Separate Cash Flow Evaluations - Applications to Investment Decisions and Tax Design
Transcript of Separate Cash Flow Evaluations - Applications to Investment Decisions and Tax Design
Separate cash Flow Evaluations - Applications to In-vestment Decisions and Tax Design*
By
Magne Emhjellen** and Petter Osmundsen***
** Petoro AS
*** University of Stavanger
Abstract
Oil project assessment using separate cashflow valuation (Jacoby and Laughton, 1992, Laughton and Jacoby, 1993 and Emhjellen, 1999), presume that the present value of the cost cashflow of oil projects can be calculated using a risk free rate. This paper examines whether this practice, at least to a first approximation, is rea-sonable. More specifically, the paper examines whether labour wage hours costs and steel prices, as cost factors in the investment cost stream, are systematic risk factors (i.e. have a beta different from zero). The paper also investigates whether oil price as a factor in the revenue stream is a systematic revenue factor. Separate cash flow evaluation has been discussed in relation to petroleum taxation. A petro-leum tax commission in Norway stated that tax reductions due to depreciation should separately be discounted by a risk free rate. We discuss the role of partial cash flow discounting in tax design.
** Magne Emhjellen, Petoro AS, Postboks 300 Sentrum 4002 Stavanger , Norway, Email: [email protected]
**** Petter Osmundsen, University of Stavanger, Department for Industrial Economics and Risk Management, 4036 Stavanger. Email: [email protected], Home page: http://www5.uis.no/kompetansekatalog/visCV.aspx?ID=08643&sprak=BOKMAL
2
1.1 Introduction
In research related to oil project valuation one often makes
the assumption that the present value of the cost cashflow may be
calculated using the risk free rate (Laughton and Jacoby, 1993,
Laughton, 1998 and Emhjellen, 1999). From a Capital Asset Pricing
Model (CAPM) (Sharpe, 1964, Lintner, 1965) point of view this is
only permissible when the uncertain changes in the cost cashflow is
not correlated with the rate of change in the market portfolio.
To examine this, in Secion 2 we test whether two important
cost factors for oil projects, labour costs and steel prices, are
systematic risk factors (i.e. correlated with the value of the market
portfolio). In addition, we examine in Section 3 whether oil prices
represent a systematic revenue factor, and thus whether the CAPM
beta obtained for oil prices support using a higher required rate of
return when discounting revenues than when discounting costs.
After identifying the main cost variables for the example project,
historical data on the cost variables, as well as historical data on a
proxy for the market portfolio (The Total Index, Oslo Stock
Exchange) are presented. The betas of these cost variables are then
calculated. The data of our analyses is documented in eight tables,
3
and can be found in our downloadable working paper 2009/16 at the
University of Stavanger.1
The results for the period examined show that the oil price
beta is higher than the cost betas and that risk free discounting of the
cost cashflow may be a reasonable approximation until other cost
factors are identified and examined. The results of the paper
therefore support the idea that revenues should be discounted at a
higher rate than costs when calculating the present value of oil
exploration projects. However, uncertainty related to the correct size
of the individual cashflow betas indicate that further research should
be undertaken on the required rate of return of individual cashflow
streams.
The issues of distinct required rates of return for discounting
individual cashflow streams of oil projects have been raised by the
Tax Commission in Norway. In a tax evaluation study they
implicitely propose that the oil companies should change their
valuation method from discounting the aggregate net cashflow
stream to a method where one specific partial cashflow is valued
separately, namely the tax reduction cash flow from tax depreciation
(Government Report NOU 2000:18).2 The companies actual
investment valuation methods is essential to evaluate the
implications of the suggested tax changes. The Commission
1 http://ideas.repec.org/p/hhs/stavef/2009_016.html
2 This deviates from previous tax theory and policy recommendations, see e.g. Osmundsen, (1999a).
4
recommended a slower pace of tax depreciation. Tax depreciation
time should expand from the current 6 years (linear depreciation) to
a time frame more accurately reflecting the economic life of
extraction and transportation installations.3
The companies argued that, with their global practise of
using average discount rates, this would cause considerable tax
increases and lead to a non-neutral tax system that would generate
underinvestment. At any rate, they said, tax reduction cash flows are
by experience not certain, as verified for example by the
Commission s own report that proposed tax increases. The Tax
Commission, on the other hand, argued that the revised tax system
would be neutral if the companies correctly discounted tax
reductions by a risk free rate.
This debate raises important questions. Present tax theory
usually presumes average discount rates. In the event of the adoption
of separate cashflow discounting, how should the tax reductions of
depreciations be discounted.
Separate cashflow betas are discussed and estimated in
section 2 and 3. Uncertainty related to tax recovery and government
tax changes are discussed in Section 4 and in section 5 an example
project valuation is shown using the standard net cashflow
3 The short depreciation time, together with an added depreciation of 30 per cent (uplift), were designed so that the special resource rent tax of 50 per cent should actually only be levied on excess returns, and so that the tax system would not distort investment decisions of the oil companies (neutrality), see White Paper Ot.prp. 1991-92.
5
discounting method and a separate cashflow discounting method.
Our data sources are presented in an Appendix.
2. CAPM and separate cashflow betas
Finance theory (Sharpe 1964, Lewellen 1977) related to valuation in
the mean-variance framework argues that in order to calculate the
present value of an uncertain individual cashflow stream one needs
an estimate of the expected value of the cashflow stream and the
cashflow streams covariance with the return of the market portfolio.
The issue of estimating the expected value is raised in section 3. We
now turn to the issue of the required rate of return. The Capital Asset
Pricing Model (CAPM) (Sharpe 1964) relationships states that:
fmifi RRERRE , (2.1)
where E(Ri) is the expected required rate of return on equity of an
asset i and Rf if the risk free rate, E(Rm) is the expected return on the
market portfolio and i
is the covariance of the return of asset i
with the return of the market portfolio divided by the variance of the
return of the market portfolio ()(
),(
m
mii rVar
rrKov).
