"Fire Qualification Test on Retrofit Penetration Seals."

113
A. O. SLAB NO.1 . . :.; e , o c.w y . ,. .ym g g, sta . m g -geng-v .. a.: ~,v;g , ,, - g . .+n - ;,w s ..w.e _ ..___ 7aa:e:.a.mm . :. -- . by Michael D. Pish NSP FINAL REPORT , < , gp% DUCl.E92 Y,SER' ACES CORPORAT10D l ' Northern States Power Company 414 Nicollet Mall Minneapolis, Minnesota 55401 Zr-~2"~T '~"~~~ ".~0="~~;C.~ra=C;." C'O JUNE 30,1980 | : uw j - R h | +. ~ SOUTHWEST RESEARCH INSTITUTE , SAN ANTONIO HOUSTON ~ | su103108[>

Transcript of "Fire Qualification Test on Retrofit Penetration Seals."

A.O.

SLAB NO.1. . :.; e , o c.w y . ,. .ym g g, sta . m g -geng-v .. a.: ~,v;g ,

,,-g

..+n - ;,w s ..w.e _ .

..___ 7aa:e:.a.mm . :.-- .

by

Michael D. Pish

NSPFINAL REPORT,

< ,

gp% DUCl.E92Y,SER' ACESCORPORAT10D

l'

Northern States Power Company414 Nicollet Mall

Minneapolis, Minnesota 55401

Zr-~2"~T '~"~~~ ".~0="~~;C.~ra=C;." C'O

JUNE 30,1980

|

:

uw j

- Rh |

+. ~ SOUTHWEST RESEARCH INSTITUTE,

SAN ANTONIO HOUSTON~

|

su103108[>

. i

%-a

Attachment

Director of Nuclear Reactor RegulationOctober 24, 1980

Items 3.1.l(2), 3.1.1(4), 3.2.2(1), and 3.2.2(2)Fire Barrier Penetration Seal Upgrading

Northern States Power Company will upgrade fire 'sarrier seals in safety,

related areas of the Prairie Island plant to a rating at least equalto the worst case fire severity present on either side of each barrier. Inaddition, seals in the following arear will be upgraded to a 3-hour rating:

a. Area 66 barriers adjacent to turbine buildingb. Area 69 and 70 barriers adjacent to auxiliary building

Elevation 735 auxiliary building barriers adjacent to turbine buildingc.

d. Area 61 barriers shared with the auxiliary buildingBarriers between diesel rooms and auxiliary buildinge.

f. Barriers between safety related areas and turbine building notlisted above

A description of the testing program developed to qualify various methodsof seal upgrading was provided for NRC Staff review and comment on November30, 1979. Drawings of proposed seal upgrade methods were also submitted.

Three slabs of 12 inches thick concrete were constructed containing a totalof 38 test penetrations. These penetrations were constructed to simulatethe configurations of existing and proposed upgrade designs, includingpairs of penetissions for non-symetrical configurations. The tes t penetra-tions include configurations like those in the plant and configurationslike th *se in the plant with add-on fire seal materials covering theexisting seal material. In some test penetrations a new seal materialwas substituted for that used in the plant.

The test slabs were subjected to a test by an independent testing laboratoryto IEEE 634-1978, IEEE Standard Cable Penetration Fire Stop QualificationTest, which replaces ASTM E 119 for nuclear power plant cable penetrationsand which uses the time temperature curve from ASTM E 119.

Summaries of the test reports for the three slabs are attached. Thedetails of the test results are considered proprietary to Northern StatesPower Company because of the expense involved in conducting this program.Complete reports are available on site for review by Inspection and Enforce-ment or other NRC personnel.

The reports have been reviewed in detail by our consulting engineer forthis project. All penetrations in safety related areas of the plant willbe surveyed. Where deficient, the seals will be upgraded with a qualifiedadd-on modification or replaced with a qualified seal.

1-1

_ __

o >.

i

SIIMMARY

On 20 March 1980, twenty-three block-out penetrations decigned

by Nuclear Services Corporation for Nortbern States Power Company and

installed by Insulation Consultants and Management Services (ICMS),

Incorporated and Southwest Research Institute were exposed to a three-

hour fire endurance qualification test following the ASTM E119-76 time /

temperature curve.

The purpose of the test was to obtain a three-hour fire racing

for existing referenced retrofit fire stop designs in~ accordance with

ASTM E119-76 time / temperature requirements. In addition, a hose stream

test as ' described in Appendix VI, Section 5.3.12 of IEEE 634 was to be

applied.

Penetration seal construction consisted of vurious loaded cable

tray and pipe sleeve openings sealed with ther=al insulating wool, bulk.

insulation fiber, silicone and polyurethane foams, insulating boards

such as Marinite, and in sone cases, coatings were applied to the

finished seals.

Test Attendees

Conducting the test project:

Mr. Michael D. Fish, Project Manager, Test EngineerMr. Al Schraeder, Senior Engineering Technologist, Test Coordinator

Witnessing the test for Nuclear Services Corporation:

Mr. Bob Dille, Senior Consultant

Witnessing the test for Northern States Pcwer Co=pany:

Mr. Donald R. 3rown,

also witnessing the test were: ;

Mr. J. R. Thomas, ICMS

Mr. Mike I.. Stine, ICMSMr. Cris R. Conner, Carboline Company

|

l-3

:|

,_ _ _ _ __

1

4 *

-.

I.

'

DESCRIPTION

i

A series of twenty-three block-out cpenings were cast into the

test slab. Three penetrations consisted of 14" x 42" cable tray open-,

ings, and the remainder consisted of 6", 8", and 10" diameter pipe sleeve

openings. A detailed description of each opening is contained in the

discussion of the test slab construction, and the slab layout is shown

in Figures 1 and 2.

All openings were cast into an 8' x 10' x 12" chick concrete

slab. Once cured, the various penetration seal materials identified in

Figure 3, and cabling as described in Appendix I were installed. , Basic

cable loading is shown in Figure 4. The penetration seal materials were

allowed to cu're' prior to the fire exposure test.

The test slab was placed on a horizontal furnace, and exposed to

the standard ASTM E119 time / temperature curve. After three hours the

test slab was lifted in a horizontal position for the hose stream test

and then moved to an area adjacent to the furnace, where it was put on

blocks to cool and view.

1-4

. m

*.

a . a

o s'- C "

!-

. b'4, neff",.

! l |i

|\, ! 'R,"| -5"p (to PLcs.) \W!

: sW? ~-

R 1

1 - 10 " p ( 3 PL C S.)

,

,

|S * ,,

G c r.:1.,, ($ i| tI l,----. 7yn

O b=4

M; - ( ? ,, i

Q - . ..i ! o.c.. -i / + 4 42

, O'"-%

*

M| - p![.-.

.1 7Qj -.

f

Do: i

,. 2S|

,

= a

OO AN

"'

"''oo.

. . ,4, I

, ,. . .

I I '; i'

,, | gf' ,=L u i sb!:|

..

ji i i;

Figure 1. Slab Layout

1-5

. _ - _ _ _ _ - _ - - . .

|_ _ _ _

. .,

i

l.

,

.

..

___ _ _ __ _ _ _ _

______________--- - _ _ _ _

i

|

|_ _ .r _ _ _-___

___ _ _ _ _ _

o

-_ ___ _ _

i 1i ..

I I I I

!- - _ _ _ _ _ _I- - i _ _ __

__ __ _. _ _ _ __ _ l I

l l 8 I | | *1 I l, . ,_ _ _; . _ _ __ _ _ _ __ __

_!_ - AA --_

A - - - - , - - , - II ; . ,AIni in ie. ; .

__ _ _I V_ _. i_V_i __ _ .l |.

! l' '

| | | |

- I_ __ _. l_(- i ; ;

__ _ __

_I |__| 1I i

l i

I |I I |_ _ _ _ - l___ __

_ _ l __ t 1* ! I-

,

i

l

I

l

I

_c c .;, .; _ - -; . . c, _.

1

c _- e__e .e__-. _ _ .

_- a_= e. IsN r ,s- -

Figure 2. Reinforcing Detail

1

1-6 i

1

|

__ _ _ _ _ . _. . __ _ __-.--___.-_I_

.

.

.

.

@@888 ,

8888@PIC Pil Pl2 Pl3 Pl+

P11 '

P--9

P2C

PI8 b5

P7n 8' (4Ot\

.

ft.us EHC

Figure 3. Penetration Identification1-7

__- --_ _ . J

1e e

l

I C "' LC EC % FILL,.

i / 'N'

!OO c.

i ! x0 8 8 O JD| .

i| NCWE NCNE NCME NCM3) INC.M E1 i

.

! f

N |0 /

/,

O /, '

! \ // .

/ ~

xU v|x

,

h1 / / !'

. ,

| % %.) , ,

i // |

,

V pg,,p,g , g L,n g 7 9 y, LLFLU E END

Figure 4. Cable Loading

1-8i

- - _ _ _

O h

-.

.

TEST SLAB

A. Construction

A floor section form (8' x 10' x 12" chick) was constructed

of 12" steel channel with a double mat of No. 8 rebar on 10" centers.

A series of twenty-three penetration openings were cast into the slab.

Three of the penetrations were 14" x 42" cable tray openings. Five

penetrations consisted of 6" pipe sleeve pairs into which were sealed

50 percent fill cable bundles. Eight penetrations consisted of 8"

pipe seals into which were sealed 50 percent fill cable bundles. Two

penetratibns were 8" pipe sleeves with a 1" and a 2" conduit sealed

therein. Four penetrations were 10" pipe sleeves with 3" pipes sealed

within, and one penetration was a 10" pipe sleeve with a 5" steel pipe.

The concrete (f, = 3000 psi) was poured on 20 December 79 and

cured for one week at 400'F, using an enclosure constructed for this

purpose. After the concrete had cured, cable tray supports were welded

to the basic framework. Details of the steel framing and slab layout

are shown in Figure 5.

B. Penetration Loading

All penetrations were loaded as defined by the Northarn States

Power Company Specifications, Revision 3, dated 7 February 1980. Table

1 shows the type and number of cables used in each opening.

C. Sealing of Penetrations

All penetrations were filled by ICMS and SwRI personnel using

the materials defined in the referenced specifications, which are re-

produced in Appendix I. A detailed listing of installation procedures

used during the seal preparation also appears in Appendix I. Photographs

1-9

l

_-

_ _ _ _

.\.

.

.

I

L 3* SEAL' U8 FAC E.

/STEEL Pi r EIS L F i! V E.

/// . _ ", O~

vC

O O Oo o O oO

o o O O //O O O

|.3

1

#5 RESM

-11(' CHANN E L

Figure 5. Schematic of Slab Layout

1-10

.

. . _ _ _ _ _ _ _

_

.

.

D R*D *D ~TAUS wS .S E a

,

i

.

TABLE 1

SI:3 CD N71 CF D3LE PEA ?I'; enc! :1PRCE T NC. 03-531*

SL',3 vt2:351 1

Penettstica Catie Dia. * Conduit * Cable P.anufacture;

W :er

36 1 3/16 7 stnnds/ 24 Ckonate4 c:nd.

21 1 3/16 * s rzads/ 24 Ck: nite4 cend.

33 1 1/3 7 strands / 16 c:ntrol (7) Ck:ni:e4 ::nd. cable wires

38 1 16 cond.s Centrol Cableinside F1:33M .

t

33 1 1/4 1 cond. 6 Genersi !!a::ricw/63 wires Super Corenal Oeoprene(1) outer cop- 250 .tC4per sheath

:D 1 3/16 7 strsnds/ 24 Ckenite4 cend. '

19 1 3/16 7 strands / 24 Ckonite4 cend.

7 1 1/16 7 strands / 68 Ckonite4 cand. Ckocrene. 6 AMG cu

20C0 volts

3 1 1/16 7 strands / 51 Ckonite4 c:nd. Ckoprese

1 19 strands / 13 Kerite14 cond. Type 1 - 600 vol:

9 1 1/8 7 strands / 3 Besten Insula:ed19 c:nd. !;r- at:3 - 600 vol:Hyp - PC *LC-33 12 uG

7/1 7 strsnds 11 Bost:n Insu11:ed12 c:nd. I:r- Wire $30 vol:Hy? - FC * L*- 33 LC ANC

3/1 7 s:Tr.ds/ 46 Bost:n insulated7 : nd. ;ft:t 100 v:1:F7R-HY? 1; wCPC C -33

I

j

1-11

_ _ _ _ _ _ _ _ _ -__ _ - .

|.s .

.

.

TABLE 1 (Continued)

f 3/4 7 stnnds/ 52 3cston Insulated i

!

|9 cand. Epr. Wire - 600 voitMyp - 70 ef.0-33 12 AliG

6 3/4 20 st;sads/ 44 General Elect-ic12 cand. 600 voit

1 1 1/4 37 st snds/ :: Genersi !!ect:1:Single tend. $1-33C07 *~

Type RMi SCC.TMit 73C

i3 11/5 39 strands / 23 Unse-kedi

Single cond.

S 1 1/3 39 strands / 22 Urdcto mSlasle cond.

'17 3/4 20 st;sads/ 39 General Electric ,12 cond. 600 volt

2 1 3/16 7 strands / 21 Ckonite4 cand. 600 voit

! 4 1 1/16 39' strand.s/ :3 UrucsomSingle cand.

37 3/4 20 Stra. sis / 39 Ceneral Elect rteo00 voit

.

'%

k

,

1-12

. m.

.

.

taken during the course of seal installation are shown in Appendix II.

Quality Control documents are in Appendix III. Drawings of the pene-

tration assemblies ajpear in F'gures 6 through 29.

,

h

i

1-13 |

,

d *

-.

TEST FACILITY

The floor penetration assembly fire resistance test was conducted

using a horizontal furnace with an open area of 8 x 10 ft. (See Figure

30). A flue gas opening was provided on one end. Eight (8) Maxon self-

aspirating -burners were mounted in the sides of the furnace. Eight (8),

furnace temperature thermocouples were located 2-1/2 f t inside each wall

at 2 foot centers with the first pair of thermocouples 1-1/2 ft fron

i the flue end of the furnace at the 24 inch elevation. Eighty-seven (87)

ther= occupies on the unexposed side and imbedded in the seal materials

of the s2bject penetration seals were connected to multi-point tem-

I perature recorders with a range of zero to 2000*F and a digital printout!

of 60 points per minute. (See Appendix IV and V). All gas flow to the

hirners was controlled manually and continuously indicated by the average

of six furnace temperature thermocouple readings taken at 12 inches from

the exposed specimen surface. These average temperatures are shown in

Figure 31 and Table 2. The temperatures recorded from the imbedded and

; unexposed side thermocouples are shown in App c.!!x IV.

Since the test was conducted outdoors, a building was erected

around the furnace to meet ASTM E119 standards. This structure was

adequate to prevent excessive air currents over the unexposed surface--

of the slab. The outside temperature was approximately 68'F at the

start of the test.

,

.

I

l-14

|

|

.

_______ _ _ _ _

-- __ _

!. >

I-

| ( ;u s

|'

i

2) recy7'"

'

$ ND}'

hetestva. ft'

p'ruauAc u. .

,/ 2 7'1 8k s,

,

,..dk\ I /. ~/s, /'.(NI / } { ~}%

/ \ ',d Nif'p, ss ,* -

-)X )'s - y. ex / >.,-

.- s -.

,~ .N

- s ,

'

+< ,**

"/

Figure 30. Test Furnace

1-15.

.

. .

.

.

.

QUADREX SLAB 1 - FURNACE AVERAGE* FURtIACE AVERAGE A E119 STD CLF.vE

:500 __ v E119 + 10% = E119 - 10%

000- ~ ~M"~~ - - - - - - "

,

J'

. .. ; - __ .= , 1-

#" _ _ '_'-^'- > ; ---- -

-:

. __

1000__ jf'

/'

d

.f500_

0| ''

' ' ' ' ' ' ' ' 'i i i i i i i i i

0 20 40 ,60 80 100 120 1.40 160 180

TITE &lIfCTES)

TEST DATE: 20 MAR 50 PROJECT tJ3. 03-5917-001.

|

Figure 31. Furnace Temperature

1

1-16

|i

| .

.- . . . _ , _

. ._ .

. .

