bahagian : 5.0 - kos sewa loji / jentera

31
BAHAGIAN : 5.0 - KOS SEWA LOJI / JENTERA Kawasan A - Perlis, Kedah, & P. Pinang Kawasan D - Johor Kawasan B - Perak Kawasan E - Pahang Kawasan C - WP.KL , Selangor Kawasan F - Terengganu N. Sembilan & Melaka & Kelantan BIL. KETERANGAN KERJA UNIT JULAT JULAT PURATA JULAT PURATA JULAT PURATA JULAT PURATA JULAT PURATA JULAT PURATA (RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM) Excavation Plant 1 Backhoe (Wheel) up to 0.4 m3 hour 30.00 - 33.88 30.00 - 35.00 35.00 - 36.00 - - 30.00 - 35.00 25.00 - 37.00 25.00 - 35.38 40.00 40.00 37.50 37.50 60.00 60.00 2 Ditto over 0.4 m3 hour - - - - - 40.00 - - - 31.25 30.00 - 43.00 30.00 - 38.08 60.00 60.00 3 Ditto over 1.0 m3 up to and including 2.0 m3. hour - - - - - 50.00 - - - - - - 50.00 4 Ditto over 2.0 m3 up to and including 4.0 m3. hour - - - - - 55.00 - - - - - - 55.00 5 Backhoe Excavator ( Case 580 ) hour 30.00 - 34.17 - - 35.00 - 47.60 - - - - 31.00 - 40.50 30.00 - 40.76 37.50 65.00 50.00 65.00 6 Dragline RB 19 hour - 40.00 25.00 - 30.00 30.00 - 42.32 - 71.00 - - - - 25.00 - 45.83 35.00 56.25 71.00 7 Ditto RB 22 hour 43.75 - 46.88 30.00 - 35.00 35.00 - 50.22 - 81.00 - - - - 30.00 - 53.28 50.00 40.00 70.00 81.00 8 Ditto RB 24 hour - - - - 45.00 - 62.00 - - - - - - 45.00 - 62.00 75.00 75.00 9 Ditto RB 30 hour - 80.00 35.00 - 42.50 - 75.00 - - - - - - 35.00 - 65.83 50.00 80.00 c: lojij KAWASAN E KAWASAN F KESELURUHAN KAWASAN B KAWASAN C KAWASAN D KAWASAN A

Transcript of bahagian : 5.0 - kos sewa loji / jentera

BAHAGIAN : 5.0 - KOS SEWA LOJI / JENTERAKawasan A - Perlis, Kedah, & P. Pinang Kawasan D - Johor

Kawasan B - Perak Kawasan E - PahangKawasan C - WP.KL , Selangor Kawasan F - Terengganu

N. Sembilan & Melaka & Kelantan

BIL. KETERANGAN KERJA UNIT JULAT JULAT PURATA JULAT PURATA JULAT PURATA JULAT PURATA JULAT PURATA JULAT PURATA(RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM)

Excavation Plant

1 Backhoe (Wheel) up to 0.4 m3 hour 30.00 - 33.88 30.00 - 35.00 35.00 - 36.00 - - 30.00 - 35.00 25.00 - 37.00 25.00 - 35.3840.00 40.00 37.50 37.50 60.00 60.00

2 Ditto over 0.4 m3 hour - - - - - 40.00 - - - 31.25 30.00 - 43.00 30.00 - 38.0860.00 60.00

3 Ditto over 1.0 m3 up to and including 2.0 m3. hour - - - - - 50.00 - - - - - - 50.00

4 Ditto over 2.0 m3 up to and including 4.0 m3. hour - - - - - 55.00 - - - - - - 55.00

5 Backhoe Excavator ( Case 580 ) hour 30.00 - 34.17 - - 35.00 - 47.60 - - - - 31.00 - 40.50 30.00 - 40.7637.50 65.00 50.00 65.00

6 Dragline RB 19 hour - 40.00 25.00 - 30.00 30.00 - 42.32 - 71.00 - - - - 25.00 - 45.8335.00 56.25 71.00

7 Ditto RB 22 hour 43.75 - 46.88 30.00 - 35.00 35.00 - 50.22 - 81.00 - - - - 30.00 - 53.2850.00 40.00 70.00 81.00

8 Ditto RB 24 hour - - - - 45.00 - 62.00 - - - - - - 45.00 - 62.0075.00 75.00

9 Ditto RB 30 hour - 80.00 35.00 - 42.50 - 75.00 - - - - - - 35.00 - 65.8350.00 80.00

c: lojij

KAWASAN E KAWASAN F KESELURUHANKAWASAN B KAWASAN C KAWASAN DKAWASAN A

BAHAGIAN : 5.0 - KOS SEWA LOJI / JENTERAKawasan A - Perlis, Kedah, & P. Pinang Kawasan D - Johor

Kawasan B - Perak Kawasan E - PahangKawasan C - WP.KL , Selangor Kawasan F - Terengganu

N. Sembilan & Melaka & Kelantan

BIL. KETERANGAN KERJA UNIT JULAT JULAT PURATA JULAT PURATA JULAT PURATA JULAT PURATA JULAT PURATA JULAT PURATA(RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM)

Excavation Plant ( cont'd )

10 Dragline RB 38 hour - - - - 80.00 - 100.00 - - - - - - 80.00 - 100.00150.00 150.00

11 Ditto RB 61 hour - - - - - 190.00 - - - - - - - 190.00

12 Ditto RB 71 hour - - - - - 190.00 - - - - - - - 190.00

13 Dragline Excavator per 0.38 m3 (1/2 cu. Yd. ) hour 45.00 - 57.50 - - - - - - - - - - 45.00 - 57.5070.00 70.00

14 Ditto per 0.57m3 ( 3/4 cu. Yd.) hour - 60.00 - - - - - - - 55.00 45.00 - 61.00 45.00 - 58.6780.00 80.00

15 Ditto per 2.29 m3 ( 3 cu. Yd. ) hour - - - - - - - - - - 30.00 - 46.67 30.00 - 46.6775.00 75.00

16 Hydraulic Excavator Track Type up to 1 m3 hour - - - - - - - - - - 43.75 - 63.60 43.75 - 63.6080.00 80.00

17 Ditto over 1 m3. hour - - - - - - - - - - 50.00 - 67.50 50.00 - 67.5090.00 90.00

18 Excavator - hydraulic operated up to 0.5m3 hour 45.00 - 51.20 32.00 - 41.00 35.00 - 48.94 63.00 63.00 31.25 - 46.88 50.00 - 64.17 31.25 - 52.5356.00 50.00 62.00 62.50 80.00 80.00

c: lojij

KAWASAN A KAWASAN B KAWASAN C KAWASAN D KAWASAN E KAWASAN F KESELURUHAN

BAHAGIAN : 5.0 - KOS SEWA LOJI / JENTERAKawasan A - Perlis, Kedah, & P. Pinang Kawasan D - Johor

Kawasan B - Perak Kawasan E - PahangKawasan C - WP.KL , Selangor Kawasan F - Terengganu

N. Sembilan & Melaka & Kelantan

BIL. KETERANGAN KERJA UNIT JULAT JULAT PURATA JULAT PURATA JULAT PURATA JULAT PURATA JULAT PURATA JULAT PURATA(RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM)

Excavation Plant ( cont'd )

19 Excavator - hydraulic operated up to 1.0 m3 hour 50.00 - 58.25 35.00 - 45.00 55.00 - 57.08 - - - - 50.00 - 53.13 35.00 - 53.3765.00 55.00 60.00 56.25 65.00

