Minutes of the 644th Meeting of SEIAA dated 07.10.2020

208
( R.K. Sharma ) Member (Rakesh K. Shrivastava) Chairman 644 th SEIAA Meeting dtd.07.10.2020 Page 1 of 208 Minutes of the 644 th Meeting of SEIAA dated 07.10.2020 The 644 th meeting of the State Level Environment Impact Assessment Authority was convened on 07.10.2020 at the Authority's Office in Environmental Planning and Co- Ordination Organization (EPCO), Paryavaran Parisar, Bhopal. The meeting was chaired by Shri Rakesh K. Shrivastava, Chairman, SEIAA. Member Secretary could not attend the meeting as he was on leave. The following members attended the meeting:- 1 Shri R.K. Sharma Member A. Following mining and other than mining cases have been considered:- S.No Case No. Category No. & date of latest SEAC & SEIAA meeting 1. 6621/2019 1(a) 462 st SEAC Meeting dated 30/9/2020. 2. 6624/2019 1(a) 462 st SEAC Meeting dated 30/9/2020. 3. 6627/2019 1(a) 462 st SEAC Meeting dated 30/9/2020. 4. 6628/2019 1(a) 462 st SEAC Meeting dated 30/9/2020. 5. 6626/2019 1(a) 462 st SEAC Meeting dated 30/9/2020. 6. 6697/2019 1(a) 462 st SEAC Meeting dated 30/9/2020. 7. 7755/2020 5(f) 462 st SEAC Meeting dated 30/9/2020. 8. 7786/2020 8(a) 462 st SEAC Meeting dated 30/9/2020. 9. 7777/2020 1(a) 463 rd SEAC Meeting dated 01/10/2020. 10. 7776/2020 1(a) 463 rd SEAC Meeting dated 01/10/2020. 11. 7780/2020 1(a) 463 rd SEAC Meeting dated 01/10/2020. 12. 7778/2020 1(a) 463 rd SEAC Meeting dated 01/10/2020. 13. 7785/2020 1(a) 463 rd SEAC Meeting dated 01/10/2020. 14. 7784/2020 1(a) 463 rd SEAC Meeting dated 01/10/2020. 15. 7779/2020 1(a) 463 rd SEAC Meeting dated 01/10/2020. 16. 7749/2020 1(a) 463 rd SEAC Meeting dated 01/10/2020. 17. 7794/2020 1(a) 463 rd SEAC Meeting dated 01/10/2020. 18. 7795/2020 1(a) 463 rd SEAC Meeting dated 01/10/2020. 19. 7792/2020 1(a) 463 rd SEAC Meeting dated 01/10/2020. 20. 7798/2020 1(a) 463 rd SEAC Meeting dated 01/10/2020. 21. 7804/2020 1(a) 463 rd SEAC Meeting dated 01/10/2020. 22. 7750/2020 1(a) 463 rd SEAC Meeting dated 01/10/2020. 23. 7799/2020 1(a) 463 rd SEAC Meeting dated 01/10/2020. 24. 7800/2020 1(a) 463 rd SEAC Meeting dated 01/10/2020. 25. 7567/2020 1(a) 463 rd SEAC Meeting dated 01/10/2020. 26. 6493/2019 1(a) 463 rd SEAC Meeting dated 01/10/2020. 27. 7662/2019 5(f) 463 rd SEAC Meeting dated 01/10/2020. 28. 7809/2020 1(a) 463 rd SEAC Meeting dated 01/10/2020. 29. 7812/2020 1(a) 463 rd SEAC Meeting dated 01/10/2020. 30. 7818/2020 5(f) 463 rd SEAC Meeting dated 01/10/2020. 31. 7728/2020 3(a) 463 rd SEAC Meeting dated 01/10/2020. 32. 7591/2020 1(a) 463 rd SEAC Meeting dated 01/10/2020. 33. 6285/2019 1(a) 463 rd SEAC Meeting dated 01/10/2020. 34. 7821/2020 1(a) 464 th SEAC Meeting dated 03/10/2020. 35. 7839/2020 1(a) 464 th SEAC Meeting dated 03/10/2020. 36. 7840/2020 1(a) 464 th SEAC Meeting dated 03/10/2020. 37. 7841/2020 1(a) 464 th SEAC Meeting dated 03/10/2020.

Transcript of Minutes of the 644th Meeting of SEIAA dated 07.10.2020

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 1 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020 The 644th meeting of the State Level Environment Impact Assessment Authority was convened on 07.10.2020 at the Authority's Office in Environmental Planning and Co-Ordination Organization (EPCO), Paryavaran Parisar, Bhopal. The meeting was chaired by Shri Rakesh K. Shrivastava, Chairman, SEIAA. Member Secretary could not attend the meeting as he was on leave. The following members attended the meeting:-

1 Shri R.K. Sharma Member

A. Following mining and other than mining cases have been considered:-

S.No Case No. Category No. & date of latest SEAC & SEIAA meeting 1. 6621/2019 1(a) 462st SEAC Meeting dated 30/9/2020. 2. 6624/2019 1(a) 462st SEAC Meeting dated 30/9/2020. 3. 6627/2019 1(a) 462st SEAC Meeting dated 30/9/2020. 4. 6628/2019 1(a) 462st SEAC Meeting dated 30/9/2020. 5. 6626/2019 1(a) 462st SEAC Meeting dated 30/9/2020. 6. 6697/2019 1(a) 462st SEAC Meeting dated 30/9/2020. 7. 7755/2020 5(f) 462st SEAC Meeting dated 30/9/2020. 8. 7786/2020 8(a) 462st SEAC Meeting dated 30/9/2020. 9. 7777/2020 1(a) 463rd SEAC Meeting dated 01/10/2020. 10. 7776/2020 1(a) 463rd SEAC Meeting dated 01/10/2020. 11. 7780/2020 1(a) 463rd SEAC Meeting dated 01/10/2020. 12. 7778/2020 1(a) 463rd SEAC Meeting dated 01/10/2020. 13. 7785/2020 1(a) 463rd SEAC Meeting dated 01/10/2020. 14. 7784/2020 1(a) 463rd SEAC Meeting dated 01/10/2020. 15. 7779/2020 1(a) 463rd SEAC Meeting dated 01/10/2020. 16. 7749/2020 1(a) 463rd SEAC Meeting dated 01/10/2020. 17. 7794/2020 1(a) 463rd SEAC Meeting dated 01/10/2020. 18. 7795/2020 1(a) 463rd SEAC Meeting dated 01/10/2020. 19. 7792/2020 1(a) 463rd SEAC Meeting dated 01/10/2020. 20. 7798/2020 1(a) 463rd SEAC Meeting dated 01/10/2020. 21. 7804/2020 1(a) 463rd SEAC Meeting dated 01/10/2020. 22. 7750/2020 1(a) 463rd SEAC Meeting dated 01/10/2020. 23. 7799/2020 1(a) 463rd SEAC Meeting dated 01/10/2020. 24. 7800/2020 1(a) 463rd SEAC Meeting dated 01/10/2020. 25. 7567/2020 1(a) 463rd SEAC Meeting dated 01/10/2020. 26. 6493/2019 1(a) 463rd SEAC Meeting dated 01/10/2020. 27. 7662/2019 5(f) 463rd SEAC Meeting dated 01/10/2020. 28. 7809/2020 1(a) 463rd SEAC Meeting dated 01/10/2020. 29. 7812/2020 1(a) 463rd SEAC Meeting dated 01/10/2020. 30. 7818/2020 5(f) 463rd SEAC Meeting dated 01/10/2020. 31. 7728/2020 3(a) 463rd SEAC Meeting dated 01/10/2020. 32. 7591/2020 1(a) 463rd SEAC Meeting dated 01/10/2020. 33. 6285/2019 1(a) 463rd SEAC Meeting dated 01/10/2020. 34. 7821/2020 1(a) 464th SEAC Meeting dated 03/10/2020. 35. 7839/2020 1(a) 464th SEAC Meeting dated 03/10/2020. 36. 7840/2020 1(a) 464th SEAC Meeting dated 03/10/2020. 37. 7841/2020 1(a) 464th SEAC Meeting dated 03/10/2020.

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 2 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020

38. 7842/2020 1(a) 464th SEAC Meeting dated 03/10/2020. 39. 7843/2020 1(a) 464th SEAC Meeting dated 03/10/2020. 40. 7860/2020 1(a) 464th SEAC Meeting dated 03/10/2020. 41. 7836/2020 1(a) 464th SEAC Meeting dated 03/10/2020. 42. 7837/2020 1(a) 464th SEAC Meeting dated 03/10/2020. 43. 7838/2020 1(a) 464th SEAC Meeting dated 03/10/2020. 44. 7857/2020 1(a) 464th SEAC Meeting dated 03/10/2020. 45. 7781/2020 1(a) 464th SEAC Meeting dated 03/10/2020. 46. 7848/2020 1(a) 464th SEAC Meeting dated 03/10/2020. 47. 7824/2020 1(a) 464th SEAC Meeting dated 03/10/2020. 48. 7827/2020 1(a) 464th SEAC Meeting dated 03/10/2020. 49. 7829/2020 1(a) 464th SEAC Meeting dated 03/10/2020. 50. 7820/2020 1(a) 464th SEAC Meeting dated 03/10/2020. 51. 7831/2020 1(a) 464th SEAC Meeting dated 03/10/2020. 52. 7823/2020 1(a) 464th SEAC Meeting dated 03/10/2020. 53. 7846/2020 1(a) 464th SEAC Meeting dated 03/10/2020. 54. 7853/2020 1(a) 464th SEAC Meeting dated 03/10/2020. 55. 7844/2020 1(a) 464th SEAC Meeting dated 03/10/2020. 56. 7849/2020 1(a) 464th SEAC Meeting dated 03/10/2020. 57. 7850/2020 1(a) 464th SEAC Meeting dated 03/10/2020. 58. 7851/2020 1(a) 464th SEAC Meeting dated 03/10/2020. 59. 7830/2020 1(a) 464th SEAC Meeting dated 03/10/2020. 60. 7847/2020 1(a) 464th SEAC Meeting dated 03/10/2020. 61. 7852/2020 1(a) 464th SEAC Meeting dated 03/10/2020. 62. 7854/2020 1(a) 464th SEAC Meeting dated 03/10/2020. 63. 7855/2020 5(f) 464th SEAC Meeting dated 03/10/2020. 64. 5763/2018 1(a) 464th SEAC Meeting dated 03/10/2020. 65. 5764/2018 1(a) 464th SEAC Meeting dated 03/10/2020. 66. 7858/2020 1(a) 464th SEAC Meeting dated 03/10/2020. 67. 6168/2019 1(a) 464th SEAC Meeting dated 03/10/2020. 68. 6749/2020 1(a) 464th SEAC Meeting dated 03/10/2020. 69. 6750/2020 1(a) 464th SEAC Meeting dated 03/10/2020. 70. 7861/2020 1(a) 464th SEAC Meeting dated 03/10/2020. 71. 7859/2020 1(a) 464th SEAC Meeting dated 03/10/2020. 72. 7862/2020 1(a) 464th SEAC Meeting dated 03/10/2020. 73. 7865/2020 5(f) 464th SEAC Meeting dated 03/10/2020. 74. 7427/2020 1(a) 464th SEAC Meeting dated 03/10/2020. 75. 7501/2020 1(a) 464th SEAC Meeting dated 03/10/2020. 76. 7608/2020 1(a) 464th SEAC Meeting dated 03/10/2020. 77. 7637/2020 1(a) 464th SEAC Meeting dated 03/10/2020. 78. 7652/2020 1(a) 464th SEAC Meeting dated 03/10/2020. 79. 7649/2020 1(a) 464th SEAC Meeting dated 03/10/2020. 80. 7495/2020 8(b) 461st SEAC Meeting dated 29/9/2020 81. 5789/2018 8(a) 457 SEAC meeting dated 18.09.20. 82. 5689/2018 8(a) 398 SEAC meeting dated 04-10-19. 83. 6090/ 2019 8(a) EC Transfer 84. 7883/2020 1(a) EC Transfer

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 3 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020

1. Case No. – 6621/2019 Prior Environmental Clearance for Limestone Mine (Opencast Fully Mechanized Method) in an area of 4.999 ha. for production capacity of 74,534 TPA at khasra no.2/1 at village Jeerabad, Tehsil - Gandhwani, Dist. Dhar M/s Satguru Cements Private Limited, 601/1, Airen Heights, Scheme No. 54, PU - 3, Oppo. C - 21 Mall, AB Road, Indore, MP, (1) This is a project pertaining to mining of Limestone mine in MLA of 4.99 ha. The

activity is mentioned at S.No. 1 (a) of the Schedule of EIA Notification 2006 as amended from time to time. The project is reported to be at a distance of more than 10 km from National Park /Sanctuary etc. thus it is not attracted by the general conditions and falls under category ‘B-1” by virtue of its location and mining lease area. The case was forwarded by SEIAA to SEAC for appraisal of EIA for environment clearance for the project. It was submitted that this is a proposed mine with production capacity of Limestone is 74,534 TPA.

(2) SEAC in its 462 SEAC meeting dtd 30.09.2020 has recommended the case with 33 special conditions for issuance of EC.

(3) It was noted that as per DFO .L.No. 4138, dtd. 07.08.2019, the National Park/Sanctuary is not located within 10 Km., radius from the mining site. Hence, the General Conditions are not attracted. There is no forest boundary within 250 m from mining site.

(4) It was noted that the water requirement is 21.0 KLD (8 KLD Dust Suppression +10 KLD Green Belt + 3.0 KLD Domestic purpose) which shall be met from Water tankers.

(5) The proposed plantation program was examined and it was found that total 9360 sapling shall be covered under plantation

(6) It was also noted that the Public Hearing was carried out on 29.08.2020 at nearby Mine Parisar Village- Jeerabad, Tehsil - Gandhwani, Dist. Dhar under Chairmanship of Upper Collector, Dhar. The major comments of applicants during public hearing are are water for irrigation, access on approach road, Controlled blasting, employment of local people, construction & maintenance of existing / approach road connecting the mine & main road, Plantation on road side, regular health check-up of mine workers & water sprinkling to suppress the dust emission.

PP/Consultant made a presentation on all aspects of the project and all concerned issues were discussed in detail After detailed discussions and perusal of recommendations of 462 SEAC meeting dtd 30.09.2020, it was decided to

85. 7884/2020 1(a) EC Transfer 86. 7885/2020 1(a) EC Transfer 87. 7886/2020 1(a) EC Transfer 88. 7787/2020 1(a) EC Transfer 89. 7888/2020 1(a) EC Transfer 90. 7889/2020 1(a) EC Transfer 91. 7354/2020 1(a) 631st SEIAA meeting dated 11.08.20 92. 4307/2015 1(a) EC Transfer 93. 7877/2020 1(a) EC Transfer

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 4 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020

accept the recommendation of SEAC for grant of prior EC to the project subject to the following specific conditions:

I. PP shall ensure to preserve thick greenery all around periphery of mining lease area and develop a green belt.

II. Before commencing any mining activity fencing shall be carried out all around the lease area. Proper watch and ward arrangements should be made with installation of signage at 4 corners of lease area to avoid any untoward incident involving public and animals by the PP.

III. Plantation programme as mentioned in EIA/EMP and presented during presentation in SEIAA & SEAC shall be followed in content and spirit.

IV. Total 9360 saplings of suitable tree species i.e. Neem, Pipal, Bargad, Mango, Amla, Amaltas, Drumstick etc. shall be planted by PP on mine lease boundary , Along the transportation road / in premises ,approach road and submit photographs of the plantation in SEIAA.PP shall also explore and identify the chunk of land in the area from revenue record to carry out plantation programme as proposed

V. All garland drains shall be connected to settling tanks through settling pits and settled water shall be used for dust suppression, green belt development. Regular de-silting of drains and pits should be carried out

VI. PP shall demarcate a barrier zone of 7.5 m as no mining zone in the periphery of mining lease area and develop a green belt. Three row plantation shall be carried out in the greenbelt area in current year with proper watering arrangement.

VII. The mining operation shall be restricted to above ground water table and in no case it should intersect the ground water table. In case of working below the ground water table approval of the Central Ground Water Board shall be obtained.

VIII. The over burden and waste will be stacked for five years and then simultaneously backfilled in the mined out area where plantation will be raised on it.

IX. No overburden will be dumped outside the mine lease area.

X. Regular air & water quality monitoring shall be carried out by PP before discharging it into the nearby agriculture fields from authorized laboratory in consultation with Regional Officer, MPPCB.

XI. PP shall ensure generation of employment opportunities to nearby Village on priority bases.

XII. Payments of wages to the workers shall be done in consonance with the provisions in the labour laws.

XIII. Proper infrastructure with shelter, drinking water, toilet and first-aid facilities shall be provided for the laborers. A provision should be made to construct a pakka rest shelter along with toilet and drinking water facility.

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 5 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020

XIV. PP should also carry out regular sprinkling of water in the mining lease area to arrest dust emission from mining activities affecting the nearby agriculture fields

XV. Mining shall be limited to the area as shown in surface plan and as per the approved mining scheme.

XVI. PP shall ensure to construct and maintain approach road from the mine site. Plantation will be carried out on both sides of the approach road. PP shall also ensure maintenance of existing pakka road in consultation with competent authority.

XVII. PP shall ensure proper water supply arrangements for plantation especially in summer season.

XVIII. PP shall ensure proper implementation of plantation, dust suppression, construction of approach road and maintenance of existing pakka road as part of Environmental Management Plan. Additional budget provision shall be made as part of EMP.

XIX. PP must ensure implementation of the following activities with separate budget provision of Rs. 2.20 Lakhs under CER as committed.

Providing infrastructure support to the village school- Fan, Solar light, boys and girls toilet,, boundary wall, drinking water facility at village Jeerabad (Rs. 0.90 lakh)

To developed grazing land at village as per OM of MoEF&CC dated 14.01.2016 with species like Stylo Hamata, Dinath, Siren, Subabul, Sewan Grass, Guner etc. (Rs. 0.20 lakh)

Provision of thermo and oxi-meters, sanitizers equipment, Mask etc. At Aganwadi and PHC of Jeerabad (Rs. 0.10 lakh)

Facilitation work for implementation of programme under Jal Jivan Mission - Contribution of fund or execution of plumbing network for implementation of Jal Jivan Scheme with to villagers houses in Jeerabad and other villages in consultation with the local administration. (Rs. 1.0 lakh)

PP shall ensure to contruct toilet with proper plumbing in the school of above village and contribute on behalf of village in Jal Jeewan Mission in consultation with Janpad Panchayat and PHED. PP shall give preference to develop/provide infrastructural facilities in schools or aganwadies of above villages The modification to the above activities can be made with the permission of the district administration and need based activity for the development of nearby villages shall be implemented by PP in consultation with the District Collector and Gram Panchayat

XX. PP should ensure to submit half yearly compliance report and CSR activity report with photographs of plantation in MP-SEIAA. If PP is failed to upload or submit two consecutive half yearly compliance reports of EC conditions to concerned authority (SEIAA and Regional Office, MoEF&CC,GoI,Bhopal) than prior environmental clearance issued to PP

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 6 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020

will automatically be treated as cancelled/ revoked as per OM No. 930/SEIAA/2019 dated 30.05.2019 issued by MPSEIAA.

Hence, Prior Environmental Clearance is granted for Limestone Mine (Opencast Fully Mechanized Method) in an area of 4.999 ha. for production capacity of 74,534 TPA at khasra no.2/1 at village Jeerabad, Tehsil - Gandhwani, Dist. Dhar for the lease period to M/s Satguru Cements Private Limited, 601/1, Airen Heights, Scheme No. 54, PU - 3, Oppo. C - 21 Mall, AB Road, Indore, MP

2. Case No. – 6624/2019 Prior Environmental Clearance for Limestone Mine (Opencast Fully Mechanized Method) in an area of 4.50 ha. for production capacity of 20,288 TPA at Khasra No. 26/1 Part at Village - Badiya, Tehsil - Gandhwani, Dist. Dhar (MP) by M/s Satguru Cements Private Limited, 601/1, Airen Heights, Scheme No. 54, PU - 3, Oppo. C - 21 Mall, AB Road, Indore, MP,

(1) This is a project pertaining to mining of Limestone mine in MLA of 4.50 ha. The activity is mentioned at S.No. 1 (a) of the Schedule of EIA Notification 2006 as amended from time to time. The project is reported to be at a distance of more than 10 km from National Park /Sanctuary etc. thus it is not attracted by the general conditions and falls under category ‘B-1” by virtue of its location and mining lease area. The case was forwarded by SEIAA to SEAC for appraisal of EIA for environment clearance for the project. It was submitted that this is a proposed mine with production capacity of Limestone is 20,288 TPA.

(2) SEAC in its 462 SEAC meeting dtd 30.09.2020 has recommended the case with 33 special conditions for issuance of EC.

(3) It was noted that as per DFO .L.No. 4140, dtd. 07.08.2019, the National Park/Sanctuary is not located within 10 Km., radius from the mining site. Hence, the General Conditions are not attracted. There is no forest boundary within 250 m from mining site.

(4) It was noted that the water requirement is 16.0 KLD (5 KLD Dust Suppression +10 KLD Green Belt + 1.0 KLD Domestic purpose) which shall be met from Water tankers.

(5) The proposed plantation program was examined and it was found that total 5700 sapling shall be covered under plantation.

(6) It was also noted that the Public Hearing was carried out on 05.09.2020 at nearby Mine Parisar Village- Badiya, Tehsil - Gandhwani, Dist. Dhar under Chairmanship of Upper Collector, Dhar. The major comments of applicants during public hearing are are water for irrigation, access on approach road, Controlled blasting, employment of local people, construction & maintenance of existing / approach road connecting the mine & main road, Plantation on road side, regular health check-up of mine workers & water sprinkling to suppress the dust emission.

PP/Consultant made a presentation on all aspects of the project and all concerned issues were discussed in detail After detailed discussions and perusal of recommendations of 462 SEAC meeting dtd 30.09.2020, it was decided to accept the recommendation of SEAC for grant of prior EC to the project subject to the following specific conditions:

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 7 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020

I. PP shall ensure to preserve thick greenery all around periphery of mining lease area and develop a green belt.

II. Before commencing any mining activity fencing shall be carried out all around the lease area. Proper watch and ward arrangements should be made with installation of signage at 4 corners of lease area to avoid any untoward incident involving public and animals by the PP.

III. Plantation programme as mentioned in EIA/EMP and presented during presentation in SEIAA & SEAC shall be followed in content and spirit.

IV. Total 5700 saplings of suitable tree species i.e. Neem, Pipal, Bargad, Mango, Amla, Amaltas, Drumstick etc. shall be planted by PP on mine lease boundary , Along the transportation road / in premises ,approach road and submit photographs of the plantation in SEIAA.PP shall also explore and identify the chunk of land in the area from revenue record to carry out plantation programme as proposed

V. All garland drains shall be connected to settling tanks through settling pits and settled water shall be used for dust suppression, green belt development. Regular de-silting of drains and pits should be carried out

VI. PP shall demarcate a barrier zone of 7.5 m as no mining zone in the periphery of mining lease area and develop a green belt. Three row plantation shall be carried out in the greenbelt area in current year with proper watering arrangement.

VII. The mining operation shall be restricted to above ground water table and in no case it should intersect the ground water table. In case of working below the ground water table approval of the Central Ground Water Board shall be obtained.

VIII. The over burden and waste will be stacked for five years and then simultaneously backfilled in the mined out area where plantation will be raised on it.

IX. No overburden will be dumped outside the mine lease area. X. Regular air & water quality monitoring shall be carried out by PP before

discharging it into the nearby agriculture fields from authorized laboratory in consultation with Regional Officer, MPPCB.

XI. PP shall ensure generation of employment opportunities to nearby Village on priority bases.

XII. Payments of wages to the workers shall be done in consonance with the provisions in the labour laws.

XIII. Proper infrastructure with shelter, drinking water, toilet and first-aid facilities shall be provided for the laborers. A provision should be made to construct a pakka rest shelter along with toilet and drinking water facility.

XIV. PP should also carry out regular sprinkling of water in the mining lease area to arrest dust emission from mining activities affecting the nearby agriculture fields

XV. Mining shall be limited to the area as shown in surface plan and as per the approved mining scheme.

XVI. PP shall ensure to construct and maintain approach road from the mine site. Plantation will be carried out on both sides of the approach road. PP shall also ensure maintenance of existing pakka road in consultation with competent authority.

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 8 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020

XVII. PP shall ensure proper water supply arrangements for plantation especially in summer season.

XVIII. PP shall ensure proper implementation of plantation, dust suppression, construction of approach road and maintenance of existing pakka road as part of Environmental Management Plan. Additional budget provision shall be made as part of EMP.

XIX. PP must ensure implementation of the following activities with separate budget provision of Rs. 1.90 Lakhs under CER as committed.

Providing infrastructure support to the village school- Fan, Solar light, boys and girls toilet,, boundary wall, drinking water facility at village Badiya (Rs. 0.60 lakh)

To developed grazing land at village as per OM of MoEF&CC dated 14.01.2016 with species like Stylo Hamata, Dinath, Siren, Subabul, Sewan Grass, Guner etc. (Rs. 0.20 lakh)

Provision of thermo and oxi-meters, sanitizers equipment, Mask etc. At Aganwadi and PHC of Badiya (Rs. 0.10 lakh)

Facilitation work for implementation of programme under Jal Jivan Mission - Contribution of fund or execution of plumbing network for implementation of Jal Jivan Scheme with to villagers houses in Badiya and other villages in consultation with the local administration. (Rs. 1.0 lakh)

PP shall ensure to contruct toilet with proper plumbing in the school of above village and contribute on behalf of village in Jal Jeewan Mission in consultation with Janpad Panchayat and PHED. PP shall give preference to develop/provide infrastructural facilities in schools or aganwadies of above villages The modification to the above activities can be made with the permission of the district administration and need based activity for the development of nearby villages shall be implemented by PP in consultation with the District Collector and Gram Panchayat

XX. PP should ensure to submit half yearly compliance report and CSR activity report with photographs of plantation in MP-SEIAA. If PP is failed to upload or submit two consecutive half yearly compliance reports of EC conditions to concerned authority (SEIAA and Regional Office, MoEF&CC,GoI,Bhopal) than prior environmental clearance issued to PP will automatically be treated as cancelled/ revoked as per OM No. 930/SEIAA/2019 dated 30.05.2019 issued by MPSEIAA.

Hence, Prior Environmental Clearance is granted for Limestone Mine (Opencast Fully Mechanized Method) in an area of 4.50 ha. for production capacity of 20,288 TPA at Khasra No. 26/1 Part at Village - Badiya, Tehsil - Gandhwani, Dist. Dhar (MP) for the lease period to M/s Satguru Cements Private Limited, 601/1, Airen Heights, Scheme No. 54, PU - 3, Oppo. C - 21 Mall, AB Road, Indore, MP

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 9 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020 3. Case No. – 6627/2019 Prior Environment Clearance for Limestone Mine (Opencast

Fully Mechanized Method) in an area of 21.080 ha. for production capacity of 1,93,150 TPA at khasra no. 9/1, 10, 13, 33/1, 33/2, 33/3, 34, 35, 37, 128, 134 at Village - Jeerabad, Tehsil - Gandhwani, Dist. Dhar (MP) by M/s Satguru Cements Private Limited, 601/1, Airen Heights, Scheme No. 54, PU - 3, Oppo. C - 21 Mall, AB Road, Indore, MP,.

(1) This is a project pertaining to mining of Limestone mine in MLA of 21.080 ha. The activity is mentioned at S.No. 1 (a) of the Schedule of EIA Notification 2006 as amended from time to time. The project is reported to be at a distance of more than 10 km from National Park /Sanctuary etc. thus it is not attracted by the general conditions and falls under category ‘B-1” by virtue of its location and mining lease area. The case was forwarded by SEIAA to SEAC for appraisal of EIA for environment clearance for the project. It was submitted that this is a proposed mine with production capacity of Limestone is 1,93,150 TPA.

(2) SEAC in its 462 SEAC meeting dtd 30.09.2020 has recommended the case with 33 special conditions for issuance of EC.

(3) It was noted that as per DFO .L.No. 4148, dtd. 07.08.2019, the National Park/Sanctuary is not located within 10 Km., radius from the mining site. Hence, the General Conditions are not attracted. There is no forest boundary within 250 m from mining site.

(4) It was noted that the water requirement is 20 KLD (4 KLD Dust Suppression +10 KLD Green Belt + 1.0 KLD Domestic purpose + 5 KLD for Drilling ) which shall be met from Water tankers.

(5) The proposed plantation program was examined and it was found that total 25250 sapling shall be covered under plantation.

(6) It was also noted that the Public Hearing was carried out on 29.08.2020 at nearby Mine Parisar Village- Jeerabad, Tehsil - Gandhwani, Dist. Dhar under Chairmanship of Upper Collector, Dhar. The major comments of applicants during public hearing are are water for irrigation, access on approach road, Controlled blasting, employment of local people, construction & maintenance of existing / approach road connecting the mine & main road, Plantation on road side, regular health check-up of mine workers & water sprinkling to suppress the dust emission.

PP/Consultant made a presentation on all aspects of the project and all concerned issues were discussed in detail After detailed discussions and perusal of recommendations of 462 SEAC meeting dtd 30.09.2020, it was decided to accept the recommendation of SEAC for grant of prior EC to the project subject to the following specific conditions:

I. PP shall ensure to preserve thick greenery all around periphery of mining lease area and develop a green belt.

II. Before commencing any mining activity fencing shall be carried out all around the lease area. Proper watch and ward arrangements should be made with installation of signage at 4 corners of lease area to avoid any untoward incident involving public and animals by the PP.

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 10 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020

III. Plantation programme as mentioned in EIA/EMP and presented during presentation in SEIAA & SEAC shall be followed in content and spirit.

IV. Total 25250 saplings of suitable tree species i.e. Neem, Pipal, Bargad, Mango, Amla, Amaltas, Drumstick etc. shall be planted by PP on mine lease boundary , Along the transportation road / in premises ,approach road and submit photographs of the plantation in SEIAA.PP shall also explore and identify the chunk of land in the area from revenue record to carry out plantation programme as proposed

V. All garland drains shall be connected to settling tanks through settling pits and settled water shall be used for dust suppression, green belt development. Regular de-silting of drains and pits should be carried out

VI. PP shall demarcate a barrier zone of 7.5 m as no mining zone in the periphery of mining lease area and develop a green belt. Three row plantation shall be carried out in the greenbelt area in current year with proper watering arrangement.

VII. The mining operation shall be restricted to above ground water table and in no case it should intersect the ground water table. In case of working below the ground water table approval of the Central Ground Water Board shall be obtained.

VIII. The over burden and waste will be stacked for five years and then simultaneously backfilled in the mined out area where plantation will be raised on it.

IX. No overburden will be dumped outside the mine lease area.

X. Regular air & water quality monitoring shall be carried out by PP before discharging it into the nearby agriculture fields from authorized laboratory in consultation with Regional Officer, MPPCB.

XI. PP shall ensure generation of employment opportunities to nearby Village on priority bases.

XII. Payments of wages to the workers shall be done in consonance with the provisions in the labour laws.

XIII. Proper infrastructure with shelter, drinking water, toilet and first-aid facilities shall be provided for the laborers. A provision should be made to construct a pakka rest shelter along with toilet and drinking water facility.

XIV. PP should also carry out regular sprinkling of water in the mining lease area to arrest dust emission from mining activities affecting the nearby agriculture fields

XV. Mining shall be limited to the area as shown in surface plan and as per the approved mining scheme.

XVI. PP shall ensure to construct and maintain approach road from the mine site. Plantation will be carried out on both sides of the approach road. PP shall also ensure maintenance of existing pakka road in consultation with competent authority.

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 11 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020

XVII. PP shall ensure proper water supply arrangements for plantation especially in summer season.

XVIII. PP shall ensure proper implementation of plantation, dust suppression, construction of approach road and maintenance of existing pakka road as part of Environmental Management Plan. Additional budget provision shall be made as part of EMP.

XIX. PP must ensure implementation of the following activities with separate budget provision of Rs. 2.50 Lakhs under CER as committed.

Providing infrastructure support to the village school- Fan, Solar light, boys and girls toilet,, boundary wall, drinking water facility at village Jeerabad (Rs1.10 lakh)

To developed grazing land at village as per OM of MoEF&CC dated 14.01.2016 with species like Stylo Hamata, Dinath, Siren, Subabul, Sewan Grass, Guner etc. (Rs. 0.20 lakh)

Provision of thermo and oxi-meters, sanitizers equipment, Mask etc. At Sub-tehsil office, Govt. Middle School of Jeerabad (Rs. 0.20 lakh)

Facilitation work for implementation of programme under Jal Jivan Mission - Contribution of fund or execution of plumbing network for implementation of Jal Jivan Scheme with to villagers houses in Jeerabad and other villages in consultation with the local administration. (Rs. 1.0 lakh)

PP shall ensure to contruct toilet with proper plumbing in the school of above village and contribute on behalf of village in Jal Jeewan Mission in consultation with Janpad Panchayat and PHED. PP shall give preference to develop/provide infrastructural facilities in schools or aganwadies of above villages The modification to the above activities can be made with the permission of the district administration and need based activity for the development of nearby villages shall be implemented by PP in consultation with the District Collector and Gram Panchayat

XX. PP should ensure to submit half yearly compliance report and CSR activity report with photographs of plantation in MP-SEIAA. If PP is failed to upload or submit two consecutive half yearly compliance reports of EC conditions to concerned authority (SEIAA and Regional Office, MoEF&CC,GoI,Bhopal) than prior environmental clearance issued to PP will automatically be treated as cancelled/ revoked as per OM No. 930/SEIAA/2019 dated 30.05.2019 issued by MPSEIAA.

Hence, Prior Environmental Clearance is granted for Limestone Mine (Opencast Fully Mechanized Method) in an area of 21.080 ha. for production capacity of 1,93,150 TPA at khasra no. 9/1, 10, 13, 33/1, 33/2, 33/3, 34, 35, 37, 128, 134 at Village - Jeerabad, Tehsil - Gandhwani, Dist. Dhar (MP) for the lease period to M/s Satguru Cements Private Limited, 601/1, Airen Heights, Scheme No. 54, PU - 3, Oppo. C - 21 Mall, AB Road, Indore, MP

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 12 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020 4. Case No. – 6628/2019 Prior Environment Clearance for Limestone Mine (Opencast

Fully Mechanized Method) in an area of 4.999 ha. for production capacity of 13,116 TPA at Khasra No. 176/1 (Part) at Village - Badiya, Tehsil - Gandhwani, Dist. Dhar by M/s Satguru Cements Private Limited, 601/1, Airen Heights, Scheme No. 54, PU - 3, Oppo. C - 21 Mall, AB Road, Indore, MP,

(1) This is a project pertaining to mining of Limestone mine in MLA of 4.999 ha. The activity is mentioned at S.No. 1 (a) of the Schedule of EIA Notification 2006 as amended from time to time. The project is reported to be at a distance of more than 10 km from National Park /Sanctuary etc. thus it is not attracted by the general conditions and falls under category ‘B-1” by virtue of its location and mining lease area. The case was forwarded by SEIAA to SEAC for appraisal of EIA for environment clearance for the project. It was submitted that this is a proposed mine with production capacity of Limestone is 13,116 TPA.

(2) SEAC in its 462 SEAC meeting dtd 30.09.2020 has recommended the case with 33 special conditions for issuance of EC.

(3) It was noted that as per DFO .L.No. 4139, dtd. 07.08.2019, the National Park/Sanctuary is not located within 10 Km., radius from the mining site. Hence, the General Conditions are not attracted. There is no forest boundary within 250 m from mining site.

(4) It was noted that the water requirement is 19.5 KLD (9 KLD Dust Suppression +10 KLD Green Belt + 0.5 KLD Domestic purpose) which shall be met from Water tankers.

(5) The proposed plantation program was examined and it was found that total 10240 saplings shall be covered under plantation.

(6) It was also noted that the Public Hearing was carried out on 05.09.2020 at Mine Parisar Village- Badiya, Tehsil - Gandhwani, Dist. Dhar under Chairmanship of Upper Collector, Dhar. The major comments of applicants during public hearing are are water for irrigation, access on approach road, Controlled blasting, employment of local people, construction & maintenance of existing / approach road connecting the mine & main road, Plantation on road side, regular health check-up of mine workers & water sprinkling to suppress the dust emission.

PP/Consultant made a presentation on all aspects of the project and all concerned issues were discussed in detail After detailed discussions and perusal of recommendations of 462 SEAC meeting dtd 30.09.2020, it was decided to accept the recommendation of SEAC for grant of prior EC to the project subject to the following specific conditions:

I. PP shall ensure to preserve thick greenery all around periphery of mining lease area and develop a green belt.

II. Before commencing any mining activity fencing shall be carried out all around the lease area. Proper watch and ward arrangements should be made with installation of signage at 4 corners of lease area to avoid any untoward incident involving public and animals by the PP.

III. Plantation programme as mentioned in EIA/EMP and presented during presentation in SEIAA & SEAC shall be followed in content and spirit.

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 13 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020

IV. Total 10240 saplings of suitable tree species i.e. Neem, Pipal, Bargad, Mango, Amla, Amaltas, Drumstick etc. shall be planted by PP on mine lease boundary , Along the transportation road / in premises ,approach road and submit photographs of the plantation in SEIAA.PP shall also explore and identify the chunk of land in the area from revenue record to carry out plantation programme as proposed

V. All garland drains shall be connected to settling tanks through settling pits and settled water shall be used for dust suppression, green belt development. Regular de-silting of drains and pits should be carried out

VI. PP shall demarcate a barrier zone of 7.5 m as no mining zone in the periphery of mining lease area and develop a green belt. Three row plantations shall be carried out in the greenbelt area in current year with proper watering arrangement.

VII. The mining operation shall be restricted to above ground water table and in no case it should intersect the ground water table. In case of working below the ground water table approval of the Central Ground Water Board shall be obtained.

VIII. The over burden and waste will be stacked for five years and then simultaneously backfilled in the mined out area where plantation will be raised on it.

IX. No overburden will be dumped outside the mine lease area.

X. Regular air & water quality monitoring shall be carried out by PP before discharging it into the nearby agriculture fields from authorized laboratory in consultation with Regional Officer, MPPCB.

XI. PP shall ensure generation of employment opportunities to nearby Village on priority bases.

XII. Payments of wages to the workers shall be done in consonance with the provisions in the labour laws.

XIII. Proper infrastructure with shelter, drinking water, toilet and first-aid facilities shall be provided for the laborers. A provision should be made to construct a pakka rest shelter along with toilet and drinking water facility.

XIV. PP should also carry out regular sprinkling of water in the mining lease area to arrest dust emission from mining activities affecting the nearby agriculture fields

XV. Mining shall be limited to the area as shown in surface plan and as per the approved mining scheme.

XVI. PP shall ensure to construct and maintain approach road from the mine site. Plantation will be carried out on both sides of the approach road. PP shall also ensure maintenance of existing pakka road in consultation with competent authority.

XVII. PP shall ensure proper water supply arrangements for plantation especially in summer season.

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 14 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020

XVIII. PP shall ensure proper implementation of plantation, dust suppression, construction of approach road and maintenance of existing pakka road as part of Environmental Management Plan. Additional budget provision shall be made as part of EMP.

XIX. PP must ensure implementation of the following activities with separate budget provision of Rs. 1.90 Lakhs under CER as committed.

Providing infrastructure support to the village school- Fan, Solar light, boys and girls toilet, drinking water facility at village Badiya (Rs 0.70 lakh)

To developed grazing land at village as per OM of MoEF&CC dated 14.01.2016 with species like Stylo Hamata, Dinath, Siren, Subabul, Sewan Grass, Guner etc. (Rs. 0.20 lakh)

Provision of thermo and oxi-meters, sanitizers equipment, Mask etc. At Aganwadi and PHC of Badiya (Rs. 0.10 lakh)

Facilitation work for implementation of programme under Jal Jivan Mission - Contribution of fund or execution of plumbing network for implementation of Jal Jivan Scheme with to villagers houses in Badiya and other villages in consultation with the local administration. (Rs. 1.0 lakh)

PP shall ensure to contruct toilet with proper plumbing in the school of above village and contribute on behalf of village in Jal Jeewan Mission in consultation with Janpad Panchayat and PHED. PP shall give preference to develop/provide infrastructural facilities in schools or aganwadies of above villages The modification to the above activities can be made with the permission of the district administration and need based activity for the development of nearby villages shall be implemented by PP in consultation with the District Collector and Gram Panchayat

XX. PP should ensure to submit half yearly compliance report and CSR activity report with photographs of plantation in MP-SEIAA. If PP is failed to upload or submit two consecutive half yearly compliance reports of EC conditions to concerned authority (SEIAA and Regional Office, MoEF&CC,GoI,Bhopal) than prior environmental clearance issued to PP will automatically be treated as cancelled/ revoked as per OM No. 930/SEIAA/2019 dated 30.05.2019 issued by MPSEIAA.

Hence, Prior Environmental Clearance is granted for Limestone Mine (Opencast Fully Mechanized Method) in an area of 4.999 ha. for production capacity of 13,116 TPA at Khasra No. 176/1 (Part) at Village - Badiya, Tehsil - Gandhwani, Dist. Dhar for the lease period to M/s Satguru Cements Private Limited, 601/1, Airen Heights, Scheme No. 54, PU - 3, Oppo. C - 21 Mall, AB Road, Indore, MP

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 15 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020 5. Case No. – 6626/2019 Prior Environment Clearance for Limestone Mine (Opencast

Fully Mechanized Method) in an area of 38.024 ha. for production capacity of 2,12,402 TPA at khasra no. 170, 172, 174/2, 199/1, 305/1, 307, 308/1, 309/1, 318, 320 & 322 at Village - Dhanora, Tehsil - Gandhwani, Dist. Dhar (MP) by M/s Satguru Cements Private Limited, 601/1, Airen Heights, Scheme No. 54, PU - 3, Oppo. C - 21 Mall, AB Road, Indore, MP, (1) This is a project pertaining to mining of Limestone mine in MLA of 38.024 ha.

The activity is mentioned at S.No. 1 (a) of the Schedule of EIA Notification 2006 as amended from time to time. The project is reported to be at a distance of more than 10 km from National Park /Sanctuary etc. thus it is not attracted by the general conditions and falls under category ‘B-1” by virtue of its location and mining lease area. The case was forwarded by SEIAA to SEAC for appraisal of EIA for environment clearance for the project. It was submitted that this is a proposed mine with production capacity of Limestone is 2,12,402 TPA.

(2) SEAC in its 462 SEAC meeting dtd 30.09.2020 has recommended the case with 33 special conditions for issuance of EC.

(3) It was noted that as per DFO .L.No. 4146, dtd. 07.08.2019, the National Park/Sanctuary is not located within 10 Km., radius from the mining site. Hence, the General Conditions are not attracted. There is no forest boundary within 250 m from mining site.

(4) It was noted that the water requirement is 48 KLD (32 KLD Dust Suppression +10 KLD Green Belt + 1.0 KLD Domestic purpose + 5KLD Drilling) which shall be met from Water tankers.

(5) The proposed plantation program was examined and it was found that total 41640 sapling shall be covered under plantation.

(6) It was also noted that the Public Hearing was carried out on 29.08.2020 at nearby Mine Parisar Village- Dhanora, Tehsil - Gandhwani, Dist. Dhar under Chairmanship of Upper Collector, Dhar. The major comments of applicants during public hearing are are water for irrigation, access on approach road, Controlled blasting, employment of local people, construction & maintenance of existing / approach road connecting the mine & main road, Plantation on road side, regular health check-up of mine workers & water sprinkling to suppress the dust emission.

PP/Consultant made a presentation on all aspects of the project and all concerned issues were discussed in detail After detailed discussions and perusal of recommendations of 462 SEAC meeting dtd 30.09.2020, it was decided to accept the recommendation of SEAC for grant of prior EC to the project subject to the following specific conditions:

I. PP shall ensure to preserve thick greenery all around periphery of mining lease area and develop a green belt.

II. Before commencing any mining activity fencing shall be carried out all around the lease area. Proper watch and ward arrangements should be made with installation of signage at 4 corners of lease area to avoid any untoward incident involving public and animals by the PP.

III. Plantation programme as mentioned in EIA/EMP and presented during presentation in SEIAA & SEAC shall be followed in content and spirit.

IV. PP will take permission from competent authority for cutting tree as 94 trees exist in the lease area as intimated by PP and additional 10 times

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 16 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020

shall be planted as compensatory plantation with inventory of trees as recommended by SEAC.

V. Total 41640 saplings of suitable tree species i.e. Neem, Pipal, Bargad, Mango, Amla, Amaltas, Drumstick etc. shall be planted by PP on mine lease boundary , Along the transportation road / in premises ,approach road and submit photographs of the plantation in SEIAA.PP shall also explore and identify the chunk of land in the area from revenue record to carry out plantation programme as proposed

VI. All garland drains shall be connected to settling tanks through settling pits and settled water shall be used for dust suppression, green belt development. Regular de-silting of drains and pits should be carried out

VII. PP shall demarcate a barrier zone of 7.5 m as no mining zone in the periphery of mining lease area and develop a green belt. Three row plantation shall be carried out in the greenbelt area in current year with proper watering arrangement.

VIII. The mining operation shall be restricted to above ground water table and in no case it should intersect the ground water table. In case of working below the ground water table approval of the Central Ground Water Board shall be obtained.

IX. The over burden and waste will be stacked for five years and then simultaneously backfilled in the mined out area where plantation will be raised on it.

X. No overburden will be dumped outside the mine lease area.

XI. Regular air & water quality monitoring shall be carried out by PP before discharging it into the nearby agriculture fields from authorized laboratory in consultation with Regional Officer, MPPCB.

XII. PP shall ensure generation of employment opportunities to nearby Village on priority bases.

XIII. Payments of wages to the workers shall be done in consonance with the provisions in the labour laws.

XIV. Proper infrastructure with shelter, drinking water, toilet and first-aid facilities shall be provided for the laborers. A provision should be made to construct a pakka rest shelter along with toilet and drinking water facility.

XV. PP should also carry out regular sprinkling of water in the mining lease area to arrest dust emission from mining activities affecting the nearby agriculture fields

XVI. Mining shall be limited to the area as shown in surface plan and as per the approved mining scheme.

XVII. PP shall ensure to construct and maintain approach road from the mine site. Plantation will be carried out on both sides of the approach road. PP shall also ensure maintenance of existing pakka road in consultation with competent authority.

XVIII. PP shall ensure proper water supply arrangements for plantation especially in summer season.

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 17 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020

XIX. PP shall ensure proper implementation of plantation, dust suppression, construction of approach road and maintenance of existing pakka road as part of Environmental Management Plan. Additional budget provision shall be made as part of EMP.

XX. PP must ensure implementation of the following activities with separate budget provision of Rs. 2.50 Lakhs under CER as committed.

Providing infrastructure support to the village school- Fan, Solar light, boys and girls toilet, boundary wall, drinking water facility at village Dhanora (Rs 1.20 lakh)

To developed grazing land at village as per OM of MoEF&CC dated 14.01.2016 with species like Stylo Hamata, Dinath, Siren, Subabul, Sewan Grass, Guner etc. (Rs. 0.20 lakh)

Provision of thermo and oxi-meters, sanitizers equipment, Mask etc. At Aganwadi and PHC of Dhanora (Rs. 0.10 lakh)

Facilitation work for implementation of programme under Jal Jivan Mission - Contribution of fund or execution of plumbing network for implementation of Jal Jivan Scheme with to villagers houses in Dhanora and other villages in consultation with the local administration. (Rs. 1.0 lakh)

PP shall ensure to contruct toilet with proper plumbing in the school of above village and contribute on behalf of village in Jal Jeewan Mission in consultation with Janpad Panchayat and PHED. PP shall give preference to develop/provide infrastructural facilities in schools or aganwadies of above villages The modification to the above activities can be made with the permission of the district administration and need based activity for the development of nearby villages shall be implemented by PP in consultation with the District Collector and Gram Panchayat

XXI. PP should ensure to submit half yearly compliance report and CSR activity report with photographs of plantation in MP-SEIAA. If PP is failed to upload or submit two consecutive half yearly compliance reports of EC conditions to concerned authority (SEIAA and Regional Office, MoEF&CC,GoI,Bhopal) than prior environmental clearance issued to PP will automatically be treated as cancelled/ revoked as per OM No. 930/SEIAA/2019 dated 30.05.2019 issued by MPSEIAA.

Hence, Prior Environmental Clearance is granted for Limestone Mine (Opencast Fully Mechanized Method) in an area of 38.024 ha. for production capacity of 2,12,402 TPA at khasra no. 170, 172, 174/2, 199/1, 305/1, 307, 308/1, 309/1, 318, 320 & 322 at Village - Dhanora, Tehsil - Gandhwani, Dist. Dhar (MP) for the lease period to M/s Satguru Cements Private Limited, 601/1, Airen Heights, Scheme No. 54, PU - 3, Oppo. C - 21 Mall, AB Road, Indore, MP

6. Case No. 6697/2019 Prior Environment Clearance for Limestone Mine (Opencast Fully Mechanized Method) in an area of 13.150 ha. for production capacity of 1,90,165 TPA at khasra no. 326, 366, 404, 410/1, 416, 417, 421 at Village - Rodada, Tehsil - Gandhwani, Dist. Dhar (MP) by M/s Satguru Cements Private Limited, 601/1, Airen Heights, Scheme No. 54, PU - 3, Oppo. C - 21 Mall, AB Road, Indore

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 18 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020

(1) This is a project pertaining to mining of Limestone mine in MLA of 13.0150 ha. The activity is mentioned at S.No. 1 (a) of the Schedule of EIA Notification 2006 as amended from time to time. The project is reported to be at a distance of more than 10 km from National Park /Sanctuary etc. thus it is not attracted by the general conditions and falls under category ‘B-1” by virtue of its location and mining lease area. The case was forwarded by SEIAA to SEAC for appraisal of EIA for environment clearance for the project. It was submitted that this is a proposed mine with production capacity of Limestone is 1,90,165 TPA.

(2) SEAC in its 462 SEAC meeting dtd 30.09.2020 has recommended the case with 33 special conditions for issuance of EC.

(3) It was noted that as per DFO .L.No. 4149, dtd. 07.08.2019, the National Park/Sanctuary is not located within 10 Km., radius from the mining site. Hence, the General Conditions are not attracted. There is no forest boundary within 250 m from mining site.

(4) It was noted that the water requirement is 40 KLD (29 KLD Dust Suppression +10 KLD Green Belt + 1.0 KLD Domestic purpose) which shall be met from Water tankers.

(5) The proposed plantation program was examined and it was found that total 23440 saplings shall be covered under plantation.

(6) It was also noted that the Public Hearing was carried out on 29.08.2020 at nearby Mine Parisar Village- Rodada, Tehsil - Gandhwani, Dist. Dhar under Chairmanship of Upper Collector, Dhar. The major comments of applicants during public hearing are are water for irrigation, access on approach road, Controlled blasting, employment of local people, construction & maintenance of existing / approach road connecting the mine & main road, Plantation on road side, regular health check-up of mine workers & water sprinkling to suppress the dust emission.

PP/Consultant made a presentation on all aspects of the project and all concerned issues were discussed in detail After detailed discussions and perusal of recommendations of 462 SEAC meeting dtd 30.09.2020, it was decided to accept the recommendation of SEAC for grant of prior EC to the project subject to the following specific conditions:

I. PP shall ensure to preserve thick greenery all around periphery of mining lease area and develop a green belt.

II. Before commencing any mining activity fencing shall be carried out all around the lease area. Proper watch and ward arrangements should be made with installation of signage at 4 corners of lease area to avoid any untoward incident involving public and animals by the PP.

III. Plantation programme as mentioned in EIA/EMP and presented during presentation in SEIAA & SEAC shall be followed in content and spirit.

IV. PP will take permission from competent authority for cutting tree as 124 trees exist in the lease area as intimated by PP and additional 10 times shall be planted as compensatory plantation with inventory of trees as recommended by SEAC.

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 19 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020

V. Total 23440 saplings of suitable tree species i.e. Neem, Pipal, Bargad, Mango, Amla, Amaltas, Drumstick etc. shall be planted by PP on mine lease boundary , Along the transportation road / in premises ,approach road and submit photographs of the plantation in SEIAA.PP shall also explore and identify the chunk of land in the area from revenue record to carry out plantation programme as proposed

VI. All garland drains shall be connected to settling tanks through settling pits and settled water shall be used for dust suppression, green belt development. Regular de-silting of drains and pits should be carried out

VII. PP shall demarcate a barrier zone of 7.5 m as no mining zone in the periphery of mining lease area and develop a green belt. Three row plantation shall be carried out in the greenbelt area in current year with proper watering arrangement.

VIII. The mining operation shall be restricted to above ground water table and in no case it should intersect the ground water table. In case of working below the ground water table approval of the Central Ground Water Board shall be obtained.

IX. The over burden and waste will be stacked for five years and then simultaneously backfilled in the mined out area where plantation will be raised on it.

X. No overburden will be dumped outside the mine lease area.

XI. Regular air & water quality monitoring shall be carried out by PP before discharging it into the nearby agriculture fields from authorized laboratory in consultation with Regional Officer, MPPCB.

XII. PP shall ensure generation of employment opportunities to nearby Village on priority bases.

XIII. Payments of wages to the workers shall be done in consonance with the provisions in the labour laws.

XIV. Proper infrastructure with shelter, drinking water, toilet and first-aid facilities shall be provided for the laborers. A provision should be made to construct a pakka rest shelter along with toilet and drinking water facility.

XV. PP should also carry out regular sprinkling of water in the mining lease area to arrest dust emission from mining activities affecting the nearby agriculture fields

XVI. Mining shall be limited to the area as shown in surface plan and as per the approved mining scheme.

XVII. PP shall ensure to construct and maintain approach road from the mine site. Plantation will be carried out on both sides of the approach road. PP shall also ensure maintenance of existing pakka road in consultation with competent authority.

XVIII. PP shall ensure proper water supply arrangements for plantation especially in summer season.

XIX. PP shall ensure proper implementation of plantation, dust suppression, construction of approach road and maintenance of existing pakka road as

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 20 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020

part of Environmental Management Plan. Additional budget provision shall be made as part of EMP.

XX. PP must ensure implementation of the following activities with separate budget provision of Rs. 2.50 Lakhs under CER as committed.

Providing infrastructure support to the village school- Fan, Solar light, boys and girls toilet, boundary wall, drinking water facility at village Rodada (Rs 1.30 lakh)

To developed grazing land at village as per OM of MoEF&CC dated 14.01.2016 with species like Stylo Hamata, Dinath, Siren, Subabul, Sewan Grass, Guner etc. (Rs. 0.20 lakh)

Provision of thermo and oxi-meters, sanitizers equipment, Mask etc. At Aganwadi and PHC of Rodada (Rs. 0.10 lakh)

Facilitation work for implementation of programme under Jal Jivan Mission - Contribution of fund or execution of plumbing network for implementation of Jal Jivan Scheme with to villagers houses in Rodada and other villages in consultation with the local administration. (Rs. 1.0 lakh)

PP shall ensure to contruct toilet with proper plumbing in the school of above village and contribute on behalf of village in Jal Jeewan Mission in consultation with Janpad Panchayat and PHED. PP shall give preference to develop/provide infrastructural facilities in schools or aganwadies of above villages The modification to the above activities can be made with the permission of the district administration and need based activity for the development of nearby villages shall be implemented by PP in consultation with the District Collector and Gram Panchayat

XXI. PP should ensure to submit half yearly compliance report and CSR activity report with photographs of plantation in MP-SEIAA. If PP is failed to upload or submit two consecutive half yearly compliance reports of EC conditions to concerned authority (SEIAA and Regional Office, MoEF&CC,GoI,Bhopal) than prior environmental clearance issued to PP will automatically be treated as cancelled/ revoked as per OM No. 930/SEIAA/2019 dated 30.05.2019 issued by MPSEIAA.

Hence, Prior Environmental Clearance is granted for Limestone Mine (Opencast Fully Mechanized Method) in an area of 13.150 ha. for production capacity of 1,90,165 TPA at khasra no. 326, 366, 404, 410/1, 416, 417, 421 at Village - Rodada, Tehsil - Gandhwani, Dist. Dhar (MP) for the lease period to M/s Satguru Cements Private Limited, 601/1, Airen Heights, Scheme No. 54, PU - 3, Oppo. C - 21 Mall, AB Road, Indore

7. Case No. 7755/2019 : Prior Environment Clearance for propsed project of Bulk Drugs, Fine Chemicals, API & its Intermediates at Plot No 36-D, Industrial area sector-3, Village-Sagor, Pithampur, Dist.- Dhar. , MP -454775 Land area – 8129 sq. m. Propsed capacity: 400 TPA by Shri Sanjay Kanhaiyalal Kewalramani, Director M/s Medilux Drugs Pvt. Ltd, 301, 3rd floor Pushparatan Landmark, 384/1 Saket Nagar Indore 452001, Email - [email protected], Telephone – 4097764 Mob : 9752090850 Envt. Conultant : Creative Enviro Services, Bhopal(MP)

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 21 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020

(1) The project is proposed for Manufacturing of Bulk Drug & Intermediate with Production Capacity – 33333.33 kg/month at Plot No. 36D, Pithampur Industrial Area, Sector-3, Village Sagor, Dist. Dhar, (M.P.)

(2) The proposed production capacity is 400 TPA. Proposed product and production capacity:- List & capacity of Products (Proposed) Capacity (Proposed)

MTPA) Sr. No Bulk drugs ,Drug intermediate & fine chemicals A Products (Proposed) With Intermediates

1 Defrasirox

400

2 Hydroquinone 3 Raloxifene Hydrochloride 4 Timolol maleate 5 Inosine pranobex 6 Bisoprolol Fumarate 7 Tofisopam 8 Penfluridol 9 Dapsone 10 Glimepiride 11 Azosemide 12 Anagliptin 13 Rivastigmine tatrate 14 Ipronazide phosphate 15 Buspirone hydrochloride 16 Mirtazapine 17 Pentetate calcium trisodium Products Under Development 18 Iguratimod

19 Garenoxacin 20 Denatonium Benzoate 21 Potassium Iodide 22 Metacresol 23 Maropitant 24 Iversol 25 Clozapine 400

(3) The proposed project is covered under 5 (f) category (B) of the schedule of EIA Notification issued by the Ministry of Environment & Forests vide S.O.1533 (E), dtd. 14.09.2006 and its amendments, hence is required to obtain prior EC. In the context of pandemic COVID -19, GoI’s MoEF&CC issued a OM vide dated 13.04.2020, for considering the API & Bulk drug Projects as B-2 category.

(4) There is no interstate boundary within 05 km and no National park, Sanctuary and Eco-sensitive areas within 05 km of the project area hence General condition are not attracted.

(5) The case was discussed in SEAC meetings 462nd dated 30.09.2020, and recommended for grant of prior EC.

(6) Today the case scheduled for presentation and after deliberations by PP the case was discussed in depth & it is recorded that:-

i. The project is proposed in the company’s existing premises having land of 8129 sq mt, PP has submitted sale agreement dtd 01.09.2020 executed between Medilux Chemicals Pvt. Ltd. through Director Shri Sanjay

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 22 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020

Kanhaiyalal Kewalramani, & M/s Medilux Drugs Pvt. Ltd through Director Ms Sruchi Deepak Kewalramani.As per the agreement Party of first part shall transfer the lease hold land alongwith the structure made on the leasehold land as per sale agreement to party of second part.Party of first part shall execute required documents including NOC for amendment of lease agreement with MPAKVN fortransfer of lease of land in favour of Party of Second Part.

ii. The major facilities will be involved as Boiler, MEE, Reactors, Cooling Towers, Effluent Treatment Plant (ETP), and R.O Plant Facilities like administrative office, parking and greenbelt/plantation will also be developed as per plan/requirement.

iii. The total water requirement for the project will be approx. 150 KLD and after recycling/reuse, the net fresh water consumption will be 90 KLD which will be sourced from AKVN water supply.Total waste water generation from proposed unit will be 98 KLD and treated in ETP, RO and MEE is 100 KLD, 150 KLD, and 12 KLD, respectively. The rejected water will be reused for floor washing and gardening/green belt. The treated water will be used for cooling towers, floor washing and gardening/green belt.

iv. Following are the EMP planned for proposed activities of the plant • Storm water drainage system will be developed and shall be maintained

preciously to prevent the flow of silt and other contaminant outside of the site

• The total water requirement is about 150KLD and waste water generated from the plant will be about 98KLD. Out of this about 39.5 KLD will be HTDS from Process, Boiler blow down & Scrubber System and 51.5 KLD LTDS from Process, Washings, R&D, QC & Cooling towers and from Domestic/ Sewage will be collected by gravity from all sources into separate collection tanks.

• HTDS Effluent will be sent to Multiple Effect Evaporator (MEE) with Stripper column followed by Agitated Thin Film Dryer (ATFD). The Condensate from MEE & LTDS Effluents will be sent to Biological ETP

• The entire trade effluent will be divided into two streams i.e. Stream-I (high concentrated streams) and Stream-II (low concentrated stream). Both the streams will be treated in well-designed ETP, RO and MEE.

• A drain along the boundary wall shall be made, which will be connected proposed settling tank to protect the flow of contaminant towards nearby area

• Regular monitoring and analysis of river is proposed. • Being a chemical based plant, it is proposed to harvest the rain water only

form the building roof top. • No treated / untreated effluent would be discharged on land in Industrial

premises or study area. v. Solid waste generated during the manufacturing process and wastewater

treatment process is mainly sludge and will be disposed at authorized TSDF facility as per Hazardous and Other Waste (Management & Transboundary Movement) Rules, 2008 (Amendment 2016).

Sr.No. Hazardous waste Waste Category

Proposed Quantity(MT)

1 Spent oil 5.1 1.0

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 23 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020

2 Spent solvents 20.2 200 3 Distillation Residue 20.3 20.0 4 Other solid wastes(poly bags, hand gloves,

tissue papers and butter papers) - 20.0

5 Process Residue & Wastes 28.1 10.0 6 Spent Ion Exchange Resin 35.2 0.2 7 Spent Carbon or Filter medium 36.2 20.0 8 off- specification Products 28.4 10.0 9 Spent solvent. 28.6 300.0 10 Empty barrels/containers/liners

contaminated with hazardous chemicals/wastes

33.1 20.0

11 Chemical sludge from waste water treatment 35.3 60.0

12 Centrifuge Filter cloths / paper - 10.0 14 HEPA filters - 8.0

• Disposal of hazardous waste on regular basis shall be ensured and there should be no dumping of these materials in the premises/outside.

• Hazardous chemicals shall be stored in sealed tanks, drums etc. Flame arrestors shall be provided on tanks. To avoid the spillage from processing unit, Industry shall provide fully mechanized filling and packaging operation unit.

• RCC layer and double layered HDPE lining for primary and secondary leachate collection shall be provided.

• Flammable, ignitable, reactive and non-compatible wastes should be stored separately and never should be stored in the same storage shed.

• In order to have appropriate measures to prevent percolation of spills, leaks etc. to the soil and ground water, the storage area should be provided with concrete floor of inert material or steel sheet depending on the characteristics of waste handled and the floor must be structurally sound and chemically compatible with wastes.

• Measures should be taken to prevent entry of runoff into the storage area. The Storage area shall be designed in such a way that the floor level is at least 150 mm above the maximum flood level.

vi. At present the total connected load of power is about 1500 KVA. In case of power failure, D.G. set (500 KVA ) will be used as a backup power source.

vii. To mitigate the impact of pollutants from boiler stack, diesel generator sets, sources of fugitive emission and vehicular traffic during the operational phase of the site, following measures are proposed for implementation:

• Height of all the stacks will be as per statutory requirement. All the stacks will have Stack Monitoring Facility (SMF) consisting of sampling port-hole, platform and access ladder.

• Bag Filters and venturi scrubber are proposed as per the requirement and nature of pollutant.

• Online monitoring system for the pollutants from the stacks with an arrangement to reflect gaseous emission parameters on company’s server shall be provided.

• Transport vehicles will be properly maintained to reduce air emissions. Vehicles will be periodically checked for pollutant emissions against stipulated norms.

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 24 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020

• Development of green belt in time bound manner in consultation with forest department.

• Provision of enclosure for all the loading & unloading operations, if possible. • Regular maintenance of air pollution control equipment. • Regular monitoring of VOC, concentration in work zone • Better process control shall also help to keep the emission within the limit • Alkaline Scrubber will be attached to the reactor vent to control process

SO2 emission. • In order to control the fugitive dust emissions due to transportation activity,

all the operational roads within the plant area shall be asphalted. • Regular maintenance of vehicles and machinery in order to control

emissions • A good housekeeping and proper maintenance will be practiced in the

industry viii. The plantation and green belt is developed in 3300 sq. mtr area by planting

520 nos.of plants. ix. PP has included Disaster Management plan in the EIA Report. For

firefighting measure PP has provided Fire extinguishers and Fire Hydrants at project site.

x. PP has proposed the rain water from the building roof will be directed through the drainage to the covered storm water drainage line. All drainage system will be concreted lined and located along the roads up to rain water harvesting pit. Roof top rain water will be collected in tanks and reused after filtration as per requirements.

xi. The total fixed cost of proposed project will be INR 31 Crore. xii. As part of CER activity PP has proposed to provide Infrastructure

development at School in nearby villagers with Budgetary Provision of 62 lakh.. Proposed CER Programme with Budgetary Provision

S. no Need Identified For CSR Plan

Activities Budgetary Provision (Capital) (Rs. In lacs )

Time Frame

1 Infrastructure development at School, Aganwadies

Infrastructure facilities at schools in terms of provision of computers, teachers, facility of safe drinking water, and separate toilets for girls and boys, provision of furniture, additional rooms etc. In consultation with district administration

Rs . 40 Lac Within 05

years

2 Distribution of Mask, Sanitizer, oxi-meter, Thermometer

School, Health centers and aganwadies

Rs 1.00 Immediately

after Clearance

3 Covid Related

Activities

To provide PPE Kit, Bed and Ventilator at nearby hospitals

Rs 9.00 Immediately after Clearance

4 Execution of Need base Activities

Execution of need base activities in coordination with district administration Dhar and Indore

Rs. 12.00 Within 05 years

Total Rs 62 Lacs

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 25 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020

Hence It is decided to accept the recommendations of 462nd SEAC meeting dtd 30.09.2020 and accord Prior Environmental Clearance for plot no. 36D, Pithampur Industrial area, Sector 3, Sagor, District Dhar-454775 (M.P) Total plot area of 8129 sq.m. Proposed Capacity – 33333.33kg/month Or 400 MTPA, by M/s Medilux Drugs Pvt. Ltd. Plot no. 36D, Pithampur Industrial area, Sector 3, Sagor, District Dhar-454775 (M.P) subject to following specific conditions:- 1. The entire demand of fresh water should be met through MPAKVN. Fresh water

should not be used for Irrigation and gardening purpose. 2. Waste water:

(a) PP should ensure “Zero effluent discharge” from the unit by 100% recycling. The water softening reject, boiler blow down reject and cooling blow down will be treated in ETP. Further treated waste water will go through the RO and finally re used/recycled in the process and unused waste water evaporate in MEE.