D D D D TABLE 2Jb W b\0\

| f11RNECE= TEMPERATURE READINGSi

| Scandard [ l|Time I Cu ve I -10: Ac nal I -10: Ti=et

0 70 63 Go 77 01 1 200 t 130 i 6 220 i 1a2 e 400 6 360 i I 440 1 2i3 I 600 1 540 t i 660 1 3'l4 i 300 i 720 i I 830 1 415 i 1000 1 900 i 380 6 1100 i 5i6 4 1100 1 990 4 6 1212 i 6i7 i 1130 1 1035 I i 1265 i 7i

,

6 3 1 1200 I 1080 1 1320 i 3I I

| 9 i 1250 1 1125 I i 1375 i 9'i 10 i 1300 i 1170 i [[20 6 1430 i 10

11 i 1320 1 1138 i i 1452 i 11 i12 i 1350 1 1206 i i 1474 i 12 i13 i 1360 6 1224 I i 1496 i 13 ila i 1380 1 1242 i I L513 a la i13 i 1399 i .1239 1 1245 i 1339 1 13 i16 i 1414 6 1274 i i 1555 i 16 I17 I 1429 e 1296 i i 1372 1 17 113 1 1435 i 1291 I i 1579 6 13 i19 e 1450 1 1205 i i 1395 e 19 I20 1 1462 1 1316 e 13ti i 1603 1 20 i21 i 1474 5 1327 i i 1621 1 21 l22 i 1436 i 1337 i i 1635 1 22 123 i 1498 i 1348 I ! 1548 I 23 i24 1 1300 1 1350 e i 1650 1 24 i25 ! 1510 1 1359 i L380 i 1661 1 25 i26 1 1520 1 1368 I i 1672 1 26 i27 1 1523 4 1375 6 i 1681 1 27 e29 i 1537 i 1363 I i 1691 1 23 129 i 1541 1 1387 I i 1695 1 29 i30 i 1350 i 1395 t 15l3 1 1705 1 30 135 i 1534 i 1425 i 1996 1 1742 1 35 I40 i 1613 i 1452 1 1603 1 1774 6 40 l45 i 1630 1 1467 6 te30 i 1793 i 45 i50 t 1661 1 1495 i te38 i 1827 i 50 t

i 55 i 1631 1 1313 i- l670 1 1349 3 55 i| 60 1 1700 i 1530 I le77 i 1370 8 60 i| 65 i 1713 1 1346 I te45 i 1390 1 65 i! 70 i 1735 e 1361 i 1735 8 1909 ! 70 ei 75 i 1750 I 1575 t 1754 i 1925 1 75 ii 30 I 1765 i 1539 i t7ed i 19e l 30 1e

} 35 - - 1779 t 1601 i 1777 I 1957 i 25 -| 90 1792 i 1613 i l702 i 1971 * 90 i) 45 I 1604 i 1524 ! 1806 i 19i4 i 15 t

00 ' 1313 1433 i t915 i !?94 8 130 i*

105 i 1325 i 164 5~ t 1927 1 2009 i 10 5 e!!35 i 1651 'I t337 4 2019 i 110 i,210 '

113 1343 1 1659 I L344 1 2007 1 113 ''

120 '.350 i 1665 i as47 i 2035 i .20~120 t li62 1 1676 i Is74 6 20-d-

.30+'

-0 i !!75 1637 ' tse0 i 2063 ';0|i.

150 t 1533 a 1679 L3G2 t 2077 i 150 I-

'l t0 19CO I 1713 i la!3 20 C') i 14.) |i'

'i il lit: 1721 i'll. i 2123+

70-

.!0 17 5 i 1733 '433'

__7 '!Oe e .

1-17i

,

- _ ___ - _ _ _ - .__ - - . ._ .- .

. .

.

.

TEST PROCEDURES,

The prepared floor penetration slab with fire stop materials inThe temperatureplace was pt::ca in position on top of the farnace.

recorders were turned on, natural gas was supplied to themulti-point

burners, ignited, and the test clock was started. The uncxposed surface

was continually observed for penetration by flame or hot gases and itsAt the endtemperature monitored, by using the multipoint recorders.

of the three hour fire exposure period, the fuel gas was shut off and,

as quickly as possible, the enclosure building was removed and the test

slab was 'lif ted from the furnace, remaining in a horizontal position.

A 30* spray stream supplied from a 1-1/2 inch fire hose with a spray

scream setting and 75 rst nozzle pressure and 75 gpm delivery was then

directed at the floor penetrat' ion fire stops from a distance of 10 feet

This hose stream test is identifiedto conduct the hoee strean test.

on page 13, Section 5.3.12 of IEEE 634-1978 (see Appendix VI) and is

co=monly referred to as the "NEL-PIA Hose Stream Test." The required

hose stream application tLme for penetrations installed in a 10 x 8 f t

slab was 2 minutes. The time / temperature record of the test is shown

in Figure 31 and Table 2. Figures 30 and 32 show an exploded view of

the test setup.

1-18

i

.

. .

.

f

.

//, .-

. /'

/ // / ,',' --- :r /b- =/=' I' '

A-/

c - - -- 1 ie

-[. ::====: = ,<--

, . . . - - - - -__, f M. // ~

/' ,

,/ /**

,, /

_

;

/ / '.s

-

5 .-- _' , _ -..- - _//\

"'2W

# < o /;

7, ,

/ 0le

/

\//

!

|

> re s a <rywic u>.5 P/s.A/ ACE EY/.cA/SCJ/ 5l.-- VE

~

C ~uRA/ACf

1

Figure 32. Furnace Assembly

,

| 1

I I( 1-19l

i

'e

-

. .

.

D{{9 bTEST RFSULTS

A. Observations

The fellowing are observations =ade during the fire exposure

cast, :he hose stream test, and the post-test inspection.

TABLE 3 - TEST OBSERVATIONS

Tsst Time Event

-0:05 Furnace loaded, systems ready. Moderate wiad,

clear skie s. Temperature approximately 68 * F.0:00 Surners on, Timer on, recceders on, Star: Tes:0:05 Temperature 880 * F0:10 Tempera:ure I L20 * F0:15 Temperature 1245 * F Heavy smoke0:20 Temperature 13 l5 'F Wind affecting burne rs

'

0:25 T empera:ure 1380 * F Within - 10%0:30 Tempera:ure 15 tS * F0:35 Temperature 1556 *F Erecting wind shield0:40 Tempera:ure 1603 *F Catching up to Normal Curve

0:45 Tempera:ure 1630 *F Right on curve0:50 Tempera:ure 1638'F -

iemperature I670 *F0: 2

1:00 Tempe rature 1677 'F Stable

1:10 Temperature 1735 * F Right on curve1:20 Temperature 1768 * F Smeke from cable trays1:30 Temperature 1792 * F Smcke also through Pl6 and Pl7L:40 Temperatur e 1815 * F Stable, right on curve1:50 Temperature 1837 * F2:00 Temperature 1349'F

2:10 Temperature 1374 * F Slightly abcve norm2:20 Temperature 1880 * F2:30 Temperature 1392 * F Scable

,

2:40 Temperature 1918 * F2:50 Tempers:ure 1922 * F3:00 Te=pera:ure i933 *F3:02 End of fire :es:3:C6 Frctec:ive cover remcved3:10 Slab hooked up :c lii:3:L3 S:22- H c se Scr e am T e 5:3:L5 End ci Hese 5:re am Te s:3:13 Slah se:: led i:: examica:i:n

|

1-20

..

. .

*e

.

Post Test Observations1. There was no passage of flame through any penetration duringthe fire exposure test.

2. There was passage of light smoke through the seals, but smokecoming through was cool to the touch.

3. There was no passage of water or flame through any penetrationduring the hose stream test.

B. Summary of Test Results

A fire stop shall be considered as meeting the requirements

far acceptable performance when it remains in the opening during the

fire endurance test and hose stream test within the following limi-tations:

1. The fire stop shall have withstood the fire endurance

test without permitting the passage of flame, or the occurrence of

flaming on any element of the unexposed surface of the assembly for

a period equal to the hourly classification for the fire stop.2. The fire stop shall have withstood the fire endurance test

and hose stream test without developing an opening that would permit

a projection of water from the stream beyond the unexposed surface.3. The transmission of heat through the fire stop during the fire

endurance test for any recorded temperature on its unexposed surface

shall not exceed 700 F'on penetrations involving cable.

Accordingly, the following shows the performance of the pene-,

trations for the test period of three hnurs as documented in the test

observations and in Appendix IV.

1-21

.

-- ,

_ - .

. .

TABLE 4

TE3T RESULTS i

Penetration Condition

Numbe r 1 2 3_

P1 Pass Pas s Pas s

P2 Pas s Pass Pars

P3 Pass Pass Pas s

P4 Pass Pass. Pass

P5 Pass Pass Pass

P6 Pas s Pas s Pass

P7 Pas s Pass Pas s

P8 Pass Pass Pas s,

P9 Pass Pass Pass

PLO Pass Pass Pass

Pil Pass Pas s Pas s,

_.

P12 Pass Pass Pas s

P 13 Pass Pass Pass-

Pl4 Pass Pas s Pass

P15 Pass Pass Pass

P16 Pass Pass Pass

PIT Pass Pass Pass

Pl9 Pas s Pass Pass

P20 Pass Pas s Pass

P21 P as s Pass Pass

P36 Pass Pass Pass

P37 Pass Pass Pass

P38 P as s Pass Pas s

1-22

_ _ _ . ._. - . _ _

\. .

.

. .

To verify the condition of the~ penetration seals after the test,

an examination was made to determine the char depth, the depth of any

remaining insulation material, such as the urethane foam and TIW, and

the condition of the coatings and insulation boards. The results of

this examination are shown in Figures 33 through 55. Photographs pf

the fire exposure period, the hose stream test, and the post test con-

dicion of the penetrations can be found in Appendix II.

,

,

s

1

e

1-23

.

_ _ _ _ _ . _ . - _ . . 7 _ _ . ,

. - -

. .

|

j

SLAB NO. 2

. .vly W:.w;7:.;g x g g g g g g g g y i- j ew_

i by

Michael D. Pish||

NSPFINAL REPORT< ,

eh DUCLERRd. SERV!CESCORPORAT10IlWNorthern States Power Company

414 Nicollet MallMinneapolis, Minnesata 55401

|

2 . ~ 2,,$ Z Z ~ " D " 1 " L ~, * 2 ! C ' 7.,, 1 7 8 0*l ". C L'''' M "d I

JUNE 30,1980

ChUW[

H j -s

' h|I SOUTHWEST RESEARCH INSTITUTE| ,,

SAN ANTONIO HOUSTON~-

1-24

__ - - - - _ . _ _ _ _ . _ _ _ -- - - - - _ _ _ _ . _ _ _ _ _ _ _ . . _ . - . _ _ . . _ , . . _ . , - , _ _ -- -

_

. . . |;

ISUMMARY !

On 24 March 1980, nine block-out penetrations designed by Nuclear

Services Corporation (NSC) for Northern States Power Company and install-

ed by Insulation Consultants and Management Services (ICMS), Carboline Co.

and Scuchwest Research Institute (SwRI) were exposed to a three-hour fire

endurance qualification test following the ASTM E119-76 time / temperature

curve.

The purpose of the test was to obtain a three-hour fire rating for

existing referenced retrofit fire stop designs in accordance with ASTM

E119-76 time / temperature requirements. In addition, a hose stream test as

described in Appendix VI, Section 5.3.12 of IEEE 634 was to be applied.

Penetration seal construction consisted of various loaded cabla tray

and pipe openings filled with thermal insulating wool, silicone and poly-

urethane foams, marinite board, and in some cases coatings were applied to

the finished seals.

TEST ATTENDEES

Conducting the test project:

Mr. Michael D. Pish, Project Manager

Mr. Al Schraeder, Senior Engineering Technologist, Test Coordinator

Witnessing the test for Nuclear Services Corporation:

Mr. Bob Dille, Senior Consultant

Witnessing the test for Northern States Power Company:

Mr. Don R. Brown

Also attending the test were:

Mr. Cris Conner, Carboline Co.

Mr. Mike Stine, ICMS> .s

1-23

-__ __ __ _

. .

.

DESCRIPTION

A series of nine openings were cast into the test slab. Two

penetrations consisted of 48" x 36" cable tray openings; six penetrat-

ions were each 14" x 14" blockout openings; and one penetration con-

sisted of a 6 inch conduit pipe opening. (See Figures 1 and 2).

All penetrations were cast into an 8 ft. x 10 ft. x 12 in. thick

concrete slab. Once cured, the various penetration seal materials

and cabling as described in Appendix I were installed. (See Figure 3.)

These were allowed to cure prior to the actual test.

The test slab was placed on a horizontal furnace and exposed to

the standard ASTM E119 time / temperature curve. After three hours the

test slab was lif ted in a horizontal position for the hose stream test

and then moved to an area adjacent to the furnace, where it was put-on

blocks to cool and view..

1-26

. - _

. .

.

L S'~ Cei

,

__ l I z", lNZ? I _ l@2E ~

t_ u ifI | | ||

bi | s !'

tO y }~o

'

,o, ,

P3C ?26 P251+=/Y /f e /f /42/f

3

6C --- 4m

_a '

- ,

_ Fl& T~

~{ }

u

pg9 P23 P22

js,je 14 Al$ 14 >.14

=

0,

.

' ."2 5 P29 '

4&x3b +5n3G

.,

ht' f Il "I'l I !C"| i 7"Ii i - i ~iFLUE ENO

Figure 1. Slab Layout and Penetration I. D.

1-27

_ .-. . _ _ - ._ _ _- __

. .

i i i [i ! i

'

! || !!'I-

, , ; .

l ! *'.

I[ t 1 -

i ; i

i i [ i'

l i '

| II,

, ,

.

I \6| .| .-

6 t 1 I

I I ! 'g ;

i l I Ie . I

!- | i i-

!l i , I I

| | 1 -1

| 1 | |

| | | I

I l iI

A|Ai I i i aAi.

i 1, ,-

|i :

|| l. I

| | | I

__ __ _ __ _ _ __ I _ li I_ - _ _ _ _ _ _ _

l

: _; , ..;_ __ . ..

'

II--- c- . .e--

SF.C T ICM A-A

Figure 2. Reinforcing Detail

1

|

||

1-28 !

. .

..

|6' FR AlRIE. ISLAND C.15 L E ,-

70 % FILL.

\

=n! %

P30 } P26 Ps

M c N T I d. EL.L OSC % FILL.

!

hh// [M //=

,,

7 y yCUADRIX SLAB 2

P25 P29

! .\ l k

I!!

\# \

/V I

TRAY I G' t*CHT9C'n ! C TP'AY L , G' PRAIR1 "-

C. ISLE,50 % FILL lSLAN C CSLE, 7C % FILL

Figure 3. Penetration Loading

1-29

|_ _ _ _ _ _ . _ _ .

. .

.

TEST SLAB

-

A. CONSTRUCTION

A floor section form (8 ft. x 10 ft. x 12 in. thick) was constructed

of twelve inch steel channel with a double mat of No. 8 rebar on ten inch

centers. A series of nine penetration openings were cast into the slab,

6 inch diameterSix were 14 inch x 14 inch cable tray openings; one was a

conduit pipe opening; and two were 12 square ft. cable tray openings,

3 ft. x 4 ft.

The concrete (f = 3000 psi) was poured on 20 December 1979 and cured

for one week at 400 F, using an enclosure constructed for this purpose.

After the concrete had cured, cable tray supports were welded to the

basic framework. Details of the steel framing are shown in Figure 4.

B. FENETRATION LOADING

All penetrations were loaded as defined by the Northern States

Power Company Specifications, Revision 3, dated 7 February, 1980.

Table I shows the type and number of cables used in each opening.

C. SEALING OF PENETRATIONS

All penetrations were filled by ICMS and SwRI personnel using the

materials defined in the Northern States Power Co. Specification. The

Specification is reproduced in Appendix I. A detailed listing of in-

sta11ation procedures used during the seal preparation also appears in

Appendix I. Photographs taken during the course of seal installation

are shown in Appendix II. Quality Control documents are in Appendix III.

Drawings of the penetration assemblies appear in Figures 5 through 14.

1-30

_

s 3

-.

og g-o

Jo Ju oJU.S.h h

~ 1 3' sa.g.e UMraq

/ r=,./ -Muv e

o'

<.

'

.

''.I:.y

1

"a,qsag'2" CHA Nu g'

|

Figure 4* 3chematic of Slab Layout|

|

1-31

__ __

_

. .

