Analysis and mitigation of transient overvoltage with integration of small scale power-electronic...

8
1 Abstract—As the amount of non-scheduled small scale distributed generation (DG) units are increasing, lack of fault ride through (FRT) capability of these generators may have an adverse affect on the overall power system. This study focuses on the basics of transient overvoltage issue arising under faulty condition with integration of power-electronic (PE) interface based DG units in a system. Reasons behind this overvoltage issue and its impact on DG integration with present grid standard have been investigated. A methodology has been utilized to overcome this overvoltage issue in a system, which has conventional generator as well as wide penetration of full- converter based solar and wind generation. An IEEE industrial test system with varieties of motor loads has been used to carry out the analysis and to verify the methodology. Index Terms-- Distributed Generation, Power-Electronic Interface, Overvoltage, STATCOM, Grid code, FRT, Voltage recovery. I. INTRODUCTION ARIOUS environmental and economic benefits for both consumer and network operator have led to wide-scale integration of distributed generation (DG) units around the world. This could include wind, solar, biomass, storage and other wide range of energy sources, which are not essentially generation in the conventional utility sense [1]. With increasing penetration of DG units, network operators will need to uphold control of overall power generation connected to the grid in a distributed manner. Severe voltage and dynamic stability problem may arise if DG units get disconnected for every fault condition. Large scale conventional synchronous generators are able to ride through such turbulent conditions and thus they can avoid tripping. Network operators demand similar FRT capability from other generators (including generation based on volatile resources such as wind and solar). FRT can be subdivided into Low Voltage Ride Through (LVRT) and High Voltage Ride Through (HVRT) [2]. Voltage at point of common coupling This work was supported by the CSIRO Intelligent Grid Flagship Collaboration Research Fund. Tareq Aziz ([email protected]), T. K. Saha ([email protected]) and N. Mithulananthan ([email protected]) are with the School of Information Technology and Electrical Engineering, The University of Queensland, Qld 4072, Australia. (PCC) must stay within these two limits to avoid unnecessary tripping. Hence, generators having FRT capability should stay connected to the network under short voltage abnormalities with temporary faults. American Wind Energy Association (AWEA) and the Western Electricity Coordinating Council (WECC) proposed LVRT requirements for all new generators greater than 20MW and no distinctions were made between conventional synchronous and inverter based variable speed generators [3]. North American Electric Reliability Council (NERC) also proposes a set of rules demanding LVRT capability from single generating unit greater than 20MW or aggregated generation greater than 75MW [4]. Similar sets of LVRT requirements have been issued by FERC orders no. 661 and 661-A for wind generators greater than 20MW. Recently, Australia and Spain have developed voltage–time profile for voltage swell conditions with large scale generator integration. Hence, FRT is a demand by grid operators and it is expected that large scale generation units should be equipped with this capability. In order to contribute more real power into the system and avoid controller interactions, small scale DG units are not permitted to operate in voltage control mode in most cases [5]. Moreover, they lack FRT capability too. Hence, proper reactive power planning with static and dynamic VAR devices can support them to adapt interconnection rules, which eventually results in increased DG integration [6], [7]. In recent years, along with existing synchronous and induction generator based DG, there has been an increased interest in power-electronic (PE) interfaced distributed generators. PE interfaced DG includes photovoltaic arrays, few types of wind turbines, fuel cells, micro-turbines and energy storage devices [8], [9]. However, with large scale penetration of these PE-interface DG units, power imbalance under faulty condition may give rise to transient overvoltage and this has been reported in [10], [11], [12]. While large scale DG units are facilitated with FRT capability, proper measures need to be taken with small scale DG units to avoid their tripping because of this overvoltage issue. This work presents an analytical study of overvoltage issue and a way of mitigating this issue with large penetration of PE-interfaced small scale DG units. Large penetration of wind and solar generation has been taken into account in presence of conventional synchronous generator in an IEEE industrial test system. Existing methodologies for mitigating overvoltage Analysis and Mitigation of Transient Overvoltage with Integration of Small Scale Power-Electronic Interfaced DG T. Aziz, Student Member, IEEE, Tapan K. Saha, Senior Member, IEEE and N. Mithulananthan, Senior Member, IEEE V 978-1-4673-2729-9/12/$31.00 ©2012 IEEE

Transcript of Analysis and mitigation of transient overvoltage with integration of small scale power-electronic...

