south eastern coalfields limited

122
SOUTH EASTERN COALFIELDS LIMITED (A MINI RATNA COMPANY) BILASPUR (CHHATTISGARH) GEVRA OC PROJECT SIX MONTHLY REPORT OF MONITORING THE IMPLEMENTATION OF ENVIRONMENT SAFE GUARDS FOR THE PERIOD ENDING SEPTEMBER 2019 AND Compliance of the conditions of MOEF letter no. - J-11015 / 85 / 2010 IA II (M) Dated 28-03-2019 For capacity enhancement of coal production 45 MTY

Transcript of south eastern coalfields limited

SOUTH EASTERN COALFIELDS LIMITED

(A MINI RATNA COMPANY)

BILASPUR (CHHATTISGARH)

GEVRA OC PROJECT

SIX MONTHLY REPORT OF MONITORING THE IMPLEMENTATION OF

ENVIRONMENT SAFE GUARDS

FOR THE PERIOD ENDING SEPTEMBER 2019

AND

Compliance of the conditions of

MOEF letter no. - J-11015 / 85 / 2010 – IA – II (M) Dated 28-03-2019

For capacity enhancement of coal production

45 MTY

SOUTH EASTERN COALFIELDS LIMITED

GEVRA PROJECT

MONITORING THE IMPLEMENTATION OF ENVIRONMENT SAFE GUARDS

FOR THE PERIOD OF SIX MONTHS UP TO “September 2019”

PART-I

(GENERAL PARTICULARS)

1 Name of the Project Gevra Opencast Expansion Project of M/S. South

Eastern Coalfields Ltd.

2 No. & Date of MOEF clearance letter J-11015 / 85 / 2010 – IA – II (M)

Dated 28-03-2019

3

Area involved in the Project & break

up purpose wise if any

4184.486Ha. (As per EIA For Gevra OCP EXP.)

(a) Quarry area : 2037.25 Ha

(b) External OB dump : 480 Ha

(c) Infrastructures : 1093.112 Ha

(d) Road diversion : 6.00Ha

(e) Rehabilitation site : 134.28 Ha

(f) Safety Zone : 418.174 Ha

4 Location

District

State

12 KM from Gevra road Rly. Station.

Korba

Chhattisgarh

PART-II

(PROJECT STATUS)

5. Present Status including: Work progress.

YEAR COAL PRODUCTION

(IN MILLION TONS)

OB EXTRACTION

(IN MILLION CUM)

2010-11 35.00 30.590

2011-12 35.00 22.843

2012-13 35.00 23.264

2013-14 38.70 35.126

2014-15 41.00 45.440

2015-16 41.00 44.010

2016-17 41.00 47.068

2017-18 41.433 58.403

2018-19 42.251 58.580

2019-20

Upto Sept 19

17.530 26.409

6 Total manpower civil amenities including

free fuel distribution

for labor force during construction

Period

2782

LPG is distributed @ one cylinder per

month Period.

7 Project cost original Total Project Cost is Rs. 11816.40 Crores

including incremental capital (for 25 to

35 MTY) of Rs. 1008.12 Crores (Sept

’2009) & 9140.726 Crores (49 MTY PR : Oct 2017 & 70 MTY PR: March 2016 )

8 Environmental safe guard expenditure, Till

March’2019

(During year 2018-19)

Rs 59.87 Crores (approx.)

9 Monitoring cell established

Yes/No if any details

Monitoring cell exists with the HODs of

Environment, Mining, Civil, E & M &

Excavation departments of Gevra Area &

Gevra project. Environment pollution

control measures are executed by

Mining, Civil, E & M and Excavation

departments. At various locations/

installations/ Machinery are under their

control.

10 How regularly/quarterly/six Monthly

progress reports are Submitted to the

Ministry

Details of last report submitted

Reports are being submitted Six monthly

to the MoEF&CC.

The Last report was submitted for

the period Ending, ‘March 2019

Vide Letter No:

SECL/GM/GA/ENVT/2019/50

Dated 09.05.2019.

11 Firefighting system emergency Plan details Central firefighting station is being

Maintained at Kusmunda about 10 KMs.

Away. Approved Mine Emergency

Response Plan exists. Fire extinguishers

and Fire tenders are also available with

the project.

PART-III

(REHABILITATION / RESETTLEMENT PROGRAMME)

1. No. of families/persons Displaced :

Sl.NO VILLAGES

INVOLVED PAFs At Site

Cash

Grant

Not

Eligible Balance

Old

1 Bareli 131 131 0 - 0

3 Dhurena 40 40 0 - 0

4 Junadih 149 149 0 - 0

5 Kusmunda 232 232 0 - 0

6 Binjhra 150 150 0 - 0

7 Ghatmunda 75 75 0 - 0

New

1 Pondi 470 0 405 65 0

2 Amgaon 491 62 231 192 6

3 Bahanpat 358 0 168 188 2

4 Bhatora 380 0 35 31 314

5 Ralia 150 0 0 0 150

6 Bhilai Bazar 400 0 0 0 400

7 Naraibodh 350 0 0 0 350

Total 3376 839 839 476 1222

2. Réhabilitation Site Identified.

Sl

No.

Rehabilitation

site

Number

of

Families

shifted

Amenities

1 Nehru Nagar 193

School, Dispensary, hand pumps, Panchayat Bawan,

Park, Wells, Training center, bus stop Streets light,

roads, ponds, Drainage, culverts, weekly market,

Community centre, etc

2 Vijay Nagar 571

School, Panchayat Bhawan, dispensary, well,pond,

Hand pumps, Internal roads approach roads.

Community centre, Streets light, Drainage, culverts,

weekly market, Play Ground, bus stop, etc

3 Ganga Nagar 75

Well, Pond, Hand pumps, School, Panchayat Bhawan,

Approach roads, Dispensary Community centre,

Streets light, Drainage, culverts, bus stop, etc

839

4 Laxman Nagar 191 School, Panchayat Bhawan, dispensary, well, pond,

approach road etc

14. No. of displaced Households /families employed : 2720 persons. Compensation

paid skilled/unskilled both skilled & unskilled

15. Quantity of solid waste/OB: produced year wise

16 Location & total Area

to be Reclaimed /

Restored

External Dump : 480 Ha .

Internal Dump : 1378 Ha. (During life time of the Mine)

Till date- Reclaimed External Dump : 367.200 Ha

Reclaimed Internal Dump : 122.600 Ha

(already done)

17 Plan for reclaiming

the excavated

The area decoaled is being filled up with OB. Quarry sites

and borrow pits Backfilled area is around 829.411 Ha.

Through filling leveling (i.e. B/F dump area already created)

YEAR OB EXTRACTION

(IN MILLION CUM)

2010-11 30.590

2011-12 22.843

2012-13 23.264

2013-14 35.126

2014-15 45.440

2015-16 44.010

2016-17 47.068

2017-18 58.403

2018-19 58.580

2019-20

(upto Sept 19)

26.409

The year wise financial allocation (infrastructural facilities) for Rehabilitation / Resettlement

YEAR FINANCIAL ALLOCATION

IN LAKHS

2010-11 10.11

2011-12 42.96

2012-13 20.00

2013-14 2357.00

2014-15 3059.00

2015-16 2596.00

2016-17 1876.00

2017-18 600.00

2018-19 550.00

2019-20 300.00

The phase programme for expenditure for Rehabilitation / Resettlement & Reclamation /

Restoration

Already incurred /future (Infrastructural facilities)

YEAR REHABILITATION &

RESETTLEMENT (LAKHS)

RECLAMATION &

RESTORATION (LAKHS)

2010-11 10.11 602.89

2011-12 42.96 632.43

2012-13 515.41 749.51

2013-14 1216.33 853.93

2014-15 945.00 676.70

2015-16 722.10 1173.97

2016-17 692.78 1217.63

2017-18 429.27 1187.97

2018-19 278.25 1501.82

20 Facilities provided to

collect Industrial

waste water & sewage

(a) Sewage Treatment Plant- for Sewage treatment -DETP of 3

MLD capacity, Covering all residential colonies of the

Project.

(b) Mine Sumps, Check dams & Sedimentation tank for

treatment of mine discharge

(c) Oil & Grease Trap for treatment of Work shop effluent.

(d) Catch drains with check dams – for channeling and settling

of OB dump & CHP Run off.

21 Quantity/ day

discharged industrial/

Colony waste water,

point of discharge &

Location map

(a) 2900 to 3000 KL/D as domestic effluent which is treated at

DETP

(b) Rain water collected in mine sumps is pumped out to

facilitate safe mining operations.

(c) During monsoon months average about

99000KLD. About 45000KLD-in other season, which is

treated at mine sumps, Check dams and sedimentation pond,

before discharge

22 Monitoring of treated

effluent, frequency,

No. of sampling

points.

Fortnightly Monitoring.

Sampling points-8

23 Air quality analysis &

its monitoring

Frequency, no. of

monitoring station.

Monitoring Twice in a week, 24 hourly.

No. of Sampling stations-8.

24 Noise Pollution

monitoring stations

Done fortnightly. Sampling Stations- 8.

25. Preventive measures for Air, Water & Noise Pollution

(A) Air pollution control facilities and control measures adopted at Gevra Project

1. Sufficient number of Mobile Water Sprinklers of capacity 70 KL (13 nos.), 28 KL (1 nos.) and

9 KL (22 nos.) are used for dust Suppression in mine haul roads and in coal tipper roads on

regular basis.

2. At all along conveyor, Transfer Points, CHP, Silo’s and at 30,000 T Ground Bunker water sprinkling arrangement is working effectively to suppress dust at source. At few crusher/

Feeder breakers and at 5000 Te capacity Ground Bunker mist spray water sprinklers are

operating for dust control.

3. Trucks are optimally loaded to prevent spillage on haul roads. Coal loaded trucks are covered

before leaving the mine premises.

4. Whenever the coal dust / slurry accumulate on Haul roads and other roads of Mine premises,

the same is cleaned by the use of Graders & Loaders.

5. Dust extractors are working effectively in Drills to reduce dust emission.

6. Extensive Plantation done on overburden dumps, which act as dust & noise barrier between

mine area and residential area.

7. Thick green belts developed around residential areas. Also plantation done along colony

roads and around other mine infrastructures.

8. Employees are provided with LP Gas connections, restricting burning of coal for domestic use.

9. All approach roads to mine and all other roads which are in regular use are black topped.

Internal roads & other permanent haul roads in side mine are WBM roads.

10. Production from Surface Miners reduced the requirement of drilling & blasting and further

crushing at In Pit & Surface crushers.

(B) Water Pollution control facilities and measures adopted at Gevra Project

a) Oil and Grease trap is in operation for treating effluent water from HEMM Washing. After

treatment, water is reused for HEMM washing .This Oil & Grease Trap is a zero discharge

plant.

b) Settling ponds are provided for treating the mine water discharge as well as OB Dump run-

off. Catch drains (at a length of 11.5 KM) with Check dams are provided for Channeling and

Settling of OB dump and CHP runoff.

c) Domestic Effluent Treatment Plant (DETP) is constructed for treating Domestic Effluent of the

residential colonies, properly constructed storm water drains have been maintained in the

colony.

(C) Noise Pollution Control facilities and measures at Gevra Project

1. Generally the blasting operations are carried out in between 12.00 noon to 4.00 PM.

2. Proper maintenance of HEMM to reduce the avoidable vibrations and noise.

3. Employees who are exposed to higher level of noise are provided with Ear Plugs.

4. Extensive Plantation done on overburden dumps, which act as noise barrier between

mine area and residential area.

5. Thick green belts developed around residential areas. Also plantation done along

Colony roads and around other mine infrastructures. These green belts also act as noise

barriers.

6. At crushers/feeder breakers synthetic liners are fitted in few hoppers to reduce noise

Generation.

7. HEMMs are provided with noise proof cabins for operators.

8. Shock tube initiation system of delay blasting is adopted for Coal & OB Blasting to

reduce blast related noise & vibrations.

9. Introduction of Surface Miners reduced the requirement of drilling & blasting and

further crushing at In Pit & Surface crushers.

(D) The year wise financial allocation (infrastructural facilities) for Rehabilitation / Resettlement

YEAR FINANCIAL ALLOCATION IN LAKHS

2010-11 10.11

2011-12 42.96

2012-13 20.00

2013-14 2357.00

2014-15 3059.00

2015-16 2596.00

2016-17 1876.00

2017-18 600.00

2018-19 550.00

2019-20 300.00

(E) The phase programme for expenditure for Rehabilitation / Resettlement & Reclamation /

Restoration

Already incurred /future (Infrastructural facilities)

YEAR REHABILITATION &

RESETTLEMENT (LAKHS)

RECLAMATION &

RESTORATION (LAKHS)

2010-11 10.11 602.89

2011-12 42.96 632.43

2012-13 515.41 749.51

2013-14 1216.33 853.93

2014-15 945.00 676.70

2015-16 722.10 1173.97

2016-17 692.78 1217.63

2017-18 429.27 1187.97

2018-19 278.25 1501.82

26. Financial allocation capital/ recurring : Expenditure incurred in Environment related

works during the Year 2018-19 is Rs 59.87

Crores (approx.)

Part-V

(GREEN BELT AND AFFORESTATION)

27. No. of tree planted Species:-

Year Total no. of plants Species Density per Ha.

1986 2,36,000

Neem, Karenj, Amla,

Siras, Sissoo, Bel,

Bamboo, GangaImli,

Bahera, Ashok,

Golmohar, Satwan,

CassiaGemec, Teak,

Jamun, Peltaforum,

CassiaGulco, Bogan

vallia, Khamar,

Sitaphal, Amrood,

Kathal, Imli, Mango,

Sisham jatropa etc.

(i) Density of

plantations on

plain areas is

around 2500

nos. per

Hectare.

(ii) Density of

plantations on

dump top is

around 2500

nos. per

Hectare.

(iii) Density of

plantations on

dump slopes

is around

5000 nos. per

Hectare.

1987 2,91,750

1988 4,19,500

1989 4,54,000

1990 3,72,883

1991 3,60,000

1992 64,900

1993 1,14,200

1994 0

1995 77,000

1996 1,32,000

1997 1,73,000

1998 1,26,000

1999 76,950

2000 1,30,000

2001 66,000

2002 40,000

2003 1,31,000

2004 1,06,000

2005 1,15,500

2005 (addl.)

planted in 2006

41,500

2006 1,20,000

2007 50000

2008 25000

2009 62500

2010 39000

2011 27500

2012 30000

2013 40000

2014 20000

2015 80000

2016 50000

2017 100000

2018 63500

2019 62750

TOTAL 4301433

Grass beds =256125 nos. on dump slopes to control soil erosion and for Stabilization.

