Transcript of Tender No. 03/Central/2016 - ANNEXURE
1
Tender No. 03/Central/2016
Sr.DEN/Central/BZA Signature of Tenderer(s)
Page 1 of 91 BZA Divn., SCR, T.No.03/Central/2016 invited vide Open Tender No.DRM/Works/BZA/03/2016 dt. 05.02.2016, date of opening on 08.03.2016 for the work of SW-I) BZA Division: GDR-BZA sec.Proposed safety related track repairs in SSE/P.Way /CLX, BPP and TEL sections of ADEN/BPP Sub- Division. SW-II) BZA Division: BZA-VSKP sec.Proposed safety related track repairs in SSE/P.Way /Eluru & Nuzvid sections of ADEN/Eluru Sub- Division. SW-III) BZA Division: GDR-BZA sec. Transportation of P.Way materials for scattered and casual renewals Departmentally and for collection scrap in yards for the year 2015-16 in ADEN/BPP sub-division. SW-IV) BZA Division: BZA - VSKP Sec. Transportation of P.Way materials for scattered and casual renewals Departmentally and for collection scrap in yards for the year 2015-16 in ADEN/EE sub-division. SW-V) BZA Division: GDR-BZA sec.: TFR - Through fitting renewal for a length of 65.45km (without ERC) and 1.46km (with all fittings) on up & Dn lines in ADEN/Bapatla Sub-division. SW-VI) BZA Division: GDR-BZA sec.KCC: Shifiting of crossover S103A &B towards Gudur duly making TRD and S&T alterations in KCC yard in ADEN/BPP sub-division SW-VII) BZA Division: GDR-BZA sec. KCC- Shifting of layout of crossover S121 in KCC yard in ADEN/BPP sub-division. SW-VIII) BZA Division: GDR-BZA sec. KCC - Replacement of
Non-standard diamond crossing at KCC yard Pt No. 144A,B & 145 A,B in KCC yard in ADEN/BPP sub-division. . . .
ANNEXURE -“I”
CHECK LIST OF DOCUMENTS TO BE SUBMITTED ALONG WITH TENDERS.
(Tenderers are requested to give certificate and/or put ( ) mark wherever applicable.)
1.0 Tenderer details:
1.1 Name of the Tenderer
1.2 Identification of Tenderer
i. In case of Partnership Firm: A copy of
Partnership deed with latest modifications of the
deed, if any, attested by any Gazetted Officer.
ii. In case of Consortium, JV or MOU: A copy of
either JV agreement attested by any Gazetted
Officer or MOU in original.
iii. In case of Company: A copy of Articles of
Association attested by any Gazetted Officer.
iv. In case of Proprietary Firm: A copy of registration
/ Income tax/ PAN No. for filing returns attested
by any Gazetted Officer.
02 Particulars of DD/MR submitted towards cost of Tender
form.
03 Particulars of MR/BC/DD submitted towards EMD.
04 Engineering Organization in Annexure – “A”
05 List of Plants & Machinery in Annexure – “B”
06 List of works completed during the last three Financial
Years in Annexure – “C”
07 List of Works on Hand in Annexure – “D”
08 Attested copy of Experience Certificate in Annexure –
“E”
09 Attested copy of Certificate showing Contractual
amounts received during the last three Financial years
and Current Financial Year in Annexure – “F”
10 NEFT MANDATE FORM
11 Registration Number of APGST / APVAT
12 Any other information / certificates required as per
Tender document.
13 Total Number of Annexure submitted ( Number of
Pages)
Address :
Phone No. : Signature of Tenderer/Contractor:
2
Tender No. 03/Central/2016
Sr.DEN/Central/BZA Signature of Tenderer(s)
Page 2 of 91 BZA Divn., SCR, T.No.03/Central/2016 invited vide Open Tender No.DRM/Works/BZA/03/2016 dt. 05.02.2016, date of opening on 08.03.2016 for the work of SW-I) BZA Division: GDR-BZA sec.Proposed safety related track repairs in SSE/P.Way /CLX, BPP and TEL sections of ADEN/BPP Sub- Division. SW-II) BZA Division: BZA-VSKP sec.Proposed safety related track repairs in SSE/P.Way /Eluru & Nuzvid sections of ADEN/Eluru Sub- Division. SW-III) BZA Division: GDR-BZA sec. Transportation of P.Way materials for scattered and casual renewals Departmentally and for collection scrap in yards for the year 2015-16 in ADEN/BPP sub-division. SW-IV) BZA Division: BZA - VSKP Sec. Transportation of P.Way materials for scattered and casual renewals Departmentally and for collection scrap in yards for the year 2015-16 in ADEN/EE sub-division. SW-V) BZA Division: GDR-BZA sec.: TFR - Through fitting renewal for a length of 65.45km (without ERC) and 1.46km (with all fittings) on up & Dn lines in ADEN/Bapatla Sub-division. SW-VI) BZA Division: GDR-BZA sec.KCC: Shifiting of crossover S103A &B towards Gudur duly making TRD and S&T alterations in KCC yard in ADEN/BPP sub-division SW-VII) BZA Division: GDR-BZA sec. KCC- Shifting of layout of crossover S121 in KCC yard in ADEN/BPP sub-division. SW-VIII) BZA Division: GDR-BZA sec. KCC - Replacement of
Non-standard diamond crossing at KCC yard Pt No. 144A,B & 145 A,B in KCC yard in ADEN/BPP sub-division. . . .
TENDER NO.03/Central/2016
1. The offer of tenderer(s) who do not enclose Experience Certificate and Turnover Certificate with requisite details and supporting documents as detailed under Para 2 & 3 of Eligibility Criteria in Page-6 to 8 along with their Tender to establish their credentials shall be summarily rejected, even though they are working contractors or contractors on approved list. 2. Tenderer may please observe the new conditions of the tender document in “Note to Tenderers” and “Conditions of Tender” vide Sl.No.9 and 10 & Sl.No.25 to 31 respectively.
For Attention of Tenderer Modification of EMD, Performance Guarantee, Security deposit, Introduction of PVC and Token penalty
S.No. Details Reference
1 Modification of EMD Item No.7 Conditions of Tender
2 Modification of Performance Guarantee Item No.9
Special conditions of Contract
3 Modification of Security Deposit Item No.10
4 Introduction of PVC Item No.11
5 Implementation of Building and other Construction
Workers Welfare Cess Act, 1996
Item 14
6 Token Penalty Item 8(b) Works Contract Clause-13
Name and address of Tenderer
Money Receipt/ D.D. No. & date for cost
of Tender form enclosed
SOUTH CENTRAL RAILWAY
WORKS CONTRACT; REGULATIONS OF TENDERS AND CONTRACTS;
CONDITIONS OF TENDER; TENDER AGREEMENT FORM
Open Tender Notice No. DRM/Works/BZA/03/2016 dt. 05.02.2016
Last date for issue of tender forms by post 24.02.2016
Last date for issue of tender forms in person 04.03.2016 upto18-00 hours
Date and time for submission of tenders 08.03.2016 upto 15.45 Hours
Date and time for opening of tenders 08.03.2016 at 16.00 Hours
Name of work:- SW-I) BZA Division: GDR-BZA sec.Proposed safety related track repairs in SSE/P.Way /CLX, BPP and TEL sections of ADEN/BPP Sub- Division. SW-II) BZA Division: BZA-VSKP sec.Proposed safety related track repairs in SSE/P.Way /Eluru & Nuzvid sections of ADEN/Eluru Sub- Division. SW-III) BZA Division: GDR-BZA sec. Transportation of P.Way materials for scattered and casual renewals Departmentally and for collection scrap in yards for the year 2015-16 in ADEN/BPP sub-division. SW-IV) BZA Division: BZA - VSKP Sec. Transportation of P.Way materials for scattered and casual renewals Departmentally and for collection scrap in yards for the year 2015-16 in ADEN/EE sub-division. SW-V) BZA Division: GDR-BZA sec.: TFR - Through fitting renewal for a length of 65.45km (without ERC) and 1.46km (with all fittings) on up & Dn lines in ADEN/Bapatla Sub-division. SW-VI) BZA Division: GDR-BZA sec.KCC: Shifiting of crossover S103A &B towards Gudur duly making TRD and S&T alterations in KCC yard in ADEN/BPP sub-division SW-VII) BZA Division: GDR-BZA sec. KCC- Shifting of layout of crossover S121 in KCC yard in ADEN/BPP sub-division. SW-VIII) BZA Division: GDR-BZA sec. KCC - Replacement of Non-standard diamond crossing at KCC yard Pt No. 144A,B & 145 A,B in KCC yard in ADEN/BPP sub-division.
Similar nature of works:- Any Railway track work or track maintenance work.
Period of completion 11 (Eleven) months
Approximate value Rs. 4,49,37,778/
E.M.D. Rs. 3,74,690/-
Cost of Tender form Rs. 10,000/-in person & Rs.10,500/-by Post
3
Tender No. 03/Central/2016
Sr.DEN/Central/BZA Signature of Tenderer(s)
Page 3 of 91 BZA Divn., SCR, T.No.03/Central/2016 invited vide Open Tender No.DRM/Works/BZA/03/2016 dt. 05.02.2016, date of opening on 08.03.2016 for the work of SW-I) BZA Division: GDR-BZA sec.Proposed safety related track repairs in SSE/P.Way /CLX, BPP and TEL sections of ADEN/BPP Sub- Division. SW-II) BZA Division: BZA-VSKP sec.Proposed safety related track repairs in SSE/P.Way /Eluru & Nuzvid sections of ADEN/Eluru Sub- Division. SW-III) BZA Division: GDR-BZA sec. Transportation of P.Way materials for scattered and casual renewals Departmentally and for collection scrap in yards for the year 2015-16 in ADEN/BPP sub-division. SW-IV) BZA Division: BZA - VSKP Sec. Transportation of P.Way materials for scattered and casual renewals Departmentally and for collection scrap in yards for the year 2015-16 in ADEN/EE sub-division. SW-V) BZA Division: GDR-BZA sec.: TFR - Through fitting renewal for a length of 65.45km (without ERC) and 1.46km (with all fittings) on up & Dn lines in ADEN/Bapatla Sub-division. SW-VI) BZA Division: GDR-BZA sec.KCC: Shifiting of crossover S103A &B towards Gudur duly making TRD and S&T alterations in KCC yard in ADEN/BPP sub-division SW-VII) BZA Division: GDR-BZA sec. KCC- Shifting of layout of crossover S121 in KCC yard in ADEN/BPP sub-division. SW-VIII) BZA Division: GDR-BZA sec. KCC - Replacement of
Non-standard diamond crossing at KCC yard Pt No. 144A,B & 145 A,B in KCC yard in ADEN/BPP sub-division. . . .
NOTE TO TENDERERS
1) Tender forms in the prescribed form may be obtained from the office of the Divisional Railway
Manager, Works, S.C. Railway, Vijayawada, on production of cash receipt for each tender form
at the rates mentioned on the cover page and in the Tender Notice. If any plan/drawing is
attached with the tender form, Rs.200/- for plan/drawing will be levied extra. The amount
towards the cost of tender form may be remitted to the Divisional Cashier (Pay) S.C.Railway,
Vijayawada, Guntur, Secunderabad, Hyderabad, Guntakal and Nanded, Chief Cashier (Pay),
S.C.Railway, Secunderabad or any Station Master/Station Superintendent on S.C. Railway and
the receipt obtained thereof should be submitted to this office with a requisition for issue of
tender form. Money Orders, Postal Orders, etc, will not be considered for issue of tender forms.
The tender forms are not transferable and the cost of the tender form is not refundable. This
office will not entertain direct payment. Tender Number, Description of the work, etc. should be
written on the sealed cover addressed to the Divisional Railway Manager (Works), S.C.Railway,
Vijayawada, while submitting the Tender document.
2) The Tender forms are available for sale in the office of Divisional Railway Manager (Works),
S.C.Railway, Vijayawada and also in S.C.Railway Web site.
3) Tender conditions / other particulars are available in the Tender documents uploaded along with
the Tender Notice on our website at http://www.scr.indianrailways.gov.in” which can be
downloaded.
4) The prospective tenderers are advised to visit website “http://www.scr.indianrailways.gov.in”
three days before the date of tender opening to note any changes/corrigenda for any tender.
5) The Tender Notice is also displayed in the Notice Board located in the office of Divisional
Railway Manager (Works), S.C.Railway, Vijayawada which can be seen on all working days.
6) The Railway reserves the right to cancel the tender without assigning any reason thereto.
7) Venue: Tender documents, duly completed in all respects shall be dropped in the Tender Box
kept for the purpose at Divisional Railway Manager‟s Office (Works), South Central Railway,
Vijayawada, Krishna District (or) may be sent by post to Divisional Railway Manager (Works),
South Central Railway, Vijayawada, Krishna District(A.P.). Railway is not responsible for any
delay in transit (or) loss of Tender form sent/received by Post.
8) If the date of opening happens to be a holiday, the tenders will be opened on the next working
day.
9) The tenders will be opened on the date and time mentioned in the tender document and in
the presence of tenderers/their authorized representatives. Any tender received after the
stipulated time will be summarily rejected.
10) Tenderers‟ representatives are advised to bring authorization letter from the
tenderer/firms for attending tender opening and when witnessing tender opening should
write their full name, contact number, agency / contractor that they are representing and
their address in the tender opening register.
Visit our site at “http://www.scr.indianrailways.gov.in
4
Tender No. 03/Central/2016
Sr.DEN/Central/BZA Signature of Tenderer(s)
Page 4 of 91 BZA Divn., SCR, T.No.03/Central/2016 invited vide Open Tender No.DRM/Works/BZA/03/2016 dt. 05.02.2016, date of opening on 08.03.2016 for the work of SW-I) BZA Division: GDR-BZA sec.Proposed safety related track repairs in SSE/P.Way /CLX, BPP and TEL sections of ADEN/BPP Sub- Division. SW-II) BZA Division: BZA-VSKP sec.Proposed safety related track repairs in SSE/P.Way /Eluru & Nuzvid sections of ADEN/Eluru Sub- Division. SW-III) BZA Division: GDR-BZA sec. Transportation of P.Way materials for scattered and casual renewals Departmentally and for collection scrap in yards for the year 2015-16 in ADEN/BPP sub-division. SW-IV) BZA Division: BZA - VSKP Sec. Transportation of P.Way materials for scattered and casual renewals Departmentally and for collection scrap in yards for the year 2015-16 in ADEN/EE sub-division. SW-V) BZA Division: GDR-BZA sec.: TFR - Through fitting renewal for a length of 65.45km (without ERC) and 1.46km (with all fittings) on up & Dn lines in ADEN/Bapatla Sub-division. SW-VI) BZA Division: GDR-BZA sec.KCC: Shifiting of crossover S103A &B towards Gudur duly making TRD and S&T alterations in KCC yard in ADEN/BPP sub-division SW-VII) BZA Division: GDR-BZA sec. KCC- Shifting of layout of crossover S121 in KCC yard in ADEN/BPP sub-division. SW-VIII) BZA Division: GDR-BZA sec. KCC - Replacement of
Non-standard diamond crossing at KCC yard Pt No. 144A,B & 145 A,B in KCC yard in ADEN/BPP sub-division. . . .
SOUTH CENTRAL RAILWAY
STANDARD REGULATIONS FOR TENDERS AND CONTRACTS
Sl.
No.
Contents Page
No.
1 Instructions for submission of Tender documents by
downloading from Website
5
2 ELIGIBILITY CRITERIA with conditions and
connected Annexures
6
3 Annexure-I(a) – Tender 15
4 Annexure-II - Agreement of works 17
5 Regulations for tenders and contracts for guidance of
contractors for civil engineering works- meaning of
terms.
18
6 Conditions of Tender 21
7 Special conditions of Contract 25
8 Works Contract Clause -13 -Annexure – „III‟ 34
9 Special Conditions Modification to Clause 63 & 64 of
General Conditions of Contract
39
10 Performance Guarantee 40
11 Schedule of items and quantities in respect of items
covered by SSR and items not cover by SSR
42
5
Tender No. 03/Central/2016
Sr.DEN/Central/BZA Signature of Tenderer(s)
Page 5 of 91 BZA Divn., SCR, T.No.03/Central/2016 invited vide Open Tender No.DRM/Works/BZA/03/2016 dt. 05.02.2016, date of opening on 08.03.2016 for the work of SW-I) BZA Division: GDR-BZA sec.Proposed safety related track repairs in SSE/P.Way /CLX, BPP and TEL sections of ADEN/BPP Sub- Division. SW-II) BZA Division: BZA-VSKP sec.Proposed safety related track repairs in SSE/P.Way /Eluru & Nuzvid sections of ADEN/Eluru Sub- Division. SW-III) BZA Division: GDR-BZA sec. Transportation of P.Way materials for scattered and casual renewals Departmentally and for collection scrap in yards for the year 2015-16 in ADEN/BPP sub-division. SW-IV) BZA Division: BZA - VSKP Sec. Transportation of P.Way materials for scattered and casual renewals Departmentally and for collection scrap in yards for the year 2015-16 in ADEN/EE sub-division. SW-V) BZA Division: GDR-BZA sec.: TFR - Through fitting renewal for a length of 65.45km (without ERC) and 1.46km (with all fittings) on up & Dn lines in ADEN/Bapatla Sub-division. SW-VI) BZA Division: GDR-BZA sec.KCC: Shifiting of crossover S103A &B towards Gudur duly making TRD and S&T alterations in KCC yard in ADEN/BPP sub-division SW-VII) BZA Division: GDR-BZA sec. KCC- Shifting of layout of crossover S121 in KCC yard in ADEN/BPP sub-division. SW-VIII) BZA Division: GDR-BZA sec. KCC - Replacement of
Non-standard diamond crossing at KCC yard Pt No. 144A,B & 145 A,B in KCC yard in ADEN/BPP sub-division. . . .
Instructions for submission of Tender documents by downloading from
Website
1. Tender schedules are uploaded along with the Tender Notice and the same can be down
loaded and used as tender document for submitting the offer. However, the cost of tender
document as indicated on the cover page and in the Tender Notice has to be deposited by
the Tenderer in the form of a bank draft payable in favour of Senior Divisional Finance
Manager, S.C. Railway, Vijayawada or original money receipt obtained from Divisional
Cashier (Pay) S.C.Railway, Vijayawada, Guntur, Secunderabad, Hyderabad, Guntakal,
Chief Cashier (Pay), S.C.Railway, Secunderabad or any Station Master/Station
Superintendent on S.C. Railway along with the Tender document. This should be paid
separately and not clubbed with the Earnest Money deposit. In case, tender documents
are downloaded from website, the tenderers should enclose the requisite cost of
tender form. If tenderers download tender document from Website and do not
enclose proper money value towards the cost of tender form, their tender shall be
considered as invalid.
2. Tenderers are free to down load the tender document from the website at their own risk
and cost for the purpose of perusal and to use the same as tender document, if so desired
for submitting their offer. If the offer of any tenderer who has submitted the Tender
document down loaded from the website is accepted, the contract agreement will be
prepared based on the master copy of the document and will be binding on the
contractor. The Railway does not own any responsibility for any alteration/omission in
the contents of the Tender form uploaded on the web site. No claim on this account will
be entertained.
3. The administration will not own any responsibility, if website is not opened for
downloading / uploading the tender documents due to any technical snag.
4. The prospective tenderers are advised to visit website
“http://www.scr.indianrailways.gov.in” three days before the date of tender opening to
note any changes/corrigenda for any tender.
5. Warning: It is hereby brought to the notice of all prospective tenderers that if any
change/additions/deletions/ alterations are found to be made by them and the same
is subsequently detected / noticed at any stage even after award of the contract, all
necessary action including banning of business would be taken. In addition, the
tenderers are liable to be prosecuted under law.
6
Tender No. 03/Central/2016
Sr.DEN/Central/BZA Signature of Tenderer(s)
Page 6 of 91 BZA Divn., SCR, T.No.03/Central/2016 invited vide Open Tender No.DRM/Works/BZA/03/2016 dt. 05.02.2016, date of opening on 08.03.2016 for the work of SW-I) BZA Division: GDR-BZA sec.Proposed safety related track repairs in SSE/P.Way /CLX, BPP and TEL sections of ADEN/BPP Sub- Division. SW-II) BZA Division: BZA-VSKP sec.Proposed safety related track repairs in SSE/P.Way /Eluru & Nuzvid sections of ADEN/Eluru Sub- Division. SW-III) BZA Division: GDR-BZA sec. Transportation of P.Way materials for scattered and casual renewals Departmentally and for collection scrap in yards for the year 2015-16 in ADEN/BPP sub-division. SW-IV) BZA Division: BZA - VSKP Sec. Transportation of P.Way materials for scattered and casual renewals Departmentally and for collection scrap in yards for the year 2015-16 in ADEN/EE sub-division. SW-V) BZA Division: GDR-BZA sec.: TFR - Through fitting renewal for a length of 65.45km (without ERC) and 1.46km (with all fittings) on up & Dn lines in ADEN/Bapatla Sub-division. SW-VI) BZA Division: GDR-BZA sec.KCC: Shifiting of crossover S103A &B towards Gudur duly making TRD and S&T alterations in KCC yard in ADEN/BPP sub-division SW-VII) BZA Division: GDR-BZA sec. KCC- Shifting of layout of crossover S121 in KCC yard in ADEN/BPP sub-division. SW-VIII) BZA Division: GDR-BZA sec. KCC - Replacement of
Non-standard diamond crossing at KCC yard Pt No. 144A,B & 145 A,B in KCC yard in ADEN/BPP sub-division. . . .
1. ELIGIBILITY CRITERIA:-
FOR THE WORKS WHOSE ADVERTISED TENDER VALUE IS COSTING ABOVE
Rs.50 LAKHS. FOR TENDERS OF VALUE MORE THAN Rs.10 Cr., JV FIRM IS
ELIGIBLE FOR THE TENDER SUBJECT TO FULFILLMENT OF TECHNICAL
AND FINANCIAL ELIGIBIITY AS PER CLAUSE 65 OF GCC.( Ref: PCE/SC
Lr.No.W.148/P (Guide lines) Vol.II, dt.13.08.2014).
1.1 Similar nature of work
physically completed
during the last three
financial years* and in
the current Financial
year**
Eligibility in terms of Experience: The Tenderer(s) should
have physically completed at least one similar nature of single
work for a minimum value of 35% of advertised Tender value
within the qualifying period i.e., last three financial years* and
in the current Financial year** upto the date of Tender opening
(even though the work might have commenced before the
qualifying period).
1.2 Total Contract amount
received during the last
three financial years* and
in the current financial
year**
Eligibility in terms of Turnover: The total contract amount
received during the last three financial years and in the current
financial Year up to the date of Tender opening should be a
minimum of 150% of Advertised Tender Value
a) Tenderer(s) should submit to this effect certificate in original
or an attested certificate from the Govt./Semi Govt./Public
sector undertakings for the work done for them
or
b) Audited balance sheet along with P& L A/C duly certified by
the Chartered Accountant as detailed in Tender document.
NOTE:
*Financial Year shall normally, be reckoned as 1st April to 31
st March of the Next Year.
However, for Turnover Criteria, the Financial Year as applicable to the Company/Tenderer is
to be considered, if it defers from the above.
**Current Financial year is reckoned as the incomplete Financial year in which the date of
tender submission falls.
2.0 Clarification on “Similar nature of work” and details to be furnished along with the Tender
Documents:
2.1 Similar nature of work:- Similar nature of work is detailed at Page-2 and Page-42
2.2 Similar Nature of works physically completed within the qualifying period i.e. the last 3 Financial
years and the current financial year should only be considered in evaluating the Minimum
Eligibility criteria ( even though the work might have commenced before the qualifying period).
2.2.1 The work executed by them for any Govt./Govt.bodies/PSUs shall only be considered for eligibility
for credential verification of similar naure of work. As such works executed for any Private
Company/Individual shall not be treated as eligible works executed and certificates issued on behalf
of Private Company/Individual will not be considered.
2.2.2 Tenderer should submit attested copy of work experience certificate in Annexure-„E‟ to establish
the eligibility criteria. All details as required in the Annexure-„E‟, shall be made available
otherwise the information is treated as incomplete.
7
Tender No. 03/Central/2016
Sr.DEN/Central/BZA Signature of Tenderer(s)
Page 7 of 91 BZA Divn., SCR, T.No.03/Central/2016 invited vide Open Tender No.DRM/Works/BZA/03/2016 dt. 05.02.2016, date of opening on 08.03.2016 for the work of SW-I) BZA Division: GDR-BZA sec.Proposed safety related track repairs in SSE/P.Way /CLX, BPP and TEL sections of ADEN/BPP Sub- Division. SW-II) BZA Division: BZA-VSKP sec.Proposed safety related track repairs in SSE/P.Way /Eluru & Nuzvid sections of ADEN/Eluru Sub- Division. SW-III) BZA Division: GDR-BZA sec. Transportation of P.Way materials for scattered and casual renewals Departmentally and for collection scrap in yards for the year 2015-16 in ADEN/BPP sub-division. SW-IV) BZA Division: BZA - VSKP Sec. Transportation of P.Way materials for scattered and casual renewals Departmentally and for collection scrap in yards for the year 2015-16 in ADEN/EE sub-division. SW-V) BZA Division: GDR-BZA sec.: TFR - Through fitting renewal for a length of 65.45km (without ERC) and 1.46km (with all fittings) on up & Dn lines in ADEN/Bapatla Sub-division. SW-VI) BZA Division: GDR-BZA sec.KCC: Shifiting of crossover S103A &B towards Gudur duly making TRD and S&T alterations in KCC yard in ADEN/BPP sub-division SW-VII) BZA Division: GDR-BZA sec. KCC- Shifting of layout of crossover S121 in KCC yard in ADEN/BPP sub-division. SW-VIII) BZA Division: GDR-BZA sec. KCC - Replacement of
Non-standard diamond crossing at KCC yard Pt No. 144A,B & 145 A,B in KCC yard in ADEN/BPP sub-division. . . .
2.2.3 The work experience certificate shall be in the name and style of the tenderer participating or as
per provisions under Clause 65.16 of GCC for JV Firm, if eligible to participate. However, in
case the tenderer is submitting the certificate issued to a JV firm of which the Tenderer is a
member, the credentials proportionate to his share in the JV will be considered. The tenderer shall
submit a copy of relevant JV Agreement attested by any Gazetted Officer along with the Tender.
2.2.4 The work experience certificate shall be issued by an Officer not below the rank of JA Grade or
Bill passing Officer in Railways and Bill passing Officer/Executive In-charge of work in other
Govt./Govt. bodies/PSUs. The certificate should bear the signature and seal of the issuing officer,
name of the department etc.
2.2.5 In case the Certificate/Documents produced are proved to be false and/or fabricated, the entire
Earnest Money (EMD) will be forfeited.
2.2.6 Work experience certificate (Annexure E) shall be attested by any Gazetted officer, in case
photo copies are submitted.
2.3 Value of similar work to be considered:-
2.3.1 The total value of similar nature of works completed during the qualifying period, and not the
payments received within qualifying period alone, shall be considered.
2.3.2 In case, the final bill of similar nature of work has not been passed and final measurements have
not been recorded, the paid amount including Statutory Deduction will be considered
2.3.3 If final measurements have been recorded and work has been completed with negative variation,
then also the paid amount including Statutory Deduction will be considered.
2.3.4 However, if final measurements have been recorded and work has been completed with positive
variation but variation has not been sanctioned, original agreement value or last sanctioned
agreement value whichever is lower shall be considered for judging eligibility.
2.3.5 In case of composite works involving combination of different works, even separately completed
works of required value should be considered while evaluating the eligibility criteria.
2.3.6 The value of work completed will not include the cost of any materials issued free of cost by the
Railway/Department concerned. Only cash value of the Agreement and executed cash value will
reckon for eligibility.
3.0 Clarification on “Eligibility on Annual Contractual Turnover and Details to be furnished
along with the Tender Documents”.
3.1 The total contract amount received in the last three financial years and the current financial year up
to the date of tender submission shall be at least 150% of the Tender value.
3.2 For the completed Financial years, the Tenderer can submit either Audited Balance Sheets showing
clearly the contractual/work receipts in the Profit & Loss account of the Balance Sheet, duly
supported by a Turnover Certificate from the Chartered Accountant as per “Annexure-F”
or
Certificate(s) in original issued by Executive are Nominated Authority of the Department
certifying the bill amounts paid Agreement-wise and Date-wise or photo copy of such certificate
attested by a Gazetted Officer. Such certificates will be accepted only from Govt./Govt. bodies /
PSUs by authorities mentioned at Para 2 above.
3.3 For the incomplete Financial Year i.e. the Current year and for any Un-Audited Completed
8
Tender No. 03/Central/2016
Sr.DEN/Central/BZA Signature of Tenderer(s)
Page 8 of 91 BZA Divn., SCR, T.No.03/Central/2016 invited vide Open Tender No.DRM/Works/BZA/03/2016 dt. 05.02.2016, date of opening on 08.03.2016 for the work of SW-I) BZA Division: GDR-BZA sec.Proposed safety related track repairs in SSE/P.Way /CLX, BPP and TEL sections of ADEN/BPP Sub- Division. SW-II) BZA Division: BZA-VSKP sec.Proposed safety related track repairs in SSE/P.Way /Eluru & Nuzvid sections of ADEN/Eluru Sub- Division. SW-III) BZA Division: GDR-BZA sec. Transportation of P.Way materials for scattered and casual renewals Departmentally and for collection scrap in yards for the year 2015-16 in ADEN/BPP sub-division. SW-IV) BZA Division: BZA - VSKP Sec. Transportation of P.Way materials for scattered and casual renewals Departmentally and for collection scrap in yards for the year 2015-16 in ADEN/EE sub-division. SW-V) BZA Division: GDR-BZA sec.: TFR - Through fitting renewal for a length of 65.45km (without ERC) and 1.46km (with all fittings) on up & Dn lines in ADEN/Bapatla Sub-division. SW-VI) BZA Division: GDR-BZA sec.KCC: Shifiting of crossover S103A &B towards Gudur duly making TRD and S&T alterations in KCC yard in ADEN/BPP sub-division SW-VII) BZA Division: GDR-BZA sec. KCC- Shifting of layout of crossover S121 in KCC yard in ADEN/BPP sub-division. SW-VIII) BZA Division: GDR-BZA sec. KCC - Replacement of
Non-standard diamond crossing at KCC yard Pt No. 144A,B & 145 A,B in KCC yard in ADEN/BPP sub-division. . . .
Financial Year, only certificate on contractual / work receipts in original issued by Executives
of the Govt./Govt. bodies / PSUs from whom the payments were received or photo copy of
such certificate attested by a Gazatted Officer, giving details of receipts Agreement-wise and
Date-wise will be accepted as proof of contractual Turnover for the current year and that
completed but un-audited Financial Year. Certificates issued by Private Companies /
Individuals will not be entertained.
4.0 Additional Documents to be submitted along with the Tender:-
4.1 List of personnel organization available on hand and proposed to be engaged for the subject
work. These two lists should be given separately and signed by Tenderer and are to be
submitted in the Proforma given in the Annexure-„A‟.
4.2 List of Plant & Machinery available on hand (own) and proposed to be inducted (own and hired
to be given separately) for the subject work and this list shall be signed by the tenderer and is to
be submitted in the Proforma given in the Annexure-„B
4.3 List of completed works in the last three Financial years giving description of work,
Organisation for whom executed, approximate value of contract at the time of award, date of
award and date of scheduled completion of work, date of actual start, actual completion and
final value of contract should also be given in the Annexure-„C‟.
4.4 List of works on hand indicating name of work, contract value, bill amount paid so far; due
date of completion etc. to be furnished by Contractor in Annexure-„D‟ and this certificate is to
be signed by Contractor.
4.5 In case, tender documents are downloaded from website, the tenderers should enclose the
requisite cost of tender form. If tenderers download tender document from Website and do not
enclose proper money value towards the cost of tender form, their tender shall be considered as
invalid.
5.0 A checklist of documents to be submitted at the time of tender submission is given as top
sheet in Annexure-I for easy guidance and compliance from prospective Tenderers.
6.0 Delayed / Post Tender submission of Documents/information of Mandatory Nature
linked to eligibility criteria called for at Tender stage:-
6.1 The offer of Tenderer(s) who do not enclose Experience Certificate and Turnover Certificate
with requisite details and supporting documents as detailed under Para 2 & 3 above along with
their Tender to establish their credentials shall be summarily rejected, even though they are
working contractors or contractors on approved list.
6.2
(i)
The offer shall be evaluated only from the certificates / documents (as referred above)
submitted along with the tender offer. (ii) Any Certificate / Documents offered after the tender opening shall not be given any credit and
shall not be considered. (iii) Tenderer(s) shall note that conditional / alternate offer will not be considered and will
summarily be rejected, even though such condition makes them as the lowest tenderer. (iv) Railway reserves the right to verify the authenticity of the documents / information furnished.
9
Tender No. 03/Central/2016
Sr.DEN/Central/BZA Signature of Tenderer(s)
Page 9 of 91 BZA Divn., SCR, T.No.03/Central/2016 invited vide Open Tender No.DRM/Works/BZA/03/2016 dt. 05.02.2016, date of opening on 08.03.2016 for the work of SW-I) BZA Division: GDR-BZA sec.Proposed safety related track repairs in SSE/P.Way /CLX, BPP and TEL sections of ADEN/BPP Sub- Division. SW-II) BZA Division: BZA-VSKP sec.Proposed safety related track repairs in SSE/P.Way /Eluru & Nuzvid sections of ADEN/Eluru Sub- Division. SW-III) BZA Division: GDR-BZA sec. Transportation of P.Way materials for scattered and casual renewals Departmentally and for collection scrap in yards for the year 2015-16 in ADEN/BPP sub-division. SW-IV) BZA Division: BZA - VSKP Sec. Transportation of P.Way materials for scattered and casual renewals Departmentally and for collection scrap in yards for the year 2015-16 in ADEN/EE sub-division. SW-V) BZA Division: GDR-BZA sec.: TFR - Through fitting renewal for a length of 65.45km (without ERC) and 1.46km (with all fittings) on up & Dn lines in ADEN/Bapatla Sub-division. SW-VI) BZA Division: GDR-BZA sec.KCC: Shifiting of crossover S103A &B towards Gudur duly making TRD and S&T alterations in KCC yard in ADEN/BPP sub-division SW-VII) BZA Division: GDR-BZA sec. KCC- Shifting of layout of crossover S121 in KCC yard in ADEN/BPP sub-division. SW-VIII) BZA Division: GDR-BZA sec. KCC - Replacement of
Non-standard diamond crossing at KCC yard Pt No. 144A,B & 145 A,B in KCC yard in ADEN/BPP sub-division. . . .
ANNEXURE-“A”
PROFORMA
ENGINEERING ORGANISATION
1. ENGINEERING ORGANISATION AVAILABLE ON HAND.
Sl.
No.
Name & Designation
of Employee
Qualification Previous
Experience
Working
From To
01 02 03 04 05
A
B
C
Z
2. ENGINEERING ORGANISATION PROPOSED TO BE ENGAGED FOR THIS
WORK FROM ABOVE.
Sl.
No.
Name & Designation
of Employee
Qualification Previous
Experience
Working
From To
01 02 03 04 05
A
B
C
Z
3. ENGINEERING ORGANISATION PROPOSED TO BE ENGAGED FOR THIS
WORK FROM OUTSIDE. (A SUITABLY WORDED CONSENT LETTER FROM SUCH A PERSON SHOULD BE
OBTAINED AND ENCLOSED).
Sl.
No.
Name & Designation
of Employee
Qualification Previous
Experience
Remarks
01 02 03 04 05
A
B
C
Z
SIGNATURE OF THE TENDERER (S):
NAME OF THE TENDERER(S):
10
Tender No. 03/Central/2016
Sr.DEN/Central/BZA Signature of Tenderer(s)
Page 10 of 91 BZA Divn., SCR, T.No.03/Central/2016 invited vide Open Tender No.DRM/Works/BZA/03/2016 dt. 05.02.2016, date of opening on 08.03.2016 for the work of SW-I) BZA Division: GDR-BZA sec.Proposed safety related track repairs in SSE/P.Way /CLX, BPP and TEL sections of ADEN/BPP Sub- Division. SW-II) BZA Division: BZA-VSKP sec.Proposed safety related track repairs in SSE/P.Way /Eluru & Nuzvid sections of ADEN/Eluru Sub- Division. SW-III) BZA Division: GDR-BZA sec. Transportation of P.Way materials for scattered and casual renewals Departmentally and for collection scrap in yards for the year 2015-16 in ADEN/BPP sub-division. SW-IV) BZA Division: BZA - VSKP Sec. Transportation of P.Way materials for scattered and casual renewals Departmentally and for collection scrap in yards for the year 2015-16 in ADEN/EE sub-division. SW-V) BZA Division: GDR-BZA sec.: TFR - Through fitting renewal for a length of 65.45km (without ERC) and 1.46km (with all fittings) on up & Dn lines in ADEN/Bapatla Sub-division. SW-VI) BZA Division: GDR-BZA sec.KCC: Shifiting of crossover S103A &B towards Gudur duly making TRD and S&T alterations in KCC yard in ADEN/BPP sub-division SW-VII) BZA Division: GDR-BZA sec. KCC- Shifting of layout of crossover S121 in KCC yard in ADEN/BPP sub-division. SW-VIII) BZA Division: GDR-BZA sec. KCC - Replacement of
Non-standard diamond crossing at KCC yard Pt No. 144A,B & 145 A,B in KCC yard in ADEN/BPP sub-division. . . .
ANNEXURE-“B”
PROFORMA
PLANT & MACHINERY
1. PLANT & MACHINERYAVAILABLE ON HAND.
Sl.
No.
Particulars
of
machinery,
Plant &
equipment
No. of
Units
Kind
and
make
Capacity Age and
Condition
Approx.
cost in Rs.
in lakhs
Purchase Bill No. &
Date and Registration
particulars
01 02 03 04 05 06 07 08
A
B
C
Z
2. PLANT & MACHINERY PROPOSED TO BE INDUCTED FROM ABOVE. Sl.
No.
Particulars
of
machinery,
Plant &
equipment
No. of
Units
Kind
and
make
Capacity Age and
Condition
Approx.
cost in
Rs. in lakhs
Purchase Bill No. &
Date and Registration
particulars
01 02 03 04 05 06 07 08
A
B
C
Z
3. PLANT & MACHINERY PROPOSED TO BE INDUCTED FROM OUTSIDE. Sl.
No.
Particulars of
machinery,
Plant &
equipment
No. of
Units
Kind
and
make
Capacity Age and
Condition
Approx.
cost in
Rs. in
lakhs
If to be purchased
give likely date of
receipt and
supplier‟s Name.
01 02 03 04 05 06 07 08
A
B
C
Z
SIGNATURE OF THE TENDERER (S):
NAME OF THE TENDERER(S):
11
Tender No. 03/Central/2016
Sr.DEN/Central/BZA Signature of Tenderer(s)
Page 11 of 91 BZA Divn., SCR, T.No.03/Central/2016 invited vide Open Tender No.DRM/Works/BZA/03/2016 dt. 05.02.2016, date of opening on 08.03.2016 for the work of SW-I) BZA Division: GDR-BZA sec.Proposed safety related track repairs in SSE/P.Way /CLX, BPP and TEL sections of ADEN/BPP Sub- Division. SW-II) BZA Division: BZA-VSKP sec.Proposed safety related track repairs in SSE/P.Way /Eluru & Nuzvid sections of ADEN/Eluru Sub- Division. SW-III) BZA Division: GDR-BZA sec. Transportation of P.Way materials for scattered and casual renewals Departmentally and for collection scrap in yards for the year 2015-16 in ADEN/BPP sub-division. SW-IV) BZA Division: BZA - VSKP Sec. Transportation of P.Way materials for scattered and casual renewals Departmentally and for collection scrap in yards for the year 2015-16 in ADEN/EE sub-division. SW-V) BZA Division: GDR-BZA sec.: TFR - Through fitting renewal for a length of 65.45km (without ERC) and 1.46km (with all fittings) on up & Dn lines in ADEN/Bapatla Sub-division. SW-VI) BZA Division: GDR-BZA sec.KCC: Shifiting of crossover S103A &B towards Gudur duly making TRD and S&T alterations in KCC yard in ADEN/BPP sub-division SW-VII) BZA Division: GDR-BZA sec. KCC- Shifting of layout of crossover S121 in KCC yard in ADEN/BPP sub-division. SW-VIII) BZA Division: GDR-BZA sec. KCC - Replacement of
Non-standard diamond crossing at KCC yard Pt No. 144A,B & 145 A,B in KCC yard in ADEN/BPP sub-division. . . .
ANNEXURE-“C”
LIST OF COMPLETED WORKS BY THE TENDERER
Sl.
No
.
Nam
e of
wo
rk
Ag
reem
ent
No
. an
d d
ate
Des
ignat
ion
and
ad
dre
ss
of
agre
emen
t
sig
nin
g
auth
ori
ty
Ag
reem
ent
val
ue
in l
akh
s
Co
mp
lete
d
val
ue
of
work
(in
lak
hs)
Dat
e of
com
pl-
etio
n
Rem
ark
s
Railway
works
A
B
C
D
E
Z
State Govt.
Works
A
B
C
D
E
Z
Public Sector
Undertaking
Works
A
B
C
D
E
Z
SIGNATURE OF THE TENDERER (S):
NAME OF THE TENDERER(S):
12
Tender No. 03/Central/2016
Sr.DEN/Central/BZA Signature of Tenderer(s)
Page 12 of 91 BZA Divn., SCR, T.No.03/Central/2016 invited vide Open Tender No.DRM/Works/BZA/03/2016 dt. 05.02.2016, date of opening on 08.03.2016 for the work of SW-I) BZA Division: GDR-BZA sec.Proposed safety related track repairs in SSE/P.Way /CLX, BPP and TEL sections of ADEN/BPP Sub- Division. SW-II) BZA Division: BZA-VSKP sec.Proposed safety related track repairs in SSE/P.Way /Eluru & Nuzvid sections of ADEN/Eluru Sub- Division. SW-III) BZA Division: GDR-BZA sec. Transportation of P.Way materials for scattered and casual renewals Departmentally and for collection scrap in yards for the year 2015-16 in ADEN/BPP sub-division. SW-IV) BZA Division: BZA - VSKP Sec. Transportation of P.Way materials for scattered and casual renewals Departmentally and for collection scrap in yards for the year 2015-16 in ADEN/EE sub-division. SW-V) BZA Division: GDR-BZA sec.: TFR - Through fitting renewal for a length of 65.45km (without ERC) and 1.46km (with all fittings) on up & Dn lines in ADEN/Bapatla Sub-division. SW-VI) BZA Division: GDR-BZA sec.KCC: Shifiting of crossover S103A &B towards Gudur duly making TRD and S&T alterations in KCC yard in ADEN/BPP sub-division SW-VII) BZA Division: GDR-BZA sec. KCC- Shifting of layout of crossover S121 in KCC yard in ADEN/BPP sub-division. SW-VIII) BZA Division: GDR-BZA sec. KCC - Replacement of
Non-standard diamond crossing at KCC yard Pt No. 144A,B & 145 A,B in KCC yard in ADEN/BPP sub-division. . . .