1

Abstract—As the amount of non-scheduled small scale

distributed generation (DG) units are increasing, lack of fault

ride through (FRT) capability of these generators may have an

adverse affect on the overall power system. This study focuses on

the basics of transient overvoltage issue arising under faulty

condition with integration of power-electronic (PE) interface

based DG units in a system. Reasons behind this overvoltage

issue and its impact on DG integration with present grid

standard have been investigated. A methodology has been

utilized to overcome this overvoltage issue in a system, which has

conventional generator as well as wide penetration of full-

converter based solar and wind generation. An IEEE industrial

test system with varieties of motor loads has been used to carry

out the analysis and to verify the methodology.

Index Terms-- Distributed Generation, Power-Electronic

Interface, Overvoltage, STATCOM, Grid code, FRT, Voltage

recovery.

I. INTRODUCTION

ARIOUS environmental and economic benefits for both

consumer and network operator have led to wide-scale

integration of distributed generation (DG) units around the

world. This could include wind, solar, biomass, storage and

other wide range of energy sources, which are not essentially

generation in the conventional utility sense [1]. With

increasing penetration of DG units, network operators will

need to uphold control of overall power generation connected

to the grid in a distributed manner. Severe voltage and

dynamic stability problem may arise if DG units get

disconnected for every fault condition. Large scale

conventional synchronous generators are able to ride through

such turbulent conditions and thus they can avoid tripping.

Network operators demand similar FRT capability from other

generators (including generation based on volatile resources

such as wind and solar). FRT can be subdivided into Low

Voltage Ride Through (LVRT) and High Voltage Ride

Through (HVRT) [2]. Voltage at point of common coupling

This work was supported by the CSIRO Intelligent Grid Flagship

Collaboration Research Fund.

Tareq Aziz ([email protected]), T. K. Saha ([email protected]) and

N. Mithulananthan ([email protected]) are with the School of

Information Technology and Electrical Engineering, The University of

Queensland, Qld 4072, Australia.

(PCC) must stay within these two limits to avoid unnecessary

tripping. Hence, generators having FRT capability should stay

connected to the network under short voltage abnormalities

with temporary faults. American Wind Energy Association

(AWEA) and the Western Electricity Coordinating Council

(WECC) proposed LVRT requirements for all new generators

greater than 20MW and no distinctions were made between

conventional synchronous and inverter based variable speed

generators [3]. North American Electric Reliability Council

(NERC) also proposes a set of rules demanding LVRT

capability from single generating unit greater than 20MW or

aggregated generation greater than 75MW [4]. Similar sets of

LVRT requirements have been issued by FERC orders no. 661

and 661-A for wind generators greater than 20MW. Recently,

Australia and Spain have developed voltage–time profile for

voltage swell conditions with large scale generator integration.

Hence, FRT is a demand by grid operators and it is expected

that large scale generation units should be equipped with this

capability.

In order to contribute more real power into the system and

avoid controller interactions, small scale DG units are not

permitted to operate in voltage control mode in most cases [5].

Moreover, they lack FRT capability too. Hence, proper

reactive power planning with static and dynamic VAR devices

can support them to adapt interconnection rules, which

eventually results in increased DG integration [6], [7].

In recent years, along with existing synchronous and

induction generator based DG, there has been an increased

interest in power-electronic (PE) interfaced distributed

generators. PE interfaced DG includes photovoltaic arrays,

few types of wind turbines, fuel cells, micro-turbines and

energy storage devices [8], [9]. However, with large scale

penetration of these PE-interface DG units, power imbalance

under faulty condition may give rise to transient overvoltage

and this has been reported in [10], [11], [12]. While large

scale DG units are facilitated with FRT capability, proper

measures need to be taken with small scale DG units to avoid

their tripping because of this overvoltage issue.

This work presents an analytical study of overvoltage issue

and a way of mitigating this issue with large penetration of

PE-interfaced small scale DG units. Large penetration of wind

and solar generation has been taken into account in presence

of conventional synchronous generator in an IEEE industrial

test system. Existing methodologies for mitigating overvoltage

Analysis and Mitigation of Transient

Overvoltage with Integration of Small Scale

Power-Electronic Interfaced DG T. Aziz, Student Member, IEEE, Tapan K. Saha, Senior Member, IEEE and N. Mithulananthan, Senior

Member, IEEE

V

978-1-4673-2729-9/12/$31.00 ©2012 IEEE

2

have been summarized and effectiveness of index-based

placement of STATic synchronous COMpensator

(STATCOM) has been verified, which was previously used

for under-voltage ride through [13].

The paper is organized as follows. Section II gives a brief

description of PE-interfaced units used in this study. Section

III presents the analysis of overvoltage problem in small-scale

DG units under transient condition. Section IV focuses on the

HVRT requirement in existing grid standards. Section V

summarizes the existing techniques followed to mitigate

overvoltage at PCC along with brief description of index

based approach of voltage recovery. Section VI presents

results obtained through various fault simulations. Conclusion

in section VII highlights the contributions of present work.

