Farakka Barrage Project ( Brief Background)
➢ Farakka Barrage Project (FBP) is located at Farakka in
West Bengal.
➢ It is a subordinate office under the DoWR, RD & GR,
MoJS.
➢ The FBP Authority was set up in 1961 with the mandate to
execute and thereafter operate and maintain FBP complex
comprising of Farakka Barrage, Jangipur Barrage, Feeder
Canal and its associated structures.
➢ The project construction commenced in 1961.
➢ The project was commissioned in 1975.
Necessity of Farakka Barrage Project
✓ The river Ganga bifurcates into two channels at about 40 km
downstream of Farakka.
✓ The Bhagirathi, known as Hooghly in its lower reach, is the
right channel which flows towards India.
✓ The Padma is the left channel and flows for about 90 km along
the Indo-Bangladesh Border and finally joins the Brahmaputra
in Bangladesh.
✓ The Bhagirathi used to receive bulk of Ganga waters centuries
ago and ensured enough flow to Bhagirathi-Hooghly river
system leading to Kolkata Port.
Necessity of Farakka Barrage Project
o Of late, the main river Ganga started flowing towards Padma in
Bangladesh, thereby depriving the Hooghly-Bhagirathi river system
of India of much needed water.
o The Kolkata Port – the main port providing commercial outlet and
inlet for the vast north, eastern hinterland was adversely affected due
to siltation because of inadequate flow through Bhagirathi / Hooghly
river system.
o Farakka Barrage was commissioned in 1975. The prime purpose was
to divert water into Hoogly river to prevent further siltation of
Kolkata port and flushing of silt deposited.
o Subsequently, for implementation of India-Bangladesh treaty-1996
for sharing of waters of river Ganga at Farakka
FUNCTIONS & OBJECTIVES OF FARAKKA BARRAGE
To divert 40000 cusecs quantity of Ganga waters into Bhagirathi - Hooghly river system though 38.38 km long Feeder canal for preservation and maintenance of Kolkata Port.
Improving the regime and navigability of the Bhagirathi -Hooghly river system through Feeder Canal in National Waterway No.1 from Allahabad to Haldia.
Water supply to power plants of NTPC Ltd at Farakka (2100MW) and WBPDC at Sagardighi (1600MW)
Bridge built over Farakka Barrage provides rail-cum-road communication link between North-Eastern Region and Eastern part of the country.
FUNCTIONS & OBJECTIVES OF FARAKKA BARRAGE
Regulation of water to Bangladesh as per Indo-Bangladesh Treaty-1996 on sharing of Ganga water at Farakka.
Checking the erosion along the river Ganga-Padma in districts Malda & Murshidabad.
Fresh Water supply to Kolkata city and en-route cities.
Farakka Barrage Project (Main Components)
➢ Farakka Barrage – 2245 M Long-largest barrage in India
➢Barrage & Head Regulator Gates (Total 123 nos.)
i. Under sluice gates (18.3m x 7.93m, 24 nos.)
ii. Spill way gates (18.3m x 6.40m, 84 Nos.)
iii. Fish Lock gates (8.23m wide in 2 tier - 4 nos.)
iv. Head Regulator Gates (12.20m x 8.45m in three tiers, 11 nos)
➢ Two lane Rail & two lane Road bridge over the barrage
➢ Feeder Canal – 38.38 Km long- (Capacity-40000 cusec).
➢ Jangipur Barrage – 212 m long, 12.20 m wide 2 tier gates, 15 Nos.).
➢ Navigation locks at Jangipur.
➢ Marginal Bunds, Canal Head Regulators, Sluices, Siphon etc.
Farakka Barrage Project (Other Establishments)
➢ Township at Farakka, Jangipur and Khejuriaghat.
➢ A Senior Secondary School at Farakka.
➢ One hospital at Farakka.
➢ Mechanical Workshop at Farakka.
➢ Left Afflux Bund of Farakka Barrage - 33.79 km in length,
Right Afflux Bund of Farakka Barrage - 7 km in length and
afflux bund of Jangipur Barrage – 16.31 km in length
➢ Two nos. rail-cum-road bridges and two road bridges across
the Feeder Canal
➢ A number of Regulators at different locations situated in
Murshidabad and Malda Districts of West Bengal
➢ Bagmari Syphon at RD 48.00 of Feeder Canal
Farakka Barrage Project (Activities)
▪ Operation & maintenance of Barrage & Head regulator
gates.
▪ Maintenance and protective measures of Feeder Canal (38.38
Km. in length), structures across Feeder Canal, Culverts,
Inlets, Ferry Services, Inspection Road (both banks), Syphon,
Buildings etc.
▪ Maintenance & protective measures of bank & bed of river
Ganga within the jurisdiction of FBP i.e upto 12 Km.
upstream and 6.9 Km downstream of Farakka Barrage.
▪ Maintenance of Farakka & Khejuriaghat Township, Project
Barrage colonies at Jangipur & Kalindri.
▪ Operation & Maintenance of equipment, vehicles and
machineries.
10
Farakka Barrage
Manikchak
Birnagar
Moya
Dhuliyan
Sagardighi
SATELLITTE IMAGE OF JURISDICTION OF
FARAKKA BARRAGE PROJECT
Jalangi
ORIGINAL JURISDICTION 12.5km u/s and 6.9km d/s restored in July 2017
Panchanandpur
Earlier EXTENDED JURISDICTION 40km
u/s to 80 km d/s
Indo-Bangladesh Border
Status of replacement of old Gates of Farakka Barrage(As on October, 2021)
11
Sl.
No.
Phase/ Type
of gate
Gate to be
replaced
Gate replaced
so farRemark
1. Phase 0 6 6 Work Completed in all respect
2. Phase 1 33 33 Work Completed in all respect.
3. Phase 2 35 32Rope fixing & control panel to be
installed.
4. Phase 3 31 18 Work is under progress.
5.Fish lock
gate4 0
Design & drawings are under
finalization and it will be
completed in this financial year.
6. H R Gate 11 To be replaced. The work is under planning stage.
Sl
no.
Regular
Establishment
Sanctioned Posts vide
ministry order dated
19-05-2021
Filled Vacant
1 Total Group – ‘A’ 24 10 14
2 Total Group- ‘B’
(Gazetted)
57 35 22
3 Total Group – B
(Non-Gazetted)
96 32 64
4 Total Group – C 110 68 42
Total (Regular) 287 145 142
FBP – Regular posts sanctioned/ filled / vacant (As on 01-11-2021)
18
“Farakka Barrage” Scheme For the year 2021-22 to 2025-26
Abstract of Cost
Sl.
No.Item
Proposed Total
(2021-2026) Rs. In Crore
1. Civil Works 183.56
2. Mechanical Works 72.96
3. Electrical Works 29.69
4. Establishment 341.42*
5. Machinery & Equipment 3.09
6. O&M of FBP Hospital 0.45
7. Other Charges 0.25
TOTAL 631.42