(CPT) Cattle Proof Trench = 25.60 KM length for the protection of trees.

28) Financial /future allocation: As per requirement,

Rs 106.34 Lakh (approx.) is required for the Year 2019-20.

Plantation target achieved for the year 2019-20. 62750 nos.

saplings planted over an area of 25.10 Ha. plain area.

29) Present condition of plantation: - good & healthy

(i) No change in mining technology and scope of working should be made without prior

approval of the Ministry of Environment and Forests.

Status of Compliance: Agreed. There has been no change in mining technology.

(ii) No change in calendar plan including excavation, quantum of mineral coal and waste should

be made.

Status of Compliance: Agreed

(iii) Four ambient air quality monitoring stations shall be established in the core zone as well as in

the buffer zone for RPM, SPM, SO2, NOx, and heavy metals such as Hg, Pb, Cr, As, etc

Location of the stations shall be decided based on the meteorological data, topographical

features and environmentally and ecologically

Status of Compliance: agreed

Point wise Compliance of the conditions of MOEF letter

No. - J-11015 / 85 / 2010 – IA – II (M) Dated 28-03-2019 for capacity 45 MTY Coal production of

Gevra Project-Gevra Area

NO. CONDITION COMPLIANCE

i The environmental clearance for the proposed increase in capacity shall be valid up to 31st March, 2019. The continuance of the project thereafter at the increased capacity shall be based on the evaluation of the proposed control measures and its impact on the ambient air quality by the EAC in later half of the FY 2018-19.

MoEF&CC accorded validity extension of 45

MTY EC up to 31st March 2020 vide letter

No: J-11015 / 85 / 2010 – IA – II (M) Dated

28-03-2019.

In addition to the existing pollution control

measures additional measures such as

Procurement of Truck Mounted Mist blower,

Mechanized Sweeping machine, Wind

breaker Arrangement system, Vertical

greenery arrangement, green belt

development etc are being implemented.

Seasonal Ambient Air quality assessment

study at baseline stations is being carried out

by the CMPDIL (NABL accredited agency).

The assessment report during Post Monsoon

period (Dec 2018 to March 19) and April

2019 to June 2019 is enclosed as Annex i.

ii To control the of dust generation at source, the crusher and in-pit belt conveyors shall be provided with mist type sprinklers.

Effective dust suppression system including mist

spray jet sprinklers have been provided in all

crusher feeder breaker installations.

Mist spray dust suppression arrangement is also

in operation at Ground bunker of all conveyor

system and in Feeder Breakers.

ANNEX 1

iii Mitigative measures shall be undertaken to control dust and other fugitive all along the roads by providing sufficient numbers of water sprinklers. Adequate corrective measures shall be undertaken to control dust emissions as presented’ before the Committee, which would include mechanized sweeping, water sprinkling/mist spraying on haul roads and loading sites, long range misting/fogging arrangement, wind barrier wall and vertical greenery system, green belt, dust suppression

The system is supported by 13 nos. 70KL & one

28KL capacity departmental mobile water

sprinklers & 22 nos. 9 KL contractual Mobile

sprinklers on haul roads and transport roads.

ANNEX 2

Presently at Gevra >90% of the Coal have been

produced by Surface Miner. Surface miners has

eliminated conventional drilling & blasting in

arrangement at railway siding, etc.

coal and it has inbuilt jet spraying system, which

drastically reduce the generation & propagation

of dust at source. ANNEX 3

Mobile mist blower/fog forming long range

water sprinkler system with horizontal throw

of 40mtrs is in operation from April 2019.

Procured Mechanized Sweeping machine

and will be in operation soon after

commissioning.

The maintenance of drains on haul roads is

done regularly. RCC drains have been

provided near CHP and Silo (200m) and

along the roads of PQ series (1.16KM) Inpit

belt conveyor. The drains (RCC Drains 1.36

KM & Katcha drains) provided at various

parts of the mine are regularly desilted and

the records of the same are being

maintained.

ANNEX 4

iv Efforts shall be made to explore the possibility of providing wind shield/breaker arrangement with creepers and climbers.

To explore the possibility of providing wind

shield/breaker arrangement with creepers and

climbers an expert team from CMPDI Ranchi visited

Gevra OC from 04.07.2018 to 06.07.2018. CMPDI

Ranchi submitted Final Report for VGS/ WBS Dt:

14.08.2018. ANNEX 5

Wind Breaker System (WBS): Installation of WBS

commenced from April 2019 after obtaining all

necessary approvals at competent level & laid down

procedures. The total length of the barrier is approx

1550 m. At present the footing work is in progressive

stage along the Railway Siding 3 and 4 over a length

of 750 m (As on date 500 m completed). Approval

from competent authority is awaiting for

Procurement of GI sheets. Expected to be completed

by Nov/Dec 2019.

Vertical Greenery System (VGS): The site near

Laxman Nagar is identified for VGS. The Offer/ Rates

has been received from CGRVVN for Plantation

Work (19.05 Lakhs including 4 years maintenance)

and accordingly administrative approval obtained

from Competent Authority. Work order will be

issued after the commencement of work for

installation of plant guiding structure. For

Installation of plant guiding structure for VGS Note

sheet vide No:158 Dtd:25.07.2019 forwarded to

Civil Dept. Gevra Area.

v Thick green belt of 50 m width at the final boundary in the down wind direction of the project site shall be developed to mitigate/check the dust pollution.

Extensive plantation has been done in the OB

dumps, Non dump, around infrastructures &

as avenue plantation. More than 43.01 lakhs

saplings have been planted since 1986 in

Gevra OC including downwind direction.

Year wise details given in Annex 6.

Work of Plantation in Safety zone in

downwind direction is under progress. About

28000 saplings have been planted covering

length of 14 kms.

In addition to the above, work of Vertical

Greenery System (VGS) will be started in next

monsoon season in downwind direction.

vi Persons of nearby villages shall be given

training for their livelihood and skill

development.

219 Project affected person were given

National Council On Vocational Training

Electrician Mines Training under Skill

Development at CETI, Gevra, since 1999.

NCVT Report is enclosed as Annex 7.

As a pilot project, SECL authority has

approved execution of skill development

training programme to unemployed youths

through CIPET (Central Institute of Plastic

Engineering and Technology), Raipur, under

CSR activities of SECL HQ. Annex 7 (i)

vii To ensure health and welfare of nearby villages, regular medical camps shall be organized at least once in six months.

Medical camps are organized regularly For

compliance of provisions of Mines Act’1952 at Gevra Project 20% employees are going for

periodic medical examination (PME) every

year so covering all employees in 05 year

period.

In nearby villages, medical camps are

organized by NCH Gevra Area regularly

under CSR. In the year 2019-20 (upto Sep

2019) 1457 beneficiaries were reported.

ANNEX 8

viii The predominant Sal species in the forest area shall be protected, and in case of coal mining operations inevitable therein, compensatory forestation of these species shall be carried out in consultation with State Forest Department.

Agreed & is undertaken in consultation with

CGRVVN / State Forest Department. During FY

2018-19, 3000 nos. and 2019-20 1000 nos. Sal

saplings have been planted. ANNEX viii

ix In view of the mining potential of the area and the pollution concerns capacity of the eco-system shall be studied through some expert agencies to assess optimal mining operations with minimal impact on ecosystem services.

Eco system Carrying Capacity: Work order

issued to IIT BHU on 09.02.2019. The study

commenced on 20th May 2019 and is in

progress ANNEX 9

x A sustainable mining practice shall be developed in the mine, catering to of ecological, societal and economical dimensions.

Agreed.

Introduction of Surface miners has

eliminated conventional drilling & blasting in

coal extraction. Surface miner has inbuilt jet

spray sprinkler system. 90% of coal

production is done through Surface Miners.

Construction of New Railway Siding for

Rapid loading system at Junadih railway

siding

Construction of additional 2 nos. of Silo

(4000te capacity).

Construction of new Inpit Conveyor System

(PQ and JK series)

Trucks are optimally loaded and vehicles

used for transportation of coal outside the

mine area are being covered with Tarpaulins.

CAAQMS has been Installed in the Gevra GM

office for continuous monitoring and is in

operation since January 2014.

4.1 a MINING

i Mining shall be carried out under strict

adherence to provisions of the Mines Act

1952 and subordinate legislations made

there-under as applicable.

Agreed /Will be complied.

ii No change in mining method i.e. OC to UG,

calendar programmed and scope of work

shall be made without obtaining prior

approval of the Ministry of Environment,

Forest and Climate Change (MoEF&CC).

Agreed.

iii Mining shall be carried out as per the approved mining plan(including Mine Closure Plan) abiding by mining laws related to coal mining and the relevant circulars issued by Directorate General Mines Safety (DGMS).

Agreed /Will be complied.

iv No mining shall be carried out in forest land without obtaining Forestry Clearance as per Forest (Conservation) Act, 1980 and also adhering to The Scheduled Tribes and Other Traditional Forest Dwellers (Recognition of Forest Rights) Act, 2006 read with provisions of Indian Forest Act, 1927.

Agreed.

4.1 b LAND RECLAMATION & WATER CONSERVATION

i Digital Survey of entire lease hold area/core zone using Satellite Remote Sensing survey shall be carried out at least once in three years for monitoring land use pattern and report in 1:50.000 scale shall be submitted to Ministry of Environment, Forest and climate Change/Regional Office (RO).

Land use & land reclamation status is being

monitored by CMPDIL every year through

satellite imagery & the report is regularly

submitted to Regional office MOEF&CC, Bhopal /

Nagpur. ANNEX 10

Copy of the same is also available in the

Company’s website i.e www.secl.gov.in. ii The surface drainage plan including surface

water conservation plan for the area of influence affected by the said mining operations, considering the presence of river/rivulet/pond/lake etc, shall be prepared and implemented by the project proponent. The surface drainage plan and/or any diversion of natural water courses shall be

Preparation of Comprehensive Catchment area

treatment plan within 5 KM from Mine Lease

Boundary is awarded to Chhattisgarh Council of

Science & Technology, Govt. of CG, Raipur vide no.

259 Dt: 23.03.2018. Work order accepted by

as per the approved Mining Plan/EIA/EMP report and with due approval of the concerned State/Got Authority. The construction of embankment to prevent any danger against inrush of surface water into the mine should be as per the approved Mining Plan and as per the permission of DGMS.

CCOST& 1st installment payment (Rs. 600430/-)

made.

Technical Team Experts Conducted field study in

Gevra Area on 24.12.2018 to 27.12.2018. Interim

Report of field study submitted by CCOST on

13.01.2019. Final report will be submitted after

physical verification of 70 MTY boundary.

ANNEX 11

iii The final mine void depth should preferably be as per the approved Mine Closure Plan, and in case it exceeds 40 m, adequate engineering interventions shall be provided for sustenance of aquatic life therein. The remaining area shall be backfilled and covered with thick and alive top soil. Post-mining land be rendered usable for agricultural/forestry purposes and shall be handed over to the respective state government as specified in the guidelines for Preparation of Mine Closure Plan issued by the Ministry of Coal dated 27th August, 2009 and subsequent amendments.

Agreed & implemented as per Final Mine Closure

Report.

Post Mining Land use shall be dealt as per Govt.

Policy

iv The entire excavated area, backfllling,

external OB dumping (including top soil)

and afforestation plan shall be in conformity

with the “during mining” / post mining” land-use pattern, which is an integral part

of the approved Mining Plan and the

EIA/EMP submitted to this Ministry.

Progressive compliance status vis-a-vis the

post mining land use pattern shall be

submitted to the Ministry of Environment,

Forest and Climate Change/Regional Office

on six monthly

Agreed & the report is regularly submitted to

MoEFCC.

The Last report was submitted for the period Ending,

‘March 2019 Vide Letter No:

SECL/GM/GA/ENVT/2019/50 Dated 09.05.2019.

ANNEX 12

v The top soil shall temporarily be stored at earmarked site(s) only and shall not be kept unutilized for long. The top soil shall be used for land reclamation and plantation purposes. Active OB dumps shall be stabilized with native grass species to prevent erosion and surface run off. The other overburden dumps shall be vegetated

As mining progresses the top 1.5 m (approx.)

depth soil is excavated and temporarily

stored at earmarked site (Internal Dump no.

8) and subsequently spread on the

technically reclaimed dump before biological

reclamation.

with native flora species. The excavated area shall be backfilled and afforested in line with the approved Mine Closure Plan. Monitoring and management of rehabilitated areas shall continue until the vegetation becomes self-sustaining. Compliance status shall be submitted to the Ministry of Environment, Forest and Climate Change/ Regional Office on six monthly basis.

Species include Sal, Neem, Karenj, Amla,

Siras, Sissoo, Bel, Bamboo, GangaImli,

Bahera, Ashok, Golmohar, Satwan,

CassiaGemec, Teak, Jamun, Peltaforum,

CassiaGulco, Bogan vallia, Khamar,

Sitaphal, Amrood, Kathal, Imli, Mango,

Sisham jatropa etc

4.1 c EMISSIONS, EFFLUENTS & WASTE DISPOSAL

i Transportation of coal, to the extent permitted by road, shall be carried out by covered trucks / conveyors. Effective control measures such as regular water/mist sprinkling/rain gun etc shall be carried out in critical areas prone to air pollution (with higher values of PM10/PM2.5) such as haul road, loading/unloading and transfer points. Fugitive dust emissions from all sources shall be controlled regularly. It shall be ensured that the Ambient Air Quality parameters conform to the norms prescribed by the Central/State Pollution Control Board.

Coal is transported by road, through

optimally loaded covered trucks. ANNEX 13

The system is supported by 13 nos.70 KL & 1

no. 28 KL capacity Departmental mobile

water sprinklers & 18 nos. 9 KL contractual

Mobile sprinklers on haul roads and

transport roads ANNEX (2)

Effective dust suppression system including

mist spray jet sprinklers have been provided

in place of conventional perforated pipe

sprinklers in all crusher feeder breaker

installations. ANNEX (1)

Mist spray dust suppression arrangement is

also in operation at Ground bunker of all

conveyor system and in Feeder Breakers.

ANNEX (1)

Drills are wet operated & fitted with Dust

extractors. ANNEX 14

To reduce the dust generation at source

surface miners have been introduced which

eliminated conventional drilling & blasting in

coal. Surface miner has inbuilt jet spray

sprinkler system. ANNEX (3)

ii Greenbelt consisting of 3-tier plantation of width not less than 7.5 m shall be developed all along the. Mine lease area in a phased manner. The green belt comprising a mix of native species shall be developed all along the major approach/ coal transportation roads.

