feasibility study of intelligent pigging in the ring main - BUET
-
Upload
khangminh22 -
Category
Documents
-
view
1 -
download
0
Transcript of feasibility study of intelligent pigging in the ring main - BUET
FEASIBILITY STUDY OF INTELLIGENT PIGGING IN THE RING MAIN TRANSMISSION LINE OF CHATTOGRAM
MUHAMMAD REFAT NOUSHAD BHUIYA
MASTER OF PETROLEUM ENGINEERING
Department of Petroleum and Mineral Resources Engineering BANGLADESH UNIVERSITY OF ENGINEERING AND TECHNOLOGY
DHAKA-1000, BANGLADESH 09 March, 2019
FEASIBILITY STUDY OF INTELLIGENT PIGGING IN THE RING MAIN TRANSMISSION LINE OF CHATTOGRAM
A Thesis Submitted to the Department of Petroleum and Mineral Resources Engineering
In partial fulfillment of the requirements for the Degree of
MASTER OF PETROLEUM ENGINEERING
By MUHAMMAD REFAT NOUSHAD BHUIYA
Roll No: 100613013(P)
DEPARTMENT OF PETROLEUM AND MINERAL RESOURCES ENGINEERING BANGLADESH UNIVERSITY OF ENGINEERING AND TECHNOLOGY
DHAKA-1000, BANGLADESH 09 March, 2019
iv
Abstract
The project work is intended to establish the appropriateness of intelligent pigging as a
single integrity assessment tool for the ring main natural gas transmission line of
Chattogram city. For the purpose of the project work, previous cleaning pigging
operations of the ring main line were reviewed. Significant portions where important
structures/installations had grown up were identified. Records and information regarding
the physical attributes and operational issues were collected from site visits, official
documents and personal communications. Calculations were done to identify the limit of
gas withdrawal rate at different operating pressures within the practiced speed limit of an
intelligent pig. Calculations done are indicative of the ability of the ring main to allow an
intelligent pig run. Alternates of intelligent pigging were checked for their
appropriateness for adopting as an assessment tool for the ring main line. Review of
previous cleaning piggings indicates existence of metal loss issue within the ring main
line. This phenomenon is widely addressed by magnetic flux leakage (MFL) technology
based metal loss intelligent pigging operation. An MFL based intelligent pigging will
cost Tk 1,939.61 /meter on an average. Immediate rehabilitation of the ring main line
would require Tk 39,518.76/meter, Tk 75,813.13/meter, Tk 46,839.52/meter and Tk
40,822.91/meter for segment 1, segment 2, segment 3 and segment 4 respectively.
Assuming yearly 10% flat price escalation, these costs would be Tk 63,645.36/meter, Tk
1,22,097.80/meter, Tk 75,435.52/meter and Tk 65,745.71/meter for the segments
mentioned above after five years. A qualitative risk analysis indicates that the intelligent
pigging of the ring main line is a medium risk project.
v
ACKNOWLEDGEMENTS
All praise goes to the Almighty Allah, who has given the ability to fulfill the
entire work. Without His wish nothing could be done at all.
My profound gratitude and appreciation goes to Mr. Shahriar Mahmud, Assistant
Professor, Department of Petroleum and Mineral Resources Engineering, BUET for
his valuable guidance, encouragement and supervision throughout the entire work.
I would like to convey my heart-felt gratitude to Dr. Mohammad Tamim,
Professor, Department of Petroleum and Mineral Resources Engineering, BUET, for his
valuable suggestions in accomplishing this work.
I would like to thank Dr. Mohammed Mahbubur Rahman, Associate Professor
and Head, Department of Petroleum and Mineral Resources Engineering, BUET for his
valuable guidance, encouragement and supervision throughout the entire work.
I would like to express my deep gratefulness to the senior officials of KGDCL
for their invaluable cooperation in providing necessary data required for this work.
My respected mother has always been a source of inspiration in completing this
work. My beloved wife has contributed greatly by her unprecedented sacrifice and
support. My brothers have been eager to hear the completion of my degree. My
colleagues at KGDCL help their best in fulfilling this work.
vi
TABLE OF CONTENTS
Declaration iii
Abstract iv
Acknowledgement v
Table of Contents vi
List of Tables ix
List of Figures xii
Abbreviations xiii
Units and Symbols xiv
CHAPTER 1. INTRODUCTION 1
1.1 Objectives 2
1.2 Outline of Methodology 2
CHAPTER 2. BACKGROUND STUDY 3
2.1 Review of previous cleaning pigging of the ring main 3
2.1.1 First on stream cleaning pigging (1990) 3
2.1.2 Second on stream cleaning pigging (1994) 4
2.1.3 Third on stream cleaning pigging (2018) 7
2.2 Pipeline integrity management and integrity assessment 9
2.2.1 Important elements of the IM programs proposed by PHMSA 9
2.2.2 Integrity Assessment Methods Proposed by PHMSA 13
2.3 Pipeline features of the ring main 15
2.3.1 Pipeline information 15
2.3.2 Valve type 17
2.3.3 Withdrawal points/ tee connections 17
2.3.4 Major crossings 17
2.3.5 Launching and receiving facilities 17
2.4 Integrity management practices of the ring main 19
2.4.1 Routine Line Patrolling 19
2.4.2 Corrosion protection 20
vii
2.4.3 Data Collection 20
2.4.4 Maintenance actions 20
2.5 Significant portions of the ring main 20
2.5.1 Segment 1 22
2.5.2 Segment 2 22
2.5.3 Segment 3 23
2.5.4 Segment 4 24
CHAPTER 3. METHODOLOGY 27
3.1 Technical Feasibility of intelligent pigging for the ring main 27
3.1.1 Intelligent pigging 27
3.1.2 Tool speed equation 32
3.1.3 Alternates of intelligent pigging 35
3.2 Economic feasibility of intelligent pigging for the ring main 41
3.2.1 Cost of MFL based metal loss run 41
3.2.2 Cost of standard pig launcher and receiver 42
3.2.3 Cost of cleaning run 43
3.2.4 Per meter based cost calculation 44
3.2.5 Replacement cost of the ring main (provisional) 44
3.2.6 Findings/observations from the cost analysis 47
3.3 Risk analysis 48
3.3.1 Risk identification 49
3.3.2 Risk plot 49
3.3.3 Risk register 51
3.3.4 Risk matrix 53
3.3.5 Findings from risk analysis 54
CHAPTER 4. RESULTS AND DISCUSSIONS 55
CHAPTER 5. CONCLUSIONS AND RECOMMENDATIONS 59
5.1 Conclusions 59
5.2 Recommendations 60
References 61
Appendix A 64
viii
List of Valve station along the ring main 64
Gas withdrawal points 66
Appendix B 68
Spread sheet calculation for gas flow range and travel time within speed limit 68
Appendix C 84
Test water quantity calculation 84
Appendix D 85
Quotation correspondence with 3P Services 85
Appendix E 89
Cost of Pig launcher and receiver 89
Appendix F 90
Segment wise provisional materials requirement for construction of the ring main line
90
Appendix G 94
Cost of construction (provisional) of the ring main as per schedule of Petrobangla 94
ix
LIST OF TABLES
Table 2.1 Chemical analysis of sludge of 2nd cleaning pigging 5
Table 2.2 Chemical analysis of the sludge of 3rd pigging 7
Table 2.3 List of Probable Threats to a Transmission Line 12
Table 3.1 Typical composition of flowing natural gas 30
Table 3.2 Gas flow range at different pressures for segment 1 33
Table 3.3 Gas flow range at different pressures for segment 2 34
Table 3.4 Gas flow range at different pressures for segment 3 34
Table 3.5 Gas flow range at different pressures for segment 4 35
Table 3.6 Segment wise test water requirement 36
Table 3.7 Segment wise pond equivalent of water requirement 37
Table 3.8 Pig launcher and receiver cost 43
Table 3.9 Segment wise costs of rehabilitation (cost of materials and cost
of construction) required for the ring main transmission line
45
Table 3.10 Segment wise costs of rehabilitation required per meter for the
ring main line
46
Table 3.11 Segment wise per meter based costs of rehabilitation forecasts
up to the year 2024
47
Table 3.12 Risk register for intelligent pigging of the ring main
transmission line of KGDCL
51
Table 3.13 Percentage of risk level as per the risk matrix 54
Table A.1 List of valve stations along the route of the ring main 64
Table A.2 List of HP-DRS along the ring main transmission line 66
x
Table B.1 Operating pressure 350 psi, gas flow rate: 19-70 MMSCFD 68
Table B.2 Operating pressure 300 psi, gas flow rate: 15-60 MMSCFD 69
Table B.3 Operating pressure 275 psi, gas flow rate: 14-53 MMSCFD 70
Table B.4 Operating pressure 250 psi, gas flow rate: 13-48 MMSCFD 71
Table B.5 Operating pressure 350 psi, gas flow rate: 8-31 MMSCFD 72
Table B.6 Operating pressure 300 psi, gas flow rate: 7-26 MMSCFD 73
Table B.7 Operating pressure 275 psi, gas flow rate: 6-24 MMSCFD 74
Table B.8 Operating pressure 250 psi, gas flow rate: 6-22 MMSCFD 75
Table B.9 Operating pressure 350 psi, gas flow rate: 10-48 MMSCFD 76
Table B.10 Operating pressure 300 psi, gas flow rate: 10-41 MMSCFD 77
Table B.11 Operating pressure 275 psi, gas flow rate: 10-37 MMSCFD 78
Table B.12 Operating pressure 250 psi, gas flow rate: 9-34 MMSCFD 79
Table B.13 Operating pressure 350 psi, gas flow rate: 19-70 MMSCFD 80
Table B.14 Operating pressure 300 psi, gas flow rate: 15-60 MMSCFD 81
Table B.15 Operating pressure 275 psi, gas flow rate: 14-53 MMSCFD 82
Table B.16 Operating pressure 250 psi, gas flow rate: 13-48 MMSCFD 83
Table E.1 Cost of pig launcher and receiver 89
Table F.1 Provisional list of materials required for the construction of
19.94 km 24" 350 psi transmission line (1st segment)
90
Table F.2 Provisional list of materials required for the construction of
2.57 km 16" 350 psi transmission line (2nd
segment),excluding river crossing portion
91
Table F.3 Provisional list of materials required for the construction of
17.78 km 20" 350 psi transmission line (3rd segment)
excluding river crossing portions
92
xi
Table F.4 Provisional list of materials required for the construction of
12.81 km 24" 350 psi transmission line (4th segment)
93
Table G.1 Provisional schedule of rates and quantities for construction of
24" 19.94 km 350 psi transmission line from CGS Fouzdarhat
to Patenga Manifold station (1st segment)
94
Table G.2 Provisional schedule of rates and quantities for construction of
16" 5.07 km 350 psi transmission line from Patenga To Shah
Mirpur Manifold station (2nd segment)
98
Table G.3 Provisional schedule of rates and quantities for construction of
20 inch 19.28 km 350 psi transmission line from Shah Mirpur
to BFIDC Manifold station (3rd segment)
103
Table G.4 Provisional schedule of rates and quantities for construction of
24" 12.81 km 350 psi transmission line from BFIDC manifold
station to CGS Fouzdarhat (4th segment)
108
xii
LIST OF FIGURES
Figure 2.1 Fouzdarhat CGS manifold station. 18
Figure 2.2 Shah Mirpur manifold station. 19
Figure 2.3 Ring main transmission line on geographic map 21
Figure 2.4 Position of ring main line at the CEPZ area. 22
Figure 2.5 Positions of river crossing, CUFL and KAFCO in segment 2 23
Figure 2.6 Positions of road crossing, industrial installations and canal
crossing in segment 3
24
Figure 2.7 Position of 20” Karnaphuli river crossing in segment 3 24
Figure 2.8 Positions of rail crossing, road crossing and Kalurghat
heavy I/A in segment 4
25
Figure 2.9 Positions of rail crossing, road crossing and vicinity of
Chattogram cantonment area in segment 4
25
Figure 2.10 Positions of rail crossing, road crossing near the Fouzdarhat
CGS in segment 4
26
Figure 3.1 Ring main transmission line with physical features 29
Figure 3.2 Risk plot with indication of different risk levels and risk scores 50
Figure 3.3 Risk matrix with risks qualitatively assessed and mapped
for intelligent pigging of the ring main line
53
Figure D.1 Quotation related document 85
Figure D.2 Quotation related document. 86
Figure D.3 Quotation related document. 87
Figure D.4 Quotation related document. 88
xiii
ABBREVIATIONS
API American Petroleum Institute
ASME American Society of Mechanical Engineers
CEPZ Chittagong Export Processing Zone
CGS City Gate Station
CIS Close Interval Survey
CMS Customer Metering Station
CUFL Chittagong Urea Fertilizer Limited
DRS District Regulating Station
ECDA External Corrosion Direct Assesment
EPZ Export Processing Zone
ERW Electric Resistance Weld
GTCL Gas Transmission Company Limited
HCA High Consequence Area
HP-DRS High Pressure District Relgulating Stations
ILI In line Inspection
IM Integrity Management
KAFCO Karnaphuli Fertilizer Company
KGDCL Karnaphuli Gas Distribution Company Limited
LNG Liquefied Natural Gas
MAOP Maximum Allowable Operating Pressure
MFL Magnetic Flux Leakage
NACE National Association of Corrosion Engineers
xiv
NDE Non Destructive Examination
PHMSA Pipeline and Hazardous Material Safety Administration
PIG Pipeline Inspection Gauge
POD Probability of Detection
R-LNG Re-gasified Liquefied Natural Gas
ROW Right of Way
SCC Stress Corrosion Cracking
SWOT Strengths, weaknesses, opportunities and threats
TEG Thermo electric generator
UNITS and SYMBOLS
Cft Cubic Feet
Km Kilometer
MMSCFD Million Standard Cubic Feet per Day
Psi Pounds/sq. inch
Tk Taka
€ Euro
1
CHAPTER 1: INTRODUCTION
Natural gas is distributed to the city of Chattogram by a segmented multi diameter
circular high pressure pipe line network known as the ring main line. This line is operated
by the Karnaphuli Gas Distribution Company Limited (KGDCL), a company under
Petrobangla. Since its commissioning, the ring main line has reached 35 years of
continuous operation. It is a matter of great concern that the line has not undergone any
integrity assessment program yet.
According to the Pipeline and Hazardous Material Safety Administration
(PHMSA) of USA, there are four integrity assessment techniques, namely pressure
testing, in line inspection (ILI)/ intelligent pigging, direct assessment and other
technologies (National Transportation Safety Board, 2015).
ILI/intelligent pigging provides the information required for the majority of
inspection and troubleshooting needs for pipelines. The two most common ILI services
are: metal loss and geometry measurement (Cordell and Vanzant, 2003). The most
proven and mature technology used in ILI services is magnetic flux leakage (MFL).
Other technologies are ultrasonic, eddy current, electromagnetic acoustic transducer
(EMAT) etc.
The ring main line has undergone three cleaning type pigging operations till date.
The intervals of these pigging operations are astonishingly irregular. However, sludge
analyses of these operations indicate presence of metal loss phenomenon within the ring
main line. Therefore, economic implication of MFL technology based metal loss
intelligent pigging is focused in the work. On the other side, technical analysis and a
qualitative risk analysis is done in a rather generalized manner.
