PAGE 1
On JULY 27, 2020, the CONCESSIONS/PROCUREMENT COMMITTEE of the GREATER ORLANDO AVIATION AUTHORITY met in regular session telephonically with the meeting live streamed on YOUTUBE (OrlandoAirports) and GOTOMEETING. Chairman Friel called the meeting to order at 1:30 p.m. The meeting was posted in accordance with Florida Statutes with a quorum participating. Office of the Governor, Executive Order Number 20-69 Committee members present: Brad Friel, Chairman Kathleen Sharman, Vice Chair Thomas Draper, Senior Director of Operations
Brian Engle, Director of Customer Experience Staff/Others present: Denise Schneider, Assistant Director of Purchasing Bruce Gant, Manager of Purchasing Contracts Jo Thacker, Nelson Mullins, Legal Counsel Larissa Bou, Recording Secretary Chairman Friel announced to all present that if a bidder or proposer is aggrieved by any of the proceedings of today’s meeting and wishes to appeal the results of actions made by this Committee, they must file an appeal stating the item they wish to appeal and the basis for which they wish to appeal, and it must be received in writing by the Chief Executive Officer, Mr. Phillip N. Brown, via email [email protected] with copy to [email protected], by Monday, August 3, 2020 at 4:00 p.m. (emails will be accepted during the pandemic COVID-19). For individuals who conduct lobbying activities with Aviation Authority employees or Board members, registration with the Aviation Authority is required each year prior to conducting any lobbying activities. A statement of expenditures incurred in connection with those lobbying instances should also be filed prior to April 1 of each year for the preceding year. Lobbying any Aviation Authority Staff who are members of any committee responsible for ranking Proposals, Letters of Interest, Statements of Qualifications or Bids and thereafter forwarding those recommendations to the Board and/or Board Members is prohibited from the time that a Request for Proposals, Request for Letters of Interests, Request for Qualifications or Request for Bids is released to the time that the Board makes an award. In the event a lobbyist meets with or otherwise communicates with Staff or a Board member, including the Mayor of the City of Orlando or the Mayor of Orange County, the lobbyist shall file a Notice of Lobbying (Form 4) detailing each instance of lobbying to the Aviation Authority within 7 calendar days of such lobbying. Lobbyists will also provide a notice to the Aviation Authority when meeting with the Mayor of the City or Mayor of Orange County at their offices. The policy, forms, and instructions are available on the web site. Please contact the Director of Board Services with questions at (407) 825-2032. MINUTES
1. Upon motion by Mr. Draper, second by Mr. Engle, motion passed unanimously by roll call vote to accept the June 29, 2020, minutes as written. RECOMMENDATION TO APPROVE AMENDMENT NO. 5, SECOND RENEWAL OPTION FOR PURCHASING CONTRACT 03-17, LANDSIDE TERMINAL LANDSCAPE MAINTENANCE AND IRRIGATION SERVICES WITH CAROL KING LANDSCAPE, INC. (CAROL KING) 2. Mr. Gant presented the item. The initial term of the contract was for thirty-six (36) months, which commenced on December 1, 2016, with the Aviation Authority having options to renew the contract for two (2) additional periods of one (1) year each. The first renewal option is due to expire on November 30, 2020. This contract requires Carol King to furnish all labor, supervision, equipment, tools, materials and supplies, licenses, permits, chemicals, and all other items necessary or proper for, or incidental to, performing the landside terminal landscape and irrigation maintenance services located at the Orlando International Airport, in accordance with the contract documents. Second Renewal Option - December 1, 2020 through November 30, 2021. Department – Concurs with the renewal option.
MINUTES FOR THE JULY 27, 2020, CONCESSIONS/PROCUREMENT COMMITTEE
PAGE 2
RECOMMENDATION TO APPROVE AMENDMENT NO. 5, SECOND RENEWAL OPTION FOR PURCHASING CONTRACT 03-17, LANDSIDE TERMINAL LANDSCAPE MAINTENANCE AND IRRIGATION SERVICES WITH CAROL KING LANDSCAPE, INC. (CAROL KING) – (con’t) Contractor – Based on the information known at this time, Carol King has performed satisfactorily during the initial term and the first renewal option. The annual value for the second renewal option is for a total not-to-exceed amount of $1,438,995.03 with no rate increase. The actual amount paid to the contractor is based on actual work requested, performed, and approved by the Aviation Authority, based on the unit prices. This contract includes a Minority and Women Business Enterprise (MWBE) and a Local Developing Business (LDB) participation requirement. The participation goal for this contract is 45% for MWBE and 11% for LDB. The Office of Small Business Development certifies that the contract is in good standing as it relates to MWBE/LDB participation. The fiscal impact for the second renewal option is a not-to-exceed amount of $1,438,995.03 with funding from the Operations and Maintenance Fund, 301.631.510.5340004.000.100001 and 301.631.210.5340004.000.100001. Funds expected to be spent under the contract in the current fiscal year are within budget. Funding required in current and subsequent fiscal years will be allocated from the Operations and Maintenance Fund, as approved through the budget process and when funds become available. It is respectfully requested that the Concessions/Procurement Committee approve the following be recommended to the Aviation Authority Board: (1) approve Amendment No. 5, Second Renewal Option for Purchasing Contract 03-17, Landside Terminal Landscape Maintenance and Irrigation Services with Carol King Landscape, Inc.; (2) authorize funding from the Operations and Maintenance Fund in the not-to-exceed amount of $1,438,995.03; and (3) authorize an Aviation Authority Officer or the Chief Executive Officer to execute the necessary documents following satisfactory review by legal counsel. Chairman Friel asked if anyone on the call would like to speak regarding this item. Ms. Bou confirmed she had not received any speaker requests. He then asked if any Committee member had questions or comments. The Committee did not have questions or comments regarding this item. Upon motion by Vice Chair Sharman, second by Mr. Draper, motion passed unanimously by roll call vote, to approve staff’s recommendation. RECOMMENDATION TO APPROVE AMENDMENT NO. 1, CONTRACT ADJUSTMENT FOR PURCHASING CONTRACT 12-19, SOUTH AIRPORT COMPLEX (SAC) TRAILER COMPLEX JANITORIAL MAINTENANCE, LOCAL DEVELOPING BUSINESS (LDB), WITH AMERICAN JANITORIAL MAINTENANCE AND SERVICES, INC. (AMERICAN JANITORIAL) 3. Ms. Schneider presented the item. The initial term of the contract commenced on May 1, 2019 and expires on April 30, 2022, with the Aviation Authority having two (2) options to renew the contract for an additional period of one (1) year each. The contract requires American Janitorial to furnish all labor, supervision, equipment, tools, janitorial cleaning supplies (except hand soap and trash liners), paper products (except paper towels and toilet tissue), fuel, oil, lubricants, uniforms and all other items necessary or proper for, or incidental to, performing South Airport Complex (SAC) Trailer Complex Janitorial Maintenance for office trailers located at the Orlando International Airport, in accordance with the contract documents. Contract Adjustment – Staff is requesting to adjust the contract by adding ten (10) new office trailers at the South Terminal Complex. These trailers are being added to house Aviation Authority staff and Owner’s Authorized Representatives (OARs) who support construction activities of the South Terminal Complex. The new office trailers will be cleaned at the same frequencies and pricing as the original six (6) trailers under the current contract. Services to clean the new trailers became effective June 8, 2020, and will continue through the remainder of the contract. Pricing is based on the daily prices for 3-day cleaning and cycle cleaning for each trailer. There is also an hourly rate for additional services, when needed. The total price for adding the ten (10)
MINUTES FOR THE JULY 27, 2020, CONCESSIONS/PROCUREMENT COMMITTEE
PAGE 3
RECOMMENDATION TO APPROVE AMENDMENT NO. 1, CONTRACT ADJUSTMENT FOR PURCHASING CONTRACT 12-19, SOUTH AIRPORT COMPLEX (SAC) TRAILER COMPLEX JANITORIAL MAINTENANCE, LOCAL DEVELOPING BUSINESS (LDB), WITH AMERICAN JANITORIAL MAINTENANCE AND SERVICES, INC. (AMERICAN JANITORIAL) - (con’t) office trailers is a not-to-exceed amount of $133,843.50. Staff will amend the contract for increases in frequencies as they become necessary. Department – Concurs with the contract adjustment. Contractor – Based on the information known at this time, the contractor is performing satisfactorily during the initial term of the contract. The total not-to-exceed price for this contract adjustment is $133,843.50. This contract has been designated as a direct procurement for a Local Developing Business (LDB). The Small Business Development department certifies that this contract is in good standing as it relates to LDB participation. The fiscal impact is a total not-to-exceed amount of $133,843.50 with funding from the Operations and Maintenance Fund 301.631.170.5340005.000.100882. Funds expected to be spent under the contract in the current fiscal year are within budget. Funding required in current and subsequent fiscal years will be allocated from the Operations and Maintenance Fund as approved through the budget process and when funds become available. It is respectfully requested that the Concessions/Procurement Committee approve that the following be recommended to the Aviation Authority Board: (1) approve Amendment No. 1, Contract Adjustment for Purchasing Contract 12-19, South Airport Complex (SAC) Trailer Complex Janitorial Maintenance Local Developing Business (LDB) with American Janitorial Maintenance and Services, Inc.; (2) authorize funding in the not-to-exceed amount of $133,843.50 from the Operations and Maintenance Fund; (3) authorize an Aviation Authority Officer or Chief Executive Officer to execute the necessary documents following satisfactory review by legal counsel. Chairman Friel asked if anyone on the call would like to speak regarding this item. Ms. Bou confirmed she had not received any speaker requests. He then asked if any Committee member had questions or comments. Vice Chair Sharman asked if there was a price increase on this item. Ms. Schneider explained that there is no price increase. The increased amount is due to the addition of 10 trailers. Upon motion by Mr. Draper, second by Mr. Friel, motion passed unanimously by roll call vote, to approve staff’s recommendation. Vice Chair Sharman congratulated Mr. Friel on his appointment as Chairman of the Concessions/Procurement Committee. ADJOURNMENT
4. Chairman Friel asked if there was further business to discuss before the Committee. Having no further business to discuss, he adjourned the meeting at 1:43 p.m.
(Digitally signed on September 24, 2020) _______________________________ ____________________________________ Larissa Bou Brad Friel Recording Secretary Chairman
PAGE 1
On AUGUST 10, 2020, the CONCESSIONS/PROCUREMENT COMMITTEE of the GREATER ORLANDO AVIATION AUTHORITY met in regular session telephonically with the meeting live streamed on YOUTUBE (OrlandoAirports) and GOTOMEETING. Chairman Friel called the meeting to order at 1:30 p.m. The meeting was posted in accordance with Florida Statutes with a quorum participating. Office of the Governor, Executive Order Number 20-69 Committee members present: Brad Friel, Chairman Kathleen Sharman, Vice Chair Brian Engle, Director of Customer Experience Deborah Silvers, Director of Risk Management Staff/Others present: Denise Schneider, Assistant Director of Purchasing Dan Gerber, Interim General Counsel Jo Thacker, Nelson Mullins, Legal Counsel Larissa Bou, Recording Secretary Chairman Friel announced to all present that if a bidder or proposer is aggrieved by any of the proceedings of today’s meeting and wishes to appeal the results of actions made by this Committee, they must file an appeal stating the item they wish to appeal and the basis for which they wish to appeal, and it must be received in writing by the Chief Executive Officer, Mr. Phillip N. Brown, via email [email protected] with copy to [email protected], by Monday, August 17, 2020 at 4:00 p.m. (emails will be accepted during the pandemic COVID-19). For individuals who conduct lobbying activities with Aviation Authority employees or Board members, registration with the Aviation Authority is required each year prior to conducting any lobbying activities. A statement of expenditures incurred in connection with those lobbying instances should also be filed prior to April 1 of each year for the preceding year. As of January 16, 2013, lobbying any Aviation Authority Staff who are members of any committee responsible for ranking Proposals, Letters of Interest, Statements of Qualifications or Bids and thereafter forwarding those recommendations to the Board and/or Board Members is prohibited from the time that a Request for Proposals, Request for Letters of Interests, Request for Qualifications or Request for Bids is released to the time that the Board makes an award. In the event a lobbyist meets with or otherwise communicates with Staff or a Board member, including the Mayor of the City of Orlando or the Mayor of Orange County, the lobbyist shall file a Notice of Lobbying (Form 4) detailing each instance of lobbying to the Aviation Authority within 7 calendar days of such lobbying. As of January 16, 2013, lobbyists will also provide a notice to the Aviation Authority when meeting with the Mayor of the City or Mayor of Orange County at their offices. The policy, forms, and instructions are available on the web site. Please contact the Director of Board Services with questions at (407) 825-2032. Chairman Friel began the meeting by welcoming Ms. Silvers as a member of the Concessions/Procurement Committee. RECOMMENDATION TO APPROVE AMENDMENT NO. 4, SECOND RENEWAL OPTION FOR PURCHASING CONTRACT 06-17, TRASH REMOVAL SERVICES WITH REPUBLIC SERVICES OF FLORIDA, LP (REPUBLIC) 1. Ms. Schneider presented the item. The initial term of the contract is for thirty-six (36) months, which commenced on October 1, 2016 and expired September 30, 2019, with the Aviation Authority having options to renew the contract for two (2) additional periods of one (1) year each. The first renewal option is due to expire on September 30, 2020. This contract requires Republic to furnish all labor, supervision, trucks, equipment, materials, and tools necessary to furnish and install trash compactors and/or trash containers. Services shall also include the pick-up and/or removal of wet and dry compacted and non-compacted trash/refuse and all other items necessary or proper for, or incidental to, performing trash removal services from various locations throughout the Orlando International Airport, in accordance with the contract documents. Second Renewal Option – October 1, 2020 to September 30, 2021. Department – Concurs with the second renewal option.
MINUTES FOR THE AUGUST 10, 2020, CONCESSIONS/PROCUREMENT COMMITTEE
PAGE 2
RECOMMENDATION TO APPROVE AMENDMENT NO. 4, SECOND RENEWAL OPTION FOR PURCHASING CONTRACT 06-17, TRASH REMOVAL SERVICES WITH REPUBLIC SERVICES OF FLORIDA, LP (REPUBLIC) – (con’t) Contractor – Based on information known at this time, Republic has performed satisfactorily during the initial term and first renewal option. This contract does not include a Minority and Women Business Enterprise (MWBE) or a Local Developing Business (LDB) participation requirement. The contractor has agreed to renew the contract at the same price, terms and conditions. The fiscal impact for the Second Renewal Option is a not-to-exceed amount of $437,370. Funding will be from the Operations and Maintenance Fund 301.416.170.5340007.000.000000. Funds expected to be spent under the contract in the current fiscal year are within budget. Funding required in current and subsequent fiscal years will be allocated from the Operations and Maintenance Fund, as approved through the budget process and when funds become available. It was respectfully requested that the Concessions/Procurement Committee approve that the following be recommended to the Aviation Authority Board: (1) approve Amendment No. 4, Second Renewal Option to Purchasing Contract 06-17, Trash Removal Services, with Republic Services of Florida, LP; (2) authorize funding in a not-to-exceed amount of $437,370 from the Operations and Maintenance Fund; and (3) authorize an Aviation Authority Officer or the Chief Executive Officer to execute the necessary documents following satisfactory review by legal counsel. Chairman Friel asked if anyone on the call would like to speak regarding this item. Ms. Bou confirmed she had not received any speaker requests. He then asked if any Committee member had questions or comments. Mr. Engle asked if the price drop shown on Attachment A (copy on file) is due to the reduction of operations. Ms. Schneider responded in the affirmative, and further indicated that this is based on the amount of trash removals estimated by staff. Upon motion by Vice Chair Sharman, second by Mr. Engle, motion passed unanimously by roll call vote, to approve staff’s recommendation. RECOMMENDATION FOR PAYMENT OF LANDFILL FEES RELATED TO PURCHASING CONTRACT 06-17, TRASH REMOVAL SERVICES 2. Ms. Schneider presented the item. Purchase Orders (POs) will be issued to pay for landfill fees when trash removed from the Aviation Authority’s premises by Republic is transported and disposed of as required by the Aviation Authority, in accordance with Purchasing Contract 06-17. Purchasing Contract allows Republic to transport and dispose of all solid waste, as requested by the Aviation Authority, at the Orange County Landfill or any other Environmental Protection Agency (EPA) approved landfill facility within a 20 mile radius from the Airport. Furthermore, Purchasing Contract 06-17 allows for the landfill facilities to be selected by Republic, provided that the fees charged at the selected landfill facility do not exceed the fees charged by Orange County Landfill. The fees will be billed directly to the Aviation Authority. Allow multiple (POs) to be issued to various landfill facilities associated with Purchasing Contract 06-17, Trash Removal Services – October 1, 2020 to September 30, 2021. Department – Concurs with issuing purchase orders. Purchasing Contract 06-17 does not include a Minority or Women Business Enterprise (MWBE) and a Local Developing Business (LDB) participation requirement. The fiscal impact for the payment of landfill fees related to Purchasing Contract 06-17 is a not-to-exceed amount of $364,800. Funding will be from the Operations and Maintenance Fund 301.416.170.5430001.000.000000. Funds expected to be spent under the contract in the current fiscal year are within budget. Funding required in current and subsequent
MINUTES FOR THE AUGUST 10, 2020, CONCESSIONS/PROCUREMENT COMMITTEE
PAGE 3
RECOMMENDATION FOR PAYMENT OF LANDFILL FEES RELATED TO PURCHASING CONTRACT 06-17, TRASH REMOVAL SERVICES (con’t) fiscal years will be allocated from the Operations and Maintenance Fund, as approved through the budget process and when funds become available. It was respectfully requested that the Concessions/Procurement Committee approve that the following be recommended to the Aviation Authority Board: (1) allow multiple purchase orders to be issued to various landfill facilities related to Purchasing Contract 06-17, Trash Removal Services; (2) authorize funding in a not-to-exceed amount of $364,800 from the Operations and Maintenance Fund for payment of landfill fees related to Purchasing Contract 06-17; and (3) authorize the Purchasing staff to issue the necessary Purchase Orders. Chairman Friel asked if anyone on the call would like to speak regarding this item. Ms. Bou confirmed she had not received any speaker requests. He then asked if any Committee member had questions or comments. There were no comments or questions posed. Upon motion by Vice Chair Sharman, second by Ms. Silvers, motion passed unanimously by roll call vote, to approve staff’s recommendation. RECOMMENDATION TO APPROVE AMENDMENT NO. 2, SECOND RENEWAL OPTION FOR PURCHASING CONTRACT 12-17, VEHICLE TOWING AND STORAGE SERVICES WITH STEPP’S TOWING SERVICE (STEPP’S TOWING) 3. Ms. Schneider presented the item. The initial term of the contract was for thirty-six (36) months, which commenced on February 1, 2017 and expired January 31, 2020, with the Aviation Authority having options to renew the contract for two (2) additional periods of one (1) year each. The first renewal option is due to expire on January 31, 2021. The contract requires Stepp’s Towing to furnish all labor, supervision, materials, signage, equipment, facilities, tools and all other accessories, activities and procedures necessary, or proper for, or incidental to, performing vehicle towing (up to and including 10,000 pounds), removal and storage services required at the Orlando International Airport (OIA) and at the Orlando Executive Airport (OEA) in accordance with the contract documents. Second Renewal Option: February 1, 2021 – January 31, 2022. Department - Concurs with the renewal. Contractor – Based on the information known at this time, the contractor has performed satisfactorily during the initial term and the first renewal option of the contract. This is a service contract for vehicle towing and storage services. Pricing for this service is based on unit prices for OIA Towing Services (Non-Standby): (A) relocation/towing to Aviation Authority Impound Lot; (B) Towing to contractor’s storage facilities; (C) relocation/towing to/within Aviation Authority property; (D) hourly rate (for tow truck stationed on Aviation Authority property); (E) relocation/towing to Aviation Authority impound lot; and (F) drop fee (rates for towing in connection with standby service). Pricing for OEA include: (G) relocation/towing to contractor’s storage and (H) relocation/towing to/within Aviation Authority property. Under additional services, the items required to be provided were: (I) deliver and retrieve junked vehicles to OIA Aircraft Rescue and Fire Fighting (ARFF) for training purposes and (J) return of previously relocated vehicles from contractor’s facility to OIA. The total not-to-exceed price for the Second Renewal Option is $329,450 with no increase in pricing from the First Renewal Option. These services will become effective February 1, 2021 through January 31, 2022. This contract did not include a Minority and Women Business Enterprise (MWBE) or Local Developing Business (LDB) participation requirement. The fiscal impact is a total not-to-exceed amount of $329,450 with funding from the Operations and Maintenance Fund 301.238.210.5340007.000.000000. Funds expected to be spent under the contract in the current fiscal year are within budget. Funding required
MINUTES FOR THE AUGUST 10, 2020, CONCESSIONS/PROCUREMENT COMMITTEE
PAGE 4
RECOMMENDATION TO APPROVE AMENDMENT NO. 2, SECOND RENEWAL OPTION FOR PURCHASING CONTRACT 12-17, VEHICLE TOWING AND STORAGE SERVICES WITH STEPP’S TOWING SERVICE (STEPP’S TOWING) – (con’t) in current and subsequent fiscal years will be allocated from the Operations and Maintenance Fund as approved through the budget process and when funds become available. It was respectfully requested that the Concessions/Procurement Committee approve that the following be recommended to the Aviation Authority Board: (1) approve Amendment No. 2, Second Renewal Option for Purchasing Contract 12-17, Vehicle Towing and Storage Services with Stepp’s Towing Service; (2) authorize funding in the not-to-exceed amount of $329,450 from the Operations and Maintenance Fund; and (3) authorize an Aviation Authority Officer or Chief Executive Officer to execute the necessary documents following satisfactory review by legal counsel. Chairman Friel asked if anyone on the call would like to speak regarding this item. Ms. Bou confirmed she had not received any speaker requests. He then asked if any Committee member had questions or comments. Mr. Engle asked if this is an estimated cost. Ms. Schneider explained that this is a set amount, as the towing company needs to be at the curb 24/7 per TSA requirements. Vice Chair Sharman made reference to Attachment C (copy on file), and asked for clarification regarding variable charges. Ms. Schneider explained that there are other charges such as storage and fees that are the responsibility of the party whose vehicle is towed, and some additional charges that may be the responsibility of the Aviation Authority. Upon motion by Mr. Engle, second by Ms. Silvers, motion passed unanimously by roll call vote, to approve staff’s recommendation. Chairman Friel asked if there were any other business to discuss. Ms. Thacker indicated that, due to technical difficulties, Mr. Gerber was unable to join the call. On behalf of Mr. Gerber, Ms. Thacker stated that Mr. Gerber has been working on developing a policy on conflicts of interest for the Aviation Authority committees; therefore, there would be a formalized process for all committee members to follow, as it relates to their responsibilities. Information, training and further discussion will follow. ADJOURNMENT
4. Chairman Friel asked if there was further business to discuss before the Committee. Having no further business to discuss, he adjourned the meeting at 1:48 p.m.
(Digitally signed on September 24, 2020) _______________________________ ____________________________________ Larissa Bou Brad Friel Recording Secretary Chairman
PAGE 1
On WEDNESDAY, AUGUST 19, 2020, the FINANCE COMMITTEE of the Greater Orlando Aviation Authority met virtually via CISCOWEBEX. Vice Chair Good called the meeting to order at 12:00 p.m. The meeting was posted in accordance with Florida Statutes with a quorum participating. Office of the Governor, Executive Order Number 20-69
Committee members present, M. Carson Good, Vice ChairMayor Buddy Dyer, Board MemberRafael E. Martinez, Board Member
Also present, Phillip N. Brown, Chief Executive Officer Kathleen Sharman, Chief Financial Officer Kathy Bond, Senior Director of Human Resources Tianna Dumond, Director of Internal Audit Marie Dennis, Interim Director of Finance Dan Gerber, Rumberger Kirk Dianne Klaiss, Frasca & Associates, LLC Doug Starcher, Legal Counsel, Nelson Mullins Larissa Bou, Recording Secretary
For individuals who conduct lobbying activities with Aviation Authority employees or Board members, registration with the Aviation Authority is required each year prior to conducting any lobbying activities. A statement of expenditures incurred in connection with those lobbying instances should also be filed prior to April 1 of each year for the preceding year. As of January 16, 2013, lobbying any Aviation Authority Staff who are members of any committee responsible for ranking Proposals, Letters of Interest, Statements of Qualifications or Bids and thereafter forwarding those recommendations to the Board and/or Board Members is prohibited from the time that a Request for Proposals, Request for Letters of Interests, Request for Qualifications or Request for Bids is released to the time that the Board makes an award. As adopted by the Board on September 19, 2012, lobbyists are now required to sign-in at the Aviation Authority offices prior to any meetings with Staff or Board members. In the event a lobbyist meets with or otherwise communicates with Staff or a Board member at a location other than the Aviation Authority offices, the lobbyist shall file a Notice of Lobbying (Form 4) detailing each instance of lobbying to the Aviation Authority within 7 calendar days of such lobbying. As of January 16, 2013, Lobbyists will also provide a notice to the Aviation Authority when meeting with the Mayor of the City of Orlando or the Mayor of Orange County at their offices. The policy, forms, and instructions are available in the Aviation Authority’s offices and the web site. Please contact the Director of Board Services with questions at (407) 825-2032.
MINUTES 1. Upon motion by Mr. Martinez, second by Mayor Dyer, motion passed unanimously
by roll call vote to accept the July 15, 2020, Finance Committee minutes as written.
CONSENT AGENDA 2. Upon motion by Mayor Dyer, second by Mr. Martinez, motion passed unanimously
by roll call vote to approve the following: A. accept the Ad Hoc Committee’s recommendation to: (1) award Purchasing
Proposal 03-21 Supplemental Auditing and Attestation Engagement Services to both Covington & Associates CPA, Inc., and L.F. Harris & Associates, CPA, P.A., for a Contract term of thirty-six (36) months with the initial service to commence on or about October 1, 2020, and with the Aviation Authority having options to renew the Contract for two (2) additional periods of one (1) year each, upon mutual agreement; (2) approve a totalnot-to-exceed Contract value of $550,000 for the base Contract term of 3 years to beallocated from the Operations and Maintenance Fund; and (3) authorize an AviationAuthority Officer or the Chief Executive Officer to enter into one or more agreementsfor Supplemental Auditing and Attestation Engagement Services, following satisfactorylegal review.
B. accept staff’s recommendation to: (1) consent to the assignment of theCustody Agreement from Wells Fargo Retirement & Trust Services to Principal Financial Group and (2) authorize an Aviation Authority Officer or the Chief Executive Officer to execute any and all documents, including the Service Continuity Agreement, deemed necessary to facilitate the consent to assignment, following satisfactory legal review.
ADJOURNMENT 3. There being no further business to be considered, Vice Chair Good adjourned the
meeting at 12:05 p.m.
(Digitally signed on October 7, 2020)
Larissa Bou Phillip N. Brown Recording Secretary Chief Executive Officer
On TUESDAY, MAY 26, 2020, the CONSTRUCTION COMMITTEE met in regular session
telephonically with the meeting live streamed on You Tube (www.OrlandoAirports.net).
Chairman Thornton called the meeting to order at 8:31 a.m. The meeting was posted
in accordance with Florida Statutes with a quorum participating. Office of the
Governor, Executive Order Number 20-69
Participating Committee members,
Stanley J. Thornton, Chairman
Kathleen Sharman, Chief Financial Officer
Mike Patterson, Director of Construction
Gary Hunt, Director of Maintenance
Denise Schneider, Assistant Director of Purchasing and Material Control
Also participating:
Davin Ruohomaki, GOAA Senior Director of Planning, Engineering, and Construction
Karen Ryan, Legal Counsel (Nelson Mullins Broad & Cassel)
Ian Brooks, GOAA Information Technology
John Carlson, GOAA Construction
Scott Shedek, GOAA Construction
Chris Kieffer, A2 Group, Inc.
Don Corthell, PSA Management, Inc.
Jamie McGonagill, Geotech Consultants International, Inc. dba GCI, Inc.
Nils Johnson, Geotech Consultants International, Inc. dba GCI, Inc.
Vicki Harvey, Hahn Integrated Systems, Inc.
Tara Ciaglia, Recording Secretary
LOBBYIST DISCLOSURE
Parties present were reminded that for individuals who conduct lobbying activities
with Aviation Authority employees or Board members, registration with the Aviation
Authority is required each year prior to conducting any lobbying activities. A
statement of expenditures incurred in connection with those lobbying instances should
also be filed prior to April 1st of each year for the preceding year. As of January
16, 2013, lobbying any Aviation Authority Staff who are members of any committee
responsible for ranking Proposals, Letters of Interest, Statements of Qualifications
or Bids and thereafter forwarding those recommendations to the Board and/or Board
Members is prohibited from the time that a Request for Proposals, Request for Letters
of Interests, Request for Qualifications or Request for Bids is released to the time
that the Board makes an award. As adopted by the Board on September 19, 2012,
lobbyists are now required to sign-in at the Aviation Authority offices prior to any
meetings with Staff or Board members. In the event a lobbyist meets with or otherwise
communicates with Staff or a Board member at a location other than the Aviation
Authority offices, the lobbyist shall file a Notice of Lobbying (Form 4) detailing
each instance of lobbying to the Aviation Authority within 7 calendar days of such
lobbying. As of January 16, 2013, lobbyists will also provide a notice to the
Aviation Authority when meeting with the Mayor of the City of Orlando or the Mayor
of Orange County at their offices. The policy, forms, and instructions are available
in the Aviation Authority’s offices and the website. Please contact the Director
of Board Services with questions at (407) 825-2032.
ANNOUNCEMENT
Any appeals of decisions made by the Construction Committee must be filed with the
Chief Executive Officer within five business days (no later than 4:00 p.m. on the
fifth business day) of the rendering of that decision. If a bidder or proposer is
aggrieved by any of the proceedings of today’s meeting and wishes to appeal the
results of actions made by this committee, they must file an appeal stating the item
they wish to appeal and the basis for which they wish to appeal, and it must be
received in writing by the Chief Executive Officer, Mr. Phillip N. Brown, via email
[email protected], with a copy to [email protected] (emails will be accepted during the
COVID-19 pandemic.)
Minutes of the Construction Committee Meeting, May 26, 2020
Page 2 of 59
COVID-19 ANNOUNCEMENT
Due to COVID-19, the Aviation Authority is adhering to a business distancing
operational plan. Please note that all Construction Committee meetings from today
until further notice will be held telephonically. If you would like to speak at the
meeting on an agenda item being considered, please contact the Recording Secretary,
Tara Ciaglia ([email protected] -or- 407-825-4461) no less than 24 hours in
advance of the meeting. Otherwise, the Construction Committee will be available via
Live Stream at www.orlandoairports.net.
MINUTES
1. The following minutes were presented for consideration:
CONSIDERATION OF MARCH 24, 2020 MINUTES
A. Upon motion of Mr. Patterson, second by Mr. Hunt, vote carried to approve the Construction Committee Minutes from the meeting held on March 24, 2020, as
presented.
CONSIDERATION OF MARCH 31, 2020 MINUTES
B. Upon motion of Mr. Patterson, second by Mr. Hunt, vote carried to approve the Construction Committee Minutes from the meeting held on March 31, 2020, as
presented.
CHANGE ORDER AGENDA
2. The following Change Orders were presented for consideration:
A. Change Order BP-00491-07 VARIOUS REVISIONS. This change order to the contract with H. W. Davis Construction, Inc. for West Security Screening Check Point
Expansion - Package 2 is to: 1. Provide labor, materials, and equipment to
level the existing concrete floor on Level 3. ADD: $31,565.00; and, 2. Provide
labor, materials, and equipment to install concrete column protection on Level
2 bag make-up. ADD: $13,256.00.
Upon motion of Mr. Hunt, second by Mr. Patterson, vote carried by roll-call
with all votes yea, to approve Change Order BP-00491-07, for a total amount
of $44,821.00 and no time extension, with funding from previously-approved
Capital Expenditure Funds and General Airport Revenue Bonds.
B. Change Order E-00239-02 VARIOUS REVISIONS. This change order to the contract with BergElectric Corp. dba Bergelectric Corp. Contractors and Engineers for
Miscellaneous Light Fixtures for Parking Garages A, B and Terminal Top is to:
1. Provide all labor, material and equipment to provide power to nine new Type
C2 and Type C3 fixtures. (Reference Contractor’s BECO-005). ADD: $15,546.61;
2. Provide all labor, material and equipment to change one existing stairwell
lighting circuit in the B Garage at Column Line N.5/28 from normal power to
emergency power. (Reference Contractor’s BECO-006). ADD: $1,631.19; 3. Provide
all labor, material and equipment to change the four existing Garage A and
Garage B helix lights from normal power to emergency power. (Reference
Contractor’s BECO-007). ADD: $6,543.60; 4. Provide all labor, material and
equipment to bring the existing lighting circuits for the B-Side auto-bridge
lights within the National Electric Code requirements. (Reference Contractor’s
BECO-008). ADD: $4,146.76; 5. Provide all labor, material and equipment to
install pendent supports for eight B-type fixtures at the R1 level of the A
and B Garages. (Reference Contractor’s BECO-010). ADD: $1,887.04; and, 6.
Reduce Allowance No. 1, Miscellaneous Wiring and Conduit Work, by ($29,755.20),
from $80,317.20 to $50,562.00, to offset the costs associates with Item Nos.
1, 2, 3, 4 and 5 above. DEDUCT: ($29,755.20).
Upon motion of Ms. Schneider, second by Ms. Sharman, vote carried by roll-call
with all votes yea, to approve Change Order E-00239-02, for a total amount of
Minutes of the Construction Committee Meeting, May 26, 2020
Page 3 of 59
$0.00 and no time extension, with funding from previously-approved Airport
Facility Discretionary Funds, and Capital Expenditure Funds.
C. Change Order E-00263-02 TERMINATION FOR CONVENIENCE. This item was deferred.
D. Change Order E-S00010-01 VARIOUS REVISIONS. This change order to the contract with Stryker Electrical Contracting, Inc. for Install Fountains at South APM
Pond is the final change order and includes the following: 1. Provide all
labor, equipment and materials to perform a directional bore underneath the
Passenger Drop-off Lobby (PDL) bus loop, to provide a path for power to the
fountain equipment rack. This change order replaces Field Change Order No.
1. ADD: $6,393.00; 2. Provide all labor, equipment, and materials to upgrade
the electrical service to the pond fountain equipment rack, from 125 amperes
to 200 amperes, as well as install a concrete pad at the equipment rack to
accommodate proposed future fountain equipment. This change order replaces
Field Change Order No. 2. ADD: $19,562.00; and, 3. Provide all labor,
equipment, and materials to eliminate three unnecessary disconnects from the
scope of work. DEDUCT: ($3,329.00).
Upon motion of Ms. Sharman, second by Mr. Patterson, vote carried by roll-call
with all votes yea, to approve Change Order E-S00010-01, for a total amount
of $22,626.00 and no time extension, with funding from previously-approved
Capital Expenditure Funds.
E. Change Order L-00038-01 FINAL ADJUSTMENT OF NTE CONTRACT. This change order to the contract with Orlando Business Telephone Systems, Inc. for Red Lot
Communications Room to North Terminal Fiber Installation (OBTS) is the final
change order and includes the final contract adjustment to reflect the actual
cost of time and material expended to complete the work. The original contract
amount was $85,702.84; actual material and labor expenditure totaled
$85,667.49. This change order reduces the contract amount by ($35.35) for a
final contract amount of $85,667.49. DEDUCT: ($35.35).
Upon motion of Ms. Schneider, second by Ms. Sharman, vote carried by roll-call
with all votes yea, to approve Change Order L-00038-01, for a total deductive
amount of ($35.35) and no time extension, with funding credited to previously-
approved Capital Expenditure Funds.
F. Change Order R-S00001-02 VARIOUS REVISIONS. This change order to the contract with P&A Roofing and Sheet Metal, Inc. for HBJ Warehouse Roof Replacement is
the final change order and includes the following: 1. Reduce the Allowance for
Roof-Mounted Curbs for HVAC Equipment by ($25,000.00), from $25,000.00 to
$0.00, for the unused portion of the Allowance. DEDUCT: ($25,000.00); and,
2. Increase the Contract Time for Substantial Completion by 146 calendar days,
from 330 calendar days to 476 calendar days. ADD: $0.00.
Upon motion of Mr. Hunt, second by Mr. Patterson, vote carried by roll-call
with all votes yea, to recommend to the Aviation Authority Board approval of
Change Order R-S00001-02, for a total deductive amount of ($25,000.00) and a
146 calendar day time extension to Substantial Completion, with funding
credited to previously-approved Capital Expenditure Funds.
G. Change Order V-00867-03 VARIOUS REVISIONS. This item was deferred.
H. Change Order V-00943-02 VARIOUS REVISIONS. This change order to the contract with Gomez Construction Company for Airsides 2 and 4 Guideway Running Surface
Refurbishment (Design/Build) is to: 1. Add New Pay Item Additional Full Width
Plinth Repairs, 175 square feet (SF), at a contract unit price of $155.65/SF,
which includes all labor, equipment and material for each additional SF of
Minutes of the Construction Committee Meeting, May 26, 2020
Page 4 of 59
full width plinth repair in excess of the 200 SF of full width repairs already
included in the Contract. Payment will be made based on the actual quantity
of Additional Full Width Plinth Repairs constructed. ADD: $27,238.75; 2.
Change Pay Item No. 12 (Cleaning, HMWM Sealing of Cracks) with an estimated
quantity of 17,600 SF at an extended Contract Price of $143,704.00, to be a
lump sum pay item at the same Contract Price for sealing the entire guideway
concrete plinth surface from the landside buffer end to the airside buffer
end, for both A2 and B4 APM Systems, at no additional cost. ADD: $0.00; and,
3. Provide a complete design, signed and sealed by a Florida Professional
Engineer, to repair and strengthen the support structure for the steel grating
located on the elevated slab portion of the maintenance platform within
Bombardier’s Landside Terminal Automated People Mover (APM) maintenance
facility. Also include in the design details for repairing the concrete spall
located adjacent to the steel grating at Track 4800. This change order replaces
Field Change Order No.1. ADD: $2,192.30. The parties negotiated this price
and agree that this change order is within the scope of the original contract
and does not materially alter the original contract such that a cardinal or
constructive change to the original agreement has occurred.
Upon motion of Ms. Sharman, second by Mr. Hunt, vote carried by roll-call with
all votes yea, to approve Change Order V-00943-02, for a total amount of
$29,431.05 and no time extension, with funding from previously-approved Capital
Expenditure Funds.
I. Change Order V-00947-02 VARIOUS REVISIONS. This item was deferred.
J. Change Order V-S00008-06 VARIOUS REVISIONS. [A handout was presented, which included a revised Coversheet and Supporting Documentation.] This change
order to the contract with Gomez Construction Company for HBJ HVAC Replacement
and Miscellaneous Electrical Improvements is the final change order and
includes the following: 1. Provide labor, material, and equipment to replace
the blower motor and belt for rooftop Air Handler Unit (AHU) No. 5. This
change order replaces Field Change Order (FCO) No. 1. ADD: $1,764.50; 2. Bond
reconciliation due to added bond costs. ADD: $202.00; and, 3. Increase the
Contract Time for Substantial Completion by 267 calendar days, from 150
calendar days to 417 calendar days.
Chairman Thornton asked if there were any additional cost. Mr. Shedek replied
no.
Upon motion of Mr. Hunt, second by Ms. Sharman, vote carried by roll-call with
all votes yea, to recommend to the Aviation Authority Board approval of Change
Order V-S00008-06, for a total amount of $1,966.50 and a 267 calendar day time
extension to Substantial Completion, with funding from previously-approved
Capital Expenditure Funds.
CONSTRUCTION MANAGEMENT AT RISK (CM@R) GUARANTEED MAXIMUM PRICE (GMP) BUDGET, BUYOUT,
AND CONTINGENCY MANAGEMENT REQUESTS AGENDA
3. The following GMP Budget, Buyout, and Contingency Management requests (related
to the South Terminal C, Phase One Project) were presented for consideration:
A. Subcontract Modification for BP-S00139 (GMP No. 5-S.2) with The Middlesex Corporation for CR0212.1-LSC-5S.2-Wooded Buffer Root Material. Mr. Corthell
presented the memorandum, requesting approval for Turner-Kiewit Joint Venture
(TKJV) to issue a Subcontract Modification on BP-S00139, South Terminal C,
Phase 1 – Landside Civil (GMP No. 5-S.2), at the Orlando International Airport,
in the total amount of $89,521.00 to The Middlesex Corporation for CR0212.1-
LSC-5S.2-Wooded Buffer Root Material. Bid Package 31.0.0 "Sitework" was
Minutes of the Construction Committee Meeting, May 26, 2020
Page 5 of 59
previously awarded within GMP No. 5-S.2 to The Middlesex Corporation, CC No.
20180504.05A.
TKJV is proposing a subcontract modification to The Middlesex Corporation in
the total lump sum amount of $89,521.00 for CR0212.1-LSC-5S.2-Wooded Buffer
Root Material. LSC Bulletin 13 relocated utilities through the wooded buffer
area that was previously designated as green space. Since there are now
permanent embankments and utilities in the wooded buffer area, Section 110-
02.2 of FDOT standard specification becomes relevant and requires removal of
all roots to a depth of at least 12-inches below finished excavation surface.
The modified scope of work consists of all additional labor, material and
equipment costs associated with removing roots from the wooded buffer area
that was priced as a green area and now has duct bank running through it. The
additional scope includes costs to furnish A3 select fill, to haul and remove
root materials from 1-foot deep in cleared area and costs to place and compact
new A3 select backfill to replace removed root material.
The approval of this subcontract modification to The Middlesex Corporation
resolves all requests for costs and time associated with CR0212.1-LSC-5S.2-
Wooded Buffer Root Material.
TKJV has submitted documentation including the subcontractor's proposal to
support their request. An independent cost Review is included. By approving
this request, the Owner does not waive its right to enforce the contract
requirements for other requests for cost or time.
The effect of this Subcontractor Modification for this project is as follows:
TKJV to issue a subcontract award to The Middlesex
Corporation in the lump sum amount of: $ 89,521.00
Deduct from P1X CM@R Contingency: $ (89,521.00)
Turner-Kiewit Joint Venture is committed to 20% MWBE and 4% LDB participation
for Construction Services. The subcontractor identified and committed to
participate on BP-S00139 (GMP No. 5-S.2) for this subcontract modification is
The Middlesex Corporation (Non-MWBE/LDB/VBE). There is 51.9% LDB participation
associated with this modification.
Ms. Sharman asked if this request takes into account any potential reductions
to the GMP. Mr. Corthell answered yes.
Agenda Item Nos. 3-A, 3-B, 3-C, 3-D, 3-E, 3-F, 3-G, 3-H, 3-I, 3-J, 3-K, 3-L,
3-M, 3-N, 3-O, 3-P, 3-Q, 3-R, 3-S, 3-T, 3-U, 3-V, 3-W, 3-X, 3-Y, 3-Z, 3-AA,
3-BB, 3-CC, 3-DD, 3-EE, 3-FF, 3-GG, 3-HH, 3-II, 3-JJ, 3-KK, 3-LL, 3-MM, 3-NN,
3-OO, 3-PP, 3-QQ, 3-RR, 3-SS, 3-TT, 3-UU, 3-VV, 3-WW, 3-XX, and 3-YY were
considered in one motion.
Upon motion of Mr. Hunt, second by Ms. Schneider, vote carried by roll-call,
with all votes yea, to approve Turner-Kiewit Joint Venture to issue a
Subcontractor Modification to The Middlesex Corporation on BP-S00139, South
Terminal C, Phase 1 – Landside Civil (GMP No. 5-S.2), for the total lump sum
amount of $89,521.00, with funding from General Airport Revenue Bonds.
B. Subcontract Modification for BP-S00139 (GMP No. 5-S.2) with The Middlesex Corporation for CR0552.1-LSC-RFI 2888.3-Temp Bypass Additional Fittings (CWA
BP-S00139-002). Mr. Corthell presented the memorandum, requesting approval
for Turner-Kiewit Joint Venture (TKJV) to issue a Subcontract Modification on
BP-S00139, South Terminal C, Phase 1 – Landside Civil (GMP No. 5-S.2), at the
Minutes of the Construction Committee Meeting, May 26, 2020
Page 6 of 59
Orlando International Airport, in the total amount of $26,001.00 to The
Middlesex Corporation for CR0552.1-LSC-RFI 2888.3-Temp Bypass Additional
Fittings (CWA BP-S00139-002). Bid Package 31.0.0 "Sitework" was previously
awarded within GMP No. 5-S.2 to The Middlesex Corporation, CC No. 20180504.05A.
TKJV is proposing a subcontract modification to The Middlesex Corporation in
the total lump sum amount of $26,001.00 for CR0552.1-LSC-Temp Bypass Additional
Fittings. RFIs 2888-2888.2 were issued to submit and coordinate the proposed
layout of the APM/ITF Utility Corridor Temporary Bypass with the EOR. The
response to RFI 2888.2 issued in October 2019 confirmed the EOR's acceptance
of the proposed layout, but indicated that input from the City of Orlando and
OUC was still required. In November 2019, in order to maintain the construction
schedule, CR0552 was approved at CCM Ref No. 20191105.02A for the necessary
temporary bypass installation of utilities servicing the ITF and APM in order
to avoid these utilities interfering with the ASC P1X deep foundations. CR0552
included costs per the EOR's approved layout contained in the response to
RFI 2888.2.
After CR0552 was approved, OUC reviewed the proposed bypass layout and
requested additional changes be made. In December 2019, RFI 2888.3 confirmed
the EOR's agreement with the layout revisions and comments presented by OUC.
The scope of work captured in this request consists of the additional revisions
requested by OUC to the temporary utilities bypass layout previously approved
in CR0552. The scope includes installation of an additional temporary 16-inch
DIP (Ductile Iron Pipe) Mechanical Joint Butterfly Valve, additional fittings
and tees, and an OUC thrust block at existing 16-inch gate valve.
The approval of this subcontract modification to The Middlesex Corporation
resolves all requests for costs and time associated with RFI 2888.3, CR0552.1-
LSC-Temp Bypass Additional Fittings and closes (CWA BP-S00139-002). No further
CRs associated with the RFI 2888 series or the Temporary Utility Bypass scope
of work will be submitted.
TKJV has submitted documentation including the subcontractor's proposal to
support their request. An independent cost estimate is included. By approving
this request, the Owner does not waive its right to enforce the contract
requirements for other requests for cost or time.
The effect of this Subcontractor Modification for this project is as follows:
TKJV to issue a subcontract award to The Middlesex
Corporation in the lump sum amount of: $ 26,001.00
Deduct from P1X CMAR Contingency: $ (26,001.00)
Turner-Kiewit Joint Venture is committed to 20% MWBE and 4% LDB participation
for Construction Services. The subcontractor identified and committed to
participate on BP-S00139 (GMP No. 5-S.2) for this subcontract modification is
The Middlesex Corporation (Non-MWBE/LDB/VBE). There is 95.7% MWBE
participation associated with this modification.
Ms. Sharman asked if this request takes into account any potential reductions
to the GMP. Mr. Corthell answered yes.
Minutes of the Construction Committee Meeting, May 26, 2020
Page 7 of 59
Agenda Item Nos. 3-A, 3-B, 3-C, 3-D, 3-E, 3-F, 3-G, 3-H, 3-I, 3-J, 3-K, 3-L,
3-M, 3-N, 3-O, 3-P, 3-Q, 3-R, 3-S, 3-T, 3-U, 3-V, 3-W, 3-X, 3-Y, 3-Z, 3-AA,
3-BB, 3-CC, 3-DD, 3-EE, 3-FF, 3-GG, 3-HH, 3-II, 3-JJ, 3-KK, 3-LL, 3-MM, 3-NN,
3-OO, 3-PP, 3-QQ, 3-RR, 3-SS, 3-TT, 3-UU, 3-VV, 3-WW, 3-XX, and 3-YY were
considered in one motion.
Upon motion of Mr. Hunt, second by Ms. Schneider, vote carried by roll-call,
with all votes yea, to approve Turner-Kiewit Joint Venture to issue a
Subcontractor Modification to The Middlesex Corporation on BP-S00139, South
Terminal C, Phase 1 – Landside Civil (GMP No. 5-S.2), for the total lump sum
amount of $26,001.00, with funding from General Airport Revenue Bonds.
C. Subcontract Modification for BP-S00143 (GMP No. 6-S.1) with Banker Steel Co., LLC for CR0497-6S1-RFI 0832 Series; Reduction of Sterile Corridor Glass -
Structural Steel (VE). Mr. Corthell presented the memorandum, requesting
approval for Hensel Phelps Construction (HPC) to issue a Subcontract
Modification on BP-S00143, South Terminal C, Phase 1 - Airside Terminal,
Structure and Enclosure (GMP No. 6-S.1), at the Orlando International Airport,
in the total deductive amount of ($65,975.00) to Banker Steel Co., LLC, for
CR0497-6S1-RFI 0832 Series; Reduction of Sterile Corridor Glass - Structural
Steel (VE). Bid Package for BP-S00143 05.01 "Structural Steel and
Miscellaneous Metals" has been previously awarded within GMP No. 6-S.1 to
Banker Steel Co., LLC, CC No. 20180410.008.
HPC is requesting to issue a Subcontractor Modification to Banker Steel Co.,
LLC in the total deductive Lump Sum amount of ($65,975.00) for CR0497-6S1-RFI
0832 Series; Reduction of Sterile Corridor Glass - Structural Steel (VE). The
modified scope of work consists of the credits associated with the Edge-of-
Slab (EOS) supports deleted where the full-height interior storefront glass
was removed, and costs associated with the newly detailed EOS supports for the
areas being replaced with gypsum walls, per RFI 0832 Series responses and
sketches.
Value-Engineering RFI 0832 Series affected the scope of work in GMP Nos.
6-S.1, 6-S.2, 6-S.3 and 6-S.4, with a total VE credit value of $401,276.00 for
Phase 1. The approval of this Subcontractor Modification to Banker Steel Co.,
LLC resolves all requests for cost and time resulting from RFI 0832 Series
scope of work in GMP No. 6-S.1. Costs for Testing and Inspection, if any, will
be submitted in a future CR. Costs for GMP Nos. 6-S.2, 6-S.3 and 6-S.4 were
approved, respectively, via CC No. 20190813.021 (CR0249-6S2 Framing and Drywall
Add), 20190709.02D (CR0249-6S3 Interior Storefront and Glass Wall Systems
Credit), and 20190709.02L (CR0249-6S4 Painting Add). Costs of RFI 0832 Series
for Phase 1X scope will be submitted in a future CR.
HPC has submitted documentation including the subcontractor's proposal to
support their request. An independent cost estimate is included. By approving
this request, the Owner does not waive its right to enforce the contract
requirements for other requests for costs or time.
The effect of this Subcontract Modification for this project is as follows:
HPC to issue a subcontract modification to Banker
Steel Co., LLC in the deductive lump sum amount of: $ 65,975.00
Add to P1 Owner Contingency: $ (65,975.00)
Hensel Phelps Construction is committed to 20% MWBE and 4% LDB participation
for Construction Services. The subcontractor identified and committed to
participate on BP-S00143 (GMP No. 6-S.1) for this subcontract modification is
Minutes of the Construction Committee Meeting, May 26, 2020
Page 8 of 59
Banker Steel Co., LLC (Non-MWBE/LDB/VBE). There is no MWBE, LDB or VBE
participation associated with this modification.
Agenda Item Nos. 3-A, 3-B, 3-C, 3-D, 3-E, 3-F, 3-G, 3-H, 3-I, 3-J, 3-K, 3-L,
3-M, 3-N, 3-O, 3-P, 3-Q, 3-R, 3-S, 3-T, 3-U, 3-V, 3-W, 3-X, 3-Y, 3-Z, 3-AA,
3-BB, 3-CC, 3-DD, 3-EE, 3-FF, 3-GG, 3-HH, 3-II, 3-JJ, 3-KK, 3-LL, 3-MM, 3-NN,
3-OO, 3-PP, 3-QQ, 3-RR, 3-SS, 3-TT, 3-UU, 3-VV, 3-WW, 3-XX, and 3-YY were
considered in one motion.
Upon motion of Mr. Hunt, second by Ms. Schneider, vote carried by roll-call,
with all votes yea, to approve Hensel Phelps Construction to issue a
Subcontract Modification to Banker Steel Co., LLC on BP-S00143, South Terminal
C, Phase 1 - Airside Terminal, Structure and Enclosure (GMP No. 6-S.1), for
the total deductive lump sum amount of ($65,975.00), with funding credited to Passenger Facility Charges and General Airport Revenue Bonds.
D. Subcontract Modifications for BP-S00143 (GMP No. 6-S.1) with T&T Construction of Central Fla., Inc.; Odyssey International Inc. dba Odyssey Global; and, Banker Steel Co., LLC; for CR0504-6S1-RFI 1533.1 Lowered IDF Rooms 01-0114 and
01-0130. Mr. Corthell presented the memorandum, requesting approval for Hensel
Phelps Construction (HPC) to issue Subcontract Modifications on BP-S00143,
South Terminal C, Phase 1 - Airside Terminal, Structure and Enclosure (GMP No.
6-S.1), at the Orlando International Airport, in the total amount of $19,657.00
to T&T Construction of Central Fla., Inc.; Odyssey International Inc. dba
Odyssey Global; and Banker Steel Co., LLC; for CR0504-6S1-RFI 1533.1 Lowered
IDF Rooms 01-0114 and 01-0130. Bid Packages 03.02 "Building Concrete"; 04.01
"Masonry"; and 05.01 "Structural Steel and Misc. Metals" were previously
awarded within GMP No. 6-S.1, respectively, to T&T Construction of Central
Fla., Inc.; Odyssey International Inc. dba Odyssey Global; and, Banker Steel
Co., LLC, CC No. 201800410.008.
HPC is requesting to issue the following Subcontractor Modifications to;
T&T Construction of Central Fla., Inc. in the Lump Sum amount of $5,078.00
for CR0504-6S1-RFI 1533.1 Lowered IDF Rooms 01-0114 and 01-0130. The
modified scope of work consists of the costs for the additional excavation
and fill associated with lowering the Slab-on-Grade (SOG), per RFI 1533.1
response.
Odyssey International Inc. dba Odyssey Global in the Lump Sum amount of
$3,118.00 for CR0504-6S1-RFI 1533.1 Lowered IDF Rooms 01-0114 and 01-
0130. The modified scope of work consists of the costs for the added
Concrete Masonry Unit (CMU) at the bottom of the CMU walls, per RFI 1533.1
response.
Banker Steel Co., LLC in the Lump Sum amount of $11,461.00 for CR0504-
6S1-RFI 1533.1 Lowered IDF Rooms 01-0114 and 01-0130. The modified scope
of work consists of the costs for the added concrete-filled metal pan
stair and railings, per RFI 1533.1 response.
The approval of these Subcontractors Modifications to T&T Construction of
Central Fla., Inc.; Odyssey International Inc. dba Odyssey Global; and Banker
Steel Co., LLC; resolves all requests for costs and time resulting from RFI
1533.1 scope of work. Costs for Testing and Inspection, if any, will be
submitted in a future CR. There are no cost impacts to GMP Nos. 6-S, 6-S.2,
6-S.3, 6-S.4, 6-S.5, and 6-S.6.
Minutes of the Construction Committee Meeting, May 26, 2020
Page 9 of 59
HPC has submitted documentation including the subcontractor's proposal to
support this request. An independent cost estimate is included. By approving
this request, the Owner does not waive its right to enforce the contract
requirements for other requests for cost or time.
The effect of these Subcontract Modifications for this project is as follows:
HPC to issue a subcontract modification to T&T
Construction of Central Fla., Inc. in the lump
sum amount of: $ 5,078.00
HPC to issue a subcontract modification to
Odyssey International Inc. dba Odyssey Global in
the lump sum amount of: $ 3,118.00
HPC to issue a subcontract modification to Banker
Steel Co., LLC in the lump sum amount of: $ 11,461.00
Deduct from P1 CMAR Contingency: $ (19,657.00)
Hensel Phelps Construction is committed to 20% MWBE and 4% LDB participation
for Construction Services. The subcontractors identified and committed to
participate on BP-S00143 (GMP-6S.1) for these subcontract modifications are
as follows: T&T Construction of Central Florida, Inc. (MWBE); Odyssey
International Inc. dba Odyssey Global (Non-MWBE at the time of award of the
"Masonry" bid package); and, Banker Steel Co., LLC (Non-MWBE/LDB/VBE). There
is an overall 43.2% MWBE participation associated with the proposed
modifications.
Agenda Item Nos. 3-A, 3-B, 3-C, 3-D, 3-E, 3-F, 3-G, 3-H, 3-I, 3-J, 3-K, 3-L,
3-M, 3-N, 3-O, 3-P, 3-Q, 3-R, 3-S, 3-T, 3-U, 3-V, 3-W, 3-X, 3-Y, 3-Z, 3-AA,
3-BB, 3-CC, 3-DD, 3-EE, 3-FF, 3-GG, 3-HH, 3-II, 3-JJ, 3-KK, 3-LL, 3-MM, 3-NN,
3-OO, 3-PP, 3-QQ, 3-RR, 3-SS, 3-TT, 3-UU, 3-VV, 3-WW, 3-XX, and 3-YY were
considered in one motion.
Upon motion of Mr. Hunt, second by Ms. Schneider, vote carried by roll-call,
with all votes yea, to approve Hensel Phelps Construction to issue Subcontract
Modifications on BP-S00143, South Terminal C, Phase 1 - Airside Terminal,
Structure and Enclosure (GMP No. 6-S.1), for the total amount of $19,657.00,
which includes the total lump sum amount of $5,078.00 to T&T Construction of Central Fla., Inc.; the total lump sum amount of $3,118.00 to Odyssey
International Inc. dba Odyssey Global; and the total lump sum amount of $11,461.00 to Banker Steel Co., LLC; with funding from Passenger Facility
Charges and General Airport Revenue Bonds.
E. Subcontract Modification for BP-S00143 (GMP No. 6-S.1) with Banker Steel Co., LLC for CR0535-6S1-RFI 1892 Antenna Array Frames. Mr. Corthell presented the
memorandum, requesting approval for Hensel Phelps Construction (HPC) to issue
a Subcontract Modification on BP-S00143, South Terminal C, Phase 1 - Airside
Terminal, Structure and Enclosure (GMP No. 6-S.1), at the Orlando International
Airport, in the total amount of $88,815.00 to Banker Steel Co., LLC, for
CR0535-6S1-RFI 1892 Antenna Array Frames. Bid Package for BP-S00143 05.01
"Structural Steel and Miscellaneous Metals" has been previously awarded within
GMP No. 6-S.1 to Banker Steel Co., LLC, CC No. 20180410.008.
HPC is requesting to issue a Subcontractor Modification to Banker Steel Co.,
LLC in the total Lump Sum amount of $88,815.00 for CR0535-6S1-RFI 1892 Antenna
Array Frames. RFI 1892 response confirmed the framing and bracing details for
the Antenna Arrays on the high roof of the Airside Concourse building. The
modified scope of work consists of the additional Detailing, Material, Labor,
Minutes of the Construction Committee Meeting, May 26, 2020
Page 10 of 59
and Erection costs associated with the added and adjusted frame supports for
the Antenna Arrays, per RFI 1892 response.
The approval of this Subcontractor Modification to Banker Steel Co., LLC
resolves all requests for cost and time resulting from RFI 1892 scope of work.
HPC has submitted documentation including the subcontractor's proposal to
support their request. An independent cost estimate is included. By approving
this request, the Owner does not waive its right to enforce the contract
requirements for other requests for costs or time.
The effect of this Subcontract Modification for this project is as follows:
HPC to issue a subcontract modification to Banker
Steel Co., LLC in the lump sum amount of: $ 88,815.00
Deduct from P1 Owner Contingency $ (88,815.00)
Hensel Phelps Construction is committed to 20% MWBE and 4% LDB participation
for Construction Services. The subcontractor identified and committed to
participate on BP-S00143 (GMP No. 6-S.1) for this subcontract modification is
Banker Steel Co., LLC (Non-MWBE/LDB/VBE). There is no MWBE, LDB, or VBE
participation associated with this modification.
Agenda Item Nos. 3-A, 3-B, 3-C, 3-D, 3-E, 3-F, 3-G, 3-H, 3-I, 3-J, 3-K, 3-L,
3-M, 3-N, 3-O, 3-P, 3-Q, 3-R, 3-S, 3-T, 3-U, 3-V, 3-W, 3-X, 3-Y, 3-Z, 3-AA,
3-BB, 3-CC, 3-DD, 3-EE, 3-FF, 3-GG, 3-HH, 3-II, 3-JJ, 3-KK, 3-LL, 3-MM, 3-NN,
3-OO, 3-PP, 3-QQ, 3-RR, 3-SS, 3-TT, 3-UU, 3-VV, 3-WW, 3-XX, and 3-YY were
considered in one motion.
Upon motion of Mr. Hunt, second by Ms. Schneider, vote carried by roll-call,
with all votes yea, to approve Hensel Phelps Construction to issue a
Subcontract Modification to Banker Steel Co., LLC on BP-S00143, South Terminal
C, Phase 1 - Airside Terminal, Structure and Enclosure (GMP No. 6-S.1), for
the total lump sum amount of $88,815.00, with funding from General Airport
Revenue Bonds.
F. Subcontract Modification for BP-S00144 (GMP No. 6-S.2) with Wal-Mark
Contracting Group, LLC for CR0503.5-6S2-ASC Bulletin 037 Non-Electrical
Trades. Mr. Corthell presented the memorandum, requesting approval for Hensel
Phelps Construction (HPC) to issue a Subcontract Modification on BP-S00144,
South Terminal C, Phase 1 - STC Airside Enclosure and Exterior Finishes (GMP
No. 6-S.2), at the Orlando International Airport, in the total amount of
$56,316.00 to Wal-Mark Contracting Group, LLC for CR0503.5-6S2-ASC Bulletin
037 Non-Electrical Trades. Bid Package for BP-S00144 09.02 "Framing and
Drywall" has been previously awarded within GMP No. 6-S.2 to Wal-Mark
Contracting Group LLC, CC No. 20180605.006.
HPC is requesting to issue this Subcontractor Modification to Wal-Mark
Contracting Group, LLC in the total Lump Sum amount of $56,316.00 for CR0503.5-
6S2-ASC Bulletin 037 Non-Electrical Trades. The modified scope of work
consists of the additional labor, material and equipment costs associated with
changes to the gypsum wall assemblies. HPC will also submit Time Impact
Analysis (TIA 088) requesting additional time associated with this scope of
work ASC Bulletin 037.
The approval of this Subcontractor Modification to Wal-Mark Contracting Group,
LLC resolves all requests for costs associated with the ASC Bulletin 037 Non-
Minutes of the Construction Committee Meeting, May 26, 2020
Page 11 of 59
Electrical Trades scope of work in GMP No. 6-S.2, with the exception of costs
for DSI ASC-003 and ASC Bulletin 036.
Costs associated with DSI ASC-003 and ASC Bulletin 036 are excluded due
to document inconsistencies and further design changes that are being
resolved and costs for these will be submitted in a future CR.
Cost impacts of ASC Bulletin 037 Mechanical Only scope of work in GMP
No. 6-S.1 were approved via CC No. 20200324.02B (CR0503.2-6S.1).
Cost impacts of ASC B037 Mechanical Only scope of work in GMP No. 6-S.6
were approved via CC No. 20200324.200 (CR0503.3-6S.6).
Cost impacts of ASC B037 to GMP No. 6-S.1 for the Non-Mechanical Trades
will be submitted in CR0503.4-6S.1 for a future CCM approval.
Cost impacts of ASC B037 to GMP No. 6-S.4 will be submitted in CR0503.6-
6S.4 for a future CCM approval.
Cost impacts of ASC B037 to GMP No. 6-S.6 for the Non-Mechanical scope
will be submitted in future CRs.
There are no cost impacts of ASC B037 to GMP No. 6-S.2 for the Electrical
scope of work.
Cost impacts of ASC B037 to GMP Nos. 6-S, 6-S.3, and 6-S.5, if any, will
be submitted in future CR.
The OAR will evaluate TIA-088 and any additional time recommended to be
granted will be submitted at a future CCM.
HPC has submitted documentation including the subcontractor's proposal to
support this request. An independent cost estimate is included. By approving
this request, the Owner does not waive its right to enforce the contract
requirements for other requests for cost or time.
The effect of this Subcontract Modification for this project is as follows:
HPC to issue a subcontract modification to Wal-Mark
Contracting Group, LLC in the lump sum amount of: $ 56,316.00
Deduct from P1 Owner Contingency: $ (56,316.00)
Hensel Phelps Construction is committed to 20% MWBE and 4% LDB participation
for Construction Services. The subcontractor identified and committed to
participate on BP-S00144 (GMP No. 6-S.2) for this subcontract modification is
Wal-Mark Contracting Group, LLC (Non-MWBE/LDB/VBE). There is no small business
participation associated with this modification.
Agenda Item Nos. 3-A, 3-B, 3-C, 3-D, 3-E, 3-F, 3-G, 3-H, 3-I, 3-J, 3-K, 3-L,
3-M, 3-N, 3-O, 3-P, 3-Q, 3-R, 3-S, 3-T, 3-U, 3-V, 3-W, 3-X, 3-Y, 3-Z, 3-AA,
3-BB, 3-CC, 3-DD, 3-EE, 3-FF, 3-GG, 3-HH, 3-II, 3-JJ, 3-KK, 3-LL, 3-MM, 3-NN,
3-OO, 3-PP, 3-QQ, 3-RR, 3-SS, 3-TT, 3-UU, 3-VV, 3-WW, 3-XX, and 3-YY were
considered in one motion.
Upon motion of Mr. Hunt, second by Ms. Schneider, vote carried by roll-call,
with all votes yea, to approve Hensel Phelps Construction to issue a
Subcontract Modification to Wal-Mark Contracting Group, LLC on BP-S00144,
Minutes of the Construction Committee Meeting, May 26, 2020
Page 12 of 59
South Terminal C, Phase 1 - STC Airside Enclosure and Exterior Finishes (GMP
No. 6-S.2), for the total lump sum amount of $56,316.00, with funding from
General Airport Revenue Bonds.
G. Subcontract Modification for BP-S00144 (GMP No. 6-S.2) with Wal-Mark
Contracting Group, LLC for CR0570.1-6S2-RFI 2173 Hub Skylight Area Ceiling -
Framing and Drywall. Mr. Corthell presented the memorandum, requesting
approval for Hensel Phelps Construction (HPC) to issue a Subcontract
Modification on BP-S00144, South Terminal C, Phase 1 - Airside Enclosure and
Exterior Finishes (GMP No. 6-S.2), at the Orlando International Airport, in
the total amount of $72,257.00 to Wal-Mark Contracting Group, LLC for CR0570.1-
6S2-RFI 2173 Hub Skylight Area Ceiling - Framing and Drywall. Bid Package for
BP-S00144 09.02 "Framing and Drywall" has been previously awarded within GMP
No. 6-S.2 to Wal-Mark Contracting Group LLC, CC No. 20180605.006.
HPC is requesting to issue this Subcontractor Modification to Wal-Mark
Contracting Group LLC in the total Lump Sum amount of $72,257.00 for CR0570.1-
6S2-RFI 2173 Hub Skylight Area Ceiling - Framing and Drywall. ACU1 Acoustic
Plaster and DF1 Textured Plaster Finish were removed entirely from the project
through the Value Engineering process and replaced with Level-4 drywall finish
and paint only at the serenity room and boarding gates, CC No. 20190709.02E,
20190709.02M and 20190716.02G respectively, CR0276-6S.3 (Interior Plaster
Credit), CR0276-6S.4 (Painting Add), and CR0276-6S.2 (Framing and Drywall
Add). There are areas of ceiling outside the serenity room and boarding gates
that originally called for ACU1 or DF1 finish. RFI 2173 was written to request
information for the replacement ceiling finish in those areas. The modified
scope of work consists of the additional costs associated with upgrading the
skylight drywall finish area ceiling from Level-1 to Level-4 finish, per
RFI 2173 response and sketches.
The approval of this Subcontractor Modification to Wal-Mark Contracting Group,
LLC resolves all requests for costs and time resulting from RFI 2173 for the
Drywall scope of work in GMP No. 6-S.2. Costs for RFI 2173 in GMP No. 6-S.4
for the Painting scope of work will be submitted via CR0570.2-6S4 for a future
CCM approval.
HPC has submitted documentation including the subcontractor's proposal to
support this request. An independent cost estimate is included. By approving
this request, the Owner does not waive its right to enforce the contract
requirements for other requests for cost or time.
The effect of this Subcontract Modification for this project is as follows:
HPC to issue a subcontract modification to Wal-Mark
Contracting Group, LLC in the lump sum amount of: $ 72,257.00
Deduct from P1 Owner Contingency: $ (72,257.00)
Hensel Phelps Construction is committed to 20% MWBE and 4% LDB participation
for Construction Services. The subcontractor identified and committed to
participate on BP-S00144 (GMP No. 6-S.2) for this subcontract modification is
Wal-Mark Contracting Group, LLC (Non-MWBE/LDB/VBE). There is no small business
participation associated with this modification.
Agenda Item Nos. 3-A, 3-B, 3-C, 3-D, 3-E, 3-F, 3-G, 3-H, 3-I, 3-J, 3-K, 3-L,
3-M, 3-N, 3-O, 3-P, 3-Q, 3-R, 3-S, 3-T, 3-U, 3-V, 3-W, 3-X, 3-Y, 3-Z, 3-AA,
3-BB, 3-CC, 3-DD, 3-EE, 3-FF, 3-GG, 3-HH, 3-II, 3-JJ, 3-KK, 3-LL, 3-MM, 3-NN,
3-OO, 3-PP, 3-QQ, 3-RR, 3-SS, 3-TT, 3-UU, 3-VV, 3-WW, 3-XX, and 3-YY were
considered in one motion.
Minutes of the Construction Committee Meeting, May 26, 2020
Page 13 of 59
Upon motion of Mr. Hunt, second by Ms. Schneider, vote carried by roll-call,
with all votes yea, to approve Hensel Phelps Construction to issue a
Subcontract Modification to Wal-Mark Contracting Group, LLC on BP-S00144,
South Terminal C, Phase 1 - Airside Enclosure and Exterior Finishes (GMP
No. 6-S.2), for the total lump sum amount of $72,257.00, with funding from
Passenger Facility Charges and General Airport Revenue Bonds.
H. Subcontractor Modification for BP-S00145 (GMP No. 6-S.3) with David Allen Company, Inc. for CR0556-6S.3-Terrazzo Floor Leveling in the Airside Concourse
Hub and W1 Areas. Mr. Corthell presented the memorandum, requesting approval
for Hensel Phelps Construction (HPC) to issue a Subcontract Modification on
BP-S00145, South Terminal C, Phase 1 - Airside Early Interiors (GMP No. 6-
S.3), at the Orlando International Airport, in the total amount of $114,371.00
to David Allen Company, Inc. for CR0556-6S.3-Terrazzo Floor Leveling in the
Airside Concourse Hub and W1 Areas. Bid Package for BP-S00145 09.05 "Terrazzo"
has been previously awarded within GMP No. 6-S.3 to David Allen Company, Inc.,
CC No. 20180807.010.
HPC is requesting to issue a Subcontractor Modification to David Allen Company,
Inc., in the total Lump Sum amount of $114,371.00 for CR0556-6S.3-Terrazzo
Floor Leveling in the Airside Concourse Hub and W1 Areas. Floor leveling is
required under the terrazzo floor on the Transfer Level at the Hub Area and
in W1 in order to achieve the desired appearance of the terrazzo floor system
in such a large open area. The concrete slab on metal deck does meet the Floor
Flatness (FF) requirements of the concrete specifications and ACI. The terrazzo
is required to meet a specified Floor Levelness (FL). An allowance was included
in GMP No. 6-S.3 to address the variance between the substrate FF and the
finish product FL. The modified scope of work consists of the costs associated
with the substrate leveling of the Slab-on-Metal-Deck (SOMD) in the Transfer
Level Hub and W1 areas prior to installation of the Terrazzo floor system.
The approval of this Subcontractor Modification to David Allen Company, Inc.,
resolves all requests for cost and time resulting from the Terrazzo Floor
System's floor flatness/leveling scopes of work in the Phase 1 ASC Transfer
Level Hub and W1 areas.
HPC has submitted documentation including the subcontractor's proposal to
support this request. An independent cost estimate is included. By approving
this request, the Owner does not waive its right to enforce the contract
requirements for other requests for cost or time.
The effect of this Subcontractor Modification for this project is as follows:
Current GMP Line Item "AL01 Floor Leveling" value: $ 250,000.00
HPC to issue a subcontract modification to David Allen
Company, Inc. in the lump sum amount of: $ 114,371.00
Deduct from GMP Line Item “AL01 Floor Leveling" value: $ (114,371.00)
Remaining GMP Line Item "AL01 Floor Leveling" value: $ 135,629.00
Hensel Phelps Construction is committed to 20% MWBE and 4% LDB participation
for Construction Services. The subcontractor identified and committed to
participate on BP-S00145 (GMP No. 6-S.3) for this subcontract modification is
David Allen Company, Inc. (Non-MWBE/LDB/VBE). There is no small business
participation associated with this modification.
Agenda Item Nos. 3-A, 3-B, 3-C, 3-D, 3-E, 3-F, 3-G, 3-H, 3-I, 3-J, 3-K, 3-L,
3-M, 3-N, 3-O, 3-P, 3-Q, 3-R, 3-S, 3-T, 3-U, 3-V, 3-W, 3-X, 3-Y, 3-Z, 3-AA,
3-BB, 3-CC, 3-DD, 3-EE, 3-FF, 3-GG, 3-HH, 3-II, 3-JJ, 3-KK, 3-LL, 3-MM, 3-NN,
Minutes of the Construction Committee Meeting, May 26, 2020
Page 14 of 59
3-OO, 3-PP, 3-QQ, 3-RR, 3-SS, 3-TT, 3-UU, 3-VV, 3-WW, 3-XX, and 3-YY were
considered in one motion.
Upon motion of Mr. Hunt, second by Ms. Schneider, vote carried by roll-call,
with all votes yea, to approve Hensel Phelps Construction to issue a
Subcontractor Modification to David Allen Company, Inc. on BP-S00145, South
Terminal C, Phase 1 - Airside Early Interiors (GMP No. 6-S.3), for the total
lump sum amount of $114,371.00, with funding from Passenger Facility Charges
and General Airport Revenue Bonds.
I. Subcontractor Modification for BP-S00145 (GMP No. 6-S.3) with MULE Engineering & Construction, Inc. for CR0573.2-6S3-RFI 2283 Added Door 01-4006B - Doors,
Frames and Hardware. Mr. Corthell presented the memorandum, requesting
approval for Hensel Phelps Construction (HPC) to issue a Subcontract
Modification on BP-S00145, South Terminal C, Phase 1 - Airside Early Interiors
(GMP No. 6-S.3), at the Orlando International Airport, in the total amount of
$7,750.00 to MULE Engineering & Construction, Inc. for CR0573.2-6S3-RFI 2283
Added Door 01-4006B - Doors, Frames and Hardware. Bid Package for BP-S00145
08.03 "Doors, Frames and Hardware" has been previously awarded within GMP No.
6-S.3 to MULE Engineering & Construction, Inc., CC No. 20181009.03C.
HPC is requesting to issue a Subcontractor Modification to MULE Engineering &
Construction, Inc. in the total Lump Sum amount of $7,750.00 for CR0573.2-6S3-
RFI 2283 Added Door 01-4006B - Doors, Frames and Hardware. The modified scope
of work consists of the costs associated with the Hollow Metal (HM) Door 01-
4006B, frame, and hardware added in Plants Room 01-1124 on the Ramp Level
Area 25, per RFI 2283 response.
The approval of this Subcontractor Modification to MULE Engineering &
Construction, Inc. resolves all requests for costs and time resulting from
RFI 2283 for the Doors, Frames and Hardware scope of work in GMP No. 6-S.3.
