Sydney – Ivanhoe & Albury (SIA) - ARTC

71
Sydney – Ivanhoe & Albury (SIA) Config 14 & NSW Super Possession Stage 1 - Chullora Jctn to Enfield West Stage 2 - Enfield West to Glenlee Stage 3 - Glenlee to Berrima Jctn Stage 4 - Berrima Jctn to Moss Vale Stage 5 - Moss Vale to Goulburn Stage 6 - Goulburn to Yass Jctn Stage 7 - Yass Jctn to Junee Stage 8 - Junee to Albury Stage 9 - Cootamundra to Stockinbingal Stage10 - Stockinbingal to Goobang Jctn Stage 1 – 3, 2230hrs Friday 4 th Sept – 0200 Monday 7 th Sept Stage 4, 0400hrs Saturday 4 th Sept – 0200 Monday 7 th Sept Stage 5, 2230hrs Friday 4 th Sept – 0200 Monday 7 th Sept Stage 6 -10, 0600hrs Saturday 5 th Sept – 180hrs Monday 7 th Sept

Transcript of Sydney – Ivanhoe & Albury (SIA) - ARTC

Sydney – Ivanhoe & Albury (SIA)Config 14 & NSW Super Possession

Stage 1 - Chullora Jctn to Enfield WestStage 2 - Enfield West to GlenleeStage 3 - Glenlee to Berrima JctnStage 4 - Berrima Jctn to Moss ValeStage 5 - Moss Vale to GoulburnStage 6 - Goulburn to Yass JctnStage 7 - Yass Jctn to JuneeStage 8 - Junee to AlburyStage 9 - Cootamundra to StockinbingalStage10 - Stockinbingal to Goobang Jctn

Stage 1 – 3, 2230hrs Friday 4th Sept – 0200 Monday 7th SeptStage 4, 0400hrs Saturday 4th Sept – 0200 Monday 7th SeptStage 5, 2230hrs Friday 4th Sept – 0200 Monday 7th SeptStage 6 -10, 0600hrs Saturday 5th Sept – 180hrs Monday 7th Sept

2

CONTENTS

• Possession Contacts• COVID–19 Declaration• Train Alteration Advice• ARTC Network Rules &

Procedures• PPE Requirements• Drug & Alcohol• Communication• Safety• Environmental Management

3

POSSESSIONCONTACTS

CONFIG 14

CHULLORA JCTN – MOSS VALE

4

POSSESSIONCONTACTS

MOSS VALE - ALBURY Position Shift Name Phone number

Possession Manager (PM) 0600 - 1800 Warren Williams 0438 672 296

Logistics Coordinator 0600 - 1800 Deane Thrower 0477 385 470

Possession Administrator (PA) 0600 - 1800 Michael Gordon 0428 562 906

Work as Executed [email protected]

NSW Super Possession PPO’s Moss Vale - AlburyPPO (Day) Stage 4,5,6 0600 - 1800 Paul Mangion 0428 341 167

PPO (Night) Stage 4,5,6 1800 - 0600 Tony Bush 0458 092 124

PPO (Day) Stage 7 0600 - 1800 Chris Sternbaur 0497 621 507

PPO (Night) Stage 7 1800 - 0600 Stephen Boyle 0408 864 565

PPO (Day) Stage 8,9,10 0600 - 1800 Craig Diesel 0401 272 818

PPO (Night) Stage 8,9,10 1800 - 0600 Barry Llewellyn 0428 592 661

5

COVID-19DECLARATION

2020 NSW Super Possession COVID-19 Declaration Record

ARTC has implemented a COVID-19 declaration form to help manage the safety of our communities, staff and contractors during the current pandemic. The measures that have been implemented is based on advice by the NSW Government website.

All personnel participating in the Config 14 & NSW Super Possession must complete the declaration prior to coming to site, and answer each question truthfully to the best of their ability.

When completing the declaration please take note the information at the top of the page and action the requirements accordingly.

You can scan the QR Code below using the camera on your phone to access the declaration. Alternatively your Project Manager (PM) should have forwarded a link, if you have not received, or cannot access via the QR Code please contact your relevant PM.

6

ARTC NETWORK RULES &

PROCESURES

ARTC NSW Network Rules & ProceduresAs part of the SIA Corridor’s Possession Teams effort to continue driving a positive safety culture for all personnel working within our possessions, we have included links via QR Codes to the NSW Network Rules and Procedures.

As with the COVID-19 declaration, you can use the camera on your phone to scan the code and you will be taken to the relevant section of the ARTC website containing the Rules and Procedures.

It is important for ALL personnel to understand the requirements to work within the corridor, and regularly check for updates to the rules and procedures.

We have included some of the relevant rules and procedures related the Config 14 & NSW Super Possession below and highly recommend you review these documents prior to the possession.

General Rules• ANGE 218 - Type F Level Crossing Management

Work on Track• ANWT 302 - Local Possession Authority• ANWT 314 - Work Trains• ANWT 316 - Track Vehicles

Procedures• ANPR 700 - Using a Local Possession Authority• ANPR 704 - Using Infrastructure Booking Advices• ANPR 710 - Piloting Trains and Track Vehicles

7

ARTC NETWORK RULES &

PROCEDURESQR CODE LINKS

ARTC NSW Network Rules & Procedures

Glossary

General Rules

Work on Track

Procedures

8

PPE REQUIREMENTS • Reflective stripes are only required at night or when there is poor light conditions or reduced visibility. Reflective vests or shirts must be available in case work extends and conditions deteriorate

• Hard hats must be worn at all times in the shared corridor• Hard hats are to be worn on a risk assessed basis, or when mandated by the

Safe Work Method Statement (SWMS)

• Safety glasses are to be worn at all times (Must meet AS/NZS 1337.1:2010)• Ear protection is to be carried and worn as required, unless mandated by the

Safe Work Method Statement (SWMS)

• Gloves are to be carried at all times, and worn as required unless mandated by the Safe Working Method Statement

• Ankle length steel / carbon fiber capped boots that are fit for purpose must be worn at all times.

• Boots must have laces, but can have zippered side. Correct fit should be checked each morning before commencing work

9

DRUGS AND ALCOHOL

• A positive drug and/or alcohol test or other breach of policy, procedure or relevant law may result in disciplinary action which may include termination of employment or contract / service and/or suspension of a worker’s rail industry worker card.

• The refusal to supply or undertake testing, is considered a positive result

• What if a worker has been prescribed or is taking medication?

• Prescription and over the counter medicine (including herbal medicine or product) may affect a worker’s ability to work safely.

• Workers must explain to their doctor, pharmacist or other practitioner the nature of their work and seek advice as to the possible effects of the medicine. Workers should ask for medication that will not affect their ability to work safely or show up as a Positive Drug Test where this is available.

• If a worker needs to take medication that may affect their ability to work safely and/or show up as a Positive Drug Test, they must declare the medication and it’s drug class(es) to their ARTC Manager and must not work contrary to any medical advice or instructions.

• ARTC may require a worker to sign a medical release to allow the Chief Medical Officer to consult with their medical practitioner.

10

FATIGUE MANAGEMENT WHAT IS FATIGUE?

Fatigue is more than feeling tired and drowsy. In a work context, fatigue is a state of mental and/or physical exhaustion that reduces a person’s ability to perform work safely and effectively. It can occur because of prolonged or intense mental or physical activity, sleep loss and/or disruption of the internal body clock.

Signs of fatigue include:

• Tiredness even after sleep • Reduced hand-eye coordination or slow reflexes • Short term memory problems and an inability to concentrate • Blurred vision or impaired visual perception • A need for extended sleep during days off work.

WHAT CAUSES FATIGUE?

Fatigue can be caused by work related or non-work related factors or a combination of both. Work related causes of fatigue include excessively long shifts, not enough time to recover between shifts and blocks of shifts, very strenuous jobs and long commuting times. An example of non-work related fatigue would be poor quality sleep due to street noise or family demands.

11

ENVIRONMENTALSOIL AND WATER CONTAMINATION

It is important for staff to plan work to avoid known contamination (particularly when excavating soils) and minimise the potential to cause contamination of soil and water. Indicators of soil and water contamination include soil staining, discoloration, smell/odours, unusual texture and oily sheens.

Planning your work Identify likely presence of contamination through site inspection, ARTC database search,

local knowledge and environmental assessment (such as REF or TBEIA). If soil or water contamination is identified seek advice from your Environmental Officer. A

specialist consultant may be required to undertake testing or help manage the site. Review the fuels, oils, chemicals or maintenance activities proposed for the project, and

ensure appropriate containment measures (e.g. contained areas, bunded fuel tanks or drip trays) and spill kits are available to capture and manage spills that may occur.

What should I do? If contamination has been identified try to avoid the area and if necessary erect signage or

fencing to delineate ‘no go zones’. If contaminated soils cannot be avoided follow advice from your Environmental Officer and

where available consultancy reports / management plan. Soil material cannot be taken outside the rail corridor without contamination testing and

having gained the correct waste transport / disposal approvals. Contaminated material is to be stockpiled separately so that it is not mixed with non-

contaminated material. Consideration to be given to covering the contaminated stockpile and / or using sandbags

to bund the area and contain the material.

12

ENVIRONMENTALSTOCKPILES

Stockpiles are often associated with construction and maintenance activities and can be in place for the short or long term. Poorly managed stockpiles can lead to issues such as erosion, vegetation removal, visual impacts and dusty sites. ARTC may receive complaints from the EPA or community if a stockpile is poorly managed.

Planning your work The following should be considered when establishing a stockpile site: Place the stockpile on flat ground rather than a slope; Locate the stockpile away from drainage lines or creeks where there is concentrated water flow

or potential for erosion; Place away from residential areas and in locations where views of surrounding environments

will not be blocked; Select locations that have previously been used for stockpiling or which are disturbed; Access to the stockpile site and associated impacts from truck and vehicle movements; and Where stockpiles are long term, consider other spoil management options such as offsite

disposal or reuse.

13

ENVIRONMENTALSTOCKPILES CONT…

What should I do? Define or delineate the stockpile area to prevent stockpiles from ‘creeping’ to other areas. Do not stockpile under tree drip lines or within tree root zones as this can damage trees. Store site topsoil separately so it can be put back and assist in revegetating the site. If contaminated soil is stockpiled on site, keep in a separate location away from other soil to

prevent cross contamination, cover and clearly delineate on maps or by way of signage or fencing.

Use sediment controls such as sand bags, sediment fence, a ballast mound or covers to minimise sediment run off.

Limit stockpile height to 2 meters as this limits the potential for dust and visual impacts. Monitor and review stockpiles after rain events, strong winds and manage in accordance with

environmental assessment (where relevant). If dust is observed from the stockpile consider using a water cart to suppress the dust. For long

term stockpiles consider using more permanent covers such as vegetation, tarpaulins or a binding agent.

14

POSSESSION REPORTING

As part of the possession, the Possession Management Team are required to issue at the end of each shift to ARTC management a report showing the below details, A nominated ARTC representative will call all sites between 16:30 – 18:00 hrs. each day for the required details;

1. Number of staff onsite and hours worked2. Production for the day3. Issues4. TSR’s

All Work as Executed information is required to be submitted within 24 hours of project completion, this includes but is not limited to certification forms.

Please send to [email protected] and use the phrase ‘Work as Executed’ in the email subject.

NOTE: If your job finishes prior to 1630 hrs. it is the responsibility of the site supervisor to call the Possession

Admin and advise of the project status

NSW Super Shut

Possession Stage Area Day

PositionNight

Position Times Hours Shift Name Location Contact Dates

PPO Stage 4,5,6 Moss Vale - Yass Junction PO4 21:00 Friday - 06:00 Saturday 9 NIGHT Tony Bush Goulburn PC 0458 092 124

Stage 4,5,6 Moss Vale - Yass Junction PO4 18:00 Saturday - 06:00 Sunday 12 NIGHT Tony Bush Goulburn PC 0458 092 124

Stage 4,5,6 Moss Vale - Yass Junction PO4 18:00 Sunday - 06:00 Monday 12 NIGHT Tony Bush Goulburn PC 0458 092 124

PPO ASSIST Stage 4,5,6 Moss Vale - Yass Junction 21:00 Friday - 06:00 Saturday 9 NIGHT Richard Luckas Goulburn PC 0428 592 860

Stage 4,5,6 Moss Vale - Yass Junction 18:00 Saturday - 06:00 Sunday 12 NIGHT Richard Luckas Goulburn PC 0428 592 860

Stage 4,5,6 Moss Vale - Yass Junction 18:00 Sunday - 06:00 Monday 12 NIGHT Richard Luckas Goulburn PC 0428 592 860

PPO Stage 4,5,6 Moss Vale - Yass Junction PO4 06:00 Saturday - 18:00 Saturday 12 DAY Paul Mangion Goulburn PC 0428 341 167

Stage 4,5,6 Moss Vale - Yass Junction PO4 06:00 Sunday - 18:00 Sunday 12 DAY Paul Mangion Goulburn PC 0428 341 167

Stage 4,5,6 Moss Vale - Yass Junction PO4 06:00 Monday - 18:00 Monday 12 DAY Paul Mangion Goulburn PC 0428 341 167

PPO ASSIST Stage 4,5,6 Moss Vale - Yass Junction 06:00 Saturday - 18:00 Saturday 12 DAY Mark Brown Goulburn PC 0413 007 863

Stage 4,5,6 Moss Vale - Yass Junction 06:00 Sunday - 18:00 Sunday 12 DAY Mark Brown Goulburn PC 0413 007 863

Stage 4,5,6 Moss Vale - Yass Junction 06:00 Monday - 18:00 Monday 12 DAY Mark Brown Goulburn PC 0413 007 863

PPO Stage 7 Yass Junction - Junee PO4 06:00 Saturday - 18:00 Saturday 12 DAY Chris Sternbauer Cootamundra PC 0497 621 507

Stage 7 Yass Junction - Junee PO4 06:00 Sunday - 18:00 Sunday 12 DAY Chris Sternbauer Cootamundra PC 0497 621 507

Stage 7 Yass Junction - Junee PO4 06:00 Monday - 18:00 Monday 12 DAY Chris Sternbauer Cootamundra PC 0497 621 507

PPO ASSIST Stage 7 Yass Junction - Junee 06:00 Saturday - 18:00 Saturday 12 DAY Michael Bereyne Cootamundra PC 0417 292 745

Stage 7 Yass Junction - Junee 06:00 Sunday - 18:00 Sunday 12 DAY Michael Bereyne Cootamundra PC 0418 292 745

Stage 7 Yass Junction - Junee 06:00 Monday - 18:00 Monday 12 DAY Michael Bereyne Cootamundra PC 0419 292 745

PPO Stage 7 Yass Junction - Junee PO4 18:00 Saturday - 06:00 Sunday 12 NIGHT Stephen Boyle Cootamundra PC 0408 864 565

Stage 7 Yass Junction - Junee PO4 18:00 Sunday - 06:00 Monday 12 NIGHT Stephen Boyle Cootamundra PC 0409 864 565

PPO ASSIST Stage 7 Yass Junction - Junee 18:00 Saturday - 06:00 Sunday 12 NIGHT Mellissa Mendeyk Cootamundra PC 0432 745 734

Stage 7 Yass Junction - Junee 18:00 Sunday - 06:00 Monday 12 NIGHT Mellissa Mendeyk Cootamundra PC 0433 745 734

PPO Stage 8,9,10 Junee - Albury & Parkes PO4 06:00 Saturday - 18:00 Saturday 12 DAY Craig Diesel Cootamundra PC 0401 272 818

Stage 8,9,10 Junee - Albury & Parkes PO4 06:00 Sunday - 18:00 Sunday 12 DAY Craig Diesel Cootamundra PC 0401 272 818

Stage 8,9,10 Junee - Albury & Parkes PO4 06:00 Monday - 18:00 Monday 12 DAY Craig Diesel Cootamundra PC 0401 272 818

PPO ASSIST Stage 8,9,10 Junee - Albury & Parkes 06:00 Saturday - 18:00 Saturday 12 DAY Michael O'donnell Cootamundra PC 0416 996 229

Stage 8,9,10 Junee - Albury & Parkes 06:00 Sunday - 18:00 Sunday 12 DAY Michael O'donnell Cootamundra PC 0416 996 229

Stage 8,9,10 Junee - Albury & Parkes 06:00 Monday - 18:00 Monday 12 DAY Matthew Robinson Cootamundra PC 0416 996 229

PPO Stage 8,9,10 Junee - Albury & Parkes PO4 18:00 Saturday - 06:00 Sunday 12 NIGHT Barry Llewellyn Cootamundra PC 0428 592 661

Stage 8,9,10 Junee - Albury & Parkes PO4 18:00 Sunday - 06:00 Monday 12 NIGHT Barry Llewellyn Cootamundra PC 0428 592 661

PPO ASSIST Stage 8,9,10 Junee - Albury & Parkes 18:00 Saturday - 06:00 Sunday 12 NIGHT Mark Walsh Cootamundra PC 0418 438 813

Stage 8,9,10 Junee - Albury & Parkes 18:00 Sunday - 06:00 Monday 12 NIGHT Mark Walsh Cootamundra PC 0418 438 813

2020 NSW SUPER POSSESSION PPO ROSTER

Friday 4th September Saturday 5th September , Sunday 6th September Monday 7th September

2020

Amendment 1 TAA 1057- 2020 Issued 02 September 2020 (JH) Page 1 of 14

TRAIN ALTERATION ADVICE No: 1057 – 2020 Amendment 1

Interstate Network

Sydney – Ivanhoe – Albury Corridor

Sydney to Albury & Cootamundra to Goobang Junction Closedown

Sydney Trains WE10 Possession Alterations

04 – 07 September 2020

TRACK POSSESSIONS

Date From Date To From Boundary Tracks To Boundary Possession Protection

Officer Area

Metropolitan Freight Network

1

2230

04/09/2020

Continuous

0200

07/09/2020

Chullora Junction

Clear of 354 Points

Up Main

Down Main

Enfield West

EW418 Signal

SP3 Signal (YL/EYL)

PPO 1

Config 14

Southern Sydney Freight Line

2

2230

04/09/2020

Continuous

0200

07/09/2020

Enfield West

EW418 Signal

Glenfield

GF22 & GF23 Signals

SSFL

Leightonfield Loop

Glenfield Loop

Glenlee

GE25 Signal

PPO 1

Config 14

Main South

3

2230

04/09/2020

Continuous

0200

07/09/2020

Glenlee

GE23 Signal

GE25 Signal

36.0 (EYL) Signal

All Lines

Berrima Junction

Clear of

188 & 189 Points

PPO 1

Config 14

Amendment 1 TAA 1057- 2020 Issued 02 September 2020 (JH) Page 2 of 14

TRAIN ALTERATION ADVICE No: 1057 – 2020 Amendment 1

Date From Date To From Boundary Tracks To Boundary

Possession Protection

Officer Area

4

0400

05/09/2020

Continuous

0200

07/09/2020

Berrima Junction

Clear of 188 and 189

Points (Inclusive)

All Lines

Moss Vale

148.1 (EYL) Signal

MV88 Signal

MV21 Signal

Clear of Frames C, D, E & F

PPO 2

Goulburn

5

2230

04/09/2020

Continuous

0400

07/09/2020

Moss Vale

148.1 (EYL) Signal

MV88 Signal

Down Main

Up Main

Goulburn

G6 Signal

Clear of 101 and 102

Points (Inclusive)

PPO 2

Goulburn

6

0600

05/09/2020

Continuous

1800

07/09/2020

Goulburn

Clear of 101 and 102

Points

All Lines

Yass Junction

YJ 22 Signal

YJ 24 Signal

PPO 2

Goulburn

7

0600

05/09/2020

Continuous

1800

07/09/2020

Yass Junction

YJ 22 Signal

YJ 24 Signal

All Lines

Junee

JE 03 Signal

JE 02 Signal

Cootamundra

Clear of 104 & 107

Points

PPO 3

Cootamundra

Amendment 1 TAA 1057- 2020 Issued 02 September 2020 (JH) Page 3 of 14

TRAIN ALTERATION ADVICE No: 1057 – 2020 Amendment 1

Date From Date To From Boundary Tracks To Boundary

Possession Protection

Officer Area

8

0600

05/09/2020

Continuous

1800

07/09/2020

Junee

JE 03 Signal

JE 02 Signal

JE 15 Signal

All Lines Albury

AY56 Signal

PPO 4

Wagga / Parkes

Cootamundra – Goobang Junction Line

9

0600

05/09/2020

Continuous

1800

07/09/2020

Cootamundra

Clear of 104 & 107

Points (Inclusive)

All Lines

Stockinbingal

SL20 Signal

SL22 Signal

PPO 4 Wagga / Parkes

10

0600

05/09/2020

Continuous

1800

07/09/2020

Stockinbingal

Start/End Train Order Working

Board

All Lines

Goobang Junction

Start/End Train Order Working

Board

PPO 4

Wagga / Parkes

To be read in conjunction with:

• Sydney Trains STN 1930-2020, 1931-2020 • TAA 1164-2020 (Albury – Melbourne Closedown)

The following train alterations will apply:

Wednesday 2nd September 2020

Pacific National (Intermodal)

4PS6 on Wed 02/09/2020 will run as timetabled, arrive Goobang Jct Sat 05/09/2020 0805 depart 0901, pass CRN/ARTC Boundary Main Line - Parkes 0903, run as arranged by the CRN & Sydney Trains, pass Flemington MFN Border 1925, arrive SOY 1932 terminate

Approval No Derek Rogers / Michael

Irons

Project No/Type (Eg RCRM, MPM,CAP, if external ie non ARTC works - provide owner

entity name)

Work Description Location / KM's Scope Shift Tracks Affected Work

GroupPlant/

RescourcesProjectOwner Comments Possession Electrical Bonding required / Power out

permitt

1 MPM Vegetation Control

Targeted Location

within Possession Boundaries

Team 1: Removal and Mulching of Wattle trees: Linden Rd LXING

Galong (367.383 km both Up and Down Main)

Team 2: Cutting and spraying of saplings: Gerogery to Table Top

(613.300 km- 631.176 km both Up and Down sides) & Culcairn to

Wagga Wagga (597.330 km-525.922 km both Up and Down sides)

Team 1: Clayton Holder 06:00 18:00 0422 542 040

Team 2: Hannah Meyer 06:00 18:00 0439 316 363

Team 1: Clayton Holder 06:00 18:00 0422 542 040

Team 2: Hannah Meyer 06:00 18:00 0439 316 363

N/A

N/A

2 CAP Underbridge Renewal or Upgrade

236.000km - Yarra, RunOff

Waters Ck

236.000 -Yarra, Run Off Waters Ck - Face retransoming up main (42)

Kurt Ellsley 0600 1800 0407 872 973

Stephen Hedley 0600 1800 0409 999 167

Dave McDowell 0600 1800 0408 919 770

Stephen Hedley 0600 1800 0409 999 167

3 MPM

Steel Underbridge Repairs

(MPM)

236.000km - Yarra RunOff

Waters Ck

236.000-UB Repairs - Yarra, RunOff Waters Ck

236.019km – Down Main (fast clip & Pandrol sleepers) Remove TD on

bridge-Materials

-1 x 110m 60kg SC rail-2 x 13.7m 53km SC Rail.