2
1.1 Objectives
To assess the current physical condition of the ring main
To establish the appropriateness of intelligent pigging as a single integrity
assessment tool for the ring main line.
1.2 Outline of Methodology
Collection of information through
o Reports
o Personal communication
o Site visits
Evaluate the technical compatibility of the ring main line for an intelligent
tool run in terms of physical and operational features of the ring main.
Examine if there were any alternative integrity assessment methods.
Evaluate all solution options in terms of cost, time, degree of difficulty,
environmental and safety issues etc.
3
CHAPTER 2: BACKGROUND STUDY
2.1 Review of previous cleaning pigging of the ring main
So far, the ring main has undergone three cleaning pigging programs. It is notable
that the programs were done at irregular intervals. For getting necessary impetus for
adopting intelligent pigging as an appropriate and urgent integrity assessment tool for the
ring main, the previous cleaning type pigging are reviewed.
2.1.1 First on stream cleaning pigging (1990). The ring main line came into
operation on 1984. From the inception, with the inclusion of various categories of
customers (power, fertilizer, other industrial, commercial and domestic), the supply of
natural gas was on increasing. Condensate entrained with natural gas (initially at gaseous
state) started to accumulate at the lower points of the pipelines. With the increasing
demand of gas and gas velocity, the cumulative amount of condensate caused surging at
the City Gate Station (CGS) and the Customer Metering Stations (CMS) of the big
industrial customers located downstream and disruption of continuous supply was
experienced. In that perspective, program for on stream pigging (cleaning) was planned.
The first on stream cleaning pigging was done on 9-15th July 1990 (BKB-CTG pipe line
and the ring main line).
After the successful completion of the pigging operation an amount of 7,11,000
liter condensate (BKB-CTG pipeline + ring main) were collected at the CGS, Fouzdarhat.
It is to be noted that this operation was done during yearly Over Hauling of the
Chittagong Urea Fertilizer Limited (CUFL).
No information regarding recommendations is available.
4
2.1.2 Second on stream cleaning pigging (1994). According to Bakhrabad Gas
Systems Limited (1994), gas transmission was comparatively sound until January, 1993.
During this period, no sign of improvement in the quality of gas was observed. Produced
gas from Bakhrabad field at higher temperature (120-1300F), entrained condensate at
gaseous state had got condensed at some distance at ground temperature (85-900F) and
started to accumulate at the lower points of the pipeline. The accumulated condensate in
the form of slug moved towards CGS resulting in surging. By this time, Feni gas field
also had started production. The 210 MW thermal power plant was commissioned and
increasing number of gas consumers resulted in transmission of 160-165 MMSCFD of
gas which was 47% of design capacity of the pipeline. Hence, the factor of higher rate of
gas flow along with higher amount of condensate and with the increase in gas velocity,
huge amount of condensate was depositing at the CGS plant. This time other elements
such as the silica gel from process plant, the corroded part of the pipeline and residue of
liquid hydrocarbon were also found. All this unwanted objects posed tremendous
operational disorder in the CGS. Moreover, the huge amount after crossing the CGS
surged different HP-DRS and Bulk Customers located at the ring main caused multiple
disruption in gas supply especially at CUFL. Important parts of CGS such as pilot,
regulator, transmitter, metering skid of bulk customers were subjected to repeated
maintenance works. Under these circumstances, to maintain the integrity of the
transmission system, second on stream pigging program was scheduled. It was assumed
that huge amount of condensate was accumulated in the pipeline as sample observed in
the CGS plant and the CMS of big industrial customers. It was considered that keeping
all the customers on stream would be risky for the pigging operation. During that time
5
CUFL, 210 MW thermal power plant and 60 MW Shikolbaha power plant were the main
consumers. Simultaneous shutdown of all these would be practically impossible.
However, considering possible risk on plant operation and shutdown of gas supply, an
inter-secretariat meeting including members from BCIC, PDB and Petrobangla was held
and the then honorable additional secretary approved pigging schedule on 03-02-94. It
was executed from 6-9th February 1994. During pigging operation, total 3,87,000 liter
condensate and 2,690 Cubic feet sludge was collected (BKB-CTG pipeline + ring main).
In The second time pigging of the then Bakhrabad Gas Systems Limited (BGSL),
unexpected amount of sludge was collected and sample of which was examined in
BUET, BAPEX, ERL and Bakhrabad gas field. The test results are reproduced in Table
2.1.
Table 2.1
Chemical analysis of sludge of 2nd
cleaning pigging
Sl No. Element BUET BAPEX ERL BKB Lab
1 Carbonaceous substance
(organic) % wt 55.09 38.79 41.322 N/A
2 Dust of Silica Gel % wt - 0.96 0.458 0.458
3 Sand/Mud % wt 9.16 23.03 26.113 26.113
4 Mill Scale (Rust) as Fe2O3 % wt 25.10 30.22 23.097 23.097
5 Mud and Other Identified
Substances % wt 10.65 07.00 - -
Note. Reprinted from On-stream pigging completion report and recommendations,
Bakhrabad Gas Systems Limited, 1994, Cumilla, Bangladesh.
6
Observations regarding the 2nd
pigging. The observations of the 2nd pigging are
as follows:
1. Huge amount of sludge recovery comparing to the 1st pigging.
2. Flow of Silicon dioxide (SiO2) with natural gas at high pressure caused sand
blasting type erosion of the pipeline.
3. Water flow in excess reacts with CO2 to form H2CO3 which might cause
corrosion of the pipeline.
4. Carbon (C) in mild steel pipeline in presence of water act as a cathode while the
iron (Fe) acts as anode allowing formation of local Galvanic cell to cause
corrosion.
Recommendations of the 2nd
pigging. The recommendations of the 2nd pigging
are as follows:
1. Flow of gas at ground temperature from the process plant.
2. Investigation should be done regarding the source of SiO2 in pipe line to make
necessary renovation of the process plant.
3. Pipe line internal should be inspected by intelligent pigging due to corrosion and
erosion. Otherwise explosion of high pressure gas line may cause huge loss of life
and property.
4. Inform BGFCL to maintain the quality of gas in specified standards.
7
2.1.3 Third on stream cleaning pigging (2018). After the second pigging of the
ring main, due to different unavoidable circumstances, a huge gap has been created to
perform on stream pigging of the pipe line. However, before inclusion of re-gasified
liquefied natural gas (R-LNG) in the KGDCL network, it had become inevitable to
perform another cleaning pigging of the ring main. This time, the project was done by a
third party. This cleaning pigging was done from 27-29th July 2018. After completion of
the pigging operation, about 1000 gallons of sludge was collected.
Chemical analysis of sludge. The chemical analysis of the sludge was done in
BUET. The analysis results are reproduced in Table 2.2.
Table 2.2
Chemical analysis of the sludge of 3rd
pigging
Sl No. Test parameters Results Unit Method
1 Total moisture 2.55 wt %
ASTM D 3172 2 Volatile matter 22.03 wt %
3 Fixed Carbon content 20.89 wt %
4 Ash content 54.53 wt %
5 Sulfur content 0.91 wt % ASTM D 3177
6 Calorific value 2885 kcal/kg ASTM D 5865
7 Iron (Fe) content 43.0 wt %
Spectrophotometric
method
8 Magnesium (Mg) content 23.56 wt %
9 Calcium (Ca) content 5.89 wt %
10 Silica (SiO2) content 3.71 wt %
11 Arsenic (As) content Nil Ppb
(continued)
8
Sl No. Test parameters Results Unit Method
12 Copper strip corrosion (10%
aqueous slurry of the sample)
1b Slight
tarnish - ASTM D 130
13 Water solubility (Dissolved in
distilled water) 32.44 wt %
Gravimetric analysis 14 Acid solubility (Dissoloved in
concentrated HCl) 82.9 wt %
15 Base solubility (Dissolved in
2N NaOH) 52.7 wt %
16 pH@ 29.4 0C (10% aqueous
slurry of the sample) 7.7 - pH meter
Note. Reprinted from On-stream pigging completion report and recommendations of 57
km multi diameter ring main line of Karnaphuli Gas Distribution Company Limited,
Libra Enterprise, 2018, Chattogram, Bangladesh.
Recommendations of the 3rd
pigging. The recommendation of the 3rd pigging are as
follows:
1. Installation of standard pig launchers and receivers with quick opening door and
proper pressure equalizer and kicker lines for ease of pigging in future.
2. Run intelligent pig to see the condition of the pipe line especially possible
thinning of pipe wall, its allowable operating pressure and any other defect that
would seriously affect the integrity of the pipeline in future.
Table 2.2 (continued)
9
3. Should closely coordinate with GTCL to ensure the pressure of the ring main at
300 psi or below.
(Libra Enterprise, 2018)
2.2 Pipeline integrity management and integrity assessment
Ensuring Transmission Pipeline safety and environmental protection in areas of
High population density and in areas sensitive to environmental damage is an inevitable
need. Pipeline related incidents worldwide suggest pipeline operators/companies to
enforce stringent integrity management plan for the safety of their pipeline.
U.S.A’s Pipeline and Hazardous Material Safety Administration (PHMSA) enact
Integrity Management Regulations as a result of several Pipeline incidents throughout the
year from 1991-2000. Employment of this regulations are destined for providing
enhanced protection for areas with human inhabitant and structures which are under risk
in case of pipeline failure. The regulations include a mix of performance-based and
prescriptive requirements, with the intent of providing sufficient flexibility to reflect
pipeline-specific conditions and risks without imposing unnecessary burdens on
operators. The regulations require gas transmission pipeline operators to develop an IM
program for their pipeline segments located within an HCA (National Transportation
Safety Board, 2015).
2.2.1 Important elements of the IM programs proposed by PHMSA.
According to National Transportation Safety Board (2015), important elements of the IM
programs proposed by PHMSA are as follows:
i. High consequence area (HCA) identification: the process of determining those
portions of a pipeline system for which a failure would have the highest impact.
10
ii. Threat identification, data integration, and risk assessment: the process of using
all available information to determine which failure mechanisms each pipeline
segment within an HCA is susceptible to and then estimating the risk of pipeline
failure due to these mechanisms; pipeline segments are ranked according to their
risks to create a prioritized schedule for integrity assessments, in which pipeline
segments are inspected or tested to verify their integrity.
iii. Baseline assessment plan: the first schedule for completing integrity assessments,
including the selection of assessment method(s) appropriate to the threats
identified; a baseline assessment plan must also be completed whenever new pipe
is installed or a new HCA is identified.
iv. Direct assessment: one method of integrity assessment, used only for assessing
corrosion threats; a direct assessment plan is required only if an operator uses this
assessment method. Other integrity assessment methods are allowed, such as
pressure testing and in-line inspection (ILI). The requirements regarding the
selection and use of these methods are included in the program elements of
baseline assessment plan and continual evaluation and assessment.
v. Confirmatory direct assessment: a direct assessment method used for integrity re-
assessments.
vi. Remediation: the process of repairing or replacing pipeline defects found during
integrity assessments.
vii. Preventive and mitigative (P and M) measures: actions which lower the likelihood
(preventive measures) or reduce the consequences (mitigative measures) of a
11
pipeline failure. P and M measures are used to reduce the risk of some threats that
cannot be assessed.
viii. Continual evaluation and assessment: the ongoing practice of repeating each of
the processes described above, including the schedule and methods for integrity
reassessments, to ensure the continued integrity of a pipeline.
Each operator’s IM program must contain supporting plans and procedures
covering performance measures, recordkeeping, and management of change, quality
assurance, communication and documentation.
PHMSA requires pipeline operators to identify and evaluate all potential threats to
each HCA. ASME B31.8S, one of the standards referenced in the PHMSA requirements,
describes three general threat types that must be considered. Each general threat type has
three specific threat categories. Additionally, operators must consider interactions among
these different threats, as well as the effects of metal fatigue, if applicable. Table 2.3
provides a listing of these threat types and associated threat categories.
12
Table 2.3
List of Probable Threats to a Transmission Line
Threat Type Threat Category Description
Time Dependent
Internal Corrosion Deterioration of pipeline Due to interaction with pipeline
material and inside environment of the pipeline
External Corrosion Deterioration of pipeline Due to interaction with pipeline
material and outside environment of the pipeline
Stress Corrosion
Cracking
Cracks in the pipe wall due to interaction of tensile
stresses in the pipe material with a corrosive environment.
Stable
Manufacturing Defects incorporated since manufacture of the pipeline
such as laminations, inclusions, hard spots, manufacturing
technique which is now considered have weakness (low
frequency electric resistance welded pipe, lap weld, butt
weld
Construction Defects and weakness during construction bad field weld,
wrinkle bends, stripped threads and broken pipe.
Equipment Equipments other than pipe, such as Pressure control and
relief valve, gasket, O-ring, seals
(continued)
13
Time
Independent
Third
Party/Mechanical
Accidental and intentional excavation damage
Incorrect Operation Incorrect operation by operators
Weather Related Earth movement, seismic events, heavy rain fall, erosion,
cold, lightning etc.
Note. Reprinted from Integrity Management of Gas Transmission Pipelines in High
Consequence Areas by the National Transportation Safety Board, 2015
https://www.ntsb.gov/safety/safety-studies/Documents/SS1501.pdf). National
Transportation Safety Board.
2.2.2 Integrity Assessment Methods Proposed by PHMSA. IM regulations by
PHMSA describe four integrity assessment methods. Depending upon the threats to and
characteristics of the pipeline, it is the operator’s responsibility to adopt the appropriate
method. Primarily, these integrity assessment methods are targeted toward detecting
defects tied to some threats namely corrosion and manufacturing defects but not others
(for example, equipment failure and incorrect operations), which are addressed by
preventive and mitigative measures. The four allowed assessment methods are:
i. In-line Inspection (ILI):
ILI is an internal pipeline inspection technique that uses magnetic flux
leakage, ultrasound, eddy current, or other sensing technology to locate and
characterize indications of defects, such as metal loss or deformation in the
pipeline. The sensor is mounted on a device (known as a “smart PIG”), which is
Table 2.3 (continued)
14
inserted into the pipeline segment between a launching station and a receiving
trap. The smart PIG moves through the pipe scanning the pipe for specific types
of defects. Pipeline segments that can accommodate ILI tools are considered
“piggable”. Different sensors are used for different defects.
ii. Pressure Testing:
A pressure test can be used as a strength or leak test. A common type of
pressure test is a hydrostatic test, which involves taking the pipeline out of service
and pressurizing a section of pipe with water to a much higher percentage of the
pipe material's maximum design strength than the pipe will ever operate at with
natural gas. This verifies the capability of a pipeline to safely operate at the
MAOP and can reveal weaknesses that could lead to defects and leaks in the pipe.
Pressure testing of pipelines is designed to find critical seam defects (as well as
other defects caused by corrosion, stress corrosion cracking and fatigue) by
causing the pipe to fail at these critical defect-locations.
iii. Direct Assessment:
Direct assessment relies on the examination of the pipeline at pre-selected
locations to evaluate a pipeline for external corrosion, internal corrosion, or stress
corrosion cracking threats. Most of the pipeline segment being inspected is
usually not directly examined. Direct assessment uses multiple steps (four steps
for external and internal corrosion, and two steps for stress corrosion cracking).
