SIA/RAP Gujarat State Disaster Management Authority
-
Upload
khangminh22 -
Category
Documents
-
view
1 -
download
0
Transcript of SIA/RAP Gujarat State Disaster Management Authority
Consultancy Services for Conducting Environment Impact Assessment (EIA), Social Impact Assessment (SIA) And Preparation of Environment Management Plan (EMP) & Resettlement Plans for Underground
Electrical Cabling Works at Gandhidham and Adipur Cities Of Kutch District, Gujarat
Executive Summary – SIA/RAP
Gujarat State Disaster Management Authority
December 2018
Submitted by:
HaskoningDHV Consulting Pvt. Ltd. Green Boulevard, Plot B 9A, Tower B, 4th Floor, Sector 62, Noida - 201301, India
T +91 120 4016100, F +91 120 4260165, Email: [email protected]
SIAandRAPforUndergroundElectricalCablingWorksatGandhidhamandAdipurcitiesofKutchdistrict,Gujarat
E‐2 FinalSocialImpactAssessmentReport&RAP
ExecutiveSummary
1.0 Background
The"NationalCycloneRiskMitigationProject"(NCRMPII)isbeingimplementedbytheNationalDisasterManagement Authority (NDMA) with support from theMinistryofHomeAffairs(MHA),GoI.ItincludesstatesofGujarat,Maharashtra,Kerala,KarnatakaandGoaon thewestcoastandWestBengalontheeastcoast.Theprojectseekstoachieveitsobjectivesbyundertakingstructuralandnon‐structuralmeasuresunderitsfourmainprojectcomponents:
A. EarlywarningDisseminationSystemsB. CycloneRiskMitigationInfrastructureC. TechnicalAssistanceforMulti‐HazardRiskManagementandD. ProjectManagementandImplementationSupport
TheGujaratDisasterManagementAuthority(GSDMA)isthenodalagencyfortheimplementationoftheNCRMPIIprojectinGujarat.
2.0 Sub‐Project
The sub‐project “underground electricalcabling works at Gandhidham and Adipurcities of Kutch district, Gujarat” is coveredunder sub‐component B1 (Cyclone RiskMitigation Infrastructure in Gujarat) ofComponent B (Cyclone Risk MitigationInfrastructure),NCRMPII.
The impact of climate change hazards &naturalcalamitiesisthreateningtheeconomicgrowth of the State and is alsodisproportionately affecting the vulnerablewhoareleastequippedwiththeresourcestoadapttochangingconditions.Inthepast,GandhidhamandAdipurcitieswereseverlyaffectedby:
the cyclonic storm that made landfall onthecoastofKandla(Kutch)nearthecityofGandhidhamonJune09,1998.Atthetimeoflandfall,theestimatedmaximumsustainedsurfacewindspeedassociatedwiththecyclonewasabout180‐220kmphandheightofthewavesupto6meters.ThetidegaugeatKandlareportedmaximumstormsurgeof1.5metersabovetheastronomicaltide.Thedeathtollfromthecyclonewasabout10000.
asevereearthquake(onJanuary26,2001)thatmeasured7.9onrichterscale.TheepicenterbeingBhachau(kutch),Gandhidham&Adipurandtheentirekutchregionfacedtremendouslossofhumanlives&infrastructure.Thedeathtollwasabout60000.
ProjectDevelopmentObjective(PDO)
To reduce vulnerability to cyclones andother hydro‐meteorological hazards ofcoastal communities in project states andincreasethecapacityoftheStateentitiestoeffectivelyplanforandrespondtodisasters.
Sub‐projectLocation‐Gandhidham&Adipur,Kutch,Gujarat
SIAandRAPforUndergroundElectricalCablingWorksatGandhidhamandAdipurcitiesofKutchdistrict,Gujarat
E‐3 FinalSocialImpactAssessmentReport&RAP
These cyclone& earthquake caused extensive devastation in all the affected districts, uprooting vastnumberoftrees,damagingroads,publicbuildings,livelihoodsanddisruptingtelecommunicationsandpowerinfrastructure.TheNeedistomoveforwardtowardsaresilientinfrastructurethatcanserveasafoundationforgrowthandeconomicdevelopmentofGandhidham‐Adipurcitiesandhelpbuilddisasterresilient‐communitiesthus,ensuringdevelopmentbenefitsoverthelongerterm.TherobustnessofUGelectricalnetworktotheeffectsofhighspeedcyclonicwindgustwhencomparedtotheoverheadelectricalsystemmakesitamoreviablechoicewhenprovidingasafeenvironmentinallaspects.This sub‐project ispartof apackage to supportGovernmentofGujarat (GOG) for reconstructionandrecovery efforts and to strengthen its capacity tomanage future disasters. Hence, the conversion ofexistingoverheadHT<electricallinesintoundergroundelectricalcablingnetworkhasbeenproposedinGandhidhamandAdipurcitiesofKutchdistricttoprovidearesilientinfrastructurethatcanwithstandnatural disaters like cyclones. The underground electrical cablingworkswill be implemented by thePaschimGujaratVijCompanyLtd(PGVCL).SignificantfeaturesofanUndergroundElectricalCablingnetworkare:
Resilientinfrastructure‐Itissafertopubliclivesandpropertyparticularlyofvulnerablesectionsof society, during calamities/disasters/thunders/lightening instances, reduces risk of vehicularaccidents,electrocutionsetc.