-Scaffolding-Will need signal support

Kurt Ellsley 0600 1800 0407 872 973

Stephen Hedley 0600 1800 0409 999 167

Dave McDowell 0600 1800 0408 919 770

Stephen Hedley 0600 1800 0409 999 167

SIGNAL SUPPORT

WORKSITE CERTIFIER

Possession of Down

Main required

on 06 Sep 2020:

0600-1600 hours

N/A

PROTECTION OFFICER

WORKSITE SUPERVISOR

Day Shift:

06 Sep 2020: 0600-1800 hours

PC Down MainRhomber

g Rail Aust PL

Hi-Rail Excavators,

Hi-Rail Trollies &

Tools

Tofiq Ahmed

PROTECTION OFFICER

WORKSITE SUPERVISOR

SIGNAL SUPPORT

WORKSITE CERTIFIER

WORKSITE CERTIFIER

Day Shift: 05 &

06 Sep 2020: 0600-1800 hours

PC Up MainRhomber

g Rail Aust PL

Hi-Rail Excavators,

Hi-Rail Trollies &

Tools

Tofiq Ahmed

Work Trains/Trac

k Machines can pass through Down

Main Only.Prior

arrangements must be made

with Project

Manager & Site

Full Possession of Up Main

Required on 05 & 06 Sep

2020

N/A

Full Possession N/A

PROTECTION OFFICER

WORKSITE SUPERVISOR

SIGNAL SUPPORT

Day PC UP and Down Mains

Weedmasters PL

Excavator, Chipper & Chainsaws

Spray Rigs &

Chainsaws

Tofiq Ahmed

Plant can be

removed from track for track

machines movement

Worksite Contact Details

NB: if not ARTC works, please obtain application pack from [email protected] The Job No will be issued upon ARTC

acceptance of the proposal then sent to the [email protected] email. By

Derek / Michael

For any projects potentially impacting ARTC network, the minimum review time is 20 business days following receipt of completed application

pack at above email. Any queries to same address. SIA Possession Bid Sheet

Date : 2nd & 3rd of May 2020 Config if Required: Config 14 & NSW Super Possession Weekend :

4 CAP

Level Crossing

Upgrade or Renewal

428.948km - Cootamundra

,Temora Rd,Ped lxing

428.948 - Cootamundra, Temora Rd, Pedlxing - Upgrade

Upgrade pedestrian level crossing

Day & Night PC All Five (5)

TracksTaylor

Rail

Hi-Rail Excavators,

Tip Trucks,

Loader & Tools

Steven Twyford

Full Possession of all five (5) Track required during

Upgrade Works No Machines can pass through this site.

Full Possession N/A

5 CAP

Level Crossing

Upgrade or Renewal

428.956km - Cootamundra, Temora Rd

428.956-Temora Rd Lxing, Cootamundra - Upgrade

- Renew bitumen level crossing surface All 5 tracks

- Install slab / culvert upside where roundabout (old channel line) rodding

was located-53kg rail-Drainage

-T/O to remain timber-Concrete sleepers for other tracks

Day & Night PC All Five (5)

TracksTaylor

Rail

Hi-Rail Excavators,

Tip Trucks,

Loader & Tools

Steven Twyford

Full Possession of all five (5) Track required during

Upgrade Works No Machines can pass through this site.

Full Possession N/A

6 CAP

Level Crossing

Upgrade or Renewal

535.529km - Uranquinty,

Yarrangundry

535.529- Yarrangundry St, Uranquinty - Upgrade Main line

crossing with bitumenRerail, drainage ect

Murry Nolan 0600 1800 0424 164 007 Phillip Ibote 1800 0600 0484 863 484

Craig Jed Holdsworth 0600 1800 0438 008 117

Samuel Tom 1800 0600 0476 718 134

Don Walker 0600 1800 0419608863

Craig Jed Holdsworth 0600 1800 0438 008 117

7 CAP

Level Crossing

Upgrade or Renewal

580.200km - Henty,

Sladen Street

580.200 - Henty, Sladen Street - Upgrade Crossing to bitumen.

Drainage

Andrew Latimer 0600 1800 0477 387 487Michael Weston 1800 0600 0490 852 580

Simon Newman 0600 1800 0428 595 247Michael Davis 1800 0600 0419 250 737

Christopher Hutchinson 0600 1800 0477 708 987

TBC 0600 1800 TBC

8 MPM3 x Ballast Undercuttin

g Teams

Moss Vale Junction -

Yass

Team 1: (05-06/09/2020)Starts at Up main: 146.896km and

finishes at Up Main: 185.930 Team 2: (05-06/09/2020)

Starts at Up main: 193.045km and finishes at Up main: 186.130km

Team 3: (05-06/09/2020)Starts at Up main: 291.750km and finishes at Up Main: 263.216km

Viktoriya Subbota: Team 1 0700 1700 0415 858 085

Nicholas Borg: Team 2 0700 1700 0405 210 928

Neil Mitchison: Team 3 0700 1700 0467 574 519

Anthony King: Team 1 0700 1700 0431 393 400

Track Machines can pass through

sites with prior

arrangements made

with Project

Manager

WORKSITE SUPERVISOR

SIGNAL SUPPORT

WORKSITE CERTIFIER

WORKSITE SUPERVISOR

Team 1 & 2:

05-06/09/2020: 0700-1700 hours

Team 3:

05

Jason Walsh Jeremy Clark

William (Adam)

Up & Down Mains

Team 1: DMT PL

Team 2 & 3:

Quickway PL

Hi-Rail Excavators,

Tip Trucks,

Loader & Tools

Tofiq Ahmed N/A

PROTECTION OFFICER

SIGNAL SUPPORT

WORKSITE CERTIFIER

Day & Night PC Main Downer

PL

Hi-Rail Excavators, Loader &

Tools

Tofiq Ahmed

Full Possession of Level Crossing Required

during works.

Full Possession

Full Possession of Level Crossing Required

during works. Track

Panels will be cut

Full Possession N/A

PROTECTION OFFICER

N/A

PROTECTION OFFICER

WORKSITE SUPERVISOR

PROTECTION OFFICER: Tim Ryan, 0434 255 780

Supervisor: Brett Schliebs 0417 245 768

PROTECTION OFFICER: Tim Ryan, 0434 255 780 , Supervisor: Brett Schliebs 0417 245

768

05-06/09/2020: 0600-1800 hours

05/09/2020: 1800-0600 hours

PC Main

Thee Rail

Specialist PL

Hi-Rail Excavators,

Hi-Rail Hydremas, Loaders &

Tools

Tofiq Ahmed

Aisake Parker: Team 2 0700 1700 0457 025 542

Mathew Sheehan: Team 3 0700 1700 0476 923 921

James Crisp 0700 1700 0449 543 216

Aisake Parker: Team 1 0700 1700 0457 025 542

Aisake Parker: Team 2 0700 1700 0457 025 542

Mathew Sheehan: Team 3 0700 1700 0476 923 921

9 MPMBallast

Undercutting (MPM)

Junee - Albury

Undercutting - Wagga PCRemoval of mudholes at various

locations

Jamie Bedimgfield 0600 1800 0438715641

shaun skates 0600 1800 0467766985

TBC 0600 1800 TBC

shaun skates 0600 1800 0467766985

10 MPM Tamping (MPM)

Joppa Junction to

Yass

Joppa Junction to Yass231.330km Joppa Jnc to 315.000km

YassKath Kirkness 0600 1800 0414 318 312 Joe Arregui 1800 0600 0405 921 886

Fred Keys 0600 1800 0474 000 623Daniel Jaunalksnis 1800 0600 0437 390 337

James Crisp 0600 1800 0449 543 216

Brett Bohringer 0600 1800 0418 261180 Daniel Jaunalksnis 1800 0600 0437 390 337

11 MPMTurnout Tamping

(MPM)

Exeter to Marulan

Turnouts and Plain Track Tamping between 155.000km Exeter to

193.000km MarulanLuke Murray 0600 1800 0400 299 286

Regan Woollard 0600 1800 0428 664 111

Dave McDowell 0600 1800 0408 919 770

Regan Woollard 0600 1800 0428 664 111

12 MPMTurnout Tamping

(MPM)

Marulan to Goulburn & Goulburn

Yard

Turnouts and Plain Track Tamping between 193.000km Marulan to

224.180km Goulburn and Goulburn Yard Works

Ethan Brophy 05-06/09/2020: 1200 2400 0403 141 545

Blake Davies 06/09/2020 0001 1200 0457 613 951

Ethan Brophy 05-06/09/2020: 1200 2400 0403 141 545

Blake Davies 06/09/2020 0001 1200 0457 613 951

Dave McDowell 0600 1800 0408919770

Ethan Brophy 05-06/09/2020: 1200 2400 0403 141 545

Justin Brimble06/09/2020 0001 1200 0402 759 562

13 MPM Tamping (MPM)

Yass to Cootamundra

Plain Track Tamping between 324.210km Yass and 428.000km

CootamundraPhil Sharp 0600 1800 0409 150 092

N/A

PROTECTION OFFICER

WORKSITE SUPERVISOR

Day Shifts: 05 07

Dean Bradley Up & Down Rhomberg Rail

09-3X Hi-Production

Tamper

Tofiq

All Sites to make

necessary arrangeme

All Sites to make

necessary arrangements not to

hold Tampers

WORKSITE SUPERVISOR

1200 hours

on 05/09/2020 to 1200 hours

on 06/09/2020:

Goulburn

Yard Works1200-2400 hours

on 06/09/2020:

Goulbu

Site RepUp & Down

Mains & Goulburn Yard

Brimble Rail PL

Plasser Turnout Tamper (Unimat)

and Regulator,

Tools

Tofiq Ahmed

SIGNAL SUPPORT

WORKSITE CERTIFIER

N/A

PROTECTION OFFICER

N/A

PROTECTION OFFICER

WORKSITE SUPERVISOR

SIGNAL SUPPORT

WORKSITE CERTIFIER

Day Shifts: 05-06 Sep 2020

Troy Collins Up & Down Mains

Brimble Rail PL

Plasser Turnout Tamper (07-275)

and Regulator,

Tools

Tofiq Ahmed

All Sites to make

necessary arrangements not to

hold Tampers

All Sites to make

necessary arrangements not to

hold Tampers

WORKSITE SUPERVISOR

Day Shifts: 05-07 Sep 2020 Night Shifts: 05-06 Sep 2020

Simon Grant (D) Rodney Walsh (N)

Up & Down Mains

Rhomberg Rail

Aust PL

09-3X Hi-Production

Tamper and

Regulator, Tools

Tofiq Ahmed

SIGNAL SUPPORT

WORKSITE CERTIFIER

N/A

PROTECTION OFFICER

N/A

PROTECTION OFFICER

WORKSITE SUPERVISOR

SIGNAL SUPPORT

WORKSITE CERTIFIER

Day shaun Skates Main Wagga pc

Hi-Rail Excavators,

Tip Trucks,

Loader & Tools

Steve Skates

Track Machines can pass through

sites with prior

arrangements made

with Project

Manager and Site

Manager and Site

Supervisor

05-07/09/2020: 0700-1700 hours

y PL

SIGNAL SUPPORT

WORKSITE CERTIFIER

David Masters 0600 1800 0429 233 093

Mitch Saxby 0600 1800 0421147091

David Bowe 0600 1800 0407 233 093

14 MPMTurnout Tamping

(MPM)

Cootamundra to Junee

Turnouts and Plain Track Tamping between 428.956km Cootamundra

and 482.000km JuneePeter Klarner 0600 1800 0407 881 166

Warren Hill 0600 1800 0401 400 619

Don Walker 0600 1800 0419 608 863

Warren Hill 0600 1800 0401 400 619

15 MPM Tamping (MPM)

Junee - Wagga Wagga

Plain Track Tamping between 488.619km Junee and 428.000km

CootamundraGreg Nuss 0600 1600 0435 030 866

Kurt Beatty 0600 1600 0437 844 266

Steven Deweske 0600 1600 0417664778

Stan Alipate 0600 1600 0402 489 225

16 MPM Tamping (MPM)

Uranquinty to Henty

Turnout & Plain Track Tamping between 531.000km Uranquinty and

582.000km HentyShift 1: Sat: Matt

Woods 1700 0400 0439 062 523

Shift 2: Sun: Greg Nuss 0400 1400 0435 030 866

Shift 3: Sun: Matt Woods 1400 2200 0439 062 523

Shift 1: Sat: Craig McKenna 1700 0400 0411 674 772

Shift 2: Sun: Kurt Beatty 0400 1400 0437 844 266

Shift 3: Sun: Craig McKenna 1400 2200 0411 674 772

Jeff Bristow 0600 1800 0418 972 554

Shift 1: Sat: Craig McKenna 1700 0400 0411 674 772

Shift 2: Sun: Stan Alipate 0400 1400 0402 489 225

Shift 3: Sun: Craig McKenna 1400 2200 0411 674 772

17 MPM

Steel Underbridge Repairs

(MPM)

184.610km Underbridge-

Tallong

184.617km (Down Main Only) Remove LOB and wheelburns on

bridge. -Materials

-1 x 110m 60kg SC rail-2 x 13.7m 53km SC Rail.

-Scaffolding-Will need signal support-Will need traffic control

05/09/2020: Owen Nhang 1200 2100 0431 240 113

05/09/2020: Owen Nhang 0800 1900 0431 240 113

05/09/2020: Alexander Dennis 1200 2100 0429 998 841

05/09/2020: Alexander Dennis 1200 2100 0429 998 841

James Crisp 0600 1800 0449 543 216

Craig Jed Holdsworth 0800 1900 0438 008 117

N/A

PROTECTION OFFICER

WORKSITE SUPERVISOR

SIGNAL SUPPORT

WORKSITE CERTIFIER

05/09/2020:

1200 – 2100 hours

06/09/2020: 0800-1900 hours

PC Down Main

Thee Rail

Specialist PL

Hi-Rail Excavators, Loaders, Welding

Tools

Tofiq Ahmed

Access through

this site be available

at adjacent

Track with Prior Arrangements to be

made with Project

Manager and Site

Supervisor for any

passage required.

Full Possession

All Sites to make

necessary arrangements not to

hold Tampers

WORKSITE SUPERVISOR

Night & Day Site Rep Main Line &

LoopsTaylor Rail PL

Pandrol Jackson Tamper

and Regulator,

Tools

Tofiq Ahmed

SIGNAL SUPPORT

WORKSITE CERTIFIER

N/A

PROTECTION OFFICER

N/A

PROTECTION OFFICER

WORKSITE SUPERVISOR

SIGNAL SUPPORT

WORKSITE CERTIFIER

Day Site Rep Main Taylor Rail PL

09-2X Hi-Production

Tamper and

Regulator, Tools

Tofiq Ahmed

All Sites to make

necessary arrangements not to

hold Tampers

All Sites to make

necessary arrangements not to

hold Tampers

WORKSITE SUPERVISORDay Paul Meale Up & Down Mains

Taylor Rail PL

Pandrol Jackson Tamper

and Regulator,

Tools

Tofiq Ahmed

SIGNAL SUPPORT

WORKSITE CERTIFIER

N/A

PROTECTION OFFICER

N/A

SIGNAL SUPPORT

WORKSITE CERTIFIER

05-07 Sep 2020

Dean Bradley Mains g Rail

Aust PL

and

Regulator, Tools

Ahmed

arrangements not to

hold Tampers

18 MPM

Redundant Infrastructure Removal

Wallendbeen Yard

407.920 Km to 408.010

Km

Remove redundant infrastructure and straight rail 6AA points ,6AB

catch points ,3AA points 3AB points and Sim Recon,lay new sleepers, rail

weld out, and resurface

Day & Night PC Up & Down Main Earthtrac

k

Excavators, Loaders,

Dump Trucks,Water Cart and Resurfacing

Team

Steven Twyford

Access through this site may be available with Prior Arrangements to be

made with Project

Manager and Site

Supervisor for any

passage required.

Full Possession

19 CAPSteel

Component Upgrade

Wingello Yard

176.853 Km to 177.060

Km

3CA points replace L & R heeled switches with flexi switches .3CB

points replace L & R heelded switches withFlexi. 14 B points

replace heeled switches with flexi 4D Points

Down Main

Day PC Up & Down Main Taylor Rail

Excavator and

welding teams

Steven Twyford

Access through this site may be available with Prior Arrangements to be

made with Project

Manager and Site

Supervisor for any

passage required.

Full Possession

20 MPM Minor Re- railing

Lockersleigh creek bridge 200.700 Km

Remove defect rail up main,up & down rails 165m in length each rail

weld in new rail Day PC Up Main Railcon

Excavator and

welding teams

Steven Twyford

Access through this site may be available with Prior Arrangements to be

made with Project

Manager and Site

Supervisor for any

passage required.

Full Possession

21 CAP

Full Recondition Upgrade turnout

from timber to concrete

Goulburn Yard

225.200Km to 225.250Km

Remove 117A,B and C points. Do a full recondition replace turnout with

new concrete turnout

Day/Night PC Up & Down

mains John

Holland

Excavators, Loaders,

Dump Trucks,Water Cart and Resurfacing

Team

Steven Twyford

There will no access

through this site

Full Possession

22 CAPSteel

Component Upgrade

Goulburn Yard

225.200 Km to 225.250

Km

119A/B points replace L7R hand heeled switches with new flexi

switches Day PC Up & Down

mainsJohn

Holland

Excavator and

welding teams

Steven Twyford

Access through this site may be available with Prior Arrangements to be

made with Project

Manager and Site

Supervisor for any

passage required.

