Community Electrification and its contribution in Energy Efficiency Context: Fund Allocation...
-
Upload
independent -
Category
Documents
-
view
0 -
download
0
Transcript of Community Electrification and its contribution in Energy Efficiency Context: Fund Allocation...
Community Electrification and its contribution in Energy Efficiency
Context: Fund Allocation Efficiency in Nepal
A Case Study by
Pramod Raj Pokharel
February. 2014
ii
List of Abbreviations
CFL Compact Fluorescent Light Danida Danish International Development Cooperation DCS Distribution Consumer Service DSM Demand Side Management EE Energy Efficiency ESAP Energy Sector Assistance Programm EU Electricity Users EUCs Electricity User’s Cooperatives FY Fiscal year GA General Assembly GIS Geographic Information System GON Government of Nepal GWh Giga Watt Hour KKREP Kailali Kanchanpur Rural electrification Project KKREUO Kailali Kanchanpur Rural Electrification Umbrella Organization Km Kilo meter kV Kilo Volt kVA Kilo Volt Ampere kWh Kilo Watt Hour LC Load Centre LV Low Voltage MIS Management Information System MoF Ministry of Finance MVA Mega Volt Ampere MW Mega Watt MWh Mega Watt Hour Ncell Ncell Pvt. Ltd., Nepal NACEUN National Association of Community Electricity Users-Nepal NEA Nepal Electricity Authority NRs Nepalese Rupees NTC Nepal Telecom RE Rural Electrification SP Service Provider S/Ss Sub-stations TOD Time of Day TSU Technical Support Unit WECS Water and Energy Commission Secretariat Yrs Years
iii
Abstract
Integrated Nepal Power System (INPS) under Nepal Electricity Authority (NEA) has been
sustaining massive system loss and in FY 2012/13 alone INPS bore 1056.7 GWh of loss which
accounted 25.03% of the total available energy in the grid (NEA 2012). Out of these lost units,
738.3 GWh loss (19.03%) was under 33 kV level. This loss termed as Distribution Consumer
Service (DCS) loss includes losses in 33 kV lines, 33/11 kV step-down facility, 11 kV lines,
11/0.4/0.23 kV step-down facility and 0.4/0.23 kV lines. Without loss segregation it is always
confusing to general public to locate the most loss prone areas among these four. Case study of
community electrification can be an advantage in this regard to judge and compare NEA
controlled distribution area in terms of system loss and energy efficiency measures. In the
context where 33 kV lines have at least 10,000 times and 11 kV lines have at least 1,000 times
less losses compared to LV lines for the same amount of power flow in the same circuit
configuration, one can easily guess where significant DCS loss is occurring from. Furthermore,
NEA charges 3% extra on top of the community TOD meter reading to take care of transformer
losses. Knowing the fact that transformers are the most efficient devices and have losses within
1% up to 75% loading, margin contribution from community makes them as if they are metered
at 33 kV level. Under such circumstances, if comparison shows that performance of community
electrification is better than NEA controlled distribution area in terms of loss and load
management then it’s time to think about it seriously. As electrical network is interwoven, better
performance within one tiny segment, though small, may improvise the overall system
performance. Unfortunately, this contribution cannot be quantified easily and is invisibly
absorbed within claimed NEA performances. Case study “Community Electrification” has been
chosen to highlight these features in detail, and to show positive impacts of DSM/EE
intervention through community based distribution services. This study also provides the insight
into the structural and procedural barriers for such interventions.
iv
Highlights of the Report
Residential sector is one of the major users of energy (and electricity) in Nepal. In the context
where nation has provided electricity services to less than 50% of the population, there exists a
huge potential to replace biomass and fossil fuel needs by electricity. But the way present
Integrated Nepal Power System (INPS) is performing, the system loss figure of 25.03% is too
much disappointing. Nepal needs a complete transformation from this loss prone electrical
system and on that accord the least cost approaches is Demand Side Management and Energy
Efficiency Measures (DSM/EE). Individual household characteristic greatly influences the overall
electricity consumption behaviour. Types of lighting bulbs and appliances, electricity use
pattern, avoiding household loads during peak hours (shifting loads) are few of the approaches
within the control of households and this must be strictly followed. And in this regard the
traditional distribution system of NEA does not bother much on this. And community based
distribution system in this regard has an edge over NEA distribution business. So, Nepal has
adopted various model for electrification on trial basis, grid extended community electrification is
one of them. In case of community electrification, electricity cooperative buys bulk power from
Nepal Electricity Authority in subsidized rate and distributes electricity within its areas. The
community organization sets its own tariff and oversees overall distribution business.
Presently there are more than 390 operational community based distribution entities in Nepal.