Reliable‐Effectiveandreliablealternativetooverheadlinesduetoreal‐timemonitoring,lowwearandtearrisk,reducedoutages(abouthalfoftheirequivalentoverheadnetworks),etc.
Low carbon footprint & energy savings‐ Approx. 30% lower power losses in comparison tooverheadlinesathighcircuitloads.ImprovedsystemefficiencyinUGcables,loweringgreenhousegasemissionsandenergysavings.
Safeandaesthetic‐UGcablenetworkenhancesthevisualsoftheareawhichimprovesaesthetics,higherpublicacceptanceandconveyenvironmentalbenefits.Also,itreducesthevehicularaccidentrisksduetoremovalofHTandLTpolesalongtheroadside.
KeyBenefitsofUndergroundingtheexistingoverheadelectricalnetworkare:
Allareascoveredunderthisprojectwillensuretopracticallyremainunaffectedinfuturefrompowerdisruptions and associated implications during or after cyclone/high winds or naturalcalamities/extreme weather conditions, hence, resilient to natural disasters, the main projectdevelopmentobjectiveofUGcablingprojectcomponentunderNCRMPII.
UGcableshave lowertransmissionlossesandcanabsorbemergencypower loads.UGcableshavelowermaintenancecostsandemitnoelectricfieldandcanbeengineeredtoemitalowermagneticfieldthananoverheadline.
Whiletheupfrontinvestmentrequiredforanundergroundcabledistributionsystemishigher,therecurringexpensesarelowerandthereforeafairfinancialcomparisonwithoverheadlinesshouldconsidertheNPVofbothtypesofcostsoveralongplanningperiode.g.25to30years.Inmostcases,undergroundcablingturnsouttobecosteffectiveinafinancialsense.
ItisanestablishedfactthatUGCablenetworkwilllowerthetransmissionlosses,whichwillresultinenergy saving and subsequently reduction in green house gases (GHG) for generation of savedenergy/electricityforUGCablenetwork.
UGcablesarenotaffectedbymomentaryinterruptionsasoccurringfromlightningandfallingoftreebranchesonoverheadlines,whichde‐energizeandthenre‐energizethecircuitmomentlater,amostcommonfeatureinoverheadlines.
SIAandRAPforUndergroundElectricalCablingWorksatGandhidhamandAdipurcitiesofKutchdistrict,Gujarat
E‐4 FinalSocialImpactAssessmentReport&RAP
Itwillsubstantiallyconservestate’sresourcesrequiredduringre‐constructionofdamagedelectricalnetworkafterthedevastationcausedbyacycloneandothernaturaldisasters.
3.0 ObjectivesoftheAssignment
TheoverallobjectiveoftheprojectistocarryoutSocialImpactAssessment(SIA)oftheproposedprojectandtoidentifyadversesocialimpacts;preparecommensurateResettlementActionplantomitigatetheimpactsthatarelikelytoariseduetoimplementationoftheproposedsub‐projectandensurethattheproposedworksaredesignedandconstructedinlinewiththeregregulationsmadeofGovernmentofIndiaandGovernmentofGujarat.Thespecificobjectivesoftheassignmentareasbelow:
Toassessthesocial impactsandissues in linewiththeover‐allguidancegivenundertheproject’sapprovedEnvironmentalandSocialManagementFramework(ESMF).
To prepare a baseline/existing conditions; analysis of data/information; consultations withstakeholdersand;assessmentofimpacts,includinganyalternativesthatcanhelpavoid/minimizetheidentifiedimpacts.
Toreviewandverifytheadequacyofexistingsystem/practicesforapplicationofrelevantsafeguardprocedures and practices, and adherence to various applicable regulations/rules and guidelinesdetailedoutintheESMF.
Preparation of relevant/comprehensive sub‐project specific SIA and RAP, including resettlementbudgetforimplementationofRAP.
4.0 Approach&SIAMethodology
Ourapproachfollowsagoal‐orientedmethodology,whereinthesocialimpactassessmentwascarriedoutinclosecoordinationwithtechnical/engineeringteamofPGVCL.Therewereintensiveconsultationswithvariousstakeholdersforprovidingnecessary inputstothestudy.Themethodologyforthestudyincludedthefollowing:
Desk‐BasedAssessment
ReconnaissanceSurveys
SocialScreening
CensusSurvey
Socio‐EconomicSurvey
TransectWalk
Videography&Photography
StakeholdersEngagement
5.0 Legalframework
Thisdealswiththeapplicableacts,notifications,guidelinesandpoliciesincontextoftheundergroundelectrical cabling works at Gandhidham and Adipur cities. The ESMF has been prepared as perGovernmentofIndiaandWorldBank’sOperationPoliciesforSocialandEnvironmentalSafeguards.ThePaschimGuajaratVijCompanyLtd(PGVCL– implementingagency)willensurecomplianceof legalandregulatoryframeworkduringtheprojectcycle.SafeguardpoliciesoftheWorldBankrelevanttotheproposedUGelectricalcableprojectare:
IndigenousPeoples(referredastribalinIndiancontext)(OP/BP4.10):Thepolicyunderscorestheneedtoidentifyindigenouspeoples,consultwiththem,ensurethattheyparticipatein,andbenefit
SIAandRAPforUndergroundElectricalCablingWorksatGandhidhamandAdipurcitiesofKutchdistrict,Gujarat
E‐5 FinalSocialImpactAssessmentReport&RAP
fromBank‐fundedoperationsinaculturallyappropriateway‐andthatadverseimpactsonthemareavoided,orwherenotfeasible,minimizedormitigated.Basedonsitevisits,initialconsultationswithstakeholdersandlocalpeoplenospecificlocalityorareawithinthecitywheretribalpopulationwithdistinctsocio‐culturalidentityvis‐à‐visthemainstreampopulationhavebeenreported.Thesocio‐economic survey also confirms non‐availability of tribal habitations with unique socio‐culturalidentityinGandhidhamandAdipurcities.AssuchOP4.10isnottriggered.