Full Possession

23 ARTC MPM Track Renewal 162.180km Skim Recon/Retimber 3BBpts

PROTECTION OFFICER

Protection Officer : Joanne Sepping 0421 852 202, Supervisor: Paul Vella 0414 066 210

Protection Officer: Paul Stephens 0477 860 964, Supervisor: Paul Whyler 0407 931 431

Protection Officer : Eddie Mott 0400 602 513, Supervisor: Lee Gomes 0401 647 824

Protection Officer Day: Hahn Germakain 0400 800 808, Protection officer Night: David Lawton 0466 981 838, Supervisor Day: Mal Gerrish 0439 631 524,

Supervisor Night: Brendan Woods 0458 379 010

Protection Officer Day: Hahn Germakain 0400 800 808, Protection officer Night: David Lawton 0466 981 838, Supervisor Day: Mal Gerrish 0439 631 524,

Supervisor Night: Brendan Woods 0458 379 010

Cherie Weiss 0600 1800 0408 987 380David Shore 1730 0530 0420 431 333Cherie Weiss 0500 1700 0408 987 380David Shore 1630 0230 0420 431 333

Ray McLellan 0700 1800 0407 879 178Jason Olejnik 1800 0600 0407 261 969

Dan Russ 0600 1600 0415 890 688Dan Russ 1600 2300 0415 890 688

Ray McLellan 0700 1700 0407 879 178

24 ARTC Incident Works Tree Removal 225.450km Remove overgrown Gum tree

Clayton Holder 0600 1800 0422 542 040

Clayton Holder 0600 1800 0422 542 040

N/A

TBA

25 CAPSpeno Defect

Removal

MossVale to Goulburn

Goulburn to Yass

Defect Removal

Andrew Lancaster 19:00 07:00 0400 999 977

James Callanan 0600 1800 0429 465 672

N/A

Adam Davidson 600 1800 0407222772

26 Incident

Renew left and right

hand switch and stock rail 116 B pts

485.323 Repairs to derailment site

Ben Caton 0600 1800 0439 407 060

Kiet Qauch 0600 1800 0408 887 445

Mick Vesperman 0600 1800 0427973979

Kiet Qauch 600 1800 0408 887 445

27 Incident

Renew right hand switch and stock rail 122 A pts

485.342 Repairs to derailment site

PROTECTION OFFICER

Nil Passing

SiteLPA

WORKSITE SUPERVISOR

SIGNAL SUPPORT

WORKSITE CERTIFIER

WORKSITE SUPERVISORDay M.Vesperman ALL main lines

except Down

ARTC / Contract

or

Welding equipment

Hi Rail Excavtor /

FEL / Dumpers

etc.

Steve Skates

SIGNAL SUPPORT

WORKSITE CERTIFIER

Sig Elec required

PROTECTION OFFICER

WORKSITE CERTIFIER

Day J.Callanan Up & Down Mains

Goulburn PC

Multiple Plant and resources

C McClella

nd

Up & Down mains

Full N/A

Full N/A

PROTECTION OFFICER

PROTECTION OFFICER

WORKSITE SUPERVISOR

SIGNAL SUPPORT

WORKSITE SUPERVISOR

SIGNAL SUPPORT

WORKSITE CERTIFIER

Day Site Rep

Up & Down Mains and Up refuge Plus Shunt Neck

Goulburn PC

Tree removalists with plant

C McClella

ndFlexible

C McClella

nd

Up Main total block

with resurfacing activitiies

FullBundanoon Pedestrian Level crossing affected. 3BBpts will be disconnected

during worksDay

Craig Bell (D) Jason Apps

(N)

Up & Down Mains

Goulburn PC

Multiple Plant and resources

Ben Caton 0600 1800 0439 407 060

Kiet Qauch 0600 1800 0408 887 445

Mick Vesperman 0600 1800 0427973979

Kiet Qauch 600 1800 0408 887 445

28 CAP

759 - Point Machine

Replacement

226.595- Goulburn

226.595 - Goulburn, 107A Pts - Upgrade

Pts machine upgrade as per 1819 design

-New cable route with Pit & Pipe-Wiring mods-New rodding-A & B timbers

PO - Day Shift 0600 1800Richard

Kambugu- 0451 663 049

PO - Night Shift 1800 0600 NA

Supervisor - Day Shift 0600 1800

Norman Smith- 0428

256 787 Supervisor - NIght Shift 1800 0600 NA

Day Shift 0600 1800Norman

Smith- 0428 256 787 Night Shift 1800 0600 NA

TBC 0600 1800 Jeff Hadaway- 0419 287 170

29 CAP

759 - Point Machine

Replacement

226.649- Goulburn

226.649 - Goulburn, 107B Pts - Upgrade

Pts machine upgrade as per 1819 design

-New cable route with Pit & Pipe-Wiring mods-New rodding-A & B timbers

PO - Day Shift 0600 1800Richard

Kambugu- 0451 663 049

Supervisor - Day Shift 0600 1800

Norman Smith- 0428

256 787

TBC 0600 1800Norman

Smith- 0428 256 787

TBC 0600 1800 Jeff Hadaway- 0419 287 170

30 CAP

759 - Point Machine

Replacement

226.523- Goulburn

226.523 - Goulburn, 109A CPts - Upgrade

Pts machine upgrade as per 1718 design

-New Pts machine-New cable route with Pit & Pipe

-Wiring Mods-New rodding

-A and B Timbers

PO - Day Shift 0600 1800Richard

Kambugu- 0451 663 049

Work Commenc

e with prior

arrangements made

with Project

Full Possession

WORKSITE SUPERVISOR

Day PC Refuge Loop SJM Excavators, Tools

Atiqul Hassan N/A

PROTECTION OFFICER

N/A

PROTECTION OFFICER

WORKSITE SUPERVISOR

SIGNAL SUPPORT

WORKSITE CERTIFIER

Day PC Down Main SJM Excavators, Tools

Atiqul Hassan

Work Commenc

e with prior

arrangements made

with Project

Manager, PO & Site Supervisor.

Full Possession

Work Commenc

e with prior

arrangements made

with Project

Manager, PO & Site Supervisor.

Full Possession

WORKSITE SUPERVISORDay PC Up Main SJM Excavators, Tools

Atiqul Hassan

SIGNAL SUPPORT

WORKSITE CERTIFIER

N/A

PROTECTION OFFICER

Sig Elec required WORKSITE SUPERVISOR

SIGNAL SUPPORT

WORKSITE CERTIFIER

Day M.Versperman

ALL main lines except Down

ARTC / Contract

or

Welding equipment

Hi Rail Excavtor /

FEL / Dumpers

etc.

Steve Skates

Nil Passing

SiteLPA

Supervisor - Day Shift 0600 1800

Norman Smith- 0428

256 787

TBC 0600 1800Norman

Smith- 0428 256 787

TBC 0600 1800 Jeff Hadaway- 0419 287 170

31 CAP

759 - Point Machine

Replacement

226.578- Goulburn

226.578 - Goulburn, 109B Pts - Upgrade

Pts machine upgrade as per 1718 design

-New Pts machine-New cable route with Pit & Pipe.

-Wiring mods-New rodding-A&B timbers

PO - Day Shift 0600 1800Richard

Kambugu- 0451 663 049

Night Shift 1800 0600 NA

Supervisor - Day Shift 0600 1800

Norman Smith- 0428

256 787 Night Shift 1800 0600 NA

Day Shift 0600 1800Norman

Smith- 0428 256 787 Night Shift 1800 0600 NA

TBC 0600 1800 Jeff Hadaway- 0419 287 170

32 CAP

764 - Level Crossing Upgrade (Signals)

580.209 - Henty Sladen

St Lxing

- Changeover of the RX5 assemblies at Sladen Street Level Crossing- boom change and boom LED

upgradeDay Shift 0600 1800 From Civil

Day Shift 0600 1800Chris

Hutchinson - 0477 708 987

Day Shift 0600 1800 Mat Rehling - 0408 467 561

TBC 0600 1800 Mat Rehling - 0408 467 561

33 Wabtec Control Systems

Upgrade of Harefield (Main Rd)

Level Crossing

Harefield (Main Rd) - 496.934 km

Level Crossing upgrade and related changes to signalling system.

Paul Fysh 07:00 19:00 0490 008 662Greg Southam 19:00 07:00 0419 696 877

Julian Roberts 07:00 19:00 0448 025 473

N/A

PROTECTION OFFICER

WORKSITE SUPERVISOR

SIGNAL SUPPORT

WORKSITE CERTIFIER

5/09/2020 -

7/09/2020

Day

PCMain LineLoop Line

Stock SidingWabtec

No On-track plant / Hi-Rail required

Rod Flett

Block section Junee

JE75 to Bomen BN26 &

BN28 will show

occupied during works.Works

trains may pass

through section

On completion of works /

shift Harefield

Full Posession

Work trains may

pass through this site

with prior arrangeme

nt

Full Possession

WORKSITE SUPERVISOR

Day PC All Lines AldridgeEWP, Hi-

ab, Excavators

Atiqul Hassan

SIGNAL SUPPORT

WORKSITE CERTIFIER

NA

PROTECTION OFFICER

N/A

PROTECTION OFFICER

WORKSITE SUPERVISOR

SIGNAL SUPPORT

WORKSITE CERTIFIER

Day PC Up Main SJM Excavators, Tools

Atiqul Hassan

Work Commenc

e with prior

arrangements made

with Project

Manager, PO & Site Supervisor.

Full Possession

Manager, PO & Site Supervisor.

SIGNAL SUPPORT

WORKSITE CERTIFIER

34 John Holland

Working on Quarrey

Rd Overbridge

at Bundanoon, cracks on parapets

will be fixes from road

level

Quarry Road Overbridge

at Bundanoon,

Plating Cracks on

Both Parapets

Plating Cracks in Parapits and Spangel Wall EWP on Track

Kerry Anne Chomiszak 0600 1800 0411 368 416

David Milsom 0600 1800 0417 128 388

David Milsom 0600 1800 0417 128 388

35 John Holland

Farm access

(Burham's Rd)

OverbridgePlating

Cracks on Both

Parapets

152.000 - 152.100

No plant on track, working from road level

Graham Hill 0600 1800 0448 422 146

Joseph Bartlett 0600 1800 0400 915 346

David Milsom 0600 1800 0417 128 388

36 TfNSW (RMS)

Detailed inspection

of twin bridges

over Hume Highway

227.050 - 227.100

MOBI (under bridge platform) which will be parked on the top of the

bridge (on the Hume hwy ) with a swing boom /flat form to inspect the

bridge girders from underside

Akisi Turagavou. 0700 1700 0490 249 485

Will Sullivan 0700 1700 0407 495 472Syed Nowmani 0700 1700 0428 688 115

1 hour notice

required

Full Possession WORKSITE SUPERVISOR

0600-1700 Sat & Sun

UP and Down Mains

MOBI (under bridge

platform) which will be parked on the top

of the bridge (on the Hume hwy ) with a swing

boom /flat form to

inspect the bridge girders from

underside

Syed Nowmani

0428 688 115

syed.nowmani@r

ms.nsw.gov.au

SIGNAL SUPPORT

WORKSITE CERTIFIER

N/A

PROTECTION OFFICER

N/A

PROTECTION OFFICER

WORKSITE SUPERVISOR

SIGNAL SUPPORT

WORKSITE CERTIFIER

0700-1700 Sat & Sun

UP and Down Mains N/A

Deblina Chowdbu

ry0407

738 [email protected]

m.au

Full Possession

Full Possession

WORKSITE SUPERVISOR

5th & 6th

September

2020

0600 - 1800

Site Rep UP and Down Mains N/A

Deblina Chowdbu

ry0407

738 [email protected]

m.au

SIGNAL SUPPORT

WORKSITE CERTIFIER

N/A

PROTECTION OFFICER

37 GHD

New level crossing staged works

Full Track Recondition

ing approximately 40m to

install strengthened subgrade

for a proposed new level crossing

577.500 - 578.500

Total Block no trains tp pass from 0600 Sat 5 Sept to 1800 Sun 6 Sept

with Track Machine to resurface

Symal - Graham Doneley 06:00 18:00 0499 085 978

Ryan Barnes 0.75 0.25 0415 151 128ASI - Meagan

Kuhn 06:00 18:00 0422 498 187

Symal - Emlyn Gray 0.75 0.25 0468 860 294

Symal - Luis Rodriguez 0.25 0.75 0477 500 092

ASI - Gary Docherty 06:00 18:00 0488 318 273

ASI - Matt Rehling 06:00 18:00 0408 467 561 ASI - Chris Hutchinson 06:00 18:00 0477 708 987

ASI - Matt Rehling (Signal

Certifier) 06:00 18:00 0408 487 561

Daryl Woodeson (Civil Certifier) 0.25 0.75 0428 470 126

38 CAPRerailing AMPR - SIA #K

165.178km-167.268km

Bundanoon - Penrose

Rerailing AMP 60kg H/H

PO. Gary Pipi 21:00 06:00 0458 575 936PO. Josh Pipi 06:00 18:00 0481 435 424

Support. Drew Paton 06:00 18:00 0409 833 966

PO. Gary Pipi 18:00 06:00 0458 575 936PO. Josh Pipi 06:00 18:00 0481 435 424

Support. Drew Paton 06:00 18:00 0409 833 966

PO. Gary Pipi 18:00 04:00 0458 575 936

Marc Ross 21:30 04:00 0419 827 888Corey Taylor 03:00 13:00 0407 525 269Marc Ross 14:00 02:00 0419 827 888

Corey Taylor 03:00 13:00 0407 525 269Marc Ross 14:00 22:00 0419 827 888

PO. Brian Koskela 21:00 09:00 0413 264 385Sig Elec. Colin

Shoemark 21:00 09:00 0409 586 620

PO. Brian Koskela 13:00 01:00 0413 264 385Sig Elec. Colin

Shoemark 13:00 01:00 0409 586 620

Marc Ross 0419 827 888

2300 Fri - 0200 Mon

Up Main

AMPRJHG

Programmed

Contractor / Plant

TBC

Steve Smith 0429

662 655

No Passing Possible

FELHi Rail

Excavator

LPA N/A

PROTECTION OFFICER

WORKSITE SUPERVISOR

SIGNAL SUPPORT

WORKSITE CERTIFIER

N/A

PROTECTION OFFICER

WORKSITE SUPERVISOR

SIGNAL SUPPORT

WORKSITE CERTIFIER

0600 Sat -1800 Sun

PC Single Main

Earthmomving

Equipment and tamper

Jeremy Smith0438

221 [email protected]

No Access Full Possession

39 CAP Rail Train #2

185.000km-155.000kmMedway - Moss Vale

67 x 110m 60kg Rails

Dean Fisher 21:30 07:30 0413 030 705Gary Pipi 21:30 06:00 0458 575 936

Todd Walklate 21:30 07:30 0416 640 274

Marc Ross 21:30 06:00 0419 827 888

Nicklaus Lichtenberger 0437 991 059

Marc Ross 21:30 06:00 0419 827 888

40 CAPRerailing AMPR - SIA #L

259.920km-260.085kmBreadalbane - Cullerin

Rerailing AMP 60kg H/H

PO. Adam Hartley 06:00 18:00 0477 119 124Support. Anthony

Grech 06:00 18:00 0498 181 096

Matthew Puttock 06:00 18:00 0424 380 992

PO. Anthony Neesom 04:00 16:00 0432 916 699

Sig Elec. Mick Every 04:00 16:00 0447 788 690

PO. Anthony Neesom 06:00 18:00 0432 916 699

Sig Elec. Mick Every 06:00 18:00 0447 788 690

PO. Anthony Neesom 08:00 20:00 0432 916 699

Sig Elec. Mick Every 08:00 20:00 0447 788 690

Matthew Puttock 06:00 18:00 0424 380 992

41 CAPRerailing AMPR - SIA #O

282.810km-283.360km

Gunning -

Oolong

Rerailing AMP 60kg H/H

PO. Fiona Saunders 06:00 18:00 0456 677 966

Support. Craig Klienberg 06:00 18:00 0417 355 916

Jye Kirkland 06:00 18:00 0408 839 202

PO. Anthony Neesom 04:00 16:00 0432 916 699

Sig Elec. Mick Every 04:00 16:00 0447 788 690

PO. Anthony Neesom 06:00 18:00 0432 916 699

Sig Elec. Mick Every 06:00 18:00 0447 788 690

PO. Anthony Neesom 08:00 20:00 0432 916 699

WORKSITE SUPERVISOR

SIGNAL SUPPORT

WORKSITE CERTIFIER

0600 Sat to

1800 Mon

Down MainAMPR

Earthtrack

Contractor / Plant

TBC

Steve Smith 0429

662 655

Nil / Limit Rail

Traffic During

LPA

LPA N/A

LPA N/A

PROTECTION OFFICER

PROTECTION OFFICER

WORKSITE SUPERVISOR

SIGNAL SUPPORT

WORKSITE SUPERVISOR

SIGNAL SUPPORT

WORKSITE CERTIFIER

1200 Sun to

1800 Mon

Up Main AMPRAnric

Contractor / Plant

TBC

Steve Smith 0429

662 655

Nil / Limit Rail

Traffic During

LPA

No Passing Possible

FELHi Rail

Excavator

N/A N/A

PROTECTION OFFICER

PILOT2300 Fri - 0700 Sat

Up Main

AMPRJHG

Programmed

PN

1 x Railset

Adrain Unwin0419

634 639

Sig Elec. Mick Every 08:00 20:00 0447 788 690

Jye Kirkland 06:00 18:00 0408 839 202

42 CAPRerailing AMPR - SIA #Y

301.900km-302.155kmJerrawa -

Yass

Rerailing AMP 60kg H/H

PO. Fiona Saunders 06:00 18:00 0456 677 966

Support. Craig Klienberg 06:00 18:00 0417 355 916

Jye Kirkland 06:00 18:00 0408 839 202

PO. Anthony Neesom 04:00 16:00 0432 916 699

Sig Elec. Mick Every 04:00 16:00 0447 788 690

PO. Anthony Neesom 06:00 18:00 0432 916 699

Sig Elec. Mick Every 06:00 18:00 0447 788 690

PO. Anthony Neesom 08:00 20:00 0432 916 699

Sig Elec. Mick Every 08:00 20:00 0447 788 690

Jye Kirkland 06:00 18:00 0408 839 202

43 CAPRerailing AMPR - SIA #P

303.420km-304.010km Jerrawa -

Yass

Rerailing AMP 60kg H/H

PO. Fiona Saunders 06:00 18:00 0456 677 966

Support. Craig Klienberg 06:00 18:00 0417 355 916

Jye Kirkland 06:00 18:00 0408 839 202

PO. Anthony Neesom 04:00 16:00 0432 916 699

Sig Elec. Mick Every 04:00 16:00 0447 788 690

PO. Anthony Neesom 06:00 18:00 0432 916 699

Sig Elec. Mick Every 06:00 18:00 0447 788 690

PO. Anthony Neesom 08:00 20:00 0432 916 699

Sig Elec. Mick Every 08:00 20:00 0447 788 690

Jye Kirkland 06:00 18:00 0408 839 202

44 CAPRerailing AMPR - SIA #Q

334.580km-334.930kmBowning - Binalong

Rerailing AMP 60kg H/H

PO. Alex Burl 06:00 18:00 0402 793 580Support. John

Murray 06:00 18:00 0410 135 353

Nick Elliott 06:00 18:00 0401 487 0930600 Sat

Contracto

Steve

Nil / Limit

PROTECTION OFFICER

WORKSITE SUPERVISOR

SIGNAL SUPPORT

N/A

PROTECTION OFFICER

WORKSITE SUPERVISOR

SIGNAL SUPPORT

WORKSITE CERTIFIER

Day / Night Site Rep Up Main AMPR

Contractor / Plant

TBC

Steve Smith 0429

662 655

Nil / Limit Rail

Traffic During

LPA

LPA

Nil / Limit Rail

Traffic During

LPA

LPA

WORKSITE CERTIFIER

WORKSITE SUPERVISOR0600 Sat to

1800 Mon

Down MainAMPREarthtr

ack

Contractor /

Plant TBC

Steve Smith 0429

662 655

SIGNAL SUPPORT

WORKSITE CERTIFIER

N/A

PROTECTION OFFICER

PO. Chantelle Young 04:00 16:00 0415 150 559

Sig Elec. Danial Klaassen 04:00 16:00 0432 290 206

PO. Chantelle Young 06:00 18:00 416 150 559

Sig Elec. Danial Klaassen 06:00 18:00 0432 290 206

PO. Chantelle Young 08:00 20:00 417 150 559

Sig Elec. Danial Klaassen 08:00 20:00 0432 290 206

Nick Elliott 06:00 18:00 0401 487 093

45 CAPRerailing AMPR - SIA #S

347.370km-348.290kmBowning - Binalong

Rerailing AMP 60kg H/H (Single Leg Hi)