Among them Kailali Kanchanpur Rural Electrification Umbrella Organization (KKREUO) has a
larger cooperative group of 216 members serving more than 50,000 consumers. These load
centre-based electricity user’s cooperatives (EUCs) were established through KKREP/Danida, a
grid extended rural electrification project in Kailali-Kanchanpur area. The case study has
revealed many encouraging facts about this intervention. The intervention includes a huge
infrastructure development works (hardware part under Danida funding) followed by a software
part implementation under NEA/GoN responsibility.
These community entities till now are performing well and are maintaining distribution system
loss within acceptable range (below 8%) which is far better than nationwide NEA average of
19.03%. All three NEA distribution branches (Dhangadi, Mahendranagar and Tikapur) are
enjoying benefits from their presence and are having quite low annual system losses (in the
range of 15%). But unfortunately these outcomes are not credited to community electrification,
rather have been invisibly absorbed within NEA’s claimed improvement. Through this case
study, an attempt has been made to highlight contributions of this intervention in terms of
v
energy efficiency and demand side management. The summary table below gives observation
summary of KKREP/Danida and 80:20 RE schemes together with approximate outcomes from
the interventions.
Summary table: Highlights of community electrification interventions
S.N. Particulars Quantity
A KKREP model
i. Public fund Investment to community (Danida + GoN); Euro 5,222,945
ii. Community Fund Investment; Euro (approx) 120,000
iii. Functional EUCs (total); nos. 216
iv. EUCs annual energy consumption; GWh 17.67
v. EUCs average annual system loss (@ 7.7%); GWh 1.36
vi. Annual energy saved (compared to NEA @ 19.03% loss); GWh 2.00
vii. Approximate annual net profit from energy business to EUCs; NRs 37,500,000
B 80:20 Scheme under NEA/GoN
i. GoN fund investment; NRs 3600,000,000
ii. Community fund investment, NRs 900,000,000
iii. Functional Community distribution entities (total); nos. 174
iv. Annual energy consumption; GWh 57.33
v. Community average annual system loss (@ 10%); GWh 5.73
vi. Annual energy saved (compared to NEA @ 19.03% loss); GWh 5.17
vii. Approximate annual net profit from energy business; NRs NA
(Source: various, Consultant compilation)
Funds so far accumulated and other regular earnings of these communities if utilized properly,
community based distribution system can be a real alternative to loss prone NEA DCS
business. But this needs strong political commitment which for the time being is missing.
Furthermore, there are various other factors which are hindering the proper adoption of DSM/EE
whether in distribution business or industrial and other sectors. Factors like Investment
biasness; lack of information; low energy price, lack of energy efficient technologies & services,
absence of policy, standards and regulations together with low priority on DSM/EE investments
are few of them. Besides these, unwillingness to change is other hidden social factor which
needs much deeper attention.
Contents Abstract ........................................................................................................................................................ iii
Highlights of the Report ............................................................................................................................... iv
1. Introduction .......................................................................................................................................... 1
2. Objective of the Study .......................................................................................................................... 1
3. Scope of Work ....................................................................................................................................... 1
4. Outputs ................................................................................................................................................. 2
5. Methodology ......................................................................................................................................... 2
6. Limitation and Assumptions ................................................................................................................. 3
7. Sector Overview .................................................................................................................................... 3
7.1 Case Description ........................................................................................................................... 5
7.2 Investment .................................................................................................................................... 7
7.3 Energy Efficiency ........................................................................................................................... 7
7.4 Allocation Efficiency .................................................................................................................... 10
7.5 Energy Efficiency Potential ......................................................................................................... 12
7.6 Barriers ........................................................................................................................................ 14
8. Conclusion and Recommendations..................................................................................................... 16
9. REFERENCES ........................................................................................................................................ 18
List of Tables Table 7.1: Sample EUCs data in Constituency 2 (KKREUO) ........................................................................... 8 Table 7.2: Sample Annual Loss Status of NEA/DCS Branch after EUC operation ......................................... 9 Table 7.3: Data related to Cooperative based distribution entities in Kailali and Kanchanpur .................. 11 Table 7.4: NEA annual data for energy and loss ......................................................................................... 11 Table 8.1: Highlights of community electrification interventions .............................................................. 16 List of Figures Figure: 7-1 Annual Report (NEA 2012/13) .................................................................................................... 4
Figure 7-2: Energy Consumption by Sector; Source: MoF, 2013 .................................................................. 5
Figure 7-3: Untapped irrigational loads in AC 9A and AC 13 respectively .................................................... 8
Figure 7-4: Sample Economic activities in the project area after KKREP implementation ......................... 10
Figure 7-5: Radial feed Vs. Distributed Generation feed ............................................................................ 14
Figure 7-6: Concept barrier in operational mechanism .............................................................................. 15
1
1. Introduction Energy is the backbone of overall development of a country and it is the most essential
basis for people‘s livelihood. However, energy has been a thorny issue in Nepal as it is
neither sufficient to meet the demands nor it is efficiently used. Energy crisis has become
daily rituals in the country and no major investments are made to reduce the demand-supply
gap of electricity for last 10 years. And despite good potential of demand side management
(DSM) and energy efficiency (EE) initiatives in Nepal, neither government nor private sector
has taken these opportunities into priority. Implementation of CFL program under Nepal
electricity Authority is only such notable program showing positive impact of DSM/EE.
