Town Investment Plan – Thudiyalur - Tamil Nadu Government

190

Transcript of Town Investment Plan – Thudiyalur - Tamil Nadu Government

Town Investment Plan – Thudiyalur

TNUIFSL

T

N

U

D

P

III

I

Final

Report

Disclaimer…

The contents of this report are based primarily on discussions with Thudiyalur

Town Panchayat and information, secondary data /Reports available with the

Town Panchayat including our discussions with the Stakeholders of the Town.

Based on the available data and information provided to us, M/s Darashaw &

Company Pvt. Ltd has prepared the Final report.

Town Investment Plan – Thudiyalur

TNUIFSL

T

N

U

D

P

III

II

Final

Report

Table of Contents…

1 Project Background .................................................................................................................. 1-1

1.1 Project Objectives............................................................................................................ 1-1

1.2 Scope of work .................................................................................................................. 1-2

1.3 Methodology Adopted .................................................................................................... 1-3

1.3.1 Database identification........................................................................................... 1-5

1.4 Detailed approach and methodology.............................................................................. 1-6

1.4.1 Inception stage report............................................................................................. 1-6

1.4.2 Draft Final Stage .................................................................................................... 1-8

1.4.3 Final Stage .............................................................................................................. 1-9

2 Town Profile ............................................................................................................................. 2-1

2.1 Regional setting and network linkages .......................................................................... 2-1

2.2 Demography..................................................................................................................... 2-3

2.2.1 Population projections............................................................................................ 2-4

2.3 Social Characteristics ...................................................................................................... 2-5

2.3.1 Social Composition ................................................................................................ 2-5

2.3.2 Gender Ratio........................................................................................................... 2-5

2.3.3 Literacy levels......................................................................................................... 2-6

2.4 Physical characteristics ................................................................................................... 2-6

2.4.1 Geology and Soil Type .......................................................................................... 2-6

2.4.2 Climate and Rainfall .............................................................................................. 2-6

3 Economic Development ........................................................................................................... 3-1

3.1 Economic Base of the town ............................................................................................ 3-1

3.2 Occupational Pattern ....................................................................................................... 3-1

Town Investment Plan – Thudiyalur

TNUIFSL

T

N

U

D

P

III

III

Final

Report

3.3 Industries .......................................................................................................................... 3-2

3.4 Tourism potential............................................................................................................. 3-2

3.4.1 Ooty......................................................................................................................... 3-2

3.4.2 Marudha malai........................................................................................................ 3-3

3.4.3 Esha yoga centre..................................................................................................... 3-3

3.4.4 Other important tourist destinations...................................................................... 3-3

4 PHYSICAL INFRASTRUCTURE ......................................................................................... 4-1

4.1 Water Supply ................................................................................................................... 4-1

4.1.1 Water Supply Sources ............................................................................................ 4-1

4.1.2 Water Supply System............................................................................................. 4-1

4.1.3 Water Availability .................................................................................................. 4-2

4.1.4 Service Adequacy................................................................................................... 4-3

4.1.5 Pillur Water Supply scheme – JNNURM............................................................. 4-3

4.1.6 Sectoral issues......................................................................................................... 4-3

4.1.7 Water Supply Demand Assessment ...................................................................... 4-3

4.2 Sewerage and Sanitation ................................................................................................. 4-4

4.2.1 Sewerage system in Thudiyalur............................................................................. 4-4

4.2.2 Sewerage and sanitation demand assessment....................................................... 4-5

4.3 Storm Water Drainage..................................................................................................... 4-6

4.3.1 Service adequacy.................................................................................................... 4-6

4.3.2 Sectoral issues......................................................................................................... 4-6

4.3.3 Storm Water drainage demand assessment........................................................... 4-6

4.4 Solid Waste Management ............................................................................................... 4-7

4.4.1 Generation and Collection ..................................................................................... 4-7

4.4.2 Disposal and treatment Facilities .......................................................................... 4-7

4.4.3 Adequacy of services ............................................................................................. 4-9

Town Investment Plan – Thudiyalur

TNUIFSL

T

N

U

D

P

III

IV

Final

Report

4.4.4 Sectoral issues......................................................................................................... 4-9

4.4.5 Solid Waste management demand assessment................................................... 4-10

4.5 Roads, Traffic and Transportation................................................................................ 4-10

4.5.1 Regional Network................................................................................................. 4-10

4.5.2 City level Road Network ..................................................................................... 4-11

4.5.3 Public Transport System...................................................................................... 4-12

4.5.4 Sectoral issues....................................................................................................... 4-12

4.5.5 Road network demand assessment...................................................................... 4-12

4.6 Street Lighting ............................................................................................................... 4-13

4.6.1 Adequacy of services ........................................................................................... 4-13

4.6.2 Sectoral issues....................................................................................................... 4-13

4.6.3 Street lighting demand assessment...................................................................... 4-13

4.7 Demand Assessment regarding Model town proposals. ............................................. 4-14

5 Socio-Economic Infrastructure................................................................................................ 5-1

5.1 Health ............................................................................................................................... 5-1

5.2 Education ......................................................................................................................... 5-1

5.3 Recreation ........................................................................................................................ 5-1

5.4 Other Amenities............................................................................................................... 5-3

5.5 Problems and Issues ........................................................................................................ 5-4

6 Slums and Urban Poverty ........................................................................................................ 6-1

6.1 Slums in Thudiyalur ........................................................................................................ 6-1

6.2 Urban poor in Thudiyalur ............................................................................................... 6-2

7 Fiscal status............................................................................................................................... 7-1

7.1 Background...................................................................................................................... 7-1

7.2 Financials ......................................................................................................................... 7-3

7.3 Analysis of Income.......................................................................................................... 7-5

Town Investment Plan – Thudiyalur

TNUIFSL

T

N

U

D

P

III

V

Final

Report

7.3.1 Own Sources........................................................................................................... 7-6

7.3.2 External Sources ..................................................................................................... 7-8

7.4 Analysis of Expenditure.................................................................................................. 7-8

7.5 Source & Use of Funds ................................................................................................. 7-11

7.6 Demand, Collection and Balance ................................................................................. 7-13

7.7 Outstanding Loan and Non-Debt Liability .................................................................. 7-15

8 Institutional capacity assessment............................................................................................. 8-1

8.1 Staff Strength................................................................................................................... 8-1

8.2 Institutional Strengthening & Capacity Building.......................................................... 8-1

9 S W O T .................................................................................................................................... 9-1

10 Stakeholders Consultation................................................................................................. 10-1

10.1 Operational Working Group ......................................................................................... 10-1

10.2 Priority based on OWG opinion survey....................................................................... 10-7

10.2.1 Physical infrastructure priority ............................................................................ 10-7

10.2.2 Social infrastructure priority................................................................................ 10-8

10.2.3 ENVIRONMENTAL ISSUES ............................................................................ 10-9

11 Asset management plan..................................................................................................... 11-1

11.1 List of Assets: ................................................................................................................ 11-2

11.2 Operations and Maintenance ........................................................................................ 11-4

11.2.1 O&M of social infrastructure assets.................................................................... 11-4

11.2.2 O&M Physical Infrastructure .............................................................................. 11-6

11.3 AMP - Recommendations............................................................................................. 11-8

11.3.1 Asset Register ....................................................................................................... 11-8

11.3.2 Asset Value and Life Cycle Management .......................................................... 11-8

11.3.3 Sustainability ........................................................................................................ 11-9

11.3.4 Integration of Technical and Financial Plans ..................................................... 11-9

Town Investment Plan – Thudiyalur

TNUIFSL

T

N

U

D

P

III

VI

Final

Report

11.3.5 Condition Assessment Survey (CAS) ................................................................. 11-9

11.3.6 Risk Assessment ................................................................................................. 11-10

11.3.7 Monitoring and Evaluation ................................................................................ 11-10

11.3.8 Budgeting............................................................................................................ 11-10

11.3.9 Training in Database management.................................................................... 11-10

12 Consolidated issues............................................................................................................ 12-1

13 Strategic planning .............................................................................................................. 13-1

13.1 Action plan for sectoral development .......................................................................... 13-1

14 Capital Investment Plan..................................................................................................... 14-1

14.1 Physical Infrastructure .................................................................................................. 14-2

14.1.1 Water Supply ........................................................................................................ 14-3

14.1.2 Sewerage and Sanitation...................................................................................... 14-4

14.1.3 Storm Water Drainage ......................................................................................... 14-5

14.1.4 Solid Waste Management .................................................................................... 14-6

14.1.5 Roads, Traffic and Transportation ...................................................................... 14-8

14.1.6 Street Lighting ...................................................................................................... 14-9

14.2 Socio-economic Infrastructure ................................................................................... 14-11

14.3 Consolidated Capital Investment Plan ....................................................................... 14-13

14.3.1 First Phase Investment Plan (2009-10 to 2013 – 14) ....................................... 14-13

14.3.2 Second Phase Investment Plan (2014-15 to 2018 – 19) .................................. 14-15

14.3.3 Third Phase Investment Plan (2019-20 to 2023-24) ........................................ 14-17

15 Reforms and Resource mobilization ......................................................................................... 15-1

15.1 Overview ............................................................................................................................. 15-1

15.2 Reform measures for Thudiyalur Town Panchayat .......................................................... 15-2

15.2.1 Financial & Accounting reforms................................................................................ 15-2

15.2.2 Institutional Reforms .................................................................................................. 15-7

Town Investment Plan – Thudiyalur

TNUIFSL

T

N

U

D

P

III

VII

Final

Report

15.2.3 Reforms in Physical Infrastructure .......................................................................... 15-11

15.3 Additional Resource Mobilization................................................................................... 15-16

16 Financial Operating Plan............................................................................................................ 16-1

16.1 Background- need for an FOP ........................................................................................... 16-1

16.2 Financial Sustainability ...................................................................................................... 16-2

16.2.1 Base Case Scenario ..................................................................................................... 16-3

16.2.2 Full project Scenario BAsed on Prudent Funding Norms ........................................ 16-3

16.3 Assumptions for FOP ......................................................................................................... 16-4

16.3.1 Revenue Income.......................................................................................................... 16-4

16.3.2 Revenue Expenditure.................................................................................................. 16-9

16.3.3 Funding Mechanism.................................................................................................. 16-10

16.4 Outcome of Financial Operating Plan ............................................................................. 16-11

16.4.1 Base Case Scenario (“Business as Usual Scenario”).............................................. 16-11

16.4.2 Full Project Scenario with suggested Reforms ....................................................... 16-13

Town Investment Plan – Thudiyalur

TNUIFSL

T

N

U

D

P

III

VIII

Final

Report

List of Tables…

Table 2-A : Population growth trends in Thudiyalur ...................................................................................... 2-3

Table 2-B Ward wise Population details .......................................................................................................... 2-3

Table 2-C : Population projections by various methods ................................................................................. 2-4

Table 2-D Social Composition .......................................................................................................................... 2-5

Table 2-E Gender Ratio ..................................................................................................................................... 2-5

Table 2-F Literacy levels ................................................................................................................................... 2-6

Table 3-A Occupational Pattern and its comparison – 2001.......................................................................... 3-1

Table 4-A Water Supply system in Thudiyalur ................................................................................................. 4-2

Table 4-B : Performance Indicators for water supply in Thudiyalur............................................................. 4-3

Table 4-C : Demand Assessment for the next fifteen year period ................................................................... 4-4

Table 4-D : Public Toilets in Thudiyalur Town Panchayat ............................................................................ 4-5

Table 4-E : Demand Assessment for the next fifteen year period ................................................................... 4-5

Table 4-F : Performance indicators for Storm Water Drainage in Thudiyalur ............................................ 4-6

Table 4-G : Demand Assessment for the next fifteen year period................................................................... 4-7

Table 4-H Waste Composition .......................................................................................................................... 4-7

Table 4-I : Performance Indicators for Solid Waste Management................................................................. 4-9

Table 4-J : Demand Assessment for the next fifteen year period.................................................................. 4-10

Table 4-K: Road network in Thudiyalur......................................................................................................... 4-11

Table 4-L : Demand Assessment for the next fifteen year period ................................................................. 4-12

Table 4-M : Performance Indicators for Street lighting in Thudiyalur........................................................ 4-13

Table 4-N : Demand Assessment for the next fifteen year period ................................................................. 4-13

Table 5-A : Approved layouts in Thudiyalur Town Panchayat....................................................................... 5-1

Table 5-B : Burial grounds in Thudiyalur Town Panchayat........................................................................... 5-3

Table 5-C : Issues related to Socio-Economic Infrastructure......................................................................... 5-4

Table 6-A Slums in Thudiyalur.......................................................................................................................... 6-1

Town Investment Plan – Thudiyalur

TNUIFSL

T

N

U

D

P

III

IX

Final

Report

Table 6-B Ward wise BPL households in Thudiyalur...................................................................................... 6-2

Table 7-A Income & Expenditure Account Rs. in lakhs ........ 7-3

Table 7-B : Income Analysis ............................................................................................................................. 7-5

Table 7-C Property Tax Particulars................................................................................................................... 7-6

Table 7-D Property Tax (Number of Assessment) ........................................................................................... 7-6

Table 7-E Profession Tax Particulars................................................................................................................ 7-7

Table 7-F : Expenditure Analysis...................................................................................................................... 7-9

Table 7-G Balance Sheet ................................................................................................................................. 7-11

Table 7-H: Fixed Assets .................................................................................................................................. 7-12

Table 7-I: DCB for the Past 5 years Rs. In Lakhs. .................................................. 7-13

Table 7-J : Collection Efficiency (%) ............................................................................................................. 7-15

Table 7-K : Outstanding Loan and Non-Debt Liability Rs. in Lakhs ................................................... 7-15

Table 8-A : The Staff strength of the Thudiyalur Town Panchayat................................................................ 8-1

Table 10-A: Suggestions and projects ........................................................................................................... 10-3

Table 11-A: Details of various social & physical infrastructure assets ....................................................... 11-3

Table 11-B: O&M and Revenue generation................................................................................................... 11-4

Table 11-C Past Growth trends in O & M expenses relating to key physical infrastructure ..................... 11-7

Table 11-D O&M rates as a % of proposed capital works ........................................................................... 11-7

Table 12-A : Consolidated Issues.................................................................................................................... 12-1

Table 14-A : Consolidated Sector wise Capital Investment requirements ................................................... 14-1

Table 14-B : Project List and Budget Estimates for Water Supply Works ................................................... 14-3

Table 14-C : Goals and Service outcomes related to Water Supply sector ................................................. 14-4

Table 14-D : Project List and Budget Estimates for Sewerage and Sanitation Works ............................... 14-4

Table 14-E : Project List and Budget Estimates for Storm Water Drainage works .................................... 14-5

Table 14-F : Goals and Service outcomes related to Storm Water Drainage sector .................................. 14-6

Table 14-G : Project List and Budget Estimates for Soild Waste Management works ............................... 14-7

Table 14-H : Goals and Service outcomes related to Solid Waste Management works ............................. 14-7

Table 14-I : Project List and Budget Estimates for Roads, Traffic and Transportation works.................. 14-8

Town Investment Plan – Thudiyalur

TNUIFSL

T

N

U

D

P

III

X

Final

Report

Table 14-J : Goals and Service outcomes related to Roads, Traffic and Transportation sector................ 14-9

Table 14-K : Project List and Budget Estimates for Street lighting works ................................................ 14-10

Table 14-L : Goals and Service outcomes related to Street lighting sector............................................... 14-10

Table 14-M : Project List and Budget Estimates for Socio-Economic Infrastructure works ................... 14-11

Table 14-N First Phase Capital Investment Plan for Thudiyalur Town Panchayat................................. 14-13

Table 14-O First Phase Capital Investment Plan for Thudiyalur Town Panchayat (after considering

escalation cost)............................................................................................................................................... 14-14

Table 14-P Second Phase Capital Investment Plan for Thudiyalur Town Panchayat .............................. 14-15

Table 14-Q Second Phase Capital Investment Plan for Thudiyalur Town Panchayat (after considering

escalation cost)............................................................................................................................................... 14-16

Table 14-R Third Phase Capital Investment Plan for Thudiyalur Town Panchayat................................. 14-17

Table 14-S Third Phase Capital Investment Plan for Thudiyalur Town Panchayat (after considering

escalation cost)............................................................................................................................................... 14-18

Table 15-A: Collection Efficiency of key revenue sources ............................................................................ 15-3

Table 15-B: Efficiency parameters of key taxes and water charges .......................................................... 15-3

Table 15-C: Reforms in property Taxes ......................................................................................................... 15-4

Table 15-D: Accounting Reforms.................................................................................................................... 15-6

Table 15-E: Possible areas of privatization/outsourcing.............................................................................. 15-9

Table 15-F: Reforms in Physical Infrastructure .......................................................................................... 15-11

Table 16-A : Key assumptions for forecasting income from Property Taxes............................................... 16-5

Table 16-B: Key assumptions for forecasting income from Water Charges................................................ 16-5

Table 16-C: Assumption for Income .............................................................................................................. 16-8

Table 16-D: Assumption for Revenue Expenditure........................................................................................ 16-9

Table 16-E: Key assumptions for forecasting future debt obligations ....................................................... 16-10

Table 16-F: Financing Pattern for Proposed projects as per prudent Funding norms ............................ 16-10

Table 16-G : Financial Operating Plan of Thudiyalur- Base Case Scenario.............................................. 16-12

Table 16-H: Full Project Cash Flow - As per Prudent Financial norms..................................................... 16-14

Table 16-I: Financial Operating Plan of Thudiyalur - Full Project with Reforms-Prudent Funding Norms16-15

Town Investment Plan – Thudiyalur

TNUIFSL

T

N

U

D

P

III

XI

Final

Report

Table 16-J: Calculation of Debt Service Coverage Ratio (DSCR) With FULL PROJECT WITH

REFORMS- As per Prudent Financial Norms ............................................................................................. 16-15

Table 16-K: Sector wise Investments. .......................................................................................................... 16-16

Table 16-L Funding Pattern........................................................................................................................... 16-17

Town Investment Plan – Thudiyalur

TNUIFSL

T

N

U

D

P

III

XII

Final

Report

List of Figures…

Figure 1-1 Approach and Methodology for Town Investment Plan .............................................. 1-4

Figure 1-2 Approach and Methodology for Inception stage........................................................... 1-7

Figure 2-1 Regional Setting and Network Linkages ....................................................................... 2-2

Figure 4-1 : Regional Network Linkages....................................................................................... 4-10

Figure 7-1 Income & Expenditure Account..................................................................................... 7-3

Figure 7-2: Break up of Income for the year 2007-08 .................................................................... 7-5

Figure 7-3 Break up of for the year 2007-08 .................................................................................. 7-9

Figure 7-4 : Source of Funds as on 2007-08.................................................................................. 7-12

Figure 7-5 Use of Funds as on 2007-08 ......................................................................................... 7-13

Figure 10-1 : First Formal Meeting on 24h July 2009................................................................... 10-2

Figure 10-2 Sector prioritization by the Stakeholders (Physical Infrastructure) ......................... 10-8

Figure 10-3 Sector prioritization by the Stakeholders (Social Infrastructure)............................. 10-9

Figure 10-4 Sector prioritization by the Stakeholders (Environmental Issues)......................... 10-10

Figure 10-5 Consultation in Thudiyalur Town Panchayat.......................................................... 10-10

Figure 14-1 Sector wise percentage share...................................................................................... 14-2

Town Investment Plan – Thudiyalur

TNUIFSL

T

N

U

D

P

III

XIII

Final

Report

Annexure……

Annexure I Population projection

Annexure II Norms Vs Current Status

Annexure III Town Map

Annexure IV Project Implementation Schedule

Annexure V Reforms Implementation Schedule

Annexure VI Minutes of the Review Committee Meeting on Inception & Draft

Final Report

Annexure VII List of Approved Layout

Annexure VIII OWG attendees list

Annexure IX Council Resoultion

Town Investment Plan – Thudiyalur

TNUIFSL

T

N

U

D

P

III

XIV

Final

Report

Acronyms…

AMP : Asset Management Plan

BE : Budget estimates

BPL : Below Poverty Line

BOT : Build-Operate-Transfer

BOOT : Build-Own-Operate-Transfer

BOLT : Build-Own-Lease-Transfer

BT : Bitumen

CAGR : Compounded Annual Growth Rate

CC : Cement Concrete

CIP : Capital investment Plan

CMA : Commissionerate of Municipal Administration

CMWSSB : Chennai Metro Water Supply & Sewerage Board

CPHEEO : Central Public Health & Environmental Engineering Organization

DSCR : Debt Service Coverage Ratio

DPR : Detailed Project Report

ESR : Elevated Storage Reservoir

ESA : Environmental and Social Assessment

FAS : Financial Accounting System

FOP : Financial Operating Plan

FY : Financial Year

GIS : Geographical Information System

Govt. : Government

G.O : Government Order

GSR : Ground Level Reservoir

HH : House hold

HP : Horse Power

Town Investment Plan – Thudiyalur

TNUIFSL

T

N

U

D

P

III

XV

Final

Report

HSC : House Hold Connections

HSS : Higher Secondary School

HUDCO : Housing and Urban Development Corporation

IHSDP : Integrated Housing & Slum Development Program

Kg : Kilo Gram

Km : Kilometer

JNNURM : Jawaharlal Nehru National Urban Renewal Mission

Sq.Km : Square Kilometer

Lpcd : Litre per capita per day

LL : Lakh Litre

LIC : Life Insurance corporation of India

OHT : Over Head Tanks

m : Meter

m2 : Square Meter

m3 : Cubic Meter

MIS : Management Information System

Mld : Million litres per day

MOA : Memorandum of Association

Mm

MRTS

MTC

:

:

:

Millimeter

Mass Rapid Transit System

Metropolitan Transport Corporation

MUDF : Municipal Urban Development Funds

MUDP : Madras Urban Development Project

NA : Not Available/Not Applicable

NGO : Non Government Organization

NH : National Highway

NHAI : National Highway Authority of India

O&M : Operations and Maintenance

Town Investment Plan – Thudiyalur

TNUIFSL

T

N

U

D

P

III

XVI

Final

Report

PF : Public Fountains

PPP : Public Private Participation

PSP : Private Sector Participation

PWD : Public Works Department

RE : Revised Budget estimates

SEZ : Special Economic Zone

Sq ft : Square Feet

Sq Km : Square Kilometer

SC/ST : Scheduled Castes/Schedule Tribes

SHG : Self Help Group

SH : State Highway

SWD : Storm Water Drains

SWM : Solid Waste Management

TIP : Town Investment Plan

TOR : Terms of Reference

TNUDP : Tamil Nadu Urban Development Project

TNUIFSL : Tamil Nadu Urban Infrastructure Financial Services Limited

TUFIDCO : Tamil Nadu Urban Finance & Infrastructure Development Corporation Limited

TWAD : Tamil Nadu Water Supply & Drainage Board

UDPFI : Urban Development Planning Formulation and Implementation

UIDSSMT : Urban Infrastructure Development Scheme for Small & Medium Towns

UGD : Under Ground Sewerage

ULB : Urban Local Bodies

WBM : Water Bound Macadam

WFPR : Work Force Participation Rate

WS : Water Supply

Town Investment Plan – Thudiyalur

TNUIFSL 1-1

T

N

U

D

P

III

Final

Report

1111 PROJECT BACKGROUND

Government of Tamilnadu and The World Bank as a partner has been involved

in Urban Reform program in Tamilnadu through Tamilnadu Urban

Development Project – TNUDP-I, TNUDP-II, TNUDP-III (in progress).

Government of Tamilnadu is now implementing TNUDP-III with focus on

furthering the urban reforms initiated under TNUDP-II.

As a financial intermediary, TNUIFSL intends to assist Annamalai Nagar,

Vadalur, Tharangampadi, Ottenchatram, Thudiyalur, Thirupattur, S.Kannanur

and Peravurani Town Panchayats in identifying infrastructure gaps and propose

capital investment needs for providing better service delivery.

In this regard, the task of preparation of Town Investment plan for the aforesaid

towns has been awarded to Darashaw & Company Private Limited. This report

pertains to the Town Investment Plan for Thudiyalur.

1.1 PROJECT OBJECTIVES

The objective of this exercise is to:

� Assess the demand for the projects specified by the towns and come out

with gap in services considering the population growth and growth

direction of towns;

� Broadly outline the short term and long term infrastructure needs;

� Define specific rehabilitation and capital improvement needs with regard

to priority of town infrastructure in both slums and other areas;

� Define revenue enhancement and revenue management improvements

required

Town Investment Plan – Thudiyalur

TNUIFSL 1-2

T

N

U

D

P

III

Final

Report

1.2 SCOPE OF WORK

The scope of works covers but not limited to the following:

� Assess the demand for the projects listed out by these Town Panchayats.

� Current coverage and additional population in the medium term (10

years) and unit costs, indicate town level investment requirement for

up gradation of town wide infrastructure.

� to improve service coverage and asset quality and define priority

assets and indicative costs of rehabilitation

� Financial assessment of the ULBs- an assessment of local finances (past

5 years) in terms of sources and uses of funds, base and basis of levy,

revision history and impacts, State assignments and transfers- base and

basis of transfer and its predictability; uses of funds outstanding

liabilities (loans, power dues, pension etc) and, a review of revenue and

service management arrangements, levels of service, coverage and

quality of municipal services in both poor and non-poor localities.

Staffing and management arrangements in delivery of services

� Initiate consultations with council and local stakeholders on the

priorities; redefine priorities and work with the Council to resolve on

adoption of the Town Investment Plan.

� Prepare a financial and operating plan (FOP). The FOP is a medium term

framework of the ULBs, and shall present the following–

� Break up of energy cost on UG, WS etc.

� Salary for all the departments including staff and payments to private

operators

� Finding out the benchmark cost i.e. at ideal condition what will be

the cost of the identified investments, a table indicating the

investment plan for next 5 years with identified source of finance.

Areas of reduction in expenditure

� Energy audit resulting in savings in energy.

Town Investment Plan – Thudiyalur

TNUIFSL 1-3

T

N

U

D

P

III

Final

Report

� Leak detection resulting either in connections or in the tariff (or)

maintaining the same supply and achieving a reduction in energy

cost.

� Privatizing the MSW collection and identifying a BoT operator for

elim9inating, composting etc, items of revenue can be identified.

� Laying of Cement concrete road / Fly ash and savings on

maintenance cost resulting in increasing operating surplus.

� Water recycling / reuse

� Rejuvenation of tanks and reduction of cost / liters of water produced

� Privatization & option for revenue raising.

Options for increasing the revenues through non-traditional methods

� Land development for raising revenue (not the traditional

commercial complexes)

� Suggestion for improvement of revenues

� Finalize Action Plan for the Town, with a resolution from the council on

the priorities

1.3 METHODOLOGY ADOPTED

The whole exercise is divided into four stages, which are further subdivided into

tasks and several sub-tasks or activities within them. Figure below shows the

adopted study methodology and is followed by a brief description on each of the

stages.

Town Investment Plan – Thudiyalur

TNUIFSL 1-4

T

N

U

D

P

III

Final

Report

Figure 1-1 Approach and Methodology for Town Investment Plan

Town Investment Plan – Thudiyalur

TNUIFSL 1-5

T

N

U

D

P

III

Final

Report

1.3.1 DATABASE IDENTIFICATION

� Database Identification and compilation

Database forms the backbone of any kind of research works and also

helps in focusing the study towards the definite approach. Under this

task, the database required and the departments responsible for such

kind of data was identified at town levels. A detailed checklist was

prepared of all the sectors, along with identifying the probable

departments for the collection of the data.

� Field survey and data collection

Secondary data was collected from Town Panchayat in relation to

different sectors identified like:

i. Town Infrastructure Services

ii. Town Economic Development

iii. Roads, Traffic and Transportation

iv. Slums and Urban Poverty

v. Human resources and Institutional Issues

vi. Financial management

vii. Environmental Management

viii. Asset Management

ix. O&M Requirements, Energy Saving Mechanism &

Capacity assessment

Data was also collected on the Finance and Institutional Arrangement of the

ULB. It Included accounts and budgets for the last five years, loan status, capital

works in the last five years with sector-wise breakup, Audit Report, Properties,

Water connections, Sewer connections registered and assessment of unregistered

properties and assets of each town Panchayats and their condition. In addition,

staffing and management arrangements in delivery of services was also collected

and assessed.

Town Investment Plan – Thudiyalur

TNUIFSL 1-6

T

N

U

D

P

III

Final

Report

1.4 DETAILED APPROACH AND

METHODOLOGY

1.4.1 INCEPTION STAGE REPORT

1.4.1.1 DEMAND ASSESSMENT

RFP document specifies that the ULBs have on their own identified certain

projects to be implemented, for which demand assessment has to be carried out

and sustainable investment plan has to be prepared for the same.

Hence, Inception stage in essence assessed the demand for various projects

proposed by the ULBs. Furthermore, Investment Plan for such projects was

reviewed (or) Investment Plan was prepared for such projects, if not attempted

by the concerned Town Panchayats. Further, Overall Demand Supply Gap

analysis in terms of Physical and Social Infrastructure for the next 15 years for

the ULB was carried out.

1.4.1.2 RAPID TOWN PERFORMANCE ASSESSMENT

Here, all the information collected from Secondary sources was analyzed to

arrive, current development status at town area level. The analysis included all

the sectors mentioned below:

i. Town Infrastructure Services

ii. Town Economic Development

iii. Roads, Traffic and Transportation

iv. Slums and Urban Poverty

v. Human resources and Institutional Issues

vi. Financial management

vii. Environmental Management

viii. Asset Management

ix. O&M Requirements, Energy Saving Mechanism &

Capacity assessment

Town Investment Plan – Thudiyalur

TNUIFSL 1-7

T

N

U

D

P

III

Final

Report

Figure 1-2 Approach and Methodology for Inception stage

Demand Assessment and Rapid Urban assessment undertaken in the

Inception stage was approved and accepted by the Review Committee on

28th August 2009.

