AGENDA ITEM - Maharashtra Pollution Control Board

154
MPCB-CAC-0000000058 (CAC Meeting Number : 8 dated August 6, 2019) Page 1 of 154 ITEM NO: 1 - Unique Number: MPCB-CONSENT-0000064230 Fresh CAC ITEM Region: SRO - Pune II Section: CAC Date: 22.05.2019 UAN Number: MPCB-CONSENT-0000064230 TAG CAC Name & Address: Keihin Fie Pvt. Ltd. (Plot no B3,Mahalunge,MIDC Chakan) Location of Industrial unit: B-3 ,MIDC Chakan Chakan MIDC Khed Email: [email protected] Telephone number: 9881473048 Industry Type: R2 Automobile Manufacturing (integrated facilities) Industry Category: RED Project Details: Existing project Consent Applied For 1st Consent to Operate for expansion and amalgamation with existing consent Application Date January 4,2019 Date of receipt of CAC/CC cell 14.02.2019 Capital Investment in Rs. (Crs) Existing Proposed Total 163.83 75 283.83 Details of project : Existing project Total Plot area (sq.m.) 50050 (sq.m) Construction BUA (sq.m.) 17048 (sq.m) Product and By-product details Sr.no Product Name Quantity 1 Fuel Injection System 2,00,000 No/M 2 Spares for Fuel Injection System 1,80,000 No/M 3 Check Valve 2,50,000 No/M Sr.no By-Product Name Quantity 4 NA 0 Applicabilty of CRZ Clearence Distance from river Industrial location policy Eco-sensitive Moratonium EC Direction of MoEF for western ghats NO YES NO NO NO NO NO If Yes provide details Indrayani - 7.00 Km Based on: Status: Not Applied Details of CCA,Consents,Authorization and EC obtained Consent no. Consent granted date Validity Capital Investment in Crs Total plot area Construction BUA (FSI+Non-FSI) Remarks C2R BO/CAC-Cell/UAN No. 0000048313-18/5th CAC-1904000971 23.04.2019 30.06.2021 163.83 C2E BO/CAC-Cell/UAN No. 0000043233-18/E/5th CAC-1811001392 29.11.2018 COU 75 Existing production details C to O Sr.No Product Name Max quantity 1 Carburetors 4,78,000 Nos./M 2 Spares for Carburetors 3,00,000 Nos./M C to E Sr.No Product Name Max quantity 1 Fuel Injection System 2,00,000 No/M 2 Spares for Fuel Injection System 1,80,000 No/M 3 Check Valve 2,50,000 No/M Bio-Medical Waste Details Annual Rpt. (Form-II): Accident Rpt. (Form-III): MPCB-CAC-0000000058

Transcript of AGENDA ITEM - Maharashtra Pollution Control Board

MPCB-CAC-0000000058 (CAC Meeting Number : 8 dated August 6, 2019) Page 1 of 154

ITEM NO: 1 - Unique Number: MPCB-CONSENT-0000064230Fresh CAC ITEMRegion: SRO - Pune II Section: CAC Date: 22.05.2019UAN Number: MPCB-CONSENT-0000064230 TAG CACName & Address: Keihin Fie Pvt. Ltd. (Plot no B3,Mahalunge,MIDC Chakan)Location ofIndustrial unit: B-3 ,MIDC Chakan Chakan MIDC Khed

Email: [email protected] Telephone number: 9881473048Industry Type: R2 Automobile Manufacturing (integrated facilities)Industry Category: REDProject Details: Existing project

Consent Applied For1st Consent to

Operate for expansionand amalgamation

with existing consentApplication Date January

4,2019Date of receipt ofCAC/CC cell 14.02.2019

Capital Investment in Rs. (Crs)Existing Proposed Total

163.83 75 283.83Details of

project :Existingproject

Total Plot area(sq.m.) 50050 (sq.m) Construction

BUA (sq.m.) 17048 (sq.m)Product and By-product details

Sr.no Product Name Quantity1 Fuel Injection System 2,00,000 No/M2 Spares for Fuel Injection System 1,80,000 No/M3 Check Valve 2,50,000 No/MSr.no By-Product Name Quantity4 NA 0Applicabilty

ofCRZ

ClearenceDistance

from riverIndustrial

location policy Eco-sensitive Moratonium EC Direction of MoEF forwestern ghats

NO YES NO NO NO NO NO

If Yesprovidedetails

Indrayani -7.00 Km

Basedon:

Status:NotApplied

Details of CCA,Consents,Authorization and EC obtained Consent no. Consent

granted date ValidityCapital

Investmentin Crs

Total plotarea

ConstructionBUA

(FSI+Non-FSI)Remarks

C2RBO/CAC-Cell/UAN

No.0000048313-18/5thCAC-1904000971

23.04.2019 30.06.2021 163.83

C2EBO/CAC-Cell/UAN

No.0000043233-18/E/5th

CAC-181100139229.11.2018 COU 75

Existing production details

C to OSr.No Product Name Max quantity

1 Carburetors 4,78,000 Nos./M

2 Spares for Carburetors 3,00,000 Nos./M

C to E

Sr.No Product Name Max quantity

1 Fuel Injection System 2,00,000 No/M

2 Spares for Fuel Injection System 1,80,000 No/M

3 Check Valve 2,50,000 No/M

Bio-Medical Waste DetailsAnnual Rpt.(Form-II):Accident Rpt.(Form-III):

MPCB-CAC-00

0000

0058

MPCB-CAC-0000000058 (CAC Meeting Number : 8 dated August 6, 2019) Page 2 of 154

BMWGeneration

Sr.No Category Max quantity (Kg/M)

1 NA NA

Disposal @CBMWTF: No

Member ofCBMWTF:CaptiveDisposal: No

Incinerator Capacity Fuel Type Auto Feeding Temp.Recorder Online Monitoring

Autoclave Type(Vertical/Horizontal)

Temp &Pressure

Recording

Shredder Plastic WasteDisposal

Compliance of Water Pollution Related Conditions Purpose Water Consumption

in CMD as appliedEffluent generationas applied in CMD

TreatmentSteps

DisposalDetails

Remarks/Adequeteland Available

1 Domestic Purposes 15 (exi-95 + CtoE-15= 110 CMD)

8 (exi-82 + CtoE-8 =90 CMD)

STP ofcapacity 82

CMDprovided

67 CMDRecycleand 90

CMD onland for

gardening

4.25 acres of land

2Processing wherebywater gets polluted &pollutants are easilybiodegradable

10 (exi-75 + CtoE- 10= 85 CMD)

9 (exi-85 + CtoE-9 =94 CMD)

ETP ofcapacity 75

CMDprovided

67 CMDRecycleand 90

CMD onland for

gardening

4.25 acres of land

3Processing wherebywater gets polluted &pollutants are noteasily biodegradable

00 00 --NA-- --NA-- NA

4IndustrialCooling,spraying inmine pits or boilerfeed

5.0 (exi- 5 + CtoE- Nil= 5 CMD) 00 --NA-- --NA-- NA

5Others such asgardening,agricultureetc

00 NA NA NA NA

Whether any deviation in water consumption observed compared toprevious consent NO Remarks:

Compliance to existing unit in case applied for expansion C to E/O/R NOSource of water supply

In case proposed discharge to CETP forfurther treatment

CETP Capacity to handle additional load NOName of CETP

Existing JVS results EffluentSr.no. Date of visit Board official's

name:Whether samplecollected or not:

Whether results areconfirming to standardsor not (Exceedingparameter with value)

1 16.05.2018 (ETPOutlet) YES YES

1 16.05.2018 (STPOutlet) YES YES

Details of fuel consumption and APC system as applied :-Sr. no Source Stack Fuel type Quantity Height-I,II,III APC system

detail

1 DG Set S-1,S-2,S-3,S-4,S-5 HSD 500 (Kg/hr.) 5 mExhaustprovided withmuffler &acoustic

2 RemeltingFurnance S-7 PNG 6 (Kg/hr.) 5 m Controls

Provided

3 AL DC Machines S-8,S-9,S-10(ALMC 3&4) PNG 12 (Kg/hr.) 5 m Controls

Provided

MPCB-CAC-00

0000

0058

MPCB-CAC-0000000058 (CAC Meeting Number : 8 dated August 6, 2019) Page 3 of 154

4 SurfaceTreatment Plant S-12 NA 10 (Kg/hr.) 5 m Controls

Provided

5AL Machineno.5(AnnextureAttached)

S-18 PNG 12 (Kg/hr.) 5 m ControlsProvided

6 Fire HydrantPump S-14 HSD 15 (Kg/hr.) 5 m Controls

Provided

7New ShotBlastingMachine

S-17 NA 00 (Kg/hr.) 5 m Control provides

8 ChasisDynamometer S-16 Petrol 0 (Kg/hr.) 5 m Controls

ProvidedWhether any deviation in fuel consumptionand APC system observed compared toprevious consent

NO Remarks:

Compliance to existing unit in case appliedfor expansion C to E/O/R NO

Existing JVS results AirSr.no. Date of visit Board official's

name:Whether samplecollected or not:

Whether results areconfirming to standardsor not (Exceedingparameter with value)

1 NO NO

Compliance of Haz. Waste ConditionDetails of hazardous waste as applied

Sr. no Type of waste Category Quantity & UOM Treatment Disposal1 5.1 Used or spent oil 5.1 1000 Kg/Day Authorized Agency Authorized Agency

2 5.2 Wastes or residuescontaining oil 5.2 50 Kg/Day Authorized Agency Authorized Agency

36.2 Zinc fines or dust orash or skimmings indispersible form

6.2 500 Kg/Day Authorized Agency Authorized Agency

4 12.1 Acidic and alkalineresidues 12.1 130 Kg/Day Authorized Agency Authorized Agency

512.3 Spent bath andsludge containingsulphide,cyanide andtoxic metals

12.3 1000 Kg/Day Authorized Agency Authorized Agency

635.3 Chemical sludgefrom waste watertreatment

35.3 130 Kg/Day Authorized Agency Authorized Agency

7 21.1 Process wastes,residues and sludges 21.1 100 Kg/Day Authorized Agency Authorized Agency

8 37.1 Sludge from wetscrubbers 37.1 1 Kg/Day Authorized Agency Authorized Agency

9 Other Hazardous Waste Other 25 Kg/Day Authorized Agency Authorized Agency10 NA NA 0 --NA-- NA NAWhether any deviation in Hz waste generation and itsdisposal,observed compared to previous consent NO Remarks:

Compliance of existing unit in case applied for expansion C to E/O/R NO

Submission of Annual Return (Form IV) NO Submission Date

Compliance of Non Hazardous/ MSW conditionDetails of Non hazardous/MSW as applied

Sr. no Type of waste Quantity & UOM Treatment Disposal1 Plastic/Waste Paper 1000 Kg/M Recycle Authorised processor2 Metal Scrap 15 MT/M Sale Sale3 Metal Container 200 No/M Sale SaleWhether any deviation in Non-Hz waste generation and itsdisposal,observed compared to previous consent NO Remarks:

Compliance of existing unit in case applied for expansion C to E/O/R NOWaterCess Returns filed upto: Paid Upto: Apr 30 2018

12:00:00:000AM

MPCB-CAC-00

0000

0058

MPCB-CAC-0000000058 (CAC Meeting Number : 8 dated August 6, 2019) Page 4 of 154

Directionissued (ifany)

BGDetails Amount Validity

BG obtained towards complience ofa) Consent/CCA condition b) directions

1 Rs. 5 lakh(CtoE) 31.12.2023 Towards compliance of consent to

establish conditions NA

2 Rs. 5 lakh(CtoR) 31.12.2021 Towards O&M of pollution control

system NA

3 Rs. 5 lakh(CtoR) 31.12.2021

Industry shall segregate the 77CMD metal bearing effluent andtreated separately and reusedagain in the process. The non-metal bearing effluent shall bemaximum recycle and remaining90 CMD shall be used on land forgardening on 4.25 acres

NA

4 Rs. 5 lakh(CtoR) 31.12.2021

Industry shall provideevaporator/MEE for treatment ofRO reject

NA

Details of BGfortified/enchasedfor noncomplience,if any:Submission ofEnvironmentalStatement

NO Year Yes,07/09/2017

Details of consentfee paid Amount Rs: 1,00,000/- Terms 1

In case of 1st C to OComplience of C toE conditions

Remarks

Recommendation ofTAC

MPCB-CAC-00

0000

0058

MPCB-CAC-0000000058 (CAC Meeting Number : 8 dated August 6, 2019) Page 5 of 154

Recommendations

Shri. Upendra C. Kulkarni (SRO-Pune II):-Process & put up with report.(Jan 9 2019 01:37:28:000PM)

Shri. Sameer S. Vastre (FO-Pune II):-Industry has obtained consent to operate (Red/LSI) category dated 15.6.2016 for manufacturingof Carburetors:478000 Nos/M,Spares for Carburetores: 300000 Nos/M and said consent wasexpired on 30.6.2018 and applied for renewal of consent and said application and submitted tohigher authority.Industry has obtained consent to establish for expansion/new products dated 29.11.2018 formanufacturing of 1) Fuel Injection system:200000 Nos/M, 2) Spares for fuel Injectionsystem:180000 Nos/M, Check Valve:250000 Nos/M.Now industry has applied for 1st consent to operate separately for above mentioned products.Industry has provided ETP consisting of primary and tertiary treatment system of capacity:75CMD and treated water is sending to RO plant and RO permeate is reused in process and ROreject is sent to filter feed tank of ETP for further treatment and disposal. Industry has providedSTP of capacity:82CMD for treatment of domestic effluent with ozonisation system . Flow meterprovided to RO permeate.Industry has installed shot blasting machine with scrubber and dust collector as APC system.Industry will be uses existing Aluminum DC machines(3 Nos) and remelting furnace and onesurface treatment plant ( existing ) with scrubber arrangement is provided for thisexpansion/new products.The installation work of assembly line and machine shop’s installation is in progress and near tocomplete for expansion/new products.Industry has submitted BG(Rs:5.0 Lacs) as per consent to establish condition and same is validupto 5.7.2021Industry has submitted undertaking for expansion only i.e Rs:75 Crs and paid consent fees ofRs:100000/- dated 8.1.2019.Submitted for further order please

(Feb 12 2019 10:04:31:000AM)

Shri. Upendra C. Kulkarni (SRO-Pune II):-Remarks of FO may please be seen. Applied for consent to operate for mfg of carburetors, sparesof carburetors, fuel injection system, spares of fuel injection system, check valve byamalgamation of C2E for expansion with existing C2O. The consent renewal application issubmitted to HQ. ETP provided for trade effluent treatment, STP provided for sewage treatment.Dust collector & scrubber provided to shot blasting. The work of expansion project is inprogress. It is submitted that consent to operate with expansion may be granted subject tocompletion of work of installation of expansion machinery.(Feb 13 2019 06:51:02:000PM)

Mr.P.K.Mirashe(AST) (CAC-CELL-HQ):-Pl Process and put up(Feb 14 2019 10:28:48:000AM)

Other RelevantInformation

SRO reported that ETP provided for trade effluent treatment, STP provided for sewagetreatment. Dust collector & scrubber provided to shot blasting. The work of expansion project isin progress. It is submitted that consent to operate with expansion may be granted subject tocompletion of work of installation of expansion machinery.

Recommendation ofCAC/CC Cell

It is noted that industry failed to provide evaporator/MEE for treatment of RO reject. Alsoindustry has not up-graded the existing STP and ETP of the adeqaute size so as to take the loadfrom effluent generated from expansion activity. The work of expansion project is in progress.

In view of above, we may issue SCN for refusal of 1st Consent to Operate for expansion andamalgamation with existing consent due to above non-compliance.

ConsentRecommended forperiod upto as perSectoral Approachpolicy

SCN for refusal

FINAL REMARKS/DECISION as on 4th CAC Meeting of 2019-20 (Booklet No 6) dated12-06-2019

DECISION

It is noted that industry failed to provide evaporator/MEE for treatment of RO reject. Alsoindustry has not up-graded the existing STP and ETP of the adeqaute size so as to take the loadfrom effluent generated from expansion activity. The work of expansion project is in progress.

In view of above, we may issue SCN for refusal of 1st Consent to Operate for expansion andamalgamation with existing consent due to above non-compliance.

MPCB-CAC-00

0000

0058

MPCB-CAC-0000000058 (CAC Meeting Number : 8 dated August 6, 2019) Page 6 of 154

InternalRemarks/Discussion:

The application for 1st Consent to Operate for expansion and amalgamation with existing consentwas discussed in CAC dated 12.06.2019. During the meeting, Committee noted that industryfailed to provide evaporator/MEE for treatment of RO reject. Also failed to up-graded theexisting STP and ETP of the adequate size so as to take the load from effluent generated fromexpansion activity.Committee also noted that the work of expansion project is in progress.In view of above, it was decided to call the industry for presentation before CAC to brief thepresent status of the project and compliance of consent conditions.Accordingly, Industry was called for presentation to explain the present operational status ofproduction and pollution control systems. Industry has made the Presentation, the details are asbelow;1. M/s. Keihin FIE Pvt. Ltd is joint venture company promoted by Keihin Corporation Japan andFuel Instruments and engineers, India Pvt. Ltd.2. Presently, the company is engaged in manufacturing of carburetors. After six month KeihinFIE will start fuel injection system manufacturing at Chakan plant with utilization of existinginfrastructure and machinery.3. The objective of new product is complying with requirement of BS6 standards. Currently,India is adopting BS4 norms. But as per the Supreme Court direction, GoI had given deadline tochange over emission norms from BS4 to BS6 well before March 2020.4. The proposed product will not change the basic raw material and doesn’t lead to change inwater and waste water attributes during operational stage.5. Dust collector will be provided to shot blasting unit.6. STP of capacity 82 CMD provided and treated effluent is used for landscaping, flushingpurpose and RO permeate will be used in process.7. Industry has proposed to provide RO followed by Evaporator so as to achieve ZLD for metalbearing effluent. Industry has already issued the purchase order and installation andcommissioning of RO and evaporator will be completed by Dec. 2019. After due deliberation, it was decided to recommend the case for 1st Consent to Operate forexpansion and amalgamation with existing consent with following conditions; 1. Industry shall restrict the generation of trade effluent quantity as per existing consent till theyinstall RO and Evaporator. Consent shall be issued after receipt of verification report from SRO regarding completion ofinstallation and commissioning of plant and machinery and installation of RO and evaporator.

Outstandingdirections, if any:Decision on Grant ofConsent: NOT APPROVED

Consent granted upto:

Resubmission Remarks

ResubmissionRemarks

Personal hearing was extended to the PP on 09/07/2019 and Industry has made the Presentation,the details are as below;1) M/s. Keihin FIE Pvt. Ltd is joint venture company promoted by Keihin Corporation Japan andFuel Instruments and engineers, India Pvt. Ltd.2) Presently, the company is engaged in manufacturing of carburetors. After six month KeihinFIE will start fuel injection system manufacturing at Chakan plant with utilization of existinginfrastructure and machinery.3) The objective of new product is complying with requirement of BS6 standards. Currently,India is adopting BS4 norms. But as per the Supreme Court direction, GoI had given deadline tochange over emission norms from BS4 to BS6 well before March 2020.4) The proposed product will not change the basic raw material and doesn’t lead to change inwater and waste water attributes during operational stage.5) Dust collector will be provided to shot blasting unit.6) STP of capacity 82 CMD provided and treated effluent is used for landscaping, flushingpurpose and RO permeate will be used in process.7) Industry has proposed to provide RO followed by Evaporator so as to achieve ZLD for metalbearing effluent. Industry has already issued the purchase order and installation andcommissioning of RO and evaporator will be completed by Dec. 2019.

III. We may consider the application by imposing following conditions

1) Industry shall restrict the generation of trade effluent quantity as per existing consent tillthey install RO and Evaporator.

Consent shall be issued after receipt of verification report from SRO regarding completion ofinstallation and commissioning of plant and machinery and installation of RO and evaporator

MPCB-CAC-00

0000

0058

MPCB-CAC-0000000058 (CAC Meeting Number : 8 dated August 6, 2019) Page 7 of 154

ITEM NO: 2 - Unique Number: MPCB-CONSENT-0000064604Fresh CAC ITEMRegion: SRO - Kalyan III Section: CAC Date: 03.06.2019UAN Number: MPCB-CONSENT-0000064604 TAG CACName & Address: MIRC ELECTRONICS LTD (Village Kudus, Bhiwandi - Wada Road,)Location ofIndustrial unit:

234C, 236, 237A/B, 240, 241, 242, 244, 246, 247, 247, 248, 249, 250, 251, 226, 226P, 239VILLAGE KUDUS, BHIWANDI - WADA ROAD WADA

Email: [email protected] Telephone number: 9766258997Industry Type:Industry Category: REDProject Details: Existing project

Consent Applied For Renewal of consentwith decrease in CI Application Date January

10,2019Date of receipt ofCAC/CC cell 27.02.2019

Capital Investment in Rs. (Crs)Existing Proposed Total

288.44 -36.02 252.4257Details of

project :Existingproject

Total Plot area(sq.m.) 216640 (sq.m) Construction

BUA (sq.m.) 67374 (sq.m)Product and By-product details

Sr.no Product Name Quantity1 COLOUR TELEVISIONS 2,50,000 No/M2 SET TOP BOX CAS 83,330 No/M3 TUNERS 3,00,000 No/M4 AIR CONDITITIONERS 41,660 No/M5 WASHING MACHINES 41,660 No/M6 LCD/LED TELEVISION & LED LIGHTING 75,000 No/M7 PLASTIC INJECTION MOLDED PARTS 830 Ton/M8 EPS SHAPE 125 Ton/MSr.no By-Product Name Quantity9 NA 0Applicabilty

ofCRZ

ClearenceDistance

from riverIndustrial

location policy Eco-sensitive Moratonium EC Direction of MoEF forwestern ghats

NO YES NO NO NO NO NO

If Yesprovidedetails

Tansa - 10.00Km

Basedon:

Status:NotApplied

Details of CCA,Consents,Authorization and EC obtained Consent no. Consent

granted date ValidityCapital

Investmentin Crs

Total plotarea

ConstructionBUA

(FSI+Non-FSI)Remarks

C2R BO/CAC-Cell/UAN No.0000018399-16/CAC-1711000635 17.11.2017 28.02.2019 288.44

Existing production details

C to O

Sr.No Product Name Max quantity

1 COLOUR TELEVISIONS 2,50,000 No/M

2 SET TOP BOX CAS 83,330 No/M

3 TUNERS 3,00,000 No/M

4 AIR CONDITITIONERS 41,660 No/M

5 WASHING MACHINES 41,660 No/M

6 LCD/LED TELEVISION & LED LIGHTING 75,000 No/M

7 PLASTIC INJECTION MOLDED PARTS 830 Ton/M

8 EPS SHAPE 125 Ton/M

C to ESr.No Product Name Max quantity

1 NA NA

Bio-Medical Waste Details

MPCB-CAC-00

0000

0058

MPCB-CAC-0000000058 (CAC Meeting Number : 8 dated August 6, 2019) Page 8 of 154

Annual Rpt.(Form-II):Accident Rpt.(Form-III):

BMWGeneration

Sr.No Category Max quantity (Kg/M)

1 NA NA

Disposal @CBMWTF: No

Member ofCBMWTF:CaptiveDisposal: No

Incinerator Capacity Fuel Type Auto Feeding Temp.Recorder Online Monitoring

Autoclave Type(Vertical/Horizontal)

Temp &Pressure

Recording

Shredder Plastic WasteDisposal

Compliance of Water Pollution Related Conditions Purpose Water Consumption

in CMD as appliedEffluent generationas applied in CMD

TreatmentSteps

DisposalDetails

Remarks/Adequeteland Available

1 Domestic Purposes 80 64STP of

capacity 75CMD

provided

On Landfor

GardeningTREATED WATERFOR GARDEN USE

2Processing wherebywater gets polluted &pollutants are easilybiodegradable

0 0 --NA-- --NA-- NA

3Processing wherebywater gets polluted &pollutants are noteasily biodegradable

5 5ETP of

capacity 5CMD

providedRecycle REUSED IN THE

PROCESS

4IndustrialCooling,spraying inmine pits or boilerfeed

85 0 --NA-- --NA--BOILER FEED

COOLING TOWER& SOFTEING

5Others such asgardening,agricultureetc

100 NA NA NA NA

Whether any deviation in water consumption observed compared toprevious consent YES

Remarks:Industry has reduced the trade effluent from 9 CMD to 5

CMD compared to existing consentCompliance to existing unit in case applied for expansion C to E/O/R NOSource of water supply

In case proposed discharge to CETP forfurther treatment

CETP Capacity to handle additional load NOName of CETP

Existing JVS results EffluentSr.no. Date of visit Board official's

name:Whether samplecollected or not:

Whether results areconfirming to standardsor not (Exceedingparameter with value)

1 NO NO

Details of fuel consumption and APC system as applied :-Sr. no Source Stack Fuel type Quantity Height-I,II,III APC system

detail

1 DG SET 1 1 HSD 90 (Kg/hr.) 6 MTR ABOVEROOF m NA

2 DG SET 2 2 HSD 90 (Kg/hr.) 6 MTR ABOVEROOF m NA

3 DG SET 3 3 HSD 175 (Kg/hr.) 6 MTR ABOVEROOF m NA

4 DG SET 4 4 HSD 175 (Kg/hr.) 6 MTR ABOVEROOF m NA

MPCB-CAC-00

0000

0058

MPCB-CAC-0000000058 (CAC Meeting Number : 8 dated August 6, 2019) Page 9 of 154

5 BOILERS 1 & 2 5 FURNANCE OIL 120 (Kg/hr.) 36 MTR ABOVEGROUND m NA

Whether any deviation in fuel consumptionand APC system observed compared toprevious consent

NO Remarks:

Compliance to existing unit in case appliedfor expansion C to E/O/R NO

Existing JVS results AirSr.no. Date of visit Board official's

name:Whether samplecollected or not:

Whether results areconfirming to standardsor not (Exceedingparameter with value)

1 NO NO

Compliance of Haz. Waste ConditionDetails of hazardous waste as applied

Sr. no Type of waste Category Quantity &UOM Treatment Disposal

1 21.1 Process wastes, residues andsludges 21.1 150 Kg/Day LAND FILLING CHWTSDF,

TALOJA

2 5.1 Used or spent oil 5.1 1.05 Kg/Day INCINERATIONCHWTSDF,TALOJA /AUTHORISEDPARTY

3 5.2 Wastes or residues containingoil 5.2 2.0 Kg/Day LAND FILLING

CHWTSDF,TALOJA /AUTHORISEDPARTY

4 31.1 Process residue and wastes 31.1 10 Kg/Day LAND FILLINGCHWTSDF,TALOJA /AUTHORISEDPARTY

533.1 Emptybarrels/containers/linerscontaminated with hazardouschemicals /wastes

33.1 12 Kg/Day RECYCLING /LAND FILLING

CHWTSDF,TALOJA /AUTHORISEDPARTY

6 NA NA 0 --NA-- NA NAWhether any deviation in Hz waste generation and itsdisposal,observed compared to previous consent NO Remarks:

Compliance of existing unit in case applied for expansion C to E/O/R NO

Submission of Annual Return (Form IV) NO Submission Date

Compliance of Non Hazardous/ MSW conditionDetails of Non hazardous/MSW as applied

Sr. no Type of waste Quantity & UOM Treatment Disposal

1 PLASTICE PACKING & SCRAPPARTS 12 Ton/Y NA

BY SALE TOAUTHORIZED VENDOR /RECYCLER

2 WOOD PACKING & SCRAPPARTS 75 Ton/Y NA

BY SALE TOAUTHORIZED VENDOR /RECYCLER

3 METAL PACKING & SCRAPPARTS 1.0 Ton/Y NA

BY SALE TOAUTHORIZED VENDOR /RECYCLER

Whether any deviation in Non-Hz waste generation and itsdisposal,observed compared to previous consent NO Remarks:

Compliance of existing unit in case applied for expansion C to E/O/R NOWaterCess Returns filed upto: Paid Upto: Jan 31 2016

12:00:00:000AMDirectionissued (ifany)

BGDetails Amount Validity

BG obtained towards complience ofa) Consent/CCA condition b) directions

1 Rs. 10 lakh 30.06.2019 Towards O&M of pollution controlsystem NA

MPCB-CAC-00

0000

0058

MPCB-CAC-0000000058 (CAC Meeting Number : 8 dated August 6, 2019) Page 10 of 154

Details of BGfortified/enchasedfor noncomplience,if any:

In previous consent BG of Rs. 5 lakh forfeited as JVS results are exceeding the consentedstandards.

Submission ofEnvironmentalStatement

NO Year YES, ON 12/09/2018

Details of consentfee paid Amount Rs: 10,09,703/- Terms two

In case of 1st C to OComplience of C toE conditions

Remarks

Recommendation ofTAC

Recommendations

Shri. Rajendra Rajput (SRO-Kalyan III):-pl. put up(Jan 17 2019 04:34:03:000PM)

Mrs. Aruna C. Jadhav(Aruna Rokde) (FO-Kalyan III):-Industry has applied for consent to renewal. Previous consent valid up to 28.02.2019. Industryengaged in manufacturing of electronic items Color Television, Set top box, Tunners, Airconditioners, Washing machines, Plastic injection molded parts. LCD, LED, EPA shapes moldedparts. Industry visited on 16.02.2019. During visit industry not in operation. Spray paintingactivity is closed form one year. Industry has carried out only assembles of machinery parts. Ind.eff. is 9.0 CMD. Industry has provided effluent treatment plant and consist of Primary andTertiary treatment. During visit ETP not in operation due to no generation of industrial effluent.STP is provided for treatment of domestic effluent and treated effluent is used on land forgardening. Industry has provided two boilers with common stack with height 36 Mtr. Furnace oilused as Fuel.Industry has obtained membership of CHWTSDF. Hazardous waste disposed on March 2018details enclosed. As per consent industry has submitted BG of Rs. 10.00 Lakhs (Top-up) for O&Mof pollution control system and valid up to 28.02.2019. Industry has obtained CGWA permissionof 4 nos of boar well. CI is decrease from Rs. 28844 lacs to 25242.57 lacs. Fees paid Rs.1009703/-. In view of above we may consider the case for renewal.

(Feb 20 2019 06:27:10:000PM)

Shri. Rajendra Rajput (SRO-Kalyan III):-industry has applied for consent to renewal. Previous consent valid up to 28.02.2019.presentlyonly Plastic injection molded parts. LCD, LED, EPA shapes molded parts.activity are in operationColor Television, Set top box, Tunners, Air conditioners, Washing machines are notmanufacturing at this location. Spray painting activity is closed form one year STP is providedfor treatment of domestic effluent and treated effluent is used on land for gardening. in view ofconsent may be granted(Feb 26 2019 06:29:24:000PM)

Mr.P.K.Mirashe(AST) (CAC-CELL-HQ):-Pl Process and put up(Feb 27 2019 10:29:41:000AM)

Other RelevantInformation

Field Officer visited the unit on 16.02.2019 and reported as below;1. Industry found not in operation.2. Spray painting activity is closed form one year.3. Industry has carried out only assembles of machinery parts. Ind. eff. is 9.0 CMD.4. Industry has provided effluent treatment plant and consist of Primary and Tertiary treatment.5. During visit ETP not in operation due to no generation of industrial effluent. STP is providedfor treatment of domestic effluent and treated effluent is used on land for gardening.6. Industry has obtained CGWA permission of 4 nos of boar well.

Recommendation ofCAC/CC Cell

We may consider the case for renewal of consent with decrease in CI for the period upto28.02.2024 by imposing following conditions;

1] Industry shall extend the existing BG of Rs. 10 lakh obtained towards O&M of pollutioncontrol system.

2] Industry shall abstract 170 CMD of ground water through four existing bore wells only. Noadditional ground water abstraction structures shall be constructed for this purpose as per NOCgranted by CGWA dated 01.05.2018.

Consent shall be issued after receipt of latest JVS results from SRO and audited balance sheetsince CI is decreased by 36.02 Cr.

ConsentRecommended forperiod upto as perSectoral Approachpolicy

28.02.2024

FINAL REMARKS/DECISION as on 4th CAC Meeting of 2019-20 (Booklet No 6) dated12-06-2019

MPCB-CAC-00

0000

0058

MPCB-CAC-0000000058 (CAC Meeting Number : 8 dated August 6, 2019) Page 11 of 154

DECISION

We may consider the case for renewal of consent with decrease in CI for the period upto28.02.2024 by imposing following conditions;

1] Industry shall extend the existing BG of Rs. 10 lakh obtained towards O&M of pollutioncontrol system.

2] Industry shall abstract 170 CMD of ground water through four existing bore wells only. Noadditional ground water abstraction structures shall be constructed for this purpose as per NOCgranted by CGWA dated 01.05.2018.

Consent shall be issued after receipt of latest JVS results from SRO and audited balance sheetsince CI is decreased by 36.02 Cr.

InternalRemarks/Discussion:

The application for renewal of consent with decrease in CI was discussed in CAC dated12.06.2019. During the meeting, committee noted that in order to have clarity about the presentoperation, it was decided to call the PP for presentation before CAC. Accordingly, Industry wascalled for presentation to explain the present operational status of production and pollutioncontrol systems. Industry has made the Presentation, the details are as below;1. At present, industry is manufacturing 04 products, the details of year wise production is asbelow

Product/Year UOM 2016-17 2017-18 2018-19

CRT Nos. in lakhs/A 0.16 0.00 0.00

LCD/LED Nos. in lakhs/A 1.97 2.50 1.85

Plastic Injection Moulding MT/A 50.30 46.50 12.70

EPS Shaped Moulding MT/A 8.80 16.20 15.60

The overall production quantity is very less @15-20% against consented quantity. 1. The major source of effluent generation is paint shop. Since, industry has stopped theproduction of CRT, no spray painting activity undertaken since last one year, therefore, ETP isnon-functional.2. Industry carryout regularly analyze the STP treated water from MoEF approved lab and allare within the consented limit.3. The Hazardous waste disposed to Mumbai Waste Management site i.e. CHWTSDF.4. Industry requested to grant renewal of consent with Nil effluent since, effluent generatingactivity i.e. paint shop is stooped. After due deliberation, it was decided to recommend the case with following conditions;1. Industry shall extend the existing BG of Rs. 10 lakh obtained towards O&M of pollutioncontrol system.2. Industry shall abstract 170 CMD of ground water through four existing bore wells only. Noadditional ground water abstraction structures shall be constructed for this purpose as per NOCgranted by CGWA dated 01.05.2018.3. Industry shall not generate trade effluent.4. Industry shall obtain specific permission from the Board, if industry want to carry out anytrade effluent generating activity, and also amend the consent.

Outstandingdirections, if any:Decision on Grant ofConsent: NOT APPROVED

Consent granted upto:

Resubmission Remarks

MPCB-CAC-00

0000

0058

MPCB-CAC-0000000058 (CAC Meeting Number : 8 dated August 6, 2019) Page 12 of 154

ResubmissionRemarks

Personal hearing was extended to the PP on 09/07/2019 and Industry has made the Presentation,the details are as below;1) At present, industry is manufacturing 04 products, the details of year wise production is asbelow

Product/Year UOM 2016-17 2017-18 2018-19CRT Nos. in lakhs/A 0.16 0.00 0.00LCD/LED Nos. in lakhs/A 1.97 2.50 1.85Plastic Injection Moulding MT/A 50.30 46.50 12.70EPS Shaped Moulding MT/A 8.80 16.20 15.60

The overall production quantity is very less @15-20% against consented quantity.

2) The major source of effluent generation is paint shop. Since, industry has stopped theproduction of CRT, no spray painting activity undertaken since last one year, therefore, ETP isnon-functional.3) Industry carryout regularly analyze the STP treated water from MoEF approved lab and allare within the consented limit.4) The Hazardous waste disposed to Mumbai Waste Management site i.e. CHWTSDF.5) Industry requested to grant renewal of consent with Nil effluent since, effluent generatingactivity i.e. paint shop is stooped

III. We may consider the application by imposing following conditions

1) Industry shall extend the existing BG of Rs. 10 lakh obtained towards O&M of pollutioncontrol system.2) Industry shall abstract 170 CMD of ground water through four existing bore wells only. Noadditional ground water abstraction structures shall be constructed for this purpose as per NOCgranted by CGWA dated 01.05.2018.3) Industry shall not generate trade effluent.4) Industry shall obtain specific permission from the Board, if industry want to carry out anytrade effluent generating activity, and also amend the consent.

MPCB-CAC-00

0000

0058

MPCB-CAC-0000000058 (CAC Meeting Number : 8 dated August 6, 2019) Page 13 of 154

ITEM NO: 3 - Unique Number: MPCB-CONSENT-0000065263Fresh CAC ITEMRegion: SRO - Nagpur II Section: CAC Date: 01.08.2019UAN Number: MPCB-CONSENT-0000065263 TAG CACName & Address: M/s. Western Coal Fields Ltd. (Umrer Sub Area Manager, WCL, Umrer Area)Location ofIndustrial unit: Sirpur, Rev. Survey P.C. 21 & 22 Umrer Project, WCL Umred

Email: [email protected] Telephone number: 8275971323Industry Type: R35 Mining and ore beneficiationIndustry Category: REDProject Details: Existing project

Consent Applied For

1st Consent to operatefor expansion i.e. for

additional miningactivity from 3.5 to 4.9

MTPA

Application Date January19,2019

Date of receipt ofCAC/CC cell 07.02.2019.

Capital Investment in Rs. (Crs)Existing Proposed Total

Rs.186.85 Crs + Rs. 138.49 Crs Increase in CI 325.34Details of

project :Existingproject

Total Plot area(sq.m.)

9446500(sq.m)

ConstructionBUA (sq.m.)

3620000(sq.m)

Product and By-product detailsSr.no Product Name Quantity1 Coal 4.9 MT/ASr.no By-Product Name Quantity2 NA 0Applicabilty

ofCRZ

ClearenceDistance

from riverIndustrial

location policy Eco-sensitive Moratonium EC Direction of MoEF forwestern ghats

NO NO NO NO NO NO NO

If Yesprovidedetails

--NA-- - 0.00Km

Basedon:

Status:NotApplied

Details of CCA,Consents,Authorization and EC obtained Consent no. Consent

granted date ValidityCapital

Investmentin Crs

Total plotarea

ConstructionBUA

(FSI+Non-FSI)Remarks

C2O BO/CAC-Cell/CAC-UAnno.24423/CAC-1901000313 05.01.2019 31.03.2021 Rs.186.85

crs

EC J-11015/86/2005-IA-II(M) 11.01.2019

Coalminingactivity

from 3.50MTPA to4.90 in

ML area944.65 Ha

Existing production details

C to OSr.No Product Name Max quantity

1 Coal mining 3.5 MTPA

C to ESr.No Product Name Max quantity

1 NA NA

Bio-Medical Waste DetailsAnnual Rpt.(Form-II): NA

Accident Rpt.(Form-III):

BMWGeneration

Sr.No Category Max quantity (Kg/M)

1 NA NA

MPCB-CAC-00

0000

0058

MPCB-CAC-0000000058 (CAC Meeting Number : 8 dated August 6, 2019) Page 14 of 154

Disposal @CBMWTF: No

Member ofCBMWTF: NA

CaptiveDisposal: No

Incinerator Capacity Fuel Type Auto Feeding Temp.Recorder Online Monitoring

NA NA NA

Autoclave Type(Vertical/Horizontal)

Temp &Pressure

Recording

Shredder Plastic WasteDisposal

Compliance of Water Pollution Related Conditions Purpose Water Consumption

in CMD as appliedEffluent generationas applied in CMD

TreatmentSteps

DisposalDetails

Remarks/Adequeteland Available

1 Domestic Purposes 720 500 STPOn Land

forGardening

-

2Processing wherebywater gets polluted &pollutants are easilybiodegradable

300 100 Primary +Secondary Recycle

3Processing wherebywater gets polluted &pollutants are noteasily biodegradable

0 0 --NA-- --NA--

4IndustrialCooling,spraying inmine pits or boilerfeed

40 0 --NA-- --NA-- -

5Others such asgardening,agricultureetc

40 NA NA NA NA

Whether any deviation in water consumption observed compared toprevious consent NO Remarks:

Compliance to existing unit in case applied for expansion C to E/O/R NOSource of water supply

In case proposed discharge to CETP forfurther treatment

CETP Capacity to handle additional load NOName of CETP

Existing JVS results EffluentSr.no. Date of visit Board official's

name:Whether samplecollected or not:

Whether results areconfirming to standardsor not (Exceedingparameter with value)

1 26.09.2014 YES YES1 14.10.2014 YES YES1 07.05.2015 YES YES1 15.06.2015 YES YES1 15.06.2015 YES YES1 16.12.2016 YES YES1 26.12.2016 YES YES1 01.09.2017 NO NO

Details of fuel consumption and APC system as applied :-Sr. no Source Stack Fuel type Quantity Height-I,II,III APC system

detail1 NA NA NA 0 (Kg/hr.) NA m NAWhether any deviation in fuel consumptionand APC system observed compared toprevious consent

NO Remarks:

Compliance to existing unit in case appliedfor expansion C to E/O/R NO

Existing JVS results Air

MPCB-CAC-00

0000

0058

MPCB-CAC-0000000058 (CAC Meeting Number : 8 dated August 6, 2019) Page 15 of 154

Sr.no. Date of visit Board official'sname:

Whether samplecollected or not:

Whether results areconfirming to standardsor not (Exceedingparameter with value)

1 28.08.2014 YES NORSPM-466 against 250

2 29.08.2014 YES NORSPM-462 against 250

3 27.09.2014 YES YES4 26.09.2014 YES YES5 26.09.2014 YES YES6 31.12.2014 YES YES7 31.12.2014 YES YES8 31.12.2014 YES YES9 07.05.2015 YES YES10 07.05.2015 YES YES11 07.05.2015 YES YES12 15.06.2015 YES YES

Compliance of Haz. Waste ConditionDetails of hazardous waste as applied

Sr. no Type of waste Category Quantity & UOM Treatment Disposal

1 5.1 Used or spent oil 5.1 50 Lit/Day NA Sold to authorizedrecycler

234.1 Chemical-containing residuearising fromdecontamination.

34.1 120 Kg/Day NADisposed off byMEPL,Nagpur(CHWTSDFButiobori)

3 NA NA 0 --NA-- NA NAWhether any deviation in Hz waste generation and itsdisposal,observed compared to previous consent NO Remarks:

Compliance of existing unit in case applied for expansion C to E/O/R NO

Submission of Annual Return (Form IV) NO Submission Date

Compliance of Non Hazardous/ MSW conditionDetails of Non hazardous/MSW as applied

Sr. no Type of waste Quantity & UOM Treatment Disposal1 NA 0 --NA-- NA NAWhether any deviation in Non-Hz waste generation and itsdisposal,observed compared to previous consent NO Remarks:

Compliance of existing unit in case applied for expansion C to E/O/R NOWaterCess Returns filed upto: Paid Upto: Jan 1 1900

12:00:00:000AMDirectionissued (ifany)

BGDetails Amount Validity

BG obtained towards complience ofa) Consent/CCA condition b) directions

1 Rs.20 Lakhs 31.07.2021 Towards installation of STP withinsix months NA

2 Rs.5.0 Lakhs 31.07.2021Towards operation andmaintanance of pollution controlsystem so as to achieve consentedstandards

NA

Details of BGfortified/enchasedfor noncomplience,if any:

No

Submission ofEnvironmentalStatement

NO Year NA

Details of consentfee paid Amount Rs: 4282720 Terms 3

MPCB-CAC-00

0000

0058

MPCB-CAC-0000000058 (CAC Meeting Number : 8 dated August 6, 2019) Page 16 of 154

In case of 1st C to OComplience of C toE conditions

Remarks

Recommendation ofTAC

Recommendations

Anand N. Katole (SRO-Nagpur II):-Process and put up(Jan 21 2019 03:21:26:000PM)

Vinod Shukla (FO-Nagpur II):-Red/LSI CAC - Red/LSI CAC – Applied for renewal of consent to operate with expansion forexcavation of coal in red category. Earlier consent is valid upto 31/03/2021 for Coal-3.5 MillionTon/A as per EC dtd. 20/05/2005. Now applied for 3.5+1.4=4.9 Million Ton/A as per granted ECdtd. 11/01/2019. CI is increased by Rs. 138.49 Cr. Provided STP of capacity 0.3 MLD based onPhytorid technology for treatment of domestic effluent. Provided ETP of capacity 150 CMDwhich consist of collection tank, O & G trap, flash mixer, flocculator, sedimentation tank & SDB.Treated effluent from STP & ETP utilized for gardening & plantation inside the mine premises.Provided concrete sedimentation tank with capacity 600 m3 for treatment of mine waterdischarged. Provided 29 nos. of fixed type water sprinkler on coal transportation road & 7 nos.mobile water sprinkler for dust suppression on haul road. Provided 10 Nos. of fixed watersprinkler at coal transfer points of common CHP area along with mist spray arrangement with150 nozzles. Provided 34 Nos. of rain guns for dust suppression at railway siding of Umred area.Provided automatic tyre wash & full body washing system for outgoing loaded trucks at Umredarea check post. Uploaded photographs of installation of STP, ETP, sedimentation tank & APCsystem. Constructed concrete road for coal transportation. Planted around 3150 nos. of trees inmonsoon 2018 along wharf wall of railway siding. Applied for CGWA NOC on 13/06/2016 forpermission to dewater ground water. Deposited fees of Rs. 42,82,720/-. Deposited BG of Rs. 20Lakhs & Rs. 5 Lakhs as per earlier consent condition which are valid upto 16/03/2019 &31/07/2019. In view of above, consent to operate for 4.9 MTPA with over ridding effect of earliergranted consent dtd. 05/01/2019 may be granted.(Feb 6 2019 12:19:00:000PM)

Anand N. Katole (SRO-Nagpur II):-EC obtained for expansion from 3.5 MTPA TO 4.9 MTPA Coal mining.Existing consent for 3.5MTPA is valid for 31.3.2021.Air pollution control arrangement such as 29 nos. of fixed typewater sprinkler on coal transportation road & 7 nos. mobile water sprinkler for dust suppressionon haul road. Provided 10 Nos. of fixed water sprinkler at coal transfer points of common CHParea along with mist spray arrangement with 150 nozzles. Provided 34 Nos. of rain guns for dustsuppression at railway siding of Umred area. Provided automatic tyre wash & full body washingsystem for outgoing loaded trucks at Umred area check post.WCL has Provided STP of capacity0.3 MLD based on Phytorid technology for treatment of domestic effluent. Provided ETP ofcapacity 150 CMD which consist of collection tank, O & G trap, flash mixer, flocculator,sedimentation tank & SDB. Treated effluent from STP & ETP utilized for gardening & plantationinside the mine premises. Provided concrete sedimentation tank with capacity 600 m3 fortreatment of mine water discharged submitted 20.0 L and 5.0 L as per CC conditions. Appliedfor CGWB NOC Consent to operate for expansion by amending the existing consent may begranted.It seems that industry has submitted excess consent fees.(Feb 7 2019 12:19:25:000PM)

Mr.P.K.Mirashe(AST) (CAC-CELL-HQ):-Pl Process and put up(Feb 7 2019 12:26:21:000PM)

Other RelevantInformation

1] PP has applied for 1st consent to operate for expansion for the additional coal mining activity-1.4.i.e. from 3.5 MTPA to 4.9 MTPA in mining lease area 944.65 Ha.

2] PP has obtained consent to operate for Coal mining activity for mining 3.5 MTPA which isvalid up to 31.03.2021.

3] PP has obtained Environmental Clarence for additional mining activity from 3.5 MTPA to 4.90MTPA in mining lease area from 944.65 Ha. on 11.01.2019.

4] PP has provided STP of capacity 0.3 MLD based on Phytorid technology for treatment ofdomestic effluent and Provided ETP of capacity 150 CMD. JVS results are within consentedlimits

6] Air pollution control systems provided.i.e.Provided 29 nos of sprinklers of fixed types on coaltransportation road,7 nos mobile water sprinklers on haul road, 10 nos fixed water sprinklers atcoal transfer points etc.

7] Submitted status of CGWA NOC dated 11/07/2019 shows NOC approved, But they have notreceived final order of NOC from CGWA.

8] Submitted details of BGs as per the consent conditions.

9] PP has submitted separate application for consent to Establish vide UAN no.77525.

MPCB-CAC-00

0000

0058

MPCB-CAC-0000000058 (CAC Meeting Number : 8 dated August 6, 2019) Page 17 of 154

Recommendation ofCAC/CC Cell

We may grant 1st consent to operate for the period up to 31.03.2021 for expansion for theadditional coal mining activity -1.4.i.e. from 3.5 MTPA to 4.9 MTPA in mining lease area 944.65Ha by imposing condition of BGs

ConsentRecommended forperiod upto as perSectoral Approachpolicy

31.03.2021.

MPCB-CAC-00

0000

0058

MPCB-CAC-0000000058 (CAC Meeting Number : 8 dated August 6, 2019) Page 18 of 154

ITEM NO: 4 - Unique Number: MPCB-CONSENT-0000065541Fresh CAC ITEMRegion: SRO - Latur Section: CAC Date: 27.07.2019UAN Number: MPCB-CONSENT-0000065541 TAG CACName & Address: M/s. ADM Agro Industries Latur & Vizag Pvt. Ltd (G 75-86, MIDC, Latur)Location ofIndustrial unit: G75-86 Latur MIDC Latur

Email: [email protected] Telephone number: 7028014269Industry Type: O71 Vegetable oil manufacturing including solvent extraction and refinery /hydrogenated oilsIndustry Category: ORANGEProject Details: Existing project

Consent Applied For1st consent to operate

[ For 6 TPH Boiler]with amalgamation of

existing consentsApplication Date January

23,2019Date of receipt ofCAC/CC cell 19.03.2019

Capital Investment in Rs. (Crs)Existing Proposed Total

Rs.88.99 Crs + Rs. 1.23 Crs Increase in CI Rs. 90.22 CrsDetails of

project :Existingproject

Total Plot area(sq.m.) 138816 (sq.m) Construction

BUA (sq.m.)43116.56(sq.m)

Product and By-product detailsSr.no Product Name Quantity1 Operation of 6 TPH boiler 0 --NA--Sr.no By-Product Name Quantity2 NA 00Applicabilty

ofCRZ

ClearenceDistance

from riverIndustrial

location policy Eco-sensitive Moratonium EC Direction of MoEF forwestern ghats

NO YES NO NO NO NO NO

If Yesprovidedetails

Manjra - 5.00Km

Basedon:

Status:NotApplied

Details of CCA,Consents,Authorization and EC obtained Consent no. Consent

granted date ValidityCapital

Investmentin Crs

Total plotarea

ConstructionBUA

(FSI+Non-FSI)Remarks

C2E BO/CAC -cell/UANno.43712/R/CAC-1812000178 03.12.2018 30.04.2023 Rs.88.93

Crs

C2E BO/CAC- Cell/CAC-UANNo.22319/CAC-1810000469 10.10.2018 COU Rs.1.23 Crs

Existing production details

C to O

Sr.No Product Name Max quantity

1 Kardi Crude oil 277 MT/M

2 Refined Sunflower /Soya Oil 7500 MT/M

3 De-oiled cake 25,000 MT/M

4 Kardi Refined oil 126 MT/M

5 Cotton Seed Crude oil 333 MT/M

6 Refined cotton seed oil 330 MT/M

7 Ground Nut Crude oil 370 MT/M

8 Lecithin 300 MT/M

9 Acid oil 150 MT/M

10 Fatty Acid 6 MT/M

11 Filter Sunflower oil / Soya Oil/Crude oil 6000 MT/M

12 Ground nut refined oil 352 MT/M

13 Tin 15 Kg/ 15 Ltrs 6000 MT/D

C to ESr.No Product Name Max quantity

1 Installation of new boiler 6 TPH

Bio-Medical Waste Details

MPCB-CAC-00

0000

0058

MPCB-CAC-0000000058 (CAC Meeting Number : 8 dated August 6, 2019) Page 19 of 154

Annual Rpt.(Form-II): NA

Accident Rpt.(Form-III):

BMWGeneration

Sr.No Category Max quantity (Kg/M)

1 NA NA

Disposal @CBMWTF: No

Member ofCBMWTF: NA

CaptiveDisposal: No

Incinerator Capacity Fuel Type Auto Feeding Temp.Recorder Online Monitoring

NA

Autoclave Type(Vertical/Horizontal)

Temp &Pressure

Recording

Shredder Plastic WasteDisposal

Compliance of Water Pollution Related Conditions Purpose Water Consumption

in CMD as appliedEffluent generationas applied in CMD

TreatmentSteps

DisposalDetails

Remarks/Adequeteland Available

1 Domestic Purposes 5.6 22.4 STPOn Land

forGardening

As per existingconsent

2Processing wherebywater gets polluted &pollutants are easilybiodegradable

417.51 49.89 Primary +Secondary

On Landfor

GardeningAs per existing

consent

3Processing wherebywater gets polluted &pollutants are noteasily biodegradable

227.2 115.8 Primary +Secondary

On Landfor

GardeningAs per existing

consent

4IndustrialCooling,spraying inmine pits or boilerfeed

13 24 Primary +Secondary

On Landfor

GardeningAs per existing

consent

5Others such asgardening,agricultureetc

NA NA NA NA NA

Whether any deviation in water consumption observed compared toprevious consent NO Remarks:

Compliance to existing unit in case applied for expansion C to E/O/R NOSource of water supply

In case proposed discharge to CETP forfurther treatment

CETP Capacity to handle additional load NOName of CETP

Existing JVS results EffluentSr.no. Date of visit Board official's

name:Whether samplecollected or not:

Whether results areconfirming to standardsor not (Exceedingparameter with value)

1 26.11.2018 [ ETP outlet ] YES

NOBOD-110.2 against-100,COD-272- against250,SS-104against-100,sulphate-2023.8against-1000 and TDS-5464against 2100

1 26.12.2018 [ ETP outlet ] YES

NOBOD-110 against-100,COD-352- against250,SS-116 against-100 andTDS-2900 against 2100

1 26.11.2018 [ STP outlet] YES

NOBOD-109 against-100,SS-108against-100,

MPCB-CAC-00

0000

0058

MPCB-CAC-0000000058 (CAC Meeting Number : 8 dated August 6, 2019) Page 20 of 154

1 26.12.2018 [ STP outlet] YES

NOBOD-115 against-100,SS-106against-100,

Details of fuel consumption and APC system as applied :-Sr. no Source Stack Fuel type Quantity Height-I,II,III APC system

detail1 Boiler 1 Coal 1200 (Kg/hr.) 42 m Bag filterWhether any deviation in fuel consumptionand APC system observed compared toprevious consent

NO Remarks:

Compliance to existing unit in case appliedfor expansion C to E/O/R NO

Existing JVS results AirSr.no. Date of visit Board official's

name:Whether samplecollected or not:

Whether results areconfirming to standardsor not (Exceedingparameter with value)

1 NO NO

Compliance of Haz. Waste ConditionDetails of hazardous waste as applied

Sr. no Type of waste Category Quantity & UOM Treatment Disposal1 NA NA 0 --NA-- NA NA2 NA NA 0 --NA-- NA NAWhether any deviation in Hz waste generation and itsdisposal,observed compared to previous consent NO Remarks:

Compliance of existing unit in case applied for expansion C to E/O/R NO

Submission of Annual Return (Form IV) NO Submission Date

Compliance of Non Hazardous/ MSW conditionDetails of Non hazardous/MSW as applied

Sr. no Type of waste Quantity & UOM Treatment Disposal1 00 00 --NA-- 00 00Whether any deviation in Non-Hz waste generation and itsdisposal,observed compared to previous consent NO Remarks:

Compliance of existing unit in case applied for expansion C to E/O/R NOWaterCess Returns filed upto: Paid Upto: Jan 1 2019

12:00:00:000AMDirectionissued (ifany)

BGDetails Amount Validity

BG obtained towards complience ofa) Consent/CCA condition b) directions

1 Rs.5.0 Lakhs 31.08.2023 Towards compliances of consentconditions NA

2 Rs.5.0 Lakhs 31.08.2023To complete up gradation work ofETP within two months andcompliance of the same

NA

3 Rs.5.0 Lakhs 31.08.2023 Towards O & M of STP and toachieve consented standards NA

Details of BGfortified/enchasedfor noncomplience,if any:Submission ofEnvironmentalStatement

NO Year 22.09.2018

Details of consentfee paid Amount Rs: 45000 Terms 3

In case of 1st C to OComplience of C toE conditions

Remarks

Recommendation ofTAC

MPCB-CAC-00

0000

0058

MPCB-CAC-0000000058 (CAC Meeting Number : 8 dated August 6, 2019) Page 21 of 154

Recommendations

Shri. V.P.Shelke (SRO-Latur):-Visit, Process & put up.(Jan 30 2019 11:54:49:000AM)

Mr. R. G. Kshirsagar (FO-Latur):-Red/LSI. CAC preview Case. Existing consent is valid up to 30.04.2023 for exiting production(Capital investment is of Rs. 88.99 cr.). Meanwhile, industry has obtained consent to establishfor installation new boiler of capacity 6 TPH which was granted on 10.10.2018 (Capitalinvestment was of Rs. 1.23 cr.) Now, industry has applied for 1st consent to operate forinstallation new boiler of capacity 6 TPH. C.I. is of Rs. 1.23 cr. accordingly this office has issueda discrepancies letter on 02.02.2019 through Admin Dashboard regarding submission of detaildrawing & design of Air Pollution control system provided to boiler and treatment of boiler blowdawn and disposal thereof. But reply from industry yet not received. Board Official has visitedthe industry on 18.02.2019 and observed that, work of installation of new boiler of capacity 6TPH was found in progress. About 70 % work was found completed. Authority has proposed toprovide mechanical dust collection system followed by Bag filter which is to be connected withexiting stack of height 42 mtr. During visit structure of bag house & MDC were found completedbut bags yet to be provided. Work of provision of ducting from bag house to exiting stack yet tobe completed. It is reported that, installation of boiler will be completed by 31st march-2019.Industry has paid consent fees Rs. 45000.00. Hence. Decision for grant of 1st consent to operatewith amalgamation of exiting consent may be taken at higher level.