Otherwise, recommendations made so far by various national and international studies for
implementing DSM/EE as one of the most cost effective tools for reducing demand supply
gaps have not been adequately considered for public and private investments.
In this context, “Fund Allocation Efficiency” is one of the hot issues in Nepal and many
studies are being carried out to figure out whether the investments justify in terms of return.
Like other sectors, significant amount of investment (both public and private) has already
been poured to Nepalese energy sector. But still, the desired performance is not attained.
To notify relevancy of investment for the deemed objectives, a small area like community
electrification has been chosen for a case study. This study investigates the actual
happenings within the sphere and comes up with its contribution to energy efficiency and
demand side management aspects. This study mainly focuses community based rural
electric entities in far-western part of Nepal.
2. Objective of the Study The objective of this study is to support the main idea of “Fund Allocation Efficiency” through
comprehensive analysis of community based RE entities chosen for the case study. It seeks
and analyses the performance of community electrification, an intervention in rural Kailali
Kanchanpur area and evaluates its contribution in terms of demand side management and
energy efficiency effectiveness against the fund allocation. The case study also focuses on
the main barriers which resisted the sector performance as envisioned by the intervention
program.
3. Scope of Work The scope of work includes, but not limited to;
2
1. Review all relevant documents related to public and private expenditure for distribution infrastructure, demand side management and energy efficiency for consistency
2. Collect information on public and private investments on intervention; including distribution infrastructures, energy efficiency and demand side measures
3. Collect data / information on distribution system performances and system losses (NEA and community based area)
4. Analyse and compare NEA verses community based distribution operation focusing accountability, transparency, accessibility and socio-economic justice issues
5. Analyze allocation efficiency of private and public spending in the case study area for supply side versus DSM/EE
6. Closely quantify the contribution of community electrification intervention in terms of DSM/EE
7. Identify structural and procedural barriers for DSM/EE investments and determine misallocation of funds if any
4. Outputs The following outputs are expected from this assignment for the specified study area:
1. A comprehensive case study of community electrification in terms of;
Investment
Energy efficiency
Allocation efficiency
Energy efficiency potential
2. Critical factors influencing investment decisions in energy infrastructures and DSM/EE in Nepal
3. Recommendations to overcome the identified structural and procedural barriers for making appropriate investment choices in energy infrastructures
5. Methodology The methodology followed is presented below:
Review of all relevant literature (as mentioned above)
Key informants’ interview and stakeholder meetings
Collection of all relevant data from secondary sources
Field visit and first hand data collection (as mush possible)
Data entry, analysis, interpretation and presentation
Concluding final figures and findings
For estimation of potential saving;
3
Potential electrical energy saving; PE =
Where;
Ex is the existing electrical energy intensity (on per unit basis)
Eo is the observed optimized electrical energy intensity (on per unit basis)
n is the number of sample
Q is the total population
And (Ex – Eo) is non-negative (≥ 0).
Here, Ex applies for NEA operated load centers and Eo applies for community operated
load centers (electricity distribution area).
6. Limitation and Assumptions Regarding electrical data, if operators are not using MIS (management information system)
data collection becomes ad-hoc and tedious. Faulty meters (TOD meter, household energy
meters, and feeder tracking meters) can’t be monitored timely and chances of error data are
high. Systematic loss segregation and point to point tracking system can minimize the error.
Unfortunately, neither NEA nor community has adopted such measures. So, our first
assumption is, the data that we collected somehow are acceptable for analysis purpose.
Furthermore, the limitations of the study can be summarized as;
NEA does not have loss segregation below 33 kV means inherent point to point energy tracking is missing and data is not precisely verified
The secondary data available in NEA annual reports are not enough for critical analysis (many data missing) and needs interpolation / pre-assumptions
It was not possible to collect NEA DCS losses from all three branch offices and only Dhangadi branch data has been used for analysis
NEA/DCS branch data are always critical and controversial and many of them do not seem to be realistic
Community consumption and loss data are also not up to date
Due to time and budget constraints, recent data could not be collected and used; only trends were verified
7. Sector Overview Residential sector is one of the major users of energy in Nepal. Compared to other sectors
(Industrial, transport, and agriculture) so far, its energy need is much higher (please refer
Figure 7-2 below). In total energy consumption by fuel types in Nepal (2010/011), the share
4
of electricity is just 2.2% where as fuelwood has highest share of 74.8% (MoF, 2013).