1.4.1.3 SUGGESTIONS OF THE REVIEW COMMITTEE ON THE

INCEPTION REPORT

The Suggestions given by the Review Committee during the meeting has been

given as under.

� To conduct stakeholders’ consultations to ascertain the demands from

public to identify infrastructure gaps.

� To present the draft final report to respective ULBs in the council after

incorporating the suggestions of stake holders meeting.

� To recheck the financials of ULBs including debt status.

� To Analyse last 5 years financials and furnish the data on existing loan,

loan repaid on due date, overdue loan, loan balance and loans sanctioned

Town Investment Plan – Thudiyalur

TNUIFSL 1-8

T

N

U

D

P

III

Final

Report

but yet to be availed. In this regard, all Town Panchayats were requested

to provide 5 years audited accounts and recent years’ un-audited

accounts along with DCB and loan statements and any other relevant

details to the consultants.

� To study on the unused / under utilized assets of the ULB and suggest

ways for the better utilization of the same.

� To identify any vacant land for development.

� Address the land issue for UGSS project.

� Address the need of the commercial centre

� Street light provision calculation to be rechecked with ULB.

1.4.2 DRAFT FINAL STAGE

In draft final stage, four tasks were carried out and are described briefly as

below:

1.4.2.1 DEVELOPMENT SCENARIO

Future Development Scenario for the ULB was developed based on Rapid Town

Performance Assessment, Demand Assessment, S-W-O-T analysis and on the

basis of Citizen’s perception and viewpoint.

1.4.2.2 SECTORAL VISION AND STRATEGIES

On the basis of the sectoral issues identified during rapid Town Performance

assessment, the sectoral vision and strategies were worked out to overcome

those issues. These strategies were further converted into Action plans and

projects. The projects were then phased on the basis of demand and stakeholders

priorities.

During Strategic plan preparation; emphasis was mainly given to Areas/ sectors

related to local Economic Development and poverty reduction

Town Investment Plan – Thudiyalur

TNUIFSL 1-9

T

N

U

D

P

III

Final

Report

1.4.2.3 TOWN INVESTMENT PLAN

The budget cost estimates for the proposed projects was worked out to

determine the financial requirements for meeting the demand for infrastructure

and services. The project phasing was also worked out so that the financials of

the ULB would not be burdened much and at the same time the objective of

provision of basic services would be achieved.

1.4.2.4 ASSET MANAGEMENT PLAN

The life cycle O&M costs for the services proposed were worked out and in

addition, O&M for lands and assets vested with the ULBs were also worked out.

On that basis, a detailed Asset Management Plan was prepared for the ULB.

The above 4 tasks were covered in this Draft Final stage report.

The Draft Final Stage was approved and accepted by the Review

Committee on 23rd December 2009.

1.4.2.5 SUGGESTIONS OF THE REVIEW COMMITTEE ON THE

DRAFT FINAL REPORT

� To recheck the financial of ULB for the financial year 2007-08, 2008-09

based on the actuals financial statement and do the FOP.

� Any changes in the rates, etc may be obtained from ULB and incorporate

the same in final report.

1.4.3 FINAL STAGE

In final Stage, there are two tasks, which have been carried out and are described

briefly as below:

1.4.3.1 FINANCIAL OPERATING PLAN

The projected FOP under four broad scenarios has been worked out to highlight

the importance of the reforms suggested to implement all identified projects

required for the development of the ULB.

Town Investment Plan – Thudiyalur

TNUIFSL 1-10

T

N

U

D

P

III

Final

Report

The four broad scenarios under which FOP has been worked out for each ULB

are as under:

� Base case scenario (“Business as usual scenario”) - In this scenario “No

New Projects” and “No reforms” over the next 15 year period is

considered.

� Full Project Scenario without undertaking the Suggested Reforms

� Full Project Scenario with Full Reforms implementation

� Sustainable Investment Scenario

1.4.3.2 DRAFT MEMORANDUM OF ASSOCIATION

Draft Memorandum of Association has been prepared which would outline the

base line (based on the Situation Analysis) and the performance benchmarks to

be monitored, apart from other financial and loan covenants. This Draft MoA

has covered two sub tasks. One is the Policy Intervention in the form of

Institutional and policy reforms for effective governance and financial

management. The other one is the technical assistance to each ULB for effective

implementation of the Town Investment Plan.

1.4.3.3 COUNCIL RESOLUTION

Council Resolution has been obtained from the ULB accepting all suggested

reforms and proposed Investments for the next 15 years period.

The final report has covered all the above stages along with incorporating the

suggestions and modifications given by the review committee and local

stakeholders.

Town Investment Plan – Thudiyalur

TNUIFSL 2-1

T

N

U

D

P

III

Final

Report

2222 TOWN PROFILE

Thudiyalur is a panchayat town in Coimbatore district in the Indian state of

Tamil Nadu. It is situated on North western side of Coimbatore City at a

distance of 12 km from city center. Thudiyalur is ideally located on the famous

Mettupalayam Road on the way from Coimbatore to Otty. Thudiyalur is a fast

developing urban centre. This town is well known for its industries of Textiles.

People residing in Thudiyalur are mainly employed in industries. Town

Panchayat extends over an area of 8.69 Sq.Km. Thudiyalur Town Panchayat is

divided into 18 wards comprising of three revenue villages.

Thudiyalur was constituted on 1958 as village panchayat and further it was

upgraded to second grade Town Panchayat in 1970. It was later upgraded to

Selection grade Town Panchayat from 1974 and functioning as such till date.

2.1 REGIONAL SETTING AND NETWORK

LINKAGES

It is located on NH-67 connecting Coimbatore with Ooty via Mettupalayam. It

is located North side of Goundampalayam third grade municipality, West side of

Vellakinar Town Panchayat, South side of Kurudampalayam Village Panchayat

and East side of Pannimadai Village Panchayat.. Thudiyalur is well connected

with Coimbatore , the district head quarters and Chennai, the state head quarters

and with other towns of Mettupalayam, Ooty, Thiruppur and Palakkad by road

transport facilities. The main mode of transportation is buses operated both by

Government Transport Corporation and private owners. The nearest airport is

located in Coimbatore near SITRA. Thudiyalur is connected with Coimbatore

by town buses run by both private agencies and public transport corporations

and by para-transit systems.

Town Investment Plan – Thudiyalur

TNUIFSL 2-2

T

N

U

D

P

III

Final

Report

Figure 2-1 Regional Setting and Network Linkages

Town Investment Plan – Thudiyalur

TNUIFSL 2-3

T

N

U

D

P

III

Final

Report

2.2 DEMOGRAPHY

Thudiyalur has a population of 21004 as per 2001 census and having male

population of 10773 and female population of 10231. Thudiyalur has shown a

high growth percentage of 59% between 1981 and 1991. Between 1991 and

2001 it has shown considerably moderate growth rate of 35%. The growth of

population and decadal variation from the year 1981 is illustrated in Table 2-A.

Table 2-A : Population growth trends in Thudiyalur

Census year Population

Percentage

Increase

1981 9787

1991 15553 58.9

2001 21004 35.0

The ward wise population as per 2001 census is shown in Table 2-B.

Table 2-B Ward wise Population details

Ward no Total Male Female SC ST

Ward No.1 727 390 337 9 -

Ward No.2 1419 681 738 101 -

Ward No.3 1498 771 727 165 11

Ward No.4 1444 746 698 586 -

Ward No.5 1171 604 567 46 -

Ward No.6 1133 579 554 47 -

Ward No.7 852 417 435 526 -

Ward No.8 896 446 450 - -

Ward No.9 1843 942 901 130 -

Ward No.10 1023 539 484 - -

Ward No.11 1001 523 478 7 -

Ward No.12 1478 775 703 45 -

Ward No.13 1389 664 725 76 -

Ward No.14 1462 760 702 132 -

Town Investment Plan – Thudiyalur

TNUIFSL 2-4

T

N

U

D

P

III

Final

Report

Ward no Total Male Female SC ST

Ward No.15 1430 742 688 185 -

Ward No.16 699 359 340 219 -

Ward No.17 1021 566 455 328 -

Ward No.18 518 269 249 156 -

TOTAL 21004 10773 10231 2758 -

Source: data collected from Thudiyalur Town Panchayat

2.2.1 POPULATION PROJECTIONS

Population projections for the next fifteen year period have been done using

various methods like Arithmetic Increase, Geometric Increase, Incremental

Increase, Least Squares and Graphical Methods. The low and high end projected

population based on the methods mentioned above in 2023 could be 33,300 and

47,900. Since the town is in close proximity to Coimbatore Metropolitan area

and further it is declared as a fast growing Town by Directorate of Town

Panchayats, it is prudent to consider high end population for future planning

purposes. Hence the same method is adopted for future planning purposes.

Projections by various methods are shown in Table 2-C.

Table 2-C : Population projections by various methods

Year

Arithmetic

Increase

Geometric

Increase

Incremental

Increase

Least

Squares

Graphical

Method

1981 9787 9787 9787 9787 9787

1991 15553 15553 15553 15553 15553

2001 21004 21004 21004 21004 21004

2009 25491 28343 27453 25543 27000

2013 27734 32925 31332 27787 29500

2018 30538 39707 36793 30591 32000

2023 33343 47886 42936 33395 35000

Town Investment Plan – Thudiyalur

TNUIFSL 2-5

T

N

U

D

P

III

Final

Report

2.3 SOCIAL CHARACTERISTICS

2.3.1 SOCIAL COMPOSITION

As per census 2001, SC population is about 13 percent of the total population

whereas ST population is insignificant as shown in Table 2-D. Ward No 04 has

maximum share of SC population followed by ward no 07 as shown in Table

2-B.

Table 2-D Social Composition

Social Composition Male Female Total % share to total

SC Population 1358 1400 2758 13.13

ST Population 7 4 11 0.05

Others 9408 8827 18235 86.82

Total Population 10773 10231 21004 100.00

2.3.2 GENDER RATIO

Gender ratio in Thudiyalur is lower than district urban and state urban gender

ratio. Gender ratio in the case of population below 6 years of age is much lower

than the general gender ratio of Thudiyalur. However, gender ratio among SC

population in the town is higher than the State urban and district urban as shown

in Table 2-E.

Table 2-E Gender Ratio

Gender ratio Population Population below 06 SC

Male 10773 1092 1358

Female 10231 986 1400

Gender ratio in Thudiyalur 950 903 1031

In Coimbatore Urban district 957 963 1002

In Tamilnadu urban 982 955 1001

Town Investment Plan – Thudiyalur

TNUIFSL 2-6

T

N

U

D

P

III

Final

Report

2.3.3 LITERACY LEVELS

As per census 2001, 84 percent of total population (excluding 0-6 years of age)

are literates of which male accounted for 90 percent and female accounted for

78 percent. Literacy levels in Thudiyalur and its comparison with state urban

and district urban figures are shown in Table 2-F.

Table 2-F Literacy levels

Literacy levels Total Male Female

Thudiyalur 84.37 90.29 78.17

Coimbatore Urban district 83.00 89.37 76.34

Tamilnadu State Urban 82.53 88.97 75.99

2.4 PHYSICAL CHARACTERISTICS

2.4.1 GEOLOGY AND SOIL TYPE

The soil formation in Coimbatore North which includes Thudiyalur is the

combination of red loam, black soil, Sandy coastal alluvium and red sandy soil.

2.4.2 CLIMATE AND RAINFALL

The mean maximum and mean minimum temperature in Coimbatore varies from

210C to 35

0C. Normal rainfall during North East Monsoon varies between 327

mm to 444 mm and during South West Monsoon it varies between 141 and 192

mm. During winter period, the rainfall varies from 11 to 26mm where as in Hot

Weather period; it varies from 128 to 148 mm.

Town Investment Plan – Thudiyalur

TNUIFSL 3-1

T

N

U

D

P

III

Final

Report

3333 ECONOMIC DEVELOPMENT

3.1 ECONOMIC BASE OF THE TOWN

Thudiyalur is a fast developing urban centre. It is basically an industrial and

service sector based town. Town has well known industrial units like Texmo

Industries, Aqua Pump industries, Texvel Starter oil engine, Steyns Fertilizers,

Mafatlal and Aanaimalai Toyotos etc in its vicinity. Further, Town is dependent

on Mother City, Coimbatore for its economic activities.

3.2 OCCUPATIONAL PATTERN

Thudiyalur is predominantly a service based town and hence its dependency on

primary sector is less when compared to district urban and state urban areas. Its

economic base is reflected in its dependency on other service related activity

which is very high (92% to total workers) due to its proximity to Coimbatore

urban area when compared to the Coimbatore district urban and state urban

occupational figures as shown in Table 3-A. Non workers percentage to total

population is low when compared to state urban non workers share.

Table 3-A Occupational Pattern and its comparison – 2001

Area Indicators Primary

Household

Industry Others

Total

workers

Non

workers

Thudiyalur % to total workers 5.3 2.0 92.6

District Urban % to total workers 10.0 3.5 86.4

State Urban % to total workers 14.0 6.3 79.6

Thudiyalur % to total population 2.2 0.9 38.8 41.9 58.1

District Urban % to total population 4.2 1.5 36.6 42.3 57.7

State Urban % to total population 5.3 2.4 29.9 37.5 62.5

Town Investment Plan – Thudiyalur

TNUIFSL 3-2

T

N

U

D

P

III

Final

Report

3.3 INDUSTRIES

Thudiyalur has prominent industries in its vicinity and are listed below:

• Texmo Industries,

• Aqua Pump industries,

• Velumani Engineering,

• Rangavel Industries

• CR spinners,

• Scan machineries,

• SB steels,

• Premier Metals,

• Texvel Starter oil engine,

• Steyns Fertilizers,

• Mafatlal and

• Aanaimalai Toyotos

3.4 TOURISM POTENTIAL

Thudiyalur itself has no tourism destinations but mother city Coimbatore is very

much known for its tourist attractions. There are lots of places to visit in and

around coimbatore which are listed below:

3.4.1 OOTY

Ooty also known as Udhagamandalam is the "Queen of hill stations" and the

capital of Nilgiris district. It is one of the most popular tourist resorts in India.

Nilgiris means "Blue Mountains". It is a land of picturesque picnic spots.

Britishers used this spot as a popular summer and weekend get away during the

Town Investment Plan – Thudiyalur

TNUIFSL 3-3

T

N

U

D

P

III

Final

Report

colonial days. It is situated at an altitude of 2,240 meters above sea level. An

added attraction for the tourists to Udagamandalam is the mountain train journey

on a ratchet and pinion track which commences from Kallar, near Mettupalayam

and wends its way through many hair-raising curves and fearful tunnels and

chugs along beside deep ravines full of verdant vegetation, gurgling streams and

tea gardens.

3.4.2 MARUDHA MALAI

Marudhamalai Hills Arulmigu Subramanyaswamy Temple is situated at a height

of about 500 feet in a plateau on the Western Ghats, fifteen kilometers North

West of Coimbatore, amidst lush vegetation and salubrious climate. It is one of

the six abodes of lord Muruga.

3.4.3 ESHA YOGA CENTRE

The Isha Yoga Center, founded under the aegis of Isha Foundation, is located on

150 acres of lush land at the foothills of the Velliangiri Mountains. Surrounded

by thick forests, it is a part of the Nilgiri Biosphere, a reserve forest with

abundant wildlife. Created as a powerful sthana (a center for inner growth), this

popular destination attracts people from all parts of the world and is unique in its

offering of all the four major paths of yoga - gnana(knowledge), karma (action),

kriya (energy), and bhakthi (devotion).

3.4.4 OTHER IMPORTANT TOURIST

DESTINATIONS

1. Aliyar Dam, Near Pollachi.

2. Thirumurthy Dam, Udumalpet.

3. Amaravathy Dam, Udumalpet.

4. Kovai Kutralum, Perur, Coimbatore.

5. Siruvani Dam, Near wallaiyar.

Town Investment Plan – Thudiyalur

TNUIFSL 3-4

T

N

U

D

P

III

Final

Report

6. Black Thunder (Water Sports),

7. Narayanakavi Memorial, Udumalaipettai

8. Valparai Hill Station.

9. Cholayar Dam, Valparai.

10. Kadamparai Power House, Valparai

11. Tamilnadu Agri. University Botanical Gardens

12. Horticulture Farms, Kallar, Near Mettupalayam.

13. Vaitheki Falls, Narasi Palayam

14. Indira Gandhi Wildlife Sanctuary & National Park (Top Slip), Pollachi

15. V.O.C Park, Coimbatore

16. Karamadai Range Forest eco-tourism

Town Investment Plan – Thudiyalur

TNUIFSL 4-1

T

N

U

D

P

III

Final

Report

4444 PHYSICAL INFRASTRUCTURE Infrastructure facilities play an important role in fostering economic growth and

enhancing public welfare. By and large, the infrastructure may be divided into

two categories:

� Physical infrastructure including Water supply, Drainage, Sewerage,

Solid Waste Management, Electricity, Telecommunications and so forth;

and

� Socio-economic infrastructure including Education, Health, other

Community facilities, Cold storages, Warehouses, Markets, Banks and

Financial Institutions.

This chapter deals with Physical Infrastructure which includes Water Supply,

Sewerage and Sanitation, Storm water drainage, Solid Waste Management

Roads and Street Lighting.

4.1 WATER SUPPLY

4.1.1 WATER SUPPLY SOURCES

The town is served by Athikadavu combined Water Supply Scheme initiated in

1995-96. The source – Pillur dam is located at a distance of 70 Kms from the

town supplies 16 lakh litres per day. Other than Combined Water Supply

Scheme, Thudiyalur has 32 bore wells supplies water for both drinking and non

drinking purposes.

4.1.2 WATER SUPPLY SYSTEM

One over head tank of 3 lakh litre capacity is located in Thudiyalur, one OHT of

2.5 lakh litre capacity is located in Subramaniyampalayam and one OHT of 1

Town Investment Plan – Thudiyalur

TNUIFSL 4-2

T

N

U

D

P

III

Final

Report

lakh litre capacity is located in Appanayakkanpalayam, stores water for

distribution purpose with a total capacity of 4.4 LL.

Thudiyalur has 6761 no of assessments having house service connections out of

total 8064 assessments. Out of 6761 household service connections, 6446 are

domestic water connections, 172 are commercial water connections and 143 are

industrial connections. In addition, 3 wells with power pump sets have been

provided within the town for non drinking purposes. Chlorination method is

followed for treating raw water at head works as well as at each tanks mentioned

above.

Table 4-A Water Supply system in Thudiyalur

4.1.3 WATER AVAILABILITY

Water is supplied from Athikadavu water supply scheme during day time to

Thudiyalur and during evening time in Subramaniyampalayam and

Description Details

Source of Water Supply : Bore wells and Athikadavu Pillur dam

Water Supply Agency : Town Panchayat, TWAD

Description regarding Storage Capacity in Lakh Litres

Thudiyalur : 3

Subramaniyampalayam : 2.5

Appanayakkanpalayam : 1

Total Storage Capacity : 6.5

Description regarding Connections

Domestic : 6446

Commercial : 172

Industrial : 143

Total : 6761

No of wells 3

No of bore wells with power pumps 32

Town Investment Plan – Thudiyalur

TNUIFSL 4-3

T

N

U

D

P

III

Final

Report

Appanayakkanpalayam. Overall, 57 LPCD water is being supplied by taking

into consideration the population for 2009 would be 28340.

4.1.4 SERVICE ADEQUACY

Table 4-B : Performance Indicators for water supply in Thudiyalur

S.No Indicators Unit Current status Norm

1 Daily per capita supply Litres 57 70/100

2 Roads covered with distribution network Percent 74 > 100

3 Storage capacity with respect to supply Percent 41 33

4 Available Treatment capacity with respect to

supply Percent

100 100

5 Assessments covered by service connections Percent 84 85

6 Proportion of non domestic service connections Percent 5 >5

4.1.5 PILLUR WATER SUPPLY SCHEME –

JNNURM

In order to achieve 70 lpcd, New Pillur combined water supply scheme is

proposed for providing water to 16 Town Panchayats around Coimbatore

including Thudiyalur Town Panchayat. TWAD board is the implementing

agency and the project cost is Rs.81.4676 crore for the entire scheme (project

cost for Thudiyalur – 5.6123 crore).

4.1.6 SECTORAL ISSUES

� Per capita supply is low (57%) against the standard norm of 70%

� 26% of the roads are not covered by distribution network

4.1.7 WATER SUPPLY DEMAND ASSESSMENT

Demand Assessment for Thudiyalur for the next fifteen year period under water

supply sector has been worked out and is tabulated below.

Town Investment Plan – Thudiyalur

TNUIFSL 4-4

T

N

U

D

P

III

Final

Report

Table 4-C : Demand Assessment for the next fifteen year period

Particulars 2009-10 2013-14 2018-19 2023-24

Thudiyalur projected population 28343 32925 39707 47886

Water Supply MLD 2009-10 2013-14 2018-19 2023-24

Thudiyalur water demand @ 70 lpcd for towns less

than 50,000 population 1.98 2.30 2.78 3.35

Existing Supply in mld 1.60 1.60 1.60 1.60

Gap 0.4 0.7 1.2 1.8

Pillur water supply scheme is proposed to meet future demand

Water Treatment Plant capacity in MLD 2009-10 2013-14 2018-19 2023-24

Demand for treatment plant capacity 1.98 2.30 2.78 3.35

Treated water supply 1.6 1.6 1.6 1.6

Gap 0.4 0.7 1.2 1.8

Water Distribution Network in Kms 2009-10 2013-14 2018-19 2023-24

Existing distribution length in Kms 50.0 50.0 50.0 50.0

Road length in Kms (exisitng and proposed) 67.4 67.4 67.4 71.8

Gap 17.4 17.4 17.4 21.8

Per Capita road length of 1.5 meter is considered for calculation

Water Service connections 2009-10 2013-14 2018-19 2023-24

No of Assessments 8064 9368 11297 13624

No of service connections 6761 7962 9603 11581

% service connections existing & proposed 83.8 85.0 85.0 85

Gap 16.2 15.0 15.0 15.0

Assessments increased on the basis of Assessment / population ratio

Service connections are proposed to be 85% by 2023-24

Storage capacity 2009-10 2013-14 2018-19 2023-24

Existing & Proposed Storage Capacity in MLD 0.65 0.65 0.65 0.65

Storage capacity demand in MLD 0.65 0.76 0.92 1.11

Gap in MLD 0.0 0.1 0.3 0.5

4.2 SEWERAGE AND SANITATION

4.2.1 SEWERAGE SYSTEM IN THUDIYALUR

Sewage is mostly the waste water of the community draining into the sewer

system with some ground water infiltration. Domestic sewage is the waste water

from kitchen, bathroom and toilets. Generally 80 percent of the water supplied

gets drained into the sewerage system.

Town Investment Plan – Thudiyalur

TNUIFSL 4-5

T

N

U

D

P

III

Final

Report

Thudiyalur currently has no underground sewerage system. Night soil is

disposed normally through individual toilets with septic tanks and low cost

sanitation facilities. 13 public convenience units have been constructed in the

town out of which one is Pay and Use, located within the Thudiyalur Shandy.

The road side drains constructed are used for disposing both waste water and

rainwater. Nearly 85% households have private sanitation facilites with septic

tank as a safe mode of disposal. Town has one sanitation tanker for cleaning

septic tanks.

Table 4-D : Public Toilets in Thudiyalur Town Panchayat

S.No Location Number Ward Numbers

1 Subramania Palayam 3 13,14

2 Appanaicken Palayam 4 17

3 Thudiyalur Town

a. Anna Colony 2 7

b. Idiyara Road 2 2

c. Muthu Nagar 1 4

Total 12

4 Pay and Use 1

4.2.2 SEWERAGE AND SANITATION DEMAND

ASSESSMENT

Demand Assessment for Thudiyalur for the next fifteen year period under

Sewerage and Sanitation sector has been worked out and is tabulated below.

Table 4-E : Demand Assessment for the next fifteen year period

Particulars 2009-10 2013-14 2018-19 2023-24

Thudiyalur projected population 28343 32925 39707 47886

Sewage generation 2009-10 2013-14 2018-19 2023-24

Thudiyalur sewage generation 1.6 1.8 2.2 2.7

Thudiyalur proposed Sewage Collection 0.0 0.0 0.0 0.0

Gap 1.6 1.8 2.2 2.7

Town Investment Plan – Thudiyalur

TNUIFSL 4-6

T

N

U

D

P

III

Final

Report

STP capacity in MLD 2009-10 2013-14 2018-19 2023-24

Capacity of proposed treatment plant 0.0 0.0 0.0 0.0

Gap 1.6 1.8 2.2 2.7

Sewer connections 2009-10 2013-14 2018-19 2023-24

Proposed connections under UGSS 0 0 0 0

Demand for sewer connections 5645 6557 7908 9537

Gap 5644.8 6557.4 7908.1 9537.0

Sewer Network in Kms 2009-10 2013-14 2018-19 2023-24

Sewer Network in Kms (Proposed ) 0.0 0.0 0.0 0.0

Sewer Network Demand 57.3 57.3 57.3 61.1

Gap 57.3 57.3 57.3 61.1

4.3 STORM WATER DRAINAGE

The total length of the Storm Water Drains constructed in the Town Panchayat

is around 47.5 Kms in which 45 Kms are pucca open drains and the remaining

2.5 Km drains are pucca closed drains.

4.3.1 SERVICE ADEQUACY

Table 4-F : Performance indicators for Storm Water Drainage in Thudiyalur

4.3.2 SECTORAL ISSUES

� Roads covered by Pucca Storm water drain is 67% against the standard

norm of 130%

4.3.3 STORM WATER DRAINAGE DEMAND

ASSESSMENT

Demand Assessment for Thudiyalur for the next fifteen year period under Storm

Water Drainage sector has been worked out and is tabulated below.

S.No Indicators Unit Current

Status

Normative

Standard Remarks

1 Road length covered

with pucca SWDs Percent 67 130

Highway road length

is also considered.

Town Investment Plan – Thudiyalur

TNUIFSL 4-7

T

N

U

D

P

III

Final

Report

Table 4-G : Demand Assessment for the next fifteen year period

Storm water drainage 2009-10 2013-14 2018-19 2023-24

Thudiyalur existing SWD 47.500 47.500 47.500 47.500

Storm water drain demand 92 92 92 98

Gap 45 45 45 50

Demand includes highway road length of 3.5 km

4.4 SOLID WASTE MANAGEMENT

4.4.1 GENERATION AND COLLECTION

Thudiyalur town generates around 7 ton of garbage per day at the rate of 247

grams per capita per day. Waste is being collected and segregated in all the 18

wards. Residential areas generate 75% of the waste and the remaining waste gets

generated from Commercial / Industrial areas as shown in Table 4-H .

Table 4-H Waste Composition

S.No Waste Generation from Quantity in MT Percentage share

1 Residential areas 5.25 75

2 Commercial areas 1.75 25

3 Total 0.8 100

Thudiyalur town Panchayat has the staff strength of 1 sanitary supervisor, 27

sanitary workers and 1 driver. Other than departmental workers, 3 Self Help

Groups having 42 members are also been involved in waste collection and

segregation. As a part of collection system, 24 tricycles are engaged in primary

waste collection.

4.4.2 DISPOSAL AND TREATMENT FACILITIES

One power tiller, one tipper and one tractor trailer is in operation for secondary

waste collection system and disposal. Panchayat has 0.2 acre land in

Appanayakkanpalayam for waste disposal and treatment. Currently, Waste being

Town Investment Plan – Thudiyalur

TNUIFSL 4-8

T

N

U

D

P

III

Final

Report

collected is segregated into bio-degradable, Non-biodegradable and recyclable

waste in Appanayakkanpalayam site.

Bio-degradable waste is converted into manure using Vermi compost method

whereas polythene papers are recycled into two type of by products which in

turn are being procured by factories for making end products like electrical

boxes; electrical conduit pipe junctions etc.

8 rectangular tanks have been constructed for Vermi composting. 2 additional

tanks are used for developing worms, 2 tanks for keeping the fodder for worms,

one tank for cow dung mix and one for keeping the chemicals. Non-

biodegradable waste is dumped in a land fill site belongs to Thudiyalur Town

Panchayat.

Compost yard in Appanayakkanpalayam

Vermi Compost Yard

Town Investment Plan – Thudiyalur

TNUIFSL 4-9

T

N

U

D

P

III

Final

Report

By product from recyclable waste

4.4.3 ADEQUACY OF SERVICES

Table 4-I : Performance Indicators for Solid Waste Management

Indicators Unit

Current

Status

Normative

Standard

Waste generation per Capita per day Grams 247.0 < 350 grams

Collection efficiency Percent 100.00 100

% of assessments covered by Door to Door

collection Percent 100.0 100

% of assessments involved in waste segregation Percent 100.0 100

Conservancy staff per Km persons 0.4 2

% capacity of Fleet vehicles to waste generated percent 28

4.4.4 SECTORAL ISSUES

� Town has inadequate land for disposal and treatment considering the

future demand.

� Town has no scientific landfill site.

Town Investment Plan – Thudiyalur

TNUIFSL 4-10

T

N

U

D

P

III

Final

Report

4.4.5 SOLID WASTE MANAGEMENT DEMAND

ASSESSMENT

Table 4-J : Demand Assessment for the next fifteen year period

Particulars 2009-10 2013-14 2018-19 2023-24

Thudiyalur projected population 28343 32925 39707 47886

Solid waste generation 2009-10 2013-14 2018-19 2023-24

Per capita waste in grams per day 247 267 295 326

Thudiyalur waste generation 7.0 8.8 11.7 15.6

Growth rate assumed 2.00%

4.5 ROADS, TRAFFIC AND TRANSPORTATION

4.5.1 REGIONAL NETWORK

It is located on NH-67 connecting Coimbatore with Ooty via Mettupalayam.