20 Ditto over 1.0 m3 up to 1.5 m3 hour 65.00 - 70.00 44.00 - 52.00 - 64.00 - - - - - - 44.00 - 62.0075.00 60.00 75.00

21 Ditto over 1.5 m3. hour - - - - - 80.00 - - - - - - - 80.00

22 Excavator CAT 300 hour - - - - 56.25 - 66.56 - - - - - - 56.25 - 66.5690.00 90.00

23 Excavator 0.25 m3 hour - 43.75 - 50.00 31.25 - 44.17 - 70.00 - 62.50 55.00 - 65.00 31.25 - 55.9062.50 80.00 80.00

24 Face shovel / dragline / skimmer and backactors up to hour - - - - - - - - - - - 39.00 - 39.00and including 0.5 m3

25 Ditto over 0.5 m3 up to and including 1.0 m3 hour - 55.00 - - 35.00 - 48.33 - 62.50 - - 31.00 - 48.22 31.00 - 53.5160.00 68.75 68.75

26 Ditto over 1.0 m3 up to and including 2.0 m3 hour 70.00 - 72.50 - - - 70.00 - 81.25 - 81.25 50.00 - 67.25 50.00 - 74.4575.00 81.25 81.25

27 Ditto over 2.0 m3 up to and including 4.0 m3 hour - 80.00 - - 80.00 - 85.00 - 112.50 - - - - 80.00 - 92.5090.00 112.50

c: lojij

KAWASAN F KESELURUHANKAWASAN A KAWASAN B KAWASAN C KAWASAN D KAWASAN E

BAHAGIAN : 5.0 - KOS SEWA LOJI / JENTERAKawasan A - Perlis, Kedah, & P. Pinang Kawasan D - Johor

Kawasan B - Perak Kawasan E - PahangKawasan C - WP.KL , Selangor Kawasan F - Terengganu

N. Sembilan & Melaka & Kelantan

BIL. KETERANGAN KERJA UNIT JULAT JULAT PURATA JULAT PURATA JULAT PURATA JULAT PURATA JULAT PURATA JULAT PURATA(RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM)

Excavation Plant ( cont'd )

28 Face shovel / dragline / skimmer and backactors over 4.0 m3. hour - - - - - - - - - - - 100.00 - 100.00

29 Excavator, face, shovel or dragline including hour 35.00 - 52.88 - 32.00 31.25 - 49.38 - 50.00 - - 43.75 - 62.48 31.25 - 49.35use of crane up to and including 1.0 m3. 85.00 75.00 80.00 85.00

30 Ditto over 1.0 m3 up to and including 2.0 m3 hour 35.00 - 57.63 - 44.00 52.50 - 62.33 - 70.00 - - 50.00 - 71.63 35.00 - 61.1275.00 81.25 90 90.00

31 Ditto over 2.0 m3. hour - - - - - - - - - - 32.00 - 46.00 32.00 - 46.0060.00 60.00

32 Trench Digger Track Type up to 60 hp. hour - - - - - - - - - - 32.00 - 46.00 32.00 - 46.0060.00 60.00

33 Ditto 90 hp. hour - - - - - - - - - - 37.00 - 58.5 37.00 - 58.5080.00 80.00

34 Shovel hour - 35.00 - - 60.00 - 61.25 - - - - 20.00 - 37.50 20.00 - 44.5865.00 55.00 65.00

35 Grader up to 3.5 m blade. hour 25.00 - 44.77 - 57.00 31.25 - 56.64 - 60.00 - - 50.00 - 63.47 25.00 - 56.3855.00 100.00 81.25 100.00

36 Ditto over 3.5 m blade hour - - - 63.00 37.50 - 71.19 - 50.00 - - 53.13 - 69.39 37.50 - 63.40125.00 90.00 125.00

c: lojij

KAWASAN F KESELURUHANKAWASAN A KAWASAN B KAWASAN C KAWASAN D KAWASAN E

BAHAGIAN : 5.0 - KOS SEWA LOJI / JENTERAKawasan A - Perlis, Kedah, & P. Pinang Kawasan D - Johor

Kawasan B - Perak Kawasan E - PahangKawasan C - WP.KL , Selangor Kawasan F - Terengganu

N. Sembilan & Melaka & Kelantan

BIL. KETERANGAN KERJA UNIT JULAT JULAT PURATA JULAT PURATA JULAT PURATA JULAT PURATA JULAT PURATA JULAT PURATA(RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM)

Excavation Plant ( cont'd )

37 Grader 12E or equivalent. hour - - - - 60.00 - 67.01 - - - - - 47.00 47.00 - 57.0180.00 80.00

38 Ditto 14E or equivalent. hour - - - - 75.00 - 79.00 - - - - - - 75.00 - 79.0090.00 90.00

39 Grader (self propelled), 90 - 140 drawbar. hour - - - - - 47.50 - - - - - - - 47.50

40 Grader CAT 112F or equivalent. hour - - - - - - - - - - 30.00 - 55.00 30.00 - 55.0070.00 70.00

41 Grader up to and Including 60 Kw. hour - 40.00 - - - 40.00 - 75.00 - - - - 40.00 - 51.6775.00

43 Ditto over 60 Kw. hour - 50.00 - - - 60.00 - 75.00 - - - - 50.00 - 61.6775.00

44 Scraper over 280 hp. hour - - - - - 40.75 - - - - - - - 40.75

45 Scraper self loading 705 m3 hour - - - - - - - - - - - 100.00 - 100.00

46 Ditto 11.5 m3 hour - - - - - - - - - - - 120.00 - 120.00

c: lojij

KAWASAN B KAWASAN C KAWASAN D KAWASAN E KAWASAN F KESELURUHANKAWASAN A

BAHAGIAN : 5.0 - KOS SEWA LOJI / JENTERAKawasan A - Perlis, Kedah, & P. Pinang Kawasan D - Johor

Kawasan B - Perak Kawasan E - PahangKawasan C - WP.KL , Selangor Kawasan F - Terengganu

N. Sembilan & Melaka & Kelantan

BIL. KETERANGAN KERJA UNIT JULAT JULAT PURATA JULAT PURATA JULAT PURATA JULAT PURATA JULAT PURATA JULAT PURATA(RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM)

Compressed Air Equipment

47 Compressor, portable with breakers, rock drills, air lines, hour 30.00 - 43.37 - 38 20.00 - 30.16 31.00 - 50.50 - 25.00 60.00 - 62.5 20.00 - 41.59lubricator and steel up to and including 3 m3/min. 50.00 60.00 70.00 65.00 70.00

48 Ditto over 3 m3/min, up to and including 5 m3/min. hour 32.00 - 38.00 - - 25.00 - 36.88 40.00 - 44.00 - 37.50 18.00 - 25.38 18.00 - 36.3545.00 60.00 48.00 39.00 60.00

49 Ditto over 5 m3/min, up to and including 10 m3/min. hour 45.00 - 49.25 - 100.00 40.00 - 63.00 60.00 - 72.50 - - 20.00 - 37.71 20.00 - 64.4957.00 75.00 85.00 80.00 100.00

50 Ditto over 10 m3/min, up to and including 15 m3/min. hour 50.00 - 58.33 - - 67.00 - 78.50 - - - - 20.00 - 26.16 20.00 - 54.3365.00 90.00 50.00 90.00