PO. Alex Burl 06:00 18:00 0402 793 580Support. John

Murray 06:00 18:00 0410 135 353

Nick Elliott 06:00 18:00 0401 487 093

PO. Chantelle Young 04:00 16:00 0415 150 559

Sig Elec. Danial Klaassen 04:00 16:00 0432 290 206

PO. Chantelle Young 06:00 18:00 416 150 559

Sig Elec. Danial Klaassen 06:00 18:00 0432 290 206

PO. Chantelle Young 08:00 20:00 417 150 559

Sig Elec. Danial Klaassen 08:00 20:00 0432 290 206

Nick Elliott 06:00 18:00 0401 487 093

46 CAPRerailing AMPR - SIA #T

353.790km-354.334kmBinalong - Binalong

Rerailing AMP 60kg H/H (Single Leg Hi)

PO. Nick Moutos 06:00 18:00 0424 237 147Support. Bob

Peters 06:00 18:00 0439 623 761

Luke Bruntflett 06:00 18:00 0455 596 270

PO. Desa Conelly 04:00 16:00 0400 766 746Sig Elec. Callum

Nolan 04:00 16:00 0459 432 252

PO. Desa Conelly 06:00 18:00 0400 766 746Sig Elec. Callum

Nolan 06:00 18:00 0459 432 252

PO. Desa Conelly 08:00 20:00 0400 766 746Sig Elec. Callum

Nolan 08:00 20:00 0459 432 252

David Horder 06:00 18:00 0479 067 398

47 CAPRerailing AMPR - SIA #U

360.085km-360.690kmBinalong -

Galong

Rerailing AMP 60kg H/H (Both Legs)

PO. Nick Moutos 06:00 18:00 0424 237 147

PROTECTION OFFICER

N/A

PROTECTION OFFICER

WORKSITE SUPERVISOR

SIGNAL SUPPORT

WORKSITE CERTIFIER

0600 Sat to

1800 Mon

Up Main AMPRCAMS

Contractor / Plant

TBC

Steve Smith 0429

662 655

Nil / Limit Rail

Traffic During

LPA

LPA

Nil / Limit Rail

Traffic During

LPA

LPA

WORKSITE SUPERVISOR0600 Sat to

1800 Mon

Up Main AMPRCorfad

Contractor / Plant

TBC

Steve Smith 0429

662 655

SIGNAL SUPPORT

WORKSITE CERTIFIER

N/A

PROTECTION OFFICER

Sat to

1800 Mon

Up Main AMPRCorfad

Contractor / Plant

TBC

Smith 0429

662 655

Rail Traffic During

LPA

LPA N/A

WORKSITE CERTIFIER

Support. Bob Peters 06:00 18:00 0439 623 761

Luke Bruntflett 06:00 18:00 0455 596 270

PO. Desa Conelly 04:00 16:00 0400 766 746Sig Elec. Callum

Nolan 04:00 16:00 0459 432 252

PO. Desa Conelly 06:00 18:00 0400 766 746Sig Elec. Callum

Nolan 06:00 18:00 0459 432 252

PO. Desa Conelly 08:00 20:00 0400 766 746Sig Elec. Callum

Nolan 08:00 20:00 0459 432 252

David Horder 06:00 18:00 0479 067 398

48 CAPRerailing AMPR - SIA #V

362.070km-362.510kmBinalong -

Galong

Rerailing AMP 60kg H/H (Both Legs)

PO. Pori Pipi 06:00 18:00 0431 475 719Support. Elsie

Sing 06:00 18:00 0426 802 822

Shaun Bouma 06:00 18:00 0477 347 582

PO. Dina Cairns 04:00 16:00 0411 105 617Sig Elec. Chris

Birkby 04:00 16:00 0419 039 101

PO. Dina Cairns 06:00 18:00 0411 105 617Sig Elec. Chris

Birkby 06:00 18:00 0419 039 101

PO. Dina Cairns 08:00 20:00 0411 105 617Sig Elec. Chris

Birkby 08:00 20:00 0419 039 101

Shaun Bouma 06:00 18:00 0477 347 582

49 CAPRerailing AMPR - SIA #W

367.850km-368.132kmGalong - Cunnigar

Rerailing AMP 60kg H/H (Single leg Low RESURFACE)

PO. Pori Pipi 06:00 18:00 0431 475 719Support. Elsie

Sing 06:00 18:00 0426 802 822

Shaun Bouma 06:00 18:00 0477 347 582

PO. Dina Cairns 04:00 16:00 0411 105 617Sig Elec. Chris

Birkby 04:00 16:00 0419 039 101

PO. Dina Cairns 06:00 18:00 0411 105 617Sig Elec. Chris

Birkby 06:00 18:00 0419 039 101

PO. Dina Cairns 08:00 20:00 0411 105 617Sig Elec. Chris

Birkby 08:00 20:00 0419 039 101

Shaun Bouma 06:00 18:00 0477 347 582

50 CAPRerailing AMPR - SIA #X

453.269km-454.039km

Junee - Cootamund

raBethungra

Spiral

Rerailing AMP 60kg H/H (Single Leg Hi)

PROTECTION OFFICER

Nil / Limit Rail

Traffic During

LPA

LPA

WORKSITE SUPERVISOR0600 Sat to

1800 Mon

Up MainAMPRQuickw

ay

Contractor / Plant

TBC

Steve Smith 0429

662 655

SIGNAL SUPPORT

WORKSITE CERTIFIER

N/A

PROTECTION OFFICER

N/A

PROTECTION OFFICER

WORKSITE SUPERVISOR

SIGNAL SUPPORT

WORKSITE CERTIFIER

0600 Sat to

1800 Mon

Up MainAMPRQuickw

ay

Contractor / Plant

TBC

Steve Smith 0429

662 655

Nil / Limit Rail

Traffic During

LPA

LPA

Nil / Limit Rail

Traffic During

LPA

LPA

WORKSITE SUPERVISOR0600 Sat to

1800 Mon

Up Main AMPRCAMS

Contractor / Plant

TBC

Steve Smith 0429

662 655

SIGNAL SUPPORT

WORKSITE CERTIFIER

N/A

Adam Hartley 06:00 18:00 0477 119 124Anthony Grech 06:00 18:00 0498 181 096

Matthew Puttock 06:00 18:00 0424 380 992

PO. Anthony Neesom 04:00 16:00 0432 916 699

Sig Elec. Mick Every 04:00 16:00 0447 788 690

PO. Anthony Neesom 06:00 18:00 0432 916 699

Sig Elec. Mick Every 06:00 18:00 0447 788 690

PO. Anthony Neesom 08:00 20:00 0432 916 699

Sig Elec. Mick Every 08:00 20:00 0447 788 690

Matthew Puttock 06:00 18:00 0424 380 992

51 CAPTrack

reconditioning

155.900 km Resurfacing and Drainage

TO Luke Murray 0600 1800 0400 299 286

Regan Woolard 0600 1800 0428 664 111

SJM Dave McDowell 0408 919 770

Regan Woolard 0600 1800 0428 664 111

52 RCRMSPENO

Ultrasonic run

Start Junee on Up main and work on

a face capturing both main

lines to Yass

Ultrasonic testing of rail to identify internal rail flaws

SPENO 5th of September 0600 1800 0427666488

SPENO 6th of September 0600 1800 0427666488

SPENO 7th of September 0600 1800 0427666488

53 CAPSpeno Defect

RemovalJunee-Albury Defect Removal

Shane green 0600 1800 0477328764

Shane green 0600 1800 0477328764

M. vesperman 0600 1800 0427973979

A. wheeler 600 1800 o418429549

54 CAP

Level Crossing

Upgrade or Renewal

Demondrille to

Cootamundra

418.640-Upgrade - Wallendbeen, Lxing

Paul Casey 0600 1800 0427 320 609

Corey Nuku 0600 1800 0457 577 222

Jeff Bristow 0600 1800 0418 972 554SIGNAL SUPPORT

N/A

PROTECTION OFFICER

WORKSITE SUPERVISORDay Site Rep Main

Earthtrack

Solutions PL

Hi-Rail Excavators,

Hi-Rail Hydremas, Loaders &

Tools

Tofiq Ahmed

All Sites to make

necessary arrangements not to

hold Tampers

1 hour notice

requiredFull

WORKSITE SUPERVISOR

SIGNAL SUPPORT

WORKSITE SUPERVISOR

Day S.Green All Tracks Wagga pc

Multiple Plant and resources

S.Skates

SIGNAL SUPPORT

WORKSITE CERTIFIER

Signal Support as Required

PROTECTION OFFICER

WORKSITE SUPERVISOR

SIGNAL SUPPORT

Day Dave Izzard Up main AND Down main

SPENO - 740CIV

SPENO car and hirail for

hand testers

Michael Simons

SPENO will require

track access via the PPO

as worksites permit.

May have to jump around

worksites and

traverse back to capture testing

Requires windows

Hi rail excavators, Loaders,

dump trucks, water carts,

resurfacing team

Steven Twyford Total Block Full

possession

WORKSITE CERTIFIER

PROTECTION OFFICER

WORKSITE CERTIFIER

NIL

Contact Michael Simons - 0427666488

Saturday

Only Day

C.Moloney Up and Down Contractor

N/A

WORKSITE SUPERVISOR

SIGNAL SUPPORT

WORKSITE CERTIFIER

0600 Sat

1200 Sun

Up / Down Main

AMPRAnric

Contractor / Plant

TBC

Steve Smith 0429

662 655

Nil / Limit Rail

Traffic During

LPA

LPA

Corey Nuku 0600 1800 0457 577 222

55 CAPSpeno Defect

RemovalYass - Junee Defect Removal

Dave Izzard 0600 1800 0477328764

Dave Izzard 0600 1800 0477328764

Rowen Bradley 0600 1800

Dave Izzard 600 1800 418429549

56 RCRM Track Patrol Yass - Junee End of Possession Track Patrol

Dave Izzard 0600 1800 0477328764

Mick Simons 0600 1800 0427666488

57 RCRM Track Patrol

Moss Vale - Yass End of Possession Track Patrol

Jason Apps 0600 1800 0409688452

Jason Apps 0600 1800 0409688452

SIGNAL SUPPORT

WORKSITE CERTIFIER

1 hour notice

requiredFull Signal Support as Required

PROTECTION OFFICER

WORKSITE SUPERVISOR

Day Jason Apps All Tracks Goulburn PC

Multiple Plant and resources

Curtis McClella

nd

WORKSITE SUPERVISOR

SIGNAL SUPPORT

WORKSITE CERTIFIER

Multiple Plant and resources

Mick Simons

1 hour notice

requiredFull Signal Support as Required

PROTECTION OFFICER

Day Mick Simons All Tracks Coota PC

WORKSITE SUPERVISOR

SIGNAL SUPPORT

Multiple Plant and resources

Mick Simons

1 hour notice

requiredFull Signal Support as Required

PROTECTION OFFICER

WORKSITE CERTIFIER

Day Dave Izzard All Tracks Coota PC

WORKSITE CERTIFIER

PROJECT MANAGER

SITE SUPERVISOR

PROTECTION OFFICER

CIVIL CERTIFIER

SIGNAL CERTIFIER

Name / Mobile No / Email Address

Down Up KM From KM To(Name / Mobile

No.)(Name / Mobile

No.)DN UP

(Name / Mobile No.)

(Name / Mobile No.)

PLANT DESCRIPTION

MOVEMENT DATE

MOVEMENT TIMES

MOVEMENT FROM / TO

DATE OF CANCELLATION

REASON FOR CANCELLATION

1 04/09/202005/09/2020

2300 to 0600Shift 1 - Rail Grinding

(LORAM RG415)

Bojan Svigelj0427 202104

[email protected]

Berrima to Tahmoor

Up Main Full Possession 0 0 143.295 km 91.846 km YES 0 0Ex Moss Vale Yard travel

to BerrimaJack Rubery

(0439 290 676)Aaron Johnson (0491 200 923)

N/A143.295km

to 91.846km

NOJack Rubery

(0439 290 676)

SJMChris Weir

(0419 250139)

LORAM RG419 Rail Grinder

4th to 5th Sept. 2020

23:00 to 06:00Up Main

143.295 km to 91.846 km

2 44079 0600 to 1900Shift 2 - Rail Grinding

(LORAM RG415)

Bojan Svigelj0427 202104

[email protected]

Tahmoor to Glenlee Jnct.

Glenlee Jnct. to Leightonfield

Up Main

SSFL Single Line

Full Possession 0 0

91.486 km

58.275 km

58.275 km

23.000 km

YES 0 0 UP Main through to SSFLSean Noble

(0474 737 213)Dean Carlisle

(0400 054 584)N/A

91.846kmto

20.400kmNO

Sean Noble (0474 737 213)

Andrew Woodford(0418 282258)

LORAM RG419 Rail Grinder

5th Sept. 2020

06:00 to 19:00Up Main

91.846km to 20.400km

3 05/09/202006/09/2020

1900 to 0430Shift 3 - Rail Grinding

(LORAM RG415)

Bojan Svigelj0427 202104

[email protected]

Leightonfield to Sefton Dive

Glenlee to Bargo

SSFL Single Line

Down Main

Full Possession 0 0

23.000 km

57.657km

20.400km

103.000 km

YES 0 0

Complete SSFL then transfer from Sefton Dive to Glenlee Junction Dn

Main (TOA)

Jack Rubery (0439 290 676)

Aaron Johnson (0491 200 923)

20.400kmto

103.000kmN/A NO

Jack Rubery (0439 290 676)

SJMChris Weir

(0419 250139)

LORAM RG419 Rail Grinder

5th to 6th Sept. 2020

19:00 to 04:30Dn Main

20.400km to 103.000km

4 44080 0430 to 1830Shift 4 - Rail Grinding

(LORAM RG415)

Bojan Svigelj0427 202104

[email protected]

Bargo to Berrima

Berrima to Bundanoon

Down Main

Up MainFull Possession 0 0

103.000 km

143.295km

143.295 km

162.698 kmYES 0 0

Transfer from Down to Up Main at Berrima

Sean Noble (0474 737 213)

Dean Carlisle(0400 054 584)

103.000kmto

162.700kmN/A NO

Sean Noble (0474 737 213)

Andrew Woodford(0418 282258)

LORAM RG419 Rail Grinder

6th Sept. 2020

04:30 to 18:30Dn Main

103.000km to 162.700km

5 06/09/202007/9/2020

1830 to 0300Shift 5 - Rail Grinding

(LORAM RG415)

Bojan Svigelj0427 202104

[email protected]

Bundanoon to Lynwood

Up Main Full Possession 0 0 162.698 km 200.000km YES 0 0 Stable clear of Lynwood Jack Rubery

(0439 290 676)Aaron Johnson (0491 200 923)

N/A162.700km

to 200.000km

NOJack Rubery

(0439 290 676)

SJMChris Weir

(0419 250139)

LORAM RG419 Rail Grinder

6th to 7th Sept. 2020

18:30 to 03:00Up Main

146.000km to 200.000km

6 05/09 - 06/090600-1700 Sat

& SunOHW Guy Anchor Footing Construction

Keshab Shrestha0437 081 034

[email protected]

Sydney TrainsLeumeah to

CampbelltownSSFL, Up & Dn

MainFull Possession LPA LPA S53+165 S53+329 NO NO YES

Access to SSFL for construction of footings on

Up South Main at SW53+165 and

SW53+329 and implement safety buffer

No plants on SSFL track

Antonio Curtale0419 421 766

Philip Ibote0484863484

S53+165 to S53+329

S53+165 to S53+329

YESLupco Kotevski0421 055 593

N/A Mobile Plants5/09/2020 and

06/09/202006:00 to 1630 daily

S53+165 to S53+329

No mobile plants on ARTC/SSFL2xHi-Rail Excavator,

1xDumpy,1xConcrete Pump truck to work on Up & Dn South Mains

7 05/09 - 06/090600 to 1630

Sat & SunOHW Rustry Pipe Replacment

Anh Nguyen0435 510 665

[email protected]

Sydney TrainsMinto To Leumeah

Up and Down South Main

Full Possession LPA LPA S50+700 S53+ 500 NO NO YES

2 MVE track machines will be working on Up and Down South Mains. No

work will be pefomed on ARTC SSFL.

Dzung Tran/ 0457525020

Muhammad Ahmed 0450661335

S50+200 to S54+000

S50+200 to S54+000

YES N/A N/A MVE5/09/2020 and

06/09/202006:00 to 1630 daily

S50+700 t0 S53+500

2 MVE track machines will be working on Up and Down South Mains. No work will

be pefomed on ARTC SSFL.

8 05/09 - 06/090600-1700 Sat

& SunOHW Clockwork weights replacement

Keshab Shrestha0437 081 034

[email protected]

Sydney Trains Macarthur Up & Dn Main Full Possession LPA LPA 56.433 58.416 NO NO YES

Access to SSFL required for Hi-Rail plants to get on the Up & Dn at 58.371km (Glenlee S/S) and travel

towards Macarthur Station. No works planned

on ARTC/SSFL track. Permission is required to implement safety buffer.

Darren Brettell0409 822 430

Nyasha Simbi0414199008

S56+433 to S58+416

S56+433 to S58+416

YES N/A N/A Hi-Rail Plants05/09/2020'06/09/2020

Sat 0530hrs &1700hrs

Sun 0530 & 1700hrs

S58+416 to/from S56+433 both

days

3xHi-Rail Plants access/exit through take-off pad at S58+371 Glenlee S/S on the Up & Dn Mn ARTC/SSFL and travel towards Macarthur Station. No works planned on

ARTC/SSFL track.

9 05/09 - 06/090600 to 1800

Sat & SunMittagong Station TAP Upgrade

Peter Page0411 016 322

[email protected]

Degnan Mittagong Station Up & Dn Main Full Possession LPA LPA 131.35 131.65 NO NO YESTrack access through site can be provided with 30

minute notice

Scott Porteous0425 559 567

Mark Hudson0400 871 526

131.350 131.650 YESTrack CertifierAaron Swain0429 922 929

N/A

alluminium scaffold, EWP, Knuckle Boom,

trucks and manitau (TBA), crane trucks, excavator (small), tippers, ladders, minor plant/tools

5/09/2020 and 06/09/2020

06:00 to 1800 daily131.350 to

131.650

As part of our scope, it will be necessary to close the pedestrian bridge. Members of the public will be directed to use the

pedestrian crossing (@ 131.685km) to the south of the Mittagong Station.

Note: this wil be advertised to the public (letterbox drop, signage, etc).