From the value additivity principle (Shall, 1972), the net present
value of an asset is the sum of the present values of the component
cashflows of the asset:
6
iM
1jiji XV , (2.2)
where Xij is the present value of the jth component of the cashflow
of asset i discounted using the expected required rate of return of the
jth component of asset i, E(Rij), and Mi is the number of cashflow
components of asset i. The expected rate of return on equity of an
asset is equal to the sum of the value weighted expected rates of re-
turn of the individual component cashflows
iM
1jijiji REwRE . (2.3)
In equation 2.3, i
ijij V
Xw
and iM
1jij 1w . From the CAPM relation-
ship, the expected required rate of return of the jth component of the
cashflow of asset i may be written:
fmijfij RRERRE )( . (2.4)
Substituting equation 2.4 into equation 2.3, i may be written as
iM
1jijiji w . (2.5)
7
An example is where there are only two distinct cashflows generated
by an asset (Lewellen, 1977 and Emhjellen and Alaouze, 2002): the
expected after tax revenue cashflow and the expected after tax cost
cashflow, where each of the expected after tax cashflow streams has
a different beta. Thus, j=1,2, and to specify notation, let iDi1 be
the expected after tax revenue cashflow beta for asset i and
iCi2 be the expected after tax cost cashflow beta for asset i.
The value of a project given by 2.3 may be written as
Ci
Dii VVV . (2.6)
In equation 2.6, DiV denotes the PV of the expected after tax reve-
nue cashflow of asset i, and 0VCi
denotes the PV of the expected
after tax cost cashflow of asset i. The beta for asset i may be written
as
CCiD
Dii ww
, (2.7)
where Ci
Di
DiD
i VV
Vw
and Ci
Di
CiC
iVV
Vw ,
This shows that if an individual cashflow valuation method is to be
used, an integral part in order for the value of the project to be de-
termined, must be to determine the cost cashflow beta and it s rela-
tive weight. In other words the systematic risk associated with the
project cost must be determined in order to estimate the required rate
8
of return and thereby calculate the present value of this cost cash-
flow. An interesting point noted by Lewellen, 1977 is that a higher
beta for the capital expenditure cost cashflow implies a higher
project value. The reason for this is that cost cashflow is a cash out-
flow where higher discounting (higher beta implies higher required
rate of return) implies a lower present value of cost. This is contrary
to what is true for revenue, where higher systematic risk implies less
value.
2.1 Calculating the ex post betas of cost input variables
Before estimating the ex post betas of cost input variables it is im-
portant to have in mind that this approach is very different from es-
timating the ex post beta of a company. Firstly, the expost beta for
the companies will have debt included amplifying the business risk
of the company (companies are normally partly debt financed). The
levered company beta is therefore higher than the company unle-
vered beta. For a discussion on this see Copeland and Weston
(1992). With a separate cashflow valuation method the individual
cost or revenue betas will have no debt associated with them since a
debt cashflow will be valued separately.
It is important to note that an investor will face, in addition to
the business and financial risk related to the betas, also the change in
the level of the risk free rate as well as the changes in the market risk
9
premium (exemplified recently with the financial crisis). Unepected
changes in these parameters will affect individual companies diffe-
rently because of different debt levels and levels of business risk (ie.
size of unlevered beta).
A final point regarding estimation of individual cashflow be-
tas is that they will be dependant on the parameters chosen, the total
period and the return period chosen and the market portfolio proxy
(index). In addition, one runs the risk that the returns on the parame-
ters chosen are correlated and or that there are parameters not se-
lected that have various degrees of correlation with the chosen pa-
rameters or the proxy for the market portfolio. However, the
company beta is given by equation 2.5 where a debt level different
from zero would be associated with a beta of debt. With no debt the
company or project beta can be described by equation 2.7. The re-
sults below are therefore only one first attempt at identifying weath-
er the chosen parameters has betas different from zero.
The rate of change of the cost data and the rate of change of the To-
tal Index were calculated using the real quarterly data on wage hour
cost, steel prices and the Total Index. The rate of change data are
shown in Table 5.
The ex post betas of the wage hour costs and steel prices were calcu-
lated using Equation (1) and the data in Table 5.
10
(1) )(
),(2 Rm
RmRiCovi .
A total of three ex post cost betas were calculated:
(2) 0052,02,140
73,0
)(
),(2
1
^
1
^
m
m
R
RRovC,
where 1
^
is the estimated offshore wage cost beta, R1 is the rate of
change of the offshore wage cost, and Rm is the rate of change of the
Total Index. Similarly, the beta of the onshore wage cost is
represented by 2
^
, and the steel price beta by 3
^
.
(3) 0747,02,140
47,10
)(
),(2
2
^
2
^
m
m
R
RRovC ,
(4) 1609,02,140
56,22
)(
),(2
3
^
3
^
m
m
R
RRovC .
These results indicate that of labour cost and steel prices,
steel prices have the highest beta, which indicates that at least the
11
materials input part in the investment cashflow of oil projects has a
positive beta.4 Hence, this part of the costs cashflow should be dis-
counted at a rate higher than the risk free rate. For labour cost, al-
though the results show positive betas, the betas (at least for offshore
workhour cost) are only marginally greater than zero.
Using a market risk premium [E(Rm)-Rf] of approximately
6% (Johnsen, 1991), this indicates a required rate of return for the
labour cost portion (with a beta of 0,0747) of approximately 0,44%
above the risk free rate [0,0747(6%)]. Similarly using the steel price
beta the required rate of return would be approximately 1% above
the risk free rate. A weighted average of labour cost and material
cost using these two betas would therefore indicate a required rate of
return less than 1% (0,7%) above the risk free rate.
3 Calculating the ex post oil price beta
The oil price beta was calculated using the price data on WTI (West
Texas Intermediate) as given in Standard & Poors Platt's Prices and
Data for the period 1986 to 1994. The nominal WTI price data in US
dollars per barrel were converted to real Norwegian currency using
the CPI (Norway) and the NOK/USD exchange rate. The real rate of
change for each period was then calculated quarterly.