Every year extensive plantation is being done both

on plain and dump areas. ANNEX 6

Species include: Sal, Neem, Karenj, Amla, Siras,

Sissoo, Bel, Bamboo, GangaImli, Bahera, Ashok,

Golmohar, Satwan, CassiaGemec, Teak, Jamun,

Peltaforum,CassiaGulco, Bogan vallia, Khamar,

Sitaphal, Amrood, Kathal, Imli,Mango, Sisham

jatropa etc.

iii The transportation of coal shall be carried out as per the provisions and route proposed in the approved Mining Plan. Transportation of the coal through the existing road passing through any village shall be avoided. In case, it is proposed to construct a ‘bypass’ road, it should be so constructed so that the impact of sound, dust and accidents could be appropriately mitigated.

Agreed/ Will be done.

iv Vehicular emissions shall be kept under

control and regularly monitored. All the

vehicles engaged in mining and allied

activities shall operate only after obtaining

‘PUC’ certificate from the authorized pollution testing centres.

Pollution under control for all heavy and

light commercial vehicles is secured

Vehicle emissions are periodically (Six

Monthly) monitored and a certificate to this

effect is being issued to each vehicle by the

authorized agency of Transport Department

Government of Chhattisgarh. ANNEX 15

Trucks are optimally loaded and vehicle used

for transportation of coal outside the mine

area are being covered with Tarpaulins.

ANNEX (13)

v Coal stock pile/crusher/feeder and breaker material transfer points shall invariably be provided with dust suppression system. Belt-conveyors shall be fully covered to avoid air borne dust. Side cladding all along the conveyor gantry should be made to avoid air borne dust. Drills shall be wet operated or fitted with dust extractors.

Effective dust suppression system including

mist spray jet sprinklers have been provided

in place of conventional perforated pipe

sprinklers in all crusher feeder breaker

installations. ANNEX (1)

Mist spray dust suppression arrangement is

also in operation at Ground bunker of all

conveyor system and in Feeder Breakers.

ANNEX (1)

Drills are wet operated & fitted with Dust

extractors. ANNEX (14)

vi Coal handling plant shall be operated with effective control measures viz, bag filters/water or mist sprinkling system etc to check fugitive emissions from crushing operations, conveyor system, transfer points, etc.

Effective dust suppression system including

mist spray jet sprinklers have been provided

in place of conventional perforated pipe

sprinklers in all crusher feeder breaker

installations. ANNEX (1)

Mist spray dust suppression arrangement is

also in operation at Ground bunker of all

conveyor system and in Feeder Breakers.

ANNEX (1)

vii Ground water, excluding mine water, shall not be used for mining operations. Rainwater harvesting shall be implemented for conservation and augmentation of ground water resources.

NOC for 11487 m3/day withdrawal of ground

water issued vide NOC no.

CGWA/NOC/MIN/ORIG/2018/4474 Dt: 22.01.2019,

from Central ground water Authority, Ministry of

water Resources Govt. of India.

ANNEX 16

For mining operations, no additional tube-well/

ground water abstraction structures, which deplete

ground water, have been constructed.

Mine water, obtained during extraction of coal &

Rainwater accumulated is utilized for industrial

purposes

Rainwater harvesting structures have been

provided at Project Office & NCH

Four sumps of cumulative capacities of 9216000

cum exist in the mine for ground water

recharge.

In the other parts of the mine lease area, water

from precipitation is collected into the ponds

located at various places.

ANNEX 17

viii Catch/garland drains and siltation ponds of appropriate size shall be constructed around the mine working, coal heaps & OB dumps to prevent run off of water and flow of sediments directly into the river and water bodies. Further, dump material shall be properly consolidated! Compacted and accumulation of water over dumps shall be avoided by providing adequate channels for flow of silt into the drains. The drains / Ponds so constructed shall be regularly de-silted particularly before onset of monsoon and maintained properly. Sump capacity should provide adequate retention period to allow proper settling of silt material. The water so collected in the sump shall be utilized for dust suppression measures and green belt development. Dimension of the retaining wall constructed, if any, at the toe

Garland Drains are constructed all along the

Mine Boundary. ANNEX 18

The sump and drains have been designed to

cater to 280 mm of rain in a day. ANNEX

17

One departmental back-hoe (1.2cum

capacity) is deployed for drain construction

& regular cleaning. The flow of drains

ultimately goes to two no’s of Sedimentation

tanks of size 80m x 34m x 2m and 130m x

60m x 3.35m. ANNEX 17

Gabion wall (3m X 3m for 0.5 Km) has been

constructed along the toe wall of approach

road / ramp (newly constructed inpit

of the OB dumps within the mine to check run-off and siltation should be based on the rainfall data. The plantation of native species to be made between toe of the dump and adjacent field/habitation/water bodies.

conveyor of Gevra Project). ANNEX 19.

2018-19 Plantation dump area has been

provided with Contour trench 300 plants per

trench, check dam 20 per cubic meter and

bund with stone boulders 20 per cubic meter

(ANNEX 4.1 c viii).

ix Industrial waste water generated from CHP, workshop and other waste water, shall be properly collected and treated so as to conform to the standards prescribed under the Environment (Protection) Act, 1986 and the Rules made there under, and as amended from time to time. Oil and grease trap shall be installed and maintained fully functional with effluents discharge adhering to the norms. Sewage treatment plant of adequate capacity shall be installed for treatment of domestic waste.

Domestic effluent treatment plant (DETP) of

3 MLD capacity has been constructed and

successfully operated for treatment of

domestic sewage of residential colonies of the

project. ANNEX 20

For treatment of workshop effluent ETP / Oil

& Grease trap of 210 KL capacity have been

provided. ANNEX 21

x Adequate groundwater recharge measures shall be taken up for augmentation of ground water. The project authorities shall meet water requirement of nearby village(s) in case the village wells go dry due to dewatering of mine.

Rainwater harvesting structures have been

provided at Project Office & NCH ANNEX (17)

Four sumps of cumulative capacities of 9216000

cum exist in the mine for ground water

recharge. ANNEX (17)

In the other parts of the mine lease area, water

from precipitation is collected into the ponds

located at various places. The extensive

plantation inside the mine lease area also helps

in effective recharge of ground water table.

The backfilled area is also systematically leveled

and biologically reclaimed, this helps in

reducing surface run off and improve

infiltration capacity of soil.

An action plan has already been implemented by

SECL, Gevra Project to provide water for different

uses in the nearby villages of the mine under

CSR/CD.

4.1 d ILLUMINATION, NOISE & VIBRATION

i Adequate illumination shall be ensured in all mine locations (as per DGMS standards) and monitored weekly. The report on the same shall be submitted to this ministry &its RO on six-monthly basis.

Agreed. ANNEX 22

ii Adequate measures shall be taken for control of noise levels below 85 dB(A) in the work ‘s environment. Workers engaged in blasting and drilling operations, operation of HEMM, etc shall be provided with personal protective equipment (PPE) like ear plugs/muffs in conformity with the prescribed norms and guidelines in this regard. Adequate awareness programme for users to be conducted. Progress in usage of such accessories to be monitored.

Workers engaged in blasting and drilling operations,

operation of HEMM etc has been provided with ear

plug and dust mask.

YEAR

EAR MUFF /

EAR PLUG

(pair)

DUST

MASK

2015 157 253

2016 51 577

2017 17 238

2018-19 29 308

2019-20 50 213

ANNEX 23

iii Controlled blasting techniques shall be practiced in order to mitigate ground vibrations and fly rocks as per the guidelines prescribed by the DGMS.

Coal cutting by Surface miners eliminated

conventional drilling & blasting in coal.

In Overburden Controlled blasting, i.e. shock tube

initiation system has been adopted in delay blasting,

which is an advanced method of blasting operation

and more environmental friendly. This practice

controls, blast related vibrations and fly rock

considerably.

Blast monitoring is being done on a regular basis.

The values of blast measured in ppv for the period

April 2019 –September 2019 lies between 1.032

mm/sec to 3.969 mm/sec. ANNEX 24

iv The noise level survey shall be carried out as per the prescribed guidelines to assess noise exposure of the workmen at vulnerable points in the mine premises, and report in this regard shall be submitted to the Ministry/RO on six-monthly basis.

Monitoring of Noise level is regularly Done on

fortnightly basis & report is Submitted to MoEF&CC

ANNEX 25

4.1 e OCCUPATIONAL HEALTH & SAFETY

i The project proponent shall undertake occupational health survey for initial and periodical medical examination of the workers engaged in the project and maintain records accordingly as per the provisions of the Mines Rules, 1955 and DGMS circulars. Besides regular periodic health check-up, 20% of the workers identified from workforce engaged in active mining operations shall be subjected to health check-up for occupational diseases and hearing impairment, if any.

In compliance to provisions of Mines Act’1952 and DGMS circular, regular periodic health checkup of

workers initially in 5 years (both contractual and

departmental) and the workers above 45 years of

age are subjected to health checkup in every 3 years.

20% of employees engaged in active mining are also

included in the above provision. ANNEX (8)

ii Personnel (including outsourcing employees) working in dusty areas shall wear protective respiratory devices and shall also be provided with adequate training and information on safety and health aspects.

Workers engaged in blasting and drilling operations,

operation of HEMM etc has been provided with ear

plug and dust mask.

YEAR EAR MUFF / EAR

PLUG

DUST

MASK

2015 157 253

2016 51 577

2017 17 238

2018-19 29 308

2019-20 50 213

ANNEX (23)

iii Skill training as per safety norms specified

by DGMS shall be provided to all workmen

including the outsourcing employees to

ensure high safety standards in mines.

Regular skill training program to all workmen has

been carried out. ANNEX 26

4.1 f ECOSYSTEM & BIODIVERSITY CONSERVATION

i The project proponent shall take all precautionary measures during mining operation for conservation and protection of endangered flora/fauna, if any, spotted/reported in the study area. The Action plan in this regard, if any, shall be prepared and implemented in consultation with the State Forest and Wildlife Department.

Necessary action has been taken.

Work for preparation of Wild life conservation plan

has been awarded to State Forest Research &

Training Institute (SFRTI), Raipur.

Work Order has been given to SFRTI, vide no. 20 DT:

11.05.2018. Full & final payment for an amount of

Rs. 26, 02,600 have been made on 2nd June 2018 to

SFRTI.

SFRTI Team members visited Gevra for the field

study from 24.11.18 to 01.12.2018. Interim report

of the field study submitted dt: 13.03.2019. . Final

report was submitted by SFRTI on 31.07.2019.

Annex 27

4.1 g PUBLIC HEARING, R&R & CSR

i Implementation of the action plan on the issues raised during the public hearing shall be ensured. The project proponent shall undertake all the tasks/measures as per the action plan submitted with budgetary provisions during the public hearing. Land oustees shall be compensated as per the norms laid down in the R&R policy of the company/State Government /Central Government, as applicable.

Issues raised during Public Hearing is

complied

Presently the R&R work is under progress as

per laid down norms of CIL

The R & R details are as under:

Employment given till date: 2720

PAFs: 3376

a. At Rehabilitation Site: 839

b. Cash Grant 839

ANNEX 28

ii The project proponent shall ensure the expenditure towards socio-economic development in and around the mine, in every financial year in pursuace of the Corporate Social Responsibility Policy as per the provisions under Section 135 of the Companies Act, 2013.

CSR activities are taken up as per Govt. Policy in

consultation with District Administration.

ANNEX 29

Year wise CSR Fund Provision is as below

2013-14:Rs. 6796.07 Lakhs

2014-15: Rs. 462.22 Lakhs

2015-16:Rs. 1878.24 Lakhs

2016-17:Rs. 6626.84 Lakhs

2017-18:Rs. 986.29 Lakhs

iii The project proponent shall follow the mitigation measures provided in this Ministry’s OM No.Z-1 I 013/5712014-1A.i1 (M) dated 29th October, 2014, titled ‘Impact of mining activities on habitations-issues related to the mining projects wherein habitations and villages are the part of mine lease areas or habitations and villages are surrounded by the mine lease area’.

Necessary R & R work has been carried out as per

Govt. Policy ANNEX (28)

iv The project proponent shall make necessary alternative arrangements, if grazing land is involved in core zone, in consultation with the State government to provide alternate areas for livestock grazing, if any. In this context, the project proponent shall implement the directions of Hon’ble Supreme Court with regard to acquiring grazing land.

As per Land Use Pattern no Grazing land is involved

in core zone. ANNEX 30

4.1

h

CORPORATE ENVIRONMENT RESPONSIBILITY

i The Company shall have a well laid down South Eastern Coalfields Limited (SECL), has a well

environment policy duly approved by Board of Directors. The environment policy should prescribe for standard operating procedures to have proper checks and balances and to bring into focus any infringements /deviation /violation of the environmental or forest norms/conditions. Also, the company shall have a defined system of reporting of non-compliances/violations of environmental norms to the Board of Directors and/or shareholders / stakeholders.

laid down Environment policy duly approved

Chairman cum Managing director (CMD), SECL

vide Noting sheet no. SECL/BSP/WBP/52/1247 dated

21.08.2009.

The copy of same is enclosed as Annexure 4.1h (i).

In addition to above Environmental Policy is also

available on the company’s website www.secl.gov.in

SECL recognizes its responsibilities for ensuring

sustainable mining with due regard to bio-physical

& socio-economic attributes in and around its

project area. This subject is one of the most

important & priority areas and the company has

ensured that it fulfills its obligations effectively.

SECL’s vision on this front is “Prevention is better

than control / cure” and has taken pro-active steps

for Environmental amelioration. The company has

secured 117 numbers of Environmental clearances

from Ministry of Environment Forest & Climate

change by way of Environment Management Plans.

The EMPs are prepared based on the approved PR

wherein comprehensive action plans with requisite

inputs of technology, manpower, equipment, capital

outlay and organizational structure for

implementation of abatement measures. SECL have

ensured the proper monitoring and compliance of

mitigation measures prescribed under the various

Rules/Regulations of Government of India/ State

Government to control the adverse impact of mining

activities.

ii The hierarchical system or Administrative Order of the company to deal with environmental issues and for ensuring compliance with the environmental clearance conditions should be displayed on website of the Company.

iii A separate environmental management cell

both at the project and company headquarter level, with suitable qualified personnel shall be set-up under the control of a Senior Executive, who will report directly to the Head of the Organization.

Details of environmental cell at area /project level is

as follows :-

Area level:

1. Staff Officer (P&P)

2. Staff Officer (Civil)

3. Area Nodal Officer (Envt./ Forest)

4. Area Survey Officer

Project level:

1. Project Officer

2. Staff Officer (Civil)

3. Environment Officer

4. Survey Officer.

iv Action plan for implementing EMP and

environmental conditions shall be prepared

and shall be duly approved by competent

authority. The year wise funds earmarked

for environmental protection measures shall

be kept in separate account and not to be

diverted for any other purpose. Year wise

progress of implementation of action plan

shall be reported to the Ministry/Regional

Office along with the Six Monthly

Compliance Report

Year-wise expenditure of environment related

works is being submitted to RO MoEF&CC

Bhopal/Nagpur in the six monthly report.