II. DG WITH POWER ELECTRONIC INTERFACE

With the development of solid-state-based packages, PE

devices can now convert almost any form of electrical energy

to a more functional form. Along with flexibility in

operations, increased functionality through better power

quality, VAR support and reduced fault contributions have

worked as driving force behind getting increased attention of

this PE interface. This sort of interface contains necessary

power electronic circuitry to convert power from one form to

another. These may contain both a rectifier and an inverter or

simply an inverter. The inverter is adjusted to voltage and

frequency of the electric power system and contains the

necessary output filters for controlling harmonics. The

interface can also contain protective functions for both DG

unit and local electric power system that allow paralleling and

disconnection from system according to grid demand. Hence,

this type of interface ensures both: decoupled and fast

operation [9]. In present work, full-converter based DG units

have been used for simulation as explained below.

A. Full-power Converter Interfaced Wind Generator

Figure 1 shows block diagram of variable speed wind

turbine with full converter as interface to grid. Small scale

wind turbines are usually equipped with permanent magnet

synchronous generators because of higher efficiency, robust

rotor structure and high-power density. However, induction

generator along with gearbox can also be utilized to extract

energy from wind and finally grid side voltage source

converter (VSC) transfers that energy to grid.

Fig. 1. Block diagram for full converter interfaced wind generator [8].

B. Inverter Interfaced Photovoltaic Generator

Block diagram for basic Photovoltaic (PV) converter,

which can also be used for other technologies such as fuel cell

and battery storage, has been shown in Fig. 2. In most cases,

DC-DC converter with embedded high-frequency transformer

is used to ensure voltage boost and maximum power point

tracking (MPPT). DC output of the PV array/DC-DC

converter is connected across a filter capacitor and output of

the capacitor connects to a full-bridge VSC. A phase-locked-

loop (PLL) is utilized to synchronize the inverter output

voltage to system voltage. PV generation unit is then

connected through isolation transformer to utility grid.

Fig. 2. Block diagram of photovoltaic generator interface [8].

Complete decoupled operation of these VSC based DG

operation gives rise to overvoltage issue under transient

condition, which has been analytically explained in the next

section.

III. ANALYSIS OF OVERVOLTAGE ISSUE

Figure 3 illustrates the schematic diagram of DG unit with

PE interface to grid. This diagram can be utilized to analyze

the origin of overvoltage issue with small scale DG

integration.

Fig. 3. Schematic diagram of PE-interface for DG integration to grid.

Power transfer equation relating grid side VSC voltage to

PCC voltage can be expressed as:

3

3 sins ts

V VP

Xα=

(1)

Where sV and tV are rms values of PCC and VSC phase

voltages respectively, X is the coupling transformer

equivalent impedance with inductance L (neglecting

transformer losses) and α is the phase shift between the

mentioned phase voltages. In dq-frame, real and reactive

power exchanged at PCC can be expressed as [12]:

3( )

2s sd d sq qP V i V i= +

(2)

3

( )2

s sd q sq dQ V i V i= − +

(3)

With balanced PCC voltage, 0sqV = and ˆsd sV V= , where

ˆsV is peak amplitude of each phase voltage. Hence,

sP becomes proportional to di and can be written as:

3 ˆ2

s s dP V i= (4)

3 ˆ2

s s qQ V i= − (5)

When fault occurs in close electrical vicinity of generator

(i.e. at PCC or near to PCC), theory of symmetrical

components [14] can be utilized to formulate resulting

balanced/unbalanced voltage at PCC. Assuming reactive

power exchange 0sQ = at PCC, the dq-frame components of

PCC voltage can be expressed as:

0 0ˆ ˆ cos[2( ) ]sd s sV aV bV tω θ ψ= + + + (6)

0 0ˆ sin[2( ) ]sq sV bV tω θ ψ= − + + (7)

Where, 0ω and 0θ are fundamental frequency and phase

angle of voltage at PCC; ψ is the phase angle of negative

sequence component relative to positive sequence if voltage at

PCC is unbalanced. Coefficients a and b depend on the type

of fault. For balanced three phase case, 1a = and 0b = ,

whereas, for asymmetrical fault 1a < and 0b ≠ .

As 0sQ = , from Eqn. (5), 0qi = . Hence, from eqn. (2),

the actual real power exchanged at PCC under faulty

condition can be written as:

{ }0 0

3 ˆ ˆ cos 2( )2

sf s s dP aV bV t iω θ ψ! "= + + +# $ (8)

Substituting Eqn. (4) in Eqn. (8) results in,

{ }0 0cos 2( )sf s sP aP bP tω θ ψ= + + + (9)

With balanced condition, s sfP P= as 1a = and 0b = .