InvoluntaryResettlement(OP4.12):Policyisintendedtoensurethataffectedpersonsareassistedintheireffortstoimprovetheirlivelihoodsandstandardsoflivingoratleasttorestorethem,inrealterms,topre‐impactlevelsortolevelsprevailingpriortothebeginningofprojectimplementation,whicheverishigher.Thispolicyistriggeredastheproposedsub‐projectimplementationislikelytoimpact encroachers and squatters along the proposed electrical cabling route particularly, incongestedareasandmayleadtolossofshelter,access,ramp,platform,sourcesoflivelihood,etc.TheabovepolicyisthusapplicableandadverseimpactswouldbemitigatedasperentitlementscoveredinESMFofNCRMPII..
TheNationalLegalandRegulatoryCompliancesActs,guidelines,lawsandpoliciespertainingtothisprojectare:
TheRighttoFairCompensationandTransparencyinLandAcquisition&RehabilitationandResettlementAct2013(Act30of2013)&TheRighttoFairCompensationandTransparencyinLandAcquisitionandRehabilitationandResettlement(GujaratAmendment)Act,2016(Act12of2016):Notapplicableasthelandacquisitionisnotproposedinthissub‐projecttherefore,theprovisionsofthisAct(compensationandR&RassistanceasperFirst&SecondSchedule)willnotapply unless otherwise requirement of additional land is necessitated during the time ofimplementation.
GovernmentofGujarat (ResolutionNoLAQ22‐2014/179/GH)dated10/11/2016:Notapplicableastheaboveresolutionwillapplyonlywhenlandacquisitionisproposed,whichisnotthecasewiththesub‐project.
TheRighttoInformationAct,2005:Applicableasundertheprovisionsofthis citizensmayseekinformationbyfollowingdueprocedureinordertopromotetransparencyandaccountabilityintheworkingofthepublicauthorities.
Resettlement and Rehabilitation Principles: Applicable as the sub‐project activities involveadverse impacts on land, structure, livelihood and other assets and hence, a Resettlement PolicyFramework has been formulated to lay down the principles and procedures for social impactassessmentandpreparationofResettlementActionPlan
EntitlementMatrix:TheentitlementmatrixforNCRMPIIhasbeenpreparedinaccordancewiththeCentral & State Acts andWorld Bank Operational Policies 4.12 & 4.10 dealing with involuntaryresettlementandindigenouspeopleforprojectsacrossparticipatingstates.ThePAPswillbeeligibleforacombinationofcompensationandassistancemeasuresdependinguponthenatureofownershiprights of lost assets, type of impact and their socio‐economic status. The GSDMA and PGVCL(executingagency)willensurecomplianceofentitlementmatrix.
VoluntaryLandDonation: Incaseof landrequirement in futureprovisionhasbeenmade intheESMFforvoluntarydonationoflandbydifferententities(individuallandowners,GramPanchayats,trust,religiousinstitutions,temples,etc)
6.0 ProjectDescription
Thesub‐projectisspreadacrossanareaof36.6sq.kmcoveringapopulationofapproximately0.3millionasperCensus2011.TheExistingOHElectricalNetworkinGandhidham‐Adipurhastwosub‐stations:
SIAandRAPforUndergroundElectricalCablingWorksatGandhidhamandAdipurcitiesofKutchdistrict,Gujarat
E‐6 FinalSocialImpactAssessmentReport&RAP
Sub‐station1:66kVGandhidham‐2substation,coveringSadhuVasvani,Gopalpuri,BharatNagarandSunderpuri11kVFeederswhichisdistributedoveranlengthof362.54KmsinGandhidham&AdipurCities
Sub‐station2: 66 kVKFTZ substation coveringGandhidham,NewGandhidham‐2, Lilashah,NewLilashah‐2,Jhulelal,KERF,Jagjivan,Ganeshnagar,Aerodram,Gurukul,Adipur,DC5, NewGJ11kVFeeders
PGVCListheImplementationagencyfortheproposedUGelectricalcablingnetworkwithinGandhidham&AdipurCities.Thetotalprojectcostisestimatedtobe161.71crores,implementationperiodbeing18monthsaftertheawardofwork.SalientfeaturesoftheproposedUGelectricalnetworkasperDPRpreparedbyPGVCLare:
Undergroundelectricalcablingnetwork(hightension&lowtension)coversalengthof430.74KmsinGandhidhamandAdipurcities.LengthofHTCablelayingisapproximately164.74KmsandofLTCablelayingisapproximately266Kms
GandhidhamandAdipurwillbefedfromseventeen11kVfeedersemanatingfromtwo66KVsub‐stations.
