Page 1 of 2 - Uttar Pradesh ( JJM - UP )

99
Page 1 of 2 Ref.: MTCPL/SWSM/TPI-Cluster 09/2021-22/15500 Date: 13.01.2022 To, The Executive Engineer 10 th Division, U.P Jal Nigam, Gorakhpur, Uttar Pradesh Sub: Third Party Inspection and Monitoring of Physical and Financial Progress of various Rural Water Supply Projects for Cluster-09 – Gorakhpur (Revenue Division), Uttar Pradesh: Verification of 2nd Installment of Mobilization Advance for Contractor M/s. NCC Limited for Cover Agreement. 216/ED/2021-22/4 dated 15.12.2021 for Gorakhpur District-Reg. References: 1. LOA No. 2717/W-23/NIT/2020-21 dated 05.03.2021 2. LOI No. 2144/W-22/NIT/2020-21, dated 13.01.2021 3. Agreement No. 67/ED/2020-21 dated 12.03.2021 4. Cover Agreement No. 216/ED/2021-22/IV dated 15.12.2021 5. Letter No. 3332/W-22 (NCC Gorakhpur)/2021-22 dated 28.12.2021 6. MTCPL/SWSM/TPI-Cluster 09/2021-22/14829 dated 04.01.2022 7. Letter No. NCC/SWSM UP-GKP/065 dated 11.01.2022 Sir, This is with reference to the aforementioned subject and referred letter, wherein TPIA was asked to submit observation on the request of TKC, M/s NCC Limited for release of 2nd Mobilization Advance i.e., 5% of agreement value in Gorakhpur District. In reference to the above, we have submitted our observations vide letter no.- MTCPL/SWSM/TPI- Cluster 09/2021-22/14829, Date: 04.01.2022 (enclosed), mentioning the status of establishment of site office, labs and mobilization of resources, which reflects that the requisite conditions for release of 2nd installment of Mobilization advance are not yet fulfilled. In view of the aforementioned, TKC has submitted a letter requesting to release 2 nd installment of 5% amount of Mobilization Advance, assuring that all the shortcomings/observations marked in TPIA report with respect to Site offices, Labs & mobilization of Key personnel will be attended by them till 15.02.2022. In light of the above observations, UPJN may take judicious decision regarding the release of 2nd installment of Mobilization advance. Thanking you and assuring our best services at all times. Yours Faithfully Gopal Verma TL – Gorakhpur Cluster Medhaj Techno Concept Private Limited

Transcript of Page 1 of 2 - Uttar Pradesh ( JJM - UP )

Page 1 of 2  

Ref.: MTCPL/SWSM/TPI-Cluster 09/2021-22/15500 Date: 13.01.2022

To, The Executive Engineer 10th Division, U.P Jal Nigam, Gorakhpur, Uttar Pradesh

Sub: Third Party Inspection and Monitoring of Physical and Financial Progress of various Rural Water Supply Projects for Cluster-09 – Gorakhpur (Revenue Division), Uttar Pradesh: Verification of 2nd Installment of Mobilization Advance for Contractor M/s. NCC Limited for Cover Agreement. 216/ED/2021-22/4 dated 15.12.2021 for Gorakhpur District-Reg.

References:

1. LOA No. 2717/W-23/NIT/2020-21 dated 05.03.2021 2. LOI No. 2144/W-22/NIT/2020-21, dated 13.01.2021 3. Agreement No. 67/ED/2020-21 dated 12.03.2021 4. Cover Agreement No. 216/ED/2021-22/IV dated 15.12.2021 5. Letter No. 3332/W-22 (NCC Gorakhpur)/2021-22 dated 28.12.2021 6. MTCPL/SWSM/TPI-Cluster 09/2021-22/14829 dated 04.01.2022 7. Letter No. NCC/SWSM UP-GKP/065 dated 11.01.2022

Sir,

This is with reference to the aforementioned subject and referred letter, wherein TPIA was asked to submit observation on the request of TKC, M/s NCC Limited for release of 2nd Mobilization Advance i.e., 5% of agreement value in Gorakhpur District. In reference to the above, we have submitted our observations vide letter no.- MTCPL/SWSM/TPI-Cluster 09/2021-22/14829, Date: 04.01.2022 (enclosed), mentioning the status of establishment of site office, labs and mobilization of resources, which reflects that the requisite conditions for release of 2nd installment of Mobilization advance are not yet fulfilled.