(b) RO and MEE should be provided for treatment of high COD waste streams and only in case of emergency/breakdown high COD wastes should be disposed off through CTSDF, Pithampur, Dhar.

3. For Air Pollution: (a) PP should ensure regular Stack monitoring & Ambient air quality monitoring

and should be carried out as per the guidelines/norms of MPPCB/CPCB. (b) In plant control measures for checking fugitive emission from all the

vulnerable sources shall be provided. Fugitive emission shall be controlled by providing closed storage, closed handling & conveyance of chemicals/materials, multi cyclone separator/bag filters and water sprinkling system.

(c) Company shall carry out the HAZOP study and report shall be submitted to ministry MoEF & CC Regional Office, Bhopal.

(d) For control of fugitive emission and VOCs following steps should be followed:- Chilled brine circulation system shall be provided and it should be

ensured that the solvent recovery efficiency is not be less than 95%. Reactor and solvent handling pump shall be provided with mechanical

seal to prevent leakage. Solvent shall be taken from underground storage tank to reactor through

closed pipeline. Storage tank shall be vented through trap receiver and condenser operated on chilled water.

4. Hazardous Waste Management: (a) As proposed above, PP should ensure disposal of hazardous waste regularly

and there should be no dumping of these materials in the premises/outside. (b) PP should ensure handling, disposal and management of hazardous waste

as per the related prescribed rules. (c) PP should obtain Renewal of authorization regularly from MPPCB for

collection storage and disposal of hazardous waste (Management, handling & transboundary Movement) Rules 2008 and its amendments. Membership of the TSDF should be obtain for hazardous waste disposal.

(d) Hazardous chemicals should be stored in sealed tanks, drums etc. Flame arrestors shall be provided on tanks. To avoid the spillage from processing unit, Industry shall provide fully mechanized filling and packaging operation unit.

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 26 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020

5. Green Belt Development: (a) PP should ensure plantation as proposed 3300 sq mt of area with 520

number of trees Plantation in the project area of indigenous local varieties like Neem, Peepal, Kadam and Kachnaar.

(b) Every effort should be made to protect the existing trees on the plot. (c) Green area including thick green-belt shall be developed in at least 33% of

the plot area to mitigate the effect of fugitive emissions all around the plant in consultation with the forest department as per the guidelines of CPCB.

6. PP should ensure the implementation of CER activities to the extent of Rs. 62.0 lakh as committed during presentation on regular basis in consultation with Collector, Dhar

7. Total quantity of runoff water generated and green belt area should be collected in underground tank & used for process in plant to minimize fresh water requirement.

8. All other conditions as laid in the consents of MPPCB shall be applicable. 8. Case No 7786/2020: Prior Environmental Clearance for Proposed Multiplex cum

shopping mall at Khasra no. Kharsa No. 47/3/1//1, 47/3/1/2, 47/2/2 and 50/2/2 Nipaniya Tehsil & District-Indore (MP) Total Plot Area - 21310 sq.m, Built up Area – 108624.44 sq.m by Shri Shaliesh Verma, Project Manager, M/s Bravo Realcon LLP & Velour Nirman Pvt. Ltd. M1 BCM Heights, Sh Badalchand Mehta Marg Scheme No. 54 Indore, Madhya Pradesh-452001 E-mail: [email protected], Telephone no. 1. This is case of Environment Clearance for Construction of Multiplex Cum

Shopping Mall (Proposed Area = 21310 sqm, Built-up area = 108624.44 sqm) at Khasra No. 47/3/1/1, 47/3/1/2, 47/2/2, 50/2/2, Nipaniya, Dist. Indore (MP)

2. The geographical coordination of the project site is Latitude 22°45’5.11” N Longitude 75°55’24.62” E

3. The project includes construction of Commercial Complex . 4. As per the approval of T & CP Indore (vide L. No. 5553/Na. Gra. Ni./2020 dtd

02.07.2019) the total land area of project is 2.131 ha. The total built up area proposed by PP is – 108624.44 sq.m .The project comes under 8 (a) category (B) of schedule of EIA Notification, 2006 as the total construction is between 20,000 sq.m & 1,50,000 sq.m.

5. The Ralamanadal sanctuary is >10.0 KM from the site. 6. The case was discussed in SEAC meetings 462nd dtd. 30.09.20 and

recommended for grant of EC subject special conditions. 7. As per Recommendation of SEAC the case was considered and recorded that:

i. Regarding land documents PP has submitted registered sale deed dtd. 07.10.2016. As per the sale deed the said land was purchased by , M/s Bravo Realcon LLP . PP has also submitted transferred deed dtd. 11.12.2018. As per the deed the some part of the said land has been transferred to & Velours Nirman Pvt. Ltd.

ii. Total water demand is anticipated to be 125.62 KLDFresh water requirement for the project is : 51.57 KLDKLD which will be met by supply from Indore Municipal Corporation. PP has submitted letter (dtd. 22.09.20) from Municipal Corporation Indore for water supply.

iii. The waste water of 124 KLD will generated during the operation phase and generated waste water shall be treated in sewage treatment plant of 160 KLD capacity based on MBBR technology and out of treated waste water of 111KLD, 52.75 KLD will be used for flushing, 21.3 KLD horticulture and 22

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 27 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020

KLD n washing & others remaining 15 KLD is proposed to discharge in Municipal sewer line. PP has submitted vide letter (dtd. 04.08.2020) from Municipal Corporation Indore for disposal of extra treated waste water.

iv. Total waste 975 Kg/day, this consist all types of wastes (Bio Degradable Waste Kg/day Non Bio Degradable Waste:) will be generated during operation phase. Twin bin waste collection system will be used within the complex – green bins for bio-degradable wastes and blue bins for non-biodegradable wastes shall be provided.

Bio degradable will be sent to organic waste convertor and Non bio-degradable will be Collected and transported to the segregation point. Rest inert MSW will be handed over to Municipal Corporation, Indore for final disposal. PP has applied vide letter (dtd. 18.08.2020) from Municipal Corporation Indore for disposal of solid waste.

Hazardous waste (Spent Oil) & e-waste will be stored at separate place. Used oil will be sold off to authorized recyclers while there will be buy-back arrangements with the supplier for DG Set batteries. Litter bin will also be provided in open areas.

v. PP has proposed the maximum height of the building is 29.45 m. PP has provided width of approach road 30.0m, Front MOS 12.0 m and Rear MOS 7.5m.

vi. Rainwater harvesting has been proposed to recharge ground water for which 06 recharge pits will be constructed. Other than rooftop area rain water will be recharged to nearest natural water drain.

vii. Emission from vehicular Traffic Harmful, dispersion of emissions from DG and Odor from STP & Garbage. PP has proposed as follows:-

Green belt to be provided with specific species. Provision of adequate parking space for the residents. Better traffic management in the complex by means of Signages Provision of Stack as per CPCB guidelines. Provision of adequate natural/mechanical ventilation. Regular pest control to mitigate the mosquito breeding and other

disease causing bacteria. viii. Noise Emission Control Technologies: DG set shall have in built acoustic

enclosure which will be designed for minimum 65 dB (A). Ambient Noise Monitoring shall be carried out as per direction of MPPCB

ix. Total Connected Load In KW : 4000 KW/5000 KVA . Total Diversified Load In Kw At 0.7 Diversity :2800 KW/3500 KVAand it will be sourced from State Electricity Board. DG sets will be used during power failure only. 4 DG sets of 937.5 KVA each. The proponent has taken various energy conservation measures which include: Use of energy efficient lighting fixtures viz. LED, T5 which give more

light output for the same watts consumed and therefore require less nos. of fixtures in Common areas

Equipment efficiency standard power factor will be maintained between 0.95 and unity for major equipment like Lift, STP etc. This will reduce electrical power distribution losses in the installation.

Motion Sensor in staircases.

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 28 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020

Use of VFD drives in lifts. Provision of Solar Hot water system. Recommending the benefits of adopting BEE 5 star rated electrical

appliances to the customers to increase energy savings. x. PP has proposed all other fire safety requirements in line with latest NBC-

2016 these are: Wet riser system, Internal fire hydrants strategically located to cover

maximum area, Fire pump, Sprinkler pump, Jockey pump, Sprinklers system,Two-way communication system, External yard hydrants, Portable fire extinguishersetc .

Addressable microprocessor based fire alarm and detection system Smoke detectors above and below false ceiling spaced as per NFPA

standards (500 Sft coverage per detector) PP has obtained NOC dtd. 31.08.2020 from UADD Bhopal for fire fighting provision.

xi. For vehicles, adequate space for smooth movement and parking shall be provided at the proposed site to avoid any congestion and idling state emissions.

xii. PP has proposed total car parking 1025ECS (Basement - 275 ECS, 150 Silt parking- 600 ECS for multilevel parking).

xiii. As details provided by PP, 4262sq.m (20% of net plot area) of area is dedicated for the green belt development by planting 120 nos of trees including two rows periphery.

xiv. Total Project cost of the project is INR Rs. 187.5 lakh. xv. Under CER activities PP has proposed as follows with. budgetary provision:

Rs. 125 lakh S.No Activities Budgetary provisions

(Rs in lacs) 1 2 3 4 5 6 7 8

Education Sector - School infrastructure , providing books in the library , sports equipments & other related activities to institutions & NGO’s etc. Assistance to employees for improved sanitation in their areas of residence, to the extent possible. Support to local admin in maintenance of public toilets. Support to local admin in road network. Development of green belt area in and around periphery From satya sai square to Best price & BCM height to shanty Niketan colony (scheme no. 54)Indore. Any other CER activities inconsultaion with the local authorities.

187.5 Lacs @ 1.5% of Total Budget Rs 125 Cr

Hence It is decided to accept the recommendations of 462nd SEAC meeting dtd. 30.09.20 with special conditions and accord Prior Environmental Clearance for the proposed Multiplex cum shopping mall at Khasra no. Kharsa No. 47/3/1//1, 47/3/1/2, 47/2/2 and 50/2/2 Nipaniya Tehsil & District-Indore (MP) Total Plot Area - 21310 sq.m, Built up Area – 108624.44 sq.m by Shri Shaliesh Verma, Project Manager, M/s Bravo Realcon LLP & Velour Nirman Pvt. Ltd. M1 BCM Heights, Sh Badalchand Mehta Marg Scheme No. 54 Indore, Madhya Pradesh-452001, subject to following specific conditions imposed by SEIAA.

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 29 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020

1. The fresh water supply arrangement should be met through Municipal Corporation, Indore (as per IMC letter dtd.22.09.2020) and there should no extraction of ground water.

2. The inlet and outlet point of natural drain system should be maintained with adequate size of channel for ensuring unrestricted flow of water.

3. Disposal of waste water.

a. PP should ensure disposal of waste water arrangement should be done in such a manner that water supply sources are not impaired.

b. PP should ensure linkage with Nagar Nigam Indore for disposal of extra treated waste water.

c. Ensure regular operation and maintenance of the STP.

d. The Project Proponent shall explore the possibilities of reusing the treated wastewater from nearby projects during rainy season.

4. The final disposal point for storm water will be municipal storm drain if storm water network is present. If storm water network is absent, the storm water surface runoff should be disposed off in proper way. The budget should be including in EMP plan for storm water management.

5. Solid Waste Management:

a. Separate wet and dry bins must be provided at the ground level for facilitating segregation of waste.

b. The solid waste generated should be properly collected and segregated. Wet garbage should be composted and dry inert solid waste should be disposed off to the approved sites for land filling after recovering recyclable material.

c. Ensure linkage with Municipal Corporation for final disposal of MSW.

6. PP should ensure building height, road width, front MOS and side / rear as per approved layout of T & CP.

7. For firefighting:-

a. PP should ensure distance of fire station approachable from the project site.

b. As per MPBVR, 2012 rule 42 (3) PP should submit necessary drawings and details to the Authority (Nagar Nigam, Indore) incorporating all the fire fighting measures recommended in National Building Code part – IV point no. 3.4.6.1. The occupancy permit shall be issued by Nagar Nigam only after ensuring that all fire fighting measures are physically in place.

8. For Rain Water Harvesting, and Storm water management:-

a. PP should ensure the rain water harvesting with 06 recharging pits and these pits should be connected laterally to consume the surplus runoff. In addition, PP should provide recharging trenches. The base of the trenches should be Kachha with pebbles.

b. The storm water from roof – top, paved surfaces and landscaped surfaces should be properly channelized to the rain water harvesting sumps through efficient storm water network as proposed. The budget should be included in EMP plan for storm water management.

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 30 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020

c. PP should ensure to proper storm water drainage system is available in and around the site for transporting excess storm water runoff to drains, thereby discarding possibility of flooding in and around the site.

9. PP should ensure to provide car parking area for total car parking 1025ECS (Basement - 275 ECS, 150 Silt parking- 600 ECS for multilevel parking).

10. Green belt :-

a. PP should ensure plantation in an area of 4262sq.m (20% of net plot area) sq.m of area is dedicated for the green belt development by planting 120 nos of trees including two rows periphery and also explore the possibility to plant trees of indigenous local varieties like Neem, Peepal, Kadam, Karanj, Kachnaar, Saltree, Gulmohar etc.

b. The green belt of the adequate width and density preferably with local species along the periphery of the plot shall be raised if possible so as to provide protection against particulates and noise.

c. Every effort should be made to protect the existing trees on the site. PP should obtain permission to cut the trees from the concern department.

11. PP should ensure to implement the CER activities as proposed for which budgetary allocation of Rs. 125.00 lakh. has been made in consultation with District administration Indore.

9. Case No. 7777/2020; Prior Environmental Clearance for stone Quarry (Opencast Manual/Semi Mechanized Method) in area of 1.0 ha. for production capacity of 10000 cum per annum at Khasra No. 1530/1/1 (Part), 1530/1/2 (Part) at Village - Sonkatchh, Tehsil - Narsinghgarh, Dist. Rajgarh, (MP) by Shri Raviraj Meena S/o Shri Bhagwan Singh Meena, R/o Village - Sonkatchh, Tehsil - Narsinghgarh, Dist. Rajgarh, MP – 455118.

This case was recommended in 463rd SEAC dated 1/10/2020 it was recorded that..........

"------------ PP has submitted the response of above quarries same date vide letter dated 01.10.2020, which was placed before the committee and the same found satisfactory. The EMP and other submissions made by the PP were found to be satisfactory and acceptable, hence committee decided to recommend the case for grant of prior EC subject to the following special conditions in addition to the standard conditions at annexure ‘A’:

PP/Consultant made a presentation on all concerned issues were discussed in detail. After detailed discussions and perusal of recommendations of 463rdt SEAC meeting dated 1.10.2020, presentation made by the PP in SEIAA, it was decided to accept the recommendation of SEAC for grant of prior EC to the project subject to the following specific conditions:-

I. Before commencing any mining activity fencing shall be carried out all around the lease area. Proper watch and ward arrangements should be made with installation of signage at 4 corners of lease area to avoid any untoward incident involving public and animals by the PP.

II. PP shall not start mining activity before execution of lease agreement.

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 31 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020

III. The depth of the pit shall be as per the Approved Mining Plan.

IV. The entire area shall be fenced and three rows of plantation should be done on the periphery of the boundary.

V. PP shall ensure the proper water supply arrangements for dust suppression, regular sprinkling, plantation and drinking purposes especially in summer season.

VI. Total 1200 saplings of suitable tree species i.e. Neem, Pipal,Bargad,Gulmohar Amla etc. shall be planted in nearby Khasra No. . 1530/1/1, 1530/1/2 of Village – Sonkatchh, Tehsil - Narsinghgarh, Dist. Rajgarh MP by PP under plantation programme in consultation with DM at identified revenue land of the district. PP shall also explore and identify the chunk of land in the area from revenue record to carry out plantation programme as proposed.

VII. PP shall ensure proper implementation of plantation, dust suppression, construction of approach road and maintenance of existing pakka road as part of Environmental Management Plan. Additional budget provision shall be made as part of EMP.

VIII. PP must ensure implementation of the following activities with separate budget provision of total Rs 0.90 Lakh/Year under CER:

1st to 3rd Year:

Provide to distribution of masks and sanitizers to villagers and conducting an awareness program through Panchayat for the protection from the spread of Corona virus (COVID 19 Pandemic)

Provide to development of grazing land

Provide to construction of Boundary wall, maintenance and furniture in Govt. Primary school, Killa

4th to 5rth Year:

Provide to whitewash, boundary wall of Govt. primary school, Kalyadeh

PP shall ensure to contruct toilet with proper plumbing in the school of above village and contribute on behalf of village in Jal Jeewan Mission in consultation with Janpad Panchayat and PHED. PP shall give preference to develop/provide infrastructural facilities in schools or aanganwadies of above villages. The modification to the above activities can be made with the permission of the district administration and need based activity for the development of nearby villages shall be implemented by

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 32 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020

PP in consultation with the District Collector and Gram Panchayat.

IX. PP should ensure to submit half yearly compliance report, Plantation and CER activity report along with photographs of all activities in MP-SEIAA. If PP is failed to upload or submit two consecutive half yearly compliance reports of EC conditions to concerned authority (SEIAA and Regional Office, MoEF&CC,GoI,Bhopal) than prior environmental clearance issued to PP will automatically be treated as cancelled/ revoked as per OM No. 930/SEIAA/2019 dated 30.05.2019 issued by MPSEIAA..

Hence, Prior Environmental Clearance is granted for stone Quarry (Opencast Manual/Semi Mechanized Method) in area of 1.0 ha. for production capacity of 10000 cum per annum at Khasra No. 1530/1/1 (Part), 1530/1/2 (Part) at Village - Sonkatchh, Tehsil - Narsinghgarh, Dist. Rajgarh, (MP) for the lease period to Shri Raviraj Meena S/o Shri Bhagwan Singh Meena, R/o Village - Sonkatchh, Tehsil - Narsinghgarh, Dist. Rajgarh, MP – 455118.

10. Case No. 7776/2020; Prior Environmental Clearance for Stone Quarry (Opencast Manual/Semi Mechanized Method) in area of 1.0 ha. for production capacity of 5000 cum per annum at Khasra No. 7/3 at Village - Sultaniya Khurd, Tehsil - Sarangpur, Dist. Rajgarh, (MP) by Shri Piyush Nagar S/o Shri Rajesh Nagar, Village - Khajuriya Hari, Tehsil - Sarangpur, Dist. Rajgarh, MP – 465689.

This case was recommended in 463rd SEAC dated 1/10/2020 it was recorded that..........

"------------ PP has submitted the response of above quarries same date vide letter dated 01.10.2020, which was placed before the committee and the same found satisfactory. The EMP and other submissions made by the PP were found to be satisfactory and acceptable, hence committee decided to recommend the case for grant of prior EC subject to the following special conditions in addition to the standard conditions at annexure ‘A’:

PP/Consultant made a presentation on all concerned issues were discussed in detail. After detailed discussions and perusal of recommendations of 463rdt SEAC meeting dated 1.10.2020, presentation made by the PP in SEIAA, it was decided to accept the recommendation of SEAC for grant of prior EC to the project subject to the following specific conditions:-

I. Before commencing any mining activity fencing shall be carried out all around the lease area. Proper watch and ward arrangements should be made with installation of signage at 4 corners of lease area to avoid any untoward incident involving public and animals by the PP.

II. PP shall not start mining activity before execution of lease agreement.

III. The depth of the pit shall be as per the Approved Mining Plan.

IV. PP shall leave 100 m from natural drain as no minin zone.

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 33 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020

V. The entire area shall be fenced and three rows of plantation should be done on the periphery of the boundary.

VI. PP shall ensure the proper water supply arrangements for dust suppression, regular sprinkling, plantation and drinking purposes especially in summer season.

VII. Total 1200 saplings of suitable tree species i.e. Neem, Pipal,Bargad,Gulmohar Amla etc. shall be planted in nearby Khasra No. . 7/3 of Village – Sultaniya Khurd, Tehsil - Sarangpur, Dist. Rajgarh,MP ,by PP in first year under plantation programme in consultation with DM at identified revenue land of the district. PP shall also explore and identify the chunk of land in the area from revenue record to carry out plantation programme as proposed.

VIII. PP shall ensure proper implementation of plantation, dust suppression, construction of approach road and maintenance of existing pakka road as part of Environmental Management Plan. Additional budget provision shall be made as part of EMP.

IX. PP must ensure implementation of the following activities with separate budget provision of total Rs 0.60 Lakh/Year under CER:

1st to 2nd Year: Provide to distribution of masks and sanitizers to villagers and conducting

an awareness program through Panchayat for the protection from the spread of Corona virus (COVID 19 Pandemic)

Provide to development of grazing land Provide to construction of Boundary wall in Govt. Primary school, Sultania

khurd 3rd ,4th & 5th Year:

Provide to whitewash, repairing of terrace of Kitchen of Govt. secondary school of Khajuriya hari

PP shall ensure to contruct toilet with proper plumbing in the school of above village and contribute on behalf of village in Jal Jeewan Mission in consultation with Janpad Panchayat and PHED. PP shall give preference to develop/provide infrastructural facilities in schools or aanganwadies of above villages. The modification to the above activities can be made with the permission of the district administration and need based activity for the development of nearby villages shall be implemented by PP in consultation with the District Collector and Gram Panchayat.

X. PP should ensure to submit half yearly compliance report, Plantation and CER activity report along with photographs of all activities in MP-SEIAA. If PP is failed to upload or submit two consecutive half yearly compliance reports of EC conditions to concerned authority (SEIAA and Regional Office, MoEF&CC,GoI,Bhopal) than prior environmental clearance issued to PP will automatically be treated as cancelled/ revoked as per OM No. 930/SEIAA/2019 dated 30.05.2019 issued by MPSEIAA..

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 34 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020

Hence, Prior Environmental Clearance is granted for Stone Quarry (Opencast Manual/Semi Mechanized Method) in area of 1.0 ha. for production capacity of 5000 cum per annum at Khasra No. 7/3 at Village - Sultaniya Khurd, Tehsil - Sarangpur, Dist. Rajgarh, (MP) for the lease period to Shri Piyush Nagar S/o Shri Rajesh Nagar, Village - Khajuriya Hari, Tehsil - Sarangpur, Dist. Rajgarh, MP – 465689.

11. Case No. 7780/2020; Prior Environmental Clearance for Murrum Quarry (Opencast Manual/Semi Mechanized Method) in area of 2.0 ha. for production capacity of 15000 cum per annum at Khasra No. 262 (Part)), Village - Tindoniya, Tehsil - Narsinghgarh, Dist. Rajgarh, (MP) by Shri Nandkishor Kalmodiya, Village - Tindoniya, Tehsil - Narsinghgarh, Dist. Rajgarh, MP – 465667.

This case was recommended in 463rd SEAC dated 1/10/2020 it was recorded that..........

"------------ The EMP and other submissions made by the PP were found to be satisfactory and acceptable, hence committee decided to recommend the case for grant of prior EC subject to the following special conditions in addition to the standard conditions at annexure ‘A’:

PP/Consultant made a presentation on all concerned issues were discussed in detail. After detailed discussions and perusal of recommendations of 463rdt SEAC meeting dated 1.10.2020, presentation made by the PP in SEIAA, it was decided to accept the recommendation of SEAC for grant of prior EC to the project subject to the following specific conditions:-

I. Before commencing any mining activity fencing shall be carried out all around the lease area. Proper watch and ward arrangements should be made with installation of signage at 4 corners of lease area to avoid any untoward incident involving public and animals by the PP.

II. PP shall not start mining activity before execution of lease agreement.

III. The depth of the pit shall be as per the Approved Mining Plan.

IV. The entire area shall be fenced and three rows of plantation should be done on the periphery of the boundary.

V. PP shall ensure the proper water supply arrangements for dust suppression, regular sprinkling, plantation and drinking purposes especially in summer season.

VI. Total 2400 saplings of suitable tree species i.e. Neem, Pipal,Bargad,Gulmohar Amla etc. shall be planted in nearby Khasra No. 258(part) of Village – Tindoniya, Tehsil - Narsinghgarh, Dist. Rajgarh ,by PP under plantation programme in consultation with DM at identified revenue land of the district. PP shall also explore and identify the chunk of land in the area from revenue record to carry out plantation programme as proposed.

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 35 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020

VII. PP shall ensure proper implementation of plantation, dust suppression, construction of approach road and maintenance of existing pakka road as part of Environmental Management Plan. Additional budget provision shall be made as part of EMP.

VIII. PP must ensure implementation of the following activities with separate budget provision of total Rs 0,60 Lakh/Year under CER:

1st to 3rdYear:

Provide to distribution of masks and sanitizers to villagers and conducting an awareness program through Panchayat for the protection from the spread of Corona virus (COVID 19 Pandemic)

Provide to development of grazing land

Provide to maintenance, Furniture's and whitewash of Health care centre, Jamaunya Ganesh

4th to 5th Year:

Provide to sports kit for students of Govt. High school, Badodiya Talab

PP shall ensure to contruct toilet with proper plumbing in the school of above village and contribute on behalf of village in Jal Jeewan Mission in consultation with Janpad Panchayat and PHED. PP shall give preference to develop/provide infrastructural facilities in schools or aanganwadies of above villages. The modification to the above activities can be made with the permission of the district administration and need based activity for the development of nearby villages shall be implemented by PP in consultation with the District Collector and Gram Panchayat.

IX. PP should ensure to submit half yearly compliance report, Plantation and CER activity report along with photographs of all activities in MP-SEIAA. If PP is failed to upload or submit two consecutive half yearly compliance reports of EC conditions to concerned authority (SEIAA and Regional Office, MoEF&CC,GoI,Bhopal) than prior environmental clearance issued to PP will automatically be treated as cancelled/ revoked as per OM No. 930/SEIAA/2019 dated 30.05.2019 issued by MPSEIAA.

Hence, Prior Environmental Clearance is granted for Murrum Quarry (Opencast Manual/Semi Mechanized Method) in area of 2.0 ha. for production capacity of 15000 cum per annum at Khasra No. 262 (Part)), Village - Tindoniya, Tehsil - Narsinghgarh, Dist. Rajgarh, (MP) for the lease period to Shri Nandkishor Kalmodiya, Village - Tindoniya, Tehsil - Narsinghgarh, Dist. Rajgarh, MP – 465667.

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 36 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020 12. Case No. 7778/2020; Prior Environmental Clearance for Stone Quarry (Opencast

Manual/Semi Mechanized Method) in area of 1.0 ha. for production capacity of 5000 cum per annum at Khasra No. 88/5/1/1 (Part)), Village - Gagaurni, Tehsil - Jeerapur, Dist. Rajgarh, (MP) by Shri Nandkishor Kalmodiya, Village - Tindoniya, Tehsil - Narsinghgarh, Dist. Rajgarh, MP – 465667.

This case was recommended in 463rd SEAC dated 1/10/2020 it was recorded that..........

"------------ The EMP and other submissions made by the PP were found to be satisfactory and acceptable, hence committee decided to recommend the case for grant of prior EC subject to the following special conditions in addition to the standard conditions at annexure ‘A’:

PP/Consultant made a presentation on all concerned issues were discussed in detail. After detailed discussions and perusal of recommendations of 463rdt SEAC meeting dated 1.10.2020, presentation made by the PP in SEIAA, it was decided to accept the recommendation of SEAC for grant of prior EC to the project subject to the following specific conditions:-

I. Before commencing any mining activity fencing shall be carried out all around the lease area. Proper watch and ward arrangements should be made with installation of signage at 4 corners of lease area to avoid any untoward incident involving public and animals by the PP.

II. PP shall not start mining activity before execution of lease agreement.

III. The depth of the pit shall be as per the Approved Mining Plan.

IV. The entire area shall be fenced and three rows of plantation should be done on the periphery of the boundary.

V. PP shall ensure the proper water supply arrangements for dust suppression, regular sprinkling, plantation and drinking purposes especially in summer season.

VI. Total 1200 saplings of suitable tree species i.e. Neem, Pipal,Bargad,Gulmohar Amla etc. shall be planted in nearby Khasra No. 88/5/1/1 of Village – Gagaurni, Tehsil - Jeerapur, Dist. Rajgarh,by PP under plantation programme in consultation with DM at identified revenue land of the district. PP shall also explore and identify the chunk of land in the area from revenue record to carry out plantation programme as proposed.

VII. PP shall ensure proper implementation of plantation, dust suppression, construction of approach road and maintenance of existing pakka road as part of Environmental Management Plan. Additional budget provision shall be made as part of EMP.

VIII. PP must ensure implementation of the following activities with separate budget provision of total Rs 0.60 Lakh/Year under CER:

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 37 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020

1st to 2nd Year: distribution of masks and sanitizers to villagers and conducting an

awareness program through Panchayat for the protection from the spread of Corona virus (COVID 19 Pandemic)

development of grazing land whitewash and maintenance (Doors, windows and walls) of Govt.

Secondary school, Gagaurni 3rd to 4th Year:

construction of pucca chabutra , whitewash and maintenance of Jan shiksha kendra Limboda

5th Year: whitewash and furnitures for Govt. primary school, Manpura

PP shall ensure to contruct toilet with proper plumbing in the school of above village and contribute on behalf of village in Jal Jeewan Mission in consultation with Janpad Panchayat and PHED. PP shall give preference to develop/provide infrastructural facilities in schools or aanganwadies of above villages. The modification to the above activities can be made with the permission of the district administration and need based activity for the development of nearby villages shall be implemented by PP in consultation with the District Collector and Gram Panchayat.

IX. PP should ensure to submit half yearly compliance report, Plantation and CER activity report along with photographs of all activities in MP-SEIAA. If PP is failed to upload or submit two consecutive half yearly compliance reports of EC conditions to concerned authority (SEIAA and Regional Office, MoEF&CC,GoI,Bhopal) than prior environmental clearance issued to PP will automatically be treated as cancelled/ revoked as per OM No. 930/SEIAA/2019 dated 30.05.2019 issued by MPSEIAA.

Hence, Prior Environmental Clearance is granted for Murrum Quarry (Opencast Manual/Semi Mechanized Method) in area of 1.0 ha. for production capacity of 5000 cum per annum at Khasra No. 88/5/1/1 (Part)), Village - Gagaurni, Tehsil - Jeerapur, Dist. Rajgarh, (MP) for the lease period to Shri Nandkishor Kalmodiya, Village - Tindoniya, Tehsil - Narsinghgarh, Dist. Rajgarh, MP – 465667.

13. Case No. – 7785/2020 Prior Environmental Clearance for Soil Quarry (Opencast Manual / Semi Mechanized Method) in an area of 1.486 ha. for production capacity of 1306.64 cum / year at Khasra No. 55/1 at Village - Kandela, Tehsil - Gaurihar, Dist. Chhatarpur by Shri Asharam Patel S/o Shri Durga Prasad Patel, Village - Kandela, Tehsil - Gaurihar, Dist. Chhatarpur, MP – 471516

This case was recommended in 463rd SEAC meeting dated 01.10.2020 and it was recorded that..........

“…………PP has submitted the response of above quarries same date vide letter dated 01.10.2020, which was placed before the committee and the same found satisfactory. The EMP and other submissions made by the PP were found to be satisfactory and acceptable, hence committee decided to recommend the case for

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 38 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020

grant of prior EC subject to the following special conditions in addition to the standard conditions at annexure ‘A’:

PP/Consultant made a presentation on all aspects of the project and all concerned issues were discussed in detail. After detailed discussions and perusal of recommendations of 463rd SEAC meeting dated 01.10.2020, presentation made by the PP in SEIAA, it was decided to accept the recommendation of SEAC for grant of prior EC to the project subject to the following specific conditions:-

I. Before commencing any mining activity fencing shall be carried out all around the lease area. Proper watch and ward arrangements should be made with installation of signage at 4 corners of lease area to avoid any untoward incident involving public and animals by the PP.

II. PP shall not start mining activity before execution of lease agreement. III. The depth of the pit shall be as per the Approved Mining Plan. IV. The entire area shall be fenced and three rows of plantation should be done

on the periphery of the boundary. V. PP shall ensure protection and conservation of existing 10 -12 trees falling

under mining lease area and in no way these will be permitted to be cut / uprooted .Trees which are located in the lease area shall be kept intact.

VI. PP shall ensure that the proper water supply arrangements for dust suppression, regular sprinkling, plantation and drinking purposes especially in summer season.

VII. PP shall ensure to construct and maintained the approach road. Plantation will be carried out on both side of approach road.

VIII. PP shall ensure proper implementation of plantation, dust suppression, construction of approach road and maintenance of existing road & as part of Environmental Management Plan. Additional budget provision shall be made as part of EMP.

IX. Total 2000 saplings of suitable tree species i.e. Neem, Pipal, Bargad, Mango, Amla, Amaltas, Drumstick etc. shall be planted by PP at barrier zone, in identified area, Remaining area of Khasra no. 55/1 under plantation programme. PP shall also explore and identify the chunk of land in the area from revenue record to carry out plantation programme as proposed.

X. PP must ensure implementation of the following activities with separate budget provision of Rs 0.50 lakh/year under CER. 1st Year

Distribution of masks and sanitizers to villagers and conducting an awareness program through Panchayat for the protection from the spread of Corona virus (COVID 19 Pandemic)

Development of grazing land Furniture's and whitewash of Govt. Primary school, Kandela

2nd & 3rd Year Construction of Boundary wall of Govt. Secondary school of

Rampurghat 4th & 5th Year

Construction of Boundary wall of Govt. Primary school of Haazipur.

PP shall ensure to contruct toilet with proper plumbing in the school of above village and contribute on behalf of village in Jal Jeewan Mission

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 39 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020

in consultation with Janpad Panchayat and PHED. PP shall give preference to develop/provide infrastructural facilities in schools or aganwadies of above villages The modification to the above activities can be made with the permission of the district administration and need based activity for the development of nearby villages shall be implemented by PP in consultation with the District Collector and Gram Panchayat

XI. PP should ensure to submit half yearly compliance report and CSR activity report with photographs of plantation in MP-SEIAA. If PP is failed to upload or submit two consecutive half yearly compliance reports of EC conditions to concerned authority (SEIAA and Regional Office, MoEF&CC,GoI,Bhopal) than prior environmental clearance issued to PP will automatically be treated as cancelled/ revoked as per OM No. 930/SEIAA/2019 dated 30.05.2019 issued by MPSEIAA.

Hence, Prior Environmental Clearance is granted for Soil Quarry (Opencast Manual / Semi Mechanized Method) in an area of 1.486 ha. for production capacity of 1306.64 cum / year at Khasra No. 55/1 at Village - Kandela, Tehsil - Gaurihar, Dist. Chhatarpur for the lease period to Shri Asharam Patel S/o Shri Durga Prasad Patel, Village - Kandela, Tehsil - Gaurihar, Dist. Chhatarpur, MP – 471516

14. Case No. – 7784/2020 Prior Environmental Clearance for Stone Quarry (Opencast Manual / Semi Mechanized Method) in an area of 3.90 ha. for production capacity of 150000 cum / year at Khasra No. 114/1 at Village - Bhulera, Tehsil - Rajnagar, Dist. Chhatarpur by M/s Ramraja Stone Crusher, Partner, Shri Sushil Tiwari, H.No. 268, Ward No. 4, Front of Govt. Warehouse, Chandla Road, Lavkush Nagar, Dist. Chhatarpur, MP – 471625,

This case was recommended in 463rd SEAC meeting dated 01.10.2020 and it was recorded that..........

“…………PP has submitted the response of above quarries same date vide letter dated 01.10.2020, which was placed before the committee and the same found satisfactory. The EMP and other submissions made by the PP were found to be satisfactory and acceptable, hence committee decided to recommend the case for grant of prior EC subject to the following special conditions in addition to the standard conditions at annexure ‘A’:

PP/Consultant made a presentation on all aspects of the project and all concerned issues were discussed in detail. After detailed discussions and perusal of recommendations of 463rd SEAC meeting dated 01.10.2020, presentation made by the PP in SEIAA, it was decided to accept the recommendation of SEAC for grant of prior EC to the project subject to the following specific conditions:-

I. Before commencing any mining activity fencing shall be carried out all around the lease area. Proper watch and ward arrangements should be made with installation of signage at 4 corners of lease area to avoid any untoward incident involving public and animals by the PP.

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 40 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020

II. PP shall not start mining activity before execution of lease agreement. III. The depth of the pit shall be as per the Approved Mining Plan. IV. The entire area shall be fenced and three rows of plantation should be done

on the periphery of the boundary and towards Pucca Road (SE direction), Kaccha Road (NE direction),.

V. Controlled blasting with arrangements of sand bags towards Pucca Road (SE direction), Kaccha Road & Isolated houses (NE direction),.

VI. PP ensure to left 20 m set back towards Kaccha road. VII. PP ensure that trees which are located in the lease barrier zone area shall be

kept intact. VIII. PP shall ensure that the proper water supply arrangements for dust

suppression, regular sprinkling, plantation and drinking purposes especially in summer season.

IX. PP shall ensure to construct and maintained the approach road. Plantation will be carried out on both side of approach road.

X. PP shall ensure proper implementation of plantation, dust suppression, construction of approach road and maintenance of existing road & as part of Environmental Management Plan. Additional budget provision shall be made as part of EMP.

XI. Total 4800 saplings of suitable tree species i.e. Neem, Pipal, Bargad, Mango, Amla, Amaltas, Drumstick etc. shall be planted by PP at barrier zone, Along boundary wall of schools with tree guards & 2400 saplings in identified area, Village –Bhulera Khasra no. 114/1(remaining part) and 118 under plantation programme. PP shall also explore and identify the chunk of land in the area from revenue record to carry out plantation programme as proposed.

XII. PP must ensure implementation of the following activities with separate budget provision of Rs 1.5 lakh/year under CER. 1st Year

Distribution of masks and sanitizers to villagers and conducting an awareness program through Panchayat for the protection from the spread of Corona virus (COVID 19 Pandemic)

Development of grazing land Maintenance of Gram Panchayat Office, Hakimpura

2nd & 3rd Year

Sports kit and Lab Equipments in Govt. High school, Rajnagar 4th & 5th Year Maintenance, Furniture and construction of boundary wall of Govt.

secondary school, Bariapurva

PP shall ensure to contruct toilet with proper plumbing in the school of above village and contribute on behalf of village in Jal Jeewan Mission in consultation with Janpad Panchayat and PHED. PP shall give preference to develop/provide infrastructural facilities in schools or aganwadies of above villages The modification to the above activities can be made with the permission of the district administration and need based activity for the development of nearby

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 41 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020

villages shall be implemented by PP in consultation with the District Collector and Gram Panchayat

XIII. PP should ensure to submit half yearly compliance report and CSR activity report with photographs of plantation in MP-SEIAA. If PP is failed to upload or submit two consecutive half yearly compliance reports of EC conditions to concerned authority (SEIAA and Regional Office, MoEF&CC,GoI,Bhopal) than prior environmental clearance issued to PP will automatically be treated as cancelled/ revoked as per OM No. 930/SEIAA/2019 dated 30.05.2019 issued by MPSEIAA.

Hence, Prior Environmental Clearance is granted for Stone Quarry (Opencast Manual / Semi Mechanized Method) in an area of 3.90 ha. for production capacity of 150000 cum / year at Khasra No. 114/1 at Village - Bhulera, Tehsil - Rajnagar, Dist. Chhatarpur for the lease period to M/s Ramraja Stone Crusher, Partner, Shri Sushil Tiwari, H.No. 268, Ward No. 4, Front of Govt. Warehouse, Chandla Road, Lavkush Nagar, Dist. Chhatarpur, MP – 471625,

15. Case No. 7779/2020; Prior Environmental Clearance for Stone Quarry (Opencast Manual/Semi Mechanized Method) in area of 1.012 ha. for production capacity of 3000 cum per annum at Khasra No. 192/7, 192/8 at Village - Rampurachakaldi, Tehsil - Rehti, Dist. Sehore, (MP) by Shri Manohar Singh Rajpoot S/o Late Shri Shankar Singh Rajpoot, R/o Indra Chowk, Dist. Hoshangabad, MP – 466446.

This case was recommended in 463rd SEAC dated 1/10/2020 it was recorded that..........

"------------ EMP and other submissions made by the PP were found to be satisfactory and acceptable, hence committee decided to recommend the case for grant of prior EC subject to the following special conditions in addition to the standard conditions at annexure ‘A’:

PP/Consultant made a presentation on all concerned issues were discussed in detail. After detailed discussions and perusal of recommendations of 463rdt SEAC meeting dated 1.10.2020, presentation made by the PP in SEIAA, it was decided to accept the recommendation of SEAC for grant of prior EC to the project subject to the following specific conditions:-

I. Before commencing any mining activity fencing shall be carried out all around the lease area. Proper watch and ward arrangements should be made with installation of signage at 4 corners of lease area to avoid any untoward incident involving public and animals by the PP.

II. PP shall not start mining activity before execution of lease agreement.

III. The depth of the pit shall be as per the Approved Mining Plan.

IV. The entire area shall be fenced and three rows of plantation should be done on the periphery of the boundary.

V. PP shall ensure the proper water supply arrangements for dust suppression, regular sprinkling, plantation and drinking purposes especially in summer season.

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 42 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020

VI. Total 1200 saplings of suitable tree species i.e. Neem, Pipal,Bargad,Gulmohar Amla etc. shall be planted in nearby Khasra No. 192(part) of Village – Rampurachakaldi, Tehsil - Rehti, Dist. Sehore MP by PP under plantation programme in consultation with DM at identified revenue land of the district. PP shall also explore and identify the chunk of land in the area from revenue record to carry out plantation programme as proposed.

VII. PP shall ensure proper implementation of plantation, dust suppression, construction of approach road and maintenance of existing pakka road as part of Environmental Management Plan. Additional budget provision shall be made as part of EMP.

VIII. PP must ensure implementation of the following activities with separate budget provision of total Rs 0.30 Lakh/Year under CER:

a) 1st Year: Provide to distribution of masks and sanitizers to villagers and conducting an awareness program through Panchayat for the protection from the spread of Corona virus (COVID 19 Pandemic) and development of grazing land

b) 2nd,3rd & 4th Year:Provide to whitewash, maintenance and furniture for Gram Panchayat building, Rampurachakaldi

c) 5th Year: Provide to whitewash,Furniture for Govt. senior secondary school of Chakaldi village

PP shall ensure to contruct toilet with proper plumbing in the school of above village and contribute on behalf of village in Jal Jeewan Mission in consultation with Janpad Panchayat and PHED. PP shall give preference to develop/provide infrastructural facilities in schools or aanganwadies of above villages. The modification to the above activities can be made with the permission of the district administration and need based activity for the development of nearby villages shall be implemented by PP in consultation with the District Collector and Gram Panchayat.

IX. PP should ensure to submit half yearly compliance report, Plantation and CER activity report along with photographs of all activities in MP-SEIAA. If PP is failed to upload or submit two consecutive half yearly compliance reports of EC conditions to concerned authority (SEIAA and Regional Office, MoEF&CC,GoI,Bhopal) than prior environmental clearance issued to PP will automatically be treated as cancelled/ revoked as per OM No. 930/SEIAA/2019 dated 30.05.2019 issued by MPSEIAA.

Hence, Prior Environmental Clearance is granted for Stone Quarry (Opencast Manual/Semi Mechanized Method) in area of 1.012 ha. for production capacity of 3000 cum per annum at Khasra No. 192/7, 192/8 at Village -

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 43 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020

Rampurachakaldi, Tehsil - Rehti, Dist. Sehore, (MP) for the lease period to Shri Manohar Singh Rajpoot S/o Late Shri Shankar Singh Rajpoot, R/o Indra Chowk, Dist. Hoshangabad, MP – 466446.

16. Case No. – 7749/2020 Prior Environmental Clearance for Stone Quarry (Opencast Manual / Semi Mechanized Method) in an area of 1.416 ha. for production capacity of 25000 cum / year at Khasra No. 1246/1, 1246/2 at Village - Dhanwaha, Tehsil - Tikamgarh, Dist. Tikamgarh (MP) by M/s A.V.S.Stone Crusher, Village - Aston, Tehsil - Tikamgarh, Dist. Tikamgarh, MP – 472005

This case was recommended in 463rd SEAC meeting dated 01.10.2020 and it was recorded that..........

“…………PP has submitted the response of above quarries same date vide letter dated 01.10.2020, which was placed before the committee and the same found satisfactory. The EMP and other submissions made by the PP were found to be satisfactory and acceptable, hence committee decided to recommend the case for grant of prior EC subject to the following special conditions in addition to the standard conditions at annexure ‘A’:

PP/Consultant made a presentation on all aspects of the project and all concerned issues were discussed in detail. After detailed discussions and perusal of recommendations of 463rd SEAC meeting dated 01.10.2020, presentation made by the PP in SEIAA, it was decided to accept the recommendation of SEAC for grant of prior EC to the project subject to the following specific conditions:-

I. Before commencing any mining activity fencing shall be carried out all around the lease area. Proper watch and ward arrangements should be made with installation of signage at 4 corners of lease area to avoid any untoward incident involving public and animals by the PP.

II. PP shall not start mining activity before execution of lease agreement. III. The depth of the pit shall be as per the Approved Mining Plan. IV. The entire area shall be fenced and three rows of plantation should be done

on the periphery of the boundary. V. PP shall ensure that the proper water supply arrangements for dust

suppression, regular sprinkling, plantation and drinking purposes especially in summer season.

VI. PP shall ensure to construct and maintained the approach road. Plantation will be carried out on both side of approach road.

VII. PP shall ensure proper implementation of plantation, dust suppression, construction of approach road and maintenance of existing road & as part of Environmental Management Plan. Additional budget provision shall be made as part of EMP.

VIII. Total 2000 saplings of suitable tree species i.e. Neem, Pipal, Bargad, Mango, Amla, Amaltas, Drumstick etc. shall be planted by PP at barrier zone, Along boundary wall of schools with tree guards & 900 saplings In identified area, village-Dhanwaha at Khasra No. 1250 under plantation programme. PP shall also explore and identify the chunk of land in the area from revenue record to carry out plantation programme as proposed.

IX. PP must ensure implementation of the following activities with separate budget provision of Rs 0.90 lakh/year under CER.

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 44 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020

1st Year - Distribution of masks and sanitizers to villagers and conducting an awareness program through Panchayat for the protection from the spread of Corona virus (COVID 19 Pandemic)

2nd Year -Development of grazing land 3rd Year - Construction of Boundary wall, periphery of handpump and

haud in Govt. School,Dhanwaha 4th Year -Furniture and sports kit for Govt. secondary school, Prakash

Bamhori 5th Year - Furniture, swings, slides & see-saw and maintenance of

boundary wall of Govt. Girls primary school, Khirkiya naka

PP shall ensure to contruct toilet with proper plumbing in the school of above village and contribute on behalf of village in Jal Jeewan Mission in consultation with Janpad Panchayat and PHED. shall give preference to develop/provide infrastructural facilities in schools or aganwadies of above villages The modification to the above activities can be made with the permission of the district administration and need based activity for the development of nearby villages shall be implemented by PP in consultation with the District Collector and Gram Panchayat

X. PP should ensure to submit half yearly compliance report and CSR activity report with photographs of plantation in MP-SEIAA. If PP is failed to upload or submit two consecutive half yearly compliance reports of EC conditions to concerned authority (SEIAA and Regional Office, MoEF&CC,GoI,Bhopal) than prior environmental clearance issued to PP will automatically be treated as cancelled/ revoked as per OM No. 930/SEIAA/2019 dated 30.05.2019 issued by MPSEIAA.

Hence, Prior Environmental Clearance is granted for Stone Quarry (Opencast Manual / Semi Mechanized Method) in an area of 1.416 ha. for production capacity of 25000 cum / year at Khasra No. 1246/1, 1246/2 at Village - Dhanwaha, Tehsil - Tikamgarh, Dist. Tikamgarh (MP) for the lease period to M/s A.V.S.Stone Crusher, Village - Aston, Tehsil - Tikamgarh, Dist. Tikamgarh, MP

17. Case No. – 7794/2020 Prior Environmental Clearance for Murrum Quarry (Opencast Manual / Semi Mechanized Method) in an area of 1.0 ha. for production capacity of 6000 cum/ year at Khasra No. 47P at Village - Dharampura, Tehsil - Tikamgarh, Dist. Tikamgarh, (MP) by Shri Neeraj Yadav S/o Shri Sobran Yadav, Village - Dharampura, tehsil & Dist. Tikamgarh, MP – 472115

This case was recommended in 463rd SEAC meeting dated 01.10.2020 and it was recorded that..........

“…………PP has submitted the response of above quarries same date vide letter dated 01.10.2020, which was placed before the committee and the same found satisfactory. The EMP and other submissions made by the PP were found to be satisfactory and acceptable, hence committee decided to recommend the case for

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 45 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020

grant of prior EC subject to the following special conditions in addition to the standard conditions at annexure ‘A’:

PP/Consultant made a presentation on all aspects of the project and all concerned issues were discussed in detail. After detailed discussions and perusal of recommendations of 463rd SEAC meeting dated 01.10.2020, presentation made by the PP in SEIAA, it was decided to accept the recommendation of SEAC for grant of prior EC to the project subject to the following specific conditions:-

I. Before commencing any mining activity fencing shall be carried out all around the lease area. Proper watch and ward arrangements should be made with installation of signage at 4 corners of lease area to avoid any untoward incident involving public and animals by the PP.

II. PP shall not start mining activity before execution of lease agreement. III. The depth of the pit shall be as per the Approved Mining Plan. IV. The entire area shall be fenced and three rows of plantation should be done

on the periphery of the boundary. V. PP ensure that the Natural Drain Within the lease area shall be dealt as no-

mining area South west to south East direction VI. PP shall ensure that the proper water supply arrangements for dust

suppression, regular sprinkling, plantation and drinking purposes especially in summer season.

VII. PP shall leave 20 m set back from the road as no mining zone. VIII. PP shall ensure to construct and maintained the approach road. Plantation

will be carried out on both side of approach road. IX. PP shall ensure proper implementation of plantation, dust suppression,

construction of approach road and maintenance of existing road & as part of Environmental Management Plan. Additional budget provision shall be made as part of EMP.

X. Total 1200 saplings of suitable tree species i.e. Neem, Pipal, Bargad, Mango, Amla, Amaltas, Drumstick etc. shall be planted by PP at barrier zone, & 400 saplings In khasra no. 47 and in non mining zone vill-Dharmpura, teh.-Tikamgarh under plantation programme. PP shall also explore and identify the chunk of land in the area from revenue record to carry out plantation programme as proposed.

XI. PP must ensure implementation of the following activities with separate budget provision of Rs 0.30 lakh/year under CER.

1st Year

Distribution of masks and sanitizers to villagers and conducting an awareness program through Panchayat for the protection from the spread of Corona virus (COVID 19 Pandemic)

Development of grazing land Whitewash in Govt. primary school of Dharmpura

2nd Year & 3rd Year Maintenance, Furniture's and whitewash of Samudayik kendra,Dharmpura

4th Year & 5th Year Construction of boundary wall of Govt. Secondary school, Bauri

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 46 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020

PP shall ensure to contruct toilet with proper plumbing in the school of above village and contribute on behalf of village in Jal Jeewan Mission in consultation with Janpad Panchayat and PHED. PP shall give preference to develop/provide infrastructural facilities in schools or aganwadies of above villages The modification to the above activities can be made with the permission of the district administration and need based activity for the development of nearby villages shall be implemented by PP in consultation with the District Collector and Gram Panchayat

XII. PP should ensure to submit half yearly compliance report and CSR activity report with photographs of plantation in MP-SEIAA. If PP is failed to upload or submit two consecutive half yearly compliance reports of EC conditions to concerned authority (SEIAA and Regional Office, MoEF&CC,GoI,Bhopal) than prior environmental clearance issued to PP will automatically be treated as cancelled/ revoked as per OM No. 930/SEIAA/2019 dated 30.05.2019 issued by MPSEIAA.

Hence, Prior Environmental Clearance is granted for Murrum Quarry (Opencast Manual / Semi Mechanized Method) in an area of 1.0 ha. for production capacity of 6000 cum/ year atKhasra No. 47P at Village - Dharampura, Tehsil - Tikamgarh, Dist. Tikamgarh, (MP) for the lease period to Shri Neeraj Yadav S/o Shri Sobran Yadav, Village - Dharampura, tehsil & Dist. Tikamgarh, MP – 472115

18. Case No. – 7795/2020 Prior Environment Clearance for Stone Quarry (Opencast Semi Mechanized Method) in an area of 1.969 ha. for production capacity of 100000 cum / year at Khasra No. 4595/7, 4595/8 at Village - Gahbara, Tehsil - Gaurihar, Dist. Chhatarpur, (MP) by Shri Aniruddha Singh S/o Shri Vijay Singh, Village - Jyoraha, Tehsil - Lavkushnagar, Dist. Chhatarpur, MP – 471516 This case was recommended in 463rd SEAC meeting dated 01.10.2020 and it was recorded that..........

“…………PP further submits that the method of mining will be opencast semi-mechanized and mine will attain a depth of mining 24m after 05 years. The EMP and other submissions made by the PP were found to be satisfactory and acceptable, hence committee decided to recommend the case for grant of prior EC subject to the following special conditions in addition to the standard conditions at annexure ‘A’:

PP/Consultant made a presentation on all aspects of the project and all concerned issues were discussed in detail. After detailed discussions and perusal of recommendations of 463rd SEAC meeting dated 01.10.2020, presentation made by the PP in SEIAA, it was observed that there are other mines exist in 500 m radius which is making cluster situation hence it was decided to seek clarification from Mining Officer , Chhatarpur about current status of other mines exist within 500 m of above said mine.

19. Case No. 7792/20 Prior Environmental Clearance for Stone Quarry (opencast manual/semi mechanized method) in an area of 1.0 ha. (9998 cum per annum)

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 47 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020

(Khasra No. 1/18), Village - Gajandoh, Tehsil - Umreth, Dist. - Chhindwara, (MP) by Shri Rohit Kaithwas S/o Shri Kishore Kaithwas, R/o Ward No. 21, Parasia, Dist. - Chhindwara, MP - 480557, Email - [email protected], Mobile - 9407055948.

This case was recommended in 463rd SEAC meeting dated 01.10.2020 and it was recorded that..........

“----------The EMP and other submissions made by the PP were found to be satisfactory and acceptable, hence committee decided to recommend the case for grant of prior EC subject to the following special conditions in addition to the standard conditions at annexure ‘A’:

PP/Consultant made a presentation on all aspects of the project and all concerned issues were discussed in detail. After detailed discussions and perusal of recommendations of 463rd SEAC meeting dated 01.10.2020, presentation made by the PP in SEIAA, it was decided to accept the recommendation of SEAC for grant of prior EC to the project subject to the following specific conditions:-

i. Before commencing any mining activity fencing shall be carried out all around the lease area. Proper watch and ward arrangements should be made with installation of signage at 4 corners of lease area to avoid any untoward incident involving public and animals by the PP.

ii. PP shall not start mining activity before execution of lease agreement.

iii. The depth of the pit shall be as per the Approved Mining Plan.

iv. The entire area shall be fenced and three rows of plantation should be done on the periphery of the boundary.

v. PP shall ensure to construct garland drain with settling tank all around the lease area and regular cleaning & maintenance shall also be carried out by PP.

vi. PP shall ensure the proper water supply arrangements for dust suppression, regular sprinkling, plantation and drinking purposes especially in summer season.

vii. Total 1200 saplings of suitable tree species i.e. Neem, Pipal, Bargad, Mango, Gulmohar, Sissoo, Kathal, etc. shall be planted by PP in first three years under plantation programme at mine lease boundary and at private waste land at khasra no. 1/18 in consultation with Gram Panchayat/ DM. PP shall also explore and identify the chunk of land in the area from revenue record to carry out plantation programme as proposed.

viii. PP shall ensure proper implementation of plantation, dust suppression, construction of approach road and maintenance of existing pakka road as part of Environmental Management Plan. Additional budget provision shall be made as part of EMP.

ix. PP must ensure implementation of the following activities with separate budget provision of Rs. 50,000/year under CER as committed:

a) 1st year (Village – Gajandoh): To provide Water Filter at Village School - Rs. 10,000/- To provide Swings & Slides to Village School – Rs.40,000/-

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 48 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020

b) 2nd year (Village – Gajandoh): Whitewash at Village School Campus.

c) 3rd, 4th & 5th year (Village – Gajandoh): To provide 05 Computers at Village High School (Rs. 30000 Each)

PP shall ensure to contruct toilet with proper plumbing in the school of above village and contribute on behalf of village in Jal Jeewan Mission in consultation with Janpad Panchayat and PHED. PP shall give preference to develop/provide infrastructural facilities in schools or aanganwadies of above villages. The modification to the above activities can be made with the permission of the district administration and need based activity for the development of nearby villages shall be implemented by PP in consultation with the District Collector and Gram Panchayat.

x. PP should ensure to submit half yearly compliance report, Plantation and CER activity report along with photographs of all activities in MP-SEIAA. If PP is failed to upload or submit two consecutive half yearly compliance reports of EC conditions to concerned authority (SEIAA and Regional Office, MoEF&CC,GoI,Bhopal) than prior environmental clearance issued to PP will automatically be treated as cancelled/ revoked as per OM No. 930/SEIAA/2019 dated 30.05.2019 issued by MPSEIAA.

Hence, Prior Environmental Clearance is granted for Stone Quarry (opencast manual/semi mechanized method) in an area of 1.0 ha. (9998 cum per annum) (Khasra No. 1/18), Village - Gajandoh, Tehsil - Umreth, Dist. - Chhindwara, (MP) for the lease period to Shri Rohit Kaithwas S/o Shri Kishore Kaithwas, R/o Ward No. 21, Parasia, Dist. - Chhindwara, MP - 480557, Email - [email protected], Mobile - 9407055948.

20. Case No. 7798/20 Prior Environmental Clearance for Stone Quarry (opencast manual/semi mechanized method) in an area of 1.0 ha. (13999 cum per annum) (Khasra No. 378/1/2, 378/3, 378/8), Village - Sirgora, Tehsil - Parasia, Dist. - Chhindwara, (MP) by Shri Dheeraj Shah S/o Shri Ganpat Shah, R/o Near Railway Station, Parasia, Dist. - Chhindwara, MP - 480441, Email - [email protected], Mobile – 9407055948.

This case was recommended in 463rd SEAC meeting dated 01.10.2020 and it was recorded that..........

“------------PP has submitted the response of above quarries same date vide letter dated 01.10.2020, which was placed before the committee and the same found satisfactory. The EMP and other submissions made by the PP were found to be satisfactory and acceptable, hence committee decided to recommend the case for grant of prior EC subject to the following special conditions in addition to the standard conditions at annexure ‘A’:

PP/Consultant made a presentation on all aspects of the project and all concerned issues were discussed in detail. After detailed discussions and perusal of recommendations of 463rd SEAC meeting dated 01.10.2020, presentation made by the PP in SEIAA, it was decided to accept the recommendation of SEAC for grant of prior EC to the project subject to the following specific conditions:-

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 49 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020

i. Before commencing any mining activity fencing shall be carried out all around the lease area. Proper watch and ward arrangements should be made with installation of signage at 4 corners of lease area to avoid any untoward incident involving public and animals by the PP.

ii. PP shall not start mining activity before execution of lease agreement.

iii. The depth of the pit shall be as per the Approved Mining Plan.

iv. The entire area shall be fenced and three rows of plantation should be done on the periphery of the boundary.

v. PP shall ensure the controlled blasting with arrangements of sand bags and three rows of plantation towards road side (south, east).

vi. PP shall ensure the proper water supply arrangements for dust suppression, regular sprinkling, plantation and drinking purposes especially in summer season.

vii. Total 1200 saplings of suitable tree species i.e. Neem, Pipal, Bargad, Mango, Gulmohar, Sissoo, Kathal, etc. shall be planted by PP in first three years under plantation programme at mine lease boundary and at private waste land at khasra no. 378/3 in consultation with Gram Panchayat/ DM. PP shall also explore and identify the chunk of land in the area from revenue record to carry out plantation programme as proposed.

viii. PP shall ensure proper implementation of plantation, dust suppression, construction of approach road and maintenance of existing pakka road as part of Environmental Management Plan. Additional budget provision shall be made as part of EMP.

ix. PP must ensure implementation of the following activities with separate budget provision of Rs. 50,000/year under CER as committed:

a) 1st, 2nd & 3rd year (Village – Sirgora): Maintenance Work of Primary School Building (School Building Roof

will be changed by New Khaprel). b) 4th year (Village – Sirgora):

To provide Water Filter at Village School with overhead water tank - Rs. 15,000/-

To provide Swings & Slides to Village School – Rs.35,000/- c) 5th year (Village – Sirgora):

To provide Bench’s at Govt primary School (25 Nos)

PP shall ensure to contruct toilet with proper plumbing in the school of above village and contribute on behalf of village in Jal Jeewan Mission in consultation with Janpad Panchayat and PHED. PP shall give preference to develop/provide infrastructural facilities in schools or aanganwadies of above villages. The modification to the above activities can be made with the permission of the district administration and need based activity for the development of nearby villages shall be implemented by PP in consultation with the District Collector and Gram Panchayat.

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 50 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020

x. PP should ensure to submit half yearly compliance report, Plantation and CER activity report along with photographs of all activities in MP-SEIAA. If PP is failed to upload or submit two consecutive half yearly compliance reports of EC conditions to concerned authority (SEIAA and Regional Office, MoEF&CC,GoI,Bhopal) than prior environmental clearance issued to PP will automatically be treated as cancelled/ revoked as per OM No. 930/SEIAA/2019 dated 30.05.2019 issued by MPSEIAA.

Hence, Prior Environmental Clearance is granted for Stone Quarry (opencast manual/semi mechanized method) in an area of 1.0 ha. (13999 cum per annum) (Khasra No. 378/1/2, 378/3, 378/8), Village - Sirgora, Tehsil - Parasia, Dist. - Chhindwara, (MP) for the lease period to Shri Dheeraj Shah S/o Shri Ganpat Shah, R/o Near Railway Station, Parasia, Dist. - Chhindwara, MP - 480441, Email - [email protected], Mobile – 9407055948.

21. Case No 7804/2020 Prior Environmental Clearance for Stone Quarry (Opencast Manual / Semi Mechanized Method) in an area of 4.0 ha. for production capacity of 28500 cum / year at Khasra No. 01 at Village - Nigrani, Tehsil - Manawar, Dist. Dhar, (MP) by Shri Vinod Patidar S/o Shri Dhartilal Patidar, Manawar, Dist. Dhar, MP – 454446.

This case was recommended in 463rd SEAC meeting dated 01.10.2020 and it was recorded that..........

“…………The EMP and other submissions made by the PP were found to be satisfactory and acceptable, hence committee decided to recommend the case for grant of prior EC subject to the following special conditions in addition to the standard conditions at annexure ‘A’:”

PP/Consultant made a presentation on all aspects of the project and all concerned issues were discussed in detail. After detailed discussions and perusal of recommendations of 463rd SEAC meeting dated 01.10.2020, presentation made by the PP in SEIAA, it was decided to accept the recommendation of SEAC for grant of prior EC to the project subject to the following specific conditions:-

I. Before commencing any mining activity fencing shall be carried out all around the lease area. Proper watch and ward arrangements should be made with installation of signage at 4 corners of lease area to avoid any untoward incident involving public and animals by the PP.

II. PP shall not start mining activity before execution of lease agreement. III. The depth of the pit shall be as per the Approved Mining Plan. IV. The entire area shall be fenced and three rows of plantation should be done

on the periphery of the boundary and towards PMGSY Pucca road (North direction) and towards Human settlement North East direction.

V. Controlled blasting with arrangements of sand bags towards PMGSY Pucca road (North direction) and towards Human settlement North East direction.

VI. PP shall ensure that the proper water supply arrangements for dust suppression, regular sprinkling, plantation and drinking purposes especially in summer season.

VII. PP shall ensure to construct and maintained the approach road. Plantation will be carried out on both side of approach road.

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 51 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020

VIII. PP shall ensure proper implementation of plantation, dust suppression, construction of approach road and maintenance of existing road & as part of Environmental Management Plan. Additional budget provision shall be made as part of EMP.

IX. Total 4800 saplings of suitable tree species i.e. Neem, Pipal, Bargad, Mango, Amla, Amaltas, Drumstick etc. shall be planted by PP at mine lease boundary & 2800 saplings at Remaining Private Waste land khasra no. 01 under plantation programme. PP shall also explore and identify the chunk of land in the area from revenue record to carry out plantation programme as proposed.

X. PP must ensure implementation of the following activities with separate budget provision of Rs 2.50 lakh under CER.

1st Year to 5th Year at Nigarni Village

Whitewash Of Primary & Middle School – 10,000/- Construction of Middle School Boundary Wall ( 40m Length ) – 1,20,000/- Construction of Primary School Boundary Wall ( 40m Length) - 1,20,000

PP shall ensure to contruct toilet with proper plumbing in the school of above village and contribute on behalf of village in Jal Jeewan Mission in consultation with Janpad Panchayat and PHED. PP shall give preference to develop/provide infrastructural facilities in schools or aganwadies of above villages The modification to the above activities can be made with the permission of the district administration and need based activity for the development of nearby villages shall be implemented by PP in consultation with the District Collector and Gram Panchayat

XI. PP should ensure to submit half yearly compliance report and CSR activity report with photographs of plantation in MP-SEIAA. If PP is failed to upload or submit two consecutive half yearly compliance reports of EC conditions to concerned authority (SEIAA and Regional Office, MoEF&CC,GoI,Bhopal) than prior environmental clearance issued to PP will automatically be treated as cancelled/ revoked as per OM No. 930/SEIAA/2019 dated 30.05.2019 issued by MPSEIAA.