Provisionofthreenewadditional11kVfeedersnamely,NewGandhidham,NewLilashah,NewGJforbalancedloadsharingamongthe11kVfeedersofGandhidhamsub‐station.
ProvisionofdiversionofloadofonefeedertoanotherfeederthroughtheproposedRingMainUnits(RMUs)networkforachievingaresilient&flexibleelectricalnetwork.
Installationof559nos.of11kVRMUs(RingMainUnits).
Installationof642nos.LTFeederPillarand4950nos.LTServicePillarforpowertoindividualLTconsumers.
Provisionofductfortelecommunicationcables,etc.
Installationof642nos.newdistributiontransformersalongwith27nos.(63KVA–18Nos.and25KVA9Nos.)existingdistributiontransformersbasedonregroupingbyconsideringthefutureloadgrowth.
SCADA(SupervisoryControlandDataAcquisitionSystem)compatibleRMU’s(Ringmainunit)willbeemployedwithaviewofdevelopingGandhidhamcity intotheSmartCityregime inthenearfuture.
SeparatetrenchforOFCcableroutingwillbeprovided,hence,avoidingre‐excavation&probabledamagetoroads/footpaths,otherutilitiesetc.
Theproposedprojecthasconsidereddifferent typesofcable trenchconfiguration(owing todifferentlocationsandsuitability)andmethodsforlayingofUGcables.Thetrenchconfigurationswillvaryasperthesiteconditionsi.e.soiltype,widthofthelane&spaceavailabletocarryoutconstructionworks.Thetrenchwillbeexcavateduptoamaximumof1200mmdepthand500mmwidthinthecitywithwideroads. However, in conjusted areas,where cable laying operationswill be difficult, LT cablewill beerectedfromFSPofTransformertoMSPsothatmorewidthisnotrequired(250‐300mm).Here,smallMSP’s(minisectionpiller)among4to5consumerswillbeerectedinfrontoftheconsumerpremisesandfromtheMSP,cableswillbeprovidedviaDWCpipetothemeteroftheconsumers(pipewillbeclampedtothecompoundwalloftheconsumerorasdesiredbytheconsumer).Forcongestedareaswithnarrowlanesandby‐lanesAerialBunch(AB)methodwillbeemployedasitisconsideredtobethebestchoiceforpowerdistribution in congestedurbanareas.Thismethod is alreadybeing implemented inmanyareasinGandhidham‐Adipur.
SIAandRAPforUndergroundElectricalCablingWorksatGandhidhamandAdipurcitiesofKutchdistrict,Gujarat
E‐7 FinalSocialImpactAssessmentReport&RAP
TheCommissioningoftheUGSystemwillbecarriedoutafterperformingandachievingtolerableresultsof the tests after laying in compliance with specifications & standards. The existing overheadinfrastructurewillbeDecommissionedanddismantledaftersixmonthsofthecommissioningoftheUGelectricalcableproject.Itwillinvolvedismantlingofalltheexistingoverheadinfrastructure(includingoverhead conductors, insulators, straight andVcrossarms, guywires,poles,distribution transformersetc.). It is estimated that 1278 number of distribution transformers (DT’s) will be dismantled. ThedismantledtransformersduringdecommissioningphasewillbereusedentirelybyPGVCLlocallyorinthereotherprojects.Further,asperthediscussionswithPGVCLofficials,itisestimatedthat80%ofthedismantledelectricpoleswhichareingoodconditionwillbereusedinotherprojectsandtherestbylocalpeopleinruralareas(tomakeboundarywalletc.).Approx.20%ofthedismantledelectricpoleswillbescrapped(end‐of‐life) and auctioned online by PGVCLwhich is an existingmethod too for rejected electrical itemsgenerated fromtheexsitingelectricalnetwork.Debrisgeneratedwillbedisposedwith theconsentofGandhidhamNagarPalikaintheexistingwastedisposalsiteoranyothersitedesignatedforConstruction&Demolitionwasteorreusedinotherconstructionworks(fillingpotholesetc.)
7.0 Socio‐EconomicProfile
DirectImpactZone–Sub‐ProjectLocation
Thesub‐projectareacomprisesthecitiesofGandhidham‐AdipurinGadhidhamTalukaofKutchdistrict,Gujarat.BothtownsaregovernedbyGandhidhamNagarPalikacomprising14wards.Theprojectsitelieswithin the Kutch region/district which has been assigned Zone V, a “severe intensity zone” whereearthquakesofmagnitude8.0canbeexpected.Gandhidham‐Adipurareafallsintohighdamageriskzonewith awind speed of 47m/s. In view of the above it is pertinent to note here that the Sub Project ‐“ConversionofhightensionandlowtensionoverheadelectricallinesintoundergroundcablingofhightensionandlowtensionelectricallinesinGandhidhamandAdipurcitiesofKutchdistrict”isproposedunderNCRMP II forwhich, resilient infrastructure needs to be put in place forwithstanding naturaldisasters,mainlycyclones.Theelectricalinfrastructuregetsbadlyaffectedduringcyclonesresultinginbreakdownofpowersupply,causinginjuryandevendeath.TheproposedundergroundelectricalHT<cablesystemcoversalengthof430.74kmsnetwork.Thebriefoverviewonthesub‐projectindicatesthatthere’snolandacquisitionproposedunderthissub‐projectand294structuresaregettingaffected.Layingofundergroundcabling,specificallyinareasthatare congested will require dismantling of boundary walls, sitting space (utha), ramp and partialdismantlingofresidential/commercialstructures.However,therepairingworkofthesestructureswillbecarriedoutbyPGVCL.