Among the consumed electrical energy, residential sector so far dominates the share with
over 44% as shown in Figure: 7-1 below. In the context where nation has provided electricity
services to less than 50% of the population (MoF, 2013), there exists a huge potential to
replace biomass and fossil fuel needs by electricity. But the way present Integrated Nepal
Power System (INPS) is performing, the system loss figure of 25.03% is too much
disappointing. Nepal needs a complete transformation from this loss prone electrical system
and on this accord the least cost approaches is Demand Side Management and Energy
Efficiency (DSM/EE) measures.
Figure: 7-1 Annual Report (NEA 2012/13)
For efficient electrical distribution system, effective DSM/EE interventions are essential that
helps system loss reduction by reducing circulating load current throughout the network.
Individual household characteristic greatly influences the overall electricity consumption
behaviour. Types of lighting bulbs and appliances, electricity use pattern, avoiding
household loads during peak hours (shifting loads) are few of the approaches within the
control of households and this must be strictly followed. And in this regard the traditional
distribution system of NEA does not bother much on this. And community based distribution
system in this regard has an edge over NEA distribution business. So, Nepal has adopted
various model for electrification on trial basis, community electrification is one of them. In
case of community electrification, electricity cooperative buys bulk power from Nepal
Electricity Authority and distributes electricity within their areas. The community organisation
sets its own tariff and oversees the overall electricity distribution business.
5
It is believed that there exists ample opportunity for efficient operation. There are, however,
no such studies carried out in the past that reveal the load pattern, load curve, types of
bulbs used and other operational characteristics. There are more than 390 operational
electricity cooperatives in Nepal and among them Kailali Kanchanpur Rural Electrification
Umbrella Organisation (KKREUO) has a larger cooperative groups under its umbrella
electrifying more than 50,000 users.
Figure 7-2: Energy Consumption by Sector; Source: MoF, 2013
This case study will reveal many insights on energy efficiency and demand side
management opportunities within community electrification specially focused to KKREUO
area.
7.1 Case Description
In line with 10th Five-Year Plan of GoN where electrification rate was planned to be
extended from 39% to 55% of the population, Danida funded grid extended rural
electrification program “Kailali Kanchanpur Rural Electrification project (KKREP)” came into
scenario (2001-2008) as part of ESAP I. In contrast to NEA’s traditional electrification
approaches, KKREP/Danida was an attempt to enhance service delivery mechanism in
Energy Consumption by Sector
6
distribution sector fostering demand side management and energy efficiency in rural
electricity business.
The model assumed to establish an efficient and cost effective electrical distribution system
owned and operated by local communities in rural areas of Kailali and Kanchanpur. In total,
216 load-centre based Electricity User’s Cooperatives (EUCs) were established. These
EUCs are united under an umbrella called the Kailali Kanchanpur Rural Electrification
Umbrella Organization (KKREUO). This EUC apex body is primarily responsible for
overseeing all the administrative, managerial and technical issues pertaining to the
distribution business of these tiny entities. The program included huge electrical
infrastructure development works. The area had very limited infrastructure available for
distribution purpose before KKREP/Danida was in picture. Three distribution branches
Dhangadi, Mahendranagar and Tikapur had total 13.5 MVA, 33/11 kV capacity serving only
about 16,000 consumers. As 33/11 kV system was overloaded, chances for new consumer
access was limited. All three distribution branches had huge annual loss figures.
Under this intervention, total 19.5 MVA, 33/11 kV system was added through 7 numbers of
new area substations scattered all around Kailali and Kanchanpur. Over two thousand
kilometres of electrical lines (33 kV, 11 kV and 0.4/0.23 kV) were constructed so that
consumers today in the area are almost 7 times up i.e. over 110,000. KKREP/Danida alone
provided service connections to about 50,000 rural households. With these distribution
system reinforcement works, NEA/DCS branch annual loss scenarios in the area have
decreased significantly in recent years. With a communal approach of collective joining,
almost 100% electrification ratio was achieved in the program. This served as one of the
landmark in program’s success where disadvantaged groups (like Dalits and Kamaiyas)
received equal treatment. To transfer distribution system ownership to community, a
household based subsidy of NRs 7200 was provided to grid extended consumers for the
first time. As the subsidy provided to electricity users was not enough to cover costs of the
low voltage distribution system, a 20 year Index loan was implemented.