Hence, Prior Environmental Clearance is granted for Stone Quarry (Opencast Manual / Semi Mechanized Method) in an area of 4.0 ha. for production capacity of 28500 cum / year at Khasra No. 01 at Village - Nigrani, Tehsil - Manawar, Dist. Dhar, (MP) for the lease period to Shri Vinod Patidar S/o Shri Dhartilal Patidar, Manawar, Dist. Dhar, MP – 454446

22. Case No. 7750/20 Prior Environmental Clearance for Stone Quarry (opencast manual/semi mechanized method) in an area of 1.320 ha. (9998 cum per annum) (Khasra No. 11 (Part)), Village - Ratana Mal, Tehsil - Bajag, Dist. - Dindori (MP) by Shri Rajiv Kumar Sahu S/o Shri Shambhu Prasad Sahu, Village - Gadasarai, Tehsil

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 52 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020

- Bajag, Dist. - Dindori, MP - 481884, Email - [email protected], Mobile – 9407055948.

This case was recommended in 463rd SEAC meeting dated 01.10.2020 and it was recorded that..........

“----------The EMP and other submissions made by the PP were found to be satisfactory and acceptable, hence committee decided to recommend the case for grant of prior EC subject to the following special conditions in addition to the standard conditions at annexure ‘A’:

PP/Consultant made a presentation on all aspects of the project and all concerned issues were discussed in detail. After detailed discussions and perusal of recommendations of 463rd SEAC meeting dated 01.10.2020, presentation made by the PP in SEIAA, it was decided to accept the recommendation of SEAC for grant of prior EC to the project subject to the following specific conditions:-

i. Before commencing any mining activity fencing shall be carried out all around the lease area. Proper watch and ward arrangements should be made with installation of signage at 4 corners of lease area to avoid any untoward incident involving public and animals by the PP.

ii. PP shall not start mining activity before execution of lease agreement.

iii. The depth of the pit shall be as per the Approved Mining Plan.

iv. The entire area shall be fenced and three rows of plantation should be done on the periphery of the boundary.

v. PP shall ensure the controlled blasting with arrangements of sand bags and three rows of plantation towards road side (south-west & south-east).

vi. PP shall ensure the proper water supply arrangements for dust suppression, regular sprinkling, plantation and drinking purposes especially in summer season.

vii. Total 1500 saplings of suitable tree species i.e. Neem, Pipal, Bargad, Mango, Gulmohar, Sissoo, Kathal, etc. shall be planted by PP in first three years under plantation programme at mine lease boundary and at private waste land at khasra no. 11 in consultation with Gram Panchayat/ DM. PP shall also explore and identify the chunk of land in the area from revenue record to carry out plantation programme as proposed.

viii. PP shall ensure proper implementation of plantation, dust suppression, construction of approach road and maintenance of existing pakka road as part of Environmental Management Plan. Additional budget provision shall be made as part of EMP.

xi. PP must ensure implementation of the following activities with separate budget provision of total Rs. 2.0 lakh under CER as committed:

a) 1st, 2nd, 3rd, 4th & 5th year (Village – Ratna Mal): To provide Water Filter at Village School - Rs. 10,000/- To provide Swings & Slides to Village School – Rs.20,000/- To provide Bench’s at Govt primary School ( 30 Nos) – 60,000/- Construction of School Boundary Wall ( 35m Length) - 1,10,000

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 53 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020

PP shall ensure to contruct toilet with proper plumbing in the school of above village and contribute on behalf of village in Jal Jeewan Mission in consultation with Janpad Panchayat and PHED. PP shall give preference to develop/provide infrastructural facilities in schools or aanganwadies of above villages. The modification to the above activities can be made with the permission of the district administration and need based activity for the development of nearby villages shall be implemented by PP in consultation with the District Collector and Gram Panchayat.

ix. PP should ensure to submit half yearly compliance report, Plantation and CER activity report along with photographs of all activities in MP-SEIAA. If PP is failed to upload or submit two consecutive half yearly compliance reports of EC conditions to concerned authority (SEIAA and Regional Office, MoEF&CC,GoI,Bhopal) than prior environmental clearance issued to PP will automatically be treated as cancelled/ revoked as per OM No. 930/SEIAA/2019 dated 30.05.2019 issued by MPSEIAA.

Hence, Prior Environmental Clearance is granted for Stone Quarry (opencast manual/semi mechanized method) in an area of 1.320 ha. (9998 cum per annum) (Khasra No. 11 (Part)), Village - Ratana Mal, Tehsil - Bajag, Dist. - Dindori (MP) for the lease period to Shri Rajiv Kumar Sahu S/o Shri Shambhu Prasad Sahu, Village - Gadasarai, Tehsil - Bajag, Dist. - Dindori, MP - 481884, Email - [email protected], Mobile – 9407055948.

23. Case No. – 7799/2020 Prior Environment Clearance for Stone Quarry (Opencast Manual / Semi Mechanized Method) in an area of 3.60 ha. for production capacity of 150000 cum / year at Khasra No. 162/1/1, 162/1/2, 162/1/3 at Village - Itwan, Tehsil - Lavkushnagar, Dist. Chhatarpur, (MP) by M/s Shiva Mines & Minerals, R/o A-803, DB City, Sachin Tendulkar Marg, City Centre, Dist. Gwalior, MP - 485774

This case was recommended in 463rd SEAC meeting dated 01.10.2020 and it was recorded that..........

“…………The EMP and other submissions made by the PP were found to be satisfactory and acceptable, hence committee after deliberation found that The EMS and other submissions made by the PP were found to be satisfactory and acceptable, hence committee decided to recommend the case for grant of prior EC subject to the following special conditions in addition to the standard conditions at annexure ‘A’:”

PP/Consultant made a presentation on all aspects of the project and all concerned issues were discussed in detail. After detailed discussions and perusal of recommendations of 463rd SEAC meeting dated 01.10.2020, presentation made by the PP in SEIAA, it was decided to accept the recommendation of SEAC for grant of prior EC to the project subject to the following specific conditions:-

I. Before commencing any mining activity fencing shall be carried out all around the lease area. Proper watch and ward arrangements should be made with installation of signage at 4 corners of lease area to avoid any untoward incident involving public and animals by the PP.

II. PP shall not start mining activity before execution of lease agreement. III. The depth of the pit shall be as per the Approved Mining Plan.

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 54 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020

IV. The entire area shall be fenced and three rows of plantation should be done on the periphery of the boundary and PP shall raise thick plantation in southern part of the lease area.

V. PP ensure that the existing 09 trees within lease are proposed felling for which PP will take permission from competent authority and 90 trees shall be additionally planted, and other trees which are located in the barrier zone shall be kept intact.

VI. PP shall ensure that the proper water supply arrangements for dust suppression, regular sprinkling, plantation and drinking purposes especially in summer season.

VII. PP shall ensure to construct and maintained the approach road. Plantation will be carried out on both side of approach road.

VIII. PP shall ensure proper implementation of plantation, dust suppression, construction of approach road and maintenance of existing road & as part of Environmental Management Plan. Additional budget provision shall be made as part of EMP.

IX. Total 4320 saplings of suitable tree species i.e. Neem, Pipal, Bargad, Mango, Amla, Amaltas, Drumstick etc. shall be planted by PP 2730 saplings in village (Khasara No. 737/1 , 737/2) under plantation programme. PP shall also explore and identify the chunk of land in the area from revenue record to carry out plantation programme as proposed.

X. PP must ensure implementation of the following activities with separate budget provision of Rs 5.0 lakh under CER. Providing infrastructure support to the village school- Providing

infrastructure support like play ground, furniture, boundary wall, toilets, etc to the village school at Itwan (Rs. 3.60 lakh)

To developed grazing land at Suitable grass species will be shown in the grazing land of the village area. (Rs. 0.10 lakh)

Provision of PPE Kit, sanitizers equipment, Mask etc. At Aganwadi and PHC of Itwan (Rs. 0.30 lakh)

Facilitation work for implementation of programme under Jal Jivan Mission - Contribution of fund or execution of plumbing network for implementation of Jal Jivan Scheme with to villagers houses in Itwan and other villages in consultation with the local administration. (Rs. 1.0 lakh)

PP shall ensure to contruct toilet with proper plumbing in the school of above village and contribute on behalf of village in Jal Jeewan Mission in consultation with Janpad Panchayat and PHED. PP shall give preference to develop/provide infrastructural facilities in schools or aganwadies of above villages The modification to the above activities can be made with the permission of the district administration and need based activity for the development of nearby villages shall be implemented by PP in consultation with the District Collector and Gram Panchayat

XI. PP should ensure to submit half yearly compliance report and CSR activity report with photographs of plantation in MP-SEIAA. If PP is failed to upload

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 55 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020

or submit two consecutive half yearly compliance reports of EC conditions to concerned authority (SEIAA and Regional Office, MoEF&CC,GoI,Bhopal) than prior environmental clearance issued to PP will automatically be treated as cancelled/ revoked as per OM No. 930/SEIAA/2019 dated 30.05.2019 issued by MPSEIAA.

Hence, Prior Environmental Clearance is granted for Stone Quarry (Opencast Manual / Semi Mechanized Method) in an area of 3.60 ha. for production capacity of 150000 cum / year at Khasra No. 162/1/1, 162/1/2, 162/1/3 at Village - Itwan, Tehsil - Lavkushnagar, Dist. Chhatarpur, (MP) for the lease period to M/s Shiva Mines & Minerals, R/o A-803, DB City, Sachin Tendulkar Marg, City Centre, Dist. Gwalior, MP - 485774

24. Case No. – 7800/2020 Prior Environmental Clearance for Stone Quarry (Opencast Manual / Semi Mechanized Method) in an area of 1.358 ha. for production capacity of 30000 cum / year at Khasra No. 116, 118, 119, 120 at Village - Itwan Tehsil - Lavkushnagar, Dist. Chhatarpur, (MP) by M/s Shiva Mines & Minerals, R/o A-803, DB City, Sachin Tendulkar Marg, City Centre, Dist. Gwalior, MP – 485774

This case was recommended in 463rd SEAC meeting dated 01.10.2020 and it was recorded that..........

“…………PP has submitted the response of above quarries same date vide letter dated 01.10.2020, which was placed before the committee and the same found satisfactory. The EMP and other submissions made by the PP were found to be satisfactory and acceptable, hence committee after deliberation found that The EMS and other submissions made by the PP were found to be satisfactory and acceptable, hence committee decided to recommend the case for grant of prior EC subject to the following special conditions in addition to the standard conditions at annexure ‘A’:”

PP/Consultant made a presentation on all aspects of the project and all concerned issues were discussed in detail. After detailed discussions and perusal of recommendations of 463rd SEAC meeting dated 01.10.2020, presentation made by the PP in SEIAA, it was decided to accept the recommendation of SEAC for grant of prior EC to the project subject to the following specific conditions:-

I. Before commencing any mining activity fencing shall be carried out all around the lease area. Proper watch and ward arrangements should be made with installation of signage at 4 corners of lease area to avoid any untoward incident involving public and animals by the PP.

II. PP shall not start mining activity before execution of lease agreement. III. The depth of the pit shall be as per the Approved Mining Plan. IV. The entire area shall be fenced and three rows of plantation should be done

on the periphery of the boundary. V. PP shall ensure to construct garland drain with settling tank all around the

lease area and regular cleaning & maintenance shall also be carried out by PP.

VI. PP shall ensure that the proper water supply arrangements for dust suppression, regular sprinkling, plantation and drinking purposes especially in summer season.

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 56 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020

VII. PP shall ensure to construct and maintained the approach road. Plantation will be carried out on both side of approach road.

VIII. PP shall ensure proper implementation of plantation, dust suppression, construction of approach road and maintenance of existing road & as part of Environmental Management Plan. Additional budget provision shall be made as part of EMP.

IX. Total 1700 saplings of suitable tree species i.e. Neem, Pipal, Bargad, Mango, Amla, Amaltas, Drumstick etc. shall be planted by PP 700 saplings In Itwan village (Khasara No. 738/1)under plantation programme. PP shall also explore and identify the chunk of land in the area from revenue record to carry out plantation programme as proposed.

X. PP must ensure implementation of the following activities with separate budget provision of Rs 2.20 lakh under CER. Providing infrastructure support to the village school- Providing

infrastructure support like play ground, furniture, boundary wall, toilets, etc to the village school at Itwan (Rs. 1.0 lakh)

To developed grazing land at Suitable grass species will be shown in the grazing land of the village area. (Rs. 0.10 lakh)

Provision of thermo and oxi-meters, sanitizers equipment, Mask etc. Govt. Primary School, Itwan (Rs. 0.10 lakh)

Facilitation work for implementation of programme under Jal Jivan Mission - Contribution of fund or execution of plumbing network for implementation of Jal Jivan Scheme with to villagers houses in Itwan and other villages in consultation with the local administration. (Rs. 1.0 lakh)

PP shall ensure to contruct toilet with proper plumbing in the school of above village and contribute on behalf of village in Jal Jeewan Mission in consultation with Janpad Panchayat and PHED. PP shall give preference to develop/provide infrastructural facilities in schools or aganwadies of above villages The modification to the above activities can be made with the permission of the district administration and need based activity for the development of nearby villages shall be implemented by PP in consultation with the District Collector and Gram Panchayat

XI. PP should ensure to submit half yearly compliance report and CSR activity report with photographs of plantation in MP-SEIAA. If PP is failed to upload or submit two consecutive half yearly compliance reports of EC conditions to concerned authority (SEIAA and Regional Office, MoEF&CC,GoI,Bhopal) than prior environmental clearance issued to PP will automatically be treated as cancelled/ revoked as per OM No. 930/SEIAA/2019 dated 30.05.2019 issued by MPSEIAA.

Hence, Prior Environmental Clearance is granted for Stone Quarry (Opencast Manual / Semi Mechanized Method) in an area of 1.358 ha. for production capacity of 30000 cum / year at Khasra No. 116, 118, 119, 120 at Village - Itwan Tehsil - Lavkushnagar, Dist. Chhatarpur, (MP) for the lease period to M/s Shiva

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 57 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020

Mines & Minerals, R/o A-803, DB City, Sachin Tendulkar Marg, City Centre, Dist. Gwalior, MP – 485774

25. Case No. 7567/20 Prior Environmental Clearance for Stone Quarry (opencast manual/semi mechanized method) in an area of 2.580 ha. (43947 cum per annum) (Khasra No. 156 & 157 Part), Village - Bahera West, Tehsil - Gopad Banas, Dist. - Sidhi (MP) by Shri Jai Bahadur Singh S/o Shri Surendra Pratap Singh, R/o South Karoudiya, Tehsil - Gopad Banas, Dist. - Sidhi, MP, Email - [email protected], Mobile – 9425177894.

This case was recommended in 463rd SEAC meeting dated 01.10.2020 and it was recorded that..........

“------------The EMP and other submissions made by the PP were found to be satisfactory and acceptable, hence committee after deliberation found that The EMS and other submissions made by the PP were found to be satisfactory and acceptable, hence committee decided to recommend the case for grant of prior EC subject to the following special conditions in addition to the standard conditions at annexure ‘A’:

PP/Consultant made a presentation on all aspects of the project and all concerned issues were discussed in detail. After detailed discussions and perusal of recommendations of 463rd SEAC meeting dated 01.10.2020, presentation made by the PP in SEIAA, it was decided to accept the recommendation of SEAC for grant of prior EC to the project subject to the following specific conditions:-

i. Before commencing any mining activity fencing shall be carried out all around the lease area. Proper watch and ward arrangements should be made with installation of signage at 4 corners of lease area to avoid any untoward incident involving public and animals by the PP.

ii. PP shall not start mining activity before execution of lease agreement.

iii. The depth of the pit shall be as per the Approved Mining Plan.

iv. The entire area shall be fenced and three rows of plantation should be done on the periphery of the boundary.

v. PP shall ensure the proper water supply arrangements for dust suppression, regular sprinkling, plantation and drinking purposes especially in summer season.

vi. Total 3120 saplings of suitable tree species i.e. Neem, Pipal, Bargad, Mango, Gulmohar, Sissoo, Jamun, Drumstick etc. shall be planted by PP in first three years under plantation programme at mine lease boundary andhilly terrain Govt. land khasra no. 147 in consultation with Gram Panchayat/ DM. PP shall also explore and identify the chunk of land in the area from revenue record to carry out plantation programme as proposed.

vii. PP shall ensure proper implementation of plantation, dust suppression, construction of approach road and maintenance of existing pakka road as part of Environmental Management Plan. Additional budget provision shall be made as part of EMP.

viii. PP must ensure implementation of the following activities with separate budget provision of total Rs. 5.25 lakh under CER as committed:

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 58 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020

a) Village – Bahera West: Distribution of masks and sanitizers to villagers for 1st year only. Development and maintenance of grassland on a nearby suitable

government land (from 1st to 5th year). Boundary wall construction of the adjacent open government land

including its levelling and developing it as a playground for primary school students.

Supply of basic school furniture and other necessary items as needed.

Maintenance of approach roads to village school.

PP shall ensure to contruct toilet with proper plumbing in the school of above village and contribute on behalf of village in Jal Jeewan Mission in consultation with Janpad Panchayat and PHED. PP shall give preference to develop/provide infrastructural facilities in schools or aanganwadies of above villages. The modification to the above activities can be made with the permission of the district administration and need based activity for the development of nearby villages shall be implemented by PP in consultation with the District Collector and Gram Panchayat.

ix. PP should ensure to submit half yearly compliance report, Plantation and CER activity report along with photographs of all activities in MP-SEIAA. If PP is failed to upload or submit two consecutive half yearly compliance reports of EC conditions to concerned authority (SEIAA and Regional Office, MoEF&CC,GoI,Bhopal) than prior environmental clearance issued to PP will automatically be treated as cancelled/ revoked as per OM No. 930/SEIAA/2019 dated 30.05.2019 issued by MPSEIAA.

Hence, Prior Environmental Clearance is granted for Stone Quarry (opencast manual/semi mechanized method) in an area of 2.580 ha. (43947 cum per annum) (Khasra No. 156 & 157 Part), Village - Bahera West, Tehsil - Gopad Banas, Dist. - Sidhi (MP) for the lease period to Shri Jai Bahadur Singh S/o Shri Surendra Pratap Singh, R/o South Karoudiya, Tehsil - Gopad Banas, Dist. - Sidhi, MP, Email - [email protected], Mobile – 9425177894.

26. Case No. – 6493/2019 Prior Environmental Clearance for Stone (Granite) Mine (Opencast Manual / Semi Mechanized Method) in an area of 1.214 ha. for production capacity of 25,886 cum / year at Khasra No. 1591/2P at Village - Didwara, Tehsil - Lavkush Nagar, Dist. Chhatarpur (MP) by M/s Om Granite, Village - Didwara, Tehsil - Lavkush Nagar, Dist. Chhatarpur, MP – 471510.

1. This is a project pertaining to mining of Stone (Granite) Mine in MLA of 1.214 ha. The activity is mentioned at S.No. 1 (a) of the Schedule of EIA Notification 2006 as amended from time to time. The project is reported to be at a distance of more than 10 km from National park and sanctuary etc. thus it is not attracted by the general conditions and considered under category ‘B-1” by virtue of its location and mining lease area. The case was forwarded by SEIAA to SEAC for appraisal of EIA for environment clearance for the project. It was submitted that this is a proposed mine with production capacity is 25,886 cum / year.

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 59 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020

2. It was noted that PP has submitted a copy of approved Mining Plan, DSR report, information in the lease’s within 500 meters radius around the site and other requisite information in the prescribed format duly verified in the Collector Office letter No. 1904 dated: 05/04/19 has reported that there are 07 more mines operating or proposed within 500 meters around the said mine with total area of 19.628 ha., including this mine.

3. SEAC in its 463rd SEAC meeting dtd 01.10.2020 has recommended the case with 37 special conditions for issuance of EC.

4. The proposed plantation programme was examined and it was found that 1500 sapling of tree species shall be covered under plantation.

5. It was noted that as per Divisional Forest Officer, Letter no. 2630 dtd. 15.07.2019, the National Park/Sanctuary are not located within 10 Km., radius from the mining site. Hence, the General Conditions are not attracted.

6. It was noted that the water requirement is 12.69 KLD (7.70 KLD for Dust Suppression + 0.24 KLD for Domestic + 3.75 KLD for Green Belt 1KLD for Mine operation) which shall be met from Tanker

7. It was also noted that the Public Hearing was carried out on 11.07.2020 at Gram Panchayat Bhawan at Village - Didwara, Tehsil - Lavkush Nagar, Dist. Chhatarpur under Chairmanship of Upper Collector, Chhatarpur.

After detailed discussions and perusal of recommendations of 463rd SEAC meeting dated 01.10.2020, presentation made by the PP in SEIAA, it was decided to accept the recommendation of SEAC for grant of prior EC to the project subject to the following specific conditions:-

I. Before commencing any mining activity fencing shall be carried out all around the lease area. Proper watch and ward arrangements should be made with installation of signage at 4 corners of lease area to avoid any untoward incident involving public and animals by the PP.

II. PP shall not start mining activity before execution of lease agreement. III. The depth of the pit shall be as per the Approved Mining Plan. IV. The entire area shall be fenced and three rows of plantation should be done

on the periphery of the boundary V. PP shall ensure that the proper water supply arrangements for dust

suppression, regular sprinkling, plantation and drinking purposes especially in summer season..

VI. PP shall ensure to construct and maintained the approach road. Plantation will be carried out on both side of approach road.

VII. PP shall ensure to construct garland drain with settling tank all around the lease area and regular cleaning & maintenance shall also be carried out by PP

VIII. PP shall ensure proper implementation of plantation, dust suppression, construction of approach road and maintenance of existing road & as part of Environmental Management Plan. Additional budget provision shall be made as part of EMP.

IX. Total 1500 saplings of suitable tree species i.e. Neem, Pipal, Bargad, Mango, Amla, Amaltas, Drumstick etc. shall be planted by PP under plantation

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 60 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020

programme. PP shall also explore and identify the chunk of land in the area from revenue record to carry out plantation programme as proposed

X. PP must ensure implementation of the following activities with separate budget provision of Rs 3.48lakh/ year under CER. 1st Year to 3rd Year

Contribution for social welfare of village school COVID-19 pandemic awareness program will be disseminated nearby

villages from project site. Provide safety kit for COVID-19 pandemic. Providing Ambulance facility Traffic awareness program will be follow as per project requirement Solar energy System & LED Street light for Village @ 8,000 per pole

(Rs. 1.92,000) (8 Poles/year) 8(pole) X 3(year) X 8000 Rs/pole)

PP shall ensure to contruct toilet with proper plumbing in the school of above village and contribute on behalf of village in Jal Jeewan Mission in consultation with Janpad Panchayat and PHED. PP shall give preference to develop/provide infrastructural facilities in schools or aganwadies of above villages The modification to the above activities can be made with the permission of the district administration and need based activity for the development of nearby villages shall be implemented by PP in consultation with the District Collector and Gram Panchayat

XI. PP should ensure to submit half yearly compliance report and CSR activity report with photographs of plantation in MP-SEIAA. If PP is failed to upload or submit two consecutive half yearly compliance reports of EC conditions to concerned authority (SEIAA and Regional Office, MoEF&CC,GoI,Bhopal) than prior environmental clearance issued to PP will automatically be treated as cancelled/ revoked as per OM No. 930/SEIAA/2019 dated 30.05.2019 issued by MPSEIAA.

Hence, Prior Environmental Clearance is granted for Crusher Stone (Granite) Mine (Opencast Manual / Semi Mechanized Method) in an area of 1.214 ha. for production capacity of 25,886 cum / year at Khasra No. 1591/2P at Village - Didwara, Tehsil - Lavkush Nagar, Dist. Chhatarpur (MP) for the lease period to M/s Om Granite, Village - Didwara, Tehsil - Lavkush Nagar, Dist. Chhatarpur, MP – 471510

27. Case No. 7662/2020 : Prior Environment Clearance for Proposed API Drugs Manufacturing Plant at Plot No. 92, Smart Industrial Park, Pithampur industrial Area, Pithampur, District Dhar MP Total Area: 34245.0 sq.m. Production Capacity : 4200 TPA by LIFEFIRST PHARMA PRIVATE LIMITED through Director, RISHABH MEHTA M/ to M/3 BCM Heights SCH No. 54 Indore, Indore, MP-452010 Email: vivek.shrivastava @lifefirstpharma.com Ph- 4266888 Mob No.-9820675585 Envt. Consultant:- Sms Envocare Limited, Pune, Maharashtra

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 61 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020

(1) The project is located over the land which comes under Smart Industrial Park, Pithampur Industrial Area, Pithampur, Dist. Dhar (MP).

(2) Geographical coordinate of project is Latitude: 22°34'3.76"N Longitude: 75°35'58.97"E and elevation of the project is 553 meters above sea level.

(3) The project is proposed for Manufacturing API Drugs at Plot No. 92, Smart Industrial Park, Pithampur Industrial Area, Pithampur, and Dist. Dhar (MP) by LIFEFIRST PHARMA PRIVATE LIMITED through Director, RISHABH MEHTA

(4) M/s. Lifefirst Pharma Pvt. Ltd. has proposed API Drug Manufacturing Plan of 4200 TPA (350 TPM) capacity. Total 57 products have been proposed.

(5) The proposed production capacity is 4200 TPA (350 TPM). Proposed product and production capacity:-

Sr. No. Product Quantity (TPA)

1 ALBENDAZOLE

200

2 ALLOPURINOL 200 3 METFORMIN HCl 1000 4 CHLOROTHALIDONE 100 5 TELMISARTAN 100 6 VALSARTAN 100 7 LOSARTAN 200 8 FAMOTIDINE 20 9 SIDENAFIL 50 10 FENOFIBRATE 20 11 PHENYLEFFRINE HCl 20 12 LUMEFANTRINE 100 13 FLUMEQUINE 50 14 PYRANTAL PAMOATE 100 15 BRIMONIDINE TARTRATE 20 16 ETODOLAC 50 17 CIPROFLOXACIN HCl 100 18 PHENOBARBITAL 20 19 MEBANDAZOLE 50 20 FEBENDAZOLE 50 21 HYDROCHLOROTHIAZIDE 50 22 MESALAMINE 100 23 MEFENAMIC ACID 100 24 GLIMEPRIDE 100 25 PENTAPRAZOLE 10 26 MONTELACUST 100 27 OFLOXACIN 10 28 ACYCLOVIR 100 29 SALBUTEMOL SULPHATE 50 30 ATAZANVIR 50 31 ARIPIPRAZOLE 100 32 OXCARBAZEPINE 50 33 CELECOXIB 20 34 GLIACLAZIDE 100 35 BROMHEXINE HCl 20 36 CINNARIZINE 20 37 PEROXICAM 10 38 MELOXICAM 10 39 SILODOSIN 50 40 TIMOLOL 10 41 PAROXETINE HCl 10 42 PAC-2(1-tert butyl 2-ethyl 5-oxopyrrolidine-1, 2-

dicarboxylate) 50

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 62 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020

43 NEBIVOLOL 20 44 LAMOTRIGINE 20 45 NEPAFENAC 10 46 OLANZAPINE 10 47 CLOTRIMAZOLE 10 48 CLOZAPINE 10 49 RUFINAMIDE 10 50 ETHIONAMIDE 10 51 PROTHIONAMIDE 10 52 PREGABALIN 50 53 QUETIAPINE FUMRATE 100 54 DEXTROMETHORPHAN (DMR) 100 55 LEVOCETIRIZINE 50 56 FUROSEMIDE 20 57 IRON SUCROSE 100 TOTAL: 4200 TPA (350 TPM)

(6) The proposed project is covered under 5(f) category “Synthetic organic chemicals industry (dyes & dye intermediates; bulk drugs and intermediates excluding drug formulations; synthetic rubbers; basic organic chemicals, other synthetic organic chemicals and chemical intermediates) as per EIA Notification 2006 and categorized under B2 Category as per recent MoEFCC So. No. 1223 (E) dated 27th March 2020 & In the context of pandemic COVID -19, MoEF&CC GoI’s issued a OM vide dated 13.04.2020, for considering the API & Bulk drug Projects as B-2 category.

(7) There is no interstate boundary (PWD letter dtd. 04.09.2020) within 05 km and no National park, Sanctuary and Eco-sensitive areas (DFO letter dtd. 22.09.2020) within 05 km of the project area hence General condition are not attracted.

(8) The case was discussed in SEAC meetings 463rd dated 01.10.2020, and recommended for grant of prior EC.

(9) After recommendation of SEAC today the case scheduled for presentation and after deliberations by PP the case was discussed in depth & it is recorded that:-

i. The project is proposed in the company’s existing premises having land of 34245.0 sq.m, Regarding land documents PP has submitted allotment letter dtd.15.05.2020 issued by MPIDC (MP Industrial Development Corporation),Bhopal. As per the allotment letter the said land is allotted to LIFEFIRST PHARMA PRIVATE LIMITED through Director, RISHABH MEHTA for setting up a Large industrial unit for manufacturing of Pharmaceuticals. The land will be given for the lease period of 99 years.The land use breakup of the project area is as follows:-

Sr. No. Building name Length (M) Width (M) Area (M) 1 Total Plot Area 203 181 33442.5 2 Production Block-01 54.8 23.6 1293.3

3 Pilot Plant 20 15 300 4 PP Area (Expansion) 15 15 225 5 Drum Yard 25 10 250 6 Explosive Tank Farm 25 20 500 7 Dining Area 10 10 100 8 RO System Building +ETP 25 15 375

9 Boiler House 20 10 200 10 RO MEE 25 10 250

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 63 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020

11 PCC Panel Room 15 5 75 12 DG + Electrical Panel Room 20 10 200

13 RM + PM + FG 50 25 1250 14 Green Area - - 11985 15 Road Area - - 6307.5 16 Open Area - - 4240.2 Total Plant Area 27551.0 Balance Building Expansion Area (in Sq.m)

Sr. No. Building name Length (M) Width (M) Area (M) 1 Production Block-01 34.2 25 855 2 Production Block-02 88.2 48.6 4286.5 3 Admin Block 20 15 300 4 Explosive Tank farm 25 10 250 5 Boiler House 20 10 200 Total Plant Area 5891.5

ii. The major facilities involved are Boiler, MEE, ATFD, Solvent recovery Plant, Solvent storage area, reactors, Cooling towers, Effluent treatment plant (ETP), and R.O Plant Facilities like administrative office, parking and greenbelt/plantation also developed as per plan/requirement.

iii. Total water requirement for the project will be 220 kl/day. The water required for the proposed activity will be fulfilled by the MPIDC.PP has submitted letter dtd.27.08.2020 issued by MPIDC (MP Industrial Development Corporation),Indore .for water supply.

iv. Solid waste generated during the manufacturing process and wastewater treatment process is mainly sludge and will be disposed at authorized TSDF facility, as per Hazardous and Other Waste (Management & Transboundary Movement) Rules, 2008 (Amendment 2016). M/s. Life First Pharma Pvt. Ltd. has to secure the membership with nearest CHWTSDF for disposal of Hazardous waste generated from the proposed project.

v. Boiler of 6 TPH capacity is proposed which will be Coal+Briquette fired and will have bag filter as APCE and then connected to chimney of 30 m height. The outgoing flue gases quality will be monitored on a regular interval within the prescribed parameters, in-order to meet the CPCB norms.

vi. Power requirement for this project will be 1000 kWH whereas connected load in 1500 KWH. Required power will be source from MP PaschimKshetraVidhyutVitran Co. Ltd. Load sanction application will be submitted. DG set of 1000 KVA has been provided as backup. Diesel will be required for the D.G. set which will be purchased from the nearest petrol pump in drum and transported by road only.

vii. For waste water management P has proposed as follows:- LIFEFIRST PHARMA PRIVATE LIMITED. Has proposed 75 KLD ETP &

20 KLD STP separately. ETP will be based on diffused aeration system followed by polishing

treatment. High COD/TDS stream will be drained separately to MEE system with

pre-treatment for physical treatment. STP will be based on MBBR packaged type separately followed by

polishing treatment & disinfection by using UV System. It is planned adjoined ETP area & final treated water storage be common for ETP & STP for further reuse in gardening area.

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 64 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020

Project will not discharge spent solvent to ETP. Solvent will be recovered separately.

Project will not discharge high TDS/COD stream of utilities to proposed ETP

Treated single outlet will be as per MPPCB norms for maintaining zero liquid discharge (ZLD) i.e. utilization of treated effluent for gardening / plantation purpose on own land within premises.

viii. The main source of air pollution is from boiler, thermic fluid heater and DG Sets for management of air pollution PP has proposed as follows:- Bag filter followed by emission stacks shall be provided of 30 m height Stack is also provided with required height of Stack As per the MPPCB directive, emission of Particulate matter shall not

exceed the limit of 150 mg/Nm3 Regular water sprinkling shall be ensured in the plant area during

construction phase. All internal roads shall be paved of concreted as per requirement to

avoid the dispersion of Particulate matters. Transportation of Raw material by closed trucks only Regular maintenance of vehicle with PUC shall be maintained. Online stack monitoring system will be provided with due compliance

from MPPCB Thick green belt shall be developed in about 35.00 % of total plot area

which will help to control the air pollution ix. Total 12 Nos. of solvents will be used during manufacturing of Respiratory

APIs. Out of 12 solvents, 6 solvents consumption is more. Solvents will be dispensed to respective reactors using solvent batching

system. Reactors are equipped with condensers for condensation of solvents during distillation.

Dedicated vacuum controller will be provided to maintain desired vacuum during distillation & to improve the recovery of solvent.

Distilled solvent will be collected in dedicated jacketed distillate receiver, further these distilled solvents will be collected in storage tanks. These recovered solvents will be sent for disposal.

During processing of API, operation like filtration, layer separation needs to carried out. In which major solvent consumption observed.

In proposed facility, filtration of reaction mass will be carried out in ANFD (Agitated Nutsche Filter Dryer). ANFD will be equipped with dedicated MLR tank and vacuum pump required during drying.

All mother liquor during filtration operation will be collected in MLR tank and which will further be sent for disposal.

Vacuum system will be provided with pre and post condenser to condensed maximum amount of solvent which evaporates during drying through ANFD.

These condensers will have utilities like chilled brine will be provided. Condensed solvent will be collected in jacketed tank

Entire condensed solvents will further be sent to disposal. Maximum amount of solvents will be recovered at primary & secondary

condenser to avoid emission of solvent through vacuum pump

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 65 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020

Vent of vacuum pump will be further connected to scrubber tank to scrub the uncondensed vapors.

Solvent recovery will be minimum 95%. Solvents leaves from all streams like cleaning, MLR, recovered etc. will

further transferred for disposal through tankers. x. As per data available with Central Ground Water Authority; average annual

rainfall at Dhar district is about 833.61 mm (0.833 m). Following are the storm management plan proposed for the plant Separate Drainage will be provided for Effluent and Storm water Storm water will be further connected to Storage tank This water will be used for green belt and other non portable domestic

purpose Drainage provided to Effluent will be connected to ETP No any kind of waste water will be discharged out side the plant

xi. The total plot area is 33442.5 Sq. m and 11985.75 sq. m of land is reserve for development of thick green belt which is about 35.00 % of total plot area. Similarly, considering the requirements of environmental rules and regulations, suitable local Plant species will be planted with adequate spacing to maintain or to develop the green zone (buffer zone) in and around the Factory. Total 750 Tree species along with ornamental plants will be planted in

entire 3 year plantation programs. Required nutrients/water/ manure and protect ion mess shall be

provided. Ground flora will also be developed in open area. Survival of plant shall

also be monitored Considering 20% of Mortality rate, provision of 200 additional plants has

been kept in planning. Avenue plantation/ road side plantation will be done under CER Plan

with consultation of local authority, Gram Panchayat . We have identified Madhavpur (Sagore) for avenue plantation

xii. PP has included Disaster Management plan in the EMP report. For firefighting measure PP has provided as follows:- Hydrant System Fire Detection and Alarm System Different types of Fire Extinguishers (CO2 & DCP) Grounding to each production vessels & reactors Bonding & Jumpers on pipeline Flame proof electrification Name and capacities of the chemicals displayed on storage tanks PPES to be used while handling of chemicals Spark proof electrification Portable fire extinguishers of different capacity and types Flame proof fitting Regular training to workers for operation of firefighting instruments

xiii. Total cost of proposed unit will be 47.75 Crore. xiv. Lifefirst Pharma Pvt. Ltd. is well aware with the corporate responsibility

towards the environment and social development etc. for the Govt. Higher

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 66 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020

Secondary School, Pithampur Ind. Area, Sambhav NGO Pithampur Mahesh Drishtiheen Kalyan Sangh, Indore, Vasudha Vikash Sansthan, Mandu Road, Dhar In line with above, company has identified total Rs.1.0 Cr towards CER initiatives. Details of the same is given below:

SN Activity 1st Yr. (21-22) (In Lakhs)

2nd Yr. (22-23) (In Lakhs)

3rd Yr. (23-24) (In Lakhs)

4th Yr. (24-25) (In Lakhs)

5th Yr. (25-26) (In Lakhs)

Total (in Lakhs)

Local Infrastructure development

1 Maintenance of Building of GP Schools Anganwadi centers, Maintenance of Water supply system and Providing RO unit for safe drinking water for GP Office, GP schools and Anganwadises, Providing By-cycle to students etc.

8 8 8 8 8 40

2 Development of New Toilets and maintenance of Existing Toilets of education centres, GP buildings, development of access road, drainage work

8 8 8 8 8 40

3 Providing digital and online study system to GP schools as per requirement

4 4 4 4 4 20

Total 20 20 20 20 20 100.0 (1.0 Crore)

Hence It is decided to accept the recommendations of 463rd SEAC meeting dtd 01.10.2020 and accord Prior Environment Clearance for proposed API Drugs Manufacturing Plant at Plot No. 92, Smart Industrial Park, Pithampur industrial Area, Pithampur, District Dhar MP Total Area: 34245.0 sq.m. Production Capacity : 4200 TPA by LIFEFIRST PHARMA PRIVATE LIMITED through Director, RISHABH MEHTA M/ to M/3 BCM Heights SCH No. 54 Indore, Indore, MP-452010 subject to following specific conditions:-

1. The entire demand of fresh water should be met through MPIDC.(NOC dtd.27.08.2020) Fresh water should not be used for Irrigation and gardening purpose.

2. Waste water: (a) PP should ensure “Zero effluent discharge” from the unit by 100% recycling. The

water softening reject, boiler blow down reject and cooling blow down will be treated in ETP. Further treated waste water will go through the RO and finally re used / recycled in the process and unused waste water evaporates in MEE.

(b) RO and MEE should be provided for treatment of high COD waste streams and only in case of emergency/breakdown high COD wastes should be disposed off through CTSDF, Pithampur, Dhar.

3. For Air Pollution: (a) PP should ensure regular Stack monitoring & Ambient air quality monitoring and

should be carried out as per the guidelines/norms of MPPCB/CPCB. (b) In plant control measures for checking fugitive emission from all the vulnerable

sources shall be provided. Fugitive emission shall be controlled by providing closed storage, closed handling & conveyance of chemicals/materials, multi cyclone separator/bag filters and water sprinkling system.

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 67 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020

(c) Company shall carry out the HAZOP study and report shall be submitted to ministry MoEF & CC Regional Office, Bhopal.

(d) PP should explore the possibility to use other instead of coal. To control source and the fugitive emissions, suitable pollution control devices shall be installed to meet the prescribed norms and/or the NAAQS. Sulphur content should not exceed 0.5% in the coal/CNG for use in coal/CNG fired boilers to control particulate emissions within permissible limits (as applicable). The gaseous emissions from the boiler, DG set shall be dispersed through stack of adequate height as per CPCB/SPCB guidelines.

(e) For control of fugitive emission and VOCs following steps should be followed:- Chilled brine circulation system shall be provided and it should be

ensured that the solvent recovery efficiency is not be less than 95%. Reactor and solvent handling pump shall be provided with mechanical

seal to prevent leakage. Solvent shall be taken from underground storage tank to reactor through

closed pipeline. Storage tank shall be vented through trap receiver and condenser operated on chilled water.

4. Hazardous Waste Management: (a) As proposed above, PP should ensure disposal of hazardous waste regularly

and there should be no dumping of these materials in the premises/outside. (b) PP should ensure handling, disposal and management of hazardous waste

as per the related prescribed rules. (c) PP should obtain Renewal of authorization regularly from MPPCB for

collection storage and disposal of hazardous waste (Management, handling & transboundary Movement) Rules 2008 and its amendments. Membership of the TSDF should be obtain for hazardous waste disposal.

(d) Hazardous chemicals should be stored in sealed tanks, drums etc. Flame arrestors shall be provided on tanks. To avoid the spillage from processing unit, Industry shall provide fully mechanized filling and packaging operation unit.

5. Green Belt Development: (a) PP should ensure plantation as proposed 11985.75 sq. m of area with 750

number of trees Plantation in the project area of indigenous local varieties like Neem, Peepal, Kadam and Kachnaar.

(b) Every effort should be made to protect the existing trees on the plot. (c) Green area including thick green-belt shall be developed in 35% of the plot

area as proposed to mitigate the effect of fugitive emissions all around the plant in consultation with the forest department as per the guidelines of CPCB.

6. PP should ensure the implementation of CER activities to the extent of Rs. 1.0 Crore for the Govt. Higher Secondary School, Pithampur Ind. Area, Sambhav NGO Pithampur Mahesh Drishtiheen Kalyan Sangh, Indore, Vasudha Vikash Sansthan, Mandu Road, Dhar as committed during presentation on regular basis in consultation with Collector, Dhar.

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 68 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020

7. Total quantity of runoff water generated and green belt area should be collected in underground tank & used for process in plant to minimize fresh water requirement.

8. All other conditions as laid in the consents of MPPCB shall be applicable. 28. Case No. 7809/20 Prior Environmental Clearance for White Clay Mine (opencast

manual/semi mechanized method) in an area of 3.238 ha. (5000 cum per annum) (Khasra No.512/2/Ka/1), Village - Parasrampur, Tehsil - Maihar, Dist. - Satna (MP) by M/s Maa Sharda Mines and Minerals, Smt. Amrita Namdeo, Partner, R/o Plot No. 107, Bairagarh Chichli, Kolar Road, Bhopal, Dist. - Bhopal, MP - 462042, Email - [email protected], Mobile- 9589602028.

This case was recommended in 463rd SEAC meeting dated 01.10.2020 and it was recorded that..........

“------------PP has submitted the response of above quarries same date vide letter dated 01.10.2020, which was placed before the committee and the same found satisfactory. The EMP and other submissions made by the PP were found to be satisfactory and acceptable, hence committee after deliberation found that The EMS and other submissions made by the PP were found to be satisfactory and acceptable, hence committee decided to recommend the case for grant of prior EC subject to the following special conditions in addition to the standard conditions at annexure ‘A’:

PP/Consultant made a presentation on all aspects of the project and all concerned issues were discussed in detail. After detailed discussions and perusal of recommendations of 463rd SEAC meeting dated 01.10.2020, presentation made by the PP in SEIAA, it was decided to accept the recommendation of SEAC for grant of prior EC to the project subject to the following specific conditions:-

i. Before commencing any mining activity fencing shall be carried out all around the lease area. Proper watch and ward arrangements should be made with installation of signage at 4 corners of lease area to avoid any untoward incident involving public and animals by the PP.

ii. PP shall not start mining activity before execution of lease agreement.

iii. The depth of the pit shall be as per the Approved Mining Plan.

iv. The entire area shall be fenced and three rows of plantation should be done on the periphery of the boundary.

v. PP shall ensure the proper water supply arrangements for dust suppression, regular sprinkling, plantation and drinking purposes especially in summer season.

vi. Total 3900 saplings of suitable tree species i.e. Neem, Pipal, Bargad, Mango, Gulmohar, Sissoo, Kathal, etc. shall be planted by PP in first three years under plantation programme at mine lease boundary and at khasra no. 512/2, Village - Parasrampur, Tehsil - Maihar, Dist. - Satna in consultation with Gram Panchayat/ DM. PP shall also explore and identify the chunk of land in the area from revenue record to carry out plantation programme as proposed.

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 69 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020

vii. PP shall ensure proper implementation of plantation, dust suppression, construction of approach road and maintenance of existing pakka road as part of Environmental Management Plan. Additional budget provision shall be made as part of EMP.

viii. PP must ensure implementation of the following activities with separate budget provision of total Rs. 75,000/- under CER as committed:

a) Village – Parasrampur: COVID-19 awareness program. Development of grazing land at village Parasrampur Installation of Handpump and arrangement of overhead tank

(750liter) with water pump (0.5HP) for drinking water facility at Parasrampur middle school.

To provide benches and table chair in primary school Parasrampur.

PP shall ensure to contruct toilet with proper plumbing in the school of above village and contribute on behalf of village in Jal Jeewan Mission in consultation with Janpad Panchayat and PHED. PP shall give preference to develop/provide infrastructural facilities in schools or aanganwadies of above villages. The modification to the above activities can be made with the permission of the district administration and need based activity for the development of nearby villages shall be implemented by PP in consultation with the District Collector and Gram Panchayat.

ix. PP should ensure to submit half yearly compliance report, Plantation and CER activity report along with photographs of all activities in MP-SEIAA. If PP is failed to upload or submit two consecutive half yearly compliance reports of EC conditions to concerned authority (SEIAA and Regional Office, MoEF&CC,GoI,Bhopal) than prior environmental clearance issued to PP will automatically be treated as cancelled/ revoked as per OM No. 930/SEIAA/2019 dated 30.05.2019 issued by MPSEIAA.

Hence, Prior Environmental Clearance is granted for White Clay Mine (opencast manual/semi mechanized method) in an area of 3.238 ha. (5000 cum per annum) (Khasra No.512/2/Ka/1), Village - Parasrampur, Tehsil - Maihar, Dist. - Satna (MP) for the lease period to M/s Maa Sharda Mines and Minerals, Smt. Amrita Namdeo, Partner, R/o Plot No. 107, Bairagarh Chichli, Kolar Road, Bhopal, Dist. - Bhopal, MP - 462042, Email - [email protected], Mobile- 9589602028.

29. Case No 7812/2020 Prior Environmental Clearance for Stone and Murrum Quarry (Opencast Manual / Semi Mechanized Method) in an area of 4.450 ha. for production capacity of Stone 70000 cum / year and Murum 14,400 cum / year at Khasra No. 4/1, 3/2 at Village - Bothiyakalan, Tehsil - Harsud, Dist. Khandwa (MP) by Shri Yashwant Patel S/o Shri Omnarayan Patel, Gadariya, Tehsil - Seoni Malwa, Dist. Hoshangabad, MP – 461223

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 70 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020

This case was recommended in 463rd SEAC meeting dated 01.10.2020 and it was recorded that..........

“…………PP has submitted the response of above quarries same date vide letter dated 01.10.2020, which was placed before the committee and the same found satisfactory. The EMP and other submissions made by the PP were found to be satisfactory and acceptable, hence committee after deliberation found that The EMS and other submissions made by the PP were found to be satisfactory and acceptable, hence committee decided to recommend the case for grant of prior EC subject to the following special conditions in addition to the standard conditions at annexure ‘A’:”

PP/Consultant made a presentation on all aspects of the project and all concerned issues were discussed in detail. After detailed discussions and perusal of recommendations of 463rd SEAC meeting dated 01.10.2020, presentation made by the PP in SEIAA, it was decided to accept the recommendation of SEAC for grant of prior EC to the project subject to the following specific conditions:-

I. Before commencing any mining activity fencing shall be carried out all around the lease area. Proper watch and ward arrangements should be made with installation of signage at 4 corners of lease area to avoid any untoward incident involving public and animals by the PP.

II. PP shall not start mining activity before execution of lease agreement. III. The depth of the pit shall be as per the Approved Mining Plan. IV. The entire area shall be fenced and three rows of plantation should be done

on the periphery of the boundary. V. PP shall ensure that the existing 04 trees within lease are proposed felling for

which PP will take permission from competent authority and 40 trees shall be additionally planted, and other trees which are located in the barrier zone shall be kept intact.

VI. No drilling and blasting shall be carried out in mining lease area VII. PP have proposed wind breaking wall in view of NH and proposal of 5350

trees to be planted in aapproach road, Mine lease boundary and at Bothiyakalan village area on government land

VIII. PP shall ensure that the proper water supply arrangements for dust suppression, regular sprinkling, plantation and drinking purposes especially in summer season.

IX. PP shall ensure to construct and maintained the approach road. Plantation will be carried out on both side of approach road.

X. PP shall ensure proper implementation of plantation, dust suppression, construction of approach road and maintenance of existing road & as part of Environmental Management Plan. Additional budget provision shall be made as part of EMP.

XI. Total 5370 saplings of suitable tree species i.e. Neem, Pipal, Bargad, Mango, Amla, Amaltas, Drumstick etc. shall be planted by PP at mine lease boundary and In Bothiyakalan village area – at government land with due permission from local gram panchayat (Khasra nos 1 , 8, 12, 15, 16 & 17 ) under plantation programme. PP shall also explore and identify the chunk of

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 71 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020

land in the area from revenue record to carry out plantation programme as proposed.

XII. PP must ensure implementation of the following activities with separate budget provision of Rs 7.0 lakh under CER. CER activities at Bothiyakalan ~100 (In 5 year period) Distribution of masks and sanitizers to villagers for 1st year only* Development and maintenance of grassland on a nearby government land

(from 1st to 5th year)** Repair & whitewash of Bothiyakalan Government Primary School building

including construction of a new toilet and its boundary wall and levelling of its playground

Construction of 2 new rooms within above school premises (15’X10’) and establishment of a library in one of them

Erection of overhead water tank in above school building with proper water supply

Instillation of slides in above school premises Contribution in future water supply scheme for the village

PP shall ensure to contruct toilet with proper plumbing in the school of above village and contribute on behalf of village in Jal Jeewan Mission in consultation with Janpad Panchayat and PHED. PP shall give preference to develop/provide infrastructural facilities in schools or aganwadies of above villages The modification to the above activities can be made with the permission of the district administration and need based activity for the development of nearby villages shall be implemented by PP in consultation with the District Collector and Gram Panchayat

XIII. PP should ensure to submit half yearly compliance report and CSR activity report with photographs of plantation in MP-SEIAA. If PP is failed to upload or submit two consecutive half yearly compliance reports of EC conditions to concerned authority (SEIAA and Regional Office, MoEF&CC,GoI,Bhopal) than prior environmental clearance issued to PP will automatically be treated as cancelled/ revoked as per OM No. 930/SEIAA/2019 dated 30.05.2019 issued by MPSEIAA.

Hence, Prior Environmental Clearance is granted for Stone and Murrum Quarry (Opencast Manual / Semi Mechanized Method) in an area of 4.450 ha. for production capacity of 70000 cum / year and Murum (14,400 cum / year at Khasra No. 4/1, 3/2 at Village - Bothiyakalan, Tehsil - Harsud, Dist. Khandwa (MP) for the lease period to Shri Yashwant Patel S/o Shri Omnarayan Patel, Gadariya, Tehsil - Seoni Malwa, Dist. Hoshangabad, MP – 461223

30. Case No. 7818/2020 : Prior Environment Clearance for proposed project Manufacturing of Drug Intermediates & Key starting materials for API at Plot No.139-A, Industrial Area, Meghnagar, Dist.Jhabua Madhya Pradesh Land area – 10,000 sq. m. Production Capacity: 4980 MT/Annum by Sanjay Vyas, Director, SHAIL CHEM DISTILLATE PVT. LTD. Plot No. 139-A, Industrial Area, Meghnagar Dist. Jhabua, Meghnagar, Jhabua ,MP-457779 Email – [email protected], Mob :-09893321712 Envt. Consultant : Creative Enviro Services, Bhopal

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 72 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020

(1) The project is proposed for Manufacturing of Drug Intermediates and Key Starting materials for API at Plot No. 139-A, Industrial Area, Village - Bedavali, Tehsil - Meghnagar, Dist. Jhabua, (MP).by SHAIL CHEM DISTILLATE PVT. LTD through Director, Sanjay Vyas.

(2) Geographical coordinate of project site is Latitude: 22°54'19.06"N Longitude: 74°33'10.98"E

(3) The proposed project is for API-Drug intermediates &Key Starting material for API, for 4980 MT/annum, proposed in the premises of 10000sq.m.

(4) The proposed production capacity is 4980 TPA. Proposed product and production capacity:-

S. No

Name and category of Product Capacity Qty (MT/PA) and

Composition 1 Bis-(4-hydroxyphenyl) methanone 1080

2 (1,3-phenylene) bis [(4-Hydroxyphenyl) methanone]

180

3 (1,4-phenylene) bis [4-hydroxyphenyl) methanone]

180

4 Bis-(4-fluorophenyl) methanone 2640 5 1-(4-hydroxyphenyl) ethan-1-one 900 Total 4980

(5) The proposed project is covered under 5(f) category “Synthetic organic chemicals industry (dyes & dye intermediates; bulk drugs and intermediates excluding drug formulations; synthetic rubbers; basic organic chemicals, other synthetic organic chemicals and chemical intermediates) as per EIA Notification 2006 and categorized under B2 Category as per recent MoEFCC So. No. 1223 (E) dated 27th March 2020 & In the context of pandemic COVID -19, MoEF&CC GoI’s issued a OM vide dated 13.04.2020, for considering the API & Bulk drug Projects as B-2 category.

(6) There is no interstate boundary within 05 km and no National park, Sanctuary and Eco-sensitive areas within 05 km of the project area hence General condition are not attracted.

(7) The case was discussed in SEAC meetings 463rd dated 01.10.2020, and recommended for grant of prior EC.

(8) After recommendation of SEAC today the case scheduled for presentation and after deliberations by PP the case was discussed in depth & it is recorded that:-

i. The total plot area is 10,000.0 sq.m. (Plot no. 139-A) for which PP has executed registered lease deed dated 16.09.2010executed between Managing Director MPAKVN, (Indore) Ltd. and M/s SHAIL CHEM DISTILLATE PVT. LTD through Director, Shri Mahendra Singh Thakur for the period of 30 years.

ii. .The land use breakup of the project area is as follows:- S.No. Particulars Total Area (Sq. Mt.)

1 Total Land Area 10,000

2 Built up area 4,100

Break up of Built up area

2.1 PRODUCTION BLOCKS 1500

2.2 WAREHOUSE 500

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 73 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020

2.3 UTILITY BUILDING 200 2.4 ADMIN QC & QA 300 2.5 UG TANK & PUMP ROOM 200 2.6 SECURITY 100

2.7 ETP 1000

2.8 Drum Storage 200

2.9 ACID Drum Storage 100

3 Green Belt - 3 Layer Trees 3500

4 Future Allocation 800 5 Open Land 1600

iii. The major facilities involved area Boiler, Cooling Towers,ZLD based Effluent Treatment system (ETP) with MEE &ATFD, Facilities like administrative office, parking and greenbelt/plantation also developed as per plan/requirement.

iv. The industrial water requirement for the proposed project is 93 KL per day which will meet from AKVN supply. The total water requirement is about 143KLD and waste water generated from the plant will be about 86.5KLD. The proposed capacity of ETP, and MEE is 150KLD, and75 KLD (output), respectively

v. Total waste water generation from proposed unit will be 86.5 KLD Out of this about 55 KLD will be High COD from Process, &Boiler blow down & washing will be15.5 KLD Low COD will be 20 KLD. Domestic/ Sewage 5 KL will be collected by gravity from all sources into soak pit.

vi. HTDS Effluent will be sent to ETP followed with Multiple Effect Evaporator (MEE) & Agitated Thin Film Dryer (ATFD).

vii. Low COD/Low TDS Effluent will be treated in an Effluent Treatment Plant comprising of Primary, Secondary & Tertiary treatment like sand filter carbon filter followed with MEE &ATFD. The treated effluent will be reused within the company premises as cooling tower makeup water and boiler feed etc.

viii. Hazardous waste generated during the manufacturing process will be disposed at authorized TSDF facility, as per Hazardous and Other Waste (Management &Trans-boundary Movement) Rules, 2008 (Amendment 2016). M/s Shailchem will take expanded authorization Under Hazardous Waste (Management, Handling & Trans-boundary Movement), Rules. S. No. Sources Type of pollutants Waste category as

per HW Rules 2016 Annual Generation ( After )

01 Processing Plant & Filters

Process Residue & Waste

28.1 175 MT

02 Solvent Refining Unit (Existing)

Distillation Residue 20.3 125 MT

03 From Plants Used or Spent Oil 5.1 1 MT

04 From Carbon filter

Spent carbon or filter medium

36.2 600 Kg

05 From Plant Polythene bags,

plastic scrap, centrifuge bags

-- 2.5 MT

06 From Plants Empty Barrels, 33.1 100

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 74 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020

07 Effluent Treatment Plant

Chemical Sludge from Waste water treatment (ETP & MEE Plant)

35.3 190 MT

ix. Power requirement will be sourced from existing line of ‘Madhya Pradesh Pashchimi Kshetra Vidyut Vitaran Company’. The company is authorized to use power load of 1300 KVA. In case of power failure, D.G. sets of 500- KVA will be used as a backup power source.

x. For waste water management P has proposed as follows:- Storm water drainage system shall be developed and shall be

maintained preciously to prevent the flow of silt and other contaminant outside of the site

The entire trade effluent will be divided into two streams i.e. Stream-I (high concentrated streams) and Stream-II (low concentrated stream). Both the streams will be treated in well-designed ETP, and MEE, ATFD system

Low COD /TDS wastewater (including process effluent, washing, blow downs from cooling towers, boiler, scrubber, Softener regeneration) will be sent to ETP followed MEE, ATFD. Treated water will be reused.

High COD / TDS wastewater (consisting process effluent & RO reject,) will be sent to ETP followed by MEE/ATFD. Condensate will be reused and bottom salt will be sent to a common TSDF site.

Utilization of treated wastewater (Steam condensate) in cooling tower, gardening, boiler etc.

A drain along the boundary wall shall be made, which will be connected proposed settling tank to protect the flow of contaminant towards nearby area

Recycling of 86.5 KLD (- 60 % of total fresh demand) water is proposed which ultimately reduces the fresh water demand.

Shailchem will install Multi Effective Evaporator, with treatment capacity of 75 KLD at outlet. The treated water will be used for cooling towers, floor washing and gardening/green belt.

Blow downs from cooling towers, boiler, ACF/MGF Cleaning, Softener regeneration, Vacuum pump will go to ETP

Water harvesting structure need to provide further strength with proper maintenance

ZERO effluent discharge shall be implemented, and maintained. xi. The main source of air pollution is from boiler, thermic fluid heater and DG

Sets for management of air pollution PP has proposed as follows:- Installation of Scrubbers as part of Air Pollution Control Measure

(APCM), Provision of adequate stack height and vents for Boiler and DG set.

As per the MPPCB directive, emission of Particulate matter shall not exceed the limit of 150 mg/Nm3

Regular water sprinkling shall be ensured in the plant area during construction phase.

All internal roads shall be paved of concreted as per requirement to avoid the dispersion of Particulate matters.

Transportation of Raw material by closed trucks only

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 75 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020

Regular maintenance of vehicle with PUC shall be maintained. Online stack monitoring system will be provided with due compliance

from MPPCB Thick green belt shall be developed in about 33.00 % of total plot area

which will help to control the air pollution xii. Risk assessment is the process of identifying, analyzing, and evaluating the

hazard posed by an industrial plant and the main aim is the prevention and mitigation of accidents in potentially hazardous facilities. Following measures taken for risk assessment & disaster management Fire extinguishers are provided (Dry chemical powder & CO2 Type) Fire exit are escape routes are always kept clear Suitable types of cable & wiring should be used for Plant First aid kit provided for employess Fire hydrant system is available PPE’s kit provides for employess

xiii. The unit will do plantation and also have planned for total garden area to be 3500square meters i.e. 33% of the total area. The green belt of 5-10 m width will be developed mainly along the periphery and road side.

xiv. The total estimated cost of the proposed project Rs. 15 Crore out of which Rs. 501.8 Lacs (capital cost) is allocated for environmental management systems and the annual recurring cost for the same is Rs 18.50 Lacs.

xv. Under CER activities PP has propsed as following activities with budgetary provision of 15 lakh. CORPORATE ENVIRONMENT RESPONSIBILITY RS IN LAKHS

1 Due to falling in brown field project we will invest 1% of the capital investment The break-up is as under.

15.00

a) Proposed to provide educational material & infrastructure to Govt. Primary & Middle Schools,high scholl of nearby Agral village, Tehsil Meghnagar district-Jhabua.

10.0

b) Proposed to provide infrastructure to Anganwaaadi in Agral nearby village TehsilGovt. Higher Secondary school in nearby Agral villages Meghnagar district-Jhabua.

5.0

Benefits of the project: Drug & API industry growth in our country is increasing continuously with rise in population as well as demand for health care sector. Indian government is also promoting in-house manufacturers to increase the capacity to fulfill the rising demand and to contribute as much as possible in Atmanirbhar Bharat Scheme. This project will help organization to grow locally as well as globally and save countries foreign exchange by making products by avoiding import.Supply as per the demand. So, no gap will be generated. Hence It is decided to accept the recommendations of 463rd SEAC meeting dtd 01.10.2020 and accord Prior Environment Clearance for proposed Manufacturing of Drug Intermediates & Key starting materials for API at Plot No.139-A, Industrial Area, Meghnagar, Dist.Jhabua Madhya Pradesh Land area – 10,000 sq. m. Production Capacity: 4980 MT/Annum by Sanjay Vyas, Director, SHAIL CHEM

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 76 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020 DISTILLATE PVT. LTD. Plot No. 139-A, Industrial Area, Meghnagar Dist. Jhabua, Meghnagar, Jhabua ,MP-457779 subject to following specific conditions:-

1. The entire demand of fresh water should be met through MPAKVN. Fresh water should not be used for Irrigation and gardening purpose.

2. Waste water: (a) PP should ensure “Zero effluent discharge” from the unit by 100% recycling. The

water softening reject, boiler blow down reject and cooling blow down will be treated in ETP. Further treated waste water will go through the RO and finally re used/recycled in the process and unused waste water evaporates in MEE.

(b) RO and MEE should be provided for treatment of high COD waste streams and only in case of emergency/breakdown high COD wastes should be disposed off through CTSDF, Pithampur, Dhar.

3. For Air Pollution: (a) PP should ensure regular Stack monitoring & Ambient air quality monitoring and

should be carried out as per the guidelines/norms of MPPCB/CPCB. (b) In plant control measures for checking fugitive emission from all the vulnerable

sources shall be provided. Fugitive emission shall be controlled by providing closed storage, closed handling & conveyance of chemicals/materials, multi cyclone separator/bag filters and water sprinkling system.

(c) Company shall carry out the HAZOP study and report shall be submitted to ministry MoEF & CC Regional Office, Bhopal.

(d) For control of fugitive emission and VOCs following steps should be followed:- Chilled brine circulation system shall be provided and it should be

ensured that the solvent recovery efficiency is not be less than 95%. Reactor and solvent handling pump shall be provided with mechanical

seal to prevent leakage. Solvent shall be taken from underground storage tank to reactor through

closed pipeline. Storage tank shall be vented through trap receiver and condenser operated on chilled water.

4. Hazardous Waste Management: (a) As proposed above, PP should ensure disposal of hazardous waste regularly

and there should be no dumping of these materials in the premises/outside. (b) PP should ensure handling, disposal and management of hazardous waste

as per the related prescribed rules. (c) PP should obtain Renewal of authorization regularly from MPPCB for

collection storage and disposal of hazardous waste (Management, handling & transboundary Movement) Rules 2008 and its amendments. Membership of the TSDF should be obtain for hazardous waste disposal.

(d) Hazardous chemicals should be stored in sealed tanks, drums etc. Flame arrestors shall be provided on tanks. To avoid the spillage from processing unit, Industry shall provide fully mechanized filling and packaging operation unit.

5. Green Belt Development: (a) PP should ensure plantation as proposed 3500square meters i.e. 33% of the

total area with 200 number of trees Plantation in the project area of indigenous local varieties like Neem, Peepal, Kadam and Kachnaar.

(b) Every effort should be made to protect the existing trees on the plot. (c) Green area including thick green-belt shall be developed in 33% of the plot

area as proposed to mitigate the effect of fugitive emissions all around the

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 77 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020

plant in consultation with the forest department as per the guidelines of CPCB.

6. PP should ensure the implementation of CER activities to the extent of Rs. 15 lakh to provide educational material & infrastructure to Govt. Primary & Middle Schools,high scholl of nearby Agral village and infrastructure to Anganwaaadi in Agral village as proposed in consultation with Collector, Jhabua..

7. Total quantity of runoff water generated and green belt area should be collected in underground tank & used for process in plant to minimize fresh water requirement.

8. All other conditions as laid in the consents of MPPCB shall be applicable. 31. Case No 7728/2020: Prior Environment Clearance for proposed to set-up Melting

Shop with Automatic Casting Process Mill into Hot Billets Re-rolling Mill at plot no. B-3 (B), adjacent to Bansal Steel Manufacturing Pvt. Ltd. casting unit, industrial area phase-II, Mandideep, Tehsil – Goharganj, Dist: Raisen (M.P.) (M.P.) Total plot area 30362.45 sq.m (3.03ha) Total Production capcity 300.0 TPD (90,000.0 TPA) M/s Bansal Ore and Metals Pvt. Ltd. through Director, Shri, Kunal Bansal,Shri Manish Khare and Shri Kartik Bansal 3rd Floor, Tawa Complex, Bittan Market, E-5, Arera Colony,Bhopal-462016 E-mail [email protected] Ph- 0755-2423736

(1) M/S Bansal Ore and Metals Pvt. Ltd. Company is a newly formed Pvt. Ltd. Company incorporated in the state of M.P. vide Certificate of Incorporation No.U27310MP2018PTC046285 dated 02.08.2018. The company is setting up a new project of Rolling Mills at B-3(B), Industrial Area Phase-II, Mandideep, Distt. Raisen (MP).

(2) The project is located in notified Industrial Growth Centre – Mandideep, Distt, - Raisen (M.P.) approved by AKVN hence exempted for public hearing as per MoEF, GoI OM dtd 10.12.2014 issued under EIA notification, 2006.

(3) The project is proposed for manufacturing of Ingot/Billet 300.00 TPD (90000 TPA). This is a rolling mill project. All non – toxic secondary metallurgical processing industries manufacturing >5000 tones/annum metal components are covered under the EIA Notification 2006 as amended 2009 and are mentioned at SN 3(a), B. Hence these projects are required to obtain prior EC before establishment.

(4) There is no inter-state boundary within 05 km and no Wildlife Sanctuaries, National Parks, and Tiger Reserves within 05 km of the boundary, hence, general conditions not attracted.

(5) The case was discussed in 463rd SEAC dtd. 01.10.2020 and recommended for grant of prior EC conditions.