Table1.0:OverviewofProjectState,DistrictandCity
Description Gujarat Kutch Gandhidham
Total Population 6,04,39,692 20,92,371 2,47,992
Area(Km2) 1,96,244 45674 36.6
Change in Population, 2001‐2011 (%) 19.28% 32.16% 63.48%
Urban Population (%) 42.6 34.82 100
Rural Population (%) 57.4 65.18 0
SC Population (%) 6.74% 12.3 20.36
SIAandRAPforUndergroundElectricalCablingWorksatGandhidhamandAdipurcitiesofKutchdistrict,Gujarat
E‐8 FinalSocialImpactAssessmentReport&RAP
Description Gujarat Kutch Gandhidham
ST Population (%) 14.75 1.16 1.65
Sex Ratio 919 908 886
Child Sex Ratio 890 921 912
Population Density/km2 308 45.8 6775
Overall Literacy (%) 78.03 70.59 81.80
Male Literacy (%) 85.75 79.40 87.9
Female Literacy (%) 69.68 60.87 74.82
Contribution to Gross State Domestic Product
(2011‐2012)
12.2% ‐ ‐
Primary (%) 49.6 37.34 0.78
Secondary (%) 1.39 1.39 1.55
Tertiary (%) 49.0 61.27 97.67
Source:CensusofIndia,2011
DemographyandSocio‐EconomicProfileofGandhidhamandAdipur
Demography: Gandhidham Municipal Council encompassing an area of 36.6 sq.km accounts forpopulationof2,47,992and54565households(Census,2011).Thehouseholdsizeofthecityis4.5.Thedensityofthepopulationisabout6775.7personspersq.km,whichishigherthanthedistrictandstateaverageof46and308personspersq.kmrespectively.ThisissobecauseavastareaofthedistrictisRann(desert)area.
Aspercensus2011,thesexratiointhetownaccountsfor886whichislowerthanthestateaverageof919andnationalaverageof943.Thescheduledcaste(SC)andscheduledtribe(ST)populationaccountsfor20percentand1.65percentofthetotalpopulationofthetown.Thetotalscheduledcastepopulationofthedistrictis12.37%with4.23%residinginurbanareas.Theliteracyrateofthetownaccountsfor81.80percent,whichishigherthanthestateaverageandnationalaverageof79.31percentand74.04percentrespectively.Whilethemaleliteracyratecomprises87.9%,femaleliteracyaccountsfor74.8%.The Hindus constitute the maximum share of population (91.23%) , followed byMuslims (5.48%) ,Christians(1.21%).Thetheworkparticipationrate(WFPR)ofGandhidhamaccountsfor36percent.Outofthetotalworkersinthetown,0.32%areengagedincultivation,0.46%areAgriculturallabourers,1.55%areengagedinhouseholdindustrialworksand97.67%areengagedinotherworks.Thetownisprimarilyaservicetown.AsthecityisoneofthefastestgrowingcitiesofGujaratitisconsideredastheeconomiccapitalofKutchdistrict.Thecityisapopulardestinationsforconventions,business,meetingsandmajorindustriesandKandlaportandKASEZarelocatedinthehinterlandofthecity.ThecityisaservicetownandcaterstoitsneighbouringareasStatusofInfrastructure(physical&social)facilitiesinthecity
PhysicalInfrastructure:
RoadsandHighways:ThetwincitiesofGandhidhamandAdipurareconnectedtotheotherpartsofGujaratthroughNationalHighway(8A)41andStateHighway46(SH46).TagoreRoadpassingthrough
SIAandRAPforUndergroundElectricalCablingWorksatGandhidhamandAdipurcitiesofKutchdistrict,Gujarat
E‐9 FinalSocialImpactAssessmentReport&RAP
thecentreofthetownlinkstheStateHighway46(SH46)totheKandlaPortRoad.Theroadnetworkwithinthetwincitiescanbebroadlyclassifiedinto60m,45mand30mwideroads.WaterSupply:RawwaterforGandhidhamWaterSupplySchemeissourcedfrombothgroundwaterandsurfacewater. The groundwater is abstracted from the deep tubewells (about 100m to 120m deep)situatedbetweenAnjarandBhujandthesurfacewaterissourcedfromTapparDamconstructedonRiverSakara,situatedat35kmfromGandhidhamandalsofrompipelinesdrawingwaterfromRiverNarmadaandRiverMacchu.Around25.00MLDissuppliedwithinGandhidhammunicipallimits.ThewatersupplyschemeinGandhidhamismanagedbyGWSSB.Sanitation: TheexistingundergroundseweragenetworkinGandhidhamwasdesignedbyKandlaPortTrustandisabout25yearsold.Thecitygeneratesabout70.00MLDofsewagedaily,servedby256kmsofundergroundseweragenetwork.