Expenditure Incurred For The Last Three FY is As

Below :

Financial Year Expenditure Of

Environment Related

Works (In Rs. Cr.)

2016-17 87.77

2017-18 84.11

2018-19 59.87

v Self-environmental audit shall be conducted

annually. Every three years third party

environmental audit shall be carried out.

Agreed.

Internal Committee has been constituted at

Area Level for Self Envt. Audit. The Internal

audit was done at Gevra Area on 25.07.2019.

Inter Area Monitoring mechanism

commenced on 05.08.19 as per the

instructions of GM (Envt), Bilaspur.

Accordingly, Gevra Area was inspected by

Kusmunda Area on 30.08.2019.

Third Party Audit is carried by ICFRE

Dehradun. Annex 4.1 h (v)

4.1 i STATUTORY OBLIGATIONS

i The environmental clearance shall be subject to orders of Hon’ble Supreme Court of India, Hon’ble High Court, NGT and any other Court of Law from time to time, and as applicable to the project.

Agreed.

ii This environmental clearance shall be subject to obtaining wildlife clearance, if applicable, from the Standing Committee of National Board for Wildlife.

Agreed.

iii The project proponent shall obtain Consent to Establish/Operate under the Air Act, 1981 and the Water Act, 1974 from the concerned State Pollution Control Board.

Agreed.

CTO renewal (2019-20) for 45 MTY under

Air and Water Act obtained vide Letter No.

7791/TS/CECB/ 2019 Dtd: 23.02.2019. Valid

till 29.02.2020. (Annex 4.1i(iii))

iv The project proponent shall obtain the necessary permission from the Central Ground Water Authority (CGWA).

NOC for 11487 m3/day withdrawal of ground

water issued vide NOC no.

CGWA/NOC/MIN/ORIG/2018/4474 Dt: 22.01.2019,

from Central ground water Authority, Ministry of

water Resources Govt. of India.

ANNEX 16

4.1 j MONITORING OF PROJECT

i Adequate ambient air quality monitoring stations shall be established in the core zone as well as in the buffer zone for monitoring of pollutants, namely PM10, PM2.5, SO2 and NOR. Location of the stations shall be decided based on the meteorological data, topographical features and environmentally and ecologically sensitive targets in consultation with the State Pollution Control Board. Online ambient air quality monitoring stations may also be installed in addition to the regular monitoring stations as per the requirement and/or in consultation with the SPCB. Monitoring of heavy metals such as Hg, As, Ni, Cd, Cr, etc to be carried out at least once in six months.

Eight ambient air quality monitoring stations have

been established (four in buffer zone and four in

core zone) based on the meteorological data,

topographical features and data is being submitted

regularly to CECB and also to MOEF&CC

Bhopal/Nagpur on monthly basis Monitoring of

heavy metals such as Hg, As, Ni, Cd, Cr, etc is carried

out.

ANNEX 31

ii The Ambient Air Quality monitoring in the core zone shall be carried out to ensure the Coal Industry Standards notified vide GSR

Eight ambient air quality monitoring stations have

been established (four in buffer zone and four in

742 (E) dated 25.9.2000 and as amended from time to time by the Central Pollution Control Board. Data on ambient air quality and heavy metals such as Hg, As, Ni, Cd, Cr and other monitoring data shall be regularly reported to the Ministry/Regional Office and to the CPCB / SPCB.

core zone) based on the meteorological data,

topographical features and data is being submitted

regularly to CECB and also to MOEF&CC

Bhopal/Nagpur on monthly basis ANNEX (25)

iii The effluent discharge (mine waste water, workshop effluent) shall be monitored In terms of the parameters notified under the Coal industry Standards vide GSR 742 (E) dated 25.9.2000 and as amended from time to time by the Central Pollution Control Board.

Regular/ fortnight Monitoring done. ANNEX (25)

iv The monitoring data shall be uploaded on

the company’s website and displayed at the project site at a suitable location. The

circular No. J-200121112006-IA.1 I (M)

dated 27.05.2009 issued by Ministry of

Environment, Forest and Climate Change

shall also be referred in this regard for its

compliance.

Agreed.

CAAQMS has been installed for continuous

monitoring of ambient air parameters and

the data is being displayed at the project site.

ANNEX 32

v Regular monitoring of ground water level and quality shall be carried out in and around the mine lease area by establishing a network of existing wells and constructing new piezometers during the mining operations. The monitoring of ground water levels shall be carried out four times a year i.e. pre-monsoon, monsoon, post-monsoon and winter. The ground water quality shall be monitored once a year, and the data thus collected shall be sent regularly to Ministry of Environment, Forest and Climate Change / Regional Office.

Seven (07) sets (Deep & Shallow) of piezometers

have been constructed and also established a

network of existing wells where levels are

monitored regularly.

CMPDIL is regularly monitoring the level of ground

water and quality in number of wells located in the

study area of the project. ANNEX 33,34

vi Monitoring of water quality upstream arid downstream of water bodies shall be carried out once in six months and record of monitoring data shall be maintained and submitted to the Ministry of Environment, Forest and Climate Change/Regional Office.

Complied ANNEX 25

vii The project proponent shall submit six monthly reports on the status of the implementation of the stipulated environmental conditions to the Ministry of Environment, Forest and Climate Change/Regional Office. For half yearly monitoring reports, the data should be monitored for the period of April to

Agreed & complied regularly.

The Last report was submitted for the period

Ending, September 2019 Vide Letter No:

SECL/GM/GA/ENVT/2019/50 Dated 09.05.2019.

September and October to March of the financial years.

viii The Regional Office of this Ministry shall monitor compliance of the stipulated conditions. The project authorities should extend full cooperation to the officer (s) of the Regional Office by furnishing the requisite data / information/monitoring reports.

Agreed

4.1 k MISCELLANEOUS

i Efforts should be made to reduce energy consumption by conservation, efficiency improvements and use of renewable energy.

Agreed

Necessary initiatives taken to reduce energy

consumption by implementing LED lights in offices

and premises.

ii The project authorities shall inform to the

Regional Office regarding commencement

of mining operations

Agreed /Will be done.

iii A copy of the environmental clearance shall

be marked to concern Panchayat. A copy of

the same shall also be sent to the concerned’ State Pollution Control Board, Regional

Office, District Industry Sector and

Collector’s Office / tehsildar Office for information in public domain within 30

days.

Complied ANNEX 35

iv The EC shall be uploaded on the company’s website. The compliance status of the

stipulated EC conditions shall also be

uploaded by the project authorities on their

website and updated at least once every six

months so as to bring the same in public

domain.

Complied.

The latest Compliance Report For the period ending

March 2019 has been uploaded in the Company

website.

v The project authorities shall advertise at

least in two local newspapers widely

circulated, one of which shall be in the

vernacular language of the locality

concerned, within 7 days of the issue of the

clearance letter informing that the project

has been accorded environmental clearance

and a copy of the clearance letter is

available with the State Pollution Control

Complied.

Grant of 45 MTY EC published in Sandya

Samikshak, NaiDuniya & Dainik Bhaskar

ANNEX 36

Board and also at web site of the Ministry of

Environment, Forest and Climate Change at

www.environnlentclearance.nic.in and a

copy of the same shall be forwarded to the

Regional Office.

vi The environmental statement for each financial year ending 31 March in Form-V is mandated to be submitted by the project proponent for the concerned State Pollution Control Board as prescribed under the Environment (Protection) Rules, 1986, as amended subsequently, shall also be uploaded on the Company’s website along with the status of compliance of EC conditions and shall be sent to the respective Regional Offices of the MoEF&CC by e-mail. Concerns raised during public hearing

Environmental Audit Statement for the year

2018-19 was submitted to RO MoEF&CC

Nagpur vide letter no:

SECL/GM/GA/ENVT/2019/237 Dt: 22/09/19.

Environmental Audit Statement for the year

2018-19 was submitted to CECB Raipur vide

letter no: SECL/GM/GA/ENVT/2019/238 Dt:

22/09/19.

vii The Ministry may stipulate any further condition for environmental protection, if so required in due course of time.

Agreed.

viii The above conditions will be enforced inter-alia, under the provisions of the Water (Prevention & Control of Pollution) Act, 1974, the Air (Prevention & Control of Pollution) Act, 1981, the Environment (Protection) Act, 1986 and the Public Liability Insurance Act, 1991 along with their amendments and Rules and any other orders passed by the Hon’ble Supreme Court of India/High Courts and any other Court of Law relating to the subject matter.

Accepted.

5 The proponent shall abide by all the commitments and recommendations made in the EIA/EMP report and also that during presentation to the EAC. All the commitments made on the issues raised during public hearing shall also be implemented in letter and spirit.

Agreed.

6 The proponent shall obtain all necessary clearances/approvals that may be required before the start of the project. The Ministry or any other competent authority may stipulate any further condition for environmental protection. The Ministry or any other competent authority may stipulate any further condition for environmental protection.

Agreed.

7 Concealing factual data or submission of false/fabricated data and failure to comply

Agreed.

Scanned by CamScanner

ANNEX 1

WATER SPRINKLING

BELT CONVEYOR OF CHP

MIST SPRAY IN CHP

ANNEX 1

FEEDER BREAKER

ANNEX 2

MOBILE WATER SPRINKLERS

ANNEX 3

SURFACE MINER

ANNEX 6

PLANTATION

ANNEX 6

GREEN BELT

STATEMENT SHOWING DETAILS OF PLANTATION OF GEVRA PROJECT

YEAR

PLANTATION DONE ON

Total Plantation

done (in nos)

CPT

(1.5mx0.9mx0.75

m) (in Rmtrs)

GRASS BED

(Nos.) On Plain

area

(nos)

On

internal

dumps

(nos)

On

External

dumps (nos)

Total

Plantation on

dumps (nos).

1 2 3 4 5=(3+4) 6=(2+3+4) 7 8

1986 236000 0 0 0 236000 0 0

1987 245750 0 46000 46000 291750 0 0

1988 419500 0 0 0 419500 0 0

1989 454000 0 0 0 454000 0 0

1990 372883 0 0 0 372883 0 0

1991 360000 0 0 0 360000 0 0

1992 64900 0 0 0 64900 0 0

1993 87230 0 26970 26970 114200 0 0

1994 0 0 0 0 0 0 0

1995 77000 0 0 0 77000 0 0

1996 68000 0 64000 64000 132000 0 0

1997 50000 17500 105500 123000 173000 0 0

1998 42000 52150 31850 84000 126000 0 15000

1999 11950 0 65000 65000 76950 3150 18000

2000 0 0 130000 130000 130000 0 15000

2001 0 0 66000 66000 66000 0 13000

2002 10000 0 30000 30000 40000 500 4000

2003 30000 81000 20000 101000 131000 1270 15000

2004 22000 5500 78500 84000 106000 3583 36000

2005 76000 0 39500 39500 115500 4800.33 39500

2005 41500 0 0 0 41500 2000 0

2006 75000 40000 5000 45000 120000 4500 45000

2007 50000 0

0 50000 0 0

2008 5000 0 20000 20000 25000 0 0

2009 32500 0 30000 30000 62,500 0 20000

2010 2500 36500

36500 39,000 0 0

2011 0 27500 0 27500 27,500 0 12500

2012 10000 20000 0 20000 30000 0 3125

2013 5000 0 35000 35000 40000 0 5000

2014 0 0 20000 20000 20000 0 0

2015 0 0 80000 80000 80000 0 10000

2016 0 0 50000 50000 50000 0 0

2017 0 0 100000 100000 100000 0 5000

2018 6500 0 60000 60000 66500 0 0

2019 62750 0 0 0 62750 0 0

Total 2917963 280150 1103320 1383470 4301433 19803.3 256125

Planted

area

(Ha)

649.52 122.6 367.2 489.8 1139.32

# 1988-89 Plantation includes Bareli Village 140000 plants over an area of 56.000 Ha.

1989-90 Plantation includes Near Bareli Village 206600 plants over an area of 82.640 Ha.

1990-91 Plantation includes Mine Boundary near Bareli 20000 plants over an area of 8.000 Ha.

1991-92 Plantation includes Bareli Bhata Village (A) 138303 plants over an area of 55.320 Ha.

Plantation includes Bareli Bhata Village (B) 144185 plants over an area of 57.670 Ha.

1992-93 Plantation includes Near Bareli Pondi Bhata Village 43802 plants over an area of 17.520 Ha.

Therefore Presently Plain area Plantation: 2225073 nos. over an area of 372.37 Ha. within the Mine

lease.

Scanned by CamScanner

ANNEX 19

Gabion wall (3m X 3m for 0.5 Km ) along the toe wall of approach road

ANNEX 20

ANNEX 21

Scanned with CamScanner

Scanned with CamScanner

Scanned with CamScanner

Scanned with CamScanner

Scanned with CamScanner

Scanned with CamScanner

ANNEX 33

2019

Piezometer Reading of Gevra Area Deep(O) shallow Platform height (0.4+/- 0.10)

Sl.No. Date Raliya Gevra Basti Bhilai Bazar Magzin Bld. CGM Office Sr..Recreation club

Backup sub station

No.2

Shallow Deep Shallow Deep Shallow Deep Shallow Deep Shallow Deep Shallow Deep Shallow Deep

1 15.01.2019 4.45 6.50 0.00 0.00 0.00 0.00 10.50 13.60 6.00 12.30 1.50 11.00 0.00 15.75

2 15.02.2019 4.45 6.50 0.00 0.00 0.00 0.00 11.20 14.60 6.15 13.05 1.60 10.90 0.00 15.85

3 04.03.2019 4.60 6.65 0.00 0.00 0.00 0.00 11.50 14.35 6.15 12.80 1.55 11.05 0.00 16.00

4 17.04.2019 5.00 7.55 0.00 0.00 0.00 0.00 12.15 15.25 6.10 13.05 1.70 12.10 0.00 16.40

5 30.05.19 4.70 7.40 0.00 0.00 0.00 0.00 13.30 16.05 7.40 13.75 2.10 14.10 0.00 11.30

6 28.06.19 4.00 6.80 0.00 0.00 0.00 0.00 13.20 15.70 6.00 13.15 1.05 11.50 0.00 11.10

7 15.07.19 3.80 6.50 0.00 0.00 0.00 0.00 13.10 15.70 5.50 12.95 1.20 11.40 0.00 11.00

8 09.08.19 1.95 5.50 0.00 0.00 0.00 0.00 12.45 15.10 3.70 12.10 0.00 10.40 0.00 10.20

9 26.09.2019 1.00 3.35 0.00 0.00 0.00 0.00 6.50 10.45 2.20 10.60 0.60 8.65 0.00 6.10

10 14.10.19 1.00 2.70 0.00 0.00 0.00 0.00 5.40 9.70 2.80 10.20 0.90 8.60 0.00 5.10

Scanned by CamScanner

Scanned by CamScanner

Scanned by CamScanner

Scanned by CamScanner

AIR QUALITY ASSESSMENT OF GEVRA OC

EXPANSION PROJECT

Capacity: 45 MTPA

Period (December 2018-March 2019)

South Eastern Coalfields Limited ( A Mini Ratna Company )

March, 2019

Prepared by - Central Mine Planning & Design Institute Limited

Regional Institute – V CMPDI Complex, 495006

BILASPUR (C.G.)