Thudiyalur is well connected with Coimbatore , the district head quarters and

Chennai, the state head quarters and with other towns of Mettupalayam, Ooty,

Thiruppur and Palakkad by road transport facilities.

Figure 4-1 : Regional Network Linkages

Town Investment Plan – Thudiyalur

TNUIFSL 4-11

T

N

U

D

P

III

Final

Report

The main mode of transportation is buses operated both by Government

Transport Corporation and private owners. The nearest airport is located in

Coimbatore near SITRA. Thudiyalur is connected with Coimbatore by town

buses run by both private agencies and public transport corporations and by

para-transit systems.

4.5.2 CITY LEVEL ROAD NETWORK

The total road Length within Thudiyalur is 67.44 Km. Out of 67.44 km road

length, 57.54 km are built with bituminous road, 3.8 km roads are made up of

Cement Concrete and Kutcha road constitutes 6.1 Kms. Road length and its type

are shown in Table 4-K.

Further, Mettupalayam Coimbatore NH road for a length of 1.00 Km,

Thudiyalur - Saravanampatti Road for a length of 0.50 Km, Thudiyalur -

Appanaickenpalayam Road for a length of 0.80 Km and Mettupalayam-

Subramaniampalayam Road for a length of 1.2 Km is passing through the

Thudiyalur Panchayat area.

Table 4-K: Road network in Thudiyalur

Road type Length in Kms Percentage Share

BT 57.54

CC 3.8

Earthen 6.1

Total 67.44

BT

85%

CC

6%

Earthen

9%

Town Investment Plan – Thudiyalur

TNUIFSL 4-12

T

N

U

D

P

III

Final

Report

4.5.3 PUBLIC TRANSPORT SYSTEM

The main mode of transportation is buses operated both by Government

Transport Corporation and private owners between Thudiyalur and Coimbatore.

Thudiyalur has no bus stand for bus parking. The town is connected with

Coimbatore by town buses parking on the road side and by para-transit systems.

Coimbatore Mettupalayam railway line passes through Thudiyalur Town

Panchayat area but there is no stoppage as on today.

4.5.4 SECTORAL ISSUES

� Mettupalayam road is heavily congested.

� 9% of the roads are kutcha.

4.5.5 ROAD NETWORK DEMAND ASSESSMENT

Demand Assessment for Thudiyalur for the next fifteen year period under Road

sector has been worked out and is tabulated below.

Table 4-L : Demand Assessment for the next fifteen year period

Particulars 2009-10 2013-14 2018-19 2023-24

Thudiyalur projected population 28343 32925 39707 47886

Road network 2009-10 2013-14 2018-19 2023-24

Existing road network in Kms 67.4 67.4 67.4 67.4

Road length demand 67.4 67.4 67.4 71.8

Gap 0.0 0.0 0.0 4.4

Per capita road length available is 2.4 meters which is greater than the standard requirement of 1.5 m /

person

Town Investment Plan – Thudiyalur

TNUIFSL 4-13

T

N

U

D

P

III

Final

Report

4.6 STREET LIGHTING

Thudiyalur has 1244 street lights positioned all over

the Town Panchayat area in which 1094 lights are 40

W tube lights, 146 lights are 250 W Sodium Vapor

lamps and 4 High Mast lights.

4.6.1 ADEQUACY OF SERVICES

Table 4-M : Performance Indicators for Street lighting in Thudiyalur

Indicators Unit Current status Norms/Standards

Spacing between lamps Meters 54 30

Proportion of tube lights W.R.T to total Percent 88 60

Proportion of high power fixtures W.R.T to

total Percent

12 40

4.6.2 SECTORAL ISSUES

� Spacing between lights is around 54 meters against the standard spacing

of 30 meters

� Most of the switches are manually operated

� Most of the fittings have conventional copper chokes.

4.6.3 STREET LIGHTING DEMAND ASSESSMENT

Table 4-N : Demand Assessment for the next fifteen year period

Street Lighting 2009-10 2013-14 2018-19 2023-24

Thudiyalur existing lights 1244 1244 1244 1244

Road length in Kms 67.4 67.4 67.4 71.8

Street light demand @ one light per 30 m 2248 2248 2248 2394

Gap 1004 1004 1004 1150

Type of fitting Nos

Tube light 1094

Sodium Vapor 146

High Mast 4

Total 1244

Town Investment Plan – Thudiyalur

TNUIFSL 4-14

T

N

U

D

P

III

Final

Report

4.7 DEMAND ASSESSMENT REGARDING

MODEL TOWN PROPOSALS.

Thudiyalur town has prepared Model Town proposals in which some of the

projects have been implemented already. The assessment regarding the current

status of the proposal is tabulated below:

4.7.1.1 WATER SUPPLY

Pillur Water supply scheme is sanctioned and to be implemented by TWAD.

4.7.1.2 SEWERAGE SCHEME

Rough cost for the underground drainage system estimated in Model town

proposal is (21004Nos x Rs.3000 / Nos) = 630.12 Lakhs. DPR preparation for

the scheme is entrusted to TWAD board.

4.7.1.3 ROAD WORKS UNDER JNNURM

Thudiyalur Town Panchayat is proposed to take up the following works under

JNNURM for the cost of Rs.304.12 Lakhs. The project status is listed below.

Town Investment Plan – Thudiyalur

TNUIFSL 4-15

T

N

U

D

P

III

Final

Report

Sl.No Name of work

Estimate

Amount

in Lakhs

Status

B.T. Roads

1 Nanjappa Gounder Colony Cross Roads 9.25 Completed

2 Rukkammal Colony Cross Roads 13.25 Proposed

3 Thirumalai Garden Cross Roads 7.4 Completed

4 Sriganth Nagar to Valarmathi Nagar 14.5 Completed

5 Valarmathi Nagar Cross Roads 3.75 Completed

6 Ganesh Nagar Cross Roads 14.8 Completed

7 Subramaniyam Palayam 1,2,3,4 Cross Roads 11.25 Completed

8 Cheran Colony Middle Cross Roads 13.85 Proposed

9 Cheran Colony West Side Cross Roads 13.85 Proposed

10 Cheran Colony East Side Cross Roads 13.85 Proposed

11 Cheran Colony North Side Cross Roads 13.85 Proposed

Culvert & Drainage

12 Subramaniyam Palayam Main Road From

Bharathi Nagar to Suryalakshmi Garden 14.2

Completed

13

Subramaniyam Palayam Main Road From

Maheshwari Theature to Subramaniyam

Palayam School

13

Completed

14 Subramaniyam Palayam Main Road From

Suryalakshmi Garden to Maheshwari Theature 13.3

Completed

15 Mullai Nagar to PRM Garden 14.15 Proposed

16 MTP Main Road from VCS Nagar to

Subramaniyam Palayam Main Road 9.4

Proposed

17 Mullai Nagar Cross Roads 7.25 Proposed

18 VCS Nagar South Side Cross Roads 14 Proposed

19 VCS Nagar North Side Cross Roads 14.4 Proposed

Town Investment Plan – Thudiyalur

TNUIFSL 4-16

T

N

U

D

P

III

Final

Report

Sl.No Name of work

Estimate

Amount

in Lakhs

Status

20 MTP Main Road from Texvel to VCS Nagar 7.85 Proposed

21 PRM Gardern to MTP Main Roads 13.27 Proposed

22 Cheran Colony North side Cross Roads 14.5 Completed

23 Cheran Colony West ide Cross Roads 12.45 Completed

24 Cheran Colony Middle Cross Roads 13.2 Completed

25 Cheran Colony East Cross Roads 13.55 Completed

Total 304.12

4.7.1.4 CREMATORIUM

Crematorium has already been completed in Thudiyalur burial ground

4.7.1.5 SHOPPING COMPLEX

Construction of Shopping Complex at weekly Shandy West side MTP Road

facing is under construction at a cost of 19.96 lakhs. Other two complex

proposals are not yet implemented.

Description of Works No of

Shops

Length

in M

Breath

in M

Area

in Sq

m

Estimate

Amount

in Lakhs

Status

Construction of Shopping

Complex at weekly shandy East

side South facing Part-I

(Vellakinar Road)

Proposed

1. Ground Floor 14 48.68 7.14 347.58 38.00

2. First Floor 14 48.68 7.14 347.58 30.00

Construction of Shopping

Complex at weekly shandy East

side South facing Part-II

(Vellakinar Road)

Proposed

Town Investment Plan – Thudiyalur

TNUIFSL 4-17

T

N

U

D

P

III

Final

Report

Description of Works No of

Shops

Length

in M

Breath

in M

Area

in Sq

m

Estimate

Amount

in Lakhs

Status

1. Ground Floor 5 19.61 7.14 140.02 16.00

2. First Floor 5 19.61 7.14 140.02 13.00

Construction of Shopping

Complex at weekly shandy

West side MTP Road facing

1. Ground Floor 48.68 7.14 347.58 38.00

2. First Floor 14 48.68 7.14 347.58 38.00

3. Second Floor 14 48.68 7.14 347.58 30.00

Total 106.00

Ongoing

4.7.1.6 IMPROVEMENTS TO OFFICE BUILDING

Parking shed proposal is under implementation whereas remaining works are yet

to be implemented.

Description of Works No of

Shops

Length

in M

Breath

in M

Area in Sq

m

Estimate

Amount

in Lakhs

Status

Store room 16.42 6.1 100.16 m2 10.8 Proposed

Record Room & Printing 16.42 6.10 100.16 m2 8.75 Proposed

Meeting Hall & A.E.

Room 2 16.12 8.00 128.96 m

2 14.45

Proposed

Parking Shed 18.30 8.00 146.40 m2 15.00 Ongoing

Providing Gardening

facility in Office

Premises

- - - 1.00

Proposed

Total 50.00

Town Investment Plan – Thudiyalur

TNUIFSL 4-18

T

N

U

D

P

III

Final

Report

4.7.1.7 COMMUNITY HALL

One Community hall is proposed under APAMT Scheme at a cost of Rs. 10

lakhs. Community hall at Muthu nagar is not feasible as suggested by

stakeholders. One more community hall needs to be created as planned in the

model plan proposal.

Description of Works Length

in M

Breath

in M

Area in Sq

m

Estimate

Amount

in Lakhs

Status

Construction of community hall

at Appanaicken palayam 15.25 9.15

139.54

m2 15.25

Proposed

Construction of community hall

at Muthu Nagar 15.25 9.15

139.54

m2

15.25 Not

feasible

Construction of community hall

at Anna colony 15.25 6.10 93.03 m

2 10.00

Proposed

Total 40.50

4.7.1.8 PARK DEVELOPMENT

Cheran Nagar Park has already been completed whereas SP Nagar Park is

ongoing at a cost of Rs. 12 lakhs. Tenders have been called for the development

of Eswar and Balasubramania park.

Location Length

in M

Breath

in M

Area in

Sq m

Estimate

Amount

in Lakhs

Status

S.P. Nagar 90 30 2700 17.50 ongoing

Balaji Nagar 30 30 900 5.80 Proposed

Srimurugan Nagar 40 40 1600 10.30 Proposed

Sai Nagar 45 15 675 4.40 Proposed

Visanatha puram 40 30 1200 7.75 Proposed

Cheran Nagar 75 30 2250 14.50 completed

2nd ward Eswar Park 40 50 2000 13.00 Tender

Town Investment Plan – Thudiyalur

TNUIFSL 4-19

T

N

U

D

P

III

Final

Report

Location Length

in M

Breath

in M

Area in

Sq m

Estimate

Amount

in Lakhs

Status

called

2nd Ward Thondupatti 30 25 750 5.00 Proposed

Appanaican palayam near

tank 40 25 1000 6.45

Proposed

Mullai nagar 40 30 1200 7.75 Proposed

Thirupathi nagar 30 30 90 6.00 Proposed

V.C.S. nagar 45 30 1350 8.75 Proposed

Balasubramania nagar 45 45 2025 13.00 Tender

called

Total 120.20

4.7.1.9 SHANDY DEVELOPMENT

Weekly market works haven’t been undertaken as planned in the model town

proposals. List of works are listed below.

Description of Works Length

in M

Breath

in M

Area in

Sq m

Estimate

Amount

(Lakhs)

Status

Construction of shed at weekly

shandy (Imported colour coated

G.I.sheet)

15 5 75 m2 36.00

Proposed

Construction of platform at

weekly shandy - - - 10.00 Proposed

Construction of drainage at

weekly shandy area - - - 10.00 Proposed

Cement concrete road 200 2.4 480 m2 16.80 Proposed

B.T. Road for shandy area - - - 10.00 Proposed

Town Investment Plan – Thudiyalur

TNUIFSL 4-20

T

N

U

D

P

III

Final

Report

Description of Works Length

in M

Breath

in M

Area in

Sq m

Estimate

Amount

(Lakhs)

Status

Street lights - - - 0.50 Proposed

Total 83.30

4.7.1.10 SLAUGHTER HOUSE

Slaughter house proposal (shop construction) has already been completed at a

cost of 5 lakhs against the budgetary cost estimate of Rs. 10 lakhs.

4.7.1.11 IMPROVEMENTS TO BURIAL GROUND

Gassifier crematorium is in operation, recently constructed in Thudiyalur burial

ground site. Remaining sites needs renovation as suggested below.

Description of Works Length

in M Estimate Amount in Lakhs

Status

Appanaikan palayam Proposed

Construction of compound wall 220 4.50

B.T road 200 2.50

Waiting shed & Burning shed - 2.50

Water Supply and Gardening work - 1.00

Subramaniam palayam Proposed

Construction of compound wall 250 5.00

B.T road 150 2.00

Waiting shed & Burning shed - 2.50

Water Supply and Gardening work - 1.00

Thudiyalur

Construction of compound wall 200 4.50

Waiting shed & Burning shed - 2.00

Water Supply and Gardening work - 1.00

Total 7.50

Gassifier

Crematorium

created on

this site

Town Investment Plan – Thudiyalur

TNUIFSL 4-21

T

N

U

D

P

III

Final

Report

4.7.1.12 WALKWAY

Walk way / foot path proposals haven’t been undertaken as on today as

suggested in the Model town proposal. List of works suggested is tabulated

below.

Description of Works Length in

M

Estimate Amount

in Lakhs

Status

MTP Main road from appnaicken

palayam main road to sowdabikha

complex

400 20.00

Proposed

Railway station Road 360 10.00 Proposed

Subramaniam palayam main road

from Mahalakshmi Bakery to

Subramaniam palayam School

(750x2)

1500 45.00

Proposed

Total 75.00

4.7.1.13 ROAD SIDE PARK

Road side park proposals haven’t been undertaken as on today as suggested in

the Model town proposal. List of works suggested is tabulated below.

Description of Works Length in M Area in

Sq m Rate

Estimate

Amount in

Lakhs

Status

Railway station road (750x2)

1500x1.50 500m

2 2250m

2 11.25

Proposed

Muthunagar roads (500x2)

1000x1.50 500m

2 1500m

2 2.50

Proposed

Cheran Colony to

Viswanathapuram

(2000x1.50)

3000 500m2 15.00

Proposed

Total 28.75

Town Investment Plan – Thudiyalur

TNUIFSL 4-22

T

N

U

D

P

III

Final

Report

4.7.1.14 SOILD WASTE MANAGEMENT

Appanaican palayam BT road, shed construction has already been completed

with treatment Plant. Compound wall needs to be created in this site. List of

works suggested is tabulated below.

Description of Works Length

in M

Estimate Amount

in Lakhs

Status

Appanaican palayam

Construction of compound wall 250 10.5 Proposed

B.T Surface the road for compost yard - 2.00 Completed

construction of shed - 4.00 Completed

Thudiyalur compost yard Proposed

Construction of compound wall 250 8.75

B.T Surface the road for compost yard - 5.00

construction of shed - 2.00

Total 32.25

4.7.1.15 TOILET PROPOSAL

Public toilet proposal has already been completed in Thudiyalur bus stop area.

Town Investment Plan – Thudiyalur

TNUIFSL 5-1

T

N

U

D

P

III

Final

Report

5555 SOCIO-ECONOMIC INFRASTRUCTURE

The Socio-economic infrastructure determines the development status of any

human settlement and this chapter covers Health, Education, Recreation and

other amenities.

5.1 HEALTH

Thudiyalur has one primary health center, one maternity center and 3 private

hospitals. Other than this, Coimbatore has very good hospitals to address higher

health complications and problems.

5.2 EDUCATION

Town has three middle schools, three primary schools, one Government and one

private industrial training institute (ITI) and three private schools. Town has one

branch library run by Coimbatore district Library association.

5.3 RECREATION

Town has parks in VKL nagar (W 09), Cheran Colony (W 04), Bund Colony (W

15), Balasubramanian nagar (W 17) and in VCS Nagar (W 09). Town has 28

approved layouts out of which 5 layouts mentioned above have already been

developed as shown in Table 5-A.

Table 5-A : Approved layouts in Thudiyalur Town Panchayat

Ward No. Approved Layouts Allotted Area

16 Captown Developers

1 Thirumurugan Nagar

1 Easwara Co Operative House Building Society 1736 Sq.m

Town Investment Plan – Thudiyalur

TNUIFSL 5-2

T

N

U

D

P

III

Final

Report

1 Rukkammal Colony 1652 Sq.m.

17 T.N.P. Nagar, Appanayakkanpalayam 13568 Sq.Ft.

9 Balaji Nagar 14630 Sq.Ft.

16 Kaliyammal Colony 4612 Sq.Ft.

9 Sri ram Nagar 9842 Sq.Ft.

9 Sri ram Nagar 14972 Sq.Ft.

16 Balaji Nagar (Capetown nearby) 6248 Sq.Ft.

15 Tiruppathi Nagar 2420 Sq.Ft.

15 Tiruppathi Nagar 5445 Sq.Ft.

17 Balasubramania Nagar * 19548 Sq.Ft.

9 VCS Nagar * 7004 Sq.Ft.

9 Sri Murugan Nagar 31745 Sq.Ft.

6 Lovely Nagar 15265 + 5755 Sq.Ft.

SF No.544 3560 Sq.Ft.

15 -----------------Bund colony * 8130 Sq.Ft.

8 V.P.V. Nagar 35649 Sq.Ft.

9 V.K.L Nagar * 47814 Sq.Ft.

16 Capetown 54672 Sq.Ft.

9 Park Avenue 26039 Sq.Ft.

4,5 Cheran Colony * 47212 Sq.Ft.

13 S.S.Garden 33332 Sq.Ft.

5 Kalaimagal Garden 4360 Sq. Ft.

9 Ayyasamy (Venu care Hospital) 21963 Sq.Ft.

17 Perinba Nagar 27961 Sq.Ft.

2 Eswara Park 18657 + 13472 Sq.Ft.

* Marked plots are developed parks.

Town Investment Plan – Thudiyalur

TNUIFSL 5-3

T

N

U

D

P

III

Final

Report

5.4 OTHER AMENITIES

Thudiyalur has banking facilities provided by Indian Bank in ward No. 18 and

Union Bank of India in ward No. 07. It has Murugan theatre in ward No. 07 and

Maheshwari theatre in ward No. 10. It has one primary health center in Ward no

02. Town has no Slaughter house but it has 12 Non veg shops.

Exisitng Town Panchayat office has adequate space and currently one more

building block is under construction for parking and for other official purposes.

Town has 4 burial grounds whose locations are listed in Table 5-B. Gassifier

crematorium is there in Thudiyalur crematorium in ward No.01. Town has

weekly market in ward No. 02 which opens on Monday every week. Further, it

has 76 daily market shops.

Panchayat has proposed one community hall at a cost of Rs. 10 lakhs under

APAMT Scheme. Further, shopping complex at a cost of Rs. 10 lakhs, BT road

with central median lights at a cost of Rs. 10 lakhs, water bodies improvement at

a cost of Rs. 10 lakhs, water supply provision at a cost of Rs. 5 lakhs and 5 more

lakhs for council determination have been proposed under this APAMT scheme

2010-11. Town Panchayat has constructed 46 commercial complex shops and it

has additional 5 old shops for revenue generating purposes. It has one two

wheeler parking space given on lease.

Table 5-B : Burial grounds in Thudiyalur Town Panchayat

Burial ground locations Number

Ward

Numbers Area

Subramaniya Palayam 1 13 50 Cents

Appanaicken Palayam- Opposite to Compost Yard 1 1 1 Acre

Appanaicken Palayam- Kaliamma Colony 1 13 50 Cents

Thudiyalur Crematarium - Gassfier 2 1 86.25Cents

Town Investment Plan – Thudiyalur

TNUIFSL 5-4

T

N

U

D

P

III

Final

Report

5.5 PROBLEMS AND ISSUES

Table 5-C : Issues related to Socio-Economic Infrastructure

Sector Issues

Socio-Economic

Infrastructure

• 23 approved layouts are undeveloped

• Weekly market lacks infrastructure facilities

• Town has no Slaughter house

• 3 burial grounds lacks infrastructure facilities

• Town has inadequate revenue generating commercial

complexes even though it is located in close proximity

to Coimbatore metropolitan area.

Town Investment Plan – Thudiyalur

TNUIFSL 6-1

T

N

U

D

P

III

Final

Report

6666 SLUMS AND URBAN POVERTY

As per Census of India, the slum areas are broadly defined as :-

� All specified areas in a town or city notified as ‘Slum’ by State/Local

Government and UT Administration under any Act including a ‘Slum

Act’.

� All areas recognized as ‘Slum’ by State/Local Government and UT

Administration, Housing and Slum Boards, which may have not been

formally notified as slum under any act;

� A compact area of at least 300 persons or about 60-70 households of

poorly built congested tenements, in unhygienic environment usually

with inadequate infrastructure and lacking in proper sanitary and

drinking water facilities.

6.1 SLUMS IN THUDIYALUR

In Thudiyalur, 6 un-notified slums are in existence. All the 6 un-notified slums

together have the population of 3050 which is equivalent to 11 percent of the

Thudiyalur current population. Slums in Thudiyalur are shown in Table 6-A.

Slums areas are provided with all basic infrastructure facilities as suggested by

the stakeholders.

Table 6-A Slums in Thudiyalur

Name of the slum Is it notified No.of households Population of the Slum

1.Anna Colony No 150 750

2. Puthu Muthu Nagar No 120 600

3. Appanaickenpalayam No 90 450

4. Kalaigner Nagar No 100 500

5. Subramaniampalayam No 80 400

6. Jallikorai No 70 350

Total 610 3050

Town Investment Plan – Thudiyalur

TNUIFSL 6-2

T

N

U

D

P

III

Final

Report

6.2 URBAN POOR IN THUDIYALUR

Thudiyalur has just 1% of the current population living below poverty line.

Ward Nos 04, 16, 17 and 18 has maximum share of BPL population which

accounts for 62% of the total BPL population in Thudiyalur. Ward wise BPL

population are shown in Table 6-B.

Table 6-B Ward wise BPL households in Thudiyalur

Ward No BPL population 2007 Percentage share

2 9 3

4 33 11

5 26 9

7 25 9

13 25 9

15 23 8

16 75 26

17 36 12

18 37 13

Total 289 100

Town Investment Plan – Thudiyalur

TNUIFSL

T

N

U

D

P

III

7-1

Final

Report

7777 FISCAL STATUS

7.1 BACKGROUND

Tamil Nadu is the first State to have introduced a classification in the status of

local bodies as ‘Town Panchayat’, which was planned as a transitional body

between Rural and Urban Local Bodies. The Town Panchayats were conferred

with individual administrative powers and unique functional characters have

been in existence for over a century. The Town Panchayats adopt well devised

accounting and auditing procedures and the service delivery to the public has

been better. Town Panchayats are under the administrative control Municipal

Administration and Water Supply Department, at Government level.

Till 1981, the Town Panchayats were under the administrative control of

Directorate of Rural Development. During 1981, the Government vide G.O. Ms.

828 Dated 7.5.1981, constituted a separate Directorate for the Town Panchayats

with the nomenclature of ‘Directorate of Town Panchayats’. However the

administrative control of the Directorate of Town Panchayats continued to be

with the Rural Development Department at the Secretariat as they were

governed under the Tamil Nadu Panchayats Act 1958.

Following the introduction of 73rd and 74th amendments to the Constitution of

India in the year 1993, all the Town Panchayats were reconstituted under the

Tamil Nadu District Municipalities Act, 1920 and treated as transitional area. i.e.

an area in transition from rural area to an Urban area. Necessary amendments

were brought on to the Tamil Nadu District Municipalities Act, 1920 for this

purpose and a separate chapter in respect of Town Panchayats was inserted in the

said Act. Consequently though the nomenclature ‘Town Panchayat’ remained

unchanged, the administrative control of the Directorate of Town Panchayats was

Town Investment Plan – Thudiyalur

TNUIFSL

T

N

U

D

P

III

7-2

Final

Report

brought under the Municipal Administration and Water Supply Department at the

Secretariat.

Municipal Corporation Acts and the District Municipalities Act of the Tamil

Nadu authorizes Urban local bodies to levy, collect and appropriate such taxes,

duties, tolls and fees in accordance with the procedures subject to limits as

specified by the legislature. Besides these, the urban local bodies are also

empowered with certain other financial powers.

The Sources of income for a Town Panchayat can be broadly categorized as

own sources (Includes both Tax and Non Tax Revenues), and External Sources

(Assigned Revenues, Devolution Funds, Grants and Contribution). Besides the

Town Panchayats can also avail of loans/ Grants/ Contribution from

Government(Central and State) and loans from various funding agencies such as

TUFIDCO, TNUIFSL, HUDCO, LIC and Banks etc, for undertaking specific

projects based on their credit worthiness.

The Town Panchayat’s Revenue Expenditure can be broadly categorized into

Personnel cost and Terminal and Retirement benefits, Operating Expenses,

Repairs & Maintenance Expenses, Programme Expenses Administrative

Expenses, Finance Expense, Provision for Depreciation. Besides the above,

significant amounts are required for undertaking capital works

Town Investment Plan – Thudiyalur

TNUIFSL

T

N

U

D

P

III

7-3

Final

Report

7.2 FINANCIALS

Figure 7-1 Income & Expenditure Account

Income & Expenditure Account

0.00100.00200.00300.00400.00500.00600.00

2003-04 2004-05 2005-06 2006-07 2007-08 2008-09

Rev.

Budget

Years

Rs

. in

la

kh

s

TOTAL INCOME TOTAL EXPENDITURE

Source : Annual Accounts of Thudiyalur Town Panchayat

Table 7-A Income & Expenditure Account Rs. in lakhs

Particulars

2003-0

4

2004-0

5

2005-0

6

2006-0

7

2007-0

8

2008-0

9

Re

Bu

dget

2009-1

0

Bu

dget

INCOME

Property Tax 33.38 39.91 47.37 55.95 64.60 90.00 120.00

Profession Tax 7.40 9.35 10.32 11.28 12.52 8.00 10.00

Vacant Land Tax - - - 26.47 13.47 - 10.00

Assigned Revenue 46.14 54.68 77.28 72.76 23.59 75.00 75.00

Devolution Fund 32.42 26.27 32.16 47.10 54.40 50.00 75.00

Service Charges & Fees 46.30 56.21 71.67 66.75 86.73 96.75 124.75

License Fees 0.51 0.66 0.09 0.65 0.67 2.50 2.00

License fees under PFA act 0.01 0.02 0.01 0.02 0.02 0.25 0.25

Building License Fees 5.03 7.60 9.08 10.61 9.38 7.00 20.00

Fees for Slaughter House 1.58 1.80 1.28 1.34 4.61 6.00 7.00

Cart Stand – Lorry Stand - Taxi Stand Fees 0.50 0.65 0.75 1.06 2.21 5.00 5.00

Fees for Pay & Use toilets 0.27 0.28 0.32 0.33 0.40 0.50 1.00

Copy Application Fees 0.15 0.29 1.40 0.35 0.54 1.50 2.00

Initial amount for new water supply under

ground 8.51 11.21 21.12 10.99 26.04 25.00 25.00

Water supply connection charges 0.57 0.72 1.34 0.79 1.45 5.00 5.00

Metered / Tap rate water supply under /ground

28.31 30.92 34.81 39.08 39.96 40.00 50.00

Others 0.85 2.06 1.48 1.54 1.45 4.00 7.50

Granted Contribution 0.16 0.01 0.38 1.76 0.72 2.00 2.00

Sales and Hire Charges 0.00 0.00 0.02 0.00 0.01 2.00 7.00

Other Income 113.89 115.53 135.96 134.85 88.69 103.95 160.45

Town Investment Plan – Thudiyalur

TNUIFSL

T

N

U

D

P

III

7-4

Final

Report

Market fees – Daily market 0.00 0.00 0.00 1.89 2.19 5.00 5.00

Market fees – weekly market 6.75 6.75 9.96 8.19 8.32 11.00 11.00

Development Charges 77.28 79.45 94.09 59.28 19.73 30.00 50.00

Rent on Shopping Complex 9.42 8.68 8.32 9.37 11.87 12.00 16.00

Interest from Bank 0.84 10.72 6.57 3.96 1.28 2.00 2.00

Projects Overhead Appropriation –

Expenses 12.36 9.63 7.45 28.12 29.37 30.00 60.00

Others 7.25 0.31 9.58 24.03 15.93 13.95 16.45

TOTAL INCOME 279.69 301.95 375.15 416.92 344.73 427.70 584.20

EXPENDITURE

Personnel Cost 21.14 20.71 22.15 30.98 38.64 42.44 66.70

Terminal and Retirement Benefits 0.20 0.20 0.20 0.20 0.00 2.25 4.50

Operating Expenses 34.39 45.92 44.61 44.56 64.86 115.00 147.00

Power charges for Head water works /

pumping station / Booster station – water

supply

15.17 18.22 17.72 20.84 30.01 25.00 50.00

Power charges for street lights 9.60 11.44 13.99 12.36 16.57 25.00 35.00

Maintains Expenses for street light 5.67 9.05 9.23 7.79 13.96 25.00 25.00

Sanitary / conservancy expenses 3.68 6.97 3.07 3.00 3.34 25.00 10.00

Expenses on sanitary materials 0.27 0.23 0.60 0.57 0.98 9.00 7.00

Others 0.00 0.01 0.00 0.00 0.00 6.00 20.00

Repairs and Maintenance Expenses 40.73 57.87 53.61 48.03 40.26 113.00 142.00

Light Vehicle Maintenance 0.06 0.00 0.00 0.00 0.00 3.00 5.00

Heavy Vehicle – Maintenance 0.89 2.60 3.94 4.95 5.32 8.00 12.00

Maintenance Water supply system 23.86 39.65 30.74 25.77 17.95 45.00 55.00

Maintenance Charges to TWAD Board 15.59 15.45 18.62 17.31 16.39 30.00 35.00

Others 0.33 0.16 0.31 0.00 0.60 27.00 35.00

Programme Expenses 0.00 0.00 0.00 0.00 0.00 10.55 15.50

Administrative Expenses 7.05 8.63 9.73 16.78 13.83 236.51 433.20

Finance Expenses 2.45 8.48 7.04 5.27 1.58 11.00 11.01

Depreciation 61.34 66.43 74.11 112.10 205.80 0.00 0.00

TOTAL EXPENDITURE 167.29 208.25 211.46 257.91 364.97 530.75 819.91

SURPLUS OR DEFICIT 112.40 93.71 163.70 159.01 -20.24 -103.05 -235.71

Source: Annual Accounts. Thudiyalur Town Panchayat

Town Investment Plan – Thudiyalur

TNUIFSL

T

N

U

D

P

III

7-5

Final

Report

7.3 ANALYSIS OF INCOME

Table 7-B : Income Analysis

Particulars 20

03

-04

20

04

-05

20

05

-06

20

06

-07

20

07

-08

20

08

-09

Sectoral Contribution to the Total Income

Property Tax 11.93% 13.22% 12.63% 13.42% 18.74% 21.04%

Profession Tax 2.65% 3.10% 2.75% 9.05% 7.54% 1.87%

Assigned Revenue 16.49% 18.11% 20.60% 17.45% 6.84% 17.54%

Devolution Fund 11.59% 8.70% 8.57% 11.30% 15.78% 11.69%

Service Charges & Fees 16.55% 18.61% 19.10% 16.01% 25.16% 22.62%

Granted Contribution 0.06% 0.00% 0.10% 0.42% 0.21% 0.47%

Sales and Hire Charges 0.00% 0.00% 0.00% 0.00% 0.00% 0.47%

Other Income 40.72% 38.26% 36.24% 32.34% 25.73% 24.30% Source: Analysis based on data provided by Thudiyalur Town Panchayat

Figure 7-2: Break up of Income for the year 2007-08

2007-08

19%

8%

7%

16%25%

0%

0%

25%

Property Tax

Other Taxes(Profession

Tax)

Asigned Revenue

Devolution Fund

Service Charges & Fees

Granted Contribution

Sales and Hire Charges

Other Income

Source: Thudiyalur Town Panchayat

The income of the Town Panchayat has increased from Rs.280 lakhs in the year

2003-04 to Rs.345 lakhs in the year 2007-08 with a CAGR of just over 5%. The

Town Panchayat has enjoyed a healthy surplus over the years except for the year

2007-08 with a small deficit of Rs.20.24 Lakhs

Town Investment Plan – Thudiyalur

TNUIFSL

T

N

U

D

P

III

7-6

Final

Report

7.3.1 OWN SOURCES

Taxes

Taxes consisting of Property and Professional Taxes have contributed more than

20% of the total income over the few years. The taxes have been growing at a

CAGR of 22% for the last few years.