In view of the aforementioned, TKC has submitted a letter requesting to release 2nd installment of 5% amount of Mobilization Advance, assuring that all the shortcomings/observations marked in TPIA report with respect to Site offices, Labs & mobilization of Key personnel will be attended by them till 15.02.2022.

In light of the above observations, UPJN may take judicious decision regarding the release of 2nd installment of Mobilization advance.

Thanking you and assuring our best services at all times.

Yours Faithfully

Gopal Verma TL – Gorakhpur Cluster Medhaj Techno Concept Private Limited

Page 2 of 2  

Encl. As above CC: i) Executive Director, SWSM Lucknow ii) Unit Coordinator (T), SWSM Lucknow iii) Chief Development Officer (CDO), Vikas Bhawan, Gorakhpur, Uttar Pradesh iv) Executive Engineer (Construction Division- E&M office) U.P. Jal Nigam, Gorakhpur, Uttar Pradesh

v) Project Manager, M/s. NCC limited, Gorakhpur, Uttar Pradesh

Page 1 of 3  

Ref.: MTCPL/SWSM/TPI-Cluster 09/2021-22/14829 Date: 04.01.2022

To, Executive Director State Water and Sanitation Mission, U.P Jal Nigam Compound, 6 Rana Pratap Marg, Lucknow- 226001

Sub: Third Party Inspection and Monitoring of Physical and Financial Progress of various Rural Water Supply Projects for Cluster-09 – Gorakhpur (Revenue Division)- Verification of 2nd Installment of Mobilization Advance for Cover Agreement No. 216/ED/2021-22/4 dated 15.12.2021 of TKC, M/s. NCC Limited for Gorakhpur District-Reg.

Ref.:

1. LOA No.:2717/W-23/NIT/2020-21 dated 05.03.2021 2. LOI No.: -2144/W-22/NIT/2020-21, dated 13.01.2021 3. Agreement no: 216/ED/2021-22/IV, dated 15.12.2021 4. Letter No. 3332/W-22 (NCC Gorakhpur)/2021-22 dated 28.12.2021

Sir,

This is with reference to the aforementioned subject and referred letter, wherein, TPIA has been asked to submit observation on the request of TKC, M/s NCC Limited for release of 2nd Mobilization Advance i.e., 5% of agreement value in Gorakhpur District. With reference to above cited subject and references, we have gone through the contract agreement number- 216/ED/2021-22/IV, dated 15.12.2021 for 79 Gram Panchayat having value of 184.23 Cr and O&M cost of 46.32 Cr. (Total value of Agreement 230.55 Cr)

With reference to the minutes of pre-bid meeting dated 22.09.2020 Mobilization advance is to be given in two parts, i.e., Part-1: 5% of agreement value after signing of the multipartite agreements and Part-2: 5% of agreement value after establishment of site office, mobilization of resources. And as we have been informed, that TKC has already been paid 1st Mobilization Advance (5% of agreement value) on account of signing the multipartite agreements & submission of Advance Bank Guarantee of any nationalized bank equivalent to 110%. Second Installment of 5% would be released after establishment of site office and mobilization of resources.

With reference to the above, TPIA had visited site office and verified the Precast/Stocking yard, Manpower deployment at site, Tools & Plants & machineries wherein following observations were noted: -

Site/District Office:

1. As per Special Term and Conditions of the contract 7.1.c (Page no- 80) Site offices as well district offices should be set up immediately on receipt of work order.

2. 1 No of District Office & 2 nos. of site office have been set up.

Page 2 of 3  

3. District Office: - Plot No.287 and 412, Rudrapur, Kusmi Bazar, Gorakhpur Pin code: 273002. Validity of this agreement is 01.03.2021 to 28.02.2024.