ANEXURE-“D”
LIST OF WORKS ON HAND WITH THE TENDERER
Sl.
No.
Name
of work
Agreement
No. and date
Designation
and address of
agreement
signing
authority
Agreement
value in
lakhs
Bill amount
paid so far
in lakhs
Due date of
completion
Number of
extensions
taken
Railway works
A
B
C
D
E
Z
State Govt.
Works
A
B
C
D
E
Z
Public Sector
Undertaking
Works
A
B
C
D
E
Z
SIGNATURE OF THE TENDERER:
NAME OF THE TENDERER:
13
Tender No. 03/Central/2016
Sr.DEN/Central/BZA Signature of Tenderer(s)
Page 13 of 91 BZA Divn., SCR, T.No.03/Central/2016 invited vide Open Tender No.DRM/Works/BZA/03/2016 dt. 05.02.2016, date of opening on 08.03.2016 for the work of SW-I) BZA Division: GDR-BZA sec.Proposed safety related track repairs in SSE/P.Way /CLX, BPP and TEL sections of ADEN/BPP Sub- Division. SW-II) BZA Division: BZA-VSKP sec.Proposed safety related track repairs in SSE/P.Way /Eluru & Nuzvid sections of ADEN/Eluru Sub- Division. SW-III) BZA Division: GDR-BZA sec. Transportation of P.Way materials for scattered and casual renewals Departmentally and for collection scrap in yards for the year 2015-16 in ADEN/BPP sub-division. SW-IV) BZA Division: BZA - VSKP Sec. Transportation of P.Way materials for scattered and casual renewals Departmentally and for collection scrap in yards for the year 2015-16 in ADEN/EE sub-division. SW-V) BZA Division: GDR-BZA sec.: TFR - Through fitting renewal for a length of 65.45km (without ERC) and 1.46km (with all fittings) on up & Dn lines in ADEN/Bapatla Sub-division. SW-VI) BZA Division: GDR-BZA sec.KCC: Shifiting of crossover S103A &B towards Gudur duly making TRD and S&T alterations in KCC yard in ADEN/BPP sub-division SW-VII) BZA Division: GDR-BZA sec. KCC- Shifting of layout of crossover S121 in KCC yard in ADEN/BPP sub-division. SW-VIII) BZA Division: GDR-BZA sec. KCC - Replacement of
Non-standard diamond crossing at KCC yard Pt No. 144A,B & 145 A,B in KCC yard in ADEN/BPP sub-division. . . .
ANNEXURE-“E”
EXPERIENCE CERTIFICATE
Sl.
No. Work Details Details
01 Name of Work
02 Agreement Number, date and name of the Agency.
03 Agreement Value in Rupees ( in words and figures)
04 Due date of completion
05 Number of Extensions granted
06 Actual date of completion of work
07 Value of Final Bill if passed (in words)
08 Work completed but Final measurements not
recorded
a) Amount paid so far as in CC Bill No.
09 Work completed, Final measurements recorded with
negative variation.
a) Amount so far paid as in CC Bill No.
10 Work completed, if Final measurements recorded
with positive variation which is not sanctioned yet
a) Original agreement value or last sanctioned
agreement value whichever is lower
Note: 1) This certificate in this proforma is to be issued only for physically Completed
work.
2) This certificate to be issued by an Officer not below the rank of JA Grade or
Bill Passing Officer in Railways and Bill Passing Officer / Executive In-charge
of work in other Govt. / Govt. bodies / Public Sector Undertaking. The
certificate should bear the signature and seal of the issuing officer, name of the
department etc.
Signature :
Name of Officer :
Designation :
Address :
Office Seal :
Phone / Fax No. :
Date :
14
Tender No. 03/Central/2016
Sr.DEN/Central/BZA Signature of Tenderer(s)
Page 14 of 91 BZA Divn., SCR, T.No.03/Central/2016 invited vide Open Tender No.DRM/Works/BZA/03/2016 dt. 05.02.2016, date of opening on 08.03.2016 for the work of SW-I) BZA Division: GDR-BZA sec.Proposed safety related track repairs in SSE/P.Way /CLX, BPP and TEL sections of ADEN/BPP Sub- Division. SW-II) BZA Division: BZA-VSKP sec.Proposed safety related track repairs in SSE/P.Way /Eluru & Nuzvid sections of ADEN/Eluru Sub- Division. SW-III) BZA Division: GDR-BZA sec. Transportation of P.Way materials for scattered and casual renewals Departmentally and for collection scrap in yards for the year 2015-16 in ADEN/BPP sub-division. SW-IV) BZA Division: BZA - VSKP Sec. Transportation of P.Way materials for scattered and casual renewals Departmentally and for collection scrap in yards for the year 2015-16 in ADEN/EE sub-division. SW-V) BZA Division: GDR-BZA sec.: TFR - Through fitting renewal for a length of 65.45km (without ERC) and 1.46km (with all fittings) on up & Dn lines in ADEN/Bapatla Sub-division. SW-VI) BZA Division: GDR-BZA sec.KCC: Shifiting of crossover S103A &B towards Gudur duly making TRD and S&T alterations in KCC yard in ADEN/BPP sub-division SW-VII) BZA Division: GDR-BZA sec. KCC- Shifting of layout of crossover S121 in KCC yard in ADEN/BPP sub-division. SW-VIII) BZA Division: GDR-BZA sec. KCC - Replacement of
Non-standard diamond crossing at KCC yard Pt No. 144A,B & 145 A,B in KCC yard in ADEN/BPP sub-division. . . .
ANEXURE-“F”
CERTIFICATE FROM CHARTERED ACCOUNTANT IN THEIR LETTER HEAD
TO WHOMSOEVER CONCERNED
We________ are the Auditors for the Firm__________________________________ since last
________(many) years. On the strength of the above association, we are issuing this certificate
Firm on the Annual Contractual Turnover during the last three Audited Financial Years as per
Audited Balance Sheets.
It is further certified that advances or loans taken by the Firm in connection with execution of the
work is not reflected in the contractual receipts from Works Contracts indicated below:
Sl.
No.
Financial
Year
Receipts reflected in
Audited Balance Sheets in
P&L account
(Rs.)
Contractual receipts from
Works Contracts
(Rs.)
Remarks
1 2 3 4 5
Signature :
Name of CA :
Address :
Office Seal :
Phone No. :
e.mail :
Date :
15
Tender No. 03/Central/2016
Sr.DEN/Central/BZA Signature of Tenderer(s)
Page 15 of 91 BZA Divn., SCR, T.No.03/Central/2016 invited vide Open Tender No.DRM/Works/BZA/03/2016 dt. 05.02.2016, date of opening on 08.03.2016 for the work of SW-I) BZA Division: GDR-BZA sec.Proposed safety related track repairs in SSE/P.Way /CLX, BPP and TEL sections of ADEN/BPP Sub- Division. SW-II) BZA Division: BZA-VSKP sec.Proposed safety related track repairs in SSE/P.Way /Eluru & Nuzvid sections of ADEN/Eluru Sub- Division. SW-III) BZA Division: GDR-BZA sec. Transportation of P.Way materials for scattered and casual renewals Departmentally and for collection scrap in yards for the year 2015-16 in ADEN/BPP sub-division. SW-IV) BZA Division: BZA - VSKP Sec. Transportation of P.Way materials for scattered and casual renewals Departmentally and for collection scrap in yards for the year 2015-16 in ADEN/EE sub-division. SW-V) BZA Division: GDR-BZA sec.: TFR - Through fitting renewal for a length of 65.45km (without ERC) and 1.46km (with all fittings) on up & Dn lines in ADEN/Bapatla Sub-division. SW-VI) BZA Division: GDR-BZA sec.KCC: Shifiting of crossover S103A &B towards Gudur duly making TRD and S&T alterations in KCC yard in ADEN/BPP sub-division SW-VII) BZA Division: GDR-BZA sec. KCC- Shifting of layout of crossover S121 in KCC yard in ADEN/BPP sub-division. SW-VIII) BZA Division: GDR-BZA sec. KCC - Replacement of
Non-standard diamond crossing at KCC yard Pt No. 144A,B & 145 A,B in KCC yard in ADEN/BPP sub-division. . . .
Annexure-I(a)
TENDER
To
The President of India
Acting through the Principal Chief Engineer,
Divisional Railway Manager,
Senior Divisional Engineer/Divisional Engineer
South Central Railway
I/We-------------------------------------------------------------------- have read the various conditions to
tender attached hereto and hereby agree to abide by the said conditions. I/We also agree to keep this
tender open for acceptance for a period of 90 days from the date fixed for opening the same and in
default thereof, I/We will be liable for forfeiture of my / our Earnest Money”. I/ We offer to do the
work for South Central Railway, at the rates quoted in the attached schedule and hereby bind myself
/ourselves to complete the work in all respects within the time period stipulated in the enclosed
Schedule from the date of issue of letter of acceptance of the tender.
2. I / We also hereby agree to abide by the General Conditions of Contract corrected with the latest
printed/advance correction slips and to carry out the work according to the special conditions of
contract and specifications of materials and works as laid down by Railway in the annexed Special
Conditions / Specifications and the South Central Railway Works Hand Book Part III corrected with
the latest printed / advance correction slips, sanitary works Hand Book corrected with the latest
printed/advance correction slips, Schedule of Rates corrected with the latest Printed/advance
correction slips for the present contract.
3. A sum of rupees as notified in the Tender Notice and on the cover page of this Tender booklet is
herewith forwarded as earnest money deposit. The full value of earnest money shall stand
forfeited without prejudice to any other rights or remedies in case my/our Tender is accepted and
if :-
a) I/ we do not execute the contract documents within 7 (Seven) days after receipt of notice
issued by the Railway that such documents are ready, and
b) I /We do not commence the work within fifteen days after receipt of orders to that effect.
4 Until a formal agreement is prepared and executed, acceptance of this tender shall constitute a
binding contract between us subject to modifications, as may be mutually agreed to between us and
indicated in the letter of acceptance of my/our offer for this work.
SIGNATURE OF WITNESSES
1.
2.
SIGNATURE OF TENDERER(S)
Date:
Address of the Tenderer (s)
16
Tender No. 03/Central/2016
Sr.DEN/Central/BZA Signature of Tenderer(s)
Page 16 of 91 BZA Divn., SCR, T.No.03/Central/2016 invited vide Open Tender No.DRM/Works/BZA/03/2016 dt. 05.02.2016, date of opening on 08.03.2016 for the work of SW-I) BZA Division: GDR-BZA sec.Proposed safety related track repairs in SSE/P.Way /CLX, BPP and TEL sections of ADEN/BPP Sub- Division. SW-II) BZA Division: BZA-VSKP sec.Proposed safety related track repairs in SSE/P.Way /Eluru & Nuzvid sections of ADEN/Eluru Sub- Division. SW-III) BZA Division: GDR-BZA sec. Transportation of P.Way materials for scattered and casual renewals Departmentally and for collection scrap in yards for the year 2015-16 in ADEN/BPP sub-division. SW-IV) BZA Division: BZA - VSKP Sec. Transportation of P.Way materials for scattered and casual renewals Departmentally and for collection scrap in yards for the year 2015-16 in ADEN/EE sub-division. SW-V) BZA Division: GDR-BZA sec.: TFR - Through fitting renewal for a length of 65.45km (without ERC) and 1.46km (with all fittings) on up & Dn lines in ADEN/Bapatla Sub-division. SW-VI) BZA Division: GDR-BZA sec.KCC: Shifiting of crossover S103A &B towards Gudur duly making TRD and S&T alterations in KCC yard in ADEN/BPP sub-division SW-VII) BZA Division: GDR-BZA sec. KCC- Shifting of layout of crossover S121 in KCC yard in ADEN/BPP sub-division. SW-VIII) BZA Division: GDR-BZA sec. KCC - Replacement of
Non-standard diamond crossing at KCC yard Pt No. 144A,B & 145 A,B in KCC yard in ADEN/BPP sub-division. . . .
ACCEPTANCE OF TENDER
I accept the tender and agree to pay the rates as per Standard Schedule of Rates_____ as
corrected by and up to correction slip No_______ of _ enhanced / diminished by
________ percent / at par in respect of schedule “A” and at the rates as entered in the
schedule__________.
DIVISIONAL RAILWAY MANAGER
DIVISIONAL ENGINEER / SENIOR DIVISIONAL ENGINEER
SOUTH CENTRAL RAILWAY
For and on behalf of the President of India.
Witness:
1.
Division_________________
Date:____________________
2.
FOR RAILWAY USE ONLY & TENDER(S) NOT
REQUIRED TO SIGN
17
Tender No. 03/Central/2016
Sr.DEN/Central/BZA Signature of Tenderer(s)
Page 17 of 91 BZA Divn., SCR, T.No.03/Central/2016 invited vide Open Tender No.DRM/Works/BZA/03/2016 dt. 05.02.2016, date of opening on 08.03.2016 for the work of SW-I) BZA Division: GDR-BZA sec.Proposed safety related track repairs in SSE/P.Way /CLX, BPP and TEL sections of ADEN/BPP Sub- Division. SW-II) BZA Division: BZA-VSKP sec.Proposed safety related track repairs in SSE/P.Way /Eluru & Nuzvid sections of ADEN/Eluru Sub- Division. SW-III) BZA Division: GDR-BZA sec. Transportation of P.Way materials for scattered and casual renewals Departmentally and for collection scrap in yards for the year 2015-16 in ADEN/BPP sub-division. SW-IV) BZA Division: BZA - VSKP Sec. Transportation of P.Way materials for scattered and casual renewals Departmentally and for collection scrap in yards for the year 2015-16 in ADEN/EE sub-division. SW-V) BZA Division: GDR-BZA sec.: TFR - Through fitting renewal for a length of 65.45km (without ERC) and 1.46km (with all fittings) on up & Dn lines in ADEN/Bapatla Sub-division. SW-VI) BZA Division: GDR-BZA sec.KCC: Shifiting of crossover S103A &B towards Gudur duly making TRD and S&T alterations in KCC yard in ADEN/BPP sub-division SW-VII) BZA Division: GDR-BZA sec. KCC- Shifting of layout of crossover S121 in KCC yard in ADEN/BPP sub-division. SW-VIII) BZA Division: GDR-BZA sec. KCC - Replacement of
Non-standard diamond crossing at KCC yard Pt No. 144A,B & 145 A,B in KCC yard in ADEN/BPP sub-division. . . .
Annexure-II SOUTH CENTRAL RAILWAY
AGREEMENT OF WORKS 1. Contract agreement No_____ dt._______ articles of agreement made this ________day of _______
between The President of India acting through the ____________ South Central Railway Administration
[herein after called the Railway which expression shall unless the context does not so admit include his
successors and assignees in office of the one part and ________ [herein after called the contractor which
expression shall unless excluded by the context includes his heirs, executors, administrators, successors
and assignees] of the other part.
2. Where as the contractor has agreed with the Railways for the work ______________ set forth in the
schedule hereto annexed up on the General Conditions of contract and the specifications of the South
Central Railway and the Special Conditions and Special Specifications, if any, and in conformity with the
drawings here to annexed, if any, and whereas the performance of the said work is an act in which the
public are interested.
3. Whereas the balance in the security deposit after adjustment of earnest money of Rs._______ originally
paid by the contractor is at the instance of the contractor recovered at 10 percent of the value of the
running bills till the amount of security deposit of Rs.________ is fully recovered.
4. Whereas the contractor has furnished an irrevocable Bank Guarantee for Rs.____________(5% of
Contract value) towards Performance Guarantee valid upto _____________(valid up to the stipulated date
of completion plus 60 days beyond that).
5. Now this indenture witnesseth that in consideration of the payments to be made by the Railway the
contractor will duly perform the said works in the said schedules set forth and shall execute the same with
great promptness, care and accuracy in a workman like manner to the satisfaction of the Railway and
will complete the same in accordance with the said specifications and said drawings and said conditions
of contract on or before the _____________ date of ________ year and will be maintain the said works
for a period of _________calendar months from the certified date of the completion and will observe,
fulfill and keep all the conditions therein mentioned (which shall be deemed and taken to be part of this
contract as if the same has been fully set forth herein), and the Railway both hereby agree that if the
contractor shall duly perform the said work in the manner aforesaid and observe and keep said terms and
conditions. The Railway will pay or cause to be paid to the contractor for the said works on the final
completion thereof, the amount due in respect thereof, at the rates setforth in the USSR,2010 as corrected
by and up to correction slip No ___ for Vijayawada division, enhanced/diminished / “At par” ________
percent of Schedule ( items covered by SSR) and the rates shown in the schedule _______ for items not
covered by SSR.
6. It is hereby agreed and declared that all the provisions of the said specifications, conditions of contract
which have been carefully read and understood by the contractor and schedule of rates, including the
general instructions contained in page _______ thereof shall be as binding up on the contractor and up on
the Railway Administration as if the same has been repeated herein and shall be read as part of these
presents.
Signature of the contractor
Name of the contractor
Address
Date:
Signature of witness with address to
Signature of contractor
Signature
Designation
For and on behalf of the President of India
South Central Railway
Date :
Witness
TO BE SIGNED AT THE TIME OF AGREEMENT ONLY
18
Tender No. 03/Central/2016
Sr.DEN/Central/BZA Signature of Tenderer(s)
Page 18 of 91 BZA Divn., SCR, T.No.03/Central/2016 invited vide Open Tender No.DRM/Works/BZA/03/2016 dt. 05.02.2016, date of opening on 08.03.2016 for the work of SW-I) BZA Division: GDR-BZA sec.Proposed safety related track repairs in SSE/P.Way /CLX, BPP and TEL sections of ADEN/BPP Sub- Division. SW-II) BZA Division: BZA-VSKP sec.Proposed safety related track repairs in SSE/P.Way /Eluru & Nuzvid sections of ADEN/Eluru Sub- Division. SW-III) BZA Division: GDR-BZA sec. Transportation of P.Way materials for scattered and casual renewals Departmentally and for collection scrap in yards for the year 2015-16 in ADEN/BPP sub-division. SW-IV) BZA Division: BZA - VSKP Sec. Transportation of P.Way materials for scattered and casual renewals Departmentally and for collection scrap in yards for the year 2015-16 in ADEN/EE sub-division. SW-V) BZA Division: GDR-BZA sec.: TFR - Through fitting renewal for a length of 65.45km (without ERC) and 1.46km (with all fittings) on up & Dn lines in ADEN/Bapatla Sub-division. SW-VI) BZA Division: GDR-BZA sec.KCC: Shifiting of crossover S103A &B towards Gudur duly making TRD and S&T alterations in KCC yard in ADEN/BPP sub-division SW-VII) BZA Division: GDR-BZA sec. KCC- Shifting of layout of crossover S121 in KCC yard in ADEN/BPP sub-division. SW-VIII) BZA Division: GDR-BZA sec. KCC - Replacement of
Non-standard diamond crossing at KCC yard Pt No. 144A,B & 145 A,B in KCC yard in ADEN/BPP sub-division. . . .
(REGULATIONS FOR TENDERS AND CONTRACTS FOR GUIDANCE OF
CONTRACTORS FOR CIVIL ENGINEERING WORKS)
MEANING OF TERMS.
Definitions:
1. In these regulations for tenders and contracts the following terms shall have
the meaning assigned hereunder except where the context otherwise
requires.
(a) Railway shall mean the President of the Republic of India or the
Administrative officer of South Central Railway or the successor Railway
authorized to invite tenders and enter into contracts for works on his behalf.
(b) General Manger shall mean the officer in Administrative charge of the
whole of South Central Railway and shall mean and include the General
Manger of the successor Railway.
(c) “Principal Chief Engineer” shall mean the officer in charge of the
Engineering department, South Central Railway.
(d) “Divisional Railway Manager” shall mean the administrative officer in
charge of the division of South Central Railway for the time being.
(e) “Divisional/Sr. Divisional Engineer” shall mean the officer in charge of the
division or district of South Central Railway.
(f) Tenderer shall mean the person/ the firm or the company who tenders for
the works with a view to secure the work on contract with the Railway and
shall include their personal representatives, successors and permitted
assignees.
(g) Limited tenders shall mean tender invited from all or some contractors from
the approved list of contractors with the Railway.
(h) Open tenders shall mean tenders invited in open and public manner and
with adequate notice.
(i) The work shall mean the works contemplated in the drawings and schedules
set forth in the tender forms and description of contract and required to be
executed according to specifications.
(j) Specification shall mean the specifications, materials and works, South
Central Railway issued under the authority of the Principal Chief Engineer
or as amplified, added to or superceded by special specifications, if any,
appended to the tender forms.
(k) Schedule of rates, South Central Railway shall mean the schedule of rates
issued under the authority of the Principal Chief Engineer from time to
time.
(l) Drawings shall mean the drawings, plans and tracing or prints thereof
annexed to the tender forms.
Singular and
plural:
2. Words imparting the singular number shall also include the plural and vice
versa where the context requires.
19
Tender No. 03/Central/2016
Sr.DEN/Central/BZA Signature of Tenderer(s)
Page 19 of 91 BZA Divn., SCR, T.No.03/Central/2016 invited vide Open Tender No.DRM/Works/BZA/03/2016 dt. 05.02.2016, date of opening on 08.03.2016 for the work of SW-I) BZA Division: GDR-BZA sec.Proposed safety related track repairs in SSE/P.Way /CLX, BPP and TEL sections of ADEN/BPP Sub- Division. SW-II) BZA Division: BZA-VSKP sec.Proposed safety related track repairs in SSE/P.Way /Eluru & Nuzvid sections of ADEN/Eluru Sub- Division. SW-III) BZA Division: GDR-BZA sec. Transportation of P.Way materials for scattered and casual renewals Departmentally and for collection scrap in yards for the year 2015-16 in ADEN/BPP sub-division. SW-IV) BZA Division: BZA - VSKP Sec. Transportation of P.Way materials for scattered and casual renewals Departmentally and for collection scrap in yards for the year 2015-16 in ADEN/EE sub-division. SW-V) BZA Division: GDR-BZA sec.: TFR - Through fitting renewal for a length of 65.45km (without ERC) and 1.46km (with all fittings) on up & Dn lines in ADEN/Bapatla Sub-division. SW-VI) BZA Division: GDR-BZA sec.KCC: Shifiting of crossover S103A &B towards Gudur duly making TRD and S&T alterations in KCC yard in ADEN/BPP sub-division SW-VII) BZA Division: GDR-BZA sec. KCC- Shifting of layout of crossover S121 in KCC yard in ADEN/BPP sub-division. SW-VIII) BZA Division: GDR-BZA sec. KCC - Replacement of
Non-standard diamond crossing at KCC yard Pt No. 144A,B & 145 A,B in KCC yard in ADEN/BPP sub-division. . . .
Inter-
pretations:
3. These regulations for tenders and contracts shall be read in conjunction
with the General Conditions of the Contract which are referred to herein
and shall be subject to modifications, additions, super cessions by special
conditions of contract and/ or special specifications, if any, annexed to
the tender forms
Contractors
credentials
4. A contractor who has not carried out any work so far on this Railway should
furnish particulars regarding.
a. his position as an independent contractor.
b. His capacity to undertake and carry out works satisfactorily, as vouched
for by a responsible official or firm.
c. His previous experience on works similar to that to be contracted for, in
proof of which original certificates or testimonials may be called for and
their genuineness verified, if need be, by reference to the signatories
thereof.
d. His knowledge, from, actual personal investigation, of the resources of
the zone or zones in which he offers to work
e. His ability to supervise the work personally or by competent and duly
authorized agents.
f. His financial position.
Omissions Discrepancies
5. Should a tenderer find discrepancies in, or omissions from the drawing or any
of the Discrepancies tender forms or should he be in doubt to their meanings
he should at once notify the authority inviting who may send a written
instruction to all tenderers. It shall be understood that every endeavor has been
made to avoid any error which can materially affect the basis of the tender
and the successful tenderer shall take upon himself and provide for the risk
of any error which may subsequently be discovered and shall make no
subsequent claim on account thereof. Earnest
Money: 6 (a) The tenderer shall be required to deposit a sum of Rs.3,74,690/- as Earnest
money deposit for the due performance of the stipulation to keep the offer
open till such date as might be specified in the tender. It shall be understood
that the tender documents have been sold/issued to the tenderer and the
tenderer is permitted to tender in consideration of the stipulation on his part,
that after submitting his tender he will not resile from his offer or modify the
terms and conditions thereof in a manner not acceptable to the Principal Chief
Engineer, Divisional Railway Manager, Divisional Engineer, Sr. Divisional
Engineer of South Central Railway. Should a tenderer fail to observe or
comply with the said stipulation, the aforesaid amount shall be liable to be
forfeited to the Railway.
6 (b) The sum mentioned in (a) above constitutes the earnest money. If his tender is
accepted this earnest money will be retained as part of security for due and
faithful fulfillment of the contract in terms of clause 16 of the General
Conditions of the Contract. The earnest money deposit of the other tenderers
shall, save as herein before provided, be returned to them, but the Railway
shall not be responsible for any loss or depreciation that may happen thereto
while in their possession nor be liable to pay interest thereon.
20
Tender No. 03/Central/2016
Sr.DEN/Central/BZA Signature of Tenderer(s)
Page 20 of 91 BZA Divn., SCR, T.No.03/Central/2016 invited vide Open Tender No.DRM/Works/BZA/03/2016 dt. 05.02.2016, date of opening on 08.03.2016 for the work of SW-I) BZA Division: GDR-BZA sec.Proposed safety related track repairs in SSE/P.Way /CLX, BPP and TEL sections of ADEN/BPP Sub- Division. SW-II) BZA Division: BZA-VSKP sec.Proposed safety related track repairs in SSE/P.Way /Eluru & Nuzvid sections of ADEN/Eluru Sub- Division. SW-III) BZA Division: GDR-BZA sec. Transportation of P.Way materials for scattered and casual renewals Departmentally and for collection scrap in yards for the year 2015-16 in ADEN/BPP sub-division. SW-IV) BZA Division: BZA - VSKP Sec. Transportation of P.Way materials for scattered and casual renewals Departmentally and for collection scrap in yards for the year 2015-16 in ADEN/EE sub-division. SW-V) BZA Division: GDR-BZA sec.: TFR - Through fitting renewal for a length of 65.45km (without ERC) and 1.46km (with all fittings) on up & Dn lines in ADEN/Bapatla Sub-division. SW-VI) BZA Division: GDR-BZA sec.KCC: Shifiting of crossover S103A &B towards Gudur duly making TRD and S&T alterations in KCC yard in ADEN/BPP sub-division SW-VII) BZA Division: GDR-BZA sec. KCC- Shifting of layout of crossover S121 in KCC yard in ADEN/BPP sub-division. SW-VIII) BZA Division: GDR-BZA sec. KCC - Replacement of
Non-standard diamond crossing at KCC yard Pt No. 144A,B & 145 A,B in KCC yard in ADEN/BPP sub-division. . . .
Care in sub
mission of
Tender
7(a) Before submitting a tender, the tenderer will be deemed to have satisfied
himself by actual inspection of the site and locality of the works, that all
conditions liable to be encountered during the execution of the works, are
taken into account and that the percentage/rates he enters in the tender forms
is/are adequate and all inclusive to accord with the provisions in Clause 37
of the General conditions of Contract for the completion of works to the
entire satisfaction of the Engineer 7(b) When work is tendered for by a firm or company of contractors, the tender
shall be signed by the individual legally authorised to enter into
commitments on their behalf.
The Railways will not be bound by any power of attorney granted by the
tenderer or by changes in the composition of the firm made subsequent to the
execution of the contract. It may, however, recognize such power of attorney
and changes after obtaining proper legal advice, the cost of which will be
chargeable to the contractor Right of
Railway
8 The Railway reserves the right of not to invite tenders for any work
or works, to invite open or limited tenders, and when tenders are
to deal with Tenders called, to accept a tender in whole or in part or reject
any tenders or all tenders without assigning reasons for any such action
Execution of
Contract
9 The tenderer whose tender is accepted shall be required to appear at the
office of the General Manager, Principal Chief Engineer, Documents Senior
Divisional Engineer or Divisional Engineer, as the case may
be in person, or if a firm or corporation or a duly authorised
representative shall so appear and to execute the contract documents within
seven days after notice issued by Railway that such documents are ready.
Failure to do so shall constitute a breach of the agreement affected by the
acceptance of the tender in which case the full value of earnest money
accompanying the tender shall stand forfeited without prejudice to any other
rights or remedies.
In the event of any tenderer whose tender is accepted shall refuse to execute
the contract documents as herein-before provided the Railway may
determine that such tenderer has abandoned the contract and there upon his
tender and the acceptance thereof shall be treated as cancelled and the
Railway shall be entitled to forfeit the full amount of the earnest money
and to recover the performance guarantee as per clause No.9 of Special
Conditions of contract Form of
Contract
Document
10 Every contract shall be completed in respect of the documents it shall so
constitute. Not less than two copies of the contract documents shall be
signed by the competent authority and the contractor and one copy given to
the contractor. The contract documents required to be executed by the
tenderer whose tender is accepted shall be the agreement at
Annexure-II
Form of Quotation
11 The Tender shall be submitted in the prescribed form annexed hereto.
21
Tender No. 03/Central/2016
Sr.DEN/Central/BZA Signature of Tenderer(s)
Page 21 of 91 BZA Divn., SCR, T.No.03/Central/2016 invited vide Open Tender No.DRM/Works/BZA/03/2016 dt. 05.02.2016, date of opening on 08.03.2016 for the work of SW-I) BZA Division: GDR-BZA sec.Proposed safety related track repairs in SSE/P.Way /CLX, BPP and TEL sections of ADEN/BPP Sub- Division. SW-II) BZA Division: BZA-VSKP sec.Proposed safety related track repairs in SSE/P.Way /Eluru & Nuzvid sections of ADEN/Eluru Sub- Division. SW-III) BZA Division: GDR-BZA sec. Transportation of P.Way materials for scattered and casual renewals Departmentally and for collection scrap in yards for the year 2015-16 in ADEN/BPP sub-division. SW-IV) BZA Division: BZA - VSKP Sec. Transportation of P.Way materials for scattered and casual renewals Departmentally and for collection scrap in yards for the year 2015-16 in ADEN/EE sub-division. SW-V) BZA Division: GDR-BZA sec.: TFR - Through fitting renewal for a length of 65.45km (without ERC) and 1.46km (with all fittings) on up & Dn lines in ADEN/Bapatla Sub-division. SW-VI) BZA Division: GDR-BZA sec.KCC: Shifiting of crossover S103A &B towards Gudur duly making TRD and S&T alterations in KCC yard in ADEN/BPP sub-division SW-VII) BZA Division: GDR-BZA sec. KCC- Shifting of layout of crossover S121 in KCC yard in ADEN/BPP sub-division. SW-VIII) BZA Division: GDR-BZA sec. KCC - Replacement of
Non-standard diamond crossing at KCC yard Pt No. 144A,B & 145 A,B in KCC yard in ADEN/BPP sub-division. . . .
CONDITIONS OF TENDER
1. The drawings for the Works can be seen in the office of the Divisional Railway Manager
(Works), South Central Railway, Vijayawada at any time during office Hours.
2. General Conditions of Contract and Specifications for Materials and works of South Central
Railway, can be seen at the Office of Divisional Railway Manager (works), South Central
Railway, Vijayawada or had on payment at the rates fixed for each book from time to time.
3. The Tenderer/Tenderers shall quote percentage rates for items covered by Schedules (items
covered by S.S.R and items not covered by S.S.R). The quantities shown in the attached
Schedules are given as a guide and are approximate only and are subject to variation according
to the needs of the Railway. The Railway accepts no responsibility for their accuracy; the
Railway does not guarantee work under each item of the Schedule.
4. Tenders containing erasures and alterations of the tender documents are liable to be rejected.
Any corrections made by the tenderer/tenderers in his/their entries must be attested by
him/them.
5. The works are required to be completed within a period of Eleven Months from the date of
issue of the acceptance of tender
6. The tender must be accompanied by a sum of Rs. 3,74,690/- as earnest money deposited in
cash or in any of the forms mentioned below failing which the tender will not be considered
and will be summarily rejected.
7. The earnest money shall be as below on the estimated tender value as indicated in the Tender
Notice. The Earnest money shall be rounded to the nearest Rs.10 (Rupees Ten only). This
earnest money shall be applicable for all modes of tendering.
Sl.No. Value of work EMD
a For works with Estimated
Tender Value costing
upto Rs.1 Crore
2 % of the Estimated Tender Value
b For works with estimated
Tender Value to cost
more than Rs.1 Crore
Rs.2 lakhs plus 1/2 % (half percent) of the
excess of estimated cost of work beyond Rs.1
Crore subject to a maximum of Rs.1 Crore
The Earnest Money should be in any of the following forms:-
“The Earnest Money should be in cash or Banker‟s Cheques / Demand Drafts executed by State
Bank of India or any of the Nationalized Banks or by a Scheduled Bank.”
(i) Earnest Money Deposit in the form of cash paid to Divisional Cashier (Pay)
S.C.Railway, Vijayawada and the cash receipt in original should be submitted along
with the offer.Banker‟s Cheque/ Demand Draft drawn in favour of Senior Divisional
Finance Manager/ S.C. Railway, Vijayawada should be submitted along with the offer
(Ref: FA&CAO/SC letter No.AFX/EMD/Policy/Vol.I dt 15-12-2014).
(ii) The Tenderers should furnish the Postal address, E.Mail address, FAX No. and Phone
No. of the Bank issuing the BC/DD towards EMD.
(iii) Any other form of EMD including Guarantee Bonds etc., other than Cash/BC/DD is
not acceptable
22
Tender No. 03/Central/2016
Sr.DEN/Central/BZA Signature of Tenderer(s)
Page 22 of 91 BZA Divn., SCR, T.No.03/Central/2016 invited vide Open Tender No.DRM/Works/BZA/03/2016 dt. 05.02.2016, date of opening on 08.03.2016 for the work of SW-I) BZA Division: GDR-BZA sec.Proposed safety related track repairs in SSE/P.Way /CLX, BPP and TEL sections of ADEN/BPP Sub- Division. SW-II) BZA Division: BZA-VSKP sec.Proposed safety related track repairs in SSE/P.Way /Eluru & Nuzvid sections of ADEN/Eluru Sub- Division. SW-III) BZA Division: GDR-BZA sec. Transportation of P.Way materials for scattered and casual renewals Departmentally and for collection scrap in yards for the year 2015-16 in ADEN/BPP sub-division. SW-IV) BZA Division: BZA - VSKP Sec. Transportation of P.Way materials for scattered and casual renewals Departmentally and for collection scrap in yards for the year 2015-16 in ADEN/EE sub-division. SW-V) BZA Division: GDR-BZA sec.: TFR - Through fitting renewal for a length of 65.45km (without ERC) and 1.46km (with all fittings) on up & Dn lines in ADEN/Bapatla Sub-division. SW-VI) BZA Division: GDR-BZA sec.KCC: Shifiting of crossover S103A &B towards Gudur duly making TRD and S&T alterations in KCC yard in ADEN/BPP sub-division SW-VII) BZA Division: GDR-BZA sec. KCC- Shifting of layout of crossover S121 in KCC yard in ADEN/BPP sub-division. SW-VIII) BZA Division: GDR-BZA sec. KCC - Replacement of
Non-standard diamond crossing at KCC yard Pt No. 144A,B & 145 A,B in KCC yard in ADEN/BPP sub-division. . . .
If the tender is accepted, the amount of earnest deposit will be held as security deposit for the due and
faithful fulfillment of the contract. The earnest money of the unsuccessful tenderer will save as herein
before provided, be returned to the unsuccessful tenderers but the Railway shall not be responsible
for any loss or depreciation that may happen to the security for the due performance of the stipulation
to keep the offer open for the period specified in the tender documents or to the earnest money while
in their possession nor be liable to pay interest thereon.
8. The Standing Earnest Money Deposit, if any with the Railway will not be considered for the
purpose of this Tender.
9. It shall not be obligatory on the said authority to accept the lowest tender and no tenderer/
tenderers shall demand any explanation for the cause of rejection of his / their tender.
10. If the tenderer deliberately gives/tenderers deliberately give wrong information in his/their
tender or creates/ create circumstances for the acceptance of his/their tender, the railway
reserves the right to reject such tender at any stage.
11. If a tenderer expires after the submission or his tender of after the acceptance of his tender, the
railway shall deem such tender as cancelled. If a partner of a firm expires after the submission
of their tender or after the acceptance of their tender,the railway shall deem such tender as
cancelled, unless the firm retains its character
12. The earnest money for the due performance of the stipulation to keep the offer open till the date
specified in the tender will be refunded to the unsuccessful tenderer/ tenderers within a
reasonable time. The earnest money deposited by the successful tenderer/tenderers will be
retained towards the security deposit for the due and faithful fulfillment of the contract but shall
be forfeited if the contractor fails/contractors fail to execute the Agreement Bond or start the
work within a reasonable time (to be determined by the Engineer-in-charge) after notification of
the acceptance of his/their tender.
13. Tenders must be enclosed in sealed covers, super scribed “The Tender for
Tender No.03/Central/2016 and must be sent by Registered Post to the address of
Divisional Railway Manager(Works), South Central Railway, Vijayawada so as to reach his
office not later than 15-45 hours. On the prescribed date of opening or deposited in the Special
Box allotted for the purpose in the office of the Divisional Railway Manager (Works)
Vijayawada. This will be sealed at 15-45 hours on the prescribed date of opening.
14. Non-compliance with any of the conditions set forth herein above is liable to result in the tender
being rejected.
15. The authority for acceptance of the tender does not bind himself to accept the lowest or any
other tender nor does he undertake to assign reasons for declining to consider any particular
tenderer / tenderers.
16. The Successful Tenderer/Tenderers shall be required to execute an agreement with the
President of India acting through the Principal Chief Engineer/Chief Engineer/ Engineer-in-
chief/Deputy Chief Engineer (Constructions), Divisional Railway Manager/ Divisional
Engineer/ Senior Divisional Engineer (Construction)of the Railway for carrying out the work
according to the General Conditions of the Contract and specifications for works and material
of South Central Railway including correction slips issued from time to time.
17. The Tenderer shall keep the offer open for a minimum period of 90 days from the date of opening
of tender, within which period the tenderer cannot withdraw his offer subject to the period being
extended further if required by mutual agreement from time to time. Any contravention of the
above condition will make the tenderer liable for forfeiture of Earnest Money Deposit for due
performance of the foregoing stipulations.
18. The Administration does not agree to pay Sales Tax in addition to the price quoted:
23
Tender No. 03/Central/2016
Sr.DEN/Central/BZA Signature of Tenderer(s)
Page 23 of 91 BZA Divn., SCR, T.No.03/Central/2016 invited vide Open Tender No.DRM/Works/BZA/03/2016 dt. 05.02.2016, date of opening on 08.03.2016 for the work of SW-I) BZA Division: GDR-BZA sec.Proposed safety related track repairs in SSE/P.Way /CLX, BPP and TEL sections of ADEN/BPP Sub- Division. SW-II) BZA Division: BZA-VSKP sec.Proposed safety related track repairs in SSE/P.Way /Eluru & Nuzvid sections of ADEN/Eluru Sub- Division. SW-III) BZA Division: GDR-BZA sec. Transportation of P.Way materials for scattered and casual renewals Departmentally and for collection scrap in yards for the year 2015-16 in ADEN/BPP sub-division. SW-IV) BZA Division: BZA - VSKP Sec. Transportation of P.Way materials for scattered and casual renewals Departmentally and for collection scrap in yards for the year 2015-16 in ADEN/EE sub-division. SW-V) BZA Division: GDR-BZA sec.: TFR - Through fitting renewal for a length of 65.45km (without ERC) and 1.46km (with all fittings) on up & Dn lines in ADEN/Bapatla Sub-division. SW-VI) BZA Division: GDR-BZA sec.KCC: Shifiting of crossover S103A &B towards Gudur duly making TRD and S&T alterations in KCC yard in ADEN/BPP sub-division SW-VII) BZA Division: GDR-BZA sec. KCC- Shifting of layout of crossover S121 in KCC yard in ADEN/BPP sub-division. SW-VIII) BZA Division: GDR-BZA sec. KCC - Replacement of
Non-standard diamond crossing at KCC yard Pt No. 144A,B & 145 A,B in KCC yard in ADEN/BPP sub-division. . . .
19. Should the Railway decide to negotiate with a view to bring down the rates, the tenderer called for
negotiations should furnish the following form of declaration before commencement of
negotiations.
“I/we, ________________do declare that in the event of failure of the contemplated
negotiations relating to Tender No. ______opened on ____________my/our original tender shall
remain open for acceptance on its original terms and conditions.
I/we also declare that I/we am/are aware that during this negotiation, I/we cannot increase
the originally quoted rates against any of the individual items and that in the event of my/our doing
so, the same would not be considered at all i.e., reduction in rates during negotiation alone would be
considered and for some items if I/we increase the rates, the same would not be considered and in
lieu my/our originally quoted rates alone would be considered and my/our offer would be evaluated
accordingly. ”
20. Employment / Partnership etc. of Retired Railway Employees: a) Should a tenderer be a retired
engineer of the Gazetted rank or any other Gazetted officer working before his retirement, whether
in the executive or administrative capacity or whether holding a pensionable post or not, in the
Engineering or any other department of any of the Railways owned and administered by the
President of India for the time being, or should a tenderer being partnership firm have as one of its
partners a retired engineer or a retired Gazetted Officer as aforesaid, or should a tenderer being an
incorporated company have any such retired Engineer or retired officer as one of its directors or
should a tenderer in his employment any retired Engineer or retired Gazetted Officer as aforesaid,
the full information as to the date of retirement of such engineer or gazetted officer from the said
service and in case where such engineer or officer had not retired from Government Service at least
One year prior to the date of the submission of the tender as to whether permission for taking such
contract, or if the contractor be a partnership Firm or an incorporated company, to become a
partner or director as the case may be, or to take employment under the contractor, has been
obtained by the tenderer or the engineer or officer, as the case may be from the President of India or
any Officer, duly authorized by him in this behalf, shall be clearly stated in writing at the time of
submitting the tender. Tenders without the information above referred to or a statement to the effect
that no such retired Engineer or retired Gazetted officer is so associated with the tenderer, as the
case may be, shall be rejected.
b) Restriction on the employment of retired Engineers of Railway services within one year of their
retirement: The contractor shall not, if he is a retired Govt. Engineer of Gazetted rank, himself
engage in or employ or associate a retired Govt. Engineer of Gazetted rank, who has not completed
one year from the date of retirement, in connection with this contract in any manner whatsoever
without obtaining prior permission of the President of India and if the contractor is found to have
contravened this provision it will constitute a breach of contract and administration will be entitled
to terminate the contract and forfeit Earnest Money Deposit (EMD), Performance Guarantee (PG)
and Security Deposit (SD) of that contract.
c) At any time after the tender relating to the contract has been signed and submitted by the
contractor, being a partnership firm admit as one of its partners or employee under it or being an
incorporated company elect or nominate or allow to act as one of its directors or employee under it
in any capacity whatsoever any retire Engineer of the Gazetted rank or any other retired Gazetted
officer working before his retirement, whether in the executive or administrative capacity, or
whether holding any pensionable post or not, in the Railways for the time being owned and
administered by the President of India before the expiry of one year from the date of retirement
from the said service of such Engineer or Officer unless such Engineer or Officer has obtained
permission from the President of India or any Officer duly authorized by him in this behalf to
become a partner or a director or to take employment under the contract as the case may be
(Ref:PCE/SC Lr.No.W.148/P/G.C.C./Vol.II dt.19-02-2015).