4 In deriving the weighted average of the ex post cost betas, we have used their relative PV weights. Assuming that the PV of the labour cost is 60% of the after tax cost cashflow, and that the PV of steel represents the remaining 40% of the af-ter tax cost cashflow (from the cost structure of project N), the cost cashflow beta is a weighted average of the two cost betas.
12
The data are presented in Table 6. The nominal oil prices in US dol-
lars are shown in column one, the exchange rates in column two, the
CPI in column three, real oil prices in Norwegian currency in col-
umn four, the percentage changes in real oil prices in column five
and the percentage changes in the Total Index in column six.
The oil price beta was calculated in the same manner as the cost be-
tas using the data in Table 1. The oil price beta was calculated to
0,293 using Equation (1). This is higher than the cost cashflow betas
obtained. It is, however, important to note that the estimated oil
price beta, as the cost betas, could be different with data from differ-
ent time periods and different length of time periods. Thus, the ex
ante oil price beta, just like the cost cashflow beta, may be very dif-
ferent from the calculated ex post beta based on historic data. For the
time period chosen here, however, the oil price beta is substantially
higher than that of the cost cashflow beta, implying that a higher risk
adjustment is called for when discounting the expected after tax rev-
enue stream than when discounting the expected after tax cost
stream. Using this oil price beta as estimate for the required rate of
return on revenues gives a rate 1,8% above the risk free rate (given a
market risk premium of 6%).5
5 It should be noted that the period examined contains the period of the Iraqi invasion of Kuwait where the stock indexes around the world (including the Total Index) depreciated in value while the oil price increased. This has the effect of re-ducing the size of the oil price beta for the period calculated.
13
4. Tax payments and risk adjustment
We will raise two issues regarding valuing the tax reduction
cashflow from tax depreciation when valuing cashflows separately.
First, there is the possible direct tax concern for the timing and
likelyhood of cost recovery. Second, there is the issue of possible
government changes in the tax level.
Is it reasonable to discount these tax reductions by a risk free
rate? This is not a trivial issue, since such tax reductions normally
are a non-linear function of both costs and income, where the latter
is crucial for determining whether the oil company is in a tax paying
position. The non-linearity, which may challenge the assumption of
additivity, makes taxes hard to separate from other cash flow
components. Discounting with a risk free rate may not be the
relevant approach, due to the option nature of tax payments, see
Lund (1992).
The Norwegian Petroleum Tax Commission makes several
recommendations that would affect the valuation of tax reductions.
In June 2001 the Norwegian Parliament approved an amendment to
the Petroleum Tax Law, allowing the oil companies to carry forward
deficit with interest (risk free rate), and allowing the companies to
14
transfer losses to other companies.6 Thus, the likelihood of effective
tax deductions are increased, the tax system has become more linear,
and the option nature of tax cash flows are less evident than in most
other petroleum tax regimes, e.g., ring fence systems. Another
suggestion from the Petroleum tax Commission, not endorsed by
Parliament, was to increase the tax depreciation time. Such a change
would have increased the political risk for the companies, as there
would be a higher risk risk of a change in tax conditions after
irreversible investments are literally sunk on the seabed. After
investments have been made in facilities that may extract petroleum
for some thirty years, new governments will come into power, and
there is limited possibilities to establish credible guarantees for a
stable tax policy, as one Parliament
according to the Constitution
cannot commit the tax policies of future Parliaments.
4.1 Tax effects resulting from revenues and costs The norwegian tax base is given by:
Tax base = Revenues (oil price x sale of oil) operating cost
tax
depreciation interest cost.
The oil companies will pay a percentage tax of this tax base, making
the tax payments a function of oil price, production and costs.
For revenues, given the assumption that the sale of oil from
6 Transfer of losses at full tax value, however, presumes an efficient market for tax deferrals. In periods of low petroleum prices, there may be a buyer s market.
15
an oil project is independent of changes in the value of the market
portfolio, would have a beta equal to the oil price. This follows,
since the after tax revenue is only a scaled down level of the
revenues before tax (timing og tax reduction from depreciation
amounts discussed separately). Consequently, the percentage
changes in the after tax cashflow will be equal to the percentage
changes in the before tax cashflow and their correlation with the
changes in the value of the market portfolio will be equal, resulting
in the same beta.
The operating cost cashflow reduces the tax base the same
year while the investment cashflow reduces the tax base through tax
depreciation. Given that the cost betas before tax are only marginally
positive, the cost betas after tax will primarily be linked to the
systematic risk of the oil price. This because the reduction in tax
(after tax cost cashflow) resulting from the cost cashflow will only
be positive when the tax base is positive. In other words, the
negative tax base resulting from low oil prices will have to be
carried forward until the project generates a positive tax base.
Consequently, even though the results of this paper indicate low
systematic risk for the cost cashflow (labour cost and steel prices),
the after tax cost cashflow has a timing risk and risk of loss (lost
after 10 years) that is a result of the systematic risk of the oil price.
This possible delay or loss of the cost recovery - if it is not fully
covered by transfer of losses - is a risk that will reduce the full value
of the tax reduction resulting from incurring cost. The calculation of
16
this tax loss must be a function of the oil price since given
production and costs the oil price level determines the likelyhood of
not beeing in a tax position.
4.2 Government changes of tax level
One major uncertainty related to future tax payments is
government changes of the tax system which may cause changes in
the tax base and/or the tax rate. It is likely, given past observations
related to tax changes, that governments are inclined to increase the
tax level when oil prices are stable and high for some time (1-2
years), and to lower the tax level when the oil prices are very low.
One could argue that these tax changes causes the risk to be lower
since over the long run this would reduce the upper levels and
increase the lower levels of the after tax cashflow of the project to
the oil companies while providing the same expected after tax
cashflow. However, from past observations, these changes in tax are
sometimes only implemented for new projects when prices are low
(to stimulate new activity), while they are implemented across the
board when prices are high (i.e., a ratchet effect). Given this type of
asymmetric tax policy over the business cycle, the risk has
increased, or rather, the expected value of the cashflow is reduced by
limiting the upside return to the companies and not limiting the
downside.