4. Sahjanwa Site office: - Plot No.337 & 338, Semra (Village), Tahsil- Sahjanwa, Gorakhpur, U.P Pin code: 273209. Validity of this agreement is 01.07.2021 to 30.06.2023

5. Gola Site office: - Plot No.151 & 152, Deidhiha, Tahsil- Gola, Gorakhpur. Pin code: -273409. Validity of this agreement is 20.08.2021 to 19.08.2023.

6. Agreements of the office are attached for your further perusal. 7. Site office is to be established in each block of district which is not done,

Precast/Stocking Yard:

1. Precast/Stocking Yard has been set up at Plot No.287 and 412, Rudrapur, Kusmi Bazzar, Gorakhpur Pin code: 273002 and Plot No.151 & 152, Deidhiha, Tahsil- Gola, Gorakhpur. Pin code: -273409.

2. Agreement of the Precast/Stocking Yard is attached for your further perusal. The Agreement is of 36 months, ending on 28.02.2024 and of 24 months, ending on 19.08.2023.

3. The Land demarcation & Boundary works has been completed. 4. Construction work at Stocking Yard is in progress. 5. Labs are not established in blocks.

Tools & Plants & Machinery:

1. 2 Diesel Generator (7.5 KVA Capacity) are available at nearby Stocking Yard. 2. Rig Machine with Compressor unit (In attached List) available. 3. All the required Tool, plants and Machineries are not available,

Manpower Deployment:

1. Manpower Deployment is done at the site however it is not as per RFP. List of Deployment is attached.

2. Date of Joining of Manpower has been provided.

General Observation:

1. BG details mentioned below-

S.N Name of Bank BG Number & Date of Issue Date of Expiry

GURANTEE AMOUNT

1 UNION BANK OF INDIA 75200IGL0026221 DT. 21-12-2021 20.09.2022 ₹ 4,00,00,000.00

2 UNION BANK OF INDIA 75200IGL0026321 DT. 21-12-2021 20.09.2022 ₹ 4,00,00,000.00

3 UNION BANK OF INDIA 75200IGL0026421 DT. 21-12-2021 20.12.2022 ₹ 4,02,67,000.00

4 UNION BANK OF INDIA 75200IGL0026521 DT. 21-12-2021 20.12.2022 ₹ 4,00,00,000.00

Page 3 of 3  

In light of the above observations made by TPIA and all conditions required for release of 2nd installment of Mobilization advance, judicious decision regarding the same may be taken by UPJN.

Appropriate deductions /withholding of amount on account of above observations may be considered before release of payment as deemed fit by UPJN,

Thanking you and assuring our best services at all times.

Yours Faithfully

Gopal Verma TL – Gorakhpur Cluster Medhaj Techno Concept Private Limited CC: i) Unit Coordinator (T), SWSM Lucknow ii) Chief Development Officer (CDO), Vikas Bhawan, Gorakhpur, Uttar Pradesh iv) Executive Engineer, 10th Division, U.P. Jal Nigam, Gorakhpur, Uttar Pradesh

v) Project Manager, M/s. NCC limited, Gorakhpur, Uttar Pradesh

Enclosures:

1. LEASE AGREEMENT 2. OFFICE DETAILS 3. QC LAB & STAFF MESS 4. RIG MACHINE DETAILS 5. STAFF DETAILS 6. STAFF GUEST HOUSE LEASE AGREEMENT 7. STORE AND YARD DETAILS 8. VEHICLES DETAILS 9. BG DETAILS

5 UNION BANK OF INDIA 75200IGL0026621 DT. 21-12-2021 20.03.2023 ₹ 4,23,86,000.00

Kushmi Main Office Photographs 

 

 

 

QC Lab & Staff Mess Photographs 

 

 

 

R.I.G Machine Photographs 

 

 

 

 

 

Store & Yard Photographs 

 

 

 