Now, power at DC link can be expressed as [12]: 2 2

2

3

ˆ4 3

d sdc sf L sf sf

s

di dPL LP P P P P

dt dtV= + = + = + (10)

DC link voltage dynamics can be formulated with the

following power balance equation:

2

( )2

dcext loss dc ext sf L

dVCP P P P P P

dt= − − ≈ − + (11)

Where, extP is the external power from generator side

converter and it is a function of generation technology and

available resources over time. Substituting Eqn. (10) in Eqn.

(11) results in:

2 2

2ˆ2 3

dc sext sf

s

dV dPC LP P

dt dtV

% &= − +' (' (

) *

(12)

Substituting eqn. (9) in eqn. (12) results in:

{ }2 2

0 02

2 2 2cos 2( )

ˆ3

dc sext s s

s

dV dPLP aP bP t

dt C C dt CVω θ ψ

! "% & ! "= − + + − + ++ ,' ( + ,' ( # $+ ,) *# $

(13)

0 0 0 0

2 2(2 ) 2 (2 ) 2

2

2 2 1 1. .

ˆ3

j j t j j tdc sext s s s

s

dV dPLP aP bPe e bPe e

dt C C dt C CV

θ ψ ω θ ψ ω+ − + −! "% & ! "

= − + + − −+ ,' ( + ,' ( # $+ ,) *# $

(14)

Eqn. (14) can be written as,

0 0 0 0

2(2 ) 2 (2 ) 20 1 1

. .j j t j j tdcs s

dV dybP e e bP e e

dt dt C C

θ ψ ω θ ψ ω+ − + −! "= + − −+ ,# $

(15)

In eqn. (15), DC link voltage dynamics have two

components: DC component is represented by 0dy

dt and

periodic AC component with frequency of 02ω is represented

by the rest of the expression.

From eqn. (9), a three phase solidly grounded fault in

electrical vicinity of generator will result in

0s sfP P= ≈ as ˆ 0sV ≈ . Eqn. (13) or (14) shows that, non-

zero value of extP will then result in

2

0dcdV

dt≠ , which

necessarily indicates developing overvoltage on DC link

terminal over time. For asymmetrical fault with 1a < and

0b ≠ , similar analysis can be derived from equations (13),

(14) and (15).

Once the fault is cleared, gating of power electronics for

grid side VSC are restored back to normal operation as it can

operate at much lower voltage [15]. Hence, assuming an ideal

pulse width modulation, the relation between converter

voltage and DC voltage can be expressed as:

0ˆt m dcV k P V= (16)

Where, mP and 0k define PWM index and DC to AC

conversion factor respectively.

As, ˆ ˆ .s t

diV V L

dt= −

!

, dynamics of overvoltage at DC link

according to eqn. (15) is reflected on ˆsV resulting overvoltage

problem at PCC. Besides this post-fault external power

injection and asymmetrical faults, overvoltage at PCC can also

be generated due to sudden load drops and switching of large

4

capacitor banks [16]. However, those situations are beyond

scope of the present work. The resulting may have various

magnitudes and durations depending on the contingency

situation. Particular segment of HVRT has been developed in

grid standards to address this issue for integration of

distributed generation.

IV. GRID STANDARDS FOR DG INTEGRATION

Grid interconnection standards specify the required

behaviour of renewable and non-renewable DG at PCC for

securing grids [17], [18]. To maintain voltage security, these

standards define continuous as well as transient voltage

requirements and they are constantly getting stringent because

of higher penetration of DG units. For continuous operation,

in most of the standards, it is expected that voltage remains

within the range of 90% to 110% of normal value at PCC

[17], [18].

IEEE and other standards demand small DG units to cease

energizing during abnormal system conditions according to

the clearing time shown in Table I [17].

TABLE I

DG RESPONSE TO ABNORMAL VOLTAGE [17]

Voltage Range (p.u.) Clearing time (sec)

V < 0.5 0.16

0.5 ! V < 0.88 2.00

1.1 < V < 1.2 1.00

V ! 1.2 0.16

The clearing time listed in Table I is a maximum threshold

for DG with capacity of 30 kW or less. For DG units with

generation capacity greater than 30 kW, the listed clearing

time is default value though this can vary with different utility

practices. Hence, regarding overvoltage limit, PCC voltage

needs to come down to 1.1pu within 1sec after the fault occurs

in generator vicinity.