24
Tender No. 03/Central/2016
Sr.DEN/Central/BZA Signature of Tenderer(s)
Page 24 of 91 BZA Divn., SCR, T.No.03/Central/2016 invited vide Open Tender No.DRM/Works/BZA/03/2016 dt. 05.02.2016, date of opening on 08.03.2016 for the work of SW-I) BZA Division: GDR-BZA sec.Proposed safety related track repairs in SSE/P.Way /CLX, BPP and TEL sections of ADEN/BPP Sub- Division. SW-II) BZA Division: BZA-VSKP sec.Proposed safety related track repairs in SSE/P.Way /Eluru & Nuzvid sections of ADEN/Eluru Sub- Division. SW-III) BZA Division: GDR-BZA sec. Transportation of P.Way materials for scattered and casual renewals Departmentally and for collection scrap in yards for the year 2015-16 in ADEN/BPP sub-division. SW-IV) BZA Division: BZA - VSKP Sec. Transportation of P.Way materials for scattered and casual renewals Departmentally and for collection scrap in yards for the year 2015-16 in ADEN/EE sub-division. SW-V) BZA Division: GDR-BZA sec.: TFR - Through fitting renewal for a length of 65.45km (without ERC) and 1.46km (with all fittings) on up & Dn lines in ADEN/Bapatla Sub-division. SW-VI) BZA Division: GDR-BZA sec.KCC: Shifiting of crossover S103A &B towards Gudur duly making TRD and S&T alterations in KCC yard in ADEN/BPP sub-division SW-VII) BZA Division: GDR-BZA sec. KCC- Shifting of layout of crossover S121 in KCC yard in ADEN/BPP sub-division. SW-VIII) BZA Division: GDR-BZA sec. KCC - Replacement of
Non-standard diamond crossing at KCC yard Pt No. 144A,B & 145 A,B in KCC yard in ADEN/BPP sub-division. . . .
21. Should a tenderer or contractor being an individual on the list of approved contractors, have a relative
employed in Gazetted capacity in the Engineering department of the South Central Railway or in the case
of a partnership firm or company incorporated under the Indian company law, should a partner or a
relative of the partner or a SHARE HOLDER or a relative of a SHARE HOLDER be employed in
Gazetted capacity in the Engineering Department of the South Central Railway, the authority inviting
tenders shall be informed of the fact at the time of submission of tenders failing which the tender may be
rejected or if such fact subsequently comes to light the contract my be rescinded in accordance with the
provisions in Clause 62 of the General conditions of the contract.
22. CONSORTIUM AGREEMENTS, JOINT VENTURE AND MOUs SHALL NOT BE
CONSIDERED FOR THE TENDER VALUE OF WORKS LESS THAN Rs.10 Crores.
23. Partnership Firm:-
i. Partnership deed is eligible if entered into and registered prior to Tender Notice. Tenderer
should enclose/submit experience certificate in the same name and style as the tenderer and their
credentials shall be considered fully to the extent of work executed by the partnership firm.
(EXPERIENCE OF INDIVIDUAL PARTNERS WILL NOT BE CONSIDERED).
ii. Any change or modification in the constitution of tendering firms for whatever purpose or intimation of
any disputes by any of the partners in the firm making tendering firm ineligible, during consideration of
Tender after opening of the Tender, shall be deemed to be backing out of the offer by the Tenderer.
24. PARTNERSHIP DEEDS, POWER OF ATTORNEY ETC.:-
In the case of Partnership firms, an attested copy (attested either by Notary or by Gazetted officer) of the
partnership deed with latest modification of the deed should be submitted along with the Tender
documents without fail.
The Tenderer shall clearly specify whether the Tender is submitted on his own or on behalf of Partnership
concern. If the tender is submitted on behalf of a Partnership concern, he should submit the certified copy
of Partnership deed along with the Tender and authorization to sign the Tender documents on behalf of the
Partnership firm. If these documents are not enclosed along with the Tender documents, the Tender
will be treated as having been submitted by individual signing the Tender document. The Railway
will not be bound by any Power of Attorney granted by the Tenderer or by changes in the composition of
firm subsequent to the execution of the contract. It may, however, recognize such power of attorney and
the changes after obtaining proper legal advice, the cost of which will be chargeable to the contractor.
25. The Tenderer shall quote rates as percentage “Above/Below/At par” for each schedule in the
respective Tender Schedule(s) only. Tenderer should sign below the rate quoted by him for each
schedule of Tender document.
26. The rate quoted anywhere, other than the respective Tender schedule shall not be considered. Any
corrections to the rate once quoted by the tenderer should be in INK and must be attested by tenderer.
However, if any tenderer wants to give discount offer prior to closing of tender box and after submission
of his tender offer, then the same is to be given in a separate sealed envelope duly signed and stamped on
letter head, prior to closing of tender i.e. sealing of the tender box. Tender number, description of work
etc., should be written on the sealed cover.
27. Where there is a discrepancy, between the rates quoted in figures and in words, the rate quoted in
words will be considered for evaluation of the tenderer offer.
28. Rates quoted without signature of tenderer will be considered as “Not Quoted” and/or if no rate is
quoted for any schedule, then the offer will be treated as incomplete offer and will not be considered
for award of work.
29. Rates quoted without prefix “Above/Below/At par” will be considered to be quoted as “Above” the
tender schedule rates.
30. No correspondence/representation from tenderer will b e considered for their failure to quote the
rates as above.
31. Tenderers shall note that conditional/alternate offer will not be considered and will summarily be
rejected, even though such condition makes them as the lowest tenderer.
25
Tender No. 03/Central/2016
Sr.DEN/Central/BZA Signature of Tenderer(s)
Page 25 of 91 BZA Divn., SCR, T.No.03/Central/2016 invited vide Open Tender No.DRM/Works/BZA/03/2016 dt. 05.02.2016, date of opening on 08.03.2016 for the work of SW-I) BZA Division: GDR-BZA sec.Proposed safety related track repairs in SSE/P.Way /CLX, BPP and TEL sections of ADEN/BPP Sub- Division. SW-II) BZA Division: BZA-VSKP sec.Proposed safety related track repairs in SSE/P.Way /Eluru & Nuzvid sections of ADEN/Eluru Sub- Division. SW-III) BZA Division: GDR-BZA sec. Transportation of P.Way materials for scattered and casual renewals Departmentally and for collection scrap in yards for the year 2015-16 in ADEN/BPP sub-division. SW-IV) BZA Division: BZA - VSKP Sec. Transportation of P.Way materials for scattered and casual renewals Departmentally and for collection scrap in yards for the year 2015-16 in ADEN/EE sub-division. SW-V) BZA Division: GDR-BZA sec.: TFR - Through fitting renewal for a length of 65.45km (without ERC) and 1.46km (with all fittings) on up & Dn lines in ADEN/Bapatla Sub-division. SW-VI) BZA Division: GDR-BZA sec.KCC: Shifiting of crossover S103A &B towards Gudur duly making TRD and S&T alterations in KCC yard in ADEN/BPP sub-division SW-VII) BZA Division: GDR-BZA sec. KCC- Shifting of layout of crossover S121 in KCC yard in ADEN/BPP sub-division. SW-VIII) BZA Division: GDR-BZA sec. KCC - Replacement of
Non-standard diamond crossing at KCC yard Pt No. 144A,B & 145 A,B in KCC yard in ADEN/BPP sub-division. . . .
SPECIAL CONDITIONS OF CONTRACT
1. The rates include all lead and if the materials obtained by rail all freight charges including
loading charges. 2. Sales tax, Royalties and Octroi duties, if any, that may be payable under Provincial
Government Sales Tax Act or Local Bodies Act or rules on any of the material that may be
used or supplied by the contractor will be payable by the contractor. The Railway will neither
pay the taxes or duties nor be bound to compensate the contractor for any amounts paid by him
by way of these taxes or duties.
Sales Tax at 4% on the materials portion of the contract will be deducted from each on account
bill where identifiable. Where the labour and material portion is not clearly identifiable, the
labour element shall be taken as 30%. On the balance 70% of the value of the work, 4% shall
be deducted pro-rata from each “on account bill” towards Sales tax.
Seigniorage charges recoverable from bills:-
Seigniorage charges for supply of earth, mooram, sand and other minerals as fixed by the State
Government and payable to them as revised from time to time during the currency of contract
will be recovered by Railway from the contractors “on account” and “final bills” and remitted
to the state government. The rates quoted by the Tenderer shall be inclusive of these charges.
Claims regarding revision of seigniorage charges and consequent enhancement of the accepted
rate will not be entertained. However, no seigniorage charges / fee shall be recovered from the
bills of the contractor, if the contractor produces documentary evidence e.g. “Transit Passes”
issued by State Govt. Officials in token of having paid seigniorage fee. In such cases, the
genuineness of such documentary evidence produced along with proof of payment of
seigniorage charges, shall be got verified by the Railway from the concerned Mining and
Geology Dept 3. WATER:- A charge of One percent will be made by the Railway for the supply by the
Railway of piped water from existing pipe lines and calculated on the amount of all items of
work (USSR/NS items) appearing in the bills payable to the contractor in respect of which
work such water has been issued to the Contractor and such charges should be deducted from
sums due or payable by the Railway to the Contractor from time to time.
4. In the event of water having to be brought by the Railway to the site of the work in traveling
tanks, the actual freight at Public Tariff rate and all other charges incurred therein including any
demurrage that may be levied shall be payable by the Contractor and deducted from sums due
or payable by the Railways to the Contractor from time to time.
In addition to the charges of one percent referred to above, if additional pipe lines to
those already existing are called for by the contractor, the cost of the same and all charges
incurred by the Railway in their laying including supervision charges will be paid by the
contractor or the contractor provides and lay his own piping at the discretion of Divisional
Engineer.
5. The Railway does not guarantee work under each items of the Master Schedule. For example if
a gate-lodge or gang huts are to be built between stations and the work order issued to the
sectional contractors additional payment on account of lead or freight charges for the materials
that may have to be brought by rail or by road, will not be admissible.
6. If there arises any discrepancy between the printed Unified Standard Schedule of Rates 2010 as
amended by addendum and corrigendum slips issued from time to time upto date and the
schedule attached to the Tender pertaining to this work, the former shall be treated as
authentative and binding in all purposes.
26
Tender No. 03/Central/2016
Sr.DEN/Central/BZA Signature of Tenderer(s)
Page 26 of 91 BZA Divn., SCR, T.No.03/Central/2016 invited vide Open Tender No.DRM/Works/BZA/03/2016 dt. 05.02.2016, date of opening on 08.03.2016 for the work of SW-I) BZA Division: GDR-BZA sec.Proposed safety related track repairs in SSE/P.Way /CLX, BPP and TEL sections of ADEN/BPP Sub- Division. SW-II) BZA Division: BZA-VSKP sec.Proposed safety related track repairs in SSE/P.Way /Eluru & Nuzvid sections of ADEN/Eluru Sub- Division. SW-III) BZA Division: GDR-BZA sec. Transportation of P.Way materials for scattered and casual renewals Departmentally and for collection scrap in yards for the year 2015-16 in ADEN/BPP sub-division. SW-IV) BZA Division: BZA - VSKP Sec. Transportation of P.Way materials for scattered and casual renewals Departmentally and for collection scrap in yards for the year 2015-16 in ADEN/EE sub-division. SW-V) BZA Division: GDR-BZA sec.: TFR - Through fitting renewal for a length of 65.45km (without ERC) and 1.46km (with all fittings) on up & Dn lines in ADEN/Bapatla Sub-division. SW-VI) BZA Division: GDR-BZA sec.KCC: Shifiting of crossover S103A &B towards Gudur duly making TRD and S&T alterations in KCC yard in ADEN/BPP sub-division SW-VII) BZA Division: GDR-BZA sec. KCC- Shifting of layout of crossover S121 in KCC yard in ADEN/BPP sub-division. SW-VIII) BZA Division: GDR-BZA sec. KCC - Replacement of
Non-standard diamond crossing at KCC yard Pt No. 144A,B & 145 A,B in KCC yard in ADEN/BPP sub-division. . . .
7. Rubble masonry shall be first sum of Railways Specification No 503 according to South
Central Railway Specification for materials and works. Contractors attention is particularly
invited to dressing of stone as laid down in the Railway‟s specification.
8. The Special conditions supplemented to the conditions of Tender and contracts the General
conditions of contract and the notes appearing under the relevant chapter and sub chapters of
the Unified Standard Schedule of Rates 2010 should be considered as part of the contract
papers where the provisions of these conditions are at variance with General Conditions of
Contract these special conditions.
9. Performance Guarantee (P.G.):-
a. The successful bidder shall have to submit a Performance Guarantee (PG) within 30
(thirty) days from the date of issue of Letter of Acceptance (excluding the date of LOA
(Ref: CE/Works/SC Lr.W.148/P/GCC/Vil.II, dt.30.05.2014). Extension of time for
submission of PG beyond 30 (thirty) days and upto 60 days from the date of issue of
LOA may be given by the Authority who is competent to sign the contract agreement.
However, a penal interest of 15% per annum shall be charged for the delay beyond 30
(thirty) days, i.e., from 31st day after the date of issue of LOA (excluding the date of
LOA). In case the contractor fails to submit the requisite PG even after 60 days from
the date of issue of LOA, the contract shall be terminated duly forfeiting EMD and
other dues, if any payable against that contract. The failed contractor shall be debarred
from participating in re-tender for that work.
b. The successful bidder shall submit a Performance Guarantee (PG) in any of the
following forms, amounting to 5% of the contract value:-
(i) A deposit of Cash,
(ii) Irrevocable Bank Guarantee,
(iii) Government Securities including State Loan Bonds at 5 percent below the
market value
(iv) Deposit receipts, Pay orders, Demand Drafts and Guarantee Bonds. These
forms of Performance Guarantee could be either of the State Bank of India or
of any of the Nationalized Banks;
(v) Guarantee Bonds executed or Deposits Receipts tendered by all Scheduled
Banks;
(vi) A Deposit in the Post Office Saving Bank;
(vii) A Deposit in the National Savings Certificates;
(viii) Twelve years National Defence Certificates;
(ix) Ten years Defence Deposits;
(x) National Defence Bonds; and
(xi) Unit Trust Certificates at 5 percent below market value or at the face value
whichever is less.
27
Tender No. 03/Central/2016
Sr.DEN/Central/BZA Signature of Tenderer(s)
Page 27 of 91 BZA Divn., SCR, T.No.03/Central/2016 invited vide Open Tender No.DRM/Works/BZA/03/2016 dt. 05.02.2016, date of opening on 08.03.2016 for the work of SW-I) BZA Division: GDR-BZA sec.Proposed safety related track repairs in SSE/P.Way /CLX, BPP and TEL sections of ADEN/BPP Sub- Division. SW-II) BZA Division: BZA-VSKP sec.Proposed safety related track repairs in SSE/P.Way /Eluru & Nuzvid sections of ADEN/Eluru Sub- Division. SW-III) BZA Division: GDR-BZA sec. Transportation of P.Way materials for scattered and casual renewals Departmentally and for collection scrap in yards for the year 2015-16 in ADEN/BPP sub-division. SW-IV) BZA Division: BZA - VSKP Sec. Transportation of P.Way materials for scattered and casual renewals Departmentally and for collection scrap in yards for the year 2015-16 in ADEN/EE sub-division. SW-V) BZA Division: GDR-BZA sec.: TFR - Through fitting renewal for a length of 65.45km (without ERC) and 1.46km (with all fittings) on up & Dn lines in ADEN/Bapatla Sub-division. SW-VI) BZA Division: GDR-BZA sec.KCC: Shifiting of crossover S103A &B towards Gudur duly making TRD and S&T alterations in KCC yard in ADEN/BPP sub-division SW-VII) BZA Division: GDR-BZA sec. KCC- Shifting of layout of crossover S121 in KCC yard in ADEN/BPP sub-division. SW-VIII) BZA Division: GDR-BZA sec. KCC - Replacement of
Non-standard diamond crossing at KCC yard Pt No. 144A,B & 145 A,B in KCC yard in ADEN/BPP sub-division. . . .
Also FDR in favour of Senior Divisional Finance Manager, S. C. Railway, Vijayawada
(free from any encumbrance) may be accepted.
1. The Performance Guarantee shall be submitted by the successful bidder after the Letter
Of Acceptance (LOA) has been issued, but before signing of the contract agreement.
This P.G. shall be initially valid up to the stipulated date of completion plus 60 days
beyond that. In case, the time for completion of work gets extended, the contractor
shall get the validity of P.G. extended to cover such extended time for completion of
work plus 60 days.
1.0 The value of PG to be submitted by the contractor will not change for variation upto
25% (either increase or decrease). In case during the course of execution, value of the
contract increases by more than 25% of the original contract value, an additional
Performance Guarantee amounting to 5%(five percent) for the excess value over the
original contract value should be deposited by the Contractor.
1.1 The Performance Guarantee (PG) shall be released after physical completion of the
work based on the „Completion Certificate‟ issued by the competent authority stating
that the contractor has completed the work in all respects satisfactorily. The security
deposit, however, shall be released only after the expiry of the maintenance period
and after passing the final bill based on „No Claim Certificate‟ from the contractor.
1.2 Whenever the contract is rescinded, the security deposit shall be forfeited and the
Performance Guarantee shall be encashed. The balance work shall be got done
independently without risk and cost of the failed contractor. The failed contractor
shall be debarred from participating in the tender for executing the balance work. If
the failed contractor is a JV or a partnership firm, then every member/ partner of such
a firm shall be debarred from participating in the tender for the balance work either in
his / her individual capacity or as a partner of any other JV / partnership firm.
1.3 The Engineer shall not make a claim under the Performance Guarantee except for
amounts to which the President of India is entitled under the contract (not
withstanding and / or without prejudice to any other provisions in the contract
agreement) and this shall be in the event of:
i) Failure of the contractor to extend the validity of the Performance Guarantee as
described herein above, in which event the Engineer may claim the full amount
of the Performance Guarantee.
ii) Failure of the contractor to pay President of India any amount due, either as
agreed by the contractor or determined under any of the Clauses / Conditions of
the agreement, within 30 days of the service of notice to this effect by Engineer.
iii) The contract being determined or rescinded under provision of the GCC the
Performance Guarantee shall be forfeited in full and shall be absolutely at the
disposal of the President of India
28
Tender No. 03/Central/2016
Sr.DEN/Central/BZA Signature of Tenderer(s)
Page 28 of 91 BZA Divn., SCR, T.No.03/Central/2016 invited vide Open Tender No.DRM/Works/BZA/03/2016 dt. 05.02.2016, date of opening on 08.03.2016 for the work of SW-I) BZA Division: GDR-BZA sec.Proposed safety related track repairs in SSE/P.Way /CLX, BPP and TEL sections of ADEN/BPP Sub- Division. SW-II) BZA Division: BZA-VSKP sec.Proposed safety related track repairs in SSE/P.Way /Eluru & Nuzvid sections of ADEN/Eluru Sub- Division. SW-III) BZA Division: GDR-BZA sec. Transportation of P.Way materials for scattered and casual renewals Departmentally and for collection scrap in yards for the year 2015-16 in ADEN/BPP sub-division. SW-IV) BZA Division: BZA - VSKP Sec. Transportation of P.Way materials for scattered and casual renewals Departmentally and for collection scrap in yards for the year 2015-16 in ADEN/EE sub-division. SW-V) BZA Division: GDR-BZA sec.: TFR - Through fitting renewal for a length of 65.45km (without ERC) and 1.46km (with all fittings) on up & Dn lines in ADEN/Bapatla Sub-division. SW-VI) BZA Division: GDR-BZA sec.KCC: Shifiting of crossover S103A &B towards Gudur duly making TRD and S&T alterations in KCC yard in ADEN/BPP sub-division SW-VII) BZA Division: GDR-BZA sec. KCC- Shifting of layout of crossover S121 in KCC yard in ADEN/BPP sub-division. SW-VIII) BZA Division: GDR-BZA sec. KCC - Replacement of
Non-standard diamond crossing at KCC yard Pt No. 144A,B & 145 A,B in KCC yard in ADEN/BPP sub-division. . . .
10. Security Deposit:-
The scale of Security Deposit that is to be recovered from the contractor shall be as follows.
i) Security Deposit should be 5% of the contract value.
ii) The rate of recovery will be at the rate of 10% of the bill amount till the
full Security Deposit is recovered.
iii) Security Deposit will be recovered only from the running bills of the contract and no
other mode of collecting SD such as SD in the form of instruments like Bank
Guarantee, Fixed Deposit Receipt etc., shall be accepted towards Security deposit.
iv) Conversion of Security Deposit into FDR after recovery of full stipulated SD (FA& CAO/SC letter No.AFX/EMD/Policy/ Vol.I dt.26.8.2010 circulated vide
PCE/SC lr. No.W.148/ SCRCA dt.30.9..2010):- If the contractor so desires, the cash
deposits in the form of security deposit may be allowed to be converted into FDRs
(in favour of respective Accounts Officers and on account of contractor), after full
recovery, at the discretion of the Railway, duly collecting necessary charges of
conversion by the Railway Administration.
The security deposit shall be released only after the expiry of the maintenance period and
after passing the final bill based on „No Claim Certificate‟.
After the work is physically completed, security deposit recovered from the running bills of a
contractor can be returned to him if he so desires, in lieu of FDR/irrevocable bank guarantee
for equivalent amount to be submitted by him.
In case of contracts of value Rs.50 crores and above, irrevocable bank guarantee can also be
accepted as a mode of obtaining security deposit.
11. REVISED COMPREHENSIVE CLAUSE 46A OF GCC– PRICE VARIATION
CLAUSE: As per Railway Board Letter No.2007/CE-CT/18/Pt.19 dt.14.12.2012-Price
Variation Clause shall be applicable only for contracts of value (contract agreement
value) Rs.50 lakh and more, irrespective of the contract completion period and
Addendum & Corrigendum Slip (ACS) No.6 to GCC, July 2013; Amendment to Clause
46A.7 (a sub-clause of PVC) to GCC, communicated vide PCE/SC Lr.No.W.148/P/
G.C.C./Vol.II dt.05.06.2014. Amendment to Clause 46A1 (ACS No.2 to GCC, July-2014),
communicated vide PCE/SC Lr.No.W.148/P/G.C.C./Vol.II dt.12.12.2014. Clause 46A-Price Variation clause:
46A.1. Price Variation clause shall be applicable only for contracts of value as prescribed
by the Ministry of Railways through instructions/circulars issued from time to time
and irrespective of the contract completion period. Variation in quantities shall not
be taken into account for applicability of PVC in the contract. Materials supplied
free of cost by Railway to the contractors shall fall outside the purview of Price
Variation clause. If, in any case, accepted offer includes some specific payment to
be made to consultants or some materials supplied by Railway free or at fixed rate,
such payments shall be excluded from the gross value of the work for the purpose
of payment/recovery of price variation.
Applicability of PVC based on original contract value is illustrated as under:
“If estimated value of tender (NIT value) is Rs.55 lakhs; but value of the contract
as per contract agreement is Rs.45 laksh, then PVC shall not apply, even if the
actual final value is Rs.50 laksh or more due to variation in quantities during
execution of the contract. Thus, variation in quantities after signing of contract
agreement is not relevant for deciding whether PVC is applicable to a contract or
not”.
29
Tender No. 03/Central/2016
Sr.DEN/Central/BZA Signature of Tenderer(s)
Page 29 of 91 BZA Divn., SCR, T.No.03/Central/2016 invited vide Open Tender No.DRM/Works/BZA/03/2016 dt. 05.02.2016, date of opening on 08.03.2016 for the work of SW-I) BZA Division: GDR-BZA sec.Proposed safety related track repairs in SSE/P.Way /CLX, BPP and TEL sections of ADEN/BPP Sub- Division. SW-II) BZA Division: BZA-VSKP sec.Proposed safety related track repairs in SSE/P.Way /Eluru & Nuzvid sections of ADEN/Eluru Sub- Division. SW-III) BZA Division: GDR-BZA sec. Transportation of P.Way materials for scattered and casual renewals Departmentally and for collection scrap in yards for the year 2015-16 in ADEN/BPP sub-division. SW-IV) BZA Division: BZA - VSKP Sec. Transportation of P.Way materials for scattered and casual renewals Departmentally and for collection scrap in yards for the year 2015-16 in ADEN/EE sub-division. SW-V) BZA Division: GDR-BZA sec.: TFR - Through fitting renewal for a length of 65.45km (without ERC) and 1.46km (with all fittings) on up & Dn lines in ADEN/Bapatla Sub-division. SW-VI) BZA Division: GDR-BZA sec.KCC: Shifiting of crossover S103A &B towards Gudur duly making TRD and S&T alterations in KCC yard in ADEN/BPP sub-division SW-VII) BZA Division: GDR-BZA sec. KCC- Shifting of layout of crossover S121 in KCC yard in ADEN/BPP sub-division. SW-VIII) BZA Division: GDR-BZA sec. KCC - Replacement of
Non-standard diamond crossing at KCC yard Pt No. 144A,B & 145 A,B in KCC yard in ADEN/BPP sub-division. . . .
46A.2. The Base Month for „Price Variation clause‟ shall be taken as month of opening of
tender including extensions. If any, unless otherwise stated elsewhere. The quarter for
applicability of PVC shall commence from the month following the month of opening
of tender. The Price Variation shall be based on the average Price Index of the quarter
under consideration.
46A.3. Rates accepted by Railway Administration shall hold good till completion of work
and no additional individual claim shall be admissible on account of fluctuations in
market rates, increase in taxes/any other levies/tolls etc., except that
payment/recovery for overall market situation shall be made as per Price Variation
Clause given hereunder.
46A.4. Adjustment for variation in prices of material, labour, fuel, explosives detonators,
steel, concreting, ferrous, non-ferrous, insulators, zinc and cement shall be
determined in the manner prescribed.
46A.5. Components of various items in a contract on which variation in prices be admissible
, shall be Material, Labour, Fuel, Explosives, Detonators, Steel, Cement, concreting,
Ferrous, Non-ferrous, Insulator, Zinc, erection etc., However, for fixed components,
no price variation shall be admissible.
46A.6. The percentages of labour component, material component, fuel component etc., in
various types of Engineering Works shall be as under:
Component Percentage Component Percentage
A) Earthwork contracts:
Labour
component
50% Other material
components
15%
Fuel
component
20% Fixed
component*
15%
B) Ballast and Quarry Products contracts
Labour
component
55% Other material
components
15%
Fuel
component
15% Fixed
component*
15%
C) Tunnelling Contracts
Labour
component
45% Detonators
component
5%
Fuel
component
15% Other material
components
5%
Explosive
component
15% Fixed
component*
15%
D) Other Works Contracts
Labour
component
30% Fuel component 15%
Material
component
40% Fixed
component*
15%
*it shall not be considered for any price variation.
46A.7. The Amount of variation in prices in several components (labour material etc., ) shall
be worked out by the following formulae:
30
Tender No. 03/Central/2016
Sr.DEN/Central/BZA Signature of Tenderer(s)
Page 30 of 91 BZA Divn., SCR, T.No.03/Central/2016 invited vide Open Tender No.DRM/Works/BZA/03/2016 dt. 05.02.2016, date of opening on 08.03.2016 for the work of SW-I) BZA Division: GDR-BZA sec.Proposed safety related track repairs in SSE/P.Way /CLX, BPP and TEL sections of ADEN/BPP Sub- Division. SW-II) BZA Division: BZA-VSKP sec.Proposed safety related track repairs in SSE/P.Way /Eluru & Nuzvid sections of ADEN/Eluru Sub- Division. SW-III) BZA Division: GDR-BZA sec. Transportation of P.Way materials for scattered and casual renewals Departmentally and for collection scrap in yards for the year 2015-16 in ADEN/BPP sub-division. SW-IV) BZA Division: BZA - VSKP Sec. Transportation of P.Way materials for scattered and casual renewals Departmentally and for collection scrap in yards for the year 2015-16 in ADEN/EE sub-division. SW-V) BZA Division: GDR-BZA sec.: TFR - Through fitting renewal for a length of 65.45km (without ERC) and 1.46km (with all fittings) on up & Dn lines in ADEN/Bapatla Sub-division. SW-VI) BZA Division: GDR-BZA sec.KCC: Shifiting of crossover S103A &B towards Gudur duly making TRD and S&T alterations in KCC yard in ADEN/BPP sub-division SW-VII) BZA Division: GDR-BZA sec. KCC- Shifting of layout of crossover S121 in KCC yard in ADEN/BPP sub-division. SW-VIII) BZA Division: GDR-BZA sec. KCC - Replacement of
Non-standard diamond crossing at KCC yard Pt No. 144A,B & 145 A,B in KCC yard in ADEN/BPP sub-division. . . .
i) L= W x (LQ-LB) x LC
LB 100
ii) M = W x (MQ-MB) x MC
MB 100
iii) F = W x (FQ-FB) x FC
FB 100
iv) E = W x (EQ-EB) x EC
EB 100
v) D = W x (DQ-DB) x DC
DB 100
vi) S = SW x (SQ-SB)
vii) C = CV x (CQ-CB)/CB
For Railway Electrification works:
viii) T = {(CS – CO) /CO X 0.4136} X Tc
ix) R = { (RT – RO) / RO + ( ZT - ZO ) / ZO x 0.06 } x Rc
x) N = { (PT – PO ) / PO } x Nc
xi) Z = { ( ZT – ZO ) / ZO } x Zc
xii) I = { ( IT – IO ) / IT } x 85
Where
L Amount of price variation in labour
M Amount of price variation in Materials
F Amount of price variation in fuel
E Amount of price variation in Explosives
D Amount of price variation in Detonators
S Amount of price variation in Steel
C Amount of price variation in Cement
T Amount of price variation in Concreting
R Amount of price variation in Ferrous Items
N Amount of price variation in Non-Ferrous Items
Z Amount of price variation in Zinc
I Amount of price variation in Insulator
LC % of Labour component
MC % of Material component
FC % of Fuel component
EC % of Explosive component
DC % of Detonators component
31
Tender No. 03/Central/2016
Sr.DEN/Central/BZA Signature of Tenderer(s)
Page 31 of 91 BZA Divn., SCR, T.No.03/Central/2016 invited vide Open Tender No.DRM/Works/BZA/03/2016 dt. 05.02.2016, date of opening on 08.03.2016 for the work of SW-I) BZA Division: GDR-BZA sec.Proposed safety related track repairs in SSE/P.Way /CLX, BPP and TEL sections of ADEN/BPP Sub- Division. SW-II) BZA Division: BZA-VSKP sec.Proposed safety related track repairs in SSE/P.Way /Eluru & Nuzvid sections of ADEN/Eluru Sub- Division. SW-III) BZA Division: GDR-BZA sec. Transportation of P.Way materials for scattered and casual renewals Departmentally and for collection scrap in yards for the year 2015-16 in ADEN/BPP sub-division. SW-IV) BZA Division: BZA - VSKP Sec. Transportation of P.Way materials for scattered and casual renewals Departmentally and for collection scrap in yards for the year 2015-16 in ADEN/EE sub-division. SW-V) BZA Division: GDR-BZA sec.: TFR - Through fitting renewal for a length of 65.45km (without ERC) and 1.46km (with all fittings) on up & Dn lines in ADEN/Bapatla Sub-division. SW-VI) BZA Division: GDR-BZA sec.KCC: Shifiting of crossover S103A &B towards Gudur duly making TRD and S&T alterations in KCC yard in ADEN/BPP sub-division SW-VII) BZA Division: GDR-BZA sec. KCC- Shifting of layout of crossover S121 in KCC yard in ADEN/BPP sub-division. SW-VIII) BZA Division: GDR-BZA sec. KCC - Replacement of
Non-standard diamond crossing at KCC yard Pt No. 144A,B & 145 A,B in KCC yard in ADEN/BPP sub-division. . . .
Tc % of Concreting Component
Rc % of Ferrous Component
Nc % of Non-Ferrous Component
Zc % of Zinc Component
W Gross value of work done by contractor as per on-account bill(s), excluding cost of materials
supplied by Railway at fixed price, minus the price values of cement and steel. This will also
exclude specific payment, if any, to be made to the consultants engaged by contractors (such
payment shall be indicated in the contractor‟s offer)
LB
Consumer Price Index Number for Industrial Workers- All India- Published in RBI Bulletin
for the base period.
LQ Consumer Price Index Number for Industrial Workers- All India-Published in RBI Bulletin
for the average price index of the 3 months of the quarter under consideration.
MB Index Number of Wholesale Prices- By Groups and sub-Groups-All commodities- as
published in the RBI Bulletin for the base period.
MQ Index Number of Wholesale Prices- By Groups and Sub-groups-All commodities- as
published in the RBI Bulletin for the average Price index of the 3 months of the quarter under
consideration.
FB Index Number of Wholesale Prices- By Groups and sub-Groups for Fuel and Power as
published in the RBI Bulletin for the base period.
FQ Index Number of Wholesale Prices- By groups and sub-groups for Fuel and Power as
published in the RBI Bulletin for the average price index of the 3 months of the quarter under
consideration.
EB Cost of explosives as fixed by DGS&D in the relevant rate contract of the firm from whom
purchases of explosives are made by the contractor for the base period.
EQ Cost of explosives as fixed by DGS&D in the relevant rate contract of the firm from whom
purchases of explosives are made by the contractor for the average price index of the 3
months of the quarter under consideration
DB Cost of detonators as fixed by DGS&D in the relevant rate contract of the firm from whom
purchases of detonators are made by the contractor for the base period.
DQ Cost of detonators as fixed by DGS&D in the relevant rate contract of the firm from whom
purchases of detonators are made by the contractor for the average price index of the 3
months of the quarter under consideration. SW Weight of steel in tonne supplied by the contractor as per the „on-account‟ bill for the month
under consideration
SQ SAILs (Steel Authority of India Limited) ex-works price plus Excise Duty thereof (In rupees
per tone) for the relevant category of steel supplied by the contractor as prevailing on the first
day of the month in which the steel was purchased by the contractor (or) as prevailing on the
first day of the month in which steel was brought to the site by the contractor whichever is
lower.
SB SAILs ex-works price plus Excise Duty thereof ( in Rs. Per tonne) for the relevant category
of steel supplied by the contractor as prevailing on the first day of the month in which the
tender was opened.
CV Value of cement supplied by contractor as per „on account‟ bill in the quarter under
consideration.
CB Index no. of Wholesale Price of sub-group (of Cement & Lime) as published in RBI Bulletin
for the base period.
CQ Index no. of Wholesale Price of sub-group (of Cement & Lime) as published in RBI Bulletin
for the average price index of the 3 months of the quarter under consideration.
32
Tender No. 03/Central/2016
Sr.DEN/Central/BZA Signature of Tenderer(s)
Page 32 of 91 BZA Divn., SCR, T.No.03/Central/2016 invited vide Open Tender No.DRM/Works/BZA/03/2016 dt. 05.02.2016, date of opening on 08.03.2016 for the work of SW-I) BZA Division: GDR-BZA sec.Proposed safety related track repairs in SSE/P.Way /CLX, BPP and TEL sections of ADEN/BPP Sub- Division. SW-II) BZA Division: BZA-VSKP sec.Proposed safety related track repairs in SSE/P.Way /Eluru & Nuzvid sections of ADEN/Eluru Sub- Division. SW-III) BZA Division: GDR-BZA sec. Transportation of P.Way materials for scattered and casual renewals Departmentally and for collection scrap in yards for the year 2015-16 in ADEN/BPP sub-division. SW-IV) BZA Division: BZA - VSKP Sec. Transportation of P.Way materials for scattered and casual renewals Departmentally and for collection scrap in yards for the year 2015-16 in ADEN/EE sub-division. SW-V) BZA Division: GDR-BZA sec.: TFR - Through fitting renewal for a length of 65.45km (without ERC) and 1.46km (with all fittings) on up & Dn lines in ADEN/Bapatla Sub-division. SW-VI) BZA Division: GDR-BZA sec.KCC: Shifiting of crossover S103A &B towards Gudur duly making TRD and S&T alterations in KCC yard in ADEN/BPP sub-division SW-VII) BZA Division: GDR-BZA sec. KCC- Shifting of layout of crossover S121 in KCC yard in ADEN/BPP sub-division. SW-VIII) BZA Division: GDR-BZA sec. KCC - Replacement of
Non-standard diamond crossing at KCC yard Pt No. 144A,B & 145 A,B in KCC yard in ADEN/BPP sub-division. . . .
Cs RBI Wholesale Price index for cement and lime for the month which is six months prior to date of
casting of foundation. Co RBI Wholesale Price index for cement and lime for the month which is one month prior to date of
opening of tender.
RT IEEMA Price index for Iron & Steel for the month which is two months prior to date of
inspection of material.
Ro IEEMA Price index for Iron & Steel for the month which is one month prior to date of opening
of tender.
PT IEEMA Price for Copper wire bar for the month which is two months prior to date of inspection
of material.
Po IEEMA Price for Copper wire bar for the month which is one month prior to date of opening of
tender.
ZT IEEMA Price for Zinc for the month which is two months prior to date of inspection of material.
Zo IEEMA Price for Zinc for the month which is one month prior to date of opening of tender.
IT RBI Wholesale Price index for structural clay products for the month which is two months prior
to date of inspection of material.
Io RBI Wholesale Price index for structural clay products for the month which is one month prior
to date of opening of tender. 46A,
8.
The demands for escalation of cost shall be allowed on the basis of provisional indices made
available by Reserve Bank of India. Any adjustment needed to be done based on the finally
published indices shall be made as and when they became available.
46A.
9.
Relevant categories of steel for the purpose of operating Price Variation formula, as mentioned
in this clause, based on Sails Ex-Works Price Plus Excise Duty thereof, shall be as under:
Sl.
No. Category of Steel supplied in Railway work
Category of Steel produced by SAIL Whose Ex-
works Price Plus Excise Duty would be adopted to
determine Price Variation.
1. Reinforcement bars and other rounds TMT 8mm IS 1786 Fe 415/Fe 500
2. All types and sizes of angles Angle 65x65x6mm IS 2062 E250A SK
3. All types and sizes of plates PM plates above 10-20mm IS 2062 E250A SK
4. All Types and sizes of channels and joists Channels 200x75mm IS 2062 E250A SK
5. Any other section of steel not covered in the
above categories and excluding HTS
Average of price for the 3 categories covered
under SL 1, 2, & 3 above.
46A.10 Price variation During Extended Period of contract.
The price adjustment as worked out above, ie., either increase or decrease shall be applicable up to the
stipulated date of completion of work including the extended period of completion where such extension
has been granted under Clause 17-1 Of the General Conditions of Contract. However, where extension of
time has been granted due to contractors failure under Clause-17B of the General conditions of Contract,
price adjustments shall be done as follows:
a) In case the indices increase above the indices applicable to the last month of original completion
period or the extended period under clause 17-A, the price adjustment for the period of extension
granted under Clause 17-B shall be limited to the amount payable as per the Indices applicable to
the last month of the original completion period or the extended period under clause 17-A of the
General conditions of contract; as the case may be.
b) In case the indices fall below the indices applicable to the last month of original/extended period of
completion under clause 17-A, as the case may be; then the lower indices shall be adopted for the
price adjustment for the period of extension under clause 17-B of the General Conditions of
Contract.
33
Tender No. 03/Central/2016
Sr.DEN/Central/BZA Signature of Tenderer(s)
Page 33 of 91 BZA Divn., SCR, T.No.03/Central/2016 invited vide Open Tender No.DRM/Works/BZA/03/2016 dt. 05.02.2016, date of opening on 08.03.2016 for the work of SW-I) BZA Division: GDR-BZA sec.Proposed safety related track repairs in SSE/P.Way /CLX, BPP and TEL sections of ADEN/BPP Sub- Division. SW-II) BZA Division: BZA-VSKP sec.Proposed safety related track repairs in SSE/P.Way /Eluru & Nuzvid sections of ADEN/Eluru Sub- Division. SW-III) BZA Division: GDR-BZA sec. Transportation of P.Way materials for scattered and casual renewals Departmentally and for collection scrap in yards for the year 2015-16 in ADEN/BPP sub-division. SW-IV) BZA Division: BZA - VSKP Sec. Transportation of P.Way materials for scattered and casual renewals Departmentally and for collection scrap in yards for the year 2015-16 in ADEN/EE sub-division. SW-V) BZA Division: GDR-BZA sec.: TFR - Through fitting renewal for a length of 65.45km (without ERC) and 1.46km (with all fittings) on up & Dn lines in ADEN/Bapatla Sub-division. SW-VI) BZA Division: GDR-BZA sec.KCC: Shifiting of crossover S103A &B towards Gudur duly making TRD and S&T alterations in KCC yard in ADEN/BPP sub-division SW-VII) BZA Division: GDR-BZA sec. KCC- Shifting of layout of crossover S121 in KCC yard in ADEN/BPP sub-division. SW-VIII) BZA Division: GDR-BZA sec. KCC - Replacement of
Non-standard diamond crossing at KCC yard Pt No. 144A,B & 145 A,B in KCC yard in ADEN/BPP sub-division. . . .
12. DEDUCTION OF INCOME TAX AT SOURCE
In terms of new Section 194-C inserted by the Finance Act 1972 , in the income tax Act 1961
the Railway shall at the time of arranging payments to the contractor and/or sub contractor(in
the case of sub contractor only when the Railway is responsible for payment of consideration
to him under the contract) for carrying out any work (including supply of labour for carrying
out any work) under the contract be entitled to deduct income tax at source on Income
comprised in the sum of such payments.
The deduction towards income tax to be made at source from the payments due to non-
residents shall continue to be governed by Section 195 of the Income Tax Act 1961.
