Modification and Revision Project-Residential Colony “Jewel ...
-
Upload
khangminh22 -
Category
Documents
-
view
3 -
download
0
Transcript of Modification and Revision Project-Residential Colony “Jewel ...
Modification and Expansion of Group Housing Project “Atharva Group Housing” at Sec-
109, Village PawalaKhusrupur, Gurugram, Haryana
EIA-EMP REPORT
M/s Raheja Developers Ltd. Page 1
TABLE OF CONTENTS
LIST OF TABLE ................................................................................................................ 7
LIST OF FIGURE .............................................................................................................. 9
CHAPTER 1:INTRODUCTION ...................................................................................... 10
1.1 INTRODUCTION ..................................................................................................................... 10
1.2 IDENTIFICATION OF PROJECT & PROJECT PROPONENT ................................................ 10
1.3 DEVELOPMENT STRATEGY OF THE PROJECT .................................................................. 11
1.4 NECESSITY AND BENEFITS OF PROJECT ........................................................................... 12
1.5 LEGISLATION, POLICY AND GUIDELINES OF BUILDING CONSTRUCTION ................. 12
1.6 NEED FOR EIA STUDY ........................................................................................................... 15
1.7 PURPOSE OF THE STUDY...................................................................................................... 16
1.8 OBJECTIVES OF EIA STUDY ................................................................................................. 16
1.9 PROCESS OF OBTAINING ENVIRONMENT CLEARANCE ................................................. 17
1.10 TOR COMPLIANCE ............................................................................................................... 17
1.11 STRUCTURE OF ENVIRONMENTAL IMPACT ASSESSMENT REPORT .......................... 20
CHAPTER 2 :PROJECT DESCRIPTION ...................................................................... 22
2.1 TYPE OF PROJECT .................................................................................................................. 22
2.1.1 DETAILS OF VIOLATION .................................................................................................... 22
2.2 PROJECT SITE LOCATION AND CONNECTIVITY .............................................................. 24
2.3 LAYOUT PLAN OF THE PROJECT ........................................................................................ 27
2.4 LAND USE PLAN OF THE PROJECT SITE ............................................................................ 29
2.5 BASIC AMENITIES ................................................................................................................. 30
2.5.1 Water Requirement ................................................................................................................. 30
2.5.2 Waste Water Treatment System ............................................................................................... 34
2.5.3 Power Requirement ................................................................................................................. 37
2.5.4 Storm Water Management System ........................................................................................... 37
2.5.5 PARKING FACILITIES ..................................................................................................... 39
2.5.6 SOLID WASTE MANAGEMENT FACILITY ................................................................... 39
2.5.7 Green Belt Development ..................................................................................................... 41
2.5.8 FIRE FIGHTING SYSTEM ................................................................................................ 42
2.6 DETAILS OF CONSTRUCTION MATERIALS ................................................................... 43
CHAPTER 3 :DESCRIPTION OF ENVIRONMENT .................................................... 45
3.1 GENERAL ................................................................................................................................ 45
Modification and Expansion of Group Housing Project “Atharva Group Housing” at Sec-
109, Village PawalaKhusrupur, Gurugram, Haryana
EIA-EMP REPORT
M/s Raheja Developers Ltd. Page 2
3.2 STUDY AREA & PERIOD ....................................................................................................... 45
3.3 DESCRIPTION OF SITE........................................................................................................... 47
3.4 ENVIRONMENT & SOCIAL SETTINGS OF THE STUDY AREA...................................... 47
3.5 METEOROLOGY ................................................................................................................. 49
3.5.1 CLIMATE & TEMPERATURE .......................................................................................... 49
3.5.2 WIND PATTERN ............................................................................................................... 51
3.5.3 RAINFALL & HUMIDITY ................................................................................................ 52
3.5.4 MICRO-METEOROLOGY AT SITE .................................................................................. 52
3.6 LAND ENVIRONMENT ....................................................................................................... 53
3.6.1 TOPOGRAPHY AND TERRAIN ....................................................................................... 53
3.6.2 LAND USE ......................................................................................................................... 55
3.6.3 NATURAL DISASTERS .................................................................................................... 58
3.6.4 GEOMORPHOLOGY ......................................................................................................... 58
3.6.5 SOIL ................................................................................................................................... 59
3.6.5.1 OBSERVATIONS ............................................................................................................ 60
3.7 WATER ENVIRONMENT .................................................................................................... 60
3.7.1 DRAINAGE ........................................................................................................................ 60
3.7.2 HYDRO-GEOLOGY .......................................................................................................... 62
3.7.3 GROUND WATER AND SURFACE WATER QUALITY ................................................. 64
3.8 AIR ENVIRONMENT ............................................................................................................... 67
3.8.1 OBSERVATIONS OF AMBIENT AIR QUALITY MONITORING ................................... 67
3.9 NOISE ENVIRONMENT .......................................................................................................... 70
3.10 TRAFFIC DENSITY ............................................................................................................... 71
3.11 BIOLOGICAL ENVIRONMENT ............................................................................................ 71
3.11.1 FLORA &FAUNA IN CORE ZONE ................................................................................. 72
3.11.2 FLORA & FAUNA IN BUFFER ZONE............................................................................ 72
3.12 SOCIOECONOMIC ENVIRONMENT ................................................................................ 73
3.12.1 DEMOGRAPHICS OF GURUGRAM DISTRICT ............................................................ 73
CHAPTER 4 :IMPACT IDENTIFICATION AND ASSESSMENT .............................. 75
4.1 GENERAL............................................................................................................................. 75
4.2 IMPACT IDENTIFICATION ................................................................................................ 75
4.3 ANALYSIS OF IMPACTS DURING CONSTRUCTION PHASE ......................................... 76
4.3.1 LAND ENVIRONMENT .................................................................................................... 76
4.3.1.1 LAND USE PATTERN, DRAINAGE& TOPOGRAPHY ................................................ 76
4.3.1.2 SOIL QUALITY .............................................................................................................. 76
Modification and Expansion of Group Housing Project “Atharva Group Housing” at Sec-
109, Village PawalaKhusrupur, Gurugram, Haryana
EIA-EMP REPORT
M/s Raheja Developers Ltd. Page 3
4.3.1.3 MITIGATION MEASURES ............................................................................................ 76
4.3.1.4 AGRICULTURE AND CROPPING PATTERN............................................................... 77
4.3.2 WATER ENVIRONMENT ................................................................................................. 77
4.3.2.1 SURFACE WATER QUALITY- IMPACT IDENTIFICATION & EVALUATION ......... 77
4.3.2.2 MITIGATION MEASURES ............................................................................................ 77
4.3.2.3 SURFACE WATER RESOURCES .................................................................................. 78
4.3.2.4 IMPACT ON GROUNDWATER QUALITY ................................................................... 78
4.3.2.5 MITIGATION MEASURES ............................................................................................ 78
4.3.3 AIR ENVIRONMENT ........................................................................................................ 79
4.3.3.1 MITIGATION MEASURES ............................................................................................ 80
4.3.4 NOISE ENVIRONMENT ................................................................................................... 80
4.3.4.1 MITIGATION MEASURES ............................................................................................ 81
4.3.5 TRANSPORT LINKAGE AND TRAFFIC ......................................................................... 81
4.3.5.1 MITIGATION MEASURES ............................................................................................ 81
4.3.5 BIOLOGICAL ENVIRONMENT ....................................................................................... 81
4.3.6 SOCIO-ECONOMIC IMPACTS ......................................................................................... 82
4.3.6.1 MITIGATION MEASURES ............................................................................................ 82
4.3.7 IMPACTS DUE TO SOLID WASTE .................................................................................. 83
4.3.7.1 MITIGATION MEASURES ............................................................................................ 83
4.4 ASSESSMENT OF THE ENVIRONMENTAL IMPACTS DURING POST CONSTRUCTION
PHASE/OPERATION PHASE ........................................................................................................ 84
4.4.1 LAND ENVIRONMENT .................................................................................................... 84
4.4.1.1 LAND USE PATTERN, DRAINAGE& TOPOGRAPHY ................................................ 84
4.4.1.2 SOIL QUALITY .............................................................................................................. 84
4.4.1.3 MITIGATION MEASURES ............................................................................................ 84
4.4.1.4 AGRICULTURE AND CROPPING PATTERN............................................................... 84
4.4.2 WATER ENVIRONMENT ................................................................................................. 85
4.4.2.1 SURFACE WATER HYDROLOGY ................................................................................ 85
4.4.2.2 SURFACE WATER QUALITY ....................................................................................... 85
4.4.2.3 MITIGATION MEASURES ............................................................................................ 86
4.4.2.4 GROUND WATER HYDROLOGY ................................................................................. 86
4.4.3 AIR ENVIRONMENT ........................................................................................................ 87
4.4.3.1 PROPOSED MITIGATION MEASURES ........................................................................ 87
4.4.4 NOISE ENVIRONMENT ................................................................................................... 88
4.4.4.1 MITIGATION MEASURES ............................................................................................ 88
Modification and Expansion of Group Housing Project “Atharva Group Housing” at Sec-
109, Village PawalaKhusrupur, Gurugram, Haryana
EIA-EMP REPORT
M/s Raheja Developers Ltd. Page 4
4.4.5 TRANSPORT LINKAGE AND TRAFFIC ......................................................................... 88
4.4.5.2 MITIGATION MEASURES ............................................................................................ 88
4.4.6 BIOLOGICAL ENVIRONMENT ....................................................................................... 88
4.4.7 IMPACT ON SOCIO-ECONOMIC ENVIRONMENT ........................................................ 88
4.4.8 ENERGY RESOURCES ..................................................................................................... 89
4.4.9 IMPACT DUE TO SOLID WASTE .................................................................................... 90
4.4.9.1 MITIGATION MEASURES ............................................................................................ 90
CHAPTER 5 :DAMAGE ASSESSMENT AND REMEDIATION PLAN ..................... 98
5.1 INTRODUCTION ..................................................................................................................... 98
5.2 HISTORICAL EC APPROVAL PRESPECTIVE AND COMPLIANCE TO SEIAA
RECOMMENDATION ................................................................................................................... 98
5.3 DAMAGE ASSESSMENT: SITE ASSESSMENT AND DEVELOPMENT .............................. 98
5.4 DAMAGE ASSESSMENT: CONSTRUCTION PHASE............................................................ 99
5.5 REMEDIATION PLAN: CONSTRUCTION PHASE .............................................................. 101
5.6 DAMAGE ASSESSMENT: OPERATION PHASE ................................................................. 103
5.6 REMEDIATION PLAN: OPERATION PHASE ...................................................................... 104
5.6 NEED AND REMEDIATION PLAN: NEED AND RECOMMENDATION ........................... 108
CHAPTER 6 :ALTERNATIVE TECHNOLOGIES ..................................................... 109
6.1 GENERAL .............................................................................................................................. 109
6.2 ENERGY CONSERVATION .................................................................................................. 109
6.3 WATER CONSERVATION .................................................................................................... 110
6.4 INTERNAL ROADS & ACCESS ROADS .............................................................................. 112
6.5 CONSTRUCTION MATERIAL .............................................................................................. 112
6.6 CONCLUSION ........................................................................................................................ 112
CHAPTER 7 :ENVIRONMENTAL MONITORING PROGRAM .............................. 113
7.1 OBJECTIVES .......................................................................................................................... 113
7.2 PERFORMANCE INDICATORS ............................................................................................ 113
7.2.1 Ambient Air Quality (AAQ) Monitoring ............................................................................... 113
7.2.2 Water Quality Monitoring ..................................................................................................... 114
7.2.3 Noise Level Monitoring ........................................................................................................ 114
7.2.4 Green Area Development ...................................................................................................... 114
7.2.5 Soil Quality ........................................................................................................................... 114
7.3 ENVIRONMENT MONITORING PLAN ................................................................................ 114
CHAPTER 8 :DISASTER MANAGEMENT PLAN ..................................................... 117
8.1 INTRODUCTION ................................................................................................................... 117
Modification and Expansion of Group Housing Project “Atharva Group Housing” at Sec-
109, Village PawalaKhusrupur, Gurugram, Haryana
EIA-EMP REPORT
M/s Raheja Developers Ltd. Page 5
8.2 APPROACH ............................................................................................................................ 117
8.3 HAZARD IDENTIFICATION ................................................................................................. 117
8.4 EMERGENCY MANAGEMENT PLAN ................................................................................. 118
8.4.1 SCOPE ................................................................................................................................. 118
8.4.2 OBJECTIVES ....................................................................................................................... 118
8.4.3 FORMULATION OF DMP................................................................................................... 119
8.4.4ONSITE EMERGENCY PLAN ............................................................................................. 119
8.4.5 ROLES AND RESPONSIBILITY......................................................................................... 120
8.4.6 ALARM AND COMMUNICATION MECHANISM ............................................................ 121
8.4.7 FIRE FIGHTING FACILITIES ............................................................................................. 121
CHAPTER 9 :PROJECT BENEFIT .............................................................................. 124
9.1 GENERAL .............................................................................................................................. 124
9.2 RESIDENTIAL FACILITIES .................................................................................................. 124
9.3 SUSTAINABLE HOUSING .................................................................................................... 124
9.4 AESTHETIC IMPROVEMENT .............................................................................................. 125
9.5 EMPLOYMENT OPPORTUNITIES ....................................................................................... 125
9.6 INFRASTRUCTURE DEVELOPMENT ................................................................................. 125
CHAPTER 10 :ENVIRONMENTAL MANAGEMENT PLAN (EMP) ....................... 126
10.1 INTRODUCTION ................................................................................................................. 126
10.2 ENVIRONMENT MANAGEMENT PLAN ........................................................................... 126
10.3 AIR POLLUTION MANAGEMENT PLAN .......................................................................... 127
10.3.1 Construction Phase .............................................................................................................. 127
10.3.2 Operation Phase .................................................................................................................. 127
10.4 WATER CONSERVATION PLAN ....................................................................................... 127
10.4.1 Construction Phase .............................................................................................................. 127
10.4.2 Operation Phase .................................................................................................................. 128
10.5 WATER QUALITY MANAGEMENT PLAN ....................................................................... 129
10.5.1 Construction Phase .............................................................................................................. 129
10.5.2 Operation Phase .................................................................................................................. 129
10.6 SOIL QUALITY MANAGEMENT PLAN ............................................................................ 130
10.6.1 Construction Phase .............................................................................................................. 130
10.6.2 Operation Phase .................................................................................................................. 130
10.7 SOLID WASTE MANAGEMENT PLAN.............................................................................. 131
10.7.1 Construction Phase .............................................................................................................. 131
10.7.2 Operation Phase .................................................................................................................. 131
Modification and Expansion of Group Housing Project “Atharva Group Housing” at Sec-
109, Village PawalaKhusrupur, Gurugram, Haryana
EIA-EMP REPORT
M/s Raheja Developers Ltd. Page 6
10.8 NOISE LEVEL MANAGEMENT PLAN............................................................................... 132
10.8.1 Construction Phase .............................................................................................................. 132
10.8.2 Operation Phase .................................................................................................................. 132
10.9 TRAFFIC MOVEMENT ........................................................................................................ 133
10.10 GREEN BELT MANAGEMENT PLAN .............................................................................. 133
10.10.1 Green Belt development Plan ............................................................................................ 134
10.10.2 Selection of Plant Species for Green Belt Development ..................................................... 134
10.10.3 After Care and Monitoring................................................................................................. 135
10.11 OCCUPATIONAL HAZARD MANAGEMENT PLAN ...................................................... 135
10.12 ENERGY CONSERVATION PLAN ................................................................................... 136
10.13 ENVIRONMENTAL MANAGEMENT CELL .................................................................... 137
10.14 ENVIRONMENT MANAGEMENT BUDGET ................................................................... 138
CHAPTER 11 :SUMMARY AND CONCLUSION ....................................................... 140
11.1 PROJECT BACKGROUND .................................................................................................. 140
11.2 PROJECT DESCRIPTION .................................................................................................... 141
11.3 BASELINE ENVIRONMENT ............................................................................................... 142
11.4 ANTICIPATED IMPACTS.................................................................................................... 144
11.5 ALTERNATIVE ANALYSIS ................................................................................................ 144
11.6 ENVIRONMENT MONITORING PLAN .............................................................................. 144
11.7 ENVIRONMENT MANAGEMENT PLAN ........................................................................... 144
CHAPTER 12 :DISCLOSURE OF CONSULTANT..................................................... 145
12.1 DISCLOSURE OF CONSULTANTS ENGAGED ................................................................. 145
12.2 FUNCTIONAL AREA EXPERT ........................................................................................... 145
Modification and Expansion of Group Housing Project “Atharva Group Housing” at Sec-
109, Village PawalaKhusrupur, Gurugram, Haryana
EIA-EMP REPORT
M/s Raheja Developers Ltd. Page 7
LIST OF TABLE
Table 1.1: Summary of Environmental Legislation, policy and guidelines as applicable on
proposed project ...................................................................................................................... 13
Table 1.2: Compliance to TOR Points ..................................................................................... 18
Figure 2.1: Location Plan of the Project .................................................................................. 25
Table 2.2: Geographical Coordinates of the Project Site .......................................................... 25
Table 2.3: Site & Surrounding of the project (10 Km radius) ................................................... 26
Table 2.6: Daily Water requirement at Calculations................................................................. 31
Table 2.7: Available Run-off from Site ................................................................................... 37
Table 2.8: Calculation for RWH Pits ....................................................................................... 38
Table 2.9: Solid Waste Management during Construction Phase ............................................. 40
Table 2.10: Calculation of Solid Waste Generation ................................................................. 40
Table 2.11: Trees Proposed to be planted at Site ...................................................................... 41
Table 2.12: Details of Construction Materials Required for The Project .................................. 43
Table 2.13: List of building materials to be used at site ........................................................... 43
Table3.3: Monthly Mean Wind Speed (KMPH) ...................................................................... 51
Table 3.4: Micro-Meteorology of Study Area During January, 2018 ....................................... 53
Table3.6: Soil Quality Testing Stations ................................................................................... 59
Table 3.7: Soil Quality Analysis Report .................................................................................. 59
Table 3.8: Generalized Geological Succession, Gurugram District .......................................... 62
Table 3.9: Ground Water Monitoring Stations ......................................................................... 65
Table 3.10: Ground Water Quality Analysis (Jan, 2018) .......................................................... 65
Table 3.11: Surface Water Quality Analysis (Jan, 2018) .......................................................... 66
Table 3.12: Locations of Ambient Air Quality Monitoring ...................................................... 67
Table: 3.13: Ambient Air Quality Test Results (Jan, 2018) ...................................................... 67
Table: 3.14: Ambient Air Quality Test Results (Jan, 2018) ...................................................... 67
Table: 3.15: National Ambient Noise Level Standards ............................................................ 70
Table 3.16: List of Noise Level Monitoring Stations ............................................................... 70
Table 3.17: Noise Level Monitoring results (Jan, 2018) .......................................................... 70
Table 3.18: Traffic Survey of SH-15A .................................................................................... 71
Table 3.19: Flora of Study Area .............................................................................................. 72
Source: Primary survey ........................................................................................................... 72
Table 3.20: Fauna of Study Area ............................................................................................. 72
Source: Primary survey ........................................................................................................... 73
Table 3.21: Demographic Profile of Gurugram ........................................................................ 73
Table 4.1:Quantity of construction material required for Existing + Expansion & Modification
............................................................................................................................................... 79
Table 4.2: Quantification of Pollution Load Due to Movement of Trucks ................................ 79
Table 4.3: Expected noise levels from various activities .......................................................... 80
Table 4.4Run-off Calculation from Site after development ...................................................... 85
Table 4.5:Standard of Emissions from Vehicles ...................................................................... 87
Modification and Expansion of Group Housing Project “Atharva Group Housing” at Sec-
109, Village PawalaKhusrupur, Gurugram, Haryana
EIA-EMP REPORT
M/s Raheja Developers Ltd. Page 8
Table 4.6:Emissions from Vehicles at site ............................................................................... 87
Table 4.7: Summary of Potential Impacts and Remedial Measures .......................................... 91
Table 5.1: Energy Efficiency Calculations............................................................................. 105
Table 5.2: EMP budget for Construction Phase (Majorly Incurred) ....................................... 105
Table 5.3: EMP budget for Operational Phase (80% Incurred) .............................................. 106
Table 5.4: Environment Monitoring Plan .............................................................................. 106
Table 6.1: Environment aspects of proposed scheme other than sources of Pollution ............. 109
Table 6.2: Energy Saving Calculations .................................................................................. 110
Table 6.3: Annual Available Run-off .................................................................................... 111
Table 7.1 – Environment Monitoring Program ...................................................................... 114
Table 10.1: Details of Green Area ......................................................................................... 134
Table 10.2: List of Trees proposed to be planted ................................................................... 135
Table 10.3: EMP budget for Construction Phase (Majorly Incurred) ..................................... 138
Table 10.4: EMP budget for Operational Phase (80% Incurred)............................................. 139
Table 11.1: Summary of built-up area ................................................................................... 141
Modification and Expansion of Group Housing Project “Atharva Group Housing” at Sec-
109, Village PawalaKhusrupur, Gurugram, Haryana
EIA-EMP REPORT
M/s Raheja Developers Ltd. Page 9
LIST OF FIGURE
Figure 1.1: Roadmap for EIA clearance of the building construction, townships and area
development projects. ............................................................................................................. 17
Figure 2.2: Geographical Coordinates of Project Site .............................................................. 26
Figure 2.5: Water Balance Diagram-Dry Season ..................................................................... 32
Figure 2.6: Water Balance Diagram-Monsoon Season ............................................................. 33
Figure 2.7: Typical flow Diagram of SAF Process Cycle......................................................... 37
Figure 2.8: Schematic Diagram of Rain Water Harvesting Pit ................................................. 38
Figure 3.1: Topographic Map Showing Study Area ................................................................. 46
Figure 3.2: Map Showing Location of Baseline Monitoring Stations ....................................... 48
Figure 3.3: Wind Rose Diagram Gurugram, Haryana .............................................................. 52
Figure 3.8: Drainage pattern of the study area ......................................................................... 61
Figure 3.9: Depth ofWater level During Pre-Monsoon in Gurugram District ........................... 63
Figure 3.10: Depth of Water level During Pre-Monsoon in Gurugram District ........................ 64
Figure 3.11: Graphical Presentation of Ambient Air Quality Monitoring Analysis .................. 69
Figure 10.1 Environnent Management Cell Structure ............................................................ 138
Modification and Expansion of Group Housing Project “Atharva Group Housing” at Sec-
109, Village PawalaKhusrupur, Gurugram, Haryana
EIA-EMP REPORT
M/s Raheja Developers Ltd. Page 10
CHAPTER 1:INTRODUCTION
1.1 INTRODUCTION
M/s Raheja Developers Ltd. had planned and developed a Group Housing Project located at
Village PawalaKhushrupur Sector 109, Gurugram. Approval was obtained from HUDA and
DTCP, Haryana for development of the project. Environmental clearance has also been obtained
for the project from SEIAA, Haryana for area measuring 59,132.5722 m2 (14.812 acres) and Built-
up area of1, 57,917.34 m2. Environmental clearance letter is attached as Annexure I. Due to
revision in HUDA Bye Laws, M/s Raheja has revised the project planning to avail the benefits of
revision in Bye Laws & TOD benefits. Due to the revision, plot area and built-up area will
increase to 63,179.4 sq. m. and 221496.1139sq mrespectively.Revised approval for modification
has been obtained from HUDA (Annexure II) but revised environmental clearance was not
obtained on assumption that environmental clearance is granted under the category of projects with
built-up area more than 1,50,000 sq m and thus increase in area under proposed modification is
deemed covered under the EC granted. But on realization of requirement of the revision of
environmentclearance, application is submitted to SEIAA, Haryana for obtaining revised
environmental clearance. Till date built-up area constructed as per modified planning is
164805.526 sq m against the approved built-up area of 1,57,917.34 m2 which has led to the
violation of EIA Notification, 2006. The violation was not intentional but has happened due to
unawareness and confusion on the scope of the EC granted. Due to involvement of the violation of
EIA Notification, project will now be reviewed as per the EIA Notification “SO 804(E)s” dated
14.03.2017 and SO 1030 dated 08.03.2018 under Category B 1 and detailed EIA study is required
to be carried out for the project along with damage assessment study.
1.2 IDENTIFICATION OF PROJECT & PROJECT PROPONENT
M/s Raheja Developers Ltd. had planned and developed a Group Housing Project located at
Village PawalaKhushrupur Sector 109, Gurugram.Environmental clearance has also been obtained
for the project from SEIAA, Haryana vide letter no SEIAA/HR/2018/863 dated 07.08.2018 for
area measuring 59,132.5722 m2 (14.812 acres) and Built-up area of1, 57,917.34 m2. Thereafter
project design was revised and plot area and built-up area after revision are increased to 63,179.4
sq. m. and 221496.1139 sq. m respectively. Land is in ownership of M/s Raheja Ltd and copy of
land documents are attached as Annexure III. Project overall comprise of development of
residential towers with 593 general DU and 72 service units, EWS with 125 units, 94 nos. of DUs
as independent floors, community building, convenient shopping/commercial and schools.
Modification and Expansion of Group Housing Project “Atharva Group Housing” at Sec-
109, Village PawalaKhusrupur, Gurugram, Haryana
EIA-EMP REPORT
M/s Raheja Developers Ltd. Page 11
M/S Raheja Developers Ltd.
M/s Raheja Developers Ltd. is established company in the Indian Realty Sector since 1990 and is
maintaining highest standards of professionals of business with a good customer satisfaction index
and the best standards for the welfare of its staff, society as well as for the environment and
provides the cost effective and holistic solutions which are specific to contemporary standards for
Residential, Commercial, SEZ and Business Centers in the Delhi and NCR. They have been
successful in providing specifically designed housing solutions to the elite professional keeping in
mind their daily needs and their exquisite taste in lifestyle. Mr. Navin Raheja Founder CMD of the
company had been member of steering committee project Tiger under MoEF&CC has made and
released over 122 real wildlife films and had received “Green Man of India Award”
The Company has traversed a path of steady growth & expansion. The systems have been
strengthened and new processes have been added. Company has well established sustainable
environmental parameters policy which mandates company to follow and adopt all the measures to
make projects sustainable and energy efficient. Company has strong CSR policy under which
Raheja group contributes in welfare of unprivileged sector and runs KMGS as NGO which is
providing education to hundreds of weaker section and underprivileged children’sa and is
registered with national open school. Registered office of the company is located in New Delhi at
Office space No. 406, 4th floor, Rectangle One, D-4, District Centre, Saket, New Delhi-110017.
Company Secretary of the company isAjay Kumar Mohanty and his contact number is
9971091904 and email id [email protected].
1.3 DEVELOPMENT STRATEGY OF THE PROJECT
The planned group housing project “Atharva” comprise of Residential towers, convenient
shopping community building, EWS, Small Towers comprising of independent residential floors
and schools.Site is located in PawalaKhusrupurvillage of Tehsil Gurugram whichis well connected
by road and railway. Area is surrounded by residential colonies and villages majorly, schools,
hospitals, religious places etc. Project development location is thus convenient for its residents and
will have access to all the facilities for comfortable living.
All the provision of parking, water requirement, green space, sewage management, structure
stability are made at site to minimize the impact of the project on the environment and the society.
Environmental Management Measures present at the site are listed below:
Proper sewerage collection and treatment in STP of 550 KLD
Re-usage of STP treated water for landscaping and flushing purpose through dual
plumbing system
Modification and Expansion of Group Housing Project “Atharva Group Housing” at Sec-
109, Village PawalaKhusrupur, Gurugram, Haryana
EIA-EMP REPORT
M/s Raheja Developers Ltd. Page 12
Installation of water conservation taps and fixtures to minimize water requirement
Provision of energy saving lighting at the site for internal and external lighting
Installation of grid connected SPV power plant of 40.3 KWp as per BIS/HAREDA/MNRE
specifications (NOC from HAREDA and satisfactory report are attached Annexure VI a &
b). Also solar street lights are provided in common areas
Proper collection and management of storm water and recharge of run-off to ground
through 6 nos. of filter packed RWH pits
Daily collection and disposal of municipal waste through local authorized vendor in the
area
Green area of 17,385.1 m2 already developed at the site which is 32.17 % of net plot area.
Green area includes peripheral green belt, avenue plantation, private lawns for each tower
and organized greens.
All the surface parking areas are provided with the grass pavers
DG sets are provided with acoustic enclosures
Provision of adequate parking and roads of adequate width
Provision of adequate fire-fighting equipment at the site
1.4 NECESSITY AND BENEFITS OF PROJECT
The built environment and urban infrastructure provide the core framework for most human
activity. Therefore, it is crucial to develop them with an effective measure of resilience so they can
withstand, and adapt to the pressures of socio-economic challenges posed by increased
urbanization, density, housing shortfall, employment, climate change etc. With nearly half of the
country’s population expected to be living in or migrating to urban areas by the end of the decade,
at the crux of this framework lie ‘Cities’- which are engines of national productivity. Also people
desire to live in localities, in which majority of their daily needs is fulfilled in the same locality.
The concept of residential, convenient shopping block is well accepted by people as they get all
the facilities like housing, community center, children parks, convenient shopping, schools etc.
The proposed scheme strives to attain the same by providing cost-effective as well as facility
equipped with all facilities of modern-day requirement and that caters to the needs of the
population. Project involves the infrastructure development keeping in mind the environmental
management. To make the project environmentally feasible it is proposed to provide adequate
open spaces, green spaces, recreational space, commercial facilities, waste management system
etc.
1.5 LEGISLATION, POLICY AND GUIDELINES OF BUILDING CONSTRUCTION
As per EIA Notification, 2006, large building and construction projects with built-up area more
than 20,000 sq m are listed under schedule 1 as category B and activity 8 (a) and area development
Modification and Expansion of Group Housing Project “Atharva Group Housing” at Sec-
109, Village PawalaKhusrupur, Gurugram, Haryana
EIA-EMP REPORT
M/s Raheja Developers Ltd. Page 13
projects with built up area more than 1,50,000 sq m are listed under schedule 1 as category B and
activity 8 (b). Project includes a group housing project with built up area more than 20,000 sq m.
Building and construction project having built-up area more than 20,000 sq m but less than
1,50,000 sq m falls under activity 8(a) and category B of schedule 1 of EIA Notification, 2006 as
amended. However the project involving violation of EIA Notification, 2006 thus the project will
be appraised as per notification of MoEF&CC, i.e. “SO 804(E)” dated 14.03.2017. We have then
applied to MoEF&CC for obtaining environmental clearance as per the EIA Notification SO 804
dated 14.03.2017 on 13.07.2017. Thereafter MoEF&CC has issued amendment SO 1030 dated 8 th
March, 2018 and has directed that Category B projects involving violation will be appraised at
State Level and all the category B proposals will be transferred to SEIAA.Accordingly, our project
has been transferred to SEIAA by MoEF&CC. Other acts, rules and guidelines applicable for the
infrastructure projects as per Legislation of Government of India are listed in Table 1.1 below.
Application to obtain environment clearance (form 1, form 1A, Standard ToR for Building and
Construction projects, Conceptual Plan and Annexures) has been submitted online on 08.05.2017
and Terms of References were obtained vide letter no SEIAA/HR/2018/863 dated 07/08/2018.
Baseline data collection and EIA study for the project is carried out in line with the standard ToR
for Building and Construction Projects issued by MoEF&CC and additional ToRs issued by SEAC
for the project. Baseline study period for the project is Jan, 2018.M/s Raheja Developers Ltd have
complied with all the environmental regulations applicable to the project apart from the above-
mentioned violation. M/s Raheja Developers Ltd has obtained consent to establish from HSPCB
(Annexure IV) for construction as applicable under Air & Water Act. M/s Raheja Developers Ltd
has also obtained consent to operate under Air & water Act (1981 & 1974) and Authorization
under Hazardous Waste Rules, 2008 (Annexure V a, b & c) as applicable for the project from
HSPCB. Occupancy certificate was also obtained for the project from the DTCP, Haryana
(Annexure VI).
Table 1.1: Summary of Environmental Legislation, policy and guidelines as applicable on
proposed project
Legislation Areas / Activities Covered Applicability
Environment (Protection)
Act, 1986 with Rules.
Overall Environment Protection
Compliance to environmental (Air, Water,
Noise) Standards issued under EPR
Applicable.
EIA Notification, 2006 and amendments
Prepare EIA / EMP report Obtain Environmental Clearance from
MoEF/SEIAA
Applicable and covered under
Activity 8 (a),
Category B. Built-up area of project is
more than 20,000 sq.
m. and 1,50,000 sq.
m. However the
Modification and Expansion of Group Housing Project “Atharva Group Housing” at Sec-
109, Village PawalaKhusrupur, Gurugram, Haryana
EIA-EMP REPORT
M/s Raheja Developers Ltd. Page 14
Legislation Areas / Activities Covered Applicability
project involving
violation of EIA
Notification, 2006 thus the project will
be appraised as per
notification of MoEF&CC, i.e. “SO
804(E)s” dated
14.03.2017 and
Notification SO 804 dated 14.03.2017 on
13.07.2017
Air (Prevention and Control of Pollution) Act, 1981
with Rules.
Protection of Air Quality Consent to Establish (NOC) for
establishing and Consent to Operate (CTO)
for activities causing air pollution from
SPCB Compliance to National Ambient Air
Quality Standard
Applicable, involves emissions of flue gases
due to operation of DG
sets
Water (Prevention and
Control of Pollution) Act, 1974 with Rules.
Protection of Water Quality
Discharge of sewage Obtaining Consent to Establish for
establishing and Consent to Operate for
activities causing water pollution from SPCB and for the discharge of effluents
Applicable, involves
generation of sewage
Noise Pollution (Regulation
and Control) Rules, 2000
Compliance with Ambient Noise and
emission Standards in accordance to use
classification for the area
Applicable, involves
generation of noise
due to operation of DG sets & pumps and
vehicular movement
Hazardous and
Other Wastes (Management
and Transboundary
Movement) Rules, 2016 as amended
Obtaining Authorization from SPCB for
handling and storing of hazardous waste
like waste oil and lubricants
Following guidelines for handling and
storing of such hazardous waste
Management (Collection, Handling,
Intermediate Storage) of domestic waste
from residences
Applicable, generation of small quantity of
used oil from DG sets
Manufacture, Storage and Import of Hazardous
Chemicals Rules, 2000 (as
amended)
Notifying regulatory authority (in this case, the State Factories Inspectorate) of storage
of hazardous substances like HSD
Follow guidelines on such storage, maintain updated MSDS, submit annual
Safety Report to authority
Prepare Onsite Emergency Plan
Not Applicable, storage of some
quantity (below
threshold limit as mentioned in schedule
2 & 3) of HSD for
operating Dg sets
Wildlife Protection Act,
MoEF 1972, amended 2010
Lays down rules and regulations pertaining
to Wildlife Sanctuaries, National Parks.