The success of the program lies in the fact that how the earnings provided to these
community based entities are managed and utilized. Properly using these funds and
opportunity, community owned and operated distribution system can prove that it can deliver
services more efficiently and cost effectively compared to NEA controlled area and can take
care of better DSM/EE roles.
7
7.2 Investment Total investment for KKREP/Danida was Euro 13,407,351 (NRs 1,338,455,850) where
Danida and GoN contributions were as follows;
Out of this total investment, the community was handed over an infrastructure costing Euro
5,222,945 (NRs 513,892,416). The breakdown is given below;
Furthermore, the community got three years of operational support till June 2011 through
ESAP II and investment involved was NRs 15,600,000. In addition to these public
investments in KKREP case, the community itself has constructed over 80 km of electrical
lines (11 kV and LV), installed 19 additional transformers (1,030 kVA, 11/0.4 kV) to electrify
over 3200 new consumers collectively after the project, whose present market value is more
than NRs 120 millions.
Besides KKREP model, 80:20 scheme under NEA is other model of community
electrification where community provides 20% of the electrification cost and rest 80% is
borne by GoN. As per NACEUN, community throughout Nepal so far has contributed NRs
900 million and GoN has added NRs 3600 million to electrify thousands of people under 174
cooperatives scattered all around Nepal.
7.3 Energy Efficiency
As expected, emergence of cooperative based distribution entities has started contributing
better demand side management and energy efficiency in the area. Despite over 365
industrial and 510 irrigation consumers injecting over 6 MW of load burden (source:
KKREUO), EUCs are maintaining their annual system loss within acceptable range. EUCs
do not allow their industrial and irrigation consumers to operate during peak hours (evening
5-9 pm) and follow this as thumb rule for DSM/EE concerns. Every industrial load is bound
to install adequate size of capacitor bank so that good power factor and healthy voltage
profile is maintained. So it’s not surprising to see low range system loss in EUC system. The
Danida Support: Euro 12,199,178 (NRs 1,217,933,957) GoN Support : Euro 1,208,273 (NRs 120,621,894) Source: KKREP Project Completion Report
Part Handed Over to Community LV line cost : Euro 3,159,642 Transformer cost : Euro 855,030 Service Connection Cost : Euro 1,208,273 Source: KKREP Project Completion Report
8
Table 7.1 below shows the average annual loss of 20 EUCs under constituency no. 2 of
KKREUO in FY 2065/66 (2008/09) which is appreciably low with mere 6.6%.
Table 7.1: Sample EUCs data in Constituency 2 (KKREUO)
Source: KKREUO
To keep system loss within acceptable range, many EUCs do not allow connections to new
industrial and irrigation loads until and unless EUC is ensured that new connections do not
deteriorate system loss scenario. Figure 7-3 below show two diesel operated water Pump
Sets both owned by EUC executives, one from AC 9A and other from AC 13 respectively.
They are waiting for right time when their respective EUC will have additional transformer
close to these loads and they can replace them with electric drive. Presently these loads are
far from the existing transformer and will add significant line loss to the system.
Figure 7-3: Untapped irrigational loads in AC 9A and AC 13 respectively
In the beginning EUCs started connecting industrial loads haphazardly and as a result the
line loss scenario increased significantly (15-18%) from the designed value of less than 7%.
Technical Support Unit under KKREUO (under ESAP II funding) then conducted various
load management training sessions to educate technicians of service providers. EUCs were
9
encouraged to invest on CFL for their own benefit. Line up-gradation, use of additional
transformers, relocation of industrial loads, phase balancing like activities were initiated to
take care of undesired system loss. Today in average the EUC system has annual loss
within 8% which is far better compared to NEA controlled distribution areas.
Table 7.2: Sample Annual Loss Status of NEA/DCS Branch after EUC operation
The Table 7.2 above shows the annual loss figures of NEA/DCS Dhangadi branch which
has 37 numbers of EUCs under its supply chain. During 2008/2009, when two area
substations (Jhalari 3 MVA, and Sripur 1.5 MVA) were not charged all 97 EUCs in the area
were supplied by Dhangadi DCS branch. Despite poor voltage profile and heavy loss in
long 11 kV feeders, Dhangadi DCS had amazingly low figure of loss within 21% range. By
that time, connections of industrial and irrigation loads were limited within EUC system and
had mainly household loads from lighting. In 2009/010, project got completed and all 11 kV
feeders got charged. This left Dhangadi DCS with only 37 numbers of EUCs. By this time,
these EUCs also started connecting industrial and irrigation load haphazardly without
following the norms. The result was obvious. The overall system loss scenario increased
drastically. Dhangadi DCS branch’s loss figure for 2009/10 depicts the fact. Then KKREUO
came into action and conducted various DSM/EE awareness programs and trainings. The
result one can see in the following years of 2010/11, 2011/12 and 2012/13. This shows the
usefulness of community based electrification at least to address DSM/EE issues. However,
the loss decreasing trend may also have some implications from NEA’s loss reduction
strategy.