For example, for external corrosion direct assessment (ECDA), the steps are
(NACE 2008): pre-assessment (the operator determines the feasibility of ECDA,
determines ECDA regions, and selects tools for indirect inspection), indirect
15
inspection (the operator conducts above-ground inspections, such as a close
interval survey (CIS), to identify and classify indicators of corrosion and pipe
coating defects), direct examination (the operator excavates the pipe at selected
locations to measure actual corrosion damage), and post-assessment (the operator
determines reassessment intervals and evaluates the effectiveness of the ECDA
process).
This-method-requires-the identification of regions within the pipeline
segments for excavation and direct examination. Therefore, even though a
pipeline segment may be inspected with direct assessment, only-a-small-sub-
segment-is-directly-examined.
iv. Other Technologies:
These technologies include methods that are industry-recognized,
approved, and published by an industry consensus standards organization or other
methodologies that follow performance requirements with documentation. One
example is guided wave ultrasonic. Operators must inform PHMSA 180 days
before an assessment if they are using these other methodologies-and-
technologies.
2.3 Pipeline features of the ring main
2.3.1 Pipeline information. The entire ring main line consists of four segments.
The segment wise information is as follows (KGDCL, personal communication, August,
2018):
Segment 1: Fouzdarhat CGS to Patenga manifold station.
Length: 19.94 km
16
Diameter: 24 inch.
Wall thickness: 0.344 inch.
Pipe manufacturing process: ERW
Pipe specification: API 5LX 56
Segment 2: Patenga manifold to Shah Mirpur manifold station.
Length: 5.07 km
Diameter: 16 inch.
Wall thickness: 0.250 inch.
Pipe manufacturing process: ERW
Pipe specification: Grade B
Segment 3: Shah Mirpur manifold to BFIDC manifold station.
Length: 19.28 km
Diameter: 20 inch.
Wall thickness: 0.312 inch.
Pipe manufacturing process: ERW
Pipe specification: Grade B
Segment 4: BFIDC manifold to Fouzdarhat CGS.
Length: 12.81 km
Diameter: 24 inch.
Wall thickness: 0.344 inch.
Pipe manufacturing process: ERW
Pipe specification: API 5LX 56
17
2.3.2 Valve type. Segment wise valve numbers are as follows:
Segment 1: Fouzdarhat CGS to Patenga manifold station.
No. of valve stations: 03 (ANSI 300 class)
Segment 2: Patenga manifold to Shah Mirpur manifold station.
No. of valve stations: 04 (ANSI 300 class)
Segment 3: Shah Mirpur manifold to BFIDC manifold station.
No. of valve stations: 04 (ANSI 300 class)
Segment 4: BFIDC manifold to Fouzdarhat CGS.
No. of valve stations: 05 (ANSI 300 class)
List of valve stations are placed in Appendix A.
2.3.3 Withdrawal points/ tee connections. List of withdrawals points (HP DRS)
and off take stations are provided in Appendix A. All the T-connections from each
segment to withdrawal points (HP DRS/CMS) and off take points are fitted with guide
bar which prevent stuck up of ILI tool.
2.3.4 Major crossings. Number of significant crossings is as follows:
Highway: 04
River: 03
Railway: 04
2.3.5 Launching and receiving facilities. There are four manifold stations in the
ring main line. These are:
1. CGS manifold (24///20//)
2. Patenga manifold (24///16//)
3. Shah Mirpur manifold (20///16//)
18
4. BFIDC manifold (24///20//)
It was noted that there is no regular launching and receiving facilities in the manifold
stations. Existing Receivers and launcher barrels are flanged extension of main line pipe.
But there are provisions for setting up standard receiving and launching facilities. So far,
the ring main line is cleaned thrice since its inception. Each time, necessary
fabrication/modification was done in the manifold stations for pig launching and
receiving. Two pig launching and receiving stations at CGS,Fouzdarhat and Shah Mirpur
are shown in Figure 2.1 and Figure 2.2.
Figure 2.1. Fouzdarhat CGS manifold station (KGDCL, personal communication, July,
2018).
19
Figure 2.2. Shah Mirpur manifold station (KGDCL, personal communication, July,
2018).
2.4 Integrity management practices of the ring main
Operation division of KGDCL is responsible for maintaining the transmission
network. There are different sections in the division for looking up specified actions. The
regular jobs are line patrolling, corrosion protection check up, data collection etc
(KGDCL, personal communication, February, 2018).
2.4.1 Routine Line Patrolling. Staffs are employed for patrolling the
transmission line regularly. There are marker posts along the line and one patrol man is
employed for one marker post to the immediate marker post spanning a distance of 4-5
kilometers. A patrol man checks for any illegal installation, excavation or any other
unusual incidents along the pipeline Right of Way (ROW). Any unusual activity is
20
immediately reported to the controlling officer for necessary steps. After completing
patrolling of the concerned distance, the next patrolling is initiated by another patrol man
and this manner continues until the patrolling reaches the beginning position. It takes 1-
1.5 days to complete full patrolling of the transmission line.
2.4.2 Corrosion protection. The outer surface of the ring main line is coated
with polyethylene tape (inner and outer wrap) and primer to protect against corrosion.
Moreover, cathodic protection (CP) system with impressed current and sacrificial anode
at different points of the ring main line have also been deployed. But there is no
protruding type corrosion monitoring probe which can act as an obstruction to the ILI
tool passage. Inspection team periodically collecting reading from the CP post and
analyze for any immediate action.
2.4.3 Data Collection. Staffs are employed at the CGS, different TBS’s for
taking the hourly pressure, flow readings and reporting the controlling authority over
telephone.
2.4.4 Maintenance actions. Necessary maintenance work like greasing of
valves, coloring DRSs etc. is done as per requirement of the authority.
2.5 Significant portions of the ring main
During the planning phase of the ring main, it was designed to surround the City
of Chattogram. Hence, the right of way of the pipe line was chosen to move through
places without human inhabitant or industrial installations. However, in the later times,
without the presence of marker posts along the route of the ring main line, human
inhabitants were built. Industrial installations at some points were also established. This
matter was taken into consideration by the related division of KGDCL and action plans
21
were undertaken to eradicate human inhabitants along the ROW of the pipe line. For
industrial installation situated in the EPZ, box culverts were constructed over the
transmission line. In this chapter, significant installations like industrial concerns, rail
crossing, road crossings, and river crossing etc. along the ROW of the ring main were
marked. It is mentionable that any failure of the ring main at these points might results in
severe loss of life and property as well as indispensable rehabilitation of the ring main.
Figure 2.3 illustrates the position of the ring main on geographic map (KGDCL, personal
communication, October, 2018).
Figure 2.3. Ring main transmission line on geographic map.
22
2.5.1 Segment 1. The significant locations at segment 1 are one rail crossing, one
road crossing and the Chattogram export processing zone (CEPZ). With the extension the
EPZ area, some industrial installations were constructed in positions situated at the outer
side of the ring main. Industries with entry points close to the ring main have constructed
box culverts as directed by relevant division of KGDCL. It is worth mentioning that any
transmission line failure in this area may cause severe consequences. Figure 2.4 is an
extraction from Figure 2.3 showing the portion of segment 1 with significant
installations.
Figure 2.4. Position of ring main line at the CEPZ area.
2.5.2 Segment 2. The significant locations at this segment are 16” 2.5 km
Karnaphuli river crossing and offtake points to two fertilizer factories (CUFL and
KAFCO). Pipe line failure at river crossing would require complete construction of the
1. 24” transmission line 2. CEPZ area
23
concerned pipeline section. Figure 2.5 is an extraction from Figure 2.3 showing the
portion of segment 2 with significant installations.
Figure 2.5. Positions of river crossing, CUFL and KAFCO in segment 2.
2.5.3 Segment 3. This segment contains Chattogram-Cox’s Bazar highway
crossing, some industrial installations and khal crossing (Figure 2.6) and 1.5 km 20”
river crossing (Figure 2.7 extracted from Figure 2.3). Pipe line failure at river crossing
would require complete construction of the concerned pipeline section.
1. 16” transmission line 2. Karnaphuli river crossing 3. CUFL 4. KAFCO
24
Figure 2.7. Position of 20” Karnaphuli river crossing in segment 3.
2.5.4 Segment 4. The significant points at this segment are three rail crossings,
two road crossings, Kalurghat heavy industrial area, approach to Chattogram cantonment
etc. (Figure 2.8, 2.9, 2.10 extracted from Figure 2.3).
1. Karnaphuli river crossing 2. Location industrial
installations 3. 20” transmission line
Figure 2.6. Positions of road crossing, industrial installations and canal crossing in segment 3.
1. Kalar khal crossing 2. Location industrial
installations 3. Ctg-Cox’s Bazar road
crossing 4. 20” transmission line
25
Figure 2.8. Positions of rail crossing, road crossing and Kalurghat heavy I/A in
segment 4.
Figure 2.9. Positions of rail crossing, road crossing and vicinity of Chattogram
cantonment area in segment 4.
1. Cantonment 2. Road crossing 3. Rail crossing 4. 24” transmission line
1. Rail crossing 2. Road crossing 3. 24” transmission line 4. Kalurghat heavy industrial
area
26
Figure 2.10. Positions of rail crossing, road crossing near the Fouzdarhat CGS
in segment 4.
1. Rail crossing 2. 24” transmission line
27
CHAPTER 3: METHODOLOGY
3.1 Technical Feasibility of intelligent pigging for the ring main
The available integrity assessment methods are ILI, pressure testing, direct
assessment and other technologies as described in Chapter 2. Since its inception, the ring
main line has not experienced any integrity assessment procedure. Different factors such
age of the pipe line, previous cleaning type pigging data analysis, determination of
maximum operating pressure and flow etc. have make it inevitable to assess the integrity
of the main transmission backbone of Chattogram.
In process of proposing the appropriate integrity assessment tool for the ring main
line, the methods proposed by PHMSA are examined for their applicability, physical and
operational constraints, degree of uncertainty, time, environmental impacts etc.
3.1.1 Intelligent pigging. The matters that must be considered for adopting an ILI
tool run are the physical and operational compatibility of the concerned pipeline. In
pipeline industry this issue is known as “piggability”. Piggability implies the ability of a
pipeline to enter and exit of a pig without damage to the pipeline or the tool used. In the
context of the project work, a piggable pipe line means a pipe line suitable for the
economic operation of a gas driven, instrumented in line inspection tool. Within the
context of this definition, it is also assumed that the pipe line internal conditions and
operating parameters are such that acceptable inspection results suitable for integrity
assessment can be obtained.
Physical issues. It involves the available facilities/adaptability of the ring main
for intelligent pigging and additional requirement (if any).
28
Facilities available. Physical compatibility issues include the nature of pipe line
details (length, diameter, wall thickness data, specification, and manufacturing process),
valve type, corrosion protection system; withdrawal points/tee connections, major
crossings, pig/ILI tool receiving and launching facilities etc (API, 2013).
Studies imply that the physical features of the ring main are eligible for an
intelligent pig run. The delivery line valves are full bore. There is no tight bends which
restricts easy passage of ILI tool.
Facilities required. Before attempting pig/ILI tool run, standard launching and
receiving facilities should be incorporated in the manifold stations (NACE International,
2010). Access to the launching and receiving/manifold stations should be made
approachable for ILI tool handling vehicle.
Figure 3.1 shows the ring main line with indications of transmission line features
and gas distribution zones of KGDCL (KGDCL, personal communication, September,
2018).
29
Figure 3.1. Ring main transmission line with physical features (KGDCL, personal communication, September, 2018).
30
Operational issues. Operational compatibility issues include the flowing fluid
type, line pressure, temperature, flow rate, tool speed etc (API, 2013).
Fluid type. The ring main line carries natural gas. Composition of the gas from
chromatograph analysis is shown in Table 3.1 (KAFCO, personal communication,
September 18, 2018) :
Table 3.1
Typical composition of flowing natural gas
Sl no. Name of component Vol %
1 Methane (CH4) 93.247
2 Ethane (C2H6) 6.574
3 Propane (C3H8) 0.024
4 Iso-butane (i-C4H10) 0.00
5 n-butane (n-C4H10) 0.00
6 Iso-pentane (i-C5H12) 0.00
7 n-pentane (n-C5H12) 0.00
8 Carbon dioxide (CO2) 0.00
9 Argon (Ar+O2) 0.003
10 Nitrogen (N2) 0.152
11 Sulfur (H2S) -
Note. Reprinted from KAFCO cms gas chromatograph analysis (KAFCO,
personal communication, September 18, 2018)
31
Compositional analysis shows that there is no sulfur content in the gas transmitted
by the ring main. Hence, there is no corrosiveness is the gas. Average specific gravity is
0.596.
Line pressure. The maximum allowable operating pressure of the ring main is
350 psi. But it has been operated below the MAOP. Before the advent LNG, there had
been crises for both flow rate and pressure. As the initial period of LNG is ongoing, still
some irregularities are experienced. But soon, supply management would be stable. Then
pressure requirement for ILI tool run would not be a problem.
Temperature. The flowing temperature of natural gas thru the ring main is
maintained at 60 0F as contracted. The allowable temperature range for pig/ILI tool is 32
0F to 180 0F (Wint, 2011). So, the flowing temperature would not be a problem for ILI
tool run.
Flow rate. It is reported that maximum capacity of the ring main is 350
MMSCFD. The flowing gas in the ring main is distributed (after regulation to 150 psi) by
number of HP DRSs and CMSs to different industrial, power, fertilizer, commercial,
domestic customers. It is found that there is no segment wise flow measurement system
in the ring main. The concerned department of KGDCL provided the amount of
maximum daily flow by HP DRSs and some major industrial offtakes.
During cleaning pigging, usually the offtake points, HP DRSs and CMSs of the
concerned segment are kept closed for preventing influx of sludge/condensate to the 150
psi network and for maintaining stable pig run.
32
3.1.2 Tool speed equation. The following formula provides a close
approximation of the velocity of pig/ILI tool (T.D. Williamson, 2016, p. 31):
Where,
Q = flowrate in MMSCFD
Pb = Absolute base pressure in psi = 14.69 psi
P = Absolute line pressure in psi
Fpv = Supercompressibility Factor
d = inside diameter of pipe in inch
Typical speed for ILI tool is 2-7 mph (Wint, 2011). Maintaining a constant speed
enables good data gathering by the ILI tool. Segment wise pressure and flow should be
maintained is such a way that the ILI tool run within the specified limit.
Calculation. Maintaining a stable flowing pressure and gas flow that allow ILI
tool run within limit is crucial for achieving good data gathering of the concerned pipe
segment. The segment wise gas flow regime allowing the tool to be run within the
practiced speed limit and time requirement for run completion is done by excel spread
sheeting at different flowing pressure. Following assumption are made in the calculation:
1. Specific gravity of flowing gas = 0.6.
2. Flowing temperature being constant at 60 0F.
3. Stable flowing pressure throughout the concerned segment.
4. Stable flow of fluid
5. Base pressure of 14.69 psi.
33
Segment wise gas flow range at different flowing pressures within the practiced
speed limit of ILI tool are summarized in the following tables. Spread sheet calculations
at different pressures for segment 1-4 are placed in Appendix B.
Segment 1: CGS to Patenga manifold. The flow range and travel time
requirement for segment 1 at different flowing pressure conditions are summarized in
Table 3.2.