No Income Tax will be deducted by the Railway on payments made for supply of materials
where such value of supply portion is distinct and ascertainable such as supply of Timber, tiles,
bricks, ballast including track/ballast etc. The deductions towards Income Tax to be made at
source from the payment due to non/residents shall continue to be governed by Section 195 of
the Income Tax Act 1961.
13. LIABILITY OF CONTRACTOR(S) - ANY DAMAGE SUSTAINED BY RAILWAYS
DURING ACCIDENTS ETC., CAUSED DUE TO CONTRACTOR(S) FAILURES, FAULT
OR NEGLIGENCE. Railway will post an Engineer-in-charge who may be SSE/SE/JE or Supervisor of any grade at
site for Technical Supervision of the work. This Engineer-in-charge will be responsible for
safety of the traffic. The work shall be executed by the contractor in a workman like manner to
the satisfaction of the Engineer-in-charge. The Contractor and his labour shall be guided by the
instructions of the Engineer-in-Charge. In the event of any accident occurring at the work site
and it is established during the departmental enquiry by the Railway or by Statutory enquiry of
CRS, that the accident occurred wholly or partly due to any act tantamounting to negligence on
the part of the contractor or his labour in not adhering to the instructions of the engineer-in-
charge, the contractor shall render himself liable for damages and also legal prosecution if loss
of life is involved.
14. Implementation of – the Building and other construction Workers (RECS) Act, 1996
and the Building and other Construction Workers Welfare Cess Act, 1996 in Railway
Contracts. “The Tenderer for carrying out any construction work in Andhra Pradesh (name of State) must
get themselves registered from the Registering Officer under Section-7 of the Building and
other Construction Workers Act, 1996 and rules made thereto by the Andhra Pradesh (name of
State)Government and submit certificate of registration issued from the Registering Officer of
the Andhra Pradesh(name of the State) Government (Labour Department). For enactment of
this act, the Tenderer shall be required to pay cess @ 1% of cost of construction work to be
deducted from each bill, Cost of material shall be outside the purview of cess, when supplied
under a separate schedule item.”
34
Tender No. 03/Central/2016
Sr.DEN/Central/BZA Signature of Tenderer(s)
Page 34 of 91 BZA Divn., SCR, T.No.03/Central/2016 invited vide Open Tender No.DRM/Works/BZA/03/2016 dt. 05.02.2016, date of opening on 08.03.2016 for the work of SW-I) BZA Division: GDR-BZA sec.Proposed safety related track repairs in SSE/P.Way /CLX, BPP and TEL sections of ADEN/BPP Sub- Division. SW-II) BZA Division: BZA-VSKP sec.Proposed safety related track repairs in SSE/P.Way /Eluru & Nuzvid sections of ADEN/Eluru Sub- Division. SW-III) BZA Division: GDR-BZA sec. Transportation of P.Way materials for scattered and casual renewals Departmentally and for collection scrap in yards for the year 2015-16 in ADEN/BPP sub-division. SW-IV) BZA Division: BZA - VSKP Sec. Transportation of P.Way materials for scattered and casual renewals Departmentally and for collection scrap in yards for the year 2015-16 in ADEN/EE sub-division. SW-V) BZA Division: GDR-BZA sec.: TFR - Through fitting renewal for a length of 65.45km (without ERC) and 1.46km (with all fittings) on up & Dn lines in ADEN/Bapatla Sub-division. SW-VI) BZA Division: GDR-BZA sec.KCC: Shifiting of crossover S103A &B towards Gudur duly making TRD and S&T alterations in KCC yard in ADEN/BPP sub-division SW-VII) BZA Division: GDR-BZA sec. KCC- Shifting of layout of crossover S121 in KCC yard in ADEN/BPP sub-division. SW-VIII) BZA Division: GDR-BZA sec. KCC - Replacement of
Non-standard diamond crossing at KCC yard Pt No. 144A,B & 145 A,B in KCC yard in ADEN/BPP sub-division. . . .
ANNEXURE- “III”
WORKS CONTRACT CLAUSE-13
1. In case cement, Steel, AC sheet with or without accessories, GI sheets with or without
accessories, glasses or any other materials/items are issued to the contractor(s) either free of
cost or on cost to be recovered for use on the work as stipulated in the agreement the supply
thereof shall be made in stages depending on the progress of the work, limited to the quantity
/quantities computed by the Railway, according to the prescribed specification and approved
drawings as per agreement.
The materials supplied should conform to Railway‟s Specification in all respects should be
in accordance with approved sample.
All such materials supplied to the contractor(s) for the work either free of charge or on
payment as the case may be will be issued to contractor(s) at the Railway depot/godown/goods
shed and will have to be transported by the contractor to the site of work at his cost. All such
materials shall be used by the Contractor for the work in such quantities as are indicated in the
schedule or in the relevant specifications or drawings or as approved by the Engineer, whose
decision thereon shall be final. Wastage or damages of such materials in any manner shall be
totally avoided. The contractor(s) shall be liable to the accountal for all such materials issued
by Railway either free of cost or on payment excluding the permissible wastage which incase
of steel materials should not in any case exceed 1% of the total quantity required for the work
as per the approved drawings. No wastage under other items is permissible. Short lengths of
rods should also be utilized to the extent possible by overlapping joints.
The Cement, Steel, A.C.Sheets with or without accessories, G.I sheets with or without
accessories glasses or any other materials issued in excess of the requirement(s) as above, shall
be returned in perfectly good condition by the contractor(s) to the Railway at the Railway
depot/Godown/Goods shed at________immediately after completion or termination of the
contract. If the contractor fails to return the said materials then the cost of such materials issued
in excess of the requirement as computed by Railway according to the specification and
approved drawings will be recovered from the contractor(s) at twice the prevailing procurement
cost at the time of last issue viz., 2 x (purchases price +5% freight only). This will be without
prejudice to the right of Railway to take action against the contractors under the condition of
the contract for not doing/completing the work according to the prescribed specification and
approved drawings. If it is discovered that the quantity of cement, steel or any other material
used is less than the quantity computed by the Railway, according to specifications and
approved drawings the cost of materials not returned will be recovered at the same rates as
applicable to excess issue of materials, indicated in the preceding para.
35
Tender No. 03/Central/2016
Sr.DEN/Central/BZA Signature of Tenderer(s)
Page 35 of 91 BZA Divn., SCR, T.No.03/Central/2016 invited vide Open Tender No.DRM/Works/BZA/03/2016 dt. 05.02.2016, date of opening on 08.03.2016 for the work of SW-I) BZA Division: GDR-BZA sec.Proposed safety related track repairs in SSE/P.Way /CLX, BPP and TEL sections of ADEN/BPP Sub- Division. SW-II) BZA Division: BZA-VSKP sec.Proposed safety related track repairs in SSE/P.Way /Eluru & Nuzvid sections of ADEN/Eluru Sub- Division. SW-III) BZA Division: GDR-BZA sec. Transportation of P.Way materials for scattered and casual renewals Departmentally and for collection scrap in yards for the year 2015-16 in ADEN/BPP sub-division. SW-IV) BZA Division: BZA - VSKP Sec. Transportation of P.Way materials for scattered and casual renewals Departmentally and for collection scrap in yards for the year 2015-16 in ADEN/EE sub-division. SW-V) BZA Division: GDR-BZA sec.: TFR - Through fitting renewal for a length of 65.45km (without ERC) and 1.46km (with all fittings) on up & Dn lines in ADEN/Bapatla Sub-division. SW-VI) BZA Division: GDR-BZA sec.KCC: Shifiting of crossover S103A &B towards Gudur duly making TRD and S&T alterations in KCC yard in ADEN/BPP sub-division SW-VII) BZA Division: GDR-BZA sec. KCC- Shifting of layout of crossover S121 in KCC yard in ADEN/BPP sub-division. SW-VIII) BZA Division: GDR-BZA sec. KCC - Replacement of
Non-standard diamond crossing at KCC yard Pt No. 144A,B & 145 A,B in KCC yard in ADEN/BPP sub-division. . . .
2. It shall be the responsibility of the contractor to keep in safe custody any Railway material plant or
equipment issued for the work. The contractor shall at his own expense provide suitable temporary
shed/sheds for this purpose on the Railway land made available by the Railway free of rent and
shall remove the shed/sheds when no longer required in terms of clause 30 of General conditions
of contract.
3. If due to any reason the Railway is not in a position to make available the Railway land the
Railway Engineer-in-charge of the work may permit the contractor to erect at his own cost
shed/sheds or secure private accommodation outside the Railway premises. In such a case the
contractor may be permitted to take the Railway material required for the works outside the
railway premises and to store in the Shed so erected or private accommodation so secured. It shall
be the responsibility of the contractor to keep the railway material in safe custody and the same
should be kept entire separate from the contractors material and the Railway shall have liberty to
inspect the same from time to time.
4. The code Nos. description and rates given in the schedule are based on the printed USSR - 2010,
of S.C.Railway. Any discrepancy noticed during the execution of the work, in the working rates
quantity of cement etc. should be rectified by reference to the printed schedule, which shall be
treated as authoritative and binding on the contract. The relevant notes applicable to the respective
sub chapters will apply to the items of the Tender schedule and should be considered as having
been incorporated in the contract agreement and binding on the Contractor.
5. For any other items not specially shown in the schedule of rates appended to the tender document,
the Divisional/Executive Engineer will offer rates as shown for the_________ zone in the South
central railway printed USSR - 2010, of S.C.Railway subject to the same percentage adjustment
accepted in the contract being applicable to the additional items.
6. Railway shall not supply from its own quota to the contractors controlled or imported
commodities. Assistance will, however given by recommending to appropriate authorities.
Contractor applications for issue of import licenses and release of controlled commodities if the
Engineer is satisfied that this material is actually required by contractor for carrying out the work
and is not available in the country.
7. VARIATION OF COSTS
Price variation clause is not applicable for contract agreement value upto Rs.50 lakhs. Time
is the essence of contract
8. (a) PERIOD OF COMPLETION: The Railway expects that a resourceful and experienced
contractor should be able to complete the work in all respects within the period as
specified in the Tender Notice and in the Schedule where items of work are furnished
from the date of letter of acceptance of the Tender
(b) Extension of time of completion will be governed by clause 17 of General Conditions of
Contract. However, while granting the extension of time under clause 17(B) of GCC, a
token penalty as deemed fit based on the circumstances of the case can be imposed on
the contractor without prejudice to other rights of Railway Administration as
provided under GCC.
9. MAINTENANCE PERIOD: The work shall be maintained after completion for a period as
specified in the Schedule where items of work are furnished by the contractor and he shall
make good any defects, imperfections, shrinkages or faults which may appear at his own cost.
10. It is HEREBY AGREED that it shall be the duty of the contractor to keep himself informed of all
corrections, and amendments of the said General conditions of contract made up to the date of the
execution of these presents and no objection shall be taken by the contractor on the ground that he
was not aware of such amendments and corrections of the said General Conditions of Contract or
to any of them.
36
Tender No. 03/Central/2016
Sr.DEN/Central/BZA Signature of Tenderer(s)
Page 36 of 91 BZA Divn., SCR, T.No.03/Central/2016 invited vide Open Tender No.DRM/Works/BZA/03/2016 dt. 05.02.2016, date of opening on 08.03.2016 for the work of SW-I) BZA Division: GDR-BZA sec.Proposed safety related track repairs in SSE/P.Way /CLX, BPP and TEL sections of ADEN/BPP Sub- Division. SW-II) BZA Division: BZA-VSKP sec.Proposed safety related track repairs in SSE/P.Way /Eluru & Nuzvid sections of ADEN/Eluru Sub- Division. SW-III) BZA Division: GDR-BZA sec. Transportation of P.Way materials for scattered and casual renewals Departmentally and for collection scrap in yards for the year 2015-16 in ADEN/BPP sub-division. SW-IV) BZA Division: BZA - VSKP Sec. Transportation of P.Way materials for scattered and casual renewals Departmentally and for collection scrap in yards for the year 2015-16 in ADEN/EE sub-division. SW-V) BZA Division: GDR-BZA sec.: TFR - Through fitting renewal for a length of 65.45km (without ERC) and 1.46km (with all fittings) on up & Dn lines in ADEN/Bapatla Sub-division. SW-VI) BZA Division: GDR-BZA sec.KCC: Shifiting of crossover S103A &B towards Gudur duly making TRD and S&T alterations in KCC yard in ADEN/BPP sub-division SW-VII) BZA Division: GDR-BZA sec. KCC- Shifting of layout of crossover S121 in KCC yard in ADEN/BPP sub-division. SW-VIII) BZA Division: GDR-BZA sec. KCC - Replacement of
Non-standard diamond crossing at KCC yard Pt No. 144A,B & 145 A,B in KCC yard in ADEN/BPP sub-division. . . .
11. VARIATION IN CONTRACT QUANTITIES:-
The procedure as detailed below shall be adopted for dealing with variations in quantities
during execution of works contracts:
a) The Railway reserves the right to alter the designs and drawings. If due to change of drawing
or design or any other reasons, there be variations, either increase or decrease in quantities,
payment will be made only for the actual quantities executed at the accepted rates. If there be
sufficient cause the Railway may grant extension of the date of completion suitably. Such
circumstances shall in no way affect or vitiate the contract or alter the character thereof, or
entitle the contractor to damages or compensation thereof except as provided for in this
contract.
b) The quantities of each item of work furnished in the Schedule are approximate and are
intended for the guidance of Tenderer/Contractor. In actual execution of work there may be
some increase in the quantities specified. Such variation upto 25% shall in no degree affect
the validity of the contract and it shall be performed by the contractor as provided therein and
be subjected to the same conditions, stipulations and obligations originally and expressly
included and provided for in specifications and drawings and the amount to be paid there for
shall be calculated in accordance with accepted schedule rates.
(1) Prior Finance concurrence is necessary for varying the individual quantities beyond
25% or where the gross agreement value exceeds 25% of the agreement value.
(2) Individual NS items in contracts shall be operated with variations of plus or minus
25% and payment would be made as per the agreement rate. For this, no Finance
concurrence would be required.
(3) In case an increase in quantity of an individual item by more than 25% of the
agreement quantity is considered unavoidable, the same shall be got executed by
floating a fresh tender. If floating a fresh tender for operating that item is considered
not practicable, quantity of that item may be operated in excess of 125% of the
agreement quantity (100% i.e. the original quantity +25% i.e. quantity over and above
the original quantity) subject to the following conditions.
a) Operation of an item by more than 125% of the agreement quantity needs the
approval of an officer of the rank not less than S.A. Grade:
i) Quantities operated in excess of 125% but upto 140% of the agreement
quantity of the concerned item, shall be paid at 98% of the rate awarded
for that item in that particular tender;
ii) Quantities operated in excess of 140% but upto 150% of the agreement
quantity of the concerned item shall be paid at 96% of the rate awarded
for that item in that particular tender;
iii) Variation in quantities of individual items beyond 150% will be
prohibited and would be permitted only in exceptional unavoidable
circumstances with the concurrence of associate finance and shall be paid
at 96% of the rate awarded for that item in that particular tender
b) The variation in quantities as per the above formula will apply only to the
Individual items of the contract and not on the overall contract value.
c) Execution of quantities beyond 150% of the overall agreement value should not
be permitted and, if found necessary should be only through fresh tenders or by
negotiating with existing contractor, with prior personal concurrence of
FA&CAO/ FA&CAO(C) and approval of General Manager.
37
Tender No. 03/Central/2016
Sr.DEN/Central/BZA Signature of Tenderer(s)
Page 37 of 91 BZA Divn., SCR, T.No.03/Central/2016 invited vide Open Tender No.DRM/Works/BZA/03/2016 dt. 05.02.2016, date of opening on 08.03.2016 for the work of SW-I) BZA Division: GDR-BZA sec.Proposed safety related track repairs in SSE/P.Way /CLX, BPP and TEL sections of ADEN/BPP Sub- Division. SW-II) BZA Division: BZA-VSKP sec.Proposed safety related track repairs in SSE/P.Way /Eluru & Nuzvid sections of ADEN/Eluru Sub- Division. SW-III) BZA Division: GDR-BZA sec. Transportation of P.Way materials for scattered and casual renewals Departmentally and for collection scrap in yards for the year 2015-16 in ADEN/BPP sub-division. SW-IV) BZA Division: BZA - VSKP Sec. Transportation of P.Way materials for scattered and casual renewals Departmentally and for collection scrap in yards for the year 2015-16 in ADEN/EE sub-division. SW-V) BZA Division: GDR-BZA sec.: TFR - Through fitting renewal for a length of 65.45km (without ERC) and 1.46km (with all fittings) on up & Dn lines in ADEN/Bapatla Sub-division. SW-VI) BZA Division: GDR-BZA sec.KCC: Shifiting of crossover S103A &B towards Gudur duly making TRD and S&T alterations in KCC yard in ADEN/BPP sub-division SW-VII) BZA Division: GDR-BZA sec. KCC- Shifting of layout of crossover S121 in KCC yard in ADEN/BPP sub-division. SW-VIII) BZA Division: GDR-BZA sec. KCC - Replacement of
Non-standard diamond crossing at KCC yard Pt No. 144A,B & 145 A,B in KCC yard in ADEN/BPP sub-division. . . .
4. The limit for varying quantities for minor value items shall be 100% (as against
25% prescribed for other items). A minor value item for this purpose is defined as
an item whose original agreement value is less than 1% of the total original
agreement value.
5. No such quantity variation limit shall apply for foundation items.
6. As far as SSR/SOR items are concerned, the limit of 25% would apply to the
value of SSR/SOR schedule as a whole and not on individual SSR/SOR items.
However, in case of NS items, the limit of 25% would apply on the individual
items irrespective of the manner of quoting the rate (single percentage rate or
individual item rate).
7. For the tenders accepted at the Zonal Railways level, variations in the quantities
will be approved by the authority in whose powers revised value of the agreement
lies.
8. For tenders accepted by General Manager, variations upto 125% of the original
agreement value may be accepted by General Manager.
9. For tenders accepted by Board Members and Railway Ministers variations upto
110% of the original agreement value may be accepted by General Manager
10. The aspect of vitiation of tender with respect to variation in quantities should be
checked and avoided. In case of vitiation of the tender (both for increase as well as
decrease of value of contract agreement) sanction of the competent authority as per
single tender should be obtained.
11. In cases where decrease is involved during execution of contract:
a. The contract signing authority can decrease the items upto 25% of
individual item without finance concurrence.
b. For decrease beyond 25% for individual items or 25% of contract
agreement value, the approval of an officer not less than rank of S.A.
Grade may be taken, after obtaining „No claim certificate‟ from the
contractor and with finance concurrence giving detailed reasons for each
such decrease in the quantities.
c. It should be certified that the quantities proposed to be reduced will not be
required in the same work at a later stage
d. In the event of any reduction in the quantity to be executed for any reasons
whatsoever, the contractor shall not be entitled to any compensation but
shall be paid only for the actual amount of work done.
e. The contractor is bound to notify the Engineer at least seven days before the
necessity arises for the execution of any item in excess of 25% of the over
all value of the agreement.
12. In case the contractor fails to attend the meeting after being notified to do so or in
the event of no settlement being arrived at, the Railway shall be entitled to execute
the extra works by other means and the contractor shall have no claim for loss or
damage that result from such procedure
38
Tender No. 03/Central/2016
Sr.DEN/Central/BZA Signature of Tenderer(s)
Page 38 of 91 BZA Divn., SCR, T.No.03/Central/2016 invited vide Open Tender No.DRM/Works/BZA/03/2016 dt. 05.02.2016, date of opening on 08.03.2016 for the work of SW-I) BZA Division: GDR-BZA sec.Proposed safety related track repairs in SSE/P.Way /CLX, BPP and TEL sections of ADEN/BPP Sub- Division. SW-II) BZA Division: BZA-VSKP sec.Proposed safety related track repairs in SSE/P.Way /Eluru & Nuzvid sections of ADEN/Eluru Sub- Division. SW-III) BZA Division: GDR-BZA sec. Transportation of P.Way materials for scattered and casual renewals Departmentally and for collection scrap in yards for the year 2015-16 in ADEN/BPP sub-division. SW-IV) BZA Division: BZA - VSKP Sec. Transportation of P.Way materials for scattered and casual renewals Departmentally and for collection scrap in yards for the year 2015-16 in ADEN/EE sub-division. SW-V) BZA Division: GDR-BZA sec.: TFR - Through fitting renewal for a length of 65.45km (without ERC) and 1.46km (with all fittings) on up & Dn lines in ADEN/Bapatla Sub-division. SW-VI) BZA Division: GDR-BZA sec.KCC: Shifiting of crossover S103A &B towards Gudur duly making TRD and S&T alterations in KCC yard in ADEN/BPP sub-division SW-VII) BZA Division: GDR-BZA sec. KCC- Shifting of layout of crossover S121 in KCC yard in ADEN/BPP sub-division. SW-VIII) BZA Division: GDR-BZA sec. KCC - Replacement of
Non-standard diamond crossing at KCC yard Pt No. 144A,B & 145 A,B in KCC yard in ADEN/BPP sub-division. . . .
12. Employment of Civil Engineering Graduates/Diploma-holders:
The contractor shall employ the following technical staff during the execution of this work.
i) One graduate engineer when the cost of the work to be executed is Rs.2 Crores and
above.
ii) One qualified diploma holder (over-seer) when the cost of the work to be executed is
more than Rs.25 lakhs but less than Rs.2 Crores. Technical staff should be available at
site whenever required by the Engineer-in-charge to take instructions. In case the
contractor fails to employ the technical staff as aforesaid, he shall be liable to pay a
reasonable amount not exceeding a sum of Rs.40,000/- (forty thousand only) for each
month of default in case of graduate engineer and Rs.25,000/- (twenty five thousand
only) for each month of default in case of diploma holder (over-seer)
(Modification of Cl.26 and introduction of new Cl.26A to IR‟s GCC Ref: Rly. Bd.
Lr.No.2012/CE-I/CT/0/20, dt.10.05.2013.)
The decision of the Engineer-in-charge as to the period for which the required technical staff
was not employed by the contractor and as to the reasonableness of the amount to be deducted
on this account shall be final and binding on the contractor.
iii) Individuals having Diploma in Railway Engineering awarded by IPWE (India) shall also
be considered as qualified Diploma holder Engineers and contractors for track contract
works can employ such individuals at their worksite on Indian Railways.
(Ref: Rly. Bd. Lr.No.2012/CE-I/CT/0/20, dt.12.07.2013.)
Note: The above clause is not applicable for contracts for Welding of Rail joints.
13. Railway Contractors / Extension of Provident Fund Act to the Employees working under
Railway Contractors:-
The Contractor shall comply with the provisions of EPF & MP Act, 1952 and obtain code
number from the concerned authorities whenever workmen employed by him are 20 or more.
He shall also indemnify Railways from and against any claim, penalties, recoveries under the
above Act and Rules. Contractors to get the code number under the EPF so as to enable the PF
Commissioners to extend the social security benefits to the workmen engaged by the Railway
contractors. The first month‟s bill will be released only after code number is taken from the PF
Office and a copy of coverage intimation produced. Subsequently for each month, bills will be
released only on submission of challans & 12 A monthly return copy in proof of remittance of
PF dues for previous month.”
14. Conservancy charges as applicable and as modified from time to time will be recovered
from Contractor‟s running bills.
39
Tender No. 03/Central/2016
Sr.DEN/Central/BZA Signature of Tenderer(s)
Page 39 of 91 BZA Divn., SCR, T.No.03/Central/2016 invited vide Open Tender No.DRM/Works/BZA/03/2016 dt. 05.02.2016, date of opening on 08.03.2016 for the work of SW-I) BZA Division: GDR-BZA sec.Proposed safety related track repairs in SSE/P.Way /CLX, BPP and TEL sections of ADEN/BPP Sub- Division. SW-II) BZA Division: BZA-VSKP sec.Proposed safety related track repairs in SSE/P.Way /Eluru & Nuzvid sections of ADEN/Eluru Sub- Division. SW-III) BZA Division: GDR-BZA sec. Transportation of P.Way materials for scattered and casual renewals Departmentally and for collection scrap in yards for the year 2015-16 in ADEN/BPP sub-division. SW-IV) BZA Division: BZA - VSKP Sec. Transportation of P.Way materials for scattered and casual renewals Departmentally and for collection scrap in yards for the year 2015-16 in ADEN/EE sub-division. SW-V) BZA Division: GDR-BZA sec.: TFR - Through fitting renewal for a length of 65.45km (without ERC) and 1.46km (with all fittings) on up & Dn lines in ADEN/Bapatla Sub-division. SW-VI) BZA Division: GDR-BZA sec.KCC: Shifiting of crossover S103A &B towards Gudur duly making TRD and S&T alterations in KCC yard in ADEN/BPP sub-division SW-VII) BZA Division: GDR-BZA sec. KCC- Shifting of layout of crossover S121 in KCC yard in ADEN/BPP sub-division. SW-VIII) BZA Division: GDR-BZA sec. KCC - Replacement of
Non-standard diamond crossing at KCC yard Pt No. 144A,B & 145 A,B in KCC yard in ADEN/BPP sub-division. . . .
SPECIAL CONDITIONS
MODIFICATION TO CLAUSE 63 & 64 OF
GENERAL CONDITIONS OF CONTRACT
1. The Provision of Clause 63 and 64 of the General Conditions of Contract will be
applicable only for settlement of claims /disputes, for values less than or equal to
20% of the original value (excluding the cost of materials supplied free by
Railway) of the contract or 20% of the actual value of the work done (excluding the
value of the work rejected) under the contract whichever is less. When
claims/disputes are of value more than 20% of the value of the original contract or
20% of the value of the actual work done under the contract, whichever is less, the
contractor will not be entitled to seek such disputes/claims for reference to
arbitration and the provisions of Clause No; 63 &64 of the General Conditions of
Contract will not be applicable for referring the disputes to be settled through
arbitration
2. The Contractor shall furnish his monthly statement of claims as per Clause 43(1) of
General Conditions of Contract. But the Contractor should seek reference to
arbitration to settle the disputes only once, subject to the conditions as per Para 1
3. The Special conditions shall prevail over the existing Clause 63 & 64 of General
Conditions of contract
40
Tender No. 03/Central/2016
Sr.DEN/Central/BZA Signature of Tenderer(s)
Page 40 of 91 BZA Divn., SCR, T.No.03/Central/2016 invited vide Open Tender No.DRM/Works/BZA/03/2016 dt. 05.02.2016, date of opening on 08.03.2016 for the work of SW-I) BZA Division: GDR-BZA sec.Proposed safety related track repairs in SSE/P.Way /CLX, BPP and TEL sections of ADEN/BPP Sub- Division. SW-II) BZA Division: BZA-VSKP sec.Proposed safety related track repairs in SSE/P.Way /Eluru & Nuzvid sections of ADEN/Eluru Sub- Division. SW-III) BZA Division: GDR-BZA sec. Transportation of P.Way materials for scattered and casual renewals Departmentally and for collection scrap in yards for the year 2015-16 in ADEN/BPP sub-division. SW-IV) BZA Division: BZA - VSKP Sec. Transportation of P.Way materials for scattered and casual renewals Departmentally and for collection scrap in yards for the year 2015-16 in ADEN/EE sub-division. SW-V) BZA Division: GDR-BZA sec.: TFR - Through fitting renewal for a length of 65.45km (without ERC) and 1.46km (with all fittings) on up & Dn lines in ADEN/Bapatla Sub-division. SW-VI) BZA Division: GDR-BZA sec.KCC: Shifiting of crossover S103A &B towards Gudur duly making TRD and S&T alterations in KCC yard in ADEN/BPP sub-division SW-VII) BZA Division: GDR-BZA sec. KCC- Shifting of layout of crossover S121 in KCC yard in ADEN/BPP sub-division. SW-VIII) BZA Division: GDR-BZA sec. KCC - Replacement of
Non-standard diamond crossing at KCC yard Pt No. 144A,B & 145 A,B in KCC yard in ADEN/BPP sub-division. . . .
PERFORMANCE GUARANTEE
In consideration of the President of India (hereinafter called “the Government”) having
agreed to exempt-------------------- ( hereinafter called “ the said Contractor(s)”) from the demand,
under the terms and conditions of an Agreement dated -------------- made between --------------
and ---------------------------- for ------------------------- (hereinafter called “the said Agreement”), of
Security deposit for the due fulfillment by the said contractor(s) of the terms and conditions
contained in the said Agreement, on production of a Bank Guarantee for Rs.-----------------------
(Rupees-------------------------only). We --------------------------------------------------
(indicate the name of the Bank) (hereinafter referred to as the Bank) at the request of ---------------
------------ (Contractor(s) do hereby undertake to pay to the Government an amount not exceeding
Rs.--------------- against any loss / damage caused to or suffered or would be caused to or suffered
by the Government by reasons of any breach by the said contractor(s) of any of the terms or
conditions contained in the said Agreement.
2. We ---------------------------------(indicate the name of the Bank) do hereby undertake to
pay the amounts due and payable under this guarantee without any demur, merely on a demand
from the Government stating that the amount claimed is due by way of loss or damage caused to
or would be caused to or suffered by the Government by reason of breach by the said
contractor(s) of any of the terms or conditions contained in the said Agreement or by reason of
the contactor(s) failure to perform the said Agreement. Any such demand made on the bank shall
be conclusive as regards the amount due and payable by the Bank under this guarantee.
However, our liability under this guarantee shall be restricted to an amount not exceeding Rs.----
--------------.
3. We undertake to pay to the Government any money so demanded notwithstanding any
dispute or disputes raised by the contractor(s)/supplier(s) in any suite or proceeding pending
before any court or Tribunal relating thereto our liability under this present being absolute and
unequivocal.
The payment so made by us under this bond shall be a valid discharge of our liability
for payment thereunder and the contractor(s) / supplier(s) shall have no claim against us for
making such payment.
41
Tender No. 03/Central/2016
Sr.DEN/Central/BZA Signature of Tenderer(s)
Page 41 of 91 BZA Divn., SCR, T.No.03/Central/2016 invited vide Open Tender No.DRM/Works/BZA/03/2016 dt. 05.02.2016, date of opening on 08.03.2016 for the work of SW-I) BZA Division: GDR-BZA sec.Proposed safety related track repairs in SSE/P.Way /CLX, BPP and TEL sections of ADEN/BPP Sub- Division. SW-II) BZA Division: BZA-VSKP sec.Proposed safety related track repairs in SSE/P.Way /Eluru & Nuzvid sections of ADEN/Eluru Sub- Division. SW-III) BZA Division: GDR-BZA sec. Transportation of P.Way materials for scattered and casual renewals Departmentally and for collection scrap in yards for the year 2015-16 in ADEN/BPP sub-division. SW-IV) BZA Division: BZA - VSKP Sec. Transportation of P.Way materials for scattered and casual renewals Departmentally and for collection scrap in yards for the year 2015-16 in ADEN/EE sub-division. SW-V) BZA Division: GDR-BZA sec.: TFR - Through fitting renewal for a length of 65.45km (without ERC) and 1.46km (with all fittings) on up & Dn lines in ADEN/Bapatla Sub-division. SW-VI) BZA Division: GDR-BZA sec.KCC: Shifiting of crossover S103A &B towards Gudur duly making TRD and S&T alterations in KCC yard in ADEN/BPP sub-division SW-VII) BZA Division: GDR-BZA sec. KCC- Shifting of layout of crossover S121 in KCC yard in ADEN/BPP sub-division. SW-VIII) BZA Division: GDR-BZA sec. KCC - Replacement of
Non-standard diamond crossing at KCC yard Pt No. 144A,B & 145 A,B in KCC yard in ADEN/BPP sub-division. . . .
4. We, -------------------------------(indicate the name of bank) further agree that the
guarantee herein contained shall remain in full force and effect during the period that would be
taken for the performance of the said Agreement and that it shall continue to be enforceable till
all the dues of the Government under or by virtue of the said Agreement have been fully paid
and its claims satisfied or discharged or till -------------------------Office/Department) Ministry of
----------------------- certifies that the terms and conditions of the said Agreement have been fully
and properly carried out by the said Contractor(s) and accordingly discharges this guarantee.
Unless a demand or claim under this guarantee is made on us in writing on or before the ----------
----------------- we shall be discharged from all liability under this guarantee thereafter.
5. We, ---------------------(indicate the name of the Bank) further agree with the Government
that the Government shall have the fullest liberty without our consent and without affecting in
any manner our obligations hereunder to vary any of the terms and conditions of the said
Agreement or to extend time of performance by the said contractor(s) from time to time or to
postpone for any time or from time to time any of the powers exercisable by the Government
against the said Contractor(s) and to forbear or enforce any of the terms and conditions relating
to the said agreement and we shall not be relieved from our liability by reason of any such
variation, or extension being granted to the said Contractor(s) or for any forbearance, act or
omission on the part of the Government or any indulgence by the Government to the said
Contractor(s) or any such matter or thing whatsoever which under the law relating to the sureties
would, but for this provision, have effect of so relieving us.
6. This guarantee will not be discharged due to the change in the constitution of the
bank or the Contractor(s) / Supplier(s).
7. We, ----------------------(indicate the name of the bank) lastly under take not to revoke this
guarantee during its currency except with the previous consent of the Government in writing.
Dated: the---------------- day of --------------- 200
For -----------------------------------
(indicate the name of the bank)
42
Tender No. 03/Central/2016
Sr.DEN/Central/BZA Signature of Tenderer(s)
Page 42 of 91 BZA Divn., SCR, T.No.03/Central/2016 invited vide Open Tender No.DRM/Works/BZA/03/2016 dt. 05.02.2016, date of opening on 08.03.2016 for the work of SW-I) BZA Division: GDR-BZA sec.Proposed safety related track repairs in SSE/P.Way /CLX, BPP and TEL sections of ADEN/BPP Sub- Division. SW-II) BZA Division: BZA-VSKP sec.Proposed safety related track repairs in SSE/P.Way /Eluru & Nuzvid sections of ADEN/Eluru Sub- Division. SW-III) BZA Division: GDR-BZA sec. Transportation of P.Way materials for scattered and casual renewals Departmentally and for collection scrap in yards for the year 2015-16 in ADEN/BPP sub-division. SW-IV) BZA Division: BZA - VSKP Sec. Transportation of P.Way materials for scattered and casual renewals Departmentally and for collection scrap in yards for the year 2015-16 in ADEN/EE sub-division. SW-V) BZA Division: GDR-BZA sec.: TFR - Through fitting renewal for a length of 65.45km (without ERC) and 1.46km (with all fittings) on up & Dn lines in ADEN/Bapatla Sub-division. SW-VI) BZA Division: GDR-BZA sec.KCC: Shifiting of crossover S103A &B towards Gudur duly making TRD and S&T alterations in KCC yard in ADEN/BPP sub-division SW-VII) BZA Division: GDR-BZA sec. KCC- Shifting of layout of crossover S121 in KCC yard in ADEN/BPP sub-division. SW-VIII) BZA Division: GDR-BZA sec. KCC - Replacement of
Non-standard diamond crossing at KCC yard Pt No. 144A,B & 145 A,B in KCC yard in ADEN/BPP sub-division. . . .
South Central Railway Vijayawada Division
Tender No. 03/Central/2016
Name of work SW-I) BZA Division: GDR-BZA sec.Proposed safety related track repairs in SSE/P.Way /CLX, BPP and TEL sections of ADEN/BPP Sub- Division. SW-II) BZA Division: BZA-VSKP sec.Proposed safety related track repairs in SSE/P.Way /Eluru & Nuzvid sections of ADEN/Eluru Sub- Division. SW-III) BZA Division: GDR-BZA sec. Transportation of P.Way materials for scattered and casual renewals Departmentally and for collection scrap in yards for the year 2015-16 in ADEN/BPP sub-division. SW-IV) BZA Division: BZA - VSKP Sec. Transportation of P.Way materials for scattered and casual renewals Departmentally and for collection scrap in yards for the year 2015-16 in ADEN/EE sub-division. SW-V) BZA Division: GDR-BZA sec.: TFR - Through fitting renewal for a length of 65.45km (without ERC) and 1.46km (with all fittings) on up & Dn lines in ADEN/Bapatla Sub-division. SW-VI) BZA Division: GDR-BZA sec.KCC: Shifiting of crossover S103A &B towards Gudur duly making TRD and S&T alterations in KCC yard in ADEN/BPP sub-division SW-VII) BZA Division: GDR-BZA sec. KCC- Shifting of layout of crossover S121 in KCC yard in ADEN/BPP sub-division. SW-VIII) BZA Division: GDR-BZA sec. KCC - Replacement of Non-standard diamond crossing at KCC yard Pt No. 144A,B & 145 A,B in KCC yard in ADEN/BPP sub-division.
Similar Nature
of work:- Any Railway track work or track maintenance work
Sl.
No Sanctioned Est. & dt. Allocation
Amount
Rs.
1 B/W 506/XIII/1834/Plg. Dt.05-01-2016. 04-211-32 1,31,34,108/-
2 B/W 506/XIII/1835/Plg. Dt.05-01-2016. 04-221-32, 99,84,778/-
3 B/W 506/XIII/1840/Plg. Dt.18-01-2016. 04-211-32 47,42,826/-
4 B/W 506/XIII/1841/Plg. Dt.18-01-2016. 04-221-32 44,82,504/-
5 W.504/BZA/496 dt.25-8-2015.
PB/PWP item No.474/31030 of 2015-16, Q.3142-03 1,04,01,976/-
6 B/W 506/XIII/1849/Plg. Dt.03.02.2016 21.3143.03 6,82,482/-
7 B/W 506/XIII/1850/Plg. Dt.03.02.2016 21.3143.03 3,30,256/-
8 B/W 506/XIII/1851/Plg. Dt.03.02.2016 21.3143.03 11,78,848/-
Approx. Cash value: Rs. 4,49,37,778/-
Period of completion 11 Months
Maintenance period 02 Months
Name of the Tenderer/
Contractor
43
Tender No. 03/Central/2016
Sr.DEN/Central/BZA Signature of Tenderer(s)
Page 43 of 91 BZA Divn., SCR, T.No.03/Central/2016 invited vide Open Tender No.DRM/Works/BZA/03/2016 dt. 05.02.2016, date of opening on 08.03.2016 for the work of SW-I) BZA Division: GDR-BZA sec.Proposed safety related track repairs in SSE/P.Way /CLX, BPP and TEL sections of ADEN/BPP Sub- Division. SW-II) BZA Division: BZA-VSKP sec.Proposed safety related track repairs in SSE/P.Way /Eluru & Nuzvid sections of ADEN/Eluru Sub- Division. SW-III) BZA Division: GDR-BZA sec. Transportation of P.Way materials for scattered and casual renewals Departmentally and for collection scrap in yards for the year 2015-16 in ADEN/BPP sub-division. SW-IV) BZA Division: BZA - VSKP Sec. Transportation of P.Way materials for scattered and casual renewals Departmentally and for collection scrap in yards for the year 2015-16 in ADEN/EE sub-division. SW-V) BZA Division: GDR-BZA sec.: TFR - Through fitting renewal for a length of 65.45km (without ERC) and 1.46km (with all fittings) on up & Dn lines in ADEN/Bapatla Sub-division. SW-VI) BZA Division: GDR-BZA sec.KCC: Shifiting of crossover S103A &B towards Gudur duly making TRD and S&T alterations in KCC yard in ADEN/BPP sub-division SW-VII) BZA Division: GDR-BZA sec. KCC- Shifting of layout of crossover S121 in KCC yard in ADEN/BPP sub-division. SW-VIII) BZA Division: GDR-BZA sec. KCC - Replacement of Non-standard diamond
crossing at KCC yard Pt No. 144A,B & 145 A,B in KCC yard in ADEN/BPP sub-division. . . .
Schedule A List of items of works that are covered by Unified SSR-2010 (works)
Sl.No SSR.No Description of Item SW-I Qty.
SW-II
Qty.
SW-III
Qty.
SW-IV
Qty.
SW-V
Qty.
SW-VI
Qty.
SW-VII
Qty.
SW-VIII
Qty.
Total Qty.
Rate Rs.
Unit Amount
Rs.
1 013120 Earth in filling in Embankment guidebunds, bridge gaps, trolley refugees etc other than BC Soils
0 0 0 0 0 500 0 1200 1700 164.84 Cum 280228
Single item Schedule - 'A' Total 280228
PERCENTAGE RATE TO BE QUOTED
IN FIGURES
PERCENTAGE RATE TO BE QUOTED
IN WORDS
44
Tender No. 03/Central/2016
Sr.DEN/Central/BZA Signature of Tenderer(s)
Page 44 of 91 BZA Divn., SCR, T.No.03/Central/2016 invited vide Open Tender No.DRM/Works/BZA/03/2016 dt. 05.02.2016, date of opening on 08.03.2016 for the work of SW-I) BZA Division: GDR-BZA sec.Proposed safety related track repairs in SSE/P.Way /CLX, BPP and TEL sections of ADEN/BPP Sub- Division. SW-II) BZA Division: BZA-VSKP sec.Proposed safety related track repairs in SSE/P.Way /Eluru & Nuzvid sections of ADEN/Eluru Sub- Division. SW-III) BZA Division: GDR-BZA sec. Transportation of P.Way materials for scattered and casual renewals Departmentally and for collection scrap in yards for the year 2015-16 in ADEN/BPP sub-division. SW-IV) BZA Division: BZA - VSKP Sec. Transportation of P.Way materials for scattered and casual renewals Departmentally and for collection scrap in yards for the year 2015-16 in ADEN/EE sub-division. SW-V) BZA Division: GDR-BZA sec.: TFR - Through fitting renewal for a length of 65.45km (without ERC) and 1.46km (with all fittings) on up & Dn lines in ADEN/Bapatla Sub-division. SW-VI) BZA Division: GDR-BZA sec.KCC: Shifiting of crossover S103A &B towards Gudur duly making TRD and S&T alterations in KCC yard in ADEN/BPP sub-division SW-VII) BZA Division: GDR-BZA sec. KCC- Shifting of layout of crossover S121 in KCC yard in ADEN/BPP sub-division. SW-VIII) BZA Division: GDR-BZA sec. KCC - Replacement of Non-standard diamond
crossing at KCC yard Pt No. 144A,B & 145 A,B in KCC yard in ADEN/BPP sub-division. . . .
Schedule A1 List of items of works that are covered by P-way SSR - 2004.
Sl.No SSR.No Description of Item SW-I Qty.
SW-II Qty.
SW-III
Qty.
SW-IV
Qty.
SW-V Qty.
SW-VI
Qty.
SW-VII
Qty.
SW-VIII
Qty.
Total Qty.
Rate Rs.
Unit Amount
Rs.
1 18061000 Carrying out pre and post tamping works on track to facilitate machine tamping of track with in the nominated traffic block as and when allotted with
all contractors labour, tools, lead and lift etc., complete including crossing of track whenever necessary and as directed by engineer in charge at site.