(6) After recommendation today the case scheduled for presentation and after deliberation the case was discussed in depth and it is noted that :- i. The total land area of the project is 30362.45 sq.m (3.03ha). Regarding land

documents PP has submitted allotment letter dtd.03.10.2018 issued by MPAKVN(Bhopal)Ltd. As per the allotment letter the said land is allotted to M/s Bansal Ore and Metals Pvt. Ltd. through Director, Shri Manish Khare for setting up a Large industrial unit for manufacturing of M.S. Billets. The land use breakup of the project area is as follows:-

S. No. Land use Classification Area in 1 Builtup 1226 2 Industry 983 3 Water body 246 4 Marshy Land 5

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 78 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020

5 Sandy Area 26 6 Mining Area 28 7 Agriculture Land 24576 8 Open Scrub 3360 9 Waste Land 340 10 Plantation 14 11 Park Open Space 428 12 Forest 3117 Total 34349 100.0

ii. Total water requirement for operation phase of the proposed project is estimated at 688 KLD and shall be received from the AKVN supply. The source of water supply for the project is AKVN. PP has submitted letter dtd 27.07.2020 issued by MPIDC for supply of water.

iii. The water shall be required only for cooling and domestic purpose hence no industrial effluent shall be discharged. Thus the production process is zero discharge. Following are the EMP planned for proposed activities of the plant Being a secondary metallurgical unit, potential of water pollution is not

envisaged at larger level, however storm water drainage system need to be taken care preciously to prevent the flow of silt and other contaminant towards nalla, river outside of the site.

The TDS level of softner reject shall be checked regularly as being done for existing plant, and if found high shall be used for quenching purposes, otherwise wastewater shall be treated in neutralization tank and shall be taken to STP plant proposed for treatment of domestic effluent.

The raw water requirement shall be optimized. The COC in cooling system shall be maximized (such as COC=5 to 7) depending upon the TDS of the supply water.

Utilization of treated domestic wastewater in toilet flushing, greenbelt development and dust suppression;

A drain along the boundary wall shall be made , which will join the proposed settling tank/water tanks to protect the flow of contaminant towards nearby land

Regular monitoring and analysis of upstream and downstream of River Sank wrt to industry shall be continued.

Effective and strict implementation of recommendation of rain water harvesting measures. Water harvesting structure has been constructed for harvesting of water at the rate of 4021.20 cum water per annum. Therefore installation of pizometers is recommended for ground water table study.

RCC dyke/platform should be constructed to avoid leachate possibility. iv. Air emissions from melting furnaces are particulates, carbon monoxide, sulfur

dioxide, nitrogen oxides, and small quantities of chlorides and fluorides. During Tapping: Emission consists of iron oxides in addition to oxide fumes from alloys to the ladle and during pouring: particulate emissions from pouring consist of fumes, CO, VOCs, and particulates from the mold and core materials when contacted by the molten steel. As the mold cools, emissions continue. Emissions from pouring are usually uncontrolled. Following measures are proposed to mitigate negative impact of operation phase of the project on the surrounding air environment

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 79 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020

Electrically operated Induction furnace is proposed hence no pollution is envisaged from combustion of the fuel.

Installation of secondary control equipment for emissions PTZ camara has also been installed for monitoring of emission and

discharge of effluent. Regular maintenance of exhausts, chimney and other abatement

equipments Provision of spark arrestor, cooling circuit and bag filter for transfer points to

control and capture dust emission. Provision of 33 mt height for the stack for furnace and will have stack

monitoring facility (SMF) consisting of sampling port-hole, platform and access ladder. The outlet dust emission from the exhaust flue gases will be <50 mg/Nm3.

The primary fume is extracted from the electric induction furnace through duct by the exhaust fan(s) of the abatement plant. The essential requirement of electric induction furnace is to control the primary fume. The sequence in which vent and bleeder valves open is important which need attention.

Measures for minimization of dust and fume generated by discharging slag from the electric Induction furnace into slag pots for CCM.

Development of Greenbelt (5) m all around the periphery of the plant to arrest the fugitive emissions.

v. Solid waste generated during construction phase will be suitably reused for leveling the site and laying of internal roads. The top soil will be preserved and used for landscaping purpose. The solid waste generated from the process namely Furnace Slag, Used Ramming mass, mill scale, fly ash etc. shall be sold to local vendor. The spent resin from softener plant and spent oil from DG sets will be sold to MPPCB authorized vendors/agencies.

vi. Ash will be sold out to nearby brick or road contractors. No waste will be generated from process. For waste disposal, the entire Solid Waste will be disposed through MP Industrial Development Corporation Limited as obtained approval vide letter no. MPIDCL/RO/BPL/CAMP MANDIDEEP/01 Dated 20.07.2020

The quantities of solid waste generation. Furnace slag has been generated from induction furnace as solid waste

the same has been crushed in to crusher. A unit of iron recovery from slag installed (2 ton/h)

Segregated in to metallic and no metallic contents. Metallic content will be recycled back as raw material Non-metallic content has been disposed-off for road embankment, brick

manufacturing. vii. The plant water management system is designed to minimize the potential for

storm water contamination occurring at the site. This will be achieved by incorporating the following features into the storm water management system: Run-off from upstream areas will be diverted to proposed water body within

the premises through storm water drain around the plant site.

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 80 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020

The quantity of contaminated run-off generated will be minimized by diverting run-off from areas external to the plant to storm water discharge points;

Hazardous material and fuel storage areas will be bounded and drains will be provided to around these facilities to prevent entering of run-off water; and

Run-off from area external to process areas of the plant will be contained within a storage system.

Regular inspection and cleaning of storm drains. viii. The total power required for the plant is 2500 KVA, 33/0.433 KV Transformer to

be installed which is sourced from the MPEB/MPIDCL. ix. PP has proposed to provide 02 nos of recharging pits for recharging of ground

water. x. A complete firefighting system will be installed with following aspects:

A suitable high-pressure system of fire hydrants consisting of suitable number of fire-hydrants.

A complete separate fire fighting water piping network for feeding the hydrants.

The tank is located that it is accessible for the fire engines. Four numbers of main hole shall be provided for the purpose of inspection, repairs, and insertion of suction hose.

Heavy duty ABC powder type fire fighting water piping network for feeding the hydrants.

Portable CO2 extinguishers will be provided in the entire area of the proposed.

Overflow of it is collected in the domestic water tank so that the stagnation of the water is prevented, and reserved storage capacity of firefighting tank is maintained.

Automatic fire extinguishing system utilizing water will also be considered.These shall be placed or hanged on wall in a group on several suitable places.

xi. About 2766 Sq.mt.(441.00 sq mt open landscape area for plantation and 2325 sq.mt. other open landscape area) area i.e. 27% of plant land area shall be developed as green belt at plant boundaries, road sides, around offices & buildings and stretch of open lands.

xii. Under CSR activities PP has proposed Construction of Community Toilets, Water supply arrangement in school with Storage Tank & Plumbing System or contribution to Gram Panchayat under pubic water supply scheme. Distribution of Computer systems and online setup to the schools. at Pipaliya Gajju, Khejdi, Jhalarkala, Mundla, & Bamuliya Pawar village. Promotion of advanced agriculture practices and water efficient farming practices etc with budgetary provision of Rs. 52.98 lacs.

Hence It is decided to accept the recommendations of 463rd SEAC meeting dtd 01.10.2020 and accord Prior Environment Clearance for proposed to set-up Melting Shop with Automatic Casting Process Mill into Hot Billets Re-rolling Mill at plot no. B-3 (B), adjacent to Bansal Steel Manufacturing Pvt. Ltd. casting unit, industrial area phase-II, Mandideep, Tehsil – Goharganj, Dist: Raisen (M.P.) (M.P.) Total plot area 30362.45 sq.m (3.03ha) Total Production

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 81 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020

capcity 300.0 TPD (90,000.0 TPA) M/s Bansal Ore and Metals Pvt. Ltd. through Director, Shri, Kunal Bansal,Shri Manish Khare and Shri Kartik Bansal 3rd Floor, Tawa Complex, Bittan Market, E-5, Arera Colony,Bhopal-462016 subject to following specific conditions:-

(1) The entire demand of fresh water should be met through AKVN supply and there should be no extraction of ground water.

(2) PP should ensure zero waste water discharge from the process.

(3) PP should ensure air pollution control measure as proposed in EMP and should conduct regular monitoring of stack emissions and ambient air as per MPPCB / CPCB norms. For regular monitoring of air emission PP should installed ambient air monitoring stations.

(4) PP should ensure to linkage with MPIDC for disposal of solid waste as per letter dtd. 27.07.2020.

(5) PP should ensure the disposal of hazardous waste through authorized agencies and obtained consents from competent Authorities.

(6) PP should ensure the roof top area of plant area including raw material storage area, finished goods area, and office building area should be used for rain water harvesting for ground water recharge. The concrete road of the site area should be regularly cleaned.

(7) PP should obtain NOC for fire and approval for onsite offsite emergency plan, health and safety plan from the Competent Authorities.

(8) Under green area development PP should ensure : -

(a) Plantation in the factory premises within the specifying of 2m x 2m, an area of 2766 sqm shall be covered with plantation / gardening & 614 sq.mt. area is for internal & outer peripheral plantation as proposed. Subject to minimum of 33% of the total area of the project with budgetary provision of Rs 1.55 lakh.

(b) Plantation of the trees of indigenous local varieties like Neem, Ficus Benjamina, Ashok, Amaltas, Canocarpus etc.

(c) Periphery Plantation should be completed within one year within the plant premises.

(d) Every effort should be made to protect the existing trees on the plot.

(9) PP should ensure implementation of CER activity of Rs. 52.98 lakh in consultation with District Collector/gram Panchyat of nearby villages.

(10) PP should ensure all the raw material including scrap, sponge iron, sludge and oily waste shall be stored separately in designated place.

(11) Monthly monitoring should be done of all the environmental parameters and Environmental Management Cell meeting should be carried out every month.

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 82 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020 32. Case No. 7591/2020 :Prior Environment Clearance for Construction of

Manufacturing of Fertilizers Unit of Single Super Phosphate Plant, at Plot No. 26-A, 26-B, 26, 27, 28, 31, 32, 33 & 34-A AKVN Industrial Area, Tehsil - Meghnagar, DIstrict - Jhabua, M.P. Total Area: 9828.56 Production Capacity : 300.0 TPD of Powder & Granulated Super Phosphate by Director, M/S TRIMBEKSHWAR AGRO INDUSTRIES PVT. LTD Plot No. 27 & 32 AKVN Industrial Area, Meghnagar, District - Jhabua, [email protected] Mob:-9479649918

(1) The M/s Trimbekshwar Agro Industries Pvt. Ltd., Plot No. 27 & 32, AKVN Industrial Area, meghnagar, District Jhabua, MP-457779.The land of 9828.56 sqm has been allotted by DIC for industrial use only.

(2) This is an existing and modernization project which is producing of City Compost with 3000.0 MT per year, NPK Mix Fertilizers Granulated (By Mixing Only) with capacity of 15000.0 MT per year, Soil Conditioner with capacity of 8000.0 MT per year and Vermi Compost with capacity 2000.0 MT per year, respectively. In these regards, consent order has been obtained from Madhya Pradesh Pollution Control Board (MPPCB) on 14.05.2019 with consent no. AW-65282 which is applicable up to 31.05.2021.

(3) The existing manufacturing plant is in operation since 2004 and consequently was not under the purview of the EIA Notification, 2006 and hence did not require Environmental Clearance. Now as it is going for the production of Single Super Phosphate, it will require prior Environmental Clearance. As per the Schedule to the EIA Notification, 2006 & its amendments, it falls under the Sl. No. 5(a) and also it will come under category B because it does not include any Sulphuric Acid manufacturing unit inside its premises.

(4) Now, PP is proposing a chemical fertilizer unit of Single Super Phosphate Plant with capacity of 300.0 TPD of Powder & Granulated Super Phosphate which will be produced in this project.

(5) The project is proposed for Manufacturing of Fertilizers Unit of Singh Super Phosphate Plant with Production capacity 300.0 TPD of Powder & Granulated Single Super Phosphate

Sl. No. Raw Product Name Capacity 1 Rock Phosphate (RP) 170 TPD 2 Sulphuric Acid 108 TPD

(6) This is a chemical fertilizer project. All non – toxic secondary metallurgical processing industries manufacturing > Single Super Phosphate are covered under the EIA Notification 2006 as amended 2009 and are mentioned at SN 5(a), B. Hence these projects are required to obtain prior EC before establishment.

(7) There is no inter-state boundary (PWD letter dtd. 31.08.2020) within 05 km and no Wildlife Sanctuaries, National Parks, and Tiger Reserves within 05 km of the boundary, hence, general conditions not attracted.

(8) The case was discussed in 463rd SEAC dtd. 01.10.2020 and recommended for grant of prior EC conditions.

(9) After recommendation today the case was scheduled for presentation and after deliberation the case was discussed in depth and it is noted that :-

i. The M/s Trimbekshwar Agro Industries Pvt. Ltd., Plot No. 27 & 32, AKVN Industrial Area, meghnagar, District Jhabua, MP-457779.The land of 9828.56 sqm has been allotted by DIC for industrial use only).PP has submitted registered transfer deed dtd. 07.01.2020 .As per the transfer deed lease holder

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 83 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020

Praveen Engineers transferred the land to M/s Trimbekshwar Agro Industries Pvt. Ltd.,

ii. Raw materials required for production of SSP are mainly rock phosphate and sulphuric acid. Rock phosphate will be sourced from RSMM (Rajasthan State Mines or imported). The sulphuric acid will be sourced from open market (local supplier) located at surrounding districts. The minimum of 31% plus grade is suitable for the production. Sulphuric acid:The technical grade Sulfuric acid that is 98.5% pure or spent sulphuric acid is suitable for the process. Sulphuric acid will be sourced from local supplier and stored in Tanks.

iii. Total water requirement for operation phase of the proposed project is estimated at 30 KLD and shall be received from the MPIDC supply. The source of water supply for the project is MPIDC.(letter dtd.11.08.20)

iv. Total water requirement for the project during its full-fledged operation phase is estimated to be 30.0KLD water which will be met from MPIDC. The fresh water requirement for the proposed project will be used for dilution of Sulphuric Acid, absorption of Hydro Fluoro Silicic Acid in scrubber, domestic and for plantation purpose.

v. Single Super Phosphate (SSP) is a versatile three in one fertilizer because it supplies 16% P205 and 12% calcium. One Ton of SSP contains 490.0 Kg of nutrients of which only 160.0 Kg are recognize. SSP is the only phosphate fertilizer in the world which supplies 100% of its guaranteed P205 in water soluble form. It is an ideal fertilize for short duration and seasonal crops which remove 70% of their total phosphate uptake from the soil in the first 30 to 40 days of their life cycle. Here, water soluble phosphate plays an important role and thus, single super phosphate has an edge over other phosphate fertilizers.

vi. The raw water requirement for the project is Rock Phosphate – 170 TPD & Sulphuric Acid – 108 TPD which will be transported by trucks from local market.

vii. Utilization of treated domestic wastewater in toilet flushing, greenbelt development and dust suppression; A drain along the boundary wall shall be made , which will join the proposed

settling tank/water tanks to protect the flow of contaminant towards nearby land

Regular monitoring and analysis of upstream and downstream of River Sank wrt to industry shall be continue.

Effective and strict implementation of recommendation of rain water harvesting measures. Water harvesting structure have been constructed for harvesting of water at the rate of 3950 cum water per annum. Therefore installation of pizometers is recommended for ground water table study.

RCC dyke/platform should be constructed to avoid leachate possibility. viii. Air emissions from melting furnaces are particulates, carbon monoxide, sulfur

dioxide, nitrogen oxides, and small quantities of chlorides and fluorides. During Tapping: Emission consists of iron oxides in addition to oxide fumes from alloys to the ladle and during pouring: particulate emissions from pouring consist of fumes, CO, VOCs, and particulates from the mold and core materials when contacted by the molten steel. As the mold cools, emissions continue. Emissions from pouring are usually uncontrolled. Following measures are proposed to mitigate negative impact of operation phase of the project on the surrounding air environment

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 84 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020

PTZ camara has also been installed for monitoring of emission and discharge of effluent.

Regular maintenance of exhausts, chimney and other abatement equipments

During the acidulation process some acidic fumes containing fluorine are emitted from den and mixer. They are scrubbed to remove toxic gases. H2SIF6 formed in scrubber can be used to make Na2AIF6 which is useful by product. The environmental problems arising out of this proposed process is due to the emission of acidic fluoride which are released during acidulation process. The detailed system for the control of this emission has been designed and proposed to be installed in the plant. The treatment system will be capable of controlling the emission from the plant.

The acidic fumes are scrubbed in very advanced to stage venture scrubber connected in series along with a cyclonic separator. In this case water is used as the absorbent for the acidic fumes and Fluorides. The fresh water for absorbent purpose is added in the final stage of scrubbing.

The reaction between rock Phosphate and Sulphuric acid takes as follow: CO2 (PO4)6 CaF2 + 7 H2SO4- CaH4 (PO4)2 + 7 CaSO4 =2HF

Above reaction clearly indicates that 23.61 (Kg) of HF is the most that can be emitted per ton of Super Phosphate manufacturing. Scrubbing with mildly alkaline medium is demonstrated to perform at an efficiency level of 99.09% in arresting fluoride in plant.

The controlled emission can be less than 0.04 Kg of F./tone of rock Phosphate processed. The proposed process stack height will be 35 meter above the ground level.

The acidic fumes are scrubbed in very advanced to stage venture scrubber connected in series along with a cyclonic separator. In this case water is used as the absorbent for the acidic fumes and Fluorides. The fresh water for absorbent purpose is added in the final stage of scrubbing.

Development of Greenbelt (5) m all around the periphery of the plant to arrest the fugitive emissions.

ix. Silica Sludge will be generated as a Hazardous waste i.e. 0.50 TPD will be generated of solid waste & it shall be disposed as per CPCB/SPCB Norms and HW Rules.

x. Non-Hazardous Solid Waste: Other municipal solid waste generated would include kitchen waste, cardboards, papers, plastics, and garden waste. Cardboard, papers and plastic wastes will be handed over to scrap dealers and kitchen & garden waste would be sent to the nearest municipal waste collection site.

xi. The plant water management system is designed to minimize the potential for storm water contamination occurring at the site. This will be achieved by incorporating the following features into the storm water management system: Run-off from upstream areas will be diverted to proposed water body within

the premises through storm water drain around the plant site. The quantity of contaminated run-off generated will be minimized by

diverting run-off from areas external to the plant to storm water discharge points;

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 85 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020

Hazardous material and fuel storage areas will be bounded and drains will be provided to around these facilities to prevent entering of run-off water; and

Run-off from area external to process areas of the plant will be contained within a storage system.

Regular inspection and cleaning of storm drains. xii. Total power requirement is estimated to be 400.0 HP KW which will be met

from Madhya Pradesh Electricity Board (MPEB). xiii. PP has proposed to provide 02 nos of recharging pits for recharging of ground

water. xiv. About 990 Sq.mt. landscape area for plantation of land area shall be developed

as green belt by planting 310 numbers of tress at plant boundaries, road sides, around offices & buildings and stretch of open lands.

xv. Project cost is estimated Rs. 493.23 Lakhs. The investment on environmental protection measures or environmental management plan has been estimated as capital investment is estimated Rs. 51.50 Lakhs and Rs. 9.20 lakhs as a recurring cost for the project.

xvi. Under CER activities PP has proposed Construction of Community Toilets, Water supply arrangement in school with Storage Tank & Plumbing System or contribution to Gram Panchayat under pubic water supply scheme. Distribution of Computer systems and online setup to the schools. at Navagaon Khalsa, Fatepura, Ghosaliya Chhota village. Promotion of advanced agriculture practices and water efficient farming practices etc with budgetary provision of Rs. 9.86 lacs. CER activities as per notifications Proposed Budget for

CER 1. Construction of

Community Toilets, Water supply arrangement in school with Storage Tank & Plumbing System or contribution to Gram Panchayat under pubic water supply scheme.

2. Distribution of Computer systems and online setup to the schools.

Implementation area project capital cost including land and machinery = INR 493.23 Lakhs Proposed CER 2% of the which is approx. =INR 9.86 Lakh.

With the help of Gram Panchayat: • Nayagaon Khalsa Village,

2.30 KM -W • Fatepura Village – 2.70 KM

– E • Ghosaliya chhota Village –

2.60 KM – NE

Hence It is decided to accept the recommendations of 463rd SEAC meeting dtd 01.10.2020 and accord Prior Environment Clearance for proposed Manufacturing of Fertilizers Unit of Singh Super Phosphate Plant (Total Production = 300.0 TPD of Powder & Granulated Single Super Phosphate) (Total Area = 9828.56 sq.mt., Built-up Area of Plant = 3300.00 sqm) at Village - AKVN Industrial Area, Tehsil - Meghnagar, District - Jhabua (MP) by M/s Trimbekshwar Agro Industries Pvt. Ltd, Shri Vikas Gupta, Director, Plot No. 27 & 32, AKVN Industrial Area, Meghnagar, DIst. Jhabua, MP – 457779 subject to following specific conditions:-

(1) The entire demand of fresh water should be met through AKVN supply and there should be no extraction of ground water.

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 86 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020

(2) PP should ensure zero waste water discharge from the process. As per the proposal submitted 100% waste water shall be re-cycled in the process. No water shall be discharged outside the premises.

(3) The acidic liquid from the scrubbing system shall be used in the process.

(4) Silica sludge from SSP manufacturing process shall be stored in designated covered and lined yard and the same shall be used as filler for the fertilizer. A logbook of the same shall be maintained.

(5) The gases from the den conveyor will be separated by scrubber fan Ventury, Cyclone separator and cyclonic scrubbers.

(6) PP should ensure air pollution control measure as proposed in EMP and should conduct regular monitoring of stack emissions and ambient air as per MPPCB / CPCB norms. For regular monitoring of air emission PP should installed ambient air monitoring stations.

(7) PP should ensure the disposal of hazardous waste through authorized agencies and obtained consents from competent Authorities.

(8) PP should ensure all the raw material shall be stored separately in designated place.

(9) Garland drain surrounding the raw material storage area has to be constructed which shall be connected to the recycling system.

(10) Scrubber system adequate capacity shall be installed to control fluorine and hydrogen fluoride gas emission from the stack so as to keep the values as per the norms of MPPCB.

(11) Concentration of fluoride has to be monitored in the ground water on regular basis.

(12) PP should obtain NOC for fire and approval for onsite offsite emergency plan, health and safety plan from the Competent Authorities.

(13) Regular monitoring of influent and effluents surface, sub-surface and ground water shall be ensured and treated waste water shall be re-cycled in the process. Leachate study for effluent generated & analyses should also be regularly carried out and report submitted to ministry and MPPCB.

(14) All types of solid wastes shall be handled and managed as per the prescribed norms.

(15) In view of use of concentrated sulphuric acid in the process industry shall take all precautions to avoid accidents from spillage/storage/ handling etc.

(16) Production of the sulphuric acid will be not allowed within the premises.

(17) Risk & Disaster Management Plan along with the mitigation measures should be prepared and copy shall be submitted to Ministry of Environment & Forests, GoI & MPPCB.

(18) Under green area development PP should ensure : -

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 87 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020

(a) Green belt development in an area of 990 sqm shall be covered with plantation by planting 310numbers of trees.

(b) Plantation of the trees of indigenous local varieties like Neem, Ficus Benjamina, Ashok, Amaltas, Canocarpus etc. Periphery Plantation should be completed within one year within the plant premises.

(c) Every effort should be made to protect the existing trees on the plot.

(d) At least 33% of the total plot area including the thick green belt shall be developed as green area through tree plantation.

(19) PP should ensure implementation of CER activity of Rs. 9.86 lakh in consultation with District Collector/gram Panchyat of nearby villages.

(20) Monthly monitoring should be done of all the environmental parameters and Environmental Management Cell meeting should be carried out every month.

(21) Secondary fugitive emissions from all sources shall be controlled within latest permission limits issued by the Ministry and regularly monitored. Guidelines / Code or practice issued by CPCB shall be followed.

33. Case no. 6285/2019: Environmental Clearance for proposed Construction of residential cum commercial multi storied building at Scheme NO.136, Plot no – CMR -5 Niranjanpur INDORE (MP) Total land area 8588 sq. m, Built up area 29214 sq.m by Executive Engineer, M/s Indore Development Authority, 7, Race Course Road, Dist. Indore, MP-452003 Mob no. 9893699178 Email: [email protected] 1. Indore Development Authority (IDA) is proposing/constructing of ‘Multi Storied

Residential Cum Commercial Building Project’ at plot no. CMR-5, Scheme No. 136 at Niranjanpur, Indore. The proposed Construction of Multi Storied Residential cum Commercial Building Project, Plot No. CMR-5, Scheme No. 136, Niranjanpur, Distt. - Indore, (M.P.)

2. The proposed multi storied residential cum commercial building project at plot no. CMR-5, Scheme 136, Niranjanpur, Indore, M.P. The Co-ordinates of the project site are 22°46ʹ30.82ʹʹN & 75°53ʹ8.58ʹʹE.

3. The project involves 180 nos of 2BHK flats and 36 nos of 3BHK flats, 41 Nos. Shops & Offices. The total maximum height of the project will be B+G+9 meters i.e. about 30.0 m.

4. Ralamandal Wildlife Sanctuary is 14.0 km in SSE direction from the project site. 5. As per the approval of T & CP Indore (vide letter 9605 dtd 03.11.2017) the total

land area of the project is 8588.00 Sq.mt.. The total built up area proposed by PP is – 29214.00 sq. m. The project comes under 8 (a) category (B) of schedule of EIA Notification, 2006 as the total construction is between 20,000 sq.m & 1,50,000 sq.m.

6. The project is a case of violation on account of not securing prior environment clearance before beginning the constriction activities at site.

7. Chronology of the project: The revised building plans were sanctioned as per T & CP in November 2017.

The construction was started in 2014-19 and the construction had already come up to plinth level, way back in 2014 itself, which was prior to the Notification of 14.09.2006 in its opening paragraph itself had clearly stated that

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 88 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020

only new projects after date of publication would need such ‘Environmental Clearance’

In the light of notification issued by MoEF & CC dtd 14.03.2017, which provides the guidelines to deal with violation cases at EAC, MoEF & CC, New Delhi, we had submitted the application under violation category for the grant of Environment Clearance at EAC, MoEF & CC.

As per notification dated 8 March 2018 in which it has been directed that all “Category B” project will be appraised at SEAC, accordingly PP has again applied in State Expert Appraisal Committee.

Baseline Environmental Monitoring has been done for one month i.e. October 2019.

8. Committee considering the recent GoI, MoEF & CC Notification dated 8th March, 2018 recommends that case may be dealt as per the provisions laid down in this notification and the project may granted Terms of Reference for undertaking Environment Impact Assessment and preparation of Environment Management Plan on assessment of ecological damage, remediation plan and natural and community resource augmentation plan and it shall be prepared as a independent chapter in the EIA report by the accredited consultant and the collection and analysis of data for assessment of ecological damage, preparation of remediation plan and natural and community resource augmentation plan shall be done by an environmental laboratory accredited by the National Accreditation Board for Testing and Calibration Laboratories.

9. Application for ToR was submitted on 22nd May 2019 and the presentation for ToR was made in 382nd SEAC meeting dtd. 09th July 2019. ToR was issued vide letter no.542/PS-MS/ MPPCB/ SEAC/ TOR (382)/2019 dated 08.08.2019.

10. PP has submitted the EIA report vide letter 2552 dated 11.08.2020 which was sent to SEAC vide letter no. Letter no. 2135-36/SEIAA/20 dated 14.08.2020, which was placed before the committee.

11. PP has submitted the remediation plan and natural community resource augmentation plan corresponding to the ecological damage assessed and economic benefits derived due to violation in the tune of suggested guidelines by the committee, with the supported by documentary proofs, such as bills, CA audit, certificates, photographs, prescribed various undertakings and CER.

12. The case was discussed in SEAC meetings 463rd SEAC meeting dated 01.10.2020 and is recommended for grant of EC subject special conditions and submission of bank gurantee (BG) with 03 years validity of Rs. 23.88 lakhs (equivalent to amount proposed in remediation and resource augmentation plan) with the MP Pollution control Board.

13. As per above recommendation the case was considered in 644th SEIAA meeting dated 07.10.2020. PP has submitted BG amount of Rs. 23.88 lakhs (equivalent to amount proposed in remediation and resource augmentation plan)

14. Today the case was scheduled for presentation and after deliberation the case was discussed in depth and it is recorded that :- i. Regarding land documents PP has submitted Collectorate office order district

Indore dtd. 08.12.2006 for the Award Yojana kramank 136. As per the order the said land is under possession of Indore development Authority.

ii. Current Construction Status

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 89 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020

24823 sqm (85% of the total built up area) built up area is already constructed.

iii. Total water requirement for the entire project will be 156 KLD. Fresh water requirement will be 104 KLD and recycle water is 112 KLD. The source of fresh water is municipal water supply is available. PP has obtained IMC NOC for Water supply dated 12.02.2019.

iv. The total 112 KLD waste water will be generated from the project which will be treated in the STP Capacity - 125 KLD based on MBBR based technology.

The treated effluent from STP shall be recycled/re-used for flushing & horticulture purpose. PP stated that no sewage or untreated effluent water would be discharged through storm water drains or municipal drain. PP has submitted Municipal Corporation, Indore letter dtd. 31.07.2018 for the disposal of extra treated waste water.

v. Total waste 0.50185 Tone/day, this consist all types of wastes, Residential waste- 0.4996 Tone/day, horticulture waste 0.0022 Tone/day and these all type of waste shall be treated/ disposed off as per provision made in the MSW Rules 2016. PP has submitted Municipal Corporation, Indore letter dtd. 31.07.2018 for the disposal of MSW.

vi. For rainwater harvesting, 2 recharge pits will be constructed for harvesting rain water. The total recharge capacity of these pits about 136.0 m3/hr.

vii. The total power demand would be 1890 KVA (1512.0 KW) which will be met from Madhya Pradesh Electricity Board (MPEB). Backup power supply, 1 no. of DG set is proposed of 315.0 KVA capacity for lift and others purposed in case of power failure or in emergency.

Window-wall ratio are balanced perfectly to achieve maximum daylight, no glare and minimum heat ingress

Regional and eco friendly materials were used. Aluminum used have recycled content.

Fly ash based cement was used. Public areas will be cooled by natural ventilation as opposed to air

conditioning. LEDs are being used for high efficiency in the common areas. Maximization of use of natural lighting through building design. Use of Solar Water Heating in group housing as per requirement. Solar lighting has been provided in common areas & streets. Sunscreen films on windows to reduce heating inside buildings

viii. Adequate provisions are made for parking in basement and stilt 216 ECS where 180 nos for 2BHK flats and 36 for 3BHK flats. Also parking facility for two wheelers shall be provided. Sufficient parking place are provided in cellars. About 6692.0 m2 parking area will be provided.

ix. Adequate fire protection facilities will be installed including fire detectors, fire alarm and fire fighting system to guard the building against fires. All fire protection facilities will be designed as per the National Building Code given in 2005.. Wet Riser System Portable Fire Extinguisher Sprinkler System Automatic Sprinkler System in basement

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 90 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020

Automatic Detection and Alarm System Manually Operated Electric Fire Alarm System Yard Hydrant (External Hydrant System) Fire Tender Route will be given with access to each tower/block (as evident

from the site plan). Provision of fire escape staircase External yard Hydrants in galvanized steel fire hose cabinet (weather-proof)

x. Total green area proposed for the project is 736 sq.m. Total 1450 Nos. trees have been planted on the periphery & other landscaping area of the site Total 200 Nos. trees have been planted on the periphery & other landscaping area of the site.The species Harsingar (Nyctanthes arbortristis), Cassia, Neem (Azadirachta indica), Bougainvillea, Pila bans (Bambusa vulgaris), Champa (Michelia), chukrasia (Chukrasia velutina), Pakhar, Ashok pendula (Polyalthia longifolia), Gulmohar, Pelta farm etc.

xi. PP has submitted the remediation plan and natural community resource augmentation plan corresponding to the ecological damage assessed and economic benefits derived due to violation in the tune of suggested guidelines by the committee, with the supported by documentary proofs, such as bills, CA audit, certificates, photographs, prescribed various undertakings.

xii. PP has proposed Rs. 1,84,53,620 /- (Rs. 23,88,000/- as Remediation Cost and Rs. 1,60,65,620 /- as EMP) for this project and PP, M/s Indore Development Authority, 7, Race Course Road, District-Indore (M.P.)-452003 has proposed to submit bank guarantee of INR Rs. 23,88,000/- towards Remediation Plan.

xiii. PP has proposed to submit bank guarantee of INR 23,88,000.00 towards Remediation Plan and Natural & Community Resource Augmentation Plan with following expenditure:-

Activity First Year (INR)

1. Environmental Management

For MSW Treatment/Installation of organic

composter 1,68,000

Fire & Safety Management 4,20,000

Rain water harvesting 1,00,000

EMP Implementation (Environmental Monitoring) 1,50,000

2. Community Resource Development

Help of Municipal Authority for maintenance of

already developed Park in nearby areas/Plantation 50,000

3. Natural Resources Augmentation

Solar system 15 KW @ 1,00,000/KW 15,00.00,000

Total Remediation Cost 23,88,000

xiv. Under CER activities PP has proposed Rs. 1.198 Crores up to five years for the following activities:

Project Cost in INR Crore Rs. 59.42 Crores

Corporate Environment Responsibility in INR Crore @ 2% of the project cost Rs. 1.198 Crores

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 91 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020

S. No. Activity

Year wise implementation and Budgetary provision during operation phase Total

Budget (Rs.) 1st

Year 2nd

Year 3rd

Year 4th

Year 5th

Year

1 Construction of sanitation facilities (toilet) in schools (2 toilets each year)

75000.0 75000.0 75000.0 75000.0 75000.0 375000.0

2 Periodic medical check-up camp by appointing specialist doctor for eyes, skin, heart and dental twice in a year

100000.0 100000.0 100000.0 100000.0 100000.0 500000.0

3 Free of cost distribution of medicine / body check-up tests in the area 75000.0 75000.0 75000.0 75000.0 75000.0 375000.0

4 Training to the locals related to healthcare 50000.0 50000.0 50000.0 50000.0 50000.0 250000.0

5 Assistance in providing study materials, uniform, books to the poor students located nearby project area

150000.0 150000.0 150000.0 150000.0 150000.0 750000.0

6 Distribution of saplings among project site or nearby area to be planted in the open and degraded areas

150000.0 150000.0 150000.0 150000.0 150000.0 750000.0

7 Provision of solar lantern’s to nearby project 100000.0 100000.0 100000.0 100000.0 100000.0 500000.0

8 Installation of sanitary vending machines in schools

400000.0 400000.0 400000.0 400000.0 400000.0 2000000.0

9 Development of external electricity in and around the project area

300000.0 300000.0 300000.0 300000.0 300000.0 1500000.0

10 Vegetation/landscaping or Development of dense greenery in and around the project area

300000.0 300000.0 300000.0 300000.0 300000.0 1500000.0

11 Maintenance and development of roads nearby project

300000.0 300000.0 300000.0 300000.0 275000.0 1475000.0

12 Maintenance of school building & community center in nearby project area

200000.0 200000.0 200000.0 200000.0 200000.0 1000000.0

13 Miscellaneous Charge 200000.0 200000.0 200000.0 200000.0 200000.0 1000000.0 Total 11,975,000.0

The submissions made by the PP were found to be satisfactory and acceptable hence It is decided to accept the recommendations of 463rd SEAC meeting dtd. 01.10.2020 with special conditions and accord Environmental Clearance for the proposed Construction of residential cum commercial multi storied building at Scheme NO.136, Plot no – CMR -5 Niranjanpur INDORE (MP) Total land area 8588 sq. m, Built up area 29214 sq.m by Executive Engineer, M/s Indore Development Authority, 7, Race Course Road, Dist. Indore, MP-452003, subject to following specific conditions imposed by SEIAA:-

1. The fresh water supply arrangement should be met through Municipal corporation Indore (letter dtd. 12.02.2019.) and there should no extraction of ground water.

2. The inlet and outlet point of natural drain system should be maintained with adequate size of channel for ensuring unrestricted flow of water.

3. Disposal of waste water.

a. PP should ensure disposal of waste water arrangement should be done in such a manner that water supply sources are not impaired.

b. PP should explore the possibility to linkage with Nagar Nigam Indore, for sewer line for disposal of extra treated waste water.

c. The project not having provision for discharge of excess treated sewage cannot permit to start operation unless proper arrangements are put in place for its safe handling.

4. Solid Waste Management:

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 92 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020

a. Separate wet and dry bins must be provided at the ground level for facilitating segregation of waste.

b. The solid waste generated should be properly collected and segregated. Wet garbage should be composted and dry inert solid waste should be disposed off to the approved sites for land filling after recovering recyclable material.

c. Ensure linkage with Indore Municipal Corporation, Indore for final disposal of MSW.

5. PP should ensure building height, road width, front MOS and side / rear as per approved layout of T & CP.

6. For fire fighting:-

PP should ensure distance of fire station approachable from the project site & provide fire fighting measures such as water sprinklers, fire hydrant pipe, Adequate fire fighting requirement shall be taken into account while designing the electrical distribution system, Wet risers and hose reel, Adequate numbers of fire extinguishers, and underground water storage tank properly.

7. For Rain Water Harvesting, and Storm water management:-

PP should ensure the rain water harvesting with 2 recharging pits and these pits should be connected laterally to consume the surplus runoff. In addition, PP should provide recharging trenches. The base of the trenches should be Kachha with pebbles.

8. Car Parking;

PP should ensure to Parking facilities shall be provided for 216 ECS where 180 nos for 2BHK flats and 36 for 3BHK flats. Also parking facility for two wheelers shall be provided. Sufficient parking place are provided in cellars. About 6692.0 m2 parking area will be provided.

9. Green belt :-

PP should ensure plantation in an area of 376 sq.mt. as a green belt and landscaped area with regular maintenance and also explore the possibility to plant trees of indigenous local varieties like Harsingar (Nyctanthes arbortristis), Cassia,Neem (Azadirachta indica), Bougainvillea,Pila bans (Bambusa vulgaris), Champa (Michelia), chukrasia Chukrasia velutina),Pakhar ,Ashok pendula (Polyalthia longifolia),Gulmohar, Pelta farm.etc.

10. PP should ensure to complete the activities listed under ecological remediation, Natural resource augmentation & community resource augmentation for a total amount of Rs. 23.88 lakhs

11. PP shall carry out the works assigned under ecological damage, natural resource augmentation and community resource augmentation within a stipulated period and submitted to same in MPSEIAA.

12. PP should ensure the implementation of CER activities to the extent of Rs. 1.198 Crores will be used for construction of community toilets, Water supply arrangement in school with Storage Tank & Plumbing System or contribution to Gram Panchayat under pubic water supply scheme & Distribution of Computer systems to the schools.

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 93 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020 34. Case No. 7821/20 Prior Environmental Clearance for Sand Quarry in an area of 2.0

ha. (9216 cum per annum) (Khasra No. 01), Village - Khairwada, Tehsil - Mohkhed, Dist. - Chindwara (MP) by Shri Shishir Khandar, Samashish Bhavan, 18, Malik Complex, Tenament Hotel, Airport Center Plient, Somalwada, Wardha Road, Dist. - Nagpur, Mah. 440028, Email – [email protected], Mobile – 9407055948.

This case was recommended in 464th SEAC meeting dated 03.10.2020 and it was recorded that..........

“------------PP has submitted the response of above quarries same date vide letter dated 03.10.2020, which was placed before the committee and the same found satisfactory. Committee observed that even after deducting the volume of sand in the submerged area, the sanctioned volume of sand can be evacuated from the available dry area as per the revised plan submitted by PP. The mining shall be done as per the approved mine plan by concerned DGMs. The EMP and other submissions made by the PP were found to be satisfactory and acceptable, hence committee decided to recommend the case for grant of prior EC subject to the following special conditions in addition to the standard conditions at annexure ‘B’:

PP/Consultant made a presentation on all aspects of the project and all concerned issues were discussed in detail. After detailed discussions and perusal of recommendations of 464th SEAC meeting dated 03.10.2020, presentation made by the PP in SEIAA, it was decided to accept the recommendation of SEAC for grant of prior EC to the project subject to the following specific conditions:-

I. PP shall not start mining activity before execution of lease agreement.

II. The production capacity shall be limited to the quantity as recommended by SEAC.

III. No ramp will be allowed within the river basin to transport sand to the other bank. Transportation will be allowed on the bank side where the mineral is being excavated.

IV. The entire lease area should be properly fenced and boundary stones marked at the site.

V. No in-stream mining shall be allowed. The local authorities should ensure that the mining activity is confined only in the dry portion where sand is exposed.

VI. The depth of the pit shall be as per Approved Mining Plan.

VII. No transportation shall be permitted within the village.

VIII. Alternate transportation route should be decided in consultation with the local Gram Panchayat.

IX. Total 2400 saplings of suitable tree species i.e. Neem, Pipal, Bargad, Mango, Gulmohar, Sissoo, Kathal, Guava, Imli, etc. shall be planted by PP in first three years under plantation programme at river bank and approach road in consultation with Gram Panchayat/ DM. PP shall also explore and identify the chunk of land in the area from revenue record to carry out plantation programme as proposed.

X. Over loading will be strictly prohibited.

XI. Water sprinkling will be done on the approach road on the regular basis.

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 94 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020

XII. PP must ensure the implementation of following activities with separate budget provision of total Rs. 90,000/- under CER as committed:

a) 1st, 2nd & 3rd Year: To provide Computers at Village School (3 Nos × 30,000).

PP shall ensure to contruct toilet with proper plumbing in the school of above village and contribute on behalf of village in Jal Jeewan Mission in consultation with Janpad Panchayat and PHED. PP shall give preference to develop/provide infrastructural facilities in schools or aanganwadies of above villages. The modification to the above activities can be made with the permission of the district administration and need based activity for the development of nearby villages shall be implemented by PP in consultation with the District Collector and Gram Panchayat.

XIII. PP should ensure to submit half yearly compliance report, Plantation and CER activity report along with photographs of all activities in MP-SEIAA. If PP is failed to upload or submit two consecutive half yearly compliance reports of EC conditions to concerned authority (SEIAA and Regional Office, MoEF&CC,GoI,Bhopal) than prior environmental clearance issued to PP will automatically be treated as cancelled/ revoked as per OM No. 930/SEIAA/2019 dated 30.05.2019 issued by MPSEIAA.

Hence, Prior Environmental Clearance is granted for Sand Quarry in an area of 2.0 ha. (9216 cum per annum) (Khasra No. 01), Village - Khairwada, Tehsil - Mohkhed, Dist. - Chindwara (MP) for the lease period to Shri Shishir Khandar, Samashish Bhavan, 18, Malik Complex, Tenament Hotel, Airport Center Plient, Somalwada, Wardha Road, Dist. - Nagpur, Mah. 440028, Email – [email protected], Mobile – 9407055948.

35. Case No. 7839/20 Prior Environmental Clearance for Sand Quarry in an area of 1.50 ha. (7830 cum per annum) (Khasra No. 01), Village - Kaparwadi, Tehsil - Chhindwara, Dist. - Chindwara (MP) by Shri Shishir Khandar, Samashish Bhavan, 18, Malik Complex, Tenament Hotel, Airport Center Plient, Somalwada, Wardha Road, Dist. - Nagpur, Mah. 440028, Email – [email protected], Mobile – 9407055948.

This case was recommended in 464th SEAC meeting dated 03.10.2020 and it was recorded that..........

“------------PP has submitted the response of above quarries same date vide letter dated 03.10.2020, which was placed before the committee and the same found satisfactory. Committee observed that even after deducting the volume of sand in the submerged area, the sanctioned volume of sand can be evacuated from the available dry area as per the revised plan submitted by PP. The mining shall be done as per the approved mine plan by concerned DGMs. The EMP and other submissions made by the PP were found to be satisfactory and acceptable, hence committee decided to recommend the case for grant of prior EC subject to the following special conditions in addition to the standard conditions at annexure ‘B’:

PP/Consultant made a presentation on all aspects of the project and all concerned issues were discussed in detail. After detailed discussions and perusal of recommendations of 464th SEAC meeting dated 03.10.2020, presentation made by

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 95 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020

the PP in SEIAA, it was decided to accept the recommendation of SEAC for grant of prior EC to the project subject to the following specific conditions:-

I. PP shall not start mining activity before execution of lease agreement.

II. The production capacity shall be limited to the quantity as recommended by SEAC.

III. No ramp will be allowed within the river basin to transport sand to the other bank. Transportation will be allowed on the bank side where the mineral is being excavated.

IV. The entire lease area should be properly fenced and boundary stones marked at the site.

V. No in-stream mining shall be allowed. The local authorities should ensure that the mining activity is confined only in the dry portion where sand is exposed.

VI. The depth of the pit shall be as per Approved Mining Plan.

VII. No transportation shall be permitted within the village.

VIII. PP shall leave set bak from the bridge as per provision of Enforcement & Monitoring Guidelines for Sand Mining, 2020 issued by the MoEF&CC, GoI

IX. Alternate transportation route should be decided in consultation with the local Gram Panchayat.

X. Total 1800 saplings of suitable tree species i.e. Neem, Pipal, Bargad, Mango, Gulmohar, Sissoo, Kathal, Guava, Imli, etc. shall be planted by PP in first three years under plantation programme at river bank and approach road in consultation with Gram Panchayat/ DM. PP shall also explore and identify the chunk of land in the area from revenue record to carry out plantation programme as proposed.

XI. Over loading will be strictly prohibited.

XII. Water sprinkling will be done on the approach road on the regular basis.

XIV. PP must ensure the implementation of following activities with separate budget provision of total Rs. 1,20,000/- under CER as committed:

a) 1st, 2nd & 3rd Year: Overhead Water tank with water filter will be provided at Kaparwadi

Primary School – Rs. 10,000/- Repairing of Boundary wall and Color paint with sticker painting with

plantation across boundary wall – 1,10,000/-

PP shall ensure to contruct toilet with proper plumbing in the school of above village and contribute on behalf of village in Jal Jeewan Mission in consultation with Janpad Panchayat and PHED. PP shall give preference to develop/provide infrastructural facilities in schools or aanganwadies of above villages. The modification to the above activities can be made with the permission of the district administration and need based activity for the development of nearby villages shall be

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 96 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020

implemented by PP in consultation with the District Collector and Gram Panchayat.

XIII. PP should ensure to submit half yearly compliance report, Plantation and CER activity report along with photographs of all activities in MP-SEIAA. If PP is failed to upload or submit two consecutive half yearly compliance reports of EC conditions to concerned authority (SEIAA and Regional Office, MoEF&CC,GoI,Bhopal) than prior environmental clearance issued to PP will automatically be treated as cancelled/ revoked as per OM No. 930/SEIAA/2019 dated 30.05.2019 issued by MPSEIAA.

Hence, Prior Environmental Clearance is granted for Sand Quarry in an area of 1.50 ha. (7830 cum per annum) (Khasra No. 01), Village - Kaparwadi, Tehsil - Chhindwara, Dist. - Chindwara (MP) for the lease period to Shri Shishir Khandar, Samashish Bhavan, 18, Malik Complex, Tenament Hotel, Airport Center Plient, Somalwada, Wardha Road, Dist. - Nagpur, Mah. 440028, Email – [email protected], Mobile – 9407055948.

36. Case No. 7840/20 Prior Environmental Clearance for Sand Quarry in an area of 1.0 ha. (2000 cum per annum) (Khasra No. 01), Village - Bijorifulla, Tehsil - Parasia, Dist. - Chindwara (MP) by Shri Shishir Khandar, Samashish Bhavan, 18, Malik Complex, Tenament Hotel, Airport Center Plient, Somalwada, Wardha Road, Dist. - Nagpur, Mah. 440028, Email – [email protected], Mobile – 9407055948.

This case was recommended in 464th SEAC meeting dated 03.10.2020 and it was recorded that..........

“------------PP has submitted the response of above quarries same date vide letter dated 03.10.2020, which was placed before the committee and the same found satisfactory. The mining shall be done as per the approved mine plan by concerned DGMs. The EMP and other submissions made by the PP were found to be satisfactory and acceptable, hence committee decided to recommend the case for grant of prior EC subject to the following special conditions in addition to the standard conditions at annexure ‘B’:

PP/Consultant made a presentation on all aspects of the project and all concerned issues were discussed in detail. After detailed discussions and perusal of recommendations of 464th SEAC meeting dated 03.10.2020, presentation made by the PP in SEIAA, it was decided to accept the recommendation of SEAC for grant of prior EC to the project subject to the following specific conditions:-

I. PP shall not start mining activity before execution of lease agreement.

II. The production capacity shall be limited to the quantity as recommended by SEAC.

III. No ramp will be allowed within the river basin to transport sand to the other bank. Transportation will be allowed on the bank side where the mineral is being excavated.

IV. The entire lease area should be properly fenced and boundary stones marked at the site.

V. No in-stream mining shall be allowed. The local authorities should ensure that the mining activity is confined only in the dry portion where sand is exposed.

VI. The depth of the pit shall be as per Approved Mining Plan.

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 97 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020

VII. No transportation shall be permitted within the village.

VIII. Alternate transportation route should be decided in consultation with the local Gram Panchayat.

IX. Total 1200 saplings of suitable tree species i.e. Neem, Pipal, Bargad, Mango, Gulmohar, Sissoo, Kathal, Guava, Imli, etc. shall be planted by PP in first three years under plantation programme at river bank and approach road in consultation with Gram Panchayat/ DM. PP shall also explore and identify the chunk of land in the area from revenue record to carry out plantation programme as proposed.

X. Over loading will be strictly prohibited.

XI. Water sprinkling will be done on the approach road on the regular basis.

XV. PP must ensure the implementation of following activities with separate budget provision of total Rs. 60,000/- under CER as committed:

a) 1st, 2nd & 3rd Year: Overhead Water tank with water filter will be provided at Bijorifulla

Primary School – Rs. 10,000/- To provide Swings & slides to Village school – Rs. 50,000/-

PP shall ensure to contruct toilet with proper plumbing in the school of above village and contribute on behalf of village in Jal Jeewan Mission in consultation with Janpad Panchayat and PHED. PP shall give preference to develop/provide infrastructural facilities in schools or aanganwadies of above villages. The modification to the above activities can be made with the permission of the district administration and need based activity for the development of nearby villages shall be implemented by PP in consultation with the District Collector and Gram Panchayat.

XII. PP should ensure to submit half yearly compliance report, Plantation and CER activity report along with photographs of all activities in MP-SEIAA. If PP is failed to upload or submit two consecutive half yearly compliance reports of EC conditions to concerned authority (SEIAA and Regional Office, MoEF&CC,GoI,Bhopal) than prior environmental clearance issued to PP will automatically be treated as cancelled/ revoked as per OM No. 930/SEIAA/2019 dated 30.05.2019 issued by MPSEIAA.

Hence, Prior Environmental Clearance is granted for Sand Quarry in an area of 1.0 ha. (2000 cum per annum) (Khasra No. 01), Village - Bijorifulla, Tehsil - Parasia, Dist. - Chindwara (MP) for the lease period to Shri Shishir Khandar, Samashish Bhavan, 18, Malik Complex, Tenament Hotel, Airport Center Plient, Somalwada, Wardha Road, Dist. - Nagpur, Mah. 440028, Email – [email protected], Mobile – 9407055948.

37. Case No. 7841/20 Prior Environmental Clearance for Sand Quarry in an area of 1.0 ha. (6500 cum per annum) (Khasra No. 369), Village - Sunari Mohgaon, Tehsil - Chhindwara, Dist. - Chindwara (MP) by Shri Shishir Khandar, Samashish Bhavan, 18, Malik Complex, Tenament Hotel, Airport Center Plient, Somalwada, Wardha

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 98 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020

Road, Dist. - Nagpur, Mah. 440028, Email – [email protected], Mobile – 9407055948.

This case was recommended in 464th SEAC meeting dated 03.10.2020 and it was recorded that..........

“------------PP has submitted the response of above quarries same date vide letter dated 03.10.2020, which was placed before the committee and the same found satisfactory. Committee observed that even after deducting the volume of sand in the submerged area, the sanctioned volume of sand can be evacuated from the available dry area as per the revised plan submitted by PP. The mining shall be done as per the approved mine plan by concerned DGMs. The EMP and other submissions made by the PP were found to be satisfactory and acceptable, hence committee decided to recommend the case for grant of prior EC subject to the following special conditions in addition to the standard conditions at annexure ‘B’:

PP/Consultant made a presentation on all aspects of the project and all concerned issues were discussed in detail. After detailed discussions and perusal of recommendations of 464th SEAC meeting dated 03.10.2020, presentation made by the PP in SEIAA, it was decided to accept the recommendation of SEAC for grant of prior EC to the project subject to the following specific conditions:-

I. PP shall not start mining activity before execution of lease agreement.

II. The production capacity shall be limited to the quantity as recommended by SEAC.

III. No ramp will be allowed within the river basin to transport sand to the other bank. Transportation will be allowed on the bank side where the mineral is being excavated.

IV. The entire lease area should be properly fenced and boundary stones marked at the site.

V. No in-stream mining shall be allowed. The local authorities should ensure that the mining activity is confined only in the dry portion where sand is exposed.

VI. The depth of the pit shall be as per Approved Mining Plan.

VII. No transportation shall be permitted within the village.

VIII. Alternate transportation route should be decided in consultation with the local Gram Panchayat.

IX. Total 1200 saplings of suitable tree species i.e. Neem, Pipal, Bargad, Mango, Gulmohar, Sissoo, Kathal, Guava, Imli, etc. shall be planted by PP in first three years under plantation programme at river bank and approach road in consultation with Gram Panchayat/ DM. PP shall also explore and identify the chunk of land in the area from revenue record to carry out plantation programme as proposed.

X. Over loading will be strictly prohibited.

XI. Water sprinkling will be done on the approach road on the regular basis.

XVI. PP must ensure the implementation of following activities with separate budget provision of total Rs. 75,000/- under CER as committed:

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 99 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020

a) 1st, 2nd & 3rd Year: Overhead Water tank with water filter will be provided at Sunari

Mohgaon Primary School – Rs. 10,000/- To provide Bench’s at Village Primary School (32 Nos) – 65,000/-

PP shall ensure to contruct toilet with proper plumbing in the school of above village and contribute on behalf of village in Jal Jeewan Mission in consultation with Janpad Panchayat and PHED. PP shall give preference to develop/provide infrastructural facilities in schools or aanganwadies of above villages. The modification to the above activities can be made with the permission of the district administration and need based activity for the development of nearby villages shall be implemented by PP in consultation with the District Collector and Gram Panchayat.

XII. PP should ensure to submit half yearly compliance report, Plantation and CER activity report along with photographs of all activities in MP-SEIAA. If PP is failed to upload or submit two consecutive half yearly compliance reports of EC conditions to concerned authority (SEIAA and Regional Office, MoEF&CC,GoI,Bhopal) than prior environmental clearance issued to PP will automatically be treated as cancelled/ revoked as per OM No. 930/SEIAA/2019 dated 30.05.2019 issued by MPSEIAA.

Hence, Prior Environmental Clearance is granted for Sand Quarry in an area of 1.0 ha. (6500 cum per annum) (Khasra No. 369), Village - Sunari Mohgaon, Tehsil - Chhindwara, Dist. - Chindwara (MP) for the lease period to Shri Shishir Khandar, Samashish Bhavan, 18, Malik Complex, Tenament Hotel, Airport Center Plient, Somalwada, Wardha Road, Dist. - Nagpur, Mah. 440028, Email – [email protected], Mobile – 9407055948.

38. Case No. 7842/20 Prior Environmental Clearance for Sand Quarry in an area of 2.0 ha. (5000 cum per annum) (Khasra No. 114), Village - Rampur, Tehsil - Junnardeo, Dist. - Chindwara (MP) by Shri Shishir Khandar, Samashish Bhavan, 18, Malik Complex, Tenament Hotel, Airport Center Plient, Somalwada, Wardha Road, Dist. - Nagpur, Mah. 440028, Email – [email protected], Mobile – 9407055948.

This case was recommended in 464th SEAC meeting dated 03.10.2020 and it was recorded that..........

“------------PP has submitted the response of above quarries same date vide letter dated 03.10.2020, which was placed before the committee and the same found satisfactory. Committee observed that even after deducting the volume of sand in the submerged area, the sanctioned volume of sand can be evacuated from the available dry area as per the revised plan submitted by PP. The mining shall be done as per the approved mine plan by concerned DGMs. The EMP and other submissions made by the PP were found to be satisfactory and acceptable, hence committee decided to recommend the case for grant of prior EC subject to the following special conditions in addition to the standard conditions at annexure ‘B’:

PP/Consultant made a presentation on all aspects of the project and all concerned issues were discussed in detail. After detailed discussions and perusal of recommendations of 464th SEAC meeting dated 03.10.2020, presentation made by the PP in SEIAA, it was decided to accept the recommendation of SEAC for grant of prior EC to the project subject to the following specific conditions:-

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 100 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020

I. PP shall not start mining activity before execution of lease agreement.

II. The production capacity shall be limited to the quantity as recommended by SEAC.

III. No ramp will be allowed within the river basin to transport sand to the other bank. Transportation will be allowed on the bank side where the mineral is being excavated.

IV. The entire lease area should be properly fenced and boundary stones marked at the site.

V. No in-stream mining shall be allowed. The local authorities should ensure that the mining activity is confined only in the dry portion where sand is exposed.

VI. The depth of the pit shall be as per Approved Mining Plan.

VII. No transportation shall be permitted within the village.

VIII. Alternate transportation route should be decided in consultation with the local Gram Panchayat.

IX. Total 2400 saplings of suitable tree species i.e. Neem, Pipal, Bargad, Mango, Gulmohar, Sissoo, Kathal, Guava, Imli, etc. shall be planted by PP in first three years under plantation programme at river bank and approach in consultation with Gram Panchayat/ DM. PP shall also explore and identify the chunk of land in the area from revenue record to carry out plantation programme as proposed.

X. Over loading will be strictly prohibited.

XI. Water sprinkling will be done on the approach road on the regular basis.

XVII. PP must ensure the implementation of following activities with separate budget provision of total Rs. 75,000/- under CER as committed:

a) 1st, 2nd & 3rd Year: Construction of Boundary Wall (Length 25m) in Primary School of the

Village.

PP shall ensure to contruct toilet with proper plumbing in the school of above village and contribute on behalf of village in Jal Jeewan Mission in consultation with Janpad Panchayat and PHED. PP shall give preference to develop/provide infrastructural facilities in schools or aanganwadies of above villages. The modification to the above activities can be made with the permission of the district administration and need based activity for the development of nearby villages shall be implemented by PP in consultation with the District Collector and Gram Panchayat.

XII. PP should ensure to submit half yearly compliance report, Plantation and CER activity report along with photographs of all activities in MP-SEIAA. If PP is failed to upload or submit two consecutive half yearly compliance reports of EC conditions to concerned authority (SEIAA and Regional Office, MoEF&CC,GoI,Bhopal) than prior environmental clearance issued to PP will

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 101 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020

automatically be treated as cancelled/ revoked as per OM No. 930/SEIAA/2019 dated 30.05.2019 issued by MPSEIAA.

Hence, Prior Environmental Clearance is granted for Sand Quarry in an area of 2.0 ha. (5000 cum per annum) (Khasra No. 114), Village - Rampur, Tehsil - Junnardeo, Dist. - Chindwara (MP) for the lease period to Shri Shishir Khandar, Samashish Bhavan, 18, Malik Complex, Tenament Hotel, Airport Center Plient, Somalwada, Wardha Road, Dist. - Nagpur, Mah. 440028, Email – [email protected], Mobile – 9407055948.

39. Case No. 7843/20 Prior Environmental Clearance for Sand Quarry in an area of 3.50 ha. (35000 cum per annum) (Khasra No. 92), Village - Mehndi, Tehsil - Sausar, Dist. - Chindwara (MP) by Shri Shishir Khandar, Samashish Bhavan, 18, Malik Complex, Tenament Hotel, Airport Center Plient, Somalwada, Wardha Road, Dist. - Nagpur, Mah. 440028, Email – [email protected], Mobile – 9407055948.

This case was recommended in 464th SEAC meeting dated 03.10.2020 and it was recorded that..........

“------------PP has submitted the response of above quarries same date vide letter dated 03.10.2020, which was placed before the committee and the same found satisfactory. Committee observed that even after deducting the volume of sand in the submerged area, the sanctioned volume of sand can be evacuated from the available dry area as per the revised plan submitted by PP. The mining shall be done as per the approved mine plan by concerned DGMs. The EMP and other submissions made by the PP were found to be satisfactory and acceptable, hence committee decided to recommend the case for grant of prior EC subject to the following special conditions in addition to the standard conditions at annexure ‘B’:

PP/Consultant made a presentation on all aspects of the project and all concerned issues were discussed in detail. After detailed discussions and perusal of recommendations of 464th SEAC meeting dated 03.10.2020, presentation made by the PP in SEIAA, it was decided to accept the recommendation of SEAC for grant of prior EC to the project subject to the following specific conditions:-

I. PP shall not start mining activity before execution of lease agreement.

II. The production capacity shall be limited to the quantity as recommended by SEAC.

III. No ramp will be allowed within the river basin to transport sand to the other bank. Transportation will be allowed on the bank side where the mineral is being excavated.

IV. The entire lease area should be properly fenced and boundary stones marked at the site.

V. No in-stream mining shall be allowed. The local authorities should ensure that the mining activity is confined only in the dry portion where sand is exposed.

VI. The depth of the pit shall be as per Approved Mining Plan.

VII. No transportation shall be permitted within the village.

VIII. Alternate transportation route should be decided in consultation with the local Gram Panchayat.

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 102 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020

IX. Total 4200 saplings of suitable tree species i.e. Neem, Pipal, Bargad, Mango, Gulmohar, Sissoo, Kathal, Guava, Imli, etc. shall be planted by PP in first three years under plantation programme at river bank and approach road in consultation with Gram Panchayat/ DM. PP shall also explore and identify the chunk of land in the area from revenue record to carry out plantation programme as proposed.

X. Over loading will be strictly prohibited.

XI. Water sprinkling will be done on the approach road on the regular basis.

XVIII. PP must ensure the implementation of following activities with separate budget provision of total Rs. 2,70,000/- under CER as committed:

a) 1st, 2nd & 3rd Year: Overhead Water tank with water filter will be provided at Mehndi Primary

School. – Rs.10,000/- To provide Swings & Slides at Village School – Rs.20,000/- Construction of One Room at Village Primary School (Size 15*15) –

2,40,000/-

PP shall ensure to contruct toilet with proper plumbing in the school of above village and contribute on behalf of village in Jal Jeewan Mission in consultation with Janpad Panchayat and PHED. PP shall give preference to develop/provide infrastructural facilities in schools or aanganwadies of above villages. The modification to the above activities can be made with the permission of the district administration and need based activity for the development of nearby villages shall be implemented by PP in consultation with the District Collector and Gram Panchayat.

XII. PP should ensure to submit half yearly compliance report, Plantation and CER activity report along with photographs of all activities in MP-SEIAA. If PP is failed to upload or submit two consecutive half yearly compliance reports of EC conditions to concerned authority (SEIAA and Regional Office, MoEF&CC,GoI,Bhopal) than prior environmental clearance issued to PP will automatically be treated as cancelled/ revoked as per OM No. 930/SEIAA/2019 dated 30.05.2019 issued by MPSEIAA.

Hence, Prior Environmental Clearance is granted for Sand Quarry in an area of 3.50 ha. (35000 cum per annum) (Khasra No. 92), Village - Mehndi, Tehsil - Sausar, Dist. - Chindwara (MP) for the lease period to Shri Shishir Khandar, Samashish Bhavan, 18, Malik Complex, Tenament Hotel, Airport Center Plient, Somalwada, Wardha Road, Dist. - Nagpur, Mah. 440028, Email – [email protected], Mobile – 9407055948.

40. Case No. 7860/20 Prior Environmental Clearance for Sand Quarry in an area of 0.809 ha. (8016 cum per annum) (Khasra No. 01), Village - Kukda Kirar, Tehsil - Mohkhed, Dist. - Chindwara (MP) by Shri Shishir Khandar, Samashish Bhavan, 18, Malik Complex, Tenament Hotel, Airport Center Plient, Somalwada, Wardha Road, Dist. - Nagpur, Mah. 440028, Email – [email protected], Mobile – 9407055948.

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 103 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020

This case was recommended in 464th SEAC meeting dated 03.10.2020 and it was recorded that..........

“------------PP has submitted the response of above quarries same date vide letter dated 03.10.2020, which was placed before the committee and the same found satisfactory. The mining shall be done as per the approved mine plan by concerned DGMs. The EMP and other submissions made by the PP were found to be satisfactory and acceptable, hence committee decided to recommend the case for grant of prior EC subject to the following special conditions in addition to the standard conditions at annexure ‘B’:

PP/Consultant made a presentation on all aspects of the project and all concerned issues were discussed in detail. After detailed discussions and perusal of recommendations of 464th SEAC meeting dated 03.10.2020, presentation made by the PP in SEIAA, it was observed from google earth that mining leaseof 0.809 ha is sanctioned in two parts having distance more than 200 m which is not as per mining rules hence it is decided to seek clarification from DGM about sanctioning mining lease in 2 parts having more than 200 m distance between two parts of mining lease.

41. Case No. 7836/20 Prior Environmental Clearance for Sand Quarry in an area of 4.0 ha. (40000 cum per annum) (Khasra No. 1), Village - Dhartikachhar, Tehsil - Shahpura, Dist. - Jabalpur (MP) by M/s Aaradhya Logistics Solution Pvt. Ltd., Shri Brajesh Sohaney, Director, 1967, Right Town, Jabalpur, Dist. - Jabalpur, MP - 482001, Email – [email protected], Mobile – 8770513644.

This case was recommended in 464th SEAC meeting dated 03.10.2020 and it was recorded that..........