(Feb 21 2019 06:30:20:000PM)

Shri. V.P.Shelke (SRO-Latur):-Red/LSI. CAC preview Case. Existing consent is valid up to 30.04.2023 for exiting production(Capital investment is of Rs. 88.99 cr.). Meanwhile, industry has obtained consent to establishfor installation new boiler of capacity 6 TPH which was granted on 10.10.2018 with Capitalinvestment of Rs. 1.23 cr. Now, industry has applied for 1st consent to operate for installationnew boiler of capacity 6 TPH. with C.I. is of Rs. 1.23 cr. accordingly this office has issued adiscrepancies letter on 02.02.2019 through Admin Dashboard regarding submission of detaildrawing & design of Air Pollution control system provided to boiler and treatment of boiler blowdawn and disposal thereof. But reply from industry yet not received. Board Official has visitedthe industry on 18.03.2019 and observed that, work of installation of new boiler of capacity 6TPH was completed. Industry has provided mechanical dust collection system followed by Bagfilter to New Boiler, and duct is connected to exiting stack of height 42 mtr. New boiler not yetstarted. Industry is having existing ETP of capacity 200 CMD which consists of Oil skimmer,Collection tank, Neutralization tank, primary clarifier, Aeration tank, Secondary clarifier, Sandfilter & SDB. At the time of visit all units of ETP was found in operation. Out of 189.69 CMDTreated industrial effluent, 33.67 CMD treated ind effluent is used for spraying on Coal Ash andremaining 156.02 CMD treated ind. Effluent is used on land for gardening within premises andadjacent farmers land. ( Industry has uploaded copy of agreement between industry & Farmers).Analysis report of JVS collected from ETP out let on 26.11.2018 & 26.12.2018 are exceedingconsented limit. Industry is having existing STP of capacity 35 CMD which consists of Screening,oil trap, Collection tank, Aeration tank I & II, Settling tank, Carbon & Sand filter. At the time ofvisit all units of STP was found in operation. Treated Domestic Effluent is used on land forgardening within premises. Analysis report of JVS collected from STP out let on 26.11.2018 &26.12.2018 are exceeding consented limit. Industry has provided bag filter type dust collector toexisting 18 TPH boiler & Thermic fluid heater separately. Industry is a member of CHWTSDF,M/s MEPL, Ranjangaon, Pune and sending Haz. Waste to CHWTSDF, M/s MEPL, Ranjangaon,Pune. As per consent dtd 03.12.2018 Industry has submitted Bank guarantees of Rs. 10.0 Lakhstowards O & M of PCs which is valid up to 31.08.2023. Industry has submitted B.G. of Rs. 5.0Lakhs whcich is valid up to 31.08.2023 towards complete up gradation of ETP within twomonths, industry has installed new oil Skimmer in existing ETP and uploaded a letter regardingUp gradation plan of ETP. Industry has submitted B.G. of Rs. 5.0 Lakhs towards O & M of STPwhich is valid up to 31.08.2023. Industry has submitted B.G. of Rs. 5.0 Lakhs towardsCompliance of consent condition which is valid up to 31.08.2023. In view of above 1st consent tooperate with amalgamation of exiting consent may be granted

(Mar 19 2019 01:05:34:000PM)

Mr.P.K.Mirashe(AST) (CAC-CELL-HQ):-Pl Process and put up(Mar 19 2019 05:11:22:000PM)

MPCB-CAC-00

0000

0058

MPCB-CAC-0000000058 (CAC Meeting Number : 8 dated August 6, 2019) Page 22 of 154

Other RelevantInformation

1] PP has applied for 1st consent to operate for 6 TPH boiler with amalgamation of consents.

2] PP is having valid consent for existing products which is valid up to 30.04.2023 and consent toEstablish forinstallation of 6 TPH boiler.

3] PP has provided ETP of 200 CMD capacity for the treatment of trade effluent and STP ofcapacity -35 CMD for treatment of sewage. The analysis results of out let of ETP and STP areexceeded consented limits.

4] PP has submitted letter dated 19.03.2019 about plan of up gradation of ETP i.e. Installation ofweir type oil skimmer to collect oil from raw effluent, Use of NAlCO chemicals to control processparameters along with BOD, COD, reduction in sludge.

5] PP has provided dust collector system to existing boiler section and completed installationwork of new 6 TPH boiler.mechanical dust collection system followed by bag filters systemprovided as APCS.

6] PP has submitted BGs as per earlier consent conditions.

7] Board has issued SCN on 08.07.2019 under Plastic Waste Management Rules,2016. In thiscontext PP has submitted reply vide letter dated 18.07.2019 stating that they had submitted EPRon 09.05.2019 and submitted Plastic Waste Management Plant with the state UrbanDevelopment department and awaiting their response.

Recommendation ofCAC/CC Cell

We may consider to grant 1st consent to operate for 6 TPH boiler with amalgamation of existingconsent. i.e. up to 30.04.2023. and inform to RO to submit separate proposal within 6 months forforfeiture of BG towards non compliance of consent conditions.

ConsentRecommended forperiod upto as perSectoral Approachpolicy

30.04.2023.

MPCB-CAC-00

0000

0058

MPCB-CAC-0000000058 (CAC Meeting Number : 8 dated August 6, 2019) Page 23 of 154

ITEM NO: 5 - Unique Number: MPCB-CONSENT-0000065883Fresh CAC ITEMRegion: SRO - Chandrapur Section: CAC Date: 01.08.2019UAN Number: MPCB-CONSENT-0000065883 TAG CACName & Address: Pauni II Expansion OC (Pauni II Expansion OC, WCL Ballarpur Area)Location ofIndustrial unit: - Near Sakhari Village Rajura

Email: [email protected] Telephone number: 8275968286Industry Type: R35 Mining and ore beneficiationIndustry Category: REDProject Details: Expansion in existing project

Consent Applied For

Consent to Establishfor expansion of coalmining activity.i.e. for

additional miningactivity 2.65 MTPA

Application Date January28,2019

Date of receipt ofCAC/CC cell 18.03.2019

Capital Investment in Rs. (Crs)Existing Proposed Total

Rs.56.75 Crs Rs.499.0042 Crs Rs. 555.75 CrsDetails of

project :Expansion inexisting project

Total Plot area(sq.m.)

10955200(sq.m)

ConstructionBUA (sq.m.) 26000 (sq.m)

Product and By-product detailsSr.no Product Name Quantity1 Coal 2.65 MT/ASr.no By-Product Name Quantity2 NA 0Applicabilty

ofCRZ

ClearenceDistance

from riverIndustrial

location policy Eco-sensitive Moratonium EC Direction of MoEF forwestern ghats

NO YES NO NO NO YES NO

If Yesprovidedetails

Wardha River- 9.00 Km

Basedon:

Status:AppliedBut Notobtained

Details of CCA,Consents,Authorization and EC obtained Consent no. Consent

granted date ValidityCapital

Investmentin Crs

Total plotarea

ConstructionBUA

(FSI+Non-FSI)Remarks

C2O BO/JD(APC)/TB-2 UANNo.33454/R/CC-1902000483 12.02.2019 31.01.2022 Rs.56.75

Crs

For coalmining

-0.6 MTPAon MLarea

316.30 Ha

EC J-110157/71/2005-IA.II(M) 02.06.2006

For coalmining

-0.6 MTPAon MLarea

316.30 Ha

EC J-11015/80/2016-IA.II(M) 28.03.2019

For coalmining-0.6 to3.25

MTPA onML area1095.52

Ha

Existing production details

C to OSr.No Product Name Max quantity

1 Coal Mining on mining lease area of 316.30 Ha 0.6 MTPA

C to ESr.No Product Name Max quantity

1 NA NA

Bio-Medical Waste Details

MPCB-CAC-00

0000

0058

MPCB-CAC-0000000058 (CAC Meeting Number : 8 dated August 6, 2019) Page 24 of 154

Annual Rpt.(Form-II): NA

Accident Rpt.(Form-III):

BMWGeneration

Sr.No Category Max quantity (Kg/M)

1 NA NA

Disposal @CBMWTF: No

Member ofCBMWTF: NA

CaptiveDisposal: No

Incinerator Capacity Fuel Type Auto Feeding Temp.Recorder Online Monitoring

NA NA NA

Autoclave Type(Vertical/Horizontal)

Temp &Pressure

Recording

Shredder Plastic WasteDisposal

Compliance of Water Pollution Related Conditions Purpose Water Consumption

in CMD as appliedEffluent generationas applied in CMD

TreatmentSteps

DisposalDetails

Remarks/Adequeteland Available

1 Domestic Purposes 50 20SepticTank &Soak Pit

Others -

2Processing wherebywater gets polluted &pollutants are easilybiodegradable

0 0 --NA-- --NA-- -

3Processing wherebywater gets polluted &pollutants are noteasily biodegradable

0 0 --NA-- --NA-- -

4IndustrialCooling,spraying inmine pits or boilerfeed

300 0 --NA-- --NA-- -

5Others such asgardening,agricultureetc

NA NA NA NA

Whether any deviation in water consumption observed compared toprevious consent NO Remarks:

Compliance to existing unit in case applied for expansion C to E/O/R NOSource of water supply

In case proposed discharge to CETP forfurther treatment

CETP Capacity to handle additional load NOName of CETP

Existing JVS results EffluentSr.no. Date of visit Board official's

name:Whether samplecollected or not:

Whether results areconfirming to standardsor not (Exceedingparameter with value)

1 NO NO

Details of fuel consumption and APC system as applied :-Sr. no Source Stack Fuel type Quantity Height-I,II,III APC system

detail1 0 0 NA 0 (Kg/hr.) NA m NAWhether any deviation in fuel consumptionand APC system observed compared toprevious consent

NO Remarks:

Compliance to existing unit in case appliedfor expansion C to E/O/R NO

Existing JVS results Air

MPCB-CAC-00

0000

0058

MPCB-CAC-0000000058 (CAC Meeting Number : 8 dated August 6, 2019) Page 25 of 154

Sr.no. Date of visit Board official'sname:

Whether samplecollected or not:

Whether results areconfirming to standardsor not (Exceedingparameter with value)

1 NO NO

Compliance of Haz. Waste ConditionDetails of hazardous waste as applied

Sr. no Type of waste Category Quantity & UOM Treatment Disposal

1 2.2 Sludge containingoil 2.2 9 Ton/Y CHWTSDF, Butibori CHWTSDF, Butibori

2 3.3 Sludge and filterscontaminated with oil 3.3 4 Ton/Y CHWTSDF, Butibori CHWTSDF, Butibori

3 NA NA 0 --NA-- NA NAWhether any deviation in Hz waste generation and itsdisposal,observed compared to previous consent NO Remarks:

Compliance of existing unit in case applied for expansion C to E/O/R NO

Submission of Annual Return (Form IV) NO Submission Date

Compliance of Non Hazardous/ MSW conditionDetails of Non hazardous/MSW as applied

Sr. no Type of waste Quantity & UOM Treatment Disposal1 NA 0 --NA-- NA NAWhether any deviation in Non-Hz waste generation and itsdisposal,observed compared to previous consent NO Remarks:

Compliance of existing unit in case applied for expansion C to E/O/R NOWaterCess Returns filed upto: Paid Upto: Jan 1 1900

12:00:00:000AMDirectionissued (ifany)

BGDetails Amount Validity

BG obtained towards complience ofa) Consent/CCA condition b) directions

1 Rs.22 lakhs 31.05.2022 BGs under water pollution aspect NA2 Rs.95 Lakhs 31.05.2022 BGs under Air pollution aspect NA

3 Rs.5.0 Lakhs 31.05.2022 BG under for non hazardous (Solidwaste )Aspect NA

4 Rs.5.0 Lakhs 31.05.2022 BG under for Hazardous wasteAspect NA

5 Rs.25.0 Lakhs 31.05.2022 Towards O & M of PCs. NADetails of BGfortified/enchasedfor noncomplience,if any:

No

Submission ofEnvironmentalStatement

NO Year Yes, submitted on 30/09/2018

Details of consentfee paid Amount Rs: 2298008 Terms 1

In case of 1st C to OComplience of C toE conditions

Remarks

Recommendation ofTAC

MPCB-CAC-00

0000

0058

MPCB-CAC-0000000058 (CAC Meeting Number : 8 dated August 6, 2019) Page 26 of 154

Recommendations

Pratap D. Jagtap (SRO-Chandrapur):-Visit, process & put up within 20 days(Feb 2 2019 01:16:28:000PM)

Shri. U. B. Bahadule (FO-Chandrapur):-Mine was visited by Board official on date 26/02/2019 .The copy of visit report is uploaded.During visit it was found that : New pit will be developed for the expansion project, weighbridge, coal stock yard, ETP of service station and sedimentation tank will be common forexisting & expansion project, not constructed concrete roads at weigh bridge and fugitiveemissions of coal dust was observed in weigh bridge area, sewage treatment plant notconstructed for treatment of domestic effluent, coal transportation road from weigh bridge toPWD road is WBM road, not started excavation of new pit and not installed CAAQM station inthe premises of existing mine .Work of installation of CAAQMS is in tendering stage and will becommissioned in FY 2019-20.Pointwise compliance status of EC conditions of existing mine and pointwise compliance statusof consent conditions of existing mine is uploaded and shows partial compliance of conditions.Mine water is used for dust suppression, firefighting and for domestic purpose and applicant hasapplied to Director CGWB Nagpur for permission to dewater ground water for Pauni-II OCM.Analysis reports of JVS of mine discharge are uploaded and it is found that parameters arewithin consented limits. Water consumption returns of all mines of Ballarpur Area have beensubmitted upto November 2017. • Water cess has been paid as per demand of MPCB upto31/08/2015.Applicant has uploaded the details of calculations of consent fees. Applicant uploaded Rs. 100/-stamp paper showing investment of total project as Rs 499.0042 crores but the same is notabout expansion part & also not ins per prescribed format.. Project capital investment beforeexpansion is Rs.56.75 Crores. Therefore for increased investment i.e. for 499.0042- 56.75 = Rs442.254 crores, the required fees is Rs 8.8508 lakhs. Adding charges on enhanced productionquantity i.e. Rs 0.4 X 2650000=1060000/. Total fees required is Rs 19.108 lakhs. Fees paid withthis application is Rs. 2298008/. Applicant has uploaded mandatory documents such as authorityletter, PAN of WCL, PAN of applicant, list of directors and certificate of registration.Submitted for further necessary action please.NOTE: Complete remarks are uploaded in MPCB documents due limits of characters in this box.(Mar 1 2019 04:39:04:000PM)

Pratap D. Jagtap (SRO-Chandrapur):-Industry has applied for consent to establish for increase in production with increase ininvestment. Earlier consent which is granted on 12.02.2019 is valid up to 31.01.2022 forproduction capacity of 0.6 Million Ton per Annum with mining lease area of 316.30 Ha withinvestment Rs. 56.75 Cr. Now applied for consent to establish for production quantity 2.65Million Ton per Annam with mining lease area of 1095.52 Ha with investment Rs. 442.2542.Industry has paid consent to establish fee with mining charges. For the proposed projectrequired water consumption for domestic is 11 cmd & effluent generation is 8.5 cmd. For thetreatment of the same septic tank along with soak pit provided. For the mine water alreadysedimentation tank of more than 1000 kld capacity provided. For work shop effluent ETP of 150KLD is already provided. Treated water will be reused. However till workshop activity notcommissioned. Propose to provide CHP. For the air pollution control system of existing plant &proposed plant 2 no. of water tanker of capacity 20 KL capacity, 10 no of rain guns around coalstock yard & 8 nos. at weighbridge provided. HW will be disposed through CHWTSDF. As perexisting consent conditions dated 12.02.2019 industry has not submitted BG as per BG regime.Only BG of Rs. 10.0 lacks submitted, installation of CAAQMS is in tendering process will beinstalled within three months, will convert existing water sprinkle arrangement into chemicalfogging arrangement, no proposal for real time coal ash analyser, black top road not provide andregarding same proposal is submitted to HQ for approval. At present coal mine activity hasstooped as the target of financial year achieved. In view of above we may call industryrepresentative for personnel hearing at HQ level for the compliance of consent conditions &after that consent to establish for increase in production may be issued.(Mar 16 2019 04:23:55:000PM)

Mr.P.K.Mirashe(AST) (CAC-CELL-HQ):-Pl Process and put up(Mar 18 2019 10:10:59:000AM)MPCB-C

AC-0000

0000

58

MPCB-CAC-0000000058 (CAC Meeting Number : 8 dated August 6, 2019) Page 27 of 154

Other RelevantInformation

1] PP has applied for consent to Establish for expansion for the additional coal mining activity-2.65 MTPA. i.e. from 0.6 MTPA to 3.25 MTPA in mining lease area 1095.52 Ha.

2] PP has obtained consent to operate for Coal mining activity- 0.6 MTPA for mining lease area316.30 Ha which is valid up to 31.01.2022.

3] PP has obtained Environmental Clarence for additional mining activity 0.6 MTPA mining leasearea 316.30 Ha on 02.02.2006.PP has submitted minutes of meeting of the Expert AppraisalCommittee (EAC) dated 24.01.2019.In this meeting recommended re-validation of EC from 0.6 to3.25 MTPA in ML area 1095.52.

4] Additional domestic sewage will be treated in Septic tank followed by soak pit.

5] Sedimentation tank of more than 1000 kld capacity provided for treatment of mine water andETP of capacity 150 CMD provided for trade effluent. Treated water will be reused. However tillworkshop activity not commissioned.

6] PP has provided 2 no. of water tanker of capacity 20 KL capacity, 10 no of rain guns aroundcoal stock yard & 8 nos. at weighbridge provided to control air pollution.

8] PP had submitted BG of 10.0 Lakhs and not submitted other BGs as per the consentconditions.

9] As per earlier consent condition of CGWA, PP has not submitted copy of NOC of CGWA in theBoard.

10] SRO has reported that this mine is not in operation from last one year.

Recommendation ofCAC/CC Cell

We may grant consent to Establish for expansion for coal mining activity from from 0.6 MTPA to3.25 MTPA in mining lease area 1095.52 Ha. by imposing condition of EC and CGWA and wemay callto PP for for the technical presentation along with the action plans about installation of PCS.

ConsentRecommended forperiod upto as perSectoral Approachpolicy

Commissioning of the unit or 5 years period.

MPCB-CAC-00

0000

0058

MPCB-CAC-0000000058 (CAC Meeting Number : 8 dated August 6, 2019) Page 28 of 154

ITEM NO: 6 - Unique Number: MPCB-CONSENT-0000066214Fresh CAC ITEMRegion: SRO - Amravati I Section: CAC Date: 03.08.2019UAN Number: MPCB-CONSENT-0000066214 TAG CACName & Address: VHM INDUSTRIES LTD (T 2 ,MIDC NANDGAON PETH ,( TEXTILE PARK),AMRAVATI)Location ofIndustrial unit: T-2 T-2 Additional MIDC Area,Nandgaon Peth Amravati

Email: [email protected] Telephone number: 9867517885

Industry Type: R40 Yarn / Textile processing involving any effluent/emission generating processes includingbleaching, dyeing, printing and colouring

Industry Category: REDProject Details: Expansion in existing project

Consent Applied ForConsent to Establishfor expansion i.e. foradditional production

with increase in CIApplication Date February

1,2019Date of receipt ofCAC/CC cell 13.05.2019

Capital Investment in Rs. (Crs)Existing Proposed Total

Rs.190.25 Crs Rs.80.87 Crs Rs. 271.12 CrsDetails of

project :Expansion inexisting project

Total Plot area(sq.m.) 55200 (sq.m) Construction

BUA (sq.m.) 14746 (sq.m)Product and By-product details

Sr.no Product Name Quantity1 Dyed Yarn 0 MT/M

2 Processed Fabric (Processing ,Dyeing &Printing 485 MT/M

Sr.no By-Product Name Quantity3 NA 0Applicabilty

ofCRZ

ClearenceDistance

from riverIndustrial

location policy Eco-sensitive Moratonium EC Direction of MoEF forwestern ghats

NO YES NO NO NO NO NO

If Yesprovidedetails

Pedhi River -10.00 Km

Basedon:

Status:NotApplied

Details of CCA,Consents,Authorization and EC obtained Consent no. Consent

granted date ValidityCapital

Investmentin Crs

Total plotarea

ConstructionBUA

(FSI+Non-FSI)Remarks

C2O BO/CAC-Cell/CAC-UANno.40584/1811001444 30.11.2018 31.01.2021 Rs.190.25

Crs

Existing production details

C to O

Sr.No Product Name Max quantity

1 Dyed Yarn 240 T/Month

2 Woven Fabrics 84 MT/M

3 Processed Fabrics ( Processing and Dying) 315 MT/M

C to ESr.No Product Name Max quantity

1 NA NA

Bio-Medical Waste DetailsAnnual Rpt.(Form-II): NA

Accident Rpt.(Form-III): NA

BMWGeneration

Sr.No Category Max quantity (Kg/M)

1 NA NA

Disposal @CBMWTF: No

MPCB-CAC-00

0000

0058

MPCB-CAC-0000000058 (CAC Meeting Number : 8 dated August 6, 2019) Page 29 of 154

Member ofCBMWTF: NA

CaptiveDisposal: No

Incinerator Capacity Fuel Type Auto Feeding Temp.Recorder Online Monitoring

NA NA NA

Autoclave Type(Vertical/Horizontal) NA

Temp &Pressure

Recording

Shredder Plastic WasteDisposal

Compliance of Water Pollution Related Conditions Purpose Water Consumption

in CMD as appliedEffluent generationas applied in CMD

TreatmentSteps

DisposalDetails

Remarks/Adequeteland Available

1 Domestic Purposes 30 20 STPOn Land

forGardening

Used for gardening

2Processing wherebywater gets polluted &pollutants are easilybiodegradable

0 0 Primary +Secondary CETP

Within previousconsent limit 1100

KLD

3Processing wherebywater gets polluted &pollutants are noteasily biodegradable

0 0 Primary CETP Within previousconsent limit

4IndustrialCooling,spraying inmine pits or boilerfeed

0 0 Primary CETPWithin previous

consent limit 272KLD

5Others such asgardening,agricultureetc

0 NA NA NA NA

Whether any deviation in water consumption observed compared toprevious consent NO Remarks:

Compliance to existing unit in case applied for expansion C to E/O/R NOSource of water supply

In case proposed discharge to CETP forfurther treatment

CETP Capacity to handle additional load YESName of CETP --NA--

Existing JVS results EffluentSr.no. Date of visit Board official's

name:Whether samplecollected or not:

Whether results areconfirming to standardsor not (Exceedingparameter with value)

1 20.04.2018 YESNOCOD-460 against-250,BOD-131 against-100

1 15.05.2018 YESNOCOD-280 against-250,BOD-110 against-100

1 07.06.2018 YES YES1 31.07.2018 YES YES1 27.08.2018 YES YES1 16.10.2018 YES YES1 19.12.2018 YES YES1 27.12.2019 YES YES

Details of fuel consumption and APC system as applied :-Sr. no Source Stack Fuel type Quantity Height-I,II,III APC system

detail

1 Boiler 1 (Existing) Coal 1800 (Kg/hr.) 40 mDust collector &Bag Filter(Existing )

Whether any deviation in fuel consumptionand APC system observed compared toprevious consent

NO Remarks:

Compliance to existing unit in case appliedfor expansion C to E/O/R NO

MPCB-CAC-00

0000

0058

MPCB-CAC-0000000058 (CAC Meeting Number : 8 dated August 6, 2019) Page 30 of 154

Existing JVS results AirSr.no. Date of visit Board official's

name:Whether samplecollected or not:

Whether results areconfirming to standardsor not (Exceedingparameter with value)

1 NO NO

Compliance of Haz. Waste ConditionDetails of hazardous waste as applied

Sr. no Type of waste Category Quantity & UOM Treatment Disposal

1 5.1 Used or spent oil 5.1 420 Ltr/A NA Sale to authorized reprocessor

2 NA NA 0 --NA-- NA NAWhether any deviation in Hz waste generation and itsdisposal,observed compared to previous consent NO Remarks:

Compliance of existing unit in case applied for expansion C to E/O/R NO

Submission of Annual Return (Form IV) NO Submission Date

Compliance of Non Hazardous/ MSW conditionDetails of Non hazardous/MSW as applied

Sr. no Type of waste Quantity & UOM Treatment Disposal1 Spent Oil 50 Ltr/M NA Sale to reprocessor2 Sized & Unsized Yarn 5 MT/M NA Sale to reprocessor3 Degraded Yarn 5 MT/M NA Sale to reprocessor4 Degraded Cloth 5 MT/M NA Sale to reprocessor5 Empty Plastic Drum 1000 No/M NA Sale to reprocessorWhether any deviation in Non-Hz waste generation and itsdisposal,observed compared to previous consent NO Remarks:

Compliance of existing unit in case applied for expansion C to E/O/R NOWaterCess Returns filed upto: Paid Upto: Jan 1 1900

12:00:00:000AMDirectionissued (ifany)

BGDetails Amount Validity

BG obtained towards complience ofa) Consent/CCA condition b) directions

1 Rs.1.0 Lakhs 31.05.2021Storage (proper( Cover , leachatecollection system, connection toETP not exceeding 90 Days)

NA

2 Rs.1.0 Lakhs 31.05.2021Mode of disposal(CHWTSDF,Recycle, Incinerationetc)

NA

3 Rs.25000/- 31.05.2021 Maintaining records NA

4 Rs.20.0 Lakhs 31.05.2021Towards the operation andMaintenance of ETP to achievedisposal standards

NA

5 Rs.5.0 Lakhs 31.05.2021Towards the operation andMaintenance of air pollutioncontrol devices to achieve emissionstandards

NA

6 Rs.10,000/- 31.05.2021 Provide ash collection and disposalarrangements NA

7 Rs.2.0 Lakhs 31.05.2021Industry shall provide on line flowmeter at ETP inlet and outlet linewith electronic data logger.

NA

Details of BGfortified/enchasedfor noncomplience,if any:

No

Submission ofEnvironmentalStatement

NO Year 14/11/2018

Details of consentfee paid Amount Rs: 125000 Terms 1

MPCB-CAC-00

0000

0058

MPCB-CAC-0000000058 (CAC Meeting Number : 8 dated August 6, 2019) Page 31 of 154

In case of 1st C to OComplience of C toE conditions

Remarks

Recommendation ofTAC

Recommendations

Shri. S. D. Patil (SRO-Amravati I):-Process and put up.(Feb 4 2019 10:30:50:000AM)

Shri. S. V. Lingade (FO-Amravati I):-1. Existing Yarn Dying, Cotton grey fabric weaving & sizing & Cotton fabric processing anddying unit applied for Consent to Establish (Expansion), as per CPCB categorization unit comesunder Red category sr. no. 40 (Yarn / Textile processing involving any effluent/emissiongenerating processes including bleaching, dyeing, printing and colouring)2. Capital investment for the expansion activity will be 80.87 Crs. Accordingly industry hassubmitted the fees of Rs. 1,25,000/- towards the grant of consent to establish (Expansion)3. Industry has utilizes existing ETP of capacity 1200 CMD comprises of Secondary treatment forthe treatment of effluent generation, but industry has submitted their explanation regarding noincrease in water consumption and effluent generation as they have adopt good operatingpractices to reduce water consumption and effluent generation in existing setup as compare toExisting consented value, details regarding the same are enclosed i.e. Production Details, Waterconsumption from MIDC & CETP.4. Industry propose to install additional stand by boiler of capacity 4 TPH using coal as fuelalong with existing air pollution control arrangement i.e. Bag Filter and cyclone along commonstack of height 40 mtr.5. Industry utilizes existing Thermic fluid heater of capacity 20 lakh Kcal/Hr using diesel as fuel.6. Industry has obtain the membership of CHWTSDF for the disposal of HW & Used oil isdisposed of through sale to authorized re-processor.7. Industry has submitted the review letter against non-forfeiture of Bank Guarantee of Rs. 10.0lakh as per existing consent condition.8. Analysis results of treated effluent & source emission is enclosed separately.In view of above recommend the case for further action, if approved.(Mar 13 2019 07:05:02:000PM)

Shri. S. D. Patil (SRO-Amravati I):-1. Industry has applied for Consent to Establish (Expansion).As per CPCB categorization unitcomes under Red category sr. no. 40 (Yarn / Textile processing involving any effluent/emissiongenerating processes including bleaching, dyeing, printing and coloring).2. Capital investment for the expansion activity will be 80.87 Crs. Accordingly industry hassubmitted the fees of Rs. 1,25,000/- towards the grant of consent to establish (Expansion).3. Industry has utilizes existing ETP of capacity 1200 CMD comprises of Primary & Secondarytreatment for the treatment of effluent generation, but industry has submitted their explanationregarding no increase in water consumption and effluent generation as they have adopt goodoperating practices to reduce water consumption and effluent generation in existing setup ascompare to Existing consented value, details regarding the same are enclosed i.e. ProductionDetails, Water consumption from MIDC & CETP.4. Industry propose to install additional stand by boiler of capacity 4 TPH using coal as fuelalong with existing air pollution control arrangement i.e. Bag Filter and cyclone along commonstack of height 40 mtr.5. Industry utilizes existing Thermic fluid heater of capacity 20 lakh Kcal/Hr using coal as fuel.6. Industry has obtain the membership of CHWTSDF for the disposal of HW & Used oil isdisposed of through sale to authorized re-processor.7. Industry has submitted the review letter against non-forfeiture of Bank Guarantee of Rs. 10.0lakh as per existing consent condition.8. Analysis results of treated effluent & source emission are enclosed separately. In view ofabove consent to establish may be granted. if approved.(May 10 2019 12:10:44:000PM)

Mr.P.K.Mirashe(AST) (CAC-CELL-HQ):-Pl Process and put up(May 13 2019 12:27:59:000PM)MPCB-C

AC-0000

0000

58

MPCB-CAC-0000000058 (CAC Meeting Number : 8 dated August 6, 2019) Page 32 of 154

Other RelevantInformation

1] PP has applied for consent to Establish for expansion.i.e. for additional production qty andwith increase in CI.

2] PP has obtained consent for the existing products which is valid up to 30.01.2021.

3] PP has provided ETP of 1250 capacity and STP of 20 CMD capacity for the treatment ofdomestic effluent.Treated effluentis disposed in CETP for further treatment.Analysis results shows fluctuation in COD and BODparameter

4] PP has informed vide letter dated 12.02.2019 that there will not be increase in the waterconsumption and effluent generation due to additional production.

5] PP has proposed to install dust collector and bag filter system to new boiler of 4 TPH capacity.[stand by].

6] PP has obtained membership of CHWTSDF.

7]PP has submitted the review letter against non-forfeiture of Bank Guarantee of Rs. 10.0 lakhas per existing consent condition.

Recommendation ofCAC/CC Cell

We may grant consent to Establish for expansion.i.e. for additional production qty by imposingcondition of BG towards compliances of consent conditions and call to PP for technicalpresentation about pollution control system provided by them with action plan to reducepollution.

ConsentRecommended forperiod upto as perSectoral Approachpolicy

Up to commissioning of the unit or 5 years period which ever is earlier.

MPCB-CAC-00

0000

0058

MPCB-CAC-0000000058 (CAC Meeting Number : 8 dated August 6, 2019) Page 33 of 154

ITEM NO: 7 - Unique Number: MPCB-CONSENT-0000066265Fresh CAC ITEMRegion: SRO - Chandrapur Section: CAC Date: 01.08.2019UAN Number: MPCB-CONSENT-0000066265 TAG CACName & Address: Gouri I&II (A) Opencast (Gouri I&II OC mine, WCL Ballarpur Area)Location ofIndustrial unit: - Near Gouri village Rajura

Email: [email protected] Telephone number: 8275968401Industry Type: R35 Mining and ore beneficiationIndustry Category: REDProject Details: Existing project

Consent Applied ForRenewal of consent tooperate for decrease

in mining qty and withincrease in CI

Application Date February1,2019

Date of receipt ofCAC/CC cell 19.03.2019

Capital Investment in Rs. (Crs)Existing Proposed Total

Rs.103.975 Crs - Rs. 29.077 Crs decrease in CI 133.052Details of

project :Existingproject

Total Plot area(sq.m.)

6765300(sq.m)

ConstructionBUA (sq.m.) - (sq.m)

Product and By-product detailsSr.no Product Name Quantity1 Coal 1.2 MT/A2 Coal 0 MT/ASr.no By-Product Name Quantity3 - 0Applicabilty

ofCRZ

ClearenceDistance

from riverIndustrial

location policy Eco-sensitive Moratonium EC Direction of MoEF forwestern ghats

NO YES NO NO NO YES NO

If Yesprovidedetails

Wardha River- 6.50 Km

Based on:

Status:Obtained (EC Ref. No. -J-11015/242/2008-IA.II(M))

Details of CCA,Consents,Authorization and EC obtained Consent no. Consent

granted date ValidityCapital

Investmentin Crs

Total plotarea

ConstructionBUA

(FSI+Non-FSI)Remarks

C2O BO/CAC-Cell/EICno.CH-1736-15/CAC-14131 05.11.2015 31.03.2019 RS.103.975

Crs

EC J-11015/242/2008-IA.II(M) 17.07.2009

For coalmining

1.50MTPA to

2.50MTPA inML area

676.53 Ha

Existing production details

C to OSr.No Product Name Max quantity

1 Coal mining 2.5 MTPA

C to ESr.No Product Name Max quantity

1 NA NA

Bio-Medical Waste DetailsAnnual Rpt.(Form-II): NA

Accident Rpt.(Form-III): NA

BMWGeneration

Sr.No Category Max quantity (Kg/M)

1 NA NA

MPCB-CAC-00

0000

0058

MPCB-CAC-0000000058 (CAC Meeting Number : 8 dated August 6, 2019) Page 34 of 154

Disposal @CBMWTF: No

Member ofCBMWTF: NA

CaptiveDisposal: No

Incinerator Capacity Fuel Type Auto Feeding Temp.Recorder Online Monitoring

NA NA NA

Autoclave Type(Vertical/Horizontal)

Temp &Pressure

Recording

Shredder Plastic WasteDisposal

Compliance of Water Pollution Related Conditions Purpose Water Consumption

in CMD as appliedEffluent generationas applied in CMD

TreatmentSteps

DisposalDetails

Remarks/Adequeteland Available

1 Domestic Purposes 8 3 SepticTank Others -

2Processing wherebywater gets polluted &pollutants are easilybiodegradable

0 0 --NA-- --NA-- -

3Processing wherebywater gets polluted &pollutants are noteasily biodegradable

0 0 --NA-- --NA-- -

4IndustrialCooling,spraying inmine pits or boilerfeed

674 0 --NA-- --NA-- -

5Others such asgardening,agricultureetc

- NA NA NA NA

Whether any deviation in water consumption observed compared toprevious consent NO Remarks:

Compliance to existing unit in case applied for expansion C to E/O/R NOSource of water supply

In case proposed discharge to CETP forfurther treatment

CETP Capacity to handle additional load NOName of CETP

Existing JVS results EffluentSr.no. Date of visit Board official's

name:Whether samplecollected or not:

Whether results areconfirming to standardsor not (Exceedingparameter with value)

1 06.02.2016 YES

NOBOD-110 agaisnt100,COD-370against-250,SS-180against-100

1 06.03.2018 YES YES1 06.03.2018 YES YES1 31.08.2017 YES YES1 31.08.2017 YES YES

1 06.03.2018 YES NOTDS-2294 against-2100

1 06.03.2018 YES YES

1 06.03.2018 YES NOTDS-2192 against-2100

Details of fuel consumption and APC system as applied :-Sr. no Source Stack Fuel type Quantity Height-I,II,III APC system

detail1 - 0 - 0 (Kg/hr.) 0 m -Whether any deviation in fuel consumptionand APC system observed compared toprevious consent

NO Remarks:

MPCB-CAC-00

0000

0058

MPCB-CAC-0000000058 (CAC Meeting Number : 8 dated August 6, 2019) Page 35 of 154

Compliance to existing unit in case appliedfor expansion C to E/O/R NO

Existing JVS results AirSr.no. Date of visit Board official's

name:Whether samplecollected or not:

Whether results areconfirming to standardsor not (Exceedingparameter with value)

1 Not enclosed NO NO

Compliance of Haz. Waste ConditionDetails of hazardous waste as applied

Sr. no Type of waste Category Quantity & UOM Treatment Disposal

1 2.2 Sludge containingoil 2.2 3 Ton/Y At CHWTSDF

ButiboriAt CHWTSDFButibori

2 3.3 Sludge and filterscontaminated with oil 3.3 18 Ton/Y At CHWTSDF

ButiboriAt CHWTSDFButibori

3 NA NA 0 --NA-- NA NAWhether any deviation in Hz waste generation and itsdisposal,observed compared to previous consent NO Remarks:

Compliance of existing unit in case applied for expansion C to E/O/R NO

Submission of Annual Return (Form IV) NO Submission Date

Compliance of Non Hazardous/ MSW conditionDetails of Non hazardous/MSW as applied

Sr. no Type of waste Quantity & UOM Treatment Disposal1 - 0 --NA-- - -Whether any deviation in Non-Hz waste generation and itsdisposal,observed compared to previous consent NO Remarks:

Compliance of existing unit in case applied for expansion C to E/O/R NOWaterCess Returns filed upto: Paid Upto: Aug 31 2015

12:00:00:000AMDirectionissued (ifany)

BGDetails Amount Validity

BG obtained towards complience ofa) Consent/CCA condition b) directions

1 Rs.8.0 Lakhs 31.07.2019 Towards O & M of Pollutioncontrol systems NA

2 Rs.5.0 Lakhs 31.07.2019 Installation of STP NADetails of BGfortified/enchasedfor noncomplience,if any:

NO

Submission ofEnvironmentalStatement

NO Year Yes, Submitted on 20/09/2018

Details of consentfee paid Amount Rs: 1492210 Terms 2

In case of 1st C to OComplience of C toE conditions

Remarks

Recommendation ofTAC

MPCB-CAC-00

0000

0058

MPCB-CAC-0000000058 (CAC Meeting Number : 8 dated August 6, 2019) Page 36 of 154

Recommendations

Pratap D. Jagtap (SRO-Chandrapur):-Visit, process & put up within 20 days(Feb 11 2019 02:08:06:000PM)

Shri. U. B. Bahadule (FO-Chandrapur):-In this application there is decrease in production quantity and no change in mine lease area(676.56 hectares). There is increase in capital investment by Rs. 29.077 crores .Mine was visitedon date 08/03/2019 .The copy of visit report is uploaded. During visit following non-complianceswere found : thick layer of coal dust found on surface of roads meant for coal transportation bytrucks, conveyor belt near other coal crusher not covered ,coal dust found on ground surface incoal crusher area, coal is stocked in large quantity on open land , 10 numbers of rain guns areinstalled in coal stock tard but it is inadequate & more numbers are required, layer of coal dustfound in CHP area, a natural pond is used as sedimentation tank & there is no provision of puccasedimentation tank,workshop ETP does not have oil skimmer for oil removal,CAAQms notinstalled and the mine has not sent ETP sludge to CHWTSDF Butibori, Nagpur since year 2018which is stored in SDB of ETP and fixed type sprinklers not installed along road sides.Pointwise compliance status of EC conditions and pointwise compliance status of consentconditions are uploaded in MPCB documents and partial compliance is found .Also WCL is notcomplying the points mentioned in the Show cause letter issued to it dated 19/3/2017 and dated07/11/2017 ( copy of their reply is uploaded by the applicant). Applicant has uploaded PAN ofWCL, list of directors, certificate of incorporation and PAN of applicant.Applicant has uploaded the letter to CGWB for permission to withdraw ground water , dated13/6/2016.Water cess returns submitted up to November 2017 and cess paid up to 31/8/2015. The analysisresults of JVS are uploaded and it is found that few times the results are exceeding the limits (parameters such as BOD,COD and TDS of mine water).Applicant has paid fees for increasedinvestment+ fees based on investment( two years)+fees based on production quantity(twoyears)with this application. Total fees paid is = Rs 1492210+Rs408050=Rs=Rs 1900260/.Applicant has paid renewal fees for two years i.e from 31/3/2019 up to 31/3/2021 and Rs 333052remains balance with MPCB. Applicant has applied to CGWB Nagpur for NOC to extract groundwater.Submitted for further necessary action please.* Note:- Kindly refer MPCB documents for complete remarks due to character limits in this box.(Mar 11 2019 06:24:20:000PM)

Pratap D. Jagtap (SRO-Chandrapur):-Applied for renewal with reduction in production quantity and increase in capital investment.Investment increased by Rs. 29.077 cr. Domestic water consumption & effluent reduced. For thetreatment of same septic tank & soak pit provided. As per earlier consent domestic waterconsumption is 180 cmd and effluent generation quantity is 140 cmd. In present applicationdomestic water consumption is 35 cmd & effluent generation is 28 cmd. For the samejustification submitted by industry is as in earlier consent mentioned quantities are consideringwater consumption of Gouri Colony. However same colony is not in the mine lease area and 4KM away from Mine on another Survey no. Hence not considered colony water consumption &effluent in this consent application. As per consent conditions industry has to provide STP within3 months. However STP for colony area is till not provided. As informed by industry at presentwork of up gradation of sewerage system is in progress and STP of capacity 1MLD is proposedto be installed in 2019-20. For mine water treatment kaccha sedimentation tank of 360 cmdcapacity provide. Mine water after treatment is used for dust suppression & fire fightingpurpose. Primary ETP for work shop effluent of 75 KL capacity provided. Treated water isreused. Propose to provide oil skimmer. However for the same Board has issued SCN in 2017.Copy enclosed. HW generation is ETP sludge & Waste oil. Disposal of HW is not regular. Lastdisposal is two year back. There are one CHP in which there are two crusher. Also there is onemobile crusher. Dust collector are not provided to CHP. Water sprinkle arrangement providedfor dust suppression. For mobile crusher conveyor belt GI sheet covering not provided. Black toproad in mine area provided. For dust suppression two mobile water tanker, 12 rain gunsprovided. Planted 4.89 Lac nos of tree. Out of Rs. 10.00 Lakh BG of only Rs. 5.00 lakh for O & Mof pollution control system provided. Consent fee with mine charges for two years paid. Forincrease in investment c to e fee @ 75000/- required. However there is balance of Rs. 408050/-with Board as per earlier consent. We may adjust same from this balance. In view of above asindustry is not disposing HW regular to CHWTSDF, not submitted BG as per consent conditions,existing BG of Rs. 5.00 lac may be for fitted & consent may be granted for a period 31.03.2021with appropriate BG. Also appropriate decision may be taken at CAC level regardingconsideration of domestic water consumption & effluent quantity of colony in existing consent ornot as said colony is not in the mine lease area and 4 KM away from Mine on another Survey no.(Mar 19 2019 03:56:56:000PM)

Mr.P.K.Mirashe(AST) (CAC-CELL-HQ):-Pl Process and put up(Mar 19 2019 05:14:02:000PM)

MPCB-CAC-00

0000

0058

MPCB-CAC-0000000058 (CAC Meeting Number : 8 dated August 6, 2019) Page 37 of 154

Other RelevantInformation

1] PP has applied for renewal of consent to operate with decrease in coal mining qty andincrease in CI.i.e. from 2.5 MTPA to 1.2 MTPA in mining lease area 676.53 Ha.

2] PP has obtained consent to operate for Coal mining activity for 2.5 MTPA which is valid up to31.03.2019..

3] PP has obtained Environmental Clarence for additional mining activity from 1.50 MTPA to 2.5MTPA in mining lease area from 676.53 Ha. on 17.07.2009

4] There is reduction in domestic water consumption and effluent generation.soak pit providedfor the treatment of sewage. STP for colony area is till not provided. As informed by industry atpresent work of up gradation of sewerage system is in progress and STP of capacity 1.0 MLD isproposed to be installed in 2019-20.

5]Primary ETP for work shop effluent of 75 KL capacity provided. Treated water is reused.

6]Board has issued SCN to this mine on 28.02.2017 for the non compliance .i.e. fugitiveemissions were observed in surrounding area and not provided adequate APCS to the variouslocations of mining activities.PP has submitted reply to SCN on 19.03.2017 which is notsatisfactory.

10] PP had not submitted BGs as per the consent conditions.Recommendation ofCAC/CC Cell

We may keep this in abeyance and we may call to PP for for the technical presentation alongwith the action plans about installation of PCS.

ConsentRecommended forperiod upto as perSectoral Approachpolicy

-----

MPCB-CAC-00

0000

0058

MPCB-CAC-0000000058 (CAC Meeting Number : 8 dated August 6, 2019) Page 38 of 154

ITEM NO: 8 - Unique Number: MPCB-CONSENT-0000066177Fresh CAC ITEMRegion: SRO - Chandrapur Section: CAC Date: 01.08.2019UAN Number: MPCB-CONSENT-0000066177 TAG CACName & Address: Pauni Opencast Mine (Pouni Opencast mine, WCL Ballarpur Area)Location ofIndustrial unit: - WCL, Ballarpur Area Rajura

Email: [email protected] Telephone number: 8275968286Industry Type: R35 Mining and ore beneficiationIndustry Category: REDProject Details: Existing project

Consent Applied For

Renewal of consent tooperate for coal

mining for the samecapacitywith increase

in CI

Application Date January31,2019

Date of receipt ofCAC/CC cell 19.03.2019

Capital Investment in Rs. (Crs)Existing Proposed Total

Rs.72.57 Crs + Increased by Rs. 23.58 Crs Rs. 96.153 crsDetails of

project :Existingproject

Total Plot area(sq.m.)

2550000(sq.m)

ConstructionBUA (sq.m.) - (sq.m)

Product and By-product detailsSr.no Product Name Quantity1 Coal 0.9 MT/ASr.no By-Product Name Quantity2 - 0Applicabilty

ofCRZ

ClearenceDistance

from riverIndustrial

location policy Eco-sensitive Moratonium EC Direction of MoEF forwestern ghats

NO YES NO NO NO YES NO

If Yesprovidedetails

Wardha River- 8.00 Km

Based on:

Status:Obtained (EC Ref. No. -J-11015/118/2013-IA.II(M)dtd: 24.12.2014)

Details of CCA,Consents,Authorization and EC obtained Consent no. Consent

granted date ValidityCapital

Investmentin Crs

Total plotarea

ConstructionBUA

(FSI+Non-FSI)Remarks

C2O BO/JD(APC)/EICno.CH-1704/1747-15/O/CC-827 19.01.2016 31.03.2019 Rs.72.57

Crs

For MLarea 255Ha and

0.9 MTPAcoal

mining

C2E J-11015/118/2013-IA(M) 24.12.2014

For MLarea 255Ha and

expansionfrom 0.7

to 0.9MTPAcoal

mining

Existing production details

C to OSr.No Product Name Max quantity

1 Coal Mining on area of 255 Ha 0.9 MTPA

C to ESr.No Product Name Max quantity

1 NA NA

Bio-Medical Waste DetailsAnnual Rpt.(Form-II): NA

Accident Rpt.(Form-III): NA

MPCB-CAC-00

0000

0058

MPCB-CAC-0000000058 (CAC Meeting Number : 8 dated August 6, 2019) Page 39 of 154

BMWGeneration

Sr.No Category Max quantity (Kg/M)

1 NA NA

Disposal @CBMWTF: No

Member ofCBMWTF: NA

CaptiveDisposal: No

Incinerator Capacity Fuel Type Auto Feeding Temp.Recorder Online Monitoring

NA NA NA

Autoclave Type(Vertical/Horizontal)

Temp &Pressure

Recording

Shredder Plastic WasteDisposal

Compliance of Water Pollution Related Conditions Purpose Water Consumption

in CMD as appliedEffluent generationas applied in CMD

TreatmentSteps

DisposalDetails

Remarks/Adequeteland Available

1 Domestic Purposes 16 5 SepticTank Others -

2Processing wherebywater gets polluted &pollutants are easilybiodegradable

0 0 --NA-- --NA-- -

3Processing wherebywater gets polluted &pollutants are noteasily biodegradable

0 0 --NA-- --NA-- -

4IndustrialCooling,spraying inmine pits or boilerfeed

318 0 --NA-- --NA-- -

5Others such asgardening,agricultureetc

0 NA NA NA NA

Whether any deviation in water consumption observed compared toprevious consent NO Remarks:

Compliance to existing unit in case applied for expansion C to E/O/R NOSource of water supply

In case proposed discharge to CETP forfurther treatment

CETP Capacity to handle additional load NOName of CETP

Existing JVS results EffluentSr.no. Date of visit Board official's

name:Whether samplecollected or not:

Whether results areconfirming to standardsor not (Exceedingparameter with value)

1 Not enclosed NO NO

Details of fuel consumption and APC system as applied :-Sr. no Source Stack Fuel type Quantity Height-I,II,III APC system

detail1 - - - 0 (Kg/hr.) 0 m -Whether any deviation in fuel consumptionand APC system observed compared toprevious consent

NO Remarks:

Compliance to existing unit in case appliedfor expansion C to E/O/R NO

Existing JVS results AirSr.no. Date of visit Board official's

name:Whether samplecollected or not:

Whether results areconfirming to standardsor not (Exceedingparameter with value)

1 NO NO

Compliance of Haz. Waste ConditionDetails of hazardous waste as applied

MPCB-CAC-00

0000

0058

MPCB-CAC-0000000058 (CAC Meeting Number : 8 dated August 6, 2019) Page 40 of 154

Sr. no Type of waste Category Quantity & UOM Treatment Disposal

1 2.2 Sludge containingoil 2.2 3 Ton/Y At CHWTSDF,

ButiboriAt CHWTSDF,Butibori

2 3.3 Sludge and filterscontaminated with oil 3.3 18 Ton/Y At CHWTSDF,

ButiboriAt CHWTSDF,Butibori

3 NA NA 0 --NA-- NA NAWhether any deviation in Hz waste generation and itsdisposal,observed compared to previous consent NO Remarks:

Compliance of existing unit in case applied for expansion C to E/O/R NO

Submission of Annual Return (Form IV) NO Submission Date

Compliance of Non Hazardous/ MSW conditionDetails of Non hazardous/MSW as applied

Sr. no Type of waste Quantity & UOM Treatment Disposal1 - 0 --NA-- - -Whether any deviation in Non-Hz waste generation and itsdisposal,observed compared to previous consent NO Remarks:

Compliance of existing unit in case applied for expansion C to E/O/R NOWaterCess Returns filed upto: Paid Upto: Aug 31 2015

12:00:00:000AMDirectionissued (ifany)

BGDetails Amount Validity

BG obtained towards complience ofa) Consent/CCA condition b) directions

1 Rs.5.0 Lakhs 31.07.2019Operation and Maintenance ofpollution control system so as toachieve the consented standards

NA

2 Rs.5.0 lakhs 31.07.2019

Ensure 10% of total fleet asmechanically closed trucks for coaltransportationas per thecommitment under companysecretary WCL letter dated05.05.2014 and GM [Environment] Letter dated02.07.2014.