51 Ditto over 15 m3/min hour - - - - - 120.00 - - - - 22.00 - 35.64 22.00 - 77.8290.00 120.00

52 Single tool compressor up to 4.3 m3/min. hour - - - - 25.00 - 38.75 - - - - - - 25.00 - 38.7550.00 50.00

53 Two tools compressor up to and including 6 m3/min. hour - - - - 30.00 - 45.00 - - - - - - 30.00 - 45.0060.00 60.00

54 Three tools compressor up to and including 9 m3/min. hour - - - - 35.00 - 56.00 - - - - - - 35.00 - 56.0080.00 80.00

c: lojij

KAWASAN B KAWASAN C KAWASAN D KAWASAN E KAWASAN F KESELURUHANKAWASAN A

BAHAGIAN : 5.0 - KOS SEWA LOJI / JENTERAKawasan A - Perlis, Kedah, & P. Pinang Kawasan D - Johor

Kawasan B - Perak Kawasan E - PahangKawasan C - WP.KL , Selangor Kawasan F - Terengganu

N. Sembilan & Melaka & Kelantan

BIL. KETERANGAN KERJA UNIT JULAT JULAT PURATA JULAT PURATA JULAT PURATA JULAT PURATA JULAT PURATA JULAT PURATA(RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM)

Compressed Air Equipment ( cont'd )

55 Mobile compressor including tools and hoses up to 2 m3/min. hour - - - - - 60.00 - - - - - - - 60.00

Pumping Plant

56 Pumps, portable including hoses, strainer, etc. - 50 mm delivery. hour 9.00 - 15.88 - 12.00 10.00 - 18.94 10.00 - 19.67 - 10.00 10.00 - 15.94 9.00 - 15.4120.00 35.00 30.00 50.00 50.00

57 Ditto, 75 mm. hour - - - - - - - - - 15.00 - 20.00 15.00 - 7.0020.00

58 Ditto, 100 mm hour 12.00 - 20.57 12.00 - 14.00 12.00 - 27.08 - 20.00 - - 15.00 - 25.82 12.00 - 21.4930.00 15.00 45.00 40.00 45.00

59 Ditto, 150 mm. hour 20.00 - 27.33 15.00 - 17.33 12.00 - 35.56 25.00 - 32.50 - - 10.00 - 36.56 10.00 - 29.8635.00 20.00 55.00 40.00 80.00 80.00

60 Ditto, over 150 mm. hour 30.00 - 34.58 17.00 - 20.67 15.00 - 43.12 30.00 - 40.00 - 20.00 30.00 - 63.00 15.00 - 36.9043.75 25.00 75.00 50.00 90.00 90.00

61 Ditto over 200 mm. hour - - - - - - - - - - - 36.00 - 36.00

c: lojij

KAWASAN B KAWASAN C KAWASAN DKAWASAN A KAWASAN E KAWASAN F KESELURUHAN

BAHAGIAN : 5.0 - KOS SEWA LOJI / JENTERAKawasan A - Perlis, Kedah, & P. Pinang Kawasan D - Johor

Kawasan B - Perak Kawasan E - PahangKawasan C - WP.KL , Selangor Kawasan F - Terengganu

N. Sembilan & Melaka & Kelantan

BIL. KETERANGAN KERJA UNIT JULAT JULAT PURATA JULAT PURATA JULAT PURATA JULAT PURATA JULAT PURATA JULAT PURATA(RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM)

Pumping Plant ( cont'd )

62 Power operated pumps self primary centrifugal 75 mm ( 3" ) hour - - - - 15.00 - 21.25 - - - 12.50 - - 12.50 - 16.8825.00 25.00

63 Ditto 150 mm ( 6" ) hour - 20.00 - - 22.50 - 28.13 - 18.00 - - 11.00 - 31.00 11.00 - 24.2835.00 62.00 62.00

64 Power operated pumps - submersible electric 75 mm ( 3" ) hour - - - - 18.75 - 30.75 - - - - - - 18.75 - 30.7560.00 60.00

65 Ditto 150 mm ( 6" ) hour - - - - 25.00 - 39.17 - - - - - 35.00 25.00 - 37.0975.00 75.00

66 Grout Pump hour - - - - - 35.00 - - - - - - - 35.00

Tractor

67 Agriculture ( Farm ) Tractor hour 23.00 - 28.08 30 .00 - 40.00 25.00 - 34.71 - - - - 25.00 - 40.25 23.00 - 35.7631.25 50.00 62.5 60.00 62.50

68 Tractor with bull or angle dozer up to 60 hp. hour - - - - 30.00 - 53.75 - - - - - 33.00 30.00 - 43.3865.00 65.00

c: lojij

KAWASAN B KAWASAN C KAWASAN DKAWASAN A KAWASAN E KAWASAN F KESELURUHAN

BAHAGIAN : 5.0 - KOS SEWA LOJI / JENTERAKawasan A - Perlis, Kedah, & P. Pinang Kawasan D - Johor

Kawasan B - Perak Kawasan E - PahangKawasan C - WP.KL , Selangor Kawasan F - Terengganu

N. Sembilan & Melaka & Kelantan

BIL. KETERANGAN KERJA UNIT JULAT JULAT PURATA JULAT PURATA JULAT PURATA JULAT PURATA JULAT PURATA JULAT PURATA(RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM)

Tractor ( cont'd )

69 Tractor with bull or angle dozer over 60 hp. Up to 90 hp. hour 27.50 - 33.75 - - - - - - - - 40.00 - 45.00 27.50 - 39.3840.00 50.00 50.00

70 Ditto over 90 hp. hour - 35.00 - - - - - - - - - 60.00 35.00 - 47.5060.00

71 Ditto over 120 hp. hour - - - - - 30.00 - - - - - - - 30.00

72 Ditto over 150 hp. hour - - - - 45.00 - 55.00 - - - - - - 45.00 - 55.0065.00 65.00

73 Ditto over 180 hp. hour - - - - 60.00 - 72.14 - - - - - - 60.00 - 72.1495.00 95.00

74 Ditto over 220 hp. hour - - - - 65.00 - 95.00 - - - - - - 65.00 - 95.00125.00 125.0

75 Tractor, backpusher. hour - 20.00 - 30.00 - 30.00 - - - - - 50.00 20.00 - 32.5050.00

76 Tractor, Pneumatic Tyre with scraper 112 hp / 83 kw. hour - - - - - - - - - - 37.00 - 58.50 37.00 - 58.5080.0 80.00

c: lojij

KAWASAN B KAWASAN C KAWASAN DKAWASAN A KAWASAN E KAWASAN F KESELURUHAN

BAHAGIAN : 5.0 - KOS SEWA LOJI / JENTERAKawasan A - Perlis, Kedah, & P. Pinang Kawasan D - Johor

Kawasan B - Perak Kawasan E - PahangKawasan C - WP.KL , Selangor Kawasan F - Terengganu

N. Sembilan & Melaka & Kelantan

BIL. KETERANGAN KERJA UNIT JULAT JULAT PURATA JULAT PURATA JULAT PURATA JULAT PURATA JULAT PURATA JULAT PURATA(RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM)

Tractor ( cont'd )

77 Tractor, Pneumatic Tyre with scraper 250 hp. hour - - - - - 80.00 - - - - - - - 80.00

78 Tractor with low ground pressure arrangement including hour 40.00 - 57.50 - - - - - - - - 32.00 - 54.00 32.00 - 55.75bull or angle dozer or ripper up to and including 70 kw. 75.00 60.00 75.00

79 Ditto over 70 kw up to 120 kw hour 45.00 - 65.00 - - - - - - - - 31.50 - 53.40 31.50 - 59.2085.00 100.00 100.00

80 Tractor track type including bull or angle dozer or ripper hour - 50.00 - - - - - - - - 20.00 - 34.20 20.00 - 42.10up to and including 70 kw. 50.00 50.00

