EIA: Thailand: Nong Saeng Natual Gas Power Project
-
Upload
khangminh22 -
Category
Documents
-
view
1 -
download
0
Transcript of EIA: Thailand: Nong Saeng Natual Gas Power Project
Final Environmental Impact Assessment Project Number: 44946 July 2011
THA: NONG SAENG NATURAL GAS POWER PROJECT Prepared by Power Generation Supply Co., Ltd. for the Asian Development Bank.
The environmental impact assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board of Directors, Management, or staff. Your attention is directed to the “Terms of Use” Section of this website.
208102_cover-ADB.doc
Environmental Report for submittal to ADB Nong-Saeng Power Plant Project
Final Report Nong-Saeng District, Saraburi Province and Pachee
District, Phra Nakhon Si Ayutthaya Province
Power Generation Supply Co., Ltd.
May 2011
T-EIA208102/SECOT (1) Table of Content.doc
Environmental Report for submittal to ADB
Nong-Saeng Power Plant Project
Power Generation Supply Co., Ltd.
CONTENTS
Page
Chapter 1 Executive Summary ___________________________________________ 1-1
1.1 Air Quality ___________________________________________________ 1-2
1.2 Noise Level __________________________________________________ 1-3
1.3 Surface Water Hydrology and Surface Water Quality __________________ 1-4
1.4 Forestry and Wildlife Ecology ____________________________________ 1-6
1.5 Aquatic Ecology and Fishery _____________________________________ 1-7
1.6 Land Use ____________________________________________________ 1-7
1.7 Water Usage __________________________________________________ 1-8
1.8 Transportation ________________________________________________ 1-9
1.9 Drainage and Flood Control ______________________________________ 1-9
1.10 Solid Wastes _________________________________________________ 1-10
1.11 Occupational Health and Safety __________________________________ 1-11
1.12 Socio-economics _____________________________________________ 1-11
1.13 Public Relations and Public Participation __________________________ 1-12
Chapter 2 Policy, Legal and Administrative Framework _____________________ 2-1
2.1 Policy, Legal, and Administrative Framework _______________________ 2-1
2.2 Scope of the EIA Study _________________________________________ 2-2
2.3 Methodology _________________________________________________ 2-3
2.4 ONEP EIA Review and Approval Process __________________________ 2-5
T-EIA208102/SECOT (2) Table of Content.doc
CONTENTS (Cont’d) Page
Chapter 3 Project Description____________________________________________ 3-1
3.1 Project Background ____________________________________________ 3-1
3.2 Project Size and Location _______________________________________ 3-1
3.3 Project Implementation Plan ____________________________________ 3-10
3.4 Generating Capacity ___________________________________________ 3-12
3.5 Machinery, Equipment and Electricity Generating Process ____________ 3-12
3.6 Fuel Utilization ______________________________________________ 3-26
3.6.1 Natural Gas _____________________________________________ 3-26
3.6.2 Diesel Oil ______________________________________________ 3-30
3.7 Chemicals ___________________________________________________ 3-33
3.8 Electricity Transmission Line System _____________________________ 3-36
3.9 Water Usage System __________________________________________ 3-36
3.9.1 Raw Water Source _______________________________________ 3-36
3.9.2 Water Treatment System __________________________________ 3-47
3.9.3 Water Consumption ______________________________________ 3-48
3.10 Drainage System _____________________________________________ 3-52
3.10.1 Drainage System for Wastewater from Office Building __________ 3-52
and Storm Water
3.10.2 Drainage System for Process Wastewater ____________________ 3-53
3.11 Number of Employees _________________________________________ 3-53
3.12 Pollutants and Control System ___________________________________ 3-54
3.12.1 Sources and Air Emission Rates _____________________________ 3-54
3.12.2 Noise Control ______________________________________ 2-58
T-EIA208102/SECOT (3) Table of Content.doc
CONTENTS (Cont’d) Page
3.12.3 Sources of Wastewater, Wastewater Treatment System __________ 3-58
and Control
3.12.3.1 Construction Phase __________________________________ 3-58
3.12.3.2 Operation Phase ____________________________________ 3-58
3.12.4 Solid Wastes Management _________________________________ 3-62
3.12.4.1 Construction Phase __________________________________ 3-62
3.12.4.2 Operation Phase ____________________________________ 3-62
3.13 Green Area __________________________________________________ 3-65
Chapter 4 Description of the Environment (Baseline Data) __________________ 4.1-1
4.1 Physical Resources ___________________________________________ 4.1-1
4.1.1 Topography _____________________________________________ 4.1-1
4.1.2 Meteorology and Air Quality _______________________________ 4.1-3
4.1.2.1 Meteorology _______________________________________ 4.1-3
4.1.2-2 Ambient Air Quality __________________________________ 4.1-7
4.1.3 Noise Level ____________________________________________ 4.1-26
4.1.4 Geology/Earthquake _____________________________________ 4.1-28
4.1.4.1 Geological Condition _______________________________ 4.1-28
4.1.4.2 Earthquake Occurrence ______________________________ 4.1-32
4.1.4.3 Soil Resource _____________________________________ 4.1-32
4.1.5 Surface Water Hydrology and Surface Water Quality ___________ 4.1-38
4.1.5.1 Surface Water Resources around the Project Site __________ 4.1-38
T-EIA208102/SECOT (4) Table of Content.doc
CONTENTS (Cont’d) Page
4.1.5.2 Hydrology Study Results of the Project-Related __________ 4.1-40
Water Resources
4.1.5.3 Surface Water Quality _______________________________ 4.1-54
4.2 Biological Resources __________________________________________ 4.2-1
4.2.1 Forestry ________________________________________________ 4.2-1
4.2.1.1 Overall Forest Area of the Province _____________________ 4.2-1
4.2.1.2 Forest Condition around the Project Area _________________ 4.2-1
4.2.2 Wildlife ________________________________________________ 4.2-3
4.2.3 Aquatic Ecology _____________________________________ 4.2-23
4.3 Human Use Values ____________________________________________ 4.3-1
4.3.1 Land Use _______________________________________________ 4.3-1
4.3.2 Utilization of Surface Water Resources ______________________ 4.3-14
4.3.2.1 Utilization of Water from Klong Huaiba ________________ 4.3-15
(Klong Nong-Ngu-Loem)
4.3.2.2 Utilization of Water from the Pa-Sak River ______________ 4.3-16
4.3.3 Transportation __________________________________________ 4.3-35
4.3.3.1 Land Transportation ________________________________ 4.3-35
4.3.4 Agriculture ____________________________________________ 4.3-43
4.3.4.1 Agricultural Aspect _________________________________ 4.3-43
4.3.4.2 Livestock _________________________________________ 4.3-45
4.3.4.3 Fishery ___________________________________________ 4.3-46
4.3.5 Industry _______________________________________________ 4.3-47
T-EIA208102/SECOT (5) Table of Content.doc
CONTENTS (Cont’d) Page
4.3.6 Infrastructure and Utility _________________________________ 4.3-50
4.3.6.1 Water Usage ______________________________________ 4.3-50
4.3.6.2 Electricity Usage ___________________________________ 4.3-50
4.3.6.3 Solid Waste Disposal _______________________________ 4.3-55
4.3.6.4 Drainage and Flood Protection ________________________ 4.3-55
4.3.6.5 Disaster Prevention _________________________________ 4.3-64
4.4 Quality of Life Values _______________________________________ 4.4.1-1
4.4.1 Socio-economic _______________________________________ 4.4.1-1
4.4.1.1 Introduction ______________________________________ 4.4.1-1
4.4.1.2 Methodology _____________________________________ 4.4.1-1
4.4.1.3 Study Results ____________________________________ 4.4.1-11
4.4.1.4 Conclusion of socio-economic study _________________ 4.4.1-39
4.4.2 Public Health _________________________________________ 4.4.2-1
4.4.2.1 Public Health Service and Staff ______________________ 4.4.2-1
4.4.2-2 Public Health Problem ____________________________ 4.4.2-16
4.4.3 Historical Sites and Objects _____________________________ 4.4.2-39
4.4.4 Aesthetics, Scenery and Tourism _________________________ 4.4.2-40
Chapter 5 Anticipated Environmental Impact and Mitigation Measures ________ 5-1
5.1 Physical Resources ____________________________________________ 5.1-1
5.1.1 Air Quality _____________________________________________ 5.1-1
5.1.1.1 Construction Phase __________________________________ 5.1-1
5.1.1.2 Operation Phase ____________________________________ 5.1-2
T-EIA208102/SECOT (6) Table of Content.doc
CONTENTS (Cont’d) Page
5.1.2 Noise Level ____________________________________________ 5.1-61
5.1.2.1 Construction Phase _________________________________ 5.1-61
5.1.2.2 Operation Phase ___________________________________ 5.1-68
5.1.3 Surface Water Hydrology _________________________________ 5.1-77
5.1.3.1 Construction Phase _________________________________ 5.1-77
5.1.3.2 Operation Phase ___________________________________ 5.1-78
5.1.4 Surface Water Quality ___________________________________ 5.1-84
5.1.4.1 Construction Phase _________________________________ 5.1-84
5.1.4.2 Operation Phase ___________________________________ 5.1-86
5.2 Biological Resources __________________________________________ 5.2-1
5.2.1 Forestry ________________________________________________ 5.2-1
5.2.1.1 Construction Phase __________________________________ 5.2-1
5.2.1.2 Operation Phase ____________________________________ 5.2-1
5.2.2 Wildlife ________________________________________________ 5.2-1
5.2.2.1 Construction Phase __________________________________ 5.2-2
5.2.2.2 Operation Phase ____________________________________ 5.2-3
5.2.3 Aquatic Ecology and Fishery _______________________________ 5.2-4
5.2.3.1 Construction Phase __________________________________ 5.2-4
5.2.3.2 Operation Phase ____________________________________ 5.2-5
5.3 Human Use Values ____________________________________________ 5.3-1
5.3.1 Land Use _______________________________________________ 5.3-1
5.3.2 Transportation ___________________________________________ 5.3-5
5.3.3 Water Usage ___________________________________________ 5.3-23
T-EIA208102/SECOT (7) Table of Content.doc
CONTENTS (Cont’d) Page
5.3.3.1 Construction Phase _________________________________ 5.3-23
5.3.3.2 Operation Phase ___________________________________ 5.3-23
5.3.4 Electricity Usage ________________________________________ 5.3-26
5.3.4.1 Construction Phase _________________________________ 5.3-26
5.3.4.2 Operation Phase ___________________________________ 5.3-26
5.3.5 Solid Wastes Management __________________________________ 5.3-27
5.3.5.1 Construction Phase __________________________________ 5.3-27
5.3.5.2 Operation Phase _____________________________________ 5.3-28
5.3.6 Drainage and Flood Control _________________________________ 5.3-30
5.3.6.1 Construction Phase __________________________________ 5.3-30
5.3.6.2 Operation Phase _____________________________________ 5.3-32
5.4 Quality of Life Value ____________________________________________ 5.4-1
5.4.1 Socio-Economic ___________________________________________ 5.4-1
5.4.1.1 Construction Phase ___________________________________ 5.4-1
5.4.1.2 Operation Phase ____________________________________ 5.4-5
5.4.2 Public Health _____________________________________________ 5.4-7
5.4.2.1 Impact of Air Pollutants on Health ______________________ 5.4-8
5.4.2.2 Assessment of Health Impacts from Project Operation _____ 5.4-13
5.4.3 Historic, Archaeological, Aesthetic and Tourism Resources ________ 5.4-15
5.4.4 Occupational Health and Safety ______________________________ 5.4-15
5.4.4.1 Noise Level _______________________________________ 5.4-15
5.4.4.2 Heat _____________________________________________ 5.4-16
5.4.4.3 Chemicals ________________________________________ 5.4-16
T-EIA208102/SECOT (8) Table of Content.doc
CONTENTS (Cont’d) Page
5.4.4.4 Fire Prevention System ______________________________ 5.4-17
5.4.5 Major Hazards Assessment _________________________________ 5.4-28
5.4.5.1 Approach of Major Hazards Assessment __________________ 5.4-28
5.4.5.2 Simulation Model ____________________________________ 5.4-29
5.4.5.3 Hazard Identification _________________________________ 5.4-30
5.4.5.4 Consequence Assessment ______________________________ 5.4-36
5.4.5.5 Summary of Major Hazard Assessment ___________________ 5.4-88
Chapter 6 Analysis of Alternatives ________________________________________ 6-1
Chapter 7 Information, Disclosure, Consultation and Participation ____________ 7-1
7.1 Introduction _____________________________________________________ 7-1
7.2 Objective _______________________________________________________ 7-2
7.3 Target Group and Implementation Area ________________________________ 7-2
7.4 Work Plan and Activities Performed __________________________________ 7-2
7.5 Results _________________________________________________________ 7-8
7.5.1 Media preparation/public relation media production _________________ 7-8
7.5.2 Communication for making understanding with offices/organization/ ___ 7-11
communities/people (First public hearing)
7.5.3 Presentation of the Study results and public hearing about ____________ 7-20
environmental measures (Second public hearing)
7.6 Conclusion of the Works on Public Relation and Public Participation _______ 7-51
7.6.1 Participation in news/information acknowledgement, understanding, ___ 7-51
and suggestion for the project
7.6.2 Participation of people and relevant persons ______________________ 7-52
T-EIA208102/SECOT (9) Table of Content.doc
CONTENTS (Cont’d) Page
7.6.3 Summary of questioning issues obtained from _____________________ 7-53
the public hearing activity
7.6.4 Implementation in accordance with the regulation __________________ 7-53
of the Office of Prime Minister
7.6.5 Suggestion for further work ___________________________________ 7-53
Chapter 8 Grievance Redress Mechanism __________________________________ 8-1
Chapter 9 Environmental Management Plan _______________________________ 9-1
Chapter 10 Conclusion and Recommendation _____________________________ 10-1
10.1 Air Quality _____________________________________________________ 10-2
10.2 Noise Level_____________________________________________________ 10-4
10.3 Surface Water Hydrology and Surface Water Quality ____________________ 10-5
10.4 Forestry and Wildlife Ecology ______________________________________ 10-7
10.5 Aquatic Ecology and Fishery _______________________________________ 10-7
10.6 Land Use ______________________________________________________ 10-7
10.7 Water Usage ____________________________________________________ 10-8
10.8 Transportation __________________________________________________ 10-9
10.9 Drainage and Flood Control ________________________________________ 10-9
10.10 Solid Wastes ___________________________________________________ 10-10
10.11 Occupational Health and Safety ____________________________________ 10-11
10.12 Socio-economics _______________________________________________ 10-12
10.13 Public Relation and Public Participation _____________________________ 10-13
10.14 Recommendation _______________________________________________ 10-14
T-EIA208102/SECOT (10) Table of Content.doc
LIST OF TABLES Table Page
3.5-1 Preliminary Technical Details of Nong-Saeng Power Plant Project ______ 3-17
3.5-2 Operating Data at Various Generating Capacity of ___________________ 3-27
Nong-Saeng Power Plant Project
Power Generation Supply Co., Ltd.
3.6-1 Specification of Diesel Oil Used as Backup Fuel ____________________ 3-31
Nong-Saeng Power Plant Project
3.7-1 Types and Consumption Rate of Chemicals for _____________________ 3-34
Nong-Saeng Power Plant Project
3.12-1 Stack Data and Air Emission Rates Incase of Natural Gas Firing ________ 3-55
Nong-Saeng Power Plant Project
Power Generation Supply Co,. Ltd.
3.12.2 Stack Data and Air Emission Rates Incase of Diesel Oil Firing _________ 3-56
Nong-Saeng Power Plant Project
Power Generation Supply Co,. Ltd.
3.12.3 Effluent Quality Standard of Nong-Saeng Power Plant Project _______ 3-60
3.12.4 Type, Quantity and Management of Solid Wastes ___________________ 3-64
Generated during Operation Phase
4.1.2-1 Climatological Data during the Period of 1976-2005 _________________ 4.1-4
4.1.2-2 Frequency of Occurrence of Wind Directions ______________________ 4.1-10
at Various Wind Speeds in the Year 2007
Don Muang Meteorological Station
4.1.2-3 Percentage of Atmospheric Stabillity Class in the Year 2007 __________ 4.1-12
Don Muang Meteorological Station
T-EIA208102/SECOT (11) Table of Content.doc
LIST OF TABLES (Cont’d) Table Page
4.1.2-4 Monitoring Results of Ambient Air Quality _______________________ 4.1-15
by Pollution Control Department
Kao Noy Fire Fighting Station, during thy Year 2005-2008
4.1.2-5 24-hr Average Concentration of Total Suspended Particulates (TSP) ___ 4.1-20
in the Vicinity Area of Nong-Saeng Power Plant
during the Year 2007-2009
4.1.2-6 1-hr Average Concentration of Nitrogen Dioxide (NO2) _____________ 4.1-22
in the Vicinity Area of Nong-Saeng Power Plant
during January 9-14, 2007 and April 24-29, 2008
4.1.2-7 1-hr Average Concentration of Sulfur Dioxide (SO2) _______________ 4.1-24
in the Vicinity Area of Nong-Saeng Power Plant
during January 9-14, 2007 and April 24-29, 2008
4.1.2-8 24-hr Average Concentration of Sulfur Dioxide (SO2) ______________ 4.1-25
in the Vicinity Area of Nong-Saeng Power Plant
during January 9-14, 2007 and April 24-29, 2008
4.1.2-9 Measurement Results of Sound Pressure Level _____________________ 4.1-27
in the Vicinity Area of Nong Saeng Power Plant Project
during January 9-14, 2007 and April 24-29, 2008
4.1.5-1 Measured Values of Water Current, Temperature, Salinity ____________ 4.1-43
and Suspended Solids of Pa-Sak River at Station A
during August 11-12, 2008
4.1.5-2 Water Current Results in Klong Huaiba _________________________ 4.1-50
(Klong Klong Nong-Ngu-Loem) at the Level of 3.10 Meters
from Bank to Water Surface on August 11, B.E.2551 (at 09.00 a.m.)
T-EIA208102/SECOT (12) Table of Content.doc
LIST OF TABLES (Cont’d) Table Page
4.1.5-3 Water Current Results in Klong Huaiba __________________________ 4.1-51
(Klong Klong Nong-Ngu-Loem) at the Level of 3.10 Meters
from Bank to Water Surface on August 11, B.E.2551 (at 11.30 a.m.)
4.1.5-4 Water Current Results in Klong Huaiba __________________________ 4.1-52
(Klong Klong Nong-Ngu-Loem) at the Level of 3.09 Meters
from Bank to Water Surface on August 11, B.E.2551 (at 2.00 p.m.)
4.1.5-5 Water Current Results in Klong Huaiba __________________________ 4.1-53
(Klong Klong Nong-Ngu-Loem) at the Level of 3.09 Meters
from Bank to Water Surface on August 11, B.E.2551 at 04.30 p.m.
4.1.5-6 Water Flow Rate and Water Depth Relation of Klong Huaiba _________ 4.1-55
(Klong Nong-Ngu-Loem)
4.1.5-7 Pa-Sak River Water Quality of the Office of Irrigation 10th -Lopburi. ___ 4.1-58
26 May B.E.2549
4.1.5-8 Water Quality in Pa-Sak River in Rama Six Dam from Examples ______ 4.1-59
24 April and 21 June B.E.2551
4.1.5-9 Water Quality in Klong Rapeepatana of the Office of Irrigation _______ 4.1-62
10th -Lopburi 26 May B.E.2549
4.1.5-10 Water Quality Analysis Result in Klong Rapeepatana _______________ 4.1-65
25 January B.E.2550
4.1.5-11 Water Quality Analysis Result in Klong Huaiba ____________________ 4.1-67
(Klong Nong-Ngu-Loem) 25 January B.E.2550
T-EIA208102/SECOT (13) Table of Content.doc
LIST OF TABLES (Cont’d) Table Page
4.1.5-12 Water Quality in in Klong Huaiba (Klong Nong-Ngu-Loem) __________ 4.1-68
from Example 24 April and 25 June B.E.2551
4.1.5-13 Monitoring Results of Water Quality in Klong Huaiba ______________ 4.1-73
(Klong Nong-Ngu-Loem) in August B.E.2551
4.2.1-1 National Forest, National Park and National Forest Park in ____________ 4.2-2
Saraburi Province
4.2.2-1 Type, Status, Abundance and Impact of Amphibian in Study Area ______ 4.2-8
4.2.2-2 Type, Status, Abundance and Impact of Reptile in Study Area _________ 4.2-9
4.2.2-3 Type, Status, Abundance and Impact of Birds in Study Area __________ 4.2-11
4.2.2-4 Type, Status, Abundance and Impact of Mammals in Study Area ______ 4.2-18
4.2.3-1 Survey Results of Phytoplankton in Study Area ____________________ 4.2-24
during January 25-26, 2007
4.2.3-2 Survey Results of Zooplanktons in Study Area _____________________ 4.2-25
during January 25-26, 2007 and on February 15, 2008
4.2.3-3 Survey Results of Bentos in Study Area __________________________ 4.2-26
during January 25-26, 2007 and on February 15, 2008
4.2.3-4 Survey Results of Phytoplankton in Study Area ____________________ 4.2-29
on December 4, 2008
4.2.3-5 Survey Results of Zooplankton in Study Area ______________________ 4.2-31
on December 4, 2008
4.2.3-6 Survey Results of Bentos in Study Area __________________________ 4.2-32
on December 4, 2008
T-EIA208102/SECOT (14) Table of Content.doc
LIST OF TABLES (Cont’d) Table Page
4.3.1-1 Agricultural Area in Nong-Saeng District, Nong-Kae District, _________ 4.3-4
Saraburi Province and Pachee District, Phra Nakhon Si Ayutthaya Province
in the year 2007
4.3.1-2 Land Use in the Study Area of 5 km. Radius ________________________ 4.3-5
4.3.1-3 Land Use in the Study Area of 500 m Radius from Water Pipeline ______ 4.3-9
Nong-Saeng Power Plant Project
4.3.2-1 Water Conveyance and Maintenance Project Area __________________ 4.3-19
of Irrigation Department in Downstream of Water Pumping Area
of Nong-Saeng Power Plant Project
4.3.2-2 Monthly Quantity of River Water at Water Pumping Point____________ 4.3-22
of Nong-Saeng Power Plant Project
4.3.2-3 Monthly Quantity of Water Released through Phra Narai Water Gate ___ 4.3-26
4.3.2-4 Monthly and Annually Average of Water Consumption of Plants ______ 4.3-32
Lopburi Meteorological Station
4.3.2-5 Water Usage Coefficient of Rice ________________________________ 4.3-32
4.3.2-6 Quantity of Water Requirement for Irrigation ______________________ 4.3-32
Based on 1,000 Rai of Rice Field and 3 Cultivating Cycles per Year
4.3.3-1 Daily Average Traffic Volume on Highway No.1 ___________________ 4.3-38
in Adjacent Project Area during the year 2005-2007
4.3.3-2 Daily Average Traffic Volume on Highway No.329 ________________ 4.3-40
in Adjacent Project Area during the year 2005-2007
4.3.3-3 Daily Traffic Volume on Highway No.3043 in Adjacent Project Area _ 3.3.3-41
during the year 2005-2007
T-EIA208102/SECOT (15) Table of Content.doc
LIST OF TABLES (Cont’d) Table Page
4.3.3-4 Daily Average Traffic Volume on Road along the Bank _____________ 4.3-42
of Klong Rapeepatana (Right Side)
during July 31-August 1, 2007
4.3.3-5 Daily Traffic Volume on Road along the Bank of Klong Rapeepatana ___ 4.3-44
(Left Side) during July 31-August 1, 2007
4.3.5-1 List of Factories in the Study Area _______________________________ 4.3-51
4.4.1-1 Number of Households and Household Samples ___________________ 4.4.1-9
for Socio-economic Survey
4.4.1-2 Administration Area, Number of Sub-districts and Villages ________ 4.4.1-13
in Saraburi, Classified by District
4.4.1-3 Administration Area, Number of Sub-districts and Villages _________ 4.4.1-14
in Phra Nakhon Si Ayutthaya, Classified by District
4.4.1-4 Temples in the Study Area and Distances _______________________ 4.4.1-17
from the Nong-Saeng Power Plant Project
4.4.1-5 Schools in the Study Area, Classes and Distances _________________ 4.4.1-18
from the Nong-Saeng Power Plant Project
4.4.1-6 Summary of Socio-economic Status of Sub-districts_______________ 4.4.1-19
in the Study Area within the Radius of 5 km from
the Nongsaeng Power Plant Project
4.4.1-7 Number of Population, Households and Population Density_________ 4.4.1-24
in the Study Area
4.4.2-1 Public Health Service of Governmental and Private Sectors __________ 4.4.2-2
of Saraburi Province, in the year 2008
T-EIA208102/SECOT (16) Table of Content.doc
LIST OF TABLES (Cont’d) Table Page
4.4.2-2 Medical and Public Health Personnel of Governmental _____________ 4.4.2-3
and Private Sectors of Saraburi Province, in the Year 2007
4.4.2-3 Public Health Service of Governmental and Private Sectors __________ 4.4.2-4
of Nong-Saeng District, in the Year 2008
4.4.2-4 Medical and Public Health Personnel of Governmental _____________ 4.4.2-4
and Private Sectors of Nong-Saeng District, in the Year 2007
4.4.2-5 Public Health Service of Governmental and Private Sectors __________ 4.4.2-5
of Nong-Kae District, in the Year 2008
4.4.2-6 Medical and Public Health Personnel of Governmental _____________ 4.4.2-6
and Private Sectors of Nong-Kae District, in the Year 2007
4.4.2-7 Public Health Service of Governmental and Private Sectors __________ 4.4.2-8
of Phra Nakhon Si Ayutthaya Province, in the Year 2007
4.4.2-8 Medical and Public Health Personnel of Governmental _____________ 4.4.2-9
and Private Sectors of Phra Nakhon Si Ayutthaya Province,
in the Year 2007
4.4.2-9 Public Health Service of Governmental and Private Sectors __________ 4.4.2-9
of Pachee District, in the Year 2007
4.4.2-10 Medical and Public Health Personnel of Governmental ____________ 4.4.2-10
and Private Sectors of Pachee District, in the year 2007
4.4.2-11 Medical and Public Health Personnel of Nong-Kob _______________ 4.4.2-10
Sub-district Health Center, Khok Sa-at Sub-district Health Center,
Nong-Kwai-So, Nong-Huapho Sub-district Health Center, Khok Toom
Sub-district Health Center and Phonthong Sub-district Health Center
T-EIA208102/SECOT (17) Table of Content.doc
LIST OF TABLES (Cont’d) Table Page
4.4.2-12 Medical and Public Health Personnel of Nong-Saeng Hospital ______ 4.4.2-12
in the Year 2008
4.4.2-13 Medical and Public Health Personnel of Nong-Kae Hospital ________ 4.4.2-13
in the Year 2008
4.4.2-14 Medical and Public Health Personnel of Nong-Namsai ___________ 4.4.2-14
Sub-district Health Center, Khok Muang Sub-district Health Center,
Donyanang Sub-district Health Center and Rasom Sub-district Health Center
4.4.2-15 Medical and Public Health Personnel of Pachee Hospital ___________ 4.4.2-15
in the Year 2007
4.4.2-16 Number of Out-Patients in Saraburi Province Classified ___________ 4.4.2-17
by Causes (21 Disease) during the Year 2006-2008
4.4.2-17 Number of Out-Patients in Nong-Saeng District Classified _________ 4.4.2-18
by Causes (21 Disease) during the Year 2006-2008
4.4.2-18 Number of Out-Patients in Nong-Kae District Classified ___________ 4.4.2-19
by Causes (21 Disease) during the Year 2006-2008
4.4.2-19 Number of Out-Patients in Nong-Kae District Classified ___________ 4.4.2-21
by Causes (21 Disease) during the Year 2006-2008
4.4.2-20 Number of Out-Patients in Nong-Kae Classified__________________ 4.4.2-22
by Causes (21 Disease) during the Year 2007-2008
4.4.2-21 Incidence Rates of Out-Patients for the First 21 Diseases ___________ 4.4.2-23
at Nong-Kob Sub-district Health Center
during the Year 2006-2008
T-EIA208102/SECOT (18) Table of Content.doc
LIST OF TABLES (Cont’d) Table Page
4.4.2-22 Incidence Rates of Out-Patients for the First 21 Diseases ___________ 4.4.2-24
at Khok Sa-at Sub-district Health Center
during the year 2005-2007
4.4.2-23 Incidence Rates of Out-Patients for the First 21 Diseases ___________ 4.4.2-26
at Nong-Kwai-So Sub-district Health Center
during the year 2005-2007
4.4.2-24 Incidence Rates of Out-Patients for the First 21 Diseases ___________ 4.4.2-27
at Nong-Huapo Sub-district Health Center
during the year 2005-2007
4.4.2-25 Incidence Rates of Out-Patients for the First 21 Diseases ___________ 4.4.2-28
at Khok Toom Sub-district Health Center
during the year 2006-2008
4.4.2-26 Incidence Rates of Out-Patients for the First 21 Diseases ___________ 4.4.2-29
at Phonthong Sub-district Health Center
during the year 2005-2007
4.4.2-27 Number of Out-Patients in Phra Nakhon Si Ayutthaya Province _____ 4.4.2-30
Classified by Causes (21 Diseases) during the Year 2005-2007
4.4.2-28 Number of Out-Patients in Pachee District Classified _____________ 4.4.2-32
by Causes (21 Diseases) during the Year 2005-2007
4.4.2-29 Number of Out-Patients in Pachee Hospital Classified ____________ 4.4.2-33
by Causes (21 Diseases) during the Year 2005-2007
4.4.2-30 Incidence Rates of Out-Patients for the First 21 Diseases __________ 4.4.2-34
at Khok Muang Sub-district Health Center
during the Year 2006-2008
T-EIA208102/SECOT (19) Table of Content.doc
LIST OF TABLES (Cont’d)
Table Page
4.4.2-31 Incidence Rates of Out-Patients for the First 21 Diseases ___________ 4.4.2-35
at Rasom Sub-district Health Center
during the Year 2006-2008
4.4.2-32 Incidence Rates of Out-Patients for the First 21 Diseases ___________ 4.4.2-36
at Donyanang Sub-district Health Center
during the Year 2005-2007
4.4.2-33 Incidence Rates of Out-Patients for the First 21 Diseases _________________ 4.4.2-38
at Nong-Namsai Sub-district Health Center
during the Year 2005-2007
5.1.1-1 Meteorological Data and Frequency of Record ______________________ 5.1-4
of Meteorological Station
5.1.1-2 Stack Data and Air Emission Rates of Emission Sources ______________ 5.1-7
In case of Natural Gas Firing, Nong-Saeng Power Plant Project
Power Generation Supply Co,. Ltd.
5.1.1-3 Stack Data and Air Emission Rates of Emission Sources ______________ 5.1-8
In case of Diesel Oil Firing, Nong-Saeng Power Plant Project
Power Generation Supply Co,. Ltd.
5.1.1-4 Details of Emission Sources in SIL Industrial Land (Saraburi) __________ 5.1-9
5.1.1-5 Details of Emission Sources to be Developed in Future ______________ 5.1-13
5.1.1-6 Modeling Results of Maximum Concentration of Air Pollutants _______ 5.1-15
in Ambient Air Using Meteorological Data of Kao Noy Fire Station
Meteorological Station of the Year 2005
In case of Natural Gas Firing, Nong-Saeng Power Plant Project
T-EIA208102/SECOT (20) Table of Content.doc
LIST OF TABLES (Cont’d)
Table Page
5.1.1-7 Modeling Results of Maximum Concentration of Air Pollutants _______ 5.1-16
in Ambient Air Using Meteorological Data of Kao Noy Fire Station
Meteorological Station of the Year 2006
In case of Natural Gas Firing, Nong-Saeng Power Plant Project
5.1.1-8 Modeling Results of Maximum Concentration of Air Pollutants _______ 5.1-17
in Ambient Air Using Meteorological Data of Kao Noy Fire Station
Meteorological Station of the Year 2007
In case of Natural Gas Firing, Nong-Saeng Power Plant Project
5.1.1-9 Modeling Results of Maximum Concentration of Air Pollutants _______ 5.1-18
in Ambient Air Using Meteorological Data of Kao Noy Fire Station
Meteorological Station of the Year 2005
In case of Diesel Oil Firing, Nong-Saeng Power Plant Project
5.1.1-10 Modeling Results of Maximum Concentration of Air Pollutants _______ 5.1-19
in Ambient Air Using Meteorological Data of Kao Noy Fire Station
Meteorological Station of the Year 2006
In case of Diesel Oil Firing, Nong-Saeng Power Plant Project
5.1.1-11 Modeling Results of Maximum Concentration of Air Pollutants _______ 5.1-20
in Ambient Air Using Meteorological Data of Kao Noy Fire Station
Meteorological Station of the Year 2007
In case of Diesel Oil Firing, Nong-Saeng Power Plant Project
5.1.1-12 Modeling Results of Maximum Concentration of Air Pollutants _______ 5.1-21
in Ambient Air Using Meteorological Data of Kao Noy Fire Station
Meteorological Station of the Year 2007
In case of Start up/Shutdown, Nong-Saeng Power Plant Project
T-EIA208102/SECOT (21) Table of Content.doc
LIST OF TABLES (Cont’d)
Table Page
5.1.1-13 Modeling Results of Maximum 1-hr Average Concentration __________ 5.1-32
of Sulfur Dioxide in Ambient Air
Using Meteorological Data of the Year 2007 (Including Background)
Nong-Saeng Power Plant Project, Power Generation Supply Co., Ltd.
5.1.1-14 Modeling Results of Maximum 1-hr Average Concentration __________ 5.1-43
of Nitrogen Dioxide in Ambient Air
Using Meteorological Data of the Year 2007 (Including Background)
Nong-Saeng Power Plant Project, Power Generation Supply Co., Ltd.
5.1.1-15 Modeling Results of Maximum 24-hr Average Concentration _________ 5.1-54
of TSP in Ambient Air
Using Meteorological Data of the Year 2007 (Including Background
Nong-Saeng Power Plant Project, Power Generation Supply Co., Ltd.
5.1.2-1 Sound Pressure Level Generated from Various _____________________ 5.1-62
Construction Equipments, Nong-Saeng Power Plant Project
Power Generation Supply Co., Ltd.
5.1.2-2 Annoyance Noise Level of Project to Communities around Project Area _ 5.1-67
during Construction Phase, Nong-Saeng Power Plant Project
Power Generation Supply Co., Ltd.
5.1.2-3 Sound Pressure Level from Equipments/Machineries Installed ________ 5.1-69
during Operation Phase, Nong-Saeng Power Plant Project
Power Generation Supply Co., Ltd.
5.1.2-4 Annoyance Noise Level of Project to Communities around Project Area _ 5.1-72
during Operation Phase, Nong-Saeng Power Plant Project
Power Generation Supply Co., Ltd.
T-EIA208102/SECOT (22) Table of Content.doc
LIST OF TABLES (Cont’d)
Table Page
5.1.3-1 Monthly River Water Discharge into Klong Huaiba ________________ 5.1-82
(Klong Nong-Ngu-Loem)
as a result of the rainfalls over around areas
5.1.4-1 Comparison of Effluent Quality _________________________________ 5.1-88
of Nong-Saeng Power Plant Supply with Standard
5.1.4-2 Comparison of Effluent Quality in Klong Huaiba ___________________ 5.1-90
(Klong Nong-Ngu-Loem) Before and After Mixing with Effluent
of Nong-Saeng Power Plant and Standard of Surface Water
which is Not Sea Water
5.3.2-1 Passenger Car Unit Factor (PCU) of Vehicle ________________________ 5.3-6
5.3.2-2 Traffic Volume Capacity of Highway _____________________________ 5.3-6
5.3.2-3 Standard for Classification of Traffic Condition in Future _____________ 5.3-6
5.3.2-4 Traffic Volume in Relation to PCU on Highway No. 1 in the Year 2007 __ 5.3-7
5.3.2-5 Comparison of Traffic Volume in Relation to PCU __________________ 5.3-7
on Highway No.1 before Construction Phase, during Construction Phase
and Operation Phase
5.3.2-6 Traffic Volume in Relation to PCU on Highway No. 329 (16+000 km) ___ 5.3-8
in the Year 2007
5.3.2-7 Comparison of Traffic Volume in Relation to PCU __________________ 5.3-8
on Highway No.329 before Construction Phase,
during Construction Phase and Operation Phase
5.3.2-8 Traffic Volume in Relation to PCU on Highway No. 3043 ____________ 5.3-10
in the Year 2007
T-EIA208102/SECOT (23) Table of Content.doc
LIST OF TABLES (Cont’d)
Table Page
5.3.2-9 Comparison of Traffic Volume in Relation to PCU _________________ 5.3-10
on Highway No.3043 before Construction Phase,
during Construction Phase and Operation Phase
5.3.2-10 Traffic Volume in Relation to PCU on the Road along the Bank _______ 5.3-12
of Klong Rapeepatana-left during July 31-August 1, 2007
5.3.2-11 Traffic Volume in Relation to PCU on the Road along the Bank _______ 5.3-13
of Klong Rapeepatana-right during July 31-August 1, 2007
5.3.2-12 Traffic Volume on the Road along the Bank ______________________ 5.3-14
of Klong Rapeepatana-left during July 31-August 1, 2007
08.00-10.00 a.m. and 04.00-06.00 p.m.
5.3.2-13 Traffic Volume on the Road along the Bank _______________________ 5.3-14
of Klong Rapeepatana-right during July 31-August 1, 2007
08.00-10.00 a.m. and 04.00-06.00 p.m.
5.3.2-14 Traffic Volume in Relation to PCU on the Road along the Bank _______ 5.3-15
of Klong Rapeepatana-left during July 31-August 1, 2007,
during 08.00-10.00 a.m.
5.3.2-15 Traffic Volume in Relation to PCU on the Road along the Bank _______ 5.3-16
of Klong Rapeepatana-left during July 31-August 1, 2007,
during 04.00-06.00 p.m.
5.3.2-16 Traffic Volume in Relation to PCU on the Road along the Bank _______ 5.3-17
of Klong Rapeepatana-right during July 31-August 1, 2007,
during 08.00-10.00 a.m.
5.3.2-17 Traffic Volume in Relation to PCU on the Road along the Bank _______ 5.3-18
of Klong Rapeepatana-right during July 31-August 1, 2007,
during 04.00-06.00 a.m.
T-EIA208102/SECOT (24) Table of Content.doc
LIST OF TABLES (Cont’d)
Table Page
5.3.2-18 Comparison of Traffic Volume in Relation to PCU _________________ 5.3-20
during 08.00-10.00 a.m. and 04.00-06.00 p.m. on the Road along the Bank
of Klong Rapeepatana-right before Construction Phase,
during Construction Phase and Operation Phase
5.3.2-19 Comparison of Traffic Volume in Relation to PCU _________________ 5.3-21
during 08.00-10.00 a.m. and 04.00-06.00 p.m. on the Road along the Bank
of Klong Rapeepatana-left before Construction Phase,
during Construction Phase and Operation Phase
5.4.2-1 Impacts of Nitrogen Dioxide on Human __________________________ 5.4-10
5.4.2-2 Effects of Sulfur Dioxide and Smoke or Particulates on Human _______ 5.4-11
5.4.5-1 Details of Natural Gas Pipeline of Nong-Saeng Power Plant Project ____ 5.4-31
5.4.5-2 Details of Diesel Oil Storage Container __________________________ 5.4-32
of Nong-Saeng Power Plant Project
5.4.5-3 Details of Diesel Oil Pipeline of Nong-Saeng Power Plant Project ______ 5.4-32
5.4.5-4 Consequence Assessment in Case of Leakage ______________________ 5.4-37
in Natural Gas Pipeline Area
Nong-Saeng Power Plant Project
5.4.5-5 Consequence Assessment in Case of Leakage _____________________ 5.4-39
in Diesel Oil Pipeline Area
Nong-Saeng Power Plant Project
5.4.5-6 Consequence Assessment in case of Leakage ______________________ 5.4-40
in the Natural Gas Pipeline Area (In case of control valve failure)
Nong-Saeng Power Plant Project
T-EIA208102/SECOT (25) Table of Content.doc
LIST OF TABLES (Cont’d)
Table Page
5.4.5-7 Consequence Assessment in case of Leakage ______________________ 5.4-42
in Diesel Oil Pipeline Area (In case of control valve failure)
Nong-Saeng Power Plant Project
5.4.5-8 Consequence Assessment in case of Leakage ______________________ 5.4-43
in the Oil Storage Tank Area
Nong-Saeng Power Plant Project
7.4-1 Summary of Public Relation and Public Participation Activities _________ 7-7
Nong-Saeng Power Plant Project
7.5-1 Summary of Media Used in Social Study and People’s Opinion _________ 7-9
Nong-Saeng Power Plant Project
7.5-2 Date/Time, Place and Number of Participants in the First Public Hearing _ 7-14
of the Nong-Saeng Power Plant Project
7.5-3 Summary of Q&A Issues and Suggestions from the Public Hearing Stages ___ 7-16
Nong-Saeng Power Plant Project
7.5-4 Participants of the Tour to the Existing Power Plants ___________________ 7-21
7.5-5 Summary of Concern Issues, Suggestions and Corrective Method ________ 7-23
of the Tour Group
7.5-6 The Meeting for Result Presentation and the Second Public Hearing ______ 7-26
Nong-Saeng Power Plant Project
7.5-7 Summary of Concern Issues, Corrective Method and Suggestion _________ 7-28
from the Second Public Hearing
Nong-Saeng Power Plant Project
7.5-8 Summary of Questioning Issues and Explanation from Public Stage _______ 7-48
Nong-Saeng Power Plant Project
T-EIA208102/SECOT (26) Table of Content.doc
LIST OF TABLES (Cont’d)
Table Page
7.6-1 Summary of Community Concern Issues and Important ________________ 7-54
Suggestion Classified by Occupational Groups.
7.6-2 Summary of Community Concern Issues Used for Designation ___________ 7-56
of Social Mitigative Measures
Nong-Saeng Power Plant Project
7.6-3 Study Implementation in accordance with the Regulation of _____________ 7-66
the Office of the Prime Minister entitled “Public Hearing” B.E.2548
6.1.1 Stack Data and Air Emission Rates In case of Natural Gas Firing __________ 6-5
Nong-Saeng Power Plant Project
Power Generation Supply Co,. Ltd.
6.1.2 Stack Data and Air Emission Rates In case of Diesel Oil Firing ___________ 6-6
Nong-Saeng Power Plant Project
Power Generation Supply Co,. Ltd.
T-EIA208102/SECOT (27) Table of Content.doc
LIST OF FIGURES Figure Page 3.2-1 Location of Nong-Saeng Power Plant Project, _______________________ 3-2
Power Generation Supply Co., Ltd.
3.2-2 Location of Nong-Saeng Power Plant Project and _____________________ 3-3
Nearby Communities
3.2-3 Aerial Photograph of Nong-Saeng Power Plant Project Location ________ 3-4
and Vicinity Area
Power Generation Supply Co., Ltd.
3.2-4 Layout of Power Plant Site, Nong-Saeng Power Plant Project ___________ 3-5
3.2-5 Layout of Reservoir Site, Nong-Saeng Power Plant Project _____________ 3-6
3.2-6 Dike Surrounding Project Area, Nong-Saeng Power Plant Project ________ 3-7
3.2-7 Traffic Routes to Nong-Saeng Power Plant Project ____________________ 3-9
3.3-1 Operation Plan of Nong-Saeng Power Plant Project __________________ 3-11
3.3-2 Transmission Line Route of Nong-Saeng Power Plant Project __________ 3-13
3.5-1 Operating Principles of Cooling Tower of _________________________ 3-16
Nong-Saeng Power Plant Project
3.5-2 Schematic Diagram of Electricity Generating Process, ________________ 3-19
Nong-Saeng Power Plant Project
3.5-3 Heat Balance at Full Load (100% Load) Operation, __________________ 3-20
Using Natural Gas as Fuel
Nong-Saeng Power Plant Project
3.5-4 Heat Balance at Partial Load (80% Load) Operation, _________________ 3-21
Using Natural Gas as Fuel
Nong-Saeng Power Plant Project
T-EIA208102/SECOT (28) Table of Content.doc
LIST OF FIGURES (Cont’d) Figure Page
3.5-5 Heat Balance at Minimum Load (58% Load) Operation, ______________ 3-21
Using Natural Gas as Fuel
Nong-Saeng Power Plant Project
3.5-6 Heat Balance at Full Load (100% Load) Operation, __________________ 3-23
Using Diesel Oil as Fuel
Nong-Saeng Power Plant Project
3.5-7 Heat Balance at Partial Load (80% Load) Operation, _________________ 3-24
Using Diesel Oil as Fuel
Nong-Saeng Power Plant Project
3.5-8 Heat Balance at minimum load (58% Load) Operation, _______________ 3-25
Using Diesel Oil as Fuel
Nong-Saeng Power Plant Project
3.6-1 Map of Natural Gas Pipeline to Nong-Saeng Power Plant Project. _______ 3-29
3.6-2 Layout of Natural Gas Pipeline of Nong-Saeng Power Plant Project _____ 3-32
3.9-1 Location of Water Pumping Station and Route of Pipeline of __________ 3-37
Nong-Saeng Power Plant Project
3.9-2 Location of Water Pumping Station and Route of Pipeline of __________ 3-38
Nong-Saeng Power Plant Project
3.9-3 Route of Pipeline within Nong-Saeng Power Plant Project _____________ 3-39
in Power Plant Site Area.
3.9-4 Route of Pipeline within Nong-Saeng Power Plant Project ____________ 3-40
in Reservoir Area
T-EIA208102/SECOT (29) Table of Content.doc
LIST OF FIGURES (Cont’d) Figure Page
3.9-5 Structure in the Vicinity Area of Effluent Discharge to _______________ 3-41
Klong Nong-Ngu-Loem of Nong-Saeng Power Plant Project
3.9-6 Details of Water Pumping Station of Nong-Saeng Power Plant Project ___ 3-42
3.9-7 Details of Water Pumping Station of Nong-Saeng Power Plant Project ___ 3-43
3.9-8 Laying Raw Water Pipeline And Effluent Drainage, _________________ 3-46
Nong-Saeng Power Plant Project
3.9-9 Water Treatment System of Nong-Saeng Power Plant Project __________ 3-49
3.9-10 Demineralization System __________________________________________________________ 3-49
3.9-11 Water Balance when Natural Gas Is Used as Fuel, ____________________________ 3-50
Nong-Saeng Power Plant Project
3.9-12 Water Balance when Diesel Oil Is Used as Fuel, ____________________ 3-51
Nong-Saeng Power Plant Project
3.14-1 Green Areas of Nong-Saeng Power Plant Project ____________________ 3-65
4.1.1-1 Aerial Photograph of Nong-Saeng Power Plant Location ______________ 4.1-2
and Vicinity Area Power Generation Supply Co., Ltd.
4.1.2-1 Atmosphefic Pressure during 30-Year Period _______________________ 4.1-5
(the year 1976-2005), Don Muang Airport Meteorological Station
4.1.2-2 Temperature during 30-Year Period ______________________________ 4.1-5
(the year 1976-2005), Don Muang Airport Meteorological Station
4.1.2-3 Relative Humidity during 30-Year Period _________________________ 4.1-6
(the year 1976-2005), Don Muang Airport Meteorological Station
T-EIA208102/SECOT (30) Table of Content.doc
LIST OF FIGURES (Cont’d) Figure Page
4.1.2-4 Rainfall during 30-Year Period _________________________________ 4.1-6
(the year 1976-2005), Don Muang Airport Meteorological Station
4.1.2-5 Wind Roses during 30-Year Period (the year 1951-1980), _____________ 4.1-8
Don Muang Meteorological Station
4.1.2-6 Wind Roses during 10-Year Period (the year 1981-1990), _____________ 4.1-9
Don Muang Meteorological Station
4.1.2-7 Wind Rose at Don Muang Meteorological Station __________________ 4.1-11
in the Year 2007
4.1.2-8 Percentage of Atmospheric Stability Class at ______________________ 4.1-13
Don Muang Meteorological Station in the Year 2007
4.1.2-9 Monitoring Results of 1-hr Average Concentration of Sulfur dioxide ___ 4.1-16
in Ambient Air during the Year 2005-2008,
Kao Noy Fire Fighting Station
4.1.2-10 Monitoring Results of 1-hr Average Concentration of Nitrogen dioxide _ 4.1-17
in Ambient Air during the Year 2005-2008,
Kao Noy Fire Fighting Station
4.1.2-11 Monitoring Results of 24-hr Average Concentration of PM-10 ________ 4.1-18
in Ambient Air during the Year 2005-2008,
Kao Noy Fire Fighting Station
4.1.2-12 Monitoring Location of Ambient Air Quality and Sound _____________ 4.1-19
Pressure Level around Nong-Saeng Power Plant Project
4.1.4-1 Geological Characteristic of the Study Area, _______________________ 4.1-29
Nong-Saeng Power Plant Project
T-EIA208102/SECOT (31) Table of Content.doc
LIST OF FIGURES (Cont’d) Figure Page
4.1.4-2 Map of Potential Areas of Sinking Holes in Thailand ________________ 4.1-30
4.1.4-3 Map of Potential Areas of Sinking Holes in Saraburi Province_________ 4.1-31
4.1.4-4 Map of Earthquake Risky Zones in Thailand_______________________ 4.1-33
4.1.4-5 Map of Fault Zones in Thailand _________________________________ 4.1-34
4.4.1-6 Map of Soil Series in the Study Area, ____________________________ 4.1-35
Nong-Saeng Power Plant Project
4.1.5-1 Surface Water Resources in the Study Area _______________________ 4.1-39
4.1.5-2 Map showing the Measuring Point of Current ______________________ 4.1-41
at the Water Pumping Point in Pa Sak River,
Nong-Saeng Power Plant Project
4.1.5-3 Hourly Water Level, Water Current Velocity, Temperature, __________ 4.1-44
Salinity, Suspended Solids at the Level of 0.2 of Water Depth
4.1.5-4 Hourly Water Level, Water Current Velocity, Temperature, ___________ 4.1-45
Salinity, Suspended Solids at the Level of 0.8 of Water Depth
4.1.5-5 25-Hour Average Values of Temperature, Salinity, _________________ 4.1-46
Suspended Solids, Water Current Velocity (u) in Flood Tide
and Ebb Tide Direction, Water Current Velocity along
Cross Section of Channel (v) at 11 Levels of Depth.
4.1.5-6 Cross Section of Klong Huaiba (Klong Nong-Ngu-Loem) in August, ___ 4.1-48
B.E.2551(Profile of Surveyed Water Level in Canal Bottom of Klong Huaiba)
4.1.5-7 Location of Surveyed Point of Water Current in Klong Huaiba ________ 4.1-49
(Klong Nong-Ngu-Loem) in August, B.E.2551
T-EIA208102/SECOT (32) Table of Content.doc
LIST OF FIGURES (Cont’d) Figure Page
4.1.5-8 Monitoring Station of Water Quality of the Office of Irrigation ________ 4.1-56
No. 10, Lopburi
4.1.5-9 Comparison of Water Quality of Pa-Sak River in Rama Six Dam Area ___ 4.1-60
4.1.5-10 Monitoring Station of Water Quality and Ecology ___________________ 4.1-63
4.1.5-11 Comparison of Water Quality in Klong Huaiba (Klong Nong-Ngu-Loem) _ 4.1-69
4.1.5-12 Water Sampling Stations of Klong Huaiba ________________________ 4.1-70
(Klong Nong-Ngu-Loem) in August B.E.2551
4.1.5-13 Physical Characteristics of Water Sampling Points __________________ 4.1-71
of Klong Huaiba Area (Klong Nong-Ngu-Loem)
in August B.E.2551
4.2.2-1 Wat Nong Sida Location where Flying Foxes were found, ____________ 4.2-22
Comparing to Nong-Saeng Power Plant Location
4.3.3-1 Zone Areas in the Radius of 5 km from Nong-Saeng __________________ 4.3-2
Power Plant Project
4.3.1-2 Land Use in the Study Area of 5 km. Radius of the Project area _________ 4.3-6
4.3.1-3 Project Area of Nong-Saeng Power Plant before Construction __________ 4.3-8
4.3.1-4 Land Use in the Study Area of 500 m Radius from __________________ 4.3-10
Water Pipeline, Nong-Saeng Power Plant Project
4.3.1-5 Location of Chicken Farm around the Project Site within 5 km. Radius _ 4.3-12
Power Generation Supply Co., Ltd.
4.3.1-6 Location of Mushroom Farm in Klong Huaiba Area ________________ 4.3-13
(Klong Nong-Ngu-Loem)
T-EIA208102/SECOT (33) Table of Content.doc
LIST OF FIGURES (Cont’d) Figure Page
4.3.2-1 Downstream of Irrigation Project Area in Water Pumping Area ________ 4.3-18
of Nong-Saeng Power Plant Project
4.3.2.2 Monthly Quantity of River Water at the Downstream ________________ 4.3-24
of Rama Six Dam and End of Phra Narain Water Gate
4.3.2-3 Water Level in Field at Various Levels ___________________________ 4.3-30
4.3.3-1 Traffic Routes to Nong-Saeng Power Plant Project __________________ 4.3-36
4.3.6.1 Flooded Area around Nong-Saeng Power Plant Project ______________ 4.3-57
in the Year B.E.2538 (1995)
4.3.6-2 Flooded Area around Nong-Saeng Power Plant Project ______________ 4.3-58
in the Year B.E.2545 (2002)
4.3.6-3 Flooded Area around Nong-Saeng power Plant Project ______________ 4.3-59
in the Year B.E.2549 (2006)
4.3.6-4 Repetitive Flooded Area around ________________________________ 4.3-60
Nong-Saeng Power Plant Project
4.3.6-5 Flooded Area in Sao Hai Irrigation Project in B.E.2549 (2006) ________ 4.3-61
4.3.6-6 Water Flow Direction in Sao Hai Irrigation Project _________________ 4.3-62
4.3.6-7 Water Flow Direction in Sao Hai Irrigation Project _________________ 4.3-63
4.4.1-1 The study Area and Location of the Communities _________________ 4.4.1-7
Surveyed for Socio-economic Status and Comments on
Nong-Saeng Power Plant Project
4.4.1-2 Distribution of Samples Surveyed for Socio-economic Status ________ 4.4.1-8
and Comments on Nong-Saeng Power Plant Project.
T-EIA208102/SECOT (34) Table of Content.doc
LIST OF FIGURES (Cont’d) Figure Page
5.1.1-1 Isopleths of Maximum 1-hr Average GLC of SO2 (g/m3) Resulting ____ 5.1-23
from Project Emission Sources In case of Natural Gas Firing and
100% Load Operation (Meteorological Data of the Year 2007)
5.1.1-2 Isopleths of Maximum 1-hr Average GLC of SO2 (g/m3) Resulting ____ 5.1-24
from the Project Emission Sources, In case of Diesel Oil Firing, and
100% Load Operation (Meteorological Data in Year 2007)
5.1.1.3 Isopleths of Maximum 1-hr Average GLC of SO2 (g/m3) Resulting ____ 5.1-25
from the Existing Emission Sources (Meteorological Data in Year 2007)
5.1.1-4 Isopleths of Maximum 1-hr Average GLC of SO2 (g/m3) Resulting ____ 5.1-27
from the Project Emission Sources and Existing Emission Sources.
In case of Natural Gas Firing and 100% Load Operation
(Meteorological Data in Year 2007)
5.1.1-5 Isopleths of Maximum 1-hr Average GLC of SO2 (g/m3) Resulting ____ 5.1-28
from the Project Emission Sources and Existing Sources. In case of
Diesel Firing and 100% Load Operation (Meteorological Data in Year 2007)
5.1.1-6 Isopleths of Maximum1-hr Average GLC of SO2 (g/m3) Resulting ____ 5.1-29
from the Project Emission Sources, Including Existing Sources
and Sources to be Developed in Future In case of Natural Gas Firing
and 100% Load Operation. (Meteorological Data of the Year 2007)
5.1.1-7 Isopleths of Maximum 1-hr Average GLC of SO2 (g/m3) Resulting ____ 5.1-30
from the Project Emission Sources, Including Existing Sources
and Sources to be Developed in Future In case of Diesel Oil Firing
and 100% Load Operation. (Meteorological Data in Year 2007)
T-EIA208102/SECOT (35) Table of Content.doc
LIST OF FIGURES (Cont’d) Figure Page
5.1.1-8 Isopleths of Maximum 1-hr Average GLC of NO2 (g/m3) Resulting ___ 5.1-33
from the Project Emission Sources, In case of Natural Gas Firing,
and 100% Load Operation. (Meteorological Data of the Year 2007)
5.1.1-9 Isopleths of Maximum 1-hr Average GLC of NO2 (g/m3) Resulting ___ 5.1-34
from the Project Emission Sources, In case of Diesel Oil Firing
and 100% Load Operation. (Meteorological Data of the Year 2007)
5.1.1-10 Isopleths of Maximum 1-hr Average GLC of NO2 (g/m3) Resulting ___ 5.1-36
from the Existing Emission Sources (Meteorological Data in Year 2007)
5.1.1-11 Isopleths of Maximum 1-hr Average GLC of NO2 (g/m3) Resulting ___ 5.1-37
from the Project Emission Sources, and Existing Emission Sources.
In case of Natural Gas Firing, and 100% Load Operating
(Meteorological Data in Year 2007)
5.1.1-12 Isopleths of Maximum 1-hr Average GLC of NO2 (g/m3) Resulting ___ 5.1-38
from the Project Emission Source, and Existing Emission Sources.
In case of Diesel Oil Firing, and 100% Load Operating
(Meteorological Data in Year 2007)
5.1.1-13 Isopleths of Maximum 1-hr Average GLC of NO2 (g/m3) Resulting ___ 5.1-41
from the Project Emission Sources, Including Existing Sources
and Sources to be Developed in Future In case of Natural Gas Firing
and 100% Load Operation. (Meteorological Data of the Year 2007)
5.1.1-14 Isopleths of Maximum 1-hr Average GLC of NO2 (g/m3) Resulting ___ 5.1-42
from the Project Emission Sources, Including Existing Sources
and Sources to be Developed in Future In case of Natural Gas Firing
and 100% Load Operation. (Meteorological Data of the Year 2007)
T-EIA208102/SECOT (36) Table of Content.doc
LIST OF FIGURES (Cont’d) Figure Page
5.1.1-15 Isopleths of Maximum 24-hr Average GLC of TSP (g/m3) Resulting __ 5.1-45
from the Project Emission Sources. In case of Natural Gas Firing
and 100% Load Operation (Meteorological Data of the Year 2007)
5.1.1-16 Isopleths of Maximum 24-hr Average GLC of TSP (g/m3) Resulting __ 5.1-46
from the Project Emission Sources, In case of Diesel Oil Firing,
and 100% Load Operation (Meteorological Data of the Year 2007)
5.1.1-17 Isopleths of Maximum 24-hr Average GLC of TSP (g/m3) Resulting __ 5.1-47
from the Existing Emission Sources (Meteorological Data in Year 2007)
5.1.1-18 Isopleths of Maximum 24-hr Average GLC of TSP (g/m3) Resulting __ 5.1-49
from the Project Emission Sources, In case of Natural Gas Firing,
and 100% Load Operation (Meteorological Data of the Year 2007)
5.1.1-19 Isopleths of Maximum 24-hr Average GLC of TSP (g/m3) Resulting __ 5.1-50
from the Project Emission Sources, In Case of Diesel Firing,
and 100% Load Operation. Including Existing Source
(Meteorological Data of the Year 2007)
5.1.1-20 Isopleths of Maximum 24-hr Average GLC of TSP (g/m3) Resulting __ 5.1-51
from the Project Source, In Case of Natural Gas Firing,
and 100% Load Operation Including Existing Source
and Source will be developed in future (Meteorological Data of the Year 2007)
5.1.1-21 Isopleths of Maximum 24-hr Average GLC of TSP (g/m3) __________ 5.1-52
Resulting from the Project Source, In Case of Diesel Oil Firing,
and 100% Load Operation. Including Existing Source
and Source will be developed in future (Meteorological Data of the Year 2007)
T-EIA208102/SECOT (37) Table of Content.doc
LIST OF FIGURES (Cont’d) Figure Page
5.1.2-1 Noise Contour around the Nong-Saeng Power Plant Project ___________ 5.1-65
during Construction Phase (Daytime Period)
5.1.2-2 Noise Contour around the Nong-Saeng Power Plant Project ___________ 5.1-66
during Construction Phase (Night-time Period)
5.1.2-3 Noise Contour around the Nong-Saeng Power Plant Project ___________ 5.1-70
during Operation Phase
5.1.2-4 Noise Contour around Production Process Area, ___________________ 5.1-71
Nong-Saeng Power Plant Project during Operation Phase
5.1.2-5 Location of Chicken Farm around Nong-Seang Power Plant Project ____ 5.1-74
in 2.1 km Radius Power Generation Supply Co., Ltd.