10
7.4 Allocation Efficiency Community electrification in the area has paved ways for enormous economic activities.
Rice mills, sawmills, tailors, computer institutes, electric shops, communication towers
(Ncell, NTC), cold storages, dairy industries, chicken farming etc are few of them. In addition
to these, community earns handsome amount of money from the sale of electricity. These
altogether has changed the overall economical situation of the area in last couple of years.
But even better contribution of community electrification is that, community is expanding its
service area to serve more and more rural people. Few of EUCs are investing their own fund
to initiate network expansion activities. And the best part is no one is left un-electrified. If
needed, EUC provides energy meters, service cables and other accessories to be refunded
later. And here, NEA versus community electrification differs.
Figure 7-4: Sample Economic activities in the project area after KKREP implementation
Although economic activities in these areas would have been similar even under NEA
distribution system, but on the aspects mentioned above NEA stands nowhere in front of
EUCs. Service delivery mechanism, operational approaches with accountability and
transparency and dedication for energy efficiency are definitely superior under community
electrification. Being bulk consumer and an integral part of NEA/DCS branch, efficient EUC
operation in fact gives direct benefit to NEA system in many ways. Improved annual loss
scenario of Dhangadi NEA/DCS branch can be taken as a good example. Seeing
distribution loss trends elsewhere in NEA system, bigger part sharing for loss reduction in
this branch can be assumed from efficient EUC operation. EUCs under Dhangadi branch in
average consume about 5 GWh of annual energy (Table 7.3 below). This annual
consumption figure would have been much bigger if EUCs were not much sensitive about
11
system loss. As mentioned earlier there are many industrial and irrigation loads waiting for
connection. EUCs knowing its limitations (transformer and LV line capacity) are not
connecting these loads within the existing system. These EUCs rather are trying to install
additional transformer near these heavy loads. And in the process, the connection uptakes
are slow. However, If this part of system were not handed over to community and would
have been a part of traditional NEA distribution system, inadequate connection permissions,
haphazard extensions, hooking and pilferage problems would have sealed its fate in similar
fashion like elsewhere under NEA practices.
Table 7.3: Data related to Cooperative based distribution entities in Kailali and Kanchanpur
To figure out actual allocation efficiency one needs to know NEA trends of distribution loss.
Table 7.4 below shows NEA energy data and trends of losses in last two years. Comparing
data of two fiscal years (2011/12 and 2012/13), some good signs are seen at least in terms
of system loss scenario. However, loss figure of 19.03% for the combined Distribution and
Consumer Services (East and West Business Groups) is too high. Compared to such high
loss figures, EUCs in Kailali and Kanchanpur are maintaining very efficient distribution
system with average annual loss figure below 8%.
Table 7.4: NEA annual data for energy and loss
In the year B.S. 2068/69 (2012/13) total energy sold to 216 EUCs is 17.67 GWh (see Table
7.3 above). This figure also includes 3% additional charges on top of the community TOD
12
meter reading to take care of transformer and line losses. This makes as if the community is
metered at 33 kV level and this is how these two NEA’s and community losses are
comparable. Taking average loss figure of 19.03% (as in NEA area), almost 3.36 GWh
annual system loss of KKREUO community can be derived. But in reality, less than 1.36
GWh loss (@ 7.7%) has occurred within community system in the year 2012/13. This
means, KKREUO community has contributed almost 2 GWh of saved energy to INPS. With
the average energy price of NRs 7.95 (Avg. per kWh sale value of NEA, 2012/13), the
community is contributing almost NRs 16 million annually to NEA/Nepal from loss reduction.
And this figure definitely justifies community electrification concept of Danida in Kailali and
Kanchanpur in addition to enormous socio-economic benefits brought into the area.
Moreover, business of 17.67 GWh enables these communities to earn millions annually.
Even with the changed tariff structure, for about 50,000 household consumers the
community gets annually 12 GWh at subsidized rate of NRs 3.6. With an average price of
NRs 7.5/kWh, the gross electricity purchase-sale margin is about 48 millions. EUCs also
collect demand charge per month based on the installed capacity of its consumers. In
average NRs 25 per month per consumer enables community to collect NRs 15 million
annually. So collectively, community has about NRs 63 millions of gross business margin.
Even if 40% is spent as operational expenses, the community is making about NRs 37.5
millions of net profit annually from this distribution business.
KKREP model in this regard should be praised that the benefit of distribution business is
directly reaching to community hands. Now it’s up to the community people how they use
these funds and resources; they either can assume a role of societal changer or become
like small NEA, choice is theirs.