70000 70000 0 0 0 0 0 0 140000 5.70 TRM 798000
Note 1.Contractor to ensure safety of his staff while working.
2. Contractor to assist to machine staff for fueling oil etc.
3. No payment will be made if no tamping is done due to any reason.
4. Contractor to provide men during tamping.
5. Tamping blocks are not identical and it may be given at any time either during day or night.
6. The work is required to be carried out in the following sequence
(I) PRE TAMPING OPERATIONS:
i) First stage of pre tamping:
During this stage the contractor is expected to mobilize/deploy a minimum of 30 work men per day, one month in advance during which period the men are required to attend the following pre identified activities as given under .
a) Filling up the ballast in the tamping zone.
b) Recouping worn-out/missing fittings as identified
c) Removal of rail head ballast
d) Removal of ballast over sleepers to make them visible while tamping
45
Tender No. 03/Central/2016
Sr.DEN/Central/BZA Signature of Tenderer(s)
Page 45 of 91 BZA Divn., SCR, T.No.03/Central/2016 invited vide Open Tender No.DRM/Works/BZA/03/2016 dt. 05.02.2016, date of opening on 08.03.2016 for the work of SW-I) BZA Division: GDR-BZA sec.Proposed safety related track repairs in SSE/P.Way /CLX, BPP and TEL sections of ADEN/BPP Sub- Division. SW-II) BZA Division: BZA-VSKP sec.Proposed safety related track repairs in SSE/P.Way /Eluru & Nuzvid sections of ADEN/Eluru Sub- Division. SW-III) BZA Division: GDR-BZA sec. Transportation of P.Way materials for scattered and casual renewals Departmentally and for collection scrap in yards for the year 2015-16 in ADEN/BPP sub-division. SW-IV) BZA Division: BZA - VSKP Sec. Transportation of P.Way materials for scattered and casual renewals Departmentally and for collection scrap in yards for the year 2015-16 in ADEN/EE sub-division. SW-V) BZA Division: GDR-BZA sec.: TFR - Through fitting renewal for a length of 65.45km (without ERC) and 1.46km (with all fittings) on up & Dn lines in ADEN/Bapatla Sub-division. SW-VI) BZA Division: GDR-BZA sec.KCC: Shifiting of crossover S103A &B towards Gudur duly making TRD and S&T alterations in KCC yard in ADEN/BPP sub-division SW-VII) BZA Division: GDR-BZA sec. KCC- Shifting of layout of crossover S121 in KCC yard in ADEN/BPP sub-division. SW-VIII) BZA Division: GDR-BZA sec. KCC - Replacement of Non-standard diamond
crossing at KCC yard Pt No. 144A,B & 145 A,B in KCC yard in ADEN/BPP sub-division. . . .
e) Squaring/spacing of sleepers
f) Rectification of tilted sleepers
g) Screening/Inserting of fresh ballast at pumping joint locations duly removing the white rounded ballast manually.
ii) Second stage of pre tamping operation:
It has to be carried out just ahead of tamping machine which includes the following
a) Opening of L.C gates and removal of check rails.
b) Removal of guard rails which requires 4 men including the item (a) above
c) Removal of OHE/S&T bonds for which one man require
d) Tightening/Re-fixing of loose fittings. 2 men required.
e) Removal/Re-fixing of joggled fish plates – 8 men required
II) During Tamping operations:
a) 4 men to be deputed for machine maintenance/for picking up dropped tools and machine parts during block.
b) 2 men for immediately re-fixing of OHE/S&T bonds after tamping
(III) Post Tamping operations:
a) Filling of voids with ballast in the tamping zone which requires 20 men per KM.
7. All the tools and plant required to carryout the work are to be arranged by the contractor at his own cost.
(Item one only) Schedule - 'A1' Total 798000
PERCENTAGE RATE TO BE QUOTED
IN FIGURES
PERCENTAGE RATE TO BE QUOTED
IN WORDS
46
Tender No. 03/Central/2016
Sr.DEN/Central/BZA Signature of Tenderer(s)
Page 46 of 91 BZA Divn., SCR, T.No.03/Central/2016 invited vide Open Tender No.DRM/Works/BZA/03/2016 dt. 05.02.2016, date of opening on 08.03.2016 for the work of SW-I) BZA Division: GDR-BZA sec.Proposed safety related track repairs in SSE/P.Way /CLX, BPP and TEL sections of ADEN/BPP Sub- Division. SW-II) BZA Division: BZA-VSKP sec.Proposed safety related track repairs in SSE/P.Way /Eluru & Nuzvid sections of ADEN/Eluru Sub- Division. SW-III) BZA Division: GDR-BZA sec. Transportation of P.Way materials for scattered and casual renewals Departmentally and for collection scrap in yards for the year 2015-16 in ADEN/BPP sub-division. SW-IV) BZA Division: BZA - VSKP Sec. Transportation of P.Way materials for scattered and casual renewals Departmentally and for collection scrap in yards for the year 2015-16 in ADEN/EE sub-division. SW-V) BZA Division: GDR-BZA sec.: TFR - Through fitting renewal for a length of 65.45km (without ERC) and 1.46km (with all fittings) on up & Dn lines in ADEN/Bapatla Sub-division. SW-VI) BZA Division: GDR-BZA sec.KCC: Shifiting of crossover S103A &B towards Gudur duly making TRD and S&T alterations in KCC yard in ADEN/BPP sub-division SW-VII) BZA Division: GDR-BZA sec. KCC- Shifting of layout of crossover S121 in KCC yard in ADEN/BPP sub-division. SW-VIII) BZA Division: GDR-BZA sec. KCC - Replacement of Non-standard diamond
crossing at KCC yard Pt No. 144A,B & 145 A,B in KCC yard in ADEN/BPP sub-division. . . .
Schedule-'B' List of items of works that are not covered by P-way SSR 2004. of S.C. Railway, Vijayawada division
Sl.No SSR.No Description of Item SW-I Qty.
SW-II Qty.
SW-III Qty.
SW-IV Qty.
SW-V Qty.
SW-VI
Qty.
SW-VII
Qty.
SW-VIII
Qty.
Total Qty.
Rate Rs.
Unit Amount
Rs.
1 NS Boxing and sectioning of ballast in LWR/CWR track including deweeding if any over the ballast and on cess duly filling the ballast wherever deficiency noticed in cribs and shoulders by leading excess ballast on cess and between completing the profile same as IRPWM ans as directed by engineer in charge with all contractors labour, tools, plant consumables, stores etc.Conplete and as directed by the Engineer-in-Charge
272300 209300 0 0 0 0 0 0 481600 18.12 TRM 8726592
2 NS
Removing and screening of ballast (excluding points and crossings) in betweeen and around the sleepers up to a depth of 50mm without disturbing the core and to a slope of 1 in 40 on either sides from centre upto the end of the sleeper including screening of ballast in the either soulders up to formation level using inclined screens and removing weeds with roots and boxing of ballast to the frofile specified in P-way manual including re-adjustment of ballast by leading the excess ballast to deficient locations upto a maximum lead of 50mts and depositing the muck etc.,Conplete and as directed by the Engineer-in-Charge.
30000 20000 0 0 0 0 0 0 50000 142.42 TRM 7121000
3 NS Removal of grass, creepers, weeds and bushes in the ballast section and on either side of track for a width of 50 cms from the toe of ballast including removal of only bushes for balance width of cess for a maximum of 1.0m, if available with all contractors labour, tools, plant with all lead and lift etc., complete as directed by engineer in charge.
47
Tender No. 03/Central/2016
Sr.DEN/Central/BZA Signature of Tenderer(s)
Page 47 of 91 BZA Divn., SCR, T.No.03/Central/2016 invited vide Open Tender No.DRM/Works/BZA/03/2016 dt. 05.02.2016, date of opening on 08.03.2016 for the work of SW-I) BZA Division: GDR-BZA sec.Proposed safety related track repairs in SSE/P.Way /CLX, BPP and TEL sections of ADEN/BPP Sub- Division. SW-II) BZA Division: BZA-VSKP sec.Proposed safety related track repairs in SSE/P.Way /Eluru & Nuzvid sections of ADEN/Eluru Sub- Division. SW-III) BZA Division: GDR-BZA sec. Transportation of P.Way materials for scattered and casual renewals Departmentally and for collection scrap in yards for the year 2015-16 in ADEN/BPP sub-division. SW-IV) BZA Division: BZA - VSKP Sec. Transportation of P.Way materials for scattered and casual renewals Departmentally and for collection scrap in yards for the year 2015-16 in ADEN/EE sub-division. SW-V) BZA Division: GDR-BZA sec.: TFR - Through fitting renewal for a length of 65.45km (without ERC) and 1.46km (with all fittings) on up & Dn lines in ADEN/Bapatla Sub-division. SW-VI) BZA Division: GDR-BZA sec.KCC: Shifiting of crossover S103A &B towards Gudur duly making TRD and S&T alterations in KCC yard in ADEN/BPP sub-division SW-VII) BZA Division: GDR-BZA sec. KCC- Shifting of layout of crossover S121 in KCC yard in ADEN/BPP sub-division. SW-VIII) BZA Division: GDR-BZA sec. KCC - Replacement of Non-standard diamond
crossing at KCC yard Pt No. 144A,B & 145 A,B in KCC yard in ADEN/BPP sub-division. . . .
Sl.No SSR.No Description of Item SW-I Qty.
SW-II Qty.
SW-III Qty.
SW-IV Qty.
SW-V Qty.
SW-VI
Qty.
SW-VII
Qty.
SW-VIII
Qty.
Total Qty.
Rate Rs.
Unit Amount
Rs.
Note:- NS item no.1, 2 and 3 shall not be operated at a time. A minimum gap of 02months shall be maintained
151200 100800 0 0 0 0 0 0 252000 15.01 TRM 3782520
4 NS Hiring of JCB for using jungle clearance /earth removal/ earth cutting/earth deposting along side the track to make-up the cess/railway bank in bridge approaches/ LC approaches/ Points and crossing approaches etc,. with all contractors labour, tools, plant etc., complete and as directed by the Engineer in- charge.
1223 1391 0 0 0 0 0 0 2614 1029.37 Per
Hour 2690773
5 NS Transportation of rails/sleepers/ fittings from any P-Way depot/station/location on S.C. Railway to any depot/station/location of concerned ADEN sub-division including loading, unloading and stacking with all contractor's labour, tools, plant, all lead, lift, consumables, transport, crossing of tracks etc., complete and as directed by the Engineer - in - charge.
a) For lead up to a 100km 0 0 34224 6171 0 0 0 0 40395 8.09 MTKM 326796
b) Lead exceeding 100km but up to 200km
0 0 100898 33528 0 0 0 0 134426 4.65 MTKM 625081
c) Lead exceeding 200km but up to 300km
0 0 113475 445441 0 0 0 0 558916 4.58 MTKM 2559835
d) Lead exceeding 300km but up to 500km
0 0 605832 278438 0 0 0 0 884270 4.17 MTKM 3687406
48
Tender No. 03/Central/2016
Sr.DEN/Central/BZA Signature of Tenderer(s)
Page 48 of 91 BZA Divn., SCR, T.No.03/Central/2016 invited vide Open Tender No.DRM/Works/BZA/03/2016 dt. 05.02.2016, date of opening on 08.03.2016 for the work of SW-I) BZA Division: GDR-BZA sec.Proposed safety related track repairs in SSE/P.Way /CLX, BPP and TEL sections of ADEN/BPP Sub- Division. SW-II) BZA Division: BZA-VSKP sec.Proposed safety related track repairs in SSE/P.Way /Eluru & Nuzvid sections of ADEN/Eluru Sub- Division. SW-III) BZA Division: GDR-BZA sec. Transportation of P.Way materials for scattered and casual renewals Departmentally and for collection scrap in yards for the year 2015-16 in ADEN/BPP sub-division. SW-IV) BZA Division: BZA - VSKP Sec. Transportation of P.Way materials for scattered and casual renewals Departmentally and for collection scrap in yards for the year 2015-16 in ADEN/EE sub-division. SW-V) BZA Division: GDR-BZA sec.: TFR - Through fitting renewal for a length of 65.45km (without ERC) and 1.46km (with all fittings) on up & Dn lines in ADEN/Bapatla Sub-division. SW-VI) BZA Division: GDR-BZA sec.KCC: Shifiting of crossover S103A &B towards Gudur duly making TRD and S&T alterations in KCC yard in ADEN/BPP sub-division SW-VII) BZA Division: GDR-BZA sec. KCC- Shifting of layout of crossover S121 in KCC yard in ADEN/BPP sub-division. SW-VIII) BZA Division: GDR-BZA sec. KCC - Replacement of Non-standard diamond
crossing at KCC yard Pt No. 144A,B & 145 A,B in KCC yard in ADEN/BPP sub-division. . . .
Sl.No SSR.No Description of Item SW-I Qty.
SW-II Qty.
SW-III Qty.
SW-IV Qty.
SW-V Qty.
SW-VI
Qty.
SW-VII
Qty.
SW-VIII
Qty.
Total Qty.
Rate Rs.
Unit Amount
Rs.
Note:1) Depending upon the actual lead involved, payment will be made under the sub-item in which the lead is covered. Variation in the quantity will not apply on individual sub-items quantity but will be considered on gross total quantity of sub-items (a)+(b)+(c)+(d)
(2) If loading is done by Departmentally of class I PSC sleepers at sleeper factory free of cost, then an amount of Rs.80/- per MT will be recovered from the contractor's bills for loading charges.
6 NS Transportation of PSC sleeper fittings such as ERC's, MS/GFN liners, GR pads from any depot/station/location on South Central Railway to any station/location between Gunadala - Pulla stations including loading, unloading and stacking with all contractor's labour, tools, plant, transport, consumables, all lead, lift and crossing of tracks etc., complete and as directed by the Engineer-in-charge.
a) For lead exceeding 50 km and up to 100 km
0 0 0 0 6700 0 0 0 6700 5.43 MTKM 36381
b) For lead exceeding 100 km and up to 300 km
0 0 0 0 71650 0 0 0 71650 4.69 MTKM 336039
c) For lead exceeding 300 km and up to 500 km
0 0 0 0 59700 0 0 0 59700 4.17 MTKM 248949
Note: Depending upon the actual lead involved, payment will be made under the sub-item in which the lead is covered. Variation in the quantity will not apply on individual sub-items quantity but will be considered on gross total qantity of subitems (a) + (b) + (c)
49
Tender No. 03/Central/2016
Sr.DEN/Central/BZA Signature of Tenderer(s)
Page 49 of 91 BZA Divn., SCR, T.No.03/Central/2016 invited vide Open Tender No.DRM/Works/BZA/03/2016 dt. 05.02.2016, date of opening on 08.03.2016 for the work of SW-I) BZA Division: GDR-BZA sec.Proposed safety related track repairs in SSE/P.Way /CLX, BPP and TEL sections of ADEN/BPP Sub- Division. SW-II) BZA Division: BZA-VSKP sec.Proposed safety related track repairs in SSE/P.Way /Eluru & Nuzvid sections of ADEN/Eluru Sub- Division. SW-III) BZA Division: GDR-BZA sec. Transportation of P.Way materials for scattered and casual renewals Departmentally and for collection scrap in yards for the year 2015-16 in ADEN/BPP sub-division. SW-IV) BZA Division: BZA - VSKP Sec. Transportation of P.Way materials for scattered and casual renewals Departmentally and for collection scrap in yards for the year 2015-16 in ADEN/EE sub-division. SW-V) BZA Division: GDR-BZA sec.: TFR - Through fitting renewal for a length of 65.45km (without ERC) and 1.46km (with all fittings) on up & Dn lines in ADEN/Bapatla Sub-division. SW-VI) BZA Division: GDR-BZA sec.KCC: Shifiting of crossover S103A &B towards Gudur duly making TRD and S&T alterations in KCC yard in ADEN/BPP sub-division SW-VII) BZA Division: GDR-BZA sec. KCC- Shifting of layout of crossover S121 in KCC yard in ADEN/BPP sub-division. SW-VIII) BZA Division: GDR-BZA sec. KCC - Replacement of Non-standard diamond
crossing at KCC yard Pt No. 144A,B & 145 A,B in KCC yard in ADEN/BPP sub-division. . . .
Sl.No SSR.No Description of Item SW-I Qty.
SW-II Qty.
SW-III Qty.
SW-IV Qty.
SW-V Qty.
SW-VI
Qty.
SW-VII
Qty.
SW-VIII
Qty.
Total Qty.
Rate Rs.
Unit Amount
Rs.
7 NS
Trucking of new/released 60kg/52kg/90R released rails/points and crossing rails, switches,crossings etc., from various locatioins to the nearest station/road approach/level crossing location with contractor,s rail dollies/rail tongs or any other means up to a lead of 1km including loading, unloading and stacking at nominated locations with all contractor's labour, tools, transport, consumables, all lift, crossing of tracks and stacking at nominated locations etc., complete and as directed by the Engineer-in-charge.
0 0 2009 2976 0 25 10 50 5070 290.15 MT 1471092
8 NS Trucking of PSC/ST/CST-9/Wooden released/new sleepers from various locatioins to the nearest station/road approach/level crossing location with contractor,s rail dollies/rail tongs or any other means including loading, unloading and stacking at nominated locations with all contractor's labour, tools, transport, consumables, all lift, crossing of tracks and stacking at nominated locations etc., complete and as directed by the Engineer-in-charge.
a) Up to an average lead of 1Km 0 0 910 426 0 0 0 0 1336 209.88 MT 280400
b) Up to an average lead of 2 Km
0 0 603 426 0 0 0 0 1029 298.10 MT 306745
9 NS Trucking/ pulling released PSC sleeper fittings from the site of work to the stores of SSE/P.Way/concerned at nearest station/road approach/L.C.location with contractor's rail dollies/rail tongs or any other means up to an average lead of 1 km including loading, unloading and stacking with all contractor's labour, tools, plant, lift, crossing of tracks etc., complete and as directed by the Engineer-in-charge.
0 0 0 0 240 0 0 0 240 121.89 MT 29254
50
Tender No. 03/Central/2016
Sr.DEN/Central/BZA Signature of Tenderer(s)
Page 50 of 91 BZA Divn., SCR, T.No.03/Central/2016 invited vide Open Tender No.DRM/Works/BZA/03/2016 dt. 05.02.2016, date of opening on 08.03.2016 for the work of SW-I) BZA Division: GDR-BZA sec.Proposed safety related track repairs in SSE/P.Way /CLX, BPP and TEL sections of ADEN/BPP Sub- Division. SW-II) BZA Division: BZA-VSKP sec.Proposed safety related track repairs in SSE/P.Way /Eluru & Nuzvid sections of ADEN/Eluru Sub- Division. SW-III) BZA Division: GDR-BZA sec. Transportation of P.Way materials for scattered and casual renewals Departmentally and for collection scrap in yards for the year 2015-16 in ADEN/BPP sub-division. SW-IV) BZA Division: BZA - VSKP Sec. Transportation of P.Way materials for scattered and casual renewals Departmentally and for collection scrap in yards for the year 2015-16 in ADEN/EE sub-division. SW-V) BZA Division: GDR-BZA sec.: TFR - Through fitting renewal for a length of 65.45km (without ERC) and 1.46km (with all fittings) on up & Dn lines in ADEN/Bapatla Sub-division. SW-VI) BZA Division: GDR-BZA sec.KCC: Shifiting of crossover S103A &B towards Gudur duly making TRD and S&T alterations in KCC yard in ADEN/BPP sub-division SW-VII) BZA Division: GDR-BZA sec. KCC- Shifting of layout of crossover S121 in KCC yard in ADEN/BPP sub-division. SW-VIII) BZA Division: GDR-BZA sec. KCC - Replacement of Non-standard diamond
crossing at KCC yard Pt No. 144A,B & 145 A,B in KCC yard in ADEN/BPP sub-division. . . .
Sl.No SSR.No Description of Item SW-I Qty.
SW-II Qty.
SW-III Qty.
SW-IV Qty.
SW-V Qty.
SW-VI
Qty.
SW-VII
Qty.
SW-VIII
Qty.
Total Qty.
Rate Rs.
Unit Amount
Rs.
Note: 1) The contractor is advised to inspect the site and availability of road approaches before quoting the rates. 2) No extra payment will be made for repairs
to service roads or for formation of roads required for transportation or for obtaining right of way if any. Rate quoted shall include all expenses, fees etc.,
10 NS Packing the existing plain track below the bottom of existing sleepers and surrounding with crow bars/ beaters to have two rounds of packing to bring the track to the normal speed including gauging, aligning squaring of sleepers and sectioning of ballast to the required profile with contractor's labour, tools, plant, etc., complete and as directed by the Engineer-in- charge.
i) First round of packing 0 0 0 0 66900 0 0 0 66900 22.95 TRM 1535355
ii) Second round of packing 0 0 0 0 66900 0 0 0 66900 21.41 TRM 1432329
11 NS
Removing BG 1 in 8.5 points and crossings under line block in stipulated time along with PSC sleepers and fastenings carting the same, separating and stacking the released materials item wise and classification wise at nominated locations (with in the yard) as indicated by the Engineer-in-charge and levelling the disturbed track after removal of the points and crossings with contractor's labour, tools, all lead, lift, including crossing of tracks wherever necessary etc., and as directed by the Engineer-in-charge.
0 0 0 0 0 0 1 0 1 17038.77 Set 17039
NOTE:-I. The expression of points and crossings include two rail lengths beyond the heel of crossing on both the main line as well as two rail lengths on loop line and the two rail lengths beyond SRJ, thus totalling to six rail lengths plus the points and crossing portion to cover the entire work.(SRJ to heel of crossing). Rate to cover the entire work.
II. Payment will be made only after stacking the released materials item wise and classification wise.JE/P.Way and ADEN should certify the same.
12 NS
Removing BG 1 in 12 points and crossings under line block in stipulated time along with PSC sleepers and fastenings carting the same, separating and stacking the released materials item wise and classification wise at nominated locations (with in the yard) as indicated by the Engineer-in-charge and levelling the disturbed track after removal of the points and crossings with contractor's labour, tools, all lead, lift, including crossing of tracks wherever necessary etc., and as directed by the Engineer-in-charge
0 0 0 0 0 3 0 4 7 17038.77 Set 119271
51
Tender No. 03/Central/2016
Sr.DEN/Central/BZA Signature of Tenderer(s)
Page 51 of 91 BZA Divn., SCR, T.No.03/Central/2016 invited vide Open Tender No.DRM/Works/BZA/03/2016 dt. 05.02.2016, date of opening on 08.03.2016 for the work of SW-I) BZA Division: GDR-BZA sec.Proposed safety related track repairs in SSE/P.Way /CLX, BPP and TEL sections of ADEN/BPP Sub- Division. SW-II) BZA Division: BZA-VSKP sec.Proposed safety related track repairs in SSE/P.Way /Eluru & Nuzvid sections of ADEN/Eluru Sub- Division. SW-III) BZA Division: GDR-BZA sec. Transportation of P.Way materials for scattered and casual renewals Departmentally and for collection scrap in yards for the year 2015-16 in ADEN/BPP sub-division. SW-IV) BZA Division: BZA - VSKP Sec. Transportation of P.Way materials for scattered and casual renewals Departmentally and for collection scrap in yards for the year 2015-16 in ADEN/EE sub-division. SW-V) BZA Division: GDR-BZA sec.: TFR - Through fitting renewal for a length of 65.45km (without ERC) and 1.46km (with all fittings) on up & Dn lines in ADEN/Bapatla Sub-division. SW-VI) BZA Division: GDR-BZA sec.KCC: Shifiting of crossover S103A &B towards Gudur duly making TRD and S&T alterations in KCC yard in ADEN/BPP sub-division SW-VII) BZA Division: GDR-BZA sec. KCC- Shifting of layout of crossover S121 in KCC yard in ADEN/BPP sub-division. SW-VIII) BZA Division: GDR-BZA sec. KCC - Replacement of Non-standard diamond
crossing at KCC yard Pt No. 144A,B & 145 A,B in KCC yard in ADEN/BPP sub-division. . . .
Sl.No SSR.No Description of Item SW-I Qty.
SW-II Qty.
SW-III Qty.
SW-IV Qty.
SW-V Qty.
SW-VI
Qty.
SW-VII
Qty.
SW-VIII
Qty.
Total Qty.
Rate Rs.
Unit Amount
Rs.
NOTE:-I. The expression of points and crossings include two rail lengths beyond the heel of crossing on both the main line as well as two rail lengths on loop line and the two rail lengths beyond SRJ, thus totalling to six rail lengths plus the points and crossing portion to cover the entire work.(SRJ to heel of crossing). Rate to cover the entire work.
II. Payment will be made only after stacking the released materials item wise and classification wise.JE/P.Way and ADEN should certify the same.
13 NS
Assembling and laying 60kg 1 in 12 prestressed RH/LH turnouts duly respreading Railways 60kg fan shaped PSC crossing sleepers fixing 60kg/52kg tongue rails, stock rails, lead rails & crossings with rubber pads, liners & all fastenings to a neat gauge of 1676mm (from stock rail joint to heel of crossing) under line block with in stipulated time complete set with all P.Way fittings to BG standards by any of the methods as elucidated in para 317(a)(i) & (ii) of IRPWM 2004 & layng 60 Kg PSC sleepers & 52 Kg rails at the 6 rail lengths portion including providing one kutcha packing followed by three additional through packings to specified cushion with stone ballast as per schedule including levelling, gauging, aligning and jointing the ends as per P.Way manual of practice profiling and boxing of the ballast etc. complete including cutting of rails to shorter lengths, drilling holes and chamfering, insertion of glued joints and any other miscellaneous work with in the points and crossing portion (SRJ to heel of crossing) and crossing of tracks wherever necessary with all lead and lift etc. complete and as per specification and as directed by the Engineer-in-charge at site and including leveling the ground to required extant for assembling of points and crossings (Rate covers the entire work).
0 0 0 0 0 3 1 4 8 22785.54 Set 182284
Note:1)The rate for insertion of glued joints, cutting of rails and drilling of holes beyond the points and crossing portion shall be paid separately under relevant items.
2) If packing is not done to the satisfaction of the Engineer-in-charge Rs.1000/- per set for each packing for 1 in 12 and Rs.700/- per set for each packing for 1 in 8.5 will be deducted
3)Only relaying machine with fuel will be supplied by the Railway free of cost and this machine will lift the assembled points and crossings and keep it in position. All other balance works in the schedule will have to be done by the contractor with this own men and materials.
52
Tender No. 03/Central/2016
Sr.DEN/Central/BZA Signature of Tenderer(s)
Page 52 of 91 BZA Divn., SCR, T.No.03/Central/2016 invited vide Open Tender No.DRM/Works/BZA/03/2016 dt. 05.02.2016, date of opening on 08.03.2016 for the work of SW-I) BZA Division: GDR-BZA sec.Proposed safety related track repairs in SSE/P.Way /CLX, BPP and TEL sections of ADEN/BPP Sub- Division. SW-II) BZA Division: BZA-VSKP sec.Proposed safety related track repairs in SSE/P.Way /Eluru & Nuzvid sections of ADEN/Eluru Sub- Division. SW-III) BZA Division: GDR-BZA sec. Transportation of P.Way materials for scattered and casual renewals Departmentally and for collection scrap in yards for the year 2015-16 in ADEN/BPP sub-division. SW-IV) BZA Division: BZA - VSKP Sec. Transportation of P.Way materials for scattered and casual renewals Departmentally and for collection scrap in yards for the year 2015-16 in ADEN/EE sub-division. SW-V) BZA Division: GDR-BZA sec.: TFR - Through fitting renewal for a length of 65.45km (without ERC) and 1.46km (with all fittings) on up & Dn lines in ADEN/Bapatla Sub-division. SW-VI) BZA Division: GDR-BZA sec.KCC: Shifiting of crossover S103A &B towards Gudur duly making TRD and S&T alterations in KCC yard in ADEN/BPP sub-division SW-VII) BZA Division: GDR-BZA sec. KCC- Shifting of layout of crossover S121 in KCC yard in ADEN/BPP sub-division. SW-VIII) BZA Division: GDR-BZA sec. KCC - Replacement of Non-standard diamond
crossing at KCC yard Pt No. 144A,B & 145 A,B in KCC yard in ADEN/BPP sub-division. . . .
Sl.No SSR.No Description of Item SW-I Qty.
SW-II Qty.
SW-III Qty.
SW-IV Qty.
SW-V Qty.
SW-VI
Qty.
SW-VII
Qty.
SW-VIII
Qty.
Total Qty.
Rate Rs.
Unit Amount
Rs.
iv) Rails are to be kept in position to pick up by cranes from released materials in yard of the same depot.
v) Placement of Rubber pads, MS liners and Pandrol clips for panel assembly.
vi) The ER clips and MS Liners are to be dipped in anti corrosive paint/coal tar/bituminous before insertion with contractors anti corrosive paint/ coal tar/bituminous and greasing the inner portion of MCI insert with contractors grease.
14 NS Removing 44.61kg/52kg/60kg rails and fastenings including removal of fish plates with bolts and nuts etc. and stacking neatly at site with all contractor's labour, tools, plant, all lead, lift, crossing of tracks etc. complete and as directed by the Engineer-in-charge.
0 0 0 0 0 200 100 300 600 21.55 TRM 12930
15 NS Laying/Insertion of 52kg /60kg rails and fastenings on existing track sleepers joining with fish plates, bolts and nuts driving MS liners, GFN liners, GR pads and ERCs for PSC sleepers with all contractor's, labour, tools, plant, all lead, lift, crossing of tracks etc., complete and as directed by the Engineer-in-charge.
0 0 0 0 0 200 100 300 600 30.22 TRM 18132
16 NS Removing the existing CST-9/ST/Wooden/PSC sleepers and fastenings from the track with contractor's labour, tools, plant, all lead, lift, crossing of tracks and stacking the released material classification wise and material wise at site of work complete and as directed by the Engineer-in-charge.
0 0 0 0 0 100 120 425 645 51.24
Each sleeper
with fittings
33050
53
Tender No. 03/Central/2016
Sr.DEN/Central/BZA Signature of Tenderer(s)
Page 53 of 91 BZA Divn., SCR, T.No.03/Central/2016 invited vide Open Tender No.DRM/Works/BZA/03/2016 dt. 05.02.2016, date of opening on 08.03.2016 for the work of SW-I) BZA Division: GDR-BZA sec.Proposed safety related track repairs in SSE/P.Way /CLX, BPP and TEL sections of ADEN/BPP Sub- Division. SW-II) BZA Division: BZA-VSKP sec.Proposed safety related track repairs in SSE/P.Way /Eluru & Nuzvid sections of ADEN/Eluru Sub- Division. SW-III) BZA Division: GDR-BZA sec. Transportation of P.Way materials for scattered and casual renewals Departmentally and for collection scrap in yards for the year 2015-16 in ADEN/BPP sub-division. SW-IV) BZA Division: BZA - VSKP Sec. Transportation of P.Way materials for scattered and casual renewals Departmentally and for collection scrap in yards for the year 2015-16 in ADEN/EE sub-division. SW-V) BZA Division: GDR-BZA sec.: TFR - Through fitting renewal for a length of 65.45km (without ERC) and 1.46km (with all fittings) on up & Dn lines in ADEN/Bapatla Sub-division. SW-VI) BZA Division: GDR-BZA sec.KCC: Shifiting of crossover S103A &B towards Gudur duly making TRD and S&T alterations in KCC yard in ADEN/BPP sub-division SW-VII) BZA Division: GDR-BZA sec. KCC- Shifting of layout of crossover S121 in KCC yard in ADEN/BPP sub-division. SW-VIII) BZA Division: GDR-BZA sec. KCC - Replacement of Non-standard diamond
crossing at KCC yard Pt No. 144A,B & 145 A,B in KCC yard in ADEN/BPP sub-division. . . .
Sl.No SSR.No Description of Item SW-I Qty.
SW-II Qty.
SW-III Qty.
SW-IV Qty.
SW-V Qty.
SW-VI
Qty.
SW-VII
Qty.
SW-VIII
Qty.
Total Qty.
Rate Rs.
Unit Amount
Rs.
17 NS Laying of PSC sleepers and fastenings in position including gauging, aligning, kutcha packing and bringing the track to run trains at a speed of 20kmph with beaters to ensure safety of trains at a restricted speed and placing the rubber pads, composite liners in position, fixing pandrol clips etc., complete and as directed by the Engineer-in-charge.
0 0 0 0 0 100 120 425 645 130.97
Each sleeper
with fittings
84476
18 NS Making LC check rail out of 52/60kg unserviceable rails trucked out from a maxiumu lead of 1km by cutting the flange and web where ever required to suit the elastic rail clips so as to get approapriate check rail clearance with all contractor's,materials,labour, gas, tools, plant, lead, lift, crossing of track etc., complete and as derected by the Engineer-in-charge
0 0 0 0 0 300 0 0 300 108.75 RM 32625
19 NS Lifing the exisiting plain track/points and crossings track by 20cm with initial packing after every stage of lift (i.e in three stages not more than 75mm in each lift) with contractors labour, tools,plant, all lead,lift incluidng gauging, squaring of sleepers, aligning, crossing of tracks etc., complete and as directed by the Engineer - in - charge.
Plain track 0 0 0 0 0 200 100 300 600 108.14 TRM 64884
1 in 12 points and crossing track 0 0 0 0 0 3 1 4 8 6655.53 Set 53244
20 NS Packing the existing plain track/Points and crossings below the bottom of existing sleepers and surrounding with crow bars/ beaters to have two rounds of packing to bring the track to the normal speed including gauging, aligning squaring of sleepers and sectioning of ballast to the required profile with contractor's labour, tools, plant, etc., complete and as directed by the Engineer-in- charge.
a) Plain track:
0
i) First round packing 0 0 0 0 0 200 100 300 600 22.95 TRM 13770
ii) Second round packing 0 0 0 0 0 200 100 300 600 21.41 TRM 12846
54
Tender No. 03/Central/2016
Sr.DEN/Central/BZA Signature of Tenderer(s)
Page 54 of 91 BZA Divn., SCR, T.No.03/Central/2016 invited vide Open Tender No.DRM/Works/BZA/03/2016 dt. 05.02.2016, date of opening on 08.03.2016 for the work of SW-I) BZA Division: GDR-BZA sec.Proposed safety related track repairs in SSE/P.Way /CLX, BPP and TEL sections of ADEN/BPP Sub- Division. SW-II) BZA Division: BZA-VSKP sec.Proposed safety related track repairs in SSE/P.Way /Eluru & Nuzvid sections of ADEN/Eluru Sub- Division. SW-III) BZA Division: GDR-BZA sec. Transportation of P.Way materials for scattered and casual renewals Departmentally and for collection scrap in yards for the year 2015-16 in ADEN/BPP sub-division. SW-IV) BZA Division: BZA - VSKP Sec. Transportation of P.Way materials for scattered and casual renewals Departmentally and for collection scrap in yards for the year 2015-16 in ADEN/EE sub-division. SW-V) BZA Division: GDR-BZA sec.: TFR - Through fitting renewal for a length of 65.45km (without ERC) and 1.46km (with all fittings) on up & Dn lines in ADEN/Bapatla Sub-division. SW-VI) BZA Division: GDR-BZA sec.KCC: Shifiting of crossover S103A &B towards Gudur duly making TRD and S&T alterations in KCC yard in ADEN/BPP sub-division SW-VII) BZA Division: GDR-BZA sec. KCC- Shifting of layout of crossover S121 in KCC yard in ADEN/BPP sub-division. SW-VIII) BZA Division: GDR-BZA sec. KCC - Replacement of Non-standard diamond
crossing at KCC yard Pt No. 144A,B & 145 A,B in KCC yard in ADEN/BPP sub-division. . . .
Sl.No SSR.No Description of Item SW-I Qty.
SW-II Qty.
SW-III Qty.
SW-IV Qty.
SW-V Qty.
SW-VI
Qty.
SW-VII
Qty.
SW-VIII
Qty.
Total Qty.
Rate Rs.
Unit Amount
Rs.
b) 1 in 12 Points and crossings
i) First round of packing 0 0 0 0 0 3 1 4 8 2242.30 Set 17938
ii) Second round of packing 0 0 0 0 0 3 1 4 8 1274.62 Set 10197
Note : Rails shall be cut true to vertical upto bottom of rail. No payment will be made if rails are half cut and bent
21 NS Cutting 52kg/60kg rails with hacksaw blade/rail cutting machine true to vertical with contractors rail cutting machine hacksaw blade complete and as directed by the Engineer-in-charge. (Rails shall be cut true to vertical upto the bottom of rail. No payment will be made if rails are half cut and bent.)
0 0 0 0 0 50 50 120 220 77.50 Each Cut
17050
22 NS Drilling fish bolt holes of 17mm to 32 mm dia for 52 kg/60kg.rails true to vertical with contractor's drill bit/drilling machine, labour, tools, plant, all lead, lift etc., complete and as directed by the Engineer-in-charge (Holes to be drilled at exact locations
0 0 0 0 0 100 100 240 440 38.93
Each hole
17129
23 NS Drilling RE Bond holes with drill bit on 52kg/60kg rails at predetermined specified locations with contractor's men and material, tools, plant, equipment including all lead, lift, tackles etc., complete and as directed by the Engineer-in-charge.
0 0 0 0 0 50 20 50 120 18.32
Each hole
2198
24 NS
Trucking of PSC released/new sleepers from at various locations to the site of work and released sleepers from site of work to the stores of SSE/P-way/concerned at nearest station/manned L.C. location/road approach up to a lead of 1km with contractor's rail dollies/rail tongs or any other means with all contractor's labour, tools, transport, consumables, all lift, crossing of tracks and stacking at nominated locations etc., complete and as directed by the Engineer-in-charge.
0 0 0 0 0 100 50 200 350 41.51
Each sleeper
14529
55
Tender No. 03/Central/2016
Sr.DEN/Central/BZA Signature of Tenderer(s)
Page 55 of 91 BZA Divn., SCR, T.No.03/Central/2016 invited vide Open Tender No.DRM/Works/BZA/03/2016 dt. 05.02.2016, date of opening on 08.03.2016 for the work of SW-I) BZA Division: GDR-BZA sec.Proposed safety related track repairs in SSE/P.Way /CLX, BPP and TEL sections of ADEN/BPP Sub- Division. SW-II) BZA Division: BZA-VSKP sec.Proposed safety related track repairs in SSE/P.Way /Eluru & Nuzvid sections of ADEN/Eluru Sub- Division. SW-III) BZA Division: GDR-BZA sec. Transportation of P.Way materials for scattered and casual renewals Departmentally and for collection scrap in yards for the year 2015-16 in ADEN/BPP sub-division. SW-IV) BZA Division: BZA - VSKP Sec. Transportation of P.Way materials for scattered and casual renewals Departmentally and for collection scrap in yards for the year 2015-16 in ADEN/EE sub-division. SW-V) BZA Division: GDR-BZA sec.: TFR - Through fitting renewal for a length of 65.45km (without ERC) and 1.46km (with all fittings) on up & Dn lines in ADEN/Bapatla Sub-division. SW-VI) BZA Division: GDR-BZA sec.KCC: Shifiting of crossover S103A &B towards Gudur duly making TRD and S&T alterations in KCC yard in ADEN/BPP sub-division SW-VII) BZA Division: GDR-BZA sec. KCC- Shifting of layout of crossover S121 in KCC yard in ADEN/BPP sub-division. SW-VIII) BZA Division: GDR-BZA sec. KCC - Replacement of Non-standard diamond
crossing at KCC yard Pt No. 144A,B & 145 A,B in KCC yard in ADEN/BPP sub-division. . . .
Sl.No SSR.No Description of Item SW-I Qty.
SW-II Qty.
SW-III Qty.
SW-IV Qty.
SW-V Qty.
SW-VI
Qty.
SW-VII
Qty.
SW-VIII
Qty.
Total Qty.
Rate Rs.
Unit Amount
Rs.
25 NS Transportation of Rails, PSC sleepers,glued joint rails, fittings etc., from any depot/station/location of South Central Railway to PQRS depot/site of work including loading, unloading and stacking with all contractor's labour, tools, plant, transport, consumables, all lead, lift, crossing of tracks etc., complete and as directed by the Engineer - in -charge.
a) For lead exceeding 50 km but upto 100 km
0 0 0 0 0 2000 1000 4000 7000 7.80 MTKM 54600
b) For lead exceeding 100 km but upto 300 km
0 0 0 0 0 15000 10000 30000 55000 5.91 MTKM 325050
c) For lead exceeding 300 km but upto 500 km
0 0 0 0 0 30000 20000 60000 110000 5.25 MTKM 577500
Note :1) Depending upon the actual lead involved, payment will be made under the sub-item in which the lead is covered. Variation in the quantity will not apply on individual sub-items quantity but will be considered on gross total quantity of sub items (a)+ (b) +(c)
26 NS
Application of grease around the liner to block entry of toilet dropping for preventing corrosion at liner contact area including removal of ERCs (excluding ceased ERCs) and cleaning liner contact area, liner and ERC using contractor’s wire brushes, scrappers, emery papers etc. and cleaning the insert hole with round wire brush and application of Railways grease inside insert hole and to the full ERC and re-fixing of ERCs with liners including filling of corrosion pits at rail foot in and around the liner contact area and application of grease to the eye of insert on both sides of insert holes with Railways grease with all contractors labour, tools, plant, all lead and lift, crossing of track etc. complete and as directed by Engineer-in-Charge.
0 0 0 0 0 2000 500 5000 7500 2.66
Per liner
contact area
19950
56
Tender No. 03/Central/2016
Sr.DEN/Central/BZA Signature of Tenderer(s)
Page 56 of 91 BZA Divn., SCR, T.No.03/Central/2016 invited vide Open Tender No.DRM/Works/BZA/03/2016 dt. 05.02.2016, date of opening on 08.03.2016 for the work of SW-I) BZA Division: GDR-BZA sec.Proposed safety related track repairs in SSE/P.Way /CLX, BPP and TEL sections of ADEN/BPP Sub- Division. SW-II) BZA Division: BZA-VSKP sec.Proposed safety related track repairs in SSE/P.Way /Eluru & Nuzvid sections of ADEN/Eluru Sub- Division. SW-III) BZA Division: GDR-BZA sec. Transportation of P.Way materials for scattered and casual renewals Departmentally and for collection scrap in yards for the year 2015-16 in ADEN/BPP sub-division. SW-IV) BZA Division: BZA - VSKP Sec. Transportation of P.Way materials for scattered and casual renewals Departmentally and for collection scrap in yards for the year 2015-16 in ADEN/EE sub-division. SW-V) BZA Division: GDR-BZA sec.: TFR - Through fitting renewal for a length of 65.45km (without ERC) and 1.46km (with all fittings) on up & Dn lines in ADEN/Bapatla Sub-division. SW-VI) BZA Division: GDR-BZA sec.KCC: Shifiting of crossover S103A &B towards Gudur duly making TRD and S&T alterations in KCC yard in ADEN/BPP sub-division SW-VII) BZA Division: GDR-BZA sec. KCC- Shifting of layout of crossover S121 in KCC yard in ADEN/BPP sub-division. SW-VIII) BZA Division: GDR-BZA sec. KCC - Replacement of Non-standard diamond
crossing at KCC yard Pt No. 144A,B & 145 A,B in KCC yard in ADEN/BPP sub-division. . . .