81 Ditto over 70 kw. hour - 60.00 - - - - - - - - 22.50 - 38.70 22.50 - 49.3550.00 60.00

82 Tractor bull or angle dozer up to and including 40 kw ( Drawbar ) hour - 35.00 - - 30.00 - 47.50 - 62.50 - - - - 30.00 - 48.3365.00 65.00

83 Ditto over 40 kw up to and including 70 kw. hour 35.00 - 40.00 - - - 40.00 - 68.75 - - 25.00 - 27.50 25.00 - 44.0645.00 30.00 68.75

84 Ditto over 70 kw up to and including 120 kw. hour 46.00 - 47.50 - - - 60.00 - 68.75 - - 45.00 45.00 45.00 - 55.3155.00 68.75

c: lojij

KAWASAN B KAWASAN C KAWASAN DKAWASAN A KAWASAN E KAWASAN F KESELURUHAN

BAHAGIAN : 5.0 - KOS SEWA LOJI / JENTERAKawasan A - Perlis, Kedah, & P. Pinang Kawasan D - Johor

Kawasan B - Perak Kawasan E - PahangKawasan C - WP.KL , Selangor Kawasan F - Terengganu

N. Sembilan & Melaka & Kelantan

BIL. KETERANGAN KERJA UNIT JULAT JULAT PURATA JULAT PURATA JULAT PURATA JULAT PURATA JULAT PURATA JULAT PURATA(RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM)

Tractor ( cont'd )

85 Ditto over 120 kw up to and including 160 kw. hour - 65.00 - - 60.00 - 61.67 - 81.25 - - - - 60.00 - 69.3165.00 81.25

86 Ditto over 160 kw up to and including 200 kw. hour - 75.00 - - 90.00 - 91.67 - 81.25 - - - - 75.00 - 82.6495.00 95.00

87 Ditto over 200 kw up to and including 250 hour - - - - 120.00 - 121.67 - - - - - - 120.00 - 121.67125.00 125.00

88 Tractor, bull or angle dozer with shovel and generating set hour - - - - - - - - - - 20.00 - 42.00 20.00 - 42.001.1 m3. 80.00 80.00

Bulldozer

89 Bulldozer D4 hour 31.25 - 35.63 37.00 - 68.50 - 72.50 - - - - - - 31.25 - 58.8840.00 100.00 100.00

90 Ditto , 250 hp. hour - - - - - - - - 68.75 - 75.00 - - 68.75 - 75.0081.25 81.25

91 Ditto D6 hour - 50.00 40.00 - 80.00 - - - - - - 50.00 - 63.95 40.00 - 64.65120.00 80.00 120.00

c: lojij

KAWASAN B KAWASAN C KAWASAN DKAWASAN A KAWASAN E KAWASAN F KESELURUHAN

BAHAGIAN : 5.0 - KOS SEWA LOJI / JENTERAKawasan A - Perlis, Kedah, & P. Pinang Kawasan D - Johor

Kawasan B - Perak Kawasan E - PahangKawasan C - WP.KL , Selangor Kawasan F - Terengganu

N. Sembilan & Melaka & Kelantan

BIL. KETERANGAN KERJA UNIT JULAT JULAT PURATA JULAT PURATA JULAT PURATA JULAT PURATA JULAT PURATA JULAT PURATA(RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM)

Bulldozer ( cont'd )

92 Bulldozer D8 hour - 80.00 44.00 - 97.00 - - - - - - - - 44.00 - 88.50150.00 150.00

93 Bulldozer CAT, 3 m3 hour - - - - 37.50 - 53.50 - - - - - - 37.50 - 53.5063.00 63.00

94 Ditto 4.2 m3. hour - - - - - 78.00 - - - - - - - 78.00

Piling Plant

95 25 ft. / 8 m. Pile Frame, boiler,winch and 1 ton drop hammer or hour 25.00 - 46.86 55.00 - 59.00 25.00 - 53.68 - 50.00 - - 50.00 - 98.25 25.00 - 61.56equivalent 75.00 63.00 75.00 120.00 120.00

96 60 ft. / 20 m. ditto. hour 50.00 - 61.88 - 100.00 56.25 - 88.94 - 70.00 - - 62.50 - 122.50 50.00 - 88.6680.00 125.00 150.00 150.00

97 Bakau Piling Frame hour - - - - 43.75 - 47.92 - 55.00 - - - - 43.75 - 51.4650.00 55.00

98 5 ton diesel hammer. hour - - - - - 93.75 - - - - - - - 93.75

c: lojij

KAWASAN B KAWASAN C KAWASAN DKAWASAN A KAWASAN E KAWASAN F KESELURUHAN

BAHAGIAN : 5.0 - KOS SEWA LOJI / JENTERAKawasan A - Perlis, Kedah, & P. Pinang Kawasan D - Johor

Kawasan B - Perak Kawasan E - PahangKawasan C - WP.KL , Selangor Kawasan F - Terengganu

N. Sembilan & Melaka & Kelantan

BIL. KETERANGAN KERJA UNIT JULAT JULAT PURATA JULAT PURATA JULAT PURATA JULAT PURATA JULAT PURATA JULAT PURATA(RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM)

Piling Plant (cont'd )

96 Pile Driver - Gravity Hammer hour - - - - - - - - - - 45.00 - 53.89 45.00 - 53.8975.00 75.00

97 Three ton Vibro - Hammer including generator. hour - - - - - 43.75 - - - - - - - 43.75

98 Pneumatic Jackhammer hour - - - - - 15.00 - - - - 10.00 - 25.66 43.75 20.3350.00

99 Hydraulic Vibro Hammer - 5 ton hour - - - - - 65.00 - - - - - - - 65.00

100 Ditto 7 ton hour - - - - - 100.00 - - - - - - - 100.00

Concrete Mixing Plant

101 Concrete mixer - 0.6 m3 output. hour 8.00 - 19.60 - - - - - - - - 5.00 - 17.00 5.00 - 18.3030.00 30.00 30.00

102 Ditto 1.0 m3 hour 10.00 - 25.06 - 25.00 12.5 - 29.13 - 25.00 - - 10.00 - 38.03 10.00 - 28.4440.00 56.25 60.00 60.00

c: lojij

KAWASAN E KAWASAN F KESELURUHANKAWASAN B KAWASAN C KAWASAN DKAWASAN A

BAHAGIAN : 5.0 - KOS SEWA LOJI / JENTERAKawasan A - Perlis, Kedah, & P. Pinang Kawasan D - Johor

Kawasan B - Perak Kawasan E - PahangKawasan C - WP.KL , Selangor Kawasan F - Terengganu

N. Sembilan & Melaka & Kelantan

BIL. KETERANGAN KERJA UNIT JULAT JULAT PURATA JULAT PURATA JULAT PURATA JULAT PURATA JULAT PURATA JULAT PURATA(RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM)

Concrete Mixing Plant (cont'd )

103 Central Concrete Mixing Plant complete including fuel and hour 20.00 - 65.83 - 130.00 80.00 - 95.00 - 40.00 - - 40.00 - 68.75 20.00 - 79.92all consumable spares. 125.00 120.00 80.00 130.00