NA

Details of BGfortified/enchasedfor noncomplience,if any:

No

Submission ofEnvironmentalStatement

NO Year Yes, Submitted on 20/09/2018

Details of consentfee paid Amount Rs: 970000 Terms 1

In case of 1st C to OComplience of C toE conditions

Remarks

Recommendation ofTAC MPCB-C

AC-0000

0000

58

MPCB-CAC-0000000058 (CAC Meeting Number : 8 dated August 6, 2019) Page 41 of 154

Recommendations

Pratap D. Jagtap (SRO-Chandrapur):-Visit, process & put up within 20 days(Feb 11 2019 02:10:45:000PM)

Shri. U. B. Bahadule (FO-Chandrapur):-In this application there is no increase in production quantity & mine lease area.There isincrease in capital investment by Rs. 23.583 crores .Mine was visited on date 01/03/2019 .Thecopy of visit report is uploaded. During visit it was found that : Mine was operational, coaltransportation road from coal stock yard to exit gate is partly WBM and partly Tar road. TheWBM road from mining pit up to coal stock yard is made wet by using water tankers. Rain gunsare installed at coal stock yard but are in adequate. To collect surface runoff a drain is dugaround coal stock yard on its one side but there is no drain on its other side. ETP sludge in somequantity was stored in SDB near ETP and same is not sent to CHWTSDF Butibori Nagpur since2018.Two numbers of kuchha sedimentation tanks are in use and one pressure sand filter isinstalled & is ready to commission. Water cess returns submitted up to 30/11/2017 and cess paidupto 31/8/2015.

Pointwise compliance status of EC conditions and pointwise compliance status of consentconditions are uploaded in MPCB documents and partial compliance is found.Applicant has uploaded the details of calculations of consent fees .Fees paid with this applicationis Rs. 970000/. Applicant has paid renewal fees for one year i.e from 31/3/2019 up to 31/3/2020,including additional charges on production quantity & fees for increased investment ( i.e. Rs.ononcreased investment by Rs 23.583 crores).Rs 70000/- is balance with MPCB. Applicant hasapplied to CGWB Nagpur for NOC to extract ground water.Applicant has not uploaded copy of letter to CGWB Nagpur for NOC to extract ground water andCA certificate of capital investment in prescribed format.Applicant has uploaded mandatory documents such as authority letter, PAN of WCL, PAN ofapplicant, list of directors and certificate of registration.Submitted for further necessary action please.Note:- Complete remarks are uploaded in MPCB documents due to limitation of number ofcharacters in this box.Kindly see MPCB documents for complete remarks.

(Mar 7 2019 02:34:03:000PM)

Pratap D. Jagtap (SRO-Chandrapur):-Applied for plain renewal with increase in investment. Investment increased by Rs. 23.58 cr. Forincreased investment consent to establish fee not paid. Domestic water consumption & effluentreduced. For the treatment of same septic tank & soak pit provided. For mine water treatmentsedimentation tank of 360 cmd capacity & pressure sand filter provide. Mine water aftertreatment is given to Charli Village. Primary ETP for work shop effluent of 75 KL capacityprovided. Treated water is reused. HW generation is ETP sludge & Waste oil. Disposal of HW isnot regular. Last disposal is two year back. There is no CHP. Black top road in mine area notprovided. However 100 M concrete road at weigh Bridge provided. Reaming is WBM road. Fordust suppression two water tanker, 12 sprinkle provided. Planted 18000 nos of tree. Out of Rs.10.00 Lakh BG of only Rs. 5.00 lakh paid. In view of above as industry is not disposing HWregular to CHWTSDF, not submitted BG as per consent conditions, not provided black top tarroad, existing BG of Rs. 5.00 lac may be for fitted & consent may be granted for a period31.03.2021 with appropriate BG after receipt of C to E fee for increased investment.(Mar 19 2019 01:19:15:000PM)

Mr.P.K.Mirashe(AST) (CAC-CELL-HQ):-Pl Process and put up(Mar 19 2019 05:12:04:000PM)

Other RelevantInformation

1] PP has applied for plain renewal of consent to operate for coal mining activity onmining Lease area 255 ha-0.9 MTPA.

2] PP has obtained consent to operate for the same mining activity and valid up to 31.03.2019.

3]PP has obtained Environmental Clearance for mining activity from 0.7 to 0.9 on ML area 255Ha on 24.12.2014.

4] PP has provided primary ETP i.e. sedimentation tank for the treatment of mine water.

5] PP has provided 2 nos of mobile tankers of 16 KL and 4 Kl capacity and provided fixedsprinklers at weigh bridge-2 nos and at coal stock yard-10 nos to control of air pollution.Also 100M concrete road at weigh Bridge provided.

Recommendation ofCAC/CC Cell

we may consider renewal of consent to operate for the period up to 31.03.2020 by imposingcondition that PP shall obtain NOC of CGWA within 3 months and to extend existing BGs. Alsowe may call separate proposal from SRO regarding forfeiture of BG, if any non compliance wereobserved.

ConsentRecommended forperiod upto as perSectoral Approachpolicy

31.03.2020.

MPCB-CAC-00

0000

0058

MPCB-CAC-0000000058 (CAC Meeting Number : 8 dated August 6, 2019) Page 42 of 154

ITEM NO: 9 - Unique Number: MPCB-CONSENT-0000066281Fresh CAC ITEMRegion: SRO - Kalyan III Section: CAC Date: 01.08.2019UAN Number: MPCB-CONSENT-0000066281 TAG CAC

Name & Address: Technocraft Industries (India) Limited (Garment Division) (Technocraft Industries (India)Ltd.(Yarn Div))

Location ofIndustrial unit: 375 village-Dhanivali murbad

Email: [email protected] Telephone number: 8108196751

Industry Type: R40 Yarn / Textile processing involving any effluent/emission generating processes includingbleaching, dyeing, printing and colouring

Industry Category: REDProject Details: Existing project

Consent Applied For1st consent to operate

for expansion andamalgamation with

increase in CIApplication Date February

2,2019Date of receipt ofCAC/CC cell 08.04.2019

Capital Investment in Rs. (Crs)Existing Proposed Total

Rs.71.92 Crs Rs. 44.70 Crs Rs. 116.62 CrsDetails of

project :Existingproject

Total Plot area(sq.m.) 142000 (sq.m) Construction

BUA (sq.m.) 81500 (sq.m)Product and By-product details

Sr.no Product Name Quantity1 Cotton Yarn 1100 MT/M2 Melange yarn 240 MT/M3 Hosiery 1000 MT/M4 T-Shirts 225000 Pcs/MSr.no By-Product Name Quantity5 Cotton Waste 546 Melange Waste 407 Fabric waste Chindi 20Applicabilty

ofCRZ

ClearenceDistance

from riverIndustrial

location policy Eco-sensitive Moratonium EC Direction of MoEF forwestern ghats

NO NO NO NO NO NO NO

If Yesprovidedetails

--NA-- - 0.00Km

Basedon:

Status:NotApplied

Details of CCA,Consents,Authorization and EC obtained Consent no. Consent

granted date ValidityCapital

Investmentin Crs

Total plotarea

ConstructionBUA

(FSI+Non-FSI)Remarks

C2O BO/CAC Cell/CAC-UANNo.38639/CAC-1906000794 18.06.2019 31.03.2023 Rs.71.92

Crs

C2E BO/CAC-Cell-UANNo.36050/CAC-190600800 18.06.2019 Establish Rs.44.70

Crs

Existing production details

C to O

Sr.No Product Name Max quantity

1 Cotton Yarn 900 MT/M

2 Hosiery Item 240 MT/M

3 T-Shirts 225 PCs /M

4 T-Shirts 225 PCs /M

C to E

Sr.No Product Name Max quantity

1 Cotton Yarn 200 MT/M

2 Milange Yarn 240 MT/M

3 Hoisery Item 760 MT/M

Bio-Medical Waste Details

MPCB-CAC-00

0000

0058

MPCB-CAC-0000000058 (CAC Meeting Number : 8 dated August 6, 2019) Page 43 of 154

Annual Rpt.(Form-II): NA

Accident Rpt.(Form-III): NA

BMWGeneration

Sr.No Category Max quantity (Kg/M)

1 NA NA

Disposal @CBMWTF: No

Member ofCBMWTF: NA

CaptiveDisposal: No

Incinerator Capacity Fuel Type Auto Feeding Temp.Recorder Online Monitoring

NA NA NA

Autoclave Type(Vertical/Horizontal)

Temp &Pressure

Recording

Shredder Plastic WasteDisposal

Compliance of Water Pollution Related Conditions Purpose Water Consumption

in CMD as appliedEffluent generationas applied in CMD

TreatmentSteps

DisposalDetails

Remarks/Adequeteland Available

1 Domestic Purposes 74 36 STPOn Land

forGardening

NA

2Processing wherebywater gets polluted &pollutants are easilybiodegradable

1000 1050Primary +Secondary+ Tertiary

Recycle NA

3Processing wherebywater gets polluted &pollutants are noteasily biodegradable

0 0 --NA-- --NA-- NA

4IndustrialCooling,spraying inmine pits or boilerfeed

45 0 --NA-- Recycle NA

5Others such asgardening,agricultureetc

NA NA NA NA

Whether any deviation in water consumption observed compared toprevious consent NO Remarks:

Compliance to existing unit in case applied for expansion C to E/O/R NOSource of water supply

In case proposed discharge to CETP forfurther treatment

CETP Capacity to handle additional load NOName of CETP

Existing JVS results EffluentSr.no. Date of visit Board official's

name:Whether samplecollected or not:

Whether results areconfirming to standardsor not (Exceedingparameter with value)

1 22.03.2018 [ETP outlet ] YES

NOBOD-380 against-100, COD-664 against -250,SS-136against-100

1 15.05.2018 [ETP outlet ] YES YES

1 06.09.2018 [ETP outlet ] YES

NOBOD-110 against-100, COD-308 against -250,SS-158against-100

1 17.01.2018 [ ROPermit] YES YES

1 16.02.2018 [ ROPermit] YES YES

MPCB-CAC-00

0000

0058

MPCB-CAC-0000000058 (CAC Meeting Number : 8 dated August 6, 2019) Page 44 of 154

1 24.04.2018 [ ROPermit] YES YES

1 12.07.2018 [ ROPermit] YES YES

1 06.09.2018 [ ROPermit] NO YES

1 06.12.2018 [ ROPermit] NO NO

Details of fuel consumption and APC system as applied :-Sr. no Source Stack Fuel type Quantity Height-I,II,III APC system

detail

1 Boiler 1 Coal 600 (Kg/hr.) 30 mWet Scrubber,Cycloneseperator

Whether any deviation in fuel consumptionand APC system observed compared toprevious consent

NO Remarks:

Compliance to existing unit in case appliedfor expansion C to E/O/R NO

Existing JVS results AirSr.no. Date of visit Board official's

name:Whether samplecollected or not:

Whether results areconfirming to standardsor not (Exceedingparameter with value)

1 17.01.2018 [Stack] YES NOTPM-855 against-150

2 23.03.2018 [Stack] YES NOTPM-206 against-150

3 15.05.2018 [ Stack] NO NOTPM-707 against-150

4 21.07.2018 [Stack] NO NOTPM-804 against-150

Compliance of Haz. Waste ConditionDetails of hazardous waste as applied

Sr. no Type of waste Category Quantity & UOM Treatment Disposal

135.3 Chemical sludgefrom waste watertreatment

35.3 33 MT/M Landfill Landfill

2 NA NA 0 --NA-- NA NAWhether any deviation in Hz waste generation and itsdisposal,observed compared to previous consent NO Remarks:

Compliance of existing unit in case applied for expansion C to E/O/R NO

Submission of Annual Return (Form IV) NO Submission Date

Compliance of Non Hazardous/ MSW conditionDetails of Non hazardous/MSW as applied

Sr. no Type of waste Quantity & UOM Treatment Disposal1 Cotton waste 54 MT/M NA Manually2 Melange waste 40 MT/M NA Manually3 Fabric Chindi 20 MT/M NA ManuallyWhether any deviation in Non-Hz waste generation and itsdisposal,observed compared to previous consent NO Remarks:

Compliance of existing unit in case applied for expansion C to E/O/R NOWaterCess Returns filed upto: Paid Upto: Jan 1 1900

12:00:00:000AMDirectionissued (ifany)

BGDetails Amount Validity

BG obtained towards complience ofa) Consent/CCA condition b) directions

1 Rs.5.0 Lakhs 31.05.2023Towards operation and maintanaceof the effluent treatment plant toachieve disposalstandards/conditions

NA

MPCB-CAC-00

0000

0058

MPCB-CAC-0000000058 (CAC Meeting Number : 8 dated August 6, 2019) Page 45 of 154

2 Rs.5.0 Lakhs 31.05.2023Towards operation andmaintenance of the air pollutioncontrol devices to achieve emissionstandards/conditions

NA

3 Rs.5.0 Lakhs 31.05.2023 Towards total recycle the treatedeffluent NA

4 Rs.5.0 Lakhs 31.05.2023Towards compliance of consentconditions and to achieve disposalstandards / conditions.

NA

Details of BGfortified/enchasedfor noncomplience,if any:

No

Submission ofEnvironmentalStatement

NO Year 08.09.2018

Details of consentfee paid Amount Rs: 300000 Terms 1

In case of 1st C to OComplience of C toE conditions

Remarks

Recommendation ofTAC

Recommendations

Shri. Rajendra Rajput (SRO-Kalyan III):-Please process and put up.(Feb 5 2019 12:53:22:000PM)

Mrs. Aruna C. Jadhav(Aruna Rokde) (FO-Kalyan III):-It is textile processing industry. Applied for consent to operate for increased in productionquantity of cotton yarn 900 MT/M. to 1100 MT/M, Hosiery 240 MT/M to 1000 MT/M.T-shirts225000Pcs/M. and mfg. addition new production .i.e. Mélange Yarn 240 MT/M. ind. eff is 1050M3/.day. ETP capacity is 1000 m3/day and old ETP capacity is 600 m3/day. Provided ZLD typeETP. Industry visited on 26.02.2019, during visit industry found in operation. Knitting activityfound in operation without consent to operate from MPCB board. Presently Mélange yarnproduction activity not in operation machinery installation work found in progress .provided ZLDtype ETP and found in operation. Conditional restart direction issued on 04.09.2018. This officehas issued action proposal on 29.01.2019 and also query letter issued on 18.03.2019 Newthermic fluid heater provided with 32.00 Mtr stack of Ht. coal is used as fuel, wet scrubbercyclone dust collector provided. Submitted B.G of Rs. 5.00 lacs 2.25 Lacs and 10.00 Lacs andvalid up to 31.05.2023. CI is 4470.00 Lakh. fees paid Rs. 300000/- in view of the above decisionregarding grant of consent may be taken at authority level please.(Mar 19 2019 05:29:29:000PM)

Shri. Rajendra Rajput (SRO-Kalyan III):-Industry is applied for first consent to operate. Previously applied for establish for proposedexpansion. Exiting unit is in operation in the same premises. Application for C to E is alreadysubmitted to HQ, but still C to E not obtained by industry. However industry has installed plantand machinery and started production knitting activity and also installed additional thermic fluidheater with 32.00 Mtr. Chimney height. Effluent generation form the said activity is approx.1050 M3/day and same will be treated in existing ETP having capacity is 1600 M3/day (Old ETP600 M3/day New ETP 1000 M3/day) C.I. of the exiting industry is 246.68 Cr. and proposedexpansion activity C. I. is 44.70 Cr. This office has submitted proposal for action, submitted toHQ on 29.01.2019 for non-compliance of consent condition and expansion activity for proposedplant carried out without obtaining consent. In view of above the consent application issubmitted for further disposal please.(Apr 5 2019 05:52:09:000PM)

Mr.P.K.Mirashe(AST) (CAC-CELL-HQ):-Pl Process and put up(Apr 8 2019 10:30:13:000AM)

MPCB-CAC-00

0000

0058

MPCB-CAC-0000000058 (CAC Meeting Number : 8 dated August 6, 2019) Page 46 of 154

Other RelevantInformation

1] PP has applied for 1st consent to operate for expansion.i.e. for additional production qty.

2]PP has obtained consent to operate for the existing production qty which is valid up to31.01.2023.

3] PP has obtained consent to Establish for the expansion.i.e. for additional production qty on18.06.2019.

4]PP has provided ETP of capacity -1000 CMD consisting of collection tank, equalizationtank,primary clarriflocculator, aeration tank-1, aeration tank-2,secondary clarifier,Activatedcarbon filters followed by RO and MEE. PP has provided ZLD system.Analysis results of ETP outlet dated 22.03.2018 and 06.09.2018 are exceeding the consented limits.

5] PP has provided STP of capacity-100 CMD consisting of aeration tank,collection tank,, settling tank,collection tank,sand filter and activated carbon filter Analysis results of STP outlet dated 16.02.2018 and 22.03.2018 are exceeding the consented limits.

6]Dust collector system provided to coal fired boiler.Analysis results of stack shows TPMparameter is exceeding the consented limits.

7] Obtained CHWTSDF membership.

8]Submitted BGs as per earlier consent conditions.

9]SRO-Kalyan -3 has issued non compliance letter to the industry on 18.03.2019.i.e. notoperation of MEE and etc.In this context PP has submitted reply on 25.03.2019 informing thatduring visit MEE was taken for jet jump cleaning and now it is in operation.

Recommendation ofCAC/CC Cell

We may grant 1st consent to operate with amalgamation of existing consent for the period up to31.01.2023 by extending existing BGs. Also we may call to justification regarding exceedance ofJVS and call separate proposal from SRO regarding forfeiture of BGs towards non compliancesand on the basis of exceeding JVS results.

ConsentRecommended forperiod upto as perSectoral Approachpolicy

31.01.2023.

MPCB-CAC-00

0000

0058

MPCB-CAC-0000000058 (CAC Meeting Number : 8 dated August 6, 2019) Page 47 of 154

ITEM NO: 10 - Unique Number: MPCB-CONSENT-0000066508Fresh CAC ITEMRegion: SRO - Ahmednagar Section: CAC Date: 13.06.2019UAN Number: MPCB-CONSENT-0000066508 TAG CACName & Address: CG POWER & INDUSTRIAL SOLUTIONS LIMITED (B110/112,MIDC Ahmednagar,Ahmednagar.)Location ofIndustrial unit: B-110,B-111/B,B-112/2 Stamping Division MIDC INDUSTRIAL AREA,AHMEDNAGAR

Email: [email protected] Telephone number: 9764440929Industry Type:Industry Category: REDProject Details: Existing project

Consent Applied ForRenewal of consent

with name change andwith increased CI and

additional plot.Application Date February

5,2019Date of receipt ofCAC/CC cell 12.03.2019

Capital Investment in Rs. (Crs)Existing Proposed Total

58.91 30.11 89.02Details of

project :Existingproject

Total Plot area(sq.m.) 10135 (sq.m) Construction

BUA (sq.m.) 8087.95 (sq.m)Product and By-product details

Sr.no Product Name Quantity1 Electrical Stamping & Lamination 2000 MT/MSr.no By-Product Name Quantity2 NA 0Applicabilty

ofCRZ

ClearenceDistance

from riverIndustrial

location policy Eco-sensitive Moratonium EC Direction of MoEF forwestern ghats

NO YES NO NO NO NO NO

If Yesprovidedetails

Sina - 4.00 Km

Basedon:

Status:NotApplied

Details of CCA,Consents,Authorization and EC obtained Consent no. Consent

granted date ValidityCapital

Investmentin Crs

Total plotarea

ConstructionBUA

(FSI+Non-FSI)Remarks

C2R BO/JD(APC)/EIC No.NK-18766-15/R/CC-14354 09.11.2015 29.02.2019 58.91

Existing production details

C to OSr.No Product Name Max quantity

1 Electrical Stamping and Lamination 2000 MT/Month

C to ESr.No Product Name Max quantity

1 NA NA

Bio-Medical Waste DetailsAnnual Rpt.(Form-II):Accident Rpt.(Form-III):

BMWGeneration

Sr.No Category Max quantity (Kg/M)

1 NA NA

Disposal @CBMWTF: No

Member ofCBMWTF:CaptiveDisposal: No

Incinerator Capacity Fuel Type Auto Feeding Temp.Recorder Online Monitoring

MPCB-CAC-00

0000

0058

MPCB-CAC-0000000058 (CAC Meeting Number : 8 dated August 6, 2019) Page 48 of 154

Autoclave Type(Vertical/Horizontal)

Temp &Pressure

Recording

Shredder Plastic WasteDisposal

Compliance of Water Pollution Related Conditions Purpose Water Consumption

in CMD as appliedEffluent generationas applied in CMD

TreatmentSteps

DisposalDetails

Remarks/Adequeteland Available

1 Domestic Purposes 25 25 STPprovided

On Landfor

Gardening800 sq. mtrs

2Processing wherebywater gets polluted &pollutants are easilybiodegradable

0 0 --NA-- --NA-- NA

3Processing wherebywater gets polluted &pollutants are noteasily biodegradable

0 0 --NA-- --NA-- NA

4IndustrialCooling,spraying inmine pits or boilerfeed

1 0 --NA-- --NA-- NA

5Others such asgardening,agricultureetc

Agriculture -5.0 cmd NA NA NA NA

Whether any deviation in water consumption observed compared toprevious consent NO Remarks:

Compliance to existing unit in case applied for expansion C to E/O/R NOSource of water supply

In case proposed discharge to CETP forfurther treatment

CETP Capacity to handle additional load NOName of CETP

Existing JVS results EffluentSr.no. Date of visit Board official's

name:Whether samplecollected or not:

Whether results areconfirming to standardsor not (Exceedingparameter with value)

1 28.02.2019 YES YES1 21.03.2018 YES YES

Details of fuel consumption and APC system as applied :-Sr. no Source Stack Fuel type Quantity Height-I,II,III APC system

detail1 D.G. 1 HSD 15 (Kg/hr.) 5 m Stack2 Furnace 2 LPG 3 (Kg/hr.) 10 m StackWhether any deviation in fuel consumptionand APC system observed compared toprevious consent

NO Remarks:

Compliance to existing unit in case appliedfor expansion C to E/O/R NO

Existing JVS results AirSr.no. Date of visit Board official's

name:Whether samplecollected or not:

Whether results areconfirming to standardsor not (Exceedingparameter with value)

1 NO NO

Compliance of Haz. Waste ConditionDetails of hazardous waste as applied

Sr. no Type of waste Category Quantity &UOM Treatment Disposal

1 5.1 Used or spent oil 5.1 85 Ltr/M Recycle Recycler/CHWTSDF2 5.1 Used or spent oil 5.1 200 Ltr/M CHWTSDF CHWTSDF

3 5.2 Wastes or residuescontaining oil 5.2 100 Kg/M CHWTSDF CHWTSDF

4 Other Hazardous Waste Other 8 No/M CHWTSDF CHWTSDF

MPCB-CAC-00

0000

0058

MPCB-CAC-0000000058 (CAC Meeting Number : 8 dated August 6, 2019) Page 49 of 154

5 Other Hazardous Waste Other 10 Ltr/A CHWTSDF CHWTSDF

633.1 Emptybarrels/containers/linerscontaminated withhazardous chemicals /wastes

33.1 50 No/M Recycle Recycler/MEPL

7 Other Hazardous Waste Other 40 Kg/Annum Recycler Recycler8 Other Hazardous Waste Other 50 Kg/Annum Recycle Recycler/Reprocessor9 NA NA 0 --NA-- NA NAWhether any deviation in Hz waste generation and itsdisposal,observed compared to previous consent YES Remarks:Industry has increased HW Catg 5.2 from

25 kg/M to 100 Kg/M compared to previous consent.Compliance of existing unit in case applied for expansion C to E/O/R NO

Submission of Annual Return (Form IV) NO Submission Date

Compliance of Non Hazardous/ MSW conditionDetails of Non hazardous/MSW as applied

Sr. no Type of waste Quantity & UOM Treatment Disposal1 Brass Wire Scrap 0.15 MT/A NA SALE2 General MS Scrap 5 MT/M NA SALE3 Melting MS Scrap 1300 MT/M NA SALE4 Waste Packing Plastic 2 MT/M NA SALE5 Waste MS Packing Strips 5 MT/M NA SALE6 G.I. Circle scrap 0.5 MT/M NA SALE7 Wooden Pallets Waste 2 MT/M NA SALE8 Paper/Corrugated waste 1.5 MT/M NA SALEWhether any deviation in Non-Hz waste generation and itsdisposal,observed compared to previous consent NO Remarks:

Compliance of existing unit in case applied for expansion C to E/O/R NOWaterCess Returns filed upto: Paid Upto: Jan 1 1900

12:00:00:000AMDirectionissued (ifany)

BGDetails Amount Validity

BG obtained towards complience ofa) Consent/CCA condition b) directions

1 Rs. 5 lakh 30.06.2019 Towards O&M of pollution controlsystem NA

2 Rs. 5 lakh 30.06.2019 Towards installation of STP before31.03.2016 NA

Details of BGfortified/enchasedfor noncomplience,if any:Submission ofEnvironmentalStatement

NO Year YES 27.9.2018

Details of consentfee paid Amount Rs: 7,00,000/- Terms 5

In case of 1st C to OComplience of C toE conditions

Remarks

Recommendation ofTAC

MPCB-CAC-00

0000

0058

MPCB-CAC-0000000058 (CAC Meeting Number : 8 dated August 6, 2019) Page 50 of 154

Recommendations

Mr Ajit V Patil (SRO-Ahmednagar):-process and put up.... CAC(Feb 20 2019 04:56:42:000PM)

Shri Pramod Doke (FO-Ahmednagar):-CAC--Board consent valid upto 29.02.2019 for mfg of Electric Stamping & lamination-2000MT/M. Now applied for renewal of consent for 5 year period. Capital investment increased fromRs.58.91 to Rs.89.02 Cr. Rs.625000 fee paid. Additional payment option of Rs.75000/- given forincrease in CI. Industrial effluent is Nil. For Domestic effluent STP provided in the form ofprimary, secondary & tertairy treatment. Treated effluent used for gardeing. JVS samplecollected on 28.02.19, Result awaited. Industry having one LPG Furnace for which stack ofheight 10 mtr provided. Presently Furnace is not in operation due to work order issue. As perconsent BG of Rs.5.0 lac & 5.0 lac submitted & valid upto 30.06.2019, Recommended for grantof Renewal of consent.(Mar 11 2019 06:22:53:000PM)

Mr Ajit V Patil (SRO-Ahmednagar):-Board consent valid upto 29.02.2019 for mfg of Electric Stamping & lamination-2000 MT/M.Now applied for renewal of consent for 5 year period. Capital investment increased fromRs.58.91 to Rs.89.02 Cr. Industrial effluent is Nil. For Domestic effluent STP provided in theform of primary, secondary & tertairy treatment. Treated effluent used for gardeing. JVS samplecollected on 28.02.19, Result awaited. Industry having one LPG Furnace for which stack ofheight 10 mtr provided. Presently Furnace is not in operation due to work order issue. As perconsent BG of Rs.5.0 lac & 5.0 lac submitted & valid upto 30.06.2019, Recommended for grantof Renewal of consent.(Mar 11 2019 06:40:56:000PM)

Mr.P.K.Mirashe(AST) (CAC-CELL-HQ):-Pl Process and put up(Mar 12 2019 12:44:48:000PM)

Other RelevantInformation

SRO reported that'

1] Industrial effluent is Nil. For Domestic effluent STP provided in the form of primary,secondary & tertairy treatment. Treated effluent used for gardening. Industry having one LPGFurnace for which stack of height 10 mtr provided. Presently Furnace is not in operation due towork order issue.

Industry vide letter dated 05.04.2019 clarified that the CI was increased by 30.12 Cr due toaddition of plot no B111/B- 7.98 Cr, construction of Shed on plot no. B11/B- 6.71 Cr and shiftingof machinery from Kanjur plant - 15.64 Cr etc. Industry further clarified that these machines arenot part of finished product and are being used for intermediate production for qualityimprovement.

Industry has submitted the ROC certificate issued by GoI vide letter dated 27.02.2017 for namechange from M/s. Crompton Greaves Ltd to M/s. CG POWER & INDUSTRIAL SOLUTIONSLIMITED (copy uploaded)

Recommendation ofCAC/CC Cell

We may consider the case for renewal of consent with increase in CI and addition of plot withname change from M/s. Crompton Greaves Ltd to M/s. CG POWER & INDUSTRIAL SOLUTIONSLIMITED to manufacture Electrical Stamping and Lamination- 2000 MT/M for the period upto28.02.2024 by imposing following conditions;

1] Industry shall extend the BG of Rs. 5 lakh obtained towards O&M of pollution control system.

Consent shall be issued after receipt of plot amalgamation letter from MIDC, latets JVS results ofSTP outlet and submission of additional requisite consent fee, if any.

ConsentRecommended forperiod upto as perSectoral Approachpolicy

28.02.2024MPCB-CAC-00

0000

0058

MPCB-CAC-0000000058 (CAC Meeting Number : 8 dated August 6, 2019) Page 51 of 154

ITEM NO: 11 - Unique Number: MPCB-CONSENT-0000066919Fresh CAC ITEMRegion: SRO - Chandrapur Section: CAC Date: 01.08.2019UAN Number: MPCB-CONSENT-0000066919 TAG CACName & Address: Pauni II Expansion OC (Pauni II Expansion OC, WCL Ballarpur Area)Location ofIndustrial unit: - Near Sakhari Village Rajura

Email: [email protected] Telephone number: 8275968286Industry Type: R35 Mining and ore beneficiationIndustry Category: REDProject Details: Existing project

Consent Applied For1st consent to operate

for expansion withincrease inCI

Application Date February12,2019

Date of receipt ofCAC/CC cell 18.03.2019

Capital Investment in Rs. (Crs)Existing Proposed Total

Rs.56.75 Crs + Increased by Rs. 499.00 Crs Rs.555.75 CrsDetails of

project :Existingproject

Total Plot area(sq.m.)

10955200(sq.m)

ConstructionBUA (sq.m.) 26000 (sq.m)

Product and By-product detailsSr.no Product Name Quantity1 Coal 2.65 MTPASr.no By-Product Name Quantity2 - 0Applicabilty

ofCRZ

ClearenceDistance

from riverIndustrial

location policy Eco-sensitive Moratonium EC Direction of MoEF forwestern ghats

NO YES NO NO NO YES NO

If Yesprovidedetails

Wardha River- 9.00 Km

Basedon:

Status:AppliedBut Notobtained

Details of CCA,Consents,Authorization and EC obtained Consent no. Consent

granted date ValidityCapital

Investmentin Crs

Total plotarea

ConstructionBUA

(FSI+Non-FSI)Remarks

C2O BO/JD(APC)/TB-2 UANNo.33454/R/CC-1902000483 12.02.2019 31.01.2022 Rs.56.75

For coalmining

-0.6 MTPAon MLarea

316.30 Ha

EC J-110157/71/2005-IA.II(M) 02.06.2006

For coalmining

-0.6 MTPAon MLarea

316.30 Ha

EC J-11015/80/2016-IA.II(M) 28.03.2019

For coalmining-0.6 to3.25

MTPA onML area1095.52

Ha

Existing production details

C to OSr.No Product Name Max quantity

1 Coal mining activity in ML Area 1095.52 Ha 2.65 MTPA

C to ESr.No Product Name Max quantity

1 NA NA

Bio-Medical Waste Details

MPCB-CAC-00

0000

0058

MPCB-CAC-0000000058 (CAC Meeting Number : 8 dated August 6, 2019) Page 52 of 154

Annual Rpt.(Form-II): NA

Accident Rpt.(Form-III):

BMWGeneration

Sr.No Category Max quantity (Kg/M)

1 NA NA

Disposal @CBMWTF: No

Member ofCBMWTF: NA

CaptiveDisposal: No

Incinerator Capacity Fuel Type Auto Feeding Temp.Recorder Online Monitoring

NA NA NA

Autoclave Type(Vertical/Horizontal)

Temp &Pressure

Recording

Shredder Plastic WasteDisposal

Compliance of Water Pollution Related Conditions Purpose Water Consumption

in CMD as appliedEffluent generationas applied in CMD

TreatmentSteps

DisposalDetails

Remarks/Adequeteland Available

1 Domestic Purposes 50 20SepticTank &Soak Pit

Others -

2Processing wherebywater gets polluted &pollutants are easilybiodegradable

0 0 --NA-- --NA-- -

3Processing wherebywater gets polluted &pollutants are noteasily biodegradable

0 0 --NA-- --NA-- -

4IndustrialCooling,spraying inmine pits or boilerfeed

300 0 --NA-- --NA-- -

5Others such asgardening,agricultureetc

0 NA NA NA NA

Whether any deviation in water consumption observed compared toprevious consent NO Remarks:

Compliance to existing unit in case applied for expansion C to E/O/R NOSource of water supply

In case proposed discharge to CETP forfurther treatment

CETP Capacity to handle additional load NOName of CETP

Existing JVS results EffluentSr.no. Date of visit Board official's

name:Whether samplecollected or not:

Whether results areconfirming to standardsor not (Exceedingparameter with value)

1mine is not inoperation from lastone year.

NO NO

Details of fuel consumption and APC system as applied :-Sr. no Source Stack Fuel type Quantity Height-I,II,III APC system

detail1 - 0 - 0 (Kg/hr.) 0 m -Whether any deviation in fuel consumptionand APC system observed compared toprevious consent

NO Remarks:

Compliance to existing unit in case appliedfor expansion C to E/O/R NO

Existing JVS results Air

MPCB-CAC-00

0000

0058

MPCB-CAC-0000000058 (CAC Meeting Number : 8 dated August 6, 2019) Page 53 of 154

Sr.no. Date of visit Board official'sname:

Whether samplecollected or not:

Whether results areconfirming to standardsor not (Exceedingparameter with value)

1mine is not inoperation from lastone year.

NO NO

Compliance of Haz. Waste ConditionDetails of hazardous waste as applied

Sr. no Type of waste Category Quantity & UOM Treatment Disposal

1 2.2 Sludge containingoil 2.2 9 Ton/Y CHWTSDF, Butibori CHWTSDF, Butibori

2 3.3 Sludge and filterscontaminated with oil 3.3 4 Ton/Y CHWTSDF, Butibori CHWTSDF, Butibori

3 NA NA 0 --NA-- NA NAWhether any deviation in Hz waste generation and itsdisposal,observed compared to previous consent NO Remarks:

Compliance of existing unit in case applied for expansion C to E/O/R NO

Submission of Annual Return (Form IV) NO Submission Date

Compliance of Non Hazardous/ MSW conditionDetails of Non hazardous/MSW as applied

Sr. no Type of waste Quantity & UOM Treatment Disposal1 - 0 --NA-- - -Whether any deviation in Non-Hz waste generation and itsdisposal,observed compared to previous consent NO Remarks:

Compliance of existing unit in case applied for expansion C to E/O/R NOWaterCess Returns filed upto: Paid Upto: Jan 1 1900

12:00:00:000AMDirectionissued (ifany)

BGDetails Amount Validity

BG obtained towards complience ofa) Consent/CCA condition b) directions

1 Rs.22.0 Lakhs 31.05.2022 BGs under water pollution aspect NA2 Rs.95.0 Lakhs 31.05.2022 BGs under Air pollution aspect NA

3 Rs.5.0 Lakhs 31.05.2022 BG under for non hazardous (Solidwaste )Aspect NA

4 Rs.5.0 Lakhs 31.05.2022 BG under for Hazardous wasteAspect NA

5 Rs.25.0 Lakhs 31.05.2022 Towards O & M of PCs. NADetails of BGfortified/enchasedfor noncomplience,if any:

No

Submission ofEnvironmentalStatement

NO Year Yes, submitted on 20/09/2018

Details of consentfee paid Amount Rs: 2058008 Terms 1

In case of 1st C to OComplience of C toE conditions

Remarks

Recommendation ofTAC

MPCB-CAC-00

0000

0058

MPCB-CAC-0000000058 (CAC Meeting Number : 8 dated August 6, 2019) Page 54 of 154

Recommendations

Pratap D. Jagtap (SRO-Chandrapur):-Visit, process & put up within 20 days(Feb 16 2019 12:59:02:000PM)

Shri. Kushal N. Aucharmal(additonal charge) (FO-Chandrapur):-Unit is a coal mine project and has applied for consent to establish and operate for expansion ofthe mine from 0.6 MTPA to 3.25 MTPA. They have submitted minutes of 42nd meeting of ExpertAppraisal Committee (EAC) held on 24/01/2019, committee has decided to grant EC for theperiod of 1 year. They have obtained consent for their existing project on 12/02/2019 for 0.6MTPA. It is valid upto 31/01/2022. Visit was carried out to the unit on 26/02/2019 and observedthat village sakhari is around 500 m from the project. Factory representative informed that theweighbridge, coal stock area, ETP of service station and Sedimentation tank will be common forexisting and expansion projects. They have not provided concrete road at weighbridge, coal dustobserved in this area. THey have provided 08 nos of rain guns in this area. 10 nos of rain gunsare provided at coal stock area but rain guns are not sufficient at coal stock area. They providedcommon ETP of capacity 150 CMD. They have provided common sedimentation tank of capacity1000 cmd. Mine water after sedimentation is pumped into pond at Sakhari village. They have notprovided STP for treatment of domestic effluent.They are having 02 nos of mobile water tankersfor dust suppression on road. They have not provided tar road of length 500 -600 m fromweighbridge to PWD road for transportation of coal. They have not yet started any excavation ofnew pit. In the existing plant they planted 25000 nos of plants in 10.0 Ha. They have not provideCAAQMS in the existing mine. They have submitted bank guarantee of Rs: 5 + 5 lakhs againstRs: 157 lakhs (BG regime). For this New Project they have applied for Consent to Establish videUAN No- MPCB-CONSENT-0000065883. Capital investment for C to O of the project isRs.49900.42 Lacks, and paid fee of Rs. 2058008/- for 1 Year. The application is hereby submittedfor further consideration.(Feb 27 2019 12:14:21:000PM)

Pratap D. Jagtap (SRO-Chandrapur):-Industry has applied for consent to operate- Expansion for increase in production with increasein investment. Also application for consent to establish for increase in production & investmentis submitted to CAC cell – UAN No. 65883. Earlier consent which is granted on 12.02.2019 isvalid up to 31.01.2022 for production capacity of 0.6 Million Ton per Annum with mining leasearea of 316.30 Ha with investment Rs. 56.75 Cr. Now applied for consent to operate- Expansionfor production quantity 3.25 Million Ton per Annam (Existing 0.6 + Proposed 2.65 Million TonPer Annum) with mining lease area of 1095.52 Ha with investment Rs. 499.0042. cr Industry haspaid consent to operate fee with mining charges for one year. Regarding EC industry hassubmitted minutes of 42nd meeting of Expert Appraisal Committee (EAC) held on 24/01/2019,committee has decided to grant EC for the period of 1 year.For the proposed project requiredwater consumption for domestic is 61 cmd & effluent generation is 43.5 cmd. For the treatmentof the same septic tank along with soak pit provided. For the mine water already sedimentationtank of more than 1000 kld capacity provided. For work shop effluent ETP of 150 KLD is alreadyprovided. Treated water will be reused. However till workshop activity not commissioned.Propose to provide CHP. For the air pollution control system of existing plant & proposed plant 2no. of water tanker of capacity 20 KL capacity, 10 no of rain guns around coal stock yard & 8nos. at weighbridge provided. HW will be disposed through CHWTSDF. As per existing consentconditions dated 12.02.2019 industry has not submitted BG as per BG regime. Only BG of Rs.10.0 lacks submitted, installation of CAAQMS is in tendering process will be installed withinthree months, will convert existing water sprinkle arrangement into chemical foggingarrangement, no proposal for real time coal ash analyser, black top road not provide andregarding same proposal is submitted to HQ for approval. At present coal mine activity hasstooped as the target of financial year achieved. In view of above we may call industryrepresentative for personnel hearing at HQ level for the compliance of existing consentconditions & after that consent to operate with a overriding effect to consent dated 12.02.2019may be granted for a period of one year only.(Mar 16 2019 05:11:06:000PM)

Mr.P.K.Mirashe(AST) (CAC-CELL-HQ):-Pl Process and put up(Mar 18 2019 10:10:38:000AM)MPCB-C

AC-0000

0000

58

MPCB-CAC-0000000058 (CAC Meeting Number : 8 dated August 6, 2019) Page 55 of 154

Other RelevantInformation

1] PP has applied for 1st consent to operate for expansion for the additional coal mining activity-2.65 MTPA. i.e. from 0.6 MTPA to 3.25 MTPA in mining lease area 1095.52 Ha.

2] PP has obtained consent to operate for Coal mining activity- 0.6 MTPA for mining lease area316.30 Ha which is valid up to 31.01.2022.and also submitted separate application for consentto Establish.

3] PP has obtained Environmental Clarence for additional mining activity 0.6 MTPA mining leasearea 316.30 Ha on 02.02.2006.PP has submitted minutes of meeting of the Expert AppraisalCommittee (EAC) dated 24.01.2019.In this meeting recommended re-validation of EC from 0.6 to3.25 MTPA in ML area 1095.52.

4] Additional domestic sewage will be treated in Septic tank followed by soak pit.

5] Sedimentation tank of more than 1000 kld capacity provided for treatment of mine water andETP of capacity 150 CMD provided for trade effluent. Treated water will be reused. However tillworkshop activity not commissioned.

6] PP has provided 2 no. of water tanker of capacity 20 KL capacity, 10 no of rain guns aroundcoal stock yard & 8 nos. at weighbridge provided to control air pollution.

8] PP had submitted BG of 10.0 Lakhs and not submitted other BGs as per the consentconditions.

9] As per earlier consent condition of CGWA, PP has not submitted copy of NOC of CGWA in theBoard.

10] SRO has reported that this mine is not in operation from last one year.Recommendation ofCAC/CC Cell

We may keep this in abeyance and we may call to PP for for the technical presentation alongwith the action plans about installation of PCS.

ConsentRecommended forperiod upto as perSectoral Approachpolicy

---

MPCB-CAC-00

0000

0058

MPCB-CAC-0000000058 (CAC Meeting Number : 8 dated August 6, 2019) Page 56 of 154

ITEM NO: 12 - Unique Number: MPCB-CONSENT-0000066513Fresh CAC ITEMRegion: SRO - Nagpur II Section: CAC Date: 01.08.2019UAN Number: MPCB-CONSENT-0000066513 TAG CAC

Name & Address: RUCHI SOYA INDUSTRIES LIMITED (P.H. No. 76, Plot No. 249-252, Butibori Umred Road,Butibori, Nagpur)

Location ofIndustrial unit: P.H. 76 PLOT NO. 249-252 & 313 BUTIBORI NAGPUR GRAMIN

Email: [email protected] Telephone number: 8800192935Industry Type: O71 Vegetable oil manufacturing including solvent extraction and refinery /hydrogenated oilsIndustry Category: ORANGEProject Details: Existing project

Consent Applied ForRenewal of consent tooperate for the sameproduct and capacitywith increase in CI

Application Date February5,2019

Date of receipt ofCAC/CC cell 28.03.2019

Capital Investment in Rs. (Crs)Existing Proposed Total

Rs.84.79 Crs + Increased by Rs. 160.78 Crs Rs.245.5796 CrsDetails of

project :Existingproject

Total Plot area(sq.m.)

266430.198(sq.m)

ConstructionBUA (sq.m.) 34580 (sq.m)

Product and By-product detailsSr.no Product Name Quantity1 Solvent Extracted Crude soyabean Oil 81000 MT/A2 De-Oiled Cake 364500 MT/A3 Refined Soyabean Oil 76200 MT/A4 Turbo Generator for Captive Power Generation 0.98 MWSr.no By-Product Name Quantity5 Lecithin 2600 MT/A6 Acid Oil 900 MT/AApplicabilty

ofCRZ

ClearenceDistance

from riverIndustrial

location policy Eco-sensitive Moratonium EC Direction of MoEF forwestern ghats

NO YES NO NO NO NO NO

If Yesprovidedetails

Venna - 4.00Km

Basedon:

Status:NotApplied

Details of CCA,Consents,Authorization and EC obtained Consent no. Consent

granted date ValidityCapital

Investment inCrs

Total plotarea

ConstructionBUA

(FSI+Non-FSI)Remarks

C2EBO/CAC-Cell/EIC

No.NG-1187-14/R/CAC-426

08.01.2016 31.03.2019 Rs.84.79 Crs

Existing production details

C to O

Sr.No Product Name Max quantity

1 Solvent Extracted Crude soyabean Oil 81000 MT/A

2 De-Oiled Cake 364500 MT/A

3 Refined Soyabean Oil 76200 MT/A

4 Turbo Generator for Captive Power Generation 0.98 MW

5 Lecithin [ By product] 2600 MT/A

6 Acid oil [ By product] 900 MT/A

C to ESr.No Product Name Max quantity

1 NA NA

Bio-Medical Waste DetailsAnnual Rpt.(Form-II): NA

MPCB-CAC-00

0000

0058

MPCB-CAC-0000000058 (CAC Meeting Number : 8 dated August 6, 2019) Page 57 of 154

Accident Rpt.(Form-III): NA

BMWGeneration

Sr.No Category Max quantity (Kg/M)

1 NA NA

Disposal @CBMWTF: No

Member ofCBMWTF: NA

CaptiveDisposal: No

Incinerator Capacity Fuel Type Auto Feeding Temp.Recorder Online Monitoring

NA NA

Autoclave Type(Vertical/Horizontal)

Temp &Pressure

Recording

Shredder Plastic WasteDisposal

Compliance of Water Pollution Related Conditions Purpose Water Consumption

in CMD as appliedEffluent generationas applied in CMD

TreatmentSteps

DisposalDetails

Remarks/Adequeteland Available

1 Domestic Purposes 07.0 5SepticTank &Soak Pit

On Landfor

Gardening

2Processing wherebywater gets polluted &pollutants are easilybiodegradable

500 200 Primary +Secondary Recycle

3Processing wherebywater gets polluted &pollutants are noteasily biodegradable

0 0 --NA-- --NA--

4IndustrialCooling,spraying inmine pits or boilerfeed

700 0 --NA-- --NA--

5Others such asgardening,agricultureetc

15 NA NA NA NA

Whether any deviation in water consumption observed compared toprevious consent NO Remarks:

Compliance to existing unit in case applied for expansion C to E/O/R NOSource of water supply

In case proposed discharge to CETP forfurther treatment

CETP Capacity to handle additional load NOName of CETP

Existing JVS results EffluentSr.no. Date of visit Board official's

name:Whether samplecollected or not:

Whether results areconfirming to standardsor not (Exceedingparameter with value)

1 Not enclosed NO NO

Details of fuel consumption and APC system as applied :-Sr. no Source Stack Fuel type Quantity Height-I,II,III APC system

detail

1 Thermax Boiler 1 coal 2500 (Kg/hr.) 40 mTrema Cyclone,Air preheater &Bag Filter

2 DG Set 1 HSD 50 (Kg/hr.) 10.5 mTrema Cyclone,Air preheater &Bag Filter

Whether any deviation in fuel consumptionand APC system observed compared toprevious consent

NO Remarks:

Compliance to existing unit in case appliedfor expansion C to E/O/R NO

Existing JVS results Air

MPCB-CAC-00

0000

0058

MPCB-CAC-0000000058 (CAC Meeting Number : 8 dated August 6, 2019) Page 58 of 154

Sr.no. Date of visit Board official'sname:

Whether samplecollected or not:

Whether results areconfirming to standardsor not (Exceedingparameter with value)

1 Not enclosed NO NO

Compliance of Haz. Waste ConditionDetails of hazardous waste as applied

Sr. no Type of waste Category Quantity & UOM Treatment Disposal

1 Other HazardousWaste Other 36 MT/A Through MEPL Through MEPL

(Authorised Agency)2 NA NA 0 --NA-- NA NAWhether any deviation in Hz waste generation and itsdisposal,observed compared to previous consent NO Remarks:

Compliance of existing unit in case applied for expansion C to E/O/R NO

Submission of Annual Return (Form IV) NO Submission Date

Compliance of Non Hazardous/ MSW conditionDetails of Non hazardous/MSW as applied

Sr. no Type of waste Quantity & UOM Treatment Disposal1 NA 0 --NA-- NA NAWhether any deviation in Non-Hz waste generation and itsdisposal,observed compared to previous consent NO Remarks:

Compliance of existing unit in case applied for expansion C to E/O/R NOWaterCess Returns filed upto: Paid Upto: Jun 30 2015

12:00:00:000AMDirectionissued (ifany)

BGDetails Amount Validity

BG obtained towards complience ofa) Consent/CCA condition b) directions

1 Rs.6.0 Lakhs 31.07.2019Towards Operation andmaintenance of pollution controlsystem

NA

Details of BGfortified/enchasedfor noncomplience,if any:

No.

Submission ofEnvironmentalStatement

NO Year Regularly Submitting (Copyenclosed ) Last date:-24/09/2018

Details of consentfee paid Amount Rs: 1285145 Terms 2

In case of 1st C to OComplience of C toE conditions

Remarks

Recommendation ofTAC MPCB-C

AC-0000

0000

58

MPCB-CAC-0000000058 (CAC Meeting Number : 8 dated August 6, 2019) Page 59 of 154

Recommendations

Anand N. Katole (SRO-Nagpur II):-process and put up(Feb 20 2019 05:29:01:000PM)

Vinod Shukla (FO-Nagpur II):-Red/LSI CAC. Applied for renewal of consent for mfg. of solvent extraction of soya oil, DOC,refined soya oil & Turbo Generator for Captive Power Generation. Production quantity is sameas earlier consent. Capacity of solvent extraction plant is 1500 TPD & refinery unit is 300 TPD.Generation of trade effluent is 200 CMD & for the same primary & secondary ETP comprises ofO & G trap, primary clarifier, aeration, secondary clarifier, carbon & sand filter and SDBprovided. Treated trade effluent from solvent extraction plant & DM plant 171 CMD recycle inthe process i.e utilized for cooling tower. Remaining treated trade effluent utilized for gardeninginside the premises. Provided CPP boiler & thermax boiler (both capacity 16 TPH & both coalfired) with common stack of height 40 Meter with individual bag filter as APC. Bag filterprovided at seed unloading & cleaning section. Generation of HW is of category 34.4 which isdisposed at CHWTSDF. Obtained NOC from CGWA authority for ground water extraction.Submitted BG of RS. 4 Lakhs & 2 Lakhs as per earlier consent condition & both are valid upto31/07/2019. Submitted Env. Statement & HW returns along with other relevant documents.Submitted reply as per query letter issued. Balance fees of Rs. 18733/- is with Board as perearlier consent. Paid fees of Rs. 9,82,318/- for 2 terms with additional fees of Rs. 3,02,827/-towards increase in CI. Clarification letter regarding increase in CI is uploaded. Hence, consentmay be renewed for 2 terms i.e upto 31/03/2021 in red category. Submitted please.(Mar 27 2019 04:07:43:000PM)

Anand N. Katole (SRO-Nagpur II):-It is edible oil refinery with power generation capacity of 0.98 MW with a plain renewal. Capitalinvestment was increased from Rs.84.79 Cr. to Rs. 245.5 Cr. due to adoption of fair valuation ofasset held on 1/4/2015. CI increased substantially in the land and building. Justification isenclosed. Raw material is soybean seed which gives 18% of oil and remaining 82% is de-oiledcake, which is sold as by-product i.e. about 1500 TPD of seed produces 270 TPD of oil. This oilfurther goes to refining process. Effluent generation is from edible oil refining washing process,from acid oil plant as well as from DM water re-generation. ETP consist of biological treatmentis provided such as O & G trap, primary clarifier, aeration, secondary clarifier, carbon & sandfilter and SDB provided. Treated trade effluent from solvent extraction plant & DM plant 171CMD recycle in the process i.e. utilized for cooling tower. Remaining treated trade effluentutilized for gardening inside the premises. 2 boilers of having capacity 16 TPH is provided, oneis for steam generation and other is for captive power generation. Power generation plant is notin operation since last 2 years. Both the boiler are equipped with individual bag house. Bagfilters are also provided at seed unloading & cleaning section. Being a sick unit and seasonalunit, operation of industry is limited to 3 to 4 months in a year. Presently, industry is running at30% of its capacity, hence regular air monitoring / water monitoring is not possible. Analysisresults are not available since 2017, latest sampling done on 16/3/2019. Power generator is notin operation Necessary statutory submission such as Environment statement, Annual report hasbeen done. Latest visit report dtd.16/3/2019 is enclosed. NOC from CGWA obtained. In view ofthis renewal of consent for 2 terms 31/3/2021 may be consider.(Mar 27 2019 06:35:10:000PM)

Mr.P.K.Mirashe(AST) (CAC-CELL-HQ):-Pl process and put up(Mar 28 2019 10:58:20:000AM)

Other RelevantInformation

1] PP has applied for renewal of consent to operate for the same product and qty with increasein CI underorange category.

2] PP has obtained consent to operate for same products which is valid up to 31.03.2019 underRed category.

3] PP has submitted justification about increase in Ci vide letter dated 25.03.2019 stating thatdue to adoption of fair valuation of asset held on 1/4/2015. CI increased substantially in the landand building.