Obtain NBWL Clearance if site is within 10 km radius of WLS/NP/ Protected Areas
Not applicable, no
eco-sensitive zone
protected under the act exists within 10
km area
Modification and Expansion of Group Housing Project “Atharva Group Housing” at Sec-
109, Village PawalaKhusrupur, Gurugram, Haryana
EIA-EMP REPORT
M/s Raheja Developers Ltd. Page 15
Legislation Areas / Activities Covered Applicability
Motor Vehicles Act with
Rules, 1988 as amended
Lay down restriction for vehicles not
having Pollution Under Control Certificate
(PUCC) or proper labeling to enter premises
Applicable
Municipal Solid Waste
Rules, 2016
Management (Collection, Handling,
Intermediate Storage) of domestic waste
from residences
Applicable, involves
generation of
municipal solid waste
Building Bye Laws of
HUDA
Obtain permits and sanction for land
Development of project in accordance with
Land-use and Master plans
Applicable
State Groundwater Regulation
Conform to restriction for drawing of groundwater
Arrange for recharge through Rainwater
Harvesting Schemes (as applicable)
Applicable, if ground water is utilized
Fly ash Notification, 2007 Use of fly ash (wholly or partly) in building
construction wherever it costs same or less
than the clay, limestone, sand etc and is not
technically infeasible, compliance of which shall be the duty of the person/ agencies
undertaking construction
Not applicable, but
options should be
explored
E- Waste Rules, 2016 Procedure of collection, storage and transportation of E-waste
Applicable
Corporate Social
Responsibility 2012
Each business entity should formulate a
CSR policy to guide its strategic planning
and provide a roadmap for its CSR initiatives
2% of total project cost shall be allocated
for CSR activities.
Applicable
Plastic Waste
Management Rules, 2016
Procedure of segregation, collection,
storage, transportation, processing and
disposal of plastic waste
Applicable
Construction & Demolition
Waste Management Rules,
2016
Procedure ofcollection, segregation of
concrete, soil and others
Procedure ofstorage of construction and
demolition waste generated
Applicable
1.6 NEED FOR EIA STUDY
EIA study involves identification of the impacts associated with the project activities during the
construction and operation phase of the project. Impact associated are assessed quantitatively and
qualitatively to know their magnitude and significance. On the basis of the severity of impacts,
experts propose the mitigation and management plan so as to ensure environmentally and socially
sound implementation of the project. Thus, EIA study helps to identify the negative impacts
associated with the project and their mitigation and management.
In order to ensure that development is sustainable it is essential to integrate environmental
concerns into development activities. EIA is currently the only explicit legal instrument available
to comprehensively assess resource impacts of large buildings and townships. The purpose of EIA
Modification and Expansion of Group Housing Project “Atharva Group Housing” at Sec-
109, Village PawalaKhusrupur, Gurugram, Haryana
EIA-EMP REPORT
M/s Raheja Developers Ltd. Page 16
Report is to assist in the decision- making process and to ensure that the project options under
consideration are environmentally sound and sustainable. The approach adopted in the EIA study
is to ensure that positive environmental impacts are maximized and the negative are
minimized/reduced to the extent possible. The steps taken generally consist of incorporation of
appropriate mitigation measures in engineering designs, construction schedules and techniques, as
well as in operational and management practices outlined as a part of Environmental Management
Plan (EMP).
The EIA study of project has been done as per Appendix-III, EIA Notification, 2006& EIA
Guidance Manual – Building, Construction, Township and Area Development, MoEF,
Government of India guidelines, Standard ToR for Building & Construction projects by MoEFCC
and additional ToR issued by SEIAA vide letter no. SEIAA/HR/2018/863 dated 07.08.2018.
1.7 PURPOSE OF THE STUDY
Project involves expansion and modification of the project “Atharva Group Housing” located at
Sec-109, Gurugram, Haryana. Built-up area of the project after expansion and modification will be
266094.125 m2 thus the project will fall under activity 8 (b) of schedule 1 of EIA Notification,
2006 as amended and is classified as Category B1.
However, the project involves violation of EIA Notification, 2006 thus the project will be
appraised as per notification of MoEF&CC, i.e. “SO 804(E)” dated 14.03.2017 and SO 1030 dated
8th March, 2018. As per the notification all building and construction projects irrespective of built-
up area will be treated as Category B1 and detailed EIA study and damage assessment study will
be required for assessment purpose.
1.8 OBJECTIVES OF EIA STUDY
In order to ensure that development is sustainable it is essential to integrate environmental
concerns into development activities. Environmental impact assessment and management have
been recognized as effective tools for facilitating the inclusion of the principles of sustainable
development into development processes or projects. It is also universally accepted that natural
resource development and environmental protection should go hand in hand. This is in- line with
the national policy that the developments of infrastructure as well as other developmental activities
have to follow the principle of development without destruction, and measures must be adopted to
have environmentally sound and sustainable environment.
In order to avoid or reduce the possible ill effects, it is essential that all the development projects
should be subjected to the requirement of an Environmental Impact Assessment (EIA). EIA will
point out potential environmental impacts of the project and to recommend appropriate mitigation
Modification and Expansion of Group Housing Project “Atharva Group Housing” at Sec-
109, Village PawalaKhusrupur, Gurugram, Haryana
EIA-EMP REPORT
M/s Raheja Developers Ltd. Page 17
measures for the possible adverse impacts. Recommendations are also made for an environmental
management plan.
1.9 PROCESS OF OBTAINING ENVIRONMENT CLEARANCE
The objective of the EIA Notification, 2006 is to set procedures of environmental clearance before
establishment of projects of identified nature and size. Process of environmental clearance for 8(b)
projects is given below in Figure 1.1.
Site Survey
Compilation of data, Preparation of Form 1, 1A, ToR
Submission of Form 1, 1A, ToR
ToR Presentation in SEAC, Issuance of additionalToR
Baseline monitoring
Inputs from FAEs & Compilation of EIA Report
Submission of EIA Report in SEAC
EIA Appraisal/ presentation in SEAC
Grant of Environment Clearance
Figure 1.1: Roadmap for EIA clearance of the building construction, townships and area
development projects.
1.10 TOR COMPLIANCE
The EIA study has been conducted in accordance with the standard TOR issued by MoEF&CCfor
building and construction Projects and additional ToR issued by SEIAA, Haryana. ToR letter is
attached as Annexure VII. The point wise compliance of Standard TOR points is given in Table
1.2below.
Modification and Expansion of Group Housing Project “Atharva Group Housing” at Sec-
109, Village PawalaKhusrupur, Gurugram, Haryana
EIA-EMP REPORT
M/s Raheja Developers Ltd. Page 18
Table 1.2: Compliance to TOR Points
S.No ToR Points Compliance
General Conditions
1. Project description, its importance and the
benefits
Details are given in Chapter 2.
2. Project site details (location, toposheet of the study area of 10 Km, coordinates, google map,
layout map, land use, geological features and
geo-hydrological status of the study area,
drainage),
Details are given in Chapter 3
3. Land use as per the approved Master Plan of the
area, Permission/approvalsrequired from the
land owning agencies, Development Authorities, Local Body,Water Supply &
Sewerage Board, etc
Land use of the project site for existing and
expansion/modification is already residential as per
the Master Plan of Gurugram, 2031.
4. Land acquisition status, R &R details. No land acquisition is involved
5. Forest and Wildlife and eco-sensitive zones, if any in the study area of 10 KmClearances
required under the Forest (Conservation) Act,
1980, the Wildlife(Protection)Act, 1972 and
/orthe Environment(Protection)Act,1986.
No forest or wildlife land is present within 5 km radius of the project site.
6. Baseline environmental study for ambient air
(PM10, PM2.5,SO2,NOx&CO),Water(both
surface and ground), noise and soil for one month (exceptmonsoon period)as per
MoEF&CC/CPCB guidelines at minimum 5
locations inthe study area of 10 KM
Details of baseline monitoring are given in Chapter 3.
7. Details on flora and fauna and socio- economic aspects in the study area.
Details are given in section 3.11 & 3.12 of Chapter 3.
8. Likely impact of the project on the
environmental parameters (ambient air,surface
and ground water, land, flora and fauna and socio-economic, etc )
Details are given in Chapter 4
9. Source of water for different identified purposes
with the quantified permissions required from the concerned authorities, both for surface water
and the ground water (by CGWA)as the case
may be, Rain water harvesting, etc,
Water for construction was and will be treated water
from nearby CSTP of HUDA (at Manesar). Source of water during operation phase is HUDA supply
supplemented by private water tankers.
10. Waste water management (treatment, reuse and disposal) for the project and also the study area,
Details are given in section 2.5.1 & 2.5.2.
11. Management of solid waste and the construction
& demolition waste for the project vis-a-vis the
Solid Waste Management Rules, 2016 and the Construction & Demolition Rules,2016
Waste management plan is designed as per these rules.
Details are given in section 2.5.6
12. Energy efficient measures (LED lights, solar
power, etc) during construction as well as during operational phase of the project.
Energy efficient measures are given in section 6.2 of
Chapter 6
13. Assessment of ecological damage with respect
to air, water, land and other environmental
attributes, The collection and analysis of data shall be done by an environmental laboratory
duly notified under the Environment
Damage assessment chapter is prepared and is given
as Chapter 5
Modification and Expansion of Group Housing Project “Atharva Group Housing” at Sec-
109, Village PawalaKhusrupur, Gurugram, Haryana
EIA-EMP REPORT
M/s Raheja Developers Ltd. Page 19
S.No ToR Points Compliance
(protection) Act, 1986, or an environmental Laboratory accredited by NABL, or a
laboratory, of a Council of scientific and
industrial Research (CSIR) institution working
in the field of environment.
14. Preparation of EMP comprising remediation
plan and natural and community resource
augmentation plan to be prepared as an independent chapter in the EIA report by the
accredited consultants corresponding to be
ecological damage assessed and economic
benefits derived due to violation to be prepared as an independent chapter in the EIA report by
the accredited consultants.
EMP is prepared and is given as Chapter 10
Specific ToR
1. The PP should submit an affidavit from the Director of the Company giving graphical
details of construction and utility services
already done.
Affidavit is attached as Annexure XIX.
2. The PP should submit remediation plan. Damage assessment chapter is prepared and is given
as Chapter 5
3. The PP should submit traffic circulation and
movement of trucks with special mitigation plan.
Details are given in section 4.3.5 of Chapter 4.
4. The PP should submit the details of court case if
any.
Name of the Court: National Green Tribunal
Case No.: M.A. No. 987/2018
5. The PP should submit approved building plan along with service plan.
Approved site plan is attached as Annexure II.
6. The PP should submit the impact on ambient
air, ground water due to expansion of the project
along with mitigation measures.
Details are given in Chapter 4.
7. The PP should submit NOC from the Forest
Department indication that the area under
consideration does not fall under the Forest Acts and Section 4 & 5 of PLPA.
Forest NOC is attached as Annexure XX.
8. The NOC from Aravali Hill Notification, 1992
shall be obtained from District Collector.
AravaliNOC is attached as Annexure XXI.
9. The PP should provide the details of internal and external developments.
Details are given in Chapter 2.
Additional ToR
1. Latest status report of the project verified by the
RO, HPSPCB and MoEF& CCto be included.
Site visit report is attached as Annexure XVIII.
2. Confirmation of the land - use as per the
'Master-Plan' of the area from DTCP.
Land use of the project site is residential a per Master
Plan of Gurugram, 2031 and also permission for
development opf the project is obtained from DTCP,
Haryana
3. Approval of Air Port Authority of India
regarding the present height of the building
wherever applicable.
NOC from Air Port Authority of India for the project
constructed is attached as Annexure XXII.NOC will
be obtained for the towers proposed to be constructed from AAI prior commencing the construction
Modification and Expansion of Group Housing Project “Atharva Group Housing” at Sec-
109, Village PawalaKhusrupur, Gurugram, Haryana
EIA-EMP REPORT
M/s Raheja Developers Ltd. Page 20
1.11 STRUCTURE OF ENVIRONMENTAL IMPACT ASSESSMENT REPORT
The EIA report contains project features, baseline environmental setup, assessment of
environmental impacts, and formulation of mitigation measures, environmental management and
monitoring plan with risk & disaster management plan. EIA report contains following chapters
Chapter 1: Introduction
This chapter provides background information on need of project, need of EIA study, details of
violation and brief of the project. The scope and EIA methodology adopted in preparation of EIA
report have also been described in this chapter. It also covers the identification of the project &
project proponent, brief description of nature, size, location of the project and its importance to the
country and the region. Scope of the study details about the regulatory scoping carried out as per
the generic structure given in the EIA notification, 2006.
Chapter 2: Project Description
This chapter deals with the details of the project including particulars of residential & commercial
developments, estimated population, water supply, sewage collection and disposal, solid waste
generation and disposal, vehicle parking management, infrastructure facilities, power system,
landscaping and green belt development and fire fighting facilities, etc.
Chapter 3: Description of the Environment
This chapter presents the existing environmental status of the study area around the proposed
project including topography, drainage pattern, water environment, geological, climate, transport
system, land use, flora & fauna, socio-economic aspects, basic amenities etc. Environmental
assessment of the project site in regard to its capability to receive the development is also
discussed in this chapter.
Chapter 4: Anticipated Environmental Impacts and Mitigation Measures
This chapter describes the overall impacts of the project activities and underscores the areas of
concern, which need mitigation measures during construction and operation phase. It predicts the
overall impact of the project on different components of the environment viz. Air, water, land,
noise, biological, and socio-economic.
Chapter 5: Damage Assessment Plan
This chapter presents the assessment made for the damage incurred during the project development
and management measures to minimize the damage.
Chapter 6: Analysis of Alternatives
This chapter covers the details of various alternatives in respect of both location of site and
technologies to be deployed relevant to the project.
Chapter 7: Environmental Monitoring Programme
Modification and Expansion of Group Housing Project “Atharva Group Housing” at Sec-
109, Village PawalaKhusrupur, Gurugram, Haryana
EIA-EMP REPORT
M/s Raheja Developers Ltd. Page 21
This chapter covers the planned Environmental Monitoring Program during construction and
operation phase. It includes the technical aspects of monitoring the effectiveness of mitigation
measures.
Chapter 8: Disaster Management Plan
This chapter describes emergency management plan for an unlikely event of emergency at the
project.
Chapter 9: Project Benefits
This chapter describes the benefits accruing to the locality, neighborhood, region and nation as a
whole. It brings out details of benefits by way of improvement in the physical infrastructure, social
infrastructure, employment potential and other tangible benefits.
Chapter 10: Environmental Management Plan
This chapter details the inferences drawn from the environmental impact assessment exercise. It
provides mitigation and control measures for environmental management plan (EMP) for
minimizing the negative environmental impacts and to strengthening the positive environmental
impacts of the project. Technical aspects of monitoring the effectiveness of mitigation measures
have been given in this chapter.
This chapter provides mitigation and control measures for environmental management plan (EMP)
for minimizing the negative environmental impacts and to strengthening the positive
environmental impacts of the project.
Chapter 11: Summary and Conclusion
This chapter provides the summary and conclusions of the EIA study of the project with overall
justification for implementation of the project and also explanation of how, adverse effects will be
mitigated.
Chapter 12: Disclosure of Consultants Engaged
This chapter provides the disclosure of consultants engaged to carry out the EIA study along with
other additional studies.
Modification and Expansion of Group Housing Project “Atharva Group Housing” at Sec-
109, Village PawalaKhusrupur, Gurugram, Haryana
EIA-EMP REPORT
M/s Raheja Developers Ltd. Page 22
CHAPTER 2 :PROJECT DESCRIPTION
2.1 TYPE OF PROJECT
Project involves expansion and modification of the group housing project “Atharva” located at
Sec-109, Gurugram, Haryana. Built-up area of the project after expansion and modification will be
266094.125 m2 thus the project will fall under activity 8 (b) of schedule 1 of EIA Notification,
2006 as amended and is classified as Category B1.
However, the project involves violation of EIA Notification, 2006 thus the project will be
appraised as per notification of MoEF&CC, i.e. “SO 804(E)” dated 14.03.2017 and SO 1030 dated
8th March, 2018. As per the notification all building and construction projects irrespective of built-
up area will be treated as Category B1 and detailed EIA study and damage assessment study will
be required for assessment purpose.
2.1.1 DETAILS OF VIOLATION
M/s Raheja Developers Ltd. has obtained environmental clearance for development of group
housing project “Atharva” from SEIAA, Haryana vide Letter no. DEH/09/SEIAA/66 dated
01.04.2009 for area measuring 59,132.5722 m2(14.812 acres) and Built-up area of 1, 57,917.34 m2
attached as (Annexure I). The application was made under activity 8 (b), Category B of Schedule
1 of EIA Notification, 2006. After obtaining the environment clearance, there were amendment in
Haryana Building Bye Laws and allowable density of people/ha was increased than existing. To
avail the allowable benefit, planning for the project was modified and details are bulleted below
Reducing size/modification of unsold units to be constructed consequent increasing nos. of
DUs to 593. Construction of 72 nos. of servant units as required by Bye Laws.
Instead of developing 18 villas it was proposed to develop residential blocks of Independent
floors (G+3/G+5) leading to addition of 94 DUs.
Construction of additional tower “Tower IV” within the existing land as per available density
norms.
Construction of addition nursery school as per requirement of HUDA Bye Laws
Increasing nos. of EWS units from 116 to 125 numbers as per statutory requirement.
Increasing area of basement by 6134.08 m2 (to be constructed)
Increase in built-up area to 266094.125 m2 from 1, 57,917.34 m2
Addition of 0.8 acres of licensed land (adjacent to existing site in East direction) increasing
area to 15.612 acres from 14.812 acres due to revised plan from DGTCP. On the additional
licensed land additional construction will be done after statutory approvals.
Modification and Expansion of Group Housing Project “Atharva Group Housing” at Sec-
109, Village PawalaKhusrupur, Gurugram, Haryana
EIA-EMP REPORT
M/s Raheja Developers Ltd. Page 23
On assumption that since project is granted environment clearance under 8(b) activity which
covers the project having built-up area more than 1,50,000 sq. m. (no closing limit), they
considered that additional built-up area will automatically be covered in this clearance and has
thus not applied for revised environmental clearance. Later M/s Raheja Developers Ltd on
realizing requirement of obtaining re-environment clearance, have applied to obtain revised
environment clearance for modification &expansion of the project to SEIAA, Haryana vide letter
dated 26.10.2015. But the environmental clearance process took time so M/s Raheja Developers
Ltd has carried out the construction at the site as per modified planning in anticipation that the
work can be conducted on the basis of EC granted for project in 2009 with the proposed EMP and
following conditions of existing environmental clearance while application for re-environment
clearance for expansion is already in process. This has led to the violation of EIA Notification,
2006 as amended. The intent was not to violate but to expedite the construction, reduce market
pressure and optimize the time and money. Status of the construction carried out till date as per
modified planning is given in Table 2.1 below.
Table 2.1: Status of Construction at Site as Per Modified Planning
S.
No.
Development Covered
Area (m2)
No. of DU Status of Violation Remarks
1. Residential
Towers
89784.22 593 general
& 72 servant
units
FAR is same but nos. of units
to increase due to increase in
density norms.
Occupied-OC
Obtained
2. EWS 3,020.7 125 FAR is same but nos. of units
increased to 125 as per
requirement.
Occupied-OC
Obtained
3. Villas/Small
Towers (IFs)
14814.692 94 FAR increased, 11730.7 sq m
approved for 18 villas
Constructed
4. Basements 55915.9 2 Area increased, 53019.34 sq
m approved
Being used-
OC Obtained
5. Community
Building
202.614 -- Decreased. Constructed. OC Obtained
6. Convenient
Shopping
262.7 -- No Change. Constructed. --
7. School 1 804.7 -- School 1 approved. School 1 is
under
construction
as per
previous EC.
Modification and Expansion of Group Housing Project “Atharva Group Housing” at Sec-
109, Village PawalaKhusrupur, Gurugram, Haryana
EIA-EMP REPORT
M/s Raheja Developers Ltd. Page 24
Total 164805.526 -- -- --
M/s Raheja Developers Ltd have complied with all the environmental regulations applicable to the
project apart from the above mentioned violation. M/s Raheja Developers Ltd has obtained
consent to establish from HSPCB (Annexure IV) for construction as applicable under Air &
Water Act. M/s Raheja Developers Ltd has also obtained consent to operate under Air & water Act
(1981 & 1974) and Authorization under Hazardous Waste Rules, 2008 (Annexure V a, b & c) as
applicable for the project from HSPCB. Occupancy certificate was also obtained for the project
from the DTCP, Haryana (Annexure VI). All the provision of parking, water requirement, green
space, sewage management, structure stability are made at site as per the modified planning so as
to minimize the impact on the environment and the society.
2.2 PROJECT SITE LOCATION AND CONNECTIVITY
Project site is located at Sector 109, Village PawalaKhusrupur, Gurugram, Haryana.Location Map
of the project site is given below in Figure 2.1. Geographical co-ordinates of the center of project
site are28°30'30.94"N & 77° 0'24.76"E. Geographical coordinates of all the corners of the project
site are given in Table 2.2 and Figure 2.2. Project site is surrounded by residential colonies and
villages majorly. Details of surroundings of the project site are given in Table 2.3. Google map
showing location of project site & its surroundings within 500 m, 2 km and 10 km are attached as
Annexure VIII (a, b &c) respectively.
Site is well connected with the roads. A 24 m wide road as per the master plan, 2031 of Gurugram
traverses through the site. This road will be developed and will be handed over to HUDA. This
road connects the site to other sector roads and ultimately connects to the Dwarka Expressway
which is app. 640 m from the site in South direction. Dwarka expressway connects the site to the
IGI airport and then to Delhi. A sector road abuts the site in North direction. Bajghera road is at
app. 1.7 km from site in East direction which connects the site to rest of the Gurugram. Gurugram
Railway station is at app. 2 km from the site in South direction and Delhi Cantt. Railway station is
at app. 16 km from site in East direction. Dwarka sec-21 metro station is at 7 km from site in East
direction and IFFCO Chowk metro station is at app. 8 km from site in South direction. IGI airport
is at app. 7 km from site in East direction. Connectivity map of the site is given in Figure2.3.
Modification and Expansion of Group Housing Project “Atharva Group Housing” at Sec-
109, Village PawalaKhusrupur, Gurugram, Haryana
EIA-EMP REPORT
M/s Raheja Developers Ltd. Page 25
Figure 2.1: Location Plan of the Project
Table 2.2: Geographical Coordinates of the Project Site
Point as in Map (Figure 3) Latitude Longitude
A 28°30'31.86"N 77° 0'16.68"E
B 28°30'34.66"N 77° 0'21.04"E
C 28°30'34.63"N 77° 0'31.57"E
D 28°30'32.79"N 77° 0'31.56"E
E 28°30'32.77"N 77° 0'31.03"E
F 28°30'30.97"N 77° 0'30.94"E
G 28°30'31.03"N 77° 0'29.10"E
H 28°30'28.99"N 77° 0'28.97"E
I 28°30'28.87"N 77° 0'26.60"E
J 28°30'26.96"N 77° 0'26.60"E
K 28°30'26.99"N 77° 0'24.19"E
L 28°30'28.64"N 77° 0'24.15"E
M 28°30'28.72"N 77° 0'20.92"E
N 28°30'29.07"N 77° 0'20.84"E
O 28°30'29.11"N 77° 0'19.30"E
P 28°30'30.97"N 77° 0'19.34"E
Q 28°30'30.90"N 77° 0'16.80"E
Modification and Expansion of Group Housing Project “Atharva Group Housing” at Sec-
109, Village PawalaKhusrupur, Gurugram, Haryana
EIA-EMP REPORT
M/s Raheja Developers Ltd. Page 26
Figure 2.2: Geographical Coordinates of Project Site
Table 2.3: Site & Surrounding of the project (10 Km radius)
S. No. Feature Distance and Direction
1. Residential
International City
Vill. PanwalaKhusropur
Sector 110
Sector 105
Vill. Babupur
New Palam Vihar
Abuts site, NE 450 m, W
500 SE
1.1 km, S
600 m, NW 300 m, E
2. Commercial
Sector Markets
space by India Bulls, Neo Developers and Conscient One
within sectors
200-250 m, S
3. Industrial
Sec 18, 19 & 20
Sec-37, 36, 24, 33 & 35
5-6 km, SE
6-7 km, SW
4. Nearest City
Gurugram
Delhi
Site is located within Gurugram City. Delhi is app. 8 km from site in East direction
5. Nearest Highway
Dwarka Expressway
640 m, S
6. Nearest Railway Station
Gurugram railway Station
Delhi Cantt Railway Station
2 km, S
16 km, E
7. Nearest Airport
Indira Gandhi international Airport
7 km, E
8. Near-by Water body
Nazafgarh Drain
2.3 km, N
9. Near-by Eco-Sensitive Zone
Modification and Expansion of Group Housing Project “Atharva Group Housing” at Sec-
109, Village PawalaKhusrupur, Gurugram, Haryana
EIA-EMP REPORT
M/s Raheja Developers Ltd. Page 27
Sultanpur Bird Sanctuary 11.5 km, W
10. Near-by School
Planned schools (2 nos) within site
Eureka Pre-school
MMI
Chiranjivi Bharti School
Blue bells model school, Jiwan Jyoti school & CCA school
Skylark school of business & technology
Amity
Dronacharya Govt. college
Within site
1.7 km, SSE
2 km, E 3 km, E
3.5-4 km, S
2.3 km, S
6 km, E
5.0 km, S
11. Near-by Hospitals
Manipal Hospital
Max Vision Super Speciality Hospital
11.4 km, NW
15 km, NW
Figure 2.3: Connectivity map of the Project Site
2.3 LAYOUT PLAN OF THE PROJECT
Total area of the project site after modification is 15.612 acres (63,179.4 m2). Built-up area of the
project after the modification and expansion will be 266094.125 m2. Area detail and built-up area
summary is given in Table 2.4& 2.5.Modified site plan as approved by Department of Town and
Country Planning is attached as Annexure II.
Modification and Expansion of Group Housing Project “Atharva Group Housing” at Sec-
109, Village PawalaKhusrupur, Gurugram, Haryana
EIA-EMP REPORT
M/s Raheja Developers Ltd. Page 28
Table 2.4: Area Summary of Group Housing as per Awarded EC
S. No Description Areas as
Approved in
EC Letter
(2009)
Areas as Per Modified
Planning
(Existing +
Modification)
1. Total Plot Area 59,941.9 63,179.4
2. Area under 24 m wide road surrendered to
HUDA
5,913.3 5,913.3
3. Net Plot Area 54,028.6 57,266.1
4. Permissible Ground Coverage 20,979.7
(35 %)
22,112.8
(35%)
5. Achieved/Proposed Ground Coverage (% of
total plot area)
19.48 21.60
6. Achieved/Proposed Ground Coverage
Residential Towers
Convenient Shopping
Community Building
EWS
Villas/Small Towers (IFs)
Tower IV
Villas in additional land patch
School-1
School-2
Tower in additional land Patch
11,679.8
6,988.7
0
202.6 734.6
3,514.7
0 0
239.2
0 0
13646.824
6,988.7
262.8
202.6 734.6
3,514.7
399.2 0
239.2
227.2 1077.824
7. Total Permissible FAR
Permissible FAR (@1.75 of total plot
area)
Permissible F.A.R. as per TOD Policy
Additional GRIHA F.A.R. @ 12% (4
star rating)
1,04,898.4
1,04,898.4
--
--
251403.833
--
1,94,273.081
57,130.752
8. Proposed FAR
Residential Towers
Convenient Shopping
Community Building
EWS
Villas/Small Towers (IFs)
Tower IV
Tower in additional land patch
Additional EWS
Additional Commercial
Residential Units over Convenient
Shopping
1,04,898
89,588.3
262.7 295.6
3020.7
11,730.7(villas)
0 --
--
-- --
162342.734
89784.22
262.7 202.614
3020.7
14814.692
820.9 46709.948
5323.385
588.67 814.905
9. Basements Lower basement
Upper basement
Basement under Community Building
Basement under Convenient Shopping
53,019.3 0
0
0
0
59153.38 27638.813
31049.167
202.7
262.7
10. Built-up/Covered Area as calculated in 2009* 1,57,917.3 221496.1139
11. Stilt 0 1552.5
Modification and Expansion of Group Housing Project “Atharva Group Housing” at Sec-
109, Village PawalaKhusrupur, Gurugram, Haryana
EIA-EMP REPORT
M/s Raheja Developers Ltd. Page 29
12. Area of School*
School 1
School 2
804.7
804.7
0
2428.406
1214.203
1214.203
13. Non FAR (Service area, Balcony area ,stilt, Mumty, Machine Room, Guard
Room /modification as per notification 2011
due to change in definition)
23,707.0 40617.105
14. Built-up Area (As defined in EIA Notification amendment dated 2011)
1,82,429.1 266094.125
15. No. of Dwelling Units 528 1093
16. N No. of EWS Units 116 191
17. No. of Basements 2 2
18. No. of Floors G+16 G+47/G+13/G+8/G+5
19. After full completion Green Area (@% of Net
Plot Area
32.2 35.7
20. After full completion Green Area 17,385.1 20,447.0
* Built-up area of school, Non-FAR area at floors and area under services was not added in built-up
area. As these were School is free from FAR and other Non-FAR area at floors and services not
considered as covered area by architect. In 2009 built-up area used to be assumed as covered area as
defined in plans. However, clarity on definition of built-up area came with amendment, 2011 to EIA Notification. Thus, now we have calculated built-up in accordance to EIA Notification, 2011 (as per revised definition)
Table 2.5: Summary of Built-up Area
S. No. Particulars Area (m2)
1. Proposed FAR (a + b + c + d) 162342.7339
a Residential FAR (Villa +Towers) 152944.665
b EWS 8344.085
c Convenient Shopping 262.7
d Community Building 202.614
e Additional Commercial 588.67
2. Non-FAR (Service area, Balcony area, stilt, Mumty,
Machine Room, Guard Room /modification as per
notification 2011 due to change in definition)
40617.105
3. Area of Schools 2428.406
4. Stilt 1,552.5
5. Basement Area 59153.38
6. Total proposed Built-up Area 266094.125
2.4 LAND USE PLAN OF THE PROJECT SITE
Land use of the project site is residential as per the Master Plan of Gurugram, 2031. There is no
change in land use due to project development.Master plan with the location of the project site is
given in Figure 2.4. The project had received license from Directorate of Town and Country
Planning Chandigarh vide memo of 257 dated 07.11.2007 and license no. 14 dated 13.02.2011 and
copy of license are attached as Annexure IX.
Modification and Expansion of Group Housing Project “Atharva Group Housing” at Sec-
109, Village PawalaKhusrupur, Gurugram, Haryana
EIA-EMP REPORT
M/s Raheja Developers Ltd. Page 30
Figure 2.4: Gurugram Manesar Urban Complex Master Plan, 2031 and Project Site Location
2.5 BASIC AMENITIES
2.5.1 WATER REQUIREMENT
Water requirement during construction phase is app. 50-60 KLD. Source of water during construction
is treated water from nearby CSTP of HUDA (at Manesar). Source of water during operation phase is
HUDA supply supplemented by private water tankers. Total water requirement for the project is 755
KLD out of which 588 KLD is domestic water requirement, 123 KLD is horticulture water
requirement and 44 KLD is used for road and car washing during non-rainy season. Fresh water
requirement is 411 KLD and recycled water requirement is 344 KLD. Detailed water calculations are
given in Table 2.6. Water balance diagram are given in Figure 2.5 & 2.6.
Sewage generation from the project site is expected to be 506 KLD which should be treated in STP of
capacity 550 KLD. STP of 550 KLD is already constructed at the site and is operational. Treated
water from the STP is being used for flushing, horticulture and road &car washing. Remaining treated
water is used for construction at the site or can be given to nearby construction sites or can be
disposed-off in sewer. STP with the SAF (Submerged Aerated filter) technology is constructed at the
site and same technology will be adopted for expansion. STP is open to air. Water is treated upto
tertiary level in the STP. Details of sewage treatment methodology and process are given in section
2.5.2. Water supply and sewerage layout are attached as Annexure X a and B
Modification and Expansion of Group Housing Project “Atharva Group Housing” at Sec-109, Village PawalaKhusrupur, Gurugram,
Haryana
EIA-EMP REPORT
M/s Raheja Developers Ltd. Page 31
Table 2.6: Daily Water requirement at Calculations
Category Standards
(LPCD)
Existing (Constructed) Expansion (Not Constructed) Total
Population/Area
(sq m)-
Constructed
Units
Water
Requirement
(KLD)
Fresh
Water-
KLD
Recycled
Water-
KLD
Population/Area
(sq m)
Water
Requirement
(sq m)
Fresh
Water-
KLD
Recycled
Water-
KLD
Total Water
Requirement
(KLD)
Total
Fresh
Water-
KLD
Total
Recycled
Water-
KLD
Residents 86 3829 330 231 99 2470 212 148 64 542 379 163
Staff/Students 30 406 12 8 4 358 11 8 3 23 16 7
Visitors 15 583 9 6 3 939 14 10 4 23 16 7
Total
Domestic
Population
-- -- 351 245 106 -- 237 166 71 588 411 177
Green Area
(m2)
6 liters/sq
m 17385.1sq m 105 0 105 3061.9sq m 18 0 18 123 0 123
Road and Car
Washing -- --- 44 -- 44 -- -- -- -- 44 0 44
Total Water
Requirement -- -- 500 245 255 -- 255 166 89 755 411 344
Sewage Generation 302 204 506
STP Capacity 550 -- 550
Treated Water 242 163 405
Re-usage of Treated
Water
Flushing
Horticulture
Road and Car washing
344
177
123
44
Usage for construction at
site/Disposal in Sewer
only after treatment
61
Modification and Expansion of Group Housing Project “Atharva Group Housing” at Sec-109, Village PawalaKhusrupur, Gurugram,
Haryana
EIA-EMP REPORT
M/s Raheja Developers Ltd. Page 32
Figure 2.5: Water Balance Diagram-Dry Season
Total Water Requirement
755 KLD
Fresh Water Requirement
411 KLD Recycled Water Requirement
344 KLD
Flushing
177 KLD
Consumption
411 KLD
Horticulture
123 KLD
Road and Car washing
44 KLD
Sewage
506 KLD
80%
100%
STP
550 KLD
80%
405 KLD
Sewer
61 KLD
344 KLD
Modification and Expansion of Group Housing Project “Atharva Group Housing” at Sec-109, Village PawalaKhusrupur, Gurugram,
Haryana
EIA-EMP REPORT
M/s Raheja Developers Ltd. Page 33
Figure 2.6: Water Balance Diagram-Monsoon Season
Total Water Requirement
588 KLD
Fresh Water Requirement
411 KLD Recycled Water Requirement
177 KLD
Flushing
177 KLD
Consumption
411 KLD
Horticulture
0 KLD
Road & Car Washing
0KLD
Sewage
506 KLD
80%
100%
STP
550 KLD 80%
405 KLD
Sewer
228 KLD
177 KLD
Modification and Expansion of Group Housing Project “Atharva Group Housing” at Sec-
109, Village PawalaKhusrupur, Gurugram, Haryana
EIA-EMP REPORT
M/s Raheja Developers Ltd. Page 34
2.5.2 WASTE WATER TREATMENT SYSTEM
2.5.2.1 SEWERAGE SYSTEM
SAF is an extremely efficient and well-proven biological treatment process which is used
to biodegrade organic matter. It can also reduce nitrogen in the wastewater to deliver a treated
wastewater that exhibits a very high level of BOD, COD and Nitrogen reduction along with high
levels of reduction in suspended solids. The SAF could be described as a “box of media”. It
utilizes a rigid, corrugated, structured polypropylene media to give a high surface area for biomass
attachment. The media is arranged into cells-in-series where effluent is contacted with the fully
submerged media in the presence of co-current aeration. Air is supplied by two low-maintenance
regenerative blowers. Air enters the process below the media via fine bubble membrane diffusers.
