Crum_10782178.pdf - Mountain Scholar
-
Upload
khangminh22 -
Category
Documents
-
view
0 -
download
0
Transcript of Crum_10782178.pdf - Mountain Scholar
T-2337
AN APPLICATION OF A PROGRAM EVALUATION
AND REVIEW TECHNIQUE MODEL
FOR THE INTRODUCTION OF A NEW PACKAGED
CONSUMER GOOD
byLester L. Crum
CLOSED RESERVE
ARTHUR LAKES LIBRARYCOLOR/ D«j .: COL oi MINES
ProQuest Number: 10782178
All rights reserved
INFORMATION TO ALL USERS The quality of this reproduction is dependent upon the quality of the copy submitted.
In the unlikely event that the author did not send a com p le te manuscript and there are missing pages, these will be noted. Also, if material had to be removed,
a note will indicate the deletion.
uestProQuest 10782178
Published by ProQuest LLC(2018). Copyright of the Dissertation is held by the Author.
All rights reserved.This work is protected against unauthorized copying under Title 17, United States C ode
Microform Edition © ProQuest LLC.
ProQuest LLC.789 East Eisenhower Parkway
P.O. Box 1346 Ann Arbor, Ml 48106- 1346
T-2337
This Thesis 1s submitted to the Faculty and the Board of Trustees
of the Colorado School of Mines 1n partial fu lfillm ent of the require
ments for the deqree of Master of Science, Mineral Economics.
Golden, Colorado
Date: Juhn JL3 , 19_gp
Slqned:Lester L Crum, Student
Golden, Colorado
Date: Juh e U » 19To
Approved: /&&>/<, tR.E.D. Woolsey, Thesis Advisor
- ttfoo/sa.)Tsey, hRobert E.D. WooTsd̂ , Head
Department of Mineral Economics
11
T-2337
ABSTRACT
This thesis demonstrates the use of a special type of
network analysis known as PERT (program evaluation and re
view technique) to ensure the precise planned timing of a
new product introduction. New consumer products which
have large volume fluctuations monthly or seasonally re
quire the introduction to occur at the optimum point to
achieve the highest potential market share. Timing is
also critical in the expected profitability of a new prod
uct: the purchase, installation, and operation of all
capital equipment with the shortest lead time before prod
uct distribution and customer sales realize higher returns
on the invested capital.
The analysis of the new product by means of the PERT
network indicated a zero probability of the project meet
ing the time schedule before the peak volume of the plan
ned year. Consequently, the project manager presented and
received acceptance from the senior management of the com
pany to reschedule the new product introduction for the
following year. The new time schedules drastically improved the odds of the project achieving the projected
profits and market share.
i i i
T-2337
CONTENTS
LIST OF ILLUSTRATIONS..................................... v
LIST OF T A B L E S ..................................... . . . vi
ACKNOWLEDGEMENTS .......................................... vii
INTRODUCTION................. 1
I. LITERATURE SURVEY.................................... 4
Critical Path Analysis.......................... 4
Networks............................................ 10
Deterministic Approach. . . .................... 16
Stocastic Approach................................. 23
II. PERT METHODOLOGY......................................2 5
Approximating the Beta Distribution ........... 25
Early and Late Time for an Event.................. 28
Probability of a Scheduled Event.................. 31
III. NEW PRODUCT EVALUATION . ........................... 36
Problem Statement ............................... 36
Solution Approach and Network ................. 37
R e s u l t s............. 42
IV. SENSITIVITY ANALYSIS: ACTIVITY AND NETWORK BASED. 46
Activity Based Errors . .........................46
Network Based Errors............................... 50
Epilogue............... 52
iv
T-2337
APPENDIX
A. Area Under Normal Curve. ................. 56
B. Input D a t a ............................................. 57
C. Input Activity Discriptions. ...................... 71
D. Output R e sults.........................................79
BIBLIOGRAPHY.......... 86
ILLUSTRATIONS
Figure
1 Gantt Chart of Job Processing Times .............. 6
2 Gantt Chart of Job Processing Times .............. 7
3 Project Network of Budgeting Process................ 15
4 Typical Job Duration Time-Cost Relationships. . . 18
5 Network Example - C P M ................................19
6 Time-Cost Trade-off for CPM Example .............. 20
7 Possible Forms of the Beta Distribution............ 27
8 Sample Network.........................................29
9 Nugget Activity Flow Network......................... 41
10 Alternative Distributions to the B e t a .............. 48
11 The Alternative Nugget Activity Chart ........... 53
v
T-2337
TABLES
1 Job Processing Times............................. 5
2 Budget Project.....................................14
3 Sample Network Event Calculations ................ 30
4 Sample Network Expected Values (T )2and Variences («r)..............................34
5 Sample Network Probabilities..................... 34
6 Nugget's Critical Path and Expected Probabilities 45
7 Comparison of Parallel Activity Paths ........... 51
8 Discription of the Alternative Activities . . . . 5 4
vi
T-2337
ACKNOWLEDGEMENTS
Writing an acceptable thesis has more than fulfilled my
expectation of frustration. The mechanics and revisions of
some sentences became a word by word construction process
which pushed the range of emotional and thought processes
to deeper thresholds of pain. Fortunately, two things kept
me going and in retrospect, made the task anything but
grim. First, the realization that most of my future prob
lem solving efforts will not require a thesis format for
communication purposes, which ensures I'll continue to en
joy my work. And second, the experience of accomplishing a
goal in which the encouragement of a few people turned a
shared frustration into one of fun. Thanks to my parents
Evelyn T. and Lester W. Crum who encouraged me while com
pleting this the si s as they have throughout the learning
experience of life. If a thesis is a learning exper
ience, then these two people have made my goal directed
life a master thesis.
I would like to thank each member of my thesis com
mittee for giving me a permanent impression which has ex
panded my knowledge and application of Operations Research. Thanks to Dr. Liernert, my first undergraduate
professor in Operations Research, whose hard work and en
thusiasm for Operations Research inspired my study in this
vi i
T-2337
discipline; to Dr. Stermole, who gave added meaning to
Benjamin Franklin's statement, "Remember that time is
money," by demonstrating the importance of the time value
of money; and most of all to my thesis advisor, Dr. R.E.D.
Woolsey, whose advice in problem solving approaches was,
"Do the simple things first."
Also, I'd like to thank J. Robert Copper who gave me
the opportunity and support to address and solve the prob
lem illustrated in this thesis. And finally, to my con
fidante, Karen Carlson, ' who typed and proof read each
draft of this thesis, my sincere appreciation.
vi i i
T-2337 1
INTRODUCTION
The corporate objective to increase revenues is common
to most firms. The increasing dollar sales is an indica
tion of a firms vitality to generate and sustain profits.
To increase total revenues, a firm must maximize the
effectiveness of pricing, advertising, promotions, and
distribution for current products and by adding new prod
ucts to the current product mix. For existing products,
revenue growth becomes an in-depth analysis of pricing and
volume relationships. If product demand is elastic, a re
duced pric'e will increase total revenue, while products
with inelastic demand will increase total revenue with an
increase in price. In the case of new products, market
share penetration for that product’s target market indi
cates the expected increase in sales to the firm.
The new products, besides increasing the revenue base
through additions to the number of products for sale, also
serve to replace the marginally economic products. The
latter function, replacing uneconomical products, is the
most important for new products. Manufactured products,
whether industrial, consumer durable, or non-durable, have
a product life cycle: introductory stage, growth stage,
maturity stage, and declining stage (1). Thus, the
backbone of the corporation then becomes the efforts to
T-2337 2
introduce new products for those in the declining stages
as additions and possible replacements in the currentproduct mix.
The firm's emphasis between new products and existing
products is weighted for the existing products. Here the
human and capital resources in the functional areas of
forecasting, procurement, marketing, manufacturing, dis
tribution, and sales are in place. Also, management can
plan pricing strategies to maximize profits having some
historical basis to forecast the future.
New products, by their non-existence, require a dif
ferent planning and management control within and between
functional areas than the mix of current products. Any
time delays to bring a new product into the product mix
represent foregone revenues and profits for the corpora
tion. The opportunity costs of poor planning and sched
uling of new products are in the millions of dollars for
delays as short as six months. For example, a consumer
goods manufacturer of non-durable goods will experience
seasonality for the various products demanded. Due to
this cyclical demand, the timing of the new product intro
duction should be just before the annual peak demand (2). At the peak of the demand cycle the new product will ex
perience more first time purchases. The larger number of
first time purchases provides a higher probability of
T-2337 3
repeat purchases (3). Therefore, the mature stage market
share for a new product is a partial function of the num
ber of first time purchases. A firm will delay until the
following demand peak if there are any delays in the new
products introduction. There are examples where the lost
profits for a year have reduced the product’s expected
return on investment to the point where the project is
stopped indefinitely.
The purpose of this paper is to illustrate a manage
ment control tool, program evaluation and review technique
(PERT), for a new product introduction. The objective of
the analysis is to provide a means for planning and man
aging activities within and between functional areas and
specifically determine the probability of meeting a sched
uled new product introduction for the peak demand period.
T-2337 4
I. LITERATURE SURVEY
CPA
Program Evaluation and Review Technique is one of a
family of planning and scheduling techniques known gener
ally as critical path analysis (CPA). Plans and schedules
have long been the tools which management has employed to
accomplish the difficult task of coordinating the efforts
of many diverse activities towards a common goal. Ide
ally, a plan is a document that states the manner and
order in which the various tasks of an operation are to be
accomplished before the operation begins. Schedules are
plans that have been fitted to the calendar in order to
meet an established objective date. The plan tells each
component of the organization what is expected of it and
the schedule tells it when it must be accomplished. By
comparing what is accomplished with what was directed,
progress towards the objective can be evaluated and reme
dial action taken if required. Most of the traditional
scheduling techniques are based on the GANTT or bar chart
which have been in common use for over 50 years (4, 5).An example of two Gantt charts depicting the elapsed times
for six jobs consisting of two technologically ordered
processes (process A must precede B) listed in Table 1
follows (5).
T-2337 5
TABLE 1
JOB PROCESSING TIMES
JOB A B
1 9 1
2 8 3
3 5 4
4 7 11
5 6 8
6 2 9
A = Processing time on machine A
B = Processing time in machine B
T-2337 6
FIGURE 1
GANTT CHART OF JOB PROCESSING TIMESJOB PROCESS
A
B 7/m
AB
A
B
AB
A
B
2 A 8
B 'ini,3
%7 I 11
□10 20 30 40 50 60
TOTAL ELAPSED TIME = 57
T-2337 7
Figure 2 shows a collapsed version of the preceding Gantt
Chart.
FIGURE 2
GANTT CHART OF JOB PROCESSING TIMES
9 8 5 7 6 2m M <y//t 11 8 9
T-2337 8
Although these techniques are valuable tools for
scheduling small projects, their use is limited and detri
mental to scheduling of large scale operations. In par
ticular, the bar chart fails to delineate complex inter
actions and relationships which exist among the project
events. In addition, they do not lend themselves to mech
anization through the use of a high speed electronic com
puter. Hence, the developement of CPA as a management
control tool enabled large and complex tasks to be system
atically planned and scheduled. Ideally, CPA functions to
( 6 ):
1. Facilitate the establishment of realistic objectives, initially, so that the likelihood of their timely achievement is good.
2. Monitor the progress of the project and alert management to potential danger areas, on an exception basis, far enough in advance of their occurrence to permit corrective action to be taken with minimum cost and disrupt ion.
3. Provide a vehicle for selecting the optimum course of action from among the several alternatives on a quantitative basis and in accordance with objective criteria when such action is indicated.
CPA was initially used in the construction industry
but is presently finding widespread usage in the defense
industries especially the segments concerned with the
development of aircraft missiles and spacecraft (6). It
has also been successfully employed in the chemical and
petroleum refinery industries and the outlook is that it
T-2337 9
will eventually find application in many other areas, par
ticularly those engaged in project type activities. Among
the many operations that may be classed as projects, are
heavy construction, facilities maintenance, ship building,
and the research and development phase of military weapons
systems acquisitions (7, 8). The organizations engaged in
these operations tend to have several things in common.
The following are of particular interest (9):
1. The end products of each operation are few in number.
2. Each operation is composed of a large number of serial and parallel jobs.
3. All of the jobs are directed toward a common objective event.
4. A significant amount of uncertainty existsregarding the exact manner in which the objective is to be accomplished, how long it will take, and how much it will cost.
The degree of uncertainty will vary with each operation depending upon such factors as the state of the technology employed and the number of times similar operations havebeen performed in the past. In general, theeffects of this uncertainty are quite noticeable when contrasted to production type activities where the operation reaches a steady state and the uncertainty is relatively low.
5. Different jobs are done by different organizations which have difficulty communicatingwith each other.
T-2337 10
NETWORKS
The main idea underlining CPA is the characterization
of a project as a network of inter-related events. The
use of a network or flow diagram as a model of the proj
ect's technological precedence relationship is the one
common element that all CPA family of techniques has in common (10). The network represents all the activity
paths or chains of events that must be accomplished before
achieving the project's objective. The most time restric
tive of these is called the critical path (11). Manage
ment's attention is focused on those activities which form
the critical path. A delay of any one of these activities
means the project's completion will be extended. For this
reason, the term critical path analysis (CPA) has been
given to this family of techniques (12).
The flow diagram or network used as the project model
is an outgrowth of the flow graph technique which has been
used for some time in systems engineering activities (13).
Systems have long been described by mathematical models in
the form of equations. However, the set of equations that
suffices to describe the behavior of a system, fails to portray the structure of the whole system in a readily
comprehended form. Each equation reveals only one com
ponent of that structure and conventional notation does
little to connect these pieces into a coherent whole.
T-2337 11
The flow graph diagram evolved to overcome these
deficiencies. They provided a visual and concise
description of the systems structure that was capable of
being manipulated and solved. "These later operations are
governed by a straight forward set of rules so that one
flow graph is the equivalent of an entire set of equations
(14)
Much work has been done in this field, particularly in
regard to the solution of networks (15, 16, 17). A proj
ect characterized as a network will show the inter-rela
tionship and sequential order of events which must be ac
complished to achieve the desired objective by a certain
date. An event initiates or marks the beginning of an
activity and another event signals the completion of that
activity (18). An event is separated from other events by
jobs or activities which consume time and resources. A
job can not begin until the preceding event has been
accomplished and the succeeding event can not occur until
the jobs which precede it are completed. Certain jobs in
a project must be accomplished in a serial fashion and
others may be accomplished concurrently. Thus, a given event may depend on the completion of two or more jobs.
Generally, it can be expected that one of these parallel
preceding jobs will require more time to complete than its
companions. Similarity, certain events will require more
T-2337 12
time to achieve than others. The particular sequence of
events which represents the most rigorous time constraint
for accomplishing the objective are the critical events/
and comprise the critical path (19). Thus, the critical
path consists of those elements that can not be delayed
without incurring an equivalent delay of the project com
pletion date.
There may be more than one critical path depending
upon the urgency of the project and the degree to which
each job is compressed. A measure of this compression is
the amount of float or slack which a job contains (19).
Float is the difference between the maximal amount of time
available to do a job as prescribed by the schedule and
the time required to do the job utilizing a given level of
resources and without regard to its predecessors or suc
cessors. Float normally has a positive value for non-
critical jobs and zero for those on the critical path.
The project network can be formed in several ways.
One of these is to start at the end or objective event and
work backwards in time in. a step-by-step fashion deter
mining what work must be performed in order to achieve a
given event. Another approach is to list all the jobs
having a bearing on the project and to determine their
precedent relationships before diagramming. A simplified
example illustrates the approach which starts with
T-2337 13
precedence relationships before diagramming (20). The
project is to determine the next year’s operating budget
for a large manufacturing firm. To accomplish this proj
ect the following jobs or activities need to be per
formed :
1. Salesmen must provide unit sales estimatesto the sales and production managers;
2. the Sales manager estimates the market pricefrom the forecast and submits this to thefinance officer;
3. the Production manager schedules the unitsfor production, forwarding the schedule to account ing;
4. the Accounting manager determines the costsof production for the finance officer; and
5. the Financial officer prepares the finalbudget from the sales and accounting departments inputs which is submitted to the president of the company.
Before diagramming, the order in which the jobs have to be
completed before others can be started must be identi
fied. In this example, the sales forecast must be done
before any other activity. The market pricing and produc
tion scheduling follow directly from the sales forecast
which is referred to as the immediate predecessor. Simi
larity, the production schedule is the immediate predecessor for costing the production; the sales pricing and
costing of production are immediate predecessors to thei*
budget preparation. Table 2 summarizes this information.
T-2337 14
TABLE 2
BUDGET PROJECT
JOB DESCRIPTION DEPARTMENT PREDECESSOR
1 Forecasting unit sales Sales
2 Pricing sales Sales 1
3 Preparing production schedules
Manufacturing 1
4 Costing the production Account ing 3
5 Preparing the budget Treasurer 2, 4
Figure 3 shows the project graph or network for the bud
geting projects. Jobs are shown as arrows leading from
one circle on the graph to another. The circles are
called nodes or events (21).
T-2337 15
FIGURE 3
PROJECT NETWORK OF BUDGETING PROCESS
►
No matter which one of the several approaches is usedin the construction of the project network, two essential
steps are found. First, determine precisely those activi
ties that must precede and follow each job and those that
must be performed concurrently. Second, diagram those
relationships without regard to the time duration of the
job. Each job is represented by an arrow which indicates
the direction of the flow of work but whose length has no
significance. Each event is represented by a circle,square or other geometric shape and appears as a nodeformed by the confluence of two or more arrows (22). In
particular, event nodes are identified by numbers assigned
in a variety of ways depending upon the characteristics of
T-2337 16
the computer program employed. Job arrows may be identi
fied by a letter or by the combination of numbers assigned to the events that precede and succede each event. In
addition to the internal work restraints, external re
straints such as deliveries of basic data, equipment,
material and other factors over which management has
little control should be shown. Thus, the project network
represents a completely stated plan, together, with the
environment in which it must be carried out (23).
DETERMINISTIC APPROACH
All CPA approaches use a network to depict and solve
the scheduling problems of a project. It is at this point
that the major difference in the various CPA techniques is
noted. The time certainty or uncertainty of the job
activities in a project determines whether the input data
will be probabilistic or deterministic. When the tech
nology being employed is well established and the degree
of uncertainty is relatively low, the use of deterministic
input data is used (24). In these cases, the operations
of the proposed project have been performed many times in
the past and the job durations are known and can be deter
mined to a reasonably high degree of accuracy.
T-2337 17
When the job duration is known or can be accurately
estimated the associated costs of performing that job is
likely to be known to the same degree of precision. The
two quantities of time and cost very inversely to one
another as shown in Figure 4 (25). Usually, there is some
region where cost is at a minimum and in which management
elects to operate in order to meet its objectives. This
is known as the normal cost and the associated job dura
tion is the normal time to do the job. For critical path
analysis this is the maximum time to do a job as shown in
the same figure. There is also a minimum time to perform
a given job which can be achieved by expending more re
sources in the form of labor, equipment, and materials.
This is referred to as the crash time and the associated
crash cost is the maximum cost for the project. The crash
cost is the total incremental expense from reducing the
activities’ completion times. Between these limits many
other job time-cost relationships exist and are available
for computing schedules as either simple linear or piece-
wise linear representation of the time-cost curve (26).
The original CPM model assumed that the time-cost trade
off for an individual activity is linear with a negative
or zero slope as in Figure 4. The steeper the slope of
the line the higher the cost of expediting the activity;
crashing the job time at no additional cost represents a
line with zero slope or a horzontal line.
T-2337 18
FIGURE 4
TYPICAL JOB DURATION TIME-COST RELATIONSHIP
JOB
COST
$
TIME
NORMAL VS. CRASH TIME-COST REGIONS
JOB
COST
$
TIME
Irash RegionMinimum Time Maximum Cost
Lineai*^ ApproximationMaximum Time Minimum Cost
ormal Region
*Crash Region
*Normal Region
T-2337 19
Since all CPA approaches use a network to depict and
solve the scheduling of the projects, CPM techniques de
termine the projects' least-cost schedule (27). A step-
by-step example from Wiest illustrates the process for
considering the crashing of job times along the critical
path (28). The project consists of four activities,
connected, as in the graph of Figure 5.
FIGURE 5
NETWORK EXAMPLE - CPM
($i)C$4) ($2)($4)
Directly beneath each activity is a pair of numbers. The
first represents the normal time for the activity (days in
this example) and the second number represents the crash
duration, which results from the application of additional
resources. The number in parenthesis is the cost per unit
of time (days) to crash the activity. Figure 6 shows the
time-cost trade-off for each of the activities assuming a
similar base or fixed cost for each activity.
T-2337 20
FIGURE 6
TIME-COST TRADE-OFF FOR CPM EXAMPLE
Activity a Activity b
10987654321
Slope=l
DAYS
10
Slope=4
s
DAYS
Activity c Activity d
10Slope=4
s
DAYS
10987654321
Slope=2
DAYS
T-2337 21
The critical path for this example network is a-c-d which
is a total of twelve days. Assuming the fixed expenses
for the project are time related at $4.50 per day, then
the incremental total cost of the schedule is $54:
Total cost = cost of crashing + cost of overhead = 0 + (12 days)($4.50)= $54.00.
Since activity d has the smallest time-cost trade-off
(slope = 2) on the critical path and the path a-b has two days of slack, the cost of reducing activity d by two days
is calculated:
Total cost = cost of crashing + cost of overhead= (2 days)($2) + (10 days)($4.50)= $49.00.
There are now two critical paths, a-b and a-c-d each
with ten days total time for the project. To reduce the
project schedule further, activities b and c, b and d, or
a must be evaluated. Because activities b and d have the
smallest combined time-cost trade-off ($3), each activity
is reduced one day. Activity d can be reduced to a mini
mum total of two days: the two days reduction at the
first step plus the one day at this point reduces the five
day schedule to the minimum. The total cost for the nine
day schedule is as follows:Total cost = cost of crashing + cost of overhead
= (1 day)($l) + (3 days)($2) + (9 days)($4.50)= $47.50.
T-2337 22
The remaining alternatives for reduction are activity
a or activity b and c. Activity a is the least expensive
($4) compared to activities b and c expense ($5). Activ
ity a can be reduced two days to its’ one day minimum for
a seven day schedule which costs-out to $46.50:
Total cost = cost of crashing + cost of overhead= (2 days)($4) + (1 day)($l) + (3 days)($2)
+ (7 days)($4.50)= $46.50.
The seven day schedule is the least-cost for this
project. Activities b and c can be reduced further but
the cost of crashing will exceed the saving from overhead
expenses.
The preceding process is described as an exhaustive
search procedure because each possible alternative action
of each step of the solution must be evaluated. For proj
ects larger than the example presented, this procedure be
comes more and more difficult to evaluate by a manual
technique. Fortunately there are a number of computer
software packages that handle deterministic inputs of time
and cost. The majority of these techniques are referred
to as Critical Path Methods (CPM) (29). Further develop
ments since 1962 reflect the addition of software programs
incorporating deterministic as well as probabilistic in
puts (30). The next section discusses the approach to
probabilistic time inputs.
T-2337 23
STOCHASTIC APPROACH
The approach to those projects having job times which
are unknown but can be estimated to a reasonable degree of
accuracy are the projects whose job duration uses a proba
bilistic approach. Program Evaluation and Review Tech
nique (PERT) is a CPA application which uses a stochastic
approach to the job activities and to the likelihood of
meeting scheduled completion dates (31). Early in 1958 an
operations research team began an investigation of CPA
techniques for use in evaluating the progress of the U. S.
Navy’s Polaris Fleet Balistic Missile Program (32). Mem
bers of this team included a management consulting firm,
Lockheed Missiles and Space Division, the prime contractor
for the weapons system, and the Navy’s special project
office which was charged with management of the program.
From this investigation came the CPA approach known widely
as PERT. The original application involved 23 networks
connected by some 3,000 job activities that provided con
tinuous appraisal of the project’s validity in terms of
plans and schedules (33). The successful use of PERT in
the Polaris Missile program lead the navy to use PERT inits Eagle Air to Air Missile project and to the aircraft
carrier which was to carry the Eagle Missile. Therefore,
the development and the successful use of PERT as a man
agement control tool had its beginning in the U. S. Navy's
T-2337 24
complex weapons development program. Since 1958, PERT has
experienced a rapid and diverse application. This is due
to the ease of adapting PERT to project type activities
where the technology is new and developing and the uncer
tainty of activities time is indefinite. These projects
are generally representative of old as well as new tech
nological ventures of production. For these cases the
PERT method determines the probability of meeting sched
uled deadlines from estimates made of the approximate
range of the job durations (34).
T-2337 25
II. PERT METHODOLOGY
The first step in the application of PERT is to
develop a network representing the activities of the pro
ject plan. Next a time estimate for each activity's dura
tion is made. Due to the uncertainty in estimating dura
tion times for developmental and research type projects,
PERT assumes the probable duration of an activity is
Beta-distributed. The choice of the Beta distribution
fulfilled three properties that would be postulated for an
actual activity distribution: unimodal, continuous, and
two nonnegative abscissa intercepts (35).
APPROXIMATING THE BETA DISTRIBUTION
The scientist, engineer or manager directly concerned
with the performance of the activity provides these esti
mates :
1. The optimistic estimate of time, symbol a.
2. The most likely estimate of time, symbol m.
3. The pessimistic estimate of time, symbol b.
The PERT literature (36) defines these time estimates as follows:
1. Optimistic time: the resultant duration ifeverything goes better than expected; usually depends upon a breakthrough of some kind. Basically, fewer than 1% of similiarjobs would be completed in less time.
T-2337 26
2. Most likely time: the resultant duration ifeverything goes as expected.
3. Pessimistic time: the duration required ifeverything goes wrong. Fewer than 1% ofsimiliar jobs would exceed this time.
The three time estimates are used to calculate an expected
time, symbol T ;rr. a + 4m + be 6
Te is a linear approximation of the mean for the beta distribution with the probability density function
f(t) = K • (t-a) «(b-t) . The end points, a and b; and the
exponents, e*6- and , must be specified to determine a
unique beta distribution. The optimistic and pessimistic
times are used to specify a and b. The most likely time
is the value used as the mode of the distribution. This
value and the assumption that the standard deviation of
~ the distribution is 1/6 of its range, - l/6(b-a), deter
mines the two parameters and (37). These two
parameters (o* ) also determines the value of the func
tion defining the constant K. The theory of T is to
divide the uncertainty by assuming a 50 percent chance of
being right. The value of Tg would approximately split
the area under the density function into two equal parts(35). This is also true for values of a, b, and m which
determine distributions skewed to the left, skewed to the
right, or non-skewed (figure 7) (38).
T-2337 27
FIGURE 7
POSSIBLE FORMS OF THE BETA DISTRIBUTION
SKEWED TO THE LEFT
SKEWED TO THE RIGHT
NON-SKEWED DISTRIBUTION
T-2337 28
EARLY AND LATE TIME FOR AN EVENT The third step in applying PERT is to calculate the
earliest and latest times which an event may begin. The
earliest time is defined as the time at which the event
will occur if all preceding activities are started as
early as possible; the latest time for an event is the
latest time an event can begin without delaying the com
pletion of the project beyond its earliest time. For
those events that have more than one path of activities
leading toward (or from) them, the earliest time (or
latest time) is calculated from the one path having the
maximum (or minimum) of the total T0 1 s leading to (or
from) that event (39). For example, in the following net
work (figure 8), there are three paths leading to event
number five. The three paths to event five and the
expected times of each are: © , Q), (j) = 6; © > @ > © = 8;
a n d © , © , (s) = 10. The earliest time is taken from the
path with the maximum expected time (T = 10) which is
the path consisting of events©, (4), © .
T-2337 29
FIGURE 8
SAMPLE NETWORK
= 4 ►0 — ►©
The remaining earliest and latest times follow in Table 3
with the associated slack value which is the latest time
minus the earliest time for each event.
T-2337 30
TABLE 3
SAMPLE NETWORK EVENT CALCULATIONS
EVENT EARLIEST TIME LATEST TIME SLACK
6 © ©© ® = i 6 © = 16 0
5 © © © = 10 © © = 1 0 0
4 ' © © - 5 ©©© ‘ 5 0
3 © © = 4 © @ © = 6 2
2 ® @ = 3 © © © = 7 4
1 oII© © © ©© = o 0
T-2337 31
The critical path is identified as those events having
zero slack. If the time unit for the expected value,
Te> is days, the path of events Q), Q), (j)> © totalling sixteen days represents the critical path. Any delay for
an activity along this path will delay the project. A
delay of two days on the pathQ^), (J) or a delay of four days
on the path (T^ Q ) will not delay the project beyond the
original sixteen days schedule.
PROBABILITY OF A SCHEDULED EVENT
The fourth and final step of the PERT application is
calculating the expected probability of an event beginning
when scheduled. PERT’S last assumption is the statistical
independence of all activity’s time in the project (40).
Therefore, the sum of the expected times, which determines
the earliest times and the associated times for the stan
dard deviation, tend toward a normal distribution accord
ing to the central limit theorem. The expected time,
Tg , and the standard deviations, , are from a betadistribution but the distribution of their sum still tend
toward normality. The central limit theorem states (41):
Let the random variables , X£> ...., Xn
be independent with means u, . u„........ u .1 * 2 * * n ’2 2respectively, and associated variance 2 *2. . • • , cs~ • The random variable Z .’ n n
T-2337 32
/ _ Xfc ~ £-1 -/n
under certain regularity conditions is approxi
mately normally distributed with zero mean and
unit variance.
The transformed cumulative density function for the normal
distribution where Z = (y-u)/^- is:2
- ooVZrr
The table of values in Appendix A is used to calculate the
probability of an event starting later than scheduled.
Appendix A is entered with K = (b-u)/^- andCO ~2̂
I
, _ / /n<
d ’z
which is the area (probability) under the normal curve of
a normal random variable being greater than K<*-=(42). Due
to the symmetry of the normal distribution, the value 1 -
gives the probability of being less than K^c • Referring
back to the Zn formula, the variables x^, u^,2and <5 * ̂ are interpreted as follows:
x^= The scheduled start date for event i wherethe start of the project is on day numberone.
ui= The (largest) sum of the Te 1s for theactivities whose path (paths) leads to event i.
2«*i= The sum of the activity variances for thecorresponding Te ’s leading to event i.
T-2337 33
Returning to the preceding example, if the scheduled start
time for each activity is based on the most likely time
estimates leading up to each activity, event six has a 16%
probability of meeting its’ schedule. The two events 2
and 3 have the highest probability of meeting their
schedule, 50% and 77%, respectively. The remaining proba
bilities are shown in the following tables 4 and 5.
T-2337 34
TABLE 4
SAMPLE NETWORK EXPECTED VALUES (Te), AND VARIANCES (^ )
EVENTOPTIMUMESTIMATE
MOSTLIKELYESTIMATE
PESSIMISTICESTIMATE T*
5 to 6 4 6 8 6 .44
2 to 5 1 3 5 3 .44
3 to 5 2 4 6 4 .44
4 to 5 4 5 6 5 .11
1 to 2 2 3 4 3 .11
1 to 3 2 3 10 4 1.78
1 to 4 3 4 7 5 .44
TABLE 5
SAMPLE NETWORK PROBABILITIES
EVENTEARLIEST TIME*
SCHEDULE PROBABILITYT* ..6 16 .99 15 .16-
5 10 .55 9 .09
4 5 .44 4 .07
3 4 1.78 3 .77
2 3 .11 3 .50
1 0 0.00 - -
*Earliest time (Te , <ar^) correspond to the definitions of 14 and ^ 2 ̂ 0n the preceding page.
T-2337 35
In summary, the PERT methodology consists of four steps:
1. Develop the projects activity flow network.
2. Obtain the relevant time estimates for each act ivi ty.
3. Calculate the earliest and latest time estimate for each event in the project.
4. Calculate the probability of an event beginning on schedule.
T-2337 36
III. NEW PRODUCT EVALUATION
PROBLEM STATEMENT
The PERT example to follow was used to resolve the
problem situation of a new product that had advanced to
the last stages of development before commercialization.
This example is the first time in the company's history
that PERT was used as a planning or as a problem solving technique related to new product introductions. Despite
the fact that personnel in the functional areas of market
research, research and development (R§D), and engineering
were familiar, in varying degrees, with PERT; the market
ing department is ultimately responsible for all stages of
new product development. Unfortunately, the marketing
personnel and specifically the New Product marketing mana
ger's low level of confidence in a new quantitative tech
nique (PERT) was understandable. This confidence level is
a particular reflection of the operating and organiza
tional structure of this company: the marketing depart
ment will defer to the experts (operations research, en
gineering, research and development, market research,
etc.) as the major source of evaluation while maintaining the final approval on all recommendations. Therefore, the
marketing department provides the primary initiative and
management in developing, assimulating, and presenting
T-2337 37
recommendations and programs for upper management’s evalu
ation. After approvals are granted, the marketing depart
ment holds the major responsibility for implementation.
The manager responsible for the commercialization
phase for this new product (for proprietary reasons the
product will be referred to as Nugget) presented hisproblem as follows:
Nugget has failed to reach the manufacturing volumes from line tests indicating that the production plants can not fill a national distribution pipeline. Reaching national distribution before the start of the bake season (October) is the marketing strategy approved by senior management. If the manufacturing and R§D problems which have been resolved and those still pending can not be implemented before September the sales and creative activities will be stopped andintroduction will be scheduled for next year.
It is critical to know the odds of success in meeting the planned start ship date. The risk of introducing Nugget into only a limited number of markets is the reaction of competitors introducing new products which would absorb enough volume the next bake season to jeopardize the current and projected profits of the product. In essence there must be enough product produced in September to distribute nationally this year with the contingency plan to delay and introduce the next year.
SOLUTION APPROACH AND NETWORK The proposed solution was to derive a PERT chart
depicting the remaining activities for the Nugget intro
duction and estimate the probability of the project
T-2337 38
meeting the scheduled start ship date. The application of
PERT involved the following steps: list all the jobs or
activities that have to be carried out to complete the
program; assign to each job the estimated time required to
perform it; logically arrange the jobs which are sequen
tial and/or concurrent; sum the time for those jobs that
must be performed consecutively; determine the critical
path; and, calculate the probability of the expected time
meeting the scheduled time for each activity on the criti
cal path.
The marketing manager did not know in total the jobs,
time duration nor precedence relationship for the commer
cialization activities in the Nugget project. This has
been the norm, rather than exception, for all new product
development because a large number of new product ideas
progress through the first stages of development: screen
ing, feasibility, and development, but very few are
approved for commercialization development.
During the first three stages of development, (screen
ing, feasibility, and development), the marketing depart
ment works directly with the R§D department. The personnel in marketing solicits, generates, and segments new product ideas while the R§D personnel will assess the pre
liminary feasibilities for formulations, packaging, and
manufacturing. This information is incorporated into a
T-2337 39
preliminary economic evaluation that if approved leads in
to the beginning of the development phase. R§D will fin
alize the technical plans for process and package design
in the development phase while the market research and
marketing departments continue product and consumer evalu
ations forming the marketing position and branding for the
product. It is at this point that data collection begins
for the finalized capital appropriations needed to bring
the project to commercialization.
Interviews with the marketing people supplied the
background information which represented the stage the
Nugget project had progressed to as of a year ago. At
that time, January, upper management. authorized the Nugget
project to proceeed to the final commercialization phase.
Usually, the first step after the commercialization
approval is the submittal of a package and graphics con
cept by a marketing manager. Simultaneously, the R§D and
operations departments develop a preliminary manufacturing
plan covering the design of the facilities and instal
lations. The problems which developed from that point
were related to the failure of the test equipment to perform at required processing speeds. For the remaining
months of that year, issues of ingredients, formulas, and
equipment were addressed. As of the first of September,
preliminary shelf-life tests indicated the Nugget project
T-2337 40
was again ready to begin the first step of commercializa
tion. One year was spent resolving problems just to bring
the Nugget project to the development point that upper
management believed it to be last September. The network
in figure 9 shows the flow of activities leading up to the
next- scheduled start production. Appendix B contains the
detailed time estimates and precedence relationships
(those activities which precede or may begin concurrently
to one another) for the network shown in figure 9, and
follow the format used by Hillier and Lieberman (43). The
descriptions of the activities are listed in Appendix C.
Time estimates, which are in weeks or a fraction of a five
day week, and precedence relationships were supplied by a
group engineer from the functional area of processing and
from packaging. These two groups of engineers formed a
manufacturing plan using the resolved inputs from market
ing and R$D which reflected changes in the flavor consid
erations, package design and the desired scale of opera
tion. Against this identified manufacturing plan - which
was approved for validity by manufacturing, as well as,
R§D departments - the scheduled time table from the marketing department was finally imposed and evaluated.
T- 2337 42
RESULTS
A time limit of six weeks was imposed for determining
the odds of starting the product production by the first
of September. With that fact in mind, the objective was
to avoid wasting time identifying people and departments
responsible for past failures and the tendency of such
groups and departments to postulate what can not be accom
plished. The approach was to identify those activities which must be successfully accomplished between now and
September (approximately 9 months), assuming all technical
process and product problems had been resolved. The pre
ceding assumption reduced the number of detailed activi
ties each technician identified. Sometimes a certain
group of activities are considered as one activity. ’’This
interpretation may be quite desirable, especially when all
the activities in the group are technologically ordered
and can be considered to form a small project in it’s own
right (44).” For example, the testing and debugging of a
case packing machine may take a week under normal condi
tions. For the Nugget project, the case packing machine
was a new model and required a new set-up configuration;
consequently, the manufacturing and testing steps were not explicitly identified but the increase in the time esti
mates for manufacturing and testing were made. A total of
one hundred and forty-six activities (figure 9) were
T- 2337 4.3
identified as those necessary to bring Nugget to a factory
production state. Approval of the identified activities,
their associated precedence relation to each other and the
time estimates, (optimistic, most likely, and pessimistic)
were given by the departments of manufacturing, R§D, and
market ing.
The network represents the tasks (excluding advertis
ing and sales activities) that a marketing manager must
monitor for one year to assure production begins on sched
ule. The output of results are given in appendix D:
Hillier and Lieberman format (45). The critical path for
the network consists of the following activities which
have a zero slack time: 4, 5 , 21 , 28 , 42 , 54 , 112 , 125,
126, 118, and 146. This is also one of the paths with the
least control because the construction of the cartoner,
activity number 42, is contracted to an outside equipment
manufacturer. The contract represented the earliest pos
sible delivery date from all the bids submitted.
Associated with the critical path are the probabili
ties of the earliest start times beginning on the schedule
assigned by senior management asserting that production start by the first of September. Table 6 is a list of the network activities having a zero slack (critical path) and
the probability of each beginning on schedule.
T-2337 44
The probability of the Nugget project having product
available in all major national markets before the start
of the current bake season is zero. The activity (number
42) which delays the schedule is the design and construc
tion of the cartoner. As mentioned previously, the con
struction of the cartoner is performed by outside contrac
tors. The information from the PERT analysis was incor
porated in the negotiation of a new delivery date on the
new capital equipment which saved the company the cost of
paying for unproductive equipment.
T-2337 45
TABLE 6
NUGGET’S CRITICAL PATH AND EXPECTED PROBABILITIES
CRITICAL PATH ACTIVITIES PROBABILITIES
4 -
5 -
21 .15
28 .13
42 .99
54 .00
112 .00
125 .00
126 .00
118 .00
146 .00
T-2337 46
IV. SENSITIVITY ANALYSIS: ACTIVITY AND NETWORK BASED
The error implications in establishing a critical path
and the associated probabilities of these activities
beginning on schedule assume that the network is correct.
The activity precedence relationships and time estimates
are made by the managers and engineers most directly con
cerned with the performance of those tasks. Therefore, a
unique network representation is identified and possible
variation in the result is a factor of activity estimates
or the network configuration (46).
ACTIVITY BASED ERRORS
There are three possible activity time errors in esti
mating the mean and standard deviation: the deviation for
an activity duration which is not beta-distributed; the
error using the PERT approximation formula for the mean
and standard deviation for a beta-distribution; and the
implication of errors made by the managers, engineers and
scientists in the optimistic, most likely, and pessimistic
time estimates.MacCrimmon and Ryavec (46) considered two extreme dis
tributions, quasi-uniform and quasi-delta, as two extreme
functions to determine the extent and direction of errors
T-2337 47
in using the beta function. This is shown in figure 10
(46). Even though the true distribution of an activity is
not known, the possibility exists that the distribution of
an activity is not beta-distributed. The uniform and
delta distributions conform to the three properties of the
beta-distribution: unimodal, continuous, and having two
non-negative abscissa intercepts; and structured to give
bounds on possible errors on the mean and standard devi
ation by using the beta-distribution. The authors (46)
state that the possible error in the mean activity time
(T ) is a function of the mode and if the mode is near
the endpoint of the distribution (a and b values) the
error could be as much as 33 percent. Associated with the
mean error was a 17 percent absolute worst error in the
standard deviation for this case. Similar error results
were noted in using the approximating formulas for the
mean and standard deviation in the beta-distribution (46).
The additive effect of these two types of errors on
the estimating of the mean and standard deviation activity
time is cancelled by the negative and positive direction
of the error values. The ranges of the activity durations
and the skewness of the activity distributions are addi
tional factors which would lower the error of the expected
worst case.
T-2337 49
The last type of error relating to an activity's time
is the estimation error given for the optimistic, most
likely, and pessimistic activity times. To evaluate this
case an assumption was specified on the extent of the
range of the errors for the time estimates (46):
80% optimistic time 1.10
90% most likely time 1.10
90% pessimistic time 1.20
The results for this case is an absolute error in the mean
and standard deviation respectively:
Maximum mean error = 1/60 (a+4m+b)/(b-a)
Maximum standard deviation error = 1/30 (b+a)/(b-a)
In summary these three factors previously mentioned can
each cause an error of 30 and 15 percent of the range,
respectively, for the activity time's mean and standard
deviation. Since some degree of cancellation can be
expected to occur when all the activities are combined in a network, and the cases considered are extreme, the
errors may be reduced from the 30 and 15 percent to 5 or
10 percent (46).
T-2337 50
As the probability of beginning the production runs as
scheduled was zero, the three types of activity errors was
analyzed for those activities along the critical path.
This was to verify any change in the probability assuming
the errors reduced the expected activity completion time
by the guidelines of 30 percent for the mean and 10 per
cent for the variance. The finding was still a zero prob
ability of meeting a 52 week start production schedule.
At best, if the sum of the optimistic times were achieved
for each activity on the critical path, the probability of
meeting the scheduled production dates is .1 percent. The
.1 percent estimate is the best improvement to expect con
sidering the types of errors previously discussed.
NETWORK BASED ERRORS
There may also be error introduced into the calcula
tion of the early start probability times due to the con
figuration of the network. The calculated mean of an
activity path will be understated and the calculated
standard deviation overstated if parallel paths in the
network are present; where parallel paths are defined as
paths not having a common activity between them. Follow
ing is the table which summarizes the results which
MacCrimmon and Ryavec (46) (table 7) observed for parallel
paths having a mean duration very close to the mean dura
tion of the critical path.
T-2337 51
TABLE 7
COMPARISON OF PARALLEL ACTIVITY PATHS
RATIO OF LENGTHS_____ 1/1 3/4 1/2 1/4
Percent error of PERT from -17% - 8% -0.5% -0.0%actual mean
Percent error of PERT from +39% +23% +4.0% +0.0%actual standard deviation
/
Table 7 implies that if there is a path through a network
that is longer than any other path, the remaining paths do
not have an effect on the project completion time distri
bution in spite of the parallel effect (46). For the
longest path in this case, the central limit theorem is
applied: the mean and standard deviation is summed to
arrive at the project mean and standard deviation.
To examine the effect of parallel paths in the Nugget
network, the early start times on all paths were compared
to the duration on the critical path up to event number
128 which is 53.50 weeks. The next largest mean duration
of an event leading into event 117 or 118 is event number
124 which is 44.6 weeks. The ratio of event 124 to 128 is.83 indicating a mean error of approximately -12% and an
error in the standard deviation of approximately + 31%.
T-2337 52
The effect on the Z value by making the preceding correc
tions is to reduce the probability below that of the orig
inal results. Therefore, the optimistic probability of
0.1% is reduced back to zero for this network. In sum
mary, to assume the worst possible error cases effecting
the specific activities and the possible errors due to
parallel activities paths, the best possible improvement
for the probability of the production beginning on time is from 0.0 to 0.1 percent.
EPILOGUE
The product manager presented the result of the Nugget
PERT analysis to the senior management committee. Their
directive was to stop all contract negotiations, and to
develop a time table which would ensure Nugget's success
ful introduction for the following year.
The Gantt chart which follows on the next page (figure
11) is the basis for the new time schedule. The first
series of activities represents the critical path from the
point where the negotiations were terminated. The remain
ing series of activities (table 8) represents the activi
ties which marketing and sales will follow in the next
year's Nugget project.
T-2337 54
TABLE 8
DISCRIPTION OF THE ALTERNATIVE ACTIVITIES
EVENT NUMBER DESCRIPTION
174 Start advertising.173 ASI results.172 16MM ASI.171 Delivery to the factory.170 Start selling to the trade.169 Kraft district meeting.168 Review first proof.167 Produce TV.166 ASI results.165 Kraft management presentations.164 Order package.163 Turn over final keylines.162 Prepare and review sales promotion
presentations.161 Animated ASI160 Animated production.159 Approve copy to go to animated.158 Order and receive sales materials.157 Final review of story board creation to
all of management.156 Review story board creative.155 Keyline ready for samples.154 Review final promotional plan.153 Start creative copy.152 Start sales promotion development work.151 Start package design.150 Written marketing plan.149 Agency strategy development and
presentation.148 Volume forecasts by market.147 Contract package design firm.
T-23 37 56
APPENDIX A
AREAS UNDER THE NORMAL CURVE FROM K«c TO O O
P (normal - K dx= <*-
K *
oo .01 .02 .03 .04 .05 .06 .07 .08 .09
0.0 .5000 .4960 .4920 .4880 .4840 .4801 .4761 .4721 .4681 .46410.1 .4602 .4562 .4522 .4483 .4443 .4404 .4364 .4325 .4286 .42470.2 .4207 .4168 .4129 .4090 .4052 .4013 .3974 .3936 .3897 .38590.3 .3821 .3783 .3745 .3707 .3669 .3632 .3594 .3557 .3520 .34830.4 .3446 .3409 .3372 .3336 .3300 .3264 .3228 .3192 .3156 .3121
0.5 .3085 .3050 .3015 .2981 .2946 .2912 .2877 .2843 .2810 .27760.6 .2743 .2709 .2676 .2643 .2611 .2578 .2546 .2514 .2483 .24510.7 .2420 .2389 .2358 .2327 .2296 .2266 .2236 .2206 .2177 .21480.8 .2119 .2090 .2061 .2033 .2005 .1977 .1949 .1922 .1894 .18670.9 .1841 .1814 .1788 .1762 .1736 .1711 .1685 .1660 .1635 .1611
1.0 .1587 .1562 .1539 .1515 .1492 .1469 .1446 .1423 .1401 .13791.1 .1357 .1335 .1314 .1292 .1271 .1251 .1230 .1210 .1190 .11701.2 .1151 .1131 .1112 .1093 .1075 .1056 .1038 .1020 .1003 .09851.3 .0968 .0951 .0934 .0918 .0901 .0885 .0869 .0853 .0838 .08231.4 .0808 .0793 .0778 .0764 .0749 .0735 .0721 .0708 .0694 .0681
1.5 .0668 .0655 .0643 .0630 .0618 .0606 .0594 .0582 .0571 .05591.6 .0548 .0537 .0526 .0516 .0505 .0495 .0485 .0475 .0465 .04551.7 .0446 .0436 .0427 .0418 .0409 .0401 .0392 .0384 .0375 .03671.8 .0359 .0351 .0344 .0336 .0329 .0322 .0314 .0307 .0301 .02941.9 .0287 .0281 .0274 .0268 .0262 .0256 .0250 .0244 .0239 .0233
2.0 .0228 .0222 .0217 .0212 .0207 .0202 .0197 .0192 .0188 .01832.1 .0179 .0174 .0170 .0166 .0162 .0158 .0154 .0150 .0146 .01432.2 .0139 .0136 .0132 .0129 .0125 .0122 .0119 .0116 .0113 .01102.3 .0107 .0104 .0102 .00990 .00964 .00939 .00914 .00889 .00866 .008422.4 .00820 .00798 .00776 .00755 .00734 .00714 .00695 .00676 .00657 .00639
2.5 .00621 .00604 .00587 .00570 .00554 .00539 .00523 .00508 .00494 .004802.6 .00466 .00453 .00440 .00427 .00415 .00402 .00391 .00379 .00368 .003572.7 .00347 .00336 .00326 .00317 .00307 .00298 .00289 .00280 .00272 .002642.8 .00256 .00248 .00240 .00233 .00226 .00219 .00212 .00205 .00199 .001932.9 .00187 .00181 .00175 .00169 .00164 .00159 .00154 .00149 .00144 .00139
Kcs .0 .1 .2 .3 .4 .5 .6 .7 .8 .9
3 .00135 •03968 .03687 .03483 .0^337 .0^233 .0^159 .03108 .04723 .044814 .04317 .04207 .04133 .05854 .05541 .05340 .05211 .0s130 .06793 .064795 .06287 .06170 .07996 .07579 .07335 .07190 .07107 .08599 .08332 .081826 .09987 •09530 .09282 .09149 .010777 .010402 .010206 .010104 -011523 .0^260
T-2337 57
APPENDIX B
INPUT DATA
EVENTNUMBER
IMMEDIATELY PRECEDING EVENTS IMMEDIATELY FOLLOWING EVENTS
EVENTNUMBER
ELAPSED TIME ESTIMATESEVENTNUMBER
ELAPSED TIME ESTIMATESEXPECTEDVALUE VARIANCE
EXPECTEDVALUE VARIANCE
146 118 3.07 .160
145 144 3.00 .018 117 2.00 .028
144 106 8.00 .054 145 2.07 .018
143 142 3.00 .010 118 3.07 .160
142 141 3.10 .018 143 2.10 .004
141 107 4.50 .040 142 3.00 .010
140 139 3.00 .010 118 3.07 .160139 138 3.10 .018 140 2.03 .004
138 109 4.93 .028 139 3.00 .010
137 136 1.00 .004 118 3.07 .160
136 135 2.07 .018 137 2.00 .004
135 110 1.00 .004 136 1.00 .004
134 133 0.97 .010 117 2.00 .028
133 132 2.00 .010 134 2.00 .004
132 111 1.00 .004 133 0.97 .010
131 120 1.00 .004 118 3.07 .160130 129 2.00 .101 131 2.00 .018'129 90
1133.031.00
.004
.010130 1.00 .004
128 127 2.53 .010 118 3.07 .160
127 126 0.50 .004 128 1.97 .004
T-2337 58
APPENDIX B(continued)
EVENTNUMBER
IMMEDIATELY PRECEDING EVENTS IMMEDIATELY FOLLOWING EVENTS
EVENTNUMBER
ELAPSED TIME ESTIMATESEVENTNUMBER
ELAPSED TIME ESTIMATESEXPECTEDVALUE VARIANCE
EXPECTEDVALUE VARIANCE
126 125 1.00 .010 127 2.53 .010
125 112 1.97 .010 126 0.50 .004
124 123 3.00 .018 118 3.07 .160
123 98 3.00 .018 124 2.07 .010
122 121 2.00 .028 118 3.07 .160
121 120 1.03 .010 122 2.10 .028
120 119 1.00 .010 121 2.00 .028
119 97 1.93 .018 120 1.03 .010
118 143 2.10 .004 146 4.00 .010140 2.03 .004137 2.00 .004131 2.00 .018128 1.97 .004124 2.07 .010122 2.10 .028117 2.00 .028
117 145 2.07 .018 118 3.07 .160134 2.00 .004116 1.97 .010108 2.07 .018101 3.00 .01086 2.97 .01084 3.00 .01881 2.93 .01080 3.00 .02877 2.00 .01074 4.00 .02863 1.90 .01862 11.10 .054
116 115 0.97 .018 117 2.00 .028
T-2337 59
APPENDIX B(continued)
IMMEDIATELY PRECEDING EVENTS IMMEDIATELY FOLLOWING EVENTSELAPSED TIME ESTIMATES ELAPSED TIME ESTIMATES
EVENTNUMBER
EVENTNUMBER
EXPECTEDVALUE VARIANCE
EVENTNUMBER
EXPECTEDVALUE VARIANCE
115 1146439
1.0012.006.00
.010
.250
.11
116 1.97 .010
114 94 1.97 .004 115 0.97 .018
113 54 11.63 .009 129 2.00 .010
112 54 11.63 .009 125 1.00 .010
111 102 2.00 .004 132 2.00 .010
110 103 2.00 .004 135 2.07 .018
109 104 2.50 .010 138 3.10 .018108 105 2.80 .018 117 2.00 .028
107 92 2.50 .010 141 3.10 .018
106 91 4.55 .028 144 3.00 .018
105 69 8.00 .028 108 2.07 .018
104 68 3.00 .004 109 4.93 .028
103 45 26.17 .111 110 1.00 .004
102 44 26.17 .111 111 1.00 .004
101 100 2.90 .018 117 2.00 .028
100 99 2.00 .028 101 3.00 .010
99 87 2.10 .028 100 2.90 .018
98 96 4.00 .010 123 3.00 .018
97 40 26.17 .250 119 1.00 .010
T-2337 60
APPENDIX B(continued)
IMMEDIATELY PRECEDING EVENTS IMMEDIATELY FOLLOWING EVENTSELAPSED TIME ESTIMATES ELAPSED TIME ESTIMATES
EVENTNUMBER
EVENTNUMBER
EXPECTEDVALUE VARIANCE
EVENTNUMBER
EXPECTEDVALUE VARIANCE
96 95 0.93 .018 98 3.00 .018
95 87 2.10 .028 96 4.00 .010
94 93 3.00 .028 114 1.00 .010
93 40 26.17 .250 94 1.97 .004
92 91 4.55 .028 107 4.50 .040
91 70 1.50 .018 10692
8.002.50
.054
.010
90 89 2.00 .001 113 1.00 .010
89 88 2.10 .028 90 3.03 .004
88 43 18.00 .111 89 2.00 .001
87 65 2.10 .028 9995
2.000.93
.028
.018
86 85 4.03 .018 117 2.00 .02885 50 16.17 .054 86 2.97 .01084 83 5.03 .018 117 2.00 .028
83 8233
12.0019.00
.028
.25084 3.00 .018
82 49 2.00 .001 83 5.03 .018
81 78 4.10 .018 117 2.00 .02880 79 2.93 .004 117 2.00 .028
79 59 8.93 .028 80 3.00 .028
78 60 14.00 .054 81 2.93 .010
T-2337 61
APPENDIX B(continued)
EVENTNUMBER
IMMEDIATELY PRECEDING EVENTS IMMEDIATELY FOLLOWING EVENTS
EVENTNUMBER
ELAPSED TIME ESTIMATESEVENTNUMBER
ELAPSED TIME ESTIMATESEXPECTEDVALUE VARIANCE
EXPECTEDVALUE VARIANCE
77 76 3.00 .028 117 2.00 .028
76 75 4.93 .018 77 2.00 .01075 55 9.17 .028 76 3.00 .02874 73 3.90 .028 117 2.00 .02873 72
712.901.93
.018
.00474 4.00 .028
72 30 3.13 .040 73 3.90 .028
71 30 3.13 .040 73 3.90 .028
70 46 9.63 .040 91 4.55 .028
69 68 3.00 .004 105 2.80 .018
68 67 4.07 .018 10469
2.508.00
.010
.02867 66 2.10 .028 * 68 3.00 .004
66 22 8.60 .028 67 4.07 .018
65 41 18.17 .250 87 2.10 .028
64 53 2.00 .001 115 0.97 .018
63 52 1.97 .001 117 2.00 .028
62 61 2.00 .028 117 2.00 .02861 51 3.17 .054 62 11.10 .05460 48 3.00 .004 78 4.10 .018
59 58 0.93 .004 79 2.93 .004
T-2337 62
APPENDIX B(continued)
IMMEDIATELY PRECEDING EVENTS IMMEDIATELY FOLLOWING EVENTSELAPSED TIME ESTIMATES ELAPSED TIME ESTIMATES
EVENTNUMBER
EVENTNUMBER
EXPECTEDVALUE VARIANCE
EVENTNUMBER
EXPECTEDVALUE VARIANCE
58 57 4.07 .018 59 8.93 .028
57 56 4.00 .018 58 0.93 .004
56 47 3.00 .004 57 4.07 .018
55 47 3.00 .004 75 4.93 .018
54 42 28.50 .160 113112
1.001.97
.010
.010
53 38 6.00 .028 64 12.00 .250
52 37 3.10 .054 63 1.90 .018
51 36 7.17 .028 61 2.00 .028
50 35 7.20 .111 85 4.03 .018
49 34 4.87 .040 82 12.00 .028
48 32 5.03 .028 60 14.00 .054
47 31 5.13 .111 5655
4.009.17
.018
.028
46 7 10.07 .160 70 1.50 .018
45 292826252019
1.073.133.003.002.932.93
.004
.018
.028
.028
.018
.018
103 2.00 .004
44 292826252019
1.073.133.003.002.932.93
.004
.018
.028
.028
.018
.018
102 2.00 .004
T-2337 63
APPENDIX B(continued)
EVENTNUMBER
IMMEDIATELY PRECEDING EVENTS IMMEDIATELY FOLLOWING EVENTS
EVENTNUMBER
ELAPSED TIME ESTIMATESEVENTNUMBER
ELAPSED TIME ESTIMATESEXPECTEDVALUE VARIANCE
EXPJatttlbVALUE VARIANCE
43 29 1.07 .004 88 2.10 .02828 3.13 .01826 3.00 .02825 3.00 .02820 2.93 .01819 2.93 ' .018
42 29 1.07 .004 54 11.63 .00928 3.13 .01826 3.00 .02825 3.00 - .02820 2.93 .01819 2.93 .018
41 29 1.07 .004 65 2.10 .02828 3.13 .01826 3.00 .02825 3.00 .02820 2.93 .01819 2.93 .018
40 29 1.07 .004 97 1.93 .01828 3.13 .018 93 3.00 .02826 3.00 .02825 3.00 .02820 2.93 .01819 2.93 .018
39 29 1.07 .004 115 0.97 .01828 3.13 .01826 3.00 .02825 3.00 .02820 2.93 .01819 2.93 .018
38 292826252019
1.073.133.003.002.932.93
.004
.018
.028
.028
.018
.018
53 2.00 .001
T-2337 64
APPENDIX B(continued)
EVENTNUMBER
IMMEDIATELY PRECEDING EVENTS IMMEDIATELY FOLLOWING EVENTS
EVENTNUMBER
ELAPSED TIME ESTIMATESEVENTNUMBER
ELAPSED TIME ESTIMATESEXPECtfii)VALUE VARIANCE
EXPECTEDVALUE VARIANCE
37 24 0.87 .018 55 1.97 .00123 2.83 .02815 2.90 .05414 3.10 .05412 4.00 .00410 4.10 .0289 4.07 .0408 3.00 .004
36 24 0.87 .018 51 3.17 .05423 2.83 .02815 2.90 .05414 3.10 .05412 4.00 .00410 4.10 .0289 4.07 .0408 3.00 .004
35 24 0.87 .018 50 16.17 .05423 2.83 .02815 2.90 .05414 3.10 .05412 4.00 .00410 4.10 .0289 4.07 .0408 3.00 .004
34 24 0.87 .018 49 2.00 .00123 2.83 .02815 2.90 .05414 3.10 .05412 4.00 .00410 4.10 .0289 4.07 .0408 3.00 .004
33 11 2.00 .018 83 5.03 .018
T-2337 65
APPENDIX B(continued)
EVENTNUMBER
IMMEDIATELY PRECEDING EVENTS IMMEDIATELY FOLLOWING EVENTS
EVENTNUMBER
ELAPSED TIME ESTIMATESEVENTNUMBER
ELAPSED TIME ESTIMATESEXPECTEl)VALUE VARIANCE
EXPECTEDVALUE VARIANCE
32 24 0.87 .018 48 3.00 .00423 2.83 .02815 2.90 .05414 3.10 .05412 4.00 .00410 4.10 .0289 4.07 .0408 3.00 .004
31 24 0.87 .018 47 3.00 .00423 2.83 .02815 2.90 .05414 3.10 .05412 4.00 .00410 4.10 .0289 4.07 .0408 3.00 .004
30 24 0.87 .018 72 2.90 .01823 2.83 .028 71 1.93 .00415 2.90 .05414 3.10 .05412 4.00 .00410 4.10 .0289 4.07 .0408 3.00 .004
29 27 0.93 .004 4544434241403938
26.1726.17 18.00 28.5018.1726.17 6.00 6.00
.111
.111
.111
.160
.250
.250
.111
.028
T-2337 66
APPENDIX B(continued)
EVENTNUMBER
IMMEDIATELY PRECEDING EVENTS IMMEDIATELY FOLLOWING EVENTS
EVENTNUMBER
ELAPSED TIME ESTIMATESEVENTNUMBER
ELAPSED TIME ESTIMATESEXPECTEDVALUE VARIANCE
EXPECTEDVALUE VARIANCE
28 21 2.07 .018 45 26.17 .11144 26.17 .11143 18.00 .11142 28.50 .16041 18.17 .25040 26.17 .25039 6.00 .11138 6.00 .028
27 18 1.17 .028 29 1.07 .00417 1.00 .004
26 18 1.17 .018 45 26.17 .11117 1.00 .004 44 26.17 .111
43 18.00 .11142 28.50 .16041 18.17 .25040 ' 26.17 .25039 6.00 .11138 6.00 .028
25 18 1.17 .018 45 26.17 .11117 1.00 .004 44 26.17 .111
43 18.00 .11142 28.50 .16041 18.17 .25040 26.17 .25039 6.00 .11138 6.00 .028
24 16 3.00 .028 37363534323130
3.107.177.204.875.035.133.13
.054
.028
.111
.040
.028
.111
.040
T-2337 67
APPENDIX B(continued)
EVENTNUMBER
IMMEDIATELY PRECEDING EVENTS IMMEDIATELY FOLLOWING EVENTS
EVENTNUMBER
ELAPSED TIME ESTIMATES ELAPSED TIME ESTIMATESEXPECTEDVALUE VARIANCE
EVENTNUMBER
EXPECTEDVALUE VARIANCE
23 13 2.07 .004 37 3,10 .05436 7.17 .02835 7.20 .11134 4.87 .04032 5.03 .02831 5.13 .11130 3.13 .040
22 6 2.50 .028 66 2.10 .028
21 5 2.17 .028 28 3.13 .0184 2.17 .028
20 5 2.17 .028 45 26.17 .1114 2.17 .028 44 26.17 .111
43 18.00 .11142 28.50 .16041 18.17 .25040 26.17 .25039 6.00 .11138 6.00 .028
19 5 2.17 .028 45 26.17 .1114 2.17 .028 44 26.17 .111
43 18.00 .11142 28.50 .16041 „ 18.17 .25040 26.17 .25039 6.00 .11138 6.00 .028
18 54
2.172.17
.028
.028272625
0.933.003.00
.004
.028
.02817 3 1.00 .028 27
2625
0.933.003.00
.004
.028
.028
T-2337 68
APPENDIX B(continued)
IMMEDIATELY PRECEDING EVENTS IMMEDIATELY FOLLOWING EVENTSELAPSED TIME ESTIMATES ELAPSED TIME ESTIMATES
EVENT EVENT EXPECTED EVENT EXPECTEDNUMBER NUMBER VALUE VARIANCE NUMBER VALUE VARIANCE
16 2 2.00 .004 24 0.87 .0181 2.00 .004
15 2 2.00 .004 37 3.10 .0541 2.00 .004 36 7.17 .028
35 7.20 .11134 4.87 .04032 5.03 .02831 5.13 .11130 3.13 .040
14 2 2.00 .004 37 3.10 .0541 2.00 .004 36 7.17 .028
35 7.20 .11134 4.87 .04032 5.03 .02831 5.13 .11130 3.13 .040
13 2 2.00 .004 23 2.83 .0281 2.00 .004
12 2 2.00 .004 37 3.10 .0541 2.00 .004 36 7.17 .028
35 7.20 .11134 4.87 .04032 5.03 .02831 5.13 .11130 3.13 .040
11 2 2.00 .004 33 19.00 .2501 2.00 .004
10 2 2.00 .004 37 3.10 .0541 2.00 .004 36 7.17 .028
35 7.20 .11134 4.87 .04032 5.03 .02831 5.13 .11130 3.13 .040
T-2337 69
APPENDIX B(continued)
IMMEDIATELY PRECEDING EVENTS IMMEDIATELY FOLLOWING EVENTSELAPSED TIME ESTIMATES ELAPSED TIME ESTIMATES
EVENT EVENT EXPECTED EVENT EXPECTEDNUMBER NUMBER VALUE VARIANCE NUMBER VALUE VARIANCE
9 2 2.00 .004 37 3.10 .0541 2.00 .004 36 7.17 .028
35 7.20 .11134 4.87 .04032 5.03 .02831 5.13 .11130 3.13 .040
8 2 2.00 .004 37 3.10 .0541 2.00 .004 36 7.17 .028
35 7.20 .11134 4.87 .04032 5.03 .02831 5.13 .11130 3.13 .040
7 46 9.63 .040
6 22 8.60 .028
5 21 2.07 .01820 2.93 .01819 2.93 .01818 1.17 .028
4 21 2.07 .01820 2.93 .01819 2.93 .01818 1.17 .028
3 17 1.00 .004
T-2337 70
APPENDIX B(continued)
IMMEDIATELY PRECEDING EVENTS IMMEDIATELY FOLLOWING EVENTSELAPSED TIME ESTIMATES ELAPSED TIME ESTIMATES
EVENT EVENT Expected EVENT ExpectedNUMBER NUMBER VALUE VARIANCE NUMBER value VARIANCE
2 16 3.00 .02815 2.90 .05414 3.10 .05413 2.07 .00412 4.00 .00411 2.00 .01810 4.10 .0289 4.07 .0408 3.00 .004
1 16 3.00 .02815 2.90 .05414 3.10 .05413 2.07 .00412 4.00 .00411 2.00 .01810 4.10 .0289 4.07 .0408 3.00 .004
T-2337 71
APPENDIX C INPUT ACTIVITY DISCRETIONS
EVENT NUMBER DESCRIPTION____________________________________
146 Start 4 week product run to build inventory.
145 Test runs of folder at N. A.
144 Install and hook-up next folder at N. A.
143 Test run second unit folder at N. A.
142 Ship and install folder at N. A.
141 Manufacture samples for shelf-life test -S. V.
140 Test run second unit sheeter at N. A.
139 Ship and install second unit at N. A.
138 Manufacture samples to inspection at S. V.
137 Test run of palletizer.
136 Make electrical hook-up for palletizer.
135 Install palletizer.
134 Check out running of case packer.
133 Make electrical hook-ups for case packers.
132 Install case packer.
131 Check out entire cartoner operation at N. A.
130 Electrical hook-up of cartoner at N.A.129 Install cartoner at N. A.
128 Check out entire cartoner operation at S. V.
127 Install electrical hook-ups.
T-2337 72
APPENDIX C(cont inued)
EVENT NUMBER DESCRIPTION____________________________________
126 Install cartoner.
125 Deliver cartoner to S. V.124 Check out sheeter at N. A.
123 Ship and install sheeter - N. A.
122 Check out pouch operation.
121 Connect electrical hook-ups.
120 Install pouch machine at N. A.
119 Deliver pouch machine to N. A.
118 In plant shakedowns.
117 All plants and lines final check out.
116 Electrical hook-up of pouch machine.
115 Install pouch machine at S. V.
114 Deliver pouch machine to S. V.
113 Deliver cartoner to N. A.
112 Test and modify cartoner.
Ill Deliver case packer.
110 Deliver palletizer.109 Synchronize test: dough, sheeter, folder
at S. V.
108 Check out slipsheeter operation - N. A.
107 Synchronize test: dough, sheeter - S. V.
T-2337 73
APPENDIX C
(cont inued)
EVENT NUMBER DESCRIPTION____________________________________
106 Order and construct folder for N. A.
105 Install and hook-up slipsheeter at N. A.104 Hand feed test case packer with folder.
103 Test palletizer.
102 Test case packers.
101 Check out of sheeter at N. A.
100 Install second unit sheeter at N. A.
99 Shop test second unit sheeter send to N. A.
98 Manufacture samples from slipsheeter - S. V.
97 Test second pouch machine.
96 Test slipsheeter at S. V.
95 Machine adjustments for slipsheeter - S. V.
94 Test first poucher machine.
93 Make modification changes to poucher.
92 Hand feed test with slipsheeter at S. V.
91 Install and hand feed test at S. V.
90 Test run poucher and cartoner.89 Make electrical hook-ups for poucher and
carton loader.
88 Deliver and install pouch and carton loader.
87 Install first sheeter unit at S. V.
T-2337 74
APPENDIX C
(cont inued)
EVENT NUMBER DESCRIPTION____________________________________
86 Check out bulk flour system.
85 Install bulk flour system.
84 Check out liquid lard system.
83 Install liquid lard system.
82 Deliver liquid lard system.
81 Check out flour cooling system.
80 Ship samples to N. A. for Q. A. comparison.
79 Manufacture samples.
78 Install flour cooling system.
77 In place testing of water and alcoholsystem.
76 Install water and alcohol system.
75 Layout water color and alcohol system.
74 Start-up of old cookie line.
73 Relocate cookie line.
72 Remove and install electrical hook-ups.
71 Remove dinner roll line.
70 Shop test folder and ship to S. V.69 Order, construct, ship second unit to N. A.
68 Hand feed test slipsheeter at S. V.
67 Install at S. V. - slipsheeter.
T-2337 75
APPENDIX C
(cont inued)
EVENT NUMBER DESCRIPTION__________________________________
66 Shop test and ship to S. V. - slipsheeter.
65 Shop test and ship to S. V. - packagesheeter.
64 Deliver construction equipment - packaging.
63 Contact supplier if required.
62 Start construction.
61 Award contract.
60 Deliver - flour cooling system.
59 Test with dough sheeter.
58 Mix review session - management.
57 Test and optimize mix process.
56 Install mixers at S. V. plant.
55 Install mixers at N. A. plant.
54 Deliver cartoner.
53 Order construction equipment.
52 Investment project analysis - review.
51 Submit bids for building modifications.
50 Delivery time - bulk flour system.49 Order equipment - liquid lard system.
48 Order equipment - flour cooling system.
47 Order equipment - mix systems - N. A. andS. V.
T-2337 76
APPENDIX C
(continued)
EVENT NUMBER DESCRIPTION____________________________________
46 Construct folder prototype.
45 Order palletizer.
44 Order case packer.
43 Cyber design pouch out-feed and cartonloader in-feed.
42 Design and construct cartoners (contracted).
41 Construct sheeter.
40 Design and construct poucher (contracted).
39 Final packaging layout.
38 Final construction system design.
37 Final cost estimates - processing.
36 Building design.
35 Final design - bulk flour.
34 Final design for liquid lard.
33 Construct liquid shortening tanks and pads.
32 Final design flour cooling.
31 Final design of mix system.
30 Electrical design - dinner roll and cookie1ines.
29 Place in preliminary production schedule.
28 Final sheeter specifications.
27 Order carton and poucher.
T-2337 77
APPENDIX C
(continued)
EVENT NUMBER DESCRIPTION____________________________________
26 Preliminary package layout.
25 Preliminary control system design.
24 Investment project analysis - update.
23 Final process flow approval.
22 Construct prototype for slipsheeter.
21 Select sheeter.
20 Final packaging ground rules.
19 Final packaging equipment specifications.
18 Select cartoner and other equipment.
17 Appropriation requests for investmentanalysis.
16 Investment project analysis first estimate.
15 Final process ground rules.
14 Final process design - liquid vs. plastic.
13 Preliminary process flow configuration.
12 Preliminary process design - bulk flour.
11 Order liquid tanks.
10 Preliminary process design liquidshortening.
9 Preliminary process design flour cooling.
8 Preliminary process design mix system.
T-2337 78
APPENDIX C
(cont inued)
EVENT NUMBER DESCRIPTION________________________
7 Design folder.
6 Design slipsheeter.
5 Preliminary packaging system ground rules.
4 Preliminary packaging equipment criteria.3 Investment project analysis - processing.
2 Processing system ground rules.
1 Preliminary process design criteria.
T-2337 79
APPENDIX D OUTPUT RESULTS
EVENT
EARLIEST TIME ...TSraSTTIHE..
SLACKORIGINALSCHEDULE
PROBABILITY
EXPECTEDVALUE VARIANCE
EXPECTEDVALUE VARIANCE
146 58.54 .431 58.54 0 0 52 .00
145 36.75 .318 51.40 .206 14.65 38 .99
144 33.75 .300 48.40 .224 14.65 35 .99143 38.85 .324 51.37 .192 12.52 40 .98142 35.85 .314 48.37 .202 12.52 37 .98
141 32.75 .296 45.27 .220 12.52 34 .99
140 33.80 • .172 53.44 .164 19.64 35 .99
139 30.80 .162 50.44 .174 19.64 32 .99
138 27.70 .144 47.34 .192 19.64 29 .99
137 39.61 .205 53.47 .164 13.86 40 .81
136 38.61 .201 52.47 .168 13.86 39 .81
135 36.54 .183 50.40 .186 13.86 37 .86134 39.51 .203 53.47 .164 13.96 40 .86
133 38.54 .193 52.50 .174 13.96 39 .85
132 36.54 .183 50.50 .184 13.96 38 .99
131 51.50 .257 53.47 .178 1.97 47 .00
130 50.50 .253 52.47 .182 1.97 46 .00
129 48.50 .243 50.47 .192 1.97 45 .00128 53.50 .267 53.50 .164 0.0 47 .00
127 50.97 .257 50.97 .174 0.0 46 .00
126 50.47 .253 50.47 .178 0.0 45.5 .00
T-2337 80
APPENDIX D(continued)
EVENT
EARLIEST TIME LATENT TIME
SLACKORIGINALSCHEDULE
PROBABILITY
EXPECTEDVALUE VARIANCE
EXPECTEDVALUE VARIANCE
125 49.47 .243 49.47 .188 0.0 45 .00
124 44.60 .426 53.40 .170 8.80 44 .18123 41.60 .408 50.40 .188 8.80 42 .74122 39.50 .380 53.37 .188 13.87 40 .79121 37.50 .352 51.37 .216 13.87 38 .80120 36.47 .342 50.34 .226 13.87 37 .82119 35.47 .332 49.34 .236 13.87 36 .82
118 55.47 .271 55.47 .160 0.0 49 .00117 42.45 .384 53.47 .188 11.02 47 .99
116 40.48 .374 51.50 .198 11.02 41 .80
115 39.51 .356 50.53 .216 11.02 40 .79114 38.51 .346 49.53 .226 11.02 39 .80
113 47.50 .233 49.47 .202 1.97 44 oo
112 47.50 .233 47.50 .198 0.0 44 .00
111 35.54 .179 49.50 .188 13.96 36 .86
110 35.54 .179 49.40 .190 13.86 36 .86
109 22.77 .116 42.41 .220 19.64 24 .99
108 31.07 .152 51.40 .206 20.33 32 .99107 28.25 .256 40.77 .260 12.52 30 .99
106 25.75 .246 40.40 .278 14.65 27 .99
105 28.27 .134 48.60 .224 20.33 29 .98
T-2337 81
APPENDIX D(continued)
EVENT
EARLIEST TIME LATEST Tl'm
SLACKORIGINALSCHEDULE
PROBABILITY
EXPECTEDVALUE VARIANCE
EXPECTEDVALUE VARIANCE
104 20.27 .106 39.91 .230 19.64 21 .99
103 33.54 .175 47.40 .194 13.86 33 .10
102 33.54 .175 47.50 .192 13.96 34 .86
101 34.64 .416 50.47 .198 15.83 36 .98
100 31.74 .398 47.57 .216 15.83 32 .66
99 29.74 .370 45.57 .244 15.83 30 .67
98 34.67 .398 47.40 .206 12.73 35 .70
97 33.54 .314 47.41 .254 13.87 34 .79
96 30.67 .388 43.40 .216 12.73 31 .70
95 29.74 .370 42.47 .234 12.73 30 .67
94 36.54 .342 47.56 .230 11.02 37 .79
93 33.54 .314 44.56 .258 11.02 34 .79
92 25.75 .246 38.27 .270 12.52 27 .99
91 21.20 .218 33.72 .298 12.52 22 .96
90 29.47 .204 46.44 .206 16.97 31 .99
89 27.47 .203 44.44 .207 16.97 29 .99
88 25.37 .175 42.34 .235 16.97 27 .99
87 27.64 .342 40.37 .262 12.73 28 .73
86 34.30 .219 50.50 .198 16.20 35 .93
85 30.27 .201 46.47 .216 16.20 31 .99
84 30.80 .123 50.47 .206 19.67 31 .72
T-2337 82
APPENDIX D(continued)
EVENTEARLIEST TIME LATEST TIME
SLACKORIGINALSCHEDULE
PROBABILITY
EXPECTEDVALUE VARIANCE
EXPECTEDVALUE VARIANCE
83 25.77 .105 45.44 .224 19.67 26 .7682 13.77 .077 33.44 .252 19.67 14 .8081 33.03 .140 50.54 .198 17.51 34 .9980 35.89 .223 50.47 .216 14.58 37 .99
79 32.96 .219 47.54 .220 14.58 34 .9978 28.93 .122 46.44 .216 17.51 30 .9977 32.13 .225 51.47 .198 19.34 33 .9776 29.13 .197 48.47 .226 19.34 30 .9875 •24.20 .179 43.54 .244 19.34 25 .97
74 16.83 .122 49.47 .216 32.64 21 .99
73 12.93 .094 45.57 .244 32.64 17 .99
72 10.03 .076 42.67 .262 32.64 15 .99
71 10.03 .076 43.64 .248 33.61 15 .99
70 19.70 .200 32.22 .316 12.52 20 .75
69 20.27 .106 40.60 .252 20.33 21 .99
68 17.27 .102 36.91 .234 19.64 18 .99
67 13.20 .084 32.84 .252 19,64 14 .99
66 11.10 .056 30.74 .280 19.64 12 .99
65 25.54 .314 38.27 .290 12.73 26 .79
64 15.37 .093 38.53 .466 23.16 16 .98
63 11.97 .091 51.57 .206 39.60 12 .54
T-2337 83
APPENDIX D(continued)
EVENT
EARLIEST TIME LATEST tiMeORIGINALSCHEDULE
PROBABILITY
EXPECTEDVALUE VARIANCE
EXPECTEDVALUE VARIANCE SLACK
62 19.24 .146 42.37 .242 23.13 20 .86
61 17.24 .118 40.37 .270 23.13 18 .99
60 14.93 .068 32.44 .270 17.51 15 .6159 24.03 .191 38.61 .248 14.58 24 .2558 23.10 .187 37.68 .252 14.58 23 .41
57 19.03 .169 33.61 .270 14.58 19 .47
56 15.03 .151 29.61 .288 14.58 15 .22
55 15.03 .151 34.37 .272 19.34 15 .22
54 35.87 .224 35.87 .211 0.0 34 .00
53 13.37 .092 36.53 .467 23.16 14 .98
52 10.00 .090 49.60 .207 39.60 10 .50
51 14.07 .064 37.20 .324 23.13 15 .9950 14.10 .147 30.30 .270 16.20 15 .9949 11.77 .076 31.44 .253 19.67 12 .80
48 11.93 .064 29.44 .274 17.51 12 .6147 12.03 .147 26.61 .292 14.58 12 .22
46 10.07 .160 22.59 .356 12.52 11 .99
45 7.37 .064 21.23 .305 13.86 6 .9944 7.37 .064 21.33 .303 13.96 6 .99
43 7.37 .064 24.34 .346 16.97 6 .99
42 7.37 .064 7.37 .371 0.0 6 .99
T-2337 84
APPENDIX D(continued)
EVENT
EARLIEST TIME LATENT M M ESLACK
ORIGINALSCHEDULE
PROBABILITY
EXPECTEDVALUE VARIANCE
EXPECTEDVALUE VARIANCE
41 7.37 .064 20.10 .540 12.73 6 .99
40 7.37 .064 18.39 .508 11.02 6 .9939 7.37 .064 44.53 .327 37.16 6 .9938 7.37 .064 30.53 .495 23.16 6 .9937 6.90 .036 46.50 .261 39.60 7 .70
36 6.90 .036 30.03 .352 23.13 7 .70
35 6.90 .036 23.10 .381 16.20 7 .70
34 6.90 .036 26.57 .293 19.67 7 .70
33 4.00 .022 26.44 .474 22.44 7 .99
32 6.90 .036 24.41 .302 17.51 7 .70
31 6.90 .036 21.48 .403 14.58 7 .70
30 6.90 .036 39.54 .302 32.64 7 .70
29 4.27 .060 6.30 .375 2.03 4 .14
28 4.24 .046 4.24 .389 0.0 4 .13
27 3.34 .056 5.37 .379 2.03 3 .08
26 3.34 .056 4.37 .399 1.03 3 .08
25 3.34 .056 4.37 .399 1.03 3 .08
24 5.00 .032 20.61 .421 15.61 5 .5023 4.07 .008 18.65 .431 14.58 4 .78
22 2.50 .028 22.14 .308 19.64 3 .99
21 2.17 .028 2.17 .407 0.0 2 .15
T-2337 85
APPENDIX D(continued)
EVENT
EARLIEST TIME LATEST TIME
SLACKORIGINALSCHEDULE
PROBABILITY
EXPECTEDVALUE VARIANCE
EXPECTEDVALUE VARIANCE
20 2.17 .028 4.44 .389 2.27 2 .15
19 2.17 .028 4.44 .389 2.27 2 .1518 2.17 .028 3.20 .427 1.03 2 .1517 1.00 .028 3.37 .403 2.31 1 .50
16 2.00 .004 17.61 .449 15.61 2 .50
15 2.00 .004 18.58 .457 16.38 2 .50
14 2.00 .004 18.38 .457 16.38 2 .50
13 2.00 .004 16.58 .435 14.58 2 .50
12 2.00 .004 17.48 .407 15.48 2 .50
11 2.00 .004 24.44 .492 22.44 2 .50
10 2.00 .004 17.38 .431 15.38 2 .50
9 2.00 .004 17.41 .443 15.41 2 .50
8 2.00 .004 18.48 .407 16.48 2 .50
7 0.0 0 12.52 .516 12.52 - -
6 0.0 0 19.64 .336 19.64 - -
5 0.0 0 0.0 .435 0.0 - -
4 0.0 0 0.0 .435 0.0 - -
3 0.0 0 2.37 .431 2.37 - -
2 0.0 0 14.58 .439 14.58 - -
1 0.0 0 14.58 .439 14.58 - -
T-2337 86
BIBLIOGRAPHY
References Cited
( 1) The PIMS Program Selected Finding, The Strategic
Planning Insitiute, pp. 18-20, (1977).
( 2) Speeches Describing Hendry Marketing Support Sys
tem, Speaking of Hendry, The Hendry Corpor
ation, (1976).
( 3) Ibid., pp. 115-116.
( 4) Clark, R. W., An Introduction to Critical Path
Analysis, Research Paper Stanford Univeristy,
pp. 1-39, (1961).
( 5) Woolsey, R.E.D., and Swanson, H.S., Operations
Research For Immediate Application - A Quick
and Dirty Manual, New York, Harber § Row, pp.
12-13, (1975).
( 6) Kelley, J. E. Jr., Critical-Path Planning and
Scheduling: Mathematical Basis, Operations
Research, Vol. 9, pp. 296-300, (1961).
( 7) Woolsey and Swanson, op. cit., pp. 129-135
( 8) Kelley, loc. cit.( 9) Clark, loc. cit.
(10) Kelley, loc. cit.
T-2337 87
(11) Hillier, F. S., and Lieberman, G. J., Introduction
to Operations Research, San Francisco, Holden-
Day, pp. 225-235, (1967).
(12) Clark, loc. cit.
(13) Huggins, W. H., Flow-Graph Representation of Systems,
Operations Research and Systems Engineering,
Ed. by Flagle, Huggins and Roy, Baltimore,
John Hopkins Press, (1960).
(14 ) Ibid., p . 9.
(15) Mason, S. J., Feedback Theory: Some Properties of
Signal Flow-Graphs, Proceedings of the IRE,
Vol. 41, pp. 1144-11566, (1953).
(16) Mason, S. J, Feedback Theory: Further Properties of
Signal Flow-Graphs, Proceedings of the IRE,
Vol. 44, pp. 920-926, (1956).
(17) Fulkerson, D. R., Increasing the Capacity of a
Network: The Parametric Budget Problem,
Management Science, Vol. 5, pp. 472-483,
(1959).
(18) Woolsey and Swanson, loc. cit.
(19) Hillier and Lieberman, loc. cit.(20) Wiest, J.E., and Levy, F.R., A Management Guide to
PERT/CPM: With GERT/PDM/DCPM and Other Net
works, New Jersey, Prentice-Hall, pp. 5-12,
(1977 ).
T-2337 88
(21) Woolsey and Swanson, loc. cit.
(22) Hillier and Lieberman, loc. cit.
(23) Kelley, loc. cit.
(24) Walker, M. R., and Sayer, J. S., Project Planning
and Scheduling, Report 6959, E. I. DuPont de
Nemours and Co., Delware, (1959).
(25) Clark, loc. cit.
(26) Kelley, J. E., Jr., and Walker, M. R., The Critical
Path Method of Planning and Scheduling, Case
Histories Presented at the 12th Annual Meeting
of the Systems and Procedures Association,
Toronto, pp. 403-411, (1960).
(27) Wiest and Levy, op. cit., pp. 62-73.
(28) Ibid.
(29) Multiple Access Limited, Project Management and Con
trol System, Ontario, Don Mills, p. 1, (1973)
(30) Wiest and Levy, op. cit., p. 80.
(31) Martino, R. L., Critical Path Networks, New York,
Gordon and Breach, p. 48, (1968).
(32) Hillier and Lieberman, loc. cit.
(33) Malcom, Roseboom, Clark, and Frazar, Application of aTechnique for Research and Development Program
Evaluation, Operations Research, Vol. 7, pp.
646-649, (1959).
(34) Hillier and Lieberman, loc. cit.
T-2337 89
(35) MacCrimmon, K. R., and Ryavec, C. A., An Analytical
Study of the PERT Assumptions, Operations
Research, Vol. 12, pp. 16-37, (1964).
(36) Martino, loc. cit.
(37) MacCrimmon and Ryavec, loc. cit.
(38) Martino, op. cit., p. 50.
(39) Hillier and Lieberman, loc. cit.
(40) MacCrimmon and Ryavec, loc. cit.
(41) Hillier and Lieberman, op. cit.,(42) Ibid . , pp. 44-47 .
(43) Ibid. , pp. 225-235 .
(44) Kelley and Walker, op. cit., pp.
(45) Hillier and Lieberman. loc. cit.
(46) MacCrimmon and Ryavec, loc. cit.