergency Surveillance
The environmental monitoring program is designed to supplement emergency
monitoring functions as well as perform the routine surveillance activities.
The monitoring stations are strategically located and equipped to provide
radiation monitoring data essential to the rapid assessment of any accidental
radioactivity release.
VYNPS DSAR Revision 1 2.0-108 of 108
2.6.5 Reports
An Annual Radiological Environmental Operating Report is submitted to the NRC.
The report contains a summary, interpretations, and an analysis of trends for
the results of the radiological environmental surveillance activities for the
report period. Included are comparisons with operational controls and
previous environmental surveillance reports, plus a description of the
radiological environmental program and a map of all sampling locations. An
assessment of the impact of the station operation on the environment is also
included.
VYNPS DSAR Revision 1 3.0-1 of 87
FACILITY DESIGN AND OPERATION
TABLE OF CONTENTS
Section Title Page
3.1 DESIGN CRITERIA ....................................................... 7
3.1.1 Conformance with 10 CFR 50 Appendix A General Design Criteria .................................................... 7
3.1.2 Classification of Structures, Systems and Components ........ 9
3.1.3 Loading Considerations for Structures, Foundations, Equipment and Systems ...................................... 10
3.1.3.1. Seismic Classification ......................... 15
3.1.3.2 Seismic Design ................................. 17
3.1.4 References ................................................. 20
3.2 FACILITY STRUCTURES .................................................. 23
3.2.1 Reactor Building ........................................... 23
3.2.1.1 Function ....................................... 23
3.2.1.2 Description .................................... 23
3.2.1.3 Seismic Analysis ............................... 25
3.2.2 Turbine Building ........................................... 26
3.2.2.1 Function ....................................... 26
3.2.2.2 Description .................................... 26
3.2.3 Plant Stack ................................................ 27
3.2.3.1 Description .................................... 27
3.2.3.2 Seismic Analysis ............................... 27
3.2.4 Control Room Building ...................................... 28
3.2.4.1 Description .................................... 28
3.2.4.2 Seismic Analysis ............................... 28
3.2.5 Circulating Water Intake and Discharge Structures .......... 28
3.2.5.1 Intake Structure ............................... 28
3.2.5.2 Discharge and Aerating Structure ............... 29
3.2.6 Cooling Tower Deep Basin ................................... 29
VYNPS DSAR Revision 1 3.0-2 of 87
3.2.7 Independent Spent Fuel Storage Installation ................ 30
3.2.7.1 Description .................................... 30
3.2.7.2 Seismic Analysis ............................... 31
3.2.8 References ................................................. 32
3.3 SYSTEMS .............................................................. 35
3.3.1 Fuel Storage and Handling .................................. 36
3.3.1.1 Nuclear Fuel ................................... 36
3.3.1.2 Spent Fuel Storage ............................. 39
3.3.1.3 Standby Fuel Pool Cooling and Demineralizer Systems ........................................ 45
3.3.1.4 Tools and Servicing Equipment .................. 48
3.3.1.5 References ..................................... 51
3.3.2 Service Water System ....................................... 57
3.3.2.1 Objective ...................................... 57
3.3.2.2 Design Bases ................................... 57
3.3.2.3 Description .................................... 57
3.3.2.4 Evaluation ..................................... 59
3.3.2.5 Inspection and Testing ......................... 59
3.3.3 Electrical Power Systems ................................... 59
3.3.3.1 Transmission System ............................ 59
3.3.3.2 Auxiliary Power System ......................... 61
3.3.3.3 Deleted ........................................ 64
3.3.3.4 125 V DC System ................................ 64
3.3.3.5 24 V DC Power System .......................... 66
3.3.4 Fire Protection System ..................................... 67
3.3.4.1 Objective ...................................... 67
3.3.4.2 Design Basis ................................... 67
3.3.4.3 Description .................................... 68
3.3.4.4 Inspection and Testing ......................... 70
3.3.4.5 References ..................................... 70
3.3.5 Heating, Ventilating and Air Conditioning Systems .......... 71
VYNPS DSAR Revision 1 3.0-3 of 87
3.3.5.1 Objective ...................................... 71
3.3.5.2 Design Bases ................................... 71
3.3.5.3 Description .................................... 72
3.3.5.4 Inspection and Testing ......................... 76
3.3.6 Instrument and Service Air Systems ......................... 76
3.3.6.1 Objective ...................................... 76
3.3.6.2 Design Basis ................................... 77
3.3.6.3 Description .................................... 77
3.3.6.4 Inspection and Testing ......................... 78
3.3.7 Process Sampling ........................................... 78
3.3.7.1 Objective ...................................... 78
3.3.7.2 Design Basis ................................... 78
3.3.7.3 Description .................................... 78
3.3.8 Deleted .................................................... 79
3.3.9 Lighting Systems ........................................... 80
3.3.9.1 Objective ...................................... 80
3.3.9.2 Design Basis ................................... 80
3.3.9.3 Description .................................... 80
3.3.9.4 Inspection and Testing ......................... 81
3.3.10 Communication Systems ...................................... 81
3.3.10.1 Objective ...................................... 81
3.3.10.2 Design Basis ................................... 81
3.3.10.3 Description .................................... 82
3.3.10.4 Inspection and Testing ......................... 83
3.3.11 Process Computer System .................................... 83
3.3.11.1 Objectives ..................................... 83
3.3.11.2 Design Bases ................................... 83
3.3.11.3 Description .................................... 84
3.3.11.4 Inspection and Testing ......................... 86
3.3.11.5 Cyber Security ................................. 86
VYNPS DSAR Revision 1 3.0-4 of 87
3.3.11.6 Process Computer Data Feed to the Plant Data Server (PDS) ................................... 87
3.3.12 Torus-as-CST System ........................................ 87
3.3.12.1 Objective ...................................... 87
3.3.12.2 Design Basis ................................... 87
3.3.12.3 Description .................................... 87
VYNPS DSAR Revision 1 3.0-5 of 87
FACILITY DESIGN AND OPERATION
LIST OF TABLES Table No. Title 3.1.1 Allowable Stresses for Class I Structures 3.1-2 Safety Margins for Several Critical Portions of Major Class I
Structures
VYNPS DSAR Revision 1 3.0-6 of 87
FACILITY DESIGN AND OPERATION LIST OF FIGURES Reference Figure No. Drawing No. Title 3.2-18 Main Stack Geometry 3.3.1-1 Fuel Storage-Arrangement 3.3.1-2 5920-6893 POOL FUEL STORAGE RACK ARRANGEMENT 3.3.1-3 5920-12795 Pool Layout Spent Fuel Storage Racks 3.3.1-4 Fuel Storage Rack Assembly 3.3.1-5 HOLTEC Fuel Storage Rack Assembly (Partial)
VYNPS DSAR Revision 1 3.0-7 of 87
3.1 DESIGN CRITERIA
3.1.1 Conformance with 10 CFR 50 Appendix A General Design Criteria
The final version of the General Design Criteria was published in the Federal
Register February 20, 1971 as 10CFR50 Appendix A. Differences between the proposed
and final versions of the criteria included a consolidation from 70 to 64 criteria
and general elaboration of design requirement details. At the time of issuance, the
Commission stressed that the final version of the criteria were not new requirements
and were promulgated to more clearly articulate the licensing requirements and
practices in effect at the time.
In a Staff Requirements Memorandum on SECY-92-223, the NRC approved a proposal in
which it was recognized that plants with construction permits issued before May 21,
1971 were not licensed to meet the final General Design Criteria. The memo
recognized that while compliance with the intent of the final General Design
Criteria was important, back fitting of these requirements to older plants would
provide little or no safety benefit.
Although VYNPS was not required to comply with the General Design Criteria, the
design and construction of VYNPS was reviewed against the intent of the General
Design Criteria proposed in July, 1967. That review was documented in the VYNPS
UFSAR, Appendix F.2, Revision 17, is historical, and is not included in the DSAR.
Although changes were made to the facility over the life of the plant that may have
invoked the final General Design Criteria as design criteria, such invocation was
not intended to constitute a regulatory commitment, unless specifically docketed as
such.
The original Appendix F information, except cross-reference to applicable FSAR
Sections, is retained here for historical significance. Indications of the present
or future tense should be understood as being related to the time frame during which
this Appendix was originally written. Refer to information elsewhere in the DSAR and
in other design basis documentation to determine current design configuration.
The proposed General Design Criteria that are considered to remain applicable in the
defueled condition include the following:
Criterion 1--Quality Standards The quality assurance program is presented in the VY Quality Assurance Program
Manual (VY QAPM). The description of the various systems and components includes
the codes and standards that are met in the design and their adequacy.
VYNPS DSAR Revision 1 3.0-8 of 87
Criterion 2--Performance Standards Conformance to the applicable structural loading criteria ensures that those systems
and components affected by this criterion are designed and built to withstand the
forces that might be imposed by the occurrence of the various natural phenomena
mentioned in the criterion, and this presents no risk to the health and safety of
the public. The phenomena considered and margins of safety are also given.
Criterion 3--Fire Protection The materials and layout used in the station design have been chosen to minimize the
possibility and to mitigate the effects of fire. Sufficient fire protection
equipment is provided in the unlikely event of a fire.
Criterion 5--Records Requirement Complete records of the as-built design of the station, changes during operation and quality assurance records will be maintained throughout the life of the station.
Criterion 11--Control Room The facility is provided with a centralized control room having adequate shielding
to permit access and continuous occupancy under 10CFR20 dose limits during the
design basis accident situation.
Criterion 12--Instrumentation and Control Systems The necessary controls, instrumentation, and alarms for safe and orderly facility operation are located in the control room. These instruments and systems allow appropriate monitoring control of the facility. Sufficient instrumentation is provided to allow monitoring of all variables necessary for effective facility control.
Criterion 17--Monitoring Radioactive Releases The station process and area radiation monitoring systems are provided for
monitoring significant parameters from specific station process systems and specific
areas including the station effluents to the site environs and to provide alarms and
signals for appropriate corrective actions.
Criterion 18--Monitoring Fuel and Waste Storage The spent fuel storage areas have been analyzed to determine their safety, and
instrumentation is provided for monitoring where needed.
VYNPS DSAR Revision 1 3.0-9 of 87
Criterion 66--Prevention of Fuel Storage Criticality Appropriate facility fuel handling and storage facilities are provided to preclude
accidental criticality for spent fuel.
Criterion 67--Fuel and Waste Storage Decay Heat The system used to cool the spent fuel pool is designed to remove sufficient decay heat to maintain the pool water temperature. The fuel storage pool contains sufficient water so that in the event of the failure of an active system component, sufficient time is available to either repair the component or provide alternate means of cooling the storage pool. Criterion 68--Fuel and Waste Storage Radiation Shielding The handling and storage of spent fuel is done in the spent fuel storage pool. Water depth in the pool is maintained at a level to provide sufficient shielding for normal reactor building occupancy by facility personnel. A demineralizer system is used to control water clarity and to reduce water radioactivity. Accessible portions of the reactor and radwaste buildings have sufficient shielding to maintain dose rates within the limits of 10CFR20. Criterion 69--Protection Against Radioactivity Release From Spent Fuel and Waste Storage The consequences of a fuel handling accident in the spent fuel pool are presented elsewhere in the DSAR. In this analysis, it is demonstrated that undue amounts of radioactivity are not released to the public. All spent fuel and waste storage systems are conservatively designed with ample margin to prevent the possibility of gross mechanical failure which could release significant amounts of radioactivity. Backup systems such as floor and trench drains are provided to collect potential leakages. Appropriate facility personnel are rigorously trained and administrative procedures are strictly followed to reduce the potential for human error. The radiation monitoring system is designed to provide facility personnel with early indication of possible malfunctions. Criterion 70--Control of Releases of Radioactivity to the Environment The station radioactive waste control systems (which include the liquid and solid radwaste systems) are designed to limit the off-site radiation exposure to levels below limits set forth in 10CFR20.
3.1.2 Classification of Structures, Systems and Components
Following certification of permanent defueling, VY is no longer authorized to
emplace or retain fuel in the reactor vessel in accordance with 10CFR50.82(a)(2).
VYNPS DSAR Revision 1 3.0-10 of 87
Since it is no longer possible to load a nuclear core, power operations can no
longer occur and reactor related design basis accidents are no longer possible.
Consequently, it was determined that the remaining design basis accident possible at
VY is a fuel handling accident (FHA) consisting of a dropped fuel bundle in the
Spent Fuel Pool. As presented in the Safety Analysis chapter of the DSAR, the dose
consequences of the fuel handling accident are well within acceptance criteria, with
no reliance on either the Standby Gas Treatment System or the Secondary Containment
System.
Based on the changed conditions described above, an evaluation of the systems,
structures and components (SSCs) described in the UFSAR was performed to determine
the SSC safety classification based on the function, if any, each SSC would perform
in the permanently defueled condition. The process and criteria used to classify
the SSCs and the conclusions of the evaluation are provided in appropriate station
documents.
3.1.3 Loading Considerations for Structures, Foundations, Equipment and Systems
All structures have been designed to withstand the combinations of dead and live
loads which give the severest credible conditions of loading. Loading, including
seismic, wind, and impact loading, are in accordance with the applicable codes, and
incorporate the applicable provisions of the Uniform Building Code, Zone II, 1967
Edition; ACI Standard Building Code Requirements for Reinforced Concrete (ACI
318-63); ACI Standard Specification for the Design and Construction of Reinforced
Concrete Chimneys (ACI 505-54); AISC Specification for the Design, Fabrication, and
Erection of Structural Steel for Buildings (1963); American Water Works Association,
"AWWA Standard for Steel Tanks, Standpipes, Reservoirs, and Elevated Tanks for Water
Storage," AWWA D-100 (1967); USA Standards Institute ASA B96.1, "Welded Aluminum
Alloy Field-Erected Storage Tanks; National Fire Protection Association Standard
NFPA No. 30, "Flammable and Combustible Liquids Codes" (1966); Section III of the
ASME Boiler and Pressure Vessel Code, "Nuclear Vessels" (1968); and Section VIII of
the ASME Boiler and Pressure Vessel Code, "Unfired Pressure Vessels" (1968).
The Reactor Building and all other Class I structures except the main stack and
ISFSI storage pad are founded on firm bedrock. The main stack rests on end-bearing
steel piles which transfer stack loads to the bedrock. The ISFSI storage pad is
founded on engineered fill placed on existing soil.
The maximum allowable bearing pressure is 50 tons per square foot. The maximum
loading on the bedrock does not exceed 20 tons per square foot.
The maximum anticipated earthquake at the site would result in a maximum horizontal
ground acceleration of 0.07g. Facility design ensures that appropriate functions
remain available during or following a ground horizontal acceleration of 0.14g.
VYNPS DSAR Revision 1 3.0-11 of 87
A strong motion, solid state digital accelerograph is floor mounted in the Reactor
Building southwest corner room, floor Elevation 213'-9". The unit is designed to
provide continuous monitoring for earthquakes by means of three orthogonal
accelerometers, two horizontal and one vertical, which sense earthquake ground
motion. Once triggered, the accelerograph will record the seismic event or a series
of events as long as the trigger levels are exceeded. The primary function of the
strong motion accelerograph is to provide data which will be of value in promptly
assessing the condition of the plant subsequent to an earthquake per 10CFR100,
Appendix A.
The maximum anticipated wind velocity that is anticipated at the site is 80 mph with
gusts to 100 mph. The station structures are designed to withstand the anticipated
wind loadings. The site is located in a geographic area which has a small
probability of being subjected to tornadic wind conditions.
Live loads, including construction loads, which are greater than the loads
prescribed under code, and loads from operating pressures and/or temperatures which
increase the stresses, have also been used in the design. Standard practice of use
and application in power plants determined the selection of the materials used in
the various structures and supports.
The loadings considered were as follows:
D is the dead load of structure and equipment plus any other permanent
loads contributing stress such as soil, hydrostatic pressure, temperature
loading, or operating pressures.
L is the live load from any nonpermanent loads such as equipment not fixed
in place, roof snow load, etc.
R is the jet force or pressure on the structure due to rupture of any one
pipe.
H is the force on the structure due to thermal expansion of pipes.
E is the design earthquake load.
E' is the maximum hypothetical earthquake load.
W is the load due to wind.
W' is the load due to tornado.
VYNPS DSAR Revision 1 3.0-12 of 87
The loading considerations, using the postulated events, which have been followed
for all Class I structures and equipment to determine the controlling stress levels
to be used in design are:
Loading Consideration Allowable Stress A. Reactor Building and All Other Class I Structures, excluding the primary containment 1. D+L+R+E Normal allowable code stresses are used.
The customary increase in design stresses for the loading combinations considered is not permitted.
2. D+L+R+E' Stresses are allowed to approach the
3. D+L+W' yield point for ductile materials, and 0.85 times the ultimate strength for concrete.
4. D+L+W Normal allowable code stresses and
customary increases in stresses are used for these load combinations.
B. Class I Tanks 1. D+L+H+E Normal allowable code stresses are 2. D+L+H+W used. The customary increases in design
stresses for the load combinations considered are not permitted.
3. D+L+H+E' Stresses are allowed to approach the yield
point for ductile materials and 0.85 times the ultimate strength for concrete.
The load combination equations listed above are based on allowable stress design.
No plastic strength design for steel structures or ultimate strength design for
concrete was used for Vermont Yankee; therefore, no load factors were applied to the
subject equations.
VYNPS DSAR Revision 1 3.0-13 of 87
To assure the required properties of concrete poured during cold weather, placing of
concrete with ambient temperatures around 15oF was done with several requirements
that included temperature control during the mixing, placing, and curing of the
concrete. The mixing water was heated to a temperature range of 100°F to 175°F
which was adequate to maintain a concrete temperature of ±65°F at the point of
discharge from the mixer. This temperature is within allowable limits for proper
concrete placement. No frozen lumps of material were allowed in the charging hopper
of the batching plant. When necessary, the area of concrete placement was sheltered
for protection against the weather and preheated. This precaution was taken to
assure that no concrete would be placed against frozen surfaces. During placement
of concrete floors, heat was provided for the underside as well as the top surface.
The ambient temperature in the area of the placement was maintained at a minimum
temperature of 45°F for at least 5 days, and special coverings or enclosures were
provided to permit proper curing conditions for the concrete. Concrete specialists
were retained to design the concrete mixes, perform testing as required, and to
assist in developing an overall concrete program for the project. They also
witnessed and reported on concrete placements and were encouraged to comment on all
phases of the program including cold weather concreting.
Table 3.1.1 gives the maximum allowable stresses used for the various loading
conditions for Class I structures.
Floor live loads are based on equipment and operating loads and applied in
accordance with the Uniform Building Code Zone II (UBC), 1967 Edition. Roof live
loads are 40 psf applied as specified in the UBC to obtain the worst condition of
stress.
The 40 psf design roof live loads (snow loading) was determined as follows:
The American National Standards Institute (formerly the American Standards
Institute) in their "Minimum Design Loads in Buildings and other Structures,"
specify the weight of seasonal snowpack equaled or exceeded 1 year in 10 as the
minimum snow load for design purposes. This figure for the Vermont Yankee Nuclear
Power Station is equal to 30 pounds per square foot. Forty pounds per square foot
or 10 psf more than specified, was conservatively used for the design of the
structures. The weight of the estimated maximum accumulation on the ground plus the
weight of the maximum possible snowstorm of 70 psf, as shown in Section 2.3.5.3, is
interpreted as applicable for the drifts on the ground where accumulation is
permitted by the terrain. Winds will not permit such accumulations to occur on
building roofs of the station; therefore, the 40 psf used in the design is
considered a conservative loading.
VYNPS DSAR Revision 1 3.0-14 of 87
The station masonry wall design for Class I structures is analyzed to meet the NRC
Bulletin 80-11 guidelines. The design approach and analysis used were approved in
References 1 and 2.
Floor dead loads include the weight of the structural components and the
architectural appurtenances. Operating loads consist of gravity loads from all
equipment and piping. All structures satisfy the requirements of the UBC, Zone II,
35 psf basic wind as per American Standards Association (ASA) A58.1, 1955. In
addition, the following Class I structures have been designed to withstand
short-term tornado winds up to 300 mph: Control Room Building, Reactor Building
below the refueling level, intake structure (service bay area), Turbine Building
self-contained Diesel Generator Rooms, tornado walls around outdoor condensate
storage and fuel oil storage tanks. The effect of a 300 mph wind on a Class I
structure was analyzed by applying a uniformly distributed positive pressure of
185 psf on the windward side of the structure and a negative pressure of 115 psf on
the leeward side in accordance with ASCE Wind Forces on Structures. It is assumed
that there is a 3 psi pressure drop associated with the passage of a tornado. Only
those structures which are enclosed require design against the effect of this
pressure drop. In the Reactor Building, the internal overpressure is relieved by
providing that specified areas of the siding enclosure (blowout panels) above the
refueling level will fail at an overpressure falling in the designated range of 0.35
psi to 0.60 psi (Reference 3). Subsequent pressure equalization is obtained at each
successive level below the refuel floor by means of large open hatch areas on each
floor. In the Diesel Generator Rooms of the Turbine Building, dedicated tornado
pressure relief dampers are provided which will allow the room to vent through the
intake air supply to the exterior of the building. Since the siding on the Turbine
Building will blow off with winds, such as those associated with a tornado, the
Daytank Rooms are vented into the Turbine Building by the open space that is
provided beneath their doors. These dampers and openings will provide adequate
venting capacity to limit the pressure differential on the enclosure walls. The
Control Room Building has been designed to withstand a 3 psi pressure drop without
venting.
Class I structures are also designed against penetration by tornado-created
missiles. The missiles which have been considered are 4 x 4 inch x 16 foot-long
wood posts and 2 x 12 inch x 16 foot-long wood planks. For an analysis of the
effects of a tornado on the spent fuel storage pool, see APED-5696, "Tornado
Protection for the Spent Fuel Storage Pool."
For tornado loading, metals are allowed to approach their yield point, and concrete,
its ultimate strength.
VYNPS DSAR Revision 1 3.0-15 of 87
3.1.3.1. Seismic Classification
The two classes of structures applicable to the earthquake design requirements are
as follows:
Class I - Structures and equipment whose failure could cause significant release of
radioactivity in excess of 10CFR100 for a low probability event or which are vital
to the removal of decay and sensible heat from the spent fuel pool.
The ISFSI storage pad (comprised of an East and West pad) is classified as Important
to Safety Class C (ITS-C) as defined in 10CFR72.3. The Important to Safety features
of the storage pad are to maintain the conditions required to store spent fuel
safely and prevent damage to the spent fuel container during storage.
Class II - Structures and equipment which may be essential or even nonessential to
the operation of the facility.
An analysis of the consequences of failure of several structures was performed.
This analysis showed that a condensate storage tank rupture could result in the
release of radioactivity resulting in potential doses in excess of the limits of
10CFR20 for unrestricted areas. It should be recognized, however, that this failure
constitutes an accident and that 10CFR50.67 rather than 10CFR20 applies. Within the
scope and bases used in this analysis, no Class I or II structures or equipment were
found which, upon failure, could result in doses in excess of the limits of
10CFR50.67 at the site boundary.
3.1.3.1.1 Class I Structures
The following is a listing of the Class I structures associated with the storage of
irradiated fuel:
Suppression Chamber (torus), including vents and penetrations
Reactor Building
Control Room Building
Plant Stack
Intake Structure (Service Water Pump Area)
Cooling Tower Deep Basin
Independent Spent Fuel Storage Installation (ISFSI) pad
VYNPS DSAR Revision 1 3.0-16 of 87
3.1.3.1.2 Class I Equipment
The following is a list of Class I equipment associated with the storage of
irradiated fuel:
• Nuclear Steam Supply System
- Fuel Assemblies
• Station Service Water System (up to the main condenser discharge block)
• Fuel Storage Facilities, to include spent fuel storage equipment
• Instrumentation and Control Systems
- Radiation Monitoring System (partial)
• Fuel Oil Storage Tank
3.1.3.1.3 Class II Structures
Administration Building
Intake and Discharge Structures (except as noted under Class I structures)
All Other Structures, not listed in Paragraph 3.1.3.1.2, that have seismic
design requirements
3.1.3.1.4 Class II Equipment
Reactor Building Cranes
Condensate Storage Transfer System
Station Auxiliary Power Busses
Electrical Controls and Instrumentation (for above systems)
All Other Piping and Equipment, not listed in Paragraph 3.1.3.1.3, that have
seismic design requirements
VYNPS DSAR Revision 1 3.0-17 of 87
3.1.3.2 Seismic Design
All Class I structures were designed conservatively so that under the worst loading
conditions the allowable stresses will not be exceeded. Several critical portions
of major Class I structures are listed in Table 3.1.2, showing the margins of safety
for the controlling loads for the listed structural member.
No. 1 shows (a) the circumferential stresses in the reactor pedestal due to a
jet force and (b) the vertical stresses at the base of the pedestal due to
direct load plus earthquake plus jet force.
No. 2 shows the stresses due to dead and live load plus design base or maximum
hypothetical earthquake at the face of the biological wall and at midspan of an
important beam in the Reactor Building. This beam supports part of the floor
deck at Elevation 280 plus an interior column which extends up to the refuel
floor.
No. 3 shows the stresses under the same loading conditions as in No. 2 in a
footing supporting a column of the Control Room.
No. 4 shows the stresses in the south wall of the housing of the service water
pumps in the intake structure under tornado wind load.
Based on seismological investigations, response spectra and dynamic analyses
established for the station, envelopes of maximum acceleration, displacement, shear,
and overturning moment versus height have been developed. The horizontal ground
acceleration for the design earthquake is 0.07 times gravity (0.07g), and the
vertical motion 2/3 that of the horizontal. Both motions are assumed to occur
simultaneously.
It is noted that Appendix A "Seismic Analysis" of the DSAR Revision 0, contained
historical information regarding the seismic design analysis for various SSCs.
VYNPS DSAR Revision 1 3.0-18 of 87
3.1.3.2.1 Class I Structures
Mathematical models whose properties correspond to those of the structures or
equipment were formulated. The seismic design for the Class I structures and
equipment is based on dynamic analysis using the acceleration response spectrum
curves. The design is such that safe shutdown can be made during a ground motion of
0.14g, combined with the vertical accelerations assumed to be 2/3 of the horizontal
ground acceleration, with no variation of the vertical coefficients with height.
For the dynamic analysis of Class I structures, the damping factors used for
vibrations below the elastic limit are as follows:
Item Percent of Critical Damping
Reinforced Concrete Structures 5.0
Steel Frame Structure 2.0
Bolted or Riveted Assembly 2.0
Welded Assembly (equipment and supports) 1.0
Vital Piping System Various
Wood Structures with Bolted Joints 5.0
Summaries of the seismic analyses for the Reactor Building, Control Room Building,
plant stack, intake structure, and deep basin are given in the Facility Structures
section under the respective structure. Detailed analyses for the ISFSI storage pad
is contained in References 4 through 8 for the East Storage Pad and References 9
through 14 for the West Storage Pad.
3.1.3.2.2 Class II Structures
Design was in accordance with the provisions of the Uniform Building Code, Zone II.
Alternately, all such structures were designed to resist a minimum horizontal
seismic coefficient of 0.05, with a 1/3 allowable increase in basic stresses.
VYNPS DSAR Revision 1 3.0-19 of 87
3.1.3.2.3 Equipment Seismic Design
Class I equipment analysis considers vertical and horizontal ground motions. The
coefficients for horizontal motion were adjusted to correct for equipment elevation
above grade, and also consider the stiffness of the equipment supports. The
magnitude of the vertical acceleration used was 2/3 of the horizontal ground
acceleration with no variation of the vertical coefficients with height. Allowable
stresses are in accordance with Table 3.1.1.
Stresses have also been checked for an earthquake with two times the seismic
coefficients. Class I equipment is bolted or fastened so that it will not be
displaced.
All Class I tanks have been analyzed for forces resulting from a horizontal
acceleration of 0.22g acting simultaneously with a vertical acceleration of 0.05g.
These accelerations take into account the height above grade of the various Class I
tanks. Stresses have been kept within the basic code allowables with no increase
for short-term loading. Further analysis was performed using twice the horizontal
and vertical accelerations, and for this condition of loading, stresses in the
ductile materials have been permitted to go to 0.90 of yield.
The selection of the horizontal seismic loading coefficient for the Class I tanks
was based on the maximum acceleration at the elevation of the tank in the supporting
structure. This permits maximum flexibility in arrangement of the vital tanks
within the structures and ensures no condition of overstress due to seismic loading.
For Class II equipment, the seismic analysis has assumed there is no vertical ground
motion. This is in accordance with the Uniform Building Code, Zone II. The
horizontal motion has been adjusted to correct for equipment elevation above grade.
Code allowable stresses with increase for short-term loading have been maintained.
Class II tanks are analyzed for forces resulting from a horizontal acceleration of
0.09g, with allowable stresses increased by 25% in accordance with the provisions of
the Uniform Building Code.
The selection of the seismic acceleration coefficients for the Class II tanks also
reflects the upper elevations of the structures where these tanks are located.
Class I equipment is principally supported on reinforced concrete. In the Reactor
Building, all supporting concrete has a minimum 4,000 psi, 28-day ultimate
compressive strength. All other supporting concrete has a minimum 3,000 psi, 28-day
ultimate compressive strength. All reinforcing has a minimum yield stress of 40,000
psi. Where structural steel is used to support Class I equipment, ASTM A36 standard
rolled shapes or other material analyzed to meet the requirements of this section
are used. The allowable stresses are as listed in Table 3.1.1.
VYNPS DSAR Revision 1 3.0-20 of 87
3.1.4 References
1. Letter, G. Lainas (USNRC) to J. B. Sinclair (VYNPC), “Masonry Wall Design, IE
Bulletin 80-11,” NVY 83-262, dated November 15, 1983.
2. Letter, D. B. Vassallo (USNRC) to R. W. Capstick (VYNPC), “Masonry Wall Design
Supplement – Inspection and Enforcement Bulletin 80-11,” NVY 85-240, dated
November 18, 1985.
3. Calculation VYC-1828, “Reactor Building Masonry Wall Review for HELB
Loadings.”
4. Calculation VYC-2427, “Development of Acceleration Time Histories for Vermont
Yankee ISFSI Analysis.”
5. Calculation VYC-2428, “Development of Strain Compatible Soil Properties for
Vermont Yankee ISFSI Analysis.”
6. Calculation VYC-2433, “Soil Structure Interaction Analysis of the Vermont
Yankee ISFSI.”
7. Calculation VYC-2435, ”Vermont Yankee Nuclear Power Plant ISFSI Facility
Concrete Storage Pad Design”
8. Calculation VYC-2434, “Vermont Yankee ISFSI Cask Sliding Analysis.”
9. Calculation VYC-3175, "Determination of Soil Parameters for ISFSI Expansion
Concrete Storage Pad."
10.Calculation VYC-3176, "Development of Response Spectra Consistent Time
Histories for ISFSI Expansion Concrete Storage Pad."
11.Calculation VYC-3177, "Development of Strain Dependent Soil Properties for
ISFSI Expansion Concrete Storage Pad."
12.Calculation VYC-3178, "Soil Structure Interaction Analysis and Cask
Stability/Sliding of ISFSI Expansion Concrete Storage Pad."
13.Calculation VYC-3179, "Liquefaction Potential for ISFSI Expansion Concrete
Storage Pad."
14.Calculation VYC-3181, "Structural Concrete Design for ISFSI Expansion Concrete
Storage Pad."
VYNPS DSAR Revision 1 3.0-21 of 87
TABLE 3.1.1 Allowable Stresses for Class I Structures
Loading Conditions
Reinforcing Steel
Maximum Allowable Stress
Concrete Maximum
Allowable Compressive
Stress
Concrete Maximum
Allowable Shear Stress
Concrete Maximum
Allowable Bearing Stress
Structural Steel
Tension on Net Section
Structural Steel Shear
on Gross
Section
Structural Steel
Compression on Gross Section
Structural Steel
Bending
1. Loading as defined without E', W and W'
0.50 Fy 0.45 f c
1.10 f c
0.25 f c
0.60 Fy 0.40 Fy Varies with slenderness ratio
0.66 Fy
to 0.60 Fy
2. Loading as defined excluding E, E' and W'
0.667 Fy 0.60 f c
1.467 f c
0.333 f c 0.80 Fy 0.53 Fy
Varies with slenderness ratio
0.88 Fy to
0.80 Fy
3. Loading as defined with E' or W' present
Seismic load (0.14g)
See Note A 0.85 f c -- -- See Note A 0.60 Fy
Varies with slenderness ratio
See Note A
* 25% Live Load is considered concurrent with seismic load. Fy is the minimum yield point of the steel used.
f c is the compressive strength of concrete.
Note A: Stresses permitted to approach but not exceed yield stress of the material.
VYNPS DSAR Revision 1 3.0-22 of 87
TABLE 3.1.2 Safety Margins for Several Critical Portions
of Major Class I Structures
Controlling
Loading
Allowable Stress in psi
Actual Stresses in psi
Safety Margins (Allowable/Actual)
Structure Condition Concrete Reinforcing Concrete Reinforcing Concrete Reinforcing
1. RPV Pedestal a. Circumferential Stresses ......... b. Vertical Stresses ................
R
D+L+E+R
3400 1800
36,000 20,000
1720 877
34,000 19,644
1.97 2.06
1.06 1.02
2. RB Biological Wall Beam a. At face .......................... b. At face .......................... c. At midspan ....................... d. At midspan .......................
D+L+E D+L+E' D+L+E D+L+E'
1800 3400 1800 400
20,000 36,000 20,000 36,000
950 1080 1640 2380
18,100 20,800 16,400 23,600
1.90 3.14 1.16 1.43
1.10 1.73 1.22 1.53
3. Control Room Footing a. Face of column ................... b. Face of column ...................
D+L+E D+L+E'
1350 2550
20,000 36,000
450 810
15,600 28,200
3.00 3.15
1.28 1.28
4. Intake Structure Service Bay a. South enclosure ..................
D+L+W'
2550
36,000
300
15,000
8.50
2.40
NOTE: Loads as defined in Section 3.1.3.
VYNPS DSAR Revision 1 3.0-23 of 87
3.2 FACILITY STRUCTURES
3.2.1 Reactor Building
3.2.1.1 Function
The Reactor Building encloses the spent fuel storage pool.
3.2.1.2 Description
The Reactor Building is constructed of monolithic reinforced concrete floors and
walls to the refueling level. Above the refueling level, the structure consists of
steel framing covered by insulated sealed siding and roof decking. The siding and
roofing can withstand a limited internal overpressure before pressure relief is
obtained by venting through the refuel floor blowout panels designed to release at
an overpressure falling in the designated range of 0.35 psi to 0.60 psi (Reference
1).
A 110/7.73 ton capacity overhead bridge crane provides services for the reactor and
refueling area. The crane is designed to remain on the rails and retain its load
with a 0.2g seismic loading. The Reactor Building bridge crane is of Class II
seismic design. Accordingly, the coefficient of 0.20g was specified based on the
building response of the level of crane supports under 0.07g minimum ground
acceleration. The crane supports are of Class I seismic design. The crane bridge
and trolley wheels are provided with seismic hold-down lugs to assure crane
stability in the event of a maximum hypothetical earthquake.
Reference 2 details the commitments to control the handling of heavy loads,
including the specific commitments made during the submittal process to the NRC, as
input to their Safety Evaluation Report, and how they are implemented at Vermont
Yankee. The Reactor Building overhead bridge crane trolley was modified to provide
redundancy in the load carrying path from the load to the crane itself, so that no
single failure would allow the load to drop. All components in the load path of the
main hoist are either redundant or designed with a large factor of safety, and are
structurally adequate to maintain the load capacity, as well as any transfer loads
should one path fail. Each load path for the main hook consists of a hook or
attachment point, load block, cable, reversing sheaves, drum, gear drive, and
brakes. Sheaves and blocks are captured so that failure would not result in
uncontrolled descent of the load. Redundant limit switches, of different types, are
provided to prevent over-hoisting, and a load indicating/limiting device prevents
overloading. An overspeed switch is provided on each load path to prevent runaway
lowering. Operating power and control for all crane motions are provided by a
control system which incorporates a torque limiter on the main hoist for additional
overload protection.
VYNPS DSAR Revision 1 3.0-24 of 87
When moving a spent fuel shipping cask, the crane speeds are reduced and the travel
path limited to prevent the cask from passing over the stored spent fuel.
The crane was designed in accordance with the Electric Overhead Crane Institute
(EOCI) Specification No. 61 and, with minor exceptions, meets all requirements of
the Crane Manufacturers Association of America (CMAA) Specification No. 70.
The primary containment structure is an integral part of the Reactor Building and
occupies the core of the building. The spent fuel storage pool is located in the
Reactor Building. Access to the drywell and reactor head space is obtained by
removing a large segmented concrete plug in the refueling level floor by means of
the bridge crane. The crane also handles the drywell head, the reactor vessel head,
the segmented pool plugs, and the spent fuel shipping cask. A refueling platform,
with the requisite handling and grappling fixtures, services the spent fuel storage
pool. A passenger-freight elevator is provided for access to the various floors
above grade level.
The steel drywell vessel is fixed to the building along its lower portion, and is
laterally supported by the building along its upper portion. Within the drywell, a
cylindrical sacrificial shield structure surrounds the reactor vessel.
There is a remote possibility that the height of ground water during a given period
could exceed the elevation of the extreme lower portion of the drywell.
Nevertheless, it is not considered possible for this ground water to reach the steel
plating, assuming a crack in the foundation concrete. The bases for this conclusion
are as follows:
1. The monolithic foundation concrete structure is greater than 18 feet thick
below the drywell and is divided into three separate pours in the horizontal
plane. It is considered almost impossible for a crack to propagate completely
through any given pour because of the thicknesses involved and the bedrock
foundation. Even if this were to occur, it is not considered possible for any
given crack to propagate beyond the joint between pours.
2. Water-stop material is used at all foundation concrete joints between pours,
both in the horizontal and vertical planes. This design assures that water
will not propagate along any given joint in the concrete.
The possible effects of a given thermal gradient through the foundation concrete
have been considered. Based on the concrete thicknesses and possible temperature
differentials, it is not considered possible for any thermal gradients to exist
which would damage or otherwise affect the structural integrity of the concrete.
Therefore, thermal gradients are not considered a factor in the above discussion on
foundation cracking.
VYNPS DSAR Revision 1 3.0-25 of 87
The reinforced concrete portion of the Reactor Building has been designed against
tornado missiles. Pressure relief below the refueling level is obtained through
large open hatches.
The general arrangement of the Reactor Building and the principal equipment is shown
on Drawings G-191148, G-191149 and G-191150.
3.2.1.3 Seismic Analysis
Dynamic earthquake analysis was made of the coupled Drywell/Reactor Building System
for an empty and flooded condition of the drywell. A separate analysis was made for
the pressure suppression chamber.
The effect of the adjacent Class II Turbine Building has been considered, and the
analysis shows that failure of the adjacent Turbine Building will not compromise the
integrity of the Class I Reactor Building in the event of a design basis or maximum
hypothetical earthquake.
The sacrificial shield wall and reactor pedestal are hollow cylinders of uniform
thickness connected by anchor bolts embedded in the top of the pedestal.
The pedestal carries the vertical load of the sacrificial shield wall including the
loads transmitted to it. The pedestal is supported at Elevation 238.0' by a
concrete foundation which rests on the lower part of the containment vessel.
Moments, vertical loads, and horizontal forces from the reactor pressure vessel,
pedestal, and drywell are transmitted to the supporting drywell foundations in the
following manner:
The reactor pressure vessel transmits vertical loads and shears directly to the
drywell foundation through the vessel skirt into the reactor pedestal via shear
rings welded to the inner skirt. The vertical and horizontal loads from the
pedestal are transferred to the interior and exterior surface of the drywell by a
combination of bond and friction forces between steel and concrete contact surfaces.
The contact between the exterior surface of the drywell and the supporting concrete
foundation is assured by the pressure grouting method used for the concreting of the
foundation itself. Additional resistance to shear is afforded by the physical
characteristics of the drywell which, in its lower portion, can be considered as a
bowl embedded in the supporting reinforced concrete foundation. No increase in
allowable stresses was permitted in any of the above considerations.
The stresses resulting from the maximum hypothetical earthquake were also checked to
make sure that their value was below allowable limits.
VYNPS DSAR Revision 1 3.0-26 of 87
The interaction of the drywell base with the exterior concrete is comprised of
bonding and friction, and it is a result of these phenomena that the relative shears
are handled.
The phenomenon of bonding, although a significant contributory factor, is ignored
for conservatism. Extreme care is exercised in placing the grout between the
drywell base and the exterior concrete. This provides adequate assurance that there
are no significant voids in this area and that the actual drywell contact area is
high. In addition to providing significant bonding, this surface area also provides
a large contact area to resist relative shears through friction.
The vertical load transmitted through the drywell is approximately 8,230k. The
horizontal load resulting from a maximum hypothetical earthquake is 3,165k. To be
conservative, the calculations assume that vertical, horizontal and moment forces
are transmitted from the drywell to the foundation mat by the reactor vessel skirt
alone. It is further assumed that the reactor vessel skirt, welded to the drywell,
will transmit the horizontal forces by bearing against the fill concrete surrounding
it. For conservatism, only the top two feet of the skirt were considered as
transmitting the load.
The concrete stresses and welding stresses were checked against the allowable
stresses to determine if the skirt and the surrounding concrete can withstand the
horizontal forces. The concrete stress is 638 psi, which is less than the 1,000 psi
allowed by ACI 318, 1963. The unit shear stress on the skirt weld is 488 psi, which
is small in comparison with the load-carrying capability of the weld.
The ability of the foundation mat to resist shear forces was also investigated. No
credit was taken for the anchor bolts which fasten the skirt to the foundation mat,
and friction alone is assumed to resist shear forces. A coefficient of friction was
conservatively assumed to be 0.4, which results in a shear resisting force
capability of 3,292k. As the maximum horizontal load is 3,165k, the adequacy of the
foundation mat is demonstrated.
3.2.2 Turbine Building
3.2.2.1 Function
The Turbine Building SSCs have been abandoned.
3.2.2.2 Description
SSCs within the Turbine Building have been abandoned. Equipment and floor drain
sumps are routed to a batch tank. Tank contents are sampled prior to being
transferred, disposed of (via offsite shipments), or discharged to the environs in
accordance with applicable permits and regulatory approvals.
VYNPS DSAR Revision 1 3.0-27 of 87
3.2.3 Plant Stack
3.2.3.1 Description
The plant stack provides an elevated point for the release of gases to the
atmosphere from portions of the Turbine Building, Reactor Building, and Radwaste
Building. Stack drainage is routed to the Liquid Radwaste Collection System via
loop seals.
The plant stack is designed for dead load, wind load, seismic load, and effects of
exhaust gas temperature. The plant stack is provided with appurtenances such as
aviation obstruction lights and isokinetic samplers for radiation monitoring, and is
designed in accordance with all applicable codes.
The unlined, freestanding, tapered, reinforced concrete stack has the following
dimensions:
Overall height above foundation 318 ft
Inside diameter at top 7 ft
Outside diameter at base 27.5 ft
Thickness at top 0.67 ft
A schematic of the stack geometry appears in Figure 3.2-18.
3.2.3.2 Seismic Analysis
Dynamic analysis was made of the reinforced concrete ventilation stack.
The foundation material for the site is such that rocking effects are small and were
neglected for the dynamic analysis of the stack. Due to its geometry, the stack is
very flexible, with the natural period of vibration of the first mode equal to about
1.5 seconds. The spectral accelerations for periods higher than this decrease with
an increase in period. The model used for the dynamic analysis of the stack
conservatively assumed a fixed base. The damping value used in the analysis for the
responses to both the design basis and maximum hypothetical earthquakes was 5%.
The controlling loading conditions were the maximum hypothetical earthquake in the
region approximately 120 feet from top and the wind loading for the remaining
portion of the stack. For the maximum hypothetical earthquake, the maximum
calculated stress in the reinforcing steel was 35.4 ksi or 0.86 Fy, and the
calculated maximum stress in concrete was 1.32 ksi or 0.377 f c.
VYNPS DSAR Revision 1 3.0-28 of 87
3.2.4 Control Room Building
3.2.4.1 Description
The Control Room Building houses all required instrumentation and controls. The
instrumentation is located in the Main Control Room. The cable vault and Switchgear
Room occupy the lower levels of the building. The location of the Control Room
Building is shown on Drawing G-191142. The building is a reinforced concrete
structure and is entirely of Class I seismic design.
Plan and elevation views of the building are shown on Drawings G-191592 and
G-191595.
3.2.4.2 Seismic Analysis
A dynamic earthquake analysis was performed on the Control Room Building utilizing a
four-mass analytical model. The effect of the adjacent Class II Turbine Building
has been considered, and the results of the analysis show that failure of the
adjacent Class II structure will not compromise the integrity of the Class I Control
Room Building in the event of a design basis or maximum hypothetical earthquake.
3.2.5 Circulating Water Intake and Discharge Structures
3.2.5.1 Intake Structure
3.2.5.1.1 Description
A reinforced concrete, single unit intake structure on the riverbank east of the
station, is supported on rock. A partial enclosure is provided at the pumps. The
following equipment is provided at the intake: manually raked coarse trash racks,
regulating sluice gates; traveling screens; provisions for stoplogs; two fire water
pumps; two service water pumps and two radwaste dilution pumps.
The deck of the structure is at Elevation 237' MSL and the invert at Elevation 190'
MSL. The intake has service water bays for two service water pumps, two fire water
pumps, and two radwaste dilution pumps. Bays are provided with trash rack and
stoplog guides, traveling screens, and fine screen guides.
Water from the pond flows into service water bays at the north end of the intake
structure. These bays furnish water for the fire pumps, intake service water pumps,
and radwaste dilution pumps.
Retaining walls are provided at the front face of the intake structure to retain
fill.
VYNPS DSAR Revision 1 3.0-29 of 87
The intake structure is shown on Drawings G-191451, G-191452 and G-191453.
3.2.5.1.2 Seismic Analysis
A dynamic earthquake analysis has been made of the intake structure. This analysis
verifies the adequacy of the design of the intake structure to withstand seismic
forces. The effect of adjacent Class II intake structures has been considered, and
the results of the analysis show that failure of an adjacent Class II structure will
not compromise the integrity of the Class I bay housing the service water pumps in
the event of a design basis or maximum hypothetical earthquake.
3.2.5.2 Discharge and Aerating Structure
A reinforced concrete discharge-aerating structure supported on rock and piles is
located near the riverbank south-southeast of the station. It is approximately 188
feet long by 108 feet wide by 46 feet deep. The top of the deck is at Elevation
248' MSL. Water elevation for siphon operation will be maintained by a reinforced
concrete weir. The top of the weir is at Elevation 225' MSL. An aerating spillway
concrete structure is adjacent and downstream of the discharge structure to provide
air entrainment, energy dissipation, and warm water dispersion of discharged water.
Sheet piling is used to prevent scour of the aerating apron.
The discharge and aerating structure is shown on Drawings G-191463, G-191461, Sh. 1
and G-200347.
3.2.6 Cooling Tower Deep Basin
The basin has been dynamically analyzed for 0.07g and 0.14g horizontal ground
accelerations; vertical accelerations were taken as 0.05g and 0.10g for the design
basis and maximum hypothetical earthquake, respectively.
The effect of adjacent Class II structures has been considered, and the analysis
show that a failure of the Class II adjacent cooling tower structures will not
compromise the integrity of the deep basin in the event of a design basis or maximum
hypothetical earthquake.
VYNPS DSAR Revision 1 3.0-30 of 87
3.2.7 Independent Spent Fuel Storage Installation
3.2.7.1 Description
The ISFSI Storage Pad (comprised of an East and West pad) is monolithic reinforced
concrete slabs supported by compacted structural fill placed on existing soils. The
two storage pads provide structural support for up to 58 spent fuel storage casks
with four extra positions to provide sufficient room to be able to access any
individual cask should the need arise, and 3 spaces available for storage of
Greater-than-Class-C (GTCC) storage casks. The East Storage Pad can store up to 40
casks arranged in a 5 X 8 array. The West Storage Pad can store up to 25 casks in a
5 X 5 array. The spent fuel storage casks are free standing on the pad. There is
temperature monitoring available for each cask if desired. Each cask will be
grounded to plates embedded in the storage pad. The top of the pad elevation is
established at El. 254’-0” to ensure that the ventilation inlets at the bottom of
the spent fuel storage casks remain above the Probable Maximum Flood (PMF) elevation
including wave run-up.