Sl.No SSR.No Description of Item SW-I Qty.
SW-II Qty.
SW-III Qty.
SW-IV Qty.
SW-V Qty.
SW-VI
Qty.
SW-VII
Qty.
SW-VIII
Qty.
Total Qty.
Rate Rs.
Unit Amount
Rs.
27 NS
Removing and screening of ballast (Deep screening) in plain track/points and crossing track by way of removing the entire stone ballast including muck lying in the track, below and between sleepers and on the shoulders up to formation level and providing clean ballast cushion of 30 Cm by manual/machine and lifting the track from 10 to 15 Cm ( in stages of 50 mm/75 mm each) duly supporting the track temporarily with wooden blocks( supplied by the Railways free of cost at the stores of SE/P.Way/ H.Qrs) for passing the trains at a restricted speed of non-stop of 20 Kmph while the work is in progress and putting back the screened clean ballast on the track, shifting of sleepers to correct spacing, removal and refixing of fittings wherever necessary of all the sleepers, squaring the sleepers including one kutcha packing and taking care to see that required cross levels are maintained, aligning, gauging, lifting, levelling, surfacing, profiling, boxing of ballast to the standard section, dressing, lowering of cess to deep screened depth with all contractor's labour, tools, all lead, lift, crossing of tracks etc., complete and as directed by the Engineer - in - charge.
Note: 1) The expression of points and crossings including two rail lengths beyond heel of crossing on both the main line as well as two rail lengths on loop line and two rail lengths beyond SRJ, thus totalling to 6 rail lengths plus points and crossing portion (SRJ to heel of crossing). Rate to cover entire above work.
2 ) The muck removed during screening shall be lead sufficiently away from the track/ cutting as directed by the Engineer - in - charge. In case of bank, the muck shall be neatly spread on cess/ bank for widening of cess/ making up of cess as per bank profile.
3) The work deep screening shall be operated in full or part based on the direction of the Railways. Non-operation of item in full or part shall not be entitle the contractor for any claim/compensation.
4) The screening of ballast shall be done using inclined screens made of square mesh of specified size and using of wire baskets shall not be permitted.
5) The entire stone ballast means ballast available on the track between the two toe points on either side of the track and ballast from its top level to 30 Cm below the sleeper level.
6) Boxing is to be done after full ballast is dumped.
7) Proportionate payment will be made if the specified cushion of 30 Cm is not provided after deep screening and lifting.
a) Plain track 0 0 0 0 0 0 200 0 200 201.29 TRM 40258
b) 1 in 12 points and crossing track
0 0 0 0 0 0 1 0 1 5590.70 Set 5591
57
Tender No. 03/Central/2016
Sr.DEN/Central/BZA Signature of Tenderer(s)
Page 57 of 91 BZA Divn., SCR, T.No.03/Central/2016 invited vide Open Tender No.DRM/Works/BZA/03/2016 dt. 05.02.2016, date of opening on 08.03.2016 for the work of SW-I) BZA Division: GDR-BZA sec.Proposed safety related track repairs in SSE/P.Way /CLX, BPP and TEL sections of ADEN/BPP Sub- Division. SW-II) BZA Division: BZA-VSKP sec.Proposed safety related track repairs in SSE/P.Way /Eluru & Nuzvid sections of ADEN/Eluru Sub- Division. SW-III) BZA Division: GDR-BZA sec. Transportation of P.Way materials for scattered and casual renewals Departmentally and for collection scrap in yards for the year 2015-16 in ADEN/BPP sub-division. SW-IV) BZA Division: BZA - VSKP Sec. Transportation of P.Way materials for scattered and casual renewals Departmentally and for collection scrap in yards for the year 2015-16 in ADEN/EE sub-division. SW-V) BZA Division: GDR-BZA sec.: TFR - Through fitting renewal for a length of 65.45km (without ERC) and 1.46km (with all fittings) on up & Dn lines in ADEN/Bapatla Sub-division. SW-VI) BZA Division: GDR-BZA sec.KCC: Shifiting of crossover S103A &B towards Gudur duly making TRD and S&T alterations in KCC yard in ADEN/BPP sub-division SW-VII) BZA Division: GDR-BZA sec. KCC- Shifting of layout of crossover S121 in KCC yard in ADEN/BPP sub-division. SW-VIII) BZA Division: GDR-BZA sec. KCC - Replacement of Non-standard diamond
crossing at KCC yard Pt No. 144A,B & 145 A,B in KCC yard in ADEN/BPP sub-division. . . .
Sl.No SSR.No Description of Item SW-I Qty.
SW-II Qty.
SW-III Qty.
SW-IV Qty.
SW-V Qty.
SW-VI
Qty.
SW-VII
Qty.
SW-VIII
Qty.
Total Qty.
Rate Rs.
Unit Amount
Rs.
28 NS
Supply and filling 50kg sizw empty cemnet polythene bags with railway ballast/Morrum/ Earth etc, placing the filled bags on the high bank/bridge approaches/ Nominated places etc.umping and spreading at nominated locations to profile under block period with all contracores labour, tools, plant, empty polythene 50kg cement bags, loading, unloading, filling spreading including all lead/ lift etc., complete and as directed by the engineer at site including Xing of track where necessary
0 0 0 0 0 8000 400 4000 12400 6.20 Bag 76880
29 NS
Painting of new rails 60 kg by brush after surface preparation with Contractor's paint anti-corrosive bituminous black to IS 9862- 1981 two coats to a thickness of 100 microns per each coat on both sides of new rails including painting of bottom of the rail but excluding gauge face and rail top with all contractor's labour, brush, tools, paint, transportation with all lead and lift including surface preparation and painting of rails as per the procedure given in procedural order for painting of rails circulated vide Head Quarters letter No. W.501/17/Vol/VII dt 8.4.04 and as specified including crossing of tracks, handling of rails and as directed by the Engineer-in-charge. NOTE:- Incase of 52 kg rails 10.59% of rate to be deducted from accepted rate for one RRM.
0 0 0 0 0 400 50 700 1150 48.62 RRM 55913
(Items Twenty nine only) Schedule - 'B' Total 37075880
PERCENTAGE RATE TO BE QUOTED
IN FIGURES
PERCENTAGE RATE TO BE QUOTED
IN WORDS
58
Tender No. 03/Central/2016
Sr.DEN/Central/BZA Signature of Tenderer(s)
Page 58 of 91 BZA Divn., SCR, T.No.03/Central/2016 invited vide Open Tender No.DRM/Works/BZA/03/2016 dt. 05.02.2016, date of opening on 08.03.2016 for the work of SW-I) BZA Division: GDR-BZA sec.Proposed safety related track repairs in SSE/P.Way /CLX, BPP and TEL sections of ADEN/BPP Sub- Division. SW-II) BZA Division: BZA-VSKP sec.Proposed safety related track repairs in SSE/P.Way /Eluru & Nuzvid sections of ADEN/Eluru Sub- Division. SW-III) BZA Division: GDR-BZA sec. Transportation of P.Way materials for scattered and casual renewals Departmentally and for collection scrap in yards for the year 2015-16 in ADEN/BPP sub-division. SW-IV) BZA Division: BZA - VSKP Sec. Transportation of P.Way materials for scattered and casual renewals Departmentally and for collection scrap in yards for the year 2015-16 in ADEN/EE sub-division. SW-V) BZA Division: GDR-BZA sec.: TFR - Through fitting renewal for a length of 65.45km (without ERC) and 1.46km (with all fittings) on up & Dn lines in ADEN/Bapatla Sub-division. SW-VI) BZA Division: GDR-BZA sec.KCC: Shifiting of crossover S103A &B towards Gudur duly making TRD and S&T alterations in KCC yard in ADEN/BPP sub-division SW-VII) BZA Division: GDR-BZA sec. KCC- Shifting of layout of crossover S121 in KCC yard in ADEN/BPP sub-division. SW-VIII) BZA Division: GDR-BZA sec. KCC - Replacement of Non-standard diamond
crossing at KCC yard Pt No. 144A,B & 145 A,B in KCC yard in ADEN/BPP sub-division. . . .
SCHEDULE - 'B1' List of items of works that are not covered by P-way SSR 2004. of S.C. Railway, Vijayawada division
Sl.No SSR.No Description of Item SW-I Qty.
SW-II Qty.
SW-III Qty.
SW-IV Qty.
SW-V Qty.
SW-VI
Qty.
SW-VII
Qty.
SW-VIII
Qty.
Total Qty.
Rate Rs.
Unit Amount
Rs.
1 NS Removing the existing elastic rail clips, MS/GFN liners, GR pads from the existing sleepers and providing with new ERCs, MS / GFN liners and GR pads including cleaning of MCI insert holes and greasing the same with Railways grease, gauging with all contractor's labour, tools, all lead, lift etc., complete and as directed by the Engineer-in-charge.
0 0 0 0 111054 0 0 0 111054 8.17
Each sleeper
907311
Note: 1. While removing ER Clips greasing, heating with blow lamps/gas to be done if necessary without breaking the PSC sleepers at the contractor's cost.
No extra payment will be made for the same. Grease will be given at SSE/P-way stores.
2 NS
Destressing of LWR with 60 kg/52 kg/90 R rails on PSC/CST-9/ST sleepers with/without using rail tensor, duly converting into 500 M/1000 M long panel by introducing closer rail including transportation of closure rail from the available spot with an average lead of 1000 M removing ERC's without damaging the MCI inserts and PSC sleepers duly applying contractor's rust removing solution/chemical wherever ERCs are jammed and removing liners from the running track and keeping it separately and lifting the rail at every 15th sleeper on straight track and as per para No.5.7.2(v) of manual of instructions on Long Welded Rails on curved track and providing railways rollers in the given traffic block and tapping the rail with wooden mallets from the centre of the panel towards ends as per provisions of Para 5.7 and Annexure-VIII of Manual of Instructions on Long Welded Rails and providing rail fastenings including replacement of wornout fittings, duly greasing all fittings with railway grease and adjusting SEJ gaps, providing standard cut rails with all contractor's men, material and tools including all lead and lift and as directed by the Engineer-in-charge.
0 0 0 0 66900 0 0 0 66900 15.32 TRM 1024908
Special Conditions
1. Contractor shall adhere to the provisions of para 5.7 of Annexure-VIII of Manual of Instructions on Long Welded Rails.
2. Contractor should engage sufficient labour to execute all the preliminary works well in advance before taking up the traffic block and to execute the work within the traffic block.
59
Tender No. 03/Central/2016
Sr.DEN/Central/BZA Signature of Tenderer(s)
Page 59 of 91 BZA Divn., SCR, T.No.03/Central/2016 invited vide Open Tender No.DRM/Works/BZA/03/2016 dt. 05.02.2016, date of opening on 08.03.2016 for the work of SW-I) BZA Division: GDR-BZA sec.Proposed safety related track repairs in SSE/P.Way /CLX, BPP and TEL sections of ADEN/BPP Sub- Division. SW-II) BZA Division: BZA-VSKP sec.Proposed safety related track repairs in SSE/P.Way /Eluru & Nuzvid sections of ADEN/Eluru Sub- Division. SW-III) BZA Division: GDR-BZA sec. Transportation of P.Way materials for scattered and casual renewals Departmentally and for collection scrap in yards for the year 2015-16 in ADEN/BPP sub-division. SW-IV) BZA Division: BZA - VSKP Sec. Transportation of P.Way materials for scattered and casual renewals Departmentally and for collection scrap in yards for the year 2015-16 in ADEN/EE sub-division. SW-V) BZA Division: GDR-BZA sec.: TFR - Through fitting renewal for a length of 65.45km (without ERC) and 1.46km (with all fittings) on up & Dn lines in ADEN/Bapatla Sub-division. SW-VI) BZA Division: GDR-BZA sec.KCC: Shifiting of crossover S103A &B towards Gudur duly making TRD and S&T alterations in KCC yard in ADEN/BPP sub-division SW-VII) BZA Division: GDR-BZA sec. KCC- Shifting of layout of crossover S121 in KCC yard in ADEN/BPP sub-division. SW-VIII) BZA Division: GDR-BZA sec. KCC - Replacement of Non-standard diamond
crossing at KCC yard Pt No. 144A,B & 145 A,B in KCC yard in ADEN/BPP sub-division. . . .
SCHEDULE - 'B1' List of items of works that are not covered by P-way SSR 2004. of S.C. Railway, Vijayawada division
Sl.No SSR.No Description of Item SW-I Qty.
SW-II Qty.
SW-III Qty.
SW-IV Qty.
SW-V Qty.
SW-VI
Qty.
SW-VII
Qty.
SW-VIII
Qty.
Total Qty.
Rate Rs.
Unit Amount
Rs.
3. Safety of track should be ensured and for any unusual occurrence, contractor is responsible.
4. Destressing operation should be done at destressing temperature range only.
5. Track gauge shall be ensured by the contractor/representative of the contractor before passing the train.
6. The contractor should ensure safety of the labour/representative at the work spot particularly on the double line track and sufficient look out men should be engaged.
7. Whenever destressing is planned with the rail tensor, tensors along with operator will be supplied by the Railway but necessary unskilled labour should be supplied by the contractor.
8. Whenever weld collars are obstructing the movement of rails, at the time of destressing, necessary re-spacing of adjacent sleepers should be done by the contractor.
9. Whenever LC gates exists check rails should be removed and proper clearance of ballast is to be done by the contractor for free movement of rails during destressing and re-fix the check rails and close the LC after destressing.
(Item two only) Schedule - 'B1' Total 1932219
PERCENTAGE RATE TO BE QUOTED
IN FIGURES
PERCENTAGE RATE TO BE QUOTED
IN WORDS
60
Tender No. 03/Central/2016
Sr.DEN/Central/BZA Signature of Tenderer(s)
Page 60 of 91 BZA Divn., SCR, T.No.03/Central/2016 invited vide Open Tender No.DRM/Works/BZA/03/2016 dt. 05.02.2016, date of opening on 08.03.2016 for the work of SW-I) BZA Division: GDR-BZA sec.Proposed safety related track repairs in SSE/P.Way /CLX, BPP and TEL sections of ADEN/BPP Sub- Division. SW-II) BZA Division: BZA-VSKP sec.Proposed safety related track repairs in SSE/P.Way /Eluru & Nuzvid sections of ADEN/Eluru Sub- Division. SW-III) BZA Division: GDR-BZA sec. Transportation of P.Way materials for scattered and casual renewals Departmentally and for collection scrap in yards for the year 2015-16 in ADEN/BPP sub-division. SW-IV) BZA Division: BZA - VSKP Sec. Transportation of P.Way materials for scattered and casual renewals Departmentally and for collection scrap in yards for the year 2015-16 in ADEN/EE sub-division. SW-V) BZA Division: GDR-BZA sec.: TFR - Through fitting renewal for a length of 65.45km (without ERC) and 1.46km (with all fittings) on up & Dn lines in ADEN/Bapatla Sub-division. SW-VI) BZA Division: GDR-BZA sec.KCC: Shifiting of crossover S103A &B towards Gudur duly making TRD and S&T alterations in KCC yard in ADEN/BPP sub-division SW-VII) BZA Division: GDR-BZA sec. KCC- Shifting of layout of crossover S121 in KCC yard in ADEN/BPP sub-division. SW-VIII) BZA Division: GDR-BZA sec. KCC - Replacement of Non-standard diamond
crossing at KCC yard Pt No. 144A,B & 145 A,B in KCC yard in ADEN/BPP sub-division. . . .
SCHEDULE - 'B2' List of items of works that are not covered by P-way SSR 2004. of S.C. Railway, Vijayawada division
Sl.No SSR.No Description of Item SW-I Qty.
SW-II Qty.
SW-III Qty.
SW-IV Qty.
SW-V Qty.
SW-VI
Qty.
SW-VII
Qty.
SW-VIII
Qty.
Total Qty.
Rate Rs.
Unit Amount
Rs.
1 NS
Picking of rags such as plastic cups, plastic water bottles, water sachets and any other materials thrown by the traveling public etc. on the railway track and in the mid section including in between the tracks, embankment slopes, cess and one mete from the toe of the embankment if required on either side of the up and down lines / full width of cuttings including their slopes duly following all safety precautions of their work men and disposal of rags away from the railway boundary complete with all the labour, tools, materials, all lead, and lift and including crossing of trackscomplete and as directed by the Engineer- in-charge.
0 0 0 0 9000000 0 0 0 9000000 17.99 100sqm 1619100
(Item one only) Schedule - 'B2' Total 1619100
PERCENTAGE RATE TO BE QUOTED
IN FIGURES
PERCENTAGE RATE TO BE QUOTED
IN WORDS
61
Tender No. 03/Central/2016
Sr.DEN/Central/BZA Signature of Tenderer(s)
Page 61 of 91 BZA Divn., SCR, T.No.03/Central/2016 invited vide Open Tender No.DRM/Works/BZA/03/2016 dt. 05.02.2016, date of opening on 08.03.2016 for the work of SW-I) BZA Division: GDR-BZA sec.Proposed safety related track repairs in SSE/P.Way /CLX, BPP and TEL sections of ADEN/BPP Sub- Division. SW-II) BZA Division: BZA-VSKP sec.Proposed safety related track repairs in SSE/P.Way /Eluru & Nuzvid sections of ADEN/Eluru Sub- Division. SW-III) BZA Division: GDR-BZA sec. Transportation of P.Way materials for scattered and casual renewals Departmentally and for collection scrap in yards for the year 2015-16 in ADEN/BPP sub-division. SW-IV) BZA Division: BZA - VSKP Sec. Transportation of P.Way materials for scattered and casual renewals Departmentally and for collection scrap in yards for the year 2015-16 in ADEN/EE sub-division. SW-V) BZA Division: GDR-BZA sec.: TFR - Through fitting renewal for a length of 65.45km (without ERC) and 1.46km (with all fittings) on up & Dn lines in ADEN/Bapatla Sub-division. SW-VI) BZA Division: GDR-BZA sec.KCC: Shifiting of crossover S103A &B towards Gudur duly making TRD and S&T alterations in KCC yard in ADEN/BPP sub-division SW-VII) BZA Division: GDR-BZA sec. KCC- Shifting of layout of crossover S121 in KCC yard in ADEN/BPP sub-division. SW-VIII) BZA Division: GDR-BZA sec. KCC - Replacement of Non-standard diamond
crossing at KCC yard Pt No. 144A,B & 145 A,B in KCC yard in ADEN/BPP sub-division. . . .
SCHEDULE - 'B3' List of items of works that are not covered by P-way SSR 2004. of S.C. Railway, Vijayawada division
Sl.No SSR.No Description of Item SW-I Qty.
SW-II Qty.
SW-III Qty.
SW-IV Qty.
SW-V Qty.
SW-VI
Qty.
SW-VII
Qty.
SW-VIII
Qty.
Total Qty.
Rate Rs.
Unit Amount
Rs.
1 NS
Galvanisation of Railway's M.S. liners by hot dip process with Zinc coating and the mass of Zinc coating shall not be less than 705g/sqm and the galvanisation thickness shall not be less than 100 microns including necessary surface preperation as per clause 4 of IS. 2629-1966 and Galvanisation shall be done as per IS. 2629-1966 and IS. 4759-1984 and as per enclosed specifications in Annexure' A' including transportation of M.S. liners/ERCs from the stores of SSE/P.Way/concerned to galvanisation plant and from galvanisation plant to the stores of SSE/P.Way/concerned, including loading, unloading and stacking etc. with all contractor's labour, material, tools, plant, all lead, lift and crossing of tracks etc. complete and as directed by the Engineer- in - charge.
0 0 0 0 117 0 0 0 117 27626.93 MT 3232351
(Item one only) Schedule - 'B3' Total 3232351
PERCENTAGE RATE TO BE QUOTED
IN FIGURES
PERCENTAGE RATE TO BE QUOTED
IN WORDS
62
Tender No. 03/Central/2016
Sr.DEN/Central/BZA Signature of Tenderer(s)
Page 62 of 91 BZA Divn., SCR, T.No.03/Central/2016 invited vide Open Tender No.DRM/Works/BZA/03/2016 dt. 05.02.2016, date of opening on 08.03.2016 for the work of SW-I) BZA Division: GDR-BZA sec.Proposed safety related track repairs in SSE/P.Way /CLX, BPP and TEL sections of ADEN/BPP Sub- Division. SW-II) BZA Division: BZA-VSKP sec.Proposed safety related track repairs in SSE/P.Way /Eluru & Nuzvid sections of ADEN/Eluru Sub- Division. SW-III) BZA Division: GDR-BZA sec. Transportation of P.Way materials for scattered and casual renewals Departmentally and for collection scrap in yards for the year 2015-16 in ADEN/BPP sub-division. SW-IV) BZA Division: BZA - VSKP Sec. Transportation of P.Way materials for scattered and casual renewals Departmentally and for collection scrap in yards for the year 2015-16 in ADEN/EE sub-division. SW-V) BZA Division: GDR-BZA sec.: TFR - Through fitting renewal for a length of 65.45km (without ERC) and 1.46km (with all fittings) on up & Dn lines in ADEN/Bapatla Sub-division. SW-VI) BZA Division: GDR-BZA sec.KCC: Shifiting of crossover S103A &B towards Gudur duly making TRD and S&T alterations in KCC yard in ADEN/BPP sub-division SW-VII) BZA Division: GDR-BZA sec. KCC- Shifting of layout of crossover S121 in KCC yard in ADEN/BPP sub-division. SW-VIII) BZA Division: GDR-BZA sec. KCC - Replacement of
Non-standard diamond crossing at KCC yard Pt No. 144A,B & 145 A,B in KCC yard in ADEN/BPP sub-division. . . .
CONDITIONS
1. The tenderers are required to quote uniform percentage rate above/below/at par on the
items of the Schedule „A,A1,B,B1,B2 & B3 separately both in figures and words. If there
is any variation in between the uniform percentage rate quoted in words and figures, the
uniform percentage rate quoted in words will be taken as correct and final.
2. The quantities shown in the tender schedule are approximate and shall be operated in full
or part at the discretion of the Engineer in charge.
3. Payment will be made based on the actual quantities operated/executed.
4. The Railway administration will not be responsible for the safety of contractor‟s Labour
engaged for this work.
5. The contractor shall make his own arrangements for men, materials, tools, consumables
etc., required for the work at his own cost and shall be responsible for safe working of
trains at a restricted speed of 20 Kmph on work spot.
6. In the event of any accident at the work site and it is established during the departmental
enquiry by the Railways that the accident occurred wholly or partly due to any act of
tentamounting to negligence on the part of the Contractor or his labour in not adhering to
the instructions of the Engineer-in-charge. The Contractor shall himself be liable for
damage and also legal prosecution if loss of life is involved.
7. The contractor is primarily responsible for safety of traffic and also that of his staff
working on track. No compensation what so ever towards damage to men, material of the
contractor will be paid by railways it is essential that adequate safety measures are taken
for safety of the trains as well as the work force.
8. The look out and whistle caution orders shall be issued to the trains and speed restrictions
imposed where considered necessary. Suitable flagmen/detonators shall be provided
where necessary for protection of trains.
9. The unloaded ballast/rails/sleepers/other P.Way materials after unloading along track
should be kept clear off moving dimensions and stacked as per the specified heights and
distance from the running track.
63
Tender No. 03/Central/2016
Sr.DEN/Central/BZA Signature of Tenderer(s)
Page 63 of 91 BZA Divn., SCR, T.No.03/Central/2016 invited vide Open Tender No.DRM/Works/BZA/03/2016 dt. 05.02.2016, date of opening on 08.03.2016 for the work of SW-I) BZA Division: GDR-BZA sec.Proposed safety related track repairs in SSE/P.Way /CLX, BPP and TEL sections of ADEN/BPP Sub- Division. SW-II) BZA Division: BZA-VSKP sec.Proposed safety related track repairs in SSE/P.Way /Eluru & Nuzvid sections of ADEN/Eluru Sub- Division. SW-III) BZA Division: GDR-BZA sec. Transportation of P.Way materials for scattered and casual renewals Departmentally and for collection scrap in yards for the year 2015-16 in ADEN/BPP sub-division. SW-IV) BZA Division: BZA - VSKP Sec. Transportation of P.Way materials for scattered and casual renewals Departmentally and for collection scrap in yards for the year 2015-16 in ADEN/EE sub-division. SW-V) BZA Division: GDR-BZA sec.: TFR - Through fitting renewal for a length of 65.45km (without ERC) and 1.46km (with all fittings) on up & Dn lines in ADEN/Bapatla Sub-division. SW-VI) BZA Division: GDR-BZA sec.KCC: Shifiting of crossover S103A &B towards Gudur duly making TRD and S&T alterations in KCC yard in ADEN/BPP sub-division SW-VII) BZA Division: GDR-BZA sec. KCC- Shifting of layout of crossover S121 in KCC yard in ADEN/BPP sub-division. SW-VIII) BZA Division: GDR-BZA sec. KCC - Replacement of
Non-standard diamond crossing at KCC yard Pt No. 144A,B & 145 A,B in KCC yard in ADEN/BPP sub-division. . . .
10. Supplementary site-specific instructions, wherever considered necessary, shall be issued
by the Engineer in Charge.
11. The contractor is responsible for safe passage of trains. All trains will be allowed with the
specific approval of SSE/SE/P.Way-in-charge in the portion of track under repairs by the
Contractor. Any variation in this regard, the Contractor will be held responsible for all
damages caused out of negligence manipulated by his staff.
12. The work to be carried out under traffic conditions. It is the responsibility of the
Contractor to see that there is no detention or interruption to the movement of trains and
„No Claim‟ will be admissible towards loss of time/wastage of labour employed etc., that
may be incurred by the contractor due to movement of trains. The rate quoted should
cover all such contingencies.
13. The contractor should engage qualified engineer/retired P.Way Inspector conversant with
P.Way work to supervise at his cost. Work should be taken up only in the presence of the
Engineer nominated for this work.
14. It is the responsibility of the contractor to arrange for watchman to guard against theft etc.,
till that time the released materials is handed over to Engineer – in - charge.
15. If any other items of works covered by S. S. R. 2010 of S. C. Railway Engg. Dept. are
required to be carried out for the same percentage shown there in enhanced/ diminished/ at
par as the case may be at the same percentage as tendered/accepted for this work.
16. The items included in the tender schedule should be carried out in accordance with the S.
C. Railway standard specifications for materials and works 2010 with the up to date
correction slip there to of S.C.Railway.
17. Payment for the earthwork will be made to the quantities arrived to cross section
measurements duly deducting 16% for ordinary soils towards subsidence allowance
if mechanical compaction was not done.
18. Leveling, dressing and sectioning to profile of earthwork should be done in layers
inclusive of breaking up of clods as per specification.
19. The contractor/tenderer has to make his own arrangements for obtaining the earth from
private land owners by paying necessary fees etc. for the same. No extra payment will be
made nor entertained towards the same or any pathway if required to be formed for
execution.
20. The amount of Royalty payable to the Government Department as per rules and the
contractor has to bring the certificate from the Government Department. IOW/PWI/ADEN
has to give the certificate in the bill that whether the earth is brought from Government
land or not.
64
Tender No. 03/Central/2016
Sr.DEN/Central/BZA Signature of Tenderer(s)
Page 64 of 91 BZA Divn., SCR, T.No.03/Central/2016 invited vide Open Tender No.DRM/Works/BZA/03/2016 dt. 05.02.2016, date of opening on 08.03.2016 for the work of SW-I) BZA Division: GDR-BZA sec.Proposed safety related track repairs in SSE/P.Way /CLX, BPP and TEL sections of ADEN/BPP Sub- Division. SW-II) BZA Division: BZA-VSKP sec.Proposed safety related track repairs in SSE/P.Way /Eluru & Nuzvid sections of ADEN/Eluru Sub- Division. SW-III) BZA Division: GDR-BZA sec. Transportation of P.Way materials for scattered and casual renewals Departmentally and for collection scrap in yards for the year 2015-16 in ADEN/BPP sub-division. SW-IV) BZA Division: BZA - VSKP Sec. Transportation of P.Way materials for scattered and casual renewals Departmentally and for collection scrap in yards for the year 2015-16 in ADEN/EE sub-division. SW-V) BZA Division: GDR-BZA sec.: TFR - Through fitting renewal for a length of 65.45km (without ERC) and 1.46km (with all fittings) on up & Dn lines in ADEN/Bapatla Sub-division. SW-VI) BZA Division: GDR-BZA sec.KCC: Shifiting of crossover S103A &B towards Gudur duly making TRD and S&T alterations in KCC yard in ADEN/BPP sub-division SW-VII) BZA Division: GDR-BZA sec. KCC- Shifting of layout of crossover S121 in KCC yard in ADEN/BPP sub-division. SW-VIII) BZA Division: GDR-BZA sec. KCC - Replacement of
Non-standard diamond crossing at KCC yard Pt No. 144A,B & 145 A,B in KCC yard in ADEN/BPP sub-division. . . .
21. The contractor has to acquire land from barrow area of earthwork against item no 1 of
schedule B1 at his own cost. If the earth is brought from barrow area within 200 mts. from
Rly. Boundary, payment for such quantity will be made only 50% of the rate quoted for
item no 1 i.e. earthwork.
22. Special Condition for earth work:
When earth work in bank or cutting is done abutting the running line, the contractor shall
take adequate precautions to avoid accidents/damages to running trains or to any other
property of the railways or the lines, persons or property of others, from what so ever
cause in connection with the work. The zone of activities for execution of work close to
the track shall be clearly demarcated at site by the contractor as directed by Engineer. The
demarcation of the area shall be done by the contractor by providing temporary rope
barricades with bamboos bullies at his cost. Railway will arrange to provide flagmen to
give indication of the running trains and directions to ensure that the work does not
interfere with running trains. The contractor as per the directions given to him without
infringing the moving dimensions shall execute the work. No vehicle should beyond the
rope carried infringing schedule of dimensions.
It should be ensured that flagmen are posted at all work sites to give an indication of
the running trains and vehicles direction to ensure that the contractor‟s workmen/vehicles
do not infringe the moving dimensions.
Seignior age charges for supply of earth, moorum , sand and other minerals as fixed by
State Government and payable to them as revised from time to time during the currency of
contract will be recovered by Railway from the contractors on account and final bills and
remitted to the state government. The rates quoted by the Tenderer shall be inclusive of
these charges. Claims regarding revision of Seignior age charges and consequent
enhancement of the accepted rate will not be entertained
Place : Vijayawada
Date : - - 2016
Signature of the Tenderer/Contractor
65
Tender No. 03/Central/2016
Sr.DEN/Central/BZA Signature of Tenderer(s)
Page 65 of 91 BZA Divn., SCR, T.No.03/Central/2016 invited vide Open Tender No.DRM/Works/BZA/03/2016 dt. 05.02.2016, date of opening on 08.03.2016 for the work of SW-I) BZA Division: GDR-BZA sec.Proposed safety related track repairs in SSE/P.Way /CLX, BPP and TEL sections of ADEN/BPP Sub- Division. SW-II) BZA Division: BZA-VSKP sec.Proposed safety related track repairs in SSE/P.Way /Eluru & Nuzvid sections of ADEN/Eluru Sub- Division. SW-III) BZA Division: GDR-BZA sec. Transportation of P.Way materials for scattered and casual renewals Departmentally and for collection scrap in yards for the year 2015-16 in ADEN/BPP sub-division. SW-IV) BZA Division: BZA - VSKP Sec. Transportation of P.Way materials for scattered and casual renewals Departmentally and for collection scrap in yards for the year 2015-16 in ADEN/EE sub-division. SW-V) BZA Division: GDR-BZA sec.: TFR - Through fitting renewal for a length of 65.45km (without ERC) and 1.46km (with all fittings) on up & Dn lines in ADEN/Bapatla Sub-division. SW-VI) BZA Division: GDR-BZA sec.KCC: Shifiting of crossover S103A &B towards Gudur duly making TRD and S&T alterations in KCC yard in ADEN/BPP sub-division SW-VII) BZA Division: GDR-BZA sec. KCC- Shifting of layout of crossover S121 in KCC yard in ADEN/BPP sub-division. SW-VIII) BZA Division: GDR-BZA sec. KCC - Replacement of
Non-standard diamond crossing at KCC yard Pt No. 144A,B & 145 A,B in KCC yard in ADEN/BPP sub-division. . . .
THE WORK HAS TO BE EXECUTED AS PER THE PAINTING PROCEDURE ORDER FOR
PAINTING OF NEW RAILS AND IN SERVICE RAILS
(A) PAINTING OF NEW RAILS ON CESS:
1.0 Surface preparation:
(a) The surface preparation of rails is one of the most important pre-requisites for
the painting to serve the purpose. Sufficient care should therefore be taken in
preparing the surface. The surface shall be made free from oil, grease and
dust. The surface shall be rubbed with wire brush and sand paper /emery
paper. The tools used may be by hand or by power operated such as scrappers,
wire brushes, emery/sand paper, pumice stones, brick bats etc. Wire brushing
should invariably be done at the end so as to obtain a uniform rubbed surface.
The surface prepared may be checked by visual observation for uniformity of
surface.
(b) Surface preparation shall not be done unless the approved paints of sufficient
quantities are available in stock at site. Special care should be taken in
preparing the surface at the weld collars, liner contact areas and uniformity of
preparation at these locations shall be attained to that of rest of the surface.
Generally weld collars and liner contact areas are considered most corrosive
prone areas. From which fatigue failures develop.
(c) Surface preparation/painting shall not be done in the following conditions.
(i) When the ambient temperature is below 10 degree centigrade or above
50 degree centigrade.
(ii) In rainy season.
(iii) During night.
(iv) In winter before 8.00 a.m.
(v) In summer between 11.00 A.M. and 3.00 P.M. on areas that are likely
to be exposed to direct Sunlight.
(vi) Extremely wind/moist/dust blowing conditions.
(d) Chemicals should not be used for surface preparation.
2.0 Painting Scheme:-
(a) 1st coat (Primer coat):-The red lead paint formed by mixing 3.3 Kg., dry
pigment red lead powder confirming to IS Type-„C‟ 57-1989 is mixed with one
Litre pure linseed oil (boiled) confirming to IS 77/1966 to thickness of 80
microns.
(b) 2nd
coat Red oxide (1st finishing coat):-Ready mixed red oxide confirming to
IS 123-1962 to a thickness of 45 microns mixed with lamp black (to
distinguish from the final coat).
66
Tender No. 03/Central/2016
Sr.DEN/Central/BZA Signature of Tenderer(s)
Page 66 of 91 BZA Divn., SCR, T.No.03/Central/2016 invited vide Open Tender No.DRM/Works/BZA/03/2016 dt. 05.02.2016, date of opening on 08.03.2016 for the work of SW-I) BZA Division: GDR-BZA sec.Proposed safety related track repairs in SSE/P.Way /CLX, BPP and TEL sections of ADEN/BPP Sub- Division. SW-II) BZA Division: BZA-VSKP sec.Proposed safety related track repairs in SSE/P.Way /Eluru & Nuzvid sections of ADEN/Eluru Sub- Division. SW-III) BZA Division: GDR-BZA sec. Transportation of P.Way materials for scattered and casual renewals Departmentally and for collection scrap in yards for the year 2015-16 in ADEN/BPP sub-division. SW-IV) BZA Division: BZA - VSKP Sec. Transportation of P.Way materials for scattered and casual renewals Departmentally and for collection scrap in yards for the year 2015-16 in ADEN/EE sub-division. SW-V) BZA Division: GDR-BZA sec.: TFR - Through fitting renewal for a length of 65.45km (without ERC) and 1.46km (with all fittings) on up & Dn lines in ADEN/Bapatla Sub-division. SW-VI) BZA Division: GDR-BZA sec.KCC: Shifiting of crossover S103A &B towards Gudur duly making TRD and S&T alterations in KCC yard in ADEN/BPP sub-division SW-VII) BZA Division: GDR-BZA sec. KCC- Shifting of layout of crossover S121 in KCC yard in ADEN/BPP sub-division. SW-VIII) BZA Division: GDR-BZA sec. KCC - Replacement of
Non-standard diamond crossing at KCC yard Pt No. 144A,B & 145 A,B in KCC yard in ADEN/BPP sub-division. . . .
(c) Third coat (2nd
finishing coat):-Ready mixed red oxide paint confirming to IS
123-1962 to a thickness of 45 microns.
NOTE:- 1. Surface preparation by way of cleaning, wiping, brushing may be
required between successive coats to remove dust, mud, night-soil etc.
2. The thickness of the film mentioned above is to be ensured at:
(i) Junction of web flange.
(ii) Liner contact area.
(iii) Flange curve near foot.
2.0 Supply of paints:-
Paints shall either be procured through stores department or supplied by the
contractor against painting contracts. Paints manufactured by the following
firms of repute alone shall either be procured or be permitted to be used by
contractors through composite contract involving supply and painting of rails. Paints for painting of Wagons, Bridges & Other Applications
(IS:102, IS:104, IS:123, IS:158, IS:341, IS:2074, IS:9862, IS:5666, IS:3678, IS:2339, IS:3607,
IS:8982)
1 M/s.Advance Paints Ltd., Advance House, Plot „A‟ Makwana Road, ARK Industrial
Compound, Marol Naka, (E) Mumbai – 400059
2 M/s. Aanupam Enterprieses, 208 Mahathma Gandhi Road, (1st floor) Kolkota – 700007
3 M/s. Alka Indusrial Paints (P) Ltd., 46 Purana Quila, Lucknow
4. M/s. Asian Paints (I) Ltd., 6A Shanti Nagar, Shantacruz (Fast), Mumbai –400 058.
5 M/s. Asian Paint & Varnishes Works (P) Ltd., 1 Rose Mary Lane, Howrah-711 101
6 M/s. Asian Industrial & Manufacturing Co., 36, Standrd Road, Kolkota – 700 017
7 M/s. Berger Paints India Ltd., Berger House, 129 Park Steet, Kolkota – 700 017.
8 M/s. Century Paints & Varnish Works, 34-B, Debendra Chandra Dey Road, Kolakota – 700 016
9 M/s. Doss Paints Mfg., Co, 62/1, Raghap Kolay Lane, Salkia, Howrah – 711 106
10 M/s. Deb Paints (P) Ltd., Methopara P. O.Ganganarar, Sistt,24 Paraganas (N)-743250 (WB)
11 M/s. Jenson & Nicholsom (I) Ltd, 225, Acharya Jagadish Chandra Bose Road, Kolkota-20
12 M/s. Kalinga Paints & Chemical Indutries (P) Ltd., Industrial area, Rourkela – 769004, Orissa
13 M/s. Modi Industries Ltd., (Paint Section) Modi Nagar – 201204 (UP)
14 M/s M.P. Paints (P) Ltd., 435-Bm, Sector C, Urla Industrial Area, Raipur – 493221 (CG)
15 M/s. P.K. Industries, Sodal Road, Jallandhar - 144004
16 M/s. Puskar Paint Industries, Badri Sarraf Bhavan, B-92, Sector-C, Mahnagar, Lacknow-
226006
17 M/s. Punjab paint Color & varnish works, 123/52-9, Fajalgunj, Kanpur – 208012
18 M/s. Raco Mercantile Traders, B-2, Govt., Industries Estate, Tlkatora, Lacknow – 226011
19 M/s. Rahul Paints, Mohan Road, Tikait Rai Talab, Lacknow – 226017
20 M/s. United Anitine & Chemicals Co., Pvt. Ltd., 56 Rose Mary Lane, Howrah – 71001 (WB)
21 M/s. Vibgyor Paints and Chemicals, Raj Flats, 42/9 Harrington Road, Chennai – 600030
22 M/s. Western India Paints & Colour Co(P) Ltd., 25/2, Natha Muni Street, T.Nagar, Chennai –
600017
23 M/s.Neo Radient Paints Pvt Ltd., RIC Industrial Estate, Durgapur – 713212 (WB)
24 M/s. Durgapur Paints, RIC Estate, G.T. Road, Durgapur – 713212 Distt. Durdwan
67
Tender No. 03/Central/2016
Sr.DEN/Central/BZA Signature of Tenderer(s)
Page 67 of 91 BZA Divn., SCR, T.No.03/Central/2016 invited vide Open Tender No.DRM/Works/BZA/03/2016 dt. 05.02.2016, date of opening on 08.03.2016 for the work of SW-I) BZA Division: GDR-BZA sec.Proposed safety related track repairs in SSE/P.Way /CLX, BPP and TEL sections of ADEN/BPP Sub- Division. SW-II) BZA Division: BZA-VSKP sec.Proposed safety related track repairs in SSE/P.Way /Eluru & Nuzvid sections of ADEN/Eluru Sub- Division. SW-III) BZA Division: GDR-BZA sec. Transportation of P.Way materials for scattered and casual renewals Departmentally and for collection scrap in yards for the year 2015-16 in ADEN/BPP sub-division. SW-IV) BZA Division: BZA - VSKP Sec. Transportation of P.Way materials for scattered and casual renewals Departmentally and for collection scrap in yards for the year 2015-16 in ADEN/EE sub-division. SW-V) BZA Division: GDR-BZA sec.: TFR - Through fitting renewal for a length of 65.45km (without ERC) and 1.46km (with all fittings) on up & Dn lines in ADEN/Bapatla Sub-division. SW-VI) BZA Division: GDR-BZA sec.KCC: Shifiting of crossover S103A &B towards Gudur duly making TRD and S&T alterations in KCC yard in ADEN/BPP sub-division SW-VII) BZA Division: GDR-BZA sec. KCC- Shifting of layout of crossover S121 in KCC yard in ADEN/BPP sub-division. SW-VIII) BZA Division: GDR-BZA sec. KCC - Replacement of
Non-standard diamond crossing at KCC yard Pt No. 144A,B & 145 A,B in KCC yard in ADEN/BPP sub-division. . . .
4.0 Shelf Life of Paints:-
(i) Paint Red lead Ready mixed: 4 months.
(ii) Paint Red Oxide Ready Mixed: 1 year.
(iii) When paste and oil are not mixed : 1 year
When paste and oil are mixed: 4 days.
(iv) Red lead Dry Pigment: No time limit.
(v) Oil Linseed Boiled: 2 years.
Paints required for primer and finishing coats may be procured from the
same firm for achieving better results.
4.1 Paints should be used within the prescribed shelf life from the date of
manufacture. The quantity of paint procured should be such that it is fully
used before the prescribed period for its use.
4.2 The Contractor/Supplier shall furnish to the Railway the date of manufacture of the
paint as certified by the manufacturer. The labels on the containers should furnish
information regarding the date of manufacture, batch No., etc.