Table 3.2
Gas flow range at different pressures for segment 1
Sl no. Operating Pressure,P
(psi)
Flow Range
(MMSCFD)
Travel time
(hr)
1 350 19.50 - 68.20
6.24 - 1.78 2 300 16.55 - 58.00
3 275 15.10 - 52.95
4 250 13.70 - 47.95
Segment 2: Patenga to Shah Mirpur manifold. The flow range and travel time
requirement for segment 2 at different flowing pressure conditions are summarized in
Table 3.3.
34
Table 3.3
Gas flow range at different pressures for segment 2
Sl no. Operating Pressure,P
(psi)
Flow Range
(MMSCFD)
Travel time
(hr)
1 350 08.65 – 30.25
1.58 – 0.45
2 300 07.35 – 25.70
3 275 06.70 – 23.46
4 250 06.06 – 21.25
Segment 3: Shah Mirpur to BFIDC manifold. The flow range and travel time
requirement for segment 3 at different flowing pressure conditions are summarized in
Table 3.4.
Table 3.4
Gas flow range at different pressures for segment 3
Sl no. Operating Pressure,P
(psi)
Flow Range
(MMSCFD)
Travel time
(hr)
1 350 13.50 – 47.25
6.01 – 1.72
2 300 11.50 – 40.20
3 275 10.50 – 36.70
4 250 09.50 – 33.20
35
Segment 4: BFIDC to CGS manifold. The flow range and travel time requirement
for segment 4 at different flowing pressure conditions are summarized in Table 3.5.
Table 3.5
Gas flow range at different pressures for segment 4
Sl no. Operating Pressure,P
(psi)
Flow Range
(MMSCFD)
Travel time
(hr)
1 350 19.50 - 68.20
4.00 - 1.14
2 300 16.55 - 58.00
3 275 15.10 - 52.95
4 250 13.70 - 47.95
3.1.3 Alternates of intelligent pigging. According to PHMSA, there are three
alternatives of intelligent pigging, namely pressure testing, direct assessment and other
technologies. For the purpose of this project, different aspects regarding the
appropriateness of the alternatives (excluding the other technologies for lack of its wide
applicability) of intelligent pigging to be applied for integrity assessment of the ring main
are studied.
Pressure testing. The most common mode of pressure testing is hydro testing.
Aspects such as physical, operational, safety and environmental issues related to pressure
testing for the ring main reveal its inappropriateness for adopting as an integrity
assessment tool.
36
Physical issues. Pressure test can be done separately for the four segments of the
ring main line if it is adopted for integrity assessment for the ring main. Segment wise
test water requirement is shown in Table 3.6.
Table 3.6
Segment wise test water requirement
Sl no. Segment name Length
(km)
Pipe line dia
(inch)
Water requirement
(barrel)
1. CGS Fouzdarhat to Patenga
manifold station
19.94 24 46514.43
2. Pateng to Shah Mirpur
manifold station
5.07 16 5228.47
3. Shah Mirpur to BFIDC
manifold station
19.28 20 31069.82
4. BFIDC manifold station to
CGS Fouzdarhat
12.81 24 29882.14
Sample calculation for test water requirement are placed in Appendix C. The
amount of water required for testing each segment of the ring main is equivalent to big
water bodies like ponds (Kiefner, & Maxey, 2013). The segment wise dimension of the
equivalent water bodies are placed in Table 3.7.
37
Table 3.7
Segment wise pond equivalent of water requirement
Sl no. Segment name Water requirement
(barrel)
Pond equivalence for
the required water
1. CGS Fouzdarhat to
Patenga manifold
station
46514.43 100 100 ft pond with
19.4 ft of depth
2. Patenga to Shah Mirpur
manifold station
5228.47 50 50 ft pond with
8.7 ft of depth
3. Shah Mirpur to BFIDC
manifold station
31069.82 100 100 ft pond with
12.9 ft of depth
4. BFIDC manifold station
to CGS Fouzdarhat
29882.14 100 100 ft pond with
12.5 ft of depth
Karnaphuli river may be considered as the source of water if the manifold stations
closer to the river are planned for line filling. But before line filling, the water quality
should be treated for corrosion inhibition, pH neutralization and other necessary
requirements such as TDS, total suspended solids etc. It is to be kept in mind that the
amounts of water required mentioned are excluding makeup requirements and failure
contingency. Therefore, segment wise test water storage amount would be higher.
Facility requirement for storing and treating such huge amount of test water is also a
significant spatial, strategic and financial issue. After test completion, disposal of water
should be done as per environmental regulation of government of Bangladesh.
38
Operational issues. Issues like supply disruption, adoption of test pressure, time
requirement are found incompatible for adopting pressure test as integrity assessment tool
for the ring main.
i. Supply disruption: The concerned segment planned for pressure testing is to be
made out of service for conducting test (Johnson, & Nannay, 2014). All segments
of the ring main line are providing natural gas to different types of consumers. In
case of making out of service for pressure testing would result in energy crisis for
consumers related to the concerned section.
ii. Test pressure: There are three types of pressure tests (API, 2007):
1. Spike test (test pressure to operating pressure ratio is greater than 1.25)
It is used to verify the structural integrity of the pipeline with time
dependant anomalies.
2. Strength test (test pressure to operating pressure ratio is 1.25)
It is used for establishing operating pressure limit.
3. Leak test (test pressure to operating pressure ratio is less than 1.25)
It is used for existence of leak.
At present, the ring main line is operating at 280-300 psi.
Lets assume the test to operating pressure ratio is 1.25.
For operating pressure 280 psi,
Test pressure = 280 1.25 = 350 psi
For operating pressure 300 psi,
Test pressure = 300 1.25 = 375 psi
39
It is clear that, the test pressure is to be maintained at or above the design pressure
of the ring main for the prescribed time period as specified by standards. It itself is a
limiting factor for adopting pressure test for integrity assessment of the ring main line.
As there is no previous integrity assessment for the ring main line, the number
and dimension of flaws within the pipeline are unknown. Adoption of higher test pressure
may result in flaw growth at critical points or failure/rupture results.
On the other side, adopting lower test to operating pressure ratio will reduce the
confidence level and thereby reducing the retest interval. Cost involvement would also be
significant.
iii. Time requirement: Comparing to intelligent pigging, pressure test will require
longer time for each segment of the ring main depending on everything being ok.
First of all, the segment under test will have to be taken out of service. Then it is
to be filled with test water. After filling, the temperature will have to be stable.
Inappropriate test pressure may result in leakages which required the anomalies to
be identified and repaired before next attempt of pressure test or placing the
segment in service.
Safety issues. In appropriate adoption of test pressure might result in failures at
described significant portions of the ring main. Improper/inefficient outage management
would result huge physical and financial losses. Soil erosion would occur in steep
portions on ROW (JACOBS Consultancy, 2013).
Environmental issues. In case of failure during test would cause emission of
pipeline contaminant posing environmental threat. As the condition of the line has not
been assessed so far, identification of failure locations is critical.
40
Direct assessment. Direct assessment is an established method for integrity
assessment of pipelines. But for the ring main line, its adoption as an integrity assessment
tool is limited by its nature.
Physical issues. Only selected portions of the ring main is to be assessed directly
other than the entire pipeline.
Operational issues. The concerned segment to be assessed need not be taken out
of service or subjected to flow curtailment.
Applicability. The nature/procedure of direct assessment technique limits it
applicability to use as integrity assessment tool for the ring main at least for the first time.
This tool only identifies the corrosion threats at the selected locations. Even there are
possibilities that some defects would be left unidentified.
41
3.2 Economic feasibility of intelligent pigging for the ring main
Integrity assessment by an MFL technology based ILI program would play a vital
role to decide whether the rehabilitation measure for entire or portion of the ring main
line is urgent or not. Moreover, the results/findings from the ILI program would act a
baseline survey for future integrity assessment projects for the line.
To make an economic feasibility study of the ILI program for the ring main
transmission line of KGDCL, quotations regarding MFL technology based tool run were
requested to world renowned ILI service providers. Amongst those only one service
provider communicated positively. Several correspondence were done with the company
for providing information of the ring main and receiving the information of
corresponding tool description and financial implications. The correspondence
documents are placed in Appendix D.
3.2.1 Cost of MFL based metal loss run. The service provider intends to visit
the related site of the ring main pipeline route for technical evaluation and finally provide
a detailed proposal for the ILI program. The inspection/ site visit program will be done by
their engineer by a two day tour and it will cost a lump sum amount of € 12,000.
Additional stay will cost of € 1200/ day. The mentioned price include visa arrangement,
flight and travel to/from the company to Chattogram, lodging and messing. They
informed that in case of awarding the project within 6 months after the proposal, 100 %
of cost for site visit will be deducted from the project price. But the quoted price is
excluding taxes and fees applicable in Bangladesh (3p Services, personal communication,
November 17, 2018).
42
A rough amount of 450000-600000 € will be required for MFL tool run. This
amount includes project preparation, the equipment and team and final reporting. In case
of gauge tool run, additional cost will be required (3p Services, personal communication,
November 22, 2018). But head by head estimate cannot be found.
However, the rough price obtained from a renowned ILI service provider can be
taken as a tool for a qualitative indication of economic feasibility of ILI tool run for the
ring main of KGDCL.
Assuming, 1€ = Tk. 94.17
(Euro to taka conversion rate, website information, April 24, 2019.Retrieved from
https://www.exchangerates.org.uk/EUR-BDT-exchangeratehistory.html)
Hence, considering the highest step,
600000 € = 94.17 600000 = Tk.5,65,02,000.00
3.2.2 Cost of standard pig launcher and receiver. Before performing ILI,
standard pig launcher and receiver would have to be installed. The launcher and receiver
diameter would be larger than that of concerned segment of the ring main for ease of
handling ILI tool. Therefore, for 24 inch segment, 36 inch diameter launcher and
receiver costs are considered. Accordingly, 30 inch dia facilities are considered for 20
inch segment and 24 inch dia facilities are considered for 16 inch segment. Rates
proposed by Petrobangla are consulted and yearly 10% increase in rate is assumed.
Segment wise cost involvements for installation of pig launcher and receiver are shown
in Table 3.8.
43
Table 3.8
Pig launcher and receiver cost
Sl Segment name Cost (Tk)
1 CGS Fouzdarhat to Patenga manifold station
(914 mm OD Pig Launcher and receiver)
61,80,493.00
2 Patenga to Shah Mirpur manifold station
(610 mm OD Pig Launcher and receiver)
37,45,753.00
3 Shah Mirpur to BFIDC manifold station
(762 mm OD Pig Launcher and receiver)
56,18,630.00
4 BFIDC manifold station to CGS Fouzdarhat
(914 mm OD Pig Launcher and receiver)
61,80,493.00
Total 2,17,25,370.00
In words: Taka Two Crore Seventeen Lac Twenty Five Thousand Three
Hundred and Seventy only.
Cost break ups for pig launcher and receiver are placed in Appendix E.
3.2.3 Cost of cleaning run. The price of cleaning pigging of July 2018 was Tk.
2,00,00,000.00 (Taka Two Crore only) (KGDCL, personal communication, July, 2018).
Assuming 10% increase, the price for a single cleaning run on year 2019 would be as
follows:
Cost of cleaning pigging (single run) = 20000000 + (20000000 10%)
= Tk. 2,20,00,000.00
44
3.2.4 Per meter based cost calculation. For performing MFL based ILI in the
ring main summing up the cost of ILI run, installation of standard pig launcher and
receiver and a single cleaning pigging run, the total cost would be as follows :
Total cost = 56502000+ 21725370 + 22000000 = Tk. 10,02,27,370.00
Per meter cost =
Tk./meter
Per meter cost = 1755.30 Tk./meter
VAT @ 5.5% = 1755.30 5.5% = Tk. 96.54
IT@ 5.0% =1755.30 5.0% = Tk. 87.77
Hence,
Cost of MFL based ILI program/per meter including VAT and IT
= 1755.30 + 96.54 + 87.77 = Tk. 1939.61
cost of MFL based ILI program/per meter including VAT and IT = Tk. 1939.61
3.2.5 Rehabilitation cost of the ring main (provisional). Cost required for
rehabilitating the ring main line is estimated in a near to real simplified quantitative
approach by consulting the schedule of rates for construction of high pressure distribution
and transmission line published by the Petrobangla on 2015. Yearly flat 10% increase in
the rates is assumed in the calculation. For materials price, rates are collected from the
bid documents of network upgradation project of KGDCL (KGDCL, personal
communication, May, 2019). Segment wise applicable construction head and cost basis
(including supervisory over head @ 2.5%, contractors profit @ 10%, VAT @ 5.5%, IT
@ 5.0%) are used to obtain total segment construction cost summary. Segment wise cost
of rehabilitation (materials cost and construction cost) with applicable heads are placed in
45
Appendix F and Appendix G respectively. It is to be mentioned that the calculations done
are provisional and simplified for the purpose of the ILI project feasibility study.
Summary of segment wise costs of rehabilitation (cost of materials and cost of
construction) required for the ring main transmission line are placed in Table 3.9.
Table 3.9
Segment wise costs of rehabilitation (cost of materials and cost of construction) required
for the ring main transmission line
Sl
no.
Segment name Length
Km
Cost of
materials
Tk
Cost of
construction
Tk
Total (D+E)
Tk
A B C D E F
1. CGS Fouzdarhat to
Patenga manifold station
19.94 48,32,68,587.00 30,47,35,566.00 78,80,04,153.00
2. Patenga to Shah Mirpur
manifold station
5.07 3,46,09,447.00 34,97,63,112.00 38,43,72,559.00
3. Shah Mirpur to BFIDC
manifold station
19.28 35,34,44,926.00 54,96,21,081.00 90,30,66,008.00
4. BFIDC manifold station
to CGS Fouzdarhat
12.81 31,96,02,602.00 20,33,38,864.00
52,29,41,466.00
Total 57.1 119,09,25,562.00 140,74,58,624.00 259,83,84,186.00
In words: Taka Two Hundred Fifty Nine Crore Eighty Three Lac Eighty Four
Thousand One Hundred and Eighty Six Only.
N.B.: 10% increases in the cost of construction are assumed.
46
For CGS Fouzdarhat to Patenga manifold station segment (segment 1),
Cost of rehabilitation required per meter =
= 39,518.76 Tk/meter
Segment wise costs of rehabilitation required per meter are shown in Table 3.10.
Table 3.10
Segment wise costs of rehabilitation required per meter for the ring main line
Sl no. Segment name Length
Km
Dia
inch
Cost
Tk/meter
1. CGS Fouzdarhat to
Patenga manifold station
19.94 24 39,518.76
2. Patenga to Shah Mirpur
manifold station
5.07 16 75,813.13
3. Shah Mirpur to BFIDC
manifold station
19.28 20 46,839.52
4. BFIDC manifold station to
CGS Fouzdarhat
12.81 24 40,822.91
47
Assuming 10% flat price escalation, segment wise per meter based costs of
rehabilitation forecasts for the next five years (up to 2024) are calculated by excel spread
sheet and placed in Table 3.11.
Table 3.11
Segment wise per meter based costs of rehabilitation forecasts up to the year 2024
Sl
no.