In Australia, technical standard of connecting embedded

generators has been formulated by Australian Energy Market

Operator (AEMO) [19]. According to this standard, though

fault clearance time may vary from 80msec to 430msec

depending on voltage level and protection arrangement,

voltage at PCC must come back to 0.8pu within 2sec to avoid

tripping. Large scale generation units (listed as capacity of

30MW or more) have to be integrated with built-in capability

of LVRT to withstand this demand. Similar to LVRT,

Australia imposes HVRT requirement, which demands large

wind power plants to withstand voltage swell of 1.3pu up to

60msec and voltage at PCC must come back to 1.1pu within

1sec. LVRT and HVRT demand in Australia has been shown

in Fig. 4 [19], [20]. Hence, if necessary steps are not taken

due to transient overvoltage as explained in section III, small

scale generation units lacking FRT capability will result in

frequent tripping. Next section summarizes the existing

techniques followed to overcome this overvoltage issue with

PE-interface DG units.

Fig. 4. AEMO voltage ride through requirements [20].

V. MITIGATION OF OVERVOLTAGE PROBLEM

Number of measures has been proposed for large scale DG

units to avoid developing over voltage in dc-link and hence at

PCC to ensure HVRT. These methods can be grouped into

two classes - dissipation of excess energy at dc-link capacitor

through breaking resistor with full-rated DC chopper [21] and

reducing generator power by de-loading generator side

converter [22]. The braking resistor and chopper control need

careful design to avoid large transients and overheating.

As STATCOM can provide both capacitive and inductive

current, it has been found extensively in literature and practice

to support both LVRT and HVRT with integration of small

scale DG units [16], [23], [24],. However, in all these studies,

STATCOM has been placed at PCC with each DG unit. In a

system with multiple DG units, this approach would lead to

large number of STATCOMs along with controller

interactions due to their close vicinity in distribution level

[25].

In a recent study, an index based approach has been

developed to reduce number of STATCOM in a multiple-DG

integrated system [13]. According to this methodology,

STATCOM has been placed at a node with the most negative

value of sensitivity index "V/"IR in presence of fixed

capacitors. The methodology ensures grid-compatible fast

low-voltage recovery under worst case scenarios. In present

work, effectiveness of this methodology has been investigated

with large integration of PE-interfaced DG units. According to

the analysis in section III, overvoltage issue can arise with

decoupled operation of wind generators and photovoltaic

generators under faulty condition. Simulations have been

carried out with various faults to understand the problem and

possible solutions.

VI. SIMULATION RESULTS AND ANALYSIS

A. Test distribution System and Analytical Tool

An IEEE 43 bus industrial distribution system, shown in

Fig. 5 with a peak demand of 28.82 MW and 12.48 MVAr,

has been studied as test system [26]. This system has five

different levels of voltage rated at 69kV, 13.8kV, 4.16kV,

2.4kV and as low as 0.48kV. This test system is weakly

connected to grid with short circuit capacity of 300MVA and

grid X/R ratio of 4. Peak load condition has been considered

5

for simulation as it is the worst case scenario for voltage and

reactive power planning. Simulations have been carried out in

DIgSILENT PowerFactory 14.0 [27] platform.

Fig. 5. Test distribution system with disitributed generation units.

B. Distributed Generation Units

DG units considered in this study include conventional

synchronous generator along with large integration of wind

and solar generators. Ten wind turbines (each with 1MVA

rating) have been connected together at node 50 whereas; five

1MVA PV generators have been connected at node 19. DG

connection details have been listed in Table II. All these

generators are operating with unity power factor. Lack of

VAR generation leads to reactive power planning with fixed

capacitors and STATCOM.

TABLE II

DISTRIBUTED GENERATION: CAPACITY AND LOCATION

DISTRIBUTED

GENERATOR

DG1 DG2 DG3

Type Synchronous

Generator

Wind

Generator

Photovoltaic

Generator

Location bus 4 50 19

MVA rating 15 1.0×10 1.0×5

Power factor 1 1 1

C. STATCOM and Voltage Recovery

In order to fulfill primary requirement of ±10% of

continuous voltage at PCC, Reactive Tabu search technique

has been used for placing optimal capacitors and "V/"IR

values for all those optimal nodes are calculated with small

perturbations [13]. Fault simulation is performed with three

phase low-impedance fault at node 24 (at electrical vicinity of

DG1) at 1sec and it has been cleared after 10 cycles as shown

in Fig. 6. Simulation results show that without any VAR

support (i.e. without any capacitor and STATCOM), voltage

at PCC node 4 fails to recover within 2sec and demands

tripping of DG1. Among all the optimal capacitor nodes, the

most negative "V/"IR value (-0.162) has been found on node

27. Placing a STATCOM of zero reactive power set-point

along with optimal capacitor of 1.2MVAr on that node will

result in voltage recovery within 0.94sec satisfying grid

requirement in [17]. STATCOM parameters have been listed

in Table III in Appendix. Voltage at bus 4 does not cross

overvoltage limit in any of these cases because of the nature

of generation.