SL NO. Employee Name Designation Educational

Qualification No of years of

experience Nof of Years employed

with the firm Date of joining for

SWSMUP-GKP-Project Task Assigned

1 R V S N RAJU Project Executive Complete Monitoring

2 SAROJ KUMAR JENA Deputy General Manager (TECH) B E Civil Engineering 24 Years 11.3 Years 1-14-2021 Complete Monitoring

3 S RAGHAVENDAR Deputy General Manager (TECH) B.TECH 32 Years 04 Years 7-1-2017 Complete Monitoring

4 V S N V K M V PRASAD Senior Project Manager B.TECH-CIVIL 30 Years 26 Years 2-1-2021 Complete Monitoring

5 DOMBER VENKATESH SPM(Tech) Diploma in Civil. Engg. 27 Years 1 Month 11-26-2021 Monitoring of Civil Works

6 SUNIL KUMAR K Deputy Project Manager (Civil) B.TECH 18 Years 12 Days 11-26-2021 Monitoring of Civil Works

7 SANJAY KUMAR SINGH Deputy Project Manager (Elec.) B.TECH 15 Years 01 Years 2-10-2021 Monitoring of Elec. Works

8 DEEPJYOT Deputy Project Manager (QS) B.TECH 10 Years 07 Years 1-6-2014QS & Planning related

works

9 SANJEEV KUMAR Junior Engineer Diploma in Civil. Engg. 06 Years 06 Years 14-01-2021 Site Engineer

10 ANUJ KUMAR Junior Engineer Diploma in Civil. Engg. 06 Years 01 Years 02/01/2021 Site Engineer

11 YOGENDRA PRASAD Junior Engineer Diploma in Civil. Engg. 04 Years 01 Years 04/01/2021 Site Engineer

12 SUBHA PAUL Junior Engineer Diploma in Civil. Engg. 06 Years 01 Years 18/01/2021 Site Engineer

13 BISWANIL CHAKRABARTY Assistant Engineer B-Tech civil 08 Years 01 Years 18/01/2021 Site Engineer

14 JAGADEESH GONNABATTULA Junior Engineer Diploma in Civil. Engg. 7 Years 01 Years 21/01/2021 Site Engineer

15 KAPIL RAI Assistant Engineer B-Tech civil/ MBA 7 Years 01 Years 04/03/2021 Site Engineer

16 SHAH AMIR NAWAB Junior Engineer B-Tech civil 04 Years 01 Years 08/04/2021 Site Engineer

17 MOHAN REDDY NAKKA Foreman ITI 13 Years 13 Years 08-06-2021 Foreman

18 VEER VICHITRA Junior Engineer Diploma in Civil. Engg. 08.9 YEARS 06.9 YEARS 08-06-2021 Site Engineer

19 RAHUL SHANKAR UPADHAYA Assistant Engineer B-Tech 4.9 Years 12 Days 26-11-2021 Site Engineer

20 Sudip Sasmal  Surveyor supervisor ITI 4.5 Years 03 Years 19-11-2021 Surveyar

NCC LTD SWSMUP‐GORAKHPUR PROJECT 

Team Composition and task assigned 

SL NO. Employee Name Designation Educational

Qualification No of years of

experience Nof of Years employed

with the firm Date of joining for

SWSMUP-GKP-Project Task Assigned

21 VEDALA VENKATA ARAVIND Assistant Engineer (QS) BE-Civil 06 Years 01 Years 03/03/2021 Planning

22 BOKKA SHIVANNARAYANA Assistant Engineer (QS) B-Tech civil 08 Years 01 Years 19/03/2021 QS-Engg.

23 GAJENDRA SINGH Junior Engineer (QS) Diploma in Civil. Engg. 08 years 04 Years 14-01-2021 QS-Engg.

24 PRADEEP SINGH Junior Engineer (QS) B-Tech civil 06 Years 09 Month 26-04-2021 QS-Engg.

25 ATISH ROY CHOUDHARI Junior Engineer (QS) M-Tech 04 Years 04 Years 07-06-2021 Site Engineer

26 Mr.Sandip Karan  Assistant Engineer (QS Diploma in Civil. Engg. 10 Years 04 Month 20-09-2021 QS-Engg.

27 Mr. Shubham suresh parate  Assistant Engineer (QS)  PG-DIPLOMA IN NICMAR 06 Years 03 Month 20-09-2021 QS-Engg.