Health: Gandhidham and Adipur cities have adequate health facilities which include Hospitals,dispensaries,healthcentres,maternityhomesetcrunbygovernment,privateorganisationsandtrusts.Education:Thereareabout79schoolsand27collegesinthecityper1000population(Census2011).FurtheraspertheGandhidhamNagarpalikathetotalnumberofschoolspresentinthecityisabout20whichincludesbothgovernmentandprivateschools.Recreation:ThecityofGandhidhamwasdevelopedwithaviewtoaccommodatetherefugesfromWestPakistan,hencethecitydoesnotincludemuchofplannedrecreationandtouristplaces.However,afewtouristandrecreationspacesinthecitycomprisestheGandhiSamadhi,theIFFCOColonywhichincludesmanyparks,greenareas,cricketground,waterbodiesandreligiousplaces.Housing and slums: There are 54054 properties in the city of which 14640 are commercial andInstitutionalproperties.(Census2011).TheslumpopulationinGandhidhamcityaccount24,914residents,accountingforaround10.05%oftotalpopulationthecity. Theslumhouseholdofthecitymainlycomprisesthe immigrants workingintheKandlaportandother industrieswhichare locatedinthesurroundingregionoftheGandhidhamandKanda.Thelargest(un‐notified)slumsintheGandhidhamareSunderpuriandGopalpuri.Main sourceofLighting inGandhidham: Approximately 96 percent household of Gandhidham haselectricalconnectionsandonly0.77percenthavenosourceoflighting.
8.0 SocialImpactAssessment&MitigationMeasures
Theimplementationof“UndergroundElectricalCablingSysteminGandhidhamandAdipurcities”islikelytocauseadverseimpactsonstructuresandassetsfallingalongthecablingrouteparticularly,especiallyincongestedareas.Thenatureof impacts identifiedbasedonthecensussurveyconductedcomprisespartialimpactsonresidential,commercial,residentialcumcommercialstructures,kiosk,CPRsetc.Since,theresettlementimpactsareonlypartial; it isnotlikelytoresult inphysicaldisplacement/relocation.Hence,anassessmentofadverseimpactsanddevelopmentofmitigationmeasureshasbeencarriedoutwhichmainlyaimstoassessthemagnitudepotentialadverseimpactsintermsofpropertiesandassetsandassociatednumberofpeople.ThedetailsofimpactofonefeederhasbeenprovidedintheStripPlan(VolumeIII)
SIAandRAPforUndergroundElectricalCablingWorksatGandhidhamandAdipurcitiesofKutchdistrict,Gujarat
E‐10 FinalSocialImpactAssessmentReport&RAP
TheassessmentisinaccordancewiththeESMF,whichhasbeenontheNational,StateLaws,andWorldBankoperationalpoliciesrelatingtosocialsafeguards.ThemethodologyadoptedandthestepsfollowedforconductingtheSIAare:
Secondarydataandliteraturereviewandsurvey StakeholdersConsultation: CensusandBaselineSocio‐EconomicSurvey:
MajorFindingsofthesurvey:
Atotalof294structureswillbepartiallyimpactedduetosub‐projectimplementation, Basedontheaveragesizeofthehousehold(5.9),itisestimatedthatmorethan2053personswould
beimpactedduetoimplementationoftheproject, Majorityof the structures (96.2%) likely tobeaffectedcomprises floors/rampsofdifferent types
(cementconcrete,tiled,interlocked,etc), Besidesindividualstructures,10commonpropertyresources(CPRs)suchastemplesandpassenger
shelterarelikelytoaffected, PhysicaldislocationofPAPsarenotlikelyasonlyapartofthestructurewouldbeimpacted, Majorityofthestructureslikelytobeaffectedhavebeenconstructedongovernmentland.Thusthe
statusofownershipmaybecategorisedasencroachersandsquatters,Itmaybenotedthatthoughthesocialimpactassessmentprovidesextentofimpactsonpropertiesandpersonsassociatedwithproperties.HoweverbasedondiscussionswithPGCVLofficialsandWorldBankteam during January 2018, these impacts will be minimized to a large extent during sub‐projectimplementation.ThemethodologyadoptedbyPGVCLwillfocusonadoptingalternatemeasuresduringcablelaying(likeshiftingofcableroutefrominsideofthepremisestowardstheedgeoftheroad/street,shiftingofcableroutefromonesideoftheroad/streetontoothersideofroad/street,makingminordeviationsinthecablelayingroute,etc)basedonthesiteconditionstofurtherminimizeimpactsonstructures.Broadly,cablelayingbytrenchingmethodwouldbefollowedinopenareas.Incongestedareas/narrowlines/by‐lanes,aerialbunchingmethodwouldbefollowed.Specificationsforcablelayingmethodologywouldbesuitably included in tenderdocument.Wherever, avoiding impactsonstructureswillnotbepossible,structureswillberepairedatprojectcostbyPGVCL.