Fig. 6. Voltage recovery at PCC of synchronous generation unit (bus 4) with

balanced three phase fault at bus 24.

To observe the overvoltage phenomenon, time domain

simulations are carried out with fault near to PE-interfaced

DG units i.e. DG2 and DG3. A low impedance three phase

short circuit fault is placed at bus 9, which is close to wind

generator DG2 at bus 50. Figure 7 shows voltage recovery

with various levels of dispatch of wind generation. It can be

observed that without any STATCOM support, 100% dispatch

has the longest recovery time as found to be 1.16sec. As

voltage at bus 50 fails to come back to 1.1pu within 1sec, grid

standards demand tripping of wind generation unit due to

violation of overvoltage limit [17], [19]. With lower levels of

dispatch, recovery is fast enough to avoid tripping. However,

reactive planning need to be prepared considering worst case

scenario. Hence, for the rest of the simulations, 100% dispatch

has been considered for both wind and solar generation.

Fig. 7. Voltage recovery at PCC of wind generator (bus 50) with various

levels of dispatch.

6

Figure 8 shows the improvement in voltage recovery with

inclusion of STATCOM at node 27. Also, because of the

presence of STATCOM, overshoot at fault clearing is

reduced to 1.1, which is much below the permitted overshoot

range in [17], [19]. Reduction of overshoot is explicable from

Fig. 9 where MVAR is found to be absorbed by STATCOM

after clearing fault.

Fig. 8. Voltage recovery at PCC of wind generator (bus 50) with balanced

three phase fault at bus 9.

Fig. 9. MVAR output from STATCOM with balanced three phase fault at bus

9.

Though three phase short circuit is the severest fault to study,

a case study is performed with single line to ground fault

(phase “a”), which is shown in Fig. 10. The positive sequence

voltage, shown in Fig. 10, does not demonstrate any voltage

recovery problem with this asymmetric fault.

Fig. 10. Positive sequence voltage at PCC of wind generator (bus 50) with

asymmetric fault at bus 9.

A similar fault study as shown in Fig. 11 is performed with

photovoltaic plant at bus 19, where a three phase low

impedance short circuit is placed at bus 6 and cleared after

10cycles. Because of the smaller size of the plant (compared

to wind plant at bus 50), the overvoltage problem is not that

severe as in Fig. 8. However, the overshoot at fault clearing

crosses 1.2pu, which is the overvoltage limit for IEEE 1547

[17]. Because of crossing the permitted range, generator unit

at bus 19 demands tripping. Inclusion of STATCOM at node

27 reduces the overshoot to permitted range and solve this

overvoltage tripping issue. A case study with single line to

ground fault at bus 6 as shown in Fig. 12 does not show any

significant problem with voltage recovery at bus 19.

Fig. 11. Voltage recovery at PCC of PV generation unit (bus 19) with

balanced three phase fault at bus 6.

Fig. 12. Positive sequence voltage at PCC of PV generation unit (bus 19) with

asymmetric fault at bus 6.

Hence, with large penetration of full-converter based small-

scale PE generation units, overvoltage issue may cause

tripping if proper measures are not taken. Results show that

this problem is more prominent with increased aggregation

and full rated operation of generation units.

VII. CONCLUSIONS

Recently there has been a large increase in small-scale

distributed generation units. A significant portion of this

7

generation is comprised of power-electronic interfaced solar

and wind plants. In this paper, we have investigated the

overvoltage issue that can be profound in a system with large

number of this type of decoupled generators. An analysis of

the origin and behavior of overvoltage dynamics have been

presented. Grid specifications due to overvoltage issue have

been discussed. An industrial system with large integration of

wind and solar has been utilized to demonstrate the

overvoltage problem. A sensitivity index "V/"IR based

reactive planning approach, previously used for providing

LVRT, has been utilized to solve the overvoltage tripping

problem. Results establish the effectiveness of the

methodology in handling overvoltage issue and offers flawless

integration of small-scale DG units with power-electronic

interface. Further studies will be carried out in future to obtain

more precise and quantitative relationship among disturbance

magnitudes, transient overvoltage and voltage recovery at

PCC.