28 SAMARAT SNEHASISH MITRA Junior Engineer (Piping) Diploma in Mech. Engg. 7 Years 02 Years 01/06/2021 E&M Engineer

29 AMIT KUMAR Junior Engineer (Piping) Diploma in Mech. Engg. 08 Years 02 yEARS 01/07/2020 E&M In-Charge

30 MD ARSHAD ALAM Junior Engineer (Piping) Diploma in Mech. Engg. 10 YEARS 2.9 Years 01-12-2021 E&M In-Charge

31 SUMAN MAITY Junior Engineer (Quality Control) B-Tech 3.4 Years 11 Months 14-01-2021 QC Activities

32 JITENDRA MAURYA Helper B.A 05 Years 3.7 Years 14-01-2021 QC-Hepler

33 KAJAL GHOSH Senior Asst Accounts B-COM. 8 Years 6 Month 24/06/2021 Accounts

34 RAJNI KANT RANJAN Senior Asst Accounts B-COM. 07Years 04 Month 16/08/2021 Accounts

35 AKHNAD RAJ SINGH Senior HR-Asst. MBA-HR/IR 10 YEARS 04 YEARS 14-01-2021 HR/ADMIN Activites

36 SUJEET KUMAR Assistant (Administration) 12th 7 Years 7 Years 01/03/2019 Admin Asst.

37 KRISHNA PRATAP Assistant (Administration) B-COM. 03 years 03 years 01-06-2021 Admin Asst.

38 Dileep Kumar Driver 12th 3.5 Years 3.5 Years 01/08/2019 Driving

39 VISHWANATH PRATAP SINGH Senior Asst.EDP MCA 07 Years 07 Month 31-03-2021 EDP Dep.

40 SURESH RAJU JAMPANASenior Assistant (Resource

Mobilisation)ITI 15 Years 15 Years 01/11/2010 R&M Incharge

41 CH DURGA RAO Deputy Manager (store) BSC 25 Years 25 Years 06-09-2021 Store

SL NO. Employee Name Designation Educational

Qualification No of years of

experience Nof of Years employed

with the firm Date of joining for

SWSMUP-GKP-Project Task Assigned

42 KASUKURTHI VENKATA RAMAIAH Officer -store B-COM. 15 Years 3 Years 13/05/2019 Store

43 M, SRINIVAS RAO Officer -store B-COM. 10 Years 06 Month 19-04-2021 Store

44 SATISH KUMAR SINGH Assistant Stores 12th 3 Years 3 Years 13-04-2021 Store

45 SUBHAM CHOURASIA Officer -store (Material ) Diploma in Mech. Engg. 03 Years 01 Month 06-11-2021 Materials

46 NARAYAN CHANDRA MAITY Assistant Engineer B.Tech 06 Years 11 Months 04-01-2021 Civil Activities

47 RAJANI KUMAR SAHU Assistant Engineer B.Tech 06 Years 05 Months 11 Months 25-01-2021 Civil Activities

48 SHAILENDRA SINGH RAWAT Assistant Engineer B.Tech 06 Years 11 Months 03-03-2021 Civil Activities

49 UTKARSH THAPAN Junior Engineer B.Tech 04 Years 11 Months 25-01-2021 Civil Activities

50 ANKIT Supervisor(Projects) Diploma 03 years 11 Months 15-02-2021 Civil Activities

51 POLAKI OMSANKAR Assistant Engineer B.Tech 08 Years 08 Months 03-06-2021 Civil Activities

52 BALARAM GORAI Junior Engineer B.Tech 05 Years 05 Months 09-06-2021 Civil Activities

53 RAJNEESH PANDEY Junior Engineer B.Tech 04 Years 04 Months 29-06-2021 Civil Activities

54 AJAY KUMAR Junior Engineer B.Tech 04 Years 05 Months 03 Months 26-07-2021 Civil Activities

55 MD ABDULLAH ANSARI Assistant Engineer B.Tech 06 Years 04 Months 02-08-2021 Civil Activities

56 ROHIT KUMAR CHAURASIA Junior Engineer B.Tech 03 years 02 Months 27-09-2021 Civil Activities

57 ANKIT ASHOK SALUNKHE Junior Engineer B.Tech 03 years 02 Months 01-10-2021 Civil Activities

58 SANY ANIL KAMBLE Junior Engineer B.Tech 03 years 15 Days 23-11-2021 Civil Activities