104 Concrete mixer :

a) 14/10 hour 12.00 - 16.00 27.00 - 28.50 12.50 - 19.30 23.00 - 31.50 15.00 - 36.25 15.00 - 18.50 12.00 - 25.0120.00 30.00 30.00 40.00 62.50 38.00 62.50

b ) 7/5 hour 10.00 - 14.00 15.00 - 17.50 - 20.00 - 20.00 - 5.00 - - 5.00 - 15.3018.00 20.00 20.00

c) 10/7 ( 0.3 m3/hr. ) hour 10.00 - 12.00 25.00 - 26.50 15.00 - 20.00 - 30.00 10.00 - 26.25 - 56.25 10.00 - 28.5014.00 28.00 25.00 50.00 56.25

d) 21/14 ( 2.0 m3/hr. ) hour - 15.00 30.00 - 35.00 - 30.00 - - - - - 60.00 15.00 - 35.0040.00 60.00

e) Five ton hour - - - - 10.00 - 27.25 - 32.00 - - - - 10.00 - 29.6349.00 49.00

f) Open Drum 0.5 m3 hour - - - - - - - - - - 18.00 - 28.50 18.00 - 28.5040.00 40.00

c: lojij

KAWASAN B KAWASAN C KAWASAN D KAWASAN E KAWASAN F KESELURUHANKAWASAN A

BAHAGIAN : 5.0 - KOS SEWA LOJI / JENTERAKawasan A - Perlis, Kedah, & P. Pinang Kawasan D - Johor

Kawasan B - Perak Kawasan E - PahangKawasan C - WP.KL , Selangor Kawasan F - Terengganu

N. Sembilan & Melaka & Kelantan

BIL. KETERANGAN KERJA UNIT JULAT JULAT PURATA JULAT PURATA JULAT PURATA JULAT PURATA JULAT PURATA JULAT PURATA(RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM)

Concrete Plant

105 Concrete vibrators, immersion type petrol driven or air driven hour 5.00 - 16.33 - 15.00 25.00 - 33.37 - 18.00 - - 18.00 - 27.32 5.00 - 22.00excluding compressor up to and including 75 mm. 25.00 50.00 60.00 60.00

106 Ditto over 75 mm. hour 20.00 - 29.50 - 20.00 35.00 - 47.50 - 25.00 - - 8.00 - 32.61 8.00 - 30.9240.00 70.00 75.00 75.00

107 Portable Concrete Vibrator up to and including 1 3/4" ( 45 mm ) hour - - - - 10.00 - 11.25 - - - - - - 10.00 - 11.2512.50 12.50

108 Ditto over 1 3/4" up to and including 2 1/2" ( 64 mm ) hour - - - - - - - 13.00 - - - - - 13.00

109 Ditto over 2 1/2" ( 64 mm ) hour - - - - - - - 19.00 - - - - - 19.00

110 Ditto 75 mm hour - - - - 10.00 - 16.77 - - - - - - 10.00 - 16.7737.50 37.50

111 Ditto over 75 mm hour - - - - 12.50 - 24.15 - - - - - - 12.50 - 24.1545.00 45.00

112 Vibrator concrete immersion type ;

a) light - 40mm hour - 20.00 - - - 20.00 - 30.00 - - 10.00 - 19.29 10.00 - 22.32

50.00 50.00

KAWASAN B KAWASAN C KAWASAN D KAWASAN E KAWASAN F KESELURUHANKAWASAN A

c: lojij

BAHAGIAN : 5.0 - KOS SEWA LOJI / JENTERAKawasan A - Perlis, Kedah, & P. Pinang Kawasan D - Johor

Kawasan B - Perak Kawasan E - PahangKawasan C - WP.KL , Selangor Kawasan F - Terengganu

N. Sembilan & Melaka & Kelantan

BIL. KETERANGAN KERJA UNIT JULAT JULAT PURATA JULAT PURATA JULAT PURATA JULAT PURATA JULAT PURATA JULAT PURATA(RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM)

Concrete Plant ( cont'd )

112 Vibrator, concrete immersion type ; (cont'd)

a) light - 50 mm hour - 30.00 - - - - - - - - 10.00 - 19.29 10.00 - 24.65

50.00 50.00

b) heavy - 50 mm and above hour - - - - - 25.00 - 45.00 - - 12.00 - 27.43 12.00 - 32.48

75.00 75.00

Crane

113 Mobile crane up to and including 1 ton hour - - - - 25.00 - 42.00 - - - - - - 25.00 - 42.0065.00 65.00

114 Ditto up to 3 ton hour - 30.00 30.00 - 34.00 50.00 - 56.25 - 50.00 50.00 - 65.63 - - 30.00 - 47.1838.00 62.50 81.25 81.25

115 Ditto up to and including 5 ton. hour 15.00 - 39.36 - 38.00 25.00 - 43.98 45.00 - 51.67 - 30.00 31.25 - 52.07 15.00 - 42.5158.00 70.00 60.00 80.00 80.00

116 Crawler crane over 6 ton up to 10 ton. hour 22.00 - 46.06 - 50.00 37.50 - 52.75 - 60.00 47.50 47.50 35.00 - 57.15 22.00 - 52.2465.00 80.00 90.00 90.00

c: lojij

KAWASAN F KESELURUHANKAWASAN B KAWASAN C KAWASAN D KAWASAN EKAWASAN A

BAHAGIAN : 5.0 - KOS SEWA LOJI / JENTERAKawasan A - Perlis, Kedah, & P. Pinang Kawasan D - Johor

Kawasan B - Perak Kawasan E - PahangKawasan C - WP.KL , Selangor Kawasan F - Terengganu

N. Sembilan & Melaka & Kelantan

BIL. KETERANGAN KERJA UNIT JULAT JULAT PURATA JULAT PURATA JULAT PURATA JULAT PURATA JULAT PURATA JULAT PURATA(RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM)

Crane ( cont'd )

117 Crawler crane over 10 ton up to 20 ton hour 30.00 - 53.28 40.00 - 51.00 45.00 - 61.96 - 80.00 - - 35.00 - 65.85 30.00 - 62.4270.00 63.00 100 100.00 100.00

118 Ditto over 20 ton up to 30 ton. hour 48.00 - 60.50 45.00 - 54.00 60.00 - 67.33 - - - - 45.00 - 68.25 45.00 - 62.5280.00 63.00 80.00 100.00 100.00

119 Ditto over 30 ton up to 40 ton hour 55.00 - 73.33 50.00 - 65.00 75.00 - 125.00 - - - - 81.25 81.25 50.00 - 86.1590.00 80.00 150.00 150.00

120 Ditto up to and including 50 ton hour 65.00 - 86.25 60.00 - 80.00 90.00 - 95.00 - - - - 54.00 - 92.36 54.00 - 88.40100.00 100.00 100.00 137.00 137.00

121 Ditto, 60 ton. hour - - - - - - - - - - - 100.00 - 100.00

122 Ditto 80 ton. hour - - - - - - - - - - - 118.75 - 118.75

123 Rough terrain crane 20 ton. hour - - - - - 62.00 - - - - - - - 62.00

124 Ditto, 25 ton. hour - - - - - 62.00 - - - - - - - 62.00

c: lojij

KAWASAN A KAWASAN B KAWASAN C KAWASAN D KAWASAN E KAWASAN F KESELURUHAN

BAHAGIAN : 5.0 - KOS SEWA LOJI / JENTERAKawasan A - Perlis, Kedah, & P. Pinang Kawasan D - Johor

Kawasan B - Perak Kawasan E - PahangKawasan C - WP.KL , Selangor Kawasan F - Terengganu

N. Sembilan & Melaka & Kelantan

BIL. KETERANGAN KERJA UNIT JULAT JULAT PURATA JULAT PURATA JULAT PURATA JULAT PURATA JULAT PURATA JULAT PURATA(RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM)

Weiding Equipments

125 Oxy - Acetylene cutting apparatus and gas. hour 8.00 - 23.82 25.00 - 33.67 10.00 - 29.97 18.75 - 27.58 - - 10.00 - 30.5 8.00 - 29.1140.00 38.00 80.00 34.00 65.00 80.00