3 Jd e I - .

TABLE 1,

TYPE AND NUMBER OF CABLES USED

St>3 Nt.St3ER 2

30 7/8 20 strands / 6 Kerite

9 cond. Type 1 600 volt

18 1 7 strands / 13 Chonite6 pr. : cond. 600 volt

:S 5/8 5 strands / 4 Seston Insulated7 cond. 600 voit

7/8 *0 strands / 14 Kerite

9 cond. Type 1600 volts

:S $/8- 8 strands / s loston Insulated7 cond. 600 voit

7/3 20 strands / 14 Kerite9 cond. Type 1 600 volts

2: 7/S 20 strsads/ 14 Karite

9 cond. Type 1 600 volts

5/8 7 strands / 4 Boston Insulated7 cand.

23 5/S 7 strands / 4 Boston Insulated'

7 cand.

7/S 20 strands / 14 T.erite9 cond. 7ype 1 600 volts

*4 5/5 7 strands / 4 Soston Insulated7 cand.

7/5 20 strands / 14 Kerite9 cond. Ty7e 1 600 volts

231st tray 3/4 20 strands / 163 Kerite

7 c:nd. Type 1 600 volts

nd trsy 7/3 7 strseds/ 90 Cenerst Electric27 cdad. Polyethelene

Flamenol Control

'9 .

1st trsy 3/4 :D strands / 170 Kerite7 cond. Type 1 600 volts

*nd tray 1 1/4 65 strsads/ 20 General Electri:w/ copper ring Super Controlsingle cand. Geoprene

1 1/4 36 st sads/ *O t.htknownw/ copper ringsingle cond.

1-32

_ _ _ _ _ _ _ - - - - _ _ _ _ _ _

. .

.

TEST FACILITY

The flocr penetrativn assembly fire resistance test was

conducted using a horizontal furnace with an open area of

8 x 10 ft. (See Figure 15). A flue gas opening was provided

on one end. Eight (8) Maxon self-aspirating burners were

mounted in the sides of the furnace. Eight (8) furnace temp-

erature thermocouples vera located 2 1/2 ft. inside each side

wall at 2 ft. centers with the first pair of thermocouples

1 1/2 ft. from the flue end of the furnace at the 24 inchelevation. Thirty-four (34) thermocouples on t~e unexposed

side and imbedded in the seal materials of the nit a subject

penetration seals were connected to multi-point temperature

recorders with a range of 0 to 2,000*F and a digital printout

of 60 points per minute. (See appendix IV and V). All gas

flow to the burners was controlled manually and continuously

indicated by the average of six furnace temperature thermoccuple

readings taken'at 12 in. from the exposed' specimen surface.

These average temperatures are shown in Figure 16 and Table 2.

The temperatures recorded from the imbedded and unexposed side

thermocouples are shown in Appendix IV.

Since the test was conducted outdoors, a building was

erected around the furnace to meet ASTM E119 standards. This

structure was adequate to prevent excessive air currents over

the unexposed surface of the slab. The outside temperature

was approximately 60*F at the start of the test.

1-33

.. .

|

[IhEI*) n ur

/$sst; '

hg,- /'sutva

~ f'.) / A-ruauAc s. m . ,

/- ../c

\ I / )* ,,)

)<x, -

.

_

: / '- f'V... .v2 g. .

Figure 15. Test Furnace

1-34

-___- _-_

. .

.

QUADREX SL AB 2 - FURNACE AVERAGE4

+ FIENACE AVEPAGE A E119 STD C'R/E

2500__ v E119 + 10% , = E119 - 10%

2000-_ __- - - - - - - -

-_

y_ _= = = =-

m s~

-m-- -

_ , , . _;

_ _

_

_,- -

~ 1500- [ ~r - = =~ _ _

~~

--- -

-

|1000__ [/[d f

500_ f '

90 ; | | | | :. ; :

0 20 40 60 80 100 120 140 160 180

TIME (MINUTES)

TEST DATE: 24 MAR SO PROTECT NO. 03-5917-001

Figure 16. E119 Furnace Temperature

1-35

_. _ _ _ ___

. .

DE Yd" tast.I 3Jhlf3)9D0 mJ P ~ b N ' 4 f11 " LL, AST/. I119 Ti=a/Ta=cora:ure Cur ro

,

Il

| S ca= car:! | | [ |*1:e I C u--r e ! -10* I A::uai I 6'0" l * ' e'

O 70_ __ 63 65 77 0t 130 i i 220 1 1i"

1 i -

2 i ' .- e i 360 I i 440 1 2i

3 I .00 i 540 I i 660 1 3L4 i SCO I 720 i I 330 i et5 l 1000 1 900 1 501 1 1100 1 566 1100 1 990 l' i 1212 1 61

'7 1150 i 1035 i i L265 1 7I3 8 1200 i 1030 i i 1320 6 3i

9 i 1250 i 1125 I i 1375 i 9110 i 1300 * 1170 i ile0 i 1430 i 10 i

l 11 1 1320 1133 i e 1452 i 11 il 12 8 1350 i L206 i i 1474 8 12 II 13 1 1360 4 1224 I i 1496 i 13 il 14 6 1330 i 1242 I i L513 i 14

15 i 1399 t 1259 1 1303 6 1539 1 15

16 i 1414 i 1274 i i 1555 i 16 !17 1 1429 t 1286 i i 1572 1 17 i13 1 1435 6 1291 1 1 1579 i 13 619 6 1450 t 1305 I i L59 5 l 19 i20 1 1462 i 1315 I 1444 i 1608 I 20 121 i 1474 t 1327 i i 16 "

'~

22

"

22 1 1436 i 1337 I i 1635 i

23 i ~1498 I 1343 i i 1643 1 23 124 1 1500 1 1350 i i 1650 1 24 i25 i 15 10 i 1359 i 1541 1 1661 6 25 126 i 1520 i 1363 I i 1672 6 26 i27 | 1523 i 1375 6 i 1631 8 27 i2S I 1537 | 1333 I i 1691 i 28 |29 6 1541 1 136, I i 1695 1 29 i30 1 1550 i 1395 i 1602 i 1705 ! 30 i35 1 1534 i 1425 i 1617 i 1742 i 35 I40 1 1613 i 1452 i 1624 1 1774 i 40 i

' 45 i 1630 i 1467 i 1626 i 1793 1 45 350 6 1661 1 1495 i 1642 i 1327 i 50 i55 i 1631 1 1513 i 1672 I 1349 i 55 i60 l 1700 1 1530 I 16G0 1 1370 6 60 e,

65 i 1713 i 1546 8 1712 i 1390 55 170 1 1735 i 1561 i L731 i 1909 i to I

75 i 1750 i 1575 + [754 i 1925 6 75 iI 30 i 1765 i 153G i L7e8 1941 i i01+

6 35 i 1779 | 1601 i 177e i 1957 35 i'

1613 i 1723 i 1971 i 90 690 1 1792 i

, 95 i 1504 i 162a 1737 i 193a i 95 i.

II:0 1 1315 8 1633 i 121- i 1994 i :00i105 i 1526 1643 i 1227 i 2009 i 10 5 i+

,11 1 1335 i 1651 i 1933 1 2019 110 i1115 i 1943 t 1659 | 1837 1 2027 i 113 ''120 i 1350 i 1665 i teso i 2035 i 120130 t l'56; i 1676 i 1656 i 2:43 i 130140 i is75 1637 i !274 i 2063 140 ,. '

>15 0 1533 i 1699 i 1:a: i 207' i 150'

P. 60 1900 '71: I i403 1 2C90 i lic. .

*1 'O 1912 i 17:1 i 1005 :103 i 177 -'

2117 i 13C I-lic i 1925 1733 l910 '.

l-36

_. . - - . .__ _ _ _ - _ _ -

. o

.

TEST PROCEDURES

The prepared floor penetration slab with fire stop materials in

place vs.s placed in position on top of the furnace. The temperature

multi-point recorders were turned on, natural gas was supplied to

the burners, ignited, and the t___ alock was started. The unexposed

surface was continually observed for penetration by flame or hot gases

and its temperature monitored, by using the multipoint recorders.

At the. end of the three-hour fire exposure period, the fuel gas was

shut off and as quickly as possible the enclosure building was re-

moved and the test slab was lifted from the furnace, remaining in a

horizontal position. A spray stream supplied from a 1-1/2 inch fire

hose with a 30' spray stream setting and 75 psi nozzle pressure and

75 gpm delivery was then directed at the floor penetration fire stops

from a distance of 10 feet to conduct the hose stream test. This hose

stream test is identified on page 13, Section 5.3.12 of IEEE 634-1978|' (See Appendix VI) and is commonly referred to as the "NEL-PIA Hose

Stream Test". The required hose stream application time for penetrations

installed in a 10 x 8 ft. slab wzs 2 minutes. The time / temperature re-

cord of the test is shown in Figure 16 and Tablt 2. Figures 15 and 17

1

show an exploded view of the test setup.

1-371

|. .

|

,--.-.--.----.--------.--,fNm/ ,'' A

/ ,

ZI:W&~4 A''

< - i

["i==. , ' " , // ,''

, c -- - - - _ _ ,, p "- N

,/ /

,A-- --.:.----- _ .| / /'

., - /

' -------.-----a

3

/) ' ' '//

/ \

| g.

,

/ \

i

I.

A TEsr SLAB (7'YP/CA !.)3 FOS / ACE E17t.NSC4' SLEEVEC Cf

Figure 17. Test Assembly

1-38

|

!

_ _ _ _ - ~~

. .

.

TEST RESULTS,

A. TEST OBSERVATIONS

The following are observations made during the fire exposure

test, the hose stream test and the post-test inspection.

TABLE 3 TEST OBSERVATIONS ;-

Test Time Event

0:00 Burners eb, timer on, recorders on, Start

0:05 Light smoke / steam, primarily from arcur.d slab edges.Temperature lagging slightly, 80l* F.

0:10 Temperature ll60 * F - Check burner supply,

Better temp rise0:15 Temperature 1303 *F -

0:20 Temperature 1444* F On curve-

0:25 Temperature 1541 * F - Getting slightly ahead0:30 Temperature 1602* F Back off on burners-

0:35 Temperature 1617'F0:40 Temperature 1624* F

Light smoke on unexposed side. Largest concentrationstill from around slab edges.

0:45 Temperature 1626 *F ' - Furnace stable0:50 Temperature 1642 * F0:55 Temperat:tre 1672 *F1:00 Temperature 1699'F1:05 Temperature 1712 * F1:10 Temperature 1731 * F1:15 Temperature 1754* F1:20 Temperature 1768'F1:25 Temperature 1776 *F1:30 Temperature 1793 *F1:35 Temperature 1797'F1:40 Temperature 1817'F

Light smoke from unexposed side, mainly fromP29 and P30. Smoke cold to touch. Bulk of smokefrom around slab edges.

1:45 Temperature 1827'F1:50 Temperature 183 3 * F1:55 Temperature 1837'F2:00 Temperature 1855'F

Same smoke characteristics as at 1:40Furnace smooth, right on curve.

2:10 Temperature 1855 'F2:20 Temperature 1874* F

1-39

.

~ --

.

!

I

TABLE 3 - TEST OBSERVATIONS (CONT'D)

Test Time Event

2:30 Temperature 1885'F2:40 Temperature 1903*F2:50 Temperature 1908'F3:00 Temperature 1920*F

End of fire test3:05 Protective building removed

3:08 Slab Hooked and removed to hose stream test3:10 Hose stream cest3:12 End of Hose Stream Test

Post-Test Observations

1. All nine seals did not allow the passage of flames during thefire test.

2. Light smoke did pass through, primarily through P28 and P29,but smoke was cold to the touch.

3. All penetrations did not allow the passage of water duringthe hose stream test.

B. SUMMARY OF IEST RESULTS

A fire stop shall be considered as meeting the requirements for

acceptable performance when it remains in the opening during the fire

endurance test and hose stream test within the following limitations:

1. The fire stop shall have withstood the fire endurance test

without permitting passage of flame, or the occurrence of flaming on

any element of the unexposed surface of the assembly for a period equal

to the hourly classification for the fire stop.

2. The fire stop shall have withstood the fire endurance test

| and hose stream test without deveieping an opening that would permit a|

| projection of water from the stream beyond the unexposed surf ace.||

l-40

l.

.

. .

.

3 The transoission of heat through the fire stop during the

endurance test for any ::cerded temperature on its unexoosed surface

shall not exceed 700*F on penetrations involving cable..

Accordingly, the following shows the performance of the pene-

trations for the test period of three hours as documented in the test

observations and in Appendix IV.

ConditionPenetration 1 2 3Number

P18 Pass Pass Pass

P22 Pass Pass Pass

Pd3 Pass Pass Pass

P24 Pass Pass Pass

P25 Pass Pass Pass

P26 Pass Pass Pass

P28 Pass Pass Pass

P29 Pass Pass Pass

P30 Pass Pass Pass

To verify the condition of the penetration seals after the test,

an examination was =ade to determine char depth, the depth of remaining

foam and TIW, and the condition of the coatings and insulating boards.

The results of this examination are shown in Figures lo through 26.

Phr.ographs of the fire exposure period, the hose stream test and the

post-test observations can be found in Appendix II.

1-41

.

_ . ___ _ _ _ _. _. -

.. .

|

|

|

|'

,

h3 h[] .hh. . . .n .- rw e,>.,rm .a.. ..

b31+bb )b'

e- , s, m n - e ~ s - w ___ _,

SLAB NO. 3,

\ ; :. si.5 :;xygdg- mgggy;;W- +

by

Michael D. Pish

NSF.FINAL REPORT-

,

% DUC1.E.92' ~ , SER'1!CES

CORPOR.9710Dl -

Northern States Power Company414 Nicollet Mall

Minneapolis, Minnesota 55401

Z C | % = ''.~''~~,|'. C C C ;":'",,0.' ~ 1: 2 0 '"." r l"

JUNE 30,1980 i

/ R <p! , ,y SOUTHWEST RESEARCH INSTITUTE

g // SAN ANTONIO HOUSTONw

1-42

.

_ _ _ _ _ _ . _ . _ . _ .- ._ .- _

. .

i|

SOD'.ARY

on 25 March,1980, six block-out penetrations designed by Nuclear

Services Corporation for Northern States P;wer Company and installed'

by Insulation Consultants and Management Services (ICMS), Carboline Co.4 and Southwest Research Institute were exposed to a three-hour fire en-

durance qualification test following the ASTM E11^-76 time / temperature

curve.

The purpose of the test was to obtain a three-hour fire rating for

existing referenced retrofit fire stop designs in accordance with ASTM

E119-76 time / temperature requirement . In addition, a hose stream test

as described in Appendix VII, Section 5.3.12 of IEEE 634 was to be

applied. ,

Penetration seal construction consisted of various loaded cable

tray and pipe openings filled with thermal insulating wool, silicone4

and polyurethane foams, marinite board, and in some cases coatings

were applied to the finished seals.

TEST AT ENDEES

Conducting the test project:

Mr. Michael D. Fish, Project Manager, Test EngineerMr. Al Schraeder, Senior Engineering Technologist, Test Coordinator

Witnessing the test for Nuclear Services Corporation:

Mr. Bob Dille, Senior Consultant.

Witnessing the test for Northern States ?cwer Company:

Mr. Don R. Brown

Also attending the test was:

Mr. Mike Stine, ICMS

1-43

. .

DESCRIPTION

A series of six penetration openings were cast into the test slab.

Three penetrations consisted of 30" x 45" cable tray openings; two

penetrations were each 14" x 42" cable tray openings; and one pene-

tration was a 10 inch diameter pipe sleeve. (See Figures 1 and 2).

All penetrations were cast into an 3 ft. x 10 ft. x 12 inch thick

concrete slab. Once cured, the various penetration seal materials and

cabling as described in Appendix I were installed. Basic cable load-

ing is shown in Figure 3. The penetration seal macerials were allowed

to cure prior to the actual test.

The test slab was placed on a horizontal furnace and exposed to

the standard ASTM E119 time / temperature curve. After three hours the

test slab was lif ted in a horizontal position for the hose st:,eam test

and then moved to an area adjacent to the furnace, where it was put on

blocks to cool and view.

I

i

||

1-44 |i

|

_ _ _ _ _ , - _. _ . '

. .

.

5'- c " ,-t

Y v"-

15 z" ( Ic 1_II" , . . . ,ecu= a n,ci i i i

-

1

U| | | | | | | 'ej i

727.' ^ l;

30x +5/4 x 42

|

t4 1

P32_._

n ,I

30 x 45 py

=

0

=' I4>+2 'f7

m::e s

.