17
Consequently, the oil companies will have to take these
possible tax changes into account when calculating project value and
deciding on new oil projects.
18
4.3 Calculating the value of the tax cashflow
Separate cashflow valuation methods require use of correct
required rates of return when discounting the individual after tax
cashflow streams. Given the arguments above the present value of
tax on revenues (and consequently the after tax revenue cashflow)
should be calculated using a required rate of return based on the
before tax beta of revenues.
The present value of the expected after tax cost cashflow
should, like for revenues, be calculated using the correct required
rate of return on the before tax cost cashflow. However, there
remains the question of how to adjust for the possible time or actual
loss of cost recovery. One possible method would be to assess the
probability of this reduction in cost recovery and adjust the cost
recovery accordingly. Another approach would be to use a higher
required rate of return when calculating the present value of the cost
recovery. Both methods would be difficult in the sense that with the
first method the probability would be difficult to assess and with the
second method the difficulty of finding a correct higher required rate
of return.
An investigation into oil companies project valuation practise
found that the standard discounted cashflow method was the method
most in use (Siew, 2001). Even though this study does not
distinquish (when asking the energy companies) whether the
discounted cashflow method (DCF) is based on discounting net after
19
tax cashflow or indvidual cashflows, it is likely that it has been
interpreted by the energy companies as standard net cashflow
valuation. The Value Additivity Principle (Shall, 1972) however,
makes a separate cashflow discounting method possible since the
sum of the individual cashflow values should be equal to the project
value. This however, does not necessarily make this valuation
approach a practical method. There remains the issue of whether one
can obtain reasonable estimates for the required rate of return of the
individual cashflow streams. The fact that most energy companies
prefer the DCF based on calculating the present value of the net after
tax cashflow is probably motivated by the difficulies in finding
correct required rates of return for the individual cashflows and/or
the above mentioned cost recovery and tax incentive issues. There
are, however, also obvious difficulties in finding a correct required
rate of return for an individual projects net cashflow (Emhjellen,
1999) , which makes further research into separate cashflow
valuation interesting.
20
5 Oil project valuation example
A valuation of an oil project will be illustrated using real oil project
data obtained from Statoil (Project N in Emhjellen, 1999). The
project data are given in Table 7.
5.1 Assumptions used in calculating project NPV
The expected after tax cashflows used in calculating present values
are based on the Norwegian tax regime. The assumptions are as fol-
lows:
1) A 50% special tax is applied to the offshore oil industry. The actual
amount of special tax is determined by the tax base, which is calculated
as follows:
Tax base = Revenue (d) - Operating cost (OC) - Depreciation tax shield
(DTS) - Interest payments (IP) - Additional depreciation allowance
(ADA). The special tax is equal to the tax base multiplied by 0.5.
2) An ordinary corporate tax rate of 28% is applied to tax base special tax
less ADA (uplift).
3) Total tax = special tax +ordinary tax
With the separate cashflow discounting method of NPV calculation,
revenue cashflow tax and cost cashflow tax are equal to:
4) Revenue cashflow tax = d
(0.5+0.28).
21
5) Cost cashflow tax = total tax - revenue cashflow tax.
6) The depreciation amount is 6 year linear depreciation applied to invest-
ment. This tax benefit can be claimed against other offshore oil revenue
of the company (no ring fence on the NCS). When calculating the ex-
pected after tax cost and revenue cashflows, the tax effect of the depre-
ciation amount is treated as a reduction in costs.
7) The additional depreciation allowance (ADA) (applicable to offshore oil
development) is 30% of investment treated as 6 year linear depreciation.
When calculating the expected after tax cost and revenue cashflows the
tax effect of this depreciation amount is treated as a reduction in costs.
8) All calculations are in US dollars
9) Expected nominal cashflows (expected cost and expected revenue) were
calculated assuming a constant expected inflation rate of 2.0%.
10) The nominal risk free rate of return is assumed equal to 6.5%.
11) The expected oil price is assumed constant at a real $20US per barrel.
12) The market risk premium (E(Rm)-Rf) is assumed equal to 6%
13) The levered beta for the company is equal to 1 based on Statoil beta level.
Given a debt level of 30% and a marginal tax rate of 78% the unlevered
company beta is equal to 0.914 (assuming Copeland and Weston, 1992.
Pp. 459). This unlevered beta is used as the project beta to reflect busi-
ness risk.
14) The required rate of return for the oil projects is calculated to be nominal
11.98% =12% based on assumption 10, 12 and 13.
22
Results
A cashflow model was created using the Excel spreadsheet (version
5.0). Discounting based on one year periods was chosen for the
model because the data are annual. The cashflow results and NPV
calculated using the standard net cashflow discounting method
(396,4 million USD) are shown in Table 8.
With separate cashflow valuation the tax on revenue is the marginal
tax rate of 78%. The tax on the cost cashflow however, may not be
calculated independantly of revenues since the revenues of the
project determines when the costs can be recovered. The tax on cost
is then calculated based on the difference between tax on revenues
and tax on the whole project.
Using a discount rate of 8,3% (1,8% above the risk free rate) when
discounting the expeted after tax revenues gives a present value for
expected after tax revenues of 1214,4 million USD, while using a
discount rate of 7,2% (0,7% above the risk free rate) when
discounting the expected after tax cost gives a present value for the
expected after tax cost casflow of 532 million USD. This gives a
project net present value of 682,4 million, which is 286 million USD
higher than the NPV obtained using the standard net cashflow
discounting method. This example illustrate the large difference in
valuation that might occur when using a separate cashflow valuation
method. In this case it is the lower discounting of the revenues that
23
gives a high net present value of revenues which is only slightly
offset (compared to the standard net cashflow discounting method)
by the lower discounting of costs.