VIII. APPENDIX

TABLE III

STATCOM PARAMETERS

Pow

er

Ratin

g

(MV

AR)

Reac

tive

powe

r set-

point

(MV

AR)

Transf

ormer

Kv

(p

u)

Tv

(s)

Kp

(p

u)

Tp

(s)

Kd

(p

u)

Td

(s)

Kq

(p

u)

Tq

(s)

1.2 0 13.8

kV/0.4

kV

0.4 0.0

02

10 0.0

02

0.6 0.0

02

0.6 0.0

1

IX. REFERENCES

[1] J. A. P. Lopes, N. Hatziargyriou, J. Mutale, P. Djapic and N. Jenkins,

"Integrating distributed generation into electric power systems: A review

of drivers, challenges and opportunities," Electric Power Systems

Research, vol. 77, pp. 1189-1203, 2007.

[2] S. Zhao, W. A. Qureshi and N. K. C. Nair, "Influence of DFIG models

on fault current calculation and protection coordination," in IEEE Power

and Energy Society General Meeting(PESGM'11), Detroit, Michigan,

USA, 2011..

[3] J. Keller and B. Kroposki, "Understanding Fault Characteristics of

Inverter-Based Distributed Energy Resources," National Renewable

Energy Laboratory, Colorado 80401-3393, Technical Report NREL/TP-

550-46698, January, 2010.

[4] R. Hudson , "PV Inverters with VAR Control, LVRT, and Dynamic

Control", High Penetration Photovoltaics Workshop, 2010. Available at:

http://www.nrel.gov/eis/pdfs/hppv_p3_t1_hudson.pdf

[5] C. Schauder, "Impact of FERC 661-A and IEEE 1547 on Photovoltaic

inverter design," in IEEE Power and Energy Society General Meeting

(PESGM'11), Detroit, Michigan, USA, 2011.

[6] F. A. Viawan and D. Karlsson, "Voltage and Reactive Power Control in

Systems With Synchronous Machine-Based Distributed Generation,"

IEEE Transactions on Power Delivery, vol. 23, no. 2, pp. 1079-1087,

2008.

[7] S. Foster, L. Xu and B. Fox, "Coordinated reactive power control for

facilitating fault ride through of doubly fed induction generator- and

fixed speed induction generator-based wind farms," IET Renewable

Power Generation, vol. 4, no. 2, pp. 128-138, 2010.

[8] B. Kroposki, C. Pink, R. DeBlasio, H. Thomas, M. Simoes and P. K.

Sen, "Benefits of Power Electronic Interfaces for Distributed Energy

Systems," IEEE Transactions on Energy Conversion, vol. 25, no. 3, pp.

901-908, 2010.

[9] J. M. Carrasco, L. G. Franquelo, J. T. Bialasiewicz, E. Galvan, R. C. P.

Guisado, M. A. M. Prats, J. I. Leon and N. Moreno-Alfonso, "Power-

Electronic Systems for the Grid Integration of Renewable Energy

Sources: A Survey," IEEE Transactions on Industrial Electronics, vol.

53, no. 4, pp. 1002-1016, 2006.

[10] V. Akhmatov, "Analysis of dynamic behavior of electric power systems

with large amount of wind power," PhD Thesis, Ørsted DTU, Denmark,

2003.

[11] Y. Jun, L. Hui, L. Yong and C. Zhe, "An Improved Control Strategy of

Limiting the DC-Link Voltage Fluctuation for a Doubly Fed Induction

Wind Generator," IEEE Transactions on Power Electronics, vol. 23, no.

3, pp. 1205-1213, 2008.

[12] A. Yazdani and R. Iravani, Voltage-sourced converters in power systems

: modeling, control, and applications. Oxford: Wiley, 2010.

[13] T. Aziz, U. P. Mhaskar, T. K. Saha, and N. Mithulananthan, "A Grid

Compatible Methodology for Reactive Power Compensation in

Renewable Based Distribution System," in IEEE Power and Energy

Society General Meeting (PESGM'11), Detroit, Michigan, USA, 2011.

[14] G. C. Paap, "Symmetrical components in the time domain and their

application to power network calculations," IEEE Transactions on

Power Systems, vol. 15, no. 2, pp. 522-528, 2000.

[15] N. R. J. Wright-Smith, J. A. Diaz de Leon II, "Single Point vs.

Distributed FACTS Installations.," presented at the CIGRE SCB4

Colloquium - HVDC and Power Electronics: Enhancing the

Transmission Networks, Brisbane, Australia, 2011.

[16] C. Wessels and F. W. Fuchs, "High voltage ride through with FACTS

for DFIG based wind turbines," in 13th European Conference on Power

Electronics and Applications(EPE '09), 2009.