30x45 %;,,,

.

wf

.a.s. .:|

10"$*

'

| ) .2 5 |: ,f J1 i

s% '-

.f7.4._"fi i

Figure 1. Slab Layout and Penetration Identification

I

1-45

.

e

_

. .

-.

kI _| _ l ! I

! !i || |

| |, ,

, ' || I ||

| | |I !

'I

| ! l. i__ _ __ _

, ,

|. _ _ _ __ _ _ _ _ _ _ _ _ _ _,

t | !1| L_ __ __ !__ .j

Af i || fAi i

; i-

l 1

l I.,_ _ _ q _ _I.

l_- I.

l 1 |-

! l |

l I j_ l__ _j j __ __

L_ _. _ L _!l I

' '

| || ||

- __| _I I || t ,

_ .c _ _ c _ _ _; _ -; _ _ _

_ _ _c _ __:_ _ _: _ ':____

SiEc_Tt o M L-A

Figure 2. Reinforcing Detail

1-46

_ . _ _ _ _

). .

i

._.

MON 7|fELLC 50 % FILL ,,

--MCN TI' E1 LC SC ", FI LL ,

.'m /

/ \% i

I .% %|

* '

L

'

5.i-, '

117PK21 '-

-

AND NC .CASL'" 'I //d!~

\'5 D _ ._

Aw/ a

_

ti'

,

9

2 :

4I

- CAPPED)(N0 CA?LE

Figure 3. Penetration Loading

1-47

. .

.

TEST SLAB

A. Construction

A floor section form (8 f t x 10 ft x 12 in thick) was constructed

of twelve inch steel channel with a double mat of No. 8 rebar or ten

inch centers. A series of six penetration openings were cast into the

slab. Three of the penetrations were 30" x 45" cable tray openings;

two were 14" x 42" cable tray openings; and one was a 10" diameter

(Sch. 40) pipe sleeve into which was sealed a capped 3 inch steel pipe.

The concrete (f, = 3000 psi) was poured on 20 December, 1979 and

cured for one week at 400*F, using an enclosure constructed for this_

purpose. After the concrete had cured, cable tray supports were welded

to the basic framework. Details of the steel framing and slab layout

are shown in Figure 4

B. Penetration Loading

All penetrations were loaded as defined by the Northern States

Power Company Specifications, Revision 3, dated 7 February,1980.

Table 1 shows the type and nunber of cables used in each opening.

C. Sealing of Penetrations

All penetrations were filled by ICMS, Carboline and SwRI personnel

using the materials defined in the Northern States Power Co. specifica-

tions. The specification is reproduced in Appendix I. A detailed list-

ing of installation procedures used during the seal preparation also

appears in Appendix I. Photographs taken during the course of seal in-

\| stallation are shown in Appendix II. Quanlity control documents are in

| Appendix III. Drawings of the penetration assemblies appear in Figures

5 throuf,h 11.

1-48|

-

, . . . .

. .

.

ad , ,

* a RESAR

. .

\ SL .c,

\ .

N% >

. ..q-.

a m>m

$ T E E L l'I P E,

-12" cHwN EL SLEEVE

Figure 4. Schematic of Slab Layout

.

1-49

. .

.

* c

TABLE 1

SIZE MiD TYP! CF C.ULE PER PENETRATICNPROJEC* NC. 03-5917

St.A8 NutBER 3

33 Pipe

34 1 1/4 62 strands / 24 Unknownw/ copper ringsingle cons.

7/8 7 senads/ 30 Seston Insulated9 cond.w/ carton core

27 1 1/4 62 strands / 1 Otknownw/ ringsingle cond.

I 1/3 7 stn nds/ 3 Boston Insulated20 cond. FPR-inP1 7 strands / 33 Ckonite

6 pr. cond.

carbon core

3/4 7 strands / 29 Soston Insulated7 cond 600 volts5/8 20 strands / 3 Ckonitesingle cond.

311st tray 11/16 7 strands / 124 Urtknown2 cond.

w/ ring

2nd tray 9/16 7 strands / 6 Unknown2 cond.w/ ring

1 7 strands / 43 Unknown12 cond.

3rd trsy 7/8 7 strands / 23 Unknown27 cond.

5/3 7 strands / 743 cond. Anaconda Fisme Cuard

IrJ

5/8 7 strands / 27 General Electric19 cond. California 69w/ ring!

1-50

. .

Dg P'D]

*D ~% [hL 3 J'sj e j\1 ef.

iT ABl.E 1, continued '

4th tray 1 1/4 64 strands / 30 Unknownw/ ringsingle cond.

321st tray 1/2 7 strands / 6 Unknown

2 cond.

1 7 strands / 48 Ur.known10 cond.

2nd tray 1/2 7 strands / 6 t,hknown2 cond.w/ ring

1 7 strands / 48 L%known12 cond.

3rd t:sy 5/8 7 strands / 1:3 General Electri:5 cond. Polyer*flene

4th t;sy 1 1/4 64 strands / 30 Lhknownsingle cond,w/rlag

1 7 strands / 3 Unknown7 ps, w/ ground

331st tray 5/3 7 strands / 138 General Electric

5 cand. Polyethylene

2nd tsay 5/8 7 strands / 138 General Electric5 cond. Polyethylene

3rd t;sy 5/3 7 st sads/ 22 General Electric5 cond. Polyethylene

1/2 7 strands / 16 Ckonite: cond.

3/4 13 strands / 75 Essex - 12 AWG IPR7 cond. 600 volts

4th tray 3/S 7 strands / 53 General Electric5 cond. Polyethylene

1 7 strands / 13 Ckonite I

6 pr. cond.,

w/grounscarton core

1 1/4 60 strands / 13 Unknownw/ ringsingle cond.

1-51

i

. .

TEST FACILITY

The ficor penetration assembly fire resistance test was conducted

using a horizontal furnace with an open area of 8 r 10 8:. (See Figure

12). A flue gas opening was provided on one end. Eight (8) Maxon self-

aspirating burners were mounted in the sides of the furnace. Eight (8)

furnace temperature thermocouples were located 2-1/2 f t inside each

side wall at 2-ft centers with the first pair of thermocouples 1-1/2

ft from the flue end of the furnace at the 24 inch elevation. Thirty-one

(31) thermocouples on the unexposed side and imbedded in the seal mat-

erials of the six subject penetration seals were connected to multi-

point temperature recorders with a range of 0 to 2,000*F and a digital

printout of 60 points per minute. (See Appendix IV and V). All gas

flow to the burners was controlled manually and continuously indicated.

by the average of six furnace termperature thermoccuple readings taken

at 12 in, from the exposed specimen surface. These average temperatures

are shown in Figure 13 and Table 2. The temperatures recorded from the

imbedded and unexposed side thernocouples are shown in Appendix IV.

Since the test was conducted outdoors, a building was erected

around the furnace tc meet ASTM E119 standards. This structure was

adequate to prevent excessive air currents over the unexposed surface

of the slab. The outside temperature was approximately 70*F at the

start of the test.

1-52

_

,

. .

.

('

.

nouiI14"DIA(GPUCES) fG.'i~O/R(9 PUCES) /

-

5LEEVE ,

f8"* \'jf.. ~b .4 ,NW[E % / 21 1,

'

$V(/e / .

- @ N.

>?<'-*< N <L /'N ggi'

h,k g, > [/ . ' '

N,,

j ,g '. -+"

. ,./ \

, - .

s ,>-

*e . / %. , s '' ,,1*.

'y-

'

i

Figure 12. Test Furnace

i

)

1-53

:

.. . _

. .

.

QUADREX SLAB 3 - FURNACE AVERAGE* FUtNACE AVERM5E A E119 STD QJtvE

2500__ v EMS + is e EMS - 1M

.

- - -'

2000-- =-=_

_

.

..

_

-- --

;

~ 1500-

-

5

1000__/

500-

0 | | ; ; ; ; ; ;

O 20 40 60 80 100 120 140 160 180

TITE (t11MJTES)

Test DATE: as req es PROJECT NO. 03-5917-001

' Figure 13. El19 Furnace Temperature

;

|

1-54 )

____ _ _

- _ _ _ - _ _ _ _

. .

TA3LE 2.

ASTM E119 Ti=a/Tcmperatura Curva

ScandardTi=e Curve -10% Actual +10: Ti=e

0 70 63 73 77 0

1 6 200 1 130 1 1 220 1 1

2 1 400 1 360 I i 440 1 2

3 I 600 1 340 I I 660 1 3

4 I 800 6 720 I I 880 1 4

5 6 1000 4 900 1 563 i 1100 1 5

6 l 1100 1 990 1 6 1212 l 6

7 I 1150 1 1035 I i 1265 6 7

8 6 1200 I 1080 1 1 1320 i 8

9 1 1250 l 1125 I I 1375 i 9

10 l 1300 6 1170 1 981 1 1430 1 10

11 i 1320 l 1188 I i 1452 I 11

12 1 1350 1 1206 1 1 1474 1 12

13 1 1360 6 1224 4 i 1496 1 13

la 1 1380 1 1242 1 1 1513 6 14

15 1 1399 1 1259 6 1210 6 1539 1 15

16 1 1414 6 1274 e i 1555 i 16

17 1 1429 | 1286 I i 1572 1 17

18 I 1435 | 1291 1 1 1579 6 18

19 6 1450 t 1305 l 1 1595 6 19

20 l 1462 1 1316 6 1279 1 1608 6 20

21 i 1474 1 1327 I I 1621 1 21

22 1 1486 6 1337 I i 1635 i 22 |

23 1 1498 1 1348 I i 1648 1 23

24 1 1500 1 1350 I i 1650 i 24

25 l 1510 1 1359 I 1324 1 166L 1 25

26 1 1520 l 1368 I i 1672 1 26

27 1 1523 1 1375 i i 1681 6 27

23 1 1537 6 1363 ! I 1691 6 2 8__

29 1 1541 1 1387 I i 1695 1 29

30 1 1550 1 1395 1 1390 1 1705 1 30

35 l 1584 | 1525 1 1400 i 1742 6 35

40 1 1613 1 1452 1 1559 1 1774 I 40

45 l 1630 1 1467 I 1o70 i 1793 1 45

50 1 1661 6 1495 i 1755 1 1827 6 50

55 i 1681 1 1513 6 1839 1 1949 1 55

60 1 1700 1 1530 i 1883 | 1370 6 60

65 6 1718 6 1546 6 1848 I 1390 1 65

70 1 1735 l 1561 1 1910 1 1909 4 70

75 1 1750 1 1575 i L924 1 1925 I 75

30 i 1765 I 1589 1 1940 i 1941 1 80

85 1 1779 l 1601 1 1953 1 1957 6 35

90 1 1792 1 1613 1 19e6 6 1971 6 90

95 1 1804 6 1624 1 197e i 1984 1 95

100 1 1815 | 1633 1 1985 i 1994 1 100

105 i 1826 | 1643 1 19o8 1 2009 1 105

110 6 1835 6 1651 6 1941 1 2019 6 110

|115 I 1843 1 1659 | 1919 | 2027 I 115

! 1120 1 1850 6 1665 i 1902 l 2035 1 120

1130 1 1862 4 1676 i 1873 i 2048 I 1301140 1 1375 l 1687 I 18o5 a 2063 1 140!150 l 1888 i 1699 8 l805 a 2077 | 1501160 1 1900 l 1710 1 1891 4 2090 1 1601170 1 1912 1 1721 1905 1 2103 6 170 i!130 l 1925 | 1733 1 1920 1 2117 I 130 i

1-55t

\_ _- -- . _ . . . - . .-

. -

. .,

'.

i

'|

TEST PROCEDURES

The prepared floor penetration slab with fire stop materials in

place was placed in position on top of the furnaco. The temperature

multi-point recorders were turned on, natural gas was supplied to the

burners, ignited, and the test clock was started. The unexposed surface

was continaully observed for penetration by flame or hot gases and its

temperature monitored, by using the multipoint recorders. At the end of

the three-hour fire exposure period, the fuel gas was shut off and, as

quickly as possible, the enclosure building was removed and the test

slab was lifted from the furnace, remaining in a horizontal position.

A spray stream supplied from a 1-1/2 inch fire hose with a 30 * spray

stream setting and 75 psi nozzle pressure and 75 gpm delivery was then

directed at the floor penetration fire stops from a distance of 10 feet

to conduct the hose stream test. This hose stream test is identified

on page 13, Section 5.3.12 of IEEE 634-1978 (See Appendix VI) and is

commonly referred to as the "NEL-PIA Hose Stream Test". The required

hose stream application cima for penetrations installed in a 10 x 8 ft.

slab was 2 minutes. The time / temperature record of the test is shown

in Figure 13 and Table 2. Figures 12 and 14 show an exploded view of the

test setup.

,

,

!

1-56

_

_ _ _ _ _ _ - _ . _

. .

/,---- ,

'' A An / ,'

Ai yil i /t'-

'- -- -

(, ,' -r/j// 1 f a= l /

c -.- - - -, w - .- .'' ,'sv t w na N g,

/ /| / / /, __---------.s- -.

s' s------..-/'

---

B

// \ -.

V. ,

!

,

C

/ \

A) Test Slab (Typical)B) Furnace F_xtension SleeveC) Furnace'

Figure 14. Furnace Assembly

1-57

|._ _

.

. .

TEST RESULTS |

A. OBSERVATIONS

The following are observations made during the fire exp;sure

test, the hose stream test, and the post-test inspection.1

TABLE 3 TEST OBSERV ATIONS-

Test Time Event-0:05 Furnace loaded, systems ready. Light overcast,

light wind, ambient temperature approx. 70 * F0:00 Burners on, timer on, recorders on, Start Test0:05 Temperature 563 *F Holding back on gas0:10 Temperature 981 *F0:15 Temperature 1210*F - Still holding back on gas0:20 Temperature 1279'F0:25 Temperature 1324*F - Increasing gas supply slightly0:30 Temperature 1390 *F - Compensating for early lows0:35 Temperature 1490 *F - Slightly faster rise0:40 Temperature 1559'F - Temp rising smoothly0:45 Temperature 1670 *F - Light smoke, stable0:50 Temperature 1755'F - Now above norm0:55 Temperature 1839'F - Still above norm1:00 Temperature 1699'F - Smooth, on curve1:10 Te mperature 1910* F - High side - readjust1:20 Temperature 1940 *F - back within 10%1:30 Temperature 1966 *F1:40 Temperature 1985'F1:50 Temperature 1941 *F - Stable, all data good2:00 Temperature 1902 * F2:10 Tempe rature 1873 * F2:20 Temperature 1865'F - All smooth and stable2:30 Temperature 1865'F2:40 Temperature 1891 * F - Slightly below norm2:50 Temperature 1905'F300 Temperature 1920 * F' 02 End of fire test,:

3:08 Protective cover removed3:10 Slab hooked up to lift3:12 Start Hose Stream Test3:14 End of Hose Stre am Test3:20 Slab settled for examination

1-58

._

. .

Post Test Observations

1. There was no passage of flame through any penetrationduring the fire exposure test.

2. There was passage of light smoke through the seals, butsmoke coming through was cool to the touch.

3. There was no passage of water through any penetrationduring the hose stream test.

B. SUMMARY OF TEST RESULTS

A fire stop shall be considered as meeting the requirements

for acceptable performance when it remains in the opening during

the fire endurance test and hose stream test within the following

limitations:

1. The fire stop shall have withstood the fire endurance test

without permitting the passage of flame, or the occurrence of flaming

on any element of the unexposed surface of the assembly for a period

equal to the hourly classification for the fire atop.

2. The fire stop shall have withstood the fire endurance test

and hose stream test without developing an opening that would permit

a projection of water from the stream beyond the unexposed surface.

3. The transmission of heat through the fire stop during the

fire endurance test for any recorded temperature on its unexposed|

surface shall not exceed 700 F on penetrations involving cable.I:

Accordingly, the following shows the performance of the pene-

trations for the test period of three hours as documented in the test

observations and in Appendix IV.

1-59

__ _ __ _ _ . _ . .

. _____ ____

. .

l4

||

T AB LE 4i

TEST RESULTS

Penetration ConditionNumber 1 2 3

P27 Pass Pass Pas s

P31 Pass Pass Pass

P32 Pass Pass Pass

P33 Pas s Pas s Pass

P34 Pass Pass Pass

P35 Pass Pas s Pass

.