4] PP has provided ETP of capacity-250 CMD consisting of primary,secondary and tertiarytreatment.Treated trade effluent from solvent extraction plant & DM plant 171 CMD recycle inthe process i.e. utilized for cooling tower. Remaining treated trade effluent utilized forgardening inside the premises.

4]Bag filters provided to the coal fired boiler section and stack provided to DG set.

5] SRO has reported that industry is in operation only 3 to 4 months in a year.hence JVS werenot collected and Analysis results are not available since 2017.

6] PP has obtained membership of CHWTSDF.

7]PP has submitted BGs as per earlier consent condition.Recommendation ofCAC/CC Cell

We may grant renewal of consent to operate for up to 31.03.2024 the same products and withincrease in CI under Red category by extending existing BGs for the period up to 31.07.2024.

MPCB-CAC-00

0000

0058

MPCB-CAC-0000000058 (CAC Meeting Number : 8 dated August 6, 2019) Page 60 of 154

ConsentRecommended forperiod upto as perSectoral Approachpolicy

31.03.2024.

MPCB-CAC-00

0000

0058

MPCB-CAC-0000000058 (CAC Meeting Number : 8 dated August 6, 2019) Page 61 of 154

ITEM NO: 13 - Unique Number: MPCB-CONSENT-0000067640Fresh CAC ITEMRegion: SRO - Kalyan II Section: CAC Date: 29/07/2019UAN Number: MPCB-CONSENT-0000067640 TAG CACName & Address: Watson Pharma Pvt. Ltd. (N-15, Additional MIDC, Anand Nagar, Ambernath (E))Location ofIndustrial unit: Plot No. N-15, Anand Nagar, Additional MIDC, Ambernath

Email: [email protected] Telephone number: 9867189582Industry Type: R58 PharmaceuticalsIndustry Category: REDProject Details: Existing project

Consent Applied For Renewal of Consent toOperate Application Date February

22,2019Date of receipt ofCAC/CC cell 10/07/2019

Capital Investment in Rs. (Crs)Existing Proposed Total

207.2 28.7429 235.9429Details of

project :Existingproject

Total Plot area(sq.m.) 40000 (sq.m) Construction

BUA (sq.m.) 25766 (sq.m)Product and By-product details

Sr.no Product Name Quantity

1 Anti-inflammatory drugs/ Analgesic drugs/Antipyretic drugs 233 MT/A

2 Immunomodulator drugs 2 MT/A

3 Antihypertensive drugs/ antianginal drugs/Antiarrythmic drugs 22 MT/A

4 Antiulcerative drugs 9 MT/A5 Antibacterial drugs 29 MT/A6 Antihyperliloproteinemic drugs 40 MT/A7 Antihistaminic drugs 15 MT/A8 Antipneumocystic 5 MT/A9 Antithrombotic 5 MT/A10 Antiasthamatic/ Decongesant 4 MT/A11 Hemorheologic agent 5 MT/A12 R&D Products 5 MT/A13 speciality chemicals & intermediates 50 MT/A

14 Anxiolytic drugs/ Antipsychotic drugs /Anticonvulsant drugs 14 MT/A

15 Antidepressant drugs / Anaesthetic drugs 34.5 MT/A16 Anti Parkinsonian drugs 17 MT/A17 Anti spasmodic drugs 1 MT/A18 Anti Acne drugs / Anti psariatic drugs 4 MT/ASr.no By-Product Name Quantity19 NA 0Applicabilty

ofCRZ

ClearenceDistance

from riverIndustrial

location policy Eco-sensitive Moratonium EC Direction of MoEF forwestern ghats

NO YES NO NO NO YES NO

If Yesprovidedetails

Ulhas - 4.62Km

Based on:

Status:Obtained (EC Ref.No. -J-11011/56/2007-IAII(I))

Details of CCA,Consents,Authorization and EC obtained Consent no. Consent

granted date ValidityCapital

Investmentin Crs

Total plotarea

ConstructionBUA

(FSI+Non-FSI)Remarks

MPCB-CAC-00

0000

0058

MPCB-CAC-0000000058 (CAC Meeting Number : 8 dated August 6, 2019) Page 62 of 154

C2RFormat 1.0/BO/CAC-

Cell/EIC No.KN-6640-14/24th

CAC-172213/02/2015 30/04/2019 207.2

Existing production details

C to O

Sr.No Product Name Max quantity

1 Anti-inflammatory drugs/ Analgesic drugs/ Antipyretic drugs 233 MT/A

2 Immunomodulator drugs 2 MT/A

3 Antihypertensive drugs/ antianginal drugs/ Antiarrythmic drugs 22 MT/A

4 Antiulcerative drugs 9 MT/A

5 Antibacterial drugs 29 MT/A

6 Antihyperliloproteinemic drugs 40 MT/A

7 Antihistaminic drugs 15 MT/A

8 Antipneumocystic 5 MT/A

9 Antithrombotic 5 MT/A

10 Antiasthamatic/ Decongesant 4 MT/A

11 Hemorheologic agent 5 MT/A

12 R&D Products 5 MT/A

13 speciality chemicals & intermediates 50 MT/A

14 Anxiolytic drugs/ Antipsychotic drugs / Anticonvulsant drugs 14 MT/A

15 Antidepressant drugs / Anaesthetic drugs 34.5 MT/A

16 Anti Parkinsonian drugs 17 MT/A

17 Anti spasmodic drugs 1 MT/A

18 Anti Acne drugs / Anti psariatic drugs 4 MT/A

C to ESr.No Product Name Max quantity

1 NA NA

Bio-Medical Waste DetailsAnnual Rpt.(Form-II):Accident Rpt.(Form-III):

BMWGeneration

Sr.No Category Max quantity (Kg/M)

1 NA NA

Disposal @CBMWTF: NA

Member ofCBMWTF:CaptiveDisposal: NA

Incinerator Capacity Fuel Type Auto Feeding Temp.Recorder Online Monitoring

Autoclave Type(Vertical/Horizontal)

Temp &Pressure

Recording

Shredder Plastic WasteDisposal

Compliance of Water Pollution Related Conditions Purpose Water Consumption

in CMD as appliedEffluent generationas applied in CMD

TreatmentSteps

DisposalDetails

Remarks/Adequeteland Available

1 Domestic Purposes 30 25 SepticTank Recycle used for cooling

tower

2Processing wherebywater gets polluted &pollutants are easilybiodegradable

135 120Primary +Secondary+ Tertiary

Recycle Used for coolingtower

3Processing wherebywater gets polluted &pollutants are noteasily biodegradable

0 0 --NA-- --NA-- NA

4IndustrialCooling,spraying inmine pits or boilerfeed

120 24Primary +Secondary+ Tertiary

Recycle used for coolingtower

MPCB-CAC-00

0000

0058

MPCB-CAC-0000000058 (CAC Meeting Number : 8 dated August 6, 2019) Page 63 of 154

5Others such asgardening,agricultureetc

15 KL/D for gardening NA NA NA NA

Whether any deviation in water consumption observed compared toprevious consent NO Remarks:

Compliance to existing unit in case applied for expansion C to E/O/R NOSource of water supply

In case proposed discharge to CETP forfurther treatment

CETP Capacity to handle additional load YES

Name of CETP Additional AmbernathCETP

Existing JVS results EffluentSr.no. Date of visit Board official's

name:Whether samplecollected or not:

Whether results areconfirming to standardsor not (Exceedingparameter with value)

1 NO NO

Details of fuel consumption and APC system as applied :-Sr. no Source Stack Fuel type Quantity Height-I,II,III APC system

detail

1 Boiler-101 &Boiler-102 Boiler stack Furnace oil 238 (Kg/hr.) 36 m NA

2 Diesel generator101 D.G. set No. 101 HSD 158 (Kg/hr.) 11.5 m NA

3 Diesel generator102 D.G. set No. 102 HSD 158 (Kg/hr.) 11.5 m NA

4 Processscrubber-1

Scrubberstack-1 NA 0 (Kg/hr.) 20 m NA

5Processscrubber-2 (central exhaust)

Scrubberstack-2 NA 0 (Kg/hr.) 20 m NA

6 Pilot plantscrubber-3

Scrubberstack-3 NA 0 (Kg/hr.) 18 m NA

7 Pilot plantscrubber-4

Scrubberstack-4 NA 0 (Kg/hr.) 18 m NA

8 Plant-2 scrubber Scrubberstack-5 NA 0 (Kg/hr.) 13 m NA

Whether any deviation in fuel consumptionand APC system observed compared toprevious consent

NO Remarks:

Compliance to existing unit in case appliedfor expansion C to E/O/R NO

Existing JVS results AirSr.no. Date of visit Board official's

name:Whether samplecollected or not:

Whether results areconfirming to standardsor not (Exceedingparameter with value)

1 NO NO

Compliance of Haz. Waste ConditionDetails of hazardous waste as applied

Sr. no Type of waste Category Quantity & UOM Treatment Disposal

134.3 Chemical sludgefrom waste watertreatment

34.3 1.56 MT/Day NA CHWTSDF

2 28.2 Spent catalyst /spent carbo 28.2 0.05 MT/Day NA CHWTSDF/ recycler

3 5.1 Used /spent oil 5.1 0.01 MT/Day NA CHWTSDF/ recycler4 20.2 Spent solvent 20.2 6.50 MT/Day NA CHWTSDF/ recycler5 20.3 Distillation residue 20.3 0.30 MT/Day NA CHWTSDF

6 28.1 Residues andwastes* 28.1 0.05 MT/Day NA CHWTSDF

733.3 Discardedcontainers / barrels /liner

33.3 1000 No/D NACHWTSDF/ recyclerafterdecontamination

MPCB-CAC-00

0000

0058

MPCB-CAC-0000000058 (CAC Meeting Number : 8 dated August 6, 2019) Page 64 of 154

8 28.2 Off specificationproduct 28.2 0.05 MT/Day NA CHWTSDF

928.3 Date-expired,discarded and off-specification drug

28.3 0.05 MT/Day NA CHWTSDF

10 NA NA 0 --NA-- NA NAWhether any deviation in Hz waste generation and itsdisposal,observed compared to previous consent NO Remarks:

Compliance of existing unit in case applied for expansion C to E/O/R NO

Submission of Annual Return (Form IV) NO Submission Date

Compliance of Non Hazardous/ MSW conditionDetails of Non hazardous/MSW as applied

Sr. no Type of waste Quantity & UOM Treatment Disposal

1 paper/cardboards 5 MT/A NA Sale to authorizedrecycler

2 glass packaging 10 MT/A NA Sale to authorizedrecycler

3 plastic packaging 12 MT/A NA Sale to authorizedrecycler

4 metal packaging/ scrap 40 MT/A NA Sale to authorizedrecycler

5 HDPE drums 40 MT/A Washing Sale to authorizedrecycler

6 general waste(cable waste) 2 MT/A NA Sale to authorizedrecycler

7 wooden packaging 4 MT/A NA Sale to authorizedrecycler

Whether any deviation in Non-Hz waste generation and itsdisposal,observed compared to previous consent NO Remarks:

Compliance of existing unit in case applied for expansion C to E/O/R NOWaterCess Returns filed upto: Paid Upto: Jan 1 1900

12:00:00:000AMDirectionissued (ifany)

BGDetails Amount Validity

BG obtained towards complience ofa) Consent/CCA condition b) directions

1 Rs. 5 Lakh 30/08/2019 O&M of PCS NA

2 Rs. 2 Lakh 04/07/2015 Submission og design details ofMBBR & Clarifier NA

Details of BGfortified/enchasedfor noncomplience,if any:Submission ofEnvironmentalStatement

NO Year yes on 28.09.2018

Details of consentfee paid Amount Rs: 23,41,436/- + Rs. 92,994/-

(Previous Balance) Terms 5

In case of 1st C to OComplience of C toE conditions

Remarks

Recommendation ofTAC

MPCB-CAC-00

0000

0058

MPCB-CAC-0000000058 (CAC Meeting Number : 8 dated August 6, 2019) Page 65 of 154

Recommendations

Shri. M. N. Jadhav (SRO-Kalyan II):-Verify & Put up(Feb 27 2019 03:48:00:000PM)

Shri.Kishor Kerlikar (FO-Kalyan II):-Red /LSI type of industry. Capital investment is Rs. 235.94 Crs. CAC case visited on 16.5.2019.Visit report uploaded. Industry engaged in mfg of Bulk Drugs. Consent expired on 30.4.2019.Applied for plain renewal of consent. D.E. qty : 25 CMD. Septic tank is provided. Overflow ofseptic tank is connected to Equalization tank of ETP. Industrial Effluent qty : 144 CMD. Presentindustrial effluent generation is about 45- 50 CMD. Full-fledged ETP provided which compriseson primary, secondary, tertiary treatment followed by RO system & MEE. Industry hassegregated high COD stream ( approx 4 KLD) the same is treated in primary treatment followedby MEE. All the units of ETP were found in operation at the time of visit. Industry is notdischarging any treated effluent in to CETP. Treated effluent is reused for cooling towerpurpose. Thus, industry has achieved ZLD. Online pH meter, flow meter, COD, BOD, TSSanalyser are installed. Web camera is also installed. 2 nos of boiler are installed (1 stand by )Stack of height 36 mtrs attached to boiler. 2 nos of process scrubbers are provided to limit theemissions. Height of stacks 20 mtrs each. 2 nos. of DG Sets (750 KVA each) are installed withacoustic enclosures. Stack of height 7.5 mtrs each above the roof. Membership of CHWTSDF isobtained for the disposal of Hazardous Waste. Industry has paid relevant consent fee as percapital investment & also paid additional consent fee for increase in capital investment. Plainrenewal of consent may be consider, if approved.(Jun 6 2019 01:42:58:000PM)

Shri. M. N. Jadhav (SRO-Kalyan II):-Red /LSI type of industry. Capital investment is Rs. 235.94 Crs. CAC case visited on 16.5.2019.Visit report uploaded. Industry engaged in mfg of Bulk Drugs. Consent expired on 30.4.2019.Applied for plain renewal of consent. D.E. qty : 25 CMD. Septic tank is provided. Overflow ofseptic tank is connected to Equalization tank of ETP. Industrial Effluent qty : 144 CMD. Presentindustrial effluent generation is about 45- 50 CMD. Full-fledged ETP provided which compriseson primary, secondary, tertiary treatment followed by RO system & MEE. Industry hassegregated high COD stream ( approx 4 KLD) the same is treated in primary treatment followedby MEE. All the units of ETP were found in operation at the time of visit. Industry is notdischarging any treated effluent in to CETP. Treated effluent is reused for cooling towerpurpose. Thus, industry has achieved ZLD. Online pH meter, flow meter, COD, BOD, TSSanalyser are installed. Web camera is also installed. 2 nos of boiler are installed (1 stand by )Stack of height 36 mtrs attached to boiler. 2 nos of process scrubbers are provided to limit theemissions. Height of stacks 20 mtrs each. 2 nos. of DG Sets (750 KVA each) are installed withacoustic enclosures. Stack of height 7.5 mtrs each above the roof. Membership of CHWTSDF isobtained for the disposal of Hazardous Waste. Industry has paid relevant consent fee as percapital investment & also paid additional consent fee for increase in capital investment. Plainrenewal of consent is commanded up to 30.4.2024.(Jul 10 2019 05:25:32:000PM)

Mr.P.K.Mirashe(AST) (CAC-CELL-HQ):-Pl Process and put up(Jul 11 2019 10:22:07:000AM)

Other RelevantInformation

1. Existing Red/LSI industry engaged in mfg.of Bulk drug, intermediates, speciality chemicals,R&D products obtained Consent to Operate with C.I. of Rs. 207.2 Crs which expired on30/04/2019.

2. D.E. qty.-25 CMD. Septic tank is provided. Overflow of septic tank is connected toEqualization tank of ETP.

Industrial Effluent qty.- 144 CMD. At present, industrial effluent generation is about 45- 50CMD. Full-fledged ETP provided which comprises on primary, secondary, tertiary treatmentfollowed by RO system & MEE. High COD stream (approx. 4 KLD) is segregated and the same istreated in primary treatment followed by MEE.

Treated effluent is 100% recycled/reused for cooling tower make up. Treated effluent is notdischarged into CETP. Thus, industry has achieved ZLD.

3. All the units of ETP were found in operation at the time of visit on 16/05/2019. Online pHmeter, flow meter, COD, BOD, TSS analyser are installed. Web camera is also installed.

4. Now, industry has applied for grant of plain renewal of Consent to Operate with increase inC.I. by 28.7 Crs from Rs. 207.2 Crs to Rs. 235.94 Crs.

5. Two nos. of boilers are installed (1 standby), Stack of height 36 mtrs attached to boiler. 2 nosof process scrubbers are provided to limit the emissions. 2 nos. of DG Sets (750 KVA each) areinstalled with acoustic enclosures.

6. Membership of CHWTSDF is obtained for the disposal of Hazardous Waste.

MPCB-CAC-00

0000

0058

MPCB-CAC-0000000058 (CAC Meeting Number : 8 dated August 6, 2019) Page 66 of 154

Recommendation ofCAC/CC Cell

-Applied for grant of plain renewal of Consent to Operate with increase in C.I. by 28.7 Crs fromRs. 207.2 Crs to Rs. 235.94 Crs.

-Provided combined ETP consisting of primary, secondary, tertiary treatment followed by ROsystem & MEE. Treated effluent is 100% recycled/reused for cooling tower make up to achieveZLD.

-Installed online pH meter, flow meter, COD, BOD, TSS analyser, Web camera.

In view of above, we may consider the case and grant plain renewal of Consent to Operate byimposing the following conditions:1. Industry shall operate combined ETP and 100% recycle treated trade effluent for coolingtower make up so as to achieve ZLD.2. Industry shall ensure that online monitoring data is connected to CPCB/ MPCB Servers.3. Industry shall furnish BG of Rs. 25 Lakh (including existing BGs) towards compliance of theConsent conditions.

ConsentRecommended forperiod upto as perSectoral Approachpolicy

Up to 30/04/2024.

MPCB-CAC-00

0000

0058

MPCB-CAC-0000000058 (CAC Meeting Number : 8 dated August 6, 2019) Page 67 of 154

ITEM NO: 14 - Unique Number: MPCB-CONSENT-0000056805Fresh CAC ITEMRegion: SRO - Solapur Section: CAC Date:UAN Number: MPCB-CONSENT-0000056805 TAG CAC

Name & Address: Sahakar Shiromani Vasantrao Kale S.S.K. Ltd., (At Chandrabhaganagar Post Bhalawani TalukaPandharpur)

Location ofIndustrial unit: 943/1,947-950,999/1,999/2,1000-1005 Chandrabhaga Nagar at Post Bhalawani Pandharpur

Email: [email protected] Telephone number: 9822207492Industry Type: R12 Sugar ( excluding Khandsari)Industry Category: REDProject Details: Existing project

Consent Applied For Operate Application Date September19,2018

Date of receipt ofCAC/CC cell

Capital Investment in Rs. (Crs)Existing Proposed Total

221.18 Cr. 29.14 Cr. 250.32 Cr.Details of

project :Existingproject

Total Plot area(sq.m.) 43.46 (sq.m) Construction

BUA (sq.m.) 12.06 (sq.m)Product and By-product details

Sr.no Product Name Quantity1 Sugar 10500 MT/MSr.no By-Product Name Quantity2 00 003 Bagasse 336004 Press mud 35005 Molasses 4900Applicabilty

ofCRZ

ClearenceDistance

from riverIndustrial

location policy Eco-sensitive Moratonium EC Direction of MoEF forwestern ghats

NO YES NO NO NO NO NO

If Yesprovidedetails

Bhima - 10.00Km

Basedon:

Status:NotApplied

Details of CCA,Consents,Authorization and EC obtained Consent no. Consent

granted date ValidityCapital

Investmentin Crs

Total plotarea

ConstructionBUA

(FSI+Non-FSI)Remarks

C2OFormat 1.0/BO/CAC-Cell/UAN

No.0000052080/R/CAC-1902000167

04.02.2019 31.07.2019 221.18 Cr

C2EFormat 1.0/BO/CAC-Cell/UAN

No.0000003121/E/CAC-1703000514

09.03.2017 COU 29.14

Existing production details

C to OSr.No Product Name Max quantity

1 Sugar 7500 MT/M

C to ESr.No Product Name Max quantity

1 Sugar 3000 MT/M

Bio-Medical Waste DetailsAnnual Rpt.(Form-II):Accident Rpt.(Form-III):

BMWGeneration

Sr.No Category Max quantity (Kg/M)

1 NA NA

Disposal @CBMWTF: No

MPCB-CAC-00

0000

0058

MPCB-CAC-0000000058 (CAC Meeting Number : 8 dated August 6, 2019) Page 68 of 154

Member ofCBMWTF:CaptiveDisposal: No

Incinerator Capacity Fuel Type Auto Feeding Temp.Recorder Online Monitoring

Autoclave Type(Vertical/Horizontal)

Temp &Pressure

Recording

Shredder Plastic WasteDisposal

Compliance of Water Pollution Related Conditions Purpose Water Consumption

in CMD as appliedEffluent generationas applied in CMD

TreatmentSteps

DisposalDetails

Remarks/Adequeteland Available

1 Domestic Purposes 60 36 STPOn Land

forGardening

2Processing wherebywater gets polluted &pollutants are easilybiodegradable

290 88Primary +Secondary+ Tertiary

On Landfor

Gardening

3Processing wherebywater gets polluted &pollutants are noteasily biodegradable

00 00 --NA-- --NA--

4IndustrialCooling,spraying inmine pits or boilerfeed

00 00 --NA-- --NA--

5Others such asgardening,agricultureetc

NA NA NA NA

Whether any deviation in water consumption observed compared toprevious consent NO Remarks:

Compliance to existing unit in case applied for expansion C to E/O/R NOSource of water supply

In case proposed discharge to CETP forfurther treatment

CETP Capacity to handle additional load NOName of CETP

Existing JVS results EffluentSr.no. Date of visit Board official's

name:Whether samplecollected or not:

Whether results areconfirming to standardsor not (Exceedingparameter with value)

1 21.01.2019 YESNOBOD-500, COD -15200, O &G - 22.2, pH - 4.5, SS- 1020,TDS - 2740

Details of fuel consumption and APC system as applied :-Sr. no Source Stack Fuel type Quantity Height-I,II,III APC system

detail1 Boiler 1 Bagasse 36166 (Kg/hr.) 75 m ESP2 DG Set 1 HSD 2.5 (Kg/hr.) 5 m StackWhether any deviation in fuel consumptionand APC system observed compared toprevious consent

NO Remarks:

Compliance to existing unit in case appliedfor expansion C to E/O/R NO

Existing JVS results AirSr.no. Date of visit Board official's

name:Whether samplecollected or not:

Whether results areconfirming to standardsor not (Exceedingparameter with value)

1 21.01.2019 YES NOPM - 1305 & TPM - 187

Compliance of Haz. Waste ConditionDetails of hazardous waste as applied

MPCB-CAC-00

0000

0058

MPCB-CAC-0000000058 (CAC Meeting Number : 8 dated August 6, 2019) Page 69 of 154

Sr. no Type of waste Category Quantity & UOM Treatment Disposal

1 5.1 Used or spent oil 5.1 2 MT/Day NA Used as fuel in ownboiler

2 NA NA 0 --NA-- NA NAWhether any deviation in Hz waste generation and itsdisposal,observed compared to previous consent NO Remarks:

Compliance of existing unit in case applied for expansion C to E/O/R NO

Submission of Annual Return (Form IV) NO Submission Date

Compliance of Non Hazardous/ MSW conditionDetails of Non hazardous/MSW as applied

Sr. no Type of waste Quantity & UOM Treatment Disposal

1 Boiler ash 18 MT/Day -- Sale to brickmanufacture

2 ETP Sludge 1.0 MT/Day -- Used as a manureWhether any deviation in Non-Hz waste generation and itsdisposal,observed compared to previous consent NO Remarks:

Compliance of existing unit in case applied for expansion C to E/O/R NOWaterCess Returns filed upto: Paid Upto: Dec 31 2011

12:00:00:000AMDirectionissued (ifany)

BGDetails Amount Validity

BG obtained towards complience ofa) Consent/CCA condition b) directions

1 NA NA NA NADetails of BGfortified/enchasedfor noncomplience,if any:Submission ofEnvironmentalStatement

NO Year Yes,22/09/2017

Details of consentfee paid Amount Rs: 75000 Terms 1

In case of 1st C to OComplience of C toE conditions

Remarks

Recommendation ofTAC

MPCB-CAC-00

0000

0058

MPCB-CAC-0000000058 (CAC Meeting Number : 8 dated August 6, 2019) Page 70 of 154

Recommendations

Shri. Prashant M Bhosale (SRO-Solapur):-CAC CASE: Visit, process & putup with compliance of consent & Directions.(Feb 26 2019 12:31:26:000PM)

Shri Sandeep Manohar Motegaonkar (FO-Solapur):-Sugar Industry has applied for first consent to operate for expansion by 1000.0 TCD. Industryhas obtained consent to establish on 09/03/17 with C.I of Rs.29.14 Cr. Industry has paid consentfees of Rs.75000/-.Existing unit (2500 TCD Sugar and 18.0 MW cogen) consent is valid upto31/07/19 (C.I 221.189 Cr).Submitted Grampanchayat Bhalwani NOC dated 12/09/18. Industryhas provided primary,Secondary and Tertiary ETP, however ETP is not having adequatetreatment capacity. Not provided CPU unit. Complaints were received from nearby residentabout discharge of effluent in nearby nala. Board has issued proposed direction on 14/12/18(copy enclosed) for not operating ETP, Not operating online monitoring system, not providedCPU.Also interim direction issued by Board on 06/02/19. Industry has got two number of ofbagasse fired Boilers to which provided separate ESP and common Stack of 75.0 mtrs height asan APC. Industry has also got two other boliers of capacity 55.0 TPH and 10.0 TPH providedmechanical dust collector and common stack of 60.0 mtrs height as an APC.JVS sample ofeffluent and air are exceeding the consented standards. CGWA NOC details not submitted. Notsubmitted bank guarantee as per consent conditions dated 04/02/19, same is communicated toindustry. Also reply to scrutiny letter is awaited. In view of above SCN for refusal of consent maybe issued as unit is not complying consent condition.(Mar 26 2019 02:09:20:000PM)

Shri. Prashant M Bhosale (SRO-Solapur):-Remarks of FO may please be seen. The industry has applied for first consent to operate forexpansion of 1000 TCD, Sugarcane crushing capacity. Earlier consent is valid upto comm. of theunit. Existing consent of 2500 TCD Sugar & 18.0 MW Co-gen capacity unit is valid upto31/07/2019. The Board official has visited the industry on 14/11/2018, visit report uploaded.Daily quantity of effluent generation will be DE-36.0 CMD & IE-88.0 CMD. Treatment providedfor DE-septic tank & soak pits & for IE-provided ETP, however not adequate for treatment ofexisting & expansion activity effluent. Existing unit is having 03 no’s of bagasse fired Boilershaving cap 55 TPH & 50 TPH x2 no’s) with Wet scrubber as APC system & 60 mtr height ofstack to 55 TPH cap Boiler. Industry has provided ESP as APC system with common 75 mtrheight of stack to both boilers (50x2 TPH), required steam will be taken from existing boilers.Industry has not provided Condensate Polishing Unit, not provided air cooled condenser systemfor recycling of effluent & minimization fresh water consumption as per consent condition.Industry has not submitted BG of Rs. 10.0 Lakhs against compliance of C to E conditions.Industry has installed continuous online effluent & emission monitoring system & the same isconnected with CPCB & MPCB server, but not operated continuously. Board has issued PD on14/12/2018 for various non compliances & ID on 06/02/2019. Industry has not complied with ID.Industry has not obtained NOC from CGWA for withdraw of ground water for sugar unit. Theanalysis results of JVS of existing unit are uploaded in the MPCB documents. The results areexceeding the consented limits. Industry has paid the requisite consent fees. Industry has notreplied to the scrutiny letter issued by this office. In view of the above non compliance's showcause notice for refusal of consent may be issued, if approved please.(Jun 13 2019 08:21:55:000PM)

Mr.P.K.Mirashe(AST) (CAC-CELL-HQ):-Pl Process and put up(Jun 14 2019 10:29:08:000AM)

Other RelevantInformation

1. Sugar Industry has applied for first consent to operate for expansion by 1000.0 TCD.2. Industry has obtained consent to establish on 09/03/173. Existing unit (2500 TCD Sugar and 18.0 MW cogen) consent is valid upto 31/07/19.4. Industry has provided primary, Secondary and Tertiary ETP, however ETP is not havingadequate treatment capacity.5. Not provided CPU unit.6. Complaints were received from nearby resident about discharge of effluent in nearby nala.Board has issued proposed direction on 14/12/18.for not operating ETP, Not operating onlinemonitoring system, not provided CPU.7. Interim direction issued by Board on 06/02/19 and as per remark of SRO unit is not compliedwith directions issued on 06.12.2019.8. Industry has got two number of of bagasse fired Boilers to which provided separate ESP andcommon Stack of 75.0 mtrs height as an APC. Industry has also got two other boilers of capacity55.0 TPH and 10.0 TPH provided mechanical dust collector and common stack of 60.0 mtrsheight as an APC.JVS sample of effluent and air are exceeding the consented standards.9. CGWA NOC details not submitted.10. Not submitted bank guarantee as per consent conditions dated 04/02/19, also not extendedBG for CPU and consent conditions.

Recommendation ofCAC/CC Cell

We may consider SCN for refusal of consent as unit is not complied with previous consentconditions like- submission of BG, Provision of CPU, JVS of effluent and air are exceeding theconsented standards and not operate ETP properly. Unit not complied with the directions issuedby the Board on 06.12.2019. We may forfeit BG obtain as per Consent condition for installationof CPU

ConsentRecommended forperiod upto as perSectoral Approachpolicy

MPCB-CAC-00

0000

0058

MPCB-CAC-0000000058 (CAC Meeting Number : 8 dated August 6, 2019) Page 71 of 154

ITEM NO: 15 - Unique Number: MPCB-CONSENT-0000067626Fresh CAC ITEMRegion: SRO - Pune I Section: CAC Date:UAN Number: MPCB-CONSENT-0000067626 TAG CAC

Name & Address: SHREENATH MHASKOBA SAKHAR KARKHANA LTD. (DISTILLERY DIVISION) (At.Shreenathnagar, Patethan, Post- Rahu, Tal- Daund, Dist- Pune.)

Location ofIndustrial unit: Gat No. 225-1 & 2 Shreenathnagar, Patethan DAUND

Email: [email protected] Telephone number: 7755992811Industry Type: R60 Distillery ( molasses / grain /yeast based)Industry Category: REDProject Details: Expansion in existing project

Consent Applied For Establish Application Date February22,2019

Date of receipt ofCAC/CC cell

Capital Investment in Rs. (Crs)Existing Proposed Total

68.75 Cr. 1.55 Cr. 70.30 Cr. (CI of Sugar Unit is107.46 Cr.)

Details ofproject :

Expansion inexisting project

Total Plot area(sq.m.)

20 Acres(sq.m)

ConstructionBUA (sq.m.)

3.5 Acres(sq.m)

Product and By-product detailsSr.no Product Name Quantity1 Rectified Spirit Or ENA 0 KL/M2 Ethanol 0 KL/M3 Fusel Oil 0 KL/MSr.no By-Product Name Quantity4 -- 0Applicabilty

ofCRZ

ClearenceDistance

from riverIndustrial

location policy Eco-sensitive Moratonium EC Direction of MoEF forwestern ghats

NO YES NO NO NO NO NO

If Yesprovidedetails

Bhima - 3.00Km

Basedon:

Status:NotApplied

Details of CCA,Consents,Authorization and EC obtained Consent no. Consent

granted date ValidityCapital

Investmentin Crs

Total plotarea

ConstructionBUA

(FSI+Non-FSI)Remarks

C2E

Existing production details

C to OSr.No Product Name Max quantity

1 RS or ENA 900 KL/M

C to ESr.No Product Name Max quantity

1 NA NA

Bio-Medical Waste DetailsAnnual Rpt.(Form-II):Accident Rpt.(Form-III):

BMWGeneration

Sr.No Category Max quantity (Kg/M)

1 NA NA

Disposal @CBMWTF: No

Member ofCBMWTF:

MPCB-CAC-00

0000

0058

MPCB-CAC-0000000058 (CAC Meeting Number : 8 dated August 6, 2019) Page 72 of 154

CaptiveDisposal: No

Incinerator Capacity Fuel Type Auto Feeding Temp.Recorder Online Monitoring

Autoclave Type(Vertical/Horizontal)

Temp &Pressure

Recording

Shredder Plastic WasteDisposal

Compliance of Water Pollution Related Conditions Purpose Water Consumption

in CMD as appliedEffluent generationas applied in CMD

TreatmentSteps

DisposalDetails

Remarks/Adequeteland Available

1 Domestic Purposes 0.5 0.3SepticTank &Soak Pit

On Landfor

GardeningExisting 16 CMD

2Processing wherebywater gets polluted &pollutants are easilybiodegradable

0 0 Primary +Secondary Others Existing 160 CMD

3Processing wherebywater gets polluted &pollutants are noteasily biodegradable

0 0 --NA-- --NA-- 0

4IndustrialCooling,spraying inmine pits or boilerfeed

20.0 5.0 OTHERS Others 0

5Others such asgardening,agricultureetc

0 NA NA NA NA

Whether any deviation in water consumption observed compared toprevious consent NO Remarks:

Compliance to existing unit in case applied for expansion C to E/O/R NOSource of water supply

In case proposed discharge to CETP forfurther treatment

CETP Capacity to handle additional load NOName of CETP

Existing JVS results EffluentSr.no. Date of visit Board official's

name:Whether samplecollected or not:

Whether results areconfirming to standardsor not (Exceedingparameter with value)

1 NO NO

Details of fuel consumption and APC system as applied :-Sr. no Source Stack Fuel type Quantity Height-I,II,III APC system

detail1 BOILER BOILER NO. 1 GAS 700 (Kg/hr.) 32 m NA

2 BOILER BOILER NO.2 Biomassbriquettes 382 (Kg/hr.) 20 m NA

Whether any deviation in fuel consumptionand APC system observed compared toprevious consent

NO Remarks:

Compliance to existing unit in case appliedfor expansion C to E/O/R NO

Existing JVS results AirSr.no. Date of visit Board official's

name:Whether samplecollected or not:

Whether results areconfirming to standardsor not (Exceedingparameter with value)

1 NO NO

Compliance of Haz. Waste ConditionDetails of hazardous waste as applied

Sr. no Type of waste Category Quantity & UOM Treatment Disposal1 NA NA 0 --NA-- NA NA2 NA NA 0 --NA-- NA NA

MPCB-CAC-00

0000

0058

MPCB-CAC-0000000058 (CAC Meeting Number : 8 dated August 6, 2019) Page 73 of 154

Whether any deviation in Hz waste generation and itsdisposal,observed compared to previous consent NO Remarks:

Compliance of existing unit in case applied for expansion C to E/O/R NO

Submission of Annual Return (Form IV) NO Submission Date

Compliance of Non Hazardous/ MSW conditionDetails of Non hazardous/MSW as applied

Sr. no Type of waste Quantity & UOM Treatment Disposal

1 BOILER ASH 700 Kg/Day SALE SALE TO AUTHORIZEDPARTY

Whether any deviation in Non-Hz waste generation and itsdisposal,observed compared to previous consent NO Remarks:

Compliance of existing unit in case applied for expansion C to E/O/R NOWaterCess Returns filed upto: Paid Upto: Jan 1 1900

12:00:00:000AMDirectionissued (ifany)

BGDetails Amount Validity

BG obtained towards complience ofa) Consent/CCA condition b) directions

1 500000 31.12.2019 Consent condition NADetails of BGfortified/enchasedfor noncomplience,if any:Submission ofEnvironmentalStatement

NO Year YES, SEPT 2018

Details of consentfee paid Amount Rs: 15000 Terms 1

In case of 1st C to OComplience of C toE conditions

Remarks

Recommendation ofTAC

MPCB-CAC-00

0000

0058

MPCB-CAC-0000000058 (CAC Meeting Number : 8 dated August 6, 2019) Page 74 of 154

Recommendations

Shri. Nitin R. Shinde (SRO-Pune I):-Pl visit, process and put up.(Feb 28 2019 12:30:31:000PM)

Shri. Sarjerao J. Bhoi (FO-Pune I):-Recently distillery has obtained renewal of CO for mfg. of 1. Rectified Spirit OR ENA - 900 KL/M,Ethanol -900 KL/M & Fusel Oil – 15 KL/M (Molasses based Distillery capacity 30 KLPD). Valid upto 31/8/2019.Now distillery has applied for CE Expansion for installation of new 2 Nos. Gas and briquettefired Boilers cap. Viz 8 TPH & 2 TPH. No change in type of product and its quantity.As per undertaking proposed CI of expansion is Rs.155.0 lacs and accordingly distillery hassubmitted consent fees of Rs.15000/-Distillery propose to install new 2 Nos. Gas and Biomass Briquette fired Boilers cap. Viz 8TPH &2 TPH and 32 mtr height of stack, 20 mtr height of stack will be provided respectively. ProposedBoilers operating only in off season. And generated steam utilized for distillery operations and R& D activity.Existing distillery has provided Bio-digester followed by MEE followed by Bio-composting for thetreatment of spent wash.Existing the distillery has provided as per CREP norms 30 days capacity concertized lagoon and6 acres of land concertized for bio-composting with leachate collection system.Existing distillery has provided online monitoring system as Web Camera and Flow meter andsame is connected with CPCB and MPCB server.In view of above consent to establish expansion may be considered accordingly, if approvedplease.(Mar 25 2019 05:10:55:000PM)

Shri. Nitin R. Shinde (SRO-Pune I):-Pl up load the JVS results of air if any and the resubmit.(Mar 26 2019 02:35:53:000PM)

Shri. Sarjerao J. Bhoi (FO-Pune I):-Latest AAQ monitoring results are not available. Previously distillery steam taken from existingSugar Unit and now distillery applied CE expansion for installation of new 2 Nos. Gas andbriquette fired Boilers cap. Viz 8 TPH & 2 TPH for distillery unit. This is submitted for furtherorder please.(Mar 29 2019 04:05:35:000PM)

Shri. Nitin R. Shinde (SRO-Pune I):-In view of above there is no change in production and water pollution load but modification inboiler and hence fuel which is going towards the clean fuel pattern hence we may consider thecase for amendment in boiler which is going to be used in off season.(Mar 30 2019 11:58:45:000AM)

Mr.P.K.Mirashe(AST) (CAC-CELL-HQ):-Pl process and put up(Apr 1 2019 11:00:01:000AM)

Other RelevantInformation

1. Unit have valid consent to operate for 30 KLPD Molasses base Distillery unit for period up to31.08.2019.2. Unit applied for installation of new 2 Nos. Gas and briquette fired Boilers cap. Viz 8 TPH & 2TPH.3. Proposed Boilers operating only in off season and generated steam utilized for distilleryoperations.4. As per processing report unit complied with CREP conditions.5. SRO recommended for C to E for installation of new Boilers.

Recommendation ofCAC/CC Cell

We may consider consent to Establish for 8 TPH & 2 TPH , Gas and briquette fired Boilers to beoperating during non-crushing g season by imposing following conditions;1. To provide adequate control system ESP/Scrubber for achieving emission conc. Below 50mg/Nm3.2. To amend existing EC for the above changes within 3 month period.3. Industry shall obtain ground water permission from CGWB/Surface water permission fromIrrigation department.4. Industry shall submit/ extend BG of Rs. 5 Lac for compliance of Consent conditions.

ConsentRecommended forperiod upto as perSectoral Approachpolicy

COU

MPCB-CAC-00

0000

0058

MPCB-CAC-0000000058 (CAC Meeting Number : 8 dated August 6, 2019) Page 75 of 154

ITEM NO: 16 - Unique Number: MPCB-CONSENT-0000067927Fresh CAC ITEMRegion: SRO - Pune II Section: CAC Date: 31.07.2019UAN Number: MPCB-CONSENT-0000067927 TAG CACName & Address: COCA-COLA INDIA PRIVATE LIMITED (Plot No 1109-1110 ,Village-Pirangut)Location ofIndustrial unit: PLOT NO.-1109/1110 VILLAGE-PIRANGUT MULSHI

Email: [email protected] Telephone number: 7030106699Industry Type:Industry Category: REDProject Details: Existing project

Consent Applied ForConsent to operate for

new ETP -50 CMD,part [ out of 150 CMD]

Application Date February26,2019

Date of receipt ofCAC/CC cell 07.05.2019

Capital Investment in Rs. (Crs)Existing Proposed Total

Rs.112.85 Crs + Rs. 7.57 Crs Increase in CI Rs. 120. 42 CrsDetails of

project :Existingproject

Total Plot area(sq.m.) 53200 (sq.m) Construction

BUA (sq.m.) 15504 (sq.m)Product and By-product details

Sr.no Product Name Quantity1 Non-Alcoholic Beverages Bases 2100 MT/M2 Lab Operations 4000 No/MSr.no By-Product Name Quantity3 Not Applicable 0Applicabilty

ofCRZ

ClearenceDistance

from riverIndustrial

location policy Eco-sensitive Moratonium EC Direction of MoEF forwestern ghats

NO YES NO NO NO NO NO

If Yesprovidedetails

Mula - 6.00Km

Basedon:

Status:NotApplied

Details of CCA,Consents,Authorization and EC obtained Consent no. Consent

granted date ValidityCapital

Investmentin Crs

Total plotarea

ConstructionBUA

(FSI+Non-FSI)Remarks

C2O BO/CAC-Cell/UANNo.26219/CR/CAC-1801000134 04.01.2018 30.04.2020 Rs.112.85

Crs

Existing production details

C to OSr.No Product Name Max quantity

1 Non-Alcoholic Beverages Bases 2100 MT/M

2 Lab Operations 4000 Nos/M

C to ESr.No Product Name Max quantity

1 NA NA

Bio-Medical Waste DetailsAnnual Rpt.(Form-II): NA

Accident Rpt.(Form-III): NA

BMWGeneration

Sr.No Category Max quantity (Kg/M)

1 NA NA

Disposal @CBMWTF: No

Member ofCBMWTF: NA

CaptiveDisposal: No

MPCB-CAC-00

0000

0058

MPCB-CAC-0000000058 (CAC Meeting Number : 8 dated August 6, 2019) Page 76 of 154

Incinerator Capacity Fuel Type Auto Feeding Temp.Recorder Online Monitoring

NA NA NA

Autoclave Type(Vertical/Horizontal)

Temp &Pressure

Recording

Shredder Plastic WasteDisposal

Compliance of Water Pollution Related Conditions Purpose Water Consumption

in CMD as appliedEffluent generationas applied in CMD

TreatmentSteps

DisposalDetails

Remarks/Adequeteland Available

1 Domestic Purposes 25 20 STP Recycle

We are applying forConsent to operate

for additional(50m3) ETP new

Module withadvance technologyMBR ,followed byRO system against

approved consent toEstablish There is

NO CHANGEenvisaged in waterconsumption and

effluent generation

2Processing wherebywater gets polluted &pollutants are easilybiodegradable

100 90Primary +Secondary+ Tertiary

On Landfor

Gardening

We are applying forConsent to operate

for additional(50m3) ETP new

Module withadvance technology

3Processing wherebywater gets polluted &pollutants are noteasily biodegradable

0 0 --NA-- --NA-- Not Applicable

4IndustrialCooling,spraying inmine pits or boilerfeed

10 0 --NA-- --NA--

We are applying forConsent to operate

for additional(50m3) ETP new

Module withadvance technology

5Others such asgardening,agricultureetc

Not Applicable NA NA NA NA

Whether any deviation in water consumption observed compared toprevious consent NO Remarks:

Compliance to existing unit in case applied for expansion C to E/O/R NOSource of water supply

In case proposed discharge to CETP forfurther treatment

CETP Capacity to handle additional load NOName of CETP

Existing JVS results EffluentSr.no. Date of visit Board official's

name:Whether samplecollected or not:

Whether results areconfirming to standardsor not (Exceedingparameter with value)

1 19.12.2017 YES YES

1 21.11.2018 YESNOBOD-45 against 30 andCOD-120 against 100

1 15.12.2018 YES YES

Details of fuel consumption and APC system as applied :-Sr. no Source Stack Fuel type Quantity Height-I,II,III APC system

detail

1Boiler(Nochange inexisting boiler)

1 LDO 52.2 (Kg/hr.) 30 m Not Applicable

2Diesel generatorsets(No changein existing DGSets)

3 HSD 170.56 (Kg/hr.) 16 m Not Applicable

MPCB-CAC-00

0000

0058

MPCB-CAC-0000000058 (CAC Meeting Number : 8 dated August 6, 2019) Page 77 of 154

Whether any deviation in fuel consumptionand APC system observed compared toprevious consent

NO Remarks:

Compliance to existing unit in case appliedfor expansion C to E/O/R NO

Existing JVS results AirSr.no. Date of visit Board official's

name:Whether samplecollected or not:

Whether results areconfirming to standardsor not (Exceedingparameter with value)

1 not enclosed NO NO

Compliance of Haz. Waste ConditionDetails of hazardous waste as applied

Sr. no Type of waste Category Quantity & UOM Treatment Disposal

1 5.1 Used /spent oil 5.1600 Lt/A (There is NOCHANGE envisaged inexisting consentquantity.) Ltr/A

NADisposal toauthorizedCHWTSDF Site

2 5.2 Wastes/residuecontaining oil 5.2

30 Kg/A (Waste residuecontaining oil,There isNO CHANGE envisagedin existing consentquantity.) Kg/Annum

NADisposal toauthorizedCHWTSDF Site

334.3 Chemicalsludge from wastewater treatment

34.3

ETP sludge - 10MT/A,(There is NOCHANGE envisaged inexisting consentquantity) MT/A

NADisposal toauthorizedCHWTSDF Site

433.3 Discardedcontainers / barrels/ liner

33.320 Nos/A,There is NOCHANGE envisaged inexisting consentquantity.) Nos./Y

NADisposal toauthorizedCHWTSDF Site

5 21.1 Wastes andresidue 21.1

15 Nos/Y (Waste andresidue,There is NOCHANGE envisaged inexisting consentquantity.) Nos./Y

NADisposal toauthorizedCHWTSDF Site

6 5.2 Wastes/residuecontaining oil 5.2

10 Nos /A (There is NOCHANGE envisaged inexisting consentquantity.) Nos./Y

NADisposal toauthorizedCHWTSDF Site

720.1 Contaminatedaromatic, aliphaticor napthenic solvent

20.130 Litr/M (There is NOCHANGE envisaged inexisting consentquantity.) Ltr/M

NADisposal toauthorizedCHWTSDF Site

8 Other HazardousWaste Other

30 Kg/M (Microbiologicalwaste,There is NOCHANGE envisaged inexisting consentquantity.) Kg/M

NADisposal toauthorizedCHWTSDF Site

9 NA NA 0 --NA-- NA NAWhether any deviation in Hz waste generation and itsdisposal,observed compared to previous consent NO Remarks:

Compliance of existing unit in case applied for expansion C to E/O/R NO

Submission of Annual Return (Form IV) NO Submission Date

Compliance of Non Hazardous/ MSW conditionDetails of Non hazardous/MSW as applied

Sr. no Type of waste Quantity & UOM Treatment Disposal1 Wooden Material 105 Ton/Y Not Applicable Sale2 Plastic Material 15 Ton/Y Not Applicable Sale3 paper 30 Ton/Y Not Applicable Sale4 MS Scrap 75 Ton/Y Not Applicable Sale5 Glass 0.3 Ton/Y Not Applicable Sale6 Aluminium 1.5 Ton/Y Not Applicable SaleWhether any deviation in Non-Hz waste generation and itsdisposal,observed compared to previous consent NO Remarks:

MPCB-CAC-00

0000

0058

MPCB-CAC-0000000058 (CAC Meeting Number : 8 dated August 6, 2019) Page 78 of 154

Compliance of existing unit in case applied for expansion C to E/O/R NOWaterCess Returns filed upto: Paid Upto: Aug 31 2016

12:00:00:000AMDirectionissued (ifany)

BGDetails Amount Validity

BG obtained towards complience ofa) Consent/CCA condition b) directions

1 Rs.5.0 Lakhs 31.08.2020Towards operation andmaintenance of pollution controlsystems

NA

2 Rs.5.0 Lakhs Towards compliance's of consentto operate conditions. NA

Details of BGfortified/enchasedfor noncomplience,if any:Submission ofEnvironmentalStatement

NO Year Yes, 27-09-2018

Details of consentfee paid Amount Rs: 25000 Terms 1

In case of 1st C to OComplience of C toE conditions

Remarks

Recommendation ofTAC

MPCB-CAC-00

0000

0058

MPCB-CAC-0000000058 (CAC Meeting Number : 8 dated August 6, 2019) Page 79 of 154

Recommendations

Shri. Upendra C. Kulkarni (SRO-Pune II):-Process & put up with report.(Mar 1 2019 12:27:20:000PM)

Shri. Sameer S. Vastre (FO-Pune II):-1) Industry has applied for 1st consent to operate (Part) for expansion.2) Industry has obtained consent to operate dated 4/1/2018 for manufacturing of Non-Alcoholicbeverages bases:2100 MT/M; Lab Operations:4000 Nos/M and said consent is valid upto30.04.2020.3) Previously industry has applied for consent to establish for installation of New ETP planthaving capa:150CMD & said consent to establish was approved in 5th CAC meeting dated27.9.2017 .(Minutes copy enclosed)4) Now industry has applied for 1st consent to operate(part) for new ETP operation only for50CMD (out of total ETP capacity:150CMD ) with advanced MBR followed by ROsystem(capacity:50m3/day)5) During visit following observations were made:-A) Industry is found in operation for manufacturing of Non-Alcoholic beverages bases howeverlab operations activity is not found in operation since Jan-2018.B) Industry has installed new ETP of capacity:150CMD near security Gate-2 and civil work fornew ETP (capacity:150CMD) is completed. The 50 CMD module of ETP out of 150CMD ETP isready for commissioning and remaining 100CMD ETP module is under installation ofinstrumentation /equipment is in progress. Industry has installed RO system ofcapacity:50m3/day.C) New ETP consists of collection tank, homogenization tank,denitrification tank,aerationtank,MBR tank, Part from MBR tank to RO Plant and remaining is sending to Ozonization systemthen to treated water tank for gardening purpose.The RO permeate is used to utility & RO reject will be sending to treated water tank(Overheadtank) for gardening purpose.D) Treated water used on land for gardening having total area about:4.69Acrs.E) Existing unit has generates trade effluent to the tune of 90CMD and treatment for sameprovided ETP(existing) consists of collection sump, equalization tank, neutralization tank,aeration tank, settling tank, clarifloculator, filter feed tank, duel media filter,Ozonization tank,treated water tank,Sludge drying beds(2Nos).ETP was found in operation. One emergency tankwas found observed with trade effluent storage about :25CMD in ETP area.F) Industry has provided STP of capacity 20CMD consists of collection sump,screening,inlettank,FAB reactor,Filter feed tank,sand and carbon filter,treated water tank.The said treatedwater used for flushing purpose.G) Industry has provided one boiler (850Kg/hr)and fuel used as LDO and provided stack ofheight about:30 mtrs.H) Industry has uses water from Bore well(3Nos) located in premises and obtained permissionfrom CGWA is valid upto 6/6/2019.J) DG set of capacity:(500KVA)- 2 Nos with acoustically enclosed and provided stack about:16mtrs to each. Another DG Set of capacity 250KVA with acoustically enclosed and provided stackabout:5 mtrs above roof.K) BG of Rs:5.0 Lacs towards O&M of PCS and is submitted and BG of Rs:5.0 Lacs towardscompliance of consent to operate conditions is submitted and both are valid upto 18.1.2020L) The last disposal of HW i.e.(34.3) ETP sludge is :3.570 MT on 19/3/2019 to CHWTSDF, MEPL,Ranjangaon. However remaining H.W. disposal (last) was not produced.6) JVS results are enclosed.( JVS result of ETP outlet for parameter pH, BOD and COD ismarginally exceeded)7) Industry informed that after grant of this consent they are going to utilizes 50CMD capacity ofNew ETP module along with 100CMD of existing ETP capacity as per submitted letter dated10.4.2019(uploaded) .8) The existing capital investment of Rs:112.85Crs as per consent dated 4.1.2018 and nowsubmitted CA certificate of Rs:128.69Crs and paid consent fees of Rs:25000/- dated 1.3.2019.(CIis increased by15.84Crs) hence this office has given link for additional consent fees ofRs:25000/- and same is not submitted.In view of above consent to operate (part) for new ETP operation(only 50CMD out of 150CMD)may be granted subject to submission of additional consent fees.(Apr 12 2019 12:07:40:000PM)

Shri. Upendra C. Kulkarni (SRO-Pune II):-1. Application is received for to obtained consent to operate for new ETP installed for 50 CMDout of 150 CMD capcity. . 2. Board has issued consent to establish to the applicant for new ETPwhich is approved in 5th CAC meeting dated 27.9.2017 Copy uploaded. 3. Industry has installednew ETP with advance technology MBR with RO syatem. 4. The MBR units are three in seriesand industry will operate only one having 50 CMD capacity which is ready, however RO ishaving capacity 150 CMD. 4. The part treated effluent from MBR will be used for gardeningdirectly and the part will be passed through RO and same will be used for utility. The RO rejectwill be mixed with MBR treated effluent to used for gardening. 5.Industry will treat the 40 CMDeffluent in existing ETP (Conventional technology) and rest will be in advanced technology. 6.Board has granted consent to the unit which is valid till 30.4.2020 for manufacturing of Non-Alcoholic beverages bases 2100 MT/M; Lab Operations:4000 Nos/M and there will not be anychanges. 7. Though the industry has installed 150 CMD plant, trade effluent generation is 90CMD and which will be remain same. 8. Technical specification of new ETP is needs to uploaded9. Due to advanced treatment capital investment increased by 7. 57 Cr. 10. We may consider thecase after receipt of technical specification from the industry.(May 7 2019 10:35:25:000AM)

Mr.P.K.Mirashe(AST) (CAC-CELL-HQ):-Pl Process and put up(May 7 2019 10:44:42:000AM)

MPCB-CAC-00

0000

0058

MPCB-CAC-0000000058 (CAC Meeting Number : 8 dated August 6, 2019) Page 80 of 154

Other RelevantInformation

1] PP has applied for 1st consent to operate for operation of new installed ETP of capacity 50CMD [ out of 150 CMD ].