A secondary clarifier tank follows the SAF for removal of any biomass that sloughs off the media
during operation. Biological phosphorus and nitrogen removal can be achieved with the SAF since
the design incorporates sequential staged operations as required for BNR flow schemes.
Phosphorus removal utilizes the anaerobic, balance tank (septic tank) used prior to the SAF.
Recycled sludge from the final clarifier is mixed with the influent in this stage. Nitrogen removal
is then achieved via denitrification in the first cell of the SAF where, with no air injected, and the
introduction of recycled nitrified effluent from the end of the process, the process becomes anoxic.
The latter SAF cells are fully aerated and BOD removal and nitrification are achieved in these.
Full BNR requires a fourcell SAF, minimum. Typically, effluent from a full BNR scheme will be:
BOD less than 10 mg/l
Total nitrogen less than 5 mg/l
Ammonia nitrogen less than 1 mg/l
Total phosphorus less than 0.5 mg/l
Process:
Raw sewage from the sewage pump station is pumped through the inlet works of the WWTP
where it undergoes screening for removal of inorganics prior to entering the balance tank. The
balance tank provides a buffer against peak inflows and provides a steady inflow to the
downstream process. Prior to entering the treated effluent storage tank the effluent may be filtered
(to achieve Class A quality). The treated effluent is stored in the irrigation tank prior to discharge
to the irrigation field or re-use, whichever is applicable.
Inlet Works
All raw sewage is pumped to the inlet works of the waste water treatment plant. A mechanical
screen is installed to remove all the inorganic material from the sewage and dispose it to the waste
bin below.
Modification and Expansion of Group Housing Project “Atharva Group Housing” at Sec-
109, Village PawalaKhusrupur, Gurugram, Haryana
EIA-EMP REPORT
M/s Raheja Developers Ltd. Page 35
Balance Tank
The Balance Tank is designed to handle peak flows and allow a pre-determined and controlled
flow for subsequent treatment. The waste water is temporarily stored in the Balance Tank before
being pumped by a submersible Balance Pump to Primary Tank 1. The flow rate is set using the
flow control valves located in the Balance Tank. Excess flow is returned to the same tank.
The Balance Tank level is regulated by 3 float-type level switches. A coagulant is dosed into the
discharge of the Balance Pump by the Coagulant Dosing Pump whenever the Balance Pump runs.
The coagulant assists both in aiding the settlement of settleable solids in the plant and in reducing
the phosphorous level in the treated effluent. The Coagulant Dosing pump draws from a bunded
carboy of coagulant.
Primary Tanks
Primary Tank 1 provides additional buffer capacity of inlet flow whilst Primary Tank 2 creates a
steady inflow for the Anoxic and the Aerobic Tanks. After the waste water is delivered to Primary
Tank 1, the top water level of the influent waste water is allowed to overflow into Primary Tank 2.
Both tanks encourage sedimentation of between 30 and 50% of the influent suspended solids and
allow anaerobic digestion to take place.
In anaerobic waste water treatment, bacteria digest organic material in the absence of oxygen and
transform part of the sludge to gases such as methane and carbon dioxide. In this design, the
anaerobic treatment occurs in Primary Tank 1 and Primary Tank 2.
Anoxic Tank
The top water level of the influent waste water is allowed to overflow from Primary Tank 2 to the
Anoxic Tank. The Anoxic Tank allows nitrate-specific bacteria to use nitrate (NO3) as an oxygen
source and a nutrient in a process called denitrification. This activity helps to remove nitrogen
based pollutants such as urea and ammonia by converting them into nitrate and nitrite before
releasing them as nitrogen gas into the atmosphere. The tank is enriched with returned activated
sludge (RAS) from the Clarifier to provide a plentiful supply of food for the bacteria. The partially
treated effluent from the Anoxic Tank contains approximately 65% of the pollution load of the
original sewage influent entering the waste water plant.
Aerobic Tank
The top water level of the influent waste water is allowed to overflow from the Anoxic Tank to the
Aerobic Tank where it is aerated. Air is introduced into the Aerobic Tank by the Biological Air
Blower through air diffusers located beneath a submerged media. Coarse air bubbles provide
favourable conditions for the growth of aerobic bacteria.
The Aerobic Tank which contains the submerged media has a large surface area, allowing bacteria
and other micro-organisms to thrive and form a biological film. These micro-organisms utilise the
dissolved oxygen in the air bubbles in the waste water to consume dissolved matter and by so
Modification and Expansion of Group Housing Project “Atharva Group Housing” at Sec-
109, Village PawalaKhusrupur, Gurugram, Haryana
EIA-EMP REPORT
M/s Raheja Developers Ltd. Page 36
doing remove a majority of the colloidal contaminants present in the waste water by converting
them into carbon dioxide and biological floc.
Floc is then allowed to settle in the Clarifier from where it is removed, thereby reducing the
accumulation of sludge. Friction from the coarse air bubbles further serves to scour and release
dead biomass from the media. Th is Aerobic Tank is partially divided by a baffle so as to prevent
under-aerated waste water from prematurely moving to the next stage in the treatment process.
This baffle also serves to alter the flow direction such that the partially treated waste water will
make intimate contact with the submerged media before entering the Clarifier.
Clarifier
The Clarifier removes heavier solids by means of settlement and separation from the liquid phase.
It is designed to have a large surface area with adequate retention time. The hopper bottom
channels the sediment to the centre of the Clarifier tank before the sediment is returned to Primary
Tank 1.
Clear liquor from the top of the Clarifier is decanted into the Chlorine Contact Tank. In this
process, clarification and thickening happen at the same time. Separation of solids from the liquid
stream occurs to produce a clarified effluent with low suspended solid levels. From thickening, the
conveyance of sludge particles to the bottom of the tank results in a slightly concentrated
underflow, known as return activated sludge (RAS).
Chlorine Contact
The top water level of the influent waste water is allowed to overflow from the Clarifier to the
Chlorine Contact Tank. The Chlorine Contact Tank contains chlorine in tablet form and it is
designed to provide 30 minutes minimum contact time for effective disinfection of the influent
with chlorine, a powerful disinfectant.
This is a process whereby chlorine compounds are added to the treated waste water for the purpose
of pathogen reduction. Calcium hypochlorite tablets are in constant contact with the effluent to
ensure that the effluent is safe for disposal.
Media Filter
A media filter is required to meet the quality to re-use it again. Before reaching the Irrigation
Tanks the effluent is filtered using a Media Filter which will remove particles above 10 microns in
size. When the pressure drop across the Media Filter reaches a pre-determined set point the Media
Filter is automatically backwashed by the Media Filter Backwash Pump which draws water from
the Irrigation Tank with the dirty backwash wash water going back to the Balance Tank.
Modification and Expansion of Group Housing Project “Atharva Group Housing” at Sec-
109, Village PawalaKhusrupur, Gurugram, Haryana
EIA-EMP REPORT
M/s Raheja Developers Ltd. Page 37
Figure 2.7: Typical flow Diagram of SAF Process Cycle
2.5.3 POWER REQUIREMENT
Maximum power demand for the project is estimated to be 8259.97 kVA. Source of power will be
DHBVNL.
Details of D.G Sets
During power failure the source of supply is through DG sets which are acoustic in nature. The total
750 kVA (500*1+250*1) DG sets are installed at site. 2 DG sets of total capacity 1000 kVA
(500*2) is proposed to be installed as per raise in demand. Layout showing electrical HT & LT
room and DG sets are given in Annexure XI aand electrical SLD is attached as Annexure XI b.
2.5.4 STORM WATER MANAGEMENT SYSTEM
Storm water drainage system is provided at project site for channelizing storm water and prevents
local flooding. Covered storm water drains are provided at the site. Run-off from the site is
collected and recharged into the ground through 7 nos. of RWH pits existing at the site. Recharge of
the rainfall run-off to ground not only prevents the local flooding during rains but als helps in
augmenting the ground water level of the aquifers. CGWB has declared entire Gurugram district as
notified zone in 2011. Ground water level in project area is app. 50 m bgl. Stage of ground water
development in project area is app. 308%. Run-off available from the site annually is calculated and
is presented in the Table 2.7. Calculations for rain water harvesting pits are given below in Table
2.8. Layout plan showing location of RWH pits is attached as Annexure XII. Schematic diagram of
RWH pit is given on Figure 2.8.
Table 2.7: Available Run-off from Site
S. No. Catchment Area (sq m) Run-off
Coefficient
Average
Annual
Rainfall
(mm)
Available
Annual
Run-off
(cum)
1. Roof top 13646.824 0.9 596 7320.1564
2. Hard green 10,966.3 0.6 596 3921.5489
3. Soft green 9,480.7 0.2 596 1130.0994
Modification and Expansion of Group Housing Project “Atharva Group Housing” at Sec-
109, Village PawalaKhusrupur, Gurugram, Haryana
EIA-EMP REPORT
M/s Raheja Developers Ltd. Page 38
4. Paved Areas 29085.576 0.7 596 12134.502
Total Run-off 24506.307
Table 2.8: Calculation for RWH Pits
S. No. Catchment Area (m2) Run-off
Coefficient
Peak
Hourly
Rainfall
(m)
Available
Annual
Run-off
(cum)
1. Roof top 13646.824 0.9 0.055 675.517
2. Hard green 10,966.3 0.6 0.055 361.88
3. Soft green 9,480.7 0.2 0.055 104.28
4. Paved Areas 29085.576 0.7 0.055 1119.79
Total Run-off 2261.48
Retention Time 10 min
Available Run-off in 10 min 226.1
Size of RWH Pit 36
Nos. of RWH Pit 6.3
Nos. of Pits proposed 7
No. of Pits Existing 6
No. of Pits to be Constructed 1
Figure 2.8: Schematic Diagram of Rain Water Harvesting Pit
Modification and Expansion of Group Housing Project “Atharva Group Housing” at Sec-
109, Village PawalaKhusrupur, Gurugram, Haryana
EIA-EMP REPORT
M/s Raheja Developers Ltd. Page 39
2.5.5 PARKING FACILITIES
Adequate parking is provided to accommodate the expected vehicles during operation phase of the
project.Parking is provided in accordance to HUDA Bye Laws. Parking required and proposed
parking is described below;
Parking Required:
As per MoEF&CC norms:
For Residential facilities = 1 ECS/ 100 m2 FAR area
= 161288.75/100 = 1612 ECS
For Commercial & Community = 1 ECS/ 50 m2 FAR area
= 851.37/50 = 17 ECS
For Nursery school = 1 ECS/ 50 m2 FAR area
= 2428.406/50 = 48 ECS
Total parking required as per MoEF&CCNorms= 1612+17+48 = 1677 ECS
As per Haryana Bye laws:
For Main DU: 1.5 ECS per DU’s (1093 DU’s) = 1640 ECS
Parking Proposed:
Parking provided in Upper Basement = 825 ECS
Parking provided in Lower Basement = 752 ECS
Parking provided on Surface = 119 ECS
Parking provided in Stilt = 40 ECS
Total Parking Provided
(Residential, Commercial, EWS, Community, School) = 825 + 752 + 119 + 40 = 1736 ECS
Car parking of 1,736 ECS will be provided within project site to accommodate expected vehicles.
Car Parking & Traffic circulation for surface and basement are attached as Annexure XIII a, b &
c.
2.5.6 SOLID WASTE MANAGEMENT FACILITY
Solid waste is generated both during construction as well as during operation phase. Solid waste
generated during construction phase is majorly excavated materials, cement bags, bricks, concrete,
Modification and Expansion of Group Housing Project “Atharva Group Housing” at Sec-
109, Village PawalaKhusrupur, Gurugram, Haryana
EIA-EMP REPORT
M/s Raheja Developers Ltd. Page 40
MS rods, tiles, wood etc. Table 2.9 details the solid waste management plan during construction
phase.
Table 2.9: Solid Waste Management during Construction Phase
S. No. Solid waste Solid waste Management
1. Waste materials like MS Rods, bricks, concrete, broken tiles,
wood pieces, cement bags etc.
Construction waste should be segregated into recyclable/reusable and discarded material. Recyclable
material should be sold to authorize dealers. Re-usable
material should be stored under covered conditions at site and reject should be disposed-off at the designated locations
by HUDA. Waste should be transported in covered vehicles
only.
2. Excavated Soil
Top soil should be stripped and stored in covered condition. Top soil should be used for landscaping within the project
site. Remaining excavated soil should be re-used within the
site for filling and leveling and construction of roads. Excess muck should be disposed-off at the designated locations.
3. Domestic Waste Waste generated from labour hutment should be segregated
into recyclable and rejected fraction. Recyclable waste
should be sold to authorized vendor and remaining should be disposed-off through local agencies in the area responsible
for waste management
During operation phase, waste comprise of municipal waste. It is estimated that approx. 3624 kg
per day (@0.5 kg per capita per day for the residents, 0.25 kg per capita per day for the staff &
0.15 kg per capita per day for the visitors and 0.2 kg/acres/day is considered for landscape wastes)
is estimated to be generated from project site after expansion and modification. Estimations for
solid waste generation during operation phase are given in Table 2.10. Municipal Waste is
managed as MSW Rules, 2016.
Table 2.10: Calculation of Solid Waste Generation
Category
Standard
(kg/day)
Existing
Population/A
rea (sq m)
Existing
Waste
Generation
(kg/day)
Expansion/
Modification
Population/
Area (sq m)
Expansion/Mo
dification
Waste
Generation
(kg/day)
Total
Waste
Generat
ion
Recyclable
/Re-usable Rejects
Residents 0.5 3829 1915 2470 1235 3150 945 2205
Staff/Students 0.25 406 101 358 90 191 57 134
Visitors 0.15 583 88 939 141 229 69 160
Green Area
(acre)
0.2 kg/acre/
day 4.3 1 0.76 0.1 1 1 0
STP Sludge -- -- 30 -- 23 53 53 0
Total Waste
Generation -- --
2135 --
1489 3624 1125 2499
(Source: For Waste Collection, Chapter 3, Table 3.6, Page no. 49, & Bio-Medical waste Chapter 7,
page 148 of Central Public Health & Environment Engineering Organization, Ministry of Urban
Development, (Government of India, May 2000))
Collection and Segregation of waste
Modification and Expansion of Group Housing Project “Atharva Group Housing” at Sec-
109, Village PawalaKhusrupur, Gurugram, Haryana
EIA-EMP REPORT
M/s Raheja Developers Ltd. Page 41
Door to door collection system is provided for collection of domestic waste
Local vendors are hired for waste collection, management and disposal
Separate colored bins for dry recyclables and rejected waste are provided to residents as well
as in common and open areas
Treatment of waste
Sludge from STP is stabilized and is used as manure
Landscape waste is composted in pit and is used as manure
Disposal
Rejected fraction of the waste is collected and disposed by local agencies on daily basis.
Recyclable waste and E-waste is sold to authorized vendors
Used oil from DG sets is sold to authorized vendors
2.5.7 Green Belt Development
Total green area measures 20,447 m2 i.e. 35.7 % of the net plot area is proposed to be put under
green cover. At present, 17,385.1 sq m of area is already under green cover at site. Evergreen and
native species are preferably planted at the project site. Native species are adapted to natural
conditions and also requires less aftercare and maintenance. Trees with large & round canopy are
planted. Plantation act as noise buffer and also provide surface for dust settlement. Trees planted
atthe project site are given in Table 2.11below. Landscape plan is attached as Annexure XIV.
Table 2.11: Trees Proposed to be planted at Site
S. No. Botanical Name Common Name
Trees
1 Albizzia lebbek Woman’s tongue tree
2 Anthocephaluscadamba Cadamba
3 Bauhinia blakeana Hong Kong Orchid
4 Bismarckianobilis Bismarckia Palm
5 Cassia fistula Amaltas
6 Cassia javanica Apple blossom
7 Crataevaadansonii Caper tree
8 Delonix regia Gulmohar
9 FicusAlii Carrion Plant
10 FicusBenjamina Weeping fig
11 Ficuslyrata Fiddle leaf
12 Ficusreginald Fig tree
13 Pterospermumacerifolium Kanak Champa
14 Plumeria obtusa/Rubra Frangipani
15 Wodiatia bifurcate Fox tail palm
16 Azadirachtaindica Neem
Shrubs
1 Dypsislutescens Arcea palm
2 Cestrum nocturnum Raatrani
3 Cycus revolute Japanese sago palm
4 Jatropha integerrima Peregrina
Modification and Expansion of Group Housing Project “Atharva Group Housing” at Sec-
109, Village PawalaKhusrupur, Gurugram, Haryana
EIA-EMP REPORT
M/s Raheja Developers Ltd. Page 42
5 Rhapis palms Broad leaf lady palm
6 Durantagoldeana Golden dewdrop
7 Ficus panda Golden ficus
8 Tecomagaudichaudi Yellow bells
9 Pittosporum tobira Japanese Mock Orange
10 Tecomacapensis Cape honeysuckle
11 Cyperusalternifolius Umberella palm
12 Anthrostylidiumurbanii Dry yellow bamboo
Grass/herbs
1 Alternetheraficoidea Red fine leaf
2 Ophiopogon japonicas Monkey grass
3 Lantana sellowiana Lantana
4 Wedeliacalendulacea Creeping oxeyes
5 Phalarisarundinacea Ribbon grass
6 Zephyranthesrosea Pink rain lily
7 Asparagus plumosa Asparagus
Creepers
1 Clerodendronsplendens Glory tree
2 Bignonia venusta Flame vine
3 Bougainvillea bonsai Bougainvillea
(Source: Guidelines for developing Green Belts by CPCB, 2000)
2.5.8 FIRE FIGHTING SYSTEM
Project involves area development. Firefighting equipment is proposed to provide during
construction and operation phase as per NBC and other applicable codes and standards at the site.
Further all the developers will provide the required firefighting equipment in respective plots. Fire-
fighting system will be provided keeping in view guidelines of the following. Fire Fighting Plan
for the project site is attached as Annexure XV.
National Building Code Sept 2005: Part IV for Fire Protection
HUDA Bye-Laws.
Relevant BIS codes: Specifically, IS: 3044, IS: 5290 and IS: 5312, IS: 908 and IS:2190,
IS: 3844, IS: 15105.
Consultation with local Fire Officer.
All Buildings have been provided with fire protection arrangements such as hose reel, hose, wet
riser, automatic sprinkler system in entire building, manual call points, automatic fire detection
system in entire buildings, underground water storage tank, overhead water tank, fire pumps,
potable fire extinguishers, exit signs, P.A. System, Yard Hydrants, Fireman’s lift grounding
switch, cautionary notices in lifts & restricted areas in case of fire, display of fire evacuation plan,
D.G. set, Compartmentalization, (meeting NBC requirement, 2005-part IV) and fire control room
from fire safety point of view. Fire NOC was obtained for the towers constructed and is attached
as Annexure XXIV.
Modification and Expansion of Group Housing Project “Atharva Group Housing” at Sec-
109, Village PawalaKhusrupur, Gurugram, Haryana
EIA-EMP REPORT
M/s Raheja Developers Ltd. Page 43
2.6 DETAILS OF CONSTRUCTION MATERIALS
Construction material required for construction of the completed and expansion/modification of the
project is given in Table 2.12below. List of building material along with R & U value for the
project is given below in Table 2.13. List of machinery to be used during construction phase of
remaining structures is listed below.
Table 2.12: Details of Construction Materials Required for The Project
S. No. Material Total Built-up (sq m) Quantity
(MT)/ sq m
Quantity for Existing +
Expansion &
Modification (MT)
1 Cement 266094.125 0.16 42575.06
2 Steel 266094.125 0.06 15965.65
3 Sand 266094.125 0.41 109098.6
4 Aggregate 266094.125 0.62 164978.4
5 Bitumen (road) 12,635.88 0.4 5054.4
Table 2.13: List of building materials to be used at site
Type of Construction U values (in W/m2deg C)
Walls:
Brick:
Plastered both sides 3.24
Solid Unplastered 2.67
Plastered both sides 2.24
Concrete, Ordinary, Dense:
-152mm 3.58
-203mm 3.18
Concrete block:
CLC Fly ash block 1.19
Hollow Concrete block, 220mm, single skin, outside rendered, inside plastered:
CLC Fly ash block 1.70
Roofs Flat
Reinforced concrete slab, 100mm, scered 63-12 mm, 3 layers bituminous felt
3.35
Floors:
Concrete on ground or hardcore fill 1.13
+ Grano, Terrazze or tile finish 1.13
+ Wood block finish 0.85
Exposure South Shelterd:
Single glazing 3.97
Double glazing 6 mm space 2.67
List of Machinery Used During Construction
Dumper
Concrete mixer with hopper
Excavator
Concrete Batching Plant
Cranes
Modification and Expansion of Group Housing Project “Atharva Group Housing” at Sec-
109, Village PawalaKhusrupur, Gurugram, Haryana
EIA-EMP REPORT
M/s Raheja Developers Ltd. Page 44
Road roller
Bulldozer
Tower Cranes
Hoist
Labor Lifts
Concrete pressure pumps
Mobile transit mixer
Modification and Expansion of Group Housing Project “Atharva Group Housing” at Sec-
109, Village PawalaKhusrupur, Gurugram, Haryana
EIA-EMP REPORT
M/s Raheja Developers Ltd. Page 45
CHAPTER 3 :DESCRIPTION OF ENVIRONMENT
3.1 GENERAL
The baseline environmental status forms the basis for evaluation of anticipated impacts due to
development on the existing conditions. This can be broadly grouped into physical, biological, and
socio-economic environments. Physical environment includes air, meteorology, noise, water, soil,
land; biological environment includes aquatic and terrestrial flora & fauna and socio-economic
environment includes demographic details, civic infrastructure, public services, surrounding
monuments, commercial facilities, employment levels, sources and levels of income, economic
base of the area, land values, land ownership, etc. Baseline conditions at and around the project are
described in following sections:
3.2 STUDY AREA & PERIOD
Project site is located at Sec-109, Village PawalaKhusrupur, Gurugram, Haryana. Geographical
coordinates of the project site are 28°30'30.94"N &77° 0'24.76"E. Study area is considered for EIA
study and is divided into core zone and buffer zone. Project site is considered as core zone and 10
kms zone is buffer zone. Topographic map showing the study area is given in Figure 3.1.Baseline
monitoring study period is January, 2018. Baseline study includes collection of primary and
secondary data. Primary data on ambient air quality, soil quality and noise level were collected
from site. Secondary data collected from various departments like Indian Meteorological
Department (IMD), Central Ground Water Board, Geological Survey of India, State Ground Water
Department, State Pollution Control Board, Census of India and Local Forest Department, Non -
Governmental Agencies etc.Following section describes the nature, type and characteristics of the
following heads:
Natural & Physical Environment
Land Environment
Water Environment
Air Environment
Noise Environment
Biological Environment
Socio-Economic Environment
Modification and Expansion of Group Housing Project “Atharva Group Housing” at Sec-109, Village PawalaKhusrupur, Gurugram,
Haryana
EIA-EMP REPORT
M/s Raheja Developers Ltd. Page 46
Figure 3.1: Topographic Map Showing Study Area
Modification and Expansion of Group Housing Project “Atharva Group Housing” at Sec-
109, Village PawalaKhusrupur, Gurugram, Haryana
EIA-EMP REPORT
M/s Raheja Developers Ltd. Page 47
3.3 DESCRIPTION OF SITE
Projectsite is located at Sector-109, Village PawalaKhusrupur, Gurugram, Haryana. Project is
surrounded by residential colonies and villages majorly. Land use of the project site is residential as
per Gurugram Master Plan, 2031. Project is developed as per the assigned land use of the area. Also
permission is obtained from Directorate of Town and Country planning for development of the
project and copy of license is attached as Annexure IX. Project site is flat land with elevation at site
ranging from 215-216 m amsl with the level difference of 1 m. Till date 164805.526 sq m of area is
constructed at site. Project activities have been taken under project premises only. Project site is well
connected with the roads.
3.4 ENVIRONMENT & SOCIAL SETTINGS OF THE STUDY AREA
The study area falls under PawalaKhusrupurvillage of GurugramDistrict. To establish the existing
physical, natural, socio-economic and cultural environment condition of the study area, data has been
collected through primary sources and secondary sources. Baseline data was generated during
January, 2017. Details of baseline environment of the study area are given in sections below. Map
showing location of baseline monitoring stations is given below in Figure 3.2.
Modification and Expansion of Group Housing Project “Atharva Group Housing” at Sec-109, Village PawalaKhusrupur, Gurugram,
Haryana
EIA-EMP REPORT
M/s Raheja Developers Ltd. Page 48
Figure 3.2: Map Showing Location of Baseline Monitoring Stations
Modification and Expansion of Group Housing Project “Atharva Group Housing” at Sec-
109, Village PawalaKhusrupur, Gurugram, Haryana
EIA-EMP REPORT
M/s Raheja Developers Ltd. Page 49
3.5 METEOROLOGY
3.5.1 CLIMATE & TEMPERATURE
The project site falls in Gurugram city. The city experiences four distinct seasons - spring (February -
March), summer (April - August), fall/autumn (September - October) and winter (November -
January), along with the monsoon season setting in towards the latter half of the summer. Summers,
from early April to mid-October, are typically hot and humid, with an average daily June high
temperature of 40 °C (104 °F). The season experiences heat indices easily breaking 43 °C (109 °F).
Winters are cold and foggy with few sunny days, and with a December daytime average of 3 °C
(37 °F). The Western Disturbance brings some rain in winters that further adds to the chill. Spring and
autumn are mild and pleasant seasons with low humidity. The monsoon season usually starts in the first
week of July and continues till August. Thunderstorms are not uncommon during the Monsoon. The
average annual rainfall is approximately 596 mm (23.5 in.). Climate data of Gurugram, Haryana is
given in Table 3.1. The monthly variations in temperature during year 2017 are presented in Table 3.2.
Modification and Expansion of Group Housing Project “Atharva Group Housing” at Sec-109, Village PawalaKhusrupur, Haryana
EIA-EMP REPORT
M/s Raheja Developers Ltd. Page | 50
Table 3.1: Climate data of Gurugram, Haryana
Table 3.2: Monthly Temperature data of Gurugram, Haryana (2017)
Month Jan,17 Feb,17 Mar,17 Apr,17 May,17 Jun,17 Jul,17 Aug,17 Sep,17 Oct,17 Nov, 17 Dec, 17
Max 24 28 34 42 40 37 40 39 37 38 31 26
Mean 18 22 29 37 35 34 36 36 34 35 27 22
Min 12 14 19 28 28 28 32 31 30 31 24 18
Source: www.worldweatheronline.com
Month Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Year
Record high °C (°F) 21.1
(70)
24.2
(75.6)
30.0
(86)
36.2
(97.2)
39.6
(103.3)
39.3
(102.7)
35.1
(95.2)
33.3
(91.9)
33.9
(93)
32.9
(91.2)
28.3
(82.9)
23.0
(73.4)
31.4
(88.5)
Average low °C (°F) 7.3
(45.1)
10.1
(50.2)
15.4
(59.7)
21.5
(70.7)
25.9
(78.6)
28.3
(82.9)
26.6
(79.9)
25.9
(78.6)
24.4
(75.9)
19.5
(67.1)
12.8
(55)
8.2
(46.8)
18.8
(65.8)
Average rainfall mm (inches) 20.3
(0.799)
15.0
(0.591)
15.8
(0.622)
6.7
(0.264)
17.5
(0.689)
54.9
(2.161)
231.5
(9.114)
258.7
(10.185)
127.8
(5.031)
36.3
(1.429)
5.0
(0.197)
7.8
(0.307)
797.3
(31.389)
Average rainy days 1.7 1.3 1.2 0.9 1.4 3.6 10.0 11.3 5.4 1.6 0.1 0.6 39.1
Mean monthly sunshine
hours 213.9 217.5 238.7 261.0 263.5 198.0 167.4 176.7 219.0 269.7 246.0 217.0 2,688.4
Modification and Expansion of Group Housing Project “Atharva Group Housing” at
Sec-109, Village PawalaKhusrupur, Haryana
EIA-EMP REPORT
M/s Raheja Developers Ltd. Page | 51
3.5.2 WIND PATTERN
Analysis of wind records during 2016-2018 shows that the winds are generally light to moderate in
this area. Wind speed data is given in Table 3.3 below. It can be seen that the annual average wind
speed varies from 7.9 to 24.8 km/h. The strongest winds are observed during June i.e. Summer
Season and the weakest during November. Wind Rose Diagram for Gurugramis given below in
Figure 3.3.
Table3.3: Monthly Mean Wind Speed (KMPH)
2016 2017 2018
Month MAX AVG MAX AVG MAX AVG
Jan 12.2 8.3 13.0 9.4 12.2 8.6
Feb 15.8 10.8 16.2 11.2 13.0 8.6
March 18.4 11.9 18.4 11.9 14.8 9.4
April 22.0 14.8 20.5 13.7 18.0 10.8
May 22.0 13.7 15.5 9.4 16.6 10.4
June 19.8 12.6 18.0 10.8 19.8 13.7
July 17.3 11.2 18.0 13.31 15.8 10.1
Aug 17.3 12.2 17.6 13.0 14.0 9.7
Sep 15.1 11.2 14.0 9.4 16.2 10.8
Oct 14.8 9.7 10.8 6.5 11.2 6.8
Nov 14.0 9.7 10.1 7.6 11.2 7.2
Dec 13.0 9.4 11.2 7.9 -- --
Source: www.worldweatheronline.com
Modification and Expansion of Group Housing Project “Atharva Group Housing” at
Sec-109, Village PawalaKhusrupur, Haryana
EIA-EMP REPORT
M/s Raheja Developers Ltd. Page | 52
Source:www.metoblue.com
Figure 3.3: Wind Rose Diagram Gurugram, Haryana
3.5.3 RAINFALL & HUMIDITY
The normal annual rainfall in Gurugram district is about 596 mm spread over 28 days and normal
monsoon rainfall is 508 mm1. The south west monsoon sets in the last week of June and withdraws
towards the end of September and contributes about 85% of the annual rainfall. July and August
are the wettest months. 15% of the annual rainfall occurs during the non-monsoon months in the
wake of thunder storms and western disturbances.
3.5.4 MICRO-METEOROLOGY AT SITE
As per collected data, micro-meteorology for the site for month of January, 2018is given below in
Table 3.4.
1CGWB
Modification and Expansion of Group Housing Project “Atharva Group Housing” at
Sec-109, Village PawalaKhusrupur, Haryana
EIA-EMP REPORT
M/s Raheja Developers Ltd. Page | 53
Table 3.4: Micro-Meteorology of Study Area During January, 2018
Month Temperature 0C humidity, % Rainfall in (mm) Wind Speed,
Km/hr.
Min
Ma
x
Av
g.
Ra
iny
da
ys
To
tal
Ra
infa
ll
mm
.
Ma
x
Av
g.
Jan 2018 15 24 20 36 1 11.9 12.2 8.6
3.6 LAND ENVIRONMENT
3.6.1 TOPOGRAPHY AND TERRAIN
Theterrainofthestudy areaisgenerallyplainwithanaverage elevationranges from 210 to 255
metersabovemeansea level(MSL) and at project site the average elevation ranges from 215-216 m
amsl with the level difference of 1 m.Contour map of the 10 km study area are given below in Figure
3.4.
Modification and Expansion of Group Housing Project “Atharva Group Housing” at Sec-109, Village PawalaKhusrupur, Haryana
EIA-EMP REPORT
M/s Raheja Developers Ltd. Page | 54
Figure 3.4: Contour Map of10 km Radius Study Area
Modification and Expansion of Group Housing Project “Atharva Group Housing” at
Sec-109, Village PawalaKhusrupur, Haryana
EIA-EMP REPORT
M/s Raheja Developers Ltd. Page | 55
3.6.2 LAND USE
The landuse / landcover of the project site isstudied to identify the existing landuseand landcover
pattern of the study area. The study of land use in the area enables one to know about the land that can
be used for various development activities envisaged in post project scenario. It also enables to
envisage the scenario emerging due to the increase in demand for land with increase in population and
the impacts arising due to the interface with the various project activities. Objectives of the land use
study are given below:
To map the study area with respect to various land use/land cover change over the past 10
years.
To identify the sensitive areas within 10 km radius around the project site
The settlement area near to the project site covers mainly the institutes, hospitals, residential
areas, worship places like PawalaKhasrupur, Mohammad Heri Village, Sec-110 Gurugram,
Babupur village etc.
The project site surrounded by residential colonies and villages majorly.
Methodology: The landuse/landcover pattern has been established based on the analysis of the data
received from satellite imagery by making landuse/landcover map with the help of GIS technique.
Also the data based on Census of India, 2011 was referred and landuse study was done within 10 km
radius area with limited ground truth verifications. Ground and ancillary information have been used
to identify the sensitive places within 10 km radius of the project.