The spent fuel cask manufacturer’s Final Safety Analysis Report (Reference 3)
requires that for free standing casks several criteria must be met to ensure that
the design features of the cask that protect the spent fuel from a cask drop or non-
mechanistic tip-over event are not jeopardized. These criteria are that the
thickness of the pad does not exceed 36 inches, the 28 day concrete compressive
strength must not be less than 3000 psi and must not exceed 4200 psi, the specified
minimum yield strength for the reinforcing steel be 60 ksi, and that the subgrade
modulus of elasticity not exceed 28,000 psi.
VYNPS DSAR Revision 1 3.0-31 of 87
3.2.7.2 Seismic Analysis
A dynamic analysis of each of the ISFSI storage pads was performed. This analysis
is composed of several parts. A subsurface investigation was performed to establish
bedrock elevations and soil properties beneath each pad (References 4 for the East
pad and 10 for the West pad). The design of the East pad meets the requirements of
Revision 3 of Section 3.7.1 of NUREG-0800 which was in effect at the time of its
design. A single set of three artificial time histories for the Design Basis
Earthquake was developed for input to the seismic analysis (Reference 5). The
design of the West pad meets the requirements of Revision 4 of Section 3.7.1 of
NUREG-0800 which was in affect the time of its design. Five sets of three
artificial time histories for the Design Basis Earthquake were developed for input
to the seismic analysis (Reference 12). These time histories envelope the design
response spectra for the site, the North 69º West component of the Taft Earthquake,
normalized to 0.14g for the Design Basis Earthquake. The earthquake(s) is applied
at the bedrock elevation under the storage pad. Analysis was then performed to
obtain strain compatible soil properties and to propagate the earthquake motion from
the bedrock to the ground surface. Since the bedrock under the storage pad is
sloping, this analysis was performed for two profiles, one profile to the deepest
bedrock depth under each pad and one profile to the shallowest bedrock depth under
each pad. This analysis is further described and provided in Reference 6 for the
East pad and 13 for the West pad. A soil structure interaction (SSI) analysis was
then performed to determine the acceleration at the center of gravity and at the
base of the casks. This analysis was performed using three separate soil cases
(upper bound, best estimate, and lower bound). The analysis also considered two
soil profiles to represent the sloping bedrock. The SSI analysis evaluates multiple
cask configurations to insure the maximum effect on the storage pad is enveloped.
The soil structure interaction analysis is further described and presented in
Reference 7 for the East pad and 14 for the West pad.
The results of the soil structure interaction analysis are used to perform a sliding
analysis and the storage pad design. The sliding analysis determines the potential
for the casks to:
(1) slide into each other, and
(2) uplift a seismic event.
VYNPS DSAR Revision 1 3.0-32 of 87
The sliding analysis evaluated coefficients of friction ranging from 0.0 to
stimulate icing conditions on the pad up to a maximum of 0.8. The results of the
analysis show that the maximum horizontal displacements of the casks for any
condition are much smaller than half the free distance between the casks and much
less than the distance between the edge of the external casks and the edge of the
pad. This analysis also shows that the casks are stable and remain upright. The
sliding analysis is provided in Reference 8 for the East pad and 14 for the West
pad. References 9 (East pad) and 16 (West pad) provide the analysis to determine
the internal forces on the storage pad for all loading conditions, including
seismic, and the design of the reinforcement for the storage pad.
3.2.8 References
1. Calculation VYC-1828, “Reactor Building Masonry Wall Review for HELB Loadings.”
2. PP 7023, “Control of Heavy Loads Program Document.”
3. Final Safety Analysis Report for the Holtec International Storage and Transfer
Operation Reinforced Module Cask System (HI-STORM 100 Cask System), NRC Docket
No. 72-1014, Holtec Report HI-2002444, Volume I and II of II, prepared by Holtec
International, Marlton, New Jersey.
4. Geotechnical Engineering Report, Proposed ISFSI Pad and Haul Path – Vermont
Yankee, prepared by GZA GeoEnvironmental, Inc., Manchester, New Hampshire,
January 2004
5. Calculation VYC-2427, “Development of Acceleration Time Histories for Vermont
Yankee ISFSI Analysis.”
6. Calculation VYC-2428, “Development of Strain Compatible Soil Properties for
Vermont Yankee ISFSI Analysis.”
7. Calculation VYC-2433, “Soil Structure Interaction Analysis of the Vermont Yankee
ISFSI.”
8. Calculation VYC-2434, “Vermont Yankee ISFSI Cask Sliding Analysis.”
9. Calculation VYC-2435, ”Vermont Yankee Nuclear Power Plant ISFSI Facility Concrete
Storage Pad Design”
10 Report VY-ROT-14-00005, "Geotechnical Soils Report for DFS-PAD-2 – Data Report to
Support the Expansion of the Independent Spent Fuel Storage Installation
(ISFSI)."
VYNPS DSAR Revision 1 3.0-33 of 87
11. Calculation VYC-3175, "Determination of Soil Parameters for ISFSI Expansion
Concrete Storage Pad."
12. Calculation VYC-3176, "Development of Response Spectra Consistent Time Histories
for ISFSI Expansion Concrete Storage Pad."
13. Calculation VYC-3177, "Development of Strain Dependent Soil Properties for ISFSI
Expansion Concrete Storage Pad."
14. Calculation VYC-3178, "Soil Structure Interaction Analysis and Cask
Stability/Sliding of ISFSI Expansion Concrete Storage Pad."
15. Calculation VYC-3179, "Liquefaction Potential for ISFSI Expansion Concrete
Storage Pad."
16. Calculation VYC-3181, "Structural Concrete Design for ISFSI Expansion Concrete
Storage Pad."
VYNPS DSAR Revision 1 3.0-34 of 87
Vermont Yankee
Defueled Safety Analysis Report
Main Stack Geometry
Figure 3.2-18
VYNPS DSAR Revision 1 3.0-35 of 87
3.3 SYSTEMS
The following systems have been or are in the process of being abandoned and removed
from service. Abandonment includes, where appropriate, draining piping and tanks,
removing electrical power, removal of combustible liquids and placing the abandoned
SSC in its lowest energy condition.
High Pressure Coolant Injection System
Main Steam
Heater Drains and Vents
Automatic Depressurization System
Air Evacuation, Auxiliary Steam, Advanced Off Gas
Condensate & Condensate Demineralizer System
Containment Air Dilution System
Circulating Water & Circulating Water Priming System (includes cooling tower
equipment)
Feedwater & Feedwater Controls Systems
Hydrogen, Hydrogen Water Chemistry, Nitrogen Supply & Oxygen Injection Systems
MG Lube Oil System
Reactor Protection and Primary Containment Isolation System
River Water Temperature and Toxic Gas Monitoring Systems
Reactor Core Isolation Cooling System
Recirculation Pumps, MG Sets & Flow Control System
Main Turbine Generator, TBCCW, Stator Cooling Seal Oil, Lube Oil, Isophase Bus
Cooling
Standby Liquid Control System
22K and 345K Volts AC Electrical System
Control Rod Drive & Hydraulic Control Unit Systems
Core Spray System
Nuclear Boiler and Nuclear Boiler Vessel Instrumentation Systems
Neutron Monitoring System
Reactor Building Closed Cooling Water System
Residual Heat Removal & RHR Service Water Systems
Radwaste System
Process Rad Monitor and Turbine Building Area Rad Monitor
Reactor Water Clean-Up System
Demineralized Water Transfer and Makeup Demineralizer Systems
Post Accident Sampling System
Primary Containment/Penetration System
VYNPS DSAR Revision 1 3.0-36 of 87
Primary Containment Atmospheric Control
Emergency Diesel Generator and Fuel Oil Systems
Normal Fuel Pool Cooling System (FPCS)
Fire Protection System, Sprinklers/Detectors (Partial Abandonment)
Potable Water Reconfiguration For SAFSTOR
400V DC System
Service Water System (Partial Abandonment)
Removal Of Low Level Radwaste Site and Other Non-SSC Buildings
24V DC RPS Neutron Monitoring System Batteries
Vital MG Set MG-2-1A
Stack Gas III Radiation Monitor (RM-17-155)
Sentry Lights
3.3.1 Fuel Storage and Handling
3.3.1.1 Nuclear Fuel
3.3.1.1.1 Objective
The nuclear fuel provides a high integrity assembly containing fissionable material
which could be arranged in a critical array. The assembly efficiently transfers
decay heat to the spent fuel pool water while maintaining structural integrity and
containing the fission products.
3.3.1.1.2 Description
A fuel assembly consists of a fuel bundle, channel fastener, and the channel which
surrounded it. Each fuel assembly was designed as Class I seismic design equipment.
A fuel bundle contains fuel rods and water rods, spaced and supported in a square
array by a lower tie plate, spacers, and an upper tie plate. The lower tie plate was
formed and machined to fit into the fuel support piece. The lower tie plate for the
GE13, GE14 and GNF2 fuel bundles also includes a debris filter. The upper tie plate
has a handle for transferring the fuel bundle from one location to another. The
identifying assembly number is engraved on the top of the handle and a boss projects
from one side of the handle to aid in assuring proper fuel assembly orientation.
The tie plates were fabricated from corrosion resistant materials. The fuel spacer
grids, which are positioned along the length of the fuel bundle, are made of
Zircaloy with Inconel springs. The GE13 and GE14 fuel spacer grids, which are
positioned along the length of the fuel bundle, are made of Zircaloy with alloy X750
springs. The GNF2 spacer is made entirely from alloy X750. The primary function of
the spacer grid is to provide lateral support and spacing of the fuel rods.
VYNPS DSAR Revision 1 3.0-37 of 87
Each fuel rod consists of fuel pellets stacked in a Zircaloy cladding tube which is
evacuated, pressurized with helium, and sealed by welding Zircaloy end plugs in each
end. The fuel rod cladding thickness is adequate to be "free-standing", i.e.,
capable of withstanding external reactor pressure without collapsing onto the
pellets within. Although most fission products were retained within the UO2, a
fraction of the gaseous products were released from the pellet and accumulated in a
plenum and the gap between the pellet stack and the clad. Sufficient plenum volume
was provided to prevent excessive internal pressure from these fission gases or
other gases liberated over the design life of the fuel. A plenum spring, or
retainer, is provided in the top plenum space to minimize movement of the fuel
column during handling or shipping. Rigid precautions are taken to prevent cladding
damage due to excessive hydrogen bearing materials. These precautions may include a
hydrogen getter in the plenum to absorb hydrogen accidentally admitted during the
fabrication process.
Eight fuel rods (called tie rods) in each bundle have end plugs which thread into
the lower tie plate and extend through the upper tie plate. Stainless steel nuts
and locking tab washers are installed on the upper end plugs to hold the assembly
together. These tie rods support the weight of the assembly only during fuel
handling operations when the assembly hangs by the handle. The remaining fuel rods
in a bundle have end plug shanks which fit into locating holes in the tie plates.
An Inconel-expansion spring located over the top end plug shank of each full length
fuel rod keeps the fuel rods seated in the lower tie plate and allows them to expand
axially by sliding within the holes in the upper tie plate to accommodate
differential axial expansion. Part length rods use a threaded lower end plug which
screws into the lower tie plate. These rods terminate near one of the spacer grids
short of the upper tie plate.
Each fuel bundle may contain one or more empty Zircaloy tubes called water rods.
Perforations at each end of the water rod(s) permit coolant flow through the tube.
Tabs are fixed at axial intervals on one or more water rods to locate the spacer
grids. Water rods provide additional moderator throughout the height of the
assembly.
The fuel is in the form of cylindrical pellets manufactured by cold pressing and
sintering uranium dioxide powder. The average density of the pellets in the core is
approximately 96.5% of the theoretical density of UO2. Ceramic uranium dioxide is
chemically inert to the cladding at operating temperatures and is resistant to
attack by water.
VYNPS DSAR Revision 1 3.0-38 of 87
Several different U-235 enrichments may be used in each fuel assembly. Fuel design,
manufacturing, and inspection procedures have been developed to prevent errors in
enrichment location within the fuel assembly. The fuel rods have unique
identification numbers. Rigid inspection techniques utilized during and following
assembly ensure that each fuel rod is in the correct position within the bundle.
Selected fuel rods contain gadolinia as a burnable poison for reactivity control.
The gadolinia is uniformly dispersed within the fuel pellets. However, the
gadolinia-bearing pellets are not uniformly distributed within the fuel rods, but
are grouped together into axial zones. These axially zoned regions of varying
gadolinia content provide reactivity control which enhances shutdown margin and/or
power distribution control to reduce axial peaking. U-235 enrichment is also zoned
axially to compliment the function of the gadolinia, and provide a more economical
fuel cycle.
The fuel channel enclosing the fuel bundle is fabricated from Zircaloy and, if
installed, performs the following functions:
1. Provides structural stiffness to the fuel bundle during lateral loading applied
from fuel rods through the fuel spacers.
2. Transmits fuel assembly seismic loadings to the top guide and fuel support of
the core internal structures.
The channel makes a sliding seal fit over finger springs attached to the lower tie
plate. The channel is attached to the upper tie plate by the channel fastener
assembly which is secured by a cap screw. Spacer buttons are located on the two
sides of the channel adjacent to the channel fastener assembly to maintain bundle
separation and form a path for the control blades in the core cell.
GNF2 fuel assemblies are arranged in a 10X10 array with two central water rods, as
well as both short and long partial length rods. Some of the design features
include the following:
Improved part-length rod configuration for improved Cold Shutdown Margin (CSDM)
and efficiency.
Modified fuel rod clad thickness to diameter ratio (T/D) with increased uranium
mass for increased bundle energy.
Modified channel that interacts with the LTP to control leakage flow while
eliminating finger springs for ease of channeling operations.
Improved Inconel X-750 grid type spacer with Flow Wings for increased margin to
Boiling Transition and reduced pressure drop.
VYNPS DSAR Revision 1 3.0-39 of 87
Defender Debris Filter Lower Tie Plate for improved resistance to the intrusion
of foreign material.
High volume pellet for increased uranium mass and manufacturing quality control.
Locking retainer spring that restrains the fuel column during shipping and
supports a wide range of column lengths.
A non-Zircaloy 2 zirconium alloy, Ziron, is used for the fuel cladding material
for 24 rods in 2 of the 4 GNF2 LUAs.
The external envelope of GNF2 is virtually identical to GE14 and the nuclear
characteristics of the GNF2 are compatible with current vintage GE14. The thermal
hydraulic characteristics of GNF2 design closely match the overall pressure drop of
previous designs.
Licensing analyses of the GNF2 LUAs have been conducted using NRC approved methods,
which are capable of evaluating/analyzing all of the LUA features.
3.3.1.2 Spent Fuel Storage
3.3.1.2.1 Objective
The spent fuel storage arrangement provides specially designed underwater storage
space for the spent fuel assemblies which require shielding during storage and
handling.
Storage of spent fuel in dry casks at the Independent Spent Fuel Storage
Installation facility is licensed in accordance with 10CFR72 and is not within the
scope of the 10CFR50 Updated Final Safety Analysis Report.
3.3.1.2.2 Design Bases
1. The spent fuel pool is designed for a maximum of twelve spent fuel storage
racks with a maximum capacity of 3,353 spent fuel assemblies.
2. Spent fuel storage racks shall be designed and arranged so that the fuel
assemblies can be efficiently handled.
3. The fuel array in the fully loaded spent fuel racks shall be substantially
subcritical such that keff is less than or equal to 0.95.
4. Each spent fuel storage rack shall be designed to withstand earthquake loading
to prevent significant distortion of spent fuel storage arrangement when empty,
half-full, or fully loaded with fuel.
VYNPS DSAR Revision 1 3.0-40 of 87
3.3.1.2.3 Description
The spent fuel storage racks provide storage at the bottom of the fuel pool for the
spent fuel received from the reactor vessel, as shown in Figure 3.3.1-1. The racks
are full length, top entry, and designed to maintain the spent fuel in a space
geometry which precludes the possibility of criticality under normal and abnormal
conditions. Normal conditions exist when the spent fuel is stored at the bottom of
the fuel pool in the design storage position. Abnormal conditions may result from
an earthquake or mishandling of equipment.
The normal arrangement of the spent fuel storage racks consists of nine NES
manufactured racks (Drawing 5920-6893) and two Holtec manufactured racks (Drawing
5920–12795), giving a total capacity of 3087 assemblies. A twelfth rack can be
installed in the cask lay-down area as shown on Drawing 5920–12795 to provide
additional full core discharge capacity and a total pool capacity of 3,353
assemblies. The control rod blade (CRB) storage rack shown on Drawing 5920–6893
will be unloaded and removed if a twelfth rack needs to be installed or when the
cask pad must be used, such as for an irradiated hardware disposal campaign.
Partial plans depicting the Boral loading are provided in Figures 3.3.1-4 and 3.3.1-
5. The spent fuel storage racks are designated Safety Class 2.
Each rack consists of a welded assembly of individual storage cells in a staggered
checkerboard array. The storage cells are comprised of Type 304L stainless steel
boxes (5.922 inches square ID) welded to each other with corner angles to maintain a
pitch of 6.218 inches. The rack dimensions are 178.50 inches tall, 87.43 inches to
125.27 inches long, and 74.99 inches to 112.83 inches wide. Each storage cell has
an interior height of 168 inches. The construction of the storage cells provides
four vented (open to the pool) compartments in which B4C neutron absorber elements
are placed for criticality control. The neutron absorber elements are positioned on
the side of the storage cell at an elevation corresponding to the fuel region of a
spent fuel assembly placed within the cell. The bottom of each storage cell sits
on, and is welded to, the rack base plate which provides the level seating surface
required for each fuel assembly and also contains the openings necessary for
adequate cooling flow. Drawing 5920-6893 shows a schematic drawing of a typical
rack.
All materials used in the construction of the rack are specified in accordance with
the applicable ASME or equivalent ASTM specification, and all welds are in
accordance with ASME Section II, for materials used, and ASME Section IX. Materials
selected are corrosion-resistant or treated to provide the necessary corrosion
resistance.
VYNPS DSAR Revision 1 3.0-41 of 87
The maximum number of assemblies stored in the pool cannot exceed 3,353.
Each rack is freestanding with no lateral restraints to the wall, and is supported
by a minimum of four steel feet that transfer load to the pool floor. Any lateral
loads on the racks will be transferred by friction between the feet and the pool
floor. The racks are designed such that a fuel assembly or grappling device cannot
become fouled during removal and, thereby, generate significant uplift loads.
No spaces exist between normal fuel storage positions so that it is not possible to
insert a fuel assembly, either deliberately or by accidental drop, in any position
not intended as a fuel storage position.
Each spent fuel storage rack loaded with fuel has been analyzed to determine its
continued operability during and after both design basis and safe shutdown
earthquakes. It has been determined that under the most severe seismic loading
condition, the rack will slide a maximum of 0.56 inches. A clear distance of 2
inches (minimum) is maintained between spent fuel storage racks, spent fuel storage
racks and walls, and spent fuel storage racks and any other objects in the pool. A
clear distance of 5 inches (minimum) is maintained between the Control Rod Blade
(CRB) storage racks and any other large or fixed objects in the pool. A clear
distance of 6.24 inches and 10.0 inches (minimum) is maintained between the CRB
storage racks and the NES and Holtec spent fuel storage racks respectively.
The fuel storage pool is designed so that no single failure of structures or
equipment will cause inability to (1) maintain irradiated fuel submerged in water,
(2) re-establish normal fuel pool water level, or (3) safely remove fuel from the
plant. In order to limit the possibility of pool leakage around pool penetrations,
the pool is lined with stainless steel. In addition to providing a high degree of
integrity, the lining is designed to withstand abuse that might occur when the
transport cask is moved about. No inlets, outlets, or drains are provided that
might permit the pool to be drained below approximately 10 feet above the top of the
active fuel. Lines extending below this level are equipped with valving.
Interconnected drainage paths are provided behind the liner welds. These paths are
designed to (1) prevent pressure buildup behind the liner plate, (2) prevent the
uncontrolled loss of contaminated pool water to other relatively cleaner locations
within the secondary containment, and (3) provide expedient liner leak detection and
measurement. These drainage paths are formed by welding channels behind the liner
weld joints and are designed to permit determination of liner weld leakage.
VYNPS DSAR Revision 1 3.0-42 of 87
The spent fuel pool is 26 feet-0 inches wide by 40 feet-0 inches long by 39 feet-3/4
inches deep. The pool is completely lined with seam-welded ASTM-A240, Type 304
stainless steel. The floor plate is 1/4-inch thick and the wall plate is 3/16-inch
thick. Pipe sleeves are welded to the liner plate by full circumferential fillet
welds on both sides of the plate.
All welds above the waterline were visually examined. Those welds which could be
exposed to water were examined by liquid penetrant tests. In addition, all joint
welds and welds at penetrations in plates were tested for leaks using a vacuum box
and soap solution tests.
3.3.1.2.4 Safety Evaluation
Administrative controls ensure a sufficient level of water is maintained to ensure
shielding and/or cooling.
The design of the spent fuel storage racks provides for a subcritical multiplication
factor (keff) for both normal and abnormal storage conditions.
For all conditions, keff is equal to or less than 0.95. Normal conditions exist when
the fuel storage racks are located at the bottom of the pool covered with a normal
depth of water (about 23 feet above the stored fuel) for radiation shielding and
with the maximum number of fuel assemblies in their design storage position. The
spent fuel is covered with water at all times by a minimum depth required to provide
sufficient shielding. Abnormal conditions may result from an earthquake, accidental
dropping of equipment, or damage caused by the horizontal movement of fuel handling
equipment without first disengaging the fuel from the hoisting equipment.
Accidental dropping of large pieces of equipment, such as a spent fuel shipping
cask, is prevented by the use of an overhead bridge crane with redundant load
bearing equipment on the main hoist.
Criticality calculations were done using a two-dimensional, two-group diffusion
theory code with a water temperature of 39°F. Water temperatures were varied
between 39°F and 248°F to assure that 39°F was the more reactive under normal
conditions. Monte Carlo calculations and verifications assured the adequacy of the
diffusion theory representation.
In order to ensure that the design criteria stated above are met, the following
loading conditions have been analyzed. The results include allowance for
calculational uncertainty.
VYNPS DSAR Revision 1 3.0-43 of 87
The off-normal conditions evaluated are:
1. Normal positioning in the NES and Holtec spent keff = 0.9469
fuel storage array
2. Eccentric positioning in the NES and Holtec spent less than 0.9469
fuel storage array
3. An assembly was placed tightly in the corner formed less than 0.9267
by an L-shaped junction of three racks (NES racks only)
Stress in a fully loaded rack will not exceed applicable stress limits for Seismic
Category I structures per requirements of the NRC Standard Review Plan,
Section 3.8.4. Horizontal acceleration time history data derived from a Bechtel
calculation and maximum vertical seismic acceleration were applied simultaneously.
Maximum vertical acceleration was taken from the applicable vertical spectra at the
fundamental vertical frequency of the rack. The stresses, due to partially loaded
and empty rack conditions, are smaller than the full loaded condition.
The storage rack structure is designed to absorb the vertical impact force imposed
by a fuel assembly dropped from a height of 36 inches above a rack onto any location
on the rack. Under this impact force, those members will remain intact whose
function it is to physically maintain the normal design subcritical spacing to
assure keff is less than 0.95.
GE topical report "Tornado Protection for the Spent Storage Pool," APED-5696,
November, 1968 investigated the potential effects of a tornado striking the fuel
storage pool of a boiling water reactor (BWR). Two key concerns were examined; (1)
whether sufficient water could be removed from the pool to prevent cooling of the
fuel, and (2) whether missiles could potentially enter the pool and damage the
stored fuel.
The fuel pool was designed with substantial capability for withstanding the effects
of a tornado. The design of the fuel pool makes the removal of five feet of water
due to tornado action highly improbable. With 25 feet of water covering the fuel
racks, the removal of five feet of water is of no concern. Protection against a
wide spectrum of tornado-generated missiles is provided by the water which covers
the fuel racks.
Protection is provided against all tornado-generated missiles having a probability
of hitting the pool greater than one per 1.4 billion reactor lifetimes. Typical
potential missiles in this category include a spectrum ranging up to a 3-inch
diameter steel cylinder 7 feet long or a 14-inch diameter wooden pole 12 feet long.
VYNPS DSAR Revision 1 3.0-44 of 87
The General Electric Company concluded that adequate protection for the fuel pool
against the effects of a tornado was provided and no additional protection was
required.
NUREG-1738, “Technical Study of Spent Fuel Pool Accident Risk at Decommissioning
Nuclear Power Plants” (Reference 1) contains the results of an NRC staff evaluation
of the potential accident risk in spent fuel pools at decommissioning plants in the
United States. The study was undertaken to support development of a risk-informed
technical basis for reviewing exemption requests and a regulatory framework for
integrated rulemaking. The NRC staff performed analyses and sensitivity studies on
evacuation timing to assess the risk significance of relaxed offsite emergency
preparedness requirements during decommissioning. The staff based its sensitivity
assessment on the guidance in Regulatory Guide 1.174, "An Approach for Using
Probabilistic Risk Assessment In Risk-Informed Decisions on Plant-Specific Changes
to the Licensing Basis” (Reference 2). The staff's analyses and conclusions apply to
decommissioning facilities with SFPs that meet the design and operational
characteristics assumed in the risk analysis.
The study found that the risk at decommissioning plants is low and well within the
Commission's Safety Goals. The risk is low because of the very low likelihood of a
zirconium fire (resulting from a postulated irrecoverable loss of SFP cooling water
inventory) even though the consequences from a zirconium fire could be serious.
NUREG-1738, Executive Summary, states in part, "the staff's analyses and conclusions
apply to decommissioning facilities with SFPs that meet the design and operational
characteristics assumed in the risk analysis. These characteristics are identified
in the study as IDCs and SDAs. Provisions for confirmation of these characteristics
would need to be an integral part of rulemaking."
Design and operation of the VY SFP has been evaluated against and confirmed to
comply with the industry decommissioning commitments (IDCs) and staff
decommissioning assumptions (SDAs) contained in NUREG-1738. The evaluation is
documented in BVY 14-009, Request for Exemptions from Portions of 10CFR50.47 and
10CFR50, Appendix E. (Reference 3)
3.3.1.2.5 Inspection and Testing
The spent fuel storage racks were tested at the plant site or visually inspected
during rack fabrication to ensure that the Boral sheets are in place and free of
voids. Since Boral absorbs neutrons, a neutron source and proportional counters
were used to verify the integrity of the Boral sheet.
VYNPS DSAR Revision 1 3.0-45 of 87
An inspection mandrel was used to test each storage cell location. The insertion
and withdrawal of the mandrel was monitored over the entire length of the cell to
ensure that acceptable drag forces were not exceeded.
3.3.1.3 Standby Fuel Pool Cooling and Demineralizer Systems
3.3.1.3.1 Objective
The Standby Fuel Pool Cooling (SFPCS) removes decay heat released from the spent
fuel to maintain fuel pool temperature within specified limits. The Fuel Pool
Demineralizer System (FPDS) maintains water clarity.
3.3.1.3.2 Design Bases
1. The FPDS shall minimize corrosion product buildup within the spent fuel pool
and shall maintain proper water clarity so that the fuel assemblies can be
efficiently handled underwater.
2. The FPDS shall minimize fission product concentration in the spent fuel pool
water, thereby minimizing the radioactivity which could be released from the
pool to the Reactor Building environment.
3. The Fuel pool water level shall be maintained at a level above the fuel
sufficient to provide shielding for normal building occupancy.
4. The Standby Fuel Pool Cooling System shall be capable of maintaining the spent
fuel pool temperature below 150°F.
3.3.1.3.3 Description
The SFPCS is shown on Drawing G-191173, Sheets 1 and 2.
Fuel Pool Structure
The fuel pool concrete structure, metal liner, spent fuel storage racks, and the
SFPCS are designed to withstand Seismic Class I earthquake loads.
FPDS
Fuel Pool clarity is maintained by the FPDS. The FPDS consists of submerged
underwater units which will be operated as required to minimize fission product
concentration and maintain water clarity through demineralization and filtration.
VYNPS DSAR Revision 1 3.0-46 of 87
Fuel Pool Makeup and Letdown
Makeup to the pool is supplied by the Torus-as-CST System.
Water may be removed from the fuel pool, if required, via letdown to the Torus.
Fuel Pool Skimmers
Two skimmer pumps are provided which take suction from the top of the pool to remove
surface debris. These pumps circulate fuel pool water through cartridge filters and
return it to the pool through service boxes located around the pool.
SFPCS
The SFPCS functions to maintain pool temperature within specified limits.
An administrative limit of 125°F has been established for maximum fuel pool
temperature during normal cooling and filtering.
The operating temperature of the fuel pool is permitted to rise up to 25°F above the
administrative temperature limit (125°F) as specified in applicable procedures.
The SFPCS is a two train, Seismic Class I, non-safety related system, designed to be
remotely placed in operation from the control room. The SFPCS circulates the pool
water in a closed loop, taking suction from the spent fuel storage pool, through
heat exchangers and discharging the water back into the fuel pool. The SFPCS heat
exchangers transfer the spent fuel decay heat to the seismic Class I, non-
safety-related Station Service Water System (SWS).
The SFPCS includes two seismic Class I centrifugal pumps. All the parts of the pump
in contact with water are corrosion-resistant. A pump low discharge pressure alarm
annunciates in the Control Room. In addition, the pumps trip automatically on low
suction pressure.
The heat exchangers are shell and tube design; all parts in contact with water are
corrosion resistant. These heat exchangers are each sized to maintain fuel pool
water temperature below 150°F.
VYNPS DSAR Revision 1 3.0-47 of 87
To minimize the potential for fuel pool water leakage into the Station SWS, service
water pressure is normally maintained greater than SFPCS pressure. The fuel pool water
side of the heat exchangers has a maximum operating pressure equivalent to the static
pressure head from the pool surface to the heat exchanger. The Station SWS side of the
heat exchangers has a minimum operating pressure which is normally greater than the
maximum pressure on the fuel pool side of the heat exchangers as long as the operating
SW pumps can maintain system header pressure above the pressure which results in NNS SW
header isolation valve closure. During events which result in low service water header
pressure, service water pressure may be lower than SFPCS pressure until the SW header
isolation valves are closed. By maintaining a positive differential pressure, leakage
of fuel pool water to the environment is prevented. The differential pressure across
each heat exchanger is monitored by a differential pressure sensor and displayed in the
control room.
Two motor operated throttling valves, V70-257A and 257B, provide service water flow
control through the respective SFPCS heat exchanger to control both pool temperature
and service water to SFPCS differential pressure.
Two motor operated isolation valves, V19-220 and 221, close on low pool level,
providing automatic pool isolation in case of a line break in the non-seismic
portion of the system.
SFPCS heat exchanger supply and return service water piping and SFPCS piping is
corrosion-resistant. The piping meets the requirements of ANSI B31.1-77.
Indication is provided in the control room and/or locally near the equipment.
Control Room indication for each train includes direct pool temperature, fuel pool
water temperature out of the heat exchangers (taken downstream of the pumps), pump
run lights, pump discharge pressures, service water flow, SWS to SFPCS heat
exchanger DP and valve position lights. Local indication includes fuel pool water
temperature into the heat exchangers, pump suction and discharge pressures, and heat
exchanger DP. Pool temperature is provided by redundant thermocouples located
within the pool. Pool level is provided by redundant transmitters located near the
pool. All other transmitters and sensors are located in or near the Fuel Pool
Cooling System cubicle.
Controls for the pumps and four MOVs are provided in the control room. Control room
controls include pump on/off switches, service water throttle valves control
switches, and V19-220 and V19-221 isolation valves control switches.
VYNPS DSAR Revision 1 3.0-48 of 87
3.3.1.3.4 Evaluation
The SFPCS has a heat removal capability of 11 MBtu/hr with one pump and one heat
exchanger in service, and 22 MBtu/hr with both pumps and heat exchangers in service
(assuming 2% plugging).
Both trains of the SFPCS in operation have sufficient capacity to maintain fuel pool
temperature within specified limits with the maximum number of fuel assemblies in
the pool after a full core offload. Under these conditions, after a period of
approximately 40 days of fuel decay time following reactor shutdown, one train of
the SFPCS has sufficient capacity to maintain fuel pool temperature within specified
limits.
3.3.1.3.5 Inspection and Testing
The SFPCS is normally in operation during all modes of facility operation.
Satisfactory operation is demonstrated continuously without the need for special
testing or inspection.
3.3.1.4 Tools and Servicing Equipment
3.3.1.4.1 Objective
To provide and use tools and servicing equipment in a way that ensures the bounds of
the design basis fuel handling accident are not exceeded.
3.3.1.4.2 Design Bases
1. The refueling platform shall withstand a seismic event without gross failure or
overturning.
2. Fuel handling equipment shall be classified in accordance with its potential
for damaging irradiated fuel.
3. Equipment weighing more than 700 pounds shall be classified as a heavy load and
handled in accordance with appropriate facility procedures.
3.3.1.4.3 Description
3.3.1.4.3.1 Introduction
All tools and servicing equipment necessary are supplied for efficiency and safe
serviceability. The following is a listing of tools and servicing equipment.
VYNPS DSAR Revision 1 3.0-49 of 87
Tools and Servicing Equipment
Quantity
Fuel Servicing Equipment
Fuel Preparation Machines 2 Channel Bolt Wrenches 2 Channel Handling Tool 1 Fuel Inspection Fixture 1 Channel Gauging Fixture 1 General Purpose Grapples 3 Channel Transfer Grapple 1 Fuel Pool Gates 2 Channel Handling Boom 1 Servicing Aids
Actuating Poles 3 General Area Underwater Lights 4 Local Area Underwater Lights 4 Drop Lights 4 Underwater TV Monitoring System 1 Underwater Vacuum Cleaner 1 Viewing Aids 4 Light Support Brackets 4 Jib Cranes 2 Refueling Equipment
Refueling Equipment Servicing Tools 1 Refueling Platform, main fuel grapple and contents 1
Storage Equipment
Control Curtain Transfer Basket 1 Spent Fuel Storage Racks 11 Channel Storage Rack 1 Control Rod Blade Storage Rack (30 Cavities per Rack) 1 Defective Fuel Storage Containers 8
3.3.1.4.3.2 Fuel Servicing Equipment
Two fuel preparation machines are used to remove the channels from and install
channels on fuel assemblies. These machines are designed to be removed from the
pool for servicing. A channel transfer grapple is provided for inserting or
withdrawing channels from storage racks.
VYNPS DSAR Revision 1 3.0-50 of 87
An equipment support railing is provided around the pool periphery in order to tie
off miscellaneous equipment such as the fuel leak detector (sipper) and service
tools. Equipment lugs fabricated as part of the pool liner are required for
fixtures that might later be desired by facility personnel. In addition, a
4 x 4-inch curb with a 4-inch wide plate of 1-inch thick stainless steel on top is
provided around the entire periphery of the refueling volume. The plate provides a
suitable welding and drilling surface for mounting additional equipment. The curb
may be used as an additional support or tie-off area. Cable ways are recessed into
the floor around the pool periphery with openings to pass cables into the pool from
underneath this curbing.
A number of different grapples are available at Vermont Yankee for use during
maintenance activities. Grapples can be attached to the Reactor Building auxiliary
hoist, or the auxiliary hoists on the refueling platform. Grapples can be used to
shuffle fuel in the pool and to handle fuel during channeling.
A channel-handling boom with an electric hoist is used to assist the operator in
supporting the weight of a channel after the channel is removed from the fuel
assembly. The boom is set between the two fuel preparation machines. With the
channel-handling tool attached to the hoist, the channel may be conveniently moved
between the fuel preparation machines.
3.3.1.4.3.3 Servicing Aids
General area underwater lights are provided with a suitable reflector for general
downward illumination.
A portable underwater vacuum cleaner is provided to assist in removing crud and
miscellaneous objects from the pool floor. The pump and the filter unit are
completely submersible for extended periods.
3.3.1.4.3.4 Fuel Handling Equipment
The refueling platform is used as the principal means of transporting fuel
assemblies in the storage pool. The platform travels on tracks extending along each
side of fuel pool. The platform supports the main hoist and fuel grapple and two
auxiliary hoists. The grapple is suspended from a trolley system that can traverse
the width of the platform. Platform operations are controlled from either the
operator station on the trolley or auxiliary stations on the auxiliary hoist control
boxes. Refueling grapple operation and platform movement are controlled through a
Programmable Logic Controller (PLC). The PLC also limits platform velocity and
movement when the grapple is in close proximity to the perimeter of the storage
pool. A Personal Computer (PC), which is also part of the system, implements the
optional automatic mode of operation to allow a preprogrammed series of platform
movements corresponding to planned fuel assembly moves. The platform contains a
position-indicating system that indicates the position of the fuel grapple.
VYNPS DSAR Revision 1 3.0-51 of 87
Mounted on both the reactor well side of the refueling platform and on the platform
trolley monorail are one-half-ton auxiliary hoists. These hoists normally can be
used with appropriate grapples to handle control rods, detectors, sources, and other
equipment. The auxiliary hoist can also serve as a means of shifting fuel elements
and other equipment within the pool.
All motions of the platform required to handle fuel assemblies may be controlled
from a single location.
3.3.1.4.3.5 Storage Equipment
A channel storage rack is located between the fuel preparation machines to permit a
logical work flow during channeling and de-channeling operations.
Racks are arranged so that fuel assemblies and control rod blades can be
conveniently positioned for storage. The racks can be removed without draining the
pool to allow inspection or replacement, should it become necessary. Capacity is
provided for a maximum of 38 control rod blades. One CRB storage rack provides a
capacity of 30 and one spent fuel storage rack provides an optional capacity of
eight.
3.3.1.4.4 Evaluation
The refueling platform can withstand a seismic event without gross failure or
overturning.
The safety classification of fuel handling equipment and tools is determined based
on their potential for damaging irradiated fuel and, as a result, exceeding
appropriate radiological dose criteria. Equipment weighing more than 700 pounds is
classified as a heavy load and is handled in accordance with Reference 4.
The design basis fuel handling accident is discussed in the Station Safety Analysis
Section of the DSAR.
3.3.1.5 References
1. NUREG-1738, “Technical Study of Spent Fuel Pool Accident Risk at Decommissioning
Nuclear Power Plants”
2. Regulatory Guide 1.174, "An Approach for Using Probabilistic Risk Assessment In
Risk-Informed Decisions on Plant-Specific Changes to the Licensing Basis”
3. BVY 14-009, Request for Exemptions from Portions of 10CFR50.47 and 10CFR50,
Appendix E.
4. PP 7023, “Control of Heavy Loads Program Document”
VYNPS DSAR Revision 1 3.0-52 of 87
Vermont Yankee
Defueled Safety Analysis Report
Fuel Storage-Arrangement
Figure 3.3.1-1
VYNPS DSAR Revision 1 3.0-55 of 87
Vermont Yankee
Defueled Safety Analysis Report
Fuel Storage Rack Assembly
(Partial)
Figure 3.3.1-4
VYNPS DSAR Revision 1 3.0-56 of 87
Vermont Yankee
Defueled Safety Analysis Report
HOLTEC Fuel Storage Rack Assembly
(Partial)
Figure 3.3.1-5
VYNPS DSAR Revision 1 3.0-57 of 87
3.3.2 Service Water System
3.3.2.1 Objective
The objective of the Service Water System (SWS) is to provide water from the
Connecticut River for spent fuel pool cooling and other miscellaneous services.
3.3.2.2 Design Bases
The design bases of the Station SWS are:
1. To provide water for spent fuel pool cooling.
2. To minimize the probability of a release of radioactive contaminants to the
environs by monitoring the system discharge and maintaining sufficient
pressures at specific areas in the system.
3.3.2.3 Description
The flow diagram for the SWS is shown on Drawing G-191159, Shs. 1 and 2.
Two pumps located in the intake structure are provided to supply the SWS
requirements. The pumps are normally started and stopped by controls on the main
control board. With a design river water temperature of 85°F, one of the two pumps
is required to supply normal station cooling demands. Operating pumps will
continue to run until stopped from the Main Control Room.
The SWS is a dual header system using two parallel 24-inch supply headers. Two
automatic self-cleaning strainers, for removal of suspended matter from the river
water, serve the headers. The headers include cross-connect lines 20"SW-3, 3"SW-28
and 3"SW-28A, and 24"SW-8. Normally, the valves in the interconnecting lines are
open, permitting either pump to supply the cooling water through both strainers and
headers. In the event of a major malfunction in either header, it is possible to
isolate the portion of the system affected (using electrically-operated valves V70-
19A and 19B in line SW-8 and manual valves in the other cross-connect lines) and
maintain all essential cooling water services.
VYNPS DSAR Revision 1 3.0-58 of 87
A pressurizing line to the Fire Water System and water for the Chlorination System
is supplied from lines tied into both headers. There is also a line, 12"SW-4A,
tying into the Fire Water System that can be supplied from either header. This
line contains a manual valve that is maintained closed and can only be opened under
specific procedural direction. The SFPCS heat exchangers and the water for the
backwash function of the traveling screens are supplied from the "B" service water
header.
The SWS discharges to the cooling tower deep basin.
A process radiation monitor is located in the station service water discharge
header. To prevent the release of radioactivity from the SFPC System to the SWS,
the system is designed such that the fuel pool side of the heat exchangers has a
maximum operating pressure equal to the static head developed by the difference in
elevation between the heat exchanger and the fuel pool surface. The minimum
operating service water pressure is normally greater than the pressure in the fuel
pool side of the heat exchanger. This positive differential pressure in the heat
exchangers will protect against any possible fuel pool water leakage into the
Station SWS.
SWS piping meets code standards, including ANSI B31.1. Those portions of the
Station SWS supplying spent fuel cooling are of Class I seismic design. Other
portions of the system, whose failure due to a seismic event could cause
unacceptable flooding, negatively impact flow to essential equipment, or impact the
ability to establish secondary containment closure, are either isolable via
automatic or manual valves or have been evaluated and determined to meet Class I
seismic requirements.
Vacuum breakers are installed in the following pipe lines to prevent water hammer
when service water flow is restored following a loss: supply line (8" SW-800) to
the standby fuel pool cooling heat exchanger, the supply line to the refuel floor
cooler lines, and the supply line (8" SW-33) to the Control Room chiller.
Operation of these valves will ensure adequate flow to essential components
following the events identified above and will prevent flooding in the Reactor
Building due to a water hammer event.
That portion of the intake structure, which houses the Station SWS equipment, is
Class I seismic design.
VYNPS DSAR Revision 1 3.0-59 of 87
3.3.2.4 Evaluation
Service water piping meets code standards, including ANSI B31.1. Those portions
supplying fuel pool cooling equipment are of Class I seismic design. In addition,
the piping whose failure could (a) cause unacceptable flooding, or (b) negatively
impact flow to essential equipment, or (c) impact the ability to establish
secondary containment closure, is isolable via automatic or manual valves, has been
designed such that loss of water through failed piping is within the capability of
the system, or has been evaluated and determined to meet Class I seismic
requirements. Vacuum breakers have been installed on those pipe lines susceptible
to a water hammer event to ensure adequate flow to essential equipment and prevent
flooding in the Reactor Building. The maximum operating pressure of the service
water within these lines is typically on the order of 110 psig. This piping is
routed in the building such that it is not in the vicinity of any heavy equipment
movement during maintenance nor in the vicinity of vehicle traffic, and therefore,
is not vulnerable to damage from collisions.
Based upon the above discussion, it is highly improbable that the piping could fail
in such a manner as to cause flooding or interrupt SWS flow for spent fuel pool
cooling.
Maintaining a positive differential pressure between the service water side and the
fuel pool side of the SFPC heat exchanger protects against any possible fuel pool
water leakage into the SWS.
3.3.2.5 Inspection and Testing
The Station SWS is normally in operation during all modes of station operation.
Satisfactory operation is demonstrated continuously without the need for special
testing or inspection.
3.3.3 Electrical Power Systems
3.3.3.1 Transmission System
3.3.3.1.1 Objective
The objective of the Transmission System is to provide reliable power from off-site
to the facility Auxiliary Power System to facilitate the safe storage and handling
of irradiated fuel.
VYNPS DSAR Revision 1 3.0-60 of 87
3.3.3.1.2 Design Basis
The Transmission System provides a reliable source of power from off-site to the
facility to facilitate the safe storage and handling of irradiated fuel.
3.3.3.1.3 Description
There are two 345 kV switchyards and two 115 kV switchyards on site at VY. The
original 345 kV and 115 kV switchyards are now called the VY switchyards. New
Vernon 345 kV and Vernon 115 kV switchyards were installed by Vermont Electric
Power Company (VELCO) as part of their Southern Loop Project. These two
switchyards are on VY property north of the existing VY switchyards.
The VY 345 kV switchyard consists of four circuit breakers in a ring bus
configuration as shown on Drawing G-191298, Sh.3.
Electric power is supplied from off-site via the transmission network to the
on-site electric distribution system through either of two 345 kV/115 kV
autotransformers to the VY 115 kV switchyard. The VY 115 kV switchyard powers the
station startup transformers.
A portion of the 345kV system, utilized for power generation, has been abandoned.
The VY 345 kV switchyard north bus powers a 400 MVA autotransformer which supplies
power to the VY 115 kV switchyard.
The Vernon 115 kV switchyard supplies a second source of normal power to the VY 115
kV switchyard via a K-40 tie line to a second autotransformer.
The auto-transformers are operated in parallel; the loss of either source will not
cause the VY 115 kV switchyard to lose power.
An alternate circuit through the 115 kV K-186 transmission line may be made
available.
A 13.2 kV underground power line runs from the adjacent Vernon Hydroelectric
Station (VHS) to a 13.2-4.16 kV transformer near the cooling towers. From there, a
4160 V underground power line connects to the Station Blackout (SBO) Diesel
Generator (DG) switchgear and then goes on to the station switchgear. The SBO DG
or the VHS can be connected to selected 4160 V buses through manually operated
circuit breakers.
VYNPS DSAR Revision 1 3.0-61 of 87
3.3.3.1.4 Evaluation of System Protection
Transmission system protection design meets the objectives of the Northeast Power
Coordinating Council, "Bulk Power System Protection Criteria."
The two tie lines between the VY switchyards and the Vernon switchyards each have
two redundant and diverse channels of the line differential, directional over-
current line and round impedance protection.
Four 345 kV and one 115 kV transmission lines are terminated in the Vernon
Switchyards. Protection in the Vernon Switchyards for the transmission lines
consists of Primary and Secondary (or backup) protection.
The 345 kV and 115 kV switchyards each have a primary and secondary bus
differential relay system. These systems are independent of one another and the
tripping of one will not cause tripping of breakers in the other substation, with
the exception that the 115 kV secondary side breaker on the 400 MVA autotransformer
will be tripped for a fault on the 345 kV switchyard's north bus.
In the unlikely event that the two sources to the 115 kV primary of the station
startup transformers, that is, the 345/115 kV autotransformer supply from the VY
345 kV switchyard, or the tie line to the Vernon 115 kV switchyard became
disconnected, the Station Blackout Diesel Generator Alternate ac source and the
line to the Vernon Hydroelectric Station, would also be available.
The 115KV switchyard contains three capacitor banks, one 30MVAr bank and two 15MVAr
banks. Each bank has its own breaker connecting it to the 115KV bus. These
breakers are individually controlled by the system operator via SCADA. Phase and
ground overcurrent, unbalance, over-voltage and breaker failure protection is
provided for each bank breaker.
3.3.3.2 Auxiliary Power System
3.3.3.2.1 Objective
The objective of the Auxiliary Power System is to provide a reliable power supply
to all station loads required for the safe storage and handling of irradiated fuel.
3.3.3.2.2 Design Basis
The Station Auxiliary Power System shall have the capacity and capability to supply
the required facility loads. Protective, control, and instrumentation devices
shall be provided to insure reliability and availability of the system.
VYNPS DSAR Revision 1 3.0-62 of 87
3.3.3.2.3 Description
The Station Auxiliary Power System is shown on Drawings G-191299, G-191300, Sh. 1
and 2, G-191301, Sheets 1 and 2. The system consists of six 4160 V buses, which
supply power to all 4000 V motors, and to the 4160-480 V station service
transformers, which supply power to the 480 V buses.
3.3.3.2.3.1 4160 V Switchgear
The normal supply for the 4160 V load is the startup transformers (T-3A and T-3B)
which are supplied from the 345/115 kV Transmission System.
The startup transformers have adequate capacity for all loads required for the safe
storage and handling of irradiated fuel.
The switchgear for the 4160 V Auxiliary System is of the metal-clad indoor type,
except 4160 V Buses 5A and 5B which are outdoor metal-clad units. Circuit breakers
are three pole, air break type, electrically-operated with control power supplied
from batteries.