2] PP has obtained consent to operate for existing products which is valid up to 30.04.2020.

3]Board has approved consent to Establish for installation of ETP in CAC meeting 27.09.2017.

4] Now PP has applied for 1st consent to operate for new ETP of capacity 50 CMD [ out of 150CMD total capacity] with advanced MBR followed by RO System .

5] PP has completed civil work for 150 CMD is completed and out of 150 CMD out of 50CMDETP module is fully ready to operate and remaining 100 CMD ETP module installation ofinstrumentation and equipments is in process. The new ETP consisting of collection tank,homogeneous tank, de-nitrification tank,aeration tank,MBR tank, MBR tank to feed to RO systemand remaining is going to ozonization system then after ozonization goes to over head tank forgardening purpose. The RO permite will be used in to utility and RO reject will be fed tooverhead treated tank for gardening purpose.

6] The total effluent generation is 90 CMD remaining 40 CMD effluent will be treated in existingETP, which consisting primary, secondary and tertiary treatment system.

7] PP has provided STP of 20 CMD capacity -FAB system.treated effluent is used for flushingpurpose.

8] PP has provided flow meter to inlet and outlet of ETP.

9]stack provided to LDO fired boiler of capacity -850 kg/hrs.

10] PP has obtained NOC of CGWA on 16.06.2017 which was valid up to 06.06.2019.Nowapplied for renewal for the same.

11]Submitted BG's as per consent conditions.

Recommendation ofCAC/CC Cell

We may grant 1st consent to operate for the period up to 30.04.2020 for operation of 50 CMDnew ETP by imposing condition of BG towards operation and maintenance of new ETP to achieveconsented standards.

ConsentRecommended forperiod upto as perSectoral Approachpolicy

30.04.2020.

MPCB-CAC-00

0000

0058

MPCB-CAC-0000000058 (CAC Meeting Number : 8 dated August 6, 2019) Page 81 of 154

ITEM NO: 17 - Unique Number: MPCB-CONSENT-0000066005Fresh CAC ITEMRegion: SRO - Raigad II Section: CAC Date: 16/07/2019UAN Number: MPCB-CONSENT-0000066005 TAG CAC

Name & Address: DRT-Anthea Aroma Chemicals Pvt. Ltd. (51-A/1 Roth Budrukh, Dhatav MIDC , Tal- Roha , Dist -Raigad Maharashtra India)

Location ofIndustrial unit: Plot No. 51A/1 Roth Budruk Roha

Email: [email protected] Telephone number: 7774098908Industry Type: R22 Organic Chemicals manufacturingIndustry Category: REDProject Details: Existing project

Consent Applied For Renewal of Consent toOperate Application Date January

29,2019Date of receipt ofCAC/CC cell 01/04/2019

Capital Investment in Rs. (Crs)Existing Proposed Total

92.61 61.58 154.1941Details of

project :Existingproject

Total Plot area(sq.m.) 26505 (sq.m) Construction

BUA (sq.m.) 18034 (sq.m)Product and By-product details

Sr.no Product Name Quantity1 Anthamber 300 MT/M2 Dihydromyrcenol 200 MT/M3 Methyl Pentenone 200 MT/MSr.no By-Product Name Quantity4 Ammonium Sulphate ((NH4)2SO4) Soln 600 KL/M5 High Boiler 170 MT/MApplicabilty

ofCRZ

ClearenceDistance

from riverIndustrial

location policy Eco-sensitive Moratonium EC Direction of MoEF forwestern ghats

NO YES NO NO NO NO NO

If Yesprovidedetails

Kundalika -0.95 Km

Basedon:

Status:Obtained

Details of CCA,Consents,Authorization and EC obtained Consent no. Consent

granted date ValidityCapital

Investment in Crs

Total plotarea

ConstructionBUA

(FSI+Non-FSI)Remarks

EC EC-2008/11/CR.1 30/01/2010 40

C2R

Format1.0/BO/CAC-Cell/EIC No.

RD-2939-14/27thCAC-4543

21/04/2015 28/02/2019 92.61

C2E

Existing production details

C to O

Sr.No Product Name Max quantity

1 Anthamber 300 MT/M

2 Dihydromyrcenol 200 MT/M

3 Methyl Pentenone 200 MT/M

4 By-products NA

5 Ammonium Sulphate ((NH4)2SO4) Soln 600 KL/M

6 High Boiler 170 MT/M

C to ESr.No Product Name Max quantity

1 NA NA

Bio-Medical Waste DetailsAnnual Rpt.(Form-II):

MPCB-CAC-00

0000

0058

MPCB-CAC-0000000058 (CAC Meeting Number : 8 dated August 6, 2019) Page 82 of 154

Accident Rpt.(Form-III):

BMWGeneration

Sr.No Category Max quantity (Kg/M)

1 NA NA

Disposal @CBMWTF: NA

Member ofCBMWTF:CaptiveDisposal: NA

Incinerator Capacity Fuel Type Auto Feeding Temp.Recorder Online Monitoring

Autoclave Type(Vertical/Horizontal)

Temp &Pressure

Recording

Shredder Plastic WasteDisposal

Compliance of Water Pollution Related Conditions Purpose Water Consumption

in CMD as appliedEffluent generationas applied in CMD

TreatmentSteps

DisposalDetails

Remarks/Adequeteland Available

1 Domestic Purposes 20 18SepticTank &Soak Pit

CETP NA

2Processing wherebywater gets polluted &pollutants are easilybiodegradable

60 60Primary +Secondary+ Tertiary

CETP NA

3Processing wherebywater gets polluted &pollutants are noteasily biodegradable

0 0 --NA-- --NA-- NA

4IndustrialCooling,spraying inmine pits or boilerfeed

250 0 --NA-- --NA-- NA

5Others such asgardening,agricultureetc

20 NA NA NA NA

Whether any deviation in water consumption observed compared toprevious consent NO Remarks:

Compliance to existing unit in case applied for expansion C to E/O/R NOSource of water supply

In case proposed discharge to CETP forfurther treatment

CETP Capacity to handle additional load YES

Name of CETP RIA CETP Co-opSociety Ltd

Existing JVS results EffluentSr.no. Date of visit Board official's

name:Whether samplecollected or not:

Whether results areconfirming to standardsor not (Exceedingparameter with value)

1 NO NO

Details of fuel consumption and APC system as applied :-Sr. no Source Stack Fuel type Quantity Height-I,II,III APC system

detail1 Steam Boiler 1 Furnace Oil 0 (Kg/hr.) 46 m -

2 Thermic FluidHeater 1 Furnace Oil 0 (Kg/hr.) 46 m -

3 DG 1 Diesel 0 (Kg/hr.) 28 m -Whether any deviation in fuel consumptionand APC system observed compared toprevious consent

NO Remarks:

Compliance to existing unit in case appliedfor expansion C to E/O/R NO

Existing JVS results Air

MPCB-CAC-00

0000

0058

MPCB-CAC-0000000058 (CAC Meeting Number : 8 dated August 6, 2019) Page 83 of 154

Sr.no. Date of visit Board official'sname:

Whether samplecollected or not:

Whether results areconfirming to standardsor not (Exceedingparameter with value)

1 NO NO

Compliance of Haz. Waste ConditionDetails of hazardous waste as applied

Sr. no Type of waste Category Quantity & UOM Treatment Disposal1 5.1 Used or spent oil 5.1 50 Kg/M Drums CHWTSDF

235.3 Chemical sludgefrom waste watertreatment

35.3 8 MT/M Bags CHWTSDG

3 NA NA 0 --NA-- NA NAWhether any deviation in Hz waste generation and itsdisposal,observed compared to previous consent NO Remarks:

Compliance of existing unit in case applied for expansion C to E/O/R NO

Submission of Annual Return (Form IV) NO Submission Date

Compliance of Non Hazardous/ MSW conditionDetails of Non hazardous/MSW as applied

Sr. no Type of waste Quantity & UOM Treatment Disposal1 NA 0 --NA-- NA NAWhether any deviation in Non-Hz waste generation and itsdisposal,observed compared to previous consent NO Remarks:

Compliance of existing unit in case applied for expansion C to E/O/R NOWaterCess Returns filed upto: Paid Upto: Jan 1 1900

12:00:00:000AMDirectionissued (ifany)

BGDetails Amount Validity

BG obtained towards complience ofa) Consent/CCA condition b) directions

1 Rs. 5 Lakh 30/06/2019 O&M of PCS NA

2 Rs. 2 Lakh 30/11/2015Performance evaluation of ETPfrom renowned Institute by31/07/2015

NA

3 Rs. 2 Lakh 30/06/2019 GPS System for by-productcarrying vehicle NA

Details of BGfortified/enchasedfor noncomplience,if any:Submission ofEnvironmentalStatement

NO Year 27-9-2018

Details of consentfee paid Amount Rs: 16,41,940/- Terms 1

In case of 1st C to OComplience of C toE conditions

Remarks

Recommendation ofTAC

MPCB-CAC-00

0000

0058

MPCB-CAC-0000000058 (CAC Meeting Number : 8 dated August 6, 2019) Page 84 of 154

Recommendations

S. L. Waghmare (SRO-Raigad II):-Process and put up(Mar 2 2019 04:22:08:000PM)

Shri. Bajirao Malvekar (FO-Raigad II):-1. The previous consent is valid up to 28/02/2019, now applied for renewal of consent.2. The unit is engaged in manufacturing of perfumery chemicals & intermediates such asAnthamber – 300 MT/M, Dihydromyrcenol – 200 MT/M, Methyl pentenone – 200 MT/M & alliedby products such as high boiler – 170 MT/M, Ammonium Sulphate – 600 KL/M.3. The basic raw material of this unit is Methyl Ethyl Ketone, Acetaldehyde, Beta Pinene,Myrcene, Dihydromyrcene, Toluene, Methyl Pentenone, Caustic Soda Lye (50% solution),Sulphuric Acid, etc., detail list of raw material is enlisted in application.4. The generation of trade effluent is 60 CMD which will be treated by ETP comprising primarytreatment followed by MEE, secondary treatment followed by RO plant. The JVS of air & water isnot available due to the fire incidence was occurred on 19/02/2018, since Feb 2018, the unit isnot in operation due to revamping process of existing manufacturing section. The unit hasupgraded the existing effluent treatment system by way of provision of MEE & RO Plant, thework of it is completed. The performance of this effluent treatment facility may be evaluatedafter commissioning of the same & after analysis results of JVS of treated effluent.5. The fire incidence was occurred on 19/02/2018, the entire manufacturing plant was damagedexcept myrecene intermediate manufacturing section & utility section. Accordingly the Boardoffice has issued the direction not to start the manufacturing activity vide dtd. 23/02/2018, sincefrom, this unit is not in operation. To resume the manufacturing activity the unit has submittedthe compliance report to this office on 29/03/19, it is under process.6. The unit is visited on 26/03/2019, during visit it is observed that the unit has completed thework in all respect of Plant No. 05 for manufacturing of dihydromyrcenol, the work of other 4Nos of plants for manufacturing of Anthamber & Methyl Pentenone is found in progress which islikely to be completed up to the end of May 2019.7. The unit has provided 3 Nos of oil fired boilers (2w+1s) & 3 Nos of oile fired thermic fluidheaters (2w+1s); however the Board office has granted the C to O for 2 Nos of Boilers & 2 Nosof thermic fluid heaters.8. The unit has obtained the EC from Environment Department, Govt. of Maharashtra vide letterdtd. 30.01.2010 for manufacturing of perfumery chemicals & intermediates.9. As compared to earlier consent & submitted CA certificate the unit has increased the CI byRs. 61.58 Crs; accordingly the unit has to submit the additional consent fees of Rs. 100000/-.10. This office has issued query letter for submission of compliance report as per EC granted,submission of proper water budget, techno-feasibility report of ETP (existing + upgraded),annual submissions, details of gaseous emissions, if any, compliance report as per directionissued dtd. 23.02.2019 & justification in respect of additional CI, etc., however the unit has notsubmitted the compliance report, till date.11. The unit has submitted the consent fees of Rs. 308388/- through online for the period up to28/02/2020; however as per Boards circular issued dtd. 19/03/2019 in respect of grant ofconsent, the unit has to pay additional consent fees of Rs. 1233552/- for grant of consent for theperiod up to 28/02/2024.By considering the above it is submitted that the renewal of consent may be considered aftersubmission of compliance report to this office query letter & requisite additional consent fees, ifapproved.(Apr 1 2019 02:05:42:000PM)

S. L. Waghmare (SRO-Raigad II):-Remarks of FO may please be seen. This is existing unit, due to fire incidence on 19/02/2018 unitwas not in operation since then. The unit is having total five manufacturing plants which weredamaged due to fire. Now they re-built all these plants & they intended to restart the plant no. 5of product Dihydromyrcenol & remaining manufacturing plants will be commissioned by end ofMay 2019. The unit has provided ETP (primary & secondary) followed by RO & MEE, the detailsare yet to be submitted. This office has issued a letter about this, reply is awaited. In view ofabove renewal of consent may be considered after receipt of reply from industry & additionalconsent fees. Submitted please.(Apr 1 2019 02:06:52:000PM)

Mr.P.K.Mirashe(AST) (CAC-CELL-HQ):-Pl Process and put up(Apr 2 2019 11:28:29:000AM)MPCB-C

AC-0000

0000

58

MPCB-CAC-0000000058 (CAC Meeting Number : 8 dated August 6, 2019) Page 85 of 154

Other RelevantInformation

1. Existing Red/LSI industry engaged in mfg. of perfumery chemicals & intermediates such asAnthamber – 300 MT/M, Dihydromyrcenol – 200 MT/M, Methyl pentenone – 200 MT/M & alliedby products such as high boiler – 170 MT/M, Ammonium Sulphate – 600 KL/M.

2. Obtained C2O which was valid up to 28/02/2019.

3. Industry is not in operation due to fire incidence occurred on 19/02/2018. Capital investmentincreased from Rs. 92.61 Crs to Rs. 154.91 Crs due to revamping process of existingmanufacturing section. The unit has also upgraded the existing effluent treatment system byway of provision of RO & MEE Plant, the work of it is completed.

The performance of this effluent treatment facility may be evaluated after commissioning of thesame & after analysis results of JVS of treated effluent.

4. The fire incidence was occurred on 19/02/2018, the entire manufacturing plant was damagedexcept myrecene intermediate manufacturing section & utility section. Accordingly, the Boardoffice has issued the direction not to start the manufacturing activity vide letter dtd. 23/02/2018.To resume the manufacturing activity the unit has submitted the compliance report to this officeon 29/03/19, which is under process.

5. The unit was visited on 26/03/2019, during visit it was observed that the unit has completedthe work in all respect of Plant No. 05 for manufacturing of Dihydromyrcenol, the work of other4 Nos. of plants for manufacturing of Anthamber & Methyl Pentenone is found in progress whichis likely to be completed up to the end of May 2019.

6. Now, industry has applied for grant of renewal of Consent to Operate.

7. From the Environment Audit Report 2017-2018, it is observed that industry has violated EC &Consent conditions by mfg. excess Dihydromyrcenol - 2,633 MT/A in place of 2,400 MT/A andHigh Boiler - 2,945.19 MT/A in place of 2,040 MT/A.

8. Board has granted conditional directions to restart mfg. activities on 20/05/2019.

9. Industry vide letter dtd. 19/06/2019 has submitted compliance of the conditional restartdirections.

Recommendation ofCAC/CC Cell

-Applied for grant of renewal of Consent to Operate for mfg. of perfumery chemicals &intermediates such as Anthamber – 300 MT/M, Dihydromyrcenol – 200 MT/M, Methyl pentenone– 200 MT/M & allied by products such as high boiler – 170 MT/M, Ammonium Sulphate – 600KL/M.

-Due to fire incidence on 19/02/2018 unit was not in operation since then. Board has issued thedirection for not to start the manufacturing activity vide letter dtd. 23/02/2018.

-Now, industry has re-built all these plants & intended to restart the plant no. 5 for mfg. productDihydromyrcenol & remaining manufacturing plants will be ready for commission by end of May2019.

-Industry has violated EC & Consent conditions by mfg. excess Dihydromyrcenol - 2,633 MT/A inplace of 2,400 MT/A and High Boiler - 2,945.19 MT/A in place of 2,040 MT/A in year 2017-2018.

-Board has granted conditional directions to restart mfg. activities on 20/05/2019 by imposingthe condition of operation of the ETP round the clock to achieve Consented standards, operationof RO followed by MEE, compliance of Consent conditions and submission of BG of Rs. 2 Lakh.

-Industry vide letter dtd. 19/06/2019 has submitted compliance of the conditional restartdirections i.e. submission of BG of Rs. 2 Lakh and assurance towards operation of ETP, RO &MEE.

In view of above, we may consider the case and grant Consent to Operate for mfg. productDihydromyrcenol by imposing the following conditions:1. Industry shall comply with the conditions of the conditional directions to restart mfg. activitieson 20/05/2019.2. Industry shall comply with the conditions of the EC.3. Industry shall O&M ETP to achieve ZLD.4. Industry shall extend all existing BGs towards compliance of the Consent conditions.5. BG of Rs. 5 Lakh is forfeited towards violation of Consent conditions by mfg. excessDihydromyrcenol - 2,633 MT/A in place of 2,400 MT/A and High Boiler - 2,945.19 MT/A in placeof 2,040 MT/A in year 2017-2018 and top-up with double amount i.e. Rs. 10 Lakh towardscompliance of the Consent conditions and O&M of pollution control systems.

ConsentRecommended forperiod upto as perSectoral Approachpolicy

For short period up to 31/02/2020.

MPCB-CAC-00

0000

0058

MPCB-CAC-0000000058 (CAC Meeting Number : 8 dated August 6, 2019) Page 86 of 154

ITEM NO: 18 - Unique Number: MPCB-CONSENT-0000067939Fresh CAC ITEMRegion: SRO - Pune I Section: CAC Date: 29/03/2019UAN Number: MPCB-CONSENT-0000067939 TAG CACName & Address: Clean Science and Technology Pvt.Ltd (Office No.503, Pentagon P4, 5th Floor, Magarpatta City)Location ofIndustrial unit: Plot No.D-26/3 Plot No.D-26/3,MIDC,Kurkumbh Daund

Email: [email protected] Telephone number: 9552587913Industry Type: R22 Organic Chemicals manufacturingIndustry Category: REDProject Details: Existing project

Consent Applied ForAmendment in

Consent to Operate forchange in product-mix

Application Date February27,2019

Date of receipt ofCAC/CC cell 27/03/2019

Capital Investment in Rs. (Crs)Existing Proposed Total

74 4.75 78.75Details of

project :Existingproject

Total Plot area(sq.m.) 19193 (sq.m) Construction

BUA (sq.m.)10964.09(sq.m)

Product and By-product detailsSr.no Product Name Quantity1 Hydroquinone,Catechol and their Derivatives 5000 MT/A2 Butylated Hydroxy Anisole (BHA) 0 MT/A3 Vanilline and their Derivatives 1300 MT/A4 Anisole and their Derivatives 9000 MT/A5 1.Dicyclohyxylcarb odiimide(DCC) 1200 MT/A6 Ascorbyl Palmitate 300 MT/ASr.no By-Product Name Quantity7 o-cresol Mix 450 MT/A8 Sodium Sulphate 3891 MT/A9 Ammonium Salt Mixture 2940 MT/A10 Hydrochloric Acid 42 MT/AApplicabilty

ofCRZ

ClearenceDistance

from riverIndustrial

location policy Eco-sensitive Moratonium EC Direction of MoEF forwestern ghats

NO YES NO NO NO YES NO

If Yesprovidedetails

Bhima - 11.00Km

Based on:

Status:Obtained (EC Ref. No. -SEIAA-EC-0000000174)

Details of CCA,Consents,Authorization and EC obtained Consent no. Consent

granted date ValidityCapital

Investmentin Crs

Total plotarea

ConstructionBUA

(FSI+Non-FSI)Remarks

EC SEIAA-EC-0000000174 16/02/2018 16/02/2025 70

C2O Format 1.0/BO/AST/UAN No.0000057290/O/CC-1901002062 28/01/2019 31/03/2021 74

Existing production details

C to O

Sr.No Product Name Max quantity

1 Hydroquinone,Catechol and their Derivatives 9,999.96 MT/A

2 Butylated Hydroxy Anisole (BHA) 2,400 MT/A

3 Vanilline and their Derivatives 3,000 MT/A

4 Anisole and their Derivatives 9,000 MT/A

C to ESr.No Product Name Max quantity

1 NA NA

Bio-Medical Waste DetailsAnnual Rpt.(Form-II):

MPCB-CAC-00

0000

0058

MPCB-CAC-0000000058 (CAC Meeting Number : 8 dated August 6, 2019) Page 87 of 154

Accident Rpt.(Form-III):

BMWGeneration

Sr.No Category Max quantity (Kg/M)

1 NA NA

Disposal @CBMWTF: NA

Member ofCBMWTF:CaptiveDisposal: NA

Incinerator Capacity Fuel Type Auto Feeding Temp.Recorder Online Monitoring

Autoclave Type(Vertical/Horizontal)

Temp &Pressure

Recording

Shredder Plastic WasteDisposal

Compliance of Water Pollution Related Conditions Purpose Water Consumption

in CMD as appliedEffluent generationas applied in CMD

TreatmentSteps

DisposalDetails

Remarks/Adequeteland Available

1 Domestic Purposes 20 16SepticTank &Soak Pit

On Landfor

GardeningNA

2Processing wherebywater gets polluted &pollutants are easilybiodegradable

99 98Primary +Secondary+ Tertiary

Recycle Zero LiquidDischarge

3Processing wherebywater gets polluted &pollutants are noteasily biodegradable

0 0 --NA-- --NA-- NA

4IndustrialCooling,spraying inmine pits or boilerfeed

400 57Primary +Secondary+ Tertiary

Recycle Zero LiquidDischarge

5Others such asgardening,agricultureetc

Gardening - 20 CMD NA NA NA NA

Whether any deviation in water consumption observed compared toprevious consent NO Remarks:

Compliance to existing unit in case applied for expansion C to E/O/R NOSource of water supply

In case proposed discharge to CETP forfurther treatment

CETP Capacity to handle additional load NOName of CETP

Existing JVS results EffluentSr.no. Date of visit Board official's

name:Whether samplecollected or not:

Whether results areconfirming to standardsor not (Exceedingparameter with value)

1 NO NO

Details of fuel consumption and APC system as applied :-Sr. no Source Stack Fuel type Quantity Height-I,II,III APC system

detail

1 DG Set 5 HSD 300 (Kg/hr.) 5.5 m AcousticEnclosure

2 Boiler 1 Coal/Brickets 666.67 (Kg/hr.) 30 mMultiCyclone/DustCollector

3 Boiler 2 Coal/Brickets 1666.67 (Kg/hr.) 30.0 mMultiCyclone/DustCollector

4 DG Set 6 HSD 140 (Kg/hr.) 5.5 m AcousticEnclosure

5 Thermopack 3 Coal 234 (Kg/hr.) 30 common mSingleCyclone/DustCollector

MPCB-CAC-00

0000

0058

MPCB-CAC-0000000058 (CAC Meeting Number : 8 dated August 6, 2019) Page 88 of 154

6 Thermopack 4 Coal 291 (Kg/hr.) 30 common mSingleCyclone/DustCollector

7 DG Set 5 HSD 300 (Kg/hr.) 5.5 m AcousticEnclosure

8 DG Set 6 HSD 140 (Kg/hr.) 5.5 m AcousticEnclosure

Whether any deviation in fuel consumptionand APC system observed compared toprevious consent

NO Remarks:

Compliance to existing unit in case appliedfor expansion C to E/O/R NO

Existing JVS results AirSr.no. Date of visit Board official's

name:Whether samplecollected or not:

Whether results areconfirming to standardsor not (Exceedingparameter with value)

1 NO NO

Compliance of Haz. Waste ConditionDetails of hazardous waste as applied

Sr. no Type of waste Category Quantity & UOM Treatment Disposal

1 20.3 Distillationresidue 20.3 2.81(Proposed) MT/M NA CHWTSDF

2 20.3 Distillationresidue 20.3 2.81(Proposed) MT/M NA CHWTSDF

333.3 Discardedcontainers / barrels /liner

33.3 200 (As per ExistingConsent) No/M NA

Sale to AuthorizedParty OR Return tovendor

433.3 Discardedcontainers / barrels /liner

33.3 200 (As per ExistingConsent) No/M NA

Sale to AuthorizedParty OR Return tovendor

534.3 Chemical sludgefrom waste watertreatment

34.3 5 (As per ExistingConsent) MT/Day NA CHWTSDF

634.3 Chemical sludgefrom waste watertreatment

34.3 5 (As per ExistingConsent) MT/Day NA CHWTSDF

7 Other HazardousWaste Other 4 (As per Existing

Consent) MT/M NA CHWTSDF

8 Other HazardousWaste Other 4 (As per Existing

Consent) MT/M NA CHWTSDF

9 NA NA 0 --NA-- NA NA10 NA NA 0 --NA-- NA NAWhether any deviation in Hz waste generation and itsdisposal,observed compared to previous consent NO Remarks:

Compliance of existing unit in case applied for expansion C to E/O/R NO

Submission of Annual Return (Form IV) NO Submission Date

Compliance of Non Hazardous/ MSW conditionDetails of Non hazardous/MSW as applied

Sr. no Type of waste Quantity & UOM Treatment Disposal

1 Plastic Waste 200 Kg/M NA Sale to AuthorizedRecycler

2 Plastic Waste 200 Kg/M NA Sale to AuthorizedRecycler

3 Boiler Ash 44 MT/M NA Landfilling / Sale toBricks Mfrs

4 Boiler Ash 44 MT/M NA Landfilling / Sale toBricks Mfrs

Whether any deviation in Non-Hz waste generation and itsdisposal,observed compared to previous consent NO Remarks:

Compliance of existing unit in case applied for expansion C to E/O/R NOWaterCess Returns filed upto: Paid Upto: Jan 1 1900

12:00:00:000AM

MPCB-CAC-00

0000

0058

MPCB-CAC-0000000058 (CAC Meeting Number : 8 dated August 6, 2019) Page 89 of 154

Directionissued (ifany)

BGDetails Amount Validity

BG obtained towards complience ofa) Consent/CCA condition b) directions

1 Rs. 5 Lakh 30/04/2021 Compliance of Consent conditions NA

2 Rs. 5 Lakh 30/12/2018 Installation of OCMS &connectivity to MPCB Server NA

3 Rs. 5 Lakh 30/07/2021 Compliance of Consent conditions NADetails of BGfortified/enchasedfor noncomplience,if any:Submission ofEnvironmentalStatement

NO Year 22.09.2018 for the period of2017-2018

Details of consentfee paid Amount Rs: 30,000/- Terms 2

In case of 1st C to OComplience of C toE conditions

Remarks

Recommendation ofTAC

Recommendations

Shri. Nitin R. Shinde (SRO-Pune I):-Pl visit, process and put up.(Mar 7 2019 09:57:20:000AM)

Upendra Kulkarni (FO-Pune I):-1. Application is received for change in product mix. 2. Industry is located at MIDC kurkumbhand engaged in manufacturing of chemicals. 3. Industry wants to curtail production ofHydroqunine Cathol and their derivatives -9999.96 T/A to 5000 T/A., Vaniline and theirderivatives -5000 MT/A to 1300 T/A, stop the production of Butylated Hydroxy anisol. andaddition of two products. 4. Industry has submitted no increase in pollution load from GoldfinchEngineering System (P) Ltd., 5. Present effleunt generation is 156 CMD and proposed will be155 CMD. 5. Hazardous waste generation ETP sludge remain as it is 5T/day and MEE salt4T/day as it is. 6. Distillation residue from 2.89 T/M to 2.81T/M. 7. Industry has providedseparate treatment for high COD waste by treating it primariliy and then to UASB. Supernant ofUASB then treated with LOW COD effluent in primary, secondary and tertiary treatment . ROand MEE is installed to achieve Zero discharge. 8. Due to change in product mix capitalinvestment is increased by Rs. 4.75 crores. hence now total investment become 78 crorestherefore under purview of CAC instead of CC. Industry has paid fees 30,000/- additionally andasked to pay additionally 30,000/- to issue the consent till 31.3.2021. 9. Two boilers and twothermopacks are installed Coal/briquette is used as a fuel, Multicyclone dust collector installed.10. In view of above decision on grant of consent may be taken at higher authority.(Mar 20 2019 06:08:11:000PM)

Shri. Nitin R. Shinde (SRO-Pune I):-Pl upload the previous results of air and water if available so that the adequacy of PCS can beremarked(Mar 26 2019 02:58:54:000PM)

Upendra Kulkarni (FO-Pune I):-Industry has provided RO and MEE to achieve ZLD and not sending or discharging effluentoutside. Multi cyclone dust collector is provided to briquette/coal fire boiler.(Mar 26 2019 04:31:44:000PM)

Shri. Nitin R. Shinde (SRO-Pune I):-The remarks of FO pl may be seen. In view of above we may consider the case for change inproduct mix with the verification of no load certification and applicability of EC accordingly. TheJVS samples have not been collected recently the previous results will be uploaded and mailedseparately. submitted for further necessery pl.(Mar 27 2019 04:20:33:000PM)

Mr.P.K.Mirashe(AST) (CAC-CELL-HQ):-Pl process and put up(Mar 28 2019 10:57:28:000AM)

MPCB-CAC-00

0000

0058

MPCB-CAC-0000000058 (CAC Meeting Number : 8 dated August 6, 2019) Page 90 of 154

Other RelevantInformation

1. Existing Red/LSI industry engaged in mfg. of Organic Chemicals (Hydroqunine Cathol andtheir derivatives- 9,999.96 MT/A, Butylated Hydroxy anisol- 2,400 MT/A, Vaniline and theirderivatives- 3,000 MT/A & Anisole & their derivatives- 9,000 MT/A) has obtained Consent toOperate with C.I. Rs. 74 Crs which is valid up to 31/03/2021.

2. Industry had obtained EC from the Env. Dept. on 16/02/2018 for above products.

3. Industry has provided ETP of designed capacity 200 CMD consisting of primary, secondary &tertiary treatment followed by RO & MEE for the treatment of 156 CMD of industrial effluentand treated effluent is 100% recycled/ reused into process and for secondary purposes likecooling tower make up, fire-fighting etc. so as to achieve Zero Liquid Discharge (ZLD).

4. 16 CMD sewage is treated in Septic Tank followed by Soak Pit. Overflow is applied on land forgardening within premise.

5. Two boilers and two thermopacks are installed, Coal/briquette is used as a fuel, Multicyclonedust collector provided.

6. Now, industry has applied for amendment in Consent to Operate for proposed change inproduct-mix for mfg. of following products & by-products:Proposed products:i) Hydroqunine Cathol and their derivatives- 5,000 MT/A, ii) Vaniline and their derivatives- 1,300MT/A, iii) Anisole and their Derivatives- 9,000 MT/A, iv) 1.Dicyclohyxylcarb odiimide(DCC)-1,200 MT/A, and v) Ascorbyl Palmitate- 300 MT/A.

Proposed by-products:i) O-Cresol Mix- 450 MT/A, ii) Sodium Sulphate- 3,891 MT/M, iii) Ammonium Salt Mixture- 2,940MT/A, and iv) Hydrochloric Acid- 42 MT/A.

7. In support of its application, industry has submitted "No increase in pollution load" Certificateissued by MoEF&CC approved Lab. M/s Goldfinch Engineering System (P) Ltd. and proforma ofself assessment of no increase in pollution load in prescribed format.

Recommendation ofCAC/CC Cell

-Applied for amendment in Consent to Operate for proposed change in product-mix.

- Obtained basic EC on 16/02/2018.

-Provided ETP & APCS.

-Achieved ZLD.

-Submitted proforma of self assessment of NIPL & NIPL Certificate issued by approved Labshowing that proposed products belongs to same group/ family and overall quantity of proposedproducts & by-products will not exceed Consented overall quantity of products.

In view of above, we may consider the case and grant amendment in Consent to Operate forproposed change in product-mix for mfg. of following products & by-products subject to approvalof Board's Technical Committee for certification of no increase in pollution load:Proposed products:i) Hydroqunine Cathol and their derivatives- 5,000 MT/A, ii) Vaniline and their derivatives- 1,300MT/A, iii) Anisole and their Derivatives- 9,000 MT/A, iv) 1.Dicyclohyxylcarb odiimide(DCC)-1,200 MT/A, and v) Ascorbyl Palmitate- 300 MT/A.

Proposed by-products:i) O-Cresol Mix- 450 MT/A, ii) Sodium Sulphate- 3,891 MT/M, iii) Ammonium Salt Mixture- 2,940MT/A, and iv) Hydrochloric Acid- 42 MT/A.

ConsentRecommended forperiod upto as perSectoral Approachpolicy

--

FINAL REMARKS/DECISION as on 1st meeting of 2019/20 dated 20-06-2019MPCB-CAC-00

0000

0058

MPCB-CAC-0000000058 (CAC Meeting Number : 8 dated August 6, 2019) Page 91 of 154

DECISION

-Applied for amendment in Consent to Operate for proposed change in product-mix.

- Obtained basic EC on 16/02/2018.

-Provided ETP & APCS.

-Achieved ZLD.

-Submitted proforma of self assessment of NIPL & NIPL Certificate issued by approved Labshowing that proposed products belongs to same group/ family and overall quantity of proposedproducts & by-products will not exceed Consented overall quantity of products.

In view of above, we may consider the case and grant amendment in Consent to Operate forproposed change in product-mix for mfg. of following products & by-products subject to approvalof Board's Technical Committee for certification of no increase in pollution load:Proposed products:i) Hydroqunine Cathol and their derivatives- 5,000 MT/A, ii) Vaniline and their derivatives- 1,300MT/A, iii) Anisole and their Derivatives- 9,000 MT/A, iv) 1.Dicyclohyxylcarb odiimide(DCC)-1,200 MT/A, and v) Ascorbyl Palmitate- 300 MT/A.

Proposed by-products:i) O-Cresol Mix- 450 MT/A, ii) Sodium Sulphate- 3,891 MT/M, iii) Ammonium Salt Mixture- 2,940MT/A, and iv) Hydrochloric Acid- 42 MT/A.

InternalRemarks/Discussion: ---

Outstandingdirections, if any:

Finally, after due deliberations, it was decided to recommend the case for change in productunder product mix with a condition to dispose the Co-product as Hazardous Waste and shallcomply the provision of HW Rules for sale/disposal of co-products. Detailed MoM uploaded.

MPCB-CAC-00

0000

0058

MPCB-CAC-0000000058 (CAC Meeting Number : 8 dated August 6, 2019) Page 92 of 154

ITEM NO: 19 - Unique Number: MPCB-CONSENT-0000064084Fresh CAC ITEMRegion: SRO - Kolhapur Section: CAC Date: 01.08.2019UAN Number: MPCB-CONSENT-0000064084 TAG CAC1.Name of HCE: Padmashri Dr. D Y Patil Education Society, Medical College & Hospital and Research Centre2.Address: 507/1,Kadamwadi,E Ward,Kolhapur,Kolhapur,KarvirEmail: [email protected] Mobile number: 98236959993.Applied For Renewal of Combined Consent & BMW Authorization with increase in CI & change in name4.ApplicationReceipt @ SRO: March 5,2019 Application Receipt

@ HQ: 06.07.2019

5.Type OfInstitution: Health Care Establishment Industry Category: R30 Health-care Establishment (

asdefined in BMW Rules)6.Total Plot area(sq.m.) 60600 Total Builtup(m2): 18925

7.Env.Clearence: No EC Ref No.:8.Date OfCommisioning 15-01-2001

9.Validity

a).C to E:

b).C to O:BO/CAC-Cell/CCA- 0271 Dated 13.02.2017 valid up to 30.04.2018.[ 650Beds] and for Total Plot Area of 60,000 sq.m. and Total ConstructionBUA of 18925.48 sq.mtrs

c)BMW Authorization:Capital Investment in Rs. (Crs)

Existing Proposed TotalRs.52.84 Crs + Increased by Rs. 37.53 Crs Rs.90.37 crs11.Number of Bedsasper BNHCertificate:

650 Beds [ Number of beds notmentioned in BNH]and valid up to31.03.2019

BNH Validity:

12.Fees paid (Rs): From: To: Amount (Rs): Addl. required:i) Consent 31.04.2018 31.04.2023 700000ii) Authorization 31.04.2018 31.04.2023 7500013.CRZ Applicable: NA ESZ Applicable: NA14.Annual Report(Form-II): No Year: Jan-2018 to Dec-2018.

15.Accident Report(Form-III): No Year:

16.Bio-Medical Waste DetailsSr. Number Category Max Quantity (Kg/M)1 Yellow 6702 Red 7403 White 5004 Blue 017 a)Disposal @CBMWTF No Membership No &

Validity: Yes, BMW-55, 12.09.2019

Member ofCBMWTF CBMWTSDF of Kolhapur Municipal Corporation

b) Captive Disposal Noa) IncineratorCapacity Fuel Type Auto Feeding Temp. Recorder Online Monitoring

NA NA NAb) Autoclave Type(Vertical/Horizontal)(litres)

Temp & PressureRecording

c) Shredder (Kg/hr) Plastic WasteDisposal

18.Detais of water consumption as applied and Effluent generation:

MPCB-CAC-00

0000

0058

MPCB-CAC-0000000058 (CAC Meeting Number : 8 dated August 6, 2019) Page 93 of 154

Purpose Water Consumptionin CMD as applied

Effluent generationas applied in CMD

TreatmentSteps

DisposalDetails

Remarks/Adequeteland Available

1 Domestic Purposes 275 250 STPOn Land

forGardening

-

2Processing wherebywater gets polluted &pollutants are easilybiodegradable

15 15Primary +Secondary+ Tertiary

On Landfor

Gardening-

3Processing wherebywater gets polluted &pollutants are noteasily biodegradable

0 0 --NA-- --NA-- -

4IndustrialCooling,spraying inmine pits or boilerfeed

0 0 --NA-- --NA-- -

5Others such asgardening,agricultureetc

50 NA NA NA NA

19.Water Budget Not Submitted Verified: No Cess Paid till Dt: Jan 1 190012:00:00:000AM

20.ETP & STP Details: ETP STPProvided/Not Provided Not Provided Not ProvidedPrimary/Secondary/Tertiary Primary PrimaryCapacity (CMD) 25 300Adequate/Not Adequate Adequete AdequeteO & M Improvement No NoPerformance

Existing JVS results EffluentSr.no. Date of visit Board official's

name:Whether samplecollected or not:

Whether results areconfirming to standardsor not (Exceedingparameter with value)

1 01.04.2017 [ STP] YES YES1 28.12.2017 [ STP] YES YES

1 22.03.2018 [ STP/ETP] YES YES

1 28.02.2019 [ STP/ETP] NO NO21.DG Set Details:

Sr. no Desciption Capacity Remarks1 D G Set 320 NA

22.Compliance of Air Pollution related conditions:Sr. no Source Stack Fuel type Quantity Height-I,II,III

APCsystemdetail

1 D G Set 02 Diesel 25 (Kg/hr.) 3 mtr aboveroof m

Inbuilt AirFilter forD.G. Set

Existing JVS results AirSr.no. Date of visit Board official's

name:Whether samplecollected or not:

Whether results areconfirming to standardsor not (Exceedingparameter with value)

1 No NO NO23.Legal Compliance

Water ETP Complied STP CompliedAir Emissions Complied

MPCB-CAC-00

0000

0058

MPCB-CAC-0000000058 (CAC Meeting Number : 8 dated August 6, 2019) Page 94 of 154

BMW

a) Complied as perpreviousAuthorization

No

b) AuthorizationNumberc) Remarks

24.Legal Action,if anyLegal Action Details

25.Bank GuaranteeBg Imposed No

BGDetails Amount Validity

BG obtained towards complience ofa) Consent/CCA condition b) directions

1 Rs.1.0 Lakhs Continuous To segregate and handle BMW asper Rule. NA

2 Rs.1.0 Lakhs ContinuousOperation and Maintenance ofSTP/ETP to achieve prescribeddischarge standards

NA

3 Rs.25,000/- Continuous To maintain records of BMW andsubmission of Annual Report NA

4 Rs.25,000/- Continuous To maintain records of BMWmaterial delivered to CBMWTSDF NA

5 Rs.75,000/- Continuous To provide seprate BMW storagefacility as per guidelines of CPCB NA

MPCB-CAC-00

0000

0058

MPCB-CAC-0000000058 (CAC Meeting Number : 8 dated August 6, 2019) Page 95 of 154

Observations

Prashant Gaikwad (SRO-Kolhapur):-Process & Put up.(Mar 28 2019 03:32:03:000PM)

Shri. S.B. More (FO-Kolhapur):-HCE previous 650 bed . CAC .Cap Inv Rs 90.37 cr. Applied for renewal of combined consent .Previous combined consent was up to 31.04.2018 for bed capacity 650 bed. M/s. Padmashri Dr.D Y Patil Education Society, Medical College & Hospital and Research Centre S.No 507/1, EWard, Kadamwadi, Tal Karveer, Kolhapur. Trade effluent from Laundry 15 CMD HCE providedETP of 25 CMD Primary treatment.. Further send to STP . Domestic effluent generation 250CMD. HCE provided STP of 300 CMD capacity with PSF & ACF. Treated effluent used on landfor gardening JVS dtd 22/03/18 are within limits. JVS datd 28/02/19 awaited. ETP (Loundry)Sludge not send to CHWTSDF or to CBMWTSDF as per consent. Kept in SDB. DG set 325 KVAprovided with acoustic enclosure and stack of 3m to it. . HCE segregating BMW and kept incolour coded bins for disposal . Kept separate storage facility at Ground floor. Kept record ofBMW by HCE and maintained . Regulary sending BMW to CBMWTSDF. submitted CBMWTSDFmembership copy valid up to 12.09.2019. HCE Bombay Nursing Home certificate valid up to31/03/2019 but not submitted with bed capacity . Not submitted Bank Guarantee of Rs 3.25 lacsas per consent and its compliance. Not submitted BMW annual Report. Now capital investmentis Rs 90.37 cr. Fees for consent Paid Rs 625000/- for 5 year up to 31.04.2023 and forauthorization Paid Rs 75000/- for 5 year however Previous capital Investment was Rs 52.84 cr ieincrease by Rs 37.53 Cr,. Called justification for increase of capital investment. and to submitlast 4 year balance sheet. And remaining fees Rs 75000/- This office sent Scrutiny letter, replyawaited. Fees yet to paid. In view of above Combined consent and authorization may be grantedafter compliance. Submitted Pl.(Apr 14 2019 07:09:42:000PM)

Prashant Gaikwad (SRO-Kolhapur):-HCE previous 650 bed . CAC .Cap Inv Rs 90.37 cr. Applied for renewal of combined consent .Previous combined consent was up to 31.04.2018 for bed capacity 650 bed. M/s. Padmashri Dr.D Y Patil Education Society, Medical College & Hospital and Research Centre S.No 507/1, EWard, Kadamwadi, Tal Karveer, Kolhapur. Trade effluent from Laundry 15 CMD HCE providedETP of 25 CMD Primary treatment.. Further send to STP . Domestic effluent generation 250CMD. HCE provided STP of 300 CMD capacity with PSF & ACF. Treated effluent used on landfor gardening JVS dtd 22/03/18 are within limits. JVS datd 28/02/19 awaited. ETP (Loundry)Sludge not send to CHWTSDF or to CBMWTSDF as per consent. Kept in SDB. DG set 325 KVAprovided with acoustic enclosure and stack of 3m to it. . HCE segregating BMW and kept incolour coded bins for disposal . Kept separate storage facility at Ground floor. Kept record ofBMW by HCE and maintained . Regulary sending BMW to CBMWTSDF. submitted CBMWTSDFmembership copy valid up to 12.09.2019. HCE Bombay Nursing Home certificate valid up to31/03/2019 but not submitted with bed capacity . Not submitted Bank Guarantee of Rs 3.25 lacsas per consent and its compliance. Not submitted BMW annual Report. Now capital investmentis Rs 90.37 cr. Fees for consent Paid Rs 625000/- for 5 year up to 31.04.2023 and forauthorization Paid Rs 75000/- for 5 year however Previous capital Investment was Rs 52.84 cr ieincrease by Rs 37.53 Cr,. Called justification for increase of capital investment. and to submitlast 4 year balance sheet. And remaining fees Rs 75000/- This office sent Scrutiny letter, replyawaited. Fees yet to paid. In view of above Combined consent and authorization may be grantedafter compliance.Submitted Pl.(May 17 2019 05:49:37:000PM)

Shri Ravindra Andhale (RO-Kolhapur):-Process and put up(May 31 2019 06:44:38:000PM)

Shri.Sushilkumar B Shinde (FO-Kolhapur):-Applied for renewal of combined consent. Hospital having 650 beds , C.I. 90.27 Crs. The Case isCC/CAC level. Submitted for further order please.(Jun 28 2019 04:38:57:000PM)

Shri Ravindra Andhale (RO-Kolhapur):-HCE having 650 beds. Submit to concern granting authority.(Jun 28 2019 04:41:42:000PM)

Prashant Gaikwad (SRO-Kolhapur):-Applied for renewal of CCA, 650 Bed HCE. Submitted the details of BMW generation as perBMW Rules 2016, Trade effluent from Laundry 15 CMD HCE provided ETP of 25 CMD Primarytreatment.. Further send to STP . Domestic effluent generation 250 CMD. HCE provided STP of300 CMD capacity with PSF & ACF. Treated effluent used on land for gardening JVS dtd22/03/18 are within limits. JVS datd 28/02/19 awaited. HCE segregating BMW and kept in colourcoded bins for disposal . Kept separate storage facility at Ground floor. Kept record of BMW byHCE and maintained . Regulary sending BMW to CBMWTSDF. submitted CBMWTSDFmembership copy valid up to 12.09.2019. HCE Bombay Nursing Home certificate valid up to31/03/2019 but not submitted with bed capacity. Now HCE uploaded details of compliance of BGcondition, the Annual Report is submitted, submitted additional fees of Rs. 75000/-, SubmittedBG as per CCA condition, uploaded fresh BNH certificate, submitted explanation for increase inCI, the said HCE is under UNIDO. The renewal of CCA may be considered, if approved.Submitted please.(Jul 4 2019 05:12:31:000PM)

Dr.Amar R. Supate (PSO-HQ):-Examined and put up(Jul 5 2019 10:20:35:000AM)

Mr. Chetan Sawant (FO-HQ):-The hospital is having 650 beds which is under the purview of CAC(Jul 5 2019 12:14:38:000PM)

Dr.Amar R. Supate (PSO-HQ):-The case is under the purview of CAC being 650 beds(Jul 5 2019 02:20:27:000PM)

Mr.P.K.Mirashe (AST-HQ):-CAC Purview Application. Transferred to CAC cell for further processing.(Jul 6 2019 12:11:44:000PM)

Mr.P.K.Mirashe(AST) (CAC-CELL-HQ):-Pl process and put up(Jul 6 2019 12:25:47:000PM)

MPCB-CAC-00

0000

0058

MPCB-CAC-0000000058 (CAC Meeting Number : 8 dated August 6, 2019) Page 96 of 154

Other RelevantInformation

1] PP has applied for combine consent and BMW authorization for 650 nos of beds and for TotalPlot Area of 60,000 sq.m. and Total Construction BUA of 18925.48 sq.mtrs with increase in CIand change in name.

2]Earlier consent was valid up to 31.04.2018 for same bed capacity and BUA.

3]PP has obtained BNH certificate of Kolhapur Municipal corporation which was valid up to31.03.2019.

4]PP has provided STP of capacity -300 CMD and ETP of capacity-25 CMD for treatment ofsewage and trade effluent. The analysis results of JVS are within the consented limits.

5] PP has obtained membership of CBMWTSDF of KMC for disposal of BMW.

6] PP has submitted copy of annual returns for the period 2018.

Recommendation ofCAC/CC Cell

We may consider renewal of Combined Consent & BMW Authorization with increase in CI &change in name up to 31.04.2023 by extending existence BGs. Consent shall be issued aftersubmission of justification of increase in CI and additional consent fees from PP, if any.

ConsentRecommended forperiod upto as perSectoral Approachpolicy

30.04.2023.

MPCB-CAC-00

0000

0058

MPCB-CAC-0000000058 (CAC Meeting Number : 8 dated August 6, 2019) Page 97 of 154

ITEM NO: 20 - Unique Number: MPCB-CONSENT-0000067557Fresh CAC ITEMRegion: SRO - Mumbai I Section: CAC Date: 21.06.2019UAN Number: MPCB-CONSENT-0000067557 TAG CAC1.Name of HCE: PRINCE ALY KHAN HOSPITAL

2.Address: PLOT NO CS376,PLOT NO CS 376, AGA HALL ,,NESBIT ROAD , MAZAGOAN,E-400010,MumbaiCity,Mumbai city,MAZAGAON 10

Email: [email protected] Mobile number: 99304565213.Applied For Renewal of Combined Consent & BMW Authorization with increase in CI4.ApplicationReceipt @ SRO: March 7,2019 Application Receipt

@ HQ: 22.04.2019

5.Type OfInstitution: Health Care Establishment Industry Category: R30 Health-care Establishment (

asdefined in BMW Rules)6.Total Plot area(sq.m.) 9100 Total Builtup(m2): 4494

7.Env.Clearence: No EC Ref No.:8.Date OfCommisioning 25-04-2015

9.Validity

a).C to E:

b).C to O:BO/CAC-Cell/CCA/CAC-1801000063 Dated 03.01.218 valid up to31.03.2019.[ 201 Beds]Total Plot Area of 9100 sq.m. and TotalConstruction BUA of 4494 sq.m

c)BMW Authorization:Capital Investment in Rs. (Crs)

Existing Proposed TotalRs.90.35 Crs + Increased by Rs. 28.51 Crs Rs. 118.86 Crs11.Number of Bedsasper BNHCertificate:

201 Nos. of the Beds and valid upto 31.03.2019 BNH Validity:

12.Fees paid (Rs): From: To: Amount (Rs): Addl. required:i) Consent 31.03.2019 31.03.2024 1188695ii) Authorization 31.03.2019 31.03.2024 50000 --13.CRZ Applicable: NA ESZ Applicable: NA14.Annual Report(Form-II): Yes Year: Jan-201 to Dec-2017.

15.Accident Report(Form-III): No Year:

16.Bio-Medical Waste DetailsSr. Number Category Max Quantity (Kg/M)1 Yellow 5760002 Red 2670003 White 285004 Blue 017 a)Disposal @CBMWTF No Membership No &

Validity: Yes

Member ofCBMWTFb) Captive Disposal Noa) IncineratorCapacity Fuel Type Auto Feeding Temp. Recorder Online Monitoring

b) Autoclave Type(Vertical/Horizontal)(litres)

Temp & PressureRecording

c) Shredder (Kg/hr) Plastic WasteDisposal

18.Detais of water consumption as applied and Effluent generation:

MPCB-CAC-00

0000

0058

MPCB-CAC-0000000058 (CAC Meeting Number : 8 dated August 6, 2019) Page 98 of 154

Purpose Water Consumptionin CMD as applied

Effluent generationas applied in CMD

TreatmentSteps

DisposalDetails

Remarks/Adequeteland Available

1 Domestic Purposes 50 60 STP LocalBodies 0

2Processing wherebywater gets polluted &pollutants are easilybiodegradable

3 0Primary +Secondary+ Tertiary

--NA-- 0

3Processing wherebywater gets polluted &pollutants are noteasily biodegradable

0 3Primary +Secondary+ Tertiary

SharedETP 0

4IndustrialCooling,spraying inmine pits or boilerfeed

0 0 --NA-- --NA-- 0

5Others such asgardening,agricultureetc

No NA NA NA NA

19.Water Budget Not Submitted Verified: No Cess Paid till Dt: Jan 1 190012:00:00:000AM

20.ETP & STP Details: ETP STPProvided/Not Provided Not Provided ProvidedPrimary/Secondary/Tertiary Primary PrimaryCapacity (CMD) 0 60Adequate/Not Adequate Adequete AdequeteO & M Improvement No NoPerformance

Existing JVS results EffluentSr.no. Date of visit Board official's

name:Whether samplecollected or not:

Whether results areconfirming to standardsor not (Exceedingparameter with value)

1 Not enclosed. NO NO21.DG Set Details:

Sr. no Desciption Capacity Remarks1 Diesel 1005 0

22.Compliance of Air Pollution related conditions:Sr. no Source Stack Fuel type Quantity Height-I,II,III

APCsystemdetail

1 0 1 Diesel 100 (Kg/hr.) 5 m m SILENCEx 2 NOS

2 0 2 Diesel 100 (Kg/hr.) 5 m m SILENCEx 2 NOS

Existing JVS results AirSr.no. Date of visit Board official's

name:Whether samplecollected or not:

Whether results areconfirming to standardsor not (Exceedingparameter with value)

1 Not enclosed NO NO23.Legal Compliance

Water ETP Complied STP CompliedAir Emissions Complied

BMW

a) Complied as perpreviousAuthorization

No

b) AuthorizationNumber

BO/CAC-Cell/EIC No.RD-3049-15/CCA(O & Autho)CAC-4717 Dated24.04.2015 valid up to 30.06.2016.[ 400 Bes] BUA-32,932 Sq.mtrs.

c) Remarks24.Legal Action,if any

Legal Action Details

MPCB-CAC-00

0000

0058

MPCB-CAC-0000000058 (CAC Meeting Number : 8 dated August 6, 2019) Page 99 of 154

25.Bank GuaranteeBg Imposed No

BGDetails Amount Validity

BG obtained towards complience ofa) Consent/CCA condition b) directions

1 Rs.1,00,000/- Continuous To segregate and Handle BMW asper Rule. NA

2 Rs. 1.0 Lakhs ContinuousOperation and Maintenance of STP/ETP to achieve prescribeddischarge standards.

NA

3 Rs.25,000/- ContinuousTo maintain records of BMW andsubmission of annual report inform -II before 31 January

NA

4 Rs.25,000/- Continuous To maintain records of BMWmaterial delivered to CBMWTSDF NA

Observations

Shri. S.R. Bhosale (SRO-Mumbai I):-Process and put up(Mar 8 2019 11:44:23:000AM)

Smt. J. P. Junonkar (FO-Mumbai I):-HCE has obtained combined consent and authorization vide No. BO/CACCell/CCA/CAC-1801000063,dtd 03/01/2018 which is valid upto 31/03/2019.Now HCE has appliedfor renewal of combined consent to operate and authorization for Hospital activity- 201 beds.Hospital authority has obtained membership of CBMWTSD Facility i.e. M/s. SMS Envoclean Pvt.Ltd., Deonar & disposing bio-medical waste generated regularly to M/s. SMS Envoclean.Hospital has provided STP having capacity 60 CMD for the treatment of domestic effluent 55CMD but detail not submitted. HCE has not submitted the details of treatment provide for solidwaste .Hospital authority has provided separate room for BMW storage. HCE has colour codedbags at source for BMW segregation. HCE has not submitted the details of BG as per previousconsent conditions. HCE has installed D. G. Sets having capacity 625 and 380 KVA. Capitalinvestment in previous consent is Rs 90.35 Cr now HCE has submitted C. A. Certificate, showingthe CI Rs. 118.86 Cr . HCE has paid consent fees of Rs. 1188695/- and authorization fees Rs50000/- .This office has issued online query letter to the HCE but till date reply not submitted. Inview of above we may keep the application awaited for the reply of query letter.(Mar 16 2019 04:43:13:000PM)

Shri. S.R. Bhosale (SRO-Mumbai I):-SEND REMINDER(Apr 8 2019 11:41:30:000AM)

Smt. J. P. Junonkar (FO-Mumbai I):-Hospital has not detail of STP provided. HCE has not submitted the details of treatment providefor solid waste. HCE has submitted the BG of Rs 300000/- as per previous consent conditions.Capital investment in previous consent is Rs 90.35 Cr now HCE has submitted C. A. Certificate,showing the CI Rs. 118.86 Cr . HCE has paid consent fees of Rs. 1188695/- and authorizationfees Rs 50000/- .This office has issued online query letter to the HCE but till date satisfactoryreply not submitted and also not submitted the additional fees for increase in capital investment.In view of above we may recommended the renewal of CCA after receipt of reply of query letterand the additional fees.(Apr 22 2019 01:25:19:000PM)

Shri. S.R. Bhosale (SRO-Mumbai I):-In view of above renewal of CCA may be granted after receipt of reply of query letter and theadditional fees.(Apr 22 2019 03:17:19:000PM)

Mr.P.K.Mirashe(AST) (CAC-CELL-HQ):-Pl Process and put up(Apr 22 2019 04:01:14:000PM)

Other RelevantInformation

1] PP has applied for renewal of combine consent and BMW authorization with increase in CI for201 Beds and for total plot area 9100 sq. mtrs and BUA 4494 sq. Mtrs.