Property Tax:

The most important category in the own sources of income is the property tax. This

tax is imposed on land and buildings depending upon their nature of use. More

than 70% of the tax revenue comes through property tax. The CAGR of property

tax revenue is close to 18% over the last few years.

Table 7-C Property Tax Particulars

Category Particulars

A (Rate Per Sq Ft) 0.90

B (Rate Per Sq Ft) 0.78

C (Rate Per Sq Ft) 0.60

No. of Assessment 2008-09 7434

No. of Assessment 2007-08 7062

No. of Assessment 2003-04 4080

% Increase in Number Assessments for the Past 5 years 7%

CAGR in Property Tax Revenue over the Last few years 17.95%

Total Property Tax (Rs. in Lakhs in 2007-08 ) 64.60

Number of sanctioned Staff in Revenue Department –

Bill Collector 2

Revenue per sanctioned person in revenue section (Rs. in Lakhs) 32.30

Average Tax Demand per property (Rs.) 1274.42

Source: Thudiyalur Town Panchayat.

Table 7-D Property Tax (Number of Assessment)

Years Residential Commercial Industrial Total

2002-03 3654 80 15 3749

2003-04 3945 110 25 4080

2004-05 5774 128 45 5947

2005-06 6232 140 55 6427

2006-07 6562 151 75 6788

2007-08 6807 162 93 7062

2008-09 7126 197 111 7434

2009-10 8064 197 111 8372

Source: Thudiyalur Town Panchayat.

Town Investment Plan – Thudiyalur

TNUIFSL

T

N

U

D

P

III

7-7

Final

Report

Profession Taxes:

It has contributed about 20% of the total taxes in the last few years with a CAGR

of over 14% in the last few years

Table 7-E Profession Tax Particulars

Total Professional Tax Revenue (Rs. in Lakhs 2007-08) 12.53

Slab for Professional Tax ( Half yearly) w.e.f. 01-10-2008

Rs.21000 Nil

Rs.21001to Rs.30000 Rs.98

Rs.30001 to Rs.45000 Rs.244

Rs.45001 to Rs.60000 Rs.488

Rs.60001 to Rs.75000 Rs.731

Above Rs.75001 Rs.975 Source: Thudiyalur Town Panchayat

Non Tax Revenues

The Town Panchayat earns revenue from Non-Tax sources such as revenue from

Service Charges and Fees and Other Income. Non tax revenue contributes about

50% of the of the Town Panchayat

Service Charges and Fees

The major sources of income under this head are Building License Fees, initial

amount for new water supply and metered tap rate water charges etc. The income

under this head has grown at a CAGR close to 17% in the last few years.

Other Income

The other income of the Town Panchayat has ranged between Rs.89 Lakhs to

Rs 136 Lakhs during the five year period from 2003-04 to 2007-08. The “other

income” mainly consists of development charges and Project overhead

appropriation etc.

Town Investment Plan – Thudiyalur

TNUIFSL

T

N

U

D

P

III

7-8

Final

Report

7.3.2 EXTERNAL SOURCES

Assigned Revenue

Assigned revenues include revenues transferred to the Town Panchayats by the

GoTN under specific acts. These are transferred to the Town Panchayats as their

share of taxes levied and collected by the GoTN. These include duty on transfer of

property, entertainment tax, surcharge on sales tax, and other assigned revenues if

any. Among all these, duty on transfer of property and entertainment tax is the

most significant ones .The contribution from Assigned Revenue has increased from

Rs.46.14 lakhs in 2003-04 to Rs.72.76 Lakhs in 2006-07

Devolution Fund

Based on the Second State Finance Commission recommendations, GOTN

transfers 8% of its state revenue to the local government. The inflows from

Devolution funds have increased from Rs.32.42 lakhs in 2003-04 to Rs.54.40 lakhs

in 2007-08 with a CAGR close to 14 % in the last few years.

7.4 ANALYSIS OF EXPENDITURE

The Revenue Expenditure of the Town Panchayat has been analyzed based on

expenditure heads which can be broadly classified under the major heads outlined

below:

• Personnel costs

• Operating Expenses

• Repairs & Maintenance Expenses

• Programme Expense

• Administrative Expenses

• Finance Expenses

• Depreciation

Town Investment Plan – Thudiyalur

TNUIFSL

T

N

U

D

P

III

7-9

Final

Report

Table 7-F : Expenditure Analysis

Particulars 20

03

-04

20

04

-05

20

05

-06

20

06

-07

20

07

-08

20

08

-09

Percentage share of Expenses to the Total Expenses

Personnel Cost 12.64% 9.94% 10.47% 12.01% 10.59% 8.00%

Terminal and Retirement Benefits 0.12% 0.10% 0.10% 0.08% 0.00% 0.42%

Operating Expenses 20.56% 22.05% 21.10% 17.28% 17.77% 21.67%

Repairs and Maintenance Expenses 24.35% 27.79% 25.35% 18.62% 11.03% 21.29%

Programme Expenses 0.00% 0.00% 0.00% 0.00% 0.00% 1.99%

Administrative Expenses 4.22% 4.15% 4.60% 6.50% 3.79% 44.56%

Finance Expenses 1.46% 4.07% 3.33% 2.04% 0.43% 2.07%

Depreciation 36.66% 31.90% 35.05% 43.46% 56.39% 0.00%

Source: Analysis based on data provided by Thudiyalur Town Panchayat

Figure 7-3 Break up of for the year 2007-08

2007-08

18%

11%

0%

4%

0%

56%

11%

0%

Personnel Cost

Terminal and Retirement

Benefits

Operating Expenses

Repairs and Maintenance

Expenses

Programme Expenses

Administrative Expenses

Finance Expenses

Depreciation

Source Annual Accounts of Thudiyalur Town Panchayat

The Expenditure of the Town Panchayat has shown an increasing trend in the last

few years. The overall expenditure of the town has increased from Rs.167.29 lakhs

in 2003-04 to Rs.364.97 lakhs in 2007-08 with a CAGR of over 21%

Personnel Costs

This expense mainly includes the staff salaries, Terminal and retirement benefits

and allowances paid to the employees of the local body. This expense has

grown by 16.27% in the last few years.

Town Investment Plan – Thudiyalur

TNUIFSL

T

N

U

D

P

III

7-10

Final

Report

Operating Expenses / Repairs & Maintenance

Expenses relating to operations and Repairs and Maintenance are very critical

indicators of the service management and maintenance capabilities and

performance of the local body..

Operating Expenses:-

The Operating expense mainly consists of such expenses which are met towards

the infrastructure facilities provided by the local body like Power charges for

Street Lights, Maintenance Expenses for Street Lights, Sanitary Conservancy

Expenses, and Expenses on sanitary material etc. Operating expenses have

increased from Rs.34.39 lakhs in 2003-04 to Rs.64.86 lakhs in 2007-08 with a

CAGR of over 17% for the last few years.

Repairs & Maintenance:-

Repairs & Maintenance expenses mainly consist of such expenses such as

Heavy Vehicle Maintenance, Maintenance expenses on account of water supply.

This expense has remained stagnant over the last few years.

Energy Costs:-

The energy costs for Water Supply for the year 2007-08 is 30.01 lakhs and that for

Street lighting is Rs. 16.57 lakhs. The power cost for Water Supply accounts for

less than 47% of the water supply expenditure. Water is supplied from Athikadavu

water supply scheme during day time in Thudiyalur and during evening time in

Subramaniyampalayam and Appanayakkanpalayam. The Panchayat has paid a sum of

Rs.16.39 Lakhs (2007-08) to TWAD Board as maintenance charges. In case of

Street lighting the power cost is about 54% of the street lighting expenditure. By

implementation of energy efficiency measures in water supply service delivery and

street lighting systems the reduction in costs can be achieved and monitored for

continuous energy savings.

Finance Expenses:-

Loan outstanding as on 31st March 2008 was Rs.30.96 lakhs.

Town Investment Plan – Thudiyalur

TNUIFSL

T

N

U

D

P

III

7-11

Final

Report

7.5 SOURCE & USE OF FUNDS

Table 7-G Balance Sheet

Rs. in lakhs

Particulars

20

03

-04

20

04

-05

20

05

-06

20

06

-07

20

07

-08

Uses of Funds

Fixed Assets 458.38 573.13 650.37 934.60 1238.18

Project in Progress 35.90 33.51 32.28 29.43 64.73

Tax & Non Tax Recoverable 9.88 7.66 4.16 2.50 2.59

Stock 0.00 0.19 0.00 0.00 0.00

Other Receivable/ Recoverable 7.36 10.63 8.39 7.94 6.30

Cash in Hand 1.44 2.48 1.25 0.82 2.63

Cash at Bank 286.02 350.75 569.94 634.21 473.73

TOTAL ASSETS 798.99 978.35 1266.39 1609.50 1788.16

Sources of Funds

Loans 41.31 39.14 36.79 33.74 30.96

Deposits 136.86 134.57 137.01 163.79 151.55

Government contribution/Mpl fund

/ Private Parties/Government Grants 30.57 38.99 81.97 112.87 117.11

Diversion of funds 0.00 0.00 0.00 0.00

Provision for doubtful Collection

of Revenue Items 0.00 4.45 4.16 2.50 2.50

Accumulated depreciation 110.07 176.61 250.72 362.82 568.62

Accumulated surplus 470.76 578.62 746.68 910.11 890.95

Others 9.42 5.97 9.07 23.67 26.47

TOTAL LIABILITIES 798.99 978.35 1266.39 1609.50 1788.16

Source : Annual Accounts of Thudiyalur Town Panchayat

Town Investment Plan – Thudiyalur

TNUIFSL

T

N

U

D

P

III

7-12

Final

Report

Table 7-H: Fixed Assets

Rs. in Lakhs

Fixed Assets

20

03

-04

20

04

-05

20

05

-06

20

06

-07

20

07

-08

Land - Gross Block 0.00 0.00 0.00 0.00 0.00

Buildings - Gross Block 81.47 104.40 125.20 137.68 151.62

Storm Water Drains, Open Drains And Culvert 135.61 158.34 173.01 177.51 190.44

Heavy Vehicles - Gross Block 2.23 2.23 2.23 2.23 8.64

Light Vehicles - Gross Block 0.76 0.76 0.76 0.76 0.76

Other Vehicles - Gross Block 0.57 0.57 0.57 0.57 0.57

Furniture & Fixtures Office Equipment Gross

Block 0.22 1.64 1.68 5.79 6.52

Electrical Installations - Lamps - Light 1.45 1.45 3.45 3.45 8.61

Plant And Machineries - Gross Block 11.65 18.77 18.77 18.77 18.77

Roads And Pavements - Concrete - Gross 14.25 14.25 14.25 14.25 18.49

Roads And Pavements - Black Topped - Gross 116.01 155.46 192.75 430.52 668.15

Roads And Pavements - Others - Gross Block 0.62 0.62 0.62 3.78 3.78

Public Fountains 0.00 0.00 0.00 0.00 0.00

Water Supply Head Works, OHT Etc. 80.09 89.83 91.20 92.51 95.74

Ground Water Wells / Deep Bore - Wells 13.44 24.81 25.87 40.22 57.52

Assets Other items - Gross Block 6.56 8.57

Trees 0.02 0.02 0.02 0.02 0.02

TOTAL 458.39 573.15 650.38 934.62 1238.19

Source : Annual Accounts of Thudiyalur Town Panchayat

Figure 7-4 : Source of Funds as on 2007-08

Sources of Funds 2007-08

2% 8%7%

0%

0%

32%

50%

1%

Loans & Advances

Deposits

Government contribution/Mpl fund /

Private Parties/Government Grants

Diversion of funds

Provision for doubtful Collection of

Revenue Items

Accumulated depreciation

Accumulated surplus

Others

Source : Thudiyalur Town Panchayat

Town Investment Plan – Thudiyalur

TNUIFSL

T

N

U

D

P

III

7-13

Final

Report

Figure 7-5 Use of Funds as on 2007-08

Uses of Funds 2007-08

70%

0%0%

4%

0%

0%

26%

Fixed Assets

Project in progress

Tax & Non Tax recoverable

Stock

Others

Receivable/Recoverable

Cash on Hand

Cash in Bank

Source : Thudiyalur Town Panchayat

More than 60% of the funds have been deployed in creation of Fixed Assets. About 77% of the

funds invested have been deployed in Infrastructure relating to storm water drains and road works.

7.6 DEMAND, COLLECTION AND BALANCE

Table 7-I: DCB for the Past 5 years Rs. In Lakhs.

Particulars

2003-0

4

2004-0

5

2005-0

6

2006-0

7

2007-0

8

Property Tax- Demand, Collection and Balance

Total Number of

Assessment 4080 5947 6427 6788 7062

Demand

1.Arrears 3.85 2.40 1.96 0.00 0.70

2.Current 33.38 39.91 47.37 55.95 64.60

3.Total 37.23 42.31 49.33 55.95 65.29

Collection

1.Arrears 3.85 2.40 1.96 0.00 0.14

2.Current 30.98 37.96 47.37 55.95 64.60

3.Total 34.83 40.35 49.33 55.95 64.74

Balance

1.Arrears 0.00 0.00 0.00 0.00 0.56

2.Current 2.40 1.96 0.00 0.00 0.00

3.Total 2.40 1.96 0.00 0.00 0.56

Profession Tax- Demand, Collection and Balance

Town Investment Plan – Thudiyalur

TNUIFSL

T

N

U

D

P

III

7-14

Final

Report

Demand

1.Arrears 2.63 2.75 1.25 0.00 0.00

2.Current 7.40 9.35 10.32 11.28 12.52

3.Total 10.03 12.10 11.57 11.28 12.52

Collection

1.Arrears 1.95 2.75 1.25 0.00 0.00

2.Current 5.33 8.10 10.32 11.28 12.52

3.Total 7.28 10.85 11.57 11.28 12.52

Balance

1.Arrears 0.68 0.00 0.00 0.00 0.00

2.Current 2.07 1.25 0.00 0.00 0.00

3.Total 2.75 1.25 0.00 0.00 0.00

Water charges- Demand, Collection and Balance

Total Number of

Assessments 3930 4146 5270 5326 6004

Demand

1.Arrears 4.40 4.71 4.45 4.16 2.50

2.Current 28.31 30.92 34.81 39.08 39.96

3.Total 32.71 35.62 39.26 43.24 42.46

Collection

1.Arrears 3.98 4.19 3.96 4.16 2.50

2.Current 24.03 26.98 31.14 36.59 37.92

3.Total 28.01 31.17 35.10 40.75 40.42

Balance

1.Arrears 0.42 0.52 0.49 0.00 0.00

2.Current 4.28 3.94 3.67 2.49 2.04

3.Total 4.70 4.45 4.16 2.49 2.04

Others

Library Cess Demand, Collection and Balance

Demand

1.Arrears 0.39 0.24 0.20 0.00 0.07

2.Current 3.34 3.99 4.71 5.60 6.46

3.Total 3.72 4.23 4.91 5.60 6.53

Collection

1.Arrears 0.39 0.24 0.20 0.00 0.01

2.Current 3.10 3.80 4.71 5.60 6.46

3.Total 3.48 4.04 4.91 5.60 6.47

Balance

1.Arrears 0.00 0.00 0.00 0.00 0.06

2.Current 0.24 0.20 0.00 0.00 0.00

3.Total 0.24 0.20 0.00 0.00 0.06

Source : Thudiyalur Town Panchayat

Town Investment Plan – Thudiyalur

TNUIFSL

T

N

U

D

P

III

7-15

Final

Report

The Collection Efficiency of important revenue sources of Thudiyalur Town Panchayat for

the last 5 years is given as under:

Table 7-J : Collection Efficiency (%)

Particulars 20

03

-

04

20

04

-

05

20

05

-

06

20

06

-

07

20

07

-

08

Property Taxes

Arrears 100.00% 100.00% 100.00% 20.11%

Current 92.82% 95.10% 100.00% 100.00% 100.00%

Total 93.56% 95.38% 100.00% 100.00% 99.15%

Professional Taxes

Arrears 74.14% 100.04% 100.00%

Current 72.03% 86.63% 100.02% 100.00% 100.00%

Total 72.58% 89.68% 100.02% 100.00% 100.00%

Water Charges

Arrears 90.39% 89.05% 88.99% 100.10% 100.00%

Current 84.88% 87.27% 89.46% 93.63% 94.90%

Total 85.62% 87.50% 89.40% 94.25% 95.20%

Library Cess

Arrears 100.00% 100.00% 100.00% 20.11%

Current 92.82% 95.10% 100.00% 100.00% 100.00%

Total 93.56% 95.38% 100.00% 100.00% 99.15% Source : DCB of Thudiyalur Town Panchayat

7.7 OUTSTANDING LOAN AND NON-DEBT

LIABILITY

The Outstanding Loan balance and Non-Debt Liability of key components of Thudiyalur Town

Panchayat is represented in the table below:

Table 7-K : Outstanding Loan and Non-Debt Liability Rs. in Lakhs

Sl.No Particulars 2007-08

1.Outstanding Principal on Loans

1 Loans From The Government 16.44

2 Loan From TUFIDCO 0.00

3 Loan From TNUDF 14.52

4 Advance 0.00

Total Loan Outstanding 30.96

2 Non-Debt Liability

1 Library cess 6.63

2 Sales Tax Payable 0.00

3 Income Tax Payable 0.00

4 Interest Payable 0.00

5 Group Insurance Schemes 0.20 Source: Thudiyalur Town Panchayat

Town Investment Plan – Thudiyalur

TNUIFSL

T

N

U

D

P

III

8-1

Final

Report

8888 INSTITUTIONAL CAPACITY ASSESSMENT

8.1 STAFF STRENGTH

Table 8-A : The Staff strength of the Thudiyalur Town Panchayat

Executive Staff Sanctioned Appointed Post Vacant

Executive Officer 1 1 0

Head Clerk 1 1 0

Junior Assistant 3 3 0

Office Assistant 1 1 0

Bill Collectors 2 2 0

Record Clerk 1 1 0

Sanitary Supervisor 1 1 0

Sanitary Workers 27 27 0

Weekly Market Watchman 1 1 0

Night Watchman 1 1 0

Water Supply workers 12 12 0

Source : Thudiyalur Town Panchayat

Staff Salary pay slip for all the sections have been enclosed in the Annexure

8.2 INSTITUTIONAL STRENGTHENING &

CAPACITY BUILDING

The following are some of the steps undertaken by the Town Panchayat for

Institutional Strengthening and Capacity building by introducing a system of

accountability and responsibility within the system

1. Computerization & E-Governance

2. Training

3. Public Grievance Redressal Mechanism

4. Public Private Partnership including Privatisation initiatives

Town Investment Plan – Thudiyalur

TNUIFSL

T

N

U

D

P

III

8-2

Final

Report

5. Tendering Process

• Computerization & E-Governance

The Town Panchayat has initiated steps for computerization of Birth & Death, Salary,

Accounts and Property Tax records

• Training

Some of the details of latest training undergone by the staff are as below:

Bhavani Sagar Training was provided to two Junior Assistants.

• Public Grievance Redressal Mechanism

Complaint register is maintained for key sectors such as Public Health, Water Supply, and

Street Lights. Majority of complaints are related to Water Supply. The Public also approach

their respective ward councilors with their complaints on service delivery system.

• Public Private Partnership including Privatization initiatives

Sector Name of the work Payment Details

Street Light

Fitting of lamps (Materials are

provided by TP and only labour

provided by Private Contractor)

Rs.3500 per person

Water Supply

Plumbing and repair works.

(Materials are provided by TP and

only labour provided by Private

Contractor)

Three persons involved

from Contractor side.

Solid Waste

Management (SWM)

Door to door collection and

segregation

Rs.1400 per month per

person given to 50

women belonging to

Self Help Group

Crematorium

Maintenance

Cleaning the burial ground and

performing other rituals inside the

burial ground

Rs.3100 per month to

one person

• Tendering process:

The projects required for the infrastructure works are decided by the Council .The

Engineer prepares the estimate and bids received have to be approved by the elected

members.

Town Investment Plan – Thudiyalur

TNUIFSL 9-1

T

N

U

D

P

III

Final

Report

9999 S W O T

Based on Stake holder’s perception and view points expressed during our

consultation with the local stakeholders and on the basis of assessment done by

the consultants, an attempt has been made to evaluate Strength, Weakness,

Opportunities and threats of the town which is shown below:

Strength

� Thudiyalur lies in close proximity to

Coimbatore metro city.

� Industrial based town lies on NH 67

between Coimbatore and Mettupalayam.

� Proximity to Tourist spots like Ooty,

Marudha malai.

� Model town for Solid Waste Management

� Town has Gassifier Crematorium

� Proposed IT park in its vicinity.

Opportunities

� Improving the Infrastructure status of

the town by merging with Coimbatore

Corporation.

� Creating environment friendly town by

developing green spaces.

� Proposed projects like Pillur water

supply scheme (under implementation)

and model town proposals

Weakness

� Dependent on distant source for water

supply

� Inadequate available land for solid waste

management

� Spacing between the lights is more than

50 meters against 30 meter spacing.

Threats

� Health hazards due to absence of

Underground drainage system

� Pollution due to traffic congestion in

NH 67

Town Investment Plan – Thudiyalur

TNUIFSL

T

N

U

D

P

III

10-1

Final

Report

10101010 STAKEHOLDERS CONSULTATION

10.1 OPERATIONAL WORKING GROUP

The success of the Town Investment Plan depends on the extent of participation

by the various agencies involved in urban governance and service delivery. As it

is very rightly said “Planning is an exercise ‘For’ the people, ‘Of’ the people and

‘By’ the people.” perception and views of the representatives from the Town

Panchayat and various Para-Statal agencies are of paramount importance.

To bring all the agencies involved in urban governance and service delivery

under one platform for the consultation process, Operational Working Group

(OWG) was formed. The first formal meeting was held in Thudiyalur Town

Panchayat on 24th July 2009 and subsequently Stakeholders meeting was held in

29th October 2009. The stakeholders meeting had a wide representation from

1. Administrative members of the Municipality

2. Elected members of the Municipality

3. Representatives from Slums /SC /ST

4. Senior Citizens

5. Self Help Groups

6. Women Groups

7. NGO members

8. Officials from Para-Statal agencies

Town Investment Plan – Thudiyalur

TNUIFSL

T

N

U

D

P

III

10-2

Final

Report

Figure 10-1 : First Formal Meeting on 24h July 2009

During the stakeholders meeting, the Consultants made a presentation on the

current status of the Thudiyalur Town in terms of Infrastructure, Financial and

Institutional aspects, findings from Rapid Urban Assessment and demand

assessment.

Further, projects already identified by Thudiyalur Town Panchayat and

additional projects proposed by the Consultants based on the Demand Supply

Gap analysis taking into consideration current and future needs and

requirements were also presented and discussed during the meeting. Sector wise

Capital Investment requirements and its phasing were also presented.

During the presentation and subsequent interaction, many ideas and suggestions

were made and the same has been encapsulated below and the same has been

considered and incorporated in this Report.

Town Investment Plan – Thudiyalur

TNUIFSL

T

N

U

D

P

III

10-3

Final

Report

Table 10-A: Suggestions and projects

Physical

Infrastructure Sector Components Key Suggestions / Projects identified

Water Sources • Dependent on Pillur dam for water sources

Head works and

Pumping main • Maintained by TWAD

ESR / GSR • Creating 1 lakh litre capacity OHT Water Supply

Distribution Network • Need to provide additional distribution

network as the demand rises.

Underground Drainage • DPR for UGD has to be prepared

Public Toilets • Not required Sewerage and

Sanitation Pay and Use Toilets • Not required

Renovating existing

drains • Nil

Storm Water

Drainage Creating New Drain

• Creating drainage line in MTP Main Road

from VCS Nagar to Subramaniyam

Palayam Main Road for a length of 0.6

Km

• Creating drainage line in Mullai Nagar

Cross Roads for a length of 0.6 Km

• Creating drainage line in VCS Nagar

South Side Cross Roads for a length of

1.05 Km

• Creating drainage line in VCS Nagar

North Side Cross Roads for a length of

1.1 Km

• Need to provide additional drains as the

demand rises

Roads Kutcha road

upgradation

• Converting 6.1 Km kutcha road into BT

road

Town Investment Plan – Thudiyalur

TNUIFSL

T

N

U

D

P

III

10-4

Final

Report

Pucca road

improvement

• Cheran Colony Middle Cross Roads for a

length of 0.62 Km

• Cheran Colony West Side Cross Roads for

a length of 0.62 Km

• Cheran Colony East Side Cross Roads for

a length of 0.62 Km

• Cheran Colony North Side Cross Roads

for a length of 0.62 Km

Building New Roads /

Links • Not required

Bye pass / Highway

projects

• Mettupalayam road needs to be widened

(Highway – Implementing agency)

Traffic Management /

Junction Improvement

• Creating foot path in Railway station Road

• Creating foot path in Subramaniam

palayam main road from Mahalakshmi

Bakery to Subramaniam palayam School

Traffic and

Transportation

Bus stand / railway

station Imp • Not required

Door to Door

collection and

Segregation

• Procuring segregation bins for each

assessments

Man power /

Privatisation

• Procuring protective gear among

conservancy workers

Vehicle requirements • Not required

Dumping site /

Compost yard

• Dumping site is insufficient. Suggested

option and solution is to use Coimbatore

Corporation’s dumping site in future after

getting prior approval from them.

Solid Waste

Management

User Charges • Possible from industries and commercial

establishments

Town Investment Plan – Thudiyalur

TNUIFSL

T

N

U

D

P

III

10-5

Final

Report

Public Awareness • Awareness about segregation bins and

protective gear is required.

Street Lighting Energy Saving

Initiatives • Needs to be adopted.

Social

Infrastructure Sector Components Key Suggestions

Proposed parks and

Playgrounds

• Creating parks in Balaji Nagar,

Srimurugan Nagar, Sai Nagar, Visanatha

puram, 2nd Ward Thondupatti, Appanaican

palayam near tank, Mullai nagar, Thirupathi

nagar and V.C.S. nagar

• Creating road side park in Railway station

road, in Muthunagar roads, from Cheran

Colony to Viswanathapuram

Parks and

Playgrounds

Approved layout for

parks and

playgrounds

• Creating parks in VP nagar, Cape Town,

Swati garden, Muthammal layout.