3.3.3.2.3.2 480 V Buses
480 V auxiliary power is supplied from the 4160 V Auxiliary System through 4160-480
V station service transformers. The 480 V system consists of switchgear buses and
motor control centers.
The 480 V switchgear buses are self-supporting, metal-clad structures with draw-out
circuit breakers.
3.3.3.2.3.3 120/240 V Instrumentation Distribution System
A 120/240 V Single Phase Instrumentation Distribution System supplies selected
instrumentation and other loads. The system consists of the 120/240 V vital ac bus
and its subpanel and the 120/240 V instrumentation distribution panel and its
subpanels.
The bus arrangement is shown on Drawing G-191372, Sheets 4 and 5.
VYNPS DSAR Revision 1 3.0-63 of 87
3.3.3.2.4 Cable Installation and Separation Criteria
1. Intermixing of Cables
Low-level instrumentation cables are routed in separate trays from control
cables.
The definition of "low level instrumentation cable" is:
A cable used for data, control, or instrumentation service. In
general, this service includes cable from thermocouples, resistance
temperature detectors, process instruments, and computer signals. As a
general rule, anything less than 50 V is considered low level.
The definition of "control cable" is:
A cable used for control, metering, relaying, and alarm circuits. In
general, these services include 125 V dc and 120 V ac control leads,
annunciator cables, PT cables, CT cables, and solenoid cables.
The following exception to the criteria for intermixing cables has been
justified as acceptable:
1. Instrumentation cable which only provides a Control Room indication function
may be run in the same tray as control cable.
2. Tray Loading and Cable Sizing
The general rules of 50% derating outside the drywell area was used in calculating
power cable sizes. The following design conditions were considered in arriving at
the 50% derating criteria for cables in tray: (1) load factor, (2) tray loading,
(3) short circuit capacity of cable, (4) ambient temperature, (5) grouping factor,
and (6) voltage drop.
For cable tray loading, the design is based on the IPCEA Code Bulletin
No. P-46-426, 1962.
For cables that are not routed in tray, derating is based on ampacities taken from
the appropriate tables in the IPCEA Code Bulletin No. P-46-426, 1962, which are a
function of the number of conductors in the conduit or duct bank.
VYNPS DSAR Revision 1 3.0-64 of 87
3. Fire Protection Criteria
The criteria used for fire protection of cable installations are as follows:
Fire stops are provided in vertical tray runs at Reactor Building fire zone
boundary designations.
In areas other than the cable vault, tray covers are utilized on cable trays to
prevent fire from migrating from tray to tray in a vertical bank.
In the area where a high concentration of cables exists, such as the cable vault,
an automatic Fire Protection System is provided; and flame resistant cable
constructions are used to minimize the propagation of fire along horizontal runs of
cable trays. Cable tray covers are not used in the cable vault except where
required to achieve physical separation. This allows fire extinguishment by the
Fire Protection System or by manual means.
3.3.3.2.5 Inspection and Testing
Periodic equipment tests are performed at scheduled intervals to detect any
deterioration of the system towards an unacceptable condition. The specific tests
and the frequency at which they are performed depend upon the specific components
installed, their function, and their environment.
3.3.3.3 Deleted
3.3.3.4 125 V DC System
3.3.3.4.1 Objective
The objective of the 125 V DC System is to provide a supply of 125 V dc power for
the operation of equipment.
3.3.3.4.2 Design Basis
The 125 V DC System shall consist of two dc systems, each capable of supplying its
required loads.
VYNPS DSAR Revision 1 3.0-65 of 87
3.3.3.4.3 Description
Two 125 V dc systems are provided to supply the station 125 V dc loads. One system
includes Main Station Battery A-1. The second system includes Main Station Battery
B-1. Each battery is of the central power station type, designed for continuous
duty at an operating voltage of 125 V dc.
Main Station Batteries A-1 and B-1 are located in the Reactor Building.
Each main station battery has a pair of constant voltage, current limiting
silicon-controlled rectifier type battery chargers, which are capable of supplying
normal continuous dc load and maintaining a float charge on the battery. Each
charger is also capable of recharging its associated battery to full charge if it
should become discharged to its minimum voltage.
The redundant distribution divisions of the 125 V dc systems are designated as the
DI and DII divisions. Division DI includes Distribution Panels DC-1, DC-1A, DC-1B,
and DC-1C connected to Main Station Battery A-1. Division DII includes
Distribution Panels DC-2, DC-2A and DC-2C connected to Main Station Battery B-1.
Distribution Panel DC-2D is powered from DII power supply DC-2.
Manual transfer switches are installed to provide a backup supply of power to
selected panels. Use of the transfer switches is administratively controlled by
procedure and limited to emergency situations or planned maintenance per
administrative control. Panel DC-3 is normally fed from Panel DC-2, but can be
connected to an alternative feed from Panel DC-1, by means of a manual transfer
switch. Other dc panels with manual transfer switches are DC-2A and DC-3A which
also have alternate feeds. The electrical arrangement of the batteries, chargers,
buses and switchgear is shown on Drawing G-191372, Sheets 1, 2 and 3.
The batteries, panels, and power feeds associated with Division DI are physically
isolated from the batteries, panels, and power feeds associated with Division DII
by a minimum of 15 feet. Where distribution circuits are separated by less than 15
feet, the cables are routed in rigid steel conduits, flexible steel conduits, or
enclosed in steel wireways.
The DC System is ungrounded and has a ground detection alarm system.
VYNPS DSAR Revision 1 3.0-66 of 87
3.3.3.4.4 Evaluation
During normal operation, the continuous dc load is supplied by the battery chargers
which are connected to the dc buses. The batteries normally float on the system,
supplying any momentary high current control requirements. Upon loss of a charger,
the associated battery supplies its total dc load requirements. The normal ac
sources for the battery chargers are the 480 V emergency buses. These buses are
energized through transformers by normal auxiliary ac power.
Feeders from redundant dc sources are provided to control circuits for the 4160 V
bus switchgear (except for buses 4, 5A and 5B), and for certain 480 V emergency bus
switchgear and 125 V dc distribution panels. These alternate feeders are connected
through manual transfer switches such that only one dc source can be connected at a
time.
The Main Station Batteries A-1 and B-1 are located on elevation 318' of the Reactor
Building. Analysis assumes that the Reactor Building temperature will be
maintained at >40°F.
The accumulation of hydrogen from the batteries would not exceed 4% concentration
with an assumed complete loss of Reactor Building Ventilation.
3.3.3.4.5 Additional DC Systems
In addition to the above dc systems, two 125 V DC Systems in each of the switchyard
control houses which provide power for breaker operation and control and protective
relaying circuitry.
3.3.3.4.6 Inspection and Testing
The batteries and other equipment associated with the 125 V DC System are easily
accessible for inspection and testing. Service and testing is performed on a
routine basis in accordance with approved station procedures/programs. Typical
periodic inspections will include visual examination for leaks and corrosion, and
check of all batteries for voltage, specific gravity of electrolyte, and
electrolyte level.
3.3.3.5 24 V DC Power System
3.3.3.5.1 Objective
The objective of the ±24 V DC Power System is to provide a supply of ±24 V DC power
for the operation of various process radiation monitoring instrumentation.
VYNPS DSAR Revision 1 3.0-67 of 87
3.3.3.5.2 Design Basis
The ±24 V DC Power System shall supply all ±24 V dc power requirements.
3.3.3.5.3 Description
A single ±24 V dc system is provided for operation of various process radiation
monitoring instruments. The system is a single channel system with no automatic or
manual transfer.
The ±24 V dc system consists of two 24 V dc power supplies connected to produce a
single ±24 V dc supply. The rating of each power supply is the same and is based
on the maximum load required by the process rad monitoring instrumentation.
The ±24 V dc system is fuse protected from high input or output current. Any
indication of a failure of the ±24 V dc power supply will be annunciated by the
associated rad monitors downscale/trouble alarms.
3.3.3.5.4 Inspection and Testing
The components of this system are inspected and tested in accordance with approved
station procedures/programs.
3.3.4 Fire Protection System
3.3.4.1 Objective
This system is designed to provide fire protection for the station through the use
of water; CO2; FM-200; dry chemicals; detection and alarm systems; and rated fire
barriers, doors, and dampers.
3.3.4.2 Design Basis
The Fire Protection System shall prevent propagation of fire and isolate the areas
of the fire by:
1. Providing a reliable supply of fresh water for firefighting purposes.
2. Providing a reliable system for delivery of the water to potential fire
locations.
3. Providing automatic fire detection in those areas where the danger of fire is
more pronounced.
VYNPS DSAR Revision 1 3.0-68 of 87
4. Providing fire extinguishment by fixed equipment activated automatically or
manually in those areas where danger of fire is most pronounced.
5. Providing manually operated fire extinguishing equipment for use by station
personnel at selected locations.
6. Providing means to isolate areas so that fires are prevented from propagating
from one area to another.
3.3.4.3 Description
The Vermont Yankee Fire Protection Program makes use of detection and suppression
systems, separation criteria, rated fire barriers and seals, fire stops, procedures
and fire watches, standpipe hose connections, and training.
The fire protection program for the permanently defueled state has been developed
based on the applicable requirements of 10CFR50.48 and BTP APCSB 9.5-1, Appendix A.
The Fire Hazards Analysis (FHA) documents existing plant configurations and defines
the resources available for the prevention and limitation of damage from fire
(Reference 1). In addition to plans and physical configurations for fire
protection, fire detection, fire suppression and limitation of fire damage, the FHA
also provides an overall description of the fire protection program.
The Fire Protection System is illustrated on Drawing G-191163, Sheets 1 and 2.
Water-type fire protection equipment has been limited in those areas where the
potential spread of radioactive contamination due to release of water for the
firefighting would result in more severe consequences than the results of a fire.
Fires in these areas will be primarily fought using portable dry chemical or carbon
dioxide extinguishers.
Water for the Fire Protection System is provided by two vertical turbine-type
pumps, one electric motor-driven and one diesel-driven. Each pump has a capacity
of 2,500 gpm at 125 psi discharge pressure. The pumps and drivers are located in
the intake structure. They discharge to an underground piping system which serves
the exterior and interior Fire Protection Systems.
The motor-driven pump is supplied from a 480 V bus. The diesel engine drive is
approved for fire pump service and is provided with its own fuel oil supply and
starting equipment.
The pressure in the Fire Main System is maintained at approximately 100 psig by an
interconnection to the Service Water System. An orifice in the 1.5 inch
pressurizing line limits pressure maintenance flow from the Service Water System to
30 gpm during normal operation. A check valve in the connecting pipe prevents
backflow.
VYNPS DSAR Revision 1 3.0-69 of 87
Operation of the fire pumps is controlled from pressure switches in the discharge
piping. The motor-driven pump starts at a predesignated system pressure (typically
85 psig). The diesel-driven pump starts if the pressure continues to drop
(typically 75 psig). The motor-driven pump automatically shuts down when the Fire
System pressure is restored to the normal range (typically 100 psig) for
approximately seven minutes. The diesel-driven pump continues to operate until
shut down manually.
The yard piping consists of a 12-inch underground piping loop around the
entire station, with valved branches serving 10 fire hydrants. Valved branches
from the piping loop supply water for interior fire protection purposes.
Sectionalizing valves in the yard piping loop permit isolation of portions of the
loop, without interruption of service to the entire system.
A heat traced and insulated fire protection header in the Turbine Building supplies
an interior Reactor Building loop. This loop services two standpipes and fifteen
standpipe hose connections.
Selected abandoned water suppression deluge valves have retained the connected heat
actuated devices (HADs) for early indication of a fire event in areas which they
were previously installed. These valves are alarmed and signal the control room
fire alarm panel. Furthermore, the remaining turbine building water curtain,
condenser/heater bay and condensate demineralizer storage fire detection systems
were not originally installed to satisfy the requirements of 10 CFR 50.48 or Branch
Technical Position APCSB 9.5-1 Appendix A.
The cable vault and Switchgear Rooms are protected by fully automatic total
flooding CO2 suppression systems. The Cable Vault CO2 suppression system is
initiated by ionization detectors. The Switchgear Room CO2 suppression system is
initiated by ionization detectors coincident with thermal detection. Bottles
located in the West Switchgear Room System may also provide a backup or second shot
to the cable vault if desired. The Diesel Fire Pump Fuel Oil Storage Tank Room is
protected by a total flooding FM-200 suppression system initiated by an ionization
detector coincident with a thermal detector.
The yard loop supplies a wet pipe sprinkler system for the warehouse* and the
house-heating Boiler Room*. These systems are equipped with alarm check valves.
* Not required to satisfy the requirements of 10CFR50.48 or BTP APCSB9.5-1, Appendix A.
VYNPS DSAR Revision 1 3.0-70 of 87
Fire detection devices are provided in areas which are not normally occupied, in
areas where substantial quantities of combustible materials are present, or in
other areas determined to be highly sensitive. These detection systems provide
local and remote alarms, as well as annunciation in the Main Control Room. In some
instances trip signals are provided directly to deluge systems or electrically
operated fire dampers.
Portable fire extinguishers are located throughout the buildings at the site.
Portable fire extinguishers use dry chemical, CO2 and water.
Buildings are constructed of steel and concrete with fire walls and/or shield walls
which isolate separate areas. Consideration has been given to the use of
noncombustible and fire-resistant materials throughout the facility, particularly
in the containment, Control Room, and areas containing critical portions of the
plant.
Fire barriers have been identified and their integrity assured by self-closing
doors (exception: RHR corner room doors at El. 213'-6" are not self-closing),
normally locked doors, alarmed doors, doors checked daily, automatic fire dampers,
and controlled procedures for penetration sealing and fire barrier repair. This
includes the northwest stairwell's ability to function as a fire exit.
Water flow alarms are provided in critical locations and annunciate in the Control
Room to provide positive indication of Fire Water System operation.
3.3.4.4 Inspection and Testing
The fire pumps, water suppression systems, CO2 systems, FM-200 system, fire
barriers, fire doors, fire dampers, detection and alarm systems, and portable
extinguishers are inspected and tested periodically in accordance with approved
station procedures/programs. All equipment is accessible for periodic inspection.
3.3.4.5 References
1. Vermont Yankee Nuclear Power Station Fire Hazards Analysis
VYNPS DSAR Revision 1 3.0-71 of 87
3.3.5 Heating, Ventilating and Air Conditioning Systems
3.3.5.1 Objective
The objective of the Heating, Ventilating, and Air Conditioning Systems is to
provide suitable environmental conditions for facility personnel and equipment.
3.3.5.2 Design Bases
The design bases of the Heating, Ventilating, and Air Conditioning Systems are as
follows:
1. Provide appropriate temperature and humidity conditions for personnel and
equipment.
2. Limit exposure of personnel to airborne contaminants by controlled migration
of air from radioactively clean areas to areas of progressively higher
contamination.
3. Normally, filter outside air to limit the introduction of particulate matter
to the plant. During winter operation, certain filter media may be removed to
prevent freezing.
4. Vent potentially contaminated leakage through systems that exhaust to the
plant stack.
VYNPS DSAR Revision 1 3.0-72 of 87
3.3.5.3 Description
Flow diagrams for the Heating and Ventilation Systems are shown on Drawings G-
191237, Sheet 1 and 2, G-191236, G-19138 and G-191254.
The design temperatures used for the Heating and Ventilation Systems are provided
as follows:
Outdoor
Summer: 90°F dry bulb, 75°F wet bulb
Winter: -12°F dry bulb
Indoor
Reactor Building:
Maximum: 100°F (occupied areas)
Minimum: 65°F (refuel floor)
55°F (occupied areas other than refuel floor)
Control Room and Service Building:
Maximum: 78°F dry bulb, 50% relative humidity
Minimum: 72°F dry bulb
3.3.5.3.1 Reactor Building
The Reactor Building normal Heating, Ventilating, and Air Conditioning System
limits exposure of personnel to airborne contaminants and maintains appropriate
temperature conditions for personnel and equipment.
The Reactor Building normal HVAC System migrates air from clean accessible areas to
areas of progressively higher contamination or potential contamination, removes the
normal heat losses from all equipment and piping in the Reactor Building, limiting
the temperatures to approximately 100ºF, filters outside air to limit the
introduction of airborne particulate matter to the station, and exhausts
potentially contaminated air to the stack. During winter operation, certain filter
media may be removed to prevent freezing.
VYNPS DSAR Revision 1 3.0-73 of 87
The Reactor Building normal HVAC System consists of a supply and exhaust side. See
Drawing G-191238.
The supply side includes in the direction of air flow, outside louvers, automatic
dampers, automatic roll-type filters, steam heating coils, and two double-width
centrifugal fans each sized for the full system capacity of 53,800 cfm. This
capacity provides approximately 1.5 net Reactor Building air changes per hour.
The exhaust side consists of two paralleled single-width centrifugal fans, each
having full system capacity of 55,800 cfm.
The excess of exhaust fan capacity over the supply fan capacity ensures against
building out leakages during normal operation. The main supply and exhaust ducts
penetrate the Reactor Building, each through two butterfly isolating valves in
series. The valves in the main supply duct are powered from different buses. This
is also true of the valves in the main exhaust duct. All four isolating valves
fail closed.
To permit maintenance of one fan while the other is in service without danger of
contamination, an isolation damper is provided at the inlet. Also, an isolation
outlet damper is provided to minimize the possibility of contamination through the
idle fan due to either stack backflow or recirculation from the active fan.
In addition, gravity dampers, i.e., non-return or backdraft dampers, are provided
to prevent reverse flow at all ventilating supply openings for areas having
contamination potential and in all branch exhaust ducts connecting with main ducts
which carry exhaust from areas having contamination potential.
Failure of a gravity damper to operate in a branch exhaust line will not result in
cross contamination. Each branch exhaust line consists of two 100% capacity
exhaust fans, a gravity damper on the discharge side of each fan, and a third
gravity damper in the branch line just prior to entering the main exhaust duct.
With the above arrangement, no backflow will occur through the branch exhaust lines
even in the event a gravity damper fails open and both exhaust fans are
inoperative.
Failure of a gravity damper to operate in a supply line could result in some
cross-contamination only if both redundant branch exhaust transfer fans are
inoperative. This is extremely unlikely.
Axial booster fans, each supported by an automatically cut-in standby unit, are
provided throughout the exhaust system to overcome air circuit losses.
VYNPS DSAR Revision 1 3.0-74 of 87
In general, duct work is of galvanized steel. Duct work under positive pressure
exhausting to the main stack is of welded construction to minimize outleakage.
A purge exhaust fan permits exhausting the drywell or the suppression chamber. The
upstream end of the purge exhaust fan is connected to the Primary Containment
Atmospheric Control System through butterfly valves which are remotely actuated
from the Main Control Room panel.
The downstream end of the purge exhaust fan discharges into the Reactor Building
normal Exhaust System where exhaust fans direct the purged air to the main stack.
All equipment and components are accessible for inspection, adjustment, and
testing. The only moving parts in a backdraft (gravity) damper are pinned joints
and bearings (dry, oil-impregnated porous metal, Teflon, or Zytel).
Proper sequences of operation, as well as correct control point adjustments were
determined during station pre-operational tests to assure conformity to the
requirements and intent of the specifications and drawings.
3.3.5.3.2 Deleted
3.3.5.3.3 Main Control Room
The system serving the Main Control Room is designed to provide summer air
conditioning and heating during the winter.
The Supply System has a 12,500 cfm capacity and includes, in the direction of flow,
a wall louver, automatic outside air damper, filters, chilled water cooling coil,
steam heating coil, centrifugal fan section, a system of duct work, and air
outlets.
The Supply System chilled water coil is serviced by a double circuit refrigeration
plant to assure continuity of cooling. Refrigeration plant components are one
double circuit water chiller with a chilled water pump, two air-cooled condensers,
piping, and controls. A separate air-cooled chiller unit was installed to provide
equivalent or better primary, or backup, cooling for the Control Room.
A remote manual switch located in the Main Control Room permits closure of the
outside air damper, Control Room kitchen and bathroom exhaust dampers, and Computer
Room supply damper, in order to isolate the Control Room, if required.
VYNPS DSAR Revision 1 3.0-75 of 87
SAC-1, which supplies the Control Room, contains a humidifier in the air supply
duct after the Computer Room duct. This unit is controlled by a humidity sensor in
the Control Room and has an alarm for high humidity level.
Upon a loss of the Control Room Ventilation System the SAC 1A/B dampers could fail
to the closed position. Operator actions, including manual control of appropriate
dampers, can be taken to restore system flow as discussed in plant procedures
The Control Room can be isolated by manually closing the fresh air inlet branch
damper, cable vault damper, and Control Room vent paths. This also puts the
Control Room ventilation in the recirculation mode of operation.
3.3.5.3.4 Service Building
The original portion of the Service Building is entirely air conditioned by an air
handling unit having 15,000 cfm capacity and which in the direction of flow,
consists of dampers, mixing box, filters, a chilled water cooling coil, and a fan
section. Electric zone reheat coils compensate for cooling load variations in
different areas.
The chilled water coil is served by a service water-cooled package chiller and
chilled water pump.
Air from spaces having potential contamination, such as the chemistry laboratory,
is not recirculated back to the air handling unit -- it is directly exhausted to
the plant stack by one of two full capacity fans.
The added portion of the Service Building on the north side is cooled and
ventilated by packaged units on the roof. Makeup and exhaust is local at each
unit. Heat is from the house boilers.
3.3.5.3.5 Deleted
3.3.5.3.6 Heating Boiler System
Drawing G-191254 shows the process flow diagram for the Station Heating Boiler
System. The Heating Boiler System is designed to provide a source of steam for
space heating and process requirements.
Each of the two boilers is rated for approximately 50% of the calculated heating
load.
All pressure containing parts have been designed to the ASME Boiler and Pressure
Vessel Code, Section I.
VYNPS DSAR Revision 1 3.0-76 of 87
The boiler plant consists of two forced draft, four pass, 50% capacity, No. 2
oil-fired fire tube boilers, supplemented by a condensate return tank and three
cross-connected 50% capacity feedwater pumps. Each boiler is equipped with a
locally mounted control panel. Indicating lights will show "flame failure," "low
water," "fuel valve open," and "load demand."
Also provided is a Fuel Oil Pumping System, blowdown tank, and remotely located
condensate pump, receiver sets, Sampling System, and Chemical Addition Systems.
The Station Heating Boiler System is located in the south end of the Turbine
Building. The heating boiler feedwater is monitored by a process liquid radiation
monitor (see Drawing G-191254).
The unit is equipped with the necessary controls and safety devices to operate
automatically. The combustion safety control is provided with a safety lockout in
the event of flame failure or failure to start, which requires manual reset before
the automatic cycling can continue. The draft fan controls are interlocked with
the burner controls to prevent operation of the burner under improper draft
conditions. The flame requirements are designed to meet FIA and NEPIA
requirements.
3.3.5.3.7 Deleted
3.3.5.4 Inspection and Testing
All equipment and components are accessible for inspection, adjustment, and
testing.
Absolute particulate filters will be factory tested with 0.3 micron monodisperse
thermally generated dioctyl phthalate (DOP) aerosol. Minimum acceptable efficiency
is 99.97% as measured by a light-scattering photometer.
To assure that gaskets and seals are properly installed and that no damage has
occurred to the filter during shipment or handling, in-place tests using a
polydisperse cold generated aerosol will be performed initially and then
periodically as required.
3.3.6 Instrument and Service Air Systems
3.3.6.1 Objective
The objective of the Instrument and Service Air Systems is to provide the station
with the compressed air requirements for pneumatic instruments and controls and
general station services.
VYNPS DSAR Revision 1 3.0-77 of 87
3.3.6.2 Design Basis
The Instrument and Service Air Systems shall provide the plant with a continuous
supply of oil-free compressed air. Dry air shall be supplied to plant instruments
and controls as required. Undried air shall be provided for various station
services.
3.3.6.3 Description
The Compressed Air Systems are shown on Drawing G-191160, Shs.1 through 8. The
systems include nonlubricated air compressors connected in parallel, each with a
built-in intake filter-silencer, after-cooler, and moisture separator. The
compressors discharge to two vertically mounted air receivers.
Each compressor will function in either the lead or lag mode. Normally,
compressors which are selected to the Lead position will maintain pressure between
100 and 105 psi. The compressors which are in the lag position will start when
header pressure drops to a predetermined value below the normal operating range.
If the backup compressors run unloaded for a preset period of time, they will
automatically shut down and remain shutdown unless header pressure drops to the
predetermined value.
Separate piping is provided at the discharge of the air receivers for the
Instrument Air System and the Service Air System. The compressed air of the
Instrument Air System passes through two parallel branches both of which contain
the following equipment:
1. Prefilter - This unit filters the air to remove moisture droplets, particles
of dirt, rust, and scale of approximately 3 microns and larger through the use
of automatic traps.
2. Dryer - This unit regenerates (dries out) its desiccant by a heater-less
pressure-swing process. Each dryer is sized to provide 450 SCFM.
3. After Filter - This unit, like the prefilter, filters the air to remove
moisture droplets, particles of dirt, rust, and scale of approximately
3 microns and larger.
The Service and Instrument Air Systems meet all appropriate seismic criteria.
All original piping is designed in accordance with USAS B31.1, 1967. The air
compressor discharge piping to Valve V72-2B is designed to USAS B31.1, 1977.
VYNPS DSAR Revision 1 3.0-78 of 87
The Service and Instrument Air Systems are designed to operate at a pressure of 100
psig and supply 322 scfm ±5% compressed air with one compressor operating.
3.3.6.4 Inspection and Testing
The Instrument and Service Air Systems are normally in continuous operation.
Satisfactory performance of these systems is demonstrated continuously without the
need for any special inspection or testing.
3.3.7 Process Sampling
3.3.7.1 Objective
The process sampling systems provide representative samples for analysis.
3.3.7.2 Design Basis
The sampling systems shall be designed to ensure accuracy and sensitivity of
measurement of process fluids.
3.3.7.3 Description
3.3.7.3.1 General
For flow diagrams of the station liquid sampling system, refer to Drawings G-191164
and G-191165.
Fluids and gases are sampled continuously or periodically from selected equipment
or systems. Samples are taken either as grab samples or continuously. Grab
samples are taken from the collection area to the laboratory for analysis. The
continuous samples pass through analyzers and the results are recorded.
The following table lists the description, location, and purpose of the various
monitoring points associated with sampling process fluids as appropriate.
VYNPS DSAR Revision 1 3.0-79 of 87
3.3.7.3.2 Radwaste Building Sample Panel
This panel includes conductivity elements, conductivity indicating transmitters,
and individual grab sample connections with the outlets enclosed in a hooded sink
provided with exhaust ventilation.
3.3.7.3.3 Gas Sampling and Monitoring
A list of gas samples, their locations, and purpose is provided below.
Description Location Purpose
Stack sample Stack Particulate and gaseous activity
Ventilation gases a) Reactor Building b) Radwaste Building
Fan discharge Fan discharge
Activity release Activity release
The capability exists to sample the ventilation gases, but these locations are not routinely sampled. The fan discharges from the Reactor Building and the Radwaste Building are routed to the stack which is sampled continuously. 3.3.8 Deleted
Description Location Purpose
Waste disposal a) Waste surge tank b) Waste collection tank c) Floor drain collection
tank d) Chemical waste tank e) Waste sample tank f) Floor drain sample tank g) Fuel pool filter
demineralizer influent h) Fuel pool filter
demineralizer effluent i) Floor drain filter
effluent j) Waste filter
demineralizer k) Waste demineralizer
Outlet pipe Pump discharge Pump discharge Pump discharge Pump discharge Pump discharge Inlet pipe Outlet pipe Outlet pipe Outlet pipe Outlet pipe
Process data Process data Process data Process data Discharge suitability Discharge suitability Fuel pool quality Filter demineralizer efficiency Filter efficiency Filter demineralizer efficiency Demineralizer efficiency
Makeup a) Condensate storage tank
Pump discharge
Water quality
VYNPS DSAR Revision 1 3.0-80 of 87
3.3.9 Lighting Systems
3.3.9.1 Objective
The lighting system provides adequate lighting in all areas of the facility where
lighting is required.
During loss of power, the lighting in all areas essential to the safe storage of
irradiated fuel is provided by the following lighting systems:
1) The emergency lighting system - dc supplied.
2) Local emergency lights with self-contained rechargeable batteries.
3.3.9.2 Design Basis
The lighting systems shall provide adequate lighting for the safe storage of
irradiated fuel under all conditions.
3.3.9.3 Description
The safe storage and handling of irradiated fuel requires that adequate lighting be
available for the operation, control, and maintenance of equipment.
Buses which supply power for lighting are normally powered from the startup
transformers. Upon a loss of normal power, the buses are manually powered from a
standby ac power source, thereby restoring normal lighting.
Critical areas and access routes are illuminated by DC lighting during the power
transition.
Portable, battery-operated lighting fixtures are available to permit maintenance of
standby power sources. They are located at the standby ac supply equipment. These
units are wall-mounted and are connected to normal ac circuits which keep the
self-contained batteries in a fully charged condition. Upon loss of ac, the lights
automatically become lighted, using the self-contained batteries as a source.
In the control room, battery-operated emergency lights are available. These units
are wall mounted with remote lights mounted in the ceiling panels and are connected
to a normal emergency ac circuit. Upon the loss of the normal emergency circuits,
the lights automatically become lighted using self-contained batteries as a source.
VYNPS DSAR Revision 1 3.0-81 of 87
The level of lighting intensity is consistent with the nature of the work likely to
be performed for maintenance and operation upon loss of normal ac power. Under
conditions where standby sources of power are limited, a minimum level of lighting
intensity is maintained in the egress routes from the main control room and other
areas, as necessary.
3.3.9.4 Inspection and Testing
Normal lighting is used continuously. Emergency lighting systems are periodically
tested to check operation of standby sources. Portable lighting sets are tested
periodically to demonstrate their functional performance.
3.3.10 Communication Systems
3.3.10.1 Objective
The objective of the communications system is to provide a reliable, convenient,
and audible communication system which meets the requirements of facility operation
and maintenance.
3.3.10.2 Design Basis
The communications system shall consist of an intra-site operation and public
address system, a sound-powered telephone system, a dial telephone system, an
inter-site communication system, and an off-site radio communication system. To
ensure continued intra-site and off-site communications, power for these systems
shall be provided from the vital ac bus.
VYNPS DSAR Revision 1 3.0-82 of 87
3.3.10.3 Description
The communications system consists of several types of communication media
including intra-site operation and public address communication, sound-powered
telephone communication, dial telephone communication, inter-site microwave
communication, and off-site radio communication.
The function of the communications system is to permit convenient and dependable
communications between all areas of the facility vital to operation and maintenance
and protection of personnel. The systems are as follows:
1. Intra-Site Operation and Public Address System
This system consists of speakers and microphones located throughout the
facility.
The system has four transistorized channels and provides separate and
independent page and party line channels. The page channel may be used to call
personnel over the speakers as well as issue facility-wide instructions. The
party line channels may be used to carry on inter-communication after the page
call is completed, thereby making the page channel available to others.
Simultaneous conversations can take place, one on each of the channels, without
interference. The system has an output adequate to be clearly audible in all
appropriate facility areas.
2. Sound-Powered Telephone System
This system allows private communications between specific areas and pieces of
equipment for maintenance purposes of either a routine or non-routine nature.
Two independent channels are provided at each location, and the system can be
used as a back-up communication system.
3. Dial Telephone System
A dial telephone system is provided for normal communications between offices
and work areas which are routinely occupied. Units are also located
conveniently within the reactor building for use by the facility personnel.
This system is connected to points outside the facility through both the
commercial telephone system and a microwave network.
VYNPS DSAR Revision 1 3.0-83 of 87
4. Microwave Communication System
The microwave system provides for the interchange of information between the
facility and the electrical dispatcher. Microwave equipment is located in the
switchyard control house and, with its battery and charger, is independent of
the other plant communications systems.
5. Off-Site Radio Communication System
Radios located in the control room provide contact with the State Police, the
Utility Emergency Radio Network, and Mutual Aid.
3.3.10.4 Inspection and Testing
Operational tests are frequently made as a result of constant use of the
communications systems.
3.3.11 Process Computer System
3.3.11.1 Objectives
The objectives of the process computer are to aid facility personnel by
continuously assessing the readout of instrumentation relative to permissible
limits, to provide data accumulation and logging functions, and to serve as a
Safety Parameter Display System (SPDS) which shall provide a display of selected
variables to aid facility personnel in determining the status of the plant
3.3.11.2 Design Bases
The Process Computer System (PCS) shall support the following SPDS functions:
Perform meaningful conversions and monitoring of radiation release
paths;
Monitor, calculate, and display meteorological data for emergency
response personnel.
Provide Data to the Plant Data System for emergency response.
VYNPS DSAR Revision 1 3.0-84 of 87
3.3.11.3 Description
3.3.11.3.1 Computer System Components
3.3.11.3.1.1 Central Processor
The central processor performs various calculations, makes necessary
interpretations, and provides for general input/output (I/O) device control and
buffered transmission between I/O devices and memory. To ensure data integrity,
the computer system has built-in testing checks and diagnostic facilities, such as
parity and error detection and correction in the processor, memories, and the
system bus, and automatic self-test at power-up. Real-time processing capability is
provided with battery backup to facilitate a rapid restart without loss of memory
or loss of processor clock time.
Power for the computer is supplied from an uninterruptible power source (UPS-2A)
which can supply power for a minimum of three hours while off-site power is not
available.
3.3.11.3.1.2 Auxiliary Memory Subsystem
Auxiliary memory consists of fixed disk drives.
The Auxiliary Memory Subsystem is designed for and provides the capability for
further expansion. The disk drives incorporate outstanding data reliability
characteristics, including Error Correction Code (ECC), microprocessor-controlled
diagnostics, and a modular design for easy maintenance.
3.3.11.3.1.3 Peripheral Input/Output Subsystem
The peripheral I/O equipment used to read programming data into and out of the
computer consists of a system console, terminals, printers, alarm typer, magnetic
tape and disk subsystems. The system console, magnetic tape and disk subsystems
are located in the Computer Room. The terminals, printers and alarm typer are
located in the Control Room.
VYNPS DSAR Revision 1 3.0-85 of 87
3.3.11.3.1.4 Process Input/Output Subsystem
The process I/O hardware is a real time distributed, microprocessor based,
intelligent industrial I/O processor. The I/O processor with its processing
capability reduces the host computer signal linearization and raw data scaling
tasks. The process I/O hardware consists of analog/digital input cards,
pulse/sequence of events input cards, and analog/digital output cards all under
microprocessor control. The analog inputs accept analog signals from plant
instrumentation and provide signal conditioning for use in the computer system.
The digital input cards provide signal conditioning and filtering. Intermittent
signals and pulse-type inputs are handled by SOE/pulse input cards. These cards
have a programmable mode of operation, including interrupt on a specific count and
continuous count. This allows immediate response for processing of information
which otherwise might be lost if digital scanning techniques were used. The
process I/O hardware supports one second scan rates for digital inputs and sub-
second scan rates for analog inputs.
3.3.11.3.4 Monitor Alarm and Logging Functions
3.3.11.3.4.1 Analog Monitor and Alarm
The processor is capable of checking each analog input variable against three types
of limits for alarming purposes: (a) process alarm limits as determined by the
computer during computation or as preprogrammed at some fixed value by the user,
(b) a reasonableness limit of the analog -input signal level as determined and
programmed by the user, and (c) a rate of change alarm limit as determined and
programmed by the user.
The alarming sequence consists of a one-line message on the alarm typer for each
point exceeding process alarm limits. Alarm messages may also be displayed on a
video display as selected by the user. A variable that is returning to normal is
signified by a one-line message on the alarm typer. Actuation of the alarm typer
provides facility personnel with an audible cue that an alarm message has printed.
The processor provides the capability to alarm the Main Control Room Annunciator
System in the event of abnormal PCS operation. Abnormal conditions for alarm
include loss of power and stall conditions. Stall conditions can be caused by
software failure, hardware failure or PCS over-temperature conditions.
VYNPS DSAR Revision 1 3.0-86 of 87
3.3.11.3.4.2 Digital Inputs Status Monitoring
1. Digital Input Status Logging
The status alarm function scans digital inputs at regular intervals and
provides a printed record of system alarms. The record includes point
description, state, and time of occurrence.
2. Sequence Annunciator Detection and Logging
Digital inputs associated with status changes of major plant equipment and
instrumentation are terminated on change-of-state detection sequence of
events input hardware.
To aid facility personnel in analysis of any plant event, this function
archives SOE messages into multiple files. The SOE messages will be logged
in the order of their detection, with one millisecond (msec) resolution
accuracy. The time logs will be synchronized to the PCS (ERFIS) internal
clock at the time of occurrence.
3.3.11.3.4.3 Alarm Logging
The alarm logs required by the associated process programs are typed by the alarm
typer. Alarm printouts, as well as alarm summary displays, are used to inform
facility personnel of computer system malfunction; system operation exceeding
acceptable limits; and potentially unreasonable, off-normal, or failed input
sensors.
3.3.11.4 Inspection and Testing
The Process Computer System is self-checking. It performs diagnostic checks to
determine the operability of certain portions of the system hardware, and it
performs internal programming checks to verify that input signals and selected
program computations are either within specific limits or within reasonable bounds.
3.3.11.5 Cyber Security
The PCS is deterministically isolated from less secure digital components and
systems by a data diode. This device can transmit PCS data to the less secure
general user community, but there is no physical channel for data flow in the
reverse direction. This prevents malicious computer code from migrating to the
PCS.
VYNPS DSAR Revision 1 3.0-87 of 87
3.3.11.6 Process Computer Data Feed to the Plant Data Server (PDS)
A datalink sends all data variables from the PPC, through the Data Diode, to PDS.
3.3.12 Torus-as-CST System
3.3.12.1 Objective
The objective of the Torus-as-CST System is to recirculate water in the Torus and
provide for Spent Fuel Pool water makeup and letdown.
3.3.12.2 Design Basis
The Torus-as-CST System utilizes the Torus for water storage. The system
recirculates water from the Torus and processes it through filters and
demineralizers. The system also provides for Spent Fuel Pool water makeup and
letdown.
3.3.12.3 Description
The chemical waste sump and sumps (equipment and floor) in the Radwaste Building
and Reactor Building are routed to the Torus. The Torus-as-CST water treatment
system, installed after permanent plant shutdown, recirculates and cleans Torus
water. The system provides for suitable Spent Fuel Pool water makeup and letdown.
The System contains parallel paths of pumps, filters and demineralizers. Suction
is taken from the Torus and discharge is either to the SFP or back to the Torus.
Water stored in the torus may be disposed offsite or discharged to the environs in
accordance with applicable permits and regulatory approvals.
VYNPS DSAR Revision 1 4.0-1 of 53
RADIOACTIVE WASTE MANAGEMENT
TABLE OF CONTENTS
Section Title Page
4.1 SOURCE TERMS .......................................................... 5
4.2 RADIATION SHIELDING ................................................... 5
4.2.1 Objective .................................................... 5
4.2.2 Design Basis ................................................. 5
4.2.3 Description .................................................. 6
4.2.3.1 Materials Description ........................... 6
4.2.3.2 Reactor Building ................................ 6
4.2.3.3 Main Control Room ............................... 6
4.2.4 Surveillance and Testing ..................................... 6
4.3 HEALTH PHYSICS INSTRUMENTATION ........................................ 7
4.3.1 Objective .................................................... 7
4.3.2 Description .................................................. 7
4.4 RADIATION PROTECTION .................................................. 9
4.4.1 Health Physics ............................................... 9
4.4.1.1 Personnel Monitoring Systems .................... 9
4.4.1.2 Personnel Protective Equipment .................. 9
4.4.1.3 Change Area and Shower Facilities ............... 9
4.4.1.4 Access Control ................................. 10
4.4.1.5 Laboratory Facilities .......................... 10
4.4.1.6 Bioassay Program ............................... 10
4.4.2 Radioactive Materials Safety Program ........................ 10
4.4.2.1 Facilities and Equipment ....................... 11
4.4.2.2 Personnel and Procedures ....................... 11
4.4.2.3 Required Materials ............................. 12
4.5 LIQUID WASTE MANAGEMENT SYSTEMS ...................................... 12
VYNPS DSAR Revision 1 4.0-2 of 53
4.5.1 Equipment and Floor Drainage Systems ........................ 12
4.5.1.1 Objective ...................................... 12
4.5.1.2 Design Basis ................................... 12
4.5.1.3 Description .................................... 13
4.5.1.4 Inspection and Testing ......................... 19
4.5.2 Liquid Radwaste System ...................................... 19
4.5.2.1 Objective ...................................... 19
4.5.2.2 Design Bases ................................... 19
4.5.2.3 Description .................................... 20
4.5.2.4 Evaluation ..................................... 24
4.5.2.5 Inspection and Testing ......................... 26
4.6 SOLID WASTE MANAGEMENT ............................................... 35
4.6.1 Solid Radwaste System ....................................... 35
4.6.1.1 Objective ...................................... 35
4.6.1.2 Design Basis ................................... 35
4.6.1.3 Description .................................... 35
4.6.1.4 Inspection and Testing ......................... 37
4.7 EFFLUENT RADIOLOGICAL MONITORING AND SAMPLING ........................ 39
4.7.1 Process Radiation Monitoring Instrumentation ................ 39
4.7.1.1 Plant Stack Radiation Monitoring System ........ 39
4.7.1.2 Process Liquid Radiation Monitoring System ......................................... 41
4.7.1.3 Reactor Building Ventilation Radiation Monitoring System .............................. 42
4.7.2 Area Radiation Monitoring System ............................ 47
4.7.2.1 Objectives ..................................... 47
4.7.2.2 Design Basis ................................... 47
4.7.2.3 Description .................................... 47
4.7.2.4 Inspection and Testing ......................... 48
VYNPS DSAR Revision 1 4.0-3 of 53
RADIOACTIVE WASTE MANAGEMENT
LIST OF TABLES Table No. Title 4.5.2.1 Vermont Yankee Radioactive Liquid Waste Processing Parameters
4.5.2.2 Vermont Yankee Liquid Radwaste System Tank Capacities
4.5.2.3 Vermont Yankee Liquid Effluents
4.5.2.4 Activity Input to Liquid Radwaste System (Ci/yr)
4.5.2.5 Radionuclide Discharge Concentrations
4.6.1.1 Solid Radwaste Annual Disposal History
4.7.1.1 Process Radiation Monitoring Systems Characteristics
4.7.1.2 Process Radiation Monitoring System Environmental and Power Supply Design Conditions
4.7.1.3 Plant Stack Radiation Monitoring System Characteristics
4.7.2.1 Area Radiation Monitoring System Environmental and Power Supply Design Conditions
4.7.2.2 Locations of Area Radiation Monitors
4.7.2.3 Reactor Building Area Airborne Radiation Monitoring System
VYNPS DSAR Revision 1 4.0-4 of 53
RADIOACTIVE WASTE MANAGEMENT LIST OF FIGURES Figure No. Title 4.5.2-8 Radwaste Area - Plan View
4.7.2-2 Reactor Building Area Airborne Radiation Monitoring System
VYNPS DSAR Revision 1 4.0-5 of 53
4.1 SOURCE TERMS
In the permanently defueled condition VYNPS will no longer produce fission,
corrosion, or activation products from operation. The radioactive inventory
that remains is primarily attributable to activated reactor components and
structural materials and residual radioactivity. The accumulation of small
amounts of solid waste may easily be controlled. Any future planned liquid
effluent releases will be evaluated prior to release, and appropriate controls
will be established. The Offsite Dose Calculation Manual ensures that VYNPS
complies with 10 CFR 50, Appendix I.
4.2 RADIATION SHIELDING
4.2.1 Objective
Radiation shielding is utilized as appropriate to limit radiation damage to
equipment and associated structures and minimize exposure of station personnel
to radiation.
4.2.2 Design Basis
Radiation shielding was provided to restrict radiation emanating from various
sources throughout the plant. Since VYNPS is permanently defueled, many
installed components are no longer required to safely store irradiated fuel.
However, many of these components continue to contain radioactive material or
remain radioactive. Shielding that was originally designed to shield these
components while they supported reactor operation continues to provide
shielding from residual radioactivity in the permanently shut down condition.
Shielding is provided to maintain personnel exposures below the limits
specified in 10CFR20. Compliance with these regulations is achieved through
shielding design based upon generalized occupancy requirements in various areas
of the station, and upon administrative radiological protection procedures.
Continuous occupancy areas outside the controlled access area, designated
Zone I, are designed to a radiation level of 0.5 mrem/hr, while those inside
the controlled access area, designated Zone II, are designed to a level of
1 mrem/hr.
Within the controlled access boundary are areas, designated Zone III, which
will allow up to 10 hours per week occupancy and are designed for 6 mrem/hr.
Controlled areas that are designed for 100 mrem/hr allowing occupancy up to
5 hours per week are designated Zone IV.
VYNPS DSAR Revision 1 4.0-6 of 53
Section 6.5 of the Vermont Yankee Permanently Defueled Technical Specifications
describes the radiation protection controls for all radiation areas with dose
rates exceeding 100 mrem/hr.
Select areas will be equipped with local area monitoring devices. The Area
Radiation Monitoring System detects, measures, and records the general
radiation levels in areas where personnel may be required to work. The system
will actuate alarms if radiation exceeds preset levels.
4.2.3 Description
4.2.3.1 Materials Description
The shielding materials used are primarily concrete, water, and steel. High
density concrete, lead, and neutron-absorbing materials are used as
alternatives in special applications.
4.2.3.2 Reactor Building
The design dose rate in most areas outside the drywell in the Reactor Building
is 1 mrem/hr. The drywell and its internal structure are shielded so that most
areas outside it are accessible.
4.2.3.3 Main Control Room
The shielding of the Main Control Room consists of poured-in-place reinforced
concrete. Side walls and roof are 2 feet thick and 1 foot, 8 inches thick,
respectively.
The Main Control Room is shielded so that no individual exposure will exceed
the limits set forth in Criterion 19, Appendix A of 10CFR Part 50.
4.2.4 Surveillance and Testing
Appropriate surveillances will be conducted by trained facility personnel.
These surveys provide continuing assurance that changes which might occur and
produce significantly different radiation fields are located and appropriately
posted.
VYNPS DSAR Revision 1 4.0-7 of 53
4.3 HEALTH PHYSICS INSTRUMENTATION
4.3.1 Objective
The health physics instrumentation system is a supplemental system which
provides a flexible radiation detection capability throughout the facility. It
is intended to supplement the facility process and area radiation monitoring
systems in assuring that the facility is within design limits and to supply the
required radiation control information.
4.3.2 Description
Health physics instrumentation consists of both portable and fixed equipment.
Portable Instrumentation
Portable health physics instrumentation consists of the following types of
equipment:
1. Alpha survey meters, which contain a thin "window" and an alpha sensitive
detecting element that permits the location and measuring of low levels of
alpha radiation contamination.
2. Beta-Gamma survey meters, which contain a thin windowed Geiger-Mueller tube
or ionization chamber, and are used for detecting low levels of surface
contamination or for making direct radiation surveys.
3. Neutron survey meters, which contain a thermal neutron sensitive BF3 tube
or tissue equivalent proportional counter. These meters are used for
locating possible shielding voids, streaming paths, etc., in the reactor
building.
4. Beta-Gamma and neutron dose rate meters are used for determining stay times
for radiation workers and for posting radiation area warning signs.
High range beta-gamma meters provide dose rate information during any event
involving high levels of radiation. Neutron dose rate meters respond to
and provide an indication of the entire spectrum of neutrons encountered
around a nuclear reactor.
VYNPS DSAR Revision 1 4.0-8 of 53
5. Emergency Kits - Emergency kits are used by the on-site mobile team during
any event involving a possible release of radioactive materials. Each kit
contains a beta-gamma survey meter and an air particulate sampler, plus any
other equipment normally used by a particular survey team.
6. Air particulate samplers, which are air pumps which pull a known flow rate
of air through filters for the purpose of sampling the atmosphere for
radioactive particulates and radioiodines. These samplers are mobile and
may be used at most parts of the plant.
7. Approved dosimeters are used in evaluating the exposure to personnel
working at the site.
Fixed and Laboratory Instrumentation
In addition to the portable health physics instrumentation available, there are
a number of fixed and laboratory instruments which are used to assess or
control the spread of radioactivity throughout the facility.
1. Gamma or beta sensitive portal monitors are located in the guardhouse and
several entrances to the controlled areas and monitor all outgoing
personnel for radioactive contamination.
2. Personal friskers are located at key places within the facility, and are
used by facility personnel to detect surface contamination on clothing,
skin, etc.
3. Dosimeter readers, which contain the equipment for measuring the dose
received by personal dosimeters. These instruments are located in an
off-site dosimeter processing facility under contract with Vermont Yankee.