To verify the condition of the penetration seals after the test,

an examination was made to determine char depth, the depth of any

remaining insulation material, such as the urethane foam and TBV,

and the condition of the coatings and insulation boards. The results

of this exam' ' are shown in Figures 15 through 20. Ph otogr aph s

of the fire exposure period, the hose stream test, and the post test

condition of the penetrations can be found in Appendix II.

1-60

__ _ _ _ _

. .

.

Item 3.1.5(1)Structural Member Coating

Northern States Power Company is committed to coat all Turbine Buildingstructural members in the vicinity of the lube oil reservoirs with asuitable fire retardant coating.

An evaluation of the effects of an unmitigated fire at the turbine lube oilreservoirs to the structural members (beams and columns) supporting thebuilding has been completed. The attached figures illustrate the extentand location of the beams and columns requiring protection.

We will apply a 3-hour coating of Pyrocrete 241 on those columns and beamsper UL design N716 for beams and UL design X-733 or X-736 for columns.

1

l

|

||

2-1

. - -_

. .

.. _ . ,

TYPICAL N0. 1U.L. DESIGN FOR COLUMNS

Design No. X736

Rating 3 Hr.

~'WQ[Npt?.*Ti~'V - ;F(a a a a w -a a

|, f ,i

d

Ia p

f.,..

s.L v_/c ..aa,: ,, 11 si ,-- /,

..

N.W.O.. T Y.A.S.,Y

3

1. Pyrocrete 241*-See table below for appropriate thickness. Prepared bymixing with water according to instructions on each bag of mixture andtrowling in one or more coats to steel surfaces. Min ave density of55 pcf with min ind value of 50 pcf. For method of density determination,see section 3.5, Construction Test Requirements. Surface of material to besmoothly finished with a trowel.

Rating Hr Minimum Thickness, In.3 1 1/4

2. Metal Lath-3.4 lb per sq yd galv expanded steel . Lath lapped 1 in. atjoint and tied together with No. 9 SWG galv steel wire spaced vertically10 in. 0.C.

3. Steel Column-Min size of column, Type W10X49.

Searing the UL Classification Marking.*

2-2

___ . . ___ . - _ _

, .

3

TYPICAL N0. 2

ADPLICATION DETAILS PYR0 CRETE 241

BOXED MEMBERWITH CORNER BEADS

i!i1

Steel Member-

i

Metal Lath

',

Plastic Nose. -

Corner Bead **..

'n ;.' ' Pyrocrete.:-

" Corner bead filled with pyrocrete i

|2-3

_-_ _ -___

. .

TYPICAL NO. 3

U.L. DESIGN FOR BEAMS

DESIGU NO. N715Restrained Beam Ratings-3 Hr.

t

j%7.T1,M C 'U.W($.4. .. .

{$r* .. .S ''- |i'. . .' ' f.0.U.* '.

I . 5.y9gW.... . .|:.t.'. y . . .,

/. p4

@N.:. .

f s...

' *?i:.: ,

h **.

.z. . ., , M.n.-'-

... _ . .

3 2

1. Steel Beam-W8x28 min size.2. Metal Lath-3.4 lbs/sq yd galv or painted expanded steel. Secured to beam

by bending tight around flanges a min of 1 1/2 in toward web of beam.3. Pyrocrete 241*-See table below for appropriate thicknesses. Where metal

lath is present, thicknesses are measured to surface of metal lath, allother thicknesses are measured to steel surface. Prepared by mixing withwater according to instructions and trowel applied on beam surfaces andover lath, as shown. When fluted or corrugated steel floor units areused, crest areas above the beam shall be sealed with pyrocrete.

4

Min avg density of 55 pef with min ind value of 50 pef. For method ofdensity determination, see Section 3.5 Construction Test Requirements.Surface of applied material to be lightly finished with a steel trowel.

Minimum Thickness In.

Rating Hr. Restrained Beam

3 1 1/4Carboline Co.-Type 241

* Bearing the UL Classification Marking.2-4

_ _ - _

. .

'.

TYPICAL N0. 4U.L. DESIGN FOR BEAMS _

Design No. N716Restrained Beam Ratings-3 Hr.

''**'.....'*;.'..'..-|-'' * . . . . ' ' .:'~

-.. <

_

r . . . .

'. , . - **:* *n; . ' .. , . . , , .. . . . * . ' ' -. . .

.-

l |J f" I' 1

"- "

3:7 { *!

2 : # 1'

5 '. 1'

# ):

. . - .

* :~ j .'-

.: J '

. .%w ,, ,, ,,

-:. ..... 1 . iM'

4 3

1. Steel Beaa-W8x28 min size.2. Beam Furring Clips-Spaced not to exceed 27 in. 0.C.3. Metal Lath-3.4 lbs/sq yd galv or painted expanded steel.4. Pyrocrete 241*-See table below for appropriate thicknesses. Prepared by

mixing with water according to instructions and trowel-applied on lathsurfaces as shown. When fluted or corrugated steel floor units are used,crest areas above the beam shall be sealed with pyrocrete. Minavg density of 55 pef with min ind value of 50 pef. For method of densitydetermination, see section 3.5. Construction test requirements. Surface ofr; plied material to be lightly finished with a steel trowel.

Minimum Thickness In.Rating Hr Restrained Beam

3 1 1/4

Carboline Co.-Type 241.* Bearin- the UL Classification Marking, j

1

2-5 |

||

1

. .

.

TYPICAL NO. 5U.L. DESIGN N 716 WITH MARINITE

/ --

/

kI I i IVI livl I I I I I ikil l*il I I I I 9/

/ I I na a a av i

g u uw

9 1% Beam3

# 2

g N Pyrocrete 241

' '{ " L' "_^__

3.4 Galvanized Lath

I 3

12"

r 1

1x x x / x x#

x X X x x

"Beam

1 x x x x x- +

x x l' x x x- i~

l |

3

1. UL Design No. N716 per Typical Dwg No. .

2. Steel grating at El. 715.3. Johns-Manvilles Marinite I Board .1 inch thick, cut 12 inches wide,

running parallel to the entire beam edge that requires protection.4. Marinite hangers-consists of saddle clamps, bolt, nuts and large washer

located approximately 3 inches in from each edge, spaced to provide 1

a minimum of 3 pairs per 8 foot section. l

2-6 ,

1

|

||

1

1, .

'

.

TYPICAL N0. 6|

U.L. DESIGN N 715 WITH MARINITE

diI I IWI IWI I I I I I IVI IWI I I I I(i | n // // // // , g |

.

u V u u

h2 / Beam

h3 _ _ _ _ _ _ h _ _ _ _

" " f' " " g !.

Pyrocrete 241

3.4 GalvanizedLath '

2

-12"

U, i

lx gx x x x |x x x x x )

ABeam

l: : 7: : raI

'

\

2

1. Steel grating at El. 715.2. Johns-Manvilles Marinite I Board .1 inch thick, cut 12 inches wide,

running parallel to the entire beam edge that requires protection.3. Marinite hangers-consists of saddle clamps, bolt, nuts and large washer

located approximately 3 inches in from each edge, spaced to providea minimum of 3 pairs per 8 foot section.

2-7

. .

9

GENERAL ARRANGEMENT - UNIT 1

TYPICAL PC.7, _..

_

|

w.

n

@- : : :--

=

_

,

@-

.

,~.

.

@ @ @ @ :

'

NOTES:

1. PROTECTIVE C0ATING APPLIED 1/2 THE DISTANCEBETWEEN COLUMN R0WS 6 & 7.

2. PROTECTIVE C0ATING APPLIED 1/4 THE DISTANCE ;

BETWEEN COLUMN R0WS F & G.

3. The 73S El. floor is solid concrete.It rests on steel purlins which aretied into the main steel members.Provide Pyrocrete 241 on first 8"of purlins from main steel beams. 2-8

!

.

.

i10iES:

G f E D

1. See General NotesTypical No. 7 ,21'- 6" 21' 6" >* 21'- 6" *><,

2. Beam at 715 El. shall *

have Marinite edging. Seetypical No. (Later).

.

3. Beam and Column UL Designs N-715are N-series and X-series, 36kr N-715_ 36tf N-715 36WF&l4XI-If4 PL T&B El 735respectively..

d - a11 e

x

24kT N-716 21kT N-716 16kF N-716 ,El. 715

'?

14WF136 14WF158

X-736 X-736 El 695

1Column how 7 1

LOOKlHG WEST|

TYPICAL 7A

i

.

_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _

6 7 8s

31'-6" 20'-6" ,

1. See General flotes, Typical ti-715fio. (Later).36W&l 1/4 R. T&B fi-715 27bF

2. Deam at 715 El. shall have El. 735flarinite edging. SeeTypical (Later).

3. Beam and column UL Designare il series and X seriesrespectively. 33F ti-715 N-716 16W g

**y,

E*s

14WF136X-736

L El. 695FLOOR

,

.

COLUMit R0W F

LOOKillG fl0RTil

TYPICAL 7b -

,

,

.

9

. _ _ . _ . . _ _ . _ . _ _ _ _ _ _ _ _ _ _ _ _ - _ _

_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ . .

. .

.

t

fl0TES:

6 7 81. See General flotes,Typical flo. (Later).

31'-6" 20'-0"2. Beam at 715 El. shall have * ** *

Marinite edging. SeeTypical (Later).

3. Beani and column UL Designare il series and X series

f_1-715 36W tt-715 27Wrespectively. EL_.735.

d7 5"

ti-716 24g 11-716 16W__

EL.715**

'

14WF158X-736-

EL.695.

l

* \

i

COLUMit R0W E

LOOKittG fiORill

TYPICAL 7c i

I

- _ - - - - _ _ _ _ _ _ _ _ _ _ _ _ - - - - - J

|. .

~N

~V...

@'

II

O

NOTE 2,/

O11-

:~

n,

1/2 D,

.-

NOTE 1 % NOTE 1

@ u : :_.

..

>

@ @ O @

NOTES:

1. PROTECTIVE C0ATING APPLIED 1/2 THE DISTANCEBETWEEN COLUMN R0WS 11 & 12.

2. PROTECTIVE C0ATING APPLIED 1/4 THE DISTANCEBETWEEN COLUMN R0WS F'& G.

3. The 735 El. floor is solid concrete.It rests on steel purlins which aretied into the main steel members.Provide Pyrocrete 241 on first 8" ;

of purlins from main steel beams. l

GENERAL ARRANGEMENT-UNIT 2

TYPICAL N0.8

2-12

_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ - _ _ _ _

'

. .

.

G f E D

21'-6" 21'-6" 21'-6"= wm - - n

"~ bNOTES:

30W N-715 36g N-715 36tF& it T&B EL. 7351. See General Notes,

~ ~ - , '-~ ~ ~~ ~ ~~ ~'~ ~ ~

Typical No. (Later).__ .._ ____ __ __ _ _ . _ __

,

2. Beam at 715 El. shallhave Marinite edging.

.

See typical (Later). ~$ .

$3. Beam and column ULy 24W * N-716 24tf N-716 16F N-716 EL. 7154 Design are N series and

__ __ __ __

X series respectively.w

__ __ __

14WF136 14WFIS8.

X-736 X-736EL. 695

COLUMN R0W 11l,

LOOKING WEST

TYPICAL 8a

i

1

_ _ _ _ . _ _ _ . _ _ _ _ _ _ _ _ _ _ _-_-

__ _____________ ______ _ _____ - . _

'in:i S: 12 11 10

1. See General, Notes, Typical 36'-6" 20 ' - O", ,No. 8

2. Beam at 715 El. shall haveMarinite edging. See !

.

Typical No. (Later).36Wral-1/.4 Pt 188 N-715 27W N-715 EL. 7353. Beam and Column UL Designs

are N-series and X-series -[ - ,,1 d-,

respectively, a'

N2

33y: N-715 16tr N-716'

EL. 715

I. I I ** I f I I II

X-73614WF136 EL'. 695

COLUMN R0W F

LOOKING NORTil

TYPICAL 8B

-

_ _ - - - - _ _ - - _ - - - _.

,

-_ - _ _ _ _ _ _ _ _ _ _ _ _

- .

.

.

It0TES: 12 11 10

1. See General Notes,31'-6" 20'-0"Typical No. (Later). + >4 >

2. Beam at 715 El. shallhave flarinite edging.See Typical (Later).

36W N-715 27W N-7153. Beam and column UL Design- are N series and X series -,, -~ -~

~-*

respectively.-- -- -- --

14WF158 -j$

2 7W ** N-715 16W N-716EL. 715,

"; T, T_ _I

~~

.T- ~_E T I ~~'

u __ __

14WF158#' X-736

'

EL. 695

COLUMN It0W E

LOOKING NORTil

TYPICAL 8c

i

_ _ _ _ . _ _ _ _ _ _ _ _ _ _ _ _ __ _ _ _ _ _ _ _ ._________l

_ _ _ .. . _ .

NOTES:-

11 10

1. See General Notes, TypicalNo. (Later).

# "2. Beam at 715 El. shall have <Marinite edging. See Typical(Later).'

3. Beam and column UL Design areN series and X series respectively.

27WEl. 735

N-715 .

i a$

7 2

5 .

IfM El. 715

.

El. 695

-;.

COLUMN R0W 1/2 D.

LOOKING NORTil

TYPICAL 8d

|

.

.

. ,

1

|

Item 3.2.5(1)Fire Damper Evaluation

The Fire Protection Safety Evaluation Report contains our committment toreview all fire zones containing safety-related systems and equipment toverify that ventilation paths are pvovided with fire dampers. Whereadditional dampers are deemed necessary, they are to be purchaaed andinstalled.

This review has been completed and a number of locations identified whereins tallation of fire dampers was recommended. Refer to the attached tablelisting these locations.

Three hour, UL lable, curtain type fire dampers are being installed atthese locations. Dampers will satisfy the following s tandards:

a. UL 555 dated May 14, 1979b. NFPA 80, 1979c. NFPA 90A, 1978d. NFPA 90B, 1976e. IEEE-344 (1975) where seismic qualification is needed

All dampers will be equipped with a 165 F fusible link and previded witha corrosion resistant coating.

3-1

-

'

AUXILIARY BUILDING

TABLE A-1

.

DUCT SIZEITEM (Inches) FIRE DAMPERNO. QTY 11 X W DESCRIPTION TAG NO. CATEGORY

l 1 36 x 28 Unit 2. Auxiliary Building through 715 floor ilFD-01 III

near RilR pit

2 1 22 x 14 IIP Office Ceiling flFD-02 III

3 1 12 x 18 llP Office to Auxiliary Building VfD-03 III

4 1 12 x 24 IIP Office to Auxiliary Building VFD-04 III

w 5 2 28 x 28 Unit 2 Turbine Building to Auxiliary Buildi;ig VfD-05-1 III

4 (elevation 718) VFD-05-2 III

6 2 18 x 18 Unit 2 Turbine Building to Auxiliary Building VFD-06-i III

18 dia VFD-06-2 III

7 2 14 x 14 llot Lab to Auxiliary Building VFD-07 III

VfD-08 III

8 1 16 x 16 ilot Lab to Auxiliary Building VfD-09 III

9 1 14 x 24 llot Lab to Auxiliary Building VFD-10 III

10 1 10 x 24 Hot Lab to Auxiliary Building VfD-ll . III ;

11 4 15 dia Auxiliary Building - Change Area (735 E1.) VfD-12 III jjVFD-13 III o

VfD-16 III da |

VFD-17 III y; '

a52

.

O

e

|*

_ _ _ _ _ _ _ .

.

-

.

%

AUXILIARY BUILDING

(continued) .

DUCT SIZEITEM (Inches) FIRE DAMPER

NO. QTY ll x W DESCRIPTION TAG NO. CATEGORY

12 4 15 dia Auxiliary Building-Chance Area (735 EL) IIFD-14 III

llFD-15 III

IIFD-18 III

IIFD-19 III

13 2 42 x 26 Control Room Supply llFD-20 III/ SEISMICllFD-21 III/ SEISMIC

14 2 30 x 62 Control Room Return liFD-22 III/SEISHICw0 llFD-23 III/ SEISMIC j

15 1 40 x 22 General' Vent Exhaust 11F0-24 III

16 1 10 x 18 General Vent Exhaust ilFD-25 III

17 1 26 x 14 General Vent Supply llFD-23 III

18 1 26 x 26 General Vent Exhaust ilFD-27 III

19 1 24 x 18 General Vent Exhaust ilFD,28 III

Ea

1 Y !

8 !

aR

!"

.

!

. _ _ _ .

, .