Segment name Cost@2020
Tk/meter
Cost@2021
Tk/meter
Cost@2022
Tk/meter
Cost@2023
Tk/meter
Cost@2024
Tk/meter
1. Segment 1 43,470.64 47,817.70 52,599.47 57,859.42 63,645.36
2. Segment 2 83,394.44 91,733.89 1,00,907.28 1,10,998.00 1,22,097.80
3. Segment 3 51,523.47 56,675.82 62,343.40 68,577.74 75,435.52
4. Segment 4 44,905.20 49,395.72 54,335.29 59,768.82 65,745.70
3.2.6 Findings/observations from the cost analysis. The findings are as follows:
Cost of MFL based ILI program = Tk 1939.61/meter (including VAT and IT)
MFL technology based ILI/intelligent pigging program would play a vital role for
taking appropriate decision regarding huge amount of investment required for
rehabilitating the entire or portion of the ring main line.
48
3.3 Risk analysis
A successful ILI operation requires effective management of risks (Pipeline
Operators Forum, 2012). Risks are needed to be clearly identified at an early stage in the
ILI process. Appropriate selection of the supplier and the tool used for the inspection are
considered key steps in the risk mitigation process.
Since the matter of ILI survey is new in our country and tendencies of failure run
is common, risk analysis for the successful ILI survey is a vital point.
Some known causes for failed ILI survey are as follows (Pipeline Operators
Forum, 2012):
1. Speed & pressure related issues
2. Pipeline related damage
3. Bend configurations
4. Wall thickness changes
5. Line debris
6. Pipeline bore restriction or openings
7. Tool component failure
8. Inappropriate technology selection
9. Pipeline valve operations
The following risk criteria are considered for risk analysis (Pipeline Operators Forum,
2012):
1. Available historical data ( pipeline design & construction process, information
from previous cleaning runs, history of known pipeline defects)
2. Pipeline geographical location
49
3. Access to launching/receiving stations and along length of pipeline for marking &
tracking
4. Operating condition
5. Product (natural gas) composition
3.3.1 Risk identification. Tools and techniques for identifying risks and
opportunities include expert judgment, brainstorming, checklists, SWOT analysis, data
analysis tools (Steyn, 2018). For conducting intelligent pigging of KGDCL ring main
transmission line, data gathering, educated guess and site visit reveals several potential
risks. These are as follows:
1. Tool failure (mechanical)
2. Tool failure (electronic)
3. Tool stuck.
Each issue may arise as a consequence of separate events or in combination.
Again, issues mentioned might occur simultaneously. In this project, individual
contribution of the possible events causing a single risk issue and occurrence of a single
issue at a time is assumed.
3.3.2 Risk plot. Risk is the product of probability of an event to occur and its
associated consequence. For the project purpose, a simplified risk plot which eventually
would be presented as a matrix (risk matrix) in section 3.3.4 consisting of two axes with
probability (P) of an event to occur in y-axis and associated consequence (C) in x-axis is
considered (see Figure 3.1). Each axis is assumed to have a maximum limit of 5 with five
equal steps. Each step of the axes mentioned is provided with perceptive, distinguishable
and gradual qualitative attributes so that the criticality of the probability of an event
50
generating the risk issue and its associated consequence can be comprehensible. The
entire plot is arbitrarily segregated into three regions indicating three distinguished risk
levels namely low, medium and high risks. The ranges of associated risk scores of each
risk level are mentioned in Figure 3.2.
Risk score = P C
Prob
abili
ty (
P)
Frequent 5 5 10 15 20 25
Likely 4 4 8 12 16 20
Possible 3 3 6 9 12 15
Unlikely 2 2 4 6 8 10
Rare 1 1 2 3 4 5
1 2 3 4 5
Significant
Minor
Moderate
Major
Catastrophic
Consequence (C)
Figure 3.2. Risk plot with indication of different risk levels and risk scores
where
: Low risk (1-4)
: Medium risk (5-12)
: High risk (15-25)
51
3.3.3 Risk register. A risk register is prepared in the form of a table showing
possible events for a single risk issue (Table 3.12). Each of the events is scored basing on
the description of section 3.3.1 and section 3.3.2 and the corresponding scores are placed
in the risk score column of the table. Background colors of the risk scores are chosen as
per the risk levels indicated in Figure 3.2.
Table 3.12
Risk register for intelligent pigging of the ring main transmission line of KGDCL
No Risk name Events Probability Consequence Risk
score
1. Tool failure
(mechanical)
1.1 Use of new tools and components Frequent
(5)
Major
(4) 20
1.2 Tool preparation & set up
inconsistency
Possible
(3)
Major
(4)
12
1.3 Tool design change within models Possible
(3)
Major
(4)
12
1.4 Operating conditions out of limit Rare
(1)
Major
(4) 4
1.5 Ineffective Cleaning Unlikely
(2)
Major
(4) 8
1.6 Bore restriction Rare
(1)
Major
(4)
4
(continued)
52
No Risk name Events Probability Consequence Risk
score
2. Tool failure
(electronics)
2.1 Electronic failure (problem with
tool “firmware or software”
Likely
(4)
Major
(4) 16
2.2 Battery Possible
(3)
Major
(4) 12
3. Tool stuck
3.1 Ineffective Cleaning Unlikely
(2)
Major
(4) 8
3.2 Bore restriction Rare
(1)
Moderate
(3) 3
3.3 Unintentional Flow bypassing Possible
(3)
Major
(4) 12
3.4 Excessive wear Unlikely
(2)
Major
(4) 8
3.5 Mechanical damage Unlikely
(2)
Major
(4) 8
3.6 Environment (line pressure,
temperature, contents, immersion
time)
Rare
(1)
Major
(4) 4
Table 3.12 (continued)
53
3.3.4 Risk matrix. Total fourteen (14) risk events with six different scores are
listed in Table 3.12. Eleven events having similar scores are congregated in three
different sets and the rest three events have three different scores. As assumed in Figure
3.2, two of these events fall within the high risk area, eight events fall within the medium
risk area and four events fall within the low risk area of the risk matrix.
Risk score = P C
Prob
abili
ty (
P)
Frequent 5 20
Likely 4 16
Possible 3 12
Unlikely 2 8
Rare 1 3 4
1 2 3 4 5
Significant
Minor
Moderate
Major
Catastrophic
Consequence (C)
Figure 3.3. Risk matrix with risks qualitatively assessed and mapped for
intelligent pigging of the ring main line.
1.1
2.1
1.2, 1.3,
2.2, 3.3
1.5, 3.1,
3.4, 3.5
1.4, 1.6,
3.6
3.2
54
Figure 3.3 illustrates the risk matrix formed by the values of risk score
column of Table 3.12. All the events are denoted by their serial no. of Table 3.12 and
placed in six risk level based squares on the right side of Figure 3.3. The relative
positions of each square on the risk matrix are indicated by arrow marks (Zaman,
Priyanta, & Trisilo, 2017).
3.3.5 Findings from risk analysis. Table 3.13 is showing the contribution of risk
levels of the events considered for risk analysis on intelligent pigging of the ring main
line.
Table 3.13
Percentage of risk level as per the risk matrix
Sl no. Risk level No. of events Percentage of
risk level
1 Low risk 4 28.57 %
2 Medium risk 8 57.14 %
3 High risk 2 14.29 %
Total 14 100 %
It is clear from Table 3.13 that percentage of high risk events is reasonably lower.
Low risk events are insignificant. But percentage of events fall within the medium risk
area is higher. Therefore, the intelligent pigging program for the ring main line primarily
can be considered as a medium risk project. However, appropriate mitigation measures
during planning and execution phase will allow a successful intelligent pigging of the
ring main line.
55
CHAPTER 4: RESULTS AND DISCUSSIONS
There are three river crossings, four railway crossings and three highway
crossings along the route of the ring main line. The Chattogram export processing zone
(CEPZ) area on its way of expansion has already crossed the ring main line. One
manifold station (BFIDC) is situated at the Kalurghat heavy industrial area. Some
industries are set up close to Moizzartek area where the ring main line passes. Figure 2.4
– Figure 2.10 describe these significant portions of the ring main line. Any gas line
failure in these portions of the ring main line may result in catastrophic consequence
related to life and property. An immediate and appropriate integrity assessment of the
entire transmission line will certainly allow adoption of necessary preventive measures.
According to PHMSA, there are four integrity assessment techniques available for
assessing the integrity of natural gas transmission line. These are ILI/ intelligent pigging,
pressure testing, direct assessment and other technologies. Pressure testing requires the
line to be taken out of service during the test period. As there is no previous integrity
assessment of the ring main line, adoption of appropriate test pressure is a great
challenge. A higher test pressure may cause failures at weakened/thinner portions (which
are unknown today) of the line. Failures in river crossings would cause the portion of the
ring main to abandon for further service. Failures in significant areas may cause severe
consequences related to life and properties. On the other hand, adoption of lower test
pressure has the possibility to leave certain classes of flaws being remain undetected.
Moreover, management regarding the test water (storage, treatment, dispose) is a difficult
and cumbersome issue. Amount of test water requirement are equivalent to big ponds
56
(see Table 3.7). Direct assessment has limitation inherent to its definition. It deals with
inspection of pre-selected portions of a transmission line. Again, because of absence of
any previous integrity assessment history of the ring main line, this method is not
considered at least for the first time. Lack of sufficient established guide lines and
information, the fourth method listed by PHMSA is not also considered appropriate for
assessing the integrity of the ring main.
As compared to the all available integrity assessment techniques, intelligent
pigging is seems to be the only applicable method, at least for the first time. The physical
and operational issues are eligible for conducting intelligent pigging. But before
intelligent pigging, standard pig launchers and receivers are needed to be installed prior.
The associated installation cost is Tk 2,17,25,370.00 (Two Crore Seventeen Lac Twenty
Five Thousand Three Hundred and Seventy only). The concerned section is not to be
taken out of service during intelligent pigging. Once the integrity is assessed by
ILI/intelligent pigging for the first time, it will serve as a base line for future survey and
would help to established appropriate inspection interval.
Since its commissioning, the ring main line has reached 35 (thirty five) years of
operation. It is a matter of great concern that no integrity assessment has not done on it
within this large span of service life. Intervals of cleaning type pigging operations are
astonishingly irregular. However, sludge analyses of these operations indicate presence of
metal loss phenomenon within the ring main line. Immediate adoption of MFL
technology based metal loss ILI/intelligent pigging as an integrity assessment tool would
57
provide necessary information of the ring main line. The findings from the ILI program
would help to decide whether any rehabilitation is required for the entire or portion of the
line. Degree of urgency of any measurement issue could also be specified.
Taking the base of information provided by a world renowned ILI service
provider, economic implications of an MFL based metal loss ILI program is calculated
per meter basis.
From the calculation done,
Cost of MFL based metal loss tool run = Tk 1939.61/meter
(Including VAT and IT)
This cost includes the cost of one cleaning run, installation of standard launcher
and receiver and MFL tool run. However, once installed, cost of launcher and receiver
would not be included in future intelligent pigging program.
Costs of rehabilitation for entire or portion of the ring main line are significantly
huge. MFL technology based metal loss ILI/intelligent pigging program would play a
vital role for taking appropriate decision regarding huge amount of investment required
for rehabilitating the entire or portion of the ring main line.
Fourteen risk events under three headings (namely tool failure (mechanical), tool
failure (electronics) and tool stuck) are considered for analyzing the risk of intelligent
pigging program of the ring main line (see Table 3.12). Two of these events fall within
the high risk area, eight events fall within the medium risk area and four events fall
within the low risk area of the risk matrix (see Figure 3.3).
58
It is clear from Table 3.13 that the contribution of high risk factors is reasonably
lower (14.29%). Low risk issues are insignificant (28.57%). But contribution of issues
fall within the medium risk area is higher (57.14%). Therefore, the intelligent pigging
program for the ring main line primarily can be considered as a medium risk project.
However, appropriate preventive/mitigation measures during planning and execution
phase will allow a successful intelligent pigging of the ring main line.
59
CHAPTER 5: CONCLUSIONS AND RECOMMENDATIONS
The conclusions and recommendations are placed in the following paragraphs in
the light of the entire project work.
5.1 Conclusions
1. Three methods proposed by PHMSA for integrity assessment of pipelines are
reviewed.
2. The ring main line has not undergone any integrity assessment program so far. In
addition, sludge analyses of previous cleaning type pigging indicate metal loss
issue within the ring main line. Therefore, appropriate integrity assessment of the
ring man line is as urgent matter.
3. Pressure test is found inappropriate in terms of some physical, operational, safety
and environmental issues.
4. Direct assessment is inappropriate at least for the first time as it deals with the
pre-selected portion of a pipe line rather than the entire one.
5. Adoption of intelligent pigging for assessing the integrity of the ring main line is
appropriate as compared to the other integrity assessment techniques in terms of
physical and operational issues.
6. Appropriate selection of intelligent pigging service provider and tool to be used
would be vital in mitigating the associated risk of intelligent pigging program of
the ring main line.
60
5.2 Recommendations
1. ILI/ intelligent pigging should be adopted immediately to assess the integrity of
the ring main line.
2. Rehabilitation of the ring main line requires huge amount of investment. The
findings from the ILI program would help to decide whether any rehabilitation is
required for the entire or portion of the line. Degree of urgency of any
measurement issue could also be specified.
3. Standard launching and receiving facilities should be installed at the manifold
stations.
4. Approach roads to the manifold stations should be made accessible for ILI tool
handling vehicles.
5. Capacity building steps (training, workshop and seminar) for personnel regarding
intelligent pigging should adopted.
61
REFERENCES
API. (2007). Pressure Testing of Steel Pipelines for the Transportation of Gas, Petroleum
Gas, Hazardous Liquids, Highly Volatile Liquids or Carbon Dioxide. Retrieved
from: http://webcache.googleusercontent.com/search?q=cache:http://gost-
snip.su/download/api_rp_11102007_pressure_testing_of_steel_pipelines_for_the
API. (2013). In-line Inspection Systems Qualification. Retrieved from
https://www.academia.edu/
38052090/API_STD_1163_2013_2nd_Edition_In_line_Inspection_Systems_Qualif
ication_Standard
Bakhrabad Gas Systems Limited. (1994). On-stream pigging completion report and
recommendations. Cumilla, Bangladesh: Bakhrabad Gas Systems Limited.
Cordell, J., and Vanzant, H. (2003). THE PIPELINE PIGGING HANDBOOK. Houston, TX:
Clarion Technical Publishers and Scientific Surveys Ltd.
JACOBS Consultancy. (2013). Technical, Operational, Practical, and Safety
Considerations of Hydrostatic Pressure Testing Existing Pipelines. Washington,
DC: The INGAA Foundation. Retrieved from
https://www.ingaa.org/File.aspx?id=21159&v=95573337
Johnson, J., & Nannay, S. (2014, September). The Role, Limitations, and Value of
Hydrotesting vs In-Line Inspection in Pipeline Integrity Management. Paper
presented at the 2014 10th International Pipeline Conference, Calgary, Alberta,
Canada. doi: 10.1115/IPC2014-33450
62
Kiefner, J. F., & Maxey, W. A. (2013). THE BENEFITS AND LIMITATIONS OF
HYDROSTATIC TESTING. Retrieved from Parliamentary Commission of Quebec
website: http://www.assnat.qc.ca/en/recherche/recherche-avancee.html
Libra Enterprise. (2018). Onstream cleaning pigging of 24-inch, 20-inch & 16-inch 57-km
Chittagong ring main high pressure natural gas pipeline. Chattogram, Bangladesh:
Author.