2] Earlier combine consent and BMW authorization was valid up to 31.03.2019.

3]PP has obtained membership of BNH which was valid up to 31.03.2019.

4]PP has provided STP of capacity- 60 CMD for the treatment of sewage.The STP consisting ofcollection tank, screening chamber, reaction tank-1,2,3, filters and SDB.

5] PP has submitted copy of the annual report for the year- 2017.

6] PP has submitted BG's as per earlier consent conditions.

MPCB-CAC-00

0000

0058

MPCB-CAC-0000000058 (CAC Meeting Number : 8 dated August 6, 2019) Page 100 of 154

Recommendation ofCAC/CC Cell

We may grant renewal of combine consent and BMW Authorization for the period up to31.03.2024 for 401 nos of beds, for total plot area 9100 sq. mtrs and BUA 4494 sq. Mtrs byimposing following conditions:

1. PP shall submit BG's as per HCEs regime.

Consent shall be issued after obtaining additional consent fees from PP, if any.ConsentRecommended forperiod upto as perSectoral Approachpolicy

31.03.2024.

MPCB-CAC-00

0000

0058

MPCB-CAC-0000000058 (CAC Meeting Number : 8 dated August 6, 2019) Page 101 of 154

ITEM NO: 21 - Unique Number: MPCB-CONSENT-0000068308Fresh CAC ITEMRegion: SRO - Raigad II Section: CAC Date: 30.07.2019UAN Number: MPCB-CONSENT-0000068308 TAG CACName & Address: JSW Dharamtar Port Pvt Ltd (Dharamtar, Post:Dolvi, Tal: Pen)Location ofIndustrial unit: 80,32 & 42 At-Dharamtar,Post-Dolvi Pen

Email: [email protected] Telephone number: 8691025525Industry Type: R46 Ports and harbour, jetties and dredging operationsIndustry Category: REDProject Details: Existing project

Consent Applied For1st Consent to

Operate [ Part] forexpansion of jetty -319

mtrs additionalApplication Date March

4,2019Date of receipt ofCAC/CC cell 20.04.2019

Capital Investment in Rs. (Crs)Existing Proposed Total

Rs.239.21 Crs + Increased by Rs.15.74 Crs Rs.254.95 CrsDetails of

project :Existingproject

Total Plot area(sq.m.) 13270 (sq.m) Construction

BUA (sq.m.)319 meter(sq.m)

Product and By-product detailsSr.no Product Name Quantity

1

Coal,Coke,All kinds of coalproducts,Bauxite,Fertilizer,Sulfur,Cement,Slag,Sugar,Steel coils, Plates & relatedproducts,Tiles, Ammoniumnitrate,DAP,Dolomite,Clinker, Lime stone,Foodgrains,Pulses,Mill scale,Iron based rawmaterial,Coal based raw material,Flux, HRcoil,GBS,Container

5 MT/A

Sr.no By-Product Name Quantity2 NA 0Applicabilty

ofCRZ

ClearenceDistance

from riverIndustrial

location policy Eco-sensitive Moratonium EC Direction of MoEF forwestern ghats

NO NO NO NO NO NO NO

If Yesprovidedetails

--NA-- - 0.00Km

Basedon:

Status:NotApplied

Details of CCA,Consents,Authorization and EC obtained Consent no. Consent

granted date ValidityCapital

Investmentin Crs

Total plotarea

ConstructionBUA

(FSI+Non-FSI)Remarks

C2O Bo/CAC-Cell/CR withexpansion-13991/CAC-181000509 11.10.2018 31.08.2019 Rs.239.21

Crs726.5

Mtrs jetty

C2E BO/CAC-Cell/UANno.23048/CAC-1905000980 16.05.2019 Establish Rs.1671.0

Crs

Revalidationexpansion

of jetty1023.5Mtrs

C2E BO/CAC-Cell/ EICNo.RD-2792-14/E9Amendment)CAC-10000 30.10.2014 Establish Rs.1671.0

Crs

expansionof jetty1023.5Mtrs

EC F No.11-79/2013-IA.III 26.11.2015

Existing production details

C to OSr.No Product Name Max quantity

1 Jetty for material handling captive purpose only- Total lengthof jetty constructed -726.5 Mtrs 21,90,000 MT/M(27 MTPA)

C to ESr.No Product Name Max quantity

1 Commissioning of the remaining expansion of jetty of the length1023.5 MtrsExpansion 35,00,00,000 MT/Year

Bio-Medical Waste Details

MPCB-CAC-00

0000

0058

MPCB-CAC-0000000058 (CAC Meeting Number : 8 dated August 6, 2019) Page 102 of 154

Annual Rpt.(Form-II): NA

Accident Rpt.(Form-III):

BMWGeneration

Sr.No Category Max quantity (Kg/M)

1 NA NA

Disposal @CBMWTF: No

Member ofCBMWTF: NA

CaptiveDisposal: No

Incinerator Capacity Fuel Type Auto Feeding Temp.Recorder Online Monitoring

NA NA NA

Autoclave Type(Vertical/Horizontal)

Temp &Pressure

Recording

Shredder Plastic WasteDisposal

Compliance of Water Pollution Related Conditions Purpose Water Consumption

in CMD as appliedEffluent generationas applied in CMD

TreatmentSteps

DisposalDetails

Remarks/Adequeteland Available

1 Domestic Purposes 15 8SepticTank &Soak Pit

On Landfor

Gardening

2Processing wherebywater gets polluted &pollutants are easilybiodegradable

0 0 --NA-- --NA--

3Processing wherebywater gets polluted &pollutants are noteasily biodegradable

0 0 --NA-- --NA--

4IndustrialCooling,spraying inmine pits or boilerfeed

0 0 --NA-- --NA--

5Others such asgardening,agricultureetc

NA NA NA NA NA

Whether any deviation in water consumption observed compared toprevious consent NO Remarks:

Compliance to existing unit in case applied for expansion C to E/O/R NOSource of water supply

In case proposed discharge to CETP forfurther treatment

CETP Capacity to handle additional load NOName of CETP

Existing JVS results EffluentSr.no. Date of visit Board official's

name:Whether samplecollected or not:

Whether results areconfirming to standardsor not (Exceedingparameter with value)

1 Not attached NO NO

Details of fuel consumption and APC system as applied :-Sr. no Source Stack Fuel type Quantity Height-I,II,III APC system

detail1 DG set 01 Diesel 0 (Kg/hr.) 24 m NAWhether any deviation in fuel consumptionand APC system observed compared toprevious consent

NO Remarks:

Compliance to existing unit in case appliedfor expansion C to E/O/R NO

Existing JVS results Air

MPCB-CAC-00

0000

0058

MPCB-CAC-0000000058 (CAC Meeting Number : 8 dated August 6, 2019) Page 103 of 154

Sr.no. Date of visit Board official'sname:

Whether samplecollected or not:

Whether results areconfirming to standardsor not (Exceedingparameter with value)

1 Not attached NO NO

Compliance of Haz. Waste ConditionDetails of hazardous waste as applied

Sr. no Type of waste Category Quantity & UOM Treatment Disposal

1 5.1 Used or spentoil 5.1 9000 Ltr/A NA

Sold to CPCB/MPCBauthorised refine/ reprocessor

2 NA NA 0 --NA-- NA NAWhether any deviation in Hz waste generation and itsdisposal,observed compared to previous consent NO Remarks:

Compliance of existing unit in case applied for expansion C to E/O/R NO

Submission of Annual Return (Form IV) NO Submission Date

Compliance of Non Hazardous/ MSW conditionDetails of Non hazardous/MSW as applied

Sr. no Type of waste Quantity & UOM Treatment Disposal1 packaging,material & papers 1 KL/A segregation non biodegradable saleWhether any deviation in Non-Hz waste generation and itsdisposal,observed compared to previous consent NO Remarks:

Compliance of existing unit in case applied for expansion C to E/O/R NOWaterCess Returns filed upto: Paid Upto: Jul 31 2017

12:00:00:000AMDirectionissued (ifany)

BGDetails Amount Validity

BG obtained towards complience ofa) Consent/CCA condition b) directions

1 Rs.5.0 Lakhs 28.02.2022 Towards compliance of the consentconditions. NA

2 Rs.25.0 Lakhs 31.12.2019Towards O & M of PCS so as toachieve consent standards andcompliance of the same

NA

Details of BGfortified/enchasedfor noncomplience,if any:

No.

Submission ofEnvironmentalStatement

NO Year 27.09.2018

Details of consentfee paid Amount Rs: 509900 Terms 1

In case of 1st C to OComplience of C toE conditions

Remarks

Recommendation ofTAC MPCB-C

AC-0000

0000

58

MPCB-CAC-0000000058 (CAC Meeting Number : 8 dated August 6, 2019) Page 104 of 154

Recommendations

Shri B. M. Kukade (SRO-Raigad II):-Visit, process & put up with report.(Mar 16 2019 11:26:54:000AM)

Shri. Bajirao Malvekar (FO-Raigad II):-1. It is captive jetty & obtained the consent to establish for expansion of existing jetty from 331.5mtrs to 1750 mtrs on dtd. 30/10/2014. Out of this the unit has completed the jetty length 395mtr & existing jetty length was 331.5 mtrs, the total length is 726.5 mtr; accordingly the unit hasobtained consent to operate on 11/10/2018 which is valid up to 31/8/2019.2. Now the unit has applied for consent to operate for expansion jetty having length 395 mtr outof 1418.5 Mtr jetty length i.e. expansion of existing jetty from 331.5 to 1750 mtr.3. The generation of trade effluent is nil & domestic effluent is 28 CMD which is treated in soakpit.4. The unit has provided the water sprinkling arrangement for dust suppression within jettypremises.5. The total CI of this unit is of Rs. 254.95 Cr; accordingly the unit has paid consent fees of Rs.509900.6. This office has issued query letter on 25/3/2019 in respect submission of self-monitoringreports, CA certificate, compliance as per CREP guidelines, annual returns & compliance reportas per consent conditions stipulated in schedule I & II; however the unit has not submitted anysay/reply to this office query letter, till date.In view of above it is submitted that the C to O for expansion of jetty length 395 mtr may beconsidered after submission of compliance report to this office query letter.(Apr 18 2019 02:23:39:000PM)

Shri B. M. Kukade (SRO-Raigad II):-Remarks of FO may please be seen. Decision may be taken for grant of consent to operate afterreceipt of compliance report to this office query letter. Submitted please.(Apr 18 2019 05:06:39:000PM)

Mr.P.K.Mirashe(AST) (CAC-CELL-HQ):-Pl Process and put up(Apr 20 2019 10:09:30:000AM)

Other RelevantInformation

1] PP has applied for 1st consent to operate [ part] for expansion of jetty -319 Meters.[ Totallength of jetty Existing 726.5 mtrs + Additional this expansion 319 mtrs = 1045.5 Mtrs]

2] PP has obtained of consent to establish for expansion of jetty from 331.5 mtrs to 1750 Mtrs on30.10.2014.Also obtained Re validation of consent to establish for expansion for remaining jetty on16.05.2019.

3] PP has obtained Environmental Clearance for the expansion of jetty on 26.11.2015.

4] PP has obtained consent to operate for the length 726.5 Mtrs on 11.10.2018.

5] PP has provided mist dust suppression at Barge unloading hoppers, Dry fog dust suppressionsystem at transfer points and transfer towers, wind barrier of 456 sq.mtrs, covered conveyorsbelt,Mechanized road sweeping, water sprinkling , covered shed storage , Hatched coveredbarges provided and mini bulk Carriers used for transportation in the channel.

6] PP has submitted reply letter on 30.03.2019 to queries raised by SRO office-Raigad-II.

Recommendation ofCAC/CC Cell

We may grant consent to operate [ part] for additional expansion jetty for the length-319 meters[ total length of jetty Existing 726.5 mtrs + Additional 319 mtrs = 1045.5 Mtrs] for materialhandling 5.0 MT/A for the period up to 31.03.2024 by imposing condition of BG towards O & Mof pollution control systems.

ConsentRecommended forperiod upto as perSectoral Approachpolicy

31.08.2024.MPCB-CAC-00

0000

0058

MPCB-CAC-0000000058 (CAC Meeting Number : 8 dated August 6, 2019) Page 105 of 154

ITEM NO: 22 - Unique Number: MPCB-CONSENT-0000069216Fresh CAC ITEMRegion: SRO - Nagpur I Section: CAC Date: 01.08.2019UAN Number: MPCB-CONSENT-0000069216 TAG CAC

Name & Address:BHANEGAON OPEN CAST COAL MINE PROJECT OF M/S WESTERN COALFIELDS LTD (WCL) -A SUBSIDIARY OF COAL IND (Officer of Sub Area Manager,Bhanegaon Shingori Sub Area ,WCLNagpur Area)

Location ofIndustrial unit:

SURVEY OF INDIA TOPOSHEET NO 550/3,KHASREA NO 12/1D & 12/2 VILLAGE BINA POSTKHAPERKHEDA KAMPTEE

Email: [email protected] Telephone number: 8275970813Industry Type: R35 Mining and ore beneficiationIndustry Category: REDProject Details: Existing project

Consent Applied For

1st consent to operatefor additional coal

mining activity 0.55MTPA [0.6 to 1.15

MTPA]

Application Date March16,2019

Date of receipt ofCAC/CC cell 16.05.2019

Capital Investment in Rs. (Crs)Existing Proposed Total

Rs.84.86 Crs + Rs. 10.06 Crs Increase in CI Rs. 94.92 CrsDetails of

project :Existingproject

Total Plot area(sq.m.)

3474600(sq.m)

ConstructionBUA (sq.m.) 2000 (sq.m)

Product and By-product detailsSr.no Product Name Quantity1 COAL 1.15 MT/ASr.no By-Product Name Quantity2 NA 0Applicabilty

ofCRZ

ClearenceDistance

from riverIndustrial

location policy Eco-sensitive Moratonium EC Direction of MoEF forwestern ghats

NO YES NO NO NO YES NO

If Yesprovidedetails

Kanhan - 0.25Km

Based on:

Status:Obtained (EC Ref. No. -J-11015/43/2004-IA.(M)Pt.FILE DATED16.02.2018 FOR APRODUCTIONCAPACITY OF 1.15MTPA PEAK)

Details of CCA,Consents,Authorization and EC obtained Consent no. Consent

granted date ValidityCapital

Investmentin Crs

Total plotarea

ConstructionBUA

(FSI+Non-FSI)Remarks

C2E BO/CAC-Cell/CAC-UANno.24111/CAC-1903000230 06.03.2019 31.10.2020. Rs.84.86 crs

EC J-11015/43/2004-IA.II(M).Pt.file 16.02.2018

Coal mineprojectfrom

0.70MTPAto 1.15 inML area

347.46 Ha

EC 3-32/2005(Env) 07.09.2017

Coal mineproject

from 0.6MTPA to0.7 in ML

area347.46 Ha

Existing production details

C to OSr.No Product Name Max quantity

1 Coal mining ML area 348.13 Ha 0.6 MTPA

C to ESr.No Product Name Max quantity

1 NA NA

Bio-Medical Waste Details

MPCB-CAC-00

0000

0058

MPCB-CAC-0000000058 (CAC Meeting Number : 8 dated August 6, 2019) Page 106 of 154

Annual Rpt.(Form-II): NA

Accident Rpt.(Form-III):

BMWGeneration

Sr.No Category Max quantity (Kg/M)

1 NA NA

Disposal @CBMWTF: No

Member ofCBMWTF: NA

CaptiveDisposal: No

Incinerator Capacity Fuel Type Auto Feeding Temp.Recorder Online Monitoring

NA NA NA

Autoclave Type(Vertical/Horizontal)

Temp &Pressure

Recording

Shredder Plastic WasteDisposal

Compliance of Water Pollution Related Conditions Purpose Water Consumption

in CMD as appliedEffluent generationas applied in CMD

TreatmentSteps

DisposalDetails

Remarks/Adequeteland Available

1 Domestic Purposes 135 80 STPOn Land

forGardening

GARDENING ANDPLANTATIONBIODIGESTER

INSTALLATION ISIN PROCESS

2Processing wherebywater gets polluted &pollutants are easilybiodegradable

0 0 --NA-- --NA-- NIL

3Processing wherebywater gets polluted &pollutants are noteasily biodegradable

0 0 --NA-- --NA--

4IndustrialCooling,spraying inmine pits or boilerfeed

9400 0 --NA-- Others

USED FOR DUSTSUPPRSEEION,FIRE FIGHTING,GREEN BELT

DEVELOPMENT ,SAND PLANT &SPRINKLERS

5Others such asgardening,agricultureetc

30032 NA NA NA NA

Whether any deviation in water consumption observed compared toprevious consent NO Remarks:

Compliance to existing unit in case applied for expansion C to E/O/R NOSource of water supply

In case proposed discharge to CETP forfurther treatment

CETP Capacity to handle additional load NOName of CETP

Existing JVS results EffluentSr.no. Date of visit Board official's

name:Whether samplecollected or not:

Whether results areconfirming to standardsor not (Exceedingparameter with value)

1 26.02.2019 YES YES

Details of fuel consumption and APC system as applied :-Sr. no Source Stack Fuel type Quantity Height-I,II,III APC system

detail1 NA NA NA 0 (Kg/hr.) 0 m 0Whether any deviation in fuel consumptionand APC system observed compared toprevious consent

NO Remarks:

Compliance to existing unit in case appliedfor expansion C to E/O/R NO

MPCB-CAC-00

0000

0058

MPCB-CAC-0000000058 (CAC Meeting Number : 8 dated August 6, 2019) Page 107 of 154

Existing JVS results AirSr.no. Date of visit Board official's

name:Whether samplecollected or not:

Whether results areconfirming to standardsor not (Exceedingparameter with value)

1 Not enclosed NO NO

Compliance of Haz. Waste ConditionDetails of hazardous waste as applied

Sr. no Type of waste Category Quantity & UOM Treatment Disposal

1 5.1 Used or spentoil 5.1 0.6 MT/M CHWTSDF

BUTTIBORICHWTSDFBUTTIBORI, BY HOECONTRACTOR

2 NA NA 0 --NA-- NA NAWhether any deviation in Hz waste generation and itsdisposal,observed compared to previous consent NO Remarks:

Compliance of existing unit in case applied for expansion C to E/O/R NO

Submission of Annual Return (Form IV) NO Submission Date

Compliance of Non Hazardous/ MSW conditionDetails of Non hazardous/MSW as applied

Sr. no Type of waste Quantity & UOM Treatment Disposal

1 OVERBURDEN 200000 m3/monthSTACKED AS AEXTERNAL DUMP ATEARMARKED SITE

BACKFILLING AS PERAPPROVED MINECLOSURE PLAN

Whether any deviation in Non-Hz waste generation and itsdisposal,observed compared to previous consent NO Remarks:

Compliance of existing unit in case applied for expansion C to E/O/R NOWaterCess Returns filed upto: Paid Upto: Jan 1 1900

12:00:00:000AMDirectionissued (ifany)

BGDetails Amount Validity

BG obtained towards complience ofa) Consent/CCA condition b) directions

1 Rs.5.0 Lakhs 28.02.2021To provide adequate capacity ofSTP within six months and towardscompliances of the same

NA

2 Rs.10.0 Lakhs 28.02.2021Towards operation andmaintenance of air pollutioncontrol system so as to achieveconsented standards

NA

Details of BGfortified/enchasedfor noncomplience,if any:

No

Submission ofEnvironmentalStatement

NO Year YES SUBMITTED ON DATED29.09.2018

Details of consentfee paid Amount Rs: 1035000 Terms 3

In case of 1st C to OComplience of C toE conditions

Remarks

Recommendation ofTAC

MPCB-CAC-00

0000

0058

MPCB-CAC-0000000058 (CAC Meeting Number : 8 dated August 6, 2019) Page 108 of 154

Recommendations

Hema Deshpande (SRO-Nagpur I):-Please process and put up(Mar 18 2019 03:01:16:000PM)

Shri. Kishor P. Pusadkar (FO-Nagpur I):-Industry authority has not replied to Query letter sent on 20/03/2019. Application can't beprocess without information. Application may be disposed suitably.(Mar 26 2019 01:21:54:000PM)

Hema Deshpande (SRO-Nagpur I):-Mine authority has uploaded reply. Visit report & analysis report are uploaded needsupgradation in Pollution control system provided &O & M of same. Application may consider for renewal of consent to operate after imposingpersonal hearing at HQ level & sutaible Bank Gurantee(May 16 2019 05:03:15:000PM)

Mr.P.K.Mirashe(AST) (CAC-CELL-HQ):-Pl Process and put up(May 16 2019 05:31:55:000PM)

Other RelevantInformation

1] PP has applied for 1st consent to operate for expansion for the additional coal miningactivity -0.55.i.e. 0.6 MTPA to 1.15 MTPA in mining lease area 347.46 Ha.

2] PP has obtained consent to operate for Coal mining activity for mining lease area 348.13 Hafor 0.6 MTPA which is valid up to 31.10.2020.

3] PP has obtained Environmental Clarence for additional mining activity from 0.6 MTPA to 0.7MTPA and 0.7 to 1.15 MTPA in mining lease area from 347.46 Ha. on 07.09.2017 & 16.02.2018repectively.

4] 2 nos of sedimentation ponds [ one sedimentation tank and one sand bed filter plantconstructed for discharged mine water treatment. Analysis results of air samples are within thelimits.

5] The installation of Biodigester is in process

6] Provided 2 nos of tankers, 18 nos of sprinklers, black topped road -2.1 Km , cement concreteroads-0.65 provided.

7] Submitted status of CGWA NOC, But they have not received final order of NOC from CGWA.

8] Not submitted details of BGs as per the consent conditions.

9] PP has not submitted separate application for consent to Establish for expansion and notobtained NOC of CGWA yet.

Recommendation ofCAC/CC Cell

We may keep this in abeyance and we may call to PP for for the technical presentation alongwith the action plans about installation of PCS.

ConsentRecommended forperiod upto as perSectoral Approachpolicy

-----

MPCB-CAC-00

0000

0058

MPCB-CAC-0000000058 (CAC Meeting Number : 8 dated August 6, 2019) Page 109 of 154

ITEM NO: 23 - Unique Number: MPCB-CONSENT-0000066431Resubmission CAC ITEMRegion: SRO - Mahad Section: CAC Date: 10/07/2019UAN Number: MPCB-CONSENT-0000066431 TAG CACName & Address: M/s. Mallak Specialties Pvt. Ltd. (C-103, MIDC Indl. Area, Mahad, Dist. Raigad, Maharashtra)Location ofIndustrial unit: Plot No C-103 Plot No C-103, MIDC Mahad, Tal- Mahad, Dist-Raigad 402301 Mahad

Email: [email protected] Telephone number: 9819069130Industry Type: R22 Organic Chemicals manufacturingIndustry Category: REDProject Details: Existing project

Consent Applied For

Consent to 1stOperate for expansion,

Renewal of existingConsent to Operateand amalgamation

Application Date February4,2019

Date of receipt ofCAC/CC cell 12/04/2019

Capital Investment in Rs. (Crs)Existing Proposed Total

78 8.2442 86.2442

Details ofproject :

Existingproject

Total Plot area(sq.m.) 80258 (sq.m) Construction

BUA (sq.m.)38581(Existing +Proposed)(sq.m)

Product and By-product detailsSr.no Product Name Quantity1 Pigment Alpha Blue 150 MT/M

2 Pigment Beta Blue/ Solvent Blue 67/ Basic Blue140/ Direct Blue 199 850 MT/M

3 Pigment Concentrates/ Pastes/ Dispersions/Master Batches/ Digital Inks 1000 MT/M

4 Pigment High Performance (Red, Yellow,Orange, Violet) 200 MT/M

5 Pearlescent Pigments 100 MT/M6 Pigment Blue Activated 300 MT/M7 Copper Phthalocyanine Blue Crude 1000 MT/M

8 Ethylene Oxide/ Propylene Oxide Condensatesand Derivatives 2000 MT/M

9 Esters/ Micronised Waxes/ Defoamers/ FlameRetardants 1000 MT/M

10 Amides/ Tackifiers/ Mold Release Agents 1000 MT/M

11 Polymeric Additives/ Polymers/ Polyurethanes/Adhesives 2000 MT/M

12 Metal Powder / Pastes 300 MT/M

13

Inorganic Metal Salts like Sulphates, Acetates,Phosphates, Oxides etc. of Aluminium, Copper,Iron, Manganese, Magnesium, Zinc, Potassium,Calcium, Cobalt, Nickel, SSP & Various othermetals

5000 MT/M

14 Pigment Green-7 100 MT/M

15Aluminium Alloys/flakes/powder ( MetalAlloys/Flakes/powder of Aluminium , Nickel,Copper, Zinc, Stainless Steel, Etc. Etc.)

1000 MT/M

Sr.no By-Product Name Quantity16 Ammonium Sulphate /Calcium Sulphate 270017 PAC/ Aluminium chloride (8- 10% solution) 100018 Hydrochloric Acid ( 20-25%) 7519 Liquor Ammonia ( 20% solution) 160020 Hypo ( NaOCl) 10 % solution 400

MPCB-CAC-00

0000

0058

MPCB-CAC-0000000058 (CAC Meeting Number : 8 dated August 6, 2019) Page 110 of 154

21 Monovalent/ Divalent Metal Salts/ Chlorides/Sulphates/ Nitrates/ Acetates 1500

22 Spent Acid ( 20%) 5250Applicabilty

ofCRZ

ClearenceDistance

from riverIndustrial

location policy Eco-sensitive Moratonium EC Direction of MoEF forwestern ghats

NO YES NO NO NO YES NO

If Yesprovidedetails

Kalu - 1.50 Km

Based on:

Status:Obtained (EC Ref. No. -SEAC-2013/CR-242/TC-2Dt. 28.01.2016)

Details of CCA,Consents,Authorization and EC obtained Consent no. Consent

granted date ValidityCapital

Investmentin Crs

Total plotarea

ConstructionBUA

(FSI+Non-FSI)Remarks

C2RFormat 1.0/BO/CAC-

Cell/UAN No. 25680/5thCAC-1801000062

03/01/2018 28/02/2019 78

C2E SEAC-2013/CR-242/TC-2 28/01/2016 28/01/2023 EC forexpansion

C2E

Format1.0/BO/AS(T)/RD-3050-1

5&RD-3051-15/EC/CC-940

6

25/07/2016 31/07/2021 34

Existing production details

C to O

Sr.No Product Name Max quantity

1 Ethylene Oxide/Propylene Oxide Condensates 2,000 MT/M

2 Esters 1,000 MT/M

3 Amides 1,000 MT/M

4 Pigment Blue (Activated) 150 MT/M

5 Pigment Alpha Blue 150 MT/M

6 Pigment Beta Blue 850 MT/M

7 Pigment Blue 150 MT/M

C to E

Sr.No Product Name Max quantity

1 Pigment Blue-Activated 150 MT/M

2 Pigment Alpha Blue 150 MT/M

3 Pigment Green-7 100 MT/M

4 Pigment Pearlescent 100 MT/M

5 Pigment, High Performance (Red, Yellow, Orange, Violet) 200 MT/M

6 Polymeric Additives/ Polymers/ Polyurethanes/ Sdhesive 2,000 MT/M

7 Pigment Concentrates/ Pastes/ Dispersion/ Master Batch/ Digital Inks 1,000 MT/M

8 Ethylene Oxide/ Propylene Oxide Condensates & Derivatives 2,000 MT/M

9 Esters 1,000 MT/M

10 Amides 1,000 MT/M

11 Pigment Beta Blue 850 MT/M

12 Copper Phthalocyanine Blue 1,000 MT/M

13 Metal Powders/ Pastes 300 MT/M

14 Mica Derivatives 100 MT/M

15 Sulphates & Oxides of Aluminium, Copper, Iron, Manganese, Zinc &various other metals 5,000 MT/M

16 Sodium/ Potassium Permanganate 200 MT/M

17 Zinc Sulphate 300 MT/M

18 Zinc Ingots 800 MT/M

19 Aluminium Alloys 1,000 MT/M

Bio-Medical Waste DetailsAnnual Rpt.(Form-II):Accident Rpt.(Form-III):

BMWGeneration

Sr.No Category Max quantity (Kg/M)

1 NA NA

MPCB-CAC-00

0000

0058

MPCB-CAC-0000000058 (CAC Meeting Number : 8 dated August 6, 2019) Page 111 of 154

Disposal @CBMWTF: NA

Member ofCBMWTF:CaptiveDisposal: NA

Incinerator Capacity Fuel Type Auto Feeding Temp.Recorder Online Monitoring

Autoclave Type(Vertical/Horizontal)

Temp &Pressure

Recording

Shredder Plastic WasteDisposal

Compliance of Water Pollution Related Conditions Purpose Water Consumption

in CMD as appliedEffluent generationas applied in CMD

TreatmentSteps

DisposalDetails

Remarks/Adequeteland Available

1 Domestic Purposes 20 18 STPOn Land

forGardening

NA

2Processing wherebywater gets polluted &pollutants are easilybiodegradable

2160 1840Primary +Secondary+ Tertiary

CETP CETP/MIDC Sump

3Processing wherebywater gets polluted &pollutants are noteasily biodegradable

0 0 --NA-- --NA-- NA

4IndustrialCooling,spraying inmine pits or boilerfeed

600 5Primary +Secondary+ Tertiary

CETP CETP/MIDC Sump

5Others such asgardening,agricultureetc

20 NA NA NA NA

Whether any deviation in water consumption observed compared toprevious consent NO Remarks:

Compliance to existing unit in case applied for expansion C to E/O/R NOSource of water supply

In case proposed discharge to CETP forfurther treatment

CETP Capacity to handle additional load YES

Name of CETP MMA-CETP Co-opSociety Ltd

Existing JVS results EffluentSr.no. Date of visit Board official's

name:Whether samplecollected or not:

Whether results areconfirming to standardsor not (Exceedingparameter with value)

1 NO NO

Details of fuel consumption and APC system as applied :-Sr. no Source Stack Fuel type Quantity Height-I,II,III APC system

detail

1 Boiler &Thermopack 1 Coal 30 (Kg/hr.) 30 m Dust Collector

2 Boiler 1 Coal 55 (Kg/hr.) 31.5 m Dust Collector3 Thermopack 1 Coal 40 (Kg/hr.) 30 m Dust Collector4 Ball Mill 1 NA 0 (Kg/hr.) 11 m Dust Collector5 Alpha Plant 1 0 0 (Kg/hr.) 15 m Scrubber

6 D.G. Set 1 LDO 100 (Kg/hr.) 11 m AcousticEnclosure

7 D.G. Set 1 LDO 100 (Kg/hr.) 11 m AcousticEnclosure

8 D.G. Set 1 LDO 100 (Kg/hr.) 9 m AcousticEnclosure

9 D.G. Set 1 LDO 100 (Kg/hr.) 9 m AcousticEnclosure

MPCB-CAC-00

0000

0058

MPCB-CAC-0000000058 (CAC Meeting Number : 8 dated August 6, 2019) Page 112 of 154

Whether any deviation in fuel consumptionand APC system observed compared toprevious consent

NO Remarks:

Compliance to existing unit in case appliedfor expansion C to E/O/R NO

Existing JVS results AirSr.no. Date of visit Board official's

name:Whether samplecollected or not:

Whether results areconfirming to standardsor not (Exceedingparameter with value)

1 NO NO

Compliance of Haz. Waste ConditionDetails of hazardous waste as applied

Sr. no Type of waste Category Quantity & UOM Treatment Disposal

1 5.1 Used /spent oil 5.1 36 Ton/Y NA Sale to AuthorisedParty

233.3 Discardedcontainers / barrels /liner

33.3 15000 Nos./Y ReturnableReturned to Supplierfor reuse/refillingafter decontamination

333.3 Discardedcontainers / barrels /liner

33.3 6 Ton/YDamaged/ TornPolythene Liners /Plastic Drums

CHWTSDF at MWMLTaloja

434.3 Chemical sludgefrom waste watertreatment

34.3 120 MT/A NA CHWTSDF at MWMLTaloja

5 NA NA 0 --NA-- NA NAWhether any deviation in Hz waste generation and itsdisposal,observed compared to previous consent NO Remarks:

Compliance of existing unit in case applied for expansion C to E/O/R NO

Submission of Annual Return (Form IV) NO Submission Date

Compliance of Non Hazardous/ MSW conditionDetails of Non hazardous/MSW as applied

Sr. no Type of waste Quantity & UOM Treatment Disposal1 Domestic Waste 50 Kg/Day NA To Civic Body Collection

2 Natural Soil Generated fromOre Processing 5000 MT/M NA Sale to Brick

Manufacturer

3 Coal Ash 25 Ton/D NA Sale to BrickManufacturer

Whether any deviation in Non-Hz waste generation and itsdisposal,observed compared to previous consent NO Remarks:

Compliance of existing unit in case applied for expansion C to E/O/R NOWaterCess Returns filed upto: Paid Upto: Jan 1 1900

12:00:00:000AMDirectionissued (ifany)

BGDetails Amount Validity

BG obtained towards complience ofa) Consent/CCA condition b) directions

1 Rs. 5 Lakh 30/11/2021 Compliance of Consent conditions NADetails of BGfortified/enchasedfor noncomplience,if any:Submission ofEnvironmentalStatement

NO Year Yes

Details of consentfee paid Amount Rs: 3,00,000/- Terms 5

In case of 1st C to OComplience of C toE conditions

Remarks

Recommendation ofTAC

MPCB-CAC-00

0000

0058

MPCB-CAC-0000000058 (CAC Meeting Number : 8 dated August 6, 2019) Page 113 of 154

Recommendations

Sagar V Auti (SRO-Mahad):-Pl process and submit.(Mar 20 2019 02:14:23:000PM)

Shri J. J. Kumbhar (FO-Mahad):-Industry has obtained Consent to Establish (Expansion) for mfg of 19 nos of synthetic organicchemicals vide consent letter dtd.25.7.2016, now applied applied for renewal of Consent withincorporation of additional products for 15 nos of synthetic organic chemicals. Existing consentwas valid upto 28.02.2019. Industry has obtained Environmental Clearance for the same videletter dtd. SEAC-2013/CR-242/TC-2 dtd. 28.1.2016. As per application for consent to operateI.E-1840 CMD & DE-18 CMD . For the treatment of industrial effluent industry has provided ETPcapacity 2000 M3/ Day consisting of Collection tank, Neutralization tank (02 Nos.), PrimaryClarifier, Bioreactor, Secondary clarifier, Holding tank (02 nos), Carbon filter & sand filter .Industry has not provided STPIndustry is having existing Boiler capacity 3 TPH provided dust collector & 8 TPH provided dustcollector & Bag filter as APC but as per C to E industry has not installed Boiler 21 TPH, 13 TPH,Thermic fluid heater-64 lakh Kcal& DG set 2000 KVA & 3000 KVA. Industry has provided dustcollector system to Ball Mill, SFD & conveying machine. Industry has submitted annual report ofHW 29.6.2018 & Env. Statement on 25.9.2018 through online. Industry has sent ETP sludge 2.0MT on 30.1.2019 to CHWTSDF. Industry is sending HW to CHWTSDF regularly. Coal Ash sent13 MT to Bricks manufacturer.Board had issued Voluntary Closure direction dtd. 19.1.2018 to the industry due to compliantreceived from MIDC Police station & Jite villagers regarding Blue color dust particlesspred/accumulated in Jite village area. In-spite of Voluntary Closure direction issued industryhas not stopped their manufacturing activities. There after Board has issued closure directiondtd.16.2.2018. Then industry has submitted their reply stated that found small perforation in oneBag at Spin Flash Dryer section which cause dusting on 6.1.2018. So industry has replaced all99 Nos. Bags filters at SFD section and also submitted the certificate of DISH approved vendorin connection to replacement of Bags & same was verified by Board Officer . Then Board officehad kept closure direction in Abeyance dtd.22.2.2018.Industry has submitted BG of Rs. 5.0 lacs towards compliance of consent conditions as perconsent to establish granted by Board which is valid upto 30.11.2021. As per consent toestablish condition no. 11. industry has provided separate pipeline from their premises up tooutlet of CETP i.e up to existing 6 MLD new separate sump. , Condition no. 12- A). Industry hasprovided online continues effluent monitoring system provided at oulet of ETP in their premises& same is connected to MPCB server. B) Industry has provided online continues effluentmonitoring system after ETP outlet before entering into MIDC sump. The application wasdiscussed in the CAC dtd 4.12.2018 & it was decided to defer the case and return the applicationto the industry for resubmission on the ground of leakage of low COD sump. Now MIDC hashanded over low COD sump to MMA CETP vide letter dtd. 06.3.2019.1. UAN No-0000011798 dtd. 14.8.2016 CI of unit 23.15 cr. Accordingly Industry had paidconsent fees of Rs. 2,50,000/- but this application was rejected by the Board. Processing fee wasapplicable Rs. 50,000/- & the balance fees with Board Rs. 2,00,000/- (A) .2. Industry has applied for C to R dtd. 31.3.2016 CI of unit was 78 cr. accordingly industry haspaid consent fees of Rs 2,25,000/- validity of consent 28.2.2019 then industry has applied forconsent to operate (part) and amalgamation with existing consent validity upto28.20.2019.UAN-0000025680 dtd. 27.9.2017 CI of unit was 78 cr accordingly industry has paidconsent fees of Rs. 1,75,000/- (Total fees paid Rs.4,00,000/-, As per consent fee slab feesapplicable was 3,25,000/- & fee balance with Board Rs. 75,000/- (B)3. Industry has applied for consent to 1st operate for part expansion and amalgamation withexisting consent to operate UAN no.00000(Apr 11 2019 03:31:21:000PM)

Sagar V Auti (SRO-Mahad):-Industry had obtained EC for their proposed expansion vide letter dated 28/01/16 from EnvtDepartment for mfg of synthetic organic chemicals and consent to establish for their proposedexpansion dated 25/07/16 with CI of Rs.34 Cr for mfg of synthetic organic chemicals .Thenindustry had obtained consent to 1st operate [part] with amalgamation of existing consent underRed/LSI category which was valid for a period up to 28/02/2019 with CI of Rs.78 Cr. Nowindustry has applied for renewal of consent to operate with increased CI of Rs.86.24 Cr.

Quantity of industrial effluent has increased from 1432 M3/day to 1840 M3/day. For treatmentof I.E. Full-fledged ETP of capacity 2000 M3/day is provided .Treated I.E. is connected to CETPfor further treatment and disposal. Industry has provided online monitoring system as per CETPprotocol & its connectivity to MPCB server. Industry is an existing member of CETP &CHWTSDF.HW form IV & Envt Statement etc are submitted.As per consent to establish condition no. 11; industry has provided separate dedicated pipelineof length 1558 RMT from their premises up to inlet of low COD sump at CETP i.e. up to existing6 MLD new separate MIDC sump.As per consent to establish Condition no. 12- a), industry has provided online continuous effluentmonitoring system provided at outlet of existing ETP in their premises & same is connected toMPCB server; and as per consent to establish Condition no. 12- b), industry has provided onlinecontinuous effluent monitoring system at CETP inlet. MIDC sump is repaired and there are noleakages from the sump and MIDC has handed over the said sump to CETP on 06/03/2019, copyof the MIDC letter is uploaded.Adequate APC system is provided to boilers, thermo pack & ball mill. Industry is having existingboiler of capacity 3 TPH provided with dust collector; 8 TPH boiler is provided with dustcollector & bag filter as APC system ; but as per C to E industry has not installed proposedBoiler of capacity 21 TPH, 13 TPH, Thermic fluid heater-64 lakh Kcal& DG set 2000 KVA & 3000KVA. Industry has provided dust collector system to Ball Mill, SFD & conveying machine etc.Scrubber to Alpha plant is provided.

Board had issued closure direction dtd.16.2.2018.Then Industry had replaced all 99 Nos. of bagsfilters at SFD section and also submitted the certificate of DISH approved vendor in connectionto replacement of bags & same was verified by Board Officer. Then Board office had keptclosure direction in Abeyance dtd.22.2.2018.Previously industry had submitted application for grant of first consent to operate for additionalproducts with UAN No.00000050198 dated 05/06/18 .The application was discussed in the CACmeeting held on 04/12/18 and it was decided to defer the case on the ground of leakages in thenew 6 MLD MIDC sump .Accordingly the application was returned back to industry vide ASTletter dated 20/12/18.Now industry has resubmitted application. Now MIDC sump is repairedand there are no leakages from the sump and MIDC has handed over the said sump to CETP on06/03/2019, copy of the MIDC letter is uploaded.Industry has submitted BG of Rs. 5.0 Lakh towards compliance of consent conditions as perconsent to establish granted by Board which is valid up to 30.11.2021; but BG of Rs. 5.0 Lakhtowards O&M of PCS as per existing consent is not submitted. As per existing consent schedule Icondition no.2 A], STP of capacity 20 M3/day is also not installed. Industry has paid consent feesfor five years terms.Therefore, decision about renewal of consent to operate under Red category with increasedcapital investment may be taken.

(Apr 12 2019 03:00:20:000PM)

Mr.P.K.Mirashe(AST) (CAC-CELL-HQ):-Pl Process and put up(Apr 12 2019 04:21:34:000PM)

MPCB-CAC-00

0000

0058

MPCB-CAC-0000000058 (CAC Meeting Number : 8 dated August 6, 2019) Page 114 of 154

Other RelevantInformation

1. Existing Red/LSI industry engaged in mfg. of Synthetic Organic Chemicals.

2. Industry had obtained C2O on 13/10/2016 (valid upto 28/02/2019) with C.I. of Rs. 41.05 Crs.for mfg. of products Pigment Beta-Activated - 150 MT/M & Pigment Blue - 150 MT/M.

3. Industry had obtained Consent to Establish on 25/07/2016 with C.I. of Rs. 34 Crs. forproposed expansion for mfg. of products Polymeric Additives/Polymers/ Polyurethanes/Adhesives- 2,000 MT/M, Pigment Concentrates/Pastes/Dispersions/Master Batches/Digitalinks1,000 MT/M, Pigment High Performance (Red,Yellow,Orange, Violet)-200 MT/M, Sulphates& Oxides of Aluminium, Copper, Iron, Manganese, Magnesium, Zinc, & Other Metals-5,000MT/M, Pearlescent Pigments-100 MT/M, Metal Powders/Pastes-300 MT/M, CopperPhthalocyanine Blue-1,000 MT/M, Pigment Green-7 - 100 MT/M, Pigment Blue-Activated- 150MT/M, Pigment Alpha Blue- 150 MT/M, Ethylene Oxide/Propylene Oxide Condensates &Derivatives- 2,000 MT/M, Mica Derivatives- 100 MT/M, Esters-1,000 MT/M, Amides-1,000 MT/M,Pigment Beta Blue-850 MT/M, Sodium/ Potassium Permangante-200 MT/M, Zinc Sulphate-300MT/M, Zinc Ingots-800 MT/M, & Aluminium Alloys-1,000 MT/M subject to the followingconditions:(i) Industry shall provide separate pipeline from their premises upto Outlet of CETP i.e. uptoexisting 6 MLD new separate sump so that treated effluent can be directly disposed into disposalpipeline of MIDC.(ii) Industry shall install online continuous effluent monitoring system at two locations (a) At theoutlet of ETP in their premises & (b) After CETP outlet before entering into MIDC sump. Thisonline monitoring data should be connected to CETP & MPCB data centre so that qualitative &quantities data will be displayed in CETP and MPCB for the online survillance and monitoring.

4. Industry had obtained Consent to 1st Operate (part) for part expansion and amalgamationwith existing C2O on 03/01/2018 (valid upto 28/02/2019) with C.I. of Rs. 78 Crs. for mfg. ofproducts- Pigment Blue- 150 MT/M, Pigment Blue (Activated)- 150 MT/M, Pigment Alpha Blue-150 MT/M, Ethylene Oxide/Propylene Oxide Condensates & Derivatives- 2,000 MT/M,Esters-1,000 MT/M, Amides-1,000 MT/M, Pigment Beta Blue-850 MT/M.

5. Industry's application UAN No. 0000050198 dtd. 05/06/2018 for grant of Consent to 1stOperate for full expansion and amalgamation with existing Consent to Operate was discussed inCAC meeting held on 04/12/2018 and it was decided to defer the case on the ground of leakagesin the new 6 MLD MIDC Sump. Accordingly, the application was returned back to industry videletter dtd. 20/12/2018.

6. Now, MIDC sump is repaired and there are no leakages from the sump and MIDC has handedover the said sump to CETP on 06/03/2019, copy of the MIDC letter is uploaded.

7. Industry has resubmitted its application for grant of Consent to 1st Operate for full expansion,renewal of existing Consent to Operate and amalgamation of two for mfg. of products PigmentAlpha Blue- 150 MT/M, Pigment Beta Blue/ Solvent Blue 67/ Basic Blue 140/ Direct Blue 199-850 MT/M, Polymeric Additives/Polymers/ Polyurethanes/ Adhesives- 2,000 MT/M, PigmentConcentrates/Pastes/Dispersions/Master Batches/Digital inks- 1,000 MT/M, Pigment HighPerformance (Red,Yellow,Orange, Violet)-200 MT/M, Inorganic Metal Salts like Sulphates,Acetates, Phosphates, Oxides etc. of Aluminium, Copper, Iron, Manganese, Magnesium, Zinc,Potassium, Calcium, Cobalt, Nickel, SSP & Various other metals-5,000 MT/M, PearlescentPigments-100 MT/M, Pigment Blue Activated- 300 MT/M, Metal Powders/Pastes-300 MT/M,Copper Phthalocyanine Blue Crude-1,000 MT/M, Ethylene Oxide/ Propylene Oxide Condensatesand Derivatives-2,000 MT/M, CPC Green-7 - 100 MT/M, Esters/ Micronised Waxes/ Defoamers/Flame Retardants- 1,000 MT/M, Amides/ Tackifiers/ Mold Release Agents- 1,000 MT/M,Aluminium Alloys/flakes/po wder ( Metal Alloys/Flakes/po wder of Aluminium , Nickel, Copper,Zinc, Stainless Steel, etc.)- 1,000 MT/M.

Also, applied for mfg. of by-products-Ammonium Sulphate/ Calcium Sulphate- 2,700 MT/M, PAC/Aluminium Chloride (8-10% solution)-1,000 MT/M, Hydrochloric Acid (20-25%)- 75 MT/M, LiquorAmmonia (20% solution)-1,600 MT/M, Hypo (NaOCl) 10% solution- 400 MT/M, Monovalent/Divalent Metal Salts (Chloride/ Sulphates/ Nitrates/ Acetates)-1,500 MT/M & Spent SulphuricAcid (20%)- 5,250 MT/M.

8. For the treatment of 1,845 CMD of industrial effluent, industry has provided ETP of designedcapacity 2,000 CMD consisting of Collection tank, Neutralisation tank (02 Nos.), Primary tank,Bioreactor, secondary tank, Holding tank (02 nos), Carbon filter & sand filter.

9. As per consent to establish condition no. 11; industry has provided separate dedicatedpipeline of length 1,558 mtrs. from their premises up to outlet treated effluent sump of CETP i.e.up to existing 6 MLD new separate MIDC sump.

SRO has reported that as per consent to establish Condition no. 12- a) industry has providedonline continuous effluent monitoring system at outlet of existing ETP in their premises & sameis connected to MPCB server; and as per consent to establish Condition no. 12- b), industry hasprovided online continuous effluent monitoring system after ETP before entering into MIDCSump.

MIDC sump is repaired and there are no leakages from the sump and MIDC has handed over thesaid sump to CETP on 06/03/2019, copy of the MIDC letter is uploaded.

10. Online monitoring data including flow is not connected to CPCB & MPCB Server.

MPCB-CAC-00

0000

0058

MPCB-CAC-0000000058 (CAC Meeting Number : 8 dated August 6, 2019) Page 115 of 154

Recommendation ofCAC/CC Cell

-Applied for grant of grant of Consent to 1st Operate for full expansion, renewal of existingConsent to Operate and amalgamation of two for mfg. of products Dyes & Dye intermediates,Pigment products.

-Obtained EC & C2E which are valid.

-Provided ETP of designed capacity 2,000 CMD consisting of Collection tank, Neutralisation tank(02 Nos.), Primary tank, Bioreactor, secondary tank, Holding tank (02 nos), Carbon filter & sandfilter for the treatment of 1,845 CMD of industrial effluent.

-As per consent to establish condition no. 11; industry has provided separate dedicated pipelineof length 1,558 mtrs. from their premises up to outlet treated effluent sump of CETP i.e. up toexisting 6 MLD new separate MIDC sump.

-As per consent to establish Condition no. 12- a) industry has provided online continuous effluentmonitoring system at outlet of existing ETP in their premises; and as per consent to establishCondition no. 12- b) industry has provided online continuous effluent monitoring system afterETP before entering into MIDC Sump.

-MIDC sump is repaired and there are no leakages from the sump and MIDC has handed overthe said sump to CETP on 06/03/2019, copy of the MIDC letter is uploaded.

-Online monitoring data was not connected to MPCB Server. Follow-up was taken up with theCompany Authority via e-mail on 06/05/2019, 20/05/2019, 07/06/2019 & 24/06/2019 and theywere asked to connect online CMS data to MPCB Server.

Company Authority via e-mail dtd. 03/07/2019 informed about connectivity of online CMS data toMPCB Server which was verified from Data Center at HQ.

Data Center Staff informed that transmission of online monitoring data was stopped from 3:00a.m. on 04/07/2019.

From the Data Center record, it is observed that industry has discharged excess effluent on02/07/2019 (3,966 CMD) & on 03/07/2019 (2,504.5 CMD) against that permitted in Consent toOperate (1,432 CMD).

As the online monitoring data is not connected to MPCB Server and industry has violatedConsent conditions by discharging excess effluent to CETP's outlet sump, we may call the PP forpresentation about adequacy of ETP provided and status of connectivity of online monitoringdata to MPCB Server.