4. Multi-channel gamma spectrometer, which consists of a NaI, GeLi, or HpGe
crystal, and analyzer circuits necessary for the identification of
individual isotopes by gamma ray energy.
5. Laboratory alpha and beta-gamma counters, which are used for measuring low
levels of radioactivity in specially prepared samples such as smears, air
particulate sample filters, etc.
VYNPS DSAR Revision 1 4.0-9 of 53
6. Body-burden counters, which are used to assess internal contamination from
both natural sources and from inhaled/absorbed radioactive gases or
particulates.
4.4 RADIATION PROTECTION
4.4.1 Health Physics
All employees of Vermont Yankee are given training in radiological safety and
in the requirements for working in the plant.
Administrative controls are established to assure that all procedures and
requirements relating to radiation protection are followed by all station
personnel. These procedures include a radiation work permit system. All work
on systems or in locations where exposure to radiation or radioactive materials
is expected to approach prescribed limits, requires an appropriate radiation
work permit before work can begin. The radiological hazards associated with
the job are determined and evaluated prior to issuing the permit.
4.4.1.1 Personnel Monitoring Systems
Personnel monitoring equipment is assigned to Vermont Yankee personnel by the
Radiation Protection Department. Personnel monitoring equipment is also
available on a day-to-day basis for visitors not assigned to the station that
enter radiation control areas. Records of radiation exposure history and
current occupational exposure are maintained by the Radiation Protection
Department for each individual issued personnel monitoring equipment.
4.4.1.2 Personnel Protective Equipment
Special protective clothing and respiratory equipment are furnished and worn as
necessary to protect personnel from radioactive contamination.
4.4.1.3 Change Area and Shower Facilities
A change area is provided where personnel may obtain clean protective clothing
required for station work. Temporary change areas are provided when required.
Decontamination shower facilities are maintained on-site to assist in timely
personnel decontamination. Monitoring equipment is used to assess the
effectiveness of personnel decontamination efforts.
VYNPS DSAR Revision 1 4.0-10 of 53
4.4.1.4 Access Control
To prevent inadvertent access to high radiation areas, warning signs, audible
and visual indicators, barricades and locked doors are used as necessary.
Procedures are also written to control access to high radiation areas.
4.4.1.5 Laboratory Facilities
The facility includes a laboratory with adequate facilities and equipment for
detecting, analyzing, and measuring radioactivity and for evaluating any
radiological problem that may be anticipated. Counting equipment, such as a
multichannel analyzer, liquid scintillation, G-M and proportional counters, and
scalars, are provided in an appropriately designed counting room.
Environmental sample analyses are conducted by outside laboratories.
4.4.1.6 Bioassay Program
In vivo bioassay counting equipment is available for quantitative and
qualitative analysis of possible internal deposition of radioactive
contaminants. Consulting laboratory services are used as backup and support
for this program. Appropriate bioassay (urine and fecal) samples are
collected, as necessary, from personnel who work in control areas as an aid in
the evaluation of internal exposure.
4.4.2 Radioactive Materials Safety Program
All Vermont Yankee personnel who work in controlled areas are given training
in radiological safety. Training Program content is specified in appropriate
training department procedures.
Additionally, those personnel in the Radiation Protection Department whose job
entails the handling of sealed and unsealed sources are given departmental
training.
Other departmental procedures detail methods of leak testing sealed sources and
receipt, handling, and storage of radioactive materials. A general calibration
procedure outlines specific techniques for the safe and expeditious handling of
all calibration sources.
VYNPS DSAR Revision 1 4.0-11 of 53
Accountability of sources is maintained in inventory records that are updated
semi-annually. Accessibility control is achieved through locked storage,
securing the source in place to prevent unauthorized removal, or continuous
surveillance by authorized personnel.
Accountability of sources that are exempt from leak testing required by the
TRM, but exceed the limits for licensable quantities of radioactive material
specified in Title 10, Code of Federal Regulations, is maintained in inventory
records that are updated annually. All sources of licensable quantity that are
not in use are kept in suitably shielded containers when it is necessary to
minimize personal radiation exposure. All sources of licensable quantity are
kept under the control of authorized personnel when in use.
This system of procedures, training, access control, and accountability is
periodically audited by the Vermont Yankee Quality Assurance Department and/or
one or more contracted service organization(s), collectively defined as the
Quality Assurance Department, as its authorized agent for provision of certain
quality assurance and related support services. Through this mechanism,
compliance with applicable regulations is assured.
4.4.2.1 Facilities and Equipment
Station laboratory facilities and monitoring equipment are discussed in DSAR
Sections 4.3 and 4.4.1.5.
4.4.2.2 Personnel and Procedures
Implementation of the Vermont Yankee radiation protection program, including
source, special, and byproduct material safety, is accomplished by Radiation
Protection Department personnel. The qualifications of these personnel in
radioactive materials safety stem from formal and informal training and from
applied experience in the radiation protection field. Specific training of
Radiation Protection personnel in the safe handling of radioactive materials is
covered by a department training program.
VYNPS DSAR Revision 1 4.0-12 of 53
4.4.2.3 Required Materials
All byproduct, source, and special nuclear materials used as reactor fuel,
sealed neutron source for reactor startups, sealed sources for calibration of
reactor instruments, and radioactive monitoring equipment and fission detectors
are possessed in the amounts required for relevant use. All byproduct material
consisting of mixed fission products and corrosion products in the form of
contamination affixed to equipment used for reactor system repair, maintenance,
testing, and/or surveillance may be received, possessed or used in amounts as
required without restriction to chemical or physical form.
With the permanent defueled condition of Vermont Yankee, fission, corrosion,
and activation products from operation are no longer produced. The radioactive
inventory that remains is primarily attributable to sealed radioactive sources,
activated reactor components, nuclear instrumentation, structural materials and
residual radioactivity. The accumulation of small amounts of solid waste as
contaminated materials may easily be controlled.
4.5 LIQUID WASTE MANAGEMENT SYSTEMS
4.5.1 Equipment and Floor Drainage Systems
4.5.1.1 Objective
The objective of the various equipment and floor drainage systems is to remove
all waste fluids from their points of origin in a controlled effective manner
and to deliver them to a suitable disposal system. Radioactive drain
collection is arranged to minimize radioactive exposure to operating personnel
and to prevent uncontrolled leakages to the environs.
4.5.1.2 Design Basis
Equipment and floor drainage systems shall operate satisfactorily and create no
danger to the health and safety of the general public. These systems shall be
designed and installed to guard against fouling, deposit of solids, and
clogging. Sumps and pumps shall be provided to preclude leakage accumulation
from preventing operation of required equipment. Nonradioactive drainage
systems shall be arranged to assure that no infiltration of radioactive waste
will occur.
VYNPS DSAR Revision 1 4.0-13 of 53
Fluids from radioactive and potentially radioactive drains will be collected,
sampled, treated, stored, and/or analyzed prior to disposal in accordance with
10CFR20. Nonradioactive equipment and floor drains empty into the Storm Sewer
System and then discharge into the Circulating Water System piping at the
discharge structure or directly to the Connecticut River at the North Storm
Drain Outfall.
4.5.1.3 Description
4.5.1.3.1 General
The six basic drainage systems are:
1. Radioactive equipment drainage systems
2. Radioactive floor drainage systems
3. Radioactive liquid chemical drainage systems
4. Oil drainage systems
5. Nonradioactive water drainage systems
6. Sanitary drainage systems
The first four systems handle fluid wastes which are radioactive or potentially
radioactive. The last two systems handle fluid wastes originating in areas
which are not radioactive or potentially radioactive. Radioactive wastes are
pumped or drained to the Radwaste System. Nonradioactive wastes are drained to
either the Storm Sewer Drainage System or Sanitary Disposal System.
Radioactive drainage piping is sloped 1/4 inch per foot, and concrete floors
are pitched a minimum of 1/8 inch per foot wherever possible to remove
radioactive wastes as quickly as possible.
Accessible cleanouts are provided at each horizontal change of direction
greater than 45 degrees. Base cleanouts are provided at the base of each stack
approximately 12 inches above the finished floor. In the event a drainage line
becomes stopped or clogged, it can be quickly cleaned out.
The chemical waste sump and equipment and floor drain sumps in the Radwaste
Building and Reactor Building are routed to the Torus. Torus water is
processed through the Torus-as-CST System and is normally used to control spent
fuel pool inventory. Water stored in the torus may be disposed offsite or
discharged to the environs in accordance with applicable permits and regulatory
approvals.
VYNPS DSAR Revision 1 4.0-14 of 53
Equipment and floor drain sumps in the Turbine Building are routed to a batch
tank. Tank contents are sampled prior to being transferred, disposed of (via
offsite shipments), or discharged to the environs in accordance with applicable
permits and regulatory approvals.
With the exception of that in the nonradioactive waste drainage systems and
sanitary drainage systems, all drainage piping is carbon steel Schedule 80,
except oil drainage piping, which is carbon steel Schedule 40, and a portion of
condensate drainage piping from the drywell cooling units, which is type 304
stainless steel, Schedule 40. Material used is ASTM A-106, Grade "B". Joints
are welded construction without backing rings. Concrete embedded piping
conforms to the USAS Code B31.1, Sections 1 and 6 for pressure piping. A
portion of condensate drainage piping from the drywell cooling unit is
stainless steel Schedule 80, ASTM A358, Grade TP304.
The Chemistry Laboratory and health physics detergent waste drains are a common
above ground polypropelene lined carbon steel flanged pipe.
Above ground drainage piping used for the Sanitary and Nonradioactive Water
Drainage System is galvanized steel Schedule 40 and galvanized cast iron
drainage fittings. Piping and fittings installed below ground are extra heavy
cast iron.
Vent piping installed above ground is galvanized steel Schedule 40 with
galvanized malleable iron fittings. Piping and fittings installed below ground
are extra heavy cast iron.
All fixtures in the health physics work area, the chemical laboratory, and
fixtures discharging into the Sanitary Drainage System are vented. Each
fixture trap is protected against siphonage and back pressure. The individual
vents collect in a main vent header and terminate full size above the roof.
The radioactive equipment drainage systems receive clean radioactive waste
which is processed and reused. These radioactive systems receive equipment
leak-offs and drains only from equipment handling radioactive liquids.
Radioactive liquids are routed to an equipment drain sump in a closed system
and then pumped to the Radwaste System waste collector tank for future
filtering and demineralization before returning to the Condensate System.
Radioactive or potentially radioactive floor drains are routed to a floor drain
sump in open-ended lines and then pumped to the Radwaste System floor drain
collector from where they are processed and reused. Nonradioactive floor
drains are routed directly to the Storm Sewer System.
VYNPS DSAR Revision 1 4.0-15 of 53
Radioactive equipment drains are connected directly to the component serviced
to preclude the possibility of spillage.
4.5.1.3.2 Radioactive Equipment Drainage Systems
Drywell Equipment Drainage Systems
Equipment drains are provided for various components in the drywell and these
lines are run directly to a 500-gallon equipment drain sump. The sump is
provided with two 50 gpm pumps and a number of level switches. A sump pump
will start automatically upon the liquid reaching a pre-set high level and will
trip automatically upon the liquid being lowered to a pre-set low level. A
second sump pump starts and an alarm sounds in the Control Room upon the liquid
reaching a high-high level. Two sump pumps are provided to improve
reliability. An alternator is provided to ensure equal wear on each pump.
Remote operating capability is provided for this system. The common discharge
pipe from the two sump pumps runs through a containment penetration and has two
air-operated valves outside the containment wall. A relief valve provides
overpressure protection of the penetration and connected piping.
Reactor Building Equipment Drainage System
Various equipment drainage in the Reactor Building is piped directly to one of
the two 1000-gallon equipment drain sumps. Each sump (one on the north side
and one on the south side of the Reactor Building) is provided with two 50 gpm
pumps, which discharge to the waste collector tank in the Radwaste Building.
Each sump is provided with level switches used for automatic pump control and
sump high-high level alarm. Pump control switches are located on the radwaste
control panel.
Turbine Building Equipment Drain System
One 1000-gallon sump, located in the feedwater heater area of the Turbine
Building, is provided to collect various equipment drainage. The sump contains
two 50 gpm pumps that discharge to the waste collector tank in the Radwaste
Building.
Sump level switches are used to operate the pumps automatically and provide a
high-high level alarm.
VYNPS DSAR Revision 1 4.0-16 of 53
Radwaste Building Equipment Drain System
Various radwaste pumps seal leakage and radwaste tanks, drains, and overflows
are piped directly to one 1000-gallon sump. One 50 gpm sump pump is controlled
automatically by sump level switches and discharges to the waste collector
tank. A sump high level alarm annunciates on the radwaste control panel and in
the Control Room.
4.5.1.3.3 Radioactive Floor Drainage Systems
Drywell Floor Drainage System
The Drywell Floor Drain System collects and disposes of leakage from various
systems and components. Remote operating capability is provided for this
system.
Reactor Building-Floor Drainage System
The Reactor Building Floor Drainage System collects drainage into two
1000-gallon sumps. Each sump (one on the north side and one on the south side
of the Reactor Building) is equipped with two 50 gpm sump pumps which discharge
to the floor drain collector tank.
Turbine Building Floor Drainage System
The Turbine Building Floor Drainage System consists of two 1000-gallon sumps,
each provided with two 50 gpm sump pumps which discharge to the floor drain
collector tank. One sump is located in the condenser area and the other is in
the condensate pump area.
Radwaste Building Floor Drainage System
The Radwaste Building contains one 1000-gallon sump utilized to collect various
floor and tank overflow drainage. One 50 gpm sump pump is provided which
discharges to the floor drain collecting tank.
VYNPS DSAR Revision 1 4.0-17 of 53
4.5.1.3.4 Radioactive Liquid Chemical Drainage Systems
The Radioactive Liquid Chemical Drainage System consists of radioactive filter
sludge piping, radioactive chemical drain piping, and radioactive detergent
waste piping. The system handles drainage of radioactive contaminants and
foreign matter such as sludge, detergents, or chemicals from equipment. The
various systems begin with floor drains, direct connection equipment drains,
gutter drains, shower drains, service sinks, and laboratory benches from the
Reactor, Turbine, and Radwaste Buildings. Drainage is collected in waste lines
and discharged into various items of storage and treatment equipment in the
Radwaste Building.
Special showers are provided in the health-physics work area for personnel
decontamination purposes. The drainage from the fixtures in this area is
collected in waste lines and discharged directly into the chemical waste tank
in the Radwaste Building.
4.5.1.3.5 Oil Drainage Systems
Oil drain systems outside the restricted are not considered radioactive. Oil
drain systems within the restricted area are treated as potentially
contaminated. Drainage from systems and equipment using oil is either
collected in sumps or drains to oil separator manholes. Separated oil is
retained while the oil-free water drains into the Storm Sewer System.
Two oil sumps are provided. One is located beneath the floor of the Reactor
Building, and the second is located in the northwest corner of the Turbine
Building.
Oil drainage not routed and collected in a sump is collected in branch lines
which empty into main lines and discharge directly into oil separator manholes
outside the Turbine Building and Control Room Building. The oil separator
manholes function to separate and retain the oil while discharging oil-free
water into the Storm Water Sewer System which drains either to the discharge
structure or the North Storm Drain Outfall to the Connecticut River.
Oil drainage systems in specific areas, which could have propagated a fire,
have been modified. To ensure that spilled fluid is contained within the
respective berm areas, various transformer oil drains have been permanently
plugged.
The oil collected in the oil sumps will be pumped to suitable containers for
disposal using a portable pump. Grab samples can be taken at this time for
radioactive analysis
VYNPS DSAR Revision 1 4.0-18 of 53
4.5.1.3.6 Nonradioactive Water Drainage System
The Storm and Nonradioactive Water Drainage System receives rain water, clear
liquid wastes not hotter than 140°F, and drainage from equipment which is
nonradioactive. This drainage is routed separately to the Storm Sewer System.
Heating, ventilation and air conditioning equipment in the Reactor and Turbine
Buildings was considered nonradioactive in the original plant design. Low
levels of tritium have been found in the various drains associated with this
equipment even though modifications to alleviate the condition have been
performed. The levels of contamination have been evaluated and found to be
acceptable for continued discharge to the storm drain system. The condition is
monitored through a surveillance program and reported in the “Annual
Radiological Environmental Operating Report”. Funnel type equipment drains and
floor drains serving this equipment are collected in branch lines, empty into
main drain lines, and discharge into the Storm Sewer System. A separate
Nonradioactive Water Drainage System is provided in the Turbine Building for
certain items of equipment. Air handling equipment, certain water pumps on the
basement floor and miscellaneous equipment on the ground floor were considered
nonradioactive in the original plant design. Low levels of activity have been
found in the turbine building clean sump associated with this equipment. The
levels of contamination have been evaluated and found to be acceptable for
continued discharge to the discharge structure. The condition is monitored
through a surveillance program and reported in the “Annual Radiological
Environmental Operating Report”. Funnel type equipment drains and floor drains
in these areas are collected in branch lines, empty into main drain lines, and
discharge into the clean equipment and floor drain sump, located below the
basement floor. To improve administrative control over the sources of
radioactive liquid entering this sump, floor drains, which are aligned to this
sump, have been permanently plugged or fitted with removable plugs. In
addition, the drain header from floor and equipment drains in the vicinity of
the demineralized water transfer pumps and the station air compressor receiver
tanks has been cut, capped and valved to allow sampling prior to release.
Other equipment drains are either permanently plugged or go directly to the
sump. Sump pumps are provided to transfer the discharge from the Turbine
Building to the service water discharge.
In addition to the low levels of tritium discussed above, surface run-off from
within the Protected Area carries low levels of particulate activity to the
Storm Sewer System. The low levels of contamination in the Storm Sewer System
have been evaluated to ensure that the calculated maximum release is a
significant percentage less than the total body and critical organ doses
allowed under the routine effluent ALARA objectives of 10CFR50, Appendix I.
VYNPS DSAR Revision 1 4.0-19 of 53
Acid resistant drains and piping are provided in areas where highly
concentrated acids are present. Duriron floor drains and piping are provided
to serve the Turbine Building water treatment area. Duriron floor drains and
piping, plus Duriron funnel type equipment drain and piping, are also provided
to serve the Battery Room in the Control Building.
4.5.1.3.7 Sanitary Drainage Systems
The Sanitary Drainage System is provided for the convenience, health, and
safety of facility personnel. This system receives the domestic sewage from
various fixtures that are water supplied and discharges liquid wastes.
Except for fixtures in the health-physics work area, all water closets,
urinals, lavatories, drinking water coolers, service sinks, kitchen units, and
showers in the Turbine and Control Buildings discharge into the Sanitary
Drainage System. Each fixture is trapped and vented, then collected in branch
lines, emptied into main soil lines, and discharged by gravity into the
Sanitary Disposal System.
4.5.1.4 Inspection and Testing
The Equipment and Floor Drainage Systems are normally in operation during all
modes of facility operation. Satisfactory operation is demonstrated
continuously without the need for special testing or inspection.
4.5.2 Liquid Radwaste System
4.5.2.1 Objective
Liquid radwaste is collected and processed as required for reuse. Any liquid
waste which would not be suitable for reuse could be diluted and discharged
from the facility.
4.5.2.2 Design Bases
Liquid radwaste is collected and processed to assure that the release of liquid
radwaste is kept as low as reasonably achievable and is within the annual dose
limits specified in 10CFR20.1301.
Liquid radwaste shall be contained to prevent the inadvertent release of
significant quantities of liquid radioactive material to unrestricted areas so
that resulting radiation exposures are within the limits of 10CFR20.1301.
VYNPS DSAR Revision 1 4.0-20 of 53
4.5.2.3 Description
The Liquid Radwaste System collects, processes, stores, and disposes of all
radioactive liquid wastes. The radwaste facility is located in the Radwaste
Building, with the exception of the waste sample tanks, floor drain sample
tank, and waste surge tank, all located outdoors at grade level (see Drawings
G-191151 and G-191152).
Included in the Liquid Radwaste System are the following:
1. Floor and Equipment Drain System for handling potentially radioactive
wastes.
2. Tanks, piping, pumps, process equipment, instrumentation, and auxiliaries
necessary to collect, process, store and dispose of potentially radioactive
wastes.
Equipment is selected, arranged, and shielded to permit operation, inspection,
and maintenance with acceptable personnel exposures. For example, sumps,
pumps, valves, and instruments are located in controlled access areas. Tanks
and processing equipment which can contain large quantities of liquid radwastes
are shielded. The Radwaste System equipment, equipment arrangement,
capacities, flow paths, and flow rates are shown in Drawings 5920-644, Sh.2 and
G-191177, Shs. 1 through 4. Operation of the Waste System is essentially
manual start-automatic stop.
This is a batch-type system wherein the wastes are separately collected and
processed based on the most efficient methods. Cross-connections between
subsystems provide additional flexibility for processing of the wastes by
alternate methods. Treated wastes can be: (a) returned to the system for
reuse, (b) diluted and discharged from the facility, or (c) if not suitable for
either reuse or discharge, they receive additional processing. The liquid
radwastes are classified, collected, and treated as high purity, low purity,
chemical or detergent wastes. The terms "high" purity and "low" purity refer
to conductivity and not radioactivity.
VYNPS DSAR Revision 1 4.0-21 of 53
The Liquid Radwaste System has been or is in the process of being abandoned and
it is no longer utilized. However, it can be restored to operational status if
desired. The chemical waste sump and sumps (equipment and floor) in the
Radwaste Building and Reactor Building are routed to the Torus. The
Torus-as-CST water treatment system, installed after permanent plant shutdown,
recirculates and cleans Torus water. The system provides for suitable Spent
Fuel Pool water makeup and letdown. The system contains parallel paths of
pumps, filters and demineralizers. Suction is taken from the Torus and
discharge is either to the SFP or back to the Torus.
The Liquid Radwaste System is operated such that any liquid radioactive waste
releases would be minimized. Successful processing of all liquid wastes to
maintain a low release system calls for special plant controls. Detergent and
soap used to clean areas and equipment are kept to a minimum. The majority of
chemical wastes are neutralized and metered slowly into higher purity water for
processing. Low purity water is filtered, and combined with higher purity
water for reprocessing. The combination of low purity, chemical, and detergent
waste into higher purity waste streams allows for reprocessing and plant reuse
and reduces the need to discharge any fraction of the waste stream. Liquid
waste could be discharged from the waste sample tank to the environment through
approved discharge pathways. The maximum concentration of tritium and
dissolved noble gases at the point of discharge will not exceed applicable
limits.
The processing equipment is located within a concrete building to provide
secondary enclosures for the wastes in the event of leaks or overflows. Tanks
and equipment which contain wastes with radioactive concentrations are
shielded. Except where flanges are required for maintenance, all pipe
connections are welded to reduce the probability of leaks. Chemistry
lab/detergent waste piping is lined with plastic and cannot be welded. As a
result, these lines are flanged, and the flanges, located in the switchgear
room, are fitted with Vue-Guards to reveal and collect any leakage to minimize
the potential for flooding. Process lines which penetrate shield walls are
routed to prevent a direct radiation path from the tanks or equipment for which
shielding is required. Control of the Waste System is from a local panel in
the Radwaste Building Control Room.
Therefore, because the radioactivity concentrations in the liquid radwaste
effluent do not exceed the guideline limits of 10CFR20, the Liquid Radwaste
System fulfills the design basis.
VYNPS DSAR Revision 1 4.0-22 of 53
4.5.2.3.1 High Purity Wastes
High purity (low conductivity) liquid wastes are collected in the waste
collector tank.
The high purity wastes are processed by filtration and ion exchange through the
waste collector filter or fuel pool and waste demineralizers as required.
After processing, the liquid is pumped to the waste sample tank where it is
sampled and either recycled for additional processing or transferred to the
condensate storage tank for spent fuel pool inventory makeup.
Should discharge be necessary, wastes would be sampled on a batch basis.
Samples from the waste sample tanks are analyzed for water quality and
radioactivity. If high purity requirements are met, the contents are
transferred to the condensate storage tank.
If high purity requirements are not met, the liquid wastes are recycled through
the Radwaste System or could be discharged. The high purity requirements are
specified in plant procedures.
Table 4.5.2.5 lists the radionuclide discharge concentrations at original 100%
power operation, assuming an 80% plant capacity factor and a dilution flow of
20,000 gallons per minute. The total annual release values are based on output
from the BWR Gale Code (NUREG-0016). The information in Table 4.5.2.5 is
historical and is being retained to provide bounding values.
It can be seen from Column 5 (Fraction of ECLw) that the concentration for each
radionuclide at the point of discharge is several orders of magnitude below
limits established in 10CFR20 for release of effluents to unrestricted areas.
The design of the Radwaste Treatment System is therefore consistent with the
policy that any radioactive effluents would be reduced to the lowest reasonably
achievable level.
Liquid effluents discharged from the plant enter a 30-inch dilution water line
which terminates in a diffuser at the head end of the aerating apron at the
discharge structure. The effluent enters the Vernon Pond at the downstream end
of the aerating apron.
VYNPS DSAR Revision 1 4.0-23 of 53
4.5.2.3.2 Low Purity Wastes
Low purity (high conductivity) liquid wastes which are collected in the floor
drain collector tank are from the following sources:
1. Drywell floor drains
2. Reactor Building floor drains
3. Radwaste Building floor drains
4. Turbine Building floor drains
These wastes generally have low concentrations of radioactive impurities, and
processing consists of filtration and a combination with the high purity waste
in the waste collector tank, with subsequent processing, as high purity waste.
Operation of the Liquid Radwaste System is such that all liquid wastes will be
processed and reused without having to discharge for total system volume
control, or water purity constraints. For the purpose of analyzing future
radiological impacts during the plant's life, it is assumed that 1% of the
combined processed stream treated each year would be discharged from the
facility. Table 4.5.2.1 indicates the radioactive liquid waste sources, flow
rates, expected activities, holdup times, decontamination factors, and assumed
fraction of waste discharged from the Liquid Waste Processing System at
original 100% power operation. The information in Table 4.5.2.1 is historical
and is being retained to provide bounding values. Table 4.5.2.2 lists the
capacity of all major tanks in the Liquid Radwaste System. The plant operating
parameters and design information provides the necessary inputs for the
calculation of potential radioactive source terms by the Nuclear Regulatory
Commission's BWR Gale Computer Code (NUREG-0016). Table 4.5.2.3 lists the
calculated liquid source terms for Vermont Yankee at original 100% power
operation. The information in Table 4.5.2.3 is historical and is being
retained to provide bounding values. Based on processing parameters in Tables
4.5.2.1 and 4.5.2.2, Table 4.5.2.4 lists the activity input to the Liquid
Radwaste System at original 100% power operation for all major nuclides. The
information in Table 4.5.2.4 is historical and is being retained to provide
bounding values. The radioactivities listed represent activities prior to
treatment and will be reduced significantly due to decontamination and isotopic
decay while passing through treatment systems.
VYNPS DSAR Revision 1 4.0-24 of 53
4.5.2.3.3 Chemical Wastes
Chemical wastes are collected in the chemical waste tank and are from the
following sources:
1. Chemical lab waste
2. Laboratory drains
3. Sample sinks
When the chemical concentrations are low enough, these wastes may be
neutralized and processed by filtration and dilution in the same manner and
with the same equipment as the low purity wastes. When the chemical
concentrations are too high, these wastes may receive additional processing.
4.5.2.3.4 Detergent Wastes
Detergent wastes are collected in the detergent waste tank. These wastes are
primarily from radioactive decontamination solutions which contain detergents.
Detergent wastes are of low radioactivity concentration (<10-5 µCi/cc). Because
detergents will foul ion exchange resins, their use is minimized in the plant.
For initial cleanings, little or no detergent is used. The facility uses an
off-site cleaning laundry, thus minimizing the quantity of waste generated.
Detergent wastes are normally dumped to the floor drain collector tank for
processing with low purity waste.
4.5.2.4 Evaluation
The Radwaste Building is classified as a Class II seismic design structure, and
the Waste System is classified as Class II seismic design equipment, since
failure of the structure and/or the equipment will not cause a significant
release of radioactivity.
VYNPS DSAR Revision 1 4.0-25 of 53
With the exception of three 10,000 gallon sample tanks and a 35,000-gallon
waste surge tank, the Radwaste System processing equipment and storage tanks
are located in the Radwaste Building. Failure of the building could be
postulated and the failure could conceivably result in damage to storage tanks
within the building. If the contents of all the tanks within the building were
released, and this is extremely unlikely because of the compartment-like
arrangement and the arrangement of shield walls, the liquid waste would
ultimately accumulate in the basement of the building. Considering the volume
with all tanks two-thirds full, and the existing basement floor space, the
accumulation would amount to approximately 18 inches of water. Considering the
low driving head of the liquid waste in the basement of the building and the
distance to the river, it is very unlikely that entrained activity would find a
leakage path to the river. It is possible that some seepage may occur through
the building foundation, but such seepage would be expected to be small in
quantity and would tend to be absorbed in the soil surrounding the foundation.
If the seepage persisted over a long period of time, the soil surrounding the
foundation would not only act as a liquid absorber, but also as a filter.
The outside storage tanks located within approximately 1.5 foot high concrete
dikes, Figure 4.5.2-8, provide a less remote potential for off-site discharge
of activity. Sumps are provided within the diked area to provide for draining
any leakage or rainwater. Although it is virtually impossible to postulate a
condition which would result in the complete discharge of the contents of the
four outside tanks into the river, the consequences of such an occurrence have
been analyzed.
The maximum gross radioactivity in the four outside tanks is limited to
3.2 curies on the basis of an accidental spill from all tanks due to a seismic
event great enough to damage them. Assuming a low river flow of 108 ft3/sec, a
one day period over which the radioactive liquid wastes are diluted in the
river, and consumption of the water by individuals at standard man consumption
rate (3,000 ml/day), the single intake by an individual would not exceed
one-third the yearly intake allowable by 10CFR20 for unidentified radioisotopes
(1 x 10-6 Ci/ml).
Radwaste liquids are processed on a batch basis. The design of the system
precludes direct discharge of either unprocessed or processed liquids without
first holding them up in the sample tanks where the liquid is analyzed for
activity levels. Procedural controls would be implemented to ensure that the
activity of processed liquid, after dilution, will not exceed the guideline
limits of 10CFR20, prior to liquids being released to the river.
VYNPS DSAR Revision 1 4.0-26 of 53
In order to release liquid from the sample tanks to the river, the sample pumps
must be started, valves opened, and the flow controller positioned. In
addition, a dilution water pump must be put into operation prior to discharge
of the processed liquid. An interlock precludes discharge of processed liquid
to the river when dilution water is unavailable.
The process radiation monitor in the discharge line from the sample tanks to
the river is provided to back up the administrative control provided by sample
tank liquid analysis. It provides a warning to the appropriate facility
personnel that the activity of the processed liquid is approaching ten times
the annual average concentration values of Appendix B, Table 2, Column 2, of
10CFR20.1001-2402. When appropriate, facility personnel could take action to
reduce processed liquid flow or terminating flow entirely to assure that the
releases do not exceed the limits for which the facility is licensed.
Sufficient administrative and design control is provided to prevent accidental
releases of liquid effluents from the Radwaste System.
Therefore, the design basis is considered met.
4.5.2.5 Inspection and Testing
The Liquid Radwaste System is normally operating on an "as-required" basis
thereby demonstrating the ability to perform its function without special
testing.
VYNPS DSAR Revision 1 4.0-27 of 53
TABLE 4.5.2.1
Vermont Yankee Radioactive Liquid Waste Processing Parameters
Waste Stream Input Sources Input Flow
Rates (gpd)
Fraction of Primary Coolant Activity (pca)
Holdup Time (Days) Available Process Decontamination Factors
Assumed
Fraction of Waste Stream Discharged
Collection Process Discharge Nuclide 1st Demin(a)
2nd Demin(b) Total DF
High Purity Waste
1) Drywell Equip. Drains
3400 1.0 I = 10 10 102
2) Reactor Bldg. Equip. Drains
3720 0.01
3) Radwaste Bldg. Equip. Drains
1060 0.01 0.75 0.15 1.11 Cs, Rb = 2 10 20 0.01
4) Turbine Bldg. Equip. Drains
2960 0.01
5) Condensate Phase Sep.
8100 2 x 10-6
6) Cleanup Phase Sep.
640 0.002 Other Nuclides =
10 10 102
7) Resin Rinse 5000 0.002
Low Purity Waste
1) Drywell Floor Drains
700 1.0 I = 10 10 102
2) Reactor Bldg. Floor Drains
2000 0.01 1.39 0.15 1.11 Cs, Rb = 2 10 20 0.01
3) Radwaste Bldg. Floor Drains
1000 0.01 Other Nuclides =
10 10 102
4) Turbine Bldg. Floor Drains
2000 0.01
Chemical Waste
1) Chem. Lab. Waste 100 0.02 I = 10 10 102
2) Lab. Drains 500 0.02 2.67 0.15 1.11 Cs, Rb = 2 10 20 0.01
3) Personal Shower and Decon. Drains
900 1.4x10-4 0.44 Other Nuclides =
10 10 102
Detergent Waste
1) Decon. Drains 900 1.4x10-4 0.44 0.15 1.11 I = 10 10 102 0.01
Cs, Rb = 2 10 20
Other Nuclides =
10 10 102
(a) Fuel Pool (Powdered Resin) Filter-Demineralizer
(b) Radwaste Deep Bed Demineralizer
NOTE: Data contained in this table is based on original 100% power operation, and is retained as historical information.
VYNPS DSAR Revision 1 4.0-28 of 53
TABLE 4.5.2.2
Vermont Yankee Liquid Radwaste System Tank Capacities
Tank Capacity Per Tank (Gal.)
Waste Collection Tank (1) 25,000 Waste Surge Tank (1) 35,000
Floor Drain Collection Tank (1) 25,000 Chemical Waste Tank (1) 4,000 Detergent Waste Tank (1) 1,000
Floor Drain Sample Tank (1) 10,000 Waste Sample Tank (2) 10,000
TABLE 4.5.2.3
Vermont Yankee Liquid Effluents
Assumption of Concentration Annual Releases to Discharge Canal in Primary Adjusted Detergent Total
Half-Life Coolant High Purity Low Purity Chemical Total Lws. Total Wastes
Nuclide (Days) (Micro Ci/ml) (Curies) (Curies) (Curies) (Curies) (Ci/Yr) (Ci/Yr) (Ci/Yr)
VYNPS DSAR Revision 1
4.0-29 of 53
CORROSION AND ACTIVATION PRODUCTS Na24 6.27E-01 8.72E-03 .00130 .00021 .00000 .00151 .01008 .00000 .01000
P32 1.43E+01 2.12E-04 .00010 .00002 .00000 .00012 .00078 .00000 .00078
Cr51 2.78E+01 5.31E-03 .00249 .00052 .00001 .00302 .02014 .00000 .02000
Mn54 3.03E+02 6.38E-05 .00003 .00001 .00000 .00004 .00025 .00000 .00025
Mn56 1.08E-01 3.90E-02 .00004 .00000 .00000 .00004 .00030 .00000 .00030
Fe55 9.49E+02 1.06E-03 .00051 .00011 .00000 .00062 .00415 .00000 .00420
Fe59 4.51E+01 3.19E-05 .00002 .00000 .00000 .00002 .00012 .00000 .00012
Co58 7.10E+01 2.13E-04 .00010 .00002 .00000 .00012 .00082 .00000 .00082
Co60 1.92E+03 4.25E-04 .00020 .00004 .00000 .00025 .00166 .00000 .00170
Cu64 5.35E-01 2.87E-02 .00352 .00054 .00001 .00407 .02713 .00000 .02700
Zn65 2.45E+02 2.13E-04 .00010 .00002 .00000 .00012 .00083 .00000 .00083
Zn69m 5.73E-01 1.92E-03 .00026 .00004 .00000 .00030 .00199 .00000 .00200
Zn69 3.95E-02 .0 .00028 .00004 .00000 .00032 .00214 .00000 .00210
W187 9.95E-01 3.00E-04 .00007 .00001 .00000 .00008 .00054 .00000 .00054
Np239 2.35E+00 7.24E-03 .00254 .00049 .00001 .00304 .02026 .00000 .02000
FISSION PRODUCTS
Br83 1.00E-01 2.13E-03 .00000 .00000 .00000 .00000 .00001 .00000 .00001
Sr89 5.21E+01 1.06E-04 .00005 .00001 .00000 .00006 .00041 .00000 .00041
Sr90 1.03E+04 6.38E-06 .00000 .00000 .00000 .00000 .00002 .00000 .00003
Sr91 4.03E-01 3.72E-03 .00030 .00004 .00000 .00034 .00227 .00000 .00230
Y91m 3.47E-02 .0 .00019 .00003 .00000 .00022 .00146 .00000 .00150
Y91 5.90E+01 4.25E-05 .00003 .00001 .00000 .00004 .00025 .00000 .00025
Sr92 1.13E-01 7.86E-03 .00001 .00000 .00000 .00001 .00008 .00000 .00008
Y92 1.47E-01 4.90E-03 .00011 .00001 .00000 .00012 .00082 .00000 .00082
Y93 4.24E-01 3.74E-03 .00033 .00005 .00000 .00037 .00249 .00000 .00250
Zr95 6.52E+01 7.44E-06 .00000 .00000 .00000 .00000 .00003 .00000 .00003
Nb95 3.50E+01 7.43E-06 .00000 .00000 .00000 .00000 .00003 .00000 .00003
Mo99 2.80E+00 2.08E-03 .00077 .00015 .00000 .00092 .00613 .00000 .00610
Tc99m 2.50E-01 1.76E-02 .00117 .00020 .00000 .00138 .00919 .00000 .00920
Ru103 3.95E+01 2.12E-05 .00001 .00000 .00000 .00001 .00008 .00000 .00008
Rh103m 3.95E-02 .0 .00001 .00000 .00000 .00001 .00008 .00000 .00008
Ru105 1.85E-01 1.69E-03 .00002 .00000 .00000 .00002 .00014 .00000 .00014
Rh105m 5.21E-04 .0 .00002 .00000 .00000 .00002 .00014 .00000 .00014
Rh105 1.50E+00 .0 .00007 .00001 .00000 .00008 .00053 .00000 .00053
Ru106 3.66E+02 3.19E-06 .00000 .00000 .00000 .00000 .00001 .00000 .00001
Rh106 3.47E-04 .0 .00000 .00000 .00000 .00000 .00001 .00000 .00001
Te129m 3.40E+01 4.25E-05 .00002 .00000 .00000 .00002 .00016 .00000 .00016
TABLE 4.5.2.3 (Continued) Vermont Yankee Liquid Effluents Concentration Annual Releases to Discharge Canal in Primary Adjusted Detergent Total Half-Life Coolant High Purity Low Purity Chemical Total Lws. Total Wastes Nuclide (Days) (Micro Ci/ml) (Curies) (Curies) (Curies) (Curies) (Ci/Yr) (Ci/Yr) (Ci/Yr)
VYNPS DSAR Revision 1 4.0-30 of 53
Te129 4.80E-02 .0 .00001 .00000 .00000 .00002 .00010 .00000 .00010
Te131m 1.25E+00 1.01E-04 .00003 .00000 .00000 .00003 .00021 .00000 .00021
Te131 1.74E-02 .0 .00000 .00000 .00000 .00001 .00004 .00000 .00004
I131 8.05E+00 5.24E-03 .00230 .00048 .00001 .00278 .01858 .00000 .01900
Te132 3.25E+00 1.04E-05 .00000 .00000 .00000 .00000 .00003 .00000 .00003
I132 9.58E-02 2.12E-02 .00002 .00000 .00000 .00002 .00011 .00000 .00011
I133 8.75E-01 1.90E-02 .00392 .00067 .00001 .00460 .03068 .00000 .03100
Cs134 7.50E+02 3.19E-05 .00008 .00002 .00000 .00009 .00062 .00000 .00062
I135 2.80E-01 1.65E-02 .00062 .00008 .00000 .00070 .00468 .00000 .00470
Cs136 1.80E+01 2.11E-05 .00005 .00001 .00000 .00006 .00039 .00000 .00039
Cs137 1.10E+04 1.45E-05 .00018 .00004 .00000 .00022 .00145 .00000 .00150
Ba137m 1.77E-03 .0 .00017 .00004 .00000 .00020 .00136 .00000 .00140
Ba140 1.28E+01 4.23E-04 .00019 .00004 .00000 .00023 .00155 .00000 .00160
Tritium Release 4 Curies per year
NOTE: Data contained in this table is based on original 100% power operation, and is retained as historical information.
La140 1.67E+00 .0 .00007 .00002 .00000 .00009 .00059 .00000 .00059
La141 1.62E-01 .0 .00000 .00000 .00000 .00000 .00003 .00000 .00003
Ce141 3.25E+01 3.18E-05 .00002 .00000 .00000 .00002 .00013 .00000 .00013
Ce143 1.38E+00 3.05E-05 .00001 .00000 .00000 .00001 .00007 .00000 .00007
Pr143 1.57E+01 4.23E-05 .00002 .00000 .00000 .00002 .00016 .00000 .00016
Ce144 2.84E+02 3.19E-06 .00000 .00000 .00000 .00000 .00001 .00000 .00001
Pr144 1.20E-02 .0 .00000 .00000 .00000 .00000 .00001 .00000 .00001
Nd147 1.11E+01 3.17E-06 .00000 .00000 .00000 .00000 .00001 .00000 .00001
All
Others 1.86E-01 .00000 .00000 .00000 .00001 .00004 0.0 .00004
Total
(Except
Tritium)
3.86E-01 02235 .00403 . .00005 02644 .17644 .00000 .18000
VYNPS DSAR Revision 1 4.0-31 of 53
TABLE 4.5.2.4
Activity Input to Liquid Radwaste System (Ci/yr)
Nuclide
ci/ml
PCA
Drywell
Equip.
Drains
Reactor
Bldg.
Equip.
Drain
Radwaste
Bldg.
Equip.
Drain
Turbine
Bldg
Equip.
Drain
Condensate
Phase Sep.
Cleanup
Phase
Sep.
Resin
Rinse
Drywell
Floor
Drains
Reactor
Bldg.
Floor
Drains
Radwaste
Bldg.
Floor
Drains
Turbine
Bldg.
Floor
Drains
Chem
Lab.
Waste
Lab.
Drains
Personal
Shower
and
Decon.
Drains
Na24 8.72E-03 3.3E+01 3.6E-01 1.02E-01 2.8E-01 1.6E-04 1.2E-02 9.6E-02 6.7E+00 1.9E-01 9.6E-02 1.9E-01 1.9E-02 9.6E-02 1.2E-03
P32 2.12E-04 7.9E-01 8.7E-03 2.5E-03 6.9E-03 3.8E-06 3.0E-04 2.3E-03 1.6E-01 4.7E-03 2.3E-03 4.7E-03 4.7E-04 2.3E-03 2.9E-05
Cr51 5.31E-03 2.0E+01 2.2E-01 6.2E-02 1.7E-01 9.6E-05 7.5E-03 5.9E-02 4.1E+00 1.2E-01 5.9E-02 1.2E-01 1.2E-02 5.9E-02 7.4E-04
Mn54 6.38E-05 2.4E-01 2.6E-03 7.5E-04 2.1E-03 1.1E-06 9.0E-05 7.0E-04 4.9E-02 1.4E-03 7.3E-04 1.4E-03 1.4E-04 7.0E-04 8.9E-06
Mn56 3.90E-02 1.47E+02 1.6E+00 4.6E-01 1.3E+00 7.0E-04 5.5E-02 4.3E-01 3.0E+01 8.6E-01 4.3E-01 8.6E-01 8.6E-02 4.3E-01 5.4E-03
Fe55 1.06E-03 3.9E+00 4.4E-02 1.2E-02 3.5E-02 1.9E-05 1.5E-03 1.2E-02 8.2E-01 2.3E-02 1.2E-02 2.3E-02 2.3E-02 1.2E-02 1.5E-04
Fe59 3.19E-05 1.2E-01 1.3E-03 3.7E-04 1.0E-03 5.7E-07 4.5E-05 3.5E-04 2.5E-02 7.0E-04 3.5E-04 7.0E-04 7.0E-05 3.5E-04 4.4E-06
Co58 2.13E-04 8.0E-01 8.8E-03 2.5E-03 7.0E-03 3.8E-06 3.0E-04 2.4E-03 1.6E-01 4.7E-03 2.4E-03 4.7E-03 4.7E-04 2.4E-03 3.0E-05
Co60 4.25E-04 1.6E+00 1.7E-02 5.0E-03 1.4E-02 7.7E-06 6.0E-04 4.7E-03 3.3E-01 9.4E-03 4.7E-03 9.4E-03 9.4E-04 4.7E-03 5.9E-05
Cu64 2.87E-02 1.1E+02 1.2E+00 3.4E-01 9.4E-01 5.2E-04 4.0E-02 3.2E-01 2.2E+01 6.3E-01 3.2E-01 6.3E-01 6.3E-02 3.2E-01 4.0E-03
Zn65 2.13E-04 8.0E-01 8.8E-03 2.5E-03 7.0E-03 3.8E-06 3.0E-04 2.4E-03 1.6E-01 4.7E-03 2.4E-03 4.7E-03 4.7E-01 2.4E-03 3.0E-05
Zn69m 1.92E-03 7.2E+00 7.9E-02 2.2E-02 6.3E-02 3.5E-05 2.7E-03 2.1E-02 1.5E+00 4.2E-02 2.1E-02 4.2E-02 4.2E-03 2.1E-02 2.7E-04
W198 3.00E-04 1.1E+00 1.2E-02 2.5E-03 9.8E-03 5.4E-06 4.2E-04 3.3E-03 2.3E-01 6.6E-03 3.3E-03 6.6E-03 6.6E-04 3.3E-03 4.2E-05
Np239 7.24E-03 2.7E+01 3.0E-01 8.5E-02 2.4E-01 1.3E-04 1.0E-02 8.0E-02 5.6E+00 1.6E-01 8.0E-02 1.6E-01 1.6E-02 8.0E-02 1.0E-03
Br83 2.13E-03 8.0E+00 8.8E-02 2.5E-02 7.0E-02 3.8E-05 3.0E-03 2.4E-02 1.6E+00 4.7E-02 2.4E-02 4.7E-02 4.7E-03 2.4E-02 3.0E-04
Sr89 1.06E-04 3.9E+00 4.4E-03 1.2E-03 3.5E-03 1.9E-06 1.5E-04 1.2E-03 8.2E-02 2.3E-03 1.2E-03 2.3E-03 2.3E-04 1.2E-03 1.5E-05
Sr90 6.38E-06 2.4E-02 2.6E-04 7.5E-05 2.1E-04 1.1E-07 9.0E-06 7.0E-05 4.9E-03 1.4E-04 7.0E-05 1.4E-04 1.4E-05 7.0E-05 8.9E-07
Sr91 3.72E-03 1.4E+01 1.5E-01 4.4E-02 1.2E-01 6.7E-05 5.2E-03 4.1E-02 2.9E+00 8.2E-02 4.1E-02 8.2E-02 8.2E-03 4.1E-02 5.2E-04
Y91 4.25E-05 1.6E-01 1.7E-03 5.0E-04 1.4E-03 7.7E-07 6.0E-05 4.7E-04 3.3E-02 9.4E-04 4.7E-04 9.4E-04 9.4E-05 4.7E-04 5.9E-03
Sr92 7.86E-03 2.9E+01 3.2E-01 9.2E-02 2.6E-01 1.4E-04 1.1E-02 8.7E-02 6.1E+00 1.7E-01 8.7E-02 1.7E-01 1.7E-02 8.7E-02 1.1E-03
Y92 4.90E-03 1.8E+01 2.0E-01 5.7E-02 1.6E-01 8.8E-05 6.9E-03 5.4E-02 3.8E+00 1.1E-01 5.4E-02 1.1E-01 1.1E-02 5.4E-02 6.8E-04
Y93 3.74E-03 1.4E+01 1.5E-01 4.4E-02 1.2E-01 6.7E-05 5.3E-03 4.1E-02 2.9E+00 8.3E-02 4.1E-02 8.3E-02 8.3E-03 4.1E-02 5.2E-04
Zr95 7.44E-06 2.8E-02 3.1E-04 8.7E-05 2.4E-04 1.3E-07 1.0E-05 8.2E-05 5.8E-03 1.6E-04 8.2E-05 1.6E-04 1.6E-05 8.2E-05 1.0E-06
Nb95 7.43E-06 2.8E-01 3.1E-04 8.7E-05 2.4E-04 1.3E-07 1.0E-05 8.2E-05 5.8E-03 1.6E-04 8.2E-05 1.6E-04 1.6E-05 8.2E-05 1.0E-06
Mo99 2.08E-03 7.8E+00 8.6E-02 2.4E-02 6.8E-02 3.7E-01 2.9E-03 2.3E-02 1.6E+00 4.6E-02 2.3E-02 4.6E-02 4.6E-03 2.3E-02 2.9E-04
Tc99m 1.76E-02 6.6E+01 7.2E-01 2.1E-01 5.8E-01 3.2E-04 2.5E-02 1.9E-01 1.4E+01 3.9E-01 1.9E-01 3.9E-01 3.9E-02 1.9E-01 2.4E-03
Ru103 2.12E-05 8.0E-02 8.7E-04 2.5E-04 6.9E-04 3.8E-07 3.0E-05 2.3E-04 1.6E-02 4.7E-04 2.3E-04 4.7E-04 4.7E-05 2.3E-04 2.9E-06
Ru105 1.69E-03 6.3E+00 6.9E-02 2.0E-02 5.5E-02 3.0E-05 2.4E-03 1.9E-02 1.3E+00 3.7E-02 1.9E-02 3.7E-02 3.7E-03 1.9E-02 2.3E-04
Ru106 3.19E-06 1.2E-02 1.3E-04 3.7E-05 1.0E-04 5.7E-08 4.5E-06 3.5E-05 2.5E-03 7.0E-05 3.5E-05 7.0E-05 7.0E-06 3.5E-05 4.4E-07
VYNPS DSAR Revision 1 4.0-32 of 53
TABLE 4.5.2.4
(Continued)
Activity Input to Liquid Radwaste System (Ci/yr)
Nuclide
ci/ml
PCA
Drywell
Equip.