COPYRIGHT WITH

CMPDI ISO 9001 company

Contents

CMPDI i

CONTENTS

Cover page

Contents

TEXT

Sl. No. Particulars Pages

1.0 Introduction 1

1.1 Scope of work 1

1.2 Methodology 1

1.3 Plan for sampling locations 1

2.0 Ambient air monitoring report 2-16

2.1 Concept & scope 2

2.2 Frequency of sampling 2

2.3 Sampling methodology 2

2.4 Result and discussion 4-16

FORWARD

M/s Central Mine Planning & Design Institute Ltd (CMPDI) RI-V, Bilaspur has undertaken the

task of Air quality assessment of Gevra OC Expansion project of M/s SECL at stations specified

in its EIA report. It entrusted the task for environmental data generation with respect of Group I

parameters viz PM100, PM10, PM2.5, SOx and NOx to Kusmunda Environmental Laboratory

CMPDIL RI-V, Bilaspur.

The data on Environmental quality for Post-Monsoon (December 2018 to March 2019) had been

collected under the guidance of Mr. I.D. Narayan, The Regional Director, RI-V; Bilaspur and Mr.

H.K. Gour, HOD (Environment), Central Mine Planning & Designing Institute, RI-V, Bilaspur.

We are thankful of all the associated executives and staff of Central Mine Planning & Designing

Institute, RI-V, Bilaspur for tremendous efforts and also Officers and staff of Gevra Area, SECL

for necessary support.

1

1.0 INTRODUCTION

1.1 SCOPE OF WORK

The scope of work in the present study is to monitor the Environmental status in order to

understand the current environmental conditions in and around the project. The monitoring will

be carried out on seasonal basis (Post-monsoon), thus the data generated will be used to estimate

the present trend in comparison with emission standards.

1.2 METHODOLOGY

In the present study we followed the standard methods for collection, analysis & interpretation of

data

AAQM Sampling & analysis: “Indian Standards (IS 5182)”, “Guidelines for the measurement of Ambient Air Pollutants, Vol-I, CPCB” & “USEPA” methods were used for Ambient Air sampling and analysis to study the present pollution load around the Proposed Project locations.

Parameters

of AAQM Standard Methods

Analytical

Instruments Make & Model

PM10 IS 5182 (P-23):2006 Analytical Balance Citizen CX401

PM2.5 USEPA CFR 40(P-50),

Appendix -L Micro Balance Citizen CM2F

PM100 IS 5182 (P-4):1999, RA

2005 Analytical Balance Citizen CX401

1.3 PLAN FOR SAMPLING LOCATIONS

As desired by SECL, the locations were same which one were identified in its EIA report. A

synopsis about the locations is as follows:

Location

Code

Name of

Location Latitude Longitude

As per Wind

Direction

Distance

in Kms

L1 Rohina Village N 22ᴼ22’04.06’’ E 82ᴼ37’06.74’’ Downwind

(NNE) 2.2

L2 Kapatmura

Village N 22ᴼ21’45.92’’ E 82ᴼ38’34.17’’

Downwind

(NE) 1.9

L3 Katkidabri

Village N 22ᴼ17’35.91’’ E 82ᴼ33’47.85’’

Upwind

(SW) 3.0

L4 Salora Village N 22ᴼ18’27.06’’ E 82ᴼ38’02.25’’ Crosswind

(SE) 0.8

L5 Gobarghora

Village N 22ᴼ21’14.76’’ E 82ᴼ33’38.06’’

Crosswind

(NW) 1.7

L6 Filter plant,

Gevra OC N 22ᴼ21’36.82’’ E 82ᴼ38’38.90’’ Core Zone 0.0

2

2.0 AMBIENT AIR MONITORING REPORT

2.1 CONCEPT & SCOPE

The Ambient Air monitoring encompasses the results and statistical evaluation of the data

monitored at Six locations in the Gevra OC project site. The scope of study includes air

quality assessment at baseline monitoring stations for three Months from December 2018

to March 2019.

Different parameters like PM100, PM10, PM2.5, Oxides of Sulphur, Oxides of Nitrogen,

were monitored for representing the ambient air quality within the study area.

2.2 FREQUENCY OF SAMPLING

The frequency of the sampling for AAQM was as follows:

Parameters Frequency of each Location

PM100, PM10, PM2.5, Oxides of Sulphur,

Oxides of Nitrogen Twice in a week

Sampling duration as per NAAQMS 2009

SI. No Parameters Sampling Duration ( Hr.)

1 PM100 24

2 PM10 24

3 PM2.5 24

4 Oxides of Sulphur (SOx) 24

5 Oxides of Nitrogen (NOx) 24

2.3 SAMPLING METHODOLOGY

AAQM METHODOLOGY :

Respirable Dust Sampler (RDS) was used for PM100 & PM10 sampling. Pre-weighted Glass Micro

fiber filter paper & NRD Cup were used to analyze PM100 & PM10 gravimetrically.

Fine Particulate Sampler (FPS) was used for PM2.5 sampling and the sample was collected on

PTFE filter paper. PM2.5 was analyzed gravimetrically.

Oxides of Sulphur in the air was absorbed in TCM using Gaseous Pollutant Sampler and analyzed

by “Improved West & Gaeke” method. Oxides of Nitrogen in the air was absorbed in mixed 0.1 (N) NaOH & Sodium arsenite solution

using Gaseous Pollutant Sampler and analyzed by “Modified Jacob & Hochheiser” method.

3

2.4 RESULTS AND DISCUSSION:

The air quality assessment results at baseline stations of Gevra OC are provided below at all

monitoring stations.

Name Of Location ROHINA VILLAGE

SL

No

Starting Date PM100 PM10 PM2.5 SOX NOx

Unit µg/m3 µg/m3 µg/m3 µg/m3 µg/m3

GSR 826 (E):

Residential

200 100 60 80 80

GSR 742 (E): Industrial 600 300 - 120 120

1 07.12.2018 168 84 50 25 20

2 11.12.2018 172 80 45 27 21

3 14.12.2018 171 80 48 26 20

4 18.12.2018 121 68 36 25 18

5 21.12.2018 147 72 39 19 15

6 25.12.2018 171 85 42 21 16

7 28.12.2018 169 78 49 26 18

8 02.01.2019 170 85 51 46 33

9 04.01.2019 150 76 43 28 18

10 08.01.2019 166 78 49 29 23

11 11.01.2019 165 72 48 25 19

12 15.01.2019 170 80 49 36 27

13 18.01.2019 162 77 51 33 22

14 22.01.2019 158 74 47 32 21

15 24.01.2019 166 80 50 27 26

16 29.01.2019 163 78 46 31 30

17 05.02.2019 177 84 45 29 34

18 08.02.2019 163 69 41 26 36

19 14.02.2019 181 74 46 23 30

20 16.02.2019 165 72 49 29 25

21 19.02.2019 179 65 43 24 34

22 22.02.2019 177 78 41 27 27

23 28.02.2019 172 84 50 28 36

24 04.03.2019 168 70 48 36 25

RESULT INTERPRETATIONS

No Of Observations 24 24 24 24 24

Maximum Concentration 181 85 51 46 36

Minimum Concentration 121 65 36 19 15

98th Percentile 179 85 51 36 36

Arithmetic Mean 165 77 46 28 25

4

Graphical Representation of the Results:

From the above graphical presentation, it is clearly interpreted that all the values of PM10, PM2.5,

PM100, SOx and NOx were lower than the prescribed limits for location L1 i.e. Rohina Village.

Coming to the result, the average concentration of PM100 in this location was found 165 µg/m3 with

the range of 121 to 181 µg/m3. As per the standards for coal mines, GSR 742(E) dated 25th September

2000, the concentration of PM100 in this location was lower than the limits i.e. 200 µg/m3 for entire

the study period.

In case of PM10, the concentration was below the limits proposed in the standards GSR 826(E) dated

16th November 2009 of MoEF. The average concentration of PM10 was found 77 µg/m3 with the range

of 65 to 85 µg/m3.

For PM2.5, the arithmetic mean was found 46 µg/m3 & the range was 36 to 51 µg/m3. Concentration

of PM2.5 for entire the study period was lower than the limits as per GSR 826(E) dated 16th November

2009 of MoEF.

It is clearly interpreted that the concentration for SOx & NOx in Rohina Village was far below from

the prescribed limits. Average values for SOx & NOx were noticed 28 & 25 µg/m3 respectively.

0

20

40

60

80

100

120

140

160

180

200Rohina Village Air Quality

PM100 PM10 48 SOx NOx

5

Name Of Location KAPATMURA VILLAGE

SL

No

Starting Date PM100 PM10 PM2.5 SOX NOx

Unit µg/m3 µg/m3 µg/m3 µg/m3 µg/m3

GSR 826 (E):

Residential

200 100 60 80 80

GSR 742 (E): Industrial 600 300 - 120 120

1 06.12.2018 173 77 47 27 19

2 10.12.2018 168 76 48 69 43

3 13.12.2018 165 61 49 26 21

4 17.12.2018 99 61 20 33 19

5 20.12.2018 158 63 47 36 27

6 24.12.2018 172 77 39 23 18

7 27.12.2018 139 78 40 29 22

8 01.01.2019 172 85 43 40 48

9 03.01.2019 164 83 48 28 22

10 07.01.2019 155 74 42 36 33

11 10.01.2019 164 78 45 27 20

12 14.01.2019 166 80 38 31 20

13 17.01.2019 168 82 43 21 18

14 21.01.2019 151 70 47 61 62

15 23.01.2019 160 74 45 33 19

16 28.01.2019 168 78 50 31 30

17 01.02.2019 169 84 47 25 30

18 07.02.2019 174 75 49 40 34

19 12.02.2019 163 78 42 31 38

20 14.02.2019 171 71 44 35 29

21 18.02.2019 165 73 47 39 34

22 21.02.2019 177 79 50 26 27

23 27.02.2019 179 75 43 37 32

24 01.03.2019 172 72 48 24 29

RESULT INTERPRETATIONS

No Of Observations 24 24 24 24 24

Maximum Concentration 179 85 50 69 62

Minimum Concentration 99 61 20 21 18

98th Percentile 177 84 50 61 48

Arithmetic Mean 163 75 44 34 29

6

Graphical Representation of the Results:

In case of Kapatmura Village (L2) average concentration of PM100 in this location was found 163

µg/m3 with the range of 99 to 179 µg/m3.

The average concentration of PM10 at Kapatmura Village was found 75 µg/m3 with the range

of 61 to 85 µg/m3.

For PM2.5, the arithmetic mean was found 44 µg/m3 & the range was 20 to 50 µg/m3.

The concentration for SOx & NOx in Kapatmura Village was far below from the prescribed

limits. Average values for SOx & NOx were noticed 34 & 29 µg/m3 respectively.

0

20

40

60

80

100

120

140

160

180

200

Kapatmura Village Air Quality

PM100 PM10 PM2.5 SOx NOx

7

Name Of Location KATKIDABRI VILLAGE

SL

No

Starting Date PM100 PM10 PM2.5 SOX NOx

Unit µg/m3 µg/m3 µg/m3 µg/m3 µg/m3

GSR 826 (E):

Residential

200 100 60 80 80

GSR 742 (E): Industrial 600 300 - 120 120

1 06.12.2018 134 75 46 21 19

2 10.12.2018 172 79 45 38 35

3 13.12.2018 150 71 42 28 21

4 17.12.2018 131 58 27 31 27

5 20.12.2018 165 70 45 32 26

6 24.12.2018 161 84 50 48 47

7 27.12.2018 174 79 44 31 48

8 01.01.2019 174 87 48 26 26

9 03.01.2019 168 78 43 28 26

10 07.01.2019 172 86 50 27 24

11 10.01.2019 165 78 48 27 22

12 14.01.2019 168 82 49 30 23

13 17.01.2019 162 72 46 29 26

14 21.01.2019 158 71 50 31 26

15 23.01.2019 164 77 45 28 26

16 28.01.2019 168 82 43 32 32

17 01.02.2019 160 82 44 40 29

18 07.02.2019 174 78 49 36 31

19 12.02.2019 168 76 41 38 42

20 14.02.2019 170 74 45 27 35

21 18.02.2019 166 79 49 25 30

22 21.02.2019 174 71 40 36 37

23 27.02.2019 173 76 48 37 37

24 01.03.2019 169 73 41 31 34

RESULT INTERPRETATIONS

No Of Observations 24 24 24 24 24

Maximum Concentration 174 87 50 48 48

Minimum Concentration 131 58 27 21 19

98th Percentile 174 86 50 40 47

Arithmetic Mean 164 77 45 32 30

8

Graphical Representation of the Results:

In case of Katkidabri Village (L3) average concentration of PM100 in this location was found

164 µg/m3 with the range of 131 to 174 µg/m3.

The average concentration of PM10 at Katkidabri Village was found 77 µg/m3 with the range of

58 to 87 µg/m3.

For PM2.5, the arithmetic mean was found 45 µg/m3 & the range was 27 to 50 µg/m3.

The concentration for SOx & NOx in Katkidabri Village was far below from the prescribed

limits. Average values for SOx & NOx were noticed 32 & 30 µg/m3 respectively.