“------------PP has submitted the response of above quarries same date vide letter dated 03.10.2020, which was placed before the committee and the same found satisfactory. Committee observed that even after deducting the volume of sand in the submerged area, the sanctioned volume of sand can be evacuated from the available dry area as per the revised plan submitted by PP. The mining shall be done as per the approved mine plan by concerned DGMs. The EMP and other submissions made by the PP were found to be satisfactory and acceptable, hence committee decided to recommend the case for grant of prior EC subject to the following special conditions in addition to the standard conditions at annexure ‘B’:

PP/Consultant made a presentation on all aspects of the project and all concerned issues were discussed in detail. After detailed discussions and perusal of recommendations of 464th SEAC meeting dated 03.10.2020, presentation made by the PP in SEIAA, it was decided to accept the recommendation of SEAC for grant of prior EC to the project subject to the following specific conditions:-

I. PP shall not start mining activity before execution of lease agreement.

II. The production capacity shall be limited to the quantity as recommended by SEAC.

III. No ramp will be allowed within the river basin to transport sand to the other bank. Transportation will be allowed on the bank side where the mineral is being excavated.

IV. The entire lease area should be properly fenced and boundary stones marked at the site.

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 104 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020

V. No in-stream mining shall be allowed. The local authorities should ensure that the mining activity is confined only in the dry portion where sand is exposed.

VI. The depth of the pit shall be as per Approved Mining Plan.

VII. No transportation shall be permitted within the village.

VIII. Alternate transportation route should be decided in consultation with the local Gram Panchayat.

IX. Total 3900 saplings of suitable tree species i.e. Neem, Pipal, Bargad, Mango, Gulmohar, Sissoo, Jamun Guava, etc. shall be planted by PP in first three years under plantation programme at river bank and approach road and at Dhartikachhar, Villages area (School, Aanganwadi, Gram Panchayat Bhawan) as per recomonded by Gram panchayat.

X. PP shall also explore and identify the chunk of land in the area from revenue record to carry out plantation programme as proposed.

XI. Over loading will be strictly prohibited.

XII. Water sprinkling will be done on the approach road on the regular basis.

XIII. PP must ensure the implementation of following activities with separate budget provision of total Rs. 4.30 lakh under CER as committed:

a) COVID related activity

b) Grazing land development

c) To provide water purifier in Govt. school Dhartikachhar & Aanganwadi.

d) Water harvesting in Gram Panchayat Bhawan and Govt. school of Dhartikachhar.

PP shall ensure to contruct toilet with proper plumbing in the school of above village and contribute on behalf of village in Jal Jeewan Mission in consultation with Janpad Panchayat and PHED. PP shall give preference to develop/provide infrastructural facilities in schools or aanganwadies of above villages. The modification to the above activities can be made with the permission of the district administration and need based activity for the development of nearby villages shall be implemented by PP in consultation with the District Collector and Gram Panchayat.

XIV. PP should ensure to submit half yearly compliance report, Plantation and CER activity report along with photographs of all activities in MP-SEIAA. If PP is failed to upload or submit two consecutive half yearly compliance reports of EC conditions to concerned authority (SEIAA and Regional Office, MoEF&CC,GoI,Bhopal) than prior environmental clearance issued to PP will automatically be treated as cancelled/ revoked as per OM No. 930/SEIAA/2019 dated 30.05.2019 issued by MPSEIAA.

Hence, Prior Environmental Clearance is granted for Sand Quarry in an area of 4.0 ha. (40000 cum per annum) (Khasra No. 1), Village - Dhartikachhar, Tehsil -

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 105 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020

Shahpura, Dist. - Jabalpur (MP) for the lease period to M/s Aaradhya Logistics Solution Pvt. Ltd., Shri Brajesh Sohaney, Director, 1967, Right Town, Jabalpur, Dist. - Jabalpur, MP - 482001, Email – [email protected], Mobile – 8770513644.

42. Case No. 7837/20 Prior Environmental Clearance for Sand Quarry in an area of 1.0 ha. (18100 cum per annum) (Khasra No. 91/274), Village - Mandala, Tehsil - Majholi, Dist. Jabalpur (MP) by M/s Aaradhya Logistics Solution Pvt. Ltd., Shri Brajesh Sohaney, Director, 1967, Right Town, Jabalpur, Dist. - Jabalpur, MP - 482001, Email – [email protected], Mobile – 8770513644.

This case was recommended in 464th SEAC meeting dated 03.10.2020 and it was recorded that..........

“------------The case was presented by the PP and their consultant. PP stated that this is a case of river sand mining on Narmada River and thus only manual mining is proposed. During presentation as per Google image based on coordinates provided by PP, it was observed that the part of lease is under submergence, for which PP submitted that they will leave submerged area as non-mining zone. The mining shall be done as per the approved mine plan by concerned DGMs. The EMP and other submissions made by the PP were found to be satisfactory and acceptable, hence committee decided to recommend the case for grant of prior EC subject to the following special conditions in addition to the standard conditions at annexure ‘B’:

PP/Consultant made a presentation on all aspects of the project and all concerned issues were discussed in detail. After detailed discussions and perusal of recommendations of 464th SEAC meeting dated 03.10.2020, presentation made by the PP in SEIAA, it was decided to accept the recommendation of SEAC for grant of prior EC to the project subject to the following specific conditions:-

I. PP shall not start mining activity before execution of lease agreement.

II. The production capacity shall be limited to the quantity as recommended by SEAC.

III. No ramp will be allowed within the river basin to transport sand to the other bank. Transportation will be allowed on the bank side where the mineral is being excavated.

IV. The entire lease area should be properly fenced and boundary stones marked at the site.

V. No in-stream mining shall be allowed. The local authorities should ensure that the mining activity is confined only in the dry portion where sand is exposed.

VI. The depth of the pit shall be as per Approved Mining Plan.

VII. No transportation shall be permitted within the village.

VIII. Alternate transportation route should be decided in consultation with the local Gram Panchayat.

IX. Total 900 saplings of suitable tree species i.e. Neem, Pipal, Bargad, Mango, Gulmohar, Sissoo, Jamun Guava, etc. shall be planted by PP in first three years under plantation programme at river bank and approach road and at Mandala, Villages area (School, Aanganwadi Gram Panchayat Bhawan,) as per recomonded by Gram Panchayat.

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 106 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020

X. Over loading will be strictly prohibited.

XI. Water sprinkling will be done on the approach road on the regular basis.

XII. PP must ensure the implementation of following activities with separate budget provision of total Rs. 1.50 lakh under CER as committed:

a) COVID related activity.

b) Grazing land development.

c) Repairing and maintenance of kachha road in Mandala village and repairing and maintenance of community hall.

PP shall ensure to contruct toilet with proper plumbing in the school of above village and contribute on behalf of village in Jal Jeewan Mission in consultation with Janpad Panchayat and PHED. PP shall give preference to develop/provide infrastructural facilities in schools or aanganwadies of above villages. The modification to the above activities can be made with the permission of the district administration and need based activity for the development of nearby villages shall be implemented by PP in consultation with the District Collector and Gram Panchayat.

XIII. PP should ensure to submit half yearly compliance report, Plantation and CER activity report along with photographs of all activities in MP-SEIAA. If PP is failed to upload or submit two consecutive half yearly compliance reports of EC conditions to concerned authority (SEIAA and Regional Office, MoEF&CC,GoI,Bhopal) than prior environmental clearance issued to PP will automatically be treated as cancelled/ revoked as per OM No. 930/SEIAA/2019 dated 30.05.2019 issued by MPSEIAA.

Hence, Prior Environmental Clearance is granted for Sand Quarry in an area of 1.0 ha. (18100 cum per annum) (Khasra No. 91/274), Village - Mandala, Tehsil - Majholi, Dist. Jabalpur (MP) for the lease period to M/s Aaradhya Logistics Solution Pvt. Ltd., Shri Brajesh Sohaney, Director, 1967, Right Town, Jabalpur, Dist. - Jabalpur, MP - 482001, Email – [email protected], Mobile – 8770513644.

43. Case No. 7838/20 Prior Environmental Clearance for Sand Quarry in an area of 4.0 ha. (10000 cum per annum) (Khasra No. 121), Village - Kalyanpur, Tehsil - Kundam, Dist. - Jabalpur (MP) by M/s Aaradhya Logistics Solution Pvt. Ltd., Shri Brajesh Sohaney, Director, 1967, Right Town, Jabalpur, Dist. - Jabalpur, MP - 482001, Email – [email protected], Mobile – 8770513644.

This case was recommended in 464th SEAC meeting dated 03.10.2020 and it was recorded that..........

“------------PP has submitted the response of above quarries same date vide letter dated 03.10.2020, which was placed before the committee and the same found satisfactory.

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 107 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020

Committee observed that even after deducting the volume of sand in the submerged area, the sanctioned volume of sand can be evacuated from the available dry area as per the revised plan submitted by PP. The mining shall be done as per the approved mine plan by concerned DGMs. The EMP and other submissions made by the PP were found to be satisfactory and acceptable, hence committee decided to recommend the case for grant of prior EC subject to the following special conditions in addition to the standard conditions at annexure ‘B’:

PP/Consultant made a presentation on all aspects of the project and all concerned issues were discussed in detail. After detailed discussions and perusal of recommendations of 464th SEAC meeting dated 03.10.2020, presentation made by the PP in SEIAA, it was decided to accept the recommendation of SEAC for grant of prior EC to the project subject to the following specific conditions:-

I. PP shall not start mining activity before execution of lease agreement.

II. The production capacity shall be limited to the quantity as recommended by SEAC.

III. No ramp will be allowed within the river basin to transport sand to the other bank. Transportation will be allowed on the bank side where the mineral is being excavated.

IV. The entire lease area should be properly fenced and boundary stones marked at the site.

V. No in-stream mining shall be allowed. The local authorities should ensure that the mining activity is confined only in the dry portion where sand is exposed.

VI. The depth of the pit shall be as per Approved Mining Plan.

VII. No transportation shall be permitted within the village.

VIII. Alternate transportation route should be decided in consultation with the local Gram Panchayat.

IX. Total 3000 saplings of suitable tree species i.e. Neem, Pipal, Bargad, Mango, Gulmohar, Sissoo, Jamun Guava, etc. shall be planted by PP in first three years under plantation programme at river bank and approach road and at Kalyanpur Villages area (School, Aanganwadi Gram Panchayat Bhawan) as per recomonded by Gram panchayat.

X. Over loading will be strictly prohibited.

XI. Water sprinkling will be done on the approach road on the regular basis.

XIV. PP must ensure the implementation of following activities with separate budget provision of total Rs. 1.15 lakh under CER as committed:

a) COVID related activity

b) Grazing land development

c) To provide furniture and fans in Govt. School Kalyanpur and Boundary wall fencing in school, Aanganwadi in consultation with Gram Panchayat.

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 108 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020

PP shall ensure to contruct toilet with proper plumbing in the school of above village and contribute on behalf of village in Jal Jeewan Mission in consultation with Janpad Panchayat and PHED. PP shall give preference to develop/provide infrastructural facilities in schools or aanganwadies of above villages. The modification to the above activities can be made with the permission of the district administration and need based activity for the development of nearby villages shall be implemented by PP in consultation with the District Collector and Gram Panchayat.

XII. PP should ensure to submit half yearly compliance report, Plantation and CER activity report along with photographs of all activities in MP-SEIAA. If PP is failed to upload or submit two consecutive half yearly compliance reports of EC conditions to concerned authority (SEIAA and Regional Office, MoEF&CC,GoI,Bhopal) than prior environmental clearance issued to PP will automatically be treated as cancelled/ revoked as per OM No. 930/SEIAA/2019 dated 30.05.2019 issued by MPSEIAA.

Hence, Prior Environmental Clearance is granted for Sand Quarry in an area of 4.0 ha. (10000 cum per annum) (Khasra No. 121), Village - Kalyanpur, Tehsil - Kundam, Dist. - Jabalpur (MP) for the lease period to M/s Aaradhya Logistics Solution Pvt. Ltd., Shri Brajesh Sohaney, Director, 1967, Right Town, Jabalpur, Dist. - Jabalpur, MP - 482001, Email – [email protected], Mobile – 8770513644.

44. Case No. 7857/2020; Prior Environmental Clearance for Sand Quarry in an area of 5.0 ha for production capacity of 2000 cum per annum at Khasra No. 26 at Village - Ghogalpur, Tehsil - Berasia, Dist. Bhopal (MP) by M/S Rao construction Shri Rao Hemraj Singh, 37/123, Village Kanjai, Post- Kanjai, Tehsil- Gotegaon, Dist.- Narsinghpur, MP – 487118.

This case was recommended in 464th SEAC dated 3/10/2020 it was recorded that..........

"------------ PP has submitted the response of above quarries same date vide letter dated 30.09.2020, which was placed before the committee and the same found satisfactory. Committee observed that even after deducting the volume of sand in the submerged area, the sanctioned volume of sand can be evacuated from the available dry area as per the revised plan submitted by PP. The mining shall be done as per the approved mine plan by concerned DGMs. The EMP and other submissions made by the PP were found to be satisfactory and acceptable, hence committee decided to recommend the case for grant of prior EC subject to the following special conditions in addition to the standard conditions at annexure ‘B’:

PP/Consultant made a presentation on all concerned issues were discussed in detail. After detailed discussions and perusal of recommendations of 464th SEAC meeting dated 3/10/2020 presentation made by the PP in SEIAA, it was decided to accept the recommendation of SEAC for grant of prior EC to the project subject to the following specific conditions:-

i. PP shall not start mining activity before execution of lease agreement.

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 109 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020

ii. The production capacity shall be limited to the quantity as recommended by SEAC.

iii. No ramp will be allowed within the river basin to transport sand to the other bank. Transportation will be allowed on the bank side where the mineral is being excavated.

iv. The entire lease area should be properly fenced and boundary stones marked at the site.

v. No in-stream mining shall be allowed. The local authorities should ensure that the mining activity is confined only in the dry portion where sand is exposed.

vi. The depth of the pit shall be as per Approved Mining Plan.

vii. No transportation shall be permitted within the village.

viii. Alternate transportation route should be decided in consultation with the local Gram Panchayat.

ix. Total 6000 saplings of suitable tree species i.e. Neem, Pipal,Bargad, Gulmohar Amla etc. shall be planted in nearby Khasra No. ------of MP by PP under plantation programme in consultation with DM at identified revenue land of the district. PP shall also explore and identify the chunk of land in the area from revenue record to carry out plantation programme as proposed.

x. Over loading will be strictly prohibited.

xi. Water sprinkling will be done on the approach road on the regular basis.

xii. PP must ensure the implementation of following activities with separate budget provision of total Rs. 0.55 Lakh under CER:

a) 1st Year: Provide to cOVID related activity

b) 2nd Year :Provide to grazing land development

c) 3rd Year Provide infrastructure facilities in school, Distribution of Books, Sports kits, and Boundary wall fencing in school, Anganbadi or Gram Panchayat Bhavan for the development of village in consultation with Gram Panchayat

PP shall ensure to contruct toilet with proper plumbing in the school of above village and contribute on behalf of village in Jal Jeewan Mission in consultation with Janpad Panchayat and PHED.PP shall give preference to develop/provide infrastructural facilities in schools or aganwadies of above villages. The modification to the above activities can be made with the permission of the district administration and need based activity for the development of nearby

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 110 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020

villages shall be implemented by PP in consultation with the District Collector and Gram Panchayat.

xiii. PP should ensure to submit half yearly compliance report, Plantation and CER activity report along with photographs of all activities in MP-SEIAA. If PP is failed to upload or submit two consecutive half yearly compliance reports of EC conditions to concerned authority (SEIAA and Regional Office, MoEF&CC,GoI,Bhopal) than prior environmental clearance issued to PP will automatically be treated as cancelled/ revoked as per OM No. 930/SEIAA/2019 dated 30.05.2019 issued by MPSEIAA.

Hence, Prior Environmental Clearance is granted for Sand Quarry in an area of 5.0 ha for production capacity of 2000 cum per annum at Khasra No. 26 at Village - Ghogalpur, Tehsil - Berasia, Dist. Bhopal (MP) for the lease period to M/S Rao construction Shri Rao Hemraj Singh, 37/123, Village Kanjai, Post- Kanjai, Tehsil- Gotegaon, Dist.- Narsinghpur, MP – 487118.

45. Case No. 7781/2020; Prior Environmental Clearance for Stone Quarry (Opencast Manual/Semi Mechanized Method) in an area of 1.0 ha. for production capacity of 7136.40 cum per annum at Khasra No. 311/1/4 at Village - Samnapurkalan, Tehsil - Goharganj, Dist. Raisen, (MP) by Shri Arif Kha S/o Shri Shameem Kha, Gram - Thikari, Tehsil - Goharganj, Dist. Raisen, MP.

This case was recommended in 464th SEAC dated 3/10/2020 it was recorded that..........

"------------ The case was presented by the PP and their consultant. PP stated that this is a case of stone mining. The EMP and other submissions made by the PP were found to be satisfactory and acceptable, hence committee decided to recommend the case for grant of prior EC subject to the following special conditions in addition to the standard conditions at annexure ‘A’:

PP/Consultant made a presentation on all concerned issues were discussed in detail. After detailed discussions and perusal of recommendations of 464th SEAC meeting dated 3.10.2020, presentation made by the PP in SEIAA, it was decided to accept the recommendation of SEAC for grant of prior EC to the project subject to the following specific conditions:-

I. Before commencing any mining activity fencing shall be carried out all around the lease area. Proper watch and ward arrangements should be made with installation of signage at 4 corners of lease area to avoid any untoward incident involving public and animals by the PP.

II. PP shall not start mining activity before execution of lease agreement.

III. The depth of the pit shall be as per the Approved Mining Plan.

IV. The entire area shall be fenced and three rows of plantation should be done on the periphery of the boundary.

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 111 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020

V. PP shall ensure the proper water supply arrangements for dust suppression, regular sprinkling, plantation and drinking purposes especially in summer season.

VI. Total 1200 saplings of suitable tree species i.e. Neem, Pipal,Bargad,Gulmohar Amla etc. shall be planted in nearby Khasra No. 304/2/5/1 of Village – Samnapurkalan, Tehsil - Goharganj, Dist. Raisen,,by PP in first year under plantation programme in consultation with DM at identified revenue land of the district. PP shall also explore and identify the chunk of land in the area from revenue record to carry out plantation programme as proposed.

VII. PP shall ensure proper implementation of plantation, dust suppression, construction of approach road and maintenance of existing pakka road as part of Environmental Management Plan. Additional budget provision shall be made as part of EMP.

VIII. PP must ensure implementation of the following activities with separate budget provision of total Rs 3.0 Lakh under CER:

Village Name: Samnapurkalan Provide to distribution of mask , sanitizer ( 1st year) . Provide to preparation of grazing land. ( 1st year) . Provide to Construction of Boundary wall in Govt primary school

Samnapurkalan Provide to contribution for Jal Jeewan Mission to janpad panchayat

Samnapurkalan

PP shall ensure to contruct toilet with proper plumbing in the school of above village and contribute on behalf of village in Jal Jeewan Mission in consultation with Janpad Panchayat and PHED.PP shall give preference to develop/provide infrastructural facilities in schools or aanganwadies of above villages. The modification to the above activities can be made with the permission of the district administration and need based activity for the development of nearby villages shall be implemented by PP in consultation with the District Collector and Gram Panchayat.

IX. PP should ensure to submit half yearly compliance report, Plantation and CER activity report along with photographs of all activities in MP-SEIAA. If PP is failed to upload or submit two consecutive half yearly compliance reports of EC conditions to concerned authority (SEIAA and Regional Office, MoEF&CC,GoI,Bhopal) than prior environmental clearance issued to PP will automatically be treated as cancelled/ revoked as per OM No. 930/SEIAA/2019 dated 30.05.2019 issued by MPSEIAA.

Hence, Prior Environmental Clearance is granted for Stone Quarry (Opencast Manual/Semi Mechanized Method) in an area of 1.0 ha. for production

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 112 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020

capacity of 7136.40 cum per annum at Khasra No. 311/1/4 at Village - Samnapurkalan, Tehsil - Goharganj, Dist. Raisen, (MP) for the lease period to Shri Arif Kha S/o Shri Shameem Kha, Gram - Thikari, Tehsil - Goharganj, Dist. Raisen, MP.

46. Case No. 7848/20 Prior Environmental Clearance for Stone Quarry (opencast manual/semi mechanized method) in an area of 1.40 ha. (12348 cum per annum) (Khasra No. 1012), Village - Khaira, Tehsil - Rampur Naikin, Dist. - Sidhi (MP) by Shri Bhanu Prakash Pandey, Village - Hanumangarh, Tehsil - Rampur Naikin, Dist. - Sidhi, MP - 486661, Email - [email protected], Mobile – 8109326215.

This case was recommended in 464th SEAC meeting dated 03.10.2020 and it was recorded that..........

“------------The case was presented by the PP and their consultant. PP stated that this is a case of stone mining. The EMP and other submissions made by the PP were found to be satisfactory and acceptable, hence committee decided to recommend the case for grant of prior EC subject to the following special conditions in addition to the standard conditions at annexure ‘A’:

PP/Consultant made a presentation on all aspects of the project and all concerned issues were discussed in detail. After detailed discussions and perusal of recommendations of 464th SEAC meeting dated 03.10.2020, presentation made by the PP in SEIAA, it was decided to accept the recommendation of SEAC for grant of prior EC to the project subject to the following specific conditions:-

i. Before commencing any mining activity fencing shall be carried out all around the lease area. Proper watch and ward arrangements should be made with installation of signage at 4 corners of lease area to avoid any untoward incident involving public and animals by the PP.

ii. PP shall not start mining activity before execution of lease agreement.

iii. The depth of the pit shall be as per the Approved Mining Plan.

iv. The entire area shall be fenced and three rows of plantation should be done on the periphery of the boundary.

v. PP shall ensure the proper water supply arrangements for dust suppression, regular sprinkling, plantation and drinking purposes especially in summer season.

vi. Total 1700 saplings of suitable tree species i.e. Neem, Pipal, Bargad, Mango, Gulmohar, Sissoo, Amla, Imli, etc. shall be planted by PP in first three years under plantation programme at mine lease boundary and at Govt. land khasra no. 89 Village - Khaira, tehsil - Rampur Naikin in consultation with Gram Panchayat/ DM. PP shall also explore and identify the chunk of land in the area from revenue record to carry out plantation programme as proposed.

vii. PP shall ensure proper implementation of plantation, dust suppression, construction of approach road and maintenance of existing pakka road as part of Environmental Management Plan. Additional budget provision shall be made as part of EMP.

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 113 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020

viii. PP must ensure implementation of the following activities with separate budget provision of total Rs. 3.50 lakh under CER as committed:

a) Village – Khaira: Covid-19 awareness campaign and distribution of mask, sanitizer

(1st year). Preparation of grazing land (1st year). Construction of 2 rooms with White wash Leveling of ground in Khaira village Aanganwadi. Contribution for Jal Jeewan Mission to janpad panchayat Khaira.

PP shall ensure to contruct toilet with proper plumbing in the school of above village and contribute on behalf of village in Jal Jeewan Mission in consultation with Janpad Panchayat and PHED. PP shall give preference to develop/provide infrastructural facilities in schools or aanganwadies of above villages. The modification to the above activities can be made with the permission of the district administration and need based activity for the development of nearby villages shall be implemented by PP in consultation with the District Collector and Gram Panchayat.

ix. PP should ensure to submit half yearly compliance report, Plantation and CER activity report along with photographs of all activities in MP-SEIAA. If PP is failed to upload or submit two consecutive half yearly compliance reports of EC conditions to concerned authority (SEIAA and Regional Office, MoEF&CC,GoI,Bhopal) than prior environmental clearance issued to PP will automatically be treated as cancelled/ revoked as per OM No. 930/SEIAA/2019 dated 30.05.2019 issued by MPSEIAA.

Hence, Prior Environmental Clearance is granted for Stone Quarry (opencast manual/semi mechanized method) in an area of 1.40 ha. (12348 cum per annum) (Khasra No. 1012), Village - Khaira, Tehsil - Rampur Naikin, Dist. - Sidhi (MP) for the lease period to Shri Bhanu Prakash Pandey, Village - Hanumangarh, Tehsil - Rampur Naikin, Dist. - Sidhi, MP - 486661, Email - [email protected], Mobile – 8109326215.

47. Case No 7824/2020 Prior Environmental Clearance for Stone Quarry (Opencast Manual / Semi Mechanized Method) in an area of 2.50 ha. for production capacity of 118560 cum / year at Khasra No. 553 at Village - Luhari, Tehsil - Jaora, Dist. Ratlam (MP) by M/s G.R.Infra Projects Ltd, Tehsil - Jaora, Dist. Ratlam, MP - 457001

This case was recommended in 464th SEAC meeting dated 03.10.2020 and it was recorded that..........

“…………The case was presented by the PP and their consultant. PP stated that this is a case of stone mining. The EMP and other submissions made by the PP were found to be satisfactory and acceptable, hence committee decided to recommend the case for grant of prior EC subject to the following special conditions in addition to the standard conditions at annexure ‘A’:”

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 114 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020

PP/Consultant made a presentation on all aspects of the project and all concerned issues were discussed in detail. After detailed discussions and perusal of recommendations of 464th SEAC meeting dated 03.10.2020, presentation made by the PP in SEIAA, it was decided to accept the recommendation of SEAC for grant of prior EC to the project subject to the following specific conditions:-

I. Before commencing any mining activity fencing shall be carried out all around the lease area. Proper watch and ward arrangements should be made with installation of signage at 4 corners of lease area to avoid any untoward incident involving public and animals by the PP.

II. PP shall not start mining activity before execution of lease agreement. III. The depth of the pit shall be as per the Approved Mining Plan. IV. The entire area shall be fenced and three rows of plantation should be done

on the periphery of the boundary. V. PP shall ensure that the proper water supply arrangements for dust

suppression, regular sprinkling, plantation and drinking purposes especially in summer season.

VI. PP shall ensure to construct and maintained the approach road. Plantation will be carried out on both side of approach road.

VII. PP shall ensure proper implementation of plantation, dust suppression, construction of approach road and maintenance of existing road & as part of Environmental Management Plan. Additional budget provision shall be made as part of EMP.

VIII. Total 3000 saplings of suitable tree species i.e. Neem, Pipal, Bargad, Mango, Amla, Amaltas, Drumstick etc. shall be planted by PP at mine lease boundary (1000 saplings) and 2000 saplings at khasra no 490 ( Govt land) under plantation programme. PP shall also explore and identify the chunk of land in the area from revenue record to carry out plantation programme as proposed.

IX. PP must ensure implementation of the following activities with separate budget provision of Rs 3.0 lakh under CER.

CER activities at village Luhari

Distribution of mask , sanitizer (1st year ) (Rs. 5000) . Preparation of grazing land. (1st year ) (Rs. 5000) .. Construction of 250 m CC Road In Luhari village (Rs. 2,20,000) .. Contribution for Jal Jeewan Mission to janpad panchayat Luhari (Rs.

70000).

PP shall ensure to contruct toilet with proper plumbing in the school of above village and contribute on behalf of village in Jal Jeewan Mission in consultation with Janpad Panchayat and PHED. PP shall give preference to develop/provide infrastructural facilities in schools or aganwadies of above villages The modification to the above activities can be made with the permission of the district administration and need based activity for the development of nearby

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 115 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020

villages shall be implemented by PP in consultation with the District Collector and Gram Panchayat

X. PP should ensure to submit half yearly compliance report and CSR activity report with photographs of plantation in MP-SEIAA. If PP is failed to upload or submit two consecutive half yearly compliance reports of EC conditions to concerned authority (SEIAA and Regional Office, MoEF&CC,GoI,Bhopal) than prior environmental clearance issued to PP will automatically be treated as cancelled/ revoked as per OM No. 930/SEIAA/2019 dated 30.05.2019 issued by MPSEIAA.

Hence, Prior Environmental Clearance is granted for Stone Quarry (Opencast Manual / Semi Mechanized Method) in an area of 2.50 ha. for production capacity of 118560 cum / year at Khasra No. 553 at Village - Luhari, Tehsil - Jaora, Dist. Ratlam (MP) for the lease period to M/s G.R.Infra Projects Ltd, Tehsil - Jaora, Dist. Ratlam, MP - 457001

48. Case No. 7827/2020; Prior Environmental Clearance for Stone Quarry (Opencast Manual/Semi Mechanized Method) in an area of 4.0 ha. for production capacity of 48051 cum per annum at Khasra No. 42, 43, 236 at Village - Panihara-Pachara, Tehsil - Khaniadhana, Dist. Shivpuri (MP) by M/s Osho Associate, 30, Satydev Nagar, Gandhi Road, Dist. Gwalior, MP – 473551.

This case was recommended in 464th SEAC dated 3/10/2020 it was recorded that..........

"------------ The case was presented by the PP and their consultant. PP stated that this is a case of stone mining. The EMP and other submissions made by the PP were found to be satisfactory and acceptable, hence committee decided to recommend the case for grant of prior EC subject to the following special conditions in addition to the standard conditions at annexure ‘A’:

PP/Consultant made a presentation on all concerned issues were discussed in detail. After detailed discussions and perusal of recommendations of 464th SEAC meeting dated 3.10.2020, presentation made by the PP in SEIAA, it was decided to accept the recommendation of SEAC for grant of prior EC to the project subject to the following specific conditions:-

I. Before commencing any mining activity fencing shall be carried out all around the lease area. Proper watch and ward arrangements should be made with installation of signage at 4 corners of lease area to avoid any untoward incident involving public and animals by the PP.

II. PP shall not start mining activity before execution of lease agreement.

III. The depth of the pit shall be as per the Approved Mining Plan.

IV. The entire area shall be fenced and three rows of plantation should be done on the periphery of the boundary.

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 116 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020

V. PP shall ensure the proper water supply arrangements for dust suppression, regular sprinkling, plantation and drinking purposes especially in summer season.

VI. Total 4800 saplings of suitable tree species i.e. Neem, Pipal,Bargad,Gulmohar Amla etc. shall be planted in nearby Khasra No. 490 of Village – Panihara-Pachara, Tehsil - Khaniadhana, Dist. Shivpuri (,by PP in first year under plantation programme in consultation with DM at identified revenue land of the district. PP shall also explore and identify the chunk of land in the area from revenue record to carry out plantation programme as proposed.

VII. PP shall ensure proper implementation of plantation, dust suppression, construction of approach road and maintenance of existing pakka road as part of Environmental Management Plan. Additional budget provision shall be made as part of EMP.

VIII. PP must ensure implementation of the following activities with separate budget provision of total Rs 5.0 Lakh under CER:

Village Name: Panihara-pachara

Provide to distribution of mask , sanitizer (1st year ) . Provide to preparation of grazing land. (1st year ) . Provide to contribution for Jal Jeewan Mission to janpad panchayat

Panihara-pachara Provide to construction of 1 Room and Leveling of ground in Anganwadi

Panihara-pachara

PP shall ensure to contruct toilet with proper plumbing in the school of above village and contribute on behalf of village in Jal Jeewan Mission in consultation with Janpad Panchayat and PHED. PP shall give preference to develop/provide infrastructural facilities in schools or aanganwadies of above villages. The modification to the above activities can be made with the permission of the district administration and need based activity for the development of nearby villages shall be implemented by PP in consultation with the District Collector and Gram Panchayat.

IX. PP should ensure to submit half yearly compliance report, Plantation and CER activity report along with photographs of all activities in MP-SEIAA. If PP is failed to upload or submit two consecutive half yearly compliance reports of EC conditions to concerned authority (SEIAA and Regional Office, MoEF&CC,GoI,Bhopal) than prior environmental clearance issued to PP will automatically be treated as cancelled/ revoked as per OM No. 930/SEIAA/2019 dated 30.05.2019 issued by MPSEIAA.

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 117 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020

Hence, Prior Environmental Clearance is granted for Stone Quarry (Opencast Manual/Semi Mechanized Method) in an area of 4.0 ha. for production capacity of 48051 cum per annum at Khasra No. 42, 43, 236 at Village - Panihara-Pachara, Tehsil - Khaniadhana, Dist. Shivpuri (MP) for the lease period to M/s Osho Associate, 30, Satydev Nagar, Gandhi Road, Dist. Gwalior, MP – 473551.

49. Case No. 7829/2020; Prior Environmental Clearance for Soil Quarry (Opencast Manual/Semi Mechanized Method) in an area of 1.0 ha. for production capacity of 2400 cum per annum at Khasra No. 846, 847, 849 at Village - Hansai Mewda, Tehsil - Morena, Dist. Morena (MP) by M/s Kailadevi Ent Udhyog, Prop. Shri Shriniwas, Gram - Hansai Mewda, Tehsil & Dist. Morena, MP – 476001.

This case was recommended in 464th SEAC dated 3/10/2020 it was recorded that..........

"------------ The case was presented by the PP and their consultant wherein it was submitted by PP that it’s a soil query and no blasting is proposed. PP further submitted that kiln will not be installed within the lease. PP stated that this is a case of soil mining. The EMP and other submissions made by the PP were found to be satisfactory and acceptable, hence committee decided to recommend the case for grant of prior EC subject to the following special conditions in addition to the standard conditions at annexure ‘A’:

PP/Consultant made a presentation on all concerned issues were discussed in detail. After detailed discussions and perusal of recommendations of 464th SEAC meeting dated 3.10.2020, presentation made by the PP in SEIAA, it was decided to accept the recommendation of SEAC for grant of prior EC to the project subject to the following specific conditions:-

I. Before commencing any mining activity fencing shall be carried out all around the lease area. Proper watch and ward arrangements should be made with installation of signage at 4 corners of lease area to avoid any untoward incident involving public and animals by the PP.

II. PP shall not start mining activity before execution of lease agreement.

III. The depth of the pit shall be as per the Approved Mining Plan.

IV. The entire area shall be fenced and three rows of plantation should be done on the periphery of the boundary.

V. PP shall ensure the proper water supply arrangements for dust suppression, regular sprinkling, plantation and drinking purposes especially in summer season.

VI. Total 1200 saplings of suitable tree species i.e. Neem, Pipal,Bargad,Gulmohar Amla etc. shall be planted in nearby Khasra No. 590 of Village- Hansai Mewda, Tehsil - Morena, Dist. Morena ,by PP in first year under plantation programme in consultation with DM at identified revenue land of the district. PP shall also explore and identify the chunk of land in the area from revenue record to carry out plantation programme as proposed.

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 118 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020

VII. PP shall ensure proper implementation of plantation, dust suppression, construction of approach road and maintenance of existing pakka road as part of Environmental Management Plan. Additional budget provision shall be made as part of EMP.

VIII. PP must ensure implementation of the following activities with separate budget provision of total Rs 0.90 Lakh under CER:

Village Name Hansai Mewda:

Distribution of mask , sanitizer. Preparation of grazing land in village area. Proper maintenance of Village anganwadi Hansai Mewda: Repairing of walls Proper electric wiring Providing Toys ,chairs and tables in anganwadi Contribution for Jal Jeewan Mission to janpad panchayat Hansai Mewda.

PP shall ensure to contruct toilet with proper plumbing in the school of above village and contribute on behalf of village in Jal Jeewan Mission in consultation with Janpad Panchayat and PHED. PP shall give preference to develop/provide infrastructural facilities in schools or aanganwadies of above villages. The modification to the above activities can be made with the permission of the district administration and need based activity for the development of nearby villages shall be implemented by PP in consultation with the District Collector and Gram Panchayat.

IX. PP should ensure to submit half yearly compliance report, Plantation and CER activity report along with photographs of all activities in MP-SEIAA. If PP is failed to upload or submit two consecutive half yearly compliance reports of EC conditions to concerned authority (SEIAA and Regional Office, MoEF&CC,GoI,Bhopal) than prior environmental clearance issued to PP will automatically be treated as cancelled/ revoked as per OM No. 930/SEIAA/2019 dated 30.05.2019 issued by MPSEIAA.

Hence, Prior Environmental Clearance is granted for Soil Quarry (Opencast Manual/Semi Mechanized Method) in an area of 1.0 ha. for production capacity of 2400 cum per annum at Khasra No. 846, 847, 849 at Village - Hansai Mewda, Tehsil - Morena, Dist. Morena (MP) for the lease period to M/s Kailadevi Ent Udhyog, Prop., Shri Shriniwas, Gram - Hansai Mewda, Tehsil & Dist. Morena, MP – 476001.

50. Case No. 7820/2020; Prior Environmental Clearance for Stone Quarry (Opencast Manual/Semi Mechanized Method) in an area of 1.0 ha. for production capacity of 5000 cum per annum at Khasra No. 61/1, 61/2 at Village - Rampurachakaldi, Tehsil

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 119 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020

- Rehti, Dist. Sehore (MP) by Shri Amjad Ali S/o Shri Ajaz Ali, Chandni Garden, Nasrullaganj, Dist. Sehore, MP.

This case was recommended in 464th SEAC dated 3/10/2020 it was recorded that..........

"------------ The case was presented by the PP and their consultant. PP stated that this is a case of stone mining. The EMP and other submissions made by the PP were found to be satisfactory and acceptable, hence committee decided to recommend the case for grant of prior EC subject to the following special conditions in addition to the standard conditions at annexure ‘A’:

PP/Consultant made a presentation on all concerned issues were discussed in detail. After detailed discussions and perusal of recommendations of 464th SEAC meeting dated 3.10.2020, presentation made by the PP in SEIAA, it was decided to accept the recommendation of SEAC for grant of prior EC to the project subject to the following specific conditions:-

I. Before commencing any mining activity fencing shall be carried out all around the lease area. Proper watch and ward arrangements should be made with installation of signage at 4 corners of lease area to avoid any untoward incident involving public and animals by the PP.

II. PP shall not start mining activity before execution of lease agreement.

III. The depth of the pit shall be as per the Approved Mining Plan.

IV. The entire area shall be fenced and three rows of plantation should be done on the periphery of the boundary.

V. PP shall ensure the proper water supply arrangements for dust suppression, regular sprinkling, plantation and drinking purposes especially in summer season.

VI. Total 1200 saplings of suitable tree species i.e. Neem, Pipal,Bargad,Gulmohar Amla etc. shall be planted in nearby Khasra No. 61/1 and 61/2 of Village – Rampurachakaldi, Tehsil - Rehti, Dist. Sehore,by PP under plantation programme in consultation with DM at identified revenue land of the district. PP shall also explore and identify the chunk of land in the area from revenue record to carry out plantation programme as proposed.

VII. PP shall ensure proper implementation of plantation, dust suppression, construction of approach road and maintenance of existing pakka road as part of Environmental Management Plan. Additional budget provision shall be made as part of EMP.

VIII. PP must ensure implementation of the following activities with separate budget provision of total Rs ------Lakh under CER:

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 120 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020

a) 1st to 2nd Year : Provide to distribution of masks and sanitizers to villagers and conducting an awareness program through Panchayat for the protection from the spread of Corona virus (COVID 19 Pandemic), development of grazing land and whitewash and maintenance (Doors, windows and walls) of Govt. Secondary school, Chakaldi

b) 3rd to 4tn Year : Provide to construction of Boundary wall of Govt. Primary school, Amajhir

c) 5tn Year : Provide to Lab equipments and furnitures for Govt. school, Satrana

PP shall ensure to contruct toilet with proper plumbing in the school of above village and contribute on behalf of village in Jal Jeewan Mission in consultation with Janpad Panchayat and PHED. PP shall give preference to develop/provide infrastructural facilities in schools or aanganwadies of above villages. The modification to the above activities can be made with the permission of the district administration and need based activity for the development of nearby villages shall be implemented by PP in consultation with the District Collector and Gram Panchayat.

IX. PP should ensure to submit half yearly compliance report, Plantation and CER activity report along with photographs of all activities in MP-SEIAA. If PP is failed to upload or submit two consecutive half yearly compliance reports of EC conditions to concerned authority (SEIAA and Regional Office, MoEF&CC,GoI,Bhopal) than prior environmental clearance issued to PP will automatically be treated as cancelled/ revoked as per OM No. 930/SEIAA/2019 dated 30.05.2019 issued by MPSEIAA.

Hence, Prior Environmental Clearance is granted for Stone Quarry (Opencast Manual/Semi Mechanized Method) in an area of 1.0 ha. for production capacity of 5000 cum per annum at Khasra No. 61/1, 61/2 at Village - Rampurachakaldi, Tehsil - Rehti, Dist. Sehore (MP) for the lease period to Shri Amjad Ali S/o Shri Ajaz Ali, Chandni Garden, Nasrullaganj, Dist. Sehore, MP.

51. Case No. 7831/2020; Prior Environmental Clearance for Fire Clay Mine (Opencast Manual/Semi Mechanized Method) in an area of 4.643 ha. for production capacity of of 9696 tonne per annum at Khasra No. 209/2 at Village - Badawar, Tehsil - Bandhavgarh, Dist. Umaria (MP) by Shri Ashok Kumar Gupta, Purana Padav, Dist. Umaria, MP – 484661.

This case was recommended in 464th SEAC dated 3/10/2020 it was recorded that..........

"------------ PP has submitted the response of above quarries same date vide letter dated 03.10.2020, which was placed before the committee and the same found satisfactory. The EMP and other submissions made by the PP were found to be satisfactory and acceptable, hence committee decided to recommend the case for grant of prior EC subject to the following special conditions in addition to the standard conditions at annexure ‘A’:

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 121 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020

PP/Consultant made a presentation on all concerned issues was discussed in detail. After detailed discussions and perusal of recommendations of 464th SEAC meeting dated 3.10.2020, presentation made by the PP in SEIAA, it was decided to accept the recommendation of SEAC for grant of prior EC to the project subject to the following specific conditions:-

I. Before commencing any mining activity fencing shall be carried out all around the lease area. Proper watch and ward arrangements should be made with installation of signage at 4 corners of lease area to avoid any untoward incident involving public and animals by the PP.

II. PP shall not start mining activity before execution of lease agreement.

III. The depth of the pit shall be as per the Approved Mining Plan.

IV. The entire area shall be fenced and three rows of plantation should be done on the periphery of the boundary.

V. PP shall ensure the proper water supply arrangements for dust suppression, regular sprinkling, plantation and drinking purposes especially in summer season.

VI. PP shall ensure the compliance of conitions given in Commissioner Committee report

VII. Total 5600 saplings of suitable tree species i.e. Neem, Pipal,Bargad, Gulmohar Amla etc. shall be planted in nearby Khasra No. ,by PP in under plantation programme in consultation with DM at identified revenue land of the district. PP shall also explore and identify the chunk of land in the area from revenue record to carry out plantation programme as proposed.

VIII. PP shall ensure proper implementation of plantation, dust suppression, construction of approach road and maintenance of existing pakka road as part of Environmental Management Plan. Additional budget provision shall be made as part of EMP.

IX. PP must ensure implementation of the following activities with separate budget provision of total Rs 3.00 Lakh under CER:

Distribution of masks and sanitizers to villagers and conducting an awareness program through Panchayat for the protection from the spread of Corona virus (COVID 19 Pandemic)

Development of grazing land

10 benches & Tables for students of Govt. School, Badawar

Whitewash and Cemented water tank with pipe fitting for drinking water in school, Pali

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 122 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020

Construction of pucca chabutra, periphery of handpump with haud, and whitewash Govt. Higher secondary school, Karkeli

PP shall ensure to contruct toilet with proper plumbing in the school of above village and contribute on behalf of village in Jal Jeewan Mission in consultation with Janpad Panchayat and PHED. PP shall give preference to develop/provide infrastructural facilities in schools or aanganwadies of above villages. The modification to the above activities can be made with the permission of the district administration and need based activity for the development of nearby villages shall be implemented by PP in consultation with the District Collector and Gram Panchayat.

X. PP should ensure to submit half yearly compliance report, Plantation and CER activity report along with photographs of all activities in MP-SEIAA. If PP is failed to upload or submit two consecutive half yearly compliance reports of EC conditions to concerned authority (SEIAA and Regional Office, MoEF&CC,GoI,Bhopal) than prior environmental clearance issued to PP will automatically be treated as cancelled/ revoked as per OM No. 930/SEIAA/2019 dated 30.05.2019 issued by MPSEIAA.

Hence, Prior Environmental Clearance is granted for Fire Clay Mine (Opencast Manual/Semi Mechanized Method) in an area of 4.643 ha. for production capacity of of 9696 tonne per annum at Khasra No. 209/2 at Village - Badawar, Tehsil - Bandhavgarh, Dist. Umaria (MP) for the lease period to Shri Ashok Kumar Gupta, Purana Padav, Dist. Umaria, MP – 484661.

52. Case No. 7823/2020; Prior Environmental Clearance for Stone Quarry (Opencast

Manual/Semi Mechanized Method) in an area of 1.0 ha. for production capacity of of 7291 cum per annum at Khasra No. 36/1 at Village - Lilatola, Tehsil - Pushprajgarh, Dist. Anuppur (MP) by M/s Shiv Shakti Stone Crusher, Prop. Smt. Sumitra Chouksey, R/o Village & Post - Lilatola, Tehsil - Pushprajgarh, Dist. Anuppur, MP.

This case was recommended in 464th SEAC dated 3/10/2020 it was recorded that..........

"------------ PP has submitted the response of above quarries same date vide letter dated 03.10.2020, which was placed before the committee and the same found satisfactory.The EMP and other submissions made by the PP were found to be satisfactory and acceptable, hence committee decided to recommend the case for grant of prior EC subject to the following special conditions in addition to the standard conditions at annexure ‘A’:

PP/Consultant made a presentation on all concerned issues were discussed in detail. After detailed discussions and perusal of recommendations of 464th SEAC meeting dated 3.10.2020, presentation made by the PP in SEIAA, it was decided to accept the recommendation of SEAC for grant of prior EC to the project subject to the following specific conditions:-

I. Before commencing any mining activity fencing shall be carried out all around the lease area. Proper watch and ward arrangements should be made with

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 123 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020

installation of signage at 4 corners of lease area to avoid any untoward incident involving public and animals by the PP.

II. PP shall not start mining activity before execution of lease agreement.

III. The depth of the pit shall be as per the Approved Mining Plan.

IV. The entire area shall be fenced and three rows of plantation should be done on the periphery of the boundary.

V. PP shall ensure the proper water supply arrangements for dust suppression, regular sprinkling, plantation and drinking purposes especially in summer season.

VI. Total 1200 saplings of suitable tree species i.e. Neem, Pipal,Bargad,Gulmohar Amla etc. shall be planted in nearby Khasra No. 39/1 of Village – Lilatola, Tehsil - Pushprajgarh, Dist. Anuppur, by PP under plantation programme in consultation with DM at identified revenue land of the district. PP shall also explore and identify the chunk of land in the area from revenue record to carry out plantation programme as proposed.

VII. PP shall ensure proper implementation of plantation, dust suppression, construction of approach road and maintenance of existing pakka road as part of Environmental Management Plan. Additional budget provision shall be made as part of EMP.

VIII. PP must ensure implementation of the following activities with separate budget provision of total Rs 2.50 Lakh under CER:

Village Name: Lilatola Distribution of masks and sanitizers to villagers for 1st year only. -Development and maintenance of grassland on a nearby suitable

government land (from 1st to 5th year). Repair and whitewash of village primary school building. Repairing work and paint in anganwadi at Lilatola village Supply of basic school furniture and other necessary items as needed.

- PP shall ensure to contruct toilet with proper plumbing in the school of above village and contribute on behalf of village in Jal Jeewan Mission in consultation with Janpad Panchayat and PHED. PP shall give preference to develop/provide infrastructural facilities in schools or aanganwadies of above villages. The modification to the above activities can be made with the permission of the district administration and need based activity for the development of nearby villages shall be implemented by PP in consultation with the District Collector and Gram Panchayat.

IX. PP should ensure to submit half yearly compliance report, Plantation and CER activity report along with photographs of all activities in MP-SEIAA. If PP

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 124 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020

is failed to upload or submit two consecutive half yearly compliance reports of EC conditions to concerned authority (SEIAA and Regional Office, MoEF&CC,GoI,Bhopal) than prior environmental clearance issued to PP will automatically be treated as cancelled/ revoked as per OM No. 930/SEIAA/2019 dated 30.05.2019 issued by MPSEIAA.

Hence, Prior Environmental Clearance is granted for Stone Quarry (Opencast Manual/Semi Mechanized Method) in an area of 1.0 ha. for production capacity of of 7291 cum per annum at Khasra No. 36/1 at Village - Lilatola, Tehsil - Pushprajgarh, Dist. Anuppur (MP) for the lease period to M/s Shiv Shakti Stone Crusher, Prop. Smt. Sumitra Chouksey, R/o Village & Post - Lilatola, Tehsil - Pushprajgarh, Dist. Anuppur, MP

53. Case No. 7846/2020; Prior Environmental Clearance for Soil Quarry (Opencast Manual/Semi Mechanized Method) in an area of 1.0 ha. for production capacity of of 2000 cum per annum at Khasra No. 1152, 1168 at Village - Nepari, Tehsil - Kailaras, Dist. Morena (MP) by Shri Damodar Prasad Rajoria S/o Shri Dwarika Prasad Rajoria, Village - Ambah Road, Gram - Mudiyakheda, Tehsil & Dist. Morena, MP.

This case was recommended in 464th SEAC dated 3/10/2020 it was recorded that..........

"------------ PP has submitted the response of above quarries same date vide letter dated 03.10.2020, which was placed before the committee and the same found satisfactory.The EMP and other submissions made by the PP were found to be satisfactory and acceptable, hence committee decided to recommend the case for grant of prior EC subject to the following special conditions in addition to the standard conditions at annexure ‘A’:

PP/Consultant made a presentation on all concerned issues were discussed in detail. After detailed discussions and perusal of recommendations of 464th SEAC meeting dated 3.10.2020, presentation made by the PP in SEIAA, it was decided to accept the recommendation of SEAC for grant of prior EC to the project subject to the following specific conditions:-

I. Before commencing any mining activity fencing shall be carried out all around the lease area. Proper watch and ward arrangements should be made with installation of signage at 4 corners of lease area to avoid any untoward incident involving public and animals by the PP.

II. PP shall not start mining activity before execution of lease agreement.

III. The depth of the pit shall be as per the Approved Mining Plan.

IV. The entire area shall be fenced and three rows of plantation should be done on the periphery of the boundary.

V. PP shall ensure the proper water supply arrangements for dust suppression, regular sprinkling, plantation and drinking purposes especially in summer season.

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 125 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020

VI. Total 1200 saplings of suitable tree species i.e. Neem, Pipal,Bargad,Gulmohar Amla etc. shall be planted in nearby Khasra No.,by PP under plantation programme in consultation with DM at identified revenue land of the district. PP shall also explore and identify the chunk of land in the area from revenue record to carry out plantation programme as proposed.

VII. PP shall ensure proper implementation of plantation, dust suppression, construction of approach road and maintenance of existing pakka road as part of Environmental Management Plan. Additional budget provision shall be made as part of EMP.

VIII. PP must ensure implementation of the following activities with separate budget provision of total Rs 0.60 Lakh under CER:

Making the availability of the water filter in the Schools, Nepari , Kailras Village

Contribution in Conservation of grazing land

PP shall ensure to contruct toilet with proper plumbing in the school of above village and contribute on behalf of village in Jal Jeewan Mission in consultation with Janpad Panchayat and PHED. PP shall give preference to develop/provide infrastructural facilities in schools or aanganwadies of above villages. The modification to the above activities can be made with the permission of the district administration and need based activity for the development of nearby villages shall be implemented by PP in consultation with the District Collector and Gram Panchayat.

IX. PP should ensure to submit half yearly compliance report, Plantation and CER activity report along with photographs of all activities in MP-SEIAA. If PP is failed to upload or submit two consecutive half yearly compliance reports of EC conditions to concerned authority (SEIAA and Regional Office, MoEF&CC,GoI,Bhopal) than prior environmental clearance issued to PP will automatically be treated as cancelled/ revoked as per OM No. 930/SEIAA/2019 dated 30.05.2019 issued by MPSEIAA.

Hence, Prior Environmental Clearance is granted for Soil Quarry (Opencast Manual/Semi Mechanized Method) in an area of 1.0 ha. for production capacity of of 2000 cum per annum at Khasra No. 1152, 1168 at Village - Nepari, Tehsil - Kailaras, Dist. Morena (MP) for the lease period to Shri Damodar Prasad Rajoria S/o Shri Dwarika Prasad Rajoria, Village - Ambah Road, Gram - Mudiyakheda, Tehsil & Dist. Morena, MP.

54. Case No. 7853/2020; Prior Environmental Clearance for Stone Quarry (Opencast Manual/Semi Mechanized Method) in an area of 1.836 ha. for production capacity of 50000 cum per annum at Khasra No. 3/1, 3/3/2, 3/4, 3/5 at Village - Gangapur, Tehsil - Dabra, Dist. Gwalior (MP) by Shri Yogendra Sharma S/o Shri Surajmal Sharma, R/o D.H. 14, 15, Parl Residency, Behind Sita Menor Hotel, Dist. Gwalior, MP.

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 126 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020

This case was recommended in 464th SEAC dated 3/10/2020 it was recorded that..........

"------------ PP has submitted the response of above quarries same date vide letter dated 03.10.2020, which was placed before the committee and the same found satisfactory.The EMP and other submissions made by the PP were found to be satisfactory and acceptable, hence committee decided to recommend the case for grant of prior EC subject to the following special conditions in addition to the standard conditions at annexure ‘A’:

PP/Consultant made a presentation on all concerned issues were discussed in detail. After detailed discussions and perusal of recommendations of 464th SEAC meeting dated 3.10.2020, presentation made by the PP in SEIAA, it was decided to accept the recommendation of SEAC for grant of prior EC to the project subject to the following specific conditions:-

I. Before commencing any mining activity fencing shall be carried out all around the lease area. Proper watch and ward arrangements should be made with installation of signage at 4 corners of lease area to avoid any untoward incident involving public and animals by the PP.

II. PP shall not start mining activity before execution of lease agreement.

III. The depth of the pit shall be as per the Approved Mining Plan.

IV. The entire area shall be fenced and three rows of plantation should be done on the periphery of the boundary.

V. PP shall ensure the proper water supply arrangements for dust suppression, regular sprinkling, plantation and drinking purposes especially in summer season.

VI. Total 2400 saplings of suitable tree species i.e. Neem, Pipal,Bargad,Gulmohar Amla etc. shall be planted in nearby Khasra No.,by PP in under plantation programme in consultation with DM at identified revenue land of the district. PP shall also explore and identify the chunk of land in the area from revenue record to carry out plantation programme as proposed.

VII. PP shall ensure proper implementation of plantation, dust suppression, construction of approach road and maintenance of existing pakka road as part of Environmental Management Plan. Additional budget provision shall be made as part of EMP.

VIII. PP must ensure implementation of the following activities with separate budget provision of total Rs 1.50 Lakh under CER:

Government School, Gangapur needs water Proofing & Roof Treatment on village school and building maintenance including repaint.

Organizing a traffic awareness camp in the village.

PP shall ensure to contruct toilet with proper plumbing in the school of above village and contribute on behalf of village in Jal Jeewan Mission in

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 127 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020

consultation with Janpad Panchayat and PHED. PP shall give preference to develop/provide infrastructural facilities in schools or aanganwadies of above villages. The modification to the above activities can be made with the permission of the district administration and need based activity for the development of nearby villages shall be implemented by PP in consultation with the District Collector and Gram Panchayat.

IX. PP should ensure to submit half yearly compliance report, Plantation and CER activity report along with photographs of all activities in MP-SEIAA. If PP is failed to upload or submit two consecutive half yearly compliance reports of EC conditions to concerned authority (SEIAA and Regional Office, MoEF&CC,GoI,Bhopal) than prior environmental clearance issued to PP will automatically be treated as cancelled/ revoked as per OM No. 930/SEIAA/2019 dated 30.05.2019 issued by MPSEIAA.

Hence, Prior Environmental Clearance is granted for Stone Quarry (Opencast Manual/Semi Mechanized Method) in an area of 1.836 ha. for production capacity of 50000 cum per annum at Khasra No. 3/1, 3/3/2, 3/4, 3/5 at Village - Gangapur, Tehsil - Dabra, Dist. Gwalior (MP) for the lease period to Shri Yogendra Sharma S/o Shri Surajmal Sharma, R/o D.H. 14, 15, Parl Residency, Behind Sita Menor Hotel, Dist. Gwalior, MP.

55. Case No. 7844/20 Prior Environmental Clearance for Marble Mine (opencast mechanized method) in an area of 4.0 ha. for ROM 9129 cum per annum (Marble Block - 1826 cum per annum + Mine Waste - 7303 cum per annum) (Khasra No. 2197 Part), Village - Karmai, Tehsil - Majholi, Dist. - Sidhi (MP) by M/s Onyx Marble, Azad Ward, Mandla, Dist. - Mandla, MP - 481661, EMail – [email protected].

This case was recommended in 464th SEAC meeting dated 03.10.2020 and it was recorded that..........

“------------PP has submitted the response of above quarries same date vide letter dated 03.10.2020, which was placed before the committee and the same found satisfactory.The EMP and other submissions made by the PP were found to be satisfactory and acceptable, hence committee decided to recommend the case for grant of prior EC subject to the following special conditions in addition to the standard conditions at annexure ‘A’:

PP/Consultant made a presentation on all aspects of the project and all concerned issues were discussed in detail. After detailed discussions and perusal of recommendations of 464th SEAC meeting dated 03.10.2020, presentation made by the PP in SEIAA, it was decided to accept the recommendation of SEAC for grant of prior EC to the project subject to the following specific conditions:-

i. Before commencing any mining activity fencing shall be carried out all around the lease area. Proper watch and ward arrangements should be made with installation of signage at 4 corners of lease area to avoid any untoward incident involving public and animals by the PP.

ii. PP shall not start mining activity before execution of lease agreement.

iii. The depth of the pit shall be as per the Approved Mining Plan.

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 128 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020

iv. The entire area shall be fenced and three rows of plantation should be done on the periphery of the boundary.

v. PP shall not uproot 47 trees exist in the lease area without permission of competent authority and leave this area as no mining zone.

vi. PP shall ensure the proper water supply arrangements for dust suppression, regular sprinkling, plantation and drinking purposes especially in summer season.

vii. Total 1000 saplings of suitable tree species i.e. Neem, Pipal, Bargad, Mango, Gulmohar, Sissoo, Kathal, etc. shall be planted by PP under plantation programme at un-worked area, backfilled area, bench area in consultation with Gram Panchayat/ DM. PP shall also explore and identify the chunk of land in the area from revenue record to carry out plantation programme as proposed.

viii. PP shall ensure proper implementation of plantation, dust suppression, construction of approach road and maintenance of existing pakka road as part of Environmental Management Plan. Additional budget provision shall be made as part of EMP.

ix. PP must ensure implementation of the following activities with separate budget provision of total Rs. 6.0 lakh under CER as committed:

Development of Grazing land Distribution of sanitizer, Mask, Oximeter, thermometer at PHC,

aanganwadi of nearby villages. To provide infrastructure support like play ground, furniture, boundary

wall, toilets, etc to the village school at Karmai & Tal. Contribution of fund or execution of plumbing network for

implementation of Jal Jivan Scheme to villagers houses or at school in Tal, Karmai and other villages in consultation with the local administration.

PP shall ensure to contruct toilet with proper plumbing in the school of above village and contribute on behalf of village in Jal Jeewan Mission in consultation with Janpad Panchayat and PHED. PP shall give preference to develop/provide infrastructural facilities in schools or aanganwadies of above villages. The modification to the above activities can be made with the permission of the district administration and need based activity for the development of nearby villages shall be implemented by PP in consultation with the District Collector and Gram Panchayat.

x. PP should ensure to submit half yearly compliance report, Plantation and CER activity report along with photographs of all activities in MP-SEIAA. If PP is failed to upload or submit two consecutive half yearly compliance reports of EC conditions to concerned authority (SEIAA and Regional Office, MoEF&CC,GoI,Bhopal) than prior environmental clearance issued to PP will automatically be treated as cancelled/ revoked as per OM No. 930/SEIAA/2019 dated 30.05.2019 issued by MPSEIAA.

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 129 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020

Hence, Prior Environmental Clearance is granted for Marble Mine (opencast mechanized method) in an area of 4.0 ha. for ROM 9129 cum per annum (Marble Block - 1826 cum per annum + Mine Waste - 7303 cum per annum) (Khasra No. 2197 Part), Village - Karmai, Tehsil - Majholi, Dist. - Sidhi (MP) for the lease period to M/s Onyx Marble, Azad Ward, Mandla, Dist. - Mandla, MP - 481661, EMail – [email protected].

56. Case No 7849/2020 Prior Environmental Clearance for Stone Quarry (Opencast Manual / Semi Mechanized Method) in an area of 1.50 ha. for production capacity of 5250 cum / year at Khasra No. 484 at Village - Akyanajik, Tehsil - Nagda, Dist. Ujjain by Shri Mohan Singh S/o Shri Kamal SIngh, Gram - Akyanajik, Tehsil - Nagda, Dist. Ujjain, MP

This case was recommended in 464th SEAC meeting dated 03.10.2020 and it was recorded that..........

“…………PP has submitted the response of above quarries same date vide letter dated 03.10.2020, which was placed before the committee and the same found satisfactory.The EMP and other submissions made by the PP were found to be satisfactory and acceptable, hence committee decided to recommend the case for grant of prior EC subject to the following special conditions in addition to the standard conditions at annexure ‘A’:”

PP/Consultant made a presentation on all aspects of the project and all concerned issues were discussed in detail. After detailed discussions and perusal of recommendations of 464th SEAC meeting dated 03.10.2020, presentation made by the PP in SEIAA, it was decided to accept the recommendation of SEAC for grant of prior EC to the project subject to the following specific conditions:-

I. Before commencing any mining activity fencing shall be carried out all around the lease area. Proper watch and ward arrangements should be made with installation of signage at 4 corners of lease area to avoid any untoward incident involving public and animals by the PP.

II. PP shall not start mining activity before execution of lease agreement. III. The depth of the pit shall be as per the Approved Mining Plan. IV. The entire area shall be fenced and three rows of plantation should be done

on the periphery of the boundary. V. PP shall ensure that the proper water supply arrangements for dust

suppression, regular sprinkling, plantation and drinking purposes especially in summer season.

VI. PP shall ensure to construct and maintained the approach road. Plantation will be carried out on both side of approach road.

VII. PP shall ensure proper implementation of plantation, dust suppression, construction of approach road and maintenance of existing road & as part of Environmental Management Plan. Additional budget provision shall be made as part of EMP.

VIII. Total 1800 saplings of suitable tree species i.e. Neem, Pipal, Bargad, Mango, Amla, Amaltas, Drumstick etc. shall be planted by PP at mine lease boundary (1200 saplings) and 600 saplings at khasra no 484 ( Govt land) under plantation programme. PP shall also explore and identify the chunk of

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 130 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020

land in the area from revenue record to carry out plantation programme as proposed.

IX. PP must ensure implementation of the following activities with separate budget provision of Rs 1.50 lakh under CER.

CER activities at village Akyajanik (1st to 5th Year)

Color Paint of Boundary Wall at Village Middle School – 50,000/- Providing Bench’s at Village Middle School (50 Nos) – Rs.1,00,000/-

PP shall ensure to contruct toilet with proper plumbing in the school of above village and contribute on behalf of village in Jal Jeewan Mission in consultation with Janpad Panchayat and PHED. PP shall give preference to develop/provide infrastructural facilities in schools or aganwadies of above villages The modification to the above activities can be made with the permission of the district administration and need based activity for the development of nearby villages shall be implemented by PP in consultation with the District Collector and Gram Panchayat

X. PP should ensure to submit half yearly compliance report and CSR activity report with photographs of plantation in MP-SEIAA. If PP is failed to upload or submit two consecutive half yearly compliance reports of EC conditions to concerned authority (SEIAA and Regional Office, MoEF&CC,GoI,Bhopal) than prior environmental clearance issued to PP will automatically be treated as cancelled/ revoked as per OM No. 930/SEIAA/2019 dated 30.05.2019 issued by MPSEIAA.

Hence, Prior Environmental Clearance is granted for Stone Quarry (Opencast Manual / Semi Mechanized Method) in an area of 1.50 ha. for production capacity of 5250 cum / year at Khasra No. 484 at Village - Akyanajik, Tehsil - Nagda, Dist. Ujjain for the lease period to Shri Mohan Singh S/o Shri Kamal SIngh, Gram - Akyanajik, Tehsil - Nagda, Dist. Ujjain, MP

57. Case No 7850/2020 Prior Environmental Clearance for Stone & Murrum Quarry (Opencast Manual / Semi Mechanized Method) in an area of 1.80 ha. for production capacity of Stone - 35013 cum / year, Murrum - 7838 cum / year at Khasra No. 1630/1, 1630/2, 1621, 1631 at Village - Elchi, Tehsil - Dalauda, Dist. Mandsaur (MP) by Shri Madhusudan Patidar S/o Shri Harivallabh Patidar, Richhalalmuha, Tehsil - Dalauda, Dist. Mandsaur, MP - 458667

This case was recommended in 464th SEAC meeting dated 03.10.2020 and it was recorded that..........

“…………PP has submitted the response of above quarries same date vide letter dated 03.10.2020, which was placed before the committee and the same found satisfactory.The EMP and other submissions made by the PP were found to be satisfactory and acceptable, hence committee decided to recommend the case for grant of prior EC subject to the following special conditions in addition to the standard conditions at annexure ‘A’”

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 131 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020

PP/Consultant made a presentation on all aspects of the project and all concerned issues were discussed in detail. After detailed discussions and perusal of recommendations of 464th SEAC meeting dated 03.10.2020, presentation made by the PP in SEIAA, it was decided to accept the recommendation of SEAC for grant of prior EC to the project subject to the following specific conditions:-

I. Before commencing any mining activity fencing shall be carried out all around the lease area. Proper watch and ward arrangements should be made with installation of signage at 4 corners of lease area to avoid any untoward incident involving public and animals by the PP.

II. PP shall not start mining activity before execution of lease agreement. III. The depth of the pit shall be as per the Approved Mining Plan. IV. The entire area shall be fenced and three rows of plantation should be done

on the periphery of the boundary. V. PP shall ensure that the proper water supply arrangements for dust

suppression, regular sprinkling, plantation and drinking purposes especially in summer season.

VI. PP shall ensure to construct and maintained the approach road. Plantation will be carried out on both side of approach road.

VII. PP shall ensure proper implementation of plantation, dust suppression, construction of approach road and maintenance of existing road & as part of Environmental Management Plan. Additional budget provision shall be made as part of EMP.

VIII. Total 2200 saplings of suitable tree species i.e. Neem, Pipal, Bargad, Mango, Amla, Amaltas, Drumstick etc. shall be planted by PP at mine lease boundary (1600 saplings) and 600 saplings at khasra no. 1624/2,1624/4 ( Private waste land) under plantation programme. PP shall also explore and identify the chunk of land in the area from revenue record to carry out plantation programme as proposed.