It is not reasonable to conclude that the separate cashflow method of
NPV is more correct than the NPV obtained using the standard net
cashflow discounting method. For the standard net cashflow
discounting method it is a question of how the required rate of return
for the individual project was obtained. For the separate cashflow
discounting method the question is if the ex post beta estimates
obtained for revenues and costs are reasonable approximations for
the ex ante betas. Is the cost risk in wage rates and steel prices (price
risk), for instance, representative for overall cost risk in the
companies? How should we effectively and objectively account for
volume risk and productivity risk, which were the main reasons for
cost overruns in the last decade on the NCS? In addition, the rate
used in calculating the present value of the expected after tax cost
cashflow does not reflect the uncertainty related to cost recovery
(depending on revenues) and, while the project required rate of
return might reflect a risk adjustment for government tax changes
(based on observed market beta for an oil company), it is not likely
that the rates used in discounting the separate cashflows include
such a risk adjustment. And how should discount factors be adjusted
to account for the recent tax changes? These are all reasons why the
implementation of a separate cashflow valuation method will be
24
difficult without more reaserch on market data related to the
required rates of return of individual cashflow streams.
6 Summary and further work
The results indicate that the present value of the expected after tax
cost cashflow stream of oil projects in the North Sea should be
calculated using a lower rate than that applied to the expected after
tax revenue stream. The size of the derived cost betas supports the
theoretical recommendations (Laughton and Jacoby, 1993), at least
to a first approximation, of using the risk free rate when calculating
the present value of the cost cashflow. However, there are reasons,
as exemplified by the large difference in net present value of the
example project valuation, that further work should be undertaken to
examine systematic risk of oil revenues as well as possible other
systematic risk factors in the cost cashflow of oil projects. One such
factor could be to examine the cost overruns and their correlation
with the value of the proxy for the market portfolio. To derive cost
betas we have used market prices of wage rates and steel prices. In
analyses of the recent cost overruns on development projects, major
factors explaining overruns were not input prices but rather volume
and productivity risk.7
In addition, for both the standard discounted net cashflow
valuation method and the separate cashflow valuation method, there
is the challenging issue of how to estimate the risk adjusted value of
7 See Emhjellen et al. (2002).
25
the tax effect of the cost cashflow when accounting the possible
delay or loss of the tax reduction.
26
References
Confederation of Norwegian Business and Industry, 1986-1995. Wages and attendance statistics, quarterly.
Copeland, T.E. and Weston, J.F. 1992. Financial Theory and Cor-porate Policy: Third Edition, Addison - Wesley. Pp. 457-459.
Emhjellen, M. and Alaouze, C. M. 2002 Project Valuation when There are Two Cashflow Streams , Energy Economics, Vol. 24, September, pp. 455-467.
Emhjellen, K., Emhjellen, M., Osmundsen, P. 2002. "Investment Cost Estimates and Investment Decisions", Energy Policy, vol. 30, pp. 91-96.
Jacoby, H. and Laughton, D. 1992. "Project Evaluation: a Practical Modern Asset Pricing Method", The Energy Journal, Vol. 13, pp. 19-47.
Johnsen, T. 1991. "Criteria for Profitable Investments in Oil Explo-rations: A Report to the Department of Oil and Energy", Norwegian School of Business, November
Lintner, J. 1965. "Security Prices, Risk and Maximal Gains from Diversification", Journal of Finance, Vol. 20, pp. 587-615.
Laughton, D. and Jacoby, H. 1993. "Reversion, Timing Options, and Long-Term Decision Making", Financial Management, Vol. 22, pp. 225-240.
Laughton, D. 1998 (1). "The Management of Flexibility in the Up-stream Petroleum Industry", The Energy Journal, Vol. 19, pp. 83-114.
Laughton, D. 1998 (2). "The Potential for Use of Modern Asset Pric-ing Methods for Upstream Petroleum Project Evaluation: Conclud-ing Remarks", The Energy Journal, Vol. 19, pp. 149-153.
27
Lewellen, W.G. 1977. "Some Observations on Risk-Adjusted Dis-count Rates", Journal of Finance, Vol. 32, pp. 1331-1337.
Lund, D. 1992. "Petroleum taxation under uncertainty - contingent claims analysis with an application to Norway", Energy Economics, 14, 23-31.
Metal Bulletin, 1986-1995. Prices and Data: Iron and Steel, Steel Reinforcing Bars, Brussels Bourse, Metal Bulletin Books Ltd.
NOU 2000: 18, Skattlegging av petroleumsvirksomhet (Taxation of the Petroleum Industry), Report by the Petroleum Tax Commission, delivered to the Ministry of Finance, 20 June 2000.
Osmundsen, P. 1999. "Risk Sharing and Incentives in Norwegian Petroleum Extraction", Energy Policy 27, 549-555.
Osmundsen, P. 1999a. Effektivitet, Insentiver og Proveny (Efficiency, Incen-tives and Revenue), Report for the Norwegian Ministry of Oil and Energy, scien-tific attachement to the annual government report on the Norwegian oil industry, Oljemeldingen, St.meld. nr. 39 (1999-2000), 9. June 2000.
Schall, L.D. 1972. "Asset Valuation, Firm Investment, and Firm Di-versification", Journal of Business, Vol. 45, pp. 11-28.
Sharpe, W. 1964. "Capital Asset Prices: A Theory of Capital Market Equilibrium under Conditions of Risk", Journal of Finance, Vol. 19, pp. 425-442.
Siew, Wei-Hun. 2001."The investment appraisal techniques used to assess risk in the oil industry" Conference Proceedings, 24th IAEE International Conference. April 25-27, 2001.
Standard & Poors. Platt's Prices and Data, 1986-1984, McGraw-Hill.
Statistics Norway. Monthly Bulletin of Statistics, 1986-1995.
28
Appendix
Cost data for example project
The cost data for the example project (project N in Emhjel-
len, 1999) were provided by Statoil and contains a division of the to-
tal investment cost into separate groups, see Table 1.
From the investment data presented in Table 1, two principal
cost classes can be identified. One class relates to the actual plan-
ning, building, and drilling, which is the "work hour" cost of the
project. The other class relates to the cost of materials required. For
the example project, 60% of the cost is related to the "work hour"
group, while 40% is specified as material costs.
We assume that Norwegian data on "work hour wages" re-
lated to the oil industry reflect the changes in the "work hour" cost
of the development over time. The second cost group, materials, is
to a large extent the cost of steel necessary to complete the project.