Drains
Reactor
Bldg.
Equip.
Drain
Radwaste
Bldg.
Equip.
Drain
Turbine
Bldg.
Equip
Drain
Condensate
Phase Sep.
Cleanup
Phase
Sep.
Resin
Rinse
Drywell
Floor
Drains
Reactor
Bldg.
Floor
Drains
Radwaste
Bldg.
Floor
Drains
Turbine
Bldg.
Floor
Drains
Chem.
Lab.
Waste
Lab.
Drains
Personal
Shower
and
Decon.
Drains
Te129m 4.25E-05 1.6E-01 1.7E-03 5.0E-04 1.4E-03 7.7E-07 6.0E-06 4.7E-04 3.3E-02 9.4E-04 4.7E-04 9.4E-04 9.4E-05 4.7E-04 5.9E-06
Te131m 1.01E-04 3.8E-01 4.2E-03 1.2E-03 3.3E-03 1.8E-06 1.4E-04 1.1E-03 7.8E-02 2.2E-03 1.1E-03 2.2E-03 2.2E-04 1.1E-03 1.4E-05
I131 5.24E-03 2.0E+00 2.2E-01 6.1E-02 1.7E-01 9.4E-05 7.4E-03 5.8E-02 4.1E+00 1.2E-01 5.8E-02 1.2E-01 1.2E-02 5.8E-02 7.3E-04
Te132 1.04E-05 3.9E-02 4.3E-04 1.2E-04 3.4E-04 1.9E-07 1.5E-05 1.1E-04 8.0E-03 2.3E-04 1.1E-04 2.3E-04 2.3E-05 1.1E-04 1.4E-06
I132 2.12E-02 8.0E+01 8.7E-01 2.5E-01 6.9E-01 3.8E-04 3.0E-02 3.0E-02 1.6E+01 4.7E-01 3.0E-02 4.7E-01 4.7E-02 3.0E-02 2.9E-03
I133 1.90E-02 7.1E+01 7.8E-01 2.2E-01 6.2E-01 3.4E-04 2.7E-02 2.1E-01 1.5E+01 4.2E-01 2.1E-01 4.2E-01 4.2E-02 2.1E-01 2.6E-03
Cs134 3.19E-05 1.2E-01 1.3E-03 3.7E-04 1.0E-03 5.7E-07 4.5E-05 3.5E-04 2.5E-02 7.0E-04 3.5E-04 7.0E-04 7.0E-05 3.5E-04 4.4E-06
I135 1.65E-02 6.2E+01 6.8E-01 1.9E-01 5.4E-01 3.0E-04 2.3E-02 1.8E-01 1.3E+01 3.6E-01 1.8E-01 3.6E-01 3.6E-02 1.8E-01 2.3E-03
Cs136 2.11E-05 7.9E-02 8.7E-04 2.5E-04 6.9E-04 3.8E-07 3.0E-05 2.3E-04 1.6E-02 4.7E-04 2.3E-04 4.7E-04 4.7E-05 2.3E-04 2.9E-06
Cs137 7.45E-05 2.8E-01 3.1E-03 8.7E-04 2.4E-03 1.3E-06 1.1E-04 8.2E-04 5.8E-02 1.6E-03 8.2E-04 1.6E-03 1.6E-04 8.2E-04 1.0E-05
Ba140 4.23E-04 1.59E+00 1.7E-02 4.9E-03 1.4E-02 7.6E-06 6.0E-04 4.7E-03 3.3E-01 9.3E-03 4.7E-03 9.3E-03 9.3E-04 4.7E-03 5.9E-05
Ce141 3.18E-05 1.2E-01 1.3E-03 3.7E-04 1.0E-03 5.7E-07 4.5E-05 3.5E-04 2.5E-02 7.0E-04 3.5E-04 7.0E-04 7.0E-05 3.5E-04 4.4E-06
Ce143 3.05E-05 1.1E-01 1.3E-03 3.6E-04 1.0E-03 5.5E-07 4.3E-05 3.4E-04 2.4E-02 6.7E-04 3.4E-04 6.7E-04 6.7E-05 3.4E-04 4.2E-06
Pr143 4.23E-05 1.6E-01 1.7E-03 4.9E-04 1.4E-03 7.6E-07 6.0E-05 4.7E-04 2.3E-02 9.3E-04 4.7E-04 9.3E-04 9.3E-05 4.7E-04 5.9E-06
Ce144 3.19E-06 1.2E-02 1.3E-04 3.7E-05 1.0E-04 5.7E-08 4.5E-06 3.5E-05 2.5E-03 7.0E-05 3.5E-05 7.0E-05 7.0E-06 3.5E-05 4.4E-07
Nd147 3.17E-06 1.2E-02 1.3E-04 3.7E-05 1.0E-04 5.7E-08 4.5E-06 3.5E-05 2.5E-03 7.0E-05 3.5E-05 7.0E-05 7.0E-06 3.5E-05 4.4E-07
All
Others 1.86E-01 7.0E+02 7.6E+00 2.2E+00 6.1E+00 3.3E-03 2.6E-01 2.1E+00 1.4E+02 4.1E+00 2.1E+00 4.1E+00 4.1E-01 2.1E+00 2.6E-02
NOTE: Data contained in this table is based on original 100% power operation, and is retained as historical information
VYNPS DSAR Revision 1
4.0-33 of 53
TABLE 4.5.2.5
Radionuclide Discharge Concentrations Nuclide
Total Annual
Release (Ci/Yr)
Discharge Concentration
(Ci/ml) ECLw
(Ci/ml) Fraction of
ECL
Na24 1.0x10-2 3.1x10-10 5x10-5 6.2x10-6
P32 7.8x10-4 2.4x10-11 9x10-6 2.7x10-7
Cr51 2.0x10-2 6.3x10-10 5x10-4 1.3x10-6
Mn54 2.5x10-4 7.8x10-12 3x10-5 2.6x10-7
Mn56 3.0x10-4 9.4x10-12 7x10-5 1.3x10-7
Fe55 4.2x10-3 1.3x10-10 1x10-4 1.3x10-6
Fe59 1.2x10-4 3.8x10-12 1x10-5 3.8x10-7
Co58 8.2x10-4 2.6x10-11 2x10-5 1.3x10-6
Co60 1.7x10-3 5.3x10-11 3x10-6 1.8x10-5
Cu64 2.7x10-2 8.5x10-10 2x10-4 4.3x10-6
Zn65 8.3x10-4 2.6x10-11 5x10-6 5.2x10-6
Zn69m 2.0x10-3 6.3x10-11 6x10-5 1.1x10-6
Np239 2.0x10-2 6.3x10-10 2x10-5 3.2x10-5
Br83 1.0x10-5 3.1x10-13 9x10-4 3.4x10-10
Sr89 4.1x10-4 1.3x10-11 8x10-6 1.6x10-6
Sr90 3.0x10-5 9.4x10-13 5x10-7 1.9x10-6
Sr91 2.3x10-3 7.2x10-11 2x10-5 3.6x10-6
Y91 2.5x10-4 7.8x10-12 8x10-6 9.8x10-7
Sr92 8.0x10-5 2.5x10-12 4x10-5 6.3x10-8
Y92 8.2x10-4 2.6x10-11 4x10-5 6.5x10-7
Y93 2.5x10-3 7.8x10-11 2x10-5 3.9x10-6
Zr95 3.0x10-5 9.4x10-13 2x10-5 4.7x10-8
Nb95 3.0x10-5 9.4x10-13 3x10-5 3.1x10-8
Mo99 6.1x10-3 1.9x10-10 2x10-5 9.5x10-6
Tc99m 9.2x10-3 2.9x10-10 1x10-3 2.9x10-7
Ru103 8.0x10-5 2.5x10-12 3x10-5 8.3x10-8
Ru105 1.4x10-4 4.4x10-12 7x10-5 6.3x10-8
Ru106 1.0x10-5 3.1x10-13 3x10-6 1.0x10-7
Te129m 1.6x10-4 5.0x10-12 7x10-6 7.1x10-7
Te131m 2.1x10-4 6.6x10-12 8x10-6 8.3x10-7
I131 1.9x10-2 6.0x10-10 1x10-6 6.0x10-4
Te132 3.0x10-5 9.4x10-13 9x10-6 1.0x10-7
I132 1.1x10-4 3.4x10-12 1x10-4 3.4x10-8
I133 3.1x10-2 9.7x10-10 7x10-6 1.4x10-4
Cs134 6.2x10-4 1.9x10-11 9x10-7 2.1x10-5
I135 4.7x10-3 1.5x10-10 3x10-5 5.0x10-6
Cs136 3.9x10-4 1.2x10-11 6x10-6 2.0x10-6
Cs137 1.5x10-3 4.7x10-11 1x10-6 4.7x10-5
Ba140 1.6x10-3 5.0x10-11 8x10-6 6.3x10-6
Ce141 1.3x10-4 4.1x10-12 3x10-5 1.4x10-7
Ce143 7.0x10-5 2.2x10-12 2x10-5 1.1x10-7
Pr143 1.6x10-4 5.0x10-12 2x10-5 2.5x10-7
Ce144 1.0x10-5 3.1x10-13 3x10-6 1.0x10-7
Nd147 1.0x10-5 3.1x10-13 2x10-5 1.6x10-8
All others 4.0x10-5 1.3x10-12 1x10-6 1.3x10-6
Tritium 4.0 1.3x10-7 1x10-3 1.3x10-4
NOTE: Data contained in this table is based on original 100% power operation, and is retained as historical
information.
VYNPS DSAR Revision 1 4.0-34 of 53
Vermont Yankee
Defueled Safety Analysis Report
Radwaste Area – Plan View
Figure 4.5.2-8
VYNPS DSAR Revision 1
4.0-35 of 53
4.6 SOLID WASTE MANAGEMENT
4.6.1 Solid Radwaste System
4.6.1.1 Objective
The Solid Radwaste System collects and processes radioactive solid wastes for
possible temporary on-site storage and off-site shipment for permanent disposal.
4.6.1.2 Design Basis
The Solid Radwaste System shall be designed to package radioactive solid wastes
for ultimate off-site shipment for disposal in accordance with applicable
published regulations.
4.6.1.3 Description
4.6.1.3.1 General
The Solid Radwaste System is a contiguous part of the Liquid Radwaste System and
is an integral part of the Radwaste Building. The system processes wet and dry
solid wastes. Because of physical differences and differences in radioactivity
or contamination levels, various methods are employed for processing and
packaging the solid radwaste. Wet solid wastes are packaged in appropriate
liners or high integrity containers for transportation within licensed shipping
casks. Dry active waste is collected in general design packages for shipment to
a licensed disposal site or a licensed processing facility for volume reduction.
Each type of waste is kept segregated to reduce shielding requirements for
storage.
Table 4.6.1 shows a history of both the wet and dry waste volumes and activity
levels that have been processed for off-site disposal. Subsequent to 1992, this
data is contained in the Radioactive Effluent Release Report.
4.6.1.3.2 Wet Wastes
Wet wastes consist of spent demineralizer resins and filter sludge. These are
pumped from the phase separators or waste sludge tanks as a slurry to disposable
liners preplaced within the licensed transportation casks. The slurry is then
dewatered from within the liner using a remote dewatering system located in the
Cask Room. The Dewatering System is kept in continuous operation as long as the
cask liner is being filled. When the cask liner is full, a high-level trip
recirculates the resin slurry to either the waste collector tank or to one of
the condensate phase separators.
VYNPS DSAR Revision 1
4.0-36 of 53
The Dewatering System level instruments indicate in the Radwaste Building
Control Room.
The Dewatering System is accessible for cleaning and maintenance when not being
operated. The Dewatering System and its associated controls are arranged for
remote operation, which is manually initiated.
When feed to the Dewatering System is stopped, the feed piping is flushed in
accordance with plant procedures. External water connections are provided for
cleaning and decontamination.
The radioactive wet wastes are transported in licensed steel/lead casks. The
casks contain disposable steel liners or high integrity containers. The casks
are placed on trolleys and rolled on tracks below the Dewatering System fill
head. The solid wastes are processed through the fill head into the cask liner.
After filling, the liner is closed and the cask is rolled to a decontamination
area in the Radwaste Building where the cask is wiped or washed down to remove
surface contamination. The cask is lifted to a truck for transportation to the
on-site waste storage area or off-site to a waste disposal site. Design and use
of the cask are in accordance with 10CFR71 and 49CFR170-178 regulations of the
Department of Transportation. All resin shipments are via sole-use vehicles.
There are associated high and high-high level alarms which initiate the
following:
1. High level - reposition the three-way V20-422 valve to recirculate resin
slurry.
2. High-high level - cessation of feed.
Spent resins from the various filter systems are flushed to the Radwaste
Processing System and normally combined for dewatering through the Dewatering
System. The moisture content of the processed spent resins is less than 1% by
weight.
The principal gamma-emitting radionuclides normally found in the spent resins
include Manganese-54, Cobalt-58 and 60, Cesium-134 and 137, and Zinc-65. The
volume of spent resin and filter sludge is provided in the yearly Radioactive
Effluent Release Report.
VYNPS DSAR Revision 1
4.0-37 of 53
4.6.1.3.3 Dry Wastes
Dry wastes consist of air filters, miscellaneous paper, rags, shoe covers, etc.,
from contaminated areas; contaminated clothing, tools, and equipment parts,
which cannot be effectively decontaminated; solid laboratory wastes; used
reactor equipment such as poison curtains, spent control rod blades, fuel
channels and in-core ion chambers; and large pieces of equipment.
The disposition of a particular item of waste is determined by its radiation
level and type, and the availability of disposal space. Because of high
activation and contamination level, used reactor equipment is stored in the fuel
storage pool for sufficient time to obtain optimum radioactive decay before
removal and final disposal. Most solid radwaste such as contaminated clothing,
rags, and paper can be handled manually because of low radioactivity or
contamination levels.
Dry Active Waste (DAW) is collected into shipping containers to be sent to an
off-site disposal site or an off-site waste processor for volume reduction.
Table 4.6.1 indicates the volume of compacted dry waste that has been shipped
for disposal between 1985 and 1992. This includes material sent directly from
Vermont Yankee and from various vendors after processing. The dry compacted
waste comprises about 65% of volume of total waste during the time period. The
volume for years subsequent to 1992 is contained in the Radioactive Effluent
Release Report.
The principal radionuclides in the dry active waste are Cesium-134, Cesium-137,
Cobalt-60, Iron-55, Manganese-54, and Zinc-65. Other nuclides which are
generally detected in the waste include Chromium-51, Cobalt-58,
Barium-Lanthanum-140, Cerium-141, Iron-59, Antomony-124, and Zirconium-95. The
ratios of these isotopes vary. Samples are drawn periodically to determine
current ratios and identify trends.
4.6.1.4 Inspection and Testing
The Solid Radwaste System is normally operated on a regular basis thereby
demonstrating functionality without special testing.
VYNPS DSAR Revision 1
4.0-38 of 53
TABLE 4.6.1.1
Solid Radwaste Annual Disposal History
Spent Resin and Filter Sludge Dry Processed Trash
Year Volume (ft3)
Activity (Ci)
Volume (ft3)
Activity (Ci)
1985 3,383 254 9,940 8.9
1986 1,836 196 9,018 16.6
1987 2,892 287 4,968 12.2
1988 2,655 417 3,467 7.7
1989* 171 2 0 0.0
1990* 0 0 0 0.0
1991 7,937 1,568 7,872 40.2
1992 2,391 476 3,238 51.7
Data for subsequent years is contained in the Radioactive Effluent Release Report pursuant to Technical Specifications.
* Vermont Yankee was denied access to disposal facilities.
VYNPS DSAR Revision 1
4.0-39 of 53
4.7 EFFLUENT RADIOLOGICAL MONITORING AND SAMPLING
4.7.1 Process Radiation Monitoring Instrumentation
A number of radiation monitors and monitoring systems are provided on process
liquid and ventilation lines that may serve as discharge routes for radioactive
materials. The monitors include the following:
Plant Stack Radiation Monitoring System
Process Liquid Radiation Monitoring System
Reactor Building Ventilation Radiation Monitoring System
These systems are described individually in the following paragraphs.
4.7.1.1 Plant Stack Radiation Monitoring System
4.7.1.1.1 Objective
The objective of the Plant Stack Radiation Monitoring System is to
representatively sample, monitor, indicate, and record the radioactivity level
of the station effluent gases being discharged from the plant stack and to alert
personnel in the event radiation levels approach or exceed pre-established
limits.
4.7.1.1.2 Design Basis
1. The Plant Stack Radiation Monitoring System shall provide a clear
indication to operations personnel of the current release level of
radioactive materials to the environs.
2. The Plant Stack Radiation Monitoring System shall record the rate of
release of radioactive materials to the environs so that determination of
the total amounts of activity release is possible.
4.7.1.1.3 Description
The Plant Stack Radiation Monitoring System is shown on Drawing 5920-3994, and
specifications are given in Table 4.7.1.3. The system consists of two (2)
radiation monitors (Stack Gas I and Stack Gas II).
The primary channel provides for the continuous monitoring of radioactive gas in
the plant stack effluent. It also provides filter media to be analyzed in the
plant laboratory by gamma spectroscopy to evaluate long-lived isotopic
composition of particulates in plant stack effluents.
VYNPS DSAR Revision 1
4.0-40 of 53
The primary stack monitoring channel consists of four (4) sampling chambers and
two (2) radiation monitors (Stack Gas I and II). The monitors observe the
radio-gas activity, and composites of long-lived particulates, iodine, and
tritium can be collected for laboratory analysis.
The sample flow is withdrawn from the plant stack through an isokinetic sample
probe located at elevation 464'-0", approximately 217 feet above the point where
the gases enter the stack. The sample train is branched prior to the point of
measurement. Branch I consists of one I-131 charcoal cartridge filter and one
radio-gas monitor with associated 8 cfm air pump and flow indicator. Branch II
is a duplicate of Branch I with the additional capability to sample gaseous
tritium. The fixed filters and tritium samplers can be changed on a routine
schedule. The plant radiochemistry laboratory analyzes filter media by gamma
spectroscopy to evaluate long-lived isotopic particulate and I-131 composition.
The tritium samplers are analyzed by liquid scintillation spectrometry.
Remote controls for pump motors are located in the station Main Control Room.
The sample flow is directed back to the stack at the completion of the
monitoring process.
All other monitoring equipment is located in an enclosure at the base of the
plant stack at grade level (elevation 250'-0"). Facilities for the collection
of air particulates and radio-gas grab samples are provided at elevation 462',
several feet downstream of the isokinetic sample probe. Facilities are also
available for sampling prior to the monitoring system at the base level at the
stack.
The monitors in the primary channel will indicate and alarm in the station Main
Control Room; no control action is provided by this system. Each monitor is
equipped with a sensor, a power supply, a logarithmic rate meter, and a trip
unit. The readout of each normal range monitor is continuously recorded in the
station Main Control Room.
Each trip unit has an adjustable trip and also signals loss of high voltage
power supply, low flow, and loss of input signal.
VYNPS DSAR Revision 1
4.0-41 of 53
4.7.1.1.4 Inspection and Testing
Each monitor is inspected according to surveillance procedures and is tested in
accordance with the Off-Site Dose Calculation Manual. Stack Gas I and II are
calibrated and functionally tested per the Off-Site Dose Calculation Manual.
4.7.1.2 Process Liquid Radiation Monitoring System
4.7.1.2.1 Objective
On process streams that normally discharge to the environs, process liquid
radiation monitors are provided to indicate when pre-established limits for the
normal release of radioactive material to the environs are exceeded.
On process streams that do not discharge to the environs, process liquid
monitors are provided to indicate process system malfunctions by detecting the
accumulation of radioactive material in a normally uncontaminated system.
4.7.1.2.2 Design Basis
Process liquid radiation monitors located in streams that normally discharge to
the environs shall provide a clear indication whenever the radioactivity level
in the stream reaches or exceeds pre-established limits for the discharge of
radioactive material to the environs.
Process liquid radiation monitors located in streams that do not discharge to
the environs shall provide a clear indication whenever the radioactivity level
in the stream reaches or exceeds a pre-established limit.
4.7.1.2.3 Description
The processes being monitored are given in Table 4.7.1.1 and monitor the
discharge from the Liquid Radwaste and service water systems. Instrumentation
is connected to the ±24 V dc system.
Each channel has a scintillation detector, a radiation monitor, and strip chart
recorder. A representative sample may be continuously extracted from either of
two possible points of discharge and monitored for radioactivity. A radwaste
system recorder is located in the Radwaste Building Control Room. All monitors
and the other recorders are located in the Main Control Room.
VYNPS DSAR Revision 1
4.0-42 of 53
Each channel has an upscale trip to indicate high radiation level and one
downscale trip to indicate instrument trouble. The trips give an alarm but no
control action.
The Liquid Radwaste System provides for collection of waste liquids through
various drainage systems. Because of high conductivity, some of the waste
liquids may not be economically purified by demineralization. Consequently,
some liquid containing radioactivity may eventually be discharged from the
system. The process liquid monitoring channel on the Liquid Radwaste System
discharge indicates discharge radiation levels.
The Service Water System serves as the heat sink for the Standby Fuel Pool
Cooling System. The water circulated through the heat exchangers by the Standby
Fuel Pool Cooling System will be spent fuel pool water, which may have a
significant activity level. Changes in the normal radiation level in the
service water discharge could indicate leakage in the Standby Fuel Pool Cooling
heat exchangers.
The environmental and power supply design conditions are given in Table 4.7.1.2.
The process liquid radiation monitors for radwaste and service water discharges
have radiation detection and monitoring characteristics sufficient to inform
facility personnel whenever radiation levels in the discharges rise above preset
limits.
4.7.1.2.4 Inspection and Testing
All alarm trip circuits can be tested by using test signals or portable gamma
sources.
Surveillances are performed as required by the Off-Site Dose Calculation Manual.
4.7.1.3 Reactor Building Ventilation Radiation Monitoring System
4.7.1.3.1 Objective
The objective of the Reactor Building Ventilation Radiation Monitoring System is
to indicate whenever abnormal amounts of radioactive material exist in the
Reactor Building ventilation exhaust.
VYNPS DSAR Revision 1
4.0-43 of 53
4.7.1.3.2 Design Basis
The Reactor Building Ventilation Radiation Monitoring System shall provide a
clear indication to facility personnel whenever abnormal amounts of
radioactivity exist in the Reactor Building ventilation exhaust.
4.7.1.3.3 Description
The Reactor Building Ventilation Radiation Monitoring System is shown on Drawing
5920-00526, and characteristics are given in Table 4.7.1.1. The system consists
of two sets of exhaust system monitors with one set of detectors located in the
refuel floor zone at one half the distance between the centerline of the reactor
vessel and centerline of the fuel pool, near the wall and 10 feet above the
refuel floor. One detector is located on one side of the refuel pool and the
other on the opposite side. The other set of detectors is located in contact
with the Reactor Building exhaust duct, upstream of the exhaust ventilation
isolation valve on elevation 280 of the Reactor Building.
Each set includes two individual channels. Each channel includes a
Geiger-Muller type detector and a combined indicator and trip unit. Both
channels share a two-pen strip chart recorder. All equipment is located in the
Main Control Room except the detectors.
Power for this system is from 120 V ac buses.
VYNPS DSAR Revision 1
4.0-44 of 53
TABLE 4.7.1.1 PROCESS RADIATION MONITORING SYSTEMS CHARACTERISTICS
Monitoring System
Instrument Range (1)
Instrument Scale
Upscale Trips Per Channel
Downscale Trips Per Channel
Liquid Process (17-351)
10-1 to 106 counts per second (2)
7 Decade Log 1 1
Reactor Building Ventilation Exhaust (17-452A, B)
0.1 mR/hr to 1 R/hr
4 Decade Log
Reactor Building Refuel Floor (17-453A, B)
1 to 104 hr
mR
4 Decade Log
(1) Range of measurements is dependent on items such as the source geometry, background radiation,
shielding, energy levels, and method of sampling. (2) Readout is dependent upon the pulse height discriminator setting.
VYNPS DSAR Revision 1
4.0-45 of 53
TABLE 4.7.1.2
PROCESS RADIATION MONITORING SYSTEM ENVIRONMENTAL AND
POWER SUPPLY DESIGN CONDITIONS
Sensor Location Main Control Room
Parameter Design
Requirements Range Design
Requirements Range
Temperature 25°C 0°C to 60°C 25°C 5° to +50°C
Relative Humidity
50% 20 to 98% 50% 20 to 90%
Power, AC 115 V 60 Hz
±10% ±5%
115 V 60 Hz
±10% ±5%
Power, DC +24 V dc -24 V dc
+22 to +29 V dc -22 to -29 V dc
+24 V dc -24 V dc
+22 to +29 V dc -22 to -29 V dc
VYNPS DSAR Revision 1
4.0-46 of 53
TABLE 4.7.1.3
PLANT STACK RADIATION MONITORING SYSTEM CHARACTERISTICS
Monitor Type Instrument Range Instrument Scale
Type Detector Remarks
Radio-Gas Monitors I & II (17-156, 157)
10 to 107 cpm 6 Decade Digital
Beta Scintillation
VYNPS DSAR Revision 1
4.0-47 of 53
4.7.2 Area Radiation Monitoring System
4.7.2.1 Objectives
The objectives of the Area Radiation Monitoring System are:
1. To warn of abnormal gamma radiation levels in areas where radioactive material
may be present, stored, handled or inadvertently introduced.
2. To warn facility personnel whenever abnormal concentrations of airborne
radioactive materials exist in the Reactor Building.
4.7.2.2 Design Basis
1. The Area Radiation Monitoring System shall provide facility personnel with a
record and an indication of gamma radiation levels at selected locations within
the various facility buildings and radioactive airborne concentrations within the
Reactor Building.
2. The Area Radiation Monitoring System shall provide local alarms where it is
necessary to warn personnel of substantial immediate changes in radiation levels.
4.7.2.3 Description
4.7.2.3.1 Monitors
1. Area Gamma Radiation Monitoring System
The Area Gamma Radiation Monitoring System is shown as a functional block
diagram on Drawing 5920-430, Sh.1. A typical channel consists of a combined
indicator and trip unit, a shared power supply, and computer points for selected
monitors. Some channels have, in addition, a local audio alarm auxiliary unit.
Each monitor has an upscale trip that indicates high radiation and a downscale
trip that may indicate instrument trouble. These trips sound alarms but cause
no control action. The system is powered from the 120 V ac instrument bus. The
trip circuits are set so that loss of power causes an alarm. The environmental
and power supply design conditions are given in Table 4.7.2.1.
2. Area Airborne Radiation Monitoring System
The Reactor Building Area Airborne Radiation Monitoring System is shown as a
functional block diagram in Figure 4.7.2-2. Applicable specifications are
provided in Table 4.7.2.3. The Reactor Building Area Airborne Radiation
Monitoring System is a two (2) channel system employing a continuous air
particulate monitor and an off-line radiogas monitor located within a single
enclosure.
VYNPS DSAR Revision 1
4.0-48 of 53
The air particulate monitor consists of a continuous moving tape sampler with a
beta scintillation detector to provide for the continuous monitoring of air
particulates. Each off-line gas monitor contains a beta scintillation probe for
measurement of radiogas.
The sample for the Reactor Building Area Airborne Monitoring System is withdrawn
from the Reactor Building Exhaust Ventilation System through an isokinetic
sample probe located in the exhaust duct. An air pump with flow indicator and a
low flow alarm is used to obtain the required sample flow. The sample is
directed back to the ventilation duct at the completion of the monitoring
process.
The air particulate and radiogas monitor will indicate an alarm in the station
Main Control Room; no control action is provided. The monitor is equipped with
a sensor, a power supply, a logarithmic ratemeter and trip unit. Trip units
have adjustable trips which may be verified by the use of a remotely operated
radioactive check source mechanism; trip units also signal loss of high voltage
power supply, low sample flow and loss of signal input. The monitor readout is
continuously recorded on a recorder located in the station Main Control Room.
4.7.2.3.2 Locations
Work areas where gamma monitors will be located are tabulated in Table 4.7.2.2.
Annunciation and indication are provided in the Main Control Room.
4.7.2.4 Inspection and Testing
Area Gamma Radiation Monitoring System
An internal trip test circuit, adjustable over the full range of the trip circuit,
is provided. The test signal is fed into the indicator and trip unit input so that
a meter reading is provided in addition to a real trip. All trip circuits are of
the latching type and must be manually reset at the front panel.
A portable calibration unit is also provided. This is a test unit designed for use
in the adjustment procedure for the area radiation monitor sensor and converter
unit. It provides five gamma radiation levels for calibration purposes. A cavity
in the calibration unit is designed to receive the sensor and converter unit.
Located on the back wall of the cylindrical lower half of the cavity is a window
through which radiation from the source emanates. A chart on each unit indicates
the radiation levels available from the unit for the various control settings.
VYNPS DSAR Revision 1
4.0-49 of 53
Reactor Building Airborne Radiation Monitoring System
The Monitoring System includes a built-in check source for each detector. The check
source is operated from the Main Control Room. Alarm circuits can be tested by
using the built-in check source.
VYNPS DSAR Revision 1
4.0-50 of 53
TABLE 4.7.2.1 AREA RADIATION MONITORING SYSTEM ENVIRONMENTAL AND POWER SUPPLY DESIGN CONDITIONS Sensor Location Control Room Design Design Parameter Requirements Range Requirements Range
Temperature 25°C 0° to 60°C 25°C 5° to 50°C Relative 50% 20 to 100% 50% 20 to 90% Humidity
Power 120 V ±10% 120 V ±10% 60 Hz ±5% 60 Hz ±5%
VYNPS DSAR Revision 1
4.0-51 of 53
TABLE 4.7.2.2 LOCATIONS OF AREA RADIATION MONITORS Station Number Location 1 Reactor Building Supp. Chamber Catwalk 232' 2 Reactor Building North Pers. Access 252' 3 Reactor Building South R.R. Access 252' 4 Reactor Building TIP Room 252' 5 Reactor Building Reactor Pers. Acc. Hatch 252' 6 Reactor Building Elev. Ent. 280' 7 Reactor Building CRD Repair 252' 8 Reactor Building Elev. Ent. 303' 9 Reactor Building RCUW Sample Sink 303' 10 Reactor Building Elev. Ent. 318' 11 Reactor Building RCUW Panel 318' 12 Reactor Building Elev. Ent. 345' 14 Reactor Building West Refuel 345' 15 Reactor Building Spent Fuel Pool 345' 16 Reactor Building New Fuel Vault 345' 17 Radwaste Recirc. Pump Room 252' 18 Radwaste R.W. Oper. Area 252' 19 Radwaste Pump and Tank Area 230'
VYNPS DSAR Revision 1 4.0-52 of 53
TABLE 4.7.2.3
REACTOR BUILDING AREA AIRBORNE RADIATION MONITORING SYSTEM
Monitor Type
Instrument Range
Instrument Scale
Type Detector
Remarks
Air Particulate Monitor
10 to 107 cpm 6 Decade Log Digital
Beta Scintillation
Tape transport mechanism - tape speed selectable .5, 1, 2, and 10 in/hr; alarm for broken tape and low flow
Radio-Gas Monitor
10 to 107 cpm 6 Decade Log Digital
Beta Scintillation
VYNPS DSAR Revision 1 4.0-53 of 53
Vermont Yankee
Defueled Safety Analysis Report
Reactor Building Area Airborne
Radiation Monitoring System
Figure 4.7.2-2
VYNPS DSAR Revision 1 5.0-1 of 5
CONDUCT OF OPERATIONS TABLE OF CONTENTS Section Title Page
5.1 ORGANIZATION AND RESPONSIBILITY ..................................... 2
5.2 TRAINING .............................................................. 2
5.2.1 Program Description (General) ............................... 2
5.2.2 General Employee Training ................................... 2
5.2.2.1 Access to Plant ................................. 2
5.2.3 Fire Brigade Training ....................................... 2
5.2.4 Operations Training ......................................... 2
5.2.5 Craft, Technician, and Engineering Staff Position (ESP) Training ..................................... 3
5.2.6 Training Records ............................................ 3
5.2.7 Training Program Approval and Evaluation .................... 3
5.2.8 Responsibility .............................................. 3
5.3 EMERGENCY PLAN ........................................................ 4
5.4 QUALITY ASSURANCE PROGRAM ............................................. 4
5.4.1 Scope ....................................................... 4
5.4.2 Responsibilities ............................................ 4
5.4.3 Implementation .............................................. 4
5.4.4 Management Evaluation ....................................... 5
5.5 REVIEW AND AUDIT OF OPERATIONS ........................................ 5
5.5.1 General ..................................................... 5
5.5.2 Independent Safety Review ................................... 5
5.5.3 Safety Review Committee ..................................... 5
5.6 TECHNICAL REQUIREMENTS MANUAL ......................................... 5
VYNPS DSAR Revision 1 5.0-2 of 5
5.1 ORGANIZATION AND RESPONSIBILITY
The Vermont Yankee Nuclear Power Station organization, including the
responsibilities and duties of staff personnel, are detailed in the Vermont
Yankee Quality Assurance Program Manual.
5.2 TRAINING
5.2.1 Program Description (General)
The objective of the Training Program is to provide qualified personnel to
operate and maintain the permanently defueled facility in a safe manner,
including the storage and handling of irradiated fuel. All operations, craft,
technician, engineering staff, and general employee training requirements are
described in position-specific program descriptions or procedures. Training
programs are implemented and maintained using a Systems Approach to Training
(SAT), in accordance with 10CFR50.120, Training and Qualification of Nuclear
Power Plant Personnel, and ANSI/ANS 3.1, 1978, Selection, Qualification, and
Training of Personnel for Nuclear Power Plants.
5.2.2 General Employee Training
All persons permanently employed at the facility shall be trained in the
applicable following areas commensurate with their job duties:
1. Chemical and Hazardous Material Program
2. Radiological Health and Safety Program
3. Site Emergency Plans
4. Industrial Safety
5. Fire Protection
6. Security
7. Quality Assurance
8. Fitness for Duty
5.2.2.1 Access to Plant
Requirements to gain access to the facility protected area, including training
requirements, are contained in applicable facility procedures.
5.2.3 Fire Brigade Training
Fire brigade training for appropriate facility personnel meets the
requirements of NFPA 600, Standard on Industrial Fire Brigades.
5.2.4 Operations Training
The initial and continuing training programs for the personnel performing
operator functions, including certified fuel handler and shift manager, are
based on a SAT.
VYNPS DSAR Revision 1 5.0-3 of 5
5.2.5 Craft, Technician, and Engineering Staff Position (ESP) Training
The initial and continuing training programs for the instrument control
technician, chemistry technician, radiation protection technician, plant
mechanic (electrical and mechanical maintenance), and engineering staff
positions are based on a SAT.
5.2.6 Training Records
Records of employee and contractor participation in, and completion of,
training activities are maintained in accordance with the VY records retention
policy.
5.2.7 Training Program Approval and Evaluation
The Vermont Yankee position-specific training program descriptions are
approved by appropriate Training Department and facility management, as
specified in applicable facility procedures. This ensures that the content and
the intent of the training programs provide the necessary training for
personnel associated with the safe storage and handling of irradiated fuel and
management of radioactive waste. Training processes are controlled and
maintained in accordance with applicable Training directives.
The effectiveness of training programs is evaluated by the performance of
employees in carrying out their assigned duties, by performance on facility
evaluations, and the employment of various types of feedback mechanisms. The
results of the evaluations are maintained in accordance with applicable
records retention requirements.
5.2.8 Responsibility
As delegated by the responsible manager, the Superintendent, Training is
responsible for the conduct and administration of the specified training
activities, including:
1. Initial and continuing training programs for the non-certified operator,
certified fuel handler and shift manager.
2. Fire brigade training.
3. Initial and continuing training programs for instrumentation and control,
maintenance, and engineering staff positions.
4. Initial and continuing training programs for chemistry and radiation
protection positions.
5. General employee training.
VYNPS DSAR Revision 1 5.0-4 of 5
5.3 EMERGENCY PLAN
The emergency plan for the Vermont Yankee Nuclear Power station was originally
issued in accordance with NRC's regulations on April 1, 1981. Any information
regarding this plan should be obtained from the most current revision to that
document.
5.4 QUALITY ASSURANCE PROGRAM
5.4.1 Scope
This section establishes the criteria to be applied to systems requiring
Quality Assurance which prevent or mitigate the consequences of postulated
accidents which could cause undue risk to the health and safety of the public.
The structures, systems, components, and other items requiring quality
assurance are listed in the Vermont Yankee Safety Classification Program.
5.4.2 Responsibilities
1. Compliance with the requirements of the VY Quality Assurance Program Manual
(VYQAPM) based on the criteria of Title 10 of the Code of Federal
Regulations, Part 50, Appendix B, and as committed to within the VYQAPM,
shall be the responsibility of all personnel involved with activities
affecting operational safety. Vermont Yankee shall cross reference the
applicable criteria of 10CFR50 Appendix B in procedures that implement the
VYQAPM. The performance of quality-related activities shall be
accomplished with specified equipment under suitable environmental
conditions.
2. Individuals having direct responsibilities for establishment/distribution
control/implementation of the VYQAPM are delineated in the “Organization,"
section of the VYQAPM.
5.4.3 Implementation
Establishment of an effective Operational Quality Assurance Program is assured
through consideration of, and conformance with, the Regulatory Position in the
Regulatory Guides listed the VYQAPM. Implementation of this program is assured
through Quality Assurance procedures, derived from Quality Assurance policies,
goals, and objectives.
VYNPS DSAR Revision 1 5.0-5 of 5
5.4.4 Management Evaluation
The Safety Review Committee (SRC) reports to the executive responsible for
oversight on those areas of responsibility specified in the Quality Assurance
Program Manual. The SRC conducts its function in accordance with a procedure
approved by the executive responsible for oversight. The SRC independently
monitors applicable programs and provides management with evaluations and
assessments related to the effectiveness of the nuclear program.
5.5 REVIEW AND AUDIT OF OPERATIONS
5.5.1 General
Two review bodies have been established to review operating procedures,
evaluate and process changes and assure compliance and safe operation.
5.5.2 Independent Safety Review
The responsibilities and authorities of the Independent Safety Review are
described in an approved Quality Assurance Program Manual implementing
procedure.
5.5.3 Safety Review Committee
An independent safety review of activities affecting nuclear safety is
performed by the Safety Review Committee in accordance with an approved
Quality Assurance Program Manual implementing procedure.
5.6 TECHNICAL REQUIREMENTS MANUAL
Requirements pertinent to the permanently defueled state which have been
relocated out of Technical Specifications, as well as any other items deemed
appropriate by facility management, which do not meet the Technical
Specification screening criteria provided in 10CFR50.36(c)(2)(ii), are located
in the Technical Requirements Manual (TRM). Changes to the TRM are evaluated
per the requirements of 10CFR50.59.
VYNPS DSAR Revision 1 6.0-1 of 37
SAFETY ANALYSIS
TABLE OF CONTENTS
Section Title Page
6.1 INTRODUCTION .......................................................... 4
6.2 ACCEPTANCE CRITERIA ................................................... 5
6.2.1 DBA Acceptance Criteria ...................................... 5
6.2.2 Site Event Acceptance Criteria ............................... 6
6.3 ACCIDENTS EVALUATED ................................................... 7
6.3.1 Fuel Handling Accident ....................................... 7
6.3.1.1 Analytical Methodology .......................... 7
6.3.1.2 Assembly Drop in SFP with Open Containment Scenario ............................ 7
6.3.1.3 Assembly Drop in SFP with Closed Containment Scenario ............................ 9
6.3.1.4 Software ........................................ 9
6.3.1.5 Assumptions ..................................... 9
6.3.1.6 Inputs ......................................... 10
6.3.1.7 Impact of Water Depth on Iodine Decontamination Factor ......................... 10
6.3.1.8 Fuel Damage from Assembly Drop onto SFP Fuel Racks ..................................... 12
6.3.1.9 Radiological Consequences/Results 13
6.4 SITE EVENTS EVALUATED ................................................ 25
6.4.1 High Integrity Container (HIC) Drop Event ................... 25
6.4.1.1 Analytical Methodology ......................... 25
6.4.1.2 Assumptions .................................... 25
6.4.1.3 Inputs ......................................... 26
6.4.1.4 Radiological Consequences/Results .............. 27
6.5 REFERENCES ........................................................... 29
6.6 APPENDICES ........................................................... 32
VYNPS DSAR Revision 1 6.0-2 of 37
SAFETY ANALYSIS
LIST OF TABLES Table No. Title 6.3.1 FHA Scenarios Analyzed
6.3.2 Input Conditions for FHA
6.3.3 Undecayed Core Inventory for Radionuclides Important in the
Radiological Evaluation of DBAs
6.3.4 Undecayed Gap Activity Available for Release from Fuel Assembly
Drop in the SFP
6.3.5 Typical Iodine Decontamination Factors and Iodine Speciation vs
Water Depth above Dropped Assembly
6.3.6 Atmospheric Dispersion Factors for the Postulated FHA
6.3.7 EAB TEDE Dose vs Long Decay Time
6.4.1 HIC Drop Source Term Release Activity
VYNPS DSAR Revision 1 6.0-3 of 37
SAFETY ANALYSIS
LIST OF FIGURES Reference Figure No. Drawing No. Title 6.3-1 VY FHA – EAB TEDE Dose vs Decay Time
6.3-2 VY FHA – MCR TEDE Dose vs Decay Time
A-1 Dimensions of SFP, Fuel Rack and Fuel
Handling Equipment
VYNPS DSAR Revision 1 6.0-4 of 37
6.1 Introduction
In January of 2015, the licensee certified to the NRC that Vermont Yankee had
both permanently ceased operations (final shutdown 12/29/14) and that all fuel
had been removed from the reactor vessel and placed in the spent fuel pool
(SFP) (Reference 6.5-1). Since Vermont Yankee will never again enter any
operational mode, reactor related accidents are no longer a possibility.
This chapter discusses: (a) a postulated fuel handling accident (FHA)
associated with fuel movement until the fuel has been transferred to the
Independent Spent Fuel Storage Installation (ISFSI); and (b) the postulated
drop of a high integrity container (HIC) containing radioactive resins
Bounding conditions, conservatism in equipment design, conformance to high
standards of material and construction, the control of loads and strict
administrative controls over facility operations all serve to assure the
integrity of the fuel while in the spent fuel pool and during fuel transfer to
the Independent Spent Fuel Storage Installation (ISFSI).
Accidents involving fuel and the Holtec International HI-STORM system storage
casks are discussed in the HI-STORM FSAR (Reference 6.5-2).
For site events, a drop and fire of a High Integrity Container (HIC) containing
resins was evaluated.
New hazards, new initiators or new accidents that may challenge offsite
guideline exposures, may be introduced as a result of certain decommissioning
activities. These issues will be evaluated when the scope and type of
decommissioning activities are finalized.
VYNPS DSAR Revision 1 6.0-5 of 37
6.2 Acceptance Criteria
6.2.1 DBA Acceptance Criteria
The radiological release acceptance criteria associated with the Alternative
Source Term (AST) methodology are identified in 10CFR50.67 (Reference 6.5-3)
and dose levels are not to exceed:
Exclusion Area Boundary (EAB): 25 rem TEDE
Low Population Zone (LPZ): 25 rem TEDE
Control Room (CR): 5.0 rem TEDE
These criteria, however, are for evaluating potential reactor accidents of
exceedingly low occurrence probability and low risk of public exposure to
radiation. For events with higher probability of occurrence, such as a FHA,
the acceptance criteria for the offsite receptors are more stringent, while
that for the control room operators remains the same. The applicable AST
criteria for an FHA are identified in Regulatory Guide 1.183 (Reference 6.5-4)
and 10CFR50.67 and dose levels are not to exceed:
Exclusion Area Boundary (EAB): 6.3 rem TEDE
Low Population Zone (LPZ): 6.3 rem TEDE
Control Room (CR): 5.0 rem TEDE
The EAB and LPZ criteria are referred to as being "well within" the regulatory
limits (i.e., 25%).
The LPZ doses are bounded by the dose at the EAB, since the LPZ is farther
away.
Additional acceptance criteria are as follows:
• The required decay time that would preclude Evacuation as a protective
action following an FHA. The limit for such an action is 1 rem TEDE (EPA
400-R-92-001, Table 2-1 (Reference 6.5-5)).
• The required decay time that would reduce the TEDE dose from gaseous
releases of iodines and particulates to unrestricted areas to "well
within" (i.e., 25 %) of the 10CFR50 Appendix I (Reference 6.5-6) annual
dose limit of 15 mrem (or 3.75 mrem).
VYNPS DSAR Revision 1 6.0-6 of 37
The latter acceptance criterion was selected as a suitable basis no longer
requiring the Standby Gas Treatment System (SGTS). The "well within" limit was
selected so as to accommodate other potential releases from the plant. It is
noted that, by definition, this criterion excludes the noble gas dose. There
exists a separate criterion applicable to the nobles, which however is of no
interest in the present application since the noble gas release is not impacted
by the SGTS filtration.
6.2.2 Site Event Acceptance Criteria
The HIC drop acceptance criteria are based on 10% of the 10CFR100 dose
acceptance criteria.
10CFR100 Acceptance Criteria (1)
(rem)
10% of 10CFR100 Acceptance Criteria
(rem)
EAB
and
LPZ
25 (whole body)
2.5 (whole body)
300 (thyroid)
30 (thyroid, critical organ)
(1) EAB and LPZ dose acceptance criteria from 10CFR100.11
VYNPS DSAR Revision 1 6.0-7 of 37
6.3 Accidents Evaluated
6.3.1 Fuel Handling Accident
Two bounding scenarios of the FHA are considered and the scenario objectives
are summarized in Table 6.3.1.
The first scenario is a drop in the SFP with an open containment (no filtration
by SGTS) with an instantaneous release (ground level) to determine the required
decay time prior to fuel movement that would result in the EAB dose, and main
control room (MCR) dose within 10CFR50.67 and R.G. 1.183 limits and the EAB
TEDE dose under the EPA PAG limit of 1 rem for evacuation.
The second scenario is with a drop in the SFP, with a closed containment (not
under a negative pressure and not ‘air tight’) and an elevated (stack release)
instantaneous release with and without filtration by the SGTS, to determine the
required decay time prior to fuel movement that would result in 25% of the
10CFR50, Appendix I TEDE annual dose limit of 15 mrem at the EAB. The 10CFR50,
Appendix I dose of 15 mrem from gaseous effluents coincides with maintaining
dose as low as reasonably achievable. A revision to the Technical
Specifications proposed by BVY 13-097 (Reference 6.5-7) and approved by NVY 15-
013 (Reference 6.5-8) contains the following commitment: "During fuel
handling/core alterations, ventilation system and radiation monitor
availability (as defined in NUMARC 91-06, Reference 6.5-9) will be assessed,
with respect to filtration and monitoring of releases from the fuel. The goal
of maintaining ventilation system and radiation monitor availability is to
reduce doses even further below that provided by the natural decay." This FHA
scenario is the analysis which demonstrates that SGTS operation is not required
to maintain dose as low as reasonably achievable consistent with 10CFR50,
Appendix I, thus fulfilling this VY commitment.