NACE International. (2010). In-Line Inspection of Pipelines. Retrieved from
https://usdocument.net/ everything-is-okay.html? utm_source=nace-sp0102-2010-pdf
National Transportation Safety Board. (2015). Integrity Management of Gas Transmission
Pipelines in High Consequence Areas (NTSB/SS-15/01 PB2015-102735).
Retrieved from https://www.ntsb.gov/safety/safety-studies/Documents/SS1501.pdf
Pipeline Operators Forum. (2012). Guidance on achieving ILI First Run Success. Retrieved
from http://www.pipelineoperators.org
Pipeline Operators Forum. (2016). Specifications and requirements for in-line inspection of
pipelines. Retrieved from http://www.pipelineoperators.org
Steyn, J. (2018, October 1). Introduction to Project Risk Management: Part 2-Identify,
analyse, action and monitor project risks. Retrieved from:
https://www.researchgate.net/publication/327981232_Introduction_to_Project_Risk
_Management_Part_2-Identify_analyse_action_and_monitor_project_risks
T.D. Williamson. (2016). T.D. Williamson 2016 Guide to Pigging. Retrieved from:
https://info.tdwilliamson.com/guidetopigging
63
Wint, D. (2011). Difficult to Pig Pipelines [PowerPoint slides]. Retrieved from
https://www.scribd.com/document/138422032/PM9-Difficult-to-Pig-Pipelines
Zaman, M. B., Priyanta, D., & Trisilo, F. (2017). Risk assessment in financial feasibility of
tanker project using monte carlo simulation. International Journal of Marine
Engineering Innovation and Research, 1(4), 303-316.
64
Appendix A
List of Valve station along the ring main
Table A.1
List of valve stations along the route of the ring main
Sl no. Name of valve station Address
01 DLVE-2 Dhaka-Chattogram rail crossing, solimpur, Chattogram.
02 DLVE-3 Nazirhat rail crossing (near Nasirabad HP-DRS),
Cantonment, Chattogram.
03 DLVE-4 Nazirhat rail crossing, Mir para, Oxygen, Chattogram
04 DLVE-5 Dohazari rail crossing, Tek para, C&B,
Kalurghat, Chattogroam
05 DLVE-6 Dohazari rail crossing, Tek para, C&B,
Kalurghat, Chattogroam
06 DLVE-7 BFIDC manifold station, Kalurghat, Chattogram.
07 DLVE-8 TK Chemical complex, Char Khizirpur, Chattogram
08 DLVS-2 Bandar rail crossing, Salimpur, Chattogram.
(continued)
65
Table A.1 (continued)
Sl no. Name of valve station Address
09 DLVS-3 Choudhury para, North Halishahar, Chattogram.
10 DLVS-4 Narikeltala, South Halishahar, Chattogram.
11 DLVS-5 Patenga manifold station, Chattogram.
12 DLVS-6 KAFCO, Anowara, Chattogram.
13 DLVS-7 Moizzartek, Cox’s Bazar road, Karnaphuli, Chattogram.
14 DLVS-8 Baruapara, Shikobaha, Chattogram.
Note. Information collected from KGDCL Transmission department (KGDCL, personal
communication, November, 2018).
66
Gas withdrawal points
Table A.2
List of HP-DRS along the ring main transmission line
Sl no Name of HP/DRS Location Capacity
(MMSCFD)
Inlet
Pressure
(psig)
Outlet
Pressure
(psig)
1. City Gate HP/DRS Fouzdarhat, Chattogram. 20 350 150
2. CEPZ HP/DRS CEPZ , Chattogram. 20 350 150
3. Kalurghat HP/DRS Chandgao, Chattogram. 25 350 150
4. Nasirabad
HP/DRS
Cantonment, Baizid
bostami, Chattogram.
35 350 150
5. Halishahar
HP/DRS
Halishahar, Chattogram. 30 350 150
6. Char Khidirpur
HP/DRS
Boalkhali, Chattogram.. 07 350 58
9. Patenga HP/DRS 15 no. Ghat, Adjacent to
Air port, Chattogram..
08 350 58
10. Char Pathar
Ghhata (Old)
HP/DRS
Adjacent to S.Alam
Mills, Moizzar Tek,
Chattogram..
07 350 60
(continued)
67
Table A.2 (continued)
Sl no Name of HP/DRS Location Capacity
(MMSCFD)
Inlet
Pressure
(psig)
Outlet
Pressure
(psig)
11. Char Pathar
Ghhata (New)
HP/DRS
Adjacent to S.Alam
Mills, Cox’s Bazar Road,
Chattogram..
30 350 150
14. CUFL HP/DRS Anowara, Chattogram. 02 350 60
15. Kalar Pool
HP/DRS
Shikalbaha, patiya,
Chattogram.
30 350 150
16. United Power
HP/DRS
Adjacent CEPZ Mazjid,
Chattogram.
20 350 150
Note. Information collected from KGDCL Transmission department (KGDCL, personal
communication, November, 2018).
68
Appendix B
Spread sheet calculation for gas flow range and travel time within speed limit
Segment 1: CGS to Patenga manifold
Table B.1
Operating pressure 350 psi, gas flow rate: 19-70 MMSCFD
Flow rate,Q
(MMSCFD)
Base
pressure,
Pb
(psi)
Operating
Pressure,
P
(psi)
Super
compressibility
factor @ 60 0F,
Fpv
Internal
diameter, d
(inch)
Tool
Speed,
VILI
(mph)
Travel
time
(hr)
19 14.69 350 1.028525 23.656 1.95 6.39
19.5 14.69 350 1.028525 23.656 2.00 6.23
25 14.69 350 1.028525 23.656 2.56 4.86
30 14.69 350 1.028525 23.656 3.08 4.05
35 14.69 350 1.028525 23.656 3.59 3.47
40 14.69 350 1.028525 23.656 4.10 3.04
45 14.69 350 1.028525 23.656 4.62 2.70
50 14.69 350 1.028525 23.656 5.13 2.43
55 14.69 350 1.028525 23.656 5.64 2.21
60 14.69 350 1.028525 23.656 6.16 2.02
65 14.69 350 1.028525 23.656 6.67 1.87
68.2 14.69 350 1.028525 23.656 7.00 1.78
70 14.69 350 1.028525 23.656 7.18 1.74
69
Table B.2
Operating pressure 300 psi, gas flow rate: 15-60 MMSCFD
Flow rate,Q
(MMSCFD)
Base
pressure,
Pb
(psi)
Operating
Pressure,
P
(psi)
Super
compressibility
factor @ 60 0F,
Fpv
Internal
diameter, d
(inch)
Tool Speed,
VILI
(mph)
Travel
time
(hr)
15 14.69 300 1.02435 23.656 1.81 6.89
16.55 14.69 300 1.02435 23.656 2.00 6.24
20 14.69 300 1.02435 23.656 2.41 5.16
25 14.69 300 1.02435 23.656 3.02 4.13
30 14.69 300 1.02435 23.656 3.62 3.44
35 14.69 300 1.02435 23.656 4.22 2.95
40 14.69 300 1.02435 23.656 4.83 2.58
45 14.69 300 1.02435 23.656 5.43 2.30
50 14.69 300 1.02435 23.656 6.03 2.07
55 14.69 300 1.02435 23.656 6.64 1.88
58 14.69 300 1.02435 23.656 7.00 1.78
60 14.69 300 1.02435 23.656 7.24 1.72
70
Table B.3
Operating pressure 275 psi, gas flow rate: 14-53 MMSCFD
Flow rate,Q
(MMSCFD)
Base
pressure,
Pb
(psi)
Operating
Pressure,
P
(psi)
Super
compressibility
factor @ 60 0F,
Fpv
Internal
diameter, d
(inch)
Tool
Speed,
VILI
(mph)
Travel
time
(hr)
14 14.69 275 1.0222625 23.656 1.85 6.73
15 14.69 275 1.0222625 23.656 1.98 6.29
15.1 14.69 275 1.0222625 23.656 2.00 6.24
17 14.69 275 1.0222625 23.656 2.25 5.55
20 14.69 275 1.0222625 23.656 2.64 4.71
25 14.69 275 1.0222625 23.656 3.30 3.77
30 14.69 275 1.0222625 23.656 3.97 3.14
35 14.69 275 1.0222625 23.656 4.63 2.69
40 14.69 275 1.0222625 23.656 5.29 2.36
45 14.69 275 1.0222625 23.656 5.95 2.10
50 14.69 275 1.0222625 23.656 6.61 1.89
52.95 14.69 275 1.0222625 23.656 7.00 1.78
53 14.69 275 1.0222625 23.656 7.01 1.78
71
Table B.4
Operating pressure 250 psi, gas flow rate: 13-48 MMSCFD
Flow rate,Q
(MMSCFD)
Base
pressure,
Pb
(psi)
Operating
Pressure,
P
(psi)
Super
compressibility
factor @ 60 0F,
Fpv
Internal
diameter, d
(inch)
Tool
Speed,
VILI
(mph)
Travel
time
(hr)
13 14.69 250 1.020175 23.656 1.90 6.57
13.7 14.69 250 1.020175 23.656 2.00 6.23
15 14.69 250 1.020175 23.656 2.19 5.69
17 14.69 250 1.020175 23.656 2.48 5.02
20 14.69 250 1.020175 23.656 2.92 4.27
25 14.69 250 1.020175 23.656 3.65 3.41
30 14.69 250 1.020175 23.656 4.38 2.85
35 14.69 250 1.020175 23.656 5.11 2.44
40 14.69 250 1.020175 23.656 5.84 2.13
45 14.69 250 1.020175 23.656 6.57 1.90
47.95 14.69 250 1.020175 23.656 7.00 1.78
48 14.69 250 1.020175 23.656 7.01 1.78
72
Segment 2: Patenga to Shah Mirpur manifold
Table B.5
Operating pressure 350 psi, gas flow rate: 8-31 MMSCFD
Flow rate,Q
(MMSCFD)
Base
pressure,
Pb
(psi)
Operating
Pressure,
P
(psi)
Super
compressibility
factor @ 60 0F,
Fpv
Internal
diameter, d
(inch)
Tool
Speed,
VILI
(mph)
Travel
time
(hr)
8 14.69 350 1.028525 15.750 1.85 1.71
8.65 14.69 350 1.028525 15.750 2.00 1.58
10 14.69 350 1.028525 15.750 2.31 1.37
15 14.69 350 1.028525 15.750 3.47 0.91
20 14.69 350 1.028525 15.750 4.63 0.68
25 14.69 350 1.028525 15.750 5.79 0.55
30 14.69 350 1.028525 15.750 6.94 0.46
30.25 14.69 350 1.028525 15.750 7.00 0.45
31 14.69 350 1.028525 15.750 7.17 0.44
73
Table B.6
Operating pressure 300 psi, gas flow rate: 7-26 MMSCFD
Flow rate,Q
(MMSCFD)
Base
pressure,
Pb
(psi)
Operating
Pressure,
P
(psi)
Super
compressibility
factor @ 60 0F,
Fpv
Internal
diameter,
d
(inch)
Tool
Speed,
VILI
(mph)
Travel
time
(hr)
7 14.69 300 1.02435 15.750 1.91 1.66
7.35 14.69 300 1.02435 15.750 2.00 1.58
10 14.69 300 1.02435 15.750 2.72 1.16
15 14.69 300 1.02435 15.750 4.08 0.78
20 14.69 300 1.02435 15.750 5.44 0.58
25 14.69 300 1.02435 15.750 6.81 0.47
25.7 14.69 300 1.02435 15.750 7.00 0.45
26 14.69 300 1.02435 15.750 7.08 0.45
74
Table B.7
Operating pressure 275 psi, gas flow rate: 6-24 MMSCFD
Flow rate,Q
(MMSCFD)
Base
pressure,
Pb
(psi)
Operating
Pressure, P
(psi)
Super
compressibility
factor @ 60 0F,
Fpv
Internal
diameter,
d
(inch)
Tool
Speed,
VILI
(mph)
Travel
time
(hr)
6 14.69 275 1.0222625 15.750 1.79 1.77
6.7 14.69 275 1.0222625 15.750 2.00 1.59
10 14.69 275 1.0222625 15.750 2.98 1.06
15 14.69 275 1.0222625 15.750 4.47 0.71
20 14.69 275 1.0222625 15.750 5.96 0.53
22 14.69 275 1.0222625 15.750 6.56 0.48
23 14.69 275 1.0222625 15.750 6.86 0.46
23.46 14.69 275 1.0222625 15.750 7.00 0.45
24 14.69 275 1.0222625 15.750 7.16 0.44
75
Table B.8
Operating pressure 250 psi, gas flow rate: 6-22 MMSCFD
Flow rate,Q
(MMSCFD)
Base
pressure,
Pb
(psi)
Operating
Pressure, P
(psi)
Super
compressibility
factor @ 60 0F,
Fpv
Internal
diameter, d
(inch)
Tool
Speed,
VILI
(mph)
Travel
time
(hr)
6 14.69 250 1.020175 15.750 1.98 1.60
6.06 14.69 250 1.020175 15.750 2.00 1.59
10 14.69 250 1.020175 15.750 3.29 0.96
15 14.69 250 1.020175 15.750 4.94 0.64
20 14.69 250 1.020175 15.750 6.59 0.48
21.25 14.69 250 1.020175 15.750 7.00 0.45
22 14.69 250 1.020175 15.750 7.25 0.44
76
Segment 3: Shah Mirpur to BFIDC manifold
Table B.9
Operating pressure 350 psi, gas flow rate: 10-48 MMSCFD
Flow rate,Q
(MMSCFD)
Base
pressure,
Pb
(psi)
Operating
Pressure,
P
(psi)
Super
compressibility
factor @ 60 0F,
Fpv
Internal
diameter, d
(inch)
Tool
Speed,
VILI
(mph)
Travel
time
(hr)
10 14.69 350 1.028525 19.688 1.48 8.14
13.5 14.69 350 1.028525 19.688 2.00 6.03
15 14.69 350 1.028525 19.688 2.22 5.42
20 14.69 350 1.028525 19.688 2.96 4.07
25 14.69 350 1.028525 19.688 3.70 3.25
30 14.69 350 1.028525 19.688 4.44 2.71
35 14.69 350 1.028525 19.688 5.18 2.32
40 14.69 350 1.028525 19.688 5.92 2.03
45 14.69 350 1.028525 19.688 6.67 1.81
47.25 14.69 350 1.028525 19.688 7.00 1.72
48 14.69 350 1.028525 19.688 7.11 1.69
77
Table B.10
Operating pressure 300 psi, gas flow rate: 10-41 MMSCFD
Flow rate,Q
(MMSCFD)
Base
pressure,
Pb
(psi)
Operating
Pressure,
P
(psi)
Super
compressibility
factor @ 60 0F,
Fpv
Internal
diameter, d
(inch)
Tool
Speed,
VILI
(mph)
Travel
time
(hr)
10 14.69 300 1.02435 19.688 1.74 6.92
11.5 14.69 300 1.02435 19.688 2.00 6.01
15 14.69 300 1.02435 19.688 2.61 4.61
20 14.69 300 1.02435 19.688 3.48 3.46
25 14.69 300 1.02435 19.688 4.36 2.77
30 14.69 300 1.02435 19.688 5.23 2.31
35 14.69 300 1.02435 19.688 6.10 1.98
40 14.69 300 1.02435 19.688 6.97 1.73
40.2 14.69 300 1.02435 19.688 7.00 1.72
41 14.69 300 1.02435 19.688 7.14 1.69
78
Table B.11
Operating pressure 275 psi, gas flow rate: 10-37 MMSCFD
Flow rate,Q
(MMSCFD)
Base
pressure,
Pb
(psi)
Operating
Pressure,
P
(psi)
Super
compressibility
factor @ 60 0F,
Fpv
Internal
diameter, d
(inch)
Tool
Speed,
VILI
(mph)