Consequently, the assumption is made that the cost of steel compris-
es the cost of materials.
Even though these assumptions are simplifications in that
work hours and steel do not constitute 100% of the cost of the
29
investment, they may reveal whether the rate of change of these two,
at least substantial cost factors, are correlated with the rate of return
of the proxy for the market portfolio over the period. The period
chosen is from 1986 through 19948.
Offshore industry work hour cost
The Norwegian quarterly "work hour cost" is obtained from The
Confederation of Norwegian Business and Industry "Wages and At-
tendance Statistics", 1986-1994. Data were collected for two sepa-
rate cost groups related to the Norwegian offshore industry.
The first group is data on the work hour wages of oil industry work-
ers performing specific tasks onshore, while the second group is the
work hour wages of oil industry workers offshore. The use of these
data as a measure of the cost to the oil companies for each work
hour is a simplification in that the overall cost of each work hour to
the oil companies is not identical to the work hour cost. Overhead
costs and employment taxes have to be added to the wage hour cost
to get the total hour cost. Because we are only interested in the
changes in work hour costs over time, however, it is likely that the
changes in wage hour costs would reflect the changes in the total
hour cost.
8 Consistent steel price data were not available before 1986.
30
The data on the wage hour cost are shown in Table 2. The wage hour
costs are denominated in Norwegian kroner (NOK, 1 krone=100
øre). The first column shows nominal offshore wage hour costs, the
second column shows nominal onshore wage hour costs, and the
third column shows the Consumer Price Index (CPI)(Monthly Bulle-
tin of statistics, Statistics Norway, 1986-1995). The fourth and fifth
columns show the real offshore and onshore wage hour costs, re-
spectively, where the real values have been calculated by deflating
the nominal values with the consumer price index.
Data on steel prices
The steel price data were obtained from the Metal Bulletin (Metal
Bulletin, 1986-1995).
The most consistent steel price data found are the data on monthly
export steel prices for reinforcing bars at Brussels Bourse. These da-
ta were therefore used to estimate the cost of steel to the oil industry.
Because 1986 was the first year when consistent steel price data
were available in the Metal Bulletin, quarterly averages were calcu-
lated from monthly data from that year.
The steel price data are presented in Table 3. The first column shows
the nominal price data in US dollars. The second column shows
quarterly averages of US/NOK exchange rate, while the third col-
umn shows the CPI. The fourth column shows real steel prices
31
quoted in Norwegian kroner using the monthly average NOK/USD
and the CPI, both data series obtained from Monthly Bulletin of Sta-
tistics. (Statistics Norway, 1986-1995, with quarterly averages cal-
culated from monthly data).
Data on the Total Index of the Oslo Stock Exchange
The Total Index is a value index of the stocks listed on "Børs 1" of
the Oslo Stock Exchange, with the value on 1 January 1983 given as
100. The monthly data on the Total Index of the Oslo Stock Ex-
change were obtained from the Monthly Bulletin of Statistics, Statis-
tics Norway. The monthly averages were used to calculate quarterly
averages for the period 1986 through 1994. The quarterly Total In-
dex averages were deflated using the consumer price index (all
goods and services) with quarterly averages calculated from monthly
data (Monthly Bulletin of statistics, 1986-1994). The quarterly Total
Index data are shown in Table 4.
Tables
Table 1. Investment Cost Data for The Example Project (Mil-
lions of 1994 USD)
32
Investment Cost for project N $US %of total
Project development costAdministration,management 74Project planning 84
FabricationProduction ship-deck 111production ship-body+hookup 101Under water installations 36
(Investment figures converted to USD)
Source: Statoil, Exploration & Production, Finance and Control, Financial Analy-
sis.
33
Table 2. Norwegian wage hour cost in the oil industry
Nominal Nominal Real (quarterly 1986 öre)Offshore Onshore Offshore Onshore
Workhour Workhour Workhour WorkhourQuarterly Cost Cost CPI Cost Cost
1986 13236 9966 177.0333 13236.00 9966.0013617 10331 180.3667 13365.35 10140.0713230 10217 185.7667 12608.03 9736.6713953 10289 189.1333 13060.34 9630.75
1987 14823 11367 194.7000 13477.99 10335.5815125 12342 197.8333 13534.77 11044.3715373 12130 200.4333 13578.25 10713.8615508 11683 203.2333 13508.77 10176.88
1988 16340 12062 208.3333 13885.08 10249.8116708 12206 211.9667 13954.42 10194.3815987 11762 213.6667 13246.02 9745.4016203 11644 215.5667 13306.65 9562.59
1989 16320 12101 218.2667 13236.95 9814.9717043 12184 221.9000 13597.02 9720.4816525 12353 223.3667 13097.19 9790.6016576 12074 224.7000 13059.66 9512.69
1990 16966 12277 227.7667 13186.95 9542.3917421 12756 230.3667 13387.78 9802.7917099 12863 231.8000 13059.07 9823.9018125 12457 234.8333 13663.86 9390.93
1991 17840 12655 236.5000 13354.23 9472.9718144 13048 238.9333 13443.47 9667.6818600 13404 239.9000 13725.80 9891.4318437 13437 241.0667 13539.67 9867.80
1992 18744 13276 242.2333 13698.83 9702.6118852 13651 244.7667 13635.16 9873.4118576 13327 245.7000 13384.50 9602.4618736 13500 246.4333 13459.61 9698.16
1993 19276 13642 248.4000 13737.90 9722.5819665 14041 250.8000 13881.02 9911.1819406 13962 250.6667 13705.49 9860.6619591 14014 251.1667 13808.60 9877.68
1994 19691 13850 251.5000 13860.69 9749.1519916 14090 253.2333 13923.11 9850.2019801 13968 254.6000 13768.41 9712.5019845 13714 255.7000 13739.64 9494.86
34
Source: Confederation of Norwegian Business and Industry. "Wages
and Attendance Statistics" quarterly, 1986-1995. The cost is given in
Norwegian øre (1NOK=100øre), and work hour overtime cost is in-
cluded. The nominal work hour costs are deflated using the consum-
er price index (all goods and services). The quarterly averages
shown in the Table were calculated from monthly data. (Monthly
Bulletin of Statistics, Statistics Norway, 1986-1995).