0

20

40

60

80

100

120

140

160

180

200

Katkidabri Village Air Quality

PM100 PM10 PM2.5 SOx NOx

9

Name Of Location SALORA VILLAGE

SL

No

Starting Date PM100 PM10 PM2.5 SOX NOx

Unit µg/m3 µg/m3 µg/m3 µg/m3 µg/m3

GSR 826 (E):

Residential

200 100 60 80 80

GSR 742 (E): Industrial 600 300 - 120 120

1 06.12.2018 145 77 51 19 26

2 10.12.2018 162 75 43 77 61

3 13.12.2018 175 65 39 27 20

4 17.12.2018 70 57 20 32 26

5 20.12.2018 169 70 40 29 22

6 24.12.2018 149 73 42 31 26

7 27.12.2018 151 77 47 30 21

8 01.01.2019 165 83 51 35 21

9 03.01.2019 170 82 45 33 22

10 07.01.2019 172 86 48 28 19

11 10.01.2019 166 75 48 30 29

12 14.01.2019 168 77 46 36 26

13 17.01.2019 157 67 45 38 26

14 21.01.2019 161 76 46 31 23

15 23.01.2019 166 84 50 39 29

16 28.01.2019 148 78 45 30 28

17 01.02.2019 170 68 50 27 34

18 07.02.2019 166 74 41 25 31

19 12.02.2019 174 78 49 29 27

20 14.02.2019 175 70 45 31 36

21 18.02.2019 172 76 46 27 25

22 21.02.2019 169 79 43 36 38

23 26.02.2019 177 75 49 28 34

24 28.02.2019 179 73 44 33 37

RESULT INTERPRETATIONS

No Of Observations 24 24 24 24 24

Maximum Concentration 179 86 51 77 61

Minimum Concentration 70 57 20 19 19

98th Percentile 177 84 51 39 38

Arithmetic Mean 162 75 45 33 29

10

Graphical Representation of the Results:

In case of Salora Village (L4) average concentration of PM100 in this location was found 162

µg/m3 with the range of 70 to 179 µg/m3.

The average concentration of PM10 at Salora Village was found 75 µg/m3 with the range of 57

to 86 µg/m3.

For PM2.5, the arithmetic mean was found 45 µg/m3 & the range was 20 to 51 µg/m3.

The concentration for SOx & NOx in Salora Village was far below from the prescribed limits.

Average values for SOx & NOx were noticed 33 & 29 µg/m3 respectively.

0

20

40

60

80

100

120

140

160

180

200

Salora Village Air Quality

PM100 PM10 PM2.5 SOx NOx

11

Name Of Location GOBARGHORA VILLAGE

SL

No

Starting Date PM100 PM10 PM2.5 SOX NOx

Unit µg/m3 µg/m3 µg/m3 µg/m3 µg/m3

GSR 826 (E):

Residential

200 100 60 80 80

GSR 742 (E): Industrial 600 300 - 120 120

1 06.12.2018 156 76 45 25 23

2 10.12.2018 124 84 38 30 30

3 13.12.2018 169 82 48 30 26

4 17.12.2018 170 81 42 37 36

5 20.12.2018 173 82 48 29 32

6 24.12.2018 143 67 38 27 25

7 27.12.2018 173 77 48 30 26

8 01.01.2019 158 78 48 20 26

9 03.01.2019 172 84 51 30 27

10 07.01.2019 175 85 52 33 29

11 10.01.2019 166 75 48 30 18

12 14.01.2019 168 80 47 28 27

13 17.01.2019 164 70 51 33 31

14 21.01.2019 158 72 52 30 20

15 23.01.2019 149 67 45 33 26

16 28.01.2019 164 70 43 31 32

17 05.02.2019 148 69 45 28 35

18 08.02.2019 165 75 49 36 33

19 13.02.2019 177 71 41 37 29

20 15.02.2019 171 78 44 32 37

21 19.02.2019 168 73 50 40 35

22 22.02.2019 173 66 44 39 30

23 27.02.2019 179 65 40 44 27

24 01.03.2019 166 71 47 29 33

RESULT INTERPRETATIONS

No Of Observations 24 24 24 24 24

Maximum Concentration 179 85 52 44 37

Minimum Concentration 124 65 38 20 18

98th Percentile 177 84 52 40 36

Arithmetic Mean 164 75 46 32 29

12

Graphical Representation of the Results:

In case of Gobarghoda Village (L5) average concentration of PM100 in this location was found

164 µg/m3 with the range of 124 to 179 µg/m3.

The average concentration of PM10 at Gobarghoda Village was found 75 µg/m3 with the range

of 65 to 85 µg/m3.

For PM2.5, the arithmetic mean was found 46 µg/m3 & the range was 38 to 52 µg/m3.

The concentration for SOx & NOx in Gobarghoda Village was below from the prescribed limits.

Average values for SOx & NOx were noticed 32 & 29 µg/m3 respectively.

0

20

40

60

80

100

120

140

160

180

200

Gobarghoda Village Air Quality

PM100 PM10 PM2.5 SO2 NOx

13

Name Of Location FILTER PLANT, GEVRA OC

SL

No

Starting Date PM100 PM10 PM2.5 SOX NOx

Unit µg/m3 µg/m3 µg/m3 µg/m3 µg/m3

GSR 826 (E):

Residential

200 100 60 80 80

GSR 742 (E): Industrial 600 300 - 120 120

1 06.12.2018 411 253 48 40 29

2 10.12.2018 408 256 52 48 32

3 13.12.2018 334 184 51 34 20

4 17.12.2018 519 249 50 65 70

5 20.12.2018 204 114 43 30 24

6 24.12.2018 224 119 40 27 26

7 27.12.2018 453 233 50 27 27

8 01.01.2019 378 158 43 14 20

9 03.01.2019 451 256 47 29 30

10 07.01.2019 440 260 48 39 36

11 10.01.2019 510 250 52 39 25

12 14.01.2019 500 210 45 36 18

13 17.01.2019 436 168 51 28 18

14 21.01.2019 395 161 50 29 23

15 23.01.2019 404 164 43 24 24

16 28.01.2019 422 159 45 32 31

17 01.02.2019 400 222 43 45 29

18 07.02.2019 393 198 43 41 35

19 12.02.2019 450 202 49 46 37

20 14.02.2019 478 230 53 42 44

21 19.02.2019 512 191 42 49 45

22 22.02.2019 443 175 49 47 39

23 27.02.2019 496 179 48 43 37

24 01.03.2019 357 205 49 49 36

RESULT INTERPRETATIONS

No Of Observations 24 24 24 24 24

Maximum Concentration 519 260 53 65 70

Minimum Concentration 204 114 40 14 18

98th Percentile 512 256 52 49 45

Arithmetic Mean 417 200 47 38 31

14

Graphical Representation of the Results:

From the above graphical presentation, it is clearly interpreted that all the values of PM10, PM2.5,

PM100, SOx and NOx were lower than the prescribed limits for location L6 i.e. Filter Plant, Gevra OC

Coming to the result, the average concentration of PM100 in this location was found 417 µg/m3 with

the range of 204 to 519 µg/m3. As per the standards for coal mines, GSR 742(E) dated 25th September

2000, the concentration of PM100 in this location was lower than the limits i.e. 600 µg/m3 for entire

the study period.

In case of PM10, the concentration was below the limits proposed in the standards GSR 742(E) dated

25th September 2000. The average concentration of PM10 was found 200 µg/m3 with the range of 114

to 260 µg/m3.

For PM2.5, the arithmetic mean was found 47 µg/m3 & the range was 40 to 53 µg/m3.

It is clearly interpreted that the concentration for SOx & NOx in Filter Plant, Gevra OC was far below

from the prescribed limits. Average values for SOx & NOx were noticed 38 & 31 µg/m3 respectively.

0

100

200

300

400

500

600

Filter plant, Gevra OC Air Quality

PM100 PM10 PM2.5 SO2 NOx

15

The air quality assessment results at baseline stations of Gevra OC are summarized below:

Summarized data on Air Quality Status of Gevra OC Project

Sr.

No. Station

Station

Category as

per G.S.R.

716(E) ,

742(E) &

826(E)

Concentration PM 100

(µg/m3)

PM10

(µg/m3)

PM2.5

(µg/m3)

SOx

(µg/m3)

NOx

(µg/m3)

1 Rohina Village Residential(B)

Maximum 181 85 51 46 36

Minimum 121 65 36 19 15

Average 165 77 46 28 25

2 Kapatmura Village Residential(B)

Maximum 179 85 50 69 62

Minimum 99 61 20 21 18

Average 163 75 44 34 29

3 Katkidabri Village Residential(B)

Maximum 174 87 50 48 48

Minimum 131 58 27 21 19

Average 164 77 45 32 30

4 Salora Village Residential(B)

Maximum 179 86 51 77 61

Minimum 70 57 20 19 19

Average 162 75 45 33 29

5 Gobarghoda Village Residential(B)

Maximum 179 85 52 44 37

Minimum 124 65 38 20 18

Average 164 75 46 32 29

6 Filter Plant Gevra OC Industrial Zone

(A-O)

Maximum 519 260 53 65 70

Minimum 204 114 40 14 18

Average 417 200 47 38 31

Lim

it (

in µ

g/m

3)-

24

hrs

Industrial Zone -

(G.S.R. 742(E), dated

25.9.2000)

A-O 600 300 - 120 120

Residential Zone-

(G.S.R. 826(E), dated

16.11.2009 and GSR

176 (E), April 02, 1996)

B 200 100 60 80 80

16

From above results it may be conclude that, all the station has pollutants concentration within

permissible limit as per Coal Mines standards.

*******************************

Signature

Approved

RI-V,BILASPUR

CMPDIDrg. No.

Scale:

Activity

Checked

Drawn

Name

S. E. C. L.

Sr.D/Man

Designation

5O3253

A.Saxena HOD(ENV)

S.R.Karsh

L5

L1L2

L3

L6

L4

SCALE:

0 2 4 6 6 KMS.

L1: ROHINA VILLAGE (DOWN WIND)

L2: KAPATMURA VILLAGE (DOWN WIND)

L3: KATKI DABRI VILLAGE (UP WIND)

L4: SALORA VILLAGE (CROSS WIND)

L5: GOBORGHORA VILLAGE (CROSS WIND)

L6: FILTER PLANT, GEVRA OC (CORE ZONE)

MET DATA STATION: DETP, GEVRA OC

ENVIRONMENTAL BASELINE DATA GENERATION FOR GEVRA OC

AIR, NOISE, WEATHER MONITORING STATION

AishwaryaAsst. Mang(ENV)

PLATE NO:

CENTRAL MINE PLANNING AND DESIGN INSTITUTE LIMITEDEnvironment Laboratory, Regional Institute-V,

Phone: (07815) 271646, email: [email protected].

website: www.cmpdi.co.in

cmpdi

AIR OUATITY REPORT

Month DECEMBER Area GEVRA Report No KSM/2078/L2102

Name of the Customer South Eastern Coalfields Ltd, Bi laspur Date of Issue 15.02.2019

Name of the Project GEVRA OC Sample Reference No. t-2

Parameter SPM PMlO PM2.5 so2 NO2

Remarks

E

E+;+EE.E

lndu5trial Zone -(c.S.R. 742(E),

dated 25.9.2000)

A-O 600 300 720 120

500 250 120 120

R.iidcnti.l Zonc-{G.S.R. 826(E),

dated 15.u.2009 and GsR 176 {E},

02.04.1996)

I 200 100 80 8t)

Method of analysis

r9s182

4:2m5

15-5182

23:2005

cPcBvot

t,2011

ts-5182

2:2001

r95182

PART

6:2m6

Uncertainty Range (in F&/m3) 119.04 10.0687 10.4420

Station f{ame

(cod€)Station

category

Date olsampling

Date of

analyris

l-Rohina Wllate B

07.72,2074 11.t2.2074 168 a4 50 25 20

11.12.2018 L4.72.20tA 172 a0 27 27

14,12.2018 18.12.2018 11t 80 48 26 20

18.12,2018 21,12.201A 121 68 36 18

25.L2.20L4 L41 39 19 19

25.12.2074 28.12.20r8 85 42 2t 15

24.72.20LA 01.01.2019 78 49 26 18

2{.pstmuraVlllage

s

06.12.2018 09.12.20la L73 77 47 27 19

10.12.201a 13.12.201a 168 76 4a 69 43

13.12.2018 r7.12,207a 165 61 49 26 21

t7,12.201a 99 51 20 33 19

20,L2,2074 158 53 47 35 27

24.12-2014 27,72.20,'4 712 77 23 18

21.L2.20La 31.12.2018 139 7A 29 22

Analvzed byo.DekChecked by La In charge

Note: 1)The results above relate to the samples tested.

2) This repon cannot be reproduced in part or full without the written permission ofthe HoD (Env), cMpDl gilaspur, Rt-v

Page I of :l

A Minl-Ratno

Compony

A.N

60

45

25

21.12.20t4

17L

169

20,72.2O1A

24,L2.2074

39

40

c{-

CENTRAL MINE PLANNING AND DESIGN INSTITUTE LIMITEDEnvironment Laboratory, Regional lnstitute-V,

Phone: (07E15) 271646, email: [email protected],

website: www.cmpdi.co.in

cmpdiA lrlini-Ratno

Compony

AIR REPORT

Month DECE M BE R Area GEVRA Report No KSM/2018/L2/02

Name of tfie Crstomer South Eastern Coalfields Ltd, Bilaspur Date of lssue 1s.02.20r.9

Ilame of the Prolect GEVRA OC Sample Reference No. 3-4

Parameter SPM PMlO PM2.5 so2 NO2

Remarks

lndustrial zone {G.S.R. 7 42lal,

dated 25.9.2O0O)

A-O 600 3m 120 120

A.N 500 250 120 120

R.sidential Zone-(G.S.R. 826(E),

dated 16.u.2009 and GSR 176 (E),

02.04.1996)

B 200 100 60 80 80

Method of analysir

rs-5182

4:2m5

ts,5182

23:2m6

CPCBvol-

t,2013

r95182

L2@1

ts-5182

6:2m6

Uncertainty Range (in F&/m3) 119.04 r0.0587

Station Name

(code)

Station

category

Date of

sampling

Date ot

analysis

3-Katkidabri

lrlllaSeB

t)6.12,2018 09.12.2014 L34 73 45 2L 19

70.L2,2074 L3.12.20L8 t2 79 45 38 35

L2.12,20L4 77 42 27

17.12.2018 131 58 27 31 27

20.72.20A4 24.72.20t4 165 70 45 32 26

24.72,207a 27,t2.20L4 161 84 50 4a 47

27 -12.207a 31.12.2018 774 79 44 48

il-Salora VlllageB

09.12.2O14 145 77 51 L9

70.L2.20L8 11.l2.20!8 L62 43 77 67

13.12.2018 L7.L2.20L4 L7S 65 39 27 20

17.12.2018 20.12.2014 70 20 32 25

20.12.2074 24.L2.20L8 169 70 40 29 22

24.!2.2044 27.t2.20L8 149 73 42 31 26

27.t2.20L4 31.12.2014 151 77 47 30 27

D&Checked by Lab ln charseAnalyzed by

r!ol! ll lhe- resutts above- relals tq thg lqrnthi tE!t]q+

4 dlE IEi6'i.i""'"gi +-,ip;pOui.,i'r ni-n o. r, tjl:w-}hp. )tI tl*.wrineq, peroriFsio&€drc. htoo EEEL (re6* er6r.r, *cv.