10 5th to 6th September

2020

07:00 to 20:30Enfield 373B Points -

Retimbering 50 timbers(Access site via Joseph St - Enfield PC site)

Bojan Svigelj (0427 202 104)

[email protected]

ARTC(Rhomberg Rail)

Berrima to Enfield West

West Enfield - Up Goods Road

Full possession SP03 EW418 19.949 km 19.949 km YES YES 0

LPA LimitGlenlee GE23/36 Signal Berrima 188PtsDn Main

189Pts Up Main / Glenlee Clear of 65Pts

Enfield West EW418 - Clear of 354Pts & SP03

to Clear of 354Pts

Justin Male / 0419 440 288

Huessin Allami/ 0424 933 229

20.5 19.5 NOJustin Male / 0419

440 288Sigtech Callum

Nolan 0459432 252 Front End Loader,

Hyrail Excavator 5-6/9/20 0600-1800 19.5-20.5

11 5th Sept - 6th Sept 2020

0700 - 1800Comms Pit installation

Site Walk

Simon Weaver0427848145

[email protected]

Sydney ProjectsLeightonfield to

GlenleeSSFL Full Possession LF11, LF13

GF16, GF18, GF22

27 36 NO YES 0Sunday likely a spare day. Works expected to finish

Saturday

Mohammad Obeid 0491061599

Hussein Al-Lami 27.000 36.000 NO Dan Wakefield N/AHydro Vac and

excavator 44079 0.291666667

12 4407906:00am - 18:00pm

Structure inspections of tunnels via hi-rail EWP

Matthew Dal Santo - 0472 501 080 -

[email protected]

Sterling Infrastructure

Picton Tunnel to Maldon Bridge

Rd

Hi-rail EWP only needs access to

one track - flexible for possession

manager to propose which track would suit

best

Full possession MN32 Dist. MN3 81.5 88 NO NO NO

Hi-rail access via Maldon Bridge road, unless a

closer access pad can be located

Matthew Dal Santo / 0472 501 080

Glen Charles / 0412 155 313 81,500KM 88,000KM YES N/A N/A Hi-Rail EWP 05/09/2020 Between 06:00am

and 18:00pm81,500KM - 88,000KM

Protection plan to be provided once completed

13 4407906:00am - 18:00pm

Structure inspections of tunnels via hi-rail EWP

Matthew Dal Santo - 0472 501 080 -

[email protected]

Sterling Infrastructure

Bowral tunnel to Railway Rd Burradoo

Hi-rail EWP only needs access to

one track - flexible for possession

manager to propose which track would suit

best

Full possession 82.5 87.4 134.9 140 NO NO NOHi-rail access via Railway

Rd, unless a closer access pad can be located

Liam Fetherston / 0429 506 414

Leanne Gray / 0422 208 208 134,900KM 140,000KM YES N/A N/A Hi-Rail EWP 05/09/2020 Between 06:00am

and 18:00pm134,900KM - 140,000KM

Protection plan to be provided once completed

14 4407906:00am - 18:00pm

Structure inspections of bridges via hi-rail EWP

Matthew Dal Santo - 0472 501 080 -

[email protected]

Sterling Infrastructure

Sefton area

Hi-rail EWP only needs access to

one track - flexible for possession

manager to propose which track would suit

best

Full possession EW407 LF6 20 22 NO NO NOAccess via access pad

near 47 Wellington Street, Birrong

Liam Fetherston / 0429 506 414

Leanne Gray / 0422 208 208 100,000KM 121,000KM YES N/A N/A Hi-Rail EWP 06/09/2020 Between 06:00am

and 18:00pm100,000KM - 121,000KM

Protection plan to be provided once completed

15 4408006:00am - 18:00pm

Structure inspections of tunnels via hi-rail EWP

Matthew Dal Santo - 0472 501 080 -

[email protected]

Sterling Infrastructure

Aymerton Tunnel to Great

Southern Road access pad,

Bargo

Hi-rail EWP only needs access to

one track - flexible for possession

manager to propose which track would suit

best

Full possession 303 80.8 100 125.5 NO NO NO

Hi-rail access via access pad near Great Southern

Rd in Bargo unless an access can be located

closer

Liam Fetherston / 0429 506 414

Leanne Gray / 0422 208 208 100,000KM 125,500KM YES N/A N/A Hi-Rail EWP 06/09/2020 Between 06:00am

and 18:00pm100,000KM - 125,500KM

Protection plan to be provided once completed

16 4408006:00am - 18:00pm

Structure inspections of tunnels via hi-rail EWP

Matthew Dal Santo - 0472 501 080 -

[email protected]

Sterling Infrastructure

Yerrinbool Tunnel to Great Southern Road

access pad, Bargo

Hi-rail EWP only needs access to

one track - flexible for possession

manager to propose which track would suit

best

Full possession 303 119 100 121 NO NO NO

Hi-rail access via access pad near Great Southern

Rd in Bargo unless an access can be located

closer

Matthew Dal Santo / 0472 501 080

Glen Charles / 0412 155 313 20,000KM 22,000KM YES N/A N/A Hi-Rail EWP 06/09/2020 Between 06:00am

and 18:00pm20,000KM - 22,000KM

Protection plan to be provided once completed

PROJECT CANCELLATION

CANCELLATION

PROJECT SCOPE DATE

WORKSITE PROTECTING SIGNAL NUMBER

Noise and public

notifications - Internal (See notes

below)

POSSESSION BID - PART BPOSSESSION BID - PART A

NOTES & COMMENTS

WORK HOURS

All lines/Main/Loop

/Up Main / Down Main - Single - Up

Goods/Bot / Dn Goods/ Bot

Possession Required (eg)

Windows / Full Possession /

PSW

SECTION (TO - FROM)

NOTES & COMMENTS

Protection Plan

completed and attached

(Yes/No)

WORKSITE LOCATION

Noise and public

notifications - External (See notes

below)

Do the works affect

signalling systems? (Yes/No)

PROTECTION KMProject No

CLOSEDPossession Bid - Part A Due: Possession Bid - Part B Due: CLOSED

Config 14 - Enfield to Berrima (SIA)2020 Possession.

POSSESSION WORK MATRIX V1

ON TRACK PLANT

ORGANISATION

175th & 6th

Septemper 2020

0600-1800

Undercutting Team 1

o Location 1: Down Main: 130 030-130 090km & Up Main: 130.000-130.155km

(Undercutting through T/Outs)o Location 2: Up Main: 113.250-113.400km

(Undercutting through T/Outs)

Tofiq AhmedPh: 0437 959 279

Email: [email protected]

TBCTennessee to

MittagongUp & Down Mains -

Tennessee to Mittagong

Track Machines can pass through

Undercuttting Sites with prior

arrangements made with Project Manager and Site

Supervisor

0 0 21.6 130.155 NO YES YES 0Paul Follington:

Ph: 0419 197 410 Wayne McDonald : Ph: 0414 358 262

0 0 0Paul Follington: Ph:

0419 197 410 0

Hi-Rail Excavators, Tip Trucks, Loader

05-06/09/2020 0600-1800 hours 111.300-130.155 0

185th & 6th

Septemper 2020

0600-1800

Undercutting Team 2o Up Arrival Road: 143.300-143.400km

o Up Arrival: 146.020-145.880km (Through T/Outs)

Tofiq AhmedPh: 0437 959 279

Email: [email protected]

TBC Moss Vale Yard Up Arrival Road

Track Machines can pass through

Undercuttting Sites with prior

arrangements made with Project Manager and Site

Supervisor

0 0 143.3 146.02 YES YES YES 0Anthony Martinuzzo:

Ph: 0410 510 005 Hasmukh Lal:

Ph: 0452 390 7880 0 0

Anthony Martinuzzo: Ph: 0410 510 005

0Hi-Rail Excavators, Tip Trucks, Loader

05-06/09/2020 0600-1800 hours 143.300-145.980 0

195th & 6th

Septemper 2020

0600-1800Undercutting Team 3

o Dn Main: 145.880-145.960km (Through T/Outs)

Tofiq AhmedPh: 0437 959 279

Email: [email protected]

TBC Moss Vale Yard Down Main

Track Machines can pass through

Undercuttting Sites with prior

arrangements made with Project Manager and Site

Supervisor

0 0 145.88 145.96 YES YES YES 0Chris Pennings: Ph:0422 441 113

David Joseski : Ph:0410 530 775

0 0 0Anthony Martinuzzo:

Ph: 0410 510 005 0

Hi-Rail Excavators, Tip Trucks, Loader

05-06/09/2020 0600-1800 hours 145.915-146.020 0

205th & 6th

Septemper 2020

0600-1800

Track Resurfacing (09-32 Tamper)o Dn Main: 82.300-86.000kmo Up Main: 94.500-95.000kmo Up Main: 97.000-97.300kmo Up Main: 95.000-94.300kmo Up Main: 86.800-85.100km

o Dn Main: 106.800-107.500kmAdditional Tamping Locations as per updated

Scope

Tofiq AhmedPh: 0437 959 279

Email: [email protected]

Laing O'Rourke Aust PL

Maldon to Tennessee

Up & Down Main

Worksites to make necessary

arrangements not to hold the Tampers

0 0 82.3 107.5 YES YES YES 0Phill Webb

Ph: 0409 716 934 Vince Constatino Ph: 0408 890 612

0 0 0Phill Webb

Ph: 0409 716 934 0

09-32 Tamper & Regulator

05-06/09/2020 0800-2000 hours 85.100-131.700 0

21

5th & 6th Septemper

20200600-1800

Turnout & Plain Track TamperoUp Arrival Road: 143 300-143 400km

oDn Main: 145 880-145 960km (Through T/Outs)

oUp Arrival: 146 020-145 880km (Through T/Outs)

oDown Main: 130 030-130 090km & Up Main: 130 000-130 155km

oUp Main: 113.250-113.400km

Tofiq AhmedPh: 0437 959 279

Email: [email protected]

Laing O'Rourke Aust PL

Moss Vale Yard & Moss Vale to

Mittagong

Up Arrival RoadUp & Down Main

Worksites to make necessary

arrangements not to hold the Tampers

0 0 146.025 113.25 YES YES YES 0Jeff McGrath

Ph: 0409 473 944 Maurice Sharp

Ph: 0407 209 0080 0 0

Jeff McGrathPh: 0409 473 944

0Jackson Tamper &

Regulator05-06/09/2020 1200-2330 hours 130.000-146.500 0

225th & 6th

Septemper 2020

0600-180021.000-Track Remediation - Sefton Dive

Track Undercutting and Ballasting

Tofiq AhmedPh: 0437 959 279

Email: [email protected]

TBC Sefton Dive Down Goods 0 0 0 20.97 21.966 NO YES YES 0Joseph Gunn

Ph: 0408 208 142Wilfred Ndeda

Ph: 0478 018 5530 0 0

Kyle WardPh: 0427 800 823

0Hi-Rail Excavators, Tip Trucks, Loader

05-06/09/2020 0600-1800 20.750-22.000 0

235th and 6th September

2020

06:00hrs to 18:00hrs

Resurfacing, monitoring equipment maintenance

Chris Bloor 0422 807 231

[email protected]

BloorRail / SIMECTahmoor to

PictonUp and Down Main Full Possession 0 0 88.5 94 NO NO YES 0

Chris Jacobsen 0409 006 398

Jim Beggs 0413 561 016

88.500km 93.500km NOChris Jacobsen

0409 006 398N/A

09-32 Tamper and SSP110 Regulator

5th and 6th September

06:00hrs and 17:00hrs

A, 84.000km Picton Siding to

90.000km Worksite B, 90.000km

Worksite to 98.000km

Tahmoor Colliery and RTN C, 90.000km

Worksite to 84.000km Picton

Siding

A, WAR on Up Main, B, 17:00hrs Sat Transfer machine to Down Main at

Tahmoor Colliery stable on Down Main overnight, C, 17:00hrs Sun WAR on Down Main and stable in Picton Up Siding upon

completion

245th and 6th September

2020

06:00hrs to 18:00hrs

Track maintenance and monitoring equipment maintenance

Chris Bloor 0422 807 231

[email protected]

BloorRail / S32Menagle to

MaldonUp and Down Main Full Possession 0 0 68 76 NO NO YES 0

Craig Stuckey 0428 231 139

Bruno Pertout 0428 191 087

68.000km 76.000km NOBruno Pertout

0428 191 087N/A Hi Rails Various Various Various Hirails can be moved clear at anytime

25 04/09/202005/09/2020

2230 Fri to 2350 Sat

AMPR Rail TrainNate Gomes

0428 286 [email protected]

AMPRTHEE Rail

Pacific National

Berrima to Glenlee to

BerrimaUp and Down Full Possession 0 0 70 57 NO YES YES

See RT tab for Movement plan

Shift 1. Fri 2230-0700

Alex Dennis0429 998 841

Shift 2. Sat 0700 - 1700

Jed Holdsworth0438 008 117

Shift 1. Fri 2100-0700

Katelin O'Hara0438 718 082

Shift 2. Sat 0700 - 1700

Paul Casey0427 320 609

70.000km 58.000km NOJed Holdsworth0438 008 117

Nick Litchenberger0437 991 059

Rail TrainFEL

Hi Rail Excavator

4th and 5th September

22:00 to 23:50 0

Pilot: Shift 1. Fri 2100-0700 Andrew Sepping 0417 804 689

Shift 2. Sat 0700 - 1700 Brian Hilditch 0481 435 424

Shift 3. Sat 1700 - 0100 Andrew Sepping 0417 804 689

26 05/09/202006/09/2021

06:00hrs to 18:00hrs

Scrap Rail RecoveryNate Gomes

0428 286 [email protected]

AMPR Berrima to Mittagong

Up and Down Full Possession 0 0 135 140 NO YES YES 0 ???? ???? 134.000km 141.000km NO ????Nick Litchenberger

0437 991 059Hi Rails

5th and 6th September

06:00 to 18:00Daily

Various 0

27 05/09/2020 06/09/2020

07.00HRS/ 16.30HRS

Welding / Speno defect removal on the SSFL- 1X Welding crews various locations

Steve Chance -0418 630 440-

[email protected].

ARTC Glenlee / Sefton All Single line full 19 58.1 YES NO NO

1x wellding team, with contracr PO and

excavator. Removing speno rail defects at

Various locations on t6hs SSFL .km54.600

km51.061 km49.163 km36.450 km23.762

paul pearce 0418 435 727

Lang O Rouke Protection Office

25.000 58.000 NOpaul pearce 0418

435 727Ingelbrun Sgnal

Welding / Speno defect removal on the

SSFL- 1X Welding crews various

locations

1x wellding team, with contracr PO and excavator. Removing speno rail defects at

Various locations on t6hs SSFL .km54.600 km51.061 km49.163 km36.450

km23.762

28 05/09/2020 06/09/2020

07.00HRS/ 17.00HRS

Welding / Speno defect removal on the - 1X Welding crews various locations

Steve Chance -0418 630 440-

[email protected].

ARTCmittagong/

tahmoorup/dn mains full 100 000 130 000 NO YES YES

1x wellding team, with contracr PO and

excavator. Removing speno rail defects at

Various locations on the up and Down main ,

Between Mittagong and Tahamoor .km102.750 km103.320 km126.517 km128.230 km127.250

Scott Richerson 0416910391

SRS Solultion Protection Office

131.500 95.000 NOJosh Moran 0419690624

Ingelbrun Sgnal

Welding / Speno defect removal on the on the up and Down mains - 1X Welding

crews various locations

1x wellding team, with contracr PO and excavator. Removing speno rail defects at

Various locations on the up and Down main , Between Mittagong and Tahamoor

.km102.750 km103.320 km126.517 km128.230 km127.250

29 05/09/2020 06/09/2020

07.00HRS/ 16.30HRS

Clear out drains / remove mud and silk/ Lift and Pack through the Sefton dive to remove

TSR with Hi Rail Excavator.

Steve Chance -0418 630 440-

[email protected].

ARTC Sefton Dive All Single line full 20.4 21.966 NO YES YES

drainage cleaning at Sefton dive pumps area to remove silk spoil from drains, Plus remove rail

out of the dive area, Plus lift and pack through the Sefton dive to remove

TSR with Hi Rail Excavator,

Graham Doherty 0418881872

Under Tofiq Protection Officer

Contractor PO WORKS at Sefton

dive

20.000 21.200 NOGraham Doherty

0418881872

Clear out drains / remove mud and silk/ Lift and Pack through

the Sefton dive to remove TSR with Hi

Rail Excavator.

Clear out drains / remove mud and silk/ Lift and Pack through the Sefton dive to

remove TSR with Hi Rail Excavator.

30 05/09/2020 06/09/2020

16.00hrs to 00.00hrs

track patrol on the SSFL to berrima

Steve Chance -0418 630 440-

[email protected].

ARTCEnfield west to

Picton

All lines/Main/Loop/Up Main / Down Main -

Single - Up Goods/Bot / Dn

Goods/ Bot

full 17.8 143 000 NO NO NOEnd of Possession track Patrol from Enfield West

/Picton

Graham Doherty 0418881872

Josh Moran 0419690624

17.700 143.000 NOGraham Doherty

0418881872track patrol on the SSFL to Berrima

17.700 143.000 track patrol on the SSFL to Berrima

31 05/09/2020 06/09/2020

07.00HRS/ 16.30HRS

RCM Maintainance

Steve Chance -0418 630 440-

[email protected].

ARTCEnfield West to

Glenlee All Single line full 19 58.1 NO NO NO RCRM WORKS MST

Ardalan Esfandiari ( 0420 504 683 )

James Gent (0404360876)

Nil Nil NO NA NA Nil Nil Nil Nil Look out working only

32 05/09/2020 06/09/2020

07.00HRS/ 16.30HRS

track centre measuring

Steve Chance -0418 630 440-

[email protected].

ARTC maldon- tahmoor up/dn mains full 78 000 98 000 NO NO NOtrack centre measuring

crewadam davidson

0427561315rod odea

0427561315mobile crew NO

adam davidson 0427561315

n/a n/a 78 000 98 000 track centre measuring crew

33 05/09/2020 06/09/2020

07.00HRS/ 16.30HRS

solar greasepot install

Steve Chance -0418 630 440-

[email protected].

ARTC picton-yerrinbool up/dn mains full 90 000 120 000 NO NO NOinstall connect solar rail

lubricatorp hokianga

0432 579 175b pertout

042819108789 500 119 000

91 000 120 500

NOJosh Moran 0419690624

n/a n/a 90 000 120 000install connect solar rail lubricator (picton j beggs 0413561016)

(yerrinbool b pertout 0428191087)

34 5-6/09/200700 - 1900 Day

ShiftsSignal Maintenance

Danial Whitty/ 0427 412 004/

[email protected]

ARTC Possession Limits All Lines Full Possession N/A N/A TBC TBC YES NO NOSignal Maintenace works to be confirmed based on

tasks due under RCRM.

Day Shift - Matt McHugh, PH: 0434

487 713

Day Shift - Matt McHugh, PH: 0434

487 713

Possession Limits LOW

Only

Possession Limits

LOW OnlyNO N/A

Day Shift - Matt McHugh, PH: 0434

487 713N/A N/A N/A N/A

Works to be carried out mainly off track, minimal on track work to be undertaken

under LOW arrangements.

35 5-6/09/201900 - 0700 Night Shifts

Signal Maintenance

Danial Whitty/ 0427 412 004/

[email protected]

ARTC Possession Limits All Lines Full Possession N/A N/A TBC TBC YES NO NOSignal Maintenace works to be confirmed based on

tasks due under RCRM.

Night Shift - Chase Abbott, PH: 0458

077 967

Night Shift - Kieren Mullen, PH: 0427

868 289

Possession Limits WIC

Only

Possession Limits WIC

OnlyNO N/A

Night Shift - Chase Abbott, PH: 0458

077 967N/A N/A N/A N/A

All work to be WIC only. No work on track to be undertaken on night shifts outside of

daylight hours.

36 5-6/09/20 04:00 to 10:00Remove Axle Counters along SSFL prior to

Rail Grinding

Dan Whitty0427 412 004

[email protected]

ARTCSSFL

Macarthur to Enfield West

SSFL Single Line Full Possession 0 0 58.275km 20.435km YES YES 0

39 Worksite Locations where Axle Counters are

to be removed prior to Loram Rail Grinder

commences rail grinding the SSFL

Dan Whitty(0427 412 004)

Dan Whitty(0417 392 398)

20.435km 58.275km NO N/ADan Whitty

(0427 412 004)Nil

5th Sept. 2020

04:00 to 10:00SSFL

58.275km to 20.435km

Off track movements along SSFL route between Macarthur and Enfield West

37 5-6/09/20 12:00 to 24:00Replace & Recalibrate Axle Counters along

SSFL after completion of Rail Grinding

Dan Whitty0427 412 004

[email protected]

ARTCSSFL

Enfield West to Macarthur

SSFL Single Line Full Possession 0 0 20.435km 58.275km YES YES 0

Hi-Rail run to replace and recalibrate Axle Counters

at 39 locations after Loram Rail Grinder has

completed rail grinding the SSFL

Dan Whitty(0427 412 004)

Todd Holland (TVO)(0409 990 620)

20.435km 58.275km NO N/ADan Whitty

(0427 412 004)ARTC

Hi-Rail Vehicle6th

Sept. 202012:00 to 24:00

SSFL20.435km to

58.275km

HiRail vehicle moving between 39 axle counter sites along SSFL from Enfield

West and Macarthur

38 Friday04/09/2020

0700 to 1200Menangle 67.255km Remove Wayside

DeviceAlan Shore

(0409 368 122)ARTC

Glenlee - Douglas Park

Up Main ATP 0 42.6 67.255 67.255 0 YES NO

Removal required prior to rail gridning scheduled for

0845 Saturday 5th September 2020.

Alan Shore(0409 368 122)

Greg Boyd (0411 514 345)

067.200 to

67.300NO

Alan Shore(0409 368 122)

N/A N/A 0 0 0Removal required prior to rail gridning

scheduled for 0845 Saturday 5th September.

39 Sunday06/09/2020

0700 to 1200Menangle 67.255km Reinstate & Recalibrate

Wayside DeviceAlan Shore

(0409 368 122)ARTC

Glenlee - Douglas Park

Up Main Possession 0 42.6 67.255 67.255 0 YES NOReinstatement required

following completion of rail gridning

Alan Shore(0409 368 122)

Greg Boyd (0411 514 345)

067.200 to

67.301NO

Alan Shore(0409 368 122)

N/A N/A 0 0 0Reinstatement required following

completion of rail grinding

40 Friday04/09/2020

0700 to 1200Burradoo 138.020km Remove Wayside

DeviceAlan Shore

(0409 368 122)ARTC

Bowral - Berrima Junction

Down Main ATP 84.5 0 138.02 138.02 0 YES NO

Removal required prior to rail gridning scheduled for

0730 Sunday 6th September 2020.

Alan Shore(0409 368 122)

Greg Boyd (0411 514 345)

137.950 to 138.050

0 NOAlan Shore

(0409 368 122)N/A N/A 0 0 0

Removal required prior to rail gridning scheduled for 0730 Sunday 6th

September.