Costs for RFI 2283 in GMP Nos. 6S.1 and 6S.4 will be submitted via CR0573.1-
6S1 and CR0573.3-6S4 for a future CCM approval.
HPC has submitted documentation including the subcontractor's proposal to
support this request. An independent cost estimate is included. By approving
this request, the Owner does not waive its right to enforce the contract
requirements for other requests for cost or time.
The effect of this Subcontractor Modification for this project is as follows:
HPC to issue a subcontract modification to MULE
Engineering & Construction, Inc. in the lump sum
amount of: $ 7,750.00
Deduct from P1 Owner Contingency: $ (7,750.00)
Hensel Phelps Construction is committed to 20% MWBE and 4% LDB participation
for Construction Services. The subcontractor identified and committed to
participate on BP-S00145 (GMP No. 6-S.3) for this subcontract modification is
MULE Engineering & Construction, Inc. (MWBE/LDB). There is 11.7% LDB
participation associated with this modification.
Agenda Item Nos. 3-A, 3-B, 3-C, 3-D, 3-E, 3-F, 3-G, 3-H, 3-I, 3-J, 3-K, 3-L,
3-M, 3-N, 3-O, 3-P, 3-Q, 3-R, 3-S, 3-T, 3-U, 3-V, 3-W, 3-X, 3-Y, 3-Z, 3-AA,
3-BB, 3-CC, 3-DD, 3-EE, 3-FF, 3-GG, 3-HH, 3-II, 3-JJ, 3-KK, 3-LL, 3-MM, 3-NN,
3-OO, 3-PP, 3-QQ, 3-RR, 3-SS, 3-TT, 3-UU, 3-VV, 3-WW, 3-XX, and 3-YY were
considered in one motion.
Minutes of the Construction Committee Meeting, May 26, 2020
Page 15 of 59
Upon motion of Mr. Hunt, second by Ms. Schneider, vote carried by roll-call,
with all votes yea, to approve Hensel Phelps Construction to issue a
Subcontractor Modification to MULE Engineering & Construction, Inc. on BP-
S00145, South Terminal C, Phase 1 - Airside Early Interiors (GMP No. 6-S.3),
for the total lump sum amount of $7,750.00, with funding from General Airport
Revenue Bonds.
J. Subcontractor Modification for BP-S00146 (GMP No. 7-S) with Banker Steel Co., LLC for CR0415-LST-RFIs 1616, 1616.1 and 1868-Interdisciplinary Coordination
of Beams and Embeds. Mr. Corthell presented the memorandum, requesting
approval for Turner-Kiewit Joint Venture (TKJV) to issue a Subcontract
Modification on BP-S00146, South Terminal C, Phase 1 - Landside Terminal,
Structure and Enclosure (GMP No. 7-S), at the Orlando International Airport,
in the total amount of $26,641.00 to Banker Steel Co., LLC for CR0415-LST-RFIs
1616, 1616.1 and 1868-Interdisciplinary Coordination of Beams and Embeds. Bid
Package 5.0.0 "Structural Steel" was previously awarded within GMP No. 7-S to
Banker Steel Co. LLC, CC No. 20180313.010.
TKJV is proposing a subcontract modification to Banker Steel Co., LLC in the
total lump sum amount of $26,641.00 for CR0415-LST-RFIs 1616, 1616.1 and 1868-
Interdisciplinary Coordination of Beams and Embeds. The modified scope of work
consists of a net deduction of 2.60 tons of structural steel, consisting of
the removal of (-4) wide flange members, addition of (2) wide flange members,
revised (7) wide flange members, removed (-1) W14 Column, modification of (24)
fabricated members due to dimensional changes, and net of (-3) erection
members, including all associated material, additional detailing, fabrication
and erection, as captured in the responses to RFIs 1616, 1616.1, and 1868.
The approval of this subcontract modification to Banker Steel Co., LLC resolves
all requests for costs and time for structural steel changes associated with
RFIs 1616, 1616.1, and 1868. There will be no forthcoming CRs.
TKJV has submitted documentation including the subcontractor's proposal with
supporting back-up to substantiate this request. An independent cost estimate
is included. By approving this request, the Owner does not waive its right to
enforce the contract requirements for other requests for costs or time.
The effect of this Subcontractor Modification for this project is as follows:
GMP No. 7-S Line Item 6 current value: $ 1,234,390.00
TKJV to issue a subcontract modification to Banker
Steel Co., LLC in the lump sum amount of: $ 26,641.00
Deduct from GMP No. 7-S Line Item 6: $ (26,641.00)
GMP No. 7-S Line Item 6 remaining balance: $ 1,207,749.00
Turner-Kiewit Joint Venture is committed to 20% MWBE and 4% LDB participation
for Construction Services. The subcontractor identified and committed to
participate on BP-S00146 (GMP No. 7-S) for this subcontract modification is
Banker Steel Co., LLC (Non-MWBE/LDB/VBE). There is no small business
participation associated with this modification.
Agenda Item Nos. 3-A, 3-B, 3-C, 3-D, 3-E, 3-F, 3-G, 3-H, 3-I, 3-J, 3-K, 3-L,
3-M, 3-N, 3-O, 3-P, 3-Q, 3-R, 3-S, 3-T, 3-U, 3-V, 3-W, 3-X, 3-Y, 3-Z, 3-AA,
3-BB, 3-CC, 3-DD, 3-EE, 3-FF, 3-GG, 3-HH, 3-II, 3-JJ, 3-KK, 3-LL, 3-MM, 3-NN,
3-OO, 3-PP, 3-QQ, 3-RR, 3-SS, 3-TT, 3-UU, 3-VV, 3-WW, 3-XX, and 3-YY were
considered in one motion.
Upon motion of Mr. Hunt, second by Ms. Schneider, vote carried by roll-call,
with all votes yea, to approve Turner-Kiewit Joint Venture to issue a
Minutes of the Construction Committee Meeting, May 26, 2020
Page 16 of 59
Subcontractor Modification to Banker Steel Co., LLC on BP-S00146, South
Terminal C, Phase 1 - Landside Terminal, Structure and Enclosure (GMP No.
7-S), for the total lump sum amount of $26,641.00, with funding from General
Airport Revenue Bonds.
K. Subcontractor Modification for BP-S00146 (GMP No. 7-S) with Banker Steel Co., LLC for CR0538-LST-RFIs 2208, 2208.1, and 2208.2 - Skylight CW Mullion
Transition. Mr. Corthell presented the memorandum, requesting approval for
Turner-Kiewit Joint Venture (TKJV) to issue a Subcontract Modification on BP-
S00146, South Terminal C, Phase 1 - Landside Terminal, Structure and Enclosure
(GMP No. 7-S), at the Orlando International Airport, in the total amount of
$71,665.00 to Banker Steel Co., LLC for CR0538-LST-RFIs 2208, 2208.1, and
2208.2 - Skylight CW Mullion Transition. Bid Package 5.0.0 "Structural Steel"
was previously awarded within GMP No. 7-S to Banker Steel Co. LLC, CC No.
20180313.010.
TKJV is proposing a subcontract modification to Banker Steel Co. LLC in the
total lump sum amount of $71,665.00 for CR0538-LST-RFIs 2208, 2208.1 and 2208.2
- Skylight CW Mullion Transition. RFIs 2208, 2208.1 and 2208.2 required the
skylight mullions to align with the curtain wall mullions. For that, the SAG
rod hangers will need to be relocated and enlarged in seven locations, as well
as relocation of curtain wall stiffener plates. The modified scope of work
consists of necessary labor, material and equipment for the relocated SAG rod
hangers and skylight mullions to align with curtain wall mullions, per RFIs
2208, 2208.1 and 2208.2.
The approval of this subcontract modification to Banker Steel Co., LLC resolves
all requests for cost and time associated with RFIs 2208, 2208.1 and 2208.2
scope of work in GMP No. 7-S. There are no cost impacts to GMP Nos. 7-S.1,
7-S.2, 7-S.3 and 7-S.4.
TKJV has submitted documentation including the subcontractor's proposal to
support their request. An independent cost estimate is included. By approving
this request, the Owner does not waive its right to enforce the contract
requirements for other requests for cost or time.
The effect of this Subcontractor Modification for this project is as follows:
TKJV to issue a subcontract modification to Banker
Steel Co., LLC in the lump sum amount of: $ 71,665.00
Deduct from P1 Owner Contingency: $ (52,122.00)
Deduct from P1X Owner Contingency: $ (19,543.00)
Turner-Kiewit Joint Venture is committed to 20% MWBE and 4% LDB participation
for Construction Services. The subcontractor identified and committed to
participate on BP-S00146 (GMP No. 7-S) for this subcontract modification is
Banker Steel Co., LLC (Non-MWBE/LDB/VBE). There is no small business
participation associated with this modification.
Ms. Sharman asked if this request takes into account any potential reductions
to the GMP. Mr. Corthell answered yes.
Agenda Item Nos. 3-A, 3-B, 3-C, 3-D, 3-E, 3-F, 3-G, 3-H, 3-I, 3-J, 3-K, 3-L,
3-M, 3-N, 3-O, 3-P, 3-Q, 3-R, 3-S, 3-T, 3-U, 3-V, 3-W, 3-X, 3-Y, 3-Z, 3-AA,
3-BB, 3-CC, 3-DD, 3-EE, 3-FF, 3-GG, 3-HH, 3-II, 3-JJ, 3-KK, 3-LL, 3-MM, 3-NN,
3-OO, 3-PP, 3-QQ, 3-RR, 3-SS, 3-TT, 3-UU, 3-VV, 3-WW, 3-XX, and 3-YY were
considered in one motion.
Minutes of the Construction Committee Meeting, May 26, 2020
Page 17 of 59
Upon motion of Mr. Hunt, second by Ms. Schneider, vote carried by roll-call,
with all votes yea, to approve Turner-Kiewit Joint Venture to issue a
Subcontractor Modification to Banker Steel Co., LLC on BP-S00146, South
Terminal C, Phase 1 - Landside Terminal, Structure and Enclosure (GMP No.
7-S), for the total lump sum amount of $71,665.00, with funding from General
Airport Revenue Bonds.
L. Subcontractor Modification for BP-S00146 (GMP No. 7-S) with Banker Steel Co., LLC for CR0600.1-LST-RFIs 2231, 2252, 3310, 3310.1 and 3310.2-Additional
Elevator Jamb and Stiffener Plates. [A handout was presented, which included
a revised Coversheet.] Mr. Corthell presented the memorandum, requesting
approval for Turner-Kiewit Joint Venture (TKJV) to issue a Subcontract
Modification on BP-S00146, South Terminal C, Phase 1 - Landside Terminal,
Structure and Enclosure (GMP No. 7-S), at the Orlando International Airport,
in the total amount of $42,330.00 to Banker Steel Co., LLC for CR0600.1-LST-
RFIs 2231, 2252, 3310, 3310.1 and 3310.2-Additional Elevator Jamb and Stiffener
Plates. Bid Package 5.0.0 "Structural Steel" was previously awarded within
GMP No. 7-S to Banker Steel Co., LLC, CC No. 20180313.010.
TKJV is proposing a subcontract modification to Banker Steel Co., LLC in the
total lump sum amount of $42,330.00 for CR0600.1-LST-RFIs 2231, 2252, 3310,
3310.1 and 3310.2-Additional Elevator Jamb and Stiffener Plates. The modified
scope of work consists of necessary labor and material to fabricate
approximately 4.20 tons of structural steel for elevator jamb supports, as
captured in RFIs 2231, 2252 and 3310 series.
The approval of this subcontract modification to Banker Steel Co., LLC resolves
all requests for costs and time associated with RFIs 2231, 2252, 3310, 3310.1
and 3310.2 in GMP No. 7-S. Cost impacts to GMP Nos. 7-S.1 and No. 7-S.2 will
be submitted for CCM review in future CRs. There are no cost impacts to GMP
Nos. 7-S.3 and 7-S.4.
TKJV has submitted documentation including the subcontractor's proposal to
substantiate this request. An independent cost estimate is included. By
approving this request, the Owner does not waive its right to enforce the
contract requirements for other requests for costs or time.
The effect of this Subcontractor Modification for this project is as follows:
Current GMP No. 7-S Line Item 6 value: $ 1,207,749.00
TKJV to issue a subcontract modification to Banker
Steel Co., LLC in the lump sum amount of: $ 42,330.00
Deduct from GMP No. 7-S Line Item 6: $ (42,330.00)
GMP No. 7-S Line Item 6 remaining balance: $ 1,165,419.00
Turner-Kiewit Joint Venture is committed to 20% MWBE and 4% LDB participation
for Construction Services. The subcontractor identified and committed to
participate on BP-S00146 (GMP No. 7-S) for this subcontract modification is
Banker Steel Co., LLC (Non-MWBE/LDB/VBE). There is no small business
participation associated with this modification.
Agenda Item Nos. 3-A, 3-B, 3-C, 3-D, 3-E, 3-F, 3-G, 3-H, 3-I, 3-J, 3-K, 3-L,
3-M, 3-N, 3-O, 3-P, 3-Q, 3-R, 3-S, 3-T, 3-U, 3-V, 3-W, 3-X, 3-Y, 3-Z, 3-AA,
3-BB, 3-CC, 3-DD, 3-EE, 3-FF, 3-GG, 3-HH, 3-II, 3-JJ, 3-KK, 3-LL, 3-MM, 3-NN,
3-OO, 3-PP, 3-QQ, 3-RR, 3-SS, 3-TT, 3-UU, 3-VV, 3-WW, 3-XX, and 3-YY were
considered in one motion.
Upon motion of Mr. Hunt, second by Ms. Schneider, vote carried by roll-call,
with all votes yea, to approve Turner-Kiewit Joint Venture to issue a
Minutes of the Construction Committee Meeting, May 26, 2020
Page 18 of 59
Subcontractor Modification to Banker Steel Co., LLC on BP-S00146, South
Terminal C, Phase 1 - Landside Terminal, Structure and Enclosure (GMP No.
7-S), for the total lump sum amount of $42,330.00, with funding from Passenger
Facility Charges and General Airport Revenue Bonds.
M. Subcontractor Modification for BP-S00146 (GMP No. 7-S) with Banker Steel Co., LLC for CR1015-LST-RFI 3789 Structural Steel Framing for Vertical Duct
Penetrations (CWA No. BP-S00146-003). Mr. Corthell presented the memorandum,
requesting approval for Turner-Kiewit Joint Venture (TKJV) to issue a
Subcontract Modification on BP-S00146, South Terminal C, Phase 1 - Landside
Terminal, Structure and Enclosure (GMP No. 7-S), at the Orlando International
Airport, in the total amount of $24,654.00 to Banker Steel Co., LLC for CR1015-
LST-RFI 3789 Structural Steel Framing for Vertical Duct Penetrations (CWA No.
BP-S00146-003). Bid Package 5.0.0 "Structural Steel" was previously awarded
within GMP No. 7-S to Banker Steel Co., LLC, CC No. 20180313.010.
TKJV is proposing a subcontract modification to Banker Steel Co., LLC in the
total lump sum amount of $24,654.00 for CR1015-LST-RFI 3789 Structural Steel
Framing for Vertical Duct Penetrations. The modified scope of work consists
of approximately 0.54 tons of additional structural steel, labor and
engineering for the installation of structural framing to support duct
penetrations at the new floor slab, per RFI 3789.
The approval of this subcontract modification to Banker Steel Co., LLC resolves
all requests for costs and time for structural steel changes associated with
RFI 3789 in GMP No. 7-S and closes CWA No. BP-S00146-003. Cost impacts to GMP
No. 7-S for the Concrete scope were approved at CC Ref. 20200407-03Q. There
will be no forthcoming CRs.
TKJV has submitted documentation including the subcontractor's proposal to
substantiate this request. An independent cost estimate is included. By
approving this request, the Owner does not waive its right to enforce the
contract requirements for other requests for costs or time.
The effect of this Subcontractor Modification for this project is as follows:
TKJV to issue a subcontract modification to Banker
Steel Co., LLC in the lump sum amount of: $ 24,654.00
Deduct from P1 Owner Contingency: $ (24,654.00)
Turner-Kiewit Joint Venture is committed to 20% MWBE and 4% LDB participation
for Construction Services. The subcontractor identified and committed to
participate on BP-S00146 (GMP No. 7-S) for this subcontract modification is
Banker Steel Co., LLC (Non-MWBE/LDB/VBE). There is no small business
participation associated with this modification.
Agenda Item Nos. 3-A, 3-B, 3-C, 3-D, 3-E, 3-F, 3-G, 3-H, 3-I, 3-J, 3-K, 3-L,
3-M, 3-N, 3-O, 3-P, 3-Q, 3-R, 3-S, 3-T, 3-U, 3-V, 3-W, 3-X, 3-Y, 3-Z, 3-AA,
3-BB, 3-CC, 3-DD, 3-EE, 3-FF, 3-GG, 3-HH, 3-II, 3-JJ, 3-KK, 3-LL, 3-MM, 3-NN,
3-OO, 3-PP, 3-QQ, 3-RR, 3-SS, 3-TT, 3-UU, 3-VV, 3-WW, 3-XX, and 3-YY were
considered in one motion.
Upon motion of Mr. Hunt, second by Ms. Schneider, vote carried by roll-call,
with all votes yea, to approve Turner-Kiewit Joint Venture to issue a
Subcontractor Modification to Banker Steel Co., LLC on BP-S00146, South
Terminal C, Phase 1 - Landside Terminal, Structure and Enclosure (GMP No.
7-S), for the total lump sum amount of $24,654.00, with funding from Passenger
Facility Charges and General Airport Revenue Bonds.
Minutes of the Construction Committee Meeting, May 26, 2020
Page 19 of 59
N. Subcontractor Modification for BP-S00146 (GMP No. 7-S) with Banker Steel Co., LLC for CR0903-LST-RFIs 3872, 3877 and 3888 Roof Supports for Plumbing Pipes.
Mr. Corthell presented the memorandum, requesting approval for Turner-Kiewit
Joint Venture (TKJV) to issue a Subcontract Modification on BP-S00146, South
Terminal C, Phase 1 - Landside Terminal, Structure and Enclosure (GMP No. 7-
S), at the Orlando International Airport, in the total amount of $112,794.00
to Banker Steel Co., LLC for CR0903-LST-RFIs 3872, 3877 and 3888 Roof Supports
for Plumbing Pipes. Bid Package 5.0.0 "Structural Steel" was previously
awarded within GMP No. 7-S to Banker Steel Co., LLC, CC No. 20180313.010.
TKJV is proposing a subcontract modification to Banker Steel Co., LLC in the
total lump sum amount of $112,794.00 for CR0903-LST-RFIs 3872, 3877 and 3888
Roof Supports for Plumbing Pipes. The modified scope of work consists of all
costs associated with the net addition of approximately 1 ton of structural
steel to reinforce the roof joists in Areas 3, 4, 7, 8, 11 and 12.
The approval of this subcontract modification to Banker Steel Co., LLC resolves
all requests for costs and time associated with RFIs 3872, 3877 and 3888 scopes
of work in GMP No. 7-S. There are no cost impacts to GMP Nos. 7-S.1, 7-S.2,
7-S.3 and 7-S.4.
TKJV has submitted documentation including the subcontractor's proposal to
substantiate this request. An independent cost estimate is included. By
approving this request, the Owner does not waive its right to enforce the
contract requirements for other requests for costs or time.
The effect of this Subcontractor Modification for this project is as follows:
TKJV to issue a subcontract modification to Banker
Steel Co., LLC in the lump sum amount of: $ 112,794.00
Deduct from P1 Owner Contingency: $ (112,794.00)
Turner-Kiewit Joint Venture is committed to 20% MWBE and 4% LDB participation
for Construction Services. The subcontractor identified and committed to
participate on BP-S00146 (GMP No. 7-S) for this subcontract modification is
Banker Steel Co., LLC (Non-MWBE/LDB/VBE). There is no small business
participation associated with this modification.
Agenda Item Nos. 3-A, 3-B, 3-C, 3-D, 3-E, 3-F, 3-G, 3-H, 3-I, 3-J, 3-K, 3-L,
3-M, 3-N, 3-O, 3-P, 3-Q, 3-R, 3-S, 3-T, 3-U, 3-V, 3-W, 3-X, 3-Y, 3-Z, 3-AA,
3-BB, 3-CC, 3-DD, 3-EE, 3-FF, 3-GG, 3-HH, 3-II, 3-JJ, 3-KK, 3-LL, 3-MM, 3-NN,
3-OO, 3-PP, 3-QQ, 3-RR, 3-SS, 3-TT, 3-UU, 3-VV, 3-WW, 3-XX, and 3-YY were
considered in one motion.
Upon motion of Mr. Hunt, second by Ms. Schneider, vote carried by roll-call,
with all votes yea, to approve Turner-Kiewit Joint Venture to issue a
Subcontractor Modification to Banker Steel Co., LLC on BP-S00146, South
Terminal C, Phase 1 - Landside Terminal, Structure and Enclosure (GMP No.
7-S), for the total lump sum amount of $112,794.00, with funding from Passenger
Facility Charges and General Airport Revenue Bonds.
O. Subcontract Modification for BP-S00147 (GMP No. 7-S.1) with MSE2, Inc. dba Mader Southeast for CR0726-LST-RFIs 3300 and 3300.1 Lath and Accessories Types
for Cement Plastering on Framing Walls. Mr. Corthell presented the memorandum,
requesting approval for Turner-Kiewit Joint Venture (TKJV) to issue a
Subcontract Modification on BP-S00147, South Terminal C, Phase 1 - Landside
Terminal Remaining Structure and Systems (GMP No. 7-S.1), at the Orlando
International Airport, in the total deductive amount of ($12,545.00) to MSE2,
Inc. dba Mader Southeast for CR0726-LST-RFIs 3300 and 3300.1 Lath and
Minutes of the Construction Committee Meeting, May 26, 2020
Page 20 of 59
Accessories Types for Cement Plastering on Framing Walls. Bid Package 9.1.0
"Drywall and Framing" was previously awarded within GMP No. 7-S.1 to MSE2,
Inc., CC No. 20181002.009.
TKJV is proposing a subcontract modification to MSE2, Inc. dba Mader Southeast
in the total deductive lump sum amount of ($12,545.00) for CR0726-LST-RFI 3300
Lath and Accessories Types for Cement Plastering on Framing Walls. RFI 3300
confirmed changes in stucco materials based on a stucco coordination meeting
held between the OAR, CM@R and design team. The modified scope of work consists
of changes in stucco materials and accessories from 2.5 lb/sq. yd. self-furred
diamond mesh and zinc to Megalath Welded Wire Mesh and vinyl stucco trim, per
RFIs 3300 and 3300.1
The approval of this subcontract modification to MSE2, Inc. dba Mader Southeast
resolves all requests for cost and time associated with RFIs 3300 and 3300.1
in GMP No. 7-S.1. There are no cost impacts to GMP Nos. 7-S, 7-S.2, 7-S.3 and
7-S.4.
TKJV has submitted documentation including the subcontractor's proposal to
support their request. An independent cost estimate is included. By approving
this request, the Owner does not waive its right to enforce the contract
requirements for other requests for cost or time.
The effect of this Subcontract Modification for this project is as follows:
TKJV to issue a subcontract modification to MSE2,
Inc. dba Mader Southeast in the deductive amount of: $ (12,545.00)
Add to P1 Owner Contingency: $ 12,545.00
Turner-Kiewit Joint Venture is committed to 20% MWBE and 4% LDB participation
for Construction Services. The subcontractor identified and committed to
participate on BP-S00147 (GMP No. 7-S.1) for this subcontract modification is
MSE2, Inc. dba Mader Southeast (Non-MWBE/LDB/VBE). There is a 95.7% reduction
in MWBE participation associated with this modification.
Agenda Item Nos. 3-A, 3-B, 3-C, 3-D, 3-E, 3-F, 3-G, 3-H, 3-I, 3-J, 3-K, 3-L,
3-M, 3-N, 3-O, 3-P, 3-Q, 3-R, 3-S, 3-T, 3-U, 3-V, 3-W, 3-X, 3-Y, 3-Z, 3-AA,
3-BB, 3-CC, 3-DD, 3-EE, 3-FF, 3-GG, 3-HH, 3-II, 3-JJ, 3-KK, 3-LL, 3-MM, 3-NN,
3-OO, 3-PP, 3-QQ, 3-RR, 3-SS, 3-TT, 3-UU, 3-VV, 3-WW, 3-XX, and 3-YY were
considered in one motion.
Upon motion of Mr. Hunt, second by Ms. Schneider, vote carried by roll-call,
with all votes yea, to approve Turner-Kiewit Joint Venture to issue a
Subcontract Modification to MSE2, Inc. dba Mader Southeast on BP-S00147, South
Terminal C, Phase 1 - Landside Terminal Remaining Structure and Systems (GMP
No. 7-S.1), for the deductive lump sum amount of ($12,545.00), with funding
credited to Passenger Facility Charges and General Airport Revenue Bonds.
P. Subcontract Modifications for BP-S00147 (GMP No. 7-S.1) with MSE2, Inc. dba Mader Southeast; and, and Taylor, Cotton & Ridley, Inc.; for CR0961-LST-RFI
3071 Electrical Room Wall Type Change. Mr. Corthell presented the memorandum,
requesting approval for Turner-Kiewit Joint Venture (TKJV) to issue Subcontract
Modifications on BP-S00147, South Terminal C, Phase 1 - Landside Terminal
Remaining Structure and Systems (GMP No. 7-S.1), at the Orlando International
Airport, in the total amount of $1,920.00 to MSE2, Inc. dba Mader Southeast; and Taylor, Cotton & Ridley, Inc.; for CR0961-LST-RFI 3071 Electrical Room
Wall Type Change.
Minutes of the Construction Committee Meeting, May 26, 2020
Page 21 of 59
Bid Package 9.1.0 "Drywall and Framing" was previously awarded within GMP
No. 7-S.1 to MSE2, Inc., CC No. 20181002.009.
Bid Package 8.0.0 "Doors, Frames and Hardware" was previously awarded within
GMP No. 7-S.1 to Taylor, Cotton & Ridley, Inc., CC No. 20181002.009.
TKJV is proposing a subcontract modification to MSE2, Inc. dba Mader
Southeast in the lump sum amount of $1,553.00 for CR0961-LST-RFI 3071
Electrical Room Wall Type Change. The modified scope of work consists of
necessary labor, material and equipment for the revised wall type from G2-
6-inch studs, 1-hour rated to G4-6-inch studs 2-hours rated, per RFI3071.
TKJV is proposing a subcontract modification to Taylor, Cotton 8i Ridley,
Inc. in the lump sum amount of $367.00 for CR0961-LST-RFI 3071 Electrical
Room Wall Type Change. The modified scope of work consists of material
costs for the revised door frame to accommodate 6-inch wall at room 02-
0021, per RFI 3071
The approval of these subcontract modifications to MSE2, Inc. dba Mader
Southeast; and Taylor, Cotton & Ridley, Inc.; resolves all requests for cost
and time associated with RFI 3071 in GMP No. 7-S.1. There are no cost impacts
to GMP Nos. 7-S, 7-S.2, 7-S.3 and 7-S.4.
TKJV has submitted documentation including the subcontractor's proposal to
support this request. An independent cost estimate is included. By approving
this request, the Owner does not waive its right to enforce the contract
requirements for other requests for cost or time.
The effect of these Subcontract Modifications for this project is as follows:
TKJV to issue a subcontract modification to MSE2,
Inc. dba Mader Southeast in the amount of: $ 1,553.00
TKJV to issue a subcontract modification to Taylor,
Cotton & Ridley, Inc. in the amount of: $ 367.00
Deduct from P1 Owner Contingency: $ (1,920,00)
Turner-Kiewit Joint Venture is committed to 20% MWBE and 4% LDB participation
for Construction Services. The subcontractors identified and committed to
participate on BP-S00147 (GMP No. 7-S.1) for these subcontract modifications
are MSE2, Inc. dba Mader Southeast (Non-MWBE/LDB/VBE); and Taylor, Cotton &
Ridley, Inc. (Non-MWBE/LDB/VBE). There is an overall 5% MWBE participation
associated with these modifications.
Agenda Item Nos. 3-A, 3-B, 3-C, 3-D, 3-E, 3-F, 3-G, 3-H, 3-I, 3-J, 3-K, 3-L,
3-M, 3-N, 3-O, 3-P, 3-Q, 3-R, 3-S, 3-T, 3-U, 3-V, 3-W, 3-X, 3-Y, 3-Z, 3-AA,
3-BB, 3-CC, 3-DD, 3-EE, 3-FF, 3-GG, 3-HH, 3-II, 3-JJ, 3-KK, 3-LL, 3-MM, 3-NN,
3-OO, 3-PP, 3-QQ, 3-RR, 3-SS, 3-TT, 3-UU, 3-VV, 3-WW, 3-XX, and 3-YY were
considered in one motion.
Upon motion of Mr. Hunt, second by Ms. Schneider, vote carried by roll-call,
with all votes yea, to approve Turner-Kiewit Joint Venture to issue Subcontract
Modifications on BP-S00147, South Terminal C, Phase 1 - Landside Terminal
Remaining Structure and Systems (GMP No. 7-S.1), for the total amount of
$1,920,00, which includes the lump sum amount of $1,553.00 to MSE2, Inc. dba
Mader Southeast; and the lump sum amount of $367.00 to Taylor, Cotton & Ridley,
Inc.; with funding from Passenger Facility Charges and General Airport Revenue
Bonds.
Minutes of the Construction Committee Meeting, May 26, 2020
Page 22 of 59
Q. Subcontract Modification for BP-S00147 (GMP No. 7-S.1) with MSE2, Inc. dba Mader Southeast for CR0559.1-LST-RFIs 1357.5 and 2610 Drywall to Exterior
Facade. Mr. Corthell presented the memorandum, requesting approval for Turner-
Kiewit Joint Venture (TKJV) to issue a Subcontract Modification on BP-S00147,
South Terminal C, Phase 1 - Landside Terminal Remaining Structure and Systems
(GMP No. 7-S.1), at the Orlando International Airport, in the total amount of
$454,511.00 to MSE2, Inc. dba Mader Southeast for CR0559.1-LST-RFIs 1357.5 and
2610 Drywall to Exterior Facade. Bid Package 9.1.0 "Drywall and Framing" was
previously awarded within GMP No. 7-S.1 to MSE2, Inc. dba Mader Southeast, CC
No. 20181002.009.
TKJV is proposing a subcontract modification to MSE2, Inc. dba Mader Southeast
in the total lump sum amount of $454,511.00 for CR0559.1-LST-RFIs 1357.5 and
2610 Drywall to Exterior Facade. The modified scope of work includes necessary
labor, material, equipment and detailing for the wall type change from EWS-
02bb to EWS-01d and added fire-rated sheathing to the exterior walls on the
North and South elevations where the stairs enter the building, per RFIs 1357.5
and 2610.
The approval of this subcontract modification to MSE2, Inc. dba Mader Southeast
resolves all requests for cost and time associated with RFIs 1357.5 and 2610
scope of work in GMP No. 7-S.1. Cost impacts to GMP No. 7-S were approved at
CC Ref. 20191203-01D. There are no cost impacts to GMP Nos. 7-S.2, 7-S.3 and
7-S.4.
TKJV has submitted documentation including the subcontractor's proposal to
support this request. An independent cost estimate is included. By approving
this request, the Owner does not waive its right to enforce the contract
requirements for other requests for cost or time.
The effect of this Subcontract Modification for this project is as follows:
TKJV to issue a subcontract modification to MSE2,
Inc. dba Mader Southeast in the amount of: $ 454,511.00
Deduct from P1 Owner Contingency: $ (392,587.00)
Deduct from P1X Owner Contingency: $ (61,924.00)
Turner-Kiewit Joint Venture is committed to 20% MWBE and 4% LDB participation
for Construction Services. The subcontractor identified and committed to
participate on BP-S00147 (GMP No. 7-S.1) for this subcontract modification is
MSE2, Inc. dba Mader Southeast (Non-MWBE/LDB/VBE). There is 16.2% MWBE
participation associated with this modification.
Ms. Sharman stated that this BBC includes both Phase 1 and Phase 1 Expansion
funding.
Ms. Sharman asked if this request takes into account any potential reductions
to the GMP. Mr. Corthell answered yes.
Agenda Item Nos. 3-A, 3-B, 3-C, 3-D, 3-E, 3-F, 3-G, 3-H, 3-I, 3-J, 3-K, 3-L,
3-M, 3-N, 3-O, 3-P, 3-Q, 3-R, 3-S, 3-T, 3-U, 3-V, 3-W, 3-X, 3-Y, 3-Z, 3-AA,
3-BB, 3-CC, 3-DD, 3-EE, 3-FF, 3-GG, 3-HH, 3-II, 3-JJ, 3-KK, 3-LL, 3-MM, 3-NN,
3-OO, 3-PP, 3-QQ, 3-RR, 3-SS, 3-TT, 3-UU, 3-VV, 3-WW, 3-XX, and 3-YY were
considered in one motion.
Upon motion of Mr. Hunt, second by Ms. Schneider, vote carried by roll-call,
with all votes yea, to approve Turner-Kiewit Joint Venture to issue a
Subcontract Modification to MSE2, Inc. dba Mader Southeast on BP-S00147, South
Terminal C, Phase 1 - Landside Terminal Remaining Structure and Systems (GMP
Minutes of the Construction Committee Meeting, May 26, 2020
Page 23 of 59
No. 7-S.1), for the total lump sum amount of $454,511.00, with funding from
Passenger Facility Charges and General Airport Revenue Bonds.
R. Subcontract Modification for BP-S00147 (GMP No. 7-S.1) with M.C. Dean, Inc. for CR0595.1-LST-Bulletin 32 Low Voltage Scope. Mr. Corthell presented the
memorandum, requesting approval for Turner-Kiewit Joint Venture (TKJV) to
issue a Subcontract Modification on BP-S00147, South Terminal C, Phase 1 -
Landside Terminal Remaining Structure and Systems (GMP No. 7-S.1), at the
Orlando International Airport, in the total deductive amount of ($43,905.00)
to M.C. Dean, Inc. for CR0595.1-LST-Bulletin 32 Low Voltage Scope. Bid Package
28.0.0 "Low Voltage" was previously awarded within GMP No. 7-S.1 to MC Dean,
Inc., CC No. 20181002.009.
TKJV is proposing a subcontract modification to M.C. Dean, Inc. in the total
deductive lump sum amount of ($43,905.00) for CR0595.1-LST-Bulletin 32 Low
Voltage Scope. The modified scope of work consists of revisions to the Signage
Design resulting in credits for the alterations to conduit, cabling, low
voltage components and flat panel displays, as captured in LST Bulletin 32.
The approval of this subcontract modification to M.C. Dean, Inc. resolves all
requests for cost and time associated with LST Bulletin 32 for the Low Voltage
scope in GMP No. 7-S.1. Cost impacts to GMP No. 7-S.1 for the Drywall scope
were approved at CC Ref. 20200218.03L. Cost impacts to GMP No. 7-S.2 for the
Signage scope will be submitted in a future CR. There are no cost impacts to
GMP Nos. 7-S, 7-S.3 and 7-S.4.
TKJV has submitted documentation including the subcontractor's proposal to
support their request. An independent cost estimate is included. By approving
this request, the Owner does not waive its right to enforce the contract
requirements for other requests for cost or time.
The effect of this Subcontract Modification for this project is as follows:
TKJV to issue a subcontract modification to M.C.
Dean, Inc. in the deductive amount of: $ (43,905.00)
Add to P1 Owner Contingency: $ 31,932.00
Add to P1X Owner Contingency: $ 11,973.00
Turner-Kiewit Joint Venture is committed to 20% MWBE and 4% LDB participation
for Construction Services. The subcontractor identified and committed to
participate on BP-S00147 (GMP No. 7-S.1) for this subcontract modification is
M.C. Dean, Inc. (Non-MWBE/LDB/VBE). There is a 3.4% reduction in MWBE
participation associated with this modification.
Ms. Sharman asked if this request takes into account any potential reductions
to the GMP. Mr. Corthell answered yes.
Agenda Item Nos. 3-A, 3-B, 3-C, 3-D, 3-E, 3-F, 3-G, 3-H, 3-I, 3-J, 3-K, 3-L,
3-M, 3-N, 3-O, 3-P, 3-Q, 3-R, 3-S, 3-T, 3-U, 3-V, 3-W, 3-X, 3-Y, 3-Z, 3-AA,
3-BB, 3-CC, 3-DD, 3-EE, 3-FF, 3-GG, 3-HH, 3-II, 3-JJ, 3-KK, 3-LL, 3-MM, 3-NN,
3-OO, 3-PP, 3-QQ, 3-RR, 3-SS, 3-TT, 3-UU, 3-VV, 3-WW, 3-XX, and 3-YY were
considered in one motion.
Upon motion of Mr. Hunt, second by Ms. Schneider, vote carried by roll-call,
with all votes yea, to approve Turner-Kiewit Joint Venture to issue a
Subcontract Modification to M.C. Dean, Inc. on BP-S00147, South Terminal C,
Phase 1 - Landside Terminal Remaining Structure and Systems (GMP No. 7-S.1),
for the total deductive lump sum amount of ($43,905.00), with funding credited
to Passenger Facility Charges and General Airport Revenue Bonds.
Minutes of the Construction Committee Meeting, May 26, 2020
Page 24 of 59
S. Subcontract Modification for BP-S00147 (GMP No. 7-S.1) with Hommes Masonry Inc., dba Toltec Construction for CR0599.1-LST-RFI 1980 Added CMU around
Area 9, Level 1. Mr. Corthell presented the memorandum, requesting approval
for Turner-Kiewit Joint Venture (TKJV) to issue a Subcontract Modification on
BP-S00147, South Terminal C, Phase 1 - Landside Terminal Remaining Structure
and Systems (GMP No. 7-S.1), at the Orlando International Airport, in the
total amount of $10,353.00 to Hommes Masonry Inc., dba Toltec Construction for
CR0599.1-LST-RFI 1980 Added CMU around Area 9, Level 1. Bid Package 4.0.0 for
Masonry was previously awarded within GMP No. 7-S.1 to Hommes Masonry Inc. dba
Toltec Construction, CC No. 20181002.09
TKJV is proposing a subcontract modification to Hommes Masonry Inc. dba Toltec
Construction in the total lump sum amount of $10,353.00 for CR0599.1-LST-RFI
1980 Added CMU around Area 9, Level 1. The modified scope of work consists of
added Concrete Masonry Unit (CMU) walls to replace framing and drywall around
columns in Area 9, Level 1, per RFI 1980.
Approval of this subcontract modification to Hommes Masonry Inc. dba Toltec
Construction resolves all requests for cost and time associated with RFI 1980
scope of work in GMP No. 7-S.1. Cost impacts to GMP No. 7-S.1 for the Framing
and Drywall scope were approved at CC Ref. 20200218.03L. There are no cost
impacts to GMP Nos. 7-S, 7-S.2, 7-S.3 and 7-S.4.
TKJV has submitted documentation including the subcontractor's proposal to
support their request. An independent cost estimate is included. By approving
this request, the Owner does not waive its right to enforce the contract
requirements for other requests for cost or time.
The effect of this Subcontract Modification for this project is as follows:
TKJV to issue a subcontract modification to Hommes
Masonry Inc., dba Toltec Construction in the amount of: $ 10,353.00
Deduct from CMAR Contingency P1: $ (10,353.00)
Turner-Kiewit Joint Venture is committed to 20% MWBE and 4% LDB participation
for Construction Services. The subcontractor identified and committed to
participate on BP-S00147 (GMP No. 7-S.1) for this subcontract modification is
Hommes Masonry Inc. dba Toltec Construction (MWBE). There is 100% MWBE
participation associated with this modification.
Agenda Item Nos. 3-A, 3-B, 3-C, 3-D, 3-E, 3-F, 3-G, 3-H, 3-I, 3-J, 3-K, 3-L,
3-M, 3-N, 3-O, 3-P, 3-Q, 3-R, 3-S, 3-T, 3-U, 3-V, 3-W, 3-X, 3-Y, 3-Z, 3-AA,
3-BB, 3-CC, 3-DD, 3-EE, 3-FF, 3-GG, 3-HH, 3-II, 3-JJ, 3-KK, 3-LL, 3-MM, 3-NN,
3-OO, 3-PP, 3-QQ, 3-RR, 3-SS, 3-TT, 3-UU, 3-VV, 3-WW, 3-XX, and 3-YY were
considered in one motion.
Upon motion of Mr. Hunt, second by Ms. Schneider, vote carried by roll-call,
with all votes yea, to approve Turner-Kiewit Joint Venture to issue a
Subcontract Modification to Hommes Masonry Inc., dba Toltec Construction on
BP-S00147, South Terminal C, Phase 1 - Landside Terminal Remaining Structure
and Systems (GMP No. 7-S.1), for the total lump sum amount of $10,353.00, with
funding from Passenger Facility Charges and General Airport Revenue Bonds.
T. Subcontract Modification for BP-S00147 (GMP No. 7-S.1) with Alpha Insulation & Waterproofing, Inc. for CR0682.1-LST-RFIs 2832 and 2832.1 Sealant for Roof-
to-Wall Transition. Mr. Corthell presented the memorandum, requesting approval
for Turner-Kiewit Joint Venture (TKJV) to issue a Subcontract Modification on
BP-S00147, South Terminal C, Phase 1 - Landside Terminal Remaining Structure
Minutes of the Construction Committee Meeting, May 26, 2020
Page 25 of 59
and Systems (GMP No. 7-S.1), at the Orlando International Airport, in the
total amount of $43,416.00 to Alpha Insulation & Waterproofing, Inc. for
CR0682.1-LST-RFIs 2832 and 2832.1 Sealant for Roof-to-Wall Transition. Bid
Package 7.3.0 "Applied Fireproofing" was previously awarded within GMP No. 7-
S.1 to Alpha Insulation & Waterproofing, Inc., CC No. 20181002.009.
TKJV is proposing a subcontract modification to Alpha Insulation &
Waterproofing, Inc. in the total lump sum amount of $43,416.00 for CR0682.1-
LST-RFIs 2832 and 2832.1 Sealant for Roof-to-Wall Transition. RFIs 2832 and
2832.1 confirmed additional areas that require an expansion joint to
accommodate for structural movement in the LST. Those locations were finalized
and included in the RFI 2832.1 and Detail A2/A5.11.47 attached to the RFI
calls for reframing of walls. The modified scope of work consists of the
necessary labor, material and equipment for the addition of a double bead of
exterior silicone sealant at exterior CIP to Framed Walls and 1-inch backer
rod, per the responses to RFIs 2832 and 2832.1.
The approval of this subcontract modification to Alpha Insulation &
Waterproofing, Inc. resolves all requests for cost and time associated with
RFIs 2832 and 2832.1 for the Insulation scope in GMP No. 7-S.1. Cost impacts
to GMP No. 7-S.1 for the Roofing and Drywall and Framing scopes were approved
at CC No. 20200428.02H. There are no cost impacts to GMP Nos. 7-S, 7-S.2,
7-S.3 and 7-S.4.
TKJV has submitted documentation including the subcontractor's proposal to
support their request. An independent cost estimate is included. By approving
this request, the Owner does not waive its right to enforce the contract
requirements for other requests for cost or time.
The effect of this Subcontract Modification for this project is as follows:
TKJV to issue a subcontract modification to Alpha
Insulation & Waterproofing, Inc. in the amount of: $ 43,416.00
Deduct from P1 Owner Contingency: $ (43,416.00)
Turner-Kiewit Joint Venture is committed to 20% MWBE and 4% LDB participation
for Construction Services. The subcontractor identified and committed to
participate on BP-S00147 (GMP No. 7-S.1) for this subcontract modification is
Alpha Insulation & Waterproofing, Inc. (Non-MWBE/LDB/VBE). There is 55.3% MWBE
participation associated with this modification.
Agenda Item Nos. 3-A, 3-B, 3-C, 3-D, 3-E, 3-F, 3-G, 3-H, 3-I, 3-J, 3-K, 3-L,
3-M, 3-N, 3-O, 3-P, 3-Q, 3-R, 3-S, 3-T, 3-U, 3-V, 3-W, 3-X, 3-Y, 3-Z, 3-AA,
3-BB, 3-CC, 3-DD, 3-EE, 3-FF, 3-GG, 3-HH, 3-II, 3-JJ, 3-KK, 3-LL, 3-MM, 3-NN,
3-OO, 3-PP, 3-QQ, 3-RR, 3-SS, 3-TT, 3-UU, 3-VV, 3-WW, 3-XX, and 3-YY were
considered in one motion.
Upon motion of Mr. Hunt, second by Ms. Schneider, vote carried by roll-call,
with all votes yea, to approve Turner-Kiewit Joint Venture to issue a
Subcontract Modification to Alpha Insulation & Waterproofing, Inc. on BP-
S00147, South Terminal C, Phase 1 - Landside Terminal Remaining Structure and
Systems (GMP No. 7-S.1), for the total lump sum amount of $43,416.00, with
funding from Passenger Facility Charges and General Airport Revenue Bonds.
U. Subcontract Modification for BP-S00147 (GMP No. 7-S.1) with Enclos Corp. for CR0715-LST-RFIs 2649 and 2649.1 FIS Wall King Post Clash. Mr. Corthell
presented the memorandum, requesting approval for Turner-Kiewit Joint Venture
(TKJV) to issue a Subcontract Modification on BP-S00147, South Terminal C,
Phase 1 - Landside Terminal Remaining Structure and Systems (GMP No. 7-S.1),
Minutes of the Construction Committee Meeting, May 26, 2020
Page 26 of 59
at the Orlando International Airport, in the total amount of $21,104.00 to
Enclos Corp. for CR0715-LST-RFIs 2649 and 2649.1 FIS Wall King Post Clash.
Bid Package 8.3.0 "Interior Glazing" was previously awarded within GMP No.
7-S.1 to Enclos Corp., CC No. 20181002.009.
TKJV is proposing a subcontract modification to Enclos Corp. in the total lump
sum amount of $21,104.00 for CR0715-LST-RFIs 2649 and 2649.1 FIS Wall King
Post Clash. The structural steel and glazing were in conflict at the FIS exit
wall glass. The modified scope of work consists of necessary labor, material
and equipment for the additional installation of approximately 27 SF of
structural glass fin, per RFIs 2649 and 2649.1.
The approval of this subcontract modification to Enclos Corp. resolves all
requests for cost and time associated with RFIs 2649 and 2649.1 scope of work
in GMP No. 7-S.1. There are no cost impacts to GMP Nos. 7-S, 7-S.2, 7-S.3 and
7-S.4.
TKJV has submitted documentation including the subcontractor's proposal with
substantiating back-up to support this request. An independent cost estimate
is included. By approving this request, the Owner does not waive its right to
enforce the contract requirements for other requests for cost or time.
The effect of this Subcontract Modification for this project is as follows:
TKJV to issue a subcontract modification to Enclos
Corp. in the amount of: $ 21,104.00
Deduct from P1 Owner Contingency: $ (21,104.00)
Turner-Kiewit Joint Venture is committed to 20% MWBE and 4% LDB participation
for Construction Services. The subcontractor identified and committed to
participate on BP-S00147 (GMP No. 7-S.1) for this subcontract modification is
Enclos Corp. (Non-MWBE/LDB/VBE). There is no MWBE, LDB or VBE participation
associated with this modification.
Agenda Item Nos. 3-A, 3-B, 3-C, 3-D, 3-E, 3-F, 3-G, 3-H, 3-I, 3-J, 3-K, 3-L,
3-M, 3-N, 3-O, 3-P, 3-Q, 3-R, 3-S, 3-T, 3-U, 3-V, 3-W, 3-X, 3-Y, 3-Z, 3-AA,
3-BB, 3-CC, 3-DD, 3-EE, 3-FF, 3-GG, 3-HH, 3-II, 3-JJ, 3-KK, 3-LL, 3-MM, 3-NN,
3-OO, 3-PP, 3-QQ, 3-RR, 3-SS, 3-TT, 3-UU, 3-VV, 3-WW, 3-XX, and 3-YY were
considered in one motion.
Upon motion of Mr. Hunt, second by Ms. Schneider, vote carried by roll-call,
with all votes yea, to approve Turner-Kiewit Joint Venture to issue a
Subcontract Modification to Enclos Corp. on BP-S00147, South Terminal C, Phase
1 - Landside Terminal Remaining Structure and Systems (GMP No. 7-S.1), for the
total lump sum amount of $21,104.00, with funding from Passenger Facility
Charges and General Airport Revenue Bonds.
V. Subcontract Modification for BP-S00147 (GMP No. 7-S.1) with M.C. Dean, Inc. for CR0916-LST-RFI 2983.1 Intermediate Distribution Frame (IDF) Rooms 01-638AX
and 01-638BX Layout (Low Voltage Scope). Mr. Corthell presented the
memorandum, requesting approval for Turner-Kiewit Joint Venture (TKJV) to
issue a Subcontract Modification on BP-S00147, South Terminal C, Phase 1 -
Landside Terminal Remaining Structure and Systems (GMP No. 7-S.1), at the
Orlando International Airport, in the total deductive amount of ($16,011.00)
to M.C. Dean, Inc. for CR0916-LST-RFI 2983.1 Intermediate Distribution Frame
(IDF) Rooms 01-638AX and 01-638BX Layout (Low Voltage Scope). Bid Package
28.0.0 "Low Voltage" was previously awarded within GMP No. 7-S.1 to MC Dean,
Inc., CC No. 20181002.009.
Minutes of the Construction Committee Meeting, May 26, 2020
Page 27 of 59
TKJV is proposing a subcontract modification to M.C. Dean, Inc. in the total
deductive lump sum amount of ($16,011.00) for CR0916-LST-RFI 2983.1
Intermediate Distribution Frame (IDF) Rooms 01-638AX and 01-638BX Layout (Low
Voltage Scope). The modified scope of work includes the addition of an
Uninterruptible Power Supply (UPS) room and updates to the technology, security
and electrical design, resulting in an overall credit, per RFI 2983.1.
The approval of this subcontract modification to M.C. Dean, Inc. resolves all
requests for cost and time associated with RFI 2983.1 scope of work in GMP
No. 7-S.1. Cost impacts to GMP No. 7-S.3 will be submitted for CCM review
under CR0916.1. There are no cost impacts to GMP Nos. 7-S, 7-S.2 and 7-S.4.
TKJV has submitted documentation including the subcontractor's proposal to
support their request. An independent cost estimate is included. By approving
this request, the Owner does not waive its right to enforce the contract
requirements for other requests for cost or time.
The effect of this Subcontract Modification for this project is as follows:
TKJV to issue a subcontract modification to M.C.
Dean, Inc. in the deductive amount of: $ (16,011.00)
Add to P1X Owner Contingency: $ 16,011.00
Turner-Kiewit Joint Venture is committed to 20% MWBE and 4% LDB participation
for Construction Services. The subcontractor identified and committed to
participate on BP-S00147 (GMP No. 7-S.1) for this subcontract modification is
M.C. Dean, Inc. (Non-MWBE/LDB/VBE). This modification is comprised of an
addition to M.C. Dean, Inc. and a reduction to its MWBE subcontractor, Quality
Cable Contractors, Inc., in the deductive amount of ($19,034.25).
Ms. Sharman asked if this request takes into account any potential reductions
to the GMP. Mr. Corthell answered yes.
Agenda Item Nos. 3-A, 3-B, 3-C, 3-D, 3-E, 3-F, 3-G, 3-H, 3-I, 3-J, 3-K, 3-L,
3-M, 3-N, 3-O, 3-P, 3-Q, 3-R, 3-S, 3-T, 3-U, 3-V, 3-W, 3-X, 3-Y, 3-Z, 3-AA,
3-BB, 3-CC, 3-DD, 3-EE, 3-FF, 3-GG, 3-HH, 3-II, 3-JJ, 3-KK, 3-LL, 3-MM, 3-NN,
3-OO, 3-PP, 3-QQ, 3-RR, 3-SS, 3-TT, 3-UU, 3-VV, 3-WW, 3-XX, and 3-YY were
considered in one motion.
Upon motion of Mr. Hunt, second by Ms. Schneider, vote carried by roll-call,
with all votes yea, to approve Turner-Kiewit Joint Venture to issue a
Subcontract Modification to M.C. Dean, Inc. on BP-S00147, South Terminal C,
Phase 1 - Landside Terminal Remaining Structure and Systems (GMP No. 7-S.1),
for the total deductive lump sum amount of ($16,011.00), with funding credited
to Passenger Facility Charges and General Airport Revenue Bonds.
W. Subcontract Modification for BP-S00147 (GMP No. 7-S.1) with P&A Roofing & Sheet Metal, Inc. for CR0949-LST-RFIs 3711 and 3711.1 Roof Membrane Flashing
for Elevators 4.1 and 12.2. Mr. Corthell presented the memorandum, requesting
approval for Turner-Kiewit Joint Venture (TKJV) to issue a Subcontract
Modification on BP-S00147, South Terminal C, Phase 1 - Landside Terminal
Remaining Structure and Systems (GMP No. 7-S.1), at the Orlando International
Airport, in the total amount of $2,128.00 to P&A Roofing & Sheet Metal, Inc.
for CR0949-LST-RFIs 3711 and 3711.1 Roof Membrane Flashing for Elevators 4.1
and 12.2. Bid Package 7.2.0 "Roofing" was previously awarded within GMP No.
7-S.1 to P&A Roofing & Sheet Metal, Inc., CC No. 20181002.009.
TKJV is proposing the following subcontract modifications to P&A Roofing &
Sheet Metal, Inc. in the total lump sum amount of $2,128.00 for CR0949-LST-
Minutes of the Construction Committee Meeting, May 26, 2020
Page 28 of 59
RFIs 3711 and 3711.1 Roof Membrane Flashing for Elevators 4.1 and 12.2. The
modified scope of work consists of all cost associated with the installation
of membrane flashing at Elevators 4.1 and 12.2 relief hoods, per RFIs 3711 and
3711.1.
The approval of this subcontract modification to P&A Roofing & Sheet Metal,
Inc. resolves all requests for cost and time associated with RFIs 3711 and
3711.1 for the Roofing scope of work in GMP No. 7-S.1. Cost impacts to GMP
No. 7-S.l for the Masonry and Waterproofing scopes will be submitted in a
future CR. Cost impacts to GMP No. 7-S for the Structural Steel and Concrete
scopes will be submitted in a future CR. There are no cost impacts to GMP
Nos. 7-S.2, 7-S.3 and 7-S.4.
TKJV has submitted documentation including the subcontractor's proposal to
support their request. An independent cost estimate is included. By approving
this request, the Owner does not waive its right to enforce the contract
requirements for other requests for cost or time.
The effect of this Subcontract Modification for this project is as follows:
TKJV to issue a subcontract modification to P&A
Roofing & Sheet Metal, Inc. in the amount of: $ 2,128.00
Deduct from P1 Owner Contingency: $ (2,128.00)
Turner-Kiewit Joint Venture is committed to 20% MWBE and 4% LDB participation
for Construction Services. The subcontractor identified and committed to
participate on BP-S00147 (GMP No. 7-S.1) for this subcontract modification is
P&A Roofing & Sheet Metal, Inc. (Non-MWBE/LDB/VBE). There is no MWBE, LDB or
VBE participation associated with this modification.
Agenda Item Nos. 3-A, 3-B, 3-C, 3-D, 3-E, 3-F, 3-G, 3-H, 3-I, 3-J, 3-K, 3-L,
3-M, 3-N, 3-O, 3-P, 3-Q, 3-R, 3-S, 3-T, 3-U, 3-V, 3-W, 3-X, 3-Y, 3-Z, 3-AA,
3-BB, 3-CC, 3-DD, 3-EE, 3-FF, 3-GG, 3-HH, 3-II, 3-JJ, 3-KK, 3-LL, 3-MM, 3-NN,
3-OO, 3-PP, 3-QQ, 3-RR, 3-SS, 3-TT, 3-UU, 3-VV, 3-WW, 3-XX, and 3-YY were
considered in one motion.
Upon motion of Mr. Hunt, second by Ms. Schneider, vote carried by roll-call,
with all votes yea, to approve Turner-Kiewit Joint Venture to issue a
Subcontract Modification to P&A Roofing & Sheet Metal, Inc. on BP-S00147,
South Terminal C, Phase 1 - Landside Terminal Remaining Structure and Systems
(GMP No. 7-S.1), for the total lump sum amount of $2,128.00, with funding from
Passenger Facility Charges and General Airport Revenue Bonds.
X. Subcontract Modification for BP-S00147 (GMP No. 7-S.1) with Alpha Insulation & Waterproofing, Inc. for CR0963-LST-RFIs 3164 and 3164.1 Firestop and Caulking
of CMU/Drywall to Columns. Mr. Corthell presented the memorandum, requesting
approval for Turner-Kiewit Joint Venture (TKJV) to issue a Subcontract
Modification on BP-S00147, South Terminal C, Phase 1 - Landside Terminal
Remaining Structure and Systems (GMP No. 7-S.1), at the Orlando International
Airport, in the total amount of $19,577.00 to Alpha Insulation & Waterproofing,
Inc. for CR0963-LST-RFIs 3164 and 3164.1 Firestop and Caulking of CMU/Drywall
to Columns. Bid Package 7.3.0 "Applied Fireproofing" was previously awarded
within GMP No. 7-S.1 to Alpha Insulation & Waterproofing, Inc., CC No.
20181002.009.
TKJV is proposing a subcontract modification to Alpha Insulation &
Waterproofing, Inc. in the total lump sum amount of $19,577.00 for CR0963-LST-
RFIs 3164 and 3164.1 Firestop and Caulking of CMU/Drywall to Columns. The
modified scope of work consists of necessary labor, material and equipment for
Minutes of the Construction Committee Meeting, May 26, 2020
Page 29 of 59
the additional firestopping and caulking at 56 each 12-inch columns that
interrupt the 12-inch CMU wall around the Early Baggage Storage Room 01-4051,
per RFIs 3164 and 3164.1.
The approval of this subcontract modification to Alpha Insulation &
Waterproofing, Inc. resolves all requests for cost and time associated with
RFIs 3164 and 3164.1 for the Insulation scope in GMP No. 7-S.1. Cost impacts
to GMP No. 7-S.1 for the Masonry scope will be submitted in a future CR. There
are no cost impacts to GMP Nos. 7-S, 7-S.2, 7-S.3 and 7-S.4.
TKJV has submitted documentation including the subcontractor's proposal to
support their request. An independent cost estimate is included. By approving
this request, the Owner does not waive its right to enforce the contract
requirements for other requests for cost or time.
The effect of this Subcontract Modification for this project is as follows:
TKJV to issue a subcontract modification to Alpha
Insulation & Waterproofing, Inc. in the amount of: $ 19,577.00
Deduct from P1 Owner Contingency: $ (19,577.00)
Turner-Kiewit Joint Venture is committed to 20% MWBE and 4% LDB participation
for Construction Services. The subcontractor identified and committed to
participate on BP-S00147 (GMP No. 7-S.1) for this subcontract modification is
Alpha Insulation & Waterproofing, Inc. (Non-MWBE/LDB/VBE). There is no MWBE,
LDB or VBE participation associated with this modification.
Agenda Item Nos. 3-A, 3-B, 3-C, 3-D, 3-E, 3-F, 3-G, 3-H, 3-I, 3-J, 3-K, 3-L,
3-M, 3-N, 3-O, 3-P, 3-Q, 3-R, 3-S, 3-T, 3-U, 3-V, 3-W, 3-X, 3-Y, 3-Z, 3-AA,
3-BB, 3-CC, 3-DD, 3-EE, 3-FF, 3-GG, 3-HH, 3-II, 3-JJ, 3-KK, 3-LL, 3-MM, 3-NN,
3-OO, 3-PP, 3-QQ, 3-RR, 3-SS, 3-TT, 3-UU, 3-VV, 3-WW, 3-XX, and 3-YY were
considered in one motion.
Upon motion of Mr. Hunt, second by Ms. Schneider, vote carried by roll-call,
with all votes yea, to approve Turner-Kiewit Joint Venture to issue a
Subcontract Modification to Alpha Insulation & Waterproofing, Inc. on
BP-S00147, South Terminal C, Phase 1 - Landside Terminal Remaining Structure
and Systems (GMP No. 7-S.1), for the total lump sum amount of $19,577.00, with
funding from Passenger Facility Charges and General Airport Revenue Bonds.
Y. Subcontract Modification for BP-S00150 (GMP No. 9-S) with Morton Electric, Inc. for CR0329.4-PKG-Bulletin 8 - Electrical Gear Storage. [A handout was
presented, which includes a revised Coversheet.] Mr. Corthell presented the
memorandum, requesting approval for Turner-Kiewit Joint Venture (TKJV) to
issue a Subcontract Modification on BP-S00150, South Terminal C, Phase 1,
Parking Facility - Phase 1 (GMP No. 9-S), at the Orlando International Airport,
in the total amount of $32,838.00 to Morton Electric, Inc. for CR0329.4-PKG-
Bulletin 8 - Electrical Gear Storage. Bid Package 26.0.0 "Electrical" was
previously awarded within the GMP No. 9-S to Morton Electric, Inc. CC No.
20171010.16.
TKJV is proposing a Subcontractor Modification to Morton Electric, Inc. in the
total Lump Sum amount of $32,838.00 for CR0329.4-PKG-Bulletin 8 - Electrical
Gear Storage. The electrical switchgear was released for fabrication in
October 2018 following the January 2019 approval of CR 080.4 for Electrical
design revisions included in PKG Bulletins 3, 4, and 5, CC No. 20190115.02M.
The gear was ready for delivery in May 2019 as originally planned at the time
of release. PKG Bulletin 8, issued on January 31, 2019, revised the structural
and electrical drawings based on the PKG elevator Lobby VE and City Comments.
Minutes of the Construction Committee Meeting, May 26, 2020
Page 30 of 59
Revisions associated with this Bulletin caused additional structural work at
the Elevator Core 4. Storage of the gear was required until the revised PKG
switchgear room in the Elevator 4 was constructed. The modified scope of work
included in this change request consists of additional storage, loading and
transportation costs associated with Morton Electric, Inc.'s Electrical Gear
stored at the Broken Arrow, OK, facility from May 6, 2019, to September 5,
2019.
The approval of this subcontract modification to Morton Electric, Inc. resolves
all requests for costs and time for the scope of work as presented in CR0329.4-
PKG-Bulletin 8 - Electrical Gear Storage associated with the PKG Bulletin 8.
The following trades were submitted and approved under separate change
requests:
CR0329.0-9S-Concrete-Early Release Rebar and Engineering-CC No.
20190507.02G.
CR0329.1-9S-Electrical-CC No. 20190625.02M.
CR0329.2-9S-HVAC, Plumbing and Fire Protection-CC No.20190730.02D.
CR0329.3-9S.l-Finishes-CC No. 20190827.02K.
CR0329.6-9S.1-Transfer of Unbought Items-Terrazzo and Interior
Decorative Glazing-CC No. 20190723.03D.
CR0375-9S.1-Resilient Flooring-CC No.20190611.02D.
CR0248-9S-PKG-Bulletin 4 and RFI 1263-EGM Removal of the Curtain Wall-
CC No. 20190115.02L.
CR934-9S-PKG CCK Remaining Cost Bulletin 8-CC No.20200407.03K.
TKJV has submitted documentation including the subcontractor's proposal to
support their request. An independent cost estimate is included. By approving
this request, the Owner does not waive its right to enforce the contract
requirements for other requests for cost or time.
The effect of this Subcontract Modification for this project is as follows:
TKJV to issue subcontract modification to Morton
Electric, Inc. in the lump sum amount of: $ 32,838.00
Deduct from P1 Owner Contingency: $ (13,647.00)
Deduct from P1 CMAR Contingency: $ (19,191.00)
Turner-Kiewit Joint Venture is committed to 20% MWBE and 4% LDB participation
for Construction Services. The subcontractor identified and committed to
participate on BP-S00150 (GMP No. 9-S) for this subcontract modification is
Morton Electric, Inc. (Non-MWBE/LDB/VBE). There is no small business
participation associated with this modification.
Agenda Item Nos. 3-A, 3-B, 3-C, 3-D, 3-E, 3-F, 3-G, 3-H, 3-I, 3-J, 3-K, 3-L,
3-M, 3-N, 3-O, 3-P, 3-Q, 3-R, 3-S, 3-T, 3-U, 3-V, 3-W, 3-X, 3-Y, 3-Z, 3-AA,
3-BB, 3-CC, 3-DD, 3-EE, 3-FF, 3-GG, 3-HH, 3-II, 3-JJ, 3-KK, 3-LL, 3-MM, 3-NN,
3-OO, 3-PP, 3-QQ, 3-RR, 3-SS, 3-TT, 3-UU, 3-VV, 3-WW, 3-XX, and 3-YY were
considered in one motion.
Upon motion of Mr. Hunt, second by Ms. Schneider, vote carried by roll-call,
with all votes yea, to approve Turner-Kiewit Joint Venture to issue a
Subcontract Modification to Morton Electric, Inc. on BP-S00150, South Terminal
C, Phase 1 - Parking Facility - Phase 1 (GMP No. 9-S), for the total lump sum
amount of $32,838.00, with funding from Customer Facility Charges and General
Airport Revenue Bonds.
Minutes of the Construction Committee Meeting, May 26, 2020
Page 31 of 59
Z. Subcontract Modification for BP-S00150 (GMP No. 9-S) with Alpha Insulation & Waterproofing, Inc. for CR0841.2-9S-PKG-Vertical Expansion Joint on Promenade
Columns Area 4 Level 3. Mr. Corthell presented the memorandum, requesting
approval for Turner-Kiewit Joint Venture (TKJV) to issue a Subcontract
Modification on BP-S00150, South Terminal C, Phase 1, Parking Facility - Phase
1 (GMP No. 9-S), at the Orlando International Airport, in the total amount of
$20,511.00 to Alpha Insulation & Waterproofing, Inc. for CR0841.2-9S-PKG-
Vertical Expansion Joint on Promenade Columns Area 4 Level 3. Bid Package
7.0.0 "Waterproofing" was previously awarded within GMP No. 9-S to Alpha
Insulation & Waterproofing, Inc. CC No. 20171010.16.
TKJV is proposing a subcontract modification to Alpha Insulation &
Waterproofing, Inc. in the total lump sum amount of $20,511.00 for CR0841.2-
9S-PKG-Vertical Expansion Joint on Promenade Columns Area 4 Level 3. The
vertical expansion joints in the plaster system for the promenade columns
Area 4 Level 3 were not included in either the MSE2, Inc. or Alpha Insulation
subcontract scopes of work, creating a scope gap. The modified scope of work
consists of all labor, material and equipment to install the vertical expansion
joint on the promenade Columns Area 4 level 3.
The approval of this subcontract modification to Alpha Insulation &
Waterproofing, Inc. resolves all requests for cost and time associated with
Vertical Expansion Joint on Promenade Columns Area 4 Level 3 scope of work and
CR0841.2-9S-PKG-Vertical Expansion Joint on Promenade Columns Area 4 Level 3.
TKJV has submitted documentation including the subcontractor's proposal to
support their request. By approving this request, the Owner does not waive its
right to enforce the contract requirements for other requests for cost or
time.
The effect of this Subcontract Modification for this project is as follows:
TKJV to issue subcontract modification to Alpha
Insulation & Waterproofing, Inc. in the lump sum
amount of: $ 20,511.00
Deduct from CMAR Contingency: $ (20,511.00)
Turner-Kiewit Joint Venture is committed to 20% MWBE and 4% LDB participation
for Construction Services. The subcontractor identified and committed to
participate on BP-S00150 (GMP No. 9-S) for this subcontract modification is
Alpha Insulation & Waterproofing, Inc. (Non-MWBE/LDB/VBE). There is no small
business participation associated with this modification.
Agenda Item Nos. 3-A, 3-B, 3-C, 3-D, 3-E, 3-F, 3-G, 3-H, 3-I, 3-J, 3-K, 3-L,
3-M, 3-N, 3-O, 3-P, 3-Q, 3-R, 3-S, 3-T, 3-U, 3-V, 3-W, 3-X, 3-Y, 3-Z, 3-AA,
3-BB, 3-CC, 3-DD, 3-EE, 3-FF, 3-GG, 3-HH, 3-II, 3-JJ, 3-KK, 3-LL, 3-MM, 3-NN,
3-OO, 3-PP, 3-QQ, 3-RR, 3-SS, 3-TT, 3-UU, 3-VV, 3-WW, 3-XX, and 3-YY were
considered in one motion.
Upon motion of Mr. Hunt, second by Ms. Schneider, vote carried by roll-call,
with all votes yea, to approve Turner-Kiewit Joint Venture to issue a
Subcontract Modification to Alpha Insulation & Waterproofing, Inc. on BP-
S00150, South Terminal C, Phase 1 - Parking Facility - Phase 1 (GMP No. 9-S),
for the total lump sum amount of $20,511.00, with funding from Customer
Facility Charges and General Airport Revenue Bonds.
Minutes of the Construction Committee Meeting, May 26, 2020
Page 32 of 59
AA. Subcontract Modification for BP-S00150 (GMP No. 9-S) with Alpha Insulation &
Waterproofing, Inc. for CR1021-9S-PKG-Existing Garage Expansion Joint Repair.
Mr. Corthell presented the memorandum, requesting approval for Turner-Kiewit
Joint Venture (TKJV) to issue a Subcontract Modification on BP-S00150, South
Terminal C, Phase 1, Parking Facility - Phase 1 (GMP No. 9-S), at the Orlando
International Airport, in the total amount of $3,267.00 to Alpha Insulation &
Waterproofing, Inc. for CR1021-9S-PKG-Existing Garage Expansion Joint Repair.
Bid Package 7.0.0 "Waterproofing" was previously awarded within GMP No. 9-S
to Alpha Insulation & Waterproofing, Inc. CC No. 20171010.16.
TKJV is proposing a subcontract modification to Alpha Insulation &
Waterproofing, Inc. in the total lump sum amount of $3,267.00 for CR1021-9S-
PKG-Existing Garage Expansion Joint Repair. Per GOAA's request during a field
walk that took place March 27, 2020, TKJV was required to proceed with the
repairs of two expansion joints at the existing Parking Garage. The modified
scope of work consists of all labor, material and equipment costs associated
with the removal and replacement of existing PKG expansion joints at Stair
No. 2 (Gridline GH) Level 4 and Stair No. 4 (Gridline G6) Level 2 as requested
on March 27, 2020.
The approval of this subcontract modification to Alpha Insulation &
Waterproofing, Inc. resolves all requests for cost and time associated with
CR1021-9S-PKG-Existing Garage Expansion Joint Repair.
TKJV has submitted documentation including the subcontractor's proposal to
support their request. By approving this request, the Owner does not waive its
right to enforce the contract requirements for other requests for cost or
time.
The effect of this Subcontract Modification for this project is as follows:
TKJV to issue subcontract modification to Alpha
Insulation & Waterproofing, Inc. in the lump sum
amount of: $ 3,267.00
Deduct from P1 Owner Contingency: $ (3,267.00)
Turner-Kiewit Joint Venture is committed to 20% MWBE and 4% LDB participation
for Construction Services. The subcontractor identified and committed to
participate on BP-S00150 (GMP No. 9-S) for this subcontract modification is
Alpha Insulation & Waterproofing, Inc. (Non-MWBE/LDB/VBE). There is no small
business participation associated with this modification.
Agenda Item Nos. 3-A, 3-B, 3-C, 3-D, 3-E, 3-F, 3-G, 3-H, 3-I, 3-J, 3-K, 3-L,
3-M, 3-N, 3-O, 3-P, 3-Q, 3-R, 3-S, 3-T, 3-U, 3-V, 3-W, 3-X, 3-Y, 3-Z, 3-AA,
3-BB, 3-CC, 3-DD, 3-EE, 3-FF, 3-GG, 3-HH, 3-II, 3-JJ, 3-KK, 3-LL, 3-MM, 3-NN,
3-OO, 3-PP, 3-QQ, 3-RR, 3-SS, 3-TT, 3-UU, 3-VV, 3-WW, 3-XX, and 3-YY were
considered in one motion.
Upon motion of Mr. Hunt, second by Ms. Schneider, vote carried by roll-call,
with all votes yea, to approve Turner-Kiewit Joint Venture to issue a
Subcontract Modification to Alpha Insulation & Waterproofing, Inc. on BP-
S00150, South Terminal C, Phase 1 - Parking Facility - Phase 1 (GMP No. 9-S),
for the total lump sum amount of $3,267.00, with funding from Customer Facility
Charges and General Airport Revenue Bonds.
Minutes of the Construction Committee Meeting, May 26, 2020
Page 33 of 59
BB. Subcontract Modification for BP-S00150 (GMP No. 9-S) with Skybuilders USA, LLC
for CR1031-9S-PKG-Promenade Remediation Work for New Expansion Joint (CWA BP-
S00150-005). Mr. Corthell presented the memorandum, requesting approval for
Turner-Kiewit Joint Venture (TKJV) to issue a Subcontract Modification on BP-
S00150, South Terminal C, Phase 1, Parking Facility - Phase 1 (GMP No. 9-S),
at the Orlando International Airport, in the total amount of $1,075.00 to
Skybuilders USA, LLC for CR1031-9S-PKG-Promenade Remediation Work for New
Expansion Joint (CWA BP-S00150-005). Bid Package 31.0.0 "Demolition" was
previously awarded within GMP No. 9-S to Skybuilders USA, LLC, CC No.
20171010.16.
TKJV is proposing a subcontract modification to Skybuilders USA, LLC in the
total lump sum amount of $1,075.00 for CR1031-9S-PKG-Promenade Remediation
work for New Expansion Joint (CWA BP-S00150-005). During the pre-construction
evaluation of existing conditions in the existing Phase 1, it was not
identified that the PKG promenade structure was 1-inch higher than shown on
the plans, and as a result additional remediation work is needed to prepare
the existing area to receive the new expansion joint along GL G2.
The approval of this subcontract modification to Skybuilders USA, LLC resolves
all requests for cost and time associated with the PKG Promenade Remediation
work for CR1031-9S-PKG-Promenade Remediation work for New Expansion Joint and
closes CWA BP-S00150-005.
TKJV has submitted documentation including the subcontractor's proposal to
support their request. By approving this request, the Owner does not waive its
right to enforce the contract requirements for other requests for cost or
time.
TKJV has submitted documentation including the subcontractor's proposal to
support their request. An independent cost estimate is included. By approving
this request, the Owner does not waive its right to enforce the contract
requirements for other requests for cost or time.
The effect of this Subcontract Modification for this project is as follows:
TKJV to issue subcontract modification to Skybuilders
USA, LLC in the lump sum amount of: $ 1,075.00
Deduct from CMAR Contingency: $ (1,075.00)
Turner-Kiewit Joint Venture is committed to 20% MWBE and 4% LDB participation
for Construction Services. The subcontractor identified and committed to
participate on BP-S00150 (GMP No. 9-S) for this subcontract modification is
Skybuilders USA, LLC (MWBE/LDB). There is 100% MWBE participation associated
with this modification.
Agenda Item Nos. 3-A, 3-B, 3-C, 3-D, 3-E, 3-F, 3-G, 3-H, 3-I, 3-J, 3-K, 3-L,
3-M, 3-N, 3-O, 3-P, 3-Q, 3-R, 3-S, 3-T, 3-U, 3-V, 3-W, 3-X, 3-Y, 3-Z, 3-AA,
3-BB, 3-CC, 3-DD, 3-EE, 3-FF, 3-GG, 3-HH, 3-II, 3-JJ, 3-KK, 3-LL, 3-MM, 3-NN,
3-OO, 3-PP, 3-QQ, 3-RR, 3-SS, 3-TT, 3-UU, 3-VV, 3-WW, 3-XX, and 3-YY were
considered in one motion.
Upon motion of Mr. Hunt, second by Ms. Schneider, vote carried by roll-call,
with all votes yea, to approve Turner-Kiewit Joint Venture to issue a
Subcontract Modification to Skybuilders USA, LLC on BP-S00150, South Terminal
C, Phase 1 - Parking Facility - Phase 1 (GMP No. 9-S), for the total lump sum
amount of $1,075.00, with funding from Customer Facility Charges and General
Airport Revenue Bonds.
Minutes of the Construction Committee Meeting, May 26, 2020
Page 34 of 59
CC. Subcontract Modification for BP-S00150 (GMP No. 9-S) with Gulf Mechanical
Contractors, LLC for CR0591-PKG-RFIs 1161 and 1161.1 CHWSR Re-routing for
Level 2 (CWA BP-S00150-006). Mr. Corthell presented the memorandum, requesting
approval for Turner-Kiewit Joint Venture (TKJV) to issue a Subcontract
Modification on BP-S00150, South Terminal C, Phase 1, Parking Facility - Phase
1 (GMP No. 9-S), at the Orlando International Airport, in the total amount of
$24,208.00 to Gulf Mechanical Contractors, LLC for CR0591-PKG-RFIs 1161 and
1161.1 CHWSR Re-routing for Level 2 (CWA BP-S00150-006). Bid Package 23.0.0
"HVAC Mechanical" was previously awarded within GMP No. 9-S to Gulf Mechanical
Contractors, LLC CC No. 20171010.16.
TKJV is proposing a subcontract modification to Gulf Mechanical Contractors,
LLC, in the total lump sum amount of $24,208.00 for CR0591-PKG-RFIs 1161 and
1161.1 CHWSR Re-routing for Level 2. Drawing M2.02.02 Note No. 2 states to
route chilled water piping in existing mechanical rooms, but there was not a
clear path for the contractor to install the piping without being in conflict
with pre-existing piping, conduit, damper, panels or gear. The submitted shop
drawings recommended running the chilled water lines exposed on the exterior
of the mechanical room wall between the existing stairwells. RFI 1161 was
issued to confirm this alternative routing and after a site visit with the
relevant parties, RFI 1161.1 confirmed the routing in approved Submittal
230500-0001-0. The modified scope of work captured in this request consists
of all material, labor and equipment costs associated with rerouting and
extending the chilled water supply and return piping on the exterior of the
mechanical room per the responses to RFIs 1161 and 1161.1.
The approval of this subcontract modification resolves all requests for cost
and time associated with PKG RFI 1161 Series and closes CWA BP-S00150-006.
TKJV has submitted documentation including the subcontractor's proposal to
support their request. An independent cost estimate is included. By approving
this request, the Owner does not waive its right to enforce the contract
requirements for other requests for cost or time.
The effect of this Subcontract Modification for this project is as follows:
TKJV to issue subcontract modification to Gulf
Mechanical Contractors, LLC in the lump sum amount of: $ 24,208.00
Deduct from P1 CMAR Contingency: $ (24,208.00)
Turner-Kiewit Joint Venture is committed to 20% MWBE and 4% LDB participation
for Construction Services. The subcontractor identified and committed to
participate on BP-S00150 (GMP No. 9-S) for this subcontract modification is
Gulf Mechanical Contractors, LLC (Non-MWBE/LDB/VBE). There is 47.4% MWBE
participation associated with this modification.
Agenda Item Nos. 3-A, 3-B, 3-C, 3-D, 3-E, 3-F, 3-G, 3-H, 3-I, 3-J, 3-K, 3-L,
3-M, 3-N, 3-O, 3-P, 3-Q, 3-R, 3-S, 3-T, 3-U, 3-V, 3-W, 3-X, 3-Y, 3-Z, 3-AA,
3-BB, 3-CC, 3-DD, 3-EE, 3-FF, 3-GG, 3-HH, 3-II, 3-JJ, 3-KK, 3-LL, 3-MM, 3-NN,
3-OO, 3-PP, 3-QQ, 3-RR, 3-SS, 3-TT, 3-UU, 3-VV, 3-WW, 3-XX, and 3-YY were
considered in one motion.
Upon motion of Mr. Hunt, second by Ms. Schneider, vote carried by roll-call,
with all votes yea, to approve Turner-Kiewit Joint Venture to issue a
Subcontract Modification to Gulf Mechanical Contractors, LLC on BP-S00150,
South Terminal C, Phase 1 - Parking Facility - Phase 1 (GMP No. 9-S), for the
total lump sum amount of $24,208.00, with funding from Customer Facility
Charges and General Airport Revenue Bonds.
Minutes of the Construction Committee Meeting, May 26, 2020
Page 35 of 59
DD. Subcontract Modification for BP-S00150 (GMP No. 9-S) with Skybuilders USA, LLC
for CR0816-9S-PKG-RFI-3798-Area 1 North Slab on Grade Removal (CWA BP-S00150-
009). Mr. Corthell presented the memorandum, requesting approval for Turner-
Kiewit Joint Venture (TKJV) to issue a Subcontract Modification on BP-S00150,
South Terminal C, Phase 1, Parking Facility - Phase 1 (GMP No. 9-S), at the
Orlando International Airport, in the total amount of $12,321.00 to Skybuilders
USA, LLC for CR0816-9S-PKG-RFI-3798-Area 1 North Slab on Grade Removal (CWA
BP-S00150-009). Bid Package 31.0.0 "Demolition" was previously awarded within
GMP 9S to Skybuilders USA, LLC, CC No. 20171010.16.
TKJV is proposing a subcontract modification to Skybuilders USA, LLC in the
total lump sum amount of $12,321.00 for CR0816-9S-PKG-RFI-3798-Area 1 North
Slab on Grade Removal. Per structural note in drawing S-1.01.04A the contractor
is required to verify that there is a minimum of 8-foot 4-inch headroom between
all driving surfaces and overhead beams prior to placing concrete. In RFI 1373
a field condition was presented to the AOR at PKG Elevator Tower No. 4 where
the overhead clearance between Level 1 and the bottom of concrete beams was
two inches below the 8-foot 4-inch minimum headroom requirement. Since the
Level 2 beams and elevated deck at this location had already been poured, TKJV
suggested as a solution to this issue lowering the elevations noted from
0-foot 0-inch to minus 2-inches, and the RFI 1373 response confirmed this as
acceptable. Based on the change in elevation in RFI 1373, there was a
difference in slope in the Slab-On-Grade (SOG) that would exceed the 2-percent
requirement per the ADA. RFI 3798 confirmed that it is acceptable to remove
the existing SOG back to the south wall of the existing electrical room and
replace to allow for the new SOG to meet the 2-percent slope requirement per
ADA. The modified scope of work consists of all labor, material and equipment
costs to remove the SOG per RFI 3798 response.
The approval of this subcontract modification to Skybuilders USA, LLC resolves
all requests for costs and time associated with RFI 3798 and closes CWA BP-
S00150-009.
TKJV has submitted documentation including the subcontractor's proposal to
support their request. An independent cost estimate is included. By approving
this request, the Owner does not waive its right to enforce the contract
requirements for other requests for cost or time.
The effect of this Subcontract Modification for this project is as follows:
TKJV to issue subcontract modification to Skybuilders
USA, LLC in the lump sum amount of: $ 12,321.00
Deduct from CMAR Contingency: $ (12,321.00)
Turner-Kiewit Joint Venture is committed to 20% MWBE and 4% LDB participation
for Construction Services. The subcontractor identified and committed to
participate on BP-S00150 (GMP No. 9-S) for this subcontract modification is
Skybuilders USA, LLC (MWBE/LDB). There is 100% MWBE participation associated
with this modification.
Agenda Item Nos. 3-A, 3-B, 3-C, 3-D, 3-E, 3-F, 3-G, 3-H, 3-I, 3-J, 3-K, 3-L,
3-M, 3-N, 3-O, 3-P, 3-Q, 3-R, 3-S, 3-T, 3-U, 3-V, 3-W, 3-X, 3-Y, 3-Z, 3-AA,
3-BB, 3-CC, 3-DD, 3-EE, 3-FF, 3-GG, 3-HH, 3-II, 3-JJ, 3-KK, 3-LL, 3-MM, 3-NN,
3-OO, 3-PP, 3-QQ, 3-RR, 3-SS, 3-TT, 3-UU, 3-VV, 3-WW, 3-XX, and 3-YY were
considered in one motion.
Upon motion of Mr. Hunt, second by Ms. Schneider, vote carried by roll-call,
with all votes yea, to approve Turner-Kiewit Joint Venture to issue a
Subcontract Modification to Skybuilders USA, LLC on BP-S00150, South Terminal
Minutes of the Construction Committee Meeting, May 26, 2020
Page 36 of 59
C, Phase 1 - Parking Facility - Phase 1 (GMP No. 9-S), for the total lump sum
amount of $12,321.00, with funding from Customer Facility Charges and General
Airport Revenue Bonds.
EE. Subcontract Modification for BP-S00150 (GMP No. 9-S) with Skybuilders USA, LLC
for CR0998-9S-PKG-RFI-4152-Additional Demolitin at Stair 1 (CWA BP-S00150-
010). Mr. Corthell presented the memorandum, requesting approval for Turner-
Kiewit Joint Venture (TKJV) to issue a Subcontract Modification on BP-S00150,
South Terminal C, Phase 1, Parking Facility - Phase 1 (GMP No. 9-S), at the
Orlando International Airport, in the total amount of $11,525.00 to Skybuilders
USA, LLC for CR0998-9S-PKG-RFI-4152-Additional Demolition at Stair 1 (CWA BP-
S00150-010). Bid Package 31.0.0 "Demolition" was previously awarded within
GMP No. 9-S to Skybuilders USA, LLC, CC No. 20171010.16.
TKJV is proposing a subcontract modification to Skybuilders USA, LLC in the
total lump sum amount of $11,525.00 for CR0998-9S-PKG-RFI-4152-Additional
Demolition at Stair 1 (CWA BP-S00150-010). Per the contract documents at
Parking Garage Stair 1, the existing 6-inch CIP wall is to be removed where
the new stair riser is to tie into the existing. In order to attach to the
existing sheer wall and deck slab, additional demolition of the existing sheer
wall and deck is required to expose the rebar couplers installed in the
previous phase. RFI 4152 was issued to confirm if this additional demolition
is required. The response confirmed that the existing concrete surface must
be chipped back to expose the couplers. The modified scope of work consists
of all labor, material and equipment costs to expose the rebar couplers per
RFI 4152.
The approval of this subcontract modification to Skybuilders USA, LLC resolves
all requests for costs and time associated with RFI 4152 and closes CWA BP-
S00150-010.
TKJV has submitted documentation including the subcontractor's proposal to
support their request. An independent cost estimate is included. By approving
this request, the Owner does not waive its right to enforce the contract
requirements for other requests for cost or time.
The effect of this Subcontract Modification for this project is as follows:
TKJV to issue subcontract modification to Skybuilders
USA, LLC in the lump sum amount of: $ 11,525.00
Deduct from CMAR Contingency: $ (11,525.00)
Turner-Kiewit Joint Venture is committed to 20% MWBE and 4% LDB participation
for Construction Services. The subcontractor identified and committed to
participate on BP-S00150 (GMP No. 9-S) for this subcontract modification is
Skybuilders USA, LLC (MWBE/LDB). There is 100% MWBE participation associated
with this modification.
Agenda Item Nos. 3-A, 3-B, 3-C, 3-D, 3-E, 3-F, 3-G, 3-H, 3-I, 3-J, 3-K, 3-L,
3-M, 3-N, 3-O, 3-P, 3-Q, 3-R, 3-S, 3-T, 3-U, 3-V, 3-W, 3-X, 3-Y, 3-Z, 3-AA,
3-BB, 3-CC, 3-DD, 3-EE, 3-FF, 3-GG, 3-HH, 3-II, 3-JJ, 3-KK, 3-LL, 3-MM, 3-NN,
3-OO, 3-PP, 3-QQ, 3-RR, 3-SS, 3-TT, 3-UU, 3-VV, 3-WW, 3-XX, and 3-YY were
considered in one motion.
Upon motion of Mr. Hunt, second by Ms. Schneider, vote carried by roll-call,
with all votes yea, to approve Turner-Kiewit Joint Venture to issue a
Subcontract Modification to Skybuilders USA, LLC on BP-S00150, South Terminal
C, Phase 1 - Parking Facility - Phase 1 (GMP No. 9-S), for the total lump sum
Minutes of the Construction Committee Meeting, May 26, 2020
Page 37 of 59
amount of $11,525.00, with funding from Customer Facility Charges and General
Airport Revenue Bonds.
FF. Subcontract Modification for BP-S00150 (GMP No. 9-S) with Alpha Insulation &
Waterproofing, Inc. for CR01033-9S-PKG-0948-0948.1 - Traffic Topping at
Level 3. Mr. Corthell presented the memorandum, requesting approval for
Turner-Kiewit Joint Venture (TKJV) to issue a Subcontract Modification on BP-
S00150, South Terminal C, Phase 1, Parking Facility - Phase 1 (GMP No. 9-S),
at the Orlando International Airport, in the total deductive amount of
($28,832.00) to Alpha Insulation & Waterproofing, Inc. for CR01033-9S-PKG-
0948-0948.1 - Traffic Topping at Level 3. Bid Package 7.0.0 "Waterproofing"
was previously awarded within GMP 9S to Alpha Insulation & Waterproofing, Inc.
CC No. 20171010.16.
TKJV is proposing a subcontract modification to Alpha Insulation &
Waterproofing, Inc. in the total deductive lump sum amount of ($28,832.00) for
CR01033-9S-PKG-0948-0948.1 - Traffic Topping at Level 3. RFI 0948 was issued
to request the traffic topping limits on Level 3 between Grid Lines G1 and G3.
The RFI response confirmed the limits of the traffic topping as per Sheets
A2.03.01 and A2.06.02. Sheets Al.03.01 and S-l.03.01 were updated to maintain
the conformity between structural and architectural drawings. Subsequently,
RFI 948.1 Revised Sheet Al.03.01 revising the limits of the traffic topping
required on Level 3 Areas 1 and 2 of the existing Parking Garage. The modified
scope of work captured in this request consists of a credit due to the deletion
of traffic coating areas at Level 3 per PKG RFIs 0948 and 0948.1.
The approval of this subcontract modification to Alpha Insulation &
Waterproofing, Inc. resolves all requests for cost and time associated with
RFIs 0948-0948.1
TKJV has submitted documentation including the subcontractor's proposal to
support their request. An independent cost estimate is included. By approving
this request, the Owner does not waive its right to enforce the contract
requirements for other requests for cost or time.
The effect of this Subcontract Modification for this project is as follows:
TKJV to issue subcontract modification to Alpha
Insulation & Waterproofing, Inc. in the deductive lump
sum amount of: $ (28,832.00)
Add to Owner Contingency: $ 28,832.00
Turner-Kiewit Joint Venture is committed to 20% MWBE and 4% LDB participation
for Construction Services. The subcontractor identified and committed to
participate on BP-S00150 (GMP No. 9-S) for this subcontract modification is
Alpha Insulation & Waterproofing, Inc. (Non-MWBE/LDB/VBE). There is no small
business participation associated with this modification.
Agenda Item Nos. 3-A, 3-B, 3-C, 3-D, 3-E, 3-F, 3-G, 3-H, 3-I, 3-J, 3-K, 3-L,
3-M, 3-N, 3-O, 3-P, 3-Q, 3-R, 3-S, 3-T, 3-U, 3-V, 3-W, 3-X, 3-Y, 3-Z, 3-AA,
3-BB, 3-CC, 3-DD, 3-EE, 3-FF, 3-GG, 3-HH, 3-II, 3-JJ, 3-KK, 3-LL, 3-MM, 3-NN,
3-OO, 3-PP, 3-QQ, 3-RR, 3-SS, 3-TT, 3-UU, 3-VV, 3-WW, 3-XX, and 3-YY were
considered in one motion.
Upon motion of Mr. Hunt, second by Ms. Schneider, vote carried by roll-call,
with all votes yea, to approve Turner-Kiewit Joint Venture to issue a
Subcontract Modification to Alpha Insulation & Waterproofing, Inc. on BP-
S00150, South Terminal C, Phase 1 - Parking Facility - Phase 1 (GMP No. 9-S),
Minutes of the Construction Committee Meeting, May 26, 2020
Page 38 of 59
for the total deductive lump sum amount of ($28,832.00), with funding credited
to Customer Facility Charges and General Airport Revenue Bonds.
GG. Subcontract Modification for BP-S00150 (GMP No. 9-S) with Gulf Mechanical
Contractors, LLC for CR1034-PKG-RFI 3768-Promenade Overflow Drains (CWA BP-
S00150-011). Mr. Corthell presented the memorandum, requesting approval for
Turner-Kiewit Joint Venture (TKJV) to issue a Subcontract Modification on BP-
S00150, South Terminal C, Phase 1, Parking Facility - Phase 1 (GMP No. 9-S),
at the Orlando International Airport, in the total amount of $20,708.00 to
Gulf Mechanical Contractors, LLC for CR1034-PKG-RFI 3768-Promenade Overflow
Drains (CWA BP-S00150-011). Bid Package 22.0.0 "Plumbing" was previously
awarded within GMP No. 9-S to Gulf Mechanical Contractors, LLC, CC No.
20171010.16.
TKJV is proposing a subcontract modification to Gulf Mechanical Contractors,
LLC, in the total lump sum amount of $20,708.00 for CR1034-PKG-RFI 3768-
Promenade Overflow Drains. RFI 3768 was generated to confirm the design teams
request to modify the overflow drains that were terminating out in the open,
down the eastern columns of the promenade. The RFI response provided direction
to install a dry well at the base of the overflow drains, dig holes 3-4 feet
in diameter at a depth of 6-feet, and line the hole with geo-textile fabric
and fill with 57 stone to finish grade. The modified scope of work consists
of all labor material and equipment costs to reroute the promenade overflow
drains. Scope of work includes PVC DWV pipes, fittings, new hangers and riser
clamps.
The approval of this subcontract modification resolves all requests for cost
and time associated with PKG RFI 3768 and closes CWA BP-S00150-011.
TKJV has submitted documentation including the subcontractor's proposal to
support their request. An independent cost estimate is included. By approving
this request, the Owner does not waive its right to enforce the contract
requirements for other requests for cost or time.
The effect of this Subcontract Modification for this project is as follows:
TKJV to issue subcontract modification to Gulf
Mechanical Contractors, LLC in the lump sum amount of: $ 20,708.00
Deduct from CWE Owner Contingency: $ (20,708.00)
Turner-Kiewit Joint Venture is committed to 20% MWBE and 4% LDB participation
for Construction Services. The subcontractor identified and committed to
participate on BP-S00150 (GMP No. 9-S) for this subcontract modification is
Gulf Mechanical Contractors, LLC (Non-MWBE/LDB/VBE). There is no small
business participation associated with this modification.
Agenda Item Nos. 3-A, 3-B, 3-C, 3-D, 3-E, 3-F, 3-G, 3-H, 3-I, 3-J, 3-K, 3-L,
3-M, 3-N, 3-O, 3-P, 3-Q, 3-R, 3-S, 3-T, 3-U, 3-V, 3-W, 3-X, 3-Y, 3-Z, 3-AA,
3-BB, 3-CC, 3-DD, 3-EE, 3-FF, 3-GG, 3-HH, 3-II, 3-JJ, 3-KK, 3-LL, 3-MM, 3-NN,
3-OO, 3-PP, 3-QQ, 3-RR, 3-SS, 3-TT, 3-UU, 3-VV, 3-WW, 3-XX, and 3-YY were
considered in one motion.
Upon motion of Mr. Hunt, second by Ms. Schneider, vote carried by roll-call,
with all votes yea, to approve Turner-Kiewit Joint Venture to issue a
Subcontract Modification to Gulf Mechanical Contractors, LLC on BP-S00150,
South Terminal C, Phase 1 - Parking Facility - Phase 1 (GMP No. 9-S), for the
total lump sum amount of $20,708.00, with funding from Customer Facility
Charges.
Minutes of the Construction Committee Meeting, May 26, 2020
Page 39 of 59
HH. Subcontract Modification for BP-S00150 (GMP No. 9-S) with Gulf Mechanical
Contractors, LLC for CR1035-PKG-RFI 3718 - Storm Drain at Ramp (CWA BP-S00150-
012). Mr. Corthell presented the memorandum, requesting approval for Turner-
Kiewit Joint Venture (TKJV) to issue a Subcontract Modification on BP-S00150,
South Terminal C, Phase 1, Parking Facility - Phase 1 (GMP No. 9-S), at the
Orlando International Airport, in the total amount of $2,588.00 to Gulf
Mechanical Contractors, LLC for CR1035-PKG-RFI 3718 - Storm Drain at Ramp (CWA
BP-S00150-012). Bid Package 22.0.0 "Plumbing" was previously awarded within
GMP No. 9-S to Gulf Mechanical Contractors, LLC, CC No. 20171010.16.
TKJV is proposing a subcontract modification to Gulf Mechanical Contractors,
LLC, in the lump sum amount of $2,588.00 for CR1035-PKG-RFI 3718 - Storm Drain
at Ramp (CWA BP-S00150-012). On Page S1.02.04, there is a floor drain tagged
at Column Line GM/G1 on the ramp to the second floor. On Page P2.02.04, there
is what appears to be a circle, but no tag or piping shown or reflected.
RFI 3718 was issued to confirm the floor drain at this location. The RFI
response provided sketches for the drain type, sizing and routing. The
modified scope of work captured in this CR consists of all labor materials and
equipment to furnish and install all hangers, piping and deck drain.
The approval of this subcontract modification resolves all requests for cost
and time associated with PKG RFI 3718 and closes CWA BP-S00150-012.
TKJV has submitted documentation including the subcontractor's proposal to
support their request. An independent cost estimate is included. By approving
this request, the Owner does not waive its right to enforce the contract
requirements for other requests for cost or time.
The effect of this Subcontract Modification for this project is as follows:
TKJV to issue subcontract modification to Gulf
Mechanical Contractors, LLC in the lump sum amount of: $ 2,588.00
Deduct from P1 Owner Contingency: $ (2,588.00)
Turner-Kiewit Joint Venture is committed to 20% MWBE and 4% LDB participation
for Construction Services. The subcontractor identified and committed to
participate on BP-S00150 (GMP No. 9-S) for this subcontract modification is
Gulf Mechanical Contractors, LLC (Non-MWBE/LDB/VBE). There is no small business
participation associated with this modification.
Agenda Item Nos. 3-A, 3-B, 3-C, 3-D, 3-E, 3-F, 3-G, 3-H, 3-I, 3-J, 3-K, 3-L,
3-M, 3-N, 3-O, 3-P, 3-Q, 3-R, 3-S, 3-T, 3-U, 3-V, 3-W, 3-X, 3-Y, 3-Z, 3-AA,
3-BB, 3-CC, 3-DD, 3-EE, 3-FF, 3-GG, 3-HH, 3-II, 3-JJ, 3-KK, 3-LL, 3-MM, 3-NN,
3-OO, 3-PP, 3-QQ, 3-RR, 3-SS, 3-TT, 3-UU, 3-VV, 3-WW, 3-XX, and 3-YY were
considered in one motion.
Upon motion of Mr. Hunt, second by Ms. Schneider, vote carried by roll-call,
with all votes yea, to approve Turner-Kiewit Joint Venture to issue a
Subcontract Modification to Gulf Mechanical Contractors, LLC on BP-S00150,
South Terminal C, Phase 1 - Parking Facility - Phase 1 (GMP No. 9-S), for the
total lump sum amount of $2,588.00, with funding from Customer Facility Charges
and General Airport Revenue Bonds.
II. Subcontractor Modifications for BP-S00151 (GMP No. 9-S.1) with MSE2, Inc. dba
Mader Southeast for CR0720.1-9S.1-PKG-RFIs 3417-3417.2 - Elevators 3 and 4
Firestop Seal (CWA BP-151-003). Mr. Corthell presented the memorandum,
requesting approval for Turner-Kiewit Joint Venture (TKJV) to issue Subcontract
Modifications on BP-S00151, South Terminal C, Phase 1 - Parking Facility Phase
2 (GMP No. 9-S.1), at the Orlando International Airport, in the total amount
Minutes of the Construction Committee Meeting, May 26, 2020
Page 40 of 59
of $26,264.00 to MSE2, Inc. dba Mader Southeast for CR0720.1-9S.1-PKG-RFIs
3417-3417.2 - Elevators 3 and 4 Firestop Seal (CWA BP-151-003). Bid Packages
9.1.0 "Drywall, Stucco and Insulation" and 9.2.1 "Acoustical Ceilings" were
previously awarded within GMP No. 9-S.1 to MSE2, Inc. dba Mader Southeast, CC
No. 20180911.004.
TKJV is proposing a subcontract modification to MSE2, Inc. dba Mader Southeast
in the lump sum amount of $26,264.00 for CR0720.1-9S.1-PKG-RFI 3417-3417.2-
Elevator 3 and 4 Firestop Seal. As a result of value engineering in PKG
Bulletin 8, the elevator lobby wall finishes at elevator fronts changed from
tiles to stucco at PKG Elevator Cores 3 and 4. The elevator door frames had
already been procured at the time Bulletin 8 was issued. The door frames are
smaller than the concrete openings at the elevator fronts. RFIs 3417 and
3417.2 confirmed the use of the Hilti Engineering Judgement firestop detail
to seal off the 2-hour rating where the elevator door frames are smaller than
the concrete openings at the elevators fronts of Cores 3 and 4. RFI 3417.1
confirmed the revised details addressing concerns related to the fire-rated
door and the conduit running through the firestopping system. The modified
scope of work consists of all material and labor to continue the fire rating
from the concrete wall to the fire-rated elevator door frame per responses to
RFIs 3417-3417.2.
The approval of this subcontract modification to MSE2, Inc. dba Mader Southeast
resolves all requests for cost and time associated with RFIs 3417-3417.2 and
closes CWA BP-151-003. There will be no forthcoming CRs associated with RFIs
34173417.2.
TKJV has submitted documentation including the subcontractor's proposal to
support their request. An independent cost estimate is included. By approving
this request, the Owner does not waive its right to enforce the contract
requirements for other requests for cost or time.
The effect of these Subcontractor Modifications for this project is as follows:
TKJV to issue subcontract modification to MSE2, Inc. dba
Mader Southeast in the lump sum amount of: $ 26,264.00
Deduct from Owner Contingency: $ (26,264.00)
Turner-Kiewit Joint Venture is committed to 20% MWBE and 4% LDB participation
for Construction Services. The subcontractor identified and committed to
participate on BP-S00151 (GMP No. 9-S.1) for this subcontract modification is
MSE2, Inc. dba Mader Southeast (Non-MWBE/LDB/VBE). There is no small business
participation associated with this modification.
Agenda Item Nos. 3-A, 3-B, 3-C, 3-D, 3-E, 3-F, 3-G, 3-H, 3-I, 3-J, 3-K, 3-L,
3-M, 3-N, 3-O, 3-P, 3-Q, 3-R, 3-S, 3-T, 3-U, 3-V, 3-W, 3-X, 3-Y, 3-Z, 3-AA,
3-BB, 3-CC, 3-DD, 3-EE, 3-FF, 3-GG, 3-HH, 3-II, 3-JJ, 3-KK, 3-LL, 3-MM, 3-NN,
3-OO, 3-PP, 3-QQ, 3-RR, 3-SS, 3-TT, 3-UU, 3-VV, 3-WW, 3-XX, and 3-YY were
considered in one motion.
Upon motion of Mr. Hunt, second by Ms. Schneider, vote carried by roll-call,
with all votes yea, to approve Turner-Kiewit Joint Venture to issue
Subcontractor Modifications to MSE2, Inc. dba Mader Southeast on BP-S00151,
South Terminal C, Phase 1 - Parking Facility Phase 2 (GMP No. 9-S.1), for the
total lump sum amount of $26,264.00, with funding from Customer Facility
Charges and General Airport Revenue Bonds.
Minutes of the Construction Committee Meeting, May 26, 2020
Page 41 of 59
JJ. Subcontractor Modifications for BP-S00151 (GMP No. 9-S.1) with MSE2, Inc. dba
Mader Southeast for CR0720-9S.1-PKG-RFIs 3074.1-3074.3, 3660 and 3782 - Drywall
and Stucco (CWA BP-S00151-002). Mr. Corthell presented the memorandum,
requesting approval for Turner-Kiewit Joint Venture (TKJV) to issue Subcontract
Modifications on BP-S00151, South Terminal C, Phase 1 - Parking Facility Phase
2 (GMP No. 9-S.1), at the Orlando International Airport, in the total amount
of $46,430.00 to MSE2, Inc. dba Mader Southeast for CR0720-9S.1-PKG-RFIs
3074.1-3074.3, 3660 and 3782 - Drywall and Stucco (CWA BP-S00151-002). Bid
Packages 9.1.0 "Drywall, Stucco and Insulation" and 9.2.1 "Acoustical Ceilings"
were previously awarded within GMP No. 9-S.1 to MSE2, Inc. dba Mader Southeast,
CC No. 20180911.004.
RFI 3074-3074.3:
TKJV is proposing a subcontract modification to MSE2, Inc. dba Mader Southeast
in the lump sum amount of $12,891.00 from Owner Contingency for CR0720-9S.1-
PKG-RFIs 3074.1-3074.3, 3660 and 3782 - Drywall and Stucco. RFI 3074.1 was
issued to request direction for the exposed pipes inside the lobby. The RFI
response revised Drawing A9.01.08 showing the location of the new wall 2-hour
rated shaft wall. RFI 3074.2 was issued to confirm a 3-5/8-inch structural
wall in front of the non-structural G13 shaft wall to comply with wind load
requirements. RFI 3074.3 confirmed additional non-fire rated structural
ceiling in order to achieve appropriate support to the walls given the setup
approved in RFI 3074.2. The modified scope of work consists of all material,
labor and equipment to install a shaft wall exterior wall at the SW corner of
Elevator 4 Level 1 to enclose the mechanical chase and non-fire rated
structural ceiling per RFI 3074 series responses.
RFI 3660:
TKJV is proposing a subcontract modification to MSE2, Inc. dba Mader Southeast
in the lump sum amount of $28,110.00 from Owner Contingency for CR0720-9S.1-
PKG-RFIs 3074.1-3074.3, 3660 and 3782 - Drywall and Stucco. RFI 3660 confirmed
that stucco was needed at the locations shown on the photos of each elevation
inside Core 4 lobby of Levels 2, 3, 4, 5, and 6. The RFI also confirmed
Sketch 1 to address stucco slopes for the areas that are exposed to non-wind
driven and wind driven areas. The modified scope of work consists of all
labor, material and equipment to add stucco on the CMU interior walls and for
the stucco sloped at top of all furred walls in elevator lobbies Levels 1 to
6, Core 4 frame at CMU locations.
RFI 3782:
TKJV is proposing a subcontract modification to MSE2, Inc. dba Mader Southeast
in the lump sum amount of $5,429.00 from CMAR contingency for CR0720-9S.1-PKG-
RFIs 3074.1-3074.3, 3660 and 3782 - Drywall and Stucco. RFI 3782 was issued
to confirm the installation of 6-inch framed wall in lieu of CMU walls,
Level 6 Core 4 on the north and south ends of the elevator lobby. The modified
scope of work consists of material, labor and equipment to install the
Level 6 Core 4 frame walls at CMU locations. The credit for the CMU wall was
included in CR 0948, CCM No. 20200331.02Q.
The approval of these subcontract modifications to MSE2, Inc. dba Mader
Southeast resolves all requests for cost and time associated with RFIS 3074
Series and 3660. This request also resolves all cost and time for the Drywall
scope in RFI 3782 and closes CWA BP-S00151-002. A CR associated with RFI 3782
CMU scope credit was submitted in CR0948, CC No. 20200331.02Q.
TKJV has submitted documentation including the subcontractor's proposal to
support their request. An independent cost estimate is included. By approving
this request, the Owner does not waive its right to enforce the contract
requirements for other requests for cost or time.
Minutes of the Construction Committee Meeting, May 26, 2020
Page 42 of 59
The effect of these Subcontractor Modifications for this project is as follows:
TKJV to issue subcontract modification to MSE2, Inc. dba
Mader Southeast in the lump sum amount of: $ 46,430.00
Deduct from P1 CM@R Contingency: $ (5,429.00)
Deduct from P1 Owner Contingency: $ (41,001.00)
Turner-Kiewit Joint Venture is committed to 20% MWBE and 4% LDB participation
for Construction Services. The subcontractor identified and committed to
participate on BP-S00151 (GMP No. 9-S.1) for this subcontract modification is
MSE2, Inc. dba Mader Southeast (Non-MWBE/LDB/VBE). There is 48.7% MWBE
participation associated with this modification.
Agenda Item Nos. 3-A, 3-B, 3-C, 3-D, 3-E, 3-F, 3-G, 3-H, 3-I, 3-J, 3-K, 3-L,
3-M, 3-N, 3-O, 3-P, 3-Q, 3-R, 3-S, 3-T, 3-U, 3-V, 3-W, 3-X, 3-Y, 3-Z, 3-AA,
3-BB, 3-CC, 3-DD, 3-EE, 3-FF, 3-GG, 3-HH, 3-II, 3-JJ, 3-KK, 3-LL, 3-MM, 3-NN,
3-OO, 3-PP, 3-QQ, 3-RR, 3-SS, 3-TT, 3-UU, 3-VV, 3-WW, 3-XX, and 3-YY were
considered in one motion.
Upon motion of Mr. Hunt, second by Ms. Schneider, vote carried by roll-call,
with all votes yea, to approve Turner-Kiewit Joint Venture to issue
Subcontractor Modifications to MSE2, Inc. dba Mader Southeast on BP-S00151,
South Terminal C, Phase 1 - Parking Facility Phase 2 (GMP No. 9-S.1), for the
total lump sum amount of $46,430.00, with funding from Customer Facility
Charges and General Airport Revenue Bonds.
KK. Subcontractor Modifications for BP-S00151 (GMP No. 9-S.1) with MSE2, Inc. dba
Mader Southeast for CR1019-9S.1-PKG-RFI 4092 - Insulation in lieu of Soffits-
Credit. Mr. Corthell presented the memorandum, requesting approval for Turner-
Kiewit Joint Venture (TKJV) to issue Subcontract Modifications on BP-S00151,
South Terminal C, Phase 1 - Parking Facility Phase 2 (GMP No. 9-S.1), at the
Orlando International Airport, in the total deductive amount of ($4,549.00)
to MSE2, Inc. dba Mader Southeast for CR1019-9S.1-PKG-RFI 4092 - Insulation
in lieu of Soffits-Credit. Bid Packages 9.1.0 "Drywall, Stucco and Insulation"
and 9.2.1 "Acoustical Ceilings" were previously awarded within GMP No. 9-S.1
to MSE2, Inc. dba Mader Southeast, CC No. 20180911.004.
TKJV is proposing a subcontract modification to MSE2, Inc. dba Mader Southeast
in the total deductive lump sum amount of ($4,549.00) for CR1019-9S.1-PKG-RFI
4092 - Insulation in lieu of Soffits-Credit. RFI 1937 confirmed the location
of an accessible sump pit for the escalators added in PKG Bulletin 5 and
indicated fire protection was required in the aforementioned sump pits.
RFI 2332 series confirmed freeze protection and provided details for a new
soffit enclosure vertically to the ground to avoid potential issues associated
with installing a fire sprinkler line exposed in an unheated corridor. On
March 6, 2020, RFI 4092 was issued to request confirmation from the AOR for
an alternative solution to the one presented in RFI 2332.1 (i.e., the use of
1-inch thick foam glass with aluminum jacketing in lieu of soffit). This
request was based on TKJV indications that the available ceiling space and
height would not allow such installation. On March 16, 2020, the AOR made a
field visit on which it was captured that insulation had been completed on the
fire sprinkler piping along the south and east walls of the ground Elevator 4
lobby and the wet-pipe piping between the ground level tenant IDF and pit, and
that the assembly did not appear to have used an aluminum jacket as noted in
the RFI. The AOR confirmed as acceptable the use of wrap insulation in lieu
of soffits, and a credit was requested for the elimination of the soffit as
the soffit had not been installed. The modified scope of work consists of a
credit for material, labor and equipment associated with the removed soffits
Minutes of the Construction Committee Meeting, May 26, 2020
Page 43 of 59
on Level 1 corridor at the freeze line as was indicated in previous RFIs 2332-
2332.1 response.
The approval of this subcontract modification to MSE2, Inc. dba Mader Southeast
resolves all requests for cost and time associated with RFI 4092 for GMP No.
9-S.1. Costs for the insulation in RFI 4092 will be submitted in CR 1019.1
in GMP No. 9-S.
TKJV has submitted documentation including the subcontractor's proposal to
support their request. An independent cost estimate is included. By approving
this request, the Owner does not waive its right to enforce the contract
requirements for other requests for cost or time.
The effect of these Subcontractor Modifications for this project is as follows:
TKJV to issue subcontract modification to MSE2, Inc. dba
Mader Southeast in the deductive lump sum amount of: $ (4,549.00)
Add to Owner Contingency: $ 4,549.00
Turner-Kiewit Joint Venture is committed to 20% MWBE and 4% LDB participation
for Construction Services. The subcontractor identified and committed to
participate on BP-S00151 (GMP No. 9-S.1) for this subcontract modification is
MSE2, Inc. dba Mader Southeast (Non-MWBE/LDB/VBE). There is no MWBE, LDB or
VBE participation associated with this modification.
Agenda Item Nos. 3-A, 3-B, 3-C, 3-D, 3-E, 3-F, 3-G, 3-H, 3-I, 3-J, 3-K, 3-L,
3-M, 3-N, 3-O, 3-P, 3-Q, 3-R, 3-S, 3-T, 3-U, 3-V, 3-W, 3-X, 3-Y, 3-Z, 3-AA,
3-BB, 3-CC, 3-DD, 3-EE, 3-FF, 3-GG, 3-HH, 3-II, 3-JJ, 3-KK, 3-LL, 3-MM, 3-NN,
3-OO, 3-PP, 3-QQ, 3-RR, 3-SS, 3-TT, 3-UU, 3-VV, 3-WW, 3-XX, and 3-YY were
considered in one motion.
Upon motion of Mr. Hunt, second by Ms. Schneider, vote carried by roll-call,
with all votes yea, to approve Turner-Kiewit Joint Venture to issue
Subcontractor Modifications to MSE2, Inc. dba Mader Southeast on BP-S00151,
South Terminal C, Phase 1 - Parking Facility Phase 2 (GMP No. 9-S.1), for the
total deductive lump sum amount of ($4,549.00), with funding credited to
Customer Facility Charges and General Airport Revenue Bonds.
LL. Subcontractor Modifications for BP-S00151 (GMP No. 9-S.1) with Taylor, Cotton
& Ridley, Inc. for CR0776-PKG-RFI 2690-Additional Access Control - Hardware
Changes (CWA BP-S00151-004). Mr. Corthell presented the memorandum, requesting
approval for Turner-Kiewit Joint Venture (TKJV) to issue Subcontract
Modifications on BP-S00151, South Terminal C, Phase 1 - Parking Facility Phase
2 (GMP No. 9-S.1), at the Orlando International Airport, in the total amount
of $7,313.00 to Taylor, Cotton & Ridley, Inc. for CR0776-PKG-RFI 2690-
Additional Access Control - Hardware Changes (CWA BP-S00151-004). Bid Packages
8.0.0 "Doors, Frames and Hardware" was previously awarded within GMP No. 9-
S.1 to Taylor, Cotton & Ridley, Inc., CC No. 20180911.004.
TKJV is proposing a subcontract modification to Taylor, Cotton & Ridley, Inc.
in the total lump sum amount of $7,313.00 for CR0776-PKG-RFI 2690-Additional
Access Control - Hardware Changes (CWA BP-S00151-004). RFI 2690 was issued to
confirm additional access control at various doors in the Parking Garage and
the response updated the garage floor plans and PACS schedule. The modified
scope of work consists of all material and labor costs for hardware changes
to Openings 01-1833, 02-2374, 03-3511, 05-5374, 05-5511 and 01-1834.
Minutes of the Construction Committee Meeting, May 26, 2020
Page 44 of 59
The approval of this subcontract modification to Taylor, Cotton & Ridley, Inc.
resolves all requests for cost and time associated with RFI 2690 for GMP
No. 9-S.1 and closes CWA BP-S00151-004. Costs for low voltage were approved
in CR0430.1, CC No. 20200218.03R
TKJV has submitted documentation including the subcontractor's proposal to
support their request. An independent cost estimate is included. By approving
this request, the Owner does not waive its right to enforce the contract
requirements for other requests for cost or time.
The effect of these Subcontractor Modifications for this project is as follows:
TKJV to issue subcontract modification to Taylor, Cotton
& Ridley, Inc. in the lump sum amount of: $ 7,313.00
Deduct from Owner Contingency: $ (7,313.00)
Turner-Kiewit Joint Venture is committed to 20% MWBE and 4% LDB participation
for Construction Services. The subcontractor identified and committed to
participate on BP-S00151 (GMP No. 9-S.1) for this subcontract modification is
Taylor, Cotton & Ridley, Inc. (Non-MWBE/LDB/VBE). There is no small business
participation associated with this modification.
Agenda Item Nos. 3-A, 3-B, 3-C, 3-D, 3-E, 3-F, 3-G, 3-H, 3-I, 3-J, 3-K, 3-L,
3-M, 3-N, 3-O, 3-P, 3-Q, 3-R, 3-S, 3-T, 3-U, 3-V, 3-W, 3-X, 3-Y, 3-Z, 3-AA,
3-BB, 3-CC, 3-DD, 3-EE, 3-FF, 3-GG, 3-HH, 3-II, 3-JJ, 3-KK, 3-LL, 3-MM, 3-NN,
3-OO, 3-PP, 3-QQ, 3-RR, 3-SS, 3-TT, 3-UU, 3-VV, 3-WW, 3-XX, and 3-YY were
considered in one motion.
Upon motion of Mr. Hunt, second by Ms. Schneider, vote carried by roll-call,
with all votes yea, to approve Turner-Kiewit Joint Venture to issue
Subcontractor Modifications to Taylor, Cotton & Ridley, Inc. on BP-S00151,
South Terminal C, Phase 1 - Parking Facility Phase 2 (GMP No. 9-S.1), for the
total lump sum amount of $7,313.00, with funding from Customer Facility Charges
and General Airport Revenue Bonds.
MM. Subcontractor Modifications for BP-S00151 (GMP No. 9-S.1) with Morton Electric,
Inc. for CR1032-PKG-Removal of DAS System. Mr. Corthell presented the
memorandum, requesting approval for Turner-Kiewit Joint Venture (TKJV) to
issue Subcontract Modifications on BP-S00151, South Terminal C, Phase 1 -
Parking Facility Phase 2 (GMP No. 9-S.1), at the Orlando International Airport,
in the total deductive amount of ($37,297.00) to Morton Electric, Inc. for
CR1032-PKG-Removal of DAS System. "DAS Antenna Locations and Raceways Level
1 to 5-inch was previously awarded via CR 0637 to Morton Electric, Inc., CC
No. 20200204.002Q.
TKJV is proposing a subcontract modification to Morton Electric, Inc. in the
total deductive lump sum amount of ($37,297.00) for CR1032-PKG-Removal of DAS
System. In order to get the Parking Garage Temporary Certificate of Occupancy
(TCO) in Area 4 on March 27, 2020, the project had to conduct radio signal
testing because the new DAS system/extension was not yet complete. The Radio
Frequency study data revealed that the 800 MHz signal levels in the Terminal
C Parking Garage Area 4 met the minimum signal strength of -95 dbm or better
in 90-percent Areas of the building. The results concluded that no public
safety enhancement system was required to meet the City of Orlando
requirements. A portion of the materials and labor in the previously approved
CR0637 had already been provided when the radio signal testing occurred, and
thus the modified scope of work consists of a credit for the remaining scope
Minutes of the Construction Committee Meeting, May 26, 2020
Page 45 of 59
of CR0637 not performed due to the removal of the DAS system resulting from
the conducted study.
The approval of this subcontract modification to Morton Electric, Inc. resolves
all requests for costs and time for CR1032-PKG-Removal of DAS System.
TKJV has submitted documentation including the subcontractor's proposal to
support their request. An independent cost estimate is included. By approving
this request, the Owner does not waive its right to enforce the contract
requirements for other requests for cost or time.
The effect of these Subcontractor Modifications for this project is as follows:
TKJV to issue subcontract modification to Morton
Electric, Inc. in the deductive lump sum amount of: $ (37,297.00)
Add to P1 Owner Contingency: $ 37,297.00
Turner-Kiewit Joint Venture is committed to 20% MWBE and 4% LDB participation
for Construction Services. The subcontractor identified and committed to
participate on BP-S00151 (GMP No. 9-S.1) for this subcontract modification is
Morton Electric, Inc. (Non-MWBE/LDB/VBE). There is no small business
participation associated with this modification.
Agenda Item Nos. 3-A, 3-B, 3-C, 3-D, 3-E, 3-F, 3-G, 3-H, 3-I, 3-J, 3-K, 3-L,
3-M, 3-N, 3-O, 3-P, 3-Q, 3-R, 3-S, 3-T, 3-U, 3-V, 3-W, 3-X, 3-Y, 3-Z, 3-AA,
3-BB, 3-CC, 3-DD, 3-EE, 3-FF, 3-GG, 3-HH, 3-II, 3-JJ, 3-KK, 3-LL, 3-MM, 3-NN,
3-OO, 3-PP, 3-QQ, 3-RR, 3-SS, 3-TT, 3-UU, 3-VV, 3-WW, 3-XX, and 3-YY were
considered in one motion.
Upon motion of Mr. Hunt, second by Ms. Schneider, vote carried by roll-call,
with all votes yea, to approve Turner-Kiewit Joint Venture to issue
Subcontractor Modifications to Morton Electric, Inc. on BP-S00151, South
Terminal C, Phase 1 - Parking Facility Phase 2 (GMP No. 9-S.1), for the total
deductive lump sum amount of ($37,297.00), with funding credited to Customer
Facility Charges and General Airport Revenue Bonds.
NN. Subcontract Modification for BP-S00156 (GMP No. 14-S) with Skybuilders USA,
LLC for CR0392.2-CEP - Bulletin 12 Stucco Changes. Mr. Corthell presented the
memorandum, requesting approval for Turner-Kiewit Joint Venture (TKJV) to
issue a Subcontract Modification on BP-S00156, South Terminal C, Phase 1 - CEP
and EPG Buildings (GMP No. 14-S), at the Orlando International Airport, in the
total deductive amount of ($3,920.00) to Skybuilders USA, LLC for CR0392.2-
CEP - Bulletin 12 Stucco Changes. Bid Package 9.2.0 "Stucco" was previously
awarded within GMP No. 14-S to Skybuilders USA, LLC, CC No. 20180807.011.
TKJV is proposing a subcontract modification to Skybuilders USA, LLC in the
total deductive lump sum amount of ($3,920.00) for CR0392.2-CEP - Bulletin 12
Stucco Changes. The scope of work includes credits for the revised stucco
system from striated stucco to smooth stucco, per CEP Bulletin 12.
The approval of this subcontract modification to Skybuilders USA, LLC resolves
all requests for cost and time associated with CEP Bulletin 12 Stucco scope
of work. Cost impacts to GMP No. 14-S for the Structural Steel scope were
approved at CC No. 20190709.02J. Cost impacts to GMP No. 14-S.1 for the
Electrical scope were approved at CC No. 20190910.02E. There will be no
forthcoming CRs associated with CEP Bulletin 12.
Minutes of the Construction Committee Meeting, May 26, 2020
Page 46 of 59
TKJV has submitted documentation including the subcontractor's proposal to
support their request. An independent cost estimate is included. By approving
this request, the Owner does not waive its right to enforce the contract
requirements for other requests for cost or time.
The effect of this Subcontract Modification for this project is as follows:
TKJV to issue a subcontract modification to Sky Builders
USA, LLC in the deductive lump sum amount of: $ (3,920.00)
Add to P1 Owner Contingency: $ 3,920.00
Turner-Kiewit Joint Venture is committed to 20% MWBE and 4% LDB participation
for Construction Services. The subcontractor identified and committed to
participate on BP-S00156 (GMP No. 14-S) for this subcontract modification is
Skybuilders USA, LLC (MWBE/LDB). There is a 100% reduction in LDB
participation associated with this modification.
Agenda Item Nos. 3-A, 3-B, 3-C, 3-D, 3-E, 3-F, 3-G, 3-H, 3-I, 3-J, 3-K, 3-L,
3-M, 3-N, 3-O, 3-P, 3-Q, 3-R, 3-S, 3-T, 3-U, 3-V, 3-W, 3-X, 3-Y, 3-Z, 3-AA,
3-BB, 3-CC, 3-DD, 3-EE, 3-FF, 3-GG, 3-HH, 3-II, 3-JJ, 3-KK, 3-LL, 3-MM, 3-NN,
3-OO, 3-PP, 3-QQ, 3-RR, 3-SS, 3-TT, 3-UU, 3-VV, 3-WW, 3-XX, and 3-YY were
considered in one motion.
Upon motion of Mr. Hunt, second by Ms. Schneider, vote carried by roll-call,
with all votes yea, to approve Turner-Kiewit Joint Venture to issue a
Subcontract Modification to Skybuilders USA, LLC on BP-S00156, South Terminal
C, Phase 1 - CEP and EPG Buildings (GMP No. 14-S), for the total deductive
lump sum amount of ($3,920.00), with funding credited to Passenger Facility
Charges and General Airport Revenue Bonds.
OO. Subcontract Modifications for BP-S00156 (GMP No. 14-S) with Hommes Masonry,
Inc. dba Toltec Construction; MULE Engineering & Construction, Inc.; Taylor
Cotton & Ridley, Inc.; and Florida Door Solutions, Inc. for CR0925-EPG-Bulletin
9-RFIs 2250 and 2283-CMU, Structural Steel and Door Changes. Mr. Corthell
presented the memorandum, requesting approval for Turner-Kiewit Joint Venture
(TKJV) to issue Subcontract Modifications on BP-S00156, South Terminal C,
Phase 1 - CEP and EPG Buildings (GMP No. 14-S), at the Orlando International
Airport, in the total deductive amount of ($1,753.00) to Hommes Masonry, Inc.
dba Toltec Construction; MULE Engineering & Construction, Inc.; Taylor, Cotton
& Ridley, Inc.; and Florida Door Solutions, Inc. for CR0925-EPG-Bulletin 9-
RFIs 2250 and 2283-CMU, Structural Steel and Door Changes. Bid Packages 4.0.0
"Masonry", 5.0.0 "Structural Steel and Misc. Metals", were previously awarded
within GMP No. 14-S, respectively, to Hommes Masonry, Inc. dba Toltec
Construction; and MULE Engineering & Construction, Inc., CC No. 20180807.011.
Bid package 9.0.0 "General Trades; Hollow Metal Doors, Frames and Hardware"
was previously awarded to Taylor, Cotton & Ridley, Inc. via CR0343, CC No.
20190423.03L Bid package 9.0.0 "General Trades; Overhead Coiling Doors" was
previously awarded to Florida Door Solutions, Inc. via CR0344, CC No.
20190507.02H
1. TKJV is proposing a subcontract modification to Hommes Masonry, Inc.
dba Toltec Construction in the deductive lump sum amount of ($3,384.00)
for CR0925-EPG-Bulletin 9-RFIs 2250 and 2283-CMU, Structural Steel and
Door Changes. The modified scope of work consists of a net credit for
the deletion of nine CIP beams (5-foot by 24-inch by 8-inch) on the
west wall, 69 SF of CMU wall and CIP Beam (8-foot 8-inch by 40-inch by
8-inch) was removed in Control Room 1015 as detailed on Sheet Al.12.01
and Sheet Sl.25.01 in result of EPG Bulletin 9 revisions.
Minutes of the Construction Committee Meeting, May 26, 2020
Page 47 of 59
2. TKJV is proposing a subcontract modification to MULE Engineering &
Construction, Inc. in the lump sum amount of $3,074.00 for CR0925-EPG-
Bulletin 9-RFIs 2250 and 2283-CMU, Structural Steel and Door Changes.
EPG Bulletin 9 revised structural steel to accommodate new stair landing
and tie-in details required for the extended CMU block wall. The
modified scope of work consists of additional materials, labor and
engineering required for tie-ins detailed on Sheet S5.00.09, El and C5
and revised stair landing per EPG Bulletin 9 revisions.
3. TKJV is proposing a subcontract modification to Taylor, Cotton & Ridley,
Inc. in the deductive lump sum amount of ($3,261.00) for CR0925-EPG-
Bulletin 9-RFIs 2250 and 2283-CMU, Structural Steel and Door Changes.
The modified scope of work consists of a credit for the deletion of
Type A3 Door 1006.
4. TKJV is proposing a subcontract modification to Florida Door Solutions,
Inc. in the lump sum amount of $1,818.00 for CR0925-EPG-Bulletin 9-
RFIs 2250 and 2283-CMU, Structural Steel and Door Changes. EPG
Bulletin 9 revised Door 1003B from a l0-foot 0-inch by l0-foot 0-inch
coiling door to a 12-foot 0-inch by 14-foot 0-inch coiling door. The
modified scope of work consists of a credit for the original door and
the added cost difference for the revised door.
The approval of these subcontract modifications to Hommes Masonry, Inc. dba
Toltec Construction; MULE Engineering & Construction, Inc.; Taylor, Cotton &
Ridley, Inc.; and Florida Door Solutions, Inc.; resolves all requests for
costs and time resulting from EPG Bulletin 9, RFIs 2250 and 2283. The following
is the status of all CRs associated with EPG Bulletin 9 that have been or will
be submitted: CR0925.1 - Electrical Scope "forthcoming"; CR0925.2 - Plumbing
Scope" forthcoming"; CR0927 - Diesel Fuel "forthcoming"; CR0933 - Concrete
Scope "approved", CC No. 20200505.02S.
TKJV has submitted documentation including the subcontractor's proposal to
support their request. An independent cost estimate is included. By approving
this request, the Owner does not waive its right to enforce the contract
requirements for other requests for cost or time.
The effect of these Subcontract Modifications for this project is as follows:
TKJV to issue a subcontract modification to Hommes Masonry,
Inc. dba Toltec Construction in the deductive lump sum
amount of: $ (3,384.00)
TKJV to issue a subcontract modification to MULE
Engineering & Construction, Inc. in the lump sum amount of: $ 3,074.00
TKJV to issue a subcontract modification to Taylor, Cotton
& Ridley, Inc.; and Florida Door Solutions, Inc.; in the
deductive lump sum amount of: $ (3,261.00)
TKJV to issue a subcontract modification to Florida Door
Solutions, Inc. in the lump sum amount of: $ 1,818.00
Add to P1 EPG Owner Contingency: $ 1,753.00
Turner-Kiewit Joint Venture is committed to 20% MWBE and 4% LDB participation
for Construction Services. The subcontractor identified and committed to
participate on BP-S00156 (GMP No. 14-S) for these subcontract modifications
are as follows: Hommes Masonry, Inc. dba Toltec Construction (MWBE); MULE
Engineering & Construction, Inc. (MWBE/LDB); Taylor, Cotton & Ridley, Inc.
(Non-MWBE/LDB); and, Florida Door Solutions, Inc. (Non-MWBE/LDB). Hommes
Masonry, Inc. dba Toltec Construction's subcontract modification reduces its
MWBE participation by ($3,384.00). MULE Engineering & Construction, Inc.'s
Minutes of the Construction Committee Meeting, May 26, 2020
Page 48 of 59
subcontract modification results in an addition of $187.00 to its LDB
participation. Taylor, Cotton & Ridley, Inc.'s subcontract modification does
not have any impact on the small business participation. Florida Door
Solutions, Inc.'s subcontract modification does not have any impact on the
small business participation.
Agenda Item Nos. 3-A, 3-B, 3-C, 3-D, 3-E, 3-F, 3-G, 3-H, 3-I, 3-J, 3-K, 3-L,
3-M, 3-N, 3-O, 3-P, 3-Q, 3-R, 3-S, 3-T, 3-U, 3-V, 3-W, 3-X, 3-Y, 3-Z, 3-AA,
3-BB, 3-CC, 3-DD, 3-EE, 3-FF, 3-GG, 3-HH, 3-II, 3-JJ, 3-KK, 3-LL, 3-MM, 3-NN,
3-OO, 3-PP, 3-QQ, 3-RR, 3-SS, 3-TT, 3-UU, 3-VV, 3-WW, 3-XX, and 3-YY were
considered in one motion.
Upon motion of Mr. Hunt, second by Ms. Schneider, vote carried by roll-call,
with all votes yea, to approve Turner-Kiewit Joint Venture to issue Subcontract
Modifications on BP-S00156, South Terminal C, Phase 1 - CEP and EPG Buildings
(GMP No. 14-S), for the total deductive lump sum amount of ($1,753.00), which
includes the deductive lump sum amount of ($3,384.00) to Hommes Masonry, Inc.
dba Toltec Construction; the lump sum amount of $3,074.00 to MULE Engineering
& Construction, Inc.; the deductive lump sum amount of ($3,261.00) to Taylor,
Cotton & Ridley, Inc.; and the lump sum amount of $1,818.00 to Florida Door
Solutions, Inc.; with funding from Passenger Facility Charges and General
Airport Revenue Bonds.
PP. Subcontract Modification for BP-S00156 (GMP No. 14-S) with Hommes Masonry,
Inc. dba Toltec Construction for CR1044-CEP-Concrete Pads at Water Treatment
Room. Mr. Corthell presented the memorandum, requesting approval for Turner-
Kiewit Joint Venture (TKJV) to issue a Subcontract Modification on BP-S00156,
South Terminal C, Phase 1 - CEP and EPG Buildings (GMP No. 14-S), at the
Orlando International Airport, in the total amount of $1,983.00 to Hommes
Masonry, Inc. dba Toltec Construction for CR1044-CEP-Concrete Pads at Water
Treatment Room. Bid Package 4.0.0 "Masonry" was previously awarded within GMP
No. 14-S to Hommes Masonry, Inc. dba Toltec Construction, CC No. 20180807.011.
TKJV is proposing a subcontract modification to Hommes Masonry, Inc. dba Toltec
Construction in the total lump sum amount of $1,983.00 for CR1044-CEP-Concrete
Pads at Water Treatment Room. The scope of work includes the concrete
materials, labor and equipment for two concrete pads in the CEP Water Treatment
Room.
The approval of this subcontract modification to Hommes Masonry, Inc. dba
Toltec Construction resolves all requests for cost and time associated with
CR1044-CEP-Concrete Pads at Water Treatment Room.
TKJV has submitted documentation including the subcontractor's proposal to
support their request. An independent cost estimate is included. By approving
this request, the Owner does not waive its right to enforce the contract
requirements for other requests for cost or time.
The effect of this Subcontract Modification for this project is as follows:
GMP No. 14-S Line Item 23 current value: $ 74,175.00
TKJV to issue a subcontract modification to Hommes Masonry,
Inc. dba Toltec Construction in the lump sum amount of: $ 1,983.00
Deduct from P1 CMAR Contingency: $ (808.00)
Deduct from GMP No. 14 Line Item 23: $ (1,175.00)
GMP No. 14-S Line Item 23 remaining balance: $ 73,000.00
Turner-Kiewit Joint Venture is committed to 20% MWBE and 4% LDB participation
for Construction Services. The subcontractor identified and committed to
Minutes of the Construction Committee Meeting, May 26, 2020
Page 49 of 59
participate on BP-S00156 (GMP No. 14-S) for this subcontract modification is
Homes Masonry, Inc. dba Toltec Construction (MWBE). There is a 100% MWBE
participation associated with this modification.
Agenda Item Nos. 3-A, 3-B, 3-C, 3-D, 3-E, 3-F, 3-G, 3-H, 3-I, 3-J, 3-K, 3-L,
3-M, 3-N, 3-O, 3-P, 3-Q, 3-R, 3-S, 3-T, 3-U, 3-V, 3-W, 3-X, 3-Y, 3-Z, 3-AA,
3-BB, 3-CC, 3-DD, 3-EE, 3-FF, 3-GG, 3-HH, 3-II, 3-JJ, 3-KK, 3-LL, 3-MM, 3-NN,
3-OO, 3-PP, 3-QQ, 3-RR, 3-SS, 3-TT, 3-UU, 3-VV, 3-WW, 3-XX, and 3-YY were
considered in one motion.
Upon motion of Mr. Hunt, second by Ms. Schneider, vote carried by roll-call,
with all votes yea, to approve Turner-Kiewit Joint Venture to issue a
Subcontract Modification to Hommes Masonry, Inc. dba Toltec Construction on
BP-S00156, South Terminal C, Phase 1 - CEP and EPG Buildings (GMP No. 14-S),
for the total lump sum amount of $1,983.00, with funding from Passenger
Facility Charges and General Airport Revenue Bonds.
QQ. Subcontractor Modification for BP-S00168 (GMP No. 6-S.4) Percopo Coatings
Company, LLC for CR0570.2-6S4-RFI 2173 Hub Skylight Area Ceiling and CR0573.3-
6S4-RFI 2283 Added Door 01-4006B - Painting. Mr. Corthell presented the
memorandum, requesting approval for Hensel Phelps Construction (HPC) to issue
a Subcontract Modification on BP-S00168, South Terminal C, Phase 1 - Interior
Finishes and Specialties (GMP No. 6-S.4), at the Orlando International Airport,
in the total amount of $25,530.00 to Percopo Coatings Company, LLC, for
CR0570.2-6S4-RFI 2173 Hub Skylight Area Ceiling and CR0573.3-6S4-RFI 2283
Added Door 01-4006B - Painting. Bid Package for BP-S00168 09.11 "Painting"
has been previously awarded within GMP No. 6-S.4 to Percopo Coatings Company,
LLC, CC No. 20181002.010.
HPC is requesting to issue a Subcontractor Modification to Percopo Coatings
Company, LLC in the total Lump Sum amount of $25,530.00 for:
1. CR0570.2-6S.4-RFI 2173 Hub Skylight Area Ceiling - Painting: $25,319.00. ACU1 Acoustic Plaster and DF1 Textured Plaster finish were removed
entirely from the project through the Value Engineering process and
replaced with Level-4 drywall finish and paint only at the serenity room
and boarding gates, CC Nos. 20190709.02E, 20190709.02M and 20190716.02G
respectively, CR0276-6S.3 (Interior Plaster credit), CR0276-6S.4
(Painting Add), and CR0276-6S.2 (Framing and Drywall Add). There are
areas of ceiling outside the serenity room and boarding gates that
originally called for ACU1 or DF1 finish. RFI 2173 was written to
request information for the replacement ceiling finish in those areas.
The modified scope of work consists of the additional costs associated
with painting the drywall Level-4 finish in the Hub Skylight area
ceiling, per RFI 2173 response and sketches.
2. CR0573.3-6S4-RFI 2283 Added Door 01-4006B - Painting: $211.00. The
modified scope of work consists of the additional costs associated with
painting the added Hollow Metal (HM) Door 01-4006B and frame in Plants
Room 01-1124 on the Ramp Level Area 25, per RFI 2283 response.
The approval of this Subcontractor Modification to Percopo Coatings Company,
LLC resolves all requests for costs and time resulting from RFI 2173 for the
Painting scope of work in GMP No. 6-S.4. Costs for RFI 2173 in GMP No. 6-S.2
for the Drywall finish scope of work will be submitted via CR0570.1-6S2 for a
future CCM approval. The approval of this subcontractor modification also
resolves all requests for cost and time resulting from RFI 2283 for the
Painting scope of work in GMP No. 6-S.4. Costs for RFI 2283 in GMP Nos.
Minutes of the Construction Committee Meeting, May 26, 2020
Page 50 of 59
6-S.1 and 6-S.3 will be submitted via CR0573.1-6S1 and CR0573.2-6S3 for a
future CCM approval.
HPC has submitted documentation including the subcontractor's proposal to
support this request. An independent cost estimate is included. By approving
this request, the Owner does not waive its right to enforce the contract
requirements for other requests for cost or time.
The effect of this Subcontractor Modification for this project is as follows:
HPC to issue a subcontract modification to Percopo
Coatings Company, LLC in the lump sum amount of: $ 25,530.00
Deduct from P1 Owner Contingency $ (25,530.00)
Hensel Phelps Construction is committed to 20% MWBE and 4% LDB participation
for Construction Services. The subcontractor identified and committed to
participate on BP-S00168 (GMP No. 6-S.4) for this subcontract modification is
Percopo Coatings Company, LLC (Non-MWBE certified at the time of award of the
"Painting" Bid Package). There is no small business participation associated
with this modification.
Agenda Item Nos. 3-A, 3-B, 3-C, 3-D, 3-E, 3-F, 3-G, 3-H, 3-I, 3-J, 3-K, 3-L,
3-M, 3-N, 3-O, 3-P, 3-Q, 3-R, 3-S, 3-T, 3-U, 3-V, 3-W, 3-X, 3-Y, 3-Z, 3-AA,
3-BB, 3-CC, 3-DD, 3-EE, 3-FF, 3-GG, 3-HH, 3-II, 3-JJ, 3-KK, 3-LL, 3-MM, 3-NN,
3-OO, 3-PP, 3-QQ, 3-RR, 3-SS, 3-TT, 3-UU, 3-VV, 3-WW, 3-XX, and 3-YY were
considered in one motion.
Upon motion of Mr. Hunt, second by Ms. Schneider, vote carried by roll-call,
with all votes yea, to approve Hensel Phelps Construction to issue a
Subcontractor Modification to Percopo Coatings Company, LLC on BP-S00168,
South Terminal C, Phase 1 - Interior Finishes and Specialties (GMP No. 6-S.4),
for the total lump sum amount of $25,530.00, with funding from Passenger
Facility Charges and General Airport Revenue Bonds.
RR. Subcontractor Modification for BP-S00168 (GMP No. 6-S.4) M.C. Dean, Inc. for
CR0366-6S4-RFI 1474 Camera Interface Box (CIB) Alternative. Mr. Corthell
presented the memorandum, requesting approval for Hensel Phelps Construction
(HPC) to issue a Subcontract Modification on BP-S00168, South Terminal C,
Phase 1 - Interior Finishes and Specialties (GMP No. 6-S.4), at the Orlando
International Airport, in the total deductive amount of ($76,878.00) to M.C.
Dean, Inc., for CR0366-6S4-RFI 1474 Camera Interface Box (CIB) Alternative.
Bid Package for BP-S00168 27.01 "Airside Concourse Low Voltage Systems" has
been previously awarded within GMP No. 6-S.4 to M. C. Dean, Inc., CC No.
20181002.010.
HPC is requesting to issue a Subcontractor Modification to M.C. Dean, Inc. in
the total deductive Lump Sum amount of ($76,878.00) for CR0366-6S4-RFI 1474
Camera Interface Box (CIB) Alternative. The modified scope of work consists
of the credits associated with deleting the Camera Interface Boxes (CIB) and
replacing them with 4-11/16-inch deep square boxes in the Back-of-House (BOH)
or concealed locations, per RFI 1474 response and sketch.
The approval of this Subcontract Modification to M.C. Dean, Inc. resolves all
requests for cost and time resulting from RFI 1474.
HPC has submitted documentation including the subcontractor's proposal to
support this request. An independent cost estimate is included. By approving
this request, the Owner does not waive its right to enforce the contract
requirements for other requests for cost or time.
Minutes of the Construction Committee Meeting, May 26, 2020
Page 51 of 59
The effect of this Subcontractor Modification for this project is as follows:
HPC to issue a subcontract modification to M.C. Dean, Inc.
in the deductive lump sum amount of: $ (76,878.00)
Add to P1 Owner Contingency $ 76,878.00
Hensel Phelps Construction is committed to 20% MWBE and 4% LDB participation
for Construction Services. The subcontractor identified and committed to
participate on BP-S00168 (GMP No. 6-S.4) for this subcontract modification is
M.C. Dean, Inc. (Non-MWBE/LDB/VBE). There is 96.8% reduction in MWBE
participation associated with this modification.
Agenda Item Nos. 3-A, 3-B, 3-C, 3-D, 3-E, 3-F, 3-G, 3-H, 3-I, 3-J, 3-K, 3-L,
3-M, 3-N, 3-O, 3-P, 3-Q, 3-R, 3-S, 3-T, 3-U, 3-V, 3-W, 3-X, 3-Y, 3-Z, 3-AA,
3-BB, 3-CC, 3-DD, 3-EE, 3-FF, 3-GG, 3-HH, 3-II, 3-JJ, 3-KK, 3-LL, 3-MM, 3-NN,
3-OO, 3-PP, 3-QQ, 3-RR, 3-SS, 3-TT, 3-UU, 3-VV, 3-WW, 3-XX, and 3-YY were
considered in one motion.
Upon motion of Mr. Hunt, second by Ms. Schneider, vote carried by roll-call,
with all votes yea, to approve Hensel Phelps Construction to issue a
Subcontractor Modification to M.C. Dean, Inc. on BP-S00168, South Terminal C,
Phase 1 - Interior Finishes and Specialties (GMP No. 6-S.4), for the total
deductive lump sum amount of ($76,878.00), with funding credited to Passenger
Facility Charges and General Airport Revenue Bonds.
SS. Subcontractor Modification for BP-S00168 (GMP No. 6-S.4) M.C. Dean, Inc. for
CR0566.1-6S4-RFI 2352 Emergency Communication System (ECS) Fault Reporting
Confirmation. Mr. Corthell presented the memorandum, requesting approval for
Hensel Phelps Construction (HPC) to issue a Subcontract Modification on BP-
S00168, South Terminal C, Phase 1 - Interior Finishes and Specialties (GMP No.
6-S.4), at the Orlando International Airport, in the total deductive amount
of ($4,940.00) to M.C. Dean, Inc., for CR0566.1-6S4-RFI 2352 Emergency
Communication System (ECS) Fault Reporting Confirmation. Bid Package for
BP-S00168 27.01 "Airside Concourse Low Voltage Systems" has been previously
awarded within GMP No. 6-S.4 to M. C. Dean, Inc., CC No. 20181002.010.
HPC is requesting to issue a Subcontractor Modification to M. C. Dean, Inc.,
in the total deductive Lump Sum amount of ($4,940.00) for CR0566.1-6S4-RFI
2352 Emergency Communication System (ECS) Fault Reporting Confirmation. The
modified scope of work consists of the costs associated with the deletion of
the Fire Alarm Logic Relay 1522LR, per RFI 2352 response.
The approval of this Subcontractor Modification to M. C. Dean, Inc. resolves
all requests for costs and time resulting from RFI 2352 scope of work within
GMP No. 6-S.4. Impacts of RFI 2352 to GMP No. 6-S.6 will be submitted via
CR0566.2-6S.6. There are no cost or time impacts to GMP Nos. 6-S, 6-S.1,
6-S.2, 6-S.3, 6-S.5.
HPC has submitted documentation including the subcontractor's proposal to
support this request. An independent cost estimate is included. By approving
this request, the Owner does not waive its right to enforce the contract
requirements for other requests for cost or time.
The effect of this Subcontractor Modification for this project is as follows:
HPC to issue a subcontract modification to M.C. Dean, Inc.
in the deductive lump sum amount of: $ (4,940.00)
Add to P1 Owner Contingency $ 4,940.00
Minutes of the Construction Committee Meeting, May 26, 2020
Page 52 of 59
Hensel Phelps Construction is committed to 20% MWBE and 4% LDB participation
for Construction Services. The subcontractor identified and committed to
participate on BP-S00168 (GMP No. 6-S.4) for this subcontract modification is
M.C. Dean, Inc. (Non-MWBE/LDB/VBE). There is no small business participation
associated with this modification.
Agenda Item Nos. 3-A, 3-B, 3-C, 3-D, 3-E, 3-F, 3-G, 3-H, 3-I, 3-J, 3-K, 3-L,
3-M, 3-N, 3-O, 3-P, 3-Q, 3-R, 3-S, 3-T, 3-U, 3-V, 3-W, 3-X, 3-Y, 3-Z, 3-AA,
3-BB, 3-CC, 3-DD, 3-EE, 3-FF, 3-GG, 3-HH, 3-II, 3-JJ, 3-KK, 3-LL, 3-MM, 3-NN,
3-OO, 3-PP, 3-QQ, 3-RR, 3-SS, 3-TT, 3-UU, 3-VV, 3-WW, 3-XX, and 3-YY were
considered in one motion.
Upon motion of Mr. Hunt, second by Ms. Schneider, vote carried by roll-call,
with all votes yea, to approve Hensel Phelps Construction to issue a
Subcontractor Modification to M.C. Dean, Inc. on BP-S00168, South Terminal C,
Phase 1 - Interior Finishes and Specialties (GMP No. 6-S.4), for the total
deductive lump sum amount of ($4,940.00), with funding credited to Passenger
Facility Charges and General Airport Revenue Bonds.
TT. Subcontract Modification for BP-S00173 (GMP No. 7-S.3) with Kirlin Florida,
LLC for CR0755-LST-RFI 2665-Deletion of Natural Gas Piping. Mr. Corthell
presented the memorandum, requesting approval for Turner-Kiewit Joint Venture
(TKJV) to issue a Subcontract Modification on BP-S00173, South Terminal C,
Phase 1, Landside Terminal, MEP Systems - FDOT (GMP No. 7-S.3), at the Orlando
International Airport, in the total deductive amount of ($43,828.00) to Kirlin
Florida, LLC for CR0755-LST-RFI 2665-Deletion of Natural Gas Piping. Bid
Package BP 23.0.0 "Plumbing and HVAC" was previously awarded via CR0239 to
Kirlin Florida, LLC, CC No. 20190205.02H
TKJV is proposing a subcontract modification to Kirlin Florida, LLC in the
total deductive lump sum amount of ($43,828.00) for CR0755-LST-RFI 2665-
Deletion of Natural Gas Piping. LST Bulletin 12 previously deleted two natural
gas lines and a credit was given in that CR. The response to LST RFI 2665
confirmed that natural gas piping has been removed from the LST project. The
modified scope of work consists of credits associated with the deletion of the
four remaining natural gas lines shown on the plumbing sheets.
The approval of this subcontract modification to Kirlin Florida, LLC resolves
all requests for cost and time associated with RFI 2665 in GMP No. 7-S.3.
There are no cost impacts to GMP Nos. 7-S, 7-S.1, 7-S.2 and 7-S.4.
TKJV has submitted documentation including the subcontractor's proposal to
support their request. An independent cost estimate is included. By approving
this request, the Owner does not waive its right to enforce the contract
requirements for other requests for cost or time.
The effect of this Subcontract Modification for this project is as follows:
TKJV to issue a subcontract modification to Kirlin
Florida, LLC in the deductive lump sum amount of: $ (43,828.00)
Add to P1 Owner Contingency: $ 43,828.00
Due to the funding source of this GMP No. 7-S.3, Turner-Kiewit Joint Venture
proposed a 10% DBE participation goal for Construction Services, in lieu of
MWBE and LDB participation goals. As such, Turner-Kiewit Joint Venture’s
committed MWBE and LDB Construction Services goals are not affected by this
modification. The subcontractor identified and committed to participate on
BP-S00173 (GMP No. 7-S.3) for this subcontract modification is Kirlin Florida,
Minutes of the Construction Committee Meeting, May 26, 2020
Page 53 of 59
LLC (Non-MWBE/LDB/VBE). There is no DBE participation associated with this
modification.
Agenda Item Nos. 3-A, 3-B, 3-C, 3-D, 3-E, 3-F, 3-G, 3-H, 3-I, 3-J, 3-K, 3-L,
3-M, 3-N, 3-O, 3-P, 3-Q, 3-R, 3-S, 3-T, 3-U, 3-V, 3-W, 3-X, 3-Y, 3-Z, 3-AA,
3-BB, 3-CC, 3-DD, 3-EE, 3-FF, 3-GG, 3-HH, 3-II, 3-JJ, 3-KK, 3-LL, 3-MM, 3-NN,
3-OO, 3-PP, 3-QQ, 3-RR, 3-SS, 3-TT, 3-UU, 3-VV, 3-WW, 3-XX, and 3-YY were
considered in one motion.
Upon motion of Mr. Hunt, second by Ms. Schneider, vote carried by roll-call,
with all votes yea, to approve Turner-Kiewit Joint Venture to issue a
Subcontract Modification to Kirlin Florida, LLC on BP-S00173, South Terminal
C, Phase 1, Landside Terminal, MEP Systems - FDOT (GMP No. 7-S.3), for the
deductive amount of ($43,828.00), with funding credited to Passenger Facility
Charges.
UU. Subcontractor Modification for BP-S00178 (GMP No. 19-S) with Kiewit
Infrastructure South Co. for CR0672.1-AFC-Asphalt Millings (Part II)(CWA BP-
S00178-002). Mr. Corthell presented the memorandum, requesting approval for
Turner-Kiewit Joint Venture (TKJV) to issue a Subcontract Modification on BP-
S00178, South Terminal C, Phase 1 - Airfield Civil (GMP No. 19-S), at the
Orlando International Airport, in the total amount of $59,102.00 to Kiewit
Infrastructure South Co. for CR0672.1-AFC-Asphalt Millings (Part II)(CWA BP-
S00178-002). Bid Package 34.0.1 "Site Electrical and Communications" was
previously awarded within GMP No. 19-S to Kiewit Infrastructure South Co., CC
No. 20190604.026.
TKJV is proposing a subcontract modification to Kiewit Infrastructure South
Co. in the total lump sum amount of $59,102.00 for CR0672.1-AFC-Asphalt
Millings (Part II), (CWA BP-S00178-002). GMP No. 19-S was procured with an
assumption that onsite milling materials would be available to the contractor
for use on crane pads, access road, pedestrian paths, and relocated laydown
yard. Due to an insufficient quantity of milling materials being available
onsite, the contractor had to purchase millings for the areas shown on the map
included in this package, for a total of 5,845 tons. CR0672 was submitted and
approved at CC No. 20200218.03AA for the cost of 2,908 tons of millings
material for crane pads, access road, and pedestrian paths. The modified
scope of work consists of all remaining costs associated with 2,937 tons of
asphalt milling RAP (Reclaimed Asphalt Pavement) for use on relocated HPC
laydown yard as tracked by the time and material (T&M) tickets.
The approval of this subcontract modification to Kiewit Infrastructure South
Co. resolves all requests for cost and time for the scope of work delineated
in CR0672.1-AFC-Asphalt Millings (Part II) (CWA BP-S00178-002) and closes CWA
BP-S00178-002.
TKJV has submitted documentation including the subcontractor's proposal to
support their request. An independent cost review is included. By approving
this request, the Owner does not waive its right to enforce the contract
requirements for other requests for cost or time.
The effect of this Subcontractor Modification for this project is as follows:
TKJV to issue a subcontract modification to Kiewit
Infrastructure South Co. in the lump sum amount of: $ 59,102.00
Deduct from P1X Owner Contingency: $ (59,102.00)
Turner-Kiewit Joint Venture is committed to 20% MWBE and 4% LDB participation
for Construction Services. The subcontractor identified and committed to
Minutes of the Construction Committee Meeting, May 26, 2020
Page 54 of 59
participate on BP-S00178 (GMP No. 19-S) for this subcontract modification is
Kiewit Infrastructure South Co. (Non-MWBE/LDB). There is 87% LDB participation
associated with this modification.
Ms. Sharman asked if this request takes into account any potential reductions
to the GMP. Mr. Corthell answered yes.
Agenda Item Nos. 3-A, 3-B, 3-C, 3-D, 3-E, 3-F, 3-G, 3-H, 3-I, 3-J, 3-K, 3-L,
3-M, 3-N, 3-O, 3-P, 3-Q, 3-R, 3-S, 3-T, 3-U, 3-V, 3-W, 3-X, 3-Y, 3-Z, 3-AA,
3-BB, 3-CC, 3-DD, 3-EE, 3-FF, 3-GG, 3-HH, 3-II, 3-JJ, 3-KK, 3-LL, 3-MM, 3-NN,
3-OO, 3-PP, 3-QQ, 3-RR, 3-SS, 3-TT, 3-UU, 3-VV, 3-WW, 3-XX, and 3-YY were
considered in one motion.
Upon motion of Mr. Hunt, second by Ms. Schneider, vote carried by roll-call,
with all votes yea, to approve Turner-Kiewit Joint Venture to issue a
Subcontractor Modification to Kiewit Infrastructure South, Co. on BP-S00178,
South Terminal C, Phase 1 - Airfield Civil (GMP No. 19-S), for the total lump
sum amount of $59,102.00, with funding from General Airport Revenue Bonds.
VV. Subcontractor Modification for BP-S00178 (GMP No. 19-S) with Kiewit
Infrastructure South Co. for CR0886-AFC-North Secure Road Permanent Lighting
(CWA No. BP-S00178-004). Mr. Corthell presented the memorandum, requesting
approval for Turner-Kiewit Joint Venture (TKJV) to issue a Subcontract
Modification on BP-S00178, South Terminal C, Phase 1 - Airfield Civil (GMP No.
19-S), at the Orlando International Airport, in the total amount of $9,114.00
to Kiewit Infrastructure South Co. for CR0886-AFC-North Secure Road Permanent
Lighting (CWA No. BP-S00178-004). Bid Package 34.10.1 "Site Electrical and
Communications" was previously awarded within GMP No. 19-S to Kiewit
Infrastructure South Co., CC No. 20190604.026.
TKJV is proposing a subcontract modification to Kiewit Infrastructure South
Co. in the total lump sum amount of $9,114.00 for CR0886-AFC-North Secure Road
Permanent Lighting (CWA No. BP-S00178-004). The Plan Sheet CE12.01.03 left
final design and routing of circuitry to the contractor to finalize and
included a note that circuit voltage, direction of feed and existing load
shall require onsite verification. There was work that could not have been
known at bid time inside the AOA in order to maintain lights along Jeff Fuqua
Boulevard, as well as Secure Road. Based on actual onsite conditions, the
contractor had to coordinate with the OAR and OUC to re-circuit the lighting
fixtures on the Secure Road to an alternate voltage source. The modified scope
of work consists of all labor, material and equipment costs associated with
installing 2-inch underground SCH40 PVC conduit, fittings and pull boxes for
OUC roadway lighting on Secure Road for AFC.
The approval of this subcontract modification to Kiewit Infrastructure South
Co. resolves all requests for cost and time for the scope of work delineated
in CR0886-AFC-North Secure Road Permanent Lighting (CWA No. BP-S00178-004) and
closes CWA No. BP-S00178-004.
TKJV has submitted documentation including the subcontractor's proposal to
support their request. An independent cost estimate is included. By approving
this request, the Owner does not waive its right to enforce the contract
requirements for other requests for cost or time.
The effect of this Subcontractor Modification for this project is as follows:
TKJV to issue a subcontract modification to Kiewit
Infrastructure South Co. in the lump sum amount of: $ 9,114.00
Deduct from P1 Owner Contingency: $ (9,114.00)
Minutes of the Construction Committee Meeting, May 26, 2020
Page 55 of 59
Turner-Kiewit Joint Venture is committed to 20% MWBE and 4% LDB participation
for Construction Services. The subcontractor identified and committed to
participate on BP-S00178 (GMP No. 19-S) for this subcontract modification is
Kiewit Infrastructure South Co. (Non-MWBE/LDB). There is 76.3% LDB
participation associated with this modification.
Agenda Item Nos. 3-A, 3-B, 3-C, 3-D, 3-E, 3-F, 3-G, 3-H, 3-I, 3-J, 3-K, 3-L,
3-M, 3-N, 3-O, 3-P, 3-Q, 3-R, 3-S, 3-T, 3-U, 3-V, 3-W, 3-X, 3-Y, 3-Z, 3-AA,
3-BB, 3-CC, 3-DD, 3-EE, 3-FF, 3-GG, 3-HH, 3-II, 3-JJ, 3-KK, 3-LL, 3-MM, 3-NN,
3-OO, 3-PP, 3-QQ, 3-RR, 3-SS, 3-TT, 3-UU, 3-VV, 3-WW, 3-XX, and 3-YY were
considered in one motion.
Upon motion of Mr. Hunt, second by Ms. Schneider, vote carried by roll-call,
with all votes yea, to approve Turner-Kiewit Joint Venture to issue a
Subcontractor Modification to Kiewit Infrastructure South, Co. on BP-S00178,
South Terminal C, Phase 1 - Airfield Civil (GMP No. 19-S), for the total lump
sum amount of $9,114.00, with funding from General Airport Revenue Bonds.
WW. Subcontractor Modification for BP-S00178 (GMP No. 19-S) with Kiewit
Infrastructure South Co. for CR0875-AFC-Sheet Pile Existing Transformer (CWA
BP-S00178-001). Mr. Corthell presented the memorandum, requesting approval
for Turner-Kiewit Joint Venture (TKJV) to issue a Subcontract Modification on
BP-S00178, South Terminal C, Phase 1 - Airfield Civil (GMP No. 19-S), at the
Orlando International Airport, in the total amount of $77,526.00 to Kiewit
Infrastructure South Co. for CR0875-AFC-Sheet Pile Existing Transformer (CWA
BP-S00178-001). Bid Package 34.10.1 "Site Electrical and Communications" was
previously awarded within GMP No. 19-S to Kiewit Infrastructure South Co., CC
No. 20190604.026.
TKJV is proposing a subcontract modification to Kiewit Infrastructure South
Co. in the total lump sum amount of $77,526.00 for CR0875-AFC-Sheet Pile
Existing Transformer. The modified scope of work consists of all labor,
material and equipment costs associated with installing sheet piling
44-foot L x 92-foot W in order to protect existing transformers that were too
close to P1X foundations, leaving it in place for two months, and then removing
the temporary sheet piling.
The approval of this subcontract modification to Kiewit Infrastructure South
Co. resolves all requests for cost and time associated with CR0875-AFC-Sheet
Pile Existing Transformer and closes (CWA BP-S00178-001).
TKJV has submitted documentation including the subcontractor's proposal to
support their request. An independent cost estimate is included. By approving
this request, the Owner does not waive its right to enforce the contract
requirements for other requests for cost or time.
The effect of this Subcontractor Modification for this project is as follows:
TKJV to issue a subcontract modification to Kiewit
Infrastructure South Co. in the lump sum amount of: $ 77,526.00
Deduct from P1X Owner Contingency: $ (77,526.00)
Turner-Kiewit Joint Venture is committed to 20% MWBE and 4% LDB participation
for Construction Services. The subcontractor identified and committed to
participate on BP-S00178 (GMP No. 19-S) for this subcontract modification is
Kiewit Infrastructure South Co. (Non-MWBE/LDB). There is no small business
participation associated with this modification.
Minutes of the Construction Committee Meeting, May 26, 2020
Page 56 of 59
Ms. Sharman asked if this request takes into account any potential reductions
to the GMP. Mr. Corthell answered yes.
Agenda Item Nos. 3-A, 3-B, 3-C, 3-D, 3-E, 3-F, 3-G, 3-H, 3-I, 3-J, 3-K, 3-L,
3-M, 3-N, 3-O, 3-P, 3-Q, 3-R, 3-S, 3-T, 3-U, 3-V, 3-W, 3-X, 3-Y, 3-Z, 3-AA,
3-BB, 3-CC, 3-DD, 3-EE, 3-FF, 3-GG, 3-HH, 3-II, 3-JJ, 3-KK, 3-LL, 3-MM, 3-NN,
3-OO, 3-PP, 3-QQ, 3-RR, 3-SS, 3-TT, 3-UU, 3-VV, 3-WW, 3-XX, and 3-YY were
considered in one motion.
Upon motion of Mr. Hunt, second by Ms. Schneider, vote carried by roll-call,
with all votes yea, to approve Turner-Kiewit Joint Venture to issue a
Subcontractor Modification to Kiewit Infrastructure South, Co. on BP-S00178,
South Terminal C, Phase 1 - Airfield Civil (GMP No. 19-S), for the total lump
sum amount of $77,526.00, with funding from General Airport Revenue Bonds.
XX. Subcontractor Modification for BP-S00179 (GMP No. 6-S.6) with M. C. Dean, Inc.
for CR0476.2-6S6-RFI 2067 Deletion of Blank Plates at Premise Distribution
System (PDS) Empty Cabinets. Mr. Corthell presented the memorandum, requesting
approval for Hensel Phelps Construction (HPC) to issue a Subcontract
Modification on BP-S00179, South Terminal C, Phase 1 - Airside Concourse (GMP
No. 6-S.6), at the Orlando International Airport, in the total deductive amount
of ($16,978.00) to M. C. Dean, Inc. for CR0476.2-6S6-RFI 2067 Deletion of
Blank Plates at Premise Distribution System (PDS) Empty Cabinets. Bid Package
for BP-S00179 27.01 "Airside Concourse Low Voltage Systems" has been previously
awarded within GMP No. 6-S.6 to M. C. Dean, Inc., CC No. 20191029.007.
HPC is requesting to issue a Subcontractor Modification to M. C. Dean, Inc.,
in the total deductive Lump Sum amount of ($16,978.00) for CR0476.2-6S6-RFI
2067 Deletion of Blank Plates at Premise Distribution System (PDS) Empty
Cabinets. The modified scope of work consists of the labor and material credits
associated with the deletion of the blank plate covers added in CWS Bulletin
007, Specification Section 27 10 00, Premise Distribution System, in all the
PDS empty cabinet spaces, per RFI 2067 response.
The approval of this Subcontractor Modification to M.C. Dean, Inc. resolves
all requests for costs and time resulting from RFI 2067 scope of work within
GMP No. 6-S.6. Impacts of RFI 2067 to GMP No. 6-S.4 were approved via CC No.
20200225.02U.
HPC has submitted documentation including the subcontractor's proposal to
support their request. An independent cost estimate is included. By approving
this request, the Owner does not waive its right to enforce the contract
requirements for other requests for costs or time.
The effect of this Subcontractor Modification for this project is as follows:
HPC to issue a subcontract modification to M. C. Dean,
Inc. in the deductive lump sum amount of: $ (16,978.00)
Add to Owner Contingency: $ 16,978.00
Due to the funding source of this GMP No. 6-S.6, Hensel Phelps Construction
proposed DBE participation goals per bid scope of work for Construction
Services. The subcontractor identified and committed to participate on BP-
S00179 (GMP No. 6-S.6) for this subcontract modification is M. C. Dean, Inc.
(Non-DBE/MWBE/LDB). There is a 100% reduction in DBE participation associated
with this modification.
Ms. Sharman stated that this BBC includes Phase 1 Expansion funding.
Minutes of the Construction Committee Meeting, May 26, 2020
Page 57 of 59
Ms. Sharman asked if this request takes into account any potential reductions
to the GMP. Mr. Corthell answered yes.
Agenda Item Nos. 3-A, 3-B, 3-C, 3-D, 3-E, 3-F, 3-G, 3-H, 3-I, 3-J, 3-K, 3-L,
3-M, 3-N, 3-O, 3-P, 3-Q, 3-R, 3-S, 3-T, 3-U, 3-V, 3-W, 3-X, 3-Y, 3-Z, 3-AA,
3-BB, 3-CC, 3-DD, 3-EE, 3-FF, 3-GG, 3-HH, 3-II, 3-JJ, 3-KK, 3-LL, 3-MM, 3-NN,
3-OO, 3-PP, 3-QQ, 3-RR, 3-SS, 3-TT, 3-UU, 3-VV, 3-WW, 3-XX, and 3-YY were
considered in one motion.
Upon motion of Mr. Hunt, second by Ms. Schneider, vote carried by roll-call,
with all votes yea, to approve Hensel Phelps Construction to issue a
Subcontractor Modification to M. C. Dean, Inc. on BP-S00179, South Terminal
C, Phase 1 - Airside Concourse (GMP No. 6-S.6), for the total deductive lump
sum amount of ($16,978.00), with funding credited to General Airport Revenue
Bonds and Passenger Facility Charges.
YY. Subcontractor Modification for BP-S00179 (GMP No. 6-S.6) with M. C. Dean, Inc.
for CR0566.2-6S.6-RFI 2352 Emergency Communication System (ECS] Fault
Reporting Confirmation. Mr. Corthell presented the memorandum, requesting
approval for Hensel Phelps Construction (HPC) to issue a Subcontract
Modification on BP-S00179, South Terminal C, Phase 1 - Airside Concourse (GMP
No. 6-S.6), at the Orlando International Airport, in the total deductive amount
of ($1,861.00) to M. C. Dean, Inc. for CR0566.2-6S.6-RFI 2352 Emergency
Communication System (ECS] Fault Reporting Confirmation. Bid Package for BP-
S00179 27.01 "Airside Concourse Low Voltage Systems" has been previously
awarded within GMP No. 6-S.6 to M. C. Dean, Inc., CC No. 20191029.007.
HPC is requesting to issue a Subcontractor Modification to M. C. Dean, Inc.
in the total deductive Lump Sum amount of ($1,861.00) for CR0566.2-6S.6-RFI
2352 Emergency Communication System (ECS) Fault Reporting Confirmation. The
modified scope of work consists of the costs associated with the deletion of
the Fire Alarm logic relay 1522LR, per RFI 2352 response.
The approval of this Subcontractor Modification to M. C. Dean, Inc. resolves
all requests for costs and time resulting from RFI 2352 scope of work within
GMP No. 6-S.6. Impacts of RFI 2352 to GMP No. 6-S.4 will be submitted via
CR0566.1-6S.4. There are no cost or time impacts to GMP Nos. 6-S, 6-S.1, 6-
S.2, 6-S.3, 6-S.5.
HPC has submitted documentation including the subcontractor's proposal to
support their request. An independent cost estimate is included. By approving
this request, the Owner does not waive its right to enforce the contract
requirements for other requests for costs or time.
The effect of this Subcontractor Modification for this project is as follows:
HPC to issue a subcontract modification to M. C. Dean,
Inc. in the deductive lump sum amount of: $ (1,861.00)
Add to Owner Contingency: $ 1,861.00
Due to the funding source of this GMP No. 6-S.6, Hensel Phelps Construction
proposed DBE participation goals per bid scope of work for Construction
Services. The subcontractor identified and committed to participate on BP-
S00179 (GMP No. 6-S.6) for this subcontract modification is M. C. Dean, Inc.
(Non-DBE/MWBE/LDB). There is no small business participation associated with
this modification.
Ms. Sharman asked if this request takes into account any potential reductions
to the GMP. Mr. Corthell answered yes.
Minutes of the Construction Committee Meeting, May 26, 2020
Page 58 of 59
Agenda Item Nos. 3-A, 3-B, 3-C, 3-D, 3-E, 3-F, 3-G, 3-H, 3-I, 3-J, 3-K, 3-L,
3-M, 3-N, 3-O, 3-P, 3-Q, 3-R, 3-S, 3-T, 3-U, 3-V, 3-W, 3-X, 3-Y, 3-Z, 3-AA,
3-BB, 3-CC, 3-DD, 3-EE, 3-FF, 3-GG, 3-HH, 3-II, 3-JJ, 3-KK, 3-LL, 3-MM, 3-NN,
3-OO, 3-PP, 3-QQ, 3-RR, 3-SS, 3-TT, 3-UU, 3-VV, 3-WW, 3-XX, and 3-YY were
considered in one motion.
Upon motion of Mr. Hunt, second by Ms. Schneider, vote carried by roll-call,
with all votes yea, to approve Hensel Phelps Construction to issue a
Subcontractor Modification to M. C. Dean, Inc. on BP-S00179, South Terminal
C, Phase 1 - Airside Concourse (GMP No. 6-S.6), for the total deductive lump
sum amount of ($1,861.00), with funding credited to Passenger Facility Charges
and General Airport Revenue Bonds.
ZZ. Subcontractor Modification for BP-S00179 (GMP No. 6-S.6) with Liberty Conshor,
LLC for CR0574-6S6-RFI 2133 Pile Caps and Adjoining Foundations.
This item was deferred.
GENERAL
REQUEST FOR RESCISSION OF PRIOR APPROVAL FOR PASSIVE OPTICAL LOCAL AREA NETWORK (POL)
TESTING OF TECHNOLOGY WITH WORLD WIDE TECHNOLOGY, LLC FOR W-00401, SELECTION OF
PASSIVE OPTICAL LOCAL AREA NETWORK (LAN) MANUFACTURER, AT THE ORLANDO INTERNATIONAL
AIRPORT.
4. Ms. Harvey presented the memorandum, dated May 26, 2020, to request for the
rescission of prior approval for Passive Optical Local Area Network (POL) Testing
of Technology with World Wide Technology, LLC for W-00401, Selection of Passive
Optical Local Area Network (LAN) Manufacturer, at the Orlando international Airport.
On September 5, 2019, the Construction Committee approved POL Testing of Technology
with World Wide Technology for the not-to-exceed amount of $20,493.84. Due to
irreconcilable contract term differences, instead of using World Wide Technology,
LLC’s facilities for the testing, the decision was made to utilize the Aviation
Authority’s Configuration Lab at HBJ Warehouse to complete this testing and
evaluation of the three shortlisted Proposers for W401, Selection of POL
Manufacturer, against specific operational requirements. Therefore, it is
respectfully requested that the previous Construction Committee approval to procure
testing services from World Wide Technology, LLC be rescinded.
The Office of Small Business Development has determined that the proposed request
to rescind prior approval to procure testing services from World Wide Technology,
LLC does not have any impact on the small business participation.
Upon motion of Ms. Sharman, second by Mr. Hunt, vote carried by roll-call, with all
votes yea, to approve the rescission of prior approval of Passive Optical Local Area
Network (POL) Testing of Technology with World Wide Technology, LLC for W-00401,
Selection of Passive Optical Local Area Network (LAN) Manufacturer, for the total
deductive amount of ($20,493.84), with funding credited to General Airport Revenue
Bonds.
INFORMATION ITEMS
5. The following items were presented for information only:
A. Field Change Order (FCO) Log
B. COVID-19 CCM Item Log
On WEDNESDAY, JUNE 3, 2020, the CONSTRUCTION COMMITTEE met in regular session
telephonically with the meeting live streamed on You Tube (www.OrlandoAirports.net).
Chairman Thornton called the meeting to order at 10:00 a.m. The meeting was posted
in accordance with Florida Statutes with a quorum participating. Office of the
Governor, Executive Order Number 20-69
Participating Committee members,
Stanley J. Thornton, Chairman
Kathleen Sharman, Chief Financial Officer
Mike Patterson, Director of Construction
Gary Hunt, Director of Maintenance
Denise Schneider, Assistant Director of Purchasing and Material Control
Also participating:
Davin Ruohomaki, GOAA Senior Director of Planning, Engineering, and Construction
Karen Ryan, Legal Counsel (Nelson Mullins Broad & Cassel)
Dan Carrington, GOAA Environmental
Scott Shedek, GOAA Construction
Alex Sorondo, HNTB Corporation
Ben Brown, A2 Group, Inc.
Chris Kieffer, A2 Group, Inc.
Don Corthell, PSA Management, Inc.
Tara Ciaglia, Recording Secretary
LOBBYIST DISCLOSURE
Parties present were reminded that for individuals who conduct lobbying activities
with Aviation Authority employees or Board members, registration with the Aviation
Authority is required each year prior to conducting any lobbying activities. A
statement of expenditures incurred in connection with those lobbying instances should
also be filed prior to April 1st of each year for the preceding year. As of January
16, 2013, lobbying any Aviation Authority Staff who are members of any committee
responsible for ranking Proposals, Letters of Interest, Statements of Qualifications
or Bids and thereafter forwarding those recommendations to the Board and/or Board
Members is prohibited from the time that a Request for Proposals, Request for Letters
of Interests, Request for Qualifications or Request for Bids is released to the time
that the Board makes an award. As adopted by the Board on September 19, 2012,
lobbyists are now required to sign-in at the Aviation Authority offices prior to any
meetings with Staff or Board members. In the event a lobbyist meets with or otherwise
communicates with Staff or a Board member at a location other than the Aviation
Authority offices, the lobbyist shall file a Notice of Lobbying (Form 4) detailing
each instance of lobbying to the Aviation Authority within 7 calendar days of such
lobbying. As of January 16, 2013, lobbyists will also provide a notice to the
Aviation Authority when meeting with the Mayor of the City of Orlando or the Mayor
of Orange County at their offices. The policy, forms, and instructions are available
in the Aviation Authority’s offices and the website. Please contact the Director
of Board Services with questions at (407) 825-2032.
ANNOUNCEMENT
Any appeals of decisions made by the Construction Committee must be filed with the
Chief Executive Officer within five business days (no later than 4:00 p.m. on the
fifth business day) of the rendering of that decision. If a bidder or proposer is
aggrieved by any of the proceedings of today’s meeting and wishes to appeal the
results of actions made by this committee, they must file an appeal stating the item
they wish to appeal and the basis for which they wish to appeal, and it must be
received in writing by the Chief Executive Officer, Mr. Phillip N. Brown, via email
[email protected], with a copy to [email protected] (emails will be accepted during the
COVID-19 pandemic.)
Minutes of the Construction Committee Meeting, June 3, 2020
Page 2 of 41
COVID-19 ANNOUNCEMENT
Due to COVID-19, the Aviation Authority is adhering to a business distancing
operational plan. Please note that all Construction Committee meetings from today
until further notice will be held telephonically. If you would like to speak at the
meeting on an agenda item being considered, please contact the Recording Secretary,
Tara Ciaglia ([email protected] -or- 407-825-4461) no less than 24 hours in
advance of the meeting. Otherwise, the Construction Committee will be available via
Live Stream at www.orlandoairports.net.
CHANGE ORDER AGENDA
1. The following Change Orders were presented for consideration:
A. Change Order BP-00482-04 VARIOUS REVISIONS. This change order to the contract with Carr & Collier Inc. for Gate E-50 and Checkpoint Charlie Development is
to: 1. Increase the Contract Time for Substantial Completion by 97 calendar
days, from 220 calendar days to 317 calendar days, for delays associated with
utility locates, delayed permit issuance, and City of Orlando inspection
rescheduling. ADD: $0.00; 2. Negotiated Settlement for project refinements to
provide all labor, materials, and equipment for: (a) Additional asphalt
pavement, Raised Pavement Markings (RPM), and flexible delineators in areas
originally designed to be non-asphalt paving, in accordance with design
drawings, provided at ‘Attachment B’; (b) Ten bollards to protect aboveground
equipment; (c) Install revised storm water system piping, structures,
flumes/dissipaters, and canopy roof-drain system, in accordance with design
drawings, provided at ‘Attachment B’; (d) Install a gate valve on the main
water lateral from Cargo Road; (e) Install 2,350 square yards of sod for
disturbed areas outside of the north project limits; (f) Implement improvements
to the electrical system, in accordance with design drawings, provided at
‘Attachment B’; (g) Install an nVent Erico Interceptor ESE i-series Lightning
Protection arrestor system to allow for continuous operation of the checkpoint
during inclement weather, in accordance with design drawings, provided at
‘Attachment B’; (h) Install an under cabinet water heater for the restroom and
janitor’s closet fixtures in accordance the City of Orlando permit comments;
and, (i) Install revised concrete canopy footings in accordance with the
delegated structural engineer’s design. This item completely resolves all cost
issues associated with the above adjustments. Contractor represents and
warrants that neither Contractor nor its subcontractors, suppliers,
materialmen, or any other persons supplying materials, supplies, services, or
labor directly or indirectly in the prosecution of the work provided in the
Contract have or are aware of any claims or potential claims on this Project.
Contractor further covenants that all subcontractors, suppliers, materialmen,
and all other persons supplying material, supplies, services, or labor used
directly or indirectly in the prosecution of the work provided in the Contract
shall be paid in full, and that Contractor shall defend, indemnify and hold
harmless the Aviation Authority from any and all debts and accounts, promises,
damages, liens, encumbrances, causes of action, suits, bonds, judgements,
claims and demands whatsoever, in law or in equity which any subcontractors,
suppliers, materialmen, or any other persons supplying material, supplies,
services, or labor used directly or indirectly in the prosecution of the work
provided in the Contract had, now has, or may ever have. ADD: $233,140.34;
and, 3. Negotiated Settlement for project refinements to: (a) Eliminate
concrete curb, traffic separator, curb infill areas, and aggregate sub-base
within the interior of the project limits; (b) Eliminate one gate arm from the
Non-AOA reject lane; (c) Eliminate two P-2 Inlet tops; (d) Eliminate the
demolition of the high mast parking lot light; (e) Eliminate Orlando Utilities
Commission connection for streetlights; (f) Eliminate original lightning
protection system; (g) Eliminate original water heater from janitor’s closet;
and, (h) Savings from fill dirt provided by the Aviation Authority.
DEDUCT: ($65,272.15).
Minutes of the Construction Committee Meeting, June 3, 2020
Page 3 of 41
Upon motion of Mr. Hunt, second by Ms. Schneider, vote carried by roll-call
with all votes yea, to recommend to the Aviation Authority Board approval of
Change Order BP-00482-04, for a total amount of $167,868.19 and a 97 calendar
day time extension to Substantial Completion, with funding from previously-
approved Capital Expenditure Funds.
B. Change Order BP-00486-03 GENERATOR CHANGE. This change order to the contract with Hubbard Construction Company for Runway 18L-36R Rehabilitation and Related
Work is to provide a credit for the procurement of a Tier 3 Generator as
opposed to a Tier 4 Generator as required by Contract. It was determined that
the lead time for the Tier 4 was not conducive to the construction dates
provided per Contract. DEDUCT: ($155,984.37).
Ms. Sharman asked if it was okay to switch from a Tier 4 to a Tier 3 generator.
Mr. Brown replied yes, that a Tier 4 generator is intended to run continuously.
A Tier 3 generator operates as needed which is acceptable.
Upon motion of Ms. Sharman, second by Mr. Hunt, vote carried by roll-call with
all votes yea, to recommend to the Aviation Authority Board approval of Change
Order BP-00486-03, for a total deductive amount of ($155,984.37) and no time
extension, with funding credited to FAA and FDOT Grants to the extent eligible,
previously-approved Capital Expenditure Funds, and General Airport Revenue
Bonds.
C. Change Order BP-00491-08 VARIOUS REVISIONS. This change order to the contract with H.W. Davis Construction Inc. for West Security Screening Check Point
Expansion Package 2 is to: 1. Provide labor, material, and equipment to provide
low voltage connections to Level 3 TSA office space, low voltage cabling to
temporary video wall monitors. ADD: $10,634.00; 2. Provide labor, material,
and equipment to install one receptacle for one Fan Coil Unit (FCU) in the
Level 3 TSA office space. ADD: $1,746.17; 3. Provide labor, material, and
equipment to install three additional circuits for three FCUs in the Level 3
TSA office space. ADD: $7,949.00; 4. Provide labor, material, and equipment
to install WT 9x53 to existing structural steel on Level 2 between Grid Lines
F.5 and G.1 at Column Line 6.9, in accordance with ASI-16. ADD: $26,788.00;
5. Provide labor, material, and equipment to install WT 9x25 to structural
steel columns at Grid Lines 3-5 and G-H, in accordance with RFI-22. ADD:
$8,209.00; 6. Provide labor, material, and equipment to level the floor at the
transition between the vomitory tile and carpet at the A and B Sides of the
West Checkpoint. This change order replaces Field Change Order No. 2. ADD:
$3,520.00; and, 7. Reduce the Allowance for Unforeseen Conditions by
($56,197.00) from $56,197.00 to $0.00, to offset the costs associated with
this change order. DEDUCT: ($56,197.00).
Chairman Thornton asked about the deviation in the circuits. Mr. Shedek replied
that these were approved units; however, different manufacturers have different
circuitry specifications and the approved units being used required some
adjustments.
Upon motion of Ms. Sharman, second by Ms. Schneider, vote carried by roll-call
with all votes yea, to approve Change Order BP-00491-08, for a total amount
of $2,649.17 and no time extension, with funding from previously-approved
Capital Expenditure Funds, and General Airport Revenue Bonds.
D. Change Order V-00867-03 VARIOUS REVISIONS. [A handout was presented, which includes a revised Coversheet.] This change order to the contract with R. L.
Burns, Inc. for Centerfield ARFF Administration Building is the final change
order and includes the following: 1. Provide all labor, equipment, and
Minutes of the Construction Committee Meeting, June 3, 2020
Page 4 of 41
materials to perform the below-listed changes to building power. (Reference
Design Bulletin-03R1, Sheets E1-0, E2-0, and E4-1, and RFI-37): (a) Revise
routing to OUC transformer; (b) Increase size of emergency generator concrete
pad; and, (c) Add circuit for the Generator Annunciator Panel (GAP). This
change order replaces Field Change Order No. 3. ADD: $23,467.90; 2. Provide
all labor, equipment and materials to install bollards around the OUC
transformer. ADD: $6,902.83; 3. Provide all labor, equipment, and materials
to add data outlets in Workstation Room 121 where Contract Documents do not
make provisions for data outlets at all necessary workstation locations.
(Reference RFC-006R2 and Sheet T-2.0). This change order replaces Field Change
Order No. 4R. ADD: $2,000.00; 4. Provide all labor, equipment, and materials
to relocate of the installed Variable Air Volume (VAV) in the mechanical room.
(Reference RFI Nos. 42 and 53). ADD: $623.15; 5. Provide all labor, equipment,
and materials to shift proposed canopy footings determined to conflict with
the existing planter foundation. (Reference RFI-56). ADD: $606.29; 6. Provide
all labor, equipment and materials to reroute the condensate discharge to the
exterior from the air handler unit. (Reference RFI-65). ADD: $714.21;
7. Provide all labor, equipment, and materials to tie into an available
irrigation source. (Reference RFI-64). ADD: $10,916.27; 8. Provide all labor,
equipment and material to install temporary irrigation. ADD: $3,766.72; 9.
Provide all labor, equipment, and materials to provide power to various items,
where raceways to service these items are not identified in the electrical
package of the Contract Drawings. (Reference RFI-67). ADD: $4,102.58; 10.
Provide all labor, equipment, and materials to address City Fire Inspector
comments, issued during Final Inspection. ADD: $5,876.82; and, 11. Increase
the Contract Time for Substantial Completion by 124 calendar days from
317 calendar days to 441 calendar days. ADD: $0.00.
Ms. Sharman asked if the change order amount had changed. Mr. Kieffer replied
no, that the handout was provided to show that the potential A/E backcharges’
amounts had been revised.
Upon motion of Ms. Schneider, second by Mr. Hunt, vote carried by roll-call
with all votes yea, to recommend to the Aviation Authority Board approval of
Change Order V-00867-03, for a total amount of $58,976.77 and a 124 calendar
day time extension to Substantial Completion, with funding from previously-
approved Capital Expenditure Funds.
CONSTRUCTION MANAGEMENT AT RISK (CM@R) GUARANTEED MAXIMUM PRICE (GMP) BUDGET, BUYOUT,
AND CONTINGENCY MANAGEMENT REQUESTS AGENDA
2. The following GMP Budget, Buyout, and Contingency Management requests (related
to the South Terminal C, Phase One Project) were presented for consideration:
A. Subcontractor Modification for BP-S00141 (GMP No. 5-S.4) with Schindler
Elevator Corporation for CR0800-LST-RFIs 2036 and 2036.1 Elevator 12.2 Stop
at Level 5 BHS Platform. Mr. Corthell presented the memorandum, requesting
approval for Turner-Kiewit Joint Venture (TKJV) to issue a Subcontractor
Modification on BP-S00141, South Terminal C, Phase 1 – Landside Conveying
Equipment (GMP No. 5-S.4), at the Orlando International Airport, in the total
amount of $1,169.00 to Schindler Elevator Corporation, for CR0800-LST-RFI 2036
and 2036.1 Elevator 12.2 Stop at Level 5 BHS Platform. Bid Package 14.0.0
"Conveying Systems" was previously awarded within GMP No. 5-S.4 to Schindler
Elevator Corporation, CC No. 20181004.007.
TKJV is proposing a subcontract modification to Schindler Elevator Corporation
in the total lump sum amount of $1,169.00 for CR0800-LST-RFIs 2036 and 2036.1
Elevator 12.2 Stop at Level 5 BHS Platform. The modified scope of work consists
of additional labor and material costs for the elevator manufacturer associated
Minutes of the Construction Committee Meeting, June 3, 2020
Page 5 of 41
with the revisions to Car-Opening Panel of Elevator 12.2 due to removal of
stop on Level 5, per RFIs 2036 and 2036.1.
The approval of this subcontract modification to Schindler Elevator Corporation
resolves all requests for costs and time resulting from RFIs 2036 and 2036.1
in GMP No. 5-S.4. Cost impacts to GMP No. 7-S.1 were approved at CC
No. 20200310-03L. There are no cost impacts to GMP Nos. 7-S, 7-S.2, 7-S.3 and
7-S.4.
TKJV has submitted documentation including the subcontractor's proposal to
support their request. An independent cost estimate included. By approving
this request, the Owner does not waive its right to enforce the contract
requirements for other requests of cost or time.
The effect of this Subcontractor Modification for this project is as follows:
TKJV to issue a subcontract modification to Schindler
Elevator Corporation in the lump sum amount of: $ 1,169.00
Deduct from P1 Owner Contingency: $ (1,169.00)
Turner-Kiewit Joint Venture is committed to 20% MWBE and 4% LDB participation
for Construction Services. The subcontractor identified and committed to
participate on BP-S00141 (GMP No. 5-S.4) for this subcontract modification is
Schindler Elevator Corporation (Non-MWBE/LDB/VBE). There is no small business
participation associated with this modification.
Agenda Item Nos. 2-A, 2-B, 2-C, 2-D, 2-E, 2-F, 2-G, 2-H, 2-I, 2-J, 2-K, 2-L,
2-M, 2-N, 2-O, 2-P, 2-Q, 2-R, 2-S, 2-T, 2-U, 2-V, 2-W, 2-X, 2-Y, 2-Z, 2-AA,
2-BB, and 2-CC were considered in one motion.
Upon motion of Mr. Patterson, second by Mr. Hunt, vote carried by roll-call,
with all votes yea, vote carried to approve Turner-Kiewit Joint Venture to
issue a Subcontractor Modification to Schindler Elevator Corporation on
BP-S00141, South Terminal C, Phase 1 – Landside Conveying Equipment (GMP No.
5-S.4), for the total lump sum amount of $1,169.00, with funding from Passenger
Facility Charges and General Airport Revenue Bonds.
B. Subcontractor Modification for BP-S00141 (GMP No. 5-S.4) with Schindler
Elevator Corporation for CR1053-GTF-RFI 4295-Exterior Escalators Hatch Access
to Sump Pump. Mr. Corthell presented the memorandum, requesting approval for
Turner-Kiewit Joint Venture (TKJV) to issue a Subcontractor Modification on
BP-S00141, South Terminal C, Phase 1 – Landside Conveying Equipment (GMP No.
5-S.4), at the Orlando International Airport, in the total amount of $829.00
to Schindler Elevator Corporation, for CR1053-GTF-RFI 4295-Exterior Escalators
Hatch Access to Sump Pump. Bid Package 14.0.0 "Conveying Systems" was
previously awarded within GMP No. 5-S.4 to Schindler Elevator Corporation, CC
No. 20181004.007.
TKJV is proposing a subcontract modification to Schindler Elevator Corporation
in the total lump sum amount of $829.00 for CR1053-GTF-RFI 4295-Exterior
Escalators Hatch Access to Sump Pump. Schindler Elevator Corporation issued
sketches in response to RFI 4295 to add removable panels to access sump pump
at exterior escalators. The sump pump pit dimensions were also revised to
36-inch W x 36-inch L x 36-inch D per the Design Team direction. The modified
scope of work consists of additional labor and material costs for the elevator
manufacturer associated with the revisions to add access hatch in the bottom
of the escalator pan to access the sump pump.
Minutes of the Construction Committee Meeting, June 3, 2020
Page 6 of 41
The approval of this subcontract modification to Schindler Elevator Corporation
resolves all requests for costs and time resulting from RFI 4295.
TKJV has submitted documentation including the subcontractor's proposal to
support their request. An independent cost estimate; included. By approving
this request, the Owner does not waive its right to enforce the contract
requirements for other requests for cost or time.
The effect of this Subcontractor Modification for this project is as follows:
TKJV to issue a subcontract modification to Schindler
Elevator Corporation in the lump sum amount of: $ 829.00
Deduct from P1X Owner Contingency: $ (829.00)
Turner-Kiewit Joint Venture is committed to 20% MWBE and 4% LDB participation
for Construction Services. The subcontractor identified and committed to
participate on BP-S00141 (GMP No. 5-S.4) for this subcontract modification is
Schindler Elevator Corporation (Non-MWBE/LDB/VBE). There is no small business
participation associated with this modification.
Agenda Item Nos. 2-A, 2-B, 2-C, 2-D, 2-E, 2-F, 2-G, 2-H, 2-I, 2-J, 2-K, 2-L,
2-M, 2-N, 2-O, 2-P, 2-Q, 2-R, 2-S, 2-T, 2-U, 2-V, 2-W, 2-X, 2-Y, 2-Z, 2-AA,
2-BB, and 2-CC were considered in one motion.
Upon motion of Mr. Patterson, second by Mr. Hunt, vote carried by roll-call,
with all votes yea, vote carried to approve Turner-Kiewit Joint Venture to
issue a Subcontractor Modification to Schindler Elevator Corporation on
BP-S00141, South Terminal C, Phase 1 – Landside Conveying Equipment (GMP No.
5-S.4), for the total lump sum amount of $829.00, with funding from General
Airport Revenue Bonds and Customer Facility Charges.
C. Subcontract Modification for BP-S00143 (GMP No. 6-S.1) with Banker Steel Co., LLC for CR0546-6S1-RFI 2172 PBP 241 Low Roof Parapet Structural Support (CWA
BP-S143-024). Mr. Corthell presented the memorandum, requesting approval for
Hensel Phelps Construction (HPC) to issue a Subcontract Modification on BP-
S00143, South Terminal C, Phase 1 - Airside Terminal, Structure and Enclosure
(GMP No. 6-S.1), at the Orlando International Airport, in the total amount of
$2,522.00 to Banker Steel Co., LLC, for CR0546-6S1-RFI 2172 PBP 241 Low Roof
Parapet Structural Support (CWA BP-S143-024). Bid Package for BP-S00143 05.01
"Structural Steel and Miscellaneous Metals" has been previously awarded within
GMP No. 6-S.1 to Banker Steel Co., LLC, CC No. 20180410.008.
HPC is requesting to issue a Subcontractor Modification to Banker Steel Co.,
LLC in the total Lump Sum amount of $2,522.00 for CR0546-6S1-RFI 2172 PBP 241
Low Roof Parapet Structural Support. The modified scope of work consists of
the additional detailing, material, labor, and erection costs associated with
the added structural steel to support the parapet framing on both sides of the
Passenger Boarding Pier PBP-241 low roof expansion joint bump-out at Gridline
A 18.9/B4.5, per RFI 2172 response and sketches.
The approval of this Subcontractor Modification to Banker Steel Co., LLC
resolves all requests for cost and time resulting from RFI 2172 scope of work
and closed out CWA BP-S143-024. Costs for Testing and Inspection, if any, will
be submitted in a future CR.
HPC has submitted documentation including the subcontractor's proposal to
support their request. An independent cost estimate is included. By approving
Minutes of the Construction Committee Meeting, June 3, 2020
Page 7 of 41
this request, the Owner does not waive its right to enforce the contract
requirements or other requests for costs or time.
The effect of this Subcontract Modification for this project is as follows:
HPC to issue a subcontract modification to Banker
Steel Co., LLC in the lump sum amount of: $ 2,522.00
Deduct from P1 Owner Contingency: $ (2,522.00)
Hensel Phelps Construction is committed to 20% MWBE and 4% LDB participation
for Construction Services. The subcontractor identified and committed to
participate on BP-S00143 (GMP No. 6-S.1) for this subcontract modification is
Banker Steel Co., LLC (Non-MWBE/LDB/VBE). There is no small business
participation associated with this modification.
Agenda Item Nos. 2-A, 2-B, 2-C, 2-D, 2-E, 2-F, 2-G, 2-H, 2-I, 2-J, 2-K, 2-L,
2-M, 2-N, 2-O, 2-P, 2-Q, 2-R, 2-S, 2-T, 2-U, 2-V, 2-W, 2-X, 2-Y, 2-Z, 2-AA,
2-BB, and 2-CC were considered in one motion.
Upon motion of Mr. Patterson, second by Mr. Hunt, vote carried by roll-call,
with all votes yea, to approve Hensel Phelps Construction to issue a
Subcontract Modification to Banker Steel Co., LLC on BP-S00143, South Terminal
C, Phase 1 - Airside Terminal, Structure and Enclosure (GMP No. 6-S.1), for
the total lump sum amount of $2,522.00, with funding from Passenger Facility
Charges.
D. Subcontract Modifications for BP-S00143 (GMP No. 6-S.1) with T&T Construction of Central Fla., Inc.; and Banker Steel Co., LLC; for CR0444-6S1-RFI 1927 High
Roof Slab at LST/ASC Connection (CWA BP-S143-020). Mr. Corthell presented the
memorandum, requesting approval for Hensel Phelps Construction (HPC) to issue
Subcontract Modifications on BP-S00143, South Terminal C, Phase 1 - Airside
Terminal, Structure and Enclosure (GMP No. 6-S.1), at the Orlando International
Airport, in the total amount of $20,825.00 to T&T Construction of Central
Fla., Inc.; and Banker Steel Co., LLC; for CR0444-6S1-RFI 1927 High Roof Slab
at LST/ASC Connection (CWA BP-S143-020). Bid Package 03.02 "Building Concrete"
and 05.01 "Structural Steel and Miscellaneous Metals" were previously awarded
within GMP No. 6-S.1, respectively, to T&T Construction of Central Fla., Inc.;
and Banker Steel Co., LLC; CC No. 201800410.008.
RFI 1927 was written to clarify a discrepancy at the High Roof LST/ASC
Connection causing a portion of the exterior framing to not have the required
structural steel supports. HPC is requesting to issue the following
Subcontractor Modifications to:
1. T&T Construction of Central Fla., Inc. in the Lump Sum amount of
$1,865.00 for CR0444-6S1-RFI 1927 High Roof Slab at LST/ASC Connection.
The modified scope of work consists of the costs associated with added
Slab-on-Metal-Deck (SOMD) at column lines A30/S2 on the High Roof for
the ASC connection to the LST (Landside Terminal), per RFI 1927
response.
2. Banker Steel Co., LLC in the Lump Sum amount of $18,960.00 for CR0444-
6S1-RFI 1927 High Roof Slab at LST/ASC Connection. The modified scope
of work consists of the detailing, material, fabrication and erection
costs associated with the additional structural steel required to
support the High Roof deck and wall, at column lines A30/S2 on the High
Roof for the ASC connection to the LST (Landside Terminal), per RFI
1927 response.
Minutes of the Construction Committee Meeting, June 3, 2020
Page 8 of 41
The approval of these Subcontractor Modifications to T&T Construction of
Central Fla., Inc.; and Banker Steel Co., LLC; resolves all requests for costs
and time resulting from RFI 1927 and closes out CWA BP-S143-020, which covered
only the Structural Steel costs as set forth in CR0444. Cost impacts associated
with patching of fireproofing and testing and inspection, if any, will be
submitted at a future date.
HPC has submitted documentation including the subcontractor's proposal to
support this request. An independent cost estimate is included. By approving
this request, the Owner does not waive its right to enforce the contract
requirements for other requests for cost or time.
The effect of these Subcontract Modifications for this project is as follows:
HPC to issue a subcontract modification to T&T
Construction of Central Fla. in the lump sum
amount of: $ 1,865.00
HPC to issue a subcontract modification to Banker
Steel Co., LLC in the lump sum amount of: $ 18,960.00
Deduct from P1 Owner Contingency: $ (20,825.00)
Hensel Phelps Construction is committed to 20% MWBE and 4% LDB participation
for Construction Services. The subcontractors identified and committed to
participate on BP-S00143 (GMP No. 6-S.1) for these subcontract modifications
are T&T Construction of Central Florida, Inc. (MWBE); and Banker Steel Co.,
LLC (Non-MWBE/LDB/VBE). There is an overall small business participation of
9.0% MWBE associated with the proposed modifications.
Agenda Item Nos. 2-A, 2-B, 2-C, 2-D, 2-E, 2-F, 2-G, 2-H, 2-I, 2-J, 2-K, 2-L,
2-M, 2-N, 2-O, 2-P, 2-Q, 2-R, 2-S, 2-T, 2-U, 2-V, 2-W, 2-X, 2-Y, 2-Z, 2-AA,
2-BB, and 2-CC were considered in one motion.
Upon motion of Mr. Patterson, second by Mr. Hunt, vote carried by roll-call,
with all votes yea, to approve Hensel Phelps Construction to issue Subcontract
Modifications on BP-S00143, South Terminal C, Phase 1 - Airside Terminal,
Structure and Enclosure (GMP No. 6-S.1), for the total amount of $20,825.00,
which includes the lump sum amount of $1,865.00 to T&T Construction of Central
Fla., Inc.; and the lump sum amount of $18,960.00 to Banker Steel Co., LLC;
with funding from Passenger Facility Charges and General Airport Revenue Bonds.
E. Subcontract Modification for BP-S00143 (GMP No. 6-S.1) with Odyssey
International dba Odyssey Global for CR0519-6S1-RFI 1562 CMU at BHS Fire
Shutter Door, and RFI 1456 BHS Lift CMU Reconfiguration. Mr. Corthell
presented the memorandum, requesting approval for Hensel Phelps Construction
(HPC) to issue a Subcontract Modification on BP-S00143, South Terminal C,
Phase 1 - Airside Terminal, Structure and Enclosure (GMP No. 6-S.1), at the
Orlando International Airport, in the total amount of $15,385.00 to Odyssey
International dba Odyssey Global for CR0519-6S1-RFI 1562 CMU at BHS Fire
Shutter Door, and RFI 1456 BHS Lift CMU Reconfiguration. Bid Package for BP-
S143 04.01 "Masonry" was previously awarded within GMP No. 6-S.1 to Odyssey
International dba Odyssey Global, CC No. 20180410.008.
HPC is requesting to issue a Subcontractor Modification to Odyssey
International dba Odyssey Global in the total Lump Sum amount of $15,385.00
for CR0519-6S1-RFI 1562 CMU at BHS Fire Shutter Door, and RFI 1456 BHS Lift
CMU Reconfiguration. The modified scope of work consists of the additional
costs associated with revising the Concrete Masonry Unit (CMU) wall layout to
Minutes of the Construction Committee Meeting, June 3, 2020
Page 9 of 41
align with the Baggage Handling System (BHS) Fire Shutter in Room 01-0078 in
the ASC Area 17, per RFI 1562 response and sketches; and with reconfiguring
the CMU wall to encapsulate the BHS Right-of-Way (ROW) lift in Room 01-0045
in the ASC Area 31, per RFI 1456 responses and sketches.
The approval of this Subcontractor Modification to Odyssey International dba
Odyssey Global resolves all requests for cost and time resulting from RFIs
1562 and 1456 scopes of work. Costs for Testing and Inspection, if any, will
be submitted in a future CR. There are no cost impacts to GMP Nos. 6-S, 6-S.2,
6-S.3, 6-S.4, 6-S.5, and 6-S.6.
HPC has submitted documentation including the subcontractor's proposal to
support their request. An independent cost estimate is included. By approving
this request, the Owner does not waive its right to enforce the contract
requirements for other requests for costs or time.
The effect of this Subcontract Modification for this project is as follows:
HPC to issue a subcontract modification to
Odyssey International dba Odyssey Global in the
lump sum amount of: $ 15,385.00
Deduct from P1 Owner Contingency: $ (15,385.00)
Hensel Phelps Construction is committed to 20% MWBE and 4% LDB participation
for Construction Services. The subcontractor identified and committed to
participate on BP-S00143 (GMP No. 6-S.1) for this subcontract modification is
Odyssey International, Inc. dba Odyssey Global (Non-MWBE/LDB/VBE at the time
of award of the "Masonry" bid package). There is 95.7% MWBE participation
associated with this modification.
Agenda Item Nos. 2-A, 2-B, 2-C, 2-D, 2-E, 2-F, 2-G, 2-H, 2-I, 2-J, 2-K, 2-L,
2-M, 2-N, 2-O, 2-P, 2-Q, 2-R, 2-S, 2-T, 2-U, 2-V, 2-W, 2-X, 2-Y, 2-Z, 2-AA,
2-BB, and 2-CC were considered in one motion.
Upon motion of Mr. Patterson, second by Mr. Hunt, vote carried by roll-call,
with all votes yea, to approve Hensel Phelps Construction to issue a
Subcontract Modification to Odyssey International dba Odyssey Global on
BP-S00143, South Terminal C, Phase 1 - Airside Terminal, Structure and
Enclosure (GMP No. 6-S.1), for the total lump sum amount of $15,385.00, with
funding from Passenger Facility Charges.
F. Subcontract Modifications for BP-S00143 (GMP No. 6-S.1) with Odyssey
International Inc. dba Odyssey Global; and Banker Steel Co., LLC; for CR0462-
6S1-RFI 1905 Elevator 24.1 Door Support Channels and Angles (CWA BP-S143-011).
Mr. Corthell presented the memorandum, requesting approval for Hensel Phelps
Construction (HPC) to issue Subcontract Modifications on BP-S00143, South
Terminal C, Phase 1 - Airside Terminal, Structure and Enclosure (GMP No. 6-
S.1), at the Orlando International Airport, in the total amount of $34,792.00
to Odyssey International Inc. dba Odyssey Global; and Banker Steel Co., LLC;
for CR0462-6S1-RFI 1905 Elevator 24.1 Door Support Channels and Angles (CWA
BP-S143-011). Bid Package 04.01 "Masonry" and 05.01 "Structural Steel and
Miscellaneous Metals" were previously awarded within GMP No. 6-S.1,
respectively, to Odyssey International Inc. dba Odyssey Global; and Banker
Steel Co., LLC; CC No. 201800410.008.
RFI 1905 was written to clarify the support details for two doorways on the
Ramp Level and one doorway on the Transfer Level for Elevator 24.1. HPC is
requesting to issue the following Subcontractor Modifications to;
Minutes of the Construction Committee Meeting, June 3, 2020
Page 10 of 41
1. Odyssey International dba Odyssey Global in the Lump Sum amount of $18,005.00 for CR0462-6S1-RFI 1905 Elevator 24.1 Door Support Channels
and Angles. The modified scope of work includes the additional labor,
material and equipment costs associated with the installation and
grouting of the added Elevator door support frames and C-channels at the
jambs and the added L-angles at the sills, per RFI 1905.
2. Banker Steel Co., LLC in the Lump Sum amount of $16,787.00 for CR0462-6S1-RFI 1905 Elevator 24.1 Door Support Channels and Angles. The modified
scope of work includes the additional costs associated with the
detailing, material, fabrication and erection of the added structural
steel angles and channels, and the Elevator door support frames for
Elevator 24.1, per RFI 1905.
The approval of these Subcontractors Modifications to Odyssey International
dba Odyssey Global; and Banker Steel Co., LLC; resolves all requests for costs
and time resulting from RFI 1905 and closes out CWA BP-S143-011. Initial CWA
BP-S143-011 amount did not anticipate scaffolding rental. Costs for Testing
and Inspection, if any, will be submitted in a future CR.
HPC has submitted documentation including the subcontractor's proposal to
support this request. An independent cost estimate is included. By approving
this request, the Owner does not waive its right to enforce the contract
requirements for other requests for cost or time.
The effect of this Subcontract Modification for this project is as follows:
HPC to issue a subcontract modification to Odyssey
International dba Odyssey Global in the lump sum
amount of: $ 18,005.00
HPC to issue a subcontract modification to Banker
Steel Co., LLC in the lump sum amount of: $ 16,787.00
Deduct from P1 CM@R Contingency: $ (34,792.00)
Hensel Phelps Construction is committed to 20% MWBE and 4% LDB participation
for Construction Services. The subcontractors identified and committed to
participate on BP-S00143 (GMP No. 6-S.1) for these subcontract modifications
are Odyssey International, Inc. dba Odyssey Global (MWBE); and Banker Steel
Co., LLC (Non-MWBE/LDB/VBE). There is an overall 49.5% MWBE participation
associated with the proposed modifications.
Agenda Item Nos. 2-A, 2-B, 2-C, 2-D, 2-E, 2-F, 2-G, 2-H, 2-I, 2-J, 2-K, 2-L,
2-M, 2-N, 2-O, 2-P, 2-Q, 2-R, 2-S, 2-T, 2-U, 2-V, 2-W, 2-X, 2-Y, 2-Z, 2-AA,
2-BB, and 2-CC were considered in one motion.
Upon motion of Mr. Patterson, second by Mr. Hunt, vote carried by roll-call,
with all votes yea, to approve Hensel Phelps Construction to issue Subcontract
Modifications on BP-S00143, South Terminal C, Phase 1 - Airside Terminal,
Structure and Enclosure (GMP No. 6-S.1), for the total amount of $34,792.00,
which includes the lump sum amount of $18,005.00 to Odyssey International Inc.
dba Odyssey Global; and the lump sum amount of $16,787.00 to Banker Steel Co.,
LLC; with funding credited to Passenger Facility Charges and General Airport
Revenue Bonds.
Minutes of the Construction Committee Meeting, June 3, 2020
Page 11 of 41
G. Subcontract Modification for BP-S00143 (GMP No. 6-S.1) with Banker Steel Co., LLC for CR0463-6S1-RFI 1944 Elevator 18.1 Pit Deck/Slab Support (CWA BP-S143-
017). Mr. Corthell presented the memorandum, requesting approval for Hensel
Phelps Construction (HPC) to issue a Subcontract Modification on BP-S00143,
South Terminal C, Phase 1 - Airside Terminal, Structure and Enclosure (GMP No.
6-S.1), at the Orlando International Airport, in the total amount of $8,603.00
to Banker Steel Co., LLC for CR0463-6S1-RFI 1944 Elevator 18.1 Pit Deck/Slab
Support (CWA BP-S143-017). Bid Package for BP-S00143 05.01 "Structural Steel
and Miscellaneous Metals" has been previously awarded within GMP No. 6-S.1 to
Banker Steel Co., LLC, CC No. 20180410.008.
HPC is requesting to issue a Subcontractor Modification to Banker Steel Co.,
LLC in the total Lump Sum amount of $8,603.00 for CR0463-6S1-RFI 1944 Elevator
18.1 Pit Deck/Slab Support. The modified scope of work consists of the
detailing, material, fabrication, and erection costs associated with the
additional structural steel supports at the Elevator 18.1 Pit Deck/Slab, per
RFI 1944 response and sketch.
The approval of this Subcontractor Modification to Banker Steel Co., LLC
resolves all requests for cost and time resulting from RFI 1944 scope of work
and closes out CWA BP-S143-017.
HPC has submitted documentation including the subcontractor's proposal to
support their request. An independent cost estimate is included. By approving
this request, the Owner does not waive its right to enforce the contract
requirements for other requests for costs or time.
The effect of this Subcontract Modification for this project is as follows:
HPC to issue a subcontract modification to
Banker Steel Co., LLC in the lump sum amount of: $ 8,603.00
Deduct from P1 Owner Contingency: $ (8,603.00)
Hensel Phelps Construction is committed to 20% MWBE and 4% LDB participation
for Construction Services. The subcontractor identified and committed to
participate on BP-S00143 (GMP No. 6-S.1) for this subcontract modification is
Banker Steel Co., LLC (Non-MWBE/LDB/VBE). There is no small business
participation associated with this modification.
Agenda Item Nos. 2-A, 2-B, 2-C, 2-D, 2-E, 2-F, 2-G, 2-H, 2-I, 2-J, 2-K, 2-L,
2-M, 2-N, 2-O, 2-P, 2-Q, 2-R, 2-S, 2-T, 2-U, 2-V, 2-W, 2-X, 2-Y, 2-Z, 2-AA,
2-BB, and 2-CC were considered in one motion.
Upon motion of Mr. Patterson, second by Mr. Hunt, vote carried by roll-call,
with all votes yea, to approve Hensel Phelps Construction to issue a
Subcontract Modification to Banker Steel Co., LLC on BP-S00143, South Terminal
C, Phase 1 - Airside Terminal, Structure and Enclosure (GMP No. 6-S.1), for
the total lump sum amount of $8,603.00, with funding from Passenger Facility
Charges and General Airport Revenue Bonds.
H. Subcontract Modification for BP-S00143 (GMP No. 6-S.1) with Odyssey
International dba Odyssey Global for CR0503.4-6S1-ASC Bulletin 037 Non-
Mechanical Trades. Mr. Corthell presented the memorandum, requesting approval
for Hensel Phelps Construction (HPC) to issue a Subcontract Modification on
BP-S00143, South Terminal C, Phase 1 - Airside Terminal, Structure and
Enclosure (GMP No. 6-S.1), at the Orlando International Airport, in the total
amount of $12,776.00 to Odyssey International dba Odyssey Global for CR0503.4-
6S1-ASC Bulletin 037 Non-Mechanical Trades. Bid Package for BP-S143 04.01
Minutes of the Construction Committee Meeting, June 3, 2020
Page 12 of 41
"Masonry" was previously awarded within GMP No. 6-S.1 to Odyssey International
dba Odyssey Global, CC No. 20180410.008.
HPC is requesting to issue a Subcontractor Modification to Odyssey
International dba Odyssey Global in the total Lump Sum amount of $12,776.00
for CR0503.4-6S1-ASC Bulletin 037 Non-Mechanical Trades. The modified scope
of work consists of the additional labor, material and equipment costs
associated with the added and changed Concrete Masonry Unit (CMU) wall
openings. HPC will also submit Time Impact Analysis (TIA 088) requesting
additional time associated with this scope of work ASC Bulletin 037.
The approval of this Subcontractor Modification to Odyssey International dba
Odyssey Global resolves all requests for costs associated with the ASC Bulletin
037 NonMechanical Trades scope of work in GMP No. 6-S.1, with the exception
of costs for DSI ASC-003 and ASC Bulletin 036, as follows:
Costs associated with DSI ASC-003 and ASC Bulletin 036 are excluded due
to document inconsistencies and further design changes that are being
resolved and costs for these will be submitted in a future CR.
Cost impacts of ASC Bulletin 037 Mechanical Only scope of work in GMP
No. 6-S.1 were approved via CC No. 20200324.02B (CR0503.2-6S.1).
Cost impacts of ASC B037 Mechanical Only scope of work in GMP No. 6-S.6
were approved via CC No. 20200324.200 (CR0503.3-6S.6).
Cost impacts of ASC B037 to GMP No. 6-S.2 for the Non-electrical Trades
in CR0503.5-6S.2 will be submitted for a future CCM approval.
Cost impacts of ASC B037 to GMP No. 6-S.4 will be submitted in CR0503.6-
6S.4 for a future CCM approval.
Cost impacts of ASC B037 to GMP No. 6-S.6 for the Non-Mechanical scope
will be submitted in future CRs.
There are no cost impacts of ASC B037 to GMP No. 6-S.2 for the Electrical
scope of work.
Cost impacts of ASC B037 to GMP Nos. 6-S, 6-S.3, and 6-S.5, if any, will
be submitted in future CR.
The OAR will evaluate TIA-088 and any additional time recommended to be
granted will be submitted at a future CCM.
HPC has submitted documentation including the subcontractor's proposal to
support their request. An independent cost estimate is included. By approving
this request, the Owner does not waive its right to enforce the contract
requirements for other requests for costs or time.
The effect of this Subcontract Modification for this project is as follows:
HPC to issue a subcontract modification to
Odyssey International dba Odyssey Global in the
lump sum amount of: $ 12,776.00
Deduct from P1 Owner Contingency: $ (12,776.00)
Minutes of the Construction Committee Meeting, June 3, 2020
Page 13 of 41
Hensel Phelps Construction is committed to 20% MWBE and 4% LDB participation
for Construction Services. The subcontractor identified and committed to
participate on BP-S00143 (GMP No. 6-S.1) for this subcontract modification is
Odyssey International, Inc. dba Odyssey Global (Non-MWBE/LDB/VBE at the time
of award of the "Masonry" bid package). There is 88.8% MWBE participation
associated with this modification.
Agenda Item Nos. 2-A, 2-B, 2-C, 2-D, 2-E, 2-F, 2-G, 2-H, 2-I, 2-J, 2-K, 2-L,
2-M, 2-N, 2-O, 2-P, 2-Q, 2-R, 2-S, 2-T, 2-U, 2-V, 2-W, 2-X, 2-Y, 2-Z, 2-AA,
2-BB, and 2-CC were considered in one motion.
Upon motion of Mr. Patterson, second by Mr. Hunt, vote carried by roll-call,
with all votes yea, to approve Hensel Phelps Construction to issue a
Subcontract Modification to Odyssey International dba Odyssey Global on BP-
S00143, South Terminal C, Phase 1 - Airside Terminal, Structure and Enclosure
(GMP No. 6-S.1), for the total lump sum amount of $12,776.00, with funding
from General Airport Revenue Bonds.
I. Subcontract Modification for BP-S00143 (GMP No. 6-S.1) with Randall Mechanical, Inc. for CR0543-6S1-ASC B014 Air Handling Units (AHU) R2A-1 and R2A-2.
Mr. Corthell presented the memorandum, requesting approval for Hensel Phelps
Construction (HPC) to issue a Subcontract Modification on BP-S00143, South
Terminal C, Phase 1 - Airside Terminal, Structure and Enclosure (GMP No. 6-
S.1), at the Orlando International Airport, in the total amount of $205,347.00
to Randall Mechanical, Inc., for CR0543-6S1-ASC B014 Air Handling Units (AHU)
R2A-1 and R2A-2. Bid Package for BP-S00143 23.01 "HVAC" has been previously
awarded within GMP No. 6-S.1 to Randall Mechanical, Inc., CC No. 20180410.008.
HPC is requesting to issue a Subcontractor Modification to Randall Mechanical,
Inc. in the total Lump Sum amount of $205,347.00 for CR0543-6S1-ASC B014 Air
Handling Units R2A-1 and R2A-2. The Subcontractor, Randall Mechanical, Inc.,
submitted its proposal for ASC Bulletin 014 which was approved, CC No.
20190402.004. The Subcontractor subsequently realized that two Air Handling
Units (AHU) were identified, but no value was included for them in their ASC
Bulletin 014 proposal and provided back-up documentation to support their
error regarding missing values. The AHUs are necessary scope that were not
paid for previously in the ASC Bulletin 014 proposal. The additional scope of
work consists of the costs associated with the procurement of the two Air
Handling Units R2A-1 and R2A-2 located at the Mechanical Equipment Room (MER)
No. 2A.
The approval of this Subcontractor Modification to Randall Mechanical, Inc.
resolves all requests for costs associated with CR0543-6S1-ASC B014 Air
Handling Units R2A-1 and R2A-2 scope of work.
HPC has submitted documentation including the subcontractor's proposal to
support this request. An independent cost estimate is included. By approving
this request, the Owner does not waive its right to enforce the contract
requirements for other requests for cost or time.
The effect of this Subcontract Modification for this project is as follows:
HPC to issue a subcontract modification to Randall
Mechanical, Inc., in the lump sum amount of: $ 205,347.00
Deduct from P1 CM@R Contingency: $ (205,347.00)
Hensel Phelps Construction is committed to 20% MWBE and 4% LDB participation
for Construction Services. The subcontractor identified and committed to
Minutes of the Construction Committee Meeting, June 3, 2020
Page 14 of 41
participate on BP-S00143 (GMP No. 6-S.1) for this subcontract modification is
Randall Mechanical, Inc. (Non-MWBE/LDB/VBE). There is no small business
participation associated with this modification.
Agenda Item Nos. 2-A, 2-B, 2-C, 2-D, 2-E, 2-F, 2-G, 2-H, 2-I, 2-J, 2-K, 2-L,
2-M, 2-N, 2-O, 2-P, 2-Q, 2-R, 2-S, 2-T, 2-U, 2-V, 2-W, 2-X, 2-Y, 2-Z, 2-AA,
2-BB, and 2-CC were considered in one motion.
Upon motion of Mr. Patterson, second by Mr. Hunt, vote carried by roll-call,
with all votes yea, to approve Hensel Phelps Construction to issue a
Subcontract Modification to Randall Mechanical, Inc. on BP-S00143, South
Terminal C, Phase 1 - Airside Terminal, Structure and Enclosure (GMP No. 6-
S.1), for the total lump sum amount of $205,347.00, with funding from General
Airport Revenue Bonds and Aviation Authority Funds.
J. Subcontract Modification for BP-S00143 (GMP No. 6-S.1) with Banker Steel Co., LLC for CR0486-6S1-RFI 1705 Fall Protection Anchor Bracing Confirmation.
Mr. Corthell presented the memorandum, requesting approval for Hensel Phelps
Construction (HPC) to issue a Subcontract Modification on BP-S00143, South
Terminal C, Phase 1 - Airside Terminal, Structure and Enclosure (GMP No. 6-
S.1), at the Orlando International Airport, in the total amount of $5,958.00
to Banker Steel Co., LLC for CR0486-6S1-RFI 1705 Fall Protection Anchor Bracing
Confirmation. Bid Package for BP-S143 05.01 "Structural Steel and
Miscellaneous Metals" has been previously awarded within GMP No. 6-S.1 to
Banker Steel Co., LLC, CC No. 20180410.008.
HPC is requesting to issue a Subcontractor Modification to Banker Steel Co.,
LLC in the total Lump Sum amount of $5,958.00 for CR0486-6S1-RFI 1705 Fall
Protection Anchor Bracing Confirmation. The modified scope of work consists
of the detailing, material, fabrication and erection costs associated with the
added structural steel braces and the shifted fall protection anchors, to meet
the parameters of the fall protection engineered system spacing, per RFI 1705.
The approval of this Subcontractor Modifications to Banker Steel Co., LLC
resolves all requests for cost and time resulting from RFI 1705 scope of work.
Costs for Testing and Inspection, if any, will be submitted in a future CR.
HPC has submitted documentation including the subcontractor's proposal to
support their request. An independent cost estimate is included. By approving
this request, the Owner does not waive its right to enforce the contract
requirements for other requests for costs or time.
The effect of this Subcontract Modification for this project is as follows:
HPC to issue a subcontract modification to Banker
Steel Co., LLC in the lump sum amount of: $ 5,958.00
Deduct from P1 CM@R Contingency: $ (5,958.00)
Hensel Phelps Construction is committed to 20% MWBE and 4% LDB participation
for Construction Services. The subcontractor identified and committed to
participate on BP-S00143 (GMP No. 6-S.1) for this subcontract modification is
Banker Steel Co., LLC (Non-MWBE/LDB/VBE). There is no small business
participation associated with this modification.
Agenda Item Nos. 2-A, 2-B, 2-C, 2-D, 2-E, 2-F, 2-G, 2-H, 2-I, 2-J, 2-K, 2-L,
2-M, 2-N, 2-O, 2-P, 2-Q, 2-R, 2-S, 2-T, 2-U, 2-V, 2-W, 2-X, 2-Y, 2-Z, 2-AA,
2-BB, and 2-CC were considered in one motion.
Minutes of the Construction Committee Meeting, June 3, 2020
Page 15 of 41
Upon motion of Mr. Patterson, second by Mr. Hunt, vote carried by roll-call,
with all votes yea, to approve Hensel Phelps Construction to issue a
Subcontract Modification to Banker Steel Co., LLC on BP-S00143, South Terminal
C, Phase 1 - Airside Terminal, Structure and Enclosure (GMP No. 6-S.1), for
the total lump sum amount of $5,958.00, with funding from Passenger Facility
Charges and General Airport Revenue Bonds.
K. Subcontract Modifications for BP-S00143 (GMP No. 6-S.1) with Kirlin Florida, LLC; and Randall Mechanical, Inc.; for CR0489-6S1-RFI 2079 IDF 01-0026 AC
Water Runoff Piping. Mr. Corthell presented the memorandum, requesting
approval for Hensel Phelps Construction (HPC) to issue Subcontract
Modifications on BP-S00143, South Terminal C, Phase 1 - Airside Terminal,
Structure and Enclosure (GMP No. 6-S.1), at the Orlando International Airport,
in the total amount of $5,704.00 to Kirlin Florida, LLC; and Randall
Mechanical, Inc.; for CR0489-6S1-RFI 2079 IDF 01-0026 AC Water Runoff Piping.
Bid Package for BP-S143 22.01 "Plumbing" has been previously awarded within
GMP No. 6-S.1 to Kirlin Florida, LLC, CC No. 20180522.04H. Bid Package for
BP-S00143 23.01 "HVAC" has been previously awarded within GMP No. 6-S.1 to
Randall Mechanical, Inc., CC No. 20180410.008.
HPC is requesting to issue the following Subcontractor Modifications to:
1. Kirlin Florida, LLC in the Lump Sum amount of $626.00 for CR0489-6S1-
RFI 2079 IDF 01-0026 AC Water Runoff Piping. The additional scope of
work consists of the costs associated with cutting and capping the
existing funnel drain in IDF Room 01-0026, per RFI 2079 response.
2. Randall Mechanical, Inc. in the Lump Sum amount of $5,078.00 for CR0489-
6S1-RFI 2079 IDF 01-0026 AC Water Runoff Piping. The modified scope of
work consists of the costs associated with relocating the pumped
condensate drain from AC-L1-4 to Mechanical Room 01-0021, per RFI 2079
response.
The approval of these Subcontractor Modifications to Kirlin Florida, LLC; and
to Randall Mechanical, Inc.; resolves all requests for cost and time resulting
from the RFI 2079. There are no cost impacts for RFI 2079 to GMP Nos. 6-S,
6-S.2, 6-S.3, 6-S.4, 6-S.5, and 6-S.6.
HPC has submitted documentation including the subcontractor's proposal to
support this request. An independent cost estimate is included. By approving
this request, the Owner does not waive its right to enforce the contract
requirements for other requests for cost or time.
The effect of this Subcontract Modification for this project is as follows:
HPC to issue a subcontract modification to Kirlin
Florida, LLC in the lump sum amount of: $ 626.00
HPC to issue a subcontract modification to Randall
Mechanical, Inc. in the lump sum amount of: $ 5,078.00
Deduct from P1 Owner Contingency: $ (5,704.00)
Hensel Phelps Construction is committed to 20% MWBE and 4% LDB participation
for Construction Services. The subcontractors identified and committed to
participated on BP-S00143 (GMP No. 6-S.1) for these subcontract modifications
are Kirlin Florida, LLC (Non-MWBE/LDB/VBE), and Randall Mechanical, Inc. (Non-
MWBE/LDB/VBE). There is no small business participation associated with the
proposed modifications.
Minutes of the Construction Committee Meeting, June 3, 2020
Page 16 of 41
Agenda Item Nos. 2-A, 2-B, 2-C, 2-D, 2-E, 2-F, 2-G, 2-H, 2-I, 2-J, 2-K, 2-L,
2-M, 2-N, 2-O, 2-P, 2-Q, 2-R, 2-S, 2-T, 2-U, 2-V, 2-W, 2-X, 2-Y, 2-Z, 2-AA,
2-BB, and 2-CC were considered in one motion.
Upon motion of Mr. Patterson, second by Mr. Hunt, vote carried by roll-call,
with all votes yea, to approve Hensel Phelps Construction to issue a
Subcontract Modification on BP-S00143, South Terminal C, Phase 1 - Airside
Terminal, Structure and Enclosure (GMP No. 6-S.1), for the total amount of
$5,704.00, which includes the lump sum amount of $626.00 to Kirlin Florida,
LLC; and the lump sum amount of $5,078.00 to Randall Mechanical, Inc.; with
funding from Passenger Facility Charges and General Airport Revenue Bonds.
L. Subcontract Modifications for BP-S00143 (GMP No. 6-S.1) with T&T Construction of Central Fla., Inc.; Banker Steel Co., LLC; Kirlin Florida, LLC; and Randall
Mechanical, Inc.; for CR0469.1-6S1-RFI 0818 Series-Ramp Level Floor Fire
Dampers without Floors (CWA BP-S143-016). Mr. Corthell presented the
memorandum, requesting approval for Hensel Phelps Construction (HPC) to issue
Subcontract Modifications on BP-S00143, South Terminal C, Phase 1 - Airside
Terminal, Structure and Enclosure (GMP No. 6-S.1), at the Orlando International
Airport, in the total amount of $134,190.00 to T&T Construction of Central
Fla., Inc.; Banker Steel Co., LLC; Kirlin Florida, LLC; and Randall Mechanical,
Inc.; for CR0469.1-6S1-RFI 0818 Series-Ramp Level Floor Fire Dampers without
Floors (CWA BP-S143-016).
Bid Package 03.02 "Building Concrete" has been previously awarded within GMP
No. 6-S.1 to T&T Construction of Central Fla., Inc., CC No. 201800410.008.
Bid Package for BP-S143 05.01 "Structural Steel and Miscellaneous Metals" has
been previously awarded within GMP No. 6-S.1 to Banker Steel Co., LLC, CC
No. 20180410.008.
Bid Package for BP-S00143 23.01 "FIVAC" has been previously awarded within GMP
No. 6-S.1 to Randall Mechanical, Inc., CC No. 20180410.008.
Bid Package 22.01 "Plumbing" has been previously awarded within GMP No. 6-S.1
to Kirlin Florida, LLC, CC No. 20180522.04H.
HPC is requesting to issue the following Subcontractor Modifications to;
1. T&T Construction of Central Fla., Inc. in the Lump Sum amount of
$8,767.00 for CR0469.1-6S1-RFI 0818 Series. The modified scope of work
consists of the costs associated with the reinforcement and the Light-
weight concrete infill of two Slab-on-Metal-Deck (SOMD) in Areas 14 and
24.
2. Banker Steel Co., LLC in the Lump Sum amount of $101,056.00 for CR0469.1-6S1-RFI 0818 Series. The modified scope of work consists of the
detailing, material, fabrication, and erection costs associated with the
additional Structural Steel (beams, channels, angles, plates and metal
deck) for the two SOMD added in Areas 14 and 24.
3. Kirlin Florida, LLC in the Lump Sum amount of $7,246.00 for CR0469.1-6S1-RFI 0818 Series. The modified scope of work consists of all costs
associated with core-drilling and fire-stopping pipe penetrations at the
added ceilings in the chases in Areas 14, 17, and 25.
4. Randall Mechanical, Inc. in the Lump Sum amount of $17,121.00 for
CR0469.1-6S1-RFI 0818 Series. The modified scope of work consists of all
Minutes of the Construction Committee Meeting, June 3, 2020
Page 17 of 41
costs associated with the added fire dampers and access doors due to the
added ceilings in chases in Areas 14, 17, and 25.
HPC will submit Time Impact Analysis (TIA-079) requesting additional time
associated with this scope of work of RFI 0818 Series.
The approval of these Subcontractor Modifications to T&T Construction of
Central Fla., Inc.; Banker Steel Co., LLC; Kirlin Florida, LLC; and Randall
Mechanical, Inc.; resolves all requests for costs resulting from RFI 0818
Series in GMP No. 6-S.1 and closes out CWA BP-S143-016, which covered only the
additional structural steel costs as set forth in CR0469.1. Cost impacts to
GMP No. 6-S.2 were approved via CC No. 20200218.003H (CR0469.2-6S2-0069). Cost
impacts for Drawing Areas 15, 16, 18, 19, 20, 21, 22, 23, 24, 26, 27, 28, 29,
30, 31, 32 and 33, included in the responses to RFI 0818 Series, if any, will
be submitted in a future CR. There are no cost impacts to GMP Nos. 6-S, 6-S.3,
6-S.4 and 6-S.5. The OAR will evaluate TIA-079 and anytime recommended to be
granted will be submitted at a future CCM.
HPC has submitted documentation including the subcontractor's proposal to
support this request. An independent cost estimate is included. By approving
this request, the Owner does not waive its right to enforce the contract
requirements for other requests for cost or time.
The effect of this Subcontract Modification for this project is as follows:
HPC to issue a subcontract modification to T&T
Construction of Central Fla., Inc. in the lump sum
amount of: $ 8,767.00
HPC to issue a subcontract modification to Banker
Steel Co., LLC in the lump sum amount of: $ 101,056.00
HPC to issue a subcontract modification to Kirlin
Florida, LLC in the lump sum amount of: $ 7,246.00
HPC to issue a subcontract modification to Randall
Mechanical, Inc. in the lump sum amount of: $ 17,121.00
Deduct from P1 Owner Contingency: $ (134,190.00)
Hensel Phelps Construction is committed to 20% MWBE and 4% LDB participation
for Construction Services. The subcontractors identified and committed to
participate on BP-S00143 (GMP No. 6-S.1) for these subcontract modifications
are T&T Construction of Central Florida, Inc. (MWBE); Banker Steel Co., LLC
(Non-MWBE/LDB/VBE); Kirlin Florida, LLC (Non-MWBE/LDB/VBE); and Randall
Mechanical, Inc. (Non-MWBE/LDB/VBE). There is an overall 6.5% MWBE
participation associated with the proposed modifications.
Agenda Item Nos. 2-A, 2-B, 2-C, 2-D, 2-E, 2-F, 2-G, 2-H, 2-I, 2-J, 2-K, 2-L,
2-M, 2-N, 2-O, 2-P, 2-Q, 2-R, 2-S, 2-T, 2-U, 2-V, 2-W, 2-X, 2-Y, 2-Z, 2-AA,
2-BB, and 2-CC were considered in one motion.
Upon motion of Mr. Patterson, second by Mr. Hunt, vote carried by roll-call,
with all votes yea, to approve Hensel Phelps Construction to issue Subcontract
Modifications on BP-S00143, South Terminal C, Phase 1 - Airside Terminal,
Structure and Enclosure (GMP No. 6-S.1), for the total amount of $134,190.00,
which includes the lump sum amount of $8,767.00 to T&T Construction of Central
Fla., Inc.; the lump sum amount of $101,056.00 to Banker Steel Co., LLC; the
lump sum amount of $7,246.00 to Kirlin Florida, LLC; and, the lump sum amount
of $17,121.00 to Randall Mechanical, Inc.; with funding from Passenger Facility
Charges and General Airport Revenue Bonds.
Minutes of the Construction Committee Meeting, June 3, 2020
Page 18 of 41
M. Subcontract Modifications for BP-S00144 (GMP No. 6-S.2) with Wal-Mark
Contracting Group, LLC; and BergElectric Corp. dba Bergelectric Corp.
Contractors and Engineers for CR0492.2-6S2-RFI 2005 Doors/Walls Fire Rating
Re-classification (CWA BP-S144-005). Mr. Corthell presented the memorandum,
requesting approval for Hensel Phelps Construction (HPC) to issue Subcontract
Modifications on BP-S00144, South Terminal C, Phase 1 - Airside Enclosure and
Exterior Finishes (GMP No. 6-S.2), at the Orlando International Airport, in
the total amount of $32,848.00 to Wal-Mark Contracting Group, LLC; and
BergElectric Corp. dba Bergelectric Corp. Contractors and Engineers; for
CR0492.2-6S2-RFI 2005 Doors/Walls Fire Rating Re-classification (CWA BP-S144-
005). Bid Package for 09.02 "Framing and Drywall" and Bid Package for 26.01
"ASC Electrical Systems" have been previously awarded within GMP No. 6-S.2 to
Wal-Mark Contracting Group LLC and BergElectric Corp. dba Bergelectric Corp.
Contractors and Engineers, respectively, CC No. 20180605.006.
The response to RFI 2005 changed the rating of multiple interior walls for
electrical rooms from 1-hour to 2-hour since the City of Orlando approved an
equivalency request for this instead of having emergency fire sprinklers in
the electrical rooms. This elevated rating requires the thickness of the wall
assembly to be increased. CWA BP-S144-005 was issued for the scope of work in
Electrical Room 02-0211 only. HPC is requesting to issue the following
Subcontractors Modifications to;
1. Wal-Mark Contracting Group LLC in the Lump Sum amount of $23,721.00 for CR0492.2-6S2-RFI 2005 Doors/Walls Fire Rating Reclassification. The
modified scope of work consists of the costs associated with the
installation and finishing of additional layers of drywall on walls of
Electrical Rooms 02-0211 and 02-0524X and firestopping to achieve UL
U408 rating in Room 02-0211.
2. BergElectric Corp. dba Bergelectric Corp. Contractors and Engineers in the Lump Sum amount of $9,127.00 for CR0492.2-6S2-RFI 2005 Doors/Walls
Fire Rating Re-classification. The modified scope of work consists of
the costs associated with removing and re-installing the existing wall-
mounted conduit and devices in Electrical Room 02-0211 to allow for wall
rating to be upgraded.
The approval of these Subcontractor Modifications to Wal-Mark Contracting
Group LLC; and BergElectric Corp. dba Bergelectric Corp. Contractors and
Engineers; resolves all requests for cost and time resulting from RFI 2005
scope of work in GMP No. 6-S.2 and closes out CWA BP-S144-005. Cost impacts
of RFI 2005 to GMP No. 6-S.4 were approved via CC No. 20200505.002T. Cost
impacts of RFI 2005 to GMP No. 6-S.1 will be submitted in a future CR. Costs
for patching of fireproofing, if any, will be submitted in a future CR. There
are no cost or time impacts to GMP No. 6-S, 6-S.3, and 6-S.5.
HPC has submitted documentation including the subcontractor's proposal to
support this request. An independent cost estimate is included. By approving
this request, the Owner does not waive its right to enforce the contract
requirements for other requests for cost or time.
Minutes of the Construction Committee Meeting, June 3, 2020
Page 19 of 41
The effect of this Subcontract Modification for this project is as follows:
HPC to issue a subcontract modification to Wal-Mark
Contracting Group, LLC in the lump sum amount of: $ 23,721.00
HPC to issue a subcontract modification to
BergElectric Corp. dba Bergelectric Corp.
Contractors and Engineers in the lump sum amount of: $ 9,127.00
Deduct from P1 Owner Contingency: $ (32,848.00)
Hensel Phelps Construction is committed to 20% MWBE and 4% LDB participation
for Construction Services. The subcontractors identified and committed to
participate on BP-S00144 (GMP No. 6-S.2) for these subcontract modifications
are Wal-Mark Contracting Group, LLC (Non-MWBE/LDB/VBE); and BergElectric Corp.
dba Bergelectric Corp. Contractors and Engineers (Non-MWBE/LDB/VBE). There is
no small business participation associated with the proposed modifications.
Agenda Item Nos. 2-A, 2-B, 2-C, 2-D, 2-E, 2-F, 2-G, 2-H, 2-I, 2-J, 2-K, 2-L,
2-M, 2-N, 2-O, 2-P, 2-Q, 2-R, 2-S, 2-T, 2-U, 2-V, 2-W, 2-X, 2-Y, 2-Z, 2-AA,
2-BB, and 2-CC were considered in one motion.
Upon motion of Mr. Patterson, second by Mr. Hunt, vote carried by roll-call,
with all votes yea, to approve Hensel Phelps Construction to issue Subcontract
Modifications on BP-S00144, South Terminal C, Phase 1 - STC Airside Enclosure
and Exterior Finishes (GMP No. 6-S.2), for the total lump sum amount of
$32,848.00, which includes the lump sum amount of $23,721.00 to Wal-Mark
Contracting Group, LLC; and the lump sum amount of $9,127.00 to BergElectric
Corp. dba Bergelectric Corp. Contractors and Engineers; with funding from
Passenger Facility Charges and General Airport Revenue Bonds.
N. Subcontractor Modification for BP-S00146 (GMP No. 7-S) with Randall Mechanical, Inc. for CR0138.1-LST-Cancel Subcontract Award for Early Mechanical
Coordination. Mr. Corthell presented the memorandum, requesting approval for
Turner-Kiewit Joint Venture (TKJV) to issue a Subcontract Modification on BP-
S00146, South Terminal C, Phase 1 - Landside Terminal, Structure and Enclosure
(GMP No. 7-S), at the Orlando International Airport, in the total deductive
amount of ($100,000.00) to Randall Mechanical, Inc. for CR0138.1-LST-Cancel
Subcontract Award for Early Mechanical Coordination. Bid Package for BP-S146
"Landside Terminal Structure and Enclosure" was previously awarded within GMP
No. 7-S to Turner-Kiewit Joint Venture (TKJV) CC No. 20180313.010. CR0138 for
"Mechanical Coordination Limited Scope Early Work Release" was previously
awarded to Randall Mechanical, Inc. CC No. 20181002.E
The scope included in the Randall Mechanical, Inc. subcontract award was
removed from GMP No. 7-S. TKJV is proposing a budget reallocation to cancel
the subcontract award to Randall Mechanical, Inc. in the deductive lump sum
amount of ($100,000.00) for CR0138.1-LST-Cancel Subcontract Awards for Early
and Mechanical Coordination. This amount will be reallocated to Phase 1 Owner
Contingency.
The effect of this Subcontractor Modification for this project is as follows:
TKJV to issue a subcontract modification to Randall
Mechanical, Inc. in the deductive lump sum amount of: $ (100,000.00)
Add to Owner Contingency: $ 100,000.00
Turner-Kiewit Joint Venture is committed to 20% MWBE and 4% LDB participation
for Construction Services. The subcontractors identified and committed to
participate on BP-S00146 (GMP No. 7-S) for these subcontract modifications are
Minutes of the Construction Committee Meeting, June 3, 2020
Page 20 of 41
Randall Mechanical, Inc. (Non-MWBE/LDB/VBE) and M.C. Dean, Inc. (Non-
MWBE/LDB/VBE). There is no small business participation associated with the
proposed modifications.
Agenda Item Nos. 2-A, 2-B, 2-C, 2-D, 2-E, 2-F, 2-G, 2-H, 2-I, 2-J, 2-K, 2-L,
2-M, 2-N, 2-O, 2-P, 2-Q, 2-R, 2-S, 2-T, 2-U, 2-V, 2-W, 2-X, 2-Y, 2-Z, 2-AA,
2-BB, and 2-CC were considered in one motion.
Upon motion of Mr. Patterson, second by Mr. Hunt, vote carried by roll-call,
with all votes yea, to approve Turner-Kiewit Joint Venture to issue a
Subcontractor Modification to Randall Mechanical, Inc. on BP-S00146, South
Terminal C, Phase 1 - Landside Terminal, Structure and Enclosure (GMP No.
7-S), for the total deductive lump sum amount of ($100,000.00), with funding
credited to Passenger Facility Charges and General Airport Revenue Bonds.
O. Budget Reallocations for BP-S00146 (GMP No. 7-S) for CR0884-LST-Budget
Reallocations from Unbought Scope and Allowance Items to Phase 1 Contingencies.
Mr. Corthell presented the memorandum, requesting approval for Turner-Kiewit
Joint Venture (TKJV) to issue Budget Reallocations on BP-S00146, South Terminal
C, Phase 1 - Landside Terminal, Structure and Enclosure (GMP No. 7-S), at the
Orlando International Airport, in the total amount of $2,073,650.00 for CR0884-
LST-Budget Reallocations from Unbought Scope and Allowance Items to Phase 1
Contingencies. Bid Package for BP-S00146 Landside Terminal Structures and
Enclosure was previously awarded within GMP No. 7-S to TKJV, CC No.
20180313.010
TKJV is proposing the following budget reallocations:
1. $595,210.00 from GMP No. 7-S Line Item 5 to P1 CM@R Contingency. 2. $1,165,419.00 from GMP No. 7-S Line Item 6 to P1 CM@R Contingency. 3. $269,221.00 from GMP No. 7-S Line Item 9 to P1 CM@R Contingency. 4. $43,800.00 from GMP No. 7-S Line Item 16 to P1 Owner Contingency.
The effect of these Budget Reallocations for this project is as follows:
Current GMP No. 7-S Line Item 5 value: $ (595,210.00)
Add to P1 CM@R Contingency: $ 595,210.00
Remaining GMP No. 7-S Line Item 5 balance: $ 0.00
Current GMP No. 7-S Line Item 6 value: $ (1,165,419.00)
Add to P1 CM@R Contingency: $ 1,165,419.00
Remaining GMP No. 7-S Line Item 6 balance: $ 0.00
Current GMP No. 7-S Line Item 9 value: $ (269,221.00)
Add to P1 CM@R Contingency: $ 269,221.00
Remaining GMP No. 7-S Line Item 9 balance: $ 0.00
Current GMP No. 7-S Line Item 16 value: $ (43,800.00)
Add to P1 Owner Contingency: $ 43,800.00
Remaining GMP No. 7-S Line Item 16 balance: $ 0.00
The Office of Small Business Development has determined that the proposed
budget reallocations do not have any impact on the small business
participation.
Agenda Item Nos. 2-A, 2-B, 2-C, 2-D, 2-E, 2-F, 2-G, 2-H, 2-I, 2-J, 2-K, 2-L,
2-M, 2-N, 2-O, 2-P, 2-Q, 2-R, 2-S, 2-T, 2-U, 2-V, 2-W, 2-X, 2-Y, 2-Z, 2-AA,
2-BB, and 2-CC were considered in one motion.
Minutes of the Construction Committee Meeting, June 3, 2020
Page 21 of 41
Upon motion of Mr. Patterson, second by Mr. Hunt, vote carried by roll-call,
with all votes yea, to approve Turner-Kiewit Joint Venture to issue Budget
Reallocations on BP-S00146, South Terminal C, Phase 1 - Landside Terminal,
Structure and Enclosure (GMP No. 7-S), for the total amount of $2,073,650.00,
with funding from Passenger Facility Charges and General Airport Revenue Bonds.
P. Subcontractor Modification for BP-S00146 (GMP No. 7-S) with Banker Steel Co., LLC for CR0959-LST-RFI 3962 Header Beam in Early Baggage Storage (EBS) Room.
Mr. Corthell presented the memorandum, requesting approval for Turner-Kiewit
Joint Venture (TKJV) to issue a Subcontract Modification on BP-S00146, South
Terminal C, Phase 1 - Landside Terminal, Structure and Enclosure (GMP No.
7-S), at the Orlando International Airport, in the total amount of $20,541.00
to Banker Steel Co., LLC for CR0959-LST-RFI 3962 Header Beam in Early Baggage
Storage (EBS) Room. Bid Package 5.0.0 "Structural Steel" was previously
awarded within GMP No. 7-S to Banker Steel Co. LLC, CC No. 20180313.010.
TKJV is proposing a subcontract modification to Banker Steel Co., LLC in the
total lump sum amount of $20,541.00 for CR0959-LST-RFI 3962 Header Beam in
Early Baggage Storage (EBS) Room. The modified scope of work consists of
necessary labor, material, equipment, and detailing costs for the installation
of an additional 0.73 tons of structural steel to support temporary wall
opening at Northwest Early Baggage Storage (EBS) Room, per RFI 3962.
The approval of this subcontract modification to Banker Steel Co., LLC resolves
all requests for cost and time associated with RFI 3962 scope of work in GMP
No. 7-S. Cost impacts to GMP No. 7-S.1 will be submitted for CCM review under
CR0959.1. There are no cost impacts to GMP Nos. 7-S.2, 7-S.3 and 7-S.4.
TKJV has submitted documentation including the subcontractor's proposal to
support their request. An independent cost estimate is included. By approving
this request, the Owner does not waive its right to enforce the contract
requirements for other requests for cost or time.
The effect of this Subcontractor Modification for this project is as follows:
TKJV to issue a subcontract modification to Banker
Steel Co., LLC in the lump sum amount of: $ 20,541.00
Deduct from P1 Owner Contingency: $ (20,541.00)
Turner-Kiewit Joint Venture is committed to 20% MWBE and 4% LDB participation
for Construction Services. The subcontractor identified and committed to
participate on BP-S00146 (GMP No. 7-S) for this subcontract modification is
Banker Steel Co., LLC (Non-MWBE/LDB/VBE). There is no small business
participation associated with this modification.
Agenda Item Nos. 2-A, 2-B, 2-C, 2-D, 2-E, 2-F, 2-G, 2-H, 2-I, 2-J, 2-K, 2-L,
2-M, 2-N, 2-O, 2-P, 2-Q, 2-R, 2-S, 2-T, 2-U, 2-V, 2-W, 2-X, 2-Y, 2-Z, 2-AA,
2-BB, and 2-CC were considered in one motion.
Upon motion of Mr. Patterson, second by Mr. Hunt, vote carried by roll-call,
with all votes yea, to approve Turner-Kiewit Joint Venture to issue a
Subcontractor Modification to Banker Steel Co., LLC on BP-S00146, South
Terminal C, Phase 1 - Landside Terminal, Structure and Enclosure (GMP No.
7-S), for the total lump sum amount of $20,541.00, with funding from Passenger
Facility Charges.
Minutes of the Construction Committee Meeting, June 3, 2020
Page 22 of 41
Q. Subcontract Modification for BP-S00147 (GMP No. 7-S.1) with MSE2, Inc. dba Mader Southeast for CR0818-LST-RFIs 3424-3424.2 Fire-Rating at Parapet Wall.
Mr. Corthell presented the memorandum, requesting approval for Turner-Kiewit
Joint Venture (TKJV) to issue a Subcontract Modification on BP-S00147, South
Terminal C, Phase 1 - Landside Terminal Remaining Structure and Systems (GMP
No. 7-S.1), at the Orlando International Airport, in the total amount of
$14,231.00 to MSE2, Inc. dba Mader Southeast for CR0818-LST-RFIs 3424-3424.2 Fire-Rating at Parapet Wall. Bid Package 9.1.0 "Drywall and Framing" was
previously awarded within GMP No. 7-S.1 to MSE2, Inc., CC No. 20181002.009.
TKJV is proposing a subcontract modification to MSE2, Inc. dba Mader Southeast
in the total lump sum amount of $14,231.00 for CR0818-LST-RFIs 3424-3424.2
Fire-Rating at Parapet Wall. The modified scope of work consists of labor and
material costs for the insulation type change from rigid insulation to
fiberglass batt insulation at the parapet walls Type EWS-02bx along Gridlines
N2 and S2, to maintain fire-rating integrity, per RFIs 3424, 3424.1 and 3424.2.
The approval of this subcontract modification to MSE2, Inc. dba Mader Southeast
resolves all requests for cost and time associated with RFIs 3424, 3424.1 and
3424.2 scope of work in GMP No. 7-S.1. There are no cost impacts to GMP Nos.
7-S, 7-S.2, 7-S.3 and 7-S.4.
TKJV has submitted documentation including the subcontractor's proposal to
support their request. An independent cost estimate is included. By approving
this request, the Owner does not waive its right to enforce the contract
requirements for other requests for cost or time.
The effect of this Subcontract Modification for this project is as follows:
TKJV to issue a subcontract modification to MSE2,
Inc. dba Mader Southeast in the amount of: $ 14,231.00
Deduct from P1 Owner Contingency: $ (14,231.00)
Turner-Kiewit Joint Venture is committed to 20% MWBE and 4% LDB participation
for Construction Services. The subcontractor identified and committed to
participate on BP-S00147 (GMP No. 7-S.1) for this subcontract modification is
MSE2, Inc. dba Mader Southeast (Non-MWBE/LDB/VBE). There is no small business
participation associated with this modification.
Agenda Item Nos. 2-A, 2-B, 2-C, 2-D, 2-E, 2-F, 2-G, 2-H, 2-I, 2-J, 2-K, 2-L,
2-M, 2-N, 2-O, 2-P, 2-Q, 2-R, 2-S, 2-T, 2-U, 2-V, 2-W, 2-X, 2-Y, 2-Z, 2-AA,
2-BB, and 2-CC were considered in one motion.
Upon motion of Mr. Patterson, second by Mr. Hunt, vote carried by roll-call,
with all votes yea, to approve Turner-Kiewit Joint Venture to issue a
Subcontract Modification to MSE2, Inc. dba Mader Southeast on BP-S00147, South
Terminal C, Phase 1 - Landside Terminal Remaining Structure and Systems (GMP
No. 7-S.1), for the total lump sum amount of $14,231.00, with funding from
Passenger Facility Charges and General Airport Revenue Bonds.
R. Subcontract Modification for BP-S00147 (GMP No. 7-S.1) with Alpha Insulation & Waterproofing, Inc. for CR0964-LST-RFIs 3436 and 3436.1 Metal Panel
Termination at Clerestory Curtain Wall. Mr. Corthell presented the memorandum,
requesting approval for Turner-Kiewit Joint Venture (TKJV) to issue a
Subcontract Modification on BP-S00147, South Terminal C, Phase 1 - Landside
Terminal Remaining Structure and Systems (GMP No. 7-S.1), at the Orlando
International Airport, in the total deductive amount of ($4,424.00) to Alpha
Insulation & Waterproofing, Inc. for CR0964-LST-RFIs 3436 and 3436.1 Metal
Panel Termination at Clerestory Curtain Wall. Bid Package 7.3.0 "Applied
Minutes of the Construction Committee Meeting, June 3, 2020
Page 23 of 41
Fireproofing" was previously awarded within GMP No. 7-S.1 to Alpha Insulation
& Waterproofing, Inc., CC No. 20181002.009.
TKJV is proposing a subcontract modification to Alpha Insulation &
Waterproofing, Inc. in the total deductive lump sum amount of ($4,424.00) for
CR0964-LST-RFIs 3436 and 3436.1 Metal Panel Termination at Clerestory Curtain
Wall. The modified scope of work consists of credits for the removal of
expansion joint flashing at Area 4 North Clerestory Wall, per RFIs 3436 and
3436.1.
The approval of this subcontract modification to Alpha Insulation &
Waterproofing, Inc. resolves all requests for cost and time associated with
RFIs 3436 and 3436.1 in GMP No. 7-S.1. There are no cost impacts to GMP Nos.
7-S, 7-S.2, 7-S.3 and 7-S.4.
TKJV has submitted documentation including the subcontractor's proposal to
support their request. An independent cost estimate is included. By approving
this request, the Owner does not waive its right to enforce the contract
requirements for other requests for cost or time.
The effect of this Subcontract Modification for this project is as follows:
TKJV to issue a subcontract modification to Alpha
Insulation & Waterproofing, Inc. in the deductive
amount of: $ (4,424.00)
Add to P1 Owner Contingency: $ 4,424.00
Turner-Kiewit Joint Venture is committed to 20% MWBE and 4% LDB participation
for Construction Services. The subcontractor identified and committed to
participate on BP-S00147 (GMP No. 7-S.1) for this subcontract modification is
Alpha Insulation & Waterproofing, Inc. (Non-MWBE/LDB/VBE). There is no small
business participation associated with this modification.
Agenda Item Nos. 2-A, 2-B, 2-C, 2-D, 2-E, 2-F, 2-G, 2-H, 2-I, 2-J, 2-K, 2-L,
2-M, 2-N, 2-O, 2-P, 2-Q, 2-R, 2-S, 2-T, 2-U, 2-V, 2-W, 2-X, 2-Y, 2-Z, 2-AA,
2-BB, and 2-CC were considered in one motion.
Upon motion of Mr. Patterson, second by Mr. Hunt, vote carried by roll-call,
with all votes yea, to approve Turner-Kiewit Joint Venture to issue a
Subcontract Modification to Alpha Insulation & Waterproofing, Inc. on BP-
S00147, South Terminal C, Phase 1 - Landside Terminal Remaining Structure and
Systems (GMP No. 7-S.1), for the total deductive amount of ($4,424.00), with
funding from Passenger Facility Charges and General Airport Revenue Bonds.
S. Subcontract Modification for BP-S00150 (GMP No. 9-S) with Cives Corp. dba Cives Steel Company - Southern Division for CR01020-9S-PKG-RFIs 3681-3681.1-
Revised Gutter Detail at Promenade Canopy around Drains. Mr. Corthell
presented the memorandum, requesting approval for Turner-Kiewit Joint Venture
(TKJV) to issue a Subcontract Modification on BP-S00150, South Terminal C,
Phase 1, Parking Facility - Phase 1 (GMP No. 9-S), at the Orlando International
Airport, in the total amount of $86,096.00 to Cives Corp. dba Cives Steel
Company - Southern Division for CR01020-9S-PKG-RFIs 3681-3681.1-Revised Gutter
Detail at Promenade Canopy around Drains. Bid Package 5.0.0 "Structural Steel
and Metal Deck" was previously awarded within GMP No. 9-S to Cives Corp. dba
Cives Steel Company - Southern Division, CC No. 20171010.016.
TKJV is proposing a subcontract modification to Cives Corp. dba Cives Steel
Company - Southern Division in the total lump sum amount of $86,096.00 for
CR01020-9S-PKG-RFIs 3681-3681.1-Revised Gutter Detail at Promenade Canopy
Minutes of the Construction Committee Meeting, June 3, 2020
Page 24 of 41
around Drains. As part of the VE efforts for the canopy, the cold-formed metal
framing was not procured or included in the Canopy Award. Therefore, RFI 3681
was issued to request a detail for the gutter support steel at the lower
canopy. The RFI response provided Sketches and Detail SC/SPS.01.01. The revised
detail added plates and angles around each drain. Subsequently, RFI 3681.1 was
issued to confirm the dimension of the drain opening and it was confirmed a
6-inch diameter in lieu of 4.5-inch diameter opening. The modified scope of
work consists of all detailing, material fabrication, erection and painting
costs associated with the addition of 2.14 tons of structural steel resulting
from RFIs 3681 and 3681.1 responses.
The approval of this subcontract modification to Cives Corp. dba Cives Steel
Company - Southern Division resolves all requests for costs and time associated
with RFIs 3681 and 3681.1.
TKJV has submitted documentation including the subcontractor's proposal to
support their request. An independent cost estimate is included. By approving
this request, the Owner does not waive its right to enforce the contract
requirements for other requests for cost or time.
The effect of this Subcontract Modification for this project is as follows:
TKJV to issue subcontract modification to Cives Corp.
dba Cives Steel Company - Southern Division in the
lump sum amount of: $ 86,096.00
Deduct from CWE CM@R Contingency: $ (86,096.00)
Turner-Kiewit Joint Venture is committed to 20% MWBE and 4% LDB participation
for Construction Services. The subcontractor identified and committed to
participate on BP-S00150 (GMP No. 9-S) for this subcontract modification is
Cives Corp. dba Cives Steel Company - Southern Division (Non-MWBE/LDB). There
is no small business participation associated with this modification.
Agenda Item Nos. 2-A, 2-B, 2-C, 2-D, 2-E, 2-F, 2-G, 2-H, 2-I, 2-J, 2-K, 2-L,
2-M, 2-N, 2-O, 2-P, 2-Q, 2-R, 2-S, 2-T, 2-U, 2-V, 2-W, 2-X, 2-Y, 2-Z, 2-AA,
2-BB, and 2-CC were considered in one motion.
Upon motion of Mr. Patterson, second by Mr. Hunt, vote carried by roll-call,
with all votes yea, to approve Turner-Kiewit Joint Venture to issue a
Subcontract Modification to Cives Corp. dba Cives Steel Company - Southern
Division on BP-S00150, South Terminal C, Phase 1 - Parking Facility – Phase 1
(GMP No. 9-S), for the total lump sum amount of $86,096.00, with funding from
Customer Facility Charges.
T. Subcontract Modification for BP-S00150 (GMP No. 9-S) with Alpha Insulation & Waterproofing, Inc. for CR0995-9S-PKG-RFIs 4022-4022.2-Additional Expansion
Joints (CWA BP-S150-013). Mr. Corthell presented the memorandum, requesting
approval for Turner-Kiewit Joint Venture (TKJV) to issue a Subcontract
Modification on BP-S00150, South Terminal C, Phase 1, Parking Facility - Phase
1 (GMP No. 9-S), at the Orlando International Airport, in the total amount of
$33,492.00 to Alpha Insulation & Waterproofing, Inc. for CR0995-9S-PKG-RFIs
4022-4022.2-Additional Expansion Joints (CWA BP-S150-013). Bid Package 7.0.0
"Waterproofing" was previously awarded within GMP No. 9-S to Alpha Insulation
& Waterproofing, Inc. CC No. 20171010.16.
TKJV is proposing a subcontract modification to Alpha Insulation &
Waterproofing, Inc. in the total lump sum amount of $33,492.00 for CR0995-9S-
PKG-RFIs 4022-4022.2-Additional Expansion Joints. RFI 4022 was issued to
request details to correct the vertical expansion joint design at the
Minutes of the Construction Committee Meeting, June 3, 2020
Page 25 of 41
Elevators. This RFI provided initial information outlining extents of required
joints. RFI 4022.1 response includes the approved image markups per site walk-
through on March 9, 2020, confirming the scope of work required at the expansion
joints. RFI 4022.2 was issue to confirm the removal of the metal flashing for
the vertical expansion joint conditions at Gridlines GH.1/G2 and GJ/G2 on
Levels 1-5. The RFI response confirmed the installation of a vertical expansion
joint to cover the exposed opening at Gridline GJ/ G2. For Gridline GH.1/G2,
a frame/air-barrier and stucco new built-built up wall on top of existing CIP
crash wall will be installed and a vertical expansion joint will be provided
to cover the exposed opening. The modified scope of work consists of all labor,
material and equipment to install expansion control joints as indicated in the
responses to RFIs 40224022.2. Scope of work covered in this request includes
195 LF of 3-inch EM seal expansion joint (EMCS-3) and 390 LF of Silicone
sealant (0.5-inch bead at each side).
The approval of this subcontract modification to Alpha Insulation &
Waterproofing, Inc. resolves all requests for cost and time associated with
RFIs 4022-4022.2 for GMP No. 9-S. Costs for GMP No. 9-S.1 will be submitted
under CR0995.1 and closes CWA BP-S150-013.
TKJV has submitted documentation including the subcontractor's proposal to
support their request. An independent cost estimate is included. By approving
this request, the Owner does not waive its right to enforce the contract
requirements for other requests for cost or time.
The effect of this Subcontract Modification for this project is as follows:
TKJV to issue subcontract modification to Alpha
Insulation & Waterproofing, Inc. in the lump sum
amount of: $ 33,492.00
Deduct from Owner Contingency: $ (14,506.00)
Deduct from CM@R Contingency: $ (14,506.00)
Deduct from CWE CM@R Contingency: $ (4,480.00)
Turner-Kiewit Joint Venture is committed to 20% MWBE and 4% LDB participation
for Construction Services. The subcontractor identified and committed to
participate on BP-S00150 (GMP No. 9-S) for this subcontract modification is
Alpha Insulation & Waterproofing, Inc. (Non-MWBE/LDB/VBE). There is no small
business participation associated with this modification.
Agenda Item Nos. 2-A, 2-B, 2-C, 2-D, 2-E, 2-F, 2-G, 2-H, 2-I, 2-J, 2-K, 2-L,
2-M, 2-N, 2-O, 2-P, 2-Q, 2-R, 2-S, 2-T, 2-U, 2-V, 2-W, 2-X, 2-Y, 2-Z, 2-AA,
2-BB, and 2-CC were considered in one motion.
Upon motion of Mr. Patterson, second by Mr. Hunt, vote carried by roll-call,
with all votes yea, to approve Turner-Kiewit Joint Venture to issue a
Subcontract Modification to Alpha Insulation & Waterproofing, Inc. on BP-
S00150, South Terminal C, Phase 1 - Parking Facility - Phase 1 (GMP No. 9-S),
for the total lump sum amount of $33,492.00, with funding from Customer
Facility Charges and General Airport Revenue Bonds.
U. Subcontract Modification for BP-S00156 (GMP No. 14-S) with Five Arrows, Inc. OBA Service Painting Corporation for CR01063-14S-CEP-RFI 4394-CEP Diagonal
Beam Paint and CEP Concrete Inertia Bases Paint. Mr. Corthell presented the
memorandum, requesting approval for Turner-Kiewit Joint Venture (TKJV) to
issue a Subcontract Modification on BP-S00156, South Terminal C, Phase 1 - CEP
and EPG Buildings (GMP No. 14-S), at the Orlando International Airport, in the
total amount of $1,573.00 to Five Arrows, Inc. dba Service Painting Corporation
for CR01063-14S-CEP-RFI 4394-CEP Diagonal Beam Paint and CEP Concrete Inertia
Minutes of the Construction Committee Meeting, June 3, 2020
Page 26 of 41
Bases Paint. Bid Package 9.5.0 "Epoxy Flooring and Paint" was previously
awarded within GMP No. 14-S to Five Arrows, Inc. dba Service Painting
Corporation, CC No. 20180807.011.
TKJV is proposing a subcontract modification to Five Arrows, Inc. dba Service
Painting Corporation in the total lump sum amount of $1,573.00 CR01063-14S-
CEP-RFI 4394-CEP Diagonal Beam Paint and CEP Concrete Inertia Bases Paint.
RFI 4394 was issued to request if it was acceptable to remove a diagonal brace
located at Column Line CG/C2.3 to meet ADA requirements, or in the alternative
if it could not be removed, to paint the diagonal brace yellow. RFI 4394
response stated the ADA requirements were not applicable in this situation,
the brace could not be removed, and it was acceptable to paint it yellow.
As construction progressed, TKJV discovered a gap in scope coverage concerning
priming/painting six inertia bases located on top of the housekeeping pads
supporting the Chilled Water Pumps in the CCP of the CEP. During the bidding
phase of the project, it was not identified that the inertia bases were
required to be painted, only the housekeeping pads. The modified scope of work
in this request consists of all labor and material costs associated with the
painting of diagonal brace at Column Line CG/C2.3, per RFI 4394, and the
painting of six concrete inertia bases with Armor Seal 8100 Tile Red Paint.
The approval of this subcontract modification to Five Arrows, Inc. dba Service
Painting Corporation resolves all requests for costs and time resulting from
RFI 4394 and the CEP concrete inertia bases painting scope of work.
TKJV has submitted documentation including the subcontractor's proposal to
support their request. An independent cost estimate is included. By approving
this request, the Owner does not waive its right to enforce the contract
requirements for other requests for cost or time.
The effect of this Subcontract Modification for this project is as follows:
TKJV to issue a subcontract modification to Five Arrows,
Inc. dba Service Painting Corporation in the lump sum
amount of: $ 1,573.00
Deduct from Pl CEP CM@R Contingency: $ (1,573.00)
Turner-Kiewit Joint Venture is committed to 20% MWBE and 4% LDB participation
for Construction Services. The subcontractor identified and committed to
participate on BP-S00156 (GMP No. 14-S) for this subcontract modification is
Five Arrows, Inc. dba Service Painting Corporation (Non-MWBE/LDB/VBE). There
is no small business participation associated with this modification.
Agenda Item Nos. 2-A, 2-B, 2-C, 2-D, 2-E, 2-F, 2-G, 2-H, 2-I, 2-J, 2-K, 2-L,
2-M, 2-N, 2-O, 2-P, 2-Q, 2-R, 2-S, 2-T, 2-U, 2-V, 2-W, 2-X, 2-Y, 2-Z, 2-AA,
2-BB, and 2-CC were considered in one motion.
Upon motion of Mr. Patterson, second by Mr. Hunt, vote carried by roll-call,
with all votes yea, to approve Turner-Kiewit Joint Venture to issue a
Subcontract Modification to Five Arrows, Inc. dba Service Painting Corporation
on BP-S00156, South Terminal C, Phase 1 - CEP and EPG Buildings (GMP No.
14-S), for the total lump sum amount of $1,573.00, with funding from Passenger
Facility Charges and General Airport Revenue Bonds.
Minutes of the Construction Committee Meeting, June 3, 2020
Page 27 of 41
V. Subcontractor Modification for BP-S00163 (GMP No. 5-S.5) with The Middlesex Corporation for CR0645-5S.5-LSC-Bridge Inverted T-Cap Cut Rebar Investigation.
Mr. Corthell presented the memorandum, requesting approval for Turner-Kiewit
Joint Venture (TKJV) to issue a Subcontract Modification on BP-S00163, South
Terminal C, Phase 1 - Enplane/Deplane Bridge and Roadways (GMP No. 5-S.5), at
the Orlando International Airport, in the total amount of $18,805.00 to The
Middlesex Corporation for CR0645-5S.5-LSC-Bridge Inverted T-Cap Cut Rebar
Investigation. Bid Package 34.0.0 "Enplane/ Deplane Bridge-Combined Piers and
Piles" was previously awarded within GMP No. 5-S.5 "Enplane/ Deplane Bridge
and Roadways Balance of Work - FDOT" to The Middlesex Corporation, CC No.
20180605.007.
TKJV is proposing a subcontract modification to The Middlesex Corporation in
the total lump sum amount of $18,805.00 for CR0645-5S.5-LSC-Bridge Inverted
T-Cap Cut Rebar Investigation. At the rebar cage of Pier 11 Level 2 Inverted
T-Cap, multiple bars within the ledges were found to be incorrectly cut while
performing a routine check. These bars were cut on the north and south edges
where the ledges are in line with the columns that support the cap (4 areas
total). Due to these findings, the OAR and CM@R held a meeting on August 14,
2019, and agreed that an investigation of the previously installed inverted
T-Cap rebar should be performed. This testing and inspection was necessary to
alleviate significant concerns about bridge piers that were placed and stripped
and to confirm the improperly installed rebar was an isolated instance. The
OAR and CM@R agreed this was a buyout issue because this level of testing and
inspection was not required per the specifications and therefore not purchased
with the CM@R's third-party quality control package. A specialist was brought
in to scan and x-ray the other inverted T-Cap rebar. The conclusion of the
investigation was that the other caps were constructed properly, per plan and
specifications. The scope of work consists of all labor and equipment costs
provided by The Middlesex Corporation to support the x-ray investigation and
costs to chip concrete for visual inspection to confirm proper installation
of reinforcing steel.
The approval of this subcontract modification to The Middlesex Corporation
resolves all requests for cost and time resulting from CR0645-5S.5-LSC-Bridge
Inverted T-Cap Cut Rebar Investigation.
TKJV has submitted the subcontractor's proposal to support this request. An
independent cost Review is included. By approving this request, the Owner does
not waive its right to enforce the contract requirements for other requests
for cost or time.
The effect of this Subcontractor Modification for this project is as follows:
TKJV to issue a subcontract modification to The
Middlesex Corporation in the lump sum amount of (LSC
Bulletin 23 and RFI 2397): $ 18,805.00
Deduct from P1 CM@R Contingency: $ (18,805.00)
Due to the funding source of this GMP No. 5-S.5, Turner-Kiewit Joint Venture
proposed a 20% DBE participation goal for Bid Package 34.0.0 Enplane/Deplane
Bridge and Roadways Balance of Work - FDOT, in lieu of MWBE and LDB
participation goals. As such, Turner-Kiewit Joint Venture’s committed MWBE
and LDB Construction Services goals are not affected by this modification. The
subcontractor identified and committed to participate on BP-S00163 (GMP No.
5-S.5) for this subcontract modification is The Middlesex Corporation (Non-
DBE). There is no small business participation associated with this
modification.
Minutes of the Construction Committee Meeting, June 3, 2020
Page 28 of 41
Agenda Item Nos. 2-A, 2-B, 2-C, 2-D, 2-E, 2-F, 2-G, 2-H, 2-I, 2-J, 2-K, 2-L,
2-M, 2-N, 2-O, 2-P, 2-Q, 2-R, 2-S, 2-T, 2-U, 2-V, 2-W, 2-X, 2-Y, 2-Z, 2-AA,
2-BB, and 2-CC were considered in one motion.
Upon motion of Mr. Patterson, second by Mr. Hunt, vote carried by roll-call,
with all votes yea, to approve Turner-Kiewit Joint Venture to issue a
Subcontractor Modification to The Middlesex Corporation on BP-S00163, South
Terminal C, Phase 1 - Enplane/Deplane Bridge and Roadways (GMP No. 5-S.5), for
the total lump sum amount of $18,805.00, with funding from General Airport
Revenue Bonds.
W. Subcontractor Modification for BP-S00170 (GMP No. 5-S.6) with Kiewit
Infrastructure South Co. for CR0542.1-LSC-Bulletin 20 Changes to the Primary
Power Distribution (PPD). Mr. Corthell presented the memorandum, requesting
approval for Turner-Kiewit Joint Venture (TKJV) to issue a Subcontract
Modification on BP-S00170, South Terminal C, Phase 1 - Underground Electrical
Distribution (GMP No. 5-S.6), at the Orlando International Airport, in the
total amount of $253,924.00 to Kiewit Infrastructure South Co., for CR0542.1-
LSC-Bulletin 20 Changes to the Primary Power Distribution (PPD). Bid Package
26.0.0 "North Section" was previously awarded within GMP No. 5-S.6 to Kiewit
Infrastructure South Co., CC No. 20180605.08.
TKJV is proposing a subcontract modification to Kiewit Infrastructure South
Co. in the total lump sum amount of $253,924.00 for CR0542.1-LSC-Bulletin 20
Changes to the Primary Power Distribution (PPD). Landside Civil Bulletin 20
included updates to the site utility and duct bank drawings that resulted in
additional work under GMP No. 5-S.6. The modified scope of work consists of
labor, material and equipment costs associated with the additional spurs at
E32, E34, and E35; the conduit relocation; the E09 stub-up to transformer
pads; the added fence at the OUC railroad crossing; and the credits associated
with the duct bank reduction at E04, E05, and Ell.
The approval of this subcontract modification to Kiewit Infrastructure South
Co. resolves all requests for cost and time for the LSC Bulletin 020 scope of
work in GMP No. 5-S.6. All other cost and time impacts associated with LSC
Bulletin 020 were submitted in CR0542-55.2.
TKJV has submitted documentation including the subcontractor's proposal to
support this request. An independent cost estimate is included. By approving
this request, the Owner does not waive its right to enforce the contract
requirements for other requests for cost or time.
The effect of this Subcontractor Modification for this project is as follows:
TKJV to issue a subcontract modification to Kiewit
Infrastructure South Co. in the lump sum amount of: $ 253,924.00
Deduct from Pl Owner Contingency: $(253,924.00)
Turner-Kiewit Joint Venture is committed to 20% MWBE and 4% LDB participation
for Construction Services. The subcontractor identified and committed to
participate on BP-S00170 (GMP No. 5-S.6) for this subcontract modification is
Kiewit Infrastructure South Co. (Non-MWBE/LDB/VBE). There is 13.6% MWBE and
8.5% LDB participation associated with this modification.
Agenda Item Nos. 2-A, 2-B, 2-C, 2-D, 2-E, 2-F, 2-G, 2-H, 2-I, 2-J, 2-K, 2-L,
2-M, 2-N, 2-O, 2-P, 2-Q, 2-R, 2-S, 2-T, 2-U, 2-V, 2-W, 2-X, 2-Y, 2-Z, 2-AA,
2-BB, and 2-CC were considered in one motion.
Minutes of the Construction Committee Meeting, June 3, 2020
Page 29 of 41
Upon motion of Mr. Patterson, second by Mr. Hunt, vote carried by roll-call,
with all votes yea, to approve Turner-Kiewit Joint Venture to issue a
Subcontractor Modification to Kiewit Infrastructure South Co. on BP-S00170,
South Terminal C, Phase 1 - Underground Electrical Distribution (GMP
No. 5-S.6), for the total lump sum amount of $253,924.00, with funding from
General Airport Revenue Bonds.
X. Subcontractor Modification for BP-S00170 (GMP No. 5-S.6) with Kiewit
Infrastructure South Co. for CR0617-LSC-Bulletin 21 and RFI 1941.1-Changes in
Primary Power Duct Bank. Mr. Corthell presented the memorandum, requesting
approval for Turner-Kiewit Joint Venture (TKJV) to issue a Subcontract
Modification on BP-S00170, South Terminal C, Phase 1 - Underground Electrical
Distribution (GMP No. 5-S.6), at the Orlando International Airport, in the
total amount of $132,637.00 to Kiewit Infrastructure South Co., for CR0617-
LSC-Bulletin 21 and RFI 1941.1-Changes in Primary Power Duct Bank. Bid Package
26.0.0 "North Section" was previously awarded within GMP No. 5-S.6 to Kiewit
Infrastructure South Co., CC No. 20180605.08.
TKJV is proposing a subcontract modification to Kiewit Infrastructure South
Co. in the total lump sum amount of $132,637.00 for CR0617-LSC-Bulletin 21 and
RFI 1941.1-Changes in Primary Power Duct Bank. LSC Bulletin 21 changes the
layout and alignment of over 600 feet of conduit in "E run 07" and adds a new
run of 241 feet from a communications box in "E run 13". RFI 1941.1 removes
4W4 conduit from Manhole "MH-LB-23 in E run 14”. The modified scope of work
consists of all labor, material and equipment costs associated with the LSC
Bulletin 21 revisions and a credit for the 4W4 conduit removed in RFI 1941.1
response.
The approval of this subcontract modification to Kiewit Infrastructure South
Co. resolves all requests for cost and time for LSC Bulletin 21 and RFI 1941.1.
TKJV has submitted documentation including the subcontractor's proposal to
support this request. An independent cost estimate is included. By approving
this request, the Owner does not waive its right to enforce the contract
requirements for other requests for cost or time.
The effect of this Subcontractor Modification for this project is as follows:
TKJV to issue a subcontract modification to Kiewit
Infrastructure South Co. in the lump sum amount of: $ 132,637.00
Deduct from Pl Owner Contingency: $(132,637.00)
Turner-Kiewit Joint Venture is committed to 20% MWBE and 4% LDB participation
for Construction Services. The subcontractor identified and committed to
participate on BP-S00170 (GMP No. 5-S.6) for this subcontract modification is
Kiewit Infrastructure South Co. (Non-MWBE/LDB/VBE). There is 9.3% MWBE and
2.5% LDB participation associated with this modification. [Subsequent to the
meeting, the Office of Small Business Development submitted an OSBD
Participation Memorandum as Information Item 12-D on the July 21, 2020,
Construction Committee Agenda.]
Agenda Item Nos. 2-A, 2-B, 2-C, 2-D, 2-E, 2-F, 2-G, 2-H, 2-I, 2-J, 2-K, 2-L,
2-M, 2-N, 2-O, 2-P, 2-Q, 2-R, 2-S, 2-T, 2-U, 2-V, 2-W, 2-X, 2-Y, 2-Z, 2-AA,
2-BB, and 2-CC were considered in one motion.
Upon motion of Mr. Patterson, second by Mr. Hunt, vote carried by roll-call,
with all votes yea, to approve Turner-Kiewit Joint Venture to issue a
Subcontractor Modification to Kiewit Infrastructure South Co. on BP-S00170,
South Terminal C, Phase 1 - Underground Electrical Distribution (GMP
Minutes of the Construction Committee Meeting, June 3, 2020
Page 30 of 41
No. 5-S.6), for the total lump sum amount of $132,637.00, with funding from
General Airport Revenue Bonds.
Y. Subcontract Modification for BP-S00173 (GMP No. 7-S.3) with Kirlin Florida, LLC for CR1052-LST-RFI 3684 Electric Water Heater Floor Drain (EWH-FD in
Storage Room 01-664X. Mr. Corthell presented the memorandum, requesting
approval for Turner-Kiewit Joint Venture (TKJV) to issue a Subcontract
Modification on BP-S00173, South Terminal C, Phase 1, Landside Terminal, MEP
Systems - FDOT (GMP No. 7-S.3), at the Orlando International Airport, in the
total amount of $3,467.00 to Kirlin Florida, LLC for CR1052-LST-RFI 3684
Electric Water Heater Floor Drain (EWH-FD in Storage Room 01-664X. Bid Package
BP 23.0.0 "Plumbing and HVAC" was previously awarded via CR0239 to Kirlin
Florida, LLC, CC No. 20190205.02H
TKJV is proposing a subcontract modification to Kirlin Florida, LLC in the
total lump sum amount of $3,467.00 for CR1052-LST-RFI 3684 EWH FD in Storage
Room 01-664X. RFI 3684 added a floor drain for the water heater that was
added in the updated plumbing drawings issued in RFI 1824 response. The
modified scope of work consists of all costs associated with added floor
drain/trap primer, sanitary piping, below grade domestic cold water, above-
grade domestic cold water and specialties, per RFI 3684 response.
The approval of this subcontract modification to Kirlin Florida, LLC resolves
all requests for cost and time associated with RFI 3684. There are no
forthcoming CRs for any other GMPs.
TKJV has submitted documentation including the subcontractor's proposal to
support their request. An independent cost estimate is included. By approving
this request, the Owner does not waive its right to enforce the contract
requirements for other requests or cost or time.
The effect of this Subcontract Modification for this project is as follows:
TKJV to issue a subcontract modification to Kirlin
Florida, LLC in the lump sum amount of: $ 3,467.00
Deduct from P1X Owner Contingency: $ (3,467.00)
Due to the funding source of this GMP No. 7-S.3, Turner-Kiewit Joint Venture
proposed a 10% DBE participation goal for Construction Services, in lieu of
MWBE and LDB participation goals. As such, Turner-Kiewit Joint Venture’s
committed MWBE and LDB Construction Services goals are not affected by this
modification. The subcontractor identified and committed to participate on
BP-S00173 (GMP No. 7-S.3) for this subcontract modification is Kirlin Florida,
LLC (Non-MWBE/LDB/VBE). There is no small business participation associated
with this modification.
Agenda Item Nos. 2-A, 2-B, 2-C, 2-D, 2-E, 2-F, 2-G, 2-H, 2-I, 2-J, 2-K, 2-L,
2-M, 2-N, 2-O, 2-P, 2-Q, 2-R, 2-S, 2-T, 2-U, 2-V, 2-W, 2-X, 2-Y, 2-Z, 2-AA,
2-BB, and 2-CC were considered in one motion.
Upon motion of Mr. Patterson, second by Mr. Hunt, vote carried by roll-call,
with all votes yea, to approve Turner-Kiewit Joint Venture to issue a
Subcontract Modification to Kirlin Florida, LLC on BP-S00173, South Terminal
C, Phase 1, Landside Terminal, MEP Systems - FDOT (GMP No. 7-S.3), for the
amount of $3,467.00, with funding from Passenger Facility Charges and General
Airport Revenue Bonds.
Minutes of the Construction Committee Meeting, June 3, 2020
Page 31 of 41
Z. Subcontractor Modification for BP-S00178 (GMP No. 19-S) with Kiewit
Infrastructure South Co. for CR0827-AFC-Grease Traps Additional Cleanouts.
Mr. Corthell presented the memorandum, requesting approval for Turner-Kiewit
Joint Venture (TKJV) to issue a Subcontract Modification on BP-S00178, South
Terminal C, Phase 1 - Airfield Civil (GMP No. 19-S), at the Orlando
International Airport, in the total amount of $8,376.00 to Kiewit
Infrastructure South Co. for CR0827-AFC-Grease Traps Additional Cleanouts.
Bid Package 34.10.1 "Site Electrical and Communications" was previously awarded
within GMP No. 19-S to Kiewit Infrastructure South Co., CC No. 20190604.026.
TKJV is proposing a subcontract modification to Kiewit Infrastructure South
Co. in the total lump sum amount of $8,376.00 for CR0827-AFC-Grease Traps
Additional Cleanouts. CR0500 was resolved through Amendment No. 1, which
limited the Bulletin 10/11 pricing solely to the grease traps and directly
related scope. The additional cleanouts came as direction from the EOR/City
during the submittal review phase No. 22 13 19-0001. This was verified in
later design coordination meetings, to follow the typical detail provided in
the plans, Sheet C35.01.14. The modified scope of work consists of all labor,
material and equipment costs associated with adding emergency exterior
cleanouts in grease waste below grade piping not included in originally
submitted CR0500 which was resolved in GMP No. 19-S – Amendment No. 1.
The approval of this subcontract modification to Kiewit Infrastructure South
Co. resolves all requests for cost and time associated with CR0827-AFC-Grease
Traps Additional Cleanouts.
TKJV has submitted documentation including the subcontractor's proposal to
support their request. An independent cost estimate is included. By approving
this request, the Owner does not waive its right to enforce the contract
requirements for other requests for cost or time.
The effect of this Subcontractor Modification for this project is as follows:
TKJV to issue a subcontract modification to Kiewit
Infrastructure South Co. in the lump sum amount of: $ 8,376.00
Deduct from P1 Owner Contingency: $ (8,376.00)
Turner-Kiewit Joint Venture is committed to 20% MWBE and 4% LDB participation
for Construction Services. The subcontractor identified and committed to
participate on BP-S00178 (GMP No. 19-S) for this subcontract modification is
Kiewit Infrastructure South Co. (Non-MWBE/LDB). There is no small business
participation associated with this modification.
Agenda Item Nos. 2-A, 2-B, 2-C, 2-D, 2-E, 2-F, 2-G, 2-H, 2-I, 2-J, 2-K, 2-L,
2-M, 2-N, 2-O, 2-P, 2-Q, 2-R, 2-S, 2-T, 2-U, 2-V, 2-W, 2-X, 2-Y, 2-Z, 2-AA,
2-BB, and 2-CC were considered in one motion.
Upon motion of Mr. Patterson, second by Mr. Hunt, vote carried by roll-call,
with all votes yea, to approve Turner-Kiewit Joint Venture to issue a
Subcontractor Modification to Kiewit Infrastructure South, Co. on BP-S00178,
South Terminal C, Phase 1 - Airfield Civil (GMP No. 19-S), for the total lump
sum amount of $8,376.00, with funding from General Airport Revenue Bonds.
AA. Subcontractor Modification for BP-S00179 (GMP No. 6-S.6) with Liberty Conshor,
LLC for CR0515-6S6-RFI 1860 Pile Locations at Area 14 P1X NE Corner. Mr.
Corthell presented the memorandum, requesting approval for Hensel Phelps
Construction (HPC) to issue a Subcontract Modification on BP-S00179, South
Terminal C, Phase 1 - Airside Concourse (GMP No. 6-S.6), at the Orlando
International Airport, in the total amount of $12,160.00 to Liberty Conshor,
Minutes of the Construction Committee Meeting, June 3, 2020
Page 32 of 41
LLC for CR0515-6S6-RFI 1860 Pile Locations at Area 14 P1X NE Corner. Bid
Package for BP P1X 03.01 "Cast-In-Place Concrete" was previously awarded within
GMP No. 6-S.6 to Liberty Conshor, LLC, CC No. 20191029.007.
HPC is requesting to issue a Subcontract Modification to Liberty Conshor, LLC
in the total Lump Sum amount of $12,160.00 for CR0515-6S6-RFI 1860 Pile
Locations at Area 14 P1X NE Corner. The piles at the northeast corner of Area
14 for P1X could not be installed in the planned location due to the size of
the piling drilling equipment and required clearance. RFI 1860 adjusted the
locations of piles that were less than 5 feet from the face of Phase 1 Airside
Concourse Building. This subsequently required that the Pile Cap at the corner
be enlarged and deepened. The modified scope of work consists of the additional
costs associated with the Pile Cap PC4 enlargement, including the concrete,
structural steel and associated excavation and backfill, per RFI 1860 response
and sketches.
The approval of this Subcontract Modification to Liberty Conshor, LLC resolves
all requests for costs and time associated with RFI 1860 scope of work.
HPC has submitted documentation including the Subcontractor's proposal to
support this request. An independent cost estimate is included. By approving
this request, the Owner does not waive its right to enforce the contract
requirements for other requests for cost or time.
The effect of this Subcontractor Modification for this project is as follows:
HPC to issue a subcontract modification to Liberty
Conshor, LLC in the deductive lump sum amount of: $ 12,160.00
Deduct from CM@R Contingency: $ (12,160.00)
Due to the funding source of this GMP No. 6-S.6, Hensel Phelps Construction
proposed DBE participation goals per bid scope of work for Construction
Services. The subcontractor identified and committed to participate on BP-
S00179 (GMP No. 6-S.6) for this subcontract modification is Liberty Conshor,
LLC (Non-DBE/MWBE/LDB). There is 13.7% DBE participation associated with this
modification.
Agenda Item Nos. 2-A, 2-B, 2-C, 2-D, 2-E, 2-F, 2-G, 2-H, 2-I, 2-J, 2-K, 2-L,
2-M, 2-N, 2-O, 2-P, 2-Q, 2-R, 2-S, 2-T, 2-U, 2-V, 2-W, 2-X, 2-Y, 2-Z, 2-AA,
2-BB, and 2-CC were considered in one motion.
Upon motion of Mr. Patterson, second by Mr. Hunt, vote carried by roll-call,
with all votes yea, to approve Hensel Phelps Construction to issue a
Subcontractor Modification to Liberty Conshor, LLC on BP-S00179, South Terminal
C, Phase 1 - Airside Concourse (GMP No. 6-S.6), for the total lump sum amount
of $12,160.00, with funding from Passenger Facility Charges and General Airport
Revenue Bonds.
BB. Subcontractor Modification for BP-S00179 (GMP No. 6-S.6) with Randall
Mechanical, Inc. for CR0548-6S6-RFI 2270 Comments on P1X Underground Shop
Drawings (CWA BP-S179-001). Mr. Corthell presented the memorandum, requesting
approval for Hensel Phelps Construction (HPC) to issue a Subcontract
Modification on BP-S00179, South Terminal C, Phase 1 - Airside Concourse (GMP
No. 6-S.6), at the Orlando International Airport, in the total amount of
$5,829.00 to Randall Mechanical, Inc. for CR0548-6S6-RFI 2270 Comments on P1X
Underground Shop Drawings (CWA BP-S179-001). Bid Package for BP-S179 23.01A
"Fire Suppression, Plumbing and HVAC" has been previously awarded within GMP
No. 6-S.6 to Randall Mechanical, Inc., CC No. 20191029.007.
Minutes of the Construction Committee Meeting, June 3, 2020
Page 33 of 41
HPC is requesting to issue a Subcontractor Modification to Randall Mechanical,
Inc. in the total Lump Sum amount of $5,829.00 for CR0548-6S6-RFI 2270 Comments
on P1X Underground Shop Drawings. The modified scope of work consists of the
additional costs associated with the added underground piping in Areas 34 and
35, per RFI 2270 response and sketch.
The approval of this Subcontractor Modification to Randall Mechanical, Inc.
resolves all requests for costs and time associated with RFI 2270 and closes
out CWA BP-S179-001.
HPC has submitted documentation including the subcontractor's proposal to
support this request. An independent cost estimate is included. By approving
this request, the Owner does not waive its right to enforce the contract
requirements for other requests for cost or time.
The effect of this Subcontractor Modification for this project is as follows:
HPC to issue a subcontract modification to Randall
Mechanical, Inc. in the deductive lump sum amount of: $ 5,829.00
Deduct from Owner Contingency: $ (5,829.00)
Due to the funding source of this GMP No. 6-S.6, Hensel Phelps Construction
proposed DBE participation goals per bid scope of work for Construction
Services. The subcontractor identified and committed to participate on BP-
S00179 (GMP No. 6-S.6) for this subcontract modification is Randall Mechanical,
Inc. (Non-DBE/MWBE/LDB). There is no small business participation associated
with this modification.
Agenda Item Nos. 2-A, 2-B, 2-C, 2-D, 2-E, 2-F, 2-G, 2-H, 2-I, 2-J, 2-K, 2-L,
2-M, 2-N, 2-O, 2-P, 2-Q, 2-R, 2-S, 2-T, 2-U, 2-V, 2-W, 2-X, 2-Y, 2-Z, 2-AA,
2-BB, and 2-CC were considered in one motion.
Upon motion of Mr. Patterson, second by Mr. Hunt, vote carried by roll-call,
with all votes yea, to approve Hensel Phelps Construction to issue a
Subcontractor Modification to Randall Mechanical, Inc. on BP-S00179, South
Terminal C, Phase 1 - Airside Concourse (GMP No. 6-S.6), for the total lump
sum amount of $5,829.00, with funding from General Airport Revenue Bonds.
CC. Subcontractor Modification for BP-S00179 (GMP No. 6-S.6) with Liberty Conshor,
LLC for CR0574-6S6-RFI 2133 Pile Caps and Adjoining Foundations (CWA BP-S179-
002). Mr. Corthell presented the memorandum, requesting approval for Hensel
Phelps Construction (HPC) to issue a Subcontract Modification on BP-S00179,
South Terminal C, Phase 1 - Airside Concourse (GMP No. 6-S.6), at the Orlando
International Airport, in the total amount of $3,373.00 to Liberty Conshor,
LLC for CR0574-6S6-RFI 2133 Pile Caps and Adjoining Foundations (CWA BP-S179-
002). Bid Package for BP PlX 03.01 "Cast-In-Place Concrete" was previously
awarded within GMP No. 6-S.6 to Liberty Conshor, LLC, CC No. 20191029.007.
HPC is requesting to issue a Subcontract Modification to Liberty Conshor, LLC
in the total Lump Sum amount of $3,373.00 for CR0574-6S6-RFI 2133 Pile Caps
and Adjoining Foundations. RFI 2133 was written to confirm that the Elevator
and Escalator foundations at Gridlines Y44 and Y43 and adjacent Pile Caps PC2
and PCS, respectively, are to be monolithic for waterproofing purposes. The
modified scope of work consists of the costs associated with the additional
concrete mud slabs and the microcrystal line concrete waterproofing additive,
per RFI 2133 response and sketch.
Minutes of the Construction Committee Meeting, June 3, 2020
Page 34 of 41
The approval of this Subcontract Modification to Liberty Conshor, LLC resolves
all requests for costs and time associated with RFI 2133 scope of work in GMP
No. 6-S.6 and closes out (CWA BP-S179-002). Impacts of RFI 2133 to GMP No.
6-S.l will be submitted in a future CR. There are no cost impacts to GMP Nos.
6-S, 6-S.2, 6-S.3, 6-S.4, and 6-S.5.
HPC has submitted documentation including the Subcontractor's proposal to
support this request. An independent cost estimate is included. By approving
this request, the Owner does not waive its right to enforce the contract
requirements for other requests for cost or time.
The effect of this Subcontractor Modification for this project is as follows:
HPC to issue a subcontract modification to Liberty
Conshor, LLC in the lump sum amount of: $ 3,373.00
Deduct from CM@R Contingency: $ (3,373.00)
Due to the funding source of this GMP No. 6-S.6, Hensel Phelps Construction
proposed DBE participation goals per bid scope of work for Construction
Services. The subcontractor identified and committed to participate on BP-
S00179 (GMP No. 6-S.6) for this subcontract modification is Liberty Conshor,
LLC (Non-DBE/MWBE/LDB). There is no small business participation associated
with this modification. [Subsequent to the meeting, the Office of Small
Business Development submitted an OSBD Participation Memorandum as Information
Item 12-E on the July 21, 2020, Construction Committee Agenda.]
Agenda Item Nos. 2-A, 2-B, 2-C, 2-D, 2-E, 2-F, 2-G, 2-H, 2-I, 2-J, 2-K, 2-L,
2-M, 2-N, 2-O, 2-P, 2-Q, 2-R, 2-S, 2-T, 2-U, 2-V, 2-W, 2-X, 2-Y, 2-Z, 2-AA,
2-BB, and 2-CC were considered in one motion.
Upon motion of Mr. Patterson, second by Mr. Hunt, vote carried by roll-call,
with all votes yea, to approve Hensel Phelps Construction to issue a
Subcontractor Modification to Liberty Conshor, LLC on BP-S00179, South Terminal
C, Phase 1 - Airside Concourse (GMP No. 6-S.6), for the total lump sum amount
of $3,373.00, with funding from Passenger Facility Charges and General Airport
Revenue Bonds.
SOUTH TERMINAL C
REQUEST FOR RECOMMENDATION OF APPROVAL OF AMENDMENT NO. 4 TO ADDENDUM NO. 3 TO THE
CONSTRUCTION MANAGEMENT AT RISK (CM@R) ENTITY SERVICES FOR THE SOUTH TERMINAL C,
PHASE 1 AGREEMENT WITH HENSEL PHELPS CONSTRUCTION FOR BP-S00142, AIRSIDE TERMINAL
FOUNDATIONS (GMP NO. 6-S), AT THE ORLANDO INTERNATIONAL AIRPORT.
3. Mr. Corthell presented the memorandum, dated June 23, 2020, to request for
recommendation of approval of an Amendment No. 4 to Addendum No. 3 to the Construction
Management at Risk (CM@R) Entity Services for the South Terminal C, Phase 1 Agreement
with Hensel Phelps Construction for BP-S00142, Airside Terminal Foundations (GMP No.
6-S), at the Orlando International Airport.
The Program Team has evaluated the Guaranteed Maximum Price (GMP) for BP-S00142,
South Terminal C, Phase 1 - Airside Terminal Foundations (GMP No. 6-S) and determined
that it is appropriate to reduce the GMP value as indicated in the tables below as
this GMP is nearing completion and closeout:
Minutes of the Construction Committee Meeting, June 3, 2020
Page 35 of 41
GMP Original GMP
Budget
Current GMP
Budget*
Proposed GMP
Amendment
Proposed GMP
Total
Direct Cost of
Work $6,066,010.00 $20,330,675.00 $0.00. $20,330,675.00
Unbought Scope $11,940,241.00 $0.00 $0.00. $0.00
Allowances $0.00 $0.00 $0.00. $0.00
CM@R
Contingency $900,313.00 $180,260.00 ($180,260.00) $0.00
Owner
Contingency $450,156.00 $46,615.00 ($46,615.00) $0.00
P&P Bond $136,302.00 $144,766.00 ($1,598.00) $143,168.00
Fee $1,167,404.00 $1,239,826.00 ($13,683.00) $1,226,143.00
TOTAL $20,660,426.00 $21,942,142.00 ($242,156.00) $21,699,986.00
*Current GMP Budget as of CCM May 26, 2020
GMP – P1 Original GMP
Budget
Current GMP
Budget*
Proposed GMP
Amendment
Proposed GMP
Total
Direct Cost of
Work $6,066,010.00 $20,330,675.00 $0.00. $20,330,675.00
Unbought Scope $11,940,241.00 $0.00 $0.00. $0.00
Allowances $0.00 $0.00 $0.00. $0.00
CM@R
Contingency $900,313.00 $180,260.00 ($180,260.00) $0.00
Owner
Contingency $450,156.00 $46,615.00 ($46,615.00) $0.00
P&P Bond $136,302.00 $144,766.00 ($1,598.00) $143,168.00
Fee $1,167,404.00 $1,239,826.00 ($13,683.00) $1,226,143.00
TOTAL $20,660,426.00 $21,942,142.00 ($242,156.00) $21,699,986.00
*Current GMP Budget as of CCM May 26, 2020
GMP – P1X Original GMP
Budget
Current GMP
Budget*
Proposed GMP
Amendment
Proposed GMP
Total
Direct Cost of
Work $0.00 $0.00 $0.00 $0.00
Unbought Scope $0.00 $0.00 $0.00 $0.00
Allowances $0.00 $0.00 $0.00 $0.00
CM@R
Contingency $0.00 $0.00 $0.00 $0.00
Owner
Contingency $0.00 $0.00 $0.00 $0.00
P&P Bond $0.00 $0.00 $0.00 $0.00
Fee $0.00 $0.00 $0.00 $0.00
TOTAL $0.00 $0.00 $0.00 $0.00
*Current GMP Budget as of CCM May 26, 2020
The Office of Small Business Development has determined that Hensel Phelps
Construction's deductive GMP Amendment for BP-S00142 (GMP No. 6-S) does not have any
impact on the small business participation.
Ms. Sharman asked if this request is enough to complete the known scope.
Mr. Corthell answered yes. Ms. Sharman asked if there was any additional scope
anticipated. Mr. Corthell responded no.
Ms. Sharman stated that this item is subject to the Construction Finance Oversight
Committee (CFOC).
Agenda Item Nos. 3, 4, and 5 were considered in one motion.
Minutes of the Construction Committee Meeting, June 3, 2020
Page 36 of 41
Upon motion of Mr. Patterson, second by Ms. Schneider, vote carried by roll-call,
with all votes yea, to recommend to the Aviation Authority Board approval of Amendment
No. 4 to Addendum No. 3 to the Construction Management at Risk (CM@R) Entity Services
for the South Terminal C, Phase 1 Agreement with Hensel Phelps Construction for
BP-S00142, Airside Terminal Foundations (GMP No. 6-S), for a total negotiated
deductive GMP Amendment amount of ($242,156.00), which includes a deductive amount
of ($180,260.00) for CM@R Contingency, a deductive amount of ($46,615.00) for Owner
Contingency, a deductive amount of ($1,598.00) for Performance and Payment Bonds,
and a deductive amount of ($13,683.00) for the CM@R Fee (6.031%), resulting in a
revised GMP amount of $21,699,986.00, with funding from Passenger Facility Charges
to the extent eligible and General Airport Revenue Bonds; subject to funding
consensus by the CFOC. [Subsequent to the Construction Committee meeting, the CFOC
consensed the funding at the meeting held on July 9, 2020, as outlined above.]
REQUEST FOR RECOMMENDATION OF APPROVAL OF AMENDMENT NO. 6 TO ADDENDUM NO. 13 TO THE
CONSTRUCTION MANAGEMENT AT RISK (CM@R) ENTITY SERVICES FOR THE SOUTH TERMINAL C,
PHASE 1 AGREEMENT WITH HENSEL PHELPS CONSTRUCTION FOR BP-S00144, SOUTH TERMINAL C,
PHASE 1 - AIRSIDE TERMINAL, ENCLOSURE AND EXTERIOR FINISHES (GMP NO. 6-S.2), AT THE
ORLANDO INTERNATIONAL AIRPORT.
4. Mr. Corthell presented the memorandum, dated June 23, 2020, to request for
recommendation of approval of Amendment No. 6 to Addendum No. 13 to the Construction Management at Risk (CM@R) Entity Services for the South Terminal C, Phase 1 Agreement
with Hensel Phelps Construction for BP-S00144, South Terminal C, Phase 1 - Airside
Terminal, Enclosure and Exterior Finishes (GMP No. 6-S.2), at the Orlando
International Airport.
The Program Team has evaluated the Guaranteed Maximum Price (GMP) for BP-S00144,
South Terminal C, Phase 1 -Airside Enclosure and Exterior Finishes (GMP No. 6-S.2)
and determined that it is necessary to increase Owner Contingency to fund design
progression of the electrical design and other design bulletins and contingency
requests. The proposed GMP value is indicated in the tables below:
GMP Original GMP
Budget
Current GMP
Budget*
Proposed GMP
Amendment
Proposed GMP
Total
Direct Cost of
Work $85,983,643.00 $127,025,475.00 $0.00 $127,025,475.00
Unbought Scope $157,441.00 $401,708.00 $0.00 $401,708.00
Allowances $5,444,000.00 $0.00 $0.00 $0.00
CM@R
Contingency $3,663,403.00 $2,692,490.00 $0.00 $2,692,490.00
Owner
Contingency $2,289,627.00 $423,912.00 $1,075,971.00 $1,499,883.00
P&P Bond $686,825.00 $919,236.00 $7,577.00 $926,813.00
Fee $5,882,524.00 $7,873,085.00 $64,892.00 $7,937,977.00
TOTAL $104,107,463.00 $139,335,906.00 $1,148,440.00 $140,484,346.00
*Current GMP Budget as of CCM May 26, 2020
Minutes of the Construction Committee Meeting, June 3, 2020
Page 37 of 41
GMP – P1 Original GMP
Budget
Current GMP
Budget*
Proposed GMP
Amendment
Proposed GMP
Total
Direct Cost of
Work $85,983,643.00 $107,363,606.00 $0.00 $107,363,606.00
Unbought Scope $157,441.00 $96,708.00 $0.00 $96,708.00
Allowances $5,444,000.00 $0.00 $0.00 $0.00
CM@R
Contingency $3,663,403.00 $1,908,717.00 $0.00 $1,908,717.00
Owner
Contingency $2,289,627.00 $73,111.00 $1,075,971.00 $1,149,082.00
P&P Bond $686,825.00 $770,648.00 $7,577.00 $778,225.00
Fee $5,882,524.00 $6,600,457.00 $64,892.00 $6,665,349.00
TOTAL $104,107,463.00 $116,813,247.00 $1,148,440.00 $117,961,687.00
*Current GMP Budget as of CCM May 26, 2020
GMP – P1X Original GMP
Budget
Current GMP
Budget*
Proposed GMP
Amendment
Proposed GMP
Total
Direct Cost of
Work $0.00 $19,661,869.00 $0.00 $19,661,869.00
Unbought Scope $0.00 $305,000.00 $0.00 $305,000.00
Allowances $0.00 $0.00 $0.00 $0.00
CM@R
Contingency $0.00 $783,773.00 $0.00 $783,773.00
Owner
Contingency $0.00 $350,801.00 $0.00 $350,801.00
P&P Bond $0.00 $148,588.00 $0.00 $148,588.00
Fee $0.00 $1,272,628.00 $0.00 $1,272,628.00
TOTAL $0.00 $22,522,659.00 $0.00 $22,522,659.00
*Current GMP Budget as of CCM May 26, 2020
The Office of Small Business Development has determined that the proposed GMP
Amendment for BP-S00144 (GMP No. 6-S.2) does not have any impact on the small
business participation.
Ms. Sharman asked if this request is enough to complete the known scope.
Mr. Corthell answered yes. Ms. Sharman asked if there was any additional scope
anticipated. Mr. Corthell responded no.
Ms. Sharman stated that this item is subject to the Construction Finance Oversight
Committee (CFOC).
Agenda Item Nos. 3, 4, and 5 were considered in one motion.
Upon motion of Mr. Patterson, second by Ms. Schneider, vote carried by roll-call,
with all votes yea, to recommend to the Aviation Authority Board approval of Amendment
No. 6 to Addendum No. 13 to the Construction Management at Risk (CM@R) Entity
Services for the South Terminal C, Phase 1 Agreement with Hensel Phelps Construction
for BP-S00144, South Terminal C, Phase 1 - Airside Terminal, Enclosure and Exterior
Finishes (GMP No. 6-S.2), for a total negotiated GMP Amendment amount of
$1,148,440.00, which includes $1,075,971.00 for Owner Contingency, $7,577.00 for
Performance and Payment Bond, and $64,892.00 for the CM@R Fee (6.031%), resulting
in a revised GMP amount of $140,484,346.00, with funding from Passenger Facility
Charges to the extent eligible and General Airport Revenue Bonds; subject to funding
consensus by the CFOC. [Subsequent to the Construction Committee meeting, the CFOC
consensed the funding at the meeting held on July 9, 2020, as outlined above.]
Minutes of the Construction Committee Meeting, June 3, 2020
Page 38 of 41
REQUEST FOR RECOMMENDATION OF APPROVAL OF AMENDMENT NO. 5 TO ADDENDUM NO. 16 TO THE
CONSTRUCTION MANAGEMENT AT RISK (CM@R) ENTITY SERVICES FOR THE SOUTH TERMINAL C,
PHASE 1 AGREEMENT WITH HENSEL PHELPS CONSTRUCTION FOR BP-S00168, AIRSIDE TERMINAL,
INTERIOR FINISHES AND SPECIALTIES (GMP NO. 6-S.4), AT THE ORLANDO INTERNATIONAL
AIRPORT.
5. Mr. Corthell presented the memorandum, dated June 23, 2020, to request for
recommendation of approval of Amendment No. 5 to Addendum No. 16 to the Construction
Management at Risk (CM@R) Entity Services for the South Terminal C, Phase 1 Agreement
with Hensel Phelps Construction for BP-S00168, Airside Terminal, Interior Finishes
and Specialties (GMP No. 6-S.4), at the Orlando International Airport. The South
Terminal C Program Team has evaluated the budget for the South Terminal C, Phase 1
Agreement with Hensel Phelps Construction for BP-S00168, Airside Terminal, Interior
Finishes and Specialties (GMP No. 6-S.4 ), and agreed to a reduction in the GMP
value as indicated in the tables below:
GMP Original GMP
Budget
Current GMP
Budget**
Proposed GMP
Amendment
Proposed GMP
Total
Direct Cost of
Work $52,104,076.00 $53,325,281.00 $0.00. $53,325,281.00
Unbought Scope $1,863,725.00 $857,100.00 $0.00. $857,100.00
Allowances ($500,000.00) $0.00 $0.00. $0.00
CM@R
Contingency $2,138,712.00 $1,805,579.00 $0.00. $1,805,579.00
Owner
Contingency $534,678.00 $4,184,957.00 ($849,096.00) $3,335,861.00
P&P Bond $395,324.00 $423,714.00 ($5,979.00) $417,735.00
Fee $3,385,875.00 $3,629,029.00 ($51,209.00) $3,577,820.00
TOTAL $59,922,390.00 $64,225,660.00 ($906,284.00) $63,319,376.00
GMP – P1 Original GMP
Budget
Current GMP
Budget
Proposed GMP
Amendment
Proposed GMP
Total
Direct Cost of
Work $52,104,076.00 $50,318,545.00 $0.00. $50,318,545.00
Unbought Scope $1,863,725.00 $693,620.00 $0.00. $693,620.00
Allowances ($500,000.00) $0.00 $0.00. $0.00
CM@R
Contingency $2,138,712.00 $1,651,771.00 $0.00. $1,651,771.00
Owner
Contingency $534,678.00 $3,471,511.00 ($849,096.00) $2,622,415.00
P&P Bond $395,324.00 $395,284.00 ($5,979.00) $389,305.00
Fee $3,385,875.00 $3,385,529.00 ($51,209.00) $3,334,320.00
TOTAL $59,922,390.00 $59,916,260.00 ($906,284.00) $59,009,976.00
GMP – P1X Original GMP
Budget
Current GMP
Budget
Proposed GMP
Amendment
Proposed GMP
Total
Direct Cost of
Work $0.00 $3,006,736.00 $0.00 $3,006,736.00
Unbought Scope $0.00 $163,480.00 $0.00 $163,480.00
Allowances $0.00 $0.00 $0.00 $0.00
CM@R
Contingency $0.00 $153,808.00 $0.00 $153,808.00
Owner
Contingency $0.00 $713,446.00 $0.00 $713,446.00
P&P Bond $0.00 $28,430.00 $0.00 $28,430.00
Fee $0.00 $243,500.00 $0.00 $243,500.00
TOTAL $0.00 $4,309,400.00 $0.00 $4,309,400.00
Minutes of the Construction Committee Meeting, June 3, 2020
Page 39 of 41
The Office of Small Business Development has determined that Hensel Phelps
Construction's deductive Amendment for BP-S00168 (GMP 6-S.4) does not have any impact
on the small business participation. [Subsequent to the meeting, the Office of
Small Business Development submitted an OSBD Participation Memorandum as Information
Item 12-F on the July 21, 2020, Construction Committee Agenda.]
Ms. Sharman asked if this request is enough to complete the known scope.
Mr. Corthell answered yes. Ms. Sharman asked if there was any additional scope
anticipated. Mr. Corthell responded no.
Ms. Sharman stated that this item is subject to the Construction Finance Oversight
Committee (CFOC).
Agenda Item Nos. 3, 4, and 5 were considered in one motion.
Upon motion of Mr. Patterson, second by Ms. Schneider, vote carried by roll-call,
with all votes yea, to recommend to the Aviation Authority Board approval of Amendment
No. 5 to Addendum No. 16 to the Construction Management at Risk (CM@R) Entity
Services for the South Terminal C, Phase 1 Agreement with Hensel Phelps Construction
for BP-S00168, Airside Terminal, Interior Finishes and Specialties (GMP No. 6-S.4),
for a total negotiated deductive GMP Amendment amount of ($906,284.00), which
includes a deductive amount of ($849,096.00) for Owner Contingency, a deductive
amount of ($5,979.00) for Performance and Payment Bond, and a deductive amount of
($51,209.00) for the CM@R Fee (6.031%), resulting in a revised GMP amount of
$63,319,376.00, with funding from Passenger Facility Charges to the extent eligible
and General Airport Revenue Bonds; subject to funding consensus by the CFOC.
[Subsequent to the Construction Committee meeting, the CFOC consensed the funding
at the meeting held on July 9, 2020, as outlined above.]
REQUEST FOR APPROVAL OF THE PURCHASE OF TECHNOLOGY (CISCO NETWORK SWITCH AND RELATED
EQUIPMENT) FROM VEYTEC, INC. FOR W-S00129, SOUTH TERMINAL COMPLEX, TRAILER PURCHASE
AND MAINTENANCE ITEMS, AND W-S00132, SOUTH TERMINAL COMPLEX, P1X TRAILER PURCHASE,
AT THE ORLANDO INTERNATIONAL AIRPORT.
6. Mr. Ruohomaki presented the memorandum, dated June 3, 2020, along with a quote
from Veytec, Inc., dated May 20, 2020, for the purchase of technology (Cisco Network
Switch and Related Equipment) from Veytec, Inc. for WS00129, South Terminal C,
Trailer Purchase and Maintenance Items, and W-S00132, South Terminal C, Phase 1
Expansion Trailer Purchase, at the Orlando International Airport. On June 2, 2020,
the Aviation Authority received three quotations for RFQ No. 93048-20 to purchase
one Cisco Network Switch 9500 network and related equipment. The apparent low bidder
was Veytec, Inc. in the not-to-exceed amount of $37,740.00 as shown in the
Bid/Proposal Tab. The network switches will be used on the South Terminal C trailer
purchase. The network switches and related components will be used in the Minimum
Point of Entry (MPOE) to support connectivity requirements as more subcontractors
start a presence at the contractor site.
Bidder / Proposer Total Price
Veytec, Inc. $37,740.00
Insight Public Sector $42,615.47
NetSync Network Solutions $44,352.60
The pricing was provided in accordance with State of Florida Contract No. 43220000-
WSCA-14-ACS (Expiring 05/31/2020). In accordance with Aviation Authority Policy
450.03, Section 450.03, NonCompetitive Procurements permits the procurement of
goods and/or services from a Supplier having a requirements contract/annual agreement
with any public entity for products and/or services described in such contract and
at prices or discounts no less favorable than any set forth in such Contract.
Minutes of the Construction Committee Meeting, June 3, 2020
Page 40 of 41
The Office of Small Business Development has determined that due to the limited
scope of the required services, Veytec, Inc. does not propose any small business
participation on this Purchase Request.
Upon motion of Mr. Patterson, second by Mr. Hunt, vote carried by roll-call, with
all votes yea, to approve the purchase of technology (Cisco Network Switch and
Related Equipment) from Veytec, Inc. for WS00129, South Terminal C, Trailer Purchase
and Maintenance Items, and W-S00132, South Terminal C, Phase 1 Expansion Trailer
Purchase, for the total not-to-exceed expense amount of $37,740.00, with funding
from General Airport Revenue Bonds.
GENERAL
REQUEST FOR RECOMMENDATION OF APPROVAL OF A JOB ORDER CONSTRUCTION SERVICES ADDENDUM
TO THE CONTINUING HORIZONTAL CONSTRUCTION SERVICES AGREEMENT WITH THE MIDDLESEX
CORPORATION FOR H-00319, TAXIWAYS C AND B REPAIRS, AT THE ORLANDO INTERNATIONAL
AIRPORT.
7. This item was deferred.
REQUEST FOR APPROVAL OF AN ADDENDUM TO THE CONTINUING PROGRAM AND PROJECT MANAGEMENT
SERVICES (OAR PRIME ENTITY) AGREEMENT WITH A² GROUP, INC. TO PROVIDE CONSTRUCTION
PHASE OAR SERVICES FOR H-00319, TAXIWAYS C AND B REPAIRS, AT THE ORLANDO INTERNATIONAL
AIRPORT.
8. This item was deferred.
REQUEST FOR APPROVAL OF AN ADDENDUM TO THE CONTINUING ENVIRONMENTAL ENGINEERING
SERVICES AGREEMENT WITH MSE GROUP, LLC TO CONDUCT A SITE ASSESSMENT AT THE
INTERSECTION OF TAXIWAYS Y AND Z , AT THE ORLANDO INTERNATIONAL AIRPORT.
9. Mr. Carrington presented the memorandum, dated June 23, 2020, along with a
proposal from MSE Group, LLC, dated May 6, 2020, to conduct a Site Assessment at the
intersection of Taxiways Y and Z. This Site Assessment is to determine the remaining
impacts from the fuel discharge from a Norwegian Airlines A-340 that occurred on
June 29, 2019, at Orlando International Airport.
If approved, these services would be effective the date of Construction Committee
approval.
The Office of Small Business Development has reviewed the qualifications of the
subject contract's MWBE/LDB/VBE specifications and determined that MSE Group, LLC
proposes 22.0% MWBE participation on this Addendum.
Ms. Sharman stated that funding for this item should be changed to Aviation Authority
Funds and previously-approved Capital Expenditure Funds. Further, Ms. Sharman stated
that there may be potential for reimbursement, but that it has not been determined
at this time.
Upon motion of Ms. Sharman, second by Mr. Hunt, vote carried by roll-call, with all
votes yea, to approve an Addendum to the Continuing Environmental Engineering
Consultant Services Agreement with MSE Group, LLC to conduct a Site Assessment at
the Intersection of Taxiways Y and Z, for the total amount of $47,430.00, which
includes the not-to-exceed fee amount of $33,468.00 and the not-to-exceed
reimbursable expense amount of $13,962.00, with funding Aviation Authority Funds and
previously-approved Capital Expenditure Funds.
On TUESDAY, JUNE 9, 2020, the CONSTRUCTION COMMITTEE met in regular session
telephonically with the meeting live streamed on You Tube (www.OrlandoAirports.net).
Chairman Thornton called the meeting to order at 8:34 a.m. The meeting was posted
in accordance with Florida Statutes with a quorum participating. Office of the
Governor, Executive Order Number 20-69
Participating Committee members,
Stanley J. Thornton, Chairman
Kathleen Sharman, Chief Financial Officer
Mike Patterson, Director of Construction
Gary Hunt, Director of Maintenance
Denise Schneider, Assistant Director of Purchasing and Material Control
Also participating:
Davin Ruohomaki, GOAA Senior Director of Planning, Engineering, and Construction
Tom Draper, Senior Director of Airport Operations
Karen Ryan, Legal Counsel (Nelson Mullins Broad & Cassel)
Greg Watson, GOAA Construction
John Carlson, GOAA Construction
Kathy Anderson, GOAA Contracts and Grants
Alex Sorondo, HNTB Corporation
Don Corthell, PSA Management, Inc.
Neil Hahn, Hahn Integrated Systems, Inc.
Rhonda Fischetti, Hahn Integrated Systems, Inc.
Tara Ciaglia, Recording Secretary
LOBBYIST DISCLOSURE
Parties present were reminded that for individuals who conduct lobbying activities
with Aviation Authority employees or Board members, registration with the Aviation
Authority is required each year prior to conducting any lobbying activities. A
statement of expenditures incurred in connection with those lobbying instances should
also be filed prior to April 1st of each year for the preceding year. As of January
16, 2013, lobbying any Aviation Authority Staff who are members of any committee
responsible for ranking Proposals, Letters of Interest, Statements of Qualifications
or Bids and thereafter forwarding those recommendations to the Board and/or Board
Members is prohibited from the time that a Request for Proposals, Request for Letters
of Interests, Request for Qualifications or Request for Bids is released to the time
that the Board makes an award. As adopted by the Board on September 19, 2012,
lobbyists are now required to sign-in at the Aviation Authority offices prior to any
meetings with Staff or Board members. In the event a lobbyist meets with or otherwise
communicates with Staff or a Board member at a location other than the Aviation
Authority offices, the lobbyist shall file a Notice of Lobbying (Form 4) detailing
each instance of lobbying to the Aviation Authority within 7 calendar days of such
lobbying. As of January 16, 2013, lobbyists will also provide a notice to the
Aviation Authority when meeting with the Mayor of the City of Orlando or the Mayor
of Orange County at their offices. The policy, forms, and instructions are available
in the Aviation Authority’s offices and the website. Please contact the Director
of Board Services with questions at (407) 825-2032.
ANNOUNCEMENT
Any appeals of decisions made by the Construction Committee must be filed with the
Chief Executive Officer within five business days (no later than 4:00 p.m. on the
fifth business day) of the rendering of that decision. If a bidder or proposer is
aggrieved by any of the proceedings of today’s meeting and wishes to appeal the
results of actions made by this committee, they must file an appeal stating the item
they wish to appeal and the basis for which they wish to appeal, and it must be
received in writing by the Chief Executive Officer, Mr. Phillip N. Brown, via email
[email protected], with a copy to [email protected] (emails will be accepted during the
COVID-19 pandemic.)
Minutes of the Construction Committee Meeting, June 9, 2020
Page 2 of 38
COVID-19 ANNOUNCEMENT
Due to COVID-19, the Aviation Authority is adhering to a business distancing
operational plan. Please note that all Construction Committee meetings from today
until further notice will be held telephonically. If you would like to speak at the
meeting on an agenda item being considered, please contact the Recording Secretary,
Tara Ciaglia ([email protected] -or- 407-825-4461) no less than 24 hours in
advance of the meeting. Otherwise, the Construction Committee will be conducted
virtually via: https://global.gotomeeting.com/join/337969773.
MINUTES
1. The following minutes were presented for consideration:
CORRECTION TO THE AUGUST 27, 2019, MINUTES
A. [Agenda Item Nos. 1-A, 1-C and 1-D were considered in one motion.] Upon motion of Mr. Patterson, second by Mr. Hunt, vote carried, by roll-call with all
votes yea, to approve a correction to the Construction Committee Minutes for
August 27, 2019, Page 21, Item 9, revise the recommended action from
“…including the Not-To-Exceed Fee Amount…” to “…including the Not-To-Exceed
Reimbursable Expenses Amount…”.
CONSIDERATION OF APRIL 7, 2020 MINUTES
B. This item was deferred.
CONSIDERATION OF April 21, 2020 MINUTES
C. [Agenda Item Nos. 1-A, 1-C and 1-D were considered in one motion.] Upon motion of Mr. Patterson, second by Mr. Hunt, vote carried, by roll-call with all
votes yea, to approve the Construction Committee Minutes from the meeting held
on April 21, 2020, as presented.
CONSIDERATION OF APRIL 28, 2020 MINUTES
D. [Agenda Item Nos. 1-A, 1-C and 1-D were considered in one motion.] Upon motion of Mr. Patterson, second by Mr. Hunt, vote carried, by roll-call with all
votes yea, to approve the Construction Committee Minutes from the meeting held
on April 28, 2020, as presented.
CHANGE ORDER AGENDA
2. The following Change Orders were presented for consideration:
A. Change Order E-00263-02 VARIOUS REVISIONS. [A handout was presented, which includes a revised Coversheet and new backup documentation.]
This item was deferred.
[The Construction Committee requested that the following discussion be
documented in the minutes.] Ms. Sharman asked if these four change orders
must be done. Chairman Thornton stated that the reductions from these four
change orders will be reallocated to other work. Ms. Sharman agreed, and
advised caution with de-scoping projects, especially with the uptick in air
traffic. Ms. Sharman then asked if it is more important to complete the work
associated with the E-00263 change order than to take the reduction. Mr.
Draper replied yes, that this work is of highest priority, and with the
international airlines scheduling flights for late July, having the work done
now will have it completed before these international flights occur. Chairman
Thornton also cautioned that there is no uptick in revenues; however,
international traffic is moving upward.
Minutes of the Construction Committee Meeting, June 9, 2020
Page 3 of 38
B. Change Order V-00927-01 TERMINATION FOR CONVENIENCE. This change order to the contract with Collage Design and Construction Group, Inc. dba The Collage
Companies for Wayfinding Signage at 50-Yard Line, A and B Sides, is the final
change order and includes the following: 1. As the result of COVID-19 Pandemic
impacts, and in accordance with Article 14.3.3 of Section 00700 of the Contract
Documents, this change order terminates for convenience Job Order Addendum No.
12 for the V-00927, Wayfinding Signage at 50-yard Line A and B Sides, project.
All work has been left in a safe condition. The following material, already
purchased, but not yet installed, will be turned over to the Aviation Authority
at a location on airport property: (a) Two 4’x20’ Wayfinding Signage with
mounting brackets; and, (b) eight 4’x6’ Support structure brackets. This change
order completely resolves all time and cost issues on the project. Contractor
represents and warrants that neither Contractor nor its subcontractors,
suppliers, materialmen, or any other persons supplying material, supplies,
services, or labor directly or indirectly in the prosecution of the work
provided in the Contract have or are aware of any claims or potential claims
on this Project. Contractor further covenants that all subcontractors,
suppliers, materialmen, and all other persons supplying material, supplies,
services, or labor used directly or indirectly in the prosecution of the work
provided in the Contract shall be paid in full, and that Contractor shall
defend, indemnify, and hold harmless the Greater Orlando Aviation Authority
from any and all debts and accounts, promises, damages, liens, encumbrances,
causes of action, suits, bonds, judgments, claims and demands whatsoever, in
law or in equity which any subcontractor, supplier, materialmen, or any other
persons supplying material, supplies, services, or labor used directly or
indirectly in the prosecution of the work provided in the Contract had, now
has, or may ever have. Credits given are as follows: (a) General Conditions:
($7,529.00); (b) Signage Credit (AC Signs, LLC): ($8,860.00); (c) Structural
Support Services Credit (Key Mechanical Services, Inc.): ($5,205.00); (d)
Electrical Support Services (Key Mechanical Services, Inc.): ($7,500.00); (e)
Additional Blocking and Touch-up (Collage Design & Const.): ($1,400.00); (f)
Paint, Patch, Penetrations (Collage Design & Const.): ($800.00); (g) Tax
(Collage Design & Const.): ($119.00); (h) Permitting (Collage Design & Const.):
($19.00); (i) Fees: ($4,420.00); and, (j) Burden: ($3,036.00). NET AMOUNT FOR
ITEM NO. 1: DEDUCT: ($38,888.00); and, 2. Additional Structural Design and
Deliverable. ADD: $5,000.00.
Mr. Patterson asked if there would be any additional expenses if this project
were to continue to completion. Mr. Watson replied yes, that there may be up
to $20,000.00 of additional electrical work.
Upon motion of Mr. Patterson, second by Ms. Sharman, vote carried by roll-call
with all votes yea, to approve Change Order V-00927-01, for a total deductive
amount of ($33,888.00) and no time extension, with funding credited to
previously-approved Capital Expenditure Funds.
C. Change Order V-00947-02 TERMINATION FOR CONVENIENCE. [A handout was presented, which includes a revised Coversheet and new backup documentation.] This change
order to the contract with H. W. Davis Construction, Inc. for MCO Roadway
Signage Structure Rehabilitation is the final change order and includes the
following: As the result of COVID-19 Pandemic impacts, and in accordance with
Article 14.3.3 of Section 00700 of the Contract Documents, this change order
terminates for convenience Job Order Addendum No. 32 for the V-00947, MCO
Roadway Signage Structure Rehabilitation, project. The overhead sign work has
been completed and the roadside sign work is deleted. All work has been left
in a safe condition and there is no project material or equipment to be turned
over to the Greater Orlando Aviation Authority. This change order completely
resolves all time and cost issues on the project. Contractor represents and
warrants that neither Contractor nor its subcontractors, suppliers,
Minutes of the Construction Committee Meeting, June 9, 2020
Page 4 of 38
materialmen, or any other persons supplying material, supplies, services, or
labor directly or indirectly in the prosecution of the work provided in the
Contract have or are aware of any claims or potential claims on this Project.
Contractor further covenants that all subcontractors, suppliers, materialmen,
and all other persons supplying material, supplies, services, or labor used
directly or indirectly in the prosecution of the work provided in the Contract
shall be paid in full, and that Contractor shall defend, indemnify, and hold
harmless the Greater Orlando Aviation Authority from any and all debts and
accounts, promises, damages, liens, encumbrances, causes of action, suits,
bonds, judgments, claims and demands whatsoever, in law or in equity which any
subcontractor, supplier, material men, or any other persons supplying material,
supplies, services, or labor used directly or indirectly in the prosecution
of the work provided in the Contract had, now has, or may ever have.
DEDUCT: ($43,931.40).
Upon motion of Ms. Sharman, second by Ms. Schneider, vote carried by roll-call
with all votes yea, to approve Change Order V-00947-02, for a total deductive
amount of ($43,931.40) and no time extension, with funding credited to
previously-approved Capital Expenditure Funds.
D. Change Order V-00950-01 TERMINATION FOR CONVENIENCE. [A handout was presented, which includes a revised Coversheet.] This change order to the contract with
Gomez Construction Company for Airside 4 Glass Window Replacement is the final
change order and includes the following: As the result of COVID-19 Pandemic
impacts, and in accordance with Article 14.3.3 of Section 00700 of the Contract
Documents, this change order terminates for convenience Job Order Addendum No.
46 for the V-00950, Airside 4 Glass Window Replacement, project. All work has
been left in a safe condition. The following replacement glass, already
purchased, but not yet installed, has been turned over to the Greater Orlando
Aviation Authority at the HBJ Warehouse and all other work on the Project has
been deleted: (a) 122-3/4" x 74" Glass for roof level in front of back hallway
leading to Bahama Breeze; (b) 138" x 74" Glass for upper level of Bahama
Breeze; and, (c) 94" x 33-1/8" Glass over top of APM station. This change
order completely resolves all time and cost issues on the project. Contractor
represents and warrants that neither Contractor nor its subcontractors,
suppliers, materialmen, or any other persons supplying material, supplies,
services, or labor directly or indirectly in the prosecution of the work
provided in the Contract have or are aware of any claims or potential claims
on this Project. Contractor further covenants that all subcontractors,
suppliers, materialmen, and all other persons supplying material, supplies,
services, or labor used directly or indirectly in the prosecution of the work
provided in the Contract shall be paid in full, and that Contractor shall
defend, indemnify, and hold harmless Greater Orlando Aviation Authority from
any and all debts and accounts, promises, damages, liens, encumbrances, causes
of action, suits, bonds, judgments, claims and demands whatsoever, in law or
in equity which any subcontractor, supplier, materialmen, or any other persons
supplying material, supplies, services, or labor used directly or indirectly
in the prosecution of the work provided in the Contract had, now has, or may
ever have. DEDUCT: ($62,590.91).
Mr. Hunt asked if the project will be left in a safe condition. Mr. Carlson
replied yes, that no work has been done on the glass. Chairman Thornton asked
about the location of the glass. Mr. Carlson replied it is near the Bahama
Breeze restaurant.
Upon motion of Ms. Sharman, second by Ms. Schneider, vote carried by roll-call
with all votes yea, to approve Change Order V-00950-01, for a total deductive
amount of ($62,590.91) and no time extension, with funding credited to
previously-approved Capital Expenditure Funds.
Minutes of the Construction Committee Meeting, June 9, 2020
Page 5 of 38
CONSTRUCTION MANAGEMENT AT RISK (CM@R) GUARANTEED MAXIMUM PRICE (GMP) BUDGET, BUYOUT,
AND CONTINGENCY MANAGEMENT REQUESTS AGENDA
3. The following GMP Budget, Buyout, and Contingency Management requests (related
to the South Terminal C, Phase One Project) were presented for consideration:
A. Subcontract Modification for BP-S00139 (GMP No. 5-S.2) with The Middlesex Corporation for CR1008-5S.2-LSC-Additional Wooded Buffer Area Demucking.
Mr. Corthell presented the memorandum, requesting approval for Turner-Kiewit
Joint Venture (TKJV) to issue a Subcontract Modification on BP-S00139, South
Terminal C, Phase 1 – Landside Civil (GMP No. 5-S.2), at the Orlando
International Airport, in the total amount of $35,764.00 to The Middlesex
Corporation for CR1008-5S.2-LSC-Additional Wooded Buffer Area Demucking. Bid
Package 31.0.0 "Sitework" was previously awarded within GMP No. 5-S.2 to The
Middlesex Corporation, CC No. 20180504.05A.
TKJV is proposing a subcontract modification to The Middlesex Corporation in
the total lump sum amount of $35,764.00 for CR1008-5S.2-LSC-Additional Wooded
Buffer Area Demucking. LSC Bulletin 13 relocated utilities through the wooded
buffer area that was previously designated as green space. CR0212.1-LSC-5S.2-
Wooded Buffer Root Material included costs for necessary demucking below the
finished excavation surface in another area of the wooded buffer and was
approved, CC 00526.03A. Subsequent to the work performed in CR0212.1, while
excavating in preparation for utility installation at the north side of the
former wooded buffer area, The Middlesex Corporation encountered unsuitable
material approximately 6' below contract demucking limits in the specific area
delineated in the marked-up Drawing C35.0.05, included in backup documentation,
which was in a different area from the demucking scope of CR0212.1. The
modified scope of work captured in this request consists of all labor, material
and equipment costs associated with removal of unsuitable material below
elevation +75.0, hauling onsite to stockpile and replacing the demucked area
with A3 sand backfill.
The approval of this subcontract modification to The Middlesex Corporation
resolves all requests for costs and time associated with the scope of work
delineated in CR1008-5S.2-LSC-Additional Wooded Buffer Area Demucking.
TKJV has submitted documentation including the subcontractor's proposal to
support their request. An independent cost Review is included. By approving
this request, the Owner does not waive its right to enforce the contract
requirements for other requests for cost or time.
The effect of this Subcontract Modification for this project is as follows:
TKJV to issue a subcontract modification to The
Middlesex Corporation in the lump sum amount of: $ 35,764.00
Deduct from P1X CMAR Contingency: $ (35,764.00)
Turner-Kiewit Joint Venture is committed to 20% MWBE and 4% LDB participation
for Construction Services. The subcontractor identified and committed to
participate on BP-S00139 (GMP No. 5-S.2) for this subcontract modification is
The Middlesex Corporation (Non-MWBE/LDB/VBE). There is 13.5% LDB participation
associated with this modification.
Ms. Sharman asked if this item has taken into account any potential scope
reductions. Mr. Corthell answered yes, that this item has been reviewed and
determined to be necessary at this time, as well as within any projected
reductions in scope.
Minutes of the Construction Committee Meeting, June 9, 2020
Page 6 of 38
Agenda Item Nos. 3-A, 3-B, 3-C, 3-D, 3-E, 3-F, 3-G, 3-H, 3-I, 3-J, 3-K, 3-L,
3-M, 3-N, 3-O, 3-P, 3-Q, 3-R, 3-S, 3-T, 3-U, 3-V, 3-W, 3-X, 3-Y, and 3-Z were
considered in one motion.
Upon motion of Mr. Patterson, second by Mr. Hunt, vote carried by roll-call,
with all votes yea, to approve Turner-Kiewit Joint Venture to issue a
Subcontract Modification to The Middlesex Corporation on BP-S00139, South
Terminal C, Phase 1 – Landside Civil (GMP No. 5-S.2), for the total lump sum
amount of $35,764.00, with funding from General Airport Revenue Bonds.
B. Subcontract Modification for BP-S00144 (GMP No. 6-S.2) with BergElectric Corp. dba Bergelectric Corp. Contractors and Engineers for CR0466-6S.2-RFI 1782
Light Fixtures Changes in Airside Concourse Area 14. Mr. Corthell presented
the memorandum, requesting approval for Hensel Phelps Construction (HPC) to
issue a Subcontract Modification on BP-S00144, South Terminal C, Phase 1 - STC
Airside Enclosure and Exterior Finishes (GMP No. 6-S.2), at the Orlando
International Airport, in the total deductive amount of ($54,081.00) to
BergElectric Corp. dba Bergelectric Corp. Contractors and Engineers for CR0466-
6S.2-RFI 1782 Light Fixtures Changes in Airside Concourse Area 14. Bid Package
for BP-S144 26.01 "ASC Electrical Systems" has been previously awarded within
GMP No. 6-S.2 to Bergelectric Corp. dba Bergelectric Corp. Contractors and
Engineers, CC No. 20180605.006.
HPC is requesting to issue a Subcontractor Modification to Bergelectric Corp
dba Bergelectric Corp. Contractors and Engineers in the total deductive Lump
Sum amount of ($54,081.00) for CR0466-6S.2-RFI 1782 Light Fixtures Changes in
Airside Concourse Area 14. The modified scope of work includes the credit
associated with the deletion of (103 Ea.) front-of-house (FOH) lighting
fixtures and all associated conduits, wires, and junction boxes, per RFI 1782
response.
The approval of this Subcontractor Modification to Bergelectric Corp. dba
Bergelectric Corp. Contractors and Engineers resolves all requests for costs
and time resulting from RFI 1782 within GMP No. 6-S.2. Impacts of RFI 1782 to
GMP No. 6-S.6 (P1X) will be submitted via future CR.
HPC has submitted documentation including the subcontractor's proposal to
support this request. An independent cost estimate is included. By approving
this request, the Owner does not waive its right to enforce the contract
requirements for other requests for cost or time.
The effect of this Subcontract Modification for this project is as follows:
HPC to issue a subcontract modification to
BergElectric Corp. dba Bergelectric Corp.
Contractors and Engineers in the deductive lump
sum amount of: $ (54,081.00)
Add to P1 Owner Contingency: $ 54,081.00
Hensel Phelps Construction is committed to 20% MWBE and 4% LDB participation
for Construction Services. The subcontractor identified and committed to
participate on BP-S00144 (GMP No. 6-S.2) for this subcontract modification is
BergElectric Corp. dba Bergelectric Corp. Contractors and Engineers (Non-
MWBE/LDB/VBE). There is 17.5% reduction in MWBE participation associated with
this modification.
Ms. Sharman asked if this item has taken into account any potential scope
reductions. Mr. Corthell answered yes, that this item has been reviewed and
Minutes of the Construction Committee Meeting, June 9, 2020
Page 7 of 38
determined to be necessary at this time, as well as within any projected
reductions in scope.
Agenda Item Nos. 3-A, 3-B, 3-C, 3-D, 3-E, 3-F, 3-G, 3-H, 3-I, 3-J, 3-K, 3-L,
3-M, 3-N, 3-O, 3-P, 3-Q, 3-R, 3-S, 3-T, 3-U, 3-V, 3-W, 3-X, 3-Y, and 3-Z were
considered in one motion.
Upon motion of Mr. Patterson, second by Mr. Hunt, vote carried by roll-call,
with all votes yea, to approve Hensel Phelps Construction to issue a
Subcontract Modification to BergElectric Corp. dba Bergelectric Corp.
Contractors and Engineers on BP-S00144, South Terminal C, Phase 1 - STC Airside
Enclosure and Exterior Finishes (GMP No. 6-S.2), for the total deductive lump
sum amount of ($54,081.00), with funding credited to Passenger Facility Charges
and General Airport Revenue Bonds.
C. Subcontractor Modification for BP-S00145 (GMP No. 6-S.3) with Alpha Insulation and Waterproofing, Inc. for CR0589.1-6S3-RFI 2114 Series; Concrete and Steel
Encased Exterior Columns on Ramp Level. Mr. Corthell presented the memorandum,
requesting approval for Hensel Phelps Construction (HPC) to issue a Subcontract
Modification on BP-S00145, South Terminal C, Phase 1 - Airside Early Interiors
(GMP No. 6-S.3), at the Orlando International Airport, in the total deductive
amount of ($13,719.00) to Alpha Insulation and Waterproofing, Inc. for
CR0589.1-6S3-RFI 2114 Series; Concrete and Steel Encased Exterior Columns on
Ramp Level. Bid Package for BP-S145 07.07 "Intumescent Fireproofing" has been
previously awarded within GMP No. 6-S.3 to Alpha Insulation and Waterproofing,
Inc., CC No. 20180807.010.
HPC is requesting to issue a Subcontractor Modification to Alpha Insulation
and Waterproofing, Inc. in the total deductive Lump Sum amount of ($13,719.00)
for CR0589.1-6S3-RFI 2114 Series; Concrete and Steel Encased Exterior Columns
on Ramp Level. The modified scope of work consists of the credit associated
with deleting the Intumescent Fire-Resistive Coating at three columns in Areas
29 and 31 on the Ramp Level. Responses to RFI 2114 Series confirmed the Design
Intent of installing concrete encasement with steel jacket at two locations
in Area 31 (Gridlines B4/X41-X42) and installing concrete encasement at one
location in Area 29 (Gridline B4/X31), per RFI 2114.2 response and sketches.
The approval of this Subcontractor Modification to Alpha Insulation and
Waterproofing, Inc. resolves all requests for cost and time resulting from RFI
2114 Series in GMP No. 6-S.3 for Phase 1. Cost impacts of RFI 2114 Series to
GMP Nos. 6-S.1, 6-S.4 and 6-S.6 will be submitted via future CRs.
HPC has submitted documentation including the subcontractor's proposal to
support this request. An independent cost estimate is included. By approving
this request, the Owner does not waive its right to enforce the contract
requirements for other requests for cost or time.
The effect of this Subcontractor Modification for this project is as follows:
HPC to issue a subcontract modification to Alpha
Insulation and Waterproofing, Inc. in the deductive
lump sum amount of: $ (13,719.00)
Add to P1 Owner Contingency: $ 13,719.00
Hensel Phelps Construction is committed to 20% MWBE and 4% LDB participation
for Construction Services. The subcontractor identified and committed to
participate on BP-S00145 (GMP No. 6-S.3) for this subcontract modification is
Alpha Insulation and Waterproofing, Inc. (Non-MWBE/LDB/VBE). There is no small
business participation associated with this modification.
Minutes of the Construction Committee Meeting, June 9, 2020
Page 8 of 38
Ms. Sharman asked if this item has taken into account any potential scope
reductions. Mr. Corthell answered yes, that this item has been reviewed and
determined to be necessary at this time, as well as within any projected
reductions in scope.
Agenda Item Nos. 3-A, 3-B, 3-C, 3-D, 3-E, 3-F, 3-G, 3-H, 3-I, 3-J, 3-K, 3-L,
3-M, 3-N, 3-O, 3-P, 3-Q, 3-R, 3-S, 3-T, 3-U, 3-V, 3-W, 3-X, 3-Y, and 3-Z were
considered in one motion.
Upon motion of Mr. Patterson, second by Mr. Hunt, vote carried by roll-call,
with all votes yea, to approve Hensel Phelps Construction to issue a
Subcontractor Modification to Alpha Insulation and Waterproofing, Inc. on BP-
S00145, South Terminal C, Phase 1 - Airside Early Interiors (GMP No. 6-S.3),
for the total deductive lump sum amount of ($13,719.00), with funding credited
to Passenger Facility Charges and General Airport Revenue Bonds.
D. Subcontractor Modification for BP-S00146 (GMP No. 7-S) with Banker Steel Co., LLC for CR0493.1-LST-RFIs 2095-2095.4 - Elevator Slab Extensions and CMU
Structural Details. Mr. Corthell presented the memorandum, requesting approval
for Turner-Kiewit Joint Venture (TKJV) to issue a Subcontract Modification on
BP-S00146, South Terminal C, Phase 1 - Landside Terminal, Structure and
Enclosure (GMP No. 7-S), at the Orlando International Airport, in the total
amount of $100,755.00 to Banker Steel Co., LLC for CR0493.1-LST-RFIs 2095-
2095.4 - Elevator Slab Extensions and CMU Structural Details. Bid Package
5.0.0 "Structural Steel" was previously awarded within GMP No. 7-S to Banker
Steel Co., LLC, CC No. 20180313.010.
TKJV is proposing a subcontract modification to Banker Steel Co., LLC in the
total lump sum amount of $100,755.00 for CR0493.1-LST-RFI 2095 Series -
Elevator Slab Extensions and CMU Structural Details. The modified scope of
work consists of necessary labor, material and engineering costs for the
installation of steel bent plates at Elevators 2.1, 2.2, 2.3, 4.1, 8.1, 8.2,
8.3, 10.1, 10.2, 12.1 and 12.2, per RFIs 2095, 2095.1, 2095.2, 2095.3, and
2095.4.
The approval of this subcontract modification to Banker Steel Co., LLC resolves
all requests for cost and time associated with RFIs 2095, 2095.1, 2095.2,
2095.3, and 2095.4 in GMP No. 7-S. Cost impacts to GMP No. 7-S.1 for the
Masonry scope were submitted under CR0493. Cost impacts to GMP No. 7-S.1 for
the Drywall scope will be submitted for CCM review in a future CR. There are
no cost impacts to GMP Nos. 7-S.2, 7-S.3 and 7-S.4.
TKJV has submitted documentation including the subcontractor's proposal to
support their request. An independent cost estimate is included. By approving
this request, the Owner does not waive its right to enforce the contract
requirements for other requests for cost or time.
The effect of this Subcontractor Modification for this project is as follows:
TKJV to issue a subcontract modification to Banker
Steel Co., LLC in the lump sum amount of: $ 100,755.00
Deduct from P1 CMAR Contingency: $ (100,755.00)
Turner-Kiewit Joint Venture is committed to 20% MWBE and 4% LDB participation
for Construction Services. The subcontractor identified and committed to
participate on BP-S00146 (GMP No. 7-S) for this subcontract modification is
Banker Steel Co., LLC (Non-MWBE/LDB/VBE). There is 22% MWBE participation
associated with this modification.
Minutes of the Construction Committee Meeting, June 9, 2020
Page 9 of 38
Ms. Sharman asked if this item has taken into account any potential scope
reductions. Mr. Corthell answered yes, that this item has been reviewed and
determined to be necessary at this time, as well as within any projected
reductions in scope.
Agenda Item Nos. 3-A, 3-B, 3-C, 3-D, 3-E, 3-F, 3-G, 3-H, 3-I, 3-J, 3-K, 3-L,
3-M, 3-N, 3-O, 3-P, 3-Q, 3-R, 3-S, 3-T, 3-U, 3-V, 3-W, 3-X, 3-Y, and 3-Z were
considered in one motion.
Upon motion of Mr. Patterson, second by Mr. Hunt, vote carried by roll-call,
with all votes yea, to approve Turner-Kiewit Joint Venture to issue a
Subcontractor Modification to Banker Steel Co., LLC on BP-S00146, South
Terminal C, Phase 1 - Landside Terminal, Structure and Enclosure (GMP No.
7-S), for the total lump sum amount of $100,755.00, with funding from Passenger
Facility Charges and General Airport Revenue Bonds.
E. Subcontractor Modification for BP-S00146 (GMP No. 7-S) with Banker Steel Co., LLC for CR0684-7S-LST-RFIs 2753 and 2754-Added Roof Openings. Mr. Corthell
presented the memorandum, requesting approval for Turner-Kiewit Joint Venture
(TKJV) to issue a Subcontract Modification on BP-S00146, South Terminal C,
Phase 1 - Landside Terminal, Structure and Enclosure (GMP No. 7-S), at the
Orlando International Airport, in the total amount of $71,467.00 to Banker
Steel Co., LLC for CR0684-7S-LST-RFIs 2753 and 2754-Added Roof Openings. Bid
Package 5.0.0 "Structural Steel" was previously awarded within GMP No. 7 to
Banker Steel Co. LLC, CC No. 20180313.010.
TKJV is proposing a subcontract modification to Banker Steel Co. LLC in the
total lump sum amount of $71,467.00 for CR0684-7S-LST-RFIs 2753 and 2754-Added
Roof Openings. The modified scope of work consists of all additional material,
labor and equipment costs associated with the additional 1.84 tons of
structural steel required to provide the corrective additional work resulting
from the coordination of structural drawings with architectural and mechanical
disciplines when structural members had been erected in the field.
The approval of this subcontract modification to Kirlin Florida, LLC resolves
all requests for cost and time associated with RFIs 2753 and 2754 in GMP No.
7. There are no cost impacts to GMP Nos. 7.1, 7-S.2, 7-S.3 and 7-S.4.
TKJV has submitted documentation including the subcontractor's proposal to
support their request. An independent cost estimate is included. By approving
this request, the Owner does not waive its right to enforce the contract
requirements for other requests for cost or time.
The effect of this Subcontractor Modification for this project is as follows:
TKJV to issue a subcontract modification to Banker
Steel Co., LLC in the lump sum amount of: $ 71,467.00
Deduct from P1 CMAR Contingency: $ (71,467.00)
Turner-Kiewit Joint Venture is committed to 20% MWBE and 4% LDB participation
for Construction Services. The subcontractor identified and committed to
participate on BP-S00146 (GMP No. 7-S) for this subcontract modification is
Banker Steel Co., LLC (Non-MWBE/LDB/VBE). There is no small business
participation associated with this modification.
Ms. Sharman asked if this item has taken into account any potential scope
reductions. Mr. Corthell answered yes, that this item has been reviewed and
Minutes of the Construction Committee Meeting, June 9, 2020
Page 10 of 38
determined to be necessary at this time, as well as within any projected
reductions in scope.
Agenda Item Nos. 3-A, 3-B, 3-C, 3-D, 3-E, 3-F, 3-G, 3-H, 3-I, 3-J, 3-K, 3-L,
3-M, 3-N, 3-O, 3-P, 3-Q, 3-R, 3-S, 3-T, 3-U, 3-V, 3-W, 3-X, 3-Y, and 3-Z were
considered in one motion.
Upon motion of Mr. Patterson, second by Mr. Hunt, vote carried by roll-call,
with all votes yea, to approve Turner-Kiewit Joint Venture to issue a
Subcontractor Modification to Banker Steel Co., LLC on BP-S00146, South
Terminal C, Phase 1 - Landside Terminal, Structure and Enclosure (GMP No.
7-S), for the total lump sum amount of $71,467.00, with funding from Passenger
Facility Charges and General Airport Revenue Bonds.
F. Subcontractor Modification for BP-S00146 (GMP No. 7-S) with Banker Steel Co., LLC for CR0733-LST-RFIs 2547-2547.2 Added Structural Steel to Mechanical Shaft.
Mr. Corthell presented the memorandum, requesting approval for Turner-Kiewit
Joint Venture (TKJV) to issue a Subcontract Modification on BP-S00146, South
Terminal C, Phase 1 - Landside Terminal, Structure and Enclosure (GMP No.
7-S), at the Orlando International Airport, in the total amount of $229,331.00
to Banker Steel Co., LLC for CR0733-LST-RFIs 2547-2547.2 Added Structural
Steel to Mechanical Shaft. Bid Package 5.0.0 "Structural Steel" was previously
awarded within GMP No. 7-S to Banker Steel Co., LLC, CC No. 20180313.010.
TKJV is proposing a subcontract modification to Banker Steel Co., LLC in the
total lump sum amount of $229,331.00 for CR0733-LST-RFIs 2547-2547.2 Added
Structural Steel to Mechanical Shaft. The modified scope of work consists of
added structural steel members to support equipment risers in the mechanical
shafts, Areas 4 and 12, as captured in RFIs 2547, 2547.1 and 2547.2.
The approval of this subcontract modification to Banker Steel Co. LLC resolves
all requests for cost and time associated with RFIs 2547, 2547.1 and 2547.2
scope of work. There are no costs impacts to GMP Nos. 7-S.1, 7S.2 and 7S.3.
TKJV has submitted documentation including the subcontractor's proposal to
support their request. An independent cost estimate is included. By approving
this request, the Owner does not waive its right to enforce the contract
requirements for other requests for cost or time.
The effect of this Subcontractor Modification for this project is as follows:
TKJV to issue a subcontract modification to Banker
Steel Co., LLC in the lump sum amount of: $ 229,331.00
Deduct from P1 CMAR Contingency: $ (229,331.00)
Turner-Kiewit Joint Venture is committed to 20% MWBE and 4% LDB participation
for Construction Services. The subcontractor identified and committed to
participate on BP-S00146 (GMP No. 7-S) for this subcontract modification is
Banker Steel Co., LLC (Non-MWBE/LDB/VBE). There is 10.7% MWBE participation
associated with this modification.
Ms. Sharman asked if this item has taken into account any potential scope
reductions. Mr. Corthell answered yes, that this item has been reviewed and
determined to be necessary at this time, as well as within any projected
reductions in scope.
Agenda Item Nos. 3-A, 3-B, 3-C, 3-D, 3-E, 3-F, 3-G, 3-H, 3-I, 3-J, 3-K, 3-L,
3-M, 3-N, 3-O, 3-P, 3-Q, 3-R, 3-S, 3-T, 3-U, 3-V, 3-W, 3-X, 3-Y, and 3-Z were
considered in one motion.
Minutes of the Construction Committee Meeting, June 9, 2020
Page 11 of 38
Upon motion of Mr. Patterson, second by Mr. Hunt, vote carried by roll-call,
with all votes yea, to approve Turner-Kiewit Joint Venture to issue a
Subcontractor Modification to Banker Steel Co., LLC on BP-S00146, South
Terminal C, Phase 1 - Landside Terminal, Structure and Enclosure (GMP No.
7-S), for the total lump sum amount of $229,331.00, with funding from Passenger
Facility Charges and General Airport Revenue Bonds.
G. Subcontractor Modification for BP-S00146 (GMP No. 7-S) with Banker Steel Co., LLC for CR0734-LST-RFIs 3340.1 and 3340.2 Removal of Wind Girts at South Wall
Area 8. Mr. Corthell presented the memorandum, requesting approval for Turner-
Kiewit Joint Venture (TKJV) to issue a Subcontract Modification on BP-S00146,
South Terminal C, Phase 1 - Landside Terminal, Structure and Enclosure (GMP
No. 7-S), at the Orlando International Airport, in the total amount of
$29,097.00 to Banker Steel Co., LLC for CR0734-LST-RFIs 3340.1 and 3340.2
Removal of Wind Girts at South Wall Area 8. Bid Package 5.0.0 "Structural
Steel" was previously awarded within GMP No. 7-S to Banker Steel Co., LLC, CC
No. 20180313.010.
TKJV is proposing a subcontract modification to Banker Steel Co., LLC in the
total lump sum amount of $29,097.00 for CR0734-LST-RFI 3340.1 Removal of Wind
Girts at South Wall Area 8. RFI 3340.1 response explains that the exterior
framing and drywall subcontractor installed a wall engineered to not utilize
any lateral bracing. The modified scope consists of necessary labor, material
and equipment for the removal of two wind girts at South Wall in Area 8, per
RFIs 3340.1 and 3340.2.
The approval of this subcontract modification to Banker Steel Co., LLC resolves
all requests for cost and time associated with RFI 3340 series in GMP No.
7-S. There are no cost impacts to GMP Nos. 7-S.1, 7-S.2, 7-S.3 and 7-S.4.
TKJV has submitted documentation including the subcontractor's proposal to
support their request. An independent cost estimate is included. By approving
this request, the Owner does not waive its right to enforce the contract
requirements for other requests for cost or time.
The effect of this Subcontractor Modification for this project is as follows:
TKJV to issue a subcontract modification to Banker
Steel Co., LLC in the lump sum amount of: $ 29,097.00
Deduct from P1 CMAR Contingency: $ (29,097.00)
Turner-Kiewit Joint Venture is committed to 20% MWBE and 4% LDB participation
for Construction Services. The subcontractor identified and committed to
participate on BP-S00146 (GMP No. 7-S) for this subcontract modification is
Banker Steel Co., LLC (Non-MWBE/LDB/VBE). There is no small business
participation associated with this modification.
Ms. Sharman asked if this item has taken into account any potential scope
reductions. Mr. Corthell answered yes, that this item has been reviewed and
determined to be necessary at this time, as well as within any projected
reductions in scope.
Agenda Item Nos. 3-A, 3-B, 3-C, 3-D, 3-E, 3-F, 3-G, 3-H, 3-I, 3-J, 3-K, 3-L,
3-M, 3-N, 3-O, 3-P, 3-Q, 3-R, 3-S, 3-T, 3-U, 3-V, 3-W, 3-X, 3-Y, and 3-Z were
considered in one motion.
Upon motion of Mr. Patterson, second by Mr. Hunt, vote carried by roll-call,
with all votes yea, to approve Turner-Kiewit Joint Venture to issue a
Minutes of the Construction Committee Meeting, June 9, 2020
Page 12 of 38
Subcontractor Modification to Banker Steel Co., LLC on BP-S00146, South
Terminal C, Phase 1 - Landside Terminal, Structure and Enclosure (GMP No.
7-S), for the total lump sum amount of $29,097.00, with funding from General
Airport Revenue Bonds.
H. Subcontractor Modification for BP-S00146 (GMP No. 7-S) with Banker Steel Co., LLC for CR0750-LST-RFI 2960 Base of Prow Details at LST Bridge. Mr. Corthell
presented the memorandum, requesting approval for Turner-Kiewit Joint Venture
(TKJV) to issue a Subcontract Modification on BP-S00146, South Terminal C,
Phase 1 - Landside Terminal, Structure and Enclosure (GMP No. 7-S), at the
Orlando International Airport, in the total amount of $10,926.00 to Banker
Steel Co., LLC for CR0750-LST-RFI 2960 Base of Prow Details at LST Bridge.
Bid Package 5.0.0 "Structural Steel" was previously awarded within GMP No.
7-S to Banker Steel Co. LLC, CC No. 20180313.010.
TKJV is proposing a subcontract modification to Banker Steel Co., LLC in the
total lump sum amount of $10,926.00 for CR0750-LST-RFI 2960 Base of Prow
Details at LST Bridge. The modified scope of work consists of all costs
associated with the added steel plates at the LST Bridge tie-in, per RFI 2960.
The approval of this subcontract modification to Banker Steel Co., LLC resolves
all requests for costs and time associated with RFI 2960 in GMP No. 7-S for
Structural Steel scope only. Additional cost impacts to GMP Nos. 7-S and
7-S.1 will be submitted under separate CRs. There are no cost impacts to GMP
Nos. 7-S.2, 7-S.3 and 7-S.4.
TKJV has submitted documentation including the subcontractor's proposal to
substantiate this request. An independent cost estimate is included. By
approving this request, the Owner does not waive its right to enforce the
contract requirements for other requests for costs or time.
The effect of this Subcontractor Modification for this project is as follows:
TKJV to issue a subcontract modification to Banker
Steel Co., LLC in the lump sum amount of: $ 10,926.00
Deduct from P1 CMAR Contingency: $ (10,926.00)
Turner-Kiewit Joint Venture is committed to 20% MWBE and 4% LDB participation
for Construction Services. The subcontractor identified and committed to
participate on BP-S00146 (GMP No. 7-S) for this subcontract modification is
Banker Steel Co., LLC (Non-MWBE/LDB/VBE). There is no small business
participation associated with this modification.
Ms. Sharman asked if this item has taken into account any potential scope
reductions. Mr. Corthell answered yes, that this item has been reviewed and
determined to be necessary at this time, as well as within any projected
reductions in scope.
Agenda Item Nos. 3-A, 3-B, 3-C, 3-D, 3-E, 3-F, 3-G, 3-H, 3-I, 3-J, 3-K, 3-L,
3-M, 3-N, 3-O, 3-P, 3-Q, 3-R, 3-S, 3-T, 3-U, 3-V, 3-W, 3-X, 3-Y, and 3-Z were
considered in one motion.
Upon motion of Mr. Patterson, second by Mr. Hunt, vote carried by roll-call
with all votes yea, to approve Turner-Kiewit Joint Venture to issue a
Subcontractor Modification to Banker Steel Co., LLC on BP-S00146, South
Terminal C, Phase 1 - Landside Terminal, Structure and Enclosure (GMP No.
7-S), for the total lump sum amount of $10,926.00, with funding from Passenger
Facility Charges and General Airport Revenue Bonds.
Minutes of the Construction Committee Meeting, June 9, 2020
Page 13 of 38
I. Subcontractor Modification for BP-S00146 (GMP No. 7-S) with Banker Steel Co., LLC for CR0752.1-LST-RFIs 2935 and 2935.1 Revised Precast Connections.
Mr. Corthell presented the memorandum, requesting approval for Turner-Kiewit
Joint Venture (TKJV) to issue a Subcontract Modification on BP-S00146, South
Terminal C, Phase 1 - Landside Terminal, Structure and Enclosure (GMP No.
7-S), at the Orlando International Airport, in the total amount of $117,528.00
to Banker Steel Co., LLC for CR0752.1-LST-RFIs 2935 and 2935.1 Revised Precast
Connections. Bid Package 5.0.0 "Structural Steel" was previously awarded
within GMP No. 7-S to Banker Steel Co., LLC, CC No. 20180313.010.
TKJV is proposing a subcontract modification to Banker Steel Co., LLC in the
total lump sum amount of $117,528.00 for CR0752.1-LST-RFIs 2935 and 2935.1
Revised Precast Connections. The modified scope of work consists of necessary
labor, material, equipment and engineering costs for the fabrication and
installation of approximately 1 ton of structural steel and stiffener plates
for the revised precast connections, per RFIs 2935 series.
The approval of this subcontract modification to Banker Steel Co., LLC resolves
all requests for costs and time associated with RFI 2935 series in GMP No.
7-S. Costs impacts to GMP No. 7-S.1 for the Precast Panels scope were submitted
under CR0752. Cost impacts to GMP No. 7-S.1 for the Drywall scope will be
submitted under CR0752.2. There are no cost impacts to GMP Nos. 7-S.2, 7-S.3
and 7-S.4.
TKJV has submitted documentation including the subcontractor's proposal with
supporting back-up to substantiate this request. An independent cost estimate
is included. By approving this request, the Owner does not waive its right to
enforce the contract requirements for other requests for costs or time.
The effect of this Subcontractor Modification for this project is as follows:
TKJV to issue a subcontract modification to Banker
Steel Co., LLC in the lump sum amount of: $ 117,528.00
Deduct from P1 CMAR Contingency: $ (117,528.00)
Turner-Kiewit Joint Venture is committed to 20% MWBE and 4% LDB participation
for Construction Services. The subcontractor identified and committed to
participate on BP-S00146 (GMP No. 7-S) for this subcontract modification is
Banker Steel Co., LLC (Non-MWBE/LDB/VBE). There is no small business
participation associated with this modification.
Ms. Sharman asked if this item has taken into account any potential scope
reductions. Mr. Corthell answered yes, that this item has been reviewed and
determined to be necessary at this time, as well as within any projected
reductions in scope.
Agenda Item Nos. 3-A, 3-B, 3-C, 3-D, 3-E, 3-F, 3-G, 3-H, 3-I, 3-J, 3-K, 3-L,
3-M, 3-N, 3-O, 3-P, 3-Q, 3-R, 3-S, 3-T, 3-U, 3-V, 3-W, 3-X, 3-Y, and 3-Z were
considered in one motion.
Upon motion of Mr. Patterson, second by Mr. Hunt, vote carried by roll-call,
with all votes yea, to approve Turner-Kiewit Joint Venture to issue a
Subcontractor Modification to Banker Steel Co., LLC on BP-S00146, South
Terminal C, Phase 1 - Landside Terminal, Structure and Enclosure (GMP No.
7-S), for the total lump sum amount of $117,528.00, with funding from Passenger
Facility Charges and General Airport Revenue Bonds.
Minutes of the Construction Committee Meeting, June 9, 2020
Page 14 of 38
J. Subcontractor Modification for BP-S00146 (GMP No. 7-S) with Physical Security, LLC for CR0835-LST-RFIs 3220 and 3220.1 Window Type H L1-L2. Mr. Corthell
presented the memorandum, requesting approval for Turner-Kiewit Joint Venture
(TKJV) to issue a Subcontract Modification on BP-S00146, South Terminal C,
Phase 1 - Landside Terminal, Structure and Enclosure (GMP No. 7-S), at the
Orlando International Airport, in the total amount of $2,755.00 to Physical
Security, LLC for CR0835-LST-RFIs 3220 and 3220.1 Window Type H L1-L2. Bid
Package 8.2.0 "Curtain Wall" was previously awarded within GMP No. 7-S to
Physical Security, LLC, CC No. 20180528.02A.
TKJV is proposing a subcontract modification to Physical Security, LLC in the
total lump sum amount of $2,755.00 for CR0835-LST-RFIs 3220 and 3220.1 Window
Type H L1-L2. The modified scope of work consists of added costs for the
installation of a new 3-foot by 10-foot Kawneer 350 door assembly, and a credit
for the previous window Type H, as captured in RFIs 3220 and 3220.1.
The approval of this subcontract modification to Physical Security, LLC
resolves all requests for costs and time associated with RFIs 3220 and 3220.1
scope of work in GMP No. 7-S. There are no cost impacts to GMP Nos. 7-S.1, 7-
S.2, 7-S.3 and 7-S.4.
TKJV has submitted documentation including the subcontractor's proposal to
substantiate this request. An independent cost estimate is included. By
approving this request, the Owner does not waive its right to enforce the
contract requirements for other requests for costs or time.
The effect of this Subcontractor Modification for this project is as follows:
TKJV to issue a subcontract modification to Physical
Security, LLC in the lump sum amount of: $ 2,755.00
Deduct from P1 CMAR Contingency: $ (2,755.00)
Turner-Kiewit Joint Venture is committed to 20% MWBE and 4% LDB participation
for Construction Services. The subcontractor identified and committed to
participate on BP-S00146 (GMP No. 7-S) for this subcontract modification is
Physical Security, LLC (Non-MWBE/LDB/VBE). There is no small business
participation associated with this modification.
Ms. Sharman asked if this item has taken into account any potential scope
reductions. Mr. Corthell answered yes, that this item has been reviewed and
determined to be necessary at this time, as well as within any projected
reductions in scope.
Agenda Item Nos. 3-A, 3-B, 3-C, 3-D, 3-E, 3-F, 3-G, 3-H, 3-I, 3-J, 3-K, 3-L,
3-M, 3-N, 3-O, 3-P, 3-Q, 3-R, 3-S, 3-T, 3-U, 3-V, 3-W, 3-X, 3-Y, and 3-Z were
considered in one motion.
Upon motion of Mr. Patterson, second by Mr. Hunt, vote carried by roll-call,
with all votes yea, to approve Turner-Kiewit Joint Venture to issue a
Subcontractor Modification to Physical Security, LLC on BP-S00146, South
Terminal C, Phase 1 - Landside Terminal, Structure and Enclosure (GMP No.
7-S), for the total lump sum amount of $2,755.00, with funding from Passenger
Facility Charges and General Airport Revenue Bonds.
K. Subcontractor Modification for BP-S00146 (GMP No. 7-S) with Banker Steel Co., LLC for CR0965-LST-RFIs 3857 and 3857.1 Curtain Wall Clearance. Mr. Corthell
presented the memorandum, requesting approval for Turner-Kiewit Joint Venture
(TKJV) to issue a Subcontract Modification on BP-S00146, South Terminal C,
Phase 1 - Landside Terminal, Structure and Enclosure (GMP No. 7-S), at the
Minutes of the Construction Committee Meeting, June 9, 2020
Page 15 of 38
Orlando International Airport, in the total amount of $7,804.00 to Banker
Steel Co., LLC for CR0965-LST-RFIs 3857 and 3857.1 Curtain Wall Clearance.
Bid Package 5.0.0 "Structural Steel" was previously awarded within GMP No.
7-S to Banker Steel Co. LLC, CC No. 20180313.010.
TKJV is proposing a subcontract modification to Banker Steel Co., LLC in the
total lump sum amount of $7,804.00 for CR0965-LST-RFIs 3857 and 3857.1 Curtain
Wall Clearance. The modified scope of work consists of necessary labor costs
to trim the top chord boulevard truss at Gridline L2 to provide clearance for
curtain wall system, per RFIs 3857 and 3857.1.
The approval of this subcontract modification to Banker Steel Co., LLC resolves
all requests for cost and time associated with RFIs 3857 and 3857.1 scope of
work in GMP No. 7-S. There are no cost impacts to GMP Nos. 7-S.1, 7-S.2, 7-
S.3 and 7-S.4.
TKJV has submitted documentation including the subcontractor's proposal to
support their request. An independent cost estimate is included. By approving
this request, the Owner does not waive its right to enforce the contract
requirements for other requests for cost or time.
The effect of this Subcontractor Modification for this project is as follows:
TKJV to issue a subcontract modification to Banker
Steel Co., LLC in the lump sum amount of: $ 7,804.00
Deduct from P1 CMAR Contingency: $ (7,804.00)
Turner-Kiewit Joint Venture is committed to 20% MWBE and 4% LDB participation
for Construction Services. The subcontractor identified and committed to
participate on BP-S00146 (GMP No. 7-S) for this subcontract modification is
Banker Steel Co., LLC (Non-MWBE/LDB/VBE). There is no small business
participation associated with this modification.
Ms. Sharman asked if this item has taken into account any potential scope
reductions. Mr. Corthell answered yes, that this item has been reviewed and
determined to be necessary at this time, as well as within any projected
reductions in scope.
Agenda Item Nos. 3-A, 3-B, 3-C, 3-D, 3-E, 3-F, 3-G, 3-H, 3-I, 3-J, 3-K, 3-L,
3-M, 3-N, 3-O, 3-P, 3-Q, 3-R, 3-S, 3-T, 3-U, 3-V, 3-W, 3-X, 3-Y, and 3-Z were
considered in one motion.
Upon motion of Mr. Patterson, second by Mr. Hunt, vote carried by roll-call,
with all votes yea, to approve Turner-Kiewit Joint Venture to issue a
Subcontractor Modification to Banker Steel Co., LLC on BP-S00146, South
Terminal C, Phase 1 - Landside Terminal, Structure and Enclosure (GMP No.
7-S), for the total lump sum amount of $7,804.00, with funding from Passenger
Facility Charges and General Airport Revenue Bonds.
L. Subcontract Modifications for BP-S00147 (GMP No. 7-S.1) with MSE2, Inc. dba Mader Southeast; Enclos Corp.; and, Hommes Masonry Inc. dba Toltec
Construction; for CR0705.1-LST-Bulletin 34 Drywall, Interior Glazing and
Masonry Scopes. Mr. Corthell presented the memorandum, requesting approval
for Turner-Kiewit Joint Venture (TKJV) to issue Subcontract Modifications on
BP-S00147, South Terminal C, Phase 1 - Landside Terminal Remaining Structure
and Systems (GMP No. 7-S.1), at the Orlando International Airport, in the
total deductive amount of ($12,511.00) to MSE2, Inc. dba Mader Southeast;
Enclos Corp.; and Hommes Masonry Inc. dba Toltec Construction; for CR0705.1-
LST-Bulletin 34 Drywall, Interior Glazing and Masonry Scopes. Bid Package
Minutes of the Construction Committee Meeting, June 9, 2020
Page 16 of 38
9.1.0 "Drywall and Framing" was previously awarded within GMP No. 7-S.1 to
MSE2, Inc., CC No. 20181002.009.
Bid Package 8.3.0 "Interior Glazing" was previously awarded within GMP No.
7-S.1 to Enclos Corp., CC No. 20181002.009.
Bid Package 4.0.0 for Masonry was previously awarded within GMP No. 7-S.1 to
Hommes Masonry Inc. dba Toltec Construction, CC No. 20181002.09
TKJV is proposing the following subcontract modifications to:
1. MSE2, Inc. dba Mader Southeast in the lump sum amount of $4,997.00 for CR0705.1-LST-Bulletin 34 Drywall Scope. The modified scope of work
consists of necessary labor and material costs for the revised CMU wall
to drywall at Stair 2.2 from ground floor to roof, as captured in LST
Bulletin 34.
2. Enclos Corp. in the lump sum amount of $583.00 for CR0705.1-LST-Bulletin 34 Interior Glazing Scope. The modified scope of work consists of
necessary labor and material costs for the added Sidelite Glass Panels
for door frame Type F3, as captured in LST Bulletin 34.
3. Hommes Masonry Inc. dba Toltec Construction in the deductive lump sum amount of ($18,091.00) for CR0705.1-LST-Bulletin 34 Masonry Scope. The
modified scope of work includes credits for the removal of CMU wall on
Stair 2.2 from ground floor to roof, as captured in LST Bulletin 34.
The approval of these subcontract modifications to MSE2, Inc. dba Mader
Southeast; Enclos Corp.; and Hommes Masonry Inc. dba Toltec Construction;
resolves all requests for cost and time associated with LST Bulletin 34 scope
of work in GMP No. 7-S.1. Cost impacts to GMP No. 7-S will be submitted for
CCM review under CR0705. There are no cost impacts to GMP Nos. 7-S.2, 7-S.3
and 7-S.4.
TKJV has submitted documentation including the subcontractor's proposal to
support their request. An independent cost estimate is included. By approving
this request, the Owner does not waive its right to enforce the contract
requirements for other requests for cost or time.
The effect of these Subcontract Modifications for this project is as follows:
TKJV to issue a subcontract modification to MSE2, Inc.
dba Mader Southeast in the amount of: $ 4,997.00
TKJV to issue a subcontract modification to Enclos
Corp. in the amount of: $ 583.00
TKJV to issue a subcontract modification to Hommes
Masonry Inc. dba Toltec Construction in the deductive
amount of: $ (18,091.00)
Add to P1 Owner Contingency: $ 12,511.00
Turner-Kiewit Joint Venture is committed to 20% MWBE and 4% LDB participation
for Construction Services. The subcontractors identified and committed to
participate on BP-S00147 (GMP No. 7-S.1) for these subcontract modifications
are MSE2, Inc. dba Mader Southeast (Non-MWBE/LDB/VBE); Enclos Corp. (Non-
MWBE/LDB/VBE); and Hommes Masonry Inc. dba Toltec Construction (MWBE). These
modifications result in a net deduct of ($17,504.70) to MWBEs.
Ms. Sharman asked if this item has taken into account any potential scope
reductions. Mr. Corthell answered yes, that this item has been reviewed and
Minutes of the Construction Committee Meeting, June 9, 2020
Page 17 of 38
determined to be necessary at this time, as well as within any projected
reductions in scope.
Agenda Item Nos. 3-A, 3-B, 3-C, 3-D, 3-E, 3-F, 3-G, 3-H, 3-I, 3-J, 3-K, 3-L,
3-M, 3-N, 3-O, 3-P, 3-Q, 3-R, 3-S, 3-T, 3-U, 3-V, 3-W, 3-X, 3-Y, and 3-Z were
considered in one motion.
Upon motion of Mr. Patterson, second by Mr. Hunt, vote carried by roll-call,
with all votes yea, to approve Turner-Kiewit Joint Venture to issue Subcontract
Modifications on BP-S00147, South Terminal C, Phase 1 - Landside Terminal
Remaining Structure and Systems (GMP No. 7-S.1), for the total deductive amount
of ($12,511.00), which includes the lump sum amount of $4,997.00 to MSE2, Inc.
dba Mader Southeast; the lump sum amount of $583.00 to Enclos Corp.; and the
deductive lump sum amount of ($18,091.00) to Hommes Masonry Inc. dba Toltec
Construction; with funding from Passenger Facility Charges and General Airport
Revenue Bonds.
M. Subcontract Modifications for BP-S00147 (GMP No. 7-S.1) with MSE2, Inc. dba Mader Southeast; and Taylor, Cotton & Ridley, Inc.; for CR0976-LST-RFI 4127
Fire Rating of Wall from Level 6 to Roof. Mr. Corthell presented the
memorandum, requesting approval for Turner-Kiewit Joint Venture (TKJV) to
issue Subcontract Modifications on BP-S00147, South Terminal C, Phase 1 -
Landside Terminal Remaining Structure and Systems (GMP No. 7-S.1), at the
Orlando International Airport, in the total amount of $40,781.00 to MSE2, Inc.
dba Mader Southeast; and Taylor, Cotton & Ridley, Inc.; for CR0976-LST-RFI
4127 Fire Rating of Wall from Level 6 to Roof. Bid Package 9.1.0 "Drywall and
Framing" was previously awarded within GMP No. 7-S.1 to MSE2, Inc., CC No.
20181002.009.
Bid Package 8.0.0 "Doors, Frames and Hardware" was previously awarded within
GMP No. 7-S.1 to Taylor, Cotton & Ridley, Inc., CC No. 20181002.009.
TKJV is proposing the following subcontract modifications to:
MSE2, Inc. dba Mader Southeast in the lump sum amount of $40,481.00 for
CR0976-LST-RFI 4127 Fire Rating of Wall from Level 6 to Roof. The
additional scope of work consists of necessary labor, material and
equipment costs for the revised wall type from EWS-00 to EWS-00e 2-hour
rated at gridline L8 in Area 3 from Level 6 to the roof, as captured in
RFI 4127.
Taylor, Cotton & Ridley, Inc. in the lump sum amount of $300.00 for
CR0976-LST-RFI 4127 Fire Rating of Wall from Level 6 to Roof. The
additional scope of work includes material costs for the upgraded fire
rating of door frame 06-0232, as captured in RFI 4127.
The approval of these subcontract modifications to MSE2, Inc. dba Mader
Southeast; and Taylor, Cotton & Ridley, Inc.; resolves all requests for cost
and time associated with RFI 4127 scope of work in GMP No. 7-S.1. There are
no cost impacts to GMP Nos. 7-S, 7-S.2, 7-S.3 and 7-S.4.
TKJV has submitted documentation including the subcontractor's proposal to
support their request. An independent cost estimate is included. By approving
this request, the Owner does not waive its right to enforce the contract
requirements for other requests for cost or time.
The effect of this Subcontract Modification for this project is as follows:
Minutes of the Construction Committee Meeting, June 9, 2020
Page 18 of 38
TKJV to issue a subcontract modification to MSE2, Inc.
dba Mader Southeast in the amount of: $ 40,481.00
TKJV to issue a subcontract modification to Taylor,
Cotton & Ridley, Inc. in the amount of: $ 300.00
Deduct from P1 Owner Contingency: $ (40,781.00)
Turner-Kiewit Joint Venture is committed to 20% MWBE and 4% LDB participation
for Construction Services. The subcontractors identified and committed to
participate on BP-S00147 (GMP No. 7-S.1) for these subcontract modifications
are MSE2, Inc. dba Mader Southeast (Non-MWBE/LDB/VBE) and Taylor, Cotton &
Ridley, Inc. (Non-MWBE/LDB/VBE). There is an overall 8.1% MWBE participation
associated with these modifications.
Ms. Sharman asked if this item has taken into account any potential scope
reductions. Mr. Corthell answered yes, that this item has been reviewed and
determined to be necessary at this time, as well as within any projected
reductions in scope.
Agenda Item Nos. 3-A, 3-B, 3-C, 3-D, 3-E, 3-F, 3-G, 3-H, 3-I, 3-J, 3-K, 3-L,
3-M, 3-N, 3-O, 3-P, 3-Q, 3-R, 3-S, 3-T, 3-U, 3-V, 3-W, 3-X, 3-Y, and 3-Z were
considered in one motion.
Upon motion of Mr. Patterson, second by Mr. Hunt, vote carried by roll-call,
with all votes yea, to approve Turner-Kiewit Joint Venture to issue Subcontract
Modifications on BP-S00147, South Terminal C, Phase 1 - Landside Terminal
Remaining Structure and Systems (GMP No. 7-S.1), for the total amount of
$40,781.00, which includes the lump sum amount of $40,481.00 to MSE2, Inc. dba
Mader Southeast; and the lump sum amount of $300.00 to Taylor, Cotton & Ridley,
Inc.; with funding from Passenger Facility Charges and General Airport Revenue
Bonds.
N. Subcontract Modification for BP-S00147 (GMP No. 7-S.1) with P&A Roofing & Sheet Metal, Inc. for CR1014-LST-RFI 4134 PVC Walkway at Skylight Eave.
Mr. Corthell presented the memorandum, requesting approval for Turner-Kiewit
Joint Venture (TKJV) to issue a Subcontract Modification on BP-S00147, South
Terminal C, Phase 1 - Landside Terminal Remaining Structure and Systems (GMP
No. 7-S.1), at the Orlando International Airport, in the total amount of
$12,794.00 to P&A Roofing & Sheet Metal, Inc. for CR1014-LST-RFI 4134 PVC
Walkway at Skylight Eave. Bid Package 7.2.0 "Roofing" was previously awarded
within GMP No. 7-S.1 to P&A Roofing & Sheet Metal, Inc., CC No. 20181002.009.
TKJV is proposing the following subcontract modification to P&A Roofing &
Sheet Metal, Inc. in the total lump sum amount of $12,794.00 for CR1014-LST-
RFI 4134 PVC Walkway at Skylight Eave. The modified scope of work consists of
all cost associated with the installation of additional Soprema Sentinel PVC
walkway pads at skylight eave, per RFI 4134.
The approval of this subcontract modifications to P&A Roofing & Sheet Metal,
Inc. resolves all requests for cost and time associated with RFI 4134 scope
of work in GMP No. 7-S.1. There are no cost impacts to GMP Nos. 7-S, 7-S.2,
7-S.3 and 7-S.4.
TKJV has submitted documentation including the subcontractor's proposal to
support their request. An independent cost estimate is included. By approving
this request, the Owner does not waive its right to enforce the contract
requirements for other requests for cost or time.
The effect of this Subcontract Modification for this project is as follows:
Minutes of the Construction Committee Meeting, June 9, 2020
Page 19 of 38
TKJV to issue a subcontract modification to P&A
Roofing & Sheet Metal, Inc. in the amount of: $ 12,794.00
Deduct from P1 Owner Contingency: $ (12,794.00)
Turner-Kiewit Joint Venture is committed to 20% MWBE and 4% LDB participation
for Construction Services. The subcontractor identified and committed to
participate on BP-S00147 (GMP No. 7-S.1) for this subcontract modification is
P&A Roofing & Sheet Metal, Inc. (Non-MWBE/LDB/VBE). There is no small business
participation associated with this modification.
Ms. Sharman asked if this item has taken into account any potential scope
reductions. Mr. Corthell answered yes, that this item has been reviewed and
determined to be necessary at this time, as well as within any projected
reductions in scope.
Agenda Item Nos. 3-A, 3-B, 3-C, 3-D, 3-E, 3-F, 3-G, 3-H, 3-I, 3-J, 3-K, 3-L,
3-M, 3-N, 3-O, 3-P, 3-Q, 3-R, 3-S, 3-T, 3-U, 3-V, 3-W, 3-X, 3-Y, and 3-Z were
considered in one motion.
Upon motion of Mr. Patterson, second by Mr. Hunt, vote carried by roll-call,
with all votes yea, to approve Turner-Kiewit Joint Venture to issue a
Subcontract Modification to P&A Roofing & Sheet Metal, Inc. on BP-S00147,
South Terminal C, Phase 1 - Landside Terminal Remaining Structure and Systems
(GMP No. 7-S.1), for the total lump sum amount of $12,794.00, with funding
from Passenger Facility Charges and General Airport Revenue Bonds.
O. Subcontract Modification for BP-S00150 (GMP No. 9-S) with Morton Electric, Inc. for CR0994-PKG-RFIs 3861, 3862, 3863, 4046, 4145, and 4373 - Multiple RFI
Electrical Revisions (CWA BP S150-007). Mr. Corthell presented the memorandum,
requesting approval for Turner-Kiewit Joint Venture (TKJV) to issue a
Subcontract Modification on BP-S00150, South Terminal C, Phase 1, Parking
Facility - Phase 1 (GMP No. 9-S), at the Orlando International Airport, in the
total amount of $49,133.00 to Morton Electric, Inc. for CR0994-PKG-RFIs 3861,
3862, 3863, 4046, 4145, and 4373 - Multiple RFI Electrical Revisions (CWA BP
S150-007).
Bid Package: 26.0.0 "Electrical" was previously awarded within the GMP No.
9-S to Morton Electric, Inc., CC No. 20171010.16.
RFI: 3861-Dry System Fire Suppression. Deduct from Owner Contingency
TKJV is proposing a Subcontractor Modification to Morton Electric, Inc.
in the Lump Sum amount of $1,367.00 for CR0994-PKG-RFIs 3861, 3862,
3863, 4046, 4145 and 4373 - Multiple RFI Electrical Revisions (CWA BP
S150-007). RFI 3861 was issued to identify the power and monitoring
requirements for the dry pipe system. The RFI response includes
electrical and fire alarm sketches for circuit designation and monitoring
requirements. The modified scope of work consists of all labor and
material costs associated with providing wiring for the air compressor
per RFI 3861 response.
RFI 3862-Elevator ATS Communication. Deduct from CMAR Contingency.
TKJV is proposing a Subcontractor Modification to Morton Electric, Inc.
in the Lump Sum amount of $25,497.00 for CR0994-PKG-RFIs 3861, 3862,
3863, 4046, 4145 and 4373 - Multiple RFI Electrical Revisions (CWA BP
S150-007). RFI 3862 was issued to request direction on how to make this
connection. The response was to utilize the existing interlock in the
Minutes of the Construction Committee Meeting, June 9, 2020
Page 20 of 38
existing Phase 1 elevator machine room, extend the existing and provide
additional pathways as required for routing the low voltage cabling to
new interlock in Elevators 3 and 4. The modified scope of work consists
of all material, labor and equipment costs to provide control
communication conduit, pull boxes, relays and wiring to perform elevator
communication for all six elevators per RFI 3862 response.
RFI 3863-Wall Switch Timer. Deduct from Owner Contingency.
TKJV is proposing a Subcontractor Modification to Morton Electric, Inc.
in the Lump Sum amount of $1,817.00 for CR0994-PKG-RFIs 3861, 3862,
3863, 4046, 4145 and 4373 - Multiple RFI Electrical Revisions (CWA BP
S150-007). RFI 3863 confirmed the Wall Switch Timer Specification - Tork
A506HFIW. The modified scope of work consists of all material and labor
costs to provide five additional 6-hr. timer switches per RFI 3863
response.
RFI 4046-IDF Electrical Panel Grounding. Deduct from CMAR Contingency
TKJV is proposing a Subcontractor Modification to Morton Electric, Inc.
in the Lump Sum amount of $2,031.00 for CR0994-PKG-RFIs 3861, 3862,
3863, 4046, 4145 and 4373 - Multiple RFI Electrical Revisions (CWA BP
S150-007). RFI 4046 was issued to confirm if the ground from TG or TBB
to the Electrical Panels is required. The RFI direction was to connect
electrical panels with a #6 ground conductor to their respective IDF
rooms TGB and connect to ground bar inside the electrical panel. The
modified scope of work consists of all labor and material costs to
provide added ground wire per RFI 4046 response which was not included
in the subcontractor's base scope.
RFI 4145-Emergency Circuit Outlets in IDF Rooms. Deduct from Owner
Contingency.
TKJV is proposing a Subcontractor Modification to Morton Electric, Inc.
in the Lump Sum amount of $16,342.00 for CR0994-PKG-RFIs 3861, 3862,
3863, 4046, 4145 and 4373 - Multiple RFI Electrical Revisions (CWA BP
S150-007). RFI 4145 was issued to confirm the request to replace the
outlets serving the HP cabinets in the IDF Rooms. The modified scope of
work consists of all labor and material costs associated with changing
thirty-eight (38) L5-20A (120V) outlets to L6-30A (208V) in IDF Rooms.
RFI 4373. Deduct from CMAR Contingency.
TKJV is proposing a Subcontractor Modification to Morton Electric, Inc.
in the Lump Sum amount of $2,079.00 for CR0994-PKG-RFIs 3861, 3862,
3863, 4046, 4145 and 4373 - Multiple RFI Electrical Revisions (CWA BP
S150-007). The modified scope of work consists of all labor and material
costs associated with revising ground bars at all IDF Rooms from 12"x4"
CU ground bars to 24"x4" CU ground bar for all IDF Rooms.
The approval of these subcontract modifications to Morton Electric, Inc.
resolves all requests for costs and time associated with RFIs 3862, 3863,
4046, 4145 and 4373. This approval will also resolve all requests for cost and
time associated with RFI 3861 for GMP No. 9-S and closes CWA BP S150-007;
remaining RFI 3861 costs and time in GMP No. 9-S.1 (Low voltage scope) will
be resolved in forthcoming CR 0994.1.
Minutes of the Construction Committee Meeting, June 9, 2020
Page 21 of 38
TKJV has submitted documentation including the subcontractor's proposal to
support their request. An independent cost estimate is included.
By approving this request, the Owner does not waive its right to enforce the
contract requirements for other requests for cost or time.
The effect of this Subcontract Modification for this project is as follows:
TKJV to issue subcontract modification to Morton
Electric, Inc. in the lump sum amount of: $ 49,133.00
Deduct from Owner Contingency (RFI 3861): $ (1,367.00)
Deduct from CMAR Contingency (RFI 3862): $ (25,497.00)
Deduct from Owner Contingency (RFI 3863): $ (1,817.00)
Deduct from CMAR Contingency (RFI 4046): $ (2,031.00)
Deduct from Owner Contingency (RFI 4145): $ (16,342.00)
Deduct from CMAR Contingency (RFI 4373): $ (2,079.00)
Turner-Kiewit Joint Venture is committed to 20% MWBE and 4% LDB participation
for Construction Services. The subcontractor identified and committed to
participate on BP-S00150 (GMP No. 9-S) for this subcontract modification is
Morton Electric, Inc. (Non-MWBE/LDB/VBE). There is no small business
participation associated with this modification.
Ms. Sharman asked if this item has taken into account any potential scope
reductions. Mr. Corthell answered yes, that this item has been reviewed and
determined to be necessary at this time, as well as within any projected
reductions in scope.
Agenda Item Nos. 3-A, 3-B, 3-C, 3-D, 3-E, 3-F, 3-G, 3-H, 3-I, 3-J, 3-K, 3-L,
3-M, 3-N, 3-O, 3-P, 3-Q, 3-R, 3-S, 3-T, 3-U, 3-V, 3-W, 3-X, 3-Y, and 3-Z were
considered in one motion.
Upon motion of Mr. Patterson, second by Mr. Hunt, vote carried by roll-call
with all votes yea, to approve Turner-Kiewit Joint Venture to issue a
Subcontract Modification to Morton Electric, Inc. on BP-S00150, South Terminal
C, Phase 1 - Parking Facility - Phase 1 (GMP No. 9-S), for the total lump sum
amount of $49,133.00, with funding from Customer Facility Charges and General
Airport Revenue Bonds.
P. Subcontract Modification for BP-S00150 (GMP No. 9-S) with Morton Electric, Inc. for CR1041-PKG-RFI 4261 - PKG Elevator Shaft Works and RFI 4261.
Mr. Corthell presented the memorandum, requesting approval for Turner-Kiewit
Joint Venture (TKJV) to issue a Subcontract Modification on BP-S00150, South
Terminal C, Phase 1, Parking Facility - Phase 1 (GMP No. 9-S), at the Orlando
International Airport, in the total amount of $8,664.00 to Morton Electric,
Inc. for CR1041-PKG-RFI 4261 - PKG Elevator Shaft Works and RFI 4261. Bid
Package 26.0.0 "Electrical" was previously awarded within the GMP No. 9-S to
Morton Electric, Inc., CC No. 20171010.16.
TKJV is proposing a Subcontractor Modification to Morton Electric, Inc. in the
total Lump Sum amount of $8,664.00 for CR1041-PKG-RFI 4261 - PKG Elevator
Shaft Works and RFI 4261. The modified scope of work consists of material and
labor costs to relocate lighting in the elevator shaft in response to the
elevator inspector's request and to provide added lighting, switching and
circuitry to the Mechanical Chase Room per RFI 4261 response.
The approval of this subcontract modification to Morton Electric, Inc. resolves
all requests for costs and time associated with RFI 4261 and the Elevator
shaft works as presented in CR1041-PKG-RFI 4261 - PKG Elevator Shaft Works and
RFI 4261.
Minutes of the Construction Committee Meeting, June 9, 2020
Page 22 of 38
TKJV has submitted documentation including the subcontractor's proposal to
support their request. An independent cost estimate is included. By approving
this request, the Owner does not waive its right to enforce the contract
requirements for other requests for cost or time.
The effect of this Subcontract Modification for this project is as follows:
TKJV to issue subcontract modification to Morton
Electric, Inc. in the lump sum amount of: $ 8,664.00
Deduct from Owner Contingency: $ (1,595.00)
Deduct from Owner Contingency (RFI 4261): $ (7,069.00)
Turner-Kiewit Joint Venture is committed to 20% MWBE and 4% LDB participation
for Construction Services. The subcontractor identified and committed to
participate on BP-S00150 (GMP No. 9-S) for this subcontract modification is
Morton Electric, Inc. (Non-MWBE/LDB/VBE). There is no small business
participation associated with this modification.
Ms. Sharman asked if this item has taken into account any potential scope
reductions. Mr. Corthell answered yes, that this item has been reviewed and
determined to be necessary at this time, as well as within any projected
reductions in scope.
Agenda Item Nos. 3-A, 3-B, 3-C, 3-D, 3-E, 3-F, 3-G, 3-H, 3-I, 3-J, 3-K, 3-L,
3-M, 3-N, 3-O, 3-P, 3-Q, 3-R, 3-S, 3-T, 3-U, 3-V, 3-W, 3-X, 3-Y, and 3-Z were
considered in one motion.
Upon motion of Mr. Patterson, second by Mr. Hunt, vote carried by roll-call
with all votes yea, to approve Turner-Kiewit Joint Venture to issue a
Subcontract Modification to Morton Electric, Inc. on BP-S00150, South Terminal
C, Phase 1 - Parking Facility - Phase 1 (GMP No. 9-S), for the total lump sum
amount of $8,664.00, with funding from Customer Facility Charges and General
Airport Revenue Bonds.
Q. Subcontract Modification for BP-S00158 (GMP No. 17-S) with Gomez Construction Company for CR1011-17S-CPD-Bulletins 3 and 4-Check Point Delta Multiple Trade
Updates (excluding canopy scope). Mr. Corthell presented the memorandum,
requesting approval for Turner-Kiewit Joint Venture (TKJV) to issue a
Subcontract Modification on BP-S00158, South Terminal C, Phase 1, Checkpoint
Delta (GMP No. 17-S), at the Orlando International Airport, in the total amount
of $5,665.00 to Gomez Construction Company for CR1011-17S-CPD-Bulletins 3 and
4-Check Point Delta Multiple Trade Updates (excluding canopy scope). Bid
Package 1.0.0 "Checkpoint Delta General Contractor" was previously awarded
within GMP No. 17-S to Gomez Construction Co., CC 20190528.004
TKJV is proposing a subcontract modification to Gomez Construction Company in
the total lump sum amount of $5,665.00 for CR1011-17S-CPD-Bulletins 3 and 4-
Check Point Delta Multiple Trade Updates (excluding canopy scope). The modified
scope of work consists of all labor, material and equipment costs associated
with the addition of a grab bar, AED, plumbing fixtures and piping, and a
credit for reduction of the height of the CMU wall per CPD Bulletin 3. The
modified scope of work for CPD Bulletin 4 consists of all labor, material and
equipment costs associated with the addition of a fire extinguisher and
cabinet, added electrical panel and associated conduit and wires.
The approval of this subcontract modification to Gomez Construction Company
resolves all requests for cost and time associated with CPD Bulletins 3 and 4
(excluding canopy scope). Changes associated with the canopy design scope will
Minutes of the Construction Committee Meeting, June 9, 2020
Page 23 of 38
be addressed in forthcoming CR 1011.1, Low Voltage costs will be submitted
under forthcoming CR1011.2.
TKJV has submitted documentation including the subcontractor's proposal to
support their request. An independent cost estimate is included. By approving
this request, the Owner does not waive its right to enforce the contract
requirements for other requests for cost or time.
The effect of this Subcontract Modification for this project is as follows:
TKJV to issue subcontract modification to Gomez
Construction Co. in the lump sum amount of: $ 5,665.00
Deduct from Owner Contingency: $ (5,665.00)
Turner-Kiewit Joint Venture is committed to 20% MWBE and 4% LDB participation
for Construction Services. The subcontractor identified and committed to
participate on BP-S00158 (GMP No. 17-S) for this subcontract modification is
Gomez Construction Company (MWBE). There is small business participation of
77.3% LDB and a reduction of 41.6% MWBE associated with this modification.
Ms. Sharman asked if this item has taken into account any potential scope
reductions. Mr. Corthell answered yes, that this item has been reviewed and
determined to be necessary at this time, as well as within any projected
reductions in scope.
Agenda Item Nos. 3-A, 3-B, 3-C, 3-D, 3-E, 3-F, 3-G, 3-H, 3-I, 3-J, 3-K, 3-L,
3-M, 3-N, 3-O, 3-P, 3-Q, 3-R, 3-S, 3-T, 3-U, 3-V, 3-W, 3-X, 3-Y, and 3-Z were
considered in one motion.
Upon motion of Mr. Patterson, second by Mr. Hunt, vote carried by roll-call,
with all votes yea, to approve Turner-Kiewit Joint Venture to issue a
Subcontract Modification to Gomez Construction Company on BP-S00158, South
Terminal C, Phase 1, Checkpoint Delta (GMP No. 17-S), for the total lump sum
amount of $5,665.00, with funding from General Airport Revenue Bonds.
R. Subcontractor Modification for BP-S00163 (GMP No. 5-S.5) with The Middlesex Corporation for CR0509-5S.5-LSC-Bulletin 23-RFIs 2608 and 2397-Bridge
Structure Modifications and Precast Fascia Panel Removal (VE Item 27).
Mr. Corthell presented the memorandum, requesting approval for Turner-Kiewit
Joint Venture (TKJV) to issue a Subcontract Modification on BP-S00163, South
Terminal C, Phase 1 - Enplane/Deplane Bridge and Roadways (GMP No. 5-S.5), at
the Orlando International Airport, in the total amount of $516,583.00 to The
Middlesex Corporation for CR0509-5S.5-LSC-Bulletin 23-RFIs 2608 and 2397-
Bridge Structure Modifications and Precast Fascia Panel Removal (VE Item 27).
Bid Package 34.0.0 "Enplane/Deplane Bridge-Combined Piers and Piles" was
previously awarded within GMP No. 5-S.5 "Enplane/Deplane Bridge and Roadways
Balance of Work - FDOT" to The Middlesex Corporation, CC No. 20180605.007.
TKJV is proposing a subcontract modification to The Middlesex Corporation in
the total lump sum amount of $516,583.00 for CR0509-5S.5-LSC-Bulletin 23-RFIs
2608 and 2397-Bridge Structure Modifications and Precast Fascia Panel Removal
(VE Item 27). LSC Bulletin 23 includes revisions to canopy column details, new
bridge deck expansion joints, and new Class 5 finish details. Class 5 finish
is currently being discussed as a potential VE item; therefore, its impacts
are not included in this request. LSC RFI 2397 confirmed an FDOT Index 422,
42-inch height vertical shape traffic railing. LSC RFI 2608 confirmed concrete
pedestals only at grid line locations where Enplane/Deplane columns exist.
CR0286 VE Item No. 27 provided a credit to Owner Contingency in the deductive
lump sum amount of ($1,250,000.00) for the LSC delete Bridge Precast Fascia
Minutes of the Construction Committee Meeting, June 9, 2020
Page 24 of 38
and Coping VE. This amount was subject to a final reconciliation with the
subcontractor and final design incorporation via RFI, bulletin and subsequent
subcontractor pricing. The final Credit submitted by the subcontractor for VE
Item No. 27 was in the deductive lump sum amount of ($1,215,000.00). The
modified scope of work captured in this request consists of additional
material, labor and equipment costs to install PVC drainpipes in concrete,
labor only for installing expansion joint systems at edge of Enplane/Deplane
Bridge and LST structure per LSC Bulletin 23; labor, material and equipment
cost to provide the changes to concrete barrier walls per RFI 2397; a credit
for decreasing quantity of canopy concrete pedestals per RFI 2608; and a
$35,000.00 net add resulting from the difference between the estimated credit
provided in CR0286 precast concrete fascia panels on Bridge VE No. 27 CC No.
20190219.002N and the credit achieved per the final reconciliation with
subcontractor.
The approval of this subcontract modification to The Middlesex Corporation
resolves all requests for cost and time resulting from RFIs 2608 and 2397, the
precast fascia panel removal (VE item No. 27) and Landside Civil Bulletin 23
changes excluding Class 5 finish changes. The following are the CR associated
with LSC Bulletin 23 that have been or will be submitted: CR0509.1 was submitted
for the expansion joint material purchase CC No. 20191119-3-R; and CR0509.2
will be submitted for the Class 5 finish or the finish determined through
Value Engineering.
TKJV has submitted documentation including the subcontractor's proposal to
support this request. An independent cost estimate is included. By approving
this request, the Owner does not waive its right to enforce the contract
requirements for other requests for cost or time.
The effect of this Subcontractor Modification for this project is as follows:
TKJV to issue a subcontract modification to The
Middlesex Corporation in the lump sum amount of:
(LSC Bulletin 23 and RFI 2397) $ 888,872.00
TKJV to issue a subcontract modification to The
Middlesex Corporation in the lump sum amount of:
(RFI 2608) $ (407,289.00)
TKJV to issue a subcontract modification to The
Middlesex Corporation in the lump sum amount of:
(VE No. 27 Final credit reconciliation) $ 35,000.00
Deduct from P1 Owner Contingency: $ (407,178.00)
Deduct from P1X Owner Contingency: $ (109,405.00)
Due to the funding source of this GMP No. 5-S.5, Turner-Kiewit Joint Venture
proposed a 20% DBE participation goal for Bid Package 34.0.0 Enplane/Deplane
Bridge and Roadways Balance of Work - FDOT, in lieu of MWBE and LDB
participation goals. As such, Turner-Kiewit Joint Venture’s committed MWBE
and LDB Construction Services goals are not affected by this modification.
The subcontractor identified and committed to participate on BP-S00163 (GMP
No. 5-S.5) for this subcontract modification is The Middlesex Corporation
(Non-DBE). There is 19.2% DBE participation associated with this modification.
Ms. Sharman asked if this item has taken into account any potential scope
reductions. Mr. Corthell answered yes, that this item has been reviewed and
determined to be necessary at this time, as well as within any projected
reductions in scope.
Minutes of the Construction Committee Meeting, June 9, 2020
Page 25 of 38
Agenda Item Nos. 3-A, 3-B, 3-C, 3-D, 3-E, 3-F, 3-G, 3-H, 3-I, 3-J, 3-K, 3-L,
3-M, 3-N, 3-O, 3-P, 3-Q, 3-R, 3-S, 3-T, 3-U, 3-V, 3-W, 3-X, 3-Y, and 3-Z were
considered in one motion.
Upon motion of Mr. Patterson, second by Mr. Hunt, vote carried by roll-call,
with all votes yea, to approve Turner-Kiewit Joint Venture to issue a
Subcontractor Modification to The Middlesex Corporation on BP-S00163, South
Terminal C, Phase 1 - Enplane/Deplane Bridge and Roadways (GMP No. 5-S.5), for
the total lump sum amount of $516,583.00, with funding from Passenger Facility
Charges.
S. Budget Reallocation for BP-S00163 (GMP No. 5-S.5) for CR01106-5S.5-LSC-Budget Reallocations-Enplane/Deplane Bridge and Roadways Balance of Work.
Mr. Corthell presented the memorandum, requesting approval for Turner-Kiewit
Joint Venture (TKJV) to issue a Budget Reallocation on BP-S00163, South
Terminal C, Phase 1 - Enplane/Deplane Bridge and Roadways (GMP No. 5-S.5), at
the Orlando International Airport, in the total amount of $620,607.00 for
CR01106-5S.5-LSC-Budget Reallocations-Enplane/Deplane Bridge and Roadways
Balance of Work. Bid package BP-S00163 was previously awarded to TKJV within
GMP No. 5-S.5, CC No. 20180605.007
TKJV is proposing to reallocate budget from:
GMP No. 5-S.5 PI CMAR Contingency to P1 Owner Contingency in the lump
sum amount of $363,079.
GMP No. 5-S.5 P1X CMAR Contingency to P1X Owner Contingency in the lump
sum amount of $257,528.
This request will resolve all cost and time for CR01106-5S.5-LSC-Budget
Reallocations-Enplane/Deplane Bridge and Roadways Balance of Work. TKJV has
submitted documentation to support their request.
The effect of this Budget Reallocation for this project is as follows:
GMP No. 5-S.5 Current P1 CMAR Contingency Balance: $ 1,234,113.00
Deduct from P1 CMAR Contingency: $ (363,079.00)
Add to P1 Owner Contingency: $ 363,079.00
Remaining P1 CMAR Contingency Balance: $ 871,034.00
GMP No. 5-S.5 Current P1X CMAR Contingency Balance: $ 515,057.00
Deduct from P1X CMAR Contingency: $ (257,528.00)
Add to P1X Owner Contingency: $ 257,528.00
Remaining P1X CMAR Contingency Balance: $ 257,529.00
The Office of Small Business Development has determined that the proposed
budget reallocation does not have any impact on the small business
participation. [Subsequent to the meeting, the Office of Small Business
Development submitted an OSBD Participation Memorandum as Information Item No.
7-F on the June 23, 2020, Construction Committee Agenda.]
Ms. Sharman asked if this item has taken into account any potential scope
reductions. Mr. Corthell answered yes, that this item has been reviewed and
determined to be necessary at this time, as well as within any projected
reductions in scope.
Agenda Item Nos. 3-A, 3-B, 3-C, 3-D, 3-E, 3-F, 3-G, 3-H, 3-I, 3-J, 3-K, 3-L,
3-M, 3-N, 3-O, 3-P, 3-Q, 3-R, 3-S, 3-T, 3-U, 3-V, 3-W, 3-X, 3-Y, and 3-Z were
considered in one motion.
Minutes of the Construction Committee Meeting, June 9, 2020
Page 26 of 38
Upon motion of Mr. Patterson, second by Mr. Hunt, vote carried by roll-call
with all votes yea, to approve Turner-Kiewit Joint Venture to issue a Budget
Reallocation on BP-S00163, South Terminal C, Phase 1 - Enplane/Deplane Bridge
and Roadways (GMP No. 5-S.5), for the total budget reallocation lump sum amount
of $620,607.00, with funding from Passenger Facility Charges.
T. Subcontractor Modification for BP-S00168 (GMP No. 6-S.4) with M.C. Dean, Inc. for CR0503.6-6S4-ASC Bulletin 037 - Low Voltage. Mr. Corthell presented the
memorandum, requesting approval for Hensel Phelps Construction (HPC) to issue
a Subcontract Modification on BP-S00168, South Terminal C, Phase 1 - Interior
Finishes and Specialties (GMP No. 6-S.4), at the Orlando International Airport,
in the total amount of $6,135.00 to M.C. Dean, Inc., for CR0503.6-6S4-ASC
Bulletin 037 - Low Voltage. Bid Package for BP-S00168 27.01 "Airside Concourse
Low Voltage Systems" has been previously awarded within GMP No. 6-S.4 to M.C.
Dean, Inc., CC No. 20181002.010.
HPC is requesting to issue a Subcontractor Modification to M.C. Dean, Inc. in
the total Lump Sum amount of $6,135.00 for CR0503.6-6S4-ASC Bulletin 037 - Low
Voltage. The modified scope of work consists of the additional labor, material
and equipment costs associated with the added conduit and fire alarm systems
for the added Fire Smoke Dampers (FSD). HPC will also submit Time Impact
Analysis (TIA 088) requesting additional time associated with this scope of
work ASC Bulletin 037.
The approval of this Subcontract Modification to M.C. Dean, Inc. resolves all
requests for costs associated with the ASC Bulletin 037 scope of work in GMP
No. 6-S.4, with the exception of costs for DSI ASC-003 and ASC Bulletin 036.
Costs associated with DSI ASC-003 and ASC Bulletin 036 are excluded due
to document inconsistencies and further design changes that are being
resolved and costs for these will be submitted in a future CR.
Cost impacts of ASC Bulletin 037 Mechanical Only scope of work in GMP
No. 6-S.1 were approved, CC No. 20200324.02B (CR0503.2-6S.1).
Cost impacts of ASC B037 Mechanical Only scope of work in GMP No. 6-S.6
were approved via CC No. 20200324.200 (CR0503.3-6S.6).
Cost impacts of ASC B037 to GMP No. 6-S.1 for the Non-Mechanical Trades
will be submitted in CR0503.4-6S.1 for a future CCM approval.
Cost impacts of ASC B037 to GMP No. 6-S.2 for the Non-Electrical Trades
was approved via CC No. 20200526.03F (CR0503.5-6S.2).
Cost impacts of ASC B037 to GMP No. 6-S.6 for the Non-Mechanical scope
will be submitted in future CRs.
There are no cost impacts of ASC B037 to GMP No. 6-S.2 for the Electrical
scope of work.
There are no cost impacts of ASC B037 to GMP Nos. 6-S, 6-S.3, and 6-S.5.
Costs for patching of Fireproofing and Testing & Inspection, if any,
will be submitted in a future CR.
The OAR will evaluate TIA-088 and any additional time recommended to be
granted will be submitted at a future CCM.
Minutes of the Construction Committee Meeting, June 9, 2020
Page 27 of 38
HPC has submitted documentation including the subcontractor's proposal to
support this request. An independent cost estimate is included. By approving
this request, the Owner does not waive its right to enforce the contract
requirements for other requests for cost or time.
The effect of this Subcontractor Modification for this project is as follows:
HPC to issue a subcontract modification to M.C. Dean, Inc.
in the lump sum amount of: $ 6,135.00
Deduct from P1 Owner Contingency $ (6,135.00)
Hensel Phelps Construction is committed to 20% MWBE and 4% LDB participation
for Construction Services. The subcontractor identified and committed to
participate on BP-S00168 (GMP No. 6-S.4) for this subcontract modification is
M.C. Dean, Inc. (Non-MWBE/LDB/VBE). There is 24% MWBE participation associated
with this modification.
Ms. Sharman asked if this item has taken into account any potential scope
reductions. Mr. Corthell answered yes, that this item has been reviewed and
determined to be necessary at this time, as well as within any projected
reductions in scope.
Agenda Item Nos. 3-A, 3-B, 3-C, 3-D, 3-E, 3-F, 3-G, 3-H, 3-I, 3-J, 3-K, 3-L,
3-M, 3-N, 3-O, 3-P, 3-Q, 3-R, 3-S, 3-T, 3-U, 3-V, 3-W, 3-X, 3-Y, and 3-Z were
considered in one motion.
Upon motion of Mr. Patterson, second by Mr. Hunt, vote carried by roll-call,
with all votes yea, to approve Hensel Phelps Construction to issue a
Subcontractor Modification to M.C. Dean, Inc., on BP-S00168, South Terminal
C, Phase 1 - Interior Finishes and Specialties (GMP No. 6-S.4), for the total
lump sum amount of $6,135.00, with funding from Passenger Facility Charges and
General Airport Revenue Bonds.
U. Subcontractor Modification for BP-S00168 (GMP No. 6-S.4) with M.C. Dean, Inc. for CR0506-6S4-Low Voltage Experiential Medial Environment (EME) Base Scope.
Mr. Corthell presented the memorandum, requesting approval for Hensel Phelps
Construction (HPC) to issue a Subcontract Modification on BP-S00168, South
Terminal C, Phase 1 - Interior Finishes and Specialties (GMP No. 6-S.4), at
the Orlando International Airport, in the total amount of $76,256.00 to M.C.
Dean, Inc., for CR0506-6S4-Low Voltage Experiential Medial Environment (EME)
Base Scope. Bid Package for BP-S00168 27.01 "Airside Concourse Low Voltage
Systems" has been previously awarded within GMP No. 6-S.4 to M.C. Dean, Inc.,
CC No. 20181002.010.
HPC is requesting to issue a Subcontractor Modification to M.C. Dean, Inc. in
the total Lump Sum amount of $76,256.00 for CR0506-6S4-Low Voltage Experiential
Medial Environment (EME) Base Scope. During the low voltage bid process, the
EME scope was undergoing design revisions. The EME scope was excluded from the
Low Voltage bid package. The modified scope of work consists of the material,
labor and equipment costs associated with the Low Voltage conduit and fittings
for the structured cabling system to the two EME features in Phase 1: Windows
on Orlando (EME-A01, EME-A02 and EME-A03) and the Moment Vault (EME-A04, EME-
A05 and EME-A06), for the base scope of work through ASC Bulletin 005 Contract
Documents.
The approval of this Subcontract Modification to M.C. Dean, Inc. resolves all
requests for cost and time associated with the Low Voltage EME base scope of
work through ASC Bulletin 5. Costs associated with changes to the EME scope
Minutes of the Construction Committee Meeting, June 9, 2020
Page 28 of 38
in ASC Bulletin 21 were approved, CC No. 20190716.02M; and costs for changes
to the EME scope in ASC Bulletin 31 were approved, CC No. 20200310.03W.
HPC has submitted documentation including the subcontractor's proposal to
support this request. An independent cost estimate is included. By approving
this request, the Owner does not waive its right to enforce the contract
requirements for other requests for cost or time.
The effect of this Subcontractor Modification for this project is as follows:
HPC to issue a subcontract modification to M.C. Dean, Inc.
in the lump sum amount of: $ 76,256.00
Deduct from P1 CMAR Contingency: $ (76,256.00)
Hensel Phelps Construction is committed to 20% MWBE and 4% LDB participation
for Construction Services. The subcontractor identified and committed to
participate on BP-S00168 (GMP No. 6-S.4) for this subcontract modification is
M.C. Dean, Inc. (Non-MWBE/LDB/VBE). There is 11.7% MWBE participation
associated with this modification.
Ms. Sharman asked if this item has taken into account any potential scope
reductions. Mr. Corthell answered yes, that this item has been reviewed and
determined to be necessary at this time, as well as within any projected
reductions in scope.
Agenda Item Nos. 3-A, 3-B, 3-C, 3-D, 3-E, 3-F, 3-G, 3-H, 3-I, 3-J, 3-K, 3-L,
3-M, 3-N, 3-O, 3-P, 3-Q, 3-R, 3-S, 3-T, 3-U, 3-V, 3-W, 3-X, 3-Y, and 3-Z were
considered in one motion.
Upon motion of Mr. Patterson, second by Mr. Hunt, vote carried by roll-call,
with all votes yea, to approve Hensel Phelps Construction to issue a
Subcontractor Modification to M.C. Dean, Inc., on BP-S00168, South Terminal
C, Phase 1 - Interior Finishes and Specialties (GMP No. 6-S.4), for the total
lump sum amount of $76,256.00, with funding from General Airport Revenue Bonds.
V. Subcontractor Modification for BP-S00170 (GMP No. 5-S.6) with Kiewit
Infrastructure South Co. for CR0697-LSC-RFI 3008-Added Conduits at South
Switchyard. Mr. Corthell presented the memorandum, requesting approval for
Turner-Kiewit Joint Venture (TKJV) to issue a Subcontract Modification on BP-
S00170, South Terminal C, Phase 1 - Underground Electrical Distribution (GMP
No. 5-S.6), at the Orlando International Airport, in the total amount of
$230,837.00 to Kiewit Infrastructure South Co., for CR0697-LSC-RFI 3008-Added
Conduits at South Switchyard. Bid Package 26.0.0 "North Section" was
previously awarded within GMP No. 5-S.6 to Kiewit Infrastructure South Co.,
CC No. 20180605.08.
TKJV is proposing a subcontract modification to Kiewit Infrastructure South
Co. in the total lump sum amount of $230,837.00 for CR0697-LSC-RFI 3008-Added
Conduits at South Switchyard. The duct bank installation was required to start
prior to the design being complete in order for the electrical contractor to
be out of this area. The design team had multiple meetings with the OAR and
OUC to determine how to route the conduit to support the power design by OUC.
RFI 3008 requested details for the conduit connections to Manholes LP-40 and
LP-41. The RFI response includes revisions to Plan Sheets CE2.00.91 and
CE7.00.22 that show the additional conduit interconnecting Manholes LP-38, LP-
39, LP-40, and LP-41, and the south switchyard pads. The revised drawings
include additional clarifications requested by OUC to support new circuiting
requirements and changes due to the location of the duct bank construction.
The modified scope of work consists of all labor, material and equipment costs
Minutes of the Construction Committee Meeting, June 9, 2020
Page 29 of 38
associated with the addition of 2-inch, 4-inch, and 6-inch conduits per RFI
3008 response.
The approval of this subcontract modification to Kiewit Infrastructure South
Co. resolves all requests for cost and time for RFI 3008.
TKJV has submitted documentation including the subcontractor's proposal to
support this request. An independent cost estimate is included. By approving
this request, the Owner does not waive its right to enforce the contract
requirements for other requests for cost or time.
The effect of this Subcontractor Modification for this project is as follows:
TKJV to issue a subcontract modification to Kiewit
Infrastructure South Co. in the lump sum amount of: $ 230,837.00
Deduct from P1 Owner Contingency: $(230,837.00)
Turner-Kiewit Joint Venture is committed to 20% MWBE and 4% LDB participation
for Construction Services. The subcontractor identified and committed to
participate on BP-S00170 (GMP No. 5-S.6) for this subcontract modification is
Kiewit Infrastructure South Co. (Non-MWBE/LDB/VBE). There is 0.6% LDB
participation associated with this modification.
Ms. Sharman asked if this item has taken into account any potential scope
reductions. Mr. Corthell answered yes, that this item has been reviewed and
determined to be necessary at this time, as well as within any projected
reductions in scope.
Agenda Item Nos. 3-A, 3-B, 3-C, 3-D, 3-E, 3-F, 3-G, 3-H, 3-I, 3-J, 3-K, 3-L,
3-M, 3-N, 3-O, 3-P, 3-Q, 3-R, 3-S, 3-T, 3-U, 3-V, 3-W, 3-X, 3-Y, and 3-Z were
considered in one motion.
Upon motion of Mr. Patterson, second by Mr. Hunt, vote carried by roll-call,
with all votes yea, to approve Turner-Kiewit Joint Venture to issue a
Subcontractor Modification to Kiewit Infrastructure South Co., on BP-S00170,
South Terminal C, Phase 1 - Underground Electrical Distribution (GMP
No. 5-S.6), for the total lump sum amount of $230,837.00, with funding from
General Airport Revenue Bonds.
W. Subcontractor Modification for BP-S00170 (GMP No. 5-S.6) with Kiewit
Infrastructure South Co. for CR0560.1-LSC-Bulletin 24 and RFI 2731-Revisions
to PPD and Access Road. Mr. Corthell presented the memorandum, requesting
approval for Turner-Kiewit Joint Venture (TKJV) to issue a Subcontract
Modification on BP-S00170, South Terminal C, Phase 1 - Underground Electrical
Distribution (GMP No. 5-S.6), at the Orlando International Airport, in the
total amount of $459,001.00 to Kiewit Infrastructure South Co., for CR0560.1-
LSC-Bulletin 24 and RFI 2731-Revisions to PPD and Access Road. Bid Package
26.0.0 "North Section" was previously awarded within GMP No. 5-S.6 to Kiewit
Infrastructure South Co., CC No. 20180605.08.
TKJV is proposing a subcontract modification to Kiewit Infrastructure South
Co. in the total lump sum amount of $459,001.00 for CR0560.1-LSC-Bulletin 24
and RFI 2731-Revisions to Primary Power Distribution (PPD) and Access Road.
LSC Bulletin 24 adds a new pull box and duct bank run for the future GSE
facility. The Bulletin also changes the roadway profile of the OUC access road
adjacent to future Heintzelman Blvd. as shown on C.3.3.03, Typical Section on
C9.0.5. RFI 2731 confirms that it is acceptable for Kiewit Infrastructure
South Co. to utilize a spare communications box in lieu of pouring a new pull
box. The modified scope of work consists of labor, material and equipment
Minutes of the Construction Committee Meeting, June 9, 2020
Page 30 of 38
costs associated with the additional civil and electrical scope of work
resulting from LSC Bulletin 24 revisions and RFI 2731 response. The following
items are being credited in this request: A portion of roadway work at STA 400
and 500 that was completed under GMP No. 18-S (costs previously submitted in
GMP No. 5-S.6 Amendment No. 2); Deleted Alt No. l scope (costs previously
submitted in GMP No. 5-S.6 Amendment No. 2); and, Two extra PME pads at the
North Switchyard that were priced but not installed (costs previously submitted
in GMP No. 5-S.6 Amendment No. 2).
The approval of this subcontract modification to Kiewit Infrastructure South
Co. resolves all requests for cost and time for RFI 2731 and LSC Bulletin 24
in GMP No. 5-S.6. Remaining time and costs associated with LSC Bulletin 24
have been submitted in CR0560 (GMP No. 5-S.2).
TKJV has submitted documentation including the subcontractor's proposal to
support this request. An independent cost estimate is included. By approving
this request, the Owner does not waive its right to enforce the contract
requirements for other requests for cost or time.
The effect of this Subcontractor Modification for this project is as follows:
TKJV to issue a subcontract modification to Kiewit
Infrastructure South Co. in the lump sum amount of: $ 459,001.00
Deduct from P1X Owner Contingency: $(459,001.00)
Turner-Kiewit Joint Venture is committed to 20% MWBE and 4% LDB participation
for Construction Services. The subcontractor identified and committed to
participate on BP-S00170 (GMP No. 5-S.6) for this subcontract modification is
Kiewit Infrastructure South Co. (Non-MWBE/LDB/VBE). There is 11.2% reduction
in MWBE participation and 7.8% LDB participation associated with this
modification.
Ms. Sharman asked if this item has taken into account any potential scope
reductions. Mr. Corthell answered yes, that this item has been reviewed and
determined to be necessary at this time, as well as within any projected
reductions in scope.
Agenda Item Nos. 3-A, 3-B, 3-C, 3-D, 3-E, 3-F, 3-G, 3-H, 3-I, 3-J, 3-K, 3-L,
3-M, 3-N, 3-O, 3-P, 3-Q, 3-R, 3-S, 3-T, 3-U, 3-V, 3-W, 3-X, 3-Y, and 3-Z were
considered in one motion.
Upon motion of Mr. Patterson, second by Mr. Hunt, vote carried by roll-call
with all votes yea, to approve Turner-Kiewit Joint Venture to issue a
Subcontractor Modification to Kiewit Infrastructure South Co., on BP-S00170,
South Terminal C, Phase 1 - Underground Electrical Distribution (GMP
No. 5-S.6), for the total lump sum amount of $459,001.00, with funding from
General Airport Revenue Bonds.
X. Subcontractor Modification for BP-S00173 (GMP No. 7-S.3) with Kirlin Florida, LLC for CR0258.4-LST-Bulletin 12-HVAC and Plumbing. Mr. Corthell presented
the memorandum, requesting approval for Turner-Kiewit Joint Venture (TKJV) to
issue a Subcontract Modification on BP-S00173, South Terminal C, Phase 1,
Landside Terminal, MEP Systems - FDOT (GMP No. 7-S.3), at the Orlando
International Airport, in the total deductive amount of ($36,103.00) to Kirlin
Florida, LLC for CR0258.4-LST-Bulletin 12-HVAC and Plumbing. Bid Package BP
23.0.0 "Plumbing and HVAC" was previously awarded via CR0239 to Kirlin Florida,
LLC, CC No. 20190205.02FI
Minutes of the Construction Committee Meeting, June 9, 2020
Page 31 of 38
TKJV is proposing a subcontract modification to Kirlin Florida, LLC in the
total deductive lump sum amount of ($36,103.00) for CR0258.4-7S.3-LST-Bulletin
12-HVAC and Plumbing. The modified scope of work consists of all additional
HVAC and plumbing work resulting from LST Bulletin 12 due to necessary
rerouting and coordination of MEP systems to accommodate the Baggage Handling
System (BHS) design, excluding equipment previously covered in CR 258.3.
The approval of this subcontract modification to Kirlin Florida, LLC resolves
all requests for cost and time associated with the HVAC and Plumbing scope,
excluding equipment covered in CR 0258.3, in GMP No. 7-S.3. The following is
the list of all remaining CRs associated with LST Bulletin 12 that have been
or will be submitted:
GMP No. 7-S-CR0258-Structural Steel and Concrete (Approved; CC No.
20190219.02C)
GMP No. 7-S.1-CR0381-Low Voltage Only (Approved; CC No. 20191008.02B)
GMP No. 7-S.1-CR0381.1-Doors, Frames, Hardware, Interior Glazing and
Drywall (Submitted)
GMP No. 7-S.2 included in the subcontracts.
GMP No. 7-S.3-CR0258.3-Kirlin Equipment Only (Approved; CC No.
20190806.03J)
TKJV has submitted documentation including the subcontractor's proposal to
support their request. An independent cost estimate is included. By approving
this request, the Owner does not waive its right to enforce the contract
requirements for other requests for cost or time.
The effect of this Subcontractor Modification for this project is as follows:
TKJV to issue a subcontract modification to Kirlin
Florida, LLC in the deductive lump sum amount of: $ (36,103.00)
Add to P1 Owner Contingency: $ 36,103.00
Due to the funding source of this GMP No. 7-S.3, Turner-Kiewit Joint Venture
proposed a 10% DBE participation goal for Construction Services, in lieu of
MWBE and LDB participation goals. As such, Turner-Kiewit Joint Venture’s
committed MWBE and LDB Construction Services goals are not affected by this
modification. The subcontractor identified and committed to participate on
BP-S00173 (GMP No. 7-S.3) for this subcontract modification is Kirlin Florida,
LLC (Non-MWBE/LDB/VBE). This modification results in an addition to Kirlin
Florida, LLC's DBE subcontractor, Freedom Insulation, Inc., in the amount of
$40,735.00.
Ms. Sharman asked if this item has taken into account any potential scope
reductions. Mr. Corthell answered yes, that this item has been reviewed and
determined to be necessary at this time, as well as within any projected
reductions in scope.
Agenda Item Nos. 3-A, 3-B, 3-C, 3-D, 3-E, 3-F, 3-G, 3-H, 3-I, 3-J, 3-K, 3-L,
3-M, 3-N, 3-O, 3-P, 3-Q, 3-R, 3-S, 3-T, 3-U, 3-V, 3-W, 3-X, 3-Y, and 3-Z were
considered in one motion.
Upon motion of Mr. Patterson, second by Mr. Hunt, vote carried by roll-call,
with all votes yea, to approve Turner-Kiewit Joint Venture to issue a
Subcontractor Modification to Kirlin Florida, LLC on BP-S00173, South Terminal
C, Phase 1, Landside Terminal, MEP Systems - FDOT (GMP No. 7-S.3), for the
total deductive lump sum amount of ($36,103.00), with funding credited to
Passenger Facility Charges.
Minutes of the Construction Committee Meeting, June 9, 2020
Page 32 of 38
Y. Subcontractor Modification for BP-S00173 (GMP No. 7-S.3) with Kirlin Florida, LLC for CR0791-LST-RFI 2309 Grease Interceptor Removal. Mr. Corthell presented
the memorandum, requesting approval for Turner-Kiewit Joint Venture (TKJV) to
issue a Subcontract Modification on BP-S00173, South Terminal C, Phase 1,
Landside Terminal, MEP Systems - FDOT (GMP No. 7-S.3), at the Orlando
International Airport, in the total deductive amount of ($82,589.00) to Kirlin
Florida, LLC for CR0791-LST-RFI 2309 Grease Interceptor Removal. Bid Package
BP 23.0.0 "Plumbing and HVAC" was previously awarded via CR0239 to Kirlin
Florida, LLC, CC No. 20190205.02H
TKJV is proposing a subcontract modification to Kirlin Florida, LLC in the
total deductive lump sum amount of ($82,589.00) for CR0791-LST-RFI 2309 Grease
Interceptor Removal. The modified scope of work consists of credits associated
with the removal of two grease traps, underground vents and all underground
grease waste piping, per RFI 2309.
The approval of this subcontract modification to Kirlin Florida, LLC resolves
all requests for cost and time associated with RFI 2309 in GMP No. 7-S.3.
There are no cost impacts to GMP Nos. 7-S, 7-S.1, 7-S.2 and 7-S.4.
TKJV has submitted documentation including the subcontractor's proposal to
support their request. An independent cost estimate is included. By approving
this request, the Owner does not waive its right to enforce the contract
requirements for other requests for cost or time.
The effect of this Subcontractor Modification for this project is as follows:
TKJV to issue a subcontract modification to Kirlin
Florida, LLC in the deductive lump sum amount of: $ (82,589.00)
Add to P1 Owner Contingency: $ 82,589.00
Due to the funding source of this GMP No. 7-S.3, Turner-Kiewit Joint Venture
proposed a 10% DBE participation goal for Construction Services, in lieu of
MWBE and LDB participation goals. As such, Turner-Kiewit Joint Venture’s
committed MWBE and LDB Construction Services goals are not affected by this
modification. The subcontractor identified and committed to participate on
BP-S00173 (GMP No. 7-S.3) for this subcontract modification is Kirlin Florida,
LLC (Non-MWBE/LDB/VBE). There is no small business participation associated
with this modification.
Ms. Sharman asked if this item has taken into account any potential scope
reductions. Mr. Corthell answered yes, that this item has been reviewed and
determined to be necessary at this time, as well as within any projected
reductions in scope.
Agenda Item Nos. 3-A, 3-B, 3-C, 3-D, 3-E, 3-F, 3-G, 3-H, 3-I, 3-J, 3-K, 3-L,
3-M, 3-N, 3-O, 3-P, 3-Q, 3-R, 3-S, 3-T, 3-U, 3-V, 3-W, 3-X, 3-Y, and 3-Z were
considered in one motion.
Upon motion of Mr. Patterson, second by Mr. Hunt, vote carried by roll-call,
with all votes yea, to approve Turner-Kiewit Joint Venture to issue a
Subcontractor Modification to Kirlin Florida, LLC on BP-S00173, South Terminal
C, Phase 1, Landside Terminal, MEP Systems - FDOT (GMP No. 7-S.3), for the
total deductive lump sum amount of ($82,589.00), with funding credited to
Passenger Facility Charges and General Airport Revenue Bonds.
Minutes of the Construction Committee Meeting, June 9, 2020
Page 33 of 38
Z. Subcontractor Award for BP-S00181 (GMP No. 8-S.1) with VSC Fire & Security, Inc. for CR0946-8S.1-GTF-Early Release Fire Suppression Award. Mr. Corthell
presented the memorandum, requesting approval for Turner-Kiewit Joint Venture
(TKJV) to issue a Subcontract Award on BP-S00181, South Terminal C, Phase 1 -
Ground Transportation Facility (GMP No. 8-S.1), at the Orlando International
Airport, in the total amount of $93,600.00 to VSC Fire & Security, Inc. for
CR0946-8S.1-GTF-Early Release Fire Suppression Award. GMP No. 8-S.l was
previously awarded to Turner-Kiewit Joint Venture via Addendum No. 26, CC No.
20191217.010.
TKJV is proposing a directly negotiated Subcontract Award to VSC Fire &
Security, Inc. in the total lump sum amount of $93,600.00 for the Ground
Transportation Facility Early Release Fire Suppression award. Bid package
21.0.0 for the GTF Fire Suppression scope was first bid on September 24, 2019.
Two bids were received. The low bidder was non-responsive for failure to
include a bid bond and failure to comply with the small business requirements.
The budget was re-evaluated and the bid package was rebid on January 9, 2020.
Two bids were received and both bidders were more than 100% over the budget.
Both bidders were provided another opportunity to submit pricing. VSC Fire &
Security, Inc. was the lowest responsive bidder and was recommended for award
in April 2020. Before the award was approved, the Aviation Authority suspended
a portion of the GTF, which requires a re-design of the existing space. TKJV
recommends this early release award for work that is required and a change
order will be submitted for the rest of the fire suppression scope once the
final GTF design is known. This early release award includes submittals, shop
drawings and BIM coordination for the entirety of the fire suppression scope
of work, and material and installation of sleeves and fittings necessary to
support the ongoing cast-in-place concrete work.
The approval of this subcontract award to VSC Fire & Security, Inc. resolves
all requests for costs and time associated with CR0946-8S.1 Ground
Transportation Facility (GTF) Early Release Fire Suppression scope of work.
This is a result of the reduction in scope of the GTF. It is for the "knuckle”
area only.
TKJV has submitted documentation including the subcontractor's proposal to
support their request, an independent cost estimate is included. By approving
this request, the Owner does not waive its right to enforce the contract
requirements for other requests for cost or time.
The effect of this Subcontractor Award for this project is as follows:
TKJV to issue a subcontract award to VSC Fire &
Security, Inc. in the lump sum amount of: $ 93,600.00
Current GMP Line Item 38 value: $ 636,000.00
Deduct from GMP line item: $ (93,600.00)
Remaining GMP Line Item 38 value: $ 542,400.00
Turner-Kiewit Joint Venture is committed to 20% MWBE and 4% LDB participation
for Construction Services. The subcontractor identified and committed to
participate on BP-S00181 (GMP No. 8-S.1) for this subcontract award is VSC
Fire & Security, Inc. (Non-MWBE/LDB/VBE). There is 22.5% MWBE participation
associated with this award.
Ms. Sharman asked if this item has taken into account any potential scope
reductions. Mr. Corthell answered yes, that this item has been reviewed and
determined to be necessary at this time, as well as within any projected
reductions in scope.
Minutes of the Construction Committee Meeting, June 9, 2020
Page 34 of 38
Agenda Item Nos. 3-A, 3-B, 3-C, 3-D, 3-E, 3-F, 3-G, 3-H, 3-I, 3-J, 3-K, 3-L,
3-M, 3-N, 3-O, 3-P, 3-Q, 3-R, 3-S, 3-T, 3-U, 3-V, 3-W, 3-X, 3-Y, and 3-Z were
considered in one motion.
Upon motion of Mr. Patterson, second by Mr. Hunt, vote carried by roll-call,
with all votes yea, to approve Turner-Kiewit Joint Venture to issue a
Subcontractor Award to VSC Fire & Security, Inc. on BP-S00181, South Terminal
C, Phase 1 - Ground Transportation Facility (GMP No. 8-S.1), for the total
lump sum amount of $93,600.00, with funding from Customer Facility Charges and
General Airport Revenue Bonds.
SOUTH TERMINAL C
REQUEST FOR APPROVAL OF AN ADDENDUM TO THE ARCHITECT OF RECORD SERVICES FOR THE
SOUTH TERMINAL C, PHASE 1 AGREEMENT WITH HNTB CORPORATION FOR DESIGN SERVICES FOR
W-S00110, SOUTH TERMINAL C, PHASE 1 - ARCHITECT OF RECORD SERVICES, AT THE ORLANDO
INTERNATIONAL AIRPORT.
4. [A handout was presented, which includes a revised Memorandum and Supporting
Documentation.] Mr. Ruohomaki presented the memorandum, dated June 9, 2020, along
with a proposal from HNTB Corporation, dated June 3, 2020, to provide design services related to the deferred elements of the Airside Concourse, Ground Transportation
Facility, Landside Civil/Site Logistics, Airfield Civil, Airfield Fuel, BHS, GSE and
related STC and RAC elements.
Services include immediately initiating early design related assistance to the
Aviation Authority, OAR, Construction Managers, Vanderlande (DBOM Contractor), and
Burns Engineering, while the construction scopes of the deferred projects are further
refined. An additional design proposal will be submitted at a later date for the
required contract document changes associated with each deferred project for
consideration by Construction Committee and the Aviation Authority Board.
If approved, these services would be effective June 9, 2020.
The Office of Small Business Development has reviewed the qualifications of the
subject contract's MWBE/LDB/VBE specifications and determined that HNTB Corporation
has not identified any small business participation at this time. [Subsequent to
the meeting, the Office of Small Business Development submitted an OSBD Participation
Memorandum as Information Item No. 7-G on the June 23, 2020, Construction Committee
Agenda.]
Chairman Thornton asked if the fees associated with this request were included in
the post-reduction budget. Mr. Ruohomaki answered yes.
Ms. Sharman stated that HNTB Corporation was already awarded lump sum fees on the
major design and asked if the not-to-exceed fees were for subcontractors or specialty
design. Chairman Thornton responded that this is to modify the design to remove the
Phase 1 Expansion scope of work. Mr. Ruohomaki added that the original design was
done and this is only for the mission critical portions of the redesign.
Ms. Sharman asked if this should be presented to the Board. Chairman Thornton stated
that the Aviation Authority Board gave the directive for the reductions, and in
order to accomplish the reductions within the required timeframe, this work needs
to proceed without delay. Legal Counsel added that it can be referenced in the next
associated Board Item, but that it is not necessary to get additional authorization
for this request.
Mr. Hunt asked if the funding had been verified. Ms. Sharman replied that this item
is subject to the Construction Finance Oversight Committee (CFOC).
Minutes of the Construction Committee Meeting, June 9, 2020
Page 35 of 38
Upon motion of Mr. Patterson, second by Mr. Hunt, vote carried by roll-call, with
all votes yea, to approve an Addendum to the Architect of Record Services for the
South Terminal C, Phase 1 Agreement with HNTB Corporation for Design Services for
W-S00110 South Terminal C, Phase 1 - Architect of Record Services (and Major Subs),
for a total not-to-exceed fee amount of $249,900.00, with funding from General
Airport Revenue Bonds; subject to the CFOC. [Subsequent to the Construction Committee
meeting, the CFOC consensed the funding at the meeting held on July 7, 2020, as
outlined above.]
REQUEST FOR APPROVAL OF AN ADDENDUM TO THE PROGRAM AND PROJECT MANAGEMENT SERVICES
FOR THE SOUTH TERMINAL C, PHASE 1 AGREEMENT WITH COST MANAGEMENT, INC., DBA CMI FOR
PASSIVE OPTICAL LOCAL AREA NETWORK (PON) SERVICES FOR W-S00111, SOUTH TERMINAL C,
PHASE 1 - PROGRAM & PROJECT MANAGEMENT SERVICES (OAR), AT THE ORLANDO INTERNATIONAL
AIRPORT.
5. [A handout was presented, which includes a revised Memorandum and Supporting
Documentation.] Ms. Fischetti presented the memorandum, dated June 9, 2020, along
with a proposal from Cost Management, Inc., dated June 3, 2020, to provide services
related to the second product demonstration to be performed by the proposing PON
manufacturers in July 2020.
Services include assistance to the Aviation Authority staff in the areas of pre-test
set-up with the IT Department, participation in the PON manufacturer voluntary second
product demonstrations, evaluate proposal responses for each demonstration, and
participation in required meetings.
If approved, these services would be effective June 9, 2020.
The Office of Small Business Development has determined that due to the specialized
scope of the services to be provided, Cost Management, Inc. does not propose any
MWBE/LDB/VBE participation on this Addendum. [Subsequent to the meeting, the Office
of Small Business Development submitted an OSBD Participation Memorandum as
Information Item No. 7-H on the June 23, 2020, Construction Committee Agenda.]
Chairman Thornton asked for an explanation of the deliverables associated with the
request. Mr. Ruohomaki answered that this is for a complete repeat of the testing
set-up and services from Hahn Integrated Systems, Inc.
Ms. Sharman asked why Item No. 5 is for not-to-exceed fees and Item No. 6 is for
lump sum fees. Mr. Ruohomaki stated that Item No. 5 is for not-to-exceed fees, as
is typical for OAR type services. Chairman Thornton stated that Burns Engineering,
Inc. has a well-defined scope but that the Hahn Integrated Systems, Inc. fees will
depend on the utilization rate of services. Mr. Hahn added that this is to reset
the test lab, participate in the retesting, review and evaluation services, and
meeting participation. Chairman Thornton stated that the services provided by Hahn
Integrated Systems, Inc. will have a level of variability that make not-to-exceed
fees appropriate.
Mr. Hunt asked if this item is subject to the Construction Finance Oversight Committee
(CFOC). Ms. Sharman answered that she had received confirmation from Finance that
this item will not require CFOC.
Agenda Item Nos. 5 and 6 were considered in one motion.
Upon motion of Mr. Hunt, second by Ms. Schneider, vote carried by roll-call, with
all votes yea, to approve an Addendum to the Program and Project Management Services
for the South Terminal C, Phase 1 Agreement with Cost Management, Inc. for Passive
Optical Local Area Network (PON) Services for W-S00111, South Terminal C, Phase 1 -
Program & Project Management Services (OAR), for a total not-to-exceed fee amount
of $22,156.00, with funding from General Airport Revenue Bonds.
Minutes of the Construction Committee Meeting, June 9, 2020
Page 36 of 38
REQUEST FOR APPROVAL OF AN ADDENDUM TO THE TECHNOLOGY AND MULTI-MEDIA SYSTEMS
SPECIALTY ENGINEER FOR THE SOUTH TERMINAL C, PHASE 1 AGREEMENT WITH BURNS
ENGINEERING, INC. FOR PASSIVE OPTICAL LOCAL AREA NETWORK (PON) SERVICES FOR W-S00113,
SOUTH TERMINAL C, PHASE 1 - TECHNOLOGY AND MULTI-MEDIA SERVICES, AT THE ORLANDO
INTERNATIONAL AIRPORT.
6. [A handout was presented, which includes a revised Memorandum and Supporting
Documentation.] Ms. Fischetti presented the memorandum, dated June 9, 2020, along
with a proposal from Burns Engineering, Inc., dated May 27, 2020, to provide services
related to the second product demonstration to be performed by the proposing PON
manufacturers in July 2020.
Services include assistance to the Aviation Authority staff in the areas of pre-test
setup with the IT Department, participation in the PON manufacturer product
demonstrations, develop the evaluation spreadsheet of each product demonstration,
and participation in required meetings. The proposal includes Burns Engineering,
Inc.’s staff and subconsultant personnel on a lump sum basis.
If approved, these services would be effective June 9, 2020.
Consultant shall, with each monthly invoice, certify that the assigned work and
services are on schedule to be completed within the contracted lump sum price, or
provide at time of certification a written notice to the Aviation Authority of any
deviations.
The Office of Small Business Development has determined that due to the specialized
scope of the services to be provided, Burns Engineering, Inc. does not propose any
MWBE/LDB/VBE participation on this Addendum. [Subsequent to the meeting, the Office
of Small Business Development submitted an OSBD Participation Memorandum as
Information Item No. 7-I on the June 23, 2020, Construction Committee Agenda.]
Ms. Sharman asked why Item No. 5 is for not-to-exceed fees and Item No. 6 is for
lump sum fees. Mr. Ruohomaki stated that Item No. 5 is for not-to-exceed fees, as
is typical for OAR type services. Chairman Thornton stated that Burns Engineering,
Inc. has a well-defined scope, but that the Hahn Integrated Systems, Inc. fees will
depend on the utilization rate of services. Mr. Hahn added that this is to reset
the test lab, participate in the retesting, review and evaluation services, and
meeting participation. Chairman Thornton stated that the services provided by Hahn
Integrated Systems, Inc. will have a level of variability that make not-to-exceed
fees appropriate.
Mr. Hunt asked if this item is subject to the Construction Finance Oversight Committee
(CFOC). Ms. Sharman answered that she had received confirmation from Finance that
this item will not require CFOC.
Agenda Item Nos. 5 and 6 were considered in one motion.
Upon motion of Mr. Hunt, second by Ms. Schneider, vote carried by roll-call with all
votes yea, to approve an Addendum to the Technology and Multi-Media Systems Specialty
Engineer for the South Terminal C, Phase 1 Agreement with Burns Engineering, Inc.
for Passive Optical Local Area Network (PON) Services for W-S00113, South Terminal
C, Phase 1 - Technology and Multi-Media Services, for a total lump sum fee amount
of $28,356.00, with funding from General Airport Revenue Bonds.
Minutes of the Construction Committee Meeting, June 9, 2020
Page 37 of 38
GENERAL
REQUEST FOR APPROVAL OF AN AMENDMENT TO ADDENDUM NO. 5 TO THE CONTINUING ENVIRONMENTAL
CONSULTING SERVICES AGREEMENT WITH VANASSE HANGEN BRUSTLIN, INC. FOR ADDITIONAL
REVISIONS OF POITRAS PROPERTY CONSERVATION EASEMENT, AT THE ORLANDO INTERNATIONAL
AIRPORT.
7. [A handout was presented, which includes a new Supporting Documentation.]
r. Sorondo presented the memorandum, dated June 9, 2020, along with a proposal from
Vanasse Hangen Brustlin, Inc., dated May 21, 2020, to provide Additional Revisions
of the Poitras Property Conservation Easement, at the Orlando International Airport.
Between March 2017 and February 2020, the Construction Committee has approved Not-
to-Exceed (NTE) Fees and NTE Expenses for Addendum No. 5 and four Amendments to
Addendum No. 5 to the above-referenced agreement, in the following amounts:
CCM Approval Date Addendum / Amendment NTE Fee NTE Expense
March 28, 2017 Addendum No. 5 $22,550.00 $75.00
October 10, 2017 Amendment No. 1 $42,042.00 $225.00
January 22, 2019 Amendment No. 2 $39,686.00 $405.00
August 20, 2019 Amendment No. 3 $24,526.00 $3,990.00
February 25, 2020 Amendment No. 4 $1,524.00 ($1,524.00)
TOTALS $130,328.00 $3,171.00
Since that time, it has been discovered that additional conservation easement release
permitting services are needed for the Poitras Property at the Orlando International
Airport as further described in Consultant's proposal, dated May 21, 2020.
If approved, these services would be effective June 9, 2020.
The Office of Small Business Development has reviewed the qualifications of the
subject contract's MWBE/LDB/VBE specifications and determined that, due to the
limited scope of the required services, Vanasse Hangen Brustlin, Inc. does not
propose any small business participation on this Amendment.
Chairman Thornton stated that this will add value to the property which will come
back to the Aviation Authority.
Upon motion of Ms. Sharman, second by Mr. Hunt, vote carried by roll-call, with all
votes yea, to approve an Amendment to Addendum No. 5 to the Continuing Environmental
Consulting Services Agreement with Vanasse Hangen Brustlin, Inc. for Additional
Revisions of Poitras Property Conservation Easement, for the total amount of
$36,646.00, which includes the not-to-exceed fee amount of $28,686.00 and the not-
to-exceed reimbursable expense amount of $7,960.00, with funding from previously-approved Discretionary Funds.
REQUEST FOR RECOMMENDATION OF APPROVAL OF NO-COST ADDENDA TO THE CONTINUING VERTICAL
CONSTRUCTION SERVICES AGREEMENTS TO EXERCISE THE SECOND AND FINAL ONE-YEAR RENEWAL
OPTION.
8. Ms. Anderson presented the memorandum, dated June 9, 2020, to request for
recommendation of approval of No-Cost Addenda to the Continuing Vertical Construction
Services Agreements to Exercise the Second and Final One-Year Renewal Option, at the
Orlando International Airport. In October 2016, the Aviation Authority Board
approved Continuing Vertical Construction Services Agreements with the below listed
firms. The provisions in the agreements include a base three-year term with two
subsequent optional one-year renewal periods upon mutual agreement of the parties.
Each firm's first one-year renewal option expires as follows:
On TUESDAY, JUNE 23, 2020, the CONSTRUCTION COMMITTEE met in regular session
telephonically with the meeting live streamed on You Tube (www.OrlandoAirports.net).
Chairman Thornton called the meeting to order at 8:36 a.m. The meeting was posted
in accordance with Florida Statutes with a quorum participating. Office of the
Governor, Executive Order Number 20-69
Participating Committee members,
Stanley J. Thornton, Chairman
Kathleen Sharman, Chief Financial Officer
Mike Patterson, Director of Construction
Gary Hunt, Director of Maintenance
Denise Schneider, Assistant Director of Purchasing and Material Control
Also participating:
Karen Ryan, Legal Counsel (Nelson Mullins Broad & Cassel)
Dan Carrington, GOAA Environmental
Greg Watson, GOAA Construction
Scott Shedek, GOAA Construction
Alex Sorondo, HNTB Corporation
Chris Kieffer, A2 Group, Inc.
Don Corthell, PSA Management, Inc.
Jamie McGonagill, Geotech Consultants International, Inc. dba GCI, Inc.
Tara Ciaglia, Recording Secretary
LOBBYIST DISCLOSURE
Parties present were reminded that for individuals who conduct lobbying activities
with Aviation Authority employees or Board members, registration with the Aviation
Authority is required each year prior to conducting any lobbying activities. A
statement of expenditures incurred in connection with those lobbying instances should
also be filed prior to April 1st of each year for the preceding year. As of January
16, 2013, lobbying any Aviation Authority Staff who are members of any committee
responsible for ranking Proposals, Letters of Interest, Statements of Qualifications
or Bids and thereafter forwarding those recommendations to the Board and/or Board
Members is prohibited from the time that a Request for Proposals, Request for Letters
of Interests, Request for Qualifications or Request for Bids is released to the time
that the Board makes an award. As adopted by the Board on September 19, 2012,
lobbyists are now required to sign-in at the Aviation Authority offices prior to any
meetings with Staff or Board members. In the event a lobbyist meets with or otherwise
communicates with Staff or a Board member at a location other than the Aviation
Authority offices, the lobbyist shall file a Notice of Lobbying (Form 4) detailing
each instance of lobbying to the Aviation Authority within 7 calendar days of such
lobbying. As of January 16, 2013, lobbyists will also provide a notice to the
Aviation Authority when meeting with the Mayor of the City of Orlando or the Mayor
of Orange County at their offices. The policy, forms, and instructions are available
in the Aviation Authority’s offices and the website. Please contact the Director
of Board Services with questions at (407) 825-2032.
ANNOUNCEMENT
Any appeals of decisions made by the Construction Committee must be filed with the
Chief Executive Officer within five business days (no later than 4:00 p.m. on the
fifth business day) of the rendering of that decision. If a bidder or proposer is
aggrieved by any of the proceedings of today’s meeting and wishes to appeal the
results of actions made by this committee, they must file an appeal stating the item
they wish to appeal and the basis for which they wish to appeal, and it must be
received in writing by the Chief Executive Officer, Mr. Phillip N. Brown, via email
[email protected], with a copy to [email protected] (emails will be accepted during the
COVID-19 pandemic.)
Minutes of the Construction Committee Meeting, June 23, 2020
Page 2 of 47
COVID-19 ANNOUNCEMENT
Due to COVID-19, the Aviation Authority is adhering to a business distancing
operational plan. Please note that all Construction Committee meetings from today
until further notice will be held telephonically. If you would like to speak at the
meeting on an agenda item being considered, please contact the Recording Secretary,
Tara Ciaglia ([email protected] -or- 407-825-4461) no less than 24 hours in
advance of the meeting. Otherwise, the Construction Committee will be conducted
virtually via: https://global.gotomeeting.com/join/337969773.
CHANGE ORDER AGENDA
1. The following Change Orders were presented for consideration:
A. Change Order BP-00491-09 VARIOUS REVISIONS. This change order to the contract with H. W. Davis Construction, Inc. for West Security Screening Check Point
Expansion - Package 2 is to: 1. Provide labor, material, and equipment to
install 80 headed stud anchors on existing Level 3 steel beams at Column Line
F.5 and H, and Column Line 6.9. This work will increase structural capacity
for BP-00491 screening equipment loading. Scope of work includes coring
existing concrete deck, installing headed stud anchors, and utilizing high
strength grout to repair concrete cores. This change order replaces Field
Change Order No. 1. ADD: $17,537.00; 2. Provide labor, material, and equipment
for additional fire sprinkler work as part of Bulletin No. 5. ADD: $2,660.00;
3. Provide labor, material, and equipment to install an additional 80 LF of
4" sanitary sewer on Level 2 to tie into existing sanitary sewer line. ADD:
$5,204.00; and, 4. Provide labor, material, and equipment to remove and re-
install approximately 60 feet of 4" sanitary vent piping to Room 04-4118. ADD:
$9,134.00.
Upon motion of Mr. Hunt, second by Ms. Schneider, vote carried by roll-call
with all votes yea, to approve Change Order BP-00491-09, for a total amount
of $34,535.00 and no time extension, with funding from previously-approved
Capital Expenditure Funds and General Airport Revenue Bonds.
B. Change Order E-00238-02 ADDITIONAL FIRE WATCH PERSONNEL. This change order to the contract with Electric Services, Inc. for Airside 4 Fire Pump
Replacement is to provide additional Aviation Authority photo-badged personnel
as required to provide one additional person for up to an additional four days
on fire watch at all times, 24 hours a day, once the old system is taken
offline and until the new equipment is fully operational. Fire watch will
consist of full time roving of both ramp and transfer levels. This change
order replaces Field Change Order No. 1. ADD: $6,471.65.
Upon motion of Ms. Sharman, second by Mr. Hunt, vote carried by roll-call with
all votes yea, to approve Change Order E-00238-02, for a total amount of
$6,471.65 and no time extension, with funding from previously-approved Capital
Expenditure Funds.
C. Change Order H-00332-01 ADDITIONAL SPALL REPAIRS. This change order to the contract with Valencia Construction Group, Inc. for MCO Employee Parking Bus
Loop Pavement Rehabilitation - Phase 2 is the final change order and provides
all labor, material, and equipment to perform two additional spall repairs at
the contract unit rate of $1,021.11/spall repair, increasing the quantity from
six spall repairs to eight spall repairs. This change order replaces Field
Change Order No. 1. ADD: $2,042.22.
Upon motion of Ms. Sharman, second by Mr. Hunt, vote carried by roll-call with
all votes yea, to approve Change Order H-00332-01, for a total amount of
$2,042.22 and no time extension, with funding from previously-approved
Operation and Maintenance Funds.
Minutes of the Construction Committee Meeting, June 23, 2020
Page 3 of 47
[Chairman Thornton left the meeting at 8:42 a.m.; a quorum was maintained with
Ms. Sharman as Vice Chair.]
D. Change Order PS-00329-15 SOFTWARE SOLUTION UPGRADE. This change order to the contract with SKIDATA, Inc. for Parking Access and Revenue Control System
(PARCS) - Excludes 5-Year Maintenance is to provide all labor and software to
upgrade the current Commend (intercom) system to the VirtuoSIS software
solution. ADD: $19,728.00
Upon motion of Ms. Schneider, second by Mr. Hunt, vote carried by roll-call
with all votes yea, to approve Change Order PS-00329-15, for a total amount
of $19,728.00 and no time extension, with funding from previously-approved
Airport Facility Discretionary Fund, Capital Expenditure Funds, and
Improvement and Development Funds.
CONSTRUCTION MANAGEMENT AT RISK (CM@R) GUARANTEED MAXIMUM PRICE (GMP) BUDGET, BUYOUT,
AND CONTINGENCY MANAGEMENT REQUESTS AGENDA
2. The following GMP Budget, Buyout, and Contingency Management requests (related
to the South Terminal C, Phase One Project) were presented for consideration:
A. Subcontract Modification for BP-S00138 (GMP No. 5-S.1) with Berkel & Company Contractors, Inc. for CR0900-5S.1-GTF-Extended Scheduled OUC Shutdown.
Mr. Corthell presented the memorandum, requesting approval for Turner-Kiewit
Joint Venture (TKJV) to issue a Subcontract Modification on BP-S00138, South
Terminal C, Phase 1 – Landside Deep Foundations (GMP No. 5-S.1), at the Orlando
International Airport, in the total amount of $28,353.00 to Berkel & Company
Contractors, Inc. for CR0900-5S.1-GTF-Extended Scheduled OUC Shutdown. Bid
Package 31.0.0 "Augercast Piles" was previously awarded within GMP No. 5-S.1
"Landside Deep Foundations" to Berkel & Company Contractors, CC
No. 20171010.013.
TKJV is proposing a subcontractor modification to Berkel & Company Contractors,
Inc. in the total lump sum amount of $28,353.00 for CR0900-5S.1-GTF-Extended
Scheduled OUC Shutdown. Berkel & Company Contractors, Inc. was approved for
an additional 42 workdays of GTF Pile Installations under GMP No. 5-S.1
Amendment No. 1, CC No.20190604.007. Berkel & Company Contractors, Inc. as
worked progressed, TKJV identified an existing underground power conduit that
ran close to Pile 1512. TKJV performed underground investigations to locate
the conduit, which was found to be approximately two feet from the designed
location of Pile 1512. TKJV, OAR and GOAA agreed that the best course of action
was to deactivate the power conduit during the installation of Pile 1512 to
avoid any accidental contact. TKJV and OAR scheduled a power shutdown with OUC
for the first available time, which was on January 10, 2020. The modified
scope of work captured in this request consists of all costs and time associated
with the three additional calendar days to Berkel & Company Contractors, Inc.
approved duration, due to the deferment of Pile completion operations.
The approval of this subcontract modification request to Berkel & Company
Contractors, Inc. resolves all requests for costs associated with the scope
of work as described CR0900-5S.1-GTF Extended Scheduled OUC Shutdown. The OAR
is evaluating TIA 067 and any additional time recommended to be granted will
be submitted at a future CCM.
TKJV has submitted documentation including the subcontractor's proposal to
support their request. An independent cost estimate is included. By approving
this request, the Owner does not waive its right to enforce the contract
requirements for other requests for cost or time.
Minutes of the Construction Committee Meeting, June 23, 2020
Page 4 of 47
The effect of this Subcontract Modification for this project is as follows:
TKJV to issue a subcontract modification to Berkel &
Company Contractors, Inc. in the lump sum amount of: $ 28,353.00
Deduct from P1X CMAR Contingency: $ (28,353.00)
Turner-Kiewit Joint Venture is committed to 20% MWBE and 4% LDB participation
for Construction Services. The subcontractor identified and committed to
participate on BP-S00138 (GMP No. 5-S.1) for this subcontract modification is
Berkel & Company Contractors, Inc. (Non-MWBE/LDB/VBE). There is no small
business participation associated with this modification.
Agenda Item Nos. 2-A, 2-B, 2-C, 2-D, 2-E, 2-F, 2-G, 2-H, 2-I, 2-J, 2-K, 2-L,
2-M, 2-N, 2-O, 2-P, 2-Q, 2-R, 2-S, 2-T, 2-U, 2-V, 2-W, 2-X, 2-Y, 2-Z, 2-AA,
2-BB, 2-DD, 2-EE, 2-FF, 2-GG, 2-HH, 2-II, 2-JJ, and 2-KK were considered in
one motion.
Upon motion of Mr. Patterson, second by Mr. Hunt, vote carried by roll-call,
with all votes yea, to approve Turner-Kiewit Joint Venture to issue a
Subcontract Modification to Berkel & Company Contractors, Inc. on BP-S00138,
South Terminal C, Phase 1 – Landside Deep Foundations (GMP No. 5-S.1), for the
total lump sum amount of $28,353.00, with funding from Customer Facility
Charges and General Airport Revenue Bonds.
B. Subcontract Modification for BP-S00139 (GMP No. 5-S.2) with The Middlesex Corporation for CR0621.1-5S.2-LSC-RFI 2544-Additional Conveyance Drainage for
LST. Mr. Corthell presented the memorandum, requesting approval for Turner-
Kiewit Joint Venture (TKJV) to issue a Subcontract Modification on BP-S00139,
South Terminal C, Phase 1 – Landside Civil (GMP No. 5-S.2), at the Orlando
International Airport, in the total amount of $57,782.00 to The Middlesex
Corporation for CR0621.1-5S.2-LSC-RFI 2544-Additional Conveyance Drainage for
LST. Bid Package 31.0.0 "Sitework" was previously awarded within GMP No.
5-S.2 to The Middlesex Corporation, CC No. 20180504.05A.
TKJV is proposing a subcontract modification to The Middlesex Corporation in
the total lump sum amount of $57,782.00 for CR0621.1-5S.2-LSC-Additional
Conveyance Drainage for LST. LST Drawing P1.10.08 notes that for "underground
storm refer to civil engineering drawings for continuation". The LSC drawings
do not show this continuation, so RFI 2544 was submitted. The EOR provided new
sheets for the LST drainage connection for plumbing roof storm drainage to
civil storm lines not shown on the drawings. CR0621 was submitted and approved
for costs and time associated with RFI 2544, CC No. 20200218-3V. However,
CR0621.1 submitted by TKJV on May 20, 2020, clarifies that the previously
approved CR0621 only addressed the LST portion and that costs and time
associated with RFI 2544 for the LSC portion remained to be resolved in this
CR. The modified scope of work captured in this request consists of all labor,
material and equipment costs associated with connecting plumbing roof leaders
to civil storm lines based on RFI 2544 response.
The approval of this subcontract modification to The Middlesex Corporation
resolves all requests for costs and time associated with RFI 2544 in GMP No.
5-S.2. All cost impacts to GMP No. 7-S.3 were resolved in approved CR0621 CC
No. 20200218-3-V. No further CRs associated with RFI 2544 will be submitted.
TKJV has submitted documentation including the subcontractor's proposal to
support their request. An independent cost estimate is included. By approving
Minutes of the Construction Committee Meeting, June 23, 2020
Page 5 of 47
this request, the Owner does not waive its right to enforce the contract
requirements for other requests for cost or time.
The effect of this Subcontract Modification for this project is as follows:
TKJV to issue a subcontract modification to The
Middlesex Corporation in the lump sum amount of: $ 57,782.00
Deduct from P1 CMAR Contingency: $ (57,782.00)
Turner-Kiewit Joint Venture is committed to 20% MWBE and 4% LDB participation
for Construction Services. The subcontractor identified and committed to
participate on BP-S00138 (GMP No. 5-S.1) for this subcontract modification is
The Middlesex Corporation (Non-MWBE/LDB/VBE). There is 5.4% LDB participation
associated with this modification.
Agenda Item Nos. 2-A, 2-B, 2-C, 2-D, 2-E, 2-F, 2-G, 2-H, 2-I, 2-J, 2-K, 2-L,
2-M, 2-N, 2-O, 2-P, 2-Q, 2-R, 2-S, 2-T, 2-U, 2-V, 2-W, 2-X, 2-Y, 2-Z, 2-AA,
2-BB, 2-DD, 2-EE, 2-FF, 2-GG, 2-HH, 2-II, 2-JJ, and 2-KK were considered in
one motion.
Upon motion of Mr. Patterson, second by Mr. Hunt, vote carried by roll-call,
with all votes yea, to approve Turner-Kiewit Joint Venture to issue a
Subcontract Modification to The Middlesex Corporation on BP-S00138, South
Terminal C, Phase 1 – Landside Deep Foundations (GMP No. 5-S.1), for the total
lump sum amount of $57,782.00, with funding from General Airport Revenue Bonds
and Customer Facility Charges.
C. Subcontract Modification for BP-S00139 (GMP No. 5-S.2) with The Middlesex Corporation for CR0671.5-LSC-Hurricane Dorian Preparation and Recovery.
Mr. Corthell presented the memorandum, requesting approval for Turner-Kiewit
Joint Venture (TKJV) to issue a Subcontract Modification on BP-S00139, South
Terminal C, Phase 1 – Landside Civil (GMP No. 5-S.2), at the Orlando
International Airport, in the total amount of $87,689.00 to The Middlesex
Corporation for CR0671.5-LSC-Hurricane Dorian Preparation and Recovery. Bid
Package 31.0.0 "Sitework" was previously awarded within GMP No. 5-S.2 to The
Middlesex Corporation, CC No. 20180504.05A.
TKJV is proposing a subcontract modification to The Middlesex Corporation in
the lump sum amount of $87,689.00 for CR0671.5-LSC-Hurricane Dorian Preparation
and Recovery. The scope of Hurricane Dorian preparatory work consists of all
material, labor and equipment required to secure or remove subcontractor owned
equipment and materials. Work includes the temporary removal of fencing,
removal of MOT, backfilling open holes around incomplete work; grading
additional slopes for drainage, expediting disposal of trash, emptying
dumpsters to prepare for recovery; and preparing fuel pumps for dewatering.
The scope of Hurricane Dorian recovery work includes costs to remobilize the
jobsite including reinstalling MOT, repairing damaged slopes and grades from
heavy rains, reinstalling fence and wind susceptible materials, recovering
materials and removing bands; and removing pumps set up for dewatering.
The approval of this subcontract modification to The Middlesex Corporation
resolves all requests for costs and time associated with Hurricane Dorian
preparation and recovery for GMP No. 5-S.2.
TKJV has submitted documentation, including the subcontractor's proposal to
support their request. An independent cost review is included. By approving
this request, the Owner does not waive its right to enforce the contract
requirements for other requests for cost or time.
Minutes of the Construction Committee Meeting, June 23, 2020
Page 6 of 47
The effect of this Subcontract Modification for this project is as follows:
TKJV to issue a subcontract modification to The
Middlesex Corporation in the lump sum amount of: $ 87,689.00
Deduct from P1 CMAR Contingency: $ (87,689.00)
Turner-Kiewit Joint Venture is committed to 20% MWBE and 4% LDB participation
for Construction Services. The subcontractor identified and committed to
participate on BP-S00138 (GMP No. 5-S.1) for this subcontract modification is
The Middlesex Corporation (Non-MWBE/LDB/VBE). There is 15.4% MWBE
participation associated with this modification.
Agenda Item Nos. 2-A, 2-B, 2-C, 2-D, 2-E, 2-F, 2-G, 2-H, 2-I, 2-J, 2-K, 2-L,
2-M, 2-N, 2-O, 2-P, 2-Q, 2-R, 2-S, 2-T, 2-U, 2-V, 2-W, 2-X, 2-Y, 2-Z, 2-AA,
2-BB, 2-DD, 2-EE, 2-FF, 2-GG, 2-HH, 2-II, 2-JJ, and 2-KK were considered in
one motion.
Ms. Schneider asked if this is the final request related to Hurricane Dorian.
Mr. Corthell replied no, that there are a couple of additional items
forthcoming. Vice Chair Sharman asked if the items in process now are the
last expected. Mr. Corthell answered yes.
Upon motion of Mr. Patterson, second by Mr. Hunt, vote carried by roll-call,
with all votes yea, to approve Turner-Kiewit Joint Venture to issue a
Subcontract Modification to The Middlesex Corporation on BP-S00138, South
Terminal C, Phase 1 – Landside Deep Foundations (GMP No. 5-S.1), for the total
lump sum amount of $87,689.00, with funding from Customer Facility Charges and
General Airport Revenue Bonds.
D. Subcontract Modification for BP-S00139 (GMP No. 5-S.2) with The Middlesex Corporation for CR0728-5S.2-LSC-RFI 3504-Tie-in to Existing Service Road and
Detour Striping. Mr. Corthell presented the memorandum, requesting approval
for Turner-Kiewit Joint Venture (TKJV) to issue a Subcontract Modification on
BP-S00139, South Terminal C, Phase 1 – Landside Civil (GMP No. 5-S.2), at the
Orlando International Airport, in the total amount of $9,698.00 to The
Middlesex Corporation for CR0728-5S.2-LSC-RFI 3504-Tie-in to Existing Service
Road and Detour Striping. Bid Package 31.0.0 "Sitework" was previously awarded
within GMP No. 5-S.2 to The Middlesex Corporation, CC No. 20180504.05A.
TKJV is proposing a subcontract modification to The Middlesex Corporation in
the total lump sum amount of $9,698.00 for CR0728-5S.2-LSC-RFI 3504-Tie-in to
Existing Service Road and Detour Striping. In order to facilitate switching
the canal configuration, TKJV had to install a detour of Terminal C Service
Road. While performing additional reviews of the Scope of work, TKJV identified
scope gap between the GMPs for the installation of the detour road. RFI 3504
was issued to request details for the transition between roads. GMP No. 5-S.2
includes the permanent installation of the Terminal C Service Road, so no
paving of the permanent road, other than the additional asphalt for the
transition in RFI 3504, is included in this request. Striping of the permanent
Terminal C Service Road is also already included in GMP No. 5-S.2; however,
The Middlesex Corporation will need to re-stripe the road after the detour is
removed. Therefore, additional striping of the detour in the areas shown on
the sketch is needed. The modified scope of work consists of all additional
labor, material and equipment costs associated with installing additional
detour for service road to Terminal C, paving transition, restripe Terminal
Service Road C after temporary detour is removed.
Minutes of the Construction Committee Meeting, June 23, 2020
Page 7 of 47
The approval of this subcontract modification to The Middlesex Corporation
resolves all requests for time and costs for the Terminal C Service Rd tie-
in. This request also resolves all time and costs associated with the detour
road installation for GMP No. 5-S.2. CR1054 will resolve all time and costs
associated with the detour road installation for GMP No. 18-S.
TKJV has submitted documentation including the subcontractor's proposal to
support their request. An independent cost Review is included. By approving
this request, the Owner does not waive its right to enforce the contract
requirements for other requests for cost or time.
The effect of this Subcontract Modification for this project is as follows:
TKJV to issue a subcontract modification to The
Middlesex Corporation in the lump sum amount of: $ 9,698.00
Deduct from P1X CMAR Contingency: $ (4,391.00)
Deduct from P1X Owner Contingency: $ (5,307.00)
Turner-Kiewit Joint Venture is committed to 20% MWBE and 4% LDB participation
for Construction Services. The subcontractor identified and committed to
participate on BP-S00138 (GMP No. 5-S.1) for this subcontract modification is
The Middlesex Corporation (Non-MWBE/LDB/VBE). There is no small business
participation associated with this modification.
Agenda Item Nos. 2-A, 2-B, 2-C, 2-D, 2-E, 2-F, 2-G, 2-H, 2-I, 2-J, 2-K, 2-L,
2-M, 2-N, 2-O, 2-P, 2-Q, 2-R, 2-S, 2-T, 2-U, 2-V, 2-W, 2-X, 2-Y, 2-Z, 2-AA,
2-BB, 2-DD, 2-EE, 2-FF, 2-GG, 2-HH, 2-II, 2-JJ, and 2-KK were considered in
one motion.
Upon motion of Mr. Patterson, second by Mr. Hunt, vote carried by roll-call,
with all votes yea, to approve Turner-Kiewit Joint Venture to issue a
Subcontract Modification to The Middlesex Corporation on BP-S00138, South
Terminal C, Phase 1 – Landside Deep Foundations (GMP No. 5-S.1), for the total
lump sum amount of $9,698.00, with funding from General Airport Revenue Bonds.
E. Subcontractor Modification for BP-S00141 (GMP No. 5-S.4) with Schindler
Elevator Corporation for CR0506-LST-RFIs 1657 and 1657.1-Additional Remote
Machine Room for Escalator VFD. Mr. Corthell presented the memorandum,
requesting approval for Turner-Kiewit Joint Venture (TKJV) to issue a
Subcontractor Modification on BP-S00141, South Terminal C, Phase 1 – Landside
Conveying Equipment (GMP No. 5-S.4), at the Orlando International Airport, in
the total amount of $39,547.00 to Schindler Elevator Corporation, for CR0506-
LST-RFIs 1657 and 1657.1-Additional Remote Machine Room for Escalator VFD.
Bid Package 14.0.0 "Conveying Systems" was previously awarded within GMP No.
5-S.4 to Schindler Elevator Corporation, CC No. 20181004.007.
TKJV is proposing a subcontract modification to Schindler Elevator Corporation
in the total lump sum amount of $39,547.00 for CR0506-LST-RFIs 1657 and 1657.1-
Additional Remote Machine Room for Escalator VFD. LST RFI1657 response
confirmed placing the Variable Frequency Drive (VFD) in a remote machine room
for LST Escalators 6.1 and 6.2, as coordinated with the escalator manufacturer
and design team to resolve the issue with building steel members and the pit
size dimensions. The modified scope of work consists of additional labor and
material costs for the escalator manufacturer associated with the relocation
of VFDs for LST escalators 6.1 and 6.2.
The approval of this subcontract modification to Schindler Elevator Corporation
resolves all requests for costs and time resulting from RFIs 1657 and 1657.1
Minutes of the Construction Committee Meeting, June 23, 2020
Page 8 of 47
in GMP No. 5-S.4. CR0506.1 was approved at CCM for hollow metal doors in GMP
No. 7-S.1 CC No. 20191001-2-O. CRs for electrical scope in GMP No. 7-S.3, and
firestopping in GMP No. 7-S.1 are forthcoming. No other costs associated with
RFIs 1657 and 1657.1 will be submitted.
TKJV has submitted documentation including the subcontractor's proposal to
support their request. An independent cost estimate is included. By approving
this request, the Owner does not waive its right to enforce the contract
requirements for other requests for cost or time.
The effect of this Subcontractor Modification for this project is as follows:
TKJV to issue a subcontract modification to Schindler
Elevator Corporation in the lump sum amount of: $ 39,547.00
Deduct from P1 CMAR Contingency: $ (39,547.00)
Turner-Kiewit Joint Venture is committed to 20% MWBE and 4% LDB participation
for Construction Services. The subcontractor identified and committed to
participate on BP-S00141 (GMP No. 5-S.4) for this subcontract modification is
Schindler Elevator Corporation (Non-MWBE/LDB/VBE). There is no small business
participation associated with this modification.
Agenda Item Nos. 2-A, 2-B, 2-C, 2-D, 2-E, 2-F, 2-G, 2-H, 2-I, 2-J, 2-K, 2-L,
2-M, 2-N, 2-O, 2-P, 2-Q, 2-R, 2-S, 2-T, 2-U, 2-V, 2-W, 2-X, 2-Y, 2-Z, 2-AA,
2-BB, 2-DD, 2-EE, 2-FF, 2-GG, 2-HH, 2-II, 2-JJ, and 2-KK were considered in
one motion.
Upon motion of Mr. Patterson, second by Mr. Hunt, vote carried by roll-call,
with all votes yea, vote carried to approve Turner-Kiewit Joint Venture to
issue a Subcontractor Modification to Schindler Elevator Corporation on
BP-S00141, South Terminal C, Phase 1 – Landside Conveying Equipment (GMP No.
5-S.4), for the total lump sum amount of $39,547.00, with funding from
Passenger Facility Charges and General Airport Revenue Bonds.
F. Subcontract Modification for BP-S00143 (GMP No. 6-S.1) with BCI, Incorporated for CR0490-6S1-RFI 1545 W2 Curtain Wall Rough Opening Dimension (CWA BP-S143-
027). Mr. Corthell presented the memorandum, requesting approval for Hensel
Phelps Construction (HPC) to issue a Subcontract Modification on BP-S00143,
South Terminal C, Phase 1 - Airside Terminal, Structure and Enclosure (GMP No.
6-S.1), at the Orlando International Airport, in the total amount of $23,642.00
to BCI, Incorporated for CR0490-6S1-RFI 1545 W2 Curtain Wall Rough Opening
Dimension (CWA BP-S143-027). Bid Package 08.01 "Exterior Glass Systems" has
been previously awarded within GMP No. 6-S.1 to BCI, Incorporated, CC No.
20180619.03B.
HPC is requesting to issue a Subcontractor Modification to BCI, Incorporated
in the total Lump Sum amount of $23,642.00 for CR0490-6S1-RFI 1545 W2 Curtain
Wall Rough Opening Dimension. Curtain wall shop drawings were submitted with
floor plan from Al.12.18 Transfer Level floor plan dimension points. Shop
drawings were returned on May 23, 2019, with a note to fabricate to 6-feet 10-
inches per dimension on Al.14.18. The subcontractor requested clarification
on June 20, 2019, since the contract drawings on Al.14.18 showed a dimension
of 6-feet 4-inches. The shop drawings note was interpreted by HPC as a
potential typo, and the subcontractor was instructed to build per the contract
drawings (i.e., 6-feet 4-inches per Al.14.18). After further investigation,
RFI 1545 was issued but the glass had been fabricated to the 6-feet 4-inches
dimension instead of 6-feet 10-inches dimension prior to receipt of RFI 1545
response. The modified scope of work consists of the costs associated with the
Minutes of the Construction Committee Meeting, June 23, 2020
Page 9 of 47
re-fabrication, deglazing and re-glazing of the Curtain Wall window at
Gridline Intersection N1.9/A19 at the Arrivals Level Area 18, including
framing, per RFI 1545 response and sketches.
The approval of this Subcontractor Modification to BCI, Incorporated resolves
all requests for cost and time resulting from RFI 1545 and closes out CWA BP-
S143-027. Costs for Testing and Inspection, if any, will be submitted via a
future CR.
HPC has submitted documentation including the subcontractor's proposal to
support this request. An independent cost estimate is included. By approving
this request, the Owner does not waive its right to enforce the contract
requirements for other requests for cost or time.
The effect of this Subcontract Modification for this project is as follows:
HPC to issue a subcontract modification to BCI,
Incorporated in the lump sum amount of: $ 23,642.00
Deduct from P1 CMAR Contingency: $ (23,642.00)
Hensel Phelps Construction is committed to 20% MWBE and 4% LDB participation
for Construction Services. The subcontractor identified and committed to
participate on BP-S00143 (GMP No. 6-S.1) for this subcontract modification is
BCI, Incorporated (Non-MWBE/LDB/VBE). There is no small business participation
associated with this modification.
Agenda Item Nos. 2-A, 2-B, 2-C, 2-D, 2-E, 2-F, 2-G, 2-H, 2-I, 2-J, 2-K, 2-L,
2-M, 2-N, 2-O, 2-P, 2-Q, 2-R, 2-S, 2-T, 2-U, 2-V, 2-W, 2-X, 2-Y, 2-Z, 2-AA,
2-BB, 2-DD, 2-EE, 2-FF, 2-GG, 2-HH, 2-II, 2-JJ, and 2-KK were considered in
one motion.
Upon motion of Mr. Patterson, second by Mr. Hunt, vote carried by roll-call,
with all votes yea, to approve Hensel Phelps Construction to issue a
Subcontract Modification to BCI, Incorporated on BP-S00143, South Terminal C,
Phase 1 - Airside Terminal, Structure and Enclosure (GMP No. 6-S.1), for the
total lump sum amount of $23,642.00, with funding from General Airport Revenue
Bonds.
G. Subcontract Modification for BP-S00143 (GMP No. 6-S.1) with Odyssey
International dba Odyssey Global for CR0597.1-6S1-RFI 2438 Trash Chute Room
Partition Change - Masonry. Mr. Corthell presented the memorandum, requesting
approval for Hensel Phelps Construction (HPC) to issue a Subcontract
Modification on BP-S00143, South Terminal C, Phase 1 - Airside Terminal,
Structure and Enclosure (GMP No. 6-S.1), at the Orlando International Airport,
in the total deductive amount of ($11,931.00) to Odyssey International dba
Odyssey Global for CR0597.1-6S1-RFI 2438 Trash Chute Room Partition Change -
Masonry. Bid Package for BP-S00143 04.01 "Masonry" was previously awarded
within GMP No. 6-S.1 to Odyssey International dba Odyssey Global, CC No.
20180410.008.
HPC is requesting to issue a Subcontractor Modification to Odyssey
International dba Odyssey Global in the total deductive Lump Sum amount of
($11,931.00) for CR0597.1-6S1-RFI 2438 Trash Chute Room Partition Change -
Masonry. RFI 2438 changed the Concrete Masonry Unit (CMU) wall partition in
the Trash Chute Room 02-0691X in the Airside Concourse Transfer Level Area 29
to a rated gypsum wall assembly due to the elevated floor slabs inability to
support a CMU wall. The modified scope of work consists of a credit for the
Minutes of the Construction Committee Meeting, June 23, 2020
Page 10 of 47
materials, labor and equipment for the CMU wall that will no longer be
installed.
The approval of this Subcontractor Modification to Odyssey International dba
Odyssey Global resolves all requests for costs and time resulting from RFI
2438 scope of work in GMP No. 6-S.1. Cost impacts of RFI 2438 for GMPs Nos.
6-S.2 and 6-S.3 will be submitted, respectively, via CR0597.2 and CR0597.3,
for a future CCM approval. There are no cost impacts to GMP Nos. 6-S, 6-S.4,
6-S.5, and 6-S.6.
HPC has submitted documentation including the subcontractor's proposal to
support their request. An independent cost estimate is included. By approving
this request, the Owner does not waive its right to enforce the contract
requirements for other requests for costs or time.
The effect of this Subcontract Modification for this project is as follows:
HPC to issue a subcontract modification to
Odyssey International dba Odyssey Global in the
deductive lump sum amount of: $ (11,931.00)
Add to P1 Owner Contingency: $ 11,931.00
Hensel Phelps Construction is committed to 20% MWBE and 4% LDB participation
for Construction Services. The subcontractor identified and committed to
participate on BP-S00143 (GMP No. 6-S.1) for this subcontract modification is
Odyssey International, Inc. dba Odyssey Global (Non-MWBE/LDB/VBE at the time
of award of the "Masonry" bid package). There is a reduction of 96.9% in MWBE
participation associated with this modification.
Agenda Item Nos. 2-A, 2-B, 2-C, 2-D, 2-E, 2-F, 2-G, 2-H, 2-I, 2-J, 2-K, 2-L,
2-M, 2-N, 2-O, 2-P, 2-Q, 2-R, 2-S, 2-T, 2-U, 2-V, 2-W, 2-X, 2-Y, 2-Z, 2-AA,
2-BB, 2-DD, 2-EE, 2-FF, 2-GG, 2-HH, 2-II, 2-JJ, and 2-KK were considered in
one motion.
Upon motion of Mr. Patterson, second by Mr. Hunt, vote carried by roll-call
with all votes yea, to approve Hensel Phelps Construction to issue a
Subcontract Modification to Odyssey International dba Odyssey Global on BP-
S00143, South Terminal C, Phase 1 - Airside Terminal, Structure and Enclosure
(GMP No. 6-S.1), for the total deductive lump sum amount of ($11,931.00), with
funding from Aviation Authority Funds.
H. Subcontract Modifications for BP-S00143 (GMP No. 6-S.1) with Odyssey
International dba Odyssey Global; Banker Steel Co., LLC; Kirlin Florida, LLC;
and Randall Mechanical, Inc.; for CR0384-6S1-ASC Bulletin 028 Updates and RFI
1356 (CWA BP-S143-010). Mr. Corthell presented the memorandum, requesting
approval for Hensel Phelps Construction (HPC) to issue Subcontract
Modifications on BP-S00143, South Terminal C, Phase 1 - Airside Terminal,
Structure and Enclosure (GMP No. 6-S.1), at the Orlando International Airport,
in the total amount of $80,608.00 to Odyssey International dba Odyssey Global;
Banker Steel Co., LLC; Kirlin Florida, LLC; and Randall Mechanical, Inc.; for
CR0384-6S1-ASC Bulletin 028 Updates and RFI 1356 (CWA BP-S143-010). Bid
Package for BP-S143 04.01 "Masonry"; 05.01 "Structural Steel and Miscellaneous
Metals"; 21.01 "Fire Suppression" and 23.01 "HVAC" were previously awarded
within GMP No. 6-S.1, respectively, to Odyssey International Inc. dba Odyssey
Global; Banker Steel Co., LLC; Randall Mechanical, Inc.; and Randall
Mechanical, Inc.; CC No. 201800410.008.
Minutes of the Construction Committee Meeting, June 23, 2020
Page 11 of 47
Bid Package 22.01 "Plumbing" was previously awarded within GMP No. 6-S.1 to
Kirlin Florida, LLC, CC No. 20180522.04H.
HPC is requesting to issue the following Subcontractors Modifications to;
1. Odyssey International Inc. dba Odyssey Global in the deductive Lump Sum amount of ($45,041.00) for CR0384-6S1-ASC Bulletin 028 Updates and RFI
1356. The modified scope of work consists of the credits associated with
the deleted Concrete Masonry Unit (CMU) walls from the Tenant Spaces in
Areas 27, 28 and 29 on the Ramp Level;
2. Banker Steel Co., LLC in the Lump Sum amount of $6,369.00 for CR0384-6S1-ASC Bulletin 028 Updates and RFI 1356. The modified scope of work
consists of the costs associated with the removal and the relocation of
the Wind Columns in Areas 27 and 29, between Gridlines B4/X22-X24 and
B4/X29-X30;
3. Kirlin Florida, LLC in the deductive Lump Sum amount of ($35,106.00) for CR0384-6S1-ASC Bulletin 028 Updates and RFI 1356. The modified scope of
work consists of the credits associated with the revised Underground
(UG) and Aboveground (AG) services for the concession spaces in Area 17;
removed water heaters and revised gas line quantities and sizes;
4. Randall Mechanical, Inc. for Fire Suppression in the Lump Sum amount of $2,467.00 for CR0384-6S1-ASC Bulletin 028 Updates and RFI 1356. The
modified scope of work consists of the costs associated with the BIM
Spatial Coordination of areas that were previously coordinated;
5. Randall Mechanical, Inc. for HVAC in the Lump Sum amount of $151,919.00 for CR0384-6S1-ASC Bulletin 028 Updates and RFI 1356. The modified scope
of work consists of the costs associated with the re-routing of ductwork
throughout the Ramp level, elimination of ductwork in Area 26 of the
Ramp Level, relocation of fire dampers from horizontal position to the
wall of shafts, added and deleted fire dampers, and kitchen ductwork
modifications.
HPC will submit Time Impact Analysis (TIA 070) requesting additional time
associated with this scope of work for ASC Bulletin 028.
ASC Bulletin 028 affected the scope of work in GMP Nos. 6-S.1, 6-S.2, 6-S.3,
6-S.4, and 6-S.6. The approval of these Subcontractors Modifications to
Odyssey International Inc. dba Odyssey Global; Banker Steel Co., LLC; Kirlin
Florida, LLC; and Randall Mechanical, Inc. resolves all requests for cost
resulting from ASC Bulletin 028; RFIs 1317, 1477, 1546, 1795, 1175, 1176,
1177, 1356.1, 1477.1, 1672, 1681, 1681.1, 1684 and 1356 in GMP No. 6-S.1 and
closes out CWA BP-S143-010, which covered only a portion of the plumbing scope
of ASC Bulletin 28 and RFI 1356. Costs for patching of Fireproofing and
Insulation, and Testing and Inspection, if any, are excluded and will be
submitted in future CRs. Costs of RFIs 0818, 0818.1, 0818.2 and 0818.3 are
excluded and will be submitted in future CRs. Costs of RFI 1177 associated
with the HVAC scope of work were approved via CC No. 20191203.01A (CR0388-
6S1). Costs of RFI 1356 associated with the Building Concrete scope of work
were approved via CC No. 20200421.03E (CR0529). Impacts of ASC Bulletin 028
to GMP No. 6-S.2 were approved via CC No. 20200204.02G (CR0385-6S2). Impacts
of ASC Bulletin 028 to GMP No. 6-S.3 were approved via CC No. 20200421.03G
(CR0386-6S3). Impacts associated with RFI 1684.1 are included only for the
Doors, Frames and Hardware trade (CR0386-6S3). Impacts of ASC Bulletin 028
to GMP No. 6-S.4 will be submitted via CR0387-6S4 for a future CCM approval.
Impacts to GMP No. 6-S.4 Low Voltage associated with RFI 1684.1 were approved
Minutes of the Construction Committee Meeting, June 23, 2020
Page 12 of 47
via CC No. 20200114.03P (CR0440.2-6S4). Impacts to GMP No. 6-S.1 Masonry
associated with RFI 1684.1 will be submitted for a future CCM approval
(CR0440.1-6S1). Impacts to GMP Nos. 6-S.4 and 6-S.6 associated with RFI 1672
were approved, respectively, via CC No. 20200303.02BB (CR0481), and CC No.
20200324.02PP (CR0509). All other trades impacted by RFI 1684.1 are to be
submitted in future CRs. There are no costs to GMP Nos. 6-S or 6-S.5. The
OAR will evaluate TIA-070 and any additional time recommended to be granted
will be submitted at a future CCM.
Hensel Phelps Construction has submitted documentation including the
subcontractor's proposal to support this request. An independent cost estimate
is included. By approving this request, the Owner does not waive its right to
enforce the contract requirements for other requests for cost or time.
The effect of these Subcontract Modifications for this project is as follows:
HPC to issue a subcontract modification to
Odyssey International dba Odyssey Global in the
deductive lump sum amount of: $ (45,041.00)
HPC to issue a subcontract modification to Banker
Steel Co., LLC in the lump sum amount of: $ 6,369.00
HPC to issue a subcontract modification to Kirlin
Florida, LLC in the deductive lump sum amount of: $ (35,106.00)
HPC to issue a subcontract modification to
Randall Mechanical, Inc. (Fire Suppression) in
the lump sum amount of: $ 2,467.00
HPC to issue a subcontract modification to
Randall Mechanical, Inc. (HVAC) in the lump sum
amount of: $ 151,919.00
Deduct from P1 Owner Contingency: $ (80,608.00)
Hensel Phelps Construction is committed to 20% MWBE and 4% LDB participation
for Construction Services. The subcontractors identified and committed to
participate on BP-S00143 (GMP No. 6-S.1) for these subcontract modifications
are as follows: Odyssey International, Inc. dba Odyssey Global (Non-
MWBE/LDB/VBE at the time of award of the "Masonry" bid package); Banker Steel
Co., LLC (Non-MWBE/LDB/VBE); Kirlin Florida, LLC (Non-MWBE/LDB/VBE); and,
Randall Mechanical, Inc. (Non-MWBE/LDB/VBE). There is no small business
participation associated with the subcontract modifications to Banker Steel
Co., LLC; Kirlin Florida, LLC; and Randall Mechanical, Inc. There is a
reduction of 88.6% in MWBE participation associated with the subcontract
modification to Odyssey International, Inc. dba Odyssey Global.
Agenda Item Nos. 2-A, 2-B, 2-C, 2-D, 2-E, 2-F, 2-G, 2-H, 2-I, 2-J, 2-K, 2-L,
2-M, 2-N, 2-O, 2-P, 2-Q, 2-R, 2-S, 2-T, 2-U, 2-V, 2-W, 2-X, 2-Y, 2-Z, 2-AA,
2-BB, 2-DD, 2-EE, 2-FF, 2-GG, 2-HH, 2-II, 2-JJ, and 2-KK were considered in
one motion.
Upon motion of Mr. Patterson, second by Mr. Hunt, vote carried by roll-call,
with all votes yea, to approve Hensel Phelps Construction to issue Subcontract
Modifications on BP-S00143, South Terminal C, Phase 1 - Airside Terminal,
Structure and Enclosure (GMP No. 6-S.1), for the total amount of $80,608.00,
which includes the deductive lump sum amount of ($45,041.00) to Odyssey
International dba Odyssey Global; the lump sum amount of $6,369.00 to Banker Steel Co., LLC; the deductive lump sum amount of($35,106.00) to Kirlin Florida,
LLC; lump sum amount of $2,467.00 to Randall Mechanical, Inc. (Fire
Suppression); and the lump sum amount of $151,919.00 to Randall Mechanical,
Minutes of the Construction Committee Meeting, June 23, 2020
Page 13 of 47
Inc. (HVAC); with funding from Passenger Facility Charges and General Airport
Revenue Bonds.
I. Subcontract Modification for BP-S00143 (GMP No. 6-S.1) with Loyal Waterproofing Construction, Inc. for CR0518.1-6S1-RFIs 2110, 2110.1 and 2124 Series P1X
Elevator Pits and Foundation Waterproofing. Mr. Corthell presented the
memorandum, requesting approval for Hensel Phelps Construction (HPC) to issue
a Subcontract Modification on BP-S00143, South Terminal C, Phase 1 - Airside
Terminal, Structure and Enclosure (GMP No. 6-S.1), at the Orlando International
Airport, in the total amount of $28,709.00 to Loyal Waterproofing Construction,
Inc. for CR0518.1-6S1-RFIs 2110, 2110.1 and 2124 Series P1X Elevator Pits and
Foundation Waterproofing. Bid Package for BP-S00143 07.05 "Foundation
Waterproofing" was previously awarded within GMP No. 6-S.1 to Loyal
Waterproofing Construction, Inc., CC No. 20180410.008.
HPC is requesting to issue a Subcontractor Modification to Loyal Waterproofing
Construction, Inc. in the total Lump Sum amount of $28,709.00 for CR0518.1-
6Sl-RFIs 2110, 2110.1 and 2124 Series P1X Elevator Pits and Foundation
Waterproofing. The modified scope of work consists of the additional costs
associated with adding the Waterproofing Membrane for each of the four P1X
Passenger Boarding Piers (PBP) foundations and Elevator sump pits, per RFIs
2110, 2110.1 and 2124 Series responses and sketches.
The approval of this Subcontractor Modifications to Loyal Waterproofing
Construction, Inc. resolves all requests for cost and time resulting from RFIs
2110, 2110.1 and 2124 scope of work in GMP No. 6-S.1. Cost impacts for RFIs
2110, 2110.1 and 2124 to GMP No. 6-S.6 were approved via CR0518-6S6, CC No.
20200421.03Y. There are no cost impacts for RFIs 2110, 2110.1 and 2124 Series
to GMP Nos. 6-S, 6-S.2, 6-S.3, 6-S.4, and 6-S.5.
HPC has submitted documentation including the subcontractor's proposal to
support their request. An independent cost estimate is included. By approving
this request, the Owner does not waive its right to enforce the contract
requirements for other requests for costs or time.
The effect of this Subcontract Modification for this project is as follows:
HPC to issue a subcontract modification to Loyal
Waterproofing Construction, Inc. in the lump sum
amount of: $ 28,709.00
Deduct from P1X Owner Contingency: $ (28,709.00)
Hensel Phelps Construction is committed to 20% MWBE and 4% LDB participation
for Construction Services. The subcontractor identified and committed to
participate on BP-S00143 (GMP No. 6-S.1) for this subcontract modification is
Loyal Waterproofing Construction, Inc. (DBE/MWBE). There is 100% MWBE
participation associated with this modification.
Agenda Item Nos. 2-A, 2-B, 2-C, 2-D, 2-E, 2-F, 2-G, 2-H, 2-I, 2-J, 2-K, 2-L,
2-M, 2-N, 2-O, 2-P, 2-Q, 2-R, 2-S, 2-T, 2-U, 2-V, 2-W, 2-X, 2-Y, 2-Z, 2-AA,
2-BB, 2-DD, 2-EE, 2-FF, 2-GG, 2-HH, 2-II, 2-JJ, and 2-KK were considered in
one motion.
Upon motion of Mr. Patterson, second by Mr. Hunt, vote carried by roll-call,
with all votes yea, to approve Hensel Phelps Construction to issue a
Subcontract Modification to Loyal Waterproofing Construction, Inc. on
BP-S00143, South Terminal C, Phase 1 - Airside Terminal, Structure and
Minutes of the Construction Committee Meeting, June 23, 2020
Page 14 of 47
Enclosure (GMP No. 6-S.1), for the total lump sum amount of $28,709.00, with
funding from Passenger Facility Charges.
J. Subcontract Modification for BP-S00143 (GMP No. 6-S.1) with Banker Steel Co., LLC for CR0547-6S1-RFI 2174 PBP 241 Curtain Wall and Concrete Slab Discrepancy
(CWA BP-S143-025). Mr. Corthell presented the memorandum, requesting approval
for Hensel Phelps Construction (HPC) to issue a Subcontract Modification on
BP-S00143, South Terminal C, Phase 1 - Airside Terminal, Structure and
Enclosure (GMP No. 6-S.1), at the Orlando International Airport, in the total
amount of $65,309.00 to Banker Steel Co., LLC, for CR0547-6S1-RFI 2174 PBP 241
Curtain Wall and Concrete Slab Discrepancy (CWA BP-S143-025). Bid Package for
BP-S143 05.01 "Structural Steel and Miscellaneous Metals" has been previously
awarded within GMP No. 6-S.1 to Banker Steel Co., LLC, CC No. 20180410.008.
HPC is requesting to issue a Subcontractor Modification to Banker Steel Co.,
LLC in the total Lump Sum amount of $65,309.00 for CR0547-6S1-RFI 2174 PBP 241
Curtain Wall and Concrete Slab Discrepancy. The modified scope of work consists
of the Detailing, Material, Fabrication and Erection costs associated with the
added structural steel required to support the Curtain Wall and Exterior
Framing at the Passenger Boarding Pier (PBP) 241, per RFI 2174.
The approval of this Subcontractor Modifications to Banker Steel Co., LLC
resolves all requests for cost and time resulting from RFI 2174 scope of work
and closes out CWA BP-S143-025. Costs for patching of Fireproofing and Testing
& Inspection, if any, will be submitted in a future CR.
HPC has submitted documentation including the subcontractor's proposal to
support their request. An independent cost estimate is included. By approving
this request, the Owner does not waive its right to enforce the contract
requirements for other requests for costs or time.
The effect of this Subcontract Modification for this project is as follows:
HPC to issue a subcontract modification to Banker
Steel Co., LLC in the lump sum amount of: $ 65,309.00
Deduct from P1 Owner Contingency: $ (65,309.00)
Hensel Phelps Construction is committed to 20% MWBE and 4% LDB participation
for Construction Services. The subcontractor identified and committed to
participate on BP-S00143 (GMP No. 6-S.1) for this subcontract modification is
Banker Steel Co., LLC (Non-MWBE/LDB/VBE). There is no small business
participation associated with this modification.
Agenda Item Nos. 2-A, 2-B, 2-C, 2-D, 2-E, 2-F, 2-G, 2-H, 2-I, 2-J, 2-K, 2-L,
2-M, 2-N, 2-O, 2-P, 2-Q, 2-R, 2-S, 2-T, 2-U, 2-V, 2-W, 2-X, 2-Y, 2-Z, 2-AA,
2-BB, 2-DD, 2-EE, 2-FF, 2-GG, 2-HH, 2-II, 2-JJ, and 2-KK were considered in
one motion.
Upon motion of Mr. Patterson, second by Mr. Hunt, vote carried by roll-call,
with all votes yea, to approve Hensel Phelps Construction to issue a
Subcontract Modification to Banker Steel Co., LLC on BP-S00143, South Terminal
C, Phase 1 - Airside Terminal, Structure and Enclosure (GMP No. 6-S.1), for
the total lump sum amount of $65,309.00, with funding from Passenger Facility
Charges.
Minutes of the Construction Committee Meeting, June 23, 2020
Page 15 of 47
K. Subcontract Modification for BP-S00143 (GMP No. 6-S.1) with Odyssey
International dba Odyssey Global for CR0573.1-6S1-RFI 2283 Added Door 01-4006B
- Masonry. Mr. Corthell presented the memorandum, requesting approval for
Hensel Phelps Construction (HPC) to issue a Subcontract Modification on
BP-S00143, South Terminal C, Phase 1 - Airside Terminal, Structure and
Enclosure (GMP No. 6-S.1), at the Orlando International Airport, in the total
amount of $16,867.00 to Odyssey International dba Odyssey Global for CR0573.1-
6S1-RFI 2283 Added Door 01-4006B - Masonry. Bid Package for BP-S00143 04.01
"Masonry" was previously awarded within GMP No. 6-S.1 to Odyssey International
dba Odyssey Global, CC No. 20180410.008.
HPC is requesting to issue a Subcontractor Modification to Odyssey
International dba Odyssey Global in the total Lump Sum amount of $16,867.00
for CR0573.1-6S1-RFI 2283 Added Door 01-4006B - Masonry. The modified scope
of work consists of the costs associated with the demolition of the Concrete
Masonry Unit (CMU) wall and preparation of opening for the Hollow Metal (HM)
Door 01-4006B added in Plants Room 01-1124 on the Ramp Level Area 25, per RFI
2283 response.
The approval of this Subcontractor Modification to Odyssey International dba
Odyssey Global resolves all requests for cost and time resulting from RFI 2283
for Masonry scope of work in GMP No. 6-S.1. Costs for RFI 2283 in GMPs No.
6-S.3 (CR0573.2 for Doors, Frames, and Hardware) and GMP No. 6-S.4 (CR0573.3
for Painting) were approved, respectively, via CC Nos. 20200526.03I and
20200526.03QQ.
HPC has submitted documentation including the subcontractor's proposal to
support their request. An independent cost estimate is included. By approving
this request, the Owner does not waive its right to enforce the contract
requirements for other requests for costs or time.
The effect of this Subcontract Modification for this project is as follows:
HPC to issue a subcontract modification to
Odyssey International dba Odyssey Global in the
lump sum amount of: $ 16,867.00
Deduct from P1 Owner Contingency: $ (16,867.00)
Hensel Phelps Construction is committed to 20% MWBE and 4% LDB participation
for Construction Services. The subcontractor identified and committed to
participate on BP-S00143 (GMP No. 6-S.1) for this subcontract modification is
Odyssey International, Inc. dba Odyssey Global (Non-MWBE/LDB/VBE at the time
of award of the "Masonry" bid package). There is 94.8% MWBE participation
associated with this modification.
Agenda Item Nos. 2-A, 2-B, 2-C, 2-D, 2-E, 2-F, 2-G, 2-H, 2-I, 2-J, 2-K, 2-L,
2-M, 2-N, 2-O, 2-P, 2-Q, 2-R, 2-S, 2-T, 2-U, 2-V, 2-W, 2-X, 2-Y, 2-Z, 2-AA,
2-BB, 2-DD, 2-EE, 2-FF, 2-GG, 2-HH, 2-II, 2-JJ, and 2-KK were considered in
one motion.
Upon motion of Mr. Patterson, second by Mr. Hunt, vote carried by roll-call,
with all votes yea, to approve Hensel Phelps Construction to issue a
Subcontract Modification to Odyssey International dba Odyssey Global on
BP-S00143, South Terminal C, Phase 1 - Airside Terminal, Structure and
Enclosure (GMP No. 6-S.1), for the total lump sum amount of $16,867.00, with
funding from General Airport Revenue Bonds.
Minutes of the Construction Committee Meeting, June 23, 2020
Page 16 of 47
L. Subcontract Modification for BP-S00143 (GMP No. 6-S.1) with Banker Steel Co., LLC for CR0587-6S1-RFIs 0774 and 0774.1 - Windows on Orlando Edge of Slab
Discrepancy (CWA BP-S143-030). Mr. Corthell presented the memorandum,
requesting approval for Hensel Phelps Construction (HPC) to issue a Subcontract
Modification on BP-S00143, South Terminal C, Phase 1 - Airside Terminal,
Structure and Enclosure (GMP No. 6-S.1), at the Orlando International Airport,
in the total amount of $6,678.00 to Banker Steel Co., LLC, for CR0587-6S1-RFIs
0774 and 0774.1 - Windows on Orlando Edge of Slab Discrepancy (CWA BP-S143-
030). Bid Package for BP-S143 05.01 "Structural Steel and Miscellaneous
Metals" has been previously awarded within GMP No. 6-S.1 to Banker Steel Co.,
LLC, CC No. 20180410.008.
HPC is requesting to issue a Subcontractor Modification to Banker Steel Co.,
LLC in the total Lump Sum amount of $6,678.00 for CR0587-6Sl-RFIs 0774 and
0774.1 - Windows on Orlando Edge of Slab Discrepancy. The modified scope of
work consists of the Detailing, Material, Fabrication and Erection costs
associated with the Structural Steel angles installed past the edge of the
previously placed Slab-on-Metal-Deck (SOMD), at the Transfer Level of the
Airside Concourse N1 Windows-on-Orlando (WOO) Bump-out Area between Column
Lines X18 and X21 and along Column Line B15, to support the exterior cold-
formed metal wall framing, per RFIs 0774 and 0774.1 responses and sketches.
The approval of this Subcontractor Modification to Banker Steel Co., LLC
resolves all requests for cost and time resulting from RFIs 0774 and 0774.1
scope of work and closes out CWA BP-S143-030. Costs for Testing and Inspection,
if any, will be submitted in a future CR. There are no cost impacts for RFIs
0774 and 0774.1 to GMP Nos. 6-S, 6-S.2, 6-S.3, 6-S.4, 6-S.5, and 6-S.6.
HPC has submitted documentation including the subcontractor's proposal to
support their request. An independent cost estimate is included. By approving
this request, the Owner does not waive its right to enforce the contract
requirements for other requests for costs or time.
The effect of this Subcontract Modification for this project is as follows:
HPC to issue a subcontract modification to Banker
Steel Co., LLC in the lump sum amount of: $ 6,678.00
Deduct from P1 Owner Contingency: $ (6,678.00)
Hensel Phelps Construction is committed to 20% MWBE and 4% LDB participation
for Construction Services. The subcontractor identified and committed to
participate on BP-S00143 (GMP No. 6-S.1) for this subcontract modification is
Banker Steel Co., LLC (Non-MWBE/LDB/VBE). There is no small business
participation associated with this modification.
Agenda Item Nos. 2-A, 2-B, 2-C, 2-D, 2-E, 2-F, 2-G, 2-H, 2-I, 2-J, 2-K, 2-L,
2-M, 2-N, 2-O, 2-P, 2-Q, 2-R, 2-S, 2-T, 2-U, 2-V, 2-W, 2-X, 2-Y, 2-Z, 2-AA,
2-BB, 2-DD, 2-EE, 2-FF, 2-GG, 2-HH, 2-II, 2-JJ, and 2-KK were considered in
one motion.
Upon motion of Mr. Patterson, second by Mr. Hunt, vote carried by roll-call,
with all votes yea, to approve Hensel Phelps Construction to issue a
Subcontract Modification to Banker Steel Co., LLC on BP-S00143, South Terminal
C, Phase 1 - Airside Terminal, Structure and Enclosure (GMP No. 6-S.1), for
the total lump sum amount of $6,678.00, with funding from General Airport
Revenue Bonds.
Minutes of the Construction Committee Meeting, June 23, 2020
Page 17 of 47
M. Subcontract Modification for BP-S00144 (GMP No. 6-S.2) with Wal-Mark
Contracting Group, LLC for CR0597.2-6S2-RFI 2438 Trash Chute Room Partition
Change - Framing and Drywall. Mr. Corthell presented the memorandum,
requesting approval for Hensel Phelps Construction (HPC) to issue a Subcontract
Modification on BP-S00144, South Terminal C, Phase 1 - STC Airside Enclosure
and Exterior Finishes (GMP No. 6-S.2), at the Orlando International Airport,
in the total amount of $11,621.00 to Wal-Mark Contracting Group, LLC for
CR0597.2-6S2-RFI 2438 Trash Chute Room Partition Change - Framing and Drywall.
Bid Package for 09.02 "Framing and Drywall" was previously awarded within GMP
No. 6-S.2 to Wal-Mark Contracting Group LLC, CC No. 20180605.006.
HPC is requesting to issue a Subcontractor Modification to Wal-Mark Contracting
Group LLC in the total Lump Sum amount of $11,621.00 for CR0597.2-6S2-RFI 2438
Trash Chute Room Partition Change - Framing and Drywall. The modified scope
of work consists of the costs associated with replacing the Concrete Masonry
Unit (CMU) walls to Gypsum Board Walls for Trash Chute Room 02-0691X at the
ASC Transfer Level Area 29, including the framing and firestopping, per RFI
2438 response and sketches.
The approval of this Subcontractor Modification to Wal-Mark Contracting Group
LLC resolves all requests for cost and time resulting from RFI 2438 scope of
work in GMP No. 6-S.2. Cost impacts of RFI 2438 to GMPs Nos. 6-S.1 and 6S.3
will be submitted, respectively, via CR0597.1 and CR0597.3, for a future CCM
approval. There are no cost or time impacts to GMP Nos. 6-S, 6-S.4, 6-S.5 and
6-S.6.
HPC has submitted documentation including the subcontractor's proposal to
support this request. An independent cost estimate is included. By approving
this request, the Owner does not waive its right to enforce the contract
requirements for other requests for cost or time.
The effect of this Subcontract Modification for this project is as follows:
HPC to issue a subcontract modification to Wal-Mark
Contracting Group, LLC in the lump sum amount of: $ 11,621.00
Deduct from P1 Owner Contingency: $ (11,621.00)
Hensel Phelps Construction is committed to 20% MWBE and 4% LDB participation
for Construction Services. The subcontractor identified and committed to
participate on BP-S00144 (GMP No. 6-S.2) for this subcontract modification is
Wal-Mark Contracting Group, LLC (Non-MWBE/LDB/VBE). There is no small business
participation associated with this modification.
Agenda Item Nos. 2-A, 2-B, 2-C, 2-D, 2-E, 2-F, 2-G, 2-H, 2-I, 2-J, 2-K, 2-L,
2-M, 2-N, 2-O, 2-P, 2-Q, 2-R, 2-S, 2-T, 2-U, 2-V, 2-W, 2-X, 2-Y, 2-Z, 2-AA,
2-BB, 2-DD, 2-EE, 2-FF, 2-GG, 2-HH, 2-II, 2-JJ, and 2-KK were considered in
one motion.
Upon motion of Mr. Patterson, second by Mr. Hunt, vote carried by roll-call,
with all votes yea, to approve Hensel Phelps Construction to issue a
Subcontract Modification to Wal-Mark Contracting Group, LLC on BP-S00144,
South Terminal C, Phase 1 - STC Airside Enclosure and Exterior Finishes (GMP
No. 6-S.2), for the total lump sum amount of $11,621.00, with funding from
General Airport Revenue Bonds.
Minutes of the Construction Committee Meeting, June 23, 2020
Page 18 of 47
N. Subcontractor Modification for BP-S00145 (GMP No. 6-S.3) with MULE Engineering & Construction, Inc. for CR0597.3-6S3-RFI 2438 Trash Chute Room Partition
Change and CR0598.3-6S3-RFI 2284.1 Mechanical Room Partition Change - Doors,
Frames and Hardware. Mr. Corthell presented the memorandum, requesting
approval for Hensel Phelps Construction (HPC) to issue a Subcontract
Modification on BP-S00145, South Terminal C, Phase 1 - Airside Early Interiors
(GMP No. 6-S.3), at the Orlando International Airport, in the total amount of
$1,108.00 to MULE Engineering & Construction, Inc. for CR0597.3-6S3-RFI 2438
Trash Chute Room Partition Change and CR0598.3-6S3-RFI 2284.1 Mechanical Room
Partition Change - Doors, Frames and Hardware. Bid Package for BP-S00145
08.03 "Doors, Frames and Hardware" has been previously awarded within GMP No.
6-S.3 to MULE Engineering & Construction, Inc., CC No. 20181009.03C.
HPC is requesting to issue a Subcontractor Modification to MULE Engineering &
Construction, Inc. in the total Lump Sum amount of $1,108.00 for:
1. CR0597.3-6S3-RFI 2438 Trash Chute Room Partition Change - $692.00.
RFI 2438 changed CMU walls to a non-CMU wall type partition, which
affected door frames at Opening 02-0056A that had already been fabricated
to accommodate a CMU wall type. The modified scope of work consists of
the material costs associated with the re-fabrication of the Hollow
Metal (HM) A1 Type single-leaf doorframe for Opening 02-0056A at the
Trash Chute Room 02-0691X, Transfer Level Area 29, per RFI 2438 response
and sketches.
2. CR0598.3-6S3-RFI 2284.1 Mechanical Room Partition Change - $416.00.
RFI 2284.1 changed a 4-inch CMU wall to a G2 wall type partition, which
affected door frames providing access to the mechanical room that had
already been fabricated to accommodate a CMU wall type. The modified
scope of work consists of the material costs associated with the re-
fabrication of the Hollow Metal (HM) F2 Type single-leaf door frame for
Opening 01-0082 at the Mechanical Room 01-0279 located in Electrical
Room 01-0014, Ramp Level Area 28, per RFI 2284.1 response and sketches.
The approval of this Subcontractor Modification to MULE Engineering &
Construction, Inc. resolves all requests for costs and time resulting from
RFIs 2438 and 2284.1 scopes of work in GMP No. 6-S.3. Cost impacts of RFI 2438
for GMPs Nos. 6-S.1 and 6-S.2 will be submitted, respectively, via CR0597.1
and CR0597.2, for a future CCM approval. Cost impacts of RFI 2284.1 for GMP
Nos. 6-S.1 and 6-S.2 will be submitted, respectively, via CR0598.1 and
CR0598.2, for a future CCM approval. There are no cost impacts to GMP Nos.
6-S, 6-S.4, 6-S.5, and 6-S.6.
HPC has submitted documentation including the subcontractor's proposal to
support this request. An independent cost estimate is included. By approving
this request, the Owner does not waive its right to enforce the contract
requirements for other requests for cost or time.
The effect of this Subcontractor Modification for this project is as follows:
HPC to issue a subcontract modification to MULE
Engineering & Construction, Inc. in the lump sum
amount of: $ 1,108.00
Deduct from P1 Owner Contingency: $ (1,108.00)
Hensel Phelps Construction is committed to 20% MWBE and 4% LDB participation
for Construction Services. The subcontractor identified and committed to
participate on BP-S00145 (GMP No. 6-S.3) for this subcontract modification is
Minutes of the Construction Committee Meeting, June 23, 2020
Page 19 of 47
MULE Engineering & Construction, Inc. (MWBE/LDB). There is 100% LDB
participation associated with this modification.
Agenda Item Nos. 2-A, 2-B, 2-C, 2-D, 2-E, 2-F, 2-G, 2-H, 2-I, 2-J, 2-K, 2-L,
2-M, 2-N, 2-O, 2-P, 2-Q, 2-R, 2-S, 2-T, 2-U, 2-V, 2-W, 2-X, 2-Y, 2-Z, 2-AA,
2-BB, 2-DD, 2-EE, 2-FF, 2-GG, 2-HH, 2-II, 2-JJ, and 2-KK were considered in
one motion.
Upon motion of Mr. Patterson, second by Mr. Hunt, vote carried by roll-call,
with all votes yea, to approve Hensel Phelps Construction to issue a
Subcontractor Modification to MULE Engineering & Construction, Inc. on
BP-S00145, South Terminal C, Phase 1 - Airside Early Interiors (GMP No.
6-S.3), for the total lump sum amount of $1,108.00, with funding from General
Airport Revenue Bonds.
O. Subcontractor Modification for BP-S00146 (GMP No. 7-S) with CCK Construction Services, Inc. for CR0774.2-LST-RFIs 3457 and 3457.1 Footings for Switchgear
Room. Mr. Corthell presented the memorandum, requesting approval for Turner-
Kiewit Joint Venture (TKJV) to issue a Subcontract Modification on BP-S00146,
South Terminal C, Phase 1 - Landside Terminal, Structure and Enclosure (GMP
No. 7-S), at the Orlando International Airport, in the total amount of
$4,104.00 to CCK Construction Services, Inc. for CR0774.2-LST-RFIs 3457 and
3457.1 Footings for Switchgear Room. Bid Package 3.0.0 "Concrete" was
previously awarded within GMP No. 7-S to CCK Construction Services, Inc., CC
No. 20180313.010.
TKJV is proposing the following subcontract modification to CCK Construction
Services, Inc. in the total lump sum amount of $4,104.00 for CR0774.2-LST-RFIs
3457 and 3457.1 Footings for Switchgear Room. The modified scope of work
consists of necessary labor, material and equipment costs for the added
concrete footings for the CMU separator walls at the North and South Switchgear
Rooms, per RFI 3457 and 3457.1.
The approval of this subcontract modification to CCK Construction Services,
Inc. resolves all requests for costs and time associated with RFIs 3457 and
3457.1 in GMP No. 7-S. Cost impacts to GMP No. 9-S were approved at CC No.
20200225-02J. Cost impacts to GMP No. 7-S.1 will be submitted in a future CR.
Cost impacts to GMP No. 7-S.3 will be submitted for CCM review under CR0774.1.
There are no cost impacts to GMP Nos. 7-S.2 and 7-S.4.
TKJV has submitted documentation including the subcontractor's proposal to
substantiate this request. An independent cost estimate is included. By
approving this request, the Owner does not waive its right to enforce the
contract requirements for other requests for costs or time.
The effect of this Subcontractor Modification for this project is as follows:
TKJV to issue a subcontract modification to CCK
Construction Services, Inc. in the lump sum amount of: $ 4,104.00
Deduct from P1 Owner Contingency: $ (4,104.00)
Turner-Kiewit Joint Venture is committed to 20% MWBE and 4% LDB participation
for Construction Services. The subcontractor identified and committed to
participate on BP-S00146 (GMP No. 7-S) for this subcontract modification is
CCK Construction Services, Inc. (Non-MWBE/LDB/VBE). There is 86.4% MWBE
participation associated with this modification.
Agenda Item Nos. 2-A, 2-B, 2-C, 2-D, 2-E, 2-F, 2-G, 2-H, 2-I, 2-J, 2-K, 2-L,
2-M, 2-N, 2-O, 2-P, 2-Q, 2-R, 2-S, 2-T, 2-U, 2-V, 2-W, 2-X, 2-Y, 2-Z, 2-AA,
Minutes of the Construction Committee Meeting, June 23, 2020
Page 20 of 47
2-BB, 2-DD, 2-EE, 2-FF, 2-GG, 2-HH, 2-II, 2-JJ, and 2-KK were considered in
one motion.
Upon motion of Mr. Patterson, second by Mr. Hunt, vote carried by roll-call,
with all votes yea, to approve Turner-Kiewit Joint Venture to issue a
Subcontractor Modification to CCK Construction Services, Inc. on BP-S00146,
South Terminal C, Phase 1 - Landside Terminal, Structure and Enclosure (GMP
No. 7-S), for the total lump sum amount of $4,104.00, with funding from
Passenger Facility Charges and General Airport Revenue Bonds.
P. Subcontractor Modification for BP-S00146 (GMP No. 7-S) with Banker Steel Co., LLC for CR0568.2-7S-LST-RFI 2608-Future Canopy Foundation Anchor Bolt
Assemblies and Couplers. Mr. Corthell presented the memorandum, requesting
approval for Turner-Kiewit Joint Venture (TKJV) to issue a Subcontract
Modification on BP-S00146, South Terminal C, Phase 1 - Landside Terminal,
Structure and Enclosure (GMP No. 7-S), at the Orlando International Airport,
in the total amount of $37,866.00 to Banker Steel Co., LLC for CR0568.2-7S-
LST-RFI 2608-Future Canopy Foundation Anchor Bolt Assemblies and Couplers.
Package 5.0.0 "Structural Steel" was previously awarded within GMP No. 7-S to
Banker Steel Co., LLC, CC No. 20180313.010.
TKJV is proposing a subcontract modification to Banker Steel Co. LLC in the
total lump sum amount of $37,866.00 for CR0568.2-7S-LST-RFI 2608-Future Canopy
Foundation Anchor Bolt Assemblies and Couplers. RFI 2608 was submitted by TKJV
seeking direction for the conflicting information between the LSC bridge
drawings and the L5T building drawings pertaining to the limits of the work
scope as it related to the canopy foundations. EOR response to the RFI included
confirmation of the overall quantity of the canopy foundations and the scope
limit as identified on the LST Drawing SI.37.00. The RFI response states that
for future canopy foundations, The Middlesex Corporation is to install embedded
anchoring steel bars' rods with couplers within the inverted Tee Pier Cap
beams and Longitudinal C.I.P. Beams between N8.2 to N21 and S8.2 to S12 in
order to facilitate the construction of future canopy columns and canopy column
pedestals. The modified scope of work consists of all labor, material and
equipment costs associated with cutting and threading 128 Anchor Rods, 120
Flex coupling Nuts, and 120 plate washer, and galvanizing 400 anchor bolt
templates, per RFI 2608 anchor bolts assemblies and couplers for future
foundations scope of work.
The approval of this subcontract modification to Banker Steel Co., LLC resolves
all requests for cost and time associated with RFI 2608 and reconciles the
scope missed in CR 0568.1. CR0568.1 was submitted and approved CC No.
20200331.002F for all costs and time associated with RFIs 2608 and 2049 for
the Structural Steel Scope. There will be no further CRs associated with the
above referenced RFIs for any other GMPs.
TKJV has submitted documentation including the subcontractor's proposal to
support their request. An independent cost estimate is included. By approving
this request, the Owner does not waive its right to enforce the contract
requirements for other requests for cost or time.
The effect of this Subcontractor Modification for this project is as follows:
TKJV to issue a subcontract modification to Banker
Steel Co., LLC in the lump sum amount of: $ 37,866.00
Deduct from P1 CMAR Contingency: $ (37,866.00)
Turner-Kiewit Joint Venture is committed to 20% MWBE and 4% LDB participation
for Construction Services. The subcontractor identified and committed to
Minutes of the Construction Committee Meeting, June 23, 2020
Page 21 of 47
participate on BP-S00146 (GMP No. 7-S) for this subcontract modification is
Banker Steel Co., LLC (Non-MWBE/LDB/VBE). There is no small business
participation associated with this modification.
Agenda Item Nos. 2-A, 2-B, 2-C, 2-D, 2-E, 2-F, 2-G, 2-H, 2-I, 2-J, 2-K, 2-L,
2-M, 2-N, 2-O, 2-P, 2-Q, 2-R, 2-S, 2-T, 2-U, 2-V, 2-W, 2-X, 2-Y, 2-Z, 2-AA,
2-BB, 2-DD, 2-EE, 2-FF, 2-GG, 2-HH, 2-II, 2-JJ, and 2-KK were considered in
one motion.
Upon motion of Mr. Patterson, second by Mr. Hunt, vote carried by roll-call,
with all votes yea, to approve Turner-Kiewit Joint Venture to issue a
Subcontractor Modification to Banker Steel Co., LLC on BP-S00146, South
Terminal C, Phase 1 - Landside Terminal, Structure and Enclosure (GMP No.
7-S), for the total lump sum amount of $37,866.00, with funding from General
Airport Revenue Bonds.
Q. Subcontractor Modification for BP-S00146 (GMP No. 7-S) with Banker Steel Co., LLC for CR0705-LST-Bulletin 34 Structural Steel. Mr. Corthell presented the
memorandum, requesting approval for Turner-Kiewit Joint Venture (TKJV) to
issue a Subcontract Modification on BP-S00146, South Terminal C, Phase 1 -
Landside Terminal, Structure and Enclosure (GMP No. 7-S), at the Orlando
International Airport, in the total amount of $18,791.00 to Banker Steel Co.,
LLC for CR0705-LST-Bulletin 34 Structural Steel. Bid Package 5.0.0 "Structural
Steel" was previously awarded within GMP No. 7-S to Banker Steel Co. LLC, CC
No. 20180313.010.
TKJV is proposing a subcontract modification to Banker Steel Co. LLC in the
total lump sum amount of $18,791.00 for CR0705-LST-Bulletin 34 Structural
Steel. The modified scope of work includes all costs associated with added
steel access ladder including safety railing and railing at landing. It also
includes engineering and detailing costs for the added BHS access ladder, as
captured in LST Bulletin 34.
The approval of this subcontract modification to Banker Steel Co., LLC resolves
all requests for cost and time associated with LST Bulletin 34 scope of work
in GMP No. 7-S. Cost impacts to GMP No. 7-S.1 were submitted under CR0705.1.
There are no cost impacts to GMP Nos. 7-S.2, 7-S.3 and 7-S.4.
TKJV has submitted documentation including the subcontractor's proposal to
support their request. An independent cost estimate is included. By approving
this request, the Owner does not waive its right to enforce the contract
requirements for other requests for cost or time.
The effect of this Subcontractor Modification for this project is as follows:
TKJV to issue a subcontract modification to Banker
Steel Co., LLC in the lump sum amount of: $ 18,791.00
Deduct from P1 Owner Contingency: $ (18,791.00)
Turner-Kiewit Joint Venture is committed to 20% MWBE and 4% LDB participation
for Construction Services. The subcontractor identified and committed to
participate on BP-S00146 (GMP No. 7-S) for this subcontract modification is
Banker Steel Co., LLC (Non-MWBE/LDB/VBE). There is 73.8% MWBE participation
associated with this modification.
Agenda Item Nos. 2-A, 2-B, 2-C, 2-D, 2-E, 2-F, 2-G, 2-H, 2-I, 2-J, 2-K, 2-L,
2-M, 2-N, 2-O, 2-P, 2-Q, 2-R, 2-S, 2-T, 2-U, 2-V, 2-W, 2-X, 2-Y, 2-Z, 2-AA,
2-BB, 2-DD, 2-EE, 2-FF, 2-GG, 2-HH, 2-II, 2-JJ, and 2-KK were considered in
one motion.
Minutes of the Construction Committee Meeting, June 23, 2020
Page 22 of 47
Upon motion of Mr. Patterson, second by Mr. Hunt, vote carried by roll-call,
with all votes yea, to approve Turner-Kiewit Joint Venture to issue a
Subcontractor Modification to Banker Steel Co., LLC on BP-S00146, South
Terminal C, Phase 1 - Landside Terminal, Structure and Enclosure (GMP No.
7-S), for the total lump sum amount of $18,791.00, with funding from Passenger
Facility Charges and General Airport Revenue Bonds.
R. Subcontractor Modification for BP-S00146 (GMP No. 7-S) with Banker Steel Co., LLC for CR0930-LST-RFIs 2831, 2831.1, 2831.2, 2831.3, 3560, 3703 and 3979 -
Skylight Eave Design. Mr. Corthell presented the memorandum, requesting
approval for Turner-Kiewit Joint Venture (TKJV) to issue a Subcontract
Modification on BP-S00146, South Terminal C, Phase 1 - Landside Terminal,
Structure and Enclosure (GMP No. 7-S), at the Orlando International Airport,
in the total amount of $5,415.00 to Banker Steel Co., LLC for CR0930-LST-RFIs
2831, 2831.1, 2831.2, 2831.3, 3560, 3703, and 3979 - Skylight Eave Design.
Bid Package 5.0.0 "Structural Steel" was previously awarded within GMP No.
7-S to Banker Steel Co. LLC, CC No. 20180313.010.
TKJV is proposing a subcontract modification to Banker Steel Co., LLC in the
total lump sum amount of $5,415.00 for CR0930-LST-RFIs 2831, 2831.1, 2831.2,
2831.3, 3560, 3703 and 3979 - Skylight Eave Design. The modified scope of work
consists of necessary labor and material costs associated with field cut
decking and installation of decking with mechanical fasteners, per RFIs 2831,
2831.1, 2831.2, 3560, 3703, and 3979.
The approval of this subcontract modification to Banker Steel Co., LLC resolves
all requests for cost and time associated with RFIs 2831, 2831.1, 2831.2,
2831.3, 3560, 3703, and 3979 structural steel scope of work in GMP No. 7-S.
Cost impacts to GMP No. 7-S for the Curtain Wall scope will be submitted in a
future CR. Cost impacts to GMP No. 7-S.1 for the Metal Wall Panels will be
submitted for CCM review under CR0930.1. Cost impacts to GMP No. 7-S.1 for the
remainder scope will be submitted in a future CR. The There are no cost impacts
to GMP Nos. 7-S.2, 7-S.3 and 7-S.4.
TKJV has submitted documentation including the subcontractor's proposal to
support their request. An independent cost estimate is included. By approving
this request, the Owner does not waive its right to enforce the contract
requirements for other requests for cost or time.
The effect of this Subcontractor Modification for this project is as follows:
TKJV to issue a subcontract modification to Banker
Steel Co., LLC in the lump sum amount of: $ 5,415.00
Deduct from P1 Owner Contingency: $ (5,415.00)
Turner-Kiewit Joint Venture is committed to 20% MWBE and 4% LDB participation
for Construction Services. The subcontractor identified and committed to
participate on BP-S00146 (GMP No. 7-S) for this subcontract modification is
Banker Steel Co., LLC (Non-MWBE/LDB/VBE). There is no small business
participation associated with this modification.
Agenda Item Nos. 2-A, 2-B, 2-C, 2-D, 2-E, 2-F, 2-G, 2-H, 2-I, 2-J, 2-K, 2-L,
2-M, 2-N, 2-O, 2-P, 2-Q, 2-R, 2-S, 2-T, 2-U, 2-V, 2-W, 2-X, 2-Y, 2-Z, 2-AA,
2-BB, 2-DD, 2-EE, 2-FF, 2-GG, 2-HH, 2-II, 2-JJ, and 2-KK were considered in
one motion.
Upon motion of Mr. Patterson, second by Mr. Hunt, vote carried by roll-call,
with all votes yea, to approve Turner-Kiewit Joint Venture to issue a
Minutes of the Construction Committee Meeting, June 23, 2020
Page 23 of 47
Subcontractor Modification to Banker Steel Co., LLC on BP-S00146, South
Terminal C, Phase 1 - Landside Terminal, Structure and Enclosure (GMP No.
7-S), for the total lump sum amount of $5,415.00, with funding from Passenger
Facility Charges and General Airport Revenue Bonds.
S. Subcontract Modification for BP-S00147 (GMP No. 7-S.1) with Leesburg Concrete Company, Incorporated for CR0689-LST-RFI 2675 Precast Panel Color.
Mr. Corthell presented the memorandum, requesting approval for Turner-Kiewit
Joint Venture (TKJV) to issue a Subcontract Modification on BP-S00147, South
Terminal C, Phase 1 - Landside Terminal Remaining Structure and Systems (GMP
No. 7-S.1), at the Orlando International Airport, in the total amount of
$15,387.00 to Leesburg Concrete Company, Incorporated for CR0689-LST-RFI 2675
Precast Panel Color. Bid Package 3.3.0 "Precast Panels" was previously awarded
within GMP No. 7-S.1 to Leesburg Concrete Company, Incorporated, CC No.
20190319.02I.
TKJV is proposing a Subcontract Modification to Leesburg Concrete Company,
Incorporated in the total lump sum amount of $15,387.00 for CR0689-LST-RFI
2675 Precast Panel Color. The modified scope of work consists of the additional
labor and material costs associated with the revised precast panels concrete
mix design and color changes from gray to white, with added special aggregates
and color pigment, to match the Airside Concourse panels, as captured in
RFI 2675.
The approval of this Subcontract Modification to Leesburg Concrete Company,
Incorporated resolves all requests for cost and time arising from RFI 2675 in
GMP No. 7-S.1. There are no cost impacts to GMP Nos. 7-S, 7-S.2, 7-S.3 and
7-S.4.
TKJV has submitted documentation including the subcontractor's proposal to
support this request. An independent cost estimate is included. By approving
this request, the Owner does not waive its right to enforce the contract
requirements for other requests for cost or time.
The effect of this Subcontract Modification for this project is as follows:
TKJV to issue a subcontract modification to Leesburg
Concrete Company, Incorporated in the amount of: $ 15,387.00
Deduct from P1 Owner Contingency: $ (15,387.00)
Turner-Kiewit Joint Venture is committed to 20% MWBE and 4% LDB participation
for Construction Services. The subcontractor identified and committed to
participate on BP-S00147 (GMP No. 7-S.1) for this subcontract modification is
Leesburg Concrete Company, Incorporated (Non-MWBE/LDB/VBE). There is no small
business participation associated with this modification.
Agenda Item Nos. 2-A, 2-B, 2-C, 2-D, 2-E, 2-F, 2-G, 2-H, 2-I, 2-J, 2-K, 2-L,
2-M, 2-N, 2-O, 2-P, 2-Q, 2-R, 2-S, 2-T, 2-U, 2-V, 2-W, 2-X, 2-Y, 2-Z, 2-AA,
2-BB, 2-DD, 2-EE, 2-FF, 2-GG, 2-HH, 2-II, 2-JJ, and 2-KK were considered in
one motion.
Upon motion of Mr. Patterson, second by Mr. Hunt, vote carried by roll-call,
with all votes yea, to approve Turner-Kiewit Joint Venture to issue a
Subcontract Modification to Leesburg Concrete Company, Incorporated on
BP-S00147, South Terminal C, Phase 1 - Landside Terminal Remaining Structure
and Systems (GMP No. 7-S.1), for the total amount of $15,387.00, with funding
from Passenger Facility Charges and General Airport Revenue Bonds.
Minutes of the Construction Committee Meeting, June 23, 2020
Page 24 of 47
T. Subcontract Modification for BP-S00147 (GMP No. 7-S.1) with MSE2, Inc. dba Mader Southeast for CR0960-7S.1-LST-RFIs 2950-2950.2-Updated Louver Schedule.
Mr. Corthell presented the memorandum, requesting approval for Turner-Kiewit
Joint Venture (TKJV) to issue a Subcontract Modification on BP-S00147, South
Terminal C, Phase 1 - Landside Terminal Remaining Structure and Systems (GMP
No. 7-S.1), at the Orlando International Airport, in the total amount of
$12,185.00 to MSE2, Inc. dba Mader Southeast for CR0960-7S.1-LST-RFIs 2950-
2950.2-Updated Louver Schedule. Bid Package 9.1.0 "Drywall and Framing" was
previously awarded within GMP No. 7-S.1 to MSE2, Inc., CC No. 20181002.009.
TKJV is proposing a subcontract modification to MSE2, Inc. dba Mader Southeast
in the total lump sum amount of $12,185.00 for CR0960-7S.1-LST-RFIs 2950-
2950.2-Updated Louver Schedule. Meeting was held with TKJV, HNTB and Syska
Hennessy Group, Inc. on July 11, 2019, to coordinate louver sizes and
locations. It was concluded that the louver schedule needed to be updated to
capture all coordinated openings for the Terminal. Current architectural
drawings referred to mechanical drawings, and mechanical drawings only show
the free area with no indication of louver types or size opening. RFI 2950 was
generated asking that an updated louver schedule be provided, along with
corresponding architectural and mechanical drawings reflecting the updated
schedule. Design team response provided an updated louver schedule and updated
sketches indicating louver locations at the ground transportation and domestic
arrivals bridge levels. The modified scope of work consists of labor, material
and equipment costs for the additional framing of interior and exterior louvers
per RFI 2950.
The approval of these subcontract modifications to MSE2, Inc. dba Mader
Southeast resolves all requests for cost and time associated with RFIs 2950 -
2950.2 for GMP No. 7-S.1 Drywall and Framing Scope. CRs associated with the
Structural Steel scope in GMP No. 7-S and Masonry scope in GMP No. 7-S.1 are
forthcoming.
TKJV has submitted documentation including the subcontractor's proposal to
support their request. An independent cost estimate is included. By approving
this request, the Owner does not waive its right to enforce the contract
requirements for other requests for cost or time.
The effect of this Subcontract Modification for this project is as follows:
TKJV to issue a subcontract modification to MSE2,
Inc. dba Mader Southeast in the amount of: $ 12,185.00
Deduct from P1 Owner Contingency: $ (12,185.00)
Turner-Kiewit Joint Venture is committed to 20% MWBE and 4% LDB