5.1.3-1 Klong Huaiba (Klong Nong-Ngu-Loem) __________________________ 5.1-81
into which Nong-Saeng Power Plant Project Drain Effluent,
and Location of Monthly River Water Analysis as a Result of Rainfall
5.3.6-1 Drainage Ditch Surrounding Project Area _________________________ 5.3-31
of Nong-Saeng Power Plant Project
during Construction and Operation Phase
5.3.6-2 Stormwater Management during Construction Phase ________________ 5.3-33
Nong-Saeng Power Plant Project
5.4.5-1 Natural Gas Pipeline, Location of Diesel Oil Storage Container ________ 5.4-33
and Diesel Oil Pipeline within Nong-Saeng Power Plant
5.4.5-2 Radius of Heat Impacts in case of Jet Fire Caused by ________________ 5.4-44
Natural Gas Leaked from PTT Metering Station to Gas Compressor of
Nong-Saeng Power Plant Unit 1 from 100 % Rapture Pipeline in F-Class
(S-1L 100% 1.5/F) of Atmospheric Stability PPT Metering Station Area
T-EIA208102/SECOT (38) Table of Content.doc
LIST OF FIGURES (Cont’d) Figure Page
5.4.5-3 Radius of Heat Impacts in case of Jet Fire Caused by ________________ 5.4-44
Natural Gas Leaked from PTT Metering Station to Gas Compressor of
Nong-Saeng Power Plant Unit 1 from 100 % Rapture Pipeline in F-Class
(S-1L 100% 1.5/F) of Atmospheric Stability
Gas Compressor of Nong-Saeng Power Plant Unit 1 Area
5.4.5-4 Radius of Heat Impacts in case of Flash Fire Caused by ______________ 5.4-45
Natural Gas Leaked from PTT Metering Station to Gas Compressor of
Nong-Saeng Power Plant Unit 1 from 100 % Rapture Pipeline in D-Class
(S-1L 100% 5D) of Atmospheric Stability PPT Metering Station Area
5.4.5-5 Radius of Heat Impacts in case of Flash Fire Caused by ______________ 5.4-45
Natural Gas Leaked from PTT Metering Station to Gas Compressor of
Nong-Saeng Power Plant Unit 1 from 100 % Rapture Pipeline in D-Class
(S-1L 100% 5D) of Atmospheric Stability
Gas Compressor of Nong-Saeng Power Plant Unit 1 Area
5.4.5-6 Radius of Heat Impacts in case of Jet Fire Caused by _______________ 5..4-47
Natural Gas Leaked from PTT Metering Station to Gas Compressor of
Nong-Saeng Power Plant Unit 2 from 100 % Rapture Pipeline in F-Class
(S-2L 100% 1.5/F) of Atmospheric Stability PPT Metering Station Area
5.4.5-7 Radius of Heat Impacts in case of Jet Fire Caused by ________________ 5.4-47
Natural Gas Leaked from PTT Metering Station to Gas Compressor of
Nong-Saeng Power Plant Unit 2 from 100 % Rapture Pipeline in F-Class
(S-2L 100% 1.5/F) of Atmospheric Stability
Gas Compressor of Nong Saeng Power Plant Unit 1 Area
T-EIA208102/SECOT (39) Table of Content.doc
LIST OF FIGURES (Cont’d) Figure Page
5.4.5-8 Radius of Heat Impacts in case of Flash Fire Caused by ______________ 5.4-48
Natural Gas Leaked from PTT Metering Station to Gas Compressor of
Nong-Saeng Power Plant Unit 2 from 100 % Rapture Pipeline in D-Class
(S-2L 100% 5D) of Atmospheric Stability PPT Metering Station Area
5.4.5-9 Radius of Heat Impacts in case of Flash Fire Caused by ______________ 5.4-48
Natural Gas Leaked from PTT Metering Station to Gas Compressor of
Nong-Saeng Power Plant Unit 2 from 100 % Rapture Pipeline in D-Class
(S-2L 100% 5D) of Atmospheric Stability
Gas Compressor of Nong Saeng Power Plant Unit 2 Area
5.4.5-10 Radius of Heat Impacts in case of Jet Fire Caused by ________________ 5.4-50
Natural Gas Leaked from Gas Compressor of Nong-Saeng Power Plant _ Unit 1
to Gas Turbine 1 of Nong-Saeng Power Plant Unit 1 from 100 %
Rupture Pipeline in F-Class (S-3L 100% 1.5/F) of Atmospheric Stability
Gas Compressor of Nong-Saeng Power Plant Unit 1 Area
5.4.5-11 Radius of Heat Impacts in case of Jet Fire Caused by ________________ 5.4-50
Natural Gas Leaked from Gas Compressor of Nong Saeng Power Plant _ Unit 1
to Gas Turbine 1 of Nong Saeng Power Plant Unit 1 from 100 % Rupture Pipeline
in F-Class (S-3L 100% 1.5/F) of Atmospheric Stability
Gas Turbine 1 of Nong Saeng Power Plant Unit 1 Area
5.4.5-12 Radius of Heat Impacts in case of Flash Fire Caused by ______________ 5.4-51
Natural Gas Leaked from Gas Compressor of Nong-Saeng Power Plant _ Unit 1
to Gas Turbine 1 of Nong-Saeng Power Plant Unit 1 from 100 % Rupture Pipeline
in D-Class (S-3L 100% 5D) of Atmospheric Stability
Gas Compressor of Nong-Saeng Power Plant Unit 1 Area
T-EIA208102/SECOT (40) Table of Content.doc
LIST OF FIGURES (Cont’d) Figure Page
5.4.5-13 Radius of Heat Impacts in case of Flash Fire Caused by ______________ 5.4-51
Natural Gas Leaked from Gas Compressor of Nong-Saeng Power Plant _ Unit 1
to Gas Turbine 1 of Nong-Saeng Power Plant Unit 1 from 100 % Rupture Pipeline
in D-Class (S-3L 100% 5D) of Atmospheric Stability
Gas Turbine 1 of Nong-Saeng Power Plant Unit 1 Area
5.4.5-14 Radius of Heat Impacts in case of Jet Fire Caused by ________________ 5.4-53
Natural Gas Leaked from Gas Compressor of Nong-Saeng Power Plant _ Unit 1
to Gas Turbine 2 of Nong-Saeng Power Plant Unit 1 from 100 % Rupture Pipeline
in F-Class (S-4L 100% 1.5/F) of Atmospheric Stability
Gas Compressor of Nong-Saeng Power Plant Unit 1 Area
5.4.5-15 Radius of Heat Impacts in case of Jet Fire Caused by ________________ 5.4-53
Natural Gas Leaked from Gas Compressor of Nong-Saeng Power Plant Unit 1
to Gas Turbine 2 of Nong-Saeng Power Plant Unit 1 from 100 % Rupture Pipeline
in F-Class (S-4L 100% 1.5/F) of Atmospheric Stability
Gas Turbine 2 of Nong-Saeng Power Plant Unit 1 Area
5.4.5-16 Radius of Heat Impacts in case of Flash Fire Caused by ______________ 5.4-54
Natural Gas Leaked from Gas Compressor of Nong Saeng Power Plant Unit 1
to Gas Turbine 2 of Nong Saeng Power Plant Unit 1 from 100 % Rupture Pipeline
in D-Class (S-4L 100% 5D) of Atmospheric Stability
Gas Compressor of Nong Saeng Power Plant Unit 1 Area
5.4.5-17 Radius of Heat Impacts in case of Flash Fire Caused by ______________ 5.4-54
Natural Gas Leaked from Gas Compressor of Nong-Saeng Power Plant Unit 1
to Gas Turbine 2 of Nong-Saeng Power Plant Unit 1 from 100 % Rupture Pipeline
in D-Class (S-4L 100% 5D) of Atmospheric Stability
Gas Turbine 2 of Nong-Saeng Power Plant Unit 1 Area
T-EIA208102/SECOT (41) Table of Content.doc
LIST OF FIGURES (Cont’d) Figure Page
5.4.5-18 Radius of Heat Impacts in case of Jet Fire Caused by ________________ 5.4-55
Natural Gas Leaked from Gas Compressor of Nong-Saeng Power Plant _ Unit 2
to Gas Turbine 1 of Nong-Saeng Power Plant Unit 2 from 100 % Rupture Pipeline
in F-Class (S-5L 100% 1.5/F) of Atmospheric Stability
Gas Compressor of Nong-Saeng Power Plant Unit 2 Area
5.4.5-19 Radius of Heat Impacts in case of Jet Fire Caused by ________________ 5.4-55
Natural Gas Leaked from Gas Compressor of Nong-Saeng Power Plant Unit 2
to Gas Turbine 1 of Nong-Saeng Power Plant Unit 2 from 100 % Rupture Pipeline
in F-Class (S-5L 100% 1.5/F) of Atmospheric Stability
5.4.5-20 Radius of Heat Impacts in case of Flash Fire Caused by ______________ 5.4-56
Natural Gas Leaked from Gas Compressor of Nong-Saeng Power Plant _ Unit 2
to Gas Turbine 1 of Nong-Saeng Power Plant Unit 2 from 100 % Rupture Pipeline
in D-Class (S-5L 100% 5D) of Atmospheric Stability
Gas Compressor of Nong-Saeng Power Plant Unit 2 Area
5.4.5-21 Radius of Heat Impacts in case of Flash Fire Caused by ______________ 5.4-56
Natural Gas Leaked from Gas Compressor of Nong-Saeng Power Plant Unit 2
to Gas Turbine 1 of Nong-Saeng Power Plant Unit 2 from 100 % Rupture Pipeline
in D-Class (S-5L 100% 5D) of Atmospheric Stability
Gas Turbine 1 of Nong-Saeng Power Plant Unit 2 Area
5.4.5-22 Radius of Heat Impacts in case of Jet Fire Caused by ________________ 5.4-58
Natural Gas Leaked from Gas Compressor of Nong-Saeng Power Plant Unit 2
to Gas Turbine 2 of Nong-Saeng Power Plant Unit 2 from 100 % Rupture Pipeline
in F-Class (S-6L 100% 1.5/F) of Atmospheric Stability
Gas Compressor of Nong-Saeng Power Plant Unit 2 Area
T-EIA208102/SECOT (42) Table of Content.doc
LIST OF FIGURES (Cont’d) Figure Page
5.4.5-23 Radius of Heat Impacts in case of Jet Fire Caused by ________________ 5.4-58
Natural Gas Leaked from Gas Compressor of Nong-Saeng Power Plant Unit 2
to Gas Turbine 2 of Nong-Saeng Power Plant Unit 2 from 100 % Rupture Pipeline
in F-Class (S-6L 100% 1.5/F) of Atmospheric Stability
Gas Turbine 2 of Nong-Saeng Power Plant Unit 2 Area
5.4.5-24 Radius of Heat Impacts in case of Flash Fire Caused by ______________ 5.4-59
Natural Gas Leaked from Gas Compressor of Nong-Saeng Power Plant Unit 2
to Gas Turbine 2 of Nong-Saeng Power Plant Unit 2 from 100 % Rupture Pipeline
in D-Class (S-6L 100% 5D) of Atmospheric Stability
Gas Compressor of Nong-Saeng Power Plant Unit 2 Area
5.4.5-25 Radius of Heat Impacts in case of Flash Fire Caused by _____________ 5.4-59
Natural Gas Leaked from Gas Compressor of Nong-Saeng Power Plant _ Unit 2
to Gas Turbine 2 of Nong-Saeng Power Plant Unit 2 from 100 % Rupture Pipeline
in D-Class (S-6L 100% 5D) of Atmospheric Stability
Gas Turbine 2 of Nong-Saeng Power Plant Unit 2 Area
5.4.5-26 Radius of Heat Impacts in case of Jet Fire Caused by ________________ 5.4-61
Diesel Oil Leaked from Diesel Oil Pipeline to Gas Turbine 1
of Nong-Saeng Power Plant Unit 1 from 100 % Rupture Pipeline
in F-Class (S-7L 100% 1.5/F) of Atmospheric Stability
Diesel Oil Storage Tank Area
5.4.5-27 Radius of Heat Impacts in case of Jet Fire Caused by ________________ 5.4-61
Diesel Oil Leaked from Diesel Oil Pipeline to Gas Turbine 1
of Nong-Saeng Power Plant Unit 1 from 100 % Rupture Pipeline
in D-Class (S-7L 100% 5D) of Atmospheric Stability
Gas Turbine 1 of Nong-Saeng Power Plant Unit 1 Area
T-EIA208102/SECOT (43) Table of Content.doc
LIST OF FIGURES (Cont’d) Figure Page
5.4.5-28 Radius of Heat Impacts in case of Pool Fire Caused by ______________ 5.4-62
Diesel Oil Leaked from Diesel Oil Pipeline to Gas Turbine 1
of Nong-Saeng Power Plant Unit 1 from 100 % Rupture Pipeline
in D-Class (S-7L 100% 5D) of Atmospheric Stability
Diesel Oil Storage Tank Area
5.4.5-29 Radius of Heat Impacts in case of Pool Fire Caused by ______________ 5.4-62
Diesel Oil Leaked from Diesel Oil Pipeline of Diesel Oil Storage Tank to
Gas Turbine 1 of Nong-Saeng Power Plant Unit 1 from 100 % Rupture Pipeline
in D-Class (S-7L 100% 5D) of Atmospheric Stability
Gas Turbine 1 of Nong-Saeng Power Plant Unit 1 Area
5.4.5-30 Radius of Heat Impacts in case of Flash Fire Caused by ______________ 5.4-63
Diesel Oil Leaked from Diesel Oil Pipeline to Gas Turbine 1
of Nong-Saeng Power Plant Unit 1 from 100 % Rupture Pipeline
in F-Class (S-7L 100% 1.5/F) of Atmospheric Stability
Diesel Oil Storage Tank Area
5.4.5-31 Radius of Heat Impacts in case of Flash Fire Caused by ______________ 5.4-63
Diesel Oil Leaked from Diesel Oil Pipeline of Diesel Oil Storage Tank
to Gas Turbine 1 of Nong-Saeng Power Plant Unit 1 from 100 %
Rupture Pipeline in F-Class (S-7L 100% 1.5/F) of Atmospheric Stability
Gas Turbine 1 of Nong-Saeng Power Plant Unit 1 Area
5.4.5-32 Radius of Heat Impacts in case of Jet Fire Caused by ________________ 5.4-65
Diesel Oil Leaked from Diesel Oil Pipeline of Diesel Oil Storage Tank
to Gas Turbine 2 of Nong-Saeng Power Plant Unit 1 from 100 %
Rupture Pipeline in D-Class (S-8L 100% 5D) of Atmospheric Stability
Diesel Oil Storage Tank Area
T-EIA208102/SECOT (44) Table of Content.doc
LIST OF FIGURES (Cont’d) Figure Page
5.4.5-33 Radius of Heat Impacts in case of Jet Fire Caused by ________________ 5.4-65
Diesel Oil Leaked from Diesel Oil Pipeline to Gas Turbine 2
of Nong-Saeng Power Plant Unit 1 from 100 % Rupture Pipeline
in D-Class (S-8L 100% 5D) of Atmospheric Stability
Gas Turbine 2 of Nong-Saeng Power Plant Unit 1 Area
5.4.5-34 Radius of Heat Impacts in case of Pool Fire Caused by ______________ 5.4-66
Diesel Oil Leaked from Diesel Oil Pipeline of Diesel Oil Storage Tank
to Gas Turbine 2 of Nong-Saeng Power Plant Unit 1 from 100 % Rupture Pipeline
in D-Class (S-8L 100% 5D) of Atmospheric Stability
Diesel Oil Storage Tank Area
5.4.5-35 Radius of Heat Impacts in case of Pool Fire Caused by ______________ 5.4-66
Diesel Oil Leaked from Diesel Oil Pipeline of Diesel Oil Storage Tank
to Gas Turbine 2 of Nong-Saeng Power Plant Unit 1 from 100 % Rupture Pipeline
in D-Class (S-8L 100% 5D) of Atmospheric Stability
Gas Turbine 2 of Nong-Saeng Power Plant Unit 1 Area
5.4.5-36 Radius of Heat Impacts in case of Flash Fire Caused by ______________ 5.4-67
Diesel Oil Leaked from Diesel Oil Pipeline of Diesel Oil Storage Tank
to Gas Turbine 2 of Nong-Saeng Power Plant Unit 1 from 100 %
Rupture Pipeline in F-Class (S-8L 100% 1.5/F) of Atmospheric Stability
Diesel Oil Storage Tank Area
5.4.5-37 Radius of Heat Impacts in case of Flash Fire Caused by _____________ 5.4-67
Diesel Oil Leaked from Diesel Oil Pipeline of Diesel Oil Storage Tank
to Gas Turbine 2 of Nong-Saeng Power Plant Unit 1 from 100 % Rupture Pipeline
in F-Class (S-8L 100% 1.5/F) of Atmospheric Stability
Gas Turbine 2 of Nong-Saeng Power Plant Unit 1 Area
T-EIA208102/SECOT (45) Table of Content.doc
LIST OF FIGURES (Cont’d) Figure Page
5.4.5-38 Radius of Heat Impacts in case of Jet Fire Caused by ________________ 5.4-69
Diesel Oil Leaked from Diesel Oil Pipeline of Diesel Oil Storage Tank
to Gas Turbine 1 of Nong-Saeng Power Plant Unit 2 from 100 % Rupture Pipeline
in D-Class (S-9L 100% 5D) of Atmospheric Stability
Diesel Oil Storage Tank Area
5.4.5-39 Radius of Heat Impacts in case of Jet Fire Caused by ________________ 5.4-69
Diesel Oil Leaked from Diesel Oil Pipeline of Diesel Oil Storage Tank
to Gas Turbine 1 of Nong-Saeng Power Plant Unit 2 from 100 %
Rupture Pipeline in D-Class (S-9L 100% 5D) of Atmospheric Stability
Gas Turbine 1 of Nong-Saeng Power Plant Unit 2 Area
5.4.5-40 Radius of Heat Impacts in case of Pool Fire Caused by ______________ 5.4-70
Diesel Oil Leaked from Diesel Oil Pipeline of Diesel Oil Storage Tank
to Gas Turbine 1 of Nong Saeng Power Plant Unit 2 from 100 %
Rupture Pipeline in D-Class (S-9L 100% 5D) of Atmospheric Stability
Diesel Oil Storage Tank Area
5.4.5-41 Radius of Heat Impacts in case of Pool Fire Caused by ______________ 5.4-70
Diesel Oil Leaked from Diesel Oil Pipeline of Diesel Oil Storage Tank
to Gas Turbine 1 of Nong-Saeng Power Plant Unit 2 from 100 % Rupture Pipeline
in D-Class (S-9L 100% 5D) of Atmospheric Stability
Gas Turbine 1 of Nong-Saeng Power Plant Unit 2 Area
5.4.5-42 Radius of Heat Impacts in case of Flash Fire Caused by _____________ 5.4-71
Diesel Oil Leaked from Diesel Oil Pipeline of Diesel Oil Storage Tank ______
to Gas Turbine 1 of Nong-Saeng Power Plant Unit 2 from 100 % Rupture Pipeline
in F-Class (S-9L 100% 1.5/F) of Atmospheric Stability
Diesel Oil Storage Tank Area
T-EIA208102/SECOT (46) Table of Content.doc
LIST OF FIGURES (Cont’d) Figure Page
5.4.5-43 Radius of Heat Impacts in case of Flash Fire Caused by ______________ 5.4-71
Diesel Oil Leaked from Diesel Oil Pipeline of Diesel Oil Storage Tank
to Gas Turbine 1 of Nong-Saeng Power Plant Unit 2 from 100 %
Rupture Pipeline in F-Class (S-9L 100% 1.5/F) of Atmospheric Stability
Gas Turbine 1 of Nong-Saeng Power Plant Unit 2 Area
5.4.5-44 Radius of Heat Impacts in case of Jet Fire Caused by ________________ 5.4-73
Diesel Oil Leaked from Diesel Oil Pipeline of Diesel Oil Storage Tank
to Gas Turbine 2 of Nong-Saeng Power Plant Unit 2 from 100 % Rupture Pipeline
in D-Class (S-10L 100% 5D) of Atmospheric Stability
Diesel Oil Storage Tank Area
5.4.5-45 Radius of Heat Impacts in case of Jet Fire Caused by ________________ 5.4-73
Diesel Oil Leaked from Diesel Oil Pipeline of Diesel Oil Storage Tank
to Gas Turbine 2 of Nong-Saeng Power Plant Unit 2 from 100 % Rupture Pipeline
in D-Class (S-10L 100% 5D) of Atmospheric Stability
Gas Turbine 2 of Nong-Saeng Power Plant Unit 2 Area
5.4.5-46 Radius of Heat Impacts in case of Pool Fire Caused by ______________ 5.4-74
Diesel Oil Leaked from Diesel Oil Pipeline of Diesel Oil Storage Tank
to Gas Turbine 2 of Nong-Saeng Power Plant Unit 2 from 100 %
Rupture Pipeline in D-Class (S-10L 100% 5D) of Atmospheric Stability
Diesel Oil Storage Tank Area
5.4.5-47 Radius of Heat Impacts in case of Pool Fire Caused by ______________ 5.4-74
Diesel Oil Leaked from Diesel Oil Pipeline of Diesel Oil Storage Tank
to Gas Turbine 2 of Nong-Saeng Power Plant Unit 2 from 100 %
Rupture Pipeline in D-Class (S-10L 100% 5D) of Atmospheric Stability
Gas Turbine 2 of Nong-Saeng Power Plant Unit 2 Area
T-EIA208102/SECOT (47) Table of Content.doc
LIST OF FIGURES (Cont’d) Figure Page
5.4.5-48 Radius of Heat Impacts in case of Flash Fire Caused by ____________ 5.4.5-75
Diesel Oil Leaked from Diesel Oil Pipeline of Diesel Oil Storage Tank
to Gas Turbine 2 of Nong-Saeng Power Plant Unit 2 from 100 %
Rupture Pipeline in F-Class (S-10L 100% 1.5/F) of Atmospheric Stability
Diesel Oil Storage Tank Area
5.4.5-49 Radius of Heat Impacts in case of Flash Fire Caused by ______________ 5.4-75
Diesel Oil Leaked from Diesel Oil Pipeline of Diesel Oil Storage Tank
to Gas Turbine 2 of Nong-Saeng Power Plant Unit 2 from 100 %
Rupture Pipeline in F-Class (S-10L 100% 1.5/F) of Atmospheric Stability
Gas Turbine 2 of Nong-Saeng Power Plant Unit 2 Area
5.4.5-50 Radius of Heat Impacts in case of Jet Fire Caused by ________________ 5.4-81
Diesel Oil Leaked from Diesel Oil Pipeline of Diesel Oil Storage Tank
to Gas Turbine 1 of Nong-Saeng Power Plant Unit 1
(In Case of Control Valve Failure) from 100 % Rapture Pipeline in F-Class
(S-17L 100% 1.5/F) of Atmospheric Stability
Diesel Oil Storage Tank Area
5.4.5-51 Radius of Heat Impacts in case of Jet Fire Caused by ________________ 5.4-81
Diesel Oil Leaked from Diesel Oil Pipeline of Diesel Oil Storage Tank
to Gas Turbine 1 of Nong Saeng Power Plant Unit 1
(In Case of Control Valve Failure) from 100 % Rapture Pipeline in F-Class
(S-17L 100% 1.5/F) of Atmospheric Stability
Gas Turbine 1 of Nong Saeng Power Plant Unit 1 Area
T-EIA208102/SECOT (48) Table of Content.doc
LIST OF FIGURES (Cont’d) Figure Page
5.4.5-52 Radius of Heat Impacts in case of Jet Fire Caused by ________________ 5.4-83
Diesel Oil Leaked from Diesel Oil Pipeline of Diesel Oil Storage Tank
to Gas Turbine 2 of Nong-Saeng Power Plant Unit 1
(In Case of Control Valve Failure) from 100 % Rapture Pipeline in F-Class
(S-18L 100% 1.5/F) of Atmospheric Stability
Diesel Oil Storage Tank Area
5.4.5-53 Radius of Heat Impacts in case of Jet Fire Caused by ________________ 5.4-83
Diesel Oil Leaked from Diesel Oil Pipeline of Diesel Oil Storage Tank
to Gas Turbine 2 of Nong-Saeng Power Plant Unit 1
(In Case of Control Valve Failure) from 100 % Rapture Pipeline in F-Class
(S-18L 100% 1.5/F) of Atmospheric Stability
Gas Turbine 2 of Nong-Saeng Power Plant Unit 1 Area
5.4.5-54 Radius of Heat Impacts in case of Jet Fire Caused by ________________ 5.4-85
Diesel Oil Leaked from Diesel Oil Pipeline of Diesel Oil Storage Tank
to Gas Turbine 1 of Nong-Saeng Power Plant Unit 2
(In Case of Control Valve Failure) from 100 % Rapture Pipeline in D-Class
(S-19L 100% 5D) of Atmospheric Stability
Diesel Oil Storage Tank Area
5.4.5-55 Radius of Heat Impacts in case of Jet Fire Caused by ________________ 5.4-85
Diesel Oil Leaked from Diesel Oil Pipeline of Diesel Oil Storage Tank
to Gas Turbine 1 of Nong-Saeng Power Plant Unit 2
(In Case of Control Valve Failure) from 100 % Rapture Pipeline in D-Class
(S-19L 100% 5D) of Atmospheric Stability
Gas Turbine 1 of Nong-Saeng Power Plant Unit 2 Area
T-EIA208102/SECOT (49) Table of Content.doc
LIST OF FIGURES (Cont’d) Figure Page
5.4.5-56 Radius of Heat Impacts in case of Jet Fire Caused by ________________ 5.4-87
Diesel Oil Leaked from Diesel Oil Pipeline of Diesel Oil Storage Tank
to Gas Turbine 2 of Nong-Saeng Power Plant Unit 2
(In Case of Control Valve Failure) from 100 % Rapture Pipeline in D-Class
(S-20L 100% 5D) of Atmospheric Stability
Diesel Oil Storage Tank Area
5.4.5-57 Radius of Heat Impacts in case of Jet Fire Caused by ________________ 5.4-87
Diesel Oil Leaked from Diesel Oil Pipeline of Diesel Oil Storage Tank
to Gas Turbine 2 of Nong-Saeng Power Plant Unit 2
(In Case of Control Valve Failure) from 100 % Rapture Pipeline in D-Class
(S-20L 100% 5D) of Atmospheric Stability
Gas Turbine 2 of Nong Saeng Power Plant Unit 2 Area
5.4.5-58 Radius of Heat Impacts in case of Pool Fire Caused by ______________ 5.4-89
Diesel Oil Leaked from Diesel Oil Storage Tank No. 1
in D-Class (S-1T 100% 5D) of Atmospheric Stability
5.4.5-59 Radius of Heat Impacts in case of Flash Fire Caused by ______________ 5.4-89
Diesel Oil Leaked from Diesel Oil Storage Tank No. 1
in F-Class (S-1T 100% 1.5/F) of Atmospheric Stability
5.4.5-60 Radius of Heat Impacts in case of Pool Fire Caused by ______________ 5.4-90
Diesel Oil Leakage from Diesel Oil Storage Tank No. 2
in D-Class (S-2T 100% 5D) of Atmospheric Stability
5.4.5-61 Radius of Heat Impacts in case of Flash Fire Caused by _____________ 5.4-90
Diesel Oil Leakage from Diesel Oil Storage Tank No. 2
in F-Class (S-2T 100% 1.5/F) of Atmospheric Stability
T-EIA208102/SECOT (50) Table of Content.doc
LIST OF FIGURES (Cont’d) Figure Page
8-1 Chart of the general complaints ___________________________________ 8-2
8-2 Chart of the emergency complaints ________________________________ 8-3
Environmental Report for submittal to ADB Nong-Saeng Power Plant Project Chapter 1 Power Generation Supply Co., Ltd. Executive Summary
T-EIA208102 1-1 F208102-Chap1E-ADB
Chapter 1
Executive Summary The Nong-Saeng Power Plant Project of Power Generation Supply Co., Ltd. is
located in an area of approximately 570 rai which is allocated into 2 portions i.e. a power
plant area of approximately 300 rai in Moo 4 of Ban Huaiba, Nong-Kob Sub-district,
Nong-Saeng District of Saraburi Province; and a reservoir area of approximately 270 rai in
Moo 7 of Ban Thamsinthusopa, Nong-Namsai Sub-district, and Moo 2 of Ban Klong,
Khok Muang Sub-district of Pachee District of Phra Nakhon Si Ayutthaya Province. The
proposed Nong-Saeng Power Plant will utilize natural gas as main fuel and diesel oil as
backup fuel. The total installed capacity of this power plant, comprising two 826.6-MW
blocks of combined cycle facilities, is approximately 1,653 MW. About 1,600 MW of the
electricity to be generated will be sold to the Electricity Generating Authority of Thailand
(EGAT) while the remaining 53 MW will be used in-house. The main components of the
proposed power plant include four combustion turbine generators (CTG), four heat
recovery steam generators (HRSG) and two steam turbine generators (STG). The
generated electricity to be sold to EGAT will be dispatched via the 500 kV Pachee Sub-
station and the transmission line connecting to EGAT’s Tatakoe-Wangnoi transmission
line. The natural gas for the project to be supplied by PTT (Public) Co., Ltd. is
approximately 265.18 million cubic feet per day and the diesel oil supply is approximately
6.594 million liters per day. The raw water will be pumped from the Pa-Sak River at
upstream of the Phra Rama Six Dam and stored in the 1,600,000-cubic meter reservoir
before use. The wastewater generated by the project will be treated and reused, and the
effluent discharged from the cooling tower (the only discharge effluent) will be drained
into the holding pond before discharging into Klong Huaiba (Klong Ngu-Loem).
The Analysis of alternatives for the project included the consideration of three
alternative sites i.e. the project site, Nong-Namsai and KK2 Power Plant along with three
major alternatives i.e. alternative fuel, alternative plant location and alternative electricity
generating technology. The key issues considered in the analysis consisted of both
engineering and environmental aspects including the distances from fuel source,
transmission line, water resource, and the stability of water supply source, land needed to
Environmental Report for submittal to ADB Nong-Saeng Power Plant Project Chapter 1 Power Generation Supply Co., Ltd. Executive Summary
T-EIA208102 1-2 F208102-Chap1E-ADB
be covered with soil, land access; and impacts on communities, air quality, water usage,
water quality and agriculture land, and conflict relating to the use of land. Based on this
analysis of alternatives, the project site was selected for the proposed power plant
development.
The Nong-Saeng Power Plant Project is subject to the requirements on the
preparation and submission of the EIA report to ONEP for review and approval (under the
Notifications of the Ministry of Science, Technology and Environment of August 24, 1992,
and No. 2 of 1992 and No. 3 of 1996). Therefore the project contracted SECOT to conduct
the required EIA study. The study must follow ONEP guidelines which also include the
requirements to have the EIA study report to include the results and documents showing
the compliance with the rules/regulations of other relevant government offices.
The results (including the summarized key environmental & social baseline
data/related activities, anticipated impacts and associated mitigative measures) and
recommendations derived from the EIA study are presented in brief as follows:
1.1 Air Quality
The main air quality impacts potentially resulted from the Nong-Saeng Power
Plant Project during the construction and operation periods will include the adverse effects
from dust dispersion during the construction phase and stack emissions during the
operation phase.
During the construction phase of the project anticipated to take 40 months,
most of the construction activities will include land preparation and construction of
foundation, transportation of construction materials, and motor vehicles entering and
exiting the project area. The project-induced dust to be generated during this period will be
rather large sizes. Thus the Nong-Saeng Power Plant Project has established suitable
environmental impact mitigation measures to cope with the fugitive dust problem during
the construction phase.
During the operation phase, the air quality impact will result from the
operation of the proposed Nong-Saeng Power Plant which will use natural gas as main fuel
and diesel oil as backup fuel to generate the electricity. The combustion of these fuels will
generate major air pollutants including primarily sulfur dioxide (SO2), oxides of nitrogen
(NOx) and particulate matters (PM) which will be emitted into the atmosphere. The air
quality impact assessment using the AERMOD model with the meteorological input data of
Environmental Report for submittal to ADB Nong-Saeng Power Plant Project Chapter 1 Power Generation Supply Co., Ltd. Executive Summary
T-EIA208102 1-3 F208102-Chap1E-ADB
the year 2007 indicated that all of the predicted SO2 concentrations resulting from the
emission sources of the project in case of natural gas firing at all operating loads (100%,
80%, 58% and start-up & shutdown) complied with the National Ambient Air Quality
Standards for the hourly, 24-hour and annual average concentrations of sulfur dioxide of
780, 300 and 100 micrograms per cubic meter respectively (under the Notification of the
National Environment Board, No.21 (2001) and No.24 (2004)). In case of diesel oil
firing, the modeling results also indicated that all of the predicted SO2 concentrations at all
operating loads were within the applicable standards for the hourly, 24-hour and annual
average concentrations of sulfur dioxide.
The estimated maximum hourly average concentrations of nitrogen dioxide in
the ambient air resulting from the emission sources of the project, in case of natural gas or
diesel oil firing at all operating loads and applying the NO2/NOx ratio of 0.75, were within
the applicable standard of 320 micrograms per cubic meter (under the Notification of the
National Environment Board, No.10 (1995)).
The estimated maximum 24-hour and annual average ambient particulate
concentrations resulting from the emission sources of the project with natural gas or diesel
oil firing at all operating loads were within the applicable standards of 330 and 100
micrograms per cubic meter for 24-hour and annual average concentrations respectively
(under the Notification of the National Environment Board, No.24 (2004)).
Accordingly, the potential impact is considered to be non-significant.
1.2 Noise Level
During the construction phase of the proposed Nong-Saeng Power Plant, the
noise sources of the project will include the equipment/machinery with the maximum
sound pressure levels at a distance of 15 meters assigned to be 101 dB(A) and 85 dB(A)
for the daytime and nighttime respectively. However, the noise levels at these noise
sources of the project will be reduced by enclosing the concerned areas with iron or zinc
sheets of at least 1.3 mm. in thickness. This will result in a reduction of noise level from
noise sources by about 25 dB(A). (Reference : FHWA (Federal Highway Administration)
U.S.A., 2006). Therefore the maximum sound pressure levels at such a distance during the
construction phase after installing the iron or zinc sheets are anticipated to be 76 dB(A)
and 60 dB(A) for the daytime and night-time respectively. The noise impact was
determined using the Decay Formula Equation. From the noise impact assessment, it was
Environmental Report for submittal to ADB Nong-Saeng Power Plant Project Chapter 1 Power Generation Supply Co., Ltd. Executive Summary
T-EIA208102 1-4 F208102-Chap1E-ADB
found that the noise levels in the plant vicinity areas at the 500-m, 1-km, 2-km and 3-km
radii during the daytime and night-time were rather low compared with the applicable
standards and the impacts of the sound pressure levels from the project decreased
according to the distance from the construction area. The assessment results indicated that
the communities nearby the project area including Wat Thamsinthusopa, Wat Nong-
Tangbun, Wat Khok Muang and Wat Nongkratart would expose to rather low noise levels
from the project during both daytime and nighttime. All estimated sound pressure levels
were below the standard of 70 dB(A) under the Notification of the National Environment
Board No.15 (B.E.2540). The noise levels generated from the project were used to estimate
the annoying noise level which was found to be below the standard of 10 dB(A) under the
Notification of National Environment Board No.29 (B.E.2550).
During the operation phase, the communities nearby the project area (Wat
Thamsinthusopa, Wat Nong-Tangbun, Wat Kok Muang and Wat Nongkratart) would
expose to low noise levels from the project. The estimated sound pressure levels were also
found to be below the standard of 70 dB(A) under the Notification of the National
Environment Board No.15 (B.E.2540). Thus the impact of annoying noise level on the
nearby communities were found to be nil during both daytime and night-time.
Therefore the potential noise impact is considered to be low.
1.3 Surface Water Hydrology and Surface Water Quality
The activities of the proposed power plant can potentially induce an impact on the quality of surface water resources outside the project area during both the construction and operation phases. During the construction phase, two major sources of wastewater will include the wastewater from the contractor(s) and construction workers. The sanitary wastewater to be generated from the construction workers will be drained into septic tanks and then retained in the sumps for later uses such as spraying over the construction area and other vacant areas of the project to suppress dust dispersion without discharging any effluent to the outside. In addition, the storm water may wash away the sediments from the construction area into the outside water resources. Hence the project has prepared the mitigative measures by requiring the storm water to be drained into a temporary sump to let the sediments settle and then the clear water from the sump will be separated for various uses in the construction area and activities, and subsequently drained into the receiving water resources outside the project area.
Environmental Report for submittal to ADB Nong-Saeng Power Plant Project Chapter 1 Power Generation Supply Co., Ltd. Executive Summary
T-EIA208102 1-5 F208102-Chap1E-ADB
During the operation phase, the project will utilize the water from the Pa-Sak River by pumping the water from the river at a rate of 46,932 cubic meters per day when using natural gas as fuel and 38,518 cubic meters per day when using diesel oil as fuel. The water from the river will be stored in the 1,600,000 cubic meter raw water reservoir and subsequently used to supply to the demineralization system, cooling system, office building and others.
The project is designed to reuse the effluent as much as possible. The management of the effluent from the project operation will include 2 parts as follows:
(1) Cooling water blowdown from the cooling system (i.e. 11,276 and 9,168 cubic meters per day when using natural gas and diesel oil as fuel respectively) will be drained into two 45,000-cu.m. cooling water blowdown ponds which can retain the effluent for 3 days before discharging into Klong Huaiba (Klong Nong-Ngu-Loem).
(2) Non-cooling water effluent will be split into 2 portions as follows: - Effluents contaminated with chemicals including the effluents from
the demineralization system, contaminated water from the chemical storage area, laboratory, etc. will be collected and piped to the neutralization pit for treatment. The treated effluents of a total rate of approximately 88 cubic meters per day will be conveyed into a zero liquid discharge system to make reusable water. The remaining solids from the final step of this system will be subsequently disposed of according to the procedure specified in the Notification of the Ministry of Industry, entitled “Disposal of garbage or unused materials, 2005.”
- Effluent from the office building of 30 cubic meters per day will be pretreated in the septic tanks and then collected in the holding pond and subsequently used for watering the plants. The remaining water (from watering the plants, if any) will be conveyed into the zero liquid discharge system. If the pretreated effluent cannot be used for watering plants, all of it will be conveyed into the zero liquid discharge system with a sufficient retention volume. The quantity of the effluent from the office building and the chemical contaminated effluent will total 118 cubic meters per day.
Environmental Report for submittal to ADB Nong-Saeng Power Plant Project Chapter 1 Power Generation Supply Co., Ltd. Executive Summary
T-EIA208102 1-6 F208102-Chap1E-ADB
The project has prepared the appropriate mitigative measures for use during
both the construction and operation phases, with a special attention to the protection of the
receiving water resources and the communities around the project area. By implementing
the water quality impact mitigative measures, the effluent quality will be controlled to
meet the effluent standards specified under the Notification of the Ministry of Industry,
No.2, B.E.2539 (1996) entitled “Characteristics of effluent discharged from factories”, and
the Order of the Royal Irrigation Department No.883/2532, entitled “The mitigation of low
quality effluent discharged into the irrigation waterways and the waterways connected to
the irrigation waterways within the irrigation project areas.” Accordingly, the potential
impact is considered to be non-significant.
1.4 Forestry and Wildlife Ecology
It was found from the study and survey of forestry and wildlife near the power
plant area that the condition of the study area could be described as typically flat lands
with flooded areas between the paddy fields and communities. The condition of forests
covering the ground was described as cultivated forests mixed with man-made structures
and none of the natural forest condition actually existed in this area. Moreover, the
remaining big trees in the area were grown by local people. For the diversity of wildlife
species in the study area, the results from the study revealed a total of 138 species
including the wildlife that could be sighted in the open, paddy field, grove and wetland
habitat areas. This is because the existing condition of the study area was typically paddy
fields where rice growing was still active with communities and some temples & trees
existed, and some wetlands sighted. This area, having no condition of natural forest land,
was found to be completely altered from its natural feature. The ecosystem in the area was
a man-made one so no natural wildlife habitats or forest was found to remain in the
environment. The only existing habitat areas included paddy fields, unused lands,
wetlands and communities, so the wildlife species found in this area were those that had
well adapted themselves to survive in this kind of community area. None of the wildlife
species normally living in the dense forest habitat areas was found here and the sighted
ones all had the capability to adapt themselves very well. Therefore the potential impact is
considered to be low.
Environmental Report for submittal to ADB Nong-Saeng Power Plant Project Chapter 1 Power Generation Supply Co., Ltd. Executive Summary
T-EIA208102 1-7 F208102-Chap1E-ADB
1.5 Aquatic Ecology and Fishery
The project will drain the flowing water during the construction phase and the
effluent from the cooling system during the operation phase into Klong Huaiba (Klong
Nong-Ngu-Loem). The drainage of the effluent may adversely affect the aquatic
ecological system by reducing the number of the planktons and young aquatic lives which
may be entrained in the water to be pumped for the project’s uses. Therefore the potential
impact is considered to be low.
1.6 Land Use
The development of the Nong-Saeng Power Plant Project requires an area of
570 rai. At present, the major parts of this area are mostly paddy fields, grass fields and
unused or vacant areas. The pumping station will occupy approximately 1 rai of land and
the water pipeline designed with an approximate length of 16 kilometers. The construction
of the water pipeline requires an area of approximately 2 meters in width, starting from the
pumping station at upstream of the Rama Six Dam and routing in parallel with the road
along the bank of Klong Rapeepatana-East to the project site. The water drainage pipeline
designed with a length of only 150 meters and a width of approximately 2 meters will be
routed from the project site and crossed under the road along the bank of Klong
Rapeepatana to merge with the discharge pipe on the reservoir side, and then directed into
Klong Huaiba (Klong Nong-Ngu-Loem) on the south side of the reservoir. Therefore the
potential impact is considered to be low.
1.7 Water Usage
During the construction phase of the project, the workers with the maximum
number of 6,000 will consume approximately 360 cubic meters of water per day (estimated
at 60 liters per person per day). The project will buy the water either from the Office of
Water Supply in Nong-Kae District or the Office of Water Supply in Taruer District.
Considering the existing water production capacity of the Office of Water Supply in Nong-
Kae District of 573,462 cubic meters per month and its water dispensing rate of 483,820
cubic meters per month, it can be noted that this agency still have the water supply reserve
of 90,042 cubic meters per month; whereas the Office of Water Supply in Taruer District
has its existing water production capacity of 159,787 cubic meters per month and water
dispensing rate of 113,378 cubic meters per month, and thus still have the water supply
Environmental Report for submittal to ADB Nong-Saeng Power Plant Project Chapter 1 Power Generation Supply Co., Ltd. Executive Summary
T-EIA208102 1-8 F208102-Chap1E-ADB
reserve of 46,409 cubic meters per month. During its operation phase, the project will
pump the water from the Pa-Sak River (at upstream of Rama Six Dam) at the average of
46,932 cubic meters per day during the rainy season or 1.41 million cubic meters per
month for its uses in various activities including electricity generation, cooling system and
others. During June to November of the rainy season, a large quantity of the remaining
water is released from the Rama Six Dam into the Pa-Sak River (at downstream of Rama
Six Dam) at a rate of 100-642 million cubic meters per month. Thus during these months
of the year the power plant can pump the water with the anticipated very low impact on the
downstream areas of the Rama Six Dam. This is because the quantity of water to be drawn
to the power plant is estimated at only less than 1.41% of the water released from the
Rama Six Dam during the period of the least quantity of water in the rainy season. In the
first month of the rainy season (May) and the beginning of the dry season (December), the
water consumption of the power plant will be approximately 5.6% of the irrigation water to
be released into the Pa-Sak River (at downstream of Rama Six Dam). This water quantity
is considered to impose only a slight effect on the water flow into the downstream of Rama
Six Dam, and definitely no impact on the water flowing into Klong Rapeepatana-Main
Canal will result. During the dry season (January through April), almost all of the water
quantity at upstream of Rama Six Dam is diverted into Klong Rapeepatana-Main Canal for
irrigation purpose. However, it was found from the analysis of the water balance that the
quantity of water usage of the project was less than 1% of the water for irrigation.
However, the project has planned to construct a reservoir with a capacity of 1,600,000
cubic meters to reserve its raw water. With this reservoir, the proposed Nong-Saeng Power
Plant will be able to operate for a period of 39 days without pumping the water from any
outside sources when a problem of water shortage arises in the dry season. Hence the water
usage of the project, particularly during the dry season, will not impose any impact on the
water quantity for the existing agricultural areas. For Klong Huaiba (Klong Nong-Ngu-
Loem), this canal will benefit from the quantity of the discharged water from the project
because of the resultant increase in the water quantity in the canal, particularly during the
dry season. Thus this can be considered as a positive impact of the project.
Environmental Report for submittal to ADB Nong-Saeng Power Plant Project Chapter 1 Power Generation Supply Co., Ltd. Executive Summary
T-EIA208102 1-9 F208102-Chap1E-ADB
1.8 Transportation
The estimated traffic volume in terms of passenger car units (PCU) on
Highways No.1, No.329, No.3043 and the roads along the banks of Klong Rapeepatana
(left and right stream) were found to be 141,541, 11,660, 3,126, 969 and 208 cars per day
respectively. The V/C ratio values indicated that the vehicular capacities of these roads
were 0.3, 0.2, 0.06, 0.02 and 0.004 respectively and that these roads could definitely
handle more traffic volumes. Besides, the V/C ratio on the roads along the banks of Klong
Rapeepatana (left and right stream) during rush hours or 08.00-10.00 a.m. and 04.00-06.00
p.m. were found to be in a range of 0.002-0.01 and 0.004-0.02 respectively. The vehicle
volume was estimated to be increased during the construction and operation phases by
approximately 150 and 80 cars per day respectively, and, accordingly, the V/C ratios were
then found to be indifferent. Therefore the impacts on traffic condition during the
construction and operation phases were considered to be quite low.
1.9 Drainage and Flood Control
The land preparation, general construction activities, and operation of the
proposed Nong-Saeng Power Plant will potentially induce the impacts on the drainage
condition and may induce flooding. The most potential cause of flooding is the rains over
the area covered by the Klong Preol Water Conveyance and Maintenance Project which
has a road along its boundary. The terrain slopes down to Klong Rapeepatana, so most of
the rainwater will flow towards this canal; but the side dike along the right bank (east) of
this canal, or the road with a high elevation, will retain and accumulate the water that flows
towards it because the water cannot flow over. The study results indicated that the project
area was considered to be in a moderate flood risk zone.
The existing drainage systems around the project include several natural
discharge canals, i.e., Klong Nong-Srueng, Klong Huaiba (Klong Nong-Ngu-Loem),
Klong Ban-Kokkeelek, and Klong Nong-Kae. All of these four canals cross Klong
Rapeepatana with a water gate located at each confluence to control the water flow. These
canals are always dredged to keep them from being shallow, but a problem still exists i.e.
the drainage that cannot be managed in time during heavy rains in the area. This problem
has caused flooding and stagnant waters, especially at the confluences of the discharge
canals (Klong Nong-Srueng/Klong Huaiba [Klong Nong-Ngu-Loem]) and Klong
Environmental Report for submittal to ADB Nong-Saeng Power Plant Project Chapter 1 Power Generation Supply Co., Ltd. Executive Summary
T-EIA208102 1-10 F208102-Chap1E-ADB
Rapeepatana. There is siphon building at Klong Ban-Kokkeelek that facilitates the
discharge flow to pass under Klong Rapeepatana. The construction of a drainage channel,
currently under consideration, which will facilitate the drainage of flood and stagnant
waters along the side dike of Klong Rapeepatana starts from the north to the south along
Klong Rapeepatana and merges with the siphon to allow the discharged water flow under
Klong Rapeepatana. At present, the terrain condition has been changed to some extent.
There have been some land preparations (i.e. land filling and elevating, self-managed land
preparation, etc.) that do not take natural drainage into consideration. Moreover, the road
network around the project area has made it difficult to drain the rainwater from the area.
If a sufficiently efficient management is not available, the impact will still persist.
Therefore, in order to prevent the impact that may be induced, the project has prepared the
mitigative measures for draining the rainwater from the project area and preventing the
occurrence of flooding in the surrounding areas.
1.10 Solid Wastes
During the construction phase, the maximum of 6,000 workers will generate
approximately 5.1 tons of garbage per day (based on the criterion of approximately 0.85
kilogram of garbage per individual per day). Other solid wastes generated during
construction will include scrap materials from soil excavation (e.g., scraps of soil, sand,
brick, etc.), scraps of construction materials (e.g., fractions of structures, or used or
unwanted materials, etc.), hazardous wastes (e.g., batteries, motor oil, hydraulic oil, filters,
mineral oil, cleaning agents or used solvents) as well as enamel products or rejected paints.
The project will provide a specific space for storing each type of solid wastes including
appropriate containers for separating the solid wastes to facilitate the disposal as per the
Notification of the Ministry of Industry, entitled “Disposal of garbage or unwanted
materials, 2005.”
During the operation phase, 6 types of solid wastes will be properly managed
or disposed of including general garbage from the office building, spent air filters, spent
lubricating oil and oil from the oil separators, spent resins, sludge from the wastewater
treatment system, and solid wastes from evaporation process.
The project will manage and dispose the solid wastes according to the
Notification of the Ministry of Industry, B.E.2548, entitled “Disposal of garbage or unused
materials.”
Environmental Report for submittal to ADB Nong-Saeng Power Plant Project Chapter 1 Power Generation Supply Co., Ltd. Executive Summary
T-EIA208102 1-11 F208102-Chap1E-ADB
1.11 Occupational Health and Safety
During construction phase, the working condition may induce a risk of
accident. So the project has prepared the mitigative measures for safe working and will
strictly enforce the implementation of these measures. For the operation phase, the
environmental conditions in the workplaces within the proposed Nong-Saeng Power Plant
may have some effects on the health and safety of the plant employees on duty. Three
factors of concern include (i) the main noise sources in the power plant i.e. the gas
turbines, gas compressors, safety valves, etc. The sound pressure levels generated from
these machines and equipment will be controlled by installing acoustic walls,
encapasulates, silencers at the noise sources, assigning employees to work in a control
room, and enforcing them to wear noise protection equipment while working in areas with
the noise levels of higher than 80 dB(A); (ii) major heat sources in the power plant area i.e.
the steam turbines, combustion turbines and HRSGs. To cope with the heat problem, the
project will use the insulating systems and enclosures of heat sources, etc. Employees are
assigned to work in a control room and enforced to wear heat protection equipment while
working in heated areas; and (iii) the proposed power plant will use some chemicals
including sulfuric acid, sodium hypochlorite, and ferric chloride to which the employees
may expose. However, the process of the proposed power plant will be within the closed
systems, and, in addition, the power plant will provide personal protective equipment to
the employees working with the chemicals as well as good ventilation within the power
plant and training on safe working with chemicals and procedures for the prevention and
test of chemical leakage.
The study results relating to the working environment revealed that the impact
on occupational health and safety of the employees in the power plant would be low.
However, the project has specified the mitigative measures in order to mitigate the impact
associated with the working conditions which may adversely affect the employees’ health
and safety.
1.12 Socio-economics
The socio-economic study was conducted by collecting the statistics relating to
the study area along with the field survey in the radius of 5 kilometers around the site of
the proposed Nong-Saeng Power Plant. The study started with visiting the chiefs of
Environmental Report for submittal to ADB Nong-Saeng Power Plant Project Chapter 1 Power Generation Supply Co., Ltd. Executive Summary
T-EIA208102 1-12 F208102-Chap1E-ADB
government offices at the provincial, district and sub-district levels, community leaders
and local administration organization executives. This activity was followed by an
organization of public hearing, power plant tour, and listening to the opinions of 1,095
families. It was found that the number of communities in the study area agreed with the
project was quite low. This was attributed to the anxieties about the impact on their
agricultural careers and people’s health. The impact on health was expectedly resulted
from the wastewater and stack emissions from the power plant. This expectation was
arisen from previous information about the impacts of other power plants. For the sample
the groups agreed with the power plant construction had shown their reasons which
included community development, local employment, more local economic growth,
convenient infrastructure and better community services, etc.
Although the project has already specified the mitigative measures for
alleviating the potential impacts relating to its operation, a work plan on socio-economics
has also been specified in order to make the project be able to cohabitate, to have good
relationship and to share benefit with the community.
1.13 Public Relations and Public Participation
The project implementation during the construction and operating periods may
cause both positive and negative effects on the people living around the project site. In
order to make the project implementation to bring about the advantages to communities
and to reduce the negative impacts as much as possible, mitigative measures are prepared
and people participation activities have been organized in every step continually during the
course of the EIA study. The activities regarding to the public hearing during the study
period were organized to make the community leaders understand about the reasons,
necessity of the project operation as well as the procedure of the study and assessment of
environmental impact which involved public participation during the course of data
collection, information dissemination and listening to the public opinion and obtaining
suggestions from community leaders and relevant persons. Public hearing was one of the
stages opened for participants to express their opinions, anxieties, important issues or
suggestions considered to be useful for setting the mitigative measures to minimize the
social impacts, and particularly the potential environmental and social impacts during the
construction and operating phases. The stakeholders had given the opinions and
suggestions considered to be useful for the completeness of the study results had led to the
Environmental Report for submittal to ADB Nong-Saeng Power Plant Project Chapter 1 Power Generation Supply Co., Ltd. Executive Summary
T-EIA208102 1-13 F208102-Chap1E-ADB
acceptance and participation of the local sector. The activities performed were attributed to
the cooperation of the community leaders and people in communities around the project
site who attended the meeting, and asked questions and made suggestions to the project.
The analysis and evaluation of the impacts indicated that some communities were still
anxious about the potential impacts to be result from the project. However, more than half
of the communities were aware of the necessity of energy development and the importance
of community participation in the study, monitoring of environmental impacts, watching
and control of environmental problems in the communities. These communities were
willing to act as representatives to join the monitoring and inspection of environmental
impacts. It was expected that if the work on making understanding and learning was
performed with the communities and community leaders, most community members would
eventually join the network for monitoring and inspection of environmental impacts in
communities around the project area. This was thought to also encourage the communities
to participate in any collaborations and profit sharing. All of these activities were
anticipated to lead to the continuous development of the project and acceptance from the
people living around the project site.
The environmental impact mitigation and environmental quality monitoring
measures recommended by in the EIA study were used as the basis to formulate the
environmental action plan of the project which includes all of the above-mentioned
environmental and social aspects. The outline for each aspect of the action plan comprises
such important headings as rationale, objectives, targets & activities (environmental impact
mitigative measures and environmental monitoring programs for all phases of the project),
responsible entities, report requirements and monitoring costs.
Based on the results of the EIA study, the following recommendations are
drawn for the project to consider conducting further studies and investigations:
- The project should, under all conditions, strictly enforce the implementation
of the proposed environmental measures designed for the construction and
operation phases in order to avoid or minimize both environmental and
social impacts on the surrounding communities and general public.
- The project should always conduct a preliminary environmental study when
planning to make any modification of the project design and/or the
environmental action plan to find out the environmental feasibility before
making the decision.
Environmental Report for submittal to ADB Nong-Saeng Power Plant Project Chapter 1 Power Generation Supply Co., Ltd. Executive Summary
T-EIA208102 1-14 F208102-Chap1E-ADB
- A study should be conduct to investigate the effect of climate change on the water availability in the Pa-Sak River and the required reserve volume of raw water in the 1.6-Mm3 reservoir during the entire operation life of the proposed power plant.
- The greenhouse gas emissions from the proposed power plant should be
investigated during the operation phase. The findings from the
investigation will be a useful database for many future uses, internally and
externally.
Environmental Report for submittal to ADB Nong-Saeng Power Plant Project Chapter 2 Power Generation Supply Co., Ltd. Policy, Legal and Administrative Framework
T-EIA208102 2-1 F208102-Chap2E-ADB
Chapter 2 Policy, Legal and Administrative Framework
The environmental impact assessment report of Nong-Saeng Power Plant
Project of Power Generation Supply Co., Ltd. is prepared for the project which in turns
supports to meet the increasing demand for electricity in Thailand and industrial
development. This project is a 1,653 MW combined cycle power plant being constructed
by Power Generation Supply Co., Ltd. within the areas of 2 provinces i.e., Moo. 4, Ban
Huaiba, Nong-Kob Sub-district, Nong-Saeng District of Saraburi Province; and Moo.7,
Ban Tamsinthusopa, Nong-Namsai Sub-district, and Moo 2, Ban Klong, Kokmuang Sub-
district, Pachee District of Phra Nakhon Si Ayutthaya Province. This project can utilize
both natural gas and diesel oil as fuels. The Nong-Saeng Power Plant Project is required to
conduct the environmental impact assessment in accordance with the Notification of the
Ministry of Science, Technology and Environment which mandates that a thermal power
plant of more than 10 MW capacity shall prepare and submit the EIA report to ONEP for
approval and to Department of Industrial Works for construction permission. Therefore,
Power Generation Supply Co., Ltd. engaged SECOT Co., Ltd. to study and prepare the
environmental impact assessment report of the project. The ONEP review and approval
procedure scheme for EIA report is presented in section 2.4.
2.1 Policy, Legal, and Administrative Framework
The EIA study of Nong-Saeng Power Plant Project fully complied with
applicable Thai laws i.e. ONEP guidelines for EIA report preparation which include
environmental standards/regulations and/or recommendations of Ministry of Environmental
Resources and Environment, Ministry of Industry, Ministry of Agriculture and
Cooperatives, Ministry of Transport and Communications, and Ministry of Labor. By
doing so, the conduct of the EIA study should more or less satisfy the ADB Safeguard
Policy 2009 in the Policy and Legal Framework.
For the Natural Gas Pipeline to Nong Saeng Power Plant Project, Gulf JP NS
Co., Ltd., had assigned Entic Co., Ltd., to conduct the study and prepare the EIA report.
Because the project nature is subject to the type and size of projects under the
Enhancement and Conservation of National Environmental Quality Act, B.E.2535 which
mandates the conduct of an EIA study and present the report to ONEP for approval. The
Environmental Report for submittal to ADB Nong-Saeng Power Plant Project Chapter 2 Power Generation Supply Co., Ltd. Policy, Legal and Administrative Framework
T-EIA208102 2-2 F208102-Chap2E-ADB
conduct of EIA study was also corresponding to the conditions in the proposal for
independent power producer (IPP) submitted to and approved by the Ministry of Energy.
Legally, Gulf JP NS Co., Ltd., the Company responsible for the EIA studies and the
construction of the power plant and its associated NGP, must adopt the measures for
mitigation and monitoring of the anticipated environmental impacts during the project
construction and operation. In the case that the Gulf JP NS Co., Ltd. transfers the NGP to
PTT after completion of construction, PTT must be responsible for the environmental
mitigative measures and environmental monitoring programme during operation.
2.2 Scope of the EIA Study
This EIA report presents the description of the project, the existing
environmental conditions, and project site area and vicinity as well as the assessment of
potential environmental impacts resulting from project operation, risk assessment, public
relations and public participation, and the recommendations on environmental mitigative
measures and environmental quality monitoring programme during construction and
operation. The scope of study followed the guidelines for EIA preparation as recommended
by ONEP.
The environmental resources and values presented in this report are as follows:
(1) Physical Resources
- Topography
- Meteorology and Air Quality
- Noise Level
- Geology and Earthquake
- Soil Resources
- Surface Water Hydrology and Surface Water Quality
(2) Biological Resources
- Terrestial Ecology
- Aquatic Ecology
(3) Human Use Values
- Land Use
- Surface Water Resource Utilization
Environmental Report for submittal to ADB Nong-Saeng Power Plant Project Chapter 2 Power Generation Supply Co., Ltd. Policy, Legal and Administrative Framework
T-EIA208102 2-3 F208102-Chap2E-ADB
- Transportation
- Agriculture/Industry
- Water Usage/Power Usage and Electricity Usage
- Solid Wastes Management
- Drainage and Flood Control
- Fire Prevention
(4) Quality of Life Values
- Socio-Economics
- Public Health
- Archaic Place and Antique
- Aesthetics and Tourism
- Occupational Health and Safety
- Major Hazard Assessment
(5) Public Relations and Public Participation
The potential impacts during construction and operation were then
evaluated using the existing environmental data.
2.3 Methodology
The information used in this study included both primary and secondary
data. The primary data were those collected from monitoring, surveying and analysis
which included the following:
(1) Ambient Air Quality
(2) Noise Level
(3) Surface Water Hydrology and Surface Water Quality
(4) Terrestrial Biological Resources/Aquatic Biological Resources
(5) Traffic Volume
(6) Socio-Economics and Attitude of Community Leaders and Household
Leaders towards the Project.
The secondary data were obtained from the project proponent and concerned
governmental offices as follows:
Environmental Report for submittal to ADB Nong-Saeng Power Plant Project Chapter 2 Power Generation Supply Co., Ltd. Policy, Legal and Administrative Framework
T-EIA208102 2-4 F208102-Chap2E-ADB
(1) Meteorological Department, Ministry of Transport and Communications
(2) Department of Highways, Ministry of Transport and Communications
(3) Department of Mineral Resources, Ministry of Industry
(4) Land Development Department, Ministry of Agriculture and Co-
operatives
(5) Royal Thai Survey Department, Ministry of Defence
(6) Department of Provincial Administration
(7) Saraburi Provincial Office
(8) Phra Nakhon Si Ayutthaya Provincial Office
(9) Saraburi Provincial Public Health Office
(10) Phra Nakhon Si Ayutthaya Provincial Public Health Office
(11) Saraburi Provincial Agricultural Extension Office
(12) Phra Nakhon Si Ayutthaya Provincial Agricultural Extension Office
(13) Saraburi Provincial Industry Office
(14) Phra Nakhon Si Ayutthaya Provincial Industry Office
(15) Tourism Authority of Thailand
(16) Saraburi Provincial Town and Country Planning Office
(17) Phra Nakhon Si Ayutthaya Provincial Town and Country Planning Office
(18) Amphur Administration Office, Nong-Saeng District
(19) Amphur Administration Office, Pachee District
(20) Nong-Saeng District Public Health Office
(21) Nong-Kae District Public Health Office
(22) Phachee District Public Health Office
(23) Nong-Saeng Hospital
(24) Nong-Kae Hospital
(25) Pachee Hospital
(26) Tambon Nong-Kob Health Center
(27) Tambon Khok Sa-ad Health Center
(28) Tambon Nong-Hua-Po Health Center
Environmental Report for submittal to ADB Nong-Saeng Power Plant Project Chapter 2 Power Generation Supply Co., Ltd. Policy, Legal and Administrative Framework
T-EIA208102 2-5 F208102-Chap2E-ADB
(29) Tambon Nong-Kwai-So Health Center
(30) Tambon Khok-Toom Health Center
(31) Tambon Poan Thong Health Center
(32) Tambon Khok Muang Health Center
(33) Tambon Ra-Som Health Center
(34) Tambon Nong-Nam-Sai Health Center
(35) Tambon Don Ya Naang Health Center
2.4 ONEP EIA Review and Approval Process
The EIA report of Nong Seang Power Plant Project must be submitted to ONEP
for review and approval according to the following procedural acheme;
Environmental Report for submittal to ADB Nong-Saeng Power Plant Project Chapter 2 Power Generation Supply Co., Ltd. Policy, Legal and Administrative Framework
T-EIA208102 2-6 F208102-Chap2E-ADB
Procedure of Revised or Recorrected EIA Report for Private Projects
Project owner
ONEP ONEP reviews and submits to Board
Board of Experts for consideration
Letter of EIA Report Approval
ONEP = Office of Natural Resources and Environmental Policy and Planning
Correct EIA Report
Not approved Approved
Submit EIA Report to
30 days
Project owner
ONEP reviews report (15 days)
ONEP reviews and comments to Board (15 days)
Board of Experts report (45 days)
Letter of EIA Report Approval
Project owner revises/or corrects
the EIA report
Submit EIA Report to ONEP
Request for additional information
Submit complete report to ONEP
Not approved
Approved
Procedure of EIA Report for Private Projects
Environmental Report for submittal to ADB Nong-Saeng Power Plant Project Chapter 6 Power Generation Supply Co., Ltd. Analysis of Alternatives
T-EIA208102 6-1 F208102-Chap6E-ADB
Chapter 6
Analysis of Alternatives
PGS has conducted an analysis of alternative for the proposed power plant as
follow:
(1) With and Without Project: Electricity consumption in Thailand is
projected to increase at an average annual rate of 6% between 2007 and 2011, 5% per
annum between 2012 and 2016, and 3% from 2017 to 2021. The minimum electricity
reserve margin for the 2007 to 2021 period ranges from 15.2 to 28.1%. It is set at higher
than 23% in 2013 and 2014 to cater for uncertainties involved with purchasing power from
overseas energy resources (under negotiation) and coal fired independent power producer
Projects that might be protested by the public. A 15% reserve margin is necessary to
maintain sufficient power in the advent that one or two power plants have to undergo
maintenance or emergency repair. Insufficient electricity supply will constrain economic
development in Thailand.
(2) Alternative Fuel: Natural gas is an extremely important source of energy
in terms of reducing environmental pollution. Thus, the use of gas turbines and steam
turbines are accepted as major source of electricity generation. Particularly high
efficiencies can be achieved through combining gas turbines with a steam turbine in
combined cycle mode. Natural gas burns cleaner than other fossil fuels, such as oil and
coal, and produces less carbon dioxide per unit energy released. For an equivalent amount
of heat, burning natural gas produces about 30% less carbon dioxide than burning
petroleum and about 45% less than burning coal. Combined cycle power generation using
natural gas is thus the cleanest source of power available using fossil fuels, and this
technology is widely used wherever gas can be obtained at a reasonable cost.
(3) Alternative Location: The location of power plants is determined by the
demand and balancing of the capacity in the transmission system and water resources
locating nearby that can be sufficiently supplied for power generation process. Moreover,
location of power plant should be closed to natural gas pipeline network to achieve
reasonable cost of fuel price. For these reasons, locating the power plant in the province of
Saraburi is the best alternative as result of location that closes to the load center of
Metropolitan Bangkok i.e. the major demand location, will reduce power losses in the
Environmental Report for submittal to ADB Nong-Saeng Power Plant Project Chapter 6 Power Generation Supply Co., Ltd. Analysis of Alternatives
T-EIA208102 6-2 F208102-Chap6E-ADB
transmission line. The site location is also closed to Pa-sak River and PTT natural gas
pipeline network, which will maximize profit to the Project
(4) Alternative Technology: Combined cycle power plants use both gas and
steam turbines to supply power to the network. A gas turbine generator generates
electricity and the waste heat is used to produce steam to generate additional electricity
through a steam turbine, which enhances the efficiency of electricity generation.
Additionally, combined cycles are characterized by flexibility, quick part-load starting,
suitability for both base-load and cyclic operation, and high efficiency over a wide range of
loads.
For the selection of land for the Nong-Saeng Power Plant Project, PGS had studied the
most appropriable information of three possibilities sites before selecting the proposed site as listed
below;
Environmental Report for submittal to ADB Nong-Saeng Power Plant Project Chapter 6 Power Generation Supply Co., Ltd. Analysis of Alternatives
T-EIA208102 6-3 F208102-Chap6E-ADB
Consideration Issues
1st Alternative Site Nong-Saeng
2nd Alternative Site Nong-Namsai
3rd Alternative Site KK2
Technical Issues
Distance from Fuel Source
Need to construct the Gas Pipeline to connect with the Wangnoi-Kang Khoi’s Gas Pipeline for the distance of 20-25 km.
Need to construct the Gas Pipeline to connect with the Wangnoi-Kang Khoi’s Gas Pipeline for the distance of 20-25 km.
No need to place the new Gas Pipeline
Distance from Transmission Line
Transmission Line supported from Wangnoi-Tah Ta Ko’s line
Transmission Line supported from Wangnoi-Tah Ta Ko’s line
Transmission Line needs improvement (cost 3,200 Million Baht)
Distance from Water Source
13 km. away from the Pasak’s River 13 km. away from the Pasak’s River 1 km. away from Pa-Sak’s River
The stability of Water Supply Source
Water source delivering from Pa-Sak’s River and Klong Chainart
Water source delivering from Pa-Sak’s River and Klong Chainart
Water source delivering from Pa-Sak’s River
Land that needed to be cover with soil
Need site preparation(to protect flooding) Need site preparation(to protect flooding) Need site preparation (to protect flooding)
Land Access Close to Klong Rapeepat’s Rd. Close to Klong Rapeepat’s Rd. Close to Sanam Thong-Pang Go’s Rd.
Environmental Issues
Impact on Social Surrounding area fill with paddy field along the site location but quite the distance away from the community
Surrounding area fill with paddy field along the site location but quite the distance away from the community
Having the idea of buying the new site location next to KK2 as being acceptable among the local community around the area.
Environmental Report for submittal to ADB Nong-Saeng Power Plant Project Chapter 6 Power Generation Supply Co., Ltd. Analysis of Alternatives
T-EIA208102 6-4 F208102-Chap6E-ADB
Consideration Issues
1st Alternative Site Nong-Saeng
2nd Alternative Site Nong-Namsai
3rd Alternative Site KK2
Impact on Air Quality
Lowland but not the vale hence not easy to gather air pollution
Lowland but not the vale hence not easy to gather air pollution
Surrounding with the mountain range starting from the north toward the northeast and the south. Thus, easily to cause and gather air pollution in some seasons.
Conflict for the use of Land
Most of the land site is neglected and unoccupied. Surrounding areas are the paddy with low population density.
Most of the site location land and the surrounding area were used as the paddy field. Along the area there is irrigation canal flow across. Only a small village is living nearby.
Most of the site location land were used as the agricultural area e.g. cultivate corn, soy bean, and mango. There is only small village is living nearby.
Impact on the use of water supply
PGS will intake water from Pa-Sak’s river where the Royal Irrigation Dept. takes all kind of responsibilities to manage adequate water supply for all source of activities. (where the river still have high source of water)
PGS will intake water from Pa-Sak’s river where the Royal Irrigation Dept. takes all kind of responsibilities to manage adequate water supply for all source of activities. (where the river still have high source of water)
PGS will pumping water from Pa-Sak’s river which predicted that it can enable the adequate source of water for those industrial without effecting the use of water source from agricultural site.
Impact on water quality from the water supply source
As Pa-Sak’s river has high volume for water supply hence the use of water from this source could not play any effect on its water quality.
As Pa-Sak’s river has high volume for water supply hence the use of water from this source could not play any effect on its water quality.
As Pa-Sak’s river has high volume for water supply hence the use of water from this source could not play any effect on its water quality.
Loss of Agricultural Area
Due to most of the areas were used as the paddy and always face flooding problems hence most of the lands were left neglected and unoccupied. Thus not effected.
Most of the lands were used as double-crop field hence the set up of PGS will truely effect the paddy field’s area and other but only effected in a lower level.
Truly effect as the site location that plan to be the land for PGS is now used as the corn field.
Environmental Report for submittal to ADB Nong-Saeng Power Plant Project Chapter 6 Power Generation Supply Co., Ltd. Analysis of Alternatives
T-EIA208102 6-5 F208102-Chap6E-ADB
Consideration Issues
1st Alternative Site Nong-Saeng
2nd Alternative Site Nong-Namsai
3rd Alternative Site KK2
Impact on ecosystem of water source
Not much impact on ecosystem from the water source as our design technology can control the pumping speed to help those aquatic animal skip away from the pipe. Also, as the river flows and circulates consistently, this enables the plankton to autogenesis themselves in case they have been pumped into the pumping pipe.
Not much impact on ecosystem from the water source as our design technology can control the pumping speed to help those aquatic animal skip away from the pipe. Also, as the river flows and circulates consistently, this enables the plankton to autogenesis themselves in case they have been pumped into the pumping pipe.
Not much impact on ecosystem from the water source as our design technology can control the pumping speed to help those aquatic animal skip away from the pipe. Also, as the river flows and circulates consistently, this enables the plankton to autogenesis themselves in case they have been pumped into the pumping pipe.
Impact on ecosystem on terrestrial
No wild animal, animal, rare plant, etc. within the area.
No wild animal, animal, rare plant, etc. within the area.
No wild animal, animal, rare plant, etc. within the area.
Impact on archaeology
No archaeology site within the site area but surrounding temples.
No archaeology site within the site area but surrounding temples.
No archaeology site within the site area but surrounding temples.
Environmental Report for submittal to ADB Nong-Saeng Power Plant Project Chapter 7 Power Generation Supply Co., Ltd. Information, Disclosure, Consultation and Participation
T-EIA208102 7-1 F208102Chap7E-ADB
Chapter 7 Information, Disclosure, Consultation and Participation
7.1 Introduction
Nong-Saeng Power Plant Project is the combined cycle type being developed
in accordance with the Power Development Plan of the year 2007 responding to the
increasing power supply demand with economic growth. The Power Generation Supply
Co., Ltd., realized that the project development could not be accomplished without public
acceptance from the communities around the power plant. Consequently, several public
relation and public participation activities were conducted in order to make the acceptance
and awareness of the Nong-Saeng Power Plant Project as a part of the communities. The
operation of community participation by the Nong-Saeng Power Plant Project included
share of awareness, co-inspection and shared benefit. The activity results during the study
period will lead to the designation of the social mitigative measures during the
preconstruction, construction, and operation periods. As a result, the communities would
be confident and less anxious about the project development, so that the project and the
communities can live together in peace.
The principles of public participation of the Nong-Saeng Power Plant Project
emphasize on the process of making the people and nearby communities participate in the
process from the beginning. This aimed to make understanding, learning and improving or
changing in the constructive way for mutual benefit. It also aimed to make careful decision,
reduce conflict and make the implementation be practical. The activities followed the
guidelines for public participation and social impact assessment in the process of
environmental impact analysis specified by the Office of Natural Resources and
Environmental Planning and Policy (ONEP), and the regulation of the Office of the Prime
Minister entitled public hearing of the year 2005.
7.2 Objective
(1) To distribute information and news of the project development to
relevant governmental officers, local officers (TAO) and community leaders in order to
make them know the benefits and impacts of the project, including the mitigative measures
of the project.
Environmental Report for submittal to ADB Nong-Saeng Power Plant Project Chapter 7 Power Generation Supply Co., Ltd. Information, Disclosure, Consultation and Participation
T-EIA208102 7-2 F208102Chap7E-ADB
(2) To allow people, community leaders and governmental officers at
different levels participate in having opinion and recommendations on their anxiety about
the project. This would lead to the cooperation in correcting and improving of the project
development procedure and to their acceptance.
(3) To make good understanding and collaboration between the project
owner and the communities for mutual benefits at both national and community levels.
7.3 Target Group and Implementation Area
Target Group
(1) People and community leaders, and occupation groups in the vicinity
area of 5 km. radius from the Nong-Saeng Power Plant Project site.
(2) Executive/staff of local administration organizations in the study area
covering 12 subdistricts in 3 districts (Nong-Saeng, Nong-Kae and Pachee) of 2 provinces
(Saraburi and Phra Nakhon Si Ayutthaya).
(3) Heads of the relevant governmental offices in the study area (given in
(2)).
(4) Environmental conservation organizations/networks in the study area.
(5) Mass media and interested people.
Implementation Area
(1) The project location is Moo 4, Ban Huaiba, Nong-Kob Subdistrict in
Nong-Saeng District of Saraburi Province.
(2) The study areas are Nong-Kob, Nong-Kwai-So, Khok Sa-at, Nong-
Huapho Subdistricts in Nong-Saeng District, Khok Toom, Phonthong and Khotsasit
Subdistricts in Nong-Kae District of Saraburi, Nongnamsai, Donyanang, Rasom, Khok
Muang and Pachee Subdistricts in Pachee District of Phra Nakhon Si Ayutthaya.
7.4 Work Plan and Activities Performed
The public relation and public participation activities were carried out along
with the socio-economic study (Chapter 4, Topic 4.4.1). The works included
preparation/planning/public relation media production, making understanding, presentation
and getting to comments on the study, data analysis, impact evaluation and designation of
social mitigative measures. The details are as follows :
Environmental Report for submittal to ADB Nong-Saeng Power Plant Project Chapter 7 Power Generation Supply Co., Ltd. Information, Disclosure, Consultation and Participation
T-EIA208102 7-3 F208102Chap7E-ADB
(1) Preparation/planning/public relation media production
The Power Generation Supply Co., Ltd. realizes that the public relation
and public participation work are sensitive and are to conducted by the experts who know
how to work with the communities/localities, understand way of life and living status of
local people, have good skill in information dissemination, and are sincere and enthusiastic
to work transparently. The activities conducted in August 2007 are.
Field data collection. This is the preliminary review of the area data in
order to know the conditions of the study area in terms of social condition, living
status/way of life, nature of communities household settlement, density, number of
households in each community, communication channel and interview of preliminarily
opinion of the community leaders. The results were used for specifying the issues for
making the survey tool, work planning, and setting the population ratio for the survey. The
survey was conducted in September 2007.
Direct coordination and communication with the local communities, i.e.,
community leaders and local people. The purposes of this activity were making familiarity,
making good understanding about the project, procedure and objectives of the study and
environmental impact assessment, asking for cooperation in the project public relation and
organizing of public hearing stage.
Assignment of team or personal media for complementing the objectives.
The Power Generation Supply Co., Ltd. assigned the team being responsible for public
relation or personal media as follows:
- The 17 mass communication staff of the Power Generation Supply Co.,
Ltd. were responsible for giving information and explanation, making
understanding, being communication medium between the
communities and the project, coordinating with community leaders,
asking for cooperation in the project public relation. They worked in
the study area during the pre-study and study periods and continued
through the pre-construction, construction and operation periods.
- The public relation and public participation study team of 8 persons
from the consultant company. They were responsible for coordinating
with community leaders and local administration organization
executives, giving information and explanation, making understanding,
organizing the first public hearing meeting, organizing the power plant
Environmental Report for submittal to ADB Nong-Saeng Power Plant Project Chapter 7 Power Generation Supply Co., Ltd. Information, Disclosure, Consultation and Participation
T-EIA208102 7-4 F208102Chap7E-ADB
tour, organizing the second public hearing meeting, organizing the
public stage, analyzing and evaluating the implementation results. The
work was conducted during August 2007 to March 2008.
- The 10 interviewers were trained before filed working in order to have
knowledge about the project at the level that they could explain basic
information to interviewees. They worked under supervision of the
field experts in October 2007.
Activities on Public Relation and Public Participation
The public relation and public participation work was conducted along
with the socio-economic study and public opinion. The activities emphasized on giving
information, making understanding, listening to opinion and suggestions. The activities
were conducted using two-way communication during the study period. The activities on
public relation and public participation were summarized below.
- Production of public relation media for facilitating the public relation
and public participation effectively which were used for making
understanding with the target groups and disseminating the project
news to the whole study area and target groups of all levels. Two
media type used were
• Making understanding media were used for making the target
groups understand the process of electricity generation. The media
were produced in several forms which were easy to understand, i.e.,
leaflet, handbill, handout, Power Point presentation for the meeting
and evaluation form, etc.
• News agenda informing media were used for making the target
groups get the project information. Since there was plenty of time
for preparation to join the project activity, the news informing
media were produced. They included the letters asking for
cooperation from provinces, districts and local administration
organizations posters of news agenda and meeting results.
Environmental Report for submittal to ADB Nong-Saeng Power Plant Project Chapter 7 Power Generation Supply Co., Ltd. Information, Disclosure, Consultation and Participation
T-EIA208102 7-5 F208102Chap7E-ADB
(2) Making understanding communication
The communication for making understanding between the project and
the communities was carried out continuously during the whole study period. It was aimed
to make the project stakeholders be able to reflect their anxiety and give suggestions for
the project. It also aimed to reduce conflict, give an opportunity for the project and the
communities to be close and credible to each other. This would lead to people’s pleasure to
participate in the project in the future. The activities related to this issue were
- Individual opinion hearing was the interview of household
representatives about the socio-economic study and public opinion.
Before the interview, the interviewer explained the project information
and got the interviewee’s opinion. This activity was performed with
1,095 persons in October 2007.
- The first meeting for information informing and public opinion
hearing was organized to make understanding with the communities.
during October 28 to November 12, 2007. The attendance of 653 was
at the meeting.
- The touring of the power plants was performed during November 10,
2007 to June 15, 2008. There were 19 plant visits with 2,218 persons
joining the activity.
(3) Result presentation and opinion hearing on the study results
The activity was performed with 2 formats as follows:
- The second meeting on public opinion hearing meeting involved the
presentation of the study results and environmental measures. It was
aimed to make the communities participate in awareness and give
additional suggestions to the environmental measures given in the
report. The activity was conducted during January 20 to February 13,
2008. There were 10 stages organized with 1,005 participants.
- The meeting for informing the project information to chicken and hen
husbandry groups in Pachee and Nong-Saeng Districts was organized
to listen to and to share idea with the occupation groups who were
Environmental Report for submittal to ADB Nong-Saeng Power Plant Project Chapter 7 Power Generation Supply Co., Ltd. Information, Disclosure, Consultation and Participation
T-EIA208102 7-6 F208102Chap7E-ADB
anxious about the project impacts. It was conducted on February 12,
2008 with 20 participants.
- The meeting for obtaining the conclusion from Nong-Kob TAO was
organized on February 14, 2008 in the meeting room of the Nong-Kob
TAO in Nong-Saeng District of Saraburi Province. There were 28
participants.
- The public stage was organized after the meeting for obtaining the
opinion on the study results. The stage was widely opened for all
representatives of people, both in and outside the study area, to widely
give their opinion about the project. It was conducted on March 27,
2008 in the meeting hall of Nong-Saeng Wittaya School in Nong-
Saeng District of Saraburi Province. There were 1,670 attendants.
The number of the participants in the public relation and public
participation activities is summarized in Table 7.4-1.
(4) Data analysis, evaluation and designation of the social mitigative
measures.
This was to monitor and inspect the activities according to the public
hearing process. The results were analyzer and evaluated after the activities of community
leader visits, meetings and individual opinion hearings were conducted. In this study, it
was aimed to make the target groups learn and accept the project by recording the opinion,
photographs and participant registration in order that the communication for additional
data or opinion about the project would be done again. The impact evaluation was base on
the following data :
- Interview results of household representatives,
- Discussion about opinion, suggestion and questioning and answering
(Q&A) in the meeting,
- Evaluation form filling in the meeting.
The results of impact evaluation were used as the frame for setting social
mitigative results.
Environmental Report for submittal to ADB Nong-Saeng Power Plant Project Chapter 7 Power Generation Supply Co., Ltd. Information, Disclosure, Consultation and Participation
T-EIA208102 7-7 F208102Chap7E-ADB
Table 7.4-1
Summary of Public Relation and Public Participation Activities
Nong-Saeng Power Plant Project
No. Activity Participant (person)
1. Individual opinion hearing 1,095
2. The first public hearing meeting on 9 stages 653
3. The power plant tour of 19 rounds 2,218
4. The second public hearing meeting on 10 stages 1,005
5. The information informing meeting with the chicken and
hen husbandry groups
20
6. The meeting for obtaining the conclusion from Nong-
Kob TAO
28
7. The public stage meeting 1,670
Total Participants 6,689
Environmental Report for submittal to ADB Nong-Saeng Power Plant Project Chapter 7 Power Generation Supply Co., Ltd. Information, Disclosure, Consultation and Participation
T-EIA208102 7-8 F208102Chap7E-ADB
7.5 Results
7.5.1 Media preparation/public relation media production
In the public relation work of the Nong-Saeng Power Plant, the consultant
company and the Power Generation Supply Co., Ltd. emphasized on disseminating the
correct and clear information to all levels of the target groups in order to make them be
confident with the electricity generation process and the power plant operation. The
reduction of the community’s anxiety about the electricity generation process would ease
the project progress. The people in the project site could live happily and they were pleased
to participate in monitoring and inspecting the potential impacts from the project operation.
In order to reach the objectives, the consultant company and the Power Generation Supply
Co., Ltd. utilized several public relation media (as shown in Table 7.5-1) appropriate for all
target group levels. The media reaching to all target groups were
(1) Personal media are the most effective media for public relation. They can
transfer the information directly to the target groups, and make two ways communication,
during which the acknowledgment and the evaluation of the immediate response of the
target groups were obtained. They also made good relationship between the consultant
company and the Power Generation Supply Co., Ltd. There were 3 teams of personal
media for public relation as follows :
- Mass communication staff of the Power Generation Supply Co., Ltd.
were responsible for specifying the policy and planning the working
strategies for mass communication in the area during the pre-study
and study periods and the operation period. They visited, coordinated,
explained the project details and listened to opinion from executives
of several levels of administration organization in the area during the
study period.