41 Sunday06/09/2020

1200 to 1800Burradoo 138.020km Reinstate &

Recalibrate Wayside DeviceAlan Shore

(0409 368 122)ARTC

Bowral - Berrima Junction

Down Main Possession 84.5 0 138.02 138.02 0 YES NOReinstatement required

following completion of rail gridning

Alan Shore(0409 368 122)

Greg Boyd (0411 514 345)

137.950 to 138.051

0 NOAlan Shore

(0409 368 122)N/A N/A 0 0 0

Reinstatement required following completion of rail grinding

42 Saturday05/09/2020

0700 to 1200Exeter 155.400km

Remove Wayside DeviceAlan Shore

(0409 368 122)ARTC

Moss Vale - Bundanoon

Up Main Possession 0 155.4 155.4 155.4 0 YES NO

Removal required prior to rail gridning scheduled for

19:30 Sunday 6th September 2020.

Alan Shore(0409 368 122)

Greg Boyd (0411 514 345)

0155.350 to

155.450NO

Alan Shore(0409 368 122)

N/A N/A 0 0 0Removal required prior to rail gridning

scheduled for 19:30 Sunday 6th September.

43Mon.-Wed.

07/09/2020 - 09/09/2020

0700 to 1200Exeter 155.400km

Reinstate & Recalibrate Wayside DeviceAlan Shore

(0409 368 122)ARTC

Moss Vale - Bundanoon

Up Main ATP 0 155.4 155.4 155.4 0 YES NOReinstatement required

following completion of rail gridning

Alan Shore(0409 368 122)

Greg Boyd (0411 514 345)

0155.350 to

155.451NO

Alan Shore(0409 368 122)

N/A N/A 0 0 0Reinstatement required following

completion of rail grinding

445-6

September 2020

Sat 0700 – 1800 Sun 0700 – 1800

Inspect culverts Site 2 - Leumeah Water Way, 1 52.34km

- Leumeah Smiths Creek, 52.442km - Leumeah Water Way 2, 52.88km

annabelle Webb / 0412823174/

[email protected]

SydneyTrains Leumeah SSFL Lookout working 0 0 52 53 NO NO NOAccess only to get get

access to SydneyTrains culverts for inspections

Tristan Marwood (0415 369 933)

Jamil Kassem 0405 505 566

Nil Nil NO NA NA Nil Nil Nil Nil Look out working only

45 5-6 September

TBC Test SSFL and all Turnout to Moss ValeJosh Moran 0419

690 624 Speeno Chullora Jctn Moss Vale Possession 0 0 17.540 146.00 YES 0 0 Moving Worksite

Sam Cross 0431 848 346

Bob Cone 0455 625 360

0 0 0 0 0 Hi Rail Truck and RRV 0 0 0 Speeno Ultrasonic Testing

0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

Signalling: If answer is Yes then the "Signal Support Form" is to be filled in and sent to the relevant Signal WGL and approved by the SME prior to Section B being submitted

Noise Requirements:

Internal - Has assessment been conducted for the works using the ARTC Noise Construction Tool to identify affected sensitive receivers, and has notification been completed or is it planned to be completed to affected sensitive receivers a minimum 5 days prior to works commencing?

External - Has a noise assessment been conducted to identify noise impacts, and have affected sensitive receivers been notified, or planned to be notified a minimum 5 days prior to works commencing?

RELEVANT PHONE NUMBERS

EMERGENCY SERVICES:INJURY HOTLINE: 1800 686 130 ENVIROLINE: 1300 550 402 [email protected]

SIA CORRIDOR MANAGER: PROJECT DELIVERY MANAGER: STRUCTURES SPECIALIST: SIA PLC:

Site based

Kane Lean 0436 323 813Thomas Haffner 0427 416 995

Wael Naser 0428 263 361Raul Agoho 0427 104 430 Anthony Godfrey 0407 066 418Deane Thrower 0477 385 470

AREA MANAGER INGELBURN:AREA MANAGER GOULBURN:

Warren Williams 0438 672 296Steven Chance 0418 630 440Curtis McClelland 0429 016 107

SIA WORKS PLANNING MANAGER:

AREA SAFETY ADVISOR:ENVIROMENTAL ADVISOR:

Shift 1 Shift 2 Shift 3 Shift 4 Shift 5 Shift 604/09/2020 05/09/2020 05/09/2020 06/09/2020 06/09/2020 07/09/2020

2300 - 0500 06:30 -1200 Maintenance 1900 - 0430 0430 - 1330 Maintenance 1830 - 0100 0300 - 1200Berrima 143 23:00Mittagong 135 8 23:45 Up MainAlymerton 124 11 0:45Tennessee 113 11 1:45 SSFLBargo 103 10 2:45Tahmoor Colliery 98 5 3:15 Down MainRed Bank 92 6 51 3:45 6:30Picton 85 7 7:15Maldon 82 3 7:30Douglas Park 73 9 8:30Menengle Park 63 10 9:30Glenlee/SSFL 58 5 10:00Glenfield 41 17 12:00Cabramatta 32 9 60 12:00 Maintenance 19:00Leightonfield 23 9 20:00End LPA 20 3 21:00

TransferGlenlee/SSFL 58 38 22:00Menengle Park 63 5 22:30 19 125000 2375000Douglas Park 73 10 23:30 50Maldon 82 9 0:30 950 2500Picton 85 3 0:15Tahmoor Colliery 98 13 1:30Bargo 103 5 57 2:00 4:30Tennessee 113 10 5:30Alymerton 124 11 6:30Mittagong 135 11 7:30Berrima 143 8 8:30Moss Vale 147 4 9:00Exter 155 8 10:00Bundanoon 162 7 59 11:00 250000

Transfer 47Moss Vale 147 15 13:00 Maintenance 18:30 5319.149Exter 155 8 19:30Bundanoon 162 7 20:30Wingello 177 15 22:00Medway 189 12 23:00Lynwood 194 5 47 1:00 3:00Towarang 208 14Goulburn 222 28 42 12:00

Up Main Total 174SSFL Total 38Down Main 104Grand Total 316

Location Km Grind KmsShift Total

Pass KmTransfer

Kms

Leightonfield Cabramatta

Speno (Fri 2230-0300) 22:30 23:30

Signal Restoration (1200-2400 Sun) 12:00

Tunnel Inspection (Sun ) Team1Sefton Dive Undercutting/Ballasting (Sat & Sun: 0700-1700)RG Shift 2 (Sat 0630 -1200) 12:00

Cabramatta Loop (0600-1800)RG Shift 3 (Sat 1900 - 0430) 21:00 19:00

Transfer to Glenlee354

217 221

Speno (Fri 2230-0300) 0:30 1:30 2:30

Signal Restoration (1200-2400 Sun) 12:00

RG Shift 2 (Sat 0630 -1200) 11:00 10:00 9:30

Sydney Trains (0600-1800)Rail Train Unload 11:30

65

222 223

38

57.600

58Glenfield Loop Macarthur Jct

56 5751 52 53 54 5539 40 41 42 43 44 45 46 47 48 49 50

34 35 36 3729 30 31 32 3320.400 21.500

20.800 22 23 24 25 26 27 2822.434

DIVE

RG Shift 3 (Sat 1900 - 0430) 22:00 Sat 23:00

Speno (0500 - 0600) 4:30 5:00

Rail Train Unload 7:00 9:00

Empty Rail Train Glenlee - Moss Vale 18:00 Sat

Down 66 61 93 90 94 95

Up 65 60 91

SSFLSpeno (0300 - 0500) 2:30

Rail Train Unload 5:30 0:30 0:00

RG Shift 2 (Sat 0630 -1200) 9:30 8:30 7:30

Signal Restoration (1200-2400 Sun)Rail Train Unload 11:30 9:30

Tahmoor Colliery

RG Shift 3 (Sat 1900 - 0430) 0:00 Sun 1:00 Sun 2:00 SunLORA 09-32 Tamper (Sun 0830-2030-Dn Mn) SUNBloor Tamper (Sat 0600 - 1800) SATEmpty Rail Train Glenlee - Moss Vale 18:30 Sat

Down 100 106 108 112 114 310 1

Up 105 110 C 311Rail Train 23:30

RG Shift 1 (Fri 2300-0500) 5:00

RG Shift 2 (Sat 0630 -1200) 6:30

LORA 09-32 Tamper (Sat 0800-2000-Up Mn) SAT SAT SATBloor Tamper (Sun 0600 - 1800) SUNTunnel Inspection (Sat ) Team1

RG Shift 3 (1900 - 0430) 2:30 SunRG Shift 4 (Sun 0430 - 1330) 4:30 5:30 SunLORA 09-32 Tamper (Sun 0830-2030-Dn Mn) SUNEmpty Rail Train 19:30 Sat

Down

UpRail Train 23:00

RG Shift 1 (Fri 2300-0500) 4:00 3:00

LORA 09-32 Tamper (Sat 0800-2000-Up Mn) SATUndercutting Team (Sat 0700-1700) 100m

RG Shift 4 (Sun 0430 - 1330) 6:30 Sun 7:30 Sun 8:30 SunLORA 09-32 Tamper (Sun 0830-2030-Dn Mn) SUN SUN SUNUndercutting Team (Sun 0700-1700) 60m

LORA Jackson Tamper (Sun 1330-2300)Empty Rail Train 20:30 Sat 21:00 Sat

Tunnel Inspection (Sat ) Team 2Degman Mittagong Platform Sat & Sun 0600 -1800

Down 3 188

Up 2 189

57.657

57.600

Alymerton144

Berrima Jct

Douglas Park

91

Tenessee121116115

94

132130 131

89

143142

120

140 141134 135 136

Menangle Bridge

126 127

Picton

105 106 107 108 109

82 83 85 86 87

63 64

88

110

Mittagong

Menangle

95 96 97

77

98

76

9993

112 113 114

75

117 118 119

70 71 72 73 74

92

6968

90

137 138 139

81

6256 57 58 59

84

60 61

78 79 80Maldon

65 66 67

122 123 124 125

111100 101 102 103 104

133128 129

Degman Mittagong Platform Sat & Sun 0600 -1800Rail Train 22:30

RG Shift 1 (Fri 2300-0500) 2:00 1:00 23:00

LORA 09-32 Tamper (Sat 0800-2000-Up Mn) SAT SAT SATLORA 09-32 Tamper (Sun 0900-1000-Up Mn) SunUndercutting Team (Sun 0700-1700) 100mLORA Jackson Tamper (Sun 1330-2300)Tunnel Inspection (Sun ) Team 2

RG Shift 4 (Sun 0430 - 1330) 9:00 10:00 11:00 Transfer to Moss Vale50,51 Bridge Repairs

72 Exeter Platform ResurfacingBrimble Rail 07-275 Tamper (Sat 0700-1800, Sun 0600-1730) SAT SAT SAT SUN SUN

Down

Up72 Exeter Platform Recon 06:00 Sat

50,51 Bridge Repairs32 3BB Points Undercutting 06:00 Sat

Rail Train 7:00

Rail Unload57 ReRail

Brimble Rail 07-275 Tamper (Sat 0700-1800, Sun 0600-1730) SAT SAT SUN SUNRG Shift 5 (Sun 1830 - 0100) 18:30 Sun 19:30 20:30

28 Steel Component Change outTallong Bridge repairs

Down

Up

Steel Component Change outRail Train

3 Tallong Bridge repairsRG Shift 5 (Sun 1830 - 0100) 21:30 22:30 23:30

Undercutting Team 1 (Sat & Sun 0700-1700) SAT SUN SUN SUNUndercutting Team 2 (Sat & Sun 0700-1700) SUN SATBrimble Rail Unimat Tamper (Sun 1200-2330) SUN

Brimble Rail Unimat Tamper (Sun 1200-2330) SUN

Undercutting Team 2 (Sat & Sun 0700-1700) SAT

Down

Up

Rail Train 22:30 Fri29 Lockersleigh Bridge repairs

Towrang L-Xing UpgradeRG Shift 5 (Sun 1830 - 0100) 0:30 1:00

RG Shift 6 (Mon 0300 - 1200) 3:00 6:00

Undercutting Team 2 (Sat & Sun 0700-1700) SATBrimble Rail Unimat Tamper (Sun 1200-2330) SUN SUN SUN

GoulburnBrimble Rail Unimat Tamper (05/09/2020: 1200 to 06/09/2020: 2330)

Bridge Inspection7 Storm Damage Repairs

30,31 Gbn Yard 39-42Down

Up117 Points RenewalStorm Damage RepairsRG Shift 6 (Mon 0300 - 1200) 9:00 12:00

Bridge Inspection

Brimble Rail Unimat Tamper (05/09/2020: 1200 to 06/09/2020: 2330)SUN

230.600230 231224 225 226 227 228 229221 222 223211 212 213 214 215 216

23:00 - 23:30

03:00 - 06:00

192 193 194 195 208 209

186 187 188169

210Medway Marulan Lynwood

202 203 204 205 206 207196 197 198 199 200 201190 191

168159 160 161 162 163 164

189176 177 178 179 180 181 183 184 185

24:00 - 03:00

35

Wingello182

38

165 166 167BundanoonExeter

153 154 155 156 157 158

Sat: 1200 to Sun 1200

Sat: 1200 to Sun 1200SUN

148 149 150 151 152

170 171 172 173 174 175

147.995

148.099

219

197.346

197.500

217 218 220

RRA 09-3X Tamper (Sat 0700 - Mon 1600) SAT SAT SAT SAT SAT SAT SAT5,6 Retransom/ReRail

Down

Up

5,6 Retransom/ReRailRRA 09-3X Tamper (Sat 0700 - Mon 1600) SUN SUN SUN SUN

RRA 09-3X Tamper (Sat 0700 - Mon 1600) SAT SAT SAT SAT SAT SUNUndercutting Team 3 (Sat, Sun & Mon 0700-1700) SUN

Down

Up59 ReRail

RRA 09-3X Tamper (Sat 0700 - Mon 1600) SUN SUN SUN SUN SUN SUN SUN SUN SUNUndercutting Team 3 (Sat, Sun & Mon 0700-1700) SUN

RRA 09-3X Tamper (Sat 0700 - Mon 1600) SUN SUN SUN SUN MON MON MON

60 ReRail

Down

UpRRA 09-3X Tamper (Sat 0700 - Mon 1600) SUN MON MON MON MONUndercutting Team 3 (Sat, Sun & Mon 0700-1700) SAT

61 RerailRRA 09-3X Tamper (Sat 0700 - Mon 1600)

Down

Up

62 ReRail

RRA 09-3X Tamper (Sat 0700 - Mon 1600) MON MON MON

310

298

321311 312 313 314 315 316

292

317 318 319 320

286

305 306 307 308 309299 300 301 302 303 304

251 252

274 275

297293 294 295 296287 288 289 290 291281 282 283 284 285

271 272 273265 266 267 268 269 270264

238 239 240 241

253 254 255 256 257 259 260 261 262 263

230.600

248 249 250242 243 244 245 246 247

580m Single Leg

553m Single Leg

235230 231 232 233 234

258

236 237

276 277 278 279 280

RRA 09-3X Tamper (Sat-Mon: 0600-1600) SAT SAT SAT

Down

Up

64 ReRail

RRA 09-3X Tamper (Sat-Mon: 0600-1600) MON

RRA 09-3X Tamper (Sat-Mon: 0600-1600) SAT SAT SAT SAT SAT

Down

Up

65 ReRail

66 ReRail

67 ReRail68 ReRail

RRA 09-3X Tamper (Sat-Mon: 0600-1600) MON MON MON

RRA 09-3X Tamper (Sat-Mon: 0600-1600) SAT SAT SAT SUN SUNSpeno (Mon)

Down

Up

69 ReRail

RRA 09-3X Tamper (Sat-Mon: 0600-1600) SUN SUN SUN SUN

RRA 09-3X Tamper (Sat-Mon: 0600-1600) SUN MON27 Wallendbean Yard. TO Removal

Speno (Mon)

Down

Up27 Wallendbean Yard. TO Removal

RRA 09-3X Tamper (Sat-Mon: 0600-1600) SUN SUN MON

Speno (Sun)TRA Jackson Tamper (Sat-Mon: 0600-1600) SUN SUN SAT SAT SAT SATWallendbean l-Xing

43 Signalling System Upgrade8,9 Temora Road

Down

Up8,9 Temora Road 43 Signalling System Upgrade

TRA Jackson Tamper (Sat-Mon: 0600-1600) SUN SUN MONSpeno (Mon)

Speno (Sun)TRA Jackson Tamper (Sat-Mon: 0600-1600) SAT SAT SAT SAT SAT

Down

Up

70 ReRail

TRA Jackson Tamper (Sat-Mon: 0600-1600) MON MONSpeno (Sat)Speno (Mon)

Speno (Sun)Down

Up

Speno (Sat)

`

Down

Up

481 482 483 484 485

476 477 478 479458 459 460 461 462 463 480470 471 472 473 474 475464 465 466 467 468 469

435 436 437 438 439 440 453 454 455447 448 449 450 451 452

433 434424 425 426 427 428 429

441 442 443 444 445 446 456 457

412 413 414 415 416 417 430 431 432

401 402 403 404 405 406

418 419 420 421 422 423

397 398 399 400

386 387 388383 384 385

407 408 409 410 411

380 381 382374 375 376 377 378 379366 367 368 369 370 371 372 373

389 390 391 392 393 394 395 396

364 365354 355 356 357 358 359353

338 339 340325

360 361 362 363

358m Single Leg

331

352

320 321 322 323 324

348 349 350 351

484.932

484.564

917m Single Leg

543m Single Leg

280m Single Leg

739m Single Leg

341 342

343 344 345 346 347

332 333 334 335 336 337326 327 328 329 330

Speno (Sat)37,38 Junee 116b , 122 points

TRA 09-2X Tamper (Sat & Mon: 0600-1600) MON MON SAT SAT48 Harefield L-Xing Upgrade

Speno (Sat)TRA 09-2X Tamper (Sat & Mon: 0600-1600) SAT SAT MON MON

TRA Jackson Tamper (Sat 1700 - Sun 2200) SUN SUN SUN SUN SUN11 Uranquinty L-Xing Upgrade

TRA Jackson Tamper (Sat 1700 - Sun 2200) SUN SAT

TRA Jackson Tamper (Sat 1700 - Sun 2200) SAT SUN53 Grubbin Road. install45 Henty L-Xing Upgrade

641 642 643 644 645635 636 637 638 639 640629 630 631 632 633 634623 624 625 626 627 628

600 601 602 603 604 605 618 619 620612 613 614 615 616 617

598 599589 590 591 592 593 594

606 607 608 609 610 611 621 622

577 578 579 580 581 582 595 596 597

566 567 568 569 570 571

583 584 585 586 587 588

562 563 564 565561

552 553548 549 550

572 573 574 575 576

532 533 534 535 536 537 538

560

551

529 530519 520 521 522 523 524

554 555 556 557 558 559

545 546 547539 540 541 542 543 544531

517 518

503 504 505490

525 526 527 528

488 489

513 514 515 516

484.392

484.564

Junee

Henty

506 507

508 509 510 511 512

497 498 499 500 501 502491 492 493 494 495 496485 486 487

04/09/2020 Stable at Picton Yard - 84.449km Up Refuge

05/09/2020 0800 hours Crew start at Picton Yard and Complete PWB 0830 hours Tamper Travel to 85.100km Up Main Site

0845-1145 hours Tamp Up Main: 85.100km-86.800km1200-1330 hours Tamp Up Main: 94.300-95.000km1345-1430 hours Tamp Up Main: 97.000-97.300km1500-1615 hours Tamp Up Main: 111.500-112.100km 1645-1745 hours Tamp Up Main: 125.300-125.700km1800-1930 hours Tamp Up Main: 129.000- 129.700km

05/09/2020 1930-2000 hours Stable Tamper at 131.076km Up Main - Mittagong Junction

06/09/2020 0830 hours Crew start at 131.076km Up Main - Mittagong Junction and Complete PWB 0900-1000 hours Tamp Up Main:131.200-131.700km1000-1030 hours Transfer Tamper at 130.140km 3C Pts from Up Main to Down Main and Reverse to 131.700km 1030-1130 hours Tamp Down Main: 131.700-131.200km1145-1300 hours Tamp Down Main: 129.700-129.000km1315-1430 hours Tamp Dn Main:126.300-125.750km1500-1630 hours Tamp Dn Main:107.500-106.800km1700-2000 hours Tamp Dn Main: 86.150-83.130km

05/09/2020 2000-2030 hours Transfer Tamper at 81.820km 106 Pts from Down Main to Up Main and Reverse back to 84.400km 110 Pts and Stable Tamper at Picton Up Refuge

LORA 09-32 Tamper Movements

04/09/2020 Stable at Moss Vale Yard

05/09/2020 1200 hours Crew start at Moss Vale Yard and Complete PWB 1230-1530 hours Tamp Up Main: 144.400-144.700km (Includes T/O)1545-1845 hours Tamp Up Main: 145.800-146.100km (Includes T/O) - 40m Undercutting 1900-2200 hours Tamp Dn Main: 145.800-146.200km (Includes T/O) - 100m Undercutting

05/09/2020 2200-2230 hours Stable Tamper at Moss Vale Yard

06/09/2020 1200 hours Crew start at Moss Vale Yard and Complete PWB 1230-1330 hours Tamp Up Arrival Road 143.300-143.400km 1330-1400 hours Travel Tamper at Down Main to 131.900km1400-1600 hours Tamp Down Main: 131.900-131.700km (Includes T/O)1600-1630 hours Transfer Tamper at 130.140km 3C Pts from Down to Up Main and Reverse to 131.900km 1630-1830 hours Tamp Up Main: 131.900-131.700km (Includes T/O)1845-2045 hours Tamp Up Main: 130.000-130.300km (Includes T/O)2100-2300 hours Tamp Down Main: 130.000-130.200km (Includes T/O)

06/09/2020 2300-2330 hours Stable Tamper at Breamar Branch Line.