Travel
time
(hr)
10 14.69 275 1.0222625 19.688 1.91 6.31
10.5 14.69 275 1.0222625 19.688 2.00 6.01
15 14.69 275 1.0222625 19.688 2.86 4.21
20 14.69 275 1.0222625 19.688 3.82 3.16
25 14.69 275 1.0222625 19.688 4.77 2.53
30 14.69 275 1.0222625 19.688 5.72 2.10
35 14.69 275 1.0222625 19.688 6.68 1.80
36.7 14.69 275 1.0222625 19.688 7.00 1.72
37 14.69 275 1.0222625 19.688 7.06 1.71
79
Table B.12
Operating pressure 250 psi, gas flow rate: 9-34 MMSCFD
Flow rate,Q
(MMSCFD)
Base
pressure,
Pb
(psi)
Operating
Pressure,
P
(psi)
Super
compressibility
factor @ 60 0F,
Fpv
Internal
diameter, d
(inch)
Tool
Speed,
VILI
(mph)
Travel
time
(hr)
9 14.69 250 1.020175 19.688 1.90 6.35
9.5 14.69 250 1.020175 19.688 2.00 6.02
10 14.69 250 1.020175 19.688 2.11 5.72
15 14.69 250 1.020175 19.688 3.16 3.81
20 14.69 250 1.020175 19.688 4.22 2.86
25 14.69 250 1.020175 19.688 5.27 2.29
30 14.69 250 1.020175 19.688 6.32 1.91
33.2 14.69 250 1.020175 19.688 7.00 1.72
34 14.69 250 1.020175 19.688 7.17 1.68
80
Segment 4: BFIDC to CGS manifold
Table B.13
Operating pressure 350 psi, gas flow rate: 19-70 MMSCFD
Flow rate,Q
(MMSCFD)
Base
pressure,
Pb
(psi)
Operating
Pressure,
P
(psi)
Super
compressibility
factor @ 60 0F,
Fpv
Internal
diameter, d
(inch)
Tool
Speed,
VILI
(mph)
Travel
time
(hr)
19 14.69 350 1.028525 23.656 1.95 4.11
19.5 14.69 350 1.028525 23.656 2.00 4.00
25 14.69 350 1.028525 23.656 2.56 3.12
30 14.69 350 1.028525 23.656 3.08 2.60
35 14.69 350 1.028525 23.656 3.59 2.23
40 14.69 350 1.028525 23.656 4.10 1.95
45 14.69 350 1.028525 23.656 4.62 1.73
50 14.69 350 1.028525 23.656 5.13 1.56
55 14.69 350 1.028525 23.656 5.64 1.42
60 14.69 350 1.028525 23.656 6.16 1.30
65 14.69 350 1.028525 23.656 6.67 1.20
68.2 14.69 350 1.028525 23.656 7.00 1.14
70 14.69 350 1.028525 23.656 7.18 1.11
81
Table B.14
Operating pressure 300 psi, gas flow rate: 15-60 MMSCFD
Flow rate,Q
(MMSCFD)
Base
pressure,
Pb
(psi)
Operating
Pressure,
P
(psi)
Super
compressibility
factor @ 60 0F,
Fpv
Internal
diameter, d
(inch)
Tool
Speed,
VILI
(mph)
Travel
time
(hr)
15 14.69 300 1.02435 23.656 1.81 4.42
16.55 14.69 300 1.02435 23.656 2.00 4.01
20 14.69 300 1.02435 23.656 2.41 3.32
25 14.69 300 1.02435 23.656 3.02 2.65
30 14.69 300 1.02435 23.656 3.62 2.21
35 14.69 300 1.02435 23.656 4.22 1.90
40 14.69 300 1.02435 23.656 4.83 1.66
45 14.69 300 1.02435 23.656 5.43 1.47
50 14.69 300 1.02435 23.656 6.03 1.33
55 14.69 300 1.02435 23.656 6.64 1.21
58 14.69 300 1.02435 23.656 7.00 1.14
60 14.69 300 1.02435 23.656 7.24 1.11
82
Table B.15
Operating pressure 275 psi, gas flow rate: 14-53 MMSCFD
Flow rate,Q
(MMSCFD)
Base
pressure,
Pb
(psi)
Operating
Pressure,
P
(psi)
Super
compressibility
factor @ 60 0F,
Fpv
Internal
diameter, d
(inch)
Tool
Speed,
VILI
(mph)
Travel
time
(hr)
14 14.69 275 1.0222625 23.656 1.85 4.33
15 14.69 275 1.0222625 23.656 1.98 4.04
15.1 14.69 275 1.0222625 23.656 2.00 4.01
17 14.69 275 1.0222625 23.656 2.25 3.56
20 14.69 275 1.0222625 23.656 2.64 3.03
25 14.69 275 1.0222625 23.656 3.30 2.42
30 14.69 275 1.0222625 23.656 3.97 2.02
35 14.69 275 1.0222625 23.656 4.63 1.73
40 14.69 275 1.0222625 23.656 5.29 1.51
45 14.69 275 1.0222625 23.656 5.95 1.35
50 14.69 275 1.0222625 23.656 6.61 1.21
52.95 14.69 275 1.0222625 23.656 7.00 1.14
53 14.69 275 1.0222625 23.656 7.01 1.14
83
Table B.16
Operating pressure 250 psi, gas flow rate: 13-48 MMSCFD
Flow rate,Q
(MMSCFD)
Base
pressure,
Pb
(psi)
Operating
Pressure,
P
(psi)
Super
compressibility
factor @ 60 0F,
Fpv
Internal
diameter, d
(inch)
Tool
Speed,
VILI
(mph)
Travel
time
(hr)
13 14.69 250 1.020175 23.656 1.90 4.22
13.7 14.69 250 1.020175 23.656 2.00 4.00
15 14.69 250 1.020175 23.656 2.19 3.66
17 14.69 250 1.020175 23.656 2.48 3.23
20 14.69 250 1.020175 23.656 2.92 2.74
25 14.69 250 1.020175 23.656 3.65 2.19
30 14.69 250 1.020175 23.656 4.38 1.83
35 14.69 250 1.020175 23.656 5.11 1.57
40 14.69 250 1.020175 23.656 5.84 1.37
45 14.69 250 1.020175 23.656 6.57 1.22
47.95 14.69 250 1.020175 23.656 7.00 1.14
48 14.69 250 1.020175 23.656 7.01 1.14
84
Appendix C
Test water quantity calculation
Segment internal volume = π (D-(d 2))/2)2 L ------------------------------------------[C.1]
Where,
π = 3.14
D = Outer diameter of concerned segment
d = wall thickness of the concerned segment
L = Length of the concerned segment
Lets consider segment 1.
Length, L = 19.94 km =
= 65419.95 ft
Outer diameter = 24 inch
Wall thickness, d = 0.344 inch
Inner diameter, ((D-(d 2)) = 24 – (0.344 2) = 23.312 inch
(D-(d 2))/2 =
= 11.656 inch
(D-(d 2))/2)2 = 11.662 = 135.86234 inch2 = 0.94 ft2
Placing the value of length, L and (D-(d 2))/2)2 in equation C.1, we get,
Test water for segment 1 = 3.14 0.94 65419.95 = 193810.11 ft3
1 ft3 = 0.24 bbl
193810.11 ft3 = 0.24 193810.11 = 46514.43 bbl
Similar procedure is followed for other segments.
85
Appendix D
Quotation correspondence with 3P Services
Figure D.1. Quotation related document (3P services, personal communication, November 17, 2018).
89
Appendix E
Cost of Pig launcher and receiver
Segment wise cost of pig launcher & receiver are placed in Table E.1.
Table E.1
Cost of pig launcher and receiver.
Sl Segment name Cost@2015 Cost@2019
1 1st segment (914 mm OD Pig Launcher & receiver)
4221360 6180493
2 2nd segment (610 mm OD Pig Launcher & receiver)
2558400 3745753
3 3rd segment (762 mm OD Pig Launcher & receiver)
3837600 5618630
4 4th segment (914 mm OD Pig Launcher & receiver)
4221360 6180493
Total 14838720 21725370
IN WORDS: TWO CRORE SEVENTEEN LAC TWENTY FIVE THOUSAND THREE HUNDRED & SEVENTY ONLY.
* Rates are inclusives of payable VAT @5.5%, [email protected]%, Sup.OH @2.5%
and contractors profit @10%
** Yearly 10 % price increase assumed.
90
Appendix F
Segment wise provisional materials requirement for construction of the ring main line
Table F.1
Provisional list of materials required for the construction of 19.94 km 24" 350 psi transmission
line (1st segment)
Sl
no.
Item Unit Unit
Cost
(in Lac
Tk)
Quantity Cost
(Tk)
CD-
VAT
Cost
including
CD-VAT
(Tk)
1 24" API 5L Gr. B Line pipe
(WT 9.53 mm)
km 150.61 19.94 300316340 45% 435458693
2 Coating materials LS 4566260 80% 8219268
3 Valves No. 13.99 3 4197000 35% 5665950
4 Butt weld fittings,
Tee's,Elbows, Flange, Gasket,
Cradle, Gauges, Insulating
joints and other necessary
fittings (5% of Line pipe cost)
LS
15015817 60% 24025307.2
5 CP materials (1.5 % of
Linepipe cost)
LS
4504745 30% 5856168.63
6 TEG No. 28.88 1 2888000 40% 4043200
TOTAL 331488162
483268587
In word : Forty Eight Crore Thirty Two Lac Sixty Eight Thousand Five Hundred & Eighty
Seven only.
91
Table F.2
Provisional list of materials required for the construction of 2.57 km 16" 350 psi transmission
line (2nd segment),excluding river crossing portion
Sl
no.
Item Unit Unit
Cost
(in Lac
Tk)
Quantity Cost
(Tk)
CD-
VAT
Cost
including
CD-VAT
(Tk)
1 16" API 5L X 52 Line pipe
(WT 7.9 mm) Km 68.32 2.57
17558240 45% 25459448
2 Coating materials LS 588530 80% 1059354
3 Valves No. 8.52 2 1704000 35% 2300400
4 Butt weld fittings, Tee's,
Elbows, Flange, Gasket,
Cradle, Gauges, Insulating
joints and other necessary
fittings (5% of Line pipe cost)
LS
877912 60% 1404659.2
5 CP materials (1.5 % of
Linepipe cost)
LS
263374 30% 342385.68
6 TEG No. 28.88 1 2888000 40% 4043200
TOTAL 23880056
34609447
In word: Three Crore Forty Six Lac Nine Thousand Four Hundred & Forty Seven only.
92
Table F.3
Provisional list of materials required for the construction of 17.78 km 20" 350 psi
transmission line (3rd segment) excluding river crossing portions
Sl
no.
Item Unit Unit
Cost
(in Lac
Tk)
Quantity Cost
(Tk)
CD-
VAT
Cost
including
CD-VAT
(Tk)
1 20" API 5L X 52 Line pipe
(WT 9.53 mm)3LPE coated
Km 125.11 17.78 222445580 45% 322546091
2 Valves No. 11.66 3 3498000 35% 4722300
3 Butt weld fittings, Tee's,
Elbows, Flange, Gasket,
Cradle, Gauges, Insulating
joints and other necessary
fittings (5% of Line pipe cost)
LS
11122279 60% 17795646.4
4 CP materials (1.5 % of
Linepipe cost)
LS
3336684 30% 4337688.81
5 TEG No. 28.88 1 2888000 40% 4043200
TOTAL 243290543
353444926
In word: Thirty Five Crore Thirty Four Lac Forty Four Thousand Nine Hundred & Twenty
Six only.
93
Table F.4
Provisional list of materials required for the construction of 12.81 km 24" 350 psi
transmission line (4th segment)
Sl
no.
Item Unit Unit
Cost
(in Lac
Tk)
Quantity Cost
(Tk)
CD-
VAT
Cost
including
CD-VAT
(Tk)
1 24" API 5L Gr. B Line pipe
(WT 9.53 mm) km 150.61 12.81
192931410 45% 279750544.5
2 Coating materials LS 2933490 80% 5280282
3 Valves No. 13.99 6 8394000 35% 11331900
4 Butt weld fittings, Tee's,
Elbows, Flange, Gasket,
Cradle, Gauges, Insulating
joints and other necessary
fittings (5% of Line pipe cost)
LS
9646570.5 60% 15434512.8
5 CP materials (1.5 % of
Linepipe cost)
LS
2893971 30% 3762162.495
6 TEG No. 28.88 1 2888000 40% 4043200
TOTAL 219687442
319602602
In word: Thirty One Crore Ninety Six Lac Two Thousand Six Hundred & Two only.
94
Appendix G
Cost of construction (provisional) of the ring main as per schedule of Petrobangla
Table G.1
Provisional schedule of rates & quantities for construction of 24" 19.94 km 350 psi transmission
line from CGS Fouzdarhat to Patenga Manifold station (1st segment)
Sl no. Description Cost basis Qty. Unit Amount (tk) Remark
1 Preparation of ROW 179580.00
Tk./km
19.94 km 3580825.20
2 Transportations, hauling of pipes
from Company's depot / pipe yard to
construction site.
58.49
Tk./ton-km
3157.80
40
ton
km
7387988.88 Assuming 40
km distance.
3 Transportation and storage of
induction Bends, valves, flanges,
tapes, primer and other pipeline
materials & fittings from company's
depot to work site.
107.26
Tk./ton-km
200
40
ton
km
858080.00 Assuming 40
km distance.
4 Stringing of line pipe along with
Right-of-way (ROW)
290.19
Tk./mtr
19940 mtr 5786388.60
5 Field bends to 8D radius using
Hydraulic Pipe bending machine
3355.17
Tk./mtr
6000 mtr 20131020.00
(continued)
95
Sl no. Description Cost basis Qty. Unit Amount (tk) Remark
6 Welding: cleaning, cutting, beveling
of pipes and fittings including
chamfering of over thickness and re-
beveling (if required) of pipes and
fittings.Line up by internal clamp
and welding and weld repairs as per
API.1104
16096.60
Tk./no
1680 nos. 27042288.00
7 External cleaning of pipe prior to
coating & wrapping operation by
sand blasting.
587.33
Tk./mtr
19940 mtr 11711360.20
8 Applying primer and polyethylene
tape (inner and other tape) by semi
mechanical machine and holyday
checking to the pipe and bends.
1293.55
Tk./mtr
19940 mtr 25793387.00
9 Cleaning of weld area of mainline
pipe by sand blasting and joint
coating by heat shrink sleeve
1230.00
Tk./no
1680 nos. 2066400.00
10 Trenching 610.08
Tk./mtr
19940 mtr 12164995.20
11 Lowering 491.02
Tk./mtr
19940 mtr 9790938.80
Table G.1 (continued)
(continued)
96
Sl no. Description Cost basis Qty. Unit Amount (tk) Remark
12 Back filling with proper compaction
including ditch plugging in hill
section along the slopes as per
company's specification.