6.3.1.1 Analytical Methodology
The postulated FHA scenarios were based on the Alternative Source Term (AST)
Methodology in RG 1.183, Appendix B. Two main configurations of the reactor
building during fuel movement were considered, one with an open containment and
the other with a closed containment.
6.3.1.2 Assembly Drop in SFP with Open Containment Scenario
(a) The reactor operated at full power (1950 MWt) for an extended period of
time until permanent shutdown and full core offload is completed with all
fuel in the SFP.
VYNPS DSAR Revision 1 6.0-8 of 37
(b) Fuel moves are in progress and an FHA takes place in the SFP with an
assembly falling onto a fuel rack at various assumed decay times after
reactor shutdown, from 1 to 19 days.
(c) The accident leads to the damage of 98 fuel rods (a bounding value from
Table 6.3.2, Item #D1), addressing both GE14 and GNF2 10x10 assemblies
removed from the final core offload. All failed rods are peak powered,
with a radial peaking factor of 1.65 (from Table 6.3.2, Item #A3).
(d) All activity within the gaps of the failed fuel rods is released to the
refueling cavity pool. The released activity corresponds to 8% of the
entire inventory of I-131 in the rods (i.e., within the fuel matrix and
gaps), 10% of the Kr-85, 5% of the remaining halogens and noble gases,
and 12% of the alkalis (Cs and Rb), from Table 6.3.2, Item #A4. The
undecayed activity released from the damaged fuel rods is presented in
Table 6.3.4; decay correction from plant shutdown to the time of the
postulated FHA is properly accounted for by the radiological software
used in the analysis (ELISA-2).
(e) All the noble gases and a fraction of the halogens (see Item (g) below)
escape from the pool and are released to the refueling level. All the
alkalis are retained by the pool. The halogen speciation above the pool
is not pertinent in this scenario since there is no pre- or post-release
filtration of radioactivity.
(f) The water depth above the dropped assembly in the SFP is 20.5 feet
(versus the 23-foot requirement in Regulatory Guide 1.183 for full credit
of the decontamination factor (DF) of 200 for iodine retention by the
pool water), leading to a corresponding decrease in the DF to 125.4 (from
Table 6.3.5).
(g) The radioactivity which becomes airborne above the SFP is instantly
released to the environment without holdup (a conservative assumption
which accommodates the 2-hr release requirement in Regulatory Guide
1.183, Appendix B, Sec. 5.3).
(h) The reactor building is open during the refueling operations, with all
post-FHA releases to the environment assumed to be at ground level, via
the RB blowout panels.
(i) Transport of the released radioactivity to the receptors of interest is
dictated by the applicable atmospheric dispersion factors in Table 6.3.6.
(j) The MCR ventilation configuration is in the normal operating mode during
the entire exposure interval (30 days), with an intake flow of 3700 cfm,
unfiltered.
(k) Breathing rates and MCR occupancy factors are as given in Table 6.3.2,
Items #F2 and #F3.
(l) The control room operator dose point is at the base of a hemispherical
cloud having a volume equal to the free air volume of the control room.
Finite-cloud correction to the submersion dose was based on the
Murphy/Campe equation in Reg. Guide 1.183 (Sec. 4.2.7).
VYNPS DSAR Revision 1 6.0-9 of 37
6.3.1.3 Assembly Drop in SFP with Closed Containment Scenario
The scenario is the same as an assembly drop in the SFP with an open
containment, except with the following differences:
(a) The radionuclide list is as given in Table 6.3.4, though without the
noble gases. The acceptance criterion for no longer requiring the SGTS
filtration was selected to be 25% of the 10CFR50, Appendix I annual TEDE
dose limit of 15 mrem (or. 3.75 mrem) from gaseous releases of iodines
and particulates to unrestricted areas. As such, this criterion excludes
the noble gas dose.
(b) The reactor building is closed during fuel moves, such that all releases
to the environment would be via the main stack, with and without credit
for filtration by the SGTS system. In-transit decay and plateout were not
credited.
(c) The decay times prior to fuel movement are fairly long in this scenario
because the interest is in determining the time beyond which there will
be no dose-wise beneficial purpose for maintaining the SGTS operational
after permanent plant shutdown.
(d) The EAB dose consequences were evaluated without SGTS filtration, but
also with SGTS filtration for informational purposes. The filtration
efficiencies for the latter case are as given in Table 6.3.2, Item #D7.
(e) The MCR is of no interest in this scenario and was therefore excluded
from the analysis.
6.3.1.4 Software
Computation of the EAB and MCR radiological consequences for the postulated FHA
were based on the ELISA-2 computer code, Version 2.4 (Reference 6.5-10) for all
analyzed scenarios.
The dose conversions in ELISA-2 are from Federal Guidance Reports 11 (Reference
6.5-11) and 12 (Reference 6.5-12). Dose rates and cumulative doses are
computed for each organ, TEDE, skin and air. Of these, only the TEDE doses are
presented for comparison to the TEDE regulatory limits.
ELISA-2 was designed to handle the pre-FHA decay correction and the time-
release from the RB for all scenarios. Its built-in logic accounts for the
time-dependent generation and release of noble gases from the decay of halogens
retained by the pool water, and also from the halogens on the SGTS exhaust
filtration system when credited. These releases extend beyond the end of the
2-hr release from the RB.
6.3.1.5 Assumptions
VYNPS DSAR Revision 1 6.0-10 of 37
Release Rate from Reactor Building
In accordance with RG 1.183, Appendix B, Sec. 4.1 for an FHA in the SFP, the
radioactive material that escapes the water pool is released to the environment
over a 2-hour interval. Analytically, this is conservatively accommodated by
assuming an instantaneous release to the environment, in all accident scenarios
and for all receptors (EAB and MCR). Credit for in-transit decay or plateout
was not taken.
Fuel Rod Gap Activity
All activity within the gaps of the failed fuel rods is released to the
refueling cavity pool. The released activity corresponds to 8% of the entire
inventory of I-131 in the rods (i.e., within the fuel matrix and gaps), 10% of
the Kr-85, 5% of the remaining halogens and noble gases, and 12% of the alkalis
(Cs and Rb), from Table 6.3.2 (Item #A4), Fuel Rod Gap Fractions. The
undecayed activity released from the damaged fuel rods is presented in Table
6.3.4.
MCR Finite Cloud Correction
Doses to MCR personnel due to the external gamma radiation from airborne
radioactivity within the MCR were adjusted using the Murphy/Campe finite-cloud
correction model in R.G. 1.183, Section 4.2.7.
Modeling Simplifications
There are no modeling simplifications.
Number of Failed Fuel Rods
Assumptions associated with determining the number of failed fuel rods due to a
dropped fuel assembly are provided in Section 6.6, Appendix A.
6.3.1.6 Inputs
Inputs for the analysis are identified in Table 6.3.2.
6.3.1.7 Impact of Water Depth on Iodine Decontamination Factor
According to RG 1.183, Appendix B, Section 2, Water Depth, if the water depth
above the damaged dropped assembly in a fuel handling accident is 23 feet or
greater, an overall decontamination factor of 200 may be credited for the
expected iodine retention by the pool water. As clarified in RIS 2006-004,
Item 8 (Reference 6.5-13) and in the proposed revision to RG 1.183, with an
iodine speciation consisting of 99.85% elemental (including CsI) and 0.15%
organic in the fuel-rod gaps, the overall DF of 200 is achieved when the DF for
the elemental iodines is 285, with the ensuing iodine composition in air above
the pool being 70% elemental and 30% organic.
VYNPS DSAR Revision 1 6.0-11 of 37
For water depths less than 23 feet, RG 1.183 recommends the use of the Burley
model (Reference 6.5-14). According to this model, the DF for a reduced water
depth is determined through use of the following formula (Reference 6.5-14, pg
26):
DFinorg = exp {(6/db)*(keff Hb / vb)} (Eq. 1)
where
DFinorg = elemental iodine pool retention factor (or DF)
db = bubble diameter (cm)
keff = effective mass transfer coefficient (cm/sec)
Hb = bubble rise height (cm, water depth above dropped
assembly)
vb = bubble rise velocity (cm/sec)
This equation can be rewritten by combining all of the independent
variables (excluding Hb), as:
DFinorg = exp (K*Hb) (Eq. 2)
where
K = {(6/db)*(keff / vb)} (Eq. 3)
The new variable K can now be back-calculated by using the
recommended values given above for DFinorg and Hb, namely 285 and 23
ft (or 701.0 cm), respectively, and is as follows:
K = loge(285) / 701.0 = 0.008063 (Eq. 4)
The applicable DF equation for reduced SFP water then becomes:
DFinorg = exp (0.008063*Hb) (Eq. 5)
For the iodine speciation given above, namely 99.85% elemental
(including CsI) and 0.15% organic, and no organic iodine retention
by the pool water (i.e., DForg = 1), the overall (total iodine) DF
is given by:
DFtotal = [(0.9985/DFinorg) + (0.0015/1)]-1 (Eq. 6)
Proceeding further, the above-water (i.e., airborne) iodine
speciation formulas (in percent) are given by:
Sinorg = 99.85* (DFtotal / DFinorg) (Eq. 7)
and
Sorg = 0.15 * DF total (Eq. 8)
VYNPS DSAR Revision 1 6.0-12 of 37
Typical DF values and iodine speciation versus SFP water depth are presented in
Table 6.3.5. The iodine speciation is of no interest since (a) there is no
filtration credit in the open containment scenario, and (b) all iodine species
were subjected to the same SGTS filtration efficiency in the closed containment
scenario.
6.3.1.8 Fuel Damage from Assembly Drop onto SFP Fuel Racks
Fuel pin damage due to a drop of a fuel assembly onto a spent fuel rack within
the SFP was evaluated. A drop in the SFP is limited to a drop distance of 3
feet, rounded up from 1.9 feet for conservatism. The General Electric Standard
Application for Reactor Fuel, GESTAR II (Reference 6.5-15) is utilized to
determine the number of damaged fuel pins resulting from the drop. This
analysis is presented in Section 6.6, Appendix A.
VYNPS DSAR Revision 1 6.0-13 of 37
6.3.1.9 Radiological Consequences/Results
The radiological consequences of the FHA scenarios are shown below.
Scenario Limiting
Dose
Acceptance
Criteria
Open Containment
Ground Level
Instantaneous
Release
No SGTS
Filtration
Closed Containment
Elevated Release
(Main Stack)
Instantaneous
Release
No SGTS Filtration
Required
Decay Time to
Meet Most
Restrictive
Acceptance
Criteria
(Section 6.2.1)
15 days 50 days
Dose
TEDE
MCR 5 rem
(10CFR50.67)
< 5 rem NA
EAB 6.3 rem
(R.G. 1.183)
< 6.3 rem NA
EAB EPA PAG
1 rem
(initiation of
evacuation)
< 1 rem
NA
EAB 10CFR50
Appendix I
15 mrem
annual limit
NA 3.75 mrem
(25% of the limit)
Decay Time and Dose Details Figure 6.3-1
Figure 6.3.2
Table 6.3.7
Note that doses at the EAB bound the corresponding dose at the Low
Population Zone (LPZ), as the LPZ is farther away from the station.
The conclusion is that if there is a FHA 50 days following cessation of
power operations, the benefits of SGTS are minimal and resultant dose
without SGTS operation at the EAB is considered to be maintained as low
as reasonably achievable.
VYNPS DSAR Revision 1 6.0-14 of 37
Table 6.3.1
FHA Scenarios Analyzed
Scenario Open containment Closed containment
Objective To determine the required
decay time prior to fuel
movement in the SFP that
would meet the following:
(a) 90% of the 10CFR
50.67 dose acceptance
criteria, and
(b) an EAB TEDE dose less
than the PAG limit of 1
rem for evacuation.
To provide basis for no longer
requiring the SGTS in support of a
VY TS commitment (contained within
Reference 6.5-7) with respect to
dose minimization following an FHA
Containment Building
Configuration
Open containment, with
instantaneous atmospheric
release via the blow-out
panels
(ground-level release)
Closed containment with
instantaneous atmospheric releases
via main stack (with and without
SGTS iodine and particulate
filtration)
Location of Assembly
Drop
SFP
(3 foot drop onto fuel
racks)
SFP
(3 foot drop onto fuel racks)
Water Depth above
Dropped Assembly
Credited for Iodine
Retention
20.5 feet
[DF = 125.4]
20.5 feet
[DF = 125.4]
Fuel Damage To be determined in
present calculation based
on both GE14 and GNF2
assembly drops
To be determined in present
calculation based on both GE14 and
GNF2 assembly drops
Pre FHA Decay Time
from Reactor
Shutdown
Required decay time to be
determined in present
calculation to meet the
dose consequence
objectives
Required decay time to meet 25% of
the 10 CFR 50 Appendix I TEDE
annual dose limit of 15 mrem at
the EAB from iodines and
particulates
VYNPS DSAR Revision 1 6.0-15 of 37
Table 6.3.2
INPUT CONDITIONS FOR FHA
Item No. DESCRIPTION VALUE REFERENCE
FHA Source TermA1 Power level for DBA analysis
[Includes 2 % measurement uncertainty] 1950 MWt
6.5‐16 (VYC‐2299) A2 Number of assemblies in core 368
A3 Maximum allowed radial peaking factor(a) 1.65A4 Fuel rod gap fractions (AST Methodology)
I‐131 Kr‐85 Other noble gases Other halogens Alkali metals (Cs and Rb)
0.08 0.10 0.05 0.05 0.12
6.5‐4 (Reg. Guide 1.183, Table 3)
A5 Undecayed core inventory for radionuclides important in the evaluation of DBAs
Table 6.3.3 6.5‐17 (VYC‐2260, Table 4.5)
A6 Post‐shutdown decay time prior to postulated accident
Various Assumed values for sensitivity analyses
Variables for Fuel Damage Calculation for FHA in Spent Fuel Pool B1 Number of fuel rods in 10x10 assemblies
(GE14 and GNF2) 92
6.5‐18 (VYC‐2206, Sec. 1)
B2 Assembly drop height above fuel racks
Bounding value 22.74"(1.9 ft)
6.5‐19 (App. A, pg 17 of 20)
Used in analysis(c)36" (3 ft)
Conservatively assumed value
B3 Wet weight of fuel assembly and channel
GE14 569.5 lbm 6.5‐18 (VYC‐2206, pg 12 of 31)
GNF2 580.0 lbm 6.5‐19 (App. A, pg 8 of 20)
B4 Weight of mast and grapple
GE14 619 lbm 6.5‐19 (App. A, pg 9 of 20) GNF2 619 lbm
B5 Percent energy for clad deformation
GE14 51% 6.5‐15 (GESTAR II , Sec. 5.3.1 (also applied to GNF2 assemblies)
GNF2 51%
B6 10x10 rod compression failure (energy required to damage stationary fuel rods)
GE14 167 ft‐lb
6.5‐19 (App. A., page 10 of 20) GNF2 157 ft‐lb
VYNPS DSAR Revision 1 6.0-16 of 37
Table 6.3.2 (Continued)
INPUT CONDITIONS FOR FHA
DESCRIPTION VALUE REFERENCE Atmospheric Release Resulting from Postulated FHA in Spent Fuel Pool
D1 Number of damaged fuel assemblies
GE14 97 6.5‐19 (VYC‐3187) GNF2 98
Used in analysis 98 Bounds both GE14 and GNF2 assembly types
D2 Water depth above dropped assembly (resting on top of fuel racks)
Minimum value 20.67 ft 6.5‐19 (App. A, pg 2 of 19)
Used in analysis 20.5 ft Conservative
D3 Undecayed gap inventory available for release from 98 damaged fuel rods
See Table 6.3.4
D4 Overall pool DF for given water depth
Noble gases 1 6.5‐4 (RG 1.183)
Halogens 125.4 See Table 6.3.5Alkalis Infinite
6.5‐4 (RG 1.183)
D5 Percent of damaged‐fuel rod gap activity release
100 %
D6
Reactor building configuration during refueling operations
Closed Containment w/wo SGTS
Instantaneous Stack Release
See Table 6.3.1 Open
Containment No SGTS
Ground Level Release
D7
Potential release point to the atmosphere (see Table 6.3.6 for the atmospheric dispersion factors)
Closed Containment w/wo SGTS
Stack Release See Table 6.3.1
Open Containment No SGTS
Instantaneous RB blowout panel release
6.5‐20 (VYC‐2275)
D8 SGTS filtration efficiency, all halogens and particulates
95% 6.5‐21 (VYC‐2302, Page 11 of 59)
D9 Release duration to atmosphere Instantaneous
Meets the RG 1.183 requirements
VYNPS DSAR Revision 1 6.0-17 of 37
Table 6.3.2 (Continued)
INPUT CONDITIONS FOR FHA
DESCRIPTION VALUE REFERENCE Control Room Characteristics
E1 Control room free air volume 41534 ft3
6.5‐16 (VYC‐2299)
E2 MCR HVAC nominal unfiltered intake flow for accident duration and all FHA scenarios (assumed to include fresh air and air from surrounding areas as a result of ingress, egress and inleakage)
3700 cfm
DESCRIPTION VALUE REFERENCE / COMMENTS Other Variables
F1 Atmospheric dispersion factors from release point to locations of interest
See Table 6.3.6
6.5‐16 and 6.5‐20 (VYC‐2299 and VYC‐2275, Section 6)
F2
Breathing rates
Control Room
0 ‐ 720 hrs
3.5E‐04 m3/sec
6.5‐4(RG 1.183, pg 1.183‐18)
EAB 0 ‐ 2 hr
3.5E‐04 m3/sec
6.5‐4(RG 1.183, pg 1.183‐16)
F3
Control room occupancy factors
0 ‐ 24 hrs
1.0
6.5‐4 (RG 1.183, pg 1.183‐18)
24 ‐ 96 hrs
0.6
96 ‐ 720 hrs
0.4
F4 Exposure Intervals(b)
Control room 30 days 6.5‐4(RG 1.183, Sections 4.1.3, 4.1.5 and 4.2.6)
EAB 2 hrs
F5 Regulatory dose limits Control room TEDE 5 rem
6.5‐4(RG 1.183, pg 1.183‐19 and 10CFR50.67, Sec. (b)(2)(iii))
EAB TEDE 6.3 rem 6.5‐4(RG 1.183, Table 6)
LPZ TEDE 6.3 rem
F6 PAG Evacuation dose limit (EAB TEDE)
1 rem 6.5‐5(EPA 400‐R‐92‐001)
(a) In line with RG 1.183, Sec. 3.1, the radial peaking factor is applied to the average fuel-
assembly inventory based on the core inventory in Table 6.3.3. This is a conservative
approach and bounds any potential variations in the FHA source term resulting from
variations in the EFPDs and burnup in any given cycle.
(b) Even though all radioactivity is released to the atmosphere within 2 hours following a
design-basis FHA, the exposure intervals for the CR personnel was assumed to be 30 days.
This provides adequate time for cleanup of the airborne radioactivity still present within
the CR after termination of the 2-hr release, and also accounts for the delayed release of
noble-gas decay products from the refueling pool water produced upon decay of halogens
retained therein.
(c) The assembly drop height within the SFP was conservatively increased to 3 ft to account for
the difference in elevations between the top of the racks and the top of an assembly within
the racks, as well as any other dimensional uncertainties.
VYNPS DSAR Revision 1 6.0-18 of 37
Table 6.3.3
Undecayed Core Inventory for Radionuclides Important in the Radiological Evaluation of DBAs
(From VYC-2260, Table 4.5, based on 1950 MWt, an enrichment range from 3.0 to 4.65 wt % U-235, and
core-average burnup from 5 to 58 GWD/MTU)
Nuclide Core Ci Nuclide Core Ci
Br‐83 8.267E+06 I‐132 7.900E+07
Kr‐83m 8.265E+06 Te‐133 6.602E+07
Br‐85 1.874E+07 Te‐133m 4.493E+07
Kr‐85 9.852E+05 I‐133 1.130E+08
Kr‐85m 1.894E+07 Xe‐133 1.128E+08
Rb‐86 2.496E+05 Xe‐133m 3.428E+06
Kr‐87 3.788E+07 Te‐134 1.036E+08
Kr‐88 5.355E+07 I‐134 1.254E+08
Kr‐89 6.755E+07 Cs‐134 2.971E+07
Sr‐89 6.724E+07 I‐135 1.051E+08
Sr‐90 7.999E+06 Xe‐135 4.540E+07
Y‐90 8.363E+06 Xe‐135m 2.232E+07
Sr‐91 8.684E+07 Cs‐136 7.602E+06
Y‐91 8.270E+07 Xe‐137 9.893E+07
Sr‐92 8.987E+07 Cs‐137 1.186E+07
Y‐92 9.008E+07 Ba‐137m 1.124E+07
Y‐93 9.857E+07 Xe‐138 9.851E+07
Zr‐95 9.645E+07 Ba‐139 1.043E+08
Nb‐95 9.673E+07 Ba‐140 1.004E+08
Zr‐97 9.596E+07 La‐140 1.009E+08
Mo‐99 1.034E+08 La‐141 9.573E+07
Tc‐99m 9.051E+07 Ce‐141 9.255E+07
Ru‐103 9.889E+07 La‐142 9.387E+07
Ru‐105 7.844E+07 Ce‐143 9.228E+07
Rh‐105 7.183E+07 Pr‐143 9.181E+07
Ru‐106 5.554E+07 Ce‐144 7.268E+07
Sb‐127 7.194E+06 Nd‐147 3.736E+07
Te‐127 7.151E+06 Np‐239 1.496E+09
Te‐127m 9.705E+05 Pu‐238 7.668E+05
Sb‐129 1.976E+07 Pu‐239 2.864E+04
Te‐129 1.947E+07 Pu‐240 6.061E+04
Te‐129m 2.890E+06 Pu‐241 1.281E+07
Te‐131m 8.405E+06 Am‐241 1.702E+04
I‐131 5.564E+07 Cm‐242 6.669E+06
Xe‐131m 6.192E+05 Cm‐244 2.358E+06
Te‐132 7.739E+07
VYNPS DSAR Revision 1 6.0-19 of 37
Table 6.3.4
Undecayed Gap Activity Available for Release from Fuel Assembly Drop in
the SFP
Nuclide
Damaged Fuel‐Rod Gap Source Term for FHA
(Ci Available for Release from 98 Damaged Fuel Rods)
Assembly Drop in SFP
Kr‐83m 1.977E+03
Kr‐85 4.713E+02
Kr‐85m 4.530E+03
Kr‐87 9.060E+03
Kr‐88 1.281E+04
Kr‐89 1.616E+04
Xe‐131m 1.481E+02
Xe‐133 2.698E+04
Xe‐133m 8.199E+02
Xe‐135 1.086E+04
Xe‐135m 5.338E+03
Xe‐137 2.366E+04
Xe‐138 2.356E+04
Br‐83 1.977E+03
Br‐85 4.482E+03
I‐131 2.129E+04
I‐132 1.889E+04
I‐133 2.703E+04
I‐134 2.999E+04
I‐135 2.514E+04
Rb‐86 1.433E+02
Cs‐134 1.705E+04
Cs‐136 4.364E+03
Cs‐137 6.808E+03
Te‐131m 3.216E+03
Te‐132 1.851E+04
Te‐133 1.579E+04
Te‐133m 1.075E+04
VYNPS DSAR Revision 1 6.0-20 of 37
Table 6.3.5
Typical Iodine Decontamination Factors and Iodine Speciation
Versus Water Depth above Dropped Assembly
SFP Water Depth (Hb) above Dropped Assembly
Iodine Decontamination Factor Iodine Speciation above Pool Water
(%)
(ft) (cm) Inorganic
(DFinorg, Eq. 5) Total
(DFtotal, Eq. 6) Inorganic (Sinorg,
Eq. 7) Organic
(Sorg, Eq. 8)
23 701.0 285.0 199.9 70.0 30.0
22.5 685.8 252.0 183.1 72.5 27.5
22 670.6 222.9 167.2 74.9 25.1
21.5 655.3 197.1 152.3 77.2 22.8
21 640.1 174.3 138.4 79.2 20.8
20.5 624.8 154.2 125.4 81.2 18.8
20 609.6 136.3 113.3 83.0 17.0
19 579.1 106.6 92.1 86.2 13.8
18 548.6 83.4 74.2 88.9 11.1
17 518.2 65.2 59.5 91.1 8.9
16 487.7 51.0 47.5 92.9 7.1
15 457.2 39.9 37.7 94.3 5.7
14 426.7 31.2 29.9 95.5 4.5
13 396.2 24.4 23.6 96.5 3.5
12 365.8 19.1 18.6 97.2 2.8
11 335.3 14.9 14.6 97.8 2.2
10 304.8 11.7 11.5 98.3 1.7
0 0.0 1.0 1.0 99.85 0.15
VYNPS DSAR Revision 1 6.0-21 of 37
Table 6.3.6
Atmospheric Dispersion Factors for the Postulated FHA
(From VYC-2299 and VYC-2275, Section 6)
Scenario Release Point
Receptor Point
Post‐FHA Interval(a)
χ/Q(b) (sec/m3)
Control RoomFresh Air Intake
Instantaneous release
6.04E‐05
FHA Spent Fuel Pool
Ground Level Release(RB blowout panel) Open Containment
EAB Instantaneous
release 1.69E‐03
Control Room Fresh Air Intake
0 ‐ 2 hrs 5.89E‐03
2 ‐ 8 hrs 1.53E‐03
8 ‐ 24 hrs 6.41E‐04
24 ‐ 96 hrs 6.64E‐04
96 ‐ 720 hrs 5.10E‐04
FHA Spent Fuel Pool
Elevated Release(Main stack)
Closed Containment (w/wo SGTS)
EAB Instantaneous
release 1.35E‐04
VYNPS DSAR Revision 1 6.0-22 of 37
Table 6.3.7
EAB TEDE Dose vs. Long Decay Time
(Assembly Drop in SFP with Closed Containment)
(Instantaneous elevated release with closed containment, with and without SGTS
filtration)
Post‐FHA Time (days)
EAB TEDE Dose (rem)
Without SGTS Filtration With SGTS Filtration
30 2.055E‐02 1.028E‐03
40 8.672E‐03 4.336E‐04
50 3.662E‐03 1.831E‐04
60 1.546E‐03 7.731E‐05
VYNPS DSAR Revision 1 6.0-23 of 37
Figure 6.3-1
VY FHA - EAB TEDE Dose vs. Decay Time
(Assembly Drop in SFP with Open Containment)
VYNPS DSAR Revision 1 6.0-24 of 37
Figure 6.3-2
VY FHA - MCR TEDE Dose vs. Decay Time
(Assembly Drop in SFP with Open Containment)
VYNPS DSAR Revision 1 6.0-25 of 37
6.4 Site Events Evaluated
6.4.1 High Integrity Container (HIC) Drop Event
The drop of a HIC containing reactor water cleanup (RWCU) resins was evaluated
as taking place during normal operation of the plant, and the results are
reported in this section. Although these types of resins are no longer
expected to be on site after a period of time subsequent to cessation of power
operations (they will no longer be generated), the source term from these
resins is expected to bound source terms from other items (spent fuel pool
demineralizer resins, filter cartridges, etc.) that may be placed in containers
and moved subsequent to permanent shutdown.
6.4.1.1 Analytical Methodology
The list of radionuclides released into the cloud following the postulated
resin fire is provided in Table 6.4.1. The basis for this table is provided in
Section 6.4.1.2. The release was assumed to be instantaneous. Radiation doses
were calculated to the total body due to cloud submersion and a 2-hr direct
shine dose from standing on contaminated ground, and to the thyroid and
identified critical organ (lung) based on the inhalation pathway.
The whole body and organ doses were based on the standard equations for
instantaneous releases and the applicable dose conversion factors. The DCFs
were extracted from NUREG/CR-1918 (ORNL/NUREG-79) (Reference 6.5-23) for the
air submersion pathway, Regulator Guide 1.109 (Reference 6.5-24) for the
inhalation pathway and all nuclides except I-129, ICRP-30 (Reference 6.5-25)
for the inhalation pathway and I-129, and Regulator Guide 1.109 (Reference 6.5-
26) for the contaminated ground-shine pathway.
With respect to the whole body dose from ground deposition, the analysis was
based on assuming uniform dispersion of the released activity from Table 6.4.1
over the deposition area, and a 2-hr radiation exposure interval. The
deposition area (about 1400 m2) was conservatively assumed to encompass the
distance between the reactor building and the closest receptor at the site
boundary and a 2-sigma plume width for the assumed prevailing atmospheric
stability (F) at the time of the postulated incident.
6.4.1.2 Assumptions
Sandia National Laboratory has conservatively estimated, for a severity
Category 3 transportation accident (which includes 99% of urban and 94% of
rural accidents), no more than 1% (0.01) of any package contents would be
released. For the purposes of the analysis, it was assumed that 0.5% of the
released activity becomes aerosolized as a result of the fire.
VYNPS DSAR Revision 1 6.0-26 of 37
A HIC of 150 feet3 capacity contains dewatered reactor water cleanup (RWCU)
resins at a density of 0.8 (g/cc), and contains all radionuclides typically
found in nuclear power plant radwaste. Each radionuclide inventory in the HIC
is at the Department of Transportation (DOT) limit for Low Specific Activity
(LSA) material, except for I-129, which is assumed to be at the 10CFR61 limit
for disposal. A source term of RWCU resins is considered to be the most
limiting from a radiological perspective.
The assumed liner drop occurs 250 meters from the site boundary (EAB). This is
based on original analysis performed for a drop of a HIC at the corner of the
waste storage pad (corner closest to the site boundary), built for
prefabricated concrete storage modules. This is a conservative assumption
because the radwaste loading area is farther away from the closest site
boundary than the 250 meters in the original HIC drop analysis.
Conservative dispersion conditions are assumed for a ‘puff release’ under
Stability Class F and a wind-speed of 1 meter/second. The puff is assumed to
travel along the ground in the direction of the nearest site boundary, at
ground level.
The dose acceptance criteria were set equal to "a small fraction" of the 10 CFR
100 dose limits of 25 rem whole body and 300 rem thyroid (i.e., to 10% of these
values, or 2.5 rem whole body and 30 rem thyroid). Because of the nature of
the source term (which consists mostly of long-lived radionuclides), the
thyroid limit of 30 rem was also applied to the critical organ (identified to
be the lung in this case).
Other assumptions are contained in the footnotes in Table 6.4.1.
6.4.1.3 Inputs
The source term for the dropped container containing RWCU dewatered resins is
provided in Table 6.4.1.
The atmospheric dispersion factor is based on a conservative downwind distance
of 250 meters (to the closest site boundary from the reactor building, and is
determined to be 0.079 sec/m3.
The breathing rate for the organ dose is 8000 m3/yr (2.537E-04 m3/sec), from RG
1.109.
VYNPS DSAR Revision 1 6.0-27 of 37
6.4.1.4 Radiological Consequences/Results
10% of 10CFR100 Dose Acceptance Criteria
(rem)
Calculated Dose (rem)
EAB (2 hours)
2.5 rem (whole body) 6.52E‐03 (a) 9.59E‐03 (b) 16.1E‐03 (c)
30 rem (thyroid, also applied to
the critical organ) 2.03E‐03 (thyroid)
4.58 (lung)
(a) Dose from standing on contaminated ground (2‐hr exposure) (b) Dose from cloud passage overhead due to resin fire and aerosol release (c) Sum of ground plane external plus airborne from cloud
VYNPS DSAR Revision 1 6.0-28 of 37
Table 6.4.1 HIC Drop Source Term Release Activity
Nuclide 1
A2 Values
2 (Ci)
LSA Limit 3
(mCi/gm)
Total Activity 4
(Ci)
Liner Drop
ReleaseActivity 5
(Ci) Cr‐51 600 0.3 1020 0.051
Mn‐54 20 0.3 1020 0.051
Fe‐55 1000 0.3 1020 0.051
Co‐58 20 0.3 1020 0.051
Co‐60 7 0.3 1020 0.051
Fe‐59 10 0.3 1020 0.051
Ni‐59 900 0.3 1020 0.051
Ni‐63 100 0.3 1020 0.051
Sb‐124 5 0.3 1020 0.051
Zn‐65 30 0.3 1020 0.051
Ag‐110m 7 0.3 1020 0.051
Sr‐89 10 0.3 1020 0.051
Sr‐90 0.4 0.005 17 0.00085
Zr‐95 20 0.3 1020 0.051
NB‐95 20 0.3 1020 0.051
Tc‐99 25 0.3 1020 0.051
I‐129 6 2 NA 0.34 0.000017
Cs‐134 10 0.3 1020 0.051
Cs‐137 10 0.3 1020 0.051
Ce‐141 25 0.3 1020 0.051
Ce‐144 7 0.3 1020 0.051
Pu‐238 0.003 0.0001 0.34 0.000017 Pu‐
239/240 0.002 0.0001 0.34 0.000017
Am‐241 0.003 0.0001 0.34 0.000017
Cm‐242 0.2 0.005 17 0.00085 Cm‐
243/244 0.01 0.0001 0.34 0.000017
19415.7 0.970785
Footnotes: 1‐ Nuclide Listing: A listing of radionuclides that typically are determined by laboratory analysis to be present in
RWCU resin. Short lived gaseous and volatile radionuclides are not detected in typical radwaste streams. 2 ‐ A2: For informational purposes, quantities of normal form (not special form) radionuclides, expressed in
curies, permitted by DOT to be contained in a Type A disposal package. Refer to 49CFR173.435 for listing. 3 ‐ LSA Limit: DOT determined Low Specific Activity concentration limit, expressed in units of millicuries per gram
of material. Under regulations dated January 1989, LSA is a function of the tabulated A2 variable above. Refer to 49CFR173.403(n)(4) for the relationship.
4 ‐ Total Activity: Because concentration and distribution of radionuclides in waste are expected to vary over time, it is assumed for purposes of this radiological accident analysis that all radionuclides are at their upper limit. In reality, a small number of radionuclides might be expected to approach a limiting condition while the majority would be at some lower level. Total activity is based on the following: A) 150 ft3 (4.25 m3) liner waste, density of 50 lb/ft3 = 4.248E+06 cc @ 0.8 gm/cc giving 3.40E+06 gm. B) Each nuclide is at the LSA limit.
5 ‐ Release Activity: The quantity of each nuclide assumed to be released from the waste liner to form the source term. The release activity is based on: A) Liner drop incident results in liner failure and release of 1% total contents. B) Of the 1% material released, 0.5% is aerosolized to form a "release cloud" source term. The release fraction is 0.01 and the aerosol fraction is 0.00005 of the total HIC activity).
6 ‐ I‐129 is limited by 10CFR61 burial requirements rather than DOT. The class C disposal limit for I‐129, as listed in 10CFR61.55, Table 1, is 0.08 Ci/m3 (or μCi/cc).
VYNPS DSAR Revision 1 6.0-29 of 37
6.5 References
1. BVY 15-001, “Certifications of Permanent Cessation of Power Operations
and Permanent Removal of Fuel from the Reactor Vessel, Vermont Yankee
Nuclear Power Station”, January 12, 2015.
2. Holtec International Final Safety Analysis Report for the Hi-Storm 100
Cask System, Revision 4.
3. Code of Federal Regulations Title 10 Part 50.67 (10CFR50.67), Accident
Source Term
4. Regulatory Guide 1.183, Alternative Radiological Source Terms for
Evaluating Design Basis Accidents at Nuclear Power Reactors, Rev. 0, July
2000
5. EPA 400-R-92-001, Manual of Protective Action Guides and Protective
Actions for Nuclear Incidents (1991)
6. 10CFR50, Appendix I, Numerical Guides for Design Objectives and Limiting
Conditions for Operation to Meet the Criterion “As Low as is Reasonably
Achievable” for Radioactive Material in Light-Water-Cooled Nuclear Power
Reactor Effluents
7. BVY 13-097, "Technical Specifications Proposed Change No. 306 – Eliminate
Certain ESF Requirements during Movement of Irradiated Fuel", Nov. 14,
2013.
8. NVY 15-013, Vermont Yankee Nuclear Power Station – Issuance of Amendment
to Renewed Facility Operating License RE: Eliminate Operability
Requirements for Secondary Containment When Handling Sufficiently Decayed
Irradiated Fuel or a Fuel Cask (TAC No. MF3086), dated February 12, 2015.
9. NUMARC 93-01, “Industry Guidelines for Monitoring the Effectiveness of
Maintenance at Nuclear Power Plants”
10. AREVA Document 32-9053350-001, “ELISA-2 - A Software Package for the
Radiological Evaluation of Licensing and Severe Accidents at Light-Water
Nuclear Power Plants Based on the Classical and Alternative-Source-Term
Methodologies” (Aug. 2008) [See also AREVA Document 2A4.26-2A4-ELISA2-
2.4_Users_Manual-000, “ELISA-2 Version 2.4 User’s Manual – Revision 2”.]
11. EPA 520/1-88-020, Federal Guidance Report No. 11, "Limiting Values of
Radionuclide Intake and Air Concentration, and Dose Conversion Factors for
VYNPS DSAR Revision 1 6.0-30 of 37
Inhalation, Submersion, and Ingestion" (ORNL, September 1988)
12. EPA 402-R-93-081, Federal Guidance Report No. 12, "External Exposure to
Radionuclides in Air, Water, and Soil" (ORNL, September 1993)
13. US NRC Regulatory Issue Summary (RIS) 2006-04, "Experience with
Implementation of Alternative Source Terms", March 2006.
14. G. Burley, "Evaluation of Fission Product Release and Transport for a
Fuel Handling Accident," U.S. NRC Technical Paper (October 1971,
Accession Number: 8402080322 in ADAMS or PARS).
15. General Electric Standard Application for Reactor Fuel, GESTAR II
(Supplement for the Unite States) Licensing Topical Report, pages US-25
through US-28, NEDE-24011-P-A-14-US, Class III14, June 2000.
16. ENTERGY Calculation VYC-2299, “Radiological AST Fuel Handling Accident
Analysis [PSAT 3019CF.QA.05, Rev. 0]” (Jun. 2003)
17. ENTERGY Calculation VYC-2260, “Bounding Core Inventories of Actinides and
Fission Products for Design-Basis Applications at 1950 MWt” (Rev. 0, Feb.
2003)
18. ENTERGY Calculation VYC-2206, “Determination of Number of Damaged Fuel
Rods due to Refueling Accident”, Rev. 0
19. ENTERGY Calculation VYC-3187, “Fuel Handling Accident Supplemental
Analysis (Specific to the Spent Fuel Pool”, Rev. 0
20. ENTERGY Calculation VYC-2275, “Control Room Air Intake X/Q Due to Release
from Reactor Building Blowout Panel Using Arcon96 Methodology” (Rev. 0,
April 2003)
21. ENTERGY Calculation VYC-2302, "Radiological AST LOCA Analysis" [PSAT
3019CF.QA.08, Rev. 2]
22. ASME Steam Tables, Sixth Edition
23. NUREG/CR-1918 (ORNL/NUREG-79), Dose Rate Conversion Factors for External
Exposure to Photons and Electrons (August 1981)
24. Regulatory Guide 1.109, Calculation of Annual Doses to Man from Routine
Releases of Reactor Effluents for the Purpose of Evaluating Compliance
with 10 CFR Part 50, Appendix I (Revision 1, October 1977), Table E-7,
Inhalation Dose Factors for Adults, Thyroid and Lung
VYNPS DSAR Revision 1 6.0-31 of 37
25. ICRP-30, Limits for Intake of Radionuclides by Workers, Supplement 1, pg
202
26. Regulatory Guide 1.109, Calculation of Annual Doses to Man from Routine
Releases of Reactor Effluents for the Purpose of Evaluating Compliance
with 10 CFR Part 50, Appendix I (Revision 1, October 1977), Table E-6,
External Dose Factors for Standing on Contaminated Ground, Total Body
VYNPS DSAR Revision 1 6.0-32 of 37
6.6 Appendices
Appendix A - Fuel Damage from Assembly Drop onto SFP Fuel Racks
BACKGROUND
Damage due to a drop of a fuel assembly within the SFP was evaluated using the
GESTAR II method (Reference 6.4-15). In GESTAR II Section S.2.2.3.5, GE presents
a methodology for estimating the number of fuel rods that fail as a result of a
fuel handling accident where one fuel bundle is dropped onto a grouping of
additional fuel bundles. This methodology was used to assess the fuel rod damage
impacts of a FHA in the spent fuel pool where one fuel bundle is dropped onto a
second fuel bundle contained within the SPF racks.
Figure A-1 shows the pertinent dimensions for the SFP. Critical to the analysis is
the maximum drop distance for an assembly, 22.74 inches (1.9 feet), increased to
3 ft to account for the difference in elevations between the top of the racks and
the top of assembly within the racks, as well as any other dimensional uncertainties
VYNPS DSAR Revision 1 6.0-33 of 37
Figure A‐1
Dimensions of SFP, Fuel Rack and Fuel Handling Equipment
METHODOLGY
Key inputs to the analysis are as shown Table 6.3.2.
The basic steps involved in the GESTAR II evaluation methodology are described in
the following paragraphs. Because this methodology is an approximation of the
behavior of an extremely complex series of mechanical interactions, a commentary
describing the explicit and implicit assumptions involved in each step is provided
with description of how each step is implemented.
VYNPS DSAR Revision 1 6.0-34 of 37
1. Calculate the available impact energy as a result of the initial drop.
The GESTAR II methodology is a simplified energy balance approach which
examines the kinetic energy of the falling fuel bundle and associated fuel
handling equipment, and from that calculates the number of failed fuel rods
based on an established fuel rod failure energy threshold. The kinetic
impact energy is taken to be equal to the initial potential energy of the
dropped bundle system, that is, the weight of the fuel bundle (with
associated fuel handling equipment weights) multiplied by the drop height.
This assumption avoids the complexities in establishing an expected impact
velocity for the fuel bundle falling through a fluid exerting a significant
drag force. This assumption will result in a conservatively high estimated
impact energy.
2. Calculate the energy available to fail rods.
The calculated impact energy is apportioned amongst the various components
involved in the impact event. One half of the energy is assumed to be
absorbed by the dropping fuel bundle and one half is assumed to be absorbed
by the stationary fuel bundle. Within the stationary fuel bundle, the impact
energy is further divided between the cladding and the remaining structural
(non-fuel pellet) material of the fuel bundle. This division is made by
using the ratio of the mass of the fuel cladding to the mass of the
remaining fuel bundle structure. For the GE fuel designs evaluated in the
GESTAR II analysis, the maximum ratio is 0.510.
3. Calculate the energy required to fail one fuel rod.
In the GESTAR II evaluation, detailed for GE-13 fuel, each fuel rod in the
stationary fuel bundles is expected to fail upon absorbing 200 ft-lb of
energy based on a failure criteria of 1% uniform plastic deformation. In
that evaluation, every rod in the dropped bundle is assumed to fail due to
excessive bending moments imposed on the lower tie plate. In VYC-2206, the
failure threshold for the stationary bundles was calculated to be 167 ft-lb
for the GE14 fuel design using a simple scaling of clad cross-sectional
area. Though no details of the derivation of this threshold are provided in
the GESTAR II documentation, it is anticipated that sufficient conservatism
is built in to use this value, particularly given the assumption of complete
fuel rod failure in the dropped bundle and the conservative apportionment of
impact energies amongst the fuel rods described below.
VYNPS DSAR Revision 1 6.0-35 of 37
4. Calculate the number of failed fuel rods as a result of the initial drop.
The number of fuel rods expected to fail as a result of the initial drop are
calculated simply as the energy available to fail fuel rods divided by the
energy required to fail one fuel rod. This method is conservative in that it
assumes that no deformation energy is “wasted” by deforming additional fuel
rods, though not to the point of failure. In other words, no other fuel rods
provide any support for the fuel rods that fail.
5. Calculate the Number of additional fuel rod failures due to the secondary, tip-over impact.
Added to the number of fuel rods failed as a result of the initial impact is
the number of rods expected to fail as the dropped fuel bundle tips over and
impacts additional fuel bundles in the core. Since the analysis considers a
drop within the spent fuel pool, and the tops of the fuel bundles being
stored are below the tops of the spent fuel racks, no additional bundle
impacts result from the tip-over portion of the accident.
ASSUMPTIONS
All rods in the dropped bundle are conservatively assumed to fail. The
number of failed rods for impacted bundles are established from an estimate
of "energy required to fail a fuel rod," given the size (thickness and
diameter) and thus the strength of the GE14 rod cladding, which is slightly
thinner than that for the GE-13 fuel (Reference 6.4-18, VYC-2206, Attachment
2). A strength for the GE14 10x10 using a ratio of cross-sectional areas
for GE-9 8x8 and GE-13 9x9 fuel arrays is determined (Reference 6.4-18, VYC-
2206. Attachment 2). Strength (necessary compression failure energy) for
the GE14 10x10 bundles was estimated to be 170.3 ft-lbs. As a conservative
estimate, the value of 167 ft-lb was used.
Fuel rods in an assembly are assumed to fail by 1% strain in compression
(Reference 6.4-15). It is expected that a GE14 fuel rod will absorb 167 ft-
lbs of energy in this failure mode. Since the partial length rods are not
attached to, and do not contact the upper tie plate, less energy should be
transferred to them if the fuel assembly is impacted. Therefore, assuming
that the part length rods fail at these force levels (if they do fail) is
conservative.
All fuel assemblies employed in the analysis were assumed to be discharged at
the same time so as to maximize the released radioactivity, as the noble gases
and halogens in older assemblies have already decayed to insignificant levels.
VYNPS DSAR Revision 1 6.0-36 of 37
The GESTAR II (Reference 6.4-15) analysis considers dropping a fuel bundle
drop, including a grapple mast and head. The added weight of the grapple
hook assembly and the fuel handling mast are added to the weight of the
dropped fuel bundle.
All rods in the dropped assembly are conservatively assumed to fail. The
GESTAR II (Reference 6.4-15) makes this assumption.
Toppling of the dropped assembly is assumed to result in no further damage
to assemblies in the rack due to the configuration of the rack, which
expends above the top of the assemblies themselves.
Conservatism relative to the results of impact is provided by assembly features that
should absorb some impact energy generated by a dropped assembly:
The raised rectangular lifting-handle assembly at the top of the assembly,
which may bend or fracture, dissipating impact energy,
Expansion springs within the assembly
The semi-circular insertion guide (assembly base extension) that stands out at
the bottom of the assembly and that are used to guide it into the centering
socket at the base of the fuel rack slot.
RESULTS
Results are summarized below for the failure of fuel rods in the impacted GE14 and
GNF2 10x10 assemblies. Most entries in this table are from Table 6.3.2;
calculated values include their derivation basis, in parentheses. All 92 rods in
the dropped assembly are assumed to fail. Impact of the dropped assembly in the
fuel rack results in an additional 5 GE14 failed rods (for a total of 97 failed
rods due to the accident), and in 6 GNF2 failed rods (for a total of 98). The
number of failed fuel rods for the drop in the SFP will be conservatively based on
98 assemblies, thus representative for both fuel assembly types.
VYNPS DSAR Revision 1 6.0-37 of 37
Description Assembly Type
GE14 GNF2
Maximum drop height (ft) 3 3
Weight of 10x10 fuel assembly and channel
submerged in water (lb) 569.5 580
Dry weight mast & grapple (lb)(a) 707.6 707.6
Weight of fuel assembly/channel submerged in
water + mast/grapple dry weight (lb)
1277.1
(569.5 +
707.6)
1287.6
(580.0
+707.6)
Available Impact Energy (wt x height, ft-lbs) 3831.3
(3 * 1277.1)
3862.8
(3 * 1287.6)
Energy absorbed by dropped fuel assembly (ft-
lbs)
1915.7
(3831.3 / 2)
1931.4
(3862.8 / 2)
Energy absorbed by stationary fuel bundle (ft-
lbs) 1915.7 1931.4
Percent energy for stationary clad deformation
(GESTAR II) 0.51 0.51
Energy to stationary fuel bundle for clad
deformation (ft-lbs)
977.0
(1915.7 *
0.51)
985.0
(1931.4 *
0.51)
Failed rods in dropped assembly (assumed all) 92 92
Energy required to damage stationary fuel rods 167 157
1st impact damaged stationary fuel rods
(analytical value)
5.9
(977.0 / 167)
6.3
(985.0 / 157)
Total number failed rods (Note: Damaged
stationary rod numbers were rounded down to
whole rods since there can be no partial rod
damage.)
97
(92+5)
98
(92+6)
(a) The mast and grapple were conservatively assigned their dry weight since the
SFP geometry permits only their partial submersion during the assembly drop.