Table 3. Steel Prices (NOK per tonne)
35
Nominal 1986 NOK per tonne Steel Prices Steel Prices
reinforcing reinforcingQuarterly bars (US$) NOK/US$ CPI bars (NOK)
1986 231.273 7.32333 177.0333 1693.69242.917 7.51667 180.3667 1792.18234.420 7.38667 185.7667 1650.18237.397 7.47000 189.1333 1659.90
1987 245.870 7.03667 194.7000 1573.12251.388 6.71000 197.8333 1509.47256.402 6.72667 200.4333 1523.37261.250 6.47667 203.2333 1473.90
1988 270.525 6.36333 208.3333 1462.81283.645 6.25667 211.9667 1482.20289.628 6.83667 213.6667 1640.60320.553 6.61000 215.5667 1740.10
1989 335.208 6.72333 218.2667 1827.96283.519 7.01000 221.9000 1585.61289.792 7.03667 223.3667 1616.18291.111 6.84667 224.7000 1570.33
1990 288.148 6.53333 227.7667 1463.24277.917 6.48667 230.3667 1385.39283.333 6.15000 231.8000 1330.80295.000 5.86333 234.8333 1303.95
1991 295.000 5.97333 236.5000 1319.05283.542 6.75333 238.9333 1418.77273.518 6.81333 239.9000 1375.22270.000 6.39333 241.0667 1267.68
1992 270.000 6.35333 242.2333 1253.68267.381 6.30667 244.7667 1219.64251.852 5.79000 245.7000 1050.69247.222 6.39667 246.4333 1136.05
1993 254.101 6.95333 248.4000 1259.22275.000 6.84667 250.8000 1329.04278.518 7.25333 250.6667 1426.76274.583 7.32333 251.1667 1417.35
1994 270.556 7.45000 251.5000 1418.83277.708 7.21000 253.2333 1399.78280.000 6.84333 254.6000 1332.36282.500 6.73667 255.7000 1317.61
Source: Metal Bulletin, Prices & Data, Iron & Steel, Steel Reinforcing Bars, Ex-
port Price, Brussels Bourse, 1986 -1995. The nominal prices were deflated using
36
the consumer price index (all goods and services), with the quarterly averages
shown in the Table calculated from monthly data. (Monthly Bulletin of statistics,
Statistics Norway, 1986-1994).
Table 4. Total Index
37
Quarterly QuarterlyNominal values Real values (1986)
Total Index Total Index (Oslo S. E.) CPI (Oslo S. E.)
1986 292.000 177.0333 292.00274.667 180.3667 269.59282.000 185.7667 268.74290.667 189.1333 272.07
1987 293.667 194.7000 267.02324.000 197.8333 289.93384.333 200.4333 339.46302.000 203.2333 263.07
1988 269.667 208.3333 229.15288.667 211.9667 241.09286.667 213.6667 237.52304.000 215.5667 249.66
1989 407.333 218.2667 330.38485.000 221.9000 386.94516.000 223.3667 408.97500.333 224.7000 394.20
1990 599.667 227.7667 466.10620.667 230.3667 476.97611.333 231.8000 466.90483.000 234.8333 364.12
1991 457.333 236.5000 342.34500.000 238.9333 370.47506.333 239.9000 373.65436.667 241.0667 320.68
1992 428.000 242.2333 312.80432.333 244.7667 312.70344.000 245.7000 247.86361.000 246.4333 259.34
1993 409.333 248.4000 291.73479.333 250.8000 338.35549.000 250.6667 387.73601.333 251.1667 423.85
1994 670.333 251.5000 471.85625.000 253.2333 436.93629.667 254.6000 437.83628.667 255.7000 435.26
38
Source: Statistics Norway. "Monthly Bulletin of Statistics", Statis-
tics Norway 1986-1995). Quarterly averages which are shown in the
Table were calculated from monthly data. The nominal values were
deflated using the Consumer Price Index (all goods and services).
39
Table 5. Rate of change: Wage Hour Cost, Steel Prices, and the
Total Index
Quarterly real rate of change (%)Total Index Offshore Onshore Steel PricesOslo Stock work hour work hour reinforcingExchange cost cost bars
1986 -7.67 0.98 1.75 5.81-0.31 -5.67 -3.98 -7.921.24 3.59 -1.09 0.59
-1.86 3.20 7.32 -5.231987 8.58 0.42 6.86 -4.05
17.08 0.32 -2.99 0.92-22.50 -0.51 -5.01 -3.25-12.89 2.79 0.72 -0.75
1988 5.21 0.50 -0.54 1.33-1.48 -5.08 -4.40 10.695.11 0.46 -1.88 6.06
32.33 -0.52 2.64 5.051989 17.12 2.72 -0.96 -13.26
5.69 -3.68 0.72 1.93-3.61 -0.29 -2.84 -2.8418.24 0.97 0.31 -6.82
1990 2.33 1.52 2.73 -5.32-2.11 -2.46 0.22 -3.94
-22.01 4.63 -4.41 -2.02-5.98 -2.27 0.87 1.16
1991 8.22 0.67 2.06 7.560.86 2.10 2.31 -3.07
-14.18 -1.36 -0.24 -7.82-2.46 1.18 -1.67 -1.10
1992 -0.03 -0.46 1.76 -2.71-20.73 -1.84 -2.74 -13.85
4.63 0.56 1.00 8.1212.49 2.07 0.25 10.84
1993 15.98 1.04 1.94 5.5414.59 -1.26 -0.51 7.35
9.31 0.75 0.17 -0.6611.33 0.38 -1.30 0.10
1994 -7.40 0.45 1.04 -1.340.21 -1.11 -1.40 -4.82
-0.59 -0.21 -2.24 -1.11
40
Numbers are real percentage rate of change (average for quarter) from one quarter
to next quarter, with the numbers in first quarter of 1986 representing the rates of
change from the first quarter of 1986 to the second quarter of 1986. Rates of
change are rounded to two decimal points.