ConsentRecommended forperiod upto as perSectoral Approachpolicy

--

MPCB-CAC-00

0000

0058

MPCB-CAC-0000000058 (CAC Meeting Number : 8 dated August 6, 2019) Page 116 of 154

ITEM NO: 24 - Unique Number: MPCB-CONSENT-0000069059Fresh CAC ITEMRegion: SRO - Kolhapur Section: CAC Date:UAN Number: MPCB-CONSENT-0000069059 TAG CACName & Address: Kirloskar Oil Engines Limited (Plot No. D-1, FIve Star MIDC Kagal Hatkanangale)Location ofIndustrial unit: D-1 Five Star MIDC Kagal-Hatkanangale Hatkanangale

Email: [email protected] Telephone number: 9881721324Industry Type:Industry Category: REDProject Details: Existing project

Consent Applied For 1st Operate withamalgamation Application Date March

14,2019Date of receipt ofCAC/CC cell 22/05/2019

Capital Investment in Rs. (Crs)Existing Proposed Total

824.23 22.69 846.92Details of

project :Existingproject

Total Plot area(sq.m.) 650900 (sq.m) Construction

BUA (sq.m.)160389.23(sq.m)

Product and By-product detailsSr.no Product Name Quantity

1 Storage of spare parts for engine shifting,metallic skids etc. 0 --NA--

2 I.C. Engines 10000 No/M3 Generating Sets 1625 No/M4 Pump sets 8000 No/M

5 Engine, Genset, Pump set machined spareparts 70000 No/M

6 Solar Power Generation Plant 5.5 MW7 Fuel Oil from plastic waste 75 Lit/DaySr.no By-Product Name Quantity8 Not Applicable 0Applicabilty

ofCRZ

ClearenceDistance

from riverIndustrial

location policy Eco-sensitive Moratonium EC Direction of MoEF forwestern ghats

NO YES NO NO NO NO NO

If Yesprovidedetails

Dudhganga -20.00 Km

Basedon:

Status:NotApplied

Details of CCA,Consents,Authorization and EC obtained Consent no. Consent

granted date ValidityCapital

Investmentin Crs

Total plotarea

ConstructionBUA

(FSI+Non-FSI)Remarks

C2EBO/CAC-Cell/UAN

No:-0000049606-18/6thCAC/18120017160

28.12.2018 COU 0.32

C2E BO/CAC-Cell/UANNo:-0000048336-18/CAC/1808000621 14.08.2018 28.02.2020 824.23

Existing production details

C to O

Sr.No Product Name Max quantity

1 I.C. Engines 10000 No/M

2 Generating Sets 1625 No/M

3 Pump sets 8000 No/M

4 Engine, Genset, Pump set machined spare parts 70000 No/M

5 Solar Power Generation Plant 5.5 MW

6 Storage of spare parts for engine shifting, metallic skids etc. -

C to ESr.No Product Name Max quantity

1 Fuel Oil from plastic waste 75 Lit/Day

Bio-Medical Waste Details

MPCB-CAC-00

0000

0058

MPCB-CAC-0000000058 (CAC Meeting Number : 8 dated August 6, 2019) Page 117 of 154

Annual Rpt.(Form-II):Accident Rpt.(Form-III):

BMWGeneration

Sr.No Category Max quantity (Kg/M)

1 NA NA

Disposal @CBMWTF: No

Member ofCBMWTF:CaptiveDisposal: No

Incinerator Capacity Fuel Type Auto Feeding Temp.Recorder Online Monitoring

Autoclave Type(Vertical/Horizontal)

Temp &Pressure

Recording

Shredder Plastic WasteDisposal

Compliance of Water Pollution Related Conditions Purpose Water Consumption

in CMD as appliedEffluent generationas applied in CMD

TreatmentSteps

DisposalDetails

Remarks/Adequeteland Available

1 Domestic Purposes 208.5 187.5 STPOn Land

forGardening

Combined ETP forprimary treated

industrial effluent &domestic sewage is

provided

2Processing wherebywater gets polluted &pollutants are easilybiodegradable

0 0 --NA-- --NA-- Not Applicable

3Processing wherebywater gets polluted &pollutants are noteasily biodegradable

125 115 PrimaryOn Land

forGardening

Combined ETP

4IndustrialCooling,spraying inmine pits or boilerfeed

121 0 --NA-- --NA-- Not Applicable

5Others such asgardening,agricultureetc

Washing 20 M3/Day NA NA NA NA

Whether any deviation in water consumption observed compared toprevious consent NO Remarks:

Compliance to existing unit in case applied for expansion C to E/O/R NOSource of water supply

In case proposed discharge to CETP forfurther treatment

CETP Capacity to handle additional load NOName of CETP

Existing JVS results EffluentSr.no. Date of visit Board official's

name:Whether samplecollected or not:

Whether results areconfirming to standardsor not (Exceedingparameter with value)

1 NO NO

Details of fuel consumption and APC system as applied :-Sr. no Source Stack Fuel type Quantity Height-I,II,III APC system

detail

1 ME test bed S-1 HSD 50 (Kg/hr.) 33 mExhaustSilencer, di?userprovided.

2 Standby DG Sets S-2a HSD 83 (Kg/hr.) 13 mExhaustSilencer, di?userprovided

3 Standby DG Sets S-2b HSD 83 (Kg/hr.) 13 mExhaustSilencer, di?userprovided

MPCB-CAC-00

0000

0058

MPCB-CAC-0000000058 (CAC Meeting Number : 8 dated August 6, 2019) Page 118 of 154

4 Standby DG Sets S-2c HSD 83 (Kg/hr.) 13 mExhaustSilencer, di?userprovided

5 Standby DG Sets S-3a HSD 83 (Kg/hr.) 13 mExhaustSilencer, di?userprovided

6 Standby DG Sets S-3b HSD 83 (Kg/hr.) 13 mExhaustSilencer, di?userprovided

7 Standby DG Sets S-3c HSD 83 (Kg/hr.) 13 mExhaustSilencer, di?userprovided

8 Standby DG Sets S-3d HSD 83 (Kg/hr.) 13 mExhaustSilencer, di?userprovided

9 Genset Test Bed S-4 HSD 45 (Kg/hr.) 33 m

ExhaustSilencer,di?user, acousticenclosure insidetest bedsprovided

10 Thermic Fluidheater S-5 LPG 1250 (Kg/hr.) 11 m Exhaust Blower

11 Varsha Pumpsettest bed S-6 HSD 1 (Kg/hr.) 33 m

ExhaustSilencer, di?userprovided

12 SE Test bed S-7 HSD 17 (Kg/hr.) 33 m

ExhaustSilencer,di?user, acousticenclosure insidetest bedprovided

13 Standby DG Sets S-8 HSD 416 (Kg/hr.) 52 m Acoustic roomfor DG set

14 ME paint Booth S-10 HSD, Plasticderived fuel 4.16 (Kg/hr.) 11 m

Water Curtainsfor scrubbingpaint emissions

15 ME paint Booth S-11 N.A. 0 (Kg/hr.) 11 mWater Curtainsfor scrubbingpaint emissions

16 ME paint Booth S-11a N.A. 0 (Kg/hr.) 11 mWater Curtainsfor scrubbingpaint emissions

17 ME paint Booth S-11b N.A. 0 (Kg/hr.) 11 mWater Curtainsfor scrubbingpaint emissions

18 ME paint Booth S-11c N.A. 0 (Kg/hr.) 11 mWater Curtainsfor scrubbingpaint emissions

19 ME paint Booth S-11d N.A. 0 (Kg/hr.) 11 mWater Curtainsfor scrubbingpaint emissions

20 ME paint Booth S-11e N.A. 0 (Kg/hr.) 11 mWater Curtainsfor scrubbingpaint emissions

21 ME paint Booth S-11f N.A. 0 (Kg/hr.) 11 mWater Curtainsfor scrubbingpaint emissions

22 ME paint Booth S-11g N.A. 0 (Kg/hr.) 11 mWater Curtainsfor scrubbingpaint emissions

23 ME paint Booth S-12 HSD 4.16 (Kg/hr.) 11 mWater Curtainsfor scrubbingpaint emissions

24 Varsha paintBooth S-13a N.A. 0 (Kg/hr.) 11 m

Water Curtainsfor scrubbingpaint emissions

25 Varsha paintBooth S-13b N.A. 0 (Kg/hr.) 11 m

Water Curtainsfor scrubbingpaint emissions

MPCB-CAC-00

0000

0058

MPCB-CAC-0000000058 (CAC Meeting Number : 8 dated August 6, 2019) Page 119 of 154

26 Varsha paintBooth S-13c N.A. 0 (Kg/hr.) 11 m

Water Curtainsfor scrubbingpaint emissions

27 Varsha paintBooth S-13d N.A. 0 (Kg/hr.) 11 m

Water Curtainsfor scrubbingpaint emissions

28 Varsha paintBooth S-14 HSD 5 (Kg/hr.) 11 m

Water Curtainsfor scrubbingpaint emissions

29 SE paint Booth S-15 N.A. 0 (Kg/hr.) 10 mWater Curtainsfor scrubbingpaint emissions

30Fire Hydrantpump drivingmachine

S-17 HSD 12.5 (Kg/hr.) 10 mExhaustSilencer, di?userprovided.

31Pretreatmentarea at powdercoating

S-18 N.A. 0 (Kg/hr.) 15 m Exhaust Blower

32Pretreatmentarea at powdercoating

S-19 N.A. 0 (Kg/hr.) 15 m Exhaust Blower

33Pretreatmentarea at powdercoating

S-20 N.A. 0 (Kg/hr.) 15 mExhaust Blower,Bag filterprovided

34 Genset TestBeds S-21 HSD 125 (Kg/hr.) 14 m

ExhaustSilencer, di?userprovided.

35 Genset TestBeds S-22 HSD 125 (Kg/hr.) 14 m

ExhaustSilencer, di?userprovided

36 Standby Genset S-23 HSD 13 (Kg/hr.) 13 mExhaustSilencer, di?userprovided

37 Standby Genset S-24 HSD 85 (Kg/hr.) 10 mExhaustSilencer, di?userprovided

38 Standby Genset S-25 HSD 85 (Kg/hr.) 10 mExhaustSilencer, di?userprovided

39 Standby Genset S-26 HSD 85 (Kg/hr.) 11 mExhaustSilencer, di?userprovided

40 DV Test beds S-27 HSD 100 (Kg/hr.) 14 mExhaustSilencer, di?userprovided

41 DV Paint Booth S-28 N.A. 0 (Kg/hr.) 10 mWater Curtainsfor scrubbingpaint emissions

42 DV Paint Booth S-29 N.A. 0 (Kg/hr.) 10 mWater Curtainsfor scrubbingpaint emissions

43 DV Test Bed No.2 S-30 HSD 100 (Kg/hr.) 14 m

ExhaustSilencer, di?userprovided

44 HA6 EngineTest Beds S-31 HSD 50 (Kg/hr.) 14 m

ExhaustSilencer, di?userprovided

45 HA6 EngineTest Beds S-32 HSD 50 (Kg/hr.) 14 m

ExhaustSilencer, di?userprovided

46 HA6 EngineTest Beds S-33 HSD 50 (Kg/hr.) 14 m

ExhaustSilencer, di?userprovided

47 6R Engine TestBeds S-34 HSD 75 (Kg/hr.) 14 m

ExhaustSilencer, di?userprovided

48 6R Engine TestBed S-35 HSD 75 (Kg/hr.) 14 m

ExhaustSilencer, di?userprovided

MPCB-CAC-00

0000

0058

MPCB-CAC-0000000058 (CAC Meeting Number : 8 dated August 6, 2019) Page 120 of 154

49 6R Engine TestBed S-36 HSD 75 (Kg/hr.) 14 m

ExhaustSilencer, di?userprovided

50 Genset TestBeds S-37 HSD 75 (Kg/hr.) 14 m

ExhaustSilencer, di?userprovided

51 SL-90 EngineTest Bed S-38 HSD 75 (Kg/hr.) 14 m

ExhaustSilencer, di?userprovided

52 SL-90 EngineTest Bed S-39 HSD 75 (Kg/hr.) 14 m

ExhaustSilencer, di?userprovided

53 Kitchen Boiler S-40 LPG, Steam 5 (Kg/hr.) 6 m N.A.

54 SL-90 PaintBooth S-41 N.A. 0 (Kg/hr.) 14 m

Water Curtainsfor scrubbingpaint emissions

55 SL-90 PaintBooth S-42 N.A. 0 (Kg/hr.) 14 m

Water Curtainsfor scrubbingpaint emissions

56 SL-90 PaintBooth S-43 N.A. 0 (Kg/hr.) 14 m

Water Curtainsfor scrubbingpaint emissions

57 1010 KVAGenset Test Bed S-44 HSD 100 (Kg/hr.) 21 m

ExhaustSilencer, di?userprovided

58 1010 KVAGenset Test Bed S-45 HSD 100 (Kg/hr.) 21 m

ExhaustSilencer, di?userprovided

59 Standby Genset S-46 HSD 30 (Kg/hr.) 11 mExhaustSilencer, di?userprovided

60 Standby Genset S-47 HSD 30 (Kg/hr.) 14 mExhaustSilencer, di?userprovided

61 ReactorScrubber S-48

HSD (one timetostart)/processedliquid

20 (Kg/hr.) 2m above roof m Wet scrubber

62 ReactorScrubber S-49

HSD (one timetostart)/processedliquid

20 (Kg/hr.) 2m above roof m wet scrubber

Whether any deviation in fuel consumptionand APC system observed compared toprevious consent

NO Remarks:

Compliance to existing unit in case appliedfor expansion C to E/O/R NO

Existing JVS results AirSr.no. Date of visit Board official's

name:Whether samplecollected or not:

Whether results areconfirming to standardsor not (Exceedingparameter with value)

1 NO NO

Compliance of Haz. Waste ConditionDetails of hazardous waste as applied

Sr. no Type of waste Category Quantity &UOM Treatment Disposal

1 5.1 Used or spent oil 5.1 7.0 KL/D N.A. To authorized oil reprocessor

2 5.2 Wastes or residuescontaining oil 5.2 5 MT/M N.A. Co-processing/CHWTSDF

3 5.2 Wastes or residuescontaining oil 5.2 1600 Kg/M N.A. To CHWTSDF

4 12.5 Phosphate sludge 12.5 7600 Kg/M N.A. Co-processing/CHWTSDF

MPCB-CAC-00

0000

0058

MPCB-CAC-0000000058 (CAC Meeting Number : 8 dated August 6, 2019) Page 121 of 154

5

20.1 Contaminatedaromatic, aliphatic ornapthenic solvents mayor may not be fit forreuse.

20.1 0.20 MT/M N.A. CHWTSDF

6 21.1 Process wastes,residues and sludges 21.1 20.7 MT/M Sludge

centrifuge Co-processing/CHWTSDF

7 21.1 Process wastes,residues and sludges 21.1 2030 Kg/M N.A. CHWTSDF

8 21.1 Process wastes,residues and sludges 21.1 1030 Kg/M N.A. CHWTSDF

9 21.1 Process wastes,residues and sludges 21.1 700 Kg/Annum N.A. CHWTSDF

10 21.1 Process wastes,residues and sludges 21.1 2 MT/A N.A. CHWTSDF

11

33.1 Emptybarrels/containers/linerscontaminated withhazardous chemicals/wastes

33.1 1500 Kg/M N.A. CHWTSDF

12

33.1 Emptybarrels/containers/linerscontaminated withhazardous chemicals/wastes

33.1 1550 No/M N.A. To CHWTSDF/Authorisedrecycler

13

33.1 Emptybarrels/containers/linerscontaminated withhazardous chemicals/wastes

33.1 900 No/M N.A. To CHWTSDF/Authorisedrecycler

14

34.2 Sludge fromtreatment of wastewater arising out ofcleaning / disposal ofbarrels / containers

34.2 46 MT/M filter press fordrying Co-processing/CHWTSDF

15 Other Hazardous Waste Other 1500 Kg/M N.A. To common e-wasteprocessing facility

16 Other Hazardous Waste Other 800 Kg/M N.A. Authorised recycler17 Other Hazardous Waste Other 210 Kg/M N.A. Authorised recycler18 NA NA 0 --NA-- NA NAWhether any deviation in Hz waste generation and itsdisposal,observed compared to previous consent NO Remarks:

Compliance of existing unit in case applied for expansion C to E/O/R NO

Submission of Annual Return (Form IV) NO Submission Date

Compliance of Non Hazardous/ MSW conditionDetails of Non hazardous/MSW as applied

Sr. no Type of waste Quantity & UOM Treatment Disposal

1 Black Ash from Plastic to fuelplant 10 Kg/Day N.A. Disposal to authorized

agency2 Bio-sludge from STP 500 Kg/M N.A. Used as manure

3 Canteen Waste 15000 Kg/M N.A. Processing to BiogasPlant

4 Metal Scrap 480 MT/M N.A. Sale to MPCB approvedagency

5 Garbage 94 MT/M N.A. Sale to MPCB approvedagency

6 Wooden scrap 156.26 MT/M N.A. Sale to MPCB approvedagency

7 Rubber plastics 128 MT/M N.A. Sale to MPCB approvedagency

8 Waste corrugated boxdes 63 MT/M N.A. Sale to MPCB approvedagency

9 Cotton waste 1.5 MT/M N.A. Sale to MPCB approvedagency

10 Grinding Dust 24 MT/M N.A. Sale to MPCB approvedagency

MPCB-CAC-00

0000

0058

MPCB-CAC-0000000058 (CAC Meeting Number : 8 dated August 6, 2019) Page 122 of 154

11 Sheet Scrap 5 MT/M N.A. Sale to MPCB approvedagency

12 Empty Barrels/Containers 44000 No/M N.A. Sale to MPCB approvedagency

13 Waste Welding Glass 200 No/M N.A. Sale to MPCB approvedagency

Whether any deviation in Non-Hz waste generation and itsdisposal,observed compared to previous consent NO Remarks:

Compliance of existing unit in case applied for expansion C to E/O/R NOWaterCess Returns filed upto: Paid Upto: Sep 30 2015

12:00:00:000AMDirectionissued (ifany)

BGDetails Amount Validity

BG obtained towards complience ofa) Consent/CCA condition b) directions

1 NA NA NA NADetails of BGfortified/enchasedfor noncomplience,if any:Submission ofEnvironmentalStatement

NO Year Submitted on 22.09.2018 FY2017-18

Details of consentfee paid Amount Rs: 50000 Terms 1

In case of 1st C to OComplience of C toE conditions

Remarks

Recommendation ofTAC

Recommendations

Prashant Gaikwad (SRO-Kolhapur):-Process & Put up.(Mar 28 2019 04:32:08:000PM)

Shri. Avinash Kadale (FO-Kolhapur):-Applied for 1st Consent to operate for Waste plastic to fuel plant. Industry has already obtainedC to E for said activity vide Boards consent dtd. 28/12/2018 (Copy attached). The manufacturingprocess will be consisting of Shredding of plastics-pyrolysis- Condensation, cooling -Filtration-Gas scrubbing. Trade and domestic effluent generation will be nil for this expansion. Also HWgeneration will be nil. Industry has provided two reactor scrubber process units for thisexpansion and both are provided with wet scrubber & stacks of 2 meter height (above roof)each. - Details attached. Scrubber effluent will be recycled back to max extent. Non hazardouswaste generation will be in the form of black ash and same will be disposed to brickmanufacturers. Total CI of this expansion is Rs. 2269 lakhs for which industry has paid consentfees of Rs. 50,000/- (one term fee). Scrutiny mail sent for seeking information aboutEnvironment Statement of existing plant, HW Annual returns submitted, self monitoring reportsetc. Reply is awaited. In view of above case is submitted for further decision please.(May 22 2019 02:09:38:000PM)

Prashant Gaikwad (SRO-Kolhapur):-Applied for consent to operate. Have obtained consent to Establish for Plastic Waste Pyrolysisactivity. The existing unit is having valid consent upto 28/2/2020 for manufacturing of Engines,Gensets, Pumps. The industrial effluent from the pyrolysis activity is NIL, the gas scrubbingsystem is provided to the reactors and uncondensed gas will be scrubbed and reused forheating. The black ash in form of non hazardous will be disposed off to brick manufacturers. Theplastic pyrolysis plant will be used for captive purpose for disposal of plastic waste generated byunits of Kirloskar oil Engines ltd., the grant of consent to operate may be considered, i approved.Submitted please.(May 22 2019 03:45:04:000PM)

Mr.P.K.Mirashe(AST) (CAC-CELL-HQ):-Pl process and put up(May 22 2019 03:55:39:000PM)

MPCB-CAC-00

0000

0058

MPCB-CAC-0000000058 (CAC Meeting Number : 8 dated August 6, 2019) Page 123 of 154

Other RelevantInformation

SRO-Kolhapur has reported that:-1. The unit has obtained consent to Establish for Plastic Waste Pyrolysis activity and haveapplied for 1st consent to operate.2. The existing unit is having valid consent upto 28/2/2020 for manufacturing of Engines,Gensets, Pumps.3. The industrial effluent from the pyrolysis activity is NIL, the gas scrubbing system is providedto the reactors and uncondensed gas will be scrubbed and reused for heating.4. The black ash in form of non hazardous will be disposed off to brick manufacturers.5. The plastic pyrolysis plant will be used for captive purpose for disposal of plastic wastegenerated by units of Kirloskar oil Engines ltd., the grant of consent to operate may beconsidered, i approved. Submitted please.

Recommendation ofCAC/CC Cell

We may consider the case for 1st consent to Operate for Fuel Oil from Plastic waste andamalgamation with existing consent for engines, Gensets, Pumps by imposing followingconditions.

1. This consent is issued with overriding effect over previous consent no. BO/CAC-Cell/UAN.48336-18/CAC-1808000621 dated 14.08.2018 which is valid upto 28.02.2020.

ConsentRecommended forperiod upto as perSectoral Approachpolicy

28.02.2020

MPCB-CAC-00

0000

0058

MPCB-CAC-0000000058 (CAC Meeting Number : 8 dated August 6, 2019) Page 124 of 154

ITEM NO: 25 - Unique Number: MPCB-CONSENT-0000068936Fresh CAC ITEMRegion: SRO - Jalgaon Section: CAC Date: 19.07.2019UAN Number: MPCB-CONSENT-0000068936 TAG CAC

Name & Address: Jalgaon Jilha Sahakari Dudh Utpadak Sangh Maryadit (Post Box no. 32, Shivaji Nagar Raod,Jalgaon)

Location ofIndustrial unit:

S No. 304/2, 305, 306, 307/2, 308, 322-324 Main Dairy Plant, Shivaji Nagar Road, Near SuratRailway Gate Jalgaon

Email: [email protected] Telephone number: 9168034821Industry Type: R16 Milk processes and dairy products(integrated project)Industry Category: REDProject Details: Expansion in existing project

Consent Applied ForConsent to Establish

for additional productswith increase in CI

Application Date March13,2019

Date of receipt ofCAC/CC cell 25.06.2019

Capital Investment in Rs. (Crs)Existing Proposed Total

Rs.23.55 Crs Rs. 75.0 Crs Rs. 93.55 CrsDetails of

project :Expansion inexisting project

Total Plot area(sq.m.) 153300 (sq.m) Construction

BUA (sq.m.) 9580 (sq.m)Product and By-product details

Sr.no Product Name Quantity1 Dahi 2000 Kg/Day2 Khawa 2000 Kg/Day3 Butter 0 MT/Day4 Milk Powder 0 MT/Day5 Ghee 0 MT/Day6 Shrikhand 0 MT/Day7 Paneer 0 MT/Day8 Flavoured Milk 2000 Lit/Day9 Lassi 7000 Lit/Day10 Buttermilk 50000 Lit/Day11 Pasterized Milk 150000 Lit/DaySr.no By-Product Name Quantity12 --NA-- 0Applicabilty

ofCRZ

ClearenceDistance

from riverIndustrial

location policy Eco-sensitive Moratonium EC Direction of MoEF forwestern ghats

NO YES NO NO NO NO NO

If Yesprovidedetails

Girna - 6.00Km

Basedon:

Status:NotApplied

Details of CCA,Consents,Authorization and EC obtained Consent no. Consent

granted date ValidityCapital

Investmentin Crs

Total plotarea

ConstructionBUA

(FSI+Non-FSI)Remarks

C2O BO/JD(WPC)/UANNo.22254/R/HOD-1712000250 07.12.2017 30.04.2022 Rs.23.55

Crs

MPCB-CAC-00

0000

0058

MPCB-CAC-0000000058 (CAC Meeting Number : 8 dated August 6, 2019) Page 125 of 154

Existing production details

C to O

Sr.No Product Name Max quantity

1 Butter 15 MT/Day

2 Milk Powder 15 MT/Day

3 Ghee 5. MT/Day

4 Shreekhand 0.5 MT/Day

5 Paneer 0.5 MT/Day

6 Pasteurized Milk 2,50,000 Ltrs/Day

C to ESr.No Product Name Max quantity

1 NA NA

Bio-Medical Waste DetailsAnnual Rpt.(Form-II): NA

Accident Rpt.(Form-III):

BMWGeneration

Sr.No Category Max quantity (Kg/M)

1 NA NA

Disposal @CBMWTF: No

Member ofCBMWTF:CaptiveDisposal: No

Incinerator Capacity Fuel Type Auto Feeding Temp.Recorder Online Monitoring

NA

Autoclave Type(Vertical/Horizontal)

Temp &Pressure

Recording

Shredder Plastic WasteDisposal

Compliance of Water Pollution Related Conditions Purpose Water Consumption

in CMD as appliedEffluent generationas applied in CMD

TreatmentSteps

DisposalDetails

Remarks/Adequeteland Available

1 Domestic Purposes 20 16SepticTank &Soak Pit

Others

2Processing wherebywater gets polluted &pollutants are easilybiodegradable

750 750Primary +Secondary+ Tertiary

On Landfor

Gardening

3Processing wherebywater gets polluted &pollutants are noteasily biodegradable

0 0 --NA-- --NA--

4IndustrialCooling,spraying inmine pits or boilerfeed

150 2 OTHERSOn Land

forGardening

5Others such asgardening,agricultureetc

0 NA NA NA NA

Whether any deviation in water consumption observed compared toprevious consent YES

Remarks:Increase in water consumption and effluent generation by

300 CMDCompliance to existing unit in case applied for expansion C to E/O/R NOSource of water supply

In case proposed discharge to CETP forfurther treatment

CETP Capacity to handle additional load NOName of CETP

Existing JVS results EffluentSr.no. Date of visit Board official's

name:Whether samplecollected or not:

Whether results areconfirming to standardsor not (Exceedingparameter with value)

MPCB-CAC-00

0000

0058

MPCB-CAC-0000000058 (CAC Meeting Number : 8 dated August 6, 2019) Page 126 of 154

1 23.03.2019 [ ETP outlet] YES

NOBOD-84 mg/l against 30,COD-280 mg/l against 250,SS-131 against-100, andChlorides -890 against-600

1 21.01.2019 [ ETP outlet] YES

NOBOD-90 mg/l against 30,COD-272 mg/l against 250,SS-111 against-100, andChlorides -780 against-600

Details of fuel consumption and APC system as applied :-Sr. no Source Stack Fuel type Quantity Height-I,II,III APC system

detail

1 DG SET (Not Yetin Operation) 1 HSD 0 (Kg/hr.) 12.50 M m Accoustic

EnclosuresWhether any deviation in fuel consumptionand APC system observed compared toprevious consent

NO Remarks:

Compliance to existing unit in case appliedfor expansion C to E/O/R NO

Existing JVS results AirSr.no. Date of visit Board official's

name:Whether samplecollected or not:

Whether results areconfirming to standardsor not (Exceedingparameter with value)

1 21.01.2019 [ Boiler-1] YESNOTPM- 213 against-150mg/Nm3 and SO2-50.40against-24 Kg/Day

2 21.01.2019 [ Boiler] YESNOTPM- 241 against-150mg/Nm3 and SO2-55.20against-24 Kg/Day

3 05.12.2018 [ Boiler-3 ] YESNOTPM- 202 against-150mg/Nm3

4 05.12.2018 [ Boiler-4 ] YESYESTPM- 161 against-150mg/Nm3

5 10.12.218 [ AAQM- 24Hrs AVG ] YES NO

RSPM-345 Ug/Nm36 21.01.2019 [ 8 Hrs] YES YES

Compliance of Haz. Waste ConditionDetails of hazardous waste as applied

Sr. no Type of waste Category Quantity & UOM Treatment Disposal

1 5.1 Used or spentoil 5.1 5 Lit/Day Recycling

Sent To Hazardouswaste recycler (AmolOils, Jalgaon)

2 NA NA 0 --NA-- NA NAWhether any deviation in Hz waste generation and itsdisposal,observed compared to previous consent NO Remarks:

Compliance of existing unit in case applied for expansion C to E/O/R NO

Submission of Annual Return (Form IV) NO Submission Date

Compliance of Non Hazardous/ MSW conditionDetails of Non hazardous/MSW as applied

Sr. no Type of waste Quantity & UOM Treatment Disposal

1 Dry sludge obtained from ETPsludge drying beds 500 Kg/Day NA

Used as manure tospread on open land orto give farmers nearby

2 Agrowaste Briquettes ash 2 MT/Day NA Given to Bricksmanufacturer

Whether any deviation in Non-Hz waste generation and itsdisposal,observed compared to previous consent NO Remarks:

Compliance of existing unit in case applied for expansion C to E/O/R NO

MPCB-CAC-00

0000

0058

MPCB-CAC-0000000058 (CAC Meeting Number : 8 dated August 6, 2019) Page 127 of 154

WaterCess Returns filed upto: Paid Upto: Jan 1 1900

12:00:00:000AMDirectionissued (ifany)

BGDetails Amount Validity

BG obtained towards complience ofa) Consent/CCA condition b) directions

1 Rs.5.0 Lakhs 31.08.2022Towards operation andMaintenance of pollution controlsystem

NA

Details of BGfortified/enchasedfor noncomplience,if any:

No

Submission ofEnvironmentalStatement

NO Year 28/09/18

Details of consentfee paid Amount Rs: 100000 Terms 1

In case of 1st C to OComplience of C toE conditions

Remarks

Recommendation ofTAC

Recommendations

Shri S. M. Kurmude. (SRO-Jalgaon):-Plz. Visit, Process & p/u. If scrutiny letter is issued, application shall be submitted after the replyof the same.(Mar 26 2019 09:58:36:000AM)

Dr. Prabhakar N. Wavde (FO-Jalgaon):-(1) Industry has applied for consent to establish (expansion) with requisite fee. Consent is validup to 30-4-2022 for the manufacturing of Pasteurized milk (250000 L/D) and other milkproducts. Now applied for expansion in production of Pasteurized milk (150000 L/D) andaddition of new milk products dahi, Khawa, flavored milk, lassi and buttermilk. Industry wasvisited on 5-4-2019, visit report enclosed.(2) Industrial effluent generation is about 450 CMD at present, expansion project will addanother 300 CMD effluent. ETP of capacity 1000 CMD is provided and found in operation duringvisit. ETP consisting of collection cum primary settling tank, aeration tank, clarifier, sludgedrying beds and final storage tank. Treated effluent is utilized on land for irrigation / gardeningwithin the industry owned adjacent land of about 23 acre. Strength up-gradation work of ETP isproposed by considering the expansion. Fat removal unit, fat collection tank, equalization tank,digester, gas holder are proposed.(3) Two briquette fired boilers and two FO fired boilers are provided. Dust collectors areprovided to both the briquette fired boilers. Stack is common to one briquette fired and FO firedboiler. Separate stack is provided to other two boilers. There is no boiler proposed in theexpansion unit.(4) Bank guarantee of 5.0 Lakh is submitted as per consent condition valid up to 31-8-2022.(5) They have submitted EPR plan for plastic waste management, which is uploaded in MPCBdocument section. Applied for plastic registration (Brand Owners) vide UAN MPCB-PLASTIC_MANF_BO-0000000090.In view of this, consent to establish (expansion) may be granted.(May 4 2019 07:34:07:000PM)

Shri S. M. Kurmude. (SRO-Jalgaon):-FO Remarks may please be seen.Red / LSI, Dist. Co-Op. Milk scheme unit. Previously consent granted for the existing unit, whichis valid up to 30/04/2022. Now applied for expansion for increase in production qty andadditional products. As the production is to be increased, effluent qty is also increased for whichind. has proposed to up-grade the existing ETP. Unit is having sufficient land for disposal oftreated effluent. Unit is to utilize existing boiler. JVS results are enclosed. JVS results of existingETP outlet exceeded the consented standards for BOD, COD, SS & Chloride and stackmonitoring results exceeded the parameter TPM. Unit has submitted BG of Rs.5.0 Lack as perprevious consent condition. In view of above C to E may be granted.(Jun 25 2019 11:10:25:000AM)

Mr.P.K.Mirashe(AST) (CAC-CELL-HQ):-Pl Process and put up(Jun 25 2019 11:40:27:000AM)

MPCB-CAC-00

0000

0058

MPCB-CAC-0000000058 (CAC Meeting Number : 8 dated August 6, 2019) Page 128 of 154

Other RelevantInformation

1] PP has applied for consent to establish for additional milk products and qty with increase inCI.

2] Existing consent is valid up to 30.04.2022.

3] PP is has provided ETP of capacity 1000 CMD, Consisting of primary settling tank, aerationtank,clarifier andSDB. There is increase in effluent qty by 300 CMD. Treated effluent 50% recycled in the processand remainingis disposed on land. The analysis results are exceeded the BOD, COD, SS and Chloridesparameters.

4] PP has proposed to provided new DG set of capacity -500 KVA. The analysis results of existingboilers areexceeded the limits of TPM and So2 parameters.

5] PP has submitted BG as per the earlier consent condition.

Recommendation ofCAC/CC Cell

We may consider case for grant of consent to establish for expansion by forfeiting BG of Rs.2.5Lakhs and obtain top of BG, and consent shall be issued after submission of detailed waterbudget including recycle and disposal qty of the effluent and after submission of action planalong with time bound program to reduce pollution.

ConsentRecommended forperiod upto as perSectoral Approachpolicy

Up to commissioning of the unit or 5 years period.

MPCB-CAC-00

0000

0058

MPCB-CAC-0000000058 (CAC Meeting Number : 8 dated August 6, 2019) Page 129 of 154

ITEM NO: 26 - Unique Number: MPCB-CONSENT-0000069354Fresh CAC ITEMRegion: SRO - Amravati I Section: CAC Date: 01.08.2019UAN Number: MPCB-CONSENT-0000069354 TAG CACName & Address: Raymond Luxury cottons Ltd (T-18/1, Addl. MIDC Nandgaon Peth, Dist. Amravati)Location ofIndustrial unit:

T-18/1, additional MIDC , Nandgaonpeth, Amravati Additional industrial area , NandgaonpethAmravati

Email: [email protected] Telephone number: 7720008670

Industry Type: R40 Yarn / Textile processing involving any effluent/emission generating processes includingbleaching, dyeing, printing and colouring

Industry Category: REDProject Details: Expansion in existing project

Consent Applied For

Consent to Establishfor expansion

i.e.installation ofBoiler of capacity 6

TPH (Stand By), WaterRecovery System &D.G. Set of 750 KVACapacity (Stand By).

Application Date March18,2019

Date of receipt ofCAC/CC cell 06.06.2019

Capital Investment in Rs. (Crs)Existing Proposed Total

Rs.152.22 Crs Rs.1.7305 crs Rs. 153.95 CrsDetails of

project :Expansion inexisting project

Total Plot area(sq.m.) 123750 (sq.m) Construction

BUA (sq.m.) 42605 (sq.m)Product and By-product details

Sr.no Product Name Quantity

1Flax/Linen spinning yarn and spinning offlax/linen/jute/mesta and other vegetable fibresand blends with manmade fibres

0 Kg/Day

2Fabrics of various fibres and their blends likeflax/linen,cotton,jute,mesta and other vegetablefibres,elastomer,polymer,remi,viscous,tayon,modaland other man made fibres etc

0 Kg/Day

Sr.no By-Product Name Quantity3 NA 0Applicabilty

ofCRZ

ClearenceDistance

from riverIndustrial

location policy Eco-sensitive Moratonium EC Direction of MoEF forwestern ghats

NO YES NO NO NO NO NO

If Yesprovidedetails

Amaravati -3.00 Km

Basedon:

Status:NotApplied

Details of CCA,Consents,Authorization and EC obtained Consent no. Consent

granted date ValidityCapital

Investmentin Crs

Total plotarea

ConstructionBUA

(FSI+Non-FSI)Remarks

C2O BO/CAC-Cell/UAnNo.26320/O/CAC/1711000971 28.11.2017 31.01.2020 Rs.152.22

crs

Existing production details

C to OSr.No Product Name Max quantity

1 Linen Fabric 3500 Kg/day

C to ESr.No Product Name Max quantity

1 NA NA

Bio-Medical Waste DetailsAnnual Rpt.(Form-II): NA

Accident Rpt.(Form-III): NA

MPCB-CAC-00

0000

0058

MPCB-CAC-0000000058 (CAC Meeting Number : 8 dated August 6, 2019) Page 130 of 154

BMWGeneration

Sr.No Category Max quantity (Kg/M)

1 NA NA

Disposal @CBMWTF: No

Member ofCBMWTF: NA

CaptiveDisposal: No

Incinerator Capacity Fuel Type Auto Feeding Temp.Recorder Online Monitoring

NA NA NA NA

Autoclave Type(Vertical/Horizontal)

Temp &Pressure

Recording

Shredder Plastic WasteDisposal

Compliance of Water Pollution Related Conditions Purpose Water Consumption

in CMD as appliedEffluent generationas applied in CMD

TreatmentSteps

DisposalDetails

Remarks/Adequeteland Available

1 Domestic Purposes 35 25 STPOn Land

forGardening

2Processing wherebywater gets polluted &pollutants are easilybiodegradable

591 566 Primary +Secondary Recycle MIDC CETP

Nandgaonpeth,Amravati

3Processing wherebywater gets polluted &pollutants are noteasily biodegradable

0 0 --NA-- --NA--

4IndustrialCooling,spraying inmine pits or boilerfeed

384 24 Primary +Secondary CETP MIDC CETP

Nandgaonpeth,Amravati

5Others such asgardening,agricultureetc

NA NA NA NA NA

Whether any deviation in water consumption observed compared toprevious consent NO Remarks:

Compliance to existing unit in case applied for expansion C to E/O/R NOSource of water supply

In case proposed discharge to CETP forfurther treatment

CETP Capacity to handle additional load YESName of CETP

Existing JVS results EffluentSr.no. Date of visit Board official's

name:Whether samplecollected or not:

Whether results areconfirming to standardsor not (Exceedingparameter with value)

1 06.02.2019 YES YES1 22.01.2019 YES YES1 27.12.2018 YES YES1 27.11.2018 YES YES1 16.10.2018 YES YES

1 24.09.2018 YES NOCOD-260 against-250

1 27.08.2018 YES YES1 15.05.2018 YES YES1 20.04.2018 YES YES1 16.02.218 YES YES

Details of fuel consumption and APC system as applied :-Sr. no Source Stack Fuel type Quantity Height-I,II,III APC system

detail

1 process boilers(both) 1 Coal 1000 (Kg/hr.) 30.5 m APH/cyclone

and bagfilter

MPCB-CAC-00

0000

0058

MPCB-CAC-0000000058 (CAC Meeting Number : 8 dated August 6, 2019) Page 131 of 154

2 DG set 2 HSD 250 (Kg/hr.) 30 m NAWhether any deviation in fuel consumptionand APC system observed compared toprevious consent

NO Remarks:

Compliance to existing unit in case appliedfor expansion C to E/O/R NO

Existing JVS results AirSr.no. Date of visit Board official's

name:Whether samplecollected or not:

Whether results areconfirming to standardsor not (Exceedingparameter with value)

1 15.05.2018 [AAQM] YES NORSPM-195.31 against-100

2 15.02.2018 [AAQM] YES NORSPM-323.56 against-100

3 20.10.2018 [Stack] YES YES4 31.08.2018 [Stack] YES YES

Compliance of Haz. Waste ConditionDetails of hazardous waste as applied

Sr. no Type of waste Category Quantity & UOM Treatment Disposal

135.3 Chemical sludgefrom waste watertreatment

35.3 30 MT/M NA CHWTSDF

2 5.1 Used or spent oil 5.1 100 Ltr/M NA Sale to Authorized Re-Processor

3 NA NA 0 --NA-- NASame as mentioned inconsent to operatescheduleII

Whether any deviation in Hz waste generation and itsdisposal,observed compared to previous consent NO Remarks:

Compliance of existing unit in case applied for expansion C to E/O/R NO

Submission of Annual Return (Form IV) NO Submission Date

Compliance of Non Hazardous/ MSW conditionDetails of Non hazardous/MSW as applied

Sr. no Type of waste Quantity & UOM Treatment Disposal1 NA 0 --NA-- NA NAWhether any deviation in Non-Hz waste generation and itsdisposal,observed compared to previous consent NO Remarks:

Compliance of existing unit in case applied for expansion C to E/O/R NOWaterCess Returns filed upto: Paid Upto: Jan 1 1900

12:00:00:000AMDirectionissued (ifany)

BGDetails Amount Validity

BG obtained towards complience ofa) Consent/CCA condition b) directions

1 Rs.10.0 Lakhs 31.05.2019Towards operation andmaintenance of pollution controlsystem and compliance of consentconditions.

NA

Details of BGfortified/enchasedfor noncomplience,if any:

No

Submission ofEnvironmentalStatement

NO Year yes , oct 2018

Details of consentfee paid Amount Rs: 15000 Terms 1

In case of 1st C to OComplience of C toE conditions

Remarks

Recommendation ofTAC

MPCB-CAC-00

0000

0058

MPCB-CAC-0000000058 (CAC Meeting Number : 8 dated August 6, 2019) Page 132 of 154

Recommendations

Shri. S. D. Patil (SRO-Amravati I):-Process and put up.(Mar 26 2019 05:28:23:000PM)

Shri. S. V. Lingade (FO-Amravati I):-1. Existing Linen/Cotton fabric manufacturing unit located in the notified industrial area i.e.Additional MIDC Nandgaonpeth, applied for grant of Consent to Establish (Expansion), as perCPCB categorization unit comes under Red category sr. no. 40 (Yarn / Textile processinginvolving any effluent/emission generating processes including bleaching, dyeing, printing andcolouring)2. Capital investment of the industry is increased from 15222.60 Lakh to 15395.65 lakh i.e. netincrease in capital investment is 173.05 lakh accordingly industry has submitted fees of Rs.15,000/- towards the grant of consent to establish (Expansion). The Existing consent valid up to30/01/2020.3. Industry has applied for the installation of additional utilities like Boiler of capacity 6 TPH(Stand By), Water Recovery System & D.G. Set of 750 KVA Capacity (Stand By).4. Industrial water consumption and effluent generation as well as fuel consumption andpollution load is not changed as the above utilities will utilize in case of failure/maintenance ofexisting one.5. Industry has provided the ETP of 660 M3 Capacity comprises of Barscreen - oil and greasetrap - Collection sump - Equalization tank - Primary clarifier tank - Aeration tank (ASP)-Secondary clarifier - Reaction tank - Tertiary clarifier - Treated effluent holding tank - SludgeThickner - Sludge collection tank – Decanter - Culture preparation tank. Also Industry hasprovided STP of capacity of 35 CMD comprises of Collection Tank – Aeration Tank (FAB Media) –Tube Settler – Treated Water Tank - Sludge Drying Bed & Centrifuge etc. Further industry hasobtained the membership of CETP for treatment and disposal of Dye-Bath/Non-Bath effluent.6. Industry already provided boiler of capacity 4 TPH & propose to install additional Boiler of 6TPH using coal as fuel to the tune of 500 Kg/Hr along with common air pollution control systemlike Cyclone, bag filter & stack of 30.5 mtr height. Also Industry has already provided the DG Setof capacity 1250 KVA and propose to provide the additional DG set of capacity of 750 KVA usingHSD as fuel to the tune of 250 Kg/Hr along with Individual stack height of 30.5 & 6.0 mtrrespectively.7. Industry has provided the water sprinkling arrangement at coal handling section.8. Industry has obtained the membership of CHWTSDF for the disposal of Hazardous Wastegenerated from the process/pollution control system.In view of above recommend the case for further approval please, if approved.(May 2 2019 12:41:52:000PM)

Shri. S. D. Patil (SRO-Amravati I):-1. Existing Linen/Cotton fabric manufacturing unit located in the notified industrial area i.e.Additional MIDC Nandgaonpeth, applied for grant of Consent to Establish (Expansion), as perCPCB categorization unit comes under Red category sr. no. 40 (Yarn / Textile processinginvolving any effluent/emission generating processes including bleaching, dyeing, printing andcolouring)2. Capital investment of the industry is increased from 15222.60 Lakh to 15395.65 lakh i.e. netincrease in capital investment is 173.05 lakh accordingly industry has submitted fees of Rs.15,000/- towards the grant of consent to establish (Expansion). The Existing consent valid up to30/01/2020.3. Industry has applied for the installation of additional utilities like Boiler of capacity 6 TPH(Stand By), Water Recovery System & D.G. Set of 750 KVA Capacity (Stand By).4. Industrial water consumption and effluent generation as well as fuel consumption andpollution load is not changed as the above utilities will utilize in case of failure/maintenance ofexisting one.5. Industry has provided the ETP of 660 M3 Capacity comprises of Barscreen - oil and greasetrap - Collection sump - Equalization tank - Primary clarifier tank - Aeration tank (ASP)-Secondary clarifier - Reaction tank - Tertiary clarifier - Treated effluent holding tank - SludgeThickner - Sludge collection tank – Decanter - Culture preparation tank. Also Industry hasprovided STP of capacity of 35 CMD comprises of Collection Tank – Aeration Tank (FAB Media) –Tube Settler – Treated Water Tank - Sludge Drying Bed & Centrifuge etc. Further industry hasobtained the membership of CETP for treatment and disposal of Dye-Bath/Non-Bath effluent.6. Industry already provided boiler of capacity 4 TPH & propose to install additional Boiler of 6TPH using coal as fuel to the tune of 500 Kg/Hr along with common air pollution control systemlike Cyclone, bag filter & stack of 30.5 mtr height. Also Industry has already provided the DG Setof capacity 1250 KVA and propose to provide the additional DG set of capacity of 750 KVA usingHSD as fuel to the tune of 250 Kg/Hr along with Individual stack height of 30.5 & 1.0 mtr abovethe roof of the building/shed where the DG set is to be installed respectively.7. Industry has provided the water sprinkling arrangement at coal handling section.8. Industry has obtained the membership of CHWTSDF for the disposal of Hazardous Wastegenerated from the process/pollution control system.In view of above it is recommend to grant the consent to establish, if approved.(Jun 4 2019 06:20:15:000PM)

Mr.P.K.Mirashe(AST) (CAC-CELL-HQ):-Pl Process and put up(Jun 6 2019 10:46:50:000AM)

MPCB-CAC-00

0000

0058

MPCB-CAC-0000000058 (CAC Meeting Number : 8 dated August 6, 2019) Page 133 of 154

Other RelevantInformation

1] PP has applied for consent to Establish for expansion.i.e.for the installation of additionalutilities like Boiler of capacity 6 TPH (Stand By), Water Recovery System & D.G. Set of 750 KVACapacity (Stand By).

2] PP has obtained consent for existing products which is valid up to 31.01.2020.

3] PP has provided ETP of capacity-660 CMD and STP of capacity of 35 CMD for treatment oftrade and domestic effluent.Analysis results of JVS are almost within consented limits.except onesample dated 24.09.2018.

4] PP has provided cyclone and bag filter to the coal fired boilers.The analysis results are withinthe limits and analysis results of AAQM are exceeded the limits.

5]Obtained membership of CHWTSDF.

Recommendation ofCAC/CC Cell

We may grant consent to establish for expansion i.e.for the installation of additional utilities likeBoiler of capacity 6 TPH (Stand By), Water Recovery System & D.G. Set of 750 KVA Capacity(Stand By) by forfeiting BG of Rs.1.0 Lakhs from the existing BG and also obtain Bg of Rs.5.0Lakhs towards compliance's of consent conditions.

ConsentRecommended forperiod upto as perSectoral Approachpolicy

Commissioning of the unit or 5 years period.

MPCB-CAC-00

0000

0058

MPCB-CAC-0000000058 (CAC Meeting Number : 8 dated August 6, 2019) Page 134 of 154

ITEM NO: 27 - Unique Number: MPCB-CONSENT-0000069930Fresh CAC ITEMRegion: SRO - Kalyan II Section: CAC Date: 27.07.2019UAN Number: MPCB-CONSENT-0000069930 TAG CACName & Address: GRASIM INDUSTRIES LIMITED ( UNIT- CENTURY RAYON) (P.B.No. 22, Murbad Road, Shahad)Location ofIndustrial unit: 45,53,56,57,58,59,76,77,78,201,202,207,55P,51(A) Shahad Ulhasnagar

Email: [email protected] Telephone number: 9322194914Industry Type: R47 Synthetic fibers including rayon,tyre cord, polyester filament yarnIndustry Category: REDProject Details: Existing project

Consent Applied For1st Consent to operate

for additionalproduction [ Part-2]

Application Date March25,2019

Date of receipt ofCAC/CC cell 18.05.2019

Capital Investment in Rs. (Crs)Existing Proposed Total

Rs.249.185 Crs + Rs. 378.79 Crs Increase in CI Rs. 627.9831 CrsDetails of

project :Existingproject

Total Plot area(sq.m.) 378656 (sq.m) Construction

BUA (sq.m.) 233563 (sq.m)Product and By-product details

Sr.no Product Name Quantity1 Viscose Filament 29300 MT/A2 Carbon- di- Sulphide 20000 MT/A3 Sulphuric Acid 76000 MT/A4 Captive power cogeneration 18 MW5 Steam( Excess from 180 MT/DaySr.no By-Product Name Quantity6 Anhydrous Sodium Sulphate 189007 Sodium Sulphide 1870Applicabilty

ofCRZ

ClearenceDistance

from riverIndustrial

location policy Eco-sensitive Moratonium EC Direction of MoEF forwestern ghats

NO YES NO NO NO NO NO

If Yesprovidedetails

Ulhas - 1.20Km

Basedon:

Status:NotApplied

Details of CCA,Consents,Authorization and EC obtained Consent no. Consent

granted date ValidityCapital

Investmentin Crs

Total plotarea

ConstructionBUA

(FSI+Non-FSI)Remarks

C2O BO/CAC-Cell/UANNo.15942/CAC-1710000311 12.10.2017 30.09.2019

C2E BO/CAC-Cell/EICNo.KN-6789-15/CAC/6595 18.05.2016 COU [

Establish]

C2OMPCB/UAN No.176/CAC-

Cell/Amend/CAC-1809000003

04.09.2018Amendmentfor change

in nameEC J-11011/415/2014-IA-II (I) 31.10.2016

MPCB-CAC-00

0000

0058

MPCB-CAC-0000000058 (CAC Meeting Number : 8 dated August 6, 2019) Page 135 of 154

Existing production details

C to O

Sr.No Product Name Max quantity

1 Rayon Viscous Filament Yarn,Tyre cord,Continuous spun yarn [Combined production ] 26,500 MT/A

2 Carbon Di Sulphide 20,000 MT/A

3 Sulphuric Acid 76,000 MT/A

4 Captive Generation [ 3 X 6.3 MW DG set] 18 MW

5 Steam [ Excess from captive power plant] 180 MT/D

6 Anhydrous Sodium Sulphate [ By product] 17,250 MT/A

7 Sodium Sulphide [ By product] 1870 MT/A

C to E

Sr.No Product Name Max quantity

1 Rayon Viscous Filament Yarn,Tyre cord,Continuous spun yarn [Combined VFY production ] 5000 MT/A

2 Anhydrous Sodium Sulphate [ By product] 3078 MT/A

Bio-Medical Waste DetailsAnnual Rpt.(Form-II): NA

Accident Rpt.(Form-III): NA

BMWGeneration

Sr.No Category Max quantity (Kg/M)

1 NA NA

Disposal @CBMWTF: No

Member ofCBMWTF: NA

CaptiveDisposal: No

Incinerator Capacity Fuel Type Auto Feeding Temp.Recorder Online Monitoring

NA NA NA

Autoclave Type(Vertical/Horizontal)

Temp &Pressure

Recording

Shredder Plastic WasteDisposal

Compliance of Water Pollution Related Conditions Purpose Water Consumption

in CMD as appliedEffluent generationas applied in CMD

TreatmentSteps

DisposalDetails

Remarks/Adequeteland Available

1 Domestic Purposes 500 300SepticTank &Soak Pit

Others Outlet of Septic tank

2Processing wherebywater gets polluted &pollutants are easilybiodegradable

14658 12500 Primary +Secondary Others

Saline Zone of Ulhascreek throughwaldhuni nala

3Processing wherebywater gets polluted &pollutants are noteasily biodegradable

0 0 --NA-- --NA--

4IndustrialCooling,spraying inmine pits or boilerfeed

2000 500 Primary +Secondary Others

Saline Zone of Ulhascreek throughwaldhuni nala

5Others such asgardening,agricultureetc

NA NA NA NA NA

Whether any deviation in water consumption observed compared toprevious consent NO Remarks:

Compliance to existing unit in case applied for expansion C to E/O/R NOSource of water supply

In case proposed discharge to CETP forfurther treatment

CETP Capacity to handle additional load NOName of CETP

Existing JVS results Effluent

MPCB-CAC-00

0000

0058

MPCB-CAC-0000000058 (CAC Meeting Number : 8 dated August 6, 2019) Page 136 of 154

Sr.no. Date of visit Board official'sname:

Whether samplecollected or not:

Whether results areconfirming to standardsor not (Exceedingparameter with value)

1 09.03.2018 [ ETPoutlet] YES YES

Details of fuel consumption and APC system as applied :-Sr. no Source Stack Fuel type Quantity Height-I,II,III APC system

detail

1 Rayon Spinning S-1 0 0 (Kg/hr.) 45.72 m Air washer withexhaust fan

2 Rayon Spinning S-2 0 0 (Kg/hr.) 61.0 m Air washer withexhaust fan

3 Rayon Spinning S-3 0 0 (Kg/hr.) 61.0 m Air washer withexhaust fan

4 Tyrecord andCSY Spinning S-9 0 0 (Kg/hr.) 53.0 m Air washer with

exhaust fan

5 Tyrecord andCSY Spinning S-10 0 0 (Kg/hr.) 41.5 m Air washer with

exhaust fan

6 CSY Spinning S-11 0 0 (Kg/hr.) 41.5 m Air washer withexhaust fan

7 Rayon Spinbath S-4 0 0 (Kg/hr.) 27.0 m Exhaust fan8 Acid Plant-1 S-5 0 0 (Kg/hr.) 41.15 m Scrubber9 Acid Plant-2 S-6 0 0 (Kg/hr.) 41.15 m Scrubber

10 CS2 Plant S-7 0 0 (Kg/hr.) 32.0 m Chiller, CS2 &H2S Scrubber

11 Scrubber S-8 0 0 (Kg/hr.) 16.38 m Scrubber

12 Boiler No.5(Standby) S-12 FO/LSHS 2580 (Kg/hr.) 30.7 m -

13 Boiler 6(Standby) S-13 FO/LSHS 2580 (Kg/hr.) 30.7 m -

14 AFBC Boiler no7 S-14 Coal 12340 (Kg/hr.) 57.5 m ESP

15Boiler No. 8(Standby forAFBC Boiler)

S-15 Coal 11240 (Kg/hr.) 50 m ESP

16 DG Set 1 & 2(Standby) S-16 FO/LSHS 2800 (Kg/hr.) 70.0 m WHRB

Whether any deviation in fuel consumptionand APC system observed compared toprevious consent

NO Remarks:

Compliance to existing unit in case appliedfor expansion C to E/O/R NO

Existing JVS results AirSr.no. Date of visit Board official's

name:Whether samplecollected or not:

Whether results areconfirming to standardsor not (Exceedingparameter with value)

1 NO NO

Compliance of Haz. Waste ConditionDetails of hazardous waste as applied

Sr. no Type of waste Category Quantity & UOM Treatment Disposal

135.3 Chemicalsludge from wastewater treatment

35.3 1760 (On drybasis) MT/A

Being sent toCHWTSDF to Mumbaiwaste ManagementLimited, Taloja

Being sent toCHWTSDF to Mumbaiwaste ManagementLimited, Taloja

2 17.2 Spent catalyst 17.2 12 MT/ABeing sent toCHWTSDF MumbaiWaste ManagementLimited

Being Sent toCHWTSDF MumbaiWaste ManagementLimited, Taloja

3 5.1 Used or spentoil 5.1 75 MT/A NA Sent to authorized

recycler

MPCB-CAC-00

0000

0058

MPCB-CAC-0000000058 (CAC Meeting Number : 8 dated August 6, 2019) Page 137 of 154

45.2 Wastes orresidues containingoil

5.2 100 MT/A NA Sent to authorizedrecycler

5 NA NA 250 MT/A

Sulphur waste - Beingsent to CHWTSDFMumbai wastemanagement Limited,Taloja

Sulphur waste - Beingsent to CHWTSDF,Mumbai WasteManagement Limited,Taloja

Whether any deviation in Hz waste generation and itsdisposal,observed compared to previous consent NO Remarks:

Compliance of existing unit in case applied for expansion C to E/O/R NO

Submission of Annual Return (Form IV) NO Submission Date

Compliance of Non Hazardous/ MSW conditionDetails of Non hazardous/MSW as applied

Sr. no Type of waste Quantity & UOM Treatment Disposal

1 Trash Sweeping 7500 MT/A NA Separate area isearmarked for disposal

2 Yarn Waste 800 MT/A NA Sold to vendor

3 Cinder ash & Fly ash 34000 MT/A NA Sold to bricksmanufacturer

4 Bio Sludge 40 MT/A NA Burnt in Boiler/ ManureWhether any deviation in Non-Hz waste generation and itsdisposal,observed compared to previous consent NO Remarks:

Compliance of existing unit in case applied for expansion C to E/O/R NOWaterCess Returns filed upto: Paid Upto: Jan 1 1900

12:00:00:000AMDirectionissued (ifany)

BGDetails Amount Validity

BG obtained towards complience ofa) Consent/CCA condition b) directions

1 Rs.5.0 Lakhs 31.01.2020 O & M of Pollution control systems NA

2 Rs.2.0 Lakhs 31.01.2020

Industry The by product generatorshould ensure that all the vehiclesused to transport by product to thevendor industry to be fitted withweb based GPS system to recordthe origin to destination positionand shall self monitor thecompliance and submit monthlyreport to the Board.Also industryshall obtain affidavit from vendorsstating the the by productpurchased from PP is used as araw material in their respectiveindustries.