- Technical staff and assistants on public relation and public
participation of the consultant company visited, coordinated,
explained the project details and listened to opinion from executives
of several levels of administration organization in the area for the
whole study period.
Environmental Report for submittal to ADB Nong-Saeng Power Plant Project Chapter 7 Power Generation Supply Co., Ltd. Information, Disclosure, Consultation and Participation
T-EIA208102 7-9 F208102Chap7E-ADB
Table 7.5-1
Summary of Media Used in Social Study and People’s Opinion
Nong-Saeng Power Plant Project
Media/Content Number Usage Target group Duration Result
Personal media 1. Mass communication
staff of the Power Generation Supply Co., Ltd.
17 persons
- Policy setting - Strategy planning
All levels Already performed in the area.
- The target groups understood the project.
- The communities cooperated with the project.
2. The consultant company
8 persons
- Giving and explaining the project information.
- Organizing the meeting.
Office/ organization/leaders
The whole study period.
- Office/organization/ leaders got the project details and
cooperated in giving information to the communities.
3. Interviewer 10 persons
- Giving the project information.
- Opinion survey using questionnaires
Households - The communities understood and accepted the project
- The response and needs of the communities were known.
Understanding establishment media 1. Leaflet of the study
and environmental impact assessment of the Nong-Saeng Power Plant.
3,000 sets
- Being distributed at the public hearing meeting.
- Giving to the interviewees.
All levels The whole study period.
- People/communities in the study area were informed about the project information and the guidelines of environmental impact assessment.
2. Leaflet of the knowledge about electricity generation and natural gas.
3,000 sets
- Being distributed at the public hearing meeting
- Giving to the interviewees
All levels The whole study period.
- People/communities in the study area were informed about the project information, safe electricity generation process and clean fuels.
3. Power point presenting the details/ characteristics of the project, procedure, the study, etc.
2 sets - Being Presented in the public hearing meeting.
Community leader/chief/ executive/ organization
- Establishing the understanding of the participants.
Environmental Report for submittal to ADB Nong-Saeng Power Plant Project Chapter 7 Power Generation Supply Co., Ltd. Information, Disclosure, Consultation and Participation
T-EIA208102 7-10 F208102Chap7E-ADB
Table 7.5-1 (Cont’d)
Media/Content Number Usage Target
Group Duration Result
Information informing media
1. Letter for cooperation.
- - Coordinating in working.
Chiefs of
offices at
provincial/
district/local
administra -
tion
organization
levels
Before
organizing
all stages
of the
public
hearing.
- Good cooperation was achieved for working.
- Data and useful suggestion for working were obtained.
2. Meeting agenda placard
15 sets - Informing of the meeting agenda 15 days in advance.
All target
groups.
15 days
before the
meeting
- People/interested persons could attend the meeting at all stages.
3. Meeting minute placard
15 sets - Minutes of the first and the second meetings.
All target
groups.
15 days
after the
meeting
- People/interested persons knew many issues and answers/corrective measures obtained from the meeting.
Environmental Report for submittal to ADB Nong-Saeng Power Plant Project Chapter 7 Power Generation Supply Co., Ltd. Information, Disclosure, Consultation and Participation
T-EIA208102 7-11 F208102Chap7E-ADB
- The 10 interviewers elucidated, publicized, explained the project
details and replied the questions before interviewing household
representatives. This made the interviewees have more knowledge and
understanding about the project.
(2) Documental media. The consultant company and the Power Generation
Supply Co., Ltd. produced several media forms with a sufficient quantity for distributing to
the target groups over the study area. The media included the following :
- The 3,000 sets on leaflet on the study and assessment of
environmental impacts of the Nong-Saeng Power Plant project were
distributed to the communities and information providers on socio-
economics.
- The leaflets on knowledge about power generation and natural gas
were distributed to all meeting attendances, the communities and
information providers on socio-economics.
- Placards of meeting agenda for public hearing were posted at public
relation boards in governmental offices and local administration
organizations at least at least 15 days before the public hearing
meeting.
- Placards of the minutes of the public hearing meeting were posted at
the public relation boards in Nong-Saeng, Nong-Kae and Pachee
District Offices and in TAOs/municipalities in the study area.
- The Power Point presentation used in the meeting.
- Questionnaires on socio-economics and people’s opinion.
7.5.2 Communication for making understanding with offices/organization/
communities/people (First public hearing)
The activities included the survey on socio-economics and people’s opinion,
the first informing meeting and public hearing and the study tour of the existing power
plants. The results were summarized bellows.
(1) Opinion hearing of each household.
In the survey on socio-economics and people’s opinion, the study team
had trained the interviewers so that they had knowledge and understanding about the
project enough for explaining the basic project information to the household
Environmental Report for submittal to ADB Nong-Saeng Power Plant Project Chapter 7 Power Generation Supply Co., Ltd. Information, Disclosure, Consultation and Participation
T-EIA208102 7-12 F208102Chap7E-ADB
representatives. It was aimed to make the interviewees have sufficient information before
making decision and giving suggestion to the project. Before interviewing, the staff handed
in the public relation media of the project, e.g., leaflets and explained about reasons and
requirement, objectives, important issues, project nature, project site, products/ outcome,
benefit and impacts of the project to the interviewees. The interviewees were allowed to
ask questions, give information and express their opinion openly. The interview using the
questionnaire was conducted in October 2007. There were 1,095 household representatives
who expressed their opinion via the questionnaire.
(2) Organizing the informing meeting and public hearing
The informing meeting and public hearing about the study on
environmental impact assessment (EIA) were the activities for making the community
leaders understand the reasons and necessity for the project operation the study
methodology of EIA which requested for public participation. The participation was
needed in many steps such as, data collection, dissemination of opinion hearing
information and suggestion of community leaders and related persons. The public hearing
was the stage opened for participants to express their ideas, relevant issues or suggestion of
communities which were useful for assigning social mitigative measures. Furthermore, the
informing meeting and public hearing organized for the communities and relevant persons
widely extended the understanding and acceptance of the study results and EIA to the
community members. The public hearing was thus organized under the following
objectives :
- To explain the project details to the community leaders and relate
persons about the guideline/steps of the study and EIA so that they
understood and realized the importance of public participation in the
project study.
- To allow the community leaders and related persons to participate in
opinion expression about the environmental mitigative measures, to be
willing or pleased to join the study and assessment of environmental
impacts, and to participate in monitoring/inspecting of the
environmental impacts.
- To ask for cooperation from the community leaders in the survey on
socio-economic status and people’s opinion.
Environmental Report for submittal to ADB Nong-Saeng Power Plant Project Chapter 7 Power Generation Supply Co., Ltd. Information, Disclosure, Consultation and Participation
T-EIA208102 7-13 F208102Chap7E-ADB
Schedule, place, media and participant number
The place for organizing the activity on community opinion hearing was
based on the area within 5 kilometer radius of the project site. The area covered the
communities in 12 subdistricts. The activity was carried out on October 28 to November
12, 2007. There were 9 stages organized with 653 participants as shown in Table 7.5-2.
- The meeting supplementary media were provided for the meeting. The
media examples shown in Appendix VI were
• The documents for project presentation consisted of reasons,
necessity, objectives, nature of the Nong-Saeng Power Plant and
study methodology of the project.
• The power point media used for presentation via a computer
consisted of reasons and necessity of the project, summary of the
project description of the combined cycle power generation,
objectives, procedure and methodology of the study and assessment
of environmental impacts and public participation.
- For the meeting agenda, the public hearing was divided into 2 sessions
as to give the information on the project background and to brainstorm
the opinion/suggestion of the participants. The public hearing activity
performed was summarized as follows :
• To explain the project description in order to make understanding
of the public hearing participants. The content of the explanation
emphasized on the 3 issues as follows :
: Project background
: Study and assessment of social impacts
: Electricity generation process and environmental mitigative
measures of the Nong-Saeng Power Plant project.
• To answer questions and to brainstorm the opinion of the
participants after the presentation of the project information. The
community leaders and participants were allowed to ask questions
about any unclear issues. This was to make correct knowledge and
understanding, and to get anxiety issues and suggestions which
were useful for the study and EIA of the project.
Environmental Report for submittal to ADB Nong-Saeng Power Plant Project Chapter 7 Power Generation Supply Co., Ltd. Information, Disclosure, Consultation and Participation
T-EIA208102 7-14 F208102Chap7E-ADB
Table 7.5-2
Date/Time, Place and Number of Participants in the First Public Hearing
of the Nong-Saeng Power Plant Project
Date/Time Place Participants Number (Persons)
Oct 28, 2007 03.00-06.00 p.m.
Nong-Kob and Nong-Kwai-So Sub-districts, at Wat Nong-Tangbun of Nong-Kob Sub-district in Nong-Saeng District of Saraburi Province
- Chief executive of the Nong-Kob TAO
- Community leaders - Local people
142
Oct 29, 2007 03.00-06.00 p.m.
Khok Sa-at and Nonghuapho Sub-districts, at Wat Ngew-ngarm of Khok Sa-at Sub-district in Nong-Saeng District of Saraburi Province
- Chief executives of the Khok Sa-at and Nonghuapho TAOs
- Community leaders - Local people
53
Oct 30, 2007 09.00-12.00 a.m.
Khotsasit Sub-district, at Khotsasit MD in Nong-Kae District of Saraburi Province
- Mayor of the Khotsasit MD - Community leaders
20
Nov 2, 2007 03.00-06.00 p.m.
Rasom Sub-district, at Wat Rakhen of Rasom Sub-district in Pachee District of Phra Nakhon Si Ayutthaya Province
- Chief executive of the Rasom TAO
- Community leaders - Local people
75
Nov 4, 2007 03.00-06.00 p.m.
Nong-Namsai Sub-district, at Nong-Namsai TAO in Pachee District of Phra Nakhon Si Ayutthaya Province
- Community leaders - Local people
36
Nov 5, 2007 09.00-12.00 p.m.
Pachee MD, at Pachee District Office in Phra Nakhon Si Ayutthaya Province
- Mayor of the Pachee MD - Deputy mayor of the Pachee MD - Municipal clerk of the Pachee
MD - Community leaders and people in
the area
38
Nov 5, 2007 03.00-06.00 p.m.
Khok Toom and Phonthong Sub-districts, at the civil defense volunteer center of Khok Toom Sub-district in Nong-Kae District of Saraburi Province
- Mayor of the Khok tpom MD - Municipal of the Khok Toom
MD - Community leaders and people in
the area
164
Nov 7, 2007 09.00-12.00 p.m.
Khok Muang Sub-district, at Khok Muang TAO in Pachee District of Phra Nakhon Si Ayutthaya Province
- Chief executive of the Khok Muang TAO, community leaders
- Local people
94
Nov 12, 2007 09.00-12.00 p.m.
Donyanang Sub-district, at Wat Wimolsoonthorn in Pachee District of Phra Nakhon Si Ayutthaya Province
- Chief executive of the Donyanang TAO
- Community leaders - Local People
31
Total 9 stages Total participants 653
Environmental Report for submittal to ADB Nong-Saeng Power Plant Project Chapter 7 Power Generation Supply Co., Ltd. Information, Disclosure, Consultation and Participation
T-EIA208102 7-15 F208102Chap7E-ADB
Results of Q&A/suggestion in the meeting
From the 9 public hearing stages, several issues raised by the participants
were summarized in Table 7.5-3.
Results of questionnaire response in the meeting
In all public hearing stages, apart from the Q&A, the participants were
asked to answer the questionnaire in order to get their opinion about the project. Out of 653
participants in 9 stages, there were 381 persons (58.4%) replying the questionnaire. The
details of the evaluation given in Appendix VI were summarized as follows :
Part 1: For general information of the respondents, most of them (61.2%)
were male with age of 31-60 years old. Most of them finished elementary schools and were
agricultures (24.7%). The second most ones were local administrator/officer/executive of
local administration organization or governmental officers of several offices.
Part 2: Knowledge, understanding and receiving of the project news.
Regarding the project information receiving, it was found that most of respondents (51.4%)
did not know about the project information beforehand. Some of them (49.7%) got the
information from local leaders/TAO/MD, from the project staff (15.6%), and from family
members/friends (14.5%).
For the levels of the knowledge and understanding about the project, it
was found that most respondents (29.1%) had knowledge and understanding about the
project at the low level. But after the public meeting, they (35.4%) had more knowledge
and understanding about the project at the moderate level. It was implied that the public
meeting made people to have more knowledge and understanding about the project.
Moreover, most respondents needed additional project information,
particularly on the environmental impacts of the project. The project could send the
information via group or community leaders (54.9%), a meeting (29.6%), and posting on
the board in the governmental offices (14.8%).
Part 3: Public participation and comments on the project. The
respondents expressed their opinion about advantages or impacts of the project to public.
Most of them commented that the project had both benefit and impacts (25.2%). The
second most saw that the project had more benefit than drawback (17.3%). In contrast, few
did not see any advantages of the project (0.8%).
Environmental Report for submittal to ADB Nong-Saeng Power Plant Project Chapter 7 Power Generation Supply Co., Ltd. Information, Disclosure, Consultation and Participation
T-EIA208102 7-16 F208102Chap7E-ADB
Table 7.5-3
Summary of Q&A Issues and Suggestions from the Public Hearing Stages
Nong-Saeng Power Plant Project Group Area Concern Issue Suggestion
1 Nong-Kob and Nong-Kwai-So Sub-districts
- The concern issue was inconclusive. Some community leaders asked for change of the project details presentation format and the public hearing procedure.
- The community leaders suggested that the meeting be organized in all villages in order to explain the project details with longer time for explanation. They needed 2 weeks for discussion among the villages in the sub-districts.
- The head of the public health center suggested a study tour at a power plant similar to that to be constructed in Nong-Saeng in order to learn about the actual impacts, and mitigative measure.
2 Khok Sa-at and Nong-Huapho Sub-districts
- The impact of the effluent discharged from the power plant on the communities, especially on agriculture.
- The impacts of the power plant on daily life of villagers.
- The impacts on drinking water and water for sanitary uses of villagers.
- The impacts on traffic and road condition.
- To request the power plant openly and clearly disclose the information both positively and negatively in details to the communities.
- To use solar cell had to for power generation instead of natural gas.
3 Khotsasit Sub-district
- The reasons for selecting this area as the power plant site.
- After the plant was operated for a while, would the power plant use
other fuels rather than natural gas?
- Would de-ionized water affect
agriculture, fishery and tourism? - Would The water consumption of the
power plant affect the agricultural
sector?
- To request that the power plant to clearly and frankly disclose the information.
- The effluent from the power plant should be discharged to other canals, not Klong Rapeepatana.
Environmental Report for submittal to ADB Nong-Saeng Power Plant Project Chapter 7 Power Generation Supply Co., Ltd. Information, Disclosure, Consultation and Participation
T-EIA208102 7-17 F208102Chap7E-ADB
Table 7.5-3 (Cont’d) Group Area Concern Issue Suggestion
4 Rasom Sub-district
- No concern. - More negative impacts and details of information should be presented e.g., loud noise level, carbon content etc. These pieces of information would be taken into consideration.
5 Nong-Namsai Sub-district
- Would the power plant use other fuels
instead of natural gas? - Would the noise level generated by
the power plant exceed the standard ? - The project site was the rice farming
area rented by some farmers. When it was purchased for power plant construction, those farmers would have no farming lands.
- How safe were the gas pipelines?
- During construction period, the roads would be damaged. How would the company manage this problem?
- How many the safety systems were there?
- No suggestion
6 Pachee Sub-district
- What advantage would the community get from the power plant?
- Would this power plant cause the global warming?
- Impacts of water on agricultural sector.
- Would air pollution from the power plant affect pregnant women and children?
- The effluent should be discharged by other means, not to Klong Rapeepatana.
- A tour of the similar power plants should be arrange in order to make understanding about a power plant.
- It was suggested to inform or publicize the channels for information inquiry or complaints about the power plant, e.g., telephone number, etc.
7 Khok Toom and Phonthong Sub-districts
- Various impacts of the power plant. - Would the light generated from the
power plant affect agricultural crops? - How many local people have a
chance to be employed by the power plant?
- No suggestion.
Environmental Report for submittal to ADB Nong-Saeng Power Plant Project Chapter 7 Power Generation Supply Co., Ltd. Information, Disclosure, Consultation and Participation
T-EIA208102 7-18 F208102Chap7E-ADB
Table 7.5-3 (Cont’d) Group Area Concern Issue Suggestion
8 Khok Muang Sub-district
- Impacts of the effluent discharged from the power plant.
- Impacts of air emissions from the power plant
- Impacts on agricultural crops. - Impacts of noise generated from the high voltage transmission line. - Noise impacts on poultry as there
were hen farms nearby the plant. - Would the power plant increase the
ambient air temperature? - Would the power substation affect
receiving signal of the household
appliances?
- Water management of the power plant as there was water shortage in the dry season.
- A tour of the existing power plants should had to be organized.
- The power plant should give priority to local people for employment.
9 Donyanang Sub-district
- Impacts on water consumption and effluent discharged from the power plant.
- Impacts of air emissions from the power plant.
- Would the power plant change the
fuel to be coal? - In the study tour of a power plant,
only good images would be presented.
- A tour of the existing power plants should be organized.
Environmental Report for submittal to ADB Nong-Saeng Power Plant Project Chapter 7 Power Generation Supply Co., Ltd. Information, Disclosure, Consultation and Participation
T-EIA208102 7-19 F208102Chap7E-ADB
For the opinion about benefit or impacts of the project on the
environmental condition in the area or on the local people, most respondents agreed that
the project had both benefit and impacts (22.3%). The second most did not give any
comments (17.6%). In contrast, few did not see any advantages of the project (0.7%).
For the whole figure, most respondents agreed that the project had to be
implemented as planned (33.3%). The second most did not give any comments (32.8%). In
contrast, a few told that the project should not be implemented (16.8%).
Part 4: Opinion and suggestion about the project. The opinion/
suggestion of the respondents about the project were summarized below.
- The project should be carried on for country development, but
environmental impacts were to be realized.
- The environmental impacts of the project should be studied and
assessed before/during/after the project operation and the study results
were to be presented to the communities.
- Sufficient mitigative measures for environmental impacts were to be
provided with life quality of communities taken into account.
- To publicize all news/information to all relevant parties and to have
regular meetings.
- To construct an alternative safer power plant, for example, the power
generation using solar cells, etc.
- To organize a tour of a power plant similar to the plant to be
constructed and operated.
- To take public benefit into account, particularly; the fund allocation to
be fair and beneficial to the communities.
(3) Organization of a study tour of the other existing power plants
After the public hearing, it was found that people in the study area had
little understanding about the project and there were concerns about the project at high
level. The Power Generation Supply Co., Ltd. organized the tour to visit the other existing
power plants in order to make the people in the study area have experience and understand
the operation details of the same or similar projects to be constructed in the area. It was
also to make people understand the problems and corrective measures and mitigation of
real practice. In the tour, heads of the governmental offices, community leaders and
household representatives visited the Kaeng Khoi 2 Power Plant and the other plants using
Environmental Report for submittal to ADB Nong-Saeng Power Plant Project Chapter 7 Power Generation Supply Co., Ltd. Information, Disclosure, Consultation and Participation
T-EIA208102 7-20 F208102Chap7E-ADB
natural gas as fuel and of the same size of Nong-Saeng Power Plant. The tour was
organized during November 10, 2007-June 15, 2008 for 19 trips with a total of 2,218
participants. The summary is presented in Table 7.5-4.
Order of the power plant tour
In order to make the tour members see the real picture and understand the
power generation process of the project, they were taken to visit the control room, air
monitoring station, stack, water treatment system and cooling tower. During the visit, there
were explanation and Q&A for making the tour members understand what they saw.
After touring, the tour members attended the lecture in a meeting room.
The lecture was related to the whole figure of the production process. This was to reinforce
their understanding. The presentation of the study and assessment of environmental
impacts of the project, including environmental measures was given. The final session was
for Q&A and opinion sharing of the tour members. The important issues from the meeting
were summarized in Table 7.5-5.
7.5.3 Presentation of the Study results and public hearing about
environmental measures (Second public hearing)
The study results of this part included the presentation and hearing of opinion
about social mitigative measures (The second time) and organization of public stage for
listening to people’s opinion. The results are as follows :
(1) Presentation and listening to opinion about the study results and
environmental measures.
The meeting activity for presentation and public hearing about the study
and EIA was to present the study results which are included in the EIA report before
starting the project. To obtain the opinion and suggestion from community leaders and
related persons led to information distribution to community members, making
understanding and acceptance of the study result and EIA. Thus the activity was organized
with the following objectives :
- To present the project details.
- To present the existing environmental resources of the project site and
its vicinity area which were potentially affected directly and indirectly
by the project.
Environmental Report for submittal to ADB Nong-Saeng Power Plant Project Chapter 7 Power Generation Supply Co., Ltd. Information, Disclosure, Consultation and Participation
T-EIA208102 7-21 F208102Chap7E-ADB
Table 7.5-4
Participants of the Tour to the Existing Power Plants
Date Place Participant Number
(person)
Nov 10, 2007 Kaengkoi 2 Power
Plant
- Community leaders and villager representatives of
Khok Sa-at, Nong-Kwai-So and Nong-Huapho
Sub-districts.
27
Nov 11, 2007 Kaengkoi 2 Power
Plant
- Community leaders and villager representatives of
Nong-Kob Sub-district.
47
Nov 13, 2007 Kaengkoi 2 Power
Plant
- Community leaders and villager representatives of
Nong-Kwai-So Sub-district.
58
Nov 14, 2007 Kaengkoi 2 Power
Plant
- Community leaders and villager representatives of
Nong-Kob, Nong-Lua and Nong-Tangbun Sub-districts.
87
Nov 25, 2007 Kaengkoi 2 Power
Plant
- Community leaders and villager representatives of
Nong-Kob, Nong-Lua and Nong-Tangbun Sub-districts.
60
Jan 31, 2008 Kaengkoi 2 Power
Plant
- Teachers and students of Nong-Saeng Wittaya School
of Saraburi Province.
216
Feb 3, 2008 Kaengkoi 2 Power
Plant
- Community leaders and villager representatives of
Nong-Namsai and Donyanang Sub-districts.
225
Feb 5, 2008 Kaengkoi 2 Power
Plant
- Community leaders and villager representatives of
Khok Muang and Pachee Sub-districts.
153
- Teachers and students of Pachee School and Donkhoi
School in Pachee District of Phra Nakhon Si
Ayutthaya Province.
71
Feb 17, 2008 Kaengkoi 2 Power
Plant
- Poultry farming groups of Pachee and Nong-Namsai
Sub-districts.
20
Feb 22, 2008 Kaengkoi 2 Power
Plant
- Community leaders and villager representatives of
Khotsasit Sub-district.
117
Feb 24, 2008 Kaengkoi 2 Power
Plant
- Community leaders and villager representatives of
Nong-Namsai Sub-district.
120
Mar 11, 2008 Kaengkoi 2 Power
Plant
- Community leaders and villager representatives of
Pachee Sub-district.
43
Mar 22-23,
2008
Kaengkoi 2 Power
Plant
- Community leaders and villager representatives of
Nong-Kob, Nong-Kwai-So, Khok Sa-at and Nong-
Huapho Sub-districts.
109
Environmental Report for submittal to ADB Nong-Saeng Power Plant Project Chapter 7 Power Generation Supply Co., Ltd. Information, Disclosure, Consultation and Participation
T-EIA208102 7-22 F208102Chap7E-ADB
Table 7.5-4 (Cont’d) Date Place Participant Number
(person)
Mar 22-23,
2008
Wangnoi Power
Plant/
Rayong Power
Plant/
Bangpakong
Power Plant
- Community leaders and villager representatives of
Nong-Kob, Nong-Kwai-So, Khok Sa-at and Nong-
Huapho Sub-districts in Nong-Saeng District.
110
Apr 30-May 1,
2008
Wangnoi Power
Plant/
Rayong Power
Plant
- Community leaders and villager representatives of
Nong-Namsai, Khok Muang and Rasom Sub-districts
in Pachee District.
151
May 3-4, 2008 Wangnoi Power
Plant/
Rayong Power
Plant
- Community leaders and villager representatives of
Pachee and Donyanang Sub-districts in Pachee
District.
157
May 17-18,
2008
Wangnoi Power
Plant/
Rayong Power
Plant
- Community leaders and villager representatives of
Nong-Kob and Nong Kwai-So Sub-districts
148
May 31- Jun 1,
2008
Wangnoi Power
Plant/
Rayong Power
Plant
- Community leaders and villager representatives of
Khok Toom and Phonthong Sub-districts.
157
Jun 14-15, 2008 Kaengkoi 2 Power
Plant/Wangnoi
Power Plant
- Community leaders of Rasom, Khok Muang,
Baanheep, Sambandit and Nongmaisung Sub-districts
in Uthai District of Phra Nakhon Si Ayutthaya.
142
Total 19 trips Total participants 2,218
Environmental Report for submittal to ADB Nong-Saeng Power Plant Project Chapter 7 Power Generation Supply Co., Ltd. Information, Disclosure, Consultation and Participation
T-EIA208102 7-23 F208102Chap7E-ADB
Table 7.5-5
Summary of Concern Issues, Suggestions and Corrective Method
of the Tour Group. Concern Issue Corrective Method/Environmental Mitigative Measures
- After the power plant is
operated, will the power plant
change to use other fuels?
- This power plant is designed to use only natural gas and diesel oil
and the license allows the plant to use only these two fuels.
- When diesel oil is used, as
backup fuel, will it cause the
odor impact?
- No odor problem is generated since the production system of the
power plant is designed as a closed-system.
- The quantity of pollutants in the stack emission must comply with
the standards of the related agencies.
- Does the magnetic field or
electromagnetic wave affect
electrical appliances and
people’s health?
- The previous study reported that there existed electromagnetic
wave under the 500 kV transmission line. Thus the power plant will
lay the grid networks underground within its area so the magnetic
field problem in the surrounding area will be reduced.
- Where is the water intake and
discharge? Does it affect the
agricultural sector?
- The water is pumped at the upstream of the Rama VI Dam and
stored for use in the dry season. So the plant will not compete for
water with people.
- The water is discharged to Huaiba (Klong Nong-Ngu-loem).
- Impact of foundation pile
hammering during construction
period
- The construction activity generating loud noise, e.g., foundation
pile hammering, etc., is to be conducted only in the daytime
(between 07.00 am.-18.00 pm.), be informed to communities and
officers of relevant offices at least 1 week before construction.
- It is necessary that the subcontractors must install a noise absorber
on loud noise generating machines used in the construction.
- Impact of noise generated from
the cooling towers of the power
plant
- The loud noise was heard in the area surrounding the cooling
towers only. No impact is imposed on the communities around the
power plant.
- Will the power plant discharge
the pollutants at night?
- No, the quantity of stack emissions from the power plant shall
comply with the standard of the related agencies.
- Will there be downstream
industries in the area?
- The power plant cannot sell electricity to other industries except to
the Electricity Generation Authority of Thailand only.
- Why this area is selected for
the power plant construction?
- There are 3 factors for power plant site selection;
1) near the transmission line
2) near water resources
3) near natural gas pipelines
Environmental Report for submittal to ADB Nong-Saeng Power Plant Project Chapter 7 Power Generation Supply Co., Ltd. Information, Disclosure, Consultation and Participation
T-EIA208102 7-24 F208102Chap7E-ADB
Table 7.5-5 (Continued) Concern issue Corrective Method/Environmental Mitigative Measures
- Will noise affect chickens? - In test run/construction periods, the loud noise is generated from
foundation pile hammering and stream pipeline cleaning. However,
there are noise protection equipments, and the operation time is
limited at 18.00 pm. The noise is generated for some times only.
- The test run plan is to be announced to people in advance.
- The poultry farm database in the area will be made in order to
assign the responsibility and damage compensation properly and
appropriately.
- There is a community development fund in the vicinity area of the
power plant.
- Is rain water drinkable? - If the rain water is drinkable at present, it will also be drinkable
when the power plant exists.
- The stack emissions from the power plant are controlled to be in
compliance with the standard of the relevant organizations.
Remark: At present, the Nong-Saeng Power Plant project is designed to recycle water for uses as much
as possible. The wastewater generated to be discharge is the effluent from the cooling towers
only. The other wastewater such as the sanitary wastewater from the offices and chemical
contaminated wastewater are treated and recycled. Some wastewater is treated by using high
quality treatment system, e.g., thermal evaporation, which can recycle the whole effluent. The
solid wastes is the residue in the final stage which is to be disposed according to the regulation
of the Ministry of Industry entitled Disposal of Sewage and Unused Materials, B.E.2548.
Environmental Report for submittal to ADB Nong-Saeng Power Plant Project Chapter 7 Power Generation Supply Co., Ltd. Information, Disclosure, Consultation and Participation
T-EIA208102 7-25 F208102Chap7E-ADB
- To present the impact evaluation of the project both qualitatively and
quantitatively for each issue during the construction and operation
periods. The positive and negative impacts of the project were
assessed.
- To present the environmental mitigative measures for construction and
operation periods in order to reduce the impacts as much as possible.
- To present the monitoring programme of environmental quality. This
aimed to have surveillance of the implementation of the purposed
mitigative masures.
- To obtain the opinion-suggestion and to answer the questions about
the project asked by participants.
Schedule/place/media and participants
- The places for the public hearing activity of the communities were
selected from the area within the radius of 5 kilometers from the
project. The area covered 12 subdistricts in 3 districts of 2 provinces.
There were 10 meeting stages with 1,005 participants, as shown in
Table 7.5-6.
- The media for meeting supplements included the following :
• Project presentation documents which consisted of the project
background, project details, methodology of study and EIA report
preparation, conclusion of the existing environmental conditions,
environmental impact assessment, environmental mitigative
measures and monitoring programme of environmental quality.
• Illustration and presentation by power point presentation containing
the project background, work plan, project size and location,
capacity, electricity generation process, fuel utilization, raw water
resource, water supply system, wastewater and wastewater
treatment system, air pollution control system, solid wastes
management, study results and EIA, environmental mitigative
measures, and monitoring programme of environmental quality.
Environmental Report for submittal to ADB Nong-Saeng Power Plant Project Chapter 7 Power Generation Supply Co., Ltd. Information, Disclosure, Consultation and Participation
T-EIA208102 7-26 F208102Chap7E-ADB
Table 7.5-6
The Meeting for Result Presentation and the Second Public Hearing
Nong-Saeng Power Plant Project
Date/Time Place Participant Number
(person)
Jan 20, 2008
03.00-06.00 p.m.
Nong-Namsai Sub-district at Nong-Namsai
TAO, Pachee District of Phra Nakhon Si
Ayutthaya Province
- Community leaders
- Local people
117
Jan 21, 2008
09.00-12.00 a.m.
Donyanang Sub-district at Wat
Wimolsoonthorn, Donyanang Subdistrict,
Pachee District of Phra Nakhon Si Ayutthaya
Province
- Community leaders
- Local people
64
Jan 22, 2008
09.00-12.00 a.m.
Nong-Huapho Sub-district at Ban
Khoksamor, Nong-Saeng District of Saraburi
Province
- Community leaders
- Local people
42
Jan 23, 2008
09.00-12.00 a.m.
Khok Muang Sub-district at Khok Muang
TAO, Pachee district of Phra Nakhon Si
Ayutthaya Province
- Community leaders
- Local people
68
Jan 26, 2008
05.00-07.00 p.m.
Khok Toom and Phonthong Sub-districts at
Wat Suntiwiharn, Khok Toom Sub-district,
Nong-Saeng District of Saraburi Province
- Community leaders
- Local people
129
Jan 27, 2008
03.00-06.00 p.m.
Rasom Sub-district at Wat Rakhen, Rasom
Subdistrict, Pachee District of Phra Nakhon
Si Ayutthaya Province
- Community leaders
- Local people
102
Jan 29, 2008
09.00-12.00 a.m.
Khok Sa-at Sub-district at Wat Ngew-ngarm,
Khok Sa-at Sub-district, Nong-Saeng District
of Saraburi Province
- Community leaders
- Local people
49
Jan 30, 2008
9.00-12.00 a.m.
Kotchasit Sub-district at Kotchasit MD,
Nong-Kae District of Saraburi Province
- Community leaders
- Local people
151
Feb 2, 2008
03.00-06.00 p.m.
Nong-Kob and Nong-Kwai-So Sub-districts
at Wat Nong-Kob, Nong-Kob Sub-district,
Nong-Saeng District of Saraburi Province
- Community leaders
- Local people
215
Feb 13, 2008
09.00-12.00 a.m.
Pachee Sub-district at Pachee District Office
of Phra Nakhon Si Ayutthaya Province
- Community leaders
- Local people
68
Total 10 stages Total participants 1,005
Environmental Report for submittal to ADB Nong-Saeng Power Plant Project Chapter 7 Power Generation Supply Co., Ltd. Information, Disclosure, Consultation and Participation
T-EIA208102 7-27 F208102Chap7E-ADB
Order of the meeting
The meeting for presentation of the study results and for obtaining
opinion about the study results and EIA was divided into 4 parts by activity nature as
follows :
- Meeting opening speech.
- Presentation of the project details, and the study results and EIA.
- Listening to opinion/suggestion from participants.
- Conclusion and closing speech.
Answering questions and brainstorming from participants
In every meeting stage, after presentation of the project details and the
study results, the participants were allowed to ask questions, express their concerns and
give useful suggestion for revising the of environmental measures of the project. The
consultant company accompanying with the Power Generation Supply Co., Ltd. to answer
the questions. Summary of the important issues is given in Table 7.5-7.
Results of questionnaire answering in the meeting
In every meeting stage, apart from asking questions, the participants
filled in a questionnaire. This was to reflect their opinion and to give suggestion about
environmental mitigative measures proposed in the EIA. In the second public hearing of 10
stages, there were 505 out of 1,005 participants (52.4%) answered the questionnaire. The
detail of evaluation results, given in Appendix VI are summarized below.
- Physical environmental resource issue
• Measures for air quality and particulates
: During construction period, most of respondents (61.8%) told
that the measures were sufficient. However, most participants
from Pachee and Khok Sa-at, and Nong-Huapho Sub-districts
(62.2% and 60.0%, respectively) had no comments.
: During operation period, most of respondents (61.6%) thought
that the measures were sufficient. Most participants from Khok
Sa-at and Nong-Huapho, and Pachee Sub-districts (70.0% and
62.2%, respectively) had no comments.
T-EIA208102
7-28
F208102Chap7E-A
DB
Environmental Report for subm
ittal to ADB
Nong-Saeng Pow
er Plant Project Chapter 7
Power G
eneration Supply Co., Ltd. Inform
ation, Disclosure, C
onsultation and Participation
Table 7.5-7
Summary of Concern Issues, Corrective Method and Suggestion from the Second Public Hearing
Nong-Saeng Power Plant Project
Stage Area Concern Issue Corrective Method / Environmental Mitigative Measures Suggestion from
Participants
1. Nong-
Namsai
Sub-district
- Does sulfur dioxide emission
from the stack have any
impacts?
- The quantity of stack emissions discharged from the power plant will be
strictly enforced under the regulation.
- From the study, it was found that after the power plant operation, the SO2
and NO2 concentrations in the ambient air were lower than the standard.
The particulates emission from the power plant was very low.
- The power plant
tour should be
organized and the
experts (not the
power plant staff)
explain the
information of the
power plant.
- Why is this area selected for
power plant construction?
- There are 3 factors for the power plant site selection including 1) near the
power transmission line, 2) near water resources and 3) near natural gas
pipelines.
- Does the effluent affect the
people and agriculture?
- The effluent quality was controlled according to the Order of Department
of Irrigation No.883/2532 (1989) entitled “Prevention and resolution for
drainage of low quality water to irrigation canals and other canals joint to
them in the irrigation zones”. By this standard, the effluent drained from
the power plant does not affect the people and agricultural crops.
- The effluent quality monitoring station will be installed. If the drained
effluent quality exceeds the standard, the valve will be automatically
turned off so that the effluent cannot be drained to the outside, but
retreated until its quality is in compliance.
- In case of natural gas shortage,
which fuel will be used in
electricity generation?
- This power plant is designed to use natural gas as main fuel and diesel oil
as backup fuel. The power plant will be shut down if the natural gas is
run out.
T-EIA208102
7-29
F208102Chap7E-A
DB
Environmental Report for subm
ittal to ADB
Nong-Saeng Pow
er Plant Project Chapter 7
Power G
eneration Supply Co., Ltd. Inform
ation, Disclosure, C
onsultation and Participation
Table 7.5-7 (Cont’d)
Stage Area Concern Issue Corrective Method / Environmental Mitigative Measures Suggestion from
participants
1. Nong-
Namsai
Sub-district
(Cont’d)
- There is a contract of natural gas purchasing among 3 organizations, i.e.,
the power plant, PTT (Public) Co., Ltd. and EGAT. It is hardly to change
the fuel.
- Is there noise pollution? Does
heat generated from the power
plant have impacts?
- Noise pollution
• During construction period, the assessment revealed that the sound
pressure levels at Wat Thammasinsopha and houses next to the project
fence exceeded the standard. Therefore, the mitigative measure will be
assigned.
• During operation period, the assessment revealed that the sound
pressure levels were predicted to be lower than the standard. The noise
annoyance might occur occasionally. Therefore, the mitigative
measure will be assigned.
• The important measures include the installation of noise adsorbents,
installing of the noisy machines in the noise adsorbent buildings and
installation of enclosure, ect.
- Heat is mainly generated at the stack of the power plant. The heat is
buoyant and its temperature is reduced and dissipated by wind current.
This does not cause sensible temperature change.
- What will Nong-Namsai people
get from the power plant?
- They will get money allocated to the local community via
• Property and machinery taxes.
• Value added taxes of gas purchasing from PTT and electricity sale to
EGAT.
T-EIA208102
7-30
F208102Chap7E-A
DB
Environmental Report for subm
ittal to ADB
Nong-Saeng Pow
er Plant Project Chapter 7
Power G
eneration Supply Co., Ltd. Inform
ation, Disclosure, C
onsultation and Participation
Table 7.5-7 (Cont’d)
Stage Area Concern Issue Corrective Method / Environmental Mitigative Measures Suggestion from
participants
1. Nong-
Namsai
Sub-district
(Cont’d)
- The community development fund was founded in the plant vicinity area
(during construction and operation periods). This is the pay back to the
communities that sacrifice the area for the power plant.
- The community utilities are improved.
- The economic system is stimulated continuously in the communities.
- Will local people be employed?
What kind of jobs and how
many?
- For the recruitment by examination, if the locals have scores higher or
lower but close to that of the candidates from outside, the locals will get
the priority. However, in the case of too low scores, the locals will be refused due to security and safety of the power plant.
- There are approximately 70 permanent staff.
2. Donyanang
Sub-district
- Where does the power plant
discharge the effluent?
- The effluent is discharged into Rapeepat Canal in front of the project site.
The pH values, conductivity, free chlorine and temperature of the effluent
were controlled to comply with the standard of the governmental office.
No comments
- Does the water consumption of
the power plant affect the people
and rice farming?
- The effluent quality was controlled according to the Order of Department
of Irrigation No.883/2532 (1989) entitled “Prevention and resolution for
drainage of low quality water to irrigation canals and other canals joint to
them in the irrigation zones”. Regarding this standard, the effluent
drained from the power plant does not affect the people and agricultural
crops.
- The effluent quality monitoring station will be installed. If the drained
effluent quality exceeds the standard, the valve will be automatically
turned off so that the effluent cannot be drained to the outside, but
retreated until its quality is in compliance.
T-EIA208102
7-31
F208102Chap7E-A
DB
Environmental Report for subm
ittal to ADB
Nong-Saeng Pow
er Plant Project Chapter 7
Power G
eneration Supply Co., Ltd. Inform
ation, Disclosure, C
onsultation and Participation
Table 7.5-7 (Cont’d)
Stage Area Concern Issue Corrective Method / Environmental Mitigative Measures Suggestion from
participants
2. Donyanang Sub-district
- The power plant will construct a water well of 1.6 million cubic meter
capacity, which can be used for 30 days without taking water from other
natural water resources. This will not affect water utilization of people. In
case of water shortage, the Department of Irrigation will order the power
plant to stop pumping water.
- What benefits will people get
from the power plant?
- The money allocated to the local communities are obtained from
• Property and machinery taxes.
• Value added taxes of gas purchasing from PTT and electricity sale to
EGAT.
- The community development fund was founded in plant vicinity area.
(during construction and operation periods). This is the pay back to the
communities that sacrifice the area for the power plant.
- The community utilities are improved.
- The economic system is stimulated continuously in the communities.
- For water in the Rapeepat Canal,
will it cause itching when it is
used by villagers?
- The effluent quality was controlled according to the Order of Department
of Irrigation No.883/2532 (1989) entitled “Prevention and resolution for
drainage of low quality water to irrigation canals and other canals joint to
them in the irrigation zones”. By this standard, the effluent drained from
the power plant does not affect the people and agricultural crops.
- The effluent quality monitoring station will be intalled. If the drained
effluent quality exceeds the standard, the valve will be automatically
turned off so that the effluent cannot be drained to the outside, but retreated until its quality is in compliance.
T-EIA208102
7-32
F208102Chap7E-A
DB
Environmental Report for subm
ittal to ADB
Nong-Saeng Pow
er Plant Project Chapter 7
Power G
eneration Supply Co., Ltd. Inform
ation, Disclosure, C
onsultation and Participation
Table 7.5-7 (Cont’d)
Stage Area Concern Issue Corrective Method / Environmental Mitigative Measures Suggestion from
participants
2. Donyanang Sub-district (Cont’d)
- How is the fund allocated to each village?
- It depends on consideration of the fund committee. - The fund committee consists of the representatives of villagers in the area
of 5 kilometers radius from the project, representatives of governmental sectors and the power plant. The number of villager representatives is more than a half of total committee members.
3. Khok Muang Sub-district
- Why is the treated effluent not reused in the power plant? Has the treated effluent been used for agricultural experiment?*
- When the water is used in several processes, its temperature is changed and the minerals in water become scaling as found in vehicle radiators. The scaling is hard to be removed. Thus the power plant has studied about how many cycles the water can be used (4 cycles) before being treated to comply with the standard of the governmental office prior to discharge.
- A demonstrated rice field should be set up in the area around the power plant.
- The electricity fee for the people living in the area within the radius of 5 kilometers should be waived.
- What is the pH value of the discharge effluent?
- The pH value of the effluent is controlled to be 6.5-8.5 according to the Order of Department of Irrigation No.883/2532 (1989) entitled “Prevention and resolution for drainage of low quality water to irrigation canals and other canals joint to them in the irrigation zones”. By this standard, the discharged effluent from the power plant will not affect general water consumption.
- Does the power plant impose the impacts on water quality and air quality?
- The pH value of the effluent is controlled to be 6.5-8.5 according to the Order of Department of Irrigation No.883/2532 (1989) entitled “Prevention and resolution for drainage of low quality water to irrigation canals and other canals joint to them in the irrigation zones”.
Remark: At present, the Nong-Saeng Power Plant project is designed to recycle water for uses as much as possible. The wastewater generated to be discharge is the effluent from the cooling towers only. The other wastewater such as the sanitary wastewater from the offices and chemical contaminated wastewater are treated and recycled. Some wastewater is treated by using high quality treatment system, e.g., thermal evaporation, which can recycle the whole effluent. The solid wastes is the residue in the final stage which is to be disposed according to the regulation of the Ministry of Industry entitled Disposal of Sewage and Unused Materials, B.E.2548.
T-EIA208102
7-33
F208102Chap7E-A
DB
Environmental Report for subm
ittal to ADB
Nong-Saeng Pow
er Plant Project Chapter 7
Power G
eneration Supply Co., Ltd. Inform
ation, Disclosure, C
onsultation and Participation
Table 7.5-7 (Cont’d)
Stage Area Concern Issue Corrective Method / Environmental Mitigative Measures Suggestion from
participants
3. Khok
Muang
Sub-district
(Cont’d)
- The effluent quality monitoring station will be installed. If the drained
effluent quality exceeds the standard, the valve will be automatically
turned off so that the effluent cannot be drained to the outside, but
retreated until its quality is in compliance.
- The content of pollutants released from the power plant chimney must
follow the regulation of the relevant organizations.
- From the study, it was found that after the power plant operation, the SO2
and NO2 concentrations in the ambient air were lower than the standard.
The particulates emission from the power plant was very low.
- Does the power plant cause
magnetic wave/radiation? Does
the magnetic wave/radiation
affect the community?
- The previous study reported that there existed electromagnetic wave
under the 500 kV transmission line. Thus the power plant will lay the grid
networks underground within its area, so the magnetic field problem in
the surrounding area will be reduced.
- When the power plant exists, is
the rain water consumable?
- The pollutants discharged from the power plant are strictly controlled by
the standards of the relevant governmental offices. Thus, no impacts are
imposed on consumable water.
- Does the power plant generated
soot? Does it cause any impacts?
- The content of pollutants released from the power plant must be followed
the regulation of the relevant governmental offices.
- From the study, it was found that after the power plant operation, the SO2
and NO2 concentrations in the ambient air were lower than the standard.
The particulates emission from the power plant was very low.
T-EIA208102
7-34
F208102Chap7E-A
DB
Environmental Report for subm
ittal to ADB
Nong-Saeng Pow
er Plant Project Chapter 7
Power G
eneration Supply Co., Ltd. Inform
ation, Disclosure, C
onsultation and Participation
Table 7.5-7 (Cont’d)
Stage Area Concern Issue Corrective Method / Environmental Mitigative Measures Suggestion from
participants
3. Khok
Muang
Sub-district
(Cont’d)
- Do the people living around the
power plant have health
problem? Will they be barren?
- The effluent quality was controlled according to the Order of Department
of Irrigation No.883/2532 (1989) entitled “Prevention and resolution for
drainage of low quality water to irrigation canals and other canals joint to
them in the irrigation zones”. Regarding this standard, the effluent
drained from the power plant does not affect the people and agricultural
crops.
- The concentrations of the stack emissions from the power plant must
comply with the standard of the relevant governmental offices.
- The health data of all families in the study area before project operation
were collected and compared to those after plant operation.
- Who are the committee to be
assigned for inspecting the
power plant?
- The committee will be selected from the people and the environmental
inspector will be appointed for inspecting the power plant operation. The
power plant will support the training budget. The term for the committee
and the inspector is 2 years.
- If the power plant operation is
found to discharge the pollutants
exceeding the standard, will the
power plant be shut down?
- In normal practice, if the machines in the power plant are not operating
according to the standard, they will be automatically turned off.
- From the study, it was found that after the power plant operation, the SO2
and NO2 concentrations in the ambient air were lower than the standard.
The particulates emission from the power plant was very low.
- Noise impact - During construct period, some noisy activities generating loud noise are
foundation pile hammering and test run of the machines. These activities
will be informed to people in advance.
- A plan for surveying chicken farms and households in the plant vicinity
area is set up to evaluate the impacts.
T-EIA208102
7-35
F208102Chap7E-A
DB
Environmental Report for subm
ittal to ADB
Nong-Saeng Pow
er Plant Project Chapter 7
Power G
eneration Supply Co., Ltd. Inform
ation, Disclosure, C
onsultation and Participation
Table 7.5-7 (Cont’d)
Stage Area Concern Issue Corrective Method / Environmental Mitigative Measures Suggestion from
participants
3. Khok
Muang Sub-
district
(Cont’d)
- Installation of noise reductions equipments, noise adsorbent wall.
- The noise generating activities are occasionally conducted.
- During operated period, the noise level will be controlled not to exceed
the standard. The noise levels will be measured at the fence.
- Will the life style of the villages
be changed?
- It will be changed. The impacts will be studied during construction and
operation periods.
- The community utilities are improved.
- The economy system will be stimulated continuously.
- The fund for community development in the area around the power plant
will be set up for immediate compensation of any damages without
evidence approval.
- Why is this area selected for the
power plant construction?
- There are 3 factors for the power plant site selection including 1) near the
power grids 2) near water resources and 3) near natural gas pipelines.
- Are there impacts on respiratory
system?
- The content of stack emission from the power plant must comply with the
standards of the relevant governmental offices.
- Will the employment be
available for the locals?
- For the recruitment by examination, if the locals have scores higher or
lower but close to that of the candidates from outside, the locals will get
the priority. However, in the case of too low scores, the locals will be
refused due to security and safety of the power plant.
- Will the minerals in the water be
reduced?
- The essential minerals in the water remain the same.
- At present, the Kaengkoi 2 Power Plant uses the water for plant watering
without any impacts.
T-EIA208102
7-36
F208102Chap7E-A
DB
Environmental Report for subm
ittal to ADB
Nong-Saeng Pow
er Plant Project Chapter 7
Power G
eneration Supply Co., Ltd. Inform
ation, Disclosure, C
onsultation and Participation
Table 7.5-7 (Cont’d)
Stage Area Concern Issue Corrective Method / Environmental Mitigative Measures Suggestion from
participants
4. Khok Toom
and
Phonthong
Sub-districts
- Will the discharged effluent
affect aquatic animals and fresh
water fishery?
- The effluent quality was controlled according to the Order of Department
of Irrigation No.883/2532 (1989) entitled “Prevention and resolution for
drainage of low quality water to irrigation canals and other canals joint to
them in the irrigation zones”. Regarding this standard, the effluent
drained from the power plant does not affect the people and agricultural
crops.
- The effluent quality monitoring station will be installed. If the drained
effluent quality exceeds the standard, the valve will be automatically
turned off so that the effluent cannot be drained to the outside, but
retreated until its quality is in compliance.
- The sub-meeting
with animal husbandry
groups should be
organized.
- The warning system
for leaked natural
gases should be
installed.
- Air quality
inspection should be
done before the
project starts. - Will the power plant generate
more dust?
- The content of pollutants released from the power plant chimney must
follow the regulation of the relevant governmental offices.
- From the study, it was found that after the power plant operation, the SO2
and NO2 concentrations in the ambient air were lower than the standard.
The particulates emission from the power plant was very low.
- How is the air quality
monitored? If it affects
occupation, what are the
preventive and corrective
measures?
- There are 4 air quality monitoring stations, i.e., Wat Nong-Tangbun, Wat
Nongkratart, Wat Khok Muang and Wat Khok Daeng, which were
installed before the construction period. The monitoring is conducted
every 6 months during the construction and operation periods.
- There are 4 permanent and continuous air quality monitoring stations in 4
communities.
- From the monitoring results and impact evaluation of air quality, it was
found that all measured values were in compliance. However, the stack
emission concentrations will be controlled to comply with the regulation
T-EIA208102
7-37
F208102Chap7E-A
DB
Environmental Report for subm
ittal to ADB
Nong-Saeng Pow
er Plant Project Chapter 7
Power G
eneration Supply Co., Ltd. Inform
ation, Disclosure, C
onsultation and Participation
Table 7.5-7(Cont’d)
Stage Area Concern Issue Corrective Method / Environmental Mitigative Measures Suggestion from
participants
4. Khok Toom
and
Phonthong
Sub-districts
(Cont’d)
of the related agencies. The plant will be automatically shutdown in case
of failure of pollution control systems.
- In case of water shortage, what
are the preventive and corrective
measures?
- The power plant has a water well which can store water for uses in 30
days without any additional pumping in. The water will be pumped into
the well in the rainy season only.
- Why is the effluent discharged? - When the water is used in several processes, its temperature is changed
and the minerals in water become scaling as found in vehicle radiators.
The scaling is hard to be removed. Thus the power plant has studied
about how many cycles the water can be used (4 cycles) before being
treated to comply with the standard of the governmental office prior to
discharge.
5. Rasom
Sub-district
- In case of the affected people
from the power plant, how will
they get compensation from the
fund? And where will they get
from?
- The fund for development of the area around the power plant will be set
up for immediate compensation of any damages without evidence
approval.
- The contact person for the case of compensation is the fund committee.
No comments
- Can the power plant use solar
cell?
- This power plant was designed to use only natural gas and diesel oil as
fuels. It is thus difficult to change to the other fuels.
- Is the discharged effluent salty?
Will it affect young trees (wild
trees)?
- The effluent quality was controlled according to the Order of Department
of Irrigation No.883/2532 (1989) entitled “Prevention and resolution for
drainage of low quality water to irrigation canals and other canals joint to
them in the irrigation zones”. Regarding this standard, the effluent
drained from the power plant does not affect the people and agricultural
crops.
T-EIA208102
7-38
F208102Chap7E-A
DB
Environmental Report for subm
ittal to ADB
Nong-Saeng Pow
er Plant Project Chapter 7
Power G
eneration Supply Co., Ltd. Inform
ation, Disclosure, C
onsultation and Participation
Table 7.5-7 (Cont’d)
Stage Area Concern Issue Corrective Method / Environmental Mitigative Measures Suggestion from
participants
5. Rasom Sub-district (Cont’d)
- The effluent quality monitoring station will be installed. If the drained effluent quality exceeds the standard, the valve will be automatically turned off so that the effluent cannot be drained to the outside, but retreated until its quality is in compliance.
6. Khok Sa-at and Nong-Huapho Sub-districts
No concerns No measures. No comments
7. Khotsasit Sub-district
- Do the proposed measures exist in the contract with the governmental sector?
- The proposed measures are presented in the EIA report which will be strictly implemented by the power plant. If there are additional suggestions, they can be added to the report.
- The public meeting should be organized with people in this TAO. - Will the life style of the
villagers be changed? - It will be changed. The impact will be studied during construction and
operation periods. - The community utilities are improved. - The economy system will be stimulated continuously. - The fund for community development in the area around the power plant
will be set up for immediate compensation of any damages without evidence approval.
- Some areas will be changed to industrial zones but the original agricultural area will be able to use for agriculture as usual.
- In order that the locals can have participation and higher quality of life, how is the company recruitment policy like?
- For the recruitment by examination, if the locals have scores higher or lower but close to that of the candidates from outside, the locals will get priority. However, in the case of too low scores the locals will be refused due to security and safety of the power plant.
- To support scholarship to poor children.
T-EIA208102
7-39
F208102Chap7E-A
DB
Environmental Report for subm
ittal to ADB
Nong-Saeng Pow
er Plant Project Chapter 7
Power G
eneration Supply Co., Ltd. Inform
ation, Disclosure, C
onsultation and Participation
Table 7.5-7 (Cont’d)
Stage Area Concern Issue Corrective Method / Environmental Mitigative Measures Suggestion from
participants
7. Khotsasit
Sub-district
(Cont’d)
- Why is the treated effluent not
recycled?*
- When the water is used in several processes, its temperature is changed
and the minerals in water become scaling as found in vehicle radiators.
The scaling is hard to be removed. Thus the power plant has studied
about how many cycles the water can be used (4 cycles) before being
treated to comply with the standard of the governmental office prior to
discharge.
- How is the committee
appointed?
- At first, the committee will be selected by local people. This committee
will designate guideline and regulation of the committee. Later, when
there is a fund for community development in the plant vicinity area.
There will be a committee to manage the fund.
8. Nong-Kob
and Nong-
Kwai-So
Sub-districts
- Potential impacts to be
imposed by the power plant.
- The impacts during construction and operation periods are to be studied
and community the mitigative measures be assigned.
- The fund for community development of the area around the power plant
will be set up for immediate compensation of any damages immediately
without evidence approval.
- The site should be
moved to the area
north of Chaopraya
River.
- The data of relevant
Remark: At present, the Nong-Saeng Power Plant project is designed to recycle water for uses as much as possible. The wastewater generated to be discharge is the effluent from the cooling towers only. The other wastewater such as the sanitary wastewater from the offices and chemical contaminated wastewater are treated and recycled. Some wastewater is treated by using high quality treatment system, e.g., thermal evaporation, which can recycle the whole effluent. The solid wastes is the residue in the final stage which is to be disposed according to the regulation of the Ministry of Industry entitled Disposal of Sewage and Unused Materials, B.E.2548.
T-EIA208102
7-40
F208102Chap7E-A
DB
Environmental Report for subm
ittal to ADB
Nong-Saeng Pow
er Plant Project Chapter 7
Power G
eneration Supply Co., Ltd. Inform
ation, Disclosure, C
onsultation and Participation
Table 7.5-7 (Cont’d)
Stage Area Concern Issue Corrective Method / Environmental Mitigative Measures Suggestion from
participants
8. Nong-Kob
and Nong-
Kwai-So Sub-
districts
(Cont’d)
- Were the values measured before the beginning of the project? What are the monitoring values during construction and operation periods?
- The impacts in constructing and operating periods will be studied and the protective and solving measures will be assigned.
- The effluent quality is controlled according to the Order of Department of
Irrigation No.883/2532 (1989) entitled “Prevention and resolution for drainage of low quality water to irrigation canals and other canals joint to
them in the irrigation zones”. Regarding this standard, the effluent
drained from the power plant does not affect the people and agricultural crops.
- The consultant company has collected some basic data, such as surface water samples, pH value, suspended solids, etc. These data will be references for data comparison in the periods before and after the power plant operation.
organizations such
as provincial
industry office,
provincial health
office, etc., should
be revealed and
compared in the
periods before and
after the power plant
operation.
- The final EIA report should be submitted to people.
- The governmental office representatives should participate in the meeting.
- Will the power plant affect way of life/ occupation/ health of the villagers?
- The power plant surrounding area will be developed. - The health data of people in various areas around the power plant were
monitored and the health data of every household were collected before having the project.
- The fund for community development in the area around the power plant will be set up for immediate compensation of any damages without evidence approval.
- How are the impacts on water quality, air quality and soil?
- The effluent quality is controlled according to the Order of Department of Irrigation No.883/2532 (1989) entitled “Prevention and resolution for drainage of low quality water to irrigation canals and other canals joint to them in the irrigation zones”.
- The concentrations of stack emissions from the power plant must comply with the regulation of the relevant governmental offices.
T-EIA208102
7-41
F208102Chap7E-A
DB
Environmental Report for subm
ittal to ADB
Nong-Saeng Pow
er Plant Project Chapter 7
Power G
eneration Supply Co., Ltd. Inform
ation, Disclosure, C
onsultation and Participation
Table 7.5-7 (Cont’d)
Stage Area Concern Issue Corrective Method / Environmental Mitigative Measures Suggestion from
participants
8. Nong-Kob
and Nong-
Kwai-So
Sub-districts
(Cont’d)
Why is this area selected for the
power plant construction?
- There are 3 factors for the power plant site selection including 1) near the power transmission line, 2) near water resources and 3) near natural gas pipelines.
- The power plant has appropriate mitigative measures for the site location.
9. Pachee
Sub-district
- Is the effluent from cooling towers recycled?*
- When the water is used in several processes, its temperature is changed and the minerals in water become scaling as found in vehicle radiators. The scaling is hard to be removed. Thus the power plant has studied about how many cycles the water can be used (4 cycles) before being treated to comply with the standard of the governmental office prior to discharge.
No comments
- Are the measures given in the EIA report social contract?
- The propose measures in the EIA report are to be strictly implemented by the power plant.
Note: At present, the Nong-Saeng Power Plant project is designed to recycle water for uses as much as possible. The wastewater generated to be discharge is the effluent from the cooling towers only. The other wastewater such as the sanitary wastewater from the offices and chemical contaminated wastewater are treated and recycled. Some wastewater is treated by using high quality treatment system, e.g., thermal evaporation, which can recycle the whole effluent. The solid wastes is the residue in the final stage which is to be disposed according to the regulation of the Ministry of Industry entitled Disposal of Sewage and Unused Materials, B.E.2548.
Environmental Report for submittal to ADB Nong-Saeng Power Plant Project Chapter 7 Power Generation Supply Co., Ltd. Information, Disclosure, Consultation and Participation
T-EIA208102 7-42 F208102Chap7E-ADB
• Measures for noise
: During construction period, most of respondents (60.0%)
thought that the measures were sufficient. However, most
participants from Pachee and Khok Sa-at, and Nong-Huapho
Sub-districts (70.0% and 62.20%, respectively) had no comments.
: During operation period, most of respondents (61.6%) thought
that the measures were sufficient. Most participants from Khok
Sa-at and Nong-Huapho, and Pachee Sub-districts (70.0% and
62.2%, respectively) did not show any comments.
• Measures for hydrology condition and surface water quality
: During construction period, most of respondents (60.0%)
thought that the measures were sufficient. However, those from
Khok Sa-at and Nong-Huapho, and Pachee Sub-districts (70.0%
and 67.6%, respectively) had no comments.
: During operation period, most of respondents (59.8%) thought
that the measures were sufficient. However, those from Khok
Sa-at and Nong-Huapho and Pachee Sub-districts (70.0% and
67.6%, respectively) did not have comments.
• Measures for groundwater water quality
: During construction period, most of respondents (60.8%)
thought that the measures were sufficient. However, those from
Khok Sa-at and Nong-Huapho, and Pachee Sub-districts (70.0%
and 62.2%, respectively) had no comments.
: During operation Period, most of respondents (60.0%) thought
that the measures were sufficient. However those from Khok Sa-
at and Nong-Huapho, and Pachee Sub-districts (70.0% and
64.9%, respectively) did not have any comments.
- Biological environmental resource issue
• Measures for water ecology
: During construction period, most of respondents (58.0%)
thought that the measures were sufficient. However, those
participants from Pachee and Khok Sa-at, and Nong-Huapho
Sub-districts (67.6% and 60.0%, respectively) had no comments.
Environmental Report for submittal to ADB Nong-Saeng Power Plant Project Chapter 7 Power Generation Supply Co., Ltd. Information, Disclosure, Consultation and Participation
T-EIA208102 7-43 F208102Chap7E-ADB
: During operation period, most of respondents (55.8%) thought
that the measures were sufficient. However those from Pachee
and Kotchasit Sub-districts (67.6% and 61.0%, respectively) did
not show any comments.
- Human uses by issue
• Measures for land utilization
: During construction period, most of respondents (57.2%)
thought that the measures were sufficient. However, those from
Pachee and Khok Sa-at, and Nong-Huapho Sub-districts (70.3%
and 60.0%, respectively) had no comments.
• Measures for traffic and transportation
: During construction period, most of respondents (56.0%)
thought that the measures were sufficient. However, those
participants from Pachee and Khok Sa-at, and Nong-Huapho
Sub-districts (70.3% and 60.0%, respectively) had no comments.
: During operation period, most of respondents (55.8%) thought
that the measures were sufficient. However, those from Pachee
and Kotchasit Sub-districts (70.3% and 60.0%, respectively) did
not have any comments.
• Measures for drainage and flood control
: During construction period, most of respondents (55.5%)
thought that the measures were sufficient. However, those from
Pachee and Khok Sa-at, and Nong-Huapho Sub-districts (70.3%
and 60.0%, respectively) had no comments.
: During operation period, most of respondents (56.0%) thought
that the measures were sufficient. However, those from Pachee
and Kotchasit Sub-districts (70.3% and 60.0%, respectively) did
not have any comments.
• Measures for solid waste management
: During construction period, most of respondents (54.3%)
thought that the measures were sufficient. However, those from
Environmental Report for submittal to ADB Nong-Saeng Power Plant Project Chapter 7 Power Generation Supply Co., Ltd. Information, Disclosure, Consultation and Participation
T-EIA208102 7-44 F208102Chap7E-ADB
Pachee, Khok Sa-at and Nong-Huapho Sub-districts (70.3% and
60.0%, respectively) had no comments.
: During operation period, most of respondents (56.6%) thought
that the measures were sufficient. However, those from Pachee
and Kotchasit Sub-districts (67.6% and 60.0%, respectively) did
not have any comments.
- Value of life quality issue
• Measures for economy-society and people participation
: During construction period, most of respondents (57.2%)
thought that the measures were sufficient. However, those from
Pachee and Khok Sa-at, and Nong-Huapho Sub-districts (67.6%
and 60.0%, respectively) had no comments.
: During operation period, most of respondents (56.8%) thought
that the measures were sufficient. However, those from Pachee
and Kotchasit Sub-districts (64.9% and 60.0%, respectively) did
not have any.
• Measures for public health, occupational health and safety
: During construction period, most respondents (54.9%) thought
that the measures were sufficient. However, those from Pachee,
Khok Sa-at and Nong-Huapho Sub-districts (67.6% and 60.0%,
respectively) had no comments.
: During operation period, most of respondents (55.5%) thought
that the measures were sufficient. However, those from Pachee
and Kotchasit Sub-districts (64.9% and 60.0%, respectively) did
not have any comments.
- Other opinions and suggestions about the project
• To take care of the nearby and affected communities fairly and
continually.
• All people should join the power plant tour.,
• To take care of villager’s health, for example, to have monthly
physical examination, etc.
• To routinely monitor water quality.
Environmental Report for submittal to ADB Nong-Saeng Power Plant Project Chapter 7 Power Generation Supply Co., Ltd. Information, Disclosure, Consultation and Participation
T-EIA208102 7-45 F208102Chap7E-ADB
• To regularly keep the safety standard and implement the measures
to reduce the impacts,
• To conduct public relation for people to clearly understand the
principles and the potential impacts and to organize training on
reading of monitoring results.
• To encourage people to participate in activities or making
careers/income for local people.
Minutes of the 10 meeting stages were made by the study team. The
minutes were placarded at 12 TAO offices in the study area, subdistrict header offices,
Nong-Saeng and Nong-Kae District Offices in Saraburi and Pachee District Office in Phra
Nakhon Si Ayutthaya. This was to inform people who did not join the meeting to know about
the minutes. The additional public hearing was also opened via postal communication. The
address and telephone number of the consultant company were given. The company also
coordinated to get additional suggestions from the local people. However, there were no
additional comments or different opinions from those in the minutes.
(2) Organization of public stage for people opinion hearing
After organization of the second public hearing in which the study results
and environmental measures were presented at 10 stages, some people in the area were still
anxious about the project. They also worried that the operation of the Nong-Saeng Power
Plant would cause impacts on the life way of the communities. Some communities gave
the comments that the study and EIA of the project were the academic work in which the
communities lacked of experience to completely understand all the process. To make the
community be confident to the project, the Power Generation Supply Co., Ltd. had
organized the meeting in the form of public stage. The meeting objectives included giving
the project information, answering the questions, clarifying the doubtful issues, being
widely opened for all participants both inside and outside the study area to present their
comments on the project and to make confidence that the project would work transparently.
The summary of the important issues was listed below.
- Schedule, place, media and participant number: The public stage of
the Nong-Saeng Power Plant was organized on March 27, 2008 at
Nong-Saeng Wittaya School in Nong-Saeng District of Saraburi. The
panel included the representatives from central offices such as
Department of Pollution Control, Office of Natural Resources and
Environmental Report for submittal to ADB Nong-Saeng Power Plant Project Chapter 7 Power Generation Supply Co., Ltd. Information, Disclosure, Consultation and Participation
T-EIA208102 7-46 F208102Chap7E-ADB
Environmental Planning and Policy (ONEP), the representatives of
provincial offices (provincial governor, provincial industrial chief
officer of Saraburi), freelance technocrats, the representatives of
private organizations, the representatives of conservative groups,
community leaders in the study area, executives of local
administration organizations in the study area, mass media and
interested people. Total participants were 1,670 persons. The meeting
chairman was Saraburi provincial governor.
• Meeting supplementary media: The media prepared for the public
meeting included
: The project presentation document consisted of reasons,
necessity, objectives, project description of the Nong-Saeng
Power Plant and the study methodology, etc.
: Figure for explanation and presentation: The Power Point
presentation consisted of reasons, necessity, the project
description, electricity generation process of the combined cycle
power plant, study methodology and assessment of
environmental impacts and public participation.
- Order of the meeting: The public hearing operation was divided into 3
sessions depending on the nature of activities which included the
explanation of the project background and brainstorming of
participants’ opinion. The public hearing activity was summarized by
order as follows:
• Opening speech by Saraburi provincial governor.
• Presentation of the project information was to present the project
background in order to make understanding of the public hearing
participants. The presentation was divided into 3 issues as.
: The project background,
: The study and assessment of environmental impacts.
: Components of the electricity generation process and
environmental impact prevention/control system in Nong-Saeng
Power Plant project,
Environmental Report for submittal to ADB Nong-Saeng Power Plant Project Chapter 7 Power Generation Supply Co., Ltd. Information, Disclosure, Consultation and Participation
T-EIA208102 7-47 F208102Chap7E-ADB
- The Q&A results: After the presentation of the project details, the
public stage participants discussed and gave comments about the
project. The consultant and representatives of the Power Generation
Supply Co., Ltd. answered and explained the details for all questions.
Summary of the important issues is given in Table 7.5-8.
- Announcement of the social contract was done after widely discussion
by the Power Generation Supply Co., Ltd. as follows:
• The power plant will be operated with care of environment and
communities.
• The power plant will be operated with acceptance of community
committee’s participation.
• The power plant will waive its legal rights by allowing the people
to inspect any times.
• The power plant will be operated with care and cooperation for
community development
(3) Appointment of public participation committee
From the concern issues of some people in the area and the Nong-Saeng
Power Plant awareness of environment and concern with communities around the plant
after the public meeting, the company had announced the social contract to allow the plant
inspection by the representatives of local people in the local area since the beginning of the
project. The company organized the third public meeting at mid year of 2008. The activity
aimed to be a public meeting for each subdistricts. The subdistrict assembly representatives
were elected from every village in the subdistrict. The assembly representatives from all
subdistricts assembled to assign regulation frame for committee appointment. When the
frame was voted by majority of the assembly, the committee was elected according to the
regulation as summarized below.
- The activity for coordination, discussion and making understanding
between the Power Generation Supply Co., Ltd. and community
leaders around the Nong-Saeng Power Plant project was done by
visiting, opinion sharing and discussion. The discussion was about the
reason for the appointment, guideline for making understanding with
local people, and guideline for participation of all people in the area.
This activity was aimed to make understanding about the community
Environmental Report for submittal to ADB Nong-Saeng Power Plant Project Chapter 7 Power Generation Supply Co., Ltd. Information, Disclosure, Consultation and Participation
T-EIA208102 7-48 F208102Chap7E-ADB
Table 7.5-8
Summary of Questioning Issues and Explanation from Public Stage
Nong-Saeng Power Plant Project Concern Explanation
1. Does the power plant construction conflict with city planning?
- No confliction because there is no city planning in the area of Nong-Saeng District.
2. Water shortage in the area. - The power plant site faces the flood problem rather than water shortage.
- From the study, the water in Pa-Sak River is sufficient. 3. Impact on health of unborn
babies, babies, children, adults and old people.
- The impacts of the power plant were generated from air pollution. But the operation of the Kaengkoi 2 Power Plant did not affect health of unborn babies, babies, children, adults and old people.
- The health check of the local people will be performed both before and after the project.
- From the study, high dust content was not generated from the power plant but was resulted from the environmental condition around the project site.
4. The impact of land filling during construction period.
- The land filling will be 1.5 meters high starting with asphaltic road being constructed in the project area.
- A canal will be constructed around the site area. After rainfall, bits of soil and rock will be flushed down to the canal. This will prevent shallowness of the public canals and stain on the road surface.
- Vehicle wheel cleaning well will be constructed. - The traffic control team/ group, such as civil defense
volunteer, was appointed during transportation period. - The villagers’ representative was appointed to control the
contractor. 5. Garbage management - The example of the Kaengkoi 2 Power Plant who invested
8 million bahts for constructing a garbage incinerator was cited.
6. Impact on surface water supply taking water from Klong Rapeepatana (Group 4 of Nong-Kob Subdistrict).
- A new tap water system will be constructed for Group 4 of Nong-kob Sub-district by the company. Then the system will be managed by the local.
7. Loud noise during construction period
- The construction activities are assigned to do only in daytime between 07.00 am.-06.00 pm.
- In the case that noise perturbs chicken farming, the farmers will be compensated.
Environmental Report for submittal to ADB Nong-Saeng Power Plant Project Chapter 7 Power Generation Supply Co., Ltd. Information, Disclosure, Consultation and Participation
T-EIA208102 7-49 F208102Chap7E-ADB
Table 7.5-8 (Cont’d) Concern Explanation
8. Why is this area selected for the power plant construction?
- The site selection factors for a power plant include water resource, power grid and natural gas pipelines.
9. Will the equipments and machineries of the power plant be in good condition for the whole life of the plant?
- The power plant will maintain the equipments and machineries in good condition for the whole plant life.
10. Why does not the power plant reuse the effluent?
- The effluent will be reused water for 4 rounds and treated to comply with the standard before being discharged to the water resource.
11. Return for the communities. - Before the foundation pile hammering, the company will support activities or the requests of the villagers or community leaders.
- When the power plant constructions starts, the fund of 80 million bahts a year will be set up and managed by the committee.
12. Why are people not informed before selecting the power plant site?
- The company followed the bidding procedure that the company having bidding right must own the land.
- In the EIA study, the complete information including plant site must be obtained so that the potential impacts can be predicted.
Environmental Report for submittal to ADB Nong-Saeng Power Plant Project Chapter 7 Power Generation Supply Co., Ltd. Information, Disclosure, Consultation and Participation
T-EIA208102 7-50 F208102Chap7E-ADB
participation committee. This was done by explaining about the
committee background, committee role, and guideline for people
participation. In the earlier step, each village would select/ elect its
representatives, which would be selected as the subdistrict assembly
committee in the next step.
- The meeting for selection of subdistrict assembly: When there were
village representatives, the working team had organized the meeting
for selecting subdistrict assembly. The candidates for the assembly
came from village representatives. The meeting was organized during
September 6-October 15, 2008 in totallly total 12 stages and 1,150
participants. The total selected subdistrict assembly was 184 persons.
For these people, 106 persons were from the project site subdistrict
and 78 persons were from the inner area subdistricts of the project.
- The drafting of people participation committee regulation: After the
subdistrict assembly selection, the representatives from various sectors
such as representatives of local people, a representative of the power
plant (1 person) and representatives of highly qualified persons
assembled in the subdistrict assembly to draft the community
participation committee regulation (Details of the regulation are given
in Appendix VI).
- The committee selection: When the regulation was voted by majority
of the subdistrict assembly, the committee selection was carried out
according to the regulation. The selected list was then presented to
Saraburi provincial governor for official appointment. (The official
appointment document is shown in Appendix VI).
There were 2 participation committees e.g., the participation committee
of the Nong-Saeng Power Plant project site subdistrict and that of the inner area
subdistricts of the Nong-Saeng Power Plant project. The committee had started meeting
and working according to their roles since October 2008.
Environmental Report for submittal to ADB Nong-Saeng Power Plant Project Chapter 7 Power Generation Supply Co., Ltd. Information, Disclosure, Consultation and Participation
T-EIA208102 7-51 F208102Chap7E-ADB
7.6 Conclusion of the Works on Public Relation and Public
Participation The works on public relation and public participation under the study and
assessment of the environmental impacts of Nong-Saeng Power Plant Project which is
located at Moo 4, Nong-Kob Subdistrict in Nong-Saeng District of Saraburi Province, were
carried out along with the socio-economic study. The activities had been carried out
continually with all target groups, provincial officers, district officers, subdistrict officers,
community leaders, local administration staff, village committee, and household
representatives. The works emphasized on two-way communication, in which the right and
clear information was disseminated to target groups and at the same time hearing of
opinion/suggestion, useful for the study and EIA. The opinion and suggestion were used
for improvement of the project operation in the future and assignment of environmental
and social mitigative measures to comply with the problem conditions and community’s
need.
The works were carried out using combined techniques of several formats
according to the guidelines of the study and social impact assement of the Office of
Natural Resources and Environmental Planning and Policy (ONEP). The conclusions of
the work were as follow :
7.6.1 Participation in news/information acknowledgement, understanding,
and suggestion for the project News/information acknowledgement
The direct communication with the target groups including provincial offices,
district offices, subdistrict offices, local people and local mass media to make them know
the project information better. The governmental offices acknowledged the objectives and
targets of the study and EIA and the work on public participation. The community leaders
and people in the area learned and understood about the reasons, necessity of the power
plant construction, the study methodology and assessment of environmental impacts for
designation of environmental measures. The guideline for participation in the study was
also acknowledged. This was evidenced by the acceptance of the project, the suggestion
and presentation of the information and problems which were useful for the study and EIA.
(1) Understanding of the matter and content of the project: Most target groups participating in the activity learned about the reason, necessity of the power plant construction and the whole country demand of electricity. In the public participation work, the study team emphasized on the content that made the target groups understand about the
Environmental Report for submittal to ADB Nong-Saeng Power Plant Project Chapter 7 Power Generation Supply Co., Ltd. Information, Disclosure, Consultation and Participation
T-EIA208102 7-52 F208102Chap7E-ADB
power plant operation and application of clean and environmental friendly technology in the project in order to reduce the community’s concern. However, some participants were not sure if the power plant construction near the community would cause any environmental impacts on the communities. The study team explained various technology including, environmental measures and public participation in inspecting and watching the potential impacts. This made the participants understand and relax from concern to the project. (2) Understanding of the process and procedure of the study and EIA: Most target groups (more than half) understood the study methodlogy and the study results presented by the study team at the first public participation meeting with 9 stages, at the second with 10 stages, and 1 public stage at fair to good levels. However, only few groups did not understand the technology used in the project which is technical issue. Some people were still anxious about the project development. (3) Opinion about the project: In the earlier study stage, most people in the study area had negative opinion on the project due to of their concern about the impacts and the negative information obtained from the outside the area. After the study team had visited the people, organized public participation activity and organized the power plant tour, the people in the study area had better knowledge and understanding of the power plant production process. This persuaded people to be relaxed from concern to the project. However, some people in the study area still had negative opinion on the project. Thus, the Power Generation Supply Co., Ltd., would make understanding to this group of people.
7.6.2 Participation of people and relevant persons All target groups showed good participation in all activities. This was evident by participation in the public hearing events, such as the first meeting of 9 stages with 653 participants the second meeting of 10 stages with 1,005 participants, and in the power plant tour of 19 rounds with 2,218 participants. The activities mentioned above caused the public participation be successful. The target groups were aware of right news/information. The participants also gave opinion/suggestion useful for the project operation as follows: (1) The community leaders and people in the study area joined the public hearing activity. They listened to the information, asked questions and gave suggestion to the project. From all stages of public participation, most of them were aware of necessity of the construction of the new power plant, importance of community participation in the study, monitoring of environmental impacts, watching and controlling of environmental conditions in the communities. They also tended to be representatives for monitoring and inspecting the environmental impacts.
Environmental Report for submittal to ADB Nong-Saeng Power Plant Project Chapter 7 Power Generation Supply Co., Ltd. Information, Disclosure, Consultation and Participation
T-EIA208102 7-53 F208102Chap7E-ADB
(2) Local administration organizations and subdistrict offices, such as chief
administrator of TAO, teachers and head of public heath center joined the meeting. They
gave suggestion and reflected the community in point of relationship, problems and
impacts caused by the project development. These people could be media for making
understanding of the community. Most of them agreed that the project progress should be
inspected. They were pleased that clean technology was applied to the project, including
the use to natural gas as fuel. The Nong-Kob TAO council voted for the power plant
construction in their area.
(3) Governmental offices at district and province levels cooperated with the
plant and gave useful suggestion for the project. They provided the information which
could be used in practics. They also suggested the guidelines for sharing benefit between
the communities and the Nong-Saeng Power Plant.
7.6.3 Summary of questioning issues obtained from the public hearing
activity
The study team collected the questioning issues, concerns and suggestions
obtained from all public hearing activities. These information were used to designatethe
the social mitigative measures. Summary of the important issues classified by occupational
groups and concern issues is given in Tables 7.6-1 and 7.6-2, respectively.
7.6.4 Implementation in accordance with the regulation of the Office of
Prime Minister
Various activities are conducted to encourages people in the study area to get
the project information sufficient for making a decision to accept the project and to be
pleased to participate with the project, the study team had followed the working frames of
the ONEP and the regulation of the Office of the Prime Minister entitled “Public hearing of
2548 (2005)”. Summary of the work is given in Table 7.6-3.
7.6.5 Suggestion for further work
From the whole figure of the working results, the community leaders in the
study area were interested in and pleased with the project development. They expected that
the project development would bring about the community development. However, people
particularly who are living in the communities around the project worried that the project
development would cause environmental and social impacts on the communities. They also
concerned that the project would use coal as fuel. Therefore, the previous works of public
hearing and mass communication provided news/information for making right understanding
T-EIA208102
7-54
F208102C
hap7E-AD
B
Environmental Report for subm
ittal to ADB
Nong-Saeng Pow
er Plant Project Chapter 7
Power G
eneration Supply Co., Ltd.
Information, D
isclosure, Consultation and Participation
Table 7.6-1
Summary of Community Concern Issues and Important Suggestion Classified by Occupational Groups.
Power Generation Supply Co., Ltd.
Issue Concern Explanation and Designation of Mitigative Measure Rice farming Will the effluent from the power plant
affect agriculture (rice farming)? - The effluent quality was controlled according to the order of the Royal
Irrigation Department No.883/B.E.2532, entitled “The prevention and resolution for the drainage of low quality effluent into the irrigation canals and other canals joint to them in the irrigation zones”. By this standard, the discharged effluents does not affect the people and agriculture crops.
- The effluent quality monitoring station will be installed. If the drained effluent quality exceeds the standard, the valve will be automatically turned off. The effluent cannot then be drained to the outside, but retreated until its quality is in compliance.
Hot gas emitted from the power plant may affect flourishing rice in field.
- The quantity of stack emissions from the power plant will be strictly enforced under the regulation.
- From the study, it was found that after the power plant operation, the SO2 and NO2 concentrations in the ambient air were lower than the standard. The particulates emission from the power plant was very low.
Light from the power plant maybe impact to flourish of rice.
- There is lighting in the power plant area as normal. No other lights affect the rice in the field
Fisheries How does the demineralized water discharged from the power plant affect aquatic lives?
- The effluent quality was controlled according to the order of the Royal Irrigation Department No.883/B.E.2532, entitled “The prevention and resolution for the drainage of low quality effluent into the irrigation canals and other canals joint to them in the irrigation zones”. By this standard, the discharged effluents does not affect the people and agriculture crops.
T-EIA208102
7-55
F208102C
hap7E-AD
B
Environmental Report for subm
ittal to ADB
Nong-Saeng Pow
er Plant Project Chapter 7
Power G
eneration Supply Co., Ltd.
Information, D
isclosure, Consultation and Participation
Table 7.6-1 (Cont’d) Issue Concern Explanation and designation of Mitigative Measure
Fisheries (Cont’d)
- The effluent quality monitoring station will be installed. If the drained effluent quality exceeds the standard, the valve will be automatically turned off. The effluent cannot then be drained to the outside, but retreated until its quality is in compliance.
Chicken-hen farming
Noise generated from the power plant may affect the nearby chicken-hen farming.
- During construct period, some noisy activities generating loud noise are foundation pile hammering and test run of the machines. These activities will be informed to people in advance.
- A plan for surveying chicken farms and households in the plant vicinity area is set up to evaluate the impacts.
- Installation of noise reductions equipments, noise adsorbent wall.
- The noise generating activities are occasionally conducted.
- During operated period, the noise level will be controlled not to exceed the standard. The noise levels will be measured at the fence.
Community drinking water
Is storm water drinkable if the power plant is constructed?
- The pollutants discharged from the power plant are strictly controlled by the standards of the relevant governmental offices. Thus, no impacts are imposed on consumable water.
Employment What is the opportunity of local people be employed in the power plant?
- For the recruitment by examination, if the locals have higher or lower scores being close to that of the candidates from outside the locals will get the priority. However, in the case of too low scores, the locals will be refused due to security and safety of the power plant.
T-EIA208102
7-56
F208102C
hap7E-AD
B
Environmental Report for subm
ittal to ADB
Nong-Saeng Pow
er Plant Project Chapter 7
Power G
eneration Supply Co., Ltd.
Information, D
isclosure, Consultation and Participation
Table 7.6-2
Summary of Community Concern Issues Used for Designation of Social Mitigative Measures
Nong-Saeng Power Plant Project Issue Concern Explanation and Designation of Social Mitigative Measures
Construction
Period 1. Traffic problem
- What are the measures for traffic
control during the construction period?
- The subcontractors must propose traffic and transportation plan to the project for approval before
the construction begins. The traffic regulation is to be strictly implemented. - Transportation of materials or large machineries is planned in order to avoid rush hours (during
07.00-09.00 a.m. and 05.00-07.00 p.m.) - The transportation through the community area should be avoided. A ring road or a special route
should be used. - The transportation is avoided during heavy rainfall or bad visibility. - Coordination with the highway police before the transportation of materials or large machineries
must be done to set the transport route and ask for motorcade for convenient transportation. - The announcement about the work plan, construction step and duration, and increases traffic due
to the project must be conducted to the communities and related governmental offices before construction in order to listen to and share opinion with them for use in work planning.
- The speed limits of vehicles are 20 kilometers per hour in the construction area, and 60 kilometers per hour on public roads.
- The transportation load must comply with the law. The trucks must be covered in order to prevent their falling on the road surface, which is a cause of accidents.
- A bus for transporting the employees from residence place to the project site area in order to reduce the number of vehicles on the roads.
- Training is provided for the driver in order to drive safety. - Signs or warning signs are posted at the place where is 100 meters ahead the construction site.
The signs must be clearly seen in daytime and night-time.
T-EIA208102
7-57
F208102C
hap7E-AD
B
Environmental Report for subm
ittal to ADB
Nong-Saeng Pow
er Plant Project Chapter 7
Power G
eneration Supply Co., Ltd.
Information, D
isclosure, Consultation and Participation
Table 7.6-2 (Cont’d) Issue Concern Explanation and Designation of Social Mitigative Measures
1. Traffic Problem
(Cont’d)
- A safety personnel is provided for waving a flag at the entrance and exit of the construction
area including the point where water pipeline is being installed.
- A parking area is particularly provided. No parking is allowed on the road shoulders of the
highway.
- Installation of supporting equipments, such as steel plate, temporary bridge or drain pipe for
facilitating the transportation of machines over the obstructing thing with safety and efficiency.
- Accident statistics due to transportation are recorded with the details and causes of the
accidents. Such data will be used for planning and setting the appropriate preventive measures.
- The road damaged by the material transportation is to be repaired to be of the same condition or
better.
- If the transportation of constructing
materials causes damage on the
road surface, what are the measures
responsible to the damage?
- Installation of supporting pieces of equipment, such as steel plate, temporary bridge or drain
pipe for facilitating the transportation of machines over the obstructing things with safety and
efficiency.
- Repairing the road damaged by the material transportation to be of the same condition or better.
- The transportation load must comply with the law. The truck must be covered in order to
prevent their falling on the road surface, which is a cause of accidents.
- The announcement about the work plan, construction step and duration, and increased traffic
due to the project must be conducted to the communities and related governmental offices
before construction in order to listen to and share opinion with them for use in work planning.
- The speed limits of vehicles are 20 kilometers per hour in the construction area, and 60
kilometers per hour on public roads.
- If the road surface in the community area is damaged due to the construction activity, the
subcontractors and the Power Generation Supply Co., Ltd. are is responsible to all damages.
T-EIA208102
7-58
F208102C
hap7E-AD
B
Environmental Report for subm
ittal to ADB
Nong-Saeng Pow
er Plant Project Chapter 7
Power G
eneration Supply Co., Ltd.
Information, D
isclosure, Consultation and Participation
Table 7.6-2 (Cont’d) Issue Concern Explanation and Designation of Social Mitigative Measures
2. Noise Problem - What are the measures to prevent the construction noise from annoying the communities?
- The earth wall with a height of 4.5 meters from the ground level is constructed. - The foundation pile hammering and noisy construction activities will be carried out only in
daytime. - The machineries and construction method generating low sound pressure level will be selected. - Utilization of various pieces of equipments or machineries generating loud more continuously
is avoided. - Reduction of the number of tools/machines working in the close area.
- Installation of the movable tools/equipments away from the sensitive area as far as possible. - Engines or tools/machines must be turned off after working. - The subcontractors are assigned to install noise reduction equipment, such as silencer or
muffler on the loud noise machines used for construction. The performance of such equipment is regularly checked.
- The equipments, machines and engines are checked to be in good condition. The heavy machines are to be checked at least once a month.
3. Problem of process water
- How is the community confident that there is no competition for water?
- If water pumping by the Nong-Saeng Power Plant project causes the problem to other water consumers, Department of Irrigation can order the Nong-Saeng Power Plant project to stop pumping water from Pasak River.
- A raw water well of 1,600,000 cu.m. capacity will be constructed by Nong-Saeng Power Plant project. Such water volume can be used by Nong-Saeng Power Plant project for 1 month without pumping water from the outside as the reserved water in dry season.
Operation period 1. Fuel used in production process
- Can the power plant use fuels other
than natural gas and diesel oil?
- The contract of 3 parties,i.e., the power plant, PTT and EGAT, clearly specifies that the power
plant uses natural gases. - The machines and equipments used in the power plant are designed to use natural gas as main
fuel and diesel oil as backup fuel only.
T-EIA208102
7-59
F208102C
hap7E-AD
B
Environmental Report for subm
ittal to ADB
Nong-Saeng Pow
er Plant Project Chapter 7
Power G
eneration Supply Co., Ltd.
Information, D
isclosure, Consultation and Participation
Table 5.6-2 (Cont’d) Issue Concern Explanation and Designation of Social Mitigative Measures
2. Problem of
process water
- The power plant pumps in large
quantity of water for production. This
may affect agricultures.
- The project has studied the equilibrium of water in order to find the water intake point which
dose not affect life way and water consumption of the community. The suitable point is
between north of the Rama VI Dam and the end of Chainat Canal.
- A well with capacity of 1,600,000 cu.m. is constructed to store water for use in the project.
Water is filled in the well when the water consumption for irrigation is less than the water
quantity at the water intake point. This period is during June to November. The power plant
will coordinate with Department of Irrigation about allocation of water from Pasak Chollasit
Dam. This will not affect the water utilization for irrigation, consumption and industries
downsteam of the water intake point.
- How is the community confident that
there is no competition for water?
- If water pumping by the Nong-Saeng Power Plant project causes the problem to other water
consumers, Department of Irrigation can order the Nong-Saeng Power Plant project to stop
pumping water from Pa-Sak River.
- A raw water well of 1,600,000 cu.m. capacity will be constructed by Nong-Saeng Power
Plant project. Such water volume can be used by Nong-Saeng Power Plant project for 1
month without water from the outside as the reserved water in dry season.
3. Effluent problem - Temperature and effluent quality
from the power plant may affect
aquatic animals in Klong
Rapeepatana and agriculture in the
area.
- The effluent discharged from the project is from the cooling tower only. The effluent is
discharged to Klong Huaiba (Klong Nong-Ngu-Loem).
- The effluent which is not cooling water is treated and reused as much as possible, e.g.,
watering on trees, machine cleaning, the power plant floor cleaning, etc. This effluent is not
discharged to the outside.
- The cooling water will be stored in the effluent holding pond for 3 days before discharge.
T-EIA208102
7-60
F208102C
hap7E-AD
B
Environmental Report for subm
ittal to ADB
Nong-Saeng Pow
er Plant Project Chapter 7
Power G
eneration Supply Co., Ltd.
Information, D
isclosure, Consultation and Participation
Table 7.6-2 (Cont’d) Issue Concern Explanation and Designation of Social Mitigative Measures
3. Effluent problem
(Continued)
- The effluent from the cooling tower of the project is treated so that its quality meets the
standard according to the Order of Department of Irrigation No.883/2532 (1989) entitled
“Prevention and resolution for drainage of low quality water to irrigation canals and other
canals joint to them in the irrigation zones” and the effluent standard according to ministerial
announcement of Ministry of Industry No.2 (1996) before being discharge to Klong Huaiba
(Klong Nong-Ngu-Loem).
- The temperature of the effluent is controlled not to exceed 34 °C. The thermometer, electrical
conductivity meter and pH meter are installed for monitoring the effluent quality in the
holding pond. If the effluent temperature is higher than 34 °C, the effluent must not be
discharged and the effluent temperature must be reduced to be lower than 34 °C before
discharge.
4. Air pollution
problem
- How to control the emission from the
stack?
- NOx control system consisting of Dry Low NOx Combustion System and Water Injection
System is installed for controlling of NOx emission in cases natural gas and diesel oil are used
as fuel.
- In case of using natural gas as fuel, the emission rates of air pollutants are controlled to be the
designed value at 100% load as follows:
• Sulfur dioxide not exceeding 10 ppm at 7%O2
or not exceeding 7.74 g/s per stack
• Oxides of nitrogen not exceeding 70 ppm at 7%O2
or not exceeding 38.93 g/s per stack
• Particulate not exceeding 20 mg/Nm3 at 7%O2
Or not exceeding 5.92 g/s per stack
T-EIA208102
7-61
F208102C
hap7E-AD
B
Environmental Report for subm
ittal to ADB
Nong-Saeng Pow
er Plant Project Chapter 7
Power G
eneration Supply Co., Ltd.
Information, D
isclosure, Consultation and Participation
Table 7.6-2 (Cont’d) Issue Concern Explanation and designation of Social Mitigative Measures
4. Air pollution
problem
- How to control smoke from the
chimney?
- The case of using diesel oil as fuel, the emission rates of air pollutants are controlled to be the
designed value at 100% load as follows:
• Sulfur dioxide not exceeding 30 ppm at 7%O2
or not exceeding 22.41 g/s per stack
• Oxides of nitrogen not exceeding 120 ppm at 7%O2
or not exceeding 64.37 g/s per stack
• Particulate not exceeding 35 mg/Nm3 at 7%O2
Or not exceeding 9.99 g/s per stack
- Continuous air quality monitoring system (Continuous Emission Monitoring System; CEMs)
is installed at HRSG stack for continuous monitoring of emission rates. This is used to control
the emission sources of the power plant.
- An alarm system will be installed if the emission rate approaches the designed value.
- The measures or working procedure are prepared for reducing the emission rates for example,
reduction of production capacity. If the emission rate is still higher than the designed value,
the plant is to be shutdown.
- The plant will be shutdown if the NOx control system fails.
- The monitoring results of stack emission and ambient air quality are displayed on the monitor
at the front of the power plant.
5. Benefit for the
community
- What are the benefits that the
communities get from the existence
of the power plant?
- The money allocated to the local communities are obtained from
• Property and machinery taxes.
• Value added taxes of gas purchasing from PTT and electricity sale to EGAT.
- The community development fund was founded in the plant vicinity area. (during construction
and operation periods). This is the pay back to the communities that sacrifice the area for the
power plant.
T-EIA208102
7-62
F208102C
hap7E-AD
B
Environmental Report for subm
ittal to ADB
Nong-Saeng Pow
er Plant Project Chapter 7
Power G
eneration Supply Co., Ltd.
Information, D
isclosure, Consultation and Participation
Table 7.6-2 (Cont’d) Issue Concern Explanation and Designation of Social Mitigative Measures
5. Benefit for the community (Cont’d)
- Activities are organized to encourage and support several community development. This aims to reduce concerns about impacts on career, to increase people’s standard of living, to develop the community. It also aims to support learning art, culture and religion, for example, supporting careers at sustainable economy learning center, agricultural demonstration plot (rice growing demonstration plot, mushroom growing demonstration plot, etc.), animal husbandry (chicken and hen farming), family accounting, integrated community and society development, monitoring and evaluating/surveying of career damages caused by the power plant operation, making understanding about the operation, annual power plant visiting and regular informing of the project information.
- Activities are organized for supporting of the community as appropriate. The power plant staff will participate in the community’s activities as if they were the household members. The activities include merit making, donation of things, granting scholarship to students in the local area, participation in community, temple and public property development.
- Regarding mass communication and community communication, community supporting projects related to public interests that bring about better life quality of local people around the project site are organized. These activities are additional operation plan of the fund, for example,
• Education supporting project for granting scholarships to students in the community and supporting of learning and sport kits to the schools in the radius of 5 kilometers away from the project site.
• Project on public health and occupational health of communities supporting project, such as organizing of mobile medical clinic, etc.
• Project on recruitment of outstanding students to be the power plant staff.
• Project on religion fostering in the plant vicinity area.
T-EIA208102
7-63
F208102C
hap7E-AD
B
Environmental Report for subm
ittal to ADB
Nong-Saeng Pow
er Plant Project Chapter 7
Power G
eneration Supply Co., Ltd.
Information, D
isclosure, Consultation and Participation
Table 7.6-2 (Cont’d) Issue Concern Explanation and Designation of Social Mitigative Measures
5. Benefit for the community (Cont’d)
• The career development project for making income to the community, such as agricultural career development or agricultural products processing in the locals for value adding. For example, the support of housewife groups to process several forms of foods from agricultural products in the locals and to sell their products to other places or even to upgrade their products to be one Tumbol (subdistrict) and one product (OTOP).
• Project on conservation of art, culture, custom and local wisdom. - The supporting plan for development of community potential in environmental field is set up
for making community understand and be aware of importance of participation in environmental problems. The plan includes the following :
• The supporting project on development of local conservation tourist sites.
• The training project on disaster mitigation, first-aid treatment, information sharing (method and channel) among the power plant representatives, governmental officers and the communities.
• Supporting school activities, such as environmental monitoring volunteer or young environmental scientists, such as wind detectives, stream detectives, etc.
The reforestation project to increase green area in the community and in the adjacent areas in Nong-Saeng, Nong-Kae Districts of Saraburi and in Pachee District of Phra Nakhon Si Ayutthaya Province will reduce concern about environmental change.
6. Concern various occupational groups, such as poultry, rice farming and mushroom growing groups.
The project operation may affect the occupation of local people. - Chicken and hen farming
Constructing period
- The project will make assurance contract for the impact on occupation. The power plant will be responsible to pay compensation of earning made from chicken and hen farming for the farmers in the radius of 1 kilometer away from the power plant site with the following conditions. (i) The farmers agree not to raise chicks at the beginning of the construction in
T-EIA208102
7-64
F208102C
hap7E-AD
B
Environmental Report for subm
ittal to ADB
Nong-Saeng Pow
er Plant Project Chapter 7
Power G
eneration Supply Co., Ltd.
Information, D
isclosure, Consultation and Participation
Table 7.6-2 (Cont’d) Issue Concern Explanation and Designation of Social Mitigative Measures
6. Concern various
occupational
groups, such as
poultry, rice
farming and
mushroom growing
groups (Cont’d)
frightened with noisy construction. Under the mentioned conditions, if the impacts exist, the
Nong-Saeng Power Plant is pleased to compensate on investment cost, turnover,
disadvantages and fee to the contract partners.
Operation period
- The project agrees to make a compensation contract for the impacts of noise and increased
temperature (if they are proved to be generated from the power plant) on chicken and hen
farmers in the radius of 1 kilometer away from the power plant site. The compensation will be
on account of the actual impacts caused by the project.
- The project agrees to make an assurance contract with chicken and hen farmers in the radius
between 1 and 2 kilometers away from the power plant site for the impacts of increase
temperature that is proved to be generated from the operation of Nong-Saeng Power Plant.
The compensation will be on account of the actual impacts caused by the project.
- The assurance conditions for the two cases are (i) the temperature and noise data in the poultry
farm which is in the radius of 1 kilometer were collected by Nong-Saeng Power Plant as
baseline data for future comparison in case of argument that whether the impact is caused by
Nong-Saeng Power Plant or not. For the poultry farm in the radius between 1 and 2
kilometers, the Nong-Saeng Power Plant will collect temperature data as reference data for
comparison in order to evaluate the temperature impacts. Adjudicating of the impacts or
damages will be done by the subcommittee appointed by the public participation committee in
the area of the Nong-Saeng Power Plant.
- Rice farming - If the rice farms are affected by the light from the project, compensation will be paid.
- The rice farming demonstration plot of 10 Rai (1 Rai = 1600 square meters) is prepared.
T-EIA208102
7-65
F208102C
hap7E-AD
B
Environmental Report for subm
ittal to ADB
Nong-Saeng Pow
er Plant Project Chapter 7
Power G
eneration Supply Co., Ltd.
Information, D
isclosure, Consultation and Participation
Table 7.6-2 (Cont’d) Issue Concern Explanation and Designation of Social Mitigative Measures
6. Concern various
occupational
groups, such as
poultry, rice
farming and
mushroom growing
groups (Cont’d)
- Rice farming by lessees - The former lessees will be allowed to do rice farming in the former rice field, now is the
power plant property, with free of charge.
- The project will inform the lessees in advance for 1 round/time before cultivation (about 4
months before the construction begins). This allows time for consideration of giving help to
the lessees.
- The lessees in the project area will be compensated or paid for dismantling cost if their houses
are in the project area.
- If any lessees want the project to find the job for them, employment in the power plant will be
given for 1 person per family.
- Mushroom growing - If there are evidences that mushroom growing is affected from the effluent discharged from
Nong-Saeng Power Plant project, the project is pleased to compensate the market price of the
decreased products for the affected people.
- If that impact occurs, the Nong-Saeng Power Plant project will find another water resources
for the mushroom growers. For example, construction of deeper artesian wells, connection of
water pipelines to other water resources or installation of water filters for the mushroom
growers.
Environmental Report for submittal to ADB Nong-Saeng Power Plant Project Chapter 7 Power Generation Supply Co., Ltd. Information, Disclosure, Consultation and Participation
T-EIA208102 7-66 F208102Chap7E-ADB
Table 7.6-3
Study Implementation in accordance with the Regulation of
the Office of the Prime Minister entitled “Public Hearing” B.E.2548 Regulation of the Office of
Prime Minister
Procedure/Implementation
No.1, No. 2, No.3 No. 4 Explanation of details-Definition
No. 5 Before conducting a governmental project, the governmental office being responsible for the project shall disseminate information as stated in No. 7 to public and shall listen to people’s opinion by any means or those stated in No. 9.
The public relation and public participation of the Nong-Saeng Power Plant project was conducted as follows: 1. Project information distribution Public relations for making the target groups be acknowledged are - Visiting community leaders and important persons in the study
area to inform about the project. This was done before listening to individual opinion. The visiting was either official or non-official. The visiting also extended to local officers in the district, sub-district and local administration organization levels to publicize the project and to survey opinion and opinion stream toward the project. This activity had been performed for the whole study period.
- Placards for inviting people who were interested to join the meeting were posted on the public relation boards of TAOs, MDs and districts in the study area.
- In all stages of public hearing, the meeting supplementary documents and other media were given to participants to learn about the project before starting the activity.
2. Public hearing The study team had given priority to public hearing since the studying period. This was implemented by organizing public participation activities in which the target groups showed their opinion, shared information, reflected opinion and idea stream via two-way communication. The techniques employed included - Organization of informing stage and the first public hearing to
inform, make understanding and give the project information for 9 times. This had been done during October 28-November 12, 2007. The project information was disseminated to 653 community leaders and people.
Environmental Report for submittal to ADB Nong-Saeng Power Plant Project Chapter 7 Power Generation Supply Co., Ltd. Information, Disclosure, Consultation and Participation
T-EIA208102 7-67 F208102Chap7E-ADB
Table 7.6-3 (Cont’d) Regulation of the Office of
Prime Minister Procedure/ Implementation
- The survey of socio-economics of the people was conducted by interviewing 1,095 individuals in October 2007. Before the interview, interviewers briefed about the important issues of the project until the interviewee clearly understood. The interviewee was allowed to show their opinion and suggestion via the questionnaire.
- Organization of project informing stage and public hearing for presentation of the study results was carried out for 10 times during January 20-February 13, 2008 with 1,005 participants.
- Organization of project presentation meeting with chicken and hen farmers in Pachee and Nong-Saeng Districts was conducted to set the mitigative measures for preventing the impacts from the power plant. This was done for 1 time on February 12, 2008 with 20 participants.
- Organization of project presentation meeting to ask for permission from Nong-Kob TAO was carried out for 1 time on February 14, 2008 in Nong-Kob TAO meeting room with 28 participants.
No. 6 In the case that the governmental office does not conduct the public hearing before starting of the project as stated in first paragraph of No.5, if the stakeholder makes a complaint to minister for central government service, to provincial governor for provincial or local government service or to Bangkok governor for Bangkok government service, They shall order the governmental office to organize the public hearing. If it happens, the governmental office must take prompt action.
The project had organized the public hearing before starting the project (the details as given in No. 5). Few community leaders and people in the study area still had concern about the project development. They also saw that the study and EIA were academic work of which the community still lacked of experience to fully understand the whole process. In order to make people be more confident with the project, the Power Generation Supply Co., Ltd. made all parties to learn in details of the project information, to discuss, to ask questions and to make understanding together in every issues. The public stage was organized on March 27, 2008 in the meeting hall of Nong-Saeng Wittaya School in Nong-Saeng District of Saraburi. The total 1,670 participants included chiefs of governmental offices at provincial/district/subdistrict levels of Saraburi, executives of local administration organizations, community leaders, people in the study area, freelance academics, private organizations, environmental conservation groups, mass media. The Saraburi governor presided over the meeting.
Environmental Report for submittal to ADB Nong-Saeng Power Plant Project Chapter 7 Power Generation Supply Co., Ltd. Information, Disclosure, Consultation and Participation
T-EIA208102 7-68 F208102Chap7E-ADB
Table 7.6-3 (Cont’d) Regulation of the Office of
Prime Minister Procedure/Implementation
No. 7 The information of the governmental project which shall be publicized by the governmental office shall contain at least the following items :
In the operation of Nong-Saeng Power Plant project, the consultant company and the Power Generation Supply Co., Ltd., emphasized on making knowledge and understanding for people and relevant persons by using the following public relation media: - Human media • The study team included the working group being responsible
for the study, EIA, public relation and participation and socio-economics,
• The interview staff for the survey of socio-economics and people’s opinion of 10 persons.
- Document media. The consultant company and the Power Generation Supply Co., Ltd., produced media for making knowledge and understanding. These included • 1,000 sets of the meeting supplementary documents (project
presentation) including details, reasons, necessity, objectives, content, site area, operator and products and outcome of the project, the study procedure and EIA and guideline for public participation were distributed to the people in the project area.
• 3,000 sets of public relation documents explaining power generation process and cogeneration were distributed to the communities and local people to make them understand the power generation process using natural gas as fuel.
• 15 sets of placard for inviting people who were interested to join the public hearing were produced.
• 1,000 sets of the meeting supplementary documents were produced, presenting the study results, project details, EIA, mitigative measures for the impacts from the project operation, and channels for communication with the project in cases of complaints or emergency. They were distribute to target groups,containing all information stated in No.7 of the regulation.
(1) Reasons, necessity and objectives of the project
- To support electrical demand sufficiently.
(2) Important issues of the project
- The Nong-Saeng Power Plant project is the combined cycle power plant operating according to the Power Development Plan (PDP 2007) to cope with to the increasing electrical demand for economic growth.
Environmental Report for submittal to ADB Nong-Saeng Power Plant Project Chapter 7 Power Generation Supply Co., Ltd. Information, Disclosure, Consultation and Participation
T-EIA208102 7-69 F208102Chap7E-ADB
Table 7.6-3 (Cont’d) Regulation of the Office of
Prime Minister
Procedure/ Implementation
(3) Operator - The operator is the Power Generation Supply Co., Ltd., who are
doing business on power generation and sell electricity to EGAT
and factories in the area.
(4) Project site - The Nong-Saeng Power Plant project is located at Moo 4, Ban
Huaiba, Nong-Kob Sub-district in Nong-Saeng District of
Saraburi.
(5) Procedure and project
development period
1. At present, the project is preparing the EIA report to submit to
ONEP and authorized governmental offices for approval.
2. Construction is planned to start in the your 2010. The
construction period is about 30-36 months.
(6) Output and outcome of the
project
- Output: power generation capacity of 1,600 MW.
- Outcome: Reinforcement of electrical energy security and
supply of electricity to be sufficient for the country demand.
(7) Potential impact on people
living or making a living in the
site nearby area and public,
including mitigative measures
or healing measures for
troubles and damages caused
by the impacts.
1. Evaluation of major impacts which are potentially caused by the
project, such as
Construction period
- Dust impact in the power plant construction area,
- Low level of noise impact resulting from the power plant
construction,
- Low level of impacts caused by sanitary wastewater from the
workers and soil sediment leaching by storm water which was
due to
• The construction workers commute to work.
• The toilets are installed at a distance of 30 meters away from
public water resource.
• The effluent from various activities is stored in the holding
pond without discharging to public water resources.
- The traffic is slightly increased. The traffic condition is still
good.
- More employment and trading cause income to communities.
Environmental Report for submittal to ADB Nong-Saeng Power Plant Project Chapter 7 Power Generation Supply Co., Ltd. Information, Disclosure, Consultation and Participation
T-EIA208102 7-70 F208102Chap7E-ADB
Table 7.6-3 (Cont’d)
Regulation of the Office of
Prime Minister
Procedure/ Implementation
Operation period - The air quality impact of the project of the project on the
communities is low and acceptable because the maximum concentrations of the air pollutants are much lower than the standard value.
- The noise level impact of the project on the community is low because the noise level generated by the project does not increase the community noise level.
- The effluent from cooling towers is stored in a holding pond before being discharged.
- The traffic is slightly increased. The traffic condition is still good.
- More employment and trading cause income to communities. - In case of natural gas leakage and ignition, the impact radius is
limited within the power plant area. 2. Important environmental mitigative measure - Using natural gas as main fuel. - Installation of air pollution control system. - Installation of continuous emission monitoring system to mesure
the concentrations of oxides of nitrogen sulfur dioxide, particulates and oxygen.
- Control the stack emission rates not to exceed the standard. - Recruitment of qualified personnel to control the air pollution
control system. - Installation of noise reduction equipment to reduce the noise
generated from machines and regular checking of their performance.
- Installation of cooling towers to reduce the effluent temperature before flowing to the holding pond of the project,
- The treated effluent is controlled to comply with the effluent standard before being drained to public water resources.,
- The garbage and solid wastes are kept in covered bins before disposal by an authorized agency.
- Designation of regulation for vehicles entering and exiting the power plant to prevent accidents.
Environmental Report for submittal to ADB Nong-Saeng Power Plant Project Chapter 7 Power Generation Supply Co., Ltd. Information, Disclosure, Consultation and Participation
T-EIA208102 7-71 F208102Chap7E-ADB
Table 7.6-3 (Cont’d)
Regulation of the Office of Prime Minister
Procedure/ Implementation
- Setting up the measures of occupational health and safety for working, such as measures for management of occupational health and safety, and measures for fire prevention and fire extinguishing system.
- Preparation of emergency plan and conducting the drill at least once a year.
- Giving priority to the recruitment of the locals. - Broadening of the public relation of the project and the
mitigative measures for impacts and deeply increasing of content by making community networks,
- Preparation and distribution of the documents of the project details and pollution prevention system which are easily understood,
- Organizing the power plant visit for community leaders and communities continously,
- Organizing public interest activities.
(8) Budget estimation in case that the governmental office conducts the project by itself. The budget sources shall be specified.
- Construction of the Nong-Saeng Power Plant uses the budget corresponding to the company business plan.
No. 8 In the public hearing, the governmental office shall aim to make people understand correctly about the governmental project and gather public opinion on the project, troubles and damages that may affect the people. The governmental office may listen to public opinion and give information to the people simultaneously.
- For all public hearing stages organized by the study team, it is aimed to make people understand correctly by the following jobs:
• Giving information by using several kinds of public relation
media suitable for target groups and situation. The media
include meeting supplementary documents, leaflets and
presentation of information via human media for the whole
study period,
• Making knowledge and understanding by organizing many
project presentation stages. The activities included interview of
1,095 individuals, the first public hearing for presentation of the
project for 9 times with 653 participants, the first round of
Environmental Report for submittal to ADB Nong-Saeng Power Plant Project Chapter 7 Power Generation Supply Co., Ltd. Information, Disclosure, Consultation and Participation
T-EIA208102 7-72 F208102Chap7E-ADB
Table 7.6-3 (Cont’d) Regulation of the Office of
Prime Minister
Procedure/ Implementation
touring consisting of 13 times, and the second round consisting of 6 times with totally 2,218 participants, the second public hearing for presentation of the study results for 10 times with 1,005 participants the meeting with occupational group for 1 time with 20 persons, the meeting for requesting of permission from Nong-Kob TAO for 1 time with 28 persons and the public stage for listening to people opinion for 1 time with 1,670 participants. The total participant was 6,689 persons.
• For all stages of listening to opinion and suggestion, the participants were encouraged to ask questions, give suggestion and discuss about the project. For the listening to individual opinion and question, were noted and used later for making the process of participation in the project for all target groups.
• The collection of people opinion about the project, troubles and damages that might affect the people were conducted by many means as follow : : Opinion expression by standing up in the meeting (collected
by note or tape recorder), : Opinion expression via an evaluation form given in the
meeting, : Opinion expression via a questionnaire for the survey of
socio-economics and public opinion. - The results of opinion expression were collected and used for
setting mitigative measures corresponding to the needs and conditions of the communities.
- The results of continuous works on public relation and public participation, from pre-study period through study period and covering all target groups, were correct understanding of people about the project.
- The study team conducted the public hearing and information dissemination simultaneously by using 2 main media:
• Human media are the most effective media. They explained, gave information and answered the questions of the target groups.
Environmental Report for submittal to ADB Nong-Saeng Power Plant Project Chapter 7 Power Generation Supply Co., Ltd. Information, Disclosure, Consultation and Participation
T-EIA208102 7-73 F208102Chap7E-ADB
Table 7.6-3 (Cont’d) Regulation of the Office of
Prime Minister
Procedure/Implementation
• Documental media are used for making understanding. They included meeting supplementary document, leaflet and Power Point presentation.
No. 9 The public hearing as stated in No. 8 may use any mean or many means as follows: (1) Opinion survey by - Individual interview. - Allow opinion expression via
post, telephone or fax, internet or others.
- Allow people to get information and express the opinion to the governmental office being responsible for the project.
- Sub-group meeting.
The work on public hearing and public relation of the project applied integrated methodologies that suitable for the targeted groups; - Interview of 1,095 family samples, - Meeting for listening to community leaders to inform the project
was organized for 9 times with 653 participants. - The public hearing for presentation of the study results consist of
• Listening to community opinion was organized for 10 stages with 1,005 participants.
• The public stage was joined by 1,670 persons.
(2) Discussion by - Public hearing - Public debate - Information sharing - Workshop - Meeting of representatives of
groups of relevant people or stakeholders
(3) Other means assigned by the permanent secretary of the Office of the Prime Minister
No. 10 The governmental office may conduct public hearing by using other means, apart from those stated in No. 9, that make the public hearing meet the objectives given in No. 8, it is allowed to do so.
- The work on public hearing met the objectives. There was no need to use the other methods.
Environmental Report for submittal to ADB Nong-Saeng Power Plant Project Chapter 7 Power Generation Supply Co., Ltd. Information, Disclosure, Consultation and Participation
T-EIA208102 7-74 F208102Chap7E-ADB
Table 7.6-3 (Cont’d) Regulation of the Office of
Prime Minister
Procedure/ Implementation
After the wok done, it shall be
reported to the office of
permanent secretary of the
Office of the Prime Minister.
No. 11 In the public hearing,
the governmental office shall
announce to public so they
understand the procedure,
duration, place and other
details sufficient for people to
understand and be able to
express opinion.
The announcement stated in
the first paragraph shall be
posted openly on information
boards of the governmental
offices and the project site for
at least 15 days before the
public hearing and it shall be
posted on the internet website
of the office of permanent
secretary of the Office of the
Prime Minister.
• Before conducting all public hearing meetings, the study team
posted placards to invite stakeholders and people who were
interested to join the meeting. The announcement was posted
for about 15 days before the public hearing. The placards were
posted on the information boards of the communities in which
the public hearing was organized. The posting places included
information boards in TAO/MD in the study area, information
boards of Nong-Saeng, Nong-Kae and Pachee District offices.
No. 12 After public hearing,
the governmental office shall
conclude the results and
announce to public within 15
days after the meeting.
- The study concluded the public hearing results and posted the
conclusion on the information boards in TAO/MD in the study
area, information boards of Nong-Saeng, Nong-Kae and Pachee
District offices.
No. 13 After finishing the
public hearing, if the operation
of the governmental project
may cause impacts to people
- Power Generation Supply Co., Ltd., has policy on operation of
mass communication in the project area from pre-construction
period to construction period and through the whole operation
period. The missions are
Environmental Report for submittal to ADB Nong-Saeng Power Plant Project Chapter 7 Power Generation Supply Co., Ltd. Information, Disclosure, Consultation and Participation
T-EIA208102 7-75 F208102Chap7E-ADB
Table 7.6-3 (Cont’d) Regulation of the Office of
Prime Minister
Procedure/Implementation
other that the data given to
people as stated in No. 7 (7)
and it is necessary to carry on
the project, the governmental
office shall designate suitable
mitigative measure or healing
measures for more troubles
and damages resulting from
the impacts before starting the
project. This shall be
announced to public according
to the second paragraph of No.
11.
• To distribute the project information and construction
information every periods.
• To listen to opinion and suggestion from people and to give answers to concerns of people about the project operation activities.
• To accept complaints or damages resulting from construction activities and during operation period, and to coordinate with relevant persons for solving and healing the troubles/damages occurred.
• Keep watching and asking subcontractors to implement the environmental mitigative measures seriously.
Nos. 14, 15, 16 explain details
of practical method for the
Office of the Prime Minister.
Environmental Report for submittal to ADB Nong-Saeng Power Plant Project Chapter 7 Power Generation Supply Co., Ltd. Information, Disclosure, Consultation and Participation
T-EIA208102 7-76 F208102Chap7E-ADB
that the project was not able to use coal as fuel. The contract for natural gas purchasing
with PTT caused less concern. However, the Nong-Saeng Power Plant Project must keep
organizing of public hearing and mass communication continuously in order to provide
information about environmental management, to listen to people’s opinion and to
encourage participation with the project. The activity running must be in the forms of
interest sharing, collaboration and participation, community watching. These will make the
project development be successful and accepted by the communities. Moreover, based on the consultations with local communities, below are the
highlighted requests from local communities around the project area for PGS to implement:
(1) Complete the construction of the road in the Project site prior to the
commencement of Power Plant Construction
(2) Support the local communities to set up Civil Defense Volunteer to
manage and supervise the traffic during the construction of the Power Plant
(3) Create the registration records of the Contractor’s labors
(4) Provide the waterworks for the local community
(5) Allow the People Participation Committee to inspect the environmental
impacts of the Power Plant
In addition to the requests from local communities, PGS has also developed the
CSR program to promote strong awareness of responsibility towards the local communities
since PGS is committed to conducting its business in conformity with good corporate
governance, local culture, and relevant environmental laws and regulations. Below are the
highlighted CSR Programs:
(1) Set up Power Development Fund to improve quality of life of local
communities around the Power Plant
(2) Donate 21 million baht/year for local communities for local
communities and environmental development
(3) Publish the 5,000 magazines quarterly to publicize the news and
information of the Power Plant to local residents in 12 sub-districts of Nong Saeng District,
Nong Khae District and Pha Chee Disitricts
(4) Broadcast the news and information of the Power Plant through local
radio every weekday from 10:00 pm to 12:00 am
(5) Participate and support the fund for events and activities to enhance local
culture, natural resources, environment, education, public health, religious, sports and
Environmental Report for submittal to ADB Nong-Saeng Power Plant Project Chapter 7 Power Generation Supply Co., Ltd. Information, Disclosure, Consultation and Participation
T-EIA208102 7-77 F208102Chap7E-ADB
occupation
(6) Take government officers, community leaders and community
representatives to visit existing power plants such as KK2 Power Plant, Wang Noi Power
Plant, Rayong Power Plant, etc
(7) Frequently meet local people to make them understand about any
concerns of the Power Plant
PGS has been supporting funding and activities of several local society groups
such as women group, occupation development group, elderly people group, public health
volunteering group, civil defense volunteer group, farmer group, etc to improve the quality
of life of the local people.
Apart from local society groups, NGOs have never requested any assistance
from the Project; however, if they would like to get assistance from the Project, PGS is
willing to support them if their requests are beneficial to the local communities.
Environmental Report for submittal to ADB Nong-Saeng Power Plant Project Chapter 8 Power Generation Supply Co., Ltd. Grievance Redress Mechanism
T-EIA208102 8-1 F208102Chap8E
Chapter 8
Grievance Redress Mechanism
The flow charts of complaint receiving/follow-up actions and the associated
time frames are as shown in Figures 8-1 and 8-2.
Local people can directly contact with PGS through telephone, People
Participation Committee, CSR team and TAO office. PGS will try to solve the problem as
soon as possible after receiving complaint. Apart from those channels, PGS has already
established the Communication Coordination Center (“CCC”) to receive the grievance
from the public including local residents. PGS will provide Grievance Boxes and put them
at the CCC, TOA, Community Leader’s houses for everyone to send inquiries to PGS. The
officers from CCC will collect the inquiry every day and PGS will inform the public about
the progress of grievance mitigation by following methods within 24 hours for the urgent
issues and 7 days for the non-urgent issues:
(1) Post the progress announcement at TAO
(2) Post the progress announcement at public relation board in front of the
Power Plant
(3) Broadcast the progress through local radio
(4) Inform the progress directly to the grievant
(5) Summarize the progress and conclusion in newsletter to be distributed in
local communities
(6) Issue letters to TAO, Community Leaders and related government
organization
(7) Inform local people through the local community meeting
The affected people can inform PGS in every matter that they get affected from
the Project including any inconvenience occurred from the construction workers.
Environmental Report for submittal to ADB Nong-Saeng Power Plant Project Chapter 8 Power Generation Supply Co., Ltd. Grievance Redress Mechanism
T-EIA208102 8-2 F208102Chap8E
Figure 8-1 : Chart of the general complaints
Appellant
Mass Communication coordination center / complaintsNatural Gas Pipeline to Nong Saeng Power Plant Project
Organize the relevant authorities responsible
Presented to the Executive to delegate the responsibility to resolve the problem
Monitored continuously/Summary and report to notify local
authorities
Monitoring Committee to resolve complaints..
Check the cause / effects / complaints
Report results back to the complainant
24 hours
24 hours
24 hours
48 hours
48 hoursPeriod from the start to inform the
result of the complaint
within 7 days
Report back to the initial complaint within 48 hours
Note : If the complaint can not complete corrective action within 7 days, progress in solving the problem will be notify the complainant every 3 days.
to Nong Saeng Power Plant Project
Environmental Report for submittal to ADB Nong-Saeng Power Plant Project Chapter 8 Power Generation Supply Co., Ltd. Grievance Redress Mechanism
T-EIA208102 8-3 F208102Chap8E
Appellant
Mass Communication coordination center / complaintsNatural Gas Pipeline to Nong Saeng Power Plant Project
Presented to the Executive.To command the problem
Monitored continuously/Summary and report to notify local
authorities
Report results back to the complainant
24 hours
Resolve within 24
hours
Figure 8-2 : Chart of the emergency complaints
to Nong Saeng Power Plant Project
Environmental Report for submittal to ADB Nong-Saeng Power Plant Project Chapter 9 Power Generation Supply Co., Ltd. Environmental Management Plan
T-EIA208102 9-1 F208102Chap9E
Chapter 9
Environmental Management Plan The Nong-Saeng Power Plant Project of Power Generation Supply Co., Ltd. is
located in an area of approximately 570 rai which is allocated into 2 portions of areas: the
power plant area of approximately 300 rai which is located in Moo 4 of Ban Huaiba,
Nong-Kob Sub-district, Nong-Saeng District of Saraburi Province; and the reservoir area
of approximately 270 rai which is located in Moo 7 of Ban Thamsinthusopa, Nong-Namsai
Sub-district, and Moo 2 of Ban Klong, Khok Muang Sub-district, Pachee District of Phra
Nakhon Si Ayutthaya Province. The Nong-Saeng Power Plant utilizes natural gas as the
main fuel and diesel oil as backup fuel. The electrical generating capacity is approximately
1,653 MW, comprising two 826.6 MW blocks. About 1,600 MW of the generated
electricity will be sold to the Electricity Generating Authority of Thailand (EGAT) and the
remaining 53 MW will be used within the Nong-Saeng Power Plant. The main components
of the project includes four combustion turbine generators (CTG), four heat recovery steam
generators (HRSG) and two steam turbine generators (STG). The generated electricity is
sold to EGAT via the 500 kV Pachee sub-station and the transmission line which is
connected to EGAT’s Tatakoe-Wangnoi transmission line. The consumption of natural gas
as the main fuel of the project to be supplied by PTT (Public) Co., Ltd. is approximately
265.18 million cubic feet per day; and diesel oil of approximately 6.594 million liters per
day as backup fuel. The raw water is pumped from the Pa-Sak River, upstream of the Phra
Rama Six Dam, and stored in the 1,600,000 cubic meter reservoir before use. The
wastewater generated by the project is treated and reused. Only the effluent discharged
from the cooling tower is drained into the holding pond before discharging into Klong
Huaiba (Klong Ngu-Loem). The quality of the discharged water meets the effluent
standard under the Notification of the Ministry of Industry, Issue No.2 (1996), entitled
“Characteristics of effluents discharged from factories” and the Decree of the Royal
Irrigation Department No. 883/B.E. 2532, entitled “The prevention and mitigation of the
discharge of low quality water into the irrigation waterways and the waterways connected
to the irrigation waterways in the irrigation project areas.”
Environmental Report for submittal to ADB Nong-Saeng Power Plant Project Chapter 9 Power Generation Supply Co., Ltd. Environmental Management Plan
T-EIA208102 9-2 F208102Chap9E
The implementation of the project may induce impacts on the environment,
health and life way of the people living in the nearby areas. From the review of the
environmental impact assessment report by the EIA Expertise Committee, the following
mitigative measures were stipulated for implementation:
(1) To implement the environmental mitigative measure and environmental
monitoring programme formulated in an environmental action plan as specified in the
environmental impact assessment report of Nong-Saeng Power Plant Project. The
measures shall be used as a guideline to be supervised, controlled, followed up and
inspected by the concerned government agencies, public and related organizations.
(2) To specify the details of the measures under the environmental action
plan in the contract between the project and the contractor, and to strictly implement these
measures for their effectiveness in practice.
(3) To report the results of performance under the environmental action plan
to the permitting agencies of Saraburi Province, Phra Nakhon Si Ayutthaya Province, and
the Office of Natural Resources and Environmental Policy and Planning (ONEP) for their
review according to the timetable specified in the action plan and guideline for submitting
the environmental monitoring results of ONEP.
(4) To routinely maintain and inspect the operation of the cooling system so
as to keep it in good and safe condition for the operators and the public living in the nearby
areas.
(5) In case the environmental monitoring results demonstrate a trend of an
induced problem including the complaints (caused by the project implementation) from the
communities, the company is required to promptly take the improvement and corrective
actions for such problem and report every event to the permitting agencies of Saraburi
Province, Phra Nakhon Si Ayutthaya Province, and the Office of Natural Resources and
Environmental Policy and Planning so as to coordinate the cooperation for solving the
problem.
(6) If the company purposes to modify the details of the project and/or the
environmental action plan, it must notify the permitting agencies about such modification
for their review as follows:
- If the permitting agencies regard such modification as not having an
effect on the impact assessment in the approved EIA report, the
company shall notify the Office of Natural Resources and
Environmental Policy and Planning about this matter.
Environmental Report for submittal to ADB Nong-Saeng Power Plant Project Chapter 9 Power Generation Supply Co., Ltd. Environmental Management Plan
T-EIA208102 9-3 F208102Chap9E
- If the permitting agencies regard such modification as having an effect
on the impact assessment in the approved EIA report, the company
shall submit the data of the impact study and assessment results of
such modification in details and in comparison with the original data
to the EIA Expertise Committee for approval before implementation.
(7) In case there is any project-related complaint from the communities, the
Company must promptly solve the problem (addressed in the complaint) and record it as a
report.
(8) If the project is not implemented within 2 years from the date of the letter
from ONEP notifying the results of the review and approval of the environmental impact
assessment report by the EIA Expertise Committee, the project shall revise the data and
environmental measures and submit them to ONEP for review.
(9) When the project is operated at the steady state, and it is found that the
aforementioned emission rates are lower, the project is required to use them as the control
values and notify ONEP promptly.
PGS will be required to perform external monitoring and submit the semi-
annual reports to ADB during construction phase and operation phase.
The implementation of the environmental mitigation and environmental quality
monitoring measures (specified as the environmental action plan) consists of 13
environmental action plans, the details of which are as follows:
(1) Action Plan on Air Quality
(2) Action Plan on Noise Level
(3) Action Plan on Surface Water Hydrology and Surface Water Quality
(4) Action Plan on Forestry and Wildlife Ecology
(5) Action Plan on Aquatic Ecology and Fishery
(6) Action Plan on Land Use
(7) Action Plan on Water Usage
(8) Action Plan on Transportation
(9) Action Plan on Drainage and Flood Control
(10) Action Plan on Solid Wastes
(11) Action Plan on Occupational Health and Safety
(12) Action Plan on Socio-economic
(13) Action Plan on Public Relation and Public Participation
Environm
ental Report for submittal to AD
B N
ong-Saeng Power Plant Project
C
hapter 9 Pow
er Generaton Supply C
o., Ltd. Environmental M
anagement Plan
T-EIA208102
9-4
F208102Chap9Ta_E-A
DB
_revised (4)
Mitigative Measure
Nong-Sang Power Plant Project of Power Generation Supply Co., Ltd.
Nong-Kob Sub-district, Nong-Saeng District of Saraburi Province
Environmental Impacts Mitigative Measures Monitoring Programme Responsibility
1. General Measure (1) To implement the environmental mitigative
measure and environmental monitoring programme
formulated in an environmental action plan as
specified in the environmental impact assessment
report of Nong-Saeng Power Plant Project. The
measures shall be used as a guideline to be
supervised, controlled, followed up and inspected by
the concerned government agencies, public and
related organizations.
(2) To specify the details of the measures under the
environmental action plan in the contract between the
project and the contractor, and to strictly implement
these measures for their effectiveness in practice.
(3) To report the results of performance under the
environmental action plan to the permitting agencies
of Saraburi Province, Phra Nakhon Si Ayutthaya
Province, and the Office of Natural Resources and
Environmental Policy and Planning (ONEP) for their
review according to the timetable specified in the
action plan and guideline for submitting the
environmental monitoring results of ONEP.
- Power Generation
Supply Co., Ltd.
Environm
ental Report for submittal to AD
B N
ong-Saeng Power Plant Project
C
hapter 9 Pow
er Generaton Supply C
o., Ltd. Environmental M
anagement Plan
T-EIA208102
9-5
F208102Chap9Ta_E-A
DB
_revised (4)
Mitigative Measure (Cont’d)
Environmental Impacts Mitigative Measures Monitoring Programme Responsibility
1. General Measure (Cont’d) (4) To routinely maintain and inspect the operation
of the cooling system so as to keep it in good and
safe condition for the operators and the public living
in the nearby areas.
(5) In case the environmental monitoring results
demonstrate a trend of an induced problem including
the complaints (caused by the project
implementation) from the communities, the company
is required to promptly take the improvement and
corrective actions for such problem and report every
event to the permitting agencies of Saraburi Province,
Phra Nakhon Si Ayutthaya Province, and the Office
of Natural Resources and Environmental Policy and
Planning so as to coordinate the cooperation for
solving the problem.
(6) If the company purposes to modify the details of
the project and/or the environmental action plan, it
must notify the permitting agencies about such
modification for their review as follows:
- If the permitting agencies regard such
modification as not having an effect on the
impact assessment in the approved EIA report,
the company shall notify the Office of Natural
Resources and Environmental Policy and
Planning about this matter.
- Power Generation
Supply Co., Ltd.
Environm
ental Report for submittal to AD
B N
ong-Saeng Power Plant Project
C
hapter 9 Pow
er Generaton Supply C
o., Ltd. Environmental M
anagement Plan
T-EIA208102
9-6
F208102Chap9Ta_E-A
DB
_revised (4)
Mitigative Measure (Cont’d)
Environmental Impacts Mitigative Measures Monitoring Programme Responsibility
1. General Measure (Cont’d) - If the permitting agencies regard such
modification as having an effect on the impact
assessment in the approved EIA report, the
company shall submit the data of the impact
study and assessment results of such
modification in details and in comparison with
the original data to the EIA Expertise
Committee for approval before
implementation.
(7) In case there is any project-related complaint
from the communities, the Company must promptly
solve the problem (addressed in the complaint) and
record it as a report.
(8) If the project is not implemented within 2 years
from the date of the letter from ONEP notifying the
results of the review and approval of the
environmental impact assessment report by the EIA
Expertise Committee, the project shall revise the data
and environmental measures and submit them to
ONEP for review.
(9) When the project is operated at the steady state,
and it is found that the aforementioned emission rates
are lower, the project is required to use them as the
control values and notify ONEP promptly.
- Power Generation
Supply Co., Ltd.
Environm
ental Report for submittal to AD
B N
ong-Saeng Power Plant Project
C
hapter 9 Pow
er Generaton Supply C
o., Ltd. Environmental M
anagement Plan
T-EIA208102
9-7
F208102Chap9Ta_E-A
DB
_revised (4)
Mitigative Measure (Cont’d)
Environmental Impacts Mitigative Measures Monitoring Programme Responsibility 2. Air Quality Pre-Construction Phase
- The ambient air quality monitoring systems (AAQMS) are installed in 4 community areas including Ban Thamsinthusopa, Ban Nong-Tangbun, Ban Nong-Ngu-Loem and Ban Khok Daeng for continuous monitoring of the concentrations of total suspended particulates, PM-10, sulfur dioxide, nitrogen dioxide, wind speed and direction, and ambient temperature.
Pre-Construction Phase Ambient Air Quality Ambient Air Quality Monitoring Systems (AAQMS) Parameter - TSP (average 24-hr) - PM-10 (average 24-hr) - NO2 (average 1-hr) - SO2 (average 1-hr and 24-hr) - Wind speed and wind direction
- Power Generation Supply Co., Ltd.
Construction Phase - To spray water, at least twice a day, on the soil
piles and the areas where excavation of soil is taking place, particularly on the communication routes within the project area.
- To cover the piles of soil and scrap materials with canvases or plastic sheets to prevent the soil dispersion during windy period.
- To have good housekeeping in the construction area.
- To limit the speed of motor vehicles within the construction area not to exceed 20 kilometers per hour.
- To limit the speed of the contractor’s motor vehicles on public roads not to exceed 60 kilometers per hour.
- Ambient temperature Location - Ban Tamsinthusopa - Ban Nong-Tangbun - Ban Nong-Ngu-Loem - Ban Khok Daeng Duration/Frequency - 24 hours continuously Analytical Method - TSP and PM-10 : Beta Ray or Taper Element
Oscillating Microbalance - NO2 : Chemiluminescence Method - SO2 : UV Fluorescence Method / Pararosaniline - Wind speed and wind direction : Cup Anemometer /
Anodized Aluminum Vane/Ultrasonic Anemometer - Temperature : Temperature Sensor Expense - Installation cost for AAQMS, approximately
10,000,000 baht - Maintenance cost for AAQMS, approximately
1,000,000 baht
Environm
ental Report for submittal to AD
B N
ong-Saeng Power Plant Project
C
hapter 9 Pow
er Generaton Supply C
o., Ltd. Environmental M
anagement Plan
T-EIA208102
9-8
F208102Chap9Ta_E-A
DB
_revised (4)
Mitigative Measure (Cont’d) Environmental Impacts Mitigative Measures Monitoring Programme Responsibility
2. Air Quality (Cont’d) - To well-cover the transported materials/articles for the entire transportation routes.
- To provide the workers for cleaning the traffic surface of public road in front of the project area after the trucks going in or out of the project area.
- To clean vehicle wheels before leaving the construction area in order to reduce the amount of soil particles (stuck on the wheels) falling off onto the traffic surface.
- To prohibit rubbish burning within the construction area.
To Audit AAQMS Parameter - TSP (average 24-hr) - PM-10 (average 24-hr) - NO2 (average 1-hr) - SO2 (average 1-hr and 24-hr) - Wind speed and wind direction - Ambient temperature Location - Ban Tamsinthusopa - Ban Nong-Tangbun
- Power Generation Supply Co., Ltd.
Operation Phase - To install NOx control systems, i.e., the dry low
NOx combustion system and water injection system for controlling NOx emission when natural gas and diesel oil are used as fuel respectively. • To control the stack emission rates, when using
natural gas as fuel, in accordance with the designed values for the 100% operating load as follows:
• Sulfur dioxide - not to exceed 10 ppm at 7% O2.
- Ban Nong-Ngu-Loem - Ban Khok Daeng Duration/Frequency - Once a year Analytical Method - To audit AAQMS in accordance with US.EPA.
standard or other method recommended by the concerned government agency.
Expense - 500,000 baht per time
or not to exceed 7.74 grams per second stack.
• Oxides of nitrogen - not to exceed 70 ppm at 7% O2.
or not to exceed 38.93 grams per second per stack.
Construction Phase Ambient Air Quality Ambient Air Quality Monitoring Systems (AAQMS) Parameter - TSP (average 24-hr) - PM-10 (average 24-hr) - NO2 (average 1-hr)
Environm
ental Report for submittal to AD
B N
ong-Saeng Power Plant Project
C
hapter 9 Pow
er Generaton Supply C
o., Ltd. Environmental M
anagement Plan
T-EIA208102
9-9
F208102Chap9Ta_E-A
DB
_revised (4)
Mitigative Measure (Cont’d)
Environmental Impacts Mitigative Measures Monitoring Programme Responsibility
2. Air Quality (Cont’d) • Particulate Matter - not to exceed 20 per cubic meter at 7% O2.
or not to exceed 5.92 grams per second per stack. - To control the stack emission rates, when using
diesel oil as fuel, in accordance with the designed values for the 100% operating load as follows: • Sulfur dioxide - not to exceed 30 ppm at 7% O2
or not to exceed 22.41 grams per second per stack.
• Oxides of nitrogen - not to exceed 120 ppm at 7% O2. or not to exceed 64.37 grams per second per stack.• Particulate matter - not to exceed 35 at 7% O2. per cubic meter
or not to exceed 9.99 second per stack. - To install the continuous emission monitoring
systems (CEMs) at the HRSG stacks for continuously monitoring the emission rates and thus controlling the air emission sources of the
- SO2 (average 1-hr and 24-hr)
- Wind speed and wind direction
- Ambient temperature Location - Ban Tamsinthusopa - Ban Nong-Tangbun
- Ban Nong-Ngu-Loem - Ban Khok Daeng Duration/Frequency - 24 hours continuously Analytical Method - TSP and PM-10 : Beta Ray or Taper Element
Oscillating Microbalance - NO2 : Chemiluminescence Method - SO2 : UV Fluorescence Method / Pararosaniline - Wind speed and wind direction : Cup Anemometer/
Anodized Aluminum Vane / Ultrasonic Anemometer
- Temperature : Temperature Sensor
Expense - Maintenance cost for AAQMS, approximately
1,000,000 baht
- Power Generation Supply Co., Ltd.
power plant. The parameters to be monitored include oxides of nitrogen, sulfur dioxide, particulates, carbon monoxide and oxygen.
- To audit the continuous emission monitoring systems (CEMs) once a year.
Operation Phase Stack Emission from Power Plant Continuous Emission Monitoring System (CEMs) Parameter - Oxides of nitrogen (NOx)
Environm
ental Report for submittal to AD
B N
ong-Saeng Power Plant Project
C
hapter 9 Pow
er Generaton Supply C
o., Ltd. Environmental M
anagement Plan
T-EIA208102
9-10
F208102Chap9Ta_E-A
DB
_revised (4)
Mitigative Measure (Cont’d)
Environmental Impacts Mitigative Measures Monitoring Programme Responsibility
2. Air Quality (Cont’d) - To install a monitor screen, at a location in front of
the project, for displaying the results of stack
emission and ambient air quality monitoring.
- To install a warning system for the case that the
emission rates approach the designed values.
- To prepare the measures and operating procedures
for the case the emission rate reduction is required,
e.g., reduction of generating capacity. However, in
case the air emission rate(s) still exceeds the
designed value, the power plant shall be shutdown.
- To shutdown the machinery in case of NOx control
system failure.
- To routinely inspect and maintain the ambient air
quality monitoring systems (AAQMS) which are
installed in 4 community areas so that these
equipment can accurately monitor the
concentrations of total suspended particulates,
PM10, sulfur dioxide and nitrogen dioxide in the
ambient air.
- To improve the condition of Wat Nongkratart and
Wat Nongkratart School areas (currently covered
with sand) by covering the pavements with
concrete blocks with a total surface area of
approximately 500 square meters, and paving the
- Sulfur dioxide (SO2)
- Particulate matter (PM)
- Carbon monoxide (CO)
- Oxygen (O2)
- Gas flow rate
Location
- 4 HRSG stacks of Nong-Saeng Power Plant
Duration/Frequency
- During operation period
Monitoring Method
- According to Notification of Ministry of Industry
(B.E.2544), specifying that every factory must
install an instrument for automatic monitoring of
stack emission.
Reporting
- To summarize the monitoring results and submit to
ONEP every 6 months. In case of non-
compliances, the duration of exceedance, causes
and corrective actions are to be reported.
Expense - Installation cost for CEM, approximately
8,000,000 baht - Maintenance cost for CEM, approximately 200,000
baht
- Power Generation
Supply Co., Ltd.
Environm
ental Report for submittal to AD
B N
ong-Saeng Power Plant Project
C
hapter 9 Pow
er Generaton Supply C
o., Ltd. Environmental M
anagement Plan
T-EIA208102
9-11
F208102Chap9Ta_E-A
DB
_revised (4)
Mitigative Measure (Cont’d)
Environmental Impacts Mitigative Measures Monitoring Programme Responsibility
2. Air Quality (Cont’d) roadways with concrete or asphalt with a total
surface area of 2 x 260 square meters in order to
reduce dust dispersion.
- To promote organic agricultural practice for local
farmers by providing the training course on
“Agricultural development to organic agricultural
practice” with an aim to reduce their production
cost (investment cost) by not burning straws and
rice stubbles but fermenting rice straws to produce
organic fertilizer. The fertilizer will be used for soil
conditioning of paddy fields under the
methodology of “New Agricultural Theory” which
encourages the farmers to lessen such burning of
straws and rice stubbles and thus alleviate the
generated dust concentration.
- To monitor the health examination results within 1
year after the commencement of the project
operation.
To compile the morbidity data every year after the
project operation and to compare the morbidity
statistics of the local residents living around the
project area before and after the project
implementation
To Audit CEMs (Audit/RAA/RATA) Parameter
- Oxides of nitrogen (NOx)
- Sulfur dioxide (SO2)
- Particulate matter (PM)
- Carbon monoxide (CO)
Oxygen (O2)Location
- 4 HRSG stacks of Nong-Saeng Power Plant
Duration/Frequency
- Once a year
Measurement Method
- To audit (RATA/RAA) CEMs in accordance with
US. EPA. standard or other method recommended
by the concerned government agency.
Expense - 500,000 baht per time Occasionally Monitoring
Parameter
- Sulfur dioxide (SO2)
- Oxides of nitrogen (NOx)
- Particulate matter (PM)
- Carbon monoxide (CO)
- Oxygen (O2)
Location
- 4 HRSG stacks of Nong-Saeng Power Plant
- Power Generation
Supply Co., Ltd.
Environm
ental Report for submittal to AD
B N
ong-Saeng Power Plant Project
C
hapter 9 Pow
er Generaton Supply C
o., Ltd. Environmental M
anagement Plan
T-EIA208102
9-12
F208102Chap9Ta_E-A
DB
_revised (4)
Mitigative Measure (Cont’d)
Environmental Impacts Mitigative Measures Monitoring Programme Responsibility
2. Air Quality (Cont’d) Duration/Frequency
- Twice a year
Measurement Method
- Sulfur dioxide (SO2) : US. EPA. Method 6/6C
- Oxides of nitrogen (NOx) : US. EPA. Method 7/7E
- Particulate matter (PM) : US. EPA. Method 5
- Carbon monoxide (CO) : US. EPA. Method 10
- Oxygen (O2) : US. EPA. Method 3A
Expense
- 200,000 baht per time
In addition to the fixed monitoring stations, at least
for first few years of full operations, a mobile air
quality monitoring station will be provided (if
required) and operate it in conjunction with air
quality model to capture ambient air at the likely
areas of maximum ground level concentration.
3. Noise Construction Phase
- To install iron or zinc sheets of the minimum
thickness of 1.3 millimeters around the
construction area, particularly on the side nearby
the residential areas of Ban Thamsinthusopa and
Ban Nong-Tangbun communities, and to construct
earth dike of 4.5 meters high above the ground
level, around the project area.
- Piling and construction activities generating loud
noises shall be carried out during daytime only
Construction Phase
Parameter - Leq 24
- Ldn
- L90
Location
- Ban Tamsinthusopa
- Ban Nong-Tangbun
- Ban Nong-Ngu-Loem
- Ban Khok Daeng
- Power Generation
Supply Co., Ltd.
Environm
ental Report for submittal to AD
B N
ong-Saeng Power Plant Project
C
hapter 9 Pow
er Generaton Supply C
o., Ltd. Environmental M
anagement Plan
T-EIA208102
9-13
F208102Chap9Ta_E-A
DB
_revised (4)
Mitigative Measure (Cont’d)
Environmental Impacts Mitigative Measures Monitoring Programme Responsibility
3. Noise (Cont’d) (0 6.00 am-07.00 pm.) with a notice to inform the
communities at least 2 weeks in advance.
- To select and use the equipments/machineries and
construction technique(s) that cause the minimum
noise levels.
- To avoid using the equipments or machineries
- The fence of the project or the nearest house to the
project
- A chicken farm within 1 km radius from the project
site.
- A chicken farm within 1 to 2 km radius from the
project site
- Power Generation
Supply Co., Ltd.
simultaneously that cause the loud noises
continuously for a long period of time.
- To reduce the number of equipments/machineries
used in the area adjacent to each other.
To install the frequently movable (back and forth)
equipments/machineries in the sensitive areas as
for as possible.
- To stop the engines or turn off the
equipments/machineries when they are not in use
every time.
- To require the contractor to install the noise
Duration/Frequency
- Twice a year for 5 consecutive days and coincide
the measurements with the peak construction
activity/loud noise generating activity during that
quarter.
Measurement Method - Integrated Sound Level Measurement or equivalent
method recommended by the concerned
government agency. Expense
- 70,000 baht per time
reduction equipment, e.g., silencers or mufflers at
the loud noise equipments/machineries used in the
construction activities and to regularly check the
efficiency of these noise reduction equipment.
Operation Phase
- Leq 24
- Ldn
- L90
- To inspect and maintain the equipments,
machineries and engines to be in good condition by
scheduling the inspection of heavy machineries at
least once a month.
- To post a warning sign in the loud noise areas and
Location
- Ban Tamsinthusopa
- Ban Nong-Tangbun
- Ban Nong-Ngu-Loem
- Ban Khok Daeng
Environm
ental Report for submittal to AD
B N
ong-Saeng Power Plant Project
C
hapter 9 Pow
er Generaton Supply C
o., Ltd. Environmental M
anagement Plan
T-EIA208102
9-14
F208102Chap9Ta_E-A
DB
_revised (4)
Mitigative Measure (Cont’d)
Environmental Impacts Mitigative Measures Monitoring Programme Responsibility
3. Noise (Cont’d) to enforce the workers to wear noise protective
devices, such as ear muffs, ear plugs, etc. before
entering the loud noise workplace.
- The fence of the project or the nearest house to the
project .
- A chicken farm within 1 km radius from the project
- Power Generation
Supply Co., Ltd.
Operation Phase
- To install the combustion turbines and loud noise
equipments such as gas compressors within the
building(s) equipped with acoustic walls and
enclosures.
- Loud noise machineries of Nong-Saeng Power
Plant Project to be installed must be equipped with
silencers at the pipe ends where loud noise may be
generated.
- To routinely check the efficiency of silencers.
- To cover up the combustion and steam turbines in
order to reduce their noise levels.
site.
- A chicken farm within 1 to 2 km radius from the
project site.
Normally, startup and shutdown will occur
infrequently as IPP power plant are operated as base
load plants
Duration/Frequency Twice a year for 5 consecutive days.
Measurement Method - Integrated Sound Level Measurement or equivalent
method recommended by the concerned
government agency.
Expense
- 70,000 baht per time
- To inspect the equipments and machineries in order
to keep them in good condition by clearly
establishing a maintenance plan for each equipment
and machinery.
- To post the signs or symbols in the areas where
noise levels exceed 80 dB(A).
- To provide the personal protective devices, e.g., ear
muffs or ear plugs for the employees working in
the area where noise levels exceed 80 dB (A).
Environm
ental Report for submittal to AD
B N
ong-Saeng Power Plant Project
C
hapter 9 Pow
er Generaton Supply C
o., Ltd. Environmental M
anagement Plan
T-EIA208102
9-15
F208102Chap9Ta_E-A
DB
_revised (4)
Mitigative Measure (Cont’d)
Environmental Impacts Mitigative Measures Monitoring Programme Responsibility
3. Noise (Cont’d) - To specify zone of loud noise area, such as the
areas of HRSG, combustion chamber of gas
turbine, and gas turbine generators; along with
posting the warning signs. The workers working in
such areas have to wear the noise protective
devices, such as ear plugs, ear muffs, etc.
4. Surface Water Hydrology
and Surface Water
Quality
Measure on Surface Water Hydrology
Construction Phase
- In the construction area prior to making the land
preparation and the construction of buildings or
structures, an earth dike of 4.5 meters high and a
drainage ditch on the outside of the dike are to be
constructed to prevent the sediment from being
washed away from the construction area and to let
the storm water from the rainfall over the areas
outside the project site flow and drain through
without being obstructed by the project area.
- For the storm water to be pumped and drained from
Construction Phase
Surface Water Quality
Parameter
- pH
- Suspended Solids (SS)
- Total Dissolved Solids (TDS)
- BOD5
- Fecal Coliform Bacteria
Location
- Klong Huaiba (Klong Nong-Ngu-Loem)
• 500 meters upstream of Nong-Saeng Power
Plant Project Site.
- Power Generation
Supply Co., Ltd.
the inside to the outside of the construction area,
the sump must be provided for sediment settling
(with the retention time of not less than 3 hours)
before discharging to the outside
• Discharge point of the project.
• 500 meters downstream of the project’s
discharge point.
Duration/Frequency
Operation Phase
- For the cooling water blow down from the cooling
system to be drained into Khlong Huaiba (Khlong
- Every 3 months
Expense
Included in the construction cost.
Environm
ental Report for submittal to AD
B N
ong-Saeng Power Plant Project
C
hapter 9 Pow
er Generaton Supply C
o., Ltd. Environmental M
anagement Plan
T-EIA208102
9-16
F208102Chap9Ta_E-A
DB
_revised (4)
Mitigative Measure (Cont’d)
Environmental Impacts Mitigative Measures Monitoring Programme Responsibility
4. Surface Water Hydrology
and Surface Water
Quality (Cont’d)
Nong-Ngu-Loem), the water level of this Khlong is
to be inspected at the discharge point. If the water
level of this canal is found to be lower than 3.5
meters (5.5 meters msl.), the project can drain the
cooling water blow down. If the water level is close
to 3.63 meters (5.63 meters msl.), the project must
stop draining the cooling water blow down.
Effluent quality
Parameter
- pH
- Temperature
- Total Dissolved Solids (TDS)
- Suspended Solids (SS)
- BOD5
- Power Generation
Supply Co., Ltd.
- The reservoir capacity is 1.6 million cubic meters.
Water consumption during full load operation at
design condition will be 46,932 cubic meters per
day. The reservoir capacity is enough for 34 day
operation at such condition.
- The reservoir will retain the effluent when the
water level of Khlong Huaiba (Khlong Nong-Ngu-
Loem) is higher than 3.5 meters (5.5 meters msl.).
- Dredging to remove the weeds and sediment in
Khlong Huaiba (Khlong Nong-Ngu-Loem) at the
- Oil & Grease
- TKN
- Free Chlorine
- Fecal Coliform Bacteria
Location
- Holding Pond of Nong-Saeng Power Plant
Duration/Frequency
- All months during construction period
Expense
- Included in the construction cost.
discharge point regularly Operation Phase
Measures on Surface Water quality
Construction Phase
- The sanitary wastewater from the construction
workers must be treated to meet the effluent quality
standard, i.e., the BOD value of not more than 20
milligrams per liter and the total suspended solids
of not more than 30 milligrams per liter.
Surface Water Quality
Parameter
- Temperature
- pH
- Suspended Solids (SS)
- Total Dissolved Solids (TDS)
- BOD5
Environm
ental Report for submittal to AD
B N
ong-Saeng Power Plant Project
C
hapter 9 Pow
er Generaton Supply C
o., Ltd. Environmental M
anagement Plan
T-EIA208102
9-17
F208102Chap9Ta_E-A
DB
_revised (4)
Mitigative Measure (Cont’d)
Environmental Impacts Mitigative Measures Monitoring Programme Responsibility
4. Surface Water Hydrology and Surface Water Quality (Cont’d)
- The toilets for the construction workers must be not less than 30 meters distance from the surface water resources outside the project area. The wastewater treatment system must be provided for treating the sanitary wastewater so that the quality of treated effluent meets the effluent standard.
- The treated effluent is used for spraying over the construction area and the vacant areas to reduce dust dispersion, but not discharging into Khlong Huaiba (Khlong Nong-Ngu-Loem). It is a must to control and make sure that the garbages and scraps of construction materials are not disposed into the water resources outside the project area. Containers are provided for collecting the solid wastes which are to be sanitary disposed. The workers will be trained on the rules for practice.
- COD - Heavy Metals: Ferric (Fe), Manganese (Mn), Lead
(Pb), Zinc (Zn), Chromium Hexavalent (Cr6+), Copper (Cu) and Nickel (Ni)
Location - Khlong Huaiba (Khlong Nong-Ngu-Loem) • 500 meters upstream of the discharge point of
Nong-Saeng Power Plant Project. • Discharge point of the project. • 500 meters downstream of the project’s
discharge point. Duration/Frequency - Avery 3 months Expense - 20,000 baht per time (analysis only) Effluent Quality Parameter
Operation Phase - The treated effluent from the cooling system of the
project shall meet the effluent standard under the Order of the Royal Irrigation Department No.883/ 2532, entitled “The mitigation of low quality effluent discharge into the irrigation waterways and the waterways connected with them within the irrigation project areas,” and the industrial effluent standard under the Notification of the Ministry of Industry, No.2 B.E.2539 (1996) before draining into Khlong Huaiba (Khlong Nong-Ngu-Loem).
- pH - Temperature - Total Dissolved Solids (TDS) - Suspended Solids (SS) - COD - Oil & Grease - Heavy Metals: Ferric (Fe), Manganese (Mn), Lead
(Pb), Zinc (Zn), Chromium Hexavalent (Cr6+), Copper (Cu) and Nickel (Ni)
- Free Chlorine
Environm
ental Report for submittal to AD
B N
ong-Saeng Power Plant Project
C
hapter 9 Pow
er Generaton Supply C
o., Ltd. Environmental M
anagement Plan
T-EIA208102
9-18
F208102Chap9Ta_E-A
DB
_revised (4)
Mitigative Measure (Cont’d)
Environmental Impacts Mitigative Measures Monitoring Programme Responsibility
4. Surface Water Hydrology
and Surface Water
Quality (Cont’d)
- To make the most possible reuses of the non-
cooling water effluent which is treated, for
example, watering plants, cleaning the machinery,
cleaning floor in the power plant, etc. without
draining to the outside.
- To provide the cooling blowdown ponds to retain
the effluent from the cooling tower for at least 3
days and to install a temperature monitoring system
for continuously measuring the effluent
temperature. If the effluent temperature is higher
than 34 oC, its discharge to the outside must be
halted; and the effluent temperature is to be
reduced not to exceed 34 oC before discharging to
the outside.
- To continuously record the quantities of water to be
pumped from the Pa-Sak River and compare with
the estimated values in the report.
- To provide a budget for supporting the activities of
local administrative organization of the Tambon
which is responsible for the areas along the course
of Klong Huaiba (Klong Nong-Ngu-Loem),
including dredging to remove the weeds/sediment
that may pile up and shallower the canal. This will
help to facilitate the water flow and drainage, and
to alleviate the problems of decomposed and
stagnant water as well as flooding from natural
overflowing of water.
Location - Holding Pond of Nong-Saeng Power Plant before
discharge
Duration/Frequency - Every 3 months
Expense - 40,000 baht per time (analysis only)
Online Monitoring
Parameter
- Temperature
- pH
- Conductivity
Location
- The point prior to draining the effluent to Khlong
Huaiba (Khlong Nong-Ngu-Loem)
Duration/Frequency
- All the time
Monitoring Method
- Continuously monitoring of temperature,
conductivity and pH.
Expense - Installation cost for the online water quality
monitor is approximately 3,000,000 baht.
- Maintenance cost for the online water quality
monitor is approximately 300,000 baht per year.
- Power Generation Supply Co., Ltd.
Environm
ental Report for submittal to AD
B N
ong-Saeng Power Plant Project
C
hapter 9 Pow
er Generaton Supply C
o., Ltd. Environmental M
anagement Plan
T-EIA208102
9-19
F208102Chap9Ta_E-A
DB
_revised (4)
Mitigative Measure (Cont’d)
Environmental Impacts Mitigative Measures Monitoring Programme Responsibility
4. Surface Water Hydrology
and Surface Water
Quality (Cont’d)
- To support the local administrative organization of
the Tambon, in conjunction with the local
residents, to oversee Klong Huaiba (Klong Nong-
Ngu-Loem) and other surface water resources
around the project site, and to manage the
wastewater from the communities by training the
local residents on the treatment of wastewater from
households and livestock using a self-constructed
system, employing the local residents to dredge the
canals, applying herbs as insect repellent to reduce
the toxic substance being discharged into the water
resources, etc.
- Power Generation
Supply Co., Ltd.
5. Forestry and Wildlife
Ecology
Measure on Forestry
Construction Phase
- To prohibit the construction workers from cutting
trees in the areas outside the construction site area.
- After the land preparation for the construction area
is completed, it is required to plant the trees
immediately in the portions of land without any
construction activities and designated as the
project’s green areas.
Construction Phase
Wildlife
Parameter
- Survey of wildlife around the project area
including species, status and abundance
Location
- Within a radius of 5 kilometers around the project
site.
Duration/Frequency
- Power Generation
Supply Co., Ltd.
Operation Phase
- To plant perennial trees or bushes around the
power plant location, reservoir and holding ponds
- Six months from the beginning of the construction.
Expense
- 200,000 baht per time
with a total area of not less than 5% of the project
area.
Operation Phase
Wildlife
Environm
ental Report for submittal to AD
B N
ong-Saeng Power Plant Project
C
hapter 9 Pow
er Generaton Supply C
o., Ltd. Environmental M
anagement Plan
T-EIA208102
9-20
F208102Chap9Ta_E-A
DB
_revised (4)
Mitigative Measure (Cont’d)
Environmental Impacts Mitigative Measures Monitoring Programme Responsibility
5. Forestry and Wildlife
Ecology (Cont’d)
- To arrange the activities in conjunction with the
local administrative organization of the Tambon
where the project is located and the nearby local
administrative organizations on conservation of
perennial trees, planting perennial trees in public
areas and places such as temples and schools as
appropriate, e.g., on the National Environment
Day, Songkran Day, etc.
Parameter
- Survey of wildlife around the project area for the
study of their diversity, species, abundance and
survival in the project area.
Location
- Within a radius of 5 kilometers around the project
site.
- Duration/Frequency
Measures for Wildlife
Construction Phase - The construction of the project requires cutting
down of big trees which are the habitats of
openbills and egrets. However, these birds only
nest and lay eggs during their mating/breeding
season (around October through April) so there are
no active bird nests on the trees in other months of
the year. Therefore, tree cutting off their
mating/breeding season will not destruct any nests
and baby birds. The implementation of various
activities will not impose any impact on the
wildlife either, and thus it will not be necessary to
require any direct measures for mitigating the
impact on the wildlife and the problem (if any) can
be solved by only selecting the right time for the
activities.
- At the beginning of the project operation and every
3 years thereafter with a survey in each of the rainy
and winter seasons of the year and for a total time
period of 10 years. If the findings do not indicate
any tendency of the project-induced impact, the
survey will be terminated.
Expense
- 200,000 baht per time
Environm
ental Report for submittal to AD
B N
ong-Saeng Power Plant Project
C
hapter 9 Pow
er Generaton Supply C
o., Ltd. Environmental M
anagement Plan
T-EIA208102
9-21
F208102Chap9Ta_E-A
DB
_revised (4)
Mitigative Measure (Cont’d)
Environmental Impacts Mitigative Measures Monitoring Programme Responsibility
5. Forestry and Wildlife
Ecology (Cont’d)
Nevertheless, the mitigation measures should be
established in order to maintain sustainable
conservation of the wildlife resource as follows:
- The plan for cutting all the big trees in the project
area must be implemented during other months of
the year instead of winter’s months. This will
prevent the destruction of the nests and baby birds
of openbills and egrets, and the parent birds will be
able to find the new places for their nesting so no
impact is imposed.
- Rules will be made to prohibit the workers and
personnel from hunting the wildlife or destructing
the lives of any species of wildlife in the project
area and its vicinity as well as to prohibit the
outsiders from such wildlife hunting.
- Power Generation
Supply Co., Ltd.
Operation Phase
- To plant perennial trees around the boundary of the
project area, the project area and around the
reservoir for bird habitats with a total area of not
less than 5% of the project area.
- To prohibit the workers and personnel from
hunting or trapping the wildlife in the power plant
and reservoir areas of the project.
- To support the arrangement of wildlife
conservation activities of the local administrative
organization of the Tambon, students and the
Environm
ental Report for submittal to AD
B N
ong-Saeng Power Plant Project
C
hapter 9 Pow
er Generaton Supply C
o., Ltd. Environmental M
anagement Plan
T-EIA208102
9-22
F208102Chap9Ta_E-A
DB
_revised (4)
Mitigative Measure (Cont’d)
Environmental Impacts Mitigative Measures Monitoring Programme Responsibility
5. Forestry and Wildlife Ecology (Cont’d)
public including such title of activities as birds, etc. This should be carried out as appropriate in order to render an opportunity for the local administrative organization of the Tambon to participate and make comments.
6. Aquatic Ecology and Fishery
Construction Phase - To prohibit the construction workers from fishing
in Klong Rapeepatana and Klong Huaiba (Klong Nong-Ngu-Loem) by making rules and posting ‘No Fishing’ signs.
Construction Phase Aquatic Ecology Parameter - Phytoplanktons - Zooplanktons
- Power Generation Supply Co., Ltd.
Operation Phase - To prohibit the employees and workers of the
power plant from fishing in Klong Huaiba (Klong Nong-Ngu-Loem) and Klong Rapeepatana.
- Benthos Location - Klong Huaiba (Klong Nong-Ngu-Loem) 500 meters upstream of Nong-Saeng Power Plant
- To provide breeds of fish, such as snake-head fish and Nile tilapia and release them into Klong Huaiba (Klong Nong-Ngu-Loem).
- To arrange the events of activities, in conjunction with the local administrative organizations of the Tambon around the project site and the public, on the release of fish breeds into the public water resources as appropriate under the suggestion of local residents.
Project Site. • Discharge point of the project. • 500 meters downstream of the project’s
discharge point. Duration/Frequency - Every 3 months throughout the construction period Sampling Method - Phytoplanktons: to be sampled vertically using a
plankton net of approximately 20-60 micron size. - Zooplanktons, fish roes and larva: to be sampled
vertically using plankton nets of approximately 100-200 micron size for zooplanktons and 300 micron size for fish roes and larva.
Environm
ental Report for submittal to AD
B N
ong-Saeng Power Plant Project
C
hapter 9 Pow
er Generaton Supply C
o., Ltd. Environmental M
anagement Plan
T-EIA208102
9-23
F208102Chap9Ta_E-A
DB
_revised (4)
Mitigative Measure (Cont’d)
Environmental Impacts Mitigative Measures Monitoring Programme Responsibility
6. Aquatic Ecology and
Fishery (Cont’d)
- Benthos: to be sampled using an Ekman Grab
(seabed sediment sampler)
Expense
- 100,000 baht per time
- Power Generation
Supply Co., Ltd.
Operation Phase
Parameter
- Phytoplanktons
- Zooplanktons
- Benthos
Location
- The Pa-Sak River
• 200 meters upstream of the water pumping point
of Nong-Saeng Power Plant Project.
• Water pumping point of the project.
• 200 meters downstream of the project’s water
pumping point.
- Klong Huaiba (Klong Nong-Ngu-Loem)
• 500 meters upstream of the discharge point of
Nong-Saeng Power Plant Project.
• Discharge point of the project.
• 500 meters downstream of the project’s
discharge point.
Duration/Frequency
• Every 6 months
Expense
- 200,000 baht per time
Environm
ental Report for submittal to AD
B N
ong-Saeng Power Plant Project
C
hapter 9 Pow
er Generaton Supply C
o., Ltd. Environmental M
anagement Plan
T-EIA208102
9-24
F208102Chap9Ta_E-A
DB
_revised (4)
Mitigative Measure (Cont’d)
Environmental Impacts Mitigative Measures Monitoring Programme Responsibility
7. Land Use Construction Phase
- To carry out the construction activities only within
the project area and to absolutely prohibit
placing/piling/parking of equipments, machineries,
materials, etc. outside the project area.
- To clearly notify the concerned government
agencies and local residents about the areas to be
used for construction, construction boundary, and
construction schedule at least one month before the
construction activities commence.
- To do the maintenance works on the damaged
traffic surface in order to restore its original
condition as per the requirements of the concerned
government agencies.
- Power Generation
Supply Co., Ltd.
- To control the construction activities as per the
required plan.
- In case the construction involves crossing of the
private roadway(s), additional measures are set up
as follows: - To inform the land owner(s) in advance about the
construction plan and schedule; and after the
pipeline construction in any excavated trench(s) is
completed, the soil must be put back in its original
place. If such work can not be completed within the
same day, metal sheets must be placed over each
excavated trench(s) so that the area can be used for
regular communication.
Environm
ental Report for submittal to AD
B N
ong-Saeng Power Plant Project
C
hapter 9 Pow
er Generaton Supply C
o., Ltd. Environmental M
anagement Plan
T-EIA208102
9-25
F208102Chap9Ta_E-A
DB
_revised (4)
Mitigative Measure (Cont’d)
Environmental Impacts Mitigative Measures Monitoring Programme Responsibility
7. Land Use (Cont’d) - To string a rope around the construction area adjacent to each of these roadways and also install the lights and post a warning sign.
- To appoint a committee on supervision and control of social performance in order to follow up the construction activities, negotiate with the land owner(s), and to solve the arisen problems. The committee have the following functions: • To inform the communities about the
complaint(s)/problem(s) by posting announcement in the public places (not less than 3 places) within the jurisdiction areas of the related Tambons.
- Power Generation Supply Co., Ltd.
• To inspect all evidences and may invite the experts to jointly investigate in case of complicated problems.
• To inform the communities about the investigation results by posting announcement in the public places (not less than 3 places) within the jurisdiction areas of the related Tambons.
• In case the problem or complaint is caused by the project, the committee will advise the project to solve it and be liable for the resultant damages.
• In case the project is unable to solve the problem, the committee will inform the concerned government agencies, e.g., the Office of Provincial Industry, Administrative Organization of the Tambons, etc.
Environm
ental Report for submittal to AD
B N
ong-Saeng Power Plant Project
C
hapter 9 Pow
er Generaton Supply C
o., Ltd. Environmental M
anagement Plan
T-EIA208102
9-26
F208102Chap9Ta_E-A
DB
_revised (4)
Mitigative Measure (Cont’d)
Environmental Impacts Mitigative Measures Monitoring Programme Responsibility
8. Water Usage Construction Phase Measures are established to prevent the scraps of construction materials from being washed into Klong Huaiba (Klong Nong-Ngu-Loem) which may cause difficulty in using the irrigation water.
Construction Phase To monitor the construction in order to ensure that no scraps of material are dropped into and obstruct the flow of Klong Rapeepatana and Klong Huaiba (Klong Nong-Ngu-Loem) which will, in turn, obstruct the usage of water from Klong Rapeepatana- Main Canal for irrigation, consumption and factories, and the usage of water from Klong Huaiba (Klong Nong-Ngu-Loem) for agriculture.
- Power Generation Supply Co., Ltd.
Operation Phase A reservoir with the capacity of 1,600,000 cubic meters is to be constructed for water storage of the project and water will be added into this reservoir when the demand for irrigation water is less than the quantity of river water at the water pumping point during May through November. Coordination with the Royal Irrigation Department will be managed to obtain the water from the Pa-Sak Cholsithi Reservoir so that no impact imposes on the water usage for irrigation, consumption and factories at the downstream of the water pumping point.
Operation Phase
• Water consumption during full load operation at design condition will be 46,932 cubic meters per day. The reservoir capacity is enough for 34 day operation at such condition.
• The reservoir will retain the effluent when the water level of Khlong Huaiba (Khlong Nong-Ngu-Loem) is higher than 3.5 meters (5.5 meters msl.)
9. Transportation Construction Phase - To assign the contractor to prepare and submit a
traffic and transportation plan to the project for consideration before starting the construction activities, and to enforce them to strictly follow the traffic rules.
- Power Generation Supply Co., Ltd.
Environm
ental Report for submittal to AD
B N
ong-Saeng Power Plant Project
C
hapter 9 Pow
er Generaton Supply C
o., Ltd. Environmental M
anagement Plan
T-EIA208102
9-27
F208102Chap9Ta_E-A
DB
_revised (4)
Mitigative Measure (Cont’d)
Environmental Impacts Mitigative Measures Monitoring Programme Responsibility
9. Transportation (Cont’d) - To avoid the transportation of materials or
machineries of large size during the rush hours, i.e.,
during 07.00-09.00 a.m. and 05.00-07.00 p.m..
- Power Generation
Supply Co., Ltd.
- To avoid the transportation passing through the
community areas by using a detour around the
outskirts of the town or a special route between the
towns.
- To avoid the transportation during the time periods
of heavy rainfalls or bad visibility.
- To contact and coordinate with highway police in
advance before making any transportation of
materials or machineries of large size in order to
set up a transportation route, and to request for a
police car to facilitate and lead the way for such
transportation.
- To conduct the public relations in order to inform
the local communities and concerned government
agencies about the timetable, procedural steps and
the time periods of construction as well as the
expectedly increased traffic load due to the project
operation. This must be conducted before the
construction takes place in order to welcome
comments from and exchange the ideas with the
communities and concerned government agencies
which will be beneficial for work planning.
Environm
ental Report for submittal to AD
B N
ong-Saeng Power Plant Project
C
hapter 9 Pow
er Generaton Supply C
o., Ltd. Environmental M
anagement Plan
T-EIA208102
9-28
F208102Chap9Ta_E-A
DB
_revised (4)
Mitigative Measure (Cont’d)
Environmental Impacts Mitigative Measures Monitoring Programme Responsibility
- To limit the driving speed, i.e., not to exceed 20
kilometers per hour within the construction area
and not to exceed 60 kilometers per hour on public
roads.
9. Transportation (Cont’d) - To load the trucks in accordance with the requirement of the laws and to well cover the transported materials in order to prevent them from falling off onto the traffic surface which may cause accidents.
- To provide passenger buses for the workers to commute from their housing to the project site area in order to reduce the number of vehicles on the roads.
- To provide training on safe driving for drivers. - To post the warning signs or signals which can be
clearly seen during daytime and nighttime, at a distance of approximately 100 meters before approaching the construction area. The installation of these warning signs must be completed before the construction starts.
- To provide a security guard or personnel responsibility for making flag signals at the entrance and exit of the project construction area and the construction areas of the water pipeline along the public roads.
- To have a parking lot and to strictly prohibit parking of vehicles on the shoulders of the highways.
- Power Generation Supply Co., Ltd.
Environm
ental Report for submittal to AD
B N
ong-Saeng Power Plant Project
C
hapter 9 Pow
er Generaton Supply C
o., Ltd. Environmental M
anagement Plan
T-EIA208102
9-29
F208102Chap9Ta_E-A
DB
_revised (4)
- To install aiding equipments, e.g., metal sheets to be laid over the trenches, temporary bridges or drainage pipes for facilitating the safe and efficient transportation of machineries across the obstacles.
9. Transportation (Cont’d) - To record the statistics of accidents from the
transportation on the transporting routes, including
the details and causes of accidents for uses in the
planning and determining appropriate preventive
measures.
- To do the maintenance works on the roads that are
damaged by the transportation of
materials/equipments in order to restore to their
original condition or better.
- Power Generation
Supply Co., Ltd.
Operation Phase
- To designate clearly the traffic routes within the
project area including the installation of warning
signs and traffic signals before project operation,
and to enforce the traffic rules to be strictly
followed.
- To limit the driving speed not to exceed 20
kilometers per hour within the project area.
10. Drainage and Flood
Control
Construction Phase
- To construct a drainage ditch for collecting the
storm water, and then start the land preparation in
the dry season. To construct a dike around the land
preparation areas before the rainy season begins.
- Power Generation Supply Co., Ltd.
- To construct 2 holding ponds and 2 storm water
sumps with a total capacity of 119,000 cubic
meters in the construction site area for retaining the
Environm
ental Report for submittal to AD
B N
ong-Saeng Power Plant Project
C
hapter 9 Pow
er Generaton Supply C
o., Ltd. Environmental M
anagement Plan
T-EIA208102
9-30
F208102Chap9Ta_E-A
DB
_revised (4)
Mitigative Measure (Cont’d)
Environmental Impacts Mitigative Measures Monitoring Programme Responsibility
10. Drainage and Flood
Control (Cont’d)
storm water from the rainfalls over the project area
during the construction phase; and to control the
pumping of the discharged water into Klong
Huaiba (Klong Nong-Ngu-Loem) by observing its
water level at the discharge point. If it is found that
the water level of this canal is lower than 3.5
meters (5.5 meters msl.), the project will discharge
the water; but if the water level gets close to 3.63
meters (5.63 meters msl.), the project must stop
discharging the water.
- Power Generation Supply Co., Ltd.
Operation Phase
- To maintain the condition of the storm water
drainage ditch around the outer boundary of the
project so that the storm water can be will drained.
- To retain the effluent in the holding ponds of the
project. If it is found that the water level of Klong
Huaiba (Klong Nong-Ngu-Loem) is lower than 3.5
meters (5.5 meters msl.), the project will discharge
the water; but if the water level gets close to 3.63
meters (5.63 meters msl.), the project must stop
discharging the water.
- To divert the storm water (from the rainfalls over
the project area during the rainy season) into the
reservoir for uses in the dry season (in combination
with the water from the Pa-Sak River).
Environm
ental Report for submittal to AD
B N
ong-Saeng Power Plant Project
C
hapter 9 Pow
er Generaton Supply C
o., Ltd. Environmental M
anagement Plan
T-EIA208102
9-31
F208102Chap9Ta_E-A
DB
_revised (4)
Mitigative Measure (Cont’d)
Environmental Impacts Mitigative Measures Monitoring Programme Responsibility
11. Solid Wastes Construction Phase
- To request the contractor to segregate the solid
wastes by their types, to provide appropriate and
adequate number of containers for each type which
are installed at various points within the
construction area, and to dispose these waste
according to the Notification of the Ministry of
Industry, entitled “Disposal of Garbages or
Unwanted Materials”, 2005.
- To contract the local agency for collecting the
garbages everyday to avoid overfilling.
Construction Phase
Parameter
- Types/quantities of solid wastes and the disposal
method for each type of solid wastes.
Location
- Project area
Duration/Frequency
- Once a month during the construction period.
Measurement Method
- Collect the records of solid waste lists and receipts
of solid wastes disposal
- Power Generation
Supply Co., Ltd.
- To manage each type of solid wastes anticipated to
be generated during the construction phase which
includes scrap materials from soil excavation (e.g.,
scraps of soil, sand, brick, etc.), scraps of
construction materials (e.g., fractions of structures,
or used or unwanted materials, etc.), hazardous
wastes (e.g., batteries, motor oil, hydraulic oil,
filters, mineral oil, cleaning agents or used
solvents) as well as enamel products or rejected
paints and general garbages of approximately 5,100
kilograms per day. The project will provide a
specific area for storing each type of garbages or
solid wastes, and appropriate containers for
segregating each type of solid wastes in order to
facilitate the disposal
Operation Phase
Parameter
- Types/quantities of solid wastes and the disposal
method for each type of solid wastes
Location
- Project area.
Duration/Frequency
- Once a month during the operation period.
Measurement Method
- Collect the records of solid waste lists and receipts
of solid waste disposal.
Environm
ental Report for submittal to AD
B N
ong-Saeng Power Plant Project
C
hapter 9 Pow
er Generaton Supply C
o., Ltd. Environmental M
anagement Plan
T-EIA208102
9-32
F208102Chap9Ta_E-A
DB
_revised (4)
Mitigative Measure (Cont’d)
Environmental Impacts Mitigative Measures Monitoring Programme Responsibility
11. Solid Wastes (Cont’d) according to the Notification of the Ministry of
Industry, entitled “Disposal of Garbages or
Unwanted Materials”, 2005.
- To prohibit burning of garbages or leaves within
the construction area.
- Power Generation
Supply Co., Ltd.
Operation Phase
- To provide a specific area for appropriate
collection and segregation of solid wastes.
- To provide appropriate containers for each type of
solid wastes to install these containers at various
points within the project area, and to dispose the
solid wastes according to the Notification of the
Ministry of Industry, entitled “Disposal of
Garbages or Unwanted Materials”, 2005.
- To contract the local agency for collecting the
garbages everyday to prevent overfilling.
- To manage each type of solid wastes as follows :
• General garbages from Office Buildings : The
garbages generated from the office buildings
including pieces of paper, glass, plastic bags,
packages/boxes are estimated to be about 59.5
kg/day which are collected in the bins and
disposed outside the plant by the contracted local
agency.
Environm
ental Report for submittal to AD
B N
ong-Saeng Power Plant Project
C
hapter 9 Pow
er Generaton Supply C
o., Ltd. Environmental M
anagement Plan
T-EIA208102
9-33
F208102Chap9Ta_E-A
DB
_revised (4)
Mitigative Measure (Cont’d)
Environmental Impacts Mitigative Measures Monitoring Programme Responsibility
11. Solid Wastes (Cont’d) • Spent Air Filters : The quantity of spent air
filters generated is estimated to be about 4,000
pieces/year which is separately collected by the
project and disposed by an authorized waste
disposal facility.
• Spent Lubricating Oil and oil from oil separators
: Spent lubricating oil and the oil from the oil
separators are estimated to be about 870
litres/month which are collected in 200 litre tanks
and disposed by an authorized waste disposal
facility.
• Spent Resins : The spent resins generated are
estimated to be about 1.3 m3/year which are
returned to their manufacturer or separately
stored and subsequently disposed by an
authorized waste disposal facility.
• Sludge from water treatment system : The
quantity of sludges generated from the water
treatment system is about 22 m3/day in case of
natural gas firing and about 18 m3/day in case of
diesel oil firing. The sludges are stored for
disposal by an authorized waste disposal facility.
• Solid wastes from evaporation process : The
solid wastes generated from the evaporation
process is about 114.4 kg/day, or 153.4 kg/day
- Power Generation
Supply Co., Ltd.
Environm
ental Report for submittal to AD
B N
ong-Saeng Power Plant Project
C
hapter 9 Pow
er Generaton Supply C
o., Ltd. Environmental M
anagement Plan
T-EIA208102
9-34
F208102Chap9Ta_E-A
DB
_revised (4)
Mitigative Measure (Cont’d)
Environmental Impacts Mitigative Measures Monitoring Programme Responsibility
11. Solid Wastes (Cont’d) when the effluent from office building is mixed with chemical contaminated effluent. The solid wastes are stored for disposal by an authorized waste disposal facility.
- Power Generation Supply Co., Ltd.
Nong-Saeng Power Plant Project will dispose the solid wastes according to the Notification of the Ministry of Industry, B.E.2548, entitled “Disposal of Garbages or Unused Materials.”
12. Occupational Health and Safety
Construction Phase
As the effect of migration is the major and profound
problem, the cooperation of all concerned
organizations and government sectors as well as
labors can bring the prevention and reduction of the
health and safety issues. Generally, the Contractor
will proceed as shown hereunder:-
- For the procedure of job application, the Contractor will perform interview and health check-up, appearance check and request for medical check certificate to confirm that that person has no incurable disease and congenital disease which obstruct to work.
- To notify government offices as follows:-
• Local clinic or hospitals
To let them acknowledge and prepare the
readiness of public health and medical care for
the increasing of population. The said
Operation Phase Noise in Working Area Parameter - Noise Dose Location/Person - Employees working in the process are of the power
plant. Duration/Frequency - 4 time per year Measurement Method - Noise Dosimeter or method recommended by the
concerned government agency Expense - 10,000 baht per time Parameter - Noise Contour Location/Person The electricity generating area having high noise level.
- Power Generation Supply Co., Ltd.
Environm
ental Report for submittal to AD
B N
ong-Saeng Power Plant Project
C
hapter 9 Pow
er Generaton Supply C
o., Ltd. Environmental M
anagement Plan
T-EIA208102
9-35
F208102Chap9Ta_E-A
DB
_revised (4)
Mitigative Measure (Cont’d)
Environmental Impacts Mitigative Measures Monitoring Programme Responsibility
12. Occupational Health and
Safety (Cont’d)
organizations will consider the suitable
programs for prevention epidemic, sexual
transmitted disease (STD) and other
diseases including medical support. The
Contractor will cooperate and follow their
advice.
• Local administrative government office such as
Municipality and Sub-district Administrative
Organization (SAO).
To let them acknowledge and prepare the
readiness for local society and commune in a
group of people including all region
regulations.
• Other Public Utility Government Office such as
Provincial Electricity Authority, Provincial
Waterworks Authority and Municipality
dealing with garbage scavenging
- Training Program The Contractor will arrange HSE Orientation Program for all labors in order to notify them our basic principles before starting to work including the way of operation and commune in labor camp. Furthermore, the additional information will be regularly provided in Safety Talk Program.
- Drug and Alcohol Check The Contractor will take a random alcohol testing
Duration/Frequency
- every 5 years
Measurement Method
- Integrated Sound Level Measurement or equivalent
method recommended by the concerned
government agency.
Expense
- 300,000 baht per time
Heat
Parameter
- Wet Bulb Globe Temperature (WBGT)
Location
Heat sources, such as
- Condenser Exhaust Unit
- Steam Pipeline Area
- Generator Area
- Combustion Turbine Area
Duration/Frequency
- 4 times per year
Measurement Method
- WBGT Method or equivalent method
recommended by the concerned government
agency
Expense
- 10,000 baht per time
Environm
ental Report for submittal to AD
B N
ong-Saeng Power Plant Project
C
hapter 9 Pow
er Generaton Supply C
o., Ltd. Environmental M
anagement Plan
T-EIA208102
9-36
F208102Chap9Ta_E-A
DB
_revised (4)
Mitigative Measure (Cont’d)
Environmental Impacts Mitigative Measures Monitoring Programme Responsibility
12. Occupational Health and
Safety (Cont’d)
of labors as periodical check and random urine
testing to look for addictive substance in labor
camp occasionally.
- Medical support program
The Contractor will provide first aid kits and
medical supplies in project site and also coordinate
with local hospital in case of emergency
Occupational Health and Safety Management
- The project in conjunction with the contractor of
the project construction will appoint a committee
and personnel for safety, occupational health and
working environment with responsibility to
establish policy and work guidelines. The safety
manual is to be prepared 1 month before the
commencement of construction works and
distributed to every employee. In addition, training
on construction safety will be arranged for all
levels of personnel and relevant knowledge be
provided to every employee working for this
project. These activities will be performed in order
to educate every employee with basic knowledge
and awareness of work safety.
- The procurement of safety equipments including
safety glasses, safety masks, safety gloves, safety
shoes, safety ropes, respirators for toxic gas, noise
protection devices, showers and eye washers in
Light
Parameter
- Light
Location
- Electrical and Control Building
- Administration Building
- Workshop
Duration/Frequency
- 4 times per year
Measurement Method
- Lux Meter or equivalent method recommended by
the concerned government agency.
Expense
- 20,000 baht per time
Health
Health Examination for New Employees of Nong-
Saeng Power Plant
Parameter
- General Physical Examination
- Lung X-rays
- Basic blood test
Duration/Frequency
- Before working within the specified period by the
law.
Health Examination for Employees of Nong-Saeng
Power Plant
- Power Generation
Supply Co., Ltd.
Environm
ental Report for submittal to AD
B N
ong-Saeng Power Plant Project
C
hapter 9 Pow
er Generaton Supply C
o., Ltd. Environmental M
anagement Plan
T-EIA208102
9-37
F208102Chap9Ta_E-A
DB
_revised (4)
Mitigative Measure (Cont’d)
Environmental Impacts Mitigative Measures Monitoring Programme Responsibility
12. Occupational Health and Safety (Cont’d)
case of contact with chemicals is provided with training on uses of these equipments and how to work safely (e.g. the application of slings, pulleys and chains for lifting, storage and inspection methods of lifting equipment/machinery, etc.), climbing up high altitude and precautions against falling off. The employees working in confined area must be trained as required by the law (e.g. on the application of gas detectors when entering the confined area, the use of ventilating fans in these areas, having a lookout person in front of the entrance of the confined area, etc.); and also on the erection of working stands, driving in the project area, application of communication instruments, proper methods for loading and unloading the chemicals, etc.
- The employees working on safety, occupational health and working environment shall be trained by the safety personal for the specified courses and duration, and get the training certificate.
- All employees shall be trained on safety before working.
- The working section of safety, occupational health and working environment will have a joint meeting for planning the construction works, summarizing the problems and suggestions for the work performance before starting the work every
Parameter - Lung X-rays - Vision Test - General Physical Examination - Blood test : Complete Blood Cell, Blood group and
Hepatitis B immunity. Duration/Frequency - Once per year Special Examination Parameter - Hearing test for mechanical workers. - Lung Function Test for maintenance workers. - Vision Test for every employee. Duration/Frequency - Once per year Fire Prevention and Fire Fighting System - The safety, occupational health and working
environment section will have a meeting in order to summarize the problems, recommendations, and to revise the safety manual and emergency plan by recording the details, statistics and comments from the employees and local fire fighting authority on the safety and occupational health of the project.
- Inspection of fire protection equipments, at least once a week.
- Evaluation of the emergency response drill in order to revise the emergency plan and practice skills
Environm
ental Report for submittal to AD
B N
ong-Saeng Power Plant Project
C
hapter 9 Pow
er Generaton Supply C
o., Ltd. Environmental M
anagement Plan
T-EIA208102
9-38
F208102Chap9Ta_E-A
DB
_revised (4)
Mitigative Measure (Cont’d)
Environmental Impacts Mitigative Measures Monitoring Programme Responsibility
12. Occupational Health and
Safety (Cont’d)
morning. Details and statistics are to be recorded,
such as accident statistics with its causes, severity
and damage, including corrective measures.
- Inspection of safety equipments shall be conducted
at least once a month.
- Arrangement for the meeting of the committee on
safety, occupational health and working
environment at least once a month in order to
evaluate and recommend for problem correction.
- Promotion of activities on safety, occupational
health and working environment.
- Posting warning signs of “No Entry for
Unconcerned People” in dangerous area, and
specifying construction zone.
- Provision of adequate sanitary utilities for
employees, such as drinking water and toilets.
- Provision of medical supplies and first-aid
equipments in case employees are injured and sent
to the hospital.
- Provision of knowledgeable personnel to be responsible for safety.
- Storage of instruments and equipments orderly, and inspection of them to be in good conditions on a regular basis.
Environm
ental Report for submittal to AD
B N
ong-Saeng Power Plant Project
C
hapter 9 Pow
er Generaton Supply C
o., Ltd. Environmental M
anagement Plan
T-EIA208102
9-39
F208102Chap9Ta_E-A
DB
_revised (4)
Mitigative Measure (Cont’d)
Environmental Impacts Mitigative Measures Monitoring Programme Responsibility
12. Occupational Health and
Safety (Cont’d)
- To specify these measures in the employment
contract for the construction contractor during
construction phase.
Fire Prevention and Fire Fighting System
- The prime contractor must provide fire
extinguishers in sufficient quantity for the
employees working in the hazardous areas or in the
area of intense heat and fire risk, such as metal
welding. Each welding crew must have a fire
extinguisher (dry powder) in their workplace. For
metal welding in an elevated area, the space
beneath the working area must be covered with
insulating materials in order to keep the sparks,
resulting from the welding, from falling onto the
lower area which may otherwise be unsafe for
those working in such area.
- The prime contractor must prepare a coordinating
plan with the local fire authority in order to get
ready in case of an emergency.
Control of the entrance and exit of the construction-
induced hazardous areas, traffic control. Posting
hazard warning signs that are apparently visible by
the foreman or safety personnel.
- Power Generation
Supply Co., Ltd.
Environm
ental Report for submittal to AD
B N
ong-Saeng Power Plant Project
C
hapter 9 Pow
er Generaton Supply C
o., Ltd. Environmental M
anagement Plan
T-EIA208102
9-40
F208102Chap9Ta_E-A
DB
_revised (4)
Mitigative Measure (Cont’d)
Environmental Impacts Mitigative Measures Monitoring Programme Responsibility
12. Occupational Health and Safety (Cont’d)
- Preparation of fire fighting equipment suitable for
area conditions and types of work along with
specifying the safe work procedure.
- Inspection of working condition and equipments
used in the construction, particularly at the
locations being subject to hazard or fire risk.
- Inspection, on a routine basis, of fire extinguishers
at least every week.
- Power Generation Supply Co., Ltd.
Operation Phase
Working Environmental Condition
Sound Pressure Level
Although the sound pressure level in the workplace
within Nong-Saeng Power Plant was specified to be
85 dB(A) which did not exceed the standard
specified in the Notification of Ministry of Interior,
Safety Protection Measures for Factories Regarding
Working Environmental Conditions B.E.2546
(2003), some factors are to be taken into
consideration in order to reduce long-term impacts.
For example, wear-out of machines in the process
can cause higher sound pressure level if maintenance
is not suitably performed. Therefore, Nong-Saeng
Power Plant provided the mitigative measures for
noise as follows:
Environm
ental Report for submittal to AD
B N
ong-Saeng Power Plant Project
C
hapter 9 Pow
er Generaton Supply C
o., Ltd. Environmental M
anagement Plan
T-EIA208102
9-41
F208102Chap9Ta_E-A
DB
_revised (4)
Mitigative Measure (Cont’d)
Environmental Impacts Mitigative Measures Monitoring Programme Responsibility
12. Occupational Health and
Safety (Cont’d)
- To prepare a preventive maintenance plan for the
machineries in production process continually.
- To prepare noise protection equipments, such as
ear plugs or ear muffs for employees.
- To post warning signs in loud noise areas in order
to remind workers to wear ear plugs or ear muffs.
To train workers on work procedures and proper
use of personnel protective equipments.
- To install silencer and enclosing the machines
generating loud noise.
Heat
The heat generated was assessed from the nature of
power plant, work, and heat exposure time of
workers. It was found that it did not impose direct
impacts on workers. However, Nong-Saeng Power
Plant provided mitigative measures to reduce the
potential impacts during plant operation, such as
insulation system and enclosure of the heat sources
according to the characteristic of process unit.
Chemicals
- To provide the chemical storage room, and material
safety data sheet (MSDS) of every chemicals, and
to post warning signs clearly in this area.
- Power Generation
Supply Co., Ltd.
Environm
ental Report for submittal to AD
B N
ong-Saeng Power Plant Project
C
hapter 9 Pow
er Generaton Supply C
o., Ltd. Environmental M
anagement Plan
T-EIA208102
9-42
F208102Chap9Ta_E-A
DB
_revised (4)
Mitigative Measure (Cont’d)
Environmental Impacts Mitigative Measures Monitoring Programme Responsibility
12. Occupational Health and Safety (Cont’d)
- To provide personal protective equipments (PPE),
such as chemical suit, chemical gloves, glasses,
chemical mask, etc. for the employees exposing to
the chemicals.
- To train the employees on working procedures and
wearing PPE properly.
- To train the employees on safe use of chemicals,
and procedures for preventing and checking
chemical leakage.
- To provide emergency washing equipments, such
as eye washer and shower in chemical storage tank
area and working area where employees can
expose to chemicals.
Occupational Health and Safety Management
- Appointment of a committee on safety,
occupational health and working environment with
responsibility for controlling the work performance
under various conditions of the power plant, such
as during normal operation, daily maintenance, and
annual plant shutdown, etc.
- Preparation of the manuals for the aforementioned
plans to be used as reference plans in the training
of the employees of the power plant. These
manuals must conform to the details of the
equipments/machineries installed in the power
plant and to the requirements under the law of
- Power Generation Supply Co., Ltd.
Environm
ental Report for submittal to AD
B N
ong-Saeng Power Plant Project
C
hapter 9 Pow
er Generaton Supply C
o., Ltd. Environmental M
anagement Plan
T-EIA208102
9-43
F208102Chap9Ta_E-A
DB
_revised (4)
Mitigative Measure (Cont’d)
Environmental Impacts Mitigative Measures Monitoring Programme Responsibility
12. Occupational Health and Safety (Cont’d)
safety and working environment. For
instances,provision of training course(s) on safety
at work for every new employee of the power plant
along with the distribution of safety manuals.
- Preparation of an annual health checkup plan for
every employee.
- Record of statistics of safe work performance, no
sick leaves because of injuries etc.
- Preparation of safety hats in sufficient number for
every employee of the power plant and the plant’s
visitors.
- Preparation of safety glasses for every plant
employee.
- Preparation of ear muffs for every plant employee.
- Preparation of safety gloves for various types of
work, such as welders, electricians, etc.
- Preparation of safety shoes in sufficient number for
every employee of the power plant.
- Preparation of safety ropes for working at high
altitude.
- Preparation of gas masks.
- Preparation of equipments and medicines, and
place for the first-aid treatment.
- Preparation of stretchers for carrying injured
employees by accidents at work.
- Power Generation Supply Co., Ltd.
Environm
ental Report for submittal to AD
B N
ong-Saeng Power Plant Project
C
hapter 9 Pow
er Generaton Supply C
o., Ltd. Environmental M
anagement Plan
T-EIA208102
9-44
F208102Chap9Ta_E-A
DB
_revised (4)
Mitigative Measure (Cont’d)
Environmental Impacts Mitigative Measures Monitoring Programme Responsibility
12. Occupational Health and
Safety (Cont’d)
- The surface of the material and
equipments/machineries having high temperature
are insulated to lower the surface temperature not
to exceed 60 °C.
- Stairways, walkways and mezzanines are wide
enough and equipped with railings for preventing
the plant’s employees from falling off. These
items are in accordance with the safety standards.
- The floor surfaces of areas subjected to oil spill and
contamination are made of anti-slip materials. The
painting system and alphabetic signs, and the flow
direction of the materials in the piping systems and
other supporting equipments are in accordance with
the international standards.
- Equipments generating loud noise are equipped
with noise absorption wall and designed with good
ventilation for air circulation.
- Installation of showers and eye washers at the
locations subjected to the risk of chemical spill or
accident. This is for the plant’s employees
involved in the accident to instantly wash off the
contaminated chemicals.
- Electrical and lighting systems: the backup power
system was installed for emergency cases. It was
designed for safety and adequate lighting at
workplace.
- Power Generation
Supply Co., Ltd.
Environm
ental Report for submittal to AD
B N
ong-Saeng Power Plant Project
C
hapter 9 Pow
er Generaton Supply C
o., Ltd. Environmental M
anagement Plan
T-EIA208102
9-45
F208102Chap9Ta_E-A
DB
_revised (4)
Mitigative Measure (Cont’d)
Environmental Impacts Mitigative Measures Monitoring Programme Responsibility
12. Occupational Health and
Safety (Cont’d)
- Control of entrance and exit of the power plant,
hazardous areas and traffic by security guards and
safety personnel.
- Provision of permit system for work entry,
preparation of area condition and working
procedures on the safety basis for the outsiders or
the in-plant employees performing maintenance
works.
- Inspection and preparation for the safety of risky
working area, such as working in confined areas,
welding/cutting area where sparks exist leading to
fire.
- Inspection of working condition and equipments in
the power plant, and locations where are hazardous
or subject to fire risk.
- Performance inspection of the following preventive
equipments/devices on a regular basis, at least
every week:
• Personal protective devices
• Showers and eye washers
• Emergency lights
• Alarm system and fire extinguishers
- Arrangement for the safety week activity to
encourage and allow skill practice on the safety
performance at least once a year.
- Power Generation
Supply Co., Ltd.
Environm
ental Report for submittal to AD
B N
ong-Saeng Power Plant Project
C
hapter 9 Pow
er Generaton Supply C
o., Ltd. Environmental M
anagement Plan
T-EIA208102
9-46
F208102Chap9Ta_E-A
DB
_revised (4)
Mitigative Measure (Cont’d)
Environmental Impacts Mitigative Measures Monitoring Programme Responsibility
12. Occupational Health and
Safety (Cont’d)
- Perform emergency response drill, at least once a
year.
- The safety, occupational health and environment
section will have a meeting to summarize the
problems, make recommendations and revise the
safety manual and emergency plan. The details of
the meeting will be recorded, including the
statistics, comments from the employees and
complaints from the nearby communities regarding
safety and occupational health of the project.
- Check of safety equipments at least once a week.
- Provision of annual health examination for pre-
employment and all employees.
- Evaluation of emergency drill in order to improve
the emergency plan and drill skill.
- Arrangement for the meeting of the committee on
safety, occupational health and working
environment at least once a month in order to
evaluate, recommend for problem solving, improve
and promote the activities on the safety,
occupational health and working environment.
Fire Prevention and Fire Fighting System
During operation phase, the measures and
installation of fire prevention and fire fighting
equipments of Nong-Saeng Power Plant are specified
in accordance with the international standard of the
- Power Generation
Supply Co., Ltd.
Environm
ental Report for submittal to AD
B N
ong-Saeng Power Plant Project
C
hapter 9 Pow
er Generaton Supply C
o., Ltd. Environmental M
anagement Plan
T-EIA208102
9-47
F208102Chap9Ta_E-A
DB
_revised (4)
Mitigative Measure (Cont’d)
Environmental Impacts Mitigative Measures Monitoring Programme Responsibility
12. Occupational Health and
Safety (Cont’d)
National Fire Protection Association (NFPA 10, 12,
13, 14, 15, 20, 24, 30, 70, 72D, 9E, ANSI B31.1,
ASME VIII and IEEE.83) as follows:
- Fire Prevention System of Nong-Saeng Power
Plant includes the following:
• Smoke Detector
• Fire Detector
• Gas Detector
• Alarm System, Sound Signal, Light Signal.
• Automatic Protection System transfers signal to
activate the automatic fire extinguisher.
• Center Control of Alarm and Fire Prevention
System.
- Fire prevention systems are installed in various
locations in the office building where fire may
occur.
- Fire Fighting System includes the following:
• Sprinkler system was installed in material
storage building. It spray water automatically for
fire fighting. Thermal bulb breaks when fire is
detected and alarm will be transferred to the
control room of the power plant for commanding
fire fighting immediately.
- Power Generation
Supply Co., Ltd.
Environm
ental Report for submittal to AD
B N
ong-Saeng Power Plant Project
C
hapter 9 Pow
er Generaton Supply C
o., Ltd. Environmental M
anagement Plan
T-EIA208102
9-48
F208102Chap9Ta_E-A
DB
_revised (4)
Mitigative Measure (Cont’d)
Environmental Impacts Mitigative Measures Monitoring Programme Responsibility
12. Occupational Health and
Safety (Cont’d)
• Yard hydrant joins to fire water pipeline which is
laid around the power plant area. The spray
radius of fire water covers over every building
and in the area where the main machines are
installed within the power plant.
• Fire house cabinet is installed at the road side in
the power plant area.
• Fire water pump system
: Main fire water pump system is electric motor
driven pumping water from raw water storage
tank in the power plant for fire fighting.
: Reserved fire water pump system is diesel
engine driven. It is used in case of electricity
shortage within the power plant. Efficiency
operates to pump water to be equal main fire
fighting water pump machine.
: Jockey pump is automatically operated when
fire water pressure level in fire water pipeline
system of the power plant is reduced to the set
value. The fire water in the system has high
pressure enough to use for fire fighting.
• Portable fire extinguisher of dry powder type is
installed for fire fighting within each building of
the power plant.
- Power Generation
Supply Co., Ltd.
Environm
ental Report for submittal to AD
B N
ong-Saeng Power Plant Project
C
hapter 9 Pow
er Generaton Supply C
o., Ltd. Environmental M
anagement Plan
T-EIA208102
9-49
F208102Chap9Ta_E-A
DB
_revised (4)
Mitigative Measure (Cont’d)
Environmental Impacts Mitigative Measures Monitoring Programme Responsibility 12. Occupational Health and Safety (Cont’d)
• CO2 fire extinguisher is installed on a cart for fire fighting
• Fire water spray pipeline system is installed to cover main equipments of the power plant, such as 115 kV main transformer steam turbine and Spent lubricating oil injection system area which may generate high thermal and fire. It is automatically operated when fire detector is active.
Fire preventions system of the project are designed in accordance with NFPA as follows :
• Transformers for combustion & steam turbine generators automatic water spray system is installed in the transformer area.
• Steam turbine generator bearing area protection system using fine water spray system is installed in this area.
• HRSG area. Hydrants are installed in HRSG area.
• Combustion turbine enclosure and turbine enclosed mechanical and electrical cabinet area are prevented from fire by carbon dioxide.
- Power Generation Supply Co., Ltd.
Operation Plan Fire protection is a function of every employee in the power plant including the executive, employees, personnel and security guards. Accordingly, their functions are designated as follows:
Environm
ental Report for submittal to AD
B N
ong-Saeng Power Plant Project
C
hapter 9 Pow
er Generaton Supply C
o., Ltd. Environmental M
anagement Plan
T-EIA208102
9-50
F208102Chap9Ta_E-A
DB
_revised (4)
Mitigative Measure (Cont’d)
Environmental Impacts Mitigative Measures Monitoring Programme Responsibility
12. Occupational Health and Safety (Cont’d)
- The Executive and Manager • To establish the power plant layout. • To specify the areas, and control the process and
equipments/machineries that may catch fire. • To specify the standard operating procedures for
fire safety. • To control the use of fire, generation of
fire/flame, sparks, electricity, heat, static electricity or other working procedures causing an outbreak of fire.
• To monitor the activities relating to fire protection.
• To have a long-term fire protection plan, such as installation of detectors for: inflammable substances or smoke, alarm systems, automatic fire fighting systems at locations where flammable or ignitable substances exist.
- Every employee must comply with the work safety rules as follows: • Lighting a fire is prohibited in the restricted or
power plant areas before permission by an authorized personnel.
• Smoking is prohibited in the areas where the following signs are posted: “Hazards of inflammable substances or explosives” or “No smoking”, except in the provided areas.
- Power Generation Supply Co., Ltd.
Environm
ental Report for submittal to AD
B N
ong-Saeng Power Plant Project
C
hapter 9 Pow
er Generaton Supply C
o., Ltd. Environmental M
anagement Plan
T-EIA208102
9-51
F208102Chap9Ta_E-A
DB
_revised (4)
Mitigative Measure (Cont’d)
Environmental Impacts Mitigative Measures Monitoring Programme Responsibility
12. Occupational Health and Safety (Cont’d)
• Maintenance of equipment/machinery without permission is prohibited in the areas where inflammable substances or ignitable materials exist unless the maintenance crew and safety personnel jointly apply for a permit to perform such maintenance works according to the specified procedures.
- Safety Personnel • To specify the zones that are subject to a fire
risk. • To routinely inspect the locations that are risky
to cause an outbreak of fire. • To specify the details of the fire prevention and
fire fighting plan as well as to provide training and practice periodically.
• To provide, maintain and inspect the fire extinguishers to be ready for use all the time.
• To fill data in Emergency Check List and Emergency Incident Form.
• To report accidents and injuries. - Security Guards • To be on patrol in order to keep the outsiders or
the deliverers of goods from entering the power plant or the fire risk areas.
• To take precaution against sabotage in the fire risk areas.
- Power Generation Supply Co., Ltd.
Environm
ental Report for submittal to AD
B N
ong-Saeng Power Plant Project
C
hapter 9 Pow
er Generaton Supply C
o., Ltd. Environmental M
anagement Plan
T-EIA208102
9-52
F208102Chap9Ta_E-A
DB
_revised (4)
Mitigative Measure (Cont’d)
Environmental Impacts Mitigative Measures Monitoring Programme Responsibility
12. Occupational Health and Safety (Cont’d)
• To report to the concerned person immediately when anything that can cause an outbreak of fire is sighted.
Emergency Plan The Nong-Saeng Power Plant Project has prepared an emergency plan for various cases in order to get ready to handle any emergency situation that may emerge. The main target of such effort is the reduction of hazards that may impose on its employees and equipments/machineries. This emergency plan consist of the following: - Emergency Control During normal operation period, the power plant manager will act as the person being responsible for all emergency control, i.e., to keep the safety for all employees of the plant. During the operation period beyond the normal working hours, the shift chart engineer will be responsible for all emergency control until the situation is back to normal or until the power plant manager arrives at the plant and resumes his responsibility as the emergency coordinator. The emergency is classified into 2 levels as follows: Level 1 Emergency Level 1 emergency is the event that takes place within the power plant and the emergency coordinator can keep the resultant damage condition
- Power Generation Supply Co., Ltd.
Environm
ental Report for submittal to AD
B N
ong-Saeng Power Plant Project
C
hapter 9 Pow
er Generaton Supply C
o., Ltd. Environmental M
anagement Plan
T-EIA208102
9-53
F208102Chap9Ta_E-A
DB
_revised (4)
Mitigative Measure (Cont’d)
Environmental Impacts Mitigative Measures Monitoring Programme Responsibility
12. Occupational Health and Safety (Cont’d)
within the limited extent. This level involves the use
of the plant’s employees and emergency equipments
that are prepared in the power plant and,
consequently, the situation can be calm down.
Level 2 Emergency
Level 2 emergency is the event that may outbreak
from its cause both within and outside the power
plant; and the emergency coordinator, based on his
evaluation of the situation, determines that the
emergency plan as prepared for level 1 emergency
case cannot be applied to keep the situation calm
down. Consequently, it is necessary to involve the
use of personnel and emergency equipments from
outside organization(s) and government agency(s) as
cooperative backup for the control of the emergency
incident in order to keep its situation under control.
- Fire Fighting Plan
The incident of fire is regarded as an emergency
event that causes the most damage to the property
and personnel, so it is a must to make a clear/detailed
fire fighting plan. Practice under the plan on a regular
basis is also required so that, in case of fire, the
situation can be calm down soon. Details of the plan
are as follows:
- Power Generation Supply Co., Ltd.
Environm
ental Report for submittal to AD
B N
ong-Saeng Power Plant Project
C
hapter 9 Pow
er Generaton Supply C
o., Ltd. Environmental M
anagement Plan
T-EIA208102
9-54
F208102Chap9Ta_E-A
DB
_revised (4)
Mitigative Measure (Cont’d)
Environmental Impacts Mitigative Measures Monitoring Programme Responsibility
12. Occupational Health and Safety (Cont’d)
Operation Procedure during Normal Working
Period
The employee who comes across a fire incident will
decide whether or not he can suppress the fire by
himself. If not, he will inform the event to the central
control building to request for help and advise the
information to the emergency director. The power
plant manager will act as the emergency director
whose functions are to evaluate the situation of the
emergency incident and to decide that such incident
is level 1 or level 2 emergency, and whether or not
the situation can be kept under control within the
power plant by its own capacity; make commands in
order to calm down the situation under the
emergency; provide safety for every employee and
the property of the power plant, e.g., contact the local
fire authority, request for ambulance(s) from the local
hospital in case the plant’s employees are injured by
the fire, etc.; command the fire fighting team of the
power plant to take action; command to evacuate the
employees from the area of incident to the assembly
point; and command to block off the traffic at certain
roadway(s) within the power plant and block off the
entrance of the power plant, etc.
- Power Generation Supply Co., Ltd.
Environm
ental Report for submittal to AD
B N
ong-Saeng Power Plant Project
C
hapter 9 Pow
er Generaton Supply C
o., Ltd. Environmental M
anagement Plan
T-EIA208102
9-55
F208102Chap9Ta_E-A
DB
_revised (4)
Mitigative Measure (Cont’d)
Environmental Impacts Mitigative Measures Monitoring Programme Responsibility
12. Occupational Health and Safety (Cont’d)
Operation Procedure during the Period beyond
Normal Working Hours
The employee(s) who comes across a fire incident
will decide that whether or not he can suppress the
fire by himself. If not, he will inform the event to the
central control building to request for help and advise
the information to the emergency director. Due to
the number of employees working in the power plant
during this period is less than the those working
during normal working hours, the head of the shift in
charge will act as the emergency director. If his
evaluation of the emergency situation results in level
2 emergency, he must notify the local fire authority
soonest, contact and call for the plant’s employees
who are on duty for the emergency to take action,
command the fire fighting and security teams to take
action under the fire fighting plan; then he will notify
the local hospital and request for an ambulance in
case it is known that someone is injured in the fire
incident, cut out the electrical circuit in the area
where fire water spraying takes place and also advise
the situation to the power plant manager, etc.
- Evacuation Plan
The project will provide for 2 options of assembly
point and the route of evacuation which will rely on
- Power Generation Supply Co., Ltd.
Environm
ental Report for submittal to AD
B N
ong-Saeng Power Plant Project
C
hapter 9 Pow
er Generaton Supply C
o., Ltd. Environmental M
anagement Plan
T-EIA208102
9-56
F208102Chap9Ta_E-A
DB
_revised (4)
Mitigative Measure (Cont’d)
Environmental Impacts Mitigative Measures Monitoring Programme Responsibility
12. Occupational Health and Safety (Cont’d)
the emergency director’s decision to choose the
choice. The consideration for a decision making will
be based on the safety and convenience at each
location of the incident.
When the emergency director proclaims an
emergency situation and advises the assembly point,
every employee will be gathered to such assembly
point for checking the total number of employees,
teaming up and preparing the equipments. If
someone is missing from the list, a search team will
look for and provide assistance for that missing
person(s).
- Rescue Plan
The rescue plan will include the following items:
• Coordinating with the government agency(s).
• Checking for the damage.
• Calling for personnel of every department to
present themselves and specifying the meeting
point for the personnel to wait for commands.
• Saving the life and digging for the dead
person(s).
• Moving the victim(s) and property of the dead
person(s).
• Evaluating the damage and result of the
operation, and reporting the fire incident.
- Power Generation Supply Co., Ltd.
Environm
ental Report for submittal to AD
B N
ong-Saeng Power Plant Project
C
hapter 9 Pow
er Generaton Supply C
o., Ltd. Environmental M
anagement Plan
T-EIA208102
9-57
F208102Chap9Ta_E-A
DB
_revised (4)
Mitigative Measure (Cont’d)
Environmental Impacts Mitigative Measures Monitoring Programme Responsibility
12. Occupational Health and Safety (Cont’d)
• Providing assistance and support for the
victim(s).
• Improving the conditions and solving the urgent
problems in order to resume the business
soonest.
- Restoration and Reformation Plan
The restoration and reformation plan to be
implemented after the fire incident at the power plant
involves the improvement and solving of problems
based on the evaluation reports on the actual situation
from every sector; particularly, the fire prevention
plan, operation plan to handle a fire incident, rescue
plan (soon after the fire is calmed down) as well as
the improvement of those defective personnel.
- Power Generation Supply Co., Ltd.
13. Socio-economics Construction Phase
The action must be done according to the suitability
and capacity of the local workers, and concentrate on
two major areas as follows:
- Contractor employment policy is based on fair
wage and compliant with local rules and regulations.
PGS will hire and will provide accommodation such
as worker camp equipped with basic utilities, health
facilities, and transportation between project site and
worker camp. Specifically, the following will be
complied with:
Construction Phase
Socio-economic
Parameter
- Socio-economic survey and opinion of people,
community leaders and representatives of
concerned agencies.
Location
- Communities in the vicinity area of the Nong-
Saeng Power Plant.
- Representative of concerned agencies.
- Power Generation Supply Co., Ltd.
Environm
ental Report for submittal to AD
B N
ong-Saeng Power Plant Project
C
hapter 9 Pow
er Generaton Supply C
o., Ltd. Environmental M
anagement Plan
T-EIA208102
9-58
F208102Chap9Ta_E-A
DB
_revised (4)
Mitigative Measure (Cont’d)
Environmental Impacts Mitigative Measures Monitoring Programme Responsibility
13. Socio-economics (Cont’d)
a. carry out activities consistent with the intent of ensuring legally permissible equal opportunity, fair treatment and non discrimination in relation to recruitment and hiring, compensation, working condition and terms of employment for its workers (including prohibiting any forms of discriminatory against women during hiring and providing equal work for equal pay for men and women engaged by the company); b. not restrict workers form developing a legally permissible means of expressing their grievances and protecting their rights regarding working condition and terms of employment; c. engage contractors and other providers of goods and services: i. who do not employ child labor or forced labor; ii. who have appropriate management systems that will allow them to operate in a manner which is consistent with the intent of (a) ensuring legally permissible equal opportunity and fair treatment and non discrimination for their workers, and (b) not restricting their workers from developing legally permissible means of expressing their grievances and protecting their rights regarding working conditions and terms of employment; and iii. whose subcontracts contain provision which are consistent with paragraph (i) and (ii).
Reporting on Social Protection (labor) - Compliance with the applicable social protection (labor) standards; To be reported semi-annually under the environment and social monitoring.
- Power Generation Supply Co., Ltd.
Environm
ental Report for submittal to AD
B N
ong-Saeng Power Plant Project
C
hapter 9 Pow
er Generaton Supply C
o., Ltd. Environmental M
anagement Plan
T-EIA208102
9-59
F208102Chap9Ta_E-A
DB
_revised (4)
Mitigative Measure (Cont’d)
Environmental Impacts Mitigative Measures Monitoring Programme Responsibility
13. Socio-economics
(Cont’d)
Protection to work-related injuries by preparing
health and safety prevention plan to be assigned to
contractor and its safety manager in order to mitigate
any risk to workers and providing personnel
protection equipment for workers as appropriate.
- Urgent action on correct information dissemination
without hidden and distorted agenda to all groups
of stake holder must be performed.
Action on listening to opinion conducted by the people
participation process emphasizing on two way
Duration/Frequency
- Every 6 months-talking and interviewing with
community leaders.
- 1 time-survey by questionnaires.
Methodology
- Visiting, talking and interviewing with community
leaders and representatives of concerned agencies.
- Survey by questionnaires.
Expense
- 500,000 baht per time
- Power Generation
Supply Co., Ltd.
communication for making acceptance of the project
in the area by the communities in the project area
and in the surrounding areas. Making understanding
leads to good wills in the form of good cooperation
and participation of people in the future. The action
must be opened for the communities to express their
opinion and suggestion for making guideline to
prevent the problems of the project owner, local
people and government sectors. The action must be
conducted in the form of a committee community
participation. This will lead to good development
and avoid bad people to disturb the peace.
- Action on the project public relation before the
beginning of construction by distributing
Operation Phase
Socio-economics
Parameter
- Socio-economic survey and opinion of people,
community leaders and representatives of
concerned agencies.
Location
- Communities in the vicinity area of the Nong-
Saeng Power Plant.
- Representative of concerned agencies.
Duration/Frequency
- Every 6 months-talking and interviewing with
community leaders.
- 1 time survey by questionnaires.
Environm
ental Report for submittal to AD
B N
ong-Saeng Power Plant Project
C
hapter 9 Pow
er Generaton Supply C
o., Ltd. Environmental M
anagement Plan
T-EIA208102
9-60
F208102Chap9Ta_E-A
DB
_revised (4)
Mitigative Measure (Cont’d)
Environmental Impacts Mitigative Measures Monitoring Programme Responsibility
13. Socio-economics (Cont’d)
documents and visiting leaders and people. The action may use several media to make targeted groups receive correct and fast information. This will prevent the consequent problems. During the construction period, placards of the project on progress must be posted on public places or in front of the project.
- Consideration on the priority of local worker recruitment, which will make career and income to the communities, leads to making good relationship with the communities. The action must be done according to suitability and capacity of the local workers, and concentrate on two major areas as follows:
- Contractor employment policy is based on fair wage and compliant with local rules and regulations. PGS will hire and will provide accommodation such as worker camp equipped with basic utilities, health facilities, and transportation between project site and worker camp. Specifically, the following will be complied with:
a. carry out activities consistent with the intent of ensuring legally permissible equal opportunity, fair treatment and non discrimination in relation to recruitment and hiring, compensation, working condition and terms of employment for its workers
Inspecting method - Visiting, talking and interviewing with community
leaders and representatives of concerned agencies. - Survey by questionnaires. Expense - 500,000 baht per time Reporting on Social Protection (labor)
- Compliance with the applicable social protection (labor) standards; To be reported semi-annually under the environment and social monitoring.
- Power Generation Supply Co., Ltd.
Environm
ental Report for submittal to AD
B N
ong-Saeng Power Plant Project
C
hapter 9 Pow
er Generaton Supply C
o., Ltd. Environmental M
anagement Plan
T-EIA208102
9-61
F208102Chap9Ta_E-A
DB
_revised (4)
Mitigative Measure (Cont’d)
Environmental Impacts Mitigative Measures Monitoring Programme Responsibility
13. Socio-economics (Cont’d)
(including prohibiting any forms of discriminatory against women during hiring and providing equal work for equal pay for men and women engaged by the company); b. not restrict workers form developing a legally permissible means of expressing their grievances and protecting their rights regarding working condition and terms of employment; c. engage contractors and other providers of goods and services: i. who do not employ child labor or forced labor; ii. who have appropriate management systems that will allow them to operate in a manner which is consistent with the intent of (a) ensuring legally permissible equal opportunity and fair treatment and non discrimination for their workers, and (b) not restricting their workers from developing legally permissible means of expressing their grievances and protecting their rights regarding working conditions and terms of employment; and iii. whose subcontracts contain provision which are consistent with paragraph (i) and (ii). - Protection to work-related injuries by preparing health and safety prevention plan to be assigned to contractor and its safety manager in order to mitigate any risk to workers and providing personnel protection equipment for workers as appropriate.
Environm
ental Report for submittal to AD
B N
ong-Saeng Power Plant Project
C
hapter 9 Pow
er Generaton Supply C
o., Ltd. Environmental M
anagement Plan
T-EIA208102
9-62
F208102Chap9Ta_E-A
DB
_revised (4)
Mitigative Measure (Cont’d)
Environmental Impacts Mitigative Measures Monitoring Programme Responsibility
13. Socio-economics
(Cont’d)
- Action on control, fostering and reiterating of the
subcontractors to seriously prevent the immigrants
and local workers from making quarrel with people
in the original communities or among themselves.
- Action to control construction activity to avoid
disturbing people in the area and to rigorously and
strictly apply the environmental measures for
safety and accident prevention from construction.
- Setting up of public relation and coordination unit
for explaining, making understanding during the
constructing period and receiving complaints from
people who are in trouble due to the construction.
- Power Generation
Supply Co., Ltd.
Operation Phase
Assigning 2 parties with the responsibility for the
communies. The SAO is responsible for taking care
of environment in the communities and the Nong-
Saeng Power Plant operator is the coordinator to
support and participate in the activities.
- Organizing activities to promote and support
various community development, particularly
reduction of anxiety about impacts on occupation,
upgrading people livelihood, developing
communities, encouraging learning and
maintaining art, culture and religion. The activities
include career supporting at sustainable
economylearning center, agricultural demonstration
Environm
ental Report for submittal to AD
B N
ong-Saeng Power Plant Project
C
hapter 9 Pow
er Generaton Supply C
o., Ltd. Environmental M
anagement Plan
T-EIA208102
9-63
F208102Chap9Ta_E-A
DB
_revised (4)
Mitigative Measure (Cont’d)
Environmental Impacts Mitigative Measures Monitoring Programme Responsibility
13. Socio-economics
(Cont’d)
plot (rice growing plot, mushroom culture plot,
etc.), animal husbandry (chicken and hen farming),
family accountancy, integrated community and
society development, monitoring and
evaluating/surveying of occupational damage
caused by activities of the Nong-Saeng Power
Plant project, making understanding about
production process or organizing an open day
every year and regular informing news/information
of the project.
- Organizing suitable community supporting
activities and participating in community activities
as if the power plant staff were family members.
The activities are merit making, donation of things,
stationery and scholarship to students in the locals,
Participation in development of community, temple
and community public property.
- Setting up a coordination center for receiving
complaints in the case that people are troubled by
the operation of the Nong-Saeng Power Plant
Project. Assigning of procedure, duration and
contact persons should be clear in order to response
to complaints rapidly.
- The purpose of Power Development Fund is to
develop local communities around power plants.
Power plants having capacity over 6 MW are
Environm
ental Report for submittal to AD
B N
ong-Saeng Power Plant Project
C
hapter 9 Pow
er Generaton Supply C
o., Ltd. Environmental M
anagement Plan
T-EIA208102
9-64
F208102Chap9Ta_E-A
DB
_revised (4)
Mitigative Measure (Cont’d)
Environmental Impacts Mitigative Measures Monitoring Programme Responsibility
13. Socio-economics
(Cont’d)
required to establish the Power Development Fund
whose size of the fund is regulated by Energy
Regulatory Commission. The Power Development
Fund will be used as a channel for implementing
the subsidy arrangements for underprivileged
power consumers; rehabilitating localities;
compensating people affected by power plant
operations, and the promotion of renewable and
environmentally friendly energy. Energy
Regulatory Commission is responsible for the
management of public development fund.
14. Public Relation and
Public Participation
Public relation plan for making understanding
Period of pre-construction/site preparation
A power plant is a large scale industry. Construction
takes a long time and may cause impacts or anxiety
on communities since site preparation period. The
Power Generation Supply Co., Ltd. has prepared
public relation plan for making understanding of
communities from the beginning of site preparation
for plant construction. In order to make the
community be relaxed from anxiety and be confident
with the operation, the public relation should be done
as follows;
- Making the project public relation placards,
communication channels and showing
- Power Generation
Supply Co., Ltd.
Environm
ental Report for submittal to AD
B N
ong-Saeng Power Plant Project
C
hapter 9 Pow
er Generaton Supply C
o., Ltd. Environmental M
anagement Plan
T-EIA208102
9-65
F208102Chap9Ta_E-A
DB
_revised (4)
Mitigative Measure (Cont’d)
Environmental Impacts Mitigative Measures Monitoring Programme Responsibility
14. Public Relation and
Public Participation
(Cont’d)
responsibility for the case of problems/ impacts
resulting from the project activity. This will make
people living in the area close to the power plant
area be relaxed from anxiety about pollution
problems, accidents and health.
- Setting up a community coordination center or call
center (temporary) of the Power Generation Supply
Co., Ltd., for receiving complaints from
communities in order to make them be confident
that the company is responsible for any impacts
caused by the project subcontractors.
- Setting up a committee on public participation for
inspection of the implementation of environmental
measures during construction phase. This will
encourage the communities to participate in
watching and inspecting the implementation of
mitigative measures including environmental
development in the communities. The project
should support the setting up of a committee on
public participation by cooperation with the
communities. The function of the committee are
• To share idea and suggestion for the
implementation of the environmental action plan
of the Nong-Saeng Power Plant Project.
• To participate in inspection of the
implementation of the environmental action plan.
- Power Generation
Supply Co., Ltd.
Environm
ental Report for submittal to AD
B N
ong-Saeng Power Plant Project
C
hapter 9 Pow
er Generaton Supply C
o., Ltd. Environmental M
anagement Plan
T-EIA208102
9-66
F208102Chap9Ta_E-A
DB
_revised (4)
Mitigative Measure (Cont’d)
Environmental Impacts Mitigative Measures Monitoring Programme Responsibility
14. Public Relation and
Public Participation
(Cont’d)
• To appoint a working team for inspection of
environmental quality of concern.
• To receive complaints on environmental
problems from communities and to analyze the
problem according to the process for complaint
receiving and solving given in the action plan on
socio-economics.
- Power Generation
Supply Co., Ltd.
Construction Phase
- To conduct proactive public relation consisting of
news/information dissemination process that
increase more learning of project in more
perspectives. The public relation should be carried
out via all local media. The deep public relation
should be performed to make understanding to
individuals directly by having meeting or seminars
on the following issues;
• Progress of the project operation.
• Technical information of the power plant
operation, particularly how safe the security
measure or method is or a method that the Power
Generation Supply Co., Ltd. has prepared to cope
with problems, obstacles and accidents during
construction period of the project.
• Promotion of green area, for example, planting
trees in the public places of communities to
Environm
ental Report for submittal to AD
B N
ong-Saeng Power Plant Project
C
hapter 9 Pow
er Generaton Supply C
o., Ltd. Environmental M
anagement Plan
T-EIA208102
9-67
F208102Chap9Ta_E-A
DB
_revised (4)
Mitigative Measure (Cont’d)
Environmental Impacts Mitigative Measures Monitoring Programme Responsibility
14. Public Relation and
Public Participation
(Cont’d)
compensate the power plant area. This makes
good attitude to the Power Generation Supply
Co., Ltd. for the consideration and response to
true need of the communities.
- To produce public relation media, such as leaflets,
hand bill and video, etc., containing the details of
the power plant and pollution prevention system
which are easy to understand. This will create the
image of the Power Generation Supply Co., Ltd.
- To coordinate and organize a meeting with
important offices or organizations in the local, such
as governmental offices or occupational groups in
order to inform the results of the mitigative actions
conducted by the Power Generation Supply Co.,
Ltd.
- Power Generation
Supply Co., Ltd.
Operation Phase
- Organization of a study tour for the communities
by coordination with community leaders to arrange
people to visit the Nong-Saeng Power Plant in
order to make feel as if they were the owner of the
power plant, to make them be confident with
production process using clean technology,
utilization of environmental friendly fuels and
waste disposal process of the power plant.
Environm
ental Report for submittal to AD
B N
ong-Saeng Power Plant Project
C
hapter 9 Pow
er Generaton Supply C
o., Ltd. Environmental M
anagement Plan
T-EIA208102
9-68
F208102Chap9Ta_E-A
DB
_revised (4)
Mitigative Measure (Cont’d)
Environmental Impacts Mitigative Measures Monitoring Programme Responsibility
14. Public Relation and Public Participation (Cont’d)
- Mass/community communication plan for setting up the projects for supporting community’s common interests that upgrade life quality of people living around the project site. This is the action plan for the activities additional to those supported by the budget of the fund for development of communities around the power plant. The activities are • The project for educational support in the form
of scholarship granting to children in communities and donation of learning and sport kits to schools locating within the radius of 5 kilometers away from the project site.
• The project for supporting public health and occupational health of communities, for example, organization of mobile medical unit.
• The project for recruitment of outstanding students to be the power plant staff.
• The project for maintaining religions in the area around the power plant.
• The project for career promotion and income development for communities, such as, promotion of agricultural occupation or processing of value-added foods from local agricultural products, supporting of housewife groups to produce several foods from local agricultural products and sell them to other locals or upgrade them to be the OTOP goods.
- Power Generation Supply Co., Ltd.
Environm
ental Report for submittal to AD
B N
ong-Saeng Power Plant Project
C
hapter 9 Pow
er Generaton Supply C
o., Ltd. Environmental M
anagement Plan
T-EIA208102
9-69
F208102Chap9Ta_E-A
DB
_revised (4)
Mitigative Measure (Cont’d)
Environmental Impacts Mitigative Measures Monitoring Programme Responsibility
14. Public Relation and Public Participation (Cont’d)
• The project for conservation of art and culture, custom and local wisdom.
- The supporting projects for development of community potential in the field of environment. The projects are for making community understand and be aware of importance of participation in taking care of environmental problems in the communities. The projects are also for supporting of the management of community development fund. They include the following : • The project on promotion of development of
local conservation tourist sites. • The training projects for disaster mitigation, first-
aid, information sharing (method and channel) between the power plant representatives, governmental officials and the communities.
• The supporting of school activities, such as environmental monitoring volunteer, young environmental scientists, e.g., wind detectives, stream detectives, etc.
• The reforestation project to increase green area in the communities and in the adjacent areas in Nong-Saeng, Nongkhae Districts of Saraburi Province, and in Pachee District of Phra Nakhon Si Ayutthaya Province will reduce concern about changing environment.
- Power Generation Supply Co., Ltd.
Environmental Report for submittal to ADB Nong-Saeng Power Plant Project Chapter 10 Power Generation Supply Co., Ltd. Conclusion and Recommendation
T-EIA208102 10-1 F208102Chap10E
Chapter 10
Conclusion and Recommendation The Nong-Saeng Power Plant Project of Power Generation Supply Co., Ltd. is
located in an area of approximately 570 rai which is allocated into 2 portions of areas: the
power plant area of approximately 300 rai which is located in Moo 4 of Ban Huaiba,
Nong-Kob Sub-district, Nong-Saeng District of Saraburi Province; and the reservoir area
of approximately 270 rai which is located in Moo 7 of Ban Thamsinthusopa, Nong-Namsai
Sub-district, and Moo 2 of Ban Klong, Khok Muang Sub-district, Pachee District of Phra
Nakhon Si Ayutthaya Province. The Nong-Saeng Power Plant utilizes natural gas as the
main fuel and diesel oil as backup fuel. The electrical generating capacity is approximately
1,653 MW, comprising two 826.6 MW blocks. About 1,600 MW of the generated
electricity will be sold to the Electricity Generating Authority of Thailand (EGAT) and the
remaining 53 MW will be used within the Nong-Saeng Power Plant. The main components
of the project includes four combustion turbine generators (CTG), four heat recovery steam
generators (HRSG) and two steam turbine generators (STG). The generated electricity is
sold to EGAT via the 500 kV Pachee sub-station and the transmission line which is
connected to EGAT’s Tatakoe-Wangnoi transmission line. The consumption of natural gas
as the main fuel of the project to be supplied by PTT (Public) Co., Ltd. is approximately
265.18 million cubic feet per day; and diesel oil of approximately 6.594 million liters per
day as backup fuel. The raw water is pumped from the Pa-Sak River, upstream of the Phra
Rama Six Dam, and stored in the 1,600,000 cubic meter reservoir before use. The
wastewater generated by the project is treated and reused. Only the effluent discharged
from the cooling tower is drained into the holding pond before discharging into Klong
Huaiba (Klong Ngu-Loem). The quality of the discharged water meets the effluent
standard under the Notification of the Ministry of Industry, Issue No.2 (1996), entitled
“Characteristics of effluents discharged from factories” and the Decree of the Royal
Irrigation Department No.883/B.E.2532, entitled “The prevention and mitigation of the
discharge of low quality water into the irrigation waterways and the waterways connected
to the irrigation waterways in the irrigation project areas.”
Environmental Report for submittal to ADB Nong-Saeng Power Plant Project Chapter 10 Power Generation Supply Co., Ltd. Conclusion and Recommendation
T-EIA208102 10-2 F208102Chap10E
10.1 Air Quality
The main air quality impacts that are potentially resulted from the Nong-Saeng
Power Plant Project during 2 phases are the impacts from dust dispersion during the
construction phase, and the impact from the stack emissions during the operation phase.
During the construction phase of the project which is anticipated to take 40
months, most of the construction activities are land preparation and construction of
foundation, transportation of construction materials, and motor vehicles entering and
exiting the power plant area. The dust generated is of large size and those who will be
imposed by the impact from the construction activities include the workers in the
construction area and the communities nearby the project site. Thus for the purpose of
mitigating such impacts, the Nong-Saeng Power Plant Project has established suitable
environmental measures in the air quality action plan during construction phase.
During the operation phase, the air quality impact resulted from the operation
of Nong-Saeng Power Plant using natural gas as the main fuel and diesel oil as the backup
fuel for electricity generation. The combustion of these fuels generates the air pollutants
including sulfur dioxide (SO2), oxides of nitrogen (NOx), and particulate matters (PM)
which will be emitted into the atmosphere. The SO2, NOx and PM emission rates of Nong-
Saeng Power Plant Project, when using natural gas as fuel, are 7.74, 38.93 and 5.92 grams
per second per stack respectively at the 100% load; 6.34, 31.87 and 4.84 grams per second
per stack respectively at the partial load (80% load); 4.92, 24.74 and 3.76 grams per
second per stack respectively at the 58% load; and 1.50, 10.77 and 1.05 grams per second
per stack respectively during startup and shutdown. When using diesel oil as fuel, SO2,
NOx and PM emission rates are 22.41, 64.37 and 9.99 grams per second per stack
respectively at the 100% load; 18.78, 53.94 and 8.37 grams per second per stack
respectively at the partial load (80% load); 16.36, 47.01 and 7.29 grams per second per
stack respectively at the 58% load; and 4.69, 13.48 and 3.83 grams per second per stack
respectively during startup and shutdown. Then, these results were used in the impact
assessment by modeling. The meteorological data of the year 2007 were used as the input
data to the model, the estimated maximum hourly average concentrations of sulfur dioxide
in the ambient resulting from the emission sources of the project, in case of using natural
gas as fuel, were 12, 11, 10 and 10 micrograms per cubic meter for the 100% load, partial
load (80% load), 58% load and startup/shutdown conditions respectively. The maximum
Environmental Report for submittal to ADB Nong-Saeng Power Plant Project Chapter 10 Power Generation Supply Co., Ltd. Conclusion and Recommendation
T-EIA208102 10-3 F208102Chap10E
24-hour average concentrations were 4, 4, 3 and 3 micrograms per cubic meter for the
100% load, partial load (80% load), 58% load and startup/shutdown conditions
respectively. The maximum annual average concentrations were estimated to be 0.7, 0.7,
0.7 and 0.6 micrograms per cubic meter for the 100% load, partial load (80% load), 58%
load and startup/shutdown conditions respectively. All predicted concentrations complied
with the standards for the hourly, 24-hour and annual average concentrations of sulfur
dioxide of 780, 300 and 100 micrograms per cubic meter respectively (under the
Notification of the National Environment Board, No.21 (2001) and No.24 (2004)).
In case of using diesel oil as fuel, the maximum hourly average concentrations
of sulfur dioxide resulting from the emission sources of the project were estimated to be
24, 24, 23 and 27 micrograms per cubic meter for the 100% load, partial load (80% load),
58% load and startup/shutdown conditions respectively. The maximum 24-hour average
concentrations were 6, 7, 7 and 8 micrograms per cubic meter for the 100% load, partial
load (80% load), 58% load and startup/shutdown conditions respectively. The maximum
annual average concentrations were 1 micrograms per cubic meter for all operating loads.
All predicted concentrations were within the applicable standards for the hourly, 24-hour
and annual average concentrations of sulfur dioxide under the Notification of the National
Environment Board, No.21 (2001) and No.24 (2004).
The estimated maximum hourly average concentrations of nitrogen dioxide in
the ambient resulting from the emission sources of the project, in case of using natural gas
as fuel and applying the NO2/NOx ratio of 0.75, were 45, 43, 39 and 75 micrograms per
cubic meter for the 100% load, partial load (80% load), 58% load and startup/shutdown
conditions respectively. When using diesel oil is used as fuel, the estimated concentrations
were found to be 52, 51, 50 and 77 micrograms per cubic meter respectively, complying
with the standard of 320 micrograms per cubic meter under the Notification of the National
Environment Board, No.10 (1995).
In case of using natural gas as fuel, the estimated maximum 24-hour average
concentrations of in the ambient resulting particulates from the emission sources of the
project were 3 micrograms per cubic meter for all operating loads. The maximum annual
average concentrations were 0.5, 0.5, 0.6 and 0.5 micrograms per cubic meter for the 100%
load, 80% load, 58% load, and startup/shutdown conditions respectively. When diesel oil
is used as fuel, the maximum 24-hour average concentrations were found to be 3, 3, 3 and
Environmental Report for submittal to ADB Nong-Saeng Power Plant Project Chapter 10 Power Generation Supply Co., Ltd. Conclusion and Recommendation
T-EIA208102 10-4 F208102Chap10E
7 micrograms per cubic meter respectively, and the maximum annual average
concentrations were 0.5, 0.5, 0.5 and 1.2 micrograms per cubic meter respectively. It can
be seen that the estimated concentrations were within the applicable standards of 330 and
100 micrograms per cubic meter for 24-hour and annual average concentrations
respectively, under the Notification of the National Environment Board, No.24 (2004).
10.2 Noise Level
During the construction phase of Nong-Saeng Power Plant, the noise sources,
of the project are those where the maximum sound pressure level at 15 meters from the
machine is assigned to be 101 dB(A) and 85 dB(A) during the daytime and nighttime
respectively. The noise levels at the noise sources are reduced by installing the iron screen
or zinc screen of at least 1.3 mm. thick around construction area, resulting in the decrease
of noise level from noise sources by about 25 dB(A). (Reference : FHWA (Federal
Highway Administration) U.S.A., 2006). Therefore, the maximum sound pressure level
during the construction phase after installing the iron screen or zinc screen were 76 dB(A)
and 60 dB(A) during the daytime and nighttime respectively. The noise impact was then
determined from Decay Formula Equation. It was found that during the daytime, the noise
levels in the plant vicinity area of 500 m, 1 km, 2 km and 3 km radius were approximately
45.5, 39.5, 33.5 and 30.0 dB(A) respectively. During the nighttime, the noise levels in the
area of 500 m, 1 km, 2 km and 3 km far from the project were approximately 29.5, 23.5,
17.6 and 14.1 dB(A) respectively. The impacts of the sound pressure level are decreased as
the distance from the construction area.
The communities nearby the project area which are Wat Thamsinthusopa, Wat
Nong-Tangbun, Wat Khok Muang and Wat Nongkratart would expose to the noise levels
of 29.0-44.5 dB(A) during daytime and 13.3-28.6 dB(A) during nighttime. The estimated
sound pressure levels were below the standard of 70 dB(A) regulated by the Notification of
the National Environment Board No.15 (B.E.2540). The noise levels generated from the
project were used to estimate the annoyed noise level which was found to be below the
standard of 10 dB(A) regulated by the Notification of National Environment Board No.29
(B.E.2550).
During the operation phase, the communities nearby the project area which are
Wat Thamsinthusopa, Wat Nong-Tangbun, Wat Kok Muang and Wat Nongkratart would
expose to noise levels of 14.7-31.0 dB(A). The estimated sound pressure levels were below
Environmental Report for submittal to ADB Nong-Saeng Power Plant Project Chapter 10 Power Generation Supply Co., Ltd. Conclusion and Recommendation
T-EIA208102 10-5 F208102Chap10E
the standard of 70 dB(A) regulated by the Notification of the National Environment Board
No.15 (B.E.2540). The impacts of the annoyed noise level on the nearby communities were
found to be nil during daytime and nighttime.
10.3 Surface Water Hydrology and Surface Water Quality
The activities of the power plant potentially impact the impacts on the surface
water quality outside the power plant during 2 phases, i.e., the construction and operation
phases. During the construction phase, there are 2 important sources of wastewater, i.e.,
the wastewater from the consumption of the contractor(s) and the construction workers.
The sanitary wastewater generated from the all construction workers is discharged to the
compact wastewater treatment systems. The treated effluent is stored in the sumps for later
uses, i.e. spraying over the construction area and other vacant areas of the project to
suppress dust dispersion without discharging to the outside. In addition, the storm water
may wash away the sediment from the construction area into the water resources. Hence,
the Nong-Saeng Power Plant Project specified the mitigative measures for flood control by
requiring the drainage of storm water into the temporary sump in order to let the sediment
settle, and the clear water is separated for uses in the construction and subsequently
drained into the receiving water resources.
During the operation phase, the Nong-Saeng Power Plant Project utilizes the
water from the Pa-Sak River by pumping it at a rate of 46,932 cubic meters per day when
using natural gas as fuel and 38,518 cubic meters per day when using diesel oil as fuel.
The water from this river will be stored in the 1,600,000 cubic meter raw water reservoir of
the project and subsequently used for the follows:
Natural gas firing Diesel oil firing
(cu.m./day) (cu.m./day)
Demineralization 936 954
Cooling 45,918 37,490
Sanitary use in the office 30 30
Other uses 48 44
The project is designed to reuse the effluent as much as possible. The
management of the effluent from the project operation is considered to be 2 parts as
follow :
Environmental Report for submittal to ADB Nong-Saeng Power Plant Project Chapter 10 Power Generation Supply Co., Ltd. Conclusion and Recommendation
T-EIA208102 10-6 F208102Chap10E
(1) Cooling water blow down from the cooling system. The quantity of this
water is 11,276 and 9,168 cubic meters per day when using natural gas and diesel oil as
fuel respectively. The cooling water blow down is drained into two 45,000 cu.m. cooling
water blow down ponds which can retain the effluent for 3 days before discharging into
Klong Huaiba (Klong Nong-Ngu-Loem).
(2) Effluent which is not the cooling water of the project is splited into 2
portions as follows:
- Effluent contaminated with chemicals includes the effluent from the
demineralization system, contaminated water from the chemical
storage area, laboratory, etc. These effluent is collected and sent to the
neutralization pit for treatment. The treated effluent of approximately
88 cubic meters per day is conveyed into the zero liquid discharge
system which turns them into reusable water. The remaining solids
from the final step of this system is subsequently disposed according
to the procedure specified in the Notification of the Ministry of
Industry, entitled “Disposal of Garbages or Unused Materials, 2005.”
- Effluent from the office buildings of 30 cubic meters per day is treated
in the septic tank and then collected in the holding pond and used for
watering the plants. The remaining water from plant watering (if any)
will be conveyed into the zero liquid discharge system. If the treated
effluent cannot be used for watering plants, all of it will be conveyed
into the zero liquid discharge system. The quantity of the effluent
from the office buildings and the chemical contaminated effluent is
118 cubic meters per day.
Therefore, in order to mitigate the potential impacts of the effluent from the
project on the receiving water resources and the communities around the project area, the
Nong-Saeng Power Plant Project established the appropriate mitigative measures in the
water quality action plan for both construction and operation phases. The effluent quality
is controlled to meet the effluent standard as specified in the Notification of the Ministry of
Industry, No.2, B.E.2539 (1996) entitled “Characteristics of effluent discharged from
factories”, and the Order of the Royal Irrigation Department No.883/2532, entitled “The
mitigation of low quality effluent discharged into the irrigation waterways and the
waterways connected with them within the irrigation project areas.”
Environmental Report for submittal to ADB Nong-Saeng Power Plant Project Chapter 10 Power Generation Supply Co., Ltd. Conclusion and Recommendation
T-EIA208102 10-7 F208102Chap10E
10.4 Forestry and Wildlife Ecology
It was found from the study and survey of forestry and wildlife living near the
power plant area that the condition of study area could be described as typically flat land
with flooded areas between rice paddy fields and communities. The conditions of forests
that covered the ground were cultivated forests mixed with structures and no natural forest
condition actually existed in this area. Moreover, the remaining big trees in the area were
grown by local people. For the diversity of wildlife species in the study area, the results
from this study revealed a total of 138 species including the wildlife that could be sighted
in the open, paddy field, grove and wetland habitat areas. This is because the existing
condition of the study area was paddy fields where rice growing was still active,
communities were generally located, some temples with a few trees also existed, and some
wetlands were sighted. This area having no condition of natural forest land was
completely altered from its natural features. Its ecosystem was a man-made one so no
natural wildlife habitats, i.e. forest, remained in the environment. The only existing habitat
areas included paddy fields, deserted lands, wetlands and communities so the wildlife
species found in this area were the species that had well adapted themselves to survive in
the communities. No wildlife species living in the dense forest habitats was found and the
sighted ones all had the capability to adapt themselves very well.
10.5 Aquatic Ecology and Fishery
The Nong-Saeng Power Plant Project will drain the flowing water during its
construction phase and the effluent from the cooling system into Klong Huaiba (Klong
Nong-Ngu-Loem) during its operation phase. The drainages of the effluent may affect
aquatic ecological system by reducing the number of the planktons and young aquatic lives
which may be entrained in the water to be pumped for the project’s uses.
10.6 Land Use
The development of Nong-Saeng Power Plant Project requires an area of 570
rai. At present, the major parts of this area are mostly paddy fields, grass fields and
deserted or vacant areas. The pumping station is located in an area of approximately 1 rai
and the water pipeline is of approximately 16 kilometers in length. The construction of the
water pipeline requires an area of approximately 2 meters in width, starting from the
pumping station upstream of the Rama Six Dam and routing in parallel with the road along
Environmental Report for submittal to ADB Nong-Saeng Power Plant Project Chapter 10 Power Generation Supply Co., Ltd. Conclusion and Recommendation
T-EIA208102 10-8 F208102Chap10E
the bank of Klong Rapeepatana-East to the project site. The water drainage pipeline with a
length of only 150 meters and a width of approximately 2 meters will be routed from the
project site, crossing under the road along the bank of Klong Rapeepatana, to merge with
the discharge pipe on the reservoir side and then into Klong Huaiba (Klong Nong-Ngu-
Loem) which is on the south side of the reservoir. Therefore, the potential impact is
considered to be low.
10.7 Water Usage
During the construction phase of the project, the maximum number of the
workers is 6,000 consuming approximately 360 cubic meters of water per day (which was
estimated from the water consumption of the workers at a rate of 60 liters per person per
day). The project will buy the water either from the Office of Water Supply in Nong-Kae
District or the Office of Water Supply in Taruer District. Considering the existing water
production capacity of the Office of Water Supply in Nong-Kae District of 573,462 cubic
meters per month and its water dispensing rate of 483,820 cubic meters per month, it can
be seen that this agency still have the water supply reserve of 90,042 cubic meters per
month. The Office of Water Supply in Taruer District has its existing water production
capacity of 159,787 cubic meters per month and water dispensing rate of 113,378 cubic
meters per month, and still have the water supply reserve of 46,409 cubic meters per
month. During its operation phase, the Nong-Saeng Power Plant Project will pump the
water from the Pa-Sak River (at the upstream of Rama Six Dam) at the average of 46,932
cubic meters per day or 1.41 million cubic meters per month for its uses in electricity
generation, cooling water and others within the power plant during the rainy season. In
June to November of this season, there is a large quantity of the remaining water released
from the Rama Six Dam into the Pa-Sak River (at the downstream of Rama Six Dam) at
the rate of 100-642 million cubic meters per month. During these months of the year, the
power plant can pump the water with very low impact on the downstream areas of the
Rama Six Dam. This is because the quantity of water to be used in the power plant is less
than 1.41% of the water released through the Rama Six Dam during the period of the least
quantity of water in the rainy season. In the first month of the rainy season (May) and the
beginning of the dry season (December), the water consumption of the power plant is
approximately 5.6% of the irrigation water to be released into the Pa-Sak River (at the
downstream of Rama Six Dam). This water quantity is considered to impose slight impact.
Environmental Report for submittal to ADB Nong-Saeng Power Plant Project Chapter 10 Power Generation Supply Co., Ltd. Conclusion and Recommendation
T-EIA208102 10-9 F208102Chap10E
on the water discharging to the downstream of Rama Six Dam, and definitely no impact on
the water flowing into Klong Rapeepatana-Main Canal. During the dry season (January
through April), almost all of the water quantity at the upstream of Rama Six Dam is
diverted into Klong Rapeepatana-Main Canal for irrigation purpose. However, it was
found from the analysis of the water balance that the quantity of water usage of the project
was less than 1% for irrigation. The project has planned to construct a reservoir with a
capacity of 1,600,000 cubic meters for reserving its raw water. With the availability of this
reservoir, the Nong-Saeng Power Plant will be able to operate for a period of 39 days
without pumping the water from any outside source when a problem of water shortage
arises in the dry season. Hence the water usage of the project, particularly during the dry
season, will not impose any impact on the existing agricultural areas. In case of Klong
Huaiba (Klong Nong-Ngu-Loem), this canal will be benificial from the quantity of the
discharged water of the project because of the increase in its water quantity, particularly
during the dry season. This can be considered as a positive impact of the project.
10.8 Transportation
The estimated traffic volume in terms of passenger car units (PCU) on
Highway No.1, No.329, No.3043 and Road along the bank of Klong Rapeepatana (left and
right stream) were found to be 141,541, 11,660, 3,126, 969 and 208 cars per day
respectively. The V/C ratio values indicating the vehicular capacity of the road were found
to be 0.3, 0.2, 0.06, 0.02 and 0.004 respectively. The results revealed that Highway No.1,
No.329, No.3043 and Road along the bank of Klong Rapeepatana (left and right stream)
could handle more traffic volume. Besides, the V/C ratio on Road along the bank of Klong
Rapeepatana (left and right stream) during rush hours or 08.00-10.00 a.m. and 04.00-06.00
p.m. were found to be in the rang of 0.002-0.01 and 0.004-0.02 respectively. The vehicle
volume was estimated to be increased during construction and operation phase by
approximately 150 and 80 cars per day respectively. The V/C ratio was then found to be
indifferent. Therefore, the impacts on traffic condition during the construction and
operation phase were considered to be quite low.
10.9 Drainage and Flood Control
The land preparation, general construction activities, and operation of Nong-
Saeng Power Plant potentially result in impacts on the drainage condition and induce
flooding. The most potential cause of flooding is the rainfalls over the area covered by the
Environmental Report for submittal to ADB Nong-Saeng Power Plant Project Chapter 10 Power Generation Supply Co., Ltd. Conclusion and Recommendation
T-EIA208102 10-10 F208102Chap10E
Klong Preol Water Conveyance and Maintenance Project which has a road along its
boundary. Moreover, the terrain slopes down to Klong Rapeepatana so most of the
rainwater will flow towards this canal; whereas the side dike along the right bank (east) of
this canal, or the road with a high elevation, will retain and accumulate the water that flows
towards it because the water cannot flow over. As mentioned earlier, the Nong-Saeng
Power Plant Project area is in the moderate flood risk zone.
The existing drainage systems around the Nong-Saeng Power Plant Project
include several natural discharge canals, i.e., Klong Nong-Srueng, Klong Huaiba (Klong
Nong-Ngu-Loem), Klong Ban-Kokkeelek, and Klong Nong-Kae. All of these four canals
cross Klong Rapeepatana with a water gate located at each confluence to control the water
flow. These canals are always dredged to keep them from being shallow. However,
problems still exists regarding the drainage that cannot be managed in time during the
heavy rainfalls over the area. This problem has caused flooding and stagnant waters
especially at the confluences of the discharge canals (Klong Nong-Srueng/Klong Huaiba
[Klong Nong-Ngu-Loem]) and Klong Rapeepatana. There is siphon building at Klong
Ban-Kokkeelek that facilitates the discharge flow to pass under Klong Rapeepatana. The
construction of a drainage channel, currently under consideration, which will facilitate the
drainage of flood and stagnant waters along the side dike of Klong Rapeepatana starts from
the north to the south along Klong Rapeepatana and merges with the siphon to allow the
discharged water flow under Klong Rapeepatana. At present, the terrain condition is
changed to some extent. There have been some land preparations (i.e. land filling and
elevating, self-managed land preparation, etc.) that do not take natural drainage into
consideration. Moreover, the road network around the project area has made it difficult to
drain the rainwater from the area. If a sufficiently efficient management is not available,
an impact may be resulted. Therefore, in order to prevent the impact that may be induced,
the project must provide a means for draining the rainwater and preventing the occurrence
of flooding.
10.10 Solid Wastes
During the construction phase, the maximum of 6,000 workers are expected to
be employed, generating approximately 5.1 tons of garbages per day (bases on the criterion
that one person will generate garbages at a rate of approximately 0.85 kilogram per
individual per day). Other solid wastes generated during the construction phase include
Environmental Report for submittal to ADB Nong-Saeng Power Plant Project Chapter 10 Power Generation Supply Co., Ltd. Conclusion and Recommendation
T-EIA208102 10-11 F208102Chap10E
scrap materials from soil excavation (e.g., scraps of soil, sand, brick, etc.), scraps of
construction materials (e.g., fractions of structures, or used or unwanted materials, etc.),
hazardous wastes (e.g., batteries, motor oil, hydraulic oil, filters, mineral oil, cleaning
agents or used solvents) as well as enamel products or rejected paints. The project will
provide a specific space for storing each type of garbages or solid wastes, including
appropriate containers for segregating each type of solid wastes which will facilitate the
disposal according to the Notification of the Ministry of Industry, entitled “Disposal of
Garbages or Unwanted Materials”, 2005.
During operation phase, 6 types of solid wastes are generated as follows :
(1) General garbages from Office Buildings are collected in the bins and
disposed outside the plant by the contracted local agency.
(2) Spent Air Filters are separately collected by the project and disposed by
an authorized waste disposal facility.
(3) Spent Lubricating Oil and oil from oil separators is collected in 200 litre
tanks and disposed by an authorized waste disposal facility.
(4) Spent Resins are returned to their manufacturer or separately stored and
subsequently disposed by an authorized waste disposal facility.
(5) Sludge from water treatment system.
(6) Solid wastes from evaporation process are stored for disposal by an
authorized waste disposal facility.
Nong-Saeng Power Plant Project will dispose the solid wastes according to the
Notification of the Ministry of Industry, B.E.2548, entitled “Disposal of Garbages or
Unused Materials.”
10.11 Occupational Health and Safety
During construction phase, there are approximately 6,000 construction
workers. Working maybe risky to cause an accident so the project must have measures for
safe working and strictly enforce the implementation of the measures. For operation phase,
the environmental conditions in workplace within Nong-Saeng Power Plant might affect
health and safety of workers who are working within the power plant. Three parameters of
concern are as follows:
(1) Noise: The main noise sources in the power plant are gas turbine, gas
compressors, safety valve, etc. The sound pressure levels generated from those machines
and equipments are controlled by installing noise reduction equipments, such as Acoustic
Environmental Report for submittal to ADB Nong-Saeng Power Plant Project Chapter 10 Power Generation Supply Co., Ltd. Conclusion and Recommendation
T-EIA208102 10-12 F208102Chap10E
Wall, Encapasulate, Silencer at these equipments, assigning employees to work in a control
room, and enforcing them to wear noise protection equipments while working in the loud
noise area of higher than 80 dB(A).
(2) Heat: The main heat sources in the power plant are steam turbine,
combustion turbine and HRSG. The power plant uses insulation system for heat protection,
and enclosure of heat sources. Employees are assigned to work in a control room and
enforced to wear heat protection equipments while working in heated area .
(3) Chemicals: The operation of the power plant concerned with some
chemicals. The important chemicals are sulfuric acid, sodium hypochlorite, ferric chloride,
which can be exposed by the employees, but the production process of the project is
operated in the closed system. However, the power plant provided personal protective
equipments for the employees who work with the chemicals, good ventilation within the
power plant, and training of employees on safe working with chemicals and procedures for
prevention and test for chemical leakage.
Regarding the measures for the working environment, it revealed that the
impacts on occupational health and safety of the employees in the power plant were low.
However, Nong-Saeng Power Plant specified the action plan on occupational health and
safety in order to mitigate the impacts of working environmental conditions on employees’
health and safety.
10.12 Socio-economics
The socio-economic study was conducted by collection of statistics related to
the study area along with the field survey in the radius of 5 kilometers around the site-to-be
of the Nong-Saeng Power Plant of the Power Generation Supply Co., Ltd. The study
started with visiting chiefs of offices at province, district and subdistrict levels, community
leaders and local administration organization executives. It was followed by organization
of public hearing, plant tour, and listening to opinion of 1,095 families. It was found that
the number of communities in the study area agreed with the project was quite low. It was
attributed to anxiety about impacts on agricultural careers and people’s health. The impacts
on health were expectly resulted from wastewater and stack emissions from the power
plant. This expectation was arisen from previous information about impacts of other power
plants. For the sample groups who agreed with the power plant construction, they showed
Environmental Report for submittal to ADB Nong-Saeng Power Plant Project Chapter 10 Power Generation Supply Co., Ltd. Conclusion and Recommendation
T-EIA208102 10-13 F208102Chap10E
their reasons, such as community development, local employment, more local economic
growth, convenient infrastructure and better community service, etc.
Although the Power Generation Supply Co., Ltd., has specificed the mitigative
measures for the potential impacts resulting from the operation of the Nong-Saeng Power
Plant project, the work plan on socio-economics is specified in order that the project is able
to cohabitate, to have good relationship and to share benefit with the community.
10.13 Public Relation and Public Participation
The project implementation during construction and operating period may
cause positive and negative impacts on people living around the Nong-Saeng Power Plant
Project. In order that the operation of the Power Generation Supply Co., Ltd. brings about
the advantages to communities and reduces negative impacts as much as possible, the
Power Generation Supply Co., Ltd., has prepared the action plan and has organized people
participation activities in every steps continually in the study and EIA. The activity of
public hearing in the study and EIA was to make community leaders understanding about
reasons, necessity of the project operation, including the procedure of the study and
assessment of environmental impact which involve public participation in data collection,
information dissemination and listening to opinion and suggestion of community leaders
and relevant persons. The public hearing was one of the stages opened for participants to
express opinion, anxiety, important issues or suggestion which are useful for setting
mitigative measures for minimizing social impacts and particularly, the potential
environmental and social impacts during construction and operating phases. The
stakeholders had given opinion and suggestion which are useful for the completeness of
the study results which led to the acceptance and participation of local sector. The
activities performed were attributed to the cooperation of community leaders and people in
communities around the power plant. They attended the meeting, asked questions and gave
suggestion to the project. Analysis and evaluation of the impacts indicated that some
communities were still anxious about potential impacts resulted from the Nong-Saeng
Power Plant Project. However, more than half were aware of necessity of energy
development work and importance of community participation in the study, monitoring of
environmental impacts, watching and control of environmental problems in the
community. They were willing to be representatives for monitoring and inspection of
environmental impacts. It is expected that if the work on making understanding and
Environmental Report for submittal to ADB Nong-Saeng Power Plant Project Chapter 10 Power Generation Supply Co., Ltd. Conclusion and Recommendation
T-EIA208102 10-14 F208102Chap10E
learning is performed with the communities and community leaders, the community
members will join the network for monitoring and inspection of environmental impacts in
communities around the Nong-Saeng Power Plant Project. It will also encourage the
communities to participate in any collaborations and profit sharing. All of these activities
will lead to continuous development of the project and acceptance from people living
around the project.
10.14 Recommendation
Based on the results of the EIA study, a few recommendations are drawn for
the project to consider conducting further studies and investigations as follows:
(1) The project should, under all conditions, strictly enforce the
implementation of the proposed environmental measures designed for the construction and
operation phases in order to avoid or minimize both environmental and social impacts on
the surrounding communities and general public.
(2) The project should always conduct a preliminary environmental study
when planning to make any modification of the project design and/or the environmental
action plan to find out the environmental feasibility before making the decision.
(3) A study should be conduct to investigate the effect of climate change on
the water availability in the Pa-Sak River and the required reserve volume of raw water in
the 1,600,000 cubic meter reservoir during the entire operation life of the proposed power
plant.
(4) The greenhouse gas emissions from the proposed power plant should be
investigated during the operation phase. The findings from the investigation will be a
useful database for many future uses, internally and externally.
Environmental Report (Pre-Construction and Construction Phases) Nong Saeng Power Plant Project
Power Generation Supply Co., Ltd.
Environmental Audit/SECOT 1 SERVER/Env Audit Text (Eng).doc
1. Background Information
Nong-Saeng Power Plant Project of Power Generation Supply Co. Ltd. is situated
in an area of about 570 rai. The area is divided into 2 parts including the power plant area of
about 300 rai in Moo 4 Ban Huaiba, Nongkob Sub-district, Nong-Saeng District, Saraburi
Province; and the reservoir area of about 270 rai in Moo 7 Ban Thamsinthusopa, Nong-
Namsai Sub-district and Moo 2 Ban Klong, Kokmuang Sub-district of Pachee District,
Ayudhya Province. The proposed power plant, using natural gas as primary fuel and diesel
oil as secondary fuel, will have an install capacity of about 1,653 megawatts (MW). About
1,600 MW of the electricity to be generated will be sold to the Electricity Generating
Authority of Thailand (EGAT) while the remaining 53 MW will be used in-house. Natural
gas for use as primary fuel of the project at a rate of about 265.18 million cubic feet per day
will be obtained from PTT (Public) Co., Ltd., whereas diesel oil as secondary fuel will be
used at a rate of about 6.594 milliion liters per day. Raw water for the project will be
pumped from the Pa-Sak River, at upstream of Rama Sixth Dam, for storage in a 1,600,000 m3
reservoir before use. Wastewater to be induced by the project will be treated and reused, and
the discharged water from the cooling tower (the only discharged effluent) will be routed into
the holding pond prior to discharge into Klong Huaiba (Klong Nong-Nguleum). The
discharged water quality will be according to the effluent standards under the Notification of
Ministry of Industry, No. 2 (1996), “Designation of characteristics of effluents to be
discharged from factories”; and Command of the Royal Irrigation Department, No. 883/1989,
“Prevention and mitigation of discharging low quality effluents into the irrigating waterways
and the waterways connected to the irrigating waterways in the irrigation project area.”
Environmental audit is to inspect and monitor the environmental performance of
the project as specified in the environmental impact assessment report (EIA) which was
approved by the Office of Natural Resources and Environmental Policy and Planning on
September 16, 2009 (Approval Letter No. NSE 1009.7/7072). At present, the project is at the
stage of conducting the land preparation work in the above-mentioned two (2) key areas i.e.
the power plant and reservoir areas.
The audit for the performance on the environmental impact mitigation measures
during the pre-construction and construction phases includes the measures on 13 aspects : i.e.
air quality, noise, surface water hydrology and quality, forestry and wildlife, aquatic ecology
and fishery, land use, water usage, transportation, drainage and flood control, solid wastes
Environmental Report (Pre-Construction and Construction Phases) Nong Saeng Power Plant Project
Power Generation Supply Co., Ltd.
Environmental Audit/SECOT 2 SERVER/Env Audit Text (Eng).doc
management, occupational health and safety, socio-economics, and public relations and
participation.
2. Objectives
To audit and evaluate the environmental performance of the project for
consistency with the conditions specified in the EIA report, and to recommend guidelines (if
any) for improving the environmental performance to make it suitable and practical.
3. Scope of Work
The environmental audit has been planned to inspect and evaluate the following
key study issues during the pre-construction and construction phases as specified in the EIA
report:
(1) Air quality
(2) Noise
(3) Surface water hydrology and quality
(4) Forestry and wildlife
(5) Aquatic ecology and fishery
(6) Land use
(7) Water usage
(8) Transportation
(9) Drainage and flood control
(10) Solid wastes management
(11) Occupational health and safety
(12) Socio-economics
(13) Public relations and participation
4. Methodology
The audit for the performance on the environmental measures includes the following
main steps:
Environmental Report (Pre-Construction and Construction Phases) Nong Saeng Power Plant Project
Power Generation Supply Co., Ltd.
Environmental Audit/SECOT 3 SERVER/Env Audit Text (Eng).doc
4.1 Review of Data
Review of related data and documents which can be classified as follows:
(1) The EIA report and environmental measures performance report
(2) Permit documents issued by various government offices as well as the
conditions attached with the permits
In detail, the pre-audit procedure is as follows:
(1) Setting a preliminary scope of work and work plan
(2) Reviewing and inspecting the related documents such as laws in use,
criteria under the EIA report and EMS (Environmental Management System), etc.
(3) Collecting/gathering project data and documents
(4) Preparing audit forms, and setting the scope and plan for the audit
4.2 On-site Survey
A survey was conducted in the two (2) key areas of the project that are at the
stage of land preparation, i.e. the power plant and reservoir areas, in order to audit the actual
performance on the environmental impact mitigation measures specified in the EIA report.
4.3 Reporting
The audit report includes the following sections:
(1) Initial summary of project data (e.g. location, process, utility systems,
pollutants and control, wastewater and management, solid wastes and management, noise and
control, occupational health and safety, and green area) includes the data relating to the
current performance of the project along with its location.
(2) Presentation of the results and analysis along with the results of audit on the
environmental impacts of the project obtained from the on-site survey and review of data by
classifying into separate issues i.e. air quality, water quality, noise, solid wastes, occupational
health and safety, and other related items as well as the audit results of the related process
supporting and utility systems.
(3) Summary of the audit results and recommendations derived from auditing
the environmental impacts, and presentation of guidelines for the improvement of
environmental impact mitigation measures and environmental quality monitoring program as
per the EIA report approved by the Office of Natural Resources and Environmental Policy
and Planning as well as presentation of other environmental impact mitigation measures to be
implemented as mandated by the concerned government offices.
Environmental Report (Pre-Construction and Construction Phases) Nong Saeng Power Plant Project
Power Generation Supply Co., Ltd.
Environmental Audit/SECOT 4 SERVER/Env Audit Text (Eng).doc
5. Anticipated Results
The project performance relating to environmental management and
implementation of environmental measures as specified in detail in the EIA report, and
recommendations (if any), derived after the environmental audit, for the project to put into
practice and improve the environmental management for its utmost benefit.
6. Audit on Environmental Impacts
Nong-Saeng Power Plant of Power Generation Supply Co., Ltd. is currently at the
stage of land preparation of two (2) key areas i.e. the power plant and reservoir areas. These
areas are as specified in the EIA report which was approved by the Office of Natural
Resources and Environmental Policy and Planning (Approval Letter No. NSE 1009.7/7072).
The audit on environmental impacts was conducted so as to be consistent with the
environmental impact mitigation measures. The results of the audit on the project performance
relating to the environmental impact mitigation measures can be summarized as shown in
Table 6-1.
Environm
ental Report (Pre-Construction Phase and C
onstruction Phase)
Nong-Saeng Pow
er Plant Project Pow
er Generation Supply C
o., Ltd. Environm
ental Audit./SEC
OT
5
SER
VER
/Env Audit Table 1 (Eng) R
ev
Table 6-1 Implementation of Environmental Mitigative Measures (Pre-Construction and Construction Phases)
Nong-Sang Power Plant Project of Power Generation Supply Co., Ltd.
Nong-Kob Sub-district, Nong-Sang District of Saraburi Province
Environmental
Impact Mitigative Measure Mitigative Action
Result Reference
compliance noncompliance
1. Air Quality Pre-Construction Phase
- Ambient air quality monitoring systems (AAQMS)
are installed in 4 community areas including Ban
Thamsinthusopa, Ban Nong-Tangbun, Ban Nong-
Ngu-Loem and Ban Khok Daeng for continuous
monitoring of the concentrations of total suspended
particulates, PM-10, sulfur dioxide, nitrogen
dioxide, and taking measurements of wind speed and
direction, and ambient temperature.
- Due to AAQMS could not
operate on time; air quality
monitoring (7 consecutive days)
was conducted during March 4-
12, 2011 as result in attachment.
Additional, continuous air quality
monitoring stations were installed
from May-September (or until
AAQMS have been installed
already).
* - Photo 1, air
quality monitoring
station.
- Appendix I,
Monitoring
results of ambient
air quality.
Construction Phase
- To spray water, at least twice a day, on soil piles and
areas where excavation of soil is taking place,
particularly on transport routes within the project
area.
- This measure is implemented.
*
- Photo 2, water
spraying.
- To cover the piles of soil and scrap materials with
canvas or plastic sheets to prevent the soil dispersion
during windy periods.
- The project immediately
crushes/presses/levels off the soil
trucked into the area, so no soil
piling is required in the project
area.
* -
Environm
ental Report (Pre-Construction Phase and C
onstruction Phase)
Nong-Saeng Pow
er Plant Project Pow
er Generation Supply C
o., Ltd. Environm
ental Audit./SEC
OT
6
SER
VER
/Env Audit Table 1 (Eng) R
ev
Table 6-1 Implementation of Environmental Mitigative Measures (Pre-Construction and Construction Phases) (Cont’d)
Environmental
Impact Mitigative Measure Mitigative Action
Result Reference
compliance noncompliance
1. Air Quality
(Cont’d)
- To have good housekeeping in the construction area. - This measure is implemented. * - Photo 3, rubbish
was kept in place.
- To limit the speed of motor vehicles within the
construction area to not exceed 20 kilometers per
hour.
- This measure is implemented. * - Photo 4, an
orderly speed
limit sign in the
project area.
- To limit the speed of the contractor’s motor vehicles
on public roads to not exceed 60 kilometers per hour.
- This measure is implemented. * - Photo 5, an
orderly speed
limit sign by the
public road.
- To well cover the trucked materials/articles for the
entire transporting routes.
- This measure is implemented. * - Photo 6, orderly
coverage of
trucked materials
with canvas.
- To provide workers to wash the traffic surface of
public road in front of the project area after the
trucks going in or out of the project area.
- This measure is implemented. * - Photo 7, public
road surface
washing.
- To wash vehicle wheels before leaving the
construction area in order to reduce the amount of
soil particles (stuck on the wheels) falling off onto
the traffic surface.
- This measure is implemented. * - Photo 8, wheel
washing stations.
Environm
ental Report (Pre-Construction Phase and C
onstruction Phase)
Nong-Saeng Pow
er Plant Project Pow
er Generation Supply C
o., Ltd. Environm
ental Audit./SEC
OT
7
SER
VER
/Env Audit Table 1 (Eng) R
ev
Table 6-1 Implementation of Environmental Mitigative Measures (Pre-Construction Phase and Construction Phase) (Cont’d)
Environmental
Impact Mitigative Measure Mitigative Action
Result Reference
compliance noncompliance
1. Air Quality
(Cont’d)
- To prohibit rubbish burning within the construction
area.
- This measure is implemented. * - Photo 9, showing
“No burning of
rubbish” sign.
2. Noise Construction Phase
- To install iron or zinc sheets of a minimum 1.3-mm
thickness around the construction area, particularly
on the side nearby the residential areas of Ban
Thamsinthusopa and Ban Nong-Tangbun
communities, and to construct an earth dike of 4.5-
meters high above the ground level around the
project area.
- None of the loud noise inducing
activities is started, but a fence
has already been instructed
around the project area.
*
- Photo 10, zinc
panels installed
around the
project area.
- Piling and construction activities generating loud
noises shall be carried out in the daytime with a
notice to inform the communities at least 2 weeks in
advance.
- No piling is started and, up to
present, no vehicle running at
night-time is started either.
* -
- To select and use the equipment/machinery, and
construction technique(s) that induce the minimum
noise levels.
- No piling is started. * -
Environm
ental Report (Pre-Construction Phase and C
onstruction Phase)
Nong-Saeng Pow
er Plant Project Pow
er Generation Supply C
o., Ltd. Environm
ental Audit./SEC
OT
8
SER
VER
/Env Audit Table 1 (Eng) R
ev
Table 6-1 Implementation of Environmental Mitigative Measures (Pre-Construction and Construction Phases) (Cont’d)
Environmental
Impact Mitigative Measure Mitigative Action
Result Reference
compliance noncompliance
2. Noise (Cont’d) - To avoid using the equipment or machinery simultaneously which cause loud noises continuously for a long period of time.
- No piling is started. * -
- To reduce the number of equipment/machinery used in areas adjacent to each other.
- No piling is started. * -
- To install the frequently movable (back and forth) equipment/machinery as far as possible from the sensitive areas.
- No piling is started. * -
- To stop the engines or turn off the equipment/ machinery when they are not in use every time.
- This measure is implemented. * - Photo 11, equipment/ machinery are turned off when not in use
- To require the contractor to install the noise reduction equipment, e.g., silencers or mufflers at the loud noise equipment/machinery used in the construction activities and to regularly check the efficiency of the noise reduction equipment.
- No piling is started. * -
- To inspect and maintain the equipment, machinery and engines in good condition by scheduling the inspection of heavy machinery at least once a month.
- No written regulations are available.
* -
- To post a warning sign in each loud noise area and to enforce the workers to wear noise protective devices, such as ear muffs, ear plugs, etc. before entering the loud noise workplaces.
- No piling is started. * -
Environm
ental Report (Pre-Construction Phase and C
onstruction Phase)
Nong-Saeng Pow
er Plant Project Pow
er Generation Supply C
o., Ltd. Environm
ental Audit./SEC
OT
9
SER
VER
/Env Audit Table 1 (Eng) R
ev
Table 6-1 Implementation of Environmental Mitigative Measures (Pre-Construction and Construction Phases) (Cont’d)
Environmental
Impact
Mitigative Measure Mitigative Action Result Reference
compliance noncompliance
3. Surface
Water
Hydrology
and Surface
Water Quality
Measures on Surface Water Hydrology
Construction Phase
- In the construction area, prior to making any land
preparation and construction of buildings or
structures, an earth dike of 4.5 meters high and a
drainage ditch on the outside of the dike are to be
constructed to prevent the sediment from being
washed away from the construction area and to let the
storm water from the rains in areas outside the project
site to flow and drain through freely without being
obstructed by the project area.
- The construction of drainage
ditch in the project area is started,
but the settling pond construction
is not started (waiting for the
drawings). There will be no
discharge of any run-off from the
project area until the settling
pond construction is completed
and a wastewater discharge
permit is issued.
*
- Photo 12, drainage
channels in the
project area.
- For the storm water to be pumped and drained from
the inside to the outside of the construction area, a
sump(s) must be provided for settling the sediment
(with the retention time of not less than 3 hours)
before discharging to the outside.
- The construction of drainage
ditch in the project area is started,
but the settling pond construction
is not started (waiting for the
drawings). There will be no
discharge of any run-off from the
project area until the settling
pond construction is completed
and a wastewater discharge
permit is issued.
* - Photo 12, drainage
channels in the
project area.
Environm
ental Report (Pre-Construction Phase and C
onstruction Phase)
Nong-Saeng Pow
er Plant Project Pow
er Generation Supply C
o., Ltd. Environm
ental Audit./SEC
OT
10
SER
VER
/Env Audit Table 1 (Eng) R
ev
Table 6-1 Implementation of Environmental Mitigative Measures (Pre-Construction and Construction Phases) (Cont’d)
Environmental
Impact
Mitigative Measure Mitigative Action Result Reference
compliance noncompliance
3. Surface
Water
Hydrology
and Surface
Water Quality
(Cont’d)
Measures on Surface Water Quality
Construction Phase
- The sanitary wastewater from the construction
workers must be treated to meet the effluent quality
standard, i.e. BOD value of not more than 20
milligrams per liter and the total suspended solids
concentration of not more than 30 milligrams per
liter.
- The sanitary wastewater will be
collected in septic tanks and then
transported for disposal by the
municipality (currently in the step
of coordination).
*
- Photo 13,
washrooms and
septic tanks.
- Toilets for the construction workers must not be less
than 30 meters away from the surface water resources
outside the project area. The wastewater treatment
system must be provided for treating the sanitary
wastewater to keep the quality of the treated effluent
meeting the effluent standards.
- This measure is implemented. * - Photo 13,
washrooms and
septic tanks.
- The treated effluent is used for spraying over the
construction area and the vacant areas to reduce dust
dispersion, but not discharging into Khlong Huaiba
(Khlong Nong-Ngu-Loem).
- This measure is implemented. * - Photo 2, water
spraying.
Environm
ental Report (Pre-Construction Phase and C
onstruction Phase)
Nong-Saeng Pow
er Plant Project Pow
er Generation Supply C
o., Ltd. Environm
ental Audit./SEC
OT
11
SER
VER
/Env Audit Table 1 (Eng) R
ev
Table 6-1 Implementation of Environmental Mitigative Measures (Pre-Construction and Construction Phases) (Cont’d)
Environmental
Impact
Mitigative Measure Mitigative Action Result Reference
compliance noncompliance
3. Surface
Water
Hydrology
and Surface
Water Quality
(Cont’d)
- It is a must to control and make sure that the garbage
and scraps of construction materials are not disposed
into the water resources outside the project area.
Containers must be provided for collecting the solid
wastes which are to be sanitarily disposed of. The
workers will be trained on the rules of practice.
- This measure is implemented. * - Photo 14, garbage
bins in the project
area.
- Appendix II, Work
safety regulation
documents.
4. Forestry and
Wildlife
Ecology
Measured on Forestry
Construction Phase
- To prohibit the construction workers from cutting
trees in the areas outside the construction site.
- This measure is implemented.
*
- Photo 15, tree cut
off prohibition
sign.
- After the land preparation for the construction area is
completed, it is required to plant the trees
immediately in all portions of land with no
construction activities and to designate the green
areas of the project.
- Land preparation related
activities are still ongoing, so the
project has not started to plant the
trees yet.
* -
Environm
ental Report (Pre-Construction Phase and C
onstruction Phase)
Nong-Saeng Pow
er Plant Project Pow
er Generation Supply C
o., Ltd. Environm
ental Audit./SEC
OT
12
SER
VER
/Env Audit Table 1 (Eng) R
ev
Table 6-1 Implementation of Environmental Mitigative Measures (Pre-Construction and Construction Phases) (Cont’d)
Environmental
Impact
Mitigative Measure Mitigative Action Result Reference
compliance noncompliance
4. Forestry and Wildlife Ecology (Cont’d)
Measures for Wildlife Construction Phase The construction of the project requires cutting down of big trees which are the habitats of openbills and egrets. However, these birds only nest and lay eggs during the mating/breeding season (around October through April) so there are no active bird nests on the trees during other months of the year. Therefore cutting the trees off the mating/breeding season will definitely not destruct any nests and baby birds. The implementation of the construction activities will not impose any impact on the wildlife either, and thus it will not be necessary to require any direct measures for mitigating the impact on the wildlife and the problem (if any) can be solved by only selecting the right time for the required activities. Nevertheless, the mitigation measures should be established in order to maintain the sustainable conservation of wildlife resources as follows:
- The plan for cutting all the big trees in the project area must be implemented during other months of the year instead of winter months. This will prevent the destruction of the nests and baby birds of openbills and egrets, and the parent birds will be able to find the new places for nesting and thus no impact is anticipated.
- The project does not cut off any big tree.
* - Photo 16, trees and their conditions in the project area at present.
Environm
ental Report (Pre-Construction Phase and C
onstruction Phase)
Nong-Saeng Pow
er Plant Project Pow
er Generation Supply C
o., Ltd. Environm
ental Audit./SEC
OT
13
SER
VER
/Env Audit Table 1 (Eng) R
ev
Table 6-1 Implementation of Environmental Mitigative Measures (Pre-Construction and Construction Phases) (Cont’d)
Environmental
Impact
Mitigative Measure Mitigative Action Result Reference
compliance noncompliance
4. Forestry and
Wildlife
Ecology
(Cont’d)
- Rules will be made to prohibit the workers and
personnel from hunting the wildlife or destructing the
lives of any species of wildlife in the project area and
its vicinity as well as prohibiting the outsiders to do
such wildlife hunting.
- This measure is implemented. * - Photo 17, hunting
prohibition sign.
5. Aquatic
Ecology and
Fishery
Construction Phase
- To prohibit the construction workers from fishing in
Klong Rapeepatana and Klong Huaiba (Klong Nong-
Ngu-Loem) by making rules and posting ‘No Fishing’
signs.
- This measure is implemented.
*
- Photo 18, fishing
prohibition sign.
6. Land Use Construction Phase
- To carry out the construction activities only within
the project area and to absolutely prohibit
placing/piling of equipment, machinery, materials,
etc. outside the project area.
- Areas for placing/piling the
materials of the project are within
the project premise which is
completely fenced.
*
- Photo 19, areas for
piling the materials
and machinery in
the project area.
- To clearly notify the concerned government agencies
and local residents about the areas to be used for
construction, construction boundary, and construction
schedule at least one month before the construction
activities commence.
- The project has already notified
the concerned Tambon
Administrative Organization(s)
[TAOs] and concerned
government agencies.
* - Appendix III,
Documents for
notifying the
concerned
government
agencies.
Environm
ental Report (Pre-Construction Phase and C
onstruction Phase)
Nong-Saeng Pow
er Plant Project Pow
er Generation Supply C
o., Ltd. Environm
ental Audit./SEC
OT
14
SER
VER
/Env Audit Table 1 (Eng) R
ev
Table 6-1 Implementation of Environmental Mitigative Measures (Pre-Construction and Construction Phases) (Cont’d)
Environmental
Impact
Mitigative Measure Mitigative Action Result Reference
compliance noncompliance
6. Land Use
(Cont’d)
- To do the maintenance works on the damaged traffic
surface in order to restore its original condition as per
the requirements of the concerned government
agencies.
- A permit for the traffic surface
maintenance/ improvement is
already issued by the Department
of Highways and the
maintenance/improvement work
for some areas is completed.
* - Appendix IV,
Documents for
requesting
permission to
improve traffic
surface from the
Department of
Highways.
- Photo 20, traffic
surface maintenance
work.
- To control the construction activities as per the
specified plan.
- No usage of private lands * -
In case the construction involves crossing of the private
roadway(s), additional measures are set up as follows:
- To inform the land owner(s) in advance about the
construction plan and schedule; and after the pipeline
construction in any excavated trench(s) is completed,
the soil must be put back in its original place. If such
work can not be completed within the same day,
metal sheets must be placed over each excavated
trench(s) for regular commuting.
- No usage of private lands * -
Environm
ental Report (Pre-Construction Phase and C
onstruction Phase)
Nong-Saeng Pow
er Plant Project Pow
er Generation Supply C
o., Ltd. Environm
ental Audit./SEC
OT
15
SER
VER
/Env Audit Table 1 (Eng) R
ev
Table 6-1 Implementation of Environmental Mitigative Measures (Pre-Construction and Construction Phases) (Cont’d)
Environmental
Impact
Mitigative Measure Mitigative Action Result Reference
compliance noncompliance
6. Land Use
(Cont’d)
- To string a rope around the construction area
adjacent to each of the involved roadways and to also
install the lights and to post warning signs.
- No usage of private lands * -
- To appoint a committee to oversee and control the
social related work performance, and to follow up the
construction activities, negotiate with the land
owner(s) and solve the arisen problems. The
committee has the following responsibilities:
- A committee is already appointed
to oversee and control the social
related work performance.
* - Appendix V,
Community
Participation
Committee
appointment
document.
• To inform the communities about the
complaint(s)/problem(s) by posting announcements
in the public places (not less than 3 places) within
the jurisdiction areas of the concerned Tambons.
- No complaint is filed. * -
• To inspect all evidences and may invite the experts
to jointly investigate in case of complicated
problems.
• To inform the communities about the investigation
results by posting announcements in the public
places (not less than 3 places) within the
jurisdiction areas of the concerned Tambons.
Environm
ental Report (Pre-Construction Phase and C
onstruction Phase)
Nong-Saeng Pow
er Plant Project Pow
er Generation Supply C
o., Ltd. Environm
ental Audit./SEC
OT
16
SER
VER
/Env Audit Table 1 (Eng) R
ev
Table 6-1 Implementation of Environmental Mitigative Measures (Pre-Construction and Construction Phases) (Cont’d)
Environmental
Impact
Mitigative Measure Mitigative Action Result Reference
compliance noncompliance
6. Land Use (Cont’d)
• In case the problem or complaint is caused by the project, the committee will advise the project to solve it and be liable for the resultant damages.
• In case the project is unable to solve the problem, the committee will inform the concerned government agencies, e.g., the Office of Provincial Industry, Tambon Administrative Organizations, etc.
7. Water Usage Construction Phase - Measures are established to prevent scraps of
construction materials from being washed into Klong Huaiba (Klong Nong-Ngu-Loem) which may cause difficulty in using the irrigation water.
- This measure is implemented.
*
- Photo 12, drainage
channels in the project area.
8. Transportation Construction Phase - To assign the contractor to prepare and submit a
traffic/transportation plan to the project for consideration before starting the construction activities, and to enforce the contractor to strictly follow the traffic rules.
- This measure is implemented.
*
- Appendix VI,
Documents/letters relating to the application for a permit to transport materials on the transporting route.
- To avoid transportation of materials or machinery of large size during the rush hours, i.e., 07.00-09.00 a.m. and 05.00-07.00 p.m.
- This measure is implemented. * -
Environm
ental Report (Pre-Construction Phase and C
onstruction Phase)
Nong-Saeng Pow
er Plant Project Pow
er Generation Supply C
o., Ltd. Environm
ental Audit./SEC
OT
17
SER
VER
/Env Audit Table 1 (Eng) R
ev
Table 6-1 Implementation of Environmental Mitigative Measures (Pre-Construction and Construction Phases) (Cont’d)
Environmental
Impact
Mitigative Measure Mitigative Action Result Reference
compliance noncompliance
8. Transportation
(Cont’d)
- To avoid transportation passing through the
community areas by using a detour around the
outskirts of the town or a special route between the
towns.
- This measure is implemented. * - Appendix VI,
Documents/letters
relating to the
application for a
permit to transport
materials on the
transporting route.
- To avoid transportation during heavy rains or bad
visibility.
- No vehicle running at night-time. * -
- To contact and coordinate with the highway police in
advance, i.e. before making any transportation of
materials or machinery of large size, for setting up a
transporting route, and requesting a police car to
facilitate and lead the way for such transportation.
- The project is at the stage of
contacting and coordinating with
the highway police.
* -
- To conduct the public relations in order to inform the
local communities and concerned government
agencies about the timetable, procedural steps and the
time periods of construction as well as the expectedly
increased traffic load due to the project
implementation. This must be conducted before the
construction takes place in order to welcome
comments from and exchange the ideas with the
communities and concerned government agencies
which will be beneficial for work planning.
- This mission is not yet
completely undertaken. The
preparation of public relations
signs is still underway. However,
project status/activities has been
informed to committee in the
meeting on regular basis.
* - Appendix VII,
Public relation
document.
Environm
ental Report (Pre-Construction Phase and C
onstruction Phase)
Nong-Saeng Pow
er Plant Project Pow
er Generation Supply C
o., Ltd. Environm
ental Audit./SEC
OT
18
SER
VER
/Env Audit Table 1 (Eng) R
ev
Table 6-1 Implementation of Environmental Mitigative Measures (Pre-Construction and Construction Phases) (Cont’d)
Environmental
Impact
Mitigative Measure Mitigative Action Result Reference
compliance noncompliance
8. Transportation
(Cont’d)
- To limit the driving speed, i.e., not to exceed 20
kilometers per hour within the construction area and
not to exceed 60 kilometers per hour on public roads.
- This measure is implemented. * - Photo 4, a speed
limit sign in the
project area.
- To load the trucks in accordance with the
requirements of the laws and to well cover the
transported materials in order to prevent them from
falling off onto the traffic surface which may cause
accidents.
- This measure is implemented. * - Photo 6, coverage
of loaded materials
on the truck with
canvas.
- To provide shuttle buses for the workers to commute
between their housing and the project site in order to
reduce the number of vehicles on the roads.
- This measure is implemented. * - Photo 21, a shuttle
vehicle (running
between the
residential areas
and project site)
for the construction
workers.
- To provide training on safe driving for drivers. - This measure is implemented. * - Appendix II, Work
safety regulation
documents.
- To post warning signs or signals which can be clearly
seen during the daytime and night-time, at a distance
of approximately 100 meters before approaching the
construction area. The installation of warning signs
must be completed before the construction starts.
- This measure is implemented. * - Photo 22, a
warning sign
saying
“Construction area
100 meters ahead”.
Environm
ental Report (Pre-Construction Phase and C
onstruction Phase)
Nong-Saeng Pow
er Plant Project Pow
er Generation Supply C
o., Ltd. Environm
ental Audit./SEC
OT
19
SER
VER
/Env Audit Table 1 (Eng) R
ev
Table 6-1 Implementation of Environmental Mitigative Measures (Pre-Construction and Construction Phases) (Cont’d)
Environmental
Impact
Mitigative Measure Mitigative Action Result Reference
compliance noncompliance
8. Transportation
(Cont’d)
- To provide a security guard or personnel with
responsibility for making flag signals at the entrance
and exit of the project construction area and the
construction area of the water pipeline along the
public roads.
- This measure is implemented. * - Photo 23, a traffic
control officer.
- To have a parking lot and to strictly prohibit parking
of vehicles on the shoulders of the highways.
- This measure is implemented. * - Photo 24, an
orderly parking lot.
- To install aiding equipment, e.g., metal sheets to be
laid over the trenches, temporary bridges or drainage
pipes for facilitating the safe and efficient transport of
machinery across the obstacles, etc.
- A plan is set for constructing a
temporary bridge to connect the
two (2) key construction areas
and a permit is already requested
from RID. The construction is
expected to complete in April
2011.
* - Photo 25, metal
sheets laying over
a trench for
vehicles crossing.
- Appendix VIII,
Document/letter
sent to request a
permit to build the
bridge.
- To record the statistics of accident from
transportation on the transporting routes including the
details and causes of accident for use in planning and
determining the appropriate preventive measures.
- This measure is implemented. * - Appendix IX,
Accident statistics
documents/reports.
Environm
ental Report (Pre-Construction Phase and C
onstruction Phase)
Nong-Saeng Pow
er Plant Project Pow
er Generation Supply C
o., Ltd. Environm
ental Audit./SEC
OT
20
SER
VER
/Env Audit Table 1 (Eng) R
ev
Table 6-1 Implementation of Environmental Mitigative Measures (Pre-Construction and Construction Phases) (Cont’d)
Environmental
Impact
Mitigative Measure Mitigative Action Result Reference
compliance noncompliance
8. Transportation
(Cont’d)
- To do the maintenance works on the roads that are
damaged by transportation of materials/equipment so
as to restore their original condition or better.
- This measure is implemented. * - Photo 21, traffic
surface maintenance
activity.
- Appendix IV,
Documents for
requesting
permission to
improve traffic
surface from the
Department of
Highways.
9. Drainage and
Flood Control
Construction Phase
- To construct a drainage ditch for collecting the storm
water and then start the land preparation in the dry
season, and to construct a dike around the land
preparation areas before the rainy season begins.
- The construction of drainage
ditch in the project area is started,
but the settling pond construction
is not started (waiting for the
drawings). There will be no
discharge of any run-off from the
project area until the settling
pond construction is completed
and a wastewater discharge
permit is issued.
*
- Photo 12, drainage
channels in the
project area.
Environm
ental Report (Pre-Construction Phase and C
onstruction Phase)
Nong-Saeng Pow
er Plant Project Pow
er Generation Supply C
o., Ltd. Environm
ental Audit./SEC
OT
21
SER
VER
/Env Audit Table 1 (Eng) R
ev
Table 6-1 Implementation of Environmental Mitigative Measures (Pre-Construction and Construction Phases) (Cont’d)
Environmental
Impact
Mitigative Measure Mitigative Action Result Reference
compliance noncompliance
9. Drainage and
Flood Control
(Cont’d)
- To construct 2 holding ponds and 2 storm water
sumps with a total capacity of 119,000 cubic meters
at the construction site for retaining the storm water
from the rains during the construction phase; and to
control the pumping of the discharged water into
Klong Huaiba (Klong Nong-Ngu-Loem) by observing
the water level at the discharge point. If it is found
that the water level of the canal is lower than 3.5
meters (5.5 meters msl.), the project will discharge
the water; but if the water level gets close to 3.63
meters (5.63 meters msl.), the project must stop
discharging the water.
- At present, the project is using an
existing sump in the area as the
temporary settling pond.
*
- Photo 26, the
temporary settling
pond.
10. Solid Wastes Construction Phase
- To request the contractor to classify the solid wastes
by types, to provide appropriate and adequate number
of containers for each type and install the containers
at various points within the construction area, and to
dispose of these wastes according to the Notification
of the Ministry of Industry, entitled “Disposal of
Garbages or Unwanted Materials”, 2005.
- Bins for the classified garbage/
rubbish are provided and the
project is coordinating with a
local government agency to
dispose of these wastes.
*
- Photo 14, garbage
bins in the project
area.
Environm
ental Report (Pre-Construction Phase and C
onstruction Phase)
Nong-Saeng Pow
er Plant Project Pow
er Generation Supply C
o., Ltd. Environm
ental Audit./SEC
OT
22
SER
VER
/Env Audit Table 1 (Eng) R
ev
Table 6-1 Implementation of Environmental Mitigative Measures (Pre-Construction and Construction Phases) (Cont’d)
Environmental
Impact
Mitigative Measure Mitigative Action Result Reference
compliance noncompliance
10. Solid Wastes (Cont’d)
- To contract the local agency for collecting the garbage everyday to avoid overfilling.
- The project is coordinating with a local government agency to disposal of these wastes.
*
- To manage each type of solid wastes anticipated to be generated during the construction phase which include scrap materials from soil excavation (e.g., scraps of soil, sand, brick, etc.), scraps of construction materials (e.g., fractions of structures or used or unwanted materials, etc.), hazardous wastes (e.g., batteries, motor oil, hydraulic oil, filters, mineral oil, cleaning agents or used solvents) as well as enamel products or rejected paints and general garbages of approximately 5,100 kilograms per day. The project will provide a specific area for storing each type of garbage or solid wastes, and appropriate containers for classifying each type of solid wastes in order to facilitate the disposal according to the Notification of the Ministry of Industry, entitled “Disposal of Garbage or Unwanted Materials”, 2005.
- Only general wastes are generated at present (no other types of wastes).
* - Photo 14, a garbage bin in the project area.
- To prohibit burning of garbage or leaves within the construction area.
- This measure is implemented. * - Photo 9, burning prohibition sign.
Environm
ental Report (Pre-Construction Phase and C
onstruction Phase)
Nong-Saeng Pow
er Plant Project Pow
er Generation Supply C
o., Ltd. Environm
ental Audit./SEC
OT
23
SER
VER
/Env Audit Table 1 (Eng) R
ev
Table 6-1 Implementation of Environmental Mitigative Measures (Pre-Construction and Construction Phases) (Cont’d)
Environmental
Impact
Mitigative Measure Mitigative Action Result Reference
compliance noncompliance
11. Occupational
Health and
Safety
Construction Phase
Occupational Health and Safety Management
- The project in conjunction with the contractor of the
project construction will appoint a committee and
personnel for safety, occupational health and working
environment with responsibility to establish policy
and work guidelines. The safety manual is to be
prepared 1 month before the commencement of
construction works and distributed to every
employee. In addition, training on construction safety
will be arranged for all levels of personnel and
relevant knowledge provided to every employee
working for this project. These activities will be
performed in order to educate every employee with
basic knowledge and awareness of work safety.
- Due to the number of workers of
the project are only 40 at present
which implies that it is not the
time to meet the requirement on
the appointment of committee.
However, the project has already
assigned a safety officer (i.e.
Khun Anucha) with the duty to
control/oversee the occupational
health/safety and working
environment.
- An orientation meeting on the
safety and work-related
rules/regulations has been
arranged for the workers before
starting to work.
- The safety manual is at the stage
of preparation.
*
-
Environm
ental Report (Pre-Construction Phase and C
onstruction Phase)
Nong-Saeng Pow
er Plant Project Pow
er Generation Supply C
o., Ltd. Environm
ental Audit./SEC
OT
24
SER
VER
/Env Audit Table 1 (Eng) R
ev
Table 6-1 Implementation of Environmental Mitigative Measures (Pre-Construction and Construction Phases) (Cont’d)
Environmental
Impact
Mitigative Measure Mitigative Action Result Reference
compliance noncompliance
11. Occupational
Health and
Safety
(Cont’d)
- The procurement of safety equipment including
safety glasses, safety masks, safety gloves, safety
shoes, safety ropes, respirators for toxic gases, noise
protection devices, and showers/eye washers in case
of direct contact with chemicals is to be managed
along with training on the use of the equipment and
how to work safely (e.g. the use of slings, pulleys and
chains for lifting, storage and inspection methods of
lifting equipment/machinery, etc.), climbing up the
high altitude, and precautions against falling off.
- This measure is implemented. * - Appendix II, Work
safety regulation
documents.
- Photo 27, a safety
warning sign.
- Photo 28, an
employee wearing
the PPE.
The employees working in the confined areas must be
trained as required by the laws (e.g. on the application
of gas detectors when entering the confined areas, use
of ventilating fans in these areas, having lookout
persons in front of the entrance of the confined areas,
etc.; and also on the erection of working stands,
driving in the project area, application of
communication instruments, proper chemical
loading/unloading methods, etc.).
- The employees working on occupational health/
safety and working environment shall be trained by
the Safety Officer including the specified courses and
duration, and awarded with a training certificate.
- Currently at the stage of starting
to set training plans
* -
Environm
ental Report (Pre-Construction Phase and C
onstruction Phase)
Nong-Saeng Pow
er Plant Project Pow
er Generation Supply C
o., Ltd. Environm
ental Audit./SEC
OT
25
SER
VER
/Env Audit Table 1 (Eng) R
ev
Table 6-1 Implementation of Environmental Mitigative Measures (Pre-Construction and Construction Phases) (Cont’d)
Environmental
Impact
Mitigative Measure Mitigative Action Result Reference
compliance noncompliance
11. Occupational
Health and
Safety
(Cont’d)
- All employees shall be trained on safety before
working.
- This measure is implemented. * - Appendix II, Work
safety regulation
documents.
- The working section of occupational health/safety
and working environment will have a joint meeting
for planning relating to the construction works,
summarizing the problems and making suggestions
for the work performance before starting the work
every morning. Details and statistics are to be
recorded such as accident statistics with its causes,
severity and damage, including corrective measures.
- This measure is under the process
of the Occupational Health/Safety
and Working Environment
Committee, but it is not the time
to appoint the committee yet.
* -
- Inspection of safety equipment shall be conducted at
least once a month.
- Setting up of safety system is just
started and expected to complete
at the end of April 2011.
* -
- Arrangement for the meeting of the Occupational
Health/Safety and Working Environment committee
at least once a month in order to evaluate and
recommend for problem correction
- Setting up of safety system is just
started and expected to complete
at the end of April 2011.
* -
Environm
ental Report (Pre-Construction Phase and C
onstruction Phase)
Nong-Saeng Pow
er Plant Project Pow
er Generation Supply C
o., Ltd. Environm
ental Audit./SEC
OT
26
SER
VER
/Env Audit Table 1 (Eng) R
ev
Table 6-1 Implementation of Environmental Mitigative Measures (Pre-Construction and Construction Phases) (Cont’d)
Environmental
Impact
Mitigative Measure Mitigative Action Result Reference
compliance noncompliance
11. Occupational
Health and
Safety
(Cont’d)
- Promotion of activities on occupational health/safety
and working environment.
- Announcements on occupational
health/ safety and working
environment are made to inform
the employees.
* - Photo 29, a sign of
announcement on
safety rules and
regulations.
- Appendix II, Work
safety regulation
documents.
- Posting warning signs with the word “No Entry for
Unconcerned People” in dangerous areas and
specifying construction zones.
- It was implemented. * - Photo 30, a sign
with the word
“Project area, no
entry”.
- Provision of adequate drinking water along with
sanitary facilities such as clean toilets for employees.
- Washrooms and toilets are
prepared for the construction
workers.
* - Photo 6,
washrooms and
septic tanks.
- Photo 31, the
provision of
adequate clean
water for the
employees.
Environm
ental Report (Pre-Construction Phase and C
onstruction Phase)
Nong-Saeng Pow
er Plant Project Pow
er Generation Supply C
o., Ltd. Environm
ental Audit./SEC
OT
27
SER
VER
/Env Audit Table 1 (Eng) R
ev
Table 6-1 Implementation of Environmental Mitigative Measures (Pre-Construction and Construction Phases) (Cont’d)
Environmental
Impact
Mitigative Measure Mitigative Action Result Reference
compliance noncompliance
11. Occupational
Health and
Safety
- Provision of medical supplies and first-aid equipment
in case employees are injured and must be sent to
hospital.
- This measure is implemented. * -
(Cont’d) - Provision of assigned knowledgeable personnel with
responsibility for safety.
- This item is still under the
process of preparing the
documents to notify the
concerned government agencies.
* -
- Storage of instruments and equipment in an orderly
manner with routine inspection to ensure that they are
in good condition.
- This measure is implemented. * - Photo 32, piles of
materials/
equipment
arranged in an
orderly manner
within the project
area.
- Incorporating the mitigative measures into the
construction contract.
- The construction contract is made
by incorporating the regulations
on the mitigative measures.
* -
Environm
ental Report (Pre-Construction Phase and C
onstruction Phase)
Nong-Saeng Pow
er Plant Project Pow
er Generation Supply C
o., Ltd. Environm
ental Audit./SEC
OT
28
SER
VER
/Env Audit Table 1 (Eng) R
ev
Table 6-1 Implementation of Environmental Mitigative Measures (Pre-Construction and Construction Phases) (Cont’d)
Environmental
Impact
Mitigative Measure Mitigative Action Result Reference
compliance noncompliance
11. Occupational Health and Safety (Cont’d)
Fire Prevention and Fire-Fighting System - The prime contractor must provide fire extinguishers
in a sufficient number for use by the employees working in the hazardous areas or in areas of intense heat and fire risk, such as metal welding. Each welding crew must have a fire extinguisher (dry powder) located in their workplace. For metal welding in any elevated area, the space beneath the working area must be covered with insulating materials in order to keep the sparks, resulting from the welding, from falling onto the lower area which may be unsafe for those working in such an area.
- The placement of fire
extinguishers is at the stage of selecting the mounting points.
*
-
- The prime contractor must prepare a coordinating plan with the local fire authority in order to get ready in case of emergency.
- This measure is implemented. * - Appendix X, Documents used for coordinating with the fire-fighting agency.
- Control of the entrance and exit of the construction-induced hazardous areas and their associated traffic, and also posting hazard warning signs that are clearly visible to the Foreman or Safety Officer.
- This measure is implemented. * - Photo 23, a traffic control personnel.
- Photo 22, a warning sign saying “Construction area 100 meters ahead”.
Environm
ental Report (Pre-Construction Phase and C
onstruction Phase)
Nong-Saeng Pow
er Plant Project Pow
er Generation Supply C
o., Ltd. Environm
ental Audit./SEC
OT
29
SER
VER
/Env Audit Table 1 (Eng) R
ev
Table 6-1 Implementation of Environmental Mitigative Measures (Pre-Construction and Construction Phases) (Cont’d)
Environmental
Impact
Mitigative Measure Mitigative Action Result Reference
compliance noncompliance
11. Occupational
Health and
Safety
- Preparation of fire-fighting equipment suitable for the
area conditions and types of work along with the
specified safe work procedure.
- The placement of fire
extinguishers is at the stage of
selecting the mounting points.
* -
(Cont’d) - Inspection of working condition and equipment used
in the construction, particularly at the locations
subject to hazards or a fire risk.
- The project is still at the stage of
selecting the points for mounting
or installing the equipment.
* -
- Routine inspection of fire extinguishers at least every
week.
- The project is still at the stage of
selecting the points for mounting
or installing the equipment.
* -
12. Socio-
economics
Construction Phase
- Urgent corrective actions on information
dissemination without any hidden and distorted
agenda to all groups of stakeholders must be
performed.
- This measure is implemented.
*
- Appendix VII,
Public relation
document.
- Actions on listening to public opinion under the
people participation process by emphasizing a two-
way communication must be conducted for the
project acceptance by the communities in the project
and surrounding areas. Making understanding to lead
to good wills in the future must be managed in the
form of good cooperation and participation of the
local people. All actions must be open for the
communities to express their opinions and
- The project is still at the stage of
setting up a plan.
* -
Environm
ental Report (Pre-Construction Phase and C
onstruction Phase)
Nong-Saeng Pow
er Plant Project Pow
er Generation Supply C
o., Ltd. Environm
ental Audit./SEC
OT
30
SER
VER
/Env Audit Table 1 (Eng) R
ev
Table 6-1 Implementation of Environmental Mitigative Measures (Pre-Construction and Construction Phases) (Cont’d)
Environmental
Impact
Mitigative Measure Mitigative Action Result Reference
compliance noncompliance
12. Socio-
economics
(Cont’d)
suggestions to support the preparation of the
guidelines to prevent problems to the project owner,
local people and government sectors; and actions
must be conducted in the form of setting up a
community participation committee. These activities
will lead to good development and also avoid people
with a bad intention to disturb the peace.
- Actions on the project public relations before the
beginning of construction by distributing documents
and visiting community leaders and the local people.
The planned actions may use several media to make
the targeted groups receive correct and quick
information. This will prevent the consequent
problems. During the construction period, placards
about the project progress must be posted in the
public places or in front of the project site.
- This measure is implemented. * - Appendix VII,
Public relation
document.
- Consideration on the priority of local worker
recruitment (to create extra careers and incomes for
the communities) will lead to a good relationship
between the project and the communities. The
planned actions must be done according to the
suitability and capacity of the local workers.
- Local workers were already
recruited.
* -
Environm
ental Report (Pre-Construction Phase and C
onstruction Phase)
Nong-Saeng Pow
er Plant Project Pow
er Generation Supply C
o., Ltd. Environm
ental Audit./SEC
OT
31
SER
VER
/Env Audit Table 1 (Eng) R
ev
Table 6-1 Implementation of Environmental Mitigative Measures (Pre-Construction and Construction Phases) (Cont’d)
Environmental
Impact
Mitigative Measure Mitigative Action Result Reference
compliance noncompliance
12. Socio- economics (Cont’d)
- Actions on the control, fostering and confirming the subcontractors to seriously prevent the migrant and local workers from quarreling among themselves and/or with the people in the local communities.
- This measure is implemented. * - Appendix II, Work safety regulation documents.
- Actions to control the construction activities to avoid disturbing the local people in the area and to rigorously and strictly apply the environmental measures for safety and accident prevention from the project construction.
- This measure is implemented. * - Appendix II, Work safety regulation documents.
- Setting up the public relations and coordination unit for explaining, making understanding during the constructing period, and receiving complaints from the people who are in trouble due to the construction
- A community coordination center is already established (the phone number is 081-704-5513).
- The project notifies the information to the communities via the quarterly reports which are distributed through mailing (starting from February 28, 2011). The communities receiving the information include twelve Tambon in Nong-Saeng District and Nong-Khae District of Saraburi Province, and Pachee District of Phra Nakorn Si Ayuthya.
* - Photo 33, the community coordination center.
- Photo 34, public relation document.
- Appendix VII,
Public relations
documents.
Environm
ental Report (Pre-Construction Phase and C
onstruction Phase)
Nong-Saeng Pow
er Plant Project Pow
er Generation Supply C
o., Ltd. Environm
ental Audit./SEC
OT
32
SER
VER
/Env Audit Table 1 (Eng) R
ev
Table 6-1 Implementation of Environmental Mitigative Measures (Pre-Construction and Construction Phases) (Cont’d)
Environmental
Impact
Mitigative Measure Mitigative Action Result Reference
compliance noncompliance
12. Socio-
economics
(Cont’d)
- To inform through the public
relations about the community
coordination center and the
project construction schedule via
the radio wave “Power plant for
the communiities” at 107.25
MHZ on Monday through Friday
at 10.00-12.00 am.
- Photo 35, the
community
coordination center
and the project
construction
schedule
announced via the
radio wave.
13. Public
Relations
and Public
Participation
Public relations plan for making understanding
during the pre-construction/site preparation periods
A power plant is a large scale industry the construction
of which takes a long time and may cause impacts or
anxieties to the communities starting from site
preparation period. The Power Generation Supply Co.,
Ltd. has prepared a public relations plan for making
understanding to the local communities starting from
the beginning of the site preparation for the power plant
construction. In order to make the local communities
relaxed from anxiety and confident about the project
implementation, the public relations activities should be
done as follows:
Environm
ental Report (Pre-Construction Phase and C
onstruction Phase)
Nong-Saeng Pow
er Plant Project Pow
er Generation Supply C
o., Ltd. Environm
ental Audit./SEC
OT
33
SER
VER
/Env Audit Table 1 (Eng) R
ev
Table 6-1 Implementation of Environmental Mitigative Measures (Pre-Construction and Construction Phases) (Cont’d)
Environmental
Impact
Mitigative Measure Mitigative Action Result Reference
compliance noncompliance
13. Public
Relation and
Public
Participation
(Cont’d)
- Making the project public relations placards,
communication channels and showing the
responsibility for the case of problems/impacts
resulting from the project-related activities. This will
make the people living in the area close to the power
plant relaxed from anxiety about the pollution
problems, accidents and health impacts.
- A community coordination center
is already established (the phone
number is 081-704-5513).
* - Photo 33, the community coordination center.
-
- Setting up a community coordination center or a call
center (temporary) of the Power Generation Supply
Co., Ltd. for receiving complaints from the
communities in order to make them confident that the
Company is responsible for any impacts caused by
the project subcontractors.
- A community coordination center
is already established (the phone
number is 081-704-5513).
- The project notifies the
information to the communities
via the quarterly reports which
are distributed through mailing
(starting from February 28,
2011). The communities
receiving the information include
twelve Tambon in Nong-Saeng
District and Nong-Khae District
of Saraburi Province, and Pachee
District in Phra Nakorn Si
Ayuthya.
* - Photo 33, the
community
coordination center
- Photo 34, public relation document.
- Appendix VII, Public relations documents.
Environm
ental Report (Pre-Construction Phase and C
onstruction Phase)
Nong-Saeng Pow
er Plant Project Pow
er Generation Supply C
o., Ltd. Environm
ental Audit./SEC
OT
34
SER
VER
/Env Audit Table 1 (Eng) R
ev
Table 6-1 Implementation of Environmental Mitigative Measures (Pre-Construction and Construction Phases) (Cont’d)
Environmental
Impact
Mitigative Measure Mitigative Action Result Reference
compliance noncompliance
13. Public
Relation and
Public
Participation
(Cont’d)
- To inform through the public
relations about the community
coordination center and the
project construction schedule via
the radio wave “Power plant for
the communiities” at 107.25
MHZ on Monday through Friday
at 10.00-12.00 am.
- Photo 35, the
community
coordination center
and the project
construction
schedule
announced via the
radio wave.
- Setting up a committee on public participation for
inspecting the implementation of environmental
measures during the construction phase. This will
encourage the communities to participate in watching
and inspecting the implementation of the mitigative
measures as well as the environmental development
in the communities. The project should support to
appoint a committee on public participation by
cooperating with the communities. The functions of
the committee should include the following:
• To share the ideas and suggestions for the
implementation of all environmental action plans of
the Nong-Saeng Power Plant Project.
• To participate in inspecting the implementation of
the environmental action plans.
- The Community Participation
Committee is already appointed.
* - Appendix V, Community Participation Committee appointment document.
Environm
ental Report (Pre-Construction Phase and C
onstruction Phase)
Nong-Saeng Pow
er Plant Project Pow
er Generation Supply C
o., Ltd. Environm
ental Audit./SEC
OT
35
SER
VER
/Env Audit Table 1 (Eng) R
ev
Table 6-1 Implementation of Environmental Mitigative Measures (Pre-Construction and Construction Phases) (Cont’d)
Environmental
Impact
Mitigative Measure Mitigative Action Result Reference
compliance noncompliance
13. Public Relations and Public Participation (Cont’d)
• To appoint a working team for inspecting the environmental quality aspect of concern.
• To receive the complaints on environmental problems (if any) from the communities and to analyze the problems according to the process of complaint receiving and solving given in the action plan on socio-economics.
-
Construction Phase - To conduct the proactive public relations consisting
of a news/information dissemination process that will increase more learning about the project in a more perspective way. The public relations program should be carried out via all local media. The public relations in depth should be performed to make understanding to the individuals directly by having meetings or seminars on the following issues:
- The project is at the stage of
preparing the plan.
*
-
• Progress of the project operation. • Technical information about the power plant
operation, particularly how safe the security measures or the methods are including the methods that the Power Generation Supply Co., Ltd. has prepared to cope with the problems, obstacles and accidents during the construction period of the project.
Environm
ental Report (Pre-Construction Phase and C
onstruction Phase)
Nong-Saeng Pow
er Plant Project Pow
er Generation Supply C
o., Ltd. Environm
ental Audit./SEC
OT
36
SER
VER
/Env Audit Table 1 (Eng) R
ev
Table 6-1 Implementation of Environmental Mitigative Measures (Pre-Construction and Construction Phases) (Cont’d)
Environmental
Impact
Mitigative Measure Mitigative Action Result Reference
compliance noncompliance
13. Public Relations and Public Participation (Cont’d)
• Promotion of the green area, for example planting the trees in the public places of communities to compensate the power plant area. This will make a good attitude towards Power Generation Supply Co., Ltd. and the Company to consider and respond to the true needs of the communities.
-
- To produce public relation media, such as leaflets, hand bill and video, etc., containing the details of the power plant and pollution prevention systems which are easy to understand. This will create a positive image of the Power Generation Supply Co., Ltd.
- The project notifies the information to the communities via the quarterly reports which are distributed through mailing (starting from February 28, 2011). The communities receiving the information include twelve Tambon in Nong-Saeng District and Nong-Khae District of Saraburi Province, and Pachee District in Phra Nakorn Si Ayuthya.
- To inform through the public relations about the community coordination center and the project construction schedule via the radio wave “Power plant for the communiities” at 107.25 MHZ on Monday through Friday at 10.00-12.00 am.
* - Photo 33, the
community
coordination center
- Photo 34, public relation document.
- Photo 35, the community coordination center and the project construction schedule announced via the radio wave.
- Appendix VII, Public relations documents.
Environm
ental Report (Pre-Construction Phase and C
onstruction Phase)
Nong-Saeng Pow
er Plant Project Pow
er Generation Supply C
o., Ltd. Environm
ental Audit./SEC
OT
37
SER
VER
/Env Audit Table 1 (Eng) R
ev
Table 6-1 Implementation of Environmental Mitigative Measures (Pre-Construction and Construction Phases) (Cont’d)
Environmental
Impact
Mitigative Measure Mitigative Action Result Reference
compliance noncompliance
13. Public Relations and Public Participation (Cont’d)
- To coordinate and organize the meetings with the
important government agencies or organizations in
the area such as the local government offices or the
occupational groups in order to inform the results of
the mitigative actions conducted by the Power
Generation Supply Co., Ltd.
- The project is at the stage of
preparing the plan.
* -
Compensation Plan for the Occupation Groups
Nong-Saeng Power Plant Project has set the
compensation measures for various occupation groups
(if they are imposed by the impacts of the project)
which are classified as follows:
- Meat Chicken–Egg Chicken Farming
• Chicken farms in a 1-km radius around the site of
power plant
Construction Phase: Nong-Saeng Power Plant
Project will make an agreement with the locals
who raise chicken for a living so as to insure
against the project-induced impacts i.e. to accept
to take responsibility to compensate for the loss
of benefit and to pay compensation for the
chicken farming if the chicken farmers intend to
not raise the chicks during the start of the power
plant construction. This is to prevent the chicks
- The compensation is in process. *
Environm
ental Report (Pre-Construction Phase and C
onstruction Phase)
Nong-Saeng Pow
er Plant Project Pow
er Generation Supply C
o., Ltd. Environm
ental Audit./SEC
OT
38
SER
VER
/Env Audit Table 1 (Eng) R
ev
Table 6-1 Implementation of Environmental Mitigative Measures (Pre-Construction and Construction Phases) (Cont’d)
Environmental
Impact
Mitigative Measure Mitigative Action Result Reference
compliance noncompliance
13. Public Relations and Public Participation (Cont’d)
from getting startled from the construction-induced nuisance noises. However, the farmers will be allowed to raise the chicks after the construction has already started so that the growing chicks can get used to the environmental conditions relating to nuisance noises and will not get startled by the construction-related noises. But if there is any impact induced, the project will be willing to take responsibility for paying the compensation for the investment cost as well as the anticipated lost profit from the farming, loss of benefit, and fines to be paid to the other party to the farming contract.
- Rice Farming • Rice farming: if the paddy fields in the project area
are adversely affected by the lights from the project, the project will pay the compensation for any damage.
• The project will consider allocating a 10-rai land parcel for conducting a demonstration paddy field.
• For the case of rice farm renters who used to rent a land parcel(s) for rice farming, the Nong-Saeng Power Plant Project will allow them to continue their rice farming in such land parcel(s) without charge.
- The compensation is in process. *
Environm
ental Report (Pre-Construction Phase and C
onstruction Phase)
Nong-Saeng Pow
er Plant Project Pow
er Generation Supply C
o., Ltd. Environm
ental Audit./SEC
OT
39
SER
VER
/Env Audit Table 1 (Eng) R
ev
Table 6-1 Implementation of Environmental Mitigative Measures (Pre-Construction and Construction Phases) (Cont’d)
Environmental
Impact
Mitigative Measure Mitigative Action Result Reference
compliance noncompliance
13. Public Relations and Public Participation (Cont’d)
• The project will notify the rice farm renters one season in advance before starting the cultivation (about 4 months before the construction starts) so as to consider assisting them as much as possible in each season.
• The project will pay the compensation to the rice farm renters who rent the land parcel(s) in the project area including the cost of dismantling for their houses built in the project area.
• If any of the rice farm renters wishes the project to find an alternative occupation for him, the project will do as requested by finding a job in the power plant for him on a one-job-per-family basis.
- The compensation is in process. *
- Mushroom Farming • In case the productivity of mushroom cultivation
is adversely affected by the use of effluent discharged from the Nong-Saeng Power Plant Project, the project will be willing to pay the compensation for any drop in mushroom productivity at a fair market price to the affected farmers.
• If such an impact occurs, the Nong-Saeng Power Plant Project will find the other water source(s) for them such as drilling a deep well or laying a water pipeline from a nearby water source or installing a filtering system.
- The compensation is in process. *
Environmental Auditing Report (Pre-Construction Phase and Construction Phase) Nong Saeng Power Plant Project
Power Generation Supply Co., Ltd
Environmental Audit/SECOT 40 SERVER/Env Audit Pic
Ban Nong-Tangbun
Ban Khok Daeng
Ban Tamsinthusopa
Ban Nong-Ngu-Loem
Photo 1 air quality monitoring station during March 4-12, 2011
Environmental Auditing Report (Pre-Construction Phase and Construction Phase) Nong Saeng Power Plant Project
Power Generation Supply Co., Ltd
Environmental Audit/SECOT 41 SERVER/Env Audit Pic
Photo 2 water spraying
Photo 3 rubbish was kept in place
Photo 4 speed limit sign in the project area
Environmental Auditing Report (Pre-Construction Phase and Construction Phase) Nong Saeng Power Plant Project
Power Generation Supply Co., Ltd
Environmental Audit/SECOT 42 SERVER/Env Audit Pic
Photo 5 speed limit sign by the public road
Photo 6 coverage of trucked materials with canvas
Photo 7 public road surface washing
Environmental Auditing Report (Pre-Construction Phase and Construction Phase) Nong Saeng Power Plant Project
Power Generation Supply Co., Ltd
Environmental Audit/SECOT 43 SERVER/Env Audit Pic
Photo 8 wheel washing stations
Photo 9 showing “No burning of rubbish” sign
Photo 10 zinc panels installed around the project area
Environmental Auditing Report (Pre-Construction Phase and Construction Phase) Nong Saeng Power Plant Project
Power Generation Supply Co., Ltd
Environmental Audit/SECOT 44 SERVER/Env Audit Pic
Photo 11 equipment/machinery are turned off when not in use
Photo 12 drainage channels in the project area
Photo 13 washrooms and septic tanks
septic tanks
Environmental Auditing Report (Pre-Construction Phase and Construction Phase) Nong Saeng Power Plant Project
Power Generation Supply Co., Ltd
Environmental Audit/SECOT 45 SERVER/Env Audit Pic
Photo 14 garbage bins in the project area
Photo 15 tree cut off prohibition sign
Photo 16 the trees and their condition in the project area at present
Environmental Auditing Report (Pre-Construction Phase and Construction Phase) Nong Saeng Power Plant Project
Power Generation Supply Co., Ltd
Environmental Audit/SECOT 46 SERVER/Env Audit Pic
Photo 17 hunting prohibition sign
Photo 18 fishing prohibition sign
Photo 19 the areas for piling the materials and machinery in the project area
Environmental Auditing Report (Pre-Construction Phase and Construction Phase) Nong Saeng Power Plant Project
Power Generation Supply Co., Ltd
Environmental Audit/SECOT 47 SERVER/Env Audit Pic
Photo 20 the traffic surface maintenance work
Photo 21 a shuttle bus (running between the residential areas and project site) for the construction workers
Photo 22 a warning sign saying “Construction area 100 meters ahead”
Environmental Auditing Report (Pre-Construction Phase and Construction Phase) Nong Saeng Power Plant Project
Power Generation Supply Co., Ltd
Environmental Audit/SECOT 48 SERVER/Env Audit Pic
Photo 23 a traffic control officer
Photo 24 an orderly parking lot
Photo 25 metal sheets laying over a trench for vehicles crossing
Environmental Auditing Report (Pre-Construction Phase and Construction Phase) Nong Saeng Power Plant Project
Power Generation Supply Co., Ltd
Environmental Audit/SECOT 49 SERVER/Env Audit Pic
Photo 26 the temporary settling pond
Photo 27 a safety warning sign
Photo 28 an employee wearing the PPE
Environmental Auditing Report (Pre-Construction Phase and Construction Phase) Nong Saeng Power Plant Project
Power Generation Supply Co., Ltd
Environmental Audit/SECOT 50 SERVER/Env Audit Pic
Photo 29 a sign of announcement on safety rules and regulations
Photo 30 a sign with the word “Project area, no entry”
Photo 31 the provision of adequate clean water for the employees
Environmental Auditing Report (Pre-Construction Phase and Construction Phase) Nong Saeng Power Plant Project
Power Generation Supply Co., Ltd
Environmental Audit/SECOT 51 SERVER/Env Audit Pic
Photo 32 piles of materials/equipment arranged
in an orderly manner within the project area.
Photo 33 the community coordination center
Environmental Auditing Report (Pre-Construction Phase and Construction Phase) Nong Saeng Power Plant Project
Power Generation Supply Co., Ltd
Environmental Audit/SECOT 52 SERVER/Env Audit Pic
Photo 34 public relation document
Photo 35 the community coordination center and the project construction schedule
announced via the radio wave
Mar 4-5, 2010 0.138 0.119 0.156 0.165
Mar 5-6, 2011 0.146 0.132 0.248 -
Mar 6-7, 2011 0.098 0.097 0.137 0.298
Mar 7-8, 2011 0.096 0.100 0.166 0.124
Mar 8-9, 2011 0.061 0.051 0.070 0.094
Mar 9-10, 2011 0.078 0.066 0.082 0.162
Mar 10-11, 2011 0.104 0.096 0.146 0.144
Mar 11-12, 2011 - - - 0.171
Table 1
Monitoring Results of TSP Concentration in Ambient Air
Power Generation Supply Co., Ltd.
during March 4-12, 2011
Nong-Saeng Power Plant Project
Ban Nong-TangbunDate
Standard* 0 330
24-hr Average Concentration (mg/m3)
Ban TamsinthusopaBan Nong-Ngu-LoemBan Khok Daeng
Remark : *Notification of National Environment Board, No.24 (B.E.2547).
Standard* 0.330
T-MTR210058/SECOT SEVER/MTR211058_Amb (Mar)/24/5/2011
Mar 4-5, 2010 0.110 0.093 0.126 0.087
Mar 5-6, 2011 0.100 0.097 0.167 -
Mar 6-7, 2011 0.067 0.069 0.085 0.113
Mar 7-8, 2011 0.058 0.062 0.078 0.052
Mar 8-9, 2011 0.040 0.035 0.048 0.037
Mar 9-10, 2011 0.050 0.046 0.055 0.094
Mar 10-11, 2011 0.076 0.072 0.094 0.085
Mar 11-12, 2011 - - - 0.085
Standard* 0 120
24-hr Average Concentration (mg/m3)
Ban TamsinthusopaBan Nong-Ngu-LoemBan Khok DaengBan Nong-TangbunDate
Table 2
Monitoring Results of PM-10 Concentration in Ambient Air
Power Generation Supply Co., Ltd.
during March 4-12, 2011
Nong-Saeng Power Plant Project
Remark : *Notification of National Environment Board, No.24 (B.E.2547).
Standard* 0.120
T-MTR210058/SECOT SEVER/MTR211058_Amb (Mar)/24/5/2011
Date
Min. Max Min. Max Min. Max Min. Max
Mar 4-5, 2010 2.1 31.7 6.8 17.1 2.9 20.0 2.3 12.5
Mar 5-6, 2011 3.6 20.5 6.2 25.6 6.1 25.0 3.2 20.8
Mar 6-7, 2011 6.4 18.2 4.7 16.6 5.5 26.1 3.8 17.6
Mar 7-8, 2011 4.8 18.8 4.6 20.9 6.3 18.1 2.9 18.2
Mar 8-9, 2011 4.7 18.4 2.3 15.7 5.8 18.3 3.1 18.4
Mar 9-10, 2011 5.1 16.5 3.7 31.5 6.0 15.6 1.7 10.6
Mar 10-11, 2011 7.4 30.0 3.5 21.5 7.9 27.2 2.8 20.7
Standard*
Remark : *Notification of National Environment Board, No.28 (B.E.2550).
Table 3
Monitoring Results of 1-hr average concentration of Nitrogen dioxide in Ambient Air Quality
Nong-Saeng Power Plant Project
Power Generation Supply Co., Ltd.
during March 4-12, 2011
1-hr Average Concentration (ppb)
170
Ban Nong-Tangbun Ban Khok Daeng Ban Nong-Ngu-Loem Ban Tamsinthusopa
T-MTR211058/SECOT SERVER/MTR211058_Amb (Mar)/NO2-1 hr/24/5/2011
Date
Min. Max Min. Max Min. Max Min. Max
Mar 4-5, 2010 2.7 17.6 2.6 10.9 1.5 8.1 1.2 9.8
Mar 5-6, 2011 3.9 12.9 3.1 6.5 7.1 9.2 1.7 15.8
Mar 6-7, 2011 4.2 17.3 5.5 7.2 4.5 9.8 1.8 9.1
Mar 7-8, 2011 3.9 6.7 6.4 7.7 5.3 6.1 1.1 8.4
Mar 8-9, 2011 3.0 7.1 2.3 7.4 5.7 6.6 1.0 12.5
Mar 9-10, 2011 1.8 8.3 0 6.8 6.0 6.7 1.3 12.5
Mar 10-11, 2011 2.0 10.6 4.4 7.2 4.5 7.4 2.3 15.7
Standard*
Remark : *Notification of National Environment Board, No.21 (B.E.2544).
1-hr Average Concentration (ppb)
Table 4
Monitoring Results of 1-hr average concentration of Sulfur Dioxide in Ambient Air Quality
Nong-Saeng Power Plant Project
Power Generation Supply Co., Ltd.
during March 4-12, 2011
300
Ban Nong-Tangbun Ban Khok Daeng Ban Nong-Ngu-Loem Ban Tamsinthusopa
T-MTR211058/SECOT SERVER/MTR211058_Amb (Mar)/SO2 (1 hr)/24/5/2011
Mar 4-5, 2010
Mar 5-6, 2011
Mar 6-7, 2011
Mar 7-8, 2011
Mar 8-9, 2011
Mar 9-10, 2011
Mar 10-11, 2011
Standard*
Remark : *Notification of National Environment Board, No.24 (B.E.2547).
5.9 5.6 8.5 6.5
Table 5
Monitoring Results of 24-hr average concentration of Sulfur Dioxide in Ambient Air Quality
Nong-Saeng Power Plant Project
Power Generation Supply Co., Ltd.
during March 4-12, 2011
Date24-hr Average Concentration (ppb)
Ban Nong-Tangbun Ban Khok Daeng Ban Nong-Ngu-Loem Ban Tamsinthusopa
6.6 6.0 4.8 5.6
6.2 6.4 6.1 4.1
5.0 6.9 5.7 4.0
4.4 5.1 6.0 8.7
4.6 5.2 6.3 6.3
6.0 6.6 6.8 7.6
120
T-MTR211058/SECOT SERVER/MTR211058_Amb (Mar)/SO2 (24 hr)/24/5/2011
T-MON208020-SECOT SERVER/Envi Audit-App.
Appendix III
Documents for notifying the concerned
government agencies
T-MON208020-SECOT SERVER/Envi Audit-App.
Appendix IV
Documents for requesting permission to improve
traffic surface from the Department of Highways
T-MON208020-SECOT SERVER/Envi Audit-App.
Appendix V
Community Participation Committee
appointment document
T-MON208020-SECOT SERVER/Envi Audit-App.
Appendix VI
Documents/letters relating to the application for a permit
to transport materials on the transporting route
T-MON208020-SECOT SERVER/Envi Audit-App.
Appendix VIII
Document/letter sent to request a permit
to build the bridge
Nong Saeng Power Plant Project
WEEKLY SAFETY REPORT (12/3/11 - 18/3/11) Date 18/3/11
1 Safety manpower report
Last Acc 12/3/11 13/3/11 14/3/11 15/3/11 16/3/11 17/3/11 18/3/11 Total Acc.
- 185 204 196 197 199 198 200 1,379
- 1,834 2,029 1,942 1,991 2,009 1,969 1,991 13,765
2 Accident report
3 Tool Box talk
POSITION
12/3/2011 Safety Office
13/3/2011 Supervisor
14/3/2011 Electric Engineer
15/3/2011 Supervisor
16/3/2011 Foreman
17/3/2011 Safety Office
18/3/2011 Civil Engineer
4 Safety Activities
123 Dust prevention from clearing work by spraying water456789
5 Other
N/A
0
This week
0
0
0
0
0
0
Last Accumulative
0
0
0
Clean public road after workingUse coversheet to protect dust out of the truck
Tool box talk to be conducted everyday workInstall safety sign board
Install waring lighting
0
0
Use temporary fence surround construction site
This Week Accumulative
0
0
0
0
0
0
Inspection heavy machineUse proper PPE during work and Traffic Control
-Stop work over 3 day
-Stop work not exceed 3 day
- Non Stop work
Manday
Manhour
DESCRIPTION
-Dead
-Disable
-Lost organ
Mr. Sompong
Mr. Arrom
Mr. Samaen
PERFORMED BY
Mr. Anucha
DATE DESCRIPTIONNAME
Mr. Sompong
Sino-Thai Engineering & Construction Public Co.,Ltd.
Mr.Chokchai
Use proper PPE during work and Traffic Control
Clean public road after working
Panelboard has the ground connection
Clean public road after working
Finish fencing work today
Speed limit control
Prepare drainage system in site
Mr. Anucha
9
T-MON208020-SECOT SERVER/Envi Audit-App.
Appendix X
Documents used for coordinating with
the fire-fighting agency
035-311-112 อ.ภาช 035-311-163 อ.ภาช 035-311-021 (199) อ.ภาช
035-311-955 (Pachee) (Pachee) (Pachee)
036-399-199 อ.หนองแซง 036-399-229 อ.หนองแซง 036-399-199 (199) อ.หนองแซง
(Nong-Saeng) (Nong-Saeng) (Nong-Saeng)
(กรณอบตเหต)
เบอรโทรศพทฉกเฉน (Emergency Telephone Numders)
Emergency Flow Chart
อบตเหต/ฉกเฉนผเหนเหตการณผปฎบตงาน
(Accident / Fire Alarm)
ผควบคมงาน
เจาหนาทความปลอดภยในการท างาน(Safety Officer)
082-823-7649
ผบาดเจบ
(Injurie)
รนแรง
(Seruous)
โรงพยาบาล
(Hospital)
สอบสวนอบตเหต
(Accident Investigate)
รายงาน
(Reporting)
ผบรหารโครงการ
(Emergency Manager)
089-500-2293
เจาของงาน(Project Manager)
(Consultant)
(081-170-0103)
หยดงาน
(Stop work)
อพยพไปจดรวมพล(Evacuate to Assembly Point)
ผควบคมงานตรวจสอบรายชอ(Foreman a roll Call All Worker)
คนหา
รอรบฟงค าสง(Stanby For Instruction)
กลบสสภาวะปกตเขาปฎบตงาน
(All Clare)
โรงพยาบาล
(Hospital)สถานต ารวจ
(Pollice Station)
สถานดบเพลง
(Fire Station)
Emission Rate Calculation Nong-Saeng Power Plant Project
The electricity generating process of Nong-Saeng Power Plant Project will emit three (3) primary air pollutants (i.e. oxides of nitrogen [NOx], sulfur dioxide [SO2] and particulate matters [PM]) through four (4) HRSG stacks. The air emission rates of Nong-Saeng Power Plant are summarized as follows:
(1) Oxides of nitrogen (NOx): under normal fuel combustion condition,
oxides of nitrogen will be formed by the reaction between nitrogen in the air and
oxygen at about 1,200 degrees Celsius. Therefore the project has selected to use the
dry low NOx combustion system designed with a lower operating combustion
temperature to reduce NOx emissions. The project is now under the process of
selecting the required gas turbines for which the bidders must propose the associated
NOx emissions of 70 ppm and 120 ppm at 7% excess O2 when using natural gas and
diesel oil as fuels respectively.
(2) Sulfur dioxide (SO2): the air pollutant that is formed by the
combustion of sulfur containing fuels, particularly coal and oil. However, the project
has proposed to use natural gas as the main fuel for electricity generating. The natural
gas to be obtained from PTT is required to have low sulfur content i.e. with hydrogen
sulfide content of 50 parts per million (ppm). When combusted, the required
hydrogen sulfide content in natural gas is estimated to form about 3 ppmvd of SO2
emission at 7% excess O2. As a safety factor, the project has proposed the SO2
emissions of 10 ppmvd at 7% excess O2 in case there is a fluctuation in the property
of the supplied natural gas and 30 ppmvd at 7% excess O2 when firing diesel oil. The
proposed SO2 emissions are still lower than Thailand’s Standards (not to exceed 20
ppm and 320 ppm at 7% excess O2respectively).
(3) Particulate matters (PM): PM is formed by the combustion of fuel. In most cases, PM is from the input air to the combustion process of gas turbines. The use of new and clean air filters can substantially reduce PM emissions but not all of the PM under actual conditions. Normally, PM emission rates also vary according to ambient dust concentrations in the area. However, the project has proposed to use a double-layered filtering system to filter the input air before it is fed into the
III-1
combustion system. Therefore the project has set the PM control values of 20
mg/Nm3 and 35 mg/Nm3 @ 7% excess O2 when using natural gas and diesel oil as
fuels respectively. These proposed control values are lower than Thailand’s Standards
(not to exceed 60 and 120 mg/Nm3 @ 7% excess O2 respectively).
The details of emission rate calculation method are as follows:
(1) Full Load Operation (100% Load) - Natural Gas Firing
The designed stack gas flow rate is 697.06 Nm3/sec @ 15% excess O2
or = 697.06 (20.9-15) @ 7% excess O2
(20.9-7) = 295.8 Nm3/sec @ 7% excess O2
Oxides of Nitrogen The required concentration of oxides of nitrogen is 70 ppm @ 7%
excess O2
Hence the emission rate of oxides of nitrogen is equal to = 70 x 46 x 295.8
24.45 x 1,000
= 38.93 g/s
Therefore the emission rate of oxides of nitrogen is 38.93 g/s/stack
Sulfur Dioxide
The required concentration of sulfur dioxide is 10 ppm @ 7% excess O2
Hence the emission rate of sulfur dioxide is equal to = 10 x 46 x 295.8
24.45 x 1,000 = 7.74 g/s
Therefore the emission rate of sulfur dioxide is 7.74 g/s/stack
Particulate Matters (PM)
The required concentration of PM is 20 mg/Nm3 @ 7% excess O2
Hence the PM emission rate is equal to
= 20 x 295.8
1,000 = 5.92 g/s
Therefore the PM emission rate is 5.92 g/s/stack
III-2
- Diesel Oil Firing The designed stack gas flow rate is 672.29 Nm3/sec @ 15% excess O2
or = 672.29 (20.9-15) @ 7% excess O2
(20.9-7) = 285.36 Nm3/sec @ 7% excess O2
Oxides of Nitrogen The required concentration of oxides of nitrogen is 120 ppm @ 7%
excess O2
Hence the emission rate of oxides of nitrogen is equal to = 120 x 46 x 285.36
24.45 x 1,000
= 64.37g/s
Therefore the emission rate of oxides of nitrogen is 64.37 g/s/stack
Sulfur Dioxide
The required concentration of sulfur dioxide is 30 ppm @ 7% excess O2
Hence the emission rate of sulfur dioxide is equal to = 30 x 46 x 285.36
24.45 x 1,000 = 22.41 g/s
Therefore the emission rate of sulfur dioxide is 22.41 g/s/stack
Particulate Matters (PM)
The required concentration of PM is 35 mg/Nm3 @ 7% excess O2
Hence the PM emission rate is equal to
= 35 x 285.36
1,000
= 9.99 g/s Therefore the PM emission rate is 9.99 g/s/stack
(2) 80% Load Operation
- Natural Gas Firing The designed stack gas flow rate is 570.62 Nm3/sec @ 15% excess O2
or = 570.62 (20.9-15) @ 7% excess O2
(20.9-7)
III-3
Oxides of Nitrogen The required concentration of oxides of nitrogen is 70 ppm @ 7%
excess O2 Hence the emission rate of oxides of nitrogen is equal to
= 70 x 46 x 242.2
24.45 x 1,000 = 31.87 g/s
Therefore the emission rate of oxides of nitrogen is 31.87 g/s/stack
Sulfur Dioxide
The required concentration of sulfur dioxide is 10 ppm @ 7% excess O2
Hence the emission rate of sulfur dioxide is equal to = 10 x 46 x 242.2
24.45 x 1,000
= 6.34 g/s Therefore the emission rate of sulfur dioxide is 6.34 g/s/stack
Particulate Matters (PM)
The required concentration of PM is 20 mg/Nm3 @ 7% excess O2
Hence the PM emission rate is equal to
= 20 x 242.2
1,000
= 4.84 g/s Therefore the PM emission rate is 4.84 g/s/stack
- Diesel Oil Firing The designed stack gas flow rate is 563.39 Nm3/sec @ 15% excess O2
or = 563.39 (20.9-15) @ 7% excess O2
(20.9-7) = 239.1 Nm3/sec @ 7% excess O2
Oxides of Nitrogen The required concentration of oxides of nitrogen is 120 ppm @ 7%
excess O2 Hence the emission rate of oxides of nitrogen is equal to
= 120 x 46 x 239.1
24.45 x 1,000
III-4
= 53.94 g/s Therefore the emission rate of oxides of nitrogen is 53.94 g/s/stack
Sulfur Dioxide
The required concentration of sulfur dioxide is 30 ppm @ 7% excess O2
Hence the emission rate of sulfur dioxide is equal to = 30 x 46 x 239.1
24.45 x 1,000 = 18.78 g/s
Therefore the emission rate of sulfur dioxide is 18.78 g/s/stack
Particulate Matters (PM)
The required concentration of PM is 35 mg/Nm3 @ 7% excess O2
Hence the PM emission rate is equal to
= 35 x 239.1
1,000 = 8.37 g/s
Therefore the PM emission rate is 8.37 g/s/stack (3) 58% Load Operation
- Natural Gas Firing The designed stack gas flow rate is 442.84 Nm3/sec @ 15% excess O2
or = 442.84 (20.9-15) @ 7% excess O2
(20.9-7) = 187.9 Nm3/sec @ 7% excess O2
Oxides of Nitrogen The required concentration of oxides of nitrogen is 70 ppm @ 7%
excess O2
Hence the emission rate of oxides of nitrogen is equal to = 70 x 46 x 187.9
24.45 x 1,000
= 24.74 g/s
Therefore the emission rate of oxides of nitrogen is 24.74 g/s/stack
Sulfur Dioxide
The required concentration of sulfur dioxide is 10 ppm @ 7% excess O2
III-5
Hence the emission rate of sulfur dioxide is equal to = 10 x 46 x 187.9
24.45 x 1,000 = 4.92 g/s
Therefore the emission rate of sulfur dioxide is 4.92 g/s/stack
Particulate Matters (PM)
The required concentration of PM is 20 mg/Nm3 @ 7% excess O2
Hence the PM emission rate is equal to
= 20 x 187.9
1,000
= 3.76 g/s Therefore the PM emission rate is 3.76 g/s/stack
- Diesel Oil Firing The designed stack gas flow rate is 491.0 Nm3/sec @ 15% excess O2
or = 491.0 (20.9-15) @ 7% excess O2
(20.9-7) = 208.4 Nm3/sec @ 7% excess O2
Oxides of Nitrogen
The required concentration of oxides of nitrogen is 120 ppm @ 7% excess O2
Hence the emission rate of oxides of nitrogen is equal to = 120 x 46 x 208.4
24.45 x 1,000
= 47.01 g/s Therefore the emission rate of oxides of nitrogen is 47.01 g/s/stack
Sulfur Dioxide
The required concentration of sulfur dioxide is 30 ppm @ 7% excess O2
Hence the emission rate of sulfur dioxide is equal to = 30 x 46 x 208.4
24.45 x 1,000
= 16.36 g/s
Therefore the emission rate of sulfur dioxide is 16.36 g/s/stack
III-6
Particulate Matters (PM) The required concentration of PM is 35 mg/Nm3 @ 7% excess O2
Hence the PM emission rate is equal to
= 35 x 208.4
1,000 = 7.29 g/s
Therefore the PM emission rate is 7.29 g/s/stack
III-7
Natural Gas Pipeline to Nong Saeng Power Plant Project Gulf JP NS Co., Ltd. Executive Summary
ENTIC Co., Ltd. 1
ENVIRONMENTAL IMPACT ASSESSMENT
NATURAL GAS PIPELINE TO NONG SAENG POWER PLANT PROJECT
GULF JP NS CO., LTD.
The Gulf JP NS Co., Ltd., has a project to construct Nong Saeng Power Plant (NSPP),
which is a combined cycle power plant (CCPP). The project is for supporting the present increase of
electricity demand and reinforcing the country energy security. The NSPP has capacity of 1,653 MW
and uses natural gas as a main fuel. Thus the company has a plan to lay natural gas pipeline (NGP) to
the NSPP with a diameter of 30 inches. The NGP will be joined to the 36-inch Wang Noi-Khang Khoi
NGP system of the Petroleum Authority of Thailand Public Company Limited (PTT) at the area of
KP11+255 of the existing NGP in Kum Hak Subdistrict (Tambol) of Nong Khae District in Saraburi. The
project NGP will be ended at the metering and regulating station (MRS) of the NSPP. Total length of
the project NGP is 19.3 kilometers coverings areas in 7 subdistricts, 3 municipalities in 2 Districts of
Saraburi. The areas crossed by the NGP include Kum Hak Subdistrict, Phai Tam Tambol Municipality
(TM), Nong Khae TM, Nong Khai Nam Subdistrict, Nong Pla Mo Subdistrict, Nong Pling Subdistrict,
Khotchasit Subdistrict, Khotchasit TM and Khok Tum Subdistrict in Nong Khae District and Nong Kop in
Nong Saeng District of Saraburi.
The Gulf JP NS Co., Ltd., has assigned the Entic Co., Ltd., to conduct a study and
prepare environmental impact assessment (EIA) report of the project. Because the project nature is
corresponding to type and size of the projects enforced by Enhancement and Conservation of National
Environmental Quality, B.E. 2535 to perform EIA and present to the relevant approval office. EIA
conduction is also corresponding to the condition in the proposal for independent power producer
(IPP) selection by Ministry of Energy. The Gulf JP NS Co., Ltd., is responsible from the study through
preparation of EIA report for approval, construction of the project NGP, practice along measures for
prevention and mitigation of environmental impacts in both construction and operation periods. In the
case that the Gulf JP NS Co., Ltd., transfers the NGP system to PTT after construction completion,
PTT will work along the environment working plan in the operation period after PTT get the right of
the NGP system.
Natural Gas Pipeline to Nong Saeng Power Plant Project Gulf JP NS Co., Ltd. Executive Summary
ENTIC Co., Ltd. 2
1. Type and size of the project
The Natural Gas Pipeline to Nong Saeng Power Plant Project of Gulf JP NS Co., Ltd., employs pipeline with a diameter of 30 inches. It is connected to the 36-inch Wang Noi-Khang Khoi NGP system of PTT and ends at Nong Saeng Power Plant in Nong Saeng District of Saraburi. It is the project of petroleum transportation by pipeline. According to the Enhancement and Conservation of National Environmental Quality, B.E. 2535 and the attachment of the Notification of Natural Resources and Environment Ministry, B.E. 2552, this project is the Project No. 3 “Projects to transport the Petroleum and Fuel Oil by Pipe”. All sizes of this project type are required to conduct EIA and prepare a report for submission in the step of licensing application or in the step of approval from relevant offices. Thus the Gulf JP NS Co. Ltd., has assigned the Entic Co., Ltd., to prepare the EIA report for submission to the Office of Natural Resources and Environmental Policy and Planning (ONEP) and authorized approval offices to approve the project before construction.
2. Project location
The Natural Gas Pipeline to Nong Saeng Power Plant Project of Gulf JP NS Co., Ltd., locates on 2 areas of Nong Khae and Nong Saeng Districts of Saraburi as shown in Fig. 2-1.
3. Project operation method
3.1 NGP route selection
Criteria for NGP route selection are considered from;
(1) Avoid crossing community area/place as much as possible
(2) Use governmental areas mainly in order to reduce impact on people areas
(3) Avoid historical area or areas with archeological places or antiques
(4) Avoid conservation areas according to laws or cabinet approval, for example, preserved forest, watershed classification area, etc.
(5) Be crossing river, canal, highway and local road as small number as possible
(6) Be able to extend the NGP system to customers easily
(7) Have shortest distance and engineering feasible
(8) Be able to access the area conveniently and quickly
ENTIC Co., Ltd. 3
Natural Gas Pipeline to Nong Saeng Power Plant Project Gulf JP NS Co., Ltd. Executive Summary
Fig. 2-1 Location of the Natural Gas Pipeline to Nong Saeng Power Plant Project
Natural Gas Pipeline to Nong Saeng Power Plant Project Gulf JP NS Co., Ltd. Executive Summary
ENTIC Co., Ltd. 4
Consideration of the areas to be the project’s NGP route by reviewing of secondary data
and field surveying, it is found that the Wang Noi-Khang Khoi NGP (the main NGP) has potential to
deliver enough natural gas to Nong Saeng Power Plant. There are 2 choices of routes, which are
suitable and corresponding to route selection criteria, as shown in Fig. 3.1-1.
(1) Route choice 1: This NGP route is divided into 2 sections;
Section 1: The project starting point-Liap Klong Rapeepat Road
The project NGP with a diameter of 30 inches is tied in with the 36-inch
Wang Noi-Kang Khoi NGP system of PTT at KP 11+255 of the Wang Noi-Kang Khoi NGP system.
The pipe joining point is the right of way (ROW) of high voltage transmission line. The pipeline is then
laid in the ROW of Kum Hak TAO Road until it reaches the intersection of Liap Klong Soi 9 Kwa Road.
The pipeline is bended to the east ROW of Liap Klong Soi 9 Kwa Road until it reaches Highway No. 1-
new route (Paholyothin Road). The pipeline is then crossed under Highway No. 1-new route to the
opposite side, which is in front of tyre manufacturing plant of Thai Bridgestone Co., Ltd. The pipeline is
laid along the west ROW of Highway No. 1-new route (outbound from Bangkok to Saraburi) until it
reaches the junction of Highway No. 1-old route and –new route. In this area, the pipeline is crossed
under Highway No. 1-old route and laid in the east of Highway No. 1-old route. When it reaches the
area in front of Wat Sahamitr Mongkol, it is crossed under Highway No. 1-old route and Klong
Rapeepat. The pipeline is laid in the ROW of East Liap Klong Rapeepat Road (on the left side of
Klong Rapeepat) because there are 2 natural gas pipelines of PTT in the West Liap Klong
Rapeepat Road whose ROW has no enough space for laying another pipeline. The total length of
this section is 4.6 kilometers.
Section 2: Liap Klong Rapeepat Road-the project end point
The whole pipeline in this section is laid in the ROW of Liap Klong Rapeepat
Road. When the Section 1 pipeline reaches the ROW of the East Liap Klong Rapeepat Road, its
extension is laid along this road until it reaches the metering and regulating station (MRS) in the
area of Nong Saeng Power Plant. Total length of NGP in this section is 14.7 kilometers.
ENTIC Co., Ltd. 5
Natural Gas Pipeline to Nong Saeng Power Plant Project Gulf JP NS Co., Ltd. Executive Summary
Fig 3.1-1 Choices for NGP routes of the Natural Gas Pipeline to Nong Saeng
Power Plant Project
Natural Gas Pipeline to Nong Saeng Power Plant Project Gulf JP NS Co., Ltd. Executive Summary
ENTIC Co., Ltd. 6
(2) Route choice 2: In this choice the whole pipeline is laid in the ROW of Liap Klong Rapeepat Road. It starts from the area of the gas control station WK#1 of the Wang Noi-Khang Khoi NGP. This station is located next to the East Liap Klong Rapeepat Road. The pipeline is laid in the ROW of the East Liap Klong Rapeepat Road (on the left side of Klong Rapeepat). It is then crossed under Highway No. 1-new route and –old route. The first part of the route choice 2 is 4.9 kilometer long. The second part of this route choice is the same as the section 2 of the route choice 1. In this part, the pipeline is laid in the ROW of the East Liap Klong Rapeepat Road for 14.7 kilometers until it reaches the MRS of Nong Saeng Power Plant. Environment conditions in 500-meter peripheries from the axis of NGP route choices are shown in Table 3.1-1
Table 3.1-1 Summary of general data of the route choices in 500-meter peripheries from the NGP route
Natural Gas Pipeline to Nong Saeng Power Plant Factor Route choice 1 Route choice 2
1. Construction Most areas can be excavated by Open Cut. Special construction techniques are needed to cross 7 obstructions, such as: 1. Highway No. 1 (Paholyothin
Road)-new route 2. Highway No. 1 (Paholyothin
Road)-old route 3. Liap Klong Rapeepat Road 4. Klong Rapeepat Road 5. Klong Baan Khok 6. Highway No. 33 7. Klong Huayba
Most areas can be excavated by Open Cut. Special construction techniques are needed to cross 14 obstructions, such as: 1. Liap Klong Rapeepat Road 2. Klong Rapeepat 3. Klong Nong Khae 4. Setha Samphan Road 5. Setha Bamroong Road 6. Tesabaan 5 Road 7. Nong Khae District Office 8. Nong Khae Police Station 9. Sophon Thamma Pracha Road 10. Highway No. 1-new route 11. Highway No. 1-old route 12. Klong Baan Khok 13. Highway No. 33 14. Klong Huayba
2. Approximated length
About 19.3 kilometers About 19.6 Kilometers
3. Number of community areas crossed by NGP route
Crossing the community area of Khotchasit TM
15.Crossing Nong Khae District Office, Nong Khae Police Station, Community in Nong Khae TM, fresh-food market and community area of Khotchasit
Natural Gas Pipeline to Nong Saeng Power Plant Project Gulf JP NS Co., Ltd. Executive Summary
ENTIC Co., Ltd. 7
Table 3.1-1 (continued) Factor Route choice 1 Route choice 2
4. Maximum usage of governmental areas
Most areas along the NGP route belong to governmental sectors and local organizations, such as Department of Highways (DOH), Royal Irrigation Department (RID) and TAO
All the areas along the NGP route belong to the governmental sector, namely RID.
5. Number of water source crossing
Crossing 3 water sources, such as Klong Rapeepat, Klong Baan Khok and Klong Huayba
Crossing 4 water sources, such as Klong Rapeepat, Klong Nong Khae, Klong Baan Khok and Klong Huayba
6. Number of highway or local road crossing
Crossing 11 highways or local roads; 1. Highway No. 1 (Paholyothin Road)-
new route 2. Highway No. 1 (Paholyothin Road)-
old route, crossing twice 3. Gateway to Wat Rat Satthatham 4. Liap Klong Rapeepat Road 5. Gateway to SIL Industrial Estate 6. Gateway to Wat Thung Din Kho 7. Gateway to Baan Kratong Loy
Group 4, KP 11+877 8. Gateway to Baan Kratong Loy
Group 4, KP 12+000 9. Highway No. 33 10. Gateway to Khotchasit TM
community in the Akathosarot Watergate office area
11. Liap Klong Huayba Road
Crossing 15 highways or local roads; 1. Sophon Thamma Pracha Road 2. Tesabaan 5 Road 3. Gateway to Baan Hua Sakhae 4. Setha Samphan Road 5. Setha Bamroong Road 6. Junction of Liap Klong Rapeepat Road
with Tesabaan 1 Road 7. Junction of Highway No. 1 (Paholyothin
Road)-new route with Klong Rapeepat Embankment Road
8. Liap Klong Rapeepat Road 9. Gateway to SIL Industrial Estate 10. Gateway to Wat Thung Din Kho 11. Gateway to Baan Kratong Loy Group 4,
KP 11+877 12. Gateway to Baan Kratong Loy Group 4,
KP 12+000 13. Highway No. 33 14. Gateway to Khotchasit TM community in
the Akathosarot Watergate office area 15. Liap Klong Huayba Road
7. Sensitive areas to impacts in 500-meter peripheries from the NGP axis
21 places, such as; 1. Wat Suan Kluay 2. War Suan Kluay School 3. Sahamitr Mongkol School 4. Wat Sahamitr Mongkol 5. Nong Khae Provincial Water Works
Authority (PWA) 6. Luang Por Samrej Saksit
29 places, such as; 1. Wat Sena Naruemitr School 2. Wat Sena Naruemitr 3. Wang Noi Power Plant water pump
station 4. Tesabaan 4 Sena Anusorn School 5. Klan Wittaya School 6. Rim Klong Rapeepat Market
Natural Gas Pipeline to Nong Saeng Power Plant Project Gulf JP NS Co., Ltd. Executive Summary
ENTIC Co., Ltd. 8
Table 3.1-1 (continued) Factor Route choice 1 Route choice 2
7. Sensitive areas to impacts in 500-meter peripheries from the NGP axis (continued)
7. Wat Chaiyasit Anusorn 8. Wat Chaiyasit Anusorn School 9. Wat Kratong Loy 10. Khotchasit Community Tesabaan
Market 11. Rapeepat Ruamjai Community 12. Khotchasit TM Office 13. Wat Santi Wihan 14. Khok Tum TAO Office 15. Wat Santi Wihan School 16. Khok Tum Subdistrict Public Health
Station 17. Wat Khok Daeng 18. Wat Thammasin Sopha School 19. Wat Thammasin Sopha 20. Nong Kop Subdistrict Public Health
Station 21. Royal Irrigation Office
7. Nong Khae District Police Station 8. Nong Khae TM 9. Nong Khae Governmental Office 10. Construction project of Royal Irrigation
Office 2 11. Sahamitr Mongkol School 12. Wat Sahamitr Mongkol 13. Nong Khae Provincial Water Works
Authority (PWA) 14. Luang Por Samrej Saksit 15. Wat Chaiyasit Anusorn 16. Wat Chaiyasit Anusorn School 17. Wat Kratong Loy 18. Khotchasit Community Tesabaan
Market 19. Rapeepat Ruamjai Community 20. Khotchasit TM Office 21. Wat Santi Wihan 22. Khok Tum TAO Office 23. Wat Santi Wihan School 24. Khok Tum Subdistrict Public Health
Station 25. Wat Khok Daeng 26. Wat Thammasin Sopha School 27. Wat Thammasin Sopha 28. Nong Kop Subdistrict Public Health
Station 29. Royal Irrigation Office
Natural Gas Pipeline to Nong Saeng Power Plant Project Gulf JP NS Co., Ltd. Executive Summary
ENTIC Co., Ltd. 9
3.2 NGP route section result
By comparison of impacts to be occurred in 2 route choices and by giving scores to
each route choice as shown in Table 3.2-1, it is found that the route choice 1 has total suitability
scores higher than that of the route choice 2. The route choice 1 not only has higher suitability
scores but it also causes less number of impacts as it crosses less amounts of road, water source
and sensitive area. Thus, it is suitable to be the route for laying NGP of the Natural Gas Pipeline to
Nong Saeng Power Plant Project.
3.3 The project NGP route
The project NGP is planned to be laid in the north ROW of RID Road to the junction
with Liap Kong Soi 9 Kwa Road. After that the pipeline is laid in the ROW of Liap Kong Soi 9 Kwa
Road until it reaches the junction between Liap Kong Soi 9 Kwa Road and Highway No. 1
(Paholyothin Road). The pipeline is then laid in the ROW of Highway No. 1 and crossed under to
the opposite side in the area in front of the plant of Thai Bridgestone Co., Ltd., which is located at
the Km. 81+740 of Highway No.1 (outbound from Bangkok-Saraburi). Then the pipeline is laid in
the ROW of Highway No.1 (outbound from Bangkok-Saraburi) until it reaches the junction between
Highway No. 1-old route and –new route. The pipeline is bended along the ROW of Highway No.
1-old route before being crossed under to the east ROW of the road. When the pipeline reaches
the junction between Highway No. 1-old route and Klong Rapeepat (the area in front of Wat
Sahamitr Mongkol) it is crossed under Highway No. 1-old route, Klong Rapeepat and Liap Klong
Rapeepat Roads (referred to the direction heading to Nong Saeng Power Plant). The pipeline is laid
in the ROW of Liap Klong Rapeepat Road on the canal left side (because there are 2 pipelines of
PTT and no enough space in the ROW of Liap Klong Rapeepat Road on the canal right side). The
pipeline is laid in the east ROW of Liap Klong Rapeepat Road on the canal left side until it reaches the
MRS of Nong Saeng Power Plant. Total project NGP is about 19.3 kilometers as shown in Fig. 3.3-1.
The studied area covers the peripheries of 500 meter from the pipeline axis. The area crosses 7
subdistricts, 3 municipalities in 2 districts of Saraburi as shown in Table 3.3-1.
ENTIC Co, Ltd.
10
Natural Gas Pipeline to Nong Saeng Power Plant Project
Gulf JP NS Co., Ltd. Executive Summary
Table 3.2-1 Consideration on weight and prioritization for route selection of Natural Gas Pipeline to Nong Saeng Power Plant
Criteria Priority
weight
Route 1 Suitability
level Score
Route 2 Suitability
level Score
Details Details
1. Engineering
1.1 Construction technique
2 Most areas can use Open Cut method, except the areas with big barriers and/or requiring impact reduction employ special construction techniques, such as HDD and Boring. Special areas include 7 places; 1. HW#1 (new route) using Boring and HDD 2. HW#1 (old route), crossing twice, using Boring 3. Liap Klong Rapeepat Road and Klong
Rapeepat using HDD 4. Crossing Khotchasit Community using HDD 5. Klong Baan Khok using HDD 6. HW# 33 using HDD 7. Klong Huayba and Liap Klong Huayba
Road using HDD
2 4 Most areas can use Open Cut method, except the areas with big barriers and/or requiring impact reduction employ special techniques. Special areas include 7 places; 1. Liap Klong Rapeepat Road and
Klong Rapeepat using HDD 2. Klong Nong Khae using Boring 3. Setthasamphan Road using Boring 4. Setthabamroong Raid using Boring 5. Tesabaan 5 Road using Boring 6. Nong Khae District Office using
HDD 7. Nong Khae Police Station using
HDD 8. Sophon Thammapracha Road using Boring 9. HW#1-new route using HDD 10. HW#1-old route using HDD
1 2
ENTIC Co, Ltd.
11
Natural Gas Pipeline to Nong Saeng Power Plant Project
Gulf JP NS Co., Ltd. Executive Summary
Table 3.2-1 (continued)
Criteria Priority
weight
Route 1 Suitability
level Score
Route 2 Suitability
level Score
Details Details
11. Khotchasit Community using HDD 12. Klong Baan Khok using HDD 13. HW# 33 using HDD 14. Klong Huayba and Liap Klong
Huayba using HDD
2. Economy or investment 2.1 Pipeline
length 2 about 19.3 km. 3 6 about 19 .6 km. 3 6
3. Economy-society 3.1 Crossed Communities number
3 1. Community areas in Khotchasit Subdistrict 2 6 1. Communities in Nong Khae TM and fresh food market area
2. Community areas in Khotchasit Subdistrict
1 3
3.2 ROW usage
3 Use most areas belonging to government and local administration organizations
2 6 Use all areas belonging to government 3 9
4. Environment 4.1 Crossing
point number withhighways olocal roads
3 Crossing 3 water sources including 1. Klong Rapeepat 2. Klong Baan Khok 3. Klong Huayba
3
9
Crossing 3 water sources including 1. Klong Nong Khae 2. Klong Rapeepat 3. Klong Baan Khok 4. Klong Huayba
2 6
ENTIC Co, Ltd.
12
Natural Gas Pipeline to Nong Saeng Power Plant Project
Gulf JP NS Co., Ltd. Executive Summary
Table 3.2-1 (continued)
Criteria Priority
weight
Route 1 Suitability
level Score
Route 2 Suitability
level Score
Details Details
4.2 Crossing point number with highways or local roads
2 Crossing 11 highways/local roads/gateways including 1. HW#1 (Paholyothin Road) new route 2. HW#1 (Paholyothin Road) old route
crossing twice 3. Gateway to Wat Rat Satthatham 4. Liap Klong Rapeepat Road 5. Gateway to SIL industrial estate 6. Gateway to Wat Toongdinkhaw 7. Gateway to Baan Kratong Loy, Group 4,
KP 11+877 8. Gateway to Baan Kratong Loy, Group 4,
KP 12+000 9. HW#33 10. Gateway to Kotchasit Municipality
Community near Akathosarot Watergate 11. Liap Klong Huayba Road
2 4 Crossing 15 highways/local roads/gateways including 1. Thammasophon Pracha Road 2. Tesabaan 5 Road 3. Gateway to Baan Hua Sakhae 4. Setthasamphan Road 5. Setthabamroong Road 6. Junction of Liap Klong Rapeepat Road
and Tesabaan 1 Road 7. HW#1 (Paholyothin Road)-new route
crossing with Klong Rapeepat Dike Road
8. Liap Klong Rapeepat Road 9. Gateway to SIL industrial estate 10. Gateway to Wat Toongdinkhaw 11. Gateway to Baan Kratong Loy, Group
4, KP 11+877 12. Gateway to Baan Kratong Loy, Group
4, KP 12+000 13. HW#33 14. Gateway to Kotchasit Municipality
Community near Akathosarot Watergate
15. Liap Klong Huayba Road
1 2
ENTIC Co, Ltd.
13
Natural Gas Pipeline to Nong Saeng Power Plant Project
Gulf JP NS Co., Ltd. Executive Summary
Table 3.2-1 (continued)
Criteria Priority
weight
Route 1 Suitability
level Score
Route 2 Suitability
level Score
Details Details
4.3 Impact sensitive areas
3 There are 21 areas including 1. Wat Suan Kluay 2. Wat Sahamitr Mongkol 3. Sahamitr Mongkol School 4. Luang Por Samrej Saksit 5. Nong Khae PWA office 6. Wat Suan Kluay School 7. Wat Chaiyasit Anusorn 8. Wat Chaiyasit Anusorn School 9. Wat Kratong Loy 10. Tesabaan Market of Kotchasit Community 11. Rapeepat Ruamjai Community 12. Khok Tum Public Health Center 13. Wat Santi Wihan 14. Wat Santi Wihan School 15. Wat Khok Daeng 16. Khok Tum TAO 17. Wat Thammasin Sopha 18. Wat Thammasin Sopha School
2 6 There are 21 areas including 1. Wat Sahamitr Mongkol 2. Wat Sena Naruemitr 3. Wat Sena Naruemitr School 4. Klan Wittaya School 5. Tesabaan 4 Sena Anusorn School 6. Sahamitr Mongkol School 7. Luang Por Samrej Saksit 8. Nong Khae Governmental Office Center 9. Rim Klong Rapeepat Market 10. Nong Khae District Police Station 11. Construction Project of RID Office 12. Nong Khae TM Office 13. Wang Noi Power Pant’s Water Pump Station 14. Nong Khae PWA Office 15. Wat Chaiyasit Anusorn 16. Wat Chaiyasit Anusorn School 17. Wat Kratong Loy 18. Tesabaan Market of Kotchasit Community
1
3
ENTIC Co, Ltd.
14
Natural Gas Pipeline to Nong Saeng Power Plant Project
Gulf JP NS Co., Ltd. Executive Summary
Table 3.2-1 (continued)
Criteria Priority
weight
Route 1 Suitability
level Score
Route 2 Suitability
level Score
Details Detials 19. Nong Kop Public Health Center
20. Kotchasit TM Office 21. RID Office
19. Rapeepat Ruamjai Community 20. Khok Tum Public Health Center 21. Wat Santi Wihan 22. Wat Santi Wihan School 23. Wat Khok Daeng 24. Khok Tum TAO 25. Wat Thammasin Sopha 26. Wat Thammasin Sopha School 27. Nong Kop Public Health Center 28. Kotchasit TM Office 29. RID Office
5. Safety 5.1 Emergency Area access convenience
3 There are roads for access the whole NGP route conveniently.
2 6 There are roads for access the whole NGP route conveniently.
2 6
Total score of Route 1 47 Total score of Route 2 37 Note: Priority from low to high, divided into 3 levels as flows;
1. Low priority weight equals to 1 1. Low suitability equals to 1 2. Medium priority weight equals to 2 2. Medium suitability equals to 2 3. High priority weight equals to 3 3. High suitability equals to 3
ENTIC Co., Ltd. 15
Natural Gas Pipeline to Nong Saeng Power Plant Project Gulf JP NS Co., Ltd. Executive Summary
Fig. 3.3-1 The studied area of the NGP route with peripheries on both sides of
500 meters from the NGP axis
Natural Gas Pipeline to Nong Saeng Power Plant Project Gulf JP NS Co., Ltd. Executive Summary
ENTIC Co., Ltd. 16
Table 3.3-1 Summary of construction methods for NGP of Natural Gas Pipeline to Nong Saeng Power
Plant Project
KP Length (meter)
Construction method
ROW usage Area
owner Note
Section 1 KP 0+000 to KP 1+363 0+000
- Hot Tap High voltage transmission line system zone
Electricity Generation Authority of Thailand (EGAT)
The project 30-inch NGP is joined to 36-inch Wang Noi-Khang Khoi NGP (main pipeline)
0+000-0+075 75 Open Cut High voltage transmission line system zone
EGAT -
0+075 - 0+260
185 Open Cut ROW of RID Road, laid at 0.9 meter from shoulder and 1.5 meter deep
RID -
0+260 - 1+363
1,103 Open Cut ROW of Liap Klong 9 Kwa Road, High voltage transmission line system zone
RID -
Section 2 KP 1+363 to KP 3+652 1+363 - 1+462
99 Open Cut ROW of Highway No. 1-new route, laid at 3.7 meter from shoulder and 1.5 meter deep
DOH Parallel to 24-inch Bang Plee-Saraburi NGP with 1.2 meter apart
1+462 – 1+527
65 Boring ROW of Highway No. 1-new route
DOH Crossing under Highway No. 1-new route with minimum 3.50 meter deep
1+527 - 3+652
2,125 HDD ROW of Highway No. 1-new route, laid at 3.7 meter from shoulder and 1.0 meter deep
DOH -
Section 3 KP 3+652 to KP 4+651 3+652 - 3+692
40 Boring ROW of Highway No. 1-old route
DOH Crossing under Highway No. 1-old route with minimum 3.50 meter deep
Natural Gas Pipeline to Nong Saeng Power Plant Project Gulf JP NS Co., Ltd. Executive Summary
ENTIC Co., Ltd. 17
Table 3.3-1 (continued)
KP Length (meter)
Construction method
ROW usage Area
owner Note
3+692 - 4+651
959 Open Cut ROW of Highway No. 1-old route, laid at 1.4 meter from shoulder with 1.5 meter deep
DOH -
Section 4 KP 4+651 to KP 18+992 4+651 - 5+723
1,072 HDD Klong Rapeepat RID Crossing under Klong Rapeepat with minimum 30 meter deep
5+723 - 6+613
890 Open Cut Liap Klong Rapeepat Road on the canal left side, 14 meter from shoulder and 1.5 meter deep
RID Parallel to existing 12-inch NGP to SIL Industrial Estate (Saraburi)
6+613 - 7+175
562 HDD Liap Klong Rapeepat Road on the canal left side
RID Crossing under the gateway to SIL Industrial Estate (Saraburi) and community streets
7+175 - 10+575
3,400 Open Cut Liap Klong Rapeepat Road on the canal left side, 14 meter from shoulder and 1.5 meter deep
RID -
10+575 -11+300
725 HDD Liap Klong Rapeepat Road on the canal left side
RID Crossing under community areas and streets and Klong Baan Khok at KP 10+900
11+300 -13+300
2,000 Open Cut Liap Klong Rapeepat Road on the canal left side, 14 meter from shoulder and 1.5 meter deep
RID -
13+300 -14+225
925 HDD Liap Klong Rapeepat Road on the canal left side
RID Crossing under Khotchasit community and public drainage canal
Natural Gas Pipeline to Nong Saeng Power Plant Project Gulf JP NS Co., Ltd. Executive Summary
ENTIC Co., Ltd. 18
Table 3.3-1 (continued)
KP Length (meter)
Construction method
ROW usage Area owner Note
14+225 -16+240
2,015 Open Cut Liap Klong Rapeepat Road
on the canal left side, 14
meter from shoulder and
1.5 meter deep
RID -
16+240 -6+807
567 HDD Liap Klong Rapeepat Road
on the canal left side, 14
meter from shoulder
RID Crossing under
community areas and
Highway No. 33
16+807 -8+310
1,503 Open Cut Liap Klong Rapeepat Road
on the canal left side, 14
meter from shoulder and
1.5 meter deep
RID -
18+310 -8+880
570 HDD Liap Klong Rapeepat Road
on the canal left side, 14
meter from shoulder
RID Crossing under Klong
Huayba at KP
18+600
18+880 -18+992
112 Open Cut Liap Klong Rapeepat Road
on the canal left side, 14
meter from shoulder and
1.5 meter deep
RID -
Section 5 KP 18+992 to KP 19+263
18+992 -
19+263
271 Open Cut Area of Nong Saeng
Power Plant, 1.5 meter
deep
Gulf JP NS
Co., Ltd.
-
Total 19,263 Open Cut = 12,612 m.
meters Boring = 105 m.
HDD = 6,546 m.
Natural Gas Pipeline to Nong Saeng Power Plant Project Gulf JP NS Co., Ltd. Executive Summary
ENTIC Co., Ltd. 19
For the project standard design of NGP, the pipe is made of steel API 5L X 65 with a diameter of 30 inches and a thickness of 0.50 inches. The design follows the standard ASME B31.8 (American Society of Mechanical Engineering, Gas Transmission and Distribution Piping Systems) with standard pipe of API 5L Grade B, maximum design pressure of 1,083 psig, operating pressure of about 600 psig. The class location identification is Location Class 3 having a design factor of 0.5.
3.4 NGP construction
The pipeline laying of the Natural Gas Pipeline to Nong Saeng Power Plant project employs 3 methods, such as Open Cut, Boring Method and Horizontal Directional Drilled Crossing (HDD) as shown in Fig. 3.4-1 and referred to Table 3.3-1.
3.5 Pipeline leak test by hydrostatic test
After pipe welding and pipeline lowering on to the right position, the pipeline leak is tested by using pressurized water with a single pressure range for the whole tested pipeline length. The pipeline ends are sealed. Near the pipeline ends, watergates are installed. One pipeline end is connected with water pump equipped with a pressure gauge for showing a pressure inside the pipeline. When the pipeline is full, the internal pressure is slowly increased in order that the pipeline can expand and move due to pressure increase. When the pressure is 1.5 times of the maximum design pressure, it will be kept for 24 hours continuously. Temperature and pressure are recorded for the whole testing period. If no pressure drop or very small drop within the requirement and no leaks on the surface or weld of the pipeline are observed, the test is finished. The water is then released from the pipeline, which is dried by using hot air with a volume of 3 times larger than the pipeline volume. Before start delivering natural gas, pure nitrogen is used to purge air out of the pipeline.
For the water for hydrostatic test, subcontractor will prepare for enough quantity without disturbing community water sources. During testing, no chemicals are added to the water. It is expected to use 8,781 cubic meters of water. After finishing the test, the pressure is reduced and rate of released water is controlled to be slow. Quality of released water is analyzed. The quality parameters include acidity-alkalinity (pH), total dispersion solid (TDS), suspension solid (SS) and temperature. The analysis is for making sure that water released from the hydrostatic test has properties in accordance with waste water standard of relevant offices. The water is collected and released to Nong Saeng Power Plant’s rain water pond with capacity of 29,000 cubic meters. Since the pipeline construction will be in the same period of power plant construction so no water will be released to public water sources.
ENTIC Co., Ltd. 20
Natural Gas Pipeline to Nong Saeng Power Plant Project Gulf JP NS Co., Ltd. Executive Summary
Fig. 3.4-1 Flowchart of NGP laying of Natural Gas Pipeline to Nong Saeng
Power Plant
Natural Gas Pipeline to Nong Saeng Power Plant Project Gulf JP NS Co., Ltd. Executive Summary
ENTIC Co., Ltd. 21
3.6 Pipeline marker posting
When pipeline laying and area recovery are finished, the project is planned to post pipeline markers at every 100 meter. However, the distance between the markers are adjusted when the pipeline is crossing communities or roads. The markers indicate the clear pipeline position. It also warns of dangers that may occur to the NGP. On the markers, the name of Gulf JP NS Co., Ltd., emergency call number and warning message to prevent digging, hammering and drilling in the area.
4. NGP construction plan
For the project NGP construction, it is estimated to take 14 months. Constructions by using Open Cut in general area can be done by 100-200 meters per section and using HDD by 1000 meters per section. Total length of the pipeline is 19.3 kilometers. The construction will begin after the EIA report is approved by ONEP. Preliminarily, the project plans to begin construction in the 4th quarter of B.E. 2553.
5. Environmental impact, measure for prevention and mitigation of environmental impact and measure for environmental quality monitoring
Summary of environmental impact, measure for prevention and mitigation of environmental impact and measure for environmental quality monitoring in the construction and operation periods of Natural Gas Pipeline to Nong Saeng Power Plant Project of Gulf JP NS Co., Ltd., is shown in the table of report on important environmental impacts in construction and operation periods (Table 5-1 and Table 5-2).
ENTIC Co, Ltd. 22
Natural Gas Pipeline to Nong Saeng Power Plant Project
Gulf JP NS Co., Ltd. Executive Summary Table 5-1
Report on important environmental impacts Measure for prevention and mitigation of environmental impacts and measure for monitoring of environmental impacts in the construction period
Natural Gas Pipeline to Nong Saeng Power Plant Environmental factors
and values Important environmental impact Measure for prevention and mitigation of environmental impact
Measure for monitoring of environmental impacts
1. Air quality By measuring of total
suspension particles (TSP) in the atmosphere, averaged for 24 hour, in the studied areas including Wat Sahamitr Mongkol, Wat Chaiyasit Anusorn, Kotchasit TM Office and Wat Thamasinsopa, during 16-19 December B.E. 2553 prior to the project construction, it was found that dust concentrations were 141-155, 93-130, 117-147 and 78-95
g/m3, respectively. When compared to air quality standard value, it was found that the
Air quality impacts during the construction period include dust from construction materials transportation, area preparation, ground excavation, machinery running, etc. When the dust concentration in the atmosphere obtained from evaluation of impacts from construction activities during the construction period of the project with averaged concentration in 24 hours at
maximum of 174.96 g/m3, it was found that total dust in the atmosphere during the construction period of the project was in the standard requirements. In addition, from the evaluation of pollutants released from machinery and automobiles including NO2 and CO, it was found that their quantities were low and the standard requirements.
(1) Spraying of water on the construction areas with ground excavation twice a day and number of spraying is increased when more dusts are in the areas, particularly communities, schools and temples, etc.
(2) Trucks carrying construction materials need to be covered and materials need to be bound to prevent dust spreading and materials falling. In case of materials or soil lump dropping on road, cleaning needs to be done.
(3) Speed limit of trucks carrying construction materials is not over 30 km/hr for passing communities and construction area and not over 80 km/hr for passing general areas (requirement in the Land Traffic Act, B.E. 2522). Signs of speed limit have to be installed in construction area and gate way.
(4) Ground excavation along the route is not conducted at the same time. Ground surface opening for construction is done for each section and immediate backfilling after finishing construction.
(5) Positioning of receiving and drilling pits of boring and HDD has to be far from communities, schools, temples and governmental offices.
(6) Inspecting and checking of engines and machines used for construction and making them be in good conditions as stated in
Monitoring index - Averaged TSP for 24 hours - Particles smaller than 10 microns (PM-10), averaged for 24 hours
Monitoring station Areas close to the NGP route construction sites constructed by Open Cut including
- Communities around Khum Hak TAO Road
- Communities around Liap Klong Soi 9 Kwa Road
- Wat Sahamitr Mongkol at area of Highway No. 1
- Khotchasit TM Office at area of Liap Klong Rapeepat Road
ENTIC Co, Ltd. 23
Natural Gas Pipeline to Nong Saeng Power Plant Project
Gulf JP NS Co., Ltd. Executive Summary Table 5-1 (continued)
Environmental factors and values
Important environmental impact Measure for prevention and mitigation of environmental impact Measure for monitoring of
environmental impacts 1. Air quality (continued) measured values were in the limitation (not higher than 330
g/m3) given in the Notification of National Environment Board (NEB), No. 24 (B.E. 2547).
Notification of Interior Ministry, on Working Safety with Machinery, dated on 28 July B.E. 2519 and Notifications of Ministry of Science, Technology and Environment No. 2 (B.E. 2540) and No.4 (B.E. 2541) on Designation of standard value of exhaust from diesel engines for reduction of pollutants from engines released to atmosphere.
(7) Turning off the engines after working or parking. (8) Installing of plastic panels/canvas walls to reduce dust spreading
in communities with respect to regulations and rules for control of dust from construction activities given in the Notification of Pollution Control Department, Ministry of Natural Resources and Environments. In case that the plastic panels cannot be installed, water spraying or construction materials covering has to be done to reduce dust spreading.
Duration/frequency 1 time for 7 consecutive days in the period that construction is crossing the monitoring point. Measuring method
- TSP : Gravimetric Method - PM-10 : Gravimetric
Method (Size Selective Inlet)
or other methods assigned or approved by relevant governmental offices
2. Noise Results of noise
measurement in the studied area showed that values of level equivalent to 24 hours (Leq 24) of noise were in the range of 52.3 - 68.8 decibel A (dBA).
In the construction period, the project noises include noises of excavation machines and devices and noises of construction machines. Forecasting of noises from construction activities in sensitive areas within the peripheries of 500 meters from the NGP route indicates that the Leq 24 values were in the range of 56.7-69.0 dBA. When compared to the standard value (not
(1) For noisy construction activities, the project has to inform the construction plan to houses and accommodations along the NGP route and submit the letter to inform the construction plan to local administration organizations in the areas 1 month before construction.
(2) In the case that the construction is crossing accommodations, governmental offices, religious places and schools, it has to inform the construction plan with clear starting and finishing dates.
(3) For the noisy construction activities, they have to be conducted
Monitoring index - Leq 24 hours - Leq 1 hour - leq 5 minute - L90 - Lmax
Monitoring station - Areas close to the NGP route sites with 6 stations including;
ENTIC Co, Ltd. 24
Natural Gas Pipeline to Nong Saeng Power Plant Project
Gulf JP NS Co., Ltd. Executive Summary
Table 5-1 (continued) Environmental
factors and values Important environmental impact Measure for prevention and mitigation of environmental impact
Measure for monitoring of environmental impacts
2. Noise (continued) The values were in the standard requirements (not higher than 70 dBA) given in the Notification of NEB No. 15 (B.E. 2540).
higher than 70 dBA) given in the Notification of NEB No. 15 (B.E. 2540), it was found that the noise level values were in the standard requirements. For disturbing noise evaluation by calculation of disturbing noise levels from the project construction activities in the sensitive areas, it was found that maximum disturbing noise was not higher than 9.7 dBA. This was in the standard value (not higher than 10 dBA) given in the Notification of NEB No. 15 (B.E. 2540).
during 08.00-18.00 o’clock if they are crossing communities. Working times are limited for 8 hours/day with respect to the Labour Protection Act, B.E. 2541. (4) It has to assign that the workers who are working in noisy areas
must have protection kits such as ear plugs and ear muffs with standard quality.
(5) Regular maintenance of construction tools and machines to be in good conditions and if loud noise occurs to any components they have to be improved immediately.
(6) Running of heavy machines with loud noise had to be finished quickly. Starting an engine only in working time and turning off immediately after work.
(7) Avoid accelerating the noisy engines. (8) Positioning of receiving and drilling pits for boring and HDD to be
far from people houses, religious places, schools and governmental offices.
(9) Installation a noise protection wall on the side next to a road and a community and on the back side of a HDD machine. The wall is made of light concrete with thickness of 4 inches and height of 2 meters. Width and length of the wall have to be adjusted to cover the drilling pit and the area for laying the construction machines in the drilling pit.
(10) During flushing of air by nitrogen, workers have to wear protection kits, such as ear plugs or ear muffs.
Community in the Khum Hak TAO Road area
Community in the Liap Klong Soi 9 kwa Road area
Wat Sahamitr Mongkol Khotchasit TM Office Nong Khae PWA Wat Suan Kluay - Measure the Lmax of N2
releasing during commissioning for 1 time
Duration/frequency - Measure Leq 24 hours and
L90 for 1 time with 5 consecutive days when the construction is in the monitoring station area
- Measure Lmax for 1 time during N2 releasing
ENTIC Co, Ltd. 25
Natural Gas Pipeline to Nong Saeng Power Plant Project
Gulf JP NS Co., Ltd. Executive Summary Table 5-1 (continued)
Environmental factors and values
Important environmental impact Measure for prevention and mitigation of environmental impact Measure for monitoring of
environmental impacts 2. Noise (continued)
Measuring method Calculation of noise level follows the Notification of NEB No. 15 (B.E. 2540) on Regulation of Ambient Noise Level Standard, the Notification of NEB No. 29 (B.E. 2550) on Disturbing Noise Level and the Notification of Pollution Control Board (B.E. 2550) on Measuring Method for Ambient Noise Level, Non-disturbed Noise Level, Measuring Method and Calculation of Disturbing Noise, Calculation of Disturbing Level and Recording of Disturbing Noise Measurement
3. Soil resource From literature review of secondary data of soil resource in the project studied area, it is found that there are 7 series including; Rangsit
Trenching and soil piling may cause mixing between soil layers. The construction may cause contamination of oil used in machines and engines. For the construction using Open Cut may cause soil erosion. By comparison between the evaluation of soil erosion in the project area with the soil erosion classification in
(1) Not open soil surface at the same time for the whole NGP route (2) Remove ground cover plants only in area to be opened (3) In excavation, it has to separate soil surface layer from a lower one
and in backfilling the lower soil layer was filled and followed by the soil surface layer in order to preserve organic substance in soil.
(4) In back filling, the excavated soil had to be spread over the pipeline route. To compensate a soil collapse, it has to crown the pipeline back with soil before being compacted to a density close to the former value.
-
ENTIC Co, Ltd. 26
Natural Gas Pipeline to Nong Saeng Power Plant Project
Gulf JP NS Co., Ltd. Executive Summary Table 5-1 (continued)
Environmental factors and values
Important environmental impact Measure for prevention and mitigation of environmental impact Measure for monitoring of
environmental impacts 3. Soil resource (continued) series, Mahaphot series, Phimai series, Tha Rua series, Saraburi series, Manorom series and Saraburi/Manorom series. Most soils contain medium to high contents of natural mineral nutrients.
Thailand, it is found that the project area has very low present soil erosion rate.
(5) After backfilling of the NGP in each section, the soil are reconditioned to the former ones promptly
(6) Construction by Open Cut requires prevention of collapse of soil and close area by installation of soil collapse prevention tools such as sheet pile or trench box or other suitable materials.
(7) Preparation of tools and adsorbed materials such as saw dust, cloth bit or sand for cleaning of oil and fuel spilt over the area. The materials used for cleaning are required to be disposed as hazardous materials.
(8) In the case of waste bentonite left from mixing or left in a pit, the project will mix bentonite mud with natural materials such as saw dust, grass bit, rice straw, rice husk, etc., with a ratio of 50:50, according to the suggestion of Land Development Department. This will add organic substance to the materials before being filled the green area of Nong Saeng Power Plant.
4. Surface water quality and aquatic ecosystem
In the project area, there are water sources crossed by the project NGP including Klong Rapeepat, Klong Baan Khok and Klong Huayba.
Laying of the project pipeline crossing those water sources employs HDD. The pipeline is at least 3 meters deep from a canal bed. Pipeline laying will not affect water quality in those water sources. Quality of the water from the hydrostatic test with a volume of 8,781 m3 will be checked as stated in the Notification of Ministry of Science, Technology and Environment (MOSTE), No. 3 (B.E. 2539) on Effluent Standard
1) General measures (1) Stop constructing in a heavy rain period and keeping soil piles
away from canal banks as far as possible to prevent soil leaching into water sources.
(2) Reclamation of the area immediately as soon as pipeline laying is finished. This is to prevent soil leaching into water sources.
(3) Preparation of rubbish containers in the constructing area to collect and take them out for disposal everyday to prevent contamination of adjacent water sources. Disposal of construction materials bits into water sources is strictly prohibited.
(4) Getting enough toilets built for workers in the area as given in the Notification of Interior Ministry on “Designation of welfare concerning health and hygiene for employee”. The toilets are at least 15 meters
1) Surface water quality (Case of pipeline laying crossing surface water sources) Measuring index
- Acidity-alkalinity (pH) - Temperature - TDS - SS - Biological oxygen demand
(BOD) - Oil and grease
ENTIC Co, Ltd. 27
Natural Gas Pipeline to Nong Saeng Power Plant Project
Gulf JP NS Co., Ltd. Executive Summary Table 5-1 (continued)
Environmental factors and values
Important environmental impact Measure for prevention and mitigation of environmental impact Measure for monitoring of
environmental impacts 4. Surface water
quality and aquatic ecosystem (continued)
Water quality in the area is comparable to the water quality Type 3 given in the Notification of NEB No. 8 (B.E. 2537).
for Industrial and Industrial Estate Sources before being released to the rain water pond of Nong Saeng Power Plant. The water from hydrostatic test will not be released to adjacent surface water sources.
from water sources. Preparation of waste water treatment tank for treating of waste water. Getting sewage pumped out regularly by a sewage truck. (5) Prohibition of cleaning of devices, tools and machines and/or
releasing of used water, contaminated water, oil contaminated water, used lubricants, and other contaminants to water sources
(6) Laying of pipeline crossing canals must employ HDD to prevent and mitigate impacts on canal water quality.
(7) Positions of the HDD drilling and receiving pits are at least 20 meters from embankment. A sediment filter is needed to be installed around the area vulnerable to soil leaching into the close water sources.
(8) Specifying the designed depth of the pipeline crossing canals by HDD to be at least 3 meters from a canal bed (considered from canal cross section) in the period of construction design.
2) Measures for releasing of water from hydrostatic test (1) No addition of any chemicals harmful to environment to the water
used for hydrostatic test (2) Installation of a sieve or a net with small open holes to separate
sediments or suspended solids at the end of the pipe used for releasing of water from hydrostatic test and collection of rubbish and waste solids for further disposal
(3) Getting the used water from hydrostatic test checked of quality, for example, acidity-alkalinity (pH), total dispersed solid (TDS), suspended solid (SS) and temperature, along the surface water quality measurement standard to ensure that the used water has quality as stated in Notification of MOSTE No. 3 (B.E. 2539) on
- Turbidity Measuring station
Area in which the pipeline is crossing surface water sources, such as
- Klong Rapeepat - Klong Baan Khok - Kong Huayba
Duration/frequency Measure for 2 times before and during construction across water sources
Measuring method Methods specified in Standard Methods for the Examination of Water and Wastewater
2) Waste water from hydrostatic test Measuring index
- Acidity-alkalinity (pH) - Temperature - TDS - SS
ENTIC Co, Ltd. 28
Natural Gas Pipeline to Nong Saeng Power Plant Project
Gulf JP NS Co., Ltd. Executive Summary Table 5-1 (continued)
Environmental factors and values
Important environmental impact Measure for prevention and mitigation of environmental impact Measure for monitoring of
environmental impacts 4. Surface water
quality and aquatic ecosystem (continued)
Effluent Standard for Industrial and Industrial Estate Sources. If the quality does not meet the standard, the used water is required to be treated before releasing to the rain water pond of Nong Saeng Power Plant.
(4) In case of complaints about releasing of water from hydrostatic test, quick action of problem solving has to be conducted.
Duration/frequency The end of the pipe for releasing of water from hydrostatic test before being transferred to the rain water pond of Nong Saeng Power Plant
Measuring method Methods specified in Standard Methods for the Examination of Water and Wastewater
5. Land ecosystem For general conditions of the area along the NGP and of the close areas, land usages include rice fields, unoccupied areas, community areas and public places. There are no forests or conservation areas.
In the ROWs of Liap Klong Soi 9 Kwa Road and Liap Klong Rapeepat Road, there are some trees scattering in the area. There are no conserved trees. The trees found are local varieties, such as Indian almond, white popinac, Manila tamarind, etc. In area excavation period, trees in the ROW may be removed depending on the agreement made with the area permit organizations because pipeline laying in the area with trees may cause difficulty in working during construction.
(1) Surveying of tree types and numbers in the area to be cleared and making a list of trees to be cut and grown as compensation after construction is finished.
(2) Making a plan and tree removal procedure to be approved by the authorized organizations before work conduction.
(3) The trees removed from ROWs would be put in a tree nursery area before being replanted in an area near the former area and at the allowed positions only.
(4) Removal of trees had to be done carefully and did not disturb other trees outside the working area.
-
ENTIC Co, Ltd. 29
Natural Gas Pipeline to Nong Saeng Power Plant Project
Gulf JP NS Co., Ltd. Executive Summary Table 5-1 (continued)
Environmental factors and values
Important environmental impact Measure for prevention and mitigation of environmental
impact Measure for monitoring of
environmental impacts 6. Transportation The important roads in the project area expected to be main traffic routes during the construction period include Highway No. 1 and Liap Klong Rapeepat Road. The present traffic conditions on both roads are fluent.
The project construction period is planned to be 14 months. Machinery, device and construction materials are transported to the project area by trailers. Transportation of workers uses small trucks. In assessment of impact caused by traffic increase in the form of V/C, it is found that Highways and related roads, such as Highway No. 1 -old and -new routes and Liap Klong Rapeepat road having present V/C values of 0.051, 0.253 and 0.081, respectively, will be able to sufficiently handle the traffic increases with V/C ratios of 0.060, 0.257 and 0.099, respectively. The traffic will be in a good flow and there will be no changes from the present conditions. However, transportations of machines and natural gas pipes may impact people living along roads, particularly in the ROWs of RID Road and Liap Klong Rapeepat Road.
1) General measures (1) Informing the construction plan to local organizations and people
in the close area and making public relationship (PR) to road users in advance for 1 month by posting the construction plan in the road section to be crossed by the NGP.
(2) Training and controlling of drivers of the vehicles related to all kinds of constructions and having them follow traffic law and DOH traffic management requirements seriously for the whole construction period.
(3) Control of machine and device loading on trucks to be within the limits given in the announcement of special highway director, highway director and concession highway director on prohibition of vehicles with overloading or with overloaded axles to use special highway, highway and concession high way, B.E. 2548.
(4) It has to have a chase vehicle to lead the transportation of devices, heavy machines and natural gas pipes in order to warn and help in the case that the trailer is passing a critical area.
(5) Limitation of the construction materials transportation speed, on RID Road, Liap Klong Soi 9 Kwa Road and Liap Klong Rapeepat Road, is not over 30 kilometers per hour.
Measuring index - Record of daily number of
traffic in and out of the construction area
- Record of number of accidents occurring in the project
- Number of complaints from road users in the project area
Measuring station - The project temporary construction office for recording of daily number of traffic in and out of the construction area
- The construction area for recording of accident number of the project
Duration/frequency - Making a monthly report
for the whole construction period
ENTIC Co, Ltd. 30
Natural Gas Pipeline to Nong Saeng Power Plant Project
Gulf JP NS Co., Ltd. Executive Summary
Table 5-1 (continued)
Environmental factors and values
Important environmental impact Measure for prevention and mitigation of environmental impact Measure for monitoring of
environmental impacts
6. Transportation (continued)
(6) Transportation of pipes to the stringing area is limited at the amount to be used on each day. Pipe stringing needs to be tidily and not obstruct the traffic.
(7) Having traffic facilitators work in the construction area and at entrance to the construction area and in the section with a closed traffic lane.
(8) Making a working plan in harmony with other construction parts in order to reduce the number of access to the same place.
(9) Preparation of construction area by clear fencing of the construction area from traffic lanes by concretes, fences or plastic clones and installation of warning signs and blinking light at day and night at least 150 meters before the construction site or with respect to the area agreement. The traffic signs should be reflecting types.
(10) In case of closure/reduction of traffic lanes for construction, the project has to inform the surrounding communities beforehand along with construction period and number of closed lanes. The construction has to be finished quickly.
(11) The construction crossing alley or gateway by Open Cut, it has to inform people about the construction time. The construction has to be finished quickly. If the work is not finished within 1 day, the trench is covered by a steel sheet to make a gateway be usable or a bypass lane is prepared before construction.
Measuring method - Record of daily in-out traffic
number to the project construction area with vehicle classification
- Record of accident number with specified cause and severity
- Record of complaints of road users
ENTIC Co, Ltd. 31
Natural Gas Pipeline to Nong Saeng Power Plant Project
Gulf JP NS Co., Ltd. Executive Summary
Table 5-1 (continued) Environmental
factors and values Important environmental impact Measure for prevention and mitigation of environmental impact
Measure for monitoring of environmental impacts
6. Transportation (continued))
(12) Avoiding putting a weld pipeline to obstruct gateways to houses or small lanes
(13) Avoiding putting materials piles to obstruct traffic and immediate moving of construction materials out of the area after construction.
(14) In case the construction caused damage to signs, traffic signals or traffic surface, it had to get them repaired promptly. Survey of road conditions for making a list of roads used for construction by classification them into crossing roads and access roads and making preparation for quick road restoration.
(15) Improving pavement and traffic surface to the former condition or even better after construction
(16) Accelerating of area reclamation after construction and installation of warning signs and/or clear pipeline makers
(17) Making a transportation plan for vehicles used in construction in order to avoid traffic problems
(18) Clear off the soil bits fallen to the roads used by the project vehicles and the public roads adjacent to the construction site every days.
ENTIC Co, Ltd. 32
Natural Gas Pipeline to Nong Saeng Power Plant Project
Gulf JP NS Co., Ltd. Executive Summary Table 5-1 (continued)
Environmental factors and values
Important environmental impact Measure for prevention and mitigation of environmental impact Measure for monitoring of
environmental impacts 6. Transportation (continued))
2) Measure for constructions using HDD and boring
(1) Getting pipes welded in a working area and been away from traffic surface by preparation and welding of pipe number just enough for HDD only in order to avoid obstructing traffic.
(2) For construction of entry and exit pits in ROWs, ground opening has to be done only for the working area which is fenced clearly and posted with warning signs for passerby at day and night.
(3) Pipe stringing has to be done in ROWs. It will not obstruct any activities in the areas for example traffic and making a living, etc.
3) Measures for mitigation of impacts from closure/reduction of traffic lanes (1) Making PR to road users crossing the project construction site to
know 1 month before the construction begins so they will cautious or take another roads.
(2) Having at least 2 traffic facilitators work for the whole period of traffic lane diversion, with one staff at the starting point of diversion and the other at the construction site end.
(3) Avoid constructing and transporting of materials in rush hours (07.00-09.00 am.) and (16.30-17.30 pm.) to reduce impacts on traffic in the areas of Kum Hak TAO Road, Liap Klong Soi 9 Kwa and Highway No. 1.
ENTIC Co, Ltd. 33
Natural Gas Pipeline to Nong Saeng Power Plant Project
Gulf JP NS Co., Ltd. Executive Summary
Table 5-1 (continued) Environmental
factors and values Important environmental impact Measure for prevention and mitigation of environmental impact
Measure for monitoring of environmental impacts
6. Transportation (continued))
(4) Having staffs conduct the traffic and making alternative stopping and moving of vehicles for each lane in order to prevent fighting for a driving lane and accident due to two-way driving.
(5) Preparation of a parking lot for trailers and worker trucks in a area which is not obstructing the traffic. Putting the machines, devices and materials with tidiness within the construction site only.
(6) Removing of unused materials and tools out of the area promptly. For the materials to be used, they are needed to keep in a suitable area.
(7) Coordination with DOH for the construction plan of the section in the area of Highway No.1.
(8) Coordination with local organizations/police stations for consultation and traffic conduction by asking policemen to take care the job.
(9) Finishing of pipeline laying in each section quickly in order to reduce impact on passerby.
(10) Getting warning signs or signals installed at least 150 meters before the construction site in order to be seen easily both at night and day. Getting fences, plastic clones, warning signs and blinking lights for closure/reduction of traffic lanes with necessary length of traffic lane diversion.
ENTIC Co, Ltd. 34
Natural Gas Pipeline to Nong Saeng Power Plant Project
Gulf JP NS Co., Ltd. Executive Summary
Table 5-1 (continued) Environmental
factors and values Important environmental impact Measure for prevention and mitigation of environmental impact
Measure for monitoring of environmental impacts
7. Waste materials management At present, most houses in the studied area dispose waste materials by burning or landfills in their own areas. In addition, local organizations, such as Nong Saeng TM, Khotchasit TM and Nong Khae TM are responsible to collect waste materials and dispose them properly.
Wastes from construction include construction materials bits from welding, metal bits, concrete bits, etc. The rubbishes from workers and the project staffs are general trashes, such as food boxes and bags, drinking water bottles, papers, etc. It is estimated to have 160 kilograms of trashes a day (rate of rubbish generation is 0.8 kilograms/person/day and maximum workers of 200 people/day). In addition, the construction by using HDD yields some remaining bentonite, which will be used for landfills in the green area of Nong Saeng Power Plant.
1) General waste management (1) Preparation of sufficient rubbish containers with lids and trash bags
at working area and to get the rubbishes disposed by local organizations
(2) Informing staffs and workers about keeping the construction site clean and asking them to do seriously.
(3) Collecting of reusable materials bits, such as metal bits and wood bits and selling of those bits to vendors. Collecting of confusable materials bits and rubbishes and getting them removed out of the construction site every day.
2) Hazardous waste (1) Hazardous wastes having characteristics and properties stated in
the Notification of Ministry of Industry on Disposal of Confusable Waste Materials B.E. 2548 in Appendix 2 stating that it is required to get a hazardous waste separated from general one and to get them disposed by an organization having a permit granted by Department of Industrial Works (DIW).
(2) The wastes generated from machinery maintenance, for example oil, lubricant, solvent, absorbent or cleaning substance and spilt oil, have to be separated from general rubbishes and getting them disposed by an organization having a permit granted by DIW.
(3) Making requirements of hazardous wastes for subcontractors to follow strictly and having subcontractors show bills of hazardous waste transportation as evidences for receiving of last payment.
Measuring index - Quantity of general
rubbishes and waste from construction activities
- Number and frequency of rubbish disposal
Measuring station - Area of the project
temporary construction office - Construction areas in the
whole NGP route
Frequency To conduct for the whole construction period
Measuring method Record of rubbish quantity and rubbish collection frequency in the construction area/ the project temporary construction office
ENTIC Co, Ltd. 35
Natural Gas Pipeline to Nong Saeng Power Plant Project
Gulf JP NS Co., Ltd. Executive Summary Table 5-1 (continued)
Environmental factors and values
Important environmental impact Measure for prevention and mitigation of environmental impact Measure for monitoring of
environmental impacts 7. Waste materials management (continued)
3) Bentonite mud management
(1) Mixing of bentonite for using in HDD in sufficient quantity only to reduce disposal quantity and disposal area
(2) For the whole period of construction by HDD, it is necessary to getting staffs take care the job and to prepare materials, such as sand sacks, for blocking the area to prevent bentonite getting out to the surrounding areas.
(3) In the case of waste bentonite left from mixing or left in a pit, the project will mix bentonite mud with natural materials such as saw dust, grass bit, rice straw, rice husk, etc., with a ratio of 50:50, according to the suggestion of Land Development Department. This will add organic substance to the materials before being filled the green area of Nong Saeng Power Plant. The procedures for management of the waste bentonite from HDD are as follows;
(a) During transportation of bentonite left from HDD, the materials have to be covered to prevent spreading. The bentonite is piled up in an empty area in Nong Saeng Power Plant.
(b) Mixing bentonite with natural materials until the mixer looks like natural soil.
ENTIC Co, Ltd. 36
Natural Gas Pipeline to Nong Saeng Power Plant Project
Gulf JP NS Co., Ltd. Executive Summary Table 5-1 (continued)
Environmental factors and values
Important environmental impact Measure for prevention and mitigation of environmental impact Measure for monitoring of
environmental impacts 8. Drainage and flood prevention
The studied area used to be flood because rain water flew to and gathered at lower land surrounded by roads. The studied area topography has a slope down to Klong Rapeepat. In addition, the left dike of Klong Rapeepat is a high road. Thus the accumulated water cannot cross over the dike.
The construction, for laying of the project NGP in road ROWs crossing 3 water sources, such as Klong Rapeepat, Klong Baan Khok and Klong Huayba, may cause waterway shallowness due to soil leaching during raining. In addition, the construction using Open Cut has to dig a trench for NGP laying. Trenching may cause flooding and drainage problems during heavy raining. Draining of water from the trench may impact the adjacent public drainage system.
(1) In the case of necessary stream blocking, a temporary by-pass stream has to be made, or spared drain pipes have to be installed, to divert the water flow.
(2) No construction activities during heavy raining.
(3) Restoring of canals crossed by the NGP to the former or better conditions and removing of construction materials bits, which are fallen into or obstruct the drain canal.
(4) Preparation of spared water pumps ready for using in the whole construction period to prevent and solve flood problem or to drain water in the working area.
(5) Prohibiting workers not to throw rubbishes into water sources and drain canals adjacent to the construction area.
(6) Avoid piling up soil from pit digging near canals or public drain canals in order to prevent water flow blocking by soil bits.
(7) Pumping of water from a trench or a pit to road surface or pavement is prohibited. For the pumping of water to existing drain pipes, it has not to let mud into the drain pipes. It has to prevent begriming of road surface or pavement by water because it may cause nuisance to road users and passerby.
-
ENTIC Co, Ltd. 37
Natural Gas Pipeline to Nong Saeng Power Plant Project
Gulf JP NS Co., Ltd. Executive Summary Table 5-1 (continued)
Environmental factors and values
Important environmental impact Measure for prevention and mitigation of environmental impact Measure for monitoring of
environmental impacts 9. Economy-society and public participation
According to the economy-society status in the development plans of TAOs in the studied area, most people are farmers. Major incomes are from plant growing, rice farming, animal raising and aquatic animal raising. In all subdistricts, there are full of infrastructures including road, tap water system, electricity system, communication, school and public health service.
The project area and surrounding areas are formerly agricultural lands (rice farms). When Nong Saeng Power Plant starts operating, demands of accommodations and various services will be increasing quickly. Housing estates and communities will be developed continuously. From the survey of economy-society and the conduction of public participation during the study and EIA period, it was found that sample groups in different community had perception of natural gas transportation and the Natural Gas Pipeline to Nong Saeng Power Plant at a good level. Their attitude to the project was positive. When the studied issues were analyzed with respect to 3 opinion types, such as opinion or feeling on natural gas, on the project responsible persons and their operation before starting of the project and on the issue of benefits to be happened or to be gained from the project, it was found
1) Public relationship and making understanding of the project The Gulf JP NS Co., Ltd., realizes and gives priority to making of
knowledge and understanding of the project. These make confidence on natural gas transportation via pipeline and make good relationship between communities and the Gulf JP NS Co., Ltd. The company sets up the “Mass Communication Coordination Center”. The center will conduct PR with people in the project area to know about procedures and construction and operation periods. It will also promote public participation, public hearing and getting complaints for environmental impact. The project makes a plan for PR and making understanding with communities as follows; (1) Getting the Gulf JP NS Co., Ltd., mass communication staffs meet
or visit communities along the NGP route to make them have friendly feeling and be opened to get news and information. The visit is also for getting people suggestions and opinion for making good understanding. The mass communication staffs are the same set for the power plant and being the same compliant channel.
(2) Meeting with community leaders and local organization/police station executives to present the construction plan and methods that may cause impacts to communities, e.g., ground opening for entry and receiver pits, machine noise and construction period, and to discuss a measure for prevention and mitigation of impact and to get cooperation during construction period, particularly mitigation of impact on gateway obstruction and PR to community about the construction plan.
Measuring index
- Community opinion and complaint, number of community visit, number of help giving and problem solving for people impacted by construction activities
- People opinion about impacts from construction activities
Measuring station - People and community
leaders in the areas close to the construction site within a periphery of 500 meters from the route.
Duration/frequency - Opinion and complaint
record is done for the whole construction period.
- Questionnaire interview is done 1 time during the construction period.
ENTIC Co, Ltd. 38
Natural Gas Pipeline to Nong Saeng Power Plant Project
Gulf JP NS Co., Ltd. Executive Summary
Table 5-1 (continued) Environmental
factors and values Important environmental impact Measure for prevention and mitigation of environmental impact
Measure for monitoring of environmental impacts
9. Economy-society and public participation (continued) For overall opinions of people who gave information in the area and had positive attitude to the NGP project, most of them agreed with the NGP project in community areas since they saw it as a public project having benefits for the whole society, e.g., energy and community development. From PR and public participation operations which had been done
that the opinion on the project responsible persons and their operation before starting of the project had a proportion of people in a group of positive opinion lower than that of other issues. However, there were some people showing concern about impacts from the project. They felt unsecured on safety of the NGP crossing a community and felt that natural gas was dangerous.
(3) Making a good relationship and coordinating with relevant organizations in governmental and private sectors continuously to make good friendship and cooperation in future problem solving.
(4) Enforcement of community understanding by proactive PR and increase of learning about different project issues by organizing of exhibition, posting boards of the project, leaflets consisting of construction plan, construction method, measure for prevention and mitigation of construction impacts and channels for communication with responsible persons in case of emergency.
(5) Performing the construction plan PR and informing the construction plan of each NGP section to communities along the route by giving PR documents including construction map, procedure, impact mitigation method and various measures to communities, particularly people living close to/next to the whole route along the roads, in which sections of pipeline laying are constructed. Information distribution has to done 1 month in advance. Informing is also done by using TAO, project PR boards, newsletters and local radios.
(6) Making PR to road users crossing the project construction site at least 1 month by posting project PR boards along the NGP route so they will cautious or take another roads.
Measuring method - Statistical record of
opinion and complaint from community and record of community visit and problem solving report
- Questionnaire interview with 300 samples by taking all families close to the route (0-50 meters) first and then interviewing the rest samples in 50-500 meter peripheries.
ENTIC Co, Ltd. 39
Natural Gas Pipeline to Nong Saeng Power Plant Project
Gulf JP NS Co., Ltd. Executive Summary Table 5-1 (continued)
Environmental factors and values
Important environmental impact Measure for prevention and mitigation of environmental impact Measure for monitoring of
environmental impacts 9. Economy-society and public participation (continued) continuously in the period from pre-study to study. They included visit, consultation, detail interview, public hearing meeting. It was found that for overall most targeted groups agreed with the project. There were some people concerning with safety of the gas leak. The project had explained to people and took the issue for making a measure for prevention and mitigation of impact.
(7) The construction crossing alley or gateway by Open Cut, it has to inform people about the construction time. The construction has to be finished quickly. If the work is not finished within 1 day, the trench is covered by a steel sheet to make a gateway be usable or a bypass lane is prepared before construction.
(8) Posting a board or warning signs on the project construction site boundary so they can be seen and known easily and clearly.
(9) Promotion of participation in society and environment care, making community knowledge for sustainable development, conducting of activities for public benefits and various sustainable developments. The promoted activities include PR activity and strengthening of people sector organization, life quality development project, religious activity, custom and culture, education, sport, health and environment activity.
(10) For traffic lane closure/reduction for construction, before working the project has to inform communities about construction along with time length and number of lanes to be closed. Construction has to be finished quickly.
(11) Assignment of clear schedules for solving general and emergency complaints and preparation of the company complaint forms.
ENTIC Co, Ltd. 40
Natural Gas Pipeline to Nong Saeng Power Plant Project
Gulf JP NS Co., Ltd. Executive Summary Table 5-1 (continued)
Environmental factors and values
Important environmental impact Measure for prevention and mitigation of environmental impact Measure for monitoring
of environmental impacts
9. Economy-society and public participation (continued)
(12) Get up the “Mass Communication coordination center” to promote the operation, measure for prevention environmental project impact and opinion hearing and complaints from communities continuously by putting opinion boxes at public places such as local government agencies temple school. Investigate the complaints everyday and inform of problem solving progress through multiple channels as follows:
(a) Posting at local government agencies such as TAOs (b) Project PR boards in front of the project site office (c) Radio stations or community radios or broadcasting towers (d) Informing directly to complainers (known and contactable
complainers) (e) Problem solving summary published in newsletters (f) Making a letter to TAO, community leaders and relevant offices (g) Informing via community meetings in villages and subdistricts
ENTIC Co, Ltd. 41
Natural Gas Pipeline to Nong Saeng Power Plant Project
Gulf JP NS Co., Ltd. Executive Summary Table 5-1 (continued)
Environmental factors and values
Important environmental impact Measure for prevention and mitigation of environmental impact Measure for monitoring
of environmental impacts
9. Economy-society and public participation (continued)
2) Mitigation of impact of community peace disturbance การลดผลกระทบ (1) For noisy construction activities, In the case that the construction is
crossing accommodations along the route, governmental offices, religious places and schools, the project has to inform the construction plan with clear starting and finishing dates and make a letter informing a construction working plan to local administration organizations for 1 month in advance.
(2) Control of worker behaviors closely to prevent them from making disturbance to communities around.
(3) Following the measures for prevention and mitigation of environmental impacts in the construction period seriously.
(4) Having subcontractors speed up the NGP construction as fast as possible. (5) Stopping of any construction activities crossing communities during heavy
raining (6) Having staffs monitor, control and take care of areas after construction.
They also receive people complaints and solve the problem promptly. 3) Making confidence of environmental impact solving to community (1) Taking details in the environmental working plan to assign clear and fine
conditions in the contracts for design, construction and operation in order to get practical efficiency and effectiveness. Posting and distributing of the conditions so they are known by communities around the project area.
ENTIC Co, Ltd. 42
Natural Gas Pipeline to Nong Saeng Power Plant Project
Gulf JP NS Co., Ltd. Executive Summary Table 5-1 (continued)
Environmental factors and values
Important environmental impact Measure for prevention and mitigation of environmental impact Measure for monitoring
of environmental impacts
9. Economy-society and public participation (continued)
(2) Operation along the working plans for economy-society and public participation in order to make community understand and participate in all steps of project development and making PR of construction plan to community, community leader, local administration organization and local relevant offices for 1 month in advance.
(3) Making the communities in the areas crossed by the project NGP route and adjacent communities participate in watching and preventing any incidents occurring to the project NGP route.
(4) Activities causing daily life and environment problems included noise, dust vibration and safety, etc. Apart from following the measure for prevention and solving of impacts strictly, it was necessary to inform and publicize to people continuously in order to make confidence and get cooperation from communities/local organizations.
(5) Organizing of activities promoting community knowledge and understanding, for example, organizing of a tour visiting the NGP security control system or the supervisory control and data acquisition (SCADA), organizing of a mobile exhibition about natural gas for schools in the studied area and making publicized documents, such as leaflets and newsletters, for giving knowledge to people continuously.
(6) Coordinating with community leaders and relevant offices to give help and solve the problem for people impacted by construction activities of the NGP.
(7) Having public insurances to protect life and property damages caused by NGP construction.
ENTIC Co, Ltd. 43
Natural Gas Pipeline to Nong Saeng Power Plant Project
Gulf JP NS Co., Ltd. Executive Summary Table 5-1 (continued)
Environmental factors and values
Important environmental impact Measure for prevention and mitigation of environmental impact Measure for monitoring
of environmental impacts
9. Economy-society and public participation (continued)
(8) In the case of property or buildings damages, subcontractors have to report the damage cause and consequences to Gulf JP NS Co., Ltd., for every case. Record with details has to be done to prevent damage duplication and to check working tidiness.
(9) Control of subcontractors to complement the measures can be done as follows;
(a) Attach the measures as parts of employment contract (b) Meeting for working conclusion and working planning between
subcontractors and the project owner before working in the morning of everyday.
(c) Having project foremen control the working of subcontractors regularly for the whole working period. If the subcontractors do against the measures or laws or complaints, the project owner will ask the subcontractors to improve. If no improvement is done, the project owner will ask the subcontractors to stop working until the problem is solved.
(d) If the problem cannot be solved within the assigned schedule or by requirements of complainers or of the project owner, it is necessary to inform the causes, rationale and problem solving progress case by case (according to complaint receiving flowchart)
ENTIC Co, Ltd. 44
Natural Gas Pipeline to Nong Saeng Power Plant Project
Gulf JP NS Co., Ltd. Executive Summary Table 5-1 (continued)
Environmental factors and values
Important environmental impact Measure for prevention and mitigation of environmental impact Measure for monitoring of
environmental impacts 10. Occupational health and safety
During construction
procedure, various
activities may impact
on occupational
health and safety of
people living around
and workers. The
impact levels are
different depending
on activity
characters. Measures
for prevention and
mitigation of impacts
are proposed.
Activity performing of each step in the project construction period may cause accidents, such as pipeline welding, pipe transportation and piling and pipeline laying. Careless working causes danger to workers or people living near the NGP. Moreover, workers may be impacted on health due to works, such as dust, construction noise and injury from working.
1) Pre-construction period (1) Design for NGP safety in all steps and with respect to international
standard, such as ASME B31.8 (2) To have personnel qualified and well-trained as occupational
health and safety officers be the inspectors of safety at work. 2) Construction period
(1) NGP joining at the beginning of the route (1.1) Preparation of personnel responsible for welding of natural gas
pipeline. It should have responsible persons in Gulf JP NS Co., Ltd., subcontractor company and PTT.
(1.2) Inspection in details on preparation of tools and devices used for welding of natural gas pipeline under supervision of the staffs of Gulf JP NS Co., Ltd.
(1.3) Organizing a meeting for working groups for production, maintenance and safety in order that they understood the same thing and briefing the welding procedure to responsible persons before operation.
(1.4) Preparation of personal danger prevention kits for workers working on welding for example safety shoes, safety helmet, gloves and glasses and having them wear personal danger prevention kits during working.
Measuring index - Statistics of accident,
illness and injury from working
Measuring station
- Construction site of the NGP
Duration/frequency - Intervals with at least once a
month Measuring method
- To have personnel qualified and well-trained as occupational health and safety officers be the inspectors of safety at work.
- Record of accidents along with causes, solving methods and damages to worker health.
ENTIC Co, Ltd. 45
Natural Gas Pipeline to Nong Saeng Power Plant Project
Gulf JP NS Co., Ltd. Executive Summary Table 5-1 (continued)
Environmental factors and values
Important environmental impact Measure for prevention and mitigation of environmental impact Measure for monitoring of
environmental impacts 10. Occupational
health and safety (continued)
(1.5)Getting fire fighting devices prepared for using in pipe welding area for the case of emergency for example fire engine, gas detector, chemical fire extinguishers with size of 15 pounds and ambulance, etc.
(1.6) Getting warning signs posted and welding area blocked and getting the work permit system worked.
(1.7) Performing pipe joining to the main pipe with respect to the guideline for hot tapping of PTT and the hot tapping procedure is required to be approved by PTT.
(1.8) Blocking of the area so a machine is not close (less than 4 meters) to high voltage transmission lines according to the announcement of EGAT.
(1.9) Preparation of a safety distance symbol or a goal post at transmission line sag for machine movement observation.
(1.10) Grounding a pipe or any metallic materials put under high voltage transmission lines and a clamp contacting area on materials to be ground should be enough for transferring current to ground.
(2) Trenching, Pit digging and pit backfilling (2.1) Getting a backhoe checked if it is in a good condition and
safe before using it. (2.2) During digging by a machine, workers are disallowed to be in
a pit or in a close area possible for getting accident from the machine working.
(2.3) Getting a fence put around pit edge to prevent falling in the pit and getting light and blinking light installed at night.
ENTIC Co, Ltd. 46
Natural Gas Pipeline to Nong Saeng Power Plant Project
Gulf JP NS Co., Ltd. Executive Summary Table 5-1 (continued)
Environmental factors and values
Important environmental impact Measure for prevention and mitigation of environmental impact Measure for monitoring of
environmental impacts 10. Occupational
health and safety (continued)
(2.4) Getting a construction area blocked. When a backhoe is working it has to put a signal board in a trench excavated area and a sign of danger restricted area.
(2.5) Putting a goal post at transmission line sag to be used for observation of machine movement not higher than the safety distance.
(2.6) Having workers for trenching and backfilling wear safety helmet, rubber floor shoes, ear plugs and glasses for the whole working time.
(2.7) Having workers wear protection equipment during working in dusting area, e.g., wearing of dust helmet and cloth mask.
(3) Natural gas pipeline welding (3.1) The project plans to make a contract with subcontractors
having workers with high quality and professional registration. (3.2) Getting welding machines checked before working and if they
are out of order, it has to get them repaired before working. (3.3) All electricity appliances must be grounded to prevent current
leak. (3.4) Having workers wear personal danger protection kits for
welding for example welding mask, light reduction glass or light reduction mask, glove, rubber floor shoes and welding sparking proof apron.
ENTIC Co, Ltd. 47
Natural Gas Pipeline to Nong Saeng Power Plant Project
Gulf JP NS Co., Ltd. Executive Summary Table 5-1 (continued)
Environmental factors and values
Important environmental impact Measure for prevention and mitigation of environmental impact Measure for monitoring of
environmental impacts 10. Occupational
health and safety (continued)
(3.5) Getting a welding area blocked and posting a danger restricted area.
(4) Welding inspection (4.1) Having experts do welding inspection by using non destructive
testing (NDT). (4.2) Getting the area for welding inspection using radiation blocked
and getting warning signs of danger restricted area installed and getting the work permit system done.
(4.3) Having workers wear danger prevention kits such as gloves, safety helmet and safety shoes.
(4.4) Workers have to get a film badge inspected and put on before working.
(4.5) The area for welding inspection using X-ray must have a sign of radiation showing a message and symbols as given below;
(5) Pipeline lowering to a trench (5.1) Getting a backhoe and lifting device conditions checked
before working. (5.2) Inspection for clearing of barricade or people in unsafe
distance from pipe lifting. (5.3) Having workers wear safety helmet, rubber floor shoes and
ear plugs for the whole working period.
ENTIC Co, Ltd. 48
Natural Gas Pipeline to Nong Saeng Power Plant Project
Gulf JP NS Co., Ltd. Executive Summary Table 5-1 (continued)
Environmental factors and values
Important environmental impact Measure for prevention and mitigation of environmental impact Measure for monitoring
of environmental impacts
10. Occupational health and safety (continued)
(6) Commissioning work Workers working with air flushing out of the pipeline before gas delivering by using nitrogen gas must wear ear plugs during working.
(7) Stock of materials (7.1) For utilization of an area for stocking of materials and natural gas
pipes, subcontractors must get permission from the land right owners and must follow regulation designated by Gulf JP NS Co., Ltd.
(7.2) Keeping environmental conditions of the materials stocking area by storing and materials piling tidily and keeping materials bits piling only when they are necessary.
(7.3) The area for storing fuel oil and lubricant for vehicles and engines must be a concrete floor with a roof and surrounded by concrete dikes of 15 centimeters high. This area is able to contain fuel oil with a volume equal to capacity of the biggest tank.
(7.4) For spared fuel oil, it has to be stored in a bin with a lid and kept on the concrete floor.
(8) Transportation and stocking of natural gas pipes (8.1) Stocking of pipes by the method agreed with Gulf JP NS Co., Ltd.,
and taking good care of pipes in order to avoiding pipe damages. (8.2) Subcontractors are responsible to acquire for sleeper timbers and
must adjust timber levels before piling the pipes. They have to use wooden wedges at the pile base to prevent pipe pile collapse and to ensure stability of contact between pipes and sleeper timbers.
ENTIC Co, Ltd. 49
Natural Gas Pipeline to Nong Saeng Power Plant Project
Gulf JP NS Co., Ltd. Executive Summary Table 5-1 (continued)
Environmental factors and values
Important environmental impact Measure for prevention and mitigation of environmental impact Measure for monitoring of
environmental impacts 10. Occupational
health and safety (continued)
(8.3) Pipe turning is not allowed. Shorter pipes must be put on top.
(8.4) For construction area restoration, subcontractors must collect materials and rubbishes so the area is tidied up before handing the area back.
(9) Management of safety and occupational health in the area of the site office
(9.1) Getting sufficient consumable water prepared for workers at a rate of 14 cubic meters a day.
(9.2) Building sufficient toilets for workers in the area according to the Notification of Interior Ministry on designation of welfare concerning employee health. The toilets must be at least 15 meters from water sources. Releasing of untreated waste to water sources is prohibited.
(9.3) Getting bins with capacity of 200 liters put in the area of the site office for collecting wet and dry rubbishes from workers separately and non-sale or non-recycled construction material bits. The rubbishes must be disposed according to the Notification of Ministry of Industry on disposal of waste or unusable materials, B.E. 2548.
(9.4) Getting sufficient amount of mobile fire extinguishers installed in the construction area and in the area easy to be seen.
(9.5) Having security guards control access at an entrance for 24 hours.
(9.6) Having employees of subcontractors put on ID cards before entering or exiting the site area.
ENTIC Co, Ltd. 50
Natural Gas Pipeline to Nong Saeng Power Plant Project
Gulf JP NS Co., Ltd. Executive Summary
Table 5-1 (continued) Environmental
factors and values Important environmental impact Measure for prevention and mitigation of environmental impact
Measure for monitoring of environmental impacts
10. Occupational health and safety (continued)
(9.7) Control workers closely to prevent them from making annoying things to people living near the construction area.
(9.8) Setting up punishment for workers who do against a regulation.
(9.9) Coordinating with local policemen and requesting for cooperation in controlling of workers behaviors and disciplines
(10) Fire prevention in the construction area and preparedness for emergency
(10.1) Ignition or putting a fire in a working place was prohibited except for the allowed case of heat related work.
(10.2) Getting first aid kit installed in the site office. (10.3) Getting a vehicle prepared for taking injured people to a
close hospital immediately in case of accident during working
(10.4) Getting enough amount of mobile fire extinguisher installed in the construction area and in the area easy to be seen.
(11) Measures for pipe laying crossing/parallel to existing NGP/infrastructure (11.1) Checking positions of existing NGP and infrastructure
systems by coordinating with authorized organizations for existing NGP and infrastructure systems.
ENTIC Co, Ltd. 51
Natural Gas Pipeline to Nong Saeng Power Plant Project
Gulf JP NS Co., Ltd. Executive Summary Table 5-1 (continued)
Environmental factors and values
Important environmental impact Measure for prevention and mitigation of environmental impact Measure for monitoring
of environmental impacts
10. Occupational health and safety (continued)
(11.2) Assignment of safety distance with respect to standards providing rules for distances between NGPs, e.g., ASME 31.8 on the topic of 841.14 Cover, Clearance, and Casing Requirement for Buried Steel Pipeline and Mains assign the NGPs clearance to be at least 6 inches (about 15 centimeters)
(11.3) In the case that trenching is doing near the existing NGPs, sheet piles with suitable size and length must be put along the NGP route to prevent soil movement and impacts on the existing NGP route.
(11.4) The Gulf JP NS Co., Ltd., must have staffs control subcontractor’s working closely during construction close to other infrastructures in order to increase carefulness and monitor impacts from pipeline laying. If the problem or damage is observed, they must coordinate and speed up the problem solving.
(12) Measures for safety and prevention of accidents by third party (12.1) It is assigned to put concrete slabs with 1 centimeter thick at
position of trenching for pipeline laying or tie-in point. (12.2) For Open Cut, it is assigned to put a yellow warning tape with
message at 0.7 meter deep and put a concrete slab at 0.5 meter deep and above the NGP route.
ENTIC Co, Ltd. 52
Natural Gas Pipeline to Nong Saeng Power Plant Project
Gulf JP NS Co., Ltd. Executive Summary Table 5-1 (continued)
Environmental factors and values
Important environmental impact Measure for prevention and mitigation of environmental impact Measure for monitoring
of environmental impacts
10. Occupational health and safety (continued)
(13) Measures for prevention and mitigation of impacts on workers working with bentonite mud
(13.1) During mixing of bentonite, workers must wear dust helmet, gloves and goggles.
(13.2) After contacting or working with bentonite, workers must clean their hands and faces before eating or drinking.
(14) Accident report
When there is injury or accident from working, it must report the foreman promptly. Preparation of an accident report describing of cause, solving method and damage.
ENTIC Co, Ltd. 53
Natural Gas Pipeline to Nong Saeng Power Plant Project
Gulf JP NS Co., Ltd. Executive Summary Table 5-2
Report showing important environmental impacts Measures for prevention and mitigation environmental impacts and measures for monitoring environmental impacts in the operation period
Natural Gas Pipeline to Nong Saeng Power Plant
Environmental factors and values
Important environmental impact Measure for prevention and mitigation of environmental impact Measure for monitoring of
environmental impacts 1. Economy-society
and public participation
Transportation of natural gas by pipeline is expected to create economy-society benefits, such as implementation of the nation electricity demand and reduction of imported fuels and electricity. It is also beneficial to communities by main policy of mass communication, which gives priority to monitoring and care of environmental condition restoration and community quality of life.
The project area and surrounding areas are formerly agricultural lands (rice farms). When Nong Saeng Power Plant starts operating, demands of accommodations and various services will be increasing quickly. Housing estates and communities will be developed continuously. From the survey of economy-society and the conduction of public participation during the study and EIA period, it was found that sample groups in different community had perception of natural gas transportation and the Natural Gas Pipeline to Nong Saeng Power Plant at a good level. Their attitude to the project was positive. When the studied issues were analyzed with respect to 3 opinion types, such as opinion or feeling on natural gas, on the project responsible persons and their operation before starting of the project and on the issue of benefits to be happened or to
(1) Having mass communication staffs follow, inspect and take care of area tidiness after construction, to receive complaint relating to people troubles caused by the project development and to solve the problem quickly.
(2) Performing PR to make people living around the NGP learn about how to work near the NGP route, to ask for cooperation in keeping watching of the NGP route and in informing the case in which someone is hammering, digging or backfilling or doing any constructions in the NGP area in order that officers of the Gulf JP NS Co., Ltd., can inspect immediately.
(3) Publicizing of news and information to make people understand and trust in the NGP system, for example posting news on message boards of SAO, village, school and temple, disseminating information using leaflets and distributing emergency handbook for people in order to make their preparedness for NGP leakage.
(4) Having a public insurance to protect damages occurring to life and properties and caused by operation of the NGP.
(5) Promotion of participation in society and environment care, making community knowledge for sustainable development, conducting of activities for public benefits and various sustainable developments. The promoted activities include PR activity and strengthening of
Measuring index Complaints from people about obtained impacts and problem solving by the project
Targeted groups People, community leaders and persons impacted from pipeline construction
Duration/frequency Every complaint from people Measuring method
- Complaint receiving by the project staffs via local administration organizations, community leaders, telephones and letters, etc.
- Record number of complaint, opinion, suggestion, solving guideline and problem solving results for the whole operation period
ENTIC Co, Ltd. 54
Natural Gas Pipeline to Nong Saeng Power Plant Project
Gulf JP NS Co., Ltd. Executive Summary Table 5-2 (continued)
Environmental factors and values
Important environmental impact Measure for prevention and mitigation of environmental impact Measure for monitoring of
environmental impacts 1. Economy-society
and public participation (continued)
be gained from the project, it was found that the opinion on the project responsible persons and their operation before starting of the project had a proportion of people in a group of positive opinion lower than that of other issues. However, there were some people showing concern about impacts from the project. They felt unsecured on safety of the NGP crossing a community and felt that natural gas was dangerous.
people sector organization, life quality development project, religious activity, custom and culture, education, sport, health and environment activity.
(6) Posting the working plan for environment and the emergency handbook for people, organizations and business places, in governmental offices and communities near the NGP route.
2. Occupational health and safety When the project
is operating, there are no activities causing dangers to people living in the areas around because there is only natural gas delivering via the pipeline system at least 1.5 meters underground and there are measures for safety protection.
In the period of gas delivering, regular pipeline patrolling will be conducted. Repair of the pipeline will be done for the case of leak. These activities may affect health of workers and people living around. From risk assessment for the case of NGP leak and flaming with jet fire, it was found that impacts due to heat radiation at the level of 37.5 kW/m2 were able to destroy buildings structures or storage tanks. From risk assessment, it was found that only a ¼ inch leak had probability to occur with a maximum radius of 2.90 meters and with heat
(1) It must have workers working with natural gas be trained/taught on suitable occupational and safety issues such as regulation and working procedure along the NGP, applications of personal danger protection kits, emergency guideline, and first aid, etc.
(2) Measures relating to prevention and controlling accidents from gas leak; (2.1) To specify the areas in the block valve station and the MRS
as special areas under serious inspection and control and with work permit system for area access.
Measuring index - Statistics of accident,
illness and injury during working of staffs
- NGP leak, emergency, cause investigation and solving method
- Worker health
ENTIC Co, Ltd. 55
Natural Gas Pipeline to Nong Saeng Power Plant Project
Gulf JP NS Co., Ltd. Executive Summary Table 5-2 (continued)
Environmental factors and values
Important environmental impact Measure for prevention and mitigation of environmental impact Measure for monitoring of
environmental impacts 2. Occupational
health and safety (continued)
radiation at a level of 12.5 kW/ m2. This was the heat that could impact on people. When the 1 inch leak, the most probable incident to occur for the project NGP, was considered, it was found that a maximum radiation radius 16.65 meters. Within the impact radius, most areas were unoccupied lands, accommodations close to the ROWs for pipeline laying and roads.
(2.2) It must have security guards work regularly at the block valve station and the MRS.
(2.3) Keeping pipeline markers to show a message and a call number easily to be seen.
(2.4) Coordinating with organizations crossed by the NGP to inform them that if they want to do any activities in a safety zone of the NGP, they had to inform the project in advance.
(2.5) Coordinating with local administration organizations to disseminate the project information, knowledge and natural gas safety and to ask for cooperation in pipeline monitoring and in notification of the case in which someone is hammering, digging or backfilling or any constructions in the NGP area in order that officers can inspect immediately.
(2.6) Coordinating with manufacturing plants around the NGP route to disseminate the project information in order to prevent them from causing ignition in the area near the NGP route and to ask for cooperation in keeping watching of any leak causes.
(2.7) For the case that the project needs to open ground surface for repairing of the project underground NGP due to an emergency, it must follow;
(a) Before working, the NGP area must be checked and
confirmed for its location and depth beforehand.
Measuring station The whole project NGP route Duration/frequency
- Record of statistics of accident, illness and injury during working of staffs and NGP leak/for every 6 month
- Worker physical check for every year
Measuring method Record of statistics of measuring indexes and cause investigation and solving method
ENTIC Co, Ltd. 56
Natural Gas Pipeline to Nong Saeng Power Plant Project
Gulf JP NS Co., Ltd. Executive Summary Table 5-2 (continued)
Environmental factors and values
Important environmental impact Measure for prevention and mitigation of environmental impact Measure for monitoring of
environmental impacts 2. Occupational
health and safety (continued)
(b) For clearing works, digging must be done by workers. A back hole is prohibited. Mired vehicles had to be lifted up by a crane only.
(c) Dynamic compaction machines are prohibited for soil compaction works.
(d) Working area must be limited to only the area for NGP repairing. It must prevent the machines from making damages to other infrastructures.
(3) Preparedness for NGP leak incident (3.1) Making an emergency working plan to control the incident
promptly for the case of NGP leak. The emergency control center will be responsible to stop an emergency incident occurring to the project NGP.
(3.2) Making the project’s emergency handbook for people and distributing the handbook to communities and governmental offices near the NGP route.
(3.3) Cooperation with disaster prevention and mitigation offices and local police stations to set up a working group ready for coping with emergency from the NGP.
(4) In case that the Gulf JP NS Co., Ltd., transfers the NGP system to PTT Plc., after the construction is finished, all pipeline system emergency plans of the project will be changed to the PTT emergency plan, after PTT receives the right of NGP system.
ENTIC Co, Ltd. 57
Natural Gas Pipeline to Nong Saeng Power Plant Project
Gulf JP NS Co., Ltd. Executive Summary Table 5-2 (continued)
Environmental factors and values
Important environmental impact Measure for prevention and mitigation of environmental impact Measure for monitoring
of environmental impacts
2. Occupational health and safety (continued)
(5) Occupational health and safety work for workers (5.1) During repairing of a leaked NGP, the work permit system must
be employed to allow workers to work on welding and weld inspection by radiation. Area fencing, posting of danger area signs and strict prohibiting of irrelevant people to enter the area.
(5.2) Working area for radiation weld inspection must have radiation signs with the message “Be aware of danger in radiation area”.
(5.3) Radiation weld inspectors had to examine and put on a film badge before working.
(6) Inspection and maintenance of the NGP (6.1) NGP route watching
(ก) Regular patrolling of the NGP laying area by following the standard ASME B31.8 topics 851.2 851.7 and 852.1 for twice a year
(ข) Regular patrolling of pipeline markers by following the standard ASME B31.8 topic 851.7 for twice a year (at the same time of area patrolling)
(6.2) NGP route maintenance Regular survey and observation of NGP collapse and soil erosion in the areas of soft soil, watercourse and slope with respect to standard ASME B 31.8 topic 841.4 for once a year.
(6.3) Leak survey (a) Regular survey of NGP leak with respect to the standard
ASME B31.8 topics 851.3 และ 852.2 for once a year.
ENTIC Co, Ltd. 58
Natural Gas Pipeline to Nong Saeng Power Plant Project
Gulf JP NS Co., Ltd. Executive Summary Table 5-2 (continued)
Environmental factors and values
Important environmental impact Measure for prevention and mitigation of environmental impact Measure for monitoring of
environmental impacts 2. Occupational
health and safety (continued)
(b) Regular checking of NPG coating damages for every 5 year or when environment changes or pipe to soil potential is lower than the requirement, special test must be done.
(c) Regular checking of insulating joint/.flange for leak or short circuit with respect to a standard for once a year.
(6.4) Maintenance of corrosion prevention system (a) Regular checking of electricity voltage used for
corrosion prevention of NGP at every 1 meter to see if any NGP section has voltage lower than the standard NACE RP 0169 for every 5 year.
(b) Regular checking of corrosion of NGP at high risk areas, such as bend joints or areas with high gas velocity and for the case that corrosion is observed on the NGP, with respect to the standard ASME B31.8 topic 863.2 for once a year.
(c) Regular checking of power supply system of the cathodic protection rectifier by measuring of different electrical parameters, such as current, potential and power, etc., or 12 times a year.
(7) Accident report Staffs who see the accidents have responsibility to make an accident
report to chiefs along the line of command and to relevant offices immediately in order to cooperate in cause analysis and making a measure to prevent duplicated accidents.