9.0 StakeholderConsultations
Stakeholders’consultationswereconductedattwolevels:LocalandCitylevel.Locallevelconsultationswere held with individuals and with group of people in different parts of the city. The City LevelConsultationworkshopwasorganizedonMay17th,2017inConferenceHallofChambersofCommerceand Industries in Gandhidham. There were 62 participants comprising PAPs, local community,representative from various organisations, Forest Department, Pollution Control Board, KPT, GIDE,GandhidhamNagarpalika,ChamberofCommerceandIndustries,publicrepresentative,eminentcitizens,PGVCL,etc.TheidentificationandpreparationoflistofkeystakeholderswasdonebytheConsultantteaminconsultationwithDivisionalOffice,PGVCLGandhidham.TherequestletterandpriorinformationforattendingthestakeholdersmeetingwasissuedbytheExecutiveEngineer,DivisionalOffice,Gandhidham.AbrochureprovidingbriefinformationabouttheproposedworksinGujaratilanguagewaspreparedfordistribution tostakeholdersbefore theconsultation fordevelopinganunderstandingof theproposedworks.ThecontentofthebrochurewassharedwithPGVCL,Rajkotbeforefinalizingthedateandvenue
SIAandRAPforUndergroundElectricalCablingWorksatGandhidhamandAdipurcitiesofKutchdistrict,Gujarat
E‐11 FinalSocialImpactAssessmentReport&RAP
ofconsultation.PGVCLofficialsfromRajkotandDivisionalOffice,Gandhidhamwerepresentduringthestakeholders’consultationalongwiththeConsultantteam.Themajorcommunityconcernsandfeedbackregardingtheproposedprojectareasfollows:
During natural disasters, risk of electrocution increases due to snapping of overhead electricaltransmissionlines.
Duringthemonsoon,duetoincreasedfluctuationinelectricitysupplyhouseholdelectricalitemsgetdamaged.TheUGelectricalsystemwillreducedamageofsuchitems
Further,duringrainyseasonschildrenandanimalsareparticularlyatrisk.Theaccidentssometimehasbeenfatal.Numberofsuchaccidentswillreduceduetotheproposedworks.
Somecasesoffireduetoelectricalshortcircuithaveoccurred.SuchcasesarelikelytobereducedduetotheUGelectricalcableworks.
Stakeholdersinformedthatthereisnogaspipelineinthecitiesandalsodrainagesystemdoesnotexist in some areas. People believed that underground cablingworks is not likely to posemuchdifficulty and desired that utmost care should be taken to avoid impacting existing undergroundutilitiesinthecities.
Existenceofelectricalpolescausealotofhindrancesandsometimeshasbeenthecauseofaccidentaswell.Removalofelectricalpoleswillincreasespaceformobility.
StakeholdersinformedthatundergroundelectricalcablesystemisverymuchneededforcitiespronetonaturaldisastersandappreciatedtheinitiativetakenbythePGVCLandexpressedwillingnesstoextendco‐operationforearlyimplementationofworks.
Demolition of structures/assets due to existence of electrical poles within the premises(residential/commercialunits)orincloseproximitytothestructures.
Qualityofmaterialstobeusedsoastoavoidfrequentfaults.
Suitableprecautiontobetakentomaintaindisposalofrainwatersystems.
Safety aspects during implementation works should be paid due attention to avoid mishaps/accidents.
Heightofdistributionboxfromthegroundlevel.
Implementationworksshouldbeproperlymonitoredtomaintainqualityofworks.
Diggingworksforvariousactivitiesarecarriedoutincitiesfrequentlyleadingtoinconveniencestocitizens.Theyraisedconcernthatfurtherinconvenienceisnotcreatedbytheundergroundelectricalcableworks.
Themajorsuggestionsfromthecommunityregardingtheproposedprojectareasfollows:
Cablerouteshouldbemarkedinadvanceandresidentsintheareashouldbeinformedatleastoneweekadvancebeforestartingthecablingworkstominimizeimpactsandinconveniencetoindividualconsumers,schools,healthfacilities,etc.
Electricalcableshouldbelaidonthesidewhichhaslessnumberofshopsandhouses.Thedepthofcablelayingshouldbe2minsteadof1.2m.
Regular coordination with community and leaders should be maintained for informationdisseminationandresolvingproblems/hurdlesduringexecutionworks.
Electricalpolesshouldberemovedaftercompletionofundergroundcablingworks.
SIAandRAPforUndergroundElectricalCablingWorksatGandhidhamandAdipurcitiesofKutchdistrict,Gujarat
E‐12 FinalSocialImpactAssessmentReport&RAP
10.0 InstitutionalArrangements
TheNCRMP‐IImandatesestablishment/settingupof institutionalarrangementsatnational, stateandsub‐project levels for implementation of sub‐project activities. The key elements of institutionalarrangements at different levels aim to supplement and complement activities of variousorganizations/agenciesinvolvedinprojectplanningandimplementation.TheDPRhasbeenpreparedbythePGVCLUnderthecurrentproject,forlayingundergroundelectricalcablingworksatGandhidhamandAdipurcities(sub‐project),theLineDepartment/executionagencyisthePaschimGujaratVijCompanyLimited(PGVCL).ThusPGVCLisresponsiblefortheimplementationoftheproposedUGelectricalactivities/workthroughcontractors.TheExecutiveEngineer,PGVCLRajkotisthenodalofficerfortheimplementationofthesub‐projectactivities.TheExecutiveEngineer,DivisionalOffice, PGVCLGandhidhamwill be involved in actual executionandoverseeingof underground cablelayingworksatsite.ForRAPimplementation,aSocialExpertshallbeappointedbyGSDMA/PGVCL foraperiodof2years having experience in RAP implementation or resettlement and rehabilitation works,includingorganizingstakeholder/communityconsultationsetc.ThesocialexpertwillbeengagedbythePGVCLforRAPimplementationatsiteandwillworkinSiteOfficeofPGVCLatGandhidham.