309.96
Tk./mtr
19940 mtr 6180602.40
13 Hydro-test 781.05
Tk./mtr
19940 mtr 15574137.00
14 Clean up and re-instatement of
ROW
311.60
Tk./mtr
19940 mtr 6213304.00
15 a) Hook up/Tie-in works at source
manifold/offtake with necessary
piping & other ancilliary works.
LS 369000.00
b) Hook up/Tie in at outlet source
manifold off/take with necessary
piping & other ancilliary works.
LS 369000.00
16 Providing assistance with
commissioning (supply of required
quantity of commissioning pigs and
Nitrogen)
85047.12
Tk./km
19.94 km 1695839.57
17 Cased Road & Rail crossing by
thrust boring as per design
and drawing.
i) Casing pipe: 762 mm OD
12226.20
Tk./mtr
24 mtr 293428.80
Table G.1 (continued)
(continued)
97
Sl no. Description Cost basis Qty. Unit Amount (tk) Remark
ii) Carrier pipe: 610 mm OD
Rail crossing = 01 no. (12 mtr)
Road Crossing = 01 no.(12 mtr)
18 Fabrication and installation of Pig
launcher, Pig receiver/valve stations
including all sorts of mechanical
erections, civil works, foundation,
fenching, painting as per design &
drawings complete in all respects.
LS 2558400.00 receiver &
launcher
19 Cost of radiography 8153.66
Tk./no
1680 nos. 13698148.80
20 Hot tapping along with piping and
off-take (as necessary to be carried
out by specialized sub-contractor on
turn key EPC contract)
30381000.00
21 Construction and placement of
Marker post including supply of MS
rod, Cement, Sand, Bricks, Chips
etc. & shuttering materials etc.
3198 Tk./no 20 nos. 63960.00
22 Mobilization and demobilization LS 4428000.00
Total 208138492
In words: TWENTY CRORE EIGHTY ONE LAC THIRTY EIGHT THOUSAND FOUR HUNDRED & NINETY TWO ONLY
Table G.1 (continued)
98
Table G.2
Provisional schedule of rates & quantities for construction of 16" 5.07 km 350 psi transmission
line from Patenga To Shah Mirpur Manifold station (2nd segment)
Sl
no.
Description Cost basis Qty. Unit Amount (tk) Remark
1 Preparation of ROW 125870.00
Tk./km
5.07 km 638160.90
2 Transportations, hauling of pipes
from Company's depot / pipe yard to
construction site.
58.49
Tk./ton-km
321.25
40
ton
km
751596.50 Assuming 40
km distance.
3 Transportation and storage of
induction Bends, valves, flanges,
tapes, primer and other pipeline
materials & fittings from company's
depot to work site.
82.66
Tk./ton-km
15
40
ton
km
49596.00 Assuming 40
km distance.
4 Stringing of line pipe along with
Right-of-way (ROW)
237.43
Tk./mtr
2570 mtr 610195.10
5 Field bends to 8D radius using
Hydraulic Pipe bending machine
3019.65
Tk./mtr
250 mtr 754912.50
(continued)
99
Sl
no.
Description Cost basis Qty. Unit Amount (tk) Remark
6 Welding: cleaning, cutting, beveling
of pipes and fittings including
chamfering of over thickness and re-
beveling (if required) of pipes and
fittings. Line up by internal clamp
and welding and weld repairs as per
API.1104
11808.00
Tk./no
230 nos. 2715840.00
7 External cleaning of pipe prior to
coating & wrapping operation by
sand blasting.
391.55
Tk./mtr
2570 mtr 1006283.50
8 Applying primer and polyethylene
tape (inner and other tape) by semi
mechanical machine and holyday
checking to the pipe and bends.
1108.76
Tk./mtr
2570 mtr 2849513.20
9 Cleaning of weld area of mainline
pipe by sand blasting and joint
coating by heat shrink sleeve
1002.92
Tk./no
230 nos. 230671.60
10 Trenching 401.80
Tk./mtr
2570 mtr 1032626.00
11 Lowering 409.18
Tk./mtr
2570 mtr 1051592.60
Table G.2 (continued)
(continued)
100
Sl
no.
Description Cost basis Qty. Unit Amount (tk) Remark
12 Back filling with proper compaction
including ditch plugging in hill
section along the slopes as per
company's specification.
206.64
Tk./mtr
2570 mtr 531064.80
13 Hydro-test 456.22
Tk./mtr
5070 mtr 2313035.40
14 Clean up and re-instatement of ROW 197.62
Tk./mtr
2570 mtr 507883.40
15 a) Hook up/Tie-in works at source
manifold/offtake with necessary
piping & other ancillary works.
LS 221400.00
b) Hook up/Tie in at outlet source
manifold off/take with necessary
piping & other ancillary works.
LS 221400.00
16 Providing assistance with
commissioning (supply of required
quantity of commissioning pigs and
Nitrogen)
49145.88
Tk./km
5.07 km 249169.61
17 Fabrication and installation of Pig
launcher, Pig receiver/valve stations
including all sorts of mechanical
LS 1359150.00 receiver &
launcher
Table G.2 (continued)
(continued)
101
Sl
no.
Description Cost basis Qty. Unit Amount (tk) Remark
erections, civil works, foundation,
fencing, painting as per design &
drawings complete in all respects.
18 Cost of radiography 5435.77
Tk./no
230 nos. 1250227.10
19 Hot tapping along with piping and
off-take (as necessary to be carried
out by specialized sub-contractor on
turn key EPC contract)
25584000.00
20 Major River Crossing along with
supply of FBE line pipe,isolation
valves, chemicals, consumables, rig,
side Boom etc. as necessary of HDD
method under EPC turn key
contract including OH, VAT, ITand
Contractors profit.
a) Karnaphuli river crossing 2500
mtr
63960000
Tk./
river width
500M -
1000M
2500 mtr 191880000.00
21 Construction and placement of
Marker post including supply of MS
rod, Cement, Sand, Bricks, Chips
3198 Tk./no 3 nos. 9594.00
Table G.2 (continued)
(continued)
102
Sl
no.
Description Cost basis Qty. Unit Amount (tk) Remark
etc. & shuttering materials etc.
22 Mobilization and demobilization LS 3075000.00
Total 238892912
In words: TWENTY THREE CRORE EIGHTY EIGHT LAC NINETY TWO THOUSAND NINE HUNDRED & TWELVE ONLY
Table G.2 (continued)
103
Table G.3
Provisional schedule of rates & quantities for construction of 20 inch 19.28 km 350 psi
transmission line from Shah Mirpur to BFIDC Manifold station (3rd segment)
Sl
no.
Description Cost basis Qty. Unit Amount (tk) Remark
1 Preparation of ROW 179580.00
Tk./km
19.28 km 3462302.40
2 Transportation, hauling of pipes
from Company's depot / pipe yard to
construction site.
57.72
Tk./ton-km
2736
40
ton
km
6316876.80 Assuming 40
km distance.
3 Transportation and storage of
induction Bends, valves, flanges,
tapes, primer and other pipeline
materials & fittings from company's
depot to work site.
92.50
Tk./ton-km
200
40
ton
km
740000.00 Assuming 40
km distance.
4 Stringing of line pipe along with
Right-of-way (ROW)
261.17
Tk./mtr
17280 mtr 4513017.60
5 Field bends to 8D radius using
Hydraulic Pipe bending machine
3355.17
Tk./mtr
10000 mtr 33551700.00
(continued)
104
Sl
no.
Description Cost basis Qty. Unit Amount (tk) Remark
6 Welding: cleaning, cutting, beveling
of pipes and fittings including
chamfering of over thickness and re-
beveling (if required) of pipes and
fittings. Line up by internal clamp
and welding and weld repairs as per
API.1104
14137.62
Tk./no
1460
nos.
20640925.20
7 External cleaning of pipe prior to
coating & wrapping operation by
sand blasting.
469.86
Tk./mtr
17280 mtr 8119180.80
8 Applying primer and polyethylene
tape (inner and other tape) by semi
mechanical machine and holyday
checking to the pipe and bends.
1194.15
Tk./mtr
17280 mtr 20634912.00
9 Cleaning of weld area of mainline
pipe by sand blasting and joint
coating by heat shrink sleeve
1107.00
Tk./no
1460 nos. 1616220.00
10 Trenching 508.40
Tk./mtr
17280 mtr 8785152.00
Table G.3 (continued)
(continued)
105
Sl
no.
Description Cost basis Qty. Unit Amount (tk) Remark
11 Lowering 409.18
Tk./mtr
17280 mtr 7070630.40
12 Back filling with proper compaction
including ditch plugging in hill
section along the slopes as per
company's specification.
258.30
Tk./mtr
17280 mtr 4463424.00
13 Hydro-test 563.34
Tk./mtr
19280 mtr 10861195.20
14 Clean up and re-instatement of ROW 254.94
Tk./mtr
17280 mtr 4405363.20
15 a) Hook up/Tie-in works at source
manifold/offtake with necessary
piping & other ancillary works.
LS 295200.00
b) Hook up/Tie in at outlet source
manifold off/take with necessary
piping & other ancillary works.
LS 295200.00
16 Providing assistance with
commissioning (supply of required
quantity of commissioning pigs and
Nitrogen)
55886.28
Tk./km
19.28 km 1077487.48
Table G.3 (continued)
(continued)
106
Sl
no.
Description Cost basis Qty. Unit Amount (tk) Remark
17 Cased Road & Rail crossing by
thrust boring as per design
and drawing.
i) Casing pipe: 610 mm OD
ii) Carrier pipe: 508 mm OD
Ctg-Cox's Bazar highway crossing
10188.50
Tk./mtr
20 mtr 203770.00
18 Fabrication and installation of Pig
launcher, Pig receiver/valve stations
including all sorts of mechanical
erections, civil works, foundation,
fencing, painting as per design &
drawings complete in all respects.
LS 1918800.00 receiver &
launcher
19 Cost of radiography 6794.71
Tk./no
1460 nos. 9920276.60
20 Hot tapping along with piping and
off-take (as necessary to be carried
out by specialized sub-contractor on
turn key EPC contract)
25830000.00
21 Major River Crossing along with
supply of FBE line pipe, Isolation
valves, Chemicals, Consumables,
65559000
Tk./
river width
Table G.3 (continued)
(continued)
107
Sl
no.
Description Cost basis Qty. Unit Amount (tk) Remark
Rig, Side Boom etc.As necessary of
HDD method under EPC turn key
contract
500 M -
1000M
a) Kalarpul crossing (500 mtr) 65559000.00
b)Kalurghat Karnaphuli crossing
(1500 mtr)
131118000.00
22 Construction and placement of
Marker post including supply of MS
rod, Cement, Sand, Bricks, Chips
etc. & shuttering materials etc.
3198 Tk./no 20 nos. 63960.00
23 Mobilization and demobilization LS 3936000.00
Total 375398594
In words: THIRTY SEVEN CRORE FIFTY THREE LAC NINETY EIGHT THOUSAND FIVE HUNDRED & NINETY FOUR ONLY
Table G.3 (continued)
108
Table G.4
Provisional schedule of rates & quantities for construction of 24" 12.81 km 350 psi transmission
line from BFIDC manifold station to CGS Fouzdarhat (4th segment)
Sl
no.
Description Cost basis Qty. Unit Amount (tk) Remark
1 Preparation of ROW 179580.00
Tk./km
12.81 km 2300419.80
2 Transportation, hauling of pipes
from Company's depot / pipe yard to
construction site.
58.49
Tk./ton-km
2028.25
40
ton
km
4745293.70 Assuming 40
km distance.
3 Transportation and storage of
induction Bends, valves, flanges,
tapes, primer and other pipeline
materials & fittings from company's
depot to work site.
107.26
Tk./ton-km
200
40
ton
km
858080.00 Assuming 40
km distance.
4 Stringing of line pipe along with
Right-of-way (ROW)
290.19
Tk./mtr
12810 mtr 3717333.90
5 Field bends to 8D radius using
Hydraulic Pipe bending machine
3355.17
Tk./mtr
1000 mtr 3355170.00
6 Welding: cleaning, cutting, beveling
of pipes and fittings including
chamfering of over thickness and re-
beveling (if required) of pipes and
16096.60
Tk./no
1090
nos. 17545294.00
(continued)
109
Sl
no.
Description Cost basis Qty. Unit Amount (tk) Remark
fittings. Line up by internal clamp
and welding and weld repairs as per
API.1104
7 External cleaning of pipe prior to
coating & wrapping operation by
sand blasting.
587.33
Tk./mtr
12810 mtr 7523697.30
8 Applying primer and polyethylene
tape (inner and other tape) by semi
mechanical machine and holyday
checking to the pipe and bends.
1293.55
Tk./mtr
12810 mtr 16570375.50
9 Cleaning of weld area of mainline
pipe by sand blasting and joint
coating by heat shrink sleeve
1230.00
Tk./no
1090 nos. 1340700.00
10 Trenching 610.08
Tk./mtr
12810 mtr 7815124.80
11 Lowering 491.02
Tk./mtr
12810 mtr 6289966.20
12 Back filling with proper compaction
including ditch plugging in hill
section along the slopes as per
company's specification.
309.96
Tk./mtr
12810 mtr 3970587.60
Table G.4 (continued)
(continued)
110
Sl
no.
Description Cost basis Qty. Unit Amount (tk) Remark
13 Hydro-test 781.05
Tk./mtr
12810 mtr 10005250.50
14 Clean up and re-instatement of ROW 311.60
Tk./mtr
12810 mtr 3991596.00
15 a) Hook up/Tie-in works at source
manifold/offtake with necessary
piping & other ancillary works.
LS 369000.00
b) Hook up/Tie in at outlet source
manifold off/take with necessary
piping & other ancillary works.
LS 369000.00
16 Providing assistance with
commissioning (supply of required
quantity of commissioning pigs and
Nitrogen)
85047.12
Tk./km
12.81 km 1089453.61
17 Cased Road & Rail crossing by
thrust boring as per design
and drawing.
i) Casing pipe: 762 mm OD
ii) Carrier pipe: 610 mm OD
Rail crossing = 03 no. (assumed 12
mtr each)
12226.20
Tk./mtr
60 mtr 733572.00
Table G.4 (continued)
(continued)
111
Sl
no.
Description Cost basis Qty. Unit Amount (tk) Remark
Road Crossing = 02 no.(assumed 12
mtr each)
18 Fabrication and installation of Pig
launcher, Pig receiver/valve stations
including all sorts of mechanical
erections, civil works, foundation,
fencing, painting as per design &
drawings complete in all respects.
LS 2558400.00 receiver &
launcher
19 Cost of radiography 8153.66
Tk./no
1090 nos. 8887489.40
20 Hot tapping along with piping and
off-take (as necessary to be carried
out by specialized sub-contractor on
turn key EPC contract)
30381000.00
21 Construction and placement of
Marker post including supply of MS
rod, Cement, Sand, Bricks, Chips
etc. & shuttering materials etc.
3198 Tk./no 12 nos. 38376.00
22 Mobilization and demobilization LS 4428000.00
Total 138883180
In words: THIRTEEN CRORE EIGHTY EIGHT LAC EIGHTY THREE THOUSAND ONE HUNDRED & EIGHTY ONLY
Table G.4 (continued)