126 Electric, 300 Amp. hour 12.00 - 31.5 30.00 - 43.33 10.00 - 28.89 18.75 - 31.92 18.75 - 21.88 12.00 - 42.33 12.00 - 33.3155.00 50.00 65.00 40.00 25.00 65.00 65.00

127 Welding or cutting gear. hour 20.00 - 21.25 - - 30.00 - 30.63 - - - 15.00 - 15.00 15.00 - 20.4725.00 31.25 31.25

Transporting Plant

128 Pick-up trucks hour - 23.00 - - - - - - - - - - - 23.00

129 Truck, flat bed up to and including 30cwt. hour - - - - - 40.00 - - - - 25.00 - 40.57 25.00 - 40.2970.00 70.00

130 Ditto over 3 ton up to and including 5 ton hour - - - - - 40.00 - - - - 25.00 - 40.54 25.00 - 40.2768.5 68.50

131 Ditto over 5 ton up to 7 ton. hour - 30.00 - - - 50.00 - - - - 35.00 - 47.97 30.00 - 42.6668.75 68.75

c: lojij

KAWASAN B KAWASAN C KAWASAN D KAWASAN E KAWASAN F KESELURUHANKAWASAN A

BAHAGIAN : 5.0 - KOS SEWA LOJI / JENTERAKawasan A - Perlis, Kedah, & P. Pinang Kawasan D - Johor

Kawasan B - Perak Kawasan E - PahangKawasan C - WP.KL , Selangor Kawasan F - Terengganu

N. Sembilan & Melaka & Kelantan

BIL. KETERANGAN KERJA UNIT JULAT JULAT PURATA JULAT PURATA JULAT PURATA JULAT PURATA JULAT PURATA JULAT PURATA(RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM)

Transporting Plant ( cont'd )

132 Water Browser hour - - - - - 50.00 - - - - - 75.00 50.00 - 62.5075.00

133 Water Tanker self propelled hour - - - - - - - - - - 20.00 - 30.00 20.00 - 30.0040.00 40.00

134 Water truck including spraying equipment up to and including hour - - - - - 30.00 - - - 25.00 50.00 - 59.00 25.00 - 38.003200 gallons. 75.00 75.00

135 Lorry tipper up to and including 3 ton hour 25.00 - 31.67 - - 25.00 - 35.00 - 43.75 37.50 - 43.75 - - 25.00 - 38.5435.00 45.00 50.00 50.00

136 Ditto over 3 ton up to and including 6 ton hour 25.00 - 37.37 - 40.00 22.50 - 39.88 40.00 - 48.13 30.00 - 36.25 25.00 - 38.25 22.50 - 39.9845.00 80.00 56.25 43.75 50.00 80.00

137 Ditto over 6 ton up to and including 10 ton hour 35.00 - 48.11 30.00 - 39.00 27.50 - 51.94 - 50.00 37.50 - 40.42 20.00 - 42.70 27.50 - 45.3670.00 50.00 90.00 43.75 60.00 90.00

138 Ditto over 10 ton hour 40.00 - 56.92 35.00 - 48.00 50.00 - 67.32 - 60.00 - - 35.00 - 57 35.00 - 57.8580.00 60.00 120.00 80.00 120.00

139 Ordinary lorry up to and including 1.5 ton. hour - 20.00 - - - 35.00 - 31.25 - - - - 20.00 - 28.7535

140 Ditto up to 3 ton hour - 25.00 - - 12.50 - 25.68 35.00 - 39.38 - - - - 12.50 - 30.0243.75 43.75 43.75

c: lojij

KAWASAN B KAWASAN C KAWASAN D KAWASAN E KAWASAN F KESELURUHANKAWASAN A

BAHAGIAN : 5.0 - KOS SEWA LOJI / JENTERAKawasan A - Perlis, Kedah, & P. Pinang Kawasan D - Johor

Kawasan B - Perak Kawasan E - PahangKawasan C - WP.KL , Selangor Kawasan F - Terengganu

N. Sembilan & Melaka & Kelantan

BIL. KETERANGAN KERJA UNIT JULAT JULAT PURATA JULAT PURATA JULAT PURATA JULAT PURATA JULAT PURATA JULAT PURATA(RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM)

Transporting Plant ( cont'd )

141 Ordinary lorry up to and including 6 ton. hour 25.00 - 34.75 35.00 - 37.5 18.75 - 32.37 40.00 - 45.00 - - 27.50 - 32.30 25.00 - 36.3850.00 40.00 50.00 50.00 40.00 50.00

142 Ditto over 6 ton up to and including 10 ton. hour 37.50 - 45.83 40.00 - 45.00 40.00 - 50.00 - - - - 31.75 - 45.75 31.75 - 46.6560.00 50.00 70.00 65.00 70.00

143 Concrete dumper up to and including 1 m3. hour - - - - 20.00 - 36.25 - - - 31.25 - - 20.00 - 33.7565.00 65.00

144 Dumper, petrol or diesel up to and including 1.5 m3 hour - 20.00 - 35.00 - 68.75 - - - - - - 20.00 - 41.2568.75

145 Ditto up to 2 m3. hour 30.00 - 47.50 - 50.00 20.00 - 40.00 - 40.00 - - - - 20.00 - 44.3860.00 60.00 60.00

146 Dito over 2 m3 up to 5 m3. hour - 32.50 - - - 30.00 - 60.00 - - - 43.00 30.00 - 41.3860.00

147 Ditto over 5 m3 up to 10 m3. hour - 35.00 - - 35.00 - 40.00 - 60.00 - - 48.00 - 56.42 35.00 - 47.8645.00 65.00 65.00

148 Off-Highway Dump Truck over 6 ton up to 10 ton. hour - - - - - - - - - - 24.00 - 33.88 24.00 - 33.8860.00 60.00

c: lojij

KAWASAN F KESELURUHANKAWASAN B KAWASAN C KAWASAN D KAWASAN EKAWASAN A

BAHAGIAN : 5.0 - KOS SEWA LOJI / JENTERAKawasan A - Perlis, Kedah, & P. Pinang Kawasan D - Johor

Kawasan B - Perak Kawasan E - PahangKawasan C - WP.KL , Selangor Kawasan F - Terengganu

N. Sembilan & Melaka & Kelantan

BIL. KETERANGAN KERJA UNIT JULAT JULAT PURATA JULAT PURATA JULAT PURATA JULAT PURATA JULAT PURATA JULAT PURATA(RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM)

Transporting Plant ( cont'd )

149 Off-Highway Dump Truck over 10 ton up to 15 ton hour - - - - - - - - - - 36.00 - 49.65 36.00 - 49.6570.00 70.00

150 Ditto over 15 ton up to 25 ton hour - - - - - - - - - - 40.00 - 51.88 40.00 - 51.8865.00 65.00

151 Trucks , dump, 8 cu. Yd. Up to and including 10 cu. Yd. hour - - - - - 55.00 - - - - 30.00 - 41.36 30.00 - 48.1860.00 60.00

152 Ditto 12 cu. Yd. Up to and including 15 cu. Yd. hour - - - - - 55.00 - - - 55.00 40.00 - 47.5 40.00 - 52.5055.00 55.00

153 Rear Dump truck up to 5 ton. hour - - - - - 60.00 - - - - - - - 60.00

154 Rear Dump truck over 5 ton up to 10 ton. hour - - - - - 70.00 - - - - - - - 70.00

155 Rear Dump truck over 10 ton up to 15 ton. hour - - - - - 90.00 - - - - - - - 90.00

156 Rear Dump truck over 15 ton up to 25 ton. hour - - - - - 110.00 - - - - - - - 110.00

c: lojij

KAWASAN A KAWASAN B KAWASAN C KAWASAN D KAWASAN E KAWASAN F KESELURUHAN

BAHAGIAN : 5.0 - KOS SEWA LOJI / JENTERAKawasan A - Perlis, Kedah, & P. Pinang Kawasan D - Johor