,

QUAD-3-80-004

NUCLEAR SERVICES CORPORATION& DevillON CF

WORDREXOC R AC A ATIO N

Notes: 1. Table A-1 lists the quantity and size of each type of

three hour fire damper. Two spare fusible links shall

be provided for each damper.

2. HFD designates a Horizontal Fire Damper.VFD designates a Vertical Fire Damper.

3. The duct size given in inches describes the height

and width (HxW) of the inside measurement of the ductfor vertical fire dampers (VFD-XX).

4. The horizontal fire damper (HFD-XX) blade dimension

is listed first.

.

3-4

|. - _ _ .- .- _ _ _ _ _ _

_

. .

D**D "O T.-

.b.soc o .a

TURBINE BUILDING

2-111 !!R. RATED FIRE DAMPERS EACil LOCATIONNSP - PRAIRIE ISLAND

FIRE DAMPER LIST.

LOCATION DUCT SIZE WORK TO BE PERFORMED INSTALLATION COND. N8# '

Elev. 695"-0Wall between

Cut hole in duct for F.D. 6'-4 Above floor.Battery Room 12 x 12 Requiring Patch & Access Duct above battery rack. /o12 & 22

DoorGrid 9

Elev. 715'-0 d7Busroom 25 46 x 10 Remove reg. 6 insert 2- Clear Access 10'7 bot.

Register 46 x 10 F.D. Replace of registerWall between Opening Registerbus Rm. 26 &25

18 x 18 Cut hole in duct for F.D. 13'-0 bot. of duct gRequiring patch and access Clear Access to work.

,, door.

Elev. 715'-0

Busroom 26 Remove sq. thr. companion Work to be installedangh elbow and, insert F.D. f rom switch:; ear Ra.

Wall at Crid D 22 x 22 Rebolt elbow & cut in A.D. Side of wall. 8.

46 x 16 Cut hole in duct for F.D. Wrequiring patch & A.D.

Elev. 715'-0

36 x 18 Cut hole in duct. for F.D. 04/"" *Requiring patch & A.D.

Wall at Crld D Work to be ins t.a ll ett f rom.

Switchg"ar Rm. side of wall.32 x .33 Remove sq. thr. companionangle elbow & insert F.D. gRebolt elbow & cut in A.D.

'

I' l ev . 715'-0i Remove Reg. 6 insert Clear access 10'-7

Bus Roon 16 %x 12 2 - 36 x 12 F.D. Replace Bot. ef ::enister dji

register.

Wall between ,

liuss Rm. 16 5 22 x th Cut hole in duct for F.D. I

15 requiring patch and access! door. C.,;i7,,i

i

|

|

Ii

3-5

r ,

__ _ _ _ _ _

_. _ -

. .

.

Item 3.2.6Fire Pump Barrier

Northern States Power Company has investigated the feasibility of. providinga three-hour fire rated enclosure for the motor-driven fire pump located inthe screen house. A fuel oil fire in this area could make both fire pumpsinoperable without additional protection measures.

A three-hour enclosure for the motor-driven pump has been designed and willbe installed. A summary of the design specifications and sketches of theenclosure design are attached for your information.

)

'.

4-1

--_ __ ... __ _

QUAD-5-80-006*

. . >

Revision 0'

'

DUCLEAR SERVICES CORPORRTIOR- a OsvsSSON Of

'

URDREE'

QQ A AQ AATION

3.14 Fire Pump Enclosure'

3.14.1 Wall Construction

Walls shall be made of nominal 8" hollow concrete block using

blocks which carrysthe Underwriters' Laboratories C-3 Certificate.Walls shall be constructed using materials as outlined in DesignNo. U904 of UL Fire Resistance Index for 3 hours fire resistance.Materials and workmanship conform to Section 3.14.10, Masonry.

3.14.2 Enclosure Roof Construction

The roof of the electric fire pump enclosure shall be of 3 hoursfire resistance construction. It shall be of normal or light

,

'

weight concrete poured in place.

Materials and workmanship conform to Section 3.14.11, Poured-in place

Concrete.

3.14.3 Fire Doors

Provide central, parting, swinging fire doors,a Dutch door on oneside, when opening, to have at least 5 feet 4 inches horizontalclearance. The doors to be Class A 3-hour UL Classification marking.The active leaf door to be automatic with an approved closer fittedwith a 212* (100 C) fusible link. Hinges, latches, stay bolts,astragals and closing equipment to be UL listed for the particulartype door and in compliance with the rules of NFPA No. 80 Fire

Dcors and Windows. The doors should be flush mounted. The inactive

4-2|

!

I

l

* *

QUAD-5-80-006.

Rovision 0* - -

RUCLERR SERVICES CORPORATIONg A Divetr04 08

Mr.JRDREXCO A AQ A ATION

leaves are to have hand and foot and side stay bolts as shown on.

Figure 1, Attachment IV. Flat plate astragals are to be mounted onthe active leaf and the upper inactive leaf to serve as stops forthe active leaf.

The doors are to be provided in a door frame, to be UL listed.Frames and doors to fit into an opening of 10'-6!s" x 5'-4" (seeEngineering Drawings).

|

3.14.4 Paintino and Caulking

The enclosure masonry, door and door frame shall be sealed andpainted to match the existing structure from plant paint stock.

All joints between block work and other types of new constructionshall be caulked unless oto rwise shown on the drawings. All

caulkira shall be grey in color. Caulking materials shall conformto Federal Specification TT-C-00598, Grade No.1.

Penetrations into the intake structure shall be sealed as firebarriers in accordance with Section 3.16, Fire Pump EnclosurePenetrations. -

3.14.5 Construction Materials and Workmanshio

3.14.5.1 Work Included

The work shall include but is not necessarily limited to:

1. All form work including special forms necessary to producearchitectural details and/or to accommodate the work of othersand removal of forms.

2. All concrete reinforcement, placement, bending and formingthereof.

|,

4-3

.

*

, ' , QUAD-5-80-006"

,,Revision 0-

NUCLEAR SERVICES CORPORRTIOR. . . . . . . . . . .

(iRGREXCO A AQ A ATION

3. All concrete and cement finishing; all surface treatment andcuring includi g non-slip finishes and color work.

4. Installation of all reglets, bolts, anchors, cins, sleeves,column anchor bolts, etc.

5. The furnishing of all items required to be, or shown on thedrawings, embedded in concrete, which are not specificallyrequired under other sections.

6. Setting headers and screeds, finishing, curing and protectingconcrete.

3.14.5.2 Work Soecified Elsewhere

1. Unit masonry and reinforcing for it (3.14.10, 3.14.7).

2. Inserts, sleeves, cans, etc. (3.14.12).

3. Materials and testing (3.14.11).

3.14.5.3 Defective Work

Work considered to be defective may be ordered by the Owner to be

replaced, in which case the Contractor shall remove and replace the i

defective work at his expense. Work considered to be defectiveshall include, out not be limited to, the following:

l

a. Reinforcing

Kinks and bends therein which are not scheduled or indicatedon the drawings; reinforcing improperly placed, or previouslyheated.

4-4

QUAD-5-80-006'. -

., ,.Revision 0

AUCI. ERR SERVICES CORPORATIONA Div+04 0F

W .J R D R E XCOR AQ A ATH3N

b. Concrete

1) Concrite in which defective or inadequate reinforcingsteel has been placad.

2) Concrete incorrectly formed or not conforming to detailsand dimensions on the drawings or with the intent ofthese documents, or concrete, the surfaces of which areout of plumb or level.

3) Concrete below specified strength.

4) Concrete containing wood, cloth, or other foreign matter,rock pockets, voids, honeycombs, cracks or cold jointsnot scheduled or indicated on the drawings.

The Owner may consent to allow defective work to be corrected incases where the construction schedule will not permit time forreplacement. The Contractor shall, at his expense, make al? suchcorrections and alleviation measures as directed.

Secure approval of chipped-out areas before patching.

3.14.6 Forming

3.14.6.1 General

The forms shall be smooth, mortar-tight, true to the required linesand grade, and of sufficient strength to resist springing out ofshape during the placing and vibrating of concrete. All dirt,

chips, sawdust and other foreign matter shall be completely removedbefore concrete is deposited therein. Forms previously used shallbe thoroughly cleaned of all dirt, mortar and foreign matter beforebeing reused. Before concrete is placed in forms, all insidesurfaces of the forms shall be thoroughly coated with an approvadform sealer. The form sealer shall be of high penetrating qualityleaving no film on the surface of the forms that can be absorbed bythe concrete or be incompatible with concrete paint.

4-5

|

* ' , , QUAD-5-80-006'

..

R0 vision 0.

DUCLERR SERVICES CORPORRT100

m . .. ... ..MUROREX

CQ A A Q R ATION

All exposed sharp edges shall be chamfered with triangular filletsnot less than 3/4 inch by 3/4 inch unless otherwise directed by theOwner. These fillets and chamfer strips shall be milled from clearstraight grain lumber and shall be surfaced on all sides.

3.14.6.2 Stripping

Forms shall be removed in such manner as to insure the completesafety of the structure.

Side forms may be removed after 48 hours provided the concrete issufficiently hard not to be injured thereby.

3.14.7 Reinforcing Steel

3.14.7.1 Materials

Bars for reinforcing shall be deformed, domestic, intermediategrade bars.

Wire mesh for floors shall be rectangular welded wire fabric ofspacing and gauge as indicated on the plans.

Wire for tieing reinforcement in place shall be No. 18 AWG blackannealed or heavier.

3.14.7.2 General Requirements

Except where specified otherwise herein or shown otherwise on the |plans, reinforcing steel shall be' cleaned, fabricated, placed, tied I

and supported in accordance with Section 2610 of the Uniform BuildingCode. Reinforcing shall not be bent or straightened in any mannerthat will injure the material. All splices for deformed bars shallbe not less than 40 bar diameters but in no case less than 12 inches.

4-6

_. - . -

._ __

i QUAD-5-80-006 - *** **

Revision 0,

RUCLEAR SERVICES CORPORATION4 0iv$04 C8

WORDREXCQ A AQ A ATION

3.14.7.3 Protective Covering

Except where otherwise shown, the minimum concrete coverage for

steel reinforcement shall be as follows:o Reinforcing for walls center of wall or 3/4"o Where concrete is deposited

against ground 3"

o Concrete in forms exposedto earth 2"

o Beams, girders and columns 1 1/2"

3.14.7.4 Installation of Reinforcing

Steel reinforcement shall be accurately placed and shall be supportedand secured against displacement by the use of adequate and propersupporting and spacing devices, tie wires, etc., so that it willremain in its correct location in the finished work. No supportingdevices shall be used that will impede the flow of concrete.

The clear spacing between parallel bars shall be not less than1.1/2 times the nominal diameter of the maximum size aggregate, andin no case less than 1 1/2 inches except at splices which may bewired together.

Wherever possible, splices of adjacent bars shall be staggered.Splice wire fabric at least one mesh wide. Rebending of bars on

the job to fit existing conditions will not be permitted withoutthe approval of the Owner.

3.14.8 Sealing

3.14.8.1 Material

The sealant called for on the dra' wings shall meet the requirementsof the ASA 116.1.

4-7

- _ _ _- - --

__ ___ . _ . ____ _ __ _

' * '

QUAD-5-80-006, . ,.

Revision 0DUCLEAR SERVICES CORPORATION

& Orwit:04 08

URDREICO RRO R ATIO N

The batch date of all caulking compound shall be certified. Materialcolor shall be as approved by the Owner.

'

|

Approval of an equal type of material will be judged upon submissionof a certified copy from a qualified testing laboratory which-

indicates performance characteristics of the material tested inaccordance with ASA 116.1 requirements.

3.14.8.2 Workmanship and Installation

All surfaces must be clean and dry before application. Cleaning

shall include removal of scale, grease, dirt and any (C eign ordeleterious materials. Concrete shall be 28 days old before beingcaulked. A joint filler shall be used as backing, as shown on theplans.

Primer shall be allowed to completely dry before sealant is applied.The mixing and application of the material shall comply closelywith the manufacturer's recommendations. Sealant shall be appliedin such a manner as to remove all air voids. The sealant shall beforced into the opening by means of a caulking gun to the requireddepth without layering the sealant.

After application, the uncured compound shall be tooled and smoothedto a plane surface, as shown on the plans. Sealant shall be allowedto cure for four days before painting or other surface treatment isapplied.

3.14.9 Grouting and Dry Packing

3.14.9.1 General

Grouting includes necessary grouting of base plates.

4-8

* '

QUAD-5-80-006' ' ''

Revisicn 0AUCLTRR SERVICCO CORPORATION

Q. 8 OIVIS.0% ofURDREXQQ ADOR ATION

Dry packing includes those concrete to concrete joints called onthe drawings to be dry packed.

3.14.9.2 Materials

Grout

Sulco grouting iron (Sullivan Company, distributed by Conrad SovigCo.), Embeco-non-shrink grout (Master Builders'), A. C. Horn non-shrink ;; rout e: approved equal.

Dry-Pack

One part Portland cement, 2 1/2 parts clean sand, and the minimumamount of water necessary to hydrate the cement without making the

mixture ).lastic.

3.14.9.3 Workmanship

Dry-Packing

After members to be dry packed are positioned and wedged at trueline and grade, they shall be dry packed in place.

The dry pack shall be hand rammed into place with shingle or othersuitable tool. Care shall be taken to avoid leaving air pockets sothat full bearing can be established. The finished work shall beneatly painted if left exposed.

3.14.10 Masonry

3.14.10.1 Materials

1. Concrete masonry units shall be standard lightweight masonryunits conforming to Uniform Building Code and ASTM C90,,

Grade A, for load bearing units. All masonry units shall be

:

4-9

!

i

QUAD-5-80-006- -

,. ,.

Revisien 0NUCLEAR SERVICES CORPORATION

4 Or4SeClls 08

W MDREXCQ A AQ A ATION

the product of one manufacturer, of one composition throughoutthe work, and uniform in texture. Units shall be cured for a

minimum of 28 days prior to delivery at the site. CMU shall

have Drying Shrinkage tests in accordance with ASTM C426. Themaximum linear shrinkage shall be .04 percent.

The following shapes shall be used:

a. 8" x 8" x 16" two cellb. Special shapes as required for construction

'

2. Portland Cement shall conform to ASTM C150, Type 1.

3. Masonry Cement shall conform to ASTM C91,' Type II.

4. Hydrated Lime shall conform to ASTM C207, Type 5.

5. Aggregate for mortar shall conform to ASTM C144 except that, ;

of sand used for the reinforced block masonry, not less than l

4 percent shall pass No. 100 sieve.

6. Reinforcing Steel Bars shall be intermediate grade new billet I

steel conforming to ASTM A15, with an approved deformationconforming to ASTM A305.

7. Anchorage items other than reinforcing steel bars and rodsshall be heavily galvanized steel of the types indicated on |

the drawings or specified.

8. Water shall be clean and free from deleterious amounts ofacids, alkalines or organic materials.

||

4-10

l1. -

.

QUAD-5-80-00G. . . .

Revision 0RUCLEAR SERVICES CORPORATION

,..m.......

4!ROREIQQ A AQ A ATION

l9. Caulking shall be one part polysulfide, PRC 5000.

3.14.10.2 Mortars

The following mixes shall be used:

1. For reinforced concrete block masonry, conform to the BuildingCode for Type A mortar with a minimum compressive strength of2,000 psi in 28 days, and mixed as follows: 1 part Portlandcement (light colored), minimum 1/4 and maximum 1/2 by volumeof hydrated lime or lime putty, not less than 2 1/2 and notmore than 3 times the sum of the volumes of the cement and -

limes.used of damp loose sand.

2. For grout in reinforced concrete block, as required, provide amix composed of one part Portland cement, and 3 parts sand, towhich may be added not more than 1/10 part hydrated lime, andmay contain an addition of pea gravel equal to maximum 2 partsby volume of cement used. Pea gravel shall be maximum 3/8 inchwith not more than 5 percent moisture.

Add sufficient water to produce consistency for pouring withoutsegregation. Grout shall have a compressive strength of2,000 psi in 28 days.

Mortar, as delivered to the mason, shall have a flow after suction

for one minute, of not less than 70 percent of that immediatelybefore suction when determined by the method described in ASTM C91.

3.14.10.3 Erection of Concrete Block Masonry

All masonry shall be laid plumb, true to line, with level andaccurately spaced courses. Work required to be built in with themasonry (including anchors) shall be built in as the wall construc-tion progresses.

4-11|

|

||

QUAD-5-80-006-

. . . .