LORA Jackson Tamper Movements

04/09/2020 Stable at Picton Yard - 84.449km Up Refuge

05/09/2020 0800 hours Crew start at Picton Yard and Complete PWB 0830 hours Tamper Travel to 85.100km Up Main Site

0845-1145 hours Tamp Up Main: 85.100km-86.800km1200-1330 hours Tamp Up Main: 94.300-95.000km1345-1430 hours Tamp Up Main: 97.000-97.300km1500-1615 hours Tamp Up Main: 111.500-112.100km 1645-1745 hours Tamp Up Main: 125.300-125.700km1800-1930 hours Tamp Up Main: 129.000- 129.700km

05/09/2020 1930-2000 hours Stable Tamper at 131.076km Up Main - Mittagong Junction

06/09/2020 0830 hours Crew start at 131.076km Up Main - Mittagong Junction and Complete PWB 0900-1000 hours Tamp Up Main:131.200-131.700km1000-1030 hours Transfer Tamper at 130.140km 3C Pts from Up Main to Down Main and Reverse to 131.700km 1030-1130 hours Tamp Down Main: 131.700-131.200km1145-1300 hours Tamp Down Main: 129.700-129.000km1315-1430 hours Tamp Dn Main:126.300-125.750km1500-1630 hours Tamp Dn Main:107.500-106.800km1700-2000 hours Tamp Dn Main: 86.150-83.130km

05/09/2020 2000-2030 hours Transfer Tamper at 81.820km 106 Pts from Down Main to Up Main and Reverse back to 84.400km 110 Pts and Stable Tamper at Picton Up Refuge

Tamper #: 1: LORA 09-32 Tamper Movements

04/09/2020 Stable at Moss Vale Yard

05/09/2020 1200 hours Crew start at Moss Vale Yard and Complete PWB 1230-1530 hours Tamp Up Main: 144.400-144.700km (Includes T/O)1545-1845 hours Tamp Up Main: 145.800-146.100km (Includes T/O) - 40m Undercutting 1900-2200 hours Tamp Dn Main: 145.800-146.200km (Includes T/O) - 100m Undercutting

05/09/2020 2200-2230 hours Stable Tamper at Moss Vale Yard

06/09/2020 1200 hours Crew start at Moss Vale Yard and Complete PWB 1230-1330 hours Tamp Up Arrival Road 143.300-143.400km 1330-1400 hours Travel Tamper at Down Main to 131.900km1400-1600 hours Tamp Down Main: 131.900-131.700km (Includes T/O)1600-1630 hours Transfer Tamper at 130.140km 3C Pts from Down to Up Main and Reverse to 131.900km 1630-1830 hours Tamp Up Main: 131.900-131.700km (Includes T/O)1845-2045 hours Tamp Up Main: 130.000-130.300km (Includes T/O)2100-2300 hours Tamp Down Main: 130.000-130.200km (Includes T/O)

06/09/2020 2300-2330 hours Stable Tamper at Breamar Branch Line.

Tamper #: 2: LORA Jackson Tamper

Track Km From Km To Length (m) Priority Ballast Stockpile Location Comments Shift Undercutting Team

Up Main 130.000 130.155 100 P1Ballast Stockpile at 129.900km- Downside (Access from

Ferguson St, Mittagong) Undercutting through 3C Pts Turnout Saturday: 05/09/2020 0700-1700 hours

Up Main 111.300 111.400 40 P1 Ballast Stockpile (250T) at 111.500km Upside

Up Main 111.650 111.850 60 P2

This site to source 100 Tonne ballast from 111.500km Upside Stockpile and remaining 140 Tonne to be sourced from

113.500km Upside Stockpile

Down Main 145.900 145.980 80 P1Ballast Stockpile (800T) at 145.140km Lackey Road, Moss Vale

Upside Laydown Area Undercutting through 152B Pts Turnout Saturday: 05/09/2020 0700-1700 hours

Up Arrival 143.300 143.400 60 P2Ballast Stockpile (200T) at 143.500km-Downside

Access from McCourt Road, Moss ValeSunday: 06/09/2020 0700-1700 hours

Up Main 146.010 146.020 10 P1Up Main 145.960 146.000 40 P2 Undercutting through 158A Pts Turnout

Up Main 145.915 145.940 25 P2 Undercutting through 149B PtsSunday: 06/09/2020 0700-1700 hours

Note:

Undercutting Team #: 3 may need to join Undercutting Team #: 1 on Sun 06/09/2020 to complete undercutting at Up Main: 111.650-111.850km

Undercutting - Tenessee to Moss Vale

Undercutting Team #: 1Sunday: 06/09/2020 0700-1700 hours

Undercutting Team #: 2Moss Vale Yard

Ballast Stockpile (800T) at 145.140km Lackey Road, Moss Vale Upside Laydown Area

Saturday: 05/09/2020 0700-1700 hours Undercutting Team #: 3

Moss Vale Yard

04/09/2020 Stable at Moss Vale Yard

05/09/2020 0630 hours Crew start at Moss Vale Yard and Complete PWB 0700-0730 hours Travel Tamper free at Up Main to 155.936km Exeter0730-1000 hours Tamp Up Main: 156.936-155.607km: (Includes Tamping in Exeter Platform area)1010-1130 hours Regulate and Broom High Ballast at Up Main: 149.500-148.350km1130-1230 hours Tamp Up Main: 147.034-146.896km (Includes Undercutting Sites: 147.034-147.014km, 147.001-146.992km & 146.905-146.896km)1230-1300 hours Transfer Tamper at 146.278km 161B Pts Moss Vale from Up to Down Main and Travel Free to 155.607km Exeter Site1300-1530 hours Tamp Down Main: 155.607-157.250km: (Includes Tamping in Exeter Platform area)1530-1700 hours Tamp Down Main: 157.950-159.280km1700-1730 hours Tamp Down Main: 161.510-161.800km

05/09/2020 1730-1800 hours Stable Tamper at 161.800km Down Main

06/09/2020 0530 hours Crew start at 161.800km Bundanoon and Complete PWB 0600-1200 hours Tamp Down Main: 161.800-162.700km and Tamp Up Main: 162.700-162.100km (Includes 3BB Pts Crossover - 3BB Crossover needs min 30mm lift)1200-1330 hours Tamp Up Main: 162.700-164.210km1340-1700 hours Tamp Up Main: 165.030-167.500km

06/09/2020 1700-1730 hours Reverse Tamper at Up Main to 162.353km Bundanoon and Stable at Bundanoon Up Refuge Siding.

Tamper #: 3: Brimble Rail Plasser (07-275) Tamper Movements

04/09/2020 Stable at Goulburn Yard

05/09/2020 1130 hours Crew start at Goulburn Yard and Complete PWB

1200 hours on 05/09/2020 to 1200 hours on 06/09/2020

06/09/2020 1130 hours Crew start at Goulburn Yard and Complete PWB 1200-1330 hours Tamp Up Main: 224.140-223.150km1345-1420 hours Tamp Up Main: 205.100-204.890km1430-1600 hours Tamp Up Main: 193.300-192.740km (Undercutting completed on 05/09/2020 at 193.045-193.053km, 192.902-192.91km, 192.882-192.894km & 192.87-192.878km)1600-1800 hours Tamp Up Main: 192.440-190.880km (Undercutting Completed on 05/09/2020 at 192.350-192.352km)1810-1930 hours Tamp Up Main: 188.400-187.360km (Undercutting Completed on 05/09/2020 at 188.165-188.17km, 188.09-188.091km & 188.045-188.062km)1930-2000 hours Reverse Tamper at Up Main to 189.649km-51 Pts Medway and Transfer from Up to Down Main2000-2130 hours Tamp Down Main: 192.150-193.010km (Undercutting Completed on 06/09/2020 at 192.810-192.812km & 192.960-192.966km)2145-2300 hours Tamp Down Main: 224.050-225.000km

06/09/2020 2300-2315 hours Stable Tamper at Goulburn Yard

Tamper #: 4: Brimble Rail Unimat Tamper Movements

Complete Tamping at 17A,B & C Pts Goulburn Yard and additional Tamping as per ARTC Project Manager/ARTC Resurfacing Representative Instructions

03/09/2020 Stable at Goulburn Yard

04/09/2020 2230-2330 hours Skeleton Crew to travel Tamper from Goulburn Yard to Goulburn South Refuge Loop and Stable till 0700 hours on 05/09/2020

05/09/2020 0630 hours Crew start at 231.330km Down Main site and complete PWB0700-0730 hours Tamp Down Main: 231.330-231.730km0730-0800 hours Tamp Down Main: 232.450-232.610km0800-0830 hours Tamp Down Main: 233.450-234.060km0830-1000 hours Tamp Down Main: 234.410-236.430km1010-1100 hours Tamp Down Main: 238.390-239.500km1115-1215 hours Tamp Down Main: 245.900-247.090km1230-1300 hours Tamp Down Main: 247.710-248.140km1300-1345 hours Tamp Down Main: 248.900-250.000km1400-1445 hours Tamp Down Main: 253.180-253.990km1445-1615 hours Tamp Down Main: 254.120-256.400km1700-1730 hours Tamp Down Main: 257.550-258.000km1740-1815 hours Tamp Down Main: 259.200-260.490km

1815-1830 hours Crew Changeover

1830-1900 hours Night Shift Crew complete PWB1900-1945 hours Tamp Down Main: 260.880-261.580km2000-2200 hours Tamp Down Main: 262.300-265.300km2210-2240 hours Tamp Down Main: 266.400-266.960km2250-2330 hours Tamp Down Main: 267.150-267.790km2340-0040 hours Tamp Down Main: 268.430-269.660km

06/09/2020 0050-0120 hours Tamp Down Main: 270.190-270.510km0130-0230 hours Tamp Down Main: 275.500-276.930km0240-0340 hours Tamp Down Main: 278.090-279.500km0350-0420 hours Tamp Down Main: 280.550-281.200km0430-0500 hours Tamp Down Main: 281.790-282.290km

0500-0630 hours Reverse Tamper at Down Main through to 230.400km Joppa Jnc 102 Pts and Transfer from Down Main to Up Main- Crew Changover at 0630 hours

06/09/2020 0630-0700 hours Day Shift Crew complete PWB0700-0730 hours Tamp Up Main: 235.000-235.400km0740-0830 hours Tamp Bridge Approaches at Up Main: 235.950-236.000km (City Approach) & 236.018-236.068km (Country Approach)0840-0910 hours Tamp Up Main: 239.280- 239.800km0930-1230 hours Tamp Up Main: 242.900-247.080km1240-1315 hours Tamp Up Main: 252.400- 253.250km1330-1430 hours Tamp Up Main: 254.120-255.200km1440-1600 hours Tamp Up Main: 259.290-260.085km 1615-1700 hours Tamp Up Main: 263.070-264.700km1715-1815 hours Tamp Up Main: 266.600-267.710km

1815-1830 hours Crew Changeover

06/09/2020 1830-1900 hours Night Shift Crew complete PWB1900-2000 hours Tamp Up Main: 268.490-269.480km2010-2110 hours Tamp Up Main: 270.190-271.000km2120-2200 hours Tamp Up Main: 271.300-271.800km2210-2240 hours Tamp Up Main: 274.540-274.940km2250-0020 hours Tamp Up Main: 278.000-279.630km

07/09/2020 0030-0150 hours Tamp Up Main: 280.550-281.790km0200-0250 hours Tamp Up Main: 283.780-284.430km0300-0350 hours Tamp Up Main: 289.080-289.900km0400-0530 hours Tamp Up Main: 294.950-296.460km0530-0630 hours Tamp Up Main: 296.740-297.400km

07/09/2020 0630-0700 hours Day Shift Crew complete PWB0700-0930 hours Tamp Up Main: 298.100-300.970km0940-1040 hours Tamp Up Main: 303.420km-304.010km - Single Leg 60kg Rail Replaced that requires Superelevation Correction1100-1200 hours Tamp Up Main: 314.080-315.000km

1200-1230 hours Transfer Tamper from Up Main to Down Main at 315.179km-51Pts and Reach 282.810km Re-Railing Site1230-1430 hours Tamp Down Main: 284.350-282.810km (Single Leg 60kg Rail Replaced that requires Superelevation Correction between 282.810-283.360km)1445-1520 hours Tamp Down Main: 291.260-291.550km

07/09/2020 1530-1600 hours Travel Tamper to 318.296km-56Pts Yass and Stable at Yass Yard

Tamper #: 5: RRA 09-3X Tamper Movements (Joppa to Yass)

Track Km From Km To Length (m) Shift CommentsUp main 146.896 146.905 9Up main 146.992 147.001 9Up main 147.014 147.034 20Up main 170.325 170.340 15Up main 170.350 170.352 2Up main 170.370 170.372 2Up main 170.424 170.430 6Up main 170.477 170.480 3Up main 170.500 170.501 1Up main 170.510 170.511 1

UP MAIN 173.494 173.500 6UP MAIN 173.562 173.580 18UP MAIN 173.714 173.720 6UP MAIN 173.746 173.750 4UP MAIN 173.772 173.780 8UP MAIN 173.790 173.800 10UP MAIN 173.866 173.900 4UP MAIN 173.940 173.950 10UP MAIN 174.020 174.022 2UP MAIN 174.040 174.041 1UP MAIN 174.140 174.143 3UP MAIN 174.330 174.332 2UP MAIN 174.355 174.356 1UP MAIN 174.520 174.523 3UP MAIN 174.710 174.713 3UP MAIN 174.760 174.623 3Up main 178.586 178.600 14Up main 178.620 178.640 20Up main 178.650 178.668 18Up main 178.665 178.670 5

DOWN MAIN 178.679 178.690 11DOWN MAIN 178.703 178.710 7

Up main 178.706 178.710 4Up main 178.715 178.720 5

DOWN MAIN 178.736 178.740 4DOWN MAIN 178.756 178.760 4

UP MAIN 178.790 178.792 2Up main 184.004 184.049 45Up main 185.435 185.439 4Up main 185.910 185.913 3Up main 185.922 185.930 8Up main 186.100 186.130 30Up main 186.155 186.170 15Up main 186.422 186.435 13Up main 188.045 188.062 17Up main 188.090 188.091 1Up main 188.165 188.170 5Up main 192.350 192.352 2

Down Main 192.810 192.812 2Up main 192.870 192.878 8Up main 192.882 192.894 12Up main 192.902 192.910 8

Down Main 192.960 192.966 6Up main 193.045 193.053 8Up main 263.190 263.216 26

Down Main 265.152 265.167 15 Down Main 265.189 265.191 2 Down Main 265.243 265.245 2

Up main 291.750 291.800 50Tuesday

0700-1700 hours

Saturday 0700-1700 hours

Undercutting Team 3: Starts at 185.435km and Finishes at 291.800km

Sunday 0700-1700 hours

Monday 0700-1700 hours

Undercutting - Moss Vale to Yass

Saturday 0700-1700 hours

Undercutting Team 1: Starts at 146.896km and Finishes at 174.523km

Sunday 0700-1700 hours

Saturday 0700-1700 hours

Undercutting Team 2: Starts at 174.710km and Finishes at 184.049km

Sunday 0700-1700 hours

04/09/2020 Stable at Yass Yard

05/09/2020 0630 hours Crew start at Yass Yard and complete PWB0700-0800 hours Tamp Down Main: 324.210-325.070km0800-0830 hours Tamp Down Main: 325.690-326.280km0815-0930 hours Tamp Down Main: 338.500-340.100km0940-1010 hours Tamp Down Main: 342.330-342.610km1030-1130 hours Tamp Down Main: 343.040-343.950km1145-1215 hours Tamp Down Main: 349.980-350.390km1230-1300 hours Tamp Down Main: 354.340-354.450km1300-1330 hours Tamp Down Main: 354.760-355.090km1345-1415 hours Tamp Down Main: 357.120-357.540km1430-1515 hours Tamp Down Main: 367.130-367.790km1515-1540 hours Tamp Down Main: 367.870-368.150km1600-1800 hours Tamp Down Main: 384.450-386.500km1800-1830 hours Stable at Harden Yard Up Goods Siding

06/09/2020 0630 hours Crew start at Harden Yard and complete PWB0700-0900 hours Tamp Down Main: 386.500-389.000km0900-0930 hours Transfer Tamper at 388.282km-110 Pts Harden from Down to Up Main and Reverse to 389.520km0930-1000 hours Tamp Up Main: 389.520-389.250km1015-1215 hours Tamp Up Main: 386.400-384.700km1230-1315 hours Tamp Up Main: 382.950-382.150km1330-1415 hours Tamp Up Main: 375.400-374.720km1415-1445 hours Tamp Up Main: 374.510-374.190km1500-1530 hours Tamp Up Main: 368.150-367.850km (Single Leg 60kg Rail Replaced that requires Superelevation Correction at 367.850km-368.132km)1530-1600 hours Reverse Tamper at Up Main back through to 407.580km Wallenbeen Site1600-1830 hours Complete portion of Tampinig at 407.580-409.800Km Up Main (Wallendbeen Straight Railing Site) - TSR at Up Main: 407.580-409.800Km

1830 hours Stable at 408.010km Up Main

07/09/2020 0630 hours Crew start at 408.010km Wallendbeen and complete PWB0700-1030 hours Complete required Tamping at Up and Down Main at 407.920-408.010km Wallendbeen Straight Railing Site - TSR at Dn Main: 407.950-408.150km1030-1100 hours Transfer Tamper from Down to Up Main at 388.282km Harden 110Pts and travel free following shunt tes loco to 355.700km site1100-1145 hours Tamp Up Main: 355.700-355.000km1200-1330 hours Tamp Up Main: 354.550-353.190km (Single Leg 60kg Rail Replaced that requires Superelevation Correction at 353.790km-354.334km)1345-1530 hours Tamp Up Main: 348.300-346.100km (Single Leg 60kg Rail Replaced that requires Superelevation Correction at 348.290km-347.370km)1545-1630 hours Tamp Up Main 334.930km-334.580km (Single Leg 60kg Rail Replaced that requires Superelevation Correction)1630-1700 hours Travel Tamper to Yass and Stable at Yass Yard.