• Implementing Urban forestry programmes

Infrastructure

Improvement

• Developing Shandy by carrying out

following works

- Construction of shed at weekly shandy

(Imported colour coated G.I.sheet)

- Construction of platform at weekly shandy

- Construction of drainage at weekly shandy

area

- Cement concrete road

- B.T. Road for shandy area

- Street lights

Daily / Weekly

Market

Revenue

Enhancement

• Construction of Shopping Complex at

weekly shandy East side South facing Part-I

Town Investment Plan – Thudiyalur

TNUIFSL

T

N

U

D

P

III

10-6

Final

Report

measures (Vellakinar Road)

• Construction of Shopping Complex at

weekly shandy East side South facing Part-

II (Vellakinar Road)

• (or) constructing city center under PPP on

this site.

Community hall Creating Community

hall

Constructing community hall in

subramaniyam palayam and in Raju garden

Slaughter House Slaughter house

improvement scheme • Creating modern slaughter house

Municipal

building

Creating new blocks /

Improving existing

blocks

• Not required

Burial ground

Improvement

• Burial ground improvement in

Appanaikan palayam and in Subramaniam

palayam

Burial grounds /

Gasifier

Gassifier provision • Already developed

Urban Finance /

Institutional

Framework

Sector Components Key Suggestions

Areas for

privatization

• The Town Panchayat has initiated

privatization in most of the sectors

Privatization /

Cost Recovery User charges

• The TP can look to collect user

charges from the Non-Domestic assesses

and after providing adequate awareness

can start collecting from the Domestic

assesses for Solid Waste Management

Town Investment Plan – Thudiyalur

TNUIFSL

T

N

U

D

P

III

10-7

Final

Report

10.2 PRIORITY BASED ON OWG OPINION

SURVEY

Projects identified both by the Town Panchayat and by the consultants cannot be

taken at one step for implementation due to constraints like finance, institutional

capabilities etc. Thus, phasing of the projects based on stake holder’s priority

could be a viable option for implementing projects. During stakeholders

meeting, they have been asked to prioritize the sectors pertaining to Physical

infrastructure, Social Infrastructure and Environment through a survey called

City Opinion survey and is presented in a scale of 0-1001 scores.

10.2.1 PHYSICAL INFRASTRUCTURE PRIORITY

Based on the opinion survey conducted during stakeholders meeting,

Stakeholders have given priority to the sectors related to Physical infrastructure

on the following order:

1. Drinking Water Supply

2. Under Ground Drainage

3. Road Network

4. Street lighting

5. Solid Waste Disposal

6. Storm Water Drainage

7. Parking facilities

1 Sector is highly prioritized by the Stakeholders if it gets 100 score and least prioritized if it

gets 0 score.

Town Investment Plan – Thudiyalur

TNUIFSL

T

N

U

D

P

III

10-8

Final

Report

Figure 10-2 Sector prioritization by the Stakeholders (Physical Infrastructure)

69.55

100.00

76.36

40.45

41.36

47.73

12.73

0 20 40 60 80 100

Road

Drinking Water

UG Drainage

SW Drainage

SW Disposal

Street Lighting

Parking Facilities

10.2.2 SOCIAL INFRASTRUCTURE PRIORITY

Based on opinion survey conducted during stakeholders meeting, they have

given priority to the sectors related to Social infrastructure on the following

order:

1. Health facilities (Maternity Center)

2. Parks, Playfields

3. Schools / Colleges

4. Community Hall

5. Public Transport

6. Burial ground / Gassifier crematorium

7. Market

8. Slaughter House

Town Investment Plan – Thudiyalur

TNUIFSL

T

N

U

D

P

III

10-9

Final

Report

Figure 10-3 Sector prioritization by the Stakeholders (Social Infrastructure)

87.7653.16

67.09

100.0064.14

46.84

2.95

37.13

0.00 20.00 40.00 60.00 80.00 100.00

Park and Playfield

Public Transport

Schools & Colleges

Health facilities

Community Hall

Burial Ground/Crematorium

Slaughter House

Daily Market

10.2.3 ENVIRONMENTAL ISSUES

Based on opinion survey conducted during stakeholders meeting, they have

given priority to the Environmental issues on the following order:

1. Air Pollution

2. Water Pollution

3. Land Pollution

4. Noise Pollution

5. Open space inadequacy in the form of parks / Playgrounds

6. River/Lake

7. Drought

8. Floods

Town Investment Plan – Thudiyalur

TNUIFSL

T

N

U

D

P

III

10-10

Final

Report

Figure 10-4 Sector prioritization by the Stakeholders (Environmental Issues)

32.95100.00

86.71

76.88

61.85

52.60

32.37

37.57

0.00 20.00 40.00 60.00 80.00 100.00

River/Lake

Air Pollution

Water Pollution

Land Pollution

Noise Pollution

Open space

Floods

Drought

Figure 10-5 Consultation in Thudiyalur Town Panchayat

Town Investment Plan – Thudiyalur

TNUIFSL

T

N

U

D

P

III

11-1

Final

Report

11111111 ASSET MANAGEMENT PLAN

Asset Management Plan involves maintenance management for preventive and

predictive maintenance, equipment recording and tracking, replacement parts

inventory, and maintenance labor scheduling. The goal of asset management is

to optimize asset use and manage all maintenance efforts involved in making

assets as reliable, accurate, and efficient as possible. Asset management Plan is

the plan developed for one or more physical assets within the Town Panchayat

that combines multi disciplinary management techniques including technical and

financial over the life cycle of the asset to a specified level of service in a most

cost effective manner.

The key aspects of asset management plan therefore involve asset inventory,

information of assets owned by the Town Panchayat and appropriate strategy to

manage the assets and increase the productivity of the same. The asset

management plan is therefore critical for maintaining, upgrading and operating

physical assets in a cost effective manner.

Thudiyalur Town Panchayat has several assets that require regular maintenance

for sustenance of reasonable service delivery levels. Given the high impact of

the O&M expenses on the finances of the Town Panchayat, it is prudent to

undertake a proper review of the assets under its control. This would aid in

identifying the revenue generating assets as well as the ones that are causing a

drain on municipal revenues. A comprehensive asset management plan aids in

achieving the same.

Town Investment Plan – Thudiyalur

TNUIFSL

T

N

U

D

P

III

11-2

Final

Report

11.1 LIST OF ASSETS:

The assets of Thudiyalur Town Panchayat can be classified as assets relating to

basic physical infrastructure such as water supply, roads, storm water drains,

street lights, light and heavy vehicles etc and those relating to social

infrastructure which include community halls, maternity centers, burial grounds

etc. Among basic physical infrastructure only water supply services can be

considered revenue generating as the Town Panchayat is able to collect taxes,

connection charges, initial deposit charges and metering/tap rate charges and

hence expenses are met mainly through dedicated water supply fund set up for

the purpose. With regard to social infrastructure, Thudiyalur has revenue

generating assets like Markets, shopping complex, bus stand, taxi stand,

slaughter house, cycle stand/taxi stand, pay & use toilets, etc currently with the

panchayat and others such as burial grounds, community hall, slaughter house,

parks, public toilets, maternity centre etc; are not revenue generating or revenue

generation is extremely nominal and may not be self sustaining. The panchayat

earns a substantial income of Rs.29.60 Lakhs (2007-08) from the remunerative

social assets .Some of the social infrastructure is required to be provided by the

Town Panchayat as the functions remain obligatory functions of the Town

Panchayat and also help to fund the non remunerative activities of the Town

Panchayat. These are also required to maintain the cleanliness and sanitation of

the city.

Town Investment Plan – Thudiyalur

TNUIFSL

T

N

U

D

P

III

11-3

Final

Report

The various physical and social infrastructure of the Town Panchayat are listed below:

Table 11-A: Details of various social & physical infrastructure assets

Particulars Unit

Area

/ Description Details / Location

Office Buildings 1

3664 Sq.m. (Comprising office Building, conference hall and godown)

Railway Station Road, Ward No.7, Thudiyalur

Commercial Complexes 3 16776 Sq.m 46 shops inside the complex

Weekly Market

1 72 Shops

Public Toilet & Pay and Use Latrines

1 Pay & Use & 12 Public Toilets

Pay & Use Inside the Weekly Market

Public Toilets:-

� Subramania Palayam – (3 Numbers)

� Appanaicken Palayam –( 4 Numbers)

� Anna Colony-(2 Numbers) � Idiyara Road (2 Numbers) � Muthu Nagar( 1 Number)

Slaughterhouse 1 500 Sq.Ft. Inside the Weekly Market (Not in use)

Community Hall 1 129.60 Sq.m Appanaickenpalayam (Presently functioning as a noon meal center)

Parks & Play Grounds 6

� V.K.L Nagar W.no.9 � Cheran Colony W.No.4, � Park Avenue W.No,9, � Easwar Park W.No.2, � Balasubramanian Nagar

W.No.12 � S.P.Nagar WNo.9.

Overhead Tank 3

� Thudiyalur- 3 Lac Litres � Subraminiapalayam – 2 Lac

Litres � Appanayaken Palayam – 1 Lac

Litres

Burial Ground 4

� Subramaniya Palayam – 50 Cents

� Appanaicken Palayam- Opposite to Compost Yard -1 Acre

� Appanaicken Palayam-

Town Investment Plan – Thudiyalur

TNUIFSL

T

N

U

D

P

III

11-4

Final

Report

Kaliamma Colony-50 Cents � Thudiyalaur Crematarium –

Gassfier -86.25 Cents

Number of Motor Vehicles for different

departments (Including SWM) 4

Tipper – 1 No., Tractor – 1 No., Tiller – 1 No, Sanitation Tanker – 1 No and 24 Push Carts

Source: Thudiyalur Town Panchayat

11.2 OPERATIONS AND MAINTENANCE

The revenue generation and the operations and maintenance activities currently being

followed and suggestions for comprehensive Asset Management including ways and

means to meet the expenses involved & make it a self sustaining for various assets

are listed below:-

11.2.1 O&M OF SOCIAL INFRASTRUCTURE ASSETS

Table 11-B: O&M and Revenue generation

Asset

Average

Annual

income

Current O&M

practice Recommendations

Markets Rs.10.51 Lakhs

Adhoc basis

Periodic inspection and

maintenance is required

As per OWG discussions and

our demand estimation, a

market improvement in

Weekly Shandy is proposed in

the CIP costing for

Rs.83.30Lakhs

Commercial Complex Rs.11.87 Lakhs

Adhoc basis

- As thudiyalur is very nearer

to the coimbatore city there is

a huge demand for

commercial development in

this area. Hence the

Town Investment Plan – Thudiyalur

TNUIFSL

T

N

U

D

P

III

11-5

Final

Report

consultants and consultation

with the OWG members had

proposed for new shopping

complex in weekly shandy and

a City Center totaling to a

project cost of Rs.597 Lakhs.

The TP should take adequate

measures in periodic

maintenance of these assets.

Office Building Nil Adhoc basis

-Periodic inspection and

maintenance is required

- The TP is planning to

undertake some renovation

works with a cost of Rs.35

Lakhs.

Slaughter House Nil NA

As per OWG discussion, TP

requires a slaughter house

which is estimated with a

capital cost of Rs.60 Lakhs in

the CIP

Community Hall Nil Ad hoc basis

As per OWG discussion, TP

requires two slaughter houses

one at Appanaicken palayam

and another at Anna Colony

which is estimated with a

capital cost of Rs.25 Lakhs in

the CIP

Pay and Use Latrines Rs.0.40 Lakhs

Ad hoc basis

Some of the routine

maintenance work can be

handed over to SHGs with

only major maintenance/new

work to be taken up by the

Town Investment Plan – Thudiyalur

TNUIFSL

T

N

U

D

P

III

11-6

Final

Report

Panchayat.

Burial Ground NIL Ad hoc basis

Periodic annual maintenance

can sustain the quality of the

asset

The TP already has a Gassifier

Crematorium.

TP requires Burial ground

improvement in Appanaikan

palayam and in Subramaniam

palayam with a capital cost of

Rs.21 Lakhs in the CIP

Parks & Play Grounds / Gardens

Nil

Can be maintained jointly with

private sector or maintained

exclusively by the private

sector on sponsorship basis.

Source: Analysis based on Information provided by Thudiyalur Town Panchayat

11.2.2 O&M PHYSICAL INFRASTRUCTURE

Operation and Maintenance of the assets related to Physical and socio-economic

infrastructure is divided under two heads;

• To maintain the existing assets for the next five years and

• To maintain the assets proposed to be created under various capital works

proposed.

Since the O & M of the existing assets related to Socio- Economic Infrastructure has

already been assessed in the above sections of this chapter, the O & M of the existing

physical Infrastructure assets and the proposed O & M for the capital works identified is

broadly discussed in this section. Past growth trends in O&M expenses relating to

existing physical infrastructure and O&M rates as a percentage of capital cost assumed

for the proposed capital works are tabulated below:

Town Investment Plan – Thudiyalur

TNUIFSL

T

N

U

D

P

III

11-7

Final

Report

Table 11-C Past Growth trends in O & M expenses relating to key physical

infrastructure

Description Current level

Existing Assets CAGR of growth rate from 2003-04 to 2007-08 (%)

Water Supply

Operating Expenses 17.19%

Power Charges for Head Water Works

18.61%

Maintenance expense for Water Supply Works

Fluctuating Trend

Solid Waste Management

Heavy vehicle expenditure Increasing Trend

Street lighting

Maintenance Expense for Street Lights

25.24%

Power charges for street lighting 14.62%

Table 11-D O&M rates as a % of proposed capital works

Description Current level Assumption

FOR CAPITAL WORKS

Water Supply NA 6% of the project cost

Sewerage & Sanitation NA 4% of the project cost

Roads and Traffic Management

NA 3% of the project cost

Storm Water Drainage NA 2% of the project cost

Solid Waste Management NA 10% of the project cost

Street Lighting NA 5% of the project cost considering Energy saving mechanism

Slum up gradation NA 1% of the project cost

Others NA 2% of the project cost

Town Investment Plan – Thudiyalur

TNUIFSL

T

N

U

D

P

III

11-8

Final

Report

11.3 AMP - RECOMMENDATIONS

The following are some of the suggestions with regard to formulation and

implementation of a comprehensive asset management plan:-

11.3.1 ASSET REGISTER

A comprehensive Asset register needs to be maintained containing details of the list of

assets, year and cost of acquisition, particulars such as the location, size of the

area/building, ownership records and all supporting documents required for the same.

These details are required for assessing the condition of the asset. The reforms

programme under TNUDP has initiated the process of computerizing and digitalizing

the asset inventory for all municipalities in Tamil Nadu. Computerization of asset

register is required with focus on proper designing, testing, installing a database

management system for municipal assets. Data thus compiled would need to be

classified on the basis of sector specific infrastructure facilities, land and properties etc

11.3.2 ASSET VALUE AND LIFE CYCLE

MANAGEMENT

The Town Panchayat needs to determine the value of various assets in regular intervals.

As all assets have a limited life expectancy, concerted efforts need to be undertaken by

the Town Panchayat on regular basis before investing further in a new asset or up

gradation of the existing assets. In case of an asset (service) that is handed over to a

private contractor for O&M, periodic review and inspection needs to be made to prevent

misuse and damage to the assets.

Town Investment Plan – Thudiyalur

TNUIFSL

T

N

U

D

P

III

11-9

Final

Report

11.3.3 SUSTAINABILITY

Sustainable management of assets is an important element of asset management plan.

Sustainable development has been defined as “meeting the needs of present generation

without compromising the ability of future generations to meet their own needs”. A

long term financial plan to provide necessary resources to operate, rehabilitate and

ultimately replace the asset at the optimal time to achieve lowest life cycle cost is

required. Preventive and operational maintenance at regular intervals can prevent higher

cost associated with the full replacement of the asset. Such a plan would ensure that the

current users pay a fair share for the service they receive so the future users do not have

the burden to pay a higher cost for the same level of the service. Sustainable

management calls for a contribution from the users to meet partially or fully the O&M

cost associated with the utilization of assets. Hence user charges and fees is critical for a

sustainable and a successful asset management programme

11.3.4 INTEGRATION OF TECHNICAL AND

FINANCIAL PLANS

An integrated plan combining technical aspects (to minimize life cycle cost & reduce

the risk level) and financial aspects (Financial plan) are required to quantify the level of

service and the cost associated with the same. The technical and financial plans need to

be flexible enough to suit the changing requirements of the public.

11.3.5 CONDITION ASSESSMENT SURVEY (CAS)

The Town Panchayat could look to undertake CAS for various assets owned by the

ULB, which could bring to light the deficiencies in a system or a component, the extent

of defects, estimated cost of repairs and the prioritizing the work to be undertaken. This

Town Investment Plan – Thudiyalur

TNUIFSL

T

N

U

D

P

III

11-10

Final

Report

systematic review could enhance the life of the asset and minimize huge capital outlay

on account of delay in taking remedial actions.

11.3.6 RISK ASSESSMENT

Asset management needs to take into account various risk factors such as financials,

environmental, regulatory, legal, public health and safety.

11.3.7 MONITORING AND EVALUATION

To optimize an asset management plan, performance of the assets and rehabilitation

strategies should be monitored regularly, and adjustments made at the appropriate stage

in the asset life cycle to achieve an acceptable balance between cost and the

performance (Level of service). It is also imperative to monitor and take damage control

measures when the Town Panchayat takes up any development works to prevent

damage to the other assets of the Town Panchayat. Prioritizing the works to be

undertaken can prevent unnecessary maintenance and capital cost.

11.3.8 BUDGETING

A regular budgeting exercise regarding the possible O&M cost for various assets needs

to be undertaken by the Town Panchayat. There should be a clear link to the financials

plans and the budgeting exercise undertaken by the Town Panchayat. An Asset

Management Plan should incorporate expenses relating to maintenance, renewal and

augmentation of the asset of the Town Panchayat.

11.3.9 TRAINING IN DATABASE MANAGEMENT

All the above requires proper training to the concerned staff. Training would involve

various issues such as methods of simplified updation of data, methods of monitoring

and follow up and training in issues relating to infrastructure facilities management,

land use, litigation, encroachment etc

Town Investment Plan – Thudiyalur

TNUIFSL

T

N

U

D

P

III

12-1

Final

Report

12121212 CONSOLIDATED ISSUES

The issues identified during Rapid Urban Assessment and the issues indicated

by the review committee and stakeholders were consolidated sector wise and are

presented below:

Table 12-A : Consolidated Issues

Sector Issues

Water Supply

• Per capita supply is low (57%) against the standard norm of

70%

• 26% of the roads are not covered by distribution network

Storm water drainage • 33 percent roads are not covered by Storm Water Drains

Roads, Traffic and

Transportation

• Mettupalayam road is heavily congested.

• 9% of the roads are kutcha.

Solid Waste

management

• Town has inadequate land for disposal and treatment

considering the future demand.

• Town has no scientific landfill site.

Street lighting

• Spacing between lights is around 54 meters against the standard

spacing of 30 meters

• Most of the switches are manually operated

• Most of the fittings have conventional copper chokes.

Socio-Economic

Infrastructure

• 23 approved layouts are undeveloped

• Weekly market lacks infrastructure facilities

• Town has no Slaughter house

• 3 burial grounds lacks infrastructure facilities

• Town has inadequate revenue generating commercial complexes

even though it is located in close proximity to Coimbatore

metropolitan area.

Town Investment Plan – Thudiyalur

TNUIFSL

T

N

U

D

P

III

13-1

Final

Report

13131313 STRATEGIC PLANNING

In order to address the issues identified during Rapid Urban Assessment stage

and during Review Committee meeting as well as during the OWG meeting, the

sectoral strategies and action plans have been proposed in this stage. Such action

plans and strategies are converted into projects and are phased out based on the

priority suggested by the review committee members which is explained in the

subsequent chapters.

13.1 ACTION PLAN FOR SECTORAL

DEVELOPMENT

Action plans for improving the existing situation of various sectoral components

as well as for creating new infrastructure facilities have been formulated in

consultation with the Operational Working Group members and are listed

below:

Sector Action plan

Land Use and

Growth

Management

• Preparing development plan for Thudiyalur Town Panchayat area for

the next twenty five years

• Setting up local planning authority or making provision to include

Thudiyalur in Coimbatore local planning area.

Water

Supply

• CWSS for Thudiyalur

• Creating Distribution network for 21.8 Km by 2023-24

• Creating 1 lakh litre capacity OHTs by 2013-14

Sewerage and

Sanitation • UGD Scheme for Thudiyalur Municipal area

Storm water

drainage

• Creating Pucca drains for 18.53 Kms between 2014-15 and 2023-24

• Creating drainage line in MTP Main Road from VCS Nagar to

Town Investment Plan – Thudiyalur

TNUIFSL

T

N

U

D

P

III

13-2

Final

Report

Sector Action plan

Subramaniyam Palayam Main Road for a length of 0.6 Km

• Creating drainage line in Mullai Nagar Cross Roads for a length of

0.6 Km

• Creating drainage line in VCS Nagar South Side Cross Roads for a

length of 1.05 Km

• Creating drainage line in VCS Nagar North Side Cross Roads for a

length of 1.1 Km

Solid Waste

Management

• Contribution to scientific land fill site

• Public awareness for Waste segregation and D-D collection and

awareness programme for conservancy workers about protective gear

• Procuring segregation bins for each assessments

• Procuring protective gear among conservancy workers

Traffic and

Transportation

• Converting 6.1 Km kutcha road into BT road

• Cheran Colony Middle Cross Roads for a length of 0.62 Km

• Cheran Colony West Side Cross Roads for a length of 0.62 Km

• Cheran Colony East Side Cross Roads for a length of 0.62 Km

• Cheran Colony North Side Cross Roads for a length of 0.62 Km

• Creating additional 4.4 Km by 2023-24.

• Creating foot path in Railway station Road

• Creating foot path in Subramaniam palayam main road from

Mahalakshmi Bakery to Subramaniam palayam School

Street Lighting

• Replacing 40W Tube lights into 36 W

• Installing electronic chokes for all tube light fittings

• Replacing 250 W 146 Nos SVL with (4 X 24) W T5 lamps

• Installing 384 light fittings with poles (1/3rd of the future demand)

Socio-Economic

Infrastructure

• Construction of Shopping Complex at weekly shandy East side South

facing Part-I (Vellakinar Road)

• Construction of Shopping Complex at weekly shandy East side South

Town Investment Plan – Thudiyalur

TNUIFSL

T

N

U

D

P

III

13-3

Final

Report

Sector Action plan

facing Part-II (Vellakinar Road)

• Construction of City Center on the same weekly shandy south side

under PPP (If TP succeed in getting the developer)

• Constructing community hall in subramaniyam palayam and in Raju

garden

• Developing parks in Balaji Nagar, Srimurugan Nagar, Sai Nagar,

Visanatha puram, 2nd Ward Thondupatti, Appanaican palayam near

tank, Mullai nagar, Thirupathi nagar and V.C.S. nagar

• Developing parks in VP nagar, Cape town, Swati garden, Muthammal

layout

• Developing Shandy by carrying out following works

- Construction of shed at weekly shandy (Imported colour coated G.I.sheet)

- Construction of platform at weekly shandy

- Construction of drainage at weekly shandy area

- Cement concrete road

- B.T. Road for shandy area

- Street lights

• Creating modern slaughter house

• Burial ground improvement in Appanaikan palayam and in

Subramaniam palayam

• Creating road side park in Railway station road, in Muthunagar

roads, from Cheran Colony to Viswanathapuram

14-1

Tow

n Investment P

lan – Thu

diyalur

TNUIFSL

T

N

U

D

P

III

Final

Report

14

14

14

14

CAPITAL INVESTMENT PLAN

The C

apital Investment Plan (CIP) identifies the investment requirem

ent of the tow

n for the next fifteen year period

without taking into consideratio

n the financial feasibility of the projects, w

hich w

ould be covered in Financial O

perating

Plan (FO

P). Thudiyalur investment requirem

ent for the next fifteen year period

is Rs. 2783.40 lakhs. Consolid

ated Sector

wise Investment requirement for Thu

diyalur Tow

n Panchayat is show

n in Table 14-A.

Table 14-A : Consolidated Sector wise Capital Investment requirem

ents

Sector

Total Investment

in Lakhs

Percentage

share

2009-10 to

2013-14

2014-15 to

2018-19

2019-20 to

2023-24

Water Sup

ply

702.63

25

.24

615.03

43

.80

43.80

Sewerage and Sa

nitation

70

0.00

25

.15

700.00

0.00

0.00

Storm W

ater Drainage

415.65

14

.93

45.05

185.30

18

5.30

So

lid W

aste M

anagem

ent

300.88

10

.81

84.71

104.54

11

1.63

Roads, T

raffic and Transportation

246.90

8.87

18

9.70

0.00

57

.20

Street Lighting

45.09

1.62

22

.05

11.52

11.52

Slum

s and Urban Poverty

0.00

0.00

0.00

0.00

0.00

So

cio-Econo

mic Infrastructure

372.25

13

.37

271.25

71

.00

30.00

Total

2783.40

100.00

1927.79

416.16

439.45

% Share

69.26

14.95

15.79

14-2

Tow

n Investment P

lan – Thu

diyalur

TNUIFSL

T

N

U

D

P

III

Final

Report

Figure 14-1 Sector wise percentage share

Socio

-Econom

ic

Infrastr

uctu

re

13%

Str

eet

Lig

hting

2%

Roads,

Tra

ffic a

nd

Tra

nsport

ation

9%

Solid

Waste

Managem

ent

11%

Sto

rm W

ate

r D

rain

age

15%

Sew

era

ge a

nd

Sanitation

25%

Wate

r S

upply

25%

14.1

PHYSICAL INFRASTRUCTURE

During Review Com

mittee m

eetin

gs, stakeholder consultation m

eetin

gs and

on the basis of dem

and supply gap analysis,

various works have been id

entified under different sectors like W

ater Supply, Sew

erage, Solid W

aste M

anagem

ent, Storm

Water Drains, Roads and

Street L

ighting which are classified as Phy

sical Infrastructure sectors. T

he Bud

get E

stim

ates for

the identified projects have been carried ou

t based on

TWAD Board Stand

ard Schedule of Rates, market rates and with

some assumptions on the technical aspects and wherever the estim

ates are available w

ith Tow

n Panchayat the same has

been con

sidered for those works.

14-3

Tow

n Investment P

lan – Thu

diyalur

TNUIFSL

T

N

U

D

P

III

Final

Report

14.1.1 WATER SUPPLY

Various w

orks have been identified under Water Sup

ply Se

ctor on the basis of Stakeho

lder’s suggestion and on the basis

of D

emand Su

pply G

ap analysis. The w

orks identified and phase wise investment for the variou

s works are listed in

Table 14-B.

Table 14-B : Project List and Budget Estimates for Water Supply W

orks

S.No

Project Components

Capital Investment

In Lakhs

2009-10 to

2013-14

2014-15 to

2018-19

2019-20 to

2023-24

A

Water Supply

1 CWSS

for Thu

diyalur

561.23

561.23

0.00

0.00

2 Creating Distribution netw

ork for 21.8 Km

by 202

3-24

13

1.40

43.80

43.80

43.80

3 Creating 1 lakh litre capacity OHTs by

2013

-14

10.00

10.00

0.00

0.00

Sub Total

702.63

615.03

43.80

43.80

It is suggested that Thu

diyalur Tow

n Panchayat has to undertake w

ater aud

it, energy audit and leak dedu

ction studies to

minim

ize Unaccounted W

ater Flow (UFW) and minim

ize the energy exp

enditure. The goals and service outcomes based

on th

e proposed strategy for the horizon period is presented below

.

14-4

Tow

n Investment P

lan – Thu

diyalur

TNUIFSL

T

N

U

D

P

III

Final

Report

Table 14-C : Goals and Service outcomes related to W

ater Supply sector

Goals

2009-10

Up to

2013-14

2014-15 to

2018-19

2019-20 to

2023-24

Network coverage in

% of a

vailable road network

74

85

95

100

Per Capita Supply in LPC

D

57

70

70

70

Service connectio

ns in

% of assessments

84

85

85

85

To address system

rehabilitation in the up

coming years, m

apping and

establishing a GIS system is pertinent to detail ou

t

system

location, characteristics, age and condition. T

his wou

ld enable identifying dilapidated sections of the network and

those that require replacement.

14.1.2 SEWERAGE AND SANITATION

Thudiyalur Tow

n Panchayat has prop

osed U

nder G

roun

d Drainage scheme in the M

odel Tow

n Proposals at an estim

ated

cost of approx

imately 70

0 lakhs. Detailed list of works, costin

g and ph

ase wise investment p

lan is given in

Table 14-D.

Table 14-D

: Project List and Budget Estim

ates for Sew

erage and Sanitation W

orks

S.No

Project Components

Capital Investment

In Lakhs

2009-10 to

2013-14

2014-15 to

2018-19

2019-20 to

2023-24

B

Sew

erage and Sanitation

4 UGD Schem

e for Thudiyalur Mun

icipal area

700.00

70

0.00

0.00

0.00

Sub Total

700.00

700.00

0.00

0.00

14-5

Tow

n Investment P

lan – Thu

diyalur

TNUIFSL

T

N

U

D

P

III

Final

Report

14.1.3 STORM W

ATER DRAINAGE

Und

er Storm

Water Drainage sector, w

orks like construction of new

drains identified during Rapid Tow

n Assessm

ent and

during stake holder’s consultation are con

sidered. The works id

entified and phase wise investments are listed below

.