Land Use Pattern Classification and description
As per the land use land cover study of 10 km radius area of the project site, it is found that 41.2%
area is covered under agricultural area. Settlement area comprises about 35.9% of land area.No
notified eco-sensitive zones are identified within 10 km radius of the project site. Land use breakup of
the study area is given in Table 3.5 and graphical representation of land use breakup of the study area
is given in Figure 3.5.The land use /land cover map of the study area within 10 km radius around the
project site is presented in Figure 3.6.
Table 3.5: Land Use Classification of Study Area
Class Area
(sq km)
Area Percent
(%)
Agricultural land 131.86 41.2
Settlement 114.87 35.9
Water body 6.16 1.9
Vegetation 44.70 14.0
Open shrub land 22.51 7.0
Total 320.1 100
Modification and Expansion of Group Housing Project “Atharva Group Housing” at
Sec-109, Village PawalaKhusrupur, Haryana
EIA-EMP REPORT
M/s Raheja Developers Ltd. Page | 56
41%
36%
2%14%
7%
Land Use Breakup
Agricultural land Settlement Water body
Vegetation Open shrub land
Figure 3.5: Graphical Representation of Land Use Break up of Study Area
Modification and Expansion of Group Housing Project “Atharva Group Housing” at Sec-109, Village PawalaKhusrupur, Haryana
EIA-EMP REPORT
M/s Raheja Developers Ltd. Page | 57
Figure3.6: LULC Map of the study area (10 km radius)
Modification and Expansion of Group Housing Project “Atharva Group Housing” at
Sec-109, Village PawalaKhusrupur, Haryana
EIA-EMP REPORT
M/s Raheja Developers Ltd. Page | 58
3.6.3 NATURAL DISASTERS
Seismicity
As per the 2014 Bureau of Indian Standards (BIS) map, Gurugram falls in Zones IV. The project site
lies in seismic zone IV which is high damage riskzone. Seismic zone map of India is given in
Figure 3.7 below. Structural design of the building should follow the NBC specification for zone
IV.
Flood Hazard
Site is not in a flood prone area. No major water body is present within 10 km radius of the project
site. Run-off from the site is increased due to development of paved surfaces which might leads to
local flooding for which Storm water drainage system is provided at project site for channelizing
storm water.
Figure 3.7: Seismic & Hazard Zoning map of India
3.6.4 GEOMORPHOLOGY
The area is conspicuously flat topography, however, in the north-eastern part small isolated hillocks
of Precambrian rocks are exposed. The alluvial plain is formed by the Sahibi river which is tributary
of River Yamuna. Soils of the Gurugram district are classified as tropical and brown soils, existing
Modification and Expansion of Group Housing Project “Atharva Group Housing” at
Sec-109, Village PawalaKhusrupur, Haryana
EIA-EMP REPORT
M/s Raheja Developers Ltd. Page | 59
in the north western extreme, northern and north eastern parts of the district and water logged and
salt affected soils in the southern parts of the district. The soils are medium textured loamy sand is
the average texture in Gurugram and Sohna blocks. In Pataudi and Sohna blocks the organic content
of soils is lowest, just up to 0.20 per cent (very low category). In the rest of the district, organic
contents is 0.2 to 0.40 percent and falls in low category.
3.6.5 SOIL
The district is covered by yellowish brown soil. The district has light soils as sandy loam, medium
soil particularly light loam (Seoti) and loam (Bhangar and Nardak), coarse loam (Dahar and
choeknote) and rocky surfaces. Soils as classified by the National Bureau of Soil Survey and Land
Use Planning (ICAR), Nagpur, the district has Ochreptps type of soils in its major parts while
Orthids-Fluvents and Ochrepts-Ustrets-Ustalfs types of soils are found in central western and south
western parts of the district respectively. Soil quality study has been carried out at the site and in the
study area of 10 km radius around the project site during Jan, 2018, to understand the physio-
chemical nature of the soil. Soil testing is carried out at 5 locations including project site. List of Soil
quality monitoring stations is given in Table 3.6 below.
Table3.6: Soil Quality Testing Stations
Code Sample Collection Points Coordinates Distance Direction
Latitude Longitude
S1 Project Site 28.509014° 77.007640° -- --
S2 PawalaKhushrupur 28.503856° 77.013139° 700 m SE
S3 Babupur 28.509719° 76.996453° 700 m W
S4 Sector-110, Gurugram 28.507926° 77.015582° 700 m E
S5 Sector-105, Gurugram 28.494693° 77.010669° 1.3 km SE
Detailed soil quality analysis of the project site and study area is given in Table 3.7below.
Table 3.7: Soil Quality Analysis Report
S. No. Parameters Unit Project
Site
(S-1)
PanwalaKh
ushrupur
(S-2)
Babupu
r
S-3)
Sector-110,
Gurugram
(S-4)
Sector-105,
Gurugram
(S-5)
Physical Characteristics
1. Colour - Yellowish
Brown
Yellowish
Brown
Yellowis
h Brown
Yellowish
Brown
Yellowish
Brown
2. Texture USDA Sandy Loam
Sandy Loam Sandy Loam
Sandy Loam
Sandy Loam
3. Particle Size Distribution
i). Sand % 58 62 56 58 54
ii). Silt % 28 22 26 26 30
iii). Clay % 14 16 18 16 16
4. Porosity % 44.9 47.9 42.6 45.7 44.2
5. Bulk Density gm/cc 1.46 1.36 1.52 1.44 1.48
6. Water Holding Capacity
% 29.6 28.8 30.1 29.2 30.5
7. Permeability cm/hr 1.55 1.18 0.94 1.20 1.22
Chemical Characteristics
Modification and Expansion of Group Housing Project “Atharva Group Housing” at
Sec-109, Village PawalaKhusrupur, Haryana
EIA-EMP REPORT
M/s Raheja Developers Ltd. Page | 60
8. pH 1:2
Slurry
7.85 7.66 7.58 7.74 7.78
9. Conductivity
(EC)
µmhos/c
m
265.4 228.5 215.8 244.6 235.2
10. CEC meq/100
gm
10.8 11.6 9.8 11.4 10.5
11. Organic Carbon % 0.45 0.42 0.39 0.37 0.44
12. Organic Matter % 0.78 0.72 0.67 0.64 0.76
13. Chloride as Cl mg/kg 110.5 106.2 104.8 98.4 112.8
14. Calcium as Ca mg/kg 72.6 59.5 62.8 78.2 71.4
15. Magnesium as
Mg
mg/kg 17.6 18.5 14.4 16.5 15.2
16. Iron as Fe mg/kg 0.65 0.62 0.56 0.68 0.57
17. Available Nutrients
i). Nitrogen as N Kg/ha 276.5 285.8 288.6 282.4 276.8
ii). Phosphorous as P Kg/ha 15.8 14.5 16.4 18.4 17.6
iii). Potassium as K Kg/ha 124.5 165.2 142.8 126.4 171.6
Source: Testing carried out by JP Lab, Sahibabad, Ghaziabad
3.6.5.1 OBSERVATIONS
The soil is in slightly alkaline to moderately alkaline range. The concentration of various parameters
indicates moderate productivity levels. In the study area, variations in the pH of the soil were found
to be 7.58 to 7.85. Conductivity ranges from 215.8 to 265.4µmhos/cm. The bulk density of the soils
was found in the range of 1.36 to 1.52gm/cm3.Water Holding Capacity of soil in the study area was
observed as 28.8 to 30.5%. The organic carbon content of soil varied from 0.37 to 0.45% (0.64 to
0.78% as organic matter), thereby implying that soils are low in organic carbon and organic matter
content. Available nitrogen content in the surface soils ranges between 276.5&288.6kg/ha thereby
indicates that soils are with low to medium level of available nitrogen content. Available phosphorus
content ranged between 14.5 & 18.4 kg/ha thereby indicating that soils are with medium levelof
available phosphorus content. Available potassium content in these soils ranges between 124.5
to171.6 kg/ha thereby is indicating that the soils are with medium levels of available potassium
content. Thus the soil of the study area are moderate fertile. Soil quality analysis report is attached
as Annexure XVI a.
3.7 WATER ENVIRONMENT
3.7.1 DRAINAGE
The 10 km study area has the no major water body present. Map showing drainage pattern of study
area is given in Figure 3.8below.
Modification and Expansion of Group Housing Project “Atharva Group Housing” at Sec-109, Village PawalaKhusrupur, Haryana
EIA-EMP REPORT
M/s Raheja Developers Ltd. Page | 61
Figure 3.8: Drainage pattern of the study area
Modification and Expansion of Group Housing Project “Atharva Group Housing” at
Sec-109, Village PawalaKhusrupur, Haryana
EIA-EMP REPORT
M/s Raheja Developers Ltd. Page | 62
3.7.2 HYDRO-GEOLOGY
General:
The Gurugram district is occupied by Quaternary alluvium and Pre-Cambrian meta- sediments of
Delhi Super Group. The alluvium comprises of thick beds of fine to coarse-grained sand with
alternating layers of thin clays. The generalized geological formation met within the area and their
water bearing characteristics are given below in Table 3.8.
Table 3.8: Generalized Geological Succession, Gurugram District
Geological Age Stratigraphic Units Lithological characters
Recent Wind-blown sand Medium to fine grained sand
buff coloured over the
alluvium
Pleistocene Newer alluvium Stream laid sand , silt, clay
and gravel
Older alluvium Semi-consolidated, poorly
sorted fine to medium grained sand, silt and caly
occasionally mixed with
kankar
UNCONFORMITY
Delhi Ajabgarh Slates,Phyllites, Quartzites.
Mica-schists, with intrusive
pagmatites
Alwar Quartzites,mica-schists with intrusive pagmatites
UNCONFORMITY
Archeans Aravalli Mica-schists, crystalline
limestone, Quartzites and schistose conglomerates
Aquifer System:
The major part of Gurugram district is underlain by Quaternary alluvium consisting of sand, clay
and silt. The quartzite ridge trending NNE-SSW is located about 7 km east of town in which ground
water occurs in fractures, joints and crevaces. Sandy layers at various depth form major water
bearing horizons above the crystalline basement.Ground water in the Gurugram block occurs in
unconfined and semiconfined condition.The upper zone of saturation consists of fine sand with silt
varying from place to place.In Udyog vihar and city area the depth of first aquifer varies from 34 to
43 mbgl.However in industrial area of Manesar top most aquifer can be encountered at 20m . The
thickness of sandy layer is very limited.The drawdown are generally high indicating absence of
highly potential ground water bearing aquifers. Tube-wells in the depth range of 45 to 90 m bgl have
been installed by different agencies in the block. The yield of these tube-wells varies in different
areas ranging within 129 to 606 lpm.
Modification and Expansion of Group Housing Project “Atharva Group Housing” at
Sec-109, Village PawalaKhusrupur, Haryana
EIA-EMP REPORT
M/s Raheja Developers Ltd. Page | 63
Depth to water level data is in the range of 3.3 – 79.70mbglduring pre-monsoon. Depth of
water level Pre monsoonis shown in Figure 3.9.
Depth to water level is in the range of 3.05 – 77.5 mbgl during post-monsoon. Depth of water
level Post Monsoon is shown in Figure 3.10.
Figure 3.9: Depth ofWater level During Pre-Monsoon in Gurugram District
Modification and Expansion of Group Housing Project “Atharva Group Housing” at
Sec-109, Village PawalaKhusrupur, Haryana
EIA-EMP REPORT
M/s Raheja Developers Ltd. Page | 64
Figure 3.10: Depth of Water level During Pre-Monsoon in Gurugram District
3.7.3 GROUND WATER AND SURFACE WATER QUALITY
Ground water qualityanalysis was carried out in the study area at 4locations including project site.
Surface water quality analysis was carried out at 1 locationin the study area at Najafgarh Drain.
Samples were taken during January, 2018. Details of ground water and surface water monitoring
stations are given in Table 3.10 below. Grab samples were collected for testing. Samples were
marked after collection and were then tested in NABL accredited laboratory. Ground water and
surface water quality analysis data for the project site and other locations in study area is presented
in Table 3.9& Table 3.10, respectively, below.
Modification and Expansion of Group Housing Project “Atharva Group Housing” at
Sec-109, Village PawalaKhusrupur, Haryana
EIA-EMP REPORT
M/s Raheja Developers Ltd. Page | 65
Table 3.9: Ground Water Monitoring Stations
Location Code Sampling Locations Coordinates Distance Direction
Latitude Longitude
GW1 Project Site -- -- --
GW2 Babarpur village 28.509719° 76.996453° 700 m W
GW3 New Palam Vihar, Phase-II 28.515058° 77.015448° 900 NE
GW4 Sector-110, Gurugram 28.507926° 77.015582° 700 m E
SW1 Najafgarh Drain -- -- --
Table 3.10: Ground Water Quality Analysis (Jan, 2018)
S.
No
.
Parameters Unit
Proje
ct Site
(GW1
)
Babar
pur
villag
e
(GW2
)
New
Palam
Vihar,
Phase-
II
(GW3)
Sector-
110,
Gurugra
m
(GW4)
Max Requirement as
per
(IS-10500-2012) Limit
Desirab
le Permissible
1 pH value - 8.26 7.21 7.69 7.78 6.5-8.5 No
Relaxation
2 Temperature 0C 24.2 24.5 24.4 24.6 - -
3 Conductivity mhos/c
m 2315 6250 5965 2410 - -
4 Turbidity NTU <1 <1 <1 <1 1 5
5 Total Dissolved Solids mg/l 1658 3896 4078 1478 500 2000
6 Total Suspended solids mg/l <2 <2 <2 <2 - -
7 Total Hardness (as CaCO3) mg/l 514 2010 1628 510 200 600
8 Chlorides (as Cl) mg/l 563 1529 1702 486 250 1000
9 Total Alkalinity as CaCO3 mg/l 396 438 615 362 200 600
10 Sulphate (as SO4) mg/l 72 184 72 49 200 400
11 Nitrate(as NO3) mg/l 6.9 8.6 8.5 5.6 45 No
Relaxation
12 Fluoride (as F ) mg/l 0.6 0.74 0.7 0.4 1 1.5
13 Iron (as Fe) mg/l 0.3 0.26 0.42 0.32 0.3 No
Relaxation
14 Zinc (as Zn) mg/l 0.64 0.83 0.58 0.58 5 15
15 Calcium (as Ca) mg/l 102 593 386 165 75 200
16 Magnesium (as Mg2+) mg/l 63 129 161.6 23.9 30 100
17 Sodium (as Na) mg/l 318 362 635 186 - -
18 Potassium (as K) mg/l 29 34 57 19 - -
19 Cadmium (as Cd) mg/l <0.01 <0.01 <0.01 <0.01 0.003 No
Relaxation
20 Copper (as Cu) mg/l <0.01 <0.01 <0.01 <0.01 0.05 1.5
21 Nickel (as Ni) mg/l <0.01 <0.01 <0.01 <0.01 0.02 No
Relaxation
22 Lead (as Pb) mg/l <0.01 <0.01 <0.01 <0.01 0.01 No
Relaxation
23 Mercury (as Hg) mg/l <0.00
1
<0.00
1 <0.001 <0.001 0.001
No
Relaxation
24 Total Chromium (as Cr) mg/l <0.05 <0.05 <0.05 <0.05 0.05 No
Relaxation
25 Total arsenic (as As) mg/l <0.01 <0.01 <0.01 <0.01 0.01 0.05
26 Phenolic Compounds (as mg/l <0.00 <0.00 <0.001 <0.001 0.001 0.002
Modification and Expansion of Group Housing Project “Atharva Group Housing” at
Sec-109, Village PawalaKhusrupur, Haryana
EIA-EMP REPORT
M/s Raheja Developers Ltd. Page | 66
Source: JP Lab, Sahibabad, Ghaziabad
3.7.3.1 OBSERVATION ON GROUND WATER QUALITY
The pH value of drinking water is an important index of acidity or alkalinity. pH value of the sample
is well within the specified standard of 6.5 to 8.5. The pH of the ground water in the study area is
slightly alkaline in nature. The parameters like hardness, TDS, chloride, Alkalinity etc, were found
on higher side in all water sample. However the ground water quality of project site and sector 110
is well within the permissible limit IS: 10500-2012 and rest other two samples were not meeting the
desired as well as permissible limit of Indian Standard IS: 10500-2012. Ground water quality
analysis report is attached as Annexure XVI b.
Table 3.11: Surface Water Quality Analysis (Jan, 2018)
Source: JP Lab, Sahibabad, Ghaziabad
3.7.3.2 OBSERVATION ON SURFACE WATER QUALITY
Quality of water of the drain is very poor. Water contains high BOD, COD and colioform content
and the quality does not matches to any of the class defined under BDU Criteria of CPCB (2008).
Surface water quality analysis report is attached as Annexure XVI c.
C6H5OH) 1 1
27 Total Coliform MPN/100ml
Not
detect
ed <2
Not
detect
ed <2
Not
detected
<2
Not
detected
<2
Shall not be detectable
S.N
o Parameters Unit Najafgarh Drain
1 pH value - 7.8
2 Temperature 0C 22.4
3 Conductivity mhos/cm 1846
4 Turbidity NTU 32
5 Total Dissolved Solids mg/l 1186
6 Total Suspended solids mg/l 188
7 Total Hardness (as CaCO3) mg/l 532
8 Chlorides (as Cl) mg/l 362
9 Total Alkalinity as CaCO3 mg/l 214
10 Nitrate(as NO3) mg/l 7.6
11 Calcium (as Ca) mg/l 144
12 Magnesium (as Mg2+) mg/l 42
13 Oil & Grease mg/l 14
14 Chemical Oxygen Demand mg/l 280
15 Bio- Chemical Oxygen Demand
as BOD (for 3 Days 27 ˚C) mg/l 76
16 Dissolved Oxygen mg/l 4.2
17 Total Coliform MPN/100ml 26 x 103
Modification and Expansion of Group Housing Project “Atharva Group Housing” at
Sec-109, Village PawalaKhusrupur, Haryana
EIA-EMP REPORT
M/s Raheja Developers Ltd. Page | 67
3.8 AIR ENVIRONMENT
Ambient air quality study for the study area was carried out for the study period, Jan, 2018. Ambient
air quality studies have been carried out at 5 locations and are listed in Table 3.12 below. Ambient
air quality analysis data for the monitoring locations is given in Table 3.13& Table 3.14below.
Results are graphically presented and are given in Figure 3.11 below.
Table 3.12: Locations of Ambient Air Quality Monitoring
S.
No.
Location Location
Code
Coordinates Distance Direction
Latitude Longitude
1. Project Site AAQ1 28.509014°N 77.007640°E -- --
2. Babupur village AAQ2 28.509719°N 76.996453°E 1.5 km N
3. Sec-110,
Gurugram
AAQ3 28.507926°N 77.015582°E 2.0 km NE
4. Village
PawalaKhasrupur
AAQ4 28.503856°N 77.013139°E 0.96 km SW
5. Sec-105,
Gurugram
AAQ5 28.494693°N 77.010669°E 1.36 km S
Table: 3.13: Ambient Air Quality Test Results (Jan, 2018)
Location PM10 (µg/m³) PM2.5 (µg/m³)
Min Max Mean 98 Percentile Min Max Mean 98 Percentile
AAQ1 122 316 212 316 94 218 145 215
AAQ2 120 256 185 255 86 168 120 165
AAQ3 112 244 185 244 78 160 123 159
AAQ4 108 232 161 228 75 152 113 150
AAQ5 105 258 188 256 82 178 132 177
Source: JP Lab, Sahibabad, Ghaziabad
Table: 3.14: Ambient Air Quality Test Results (Jan, 2018)
Location
SO₂ (µg/m³) NO₂ (µg/m³) CO(mg/
m³)
Min Max Mean 98
Percentile Min Max Mean
98
Percentile Mean
AAQ1 5.3 8.6 7.2 8.6 14.2 20.6 16.6 20.6 0.84
AAQ2 5.8 8.4 7.1 8.4 12.2 18.6 15.6 18.6 0.85
AAQ3 6.1 8.6 7.4 8.6 11 18.2 14.7 18.1 0.84
AAQ4 3.4 9.3 7.7 9.1 12.7 9.2 15.4 19 0.85
AAQ5 6.5 9.4 7.7 9.3 14.4 21.5 17.8 21.4 0.85
Source: JP Lab, Sahibabad, Ghaziabad
3.8.1 OBSERVATIONS OF AMBIENT AIR QUALITY MONITORING
The maximum PM10 level of 316 µg/m3 was observed at project site. The mean value of PM10 level
at various monitoring stations ranged from 161 to 212 µg/m3. The PM10 values at monitoring
stations were found higher than the permissible limit of 100 µg/m3 specified in NAAQS, 2009 at all
locations.
Modification and Expansion of Group Housing Project “Atharva Group Housing” at
Sec-109, Village PawalaKhusrupur, Haryana
EIA-EMP REPORT
M/s Raheja Developers Ltd. Page | 68
The maximum PM2.5 level of 218µg/m3 was observed at Project Site. The mean value of PM2.5 level
at various monitoring stations ranged from 113 to145µg/m3. The PM2.5 values at the monitoring
stations were found higher than the permissible limit of 60 µg/m3 specified in NAAQS, 2009 at all
locations.
The mean value of SO2 levels was observed at various stations in the study area ranges from 7.1 to
7.7µg/m3. The values of SO2 monitored during the field survey were well within the permissible
limit of 80 g/m3 specified in NAAQS, 2009
The mean value of NO2 levels was observed at various stations in the study area ranges from 14.7 to
17.8 µg/m3. The NO2 levels monitored during the field survey were well within the permissible limit
of 80 g/m3as specified in NAAQS, 2009.
The mean value of CO levels was observed at various stations in the study area ranges from 0.84
µg/m3to 0.85µg/m3. The CO levels monitored during the field survey were well within the
permissible limit of 4 mg/m3 (For 1 Hr.) as specified in NAAQS, 2009. Ambient air quality analysis
report is attached as Annexure XVI d.
Modification and Expansion of Group Housing Project “Atharva Group Housing” at Sec-109, Village PawalaKhusrupur, Haryana
EIA-EMP REPORT
M/s Raheja Developers Ltd. Page | 69
0
50
100
150
200
250
300
350
AAQ1 AAQ2 AAQ3 AAQ4 AAQ5
Conc
entr
atio
n (µ
g/m
³))
Ambient Air Quality Monitoring Station
PM10 (µg/m³) Min
PM10 (µg/m³) Max
PM10 (µg/m³) Mean
PM10 (µg/m³) 98 Percentile
PM10 (µg/m³) CPCB Std.
0
50
100
150
200
250
AAQ1 AAQ2 AAQ3 AAQ4 AAQ5
Co
nce
ntr
atio
n (
µg/
m³)
)
Ambient Air Quality Monitoring Station
PM2.5 (µg/m³) Min
PM2.5 (µg/m³) Max
PM2.5 (µg/m³) Mean
PM2.5 (µg/m³) 98 Percentile
PM2.5 (µg/m³) CPCB Std.
Figure 3.11: Graphical Presentation of Ambient Air Quality Monitoring Analysis
0
10
20
30
40
50
60
70
80
90
AAQ1 AAQ2 AAQ3 AAQ4 AAQ5
Conc
entr
atio
n (µ
g/m
³))
Ambient Air Quality Monitoring Station
SO₂ (µg/m³) Min
SO₂ (µg/m³) Max
SO₂ (µg/m³) Mean
SO₂ (µg/m³) 98 Percentile
SO₂ (µg/m³) CPCB Std.0
10
20
30
40
50
60
70
80
90
AAQ1 AAQ2 AAQ3 AAQ4 AAQ5
Conc
entr
atio
n (µ
g/m
³))
Ambient Air Quality Monitoring Station
NO₂ (µg/m³) Min
NO₂ (µg/m³) Max
NO₂ (µg/m³) Mean
NO₂ (µg/m³) 98 Percentile
NO₂ (µg/m³) CPCB Std.
Modification and Expansion of Group Housing Project “Atharva Group Housing”
at Sec-109, Village PawalaKhusrupur, Gurugram, Haryana
EIA/EMP Report
M/s Raheja Developers Ltd. Page | 70
3.9 NOISE ENVIRONMENT
Noise attributed to roads depends on factors such as traffic intensity, the type and condition of
the vehicles plying on the road, acceleration/deceleration/gear changes by the vehicles
depending on the level of congestion and smoothness of road surface (IRC: 104-1988). High
noise levels are a concern for sensitive receptors, i.e., hospitals, educational institutions, etc.
The Central Pollution Control Board has specified ambient noise levels for different land uses
for day and night times and are given in Table 3.15. Importance was given to the timing of
exposure and areas designated as sensitive.
Table: 3.15: National Ambient Noise Level Standards
Area Code Category Limits in Decibels dB (A)
Day Time Night Time
A Industrial 75 70
B Commercial 65 55
C Residential 55 45
D Silence 50 40
Source: Central Pollution Control Board, New Delhi
Note: Daytime: 6 AM to 10 P.M., Night-time: 10 PM to 6 AM;
Noise monitoring study is carried out at 5 locations within study area including project site. All
land use are considered while preparation of monitoring plan. List of the Noise level monitoring
stations is given below in Table 3.16.
Table 3.16: List of Noise Level Monitoring Stations
S.
No.
Location Location
Code
Coordinates Distance Direction
Latitude Longitude
1. Project Site N-1 28.509014° 77.007640° -- --
2. Babupur village N-2 28.509719° 76.996453° 1.5 km N
3. Sec-110, Gurugram N-3 28.507926° 77.015582° 2.0 km NE
4. Village PawalaKhasrupur N-4 28.503856° 77.013139° 0.96 km SW
5. Sec-105, Gurugram N-5 28.494693° 77.010669° 1.36 km S
Noise level monitoring study was carried out during Jan, 2018. Results of noise level monitoring
study are presented in Table 3.17below.
Table 3.17: Noise Level Monitoring results (Jan, 2018)
S. No. Location
Noise Levels in dB(A)
LeqDay
Time
Standard
dB(A) Leq
LeqNight
Time
Standard
dB(A)
Leq
1. Project Site (N-1) 54.6 55 43.2 45
2. Babupur village (N-2) 53.5 55 42.0 45
3. Sec-110, Gurugram (N-3) 53.0 55 43.0 45
4. Village PawalaKhasrupur (N-4) 52.8 55 42.7 45
5. Sec-105, Gurugram (N-5) 54.4 55 42.9 45
Source: EQMS
Modification and Expansion of Group Housing Project “Atharva Group Housing”
at Sec-109, Village PawalaKhusrupur, Gurugram, Haryana
EIA/EMP Report
M/s Raheja Developers Ltd. Page | 71
The daytime equivalent noise level ranges from 52.8 to 54.6 dB (A). Likewise, night-time
equivalent noise level ranges from 42.7 to 43.2 dB (A) at various sampling stations. The day
time and night time equivalent noise levels werewithin the standard limit specified for
residential area.
3.10 TRAFFIC DENSITY
Project site abuts the proposed master plan road and Dwarka express way (Northern Peripheral
Road/NH 248-BB) is at approx. 640 m from the site in South direction. It is 27.6 km long, 8
lane-controlled access highway connecting Dwarka in Delhi to Gurugram in Haryana. This
expressway is not completely constructed till date and many of its stretches are under-
construction. Thus, traffic survey is considered for the SH-15A which is crosses this Dwarka
Expressway near Sector 102 of Gurugram. SH-15 A is 43.03 km long highway which connects
Jhajjar, Faraqnagar and Gurgaon. Annual Average Daily Traffic on SH-15 A is 16786 PCU.
Traffic data on SH-15 A is given below in Table 3.18. Traffic volume at SH-15A is 25984 PCU
and carrying capacity of SH is 30000 PCU. V/C ratio of the state highway is 0.87 and level of
service is D. At present SH-15 is 2 lanes. There will be requirement of expansion of this
highway to 4 lanes by 2021. At present this highway is sufficient to carry the load.
Table 3.18: Traffic Survey of SH-15A
Traffic Count (PCU), 2009
Car Bus Truck 2W Cycle ADV Other Total
3900 121 5186 1182 272 399 3818 14878
Traffic Count (PCU), 2014
5600 570 7483 1860 331 486 4873 21202
Traffic Volume (PCU), 2018
7800 210 9100 2304 350 520 5700 25984
Projected Traffic Count (PCU), 2021
8700 1410 11151 3511 435 639 6856 32703
Growth Rates
10.15 9.23 7.66 9.5 4 4 5 -- Source: Preparation of Sub-Regional Plan for Haryana Sub Region of NCR-2021: Interim Report-II
3.11 BIOLOGICAL ENVIRONMENT
The ecological survey has been done to establish the baseline ecological conditions of the study
area (with in project area and 10 Km radius around the project site). To assess the potential
ecological impacts of the proposed project upon ecology and to develop adequate and feasible
mitigation measures (via inputs to project design and layout, working practices). This section of
report presents ecological baseline of the area and study was carried out in two separate
headings for floral and faunal community respectively. Biological study is carried out for core
zone and buffer zone.
Modification and Expansion of Group Housing Project “Atharva Group Housing”
at Sec-109, Village PawalaKhusrupur, Gurugram, Haryana
EIA/EMP Report
M/s Raheja Developers Ltd. Page | 72
3.11.1 FLORA &FAUNA IN CORE ZONE
The project site doesnot support any significant vegetation except the green area developed at
the site. Also due to location in the urban stretch (residential colonies and villages mainly) no
threatened, rare, endangered or endemic species were observed at the site during the visit.
3.11.2 FLORA & FAUNA IN BUFFER ZONE
Study area is majorly settlement area followed by residential colonies and villages mainly.
Vegetation is mainly in the form of parks and green belt maintained along the drains. Flora and
fauna of the study area is given in Table 3.19& Table 3.20
Table 3.19: Flora of Study Area
S. No. Local Names Botanical Names
1. Neem Azadirachtaindica
2. Safeda Eucalyptus
3. Dhatura Datura sp.
4. Arandi Ricinus communis
5. Peepal Ficusreligiosa
6. Bougainvelia Bougainvelli
7. Bottle palm Beaucarnearecurvata
8. Amaltas Cassia fistula
9. Shisham Dalbergia sissoo
10. Bottle brush Callistemon lanceolatus
11. Carrot grass Parthenium sp.
12. Gulmohar Delonix regia
13. Oak Quercus sp
14. Japanese maples Acer palmatum
15. Trident maples Acer buergerianum
Source: Primary survey
Table 3.20: Fauna of Study Area
S. No. Local Names Zoological Names
Amphibians
1. Toad Bufo sp.
2. Frog Ranatigrina
Reptiles
3. Indian garden lizards Calotesversicolor
4. House lizards Hemidactylus sp.
Mammals
5. Indian palm squirrel Fumambuluspennanti
6. Cat Felis sp.
7. Dog Cuon sp.
8. Cow Bos sp.
9. Horse Equs sp.
10. Rat Rattusrattus
Aves
11. Crow Corves splendens
12. Sparrow Passer domesticus
Modification and Expansion of Group Housing Project “Atharva Group Housing”
at Sec-109, Village PawalaKhusrupur, Gurugram, Haryana
EIA/EMP Report
M/s Raheja Developers Ltd. Page | 73
13. Baya Ploceusphilippinus
14. Parrot Psittaculakrameri
15. Peafowl Pavocristatus
16. Pigeon Columba livia
17. Egretta Egretta sp.
18. Myna Acridotherestristis
Source: Primary survey
3.12 SOCIOECONOMIC ENVIRONMENT
3.12.1 DEMOGRAPHICS OF GURUGRAM DISTRICT
Project site is located in Gurugram. Gurugram District is located in the State of Haryana, India
and has area of app. 1258sq km. As per Census, 2011,Gurugramhas population of 1,514,432 of
which male and female were 816,690 and 697,742, respectively. There is change of 73.96
percent in the population compared to population in 2001. Average literacy rate of Gurugram in
2011 was84.70 compared to 78.5 % in 2001. Sex Ratio in Gurugram District is854in 2011 and
was 850 in 2001. GurugramDistrict population constituted 5.97 percent of total Haryana
population in 2011. Demographic profile of Gurugram District is given below in Table
3.21.Project site is located in Gurugram city.
Table 3.21: Demographic Profile of Gurugram
Description Year 2011
Actual Population 1,514,432
Male 816,690
Female 697,742
Population Growth 73.96%
Area Sq. Km 1,258
Density/km2 1,204
Proportion to Uttar Pradesh Population 5.97%
Sex Ratio (Per 1000) 854
Child Sex Ratio (0-6 Age) 830
Average Literacy 84.70
Male Literacy 90.46
Female Literacy 77.98
Total Child Population (0-6 Age) 202,602
Male Population (0-6 Age) 110,705
Female Population (0-6 Age) 91,897
Literates 1,111,116
Male Literates 638,666
Female Literates 472,450
Child Proportion (0-6 Age) 13.38%
Boys Proportion (0-6 Age) 13.56%
Girls Proportion (0-6 Age) 13.17%
Modification and Expansion of Group Housing Project “Atharva Group Housing”
at Sec-109, Village PawalaKhusrupur, Gurugram, Haryana
EIA/EMP Report
M/s Raheja Developers Ltd. Page | 74
Source: Census 2011
Project area is well developed area and is equipped with all infrastructure facilities and
amenities like roads, electricity, water supply, sewerage and drainage. All other facilities like
post-office, communication, banks and ATMs are available in the project area.
Modification and Expansion of Group Housing Project “Atharva Group Housing”
at Sec-109, Village PawalaKhusrupur, Gurugram, Haryana
EIA/EMP Report
M/s Raheja Developers Ltd. Page | 75
CHAPTER 4 :IMPACT IDENTIFICATION AND ASSESSMENT
4.1 GENERAL
The potential receptors of environmental and social impacts in project development are mostly
the ambient air quality, ambient noise level, soil, water and solid waste management. Following
section summarizes the potential impacts on the physical, natural and socio-economic impacts
triggered by the project activities. The extent of impacts depends primarily on the environmental
management practices that would be adopted during the facility operation. The various
environmental and social parameters have been investigated to identify the impacts that are
likely to occur during the development, construction and operation periods of this project.
Project has partially been developed and constructed gradually in the time span of 5 to 6 years.
In development phase, basic infrastructure facilities like internal roads, rainwater harvesting,
storm water drainage, street lighting etc. is developed.
For proper evaluation and assessment of the environmental impacts due to development and
construction and functional phase of theproject, understanding to the various activities
associated with the project is essential. Various activities related to the project are different, in
terms of nature during the development, construction and functional phase.
The impact identification and prediction process aims to:
Identify potential source or cause of impact throughout the life of project.