Kawasan B - Perak Kawasan E - PahangKawasan C - WP.KL , Selangor Kawasan F - Terengganu

N. Sembilan & Melaka & Kelantan

BIL. KETERANGAN KERJA UNIT JULAT JULAT PURATA JULAT PURATA JULAT PURATA JULAT PURATA JULAT PURATA JULAT PURATA(RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM)

Transporting Plant ( cont'd )

157 Rear Dump truck over 25 ton hour - - - - - 125.00 - - - - - - - 125.00

158 Three ton Vibro - Hammer including generator. hour - - - - - 43.75 - - - - - - - 43.75

159 Dumper self propelled up to 2.5 m3. hour - - - - 18.75 - 36.43 - - - - - - 18.75 - 36.4350.00 50.00

160 Low loader 40 ton hour - 75.00 43.00 - 96.50 - - - - - 62.50 55.00 - 70.83 43.00 - 76.21150.00 120.00 150.00

161 Wheel Loader up to 2.5 m3 hour 30.00 - 63.33 - - - 60.00 - - - - 18.75 - 50.94 18.75 - 58.09100.00 75.00 100.00

162 Ditto over 2.5 m3 up to 5 m3. hour 40.00 - 75.00 - - - 82.00 - - - - 31.25 - 70.45 31.25 - 75.82120.00 120.00 120.00

163 Front End Wheel Loader up to 1.5 cu. Yd. hour - - - - - - - - - - 30.00 - 47.86 30.00 - 47.8670.00 70.00

164 Ditto up to 3 cu. Yd. hour - - - - - 60.00 - - - - - - - 60.00

165 Ditto over 2 m3 up to 5 m3 hour - - - - - 90.00 - - - - - - - 90.00

c: lojij

KAWASAN B KAWASAN C KAWASAN D KAWASAN E KAWASAN F KESELURUHANKAWASAN A

BAHAGIAN : 5.0 - KOS SEWA LOJI / JENTERAKawasan A - Perlis, Kedah, & P. Pinang Kawasan D - Johor

Kawasan B - Perak Kawasan E - PahangKawasan C - WP.KL , Selangor Kawasan F - Terengganu

N. Sembilan & Melaka & Kelantan

BIL. KETERANGAN KERJA UNIT JULAT JULAT PURATA JULAT PURATA JULAT PURATA JULAT PURATA JULAT PURATA JULAT PURATA(RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM)

Transporting Plant ( cont'd )

166 Front End Wheel Loader over 5 m3. hour - - - - - 120.00 - - - - - - - 120.00

167 Trailer hour - - - - 18.75 - 31.25 - - - - - - 18.75 - 31.2543.75 43.75

Roller

168 Roller 1.5 ton hour - - - - - 31.25 - - - - - - - 31.25

169 Ditto 3 ton hour - 35.00 - - - - - - - - - - - 35.00

170 Ditto 5 ton hour - 30.00 - - - 45.00 - 68.75 - 30.00 - - 30.00 - 43.4468.75

171 Ditto over 5 ton up to 10 ton hour 31.25 - 33.13 35.00 - 36.50 35.00 - 42.50 - 81.25 50.00 - 56.25 25.00 - 48.08. 25.00 - 49.6235.00 38.00 55.00 62.50 80.00 81.25

172 Ditto over 10 ton hour - 30.00 42.00 - 43.50 - 42.00 - - - - 31.00 - 48.88 30.00 - 41.1045.00 100.00 100.00

c: lojij

KAWASAN B KAWASAN C KAWASAN D KAWASAN E KAWASAN F KESELURUHANKAWASAN A

BAHAGIAN : 5.0 - KOS SEWA LOJI / JENTERAKawasan A - Perlis, Kedah, & P. Pinang Kawasan D - Johor

Kawasan B - Perak Kawasan E - PahangKawasan C - WP.KL , Selangor Kawasan F - Terengganu

N. Sembilan & Melaka & Kelantan

BIL. KETERANGAN KERJA UNIT JULAT JULAT PURATA JULAT PURATA JULAT PURATA JULAT PURATA JULAT PURATA JULAT PURATA(RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM)

Roller ( cont'd )

173 Drawn Vibratory Roller 15 ton compaction force hour - 50.00 - - - 50.00 - - - - 40.00 - 57.86 40.00 - 52.62110.00 110.00

-174 Vibrating Roller 3 ton. hour - 25.00 - - - 60.00 - - - - - - 25.00 - 42.50

60.00

175 Ditto over 5 ton up to and including 7 ton hour - - - - - - - - - - - 68.75 - 68.75

176 Ditto over 10 ton up to 12 ton hour - - - 50.00 - - - - - - - 75.00 50.00 - 62.5075.00

177 Vibrating Roller self propelled up to 0.5 ton hour - - - - - 30.00 - - - - - - - 30.00

178 Ditto up to 5 ton hour - - - - - - - - - 37.50 - - - 37.50

179 Ditto over 5 ton up to 10 ton hour - - - - - - - - - 43.75 - - - 43.75

180 Ditto over 10 ton up to 15 ton hour - - - - - - - - - - 40.00 - 58.28 40.00 - 58.28100.00 100.00

c: lojij

KAWASAN F KESELURUHANKAWASAN B KAWASAN C KAWASAN D KAWASAN EKAWASAN A

BAHAGIAN : 5.0 - KOS SEWA LOJI / JENTERAKawasan A - Perlis, Kedah, & P. Pinang Kawasan D - Johor

Kawasan B - Perak Kawasan E - PahangKawasan C - WP.KL , Selangor Kawasan F - Terengganu

N. Sembilan & Melaka & Kelantan

BIL. KETERANGAN KERJA UNIT JULAT JULAT PURATA JULAT PURATA JULAT PURATA JULAT PURATA JULAT PURATA JULAT PURATA(RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM)

Roller ( cont'd )

181 Self Propelled Road Roller less than 6 ton. hour - - - - 43.75 - 49.58 - - - - - - 43.75 - 49.5855.00 55.00

182 Ditto over 6 ton hour - - - - 54.00 - 57.17 - - - - - - 54.00 - 57.1760.00 60.00

183 Vibrating Roller trailer type up to 5 ton. hour - - - - 50.00 - 57.50 - - - - - - 50.00 - 57.5065.00 65.00

184 Pneumatic Tyred Roller 7 ton up to 14 ton. hour - - - - 60.00 - 66.25 - - - - - - 60.00 - 66.2572.5 72.50

185 Draw Grid Roller hour - - - - - - - - - - - 81.25 - 81.25

186 Macadam Roller over 5 ton up to 10 ton. hour 25.00 - 39.86 - 38.00 25.00 - 49.25 - 35.00 - - 50.00 - 96.5 25.00 - 51.7260.00 65.00 130.00 130.00

Mechanical Handling

187 Drilling Machine complete with all necessary equipment hour 20.00 - 42.34 38.00 - 65.33 25.00 - 69.79 - 45.00 - - 50.00 - 75.00 20.00 - 59.4980.00 120.00 100.00 90.00 120.00

188 Crawler Drill hour - - - - - - - - - - - 65.00 - 65.00

c: lojij

KAWASAN A KAWASAN B KAWASAN C KAWASAN D KAWASAN E KAWASAN F KESELURUHAN

BAHAGIAN : 5.0 - KOS SEWA LOJI / JENTERAKawasan A - Perlis, Kedah, & P. Pinang Kawasan D - Johor