Table 14-E : Project List and Budget Estim

ates for Storm

Water Drainage works

S.No

Project Components

Capital Investment

In Lakhs

2009-10 to

2013-14

2014-15 to

2018-19

2019-20 to

2023-24

C

Storm W

ater Drainage

5 Creating Pu

cca drains for 18.53 Kms between

2014-15 and 2023-24

370.60

0.00

18

5.30

18

5.30

6 Creating drainage line in

MTP Main Road from

VCS Nagar to

Sub

ramaniyam

Palayam

Main Road

for a length of 0.6 Km

9.40

9.40

0.00

0.00

7 Creating drainage line in

Mullai N

agar Cross

Roads for a length of 0.6 Km

7.25

7.25

0.00

0.00

8 Creating drainage line in

VCS Nagar South Side

Cross Roads for a length of 1.05 Km

14.00

14.00

0.00

0.00

9 Creating drainage line in

VCS Nagar North Side

Cross Roads for a length of 1.1 Km

14.40

14.40

0.00

0.00

Sub Total

415.65

45.05

185.30

185.30

14-6

Tow

n Investment P

lan – Thu

diyalur

TNUIFSL

T

N

U

D

P

III

Final

Report

The goals and service outcomes based on the prop

osed strategy for the ho

rizon period

is presented in

Table 14-F.

Table 14-F : Goals and Service outcomes related to Storm

Water Drainage sector

Goals

2009-10

Up to

2013-14

2014-15 to

2018-19

2019-20 to

2023-24

Storm W

ater Drainage Cov

erage (%

of road leng

th)

67

72

86

100

14.1.4 SOLID W

ASTE M

ANAGEMENT

Protective gear for conservancy workers is proposed in such a w

ay that workers w

ould get protective gear each year. In

additio

n, H

ousehold segregation bins (2 N

os) are proposed for each assessment in Thu

diyalur Tow

n Panchayat with

due

consideration given to projected assessm

ents also. Househo

ld segregatio

n bins are propo

sed to be replaced once in 5 years.

Awareness drive to improve Door-Door collection efficiency, w

aste segregation efficiency and aw

areness about the

impo

rtance of protectiv

e gear amon

g the conservancy workers is proposed to be conducted by th

e Tow

n Panchayat. Tow

n

Panchayat’s contribution for setting u

p region

al land

fill

site in

association

with

nearby

Mun

icipalities and

Tow

n

Panchayats is also con

sidered. The w

orks identified and phase wise investment for the variou

s works are listed in Table

14-G

14-7

Tow

n Investment P

lan – Thu

diyalur

TNUIFSL

T

N

U

D

P

III

Final

Report

Table 14-G

: Project List and Budget Estim

ates for Soild W

aste Managem

ent works

S.No

Project Components

Capital Investment

In Lakhs

2009-10 to

2013-14

2014-15 to

2018-19

2019-20 to

2023-24

D

Solid W

aste Managem

ent

10

Con

tribution to scientific land

fill site

10

.37

0.00

10

.37

0.00

11

Public aw

areness for Waste segregation

and

D-D

collectio

n and aw

areness prog

ramme for

conservancy workers abo

ut protective gear

5.00

5.00

0.00

0.00

12

Procuring

segregation bins for each assessm

ents

257.17

70

.26

84.73

102.18

13

Procuring

protective gear amon

g conservancy

workers

28.35

9.45

9.45

9.45

Sub Total

300.88

84.71

104.54

111.63

The goals and service outcomes based on the prop

osed strategy for the ho

rizon period

is presented in

Table 14-H.

Table 14-H

: Goals and Service outcomes related to Solid W

aste Managem

ent works

Goals

2009-10

Up to

2013-14

2014-15 to

2018-19

2019-20 to

2023-24

Doo

r to Doo

r Collection (%

of assessments cov

ered)

Covered in

all w

ards

100

100

100

Source Segregation

(% of assessments cov

ered)

Covered in

all w

ards

100

100

100

Scientific dispo

sal

0 0

√ √

Collection efficiency in

%

100

100

100

100

14-8

Tow

n Investment P

lan – Thu

diyalur

TNUIFSL

T

N

U

D

P

III

Final

Report

14.1.5 ROADS, TRAFFIC AND TRANSPORTATION

Und

er th

is sector it is proposed to con

vert earthen roads in

to BT roads during the first five year period. Further, foot p

aths

and

road improvem

ent works are p

roposed

after having d

iscussion

with

stakeholders in

stakeholder’s consultation

meetin

g. C

oimbatore - M

ettupalayam highw

ay w

idening project has already been propo

sed by

NHAI to reduce traffic

congestio

n in that im

portant link. F

or bud

get cost estim

ates unit rates per km

length are considered. T

he w

orks identified

and phase wise investment for th

e variou

s works are listed in

Table 14-I.

Table 14-I : Project List and Budget Estim

ates for Roads, Traffic and Transportation works

S.No

Project Components

Capital Investment

In Lakhs

2009-10 to

2013-14

2014-15 to

2018-19

2019-20 to

2023-24

E

Roads, Traffic and Transportation

14

Con

verting 6.1 Km kutcha road in

to BT road

79.30

79.30

0.00

0.00

15

Cheran Colon

y Middle Cross Roads for 0.62 Km

13.85

13.85

0.00

0.00

16

Cheran Colon

y West S

ide Cross Roads for 0.62 Km

13.85

13.85

0.00

0.00

17

Cheran Colon

y East S

ide Cross Roads for 0.62 Km

13.85

13.85

0.00

0.00

18

Cheran Colon

y North Side Cross Roads for 0.62 Km

13.85

13.85

0.00

0.00

19

Creating addition

al 4.4 Km by 20

23-24.

57.20

0.00

0.00

57

.20

20

Creating foot path in Railw

ay statio

n Road

10.00

10.00

0.00

0.00

21

Creating foot path in Sub

ramaniam palayam

main

road from M

ahalakshmi B

akery to Sub

ramaniam

palayam Schoo

l 45

.00

45.00

0.00

0.00

Sub Total

246.90

189.70

0.00

57.20

14-9

Tow

n Investment P

lan – Thu

diyalur

TNUIFSL

T

N

U

D

P

III

Final

Report

The goals and service outcomes based on the prop

osed strategy for the ho

rizon period

is presented in

Table 14-J.

Table 14-J : Goals and Service outcomes related to Roads, Traffic and Transportation sector

Goals

2009-10

Up to

2013-14

2014-15 to

2018-19

2019-20 to

2023-24

Per Capita

road leng

th in

meters

2.4

2.0

1.7

1.5

Percentage of kutcha roads to

total road

leng

th

9 0

0 0

14.1.6 STREET LIGHTING

It is proposed to convert all conventional lights into energy saving lightin

g system

s to save more energy and

reduce carbon

emission

. It is proposed to replace 40

W tub

e lights into 36 W

energy saving lam

ps w

hen the life of existing 40 W lam

p

gets over. It is propo

sed to install electronic chok

es in all fittings. It is further propo

sed to replace 250 W

Sod

ium V

apor

with (4X24) W T5 lamps. T

he tender process for procurement o

f T5 lamps can have the provision for purchase of existing

Sodium

Vapor lam

ps at a competitiv

e rate. It is proposed to install nearly 384

additional light fittings in ph

ases to cater

future dem

and (1/3 rd demand is considered).

14-10

Tow

n Investment P

lan – Thu

diyalur

TNUIFSL

T

N

U

D

P

III

Final

Report

Table 14-K : Project List and Budget Estim

ates for Street lighting works

S.No

Project Components

Capital

Investment In

Lakhs

2009-10 to

2013-14

2014-

15 to

2018-

19

2019-

20 to

2023-

24

F

Street Lighting

22

Replacing 40W

Tub

e lights in

to 36 W

0.77

0.77

0.00

0.00

23

Installing

electronic chok

es for all tu

be ligh

t fittings

3.56

3.56

0.00

0.00

24

Replacing 250

W 146

Nos SVL with (4 X 24) W

T5 lamps

6.21

6.21

0.00

0.00

25

Installing

384

light fittings with poles (1/3rd of the future dem

and)

34.56

11.52

11.52

11.52

Sub Total

45.09

22.05

11.52

11.52

It is suggested that Tow

n Panchayat has to undertake energy audit stud

ies before and after installing energy savers and

devices to find out the exact energy saving

s.

The goals and service outcomes based on the prop

osed strategy for the ho

rizon period

is presented in

Table 14-L.

Table 14-L : Goals and Service outcomes related to Street lighting sector

Goals

2009-10

Up to

2013-14

2014-15 to

2018-19

2019-20 to

2023-24

Spacing betw

een lamps in

meters

54

49

45

41

Energy auditin

g Not don

e To be don

e

to be done

Energy saving

initiatives

Don

e partially

to be done com

pletely

14-11

Tow

n Investment P

lan – Thu

diyalur

TNUIFSL

T

N

U

D

P

III

Final

Report

14.2

SOCIO-ECONOMIC INFRASTRUCTURE

Socio-Economic Infrastructure works are identified based on D

emand

Supply G

ap analysis and during S

takeholder

consultation m

eetin

gs. These w

orks include improving the existin

g weekly market, creatin

g green spaces like parks and

playgrou

nds, creating shopping complexes, im

proving

burial grou

nd infrastructure, creating slaughter house

and

community halls. P

roject list and Budget estim

ates for Socio-Econo

mic Infrastructure works are listed out in

Table 14-M

.

Table 14-M

: Project List and Budget Estim

ates for Socio-Economic Infrastructure works

S.No

Project Components

Capital Investment

In Lakhs

2009-10 to

2013-14

2014-15 to

2018-19

2019-20 to

2023-24

H

Socio-Economic Infrastru

cture

26

Con

struction of Sho

pping Com

plex at w

eekly shandy

East side So

uth facing Part-I (V

ellakinar Road)

68.00

68.00

0.00

0.00

27

Con

struction of Sho

pping Com

plex at w

eekly shandy

East side So

uth facing Part-II (Vellakinar Road)

29.00

29.00

0.00

0.00

28

Con

struction of City Center on

the same weekly

shandy sou

th side un

der PPP

(If TP succeed in gettin

g the developer)

0.00

0.00

0.00

0.00

29

Con

structing community hall in

sub

ramaniyam

palayam

30.00

0.00

30

.00

0.00

30

Develop

ing parks in Balaji N

agar, S

rimurug

an Nagar,

Sai N

agar, V

isanatha puram

, 2nd

Ward Tho

ndup

atti,

App

anaican palayam near tank, M

ullai n

agar,

Thirupathi n

agar and

V.C.S. nagar

62.20

62.20

0.00

0.00

31

Develop

ing parks in VP nagar, C

ape town, Swati

garden, M

uthammal layout

20.00

0.00

20

.00

0.00

32

Develop

ing Sh

andy by carrying

out following works

0.00

0.00

0.00

0.00

14-12

Tow

n Investment P

lan – Thu

diyalur

TNUIFSL

T

N

U

D

P

III

Final

Report

S.No

Project Components

Capital Investment

In Lakhs

2009-10 to

2013-14

2014-15 to

2018-19

2019-20 to

2023-24

a - Construction of shed at weekly shandy (Imported

colour coated G.I.sheet)

36.00

36.00

0.00

0.00

b

- Construction of platform

at weekly shandy

10.00

10.00

0.00

0.00

c

- Construction of drainage at weekly shandy area

10.00

10.00

0.00

0.00

d

- Cem

ent concrete road

16.80

16.80

0.00

0.00

e

- B.T. Road for shandy area

10.00

10.00

0.00

0.00

f

- Street lights

0.50

0.50

0.00

0.00

33

Creating mod

ern slaugh

ter ho

use

30.00

0.00

0.00

30

.00

34

Burial g

roun

d im

prov

ement in App

anaikan palayam

and in Sub

ramaniam palayam

21

.00

0.00

21

.00

0.00

35

Creating road side park in

Railw

ay statio

n road, in

Muthu

nagar roads, from Cheran Colon

y to

Viswanathapu

ram

28.75

28.75

0.00

0.00

Sub Total

372.25

271.25

71.00

30.00

14-13

Tow

n Investment P

lan – Thu

diyalur

TNUIFSL

T

N

U

D

P

III

Final

Report

14.3

CONSOLIDATED CAPITAL INVESTMENT PLAN

14.3.1 FIRST PHASE INVESTMENT PLAN (2009-10 TO 2013 – 14)

First Phase investm

ent plan for Thu

diyalur is given in Table 14-N. The total Estim

ated C

ost for all the Sectors is R

s.

1927.79 lakhs. The total estim

ated cost after considering escalation for I phase is Rs. 2267.45 lakhs w

hich is show

n in

Table 14-O.

Table 14-N First Phase Capital Investment Plan for Thudiyalur Town Panchayat

Rs. in

Lakhs

Project Sector

2009-10

2010-11

2011-12

2012-13

2013-14

Investment in

phase I

Water Supply

0.00

582.18

10

.95

10.95

10.95

615.03

Sewerage

0.00

0.00

0.00

350.00

350.00

700.00

Sanitatio

n 0.00

0.00

0.00

0.00

0.00

0.00

Storm W

ater Drainage

0.00

9.40

21.25

14.40

0.00

45.05

Solid Waste M

anagem

ent w

ithout gear and bins

0.00

0.00

0.00

0.00

0.00

0.00

Solid Waste M

anagem

ent

16.94

16.94

16.94

16.94

16.94

84.71

Roads, T

raffic and Transportation

0.00

79.30

27.70

27.70

55.00

189.70

Street Lighting

4.41

4.41

4.41

4.41

4.41

22.05

Slum

s and Urban Poverty

0.00

0.00

0.00

0.00

0.00

0.00

Socio-Economic Infrastructure

0.00

83.55

127.85

44

.30

15.55

271.25

Total

21.35

775.78

209.10

468.70

452.85

1927.79

14-14

Tow

n Investment P

lan – Thu

diyalur

TNUIFSL

T

N

U

D

P

III

Final

Report

Table 14-O

First Phase Capital Investment Plan for Thudiyalur Town Panchayat (after considering escalation cost)

Rs. in

Lakhs

Project Sector

2009-10

2010-11

2011-12

2012-13

2013-14

Investment in

Phase I

Water Supply

0.00

641.85

12.68

13.31

13.98

681.81

Sewerage

0.00

0.00

0.00

425.43

446.70

872.13

Sanitatio

n 0.00

0.00

0.00

0.00

0.00

0.00

Storm W

ater Drainage

0.00

10.36

24.60

17.50

0.00

52.47

Solid

Waste Managem

ent

witho

ut

gear and bins

0.00

0.00

0.00

0.00

0.00

0.00

Solid Waste M

anagem

ent Bins and

Gears

17.79

18.68

19.61

20.59

21.62

98.30

Roads, T

raffic and Transportation

0.00

87.43

32.07

33.67

70.20

223.36

Street Lighting

4.63

4.86

5.10

5.36

5.63

25.58

Slum

s and Urban Poverty

0.00

0.00

0.00

0.00

0.00

0.00

Socio-Economic Infrastructure

0.00

92.11

148.00

53.85

19.85

313.81

Total

22.42

855.30

242.06

569.71

577.97

2267.45

14-15

Tow

n Investment P

lan – Thu

diyalur

TNUIFSL

T

N

U

D

P

III

Final

Report

14.3.2 SECOND PHASE INVESTMENT PLAN (2014-15 TO 2018 – 19)

Second Ph

ase investment plan for Thudiyalur is given in Table 14-P. The total Estim

ated C

ost for all the Sectors is R

s.

416.16 lakhs. T

he to

tal estim

ated cost after considering escalation for II phase is Rs. 612.08 lakhs which is sho

wn below.

Table 14-P Second Phase Capital Investment Plan for Thudiyalur Town Panchayat

Rs. in

Lakhs

Project Sector

2014-15

2015-16

2016-17

2017-18

2018-19

Investment in

phase II

Water Supply

8.76

8.76

8.76

8.76

8.76

43.80

Sewerage

0.00

0.00

0.00

0.00

0.00

0.00

Sanitatio

n 0.00

0.00

0.00

0.00

0.00

0.00

Storm W

ater Drainage

37.06

37.06

37.06

37.06

37.06

185.30

Solid

Waste M

anagem

ent witho

ut

gear and bins

0.00

0.00

0.00

0.00

10.37

10.37

Solid

Waste M

anagem

ent

18.84

18.84

18.84

18.84

18.84

94.18

Roads, T

raffic and Transportation

0.00

0.00

0.00

0.00

0.00

0.00

Street Lighting

2.30

2.30

2.30

2.30

2.30

11.52

Slum

s and Urban Poverty

0.00

0.00

0.00

0.00

0.00

0.00

Socio-Econo

mic Infrastructure

30.00

20.00

21.00

0.00

0.00

71.00

Total

96.96

86.96

87.96

66.96

77.33

416.16

14-16

Tow

n Investment P

lan – Thu

diyalur

TNUIFSL

T

N

U

D

P

III

Final

Report

Table 14-Q

Second Phase Capital Investment Plan for Thudiyalur Town Panchayat (after considering escalation cost)

Rs. in

Lakhs

Project Sector

2014-15

2015-16

2016-17

2017-18

2018-19

Investment in

Phase II

Water Supply

11.74

12.33

12.94

13.59

14.27

64.87

Sewerage

0.00

0.00

0.00

0.00

0.00

0.00

Sanitatio

n 0.00

0.00

0.00

0.00

0.00

0.00

Storm W

ater Drainage

49.66

52.15

54.75

57.49

60.37

274.42

Solid

Waste M

anagem

ent witho

ut gear and

bins

0.00

0.00

0.00

0.00

16.89

16.89

Solid

Waste M

anagem

ent B

ins and Gears

25.24

26.50

27.83

29.22

30.68

139.47

Roads, T

raffic and Transportation

0.00

0.00

0.00

0.00

0.00

0.00

Street Lighting

3.09

3.24

3.40

3.57

3.75

17.06

Slum

s and Urban Poverty

0.00

0.00

0.00

0.00

0.00

0.00

Socio-Econo

mic Infrastructure

40.20

28.14

31.03

0.00

0.00

99.37

Total

129.94

122.36

129.96

103.88

125.96

612.08

14-17

Tow

n Investment P

lan – Thu

diyalur

TNUIFSL

T

N

U

D

P

III

Final

Report

14.3.3 THIRD PHASE INVESTMENT PLAN (2019-20 TO 2023-24)

Third phase investm

ent plan for Thudiyalur is given in Table 14-R. The total Estim

ated C

ost for all the Sectors is R

s.

439.45 lakhs. T

he to

tal estim

ated cost after considering escalation for III ph

ase is Rs. 836.03 lakhs which is shown below.

Table 14-R Third Phase Capital Investment Plan for Thudiyalur Town Panchayat

Rs. in

Lakhs

Project Sector

2019-20

2020-21

2021-22 2022-23 2023-24 Investment in

phase III

Water Supply

8.76

8.76

8.76

8.76

8.76

43.80

Sewerage

0.00

0.00

0.00

0.00

0.00

0.00

Sanitatio

n 0.00

0.00

0.00

0.00

0.00

0.00

Storm W

ater Drainage

37.06

37.06

37.06

37.06

37.06

185.30

So

lid Waste M

anagem

ent w

ithout gear and bins

0.00

0.00

0.00

0.00

0.00

0.00

Solid Waste M

anagem

ent

22.33

22.33

22.33

22.33

22.33

111.63

Roads, T

raffic and Transportation

0.00

0.00

0.00

0.00

57.20

57.20

Street Lighting

2.30

2.30

2.30

2.30

2.30

11.52

Slum

s and Urban Poverty

0.00

0.00

0.00

0.00

0.00

0.00

Socio-Economic Infrastructure

30.00

0.00

0.00

0.00

0.00

30.00

Total

100.45

70.45

70.45

70.45

127.65

439.45

14-18

Tow

n Investment P

lan – Thu

diyalur

TNUIFSL

T

N

U

D

P

III

Final

Report

Table 14-S Third Phase Capital Investment Plan for Thudiyalur Town Panchayat (after considering escalation cost)

Rs. in

Lakhs

Project Sector

2019-20

2020-21

2021-22

2022-23

2023-24

Investment in

Phase III

Water Supply

14.98

15.73

16.52

17.34

18.21

82.79

Sewerage

0.00

0.00

0.00

0.00

0.00

0.00

Sanitatio

n 0.00

0.00

0.00

0.00

0.00

0.00

Storm W

ater Drainage

63.39

66.55

69.88

73.38

77.05

350.24

So

lid Waste Managem

ent

without

gear and bins

0.00

0.00

0.00

0.00

0.00

0.00

Solid

Waste Managem

ent Bins and

Gears

38.19

40.09

42.10

44.20

46.41

211.00

Roads, T

raffic and Transportation

0.00

0.00

0.00

0.00

118.91

118.91

Street Lighting

3.94

4.14

4.34

4.56

4.79

21.77

Slum

s and Urban Poverty

0.00

0.00

0.00

0.00

0.00

0.00

Socio-Economic Infrastructure

51.31

0.00

0.00

0.00

0.00

51.31

Total

171.80

126.52

132.84

139.49

265.38

836.03

Town Investment Plan – Thudiyalur

TNUIFSL

T

N

U

D

P

III

15-1

Final

Report

15151515 REFORMS AND RESOURCE

MOBILIZATION

15.1 OVERVIEW

Urban reforms are the main focus of good governance and service delivery to the

inhabitants of the urban area. Several initiatives and reforms have been taken up at the

national level and state level. These reforms need to be replicated and implemented by

the ULBs completely in a time bound manner. The State Government and the Urban

Local Bodies have executed a Memorandum of Agreement with the Government of

India, committing to implement the reform programme.

Under the Urban Local Bodies level, reforms committed viz., E-Governance, shift to

Accrual based double entry accounting, property tax (85% coverage), property tax

collection efficiency (90%). 100% cost recovery for water supply and solid waste

services have been committed to be achieved in the year 2012. Internal earmarking of

funds for services to Urban Poor has been done and provision of Basic services to urban

poor has been committed to be achieved in the year 2012.

Encouragement of Public Private Partnership to be carried on through outsourcing in

solid waste management, street light maintenance, pumping station maintenance, STP

maintenance and hiring of vehicles. Many of the suggested reforms have been

implemented to some extent though at the ULB level further refinement and qualitative

implementation needs to be carried out. Besides these mandatory reforms the ULBs have

initiated Institutional Strengthening, Capacity building for administrative and elected

representatives under various reform programs of TNUDP and State Government.

Town Investment Plan – Thudiyalur

TNUIFSL

T

N

U

D

P

III

15-2

Final

Report

15.2 REFORM MEASURES FOR THUDIYALUR

TOWN PANCHAYAT

The reform measures to be undertaken by the Town Panchayat can be broadly classified

into 3 broad heads:

� Financial and Accounting Reforms

� Institutional reforms

� Reforms in physical infrastructure

15.2.1 FINANCIAL & ACCOUNTING REFORMS

15.2.1.1 FINANCIAL REFORMS

As a part of financial reforms, tax mobilization reforms in tax and non tax collection

needs to be taken up for improving the financial position of the Town Panchayat. The

reform process of tax collection should be comprehensive and should focus on structural

and systematic changes so that the increase in efficiency is sustained. This is vital for

achieving self-sufficiency and improving its financial health to make it possible for the

TP to undertake various projects for the welfare of the people.

The Executive officer and the bill collectors are responsible for collection of various

taxes and charges from its citizens including raising the demand for key revenue items

like property tax, profession tax, water charges etc., follow up on outstanding payment

and prepare the Demand Collection Balance (DCB) statement. There are Two Bill

Collectors in the revenue collection department and all the posts are filled up.

Town Investment Plan – Thudiyalur

TNUIFSL

T

N

U

D

P

III

15-3

Final

Report

One of the most important yard stick for measuring the robustness of tax collection is

collection efficiency. The Collection Efficiency of important revenue sources of

Thudiyalur Town Panchayat for the last 5 years ending 2007-08 is given as under:

Table 15-A: Collection Efficiency of key revenue sources

Particulars 2003-04 2004-05 2005-06 2006-07 2007-08

Property Taxes

Arrears 100.00% 100.00% 100.00% NA 20.11%

Current 92.82% 95.10% 100.00% 100.00% 100.00%

Total 93.56% 95.38% 100.00% 100.00% 99.15%

Professional Taxes

Arrears 74.14% 100.04% 100.00% NA NA

Current 72.03% 86.63% 100.02% 100.00% 100.00%

Total 72.58% 89.68% 100.02% 100.00% 100.00%

Water Charges

Arrears 90.39% 89.05% 88.99% 100.10% 100.00%

Current 84.88% 87.27% 89.46% 93.63% 94.90%

Total 85.62% 87.50% 89.40% 94.25% 95.20%

Library Cess

Arrears 100.00% 100.00% 100.00% NA 20.11%

Current 92.82% 95.10% 100.00% 100.00% 100.00%

Total 93.56% 95.38% 100.00% 100.00% 99.15%

Source: DCB of Thudiyalur Town Panchayat

Table 15-B: Efficiency parameters of key taxes and water charges

Particulars Current Collection efficiency

Arrears Collection efficiency

CAGR in no of assessments (%)

Last 5 years

CAGR in the terms of value (%)

Property taxes (2007-08)

100% 20.11% 12.73% 17.95%

Profession Taxes

(2007-08)

100 % NA NA 14.05%

Water Charges

(2007-08)

94.90% 100% 8.69% 9%

Source: Thudiyalur Town Panchayat

Town Investment Plan – Thudiyalur

TNUIFSL

T

N

U

D

P

III

15-4

Final

Report

15.2.1.1.1 Property taxes:

The most important category in the own sources of income is the property tax. This tax is

imposed on land and buildings depending upon their class of areas & nature of use.

About 80% of the tax revenue comes through property taxes. The CAGR of number of

Property tax assessment has been around 12.73% (2003-04 till 2007-08) which is very

promising and thus has lead to increased contribution of this revenue to the total income

of the Town Panchayat. The CAGR of property tax revenue collection has been around

17.95% over the last few years. (2003-04 till 2007-08). The Town Panchayat enjoys very

good current collection efficiency and the arrear collection efficiency needs to be looked

into for improving its realization of old dues.

15.2.1.1.2 Profession Tax:

Profession tax has contributed about 20% of the total Taxes in the last few years. The

CAGR has been close to 14.05% for the past few years. The Town Panchayat enjoys a

very good current and arrear collection efficiency

Robust growth in Taxes is required to fund the projects. Proper implementation of

reforms is a pre-requisite for healthy revenue generation. Healthy growth in number of

assessments, updated tax demand, periodic revisions and high collection efficiency is

important for strong growth in property tax collection

Hence the following reforms have been suggested to bring about improvement in

property tax collection

Table 15-C: Reforms in property Taxes

Suggested Property taxes Reforms

• Mandatory Implementation of Revision of Property Tax once in every five years

is required

• Digitization of the property maps through GIS to identify un-assessed and under

assessed properties is required. GIS based mapping system is advisable for each

property identified on GIS (Whether it is residential, commercial or

industrial).The above database can be crossed checked with the data from various

governmental authorities/sources such as Income Tax, Profession Tax, and

Town Investment Plan – Thudiyalur

TNUIFSL

T

N

U

D

P

III

15-5

Final

Report

Suggested Property taxes Reforms

Electricity Bills etc. Such database also would help the Town Panchayat to verify

the utility of the property against the purpose for which permission was taken.

• Computerization of records of encroached properties, action taken, list of

encroachers through MIS would enable linking the same with GIS.

• Making the payment of property tax more convenient for the assesses through the

use of various alternative modes can be explored through a decentralized

approach such as :

1. Through banks

2. Through Post Offices, Bus terminus, Kiosks etc.

3. Through online payment through using internet.

4. Through ECS/ EFT

• Using special schemes and incentives to encourage people to make the payment

of property tax before the lapse of the due date can be considered. Rebates can be

offered for advance payment of property taxes.

• The Town Panchayat can do more initiatives to increase the number of self

assessed tax payers by creating well awareness among the people themselves

about the social responsibility of paying tax in time

• Collection of arrears through innovative means such as community participation

and fast track litigation methods need to be attempted. Law enforcement powers

should be given to the Town Panchayat to compel payment of taxes and other

charges levied by them.

• Improve enforcement against defaulters by modifying byelaws with adequate

recourse to Town Panchayat within the current framework for enforcing

disconnections on defaulters.

• PSP involvement in computerization, billing, collections and survey of properties

can be explored.

• Rewarding collection efforts of the employees to encourage more aggressive

collection.

• List of consistent major defaulters can be published in the notice board of the

Town Panchayat office. This can be resorted in the case of extreme default.

• Suitable legislation at state level to ensure that in the case of disputed property

Town Investment Plan – Thudiyalur

TNUIFSL

T

N

U

D

P

III

15-6

Final

Report

Suggested Property taxes Reforms

tax the assessee should first pay the tax under protest and then can take the

necessary legal recourse as done in customs/excise duties can be considered.

• Currently the payment of property taxes is possible only in the Town Panchayat

office. The ULB can look to the possibility of introducing additional collection

centers to enable the citizens to pay the taxes easily

• Late payment of property tax after the grace period can be penalized with

nominal charges as being done in the case of insurance payments etc

15.2.1.2 ACCOUNTING REFORMS

The administrative section is responsible for maintenance of all income and expenditure

statements, payment, preparation and implementation of budget. The system of accounting has

undergone a transformation from cash based accounting system to accrual accounting system

in line with the State government’s reforms initiative. Presently they do not have fully

computerized accounts department. As on date Thudiyalur Town Panchayat has completed

finalizing its accounts up to FY 2007-08.

The following reform measures are suggested:

Table 15-D: Accounting Reforms

Suggested Accounting Reforms

� Zero based budgeting would need to be carried out for continual monitoring of budgets and

cash flow management.

� As a part of a larger accounting reform process at the State level, it is suggested that the ULB

can include disclosures in its Annual Accounts and other published documents details on cost

recovery of essential services through direct “user charges”, indirect “taxes” and

Environmental status report. This information can be made available to the public through

various channels (Such as hosted the details on the website, distribution of pamphlets,

Involving SHGs/NGOs/Woman Groups for spreading awareness, Public announcements etc)

in simple effective language to facilitate substantial/full recovery of O&M costs of the

various essential services such as Water Supply, Solid Waste Management, etc. The

awareness creation at various levels will increase the “willingness to pay” actions of the

citizens of the area.