The dry weight of 707.6 lbs. was calculated based on a wet weight of 619
lbs. (Table 6.3-2, Item #B4), a density of 7.85 g/cc for the mast and
grapple (i.e., that of iron) and a density of 0.983 g/cc for water at 140 oF
from ASME Steam Tables, Sixth Edition (Reference 6.4-22): 619 * 7.85 /
(7.85 – 0.983) = 707.6 lb.
VYNPS DSAR Revision 1 7.0-1 of 13
AGING MANAGEMENT
TABLE OF CONTENTS Section Title Page
7.1 SUPPLEMENT FOR RENEWED OPERATING LICENSE ............................. 2
7.2 AGING MANAGEMENT PROGRAMS AND ACTIVITIES .............................. 2
7.2.1 Deleted ..................................................... 2
7.2.2 Diesel Fuel Monitoring Program .............................. 3
7.2.3 Fire Protection Program ..................................... 3
7.2.4 Fire Water System Program ................................... 3
7.2.5 Instrument Air Quality Program .............................. 4
7.2.6 Non-EQ Inaccessible Medium-Voltage Cable Program ............................................................ 4
7.2.7 Oil Analysis Program ........................................ 5
7.2.8 Periodic Surveillance and Preventive Maintenance Program ..................................................... 5
7.2.9 Service Water Integrity Program ............................. 5
7.2.10 Structures Monitoring – Masonry Wall Program. ................ 6
7.2.11 Structures Monitoring – Structures Monitoring Program ..................................................... 6
7.2.12 System Walkdown Program ..................................... 6
7.2.13 Water Chemistry Control – Auxiliary Systems Program ..................................................... 6
7.2.14 Water Chemistry Control – BWR Program ....................... 7
7.2.15 Deleted ..................................................... 7
7.2.16 Bolting Integrity Program ................................... 7
7.2.17 Deleted ..................................................... 7
7.2.18 Deleted ..................................................... 7
7.2.19 Neutron Absorber Monitoring Program ......................... 7
7.3 REFERENCES ........................................................... 8
7.4 LIST OF LICENSE RENEWAL COMMITMENTS .................................. 9
VYNPS DSAR Revision 1 7.0-2 of 13
7.1 SUPPLEMENT FOR RENEWED OPERATING LICENSE
The Vermont Yankee Nuclear Power Station (VYNPS) license renewal application
(LRA) (Reference 7.3.1) and information in subsequent related correspondence
provided sufficient basis for the NRC to make the findings required by 10 CFR
54.29 (Final Safety Evaluation Report) (References 2, 3 and 4). As required by
10 CFR 54.21(d), this DSAR supplement contains a summary description of the
remaining programs and activities for managing the effects of aging.
7.2 AGING MANAGEMENT PROGRAMS AND ACTIVITIES
The integrated plant assessment for license renewal identified aging
management programs necessary to provide reasonable assurance that components
within the scope of license renewal will continue to perform their intended
functions consistent with the current licensing basis (CLB). This section
describes the aging management programs and activities that will be required
during the period of wet fuel storage.
VYNPS quality assurance (QA) procedures, review and approval processes, and
administrative controls are implemented in accordance with the requirements of
10 CFR 50, Appendix B. The Quality Assurance Program applies to safety-related
structures and components. Corrective actions and administrative (document)
control for both safety-related and non-safety related structures and
components are accomplished per the existing VYNPS corrective action program
and document control program and are applicable to all aging management
programs and activities that will be required during the period of wet fuel
storage. The confirmation process is part of the corrective action program and
includes reviews to assure that proposed actions are adequate, tracking and
reporting of open corrective actions, and review of corrective action
effectiveness. Any follow-up inspection required by the confirmation process
is documented in accordance with the corrective action program.
The corrective action, confirmatory process, and administrative controls of
the (10 CFR Part 50, Appendix B) Quality Assurance Program are applicable to
all aging management programs and activities that will be required during the
period of wet fuel storage.
7.2.1 Deleted
VYNPS DSAR Revision 1 7.0-3 of 13
7.2.2 Diesel Fuel Monitoring Program
The Diesel Fuel Monitoring Program entails sampling to ensure that adequate
diesel fuel quality is maintained to prevent plugging of filters, fouling of
injectors, and corrosion of fuel systems. Exposure to fuel oil contaminants
such as water and microbiological organisms is minimized by periodic draining
and cleaning of tanks and by verifying the quality of new oil before its
introduction into storage tanks.
7.2.3 Fire Protection Program
The Fire Protection Program includes a fire barrier inspection and a diesel-
driven fire pump inspection. The fire barrier inspection requires periodic
visual inspection of fire barrier penetration seals, fire barrier walls,
ceilings, and floors, and periodic visual inspection and functional tests of
fire rated doors to ensure that their functionality is maintained. The diesel-
driven fire pump inspection requires that the pump be periodically tested to
ensure that the fuel supply line can perform its intended function.
Corrective actions, confirmation process, and administrative controls in
accordance with the requirements of 10 CFR Part 50 Appendix B are applied to
the Fire Protection Program.
7.2.4 Fire Water System Program
The Fire Water System Program applies to water-based fire protection systems
that consist of sprinklers, nozzles, fittings, valves, hydrants, standpipe
hose connections, standpipes, and aboveground and underground piping and
components that are tested in accordance with applicable National Fire
Protection Association (NFPA) codes and standards. Such testing assures
functionality of systems. Also, many of these systems are normally maintained
at required operating pressure and monitored such that leakage resulting in
loss of system pressure is immediately detected and corrective actions
initiated.
In addition, wall thickness evaluations of fire protection piping are
periodically performed on system components using non-intrusive techniques
(e.g. volumetric testing) to identify evidence of loss of material due to
corrosion.
A sample of sprinkler heads will be inspected using the guidance of NFPA 25
(2002 Edition) Section 5.3.1.1.1, which states, “Where sprinklers have been in
place for 50 years, they shall be replaced or representative samples from one
or more sample areas shall be submitted to a recognized testing laboratory for
field service testing.” This sampling will be repeated every 10 years after
initial field service testing.
VYNPS DSAR Revision 1 7.0-4 of 13
7.2.5 Instrument Air Quality Program
The Instrument Air Quality Program ensures that instrument air supplied to
components is maintained free of water and significant contaminants, thereby
preserving an environment that is not conducive to loss of material. Dew point
and hydrocarbon concentration are periodically checked to verify the instrument
air quality is maintained.
7.2.6 Non-EQ Inaccessible Medium-Voltage Cable Program
In the Non-EQ Inaccessible Medium-Voltage Cable Program, medium-voltage cables
with a license renewal intended function that are exposed to significant
moisture and voltage are tested at least once every six years to provide an
indication of the condition of the conductor insulation. The specific test
performed is a proven test for detecting deterioration of the insulation
system due to wetting, such as power factor, partial discharge, polarization
index, or other testing that is state-of-the-art at the time the test is
performed. Significant moisture is defined as periodic exposures that last
more than a few days.
Inspections for water collection in cable manholes containing inaccessible
low-voltage and medium-voltage cables with a license renewal intended function
will occur at least once every year. Additional condition-based inspections of
these manholes will be performed based on: a) potentially high water table
conditions, as indicated by high river level, and b) after periods of heavy
rain. The inspection results are expected to indicate whether the inspection
frequency should be modified. The manhole inspection will include direct
observation that cables are not wetted or submerged, that cables/splices and
cable support structures are intact, and that dewatering/drainage systems
(i.e. sump pumps), if installed, and associated alarms operate properly.
Inaccessible low-voltage cables (cables with operating voltage from 400 V to 2
kV) with a license renewal intended function are included in this program.
Inaccessible low-voltage cables will be tested for degradation of the cable
insulation prior to the period of extended operation and at least once every
six years thereafter. A proven, commercially available test will be used for
detecting deterioration of the insulation system for inaccessible low-voltage
cables potentially exposed to significant moisture. Failure of the cable test
results and manhole inspections to meet the acceptance criteria will require
corrective actions. The corrective actions will address modifying the cable
test frequency and the manhole inspection frequency.
VYNPS DSAR Revision 1 7.0-5 of 13
7.2.7 Oil Analysis Program
The Oil Analysis Program maintains oil systems free of contaminants (primarily
water and particulates) thereby preserving an environment that is not
conducive to loss of material, cracking, or fouling. Activities include
sampling and analysis of lubricating oil for detrimental contaminants, water,
and particulates.
Sampling frequencies are based on vendor recommendations, accessibility during
facility operation, equipment importance to facility operation, and previous
test results.
7.2.8 Periodic Surveillance and Preventive Maintenance Program
The Periodic Surveillance and Preventive Maintenance Program includes periodic
inspections and tests that manage aging effects not managed by other aging
management programs. The preventive maintenance and surveillance testing
activities are generally implemented through repetitive tasks or routine
monitoring of facility operations.
Periodic inspections using visual or other non-destructive examination
techniques verify that the following components are capable of performing
their intended function.
reactor building crane, rails, and girders
refueling platform carbon steel components
equipment lock sliding doors
yard concrete handholes and manholes
housings of control room HVAC package heating and cooling coils, control room chiller, and control room chilled water condensers
control room ventilation fan duct flexible connections
instrument air supply systems
internal surfaces of carbon steel components in the potable water system containing untreated water
internal surfaces of carbon steel and copper alloy components in the radwaste system containing untreated water
7.2.9 Service Water Integrity Program
The Service Water Integrity Program ensures that the effects of aging on the
service water system (SWS) will be managed for the period of wet fuel storage.
The program includes opportunistic component inspections for erosion,
corrosion, and blockage to verify the heat transfer capability of the safety-
related and nonsafety-related heat exchangers cooled by SWS. Chemical
treatment and periodic cleaning are used to control or prevent fouling within
the SWS heat exchangers.
VYNPS DSAR Revision 1 7.0-6 of 13
7.2.10 Structures Monitoring – Masonry Wall Program.
The objective of the Masonry Wall Program is to manage cracking so that the evaluation basis established for each masonry wall within the scope of license renewal remains valid through the period of wet fuel storage.
The program includes all masonry walls identified as performing intended functions in accordance with 10 CFR 54.4. Included walls are the 10 CFR 50.48 required walls and masonry walls in the reactor building, intake structure and control room building.
Masonry walls are visually examined at a frequency selected to ensure there is no loss of intended function between inspections.
7.2.11 Structures Monitoring – Structures Monitoring Program Structures monitoring is in accordance with 10 CFR 50.65 (Maintenance Rule) as
addressed in Regulatory Guide (RG) 1.160 and NUMARC 93-01. Periodic
inspections are used to monitor condition of structures and structural
components to ensure there is no loss of structure or structural component
intended function.
7.2.12 System Walkdown Program The System Walkdown Program entails inspections of external surfaces of
components subject to aging management review. The program is also credited
with managing loss of material from internal surfaces, for situations in which
internal and external material and environment combinations are the same such
that external surface condition is representative of internal surface
condition.
Surfaces that are not readily accessible, such as piping located in
underground vaults, are inspected at least once every 5 years. The inspection
frequencies provide reasonable assurance that the effects of aging will be
managed such that applicable components will perform their intended function
during the period of wet fuel storage.
7.2.13 Water Chemistry Control – Auxiliary Systems Program
The purpose of the Water Chemistry Control – Auxiliary Systems Program is to
manage aging effects for components exposed to treated water.
VYNPS DSAR Revision 1 7.0-7 of 13
7.2.14 Water Chemistry Control – BWR Program
The objective of the Water Chemistry Control - BWR Program is to manage aging
effects caused by corrosion and cracking mechanisms. The program relies on
monitoring and control of water chemistry based on BWR Water Chemistry
Guidelines, 2008 Revision (BWRVIP-190). EPRI guidelines in BWRVIP-190 include
recommendations for controlling water chemistry in the torus, condensate
storage tank, demineralized water storage tanks, and spent fuel pool.
7.2.15 Deleted
7.2.16 Bolting Integrity Program
The Bolting Integrity Program relies on recommendations for a comprehensive
bolting integrity program, as delineated in NUREG-1339, and industry
recommendations, as delineated in the Electric Power Research Institute (EPRI)
NP-5769, with the exceptions noted in NUREG-1339 for safety-related bolting.
The program relies on industry recommendations for comprehensive bolting
maintenance, as delineated in EPRI TR-104213 for pressure retaining bolting
and structural bolting.
7.2.17 Deleted
7.2.18 Deleted
7.2.19 Neutron Absorber Monitoring Program
The Neutron Absorber Monitoring Program is a new program that will manage loss
of material and reduction of neutron absorption capacity of Boral neutron
absorption panels in the spent fuel racks. The loss of material and the
reduction of the neutron-absorbing capacity will be determined through coupon
testing, direct in situ testing or both. Such testing will include periodic
verification of boron loss through areal density measurement of coupons or
through direct in situ techniques, such as measurement of boron areal density,
measurement of geometric changes in the material (blistering, pitting and
bulging), and detection of gaps through blackness testing.
VYNPS DSAR Revision 1 7.0-8 of 13
7.3 REFERENCES
1. VYNPS License Renewal Application
2. NUREG-1907, “Safety Evaluation Report Relating to the License
Renewal of Vermont Yankee Nuclear Power Station,” May 2003.
3. NUREG-1907, Supplement 1, “Safety Evaluation Report Related to the
License Renewal of Vermont Yankee Nuclear Power
Station,” September 2009.
4. NUREG-1907, Supplement 2, “Safety Evaluation Report Related to the
License Renewal of Vermont Yankee Nuclear Power Station,” April 2011.
VERMONT YANKEE NUCLEAR POWER STATION LICENSE RENEWAL COMMITMENT LIST
VYNPS DSAR
Revision 1 7.0-9 of 13
7.4 LIST OF LICENSE RENEWAL COMMITMENTS
During the review of the VYNPS LRA by the staff of the US Nuclear Regulatory Commission (NRC), Entergy Nuclear
Operations, Inc. made commitments related to aging management programs (AMPs) to manage the aging effects of
structures and components prior to the period of extended operation. The following table lists these
commitments remaining applicable following permanent cessation of operations and certification of permanent
defueling. The implementation schedules and the sources for each commitment are also provided.
ITEM
COMMITMENT
IMPLEMENTATION
SCHEDULE
LRA Section
SOURCE
3
The Diesel Fuel Monitoring Program will be enhanced to ensure ultrasonic thickness measurement of the fuel oil storage tank bottom surface will be performed every 10 years during tank cleaning and inspection. Ultrasonic thickness measurement of the fire pump diesel storage (day) tank bottom will be performed every 10 years.
March 21, 2012
B.1.9
BVY 06-009
BVY 07-018
LBDCR# FCR 26/009
4
The Diesel Fuel Monitoring Program will be enhanced to specify that UT measurements of the fuel oil storage tank bottom surface will have acceptance criterion in accordance with American Petroleum Institute standard API 653 and UT measurements of the fire pump diesel storage (day) tank bottom surface will have acceptance criterion in accordance with Steel Tank Institute standard STI SP001.
March 21, 2012
B.1.9
BVY 06-009
BVY 07-018
BVY 10-069 BVY 11-007
8
Procedures will be enhanced to specify that fire damper frames in fire barriers will be inspected for corrosion. Acceptance criteria will be enhanced to verify no significant corrosion.
March 21, 2012
B.1.12.1
BVY 06-009
VERMONT YANKEE NUCLEAR POWER STATION LICENSE RENEWAL COMMITMENT LIST
VYNPS DSAR
Revision 1 7.0-10 of 13
ITEM
COMMITMENT
IMPLEMENTATION
SCHEDULE
LRA Section
SOURCE
9
Procedures will be enhanced to state that the diesel engine sub-systems (including the fuel supply line) will be observed while the pump is running. Acceptance criteria will be enhanced to verify that the diesel engine did not exhibit signs of degradation while it was running; such as fuel oil, lube oil, coolant, or exhaust gas leakage.
March 21, 2012
B.1.12.1
BVY 06-009
10
Fire Water System Program procedures will be enhanced to specify that in accordance with NFPA 25 (2002 edition), Section 5.3.1.1.1, when sprinklers have been in place for 50 years a representative sample of sprinkler heads will be submitted to a recognized testing laboratory for field service testing. This sampling will be repeated every 10 years.
March 21, 2012
B.1.12.2
BVY 06-009
11
The Fire Water System Program will be enhanced to specify that wall thickness evaluations of fire protection piping will be performed on system components using non-intrusive techniques (e.g., volumetric testing) to identify evidence of loss of material due to corrosion. These inspections will be performed before the end of the current operating term and during the period of extended operation. Results of the initial evaluations will be used to determine the appropriate inspection interval to ensure aging effects are identified prior to loss of intended function.
March 21, 2012
B.1.12.2
BVY 06-009
VERMONT YANKEE NUCLEAR POWER STATION LICENSE RENEWAL COMMITMENT LIST
VYNPS DSAR
Revision 1 7.0-11 of 13
ITEM
COMMITMENT
IMPLEMENTATION
SCHEDULE
LRA Section
SOURCE
13
Implement the Non-EQ Inaccessible Medium-Voltage Cable Program as described in LRA Section B.1.17.
Inspections for water accumulation in manholes containing inaccessible low-voltage and medium-voltage cables with a license renewal intended function will be performed at least once every year. Additional condition-based inspections of these manholes will be performed based on: a) potentially high water table conditions, as indicated by high river level, and b) after periods of heavy rain. The inspection results are expected to indicate whether the inspection frequency should be modified.
Inaccessible low-voltage cables (400 V to 2 kV) with a license renewal intended function are included in this program. Inaccessible low-voltage cables will be tested for degradation of the cable insulation prior to the period of extended operation and at least once every six years thereafter. A proven, commercially available test will be used for detecting deterioration due to wetting of the insulation system for inaccessible low-voltage cables.
March 21, 2012
B.1.17
BVY 06-009
BVY 10-050
BVY 10-058
17
Enhance the Periodic Surveillance and Preventive Maintenance Program to assure that the effects of aging will be managed as described in LRA Section B.1.22, with the exception of SSCs which have been abandoned.
March 21, 2012
B.1.22
BVY 06-009
20
Enhance the Structures Monitoring Program to specify that process facility crane rails and girders, condensate storage tank (CST) enclosure, CO2 tank enclosure, N2 tank enclosure and restraining wall, CST pipe trench, diesel generator cable trench, fuel oil pump house, service water pipe trench, man-way seals and gaskets, and hatch seals and gaskets are included in the program.
March 21, 2012
B.1.27.2
BVY 06-009
VERMONT YANKEE NUCLEAR POWER STATION LICENSE RENEWAL COMMITMENT LIST
VYNPS DSAR
Revision 1 7.0-12 of 13
ITEM
COMMITMENT
IMPLEMENTATION
SCHEDULE
LRA Section
SOURCE
22
Guidance for performing structural examinations of elastomers (seals and gaskets) to identify cracking and change in material properties (cracking when manually flexed) will be enhanced in the Structures Monitoring Program procedure.
March 21, 2012
B.1.27.2
BVY 06-009
24
System walkdown guidance documents will be enhanced to perform periodic system engineer inspections of systems in scope and subject to aging management review for license renewal in accordance with 10 CFR 54.4 (a)(1) and (a)(3). Inspections shall include areas surrounding the subject systems to identify hazards to those systems. Inspections of nearby systems that could impact the subject system will include SSCs that are in scope and subject to aging management review for license renewal in accordance with 10 CFR 54.4 (a)(2).
March 21, 2012
B.1.28
BVY 06-009
28
Revise program procedures to indicate that the Instrument Air Program will maintain instrument air quality in accordance with ISA S7.3
March 21, 2012
B.1.16
BVY 06-009
30
Revise System Walkdown Program to specify CO2 system inspections every 6 months.
March 21, 2012
B.1.28
BVY 06-009
31
Revise Fire Water System Program to specify annual fire hydrant gasket inspections and flow tests.
March 21, 2012
B.1.12.2
BVY 06-009
33
Include within the Structures Monitoring Program provisions that will ensure an engineering evaluation is made on a periodic basis (at least once every five years) of groundwater samples to assess aggressiveness of groundwater to concrete. Samples will be monitored for sulfates, pH and chlorides.
March 21, 2012
B.1.27
BVY 06-009
VERMONT YANKEE NUCLEAR POWER STATION LICENSE RENEWAL COMMITMENT LIST
VYNPS DSAR
Revision 1 7.0-13 of 13
ITEM
COMMITMENT
IMPLEMENTATION
SCHEDULE
LRA Section
SOURCE
34
Implement the Bolting Integrity Program.
Details are provided in a LRA Amendment 16, Attachment 2 and LRA Amendment 23, Attachment 5.
March 21, 2012
B.1.31
BVY 06-058
BVY 07-003
BVY 06-091
35
Provide within the System Walkdown Training Program a process to document biennial refresher training of Engineers to demonstrate inclusion of the methodology for aging management of plant equipment as described in EPRI Aging Assessment Field Guide or comparable instructional guide.
March 21, 2012
B.1.28
BVY 06-058
46 Enhance the Diesel Fuel Monitoring Program to specify that fuel oil in the fire pump diesel storage (day) tank will be analyzed according to ASTM D975 and for particulates per ASTM D2276.
March 21, 2012 B.1.9 BVY 07-018
BVY 10-069
BVY 11-007
47
Enhance the Diesel Fuel Monitoring Program to specify that fuel oil in the common portable fuel oil storage tank will be analyzed according to ASTM D975, per ASTM D2276 for particulates, and per ASTM D2709 for water and sediment.
March 21, 2012
B.1.9
BVY 07-018
BVY 10-069
BVY 11-007
52
Implement the Neutron Absorber Monitoring Program as described in LRA Section B.1.31.
Test one coupon prior to the PEO to measure B-10 areal density and assess the geometric and physical condition of the tested coupon. If coupons are not able to be retrieved and tested or if coupons cannot be demonstrated representative of the Boral in the Holtec racks, then perform neutron attenuation testing using in-situ methods, as described in BVY 11-010, (BADGER or blackness testing method) prior to the end of 2014.
March 21, 2012
B.1.31
BVY 10-052
BVY 10-058
BVY 11-013
VYNPS DSAR Revision 1 G.2-1 of 40
APPENDIX G.2 CURRENT ON-SITE METEOROLOGICAL PROGRAM TABLE OF CONTENTS Section Title Page
G.2.1 Introduction......................................................... 4
G.2.2 Description of the Monitoring Program................................ 4
G.2.3 Results.............................................................. 5
G.2.3.1 Wind Data ................................................. 5
G.2.3.2 Inversion Data ............................................ 6
VYNPS DSAR Revision 1 G.2-2 of 40
CURRENT ON-SITE METEOROLOGICAL PROGRAM LIST OF TABLES Table No. Title
G.2.1 Meteorological Data Recovery Rates for 1980
G.2.2 Joint Frequency Distribution of Wind Speed, Wind Direction,
and Stability Class (Stability Based on 295-33 Foot Delta-
T)(35.0 FT Wind Data)
G.2.3 Joint Frequency Distribution of Wind Speed, Wind Direction,
and Stability Class (Stability Based on 295-33 Foot Delta-T)
(297 foot level FT Wind Data)
G.2.4 Wind Direction Persistence Summary (35 foot level)
G.2.5 Wind Direction Persistence Summary (297 foot level)
G.2.6 Inversion Persistence Summary (198-33 foot Delta T)
G.2.7 Inversion Persistence Summary (295-33 foot Delta T)
VYNPS DSAR Revision 1 G.2-3 of 40
CURRENT ON-SITE METEOROLOGICAL PROGRAM LIST OF FIGURES Reference Figure No. Drawing No. Title G.2-1 Location of Primary and Backup
Meteorological Towers
G.2-2 "Spring Wind Rose (35 foot level)
March 1980 May 1980"
G.2-3 Summer Wind Rose (35 foot level) June 1980
August 1980
G.2-4 Autumn Wind Rose (35 foot level) September
1980 November 1980
G.2-5 Winter Wind Rose (35 foot level) January
1980 February 1980; December 1980
G.2-6 Annual Wind Rose (35 foot level) January
1980 December 1980
G.2-7 Spring Wind Rose (297 foot level) March
1980 May 1980
G.2-8 Summer Wind Rose (297 foot level) June
1980 August 1980
G.2-9 Autumn Wind Rose (297 foot level)
September 1980 November 1980
G.2-10 Winter Wind Rose (297 foot level) January
1980 February 1980; December 1980
G.2-11 Annual Wind Rose (297 foot level) January
1980 December 1980
VYNPS DSAR Revision 1 G.2-4 of 40
G.2 CURRENT ON-SITE METEOROLOGICAL PROGRAM
G.2.1 Introduction
The On-Site Meteorological Data Collection Program was upgraded in early 1976
to meet the intent of Revision 0 of Regulatory Guide 1.23. This report
describes the current on-site monitoring program and presents wind and
stability data summaries for one full year of operation; January 1, 1980
through December 31, 1980. A discussion of the data summaries is included,
and a comparison is made between data collected by the initial monitoring
program (August 1967 - July 1968) and data collected by the current monitoring
program (January 1980 - December 1980). It is concluded that results from
both monitoring programs are compatible, and that both programs produced data
bases which are representative of site meteorology.
G.2.2 Description of the Monitoring Program
The current Meteorological Monitoring System includes both a primary and a
backup system. The primary system utilizes a guyed 305-foot tower located
on-site as shown in Figure G.2-1. The parameters measured on the tower
include the following:
Wind speed at the 35-foot and 297-foot levels (3-cup anemometer sensors)
Wind direction at the 35-foot and 297-foot levels (airfoil vane sensors)
Temperature at the 33-foot level (RTD located in a radiation-shielded
aspirator)
Delta-temperature between the 198-33 foot and between the 295-33 foot
levels (RTDs located in radiation-shielded aspirators)
In addition, both precipitation and barometric pressure are measured on the
ground.
The translator cards for the tower sensors are located in an instrument shed
near the base of the tower. The analog output is then digitally transmitted
to one of the plant process computer's remote data acquisition terminals. The
plant process computer periodically scans each parameter and then digitally
compiles and records the data as 15-minute averages. The 15-minute averages
are available for display in the Control Room. A digital recorder, located in
the relay house is also utilized as an auxiliary data logger. The entire
system is currently supplied by redundant power sources.
A 140-foot guyed tower used previously for meteorological monitoring was
VYNPS DSAR Revision 1 G.2-5 of 40
reinstrumented during 1980 to serve as a backup tower. This tower's location
is also shown in Figure G.2-1. The parameters measured on the backup tower
include:
Wind speed at the 100-foot level (3-cup anemometer sensor)
Wind direction at the 100-foot level (airfoil vane sensors)
Delta-temperature between the 135-33 foot levels (RTDs located in
radiation-shielded aspirators)
The translator cards for the tower sensors are located in an instrument shed
near the base of the tower. The analog is then transmitted digitally to the
Control Room and sampled by the plant process computer. The signals are also
captured by a digital recorder, which is also utilized as an auxiliary data
logger.
G.2.3 Results
The primary meteorological system was the data source for the 1980 data
summaries which follow. The digital recording system was the principal data
collection mechanism. The data base consists of hourly data where the first
15-minute average collected each hour is used to represent the hour. The
analog strip chart recorders were utilized as backup data loggers for quality
control analysis, and data from the strip charts were used to fill in gaps in
the digital data base. The resulting data recovery rates, which are well
above the Regulatory Guide 1.23 goal of 90%, are presented in Table G.2.1.
G.2.3.1 Wind Data
Seasonal and annual wind roses for all stabilities combined from each tower
level are presented in Figures G.2-2 through G.2-11. Annual three-way joint
frequency summaries of wind speed, wind direction, and stability (stability
defined as a function of delta-temperature per Rev. 0 of Regulatory Guide
1.23) for both tower levels are also presented in Tables G.2.2 and G.2.3.
Comparison with the initial monitoring program results shows good agreement.
The seasonal and annual wind roses from each tower level continue to
illustrate the channelling effect of the Connecticut River Valley upon the
winds. Winds generally blow with the highest frequency from the NNW and SSE.
The annual average wind speeds for the current monitoring program were 6.2 mph
for the 35-foot level and 9.2 mph for the 297-foot level. These average wind
speeds compare well with the 140-foot level annual average wind speed of 7.5
mph for the initial monitoring program, if one considers the expected
variation of wind speed with height from the surface.
VYNPS DSAR Revision 1 G.2-6 of 40
Wind direction persistence summaries for 1980 are presented in Tables G.2.4
and G.2.5. Summarizing the persistence information, 74.9% of the 35-foot and
69.5% of the 297-foot cases during 1980 were one-hour events, and only one of
the 35-foot and nine of the 297-foot persistence cases were more than 15 hours
long. This compares well with the initial monitoring program which found that
69.0% of its persistence cases were one-hour events and only five persistence
cases were more than 15 hours long.
G.2.3.2 Inversion Data
The annual stability class frequency distribution for the initial and current
monitoring programs compare as follows:
Stability Case Initial Program Current Program
140-5 Foot Delta-T
198-33 Foot Delta-T
(Ref. Table G.2.2)
295-33 Foot Delta-T
(Ref. Table G.2.3)
Unstable (A,B,C) 25.4% 14.9% 8.1%
Neutral (D) 25.1% 37.1% 43.0%
Stable (E,F,G) 49.5% 48.0% 48.9%
Differences in the above frequency distributions can be expected due to the
differences in measurement heights. Measurement heights are important because
the largest temperature gradients occur near the ground due to surface heating
during the day and radiative cooling at night.
Inversions, defined as a positive value of delta-temperature, occurred 33.6%
and 32.7% of the time during 1980 for the 198-33 foot and 295-33 foot
delta-temperature measurements, respectively. Inversions occurred at the site
nearly 39% of the time during the initial data collection period.
Tables G.2.6 and G.2.7 present the annual inversion persistence summaries for
1980. The longest inversion measured during the year lasted 38 hours.
VYNPS DSAR Revision 1 G.2-7 of 40
TABLE G.2.1 Meteorological Data Recovery Rates for 1980
Parameter Possible Hours Usable Hours Recovery Rate
35-Foot Wind Speed 8784 8723 99.3%
297-Foot Wind Speed 8784 8721 99.3%
35-Foot Wind Direction 8784 8763 99.8%
297-Foot Wind Direction 8784 8573 97.6%
33-Foot Temperature 8784 8734 99.4%
198-33 Foot Delta-T 8784 8703 99.1%
295-33 Foot Delta-T 8784 8710 99.2%
Precipitation 8784 8474 96.5%
Solar Radiation 8784 8768 99.8%
Composite (35' WS, 35' WD, 198-33' DT)
8784
8659
98.6%
Composite (297' WS, 297' WD, 295-33' DT)
8784
8474
96.5%
VYNPS DSAR Revision 1 G.2-8 of 40
Table G.2.2
Joint Frequency Distribution of Wind Speed Wind Direction, and Stability Class
(Stability Based on 198-33 Foot Delta-T) 35.0 FT WIND DATA STABILITY CLASS A CLASS FREQUENCY (PERCENT) = 6.14 WIND DIRECTION FROM
SPEED (MPH) N NNE NE ENE E ESE SE SSE S SSW SW WSW W WNW NW NNW VRBL TOTAL
CALM (1) (2)
0 0.00 0.00
0 0.00 0.00
0 0.00 0.00
0 0.00 0.00
00.000.00
00.000.00
00.000.00
00.000.00
00.000.00
00.000.00
0 0.00 0.00
00.000.00
00.000.00
00.000.00
00.000.00
00.000.00
00.000.00
0 0.00 0.00
C-3 (1) (2)
2 .38 .02
7 1.32 .08
6 1.13 .07
7 1.32 .08
71.32.08
101.88.12
91.69.10
5.94.06
4.75.05
00.000.00
2 .38 .02
2.38.02
1.19.01
1.19.01
1.19.01
3.56.03
00.000.00
67 12.59
.77
4-7 (1) (2)
14 2.63 .16
10 1.88 .12
13 2.44 .15
19 3.57 .22
285.26.32
173.20.20
142.63.16
203.76.23
71.32.08
4.75.05
2 .38 .02
1.19.01
1.19.01
3.56.03
173.20.20
366.77.42
00.000.00
206 38.72 2.38
8-12 (1) (2)
16 3.01 .18
3 .56 .03
2 .38 .02
0 0.00 0.00
5.94.06
4.75.05
142.63.16
458.46.52
193.57.22
5.94.06
1 .19 .01
2.38.02
5.94.06
4.75.05
224.14.25
6211.65
.72
00.000.00
209 39.29 2.41
13-18 (1) (2)
4 .75 .05
0 0.00 0.00
0 0.00 0.00
0 0.00 0.00
00.000.00
00.000.00
00.000.00
1.19.01
00.000.00
00.000.00
1 .19 .01
1.19.01
3.56.03
1.19.01
112.07.13
275.08.31
00.000.00
49 9.21 .57
19-24 (1) (2)
0 0.00 0.00
0 0.00 0.00
0 0.00 0.00
0 0.00 0.00
00.000.00
00.000.00
00.000.00
00.000.00
00.000.00
00.000.00
0 0.00 0.00
00.000.00
00.000.00
1.19.01
00.000.00
00.000.00
00.000.00
1 .19 .01
GT 24 (1) (2)
0 0.00 0.00
0 0.00 0.00
0 0.00 0.00
0 0.00 0.00
00.000.00
00.000.00
00.000.00
00.000.00
00.000.00
00.000.00
0 0.00 0.00
00.000.00
00.000.00
00.000.00
00.000.00
00.000.00
00.000.00
0 0.00 0.00
ALL SPEEDS (1) (2)
36 6.77 .42
20 3.76 .23
21 3.95 .24
26 4.89 .30
407.52.46
315.83.36
376.95.43
7113.35
.82
305.64.35
91.69.10
6 1.13 .07
61.13.07
101.88.12
101.88.12
519.59.59
12824.061.48
00.000.00
532 100.00
6.14
(1) = PERCENT OF ALL GOOD OBSERVATIONS FOR THIS PAGE (2) = PERCENT OF ALL GOOD OBSERVATIONS FOR THIS PERIOD C=CALM (WIND SPEED LESS THAN OR EQUAL TO .60 MPH)
VYNPS DSAR Revision 1 G.2-9 of 40
TABLE G.2.2 35.0 FT WIND DATA STABILITY CLASS B CLASS FREQUENCY (PERCENT) = 4.09 WIND DIRECTION FROM
SPEED (MPH) N NNE NE ENE E ESE SE SSE S SSW SW WSW W WNW NW NNW VRBL TOTAL
CALM (1) (2)
0 0.00 0.00
0 0.00 0.00
0 0.00 0.00
0 0.00 0.00
00.000.00
00.000.00
00.000.00
00.000.00
00.000.00
00.000.00
0 0.00 0.00
00.000.00
00.000.00
00.000.00
00.000.00
00.000.00
00.000.00
0 0.00 0.00
C-3 (1) (2)
0 0.00 0.00
7 1.98 .08
2 .56 .02
4 1.13 .05
51.41.06
51.41.06
51.41.06
41.13.05
3.85.03
2.56.02
1 .28 .01
1.28.01
1.28.01
1.28.01
1.28.01
3.85.03
00.000.00
45 12.71
.52
4-7 (1) (2)
14 3.95 .16
5 1.41 .06
3 .85 .03
8 2.26 .09
195.37.22
82.26.09
113.11.13
92.54.10
51.41.06
1.28.01
3 .85 .03
2.56.02
1.28.01
61.69.07
123.39.14
257.06.29
00.000.00
132 37.29 1.52
8-12 (1) (2)
9 2.54 .10
0 0.00 0.00
0 0.00 0.00
0 0.00 0.00
1.28.01
1.28.01
2.56.02
71.98.08
102.82.12
00.000.00
4 1.13 .05
41.13.05
51.41.06
113.11.13
123.39.14
349.60.39
00.000.00
100 28.25 1.15
13-18 (1) (2)
2 .56 .02
1 .28 .01
0 0.00 0.00
0 0.00 0.00
00.000.00
00.000.00
00.000.00
2.56.02
3.85.03
00.000.00
2 .56 .02
1.28.01
113.11.13
92.54.10
123.39.14
287.91.32
00.000.00
71 20.06
.82
19-24 (1) (2)
0 0.00 0.00
0 0.00 0.00
0 0.00 0.00
0 0.00 0.00
00.000.00
00.000.00
00.000.00
00.000.00
00.000.00
00.000.00
0 0.00 0.00