Characterize the potential impacts affecting a target or receptor (physical, human and
socio-economic).
Assess the potential of changing the likely-hood of impact through Environmental
Management Plan (EMP).
Prediction of the impacts due to the development, construction and functional activities
encompass the development process to be undertaken during construction and functional phases.
For each category of environmental receptor (such as, ambient air quality, water quality, soils,
land, etc) the potential impacts of activities during development, construction and functional
phases and magnitude of the impacts have been assessed and discussed in detail in following sub
sections. In each case, cognizance has been taken to mitigation measures inherited in the
development, construction and functional phase. The baseline status of the environment at the
proposed site and the surrounding study area has been quantified and presented in chapter-3.
4.2 IMPACT IDENTIFICATION
The areas of environmental concerns for which the impacts and their predictions are taken into
consideration are mainly:
Land Environment
Modification and Expansion of Group Housing Project “Atharva Group Housing”
at Sec-109, Village PawalaKhusrupur, Gurugram, Haryana
EIA/EMP Report
M/s Raheja Developers Ltd. Page | 76
Water Environment
Air Environment
Noise Environment
Biological Environment
Socio economic Environment
Solid Waste
4.3 ANALYSIS OF IMPACTS DURING CONSTRUCTION PHASE
4.3.1 LAND ENVIRONMENT
4.3.1.1 LAND USE PATTERN, DRAINAGE& TOPOGRAPHY
Land use of the project site is residential as per the Master Plan of Gurugram, 2031. Entire land
is in possession of the Raheja group. Also, the site is flat land with variation of app. 1 m,
excavation was carried out for development of basement. Excavated soil was used for filling and
leveling and construction of roads. Topsoil was used for landscaping within the project site.
Adequate storm water drainage system is proposed at the site to channelize the storm water to be
generated from the site to prevent any water logging or local flooding during rains. Covered
storm water drains are provided at the site. Run-off from the site is collected and recharged into
the ground through 7 nos. of RWH pits (6 existing +1 proposed) at the site. Drainage pattern is
proposed as per natural and existing drainage pattern of the area. Recharge of the rainfall run-off
to ground not only prevents the local flooding during rains but also helps in augmenting the
ground water level of the aquifers. CGWB has declared entire Gurugram district as notified zone
in 2011. Hence recharging storm water into ground helps in maintaining ground water level.
4.3.1.2 SOIL QUALITY
Soil was excavated during construction of basement. Top soil was stripped off and was stored in
covered shed. This top soil was used for landscaping purpose at site. Remaining soil was used
within the site for road construction and filling & leveling purpose. Same will be followed
during construction of remaining basement area as proposed. However, there could be soil
contamination due to spillage of materials like paint, varnishes, fuel on the site. But such
contaminations can be minimized and are manageable. Thus,there is no major impact
anticipated on soil quality but mitigation measures are required to further minimize the issues
anticipated due to the project on soil quality. Mitigation measures proposed for prevention of
impact on soil quality are given below:
4.3.1.3 MITIGATION MEASURES
The top soil was and will be stripped off from excavation areas (app 15 cm) and
stockpiled for later reuse in landscaping in covered sheds. Total muck generation is
anticipated approx. 177460.14 cum.
Modification and Expansion of Group Housing Project “Atharva Group Housing”
at Sec-109, Village PawalaKhusrupur, Gurugram, Haryana
EIA/EMP Report
M/s Raheja Developers Ltd. Page | 77
Remaining soil was stored separately from top soil and wasused for filling &
construction purpose at the site and same will be followed for remaining construction.
Site is lower than the adjacent road level. Excavated soil was used for filling the
setback areas and construction of roads.
Site is being cleaned on daily basis. Debris and raw material which may pollute the soil
arebeing stored on the covered &paved surfaces
HSD is being stored on paved surface and drains are provided around such surfaces so
as to drain out the spillage.
Paints, solvents, wood preservatives, pesticides, adhesives and sealants are being
stored-in sealed containers, labelled, and disposed-off as per Hazardous and Other
Wastes (Managementand Trans-boundary Movement) Rules, 2016
Dustbins are provided at the site and in labour hutment area for collection of the waste.
Municipal waste from labour camp is being disposed-off through authorized vendor.
4.3.1.4 AGRICULTURE AND CROPPING PATTERN
Project site falls under residential land use and is in ownership of Raheja group. No agriculture
land and cropping pattern will be disturbed due to the project.
4.3.2 WATER ENVIRONMENT
4.3.2.1 SURFACE WATER QUALITY- IMPACT IDENTIFICATION &
EVALUATION
During construction phase, raw material/debris will be stored at the site or there could be
spillage of raw material, debris, paints etc. at the site. Run-off from site can get contaminated
with the raw materials, debris, paints and oil which may be spilled/stored at the site. This
contaminated run-off may enter the water body and pollute the water bodies close to the project
site. However, no water body except a drain exists within 10 km radius area. Thus, no major
impact is anticipated on surface water quality during operation phase. But measures are
proposed to minimize contamination of run-off and are given below.
To manage surface run-off during operation phase, M/s Raheja has planned to develop storm
water collection and recharge system at the site. This helps in collection of 100% run-off from
site and recharge to the ground. This will manage the storm water and also will augment the
aquifers which are being depleted. Total 7 nos of RWH pits are planned at the site out of which
6 are already existing.
4.3.2.2 MITIGATION MEASURES
Excavation willnot be carried out during monsoon season. Temporary drains should be
provided around the excavated area to prevent entry of any run-off to the pit.
Modification and Expansion of Group Housing Project “Atharva Group Housing”
at Sec-109, Village PawalaKhusrupur, Gurugram, Haryana
EIA/EMP Report
M/s Raheja Developers Ltd. Page | 78
Curing of structures was done using sprinklers during early morning and evening time.
This conserves the water and same will be followed for construction of remaining
structuresalso.
Raw materials wasstored in covered areas to the extent possible or covered with
tarpaulin covers to avoid their mixing with run-off and same will be followed for
construction of remaining structures also.
Oil is being stored at site in limited quantity in covered HDPE drums. Oil is stored on
paved surface provided with temporary drain. This will help in collection of spilled oil,
if any
Management and maintenance of existing RWH system
4.3.2.3 SURFACE WATER RESOURCES
Surface water was not used for construction of existing tower and will not be used for
constructing remaining tower also. Source of water during construction is treated water from
nearby CSTP of HUDA (at Manesar). Thus, there is no impact on surface water resources.
4.3.2.4 IMPACT ON GROUNDWATER QUALITY
App. 100-150labours were contracted for existing structures and they will continue for the
construction of remaining structures also. Water requirement during construction phase was 50-
60 KLD (treated water) which was sourced from nearby CSTP of HUDA (at Manesar).No
ground water is being extracted for construction thus impact on ground water is anticipated to be
insignificant. Wastewater generated from labour hutments and toilets was disposed-off through
septic tank and soak pits and same will be followed for construction of remaining structures.
Thus, impact on ground water due to project during construction phase is negligible. Some of
the measures proposed to prevent impact on ground water are given below:
4.3.2.5 MITIGATION MEASURES
No waste material, fuel, paints, emulsions and such raw material was and will be stored
on unpaved area
Proper waste management system was and will be followed at site for municipal waste,
hazardous waste and e-waste.
Toilets and bathrooms were and will be provided at site for construction labour with
proper drainage system
Wastewater from the toilets and bathrooms was and will be disposed-off through septic
tanks & soak pits. Septic tanks will be lined properly.
Modification and Expansion of Group Housing Project “Atharva Group Housing”
at Sec-109, Village PawalaKhusrupur, Gurugram, Haryana
EIA/EMP Report
M/s Raheja Developers Ltd. Page | 79
4.3.3 AIR ENVIRONMENT
Sources of air pollution during construction phase are construction activities, vehicular
movement, vehicular emissions, storage of raw material, piling of spoils, transportation of
material, unloading/loading activities, operation of DG sets and other diesel operated
construction equipment/machinery. Pollutants which may generate includes dust, SO2, NO2&
CO majorly.Estimations of the emission which may generate due to transportation of
construction raw material are made. Quantity of raw material required for remaining structures
of the project is given in Table 4.1 below.
Table 4.1:Quantity of construction material required for Existing + Expansion &
Modification
Construction
Material
Total Quantity (MT)
Cement 42575.06
Steel 15965.65
Sand 109098.6
Aggregate 164978.4
Bitumen (road) 5054.4
337672.11
Supposing, construction of remaining structureswill be completed in 2year time.
Total construction material required per day = 482MT
Capacity of one truck = 20 MT
Therefore, daily 24trucks are required to carry the load of construction material. Pollution load
due to transportation of raw material for construction phase is givenbelow in Table 4.2.
Table 4.2: Quantification of Pollution Load Due to Movement of Trucks
Parameter Emission Factor
(g/Km)*
Pollution Load
(g/Km) per day
CO 3.6 86.4
NOx 6.3 151.2
PM 0.28 6.72
SO2 1.42 34.08
HC 0.87 20.88
Source: CPCB, 2007
Note: It is assumed that diesel is used as fuel.
Emissions generated during transportation of construction raw material may impact the air
environment significantly but the impact is short term and will be there during construction
phase only. To minimize the impacts, it is required to manage the emissions and measures
proposed for managing the impacts are given below. Same measures are being followed for the
existing phase also.
Modification and Expansion of Group Housing Project “Atharva Group Housing”
at Sec-109, Village PawalaKhusrupur, Gurugram, Haryana
EIA/EMP Report
M/s Raheja Developers Ltd. Page | 80
4.3.3.1 MITIGATION MEASURES
Transportation of raw material and debris in vehicles covered with tarpaulin cover.
Storage of raw materials like cement, sand, soil etc in covered sheds or should be
covered by tarpaulin cover
Fuel used in construction vehicles and DG sets to be low in sulphur content.
Vehicles and equipment are being regularly serviced and maintained
DG sets are provided with stack of adequate height as per CPCB norms
Construction workers are provided with face mask
Sprinkling of water will be carried out at dust generation areas and haul roads
Vehicles entering the site will be checked for PUC certificates
Barricading the site for suppression of dust generation
Covering the scaffolding to minimize dust generation
4.3.4 NOISE ENVIRONMENT
During the construction of remaining structures of project, noise will be generated from the
various sources. Some major sources of noise generation at project site are listed here under:
Movement of vehicles carrying materials and loading & unloading activities.
Operating excavation machines, concrete mixer and other construction machines.
Operation of DG set.
Construction activities like concreting, hammering, etc.
All the above-mentioned sources at proposed development and construction activities will be
intermittent and would be experienced occasionally. The expected noise levels from various
activities are given hereunder in Table 4.3.
Table 4.3: Expected noise levels from various activities
From vehicles bringing materials to the site 70 dB (A)
DG set 85 dB (A)
Excavation 80 dB (A)
Concrete Mixtures 80 dB (A)
Hammering 80 dB (A)
Noise level which will be generated will be higher than the noise level standards as per Noise
Pollution (Regulations and Control) Rules, 2000 for residential land use (55 day time and 45
night time) and commercial use (65 Day time and 55 Night time). But the noise generation will
not be continuous for 24 hours. Also the noise levels reduces with the distances and with
provision of barriers. No worker will be exposed to noise levels of more than 80 dB(A) for
more than 8 hours. Mitigation measures proposed to manage the noise levels at the site are
listed below. Same measures are being followed for existing phase also.
Modification and Expansion of Group Housing Project “Atharva Group Housing”
at Sec-109, Village PawalaKhusrupur, Gurugram, Haryana
EIA/EMP Report
M/s Raheja Developers Ltd. Page | 81
4.3.4.1 MITIGATION MEASURES
Workers exposed to high noise level are provided with ear plugs
Job rotations are being carried out for workers involved in high noise generating
activities so as working hours in high noise area does not exceeds 8 hours
Site is barricaded which minimizes the impact of noise at site in neighboring areas
Working hours for noise generation activities are being restricted to day hours (6:00 am
to 10:00 pm).
DG sets are provided with acoustic enclosures
Machinery being used is regularly serviced and repaired.
Speed limits is restricted at site
Honking is prohibited at site
4.3.5 TRANSPORT LINKAGE AND TRAFFIC
Movement of transportation vehicles may add to the existing traffic on the connecting roads.
However raw material was and will be purchased from nearby market areas preferably to cut
down the transportation cost and emissions. The site is well connected by roads. App. 24nos. of
trucks are expected to carry material to the site daily. Timings of the trucks weremanaged to
avoid the peak traffic hours and same will be followed for the remaining construction.
4.3.5.1 MITIGATION MEASURES
Time of construction material carrying vehicles should be managed to avoid peak
traffic hours
Routes for transportation of materials is fixed
Raw material will be purchased from the nearby markets preferably
Parking space of transportation vehicles will be provided within the site to prevent
blockage of roads and congestion
4.3.5 BIOLOGICAL ENVIRONMENT
No significant flora & fauna is present at site. No wildlife movement is observed at site as site is
located near urban area. Thus no impacts are anticipated on biological environment. It is
proposed to reserve 35.7% of net plot area (20,447 sqm) for development of greens which
includes peripheral green belt and organized green spaces.At present, 17,385.1 sq m of area is
already under green cover at site.
Green spaces will provide the habitat to the avifauna and the small insects and animals like
squirrels etc. Greens will also provide good aesthetics in the area and will reduce the impact of
air & noise pollutions. Also the greens will keep the area cooler. Same green area will be
maintained during construction of remaining towers. No. of trees proposed to be planted are 716
(1 tree/80 sq m of plot area).
Modification and Expansion of Group Housing Project “Atharva Group Housing”
at Sec-109, Village PawalaKhusrupur, Gurugram, Haryana
EIA/EMP Report
M/s Raheja Developers Ltd. Page | 82
4.3.6 SOCIO-ECONOMIC IMPACTS
Project development involves transportation of material and construction activities.
Construction activities have their impacts on surroundings like unpleasant view, increased
traffic, increased noise, emissions, waste generation & piling of waste etc. All these have mal
impacts on the society. However construction phase generates employment options for skilled
and unskilled labour. Local people were and will be hired at the site to the extent possible.
Construction activities involve various risks for construction labour like slip, fall, fire, collapse
of structure etc. Accidents at construction site can be fatal not only for workers but for the
residents of nearby areas. Following measures were taken to minimize impact on socio-
economic environment and will be implemented during construction of remaining towers also:
4.3.6.1 MITIGATION MEASURES
Mitigation measures proposed for pollution control should be adequately followed
Hygienic conditions have been maintained at site by provision of dustbins at site for
collection of waste, regular cleaning of site, provision of toilets at site, regular disposal
of construction spoils, avoiding stockpiling of construction material at site etc.
Barricading the site to obstruct the unpleasant view
Following the occupational health & safety management plan which is as follows
o Provision of PPE to the workers like helmets, safety jackets, masks, ear plugs,
gum boots etc.
o Provision of neat and clean living space for construction labour
o Adequate illumination is provided at site and in labour camps, if any
o Clean drinking water facility is provided for construction labour
o Toilets and bathing facility is provided at the site to prevent open defecation and
unhygienic conditions at site
o Proper drainage and wastewater collection is provided at the site.
o Septic tanks and soak pits are provided at site for disposal of sewage generated
from toilets and bathrooms
o Dustbins are provided at site for collection of waste and workers should be made
aware for using the dustbins
o Municipal waste is being disposed off through local agency in the area on daily
basis. Construction material is also being disposed off regularly
o Water ponding is avoided at the site as it encourages breeding of mosquitoes
o LPG is provided as fuel and no open burning of fuel has been carried out at site
Modification and Expansion of Group Housing Project “Atharva Group Housing”
at Sec-109, Village PawalaKhusrupur, Gurugram, Haryana
EIA/EMP Report
M/s Raheja Developers Ltd. Page | 83
o Structure design of building is as per NBC, 2005. Good quality construction
material was used for construction of existing structures to prevent any collapse of
structure and will be used in remaining structures also.
o Quality supervisor was and will be deputed at site to ensure the quality of raw
material and the structures constructed
o EHS supervisor was and will be deputed at site to ensure the healthy and safe
environment at work place
o Workers are given training at the site for safety for handling the construction
material and equipment
o Fire-fighting facility is provided at the site and workers are being trained to handle
such emergency conditions
o Entry to the fuel storage area and electricity meter area is restricted
o Cautionary notice has been provided for safety and no entry in areas associated
with the risks
4.3.7 IMPACTS DUE TO SOLID WASTE
Solid waste expected to be generated during construction phase comprises of excavated
materials, used bags, bricks, concrete, MS rods, tiles, wood etc. Apart from this some quantity
of municipal waste also generate from labour camps. This waste requires being collected
segregated and disposed in manner that it does not mixes or polluting air, water and soiling
environment. Measures for management of solid waste carried out at site and will be followed
during construction of remaining tower also are listed below:
4.3.7.1 MITIGATION MEASURES
Dustbins are provided at site for collection of municipal waste. Municipal waste is
handed over to local authority on daily basis for disposal
Construction waste is being collected at designated location
Waste storage is done on paved surface and covered area
Waste is being segregated into re-usable at site, recyclable through vendors and rejected
waste
Re-usable waste is being stored at site in covered conditions
Recyclable waste is being sold to authorized vendors on regular basis
Rejected waste is disposed off through authorized agency on regular basis on locations
designated for construction waste disposal
Waste carrying vehicles is taken care not to be overloaded and should be covered
All these measures should be followed for expansion phase also
Modification and Expansion of Group Housing Project “Atharva Group Housing”
at Sec-109, Village PawalaKhusrupur, Gurugram, Haryana
EIA/EMP Report
M/s Raheja Developers Ltd. Page | 84
4.4 ASSESSMENT OF THE ENVIRONMENTAL IMPACTS DURING POST CONSTRUCTION
PHASE/OPERATION PHASE
4.4.1 LAND ENVIRONMENT
4.4.1.1 LAND USE PATTERN, DRAINAGE& TOPOGRAPHY
No impact on land use, drainage and topography are anticipated during operation Phase.
4.4.1.2 SOIL QUALITY
Soil erosion may happen, if open areas are left without paving or plantation. Thus, it is required
to either pave or green the open areas. Soil may get contaminated due to disposal of sewage on
soil, littering of municipal waste& e-waste and spillage of HSD. Thus, best management
practices have been adopted to avoid the contamination of soil. Mitigation measures are listed
below.
4.4.1.3 MITIGATION MEASURES
Proper municipal solid waste collection, management, treatment and disposal system is
followed for management of solid waste.
Local agency should be hired for collection and management of the waste from the site.
Door to door collection of the waste is carried out. Three binssystemhas been adopted
for collection and segregation of waste at source.
Recyclable waste is collected and sold to authorized vendors regularly
Inert fraction of waste is sent for disposal through local agency on daily basis and is
disposed at the designated locations
A room has been provided at site for storage of e-waste and it should be sold off to
authorized vendors on regular basis
HSD is stored in isolated location on paved areas to prevent contamination of soil due
to spillage. Drains are provided around HSD storage yards and drains should be fitted
with oil interceptors
No left-over construction debris or material should be stored at site
Waste oil from DG sets is stored in HDPE containers and is stored in isolated paved
areas. It is sold to authorized vendors on regular basis.
4.4.1.4 AGRICULTURE AND CROPPING PATTERN
No impacts are anticipated on agriculture and cropping pattern during operation phase of the
project.
Modification and Expansion of Group Housing Project “Atharva Group Housing”
at Sec-109, Village PawalaKhusrupur, Gurugram, Haryana
EIA/EMP Report
M/s Raheja Developers Ltd. Page | 85
4.4.2 WATER ENVIRONMENT
4.4.2.1 SURFACE WATER HYDROLOGY
Project site does not interface with any river/ water body thus no impact on hydrology is
anticipated. Due to development of the project, run-off from the site will increase. Run-off from
site initially (without any development) is estimated to be 7531 m3/ year which will increase to
24506.307 m3/ year (Table 4.4) after completion of project (existing + proposed), which is app.
3.25 times of the initial stage. However,to manage the storm water, adequate storm water
collection system has been developed at site and collected storm water isrecharged into ground
through filter packed RWH pits provided at site. 7such pits are proposed to be constructed (No.
of existing pits is 6 and No. of pits to be constructed 1). Thus, no impacts are anticipated on
surface water hydrology during operation phase.
Runoff before construction:
Total runoff before construction = Runoff Coefficient x Area (in m2) x Rainfall intensity
= 0.2 x 63,179.4 x0.596
= 7531m3/ year
Runoff after construction:
Run-off post construction = 24506.306m3/year.
Table 4.4Run-off Calculation from Site after development
S. No. Catchment Area (sq m) Run-off
Coefficient
Average
Annual
Rainfall
(mm)
Available
Annual
Run-off
(cum)
1. Roof top 13646.824 0.9 596 7320.1564
2. Hard green 10,966.3 0.6 596 3921.5489
3. Soft green 9,480.7 0.2 596 1130.0994
4. Paved Areas 29085.576 0.7 596 12134.502
Total Run-off 24506.307
4.4.2.2 SURFACE WATER QUALITY
Surface water quality may get polluted, if wastewater/sewage generated is disposed-off in water
body/canal without treatment. However, STP is provided at site for treatment of the sewage.
Dual plumbing system is provided to re-use treated water within the site for flushing and
gardening purpose. No wastewater is being discharged into any water body or canal nearby the
site. 61.32 KLD of STP treated water (at full capacity) will be discharged into sewer during dry
season and 228 KLD of treated STP waterwill be disposed off into municipal sewer during
rainy season. Treatment is given upto tertiary level. This water can be given to construction
sites in nearby areas or can be utilized for maintain the green buffer surrounding the site. Thus
no significant impact is anticipated on surface water quality. Run-off from the site especially the
Modification and Expansion of Group Housing Project “Atharva Group Housing”
at Sec-109, Village PawalaKhusrupur, Gurugram, Haryana
EIA/EMP Report
M/s Raheja Developers Ltd. Page | 86
areas near storage of HSD or waste may also affect the water quality of receiving waterbody.
However, it is planned to provide storm water collection system at the site. Collected storm
water will be recharged into ground through RWH system and thus prevent mixing of surface
water run-off in waterbody/canal. RWH system comprises of de-silting chambers & grease
traps. RWH pits contain filter media which helps purifying the water before recharging. Some
of the recommended mitigation measures are as follows:
4.4.2.3 MITIGATION MEASURES
STP is provided to treat the sewage generated at the site. STP designed is of capacity
more than the estimated sewage. Sewage generated will be treated in the STP of 550
KLD within the premises. STP of 550 KLD is already constructed at the site and is
operational.
An agency should be hired for operation and maintenance of STP
Dual plumbing system proposed to be provided at the site should be maintained
properly to continue re-use of STP treated water as proposed
Proper maintenance of green belt and green area so as run-off from site should not carry
sediments.
Provision of storm water management system at site and the collected storm water is
recharged into ground through filter packed RWH pits fitted with injection wells. This
minimizes the run-off from site.
4.4.2.4 GROUND WATER HYDROLOGY
Source of water during the operation phase is HUDA supply supplemented by private water
tankers. Groundwater will not be used for the project at any stage. Hence,there will be
insignificant impact on ground water hydrology. Total water demand after fully operational of
site will be 755 KLD out of which 411KLD is fresh water requirement. Provision of dual
plumbing system has minimized the fresh water requirement. Mitigation measures are proposed
to minimize impact on ground water hydrology and to reduce water consumption:
Sewage is treated in the inhouse STP provided within the site.
STP treated water should be recycled within project site to fulfill flushing, and
landscaping demand and reducing fresh water demand
Installation of water conservation fixtures like dual flush cistern, low water urinals, low
faucet taps, low flow showers etc. Adoption of these fixtures reduces the water demand
significantly
Flow regulators and water meter s should be provided at inlet point
Provision of rain water harvesting system. App. 13695.6m3/year of water will be
recharged annually through rain water harvesting system.
Modification and Expansion of Group Housing Project “Atharva Group Housing”
at Sec-109, Village PawalaKhusrupur, Gurugram, Haryana
EIA/EMP Report
M/s Raheja Developers Ltd. Page | 87
Notices shall be displayed at required location to make residents, staff and visitors
aware about necessity of water conservation
4.4.3 AIR ENVIRONMENT
Source of air pollution during operation phase are movement of vehicles and operation of DG
sets. Air emissions include dust, SO2, NOx, CO, PM10& PM2.5. It is estimated that traffic of
1736 PCU will generate due to development of project (existing + expansion project). Out of
1736 PCU, 1302 PCU are estimated to be car and 1302 PCU will be two wheelers. Standards as
given in “Emission Factor development for Indian Vehicles” Report by ARAI, 2008 are
followed for calculation of emissions and are given in Table 4.5. Emissions anticipated to
generate from movement of vehicles from site are estimated and are given in Table 4.6.
Table 4.5:Standard of Emissions from Vehicles
S. No. Vehicles at Site CO
Emission
Standard
(g/km)
HC
Emission
Standard
(g/km)
PM
Emission
Standard
(g/km)
NOx
Emission
Standard
(g/km)
1 Car-Petrol 0.84 0.12 0.002 0.09
2 Car-CNG 0.06 0.46 0.006 0.74
3 Car-Diesel 0.06 0.08 0.015 0.28
4 Scooter 0.4 0.15 0.015 0.25
5 Motorcycle 1.48 0.5 0.013 0.15
Table 4.6:Emissions from Vehicles at site
S. No. Vehicles at
Site
Nos. of
vehicles at
site
CO
Emission
(g/km/hr)
HC
Emission
(g/km/hr)
PM
Emission
(g/km/hr)
NOx
Emission
(g/km/hr)
1 Car-Petrol 63 11.375 1.625 0.027083 1.21875
2 Car-CNG 64 0.815 6.248333 0.0815 10.05167
3 Car-Diesel 126 1.6275 2.17 0.406875 7.595
4 Scooter 127 10.85 4.06875 0.406875 6.78125
5 Motorcycle 128 40.145 13.5625 0.352625 4.06875
The total 750 kVA (500*1+250*1) DG sets are installed at site. 2 DG sets of total capacity 1000
kVA (500*2) is proposed to be installed as per raise in demand. Details of DG sets are as
follows: DG sets are operational only during power failure. Thus, no significant emissions are
generated due to operation of DG sets. Mitigation measures are proposed to prevent the air
pollution during operation phase:
4.4.3.1 PROPOSED MITIGATION MEASURES
Maintenance of the peripheral green belt & avenue plantation developed at site
Provision of stacks as per CPCB norms with the DG sets
Use of low sulphur diesel as fuels for DG sets.
Sprinkling of water on the roads
Modification and Expansion of Group Housing Project “Atharva Group Housing”
at Sec-109, Village PawalaKhusrupur, Gurugram, Haryana
EIA/EMP Report
M/s Raheja Developers Ltd. Page | 88
Restriction of speed limit at site
4.4.4 NOISE ENVIRONMENT
Source of noise pollution during operation phase are DG sets operation, operation of pumps and
movement of vehicles. Following measures are proposed to be taken to minimize the impact of
noise:
4.4.4.1 MITIGATION MEASURES
DG sets are provided with acoustic enclosure. This will prevent exposure of residents to
DG noise
Pumps installed with STP, water supply system, sewage system, storm water system etc
shall be provided with noise mufflers so as noise during operation is minimal.
Regular repair & service of the pumps and machinery to minimize the noise generation
Proposed peripheral green belt will act as noise buffer
Speed limits are restricted within the site
Honking is prohibited at the site
4.4.5 TRANSPORT LINKAGE AND TRAFFIC
From traffic survey study, it is found that the traffic on the SH-15 A is still less than the
carrying capacity of highway. Expansion of the highway may be required in 2021 only. At
present SH-15 A can handle the load of the surveyed traffic.
4.4.5.2 MITIGATION MEASURES
Awareness to be spread for usage of public transport and car-pooling through posters
4.4.6 BIOLOGICAL ENVIRONMENT
Project site does not lies within eco-sensitive zone and is surrounded by agriculture and
residential area. Thusno negative impact on biological environment is anticipated. It is proposed
to be reserve 35.7% of plot area as green (20,447 sq m).At present, 17,385.1 sq m of area is
already under green cover at site. A thick peripheral green belt has been developed all along the
project site and organized greens will be maintained at the site. The peripheral
greenbeltconsistsof native plant species. Evergreen trees, ornamental trees & shrubs are planted
inside the premises and during construction of remaining structures, same will be followed.
Development of green belt renders positive impact on the project and surrounding by keeping
the surroundings coolers, improving the aesthetics, lowering down the dust and levels of other
pollutants in the air and controlling the noise level. Green belt also attracts the small animals
and birds and will provide them habitat.
4.4.7 IMPACT ON SOCIO-ECONOMIC ENVIRONMENT
Development of the project leads to increase in generation of sewage, increase in vehicles,
increased water demand and increased emissions from vehicles and operating DG sets etc. All
Modification and Expansion of Group Housing Project “Atharva Group Housing”
at Sec-109, Village PawalaKhusrupur, Gurugram, Haryana
EIA/EMP Report
M/s Raheja Developers Ltd. Page | 89
these increase the pressure on the existing resources thereby affecting the social environment.
However, adequate parking and wide roads are provided within the project site to accommodate
the expected vehicle. Traffic may increase on the Dwarka expressway which is app. 640 m from
the site in South directionand SH-15 A. Dwarka expressway is 8 lane highway and have
sufficient capacity to accommodate existing as well as incremental traffic due to the project.
However SH-15 A has sufficient capacity at present to accommodate the existing traffic and
traffic from project area but may require expansion in 2021. However due to provision of
multiples entry/exit and adequate parking at site there will not be significant impact on traffic
due to the project.
STP is provided to treat sewage and dual plumbing system is provided to re-utilize the STP
treated water. This has overall minimized the fresh water requirement of the project. DG set is
operated only in case of power failure and exhaust will be emitted through the stacks of height 6
m higher than the highest building. Water conservation fixtures are provided in the project to
minimize the water demand and rain water harvesting system is provided to recharge the ground
water aquifers. All these measures have minimized the impact on socio-economic environment
which may result from project development. Also, various facilities like park, benches & rides
inside the park, commercial area with facilities like ATM, shops,etc is proposed to be provided
within the project site which will facilitate the residents.
Also project development will provide employment opportunity to app 200 people for various
skilled, semi-skilled and unskilled jobs. Development of project will improve the infrastructure
in the area and the green belt will improve the aesthetic value. Thus, the project is anticipated to
have positive impacts on the socio-economic environment
4.4.8 ENERGY RESOURCES
Operating load for the project is calculated to be 8259.97 kVA. Source of power will be
DHBVNL. DG sets are proposed to be provided in case of power failure. Energy conservation
measures and alternative energy options have been incorporatedto minimize the energy
consumption in following manner:
Green belt and greenery developed around the project periphery
Usage of low energy embodied locally available construction material. Usage of fly ash
bricks, hollow bricks and fly ash mix cement for construction purpose. Usage of
excavated soil and construction debris within the project site as filling material
Orientation of building is kept such that it allows natural lightning and ventilation
Overhangs and façade are provided to control the direct sun heat
Over-deck insulation is provided in towers and community building to provide
insulation to the building
Modification and Expansion of Group Housing Project “Atharva Group Housing”
at Sec-109, Village PawalaKhusrupur, Gurugram, Haryana
EIA/EMP Report
M/s Raheja Developers Ltd. Page | 90
Usage of AAC blocks in building construction
Painting wall with white/light color heat reflecting paint
Provision of energy saving lighting at the site for internal and external lighting. All
internal lighting are BEE star rated. All internal lightning will be CFL or T5 lamps
based
Installation of grid connected SPV power plant of 40.3 KWp as per
BIS/HAREDA/MNRE specifications (NOC from HAREDA and satisfactory report are
attached Annexure XVII a & b).Also solar street lights are provided in common areas
along with LED street lights in ration of 1:3.
Usage of energy efficient lifts
Common lights are shut down to 50% after 10:pm when traffic movement is drastically
reduced
Solar based direction signage are provided within the project site
4.4.9 IMPACT DUE TO SOLID WASTE
It has been estimated that app. 3624 kg/day quantity of solid waste is generated from the project
site. If solid waste generated on site is stored in unregulated locations, it can lead to leachate
and other components of the decomposing solid waste to penetrate the soil surface, ground
water leading to the deterioration of soil quality at the project site. Solid waste generated on site
if allowed to accumulate without a proper disposal site and proper management, will adversely
affect the aesthetics of the project site. However, with proper mitigation measures in place, the
impacts could be short term and reversible.
4.4.9.1 MITIGATION MEASURES
Provision of twin color dustbins for collection of wet waste/food waste and other waste
in each dwelling unit and commercial unit.
Provision of door to door waste collection system
Provision of a site within project site for segregation and storage of MSW for minimum
two days in isolated location
Non-recyclable waste is disposed-off through local bodies on daily basis
Recyclable waste is sold to authorized vendor on regular basis
Room is provided at site for storage of E-waste and that shall be sold to authorized
vendors regularly
Used oil from DG sets is stored in HDPE containers and will be sold to authorized
vendors
All measures will be followed for expansion phase also
Modification and Expansion of Group Housing Project “Atharva Group Housing” at Sec-109, Village PawalaKhusrupur, Gurugram,
Haryana
EIA/EMP Report
M/s Raheja Developers Ltd. Page | 91
Table 4.7: Summary of Potential Impacts and Remedial Measures
S.
No.
Environmental
components
Potential
Impacts
Potential Source of
Impact
Controls Through EMP
& Design
Impact
Evaluation
Remedial Measures
1. Ground Water Quality
Ground Water Contamination
Construction Phase
Waste water generated from
temporary labor
tents.
Waste water will be
managed to achieve zero discharge and to maintain
hygienic condition at site
No significant impact as majority
of labors would be
locally deployed
Waste water arising from
the project is disposed off conforming to standars of
CPCB by septic tanks/soak
pits
Operation Phase
Discharge from the project site
No untreated water will
be discharged in sewer
No negative impact on ground
water quality
envisaged.
Waste water generated is
treated in STP within the site. Treated water is re-used at the
site for flushing, landscaping
and road & car washing. Remaining treated water may
be used for construction
within the site as proposed under expansion &
modification or in nearby
areas or may be discharged to
sewer
2. Ground Water
Quantity
Ground Water
Depletion
Construction Phase
No impact as
ground water will
not be used
No water ponding will be allowed at site
No impact Treated water from HUDA CSTP at Manesar is used for
carrying out construction.
Operation Phase
Source of water will be municipal
supply.
Water management will
be practiced to conserve water. Rain water
harvesting will be carried
out.