NA

3 Rs.10.0 Lakhs 31.01.2020 Towards compliance of EC and Cto E conditions. NA

4 RS.10.0 Lakhs 31.10.2021Industry shall not take effectivesteps before obtainingEnvironmental Clearance

NA

5 Rs.2.0 Lakhs 31.12.2016

Industry shall install continiousonline monitoring system of pHmeter, BOD and Flow meter alongwith data logger at the outlet oftreated trade effluent discharge toUlhas Creek through WaldhuniNala.

NA

6 Rs.2.0 Lakhs 31.12.2016Industry shall carryout WaterAudit from renowned Instituteslike IIT or NEERI.

NA

Details of BGfortified/enchasedfor noncomplience,if any:

No

Submission ofEnvironmentalStatement

NO Year Yes, 24.09.2018

MPCB-CAC-00

0000

0058

MPCB-CAC-0000000058 (CAC Meeting Number : 8 dated August 6, 2019) Page 138 of 154

Details of consentfee paid Amount Rs: 1255966 Terms 1

In case of 1st C to OComplience of C toE conditions

Remarks

Recommendation ofTAC

MPCB-CAC-00

0000

0058

MPCB-CAC-0000000058 (CAC Meeting Number : 8 dated August 6, 2019) Page 139 of 154

Recommendations

Shri. M. N. Jadhav (SRO-Kalyan II):-Put up & Verify(Mar 27 2019 12:25:21:000PM)

Shri Pramod Lone (FO-Kalyan II):-1) Applied for consent to Operate of M/s Century Rayon ,P.B. No-22,Murbad Road ,Shahad,Ulhasnagar ,Dist-Thane vide no. MPCB/UAN no.176/CAC-Cell/Amend/CAC-1809000003dated-4.9.2018Mentioned in the consent to Operate granted on 12.10.2017 Read asM/s Century Rayon,P.B No-22, Murbad road, Shahad Ulhasnagar Dist-Thane-421103

M/s Grasim Industries Limited( Formerly Known as M/s Century Rayon,P.B No-22, Murbad road, Shahad Ulhasnagar Dist-Thane-421103

2) Board has granted consent vide no.BO/CAC-Cell/UAN No.15942/CAC/1710000311dated-12.10.2017 Valid up to 30.9.2019 for the product ofSr. No. Product Name Qty Additional Production qty Total1 Rayon Viscose Filament Yarn ,Tyre cord ,continuous spun yarn ( Combined Production) 26500MT/A 2800 MT/A 29300 MT/A2 Carbon di Sulphide 20,000 MT/A ….. …..3 Sulphric Acid 76000 MT/A4 Captive Power generation ( 3 X 6.3 MW DG set) 18 MW …… ……5 Steam (Excess from Capative Power Plant ) 180 MT/D …. …BY Product1 Anhydrous Sodium Sulphate 17250 MT/A 1650 MT/A 18900 MT/A2 Sodium Sulphide 1870 MT/A … ….

I.E- 13000 CMD to saline Zone of Ulhas creek through Waldhuni Nala & 700 CMD 100%recycled in process.D.E- 300.0 CMD, Discharge along with trade effluent after treatment in ETP to Saline zone ofUlhas creeck trough Waldhuni Nala.2) Govt of India has issued Environmental Clearance vide no.J-11011/415/2014-IA II(I)dated-31.10.2016

Sr.No. Product Name Existing Qty( MT/A ) Proposed additional Qty MT/A Total MT/A1 Viscose Filament Yarn ,Tyre cord ,continuous spun yarn( Combined Production) 25000 MT/A5000 30,0002 Carbon di Sulphide 20,000 MT/A ….. 20,0003 Sulphric Acid 76000 MT/A 76000 76000By-product Anhydrous Sodium Sulphate 16272 19350

3.) Now industry has applied for Viscose Filament increasing in production qty 26500 MT/A to29300 MT/A. As per EC quantity.

4) Earlier consent C.I. of Rs. 249.185 crores + additional C.I. 378.798 Crores total = 627 .983Crores as per CA certificate submitted by industry. Industry clarification etter submitted w.r.t.increasing CI The board of Century Textiles and Industries Ltd ( CTIL ) vide its resolution dated12.12.2017 has transferred “Right to Manage and Operate “ its Viscose Filament Yarn businessto “Gramism Industries Ltd ” effective from 01.2.2018.The Gross Fixed Assest ( GFA) value/Gross Block of Rs.6279831,213 . & Consent fees paid of Rs.1255966/- Dr. No. 5448115, NEFTdated 27.3.2019.5) ETP: - Industry has provided ETP consisting Primary, Secondary, Tertiary treatment facilities.Existing Treated effluent qty-13000 CMD discharge in to Saline Zone of Ulhas Creeck throughWaldhuni Nala & 700 CMD 100% recycled in the process.6) 700 CMD trade effluent used in process & degasser unit. Industry has provided separate flowmeter for recycle water.7) AS per Information industry now increasing I.E. 900 CMD including previous 700 CMDindustrial effluent 100% will be recycled & reused.8) H.W- Now increasing HW generated 1600 MT/A to 1760 MT/A. ( on dry basis)9) Industry is sending H.W to MWML qty-4.664 MT dated 27.2.2019 (as per manifest record videno. A-95680).10) APC; - Industry has provided ESP for Coal fired Boiler.11) A) Industry has provided Mist Eliminators & Alkali scrubber for Sulphuric acid plant I & II.B) Industry has provided Air washers & Exhaust fans for Rayon, Tyre cord plant, I, II, II plant.c) Industry has provided So2 scrubber & H2s Scrubbing system for Caron disulphide plant(CS2).12) Industry has submitted BG as per existing valid consent consent condition Schedule-III.13) Board has issued PD vide no. MPCB/ROK/TB/PD-P/30 dated-21.12.2018.Now industry hascomplied. Industry has provided scrubber for spin bath.In view of above C to O with increasing production quantity may be granted if approved higherauthority.

(May 17 2019 06:32:00:000PM)

Shri. M. N. Jadhav (SRO-Kalyan II):-Remarks of the Field Officer may please be seen.1) Red/LSI (CAC) existing unit applied for consent to operate for expansion (Phase-II).2) Existing unit has changed its name from M/s. Century Rayon to M/s. Grasim Industries Ltd.(Unit- Century Rayon).3) The existing CI as per consent Rs. 249.185 CR is increased to Rs. 627.983 Cr. As per the CAcertificate dtd. 25.3.2019, this includes increase of Rs. 580.10 cr towards transfer of "Right toManage & Operate viscose filament yarn business to Grasim Industries Ltd w.e.from 1.2.2018.Thereafter increase in Ci of RS. 47.88 cr from 1.2.2018 to 28.2.2019 which includes actualinvestment of Rs. 15.21 cr and RS. 32.67 cr towards capital work in progress. Uit has paid oneterm fees on total CI of RS. 627.98 Cr.4) Existing unit consent is valid up to 30.9.2019 for mfg of (a) Viscose Filament Yarn (26500MT/A) (b) Carbon Di sulphide ( 20000 MT/A), (c) Sulphuric Acid ( 76000 MT/A) and d) Captivepower plant(18 MW) and by-products.5) Unit applied for C to O for additional VFY = 2800 MT/A and by-product namely AnhydrousSodium Sulphate= 1650 MT/A6) Consent to establish for expansion is granted vide letter dtd. 18.5.2016 for mfg. of RayonViscose Filament yarn, Tyre cord, continuous spun yarn(VFY) = 5000 MT/A and by productAnhydrous Sodium Sulphate= 3078 MT/A. Unit applied and obtained consent to operate (Phase-I) for additional VFY = 1500 MT/A and Anhydrous Sodium Sulphate (by product)= 928 MT/Awhich is amalgamated in the consent dtd.4.9.20187) Environmental clearance is issued by MoEF & CC on 31.10.2016 for existing as well proposedproduction activity. (i) Viscose Filament Yarn = 30000 MT/A, (ii) CS2 = 20000 MT/A, (iii) H2SO4= 76000 MT/A and By-product Anhydrous Sodium Sulphate = 19350 MT/A.8) Now industry has applied for consent to 1st operate for phase-Ii expansion for mfg of RayonViscose Filament Yarn, Tyre Cord, continuous spun yarn (combined VFY production ) = 2800MT/A and by-product namely Anhydrous Sodium Sulphate= 1650 MT/A. As informed by therepresentative and uploaded letter, for this production unit has new VFI machines and processmodification.9) Additional water requirement for this phase-II expansion is 1358 CMD and additional effluentgeneration will be 900 CMD. Additional effluent generated will be treated in existing ETP ofcapacity 16000 CMD.10) HW i.e ETP sludge (Dry basis) generation will be 160 MT/A. Disposal at CHWTSDF.11) For existing unit, Effluent treatment plant of 16 MLD capacity (30 mg/lit BOD) comprisingequalization tank, primary clarifier, aeration, secondary lamella clarifier and pressure sand filteris provided. Also separate pretreatment facility for treatment of zinc based effluent is provided.This effluent is further treated in main ETP. Treated effluent is recycled (700 CMD as perconsent) and balance is discharged through pipe line into Waldhuni river which further meets toUlhas river in saline water zone.12) Online monitoring system for pH, BOD, Flow is installed at ETP.13) Online SO2 monitoring system is installed at Sulphuric acid plant.14) CS2 and H2S detectors are installed in spin bath section and Rayon plant.15) Caustic and Bio scrubber for Rayon spin bath section for CS2 and H2S gases is provided.16) Unit has complied the directions issued vide letter dtd. 20.2.2018.17) Compliance of C to E : (a) The effluent generated i.e. 100 % will be recycled/reused aftertreatment. (b) Unit has installed online monitoring system for measurement of flow, pH, CODand BOD. (c) To achieve BOD- 30 mg/l, upgradation of existing effluent Treatment plant iscompleted and commissioned. (d) Industry has carried out water audit from M/s. TeslaInnovations Pvt. Ltd. Which is vetted by Prof. Sandip Roy, Chemical Engineering Dept. IITBombay.Submitted for consideration for grant of consent to 1st operate for expansion (Phase-II).

(May 27 2019 06:03:43:000PM)

Mr.P.K.Mirashe(AST) (CAC-CELL-HQ):-PL Process and put up(May 28 2019 10:45:20:000AM)

MPCB-CAC-00

0000

0058

MPCB-CAC-0000000058 (CAC Meeting Number : 8 dated August 6, 2019) Page 140 of 154

Other RelevantInformation

1] PP has applied for consent to operate for additional production qty [ Phase-II] ..i.e. additionalproduction of Viscous Filament Yarn -VFY - 2800 MT/A [ Existing 25,000 MT/A + 1st Phase-1,500 MT/A + Now for 2nd Phase- 2,800 MT/A = Total 29,300 MT/A] and By product AnhydrousSodium Sulphate [ Existing 16,272 MT/A, + 1st Phase -978 MT/A + Now for 2nd Phase-1650MT/A = 18,900 MT/A]

2] PP is having consent fro existing products valid up to 30.09.2019 and obtained consent toEstablish for additional production qty on 18.05.2016.Also having amendment in consent forchange in name of Grasim Ind.Ltd.

3] PP has obtained Environmental Clearance for additional production qty on 31.10.2016.

4]There is increase in qty of effluent by 1358 CMD, Additional effluent will be treated in theexisting ETP of capacity -16000 CMD consisting of equalization tank, equalization tank for zincremoval, Clarifier, Thickener, Aeration (FMR), secondary lamella clarifier. Out of total treatedeffluent qty-14600 CMD , 1600 CMD will be recycled and remaining 13,000 CMD will bedischarged in to saline zone of ulhas creek through Waldhuni Nalla. There is no increase indomestic effluent qty.

5] There will be no additional increase in fuel consumption.

6] There will be increase in ETP sludge generation by 160 MTPA (on dry basis) which will bedisposed at CHWTSDF.

7] PP has provided air washer with exhaust system to Rayon Spinning sections and Tyrecord andCSY spinning sections, Scrubber mist eliminetor system to Acid plants and Chiller and CS2, H2Sscrubber to CS2 plantESP to coal boiler section and stacks to FO/LSHS boiler section.8] PP has submitted BG's as per earlier consent conditions.

9]PP has provided on line monitoring system for the parameter CS2 and H2S to tyre cord andRayon plant, installed CS2 and H2s detection system to spin bath area, installed 3 CAAQMS inthe premises and installed pH , BOD and flow meter at end of outlet.

10]PP has provided GPRS to the road tankers.

11] PP has submitted copy of the letter those are using Sodium Sulphate Anhydrous as rawmaterial in their process.

11] PP has submitted copy of the water audit report prepared by IIT Mumbai.

Recommendation ofCAC/CC Cell

We may grant 1st consent to operate for additional production [ phase -II] with renewal up to30.09.2020 by imposing condition of BG towards compliance's of EC and consent conditions andcondition of 100% recycle condition for the additional treated effluent.

ConsentRecommended forperiod upto as perSectoral Approachpolicy

30.09.2020.

MPCB-CAC-00

0000

0058

MPCB-CAC-0000000058 (CAC Meeting Number : 8 dated August 6, 2019) Page 141 of 154

ITEM NO: 28 - Unique Number: MPCB-CONSENT-0000069007Fresh CAC ITEMRegion: SRO - Amravati I Section: CAC Date: 30.07.2019UAN Number: MPCB-CONSENT-0000069007 TAG CACName & Address: GOLDEN FIBER LLP (Plot No. T-8, Nandgoan Peth Amravatin)Location ofIndustrial unit:

PLOT NO. T-8 ADD. AMARAVATI INDUSTRIAL AREA (TEXTILE PART) NADGAON PETH MIDCAMRAVATI

Email: [email protected] Telephone number: 7498208758

Industry Type: R40 Yarn / Textile processing involving any effluent/emission generating processes includingbleaching, dyeing, printing and colouring

Industry Category: REDProject Details: Existing project

Consent Applied For1st consent to operate

[ Part] withamalgamation of the

consentsApplication Date March

14,2019Date of receipt ofCAC/CC cell 09.05.2019.

Capital Investment in Rs. (Crs)Existing Proposed Total

Rs.86.50 Crs Rs. 32.74 Crs Rs..119.24 CrsDetails of

project :Existingproject

Total Plot area(sq.m.) 100534 (sq.m) Construction

BUA (sq.m.)11950.49(sq.m)

Product and By-product detailsSr.no Product Name Quantity

1 ALL TYPE OF FLAX & BLENDED YARNSPINNING 6.5 MT/Day

2 CONCRETE BATCHING PLANT 36 m3/hrSr.no By-Product Name Quantity3 NA 04 FLAX DUST BRIQUETTE 500Applicabilty

ofCRZ

ClearenceDistance

from riverIndustrial

location policy Eco-sensitive Moratonium EC Direction of MoEF forwestern ghats

NO YES NO NO NO NO NO

If Yesprovidedetails

Wardha River- 35.00 Km

Basedon:

Status:NotApplied

Details of CCA,Consents,Authorization and EC obtained Consent no. Consent

granted date ValidityCapital

Investmentin Crs

Total plotarea

ConstructionBUA

(FSI+Non-FSI)Remarks

C2OBO/CAC-Cell/UAN

no.36889/CAC-1807000192

06.07.2018 31.01.2023 Rs.86.50Crs

C2EBO/CAC-Cell/UAN

no.48568/CAC-1812001723

28.12.2018 Establish Rs.182.50Crs

Existing production details

C to OSr.No Product Name Max quantity

1 Flax Yarn Spinning 4.0 T/Day

C to E

Sr.No Product Name Max quantity

1 Flax Yarn Spinning 4.5 MT/Day

2 Concrete Batching plant 18 M3/Hrs

3 Concrete Batching plant 18 M3/Hrs

4 Flax Dust Briquette [ By product] 500 Kg/D

Bio-Medical Waste DetailsAnnual Rpt.(Form-II): NA

Accident Rpt.(Form-III):

MPCB-CAC-00

0000

0058

MPCB-CAC-0000000058 (CAC Meeting Number : 8 dated August 6, 2019) Page 142 of 154

BMWGeneration

Sr.No Category Max quantity (Kg/M)

1 NA NA

Disposal @CBMWTF: No

Member ofCBMWTF: NA

CaptiveDisposal: No

Incinerator Capacity Fuel Type Auto Feeding Temp.Recorder Online Monitoring

NA NA NA

Autoclave Type(Vertical/Horizontal)

Temp &Pressure

Recording

Shredder Plastic WasteDisposal

Compliance of Water Pollution Related Conditions Purpose Water Consumption

in CMD as appliedEffluent generationas applied in CMD

TreatmentSteps

DisposalDetails

Remarks/Adequeteland Available

1 Domestic Purposes 45 35 STPOn Land

forGardening

2Processing wherebywater gets polluted &pollutants are easilybiodegradable

550 494Primary +Secondary+ Tertiary

CETP

3Processing wherebywater gets polluted &pollutants are noteasily biodegradable

0 0 --NA-- --NA--

4IndustrialCooling,spraying inmine pits or boilerfeed

320 0 --NA-- --NA--

5Others such asgardening,agricultureetc

35 NA NA NA NA

Whether any deviation in water consumption observed compared toprevious consent NO Remarks:

Compliance to existing unit in case applied for expansion C to E/O/R NOSource of water supply

In case proposed discharge to CETP forfurther treatment

CETP Capacity to handle additional load YES

Name of CETPAdditional MIDCNandgaonpethAmravati

Existing JVS results EffluentSr.no. Date of visit Board official's

name:Whether samplecollected or not:

Whether results areconfirming to standardsor not (Exceedingparameter with value)

1 06.02.2019 YES YES1 22.01.2019 YES YES1 27.12.2018 YES YES

1 27.11.2018 YES NOCOD-260 against- 250

1 16.10.2018 YES YES

1 24.09.2018 YES NOCOD-420 against- 250

1 27.08.2019 YES YES

1 16.05.2018 YES NOCOD-440 against- 250

1 21.04.2018 YES YES

1 17.02.2018 YES NOCOD-280 against- 250

Details of fuel consumption and APC system as applied :-

MPCB-CAC-00

0000

0058

MPCB-CAC-0000000058 (CAC Meeting Number : 8 dated August 6, 2019) Page 143 of 154

Sr. no Source Stack Fuel type Quantity Height-I,II,III APC systemdetail

1 BOILER 1 FURNACE OIL 160 (Kg/hr.) 30 mSTACK OFSUFFICIENTHEIGHT

2 D G SET 2 DIESEL 210 (Kg/hr.) 12 mSTACK OFSUFFICIENTHEIGHT

Whether any deviation in fuel consumptionand APC system observed compared toprevious consent

NO Remarks:

Compliance to existing unit in case appliedfor expansion C to E/O/R NO

Existing JVS results AirSr.no. Date of visit Board official's

name:Whether samplecollected or not:

Whether results areconfirming to standardsor not (Exceedingparameter with value)

1 16.10.2018 [AAQM] YES YES2 24.09.2018 [AAQM] YES YES3 28.08.2018 [AAQM] YES YES4 21.04.2018 [AAQM] YES YES5 17.02.2018 [AAQM] YES YES6 16.05.2018 [Stack] YES YES

7 03.10.2018 [Stack] YES NOTPM- 161.32 against 150

8 24.04.2018 [Stack] YES YES

Compliance of Haz. Waste ConditionDetails of hazardous waste as applied

Sr. no Type of waste Category Quantity &UOM Treatment Disposal

1 5.1 Used orspent oil 5.1 20 Ltr/M NA SALE TO AUTHORIZED RE-

PROCESSOR

2

34.2 Sludgefrom treatmentof waste waterarising out ofcleaning /disposal ofbarrels /containers

34.2 20 MT/M CHTSDF-BUTTIBORI CHTSDF-BUTTIBORI

3 NA NA 0 --NA-- NA NAWhether any deviation in Hz waste generation and itsdisposal,observed compared to previous consent NO Remarks:

Compliance of existing unit in case applied for expansion C to E/O/R NO

Submission of Annual Return (Form IV) NO Submission Date

Compliance of Non Hazardous/ MSW conditionDetails of Non hazardous/MSW as applied

Sr. no Type of waste Quantity & UOM Treatment Disposal

1 FLAX WASTE 300 Kg/Day NA SALE TO AUTHORIZEDRE-PROCESSIR

2 DOMESTIC WASTE 50 Kg/Day NA SALE TO AUTHORIZEDVENDOR

3 SCRAP 50 Kg/Day NA SALE TO AUTHORIZEDVENDOR

4 FLEX DUST 500 Kg/Day NA SALE5 PUTTHA 150 Kg/M NA SALE6 POLYTHENE & P PATTI 160 Kg/M NA SALE7 MT DRUM 300 No/M NA SALEWhether any deviation in Non-Hz waste generation and itsdisposal,observed compared to previous consent NO Remarks:

Compliance of existing unit in case applied for expansion C to E/O/R NO

MPCB-CAC-00

0000

0058

MPCB-CAC-0000000058 (CAC Meeting Number : 8 dated August 6, 2019) Page 144 of 154

WaterCess Returns filed upto: Paid Upto: Jan 1 1900

12:00:00:000AMDirectionissued (ifany)

BGDetails Amount Validity

BG obtained towards complience ofa) Consent/CCA condition b) directions

1 Rs..5.0 Lakhs [C to O] 30.05.2023 Towards O & M of pollution

control system NA

2 Rs.5.0 Lakhs [ CTo O] 30.05.2023

All the effluent generated from theprocess shall be treated at RO andMEE [ Combine treatment facilityprovided at CETP] to achieve ZLDtill Board allows part of treatedeffluent on the SSHEHS as per EC.

NA

3 Rs.5.0 Lakhs [Establish] 30.04.2024. Towards compliances of consent to

Establish conditions., NA

Details of BGfortified/enchasedfor noncomplience,if any:

No

Submission ofEnvironmentalStatement

NO Year 29.09.2018

Details of consentfee paid Amount Rs: 300000 Terms 4

In case of 1st C to OComplience of C toE conditions

Remarks

Recommendation ofTAC

MPCB-CAC-00

0000

0058

MPCB-CAC-0000000058 (CAC Meeting Number : 8 dated August 6, 2019) Page 145 of 154

Recommendations

Shri. S. D. Patil (SRO-Amravati I):-Process & putup(Mar 28 2019 12:58:52:000PM)

Shri. S. V. Lingade (FO-Amravati I):-1. Existing Flax yarn spinning unit applied for grant of consent to 1st operate (expansionactivity), as per CPCB categorization unit comes under Red category sr. no. 40 (Yarn / Textileprocessing involving any effluent/emission generating processes including bleaching, dyeing,printing and colouring) applied for consent to establish expansion.2. Previous capital investment of the industry is 8650 lakh & industry has increase the capitalinvestment by 3274.33 lakh i.e. total investment of the project will be 11924.33 lakh.3. Industry has obtained the Consent to establish for complete expansion of project i.e Flax YarnSpinning – 4.5 MT/Day total cost of complete expansion is Rs. 9600 lakh but industry applied for1st operate partly i.e. All type of flax & blended yarn spinning – 2.5 MT/Day Rs. 3274.33 lakhaccordingly industry has paid the fees for 4 terms i.e. up to 30/04/2023.4. Industry has provided the ETP of capacity 500 M3 comprises of Collection Tank – Flash Mixer– Flocculator - Primary Clarifier – Aeration Tank 1 & 2 – Secondary Clarifier – Holding Tank –PSF & ACF – Discharge to CETP, Centrifuge etc. Industry has treated the same in existing ETP(i.e. Previous effluent quantity 406 CMD + Proposed effluent 88 CMD = 494 CMD. (JVS Resultsare attached).5. Industry has provided 2.8 TPH Boiler using furnace oil as fuel to the tune of 160 Kg/Hr alongwith Stack of 30.0 mtr height as an Air Pollution Control system. Also Industry has provided theDG Set of 1500 KVA using HSD as fuel to the tune of 250 Kg/Hr along with stack of 3 mtr height.6. Existing consent to operate is valid up to 31/01/2023.7. Industry has obtained the membership of CHWTSDF for the disposal of Hazardous Wastegenerated from the process/pollution control system.8. Industry has obtained the membership of CETP for the further treatment & disposal ofpartially treated effluent in to CETP.In view of above recommend the case for further approval please, if approved.(May 6 2019 02:19:14:000PM)

Shri. S. D. Patil (SRO-Amravati I):-The industry has applied for grant of consent to first operate (Expansion) activity for expansionof All types of Flax & Blended Yarn Spinning -2.5 MT/D & RMC Plant-36 M3/hr.Industry hasprovided ETP of capacity 500 CMD comprises of collection tank-flash mixer-flocculator - primaryclarifier- Aeration tank 1 & 2- secondary clarifier-Holding tank-PSF& ACF-discharge to CETP forfurther treatment. The total effluent generation will be 494 CMD. The existing consent toOperate is valid upto 31.01.2023.The industry has made the consent fees for Four terms i.eperiod upto 31.01.2023 considering the CI i.e.3274.33 Lacs incurred in the expansion activityamounting to Rs.3,00,000/- .Accordingly the consent to operate (Expansion) may be granted upto31.01.2023(May 9 2019 04:06:14:000PM)

Mr.P.K.Mirashe(AST) (CAC-CELL-HQ):-Pl Process and put up(May 9 2019 05:08:45:000PM)

Other RelevantInformation

1] PP has applied for 1st consent to operate [ Part] with amalgamation of the existing consentwith increase in CI.

2] PP is having consent to operate for the existing production which is valid up to 31.01.2023.

3] PP has obtained consent to Establish for additional production on 28.12.2018.

4] The manufacturing process consisting of Hacking,Draw frame passage 1-2-3-4-5-6, Roving,Bleaching and De-Gumming , spinning, winding and Packing activity.

5] The additional effluent will be treated in existing ETP of 500 CMD capacity consisting ofequalization tank, primary clarifier,aeration tank,secondary clarifier, filter water tank and SDB.Analysis results of JVS samples are fluctuating COD parameter.Treated effluent disposed in toCETP for further treatment.

6] PP has provided soak pit for domestic effluent.

7] Provided stacks to the FO fired boiler and DG set. Analysis result dated 03.10.2018 exceededTPM parameter.

8]CHWTSDF - Membership obtained.Recommendation ofCAC/CC Cell

We may grant 1st consent to operate [ Part] up to 31.01.2023 by forfeiting BG of Rs.1.0 lakhstowards exceeding the JVS samples and extending the existing BGs up to 31.05.2023.

ConsentRecommended forperiod upto as perSectoral Approachpolicy

31.01.2023.

MPCB-CAC-00

0000

0058

MPCB-CAC-0000000058 (CAC Meeting Number : 8 dated August 6, 2019) Page 146 of 154

ITEM NO: 29 - Unique Number: MPCB-CONSENT-0000069719Fresh CAC ITEMRegion: SRO - Pune I Section: CAC Date: 31.07.2019UAN Number: MPCB-CONSENT-0000069719 TAG CACName & Address: AIRPORTS AUTHORITY OF INDIA (Pune Airport)Location ofIndustrial unit: 224, 225 & 226 LOHEGAON HAVELI

Email: [email protected] Telephone number: 8698403144Industry Type: R23 Airports and Commercial Air StripsIndustry Category: REDProject Details: Existing project

Consent Applied ForRenewal of consent tooperate with increase

in CIApplication Date March

22,2019Date of receipt ofCAC/CC cell 20.05.2019

Capital Investment in Rs. (Crs)Existing Proposed Total

Rs.128.50 Crs + Increased by Rs. 8.45 Crs Rs. 136.95 CrsDetails of

project :Existingproject

Total Plot area(sq.m.) 17000 (sq.m) Construction

BUA (sq.m.) 19600 (sq.m)Product and By-product details

Sr.no Product Name Quantity

1

AIrport operation of Civil Enclave / Terminalbuilding to facilitate arrival and depature of airpassengers airport at Lohgaon Sr.No.225 &226 Total Plot area 17,000 Sq,mtrs and BUA19,600 Sq.Mtrs

0 --NA--

Sr.no By-Product Name Quantity2 NA 0Applicabilty

ofCRZ

ClearenceDistance

from riverIndustrial

location policy Eco-sensitive Moratonium EC Direction of MoEF forwestern ghats

NO YES NO NO NO YES NO

If Yes providedetails

Mula-Mutha -4.90 Km

Based on:

Status:Obtained (EC Ref.No. -IA/MH/MIS/78440/2018 Dt.11.09.2018)

Details of CCA,Consents,Authorization and EC obtained Consent no. Consent

granted date ValidityCapital

Investmentin Crs

Total plotarea

ConstructionBUA

(FSI+Non-FSI)Remarks

C2EBO/CAC-Cell/UAN

no.53607/53665/E/O/CAC-1809002180

25.01.2018 31.03.2019 Rs.128.50Crs

Existing production details

C to O

Sr.No Product Name Max quantity

1AIrport operation of Civil Enclave / Terminal building to facilitate arrivaland depature of air passengers airport at Lohgaon Sr.No.225 & 226 TotalPlot area 17,000 Sq,mtrs and BUA 19,600 Sq.Mtrs

NA

C to ESr.No Product Name Max quantity

1 NA NA

Bio-Medical Waste DetailsAnnual Rpt.(Form-II): NA

Accident Rpt.(Form-III):

BMWGeneration

Sr.No Category Max quantity (Kg/M)

1 NA NA

Disposal @CBMWTF: No

MPCB-CAC-00

0000

0058

MPCB-CAC-0000000058 (CAC Meeting Number : 8 dated August 6, 2019) Page 147 of 154

Member ofCBMWTF: NA

CaptiveDisposal: No

Incinerator Capacity Fuel Type Auto Feeding Temp.Recorder Online Monitoring

NA

Autoclave Type(Vertical/Horizontal)

Temp &Pressure

Recording

Shredder Plastic WasteDisposal

Compliance of Water Pollution Related Conditions Purpose Water Consumption

in CMD as appliedEffluent generationas applied in CMD

TreatmentSteps

DisposalDetails

Remarks/Adequeteland Available

1 Domestic Purposes 115 70 --NA-- LocalBodies

2Processing wherebywater gets polluted &pollutants are easilybiodegradable

0 0 --NA-- --NA--

3Processing wherebywater gets polluted &pollutants are noteasily biodegradable

0 0 --NA-- --NA--

4IndustrialCooling,spraying inmine pits or boilerfeed

30 0 --NA-- --NA--

5Others such asgardening,agricultureetc

5 NA NA NA NA

Whether any deviation in water consumption observed compared toprevious consent NO Remarks:

Compliance to existing unit in case applied for expansion C to E/O/R NOSource of water supply

In case proposed discharge to CETP forfurther treatment

CETP Capacity to handle additional load NOName of CETP

Existing JVS results EffluentSr.no. Date of visit Board official's

name:Whether samplecollected or not:

Whether results areconfirming to standardsor not (Exceedingparameter with value)

1 Not enclosed NO NO

Details of fuel consumption and APC system as applied :-Sr. no Source Stack Fuel type Quantity Height-I,II,III APC system

detail

1 DG SET 4 DIESEL 600 (Kg/hr.) 19 m STACKSPROVIDED

Whether any deviation in fuel consumptionand APC system observed compared toprevious consent

NO Remarks:

Compliance to existing unit in case appliedfor expansion C to E/O/R NO

Existing JVS results AirSr.no. Date of visit Board official's

name:Whether samplecollected or not:

Whether results areconfirming to standardsor not (Exceedingparameter with value)

1 Not enclosed NO NO

Compliance of Haz. Waste ConditionDetails of hazardous waste as applied

Sr. no Type of waste Category Quantity & UOM Treatment Disposal1 NA NA 0 --NA-- NA NA2 NA NA 0 --NA-- NA NA

MPCB-CAC-00

0000

0058

MPCB-CAC-0000000058 (CAC Meeting Number : 8 dated August 6, 2019) Page 148 of 154

Whether any deviation in Hz waste generation and itsdisposal,observed compared to previous consent NO Remarks:

Compliance of existing unit in case applied for expansion C to E/O/R NO

Submission of Annual Return (Form IV) NO Submission Date

Compliance of Non Hazardous/ MSW conditionDetails of Non hazardous/MSW as applied

Sr. no Type of waste Quantity & UOM Treatment Disposal

1 SOLID WASTE 500 Kg SEGREGATION Recycling& land filldisposal

Whether any deviation in Non-Hz waste generation and itsdisposal,observed compared to previous consent NO Remarks:

Compliance of existing unit in case applied for expansion C to E/O/R NOWaterCess Returns filed upto: Paid Upto: Jan 1 1900

12:00:00:000AMDirectionissued (ifany)

BGDetails Amount Validity

BG obtained towards complience ofa) Consent/CCA condition b) directions

1 Rs.5.0 Lakhs 31.12.2023 Towards Compliance's of consentconditions NA

Details of BGfortified/enchasedfor noncomplience,if any:

No.

Submission ofEnvironmentalStatement

NO YearFor existing Terminal Buildingenvironmental clearance was notrequired. For proposed NITB EChas be

Details of consentfee paid Amount Rs: 273918 Terms 1

In case of 1st C to OComplience of C toE conditions

Remarks

Recommendation ofTAC

Recommendations

Shri. Nitin R. Shinde (SRO-Pune I):-Pl visit, process and put up(Mar 30 2019 11:29:05:000AM)

Suryakant J. Shinde (FO-Pune I):-This is CAC Case. Application for renewal of consent. Board has issued consent to AirportAuthority of India on 25.09.2018 for Airport terminal building / civil enclave at pune air port fortotal plot are 17000 sq mtrs and built up area 19600 sq mtrs which was valid upto 31.03.2019.Board has impose condition regarding domestic effluent that, Airport Authority of India shallprovide STP of the capacity 70 CMD, treated domestic effluent shall be 60% recycle forsecondary purpose for various usages and remaining shall use on land for gardening andremaining dispose to sewage provided by local body. But Airport Authority of India has notprovided STP also disposing entire domestic effluent to sewage system provided by punemunicipal corporation. Industrial effluent is Nil. DG Set of 750 KVA capacity x 4 nos providedwith 19 mtrs height of stack. Bio degradable waste given to recycle and land fill instead ofprovided in house OWC and use as manure as per condition impose in consent. Airport Authorityof India has not submitted copy of Bank Guarantee of Rs. 5.0 Lacs. and Environment Clearancecopy along with consent application. Previous consented capital investment was Rs. 128.50 Crs.Now showing capital investment Rs. 136.89 Crs. Consent fee paid Rs. 2,73,918/- for one termonly. Airport Authority of India has not paid additional consent fee for increase of capitalinvestment also not submitted justification for increase in capital investment. This office hasissued scrutiny letter for above point. In view of the above, we may consider the case for grant ofrenewal of consent after receipt of reply to scrutiny letter, if approved.(May 16 2019 09:24:41:000PM)

Shri. Nitin R. Shinde (SRO-Pune I):-In view of above non compliance we may issue SCN and after the receipt of compliance and itsverification, we may consider the case for operate ,if approved.(May 20 2019 10:17:28:000AM)

Mr.P.K.Mirashe(AST) (CAC-CELL-HQ):-Discussed in CAC Meeting, Approved and submitted for final signature(May 20 2019 11:55:32:000AM)

MPCB-CAC-00

0000

0058

MPCB-CAC-0000000058 (CAC Meeting Number : 8 dated August 6, 2019) Page 149 of 154

Other RelevantInformation

1] PP has applied for renewal of consent to operate with increase in CI for airport terminalbuilding /Civil enclave at Pune Airport for operation of civil Enclave /terminal building tofacilitate arrival and departure of air passengers Airport at Lohegaon, Sr.no.224,225 and 226,Taluka haveli,Dist:Pune on total plot area 17,000 sq.mtrs and BUA 19,600 sq.mtrs.

2]Earlier consent was valid up to 31.03.2019.

3] PP has not installed STP and untreated effluent discharged in to sewage system provided byPune municipal corporation.

4] Stacks provided to DG sets.

5] PP has not submitted copy of BG submitted in the Board.

Recommendation ofCAC/CC Cell

We may grant consent to operate for short period i.e.31.03.2020 with the condition of BG andconsent shall be issued after receipt of BG .Also SRO shall submit separate proposal forforfeiture of BG for the non compliance of consent conditions,if any.

ConsentRecommended forperiod upto as perSectoral Approachpolicy

31.03.2020.

MPCB-CAC-00

0000

0058

MPCB-CAC-0000000058 (CAC Meeting Number : 8 dated August 6, 2019) Page 150 of 154

ITEM NO: 30 - Unique Number: MPCB-CONSENT-0000069937Fresh CAC ITEMRegion: SRO - Pune II Section: CAC Date:UAN Number: MPCB-CONSENT-0000069937 TAG CAC

Name & Address: MINDA CORPORATION LIMITED (Plot no. D - 225, 226, 227, Phase - II, Chakan Industrial Area,Bhamboli, Tal. Khed, Dist. pune)

Location ofIndustrial unit: PLOT NO D-227/1, D-226 & D-227, VILLAGE- BHAMBOLI CHAKAN INDUSTRIAL AREA KHED

Email: [email protected] Telephone number: 9552521990Industry Type:Industry Category: REDProject Details: Existing project

Consent Applied ForRenewal with

increased CI andadditional product

Application Date March25,2019

Date of receipt ofCAC/CC cell 10/05/2019

Capital Investment in Rs. (Crs)Existing Proposed Total

80.0 27.91 107.91Details of

project :Existingproject

Total Plot area(sq.m.) 34955 (sq.m) Construction

BUA (sq.m.) 12000 (sq.m)Product and By-product details

Sr.no Product Name Quantity

1 PARTS & ACCESSORIES OF CARS &MOTORCYCLES 5500 MT/A

Sr.no By-Product Name Quantity2 NA 0Applicabilty

ofCRZ

ClearenceDistance

from riverIndustrial

location policy Eco-sensitive Moratonium EC Direction of MoEF forwestern ghats

NO YES NO NO NO NO NO

If Yesprovidedetails

Indrayani -8.69 Km

Basedon:

Status:NotApplied

Details of CCA,Consents,Authorization and EC obtained Consent no. Consent

granted date ValidityCapital

Investmentin Crs

Total plotarea

ConstructionBUA

(FSI+Non-FSI)Remarks

C2E RO-Pune/CONSENT/1612000673 20.12.2016 COU 80.0C2O RO-Pune/CONSENT/1710000593 16.10.2017 31.03.2019 80.0

Existing production details

C to OSr.No Product Name Max quantity

1 Parts & Accessories of Motorcycles & Cars 5500 MT/A

C to ESr.No Product Name Max quantity

1 Parts & Accessories of Motorcycles & Cars 5500 MT/A

Bio-Medical Waste DetailsAnnual Rpt.(Form-II):Accident Rpt.(Form-III):

BMWGeneration

Sr.No Category Max quantity (Kg/M)

1 NA NA

Disposal @CBMWTF: No

Member ofCBMWTF:CaptiveDisposal: No

MPCB-CAC-00

0000

0058

MPCB-CAC-0000000058 (CAC Meeting Number : 8 dated August 6, 2019) Page 151 of 154

Incinerator Capacity Fuel Type Auto Feeding Temp.Recorder Online Monitoring

Autoclave Type(Vertical/Horizontal)

Temp &Pressure

Recording

Shredder Plastic WasteDisposal

Compliance of Water Pollution Related Conditions Purpose Water Consumption

in CMD as appliedEffluent generationas applied in CMD

TreatmentSteps

DisposalDetails

Remarks/Adequeteland Available

1 Domestic Purposes 50 45 STPOn Land

forGardening

NA

2Processing wherebywater gets polluted &pollutants are easilybiodegradable

3 2 Primary +Tertiary

On Landfor

GardeningNA

3Processing wherebywater gets polluted &pollutants are noteasily biodegradable

0 0 --NA-- --NA-- NA

4IndustrialCooling,spraying inmine pits or boilerfeed

25 10Primary +Secondary+ Tertiary

--NA-- NA

5Others such asgardening,agricultureetc

0 NA NA NA NA

Whether any deviation in water consumption observed compared toprevious consent NO Remarks:

Compliance to existing unit in case applied for expansion C to E/O/R NOSource of water supply

In case proposed discharge to CETP forfurther treatment

CETP Capacity to handle additional load NOName of CETP

Existing JVS results EffluentSr.no. Date of visit Board official's

name:Whether samplecollected or not:

Whether results areconfirming to standardsor not (Exceedingparameter with value)

1 NO NO

Details of fuel consumption and APC system as applied :-Sr. no Source Stack Fuel type Quantity Height-I,II,III APC system

detail

1 DG SET 1 HSD 280 (Kg/hr.) 6.5 mtr. aboveroof level m Provided

2 DG SET 1 HSD 280 (Kg/hr.) 6.5 mtr. aboveroof level m Provided

3 DG SET 1 HSD 140 (Kg/hr.) 4.5 mtr. aboveroof. m NA

Whether any deviation in fuel consumptionand APC system observed compared toprevious consent

NO Remarks:

Compliance to existing unit in case appliedfor expansion C to E/O/R NO

Existing JVS results AirSr.no. Date of visit Board official's

name:Whether samplecollected or not:

Whether results areconfirming to standardsor not (Exceedingparameter with value)

1 NO NO

Compliance of Haz. Waste ConditionDetails of hazardous waste as applied

Sr. no Type of waste Category Quantity & UOM Treatment Disposal

1 5.1 Used or spent oil 5.1 600 Ltr/A Authorized Re-cycler

Authorized Re-cycler

MPCB-CAC-00

0000

0058

MPCB-CAC-0000000058 (CAC Meeting Number : 8 dated August 6, 2019) Page 152 of 154

2Chemical Sludge fromwaste wastertreatment

35.3 50 Kg/M NA CHWTSDF

Whether any deviation in Hz waste generation and itsdisposal,observed compared to previous consent NO Remarks:

Compliance of existing unit in case applied for expansion C to E/O/R NO

Submission of Annual Return (Form IV) NO Submission Date

Compliance of Non Hazardous/ MSW conditionDetails of Non hazardous/MSW as applied

Sr. no Type of waste Quantity & UOM Treatment Disposal1 NA 0 --NA-- NA NA2 GARBAGE 40 Kg/Day NA Safe disposal3 METAL SCRAP 15 Ton/Y NA Sale

4 PACKAGING MATERIAL(PLASTIC & PAPERS) 7 Ton/Y NA Sale

Whether any deviation in Non-Hz waste generation and itsdisposal,observed compared to previous consent NO Remarks:

Compliance of existing unit in case applied for expansion C to E/O/R NOWaterCess Returns filed upto: Paid Upto: Jan 1 1900

12:00:00:000AMDirectionissued (ifany)

BGDetails Amount Validity

BG obtained towards complience ofa) Consent/CCA condition b) directions

1 NA NA NA NADetails of BGfortified/enchasedfor noncomplience,if any:Submission ofEnvironmentalStatement

NO Year Yes

Details of consentfee paid Amount Rs: 375000 Terms 3

In case of 1st C to OComplience of C toE conditions

Remarks

Recommendation ofTAC

MPCB-CAC-00

0000

0058

MPCB-CAC-0000000058 (CAC Meeting Number : 8 dated August 6, 2019) Page 153 of 154

Recommendations

Shri. Upendra C. Kulkarni (SRO-Pune II):-Process and Put up(Apr 1 2019 03:34:32:000PM)

Shri. Sameer S. Vastre (FO-Pune II):-1) Industry has obtained consent to operate dated 16/10/2017 in Orange/LSI category for mfg. ofParts & Accessories of Motorcycle and cars: 5500 MT/A and said consent was expired on31.3.2019 .2) Now Industry has applied for renewal of consent in Red category.3) The trade effluent generation is :15CMD and for treatment of same provided ETP ofcapacity:25CMD . ETP consists of inlet collection tank, oil skimmer, collection tank, dosingsystem , aeration tank, settling tank, filter feed tank, ACF, PSF and treated water tank. ETP wasin operation and treated water is used on land for gardening purpose. Flow meter provided atoutlet.4) Industry has provided STP for treatment of domestic effluent and STP was found in operation.STP consists of bar screen, O&G chamber, collection tank, aeration tank, settling tank, filterfeed tank, ACF, PSF, disinfection system is provided and treated water is used on land forgardening purpose. Flow meter provided at outlet of STP.5) Industry has provided heat treatment furnaces (2 Nos) with operation on electric heating.6) There are 15 nos of holding furnaces are found installed and is in operation on electricity.7) Industry has installed 06 nos of melting furnaces out of which 02 nos (furnace) are stationeryand 04 nos (furnace) are tilting type furnaces with provision of hood to each and common ductwith common stack about 33 mtrs height. These are operated on natural gas.8) DG set:750KVA (2Nos) and 500KVA with acoustic enclosure and provided stack about 22 mtrsto each.9) Industry has provided one shot blasting machine with dust collector as APC system alsoprovided dust collector with stack about 18 mtrs to buffing section.10) Industry has provided one hot water generator operated on natural gas and providedrectangular stack of height about 12 mtrs.11)Industry has provided seven tank process as pretreatment for powder coating activity andprovided dust collector as APC system. And found in operation and informed that taken trial run.12)Industry has obtained membership of CHWTSDF for disposal of Hazardous Waste and saidmembership valid upto 29.4.2023. Proper storage arrangement is not provided to oily cottonwaste and ETP sludge.13)Industry has installed furnaces, shot blasting, buffing, powder coating and same were notincorporated in previous consent.14)The JVS samples are collected.15)Industry has applied renewal with production quantity:11000 MT/Y however industry hassubmitted letter and also during visit clarifies that the additional production quantity mentionedin application was a typographical error and the production quantity as not changed i.e. 5500MT/Y.16)The existing capital investment of Rs:80 Crs as per consent dated 16.10.2017 and nowsubmitted CA certificate of Rs:107.91 Crs and paid consent fees of Rs:375000/- dated30.3.2019through RTGS..17)This office has issued query letter and partial reply is submitted.In view of above renewal of consent may be considered after satisfactory reply of query letter, ifapproved.(May 8 2019 10:07:39:000AM)

Shri. Upendra C. Kulkarni (SRO-Pune II):-1.Application is received for consent to renewal. 2.Existing consent is valid upto 31.3.2019under orange category without any metal surface treatment. 3. Industry is engaged inmanufacturing of Parts & Accessories of Motorcycle and cars: 5500 MT/A. 4. In existing consentthere is no any reflection of melting activity as well as heating activities and also metal surfacetreatment. 5. However during visit of Field Officer , Industry has provided heat treatmentfurnaces (2 Nos) with operation on electric heating. 6. There are 15 nos of holding furnaces arefound installed and is in operation on electricity.7. Industry has installed 06 nos of meltingfurnaces out of which 02 nos (furnace) are stationery and 04 nos (furnace) are tilting typefurnaces with provision of hood to each and common duct with common stack about 33 mtrsheight. These are operated on natural gas. 8. Industry has provided seven tank process as pretreatment for powder coating activity and provided dust collector as APC system. 9. Tradeeffluent generation is 2.0CMD + 15CMd effluent from cooling tower. 10. Treatment provided ,ETP of capacity:25CMD . ETP consists of inlet collection tank, oil skimmer, collection tank,dosing system , aeration tank, settling tank, filter feed tank, ACF, PSF and treated water tank.ETP was in operation and treated water is used on land for gardening purpose. 11. Domesticeffluent generation is 45CMD as per consent however ETP having 35CMD capacity as reportedin visit report. 12. STP comprises bar screen, O&G chamber, collection tank, aeration tank,settling tank, filter feed tank, ACF, PSF, disinfection system is provided and treated water isused on land for gardening purpose. Flow meter provided at outlet of STP. 13. Industry is amember of CHWTSDF. 14. JVS sample collected and results are awaited.15. Though theapplication reflects production quantity:11000 MT/A , it should be considered as :5500 MT/A asindustry has submitted separate letter.16.The existing capital investment of Rs:80 Crs as perconsent dated 16.10.2017 and now submitted CA certificate of Rs:107.91 CrsIn view of above industry seems to be gross violating and started the activities for which theyhave not obtained consent to establish. We may issue stringent action against unit and thendecide grant on consent.(May 9 2019 09:04:15:000PM)

Mr.P.K.Mirashe(AST) (CAC-CELL-HQ):-Pl Process and put up(May 10 2019 10:23:45:000AM)

MPCB-CAC-00

0000

0058

MPCB-CAC-0000000058 (CAC Meeting Number : 8 dated August 6, 2019) Page 154 of 154

Other RelevantInformation

SRO-Pune II reported that:-1.Application is received for consent to operate.2.Existing consent is valid upto 31.3.2019 under orange category without any metal surfacetreatment.3. Industry is engaged in manufacturing of Parts & Accessories of Motorcycle and cars: 5500MT/A.4. In existing consent there is no any reflection of melting activity as well as heating activitiesand also metal surface treatment.5. However during visit of Field Officer , Industry has provided heat treatment furnaces (2 Nos)with operation on electric heating.6. There are 15 nos of holding furnaces are found installed and is in operation on electricity.7. Industry has installed 06 nos of melting furnaces out of which 02 nos (furnace) are stationeryand 04 nos (furnace) are tilting type furnaces with provision of hood to each and common ductwith common stack about 33 mtrs height. These are operated on natural gas.8. Industry has provided seven tank process as pre treatment for powder coating activity andprovided dust collector as APC system.9. Trade effluent generation is 2.0CMD + 15 CMD effluent from cooling tower.10. Treatment provided , ETP of capacity:25CMD . ETP consists of inlet collection tank, oilskimmer, collection tank, dosing system , aeration tank, settling tank, filter feed tank, ACF, PSFand treated water tank. ETP was in operation and treated water is used on land for gardeningpurpose.11. Domestic effluent generation is 45 CMD as per consent however ETP having 35 CMDcapacity as reported in visit report.12. STP comprises bar screen, O&G chamber, collection tank, aeration tank, settling tank, filterfeed tank, ACF, PSF, disinfection system is provided and treated water is used on land forgardening purpose. Flow meter provided at outlet of STP.13. Industry is a member of CHWTSDF.14. JVS sample collected and results are awaited.15. Though the application reflects production quantity:11000 MT/A , it should be considered as:5500 MT/A as industry has submitted separate letter.16.The existing capital investment of Rs:80 Crs as per consent dated 16.10.2017 and nowsubmitted CA certificate of Rs:107.91 CrsIn view of above industry seems to be gross violating and started the activities for which theyhave not obtained consent to establish. We may issue stringent action against unit and thendecide grant on consent.

Recommendation ofCAC/CC Cell

As Industry has increased C.I. by Rs. 27.91 Crs. and installed one additional heat treatment &Melting furnaces and metal surface treatment facility without obtaining Consent to Establishfrom the Board and is in operation.

In view of above, we may issue SCN for refusal of consent for above non-compliance.ConsentRecommended forperiod upto as perSectoral Approachpolicy

SCN for refusal of consent

MPCB-CAC-00

0000

0058