41
Table 6. Oil Price (WTI) and percentage change.
WTI Price Exchange rate CPI Real WTI price Real % change Real % changeUSD/barrel NOK/USD Index NOK per barrel WTI per barrel Total Index
1986 17,243 7,3233 1,0000 126,2800 -18,3971 -7,674513,967 7,5167 1,0188 103,0500 -5,5971 -0,314613,819 7,3867 1,0493 97,2800 10,7710 1,238515,411 7,4700 1,0684 107,7600 8,2916 -1,8565
1987 18,238 7,0367 1,0998 116,6900 -0,2608 8,581819,383 6,7100 1,1175 116,3900 4,1447 17,082720,401 6,7267 1,1322 121,2100 -13,1885 -22,505018,651 6,4767 1,1480 105,2200 -14,2683 -12,8923
1988 16,683 6,3633 1,1768 90,2100 -0,1873 5,210917,231 6,2567 1,1973 90,0400 -4,4330 -1,483015,191 6,8367 1,2069 86,0500 -6,5901 5,111814,807 6,6100 1,2177 80,3800 25,6671 32,3337
1989 18,523 6,7233 1,2329 101,0100 13,6798 17,117520,532 7,0100 1,2534 114,8300 -6,2915 5,693219,294 7,0367 1,2617 107,6000 2,0113 -3,611520,349 6,8467 1,2693 109,7700 0,7774 18,2397
1990 21,784 6,5333 1,2866 110,6200 -19,9907 2,333817,755 6,4867 1,3013 88,5100 39,0986 -2,112826,211 6,1500 1,3094 123,1100 15,5274 -22,012932,177 5,8633 1,3265 142,2300 -30,9684 -5,9813
1991 21,958 5,9733 1,3359 98,1800 5,8623 8,216020,772 6,7533 1,3497 103,9400 4,7582 0,858621,656 6,8133 1,3551 108,8800 -6,0795 -14,176421,781 6,3933 1,3617 102,2600 -14,2080 -2,4568
1992 18,895 6,3533 1,3683 87,7300 10,2897 -0,033021,213 6,3067 1,3826 96,7600 -6,6441 -20,734021,653 5,7900 1,3879 90,3300 4,2685 4,629620,497 6,3967 1,3920 94,1900 4,3272 12,4910
1993 19,829 6,9533 1,4031 98,2600 -2,9042 15,980419,742 6,8467 1,4167 95,4100 -4,4361 14,595017,799 7,2533 1,4159 91,1800 -6,9918 9,314416,429 7,3233 1,4188 84,8000 -8,2747 11,3268
1994 14,833 7,4500 1,4206 77,7900 15,6529 -7,401017,848 7,2100 1,4304 89,9600 -2,2839 0,205918,474 6,8433 1,4382 87,9100 -6,3276 -0,588317,655 6,7367 1,4444 82,3400
42
WTI prices obtained from Standard & Poors Platt's Prices and Data. The CPI was
calculated using the consumer price numbers given in Table 3.
43
Table 7. Oil Project Data.
Production Real inve- Real oper-
YEAR stment cost ating cost
Mill. barrels Mill USD MUSD
13,7%
4,7%
Sum 442,4 1402,9 1533,3
0 0,00 28,60 0,90
1 0,00 417,10 10,30
2 0,00 588,60 20,40
3 0,00 257,90 41,80
4 55,50 72,10 115,80
5 57,10 38,60 120,20
6 56,80 0,00 119,50
7 54,00 0,00 117,90
8 46,40 0,00 113,60
9 37,80 0,00 109,40
10 30,80 0,00 105,70
11 24,20 0,00 102,30
12 20,30 0,00 100,00
13 16,50 0,00 97,90
14 13,80 0,00 96,30
15 10,80 0,00 87,70
16 9,60 0,00 87,00
17 8,80 0,00 86,60
44
Table 8. Project Cashflows and WACC method for calculating
NPV
Nominal Total Tax Total Tax on Tax on Revenue Cost Net CF. payments Cashflow revenue cost Cashflow Cashflow
before tax after tax cashflow cashflow after tax after tax 0 -29,5 0,0 -29,5 0,0 0,0 0,0 -29,5 1 -435,9 0,0 -435,9 0,0 0,0 0,0 -435,9 2 -633,6 0,0 -633,6 0,0 0,0 0,0 -633,6 3 -318,0 0,0 -318,0 0,0 0,0 0,0 -318,0 4 998,1 111,7 886,4 937,2 -825,5 264,3 622,1 5 1085,5 653,5 432,0 983,5 -329,9 277,4 154,6 6 1144,7 670,9 473,8 997,9 -327,0 281,5 192,4 7 1105,2 706,0 399,2 967,7 -261,7 272,9 126,2 8 954,2 683,2 271,0 848,1 -164,9 239,2 31,8 9 772,7 584,0 188,7 704,7 -120,7 198,8 -10,1
10 622,1 478,6 143,5 585,7 -107,1 165,2 -21,7 11 474,6 370,2 104,4 469,4 -99,2 132,4 -28,0 12 388,1 302,7 85,4 401,6 -98,9 113,3 -27,9 13 300,2 234,2 66,1 333,0 -98,8 93,9 -27,9 14 237,1 184,9 52,2 284,1 -99,1 80,1 -28,0 15 172,7 134,7 38,0 226,8 -92,1 64,0 -26,0 16 144,1 112,4 31,7 205,6 -93,2 58,0 -26,3 17 125,2 97,6 27,5 192,2 -94,6 54,2 -26,7
18
0,0
0,0
0,0
0,0
0,0
0,0
0,0
19
0,0
0,0
0,0
0,0
0,0
0,0
0,0
20
0,0
0,0
0,0
0,0
0,0
0,0
0,0
21
0,0
0,0
0,0
0,0
0,0
0,0
0,0
22
0,0
0,0
0,0
0,0
0,0
0,0
0,0
23
0,0
0,0
0,0
0,0
0,0
0,0
0,0