No Impact Using water efficiently
Re-cycle & Re-use of
water
Use of Water Efficient fixtures like flow regulators
& dual flushing cisterns
Provision of RWH drains
and pits (6 nos existing & 1 no proposed) to collect rain
Modification and Expansion of Group Housing Project “Atharva Group Housing” at Sec-109, Village PawalaKhusrupur, Gurugram,
Haryana
EIA/EMP Report
M/s Raheja Developers Ltd. Page | 92
water and ground water
recharge.
3. Surface Water
Quality
Surface water
contamination
Construction Phase
Surface runoff from
site during construction activity
& open defecation
of construction labour
Water & Sewage
management carried out at
the site to control water pollution
Measures are
taken to restrict the run-off from
site.
Silt traps and diversion
ditches are constructed to
control surface run-off during site construction and will be
constructed in construction
site area for expansion phase
Curing is done by spraying water to reduce run-off
Toilets are provided at site
to control open defecation
and sewage is disposed
through septic tank and soak pits
Operation Phase
Discharge from
Project Site
No untreated water will
be discharged outside
project site
No negative
impact on ground water quality
envisaged.
Treated water will be
recycled and re-used for flushing, horticulture and
road & car washing.
Remaining treated water may
be used for construction within the site as proposed
under expansion &
modification or in nearby areas or may be discharged to
sewer
4. Air Quality Dust Emissions
(PM)
Construction Phase
Construction
activities
Vehicular movement
Suitable control measures
are adopted for reducing
the PM level in the air as per air pollution control
plan.
Dust generation is
temporary and settles fast due to
dust suppression
techniques. Impacts are
restricted to small
Water sprinklers are
provided and will also be
provided for expansion & modification phase
Regular cleaning of
construction site
Construction material &
Modification and Expansion of Group Housing Project “Atharva Group Housing” at Sec-109, Village PawalaKhusrupur, Gurugram,
Haryana
EIA/EMP Report
M/s Raheja Developers Ltd. Page | 93
area. debris carrying vehicles are
covered.
Construction material stored
in covered area
SO2, NO2 and CO
Construction Phase
Vehicular exhaust
Running D.G. set (back up)
Rapid on-site
construction
Impact will be for short duration
Regular monitoring of
emissions and control measures are taken to reduce
the emission levels.
Ambient air quality
monitoring at site carried out every six monthly
Use of low sulfur diesel in
DG sets as fuel
Regular maintenance and
servicing of vehicles.
Emissions of PM, SO2, NOx
and CO
Operation Phase
Vehicular movement
Vehicular exhaust
Running D.G. set
(back up)
Suitable control
measures will be adopted for reducing emissions
Not significant. Regular
monitoring of air
quality will be carried out to
maintain air
quality
Stack height of DG
provided as per CPCB standards and will be
followed for proposed DG
also
Use of low sulfur diesel
Traffic management
Providing Footpath
Developing Green belt
All vehicles will carry PUC
5. Noise Environment
Construction phase
Construction
Activities
Operation of
Machinery
Operation of DG
sets
Noise Management by adopting suitable
measures.
Impact will be temporary and
will be restricted
to small area.
Provision of Noise shields
DG sets are provided with acoustic enclosures
Construction activities
involving high level noise
generation is restricted to
day time
Modification and Expansion of Group Housing Project “Atharva Group Housing” at Sec-109, Village PawalaKhusrupur, Gurugram,
Haryana
EIA/EMP Report
M/s Raheja Developers Ltd. Page | 94
Provision of ear muffs to workers
Traffic Management at site
to prevent honking
Use of machinery of
modern make, meeting the
noise standards
Vehicle randomly may checked for PUC certificate
Operation Phase
Noise from
vehicular movement
Noise from DG set
operation
Noise Management by
adopting suitable
measures
Not Significant. Development of green belt
at site carried out along with
organized greens. More area will be put under green
cover. Green belts acts as
noise buffer
DG sets provided with
acoustic enclosure
Proper traffic management & circulation at site. Speed
limits restricted to 15 kmph
and rumble strips provided for speed regulation.
Honking is prohibited in the
premise
6. Land Environment
Soil contamination
Construction Phase
Disposal of construction debris
Spillage of oil or
paints
Excavation of soil
By controlling soil
erosion and maintaining soil quality by periodic
soil quality monitoring
No significant impact.
Impact restricted
to project site
Construction debris are re-
used at site and remaining sent for disposal to
designated location of
HUDA. Same will be followed for expansion
Proper work management
to avoid spillage
Modification and Expansion of Group Housing Project “Atharva Group Housing” at Sec-109, Village PawalaKhusrupur, Gurugram,
Haryana
EIA/EMP Report
M/s Raheja Developers Ltd. Page | 95
Excavated soil will is re-used for landscaping in
project area.
Silt traps and dykes
provided to arrest silt as
required and will be provided for the
construction areas in
expansion and modification phase
Operation Phase
Municipal solid
waste
Used oil from
D.G. set
Solid waste
management as per MSW
Rules, 2016.
Since solid waste
is handled by the
authorized agency, open
waste dumping
is not practiced thus impact is
not significant.
Negligible impact.
MSW Management Rules,
2016 are followed. Vendors
hired for door to door
collection of the waste and will be followed in future as
well
Used oil generated is sold
to authorized vendors on regular basis. It is stored in
HDPE drums at isolated
location on paved surface
7. Biological Environment
Displacement of Flora and
Fauna on site
Construction Phase
Site Development during
construction
Important species
of trees, if any, will be identified and marked and
will be merged with
landscape plan
No significant vegetation exists
at project site so
no tree felling
involved.
No clearing of trees is or
will be carried out. Trees at site will be retained (in
boundary) and will be made
part of the green belt
Modification and Expansion of Group Housing Project “Atharva Group Housing” at Sec-109, Village PawalaKhusrupur, Gurugram,
Haryana
EIA/EMP Report
M/s Raheja Developers Ltd. Page | 96
Operation Phase
Day to day
activities
Development of Green Belt
Positive Impact Development of green belt at site carried out along with
organized greens. More area
will be put under green
cover. Green areas provide habitat to avifauna, insects
and small tree dwellers like
squirrels
Avenue plantation is carried out
Proper after care &
maintenance will be done
Proper peripheral green
belt is maintained on 24 m wide road crossing the site.
Median is also provided
with the green area
8. Socio-Economic
Environment
Population displacement
Construction Phase
Construction activities may lead
to temporary
relocation
Generation of
employment for local people especially labor
Positive Impact Generation of employment
for skilled, unskilled and semiskilled people
Development of an area
due to improved
infrastructure
Employment preferably is given to local people
Operation Phase
Site operation Generation of living
facility with all modern
facilities at affordable
rates & employment for local people
Positive impact
Modification and Expansion of Group Housing Project “Atharva Group Housing” at Sec-109, Village PawalaKhusrupur, Gurugram,
Haryana
EIA/EMP Report
M/s Raheja Developers Ltd. Page | 97
9. Traffic Pattern Increase in
traffic
Construction Phase
Transportation of
construction
material & debris
Proper Traffic Management &
circulation
Impact is short
time and
restricted to
construction phase
Provision of adequate parking space at site to
prevent parking of vehicle
on road
Proper traffic circulation
system at site
Proper signage system
Restrict hours of material transport to avoid peak
hours
Routes should be
designated so as to avoid already busy routes
Operation Phase
Vehicles of
residents, staff &
visitors
Proper Traffic
Management &
circulation
Not Significant
as project site is
well connected via network of
roads
Provision of adequate
parking space within site
Provision of adequate no
of entry and exit to prevent
congestion
Entry is through 24 m wide approach road
Proper traffic circulation
system at site
Informatory & directive
Sign boards are provided
Provision of pedestrian path to encourage walking
Modification and Expansion of Group Housing Project “Atharva Group Housing” at Sec-
109, Village PawalaKhusrupur, Gurugram, Haryana
EIA/EMP Report
M/s Raheja Developers Ltd. Page | 98
CHAPTER 5 :DAMAGE ASSESSMENT AND REMEDIATION PLAN
5.1 INTRODUCTION
Modification & Expansion of Atharva Group Housing is a construction project located at Sec-
109, Village PawalaKhusrupur, Haryana. Project site is spread over 63,179.4sq m (15.612 acres)
and will have built-up area of 2,66,094.125 sq m after expansion and modification. Project
comprise of residential towers, convenient shop, Villas/small tower (IFs), Community Building,
2 schools, EWS along with allied facilities. Project is developed partially after obtainingthe
environmental clearance from SEIAA, Haryana vide Letter no. DEH/09/SEIAA/66 dated
01.04.2009. Project is developed as per approval obtained from theDepartment of Town and
Country Planning as per modified planning.
5.2 HISTORICAL EC APPROVAL PRESPECTIVE AND COMPLIANCE TO SEIAA
RECOMMENDATION
Project will have built-up area more than 1,50,000 sq m thus the project will fall under Activity
8 (b) and Category B of EIA Notification, 2006 and thus requires prior environmental clearance.
Environmental clearance has been obtained from SEIAA, Haryana for built up area of 1,
57,917.34 m2. But the planning of the project was changed after obtaining the environmental
clearance and change in planning has led to increase in built-up area to 2,66,094.125sq m. But
the revised environmental clearance was not obtained for the project in anticipation that
environmental clearance is obtained for the built-up area more than 1,50,000 sq m. But on
realizing the requirement of environmental clearance for proposed modification, application was
submitted to SEIAA, Haryana for obtaining revised environmental clearance.
Other than this M/s Raheja has complied with all the conditions of the environmental clearance
issued to them and the status report on the compliance from MoEF&CC is attached as Annexure
XVIII. All proposed environmental measures have been taken up by M/s Raheja Developers
M/s Raheja Developers Ltd has obtained consent to establish from HSPCB (Annexure IV) for
construction as applicable under Air & Water Act. M/s Raheja Developers Ltd has also obtained
consent to operate under Air & water Act (1981 & 1974) and Authorization under Hazardous
Waste Rules, 2008 (Annexure V a, b & c) as applicable for the project from HSPCB.
Occupancy certificate was also obtained for the project from the DTCP, Haryana (Annexure
VI).
5.3 DAMAGE ASSESSMENT: SITE ASSESSMENT AND DEVELOPMENT
Location, Connectivity and Accessibility
Location of the project makes the site suitable for development of residential project. The site is
well connected with the roads and is located in urban area where markets, schools, hospital,
Modification and Expansion of Group Housing Project “Atharva Group Housing” at Sec-
109, Village PawalaKhusrupur, Gurugram, Haryana
EIA/EMP Report
M/s Raheja Developers Ltd. Page | 99
religious places etc are nearby. Surroundings are urban so the project has not affected any
pristine environment nor has caused any obstruction in scenic beauty of the place.
Environmental, Historical and Cultural Sensitivity
Project does not have any adverse impact on the surrounding environment. No archaeological
site or notified eco-sensitive zone is present within 2 km radius of the project site.
Vegetation removal and Tree Cutting
Project site was open land with no vegetation. No tree cutting was undertaken at the site. Project
is planned activity and 35.7% of the net plot area, i.e. 20,447sq m of area is reserved for
development of greens. At present, 17,385.1 sq m of area is already under green cover at site.
This green area includes trees, shrubs, small lawns and planters. Majorly native species are and
will be planted at the site.
Site Conditions
Project site was vacant land and no building or structure exists on the site so no demolition work
was involved.
Existing Utilities and Surrounding Population
All the project activities were undertaken within the site only without affecting the existing
utilities in area and surrounding areas. Project is equipped with all the facilities and amenities.
No complaints were received from surrounding population while developing the project.
Development of the project has improved the infrastructure in the area and project provides the
housing facility for people at affordable price.
Natural Drainage and Erosion Issues
Project site is flat land and no water body presents within 10 km from the project site. Only
Nazafgarh drain is present at 2.3 km distance from the project site. No drainage or water body
was affected due to project development. Project site is flat land and is not prone to erosion or
any land subsidence.
Land Use Suitability
Land use of the project site is residential and accordingly the residential project is developed by
M/s Raheja Developers Ltd. Thus, land use is in line with the Master Plan of Gurugram, 2031.
Conclusion
Site was suitable for the proposed development. No damage is caused due to the project on the
location and surroundings.
5.4 DAMAGE ASSESSMENT: CONSTRUCTION PHASE
Sourcing and Transportation of Construction Raw Material
Raw material was sourced from authorized suppliers and majority of material was sourced from local
area only which has minimized the emission during the construction phase. Site was already flat and
Modification and Expansion of Group Housing Project “Atharva Group Housing” at Sec-
109, Village PawalaKhusrupur, Gurugram, Haryana
EIA/EMP Report
M/s Raheja Developers Ltd. Page | 100
leveled and no earth was required from borrow areas for filling the site. Only excavated soil from the
site was used to level the site
Sourcing of Construction Water
During construction phase, source of water was treated water from nearby CSTP of HUDA (at
Manesar), sourced from private water tanker suppliers and no ground or surface water body was
disturbed.
Excavation of Soil and Impact on Soil
Land/soil environment was temporarily affected due to activities like site preparation, excavation,
material handling & storage etc. during construction phase. But disturbance was limited only to the
activity area.
Top Soil Management
Top soil was preserved and was used for landscaping purpose.
Natural Drainage and Storm Water Management
Storm water during the construction phase was managed with help of temporary drains and
sedimentation tank. To manage the storm water during operation phase, 7nos RWH pits (6 nos. of pits
are already constructed and 1 no. of pit to be constructed)are provided at the site. These structures will
help in recharging the storm water to the ground
Construction Waste Management
Waste generated during construction was segregated into recyclable and non-recyclable waste.
Recyclable waste was sent to the recyclers and non-recyclable was disposed-off through the local
bodies. Soil was excavated for foundations and construction of basements. Excavated soil was used
for leveling the site and landscaping purpose. Surplus soil was disposed-off through the authorized
agencies on payment basis. No construction waste was thrown in any water body.
Wastewater Management
The incremental pollution load from waste water generated from the project activity is negligible.
Toilets were provided at the site to prevent open defecation. Septic tanks and soak pits were provided
for disposal of this wastewater. Also, to manage sewage during operation phase STP of 550 KLD is
provided. Dual plumbing system is also proposed which minimized the water requirement and
reduced it by 343.68 KLD. Remaining treated water is given to near-by construction sites for
construction purpose and remaining is discharged into sewer.
Air Quality Management
Emission were generated during transport and handling of construction material. Such emissionswere
temporary. Dust was controlled by providing water sprinkling. Machinery and vehicle used during
construction phase were complying with emission and noise standards as prescribed by CPCB and
AutomativeResearch Authority of India. No major impact on environment was caused due to
Modification and Expansion of Group Housing Project “Atharva Group Housing” at Sec-
109, Village PawalaKhusrupur, Gurugram, Haryana
EIA/EMP Report
M/s Raheja Developers Ltd. Page | 101
operation of construction machinery and vehicle. DG set are also provided with the stack for
dispersion of the pollutants.
Noise Level Management
Site was barricaded during the construction phase. All noisy activities were undertaken during the day
time only. All construction vehicles and machinery were of high standard and make and regularly
serviced to minimize the abrasion and noise generation.
Health and Safety of the Workers
Measures were taken to minimize the impact on health and safety of workers. Workers were provided
with all the personal protective equipment. All machinery was serviced timely to minimize the impact
and chances of accidents. All fire safety measures were taken at the site
Conclusion
Though project has led to violation of the EIA Notification, 2006 but it can be said that the project
development has not caused any significant damage to the environment. Consideration of the
environmental management measures during construction phase and in project design has made
project environmentally and socially viable. Also,Environmental conditions were followed and abided
by during project execution. Violation was done due to confusion and improper understanding of
scope of the environmental clearance granted and was not intentional. M/s Raheja has complied with
all the conditions of the environmental clearance certificate and has also obtained all the statutory
clearances. Remediation is proposed to be undertaken for the construction of the proposed expansion
area and also for operation phase to minimize the damage.
5.5 REMEDIATION PLAN: CONSTRUCTION PHASE
Remediation plan was followed during the construction of project and will also be followed during
construction of remaining project and expansion & modification, also.
A. Air Quality Management
All the raw materials will be sourced from local areas only
All the materials will be transported in covered vehicles only
All construction material will be sourced in covered condition only
Water will be sprinkled at the site to suppress the dust especially in loading and unloading areas
Usage of low sulphur diesel in DG sets and machinery to be used
Maintenance of existing green belt and development of the remaining green belt area parallel to
the construction works
DG sets will be provided with the stack of appropriate height as per CPCB norms
B. Water Quality Management
Toilets will be provided at the construction site
Septic tanks and soak pits will be provided at the site for treatment of the wastewater from the
toilets
Modification and Expansion of Group Housing Project “Atharva Group Housing” at Sec-
109, Village PawalaKhusrupur, Gurugram, Haryana
EIA/EMP Report
M/s Raheja Developers Ltd. Page | 102
Curing will be done by spraying only and curing run-off will be collected and will be used for dust
suppression
No wastewater will be disposed off into any water-body
Water for construction will be treated water from nearby CSTP of HUDA (at Manesar) through
private water tanker suppliers. Also water from existing STP at site will be used for construction
purpose.
C. Soil Quality Management
Waste generated will be collected and segregated at site into recyclable and non recyclable waste
Recyclable waste will be sold to the vendors and non recyclable waste will be disposed off
through local agencies.
Excavated soil will be used for leveling and landscaping and remaining soil will be disposed off
through the authorized vendors.
Oil will not be stored on unpaved area. Oil will be stored on paved area in sealed containers. Care
will be taken to prevent spilling of oil
Waste will not be littered and wastewater will not be disposed on the soil/land
D. Noise Level Management
All noisy construction works will be undertaken during the day time only
All construction machinery and vehicle will have noise levels as per standards prescribed by
CPCB
Honking will be prohibited at site
All construction vehicle and machinery will be properly serviced
DG sets will be provided with acoustic enclosures
Ear muffs will be provided to workers working in noise areas
E. Socio-economy
Majorly local people will be employed during construction phase
If labour is required to be hire from outside, hutments will be provided within the site or any
rented accommodation will be hired
No labour hutment will be established outside the site
Clean drinking water, toilets, first aid and rest facility will be provided to labour at site
Proper illumination levels will be maintained at the site
Proper communication system will be provided at the site
All labour will be provided with the required personal protective equipment like helmet, gloves,
safety jacket and safety shoes
All basic facilities including bedding, drinking water, illumination, ventilation, sanitation facility
etc will be provided if accommodation is required to be provided for labour
F. Fire and Safety Management
Provision of sand buckets at site
Provision of fire extinguishers at the site
All the electrical equipment and circuits should be earthed
All wires should be covered and properly insulated
Modification and Expansion of Group Housing Project “Atharva Group Housing” at Sec-
109, Village PawalaKhusrupur, Gurugram, Haryana
EIA/EMP Report
M/s Raheja Developers Ltd. Page | 103
5.6 DAMAGE ASSESSMENT: OPERATION PHASE
Air Quality Management
No major source of air pollution during operation phase. DG of total capacity of 750 kVA (500*1
kVA +250*1 kVA) is provided at the site. 2 DG sets of total capacity 1000 kVA (500*2) is proposed
to be installed as per raise in demand. This will provide power back-up during power failure only. DG
sets are provided with stack for dispersion of pollutants. These stacks will aid release of gases at a
height such that it will not have significant impact on Ground Level Concentration of various gases.
Green area developed is and will properly being maintained and managed. Ambient air quality
monitoring will be done every six monthly.
Noise Management
No major noise generation is anticipated at the site. All equipment, machinery and DG sets are
provided with acoustic enclosures. Ambient noise level monitoring will be done every six monthly
Water Quality Management
Water flow meters are provided at the inlet point of raw water to meter the water requirement. Regular
inspection is being carried out to detect leakages in water supply system and if any found is repaired
immediately. Water requirement is minimized due to provision of dual plumbing system, i.e. usage of
STP treated water for flushing and landscaping and usage of the water conservation fixtures like the
dual flushing cisterns, low flow taps and faucets etc. Water quality will be tested every sox monthly
Traffic Management
Parking facility is provided as per the HUDA bye laws. No parking will be done outside the site which
will not lead to congestion at entry exit point. Parking space provision for visitors is also kept for the
visitors. Roads of adequate width are provided as per HUDA bye laws.
Wastewater Management
Sewage generated is treated upto the tertiary level in STP of 550 KLD (already constructed and
operational) at the site. Additional STP will be constructed adjacent to existing STP for treatment of
sewage which will be generated after construction of remaining project. Dual plumbing system is
provided so as the treated water is used for flushing and landscaping purpose. STP water is treated
upto the tertiary level STP treated water will be tested every six monthly
Energy Saving
All measures for energy savings were taken and complied with during operation phase. Approx 20.4
% of energy is saved. Details are given in remediation phase below
Conclusion
All environmental management measures are adopted and the damage assessed during operation phase
is nil. Budget for estimation of damage is presented in Tables 5.2and 5.3below. Also, to check the
effectiveness of the mitigation measures, it is proposed to conduct environmental monitoring and
schedule for environmental monitoring is given below in Table 5.4.
Modification and Expansion of Group Housing Project “Atharva Group Housing” at Sec-
109, Village PawalaKhusrupur, Gurugram, Haryana
EIA/EMP Report
M/s Raheja Developers Ltd. Page | 104
5.6 REMEDIATION PLAN: OPERATION PHASE
Remediation plan was followed during the construction of project and will also be followed during
construction of remaining project
Air Quality Management
Proper maintenance of the green area provided at the site
Sprinkling of the water on roads for dust suppression
All private vehicle owners will be asked to have PUC certificate
Air quality monitoring will be carried out every six-monthly
Water Resources and Quality Management
Dual plumbing system provided at the site will be maintained
Recycled water will continued to be used for flushing, road & car washing and landscaping
purpose
No wastewater will be dumped in sewer without treatment
STP will be properly operated and maintained
Rain water harvesting system will be regularly maintained and cleaned twice a year
Water to be stored in rain water harvesting tank will be used for car washing purpose
Water saving posters will be displayed at the site in all appropriate location
Flow meters will be provided at inlet point of fresh water to meter the water consumption.
Also flow meters will be provided at effluent point of STP to monitor the treated effluent
discharged
Treated water quality will be monitored on monthly basis
Water quality will be carried out every six monthly
Waste Management
Door to door collection system is provided for collection of domestic waste
Local vendors are hired for waste collection, management and disposal
Separate colored bins for dry recyclables and rejected waste are provided to residents as
well as in common and open areas
Rejected fraction of the waste is collected and disposed by local agencies on daily basis and
will be disposed at the designated locations. Recyclable waste and E-waste is sold to
authorized vendors
Green Area Management
Green area developed will be regularly maintained
Only organic manure and pesticides should be used for landscaping
Treated water from STP should be used for landscaping purpose as it is rich in NPK
Fine should be imposed on residents/visitors for harming the plants and vegetation
No resident should be allowed to cut the tree
Noise Management
DG sets will be provided with acoustic enclosures only
Noise monitoring will be carried out every six-monthly
Honking should be prohibited at the site
Modification and Expansion of Group Housing Project “Atharva Group Housing” at Sec-
109, Village PawalaKhusrupur, Gurugram, Haryana
EIA/EMP Report
M/s Raheja Developers Ltd. Page | 105
Speed limit should be maintained at the site
Energy Conservation Measures
Green belt and greenery developed around the project periphery
Usage of low energy embodied locally available construction material. Usage of fly ash
bricks, hollow bricks and fly ash mix cement for construction purpose. Usage of excavated
soil and construction debris within the project site as filling material
Orientation of building is kept such that it allows natural lightning and ventilation
Overhangs and façade are provided to control the direct sun heat
Over-deck insulation is provided in towers and community building to provide insulation to
the building
Usage of AAC blocks in building construction
Painting wall with white/light color heat reflecting paint
Provision of energy saving lighting at the site for internal and external lighting. All internal
lighting are BEE star rated. All internal lightning will be CFL or T5 lamps based
Installation of grid connected SPV power plant of 40.3 KWp as per BIS/HAREDA/MNRE
specifications (NOC from HAREDA and satisfactory report are attached Annexure XVII a
& b). Also solar street lights are provided in common areas along with LED street lights in
ration of 1:3.
Usage of energy efficient lifts
Common lights are shut down to 50% after 10:pm when traffic movement is drastically
reduced
Solar based direction signage are provided within the project site
Table 5.1: Energy Efficiency Calculations
S. No. Energy Saving Measures Units
consumption
with
conventional
lights-KWH
Units
consumption
with energy
saving measures
Total savings-
KWH
1 LED lights for internal lighting 818127.61 581921.69 236205.92
2 LED lights for lighting in common
areas
291596.31
197592.75
94003.56
3 Using BEE star rated appliance (3
star rating)
11559800.94
9994674.55
1565126.39
4 Energy efficient Motors 740512.00
702552.00
37960.00
5 Total 13410036.86
11476740.99
1933295.87
6 Percentage energy saving 14.4%
7 Energy saving with building design
and provision of green cover 6%
8 Total energy saving 20.4%
Table 5.2: EMP budget for Construction Phase (Majorly Incurred)
S. No. Activity Capital Cost (Lacs) Annual Recurring Cost (Lacs)
1. Health & safety of Workers (PPE,
safety officers etc)
4.0 1.0
Modification and Expansion of Group Housing Project “Atharva Group Housing” at Sec-
109, Village PawalaKhusrupur, Gurugram, Haryana
EIA/EMP Report
M/s Raheja Developers Ltd. Page | 106
2. Environmental Monitoring 2.0 2.0
3. Septic Tank & Soak Pit 4.0 1.0
4. Sedimentation tanks 3.0 0.5
5. Covered sheds for storage of material
3.0 0.5
Total 16.0 5.0
Table 5.3: EMP budget for Operational Phase (80% Incurred)
S. No. Activity Capacity/
Area/Nos./parameters
Capital
Cost
(Lacs)
Annual Recurring
Cost (Lacs)
1. STP 550 KLD 110 12
2. Landscaping &
planting trees
20,447 sq m 15 6
3. Solid waste Management
3624 kg/day 6 5
4. RWH Pit Installation 7 pits 21 3
5. Energy Saving 20% + SPV plant 20 5
6. Environmental
Monitoring*
Air, water, soil and noise 2.0 2
Total 174 33
* Environment monitoring to be carried out twice in year so recurring cost per annum is double that of
onetime cost of environmental monitoring.
Table 5.4: Environment Monitoring Plan
Environmental
Attribute
Parameter Regulatory
Body
Location Frequency Implementation
Construction Phase
Air PM10. PM2.5, SO2, NOx
SPCB Project Site Twice in a year (Pre &
Post
monsoon
seasons) -24 hourly
Project proponent through NABL
accredited
Laboratory
Water Quality As per
IS 10500:2012
SPCB Project Site Twice in a
year (Pre & Post
monsoon
seasons)
Project proponent
through NABL accredited
Laboratory
Noise Levels Leq dB(A) (Day &
Night),
Average and Peak values
SPCB Project Site Twice in a year (Pre &
Post
monsoon seasons)
Project proponent through
Laboratory
Soil Physical:
Texture, Grain
Size Sand, Silt, Clay;
Chemical: pH,
SPCB Project Site Twice in a
year (Pre &
Post monsoon
seasons)
Project proponent
through NABL
accredited Laboratory
Modification and Expansion of Group Housing Project “Atharva Group Housing” at Sec-
109, Village PawalaKhusrupur, Gurugram, Haryana
EIA/EMP Report
M/s Raheja Developers Ltd. Page | 107
Conductivity,
Ca, Mg, NA,
K, SAR, TKN, P, Organic
matter
Waste
Generation
Construction
debris, municipal
waste at site
and labour
camps
Local Bodies STP and
toilets at construction
site
Daily Project Proponent
Operation Stage
Air PM10. PM2.5,
SO2, NOx
SPCB Project Site Twice in a
year (Pre & Post
monsoon
seasons) -24
hourly
Project proponent
through NABL accredited
Laboratory
Water Quality As per
IS 10500:2012
SPCB Project Site Twice in a
year (Pre &
Post
monsoon seasons)
Project proponent
through NABL
accredited
Laboratory
Noise Levels Leq dB(A)
(Day & Night),
Average and
Peak values
SPCB Project Site Twice in a
year (Pre & Post
monsoon
seasons)
Project proponent
through Laboratory
Soil Physical: Texture, Grain
Size Sand,
Silt, Clay; Chemical: pH,
Conductivity,
Ca, Mg, NA,
K, SAR, TKN, P, Organic
matter
SPCB Project Site Twice in a year (Pre &
Post
monsoon seasons)
Project proponent through NABL
accredited
Laboratory
Green Belt Nos. of trees, area under
green cover,
survival rate
Head of Environment
Management
Cell
Project Site Six Monthly Project proponent & Plot Owners
Waste Domestic waste
Head of Environment
Management
Cell of each industry and
Plastic Park
Project Site Daily Project proponent & Plot Owners
Modification and Expansion of Group Housing Project “Atharva Group Housing” at Sec-
109, Village PawalaKhusrupur, Gurugram, Haryana
EIA/EMP Report
M/s Raheja Developers Ltd. Page | 108
5.6 NEED AND REMEDIATION PLAN: NEED AND RECOMMENDATION
Remediation plan and damage assessment plan is essential for violation case to ascertain damage
caused but as from the above assessment, no damage is caused so no remediation is required. However,
management measures are proposed and given in sections above and budget is also proposed which is
given above in Table 5.2 and 5.3above.
Modification and Expansion of Group Housing Project “Atharva Group Housing” at Sec-
109, Village PawalaKhusrupur, Gurugram, Haryana
EIA/EMP Report
M/s Raheja Developers Ltd. Page | 109
CHAPTER 6 :ALTERNATIVE TECHNOLOGIES
6.1 GENERAL
Consideration of alternative technologies used in building material, energy conservation and
transportation methods are discussed in this chapter.Environmental aspects of present scheme are not
just limited to impact of sources of pollution but also related to energy conservation, water
conservation and other issues, which are mentioned in Table 6.1below.
Table 6.1: Environment aspects of proposed scheme other than sources of Pollution
S.I. Area Aspect
I. Energy Conservation Solar Heating, Day Lighting, Design Natural Ventilation,
Thermal Transfer value of Building Material, Energy Efficient
Building Services and Equipment,Public Area Lighting, Exterior
Lighting, use of sensors.
II. Water Conservation Use of Recycled Water
Gardening water sources
Flushing water sources
Rainwater Harvesting
III. Internal Roads and
Accesses
Pedestrian Access Ramps for Disabled persons, Road painting
and Signage Speed Breakers
IV. Construction Material
Use
Low embodied construction materials selection
Use of recycled materials
6.2 ENERGY CONSERVATION
Operating load for the project is calculated to be 8259.97 kVA. Source of power will be DHBVNL.
For power supply during power failure, it is proposed to provide 2 nos. of DG sets oftotal capacity 750
kVA (500*1+250*1. 2 DG sets of total capacity 1000 kVA (500*2) is proposed to be installed as per
raise in demand. To reduce the emission load from DG set, only low sulphur diesel oilas fuel is used.
To manage the emissions, DG sets are provided with stack such that it is 6 m higher than the highest
building and emissions being discharged above the level of building.
Noise levels in DG sets are managed by providing the acoustic enclosures with DG sets. These
enclosures ensure that noise levels shall not exceed the permissible limits as specified by CPCB for
residential zone.
To make the building energy efficient various alternative lighting and energy options were considered.
These options were analyzed keeping in mind the capital cost, life, emissions generation, recyclability
and harmful impacts on environment. Energy efficient measures taken as per alternative analysis are
listed below.
Energy Efficient Features:
• Green belt and greenery developed around the project periphery
Modification and Expansion of Group Housing Project “Atharva Group Housing” at Sec-
109, Village PawalaKhusrupur, Gurugram, Haryana
EIA/EMP Report
M/s Raheja Developers Ltd. Page | 110
• Usage of low energy embodied locally available construction material. Usage of fly ash bricks,
hollow bricks and fly ash mix cement for construction purpose. Usage of excavated soil and
construction debris within the project site as filling material
• Orientation of building is kept such that it allows natural lightning and ventilation
• Overhangs and façade are provided to control the direct sun heat
• Over-deck insulation is provided in towers and community building to provide insulation to the
building
• Usage of AAC blocks in building construction
• Painting wall with white/light color heat reflecting paint
• Provision of energy saving lighting at the site for internal and external lighting. All internal
lighting are BEE star rated. All internal lightning will be CFL or T5 lamps based
• Installation of grid connected SPV power plant of 40.3 KWp as per BIS/HAREDA/MNRE
specifications (NOC from HAREDA and satisfactory report are attached Annexure XVII a &
b).Also solar street lights are provided in common areas along with LED street lights in ration
of 1:3.
• Usage of energy efficient lifts
• Common lights are shut down to 50% after 10:pm when traffic movement is drastically reduced
• Solar based direction signage are provided within the project site
It is estimate by using this equipment, material and adopting these measures that app 20.4% of energy
will be saved at site. Energy saving calculations are given in Table 6.2 below.
Table 6.2: Energy Saving Calculations
S. No. Energy Saving Measures Units
consumption
with
conventional
lights-KWH
Units
consumption
with energy
saving measures
Total savings-
KWH
1 LED lights for internal lighting 818127.61 581921.69 236205.92
2 LED lights for lighting in common
areas
291596.31
197592.75
94003.56
3 Using BEE star rated appliance (3
star rating)
11559800.94
9994674.55
1565126.39
4 Energy efficient Motors 740512.00
702552.00
37960.00
5 Total 13410036.86
11476740.99
1933295.87
6 Percentage energy saving 14.4%
7 Energy saving with building design
and provision of green cover 6%
8 Total energy saving 20.4%
6.3 WATER CONSERVATION
With respect to stage of ground water development Gurugramcomes under “Over exploited zone”. The
average stage of ground water development in the district is 308%. Although, various options have
Modification and Expansion of Group Housing Project “Atharva Group Housing” at Sec-
109, Village PawalaKhusrupur, Gurugram, Haryana
EIA/EMP Report
M/s Raheja Developers Ltd. Page | 111
been analyzed to minimize water foot prints of the project. Fresh Water demand of the project has been
tried to minimize by adopting dual plumbing alternative in place of conventional single piping system.
Dual plumbing system in place of single plumbing system enables usage of STP treated for various
uses and minimizes the fresh water demand. It is calculated that app. 343.68 KLD of STP treated water
will be recycled in the project after completion of the project. This water will be used to meet
horticulture, flushing, road and car washing water demand. Fresh water demand for project has been
reduced from 754.68 KLD to 411 KLD due to adoption of this alternative.