59 MD MAHTAB Graduate Engineer Trainee B.Tech - 02 Months 21-10-2021 Civil Activities

60 ASHISH KUMAR RANJAN Manager (QS & Planning) B.Tech 11 Years 08 Months 05-04-2021 QS & Planning

61 MANDAPATI SANDEEP VARMA Junior Engineer B-Tech Civil 03 years 10 Months 07-02-2021 Planning

62 G. SYAM PRASAD Senior Engineer (QS) B-Tech Civil 08 Years 01 Month 30.11.2021 Quantity Survey

SL NO. Employee Name Designation Educational

Qualification No of years of

experience Nof of Years employed

with the firm Date of joining for

SWSMUP-GKP-Project Task Assigned

63 ABDULHAMEED ADDULSAMAD Junior Engineer (QS) B.Tech 04 Years 11 Months 08-02-2021 Quantity Survey

64 SACHIN VILAS GARAD Junior Engineer (QS) B.Tech 03 years 11 Months 22-03-2021 Quantity Survey

65 JAY SHANKAR TIWARI Junior Engineer (QS) B-Tech Civil 04 Years 02 Months 22-10-2021 Quantity Survey

66 RAM PRAVESH KUMAR Junior Engineer (QS) B-Tech Civil 07 Years 02 Months 19-10-2021 Quantity Survey

67 KULDEEP KUMAR MISHRA Assistant Engineer (QA/QC) B.Tech 05 Years 11 Months 30-12-2020 Quality Control

68 DEEPAK KUMAR TOMAR Junior Engineer (QA/QC) B-Tech Civil 02 Years 02 Months 27-09-2021 Quality Control

69 MISBAH KHAN Assistant Engineer (MEP) B.Tech 05 Years 05 Months 01-07-2021 MEP Activities

70 AMIT KUMAR Junior Engineer (MEP) B.Tech 05 Years 05 Months 01-04-2021 MEP Activities

71 MADDALA SINGA RAO Deputy Manager (Accounts) MBA-Finance (ICWA) 16 Years 03 Years 01-02-2021 Accounts Activities

72 SUBHASH TIWARI SR Assistant (Accounts) M.Com (Accounts) 04 Years 01 Months 18-10-2021 Accounts Activities

73 SWETANSHU VERMA Assistant (Accounts) B.Com (Accounts) - 09 Months 17-03-2021 Accounts Activities

74 V VENKAT RAO Assistant Manager (Store) B.Sc (Computers) 17 Years 01 Months 15 Days 18-10-2021 Store Activities

75 ABHIJIT MAITI Officer Stores BA 05 Years 03 Years 01-02-2021 Store Activities

76 M RAMA KRISHNA SR Assistant (Stores) BA 11 Years 11 Years 01-05-2010 Store Activities

77 PATIL SHARAD SHRIRAM Officer Stores BA 13 Years 07 Years 25-02-2021 Store Activities

78 PRAMOD KUMAR SR Assistant (Stores) BA 05 Years 11 Months 16-03-2021 Store Activities

79 RAVINDRA KUMAR YADAV SR Assistant (Stores) BA 06 Years 03 Years 19-10-2021 Store Activities

80 CH SURESH Assistant Manager (Materials) MBA- MKTG/HR 15 Years 14 Years 12-03-2021 Material Activities

81 ANAND PRASAD SINGH SR Assistant (Admin) B.Sc (Chemistry) 7 Years 05 Months 08 Months 01-04-2021 ADMIN Activites

82 MOHAMMAD FAROOQUE AHMAD Officer (Saftey) B.Tech 04 Years 11 Months 28-02-2021 Safety Activities

83 T S K PRAVEEN AM (EDP) M.Com- Commerce 17 Years 06 Months 14 Years 06 Months 19-06-2007 EDP Activities

SL NO. Employee Name Designation Educational

Qualification No of years of

experience Nof of Years employed

with the firm Date of joining for

SWSMUP-GKP-Project Task Assigned

84 SHABBIR AHMAD SR Assistant (EDP) B.Sc 05 Years 08 Months 01-04-2021 EDP Activities

85 PAWAN TYAGI SR ASSISTANT (SAFETY) B.Sc (Nursing) 06 Years 03 Years 04-05-2021 Safety Activities