7.5 Energy Efficiency Potential With available funds and resources there exists ample opportunity for energy efficiency in
community electrification. Community based distribution entities throughout Nepal
collectively purchase more than 75 GWh of energy from NEA annually. With KKREUO
experience, one can easily imagine how beneficial this distribution business can be to the
entire rural community. With simple funda “more GWh is consumed, more profit
cooperatives will make”, many fossil fuel based industrial and irrigation loads can be
replaced with electricity. This not only helps cooperatives and consumer businesses but will
equally relieve nation from currency drain-out on fossil fuels.
13
Cooperatives should also promote more efficient electrical appliances in its distribution area.
They can optimize their distribution system as well. Installation of additional transformers
and relocation of existing transformers closer to bigger loads are few most practiced
traditional approaches. Use of bigger sized conductor to reduce radial feed system losses
can still be beneficial to present context. However, the thumb rule of distribution system is:
less the LV line length, better is the system performance. Unfortunately many EUCs have
bigger sized transformers (160 kVA, 100 kVA) with LV lines extending over 4/5 km. Effective
distribution system usually has many small sized transformers each serving only few
consumers in closer periphery.
System optimization as mentioned above costs significant amount of investment and the
process is never ending. So it’s time to think differently and to use the existing infrastructure
as much as possible. The best alternative is to think opposite of radial feed system and go
for hybrid system with distributed generation from renewable resources. Widespread use of
bulk solar generation and injecting power in community owned LV system will be one of the
easiest options. As there is already a bulk consumer meter to monitor cooperative
consumption of NEA energy, there won’t be need for much talked bi-directional meter. And
due to cost constraint no community will be able to generate solar energy more than they
are consuming for the time being. Energy fed in this way avoids the need of bigger sized
conductor and expenses in additional transformer and rehab lines. It will also reinforce the
entire distribution system as the current flowing in the network reduces significantly. The
figure below shows how load sharing can be useful for distribution system reinforcement.
Though theoretical, effective current flowing in the circuitry if is reduced to half and
conductor type throughout circuitry is assumed same, half load sharing from both the ends
can reduce system line loss figure by 75%. Not only this, the improved voltage profile in a
segment provides positive feedback loop to other nodes of the network helping more loss
reduction.
To present context where NEA supply system is highly congested and needs thorough up-
gradation, the best way is to create local generation as much as possible to meet local
energy demand. For the time being, the best loss reduction strategy is – to avoid
transporting much from distance.
14
Figure 7-5: Radial feed Vs. Distributed Generation feed
For bulk generation, now a day solar system are available in less than NRs 250/W. EUCs
under KKREUO alone can install solar system of over 150 kW annually with average local
energy generation of 380 MWh (i.e. saving of about NRs 2.8 million from NEA billing). This
is in addition to the improvised voltage profile and loss reduction (to both NEA and EUC
area). If the same is projected nationwide, almost 600 kW of bulk solar system in total can
be installed per year providing almost 1.5 GWh of local energy and saving of over NRs 11.4
million from NEA billing annually. And perhaps, over 1 GWh loss reduction in entire INPS
system with distributed injections of power reinforcing the system.
7.6 Barriers The main barriers are legal and institutional. In KKREUO case, Danida envisioned KKREP
was an offer to GoN for an effective RE model with following features;
RE implementation with reproduction modality
To demonstrate RE implementation cheaper in contrast to artificial price hiking
Establishing cost-effective, transparent and efficient cooperative based distribution business
Distribution system with MIS/GIS
An alternative to NEA's traditional distribution management approach including 80:20 scheme
RE as a rural community based business through Electricity User’s Cooperatives (EUCs)
Distribution right delegation to community
15
But unfortunately concept barrier became the biggest gap. The following Figure 7-6 below
show what was intended and what was accomplished in KKREP/Danida program.
Danida Envisioned KKREP NEA/GoN Implemented KKREP
Figure 7-6: Concept barrier in operational mechanism
Today EUCs under KKREUO has millions of annual earnings but these funds are not fully
and properly utilized. Political hijacking has jeopardized its mission. As a result, majority of
these EUCs have become like small NEA branch offices abusing funds and resources. The
main reasons for that are;
No one to monitor and control financial, administrative and managerial issues of EUCs
Neither NEA nor Cooperative Department are efficient to take care of such issues
NEA not willing to give Intermediate Authority role to any one (including KKREUO)
KKREUO struggling to get recognition and legal authority to control and look after EUCs affairs
16
Same is the situation with other community based distribution entities elsewhere in the
country. Authorized institution to look after these cooperatives and guide them for better
roles are missing.