Town Investment Plan – Thudiyalur

TNUIFSL

T

N

U

D

P

III

15-7

Final

Report

Suggested Accounting Reforms

� The audited annual accounts can contain ULB Discussion and Analysis Report (UDAR)

providing a holistic view on the financial health, quality of service level rendered, initiatives

taken/proposed by the ULB to improve the city, areas of concern, targets and action plan to

achieve the same etc. This report along with the Urban Performance indicators can provide a

qualitative edge to the accounting and financial reporting system that can go a long way

towards achieving high levels transparency, accountability and easy and smoother facilitation

of the reform process required. Thus the support from the stake holders of the city would

become easier if the awareness is created with these qualitative reports being prepared and

shared with the key stake holders of the city.

15.2.2 INSTITUTIONAL REFORMS

The Institutional reforms suggested for Thudiyalur Town Panchayat can be broadly divided

into the following heads:

� Training and Capacity Building for administrative staff and elected officials

� Private Sector Participation

� User charges

� E-Governance

15.2.2.1 TRAINING AND CAPACITY BUILDING FOR ADMINISTRATIVE

STAFF AND ELECTED OFFICIALS

• Training

The training undergone by the staff of Thudiyalur Town Panchayat has been stated as under:

Bhavani Sagar Training was provided to two Junior Assistants.

• Public Grievance Redressal Mechanism

Public Grievance registers maintained for all key sectors such as Public Health, Water

Supply, and Street Lights. The Public also approach their respective ward councilors with

their complaints on service delivery system.

It is recommended that the periodicity of the training can be enhanced coupled with more

qualitative in-depth focus on the type of training offered. This would result in increased

awareness among the administrative staff on various issues there by enhancing their

Town Investment Plan – Thudiyalur

TNUIFSL

T

N

U

D

P

III

15-8

Final

Report

productivity and creating awareness about their responsibility towards the public. For

both elected and administrative members educational and awareness tours can be

organized to understand the best practices in various services of other ULBs.

As the ULB is already maintaining a public grievance register for all key sectors, it

should now depute one person as the in charge for this grievance book and the

complaints needs to be redressed within 24 hours.

15.2.2.2 PRIVATE SECTOR PARTICIPATION

Government of Tamil Nadu (GoTN) has laid down a policy clearance order for the ULBs in

the State, indicating the areas of privatization in the sectors of Solid Waste Management,

Water Supply, Sewerage, Drain Cleaning, Public Toilets, Road Maintenance, Street Lighting,

Parking lots, parks and play grounds, and vehicle maintenance. The GoTN states that this list

is indicative and local bodies are free to investigate other areas of privatization. The local

body would be saving the indirect cost towards pension, gratuity, etc if privatization efforts

are initiated and effective monitoring and evaluation on the delivery of services of private

contractor is adopted.

• Public Private Partnership including Privatization initiatives taken by

the Town Panchayat as stated below.

Sector Name of the work Payment Details

Street Light

Fitting of lamps (Materials are

provided by TP and only labour

provided by Private Contractor)

Rs.3500 per person

Water Supply

Plumbing and repair works.

(Materials are provided by TP

and only labour provided by

Private Contractor)

Three persons

involved from

Contractor side.

Solid Waste

Management

(SWM)

Door to door collection and

segregation

Rs.1400 per month

per person given to

50 women

Town Investment Plan – Thudiyalur

TNUIFSL

T

N

U

D

P

III

15-9

Final

Report

belonging to Self

Help Group

Crematorium

Maintenance

Cleaning the burial ground and

performing other rituals inside

the burial ground

Rs.3100 per month

to one person

Table 15-E: Possible areas of privatization/outsourcing

Areas of privatization

� Privatization of Solid Waste Management covering all wards of the town.

� Providing household segregation bins once in five years for source

segregation and D-D collection.

� Procuring protective gear (gumboots, gloves and masks) for

conservancy workers once in two years

� The ULB can also seek private sponsorship for purchase of household bins for

waste segregation once awareness is created among the public on the waste

segregation

15.2.2.3 USER CHARGES

There is a need to introduce in phases “User Charges” for various infrastructure amenities

provided by the Town Panchayat. Cross subsidization of tariff, Innovative product

structuring and community participation are some of the measures which could be

explored to provide services for the urban poor.

Currently only for water supply the ULB is able to generate direct revenue in the form of

water charges, initial deposit and connection charges and indirectly through water tax

which is a component of property tax. For other services the ULB depends on its taxes

and external funds to fund its activities. As these are inadequate the ULB faces

constraints to initiate any major improvement scheme for development of the city.

To enhance its revenue the ULB would need to increase the deposit charges for new

connections and can explore the option of increasing the water charges. This backed by

Town Investment Plan – Thudiyalur

TNUIFSL

T

N

U

D

P

III

15-10

Final

Report

higher collection efficiency and enhanced service coverage of water connections can

minimize revenue leakages from water sources.

15.2.2.4 E-GOVERNANCE & COMPUTERIZATION

E-governance is the application of information & communication technologies to

transform the efficiency, effectiveness, transparency and accountability of informational

& transactional exchanges with in government, between govt. & govt. agencies of

National, State, Municipal & Local levels, citizen & businesses, and to empower citizens

through access & use of information.

At ULB level, an e-governance shall serve the following three basic requirements in a

user friendly manner

� Information to the office bearers for their effective discharges of their duties, safeguard

the assets of the municipality and for future planning and development of their city.

� Information to councilors to do effective service delivery to their constituents.

� Information to public to pay their duty, update the information on assessment and to get

the right services of the ULB in time.

Best Practices in e-governance:

Five key components of best practices in e-governance system are as below:

� Better service delivery to citizens.

� Improved services for business.

� Transparent & anticorruption.

� Empowerment through information.

� Efficient Government purchasing.

Current Status in Thudiyalur Town Panchayat

The Town Panchayat has initiated steps for computerization of Birth & Death, Salary,

Accounts and Property Tax records

The GoTN has prescribed a list of E-Governance Module to all the municipalities; hence

the Town Panchayat should also start working on E-Governance module. The following

are the standard module suggested by GoTN

• Birth & Death,

• Property Tax

Town Investment Plan – Thudiyalur

TNUIFSL

T

N

U

D

P

III

15-11

Final

Report

• Non-Tax

• Water Charges

• Building Plan

• F.A.S

• Vehicle Maintenance

• Pay Roll

• Professional Tax

• D&O

• Movable& immovable

• Solid Waste Management

• Grievance Records

15.2.3 REFORMS IN PHYSICAL INFRASTRUCTURE

Table 15-F: Reforms in Physical Infrastructure

Sectors Suggested Reforms

Water Supply

� Service coverage of water connections to be increased from

current 84% to 85% by 2013-14

� Water supply charges and connection charges need to be revised

on periodic basis i.e. once in 5 years to fund its future investments

in water supply.

� Monthly service charges for the consumers can be increased

minimum of 25% every 5 years.

� For funding its investments in water supply, the Town Panchayat

can consider alternative payment structures for water. It could

offer one-time payment options, where the connection fee is

bundled with usage fees for a number of years. The packages

could be made attractive by offering suitable levels of discounts.

This could result in reduction in collection risk and reduced cost

of billing and collections. The same could be used for other

services, where the collection requires the effort of the municipal

staff.

Town Investment Plan – Thudiyalur

TNUIFSL

T

N

U

D

P

III

15-12

Final

Report

Sectors Suggested Reforms

� To improve the collection levels, the Town Panchayat could look

at providing an incentive and penalty structure for payment of

water taxes and charges.

� For reducing operating and maintenance costs, water leakage

audit, installation of leak detection equipment and replacement of

pipes needs to be done on regular basis.

� Prior to the year 1987-88, there existed a water supply leak

detection system for minimizing the cost of water supply. It can

be now redefined and updated to serve as a record maintained for

Unaccounted for Water (UFW). UFW is the difference between

the volume of water delivered into the distribution system and the

water sold/billed or accounted for by legitimate consumption.

There is need for maintaining such a record for reducing the

possibilities of revenue leak through unauthorized/illegal

connections.

� It may be mentioned that the percentage of non-revenue water is

ascertained based on the condition assessment of the water supply

system. It is necessary to carry out a detailed study to estimate the

non-revenue losses to enhance the efficiency of the water supply

system. In addition, the Town Panchayat has to under take a

series of initiatives to arrest illegal water connections and

enhance the coverage of House Service Connections (HSC).

� Pumps, motors and distribution network which undergo severe

wear and tear impact power costs of the Town Panchayat besides

reducing operational efficiency. Hence periodic maintenance of

the system with regular investments in up gradation and

replacement of pipelines, motors and pumps needs to be followed

to avoid huge one time expenditure to the maximum extent

possible.

� Privatization in routine maintenance relating to water supply

such as hand pumps can be considered

Town Investment Plan – Thudiyalur

TNUIFSL

T

N

U

D

P

III

15-13

Final

Report

Sectors Suggested Reforms

� Periodic technical training to its engineering cell is required.

� Implementation of 24/7 water supply system with the main

features of:

� Anytime full availability of water.

� Confessional water user charges to slum dwellers and higher

charges for commercial users.

� Reduction of water wastages and unaccounted water flow by

installing water audit equipments, energy saving equipments,

water metering and conducting periodic water audits, energy

audits etc.

� 100% accounting of water received and distributed.

� Water quality monitoring system on daily basis.

� Chlorinators at each pumping station.

� Increased collection of revenue on water charges at ULB level

by using GIS based billing system on 24*7 systems.

Solid Waste

Management

� Door to door collection of garbage at household level and

segregation of waste at source need to be implemented after

creating suitable awareness level. In case of Thudiyalur 100 % of

assessments covered by Door to Door collection and 100% of

assessments involved in waste segregation

� Private sponsorship of bins for waste segregation at house hold

level can be looked into

� Vehicles used in SWM and conservancy activities such as tipper

lorries, tractors; dumper blazer etc can be maintained through

outsourcing arrangement with reputed contractors. The Annual

Maintenance Contract should be all comprehensive covering

various critical clauses in order to protect the Town Panchayat

from possible claims from the Ways to improve the revenue from

charges that are being collected from different commercial

establishments like hotels including kiosks, eating houses,

restaurants, star hotels and retail markets should be studied.

Town Investment Plan – Thudiyalur

TNUIFSL

T

N

U

D

P

III

15-14

Final

Report

Sectors Suggested Reforms

� The Town Panchayat can identify the ways to generate revenue

from Solid Waste by selling compost at market.

� The Town Panchayat can auction to the private parties for

disposal of recyclables.

� Potential for getting carbon credit benefit through the Clean

Development Mechanism (CDM) need to be studied in making a

comprehensive solid waste management scheme.

� Privatization of services for the following activities should be

undertaken to reduce the establishment charges and O&M

charges of Town Panchayat:

o Door to door collection of domestic waste

o Door to door collection of commercial waste, construction

waste and Market waste.

o Setting up and operation and maintenance of waste treatment

plants.

o Supplying vehicles on rent

o Transportation of waste on contract basis.

� Delegation of powers and fixing accountability should be done for

better management of the system. .

� Human Resources Development

� Special training to unqualified staff

� Refresher courses for all levels of staff about advances in

the field of SWM

� Exposure to elected members

� Design of SWM course to Public Health staff

Street lights

� As a measure to save energy, the Town Panchayat shall replace

its other existing non-energy saving lamps to energy saving

lamps.

� Meeting the norms of one pole per 40 meters by 2023-24.

� Energy Audit needs to be conducted periodically.

� Private parties can be involved for financing, operation and

Town Investment Plan – Thudiyalur

TNUIFSL

T

N

U

D

P

III

15-15

Final

Report

Sectors Suggested Reforms

maintenance of energy efficient street light projects to reduce the

cost incurred for the same.

Roads

� Relaying Bitumen roads once in three years with patch works to

be undertaken based on the need in between years

� Future roads to be laid with dedicated service lanes.

� Relaying roads with recyclable materials like fly ash, can be

explored.

Sewerage

Systems

� Privatization of maintenance of sewerage system can be

considered to reduce the establishment charges of municipality

and O&M Charges.

� Sewer Connection charges to the users can be increased once in

five years for better revenue generation.

� Monthly service charges for the consumers can be increased

minimum of 25% every 5 years.

� To improve the collection levels of monthly charges, the

municipality could look at providing an incentive and penalty

structure for payment of charges and privatize the collection

system.

� Pumps, motors in sewage pumping stations undergo severe wear

and tear and impacts power costs of the municipality besides

reducing operational efficiency. Hence periodic maintenance of

the system with regular investments in up gradation and

replacement of pipelines, motors and pumps needs to be followed

to avoid huge one time expenditure to the maximum extent

possible.

� Annual Maintenance Contract for Sewage Pumping Stations and

Sewage Treatment Plants can be adopted.

� Periodic technical training to its engineering cell is required in

O&M of Sewage Treatment Plant, Pumping Stations and Sewer

Networking System.

Town Investment Plan – Thudiyalur

TNUIFSL

T

N

U

D

P

III

15-16

Final

Report

15.3 ADDITIONAL RESOURCE MOBILIZATION

Thudiyalur has been initiated both the traditional and non-traditional alternatives for

resource mobilization. Resource Mobilization efforts need to be directed towards

generating additional revenue from existing avenues such as property taxes, profession

tax, water charges, service charges and fees and remunerative assets of the Town

Panchayat. Besides this the Town Panchayat would need to take measures to control

expenditure in water supply, sewerage systems, solid waste management, street lighting

etc.

Additional resource mobilization options such as Daily market fees, Weekly market fees,

Bus stand fees, Fess from Pay & Use toilets, rent from commercial complex and rent

from shopping mall and community hall for the Town Panchayat are discussed in detail

in subsequent paragraphs.

Incase of Thudiyalur the share Non-Tax revenue to the total revenue has been more than

70% in the last few years. The Non-Tax Revenue has grown at a CAGR of around 3% in

the last 6 years ending .The town panchayat can take more positive initiatives to increase

its growth in coming years. The “Other income” under the Non-tax revenue consists

mainly of Income from Weekly market and Rent from shopping complex accounting for

only about 17% of this income. This income has grown at a CAGR of over 8.46 % in the

last few years.

Revenue from Social Assets

Particulars 200

4-0

5

200

5-0

6

200

6-0

7

200

7-0

8

200

8-0

9

Bu

dg

et

200

9-1

0

Bu

dg

et

Cart Stand – Lorry Stand -

Taxi Stand Fees 0.50 0.65 0.75 1.06 2.21 5.00

Fees for Pay & Use toilets 0.27 0.28 0.32 0.33 0.40 0.50

Market fees – Daily market 0.00 0.00 0.00 1.89 2.19 5.00

Market fees – weekly

market 6.75 6.75 9.96 8.19 8.32 11.00

Rent on Shopping

Complex 9.42 8.68 8.32 9.37 11.87 12.00

Town Investment Plan – Thudiyalur

TNUIFSL

T

N

U

D

P

III

15-17

Final

Report

Particulars Area

Annual Income

(2009-10) - Budget

in Rs.Lakhs

Cart Stand – Lorry Stand - Taxi

Stand Fees 5.00

Fees for Pay & Use toilets

1 Pay & Use & 12 Public Toilets

� Subramania Palayam – (3

Numbers) � Appanaicken Palayam –( 4

Numbers)

� Anna Colony-(2 Numbers) � Idiyara Road (2 Numbers)

Muthu Nagar( 1 Number)

0.50

Market fees – Daily market 5.00

Market fees – weekly market 72 Shops 11.00

Rent on Shopping Complex 16776 Sq.m - 46 shops inside the

complex 12.00

From the above table it is clear that Thudiyalur Town Panchayat earns an average of Rs.10

Lakhs from Market fees (Daily & Weekly) and about Rs9.94 Lakhs from shopping complex

rentals. The Cart Stand – Lorry Stand - Taxi Stand Fees also contribute its share to the Non-

Tax revenue with an average fee of about Rs.1.70 Lakhs.

Based on our analysis and discussions with the officials/stake holders, the following are

additional revenue projects which are conceived in the Capital Investment Plan of the Town

Panchayat:

� Creating Shopping complexes in weekly market area at an estimated cost of

Rs.97Lakhs (Construction of Shopping Complex at weekly shandy East side

South facing Part-I & II (Vellakinar Road))

� Construction of City Center on the same weekly shandy south side under PPP

(If TP succeed in getting the developer)

� Constructing community hall in Subramaniyam palayam and in Raju garden

at an estimated cost of Rs.30 Lakhs

� Creating Slaughter house at an estimated cost of Rs.30 Lakhs.

� Improving Infrastructure in weekly market in an estimated cost of Rs. 83.03

lakhs

Town Investment Plan – Thudiyalur

TNUIFSL

T

N

U

D

P

III

16-1

Final

Report

16161616 FINANCIAL OPERATING PLAN

16.1 BACKGROUND- NEED FOR AN FOP

The Financial Operating Plan (FOP) assesses the financial strength of the Town Panchayat to

implement the identified investments. The Financial Operating Plan (FOP) forecasts the

Town’s finances on the basis of certain assumptions on income and expenditure. The primary

objective of the FOP is to ascertain the investment sustenance capacity of the Town Panchayat

under full project scenario of revenue enhancement and expenditure control.

In the FOP following scenarios are envisaged

Scenarios Details

Base Case Scenario No New Projects and No Reforms

(“Business as Usual” Scenario)

Full Project -Scenario II Implementation of all Projects required for

the next 15 years with Reform

implementation

The key reforms are highlighted in Table below. The total reforms suggested have been

elaborated in Reforms Implementation Schedule (Annexure IV

Key reforms

Particulars Current practice Reform suggested

Revision in

Property tax rates

Revision once in 10 years 25% increase in every 5

years

Service level

Coverage (Water

Supply- Number of

84% 0.20% increase every year

achieving 85% coverage by

2013-14

Town Investment Plan – Thudiyalur

TNUIFSL

T

N

U

D

P

III

16-2

Final

Report

assessments)

Revision in Initial

Deposit for New

Water Connections

Adhoc revision Rs.2000 increase every 5

years for each new

connection

Revision in Water

Charges

Adhoc revision 25% increase every 5 years

Revision in Initial

Deposit for New

UGD Connections

Adhoc revision Rs.2000 increase every 5

years for each new

connection

Revision in

Monthly user

charges for UGD

Not Implemented Currently 25% increase every 5 years

(Proposed)

User Charges for

Solid Waste

Management

Not Charged Rs.50 per month from Non-

Domestic assesses from the

year 2011-12 and Rs.15 per

month from Domestic

assesses from the year 2013-

14. A 25% increase every 5

years in the user charges has

been proposed

16.2 FINANCIAL SUSTAINABILITY

The financial sustainability Analysis is carried out with the basic assumption that the

Town Panchayat will carry out reforms and projects envisaged under full project

scenario. The Financial Operating plan prepared for Thudiyalur Town Panchayat

evaluates the Town Panchayat’s financial position based on the base care scenario and

the full project scenario which are described below:

Town Investment Plan – Thudiyalur

TNUIFSL

T

N

U

D

P

III

16-3

Final

Report

16.2.1 BASE CASE SCENARIO

In the base case scenario, the finances of the Town are forecast for next 15 years without

taking into consideration any new projects envisaged in Capital Investment Plan. .

Current practices with regard to tariff revision of key services are only considered.

Additional resources mobilized through various initiatives such as resource mobilization

through enhanced revision of property tax rates and the number of assessments (based on

projected population increase), increased revenue realization through faster growth in

service charges and fees including revision of user charges and connection charges for

water supply, other income etc are loaded to the FOP in the base case scenario. Routine

revenue expenses including Operations and Maintenance of existing assets have also

been considered and loaded to the FOP. Revenue surplus thus generated indicates

Town’s capacity to service the usual capital expenditure in the normal course of running

its operations.

16.2.2 FULL PROJECT SCENARIO BASED ON

PRUDENT FUNDING NORMS

Full Project scenario for Thudiyalur has been worked out based on estimated demand

supply analysis of various physical and social infrastructure requirements of the Town

and feedback of Operating Working Group’s (OWG’S) consultation on the Town’s needs

for the next 15 years. The financial mix for funding these projects has been based on

prudent financial norms of funding and existing practices of funding currently being

followed today. The projects identified are vital for meeting the basic requirements of the

Town as per the infrastructure standards. Furthermore all the projects identified fall under

the obligatory functions under the 12th Schedule. In the event of the Town not

undertaking the project, the key problems would be poor infrastructure resulting in poor

service delivery and loss of potential revenue from new revenue streams. To overcome

these issues the framework for FOP is developed taking into account existing strengths of

the Town and also reducing the inefficiencies in the system.

Phasing of the identified projects is done based on the possible year of construction,

demand supply gap analysis and investment priority of the OWG. Implications of the

Town Investment Plan – Thudiyalur

TNUIFSL

T

N

U

D

P

III

16-4

Final

Report

investments worked out in terms of external borrowing required & the resulting debt

servicing commitments, external support in form of grants and additional operation and

maintenance expenditure anticipated due to the new projects identified have been worked

out for the next 15 years. Debt servicing capabilities, gaps in required investments from

Town for the said projects vs the actual availability with the Town Panchayat for the

Town’s contribution for the said projects has been worked out to estimate the extent of

Town’s capability to meet its contribution for financing the new projects identified under

Capital Investment Plan.

The implications on the investment and borrowing capability of the Town for all the

identified projects is worked out taking into consideration of all suggested reforms.

The objective of working out with all the reforms mainly to highlight the importance of

implementing the reforms on improving the financial capability of the Town for

successful implementation of the projects envisaged in CIP.

16.3 ASSUMPTIONS FOR FOP

This FOP is based on a whole range of assumptions related to income and expenditure.

These are critical to understand the financial projections worked out, sustenance of the

projected increase in revenue and expenditure under various scenarios and surplus thus

generated. Assumptions regarding interest rates, repayment terms and conditions,

financing pattern have also been explained in subsequent paragraphs. Assumptions

regarding additional Operation and Maintenance Expenses for the new projects identified

have also been provided. The assumptions would help in understanding the extent of

investment sustenance for future projects envisaged.

16.3.1 REVENUE INCOME

In case of taxes and non tax revenue such as property taxes, water charges, sewerage

charges and solid waste management charges where the base and basis of revenue is

fairly well known and predictable the likely revenue is forecast based on certain

Town Investment Plan – Thudiyalur

TNUIFSL

T

N

U

D

P

III

16-5

Final

Report

assumptions regarding growth in number of assessment, revision in average revenue per

property (for property taxes), revision in charges/Tariffs (water charges and solid waste

charges). Table 16-A and Table 16-B, lists out the assumptions with regard to

forecasting income from property tax, water charges, sewerage charges and solid waste

charges respectively. Assumptions regarding other sources of revenue income have been

given in Table 16 C. Tables indicate the assumptions in revenue income in base case

scenario and investment scenario.

16.3.1.1 PROPERTY TAXES

Table 16-A : Key assumptions for forecasting income from Property Taxes

Source: Analysis

16.3.1.2 WATER CHARGES

Table 16-B: Key assumptions for forecasting income from Water Charges

Description Current

Level

Base Case

Scenario

Investment Scenario

% OF WATER CONNECTIONS TO PROPERTY TAX ASSESSMENT

2007-08 84%

2013-14 85% 85%

2017-18 85% 85%

2023-24 85% 85%

Description Current Level Base Case Scenario Investment Scenario

Annual Growth in

Number of Assessment

12.73 %

(From 2003-04

till 2009-10)

Projected based on the

estimated increase in

population of the city

Projected based on the

estimated increase in

population of the city

Periodic Increase in

Average Revenue per

property (%)

25% increase in every

10 years

25% increase in every

5 years

Town Investment Plan – Thudiyalur

TNUIFSL

T

N

U

D

P

III

16-6

Final

Report

INITIAL DEPOSIT FOR NEW WATER SUPPLY CONNECTIONS ( Rs. per connection)

Domestic (Rs.)

From 2009-10 till 2013-

14 Rs.3000 Rs.3000 Rs.3000

From 2014-15 till 2018-

19 Rs.3000 Rs.5000

From 2019-20 till 2023-

24 Rs.5000 Rs.7000

Non-Domestic (Rs.)

From 2008-09 till 2012-

13 Rs.5000 Rs.5000 Rs.5000

From 2013-14 till 2017-

18 Rs.5000 Rs.7000

From 2018-19 till 2022-

23 Rs.7000 Rs.9000

WATER CHARGES (per month)

Domestic (Rs.)

From 2009-10 till 2013-

14 Rs. 60 Rs. 60

From 2014-15 till 2018-

19 Rs. 60 Rs. 75 (25% increase)

From 2019-20 till 2023-

24 Rs. 75(25% increase) Rs. 93.75 (25% increase)

Non-Domestic (Rs.)

From 2009-10 till 2013-

14 Rs.120 Rs.120

From 2014-15 till 2018-

19 Rs.120 Rs.150 (25%

increase)

From 2019-20 till 2023-

24 Rs.150 (25%

increase)

Rs.187.50 (25% increase)

Industry (Rs.)

From 2009-10 till 2013-

14 Rs.180 Rs.180

From 2014-15 till 2018-

19 Rs.180 Rs.225(25%

Increase)

From 2019-20 till 2023-

24 Rs.225(25%

Increase)

Rs.281.25(25% Increase)

INITIAL DEPOSIT FOR NEW SEWERAGE CONNECTIONS( Rs. per connection)

Domestic (Rs.)

From 2009-10 till 2013-

14 Rs.4000 Rs.4000 Rs.4000

Town Investment Plan – Thudiyalur

TNUIFSL

T

N

U

D

P

III

16-7

Final

Report

From 2014-15 till 2018-

19 Rs.4000 Rs.6000

From 2019-20 till 2023-

24 Rs.6000 Rs.8000

Non-Domestic (Rs.)

From 2009-10 till 2013-

14 Rs.14000 Rs.14000 Rs.14000

From 2014-15 till 2018-

19 Rs.14000 Rs.16000

From 2019-20 till 2023-

24 Rs.16000 Rs.18000

SEWERAGE CHARGES (per month)

Domestic (Rs.)

From 2009-10 till 2013-

14 Rs.150 Rs.150 Rs.150

From 2014-15 till 2018-

19 Rs.150 Rs.188(25% Increase)

From 2019-20 till 2023-

24 Rs.188(25%

Increase

Rs.234 (25% Increase

Non-Domestic (Rs.)

From 2009-10 till 2013-

14 Rs.1200 Rs.1200 Rs.1200

From 2014-15 till 2018-

19 Rs.1200 Rs.1500(25% Increase)

From 2019-20 till 2023-

24 Rs.1500(25

% Increase)

Rs.1875 (25% Increase)

Source: Analysis

Town Investment Plan – Thudiyalur

TNUIFSL

T

N

U

D

P

III

16-8

Final

Report

16.3.1.3 OTHER SOURCES OF REVENUE INCOME

Table 16-C: Assumption for Income

Particulars CAGR-(%) Projected

growth

Rates

(%)

Notes

Profession

Tax

14.05%

(2003-04 till

2007-08)

15% -

External

Sources

(Assigned

Revenue+

Devolution

Funds + Grants

&

Contribution)

Inconsistent

trend in

Assigned

Revenue and

12% in

Devolution

funds (2003-04

till 2007-08)

2% in

Assigned

Revenue

and 12%

in

Devolution

funds

Service

Charges &

fees(

Excluding

Water

Charges)

16.99% 15%

Other Income Inconsistent

trend

9% 2009-10 (Budget) is taken as the

base year for projections. This

includes project overhead

appropriation expenses.

Town Investment Plan – Thudiyalur

TNUIFSL

T

N

U

D

P

III

16-9

Final

Report

User Charges

for Solid

Waste

Management

Not charged

Rs.50 per month from Non-

Domestic assesses from 2011-12

and Rs.15 per month from

Domestic assesses from 2013-

14. A 25% increase every 5

years in the user charges has

been envisaged.

Source: Analysis based on past financials provided by Thudiyalur Town Panchayat

16.3.2 REVENUE EXPENDITURE

16.3.2.1 CURRENT REVENUE EXPENDITURE

Table 16-D: Assumption for Revenue Expenditure

Particulars CAGR-(%) Projected Growth

Rates (%)

Personnel Cost &

Retirement Benefits ( Salaries)

Salaries- 16.27% (2003-

04 till 2007-08)

Retirement Benefits-

Inconsistent trend

6%

Operating Expenses 17.19% 10%

Repairs & Maintenance Inconsistent Trend 6%

Administrative Expenses 18.34% 5%

Source: Analysis based on past financials provided by Thudiyalur Town Panchayat

16.3.2.2 ADDITIONAL O&M EXPENDITURE DUE TO SUB-PROJECTS

This has already been covered in Chapter 11: Asset Management Plan: Table 11 E- O&M

for Proposed works

Town Investment Plan – Thudiyalur

TNUIFSL

T

N

U

D

P

III

16-10

Final

Report

16.3.2.3 FUTURE DEBT OBLIGATIONS

Table 16-E: Key assumptions for forecasting future debt obligations

Sector Tenure Moratorium Rate of Interest (%)

Water Supply, UGD 20 5 10.00

Roads, Storm Water Drains 10 2 9.00

Others 5 NIL 9.00

Source: Analysis

16.3.3 FUNDING MECHANISM

Table 16-F: Financing Pattern for Proposed projects as per prudent Funding norms

Particulars Loan Grant TOWN Share/

Public

Contribution

Notes

Water Supply 50 30 20

UGD 50 30 20

Sanitation 50 50

Storm Water

Drainage

60 30 10

Solid Waste

Management

60 30 10

Roads, Traffic and

Transportation

60 30 10

Street Lighting 60 30 10

Socio-Economic Infrastructure

Shopping Complex 90 10

City Centre 90 10

Community Hall 50 50

Parks 50 50

Bus Shed 50 50

Road Platforms 50 50

Development of Office building 50 50

Creation of Slaughter House 50 50

Burial Ground Improvement 50 50

Source: Analysis

Town Investment Plan – Thudiyalur

TNUIFSL

T

N

U

D

P

III

16-11

Final

Report

16.4 OUTCOME OF FINANCIAL OPERATING PLAN

16.4.1 BASE CASE SCENARIO (“BUSINESS AS USUAL

SCENARIO”)

In the Base Case Scenario, the finances of TOWN are forecast for the next 15 years without

taking into consideration any new projects envisaged in Capital Investment Plan (CIP). The

past trends in growth rates in revenue income and expenditure are assumed to continue over

the next 15 years. No new revenue sources such as user charges for service delivery systems

of the Town are envisaged under this scenario. Revenue surplus thus generated indicates

Town’s capacity to service the usual capital expenditure in the normal course of running its

operations. Table 16 G indicates the revenue surplus position of the Town over the 15 year

period.