Kawasan B - Perak Kawasan E - PahangKawasan C - WP.KL , Selangor Kawasan F - Terengganu

N. Sembilan & Melaka & Kelantan

BIL. KETERANGAN KERJA UNIT JULAT JULAT PURATA JULAT PURATA JULAT PURATA JULAT PURATA JULAT PURATA JULAT PURATA(RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM)

Miscellaneous

189 Bitumen Heating and spraying plant. hour - 62.50 - - - 43.75 - - - - - 30.00 30.00 - 45.4262.50

190 Asphalt or bitumen Macadam spread self propelled up to hour - - - - - - - - - - - 30.00 - 30.00and including 40 hp.

191 Bitumenuos Mixing Plant of capacity not less than 50 ton/hr. hour - - - - - - - - - - - 26.00 - 26.00

192 Bitumenuos Emulsion Sprayer hour - - - - - - - - - - - 25.00 - 25.00

193 Chain Saw hour - 15.00 - - - - - - - - - - - 15.00

194 Vibrating Plate Compactor up to and including hour 25.00 - 51.66 - - - - - - - - 56.25 - 74.05 25.00 - 62.866 ton/m2. 100.00 100.00 100.00

-195 Portable Compactor hour - - - - - 15.00 - - - - 20.00 - 25.00 15.00 - 20.00

30.00 30.00

196 Motorcar including driver, fuel and all consumable. hour - 100.00 - - - - - - - - - - - 100.00

c: lojij

KAWASAN B KAWASAN C KAWASAN D KAWASAN E KAWASAN F KESELURUHANKAWASAN A

BAHAGIAN : 5.0 - KOS SEWA LOJI / JENTERAKawasan A - Perlis, Kedah, & P. Pinang Kawasan D - Johor

Kawasan B - Perak Kawasan E - PahangKawasan C - WP.KL , Selangor Kawasan F - Terengganu

N. Sembilan & Melaka & Kelantan

BIL. KETERANGAN KERJA UNIT JULAT JULAT PURATA JULAT PURATA JULAT PURATA JULAT PURATA JULAT PURATA JULAT PURATA(RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM)

Miscellaneous ( cont'd )

197 Rowing Boat or Sampan with crew hour - 50.00 - - - - - - - - - - - 50.00

198 Power launch including attendance coxwein crew, fuel, water hour - 120.00 - - - - - - - - - - - 120.00and all consumables spares.

199 Extra over D4 for echo sounder and operator hour - 50.00 - - - - - - - - - - - 50.00

200 Prestressing jack 100 ton capacity hour - - - - - 125.00 - - - - - - - 125.00

201 Ditto 150 ton capacity hour - - - - - - - - - - - 50.00 - 50.00

202 Generating set up to and including 5 kw. hour 15.00 - 38.33 - - 20.00 - 40.00 - 50.00 - - - - 15.00 - 42.7860.00 60.00 60.00

203 Ditto over 5 kw up to and including 10 kw. hour 25.00 - 46.67 - - - 30.00 - 68.75 - - - - 25.00 - 48.4770.00 70.00

204 Ditto over 10 kw. hour - 35.00 - - - 25.00 - 81.25 - - - - 25.00 - 47.0881.25

c: lojij

KAWASAN B KAWASAN C KAWASAN D KAWASAN E KAWASAN F KESELURUHANKAWASAN A

BAHAGIAN : 5.0 - KOS SEWA LOJI / JENTERAKawasan A - Perlis, Kedah, & P. Pinang Kawasan D - Johor

Kawasan B - Perak Kawasan E - PahangKawasan C - WP.KL , Selangor Kawasan F - Terengganu

N. Sembilan & Melaka & Kelantan

BIL. KETERANGAN KERJA UNIT JULAT JULAT PURATA JULAT PURATA JULAT PURATA JULAT PURATA JULAT PURATA JULAT PURATA(RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM)

Miscellaneous ( cont'd )

205 Generator hour - - - - - - - - 8.25 - 16.88 8.25 - 16.8825.00 25.00

206 Rammer Mechanical hour - 20.00 - - - 50.00 - - - - - - 20.00 - 35.0050.00

207 Rock Drill 4" air power crawler Rig. hour - - - - - - - - - - 35.00 - 57.83 35.00 - 57.83100.00 100.00

208 Asphalt Pavior hour - - - - - - - - - - - 28.00 - 28.00

209 Asphalt Plant hour - - - - - - - - - - - 150.00 - 150.00

210 Pneumatic hand breaker hour - - - - 18.75 - 28.13 - - - - - - 18.75 - 28.1337.50 37.50

211 Pneumatic Concrete Breaker including tools and hoses. hour - - - - - - - - - 25.00 - - - 25.00

212 Paver - BK 175 ( 120 ton/hr ) hour - - - - - 85.00 - - - - - - - 85.00

c: lojij

KAWASAN F KESELURUHANKAWASAN B KAWASAN C KAWASAN D KAWASAN EKAWASAN A

BAHAGIAN : 5.0 - KOS SEWA LOJI / JENTERAKawasan A - Perlis, Kedah, & P. Pinang Kawasan D - Johor

Kawasan B - Perak Kawasan E - PahangKawasan C - WP.KL , Selangor Kawasan F - Terengganu

N. Sembilan & Melaka & Kelantan

BIL. KETERANGAN KERJA UNIT JULAT JULAT PURATA JULAT PURATA JULAT PURATA JULAT PURATA JULAT PURATA JULAT PURATA(RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM)

Miscellaneous ( cont'd )

213 Paver - BK 165 ( 100 ton/hr. ) hour - - - - - 80.00 - - - - - - - 80.00

214 Crushing Plant hour - - - - - - - - - - - 185.00 - 185.00

215 Diving Equipment hour - - - - - - - - - - - 31.25 - 31.25

216 Cutter Suction Dredger ( 2300 hp. ) hour - - - - - - - - - - - 1062.50 - 1062.50

217 Ditto ( 6500 hp. ) hour - - - - - - - - - - - 1437.50 - 1437.50

218 Anchor Boat ( 730 hp. ) hour - - - - - - - - - - - 231.25 - 231.25

219 Tug Boat hour - - - - - - - - - - 145.63 - 166.56 145.63 - 166.56187.5 187.5

220 Barge ( 180' x 50' ) hour - - - - - - - - - - - 106.25 - 106.25

c: lojij

KAWASAN A KAWASAN B KAWASAN C KAWASAN D KAWASAN E KAWASAN F KESELURUHAN

BAHAGIAN : 5.0 - KOS SEWA LOJI / JENTERAKawasan A - Perlis, Kedah, & P. Pinang Kawasan D - Johor

Kawasan B - Perak Kawasan E - PahangKawasan C - WP.KL , Selangor Kawasan F - Terengganu

N. Sembilan & Melaka & Kelantan

BIL. KETERANGAN KERJA UNIT JULAT JULAT PURATA JULAT PURATA JULAT PURATA JULAT PURATA JULAT PURATA JULAT PURATA(RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM)

Miscellaneous ( cont'd )

221 Barge ( 100' x 30' ) hour - - - - - - - - - - - 62.50 - 62.50

222 Self Propelled Hopper Barge 400 m3. hour - - - - - - - - - - - 162.50 - 162.50

223 Ditto 600 m3 hour - - - - - - - - - - - 187.50 - 187.50

224 Ditto 800 m3 hour - - - - - - - - - - - 250.00 - 250.00

225 Ditto 7 ton hour - - - - - 100 - - - - - - - 100.00

c: lojij

KAWASAN B KAWASAN C KAWASAN D KAWASAN E KAWASAN F KESELURUHANKAWASAN A