PaEe 2 of,

g.E

.EEJ<3

lo-4420

77,L2.20L4 150 2A

20,12.2018

31

6.L2.2074 26

75

s7

ci--

CENTRAL MINE PLANNING AND DESIGN INSTITUTE LIMITEDEnvironment Laboratory, Regional lnstitute-V,

Phone: (07E'15) 271646, email: [email protected],

website: ltiwvv. cmpdi. co. in

cmpdiA Mini-Rqtna

ComNny

Month DECEMBER Area GEVRA Report No KSM/2or8/ t2l02

South Eastern Coalfields Ltd, Bilaspur Date of lssue 15.02.2019

Name ot the Project GEVRA OC Sample Reference No.

Paramet€r SPM PMlO so2 N02

Remarks

.E+,: -t-.Et

L

lndurtri.lzo e -(G.S.R. r42(E),

dated 25.9.2mO)

A-O 500 120 120

A-N 500 250 720 720

Residentlal zone-(G.S.R. 826(E),

dated 16.U.2Ur9 and GSR 176 (E),

02.04.lqr)B 2m 100 60 80 80

Method of analysis

r95182

PART

4:2005

ts 5182

PART

23:2006

CPCB Vol'

l, 2013

195182

PART

22@1

t95182

PART

6t2m6

Unc€rtainty Range (in [&/m3) 119.04 10.0687 !0.4420

Strtlon Name

(codel

Station

cateSory

Date of

samPling

Date ofanalysis

s-Gobarghora

Vill{rB

o7.12,2014 11.12.2014 156 76 45 25 z3

11.12.2018 14.12.2014 t24 84 3A 30 30

14.12.2018 18.12,2018 169 az 4a 30 26

18.12.2018 zL-L2.2074 L70 81 37 36

2t.r2.20L4 173 a2 48 29 t2

143 38 27 25

2A.72.201A 01.01,2019 L7t 77 30 26

6-fiher plantGevra

oc

06.12.2018 09.12.2018 411 253 4a u) 29

10.12.2018 13.12.2018 52 48 32

13.72,2014 L7.r2-ZOlA t14 184 51 34 20

17.12.2014 20.12.2018 519 249 50 55 70

20,L2.20L4 24.L2,2014 2M 114 43 30 24

24,72,20L4 27,L2.20L4 224 119 40 27 26

27.72.2014 31.12,2018 453 233 50 27

D*Checked by Lab ln charseAnalyzed by

!lc_!!:1lfliE !C_!!ll!! abgre.elet! to th. samples tested.

ll Thiq rBmrt canalqf be repfoduEed in part or full without the written permission of the HOO {Env}, CMPOI Eilaspur, Rl-V

Page 3 of 3

AIR QUALITY REPORT

Name of the Customer

5-6

PM2.5

300

42

25.12.2018

25.12,2018 28.12.2018 67

A-O

'108256

27

s)-

CENTRAL MINE PLANNING AND DESIGN INSTITUTE LIMITED

Environment Laboratory, Regional lnstitute-V,

Phone: (07815) 271646. email: [email protected],

website: www.cmPdi.co.in

ar,t/;A H;*Pl*.e

Aa.r.lr4,l

AIR QUATITY REPORT

Month ]ANUARY Area GEVRA Report No KSMl20L8/0r/02

Name of the Customer South Eastern Coalfields Ltd, Bilaspur Date of lssue 15.02.2019

Name of the Proiect GEVRA OC Sample Reference No. 7-2

so2 NO2PMlOSPM

120600 300A-O

120120s00 250A-N

lndustrial zone -(G.S.R. 742(E),

dated 25.9.2000)

80 80200 100 60B

.E+

Residential zone-(G.s.R. 826(E),

dated 16.11.2009 and GSR 175 {E),

02.04.1996)rs 5182

2:2001.

rs,5182

6:2005

rs-5182

PART

23:2m6

ts-5182

4r2005Method oI analysis

lo.4420

Remarks

10.0687119.04Uncertainty Range (in Fg,/m3)

Date of

analysis

Station

category

oate of

sampling

Station Name

(code)

4685 5102.01.2019 04.01.2019 170

2a 18150 76 4304.01.2019 08.01.2019

29155 78 4908.01_2019 11.01.2019

19487211.01.2019

36 2149t70 8018.01.2019

33 2277 5122.O1.201918.01.2019

2l47158 7422.01.2019 24.01.2019

2550 27156

3046 311a

B

29.01.2019 31.01.2019

1-Rohina Village

40 48438501.01.2019 03.01.2019

28 22164 8307.01.2019

3610.01.2019 155 74

207a 4510.01.2019 14.01.2019 164

313816614.01.2019 17.01.2019

182182 4321.01.2019 15817.01.2019

6247 61151 7021.01.2019 23.01.2019

1945160 742t.01.2019

31 3050158 7828.01.2019 31.01.2019

2-Kapatmura

Village

B

+)*gAnaly zed by ecked bv La b In charse

Note: 1)The results above relate to the samples tested.

2) This report cannot be reproduced in part or fuil without the writlen permission of the HoD (Env), cMPDI Bilaspur, Rl'v

PaBe 1of 3

PM2.5Parameter

720

CPCB Vol

t,2013

2515.01.2019

15.01.2019

162

8024.01.2019 29.01.2019

L72

4803.01.2019

07.01.2019

2080

28.01.2019

CENTRAL MINE PLANNING AND DESIGN INSTITUTE LIMITED

Environment Laboratory, Regional lnstitute-V,

Phone: (0781 5) 271646, email: [email protected],

website: www.cmPdi.co.in

cr,t/;,4 ht*P4z*

Cor.fir.l

AIR QUALITY REPORT

Month JANUARY Area Report No KSMl2078l01-/02

Name of the Customer South Eastern Coalfields Ltd, Bilaspur Date of lssue 1s.02.2019

Name of the Project GEVRA OC Sample Reference No. 3,4

Parameter SPM PMlO PM2.5 so2 NO2

Remarks

.g<lnduetrial zone -(G.S.R. 742(E),

dated 25.9.2000)

A-O 600 300 L20 120

A.N 500 250 120 120

Residential zone-(G.s.R. 826(E),

dated 16.11.2009 and GSR 176 (E),

02.04.1996)

B 200 100 80 80

Method of analysis

r5,5182

4:2005

ts-5182

23r2006

CPCB Vol-

r,2013

rs-5182

2t2OO1

rs-5182

6:2006

Uncertainty Range (in B&/m3) !19 04 r0.4420

Station Name

(code)

Station

category

Date of

sampling

Date of

analysis

3-Katkidabri

Village

B

01.01-2019 03.01.2019 174 a7 48 26

07.01.2019 168 7A 43 2a 26

07.01.2019 10.01.2019 t72 86 50 27 24

10.01.2019 14.01.2019 155 78 48 27

14.01.2019 168 49 30 23

17.01.2019 21.01.2019 162 72 46 29 26

21.01.2019 23.01.2019 11 50 31 25

23.01.2019 28.01.2019 t64 77 45 28 26

28.01.2019 168 82 32

B

03.01.2019 165 83 51 35 21

03.01.2019 07.01.2019 170 82 4S 33

07.01.2019 10.01.2019 t72 48 28 19

10.01.2019 14.01.2019 166 75 48 30 29

14-O1.2019 17.01.2019 168 46 36 26

17.01.2019 21.01.2019 157 67 45 38 26

21.01.2019 23.01.2019 16 46 31 21

23.01.2019 28.01.2019 166 84 50

28.01.2019 31.01.2019 148 45 30 28

n'# {yChecked bv Lab ln charge

Note: 1) The results above relate to the samples tested.

2) This report cannot be reproduced in part or fullwithout the written permission ofthe HOD (Env). CMPDI Bilaspur, Rl-V

Page 2 of 3

GEVRA

50

10.0687

26

03.01.2019

72

17.01.2019

158

4331.01.2019

01.01.2019

86

11

39

4-salora village

c-

CENTRAL MINE PLANNING ANO DESIGN INSTITUTE LIMITED

Environment Laboratory, Regional lnstitute-V'

Phone: (0781 5) 271646, email: [email protected],

website: www.cmPdi.co.in

ar^+/;A H:*&z.t

Ca*fry

Month .JA N U ARY Area GEVRA Report No KSM/2078/0Ll02

Parameter SPM PMlO P M2.5 so2 NO2

Remarks

e+"

=E4

lndustrial zone -(G.S.R. 742(E),

dated 25.9.2000)

A-O 300 720 t20

A.N 500 2s0 120 120

Residential Zone-(G.S.R. 825(E),

dated 16.11.2009 and GSR 176 (E),

02.04.1996)

B 200 100 60 80 80

Method ot analysis

rs,5182

4:2005

t5-5182

23:2006

CPCB Vol-

r,2013

ts-5182

2:2001

t5-5182

6:2006

Uncertainty Range (in l.lg/m3) 119.04 !0.0687 10 4420

Station Name

(code)

Station

category

Date of

sampling

Date of

analysis

5-Gobarghora

village

02.01.2019 04.01.2019 158 78 48 20 26

04.01.2019 08.01.2019 112 84 51 30 27

08.01.2019 11.01.2019 175 85 52 33 29

11.01.2019 15.01.2019 7S 48 18

15.01.2019 18.01.2019 80 28

18.01.2019 22.01.2019 164 70 51 33

22.OL.2019 24.O1.20L9 158 72 30

24.OL.2019 29.01.2019 4S 25

29.01.2019 31.01.2019 164 70 43 31

6-Filter

plant,Gevra OC

A-O

02.01.2019 04.01.2019 378 158 A3 14 20

04.01.2019 08.01.2019 451 256 41

08.01,2019 11.01.2019 440 260 39 36

11.01.2019 15.01.2019 510 250 52 39 25

15.01.2019 18.01.2019 500 210 45 35 18

18.01.2019 22.01.2019 168 51 18

22.01.2019 24.01.2019 161 50 29

24.O1.2019 29.01.2019 404 164 43 24 24

29.01.2019 31.01.2019 472 159 45 32 31

South Eastern Coalfields Ltd, Bilaspur Date of lssue 15.02.2019

Name of the Proiect GEVRA OC Sample Reference No, 5-6

Ana lyzed by Checked bV Lab ln charge

Page 3 of 3

AIR QUAI.IW REPORT

Name of the Customer

600

B

166 30

47

20

149 67

30

48

28

395 23

Note: liThe resultsabove relate tothe samplestested.

2) This report cannot be reproduced in part or full without the written permission of the HOD (Env), CMPDI Bilaspur, Rl_V.

CENTRAL MINE PLANNING AND DESIGN INSTTTUTE LIMITEDEnvironment Laboratory, Regional lnstitute-V,

Phone: (07E15) 271646, email: [email protected],

website; wvrw.cmpdi.co.in

cm0dA Mini-lotno

Company

AIR OUALITY REPORT

Month FEBRUARY Area G EVRA Report No KSM/2079102/02

Name of the Customer South Eastern Coalfields Ltd, Bilaspur 15.03.2019

,{ame of the Project GEVRA OC Sample Reference No.

Parameter 5PM PMlO PM2.5 so2 NO2

Remarks

lndqrtrirl Zonc {G.S.R, 742(E},

dated 25.9.200,0)

A{ 500 300 120 120

A.N 500 250 120 120

Residential Zone{G.S.R. 826(E},

d.ted 16.u.2009 and GsR 176 (E).

02.04.19!15)

B 200 100 50 80 80

irethod of an.lysl!

195182

4r2005

ts-5182

PART

23:1006

t'5182PAf,T

2:2001

195182

PART

6:2006

Uncertainty RarBc (in [&/m3] 1L9-04 io.0687 i0.4420

Strtlon I{ame

(Code)

Station

cat€gory

Date of

sampllng

Date of

analysis

I

05.02.2019 08.02.2019 t77 84 45 29 34

08,02.2019 11-O2.2019 163 59 41 26 36

13.02.2019 181 46 2t 30

1S.02.2019 19.O2.2019 155 29 25

19.02.2019 22,O2.2079 179 65 43 24 ?4

22.02.2019 25.02.2019 l7? 4L 27 27

28.02,2019 o2.03-2019 t12 84 50 2A

04.03.2019 06.03.2019 154 70 t6 25

2-l(apatmura

Villa8€B

01.02.2019 03.02,2019 159 a4 25

07.02.2019 10.02.2019 L74 7S 49 40 34

12.02.2019 15.02.2019 153 31

l't.02.2019 17.02,2019 L77 7L 44 35 29

16.02.2019 21.02.2019 165 73 47 39 34

27.O2.2019 24.02.2019 L'r7 19 50 26 27

27.O2.?.O19 01.03,2019 99 75 43 3' 32

01.03,2019 04.03.2019 t72 72 48 24 29

al- ,*gT)Analvzed bv Checked La n charce

t'lote: 1) Th€ re3uhs .bove relele to th€ iamplei tested.

2) thi5 report cannot bc rrproduced in pan or fullwithoutthe wrltten p€rmlcslon ofthe HOO (Env), CMPo| Eilaspur, Rl-V

Pate 1 of 3

Date of lssue

e_E

Ei-ECPCB Vol-

1,201|

l-Rohina Village

17.02.2019 74

49

7A

35

4a

a7 !0

7A 42 38

cm0diA Mini-iotna

Compony

AtR QUAI.ITY REPORT

FEBRUARY Area GEVRA Report No KSMl2079/o2l02

t{ame of the Customer South Eastern @alfields [td, Bilaspur Date of lssue

Name of the Project Sample Reference No. 3-4

Parameter PMlO PM2.5 so2 NO2

E,E+rE -!-EE

I

lndurtd.l Zooc {G.S.R 742{EL

d.ted 25.9.2@o)

A-O 600 300 120 120

A.N soo 250 120

R6ldentlal Zone{G.S.R. 826{E),

dated 15.u.2009 and GsR 176 (C),

02.04.1995)

B 200 100 60 80 80

Mlthod ofanaly5ls

t95182

4:2mS

195182

PART

23:2005

CPCB vol"

r,2013

r's182PARI

6:2m6

Uncertalnty RarEc {ln I&/m!} i19.0rl 10.0687 tO.{420

Statlon Name

(codllStatlon

category

D.t€ olsamplin!