The following are the outcome under this scenario:-

� The projected cumulative revenue surplus (Closing Balance) of the TOWN shows a

healthy surplus position over the 15 year period with a revenue surplus touching

Rs.7356.42 Lakhs in the year 2023-24 after meeting its current debt obligations.

Town Investment Plan – Thudiyalur

TNUIFSL

16-12

Final

Report

Table 16-G : Financial Operating Plan of Thudiyalur- Base Case Scenario

Town Investment Plan – Thudiyalur

TNUIFSL

16-13

Final

Report

T

N

U

D

P

III

16.4.2 FULL PROJECT SCENARIO WITH SUGGESTED

REFORMS

The cash flows from the new projects under this scenario are shown in Table 16 H, the

financial impact for the Town Panchayat in implementing full projects through additional

resources generated on account of reforms suggested and as per the norms of funding is

given in Table 16 I and also the debt service capability of the corporation is given in

Table 16 J. Implications of this investment in terms of external borrowings required,

resultant debt service commitment, and additional operation and maintenance expenditure

are worked out to ascertain sub-project cash flows. Revenue surpluses are applied to sub-

project cash flows emerging from full project investments – the Town’s fund net

surpluses indicates its ability to sustain full investments

Town Investment Plan – Thudiyalur

TNUIFSL

16-14

Final

Report

Table 16-H: Full Project Cash Flow - As per Prudent Financial norms

Town Investment Plan – Thudiyalur

TNUIFSL

16-15

Final

Report

Table 16-I: Financial Operating Plan of Thudiyalur - Full Project with Reforms-Prudent Funding Norms

Table 16-J: Calculation of Debt Service Coverage Ratio (DSCR) With FULL PROJECT WITH REFORMS- As per Prudent Financial Norms

Town Investment Plan – Thudiyalur

TNUIFSL

16-16

Final

Report

T

N

U

D

P

III

The full project investment proposed for the Town is to the tune of Rs.3715.56 Lakhs, the

details of sector wise financing pattern is presented in the following table.

Table 16-K: Sector wise Investments.

Project Sector

Total Investment (Rs. In

lakhs)

Water Supply 829.47

Sewerage 872.13

Sanitation 0.00

Storm Water Drainage 677.13

Solid Waste Management with gear and

bins 465.65

Roads, Traffic and Transportation 342.27

Street Lighting 64.42

Slums and Urban Poverty 0.00

Socio-Economic Infrastructure 464.49

Total 3715.56

Water Supply

22%

Sewerage

23%Storm Water

Drainage

18%

Solid Waste

Management with

gear and bins

13%

Roads, Traffic and

Transportation

9%

Street Lighting

2%

Socio-Economic

Infrastructure

13%

Town Investment Plan – Thudiyalur

TNUIFSL

16-17

Final

Report

T

N

U

D

P

III

Funding pattern for the full projects is as stated in table below:

Table 16-L Funding Pattern.

Particulars

Full project Scenario-

Funding based on prudent

financial norms (Rs.lakhs)

Loan Amount 1846.35

External Support 1114.67

TOWN’s Contribution 355.02

Public Contribution 399.53

PPP 0.00

Project Cost 3715.56

% of loan on Project

cost 50%

Funding Pattern

49%

30%

10%

11%

Loan

External Support

TP's Contribution

Public Contribution

Out of the total project costs, the share of Town Panchayat is Rs. 355.02 lakhs, which

would be financed through internal accruals, after implementing the reforms with external

borrowings. The Town Panchayat would mobilize the resources to the tune of 20% from

Town Investment Plan – Thudiyalur

TNUIFSL

16-18

Final

Report

T

N

U

D

P

III

their internal accruals with the remaining 80 % funding from lending agencies by way of

Grant and Loan components.

Full reform implementation by the Town within the scheduled time frame (as shown in

Annexure IV – Reform Implementation schedule) backed by strong external support is a must

for bringing in projects required for improving the Town over the next 15 years. The reform

efforts of the Town need to be supported and rewarded by financial assistance from funding

agencies and strong external support in order to implement all projects suggested under CIP.

POPULATION PROJECTION FOR THUDIYALUR

Arithmetical IncreaseProjected population

= P +ni

Where P = Present

Population

And ni = Average

increase per decade

Year Population Increment

1981 9787

1991 15553 5766 58.9

2001 21004 5451 35.0

Total 11217

Average 5609

Projected Population Percentage Increase

2009 25491 0.8 21.36 2024

2013 27734 1.2 8.80

2018 30538 1.7 10.11

2023 33343 2.2 9.18 14 2009

2010

2011

2012

2013

2014

Geometrical Increase Method 2015

Projected Population

Pn = P(1+Rg)^n 2016

where Rg =

Geometric mean 2017

n=number of decades 2018

2019

Census year Pop Increment Geometric growth 2020

1981 9787 2022

1991 15553 5766 0.59 2023

2001 21004 5451 0.35 2024

Geometric mean Rg 0.45

Year Projected Population

Percentage

increase

2009 28343 0.8 34.94

2013 32925 1.2 16.16

2018 39707 1.7 20.60

2023 47886 2.2 20.60

POPULATION PROJECTION FOR THUDIYALUR

Incremental IncreaseProjected Population

Pn =

P2001+nx+(n(n+1)/2

)y

Where P = Present

Population

Pn = Projected

population for nth

decade

n= number of decades

x=average increase

per decade

y=average

incremental increase

per decade

Year Population Increment Incremental increase

1981 9787

1991 15553 5766 5766

2001 21004 5451 -315

Total 11217 5451

Average 5609 2726

Year projected population Percentage increase

2009 27453 0.8 30.70

2013 31332 1.2 14.13

2018 36793 1.7 17.43

2023 42936 2.2 16.70

POPULATION PROJECTION FOR THUDIYALUR

Least Squares

Year (X) Population (Y) in lakhs X^2 XY

1981 9787 3924361 19388047

1991 15553 3964081 30966023

2001 21004 4004001 42029004

5973 46344 11892443 92383074.00

n = number of items = 3

Y = a + bX

ΣY = a(n) + bΣX Eq 01

ΣXY = aΣX + bΣX^2 Eq 02

3a + 5973b = 46344

5973a + 11892443b

= 92383074.00

rough work

5973a+11892243b 92270904 1991 5973 11892243

5973a+11892443b 92383074 11892443

200b = 112170 200

b = 560.85

3a + 5973b = 46344 7738047.45

3a = -3303613.05

a = -1101204.35

Solving the equation

Y = a + bX

Year Projected Population Percentage Increase

2009 25543 21.61

2013 27787 8.78

2018 30591 10.09

2023 33395 9.17

POPULATION PROJECTION FOR THUDIYALUR

Graphical MethodYear Population Percentage increase

1981 9787

1991 15553 58.91

2001 21004 35.05

2009 27000 38000 80.92

2013 29500 40000 5.26

2018 32000 42500 6.25

2023 35000 47000 10.59

Year

Arithmetic

Increase

Geometric

Increase

Incremental

Increase

Least

Squares

Graphical

Method Average

1981 9787 18316 18316 18316 18316 18316

1991 15553 22152 22152 22152 22152 22152

2001 21004 23559 23559 23559 23559 23559

2009 25491 28343 27453 25543 27000 26766

2013 27734 32925 31332 27787 29500 29856

2018 30538 39707 36793 30591 32000 33926

2023 33343 47886 42936 33395 35000 38512

R2 = 0.9981

0100002000030000400005000060000700008000090000

100000110000120000

1961 1971 1981 1991 2001 2011 2021

Annexure II: Norms Vs Current Status for Thudiyalur

Reform Agenda for Thudiyalur Town Panchayat

Sector Indicators Unit Current Status Norms/Standard

Daily per capita supply Litres 57 70/100

Roads covered with distribution network Percent 74 100

Storage capacity with respect to supply Percent 41 33

Service connection Percent 84 85

Collection efficiency in water charges Percent 94.90 100

Storm Water Drainage Roads covered with Storm water drainage Percent 67 130

Waste generation per Capita per day Grams 247.7 < 350 grams

Collection efficiency Percent 100 100

Conservancy staff per Km Persons 0.4 2

Door-Door collection

efficiency(Assessments covered) Percent 100 100

Assessments involved in waste

segregation Percent 100 100

Per capita road length Meters/Person 2.4 1.5

Percentage of Surface roads Percent 91 100

Street Lighting Spacing between lamps Meters 54 30

Collection efficiency in Property taxes Percent 100 100

Revision in Property tax Years Once in 10 years Once in 5 years

Privatisation Areas

The Town Panchayat has

initiated to outsource its

services in the following

sectors namely in Strret

lights, Water Supply, Solid

Waste Management ,

Crematorium Maintenance

Solid Waste Management, Street

Light Maintenance, Pumping Station

Maintenance, STP Maintenance and

Hiring of Vehicles

E-Governance Modules

The Town Panchayat has

initiated steps for

computerization of Birth &

Death, Accounts and

Property Tax records 18Institutional Reforms

Urban Finance

Water Supply

Roads

Solid Waste management

Annexure IV: Project Implementation Schedule for Thudiyalur

THUDIYALUR

Particulars Current Status 2009-10

2010-11

2011-12

2012-13

2013-14

2014-15

2015-16

2016-17

2017-18

2018-19

2019-20

2020-21

2021-22

2022-23

2023-24

Technical Financial

Water Supply

CWSS for Thudiyalur

Identiifed based on

Demand supply Gap

Analysis and to be

implemented in 2010-11 CWSS & ULB

Government/Financial

Institution. ULB

Creating Distribution network for 21.8 Km by 2023-

24

Identiifed based on

Demand supply Gap

Analysis and to be

implemented in phases ULB

Government/Financial

Institution. ULB

Creating 1 lakh litre capacity OHTs by 2013-14

Identiifed during OWG

Meeting and to be

implemented during

2010-11 ULB

Government/Financial

Institution. ULB

Sewerage and Sanitation

UGD Scheme for Thudiyalur Municipal area

Identified during OWG

meeting and to be

implemented in 2012-13

& 2013-14 ULB

Government/Financial

Institution. ULB, Public

Contribution

Assistance

Annexure IV: Project Implementation Schedule for Thudiyalur

Particulars Current Status 2009-10

2010-11

2011-12

2012-13

2013-14

2014-15

2015-16

2016-17

2017-18

2018-19

2019-20

2020-21

2021-22

2022-23

2023-24

Assistance

Storm Water Drainage

Creating Pucca drains for 18.53 Kms between 2014-15

and 2023-24

Identiifed based on

Demand supply Gap

Analysis and to be

implemented in phases

Creating drainage line in MTP Main Road from VCS

Nagar to Subramaniyam Palayam Main Road for a

length of 0.6 Km

Identiifed during OWG

Meeting and to be

implemented during

2010-11

Creating drainage line in Mullai Nagar Cross Roads for a

length of 0.6 Km

Identiifed during OWG

Meeting and to be

implemented during

2011-12

Creating drainage line in VCS Nagar South Side Cross

Roads for a length of 1.05 Km

Meeting and to be

implemented during

2011-12

Creating drainage line in VCS Nagar North Side Cross

Roads for a length of 1.1 Km

Identiifed during OWG

Meeting and to be

implemented during

2012-13

Solid Waste Management

Contribution to scientific land fill site

Identified during OWG

meeting and Demand

and Supply Analysis

Public awareness for Waste segregation and D-D

collection and awareness programme for

conservancy workers about protective gear

Identified during OWG

meeting and Demand

and Supply Analysis

Procuring segregation bins for each assessments

Identified during OWG

meeting and Demand

and Supply Analysis ULB & PSP

Support from

Government , Financial

Institution and ULB

Procuring protective gear for conservancy workers

Identified during OWG

meeting and Demand

and Supply Analysis ULB

Support from

Government , Financial

Institution and ULB

Annexure IV: Project Implementation Schedule for Thudiyalur

Particulars Current Status 2009-10

2010-11

2011-12

2012-13

2013-14

2014-15

2015-16

2016-17

2017-18

2018-19

2019-20

2020-21

2021-22

2022-23

2023-24

Assistance

Roads, Traffic &

Transportation

Converting 6.1 Km kutcha road into BT road

Identified during OWG

meeting and Demand

and Supply Analysis ULB

Support from

Government/Financial

institution, ULB

Contribution

Rukkammal Colony Cross Roads for a length of

0.6 Km

Identified during OWG

meeting and Demand

and Supply Analysis ULB

Support from

Government/Financial

institution, ULB

Contribution

Cheran Colony Middle Cross Roads for a length of

0.62 Km

Identified during OWG

meeting and Demand

and Supply Analysis ULB

Support from

Government/Financial

institution, ULB

Contribution

Cheran Colony West Side Cross Roads for a

length of 0.62 Km

Identified during OWG

meeting and Demand

and Supply Analysis ULB

Support from

Government/Financial

institution, ULB

Contribution

Cheran Colony East Side Cross Roads for a length

of 0.62 Km

Identified during OWG

meeting and Demand

and Supply Analysis ULB

Support from

Government/Financial

institution, ULB

Contribution

Cheran Colony North Side Cross Roads for a

length of 0.62 Km

Identified during OWG

meeting and Demand

and Supply Analysis ULB

Support from

Government/Financial

institution, ULB

Contribution

Creating additional 4.4 Km by 2023-24.

Identified during OWG

meeting and Demand

and Supply Analysis ULB

Support from

Government/Financial

institution, ULB

Contribution

Creating foot path in MTP Main road from

Appnaicken palayam main road to Sowdabikha

complex

Identified during OWG

meeting and Demand

and Supply Analysis ULB

Support from

Government/Financial

institution, ULB

Contribution

Creating foot path in Railway station Road

Identified during OWG

meeting and Demand

and Supply Analysis ULB

Government/Financial

institution, ULB

Contribution

Creating foot path in Subramaniam palayam main

road from Mahalakshmi Bakery to Subramaniam

palayam School

Identified during OWG

meeting and Demand

and Supply Analysis ULB

Support from

Government/Financial

institution, ULB

Contribution

Annexure IV: Project Implementation Schedule for Thudiyalur

Particulars Current Status 2009-10

2010-11

2011-12

2012-13

2013-14

2014-15

2015-16

2016-17

2017-18

2018-19

2019-20

2020-21

2021-22

2022-23

2023-24

Assistance

Street Lighting & Energy

Saving Mechanism

Replacing 40W Tube lights into 36 W

Identiifed based on

Demand supply Gap

Analysis and to be

implemented in Phases PSP ULB

Installing electronic chokes for all tube light fittings

Identiifed based on

Demand supply Gap

Analysis and to be

implemented in Phases PSP ULB

Replacing 250 W 146 Nos SVL with (4 X 24) W T5

lamps

Identiifed based on

Demand supply Gap

Analysis and to be

implemented in Phases PSP ULB

Installing 384 light fittings with poles (1/3rd of the

future demand)

Identiifed based on

Demand supply Gap

Analysis and to be

implemented in Phases PSP ULB

Annexure IV: Project Implementation Schedule for Thudiyalur

Particulars Current Status 2009-10

2010-11

2011-12

2012-13

2013-14

2014-15

2015-16

2016-17

2017-18

2018-19

2019-20

2020-21

2021-22

2022-23

2023-24

Assistance

Socio-Economic

Infrastructure

Construction of Shopping Complex at weekly

shandy East side South facing Part-I (Vellakinar

Road)

Identified during OWG

meeting and to be

implemented in 2010-11 ULB

Support from

Government and ULB

Construction of Shopping Complex at weekly

shandy East side South facing Part-II (Vellakinar

Road)

Identified during OWG

meeting and to be

implemented in 2011-12 ULB

Support from

Government and ULB

Constructing community hall in subramaniyam

palayam and in Raju garden

Identified during OWG

meeting and to be

implemented in 2014-15 ULB

Support from

Government and ULB

Developing parks in Balaji Nagar, Srimurugan

Nagar, Sai Nagar, Visanatha puram, 2nd Ward

Thondupatti, Appanaican palayam near tank,

Mullai nagar, Thirupathi nagar and V.C.S. nagar

Identified during OWG

meeting and to be

implemented in phases ULB

Support from

Government and ULB

Developing parks in VP nagar, Cape town, Swati

garden, Muthammal layout

Identified during OWG

meeting and to be

implemented in 2015-16 ULB

Support from

Government and ULB

Developing Shandy

Identified during OWG

meeting and to be

implemented in 2011-12 ULB

Support from

Government and ULB

Creating modern slaughter house

Identified during OWG

meeting and to be

implemented in 2019-20

Burial ground improvement in Appanaikan

palayam and in Subramaniam palayam

Identified during OWG

meeting and to be

implemented in 2016-17

Creating road side park in Railway station road, in

Muthunagar roads, from Cheran Colony to

Viswanathapuram

Identified during OWG

meeting and to be

implemented in 2012-13

Annexure V: Reforms Implementation Schedule For Thudiyalur

Reforms

Current status 20

09

-10

20

10

-11

20

11

-12

20

12

-13

20

13

-14

20

14

-15

20

15

-16

20

16

-17

20

17

-18

20

18

-19

20

19

-20

20

20

-21

20

21

-22

20

22

-23

20

23

-24

Property Tax

Mandatory Implementation of Revision of Property

Tax once in every five years is required Once in 10 years

Digitization of the property maps through GIS Not done

Computerization of Property tax records To be Initiated

Introducing alternate methods of tax payment

(ECS/EFT/Online Payment)

Currently in Municipal

office only

Other Reforms in property taxes as mentioned in

Reforms Chapter 15 of this report Limited extent

Water Supply

Service coverage of water connections to be

increased from current 84% to 85% 84% 84.00% 84.42% 84.46% 84.48%

Revision of Water supply charges and initial deposit

for new water connection Ad hoc basis

THUDIYALUR

85%

Annexure V: Reforms Implementation Schedule For Thudiyalur

Reforms

Current status 20

09

-10

20

10

-11

20

11

-12

20

12

-13

20

13

-14

20

14

-15

20

15

-16

20

16

-17

20

17

-18

20

18

-19

20

19

-20

20

20

-21

20

21

-22

20

22

-23

20

23

-24

One time payment options for monthly water

charges Not done

Incentive and penalty structure for payment of water

taxes and charges. Not done

Water Leakage Audit for Un-accounted for Water

(UFW) Not done

Energy Audit Study has been initiated

Periodic maintenance of Water supply systems Ad hoc maintenance

Periodic Training to Water Supply Staff

Not done. To be

imparted on a regular

basis

Privatization in routine maintenance relating to water

supply Not done

Annexure V: Reforms Implementation Schedule For Thudiyalur

Reforms

Current status 20

09

-10

20

10

-11

20

11

-12

20

12

-13

20

13

-14

20

14

-15

20

15

-16

20

16

-17

20

17

-18

20

18

-19

20

19

-20

20

20

-21

20

21

-22

20

22

-23

20

23

-24

Sewerage and Sanitation

Privatization of maintenance of sewerage system

can be considered to reduce the establishment

charges of municipality and O&M Charges NA

Revision in Sewer Monthly user charges NA

Revision in initial deposit for new sewer connections NA

Periodic maintenance of Sewer supply systems NA

Annual Maintenance Contract for Sewage Pumping

Stations and Sewage Treatment Plants can be

adopted. NA

Incentive and penalty structure for payment of

Sewer taxes and charges. NA

Periodic technical training to its engineering cell is

required in O&M of Sewage Treatment Plant,

Pumping Stations and Sewer Networking System. NA

Storm Water Drainage

Achieving drain length of 100 percent of road length

by 2023-24 67 72% 86%

100%

Annexure V: Reforms Implementation Schedule For Thudiyalur

Reforms

Current status 20

09

-10

20

10

-11

20

11

-12

20

12

-13

20

13

-14

20

14

-15

20

15

-16

20

16

-17

20

17

-18

20

18

-19

20

19

-20

20

20

-21

20

21

-22

20

22

-23

20

23

-24

Solid Waste Management

Door to door collection of garbage at household

level and segregation of waste at source

All of assessments are

covered by Door to

Door collection and

waste segregation

Private Sponsorship of bins for waste segregation at

source Not done

Introduction of user charges for Non-Domestic

assesses Not done

Introduction of user charges for Domestic assesses Not done

Annual Maintenance Contract for Vehicles used in

SWM Not done

Potential for getting carbon credit benefit through

the Clean Development Mechanism (CDM) need to

be studied in making a comprehensive solid waste

management scheme Not undertaken

Periodic Training to Public Health Staff Regularly

Annexure V: Reforms Implementation Schedule For Thudiyalur

Reforms

Current status 20

09

-10

20

10

-11

20

11

-12

20

12

-13

20

13

-14

20

14

-15

20

15

-16

20

16

-17

20

17

-18

20

18

-19

20

19

-20

20

20

-21

20

21

-22

20

22

-23

20

23

-24

Roads, Traffic & Transportation

Relaying Bitumen roads once in three years with

patch works to be undertaken based on the need in

between years ( Through use of recyclable materials

) Adhoc basis

Street Lighting & Energy Saving

Mechanism

Achieving 41 meters street light spacing by 2023-24 54 metres

Energy Audit Studies

To be Initiated. At

present None

Private parties can be involved for financing,

operation and maintenance of energy efficient street

light projects to reduce the cost incurred for the

same.

Only O & M of street

lights

Annexure V: Reforms Implementation Schedule For Thudiyalur

Reforms

Current status 20

09

-10

20

10

-11

20

11

-12

20

12

-13

20

13

-14

20

14

-15

20

15

-16

20

16

-17

20

17

-18

20

18

-19

20

19

-20

20

20

-21

20

21

-22

20

22

-23

20

23

-24

Municipal Assets

Creation and updating the Comprehensive asset

register with regard to land and building Not Comprehensive

Valuation of assets and liabilities of the Municipality Not done

Periodic maintenance of Social Infrastructure Ad hoc

Accounting Reforms

Comprehensive Budgeting incorporating O&M costs

of various assets Not Done

Periodic Training to Accounting Staff Regularly

Finalisation of accounts and completion of audit of

accounts with in that specific year Not done

Zero based budgeting would need to be carried out

for continual monitoring of budgets and cash flow

management Not done

Page 1 of 3

Minutes of the Inception Report review meeting for the consultancy

assignment for City Investment Plan (CIP) prepared by M/s. Darashaw &

Company Limited for Annamalai Nagar, Vadalur, Tharangampadi,

Ottenchataram, Thudiyalur, Thirupattur, S. Kannanur and Peravurani Town

Panchayats (Cluster 1) held on 28.08.2009 at 3.00 PM at TNUIFSL office.

Members Present:

S.No. Name Designation / Organisation

1 Mr.T.P.Subramanian President, Thudiyalur

2 Mr.A.Mahalingam EO, Thudiyalur

3 Mr.R.Subramanian Sanitary Inspector, Tharangampadi

4 Mr.A.Amanulla EO, Tirupattur

5 Mr.M.Jeyakodi EO, Ottenchataram

6 Mr.S.Gunalan EO, S.Kannanur

7 Mr.T.Srinivasan Junior Assistant, Vadalur

8 Mr.D.Ranganathan EO, Annamalai Nagar

9 Mr.B.Janarthanan EO,Peravurani

10 Mr.G.Habeeb Raja Jr.Asst, Tirupattur

11 Mr.D.Rajendiran AVP,TNUIFSL

12 Mr.U.Vijayaraghavan DM, TNUIFSL

13 Ms.K.Vyjayanthi Head-Southern Region,Darashaw

14 Mr.C.Gandhiraj Sr.Associate, Darashaw

15 Ms.R.Devi Associate, Darashaw

The consultants made the presentation through power point for inception report

for the consultancy assignment for City Investment Plan (CIP) for Annamalai

Nagar, Vadalur, Tharangampadi, Ottenchataram, Thudiyalur, Thirupattur, S.

Kannanur and Peravurani Town Panchayats (Cluster 1) in detail and the

consultants are requested to

1. To conduct stakeholders’ consultations to ascertain the demands from

public to identify infrastructure gaps.

Page 2 of 3

2. To present the draft final report to respective ULBs in the council after

incorporating the suggestions of stake holders meeting.

3. Recheck the financials of ULBs including debt status.

4. Analyse last 5 years financials and furnish the data on existing loan, loan

repaid on due date, overdue loan, loan balance and loans sanctioned but

yet to be availed. In this regard, all Town Panchayats were requested to

provide 5 years audited accounts and recent years’ un-audited accounts

along with DCB and loan statements and any other relevant details to the

consultants.

5. Study on the unused / under utilized assets of the ULB and suggest ways

for the better utilization of the same.

6. To identify any vacant land for development.

Annamalai Nagar:

- The consultants were requested to include the Storm Water Drain Project.

- Street light provision calculation to be rechecked with ULB.

Vadalur:

- DCB presented to be rechecked with ULB.

Tarangambadi:

- The consultants were requested to include the treatment plant in the

Water Supply Project.

- Reason for reduction in property tax assessment to be addressed

Ottanchataram:

- SWM on wastage generated in the markets area to be addressed and

suggest the ways / methodologies for improvement.

Page 3 of 3

Thudiyalur:

- Address the land issue for UGSS project.

- Address the need of the commercial centre

- Street light provision calculation to be rechecked with ULB.

Tirupathur:

- Address the need of the water body improvement.

The representatives of ULBs were requested to provide details of all the assets to

the consultants and the consultants were requested to include the same and

suggest optimum utilization of the assets.

The inception report submitted by the consultant is approved and consultant

was requested to incorporate the above comments in draft final report and

adhere to the schedule as per the Term of Reference for submitting the Draft

Final Report.

Minutes of the Draft Final Report review meeting for the consultancy

assignment for Town Investment Plan (TIP) submitted by M/s. Darashaw &

Company Limited for Annamalai Nagar, Vadalur, Tharangambadi,

Ottenchataram, Thudiyalur, Thirupattur, S. Kannanur and Peravurani Town

Panchayats (Cluster 1) held on 23.12.2009 at 2.30 P M at Directorate of Town

Panchayats office, Chennai - 108.

Members Present:

S.No. Name Designation / Organisation

1 Mr. D. Rajendiran, IAS Director of Town Payanchayat

2 Mr. T.P. Subramanian President, Tudiyalur TP

3 Mr. G. Rajendiran EE / DTP

4 Mr. Nellai Sivagaminathan AEE / DTP

5 Mr. U. Vijayaraghavan DM / TNUIFSL

6 Mr. A. Sadayappan ADTP / Cuddalore

7 Ms. R. Joychirstel ADTP / Coimbatore

8 Mr. M. Balasubramanian ADTP / Thanjavore

9 Mr. K.S. Rajagopalan Asst. / DTP

10 Mr. M. Jayakodi EO, Ottanchatiram

11 Mr. S. Gunalan EO, S. Kannanur

12 Mr. D. Ranganathan EO, Annamalai Nagar

13 Mr. A. Mahalingam EO, Tudiyalur

14 Mr. G. Mangaleswaran EO, Tiruppattur

15 Mr. K. Balasubramanian EO, Tarangambadi

16 Mr. B. Janarthanan EO, Peravurani

17 Mr. K. Sridhar Associate, Darashaw & Co.,

18 Mr. C. Gandhiraj Sr. Associate, Darashaw & Co.,

19 Ms. R. Devi Associate, Darashaw & Co.,

The consultants submitted the draft final report and made presentation for the

consultancy assignment for Town Investment Plan (TIP) for Annamalai Nagar,

Vadalur, Tharangampadi, Ottenchataram, Thudiyalur, Thirupattur, S. Kannanur

and Peravurani Town Panchayats (Cluster 1) in detail and the consultants are

requested to incorporate the following suggestions / comments in the final report

which are listed below:

Thudiyalur:

� To recheck the financial of ULB for the financial year 2007-08, 2008-09

based on the actuals financial statement and do the FOP.

� Any changes in the rates, etc may be obtained from ULB and incorpoorate

the same in final report.

Vadalur:

� The ULB is requested to provide the break up of Programme expense for

preparation of FOP for the town.

Tharangambadi:

� The land ownership details of the agricultural office building in the same

premises of the Town Panchayat Office has to be provided by the ULB to

the consultants and the project cost of Rs. 30 lakhs for the same can be

shifted to second phase.

Oddanchatram:

� After consultation with EO, TP the Combined Water Supply Scheme the

finalise the priority of the project from second phase to third phase in CIP.

� Creating Green spaces in the Gassifier crematorium ground – As the town

has already taken up the project worth Rs. 5 Lakhs the same needs to be

removed from the CIP.

� The cost of ponnagramkulam improvement project which was earlier

suggested under revenue department purview can be implemented by TP

and the cost for the same needs to be incorporated in the CIP.

� After consultation with EO the cost of office building to be included in the

CIP.

� The ULB is requested to provide the break up of Programme expense to

consultants in detail.

Peravurani:

� Strengthening banks in ward 13 & 14 has to be checked as the same is

repeated twice in the CIP.

The representatives of TPs were requested to provide details of their updated

financials, Loan details, and also on the works/projects already taken up by them

to the consultants. The Draft Final Report submitted by the consultant is hereby

approved and consultants were requested to incorporate the above comments in

Final Report and adhere to the schedule as per the Term of Reference for

submitting the Final Report.