Tamper #: 6: RRA 09-3X Tamper Movements (Yass to Wallendbeen)

04/09/2020 Stable Tamper at Bethungra Yard

05/09/2020 0630 hours Crew start at Bethungra Yard and complete PWB0700-0830 hours Tamp Down Main: 452.780-452.130km0830-1000 hours Tamp Down Main: 451.620-450.400km1010-1115 hours Tamp Down Main: 448.400-447.880km1130-1230 hours Tamp Down Main: 436.940-436.180km1245-1415 hours Tamp Down Main: 435.580-434.140km1430-1515 hours Tamp Down Main: 433.420-433.030km1530-1730 hours Tamp Down Main: 432.230-430.150km1730-1800 hours Stable Tamper at Cootamundra Yard

06/09/2020 0530 hours Crew start at Cootamundra Yard and complete PWB0600-1700 hours Tamp 428.956km Temora Road, Cootamundra Level Crossing Five Tracks and adjacent Turntouts (Tamping of Down Main must cover: 427.260-429.360km)

1730 hours Stable Tamper at Cootamundra Yard

07/09/2020 0700 hours Crew start at Cootamundra Yard and complete PWB0730-0900 hours Tamp Up Main: 431.060-430.000km

0900-1030 hours

1030-1230 hours Tamp Up Main: 453.269km-454.039km (Single Leg 60kg Rail Replaced that requires Superelevation Correction)1300-1600 hours Tamp Up Main: 442.750-445.560km1600-1645 hours Travel Tamper free at Up Main to Cootamundra and Stable at Cootamundra Yard

Tamper #: 7: TRA Pandrol Jackson Tamper Movements (Cootamundra to Bethungra)

Transfer Tamper from Up to Down Main at 430.023km-133 Pts, Travel to 456.194km Bethungra 3B Pts, transfer from Down to Up Main and reach Re-Railing site at 454.039km (Shunt Test Loco Travelling to Cootamundra at Up Main)

04/09/2020 Stable at Junee Yard

05/09/2020 0630 hours Crew start at Junee Yard and complete PWB0700-0730 hours Travel Tamper free to 499.000km Harefield0730-1030 hours Tamp 499.000-502.500km1045-1130 hours Tamp 504.320-505.100km1140-1400 hours Tamp 508.000-511.000km1410-1520 hours Tamp 512.270-513.700km1530-1600 hours Travel Tamper to Wagga and Stable at Wagga Yard

06/09/2020 0630-1800 hours

07/09/2020 0600 hours Crew start at Wagga Yard and complete PWB0630-0645 hours Travel Tamper to 527.180km Site0645-1015 hours Tamp 527.180-524.000km1015-1030 hours Travel Tamper to Wagga Loop for Shunt Test Loco to pass at Main Line towards Uranquinty1030-1230 hours Tamp 522.500-520.570km1300-1400 hours Tamp 496.400-495.700km (Undercutting completed duirng possession at 496.350-496.355km)1400-1530 hours Tamp 495.300-494.000km (Undercutting completed during possession at 494.400-494.405km, 494.100-494.105km, 494.040-494.045km)1545-1630 hours Tamp 484.570-484.300km (Undercutting completed during possession at 484.560-484.565km, 484.340-484.370km)1630-1645 hours Stable Tamper at Junee Yard

Tamper #: 8: TRA 09-2X Tamper Movements (Junee to Wagga)

Keep Tamper Stabled at Wagga Yard (This Tamper Crew to Operate Tamper 9 - TRA Pandrol Jackson - 0400-1500 hours on 06/09/2020 between Uranquinty and Henty)

04/09/2020 Stable at Yerong Creek Yard-Goods Siding Southern End Only (Enter Goods Siding from Southern End: 565.236km Only)

05/09/2020 1630 hours Crew start at Yerong Creek Yard and complete PWB1700-1730 hours Travel Tamper free to 577.500km Grubben Road Level Crossing Site1730-2100 hours Tamp 578km Grubben Road Level Crossing Site2140-0115 hours Tamp 567.000-565.242km Passing Lane

06/09/2020 0130-0245 hours Tamp 560.700-560.050km 0245-0345 hours Travel Tamper to 579.700km Sladen Street, Henty Level Crossing Site and stable at 570.700km

06/09/2020 0400 hours Day Shift Crew Start at 0400 hours at 579.700km

06/09/2020 0400-0430 hours Day Shift Crew start at 579.700km and complete PWB0430-0700 hours Tamp 580.200km Sladen Street Level Crossing Site at Main and Loop Line Includes Turnout Tamping0700-0900 hours Travel Tamper to 536.029km Yarragundry Street, Uranquinty Level Crossing Site0900-1200 hours Tamp 535.580-535.480km Yarragundry Street Level Crossing Site at both Main Line and Loop Line - Includes Turnout Tamping1200-1400 hours Tamp 535.580-536.500km Mainline

1400 hours Stable Tamper at 536.500km

06/09/2020 1400 hours Crew Start shift at 536.500km and complete PWB1430-1530 hours Tamp 535.050-535.480km Passing Lane1440-2040 hours Tamp 534.500-531.500km2100-2200 hours Tamp 545.500-546.000km Mainline

06/09/2020 2230 hours Stable Tamper at 550.500km The Rock Yard

Tamper #: 9: TRA Pandrol Jackson Tamper Movements (Henty to Uranquinty)

Prior to possession test the following:

Main Line, Passing Lanes and Loops as required Albury to Wagga. Fernleigh Road 524.546km.

Run Light to Bomen. Test Passing Lane.

Run Light to Shepherds Siding 504.660km.

Test Shepherds Siding 504.660km to Marinna 478.138km

Main Line, Loops, Up Main and Down Main as required.

Test Up Main Bethungra 456.611km to Olympic Highway 449.872km

Saturday 5th

On Track Fernleigh Road 524.546km test Main Line to Test Shepherds Siding 504.660km.

Including Viaduct.

Travel to Marinna 478.138km

On Track Marinna 478.138km test UP Main Line to Bethungra 456.611km

41.413km

Sunday 6th

On Track Cootamundra Cowcumbla Road 430.753km test Down Main Line to Marinna 478.138km

Change Tracks.

On Track Marinna 478.138km test UP Main Line to Marinna Bethungra 456.611km

68.912km

Monday 7th

On Track Olympic Highway 449.872km test UP Main Line to Cootamundra 430.753km

Travel to Cunningar

On Track Cunningar 381.153km test DOWN Main Line to Cootamundra 430.753km

Tuesday 8th

On Track Cootamundra 430.753km test UP Main Line to Cunningar 381.153km

49.600km

Then As Traffic Permits

Date Time Scope Base Code Location Dur Km From Km To Comments

04/09/2020 22:00 Put on Track ??? 0:30 Put on at ????04/09/2020 22:30 Run to test 0:1004/09/2020 22:40 Test Track 12986 Southern Sydney Freight Line 0:15 20.421 22.30404/09/2020 22:55 Test Track 14986 Southern Sydney Freight Line 0:20 20.660 24.28304/09/2020 23:15 Shunt to test Southern Sydney Freight Line 0:15 24.283 22.57304/09/2020 23:30 Test Track 11471 Leightonfield Loop 0:10 22.573 24.28304/09/2020 23:40 Test Track 14986 Southern Sydney Freight Line 0:35 24.283 28.21005/09/2020 00:15 Test Track 14986 Southern Sydney Freight Line 0:55 31.774 39.34705/09/2020 01:10 Test Track 17986 Glenfield Loop 0:10 39.347 41.47505/09/2020 01:20 Shunt to test Southern Sydney Freight Line 0:15 41.475 39.34705/09/2020 01:35 Test Track 14986 Southern Sydney Freight Line 1:35 41.475 58.09205/09/2020 03:10 Test Track 13922 Glenlee 66 Crossover 0:25 58.107 58.25105/09/2020 03:35 Run to test 0:0505/09/2020 03:40 Test Track 13711 Glenlee 61 Crossover 0:25 59.265 59.34505/09/2020 04:05 Run to test 0:0505/09/2020 04:10 Test Track 13899 Glenlee 93 Crossover 0:25 60.251 60.42405/09/2020 04:35 Run to test 0:0505/09/2020 04:40 Test Track 13343 Glenlee 90 Crossover 0:25 60.495 60.54005/09/2020 05:05 Run to test 0:1005/09/2020 05:15 Test Track 13926 Menangle Park 94 Crossover 0:25 62.941 63.05105/09/2020 05:40 Test Track 13927 Menangle Park 95 Crossover 0:25 63.069 63.17905/09/2020 06:05 Take Off Track 0:30 Take off at ????Menangle Park 95 Crossover

Date Time Scope Base Code Location Dur Km From Km To Comments

05/09/2020 21:00 Put on Track ??? 0:30 Put on at ????05/09/2020 21:30 Run to test 0:1005/09/2020 21:40 Test Track 13467 Mittagong 17 Cross Over 0:25 131.730 131.81605/09/2020 22:05 Run to test 0:3005/09/2020 22:35 Test Track 13275 Berrima Junction 188 Crossover 0:25 143.243 143.29505/09/2020 23:00 Run to test 0:0505/09/2020 23:05 Test Track 13930 Moss Vale 113 Crossover 0:25 144.458 144.54205/09/2020 23:30 Test Track 13931 Moss Vale 119 Crossover 0:25 144.554 144.64005/09/2020 23:55 Run to test 0:0506/09/2020 0:00 Test Track 13932 Moss Vale 137 Crossover 0:25 145.180 145.26006/09/2020 0:25 Test Track 13933 Moss Vale 140 Crossover 0:25 145.264 145.32406/09/2020 0:50 Run to test 0:0506/09/2020 0:55 Test Track 13934 Moss Vale 158 Crossover 0:25 145.950 146.01106/09/2020 1:20 Run to test 0:0506/09/2020 1:25 Test Track 13935 Moss Vale 161 Crossover 0:25 146.195 146.278

Proposed Speno Ultra Sonic Test Programmme' September 2020

06/09/2020 1:50 Take off track ??? 0:30 Take off at ???? **Note to Kiwi - would they be better off travelling track??06/09/2020 3:15 Put on Track 0:30 Put on at ????06/09/2020 3:45 Run to test 0:0506/09/2020 3:50 Test Track 13462 Medway 51 Crossover 0:25 189.640 189.73006/09/2020 4:15 Run to test 0:2006/09/2020 4:35 Test Track 13925 Lynwood Junction 61 Crossover 0:25 196.228 196.35806/09/2020 5:00 Take Off Track 0:30 Take off at ????Lynwood Junction 61 Crossover

Date Time Scope Base Code Location Dur Km From Km To Comments

06/09/2020 20:00 Put on Track ??? 0:30 Put on at ????06/09/2020 20:30 Run to test 0:0506/09/2020 20:35 Test Track 13372 Tahmoor 310 Crossover 0:25 97.570 97.63006/09/2020 21:00 Run to test 0:2006/09/2020 21:20 Test Track 13939 Picton 114 Crossover 0:25 85.767 85.87806/09/2020 21:45 Run to test 0:0506/09/2020 21:50 Test Track 13938 Picton 112 Crossover 0:25 85.638 85.74906/09/2020 22:15 Run to test 0:1006/09/2020 22:25 Test Track 13924 Maldon 106 Crossover 0:25 81.580 81.82006/09/2020 22:50 Run to test 0:0506/09/2020 22:55 Test Track 13923 Maldon 100 Crossover 0:25 81.180 81.28906/09/2020 23:20 Take off track ??? 0:30 Take off at ???? Maldon 100 Crossover???07/09/2020 1:00 Put on Track ??? 0:30 Put on at ????07/09/2020 1:30 Shunt to test 0:20 18.909 17.08507/09/2020 1:50 Test Track 10150 Enfield West Jct to Sefton East Jct Down 0:15 17.085 20.42107/09/2020 2:05 Shunt to Pad 0:20 20.421 18.00007/09/2020 2:25 Shunt to test 0:15 18.000 21.28507/09/2020 2:40 Test Track 10151 Enfield West Jct to Sefton East Jct Up 0:30 21.285 17.08407/09/2020 3:10 Shunt to test 0:20 17.084 16.46907/09/2020 3:30 Test Track 10090 Botany Line UP 0:20 16.469 14.03107/09/2020 3:50 Test Track 11036 Cooks River Run Round Road 0:15 14.031 14.63607/09/2020 4:05 Shunt to test 0:05 14.636 14.03107/09/2020 4:10 Test Track 10090 Botany Line UP 0:10 14.031 13.61507/09/2020 4:20 Test Track 11813 Cooks River Loop 0:15 13.615 12.82207/09/2020 4:35 Shunt to test 0:10 12.822 13.61507/09/2020 4:45 Test Track 10090 Botany Line UP 0:15 13.615 12.61007/09/2020 5:00 Test Track 10089 Botany Line Down 0:40 12.610 16.47207/09/2020 5:40 Shunt to test 0:30 16.472 12.61007/09/2020 6:10 Test Track 10089 Botany Line Single 0:15 12.610 9.94107/09/2020 6:25 Take Off Track 0:30 Take off at ????

Date Time Scope Base Code Location Dur Km From Km To Comments

07/09/2020 20:00 Put on Track ??? 0:30 Put on at ????07/09/2020 20:30 Run to test 0:10

07/09/2020 20:40 Test Track 11581 Botany Departure Rd 2 0:25 6.620 9.25007/09/2020 21:05 Shunt to test 0:30 9.250 6.62007/09/2020 21:35 Test Track 11582 Botany Departure Road 1 0:25 6.620 9.29307/09/2020 22:00 Shunt to test 0:20 9.293 7.42807/09/2020 22:20 Test Track 11577 Botany Arrival Rd 2 0:25 7.428 9.94107/09/2020 22:45 Shunt to test 0:20 9.941 6.85607/09/2020 23:05 Test Track 10089 Botany Arrival Rd 1 0:25 6.856 9.94107/09/2020 23:30 Shunt to test 0:20 9.941 6.37107/09/2020 23:50 Test Track 10092 Metropolitan Goods Main Down 1:30 6.371 18.90908/09/2020 1:20 Test Track 10094 Metropolitan Goods Main Up 1:30 18.909 6.37108/09/2020 2:50 Shunt to test 0:40 6.371 13.73108/09/2020 3:30 Test Track 10246 Enfield South-Nth Via Delec Single Line (Link to No 1 Staging Rd 0:10 13.731 13.90708/09/2020 3:40 Test Track 14078 Enfield Staging Rd 1 0:20 13.907 16.82908/09/2020 4:00 Shunt to test 0:20 16.829 14.53608/09/2020 4:20 Test Track 14133 Enfield Staging Rd 2 0:15 14.536 16.44808/09/2020 4:35 Shunt to test 0:10 16.448 17.16008/09/2020 4:45 Test Track 10195 North Fork to Metro Goods Line 0:10 17.160 17.60008/09/2020 4:55 Take Off Track 0:30 Take off at ????

Night Shift 08/09 - Contingency Night (if required)

Version 1.0 Date of last revision: 13 August 2019 Page 1 of 2 This document is uncontrolled when printed. See ARTC Intranet for latest version.

Engineering (General) Procedure - Form EGP-20-01 Project Management

Form number: EGP2001T-10

Infrastructure Certification and Handover Form

This form is to be used to certify that the work on the infrastructure has been completed in accordance with the original scope and is fit for operational use.

Project Description Km’s From Km’s To Track(s) Location

: :

: :

: :

: :

I certify that the infrastructure has been constructed and is being handed over in accordance with the original scope and is fit for traffic in accordance with ARTC’s relevant

standards, practices and procedures.

Certification Details

Infrastructure Certifying Person (Name) Contact No. Certifying Qualification Signature Time/Date Remarks

Track

Electrical

Signals

Structure

Drainage

Earthworks

Environment

Operations

Version 1.0 Date of last revision: 13 August 2019 Page 2 of 2 This document is uncontrolled when printed. See ARTC Intranet for latest version.

Engineering (General) Procedure - Form EGP-20-01 Project Management

Form number: EGP2001T-10

Civil or Signalling Equipment Book Out of Use and Restored to Use: Yes / No

Infrastructure Booking Authority Form Completed: Yes / No Attached: Yes / No

Outstanding Scope / Any Minor Defects:

List any temporary works installed that may affect the reliability, safety

or operation of the system (speed restrictions, temporary boards, etc.):

Project Manager Area Manager Asset Management Representative Operational Representative

Name:

Name:

Name:

Name:

Signature:

Signature:

Signature:

Signature:

Date:

Date:

Date:

Date:

Version 1.0 Date of last revision: 13 August 2019 Page 1 of 2 This document is uncontrolled when printed. See ARTC Intranet for latest version.

Engineering (General) Procedure - Form EGP-20-01 Project Management

Form number: EGP2001T-10

Infrastructure Certification and Handover Form

This form is to be used to certify that the work on the infrastructure has been completed in accordance with the original scope and is fit for operational use.

Project Description Km’s From Km’s To Track(s) Location

: :

: :

: :

: :

I certify that the infrastructure has been constructed and is being handed over in accordance with the original scope and is fit for traffic in accordance with ARTC’s relevant

standards, practices and procedures.

Certification Details

Infrastructure Certifying Person (Name) Contact No. Certifying Qualification Signature Time/Date Remarks

Track

Electrical

Signals

Structure

Drainage

Earthworks

Environment

Operations

Version 1.0 Date of last revision: 13 August 2019 Page 2 of 2 This document is uncontrolled when printed. See ARTC Intranet for latest version.

Engineering (General) Procedure - Form EGP-20-01 Project Management

Form number: EGP2001T-10

Civil or Signalling Equipment Book Out of Use and Restored to Use: Yes / No

Infrastructure Booking Authority Form Completed: Yes / No Attached: Yes / No

Outstanding Scope / Any Minor Defects:

List any temporary works installed that may affect the reliability, safety

or operation of the system (speed restrictions, temporary boards, etc.):

Project Manager Area Manager Asset Management Representative Operational Representative

Name:

Name:

Name:

Name:

Signature:

Signature:

Signature:

Signature:

Date:

Date:

Date:

Date:

Version 1.0 Date of last revision: 13 August 2019 Page 1 of 2 This document is uncontrolled when printed. See ARTC Intranet for latest version.

Engineering (General) Procedure - Form EGP-20-01 Project Management

Form number: EGP2001T-10

Infrastructure Certification and Handover Form

This form is to be used to certify that the work on the infrastructure has been completed in accordance with the original scope and is fit for operational use.

Project Description Km’s From Km’s To Track(s) Location

: :

: :

: :

: :

I certify that the infrastructure has been constructed and is being handed over in accordance with the original scope and is fit for traffic in accordance with ARTC’s relevant

standards, practices and procedures.

Certification Details

Infrastructure Certifying Person (Name) Contact No. Certifying Qualification Signature Time/Date Remarks

Track

Electrical

Signals

Structure

Drainage

Earthworks

Environment

Operations

Version 1.0 Date of last revision: 13 August 2019 Page 2 of 2 This document is uncontrolled when printed. See ARTC Intranet for latest version.

Engineering (General) Procedure - Form EGP-20-01 Project Management

Form number: EGP2001T-10

Civil or Signalling Equipment Book Out of Use and Restored to Use: Yes / No

Infrastructure Booking Authority Form Completed: Yes / No Attached: Yes / No

Outstanding Scope / Any Minor Defects:

List any temporary works installed that may affect the reliability, safety

or operation of the system (speed restrictions, temporary boards, etc.):

Project Manager Area Manager Asset Management Representative Operational Representative

Name:

Name:

Name:

Name:

Signature:

Signature:

Signature:

Signature:

Date:

Date:

Date:

Date:

Shift Commenced Start time on site

Shift completed Finish time on site

Total shift hours Total site hours

Activity: Activity: Activity: Activity:

Line Segment: Line Segment:

Line Segment:

Line Segment:

KM from KM to KM from KM to KM from KM to KM from KM to

% of Work Complete

Defects Removed:-

Defects Identified:-

Speed restriction required post daily work:-

Date S M T W T F S Date

Project Project code

Employee Names Hours Position Company

Total USE BACK OF SHEET IF MORE LINES REQUIRED

Plant Operator Name Hours Plant (full description) Company

Additional Plant/Vehicles (not specified above)

Description No. Description No.

4x4 vehicle

Materials

Description Qty Description Qty

Ballast

DAILY SITE DIARY

PROJECT

WEATHER RECORD Temperature

Conditions

Other factors

Industrial

Lost Time

Details of Work Completed:

Geographic Site Issue: eg. In a cutting, bad access etc.

Train Running Issues:

Prepared By Signature

LTI (lost time injury) Yes No

MTI (medical treatment injury) Yes No

FAI (first aid injury) Yes No

SAFETY

DAILY SITE DIARY

WEATHER RECORD Temperature

Conditions

Other factors

Industrial

Lost Time

Details of Work Completed:

Geographic Site Issue: eg. In a cutting, bad access etc.

Train Running Issues:

Prepared By Signature

LTI (lost time injury) Yes No

MTI (medical treatment injury) Yes No

FAI (first aid injury) Yes No

SAFETY

DAILY SITE DIARY