5.0 Application of paint:-
(i) First coat of painting shall be done only after the surface preparation is
approved by the PWI/ADEN. Paint shall be applied on dry surface free from
any type of moisture and shall not be done under the conditions mentioned
earlier in 1© of Para A
(ii) Paint shall be mixed well in the container before it is applied. Over mixing
shall not be done. Visible air bubbles or foam formation shall totally be
avoided.
(iii) Brush shall not be less than 2” (5 cm.) in width and should have good flexible
bristies. If a new brush is used, the same should be soaked in Raw Linseed
Oil for at least 24 hours before using the painting. The brushes shall be
cleaned at the end of each day‟s work.
(iv) Dust settled after scraping shall be cleaned before applying paint.
(v) When the paint is applied by brush, the brush shall be held at 45 degree to the
surface and paint applied with several light vertical/latest strokes turning the
brush frequently and transferring the paint and covering the whole surface.
After this, the brush shall be used cross-wise for a complete coverage and
finally finish with vertical/lateral strokes to achieve uniform and even surface.
(vi) Rags, waste cotton, cloth or similar articles should not be used for applying
paint.
68
Tender No. 03/Central/2016
Sr.DEN/Central/BZA Signature of Tenderer(s)
Page 68 of 91 BZA Divn., SCR, T.No.03/Central/2016 invited vide Open Tender No.DRM/Works/BZA/03/2016 dt. 05.02.2016, date of opening on 08.03.2016 for the work of SW-I) BZA Division: GDR-BZA sec.Proposed safety related track repairs in SSE/P.Way /CLX, BPP and TEL sections of ADEN/BPP Sub- Division. SW-II) BZA Division: BZA-VSKP sec.Proposed safety related track repairs in SSE/P.Way /Eluru & Nuzvid sections of ADEN/Eluru Sub- Division. SW-III) BZA Division: GDR-BZA sec. Transportation of P.Way materials for scattered and casual renewals Departmentally and for collection scrap in yards for the year 2015-16 in ADEN/BPP sub-division. SW-IV) BZA Division: BZA - VSKP Sec. Transportation of P.Way materials for scattered and casual renewals Departmentally and for collection scrap in yards for the year 2015-16 in ADEN/EE sub-division. SW-V) BZA Division: GDR-BZA sec.: TFR - Through fitting renewal for a length of 65.45km (without ERC) and 1.46km (with all fittings) on up & Dn lines in ADEN/Bapatla Sub-division. SW-VI) BZA Division: GDR-BZA sec.KCC: Shifiting of crossover S103A &B towards Gudur duly making TRD and S&T alterations in KCC yard in ADEN/BPP sub-division SW-VII) BZA Division: GDR-BZA sec. KCC- Shifting of layout of crossover S121 in KCC yard in ADEN/BPP sub-division. SW-VIII) BZA Division: GDR-BZA sec. KCC - Replacement of
Non-standard diamond crossing at KCC yard Pt No. 144A,B & 145 A,B in KCC yard in ADEN/BPP sub-division. . . .
(vii) The coat of paint applied shall be such that the prescribed dry film thickness is
achieved by actual trial for the particular brand of paint. The applied coat of
paint shall be uniform, and free from brush marks, sags, blemishes, scattering,
crawling, uneven thickness, holes, lap marks, lifting, peeling, staining,
cracking, checking, scaling, holidays and allegatoring.
(viii) Each coat of paint shall be left to dry till it sufficiently hardens before the
subsequent coat is applied. The time lag between the completion of the primer
coat and the commencement of the covering coat shall not exceed 7 days. The
drying time shall not be less than 3 days in the case of Red Lead Paint. Each
coat of paint shall be inspected by PWI/ADEN and certified as satisfactory
before applying the subsequent coat.
(ix) The thickness of the dry film shall not be less than the specified thickness. If
the thickness is found less than specified thickness, additional coat of paint has
to be applied to bring it to the required thickness. The thickness shall be
measured at various locations to ensure that the minimum prescribed thickness
is attained all over the areas painted. Engineer-in-charge should satisfy himself
that the thickness obtained is not less than that specified.
(x) Painted surface shall be smooth and uniform in colour. The thickness of each
coat of paint shall be measured by ELCO Meter.
(xi) The time lag between successive operations indicated below shall under no
circumstances be exceeded.
(a) Between completion of surface preparation standard : 4 hours.
and the Application of primer coat.
(b) Between the primer coat and the 1st finishing coat. : 7 days
(c) Between the 1st finishing coat and the 2
nd finishing coat. : 7 days
6.0 Testing of the paint:-
(i) The paints/painting shall be tested by the following instruments in the filed by
PWI/ADEN in addition to the tests conducted by CMT/LGD or any national
Test house.
(a) Weight per litre cup 100 ml. Capacity stainless steel.
(b) Ford Cup No.4
(c) Scratch Hardness Tester Hand Operated preferably with lighting
arrangement.
(d) Flexibility and Adhesion Tester with ¼” (6.25 mm) dia rod.
69
Tender No. 03/Central/2016
Sr.DEN/Central/BZA Signature of Tenderer(s)
Page 69 of 91 BZA Divn., SCR, T.No.03/Central/2016 invited vide Open Tender No.DRM/Works/BZA/03/2016 dt. 05.02.2016, date of opening on 08.03.2016 for the work of SW-I) BZA Division: GDR-BZA sec.Proposed safety related track repairs in SSE/P.Way /CLX, BPP and TEL sections of ADEN/BPP Sub- Division. SW-II) BZA Division: BZA-VSKP sec.Proposed safety related track repairs in SSE/P.Way /Eluru & Nuzvid sections of ADEN/Eluru Sub- Division. SW-III) BZA Division: GDR-BZA sec. Transportation of P.Way materials for scattered and casual renewals Departmentally and for collection scrap in yards for the year 2015-16 in ADEN/BPP sub-division. SW-IV) BZA Division: BZA - VSKP Sec. Transportation of P.Way materials for scattered and casual renewals Departmentally and for collection scrap in yards for the year 2015-16 in ADEN/EE sub-division. SW-V) BZA Division: GDR-BZA sec.: TFR - Through fitting renewal for a length of 65.45km (without ERC) and 1.46km (with all fittings) on up & Dn lines in ADEN/Bapatla Sub-division. SW-VI) BZA Division: GDR-BZA sec.KCC: Shifiting of crossover S103A &B towards Gudur duly making TRD and S&T alterations in KCC yard in ADEN/BPP sub-division SW-VII) BZA Division: GDR-BZA sec. KCC- Shifting of layout of crossover S121 in KCC yard in ADEN/BPP sub-division. SW-VIII) BZA Division: GDR-BZA sec. KCC - Replacement of
Non-standard diamond crossing at KCC yard Pt No. 144A,B & 145 A,B in KCC yard in ADEN/BPP sub-division. . . .
Representative samples from each Batch of paint shall be got tested by either
the Chemist & Mettalurgist/Lallaguda (Secunderabad) or at any other National
Testing Laboratories, whichever, is convenient at the cost of the Contractor. If
the samples of paint tested, do not conform to the ISI Specifications, the
whole lot of paint pertaining to that Batch shall be rejected.
(ii) Paints supplied by the Stores Department shall also be tested and used only if
they are found suitable. Paints, which are either over-age or not conforming to
specificatiions, shall be scrapped and returned to stores for disposal.
(B) Painting of In-service Rails: 1. Surface preparation: The surface preparation may be carried out as described at Para
A(1.0) as in case of new rails, except removal of loose paint/flaked paint also to be
removed.
2. Painting scheme:- (i) 1
st Coat: Anti corrosive bituminous black paint confirming to IS 9862-1981
to a thickness of 100 microns.
(ii) 2nd
Coat: Anti corrosive bituminous black paint confirming to IS 9862-1981
to a thickness of 100 microns.
3. Paints shall either be procured through Stores Department or supplied by the
Contractor/Agency against painting contracts. Paints manufactured by the following
Firms approved by RDSO and ICF alone shall either be procured or be permitted to be
used by the Contractors through composite contracts involving supply and painting of
rails.
Paints for painting of Wagons, Bridges & Other Applications
(IS:102, IS:104, IS:123, IS:158, IS:341, IS:2074, IS:9862, IS:5666, IS:3678, IS:2339, IS:3607, IS:8982)
1 M/s.Advance Paints Ltd., Advance House, Plot „A‟ Makwana Road, ARK Industrial Compound,
Marol Naka, (E) Mumbai – 400059
2 M/s. Aanupam Enterprieses, 208 Mahathma Gandhi Road, (1st floor) Kolkota – 700007
3 M/s. Alka Indusrial Paints (P) Ltd., 46 Purana Quila, Lucknow
4. M/s. Asian Paints (I) Ltd., 6A Shanti Nagar, Shantacruz (Fast), Mumbai –400 058.
5 M/s. Asian Paint & Varnishes Works (P) Ltd., 1 Rose Mary Lane, Howrah-711 101
6 M/s. Asian Industrial & Manufacturing Co., 36, Standrd Road, Kolkota – 700 017
7 M/s. Berger Paints India Ltd., Berger House, 129 Park Steet, Kolkota – 700 017.
8 M/s. Century Paints & Varnish Works, 34-B, Debendra Chandra Dey Road, Kolakota – 700 016
9 M/s. Doss Paints Mfg., Co, 62/1, Raghap Kolay Lane, Salkia, Howrah – 711 106
10 M/s. Deb Paints (P) Ltd., Methopara P. O.Ganganarar, Sistt,24 Paraganas (N)-743250 (WB)
11 M/s. Jenson & Nicholsom (I) Ltd, 225, Acharya Jagadish Chandra Bose Road, Kolkota-20
12 M/s. Kalinga Paints & Chemical Indutries (P) Ltd., Industrial area, Rourkela – 769004, Orissa
13 M/s. Modi Industries Ltd., (Paint Section) Modi Nagar – 201204 (UP)
14 M/s M.P. Paints (P) Ltd., 435-Bm, Sector C, Urla Industrial Area, Raipur – 493221 (CG)
15 M/s. P.K. Industries, Sodal Road, Jallandhar - 144004
16 M/s. Puskar Paint Industries, Badri Sarraf Bhavan, B-92, Sector-C, Mahnagar, Lacknow-226006
17 M/s. Punjab paint Color & varnish works, 123/52-9, Fajalgunj, Kanpur – 208012
18 M/s. Raco Mercantile Traders, B-2, Govt., Industries Estate, Tlkatora, Lacknow – 226011
70
Tender No. 03/Central/2016
Sr.DEN/Central/BZA Signature of Tenderer(s)
Page 70 of 91 BZA Divn., SCR, T.No.03/Central/2016 invited vide Open Tender No.DRM/Works/BZA/03/2016 dt. 05.02.2016, date of opening on 08.03.2016 for the work of SW-I) BZA Division: GDR-BZA sec.Proposed safety related track repairs in SSE/P.Way /CLX, BPP and TEL sections of ADEN/BPP Sub- Division. SW-II) BZA Division: BZA-VSKP sec.Proposed safety related track repairs in SSE/P.Way /Eluru & Nuzvid sections of ADEN/Eluru Sub- Division. SW-III) BZA Division: GDR-BZA sec. Transportation of P.Way materials for scattered and casual renewals Departmentally and for collection scrap in yards for the year 2015-16 in ADEN/BPP sub-division. SW-IV) BZA Division: BZA - VSKP Sec. Transportation of P.Way materials for scattered and casual renewals Departmentally and for collection scrap in yards for the year 2015-16 in ADEN/EE sub-division. SW-V) BZA Division: GDR-BZA sec.: TFR - Through fitting renewal for a length of 65.45km (without ERC) and 1.46km (with all fittings) on up & Dn lines in ADEN/Bapatla Sub-division. SW-VI) BZA Division: GDR-BZA sec.KCC: Shifiting of crossover S103A &B towards Gudur duly making TRD and S&T alterations in KCC yard in ADEN/BPP sub-division SW-VII) BZA Division: GDR-BZA sec. KCC- Shifting of layout of crossover S121 in KCC yard in ADEN/BPP sub-division. SW-VIII) BZA Division: GDR-BZA sec. KCC - Replacement of
Non-standard diamond crossing at KCC yard Pt No. 144A,B & 145 A,B in KCC yard in ADEN/BPP sub-division. . . .
19 M/s. Rahul Paints, Mohan Road, Tikait Rai Talab, Lacknow – 226017
20 M/s. United Anitine & Chemicals Co., Pvt. Ltd., 56 Rose Mary Lane, Howrah – 71001 (WB)
21 M/s. Vibgyor Paints and Chemicals, Raj Flats, 42/9 Harrington Road, Chennai – 600030
22 M/s. Western India Paints & Colour Co(P) Ltd., 25/2, Natha Muni Street, T.Nagar, Chennai –
600017
23 M/s.Neo Radient Paints Pvt Ltd., RIC Industrial Estate, Durgapur – 713212 (WB)
24 M/s. Durgapur Paints, RIC Estate, G.T. Road, Durgapur – 713212 Distt. Durdwan
4. Method of painting:- Method of painting: SR of 50 Kmph is imposed in a selected stretch and only
alternative ERCs are removed either inside of the gauge face or outside of the gauge
face. At no point of time both inside and outside ERCs even on alternate sleepers
should be removed. The work shall be started at around 8.00 hrs., and the ERCs shall
be removed at alternate sleepers and on carrying out surface preparation, and
bituminous black confirming to IS 9862-1981 shall be applied to a thickness of 100
microns and is allowed for a drying of 8 hours time and subsequently the same second
coat is applied to a thickness of 100 microns and allowed for drying for 8 hours and
then liner and ERCs are fixed to the rails duly greasing insert holes and central leg of
ERC. All the liners and ERCs and insert top surface shall also be painted with anti-
corrosive black after duly cleaning the surface. Similarly in the same caution order
alternative left over ERCs are removed and painting to be done as indicated above.
5. Frequency of painting of Rail:-
(i) Painting of new rails on cess: All new rails shall be painted before
they are laid in track with red lead and red oxide as indicated under
painting of rails on cess vide Para –(A).
(ii) Painting of in-service Rails: Subsequently once in a year painting
shall be carried out for the inside gauge face of rails including foot and
web and excluding gauge face surface
(iii) Non-gauge face side foot of the rail including web and non-guage face
and excluding rail top should be painted once in 3 years.
6. Maintenance of Field-cum-site Order Books:-
(i) Field-cum-site order books shall invariably be maintained for the
painting work. Two separate Field Books shall be maintained, so that
one Book can be with the Inspector concerned, while the other book
accompanies the Bill and M.Book for check and passing of the bill. All
the field books shall accompany the Final bill and they shall be finally
filed in DEN office.
71
Tender No. 03/Central/2016
Sr.DEN/Central/BZA Signature of Tenderer(s)
Page 71 of 91 BZA Divn., SCR, T.No.03/Central/2016 invited vide Open Tender No.DRM/Works/BZA/03/2016 dt. 05.02.2016, date of opening on 08.03.2016 for the work of SW-I) BZA Division: GDR-BZA sec.Proposed safety related track repairs in SSE/P.Way /CLX, BPP and TEL sections of ADEN/BPP Sub- Division. SW-II) BZA Division: BZA-VSKP sec.Proposed safety related track repairs in SSE/P.Way /Eluru & Nuzvid sections of ADEN/Eluru Sub- Division. SW-III) BZA Division: GDR-BZA sec. Transportation of P.Way materials for scattered and casual renewals Departmentally and for collection scrap in yards for the year 2015-16 in ADEN/BPP sub-division. SW-IV) BZA Division: BZA - VSKP Sec. Transportation of P.Way materials for scattered and casual renewals Departmentally and for collection scrap in yards for the year 2015-16 in ADEN/EE sub-division. SW-V) BZA Division: GDR-BZA sec.: TFR - Through fitting renewal for a length of 65.45km (without ERC) and 1.46km (with all fittings) on up & Dn lines in ADEN/Bapatla Sub-division. SW-VI) BZA Division: GDR-BZA sec.KCC: Shifiting of crossover S103A &B towards Gudur duly making TRD and S&T alterations in KCC yard in ADEN/BPP sub-division SW-VII) BZA Division: GDR-BZA sec. KCC- Shifting of layout of crossover S121 in KCC yard in ADEN/BPP sub-division. SW-VIII) BZA Division: GDR-BZA sec. KCC - Replacement of
Non-standard diamond crossing at KCC yard Pt No. 144A,B & 145 A,B in KCC yard in ADEN/BPP sub-division. . . .
(ii) Inspector-in-charge shall record certificates in both Field books and
M.Books on completion of each stage of work i.e., surface preparation,
primer coats, 1st finishing coat and 2
nd finishing coat in token of the
completion of each stage of work confirming that each operation is
done satisfactorily and completely. The minimum thickness of paint
for each coat has to be recorded by the Inspectors and the ADENs shall
test checks the same.
(iii) The certificate be forwarded by the Inspectors and ADENs shall read as
under:
“Certified that Primer of Km_____________ to Km___________
1st finishing coat of Km_____________ to Km___________
2nd
finishing coat of Km_____________ to Km___________
is satisfactorily completed in full (except for _________________)
The total quantity of paint consumed is __________________ Lits. And the minimum
thickness of the paint is __________ microne.”
(iv) Field-cum-site order book shall contain the following information:
(a) Section, Km., TP, LH/RH, Rail, Gauge/Non-gauge face side.
(b) Contractor‟s Name and Address: Details of Agreement.
(c) Name of manufacturer of the paint, Specifications, Batch No.,
Manufacturing Date, expiry date, Reference to certificate by the
Chemist and Metallurgist, Lallaguda or certificate issued by National
Test House.
(d) Date of commencement and completion of each of the following
operations:
Surface preparation.
Painting primer coat.
Painting 1st Finishing coat.
Painting 2nd
Finishing coat.
(v) (a) The paints supplied shall be taken into account by the SSE and
issued back to the agency for painting as per requirement.
(b) The Agency on completion of the work shall return back the
empty drums to the SSE, who shall ensure that the empty
drums are kept safe for a minimum period of 3 months after
completion of work and thereafter return the same to Stores /
Shop them duly obtaining concurrence from ADEN of the
section.
(vi) Results of tests conducted by PWI on Paint shall also be recorded in the
Field/Site Order Books. A minimum of two tests per batch of paint
shall be conducted at random.
72
Tender No. 03/Central/2016
Sr.DEN/Central/BZA Signature of Tenderer(s)
Page 72 of 91 BZA Divn., SCR, T.No.03/Central/2016 invited vide Open Tender No.DRM/Works/BZA/03/2016 dt. 05.02.2016, date of opening on 08.03.2016 for the work of SW-I) BZA Division: GDR-BZA sec.Proposed safety related track repairs in SSE/P.Way /CLX, BPP and TEL sections of ADEN/BPP Sub- Division. SW-II) BZA Division: BZA-VSKP sec.Proposed safety related track repairs in SSE/P.Way /Eluru & Nuzvid sections of ADEN/Eluru Sub- Division. SW-III) BZA Division: GDR-BZA sec. Transportation of P.Way materials for scattered and casual renewals Departmentally and for collection scrap in yards for the year 2015-16 in ADEN/BPP sub-division. SW-IV) BZA Division: BZA - VSKP Sec. Transportation of P.Way materials for scattered and casual renewals Departmentally and for collection scrap in yards for the year 2015-16 in ADEN/EE sub-division. SW-V) BZA Division: GDR-BZA sec.: TFR - Through fitting renewal for a length of 65.45km (without ERC) and 1.46km (with all fittings) on up & Dn lines in ADEN/Bapatla Sub-division. SW-VI) BZA Division: GDR-BZA sec.KCC: Shifiting of crossover S103A &B towards Gudur duly making TRD and S&T alterations in KCC yard in ADEN/BPP sub-division SW-VII) BZA Division: GDR-BZA sec. KCC- Shifting of layout of crossover S121 in KCC yard in ADEN/BPP sub-division. SW-VIII) BZA Division: GDR-BZA sec. KCC - Replacement of
Non-standard diamond crossing at KCC yard Pt No. 144A,B & 145 A,B in KCC yard in ADEN/BPP sub-division. . . .
SAFETY PRECAUTIONS TO BE TAKEN AT WORK SITE.
1.1. The Contractor shall not allow any road vehicle belonging to his or his suppliers etc. to
ply in railway land next to the running line. If for execution of certain works, viz.,
earthwork for parallel railway line, supply of ballast for new or existing railway line
etc. road vehicles are necessarily to be used in railway land next to the railway line,
the contractor shall apply to the Engineer-in-charge for granting permission giving
the type and number of individual vehicles, names and license particulars and
permanent addresses of drivers, location, duration and timings for such
work/movement. The Engineer-in-charge or his authorized representative will
personally counsel, examine and certify the road vehicle drivers, contractor‟s flagmen
and his supervisors to be deployed on the work, location, period and timing of the
work.
This permission will be subject to the following obligatory conditions:-
i) The Road vehicle will ply only between sunrise and sunset.
ii) Nominated vehicles and drivers will be utilized for work in the presence of at
least one flagmen and one supervisor or his representative certified for such
work.
iii) The vehicles shall ply 6 Meters (from Centre of Track) away from track. Any
movement /work at less than 6 Meters and up to minimum 3.5 Meters clear of
track center shall only be done in presence of railway employees authorized by
the Engineer-in-charge . No part of road vehicle will be allowed at less than 3.5
Meters from track center.
iv) The Contractor shall remain fully responsible for ensuring safety and in case of
accident, shall bear the cost of all damages to the equipments and men and also
damages to railway and its passengers.
v) Engineer-in-charge may impose any other condition necessary for a particular
work or site.
1.2.1. The Contractor at all times shall adopt safe working methods to ensure safety of
structures, equipments and labour at site of works.
1.2.2. The contractor shall not start any work without the presence of Railway supervisor or
his representative authorized by ADEN-in-charge and Contractor‟s supervisor at site.
73
Tender No. 03/Central/2016
Sr.DEN/Central/BZA Signature of Tenderer(s)
Page 73 of 91 BZA Divn., SCR, T.No.03/Central/2016 invited vide Open Tender No.DRM/Works/BZA/03/2016 dt. 05.02.2016, date of opening on 08.03.2016 for the work of SW-I) BZA Division: GDR-BZA sec.Proposed safety related track repairs in SSE/P.Way /CLX, BPP and TEL sections of ADEN/BPP Sub- Division. SW-II) BZA Division: BZA-VSKP sec.Proposed safety related track repairs in SSE/P.Way /Eluru & Nuzvid sections of ADEN/Eluru Sub- Division. SW-III) BZA Division: GDR-BZA sec. Transportation of P.Way materials for scattered and casual renewals Departmentally and for collection scrap in yards for the year 2015-16 in ADEN/BPP sub-division. SW-IV) BZA Division: BZA - VSKP Sec. Transportation of P.Way materials for scattered and casual renewals Departmentally and for collection scrap in yards for the year 2015-16 in ADEN/EE sub-division. SW-V) BZA Division: GDR-BZA sec.: TFR - Through fitting renewal for a length of 65.45km (without ERC) and 1.46km (with all fittings) on up & Dn lines in ADEN/Bapatla Sub-division. SW-VI) BZA Division: GDR-BZA sec.KCC: Shifiting of crossover S103A &B towards Gudur duly making TRD and S&T alterations in KCC yard in ADEN/BPP sub-division SW-VII) BZA Division: GDR-BZA sec. KCC- Shifting of layout of crossover S121 in KCC yard in ADEN/BPP sub-division. SW-VIII) BZA Division: GDR-BZA sec. KCC - Replacement of
Non-standard diamond crossing at KCC yard Pt No. 144A,B & 145 A,B in KCC yard in ADEN/BPP sub-division. . . .
1.2.3. The methodology proposed to be adopted by the Contractor is to be approved by
Engineer-in-charge with a view to ensure of safety of trains, passengers and workers
and he shall also ensure that the methods and arrangements are actually available at
site before start of the work and the contractor‟s supervisors and the workers have
clearly understood the safety aspects and requirements to be adopted / followed while
executing the work.
1.2.4. There shall be an assurance Register kept at each site, which will have to be signed by
both, ie., Railway Supervisor or his representative as well as the contractor‟s
supervisor as a token of their having understood the safety precautions to be observed
at site.
1.2.5. Survey of site by Supervisor of contractor and Railway‟s Supervisor is to be done to
assess precautions to be taken at site for working of trains and materials required for
protection.
1.2.6. The list of permissible / sanctioned infringements to moving dimensions for the section
shall be made available where work is to be done to execute the works without
infringing the moving dimensions.
1.2.7. Competency certificate issued by ADEN-in-charge with the Contractor‟s supervisor at
site should be available in the format given in Annexure-I.
1.2.8. The detailed plans for safe execution of works, duly approved by the Division should
be available for undertaking execution of such works which have bearing on moving
dimensions, especially those works close to the running lines and fixed structures on
brides, inside tunnels etc.,
1.2.9 Look-out caution, speed restrictions as well as traffic block shall be ensured where
necessary for execution of works affecting running lines.
1.2.10 Mobile phones or Walky-Talkie sets where necessary should be provided at work
sites.
1.3. Precautionary measures to be taken at work site away from the track:-
1.3.1. Trenches and foundation pits should be adequately and securely fenced, provided with
proper caution signs and marked with red lights at suitable intervals during night to
avoid accidents. Adequate protective measures should be taken to see that the
excavation operations do not affect or damage adjoining existing buildings.
1.3.2. Proper precautions should be taken for safety of persons and adjoining property before
undertaking any blasting operation. Red flags should be prominently displayed around
the area to be blasted. All the people on the work except those, who actually light the
fuses, should be withdrawn to a safe distance of not less than 300 meters from the
blasting site. Recommendations given in I.S. 4081:1986 should be followed for safety
during various operations involved in the process of blasting.
74
Tender No. 03/Central/2016
Sr.DEN/Central/BZA Signature of Tenderer(s)
Page 74 of 91 BZA Divn., SCR, T.No.03/Central/2016 invited vide Open Tender No.DRM/Works/BZA/03/2016 dt. 05.02.2016, date of opening on 08.03.2016 for the work of SW-I) BZA Division: GDR-BZA sec.Proposed safety related track repairs in SSE/P.Way /CLX, BPP and TEL sections of ADEN/BPP Sub- Division. SW-II) BZA Division: BZA-VSKP sec.Proposed safety related track repairs in SSE/P.Way /Eluru & Nuzvid sections of ADEN/Eluru Sub- Division. SW-III) BZA Division: GDR-BZA sec. Transportation of P.Way materials for scattered and casual renewals Departmentally and for collection scrap in yards for the year 2015-16 in ADEN/BPP sub-division. SW-IV) BZA Division: BZA - VSKP Sec. Transportation of P.Way materials for scattered and casual renewals Departmentally and for collection scrap in yards for the year 2015-16 in ADEN/EE sub-division. SW-V) BZA Division: GDR-BZA sec.: TFR - Through fitting renewal for a length of 65.45km (without ERC) and 1.46km (with all fittings) on up & Dn lines in ADEN/Bapatla Sub-division. SW-VI) BZA Division: GDR-BZA sec.KCC: Shifiting of crossover S103A &B towards Gudur duly making TRD and S&T alterations in KCC yard in ADEN/BPP sub-division SW-VII) BZA Division: GDR-BZA sec. KCC- Shifting of layout of crossover S121 in KCC yard in ADEN/BPP sub-division. SW-VIII) BZA Division: GDR-BZA sec. KCC - Replacement of
Non-standard diamond crossing at KCC yard Pt No. 144A,B & 145 A,B in KCC yard in ADEN/BPP sub-division. . . .
1.3.3. Suitable scaffold should be provided for workman for all works that cannot be safely
done from the ground or from solid constructions except such works which can be
done safely from ladders for a short period. When a ladder is used, extra labour should
be engaged for holding the ladder and if the ladder is used for carrying materials as
well, suitable foot holds and handholds should be provided on the ladder and ladder
should be given an inclination not steeper than 4 to 1 ( Four vertical to one
Horizontal).
1.3.4. Workers employed on mixing asphalt materials, cement and lime mortars should be
provided with protective hand and footwear and protective goggles.
1.3.5. Workers employed in white washing and stacking of cement bags or any materials
which are injurious to the eyes should be provided with protective goggles.
1.3.6. Workers engaged in welding works should be provided with welder protective eye-
shields, single piece cotton cloth and shoes.
1.3.7. Stone breakers should be provided with protective goggles, leg-guards and protective
clothing and they should be seated at sufficiently safe distance from each other.
1.3.8. A fully equipped First-Aid Box should be maintained at site by the Agency with at
least one person fully trained to give First-Aid.
1.3.9. Inflammable articles such as Petrol, oil etc., should be stored separately from other
materials and all prescribed precautions as per the Indian Explosive Act should be
taken.
1.3.10. In the Bridge work, Track works, repairs to tunnel and demolition of structures
through contractual Agency, the safe working and ensuring safety of workman
employed should be specifically laid down in the contract itself.
1.4. Precautionary measures to be taken at work site in vicinity of track:- 1.4.1. Drivers of trains must be served with caution order to look out for any obstruction at the place
of work.
1.4.2. Arrangements should be made to protect the track in case of emergency at work site.
1.4.3. Before the start of the work, the land strip adjacent to the running track where road vehicle /
machinery is to ply for the work shall be demarcated by lime in advance at the appropriate
distance from the centre of existing track in consultation with the Railway
Supervisor[Annexure-IV(A)]. Sketch showing the location of marking and barricading along
the full length of the work area should be done as per the sketch given in [Annexure-IV (B)].
This will enable the workmen posted at the site and also the lorry drivers to have clear
guidelines on the movement of vehicles.
1.4.4. Movement of Lorries near the track should be prohibited during night. In case it is
unavoidable adequate protective measures including lighting must be ensured in the complete
work area for the safety of the Public and Passengers. Also additional staff shall be posted as
necessary for night working.
75
Tender No. 03/Central/2016
Sr.DEN/Central/BZA Signature of Tenderer(s)
Page 75 of 91 BZA Divn., SCR, T.No.03/Central/2016 invited vide Open Tender No.DRM/Works/BZA/03/2016 dt. 05.02.2016, date of opening on 08.03.2016 for the work of SW-I) BZA Division: GDR-BZA sec.Proposed safety related track repairs in SSE/P.Way /CLX, BPP and TEL sections of ADEN/BPP Sub- Division. SW-II) BZA Division: BZA-VSKP sec.Proposed safety related track repairs in SSE/P.Way /Eluru & Nuzvid sections of ADEN/Eluru Sub- Division. SW-III) BZA Division: GDR-BZA sec. Transportation of P.Way materials for scattered and casual renewals Departmentally and for collection scrap in yards for the year 2015-16 in ADEN/BPP sub-division. SW-IV) BZA Division: BZA - VSKP Sec. Transportation of P.Way materials for scattered and casual renewals Departmentally and for collection scrap in yards for the year 2015-16 in ADEN/EE sub-division. SW-V) BZA Division: GDR-BZA sec.: TFR - Through fitting renewal for a length of 65.45km (without ERC) and 1.46km (with all fittings) on up & Dn lines in ADEN/Bapatla Sub-division. SW-VI) BZA Division: GDR-BZA sec.KCC: Shifiting of crossover S103A &B towards Gudur duly making TRD and S&T alterations in KCC yard in ADEN/BPP sub-division SW-VII) BZA Division: GDR-BZA sec. KCC- Shifting of layout of crossover S121 in KCC yard in ADEN/BPP sub-division. SW-VIII) BZA Division: GDR-BZA sec. KCC - Replacement of
Non-standard diamond crossing at KCC yard Pt No. 144A,B & 145 A,B in KCC yard in ADEN/BPP sub-division. . . .
1.4.5. Work should not be allowed to progress without the prior approval of the Engineer-in- charge
in case movement of vehicles close to the track is involved.
1.4.6. Machines and vehicles should ply 6 meters (from Track centre) in case movement at less than
6 meters away from the track is inescapable, it should be permitted in the presence of Railway
employee authorized by the Engineer-in-charge.
1.4.7. Contractor‟s representative should be issued a certificate by ADEN to the effect that they have
acquired sufficient knowledge about the safety precautions that are needed to be followed
while working near the track.
1.4.8. The worksite shall be suitably demarcated to keep public and passengers away from work
area. Necessary sign boards such as Work in progress etc. shall be provided at appropriate
locations to warn the Public / passengers.
1.4.9. Check lists given in Annexure-II and III shall be used to ensure that all the requisite
measures have been taken before start of work and work in progress.
1.4.10. All temporary arrangements required to be made during execution of work shall be made in
such a manner that moving dimensions do not infringe. Necessary checks shall be exercised
by Site in-charge from time to time.
WORKING OF CONTRACTOR‟S VEHICLES AT SITE
a. When the contractor‟s vehicles are to be worked closer to 6m but not less than 3.5m from
center line of the running track (Annexure-VA)
i) Drivers of vehicle shall be briefed about safety and precautions to be taken while
moving/working close to traffic.
ii) Demarcation of the land shall be done by bright coloured red ribbon/nylon rope of 12mm thick
suspended on 75cm high wooden/bamboo posts at a distance of 3.5m from center line of nearest
running track as shown in (Annexure-IVC)
iii) Contractor shall ensure the road vehicle/Machinery ply in a way so that these do not infringe the
line of demarcation.
iv) Presence of an authorized Railways representative shall be ensured before plying of vehicles or
working machinery.
v) Railway supervisor shall issue suitable caution order to drivers of approaching train about road
vehicles plying or machinery working close to running tracks. The train drivers shall be advised
to whistle freely to warn about the approaching train. Whistle boards shall be provided
wherever considered necessary.
vi) Lookout men shall be posted along the track at a distance of 800m from such locations, which
will carry red flag and whistles to warn to the road vehicles/machinery users about the
approaching trains.
vii) On curves where visibility is poor, additional lookout men shall be posted.
viii) In unusual circumstances, where operator apprehends infringement to track while working
truck/machinery near running track, following action shall be taken:
76
Tender No. 03/Central/2016
Sr.DEN/Central/BZA Signature of Tenderer(s)
Page 76 of 91 BZA Divn., SCR, T.No.03/Central/2016 invited vide Open Tender No.DRM/Works/BZA/03/2016 dt. 05.02.2016, date of opening on 08.03.2016 for the work of SW-I) BZA Division: GDR-BZA sec.Proposed safety related track repairs in SSE/P.Way /CLX, BPP and TEL sections of ADEN/BPP Sub- Division. SW-II) BZA Division: BZA-VSKP sec.Proposed safety related track repairs in SSE/P.Way /Eluru & Nuzvid sections of ADEN/Eluru Sub- Division. SW-III) BZA Division: GDR-BZA sec. Transportation of P.Way materials for scattered and casual renewals Departmentally and for collection scrap in yards for the year 2015-16 in ADEN/BPP sub-division. SW-IV) BZA Division: BZA - VSKP Sec. Transportation of P.Way materials for scattered and casual renewals Departmentally and for collection scrap in yards for the year 2015-16 in ADEN/EE sub-division. SW-V) BZA Division: GDR-BZA sec.: TFR - Through fitting renewal for a length of 65.45km (without ERC) and 1.46km (with all fittings) on up & Dn lines in ADEN/Bapatla Sub-division. SW-VI) BZA Division: GDR-BZA sec.KCC: Shifiting of crossover S103A &B towards Gudur duly making TRD and S&T alterations in KCC yard in ADEN/BPP sub-division SW-VII) BZA Division: GDR-BZA sec. KCC- Shifting of layout of crossover S121 in KCC yard in ADEN/BPP sub-division. SW-VIII) BZA Division: GDR-BZA sec. KCC - Replacement of
Non-standard diamond crossing at KCC yard Pt No. 144A,B & 145 A,B in KCC yard in ADEN/BPP sub-division. . . .
a) The contractor /supervisor/vehicle operator immediately advise the situation to Railway official
and assist him in protecting the track.
b) Protection shall be done for other emergencies.
2. When the contractor‟s vehicles are to be worked close to 3.5m from center line of running
track:
i) Plying of vehicle or working of machinery closer to 3.5m of running track shall be done under
protection of track. Traffic block shall be imposed wherever considered necessary. The site
shall be protected as per the sketch given in (Annexure-VB) and the provisions of Para No. 806
& 807 of P-way Manual as the case may be.
ii) Presence of a Railway supervisor shall be ensured at work site.
iii) Railway supervisor shall issue suitable caution order to drivers of approaching train about road
vehicles plying or machinery working close to running tracks. The train drivers shall whistle
freely to warn about the approaching train.
3. Parking of vehicles or construction machinery:
i) No vehicle or construction machinery shall be parked in unmanned condition on a gradient
sloping towards running track.
ii) Even on level ground or gradients sloping away from the track, vehicles or construction
machinery shall be parked in unmanned conditions at a minimum distance of 6m from nearest
track center in fully braked condition. In addition to brakes, suitable wedges shall also be
applied on all the wheels.
TRAINING
Training in safe working methods for both along and on the track should be imparted to
supervisors /operators of the work executing agencies. Such training may be imparted at
zonal/divisional training schools for required duration as deemed fit, with a view to ensure that
the field staff engaged in such works get acquainted with the safety precautions that are needed
to be taken while executing the works.
77
Tender No. 03/Central/2016
Sr.DEN/Central/BZA Signature of Tenderer(s)
Page 77 of 91 BZA Divn., SCR, T.No.03/Central/2016 invited vide Open Tender No.DRM/Works/BZA/03/2016 dt. 05.02.2016, date of opening on 08.03.2016 for the work of SW-I) BZA Division: GDR-BZA sec.Proposed safety related track repairs in SSE/P.Way /CLX, BPP and TEL sections of ADEN/BPP Sub- Division. SW-II) BZA Division: BZA-VSKP sec.Proposed safety related track repairs in SSE/P.Way /Eluru & Nuzvid sections of ADEN/Eluru Sub- Division. SW-III) BZA Division: GDR-BZA sec. Transportation of P.Way materials for scattered and casual renewals Departmentally and for collection scrap in yards for the year 2015-16 in ADEN/BPP sub-division. SW-IV) BZA Division: BZA - VSKP Sec. Transportation of P.Way materials for scattered and casual renewals Departmentally and for collection scrap in yards for the year 2015-16 in ADEN/EE sub-division. SW-V) BZA Division: GDR-BZA sec.: TFR - Through fitting renewal for a length of 65.45km (without ERC) and 1.46km (with all fittings) on up & Dn lines in ADEN/Bapatla Sub-division. SW-VI) BZA Division: GDR-BZA sec.KCC: Shifiting of crossover S103A &B towards Gudur duly making TRD and S&T alterations in KCC yard in ADEN/BPP sub-division SW-VII) BZA Division: GDR-BZA sec. KCC- Shifting of layout of crossover S121 in KCC yard in ADEN/BPP sub-division. SW-VIII) BZA Division: GDR-BZA sec. KCC - Replacement of
Non-standard diamond crossing at KCC yard Pt No. 144A,B & 145 A,B in KCC yard in ADEN/BPP sub-division. . . .
ANNEXURE - I
COMPETENCY CERTIFICATE
Certified that Shri………………………………………………….
P.Way supervisor of M/s. …………………………… has been
Examined regarding P.Way working on ………………………….
Work. His knowledge has been found satisfactory and he is capable of
Supervising the work safely.
ASSISTANT ENGINEER
78
Tender No. 03/Central/2016
Sr.DEN/Central/BZA Signature of Tenderer(s)
Page 78 of 91 BZA Divn., SCR, T.No.03/Central/2016 invited vide Open Tender No.DRM/Works/BZA/03/2016 dt. 05.02.2016, date of opening on 08.03.2016 for the work of SW-I) BZA Division: GDR-BZA sec.Proposed safety related track repairs in SSE/P.Way /CLX, BPP and TEL sections of ADEN/BPP Sub- Division. SW-II) BZA Division: BZA-VSKP sec.Proposed safety related track repairs in SSE/P.Way /Eluru & Nuzvid sections of ADEN/Eluru Sub- Division. SW-III) BZA Division: GDR-BZA sec. Transportation of P.Way materials for scattered and casual renewals Departmentally and for collection scrap in yards for the year 2015-16 in ADEN/BPP sub-division. SW-IV) BZA Division: BZA - VSKP Sec. Transportation of P.Way materials for scattered and casual renewals Departmentally and for collection scrap in yards for the year 2015-16 in ADEN/EE sub-division. SW-V) BZA Division: GDR-BZA sec.: TFR - Through fitting renewal for a length of 65.45km (without ERC) and 1.46km (with all fittings) on up & Dn lines in ADEN/Bapatla Sub-division. SW-VI) BZA Division: GDR-BZA sec.KCC: Shifiting of crossover S103A &B towards Gudur duly making TRD and S&T alterations in KCC yard in ADEN/BPP sub-division SW-VII) BZA Division: GDR-BZA sec. KCC- Shifting of layout of crossover S121 in KCC yard in ADEN/BPP sub-division. SW-VIII) BZA Division: GDR-BZA sec. KCC - Replacement of
Non-standard diamond crossing at KCC yard Pt No. 144A,B & 145 A,B in KCC yard in ADEN/BPP sub-division. . . .
ANNEXURE – II
CHECK LIST
(BEFORE STARTING THE WORK)
Name of the work : ………………………………………………………………………………
Location …………………………………………………………………………………………
Duration of the work : From …………………………… To …………………………………
Sl.
No Details Yes No
1 Contractor‟s supervisor identified / Selected. Who is going to
be site in-charge?
2 Training imparted to contractors supervisor & Certificate
issued?
3 Work site inspected by Constructions supervisor / other
department‟s supervisors along with contractor‟s supervisor?
4 Precautions to be taken identified and listed?
5 Plan of work, drawn out by contractor‟s supervisor in
consultation with Railway‟s supervisor?
6 Plan of work, brought to the knowledge of open line
AEN/IOW & PWI?
7 Before start of the work, proper lime marking / barricading
had done at site of work?
8 Men deputed for protection of track along with safety
equipments?
9 Caution order issued for the train drivers in case work is being
done within 6mts of centre of running track?
10 Drivers of vehicles/machinery being used have been
identified?
11 Drivers of vehicles/machinery briefed about the safe working?
12 Sufficient lighting provided at site of work for night working?
13 Infringements checked?
14 Sectional (Open line) AEN/PWI/IOW have satisfied
themselves regarding safety arrangements?
15 Availability of Walkie –Talkie sets for communication?
Signature of construction/
Other departments Supervisor
Date: Signature of Open line‟s Supervisor.