Other than this, various water conservation measures has been adopted in the project thereby reducing
the water requirement. Water conservation measures includes low faucet taps, low water urinals in
commercial areas, dual flushing cisterns, low flow showers, provision of flow meter at inlet & outlet
points, sensor operated low faucet taps in commercial area, tap aerators, flow regulators, etc. These
equipmentshave been installed in the project and have been reduce the water demand to larger extents.
These alternatives have been analyzed in terms of cost, water consumption, water saving, etc. Adoption
of these measures has higher capital cost than conventional taps and flushing system but will save cost
in operation phase.
In the project scheme, proposal of rain water harvesting is considered instead of discharging storm
water into the storm water drains of city. Rain water is collected from the site and is recharged into
ground through rain water harvesting pits and injection wells. Annual available run-off from site is
estimated to be 24506.307 cum (refer Table 6.3). This run-off is recharged to the ground. This doesn’t
only augment the ground water level of the site but also helps in reducing the run-off on roads & storm
water drains during heavy rains which may sometime leads to local flooding.
Table 6.3: Annual Available Run-off
S. No. Catchment Area (sq m) Run-off
Coefficient
Average
Annual
Rainfall
(mm)
Available
Annual
Run-off
(cum)
1. Roof top 13646.824 0.9 596 7320.1564
2. Hard green 10,966.3 0.6 596 3921.5489
3. Soft green 9,480.7 0.2 596 1130.0994
4. Paved Areas 29085.576 0.7 596 12134.502
Total Run-off 24506.307
Modification and Expansion of Group Housing Project “Atharva Group Housing” at Sec-
109, Village PawalaKhusrupur, Gurugram, Haryana
EIA/EMP Report
M/s Raheja Developers Ltd. Page | 112
6.4 INTERNAL ROADS & ACCESS ROADS
Road construction has been undertaken in the project site to facilitate movement of the vehicles expected
at the site. Road are designed so as they can bear the expected vehicle load and also width is as per NBC
standards for movement of fire tender. Green belt is provided all along the roads.
A 24 m wide road (as per Master Plan, 2031 of Gurugram) traverses through the plot. Pavements and
footpaths are provided for pedestrian movement. In place of concreted pavements & foot paths, grass
pavers are proposed to be layering the foot path.
Adequate parking is provided to accommodate the expected vehicles during operation phase of the
project. Parking is provided in accordance to HUDA Bye Laws.
For the purpose of lighting in common areas LED lightshas been provided, which saves approx.
94003.56 KWH energy. Automatic system for lighting shall be installed in common areas. Lights should
be switched on at 6:00 PM and should be reduced to half after 11:00 PM.
6.5 CONSTRUCTION MATERIAL
It is generally anticipated that building & construction projects do not have high emissions and
discharges involved. However, emissions and discharges are involved but indirectly. Production of
construction raw material is one of the majorly polluting sectors e.g. cement plant, brick kilns, steel
plants, batching plants etc. Some of the construction materials are energy intensive and their
manufacturing involves large amount of energy consumption. Along with the energy requirement,
emissions and raw material requirement for production of construction raw material, additional cost is
associated which is transportation of construction material. Transportation of material to longer distance
adds to cost, fuel requirement, emission and time.
Thus, analysis was made to opt for less energy intensive raw material. Locally available raw material,
i.e. sandstone shall be used for construction purpose to the extent possible. Additionally, option for
usage of fly-ash mix cement was also considered. Additionally, best practices were adopted like
avoiding stock piling of material at site, storage of raw material under covered sheds and careful usage
of raw material. These alternatives have to some extent reduced the requirement of raw material and
energy foot prints of the building.
6.6 CONCLUSION
No alternative site was analyzed for development of proposed project as the development was started
after obtaining environmental clearance from SEIAA, Haryana, for development of the project in 2009
and permission from Directorate of Town and Country Planning, Haryana. Alternatives were analyzed
in terms of technology. Alternative energy options, building material options, fixtures etcare analyzed.
Options having low cost (both capital & maintenance), low environmental impacts and high life were
tried to be selected. Some of the chosen alternatives have high capital cost but low O & M cost. Chosen
alternatives have made the project environmentally and socially feasible.
Modification and Expansion of Group Housing Project “Atharva Group Housing” at Sec-
109, Village PawalaKhusrupur, Gurugram, Haryana
EIA/EMP Report
M/s Raheja Developers Ltd. Page | 113
CHAPTER 7 :ENVIRONMENTAL MONITORING PROGRAM
7.1 OBJECTIVES
Monitoring program has the underlying objective to ensure that the intended environmental mitigations
are realized and these results in desired benefits to the target population causing minimal deterioration to
the environmental parameters. Such program targets proper implementation of the EMP. The broad
objectives are:
To evaluate the performance of mitigation measures proposed in the EMP.
To evaluate the adequacy of Environmental Assessment.
To suggest ongoing improvements in management plan based on the monitoring and to
devise fresh monitoring on the basis of the improved EMP.
To enhance environmental quality through proper implementation of suggested mitigation
measures.
To meet the requirements of the existing environmental regulatory framework and
community obligations.
The purpose of environmental monitoring is to evaluate the effectiveness of implantation of
Environmental Management Plan (EMP) by periodically monitoring the important environmental
parameters within impact area, so that any adverse effects are detected and timely action can be taken.
7.2 PERFORMANCE INDICATORS
The significant physical, biological and social components affecting the environment at critical locations
serve as wider/overall Performance Indicators. However, the following specific environmental
parameters can be quantitatively measured and compared over a period of time, therefore selected as
specific Performance Indicators (PIS) for monitoring because of their regulatory importance and the
availability of standardized procedures and relevant expertise.
Air Quality with respect to Particulate Matters (PM10, PM2.5), CO, NOx and SO2.
Water Quality for parameters defined in IS 10500: 2012 and amendments.
Noise levels as per CPCB Guidelines and at selected locations.
Soil Quality
Survival rates of trees planted and Green area development.
7.2.1 AMBIENT AIR QUALITY (AAQ) MONITORING
Ambient air quality parameters recommended for monitoring the project are Particulate Matters
(PM10& PM2.5), Oxides of Nitrogen (NOx) and Sulphur Dioxide (SO2). These are to be monitored, right
from the commencement of construction activity of the remaining blocks at selected locations on site,
excavation works, residential areas near the project site etc. Data is generated once in a season
Modification and Expansion of Group Housing Project “Atharva Group Housing” at Sec-
109, Village PawalaKhusrupur, Gurugram, Haryana
EIA/EMP Report
M/s Raheja Developers Ltd. Page | 114
excluding monsoon at the monitoring locations in accordance with the National Ambient Air Quality
Standards formulated by MoEF through Notification on November 18, 2009.
7.2.2 WATER QUALITY MONITORING
The physical and chemical parameters recommended for analysis of water quality relevant to project
will be as mentioned in IS 10500: 2012. The location, duration and the pollution parameters to be
monitored and the responsible institutional arrangements are given in the Environmental Monitoring
Plan.
7.2.3 NOISE LEVEL MONITORING
The measurements for monitoring noise levels would be carried out at sensitive receptors and
construction sites. Sound pressure levels would be monitored on twenty-four hour basis. Noise is
recorded at “A” weighted frequency using a “slow time response mode” of the measuring instrument.
7.2.4 GREEN AREA DEVELOPMENT
The green area development will be monitored during the construction and operation phase. The main
indicator will be survival rate of grasses and plants.
7.2.5 SOIL QUALITY
Soil quality will be monitored and compared with the Baseline soil quality generated before the start of
construction.
7.3 ENVIRONMENT MONITORING PLAN
The monitoring plan covering various performance indicators, frequency and institutional arrangements
of the project in the Pre-construction, Construction and Operation stages is shown in Table 7.1.
Table 7.1 – Environment Monitoring Program
Environment
al Attribute
Parameter Regulator
y Body
Location Frequency Implementation
Construction Phase
Air PM10. PM2.5, SO2,
NOx
SPCB Project Site Twice in a year (Pre & Post monsoon
seasons) -24 hourly
Project proponent through NABL
accredited
Laboratory
Water
Quality
As per IS
10500:2012
SPCB Project Site Twice in a year (Pre & Post monsoon
seasons)
Project proponent through NABL
accredited
Laboratory
Noise Levels Leq dB(A)
(Day &
Night),
Average and Peak values
SPCB Project Site Twice in a year (Pre
& Post monsoon
seasons)
Project proponent
through Laboratory
Soil Physical:
Texture,
SPCB Project Site Twice in a year (Pre
& Post monsoon
Project proponent
through NABL
Modification and Expansion of Group Housing Project “Atharva Group Housing” at Sec-
109, Village PawalaKhusrupur, Gurugram, Haryana
EIA/EMP Report
M/s Raheja Developers Ltd. Page | 115
Grain Size
Sand, Silt,
Clay; Chemical:
pH,
Conductivity,
Ca, Mg, NA, K, SAR,
TKN, P,
Organic matter
seasons) accredited
Laboratory
Waste
Generation
Construction
debris,
municipal waste at site
and labour
camps
Local
Bodies
STP and
toilets at
construction site
Daily Project Proponent
Operation Stage
Air PM10.
PM2.5, SO2,
NOx
SPCB Project Site Twice in a year (Pre
& Post monsoon
seasons) -24 hourly
Project proponent
through NABL
accredited Laboratory
Water
Quality
As per
IS
10500:2012
SPCB Project Site Twice in a year (Pre
& Post monsoon
seasons)
Project proponent
through NABL
accredited Laboratory
Noise Levels Leq dB(A)
(Day &
Night), Average and
Peak values
SPCB Project Site Twice in a year (Pre
& Post monsoon
seasons)
Project proponent
through Laboratory
Soil Physical: Texture,
Grain Size
Sand, Silt,
Clay; Chemical:
pH,
Conductivity, Ca, Mg, NA,
K, SAR,
TKN, P, Organic
matter
SPCB Project Site Twice in a year (Pre & Post monsoon
seasons)
Project proponent through NABL
accredited
Laboratory
Green Belt Nos. of trees,
area under green cover,
survival rate
Head of
Environment
Manageme
nt Cell
Project Site Six Monthly Project proponent
& Plot Owners
Waste Domestic waste
Head of Environme
nt
Manageme
Project Site Daily Project proponent & Plot Owners
Modification and Expansion of Group Housing Project “Atharva Group Housing” at Sec-
109, Village PawalaKhusrupur, Gurugram, Haryana
EIA/EMP Report
M/s Raheja Developers Ltd. Page | 116
nt Cell of
each
industry and Plastic
Park
Modification and Expansion of Group Housing Project “Atharva” at Sec-109, Village
PawalaKhusrupur, Gurugram, Haryana
EIA-EMP REPORT
M/s Raheja Developers Ltd. Page | 117
CHAPTER 8 :DISASTER MANAGEMENT PLAN
8.1 INTRODUCTION
Hazard Analysis involves identification and quantification of various hazards (unsafe
conditions). On the other hand, risk analysis deals with identification and quantification of risks,
the equipment and personnel are exposed to, due to accidents resulting from the hazard present
in the project.
Risk analysis follows an extensive hazard analysis. It involves the identification and assessment
of risks, which the neighboring populations are exposed to as a result of hazards present. This
requires a thorough knowledge of failure probability, credible accident scenario, vulnerability of
populations etc. Much of this information is difficult to get or generate. Consequently, the risk
analysis is often confined to maximum credible accident studies.
8.2 APPROACH
Risk involves the occurrence or potential occurrence of some accident consisting of an event or
sequence of events. The risk analysis assessment study covers the following:
Identification of potential hazard areas
Visualization of the resulting scenarios in terms of fire
Assess the overall damage potential of the identified hazardous events and the impact
zones from the accidental scenarios
Assess the overall suitability of the site from hazard minimization and disaster
mitigation point of view
Preparation of broad emergency management plan (DMP).
8.3 HAZARD IDENTIFICATION
Identification of hazards at the project site was of primary significance in the analysis,
quantification and cost-effective control of unlikely events of accidents. A classic definition of
hazard states that hazard is in fact the characteristics of system/process that presents potential for
an accident. Hence, all the components of project need to be thoroughly examined to assess their
potential for initiating or propagating an unplanned event/sequence of events, which can be
termed as an accident.
Based on information available, project stores HSD, which is flammable and can catch fire in the
event of spillage if ignition source would be available near the storage. In the event of spillage
followed by fire, pool fire will take place. Thermal radiation from pool fire will be confined with
the short distance. Further, state-of-the-art fire-fighting facilities has been provided to extinguish
fire. Therefore, risk of fire in HSD barrel will be negligible. No other toxic hazard will be stored
at the proposed project.
Modification and Expansion of Group Housing Project “Atharva” at Sec-109, Village
PawalaKhusrupur, Gurugram, Haryana
EIA-EMP REPORT
M/s Raheja Developers Ltd. Page | 118
8.4 EMERGENCY MANAGEMENT PLAN
Emergency Management Plan is necessarily a combination of various actions, which are to be
taken in a very short time but in a pre-set sequence to deal effectively and efficiently with any
disaster, emergency or accident with an aim to keep the loss to the minimum.
The project will have to have complete liaison and co-ordination with outside agencies to
minimize the effect of such disaster/emergency. The major function of the plan is to formulate a
procedure for:
Controlling it with minimum damage to men, material and machine
Rescuing victims and treat them suitably
Safeguarding others (evacuating them to safe places)
Identifying the person affected
Information to relatives of the causalities
Providing authoritative information to news media and others concerned
Preserving relevant records needed as evidence in any subsequent enquiry
8.4.1 SCOPE
The aim of hazard control and disaster management is concerned with preventing accidents
through good design, operation, maintenance and inspection, by which it is possible to reduce the
risk of an accident, but it is not possible to eliminate it. Since, absolute safety is not achievable,
an essential part of hazard control must include mitigating the effect of an accidents.
An important element of mitigating is emergency planning i.e. recognizing that accidents are
possible, assessing the consequences of such accidents and deciding on the emergency
procedures, both on site and off site, that would need to be implemented in the event of
emergency.
Emergency planning is just one aspect of safety and cannot be considered in isolation. In
particular, it is not a substitute for maintaining good standards within the project. Before starting
to prepare the plan, project management will ensure that the necessary standards and safety
precautions are administered.
Emergency plans are likely to be separate for on-site and off-site, but they must be consistent
with each other, i.e. they must be related to the same assessed emergency conditions. The on-site
plan is called Disaster Management Plan (DMP) and the off-site plan is called Emergency
Preparedness Plan (EPP).
8.4.2 OBJECTIVES
The overall objectives of an emergency plan are:
To localize the emergency and if possible, eliminate it; and
Modification and Expansion of Group Housing Project “Atharva” at Sec-109, Village
PawalaKhusrupur, Gurugram, Haryana
EIA-EMP REPORT
M/s Raheja Developers Ltd. Page | 119
To minimize the effects of the accident on people and property
Elimination of hazard will require prompt action by operators and emergency staff using, for
example, fire-fighting equipment and water sprays. Minimizing the effect will include rescue,
first aid, evacuation, rehabilitation and giving information promptly to people living nearby.
8.4.3 FORMULATION OF DMP
The assessment of the risk and hazards leads either to improvements being made to the project,
in the form of additional safeguards or better procedures, or to the decision being taken that the
risk is sufficiently small to be accepted.
The plan will be substantial document including following:
Assessment of the size and nature of the events foreseen and probability of their
occurrence;
Formulation of the plan and liaison with outside authorities, including the emergency
services;
Procedure for- raising the alarm and communication both within and outside the
works;
Appointment of key personnel and their duties and responsibilities are:
o work incident controller
o works main controller
Emergency control centre;
The project will set out the way for the remaining construction in which designed people at the
site for the incident can initiate supplementary action both insides or outside the works at an
appropriate time. An essential element of the plan must be the provision for attempting to make
safe the affected unit, for example by shutting it down. On a project site, the plan will contain the
full sequence of key personnel to be called in from other sections or from off-site.
It is particularly important that the requirement of the plan for emergency resources, both
personnel and equipment, are reasonable and can be quickly assembled in the event of an
emergency. Management will consider whether sufficient resources exist at the site to carry out
the plan for the various assessed incidents in conjunction with the emergency services, for
example sufficient water for cooling and fire fighting. The time element is of great significance
but is often overlooked.
8.4.4ONSITE EMERGENCY PLAN
Emergency is the one which may or may not cause material damage or injury but likely to have
an impact on the project. Such an emergency may be controlled using resources and resources
available in the surrounding establishments.
Scope of Onsite Emergency Plan
The scope of the plan is to ensure safety of life, protection of environment and protection of
property. Although the emergency may be caused by different factors such as natural calamity,
Modification and Expansion of Group Housing Project “Atharva” at Sec-109, Village
PawalaKhusrupur, Gurugram, Haryana
EIA-EMP REPORT
M/s Raheja Developers Ltd. Page | 120
civil disturbance, sabotage, equipment failure, human error, it will normally manifest in the form
of fire, etc.
Objective of Emergency Plan
To localize the emergency and if possible eliminate
To control and contain the incident as early as possible
To safeguard other employees by evacuating them to safe assembly points
To minimize the damage to the project;
To rescue accident victims and organize medical treatments
To re-establish normal conditions; and preserve relevant records and equipment for the
subsequent enquiry into the cause and circumstances of the emergency.
8.4.5 ROLES AND RESPONSIBILITY
Site Controller
Upon hearing announcement on P.A. system, he will proceed to emergency control
centre.
Establish contact with the Incident Controller through telephone
Declare emergency in consultation with incident controller
Review all possible action and assesses in consultation with incident controller and other
personnel.
Directs the evacuation of personnel.
Arranges for additional help from pot side agencies if required.
Exercises direct operational control over the works outside the affected area, with the help
of emergency coordinator (service/communicator) and emergency coordinator (first aid
and medical)
Liaison with Government official, if required
Once the situation is brought under control, calls off onsite emergency in consultation
with incident controller.
Emergency Coordinator (First Aid and Medical Management)
Arranges for first aid specific treatment with the advice of doctor
Organizes to shift injured to nearby clinic. Accompanies the victim if the case is critical
based on doctor’s advice
In case of need arrange for shifting to other medical centres as the case may be, maintains
contact with site controller from time to time
Emergency Coordinator (Security and Supply)
Upon hearing the siren, all person will be sent out and closes the gate
Modification and Expansion of Group Housing Project “Atharva” at Sec-109, Village
PawalaKhusrupur, Gurugram, Haryana
EIA-EMP REPORT
M/s Raheja Developers Ltd. Page | 121
Restricts visitor entry inside the premises
Directs the ambulance to the vicinity of site of incident
Ensures all the security guards are reporting to main gate.
He will rush to scene and reports to incident controller.
Additional fire extinguisher, hoses, nozzles, located in various points will be drawn and
arranged for fire fighting
Organizes to open the main gate as soon as the ambulance reaches
Co-ordinates with fire brigade group and help them
Driver-Ambulance
Keeps engine in running condition
Opens the back door of the ambulance
Goes back to seat
Takes the injured to hospital, stops the vehicle and opens the back door.
8.4.6 ALARM AND COMMUNICATION MECHANISM
Communication is crucial factor in handling an emergency. It is the practice that many persons
can raise an emergency alarm, so allowing the earliest possible action to be taken to control the
situation.
There will be an adequate number of points from which the alarm can be raised either directly,
by activating an audible warning, or indirectly, viz., a signal or message to a permanently
manned location. The alarm will alert the incident controller who will assess the situation and
implement appropriate emergency procedures. In areas where there is a high level of noise, it
may be necessary to install more than one audible alarm transmitter or flashing lights. Automatic
alarms may be appropriate on some site.
There will be a reliable system for informing the emergency services as soon as the alarm is
raised on site. The details of the communication arrangements will be agreed locally; in some
cases it may be advisable to have a direct line to the fire brigade. Pre determined code words to
indicate the scale and type of the emergency may be valuable.
8.4.7 FIRE FIGHTING FACILITIES
Adequate fire-fighting facilities is provided as per applicable rules in the various parts of the
proposed project as per applicable regulations.
Fire-fighting equipment is provide at the site as per norms of HUDA Bye-Laws., NBC, 2005
&Consultation with local Fire Officer
A. Fire Fighting System during Construction period
Modification and Expansion of Group Housing Project “Atharva” at Sec-109, Village
PawalaKhusrupur, Gurugram, Haryana
EIA-EMP REPORT
M/s Raheja Developers Ltd. Page | 122
During construction period the project proponent is provided with the following fire protection
measures:
i. Dry riser of minimum 100 m diameter pipe with hydrant outlets on the floor constructed with
a fire service inlet to boost the water in the dry rise.
ii. Two fire buckets on each floor is provided.
B. Design criteria considering Fire Safety
a) Openings in the separating wall
Openings in the wall or floor which are necessary to be provided to allow passage of all building
service like cable, electrical wiring, telephone cables, plumbing pipe etc. shall be protected by
enclosures in the form of duct/shafts, which is fire resistant.
b) Exits
i. All exits are provided continuous means of egress to the exterior of the building.
c) Staircases
i. Internal Stairs shall be constructed of non-combustible materials.
ii. No gas-piping or electrical panel shall be allowed in the stairway.
iii. External exit door of staircase enclosure at ground level shall open directly to the open
spaces.
iv. The main and external staircase is continuous from ground floor to terrace level.
C. Fire Fighting System
a) Fire Detection and Warning
Automatic fire detection and alarm facilities are provided to warn occupants early of the
existence of fire.
b) Automatic Sprinklers
Automatic Sprinklers are installed in:
• Basements.
• Shopping facilities
• Club
• On all floors of the building
c ) Fire-Water Connections
i. Firewater inlet & outlet connections are provided to the water storage tanks;
ii. External main fire ring, having 150 mm diameter and hydrants @ 45 m3/s spacing is
provided. This external fire ring is separated from the Sprinkler Main Systems;
iii. All flow switches, test valves, drain pipes etc. are provided as per NFPA guidelines
on the sprinkler system;
iv. All pump installation and arrangements are in accordance with IRI guidelines and
NFPA-20;
Modification and Expansion of Group Housing Project “Atharva” at Sec-109, Village
PawalaKhusrupur, Gurugram, Haryana
EIA-EMP REPORT
M/s Raheja Developers Ltd. Page | 123
v. All pumps and accessories and electrical controllers are as per UL/FM lists, tested,
approved and certified; and
vi. By-pass arrangements are provided (150 mm Dia. Nominal bore) with NRV & gate
valve and bulk flow meter on the discharge header of each pump to check the duties
of pumps.
d) Static Water Storage Tank.
i. A satisfactory supply of water for the purpose of fire-fighting shall always be
available in the form of underground and terrace level static water storage tank.
ii. To avoid the stagnation of water in the static water storage tank, the suction tank of
domestic water supply shall be fed only through an average overflow arrangement.
iii. The static water storage tank will be provided with a fire brigade collecting head with
numbers of male inlets in a valve box at suitable at street level.
Modification and Expansion of Group Housing Project “Atharva” at Sec-109, Village
PawalaKhusrupur, Gurugram, Haryana
EIA-EMP REPORT
M/s Raheja Developers Ltd. Page | 124
CHAPTER 9 :PROJECT BENEFIT
9.1 GENERAL
A symbol of modern day town planning, the area is the witness of fastest growing township in
the Gurugram Region, with international standard infrastructure. It has an exceptional demand
for residential complexes surrounded with modern amenities like convenient shopping, park,
EWS Blocks etc. Keeping this fact under consideration M/sRaheja Developers Ltd.are in process
of developing an group housing Project “Atharva Group Housing” At Sec-109, Village
PawalaKhusrupur, Gurugram, Haryana. Project site location, i.e. close to road, railway station,
hospital, school, religious places is suitable for development of residential project.
The project would provide positive benefits such as employment for a significant number of
people, many of who will be employed from the wider community. Additionally, the cumulative
effect of this type of development would result in noticeable economic benefits for the
community. The proposed project will also make a positive contribution to social infrastructure
and overall residential development. The benefits of the project are given as under:
9.2 RESIDENTIAL FACILITIES
M/s Raheja Devlopers Ltd. has provided excellent and affordable residential facilities. It offers
for the spacious apartments to portray a modern style of living with optimum space utilization
and well – designed interiors and special features like 24 Hour manned security on entrance
gates, Water supply through underground lines/ overhead tanks, Fire detection/ sprinkler system
as per fire safety norms, Electrical wiring in concealed conduits with modular switches and
power back up. These apartments are characterized by large open spaces, efficiently planned
interior design that ensures optimum space utilization yet giving a spacious feel to the home. For
a comfortable lifestyle these apartments are complete with all modern amenities and outstanding
levels of security. The apartments have been designed for efficiency and demand minimal
maintenance along with their very own social clubs and world class facilities.
9.3 SUSTAINABLE HOUSING
Planned project apart from having infrastructural comforts also has considered environmental
management, concept of resource efficiency and alternative energy resources in planning to
make the project sustainable.
Wastewater water generated within the site is treated within inhouse STP and treated water is
used within the site. The surplus treated water can be stored and can be used for watering the
green belt existing near the site and can be given at nearby construction sites. Air emission
sources at the site are DG sets and vehicular pollution majorly. Green belt is developed as
Modification and Expansion of Group Housing Project “Atharva” at Sec-109, Village
PawalaKhusrupur, Gurugram, Haryana
EIA-EMP REPORT
M/s Raheja Developers Ltd. Page | 125
peripheral plantation. Additionally green areas are provided within the site, which helps in
reducing the pollutant levels in the air. DG sets are used only in case of power failure and are use
only low sulphur diesel. Also DG sets have been provided with stacks for discharge of exhaust
gases. For management of solid waste generated from project, proper segregation, collection,
treatment and disposal plan is proposed. It is planned to segregate waste at source. Segregated
waste is collected door to door through contracted agency. Non recyclable waste is disposed off
through local bodies on daily basis. Recyclable waste is sold to authorized vendors.
As alternate energy option, it is proposed to reduce the power demand from project by using
solar power instead of the main power supply. Solar powered heaters and lights have been
installed within the site.
App 35.7 % i.e. 20,447 m2of the net plot area is planned under greens. Green includes green belt
which may attract avifauna and insect, parks and play area for kids. This adds on to aesthetic
view of area making it more acceptable for neighbors. Club is also provided within the project
site.
9.4 AESTHETIC IMPROVEMENT
Project is partially completed at present. After fully development of project a well planned
residential will come up. This will improve visual appearance of the area. Also it is proposed to
provide thick green belt &organized green area within the site.
20,447 sq. m. (35.7 % of the net plot area) is kept under green cover which will enhance the
aesthetics in and around the project site after completion of the project.
9.5 EMPLOYMENT OPPORTUNITIES
The proposed project envisions generation of employment through all phases of project. During
design phase skilled worker architecture, urban planners, consultants etc were employed. During
construction phase approx 100-150 labors were employed and will be employed for the
remaining construction. More employment generates during operational phase of the project.
Also during operation phase staff will be employed for convenient shops, as maintenance and
security staff and house-keeping staff. Thus project has potential to generate the employment.
Local people have higher probability of getting the employment.
9.6 INFRASTRUCTURE DEVELOPMENT
The project being residential group housing project is surrounded by developed urban area and
agriculture area. Further with development of the project, more development is expected to come
up in the region. More residential colony, markets, hospitals, hotels may come up in the area
seeing the increased population and potential for their growth in the area
Modification and Expansion of Group Housing Project “Atharva” at Sec-109, Village
PawalaKhusrupur, Gurugram, Haryana
EIA-EMP REPORT
M/s Raheja Developers Ltd. Page | 126
CHAPTER 10 :ENVIRONMENTAL MANAGEMENT PLAN (EMP)
10.1 INTRODUCTION
The Environmental Management Plan (EMP) is the synthesis of all proposed mitigating and
monitoring actions, set to a time frame with specific responsibility assigned and follow-up
actions defined. The EMP is a plan of action for avoidance, mitigation and management of the
negative impacts of the project. Environmental enhancement is also an important component of
EMP.
During the construction and operation phase of proposed project, anticipated impacts have been
identified, assessed and evaluated. To mitigate such adverse environmental impacts,
environmental management plan has been suggested in the following subsections. Environmental
Management Plan (EMP) also includes environmental monitoring plan and training plan for
implementation of environmental management plan.
The suggested environment management plan implemented with good management practices, is
not only yield desirable conditions but also leads to enhancement of positive impacts from the
project.
10.2 ENVIRONMENT MANAGEMENT PLAN
An EMP consists of a set of mitigation, monitoring and institutional measures applicable to
design, construction and operation (Post construction) stages. The major components of EMP
are:
Implementation of mitigation measures for mitigation of potentially adverse impacts
Monitoring during project implementation and operation
Integration of EMP with project planning and implementation framework
Implementation schedule
The EMP has been designed for construction phase and operational phase and majorly incurred
considering regulatory and other requirements to ensure minimal disturbance to the baseline
environmental conditions in the project area. EMP for both construction and operation phase of
the project is defined with respect to activities which may have an impact on the environment
and society. The mitigation measures, as proposed in Chapter 4, are implemented under the
overall supervision of project proponent. Additional best practices and management plan for
various concern areas are defined in the Sections below.
Modification and Expansion of Group Housing Project “Atharva” at Sec-109, Village
PawalaKhusrupur, Gurugram, Haryana
EIA-EMP REPORT
M/s Raheja Developers Ltd. Page | 127
10.3 AIR POLLUTION MANAGEMENT PLAN
10.3.1 CONSTRUCTION PHASE
Source of pollution during construction phase are operating DG sets, construction equipment,
construction activities, vehicular emissions and movement. Air Pollution Management Plan
includes the measures which are being taken at the site for reducing the emission and its impacts
on the working population at site and residing population in nearby areas. Measures are given
below and the same will be followed during remaining construction and expansion:
Transportation of raw material and debris in vehicles covered with tarpaulin cover
Storage of raw materials like cement, sand, soil etc in covered sheds or being covered by
tarpaulin cover
Fuel used in construction vehicles and DG sets are low in sulphur content.
Vehicles and equipment are regularly serviced and maintained
DG sets are provided with stack of adequate height as per CPCB norms
Temporary Green belt development is provided at the site for construction phase
Construction workers are provided with face mask
Sprinkling of water is being carried out at dust generation areas and haul roads
Vehicles entering the site are being checked for PUC certificates
Barricading the site for suppression of dust generation
Covering the scaffolding to minimize dust generation
10.3.2 OPERATION PHASE
Source of pollution during operation phase are operating DG sets, vehicular emissions and
movement. Air Pollution Management Plan includes the measures proposed to be taken at the
site for reducing the emission and its impacts on the working and residing population at site and
in nearby areas. Measures proposed are given below:
Maintenance of the peripheral green belt & avenue plantation developed at site
Provision of stacks as per CPCB norms with the DG sets
Use of low sulphur diesel as fuels for DG sets.
Sprinkling of water on the roads
Restriction of speed limit at site
10.4 WATER CONSERVATION PLAN
10.4.1 CONSTRUCTION PHASE
Water requirement during construction phase was50-60 KLD. Water is required for construction
activities, curing purpose, domestic use of workers, cleaning and sprinkling on road. Source of
water was treated water from nearby CSTP of HUDA (at Manesar) through private water
Modification and Expansion of Group Housing Project “Atharva” at Sec-109, Village
PawalaKhusrupur, Gurugram, Haryana
EIA-EMP REPORT
M/s Raheja Developers Ltd. Page | 128
tankers.Water requirement was and will be minimized by careful usage of water, avoiding
wastage and using water conservation fixtures. Following measures were and will be taken at site
to conserve water during construction phase of the existing blocks and will be implemented
during remaining construction:
Avoid excavation during monsoon season
Care taken to avoid soil erosion
Toilets are constructed on site during construction phase and the sewage is channelized
to the septic tanks in order to prevent waste water to enter into the water bodies
Any area with loose debris within the site is seeded with grass
To prevent surface and ground water contamination by oil and grease, leak-proof
containers are used for storage and transportation of oil and grease. The floors of oil and
grease handling area kept effectively impervious. Any wash off from the oil and grease
handling area or workshop is disposed off after passing it through oil & grease traps.
Storm run-off is channelized through temporary drains and is collected in sedimentation
tanks. This water is used for various purposes at site like wheel washing, curing,
cleaning etc
All stacking and loading areas are provided with proper garland drains, equipped with
baffles, to prevent run off from the site, to enter into any water body.
10.4.2 OPERATION PHASE
Water requirement during operation phase is 754.68 KLD out of which 588 KLD is domestic
water requirement, 122.68 KLD is horticulture water requirement and 44 KLD is used for road
and car washing during non rainy season. Fresh water requirement is 411 KLD and recycled
water requirement is 343.68 KLD after expansion and modification.Source of water during
operation phase is HUDA supply supplemented by private water tankers. Water conservation
measures proposed are given below:
STP treated water is recycled within project site to fulfill flushing and landscaping
demand and reducing fresh water demand
Installation of water conservation fixtures like dual flush cistern, low water urinals, low
faucet taps, low flow showers etc. Adoption of these fixtures reduces the water demand
significantly
Flow regulators and water meter should be provided at inlet point
Provision of rain water harvesting system. App. 24506.307m3/ year of water will be
recharged annually through rain water harvesting system after completion of all blocks.
Notices are displayed at required location to make residents, staff and visitors aware
about necessity of water conservation
Modification and Expansion of Group Housing Project “Atharva” at Sec-109, Village
PawalaKhusrupur, Gurugram, Haryana
EIA-EMP REPORT
M/s Raheja Developers Ltd. Page | 129
10.5 WATER QUALITY MANAGEMENT PLAN
10.5.1 CONSTRUCTION PHASE
Water quality of the project area can be impacted due to contamination of run-off with the waste
material at site. Measures which have been adopted to keep site clean and minimize the pollution
of run-off are listed below:
Bathrooms and toilets were and will be provided for construction labour with proper
drainage system. No run-off is there at site due to bathing and washing in open.
Septic tanks and soak pits were and will be provided for disposal of sewage generated at
site to prevent contamination of run-off and mixing of sewage with water of canal
nearby the site.
Site gets cleaned on daily basis so as mixing of run-off with debris can be prevented.
Raw material is stored in covered areas to the extent possible or covered with tarpaulin
covers to avoid their mixing with run-off
Drains are provided with the diesel storage area. These drains are provided with oil
interceptor to remove the oil from run-off before discharging.