[17] "IEEE Application Guide for IEEE Std 1547, IEEE Standard for

Interconnecting Distributed Resources with Electric Power Systems,"

IEEE Std 1547.2-2008, pp. 1-207, 2009.

[18] R. C. Dugan, T. S. Key, and G. J. Ball, "Distributed resources

standards," IEEE Industry Applications Magazine, vol. 12, pp. 27-34,

2006.

[19] A. E. M. Commission, "National Electricity Amendment (Technical

Standards for wind and other generators connections) Rule 2007," 8

March, 2007, www.aemc.gov.au.

[20] R. D. Narend Reddy, Addressing Global Wind Farm Interconnection

Challenges, American Superconductor (AMSC), 2009. Available at:

http://windenergy.org.nz/documents/conference08/davey.pdf

[21] J. F. Conroy and R. Watson, "Low-voltage ride-through of a full

converter wind turbine with permanent magnet generator," IET

Renewable Power Generation, vol. 1, no. 3, pp. 182-189, 2007.

[22] G. Ramtharan, A. Arulampalam, J. B. Ekanayake, F. M. Hughes, and N.

Jenkins, "Fault ride through of fully rated converter wind turbines with

AC and DC transmission," Renewable Power Generation, IET, vol. 3,

pp. 426-438, 2009.

[23] M. Molinas, S. Jon Are, and T. Undeland, "Low Voltage Ride Through

of Wind Farms With Cage Generators: STATCOM Versus SVC," IEEE

Transactions on Power Electronics, vol. 23, no. 3, pp. 1104-1117, 2008.

[24] Y. M. Alharbi, A. M. S. Yunus, and A. Abu-Siada, "Application of

STATCOM to Improve the High-Voltage-Ride-Through Capability of

Wind Turbine Generator," in IEEE PES Conference on Innovative Smart

Grid Technologies Asia 2011, Perth, Western Australia, 13-16

November, 2011.

[25] P. Rao, M. L. Crow, and Z. Yang, "STATCOM control for power system

voltage control applications," IEEE Transactions on Power Delivery,

vol. 15, no. 4, pp. 1311-1317, 2000.

[26] "IEEE Recommended Practice for Industrial and Commercial Power

Systems Analysis," IEEE Std 399-1997, p. I, 1998.

[27] DIgSILENTGmbH, "DIgSILENT PowerFactory V14.0 -User Manual,"

DIgSILENT GmbH, 2008.

8

X. BIOGRAPHIES

Tareq Aziz (M’09) was born in Dhaka, Bangladesh.

He completed his B.Sc. (Engg.) and M.Sc. (Engg.) in

Electrical & Electronic Engineering both from

Bangladesh University of Engineering & Technology

(BUET) in 2002 and 2005 respectively. Currently he

is doing his PhD in School of ITEE, The University

of Queensland, Australia. His research interests

include distributed generation, renewable energy

integration, power system stability and signal

processing.

Tapan Kumar Saha (M’93, SM’97) was born in

Bangladesh in 1959 and immigrated to Australia in

1989. He received B.Sc.Eng. Degree in 1982 from

Bangladesh University of Engineering &

Technology, Dhaka, Bangladesh, M.Tech. in 1985

from the Indian Institute of Technology, New Delhi,

India and PhD in 1994 from the University of

Queensland, Brisbane, Australia.

Tapan is currently a Professor in Electrical

Engineering in the School of Information Technology

and Electrical Engineering, University of Queensland, Australia. Previously

he has had visiting appointments for a semester at both the Royal Institute of

Technology (KTH), Stockholm, Sweden and at the University of Newcastle

(Australia). He is a Fellow of the Institution of Engineers, Australia. His

research interests include condition monitoring of electrical plants, power

systems and power quality.

Nadarajah Mithulananthan (M’02, SM’10)

received his Ph.D. from University of Waterloo,

Canada in Electrical and Computer Engineering in

2002. His B.Sc. (Eng.) and M. Eng. Degrees are from

the University of Peradeniya, Sri Lanka, and the

Asian Institute of Technology, Bangkok, Thailand, in

May 1993 and August 1997, respectively. He has

worked as an electrical engineer at the Generation

Planning Branch of the Ceylon electricity Board, and

as a researcher at Chulalongkorn University,

Bangkok, Thailand. Dr. Mithulan is currently a senior lecture at the University

of Queensland (UQ), Brisbane, Australia. Prior to joining UQ he was

associate Professor at Asian Institute of Technology, Bangkok, Thailand. His

research interests are integration of renewable energy in power systems and

power system stability and dynamics.