79
Tender No. 03/Central/2016
Sr.DEN/Central/BZA Signature of Tenderer(s)
Page 79 of 91 BZA Divn., SCR, T.No.03/Central/2016 invited vide Open Tender No.DRM/Works/BZA/03/2016 dt. 05.02.2016, date of opening on 08.03.2016 for the work of SW-I) BZA Division: GDR-BZA sec.Proposed safety related track repairs in SSE/P.Way /CLX, BPP and TEL sections of ADEN/BPP Sub- Division. SW-II) BZA Division: BZA-VSKP sec.Proposed safety related track repairs in SSE/P.Way /Eluru & Nuzvid sections of ADEN/Eluru Sub- Division. SW-III) BZA Division: GDR-BZA sec. Transportation of P.Way materials for scattered and casual renewals Departmentally and for collection scrap in yards for the year 2015-16 in ADEN/BPP sub-division. SW-IV) BZA Division: BZA - VSKP Sec. Transportation of P.Way materials for scattered and casual renewals Departmentally and for collection scrap in yards for the year 2015-16 in ADEN/EE sub-division. SW-V) BZA Division: GDR-BZA sec.: TFR - Through fitting renewal for a length of 65.45km (without ERC) and 1.46km (with all fittings) on up & Dn lines in ADEN/Bapatla Sub-division. SW-VI) BZA Division: GDR-BZA sec.KCC: Shifiting of crossover S103A &B towards Gudur duly making TRD and S&T alterations in KCC yard in ADEN/BPP sub-division SW-VII) BZA Division: GDR-BZA sec. KCC- Shifting of layout of crossover S121 in KCC yard in ADEN/BPP sub-division. SW-VIII) BZA Division: GDR-BZA sec. KCC - Replacement of
Non-standard diamond crossing at KCC yard Pt No. 144A,B & 145 A,B in KCC yard in ADEN/BPP sub-division. . . .
ANNEXURE – III
CHECK LIST
( WHILE WORK IN PROGRESS )
Name of the work : ………………………………………………………………………………
Location …………………………………………………………………………………………
Duration of the work: From …………………………… To …………………………………
Date of inspection ……………………………………………………
Sl.N
o Details Yes No
1 Does the contractor‟s supervisor have the certificate?
2 Does the knowledge of contractor‟s supervisor on safety of
track & work site is up to the mark?
3 Is the Railway‟s supervisor of Construction
Organization/other departments available at site?
4 Is knowledge of Railway‟s supervisor O.K.?
5 Is lime marking/barricading done?
6 Are adequate safety precaution taken?
7 Are communication facility (Walkie – Talkie sets) available at
site?
8 Are only identified drivers driving the vehicles/machinery?
9 Is whole work site safe for working of men/vehicles & trains?
10 Are adequate lighting arrangements done at site?
11 Are adequate protection equipment available at site?
12 Is caution order to trains being issued?
13 Are train drivers following the enforced temporary speed
restriction?
14 Has work permit been taken for working in Electrified
territory/Station yards (P &C areas)
Signature of inspecting officer
Designation
80
Tender No. 03/Central/2016
Sr.DEN/Central/BZA Signature of Tenderer(s)
Page 80 of 91 BZA Divn., SCR, T.No.03/Central/2016 invited vide Open Tender No.DRM/Works/BZA/03/2016 dt. 05.02.2016, date of opening on 08.03.2016 for the work of SW-I) BZA Division: GDR-BZA sec.Proposed safety related track repairs in SSE/P.Way /CLX, BPP and TEL sections of ADEN/BPP Sub- Division. SW-II) BZA Division: BZA-VSKP sec.Proposed safety related track repairs in SSE/P.Way /Eluru & Nuzvid sections of ADEN/Eluru Sub- Division. SW-III) BZA Division: GDR-BZA sec. Transportation of P.Way materials for scattered and casual renewals Departmentally and for collection scrap in yards for the year 2015-16 in ADEN/BPP sub-division. SW-IV) BZA Division: BZA - VSKP Sec. Transportation of P.Way materials for scattered and casual renewals Departmentally and for collection scrap in yards for the year 2015-16 in ADEN/EE sub-division. SW-V) BZA Division: GDR-BZA sec.: TFR - Through fitting renewal for a length of 65.45km (without ERC) and 1.46km (with all fittings) on up & Dn lines in ADEN/Bapatla Sub-division. SW-VI) BZA Division: GDR-BZA sec.KCC: Shifiting of crossover S103A &B towards Gudur duly making TRD and S&T alterations in KCC yard in ADEN/BPP sub-division SW-VII) BZA Division: GDR-BZA sec. KCC- Shifting of layout of crossover S121 in KCC yard in ADEN/BPP sub-division. SW-VIII) BZA Division: GDR-BZA sec. KCC - Replacement of
Non-standard diamond crossing at KCC yard Pt No. 144A,B & 145 A,B in KCC yard in ADEN/BPP sub-division. . . .
ANNEXURE – IV
(A)Marking of Line with Lime
3500mm
150 mm wide white line with lime
Vehicle / trucks can ply in this` area
(B) Provision of Barricading
3500mm Barricading
Luminous tape/Red Colour Nylon Rope 12 mm thick
Post (Bamboo / Steel / Concrete)
1200mm
3500mm 3500mm 3500 mm
C) Elevation of Barricading
81
Tender No. 03/Central/2016
Sr.DEN/Central/BZA Signature of Tenderer(s)
Page 81 of 91 BZA Divn., SCR, T.No.03/Central/2016 invited vide Open Tender No.DRM/Works/BZA/03/2016 dt. 05.02.2016, date of opening on 08.03.2016 for the work of SW-I) BZA Division: GDR-BZA sec.Proposed safety related track repairs in SSE/P.Way /CLX, BPP and TEL sections of ADEN/BPP Sub- Division. SW-II) BZA Division: BZA-VSKP sec.Proposed safety related track repairs in SSE/P.Way /Eluru & Nuzvid sections of ADEN/Eluru Sub- Division. SW-III) BZA Division: GDR-BZA sec. Transportation of P.Way materials for scattered and casual renewals Departmentally and for collection scrap in yards for the year 2015-16 in ADEN/BPP sub-division. SW-IV) BZA Division: BZA - VSKP Sec. Transportation of P.Way materials for scattered and casual renewals Departmentally and for collection scrap in yards for the year 2015-16 in ADEN/EE sub-division. SW-V) BZA Division: GDR-BZA sec.: TFR - Through fitting renewal for a length of 65.45km (without ERC) and 1.46km (with all fittings) on up & Dn lines in ADEN/Bapatla Sub-division. SW-VI) BZA Division: GDR-BZA sec.KCC: Shifiting of crossover S103A &B towards Gudur duly making TRD and S&T alterations in KCC yard in ADEN/BPP sub-division SW-VII) BZA Division: GDR-BZA sec. KCC- Shifting of layout of crossover S121 in KCC yard in ADEN/BPP sub-division. SW-VIII) BZA Division: GDR-BZA sec. KCC - Replacement of
Non-standard diamond crossing at KCC yard Pt No. 144A,B & 145 A,B in KCC yard in ADEN/BPP sub-division. . . .
ANNEXURE –V
A) Plying of Vehicles/Machinery between 3.5 mts.
to 6.0 mts from centre of track
3500mm
Contractor‟s supervisor Railway‟s supervisor
150 mm wide white line with lime
6000mm
B) Plying of Vehicles / Machinery within 3.5 mts from center of track
DN LINE
Banner flag in day time / HS lamps in night
detonators
P LINE
1200 metres
3500mm detonators
Contractor‟s supervisor Railway‟s supervisor
82
Tender No. 03/Central/2016
Sr.DEN/Central/BZA Signature of Tenderer(s)
Page 82 of 91 BZA Divn., SCR, T.No.03/Central/2016 invited vide Open Tender No.DRM/Works/BZA/03/2016 dt. 05.02.2016, date of opening on 08.03.2016 for the work of SW-I) BZA Division: GDR-BZA sec.Proposed safety related track repairs in SSE/P.Way /CLX, BPP and TEL sections of ADEN/BPP Sub- Division. SW-II) BZA Division: BZA-VSKP sec.Proposed safety related track repairs in SSE/P.Way /Eluru & Nuzvid sections of ADEN/Eluru Sub- Division. SW-III) BZA Division: GDR-BZA sec. Transportation of P.Way materials for scattered and casual renewals Departmentally and for collection scrap in yards for the year 2015-16 in ADEN/BPP sub-division. SW-IV) BZA Division: BZA - VSKP Sec. Transportation of P.Way materials for scattered and casual renewals Departmentally and for collection scrap in yards for the year 2015-16 in ADEN/EE sub-division. SW-V) BZA Division: GDR-BZA sec.: TFR - Through fitting renewal for a length of 65.45km (without ERC) and 1.46km (with all fittings) on up & Dn lines in ADEN/Bapatla Sub-division. SW-VI) BZA Division: GDR-BZA sec.KCC: Shifiting of crossover S103A &B towards Gudur duly making TRD and S&T alterations in KCC yard in ADEN/BPP sub-division SW-VII) BZA Division: GDR-BZA sec. KCC- Shifting of layout of crossover S121 in KCC yard in ADEN/BPP sub-division. SW-VIII) BZA Division: GDR-BZA sec. KCC - Replacement of
Non-standard diamond crossing at KCC yard Pt No. 144A,B & 145 A,B in KCC yard in ADEN/BPP sub-division. . . .
SPECIAL CONDITIONS (INDIAN RAILWAYS - TRACK WORKS)
1. The sleepers, rails and fastenings will be supplied by the Railways at for
carrying out the work
2. All the released materials as per the inventory taken by the ADEN/PWI
has to truck out the materials and hand over to the department depot by the contractor, if
any loss or damage occurred for the released materials, the cost of the same which will
recovered from the contractor‟s bills as per the extent rules and certificate in the bill has
to be furnished by the ADEN/PWI stating that all the released materials are returned and
accounted for the relevant register duly giving page No and date.
3. No plant or machinery will be supplied by the Railway for this work. It is the
contractor‟s responsibility to supply at his own cost, any materials and plant, machinery
required for this work.
4.Sales tax Royalty fees, and control duties if any be payable under State Government
sales Tax Act or Local bodies Act or rules on any of the materials that may be used or
supplied by the Contractor will be payable by the contractor. The Railway will neither
pay the taxes nor duties not be bound to compensate the contractor for any amounts paid
by way of these taxes or duties.
5. For any items of work in the event of these being any conflict in the working or
drawing referred to in the schedule and specifications of work, ;the former shall prevail.
The decision of Engineer-in-charge will be final in all such matters.
6. Use of raw materials secured with Government assistance where any raw materials
for the executing of the contract are procured with the assistance of Government either
by issue from Government stocks or purchased under arrangements made on permits of
license issued by the Government, the contractor shall hold the said materials as trustee
for Government and use such materials economically and solely for the purpose of the
contract against which they are issued and not disposed them without the permission of
Government and returned if required by the purchaser all surplus of unserviceable
materials that may be left with him after completion of the contract as Government may
fix the due regard to the condition of the materials The freight charges for the return if
the materials according to the direction of the purchase shall be borned by the
Contractor, in the event of the decision of Government shall be final and conclusive. In
the event of any breach of the afore said condition, ;the contractor shall in addition to the
owing himself open action for contravention of terms of the licenses, the permit and for
any reason whatsoever on his being paid such price or for original breach of trust be
liable for account to government for all money advantageous or profit resulting of which
is in the usual course and would have resulted him by reason of breach.
83
Tender No. 03/Central/2016
Sr.DEN/Central/BZA Signature of Tenderer(s)
Page 83 of 91 BZA Divn., SCR, T.No.03/Central/2016 invited vide Open Tender No.DRM/Works/BZA/03/2016 dt. 05.02.2016, date of opening on 08.03.2016 for the work of SW-I) BZA Division: GDR-BZA sec.Proposed safety related track repairs in SSE/P.Way /CLX, BPP and TEL sections of ADEN/BPP Sub- Division. SW-II) BZA Division: BZA-VSKP sec.Proposed safety related track repairs in SSE/P.Way /Eluru & Nuzvid sections of ADEN/Eluru Sub- Division. SW-III) BZA Division: GDR-BZA sec. Transportation of P.Way materials for scattered and casual renewals Departmentally and for collection scrap in yards for the year 2015-16 in ADEN/BPP sub-division. SW-IV) BZA Division: BZA - VSKP Sec. Transportation of P.Way materials for scattered and casual renewals Departmentally and for collection scrap in yards for the year 2015-16 in ADEN/EE sub-division. SW-V) BZA Division: GDR-BZA sec.: TFR - Through fitting renewal for a length of 65.45km (without ERC) and 1.46km (with all fittings) on up & Dn lines in ADEN/Bapatla Sub-division. SW-VI) BZA Division: GDR-BZA sec.KCC: Shifiting of crossover S103A &B towards Gudur duly making TRD and S&T alterations in KCC yard in ADEN/BPP sub-division SW-VII) BZA Division: GDR-BZA sec. KCC- Shifting of layout of crossover S121 in KCC yard in ADEN/BPP sub-division. SW-VIII) BZA Division: GDR-BZA sec. KCC - Replacement of
Non-standard diamond crossing at KCC yard Pt No. 144A,B & 145 A,B in KCC yard in ADEN/BPP sub-division. . . .
7. The work shall be maintained by the contractor after certified date of completion for a
period of two months and he will make good any defects imperfections, shrinkage or
faults which may appear during the period of maintenance at his own cost.
8. If due to any reason, the Railway is not in a position to make available the Railway
Land the Railway Engineer-in-charge of the work may permit the contractor to erect at
his own cost shed, sheds or secure private accommodation out side the Railway
premises. In such a case, the contractor may be permitted to take the Railway materials
required for the work out side the Railway premises and to store in the shed so erected
or private accommodation, so secured. It shall be the responsibility of the contractor to
keep the entirely separate from the Contractor‟s materials and the Railway shall be at
liberty to inspect the same time to time.
9.SPEED RESTRICTIONS
9.1 Speed restrictions as required for safety of traffic will be arranged by the Engineer-
in-charge. No work on the track should be completed until the permanent way
Inspector of the Railway has imposed the speed restrictions are erected speed
indicators.
9.2 After a speed restriction is imposed, the contractor shall progress with work in a
systematic manner.
9.3 Long length of track under speed restrictions should avoided.
9.4 If the contractor fails to employs adequate labour for attention to the track so as to
permit the train to go at restricted speed, the Railway will take action to employ
such labour as it is necessary at the risk and cost of the contractor to attend to track
and make it fit for passage if trains at the prescribed speed.
9.5 Caution watchman as necessary during day and night would be arranged for free by
the Railway.
9.6 The work should be executed in a work man like manner to the satisfaction of the
Engineer-in-charge. In the event of any accident at the work spot departmental
enquiry will be held by the Railway or enquiry by CRS will be held. If it is
established that the accident occurred wholly or partly due to any act tentamounting
to negligence on the part of the contractor or his labour, the contractor shall render
himself liable for all damage and also legal prosecution if loss of life is involved.
10. Contractor‟s supervision.
10.1 The Contractor shall employ and post at site a technical supervisor who should be
adequately qualified and well experienced in execution of Permanent Way Works.
The name, particulars of technical qualifications and record of experience of the
supervisor employed should be advised to the Engineer-in-charge. If in the opinion
of the Engineer-in-charge the supervisor is not fit to be in-charge of the work
should be forth with replaced. In this matter, the opinion of the Engineer-in-charge
will be final and binding on the contract.
84
Tender No. 03/Central/2016
Sr.DEN/Central/BZA Signature of Tenderer(s)
Page 84 of 91 BZA Divn., SCR, T.No.03/Central/2016 invited vide Open Tender No.DRM/Works/BZA/03/2016 dt. 05.02.2016, date of opening on 08.03.2016 for the work of SW-I) BZA Division: GDR-BZA sec.Proposed safety related track repairs in SSE/P.Way /CLX, BPP and TEL sections of ADEN/BPP Sub- Division. SW-II) BZA Division: BZA-VSKP sec.Proposed safety related track repairs in SSE/P.Way /Eluru & Nuzvid sections of ADEN/Eluru Sub- Division. SW-III) BZA Division: GDR-BZA sec. Transportation of P.Way materials for scattered and casual renewals Departmentally and for collection scrap in yards for the year 2015-16 in ADEN/BPP sub-division. SW-IV) BZA Division: BZA - VSKP Sec. Transportation of P.Way materials for scattered and casual renewals Departmentally and for collection scrap in yards for the year 2015-16 in ADEN/EE sub-division. SW-V) BZA Division: GDR-BZA sec.: TFR - Through fitting renewal for a length of 65.45km (without ERC) and 1.46km (with all fittings) on up & Dn lines in ADEN/Bapatla Sub-division. SW-VI) BZA Division: GDR-BZA sec.KCC: Shifiting of crossover S103A &B towards Gudur duly making TRD and S&T alterations in KCC yard in ADEN/BPP sub-division SW-VII) BZA Division: GDR-BZA sec. KCC- Shifting of layout of crossover S121 in KCC yard in ADEN/BPP sub-division. SW-VIII) BZA Division: GDR-BZA sec. KCC - Replacement of
Non-standard diamond crossing at KCC yard Pt No. 144A,B & 145 A,B in KCC yard in ADEN/BPP sub-division. . . .
10.2 No work on the track should done unless and until the PWI, Contractor‟s technical
supervisor is present at site.
11. The completion period for the entire work is the essence of the contract and suitable
arrangements should be made for the progressive execution of the work so that the
entire work is completed within 11 months from the date of issue of letter of
acceptance of the tender.
12. The minimum progress for the complete track renewals and through sleeper
renewals and the penalties for slow progress is as under vide this office letter No.
B/w.496/I/4 dated 17-2-1988.
i) For CTR and TSR works 3 (three) kms per month.
ii) For TRR and Deep screening work 4 (four) kms per month
iii) For every lineal metre of shortage, recovery of the following rates should
be made from the contractor‟s bills.
Complete track renewals Rs.10/- per metre of shortage.
a) Through sleeper renewals Rs.8/- per metre of shortage
b) Deep screening Rs.6/- per metre of shortage
c) Through rail renewals Rs.4/- per metre of shortage
13. The quantities shown in the tender schedule are approximate and will be operated in
full or part at the discretion of the Engineer-in-charge.
14. Payment will be made based on actual quantity/items operated.
15. The existing rails, sleepers and fastenings from the track shall be removed including
excavation, etc., with utmost care to avoid any damage to the rails, sleepers, and
fastenings, etc., shall be neatly removed re-laid and balance of released materials should
be handed over to the PWI concerned at his depot.
16. The contractor shall carry out the work in such a manner to avoid any inconvenience
and disturbance to Railway working and to the public using the railway premises and
will adjusts the program of the work accordingly in consultation with the engineer-in-
charge.
17. The Railway administration will not be responsible for the safety of contractor‟s
labour engaged for their work and should be ensured that all the labour are medically fit
with good eye sight so that they can safe guard themselves.
18. The work must be supervised by PWI. No work is carried out by the contractor
unless PWI in charge of the work is at site. It is necessary that safety of the track is
ensured by the PWI in-charge supervising the work.
85
Tender No. 03/Central/2016
Sr.DEN/Central/BZA Signature of Tenderer(s)
Page 85 of 91 BZA Divn., SCR, T.No.03/Central/2016 invited vide Open Tender No.DRM/Works/BZA/03/2016 dt. 05.02.2016, date of opening on 08.03.2016 for the work of SW-I) BZA Division: GDR-BZA sec.Proposed safety related track repairs in SSE/P.Way /CLX, BPP and TEL sections of ADEN/BPP Sub- Division. SW-II) BZA Division: BZA-VSKP sec.Proposed safety related track repairs in SSE/P.Way /Eluru & Nuzvid sections of ADEN/Eluru Sub- Division. SW-III) BZA Division: GDR-BZA sec. Transportation of P.Way materials for scattered and casual renewals Departmentally and for collection scrap in yards for the year 2015-16 in ADEN/BPP sub-division. SW-IV) BZA Division: BZA - VSKP Sec. Transportation of P.Way materials for scattered and casual renewals Departmentally and for collection scrap in yards for the year 2015-16 in ADEN/EE sub-division. SW-V) BZA Division: GDR-BZA sec.: TFR - Through fitting renewal for a length of 65.45km (without ERC) and 1.46km (with all fittings) on up & Dn lines in ADEN/Bapatla Sub-division. SW-VI) BZA Division: GDR-BZA sec.KCC: Shifiting of crossover S103A &B towards Gudur duly making TRD and S&T alterations in KCC yard in ADEN/BPP sub-division SW-VII) BZA Division: GDR-BZA sec. KCC- Shifting of layout of crossover S121 in KCC yard in ADEN/BPP sub-division. SW-VIII) BZA Division: GDR-BZA sec. KCC - Replacement of
Non-standard diamond crossing at KCC yard Pt No. 144A,B & 145 A,B in KCC yard in ADEN/BPP sub-division. . . .
19. At any stage during the execution of work, if contractor fails to employ adequate
labour to complete the works in traffic blocks to raise the speed by rear packing and
restore traffic etc., as decided by the Engineer in charge such work will be carried out by
deploying departmental labour at the cost of contractor, without prejudice to action as
per GCC in clause 62 and recovery of cost of such labour shall be made from
contractor‟s bill as per extent rules.
20.Vehicles and equipment of contractors can be drafted by Railway administration in case
of accidents/natural calamities involving human lives. However, the number of hours,
the equipment put to use is to be compensated as per prevailing rtes inclusive of fuel
charges on actual basis.
Place: Vijayawada
Date: / / 2015.
SIGNATURE OF TENDERER(S)
86
Tender No. 03/Central/2016
Sr.DEN/Central/BZA Signature of Tenderer(s)
Page 86 of 91 BZA Divn., SCR, T.No.03/Central/2016 invited vide Open Tender No.DRM/Works/BZA/03/2016 dt. 05.02.2016, date of opening on 08.03.2016 for the work of SW-I) BZA Division: GDR-BZA sec.Proposed safety related track repairs in SSE/P.Way /CLX, BPP and TEL sections of ADEN/BPP Sub- Division. SW-II) BZA Division: BZA-VSKP sec.Proposed safety related track repairs in SSE/P.Way /Eluru & Nuzvid sections of ADEN/Eluru Sub- Division. SW-III) BZA Division: GDR-BZA sec. Transportation of P.Way materials for scattered and casual renewals Departmentally and for collection scrap in yards for the year 2015-16 in ADEN/BPP sub-division. SW-IV) BZA Division: BZA - VSKP Sec. Transportation of P.Way materials for scattered and casual renewals Departmentally and for collection scrap in yards for the year 2015-16 in ADEN/EE sub-division. SW-V) BZA Division: GDR-BZA sec.: TFR - Through fitting renewal for a length of 65.45km (without ERC) and 1.46km (with all fittings) on up & Dn lines in ADEN/Bapatla Sub-division. SW-VI) BZA Division: GDR-BZA sec.KCC: Shifiting of crossover S103A &B towards Gudur duly making TRD and S&T alterations in KCC yard in ADEN/BPP sub-division SW-VII) BZA Division: GDR-BZA sec. KCC- Shifting of layout of crossover S121 in KCC yard in ADEN/BPP sub-division. SW-VIII) BZA Division: GDR-BZA sec. KCC - Replacement of
Non-standard diamond crossing at KCC yard Pt No. 144A,B & 145 A,B in KCC yard in ADEN/BPP sub-division. . . .
ANNEXURE - A
SPECIFICATIONS FOR GALVANISATION:
Galvanising of MS liners (T-3738/3740/3741/3742) shall be done by hot dip process of thickness not less than 100 microns with zinc conforming to IS 209-1979 (latest).
1.0: SCOPE:
1.1: This standard specifies the requirements for zinc coating applied by hot dip galvanizing and criteria for sampling and inspection of such galvanized members.
2.0 GENERAL REQUIREMENTS:
2.1 Quality of Zinc: Zinc confirming to at least grade 99.5 specified in IS 209-1979 (latest) shall be used for the purpose of galvanization.
2.2.1: Surface preparation: Surface preparation shall be as per Clause 4 of IS.2629-1966. Shot or sand blasting may be used.
2.2: Base Metal: Requirement shall be in accordance with clauses 2.1 to 2.1.3 of IS.6158-1971.
2.3 Galvanising: The MS liners may be galvanised as per the IS.2629/1966 and IS.4759-1984 unless otherwise specified in the succeeding paragraphs.
3.0: COATING REQUIREMENT:
3,1. Mass of Zinc coating: The requirement for the mass of Zinc coating for all steel structure shall not be less than 705g/Sq.m and the galvanization thickness shall not be less than 100 microns.
3.2: Freedom from defects: The Zinc coating shall be uniform, adherent, reasonably smooth and free from imperfections such as fluk, ash and doss inclusions; bars patches, black spots, pimples, lumpiness and runs, rust stains, bulky white deposits and blisters. These terms have been; defined in IS.2629-1966, which as amended is enclosed at Appendix-“A”.
4.0: SAMPLING AND CRITERIA FOR CONFORMITY:
4.1: The following sampling plan shall be followed for ascertaining the conformity of galvanised coating.
4.2: Lot All rolled and fabricated sleepers galvanised to a coating bath and comprising of one complete day turnover shall constitute a lot. For all others, materials of the same type in a coating bath whose coating characteristics are intended to be uniform shall form a lot.
4.3: Samples shall be taken from each lot and tested for conformity of coating. A test piece of mild steel plates of 6mm thick and of size 100 x 100mm shall be used as sampling piece.
4.4: Scale of sampling: The number of units to be selected from a bath shall be in accordance with column 1 and 2 of the Table given below:
TABLE – SCALE OF SAMPLING
Lot size (No. of units)
Sample size Permissible No. of defective units
Upto 25 3 0
87
Tender No. 03/Central/2016
Sr.DEN/Central/BZA Signature of Tenderer(s)
Page 87 of 91 BZA Divn., SCR, T.No.03/Central/2016 invited vide Open Tender No.DRM/Works/BZA/03/2016 dt. 05.02.2016, date of opening on 08.03.2016 for the work of SW-I) BZA Division: GDR-BZA sec.Proposed safety related track repairs in SSE/P.Way /CLX, BPP and TEL sections of ADEN/BPP Sub- Division. SW-II) BZA Division: BZA-VSKP sec.Proposed safety related track repairs in SSE/P.Way /Eluru & Nuzvid sections of ADEN/Eluru Sub- Division. SW-III) BZA Division: GDR-BZA sec. Transportation of P.Way materials for scattered and casual renewals Departmentally and for collection scrap in yards for the year 2015-16 in ADEN/BPP sub-division. SW-IV) BZA Division: BZA - VSKP Sec. Transportation of P.Way materials for scattered and casual renewals Departmentally and for collection scrap in yards for the year 2015-16 in ADEN/EE sub-division. SW-V) BZA Division: GDR-BZA sec.: TFR - Through fitting renewal for a length of 65.45km (without ERC) and 1.46km (with all fittings) on up & Dn lines in ADEN/Bapatla Sub-division. SW-VI) BZA Division: GDR-BZA sec.KCC: Shifiting of crossover S103A &B towards Gudur duly making TRD and S&T alterations in KCC yard in ADEN/BPP sub-division SW-VII) BZA Division: GDR-BZA sec. KCC- Shifting of layout of crossover S121 in KCC yard in ADEN/BPP sub-division. SW-VIII) BZA Division: GDR-BZA sec. KCC - Replacement of
Non-standard diamond crossing at KCC yard Pt No. 144A,B & 145 A,B in KCC yard in ADEN/BPP sub-division. . . .
ANNEXURE - A
SPECIFICATIONS FOR GALVANISATION:
26 to 50 5 0
51 to 100 8 0
101 and above in bath
13 1
4.5. Tests for visual inspection:
4.5.1 Visual inspection of the material in a lot shall be made to determine the conformity with the requirements of 3.2. If the inspection warrants rejection of the lot, the galvaniser may segregate the good pieces of the lot ;and submit it once again for inspection.
4.5.2: If the lot inspected for visual inspection passes, then the lot shall be declared as conforming to requirements of 3.2.
4.6: Number of tests for coating characteristics:
4.6.1: Actual products may be used as test specimen.
4.6.2: Each sample shall be tested by testing one test specimen. In case the first test specimen representing a sample unit fails to conform to the requirements specified in 5,the second and the third specimens shall be tested. If any one of the second or third specimens fails to conform to the requirements, the sample unit shall be considered defective. If the number of defective units in a lot exceed permissible number specified in the above table, the lot shall be rejected.
4.6.3: The materials in a lot, which have been rejected, may be stripped and re-galvanised and again submitted for inspection and tests.
4.6.4: The lot shall be declared as conforming to the specification of 4.6.2 is satisfied.
5.0: TEST PROCEDURE FOR MASS OR GALVANISED COATING:
5.1: The mass of galvanised coating shall be determined by any of the method as mentioned below, as mutually agreed between the Railway and galvaniser.
5.1.1: Stripping method:
5.1.1.1: Cleaning of test piece: The test pieces shall be washed with solvent naphtha, trichloroethvlene or any other suitable organic solvent, followed by alcohol and finally dried thoroughly.
5.1.1.2: Stripping solution: Dissolve 20g. of Antimony Trioxide (Sb2 03) or 32gm, of Antimony Trichloride (Sb C in 100ml., of concentrated Hydrochloric Acid (specific gravity 1.16).
5.1.1.3: Immediately before tests, prepare the stripping solution by adding 5ml. Of the solution prepared under 5.1.1.2 to 100ml. Of concentrated Hydrochloric Acid (Specific gravity 1.16). Mix well.
5.1.1.4: Procedure: (I.S:6745-1972): weight and cleaned test specimen whose mass is less than 200g. Nearest to 0.01g for test pieces whose mass is between 300 to 1000g. Weight to the nearest 0.1g and for masses over 1000g., the accuracy of weighing Shall be nearest to 0.5g after weighing immerse each test piece singly in test solution prepared in 5.1.1.2 and allow to remain there until the violent evolution of Hydrogen ceases and only a few bubbles are being evolved. This requires about I5 to 30 secs.
88
Tender No. 03/Central/2016
Sr.DEN/Central/BZA Signature of Tenderer(s)
Page 88 of 91 BZA Divn., SCR, T.No.03/Central/2016 invited vide Open Tender No.DRM/Works/BZA/03/2016 dt. 05.02.2016, date of opening on 08.03.2016 for the work of SW-I) BZA Division: GDR-BZA sec.Proposed safety related track repairs in SSE/P.Way /CLX, BPP and TEL sections of ADEN/BPP Sub- Division. SW-II) BZA Division: BZA-VSKP sec.Proposed safety related track repairs in SSE/P.Way /Eluru & Nuzvid sections of ADEN/Eluru Sub- Division. SW-III) BZA Division: GDR-BZA sec. Transportation of P.Way materials for scattered and casual renewals Departmentally and for collection scrap in yards for the year 2015-16 in ADEN/BPP sub-division. SW-IV) BZA Division: BZA - VSKP Sec. Transportation of P.Way materials for scattered and casual renewals Departmentally and for collection scrap in yards for the year 2015-16 in ADEN/EE sub-division. SW-V) BZA Division: GDR-BZA sec.: TFR - Through fitting renewal for a length of 65.45km (without ERC) and 1.46km (with all fittings) on up & Dn lines in ADEN/Bapatla Sub-division. SW-VI) BZA Division: GDR-BZA sec.KCC: Shifiting of crossover S103A &B towards Gudur duly making TRD and S&T alterations in KCC yard in ADEN/BPP sub-division SW-VII) BZA Division: GDR-BZA sec. KCC- Shifting of layout of crossover S121 in KCC yard in ADEN/BPP sub-division. SW-VIII) BZA Division: GDR-BZA sec. KCC - Replacement of
Non-standard diamond crossing at KCC yard Pt No. 144A,B & 145 A,B in KCC yard in ADEN/BPP sub-division. . . .
ANNEXURE - A
SPECIFICATIONS FOR GALVANISATION:
5.1.1.5: The mass of Zinc coating of g/m sq. of surface may be calculated as per the following formula: -
M = M1 – M2 x t x 3930
M2
Where M= Mass of Zinc locating in g/m sq. of surface.
M1 = Original Mass in gm., of test piece
M2 = Mass in gm of stripped test piece, and
t = thickness of the stripped test piece in mm.
5.1.2.: Magnetic or microscopic method as per IS: 3203-1965 ireddy current method ;as per IS:6012-1970 may be employed to determine the thickness of coating. The mass of coating in g/m sq. Shall then be calculated by multiplying the thickness in mm. by a factor 7047.
5.2: Determination of Uniformity of galvanised coating: where practicable the uniformity of galvanised coating shall be determined by the Preece test as prescribed in IS.2633-1972. The article should withstand four 1-minute dips.
5.3: Adhesion of galvanised coating: 6 coating shall withstand; the pivoted hammer and knife test as prescribed in IS:2629-1966.
6.0: INSPECTION:
6.1; Visual inspection of material shall be made to determine conformity with the requirement of 3.2 when partial inspection warrants rejection of a lot, the Galvaniser may reject the lot and submit it once again for inspection.
6.2: Should one specimen/specimens fail to conform to the requirements specified in 5 for the mass of coating the second and third specimen/specimens shall be tested. Failure of either the second or third specimen/specimens to conform to the requirement shall be the cause for rejection of the lot which the samples represent.
6.3: Materials that have been rejected may be stripped and re-galvanised and re-submitted for inspection and test when they shall conform to the requirements of this specification, otherwise the entire lot shall be rejected.
7.0: RECTIFICATION OF DAMAGE:
7.1; Normally all fabrication work in the case of galvanised articles shall be completed prior to galvanising. If for any reason, fabrication such as cutting, drilling or welding has to be under taken after galvanising, protection of metal exposed as a result of fabrication and rectification of damaged galvanised areas shall be done in accordance with either of the following methods or any other method approved by the Railway Administration.
89
Tender No. 03/Central/2016
Sr.DEN/Central/BZA Signature of Tenderer(s)
Page 89 of 91 BZA Divn., SCR, T.No.03/Central/2016 invited vide Open Tender No.DRM/Works/BZA/03/2016 dt. 05.02.2016, date of opening on 08.03.2016 for the work of SW-I) BZA Division: GDR-BZA sec.Proposed safety related track repairs in SSE/P.Way /CLX, BPP and TEL sections of ADEN/BPP Sub- Division. SW-II) BZA Division: BZA-VSKP sec.Proposed safety related track repairs in SSE/P.Way /Eluru & Nuzvid sections of ADEN/Eluru Sub- Division. SW-III) BZA Division: GDR-BZA sec. Transportation of P.Way materials for scattered and casual renewals Departmentally and for collection scrap in yards for the year 2015-16 in ADEN/BPP sub-division. SW-IV) BZA Division: BZA - VSKP Sec. Transportation of P.Way materials for scattered and casual renewals Departmentally and for collection scrap in yards for the year 2015-16 in ADEN/EE sub-division. SW-V) BZA Division: GDR-BZA sec.: TFR - Through fitting renewal for a length of 65.45km (without ERC) and 1.46km (with all fittings) on up & Dn lines in ADEN/Bapatla Sub-division. SW-VI) BZA Division: GDR-BZA sec.KCC: Shifiting of crossover S103A &B towards Gudur duly making TRD and S&T alterations in KCC yard in ADEN/BPP sub-division SW-VII) BZA Division: GDR-BZA sec. KCC- Shifting of layout of crossover S121 in KCC yard in ADEN/BPP sub-division. SW-VIII) BZA Division: GDR-BZA sec. KCC - Replacement of
Non-standard diamond crossing at KCC yard Pt No. 144A,B & 145 A,B in KCC yard in ADEN/BPP sub-division. . . .
i).Sticks or rods, 5-10 dia of high purity Zinc shall be used for this purpose. The surface to be protected, or the surface where galvanising has bee damaged , shall be cleaned and any oxides removed with a weak acid solution and a wire brush. The surface shall be thoroughly washed with water to market it free from any traces of acid. The cleaned area may be heated with welding torch and rubbed with white salammonic. A piece of the stick or rod high purity shall be melted on those areas and spread out with a heated piece of salammoniac. The area shall then be washed down by water and lightly wire brushed. The workmen ship shall be such that the finished surface is smooth and non/porous. ii.)The damaged surface after cleaning, as mentioned in para (1) above, shall be painted with two or more coats of Zinc rich primer followed by a finished coat, as per the painting Schedule recommended by the supplier or Zinc rich primer. iii)It is to be ensured that the dry film thickness of Zinc rich primer shall not be less than the average thickness of the galvanised coating. The complete painting system i.e., Zinc rich primer
with the finishing paint for this purpose shall be procured from the same source of repute and as approved by the Railway Administration.
APPENDIX-„A‟ (Clause.3.2)
DEFECTS THEIR CAUSES AND REMEDI –MEASURES
Defects Causes Recommended actions Ground for Rejection
Paint, grease or oil residues. Check cleaning practices
Scale of rush residues Check pickling practices
Bare spots Residual welding slag Blast-clean welds ,avoid coating rods
Yes, if bars spot the bigger than 8m dia
Breakdown of preflux coating Check prefluk and drying conditions
Alluminium content of bath too high.
Regulate aluminium additions
Rolling defects is basic steel Check steel supply
Articles in contact during galvanising
Keep articles separated
General roughness
Analysis of original surface condition of steel
Check steel supply
Over-pickling Reduced pickling, use inhibitor
No
90
Tender No. 03/Central/2016
Sr.DEN/Central/BZA Signature of Tenderer(s)
Page 90 of 91 BZA Divn., SCR, T.No.03/Central/2016 invited vide Open Tender No.DRM/Works/BZA/03/2016 dt. 05.02.2016, date of opening on 08.03.2016 for the work of SW-I) BZA Division: GDR-BZA sec.Proposed safety related track repairs in SSE/P.Way /CLX, BPP and TEL sections of ADEN/BPP Sub- Division. SW-II) BZA Division: BZA-VSKP sec.Proposed safety related track repairs in SSE/P.Way /Eluru & Nuzvid sections of ADEN/Eluru Sub- Division. SW-III) BZA Division: GDR-BZA sec. Transportation of P.Way materials for scattered and casual renewals Departmentally and for collection scrap in yards for the year 2015-16 in ADEN/BPP sub-division. SW-IV) BZA Division: BZA - VSKP Sec. Transportation of P.Way materials for scattered and casual renewals Departmentally and for collection scrap in yards for the year 2015-16 in ADEN/EE sub-division. SW-V) BZA Division: GDR-BZA sec.: TFR - Through fitting renewal for a length of 65.45km (without ERC) and 1.46km (with all fittings) on up & Dn lines in ADEN/Bapatla Sub-division. SW-VI) BZA Division: GDR-BZA sec.KCC: Shifiting of crossover S103A &B towards Gudur duly making TRD and S&T alterations in KCC yard in ADEN/BPP sub-division SW-VII) BZA Division: GDR-BZA sec. KCC- Shifting of layout of crossover S121 in KCC yard in ADEN/BPP sub-division. SW-VIII) BZA Division: GDR-BZA sec. KCC - Replacement of
Non-standard diamond crossing at KCC yard Pt No. 144A,B & 145 A,B in KCC yard in ADEN/BPP sub-division. . . .
High galvanising tempperature or long immersion time or both
Adjust galvanising conditions
Pimples Entrapped dross Avoid agitation of dross layer. Check carry over of pickle salts.
No unless dross contamination is heavy.
Withdrawal speed Remove work slowly.
Lumpiness Cold galvanising and bath Increase temperature
Runs uneven Delayed run-off from seams joints bolts, holes etc.
Remove work slowly No
Articles in contact during withdrawal.
Keep articles separated.
Stale flush burnt on during dipping
Refresh or renew flux blanket.
Flux inclusions Surface residues on steel Check steel preparation.
Yes
Flux picked up from top of bath. Skim before withdrawal.
Ash inclusions Ash burnt on during dipping Skim bath before dipping.
Ash picked from top of bath. Skim bath before withdrawal.
Yes, if the gross lumps.
Black spots Includes flux particles from flux dusting dirt smut
Confine fluxing to top of bath.
Yes
Check storage conditions.
No.
Dull gray coating (all alloy no free Zinc)
Steel composition high silicon, phosphorous (or Carbon) or severe cold work.
Check steel supply for composition order to adjust for galvanising
Slow cooling after galvanising. Avoid hot stacking, quench.
No
Release absorbed Hydrogen during solidification of c coating
Avoid over pickling, use inhibitor
Weeping of acid etc., from seams land floods.
Check product design and fabrication.
91
Tender No. 03/Central/2016
Sr.DEN/Central/BZA Signature of Tenderer(s)
Page 91 of 91 BZA Divn., SCR, T.No.03/Central/2016 invited vide Open Tender No.DRM/Works/BZA/03/2016 dt. 05.02.2016, date of opening on 08.03.2016 for the work of SW-I) BZA Division: GDR-BZA sec.Proposed safety related track repairs in SSE/P.Way /CLX, BPP and TEL sections of ADEN/BPP Sub- Division. SW-II) BZA Division: BZA-VSKP sec.Proposed safety related track repairs in SSE/P.Way /Eluru & Nuzvid sections of ADEN/Eluru Sub- Division. SW-III) BZA Division: GDR-BZA sec. Transportation of P.Way materials for scattered and casual renewals Departmentally and for collection scrap in yards for the year 2015-16 in ADEN/BPP sub-division. SW-IV) BZA Division: BZA - VSKP Sec. Transportation of P.Way materials for scattered and casual renewals Departmentally and for collection scrap in yards for the year 2015-16 in ADEN/EE sub-division. SW-V) BZA Division: GDR-BZA sec.: TFR - Through fitting renewal for a length of 65.45km (without ERC) and 1.46km (with all fittings) on up & Dn lines in ADEN/Bapatla Sub-division. SW-VI) BZA Division: GDR-BZA sec.KCC: Shifiting of crossover S103A &B towards Gudur duly making TRD and S&T alterations in KCC yard in ADEN/BPP sub-division SW-VII) BZA Division: GDR-BZA sec. KCC- Shifting of layout of crossover S121 in KCC yard in ADEN/BPP sub-division. SW-VIII) BZA Division: GDR-BZA sec. KCC - Replacement of
Non-standard diamond crossing at KCC yard Pt No. 144A,B & 145 A,B in KCC yard in ADEN/BPP sub-division. . . .
Rust stains. Storage near rusty material. Check storage condition.
No
Bulky white deposit (wet storage strain white rust.)
Confinement of close packed articles under damp conditions
Store and ship in dry well ventilated conditions separate articles with spacer.
Packing of articles while damp Dry before packing include desiccant.
No
Expansion of entrapped Hydrogen and moisture in flaws.
Check steel quantity.
Blisters. Driving off of Hydrogen absorbed during
Use shot blast instead of pickle check steel supply
Yes, if General
Improper malleablising(for malleable from casting only)
Check malleablising practice.
Tiny blisters. Effect some times observed on quenched work, notably malleable casting. May be caused by gas evolved from the work resulting from absorbed hydrogen or breakdown of combined carbon near surface.
Use shot blast instead of pickle. Check malleable treatment. Should have no combined carbon near surface of coating
Yes, if blistering is generally widespread.