10.5.2 OPERATION PHASE
Water requirement during operation phase is 754.68 KLD out of which 588 KLD is domestic
water requirement, 122.68 KLD is horticulture water requirement and 44 KLD is used for road
and car washing during non rainy season. Fresh water requirement is 411 KLD and recycled
water requirement is 343.68 KLD.Source of water during operation phase is HUDA supply
supplemented by private water tankers. App. 505.8 KLD (after completion of the project) of
sewage will be generated from the site which after occupying the project site fully by the
residents, if not managed will add on to pollution loads of the area significantly. Measures
proposed to manage the surface & ground water quality of the area are:
STP is to treat the sewage generated at the site. STP designed is of capacity more than
the estimated sewage quantity. STP of 550 KLD is already constructed and operational
at the site.
An agency should be hired for operation and maintenance of STP
Dual plumbing system is provided at the site and is maintained properly to continue re-
use of STP treated water as proposed and no untreated/treated water is discharged into
sewer system or land or water body.
Treated water is used within the site and if any remaining, isgiven to construction sites
near-by, or used to maintain public parks etc or discharge into the municipal sewer.
Modification and Expansion of Group Housing Project “Atharva” at Sec-109, Village
PawalaKhusrupur, Gurugram, Haryana
EIA-EMP REPORT
M/s Raheja Developers Ltd. Page | 130
Provision of storm water management system at site and the collected storm water shall
be recharged into ground through filter packed RWH pits fitted with injection wells.
This will minimize the run-off from site.
Proper maintenance of green belt and green area so as run-off from site should not carry
sediments.
10.6 SOIL QUALITY MANAGEMENT PLAN
10.6.1 CONSTRUCTION PHASE
Soil of the area can be affected significantly during construction phase. Soil may get compacted
due to movement of construction vehicle and machinery. Measures proposed to minimize the
impact on soil quality of the area were:
Total muck generation is anticipated from the project site is 177460.14 cum for the
entire project. The top soil was stripped from excavation areas (app 15 cm) and
stockpiled for later reuse in landscaping in covered sheds.
Remaining soil was stored separately from top soil and has been used for filling &
construction purpose at the site and same will be followed for remaining construciton.
Site is lower than the adjacent road level. Excavated soil was used for filling the setback
areas and construction of roads.
Site is being cleaned on daily basis. Debris and raw material which may pollute the soil
arebeing stored on the covered & paved surfaces
HSD is being stored on paved surface and drains are provided around such surfaces so as
to drain out the spillage.
Paints, solvents, wood preservatives, pesticides, adhesives and sealants are being stored-
in sealed containers, labelled, and disposed off as per Hazardous And Other Wastes
(Managementand Trans-boundary Movement) Rules, 2016
Dustbins are provided at the site and in labour hutment area for collection of the waste.
Municipal waste from labour camp is being disposed off through authorized vendor.
10.6.2 OPERATION PHASE
Soil is not being affected significantly during operation phase but gets polluted if solid waste or
sewage is allowed to spill over soil. Measures are proposed to minimize soil quality pollution
and are given below:
Proper municipal solid waste collection, management, treatment and disposal system
should be followed for management of solid waste
A room should be provided at site for storage of e-waste and it should be sold off to
authorized vendors on regular basis
Modification and Expansion of Group Housing Project “Atharva” at Sec-109, Village
PawalaKhusrupur, Gurugram, Haryana
EIA-EMP REPORT
M/s Raheja Developers Ltd. Page | 131
HSD should be stored in isolated location on paved areas to prevent contamination of
soil due to spillage. Drains should be provided around HSD storage yards and drains
should be fitted with oil interceptors
No left over construction debris or material should be stored at site
Waste oil from Dg sets is stored in HDPE containers and should be stored in isolated
paved areas. It should be sold to authorized vendors on regular basis.
10.7 SOLID WASTE MANAGEMENT PLAN
10.7.1 CONSTRUCTION PHASE
Solid waste is generated during construction phase and comprises of construction debris,
excavated soil and domestic waste from labour camp. Management measures proposed for solid
waste management are listed below:
Dustbins are provided at site for collection of municipal waste.
Municipal waste should be disposed off through local bodies on daily basis
Construction waste is being collected at designated location
Waste storage is done on paved surface and covered area
Waste is being segregated into re-usable at site, recyclable through vendors and rejected
waste
Re-usable waste is being stored at site in covered conditions
Recyclable waste has been sold to authorized vendors on regular basis
Rejected waste is being disposed off through authorized agency on regular basis on
locations designated for construction waste disposal
Waste carrying vehicles is taken care of not to be overloaded and should be covered
10.7.2 OPERATION PHASE
Solid waste is being generated during operation phase is majorly be municipal waste. Apart from
municipal waste some quantity of e-waste and hazardous waste (used oil) may be generated from
project site. Also the fuel stored at the site for DG sets may spill and lead to contamination of the
soil. Measures are proposed to manage the soil quality and are given below
Proper municipal solid waste collection, management, treatment and disposal system is
being followed for management of solid waste.
Local agency was hired for collection and management of the waste from the site.
Door to door collection of the waste is being carried out. Three bins system has been
adopted for collection and segregation of waste at source.
Non recyclable waste is being disposed off through local bodies on daily basis
Recyclable waste is collected and sold to authorized vendors regularly
Modification and Expansion of Group Housing Project “Atharva” at Sec-109, Village
PawalaKhusrupur, Gurugram, Haryana
EIA-EMP REPORT
M/s Raheja Developers Ltd. Page | 132
Inert fraction of waste is sent for disposal through local agency
A room has been provided at site for storage of e-waste and it sold off to authorized
vendors on regular basis
HSD is stored in isolated location on paved areas to prevent contamination of soil due to
spillage. Drains have been provided around HSD storage yards and drains are fitted with
oil interceptors
No left over construction debris or material is stored at site
Waste oil from DG sets is stored in HDPE containers and is stored in isolated paved
areas. It is being sold to authorized vendors on regular basis.
10.8 NOISE LEVEL MANAGEMENT PLAN
10.8.1 CONSTRUCTION PHASE
Source of noise during construction phase comprises of construction activities, operating
construction vehicles, equipment, vehicular movement etc. Measures proposed for managing the
noise level at site are given belowand will be implemented during remaining construction phase:
Workers exposed to high noise level were provided with ear plugs and will be provided
for remaining construction.
Job rotations were being carried out for workers involved in high noise generating
activities so as working hours in high noise area does not exceeds 8 hours and will be
followed the same for remaining construction.
Site is barricaded which minimizes the impact of noise at site in neighboring areas
Working hours for noise generation activities were being restricted to day hours (6:00
am to 10:00 pm) and will be followed the same for remaining construction.
DG sets are provided with acoustic enclosures
Machinery being used was regularly serviced and repaired and will be followed the same
for remaining construction.
Speed limits is restricted at site
Honking is prohibited at site
10.8.2 OPERATION PHASE
Source of noise during operation phase is vehicular movement & operation of pumps etc.
Measures proposed to manage the noise level at site are given below.
DG set is provided with acoustic enclosure. This prevents exposure of residents to DG
noise
Pumps installed with STP, water supply system, sewage system, storm water system
etchave been provided with noise mufflers so as noise during operation is minimal.
Modification and Expansion of Group Housing Project “Atharva” at Sec-109, Village
PawalaKhusrupur, Gurugram, Haryana
EIA-EMP REPORT
M/s Raheja Developers Ltd. Page | 133
Regular repair & service of the pumps and machinery to minimize the noise generation
Proposed peripheral green belt will act as noise buffer
Speed limits is restricted within the site
Honking is prohibited at the site
10.9 TRAFFIC MOVEMENT
For vehicles, adequate space for smooth movement and parking has been provided at the
proposed site to avoid any congestion and idling state emissions.
Proposed project have parking as per norms in the basement and open, as the case may
be.
A 24 m wide road as per the master plan, 2031 of Gurugram traverses through the site.
This road will be developed and will be handed over to HUDA. Internal roads are 9 m,
8m & 6m wide (including additional pathway) will be provided within the complex. So
there is not any impact on traffic movement due to the proposed project.
Separate entries and exits for smooth movement of traffic through adequate traffic
signage.
Carpooling shall be encouraged to minimize the use of private cars and pick up and drop
system from running metro.
Plantation shall be provided at roadsides and open spaces with the specific species to
attenuate dust and cyclonic winds.
The ambient air quality shall be monitored regularly to ensure that the activities at the site
are not polluting the ambient environment.
As mentioned above that the stand by D.G sets does not run continuously, only be operated
during interruption of electric supply. For good dispersion of gaseous emission, all D.G. setis
provided with adequate stack height, as per norms of CPCB. Regarding spread of PM10 and
PM2.5into the environment stringent action shall be taken for the maintenance of roads and
roadside plantation.
10.10 GREEN BELT MANAGEMENT PLAN
Total green area measuring20,477 m2 i.e. 35.7% of the net plot area is reserved for green spaces
in form of peripheral green belt and organized greens. The peripheral greenbelt consisting of
native plant species is already developed at site. Evergreen trees, ornamental trees & shrubs are
planted inside the premises. Trees with large & round canopy will be planted. Plantation will act
as noise buffer and will provide surface for dust settlement. Green belt development plan for the
area is given below
Modification and Expansion of Group Housing Project “Atharva” at Sec-109, Village
PawalaKhusrupur, Gurugram, Haryana
EIA-EMP REPORT
M/s Raheja Developers Ltd. Page | 134
10.10.1 GREEN BELT DEVELOPMENT PLAN
All the developments are associated with the pollution of one or more environmental component.
Plants are the natural sink of that pollution. Plants help in abatement of the pollution and restore
the degraded environment. Green belt lowers down the air pollution by providing a surface to
settle down or by absorbing the pollutants, attenuate noise level and uses the waste water. Phyto-
remediation is one of the most successful available technologies of restoring the degraded
environment. For this project area of 20,447 m2 i.e. 35.7 % of the net plot area is kept under
green cover. Green cover will comprise of:
A peripheral green belt
Avenue plantation
Lawns/parks & grass cretes
Planters
Table 10.1: Details of Green Area
S. No. Type of trees Area (sq m)
1 Green Area 20,447
2 No of Trees Required (@1 tree/80 sq m) 716 trees (57,266.1/80)
10.10.2 SELECTION OF PLANT SPECIES FOR GREEN BELT DEVELOPMENT
Selection of plant species for the development depends on various factors such as climate,
elevation and soil. The plants exhibits the following desirable characteristics in order has been
selected for plantation
Species should be fast growing and providing optimum penetrability with minimal
maintenance. Perennial, evergreen &fast growing trees
Species should be wind-firm and deep rooted
Indigenous and locally available species to be planted
Trees with high foliage density, leaves with larger leaf area and hairy on both the
surfaces. Round, thick & spreading canopy is preferred for peripheral green belt and
oblong canopy for road side plantation
Ability to withstand conditions like inundation and drought
Soil improving plants (Nitrogen fixing rapidly decomposable leaf litter)
Bird and insect attracting tree species
Tolerant to climatic conditions of the area and with less water requirement & after care
will preferable be planted. Species tolerance to air pollutants like SO2 and NO2 should
be preferred
Plantation trees with ornamental foliage & shrubs with fragrant flowers will enhance
scenic beauty of the area. Attractive appearance with good flowering and fruit bearing
Modification and Expansion of Group Housing Project “Atharva” at Sec-109, Village
PawalaKhusrupur, Gurugram, Haryana
EIA-EMP REPORT
M/s Raheja Developers Ltd. Page | 135
Plantation should be such that it maintains ecological & hydrological balance of the
region.
Trees and shrubs proposed to be planted at project site are given below in Table 10.2 below:
Table 10.2: List of Trees proposed to be planted
General Plantation:
1. Alstoniascholaris 2. Bauhineablackeana
3. Cassia fistula
4. Azadirachta indica 5. Erythrina cristagalli
Ornamental Trees
1. Solanum macaranthum 2.Callistemon lanceolatus
3. Plumeria alba
4. Plumeria rubra 5. Tabebuia rosea
Shrubs
1. Agave 2. Furcraea
3. Adenium
4. Bambusa vulgaris 5. Tabernum spp.
6. Lagerstroemia indica
Trees for Pollution Control and Noise
Absorbent
1. Grevillea robusta
2. Ficus benjamina
Palms 1. Phoenix dactylifera
2. Washingtoniafilifera
3. Foxtail palm
4. Cycus revolute
Climbers 1. Bougainvillea spp.
2. Jaquamontia
Ground Covers
1. Wedilia trilobata 2. Eranthemum nigrum
3. Clerodendron inermae
(Source: Guidelines for developing Green Belts by CPCB, 2000)
10.10.3 AFTER CARE AND MONITORING
Plants grown will be monitored for first three years. Nutrients will be supplemented and the
juveniles provided protection. Following measures will be taken:
Adequate nutrient supply will be maintained by providing manure timely
Absence of water stress
Construction of the protection wall all around to protect from animals and outsiders
from damage
Regular inspection of the site will be kept. Record keeping of number of saplings planted and
surviving will be kept. Regular pruning of road side trees will be done as per requirement.
Weeding will be carried out along with regular manuring & watering. Treated water from STP
will be used for watering plant which is rich in nutrients.
10.11 OCCUPATIONAL HAZARD MANAGEMENT PLAN
Construction activities have potential risk to construction worker. Occupational hazard
management plan werebeingfollowed for the project and are listed below and same will be
followed for the remaining construction:
Provision of PPE to the workers like helmets, safety jackets, masks, ear plugs, gum
boots etc.
Provision of neat and clean living space for construction labour
Modification and Expansion of Group Housing Project “Atharva” at Sec-109, Village
PawalaKhusrupur, Gurugram, Haryana
EIA-EMP REPORT
M/s Raheja Developers Ltd. Page | 136
Adequate illumination should be provided at site and in labour camps, if any
Clean drinking water facility should be provided for construction labour
Toilets and bathing facility should be provided at the site to prevent open defecation
and unhygienic conditions at site
Proper drainage and wastewater collection should be provided at the site.
Septic tanks and soak pits were provided at site for disposal of sewage generated from
toilets and bathrooms
Dustbins should be provided at site for collection of waste and workers should be made
aware for using the dustbins
Municipal waste shall be disposed off through local agency in the area on daily basis.
Construction material shall also be disposed off regularly
Water ponding should be avoided at the site as it encourages breeding of mosquitoes
LPG should be provided as fuel and no open burning of fuel should be carried out at
site
Structure design of building should be as per NBC, 2005. Good quality construction
material should be used for construction to prevent any collapse of structure
Quality supervisor should be available at site to ensure the quality of raw material and
the structures constructed
EHS supervisor should be deputed at site to ensure the healthy and safe environment at
work place
Workers should be given training at the site for safety for handling the construction
material and equipment
Fire-fighting facility is provided at the site and workers should be trained to handle
such emergency conditions
Entry to the fuel storage area and electricity meter area should be restricted
Cautionary notice is provided for safety and no entry in areas associated with the risks
The above mentioned management plan will be implemented during remaining construction
also phase.
10.12 ENERGY CONSERVATION PLAN
Project involves energy consumption for various purposes. Measures are proposed to minimize
the energy requirement and are listed below.
Green belt and greenery developed around the project periphery
Modification and Expansion of Group Housing Project “Atharva” at Sec-109, Village
PawalaKhusrupur, Gurugram, Haryana
EIA-EMP REPORT
M/s Raheja Developers Ltd. Page | 137
Usage of low energy embodied locally available construction material. Usage of fly ash
bricks, hollow bricks and fly ash mix cement for construction purpose. Usage of
excavated soil and construction debris within the project site as filling material
Orientation of building is kept such that it allows natural lightning and ventilation
Overhangs and façade are provided to control the direct sun heat
Over-deck insulation is provided in towers and community building to provide
insulation to the building
Usage of AAC blocks in building construction
Painting wall with white/light color heat reflecting paint
Provision of energy saving lighting at the site for internal and external lighting. All
internal lighting are BEE star rated. All internal lightning will be CFL or T5 lamps
based
Installation of grid connected SPV power plant of 40.3 KWp as per
BIS/HAREDA/MNRE specifications (NOC from HAREDA and satisfactory report are
attached Annexure XVII a & b).Also solar street lights are provided in common areas
along with LED street lights in ration of 1:3.
Usage of energy efficient lifts
Common lights are shut down to 50% after 10:pm when traffic movement is drastically
reduced
Solar based direction signage are provided within the project site
10.13 ENVIRONMENTAL MANAGEMENT CELL
Apart from having an Environmental Management Plan, it is also proposed to have a permanent
organizational set up charged with the task of ensuring its effective implementation of mitigation
measures and to conduct environmental monitoring. The major duties and responsibilities of
Environmental Management Cell shall be as given below:
To implement the environmental management plan.
To assure regulatory compliance with all relevant rules and regulations.
To ensure regular operation and maintenance of pollution control devices.
To minimize environmental impact of operations as by strict adherence to the EMP.
To initiate environmental monitoring as per approved schedule.
Review and interpretation of monitored results and corrective measures in case
monitored results are above the specified limit.
Maintain documentation of good environmental practices and applicable environmental
laws for a ready reference.
Modification and Expansion of Group Housing Project “Atharva” at Sec-109, Village
PawalaKhusrupur, Gurugram, Haryana
EIA-EMP REPORT
M/s Raheja Developers Ltd. Page | 138
Maintain environmental related records.
Coordination with regulatory agencies, external consultants, monitoring laboratories.
Maintenance of log of public complaints and the action taken.
Hierarchical Structure of Environmental Management Cell
Normal activities of the EMP cell are to be supervised by a dedicated person who report to the site
manager/coordinator of the project. The hierarchical structure of suggested Environmental
Management Cell is given in following Figure 10.1.
Figure 10.1 Environnent Management Cell Structure
10.14 ENVIRONMENT MANAGEMENT BUDGET
Environment management is essential component at all stages of project and various measures
are proposed to ensure environmental management during project construction & operation
stage. Budget has been allocated for environment management activities to be undertaken during
construction and operation phase of project and is given in Table 10.3 &10.4.
Table 10.3: EMP budget for Construction Phase (Majorly Incurred)
S. No. Activity Capital Cost (Lacs) Annual Recurring Cost (Lacs)
1. Health & safety of Workers
(PPE, safety officers etc)
4.0 1.0
2. Environmental Monitoring 2.0 2.0
3. Septic Tank & Soak Pit 4.0 1.0
Environmental
Cell
Environment
Health & Safety
Officer
Project Planning
group
Site Manager
Waste water
Treatment Plant
Operator
Greenbelt Dev. And
Maintenance Incharge Site Incpector &
Environment Awareness
Campaign Organizer
Modification and Expansion of Group Housing Project “Atharva” at Sec-109, Village
PawalaKhusrupur, Gurugram, Haryana
EIA-EMP REPORT
M/s Raheja Developers Ltd. Page | 139
4. Sedimentation tanks 3.0 0.5
5. Covered sheds for storage of material
3.0 0.5
Total 16.0 5.0
Table 10.4: EMP budget for Operational Phase (80% Incurred)
S. No. Activity Capacity/
Area/Nos./parameters
Capital
Cost
(Lacs)
Annual Recurring
Cost (Lacs)
1. STP 550 KLD 110 12
2. Landscaping & planting trees
20,447 sq m 15 6
3. Solid waste
Management
3624 kg/day 6 5
4. RWH Pit Installation 7 pits 21 3
5. Energy Saving 20% + SPV plant 20 5
6. Environmental Monitoring*
Air, water, soil and noise 2.0 2
Total 174 33
* Environment monitoring to be carried out twice in year so recurring cost per annum is double that of
onetime cost of environmental monitoring.
Modification and Expansion of Group Housing Project “Atharva” at Sec-109, Village
PawalaKhusrupur, Gurugram, Haryana
EIA-EMP REPORT
M/s Raheja Developers Ltd. Page | 140
CHAPTER 11 :SUMMARY AND CONCLUSION
11.1 PROJECT BACKGROUND
M/s Raheja Developers Ltd. had planned a Group Housing Project located at Village
PawalaKhushrupur Sector 109, Gurugram, Haryana for which environment clearance had been
obtained from SEIAA, Haryana vide Letter no. DEH/09/SEIAA/66 dated 01.04.2009 for an
area measuring 59,132.5722 m2 (14.812 acres) and Built-up area of 1, 57,917.34 m2.
After obtaining the environment clearance, there were amendment in Haryana Building Bye
Laws and allowable density of people/ha was increased than existing. To avail the allowable
benefit, planning for the project was modified.
Modification of planning led to increase in nos. of DUs to 703 from 528, increase in EWS units
from 116 to 125 and increase in plot area, basement area, total built-up area, expected
population, water demand and waste generation of the project.
On assumption that since project is granted environment clearance under 8(b) activity which
covers the project having built-up area more than 1,50,000 sq m (no closing limit), they
considered that some extra construction will automatically be covered in this clearance. Status
of construction of at site as per modified planning is given below:
S.
No.
Development Covered
Area (m2)
No. of DU Status of Violation Remarks
1. Residential
Towers
89784.22 593 general
& 72 servant
units
FAR is same but nos. of units
to increase due to increase in
density norms.
Occupied-OC
Obtained
2. EWS 3,020.7 125 FAR is same but nos. of units
increased to 125 as per
requirement.
Occupied-OC
Obtained
3. Villas/Small Towers (IFs)
14814.692 94 FAR increased, 11730.7 sq m approved for 18 villas
Constructed
4. Basements 55915.9 2 Area increased, 53019.34 sq
m approved
Being used-
OC Obtained
5. Community Building
202.614 -- Decreased. Constructed. OC Obtained
6. Convenient
Shopping
262.7 -- No Change. Constructed. --
7. School 1 804.7 -- School 1 approved. School 1 is under
construction
as per previous EC.
Total 164805.526 -- -- --
Modification and Expansion of Group Housing Project “Atharva” at Sec-109, Village
PawalaKhusrupur, Gurugram, Haryana
EIA-EMP REPORT
M/s Raheja Developers Ltd. Page | 141
Later M/s Raheja Developers Ltd on realizing requirement of obtaining re-environment
clearance, have applied for revised environment clearance for expansion of the project to
SEIAA, Haryana vide letter dated 26.10.2015 as per modified planning.
M/s Raheja Developers Ltd. has not applied for revised environment clearance to SEIAA,
Haryana initially for modifications in the plan but they have made provisions of all
environmental requirements for increased levels as per the EC. Environmental Management
Measures present at the site are listed below:
Proper sewerage collection and treatment in STP of 550 KLD
Re-usage of STP treated water for landscaping and flushing purpose through dual
plumbing system
Installation of water conservation taps and fixtures to minimize water requirement
Provision of energy saving lighting at the site for internal and external lighting
Installation of grid connected SPV power plant of 40.3 KWp as per
BIS/HAREDA/MNRE specifications. Also solar street lights are provided in common
areas
Proper collection and management of storm water and recharge of run-off to ground
through 6 nos. of filter packed RWH pits
Daily collection and disposal of municipal waste through local authorized vendor in the
area
Green area of 17,385.1 m2 already developed at the site which is 32.17 % of net plot
area. Green area includes peripheral green belt, avenue plantation, private lawns for
each tower and organized greens.
All the surface parking areas are provided with the grass pavers
DG sets are provided with acoustic enclosures
Provision of adequate parking and roads of adequate width
Provision of adequate fire-fighting equipment at the site
11.2 PROJECT DESCRIPTION
As discussed in section 2.1.1 as per modification, total area of the project site is 15.612 acres
(63,179.4 m2). Built-up area of the project after the modification and expansion will be
266094.125 m2.
Table 11.1: Summary of built-up area
S. No. Particulars Area (m2)
1. Proposed FAR (a+b+c+d) 162342.7339
a Residential FAR (Villa +Towers) 152944.665
b EWS 8344.085
c Convenient Shopping 262.7
d Community Building 202.614
e Additional Commercial 588.67
2. Non FAR (Service area, Balcony area ,stilt, Mumty,
Machine Room, Guard Room /modification as per
40617.105
Modification and Expansion of Group Housing Project “Atharva” at Sec-109, Village
PawalaKhusrupur, Gurugram, Haryana
EIA-EMP REPORT
M/s Raheja Developers Ltd. Page | 142
notification 2011 due to change in definition)
3. Area of Schools 2428.406
4. Stilt 1,552.5
5. Basement Area 59153.38
6. Total proposed Built-up Area 266094.125
Storm water harvesting system has been provided within the project site as per CPCB guideline
on Rainwater Harvesting & Artificial Ground water Recharge. 7 nos. of RWH pits are proposed
to be provided at the site for recharging the rain water.
11.3 BASELINE ENVIRONMENT
Baseline environment of the site has been studied through site visits, environmental monitoring
and through literature review.
Climate
The project site falls in Gurugram city. The city experiences four distinct seasons - spring
(February - March), summer (April - August), fall/autumn (September - October) and winter
(November - January), along with the monsoon season setting in towards the latter half of the
summer. Summers, from early April to mid-October, are typically hot and humid, with an
average daily June high temperature of 40 °C (104 °F). The season experiences heat indices
easily breaking 43 °C (109 °F). Winters are cold and foggy with few sunny days, and with a
December daytime average of 3 °C (37 °F). The Western Disturbance brings some rain in
winters that further add to the chill. The average annual rainfall is approximately 596 millimetres
(23.5 in). Wind speed varies from 7.9 to 24.8 kmph throughout the year and dominant wind
direction is from W.
Topography & Land Use
The terrain of the study area is generally plain with an average elevation ranges from 210 to 255
meters above mean sea level (MSL) and at project site the average elevation ranges from 215-
216 m amsl with the level difference of 1 m.As per the land use land cover study of 10 km radius
area of the project site, it is found that 41.2 % area is covered under Agriculture area. Settlement
area comprises about 35.9% of land area.
Seismicity
As per the 2014 Bureau of Indian Standards (BIS) map, Gurugram falls in Zones IV. The project
site lies in seismic zone IV which is high damage risk zone.
Soil Quality
Soil quality study has been undertaken at site and nearby 5 locations and it was found that soil
has sandy loam texture and is yellowish brown in color. As per physio-chemical analysis study,
it was found that soil is moderately fertile in the area.
Modification and Expansion of Group Housing Project “Atharva” at Sec-109, Village
PawalaKhusrupur, Gurugram, Haryana
EIA-EMP REPORT
M/s Raheja Developers Ltd. Page | 143
Drainage & Surface Water Quality
No major water body is present within 10 km radius of the project site. Surface water quality
testing is carried out for the Najafgarh drain present in the study area. Water quality of the drain
is poor and does not match any criteria as per the BDU criteria of CPCB for surface water body
classification.
Hydro-Geology & Ground water Quality
The Gurugram district is occupied by Quaternary alluvium and Pre-Cambrian meta- sediments of
Delhi Super Group. The alluvium comprises of thick beds of fine to coarse-grained sand with
alternating layers of thin clays. Water level ranges between 3.3 – 79.70 mbgl during pre-
monsoon period and during post monsoon period it varies between 3.05 – 77.5 mbgl.
Ground water quality of project site and Sector 110 was found potable and within the permissible
limites defined under IS:10500-2012 but ground water quality of Babarpur village and New
Palam Vihar was not found to be good and does not fall within the permissible limits of
parameters as given in IS:10500-2012
Air Quality
Air quality testing was carried out at the site and 4 other locations and it was found that level of
PM10 and PM2.5 exceeds the NAAQS standards, 2009 but value of SO2 and NO2 are within the
defines standards as per NAAQS, 2009
Noise Levels
Noise level monitoring was carried out at 5 locations including project site. The daytime
equivalent noise level ranges from 52.8 to 54.6 dB (A) and night-time equivalent noise level
ranges from 42.7 to 43.2 dB (A) at various sampling stations in the study area. The day time and
night time equivalent noise levels were within the standard limit specified for residential area.
Traffic Survey
Traffic survey data of SH-15 A is studied and is found that currently traffic volume on SH-15 A
is less than the defined capacity of SH-15 A but expansion may be required in 2021.
Biological Environment
No tree cutting was undertaken at the site. The project site does not support any significant
vegetation. Total green area measures 20,447 m2 i.e. 35.7 % of the net plot area is planned to be
kept under green cover. At present, 17,385.1 m2 of area is already kept under green cover at site.
This has improved the ecology of the area as native plant species are planted in green area.
Proper plantation including side green belt and green belt at median are developed on the 24 m
wide road traversing through the site. All the project activities were undertaken within the site
only without affecting the existing utilities in area and surrounding areas. No threatened, rare,
endangered or endemic species faunal species was recorded at the project site.
Modification and Expansion of Group Housing Project “Atharva” at Sec-109, Village
PawalaKhusrupur, Gurugram, Haryana
EIA-EMP REPORT
M/s Raheja Developers Ltd. Page | 144
Socio-Economic Environment
As per provisional reports of Census India, population of Gurugram district in 2011 is 1,514,432;
of which male and female are 816,690 and 697,742 respectively. Average literacy rate of
Gurugram is 84.70 %. Male literacy rate of Gurugram is 90.46% and Female literacy rate is
77.98%.
11.4 ANTICIPATED IMPACTS
Impacts which may result due to development of project are analyzed and studied. It is found
that project will have moderate impact on socio-economic environment, noise level and air
quality, water quality, soil quality traffic during construction phase. However these impacts are
temporary and manageable. Measures are proposed which should be taken during construction
phase. This can help in management of the impacts.
Similarly impact assessment has been undertaken for operation phase. It is found that project
may have moderate impact on air quality, water resources, traffic density aesthetics of the area,
ecology and socio-economic environment. Mitigation measures are proposed for management of
the anticipated impact for their mitigation and reduction.
11.5 ALTERNATIVE ANALYSIS
No alternative site has been analyzed for project development as development was started after
obtaining environmental clearance from SEIAA, Haryana and Directorate of Town and Country
Planning, Haryana. Analysis in terms of building material, electrical equipment, wastewater
treatment methodology etc., has been done. Options having minimal environmental and financial
cost are tried to be selected for development of project.
11.6 ENVIRONMENT MONITORING PLAN
The monitoring plan covering various performance indicators, frequency and institutional
arrangements of the project in the Pre-construction, Construction and Operation stages is
proposed and is given in the Environment Management Plan of the EIA Report
11.7 ENVIRONMENT MANAGEMENT PLAN
Environment management plan has been prepared for the construction of remaining blocks and
operation phase of the project. Management plan comprises of proposed pollution control
measures and best practices proposed to be adopted to minimize the pollution. Management
plans are proposed to prevent the negative impacts anticipated due to project development during
construction and operation phase. Environment management budget is also reserved both during
construction and operation phase. Environment budget of INR 16 lakhs is reserved for
construction phase with recurring cost of INR 5 lakhs and budget of INR 174 Lkahs is reserved
for operation phase with recurring cost of 33 Lakhs annually.
Modification and Expansion of Group Housing Project “Atharva” at Sec-109, Village
PawalaKhusrupur, Gurugram, Haryana
EIA-EMP REPORT
M/s Raheja Developers Ltd. Page | 145
CHAPTER 12 :DISCLOSURE OF CONSULTANT
12.1 DISCLOSURE OF CONSULTANTS ENGAGED
Declaration by Experts Contributing to the ‘EIA/EMP’ of Modification and Expansion of Group
Housing Project “Atharva” at Sec-109, Village PawalaKhusrupur, Gurugram, Haryana by M/s
Raheja Developers Ltd.
I, hereby, certify that I was a part of the EIA team in the following capacity that developed the
above EIA.
EIA Coordinator
Name Nisha Rani
Signature
12.2 FUNCTIONAL AREA EXPERT
The team composition and their respective responsibilities are listed in
Functional
Areas
Name of
Expert Involvement (Period and Task) Jan 2018 to finalization of report
Signature & Date
Air Pollution
Monitoring &
Control (AP)
Om
Prakash
Air pollution monitoring.
Meteorological data collection.
Identification & assessment of
quantum of emission and its Mitigation
measures.
26.12.2018
Water Pollution
(WP)*
Nisha
Rani
Water Quality monitoring
network designing.
Sampling of water samples
(surface and ground water).
Monitoring of water quality.
Water Balance
Identification & assessment of
quantum of water pollution and its
Mitigation measures.
STP Technology Suggestion.
26.12.2018
Modification and Expansion of Group Housing Project “Atharva” at Sec-109, Village
PawalaKhusrupur, Gurugram, Haryana
EIA-EMP REPORT
M/s Raheja Developers Ltd. Page | 146
Municipal Solid
Waste
Management
(MSW)**
S K Jain
Identification of nature of waste
generated during all project phase
Quantification of the waste
generated
Formulation of waste
managment plans
26.12.2018
Socio-
Economics (SE)
Anil
Kumar
Baseline socio economic data
collection
Evaluation of Socio economic
development status of the area.
Impact assessment on socio-
economy due to project development &
prepratio of managment plan
CSR Plan
26.12.2018
Ecology and
Bio-diversity
Conservation
(EB)
Ratnesh
Kotiyal
Collection of baseline ecological
data of study area
Identification of RET species
and eco-sensitive zone within study area
Formulation of bio-diversity
managment plan
26.12.2018
Hydrogeology
and Ground
Water & Water
Conservation
(HG)
Nisha
Rani
Estimation of run-off generation
from site & post project development
Formulation of rain water
harvesting plan
Formulation of water
conseravtion plan
26.12.2018
Soil
Conservation
(SC)
Manoj
Sharma Formulation of soil monitoring
plan
Soil sample collection and
testing
Impact assessment of project on
soil quality and development of
management plan
26.12.2018
Noise (N) Shweta
Gupta Formulation of noise monitoring
plan
Assessment of collected data
Impact assessment of project on
ambient noise levels and development
26.12.2018
Modification and Expansion of Group Housing Project “Atharva” at Sec-109, Village
PawalaKhusrupur, Gurugram, Haryana
EIA-EMP REPORT
M/s Raheja Developers Ltd. Page | 147
of management plan
Land Use (LU) Anil
Kumar Land use land cover study of
study area
Preparation of land use,
drainage, contour, DEM and other maps
Impact assessment of project on
land use and land cover and formulation
of land use management plan
26.12.2018
Declaration by the Head of the Accredited Consultant Organization/authorized person
I, S.K.Jain hereby, confirm that the above mentioned experts prepared the ‘EIA/EMP’ report
ofModification and Expansion of Group Housing Project “Atharva” at Sec-109, Village
PawalaKhusrupur, Gurugram, Haryana by M/s Raheja Developers Ltd.
I also confirm that the consultant organization shall be fully accountable for any mis-leading
information mentioned in this statement.
Signature:
26.12.2018
Name: S.K.Jain
Designation: Director, Technical
Name of the EIA Consultant organization EQMS India Pvt. Ltd.
NABET Certificate No. NABET/EIA/RA11/007
Director (Technical)
Date: 26.12.2018