00.000.00
2.56.02
1.28.01
1.28.01
2.56.02
00.000.00
6 1.69 .07
GT 24 (1) (2)
0 0.00 0.00
0 0.00 0.00
0 0.00 0.00
0 0.00 0.00
00.000.00
00.000.00
00.000.00
00.000.00
00.000.00
00.000.00
0 0.00 0.00
00.000.00
00.000.00
00.000.00
00.000.00
00.000.00
00.000.00
0 0.00 0.00
ALL SPEEDS (1) (2)
25 7.06 .29
13 3.67 .15
5 1.41 .06
12 3.39 .14
257.06.29
143.95.16
185.08.21
226.21.25
215.93.24
3.85.03
10 2.82 .12
82.26.09
205.65.23
287.91.32
3810.73
.44
9225.991.06
00.000.00
354 100.0
4.09
(1) = PERCENT OF ALL GOOD OBSERVATIONS FOR THIS PAGE (2) = PERCENT OF ALL GOOD OBSERVATIONS FOR THIS PERIOD C=CALM (WIND SPEED LESS THAN OR EQUAL TO .60 MPH)
VYNPS DSAR Revision 1 G.2-10 of 40
TABLE G.2.2 35.0 FT WIND DATA STABILITY CLASS C CLASS FREQUENCY (PERCENT) = 4.64 WIND DIRECTION FROM
SPEED (MPH) N NNE NE ENE E ESE SE SSE S SSW SW WSW W WNW NW NNW VRBL TOTAL
CALM (1) (2)
0 0.00 0.00
0 0.00 0.00
0 0.00 0.00
0 0.00 0.00
00.000.00
00.000.00
00.000.00
00.000.00
00.000.00
00.000.00
0 0.00 0.00
00.000.00
00.000.00
00.000.00
00.000.00
00.000.00
00.000.00
0 0.00 0.00
C-3 (1) (2)
5 1.24 .06
5 1.24 .06
2 .50 .02
3 .75 .03
3.75.03
61.49.07
71.74.08
61.49.07
2.50.02
1.25.01
2 .50 .02
3.75.03
1.25.01
00.000.00
51.24.06
41.00.05
00.000.00
55 13.68
.64
4-7 (1) (2)
18 4.48 .21
5 1.24 .06
6 1.49 .07
6 1.49 .07
122.99.14
102.49.12
61.49.07
2.50.02
3.75.03
3.75.03
3 .75 .03
41.00.05
1.25.01
71.74.08
122.99.14
245.97.28
00.000.00
122 30.35 1.41
8-12 (1) (2)
9 2.24 .10
0 0.00 0.00
0 0.00 0.00
0 0.00 0.00
2.50.02
00.000.00
3.75.03
204.98.23
143.48.16
41.00.05
9 2.24 .10
61.49.07
102.49.12
153.73.17
102.49.12
235.72.27
00.000.00
125 31.09 1.44
13-18 (1) (2)
7 1.74 .08
1 .25 .01
0 0.00 0.00
0 0.00 0.00
00.000.00
00.000.00
1.25.01
1.25.01
1.25.01
00.000.00
1 .25 .01
41.00.05
112.74.13
215.22.24
163.98.18
225.47.25
00.000.00
86 21.39
.99
19-24 (1) (2)
0 0.00 0.00
0 0.00 0.00
0 0.00 0.00
0 0.00 0.00
00.000.00
00.000.00
00.000.00
00.000.00
00.000.00
00.000.00
0 0.00 0.00
1.25.01
1.25.01
2.50.02
3.75.03
61.49.07
00.000.00
13 3.23 .15
GT 24 (1) (2)
0 0.00 0.00
0 0.00 0.00
0 0.00 0.00
0 0.00 0.00
00.000.00
00.000.00
00.000.00
00.000.00
00.000.00
00.000.00
0 0.00 0.00
00.000.00
00.000.00
00.000.00
1.25.01
00.000.00
00.000.00
1 .25 .01
ALL SPEEDS (1) (2)
39 9.70 .45
11 2.74 .13
8 1.99 .09
9 2.24 .10
174.23.20
163.98.18
174.23.20
297.21.33
204.98.23
81.99.09
15 3.73 .17
184.48.21
245.97.28
4511.19
.52
4711.69
.54
7919.65
.91
00.000.00
402 100.00
4.64
(1) = PERCENT OF ALL GOOD OBSERVATIONS FOR THIS PAGE (2) = PERCENT OF ALL GOOD OBSERVATIONS FOR THIS PERIOD C=CALM (WIND SPEED LESS THAN OR EQUAL TO .60 MPH)
VYNPS DSAR Revision 1 G.2-11 of 40
TABLE G.2.2
35.0 FT WIND DATA STABILITY CLASS D CLASS FREQUENCY (PERCENT) = 37.14 WIND DIRECTION FROM
SPEED (MPH) N NNE NE ENE E ESE SE SSE S SSW SW WSW W WNW NW NNW VRBL TOTAL
CALM (1) (2)
0 0.00 0.00
0 0.00 0.00
0 0.00 0.00
0 0.00 0.00
00.000.00
00.000.00
00.000.00
00.000.00
00.000.00
00.000.00
0 0.00 0.00
00.000.00
00.000.00
00.000.00
00.000.00
00.000.00
00.000.00
0 0.00 0.00
C-3 (1) (2)
39 1.21 .45
15 .47 .17
22 .68 .25
26 .81 .30
401.24.46
23.72.27
411.27.47
391.21.45
331.03.38
321.00.37
28 .87 .32
421.31.49
24.75.28
421.31.49
521.62.60
601.87.69
00.000.00
558 17.35 6.44
4-7 (1) (2)
106 3.30 1.22
42 1.31 .49
28 .87 .32
20 .62 .23
351.09.40
571.77.66
1013.141.17
1454.511.67
652.02.75
15.47.17
22 .68 .25
28.87.32
441.37.51
541.68.62
1123.481.29
2317.182.67
00.000.00
1105 34.36 12.76
8-12 (1) (2)
74 2.30 .85
16 .50 .18
14 .44 .16
9 .28 .10
12.37.14
25.78.29
21.65.24
922.861.06
802.49.92
16.50.18
20 .62 .23
29.90.33
1304.041.50
1304.041.50
1193.701.37
1705.291.96
00.000.00
957 29.76 11.05
13-18 (1) (2)
34 1.06 .39
1 .03 .01
3 .09 .03
0 0.00 0.00
00.000.00
1.03.01
1.03.01
7.22.08
14.44.16
1.03.01
6 .19 .07
8.25.09
892.771.03
1093.391.26
1073.331.24
1263.921.46
00.000.00
507 15.76 5.86
19-24 (1) (2)
0 0.00 0.00
0 0.00 0.00
0 0.00 0.00
0 0.00 0.00
00.000.00
00.000.00
00.000.00
1.03.01
2.06.02
00.000.00
0 0.00 0.00
3.09.03
12.37.14
13.40.15
28.87.32
24.75.28
00.000.00
83 2.58 .96
GT 24 (1) (2)
0 0.00 0.00
0 0.00 0.00
0 0.00 0.00
0 0.00 0.00
00.000.00
00.000.00
00.000.00
00.000.00
00.000.00
00.000.00
0 0.00 0.00
00.000.00
00.000.00
4.12.05
2.06.02
00.000.00
00.000.00
6 .19 .07
ALL SPEEDS (1) (2)
253 7.87 2.92
74 2.30 .85
67 2.08 .77
55 1.71 .64
872.711.00
1063.301.22
1645.101.89
2848.833.28
1946.032.24
641.99.74
76 2.36 .88
1103.421.27
2999.303.45
35210.954.07
42013.064.85
61119.007.06
00.000.00
3216 100.00 37.14
(1) = PERCENT OF ALL GOOD OBSERVATIONS FOR THIS PAGE (2) = PERCENT OF ALL GOOD OBSERVATIONS FOR THIS PERIOD C=CALM (WIND SPEED LESS THAN OR EQUAL TO .60 MPH)
VYNPS DSAR Revision 1 G.2-12 of 40
TABLE G.2.2
35.0 FT WIND DATA STABILITY CLASS E CLASS FREQUENCY (PERCENT) = 30.70 WIND DIRECTION FROM
SPEED (MPH) N NNE NE ENE E ESE SE SSE S SSW SW WSW W WNW NW NNW VRBL TOTAL
CALM (1) (2)
0 0.00 0.00
0 0.00 0.00
0 0.00 0.00
0 0.00 0.00
00.000.00
00.000.00
00.000.00
00.000.00
00.000.00
00.000.00
0 0.00 0.00
00.000.00
00.000.00
00.000.00
00.000.00
00.000.00
00.000.00
0 0.00 0.00
C-3 (1) (2)
50 1.88 .58
26 .98 .30
30 1.13 .35
22 .83 .25
311.17.36
351.32.40
421.58.49
592.22.68
1043.911.20
1304.891.50
143 5.38 1.65
1224.591.41
1505.641.73
1274.781.47
1324.971.52
993.721.14
00.000.00
1302 48.98 15.04
4-7 (1) (2)
38 1.43 .44
16 .60 .18
1 .04 .01
7 .26 .08
16.60.18
321.20.37
602.26.69
873.271.00
853.20.98
281.05.32
29 1.09 .33
421.58.49
792.97.91
913.421.05
1636.131.88
1666.251.92
00.000.00
940 35.36 10.86
8-12 (1) (2)
16 .60 .18
1 .04 .01
0 0.00 0.00
0 0.00 0.00
2.08.02
6.23.07
18.68.21
371.39.43
391.47.45
3.11.03
5 .19 .06
8.30.09
521.96.60
441.66.51
501.88.58
672.52.77
00.000.00
348 13.09 4.02
13-18 (1) (2)
3 .11 .03
0 0.00 0.00
0 0.00 0.00
0 0.00 0.00
00.000.00
00.000.00
1.04.01
6.23.07
7.26.08
00.000.00
0 0.00 0.00
1.04.01
4.15.05
7.26.08
17.64.20
17.64.20
00.000.00
63 2.37 .73
19-24 (1) (2)
0 0.00 0.00
0 0.00 0.00
0 0.00 0.00
0 0.00 0.00
00.000.00
00.000.00
00.000.00
2.08.02
1.04.01
00.000.00
0 0.00 0.00
00.000.00
1.04.01
00.000.00
1.04.01
00.000.00
00.000.00
5 .19 .06
GT 24 (1) (2)
0 0.00 0.00
0 0.00 0.00
0 0.00 0.00
0 0.00 0.00
00.000.00
00.000.00
00.000.00
00.000.00
00.000.00
00.000.00
0 0.00 0.00
00.000.00
00.000.00
00.000.00
00.000.00
00.000.00
00.000.00
0 0.00 0.00
ALL SPEEDS (1) (2)
107 4.03 1.24
43 1.62 .50
31 1.17 .36
29 1.09 .33
491.84.57
732.75.84
1214.551.40
1917.192.21
2368.882.73
1616.061.86
177 6.66 2.04
1736.512.00
28610.763.30
26910.123.11
36313.664.19
34913.134.03
00.000.00
2658 100.00 30.70
(1) = PERCENT OF ALL GOOD OBSERVATIONS FOR THIS PAGE (2) = PERCENT OF ALL GOOD OBSERVATIONS FOR THIS PERIOD C=CALM (WIND SPEED LESS THAN OR EQUAL TO .60 MPH)
VYNPS DSAR Revision 1 G.2-13 of 40
TABLE G.2.2 35.0 FT WIND DATA STABILITY CLASS F CLASS FREQUENCY (PERCENT) = 13.87 WIND DIRECTION FROM
SPEED (MPH) N NNE NE ENE E ESE SE SSE S SSW SW WSW W WNW NW NNW VRBL TOTAL
CALM (1) (2)
0 0.00 0.00
0 0.00 0.00
0 0.00 0.00
0 0.00 0.00
00.000.00
00.000.00
00.000.00
00.000.00
00.000.00
00.000.00
0 0.00 0.00
00.000.00
00.000.00
00.000.00
00.000.00
00.000.00
00.000.00
0 0.00 0.00
C-3 (1) (2)
14 1.17 .16
10 .83 .12
8 .67 .09
10 .83 .12
10.83.12
9.75.10
181.50.21
433.58.50
514.25.59
1169.661.34
197 16.40 2.28
15713.071.81
1099.081.26
685.66.79
715.91.82
393.25.45
00.000.00
930 77.44 10.74
4-7 (1) (2)
6 .50 .07
0 0.00 0.00
0 0.00 0.00
0 0.00 0.00
4.33.05
3.25.03
3.25.03
8.67.09
151.25.17
181.50.21
38 3.16 .44
322.66.37
191.58.22
201.67.23
473.91.54
373.08.43
00.000.00
250 20.82 2.89
8-12 (1) (2)
0 0.00 0.00
0 0.00 0.00
0 0.00 0.00
0 0.00 0.00
00.000.00
2.17.02
00.000.00
00.000.00
00.000.00
00.000.00
0 0.00 0.00
2.17.02
2.17.02
1.08.01
5.42.06
8.67.09
00.000.00
20 1.67 .23
13-18 (1) (2)
0 0.00 0.00
0 0.00 0.00
0 0.00 0.00
0 0.00 0.00
00.000.00
00.000.00
00.000.00
00.000.00
00.000.00
00.000.00
0 0.00 0.00
1.08.01
00.000.00
00.000.00
00.000.00
00.000.00
00.000.00
1 .08 .01
19-24 (1) (2)
0 0.00 0.00
0 0.00 0.00
0 0.00 0.00
0 0.00 0.00
00.000.00
00.000.00
00.000.00
00.000.00
00.000.00
00.000.00
0 0.00 0.00
00.000.00
00.000.00
00.000.00
00.000.00
00.000.00
00.000.00
0 0.00 0.00
GT 24 (1) (2)
0 0.00 0.00
0 0.00 0.00
0 0.00 0.00
0 0.00 0.00
00.000.00
00.000.00
00.000.00
00.000.00
00.000.00
00.000.00
0 0.00 0.00
00.000.00
00.000.00
00.000.00
00.000.00
00.000.00
00.000.00
0 0.00 0.00
ALL SPEEDS (1) (2)
20 1.67 .23
10 .83 .12
8 .67 .09
10 .83 .12
141.17.16
141.17.16
211.75.24
514.25.59
665.50.76
13411.161.55
235 19.57 2.71
19215.992.22
13010.821.50
897.411.03
12310.241.42
846.99.97
00.000.00
1201 100.00 13.87
(1) = PERCENT OF ALL GOOD OBSERVATIONS FOR THIS PAGE (2) = PERCENT OF ALL GOOD OBSERVATIONS FOR THIS PERIOD C=CALM (WIND SPEED LESS THAN OR EQUAL TO .60 MPH)
VYNPS DSAR Revision 1 G.2-14 of 40
TABLE G.2.2 35.0 FT WIND DATA STABILITY CLASS G CLASS FREQUENCY (PERCENT) = 3.42 WIND DIRECTION FROM
SPEED (MPH) N NNE NE ENE E ESE SE SSE S SSW SW WSW W WNW NW NNW VRBL TOTAL
CALM (1) (2)
0 0.00 0.00
0 0.00 0.00
0 0.00 0.00
0 0.00 0.00
00.000.00
00.000.00
00.000.00
00.000.00
00.000.00
00.000.00
0 0.00 0.00
00.000.00
00.000.00
00.000.00
00.000.00
00.000.00
00.000.00
0 0.00 0.00
C-3 (1) (2)
5 1.69 .06
1 .34 .01
7 2.36 .08
5 1.69 .06
51.69.06
2.68.02
113.72.13
51.69.06
268.78.30
3311.15
.38
39 13.18
.45
258.45.29
268.78.30
217.09.24
124.05.14
134.39.15
00.000.00
236 79.73 2.73
4-7 (1) (2)
1 .34 .01
0 0.00 0.00
0 0.00 0.00
0 0.00 0.00
1.34.01
00.000.00
2.68.02
00.000.00
2.68.02
113.72.13
14 4.73 .16
72.36.08
41.35.05
41.35.05
41.35.05
31.01.03
00.000.00
53 17.91
.61
8-12 (1) (2)
0 0.00 0.00
0 0.00 0.00
0 0.00 0.00
0 0.00 0.00
00.000.00
00.000.00
00.000.00
00.000.00
00.000.00
00.000.00
0 0.00 0.00
00.000.00
00.000.00
00.000.00
2.68.02
51.69.06
00.000.00
7 2.36 .08
13-18 (1) (2)
0 0.00 0.00
0 0.00 0.00
0 0.00 0.00
0 0.00 0.00
00.000.00
00.000.00
00.000.00
00.000.00
00.000.00
00.000.00
0 0.00 0.00
00.000.00
00.000.00
00.000.00
00.000.00
00.000.00
00.000.00
0 0.00 0.00
19-24 (1) (2)
0 0.00 0.00
0 0.00 0.00
0 0.00 0.00
0 0.00 0.00
00.000.00
00.000.00
00.000.00
00.000.00
00.000.00
00.000.00
0 0.00 0.00
00.000.00
00.000.00
00.000.00
00.000.00
00.000.00
00.000.00
0 0.00 0.00
GT 24 (1) (2)
0 0.00 0.00
0 0.00 0.00
0 0.00 0.00
0 0.00 0.00
00.000.00
00.000.00
00.000.00
00.000.00
00.000.00
00.000.00
0 0.00 0.00
00.000.00
00.000.00
00.000.00
00.000.00
00.000.00
00.000.00
0 0.00 0.00
ALL SPEEDS (1) (2)
6 2.03 .07
1 .34 .01
7 2.36 .08
5 1.69 .06
62.03.07
2.68.02
134.39.15
51.69.06
289.46.32
4414.86
.51
53 17.91
.61
3210.81
.37
3010.14
.35
258.45.29
186.08.21
217.09.24
00.000.00
296 100.00
3.42
(1) = PERCENT OF ALL GOOD OBSERVATIONS FOR THIS PAGE (2) = PERCENT OF ALL GOOD OBSERVATIONS FOR THIS PERIOD C=CALM (WIND SPEED LESS THAN OR EQUAL TO .60 MPH)
VYNPS DSAR Revision 1 G.2-15 of 40
TABLE G.2.2 35.0 FT WIND DATA STABILITY CLASS ALL CLASS FREQUENCY (PERCENT) = 100.00 WIND DIRECTION FROM
SPEED (MPH) N NNE NE ENE E ESE SE SSE S SSW SW WSW W WNW NW NNW VRBL TOTAL
CALM (1) (2)
0 0.00 0.00
0 0.00 0.00
0 0.00 0.00
0 0.00 0.00
00.000.00
00.000.00
00.000.00
00.000.00
00.000.00
00.000.00
0 0.00 0.00
00.000.00
00.000.00
00.000.00
00.000.00
00.000.00
00.000.00
0 0.00 0.00
C-3 (1) (2)
115 1.33 1.33
71 .82 .82
77 .89 .89
77 .89 .89
1011.171.17
901.041.04
1331.541.54
1611.861.86
2232.582.58
3143.633.63
412 4.76 4.76
3524.074.07
3123.603.60
2603.003.00
2743.163.16
2212.552.55
00.000.00
3193 36.87 36.87
4-7 (1) (2)
197 2.28 2.28
78 .90 .90
51 .59 .59
60 .69 .69
1151.331.33
2271.471.47
1972.282.28
2713.133.13
1822.102.10
80.92.92
111 1.28 1.28
1161.341.34
1491.721.72
1852.142.14
3674.244.24
5226.036.03
00.000.00
2808 32.43 32.43
8-12 (1) (2)
124 1.43 1.43
20 .23 .23
16 .18 .18
9 .10 .10
22.25.25
38.44.44
58.67.67
2012.322.32
1621.871.87
28.32.32
39 .45 .45
51.59.59
2042.362.36
2052.372.37
2202.542.54
3694.264.26
00.000.00
1766 20.39 20.39
13-18 (1) (2)
50 .58 .58
3 .03 .03
3 .03 .03
0 0.00 0.00
00.000.00
1.01.01
3.03.03
17.20.20
25.29.29
1.01.01
10 .12 .12
16.18.18
1181.361.36
1471.701.70
1631.881.88
2202.542.54
00.000.00
777 8.97 8.97
19-24 (1) (2)
0 0.00 0.00
0 0.00 0.00
0 0.00 0.00
0 0.00 0.00
00.000.00
00.000.00
00.000.00
3.03.03
3.03.03
00.000.00
0 0.00 0.00
4.05.05
16.18.18
17.20.20
33.38.38
32.37.37
00.000.00
108 1.25 1.25
GT 24 (1) (2)
0 0.00 0.00
0 0.00 0.00
0 0.00 0.00
0 0.00 0.00
00.000.00
00.000.00
00.000.00
00.000.00
00.000.00
00.000.00
0 0.00 0.00
00.000.00
00.000.00
4.05.05
3.03.03
00.000.00
00.000.00
7 .08 .08
ALL SPEEDS (1) (2)
486 5.61 5.61
172 1.99 1.99
147 1.70 1.70
146 1.69 1.69
2382.752.75
2562.962.96
3914.524.52
6537.547.54
5956.876.87
4234.894.89
572 6.61 6.61
5396.226.22
7999.239.23
8189.459.45
106012.2412.24
136415.7515.75
00.000.00
8659 100.00 100.00
(1) = PERCENT OF ALL GOOD OBSERVATIONS FOR THIS PAGE (2) = PERCENT OF ALL GOOD OBSERVATIONS FOR THIS PERIOD C=CALM (WIND SPEED LESS THAN OR EQUAL TO .60 MPH)
VYNPS DSAR Revision 1 G.2-16 of 40
TABLE G.2.3
Joint Frequency Distribution of Wind Speed, Wind Direction, and Stability Class (Stability Based on 295-33 Foot Delta-T) 297.0 FT WIND DATA STABILITY CLASS A CLASS FREQUENCY (PERCENT) = .91 WIND DIRECTION FROM
SPEED (MPH) N NNE NE ENE E ESE SE SSE S SSW SW WSW W WNW NW NNW VRBL TOTAL
CALM (1) (2)
0 0.00 0.00
0 0.00 0.00
0 0.00 0.00
0 0.00 0.00
00.000.00
00.000.00
00.000.00
00.000.00
00.000.00
00.000.00
0 0.00 0.00
00.000.00
00.000.00
00.000.00
00.000.00
00.000.00
00.000.00
0 0.00 0.00
C-3 (1) (2)
0 0.00 0.00
0 0.00 0.00
2 2.60 .02
2 2.60 .02
00.000.00
00.000.00
33.90.04
00.000.00
00.000.00
00.000.00
0 0.00 0.00
00.000.00
00.000.00
11.30.01
00.000.00
11.30.01
00.000.00
9 11.69
.11
4-7 (1) (2)
2 2.60 .02
2 2.60 .02
0 0.00 0.00
0 0.00 0.00
11.30.01
11.30.01
00.000.00
00.000.00
00.000.00
00.000.00
0 0.00 0.00
00.000.00
00.000.00
00.000.00
22.60.02
56.49.06
00.000.00
13 16.88
.15
8-12 (1) (2)
1 1.30 .01
0 0.00 0.00
0 0.00 0.00
0 0.00 0.00
00.000.00
45.19.05
11.30.01
1215.58
.14
67.79.07
00.000.00
0 0.00 0.00
00.000.00
00.000.00
00.000.00
11.30.01
1012.99
.12
00.000.00
35 45.45
.41
13-18 (1) (2)
1 1.30 .01
0 0.00 0.00
0 0.00 0.00
0 0.00 0.00
00.000.00
00.000.00
11.30.01
67.79.07
33.90.04
00.000.00
0 0.00 0.00
00.000.00
00.000.00
22.60.02
11.30.01
45.19.05
00.000.00
18 23.38
.21
19-24 (1) (2)
0 0.00 0.00
0 0.00 0.00
0 0.00 0.00
0 0.00 0.00
00.000.00
00.000.00
00.000.00
00.000.00
00.000.00
00.000.00
0 0.00 0.00
00.000.00
00.000.00
00.000.00
00.000.00
22.60.02
00.000.00
2 2.60 .02
GT 24 (1) (2)
0 0.00 0.00
0 0.00 0.00
0 0.00 0.00
0 0.00 0.00
00.000.00
00.000.00
00.000.00
00.000.00
00.000.00
00.000.00
0 0.00 0.00
00.000.00
00.000.00
00.000.00
00.000.00
00.000.00
00.000.00
0 0.00 0.00
ALL SPEEDS (1) (2)
4 5.19 .05
2 2.60 .02
2 2.60 .02
2 2.60 .02
11.30.01
56.49.06
56.49.06
1823.38
.21
911.69
.11
00.000.00
0 0.00 0.00
00.000.00
00.000.00
33.90.04
45.19.05
2228.57
.26
00.000.00
77 100.00
.91
(1) = PERCENT OF ALL GOOD OBSERVATIONS FOR THIS PAGE (2) = PERCENT OF ALL GOOD OBSERVATIONS FOR THIS PERIOD C=CALM (WIND SPEED LESS THAN OR EQUAL TO .60 MPH)
VYNPS DSAR Revision 1 G.2-17 of 40
TABLE G.2.3
297.0 FT WIND DATA STABILITY CLASS B CLASS FREQUENCY (PERCENT) = 2.62 WIND DIRECTION FROM
SPEED (MPH) N NNE NE ENE E ESE SE SSE S SSW SW WSW W WNW NW NNW VRBL TOTAL
CALM (1) (2)
0 0.00 0.00
0 0.00 0.00
0 0.00 0.00
0 0.00 0.00
00.000.00
00.000.00
00.000.00
00.000.00
00.000.00
00.000.00
0 0.00 0.00
00.000.00
00.000.00
00.000.00
00.000.00
00.000.00
00.000.00
0 0.00 0.00
C-3 (1) (2)
1 .45 .01
1 .45 .01
1 .45 .01
2 .90 .02
1.45.01
1.45.01
2.90.02
2.90.02
00.000.00
00.000.00
0 0.00 0.00
00.000.00
00.000.00
1.45.01
00.000.00
00.000.00
00.000.00
12 5.41 .14
4-7 (1) (2)
12 5.41 .14
3 1.35 .04
1 .45 .01
2 .90 .02
83.60.09
83.60.09
41.80.05
2.90.02
1.45.01
00.000.00
0 0.00 0.00
00.000.00
00.000.00
00.000.00
00.000.00
94.05.11
00.000.00
50 22.52
.59
8-12 (1) (2)
8 3.60 .09
0 0.00 0.00
0 0.00 0.00
0 0.00 0.00
00.000.00
62.70.07
52.25.06
114.95.13
125.41.14
2.90.02
0 0.00 0.00
1.45.01
1.45.01
1.45.01
52.25.06
2310.36
.27
00.000.00
75 33.78
.89
13-18 (1) (2)
5 2.25 .06
3 1.35 .04
0 0.00 0.00
0 0.00 0.00
00.000.00
1.45.01
1.45.01
41.80.05
52.25.06
00.000.00
1 .45 .01
00.000.00
62.70.07
2.90.02
83.60.09
3013.51
.35
00.000.00
66 29.73
.78
19-24 (1) (2)
0 0.00 0.00
0 0.00 0.00
0 0.00 0.00
0 0.00 0.00
00.000.00
00.000.00
00.000.00
00.000.00
00.000.00
00.000.00
0 0.00 0.00
00.000.00
00.000.00
1.45.01
4.180.05
125.41.14
00.000.00
17 7.66 .20
GT 24 (1) (2)
0 0.00 0.00
0 0.00 0.00
0 0.00 0.00
0 0.00 0.00
00.000.00
00.000.00
00.000.00
00.000.00
00.000.00
00.000.00
0 0.00 0.00
00.000.00
00.000.00
00.000.00
00.000.00
2.90.02
00.000.00
2 .90 .02
ALL SPEEDS (1) (2)
26 11.71
.31
7 3.15 .08
2 .90 .02
4 1.80 .05
94.05.11
167.21.19
125.41.14
198.56.22
188.11.21
2.90.02
1 .45 .01
1.45.01
73.15.08
52.25.06
177.66.20
7634.23
.90
00.000.00
222 100.00
2.62
(1) = PERCENT OF ALL GOOD OBSERVATIONS FOR THIS PAGE (2) = PERCENT OF ALL GOOD OBSERVATIONS FOR THIS PERIOD C=CALM (WIND SPEED LESS THAN OR EQUAL TO .60 MPH)
VYNPS DSAR Revision 1 G.2-18 of 40
TABLE G.2.3
297.0 FT WIND DATA STABILITY CLASS C CLASS FREQUENCY (PERCENT) = 4.60 WIND DIRECTION FROM
SPEED (MPH) N NNE NE ENE E ESE SE SSE S SSW SW WSW W WNW NW NNW VRBL TOTAL
CALM (1) (2)
0 0.00 0.00
0 0.00 0.00
0 0.00 0.00
0 0.00 0.00
00.000.00
00.000.00
00.000.00
00.000.00
00.000.00
00.000.00
0 0.00 0.00
00.000.00
00.000.00
00.000.00
00.000.00
00.000.00
00.000.00
0 0.00 0.00
C-3 (1) (2)
8 2.05 .09
4 1.03 .05
1 .26 .05
2 .51 .02
3.77.04
41.03.05
41.03.05
41.03.05
00.000.00
1.26.01
0 0.00 0.00
1.26.01
2.51.02
00.000.00
2.51.02
3.77.04
00.000.00
39 10.00
.46
4-7 (1) (2)
13 3.33 .15
4 1.03 .05
6 1.54 .07
3 .77 .04
92.31.11
184.62.21
82.05.09
82.05.09
2.51.02
1.26.01
1 .26 .01
00.000.00
1.26.01
2.51.02
102.56.12
184.62.21
00.000.00
104 26.67 1.23
8-12 (1) (2)
9 2.31 .11
5 1.28 .06
0 0.00 0.00
0 0.00 0.00
1.26.01
51.28.06
41.03.05
215.38.25
41.03.05
41.03.05
0 0.00 0.00
00.000.00
1.26.01
92.31.11
123.08.14
287.18.33
00.000.00
103 26.41 1.22
13-18 (1) (2)
8 2.05 .09
1 .26 .01
0 0.00 0.00
0 0.00 0.00
00.000.00
1.26.01
00.000.00
51.28.06
41.03.05
1.26.01
0 0.00 0.00
1.26.01
82.05.09
112.82.13
92.31.11
379.49.44
00.000.00
86 22.05 1.01
19-24 (1) (2)
2 .51 .02
0 0.00 0.00
0 0.00 0.00
0 0.00 0.00
00.000.00
00.000.00
00.000.00
00.000.00
00.000.00
00.000.00
0 0.00 0.00
00.000.00
3.77.04
51.28.06
82.05.09
266.67.31
00.000.00
44 11.28
.52
GT 24 (1) (2)
2 .51 .02
0 0.00 0.00
0 0.00 0.00
0 0.00 0.00
00.000.00
00.000.00
00.000.00
00.000.00
00.000.00
00.000.00
0 0.00 0.00
00.000.00
1.26.01
1.26.01
2.51.02
82.05.09
00.000.00
14 3.59 .17
ALL SPEEDS (1) (2)
42 10.77
.50
14 3.59 .17
7 1.79 .08
5 1.28 .06
133.33.15
287.18.33
164.10.19
389.74.45
102.56.12
71.79.08
1 .26 .01
2.51.02
164.10.19
287.18.33
4311.03
.51
12030.771.42
00.000.00
390 100.00
4.60
(1) = PERCENT OF ALL GOOD OBSERVATIONS FOR THIS PAGE (2) = PERCENT OF ALL GOOD OBSERVATIONS FOR THIS PERIOD C=CALM (WIND SPEED LESS THAN OR EQUAL TO .60 MPH)
VYNPS DSAR Revision 1 G.2-19 of 40
TABLE G.2.3
297.0 FT WIND DATA STABILITY CLASS D CLASS FREQUENCY (PERCENT) = 43.03 WIND DIRECTION FROM
SPEED (MPH) N NNE NE ENE E ESE SE SSE S SSW SW WSW W WNW NW NNW VRBL TOTAL
CALM (1) (2)
0 0.00 0.00
0 0.00 0.00
0 0.00 0.00
0 0.00 0.00
00.000.00
00.000.00
00.000.00
00.000.00
00.000.00
00.000.00
0 0.00 0.00
00.000.00
00.000.00
00.000.00
00.000.00
00.000.00
00.000.00
0 0.00 0.00
C-3 (1) (2)
34 .93 .40
24 .66 .28
23 .63 .27
26 .71 .31
23.63.27
401.10.47
481.32.57
22.60.26
21.58.25
12.33.14
5 .14 .06
10.27.12
11.30.13
5.14.06
16.44.19
421.15.50
00.000.00
362 9.93 4.27
4-7 (1) (2)
59 1.62 .70
29 .80 .34
21 .58 .25
19 .52 .22
28.77.33
381.04.45
902.471.06
952.611.12
501.37.59
15.41.18
11 .30 .13
4.11.05
12.33.14
20.55.24
481.32.57
1544.221.82
00.000.00
693 19.01 8.18
8-12 (1) (2)
105 2.88 1.24
44 1.21 .52
24 .66 .28
13 .36 .15
15.41.18
18.49.21
411.12.48
1704.662.01
932.551.10
22.60.26
29 .80 .34
32.88.38
812.22.96
1193.261.40
681.87.80
2035.572.40
00.000.00
1077 29.54 12.71
13-18 (1) (2)
82 2.25 .97
11 .30 .13
9 .25 .11
10 .27 .12
8.22.09
12.33.14
8.22.09
36.99.42
802.19.94
14.38.17
17 .47 .20
16.44.19
772.11.91
1925.272.27
1253.431.48
2175.952.56
00.000.00
914 25.07 10.79
19-24 (1) (2)
46 1.26 .54
3 .08 .04
3 .08 .04
0 0.00 0.00
00.000.00
1.03.01
1.03.01
3.08.04
15.41.18
1.03.01
5 .14 .06
3.08.04
26.71.31
992.721.17
972.661.14
1484.061.75
00.000.00
451 12.37 5.32
GT 24 (1) (2)
25 .69 .30
0 0.00 0.00
0 0.00 0.00
0 0.00 0.00
00.000.00
00.000.00
00.000.00
1.03.01
00.000.00
00.000.00
0 0.00 0.00
5.14.06
9.25.11
18.49.21
34.93.40
571.56.67
00.000.00
149 4.09 1.76
ALL SPEEDS (1) (2)
351 9.63 4.14
111 3.04 1.31
80 2.19 .94
68 1.87 .80
742.03.87
1092.991.29
1885.162.22
3278.973.86
2597.103.06
641.76.76
67 1.84 .79
701.92.83
2165.922.55
45312.425.35
38810.644.58
82122.529.69
00.000.00
3646 100.00 43.03
(1) = PERCENT OF ALL GOOD OBSERVATIONS FOR THIS PAGE (2) = PERCENT OF ALL GOOD OBSERVATIONS FOR THIS PERIOD C=CALM (WIND SPEED LESS THAN OR EQUAL TO .60 MPH)
VYNPS DSAR Revision 1 G.2-20 of 40
TABLE G.2.3
297.0 FT WIND DATA STABILITY CLASS E CLASS FREQUENCY (PERCENT) = 34.06 WIND DIRECTION FROM
SPEED (MPH) N NNE NE ENE E ESE SE SSE S SSW SW WSW W WNW NW NNW VRBL TOTAL
CALM (1) (2)
0 0.00 0.00
0 0.00 0.00
0 0.00 0.00
0 0.00 0.00
00.000.00
00.000.00
00.000.00
00.000.00
00.000.00
00.000.00
0 0.00 0.00
00.000.00
00.000.00
00.000.00
00.000.00
00.000.00
00.000.00
0 0.00 0.00
C-3 (1) (2)
88 3.05 1.04
41 1.42 .48
48 1.66 .57
49 1.70 .58
682.36.80
903.121.06
1103.811.30
541.87.64
19.66.22
18.62.21
15 .52 .18
7.24.08
18.62.21
19.66.22
391.35.46
722.49.85
00.000.00
755 26.16 8.91
4-7 (1) (2)
103 3.57 1.22
15 .52 .18
5 .17 .06
16 .55 .19
17.59.20
521.80.61
1314.541.55
1254.331.48
411.42.48
23.80.27
15 .52 .18
17.59.20
25.87.30
371.28.44
772.67.91
2679.253.15
00.000.00
966 33.47 11.40
8-12 (1) (2)
70 2.43 .83
6 .21 .07
0 0.00 0.00
2 .07 .02
7.24.08
14.49.17
411.42.48
873.011.03
702.43.83
15.52.18
15 .52 .18
17.59.20
531.84.63
602.08.71
622.15.73
2588.943.04
00.000.00
777 26.92 9.17
13-18 (1) (2)
31 1.07 .37
4 .14 .05
0 0.00 0.00
0 0.00 0.00
3.10.04
9.31.11
10.35.12
26.90.31
441.52.52
4.14.05
3 .10 .04
3.10.04
26.90.31
441.52.52
301.04.35
752.60.89
00.000.00
312 10.81 3.68
19-24 (1) (2)
4 .14 .05
0 0.00 0.00
0 0.00 0.00
0 0.00 0.00
00.000.00
00.000.00
00.000.00
2.07.02
14.49.17
00.000.00
0 0.00 0.00
00.000.00
4.14.05
7.24.08
9.31.11
22.76.26
00.000.00
62 2.15 .73
GT 24 (1) (2)
1 .03 .01
0 0.00 0.00
0 0.00 0.00
0 0.00 0.00
00.000.00
00.000.00
00.000.00
1.03.01
6.21.07
00.000.00
0 0.00 0.00
00.000.00
1.03.01
1.03.01
1.03.01
3.10.04
00.000.00
14 .49 .17
ALL SPEEDS (1) (2)
297 10.29 3.50
66 2.29 .78
53 1.84 .63
67 2.32 .79
953.291.12
1655.721.95
29210.123.45
29510.223.48
1946.722.29
602.08.71
48 1.66 .57
441.52.52
1274.401.50
1685.821.98
2187.552.57
69724.158.23
00.000.00
2886 100.00 34.06
(1) = PERCENT OF ALL GOOD OBSERVATIONS FOR THIS PAGE (2) = PERCENT OF ALL GOOD OBSERVATIONS FOR THIS PERIOD C=CALM (WIND SPEED LESS THAN OR EQUAL TO .60 MPH)
VYNPS DSAR Revision 1 G.2-21 of 40
TABLE G.2.3
297.0 FT WIND DATA STABILITY CLASS F CLASS FREQUENCY (PERCENT) = 13.03
WIND DIRECTION FROM
SPEED (MPH) N NNE NE ENE E ESE SE SSE S SSW SW WSW W WNW NW NNW VRBL TOTAL
CALM (1) (2)
0 0.00 0.00
0 0.00 0.00
0 0.00 0.00
0 0.00 0.00
00.000.00
00.000.00
00.000.00
00.000.00
00.000.00
00.000.00
0 0.00 0.00
00.000.00
00.000.00
00.000.00
00.000.00
00.000.00
00.000.00
0 0.00 0.00
C-3 (1) (2)
48 4.35 .57
42 3.80 .50
22 1.99 .26
21 1.90 .25
302.72.35
403.62.47
403.62.47
302.72.35
221.99.26
131.18.15
13 1.18 .15
4.36.05
171.54.20
111.00.13
232.08.27
474.26.55
00.000.00
423 38.32 4.99
4-7 (1) (2)
41 3.71 .48
8 .72 .09
2 .18 .02
5 .45 .06
131.18.15
343.08.40
665.98.78
393.53.46
252.26.30
121.09.14
16 1.45 .19
191.72.22
161.45.19
292.63.34
373.35.44
928.331.09
00.000.00
454 41.12 5.36
8-12 (1) (2)
12 1.09 .14
0 0.00 0.00
0 0.00 0.00
0 0.00 0.00
1.09.01
2.18.02
10.91.12
151.36.18
121.09.14
5.45.06
5 .45 .06
6.54.07
221.99.26
111.00.13
292.63.34
756.79.89
00.000.00
205 18.57 2.42
13-18 (1) (2)
1 .09 .01
0 0.00 0.00
0 0.00 0.00
0 0.00 0.00
00.000.00
00.000.00
00.000.00
00.000.00
4.36.05
00.000.00
0 0.00 0.00
00.000.00
2.18.02
4.36.05
00.000.00
8.72.09
00.000.00
19 1.72 .22
19-24 (1) (2)
0 0.00 0.00
0 0.00 0.00
0 0.00 0.00
0 0.00 0.00
00.000.00
00.000.00
00.000.00
00.000.00
00.000.00
00.000.00
0 0.00 0.00
00.000.00
1.09.01
00.000.00
00.000.00
2.18.02
00.000.00
3 .27 .04
GT 24 (1) (2)
0 0.00 0.00
0 0.00 0.00
0 0.00 0.00
0 0.00 0.00
00.000.00
00.000.00
00.000.00
00.000.00
00.000.00
00.000.00
0 0.00 0.00
00.000.00
00.000.00
00.000.00
00.000.00
00.000.00
00.000.00
0 0.00 0.00
ALL SPEEDS (1) (2)
102 9.24 1.20
50 4.53 .59
24 2.17 .28
26 2.36 .31
443.99.52
766.88.90
11610.511.37
847.61.99
635.71.74
302.72.35
34 3.08 .40
292.63.34
585.25.68
554.98.65
898.061.05
22420.292.64
00.000.00
1104 100.00 13.03
(1) = PERCENT OF ALL GOOD OBSERVATIONS FOR THIS PAGE (2) = PERCENT OF ALL GOOD OBSERVATIONS FOR THIS PERIOD C=CALM (WIND SPEED LESS THAN OR EQUAL TO .60 MPH)
VYNPS DSAR Revision 1 G.2-22 of 40
TABLE G.2.3
297.0 FT WIND DATA STABILITY CLASS G CLASS FREQUENCY (PERCENT) = 1.76
WIND DIRECTION FROM
SPEED (MPH) N NNE NE ENE E ESE SE SSE S SSW SW WSW W WNW NW NNW VRBL TOTAL
CALM (1) (2)
0 0.00 0.00
0 0.00 0.00
0 0.00 0.00
0 0.00 0.00
00.000.00
00.000.00
00.000.00
00.000.00
00.000.00
00.000.00
0 0.00 0.00
00.000.00
00.000.00
00.000.00
00.000.00
00.000.00
00.000.00
0 0.00 0.00
C-3 (1) (2)
2 1.34 .02
1 .67 .01
3 2.01 .04
1 .67 .01
1.67.01
42.68.05
21.34.02
32.01.04
42.68.05
32.01.04
3 2.01 .04
00.000.00
21.34.02
21.34.02
1.67.01
21.34.02
00.000.00
34 22.82
.40
4-7 (1) (2)
3 2.01 .04
1 .67 .01
0 0.00 0.00
0 0.00 0.00
00.000.00
21.34.02
74.70.08
53.36.06
74.70.08
32.01.04
3 2.01 .04
85.37.09
64.03.07
85.37.09
128.05.14
106.71.12
00.000.00
75 50.34
.89
8-12 (1) (2)
1 .67 .01
0 0.00 0.00
0 0.00 0.00
0 0.00 0.00
00.000.00
00.000.00
21.34.02
21.34.02
32.01.04
00.000.00
3 2.01 .04
32.01.04
117.38.13
32.01.04
21.34.02
74.70.08
00.000.00
37 24.83
.44
13-18 (1) (2)
0 0.00 0.00
0 0.00 0.00
0 0.00 0.00
0 0.00 0.00
00.000.00
00.000.00
00.000.00
1.67.01
00.000.00
00.000.00
1 .67 .01
00.000.00
00.000.00
00.000.00
00.000.00
1.67.01
00.000.00
3 2.01 .04
19-24 (1) (2)
0 0.00 0.00
0 0.00 0.00
0 0.00 0.00
0 0.00 0.00
00.000.00
00.000.00
00.000.00
00.000.00
00.000.00
00.000.00
0 0.00 0.00
00.000.00
00.000.00
00.000.00
00.000.00
00.000.00
00.000.00
0 0.00 0.00
GT 24 (1) (2)
0 0.00 0.00
0 0.00 0.00
0 0.00 0.00
0 0.00 0.00
00.000.00
00.000.00
00.000.00
00.000.00
00.000.00
00.000.00
0 0.00 0.00
00.000.00
00.000.00
00.000.00
00.000.00
00.000.00
00.000.00
0 0.00 0.00
ALL SPEEDS (1) (2)
6 4.03 .07
2 1.34 .02
3 2.01 .04
1 .67 .01
1.67.01
64.03.07
117.38.13
117.38.13
149.40.17
64.03.07
10 6.71 .12
117.38.13
1912.75
.22
138.72.15
1510.07
.18
2013.42
.24
00.000.00
149 100.00
1.76
(1) = PERCENT OF ALL GOOD OBSERVATIONS FOR THIS PAGE (2) = PERCENT OF ALL GOOD OBSERVATIONS FOR THIS PERIOD C=CALM (WIND SPEED LESS THAN OR EQUAL TO .60 MPH)
VYNPS DSAR Revision 1 G.2-23 of 40
TABLE G.2.3
297.0 FT WIND DATA STABILITY CLASS ALL CLASS FREQUENCY (PERCENT) = 100.00
WIND DIRECTION FROM
SPEED (MPH) N NNE NE ENE E ESE SE SSE S SSW SW WSW W WNW NW NNW VRBL TOTAL
CALM (1) (2)
0 0.00 0.00
0 0.00 0.00
0 0.00 0.00
0 0.00 0.00
00.000.00
00.000.00
00.000.00
00.000.00
00.000.00
00.000.00
0 0.00 0.00
00.000.00
00.000.00
00.000.00
00.000.00
00.000.00
00.000.00
0 0.00 0.00
C-3 (1) (2)
181 2.14 2.14
113 1.33 1.33
100 1.18 1.18
103 1.22 1.22
1261.491.49
1792.112.11
2092.472.47
1151.361.36
66.78.78
47.55.55
36 .42 .42
22.26.26
50.59.59
39.46.46
81.96.96
1671.971.97
00.000.00
1634 19.28 19.28
4-7 (1) (2)
233 2.75 2.75
62 .73 .73
35 .41 .41
45 .53 .53
76.90.90
1531.811.81
3063.613.61
2743.233.23
1261.491.49
54.64.64
46 .54 .54
48.57.57
60.71.71
961.131.13
1862.192.19
5556.556.55
00.000.00
2355 27.79 27.79
8-12 (1) (2)
206 2.43 2.43
55 .65 .65
24 .28 .28
15 .18 .18
24.28.28
49.58.58
1041.231.23
3183.753.75
2002.362.36
48.57.57
52 .61 .61
59.70.70
1691.991.99
2032.402.40
1792.112.11
6047.137.13
00.000.00
2309 27.25 27.25
13-18 (1) (2)
128 1.51 1.51
19 .22 .22
9 .11 .11
10 .12 .12
11.13.13
23.27.27
20.24.24
78.92.92
1401.651.65
19.22.22
22 .26 .26
20.24.24
1191.401.40
2553.013.01
1732.042.04
3724.394.39
00.000.00
1418 16.73 16.73
19-24 (1) (2)
52 .61 .61
3 .04 .04
3 .04 .04
0 0.00 0.00
00.000.00
1.01.01
1.01.01
5.06.06
29.34.34
1.01.01
5 .06 .06
3.04.04
34.40.40
1121.321.32
1181.391.39
2122.502.50
00.000.00
579 6.83 6.83
GT 24 (1) (2)
28 .33 .33
0 0.00 0.00
0 0.00 0.00
0 0.00 0.00
00.000.00
00.000.00
00.000.00
2.02.02
6.07.07
00.000.00
0 0.00 0.00
5.06.06
11.13.13
20.24.24
37.44.44
70.83.83
00.000.00
179 2.11 2.11
ALL SPEEDS (1) (2)
828 9.77 9.77
252 2.97 2.97
171 2.02 2.02
173 2.04 2.04
2372.802.80
4054.784.78
6407.557.55
7929.359.35
5676.696.69
1691.991.99
181 1.90 1.90
1571.851.85
4435.235.23
7258.568.56
7749.139.13
198023.3723.37
00.000.00
8474 100.00 100.00
(1) = PERCENT OF ALL GOOD OBSERVATIONS FOR THIS PAGE (2) = PERCENT OF ALL GOOD OBSERVATIONS FOR THIS PERIOD C=CALM (WIND SPEED LESS THAN OR EQUAL TO .60 MPH)
VYNPS DSAR Revision 1 G.2-24 of 40
TABLE G.2.4
Wind Direction Persistence Summary (35-foot level)
WIND DIRECTION PERSISTENCE SUMMARY = NUMBER OF OBSERVATIONS AND PERCENT PROBABILITY DIRECTION PERSISTENCE (HOURS) DIRECTION 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 GT.24 TOTAL
N 254 73
61 91
18 96
8 99
2 99
1 99
2100
00
00
00
00
00
00
00
00
00
0 0
00
00
00
00
00
00
00
00
346
NNE 120 82
22 97
3 99
1 100
0 0
0 0
00
00
00
00
00
00
00
00
00
00
0 0
00
00
00
00
00
00
00
00
146
NE 113 90
8 96
2 98
1 98
1 99
0 99
1100
00
00
00
00
00
00
00
00
00
0 0
00
00
00
00
00
00
00
00
126
ENE 104 84
17 98
2 99
1 100
0 0
0 0
00
00
00
00
00
00
00
00
00
00
0 0
00
00
00
00
00
00
00
00
124
E 153 80
31 96
6 99
0 99
1 99
1 100
00
00
00
00
00
00
00
00
00
00
0 0
00
00
00
00
00
00
00
00
192
ESE 177 83
25 95
6 98
4 100
0 0
0 0
00
00
00
00
00
00
00
00
00
00
0 0
00
00
00
00
00
00
00
00
212
SE 234 78
43 93
15 98
5 99
2 100
0 0
00
00
00
00
00
00
00
00
00
00
0 0
00
00
00
00
00
00
00
00
299
SSE 273 67
83 87
26 94
9 96
6 97
5 99
5100
0100
0100
1100
00
00
00
00
00
00
0 0
00
00
00
00
00
00
00
00
408
S 340 79
46 90
19 95
10 97
7 99
4 100
0100
0100
2100
00
00
00
00
00
00
00
0 0
00
00
00
00
00
00
00
00
428
SSW 304 84
47 97
6 99
3 100
0 0
0 0
00
00
00
00
00
00
00
00
00
00
0 0
00
00
00
00
00
00
00
00
360
SW 347 78
75 95
14 98
4 99
1 100
1 100
0100
1100
00
00
00
00
00
00
00
00
0 0
00
00
00
00
00
00
00
00
443
WSW 357 82
68 97
9 99
2 100
1 100
1 100
00
00
00
00
00
00
00
00
00
00
0 0
00
00
00
00
00
00
00
00
438
W 439 76
94 92
26 97
12 99
3 99
1 99
3100
0100
1100
00
00
00
00
00
00
00
0 0
00
00
00
00
00
00
00
00
579
WNW 443 75
108 93
16 96
18 99
4 94
2 100
1100
1100
00
00
00
00
00
00
00
00
0 0
00
00
00
00
00
00
00
00
593
NW 500 71
121 89
39 94
21 97
12 99
2 99
294
099
2100
1100
0100
0100
0100
0100
1100
00
0 0
00
00
00
00
00
00
00
00
701
NNW 384 57
133 77
67 87
27 91
17 94
18 97
497
398
298
799
199
199
199
1100
2100
1100
0 0
00
00
00
00
00
00
00
00
669
TOTAL 4542 982 274 126 57 36 18 5 7 9 1 1 1 1 3 1 0 0 0 0 0 0 0 0 0 6064
VYNPS DSAR Revision 1 G.2-25 of 40
TABLE G.2.5
Wind Direction Persistence Summary
(297-foot level)
WIND DIRECTION PERSISTENCE SUMMARY = NUMBER OF OBSERVATIONS AND PERCENT PROBABILITY
DIRECTION PERSISTENCE (HOURS) DIRECTION 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 GT.24 TOTAL
N 351 69
85 86
33 93
13 95
12 97
5 98
499
199
1100
0100
0100
0100
1100
0100
0100
1100
0 0
00
00
00
00
00
00
00
00
507
NNE 169 83
25 95
8 99
0 99
1 100
1 100
00
00
00
00
00
00
00
00
00
00
0 0
00
00
00
00
00
00
00
00
204
NE 109 82
16 94
6 98
1 99
0 99
0 99
099
1100
00
00
00
00
00
00
00
00
0 0
00
00
00
00
00
00
00
00
133
ENE 134 88
16 99
0 99
1 99
1 100
0 0
00
00
00
00
00
00
00
00
00
00
0 0
00
00
00
00
00
00
00
00
152
E 160 83
24 96
3 97
4 99
1 100
0 0
00
00
00
00
00
00
00
00
00
00
0 0
00
00
00
00
00
00
00
00
192
ESE 264 81
52 97
5 98
3 99
2 100
1 100
00
00
00
00
00
00
00
00
00
00
0 0
00
00
00
00
00
00
00
00
327
SE 317 72
79 89
31 96
6 98
7 99
1 100
1100
0100
1100
00
00
00
00
00
00
00
0 0
00
00
00
00
00
00
00
00
443
SSE 301 66
74 83
33 99
19 94
7 96
10 98
499
399
2100
0100
0100
0100
1100
00
00
00
0 0
00
00
00
00
00
00
00
00
454
S 205 65
60 84
17 89
13 93
10 96
2 97
498
299
199
199
1100
0100
1100
00
00
00
0 0
00
00
00
00
00
00
00
00
317
SSW 140 91
12 99
1 99
1 100
0 0
0 0
00
00
00
00
00
00
00
00
00
00
0 0
00
00
00
00
00
00
00
00
154
SW 119 85
17 97
4 100
0 0
0 0
0 0
00
00
00
00
00
00
00
00
00
00
0 0
00
00
00
00
00
00
00
00
140
WSW 98 80
19 95
3 98
2 99
0 99
1 100
00
00
00
00
00
00
00
00
00
00
0 0
00
00
00
00
00
00
00
00
123
W 220 73
49 89
20 96
6 98
2 98
2 99
3100
00
00
00
00
00
00
00
00
00
0 0
00
00
00
00
00
00
00
00
302
WNW 246 62
79 82
31 89
24 95
7 97
3 98
098
298
399
199
099
1100
0100
0100
0100
0100
1 100
00
00
00
00
00
00
00
00
398
NW 336 69
81 86
33 93
14 96
10 98
2 98
6100
0100
1100
0100
0100
0100
0100
1100
00
00
0 0
00
00
00
00
00
00
00
00
484
NNW 336 47
147 68
77 78
38 84
35 89
21 91
1093
1094
795
997
597
698
398
499
099
099
1 99
099
299
099
1100
0100
0100
0100
3*100
715
TOTAL 3505 835 305 145 95 49 32 19 16 11 6 7 6 5 0 1 2 0 2 0 1 0 0 0 3 5045
* Of these three occurrences, one lasted 26 hours, the second lasted 34 hours, and the third lasted 36 hours.
TABLE G.2.6 Inversion Persistence Summary (198-33 foot Delta-T)
THE LONGEST INVERSION LASTED 38 HOURS OF THE LONGEST INVERSIONS, NUMBER 1 STARTED 18 HOURS INTO DAY 327 THIRD COLUMN DEFINES THE PERCENT PROBABILITY THAT IF AN INVERSION OCCURS, ITS DURATION WILL BE LESS THAN THE NUMBER OF HOURS SPECIFIED
VYNPS DSAR Revision 1 G.2-26 of 40
Duration (hours)
Number of Observations
Percent Probability
1 146 27.39
2 60 38.65
3 49 47.84
4 34 54.22
5 31 60.04
6 22 64.17
7 26 69.04
8 20 72.80
9 20 76.55
10 27 81.61
11 24 86.12
12 26 90.99
13 21 94.93
14 12 97.19
15 4 97.94
16 3 98.50
17 2 98.87
18 1 99.06
19 1 99.25
20 2 99.62
21 0 99.62
22 0 99.62
23 1 99.81
24 0 99.81
25 0 99.81
26 0 99.81
TABLE G.2.6 Inversion Persistence Summary (198-33 foot Delta-T)
THE LONGEST INVERSION LASTED 38 HOURS OF THE LONGEST INVERSIONS, NUMBER 1 STARTED 18 HOURS INTO DAY 327 THIRD COLUMN DEFINES THE PERCENT PROBABILITY THAT IF AN INVERSION OCCURS, ITS DURATION WILL BE LESS THAN THE NUMBER OF HOURS SPECIFIED
VYNPS DSAR Revision 1 G.2-27 of 40
Duration (hours)
Number of Observations
Percent Probability
27 0 99.81
28 0 99.81
29 0 99.81
30 0 99.81
31 0 99.81
32 0 99.81
33 0 99.81
34 0 99.81
35 0 99.81
36 0 99.81
37 0 99.81
38 1 100.00
THE LONGEST INVERSION LASTED 38 HOURS OF THE LONGEST INVERSIONS, NUMBER 1 STARTED 18 HOURS INTO DAY 327 THIRD COLUMN DEFINES THE PERCENT PROBABILITY THAT IF AN INVERSION OCCURS, ITS DURATION WILL BE LESS THAN THE NUMBER OF HOURS SPECIFIED
VYNPS DSAR Revision 1 G.2-28 of 40
TABLE G.2.7 Inversion Persistence Summary (295-33 foot Delta-T)
Duration (hours)
Number of Observations
Percent Probability
1 140 27.94
2 50 37.92
3 49 47.70
4 25 52.69
5 27 58.08
6 19 61.88
7 31 68.06
8 18 71.66
9 17 75.05
10 23 79.64
11 25 84.63
12 29 90.42
13 15 93.41
14 15 96.41
15 4 97.21
16 2 97.60
17 3 98.20
18 4 99.00
19 1 99.20
20 1 99.40
21 0 99.40
22 0 99.40
23 1 99.60
24 0 99.60
25 1 99.80
26 0 99.80
27 0 99.80
THE LONGEST INVERSION LASTED 38 HOURS OF THE LONGEST INVERSIONS, NUMBER 1 STARTED 18 HOURS INTO DAY 327 THIRD COLUMN DEFINES THE PERCENT PROBABILITY THAT IF AN INVERSION OCCURS, ITS DURATION WILL BE LESS THAN THE NUMBER OF HOURS SPECIFIED
VYNPS DSAR Revision 1 G.2-29 of 40
TABLE G.2.7 (Continue)
Inversion Persistence Summary (295-33 foot Delta-T)
Duration (hours)
Number of Observations
Percent Probability
28 0 99.80
29 0 99.80
30 0 99.80
31 0 99.80
32 0 99.80
33 0 99.80
34 0 99.80
35 0 99.80
36 0 99.80
37 0 99.80
38 1 100.00
VYNPS DSAR Revision 1 G.2-30 of 40
Vermont Yankee
Defueled Safety Analysis Report
Location of Primary and Backup Meteorological Towers
Figure G.2-1
VYNPS DSAR Revision 1 G.2-31 of 40
Vermont Yankee
Defueled Safety Analysis Report
Spring Wind Rose (35-Foot Level)
March 1980 – May 1980 Figure G.2-2
VYNPS DSAR Revision 1 G.2-32 of 40
Vermont Yankee
Defueled Safety Analysis Report
Summer Wind Rose (35-Foot Level)
June 1980 – August 1980 Figure G.2-3
VYNPS DSAR Revision 1 G.2-33 of 40
Vermont Yankee
Defueled Safety Analysis Report
Autumn Wind Rose (35-Foot Level)
September 1980 – November 1980 Figure G.2-4
VYNPS DSAR Revision 1 G.2-34 of 40
Vermont Yankee
Defueled Safety Analysis Report
Winter Wind Rose (35-Foot Level)
January 1980 – February 1980; December 1980 Figure G.2-5
VYNPS DSAR Revision 1 G.2-35 of 40
Vermont Yankee
Defueled Safety Analysis Report
Annual Wind Rose (35-Foot Level)
January 1980 – December 1980 Figure G.2-6
VYNPS DSAR Revision 1 G.2-36 of 40
Vermont Yankee
Defueled Safety Analysis Report
Spring Wind Rose (297-Foot Level)
March 1980 – May 1980 Figure G.2-7
VYNPS DSAR Revision 1 G.2-37 of 40
Vermont Yankee
Defueled Safety Analysis Report
Summer Wind Rose (297-Foot Level)
June 1980 – August 1980 Figure G.2-8
VYNPS DSAR Revision 1 G.2-38 of 40
Vermont Yankee
Defueled Safety Analysis Report
Autumn Wind Rose (297-Foot Level)
September 1980 – November 1980 Figure G.2-9
VYNPS DSAR Revision 1 G.2-39 of 40
Vermont Yankee
Defueled Safety Analysis Report
Winter Wind Rose (297-Foot Level)
January 1980 – February 1980; December 1980 Figure G.2-10