Date of

analysi:

:t-l6tlid!brlVlll.ge

B

01.02.2019 03.02.2019 82 /u) 29

o7,o2.20t9 10.o2.2019 774 7A 49 36

12.02.2019 15,02.2019 158 76 41 38 42

14.02.2019 tl.02.2019 170 74 z7 35

18.02.2019 2L,O2,20t9 L66 79 49 25 fo

24,02.2079 774 77 u) t6 37

25.02.2019 01.03.2019 L'I 76 /la ?, ?,

28-02.2019 03,03.2019 71 al 31 34

&Salore Vill.ScB

o1.02_2019 03.02.2019 170 58 s0 21 34

07.02.2019 10.02.2019 166 74 4l 31

a2.o2.20t9 L74 49 29 27

14.02,2019 71,02,2019 175 ,0 45 31 36

18.02.2019 21.0?.2019 772 75 46 27 25

21.02.2019 24.02.2019 169 79 43 36 38

26.02.2019 01.03,2019 t7 73 49 2A 3r

28.02.2019 03,03,2019 179 13 44 33 t7

"*&Analvzed bv Checked bv Lab n charse

Nole: U Th€ re3uhi abov€ relate to th€ semplct tested-

2) this rcpon cannot b€ reproduced in part or full without the written permission ofthe HOO (Env), CMPOI Eilaspur. Rl-V.

Page 2 of 3

CENTRAL MINE PLANNING AND DESIGN INSTITUTE LIMITEDEnvironment Laborstory, Regional lnstituleV,

Phons: (0781 5) 271&6, email: [email protected]'

rvebsite: www.cmpdi.co.in

Month

15.03.2019

GEVRA OC

SPM

Remarks

120

r!5182PART

2:2001

160 44

31

45

21.O2.2|JL9

169

25

15.02.2019 1a

c-

CENTRAL MINE PLANNING AND DESIGN INSTITUTE LIMITEDEnvironment Laboratory, Regional lnstitute-V,

Phone: (07815) 271646, emaitr E[i5Etrp9!i@s[!E!aI,website: www.cmpdi.co. in

cm0diA Mini-fiotno

Compqny

AIR OUALIW REPORT

Month FEBRUARY Area GEVRA Report No KsMl2OL9/o2l02

t{ame of the Customer south Eastern coalfields Ltd, Eilaspur Date of lssue 15.03.2019

l{ame of the ProJect GEVRA OC Sample Reference No. 5-5

Parameter SPM PMIO PM2.5 NO2

Eac? El5t

A.o 600 120

A.N 5@ 250 120 720

Rlddential Zon€{G,S,R. 825{E},

dated 15.11.2qx, and GSR 176 (E!,

02.04.r9{r}

200 100 60 80 80

M.thod ot analysis

rs-5182

PART

4:2mS

rs-5182

PART

23:2005

CPCBvol-

t,2011

ts,5182

PART

2r2m1

rs-5182

PART

6:2m6

Unccrtainty RanS€ 0n Fgilmr) r19.04 r0.0687 19.4420

Statlon Name(codG)

Date ofsampllng

Date olanalysls

reob8r8hora

WlageB

05,02.2019 08,02.2019 1,la 69 45 2A 35

08,02.201' 11.02.2019 7S 49 36 33

13,O2,2019 17.02,2019 777 ,r 41 29

15.02.2019 19.02.2019 L7L 7A 44 32 3'

19.02.2019 22.07.,2079 168 50 40 35

22.02,2079 23.02.2079 rr3 66 44 39 30

27,02,2019 01.03.2019 179 65 40 rl4 27

01.03.2019 04,o3,2079 155 77 47 29 33

6+llterplant Gavra Oc

a-o

01.02,2019 03.02.2019 400 43 45

o7,o2.20a9 10.02.2019 393 198 c3 41 35

12.02.2019 450 202 49 l7

14.02.2019 17.02,2019 230 53 42 44

19.02.2019 2!,O2,2079 5L2 191 42 49 45

72.02.2079 ?4.O2.2D19 4t! 775 47 t9

01,03.2019 496 L79 48 43

o1.03.2019 357 205 49 35

Dg

Analvzed bv Checked Lab ln charae

l,lotE: ll The relfh! tqeyB rthlq tc the EqmFlE! tErtfC.

it mis ffegn raqqgr Fe reArqdqccd in part or fullwhhout thc *rmen permiEron etthe HOE (Env), eMFol Bilaspur, Rl-v.

PaSe 3 of 3

so2

Remark

lndurtrlal zone {6.s.k 7 42lEl,

dated 2s.9.2000)

300 120

B

Station

cateSory

,7

7t

29

1s.02.2019 46

414

49

27.02,20L9 t7

04.03.2019 49

d-

EXECUTIVE SUMMARY OF AIR QUALITY OF BASELINE

DATA GENERATION OF GEVRA OC EXPANSION PROJECT

PERIOD OF BASELINE DATA GENERATION: APRIL-JUNE, 2019

DONE BY: M/s Head Office & Lab: Dayal Estate,

National Highway No. 8, Opp. APMC Market Gate – 1, Jetalpur, Ahmedabad – 382426.(NABL accredited/MoEFCC recognized lab)

Suspended Particulate Matter

Site Minimum Maximum Average 98 Percentile GSR 742 (E)

Gevra Filter Plant 153.6 215.6 178.0 198.5 600

Korai Village 123.5 168.0 146.3 163.0 600

Dadarpara Village 123.5 169.5 151.4 169.5 600

Purena Village 123.0 173.2 145.5 167.2 600

Salora Village 128.0 190.4 156.8 182.5 600

Chhindpur Village 124.0 186.5 162.7 186.3 600

Rampur Village 113.8 192.5 148.6 182.4 600

Birda Village 118.9 165.9 145.5 165.9 600

Gevra Workshop 121.0 216.5 172.5 206.5 600

Saraisingar Village 135.2 197.5 168.9 197.2 600

Binjhri Village 101.2 186.0 140.9 185.0 600

Particulate Matter (PM10)

Site Minimum Maximum Average 98 Percentile GSR 826 (E) GSR 742 (E)

Gevra Filter Plant 76.0 114.2 90.2 112.5 100 250

Korai Village 62.5 80.5 73.7 80.4 100 250

Dadarpara Village 69.5 85.7 79.4 85.1 100 250

Purena Village 59.5 87.9 71.7 86.3 100 250

Salora Village 62.2 90.2 78.0 90.2 100 250

Chhindpur Village 63.9 83.5 75.6 82.6 100 250

Rampur Village 49.5 90.4 73.2 86.8 100 250

Birda Village 59.5 82.5 72.8 82.5 100 250

Gevra Workshop 70.5 106.5 89.2 103.2 100 250

Saraisingar Village 74.5 85.6 80.5 85.4 100 250

Binjhri Village 54.2 94.5 78.5 89.4 100 250

Particulate Matter (PM2.5)

Site Minimum Maximum Average 98 Percentile GSR 826 (E)

Gevra Filter Plant 40.2 59.5 48.5 56.3 60

Korai Village 21.5 41.2 28.7 40.2 60

Dadarpara Village 28.5 42.1 36.3 41.6 60

Purena Village 17.4 42.5 29.2 40.9 60

Salora Village 26.0 52.1 38.5 50.1 60

Chhindpur Village 21.5 42.1 30.3 41.5 60

Rampur Village 21.5 52.1 31.6 42.6 60

Birda Village 19.5 43.2 29.4 42.5 60

Gevra Workshop 32.5 60.2 48.3 59.5 60

Saraisingar Village 34.2 43.1 38.9 42.3 60

Binjhri Village 26.5 73.8 37.9 41.9 60

Sulphur Dioxide (SO2)

Site Minimum Maximum Average 98 Percentile GSR 826 (E) GSR 742 (E)

Gevra Filter Plant 26.9 47.1 39.2 46.7 80 120

Korai Village 13.2 30.2 22.4 28.4 80 120

Dadarpara Village 18.5 40.4 29.4 39.5 80 120

Purena Village 12.6 29.6 19.3 26.5 80 120

Salora Village 20.1 39.1 26.1 38.5 80 120

Chhindpur Village 16.9 32.4 24.4 31.4 80 120

Rampur Village 9.5 32.5 18.4 30.0 80 120

Birda Village 14.5 29.5 20.7 28.7 80 120

Gevra Workshop 19.7 44.1 34.3 43.3 80 120

Saraisingar Village 17.3 30.7 26.1 29.8 80 120

Binjhri Village 21.4 29.9 26.4 29.7 80 120

Oxides of Nitrogen (NOx)

Site Minimum Maximum Average 98 Percentile GSR 826 (E) GSR 742 (E)

Gevra Filter Plant 21.6 36.2 30.2 36.2 80 120

Korai Village 9.5 22.6 15.2 21.5 80 120

Dadarpara Village 13.7 26.5 20.4 26.5 80 120

Purena Village 8.5 19.5 13.2 19.5 80 120

Salora Village 16.5 28.5 20.2 26.5 80 120

Chhindpur Village 12.6 25.6 18.1 23.4 80 120

Rampur Village 7.9 14.9 11.7 14.9 80 120

Birda Village 10.5 20.1 14.0 19.5 80 120

Gevra Workshop 12.5 38.4 23.3 32.7 80 120

Saraisingar Village 12.4 26.5 19.4 25.1 80 120

Binjhri Village 16.5 22.5 19.5 22.3 80 120

From all the above graphical representation it is clearly interpreted that all the values of SPM, PM10, PM2.5,

SO2 and NOX were lower than the prescribed limits for all the stated locations. As per the standards for coal

mines, GSR 742 (E) dated 25th September 2000, the concentration of SPM at all the location was found to

be lower than the prescribed limit i.e. 600 µg/m3 for the entire study period. In case of PM10 and PM2.5, the

concentration was within the limits proposed in the standards GSR 826(E) dated 16th November 2009 of

MoEF. The concentration of SO2 and NOx for all the locations is within the prescribed limits.

AAQM RESULTS FOR HEAVY METALS, BENZENE, CO, O3, NH3 AND BAP

In this study, we also monitored some other critical pollutants like Ozone, Ammonia, Lead & CO to assess the existing levels of air pollutants as well as the regional background concentration of the cluster area.

Beside these, some Heavy metal concentration in the ambient air were also monitored in and around the project area. The following tabulated pollutants were monitored once in a month.

Location Sampling

Month O3 NH3 CO C6H6 As BAP Cd Cr Pb Hg NI

Unit µg/m3 µg/m3 mg/m3 µg/m3 ng/m3 ng/m3 ng/m3 ng/m3 µg/m3 ng/m3 ng/m3

Limits as per GSR 826 Standard

180 400 4 5 6 1 - - 1 - 20

Gevra Filter

plant

April’19 BQL 12.1 0.84 BQL BQL BQL 0.5 BQL BQL 1.4 BQL May’19 BQL 7.7 0.88 BQL BQL BQL 0.8 BQL BQL 2.5 BQL

June’19 BQL 8.6 0.88 BQL BQL BQL 0.3 BQL BQL 1.5 BQL

Korai village April’19 BQL 8.6 0.81 BQL BQL BQL 0.7 BQL BQL BQL BQL May’19 BQL 11.5 0.81 BQL BQL BQL 0.3 BQL BQL BQL BQL

June’19 BQL 10.8 0.9 BQL BQL BQL 0.8 BQL BQL BQL BQL

Dadarpara Village

April’19 BQL 15.1 0.85 BQL BQL BQL 0.9 BQL BQL BQL BQL

May’19 BQL 13.4 0.82 BQL BQL BQL 0.4 BQL BQL BQL BQL June’19 BQL 13.8 0.85 BQL BQL BQL 0.6 BQL BQL BQL BQL

Purena

Village

April’19 BQL 12.1 0.79 BQL BQL BQL 0.3 BQL BQL BQL BQL

May’19 BQL 15.1 0.77 BQL BQL BQL 0.6 BQL BQL BQL BQL June’19 BQL 15.7 0.71 BQL BQL BQL 0.4 BQL BQL BQL BQL

Salora village April’19 BQL 15.5 0.9 BQL BQL BQL 0.5 BQL BQL 1.1 BQL May’19 BQL 19.4 0.85 BQL BQL BQL 0.7 BQL BQL 1.2 BQL

June’19 BQL 17.2 0.83 BQL BQL BQL 0.7 BQL BQL 1.5 BQL

Chhindpur Village

April’19 BQL BQL 0.84 BQL BQL BQL 1.6 BQL BQL BQL BQL May’19 BQL BQL 0.8 BQL BQL BQL 1.5 BQL BQL BQL BQL

June’19 BQL BQL 0.86 BQL BQL BQL 1.5 BQL BQL BQL BQL

Rampur Village

April’19 BQL 19.1 0.82 BQL BQL BQL 3.4 BQL BQL BQL BQL

May’19 BQL 11.5 0.86 BQL BQL BQL 3.7 BQL BQL BQL BQL June’19 BQL 13.4 0.89 BQL BQL BQL 3.9 BQL BQL BQL BQL

Birda Village

April’19 BQL BQL 0.84 BQL BQL BQL 2.9 BQL BQL BQL BQL

May’19 BQL BQL 0.81 BQL BQL BQL 3.1 BQL BQL BQL BQL June’19 BQL BQL 0.85 BQL BQL BQL 3.1 BQL BQL BQL BQL

Gevra

workshop

April’19 BQL BQL 0.94 BQL BQL BQL 5.1 BQL BQL 1.7 BQL May’19 BQL BQL 0.95 BQL BQL BQL 5.1 BQL 0.1 1.4 BQL

June’19 BQL BQL 0.91 BQL BQL BQL 5.2 BQL BQL 1.9 BQL

Saraisingar Village

April’19 BQL BQL 0.87 BQL BQL BQL 1.6 BQL BQL BQL BQL

May’19 BQL BQL 0.81 BQL BQL BQL 1.8 BQL BQL BQL BQL

June’19 BQL BQL 0.87 BQL BQL BQL 1.4 BQL BQL BQL BQL

Binjhri Village April’19 BQL 7.7 0.85 BQL BQL BQL 0.7 BQL BQL BQL BQL

May’19 BQL 9.6 0.84 BQL BQL BQL 0.4 BQL BQL BQL BQL

June’19 BQL 9.6 0.88 BQL BQL BQL 0.9 BQL BQL BQL BQL

From the above tabulated results it is concluded that the concentration of the said pollutants are within the

prescribed limits.

Remark: The above data for Saraisingar Village and Binjhri Village has been taken from the results of

ambient air monitoring conducted for Dipka OC Expansion Project.

Note: BQL= Below Quantification Limit. The Quantification Limit (QL) of various parameters is as follows:

Parameter Quantification Limit (QL)

Ozone (O3) 20 µg/m3

Ammonia (NH3) 5 µg/m3 Benzene 0.1 µg/m3

Arsenic 1.0 ng/m3 Benzo(α)Pyrene 1.0 ng/m3

Cadmium 0.2 ng/m3 Chromium 0.7 ng/m3

Lead 0.1 µg/m3

Mercury 0.02 µg/m3 Nickel 1.0 ng/m3

ANNEX viii

SAL PLANTATION