11.0 GrievanceRedressalMechanism(GRM)
The GRM has been designed at national and state levels to address complaints and grievances andengagement of a third party auditor. Third party will be appointed by the GSDMA to provideindependentassuranceoncompliancewiththeEMSF.Thethirdpartyauditorsshall: SupporttheGSDMAinpreparingtheauditplan.
Prepare compliance report for sub‐project activities in line with ESMF guidelines and otherstatutoryrequirementsasapplicablethroughscheduledorunscheduledaudits.
Conductingrandomfieldvisitsandreviewcompliance,especiallyattheenvironmentallysensitiveareas.
ReviewtheperformanceoftheprojectthroughanassessmentofperiodicalmonitoringreportssubmittedbytheimplementationagencyandPMSC.
ShareauditfindingswiththeGSDMAtoaidintimelydecisionmakingandadoptingappropriatemitigationaction/s,ifnecessary.
The Social Specialists at the state level (PMSC) shall provide feedback based on the field visits,regularsupervisionandmonitoringactivities, including thoseundertakenaspartofThirdPartyaudits to the SocialExperts at thenational level inNDMA.The Social Specialists at thenationallevelwillinturnprovidetechnicalassistanceinplanninganddesignoftheactivities,includingreviewsandtrainings.
12.0 Monitoring&Evaluation
MonitoringandevaluationofResettlementActionPlanimplementationarecriticalinordertomeasuretheprojectperformanceandfulfilmentofsub‐projectobjectives. Themonitoringwilloccurasaperiodicfunction, andwill include process reviews/audits, reporting of outputs, andmaintaining progressiverecords.ItwillcoverPhysicalProgressandSocialMonitoring.
SIAandRAPforUndergroundElectricalCablingWorksatGandhidhamandAdipurcitiesofKutchdistrict,Gujarat
E‐13 FinalSocialImpactAssessmentReport&RAP
(a) PeriodicPhysicalProgressMonitoring‐PhysicalprogressmonitoringwillbecarriedoutbythePMSConamonthlybasis.TheRROwillreportontheprogressofRAPimplementation.Monitoringwillalsocoverconstraintsanddelayingfactors.
(b) SocialMonitoring‐Thiswillcompriseofthefollowingsetsofactivities:
a) Compliance of entitlements to different categories of PAPs as per Environmental and SocialManagementFramework(ESMF),and
b) Monitoringandoversightofsocialissuesatstatelevel.
TheformatforinternalmonitoringwillbedevelopedbythePMSCbasedonsiteconditionswithregardtoRAPimplementationandanyotherspecificrequirementsoftheproject.EndTermEvaluation
Since theproject impactsarevery limited, theengagementofThirdPartyAuditor isnot required forperiodicmonitoring.However,anagencymaybeengagedforendtermevaluation.
13.0 ImplementationSchedule
Thestandardconditionsofcivilcontractsrequireavailabilityofencumbrancefreelandtothecontractorforexecutingconstructionworks.Thoughacquisitionofprivatelandisnotproposedforthissub‐project,nevertheless entire landstretch (government land) isnot free fromencumbrances.TheRightofWay(vacant landbeyondcarriageway)along theoverheadelectrical transmission lineshasbeenoccupied(encroachedandsquatted)forvariouspurposes.LayingofUGelectricalcablewillbecarriedoutintheavailableland(RoW)broadlyfollowingtheexistingoverheadelectricaltransmissionline.Encumbrance free routes are not available at site. Thus, variousmethods for laying of undergroundelectricalcablingisproposedviz:byburied,trench,pipeorductmethod.While,majorworkslayingforUG electrical cabling will done by manual digging, trenchless technology will be adopted, whereverelectricalcablecrossesfromonesidetoanotherside.Nevertheless,alargenumberofstructureswouldbeaffectedpartially,particularlyincongestedareas.Atimelinefortheimplementationofsub‐projectconstructionworks is estimated to be two years. The time frame for implementation of RAPwill besynchronized with the sub‐project implementation (construction schedule) activities so thatcommencementandprogressofcivilworksisnotdisturbed.TheR&Ractivitiesunderthesub‐projectshallbecompletedbeforethestartofworkonthegroundsothattheresidentsandbusinessunitsremovetheirassetsduringthecablelayingworks.
14.0 Resettlement&RehabilitationBudget
The resettlement and rehabilitation budget comprises amount equivalent for impacted structures atreplacementcostdeterminedaspertheScheduleofRateswithoutdepreciation,costofhiringofSocialExpert, contingency, etc. The replacement cost for impacted structures has been considered budgetpurpose.However,itisnotlikelytobedisbursedasrepairingofimpactedstructureswouldbecarriedoutbyPGVCLatprojectcost.RemunerationforengagingSocialExpertfortheimplementationofRAPwillbebornebornebytheGSDMA.ThebudgetforimplementationofRAPisestimatedtobeRs.59.40lakhs