IX. PP must ensure implementation of the following activities with separate budget provision of Rs 3.50 lakh under CER.

CER activities at village Elchi (1st to 5th Year)

Providing Water Filter at Village School- Rs. 10,000/-

Construction of Village School Boundary Wall (120m) – Rs.3,00,000/- Providing Bench’s at Village Primary School (20 Nos) – Rs. 40,000/-

PP shall ensure to contruct toilet with proper plumbing in the school of above village and contribute on behalf of village in Jal Jeewan Mission in consultation with Janpad Panchayat and PHED. PP shall give preference to develop/provide infrastructural facilities in schools or aganwadies of above villages The modification to the above activities can be made with the permission of the district administration and need based activity for the development of nearby villages shall be implemented by PP in consultation with the District Collector and Gram Panchayat

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 132 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020

X. PP should ensure to submit half yearly compliance report and CSR activity report with photographs of plantation in MP-SEIAA. If PP is failed to upload or submit two consecutive half yearly compliance reports of EC conditions to concerned authority (SEIAA and Regional Office, MoEF&CC,GoI,Bhopal) than prior environmental clearance issued to PP will automatically be treated as cancelled/ revoked as per OM No. 930/SEIAA/2019 dated 30.05.2019 issued by MPSEIAA.

Hence, Prior Environmental Clearance is granted for Stone & Murrum Quarry (Opencast Manual / Semi Mechanized Method) in an area of 1.80 ha. for production capacity of Stone - 35013 cum / year, Murrum - 7838 cum / year at Khasra No. 1630/1, 1630/2, 1621, 1631 at Village - Elchi, Tehsil - Dalauda, Dist. Mandsaur (MP) for the lease period to Shri Madhusudan Patidar S/o Shri Harivallabh Patidar, Richhalalmuha, Tehsil - Dalauda, Dist. Mandsaur, MP - 458667

58. Case No 7851/2020 Prior Environmental Clearance for Stone Quarry (Opencast Manual / Semi Mechanized Method) in an area of 1.80 ha. for production capacity of Stone - 29175 cum/ year, Murrum - 5835 cum/ year at Khasra No. 163 at Village - Mahumandli, Tehsil - Gogawa, Dist. Khargone (MP) by M/s J.P.Group of Construction, Prop. Shri Aanand Sen, Krishan Kunj Colony, Dist. Khargone, MP – 451441

This case was recommended in 464th SEAC meeting dated 03.10.2020 and it was recorded that..........

“…………PP has submitted the response of above quarries same date vide letter dated 03.10.2020, which was placed before the committee and the same found satisfactory.The EMP and other submissions made by the PP were found to be satisfactory and acceptable, hence committee decided to recommend the case for grant of prior EC subject to the following special conditions in addition to the standard conditions at annexure ‘A’:’”

PP/Consultant made a presentation on all aspects of the project and all concerned issues were discussed in detail. After detailed discussions and perusal of recommendations of 464th SEAC meeting dated 03.10.2020, presentation made by the PP in SEIAA, it was decided to accept the recommendation of SEAC for grant of prior EC to the project subject to the following specific conditions:-

I. Before commencing any mining activity fencing shall be carried out all around the lease area. Proper watch and ward arrangements should be made with installation of signage at 4 corners of lease area to avoid any untoward incident involving public and animals by the PP.

II. PP shall not start mining activity before execution of lease agreement. III. The depth of the pit shall be as per the Approved Mining Plan. IV. The entire area shall be fenced and three rows of plantation should be done

on the periphery of the boundary. V. PP shall ensure that the proper water supply arrangements for dust

suppression, regular sprinkling, plantation and drinking purposes especially in summer season.

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 133 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020

VI. PP shall ensure to construct and maintained the approach road. Plantation will be carried out on both side of approach road.

VII. PP shall ensure proper implementation of plantation, dust suppression, construction of approach road and maintenance of existing road & as part of Environmental Management Plan. Additional budget provision shall be made as part of EMP.

VIII. PP shall ensure that 50 meters setback be left a surface drain is in existance on the southern side

IX. Total 2200 saplings of suitable tree species i.e. Neem, Pipal, Bargad, Mango, Amla, Amaltas, Drumstick etc. shall be planted by PP at mine lease boundary (1600 saplings) and 600 saplings at khasra no. 163 ( Private waste land) under plantation programme. PP shall also explore and identify the chunk of land in the area from revenue record to carry out plantation programme as proposed.

X. PP must ensure implementation of the following activities with separate budget provision of Rs 3.0 lakh under CER.

CER activities at village Mahumandli (1st to 5th Year)

Providing Water Filter at Village School- Rs. 10000/-

Tiling Work at One Village Classroom – 40,000/- Construction of School New Toilet with overhead water tank – 55,000/- Construction of Village School Boundary Wall (65m) – Rs.1,95,000/-,

PP shall ensure to contruct toilet with proper plumbing in the school of above village and contribute on behalf of village in Jal Jeewan Mission in consultation with Janpad Panchayat and PHED. PP shall give preference to develop/provide infrastructural facilities in schools or aganwadies of above villages The modification to the above activities can be made with the permission of the district administration and need based activity for the development of nearby villages shall be implemented by PP in consultation with the District Collector and Gram Panchayat

XI. PP should ensure to submit half yearly compliance report and CSR activity report with photographs of plantation in MP-SEIAA. If PP is failed to upload or submit two consecutive half yearly compliance reports of EC conditions to concerned authority (SEIAA and Regional Office, MoEF&CC,GoI,Bhopal) than prior environmental clearance issued to PP will automatically be treated as cancelled/ revoked as per OM No. 930/SEIAA/2019 dated 30.05.2019 issued by MPSEIAA.

Hence, Prior Environmental Clearance is granted for Stone Quarry (Opencast Manual / Semi Mechanized Method) in an area of 1.80 ha. for production capacity of Stone - 29175 cum/ year, Murrum - 5835 cum/ year at Khasra No. 163 at Village - Mahumandli, Tehsil - Gogawa, Dist. Khargone (MP) for the lease period to M/s J.P.Group of Construction, Prop. Shri Aanand Sen, Krishan Kunj Colony, Dist. Khargone, MP – 451441

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 134 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020 59. Case No 7830/2020 Prior Environmental Clearance for Murrum Quarry (Opencast

Manual / Semi Mechanized Method) in an area of 2.0 ha. for production capacity of 18900 cum / year ar Khasra No. 273/1 at Village - Nogawan Kala, Tehsil - Ratlam, Dist. Ratlam (MP) by Shri Rajesh Jat S/o Shri Lalji Jat, Gram - Badoda, Tehsil & Dist. Ratlam, MP – 457222

This case was recommended in 464th SEAC meeting dated 03.10.2020 and it was recorded that..........

“…………The case was presented by the PP and their consultant. PP stated that this is a case of Murrum mining and no blasting is proposed. The EMP and other submissions made by the PP were found to be satisfactory and acceptable, hence committee decided to recommend the case for grant of prior EC subject to the following special conditions in addition to the standard conditions at annexure ‘A’:”

PP/Consultant made a presentation on all aspects of the project and all concerned issues were discussed in detail. After detailed discussions and perusal of recommendations of 464th SEAC meeting dated 03.10.2020, presentation made by the PP in SEIAA, it was decided to accept the recommendation of SEAC for grant of prior EC to the project subject to the following specific conditions:-

I. Before commencing any mining activity fencing shall be carried out all around the lease area. Proper watch and ward arrangements should be made with installation of signage at 4 corners of lease area to avoid any untoward incident involving public and animals by the PP.

II. PP shall not start mining activity before execution of lease agreement. III. The depth of the pit shall be as per the Approved Mining Plan. IV. The entire area shall be fenced and three rows of plantation should be done

on the periphery of the boundary. V. PP shall ensure that the proper water supply arrangements for dust

suppression, regular sprinkling, plantation and drinking purposes especially in summer season.

VI. PP shall ensure to construct and maintained the approach road. Plantation will be carried out on both side of approach road.

VII. PP shall ensure proper implementation of plantation, dust suppression, construction of approach road and maintenance of existing road & as part of Environmental Management Plan. Additional budget provision shall be made as part of EMP.

VIII. Total 2400 saplings of suitable tree species i.e. Neem, Pipal, Bargad, Mango, Amla, Amaltas, Drumstick etc. shall be planted by PP at mine lease boundary (1600 saplings) and 800 saplings at khasra no. 273/1 ( Private waste land) under plantation programme. PP shall also explore and identify the chunk of land in the area from revenue record to carry out plantation programme as proposed.

IX. PP must ensure implementation of the following activities with separate budget provision of Rs 1.50 lakh under CER.

CER activities at village Nowgaon Kala (1st to 5th Year)

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 135 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020

Construction of New Toilet at Village School – 60,000/- Providing Bench’s at Village Middle School (45 Nos) – Rs.90,000/-

PP shall ensure to contruct toilet with proper plumbing in the school of above village and contribute on behalf of village in Jal Jeewan Mission in consultation with Janpad Panchayat and PHED. PP shall give preference to develop/provide infrastructural facilities in schools or aganwadies of above villages The modification to the above activities can be made with the permission of the district administration and need based activity for the development of nearby villages shall be implemented by PP in consultation with the District Collector and Gram Panchayat

X. PP should ensure to submit half yearly compliance report and CSR activity report with photographs of plantation in MP-SEIAA. If PP is failed to upload or submit two consecutive half yearly compliance reports of EC conditions to concerned authority (SEIAA and Regional Office, MoEF&CC,GoI,Bhopal) than prior environmental clearance issued to PP will automatically be treated as cancelled/ revoked as per OM No. 930/SEIAA/2019 dated 30.05.2019 issued by MPSEIAA.

Hence, Prior Environmental Clearance is granted for Murrum Quarry (Opencast Manual / Semi Mechanized Method) in an area of 2.0 ha. for production capacity of 18900 cum / year ar Khasra No. 273/1 at Village - Nogawan Kala, Tehsil - Ratlam, Dist. Ratlam (MP) for the lease period to Shri Rajesh Jat S/o Shri Lalji Jat, Gram - Badoda, Tehsil & Dist. Ratlam, MP – 457222

60. Case No. 7847/20 Prior Environmental Clearance for Stone Quarry (opencast manual/semi mechanized method) in an area of 1.0 ha. (11995.20 cum per annum) (Khasra No. 81, 82/1/1, 83), Village - Baijnath, Tehsil - Huzur, Dist. - Rewa (MP) by M/s M.R. Stone Products & Mines, Partner, Shri Akram Siddiqui, R/o Ward No. 1, Nipaniya, Tehsil - Huzur, Dist. - Rewa, MP - 486001, EMail - [email protected], Mobile – 7389259443.

This case was recommended in 464th SEAC meeting dated 03.10.2020 and it was recorded that..........

“------------The case was presented by the PP and their consultant. PP stated that this is a case of stone mining. During presentation it was observed by committee that a kachha road is in existence on the western and southern side of the lease at a distance of 45 and 27 meters respectively. The EMP and other submissions made by the PP were found to be satisfactory and acceptable, hence committee decided to recommend the case for grant of prior EC subject to the following special conditions in addition to the standard conditions at annexure ‘A’:

PP/Consultant made a presentation on all aspects of the project and all concerned issues were discussed in detail. After detailed discussions and perusal of recommendations of 464th SEAC meeting dated 03.10.2020, presentation made by

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 136 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020

the PP in SEIAA, it was decided to accept the recommendation of SEAC for grant of prior EC to the project subject to the following specific conditions:-

i. Before commencing any mining activity fencing shall be carried out all around the lease area. Proper watch and ward arrangements should be made with installation of signage at 4 corners of lease area to avoid any untoward incident involving public and animals by the PP.

ii. PP shall not start mining activity before execution of lease agreement.

iii. The depth of the pit shall be as per the Approved Mining Plan.

iv. The entire area shall be fenced and three rows of plantation should be done on the periphery of the boundary.

v. PP shall ensure the proper water supply arrangements for dust suppression, regular sprinkling, plantation and drinking purposes especially in summer season.

vi. Total 1200 saplings of suitable tree species i.e. Neem, Pipal, Bargad, Mango, Gulmohar, Sissoo, Amla, Imli, etc. shall be planted by PP in first three years under plantation programme at mine lease boundary and at Govt. land khasra no. 10 Village – Baijnath in consultation with Gram Panchayat/ DM. PP shall also explore and identify the chunk of land in the area from revenue record to carry out plantation programme as proposed.

vii. PP shall ensure proper implementation of plantation, dust suppression, construction of approach road and maintenance of existing pakka road as part of Environmental Management Plan. Additional budget provision shall be made as part of EMP.

x. PP must ensure implementation of the following activities with separate budget provision of total Rs. 3.50 lakh under CER as committed:

a) Village – Baijnath: Distribution of mask, sanitizer (1st year). Preparation of grazing land (1st year) Construction of 2 rooms with White wash in swathya kendra

Baijnath. Contribution for Jal Jeewan Mission to janpad panchayat Baijnath.

PP shall ensure to contruct toilet with proper plumbing in the school of above village and contribute on behalf of village in Jal Jeewan Mission in consultation with Janpad Panchayat and PHED. PP shall give preference to develop/provide infrastructural facilities in schools or aanganwadies of above villages. The modification to the above activities can be made with the permission of the district administration and need based activity for the development of nearby villages shall be implemented by PP in consultation with the District Collector and Gram Panchayat.

viii. PP should ensure to submit half yearly compliance report, Plantation and CER activity report along with photographs of all activities in MP-SEIAA. If PP is failed to upload or submit two consecutive half yearly compliance reports of EC conditions to concerned authority (SEIAA and Regional Office,

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 137 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020

MoEF&CC,GoI,Bhopal) than prior environmental clearance issued to PP will automatically be treated as cancelled/ revoked as per OM No. 930/SEIAA/2019 dated 30.05.2019 issued by MPSEIAA.

Hence, Prior Environmental Clearance is granted for Stone Quarry (opencast manual/semi mechanized method) in an area of 1.0 ha. (11995.20 cum per annum) (Khasra No. 81, 82/1/1, 83), Village - Baijnath, Tehsil - Huzur, Dist. - Rewa (MP) for the lease period to M/s M.R. Stone Products & Mines, Partner, Shri Akram Siddiqui, R/o Ward No. 1, Nipaniya, Tehsil - Huzur, Dist. - Rewa, MP - 486001, EMail - [email protected], Mobile – 7389259443.

61. Case No. 7852/20 Prior Environmental Clearance for Stone Quarry (opencast manual/semi mechanized method) in an area of 1.80 ha. (20998 cum per annum) (Khasra No. 31/1, 35/1), Village - Jurtara, Tehsil - Seoni, Dist. - Seoni (MP) by Smt. Barkha Chouhan W/o Shri Narendra Chouhan, R/o Jurtara, PO - Banki, Tehsil & Dist. - Seoni, MP - 480661, Email - [email protected], Mobile – 9009804027.

This case was recommended in 464th SEAC meeting dated 03.10.2020 and it was recorded that..........

“------------The case was presented by the PP and their consultant. PP stated that this is a case of stone mining. During presentation it was observed by committee that a road is in existnace on the western side of the lease at a distance of approx. 50 meters. The EMP and other submissions made by the PP were found to be satisfactory and acceptable, hence committee decided to recommend the case for grant of prior EC subject to the following special conditions in addition to the standard conditions at annexure ‘A’:

PP/Consultant made a presentation on all aspects of the project and all concerned issues were discussed in detail. After detailed discussions and perusal of recommendations of 464th SEAC meeting dated 03.10.2020, presentation made by the PP in SEIAA, it was decided to accept the recommendation of SEAC for grant of prior EC to the project subject to the following specific conditions:-

i. Before commencing any mining activity fencing shall be carried out all around the lease area. Proper watch and ward arrangements should be made with installation of signage at 4 corners of lease area to avoid any untoward incident involving public and animals by the PP.

ii. PP shall not start mining activity before execution of lease agreement.

iii. The depth of the pit shall be as per the Approved Mining Plan.

iv. The entire area shall be fenced and three rows of plantation should be done on the periphery of the boundary.

v. PP shall ensure the proper water supply arrangements for dust suppression, regular sprinkling, plantation and drinking purposes especially in summer season.

vi. Total 2200 saplings of suitable tree species i.e. Neem, Pipal, Bargad, Mango, Gulmohar, Sissoo, Drumstick, Amaltas, etc. shall be planted by PP in first two years under plantation programme at khasra no. 45/1, 45/2, 46/1, 46/2 & 44/1 Govt land of Village - Bandol, Tehsil & District -Seoni in consultation with Gram Panchayat/ DM. PP shall also explore and identify

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 138 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020

the chunk of land in the area from revenue record to carry out plantation programme as proposed.

i. PP shall ensure proper implementation of plantation, dust suppression, construction of approach road and maintenance of existing pakka road as part of Environmental Management Plan. Additional budget provision shall be made as part of EMP.

ii. PP must ensure implementation of the following activities with separate budget provision of total Rs. 1.20 lakh under CER as committed:

a) 1st Year: Distribution of Masks and sanitizers to villagers and to conduct an

awareness program through Panchayat for protection from the spread of Corona Virus ( COVID 19 Pandemic)

Swing and slides for Govt. Primary school of Banki Village Development of grazing land

b) 2nd Year:

Repairing and whitewash of Gram Panchayat Bhawan, Village Nandani.

c) 3rd Year:

Construction of boundary wall for Govt. School of Jamuniya Village.

d) 4th Year: Repairing and whitewash of Anganwadi, Village Jurtara.

e) 5th Year: To provide Water Filter with overhead water tank at Village School of

Bakodi.

PP shall ensure to contruct toilet with proper plumbing in the school of above village and contribute on behalf of village in Jal Jeewan Mission in consultation with Janpad Panchayat and PHED. PP shall give preference to develop/provide infrastructural facilities in schools or aanganwadies of above villages. The modification to the above activities can be made with the permission of the district administration and need based activity for the development of nearby villages shall be implemented by PP in consultation with the District Collector and Gram Panchayat.

iii. PP should ensure to submit half yearly compliance report, Plantation and CER activity report along with photographs of all activities in MP-SEIAA. If PP is failed to upload or submit two consecutive half yearly compliance reports of EC conditions to concerned authority (SEIAA and Regional Office, MoEF&CC,GoI,Bhopal) than prior environmental clearance issued to PP will automatically be treated as cancelled/ revoked as per OM No. 930/SEIAA/2019 dated 30.05.2019 issued by MPSEIAA.

Hence, Prior Environmental Clearance is granted for (opencast manual/semi mechanized method) in an area of 1.80 ha. (20998 cum per annum) (Khasra No. 31/1, 35/1), Village - Jurtara, Tehsil - Seoni, Dist. - Seoni (MP) for the lease

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 139 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020

period to Smt. Barkha Chouhan W/o Shri Narendra Chouhan, R/o Jurtara, PO - Banki, Tehsil & Dist. - Seoni, MP - 480661, Email - [email protected], Mobile – 9009804027.

62. Case No. 7854/20 Prior Environmental Clearance for Stone Quarry (opencast manual/semi mechanized method) in an area of 1.60 ha. (8970 cum per annum) (Khasra No. 38), Village - Rahangi Mal, Tehsil - Dindori, Dist. - Dindori (MP) by Shri Tulsiram Rajput S/o Shri Tek Singh, Village - Chhanta, Tehsil & Dist. - Dindori, MP - 481880, EMail - [email protected], Mobile – 7354217702.

This case was recommended in 464th SEAC meeting dated 03.10.2020 and it was recorded that..........

“------------The case was presented by the PP and their consultant. PP stated that this is a case of stone mining. During presentation it was observed by committee that a river is in existance on the western side of the lease at a distance of 60 meters. PP was asked to submit proposal for 2000 plantation which was submitted by PP instantly. The EMP and other submissions made by the PP were found to be satisfactory and acceptable, hence committee decided to recommend the case for grant of prior EC subject to the following special conditions in addition to the standard conditions at annexure ‘A’:

PP/Consultant made a presentation on all aspects of the project and all concerned issues were discussed in detail. After detailed discussions and perusal of recommendations of 464th SEAC meeting dated 03.10.2020, presentation made by the PP in SEIAA, it was decided to accept the recommendation of SEAC for grant of prior EC to the project subject to the following specific conditions:-

i. Before commencing any mining activity fencing shall be carried out all around the lease area. Proper watch and ward arrangements should be made with installation of signage at 4 corners of lease area to avoid any untoward incident involving public and animals by the PP.

ii. PP shall not start mining activity before execution of lease agreement.

iii. The depth of the pit shall be as per the Approved Mining Plan.

iv. The entire area shall be fenced and three rows of plantation should be done on the periphery of the boundary.

v. PP shall ensure the proper water supply arrangements for dust suppression, regular sprinkling, plantation and drinking purposes especially in summer season.

vi. PP shall leave set back of 50 m from the natural drain as no mining zone and raise plantation in this area.

vii. Total 2000 saplings of suitable tree species i.e. Neem, Pipal, Bargad, Mango, Gulmohar, Sissoo, Amaltas, Guava, etc. shall be planted by PP in first three years under plantation programme at mine lease boundary khasra no. 38 in consultation with Gram Panchayat/ DM. PP shall also explore and identify the chunk of land in the area from revenue record to carry out plantation programme as proposed.

viii. PP shall ensure proper implementation of plantation, dust suppression, construction of approach road and maintenance of existing pakka road as

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 140 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020

part of Environmental Management Plan. Additional budget provision shall be made as part of EMP.

ix. PP must ensure implementation of the following activities with separate budget provision of total Rs. 60,000/- under CER as committed:

a) To provide Separate toilets for girls & boys for primary school Rahangi Mal.

PP shall ensure to contruct toilet with proper plumbing in the school of above village and contribute on behalf of village in Jal Jeewan Mission in consultation with Janpad Panchayat and PHED. PP shall give preference to develop/provide infrastructural facilities in schools or aanganwadies of above villages. The modification to the above activities can be made with the permission of the district administration and need based activity for the development of nearby villages shall be implemented by PP in consultation with the District Collector and Gram Panchayat.

x. PP should ensure to submit half yearly compliance report, Plantation and CER activity report along with photographs of all activities in MP-SEIAA. If PP is failed to upload or submit two consecutive half yearly compliance reports of EC conditions to concerned authority (SEIAA and Regional Office, MoEF&CC,GoI,Bhopal) than prior environmental clearance issued to PP will automatically be treated as cancelled/ revoked as per OM No. 930/SEIAA/2019 dated 30.05.2019 issued by MPSEIAA.

Hence, Prior Environmental Clearance is granted for Stone Quarry (opencast manual/semi mechanized method) in an area of 1.60 ha. (8970 cum per annum) (Khasra No. 38), Village - Rahangi Mal, Tehsil - Dindori, Dist. - Dindori (MP) for the lease period to Shri Tulsiram Rajput S/o Shri Tek Singh, Village - Chhanta, Tehsil & Dist. - Dindori, MP - 481880, EMail - [email protected], Mobile – 7354217702.

63. Case No. 7855/2020 : Prior Environment Clearance for propsed project Manufacturing of Bulk Drug & API at Plot No.17-B, 18-ASector F, Industrial Area, Sanwer Road, Indore Madhya Pradesh ,452015 Land area – 16 Acres. Production Capacity: 823 TPA by M/s SUDARSHAN PHARMACEUTICALS PVT. LTD through Owner Kusum Randhar, 17-B, 18-ASector F, Industrial Area, Sanwer Road, Indore MP- 452015 Email [email protected] Mob :-09425062717

The case was considered in SEAC 464 meeting dtd. 03.10. 2020 and recorded that :-

“This is case of Prior Environment Clearance for Bulk Drug & API Unit at 17B, 18-A, Sanwer Road, Indore, (MP).

The case was scheduled for presentation but neither the Project Proponent (PP) nor his representative was present to explain the query which might be raised or to make any commitment which may be desired by the committee during the deliberation. From the above it is clear that PP is not interested to continue with the project. Since the tenure of SEAC will be over on 09 October, 2020 and all such cases which are

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 141 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020

pending at SEAC will become category-I cases in the absence of SEAC. Thus case file is being sent to SEIAA for onward necessary action please”.

In context of above it has been decided to delist the case from MPSEIAA on the basis of the tenure of SEIAA will be over on 09 October, 2020 as per EIA Notification 2006 & its ammendment ” In the absence of a duly constituted SEIAA or SEAC, a Category ‘B’ project shall be treated as a Category ‘A’ project; Copy to PP and all concerned.

64. Case No. 5763/18 Prior Environmental Clearance for Expansion in Laterite & Ocher mine (opencast semi mechanized method without blasting) in an area of 15.00 ha, for total production capacity of Laterite 1,20,000 Ton and Ocher 20,013 Ton at khasra no. 339/543 at Village - Budhanwara, Tehsil – Bahoribandh, District - Katni (MP) by Shri Neeraj Kumar Jain, R/o Sawarkar Ward, Nai Basti, Katni, District - Katni (MP) - 483501.

(1) This is a project pertaining to mining of Laterite & Ocher Mine in MLA of 15.00 ha. The activity is mentioned at S.No. 1 (a) of the Schedule of EIA Notification 2006 as amended from time to time. The project is reported to be at a distance of more than 10 km from National Park /Sanctuary/Biodiversity etc. thus it is not attracted by the general conditions and falls under category ‘B-1” by virtue of its location and mining lease area. There is no forest boundary in less than 250 m distance from the ML area. The case was forwarded by SEIAA to SEAC for appraisal of EIA for environmental clearance for the project. It was submitted that the mine is an existing mine having valid lease period upto 02.08.2060.

(2) The mining lease was granted to Mr. Neeraj Kumar Jain by State Govt. vide order no. 3-40/2007/12/2 Bhopal dated 23.02.2010 for 20 years i.e. from 03.08.2010 to 02.08.2030 which has been extended for 50 years i.e. 02.08.2060 as per the Mines & Minerals (Development & Regulation) Amendment Ordinance 2015 and the State Govt. of M.P. circular No. F-19-5/2015/12-1 dtd. 12.03.2015. The scheme of mining has been approved by DGM, Bhopal Vide Letter No. - 2262-63/Mining Plan Cell-10/Na.Kra. 14/2018 dated 17.02.2020.

(3) PP has produced an order of the Mineral Resources Deptt. GoMP dtd. 03.09.2015 in which after hearing the case the State Govt. has established that action be taken according to the latest circular No. F-19-5/2015/12-1 dtd. 12.03.2015, which states that “all mining leases granted before the commencement of the Mines & Minerals (Development & Regulation) Amendment Ordinance 2015 shall be deemed to have been granted for a period of fifty years”.

(4) SEAC in its 464th meeting dated 03.10.2020 has recommended the case with 32 special conditions for issuance of EC.

(5) It was noted that as per DFO L.No. 6218 Katni, dtd. 27.09.2013, the National Park/Sanctuary/Biodiversity area is not located within 10 Km. radius from the mining site. Hence, the General Conditions are not attracted. There is no forest boundary in less than 250 m distance from the ML area.

(6) PP/Consultant made a presentation on all aspects of the project and all concerned issues were discussed in detail.

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 142 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020

(7) It was noted that the water requirement is 8.0 KLD (2.0 KLD for Drinking Purpose + 3.0 KLD for Dust Suppression + 3.0 KLD for Plantation) which shall be meet through hired tankers.

(8) The proposed plantation programme was examined and it was found that 8000 saplings shall be covered under plantation program.

(9) Earlier prior Environmental Clearance was granted by MPSEIAA Case No. (659/2011) Letter No. 1164/SEIAA/14 dtd 27.09.2014

(10) PP has now applied for Prior Environmental Clearance for expansion in production capacity for total production capacity of Laterite 1,20,000 Ton and Ocher 20,013 Ton.

(11) PP has submitted compliance report of earlier prior EC certified by MoEF &CC Regional Office, Bhopal (vide letter no. 18 B – 10/2019/SEIAA/ (ENV)/ 743 dtd. 04.07.2019). As per the report the implementation of environmental safeguards are found satisfactory and some compliance needs improvement which are in progress and has been advised to take care for conditions like environmental management, green belt development, OB and Soil management also the submission and uploading of data and six monthly compliance reports as per stipulations. It is decided that PP should ensure the implementation of the observations of MOEF & CC RO, Bhopal report dtd 04.07.2019.

(12) It was also noted that the Public Hearing was carried out on 16.10.2019 at Mine Parisar Village - Budhanwara, Tehsil – Bahoribandh, District - Katni (MP) under the Chairmanship of Collector, Katni. The major comments of applicants during public hearing are employment of local people, OB management, construction & maintenance of existing / approach road connecting the mine & main road, grazing land development, water sprinkling to suppress the dust emission etc.

After detailed discussions and perusal of recommendations of 464th SEAC meeting dated 03.10.2020, it was decided to accept the recommendation of SEAC for grant of prior EC to the project subject to the following specific conditions:-

I. Before commencing any mining activity fencing shall be carried out all around the lease area. Proper watch and ward arrangements should be made with installation of signage at 4 corners of lease area to avoid any untoward incident involving public and animals by the PP.

II. Lease agreement shall be carried out before execution of mining operation.

III. Plantation programme as mentioned in EIA/EMP and presented during presentation in SEIAA & SEAC shall be followed in content and spirit.

IV. PP shall demarcate a barrier zone of 7.5 m as no mining zone in the periphery of mining lease area and develop a green belt. Three rows plantation shall be carried out in the greenbelt area in current year with proper watering arrangement.

V. Total 8000 saplings of suitable tree species i.e. Neem, Pipal, Bargad, Mango, Gulmohar, Sissoo, Drumstick, Amaltas, Amla, Ashok etc. shall be

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 143 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020

planted by PP under plantation programme at lease periphery, reclaimed area, undisturbed area, buffer zone etc. and at Govt. land khasra no. 339/543 as suggested by BDO/ Village Panchayat. PP shall also explore and identify the chunk of land in the area from revenue record to carry out plantation programme as proposed.

VI. The mining operation shall be restricted to above ground water table and in no case it should intersect the ground water table. In case of working below the ground water table, approval of the Central Ground Water Board shall be obtained.

VII. The overburden and waste will be stacked for five years and simultaneously backfilled in the mined out area where plantation will be raised on it.

VIII. No overburden will be dumped outside the mine lease area.

IX. PP shall leave set back of 50 m from the canal towards northern side of lease area as no mining zone and raise plantation in this area.

X. Regular water quality monitoring shall be carried out by PP before discharging it into the nearby agriculture fields from authorized laboratory in consultation with Regional Officer, MPPCB. Regular air and noise quality monitoring shall also be carried out by PP from authorized laboratory in consultation with Regional Officer, MPPCB.

XI. PP shall ensure the generation of employment opportunities nearby Village on priority basis.

XII. Payments of wages to the workers shall be done in consonance with the provisions in the labour laws.

XIII. Proper infrastructure with shelter, drinking water, toilet and first-aid facilities shall be provided for the laborers. A provision should be made to construct a pakka rest shelter along with toilet and drinking water facility.

XIV. PP should also carry out regular sprinkling in the mining lease area to arrest dust emission from mining activities affecting the nearby agriculture fields.

XV. Mining shall be limited to the area as shown in surface plan and as per the approved mining scheme.

XVI. PP shall ensure the proper water supply arrangements for plantation especially in summer season.

XVII. PP shall ensure proper implementation of plantation, dust suppression, construction of approach road and maintenance of existing pakka road as part of Environmental Management Plan. Additional budget provision shall be made as part of EMP.

XVIII. PP must ensure implementation of the following activities with separate budget provision of Rs. 3.00 Lakhs/year under CER as committed:

a) 1st Year:

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 144 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020

Construction of medium size community hall with toilet in consultation with Panchayat, near to Bachaiya Panchayat Office.

b) 2nd Year:

Repairing & Maintenance of boundary wall & colouring of school building at Govt. Higher Senior Secondary School of village Budhanwara & construction of dining room within premise.

c) 3rd Year:

Upliftment of women skills of nearby villages by distributing Sewing Machines and contribution of indoor game facilities at aanganwadi kendra of nearby villages i.e. Budhanwara, Nayagaon & Somkhund & Bachaya.

Blankets & Seed distributation of needy peoples of nearby villages.

PP shall ensure to contruct toilet with proper plumbing in the school of above village and contribute on behalf of village in Jal Jeewan Mission in consultation with Janpad Panchayat and PHED. PP shall give preference to develop/provide infrastructural facilities in schools or aanganwadies of above villages. The modification to the above activities can be made with the permission of the district administration and need based activity for the development of nearby villages shall be implemented by PP in consultation with the District Collector and Gram Panchayat.

XIX. PP should ensure to submit half yearly compliance report, Plantation and CER activity report along with photographs of all activities in MP-SEIAA. If PP is failed to upload or submit two consecutive half yearly compliance reports of EC conditions to concerned authority (SEIAA and Regional Office, MoEF&CC,GoI,Bhopal) than prior environmental clearance issued to PP will automatically be treated as cancelled/ revoked as per OM No. 930/SEIAA/2019 dated 30.05.2019 issued by MPSEIAA.

Hence, Prior Environmental Clearance is granted for Expansion in Laterite & Ocher mine (opencast semi mechanized method without blasting) in an area of 15.00 ha, for total production capacity of Laterite 1,20,000 Ton and Ocher 20,013 Ton at khasra no. 339/543 at Village - Budhanwara, Tehsil – Bahoribandh, District - Katni (MP) for the lease period to Shri Neeraj Kumar Jain, R/o Sawarkar Ward, Nai Basti, Katni, District - Katni (MP) - 483501.

65. Case No. 5764/18 Prior Environmental Clearance for Fireclay Mine (opencast semi mechanized method) in an area of 7.441 ha. (as per lease agreement) for production capacity of 10,485 TPA at khasra no. 483/1 at Village - Chilachond, Tehsil - Narsinghpur, District - Narsinghpur (MP) by Shri Virendra Singh Patel, Village - Chilachond, Tehsil - Narsinghpur, District - Narsinghpur (MP) - 487001.

(1) This is a project pertaining to mining of Fireclay Mine in MLA of 7.441 ha. The activity is mentioned at S.No. 1 (a) of the Schedule of EIA Notification 2006 as

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 145 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020

amended from time to time. The project is reported to be at a distance of more than 10 km from National Park /Sanctuary/Biosphere Reserve etc. thus it is not attracted by the general conditions and falls under category ‘B-1” by virtue of its location and mining lease area. There is no forest boundary in less than 250 m distance from the ML area. The case was forwarded by SEIAA to SEAC for appraisal of EIA for environmental clearance for the project. It was submitted that this is an existing mine having valid lease period upto 14.01.2047.

(2) The mining lease was first granted to Shri Virendra Singh Patel vide Govt. letter no. 3-49/96/12/2 dated 21.08.1996 for 20 years i.e. from 15.01.1997 to 14.01.2017 which has been extended for 50 years i.e. 14.01.2047 as per the Mines & Minerals (Development & Regulation) Amendment Ordinance 2015 and the State Govt. of M.P. circular No. F-19-5/2015/12-1 dtd. 12.03.2015. The Scheme of Mining has been approved by DGM, Bhopal Vide Letter No. – 10877-78/Mining Plan Cell-2/Na.Kra. 87/2018 dated 28.06.2018.

(3) PP has produced an order of the Mineral Resources Deptt. GoMP dtd. 03.09.2015 in which after hearing the case the State Govt. has established that action be taken according to the latest circular No. F-19-5/2015/12-1 dtd. 12.03.2015, which states that “all mining leases granted before the commencement of the Mines & Minerals (Development & Regulation) Amendment Ordinance 2015 shall be deemed to have been granted for a period of fifty years”.

(4) SEAC in its 464th meeting dated 03.10.2020 has recommended the case with 31 special conditions for issuance of EC.

(5) It was noted that as per DFO L.No. 7685 Narsinghpur, dtd. 23.12.2015, the National Park/Sanctuary/Eco Sensitive Zone is not located within 10 Km. radius from the mining site. Hence, the General Conditions are not attracted. There is no forest boundary in less than 250 m distance from the ML area.

(6) PP/Consultant made a presentation on all aspects of the project and all concerned issues were discussed in detail.

(7) It was noted that the water requirement is 4.0 KLD (2.0 KLD for Drinking Purpose + 1.0 KLD for Dust Suppression + 1.0 KLD for Plantation which shall be meet through tired tankers.

(8) The proposed plantation programme was examined and it was found that 4000 saplings shall be covered under plantation program.

(9) It was also noted that the Public Hearing was carried out on 08.11.2019 at Mine Parisar Village - Chilachond, Tehsil - Narsinghpur, District - Narsinghpur (MP) under the Chairmanship of ADM, Narsinghpur.

After detailed discussions and perusal of recommendations of 464th SEAC meeting dated 03.10.2020, it was decided to accept the recommendation of SEAC for grant of prior EC to the project subject to the following specific conditions:-

I. Before commencing any mining activity fencing shall be carried out all around the lease area. Proper watch and ward arrangements should be

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 146 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020

made with installation of signage at 4 corners of lease area to avoid any untoward incident involving public and animals by the PP.

II. Lease agreement shall be carried out before execution of mining operation.

III. Plantation programme as mentioned in EIA/EMP and presented during presentation in SEIAA & SEAC shall be followed in content and spirit.

IV. PP shall demarcate a barrier zone of 7.5 m as no mining zone in the periphery of mining lease area and develop a green belt. Three rows plantation shall be carried out in the greenbelt area in current year with proper watering arrangement.

V. Total 4000 saplings of suitable tree species i.e. Neem, Pipal, Bargad, Mango, Gulmohar, Sissoo, Drumstick, Amaltas, Amla, Ashok etc. shall be planted by PP under plantation programme at lease periphery, reclaimed area, undisturbed area, buffer zone etc. and at Govt. land khasra no. 483/1 as suggested by BDO/ Village Panchayat. PP shall also explore and identify the chunk of land in the area from revenue record to carry out plantation programme as proposed.

VI. The mining operation shall be restricted to above ground water table and in no case it should intersect the ground water table. In case of working below the ground water table, approval of the Central Ground Water Board shall be obtained.

VII. The overburden and waste will be stacked for five years and simultaneously backfilled in the mined out area where plantation will be raised on it.

VIII. No overburden will be dumped outside the mine lease area.

IX. Regular water quality monitoring shall be carried out by PP before discharging it into the nearby agriculture fields from authorized laboratory in consultation with Regional Officer, MPPCB. Regular air and noise quality monitoring shall also be carried out at by PP from authorized laboratory in consultation with Regional Officer, MPPCB.

X. PP shall ensure the generation of employment opportunities nearby Village on priority basis.

XI. Payments of wages to the workers shall be done in consonance with the provisions in the labour laws.

XII. Proper infrastructure with shelter, drinking water, toilet and first-aid facilities shall be provided for the laborers. A provision should be made to construct a pakka rest shelter along with toilet and drinking water facility.

XIII. PP should also carry out regular sprinkling in the mining lease area to arrest dust emission from mining activities affecting the nearby agriculture fields.

XIV. Mining shall be limited to the area as shown in surface plan and as per the approved mining scheme.

XV. PP shall ensure the proper water supply arrangements for plantation especially in summer season.

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 147 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020

XVI. PP shall ensure proper implementation of plantation, dust suppression, construction of approach road and maintenance of existing pakka road as part of Environmental Management Plan. Additional budget provision shall be made as part of EMP.

XVII. PP must ensure implementation of the following activities with separate budget provision of Rs. 1.00 Lakhs/year under CER as committed:

a) 1st Year: Construction of medium size community hall with toilet in

consultation with Panchayat near to Chilachond Panchayat Office.

b) 2nd Year: Construction of boundary wall around Chilachond Panchayat

premise. c) 3rd Year:

Construction of kitchen in middle school premise of Badgawn. d) 4th Year:

Construction of kitchen in middle school premise of Badgawn & Other related aminities

e) 5th Year: Boundary wall white wash & repairing at Jharkuba high school.

PP shall ensure to contruct toilet with proper plumbing in the school of above village and contribute on behalf of village in Jal Jeewan Mission in consultation with Janpad Panchayat and PHED. PP shall give preference to develop/provide infrastructural facilities in schools or aanganwadies of above villages. The modification to the above activities can be made with the permission of the district administration and need based activity for the development of nearby villages shall be implemented by PP in consultation with the District Collector and Gram Panchayat.

XVIII. PP should ensure to submit half yearly compliance report, Plantation and CER activity report along with photographs of all activities in MP-SEIAA. If PP is failed to upload or submit two consecutive half yearly compliance reports of EC conditions to concerned authority (SEIAA and Regional Office, MoEF&CC,GoI,Bhopal) than prior environmental clearance issued to PP will automatically be treated as cancelled/ revoked as per OM No. 930/SEIAA/2019 dated 30.05.2019 issued by MPSEIAA.

Hence, Prior Environmental Clearance is granted for Fireclay Mine (opencast semi mechanized method) in an area of 7.441 ha. (as per lease agreement) for production capacity of 10,485 TPA at khasra no. 483/1 at Village - Chilachond, Tehsil - Narsinghpur, District - Narsinghpur (MP) for the lease period to Shri Virendra Singh Patel, Village - Chilachond, Tehsil - Narsinghpur, District - Narsinghpur (MP) - 487001.

66. Case No 7858/2020 Prior Environmental Clearance for Stone Quarry (Opencast Manual / Semi Mechanized Method) in an area of 4.0 ha. for production capacity of 45671 cum / year at Khasra No. 315 at Village - Pathari, Tehsil - Orchha, Dist.

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 148 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020

Niwari (MP) by Shri Subhash Chandra Omhare S/o Ramprasad Omhare, Village - 648/32/A, CIvil Lines, Dist. Jhansi, UP

This case was recommended in 464th SEAC meeting dated 03.10.2020 and it was recorded that..........

“…………The case was presented by the PP and their consultant. PP stated that this is a case of stone mining. During presentation it was observed by committee that orcha Abhayaran is 8.00 kms away from the lease but PP was unable to explain the distance of notified ESZ thus was asked to provide copy of notification. PP was also asked to submit proposal for 4800 plantation which was submitted by PP on dated 03/10/2020. The EMP and other submissions made by the PP were found to be satisfactory and acceptable, hence committee decided to recommend the case for grant of prior EC subject to the following special conditions in addition to the standard conditions at annexure ‘A’:”

PP/Consultant made a presentation on all aspects of the project and all concerned issues were discussed in detail. After detailed discussions and perusal of recommendations of 464th SEAC meeting dated 03.10.2020, presentation made by the PP in SEIAA, it was decided to accept the recommendation of SEAC for grant of prior EC to the project subject to the following specific conditions:-

I. Before commencing any mining activity fencing shall be carried out all around the lease area. Proper watch and ward arrangements should be made with installation of signage at 4 corners of lease area to avoid any untoward incident involving public and animals by the PP.

II. PP shall not start mining activity before execution of lease agreement. III. The depth of the pit shall be as per the Approved Mining Plan. IV. The entire area shall be fenced and three rows of plantation should be done

on the periphery of the boundary. V. PP shall ensure that the proper water supply arrangements for dust

suppression, regular sprinkling, plantation and drinking purposes especially in summer season.

VI. PP shall ensure to construct and maintained the approach road. Plantation will be carried out on both side of approach road.

VII. PP shall ensure proper implementation of plantation, dust suppression, construction of approach road and maintenance of existing road & as part of Environmental Management Plan. Additional budget provision shall be made as part of EMP.

VIII. Total 2500 saplings of suitable tree species i.e. Neem, Pipal, Bargad, Mango, Amla, Amaltas, Drumstick etc. shall be planted by PP at Mine Lease Boundary & Govt.Land suggested by BDO/village .panchayt Khasra no 315 under plantation programme. PP shall also explore and identify the chunk of land in the area from revenue record to carry out plantation programme as proposed.

IX. PP must ensure implementation of the following activities with separate budget provision of Rs 1.50 lakh/ year under CER. To provide Separate toilets for girls & boys for primary school Pathari 01

dining room for primary schools boundary wall repairing, coloring,

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 149 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020

maintenance Other suggestion from village head will also be included for future planning.

CER activities in following villages 1st

Year – Pathari, 2nd

Year – Pathari, 3rd

Year – Pathari, 4th

Year – Lathesara, 5th

Year - Lathesara PP shall ensure to contruct toilet with proper plumbing in the school of above village and contribute on behalf of village in Jal Jeewan Mission in consultation with Janpad Panchayat and PHED. PP shall give preference to develop/provide infrastructural facilities in schools or aganwadies of above villages The modification to the above activities can be made with the permission of the district administration and need based activity for the development of nearby villages shall be implemented by PP in consultation with the District Collector and Gram Panchayat

X. PP should ensure to submit half yearly compliance report and CSR activity report with photographs of plantation in MP-SEIAA. If PP is failed to upload or submit two consecutive half yearly compliance reports of EC conditions to concerned authority (SEIAA and Regional Office, MoEF&CC,GoI,Bhopal) than prior environmental clearance issued to PP will automatically be treated as cancelled/ revoked as per OM No. 930/SEIAA/2019 dated 30.05.2019 issued by MPSEIAA.

Hence, Prior Environmental Clearance is granted for Stone Quarry (Opencast Manual / Semi Mechanized Method) in an area of 4.0 ha. for production capacity of 45671 cum / year at Khasra No. 315 at Village - Pathari, Tehsil - Orchha, Dist. Niwari (MP) for the lease period to Shri Subhash Chandra Omhare S/o Ramprasad Omhare, Village - 648/32/A, CIvil Lines, Dist. Jhansi, UP

67. Case No. – 6168/2019 Prior Environmental Clearance for Limestone Mine (Opencast Manual / Semi Mechanized Method) in an area of 4.90 ha. for production capacity of 57,475 TPA at khasra no.Khasra No. 1 at Village - Balwarikalan, Tehsil - Gandhawani, Dist. Dhar, MP. (MP) by Shri Sanjay Khandelwal, Dhar Road, Manawar, Dist. Dhar, MP -45446.

(1) This is a project pertaining to mining of Limestone mine in MLA of 4.90 ha. The activity is mentioned at S.No. 1 (a) of the Schedule of EIA Notification 2006 as amended from time to time. The project is reported to be at a distance of more than 10 km from National Park /Sanctuary etc. thus it is not attracted by the general conditions and falls under category ‘B-1” by virtue of its location and mining lease area. The case was forwarded by SEIAA to SEAC for appraisal of EIA for environment clearance for the project. It was submitted that this is a proposed mine with production capacity of Limestone is 57,475 TPA.

(2) SEAC in its 464 SEAC meeting dtd 03.10.2020 has recommended the case with 33 special conditions for issuance of EC.

(3) It was noted that as per Forest Conservator .L.No. 4900, dtd. 18.10.2017, the National Park/Sanctuary is not located within 10 Km., radius from the mining

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 150 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020

site. Hence, the General Conditions are not attracted. There is no forest boundary within 250 m from mining site.

(4) It was noted that the water requirement is 5 KLD (2.5 KLD Dust Suppression +1.75 KLD Green Belt + 0.75 KLD Domestic purpose) which shall be met from Water tankers.

(5) The proposed plantation program was examined and it was found that total 6000 sapling shall be covered under plantation

(6) It was also noted that the Public Hearing was carried out on 26.09.2020 at nearby Mine Parisar Village - Balwarikalan, Tehsil - Gandhawani, Dist. Dhar, MP.under Chairmanship of Upper Collector, Dhar. The major comments of applicants during public hearing are are water for irrigation, access on approach road, Controlled blasting, employment of local people, construction & maintenance of existing / approach road connecting the mine & main road, Plantation on road side, regular health check-up of mine workers & water sprinkling to suppress the dust emission.

PP/Consultant made a presentation on all aspects of the project and all concerned issues were discussed in detail After detailed discussions and perusal of recommendations of 464 SEAC meeting dtd 03.10.2020, it was decided to accept the recommendation of SEAC for grant of prior EC to the project subject to the following specific conditions:

I. PP shall ensure to preserve thick greenery all around periphery of mining lease area and develop a green belt.

II. Before commencing any mining activity fencing shall be carried out all around the lease area. Proper watch and ward arrangements should be made with installation of signage at 4 corners of lease area to avoid any untoward incident involving public and animals by the PP.

III. Plantation programme as mentioned in EIA/EMP and presented during presentation in SEIAA & SEAC shall be followed in content and spirit.

IV. Total 6000 saplings of suitable tree species i.e. Neem, Pipal, Bargad, Mango, Amla, Amaltas, Drumstick etc. shall be planted by PP on priority Mine lease boundary , In khasra no. 1 part, Approach Road& village road, Both the side by of road connecting the Hanuman temple and Dribbling of Prosopis seed in trench soil of excavated garland drain submit photographs of the plantation in SEIAA.PP shall also explore and identify the chunk of land in the area from revenue record to carry out plantation programme as proposed

V. All garland drains shall be connected to settling tanks through settling pits and settled water shall be used for dust suppression, green belt development. Regular de-silting of drains and pits should be carried out

VI. PP shall demarcate a barrier zone of 7.5 m as no mining zone in the periphery of mining lease area and develop a green belt. Three row plantation shall be carried out in the greenbelt area in current year with proper watering arrangement.

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 151 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020

VII. The mining operation shall be restricted to above ground water table and in no case it should intersect the ground water table. In case of working below the ground water table approval of the Central Ground Water Board shall be obtained.

VIII. The over burden and waste will be stacked for five years and then simultaneously backfilled in the mined out area where plantation will be raised on it.

IX. No overburden will be dumped outside the mine lease area.

X. PP shall leave set back of 50 m from road as no mining zone and raise plantation in this area.

XI. Regular air & water quality monitoring shall be carried out by PP before discharging it into the nearby agriculture fields from authorized laboratory in consultation with Regional Officer, MPPCB.

XII. PP shall ensure generation of employment opportunities to nearby Village on priority bases.

XIII. Payments of wages to the workers shall be done in consonance with the provisions in the labour laws.

XIV. Proper infrastructure with shelter, drinking water, toilet and first-aid facilities shall be provided for the laborers. A provision should be made to construct a pakka rest shelter along with toilet and drinking water facility.

XV. PP should also carry out regular sprinkling of water in the mining lease area to arrest dust emission from mining activities affecting the nearby agriculture fields

XVI. Mining shall be limited to the area as shown in surface plan and as per the approved mining scheme.

XVII. PP shall ensure to construct and maintain approach road from the mine site. Plantation will be carried out on both sides of the approach road. PP shall also ensure maintenance of existing pakka road in consultation with competent authority.

XVIII. PP shall ensure proper water supply arrangements for plantation especially in summer season.

XIX. PP shall ensure proper implementation of plantation, dust suppression, construction of approach road and maintenance of existing pakka road as part of Environmental Management Plan. Additional budget provision shall be made as part of EMP.

XX. PP must ensure implementation of the following activities with separate budget provision of Rs. 5.0 Lakhs under CER as committed.

1st to 4th year

Distribution of hand sanitizer, mask, gloves etc. in village due to COVID -19. for village Bhutiyapura and Balwarikalan. (Rs. 0.20 lakh)

Development of grazing land in Balwari Kalan (Rs. 0.10 lakh)

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 152 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020

Contribution in construction shed at chauraha of village Balwari. (Rs. 1.10 lakh)

Construction of building for Hanumaan temple at village Balwarikalan (Rs. 4.20 lakh)

5th year

Contribution in construction of boundary wall of primary School, Balwarikalan (Rs. 1.40 lakh)

PP shall ensure to contruct toilet with proper plumbing in the school of above village and contribute on behalf of village in Jal Jeewan Mission in consultation with Janpad Panchayat and PHED. PP shall give preference to develop/provide infrastructural facilities in schools or aganwadies of above villages The modification to the above activities can be made with the permission of the district administration and need based activity for the development of nearby villages shall be implemented by PP in consultation with the District Collector and Gram Panchayat

XXI. PP should ensure to submit half yearly compliance report and CSR activity report with photographs of plantation in MP-SEIAA. If PP is failed to upload or submit two consecutive half yearly compliance reports of EC conditions to concerned authority (SEIAA and Regional Office, MoEF&CC,GoI,Bhopal) than prior environmental clearance issued to PP will automatically be treated as cancelled/ revoked as per OM No. 930/SEIAA/2019 dated 30.05.2019 issued by MPSEIAA.

Hence, Prior Environmental Clearance is granted for Limestone Mine (Opencast Manual / Semi Mechanized Method) in an area of 4.90 ha. for production capacity of 57,475 TPA at khasra no.Khasra No. 1 at Village - Balwarikalan, Tehsil - Gandhawani, Dist. Dhar, MP. (MP) for the lease period to Shri Sanjay Khandelwal, Dhar Road, Manawar, Dist. Dhar, MP -45446.

68. Case No 6749/2020 Prior Environmental Clearance for Laterite Deposit (Opencast Manual / Semi Mechanized Method) in an area of 17.010 ha. for production capacity of 40,320 cum/ year at Khasra No. 153, 154, 158 at Village - Tarawali, Tehsil - Suwasara, Dist. Mandsaur by M/s Harshwardhan Industries Pvt. Ltd, B-64, Shaligram Tower, Near Sharon Park, Satellite Road, Dist. Ahmedabad, Gujarat

1. This is a project pertaining to mining of Laterite Deposit in MLA of 17.010 ha The activity is mentioned at S.No. 1 (a) of the Schedule of EIA Notification 2006 as amended from time to time. The project is reported to be at a distance of more than 10 km from National park and sanctuary etc. thus it is not attracted by the general conditions and considered under category ‘B-1” by virtue of its location and mining lease area. The case was forwarded by SEIAA to SEAC for appraisal of EIA for environment clearance for the project. It was submitted that this is a proposed mine with production capacity of Laterite Deposit is 40,320 cum/ year.

2. It was noted that PP has submitted a copy of approved Mining Plan, DSR report, information in the lease’s within 500 meters radius around the site and other requisite information in the prescribed format duly verified in the Collector Office

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 153 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020

letter no 3143 dated 28/12/19 has reported that there are no more mines operating or proposed within 500 meters around the said mine.

3. SEAC in its 464th SEAC meeting dtd 03.10.2020 has recommended the case with 37 special conditions for issuance of EC.

4. The proposed plantation programme was examined and it was found that 20425 sapling of tree species shall be covered under plantation.

5. It was noted that as per Divisional Forest Officer, Letter no. 5675 dtd. 02.11.2019, the National Park/Sanctuary are not located within 10 Km., radius from the mining site. Hence, the General Conditions are not attracted.

6. It was noted that the water requirement is 6.5 KLD (4 KLD for Dust Suppression + 1.5 KLD for Domestic + 1 KLD for Green Belt) which shall be met from Tanker

7. It was also noted that the Public Hearing was carried out on 31.07.2020 at nearby mine site at Village - Tarawali, Tehsil - Suwasara, Dist. Mandsaur (MP) under Chairmanship of Additional District Magistrate, Mandsaur..

After detailed discussions and perusal of recommendations of 461st SEAC meeting dated 29.09.2020, presentation made by the PP in SEIAA, it was decided to accept the recommendation of SEAC for grant of prior EC to the project subject to the following specific conditions:-

I. Before commencing any mining activity fencing shall be carried out all around the lease area. Proper watch and ward arrangements should be made with installation of signage at 4 corners of lease area to avoid any untoward incident involving public and animals by the PP.

II. PP shall not start mining activity before execution of lease agreement. III. The depth of the pit shall be as per the Approved Mining Plan. IV. The entire area shall be fenced and three rows of plantation should be done

on the periphery of the boundary V. PP shall ensure that the proper water supply arrangements for dust

suppression, regular sprinkling, plantation and drinking purposes especially in summer season..

VI. PP shall ensure to construct and maintained the approach road. Plantation will be carried out on both side of approach road.

VII. PP shall ensure to construct garland drain with settling tank all around the lease area and regular cleaning & maintenance shall also be carried out by PP

VIII. PP shall ensure proper implementation of plantation, dust suppression, construction of approach road and maintenance of existing road & as part of Environmental Management Plan. Additional budget provision shall be made as part of EMP.

IX. Total 20425 saplings of suitable tree species i.e. Neem, Pipal, Bargad, Mango, Amla, Amaltas, Drumstick etc. shall be planted by PP at Mine lease boundary , Approach Road & village road ,Dribbling of Prosopis seed in trench soil of excavated garland drain, and in Khasra no. 153,under plantation programme. PP shall also explore and identify the chunk of land in the area from revenue record to carry out plantation programme as proposed

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 154 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020

X. PP must ensure implementation of the following activities with separate budget provision of Rs 1.5 lakh/ Year under CER. 1st Year Distribution of sanitizer, masks, gloves, hand wash, soap etc. for the

villagers of Ajaypur due to covid 19. (Rs. 0.10 lakh) Development of grazing land in the village area (Charnoi Bhoomi). (Rs.

0.10 lakh) Renovation of Aaganwadi kendra of village tarawali (Rs. 1.30 lakh)

2nd to 5th Year (Rs. 6.0 lakh) Construction of separate toilets for boys & girls at Govt. School, Village

Ajaypur Construction of Boundary wall for Village School at Tarawali &

Pratappura. Construction of Farsh for Village School at Tarawali.

PP shall give preference to develop/provide infrastructural facilities in schools or aganwadies of above villages The modification to the above activities can be made with the permission of the district administration and need based activity for the development of nearby villages shall be implemented by PP in consultation with the District Collector and Gram Panchayat

XI. PP should ensure to submit half yearly compliance report and CSR activity report with photographs of plantation in MP-SEIAA. If PP is failed to upload or submit two consecutive half yearly compliance reports of EC conditions to concerned authority (SEIAA and Regional Office, MoEF&CC,GoI,Bhopal) than prior environmental clearance issued to PP will automatically be treated as cancelled/ revoked as per OM No. 930/SEIAA/2019 dated 30.05.2019 issued by MPSEIAA.

Hence, Prior Environmental Clearance is granted for Laterite Deposit (Opencast Manual / Semi Mechanized Method) in an area of 17.010 ha. for production capacity of 40,320 cum/ year at Khasra No. 153, 154, 158 at Village - Tarawali, Tehsil - Suwasara, Dist. Mandsaur for the lease period to M/s Harshwardhan Industries Pvt. Ltd, B-64, Shaligram Tower, Near Sharon Park, Satellite Road, Dist. Ahmedabad, Gujarat

69. Case No 6750/2020 Prior Environmental Clearance for Laterite Deposit (Opencast Manual / Semi Mechanized Method) in an area of 20.740 ha. for production capacity of 56,700 cum/ year at Khasra No. 525, 642, 643 at Village - Ajaypur, Tehsil - Suwasara, Dist. Mandsaur (MP) by M/s. Harshwardhan Industries Pvt. Ltd, B-64, Shaligram Tower, Near Sharon Park, Satellite Road, Dist. Ahmedabad, Gujarat.

1. This is a project pertaining to mining of Laterite Deposit in MLA of 20.740 ha The activity is mentioned at S.No. 1 (a) of the Schedule of EIA Notification 2006 as amended from time to time. The project is reported to be at a distance of more than 10 km from National park and sanctuary etc. thus it is not attracted by the general conditions and considered under category ‘B-1” by virtue of its location and mining lease area. The case was forwarded by SEIAA to SEAC for appraisal

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 155 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020

of EIA for environment clearance for the project. It was submitted that this is a proposed mine with production capacity of Laterite Deposit is 56,700 cum/ year.

2. It was noted that PP has submitted a copy of approved Mining Plan, DSR report, information in the lease’s within 500 meters radius around the site and other requisite information in the prescribed format duly verified in the Collector Office letter no 3145 dated 28/12/19 has reported that there are no more mines operating or proposed within 500 meters around the said mine.

3. SEAC in its 464th SEAC meeting dtd 03.10.2020 has recommended the case with 37 special conditions for issuance of EC.

4. The proposed plantation programme was examined and it was found that 24900 sapling of tree species shall be covered under plantation.

5. It was noted that as per Divisional Forest Officer, Letter no. 5671 dtd. 02.11.2019, the National Park/Sanctuary are not located within 10 Km., radius from the mining site. Hence, the General Conditions are not attracted.

6. It was noted that the water requirement is 12 KLD (2 KLD for Dust Suppression + 3 KLD for Domestic + 7 KLD for Green Belt) which shall be met from Tanker

7. It was also noted that the Public Hearing was carried out on 29.07.2020 at nearby mine site at Village - Ajaypur, Tehsil - Suwasara, Dist. Mandsaur (MP) under Chairmanship of Additional District Magistrate, Mandsaur..

After detailed discussions and perusal of recommendations of 461st SEAC meeting dated 29.09.2020, presentation made by the PP in SEIAA, it was decided to accept the recommendation of SEAC for grant of prior EC to the project subject to the following specific conditions:-

I. Before commencing any mining activity fencing shall be carried out all around the lease area. Proper watch and ward arrangements should be made with installation of signage at 4 corners of lease area to avoid any untoward incident involving public and animals by the PP.

II. PP shall not start mining activity before execution of lease agreement. III. The depth of the pit shall be as per the Approved Mining Plan. IV. The entire area shall be fenced and three rows of plantation should be done

on the periphery of the boundary V. PP ensure to left 160 meters set back as a no mining zone towards dam

side (NW direction) VI. No drilling and blasting shall be carried out

VII. PP shall ensure that the proper water supply arrangements for dust suppression, regular sprinkling, plantation and drinking purposes especially in summer season..

VIII. PP shall ensure to construct and maintained the approach road. Plantation will be carried out on both side of approach road.

IX. PP shall ensure to construct garland drain with settling tank all around the lease area and regular cleaning & maintenance shall also be carried out by PP

X. PP shall ensure proper implementation of plantation, dust suppression, construction of approach road and maintenance of existing road & as part of

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 156 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020

Environmental Management Plan. Additional budget provision shall be made as part of EMP.

XI. PP shall leave set back of 200 m from earthern dam towards northern part of mining lease area as no mining zone and raise plantation in this area.

XII. Total 24900 saplings of suitable tree species i.e. Neem, Pipal, Bargad, Mango, Amla, Amaltas, Drumstick etc. shall be planted by PP at Mine lease boundary , Approach Road & village road ,Dribbling of Prosopis seed in trench soil of excavated garland drain, and in Khasra no. 153,under plantation programme. PP shall also explore and identify the chunk of land in the area from revenue record to carry out plantation programme as proposed

XIII. PP must ensure implementation of the following activities with separate budget provision of Rs 1.60 lakh/ Year under CER. 1st Year Distribution of sanitizer, masks, gloves, hand wash, soap etc. for the

villagers of Ajaypur due to covid 19. (Rs. 0.10 lakh) Development of grazing land in the village area (Charnoi Bhoomi). (Rs.

0.10 lakh) Construction of separate toilets for boys & girls at Govt. School, Village

Ajaypur & Pratap pura (Rs. 1.40 lakh) 2nd to 5th Year (Rs. 6.40 lakh) Construction of Boundary wall for Gram Panchayt Ajaypur Construction of 03 classroom at Govt. School Ajaypur..

PP shall ensure to contruct toilet with proper plumbing in the school of above village and contribute on behalf of village in Jal Jeewan Mission in consultation with Janpad Panchayat and PHED. PP shall give preference to develop/provide infrastructural facilities in schools or aganwadies of above villages The modification to the above activities can be made with the permission of the district administration and need based activity for the development of nearby villages shall be implemented by PP in consultation with the District Collector and Gram Panchayat

XIV. PP should ensure to submit half yearly compliance report and CSR activity report with photographs of plantation in MP-SEIAA. If PP is failed to upload or submit two consecutive half yearly compliance reports of EC conditions to concerned authority (SEIAA and Regional Office, MoEF&CC,GoI,Bhopal) than prior environmental clearance issued to PP will automatically be treated as cancelled/ revoked as per OM No. 930/SEIAA/2019 dated 30.05.2019 issued by MPSEIAA.

Hence, Prior Environmental Clearance is granted for Laterite Deposit (Opencast Manual / Semi Mechanized Method) in an area of 20.740 ha. for production capacity of 56,700 cum/ year at Khasra No. 525, 642, 643 at Village - Ajaypur, Tehsil - Suwasara, Dist. Mandsaur (MP) for the lease period to M/s. Harshwardhan Industries Pvt. Ltd, B-64, Shaligram Tower, Near Sharon Park, Satellite Road, Dist. Ahmedabad, Gujarat.

70. Case No. 7861/20 Prior Environmental Clearance for Stone Quarry (opencast manual/semi mechanized method) in an area of 1.283 ha. (4998 cum per annum)

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 157 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020

(Khasra No. 478/2/Ka, 478/2/Ja, 478/2/Ta), Village - Chormari, Tehsil - Rampur Baghelan, Dist. - Satna (MP) by Shri Pankaj Mishra, S/o Shri Chandra Sekhar Prasad Mishra, Village - Chormari, Tehsil - Rampur Baghelan, Dist. - Satna, MP - 485115, Email - [email protected], Mobile – 9752957808.

This case was recommended in 464th SEAC meeting dated 03.10.2020 and it was recorded that..........

“------------The case was presented by the PP and their consultant. PP stated that this is a case of stone mining. During presentation it was observed by committee pucca road and a canal is in existance at a distance of 100 meters & 190 meters respectively. The EMP and other submissions made by the PP were found to be satisfactory and acceptable, hence committee decided to recommend the case for grant of prior EC subject to the following special conditions in addition to the standard conditions at annexure ‘A’:

PP/Consultant made a presentation on all aspects of the project and all concerned issues were discussed in detail. After detailed discussions and perusal of recommendations of 464th SEAC meeting dated 03.10.2020, presentation made by the PP in SEIAA, it was decided to accept the recommendation of SEAC for grant of prior EC to the project subject to the following specific conditions:-

i. Before commencing any mining activity fencing shall be carried out all around the lease area. Proper watch and ward arrangements should be made with installation of signage at 4 corners of lease area to avoid any untoward incident involving public and animals by the PP.

ii. PP shall not start mining activity before execution of lease agreement.

iii. The depth of the pit shall be as per the Approved Mining Plan.

iv. The entire area shall be fenced and three rows of plantation should be done on the periphery of the boundary.

v. PP shall ensure the proper water supply arrangements for dust suppression, regular sprinkling, plantation and drinking purposes especially in summer season.

vi. Total 1550 saplings of suitable tree species i.e. Neem, Pipal, Bargad, Mango, Gulmohar, Sissoo, Guava, Amaltas, etc. shall be planted by PP in first three years under plantation programme at mine lease boundary and at khasra no. 483 in consultation with Gram Panchayat/ DM. PP shall also explore and identify the chunk of land in the area from revenue record to carry out plantation programme as proposed.

vii. PP shall ensure proper implementation of plantation, dust suppression, construction of approach road and maintenance of existing pakka road as part of Environmental Management Plan. Additional budget provision shall be made as part of EMP.

viii. PP must ensure implementation of the following activities with separate budget provision of total Rs. 3.0 lakh under CER as committed:

a) 1st Year: Distribution of Mask & Hand Sanitizer for School at village Umariha

(due to COVID-19)

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 158 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020

Cost of development of grazing land in the village area (Charnoi Bhoomi)

Water filter with 2000L overhead tank at Govt. School Umariha. b) 2nd, 3rd, 4th & 5th Year:

Toilet for school children, Umariha. Contribution for construction of boundary wall of school, Umariha.

PP shall ensure to contruct toilet with proper plumbing in the school of above village and contribute on behalf of village in Jal Jeewan Mission in consultation with Janpad Panchayat and PHED. PP shall give preference to develop/provide infrastructural facilities in schools or aanganwadies of above villages. The modification to the above activities can be made with the permission of the district administration and need based activity for the development of nearby villages shall be implemented by PP in consultation with the District Collector and Gram Panchayat.

ix. PP should ensure to submit half yearly compliance report, Plantation and CER activity report along with photographs of all activities in MP-SEIAA. If PP is failed to upload or submit two consecutive half yearly compliance reports of EC conditions to concerned authority (SEIAA and Regional Office, MoEF&CC,GoI,Bhopal) than prior environmental clearance issued to PP will automatically be treated as cancelled/ revoked as per OM No. 930/SEIAA/2019 dated 30.05.2019 issued by MPSEIAA.

Hence, Prior Environmental Clearance is granted for Stone Quarry (opencast manual/semi mechanized method) in an area of 1.283 ha. (4998 cum per annum) (Khasra No. 478/2/Ka, 478/2/Ja, 478/2/Ta), Village - Chormari, Tehsil - Rampur Baghelan, Dist. - Satna (MP) for the lease period to Shri Pankaj Mishra, S/o Shri Chandra Sekhar Prasad Mishra, Village - Chormari, Tehsil - Rampur Baghelan, Dist. - Satna, MP - 485115, Email - [email protected], Mobile – 9752957808.

71. Case No 7859/2020 Prior Environmental Clearance for Stone Quarry (Opencast Manual / Semi Mechanized Method) in an area of 2.823 ha. for production capacity of 62500 cum / year at Khasra No. 1068 at Village - Risthal, Tehsil - Sitamau, Dist. Mandsaur (MP) by M/s Ankita Construction, 22, Sawariya Colony, Nimbaheda, Raj. – 485990

This case was recommended in 464th SEAC meeting dated 03.10.2020 and it was recorded that..........

“…………The case was presented by the PP and their consultant. PP stated that this is a case of stone mining. After presentation PP was asked to submit proposal for revised CER & EMP as suggested by committee. PP vide letter dated 03/10/2020 submitted the reply which was placed before the committee and same were found satisfactory. The EMP and other submissions made by the PP were found to be satisfactory and acceptable, hence committee decided to recommend the case for grant of prior EC subject to the following special conditions in addition to the standard conditions at annexure ‘A’:”

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 159 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020

PP/Consultant made a presentation on all aspects of the project and all concerned issues were discussed in detail. After detailed discussions and perusal of recommendations of 464th SEAC meeting dated 03.10.2020, presentation made by the PP in SEIAA, it was decided to accept the recommendation of SEAC for grant of prior EC to the project subject to the following specific conditions:-

I. Before commencing any mining activity fencing shall be carried out all around the lease area. Proper watch and ward arrangements should be made with installation of signage at 4 corners of lease area to avoid any untoward incident involving public and animals by the PP.

II. PP shall not start mining activity before execution of lease agreement. III. The depth of the pit shall be as per the Approved Mining Plan. IV. The entire area shall be fenced and three rows of plantation should be done

on the periphery of the boundary. V. PP shall ensure that the proper water supply arrangements for dust

suppression, regular sprinkling, plantation and drinking purposes especially in summer season.

VI. PP shall ensure to construct and maintained the approach road. Plantation will be carried out on both side of approach road.

VII. PP shall ensure proper implementation of plantation, dust suppression, construction of approach road and maintenance of existing road & as part of Environmental Management Plan. Additional budget provision shall be made as part of EMP.

VIII. Total 3000 saplings of suitable tree species i.e. Neem, Pipal, Bargad, Mango, Amla, Amaltas, Drumstick etc. shall be planted by PP at mine lease boundary (1000 saplings) and 2000 saplings at khasra no 1068( Govt. waste land) under plantation programme. PP shall also explore and identify the chunk of land in the area from revenue record to carry out plantation programme as proposed.

IX. PP must ensure implementation of the following activities with separate budget provision of Rs 2.0 lakh for 2 years under CER.

CER activities at village Risthal (1st and 2nd year)

Construction of Village School Boundary Wall (Length 70m) – 2,00,000/- PP shall ensure to contruct toilet with proper plumbing in the school of above village and contribute on behalf of village in Jal Jeewan Mission in consultation with Janpad Panchayat and PHED. PP shall give preference to develop/provide infrastructural facilities in schools or aganwadies of above villages The modification to the above activities can be made with the permission of the district administration and need based activity for the development of nearby villages shall be implemented by PP in consultation with the District Collector and Gram Panchayat

X. PP should ensure to submit half yearly compliance report and CSR activity report with photographs of plantation in MP-SEIAA. If PP is failed to upload or submit two consecutive half yearly compliance reports of EC conditions to concerned authority (SEIAA and Regional Office, MoEF&CC,GoI,Bhopal)

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 160 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020

than prior environmental clearance issued to PP will automatically be treated as cancelled/ revoked as per OM No. 930/SEIAA/2019 dated 30.05.2019 issued by MPSEIAA.

Hence, Prior Environmental Clearance is granted for Stone Quarry (Opencast Manual / Semi Mechanized Method) in an area of 2.823 ha. for production capacity of 62500 cum / year at Khasra No. 1068 at Village - Risthal, Tehsil - Sitamau, Dist. Mandsaur (MP) for the lease period to M/s Ankita Construction, 22, Sawariya Colony, Nimbaheda, Raj. – 485990

72. Case No 7862/2020 Prior Environmental Clearance for Stone and Murrum Quarry (Opencast Manual / Semi Mechanized Method) in an area of 1.0 ha. for production capacity of Stone - 15000 cum/ year, Murrum - 5949 cum/ year at Khasra No. 420/1 at Village - Machhalgaon, Tehsil - Gogawa, Dist. Khargone (MP) by Shri Santosh Chandel S/o Shri Shyamlal Chandel, Gram - Machhalgaon, Tehsil - Bhikangaon, Dist. Khargone, MP - 451441

This case was recommended in 464th SEAC meeting dated 03.10.2020 and it was recorded that..........

“…………The case was presented by the PP and their consultant. PP stated that this is a case of stone mining wherein during presentation it wass observed by the committee that a dam is in existance at a distance of 225 meters and seasonal drain at a distance of 50 meters on the eastern and southern side respectively. Considering sensitivity committee recommends that the maximum depth shall be restricted to 15 meters. After presentation PP was asked to submit proposal for depth restriction, revised CER & EMP as suggested by committee. PP vide letter dated 03/10/2020 submitted the reply which was placed before the committee and same were found satisfactory. The EMP and other submissions made by the PP were found to be satisfactory and acceptable, hence committee decided to recommend the case for grant of prior EC subject to the following special conditions in addition to the standard conditions at annexure ‘A’::”

PP/Consultant made a presentation on all aspects of the project and all concerned issues were discussed in detail. After detailed discussions and perusal of recommendations of 464th SEAC meeting dated 03.10.2020, presentation made by the PP in SEIAA, it was decided to accept the recommendation of SEAC for grant of prior EC to the project subject to the following specific conditions:-

I. Before commencing any mining activity fencing shall be carried out all around the lease area. Proper watch and ward arrangements should be made with installation of signage at 4 corners of lease area to avoid any untoward incident involving public and animals by the PP.

II. PP shall not start mining activity before execution of lease agreement. III. The depth of the pit shall be as restricted to 15 meters as recommended by

SEAC. IV. The entire area shall be fenced and three rows of plantation should be done

on the periphery of the boundary. V. PP shall ensure that the proper water supply arrangements for dust

suppression, regular sprinkling, plantation and drinking purposes especially in summer season.

VI. PP shall ensure to construct and maintained the approach road. Plantation will be carried out on both side of approach road.

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 161 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020

VII. PP shall ensure proper implementation of plantation, dust suppression, construction of approach road and maintenance of existing road & as part of Environmental Management Plan. Additional budget provision shall be made as part of EMP.

VIII. Total 1200 saplings of suitable tree species i.e. Neem, Pipal, Bargad, Mango, Amla, Amaltas, Drumstick etc. shall be planted by PP at mine lease boundary ,At Remaining Private Waste land khasra no.439 under plantation programme. PP shall also explore and identify the chunk of land in the area from revenue record to carry out plantation programme as proposed.

IX. PP must ensure implementation of the following activities with separate budget provision of Rs 2.50 lakh for 5 years under CER.

CER activities at village Machalgaon (1st to 5th year)

Providing Water Filter at Village School- Rs. 10,000/- Providing Swings & Slides to Village School – 30,000/- Construction of Village School Boundary Wall (70m) – Rs.2,10,000/-

PP shall ensure to contruct toilet with proper plumbing in the school of above village and contribute on behalf of village in Jal Jeewan Mission in consultation with Janpad Panchayat and PHED. PP shall give preference to develop/provide infrastructural facilities in schools or aganwadies of above villages The modification to the above activities can be made with the permission of the district administration and need based activity for the development of nearby villages shall be implemented by PP in consultation with the District Collector and Gram Panchayat

X. PP should ensure to submit half yearly compliance report and CSR activity report with photographs of plantation in MP-SEIAA. If PP is failed to upload or submit two consecutive half yearly compliance reports of EC conditions to concerned authority (SEIAA and Regional Office, MoEF&CC,GoI,Bhopal) than prior environmental clearance issued to PP will automatically be treated as cancelled/ revoked as per OM No. 930/SEIAA/2019 dated 30.05.2019 issued by MPSEIAA.

Hence, Prior Environmental Clearance is granted for Stone and Murrum Quarry (Opencast Manual / Semi Mechanized Method) in an area of 1.0 ha. for production capacity of Stone - 15000 cum/ year, Murrum - 5949 cum/ year at Khasra No. 420/1 at Village - Machhalgaon, Tehsil - Gogawa, Dist. Khargone (MP) or the lease period to Shri Santosh Chandel S/o Shri Shyamlal Chandel, Gram - Machhalgaon, Tehsil - Bhikangaon, Dist. Khargone, MP – 451441

73. Case No. 7865/2020 : Prior Environment Clearance for propsed project Expansion of Active Pharmaceutical Ingredient (API)/ Bulk Drugs & Intermediates at Industrial Area 3, A.B. Road, Dewas MP- 455001 Total Plant area – 112 Acres Expansion Area :0.151 Acres wihin the existing plant area Production Capacity: 1372 TPA by M/S. SUN PHARMACEUTICAL INDUSTRIES LTD through Deputy General Manager Shri Suresh Kumar Golla Industrial Area 3, A.B. Road, Dewas, Madhya Pradesh-455001 Email : [email protected] Ph:- 07272-496100

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 162 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020

1) The Plant had started its operations since 1992 with name M/s Ranbaxy Laboratories Limited for production of bulk drugs with valid EC granted in 2005 for expansion to increase the capacity from 282 TPA to 805 TPA with the production capacity approval of 805 TPA. Later at 2015 M/s Ranbaxy limited amalgamated with M/s Sun Pharmaceuticals Industries Limited. Now the plant desires to expand its capacity to 1372 TPA for API & Intermediates.

2) This is case of Prior Environment Clearance for Expansion of Active Pharmaceutical Ingradient (API)/Bulk Drugs & Intermediates at Industrial Area, 3, AB Road, Dist. Dewas, (MP) from 805 TPA to 1372 TPA at Plot No. 2 and 2A, Dewas Industrial Area 3, A.B. Road, Dewas, Madhya Pradesh

3) SPIL is currently situated over an area of 112 acres within which expansion will be taking place in area of 0.151 acres. SPIL involve in business of manufacturing of APIs & Intermediate having a capacity of manufacturing of 805 TPA and after proposed expansion capacity will be increase up to 1372 TPA. The cost of the project is INR. 62.9 Cr.

4) The Co-ordinates of the project site are latitude from 22°92’ to 22°93’ N and longitude 76°02’ to 76°03’ E with ground level 532 m above MSL.

5) The Dewas unit, one of the units of Sun Pharma, is engaged in the manufacture of Active Pharmaceutical Ingredients (APIs) & Intermediates. It is a multi-product manufacturing site engaged in manufacturing of APIs & Intermediates. These products are manufactured in campaigns through multi-step organic synthesis using batch processes.

6) The company has taken the ‘Consent to Operate’ for the production capacity of 805 TPA for Air and Water from Madhya Pradesh Pollution Control Board with consent no. AW-50636 validity up to. 31/10/2020.

7) PP has submitted capacity of existing and proposed products are as follows:- Sl. No

Product Name Existing Capacity TPA (As per the CTO)

Additional Capacity TPA

After expansion total Capacity TPA

1 Antibiotic Cilastatin 10 10 20 2 Antibiotic Imipenem 10 10 20 3 Anti-viral: Aciclovir & Salts

Gancyclovir/ Valacyclovir valgyancyclovir

50 -20 30

4 Ciprofloxacin & Salts 250 0 250 5 Macrolide (Clarithromycin) 100 0 100 6 Antiepilliptic gabapentene 80 -80 0 7 Antiviral Acyclovir and salts 70 -70 0 8 Azhithromycin 10 -10 0 9 Citalopram 50 -50 0 10 Entrofloxacin 06 -06 0 11 Etadolac 36 -36 0 12 Intermediate 36 -36 0 13 Lamuvidine 10 -10 0 14 Oflaxacin and salts 50 -50 0 15 Simvastatin/ Rosuvastatin/

Fluvastatin 37 -37 0

16 Pentoxifylline 0 50 50

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 163 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020

17 Piroxicam Betacyclodextrin 0 5 5 18 Orlistat 0 30 30 19 Sodium bicarbonate sterile 0 2 2 20 Sodium carbonate sterile 0 5 5 21 Metadoxin 0 15 15 22 Mephentermine 0 15 15 23 Oxetacaine 0 70 70 24 Esmoprozole 0 10 10 25 Sodium Valporate 0 30 30 26 Sodium Valporate 0 30 30 27 T-3811 A03 Toyama 0 20 20 28 Levitracetam 0 240 240 29 Meropenem 0 26 26 30 Doripenem 0 2 2 31 Penem blend 0 0 0 32 4,7 Di Chloro Quinoline 0 40 40 33 Ertapenem 0 2 2

34 Anti-hypertension Sartans (Irbesartan, Valsartan, Cande saratan, Telmesartan, Losartan)

0 240 240

35 Dipropyl Diethyl Malonate 0 100 100 36 R & D Product validation 0 20 20

Total 805 567 1372

8) As per EIA Notification dated 14th September 2006 and its amendment, the project is located under the Notified Industrial area of Dewas, District-Dewas (M.P.) so the project falls under activity ‘5(f)’ of schedule ‘B’ (i.e. for Synthetic Organic Chemicals) and as per the Notification S.O. 1223 (E) dated 27.03.2020 in which it is clearly mentioned that “All proposals for projects or activities in respect of Active Pharmaceutical Ingredients (API), received up to the 30th September 2020, shall be appraised, as Category ‘B2’ projects, provided that any subsequent amendment or expansion or change in product mix, after the 30th September 2020, shall be considered as per the provisions in force at that time.”

9) There is no interstate boundary (PWD letter dtd. 23.09.2020) within 05 km and no National park, Sanctuary and Eco-sensitive areas within 05 km of the project area hence General condition are not attracted.

10) During presentation in SEAC PP submitted that they have applied for expansion only by adding shift from one and half shift working to three shifts. Earlier EC was obtained in 2005 and have applied for compliance of EC condition but due to COVID-19 compliance inspection could not be done by the authority. However, we are regularly submitting half yearly compliance report and requesting that this case shall be recommended to SEIAA and will submit compliance report shortest possible time.

11) The case was discussed in SEAC meetings 464th dated 03.10.2020, and recommended for grant of prior EC.

12) Today the case scheduled for presentation and after deliberations by PP the case was discussed in depth & it is recorded that:-

13) After the deliberation the case was discussed in detail and recorded that:- i. Salient Feature of Proposed Project:(Existing & Proposed):-

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 164 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020

Project Name Expansion of Active Pharmaceutical Ingredient (API) Manufacturing Unit from 805 TPA To 1372 TPA at Village Dewas, District – Dewas, Madhya Pradesh

Production Capacity Existing Capacity

Proposed Capacity

805 TPA 1372 TPA

Land Requirement SPIL is currently situated over an area of 112 acres within which expansion will be take place in area of 0.151 acres.

Water Requirement/Sources

Existing Plant Additional After Expansion

1210 KLD

240 KLD

1450 KLD

Dewas Water-Projects Works Private Limited

Power Requirement /Sources

Existing Plant

Additional After Expansion

4800 kVA 900 kVA 5700 kVA Madhya Pradesh Paschim Kshetra Vidyut Vitaran Company (MPPKVVC)

Area for Greenbelt/Plantation

66.4 acres (59%)

Project Cost INR 62.9 Crores

ii. The Land is taken on lease by M/s Sun Pharmaceuticals Industries Limited from the Govt. of Madhya Pradesh AKVN. The project is for the expansion of API & Intermediate manufacturing facilities within the existing plant.SPIL is currently situated over an area of 112 acres within which expansion will be take place in area of 0.151 acres.

Sl.No Area Description Area in m2 Area in acres

% of Total Plot Area

1 Manufacturing Area API

14546.11 3.6 3.21

2 Manufacturing Area Formulations

145553.58 36.0 32.11

3 Green belt 268965.0 66.4 59.34

4 Road Area 24183.22 6.0 5.34

Total Area 453247.91 112.0 100

iii. The major facilities involved are MEE, ATFD, Solvent recovery Plant, Solvent storage area, reactors, Cooling towers, DG set, Effluent treatment plant (ETP), and R.O Plant. Facilities like parking & plantation also developed as per plant requirement.

i. The total water requirement for the project after the proposed expansion will be 1450 KLD which will be sourced from surface water supplied by Dewas Water-projects Works Private Limited.

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 165 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020

ii. There is no discharge of effluents outside the plant premises as the unit is based on “Zero Liquid Discharge”. The total wastewater generation from the project at present is 460 KLD. After proposed expansion of production the total wastewater generation will be 700 KLD. The wastewater (Industrial) is treated in an ETP of capacity 1000 KLD. The domestic sewerage system existing within the plant receives sewage from only domestic points. Industrial and domestic sewerage systems are properly segregated and are ensured that they do not mix. The domestic sewage arising within the plant would be treated in an STP and the recycled water would be reused for flushing, and horticultural purposes thereby reducing the overall freshwater requirement

iii. There will be two types of Solid wastes generated from the project.

Non Hazardous Solid waste:

(1) Municipal Solid Waste: The Municipal solid waste includes the paper waster from Office as well as other domestic wastes. Paper wastes would be sold to scrap vendors, while other wastes would be disposed off as per Solid Waste Management Rules, 2016.

(2) Sludge: Horticulture waste and sludge from STP are dried and used as manure.

(3) Fly Ash: The fly ash generated from the boiler and will be send for Brick making.

(b) Hazardous Solid waste: All the hazardous waste generated at the manufacturing facility is to be disposed as per the legal requirement. For Hazardous Waste, Dewas unit has taken the authorization under Hazardous and Other Waste (Management & Trans boundary Movement) Rules, 2016 as amended, from MPPCB.

(Sludge: Sludge from Effluent Treatment Plant (ETP) which would Collection, storage and disposed at TSDF Site as the company is having the membership under Madhya Pradesh Waste Management Project (division of RAMKY Enviro Engineers Ltd.) with membership valid till 29.01.2025.

iv. Solid waste generated during the manufacturing process and wastewater treatment process is mainly sludge and will be disposed at authorized TSDF facility, as per Hazardous and Other Waste (Management & Trans boundary Movement) Rules, 2016 as amendment. The Company is having the membership of TSDF from ‘RAMKY ENVIRO ENGINEERS LTD’ with membership valid till. 29.01.2025.

v. SPIL using LNG in 5 TPH and 10 TPH Boilers, which are clean fuel. Only in 14 TPH Boiler, Agro based Biomass is used as a fuel. SPIL will switch over to LNG in this boiler also after making alterations in next 3 years. For all DG Sets, SPIL will use low sulphur HSD.

vi. Power requirement will be sourced from existing line of ‘Madhya Pradesh Madhya Kshetra Vidyut Vitaran Company’. The company is already authorized to use power load of 4800 kVA & 900 kVA additional power load will be required for proposed expansion. In case of power failure, D.G. set will be used as a backup power source.

vii. For control of air pollution PP has adopted following measures:

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 166 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020

The process emissions contain Carbon dioxide, Hydrogen, Nitrogen & solvent emission which will be sent to scrubber and the waste scrubbing medium to be sent to effluent treatment system. SO2 will be sent to scrubber and the resultant medium containing Sodium Bi-sulfite to be sent to effluent treatment system. The process emissions contain Carbon dioxide, Hydrogen, Nitrogen & solvent emission which will be sent to scrubber and the waste scrubbing medium to be sent to effluent treatment system. SO2 will be sent to scrubber and the resultant medium containing Sodium Bi-sulfite to be sent to effluent treatment system.

Condensers and Heat Exchangers to control solvent emissions/losses from manufacturing processes. Where practicable, liquids are handled in closed systems to eliminate any chances of fugitive emissions. All solvents/liquids are charged mechanically in the closed loop to avoid solvent losses thus eliminating chances of air pollution also due to fugitive emissions.

All the solvent recovery systems are attached with double stage chilled water/chilled brine condensers to control solvent vapour emissions. Additionally, closed loop auto heating cut-off system in solvent recovery columns to arrest fugitive emissions of solvents.

Breather Valves on storage tanks and process equipment to arrest fugitive emissions.

Stacks of adequate heights have been provided for effective dispersion of the air pollutants in the atmosphere from emission sources, namely, boilers, and DG sets.

viii. Noise attenuating devices like earplugs and earmuffs shall be provided to workers exposed to high noise levels. Noise barriers, silencer and enclosures shall be incorporated in the equipments, which emit high noise level. All basic equipments and various machineries should be kept well maintained. Green belts are good noise barriers and same will be developed around the plant. The sufficient green belt may be proposed to control noise levels.

ix. Particulate matters & other gaseous emission are envisaged as pollutant from boiler and other sources apart from other sources of fugitive emission .Depending on quality of emission from different sources, suitable air pollution control system will be provided.

x. PP has proposed 268965.0 sq.m. (approx. 59% of total area) by planting trees around the peripher and within the premises of the project area.

xi. PP has submitted on site and of site emergency plan including Disaster Management, Risk Assessment and Fire Fighting.

xii. The proposed project has planned extensive pollution control and environmental conservation measures. Under the CER PP has proposed following activities with 62.0 Lakh budgetary provision as per OM of MOEF & CC dated 1st May, 2018:-

Sl. No. Activity Year wise implementation and Budgetary provision during

operation phase

Total budgetary provision (Rs.)

1st year 2nd year

3rd year

4th year 5th year

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 167 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020

1 Construction of sanitation facilities (toilet) in schools and villages

3,00,000 3,00,000 3,00,000 3,00,000 3,00,000

15,00,000

2 Infrastructure for Periodic medical check-up camp by appointing specialist doctor for eyes, skin, heart and dental in a year

50,000 50,000 50,000 50,000 50,000

2,50,000

3 Facilities for solid waste management

50,000 50,000 50,000

50,000 50,000 2,50,000

4 Training to the farmers related to healthcare and crop production

50,000 50,000 50,000

50,000 50,000 2,50,000

5 Infrastructure for development of technical skills and training to the local persons

2,00,000 2,00,000 2,00,000 2,00,000 2,00,000 10,00,000

6

Assistance in providing study materials, uniform, books to the poor students located nearby area

50,000 50,000 50,000 50,000 50,000 2,50,000

7 Construction of roads and storm water drainage facility in nearby village

3,00,000 3,00,000 3,00,000 3,00,000 3,00,000 15,00,000

8 Provision of solar lanterns in villagers

40,000 40,000 40,000 40,000 40,000 2,00,000

9 Distribution of saplings among villagers to be planted in the open and degraded areas

1,00,000 1,00,000 1,00,000 1,00,000 1,00,000 5,00,000

10 Facility for rain water harvesting by desilting nearby ponds

1,00,000 1,00,000 1,00,000 1,00,000 1,00,000 5,00,000

Total 62,000,00

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 168 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020 The submissions made by the PP were found to be satisfactory and acceptable hence It is decided to accept the recommendations of 464th SEAC meeting dtd. 03.10.20.and accord Prior Environmental Clearance for Proposed Expansion of Active Pharmaceutical Ingredient (API)/ Bulk Drugs & Intermediates at Industrial Area 3, A.B. Road, Dewas MP- 455001 Total Plant area – 112 Acres Expansion Area :0.151 Acres wihin the existing plant area Production Capacity: 1372 TPA by M/S. SUN PHARMACEUTICAL INDUSTRIES LTD through Deputy General Manager Shri Suresh Kumar Golla Industrial Area 3, A.B. Road, Dewas, Madhya Pradesh-455001 subject to following specific conditions imposed by SEIAA:-.

1. PP should ensure to submit the certified compliance report in MP SEIAA at the earliest.

2. The entire demand of fresh water should be met through Dewas Water-projects Works Private Limited. and there should be no extraction of ground water.

3. Waste water: (a) PP should ensure “Zero effluent discharge” from the unit by 100% recycling. The

water softening reject, boiler blow down reject and cooling blow down will be treated in ETP. Further treated waste water will go through the RO and finally re used/recycled in the process and unused waste water evaporates in MEE.

(b) RO and MEE should be provided for treatment of high COD waste streams and only in case of emergency/breakdown high COD wastes should be disposed off through CTSDF, Pithampur, Dhar.

4. For Air Pollution: a) In plant control measures for checking fugitive emission from all the vulnerable

sources shall be provided. Fugitive emission shall be controlled by providing closed storage, closed handling & conveyance of chemicals/materials, multi cyclone separator/bag filters and water sprinkling system.

b) Dust suppression system including water sprinkler system/ foaming arrangement shall be provided at loading and unloading areas to control dust emission.

c) Fugitive emission in the work zone environment, product, raw material storage areas etc. shall be regularly monitored.

d) Transportation of raw material and finished goods should be carried out in covered trucks.

e) For control of fugitive emission and VOCs following steps should be followed:- Chilled brine circulation system shall be provided and it should be ensured

that the solvent recovery efficiency will not be less than 98%. Reactor and solvent handling pump shall be provided with mechanical seal

to prevent leakage. Closed handling system should be provided for chemicals. System of leak detection and repair of pump/pipeline should be based on

preventive maintenance. Solvent shall be taken from underground storage tank to reactor through

closed pipeline. Storage tank shall be vented through trap receiver and condenser operated on chilled water.

9. Hazardous Waste Management: (a) As proposed above, PP should ensure disposal of hazardous waste regularly

and there should be no dumping of these materials in the premises/outside.

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 169 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020

(b) PP should ensure handling, disposal and management of hazardous waste as per the related prescribed rules.

(c) PP should obtain Renewal of authorization regularly from MPPCB for collection storage and disposal of hazardous waste (Management, handling & transboundary Movement) Rules 2008 and its amendments. Membership of the TSDF should be obtain for hazardous waste disposal.

(d) Hazardous chemicals should be stored in sealed tanks, drums etc. Flame arrestors shall be provided on tanks. To avoid the spillage from processing unit, Industry shall provide fully mechanized filling and packaging operation unit.

5. PP should obtain NOC /approval from competent authority for health & safety measure, Onsite & Offsite disaster management, and Risk management plan before commencing the operation of the unit.

6. PP should ensure installation of photovoltaic cells (solar energy) for lighting in common areas, LED light fixtures and energy efficient equipments.

7. Green Belt: (a) PP should ensure plantation as proposed in 268965.0 m2 (approx. 59% of

total area) by planting trees at the propsed locations and Plantation in the project area of indigenous local varieties like Neem, Peepal, Kadam, Kachnaar etc.

(b) Every effort should be made to protect the existing trees on the plot. (c) Green area including thick green-belt shall be developed in the plot area to

mitigate the effect of fugitive emissions all around the project area in consultation with the forest department as per the guidelines of CPCB.

8. PP should ensure the implementation of CER activities to the extent of 62lakh will be used Infrastructure facilities at schools in terms of provision of computers, teachers, facility of safe drinking water, separate toilets for girls and boys, provision of furniture, additional rooms etc. In consultation with district administrationDewas. Execution of need base activities in coordination with district administration Dewas

9. Total quantity of runoff water generated and green belt area should be collected in underground tank & used for process in plant to minimize fresh water requirement.

10. All other conditions as laid in the consents of MPPCB shall be applicable. 74. Case No. 7427/2020; Prior Environmental Clearance for Stone Quarry (Opencast

Manual/Semi Mechanized Method) in an area of 2.213 ha. for production capacity of 49260 cum per annum at Khasra No. 467, 468 at Village - Parsel Kalan, Tehsil - Pushparajgarh, Dist. Anuppur (MP) by M/s Saraswati Mining & Crushing, SHri Jai Prakash Shivdasani, Village & Post - Pendra Road, Dist. Bilaspur, CG

This case was recommended in 464th SEAC dated 3/10/2020 it was recorded that..........

"------------ PP Vide letter dated 28/09/2020 has submitted the reply which was placed before the committee. Committee accepts the reply submitted by PP and decided to recommend the case for grant of prior EC subject to the following special conditions in addition to the standard conditions at annexure ‘A’:

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 170 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020

PP/Consultant made a presentation on all concerned issues were discussed in detail. After detailed discussions and perusal of recommendations of 464th SEAC meeting dated 3.10.2020, presentation made by the PP in SEIAA, it was decided to accept the recommendation of SEAC for grant of prior EC to the project subject to the following specific conditions:-

I. Before commencing any mining activity fencing shall be carried out all around the lease area. Proper watch and ward arrangements should be made with installation of signage at 4 corners of lease area to avoid any untoward incident involving public and animals by the PP.

II. PP shall not start mining activity before execution of lease agreement.

III. The depth of the pit shall be as per the Approved Mining Plan.

IV. The entire area shall be fenced and three rows of plantation should be done on the periphery of the boundary.

V. PP shall ensure the proper water supply arrangements for dust suppression, regular sprinkling, plantation and drinking purposes especially in summer season.

VI. Total 2700 saplings of suitable tree species i.e. Neem, Pipal,Bargad,Gulmohar Amla etc. shall be planted in nearby Khasra No. 313 of Village – Parsel Kalan, Tehsil - Pushparajgarh, Dist. Anuppur,by PP in three year under plantation programme in consultation with DM at identified revenue land of the district. PP shall also explore and identify the chunk of land in the area from revenue record to carry out plantation programme as proposed.

VII. PP shall ensure proper implementation of plantation, dust suppression, construction of approach road and maintenance of existing pakka road as part of Environmental Management Plan. Additional budget provision shall be made as part of EMP.

VIII. PP must ensure implementation of the following activities with separate budget provision of total Rs 5.50 Lakh under CER:

Village Name: Parsel Kalan Distribution of masks and sanitizers to villagers for 1st year only. Development and maintenance of grassland on a nearby suitable

government land (from 1st to 5th year). Construction of two class room in Primary School and whitewash and

furnished. -Construction of Village Road at Malaiki & Parselkalan.-2 nos.

PP shall ensure to contruct toilet with proper plumbing in the school of above village and contribute on behalf of village in Jal Jeewan Mission in consultation with Janpad Panchayat and PHED. PP shall give preference to develop/provide infrastructural facilities in schools or aanganwadies of

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 171 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020

above villages. The modification to the above activities can be made with the permission of the district administration and need based activity for the development of nearby villages shall be implemented by PP in consultation with the District Collector and Gram Panchayat.

IX. PP should ensure to submit half yearly compliance report, Plantation and CER activity report along with photographs of all activities in MP-SEIAA. If PP is failed to upload or submit two consecutive half yearly compliance reports of EC conditions to concerned authority (SEIAA and Regional Office, MoEF&CC,GoI,Bhopal) than prior environmental clearance issued to PP will automatically be treated as cancelled/ revoked as per OM No. 930/SEIAA/2019 dated 30.05.2019 issued by MPSEIAA.

Hence, Prior Environmental Clearance is granted for Stone Quarry (Opencast Manual/Semi Mechanized Method) in an area of 2.213 ha. for production capacity of 49260 cum per annum at Khasra No. 467, 468 at Village - Parsel Kalan, Tehsil - Pushparajgarh, Dist. Anuppur (MP) for the lease period to M/s Saraswati Mining & Crushing, SHri Jai Prakash Shivdasani, Village & Post - Pendra Road, Dist. Bilaspur, CG

75. Case No 7501/2020 Prior Environmental Clearance for Stone Quarry (Opencast

Manual / Semi Mechanized Method) in an area of 1.683 ha. for production capacity of 10450 cum / year at Khasra No. 75/4 at Village - Jamuniya Raiyat, Tehsil - Khaknar, Dist. Burhanpur (MP) by M/s Hanuman Stone Crusher, Prop. Smt. Chhaya Vasankar, Hanuman Mandir Ke Pass, Khaknar, DIst. Burhanpur, MP - 450331

This case was recommended in 464th SEAC meeting dated 03.10.2020 and it was recorded that..........

“…………Vide letter dated 28/09/2020 PP has submitted the analysis report of soil sample. Committee accepts the reply submitted by PP with a condition PP shall also promote organic farming in the nearby agricultural fields. The EMP and other submissions made by the PP were found to be satisfactory and acceptable, hence committee decided to recommend the case for grant of prior EC subject to the following special conditions in addition to the standard conditions at annexure ‘A’:”

PP/Consultant made a presentation on all aspects of the project and all concerned issues were discussed in detail. After detailed discussions and perusal of recommendations of 464th SEAC meeting dated 03.10.2020, presentation made by the PP in SEIAA, it was decided to accept the recommendation of SEAC for grant of prior EC to the project subject to the following specific conditions:-

I. Before commencing any mining activity fencing shall be carried out all around the lease area. Proper watch and ward arrangements should be made with installation of signage at 4 corners of lease area to avoid any untoward incident involving public and animals by the PP.

II. PP shall not start mining activity before execution of lease agreement. III. The depth of the pit shall be as per the Approved Mining Plan. IV. The entire area shall be fenced and three rows of plantation should be done

on the periphery of the boundary.

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 172 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020

V. PP shall ensure that the proper water supply arrangements for dust suppression, regular sprinkling, plantation and drinking purposes especially in summer season.

VI. PP shall also promote organic farming in the nearby agricultural fields VII. PP shall ensure to construct and maintained the approach road. Plantation

will be carried out on both side of approach road. VIII. PP shall ensure proper implementation of plantation, dust suppression,

construction of approach road and maintenance of existing road & as part of Environmental Management Plan. Additional budget provision shall be made as part of EMP.

IX. Total 1700 saplings of suitable tree species i.e. Neem, Pipal, Bargad, Mango, Amla, Amaltas, Drumstick etc. shall be planted by PP at mine lease boundary 100 trees , (Total 1600 trees) In the Govt. Land, Area: 2.736 ha, Survey No.- 47 under plantation programme. PP shall also explore and identify the chunk of land in the area from revenue record to carry out plantation programme as proposed.

X. PP must ensure implementation of the following activities with separate budget provision of Rs 3.50 lakh for 5 years @ 70,000/ Year under CER.

CER activities at village JAMUNIYA RAIYAT (1st to 5th year)

Distribution of mask , sanitizer for village people (In 1st year ) (Rs.10,000).

Preparation of grazing land . (In 1st year ) (Rs.10,000). Construction of 1 rooms with white wash in govt. primary school village

Jamuniya raiyat. (Rs.1,80,000). Contribution for Jal Jeewan Mission to janpad panchayat Jamuniya raiyat.

(Rs.1,50,000). PP shall give preference to develop/provide infrastructural facilities in schools or aganwadies of above villages The modification to the above activities can be made with the permission of the district administration and need based activity for the development of nearby villages shall be implemented by PP in consultation with the District Collector and Gram Panchayat

I. PP should ensure to submit half yearly compliance report and CSR activity report with photographs of plantation in MP-SEIAA. If PP is failed to upload or submit two consecutive half yearly compliance reports of EC conditions to concerned authority (SEIAA and Regional Office, MoEF&CC,GoI,Bhopal) than prior environmental clearance issued to PP will automatically be treated as cancelled/ revoked as per OM No. 930/SEIAA/2019 dated 30.05.2019 issued by MPSEIAA.

Hence, Prior Environmental Clearance is granted for Stone Quarry (Opencast Manual / Semi Mechanized Method) in an area of 1.683 ha. for production capacity of 10450 cum / year at Khasra No. 75/4 at Village - Jamuniya Raiyat, Tehsil - Khaknar, Dist. Burhanpur (MP) for the lease period to M/s Hanuman

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 173 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020

Stone Crusher, Prop. Smt. Chhaya Vasankar, Hanuman Mandir Ke Pass, Khaknar, DIst. Burhanpur, MP – 450331

76. Case No. 7608/2020; Prior Environmental Clearance for Stone Quarry (Opencast Manual/Semi Mechanized Method) in an area of 1.0 ha. for production capacity of 5761 cum per annum at Khasra No. 176, 177/3 at Village - Kapuri, Tehsil - Sehore, Dist. Sehore (MP) by Shri Mukesh Kumar Patel S/o Shri Dhanraj Patel, Village - Kapuri, Dist. Sehore, MP.

This case was recommended in 464th SEAC dated 3/10/2020 it was recorded that..........

"------------ Vide letter dated 30/09/2020 PP has submitted the analysis report of soil sample. Committee accepts the reply submitted by PP with a condition that PP shall also promote organic farming in the nearby agricultural fields. The EMP and other submissions made by the PP were found to be satisfactory and acceptable, hence committee decided to recommend the case for grant of prior EC subject to the following special conditions in addition to the standard conditions at annexure ‘A’:

PP/Consultant made a presentation on all concerned issues were discussed in detail. After detailed discussions and perusal of recommendations of 464th SEAC meeting dated 3.10.2020, presentation made by the PP in SEIAA, it was decided to accept the recommendation of SEAC for grant of prior EC to the project subject to the following specific conditions:-

I. Before commencing any mining activity fencing shall be carried out all around the lease area. Proper watch and ward arrangements should be made with installation of signage at 4 corners of lease area to avoid any untoward incident involving public and animals by the PP.

II. PP shall not start mining activity before execution of lease agreement.

III. The depth of the pit shall be as per the Approved Mining Plan.

IV. The entire area shall be fenced and three rows of plantation should be done on the periphery of the boundary.

V. PP shall ensure the proper water supply arrangements for dust suppression, regular sprinkling, plantation and drinking purposes especially in summer season.

VI. PP shall leave 10 m set back from road as no mining zone.

VII. Total1200 saplings of suitable tree species i.e. Neem, Pipal,Bargad,Gulmohar Amla etc. shall be planted in nearby Khasra No. 58 of Kapuri, Tehsil - Sehore, Dist. Sehore ,by PP in three year under plantation programme in consultation with DM at identified revenue land of the district. PP shall also explore and identify the chunk of land in the area from revenue record to carry out plantation programme as proposed.

VIII. PP shall ensure proper implementation of plantation, dust suppression, construction of approach road and maintenance of existing pakka road as

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 174 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020

part of Environmental Management Plan. Additional budget provision shall be made as part of EMP.

IX. PP must ensure implementation of the following activities with separate budget provision of total Rs 3.0 Lakh under CER:

1st ,2nd and 3rd Year

Repair & Construction of Boundary wall & School Farsh of Govt. School, Kapuri

Distribution of Mask & Hand Sanitizer for Primary School Cost of development of grazing land in the village area (Charnoi Bhoomi)

4th and 5thYear

Toilet for school children with 2000L overhead tank with Proper water facility

Construction of one Classroom for the student PP shall give preference to develop/provide infrastructural facilities in schools or aanganwadies of above villages. The modification to the above activities can be made with the permission of the district administration and need based activity for the development of nearby villages shall be implemented by PP in consultation with the District Collector and Gram Panchayat.

X. PP should ensure to submit half yearly compliance report, Plantation and CER activity report along with photographs of all activities in MP-SEIAA. If PP is failed to upload or submit two consecutive half yearly compliance reports of EC conditions to concerned authority (SEIAA and Regional Office, MoEF&CC,GoI,Bhopal) than prior environmental clearance issued to PP will automatically be treated as cancelled/ revoked as per OM No. 930/SEIAA/2019 dated 30.05.2019 issued by MPSEIAA.

Hence, Prior Environmental Clearance is granted for Stone Quarry (Opencast Manual/Semi Mechanized Method) in an area of 1.0 ha. for production capacity of 5761 cum per annum at Khasra No. 176, 177/3 at Village - Kapuri, Tehsil - Sehore, Dist. Sehore (MP) for the lease period to Shri Mukesh Kumar Patel S/o Shri Dhanraj Patel, Village - Kapuri, Dist. Sehore, MP

77. Case No. 7637/20 Prior Environmental Clearance for Stone Quarry (opencast manual/semi mechanized method) in an area of 1.150 ha. (17232 cum per annum) (Khasra No. 5, 74), Village - Jhagrauha, Tehsil - Chitrangi, Dist. - Singrauli (MP) by Smt. Babita Jaiswal W/o Shri Vijendra Jaiswal, R/o Ward No. 3, Chudi Gali Cinema Road, Obra, Dist. - Sonbhadra, UP - 231219, Email - [email protected], Mobile – 9651800001.

This case was recommended in 464th SEAC meeting dated 03.10.2020 and it was recorded that..........

“------------Vide letter dated 28/09/2020 PP has submitted the reply. Committee observed that Tehsildar vide letter dated 24/09/20 has informed that above mine is located on government land and an old excavated pit is in existance where water is accumulated. Committee recommends that since a drain is in existance, PP shall leave 10 meters area both side as

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 175 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020

non mining area. Further PP submitted that 08 trees will be uprooted thus 80 additional trees shall be planted by PP for which PP has submitted the proposal. The other replies submitted by PP were found to be satisfactory and acceptable, hence committee decided to recommend the case for grant of prior EC subject to the following special conditions in addition to the standard conditions at annexure ‘A’:

PP/Consultant made a presentation on all aspects of the project and all concerned issues were discussed in detail. After detailed discussions and perusal of recommendations of 464th SEAC meeting dated 03.10.2020, presentation made by the PP in SEIAA, it was observed from google earth that there are other mines exist within 500 m radius of proposed mine hence it is decided to seek clarification from Mining Officer, Singrauli about current status of other mines exist within 500 m radius of above said mine.

78. Case No 7652/2020 Prior Environment Clearance for Stone Quarry (Opencast Manual / Semi Mechanized Method) in an area of 1.48 ha. (3060 cum per annum) (Khasra No. 109, 111, 112, 115, 116/2), Village - Ratanpur, Tehsil - Shahgarh, Dist. Sagar (MP) by Shri Khurshid Ahamad Qureshi, H.No. 203, Mission Chowk, Dist. katni, MP - 470001,

This case was recommended in 460th SEAC dated 24.09.2020 and PP was called for presentation but PP could not present in the meeting for presentation hence, case is deferred for upcoming SEIAA meeting.

79. Case No 7649/2020 Prior Environmental Clearance for Stone Quarry (Opencast Manual / Semi Mechanized Method) in an area of 1.70 ha. for production capacity of 6687 cum / year at Khasra No. 317 at Village - Belaighat, Tehsil - Sagar, Dist. Sagar (MP) by Shri Avdesh Kumar Sahu, Village - Belaighat, Tehsil & Dist. Sagar, MP - 462008,

This case was recommended in 464th SEAC meeting dated 03.10.2020 and it was recorded that..........

“…………Vide letter dated 28/09/2020 PP has submitted the reply which was found to be satisfactory and acceptable, hence committee decided to recommend the case for grant of prior EC subject to the following special conditions in addition to the standard conditions at annexure ‘A’:”

PP/Consultant made a presentation on all aspects of the project and all concerned issues were discussed in detail. After detailed discussions and perusal of recommendations of 464th SEAC meeting dated 03.10.2020, presentation made by the PP in SEIAA, it was decided to accept the recommendation of SEAC for grant of prior EC to the project subject to the following specific conditions:-

I. Before commencing any mining activity fencing shall be carried out all around the lease area. Proper watch and ward arrangements should be made with installation of signage at 4 corners of lease area to avoid any untoward incident involving public and animals by the PP.

II. PP shall not start mining activity before execution of lease agreement. III. The depth of the pit shall be as per the Approved Mining Plan. IV. The entire area shall be fenced and three rows of plantation should be done

on the periphery of the boundary.

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 176 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020

V. PP shall ensure that the proper water supply arrangements for dust suppression, regular sprinkling, plantation and drinking purposes especially in summer season.

VI. PP shall ensure to construct and maintained the approach road. Plantation will be carried out on both side of approach road.

VII. PP shall ensure proper implementation of plantation, dust suppression, construction of approach road and maintenance of existing road & as part of Environmental Management Plan. Additional budget provision shall be made as part of EMP.

VIII. Total 2550 saplings of suitable tree species i.e. Neem, Pipal, Bargad, Mango, Amla, Amaltas, Drumstick etc. shall be planted by PP at Mine Lease Boundary village area & Khasra no -317 village belaighat tehsil and district Sagar under plantation programme. PP shall also explore and identify the chunk of land in the area from revenue record to carry out plantation programme as proposed.

IX. PP must ensure implementation of the following activities with separate budget provision of Rs 0.75 lakh under CER.

CER activities in village Belaighat

Playground devlopement in village. (Rs. 20,000). Traffic awareness training in village (Rs. 20,000). School building wall white wash and paint (Rs. 10,000). COVID-19 HELP (Rs. 15,000). Cost of devlopment of grazing land in the identified village area charnoi

bhumi (Rs. 11,000). PP shall give preference to develop/provide infrastructural facilities in schools or aganwadies of above villages The modification to the above activities can be made with the permission of the district administration and need based activity for the development of nearby villages shall be implemented by PP in consultation with the District Collector and Gram Panchayat

X. PP should ensure to submit half yearly compliance report and CSR activity report with photographs of plantation in MP-SEIAA. If PP is failed to upload or submit two consecutive half yearly compliance reports of EC conditions to concerned authority (SEIAA and Regional Office, MoEF&CC,GoI,Bhopal) than prior environmental clearance issued to PP will automatically be treated as cancelled/ revoked as per OM No. 930/SEIAA/2019 dated 30.05.2019 issued by MPSEIAA.

Hence, Prior Environmental Clearance is granted for Stone Quarry (Opencast Manual / Semi Mechanized Method) in an area of 1.70 ha. for production capacity of 6687 cum / year at Khasra No. 317 at Village - Belaighat, Tehsil - Sagar, Dist. Sagar (MP) for the lease period to Shri Avdesh Kumar Sahu, Village - Belaighat, Tehsil & Dist. Sagar, MP – 462008

80. Case No. 7495/2020: Application for Environmental Clearance for proposed plotted development and group housing project “Treasure Town and Vihar’ at Village-

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 177 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020

Bijalpur District & Tehsil – Indore (M.P.) Total Plot Area- 3,60120 sq.m. Built up area – 3, 73,152 sq.m by M/s Indore Tresure Town Pvt. Ltd. through Authorised Signatory, Bijalpur District & Tehsil – Indore (M.P.) E-mail:[email protected] Telephone No. 0731-4203010

The case was considered in 643rd SEIAA meeting dtd. 06.10.2020 and recorded that:-

“After recommendation of 461st SEAC meeting dtd. 29.09.2020 today the case was scheduled for the presentation however PP has requested that due to unavoidable circumstances, they are unable to come for presentation and be given another chance. On the request of PP it is decided that, the case is deferred to next upcoming meeting of SEIAA”

Accordingly today the case was scheduled for presentation and after deliberation recorded that:-

1. This is case of Environment Clearance for "Treasure Town and Vihar" Plotted Development and Group Housing Project Total Plot Area - 360120.000 sqm, Total Proposed Built-up Area - 373152 sqm] at Village - Bijalpur, Tehsil & Dist. -Indore (MP).The project proponent is M/s Indore Tresure Town Pvt. Ltd. through Authorised Signatory,

2. The Co-ordinates of the project site are latitude 22°40.5.09”N and longitude 75°50’41.42”E

3. PP stated that this project is <10 KM from Ralamandal sanctuary hence, vide application no. FP/MP/others/5315/2020 dated 28.8.2020 they have applied for NBWL Clearance.

4. The Project comprises of plotted development,group housing and residential units with basic ammenities.

5. As per the approval of T & CP Indore (vide letter no. 4278 dtd 06.07.2019) the total land area of the project is 39.001 ha., The total built up area proposed by PP is –373152 sq. m. The project comes under 8 (b) category (B) of schedule of EIA Notification 2006 because total built up area is more than 1,50,000 sqm.

6. The project is a case of violation on account of not securing prior environment clearance before starting the construction activities at site. The construction work was started at site and before the application was submitted to MPSEIAA for grant of prior environmental clearance.

7. PP stated that this is case of violation and about 60% construction took place. 8. Committee considering the recent GoI, MoEF & CC Notification dated 8th March,

2018 recommends that case may be dealt as per the provisions laid down in this notification and the project may granted Terms of Reference for undertaking Environment Impact Assessment and preparation of Environment Management Plan on assessment of ecological damage, remediation plan and natural and community resource augmentation plan and it shall be prepared as a independent chapter in the EIA report by the accredited consultant and the collection and analysis of data for assessment of ecological damage, preparation of remediation plan and natural and community resource augmentation plan shall be done by an environmental laboratory accredited by the National Accreditation Board for Testing and Calibration Laboratories.

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 178 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020

9. Application for ToR was submitted on 24th August 2020 and the presentation for ToR was made in 457th SEAC meeting dtd. 18th September 2020. PP has submitted the EIA report vide letter dated 20.09.2020 which was sent to SEAC vide letter no. 3277 dated 24.09.2020, which was placed before the committee.

10. The case was discussed in SEAC meetings 461st SEAC meeting dated 29.09.2020 and is recommended for grant of EC subject special conditions and submission of bank gurantee (BG) with 03 years validity of Rs. 22,39,086/- (equivalent to amount proposed in remediation and resource augmentation plan) with the MP Pollution control Board.

11. As per above recommendation PP has submitted BG amount of Rs. 22,39,086 (equivalent to amount proposed in remediation and resource augmentation plan) and decide that the as per recommendation of SEAC the said amout is approved and send to MPPCB for further procedure.

12. After submission of BG today the case was scheduled for presentation and recorded that:

i. Regarding land documents submitted by PP the land is under possession of the M/s Indore Tresure Town Pvt. Ltd. through Authorised Signatory, Bijalpur District & Tehsil – Indore (M.P.)

ii. Total water requirement for the entire project will be 1022 KLD. Fresh water requirement will be 307KLD and recycle water is 715 KLD. The source of fresh water is municipal water supply is available. PP has submitted letter dtd. 08.10.2012 issued by Nagar Nigam, Indore for water supply.

iii. The total 818 KLD waste water will be generated from the project which will be treated in the STP Capacity - 1000 KLD based on MBBR based technology. The treated water 735 KLD available from STP shall be recycled/re-used for flushing & horticulture purpose. Extra treated water of 20.0 KLD will be drained to sewer line of IMC. PP has submitted letter dtd. 08.10.2012 issued by Municipal Corporation, Indore for disposal of extra treated waste water.

iv. The Municipal Solid Waste approx. 3785 Kg/day this consist all types of wastes as domestic waste, Horticulture Waste, e- waste etc shall be generated. Generated Solid waste are being segregated & collected and temporarily stored at common solid waste collection center inside the project premises for having a capacity of 48 hour garbage storage, then picked up by hired waste management/ municipal agency for their treatment and disposal. The recyclable inorganic & e-waste wastes will be sold to authorized buyers and inert waste will be used for construction of road & pavement. Biodegradable segregated garden liter along with STP sludge will be transported to the compost site for bio composting and energy recovery. Hazardous waste (Spent/ Used Oil) & e-waste will be stored at separate place and handover to authorized dealers of CPCB.PP has submitted letter dtd. 08.10.12 issued by Municipal Corporation, Indore for disposal of solid waste.

v. For rainwater harvesting, 23 recharge pits will be constructed for harvesting rain water. The Mesh will be provided at the roof so that leaves or any other solid waste/debris will be prevented from entering the pit.

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 179 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020

vi. PP has proposed the maximum height of the building is 18m. PP has provided width of Width of main assess 9.0 m, Front MOS 12.0 m and Rear 9.0.

vii. Total Power requirement of the project is 5300 KW. The power shall be supplied by Madhya Pradesh Madhya Kshetra Vidyut Vitran Company Limited. There is a provision of DG set with AMF Panel of 50 KVA in 23 no, 15KVA in 2 no & 24 KVA in 9 no. The proponent has taken various energy conservation measures which include:

Window-wall ratio are balanced perfectly to achieve maximum daylight, no glare and minimum heat ingress

Regional and eco friendly materials were used. Aluminum used have recycled content.

Flyash based cement was used. Public areas will be cooled by natural ventilation as opposed to air

conditioning. LEDs are being used for high efficiency in the common areas. Maximization of use of natural lighting through building design. Use of Solar Water Heating in group housing as per requirement. Solar lighting has been provided in common areas & streets. Sunscreen films on windows to reduce heating inside buildings

viii. Systematic circulation of internal traffic has been designed for the township Access roads for driveways have been proposed to be provided to facilitate the free flow of traffic movement inside the premises

All gates are manned with efficient security who can guide the entry and exit of vehicles.

Merging of vehicles will be performed only to left traffic from the exit gates and this ensures safety

ix. Adequate provisions are made for car/vehicle parking for the Project. There are also adequate parking provisions for visitors so as not to disturb the traffic and allow smooth movement at the site. PP has proposed total car parking 1795 ECS (Stilt- 829 ECS, ,Open-966 ECS)

x. Adequate fire protection facilities will be installed including fire detectors, fire alarm and fire fighting system to guard the building against fires. All fire protection facilities will be designed as per the National Building Code given in 2005.

Wet riser system Internal fire hydrants strategically located to cover maximum area. Fire pump, Sprinkler pump, Jockey pump Sprinklers system Two-way communication system. External yard hydrants Portable fire extinguishers Addressable microprocessor based fire alarm and detection system Smoke detectors above and below false ceiling spaced as per NFPA

standards (500 Sft coverage per detector)

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 180 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020

xi. Total green area proposed for the project is 73847.50 sq. m. by planting 3500 numbers of trees in 2 rows periphery plantation The species were planted on site are Ashok, Neem, Kusum, Amaltas, Kachnar, Kanchan, Champa, Amlaetc.

xii. PP has submitted the remediation plan and natural community resource augmentation plan corresponding to the ecological damage assessed and economic benefits derived due to violation in the tune of suggested guidelines by the committee, with the supported by documentary proofs, such as bills, CA audit, certificates, photographs, prescribed various undertakings.

xiii. PP has proposed Rs. 6,91,69,855 (Rs. 22,39,086 as Remediation Cost and Rs. 6,69,30,769 as EMP) for this project. PP has submitted bank guarantee of INR Rs. 22,39,086 towards Remediation Plan. As per recommendation of SEAC it is decided to approved the remediation plan and bank guarantee of INR 22,39,086 /- towards Remediation Plan and Natural & Community Resource Augmentation Plan and send to MPPCB for further action.

xiv. PP has proposed to submit bank guarantee of INR 22,39,086 towards Remediation Plan and Natural & Community Resource Augmentation Plan with following expenditure:-

Activity Remark Total First Year

(INR) Second

Year (INR) Third Year

(INR) (INR)

1. Environmental Management

Plantation of trees along the roadside area

inside or outside the project

Plantation of trees near

project site or any other nearby

projects

10,00,000

- 10,00,000

2. Community resource development

Help of municipal authority for

maintenance of already developed park in surrounding area.

Development of

park 2,39,086

- 2,39,086

3. Natural resources augmentation

Solar street light /led in nearby road side

50 @ Rs 25,000/ pieces

12,50,000 2,25,000 5,00,000 5,00,000

Total remediation cost (1+2+3)

22,39,086 2,50,000 5,00,000 17,39,086

Project Benefit: The proposed project makes a positive contribution to social infrastructure and over all residential development. The project also provides positive benefits such as employment for a significant number of persons; many of whom got employment from the residing community as well as surrounding area. Additionally, the cumulative effects of this type of development would result in noticeable economic benefits for the area.

xv. Under CER activities PP has proposed Rs. 2.00 crore up to three years for the following activities:

S.No. Activity Remark Total Cost 1st Year 2nd Year 3rd Year

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 181 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020

(INR) (INR) (INR) (INR) 1 Donation in

Nearby Hospitals for COVID care.

Indira Memorial hospital & Government Hospital Polio Point, Rajendra Nagar main road.

1,00,00,000 40,00,000 40,00,000 20,00,000

2 Water purification system in Bijalpur Village & Schools/ Aanganbadi.

50 cooler @ Rs. 35,000/ cooler

17,50,000 - 2,50,000

15,00,000

3 Development of RWH Pits at Bijalpur Government schools / Aanganbadi.

- 32,50,000 - 32,50,000

4 Solar Panels Installations

50,00,000 50,00,000

Total 2,00,00,000 40,00,000 92,50,000 62,50,000 The submissions made by the PP were found to be satisfactory and acceptable hence It is decided to accept the recommendations of 461st SEAC meeting dtd. 29.09.2020 with special conditions and accord Environnemental Clearance for the proposed plotted development and group housing project “Treasure Town and Vihar’ at Village- Bijalpur District & Tehsil – Indore (M.P.) Total Plot Area- 3,60120 sq.m. Built up area – 3, 73,152 sq.m by M/s Indore Tresure Town Pvt. Ltd. through Authorised Signatory, Bijalpur District & Tehsil – Indore (M.P.), subject to following specific conditions imposed by SEIAA:-

1. The fresh water supply arrangement should be met through Municipal Corporation, Indore (as per IMC letter dtd.08.10.12) and there should no extraction of ground water.

2. The inlet and outlet point of natural drain system should be maintained with adequate size of channel for ensuring unrestricted flow of water.

3. Disposal of waste water.

a. PP should ensure disposal of waste water arrangement should be done in such a manner that water supply sources are not impaired.

b. PP should ensure to linkage with Nagar Nigam Indore (letter dtd. 08.10.12) for sewer line for disposal of extra treated waste water.

c. The project not having provision for discharge of excess treated sewage cannot permit to start operation unless proper arrangements are put in place for its safe handling.

4. Solid Waste Management:

a. Separate wet and dry bins must be provided at the ground level for facilitating segregation of waste.

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 182 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020

b. The solid waste generated should be properly collected and segregated. Wet garbage should be composted and dry inert solid waste should be disposed off to the approved sites for land filling after recovering recyclable material.

c. Ensure linkage with Municipal Corporation Indore (letter dtd.08.10.12) for final disposal of MSW.

5. PP should ensure building height, road width, front MOS and side / rear as per approved layout of T & CP.

6. For firefighting:-

PP should ensure distance of fire station approachable from the project site & provide fire fighting measures such as water sprinklers, fire hydrant pipe, Adequate firefighting requirement shall be taken into account while designing the electrical distribution system, Wet risers and hose reel, Adequate numbers of fire extinguishers, and underground water storage tank. properly as per NBC 2005. PP should obtain fire fighting NOC from concerned department.

7. For Rain Water Harvesting, and Storm water management:-

PP should ensure the rain water harvesting with 23 recharging pits and these pits should be connected laterally to consume the surplus runoff. In addition, PP should provide recharging trenches. The base of the trenches should be Kachha with pebbles. PP should also ensure to make arrangements for the flushing of first rain water to ensure that only clean water enters the recharge system.

8. Car Parking:-

PP has proposed total car parking car parking 1795 ECS (Stilt- 829 ECS, Open- 966 ECS). The parking area should not be diverted for any other activities.

9. Green belt :-

PP should ensure plantation in an area of 73847.50 sq. m. by planting 3500 numbers of trees as a green belt and landscaped area with regular maintenance and also explore the possibility to plant trees of indigenous local varieties like Ashok, Neem, Kusum, Amaltas, Kachnar, Kanchan, Champa, Amla etc.

10. PP should ensure to complete the activities listed under ecological remediation, Natural resource augmentation & community resource augmentation for a total amount of Rs. 22,39,086 /- .

11. PP shall carry out the works assigned under ecological damage, natural resource augmentation and community resource augmentation within a stipulated period and submitted to same in MPSEIAA.

12. PP should ensure the implementation of CER activities to the extent of Rs. 2.00 crore up to three years for Donation in Nearby Hospitals for COVID care Water purification system in Bijalpur Village & Schools/ Aanganbadi, Development of RWH Pits at Bijalpur Government schools / Aanganbadi. Solar Panels Installations to the schools in consultation with district administration.

81. Case No 5789/2018:Environmental Clearance for proposed Residential Building at Khasra No. 537 Village Rangwasa Taluka &District Indore, MP, Total Plot Area : 24021 sq.m and, Total Built- up area 28433 sq.m. by Director, M/S SATYAMITRA

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 183 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020

INFRASTRUCTURE PVT.LTD 247,Prem Trade Centre, Maharani Road, Indore (MP) E-mail: [email protected] Telephone No. 9010529529

1. The project is proposed for construction of Residential Building located at Khasra No. 537 Village Rangwasa Taluka &District Indore, MP. The project proponent is Director, M/S SATYAMITRA INFRASTRUCTURE PVT.LTD,

2. The Co-ordinates of the project site are Latitude 22°39‘15.51"N and longitude 75°48‘0.58"E

3. PP stated that this project is >10 KM from Ralamandal sanctuary. 4. The Project comprises of,group housing flats-312 unit,Row houses- 81 commercial

shop-11,EWS unit and club house. 5. As per the approval of T & CP Indore (vide letter no. 620 dtd 20.03.2012) the total

land area of the project is 2.4047ha., The total built up area proposed by PP is –28433 sq. m. The project comes under 8 (a) category (B) of schedule of EIA Notification 2006 because total built up area is less than 1,50,000 sqm.

6. The project is a case of violation on account of not securing prior environment clearance before starting the construction activities at site. The construction work was started at site and before the application was submitted to MPSEIAA for grant of prior environmental clearance.

7. PP stated that this is case of violation and about 80% construction took place.

Type of dwelling units

Unit proposed

Posses ssion given

Unit incomplete

Unit completed

Percentage

Row houses 312 60 216 96 31

Commercial shops

81 60 18 63 77

11 9 0 2 82

8. Committee considering the recent GoI, MoEF & CC Notification dated 8th March, 2018 recommends that case may be dealt as per the provisions laid down in this notification and the project may granted Terms of Reference for undertaking Environment Impact Assessment and preparation of Environment Management Plan on assessment of ecological damage, remediation plan and natural and community resource augmentation plan and it shall be prepared as a independent chapter in the EIA report by the accredited consultant and the collection and analysis of data for assessment of ecological damage, preparation of remediation plan and natural and community resource augmentation plan shall be done by an environmental laboratory accredited by the National Accreditation Board for Testing and Calibration Laboratories.

9. Application for ToR was submitted on 13th November 2018 and the presentation for ToR was made in 333th SEAC meeting dtd. 29th November 2018. PP has submitted the EIA report vide letter dated 14.07.2020 which was sent to SEAC vide letter no. 1871 dated 25.07.2020, which was placed before the committee.

10. The case was discussed in SEAC meetings 457th SEAC meeting dated 18.09.2020 and is recommended for grant of EC subject special conditions and

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 184 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020

submission of bank gurantee (BG) with 03 years validity of Rs. 16,26,605/- (equivalent to amount proposed in remediation and resource augmentation plan) with the MP Pollution control Board.

11. As per above recommendation PP has submitted BG amount of Rs. 16,26,605/- (equivalent to amount proposed in remediation and resource augmentation plan) and decide that the as per recommendation of SEAC the said amout is approved and send to MPPCB for further procedure.

12. After submission of BG today the case was scheduled for presentation and recorded that: i. Regarding land documents submitted by PP the land is under possession of

the SATYAMITRA INFRASTRUCTURE PVT.LTD through Director,Shri Pramod S/o Shri Shivramji Khandelwal and Shri Satyendra S/o Shri Ram Chandra Bhawsar . PP has submitted sale deed dtd. 1304.2011. As per the sale deed the said land was purchased by SATYAMITRA INFRASTRUCTURE PVT.LTD from Shri Devram S/o Shri Ram Ratanji.

ii. The total water requirement during operation phase is 268 KLD out of which 156 KLD is fresh water requirement and 192 KLD will be the total recycled water generated. 90 KLD recycled water will be used for flushing and, while 17 KLD water will be used for horticulture.The source of fresh water is Gram Panchyat water supply is available. PP has submitted letter dtd. 06.08.2018 issued by office of the Gram Panchayat Rangwasa Janpad district Indore for water supply.

iii. The total 214 KLD waste water will be generated from the project which will be treated in the STP Capacity - 250 KLD based on MBBR based technology. The treated water 192 KLD available from STP shall be recycled/re-used for flushing & horticulture purpose. Extra treated water of 80.0 KLD will be drained to sewer line of IMC. PP has submitted letter dtd. 06.08.2018 issued by office of the Gram Panchayat Rangwasa Janpad district Indore for for disposal of extra treated waste water.

iv. The Municipal Solid Waste approx. 1006 Kg/day this consist all types of wastes as domestic waste, Horticulture Waste, e- waste etc shall be generated. Generated Solid waste are being segregated & collected and temporarily stored at common solid waste collection center inside the project premises for having a capacity of 48 hour garbage storage, then picked up by hired waste management/ municipal agency for their treatment and disposal. The recyclable inorganic & e-waste wastes will be sold to authorized buyers and inert waste will be used for construction of road & pavement. Biodegradable segregated garden liter along with STP sludge will be transported to the compost site for bio composting and energy recovery. Hazardous waste (Spent/ Used Oil) & e-waste will be stored at separate place and handover to authorized dealers of CPCB.PP has submitted letter dtd. 06.08.18 issued by issued by office of the Gram Panchayat Rangwasa Janpad district Indore for disposal of solid waste.

v. For rainwater harvesting, 06recharge pits will be constructed for harvesting rain water. The Mesh will be provided at the roof so that leaves or any other solid waste/debris will be prevented from entering the pit.

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 185 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020

vi. PP has proposed the maximum height of the building is 18m. PP has provided width of approach road 12.0m, Width of internal road .7.50 m, Front MOS 9.0 m and Rear 7.50m.

vii. Total Power requirement of the project is 1675 KW. The power shall be supplied by Madhya Pradesh Madhya Kshetra Vidyut Vitran Company Limited. There is a provision of DG set with 250 KVA (250 KVA x 1). The proponent has taken various energy conservation measures which include:

Window-wall ratio are balanced perfectly to achieve maximum daylight, no glare and minimum heat ingress

Regional and eco friendly materials were used. Aluminum used have recycled content.

Flyash based cement was used. Public areas will be cooled by natural ventilation as opposed to air

conditioning. LEDs are being used for high efficiency in the common areas. Maximization of use of natural lighting through building design. Use of Solar Water Heating in group housing as per requirement. Solar lighting has been provided in common areas & streets. Sunscreen films on windows to reduce heating inside buildings

viii. Systematic circulation of internal traffic has been designed for the township Access roads for driveways have been proposed to be provided to facilitate the free flow of traffic movement inside the premises

All gates are manned with efficient security who can guide the entry and exit of vehicles.

Merging of vehicles will be performed only to left traffic from the exit gates and this ensures safety

ix. Adequate provisions are made for car/vehicle parking for the Project. There are also adequate parking provisions for visitors so as not to disturb the traffic and allow smooth movement at the site. PP has proposed total car parking 286 ECS (Stilt- 154 ECS, ,Open-132 ECS)

x. Adequate fire protection facilities will be installed including fire detectors, fire alarm and fire fighting system to guard the building against fires. All fire protection facilities will be designed as per the National Building Code given in 2005.

Wet riser system Internal fire hydrants strategically located to cover maximum area. Fire pump, Sprinkler pump, Jockey pump Sprinklers system Two-way communication system. External yard hydrants Portable fire extinguishers Addressable microprocessor based fire alarm and detection system Smoke detectors above and below false ceiling spaced as per NFPA

standards (500 Sft coverage per detector)

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 186 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020

xi. Total green area proposed for the project is 2403.53 sq. mt. (10 % of net plot area). by planting 250 numbers of trees in 2 rows periphery plantation The species were planted on site are Ashok, Neem, Kusum, Amaltas, Kachnar, Kanchan, Champa, Amlaetc.

xii. PP has submitted the remediation plan and natural community resource augmentation plan corresponding to the ecological damage assessed and economic benefits derived due to violation in the tune of suggested guidelines by the committee, with the supported by documentary proofs, such as bills, CA audit, certificates, photographs, prescribed various undertakings.

xiii. PP has submitted bank guarantee of INR 16,26,605 towards Remediation Plan and Natural & Community Resource Augmentation Plan with following expenditure:-

Activity Remark Total First Year

(INR) Second

Year (INR) Third Year

(INR) (INR)

1. Environmental Management

Plantation of trees along the roadside area

inside or outside the project

Plantation of trees near

project site or any other nearby

projects

11,00,000

- 11,00,000

2. Community resource development

Help of municipal authority for

maintenance of already developed park in surrounding area.

Development of

park 2,26,605

- 2,26,605

3. Natural resources augmentation

Solar street light /led in nearby road side

12 @ Rs 25,000/ pieces

3,00,000 1,00,000 1,00,000 1,00,000

Total remediation cost (1+2+3)

16,26,605 2,00,000 2,00,000 12,26,605

Project Benefit: The proposed project makes a positive contribution to social infrastructure and over all residential development. The project also provides positive benefits such as employment for a significant number of persons; many of whom got employment from the residing community as well as surrounding area. Additionally, the cumulative effects of this type of development would result in noticeable economic benefits for the area.

xiv. Under CER activities PP has proposed Rs. 95.78 lakh up to three years for the following activities:

S.No. Activity Remark Total Cost

(INR) 1st Year (INR)

2nd Year (INR)

3rd Year (INR)

1 Donation in Nearby Hospitals for COVID care.

Consultation with nearby hospitals

40,00,000 20,00,000 20,00,000

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 187 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020

2 Water purification system in nearby Schools

50 cooler @ Rs. 35,000/ cooler

15,78,000 -

15,78,000

3 Plantation along with roads.

- 20,00,000 - 20,00,000

4 Solar Panels Installations

20,00,000 20,00,000

Total 95,78,000 20,00,000 40,00,000 35,78,000

The submissions made by the PP were found to be satisfactory and acceptable hence It is decided to accept the recommendations of 457th SEAC meeting dtd. 18.09.2020 with special conditions and accord Environnemental Clearance for the proposed Residential Building at Khasra No. 537 Village Rangwasa Taluka &District Indore, MP, Total Plot Area : 24021 sq.m and, Total Built- up area 28433 sq.m. by Director, M/S SATYAMITRA INFRASTRUCTURE PVT.LTD 247,Prem Trade Centre, Maharani Road, Indore (MP), subject to following specific conditions imposed by SEIAA:-

1. PP should explore the possibility fresh water supply arrangement from Municipal Corporation, Indore and there should no extraction of ground water.

2. The inlet and outlet point of natural drain system should be maintained with adequate size of channel for ensuring unrestricted flow of water.

3. Disposal of waste water.

a. PP should ensure disposal of waste water arrangement should be done in such a manner that water supply sources are not impaired.

b. PP should explore the possibility to linkage with Nagar Nigam Indore for sewer line for disposal of extra treated waste water.

c. The project not having provision for discharge of excess treated sewage cannot permit to start operation unless proper arrangements are put in place for its safe handling.

4. Solid Waste Management:

a. Separate wet and dry bins must be provided at the ground level for facilitating segregation of waste.

b. The solid waste generated should be properly collected and segregated. Wet garbage should be composted and dry inert solid waste should be disposed off to the approved sites for land filling after recovering recyclable material.

c. PP should explore the possibility to linkage with Municipal Corporation Indore for final disposal of MSW.

5. PP should ensure building height, road width, front MOS and side / rear as per approved layout of T & CP.

6. For fire fighting:-

PP should ensure distance of fire station approachable from the project site & provide fire fighting measures such as water sprinklers, fire hydrant pipe,

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 188 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020

Adequate firefighting requirement shall be taken into account while designing the electrical distribution system, Wet risers and hose reel, Adequate numbers of fire extinguishers, and underground water storage tank. properly as per NBC 2005. PP should obtain fire fighting NOC from concerned department.

7. For Rain Water Harvesting, and Storm water management:-

PP should ensure the rain water harvesting with 06 recharging pits and these pits should be connected laterally to consume the surplus runoff. In addition, PP should provide recharging trenches. The base of the trenches should be Kachha with pebbles. PP should also ensure to make arrangements for the flushing of first rain water to ensure that only clean water enters the recharge system.

8. Car Parking:-

PP has proposed total car parking car parking 286 ECS (Stilt- 154 ECS, , Open-132 ECS) The parking area should not be diverted for any other activities.

9. Green belt :-

PP should ensure plantation in an area of 2403.53 sq. mt..by planting 250 numbers of trees as a green belt and landscaped area with regular maintenance and also explore the possibility to plant trees of indigenous local varieties like Ashok, Neem, Kusum, Amaltas, Kachnar, Kanchan, Champa, Amla etc.

10. PP should ensure to complete the activities listed under ecological remediation, Natural resource augmentation & community resource augmentation for a total amount of Rs. 16,26,605/- .

11. PP shall carry out the works assigned under ecological damage, natural resource augmentation and community resource augmentation within a stipulated period and submitted to same in MPSEIAA.

12. PP should ensure the implementation of CER activities to the extent of Rs. 95,78,000 up to three years for Donation in Nearby Hospitals for COVID care Water purification system in Bijalpur Village & Schools/ Aanganbadi, Development of RWH Pits at Bijalpur Government schools / Aanganbadi. Solar Panels Installations to the schools in consultation with district administration.

82. Case No. 5689/2018: Environment Clearance for “Group Housing Project “Royal Amar Greens”at Khasra No. 37/1/2, 38/1, 38/2 min 1, 38/2 min 2, 38/2 min 3, 38/2 min 4, 38/2 min 5, 39/1/1, 39/1/2, 39/1/3, 39/2 min 1, 39/2 min 2, 39/2 min 3, 39/2 min 4 and 39/2 min 5 Village Niranjanpur Tehsil Indore District Indore M.P. Total Plot Area: 20350.0 m 2 Net Plot Area: 19405.0 sq.m Built-up Area: 67100.423 sq.m Built-up Area Constructed: 34526.54 sq.m by M/s Man Developments through Partner Mr. Rajendra Kumar Mansukhani G-9, Man Heritage, 6/2 South, Tukoganj, Indore (M.P.) - 452001 E-mail [email protected] Telephone No. +91-98270-29900 Envt. Consultant: EQMS India Pvt. Ltd.

The case was discussed in 578th SEIAA meeting dtd. 23.10.2019 and recorded that:-

1. This is case of Prior Environment Clearance for Group Housing Project ‘’Royal Amar Greens’’; at Khasra Nos. 37/1/2, 38/1, 38/2 min 1, 38/2 min 2, 38/2 min 3,

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 189 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020

38/2 min 4, 38/2 min 5, 39/1/1, 39/1/2, 39/1/3, 39/2 min 1, 39/2 min 2, 39/2 min 3, 39/2 min 4, 39/2 min 5, at Village - Niranjanpur, Tehsil - Indore, Distt. - Indore, (M.P.), Total Plot Area: 20350.0 sqm, Net Plot Area: 19405.0 sq.m, Built-up Area: 67100.423 sq.m, Built-up Area Constructed: 39843.55 sq.m.

2. As per the approval of T & CP Indore (vide L. No. 2344/S.P.604/10/Na. Gra. Ni./2011 dtd 08.04.11) the total land area is 20,350 sq.m.(2.035 ha) at Village –Niranjanpur, Tehsil – Indore, Distt. –Indore (M.P.). The total built up area proposed by PP is 45,159.98 sq m (Form-1 & 109th SEAC meeting dtd 06.11.12). The project comes under 8 (a) category (B) of schedule of EIA Notification, 2006 as the total construction is between 20,000 sqmt. & 1,50,000 sqmt. The project includes development of residential Complex (Group Housing) (P+6 floor) 10 Blocks.

3. Chronology of the project:

M/s Man Developments has planned a group housing project “Royal Amar Greens” located at Village- Niranjanpur, District Indore, M.P.

Project site is spread over 20350 sq m (5.028 acres) and will have built-up area of 67100.423 sq m. Project comprise of 4 blocks comprising of 11 residential towers, EWS & LIG housing and club along with allied facilities.

Till date 6 no. of towers are constructed and built up area of 39843.55 sq. m. is constructed.

M/s Man Developments has obtained approval from Town and Country Planning (T&CP), M.P. for development of the project in 2011. Due to change in the project planning, layout was revised again in 2016 and approval was taken from the Indore Municipal Corporation (IMC) vide letter dated 15th September, 2016.

4. Details of violation

M/s Man Developments has submitted application to obtain environment clearance to SEIAA, M.P. on 12.07.2012.

After that the case was appraised by SEAC in 104th, 106th, 109th and 119th SEAC meeting and SEAC recommended the project for grant of environment clearance in its 119th SEAC meeting held on 02.02.2013.

Project was then considered in 127th, 141st, 146th SEIAA meeting and then the SEIAA, M.P. got dissolved in November, 2013 after completion of tenure of 3 years.

SEIAA was formed in July, 2014 and project was considered in 161st SEIAA meeting held in June, 2014 and thereafter in 204th, 211th& 214th SEIAA meeting.

In 214th SEIAA meeting, SEIAA considered it as violation and thus recommended SEAC to conduct a site visit.

Case was then considered in the 227th SEIAA meeting and therein SEIAA asked proponent to submit the details as per MoEF&CC memorandum dated 12.12.2012 and initiated the credible action process against the proponent.

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 190 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020

Also there was a notice of NGT dated 7.07.2016 regarding violation cases and on the basis of the notice the project was kept on abeyance by SEIAA in 274th SEIAA meeting.

A letter dated 1.1.2016 was sent by SEIAA to SEAC to conduct site visit to know status of construction at the site and the site visit was conducted by SEAC in February, 2016 and SEAC reported the status of construction at the site in its 277th meeting and send it to SEIAA for further action.

SEIAA took up the case in 345th meeting and suggested to keep project on abeyance due to MoEF&amp;CC draft notification dated 10.05.2016 related to violation cases.

All the violation cases were declared on abeyance again by SEIAA in 352nd meeting and closed all the violation cases in its 417th meeting held on 20.03.2017.

Then application for grant of environment clearance was submitted to MoEF& CC as per MoEF&;CC Notification 804 (E) dated 14.03.2017. Thereafter MoEFC & CC has issued amendment SO 1030 dated 8th March, 2018 and has directed that Category B projects involving violation will be appraised at State Level and all the category B proposals will be transferred to SEIAA. In view of this MOEF&;CC transferred our project to SEIAA, MP on 28th March, 2018.

5. ToR was granted to the project by SEAC/SEIAA, M.P. vide letter no 207/PS-MS/MPPCB/SEAC/TOR(319)/2018 dated 10/7/2018. EIA for the project was submitted on 24.12.2018.

6. The case was discussed in SEAC meetings 359th dtd.10.04.19 and 398th dtd. 04.10.19 is recommended for grant of prior EC subject special conditions.

7. PP has submitted the remediation plan and natural community resource augmentation plan corresponding to the ecological damage assessed and economic benefits derived due to violation in the tune of suggested guidelines by the committee, with the supported by documentary proofs, such as bills, CA audit, certificates, photographs, prescribed various undertakings and CER.

8. PP has proposed Rs. 30,98, 200.00 Lakhs as Remediation Cost and Rs.29,12,000.00 Lakhs as EMP for this project and PP, M/s Man Developments, has proposed tosubmit bank guarantee of INR Rs. Rs. 30,98,200.00 Lakhs towards Remediation Plan and Rs.23,20,000.00 Lakhs capital cost and Rs. 5,92,000.0 Lakh as recurring cost for EMP of this project.

After deliberation it was observed by the authority PP has not proposed adequate measure in the remediation plan corresponding to the ecological damage assessment with respect to air, water, land and other environmental attributes. Hence it is decided that PP should submit revised remediation plan incorporating all environmental issues.

The case was discussed in 581 SEIAA meeting dtd. 14.11.2019 and recorded that:-

“After deliberation it was observed by the authority PP has not proposed adequate measure in the remediation plan corresponding to the ecological damage assessment with

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 191 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020

respect to air, water, land and other environmental attributes. Hence it is decided that PP should submit revised remediation plan incorporating all environmental issues”.

In response to above vide letter dtd. 13.11.19 received in SEIAA office on 13.11.19 PP has submitted revised remediation plan incorporating all environmental issues. Further under CER activities, PP has proposed to construction/modernization work for the Mahesh Drishtiheen Kalyan Sangh by providing Rs. 10 Lakh financial support. The submission made by PP was found satisfactory and decided that PP should deposit the bank guarantee (BG) with three years validity of Rs. 30,98,200.00 Lakhs (equivalent to amount proposed in Remediation Plan /Restoration Plan) with the MP Pollution control Board as per the procedure laid down in the MoEF&CC Notification dated 08/03/2018.

In response to above vide letter dtd. 06.10.2020 received in SEIAA office on 06.10.2020 PP has submitted bank guarantee (BG) with three years validity of Rs. 30,98,200.00 (equivalent to amount proposed in Remediation Plan /Restoration Plan) and requested for re-list the case for further consideration. Accordingly the case was scheduled for consideration and after detail discussion it is recoded that:-

i. Project site belongs to M/s Man Developments through Partner Mr. Rajendra Kumar Mansukhani and M/s Amardeep Builders are developers of the project. Man Developments and Amardeep Builders have entered into a ratio joint development agreement for the development of project.

PP has submitted copy of sale deed dtd. 31.03.2010. As per sale deed the said land was purchased by M/s Amardeep Builders.. through Partner Shri Pawan Agrawal. A joint development agreement has been made on 30.03.2011 between M/s Amardeep Builders. through Partner shri Pawan Agrawal and M/s Man Developments through Partner Mr. Rajendra Kumar Mansukhani and Shri Umesh Lilani for development of the project.

ii. No major source of air pollution during operation phase. A small DG of 250 kVA is provided at the site. This will provide power back-up only for essential utilities like STP, Water supply etc. Green area developed is and will properly being maintained and managed. Ambient air quality monitoring will be done every six monthly

iii. Total water requirement of the project is estimated to be approx. 330 KLD, out of which domestic water requirement is 315 KLD. Fresh water requirement for the project is approx. 226 KLD (Consumption: 221 KLD, Swimming pool: 5 KLD). Recycled water requirement for the project is 104 KLD (Flushing:94 KLD, Landscaping: 10 KLD). Source of water during operation phase is ground water/Municipal corporation,Indore PP has has been taken permission(letter dtd 31.08.15) from District collectorate, Indore for withdrawl of ground water and NOC from IMC (letter dtd.01.06.2015 ) for water supply.

iv. Sewage generation from the project site during operation phase is approx. 271KLD. A STP of 325 KLD is required for treatment of sewage at the site. Dual plumbing system for re-usage of STP treated water for flushing and horticulture.It is estimated 216 KLD of water will be recovered after treatment in STP out of which 94 KLD will be used in flushing, 10 KLD in horticulture (Within Site) and 30 KLD Maintaining Park outside the project site.Excess 82 KLD of water is discharged into sewer. This excess water may also be used for green belt along the roads or may be given to nearby construction site for construction purpose. Permission of discharge of excess treated sewage to sewer is granted by Indore Municipal Corporation (letter dtd 14.06.12). STP of 250 KLD is already installed at site and rest 125 KLD STP will be installed in second phase of construction.

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 192 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020

v. The Municipal Solid Waste approx. 1232 Kg/day, this consist all types of wastes (as recyclable waste 361 Kg/day and non- recyclable waste 871Kg/day) –Generated Solid waste are being segregated & collected and temporarily stored at common solid waste collection center inside the project premises for having a capacity of 48 hour garbage storage, then picked up by hired waste management/ municipal agency for their treatment and disposal. Rejected fraction of the waste is collected and disposed by local agencies on daily basis and will be disposed at the locations designated by Indore Municipal Corporation. Permission is given by IMC (letter dtd 03.08.13) to dispose the solid waste from the project site..

vi. Storm water drainage system is provided at project site for channelizing storm water and prevents local flooding. Covered storm water drains are provided at the site. Run-off from the site is collected and recharged into the ground through RWH pits. For rainwater harvesting, 03 recharge pits & 1 tank will be constructed for harvesting rain water.

vii. Power requirement for the entire project is 2290 kVA and it will be supplied by Madhya Pradesh State Electricity Board (MPSEB). DG sets of total capacity 250 kVA DG sets are open to air, air cooled & are provided with acoustic enclosure. The proponent has taken various energy conservation measures which include: Energy efficient lifts installed at the site All the electrical fittings and lighting is 5 BEE star rated Usage of low energy embodied locally available construction material. Usage of fly ash

bricks, hollow bricks and fly ash mix cement for construction purpose. Usage of excavated soil and construction debris within the project site as filling material

Green belt and greenery developed around the project periphery Usage of AAC blocks in building construction Painting wall with white/light colour heat reflecting paint LED lights are used for common area. Detailed calculation is given below:

S. No. Energy Saving Measure Energy saving (kVA)

1 LED lights for lighting in common areas 3.6

2 LED lights for internal lighting 189

3 Total energy saving 192.6

4 Power requirement 1832

Energy Saving percentage 10.5%

viii. Road construction has been undertaken in the project site to facilitate movement of the vehicles expected at the site. Internal roads of adequate width /pedestrian pathways are developed in the project site. Road are designed so as they can bear the expected vehicle load and also width is as per NBC standards for movement of fire tender.

ix. PP has proposed to provide fire fighting provisions with hose reel, hose, wet riser, automatic sprinkler system in entire building, manual call points, automatic fire detection system in entire buildings, underground water storage tank, overhead water tank, fire pumps, potable fire extinguishers, exit signs, P.A. System, Yard Hydrants etc. as per NBC 2005.

x. Parking facility is provided as per the By Laws of MPBVN. No parking will be done outside the site which will not lead to congestion at entry exit point. Parking space provision for visitors is also kept for the visitors. Roads of adequate width are provided as per MPBVN.

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 193 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020 PP has proposed total car parking 438 ECS (Basement Parking –196 ECS Stilt Parking- 142 ECS ;

xi. Total area measuring 3280 m2 i.e. 17 % of the net plot area is proposed to be put under green cover. Out of 3280 sq m, approx. 2136 sq m is already developed at the site.

xii. PP has submitted the remediation plan and natural community resource augmentation plan corresponding to the ecological damage assessed and economic benefits derived due to violation in the tune of suggested guidelines by the committee, with the supported by documentary proofs, such as bills, CA audit, certificates, photographs, prescribed various undertakings.

xiii. PP has proposed to submit bank guarantee of INR 30,98,200.00 towards Remediation Plan and Natural & Community Resource Augmentation Plan with following expenditure:-

Activity Total (INR)

First Year (INR)

Second Year (INR)

Third Year (INR)

Greenery within the site will be enhanced as remediation for remediating the ecological impacts of the site. No of trees will be increased at the site

1500000 250000 250000 1000000

Installation of solar lights within the site for promoting the solar energy usage-Provision of 20 nos. of solar lights within the site

500000 250000 -- 250000

Replacing the single dustbins with the twin color dustbins with trolleys at the site for at source segregation of the waste-11 sets (22 nos.)

110000 55000 -- 55000

Provision of signage within the site for enhancing awareness among the residents and staff on energy conservation, waste management and water conservations

50,000 -- -- 50,000

Improvement of fire safety signage and notices in the building for enhancing awareness on fire hazards 50,000 -- -- 50,000

Replacing the CC areas with the pavers at site in common areas for enhancing the ground water recharge (only in non-basement areas)

8,50,000 350000 350000 1,50,000

Installation of fire hooter/alarm in the club room as per recommendation of SEAC and improving infrastructure for specially abled people in the club (Not required as per the Fire Norms for club room)

40,000 -- -- 40,000

Total 31,00,000 9,05,000 6,00,000 15,95,000

xiv. Total Project Cost of the project is : Rs. 44 Crores Under CER activities PP has proposed cost for the total project As per CER OM, CER cost is 2 % of Rs. 46 Crores, i.e. Rs. 0.88 crores (INR 88 lakhs).

CER Cost Already Incurred

Activity Cost incurred (INR)

Plantation Outside the site (Development of Municipal Garden) 21,03,580

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 194 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020

Development of Cost of Road Outside the project site 33,38,000

Provision of LED on road outside the project site 5,00,000

Landscaping and Maintenance of Sapna Sangeetha Road 13,25,000

Street lights on Sapna Sangeetha Road 5,98,000

Total CSR Incurred 78,64,580

Remaining Cost of CSR/CER 9,35,420

Proposed CER Expenditure:

S.No. Activity Total Cost (INR) 1st Year 2nd Year 3rd Year

1 Improvement of the Municipal Garden along with provision of garden furniture and development of the walking tracks

9,50,000 3,50,000 3,00,000 3,00,000

Total 9,50,000 3,50,000 3,00,000 3,00,000

The submissions made by the PP were found to be satisfactory and acceptable hence It is decided to accept the recommendations of 398th SEAC meeting dtd. 04.10.19 with special conditions and accord Environmental Clearance for the proposed “Group Housing Project “Royal Amar Greens”at Khasra No. 37/1/2, 38/1, 38/2 min 1, 38/2 min 2, 38/2 min 3, 38/2 min 4, 38/2 min 5, 39/1/1, 39/1/2, 39/1/3, 39/2 min 1, 39/2 min 2, 39/2 min 3, 39/2 min 4 and 39/2 min 5 Village Niranjanpur Tehsil Indore District Indore M.P. Total Plot Area: 20350.0 m 2 Net Plot Area: 19405.0 sq.m Built-up Area: 67100.423 sq.m Built-up Area Constructed: 34526.54 sq.m by M/s Man Developments through Partner Mr. Rajendra Kumar Mansukhani G-9, Man Heritage, 6/2 South, Tukoganj, Indore (M.P.) - 452001, subject to following specific conditions imposed by SEIAA:-

1. The fresh water supply arrangement should be met through Municipal Corporation Indore as per letter dtd.07.05.16 and bore well .PP should explore the possibility to entire demand of the water met from the Municipal Corporation Indore.

2. The inlet and outlet point of natural drain system should be maintained with adequate size of channel for ensuring unrestricted flow of water.

3. Disposal of waste water.

a. PP should ensure disposal of waste water arrangement should be done in such a manner that water supply sources are not impaired.

b. PP should explore the possibility to linkage with Nagar Nigam Indore for sewer line for disposal of extra treated waste water.

c. The project not having provision for discharge of excess treated sewage cannot permit to start operation unless proper arrangements are put in place for its safe handling.

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 195 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020

4. Solid Waste Management:

a. Separate wet and dry bins must be provided at the ground level for facilitating segregation of waste.

b. The solid waste generated should be properly collected and segregated. Wet garbage should be composted and dry inert solid waste should be disposed off to the approved sites for land filling after recovering recyclable material.

c. Ensure linkage with Municipal Corporation, Indore (dtd.03.08.13) for final disposal of MSW.

5. PP should ensure building height, road width, front MOS and side / rear as per approved layout of T & CP.

6. For firefighting:-

PP should ensure distance of fire station approachable from the project site & provide fire fighting measures such as water sprinklers, fire hydrant pipe, Adequate firefighting requirement shall be taken into account while designing the electrical distribution system, Wet risers and hose reel, Adequate numbers of fire extinguishers, and underground water storage tank properly.

7. For Rain Water Harvesting, and Storm water management:-

PP should ensure the rain water harvesting with 03 recharge pits & 1 tank and these pits should be connected laterally to consume the surplus runoff. In addition, PP should provide recharging trenches. The base of the trenches should be Kachha with pebbles.

8. PP should ensure to provide car parking 438 ECS (Basement Parking –196 ECS Stilt Parking- 142 ECS ;The parking area should not be diverted for any other activities.

9. Green belt :-

PP should ensure the area of 3280 m2 i.e. 17 % of the net plot should be developed as greenbelt development with regular maintenance and also explore the possibility to plant trees of indigenous local varieties like Neem, Peepal, Kadam, Karanj, Kachnaar, Saltree, Gulmohar etc.

10. PP should ensure to complete the activities listed under ecological remediation, Natural resource augmentation & community resource augmentation for a total amount of Rs. 30,98,200.00 PP shall carry out the works assigned under ecological damage, natural resource augmentation and community resource augmentation within a stipulated period and submitted to same in MPSEIAA.

11. PP should ensure the implementation of CER activities to the extent of Rs. 9,50,000 (remaining amount of proposed activities) up to three years will be used in Improvement of the Municipal Garden along with provision of garden furniture and development of the walking tracks consultantion with district administration Indore (MP).

83. Case No. 6090/ 2019 Prior Environment Clearance for Granite Quarry (Opencast Semi Mechanized Method) in an area of 2.250 ha. for production capacity of 135564 cum / year at Khasra No. 479, 484, 485 at Village - Lausi, Tehsil - Gaurihar, Dist. Chhatarpur (MP) by M/s Naveen Infratech Pvt. Ltd, 617/1604, Digdiga, Vishal Khand-1, Opposite 1/736, Gomti Nagar, Lucknow, UP – 226010- –- Regarding

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 196 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020

transfer of EC in the name of M/s Shri Balaji Granite, R/o – 10, House of Snehlata Chourasiya, Didwara Road, Jujharnagar, Barigarh, Tehsil Gaurihar, District- Chhatarpur MP.

(1) It was noted that the PP had applied in Form-I for Prior Environmental Clearance of 2.250 ha. for production capacity of 135564 cum / year at Khasra No. 479, 484, 485 at Village - Lausi, Tehsil - Gaurihar, Dist. Chhatarpur (MP) by M/s Naveen Infratech Pvt. Ltd, 617/1604, Digdiga, Vishal Khand-1, Opposite 1/736, Gomti Nagar, Lucknow, UP – 226010.

(2) The Prior Environmental Clearance letter was issued SEIAA vide L.No. 1682/SEIAA/20 dtd.10.07.2020 in the name of " M/s Naveen Infratech Pvt. Ltd, 617/1604, Digdiga, Vishal Khand-1, Opposite 1/736, Gomti Nagar, Lucknow, UP – 226010.”

(3) It is noted that PP has requested vide no nil dtd. nil received in SEIAA office 03.10.2020 to make amendment in the Prior EC letter by changing the name of PP of the mining project namely " M/s Shri Balaji Granite, R/o – 10, House of Snehlata Chourasiya, Didwara Road, Jujharnagar, Barigarh, Tehsil Gaurihar, District- Chhatarpur MP.” in place of “M/s Naveen Infratech Pvt. Ltd, 617/1604, Digdiga, Vishal Khand-1, Opposite 1/736, Gomti Nagar, Lucknow, UP – 226010..".

(4) It is noted that in support of his request the PP has submitted the following documents

i. No objection letter of previous Project Proponent (to whom prior EC was granted) for transfer of prior EC in the name of M/s Shri Balaji Granite, R/o – 10, House of Snehlata Chourasiya, Didwara Road, Jujharnagar, Barigarh, Tehsil Gaurihar, District- Chhatarpur MP.

ii. Notarised affidavit of Shri Dharmendra Singh Tomar Partner M/s Naveen Infratech Pvt. Ltd, 617/1604, Digdiga, Vishal Khand-1, Opposite 1/736, Gomti Nagar, Lucknow, UP – 226010..., mentioning that no legal action/ credible action has been initiated against the mine till date and commitment to comply all the standard and specific conditions stipulated in the prior EC issued. .

iii. Copy of Prior EC issued by SEIAA. vide L.No. 1682/SEIAA/20 dtd.10.07.2020.

iv. Copy of Approved Mining Plan with Environmental Management Plan of M/s Shri Balaji Granite, R/o – 10, House of Snehlata Chourasiya, Didwara Road, Jujharnagar, Barigarh, Tehsil Gaurihar, District- Chhatarpur MP

v. Lease transfer order issued by Collector Office (Mining Division) order to of M/s Shri Balaji Granite, R/o – 10, House of Snehlata Chourasiya, Didwara Road, Jujharnagar, Barigarh, Tehsil Gaurihar, District- Chhatarpur MP, vide letter No. 1768/khanij/2020/dated 14.09.2020.

(5) It is noted that in EIA Notification 2006 as per Para-11 Transferability of Environmental Clearance (EC) there is a provision of transferring the EC.

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 197 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020

Para-11 :- A prior environmental clearance granted for a specific project or activity to an applicant may be transferred during its validity to another legal person entitled to undertake the project or activity on application by the transferor, or by the transferee with a written “no objection” by the transferor, to, and by the regulatory authority concerned, on the same terms and conditions under which the prior environmental clearance was initially granted, and for the same validity period. No reference to the Expert Appraisal Committee or State Level Expert Appraisal Committee concerned is necessary in such cases.

In context of above it seems that PP has submitted adequate documents to make the change in the name of PP as per EIA Notification 2006 (Para-11). Hence, prior EC issued SEIAA on 10.03.2020 in the name of " M/s Naveen Infratech Pvt. Ltd, 617/1604, Digdiga, Vishal Khand-1, Opposite 1/736, Gomti Nagar, Lucknow, UP – 226010." is hereby transferred to “M/s Shri Balaji Granite, R/o – 10, House of Snehlata Chourasiya, Didwara Road, Jujharnagar, Barigarh, Tehsil Gaurihar, District- Chhatarpur MP -". for Granite Quarry (Opencast Semi Mechanized Method) in an area of 2.250 ha. for production capacity of 135564 cum / year at Khasra No. 479, 484, 485 at Village - Lausi, Tehsil - Gaurihar, Dist. Chhatarpur (MP)." on the same terms & conditions and validity period under which the prior environmental clearance was initially granted. All concerned be informed accordingly.

84. Case No. 7883/2020: Prior Environmental Clearance for Stone Quarry (OpencastSemi Mechanized Method) in an area of 1.450 ha. for production capacity of 30000 cum per annum at Khasra No. 653/1, 653/2, 654 at Village - Pali Dirmon, Tehsil - Gohad, Dist. Bhind (MP) by Shriji Intratech Partner Shri Prateek Khandewal R/o Kali Mai Santar, Murar, Dist. Gwalior, MP. Regarding transfer of EC in the name of M/s Bhagwati Infratech, Partner Shri Chetan Prakash Gupta R/o E-9, Chetakpuri, Jhansi Road, Lashkar, Dist. Gwalior, MP,

(1) It was noted that the PP had applied in Form-I for Prior Environmental Clearance of 1.450 ha. for production capacity of 30000 cum per annum at Khasra No. 653/1, 653/2, 654 at Village - Pali Dirmon, Tehsil - Gohad, Dist. Bhind MP) by Shriji Intratech Partner Shri Prateek Khandewal R/o Kali Mai Santar, Murar, Dist. Gwalior, MP.

(2) The Prior Environmental Clearance letter was issued DEIAA vide L.No. 3414/ DEIAA/17 dtd.11.7.2017.in the name of " Shriji Intratech Partner Shri Prateek Khandewal R/o Kali Mai Santar, Murar, Dist. Gwalior, MP.

(3) It is noted that PP has requested vide no Nil dtd.3.10..2020 to make amendment in the Prior EC letter by changing the name of PP of the mining project namely " M/s Bhagwati Infratech, Partner Shri Chetan Prakash Gupta R/o E-9, Chetakpuri, Jhansi Road, Lashkar, Dist. Gwalior, MP, ,.” in place of Shriji Intratech Partner Shri Prateek Khandewal R/o Kali Mai Santar, Murar, Dist. Gwalior, MP.

(4) It is noted that in support of his request the PP has submitted the following documents

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 198 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020

i. No objection letter of previous Project Proponent (to whom prior EC was granted) for transfer of prior EC in the name of M/s Bhagwati Infratech, Partner Shri Chetan Prakash Gupta R/o E-9, Chetakpuri, Jhansi Road, Lashkar, Dist. Gwalior, MP.

ii. Notarised affidavit of Shriji Intratech Partner Shri Prateek Khandewal R/o Kali Mai Santar, Murar, Dist. Gwalior, MP.. mentioning that no legal action/ credible action has been initiated against the mine till date and commitment to comply all the standard and specific conditions stipulated in the prior EC issued.

iii. Copy of Prior EC issued by DEIAA vide letter No. 3414/ DEIAA/17 dtd.11.7.2017..

iv. Copy of Approved Mining Plan with Environmental Management Plan of M/s Bhagwati Infratech, Partner Shri Chetan Prakash Gupta R/o E-9, Chetakpuri, Jhansi Road, Lashkar, Dist. Gwalior, MP,

v. Lease transfer order issued by Collector (Mining Division) to M/s Bhagwati Infratech, Partner Shri Chetan Prakash Gupta R/o E-9, Chetakpuri, Jhansi Road, Lashkar, Dist. Gwalior, MP vide letter No. 499 dated 30.7.2020.

(5) It is noted that in EIA Notification 2006 as per Para-11 Transferability of Environmental Clearance (EC) there is a provision of transferring the EC.

Para-11 :- A prior environmental clearance granted for a specific project or activity to an applicant may be transferred during its validity to another legal person entitled to undertake the project or activity on application by the transferor, or by the transferee with a written “no objection” by the transferor, to, and by the regulatory authority concerned, on the same terms and conditions under which the prior environmental clearance was initially granted, and for the same validity period. No reference to the Expert Appraisal Committee or State Level Expert Appraisal Committee concerned is necessary in such cases.

In context of above it seems that PP has submitted adequate documents to make the change in the name of PP as per EIA Notification 2006 (Para-11). Hence, prior EC issued DEIAA Bhind on`11.7.2017 in the name of " Shriji Intratech Partner Shri Prateek Khandewal R/o Kali Mai Santar, Murar, Dist. Gwalior, MP.." is hereby transferred to M/s Bhagwati Infratech, Partner Shri Chetan Prakash Gupta R/o E-9, Chetakpuri, Jhansi Road, Lashkar, Dist. Gwalior, MP. for Stone Quarry in an area of 1.450 ha. for production capacity of 30000 cum per annum at Khasra No. 653/1, 653/2, 654 at Village - Pali Dirmon, Tehsil - Gohad, Dist. Bhind (MP)." on the same terms & conditions and validity period under which the prior environmental clearance was initially granted. All concerned be informed accordingly.

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 199 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020 85. Case No.7884/2020 Prior Environment Clearance for Stone Quarry (Opencast Semi

Mechanized Method) in an area of 4.0 ha. (25057 cum per annum) (Khasra No. 847), Village - Kalma, Tehsil - Tonkkurd, Dist. Dewas (MP) by M/s Thekadar, Shri Laxman Singh Rajput, R/o – 182, Push Kunj Colony,Etava Dewas, Tehsil & District Dewas, MP – 455001- Regarding transfer of EC in the name of M/s Udai Mines, Partner – Shri Udai Mishra, R/o Scheme no. 94, Bharfani Dham Chouraha, Ring road , Dist. Indore, MP – 455001

1. It was noted that the PP had applied in Form-IM for Prior Environmental Clearance of 4.0 ha. (25057 cum per annum) (Khasra No. 847), Village - Kalma, Tehsil - Tonkkurd, Dist. Dewas (MP) by M/s Thekadar, Shri Laxman Singh Rajput, R/o – 182, Push Kunj Colony,Etava Dewas, Tehsil & District Dewas, MP – 455001.

2. The Prior Environmental Clearance letter was issued DEIAA (Case no.76/2016) vide L.No. 73/DEIAA/16 dtd.05.07.2016 in the name of " M/s Thekadar, Shri Laxman Singh Rajput, R/o – 182, Push Kunj Colony,Etava Dewas, Tehsil & District Dewas, MP – 455001.”

3. It is noted that PP has requested vide no nil dtd. nil received in SEIAA office 03.10.2020 to make amendment in the Prior EC letter by changing the name of PP of the mining project namely " M/s Udai Mines, Partner – Shri Udai Mishra, R/o Scheme no. 94, Bharfani Dham Chouraha, Ring road , Dist. Indore, MP – 455001” in place of “M/s Thekadar, Shri Laxman Singh Rajput, R/o – 182, Push Kunj Colony,Etava Dewas, Tehsil & District Dewas, MP – 455001..".

4. It is noted that in support of his request the PP has submitted the following documents

i. No objection letter of previous Project Proponent (to whom prior EC was granted) for transfer of prior EC in the name of M/s Udai Mines, Partner – Shri Udai Mishra, R/o Scheme no. 94, Bharfani Dham Chouraha, Ring road , Dist. Indore, MP – 455001.

ii. Notarised affidavit of M/s Thekadar, Shri Laxman Singh Rajput, R/o – 182, Push Kunj Colony,Etava Dewas, Tehsil & District Dewas, MP – 455001, mentioning that no legal action/ credible action has been initiated against the mine till date and commitment to comply all the standard and specific conditions stipulated in the prior EC issued. .

iii. Copy of Prior EC issued byDEIAA (Case no.76/2016) vide L.No. 73/DEIAA/16 dtd.05.07.2016.

iv. Copy of Approved Mining Plan with Environmental Management Plan of M/s Udai Mines, Partner – Shri Udai Mishra, R/o Scheme no. 94, Bharfani Dham Chouraha, Ring road , Dist. Indore, MP – 455001

v. Lease transfer order issued by Collector Office (Mining Division) order to of M/s Udai Mines, Partner – Shri Udai Mishra, R/o Scheme no. 94, Bharfani Dham Chouraha, Ring road , Dist.

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 200 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020

Indore, MP – 455001, vide letter No. 147/khanij/2020/dated 31.01.2017.

5. It is noted that in EIA Notification 2006 as per Para-11 Transferability of Environmental Clearance (EC) there is a provision of transferring the EC.

Para-11 :- A prior environmental clearance granted for a specific project or activity to an applicant may be transferred during its validity to another legal person entitled to undertake the project or activity on application by the transferor, or by the transferee with a written “no objection” by the transferor, to, and by the regulatory authority concerned, on the same terms and conditions under which the prior environmental clearance was initially granted, and for the same validity period. No reference to the Expert Appraisal Committee or State Level Expert Appraisal Committee concerned is necessary in such cases.

In context of above it seems that PP has submitted adequate documents to make the change in the name of PP as per EIA Notification 2006 (Para-11). Hence, prior EC issued SEIAA on 25.07.2016 in the name of " M/s Thekadar, Shri Laxman Singh Rajput, R/o – 182, Push Kunj Colony,Etava Dewas, Tehsil & District Dewas, MP " is hereby transferred to “M/s Udai Mines, Partner – Shri Udai Mishra, R/o Scheme no. 94, Bharfani Dham Chouraha, Ring road , Dist. Indore, MP – 455001-". for Stone Quarry (Opencast Semi Mechanized Method) in an area of 4.0 ha. (25057 cum per annum) (Khasra No. 847), Village - Kalma, Tehsil - Tonkkurd, Dist. Dewas (MP)." on the same terms & conditions and validity period under which the prior environmental clearance was initially granted. All concerned be informed accordingly.

86. Case No.7885/2020 (DEIAA Case) Prior Environment Clearance for Stone Quarry(Opencast Mechanized Method) in an area of 3.0 ha. (6000 cum per annum) (Khasra No. 757), Village - Jamgod, Tehsil - Dewas, Dist. Dewas by Ku. Naina Pawar D/o Shri Liladhar Panwar, Add. 328 Shiv Shakti Nagar, Tehsil & District Dewas - Regarding transfer of EC in the name of M/s Udai Mines, Partner – Shri Udai Mishra, R/o Scheme no. 94, Bharfani Dham Chouraha, Ring road , Dist. Indore, MP – 455001

1. It was noted that the PP had applied in Form-IM for Prior Environmental Clearance Stone Quarry(Opencast Mechanized Method) in an area of 3.0 ha. (6000 cum per annum) (Khasra No. 757), Village - Jamgod, Tehsil - Dewas, Dist. Dewas by Ku. Naina Pawar D/o Shri Liladhar Panwar, Add. 328 Shiv Shakti Nagar, Tehsil & District Dewas

2. The Prior Environmental Clearance letter was issued DEIAA (Case no.185/2018) vide L.No. 216/DEIAA/18 dtd.04.03.2018 in the name of " Ku. Naina Pawar D/o Shri Liladhar Panwar, Add. 328 Shiv Shakti Nagar, Tehsil & District Dewas.”

3. It is noted that PP has requested vide no nil dtd. nil received in SEIAA office 03.10.2020 to make amendment in the Prior EC letter by changing the name of PP of the mining project namely " M/s Udai Mines, Partner – Shri Udai Mishra, R/o Scheme no. 94, Bharfani Dham Chouraha, Ring road , Dist. Indore, MP – 455001” in place of “Ku. Naina Pawar D/o Shri Liladhar Panwar, Add. 328 Shiv Shakti Nagar, Tehsil & District Dewas.".

4. It is noted that in support of his request the PP has submitted the following documents

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 201 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020

i. No objection letter of previous Project Proponent (to whom prior EC was granted) for transfer of prior EC in the name of M/s Udai Mines, Partner – Shri Udai Mishra, R/o Scheme no. 94, Bharfani Dham Chouraha, Ring road , Dist. Indore, MP – 455001.

ii. Notarised affidavit of Ku. Naina Pawar D/o Shri Liladhar Panwar, Add. 328 Shiv Shakti Nagar, Tehsil & District Dewas., mentioning that no legal action/ credible action has been initiated against the mine till date and commitment to comply all the standard and specific conditions stipulated in the prior EC issued. .

iii. Copy of Prior EC issued by DEIAA (Case no.185/2018) vide L.No. 216/DEIAA/18 dtd.04.03.2018.

iv. Copy of Approved Mining Plan with Environmental Management Plan of M/s Udai Mines, Partner – Shri Udai Mishra, R/o Scheme no. 94, Bharfani Dham Chouraha, Ring road , Dist. Indore, MP – 455001

v. Lease transfer order issued by Collector Office (Mining Division) order to of M/s Udai Mines, Partner – Shri Udai Mishra, R/o Scheme no. 94, Bharfani Dham Chouraha, Ring road , Dist. Indore, MP – 455001, vide letter No. 1917/khanij/2018/dated 05.12.2018.

5. It is noted that in EIA Notification 2006 as per Para-11 Transferability of Environmental Clearance (EC) there is a provision of transferring the EC.

Para-11 :- A prior environmental clearance granted for a specific project or activity to an applicant may be transferred during its validity to another legal person entitled to undertake the project or activity on application by the transferor, or by the transferee with a written “no objection” by the transferor, to, and by the regulatory authority concerned, on the same terms and conditions under which the prior environmental clearance was initially granted, and for the same validity period. No reference to the Expert Appraisal Committee or State Level Expert Appraisal Committee concerned is necessary in such cases.

In context of above it seems that PP has submitted adequate documents to make the change in the name of PP as per EIA Notification 2006 (Para-11). Hence, prior EC issued SEIAA on 04.03.2018 in the name of " Ku. Naina Pawar D/o Shri Liladhar Panwar, Add. 328 Shiv Shakti Nagar, Tehsil & District Dewas " is hereby transferred to “M/s Udai Mines, Partner – Shri Udai Mishra, R/o Scheme no. 94, Bharfani Dham Chouraha, Ring road , Dist. Indore, MP – 455001-". for Stone Quarry(Opencast Mechanized Method) in an area of 3.0 ha. (6000 cum per annum) (Khasra No. 757), Village - Jamgod, Tehsil - Dewas, Dist. Dewas." on the same terms & conditions and validity period under which the prior environmental clearance was initially granted. All concerned be informed accordingly.

87. Case No. 7886/2020 (DEIAA Case) - Prior Environment Clearance for Stone Quarry (Opencast Semi Mechanized Method) in an area of 4.0 ha. (10260 cum per annum) (Khasra No. 159), Village - Gunaikhalsa, Tehsil - Ujjain, Dist. Ujjain by Shri Sanjay S/o Shri Pratap Mehta, R/o 40 Mhasweta Nagar, Ujjain, Tehsil & Dist. Ujjain Regarding transfer of EC in the name of M/s Vijay Construction, 105, Durga Paaza, Free Ganj, Dewas Road, Dist. Ujjain, MP - 456010

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 202 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020

1. It was noted that the PP had applied in Form-IM for Prior Environmental Clearance Stone Quarry (Opencast Semi Mechanized Method) in an area of 4.0 ha. (10260 cum per annum) (Khasra No. 159), Village - Gunaikhalsa, Tehsil - Ujjain, Dist. Ujjain by Shri Sanjay S/o Shri Pratap Mehta, R/o 40 Mhasweta Nagar, Ujjain, Tehsil & Dist. Ujjain

2. The Prior Environmental Clearance letter was issued DEIAA (Case no.26/2016) vide L.No. 1990/DEIAA/16 dtd.17.10.2016 in the name of " Shri Sanjay S/o Shri Pratap Mehta, R/o 40 Mhasweta Nagar, Ujjain, Tehsil & Dist. Ujjain.”

3. It is noted that PP has requested vide no nil dtd. nil received in SEIAA office 01.10.2020 to make amendment in the Prior EC letter by changing the name of PP of the mining project namely " M/s Vijay Construction, 105, Durga Paaza, Free Ganj, Dewas Road, Dist. Ujjain, MP – 456010 ” in place of “Shri Sanjay S/o Shri Pratap Mehta, R/o 40 Mhasweta Nagar, Ujjain, Tehsil & Dist. Ujjain.".

4. It is noted that in support of his request the PP has submitted the following documents

i. No objection letter of previous Project Proponent (to whom prior EC was granted) for transfer of prior EC in the name of " M/s Vijay Construction, 105, Durga Paaza, Free Ganj, Dewas Road, Dist. Ujjain, MP – 456010.

ii. Notarised affidavit of Shri Sanjay S/o Shri Pratap Mehta, R/o 40 Mhasweta Nagar, Ujjain, Tehsil & Dist. Ujjain., mentioning that no legal action/ credible action has been initiated against the mine till date and commitment to comply all the standard and specific conditions stipulated in the prior EC issued. .

iii. Copy of Prior EC issued by DEIAA (Case no.26/2016) vide L.No. 1990/DEIAA/16 dtd.17.10.2016

iv. Copy of Approved Mining Plan with Environmental Management Plan of M/s Vijay Construction, 105, Durga Paaza, Free Ganj, Dewas Road, Dist. Ujjain, MP – 456010

v. Lease transfer order issued by Collector Office (Mining Division) order to of M/s Vijay Construction, 105, Durga Paaza, Free Ganj, Dewas Road, Dist. Ujjain, MP – 456010, vide letter No. 1707/Na. Kra 2019/dated 19.11.2019.

5. It is noted that in EIA Notification 2006 as per Para-11 Transferability of Environmental Clearance (EC) there is a provision of transferring the EC.

Para-11 :- A prior environmental clearance granted for a specific project or activity to an applicant may be transferred during its validity to another legal person entitled to undertake the project or activity on application by the transferor, or by the transferee with a written “no objection” by the transferor, to, and by the regulatory authority concerned, on the same terms and conditions under which the prior environmental clearance was initially granted, and for the same validity period. No reference to the Expert Appraisal Committee or State Level Expert Appraisal Committee concerned is necessary in such cases.

In context of above it seems that PP has submitted adequate documents to make the change in the name of PP as per EIA Notification 2006 (Para-11). Hence, prior EC issued SEIAA on 17.10.2016 in the name of " Shri Sanjay S/o Shri Pratap

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 203 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020

Mehta, R/o 40 Mhasweta Nagar, Ujjain, Tehsil & Dist. Ujjain " is hereby transferred to “M/s Vijay Construction, 105, Durga Paaza, Free Ganj, Dewas Road, Dist. Ujjain, MP - 456010-". for Stone Quarry (Opencast Semi Mechanized Method) in an area of 4.0 ha. (10260 cum per annum) (Khasra No. 159), Village - Gunaikhalsa, Tehsil - Ujjain, Dist. Ujjain." on the same terms & conditions and validity period under which the prior environmental clearance was initially granted. All concerned be informed accordingly.

88. Case No. 7887/2020 Prior Environmental Clearance for Stone Quarry in an area of 1.44 ha. (11400 cum per annum) (Khasra No. 53) at Village - Manegaon, Tehsil - Jabalpur, District - Jabalpur (MP) by Shri Kandarp Sharma S/o Shri Kameshwar Sharma, R/o 2262, Saket Nagar, MR-4 Road, Vivekanand Ward, Jabalpur, Dist. – Jabalpur (MP) – Regarding transfer of EC in the name of M/s Shakti Stone Crusher, Partner Shri Vipin Agrawal S/o Late Sudama Agrawal R/o Shop No. 19, Shiv Vihar Complex, Opposite Sai Mandir, Damoh Road, Jabalpur, Dist. – Jabalpur (MP).

The prior EC was issued by DEIAA Dist. – Jabalpur to Shri Kandarp Sharma S/o Shri Kameshwar Sharma, R/o 2262, Saket Nagar, MR-4 Road, Vivekanand Ward, Jabalpur, Dist. – Jabalpur (MP) vide Letter No. 80/DEIAA/16 dtd. 03.09.2016 for an area of 1.44 ha at khasra no. 53 at Village - Manegaon, Tehsil - Jabalpur, District - Jabalpur (MP).

Applicant M/s Shakti Stone Crusher, Partner Shri Vipin Agrawal S/o Late Sudama Agrawal R/o Shop No. 19, Shiv Vihar Complex, Opposite Sai Mandir, Damoh Road, Jabalpur, Dist. – Jabalpur (MP) has submitted the following documents in support of his request:-

a) Application for transfer of Prior EC in favour of M/s Shakti Stone Crusher, Partner Shri Vipin Agrawal S/o Late Sudama Agrawal R/o Shop No. 19, Shiv Vihar Complex, Opposite Sai Mandir, Damoh Road, Jabalpur, Dist. – Jabalpur (MP).

b) No objection certificate (in form of notarised affidavit) of previous Project Proponent Shri Kandarp Sharma S/o Shri Kameshwar Sharma, R/o 2262, Saket Nagar, MR-4 Road, Vivekanand Ward, Jabalpur, Dist. – Jabalpur (MP) for transfer of prior EC in the name of M/s Shakti Stone Crusher, Partner Shri Vipin Agrawal S/o Late Sudama Agrawal R/o Shop No. 19, Shiv Vihar Complex, Opposite Sai Mandir, Damoh Road, Jabalpur, Dist. – Jabalpur (MP).

c) Notarised affidavit of M/s Shakti Stone Crusher, Partner Shri Vipin Agrawal S/o Late Sudama Agrawal R/o Shop No. 19, Shiv Vihar Complex, Opposite Sai Mandir, Damoh Road, Jabalpur, Dist. – Jabalpur (MP) mentioning that no legal action/ credible action has been initiated against the mine till date and commitment to comply all the standard and specific conditions stipulated in the prior EC issued.

d) Lease transfer order issued by Office of Collector (Mining Division) Jabalpur to M/s Shakti Stone Crusher, Partner Shri Vipin Agrawal S/o Late Sudama Agrawal R/o Shop No. 19, Shiv Vihar Complex, Opposite Sai

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 204 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020

Mandir, Damoh Road, Jabalpur, Dist. – Jabalpur (MP) vide letter No. 275/Khanij/QL/2018-19 dated 06.03.2019.

e) Copy of Prior EC issued by DEIAA Dist. - Jabalpur vide letter no. 80/DEIAA/16 dtd. 03.09.2016.

As per the notification issued by MoEF&CC on 14.09.2006, the policy on transferability of EC is as follows:-

11. Transferability of Environmental Clearance (EC):

A prior environmental clearance granted for a specific project or activity to an applicant may be transferred during its validity to another legal person entitled to undertake the project or activity on application by the transferor, or by the transferee with a written “no objection” by the transferor, to, and by the regulatory authority concerned, on the same terms and conditions under which the prior environmental clearance was initially granted, and for the same validity period. No reference to the Expert Appraisal Committee or State Level Expert Appraisal Committee concerned is necessary in such cases.

After detailed discussions on the MoEF&CC Notification regarding transferability and perusal of the above information, it has been decided to transfer the Prior EC issued by DEIAA on 03.09.2016 in favour of M/s Shakti Stone Crusher, Partner Shri Vipin Agrawal S/o Late Sudama Agrawal R/o Shop No. 19, Shiv Vihar Complex, Opposite Sai Mandir, Damoh Road, Jabalpur, Dist. – Jabalpur (MP) in place of Shri Kandarp Sharma S/o Shri Kameshwar Sharma, R/o 2262, Saket Nagar, MR-4 Road, Vivekanand Ward, Jabalpur, Dist. – Jabalpur (MP) for Stone Quarry in an area of area of 1.44 ha. ha for production capacity of 11400 cum per annum at Khasra No. 53 at Village - Manegaon, Tehsil - Jabalpur, District - Jabalpur (MP) on the same terms & conditions and validity period under which the prior environmental clearance was initially granted. Copy to PP and all concerned.

89. Case No. 7888/2020 Prior Environment Clearance for Stone Quarry in an area of 1.0 ha. (5130 cum per annum) (Khasra No. 156/2), Village - Jhitapati, Tehsil - Amla, Dist. - Betul (MP) by M/s Dayaram Chhagonmal Partner Shri Deepak Senani, R/o Jawahar Ward, Betul Ganj, Betul, Dist. – Betul (MP) – Regarding transfer of EC in the name of Shri Nitin Harode, Vikas Nagar, Kalpatha, Dist. - Betul, MP - 460001, Email - [email protected], Mobile – 9827560489.

The prior EC was issued by DEIAA Dist. – Betul to M/s Dayaram Chhagonmal Partner Shri Deepak Senani, R/o Jawahar Ward, Betul Ganj, Betul, Dist. – Betul (MP) vide Letter No. 22/DEIAA/16 dtd. 17.05.2016 for an area of 1.0 ha at khasra No. 156/2 at Village - Jhitapati, Tehsil - Amla, Dist. - Betul (MP).

Applicant Shri Nitin Harode, Vikas Nagar, Kalpatha, Dist. - Betul, MP - 460001 has submitted the following documents in support of his request:-

a) Application for transfer of Prior EC in favour of Nitin Harode, Vikas Nagar, Kalpatha, Dist. - Betul, MP - 460001.

b) No objection certificate (in form of notarised affidavit) of previous Project Proponent (to whom prior EC was granted) for transfer of prior EC in the name of Nitin Harode, Vikas Nagar, Kalpatha, Dist. - Betul, MP - 460001.

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 205 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020

c) Notarised affidavit of Nitin Harode, Vikas Nagar, Kalpatha, Dist. - Betul, MP - 460001 mentioning that no legal action/ credible action has been initiated against the mine till date and commitment to comply all the standard and specific conditions stipulated in the prior EC issued.

d) Lease transfer order issued by Office of Collector (Mining Division) Betul to Shri Nitin Harode, Vikas Nagar, Kalpatha, Dist. - Betul, MP - 460001 vide letter No. Khanij-1/19/2081 Betul dated 12.12.2019.

e) Copy of Prior EC issued by DEIAA Dist. - Betul vide letter no. 22/DEIAA/16 dtd. 17.05.2016.

As per the notification issued by MoEF&CC on 14.09.2006, the policy on transferability of EC is as follows:-

11. Transferability of Environmental Clearance (EC):

A prior environmental clearance granted for a specific project or activity to an applicant may be transferred during its validity to another legal person entitled to undertake the project or activity on application by the transferor, or by the transferee with a written “no objection” by the transferor, to, and by the regulatory authority concerned, on the same terms and conditions under which the prior environmental clearance was initially granted, and for the same validity period. No reference to the Expert Appraisal Committee or State Level Expert Appraisal Committee concerned is necessary in such cases.

After detailed discussions on the MoEF&CC Notification regarding transferability and perusal of the above information, it has been decided to transfer the Prior EC issued by DEIAA on 17.05.2016 in favour of Shri Nitin Harode, Vikas Nagar, Kalpatha, Dist. - Betul, MP – 460001 in place of M/s Dayaram Chhagonmal Partner Shri Deepak Senani, R/o Jawahar Ward, Betul Ganj, Betul, Dist. – Betul (MP) for Stone Quarry in an area of 1.0 ha for production capacity of 5130 cum/year at Khasra No. 156/2 at Village - Jhitapati, Tehsil - Amla, Dist. - Betul (MP) on the same terms & conditions and validity period under which the prior environmental clearance was initially granted. Copy to PP and all concerned.

90. Case No. 7889/2020 - Prior Environment Clearance for Stone Quarry (Opencast Semi Mechanized Method) in an area of 2.0 ha. (12000 cum per annum) (Khasra No. 343/1), Village - Pingleswer, Tehsil - Ujjain, Dist. Ujjain (MP) by Shri Jitendra S/o Shri Jagdish Jat , R/o Village Shankarpur, Tehsil & Dist. Ujjain, MP – 456001 .- Regarding transfer of EC in the name of Shri Shyam Borasi,S/o Shri Gaya Borasi A-23, Anand Nagar, Dist. Ujjain, MP – 456001

1. It was noted that the PP had applied in Form-IM for Prior Environmental Clearance for Stone Quarry (Opencast Semi Mechanized Method) in an area of 2.0 ha. (12000 cum per annum) (Khasra No. 343/1), Village - Pingleswer, Tehsil - Ujjain, Dist. Ujjain (MP) by Shri Jitendra S/o Shri Jagdish Jat , R/o Village Shankarpur, Tehsil & Dist. Ujjain, MP – 456001

2. The Prior Environmental Clearance letter was issued DEIAA vide L.No. 1132/DEIAA/16 dtd.31.05.2016 in the name of " Shri Jitendra S/o Shri Jagdish Jat , R/o Village Shankarpur, Tehsil & Dist. Ujjain, MP – 456001.”

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 206 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020

3. It is noted that PP has requested vide no nil dtd. nil received in SEIAA office 06.10.2020 to make amendment in the Prior EC letter by changing the name of PP of the mining project namely " Shri Shyam Borasi,S/o Shri Gaya Borasi A-23, Anand Nagar, Dist. Ujjain, MP – 456001 ” in place of “Shri Jitendra S/o Shri Jagdish Jat , R/o Village Shankarpur, Tehsil & Dist. Ujjain, MP – 456001.".

4. It is noted that in support of his request the PP has submitted the following documents

i. No objection letter of previous Project Proponent (to whom prior EC was granted) for transfer of prior EC in the name of " Shri Shyam Borasi,S/o Shri Gaya Borasi A-23, Anand Nagar, Dist. Ujjain, MP – 456001.

ii. Notarised affidavit of Shri Jitendra S/o Shri Jagdish Jat , R/o Village Shankarpur, Tehsil & Dist. Ujjain, MP – 456001., mentioning that no legal action/ credible action has been initiated against the mine till date and commitment to comply all the standard and specific conditions stipulated in the prior EC issued. .

iii. Copy of Prior EC issued by DEIAA vide L.No. 1132/DEIAA/16 dtd.31.05.2016

iv. Copy of Approved Mining Plan with Environmental Management Plan of Shri Shyam Borasi,S/o Shri Gaya Borasi A-23, Anand Nagar, Dist. Ujjain, MP – 456001.

v. Lease transfer order issued by Collector Office (Mining Division) order to of Shri Shyam Borasi,S/o Shri Gaya Borasi A-23, Anand Nagar, Dist. Ujjain, MP – 456001., vide letter No. 543/Na. Kra 2020/dated 18.05.2020.

5. It is noted that in EIA Notification 2006 as per Para-11 Transferability of Environmental Clearance (EC) there is a provision of transferring the EC.

Para-11 :- A prior environmental clearance granted for a specific project or activity to an applicant may be transferred during its validity to another legal person entitled to undertake the project or activity on application by the transferor, or by the transferee with a written “no objection” by the transferor, to, and by the regulatory authority concerned, on the same terms and conditions under which the prior environmental clearance was initially granted, and for the same validity period. No reference to the Expert Appraisal Committee or State Level Expert Appraisal Committee concerned is necessary in such cases.

In context of above it seems that PP has submitted adequate documents to make the change in the name of PP as per EIA Notification 2006 (Para-11). Hence, prior EC issued SEIAA on 31.05.2016 in the name of " Shri Jitendra S/o Shri Jagdish Jat , R/o Village Shankarpur, Tehsil & Dist. Ujjain, MP – 456001" is hereby transferred to “Shri Shyam Borasi,S/o Shri Gaya Borasi A-23, Anand Nagar, Dist. Ujjain, MP – 456001-". for Stone Quarry (Opencast Semi Mechanized Method) in an area of 2.0 ha. (12000 cum per annum) (Khasra No. 343/1), Village - Pingleswer, Tehsil - Ujjain, Dist. Ujjain (MP)." on the same terms & conditions and validity period under which the prior environmental clearance was initially granted. All concerned be informed accordingly.

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 207 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020 91. Case No. 7354/2020- Prior Environment Clearance for Limestone Mine in an area of

2.30 ha. (18000 cum per annum) (Khasra No. 110/2/2(Part)) at Village- Soyla, Tehsil- Gandhawani, District- Dhar by M/s Khandelwal Mines & Minerals, Prop. Smt. Shobha Gupta W/o Shri Ranchordas Khendelwal, 138/, Vallabh Bhai Patel Marg, Ward No. 3, Main Dhar Road, Manawar, Dist. Dhar, MP – 454446

The case was discussed in 449th SEAC meeting dated 24.07.20 and it was recorded that………..

The case was presented by the PP and their consultant. During appraisal of the case it was observed by the committee that lease is already excavated. PP submitted that they were carrying mining operations till 2018. On perusal of case file committee observed that PP has appended a judgenment made by Hon’ble High Court of Indore dated 22/07/2019 wherein Hon’ble High Court of Indore has passed an order stating that PP shall obtain EC. On perusal of the judgement it is clear that PP has not obtained EC even after renewal of lease in 2016. Committee after deliberations recommends that case file may be sent to SEIAA as it’s a case of violation wherein PP has continued mining even after renewal of lease in 2016 and needs to be delt as per the provisions made for violation cases by MoEF&CC in relevant OMs and notifications.

The case was discussed in 631st SEIAA meeting dated 11.08.20 and it was recorded that………..

As per above observation of 449th SEAC meeting dtd 24.7.2020, it was decided to defer the case for upcoming meeting.

As per observation of 449th SEAC meeting dated 24.07.20, it was found that PP has continued mining even after renewal of lease in 2016 without obtaining prior environmental clearance which seems violation case as per provisions made in OMs and notification of MoEF&CC, GoI. After detail discussion and delebration, it was decided to ask PP to submit chronological details of mining activities with proper justification and legal provisions to consider prior environmental clearance in compliance of Hon’ble High Court of Indore order dated 22/07/2019.

92. Case No. 4307/2015- Prior Environment Clearance for Sand Quarry in an area of 6.069 ha. (80,500 cum/year) at Village-Raver, Tehsil-Barwah (Sanawad), District-Khargone (MP)by Shri Kailash Chandra Gupta, M/s Shiva Corporation India Pvt. Ltd., 312, Ganpati Plaza, MIG Road, District-Jaipur (Raj.)

Project Proponent has applied for EC transfer in the name of M/s R.K.Gupta Contractors and Engineers Pvt. Ltd It has been observed from the record that the validity of auctioned lease of previous PP’ to whom prior EC was issued, is expired on 01.06.2020. After discussion, it is decided that EC can not be transferred as auctioned lease is expired hence PP may be asked to apply afresh online application for prior EC.

93. Case No. 78772020- Prior Environment Clearance for Sand Quarry in an area of 4.0 ha. (34500 cum per annum) (Khasra No. 44), Village - Lalpura, Tehsil - Maheshwar, Dist. Khargone (MP) by M/s R.K.Gupta Contractors and Engineers Pvt. Ltd, Authorized Person, Shri Rajendra Kumar Gupta, B-72, Shahpura, Dist. Bhopal, MP - 451115, Email - khargonesandmine1[at]gmail[dot]com, Mobile - 9425017064

( R.K. Sharma ) Member

(Rakesh K. Shrivastava) Chairman

644th SEIAA Meeting dtd.07.10.2020 Page 208 of 208

Minutes of the 644th Meeting of SEIAA dated 07.10.2020

Project Proponent has applied for EC transfer in the name of M/s R.K.Gupta Contractors and Engineers Pvt. Ltd It has been observed from the record that the validity of auctioned lease of previous PP’ to whom prior EC was issued, is expired on 28.04.2020. After discussion, it is decided that EC can not be transferred as auctioned lease is expired hence PP may be asked to apply afresh online application for prior EC.

Meeting ended with a vote of thanks to the Chair.