Revision 0AUCLERR SERVICES CORPORRT100

& Olv'Si0th 08

CRCREXC O A A Q A ATION

Concrete masonry unit walls shall be erected where shown on thedrawings. Fach course shall be solidly bedded in mortar and verticaljoints buttered full.

Jamb units shall be of shapes and sizes required to bond with wallunits and shall be built in where shown on the drawings, or required.

Standard width of mortar joints for both horizontal and verticaljoints shall be 3/8 inch,

Joints on interior exposed surfaces shall be struck. Joints shallbe tooled in such a manner as to squeeze the mortar back into thejoints, and then struck. No tooling shall be done until after themortar has taken its initial set.

.

After tooling, the exposed surfaces shall be wiped down with burlap.Color of mortar will be selected by the Owner.

Cutting and patching of masonry required to accommodate the work ofothers shall be performed by masonry mechanics. Work shall beneatly performed using approved power saws.

Unfinished work shall be stepped back for joining with new work.Toothing may be resorted to only when specifically approved by theOwner.

Before new work is started, all loose mortar shall be removed and

the exposed joint thoroughly wetted before laying new work.

Reinforcement shall conform to the applicable requirements of theUniform Building Code. Laps shall be a minimum of 40 diacetc>s and

centered in the cells of the concrete block. Masonry shall beadequately doweled to foundations and bond beams.

4-12

_

QUAD-5-80-006 - -

i., ..

Revision 0 .

DUCLERR SERVICES CORPORATION |

Q~dRGREXa nivesioe ce

|'

CQ ARQ A ATION

Masonry unit cells shall be filled where called for on the drawirgs.

Block laying sh-11 be scheduled for filling cells in lifts, eachlift to be 4 feet in height and 15 minutes shall elapse from thetime the last block of any lift is in place until grouting commences.

Joints shall be full buttered, and all cells swabbed and clean offoreign matter. Reinforcing bars shall be secured to the indicatedposition in the cell with approved ties. Grout shall be rodded tocompletely fill the cells and eliminate voids.

Provide clean-outs at bottom of cells as required.

3.14.11 Materials and Testing

Except as herein specified or indicated on the drawings only approvedmaterials conforming to ACI 318 shall be used in the work. Ready-Mix

concrete shall be mixed and delivered in accordance with the require-

ments of ASTM C94.

All materials and workmanship shall conform to and be tested inaccordance with the following requirements and standards:

a. Portland cement shall be Type I or Type III, ASTM C150, for

Portlana cement. If the Contractor, in order to facilitate

his own operation, chooses to use high early-strength cement(Type III) in portions of the work, written permission shallbe obtained from the Owner.

b. All concrete aggregates shall conform to ASTM C33.

c. Mix water shall be clean and' free from injurious amounts ofIoil, acids, alkalis, organic materials, or other deleterious

materials or substances.

4-13

.

, ~-

'' *

QUAD-5-80-006. . . .

Revision 0AUCL. ERR SERVICES CORPORATI0n

g A OlvaS104 0F

MdliT[3i2EE):CQ A AQ A ATIO N

d. Design mix strength shall be 3,000 psi at 28 days for normalweight concrete, unless otherwise shown on the drawings. |

|

!e. Testing of mix shall be Contractor's responsibility. Concrete

test specimens shall be made and cured in accordance with !

ASTM C31 and shall be tested in accordance with ASTM C39. Not

less than three specimens shall be laboratory-cured and testedat seven days and twenty-eight days. The Contractor shallengage the services of an approved testing laboratory.

3.14.12 Structural Steel and Miscellaneous Metals

3.14.12.1 Materials

1. All structural and miscellaneous steel, except as noted below,shall be new and of basic open hearth process steel and ofdomestic manufacture conforming to all applicable requirementsof ASTM A36.

2. iiigh-strength bolts shall conform to ASTM A325..

3. Arc welding electrodes shall conform to AWS A5.1.1

4. Power driven shop and field rivets shall conform to ASTM A502.

5. Primer paint snall be red lead or zinc chromate.

6. All steel indicated as galvanized on the drawings shall behot-dipped galvanized after fabrication.

4-14

. _ . .

, .

'

QUAD-5-80-006~,, ,

Revision 0NUCLEAR SERVICE 0 CORPORRTIOR

A cevtS80N OF

M/JRGAEXCO A AQ A ATH3 N

3.14.12.2 Fabrication

The workmanship shall be in accordance with standard specificationspreviously mentioned and of highest quality found in contemporary Istructural work.

1

Verify all dimensions at job site before fabricating steel.|

Welding shall be done by operators who have been qualifiedstsperform the type of work requirsd (ASME Section IX). Use equipment

which will supply proper currelt as recommended by manufacturer forthe size of electrodes used, adjusted to suit arrangements andthickness of base metals used.

Make allowance for line drop when meters are not adjacent to pointof welding. Measure line voltage with suitable meters.

All connections shall be bolted, riveted, or welded as shown andnoted on the drawings.

Apply one coat of metal primer on all steel not galvanized prior toshipment from fabricating shop. Surfaces to be joined by highstrength steel bolts or field welded shall not be painted in theshop.

3.14.12.3 3rection

Temporary shoring and additional bracing of both existing and newsteel frames shall be provided as necessary to adequately andsafely support any or all loads which may be imposed on the struc-ture durinp construction.

4-15

QUAD-5-80-006. . . ..

Revision 0DUCLEAR SERVICES CORPORATIOD

A OtvilsofW 08

W.GADREXQ Q A A Q A ATIQN

After erection, all field welds, field bolts and abraded or scratched |

surfaces shall be cleaned and given an additional spot coat of thesame prime paint used for shop primer coat.

||

Trim trench : overs in field as required to fit around any incidentalequipment selected and installed under the mechanical portion ofthis job.

3.15 Fire Pump Enclosure Cooler

A room cooler shall be installed (Attachment IV) in the fire pumpenclosure to limit room temperature to less than 104*F (the ambienttemperature rating of the fire pump motor), sized for the maximumanticipated heat losses from the fire pump motor (10% of ratedhorsepower). All cooling air will be 100% recirculated; the enclosureis sealed off by normally-closed fire doors. The cooler fan shallbe automatically controlled to come on at above 80 F room temperaturewhen the fire pump is operating.

The room cooler shall consist of a coil unit and fan unit, combined

in an assembly (Attachment VII), suspended below the enclosure

ceiling.

The coil unit shall be equipped with copper / nickel to minimizescale and corrosion deposits. (Cooling water will be fire water /circulating water). The cooling water shall be piped from a tappedconnection in the fire pump casing, through a stop valva, meteringvalve, and stainless steel tubing to the cooling coil, and back toa fluor drain adjacent to the fire pump. The tubing and coil shallbe arranged to permit complete drainage of the coil, and shall beequipped with a high point vacuum relief valve. In order to assurethat cooling water does not flow to the floor drain except when the

4-16

' '

QUAD-5-80-006., .

Revision 0DUCLERR SERVICES CORPORATION

S D'v81804 08

W/lADREXCQ A AQ A ATION

fire pump is operating, the supply tap from the pump casing shallbe equipped with a spring-loaded check valve (Attachment VII) whichprevents flow due to the static head at maximum river level.

The cooling fan shall be powered from the incoming feeders to thefire pump controller (460V, 3P), using a locally-mounted starter,and adjustable thermostat (temperature switch). Control of t s

fan shall be arranged (using auxiliary contacts in the fire pumpcontroller) so that the fan operates automatically when the firepump is running and the room temperature exceeds 80*F.

The cooler and fan shall be sized to maintain less than 104*Fambient temperature in the enclosure with a maximum circulating

,

water temperature of 80*F, and less than 25 gpm water flow (whichis less than 1% of rated pump capacity). Preliminary calculationsshow that the fan / coil assembly will be about 44"L x 36"W x 23"H,310 lbs., 1072 RPM, 0.45 BHP with a 3/4 HP motor, using about 8 gpmof water (after installation, the metering valve shall be adjustedto the required flow rate).

,

Install as follows:

o Insert reducer bushing in existing plug tap in pump dischargecasing.

o Support tubing from fire main piping or enclosure roof atleast every 5 ft.

o Route tubing to allow maintenance access to the pump (minimum

bend radius 4").o Run tubing discharge to existing fic'r drain,o Suspend the fan-coil cooling unit fron, +he enclosure ceiling

using Vendor-supplied vibration isolators and Contractor-suppliedconcrete wedge anchors. Run' supply tubing to uppermost tap of

the coil (leaving air side) with the vacuum relief valve at

4-17

__ ..

-. _ _ _ _ - - _ . _ _ _ _ _ _ _ _ _

QUAD-5-80-006'- .

Revision 0'- *i

RUCLERR SERVICES CORPORATION|

h .o~,.... ..h.!ROREXCQ A AQ A ATION

high point. Run discharge tubing to the lowermost tap (enteringair side). Cap two remaining connections. Use brass caps,tees and reducers. Slope discharge tubing to drain.

Run 3/8" copper drain tubing from fan-coil housing drain

connection to the floor drain.

3.16 Fire Pumo Enclosure Penetrations

3.16.1 Large Penetrations

The two 10" pipes penetrating the enclosure ceiling shall have 12"pipe sleeves, 8" long, packed with ICMS Product 60 and Fiberfrax asshown on Figure 4, Attachment IV.

3.16.2 Small Penetrations

All conduits and small pipes penetrating the enclosure ceiling orthe concrete block wall shall have 6" pipe sleeves, 8" long, packedwith ICMS Product 60 and Fiberfrax as shown on Figure 5, Attach-

ment IV.

.

!

1

|1

4-18

s

*... ..

APPENDIX A QUA0 3-80-007ATTACHMENT IV QUAD-5-80-006

R'evision 0

2" -- CONC. SLAB(FRAME) k ^9 V'/\

'

a

: : zisa , .

a , , . .a. I

O, 'h* I

INACTIVE ig N -STEEL FRAME -iFILL WITH CEMENTi LEAF

I A-A MORTARi

I |

gi h | @ HEAD & FOOTh_ BOLTS OPERATED

_ _ ,

| MANUALLY FROM-- --

A ;q INSIDE.,rC=3 INACTIVE

Ih LEAF I@ APPROVEDI I AUTOMATIC

I DOORCL0gERI I , 3,, 10' 7" HI g WITH 212 FFUSIBLE LINK,

i|g ARRANGED SO

I| AS TO DISCON-

I ACTIVE NECT OCCASIONALLYi

I LEAF FOR 180 CEGREE1 l OPENING OF 000R.

KNOB1I &O =

i uTG I

I l[ i

$I I d i ||i

i i / ''

;

9 I I li i FLAT PLATE ASTRAGALS

4 6" CURB | 9 TO BE PROVIDEDI ON ACTIVE LEAF AND

ON RIGHT EDGE OF_

2*-8" __ _ 2'-8" _UPPER INACTIVE LEAF.

,,

b ki

3 7.,

STEEL FRAMEASTRAGAL { (SAME AS SEC A-A)ACTIVE LEAF

(ANDUPPER

INACTIVE LEAF) FIG'URC 1

FIRE DOORS.

4-19

. _ _ _ _ - - - . . _ . _ _ _ . _ . _ ,_

__

.

,. .

'

ATTACitMENT IV QUAD-5-80-006MAX RIVER ELEVATION (FSAR 2.7-6) Revision 0 *

,

150 YEAR FLOOD 687.8'

1000 YEAR FLOOD 693.5'RN VA(E[/AMAX. FLOOD 703.6'

APPR0X. EL. 680'-- - - -

C0ll-FAN) UNIT

}| TS.

(MAX. FLOOD DIFFERENTIAL '{'

~

HEAD = 23' = 10 PSI !USE A SPRING LOADED ~~ Y -~CllECK VALVE TO HOLD. | |

10 PSI TO PREVEt:I FLO!! 3/4" OD SS TUBING ||

TO DRAIN DURING lilGli!- - - itsi RIVERLEVELS)

o

f (SPhiNG CHECK VALVE10 PSI CRACKING PRESSURE)1

ELECTRIC-

FIRE PUMP

CONTROLLER

X TilROTTLING VALVE

RIVER BASIN \[FLOORDRAIN

ELECTRICFIRE PUMP

FIGURE 2

FLOW DIAGRAM - FIRE PUMP ENCLOSURE

COOLING UNIT A4-2

_ - _ _ _ - - - - - _ _ _

.

. .

. ..

ATTACHMENT IV QUAD 5-80-006

Revision 0

g* COIL INTAKE

('

b EL 8 '-2"FAN

/

7

MOTOR

DISCHARGE h

/'

N p

\ #L R

ORALN I j\ FIRE. PUMPFIRE N/ \ CONTROLLERWATER"

s

NN -

d /fNL>.

-

N,,MOTOR

op ,

h s-: 9! 2

N

hSEE ATTACHMENT VIIFOR DESCRIPTION

FIGURE 3

FIRE PUMP ENCLOSURECOOLING UNITARRANGEMENT

4-21

l

|*

..

ATTACHMENT IV QUAO-5-80-006Revision 0

_

AREA COVERED BY'

FLAMEMASTIC 77

?

\ 0 )' (g) U'

_24" .

V'

(APPROX.)~

& m GA2" FIBERFRAX DAM

-VOID - FILL WITH (TO,P)'

ICMS PRODUCT 60

*

SEE NOTE 2PIPE SLEEVES

1 '. 9" LONG, 2 REQ.

c.9:egay .o6 AG - - : 9a yc. ., .

6 ab.c C7.:;O -.A.':Q:9a.g. 6.'o' p:-

- %cQaL*:9

'.-

P. h.. - - -

1" FIBERFRAX OAM|

(BOTTOM SIDE)NOTE 2: APPLY 1/8"C0ATING OF FLAMASTIC 77

| 8" REINF. CONC.TO TOP SURFACE ONLY. ROOF SLABFILL CRACKS, IF ANY,AFTER DRYING, WITH SAMEMATERIAL. (PURPOSE IS v CD) Ac

TO XEEP MOISTURE AND/0ROIL OUT OF PENETRATIONS,NOT REQUIRED FOR EIRE NOTE 1: THIS DESIGN IS QUALIFIEDRESISTANCE.) 4TER PIPES BY SUCCESSFUL 3 HOUR FIRE

"' 'oMP DISCHARGE) TEST AT SOUTHWEST RESEARCH

SEC A-A INSTITUTE, THEIR PROJECT N0.03-5734-001, PENETRATION N0. 2TEST REPORT DATED NOV. 30, 1979.

FIGURE 4LARGE PIPE PENETRATIONS

4-22

_

. .

,

. . . .

ATTACHMENT IV QUAD-5-80-006REV8Sf0N 0

- _

AREA COVERED BY hA | AFLAMEMASTIC 77 [

''A A

OV

.

/ ~

VOID - FILL WITH ICMS 2" FIBERFRAX OAM (TOP)

PRODUCT 60

SEE NOTE 2 8" REINF. CONC.

\ .- 1 a ROOF SLAB

%_mg a

O : <3 c.O h, N.9 ';G .:.'

-

o . c; Q " -. .. '

. . y .d ' O P'

|

a..o .. o .a.

.. . -.-.

. . ' - .-. .- .-....3.c ..o,;6::.O..

O . D f. .:. 9 . ...

-

.o. a....

- -. . . . . . , . .

. .

1" FICERFRAX DAM (BOTTOM)

9" LONG , STEEL 3 1/2" CONDUITSEC. A - A (EXISTING)

NOTE 1: THIS DESIGN IS QUALIFIED NOTE 2: APPLY 1/8"BY SUCCESSFUL 3 HOUR FIRE COATING OF FLAMEMASTIC 77

TEST AT SOUTHWEST RESEARCH TO TOP SURFACE ONLY.

INSTITUTE THEIR PROJECT FILL CRACKS, IF ANY,NO. 03-5734-001, PENETRATION A'TER DRYING, WITH SAME

NO. 14, TEST REPORT DATED MilERIAL. (PURPOSE ISNOV. 30, 1979. TO KEEP M0ISTURE AND/OR

OIL OUT OF PENETRATIONSjNOT REQUIRED FOR FIRERESISTANCE.)

|

FIGURE 5 l

TYPICAL SMALL PIPE OR CONOUITPENETRATION

4-23

|

. . .. .. - .

!. .

Item 3.2.8Fire Detector Response

In our letter dated November 30, 1979 we provided response testing reportsprepared by Pyrotronics, Incorporated for a number of different cable types

i used in the Prairie Island plant. At that time, response testing data forseveral other cable types was not available. The data is now available and

,

i is attached for your information.

t

1

i

!

|

|

|

|

5-1

-_. ___ . - _ - - - .. _ _ _ . - - _ _ _ _ _

, .

B AM E N'.

Pyrotron.icJ8 Ridgedale Avenue. Cedar Knolls. New Jersey 07927(201) 267-1300 Cable Address: Baker Pyro

o,,,g

September 29, 1980

Mr. D. BrownNorthern State Power CompanyPrairie Island N.P.S.RR 2Welch, Minnesota 55089

Subject: Pyrotronics Fire DetectorsResponse to Burning Cables

Dear Don:

Please forgive our delay in conducting fire tests on the variouscable samples you sent to us quite some time ago. As you know,we were and still are having some leakage problems in our smokeexhaust system 19 the fire test room. However, we recentlystarted conducting these tests one at a time at off scheduledworking hours and fically have completed the series.

The enclosed test report includes the submitted cable samplesas listed below, and we recorded the responses of only our highvoltage detector models 3/5A and 5B. These detectors are thetype installed in P.I.N.P.S.

Cable Type Test Numbers.

Belden 1 and 2Kerite Black 3 and 4Bcston CSPE 5 and 6Westinghouse FEP 7

Teflon Jacket dia. 8 and 9Okonite EPR 1 and 2 (page 4)

Please note that the last listed test of Okonite EPR was conductedpreviously for Commonwealth Edison. We thought that this informa-tion would be acceptable for your purpose as the cable is of thesame type and manufacturer.

5-2

'O A Division of Baker Protective Services Inc

, .

|

I,

Page 2.:

!

The results of the tests proved very positive and acceptablefast response by the detectors to both flame and heat exposureto all sample cable types. As we get more experience with thesekinds of tests, it is becoming obvious that there is very littledifference in the time of detector response to cable insulatingmaterials.

' We believe that this information will satisfy your needs, how-ever if any questions arise or if any further details are needed,please let me know.

Very truly yours, ,

.

--

Ed BierwirthManager of Training

ECB/ cmc

cc: W. CollinsG. Toth

!

i

l

i

j

e

5-3

,_. . _ _ _ ._. . _ _ _ . _ . _ . _,

- _ _ _ _

~ " ' ' '

* ~

jf/'Oi'O.*u)/<CS .,r:7s=:s 7 =..cr ,G% >x/v/ spa 2pO .

..

}-7 'M,676 /.9 './7 i.) b "wrs ?/11//., ivue, rn,o rwic.c ru=nr en.=. e sz<w -ray

DGMC7~~o 4. 72Cs7 / 77 GT~ L n.***S7~~ .9 7257 9'- ;2S7uw.

NO. R<Cn/# 7m \ n>w ?. Mic.o tbr am

.ss% |S3 oyh M6 2W/ F~3 % /9.s- V |Y7 o n/p 'I9s 2:SC c oc '- * 3 01 a ,

? 4% Mri,127,s

*:7,,

5 '- OMA ep4 ans Gc.of.3h" e44 2-f f. V 30 o% 8h ?'M 2.n{> W& |VL n/o 'i04 /.*fi . yn 'I p/. . ,

/9 p_ _3

.

.

'b | "

C L oc/ ."/ oits; epig os/r ~' t gm$ (5~8. Vx,w? ?yy |55 0% ? Ors 3:60 s.p ec, ?Ad I.'n!) ap 6'}.):i 2.?4) rq M /4 !.

!

/o i

ecocnyey I on> s;.w ci/p essi,9'lts M7 vs MO7 f M a w.::.u n . v *37 on oni 2:% nW& :le op

8 -

i

? .

/QI

! ( .

/2 ,.

'

/7

1/%_

hec wn 5szaw r:eeirz cur. /rsk/yrsw.r-

92/GL $ /IM7~ < ric . 4.''C. ray nA.f,"Ghn1 Mc. S "n-P.v:t 3rr,& -/r,./

\

$ 2 6 % /.: ro x x a.oc.s / r-to ,o | SEs 26 / |~ ~~~-

I

| '

NIRX. % 085 i

f2*MP. W Hc)Ma '7,"2 E $ 2 "/o ~~~ ~-

!' I,ip"'/d 4 -t' or G

,

.2 W 7 3 c r a e t.c r /r r / w J C & n 4./ - - -

A/9 M E ppy/y/;rE 72, ,,w - ?. 7/k .* *;~C*

sVO7 q3 : /?& coa /o4. p,3,, c,9vf_,, . ..

.39rn 3.c.>r/r-. . . . . .

. .. .. . .. . . . . . . .

-

&..

A 5-4D*Fi o

A e mm .

--.~ _. . . - _ _ .

--

.

M c)i K o,v'V S f M E. 7 '.-Gr~S7)w w ?M f' o

@ 0 oW3

' --

: w ? 7h=r '7/2/ A/m/ Ann pc.v&n trnitr cAkcf % -+Naf7'2_-_.

,

ZW* ~~dc. 7'~o.,e., 7r vr- / 7?:5rRE 7 Gs7".2 : 72sr ,'A4 72'3,

an |

?N. M.ic iNo. -1tsscninrm | nw_

<:<.ec.n n eu, ce n two

_/ f3/fn /R.f V 2:IO 3.% 90/>, los on % ,*fo :.<oy,<for,, :n ;?C, 77ty

''2ak' #2. 1 * w

77th :T3 .a'a<28 r, I;!n "M'4 em'' "'

c wsh /9 *ts.v \ 2:72 3 M', car,, /:50 os3 p ..

I

Y C'ti''jjC G o c.s ;f,Et cy.itf OMN M,d

e n,'r|IW 27m 8%6' p 5- 5 . >zm m g 7.v 2:.G' 3.C, t'G 2:2c' mb % I:sf ? %n

to*

Cc o C A- # <r' WI'' G'l'* 5 '''' S '''

7 s.s-e w rn n.v' 2*x 3.Wo % %0 o% 'A f?- ;'@ % W) 2??> 8%|

~8 i ._l I

? l I.

-

;

/OL I

i I// .

1

/2,

|*

/3/Y h

A, <. ,,,g. g,,,a.,s,1,s,i.ewa eaemc ,epie, |

-

h ws r v-c w a x6srouem: s~~-:92)er G' A%y7- 2m . c,%ns vn.es cc.-js

_,n . ,.,,, a |

pos /.,./o ,,- |f'/26 hwsr, r,x e 1 ss<= ris. t ,

|tonx. % cas. |-

':

- - - |7'e~A 7 p. 1 H u m . ??.* f S.2?b'

i2

$$$ Y/ A'ic_W |

3872ic7Dt'fxtir ed ( iI

t

fior i:><,,-e ,curas r o w x >rs.cz irorpi ,rs=-

o:i m o-osvo' rd 3 : gzcopoz.7c57%* -iosra d cs pc (Bosrevo"7 ) Q-i>m e</rd- (<,t$c Novc.ropg

.,

s

7s g7 ,eg, , snare As 76* S7 '*'C'*

..

, _ ____

7'!57-afZ -- M/CS??.</&/fo US C 64 A 3 C CAJDuc 7'oic -r-ff z o/J(r ycp>c zy .g.e

VAA/JS fad'/|?d'A 0(/G2. LO,AD 2. 5 '}bC7'S - (o O/4ifP3,*

A"8 Y 7"2)~ Lot.)JncJ-E7' 2 2 CouDuc7'W' (* P &.5 'z-1)/ A' ' '/FC. 6 '2 0 ''''SCwins Th:-p i ,y*,;,,- /,,,,. .- (",. ,,,. ,.,, ,,y ,.,, ,,,,,.,,,,,,,,,) .

--

|AC)I"|0C/f Y ~|d/.X-i ~~/ "$7~ bDM/V/" //Mf *

'G -

,12/C 7~ 6 7)h./ /"Y. ' f 'S |_'~d. MJ.O_ . _ _ _ _ . _ _ .

NY~d6 "T~Ok M9 ~~~~ V M " G7~~ 2- YS~V8 | DSY Y I ID~}|\ un

%. M.ic. INo. -Dc5cg/p r-m ; n~C

/ f.5/.6~ A /8 $ V 'V$ 'o//p YhpC 4 oc. L~ # .3

'

> 9/n.

?sC L OC CM k OA(H

b / }b~/? /0 t/ Y 0*b lob#

f!

l* l'/GGOt.K #/ 12t/p \*

$ / S~-/ % // s or D */ |'M QRio hbh | ,

,

I |,.

D

CCO(^=#f' I e// /*7 rs-n w m' | 'Vs no 7%

'8 -

i

7

/Q_

l

_/ /'

/s - .-

\'

/3,

,

'f6 f404) J HCKC7p*/)5$ k/V)[ k b'A.CACT

,00.9 / 7~~/o /) | \

k/b5 b/$7*ns)CG | *MS / )1

'

mnx. % oss. \.

feivip. E' sua. 7? f *o n \.

l ! |5'/24 W/ k7/E' ]

.'D&Ks&Yoe bxsir?w/ {'

/E/?Ni e/67 *

sVC7"C 3.* N'^~

. ..

N d f I '2 0 0 A / 0 ' C lE' A $ # f~ % O O Oa V 6 ~ d 5 ",'f W 9 f6/*20<.) J/?C Jao

0A8E6~d3/4' VfC G"l'9U4 .//>'Co/J7A.uGA? .if& Cost'a f-.. .

8sfn (mp>rinfurce uix2cwo): ..

m .,g. - ) < v y3

-

e j' 1 S 5-6 :=

.-. . ,- , , . . - . .

..a / ; m ,,r .' ., o _.,..,,io . , ,/ p /.*,fe J.' ) y*- , s , . , . ,:.-, . * * ~ ~j'sf /g.:.yis / s /- . * . ' . //>*/ /L ."/ 4 ' ? N :' *~".-| f', '

*

> * A v | ? $ ( *n M ?.*.2 m a><!. g'. ..:}.~.fd. .:.C'_. .,)p) (,,', .-)_ . . _ .' {||. * /. ( ,............'s'c.a.>'y # r'

'sn*

:.. ,-

./ ,*'E / < '.~. '".,2*

._ .. . . . . . . . . . _ _--

._ .. .; ... , . . . . _ . . ... -- . ._

. ., .. - , _

a , s [. . * -. . . . . .. . . , . . . . , . , ...*"'s ' ~~. . , . . . . , '* **

* *. Q s~~t'~~( ?" Q /J, ; c'- . '/ s / t. . * * * * i*.~o'

*.

'

..'$._$1/..!~~ \, .l|E'.I .'.E, ,?'.?? b.'.i..*I'.l.i I a' .,,.

"?!'a''' ~~/. . .m .I~' Id E..' /.' #I: 'IIil' l~ '~~

. ' . . .~ ~ ~ ~' *~

/Oe ? *~'.~r'M / 2.''./ './ / .< _ilI'.1 f. . . ~ . . . . ...... . s. .. ..

t Wr* rr.,,a . . .

i ,w: n:.:/, .s :''c 2.rrn 3:'u .a.m I i:n . a A l .

| |! i - r=g,

$ l | f3

\ s fi.,i: ; .s ,s :..,.

:.n 2. % . xu 1.% : s't ' s.w '

| |1 eig It '

'

,

|.

!A *

* e *t* .

.-

b( ).' / * .'/ _3 y |,*,*/ /) .$ *.Y * s $ .) ' Ar.Y) *'

/ ,+

| | | | 1 - i'

|*

| |' '

6.. j

. ....

'

% . . ... . ' .! !,.-

,

|=E . !!$|C}!' '

'N . . h $ b'$ " . .L' ']; / ,*l, .. / . .. .

I r | | t I _.{.b - . . .

,

i . , g- !'

. .

} )> j.

|-

,

,Aj / ' -|

-

I,

! | \E3A 3 % }}- 1

'/.

'

'd Y 1 .'.') 7 .,!. , ,r < >-

,

i 6| .

ji i *

*'

, /- e s- e

|* * *| } ,i,* / 3 * A f oJ ;"*2 * ~ . * , ' A ' '' *

. , .

. . 6 g

I a i'' .e

7*

|

. - - . ... ! t

a.. __.

..

| I! 1

- | . . . . ,'.

,

!.

i -./.~

.. . -_ . . . . - . . . . - _ . . - _ ....t.,..

/. .:r' G . s;y c, /.1'' t a sr)f., 3 f*:o 3 r M o.*e *Joh { _.i

.

J"C/e:- ._[ I;, /W''f. '.l. : . . . . , .c') >~(v> /72. [rr . :.t '. / o ~ :- .t~/. /.. - .P.."'**' * ' _' ... - II

- -... - -. .. ..- , . . _ .

' *

226*f.d.s/ .r-*/O r/ & <.; .. .:::',g':> c

- |-

- -

. . s_.r/._c..a.. . --.-. ..

1 I7 ;,. -

/w, - |min:.-%- o a :.:.. .. . _ . ..|...._.......g_-...__

,

7~9: ,c. .s' /./w.-~_. p .a 9'mo - |-- | I

_

.

.

.- . _'7_ _

'a '*-;*.*~--. . . . . _ . .. . .. . . _ . . _ . . _ _ _ _ ._.{ /.~/ / *~

..

(Wit 5.''s^~Q/, ' N!">'.~ /) Af.W ] ._' C/i'_ .* . ) : 3 t't _ . /,:. [ . ,; _ .-. .. t.__ ._ . . _

'

. . '.j :,

. . . . . . . . . .

res r et .wou: i i<><, c.mrp'ra>r v> '750 / tor p.wn.- ,

s '; ",7~rf.k. - /2N:? #/J.$ ~ [];C. /,.;.''t .s oua .$ pp p pj of *,",r /;. ntonff)/ / t M*, f. ",=, g=;*p f f :, .o to .o r. J'. 9* ,* V ,** /'

O'

.ir; ''sFGo~b'E/'?.\3"fC'O'''' " '

jy $7'!3 - 72 /;,.-;

J W AJ . hi

..5-7

.

-% .g.,--- - , -- w _ . - - . + - - - _ . - a - 9

. . . . . . . .

_

.- .s

G-

s)Q-- - k:1-i - ,,

'3=< l f} 7- , ij <

C'l s}j.( l

i

i..

sq g~s.s

't ({.

'L' 9 u R tLi L- @ (g'f' - y , --- 4

,

--- 7 Sn- --

,g',(,,,, - c- >- n--n

2.O c-,

-

.

1.)11

-N .

.b'.

\\ 'h T b)' t |i

i--

.

\9N, fs

-

?,d4)N\~.

b '-

.p s> . - a.

' uy ,-h. (y,: s.

.

---%. ~q

'd"hi'tc/-

1

k/ u'u o "

V'}iRN( 'ed~k'e ' N i! h.

l i s/ '- K o ,g f}{..'

. '

! _'-

h,. O g4p ? ) Q, q -

M .\~~~ j'NN sf s. .n3 j. i.ch ~~ : s 'W ,

U,0N '" M, . , s e''\;s >|.- ,> k'

-.

i.

r-}N ' ''''.-. q .x . q ''

j[>p~ "' "

j yt('

; O ,

; y~

(D !: .

!, y)Ii,;i--

...

4 c.i1 :1

| .-( . . - -j ..g | t

! ....

___

o. _ _'.s .-,

.

s - - -.

. - -

! '

'| | b, . . . , !-

- c2,

/ //. (**'''-' '

-

ij .

i

j . . .

-

t _.

Tb6ci a p_ |_d, .h"i

!,

3-8,

- . . - - - - , .- - ~ - -- ., -

|*os 9

.

} W &

sVU'.L tCAA SN?WC/J !?/~Pd.S* RFd n: :~~$ 7,s'A}

//0. ./QS72*C7'OK 6 6A /S / f/ W/s#Y~~

'

f3/SA /8.5*V/

3 F3/.s A /? Y

f Ff-e /,4 rim 37 v

7 /*f' - 8 SMM / '7 V

Cnes s 7%osW77??- /.Cy,M. E'5'n'. (4MY -/bp//Yn,;t?n'C/ Bez W

2.M rim!-7y/t- / '''%;e. N D w

3 Bosros)-qsAs -i=ow ;o,cL> #7 5S D/n./3c.ac<

Y wcsn,06Houss Egn .3cox>D. f6Kcad Cwd.fG WS. M/Zodd Ack-67~ A2 codouc7sx? ycfzoa wsdurcc

C A8&G d 'D/4. mnua meroecre u.<>-sowJ

.

'

| mi

<