8. Conclusion and Recommendations Knowingly or unknowingly community electrification has contributed considerably in
DSM/EE. But unfortunately these outcomes are not quantified and observed, rather have
been invisibly absorbed within NEA’s claimed improvement. Through this study, an attempt
has been made to highlight the contribution of these community electrifications, though little
but significant. Table 8.1 below gives observation summary of KKREP/Danida and 80:20 RE
schemes together with tentative outcomes from the interventions.
Table 8.1: Highlights of community electrification interventions
S.N. Particulars Quantity
A KKREP model
i. Public fund Investment to community (Danida + GoN); Euro 5,222,945
ii. Community Fund Investment; Euro (approx) 120,000
iii. Functional EUCs (total); nos. 216
iv. EUCs annual energy consumption; GWh 17.67
v. EUCs average annual system loss (@ 7.7%); GWh 1.36
vi. Annual energy saved (compared to NEA @ 19.03% loss); GWh 2.00
vii. Tentative annual net profit from energy business to EUCs; mil. NRs 37.5
B 80:20 Scheme under NEA/GoN
i. GoN fund investment; NRs 3600,000,000
ii. Community fund investment, NRs 900,000,000
iii. Functional Community distribution entities (total); nos. 174
iv. Annual energy consumption; GWh 57.33
v. Community average annual system loss (@ 10%); GWh 5.73
vi. Annual energy saved (compared to NEA @ 19.03% loss); GWh 5.17
vii. Tentative annual net profit from energy business; NRs NA
(Source: various, Consultant compilation)
If accumulated funds so far and other regular earnings of these communities are properly
utilized, there exists ample opportunity for efficient operation of these systems. The study
finds it’s already been late to encourage these community entities to invest in the distributed
17
generation concept as described above. After all, the thumb rule for best energy practice is
– “Meet local energy demand by local generation”.
Furthermore, for future interventions following structural and procedural barriers in energy
investment should be minimized and if possible avoided;
Investment biasness – government more focused on supply side (hydropower generation) and very low priority on DSM
Lack of information about DSM/EE; distribution system and Industry can gain a lot from it and financial sector needs to understand that saving is a kind of gaining - to promote financing product to DSM/EE interventions
Energy price being low for residential and industrial sector compared to other neighboring country does not motivate business entities to invest in DSM/EE interventions
Inadequate availability of services related to EE – Almost all the business entities and industries run without energy managers regardless of size of the industry
Unavailability of energy efficient technologies in local market
Absence of clear policy, standards and regulations on equipments and appliances
No financial incentive - Policy should distinguish between energy intensive and energy efficient technologies
Access to investment capital – investment focused more on productivity improvement projects than low priority EE
Unwillingness to change – a hidden social factor responsible for the continuation of bottle-necking attitude to sustain ongoing corrupt system
18
9. REFERENCES
1. Energy Consult (2009), Nepal NEA DSM/EE Project, Task 3: Interim Results on DSM Options based on Energy Audits, the World Bank and Nepal Electricity Authority.
2. Energy Consult (2010), Nepal NEA DSM/EE Project Task 5&6: DSM Action Plan with Policy Recommendations, the World Bank and Nepal Electricity Authority.
3. Energy Consult (2011), Evaluation of Pilot CFL Distribution Program and Capacity Building of DSM Cell, the World Bank and Nepal Electricity Authority.
4. ESCAP (2011). Guidelines for strengthening energy efficiency planning and management in Asia and the Pacific, Economic and Social Commission for Asia and the Pacific, United Nation.
5. GoN/NEA Implemented KKREP; Available at: http://www.kkreuo.org.np/admin/upload/15_GoN%20Adopted%20KKREP%20-%20A%20Case%20of%20Concept%20Barrier.pdf (Accessed on September 5, 2013)
6. KKREP Component Document; Available at: http://www.kkreuo.org.np/index.php?module=library (Accessed on September 5, 2013)
7. KKREP Project Completion Report; Available at: http://www.kkreuo.org.np/index.php?module=library (Accessed on September 5, 2013)
8. Ministry of Finance (MoF), (2013). Economic Survey. Kathmandu, Nepal.
9. Ministry of Finance (MoF), (2010). Economic Survey. Kathmandu, Nepal.
10. NEA (2012), Nepal Electricity Authority, A Year in Review Fiscal Year 2011/012. Durbarmarg, Nepal.
11. NEA (2013), Nepal Electricity Authority, A Year in Review Fiscal Year 2012/013. Durbarmarg, Nepal.
12. PACE Nepal, (2012). Baseline study of selected sector industries to assess the potentials for more efficient use of energy , Nepal Energy Efficiency Programme (NEEP)/GIZ
13. Proposal of KKREUO for Redefinition of Index loan: Available at: http://www.kkreuo.org.np/index.php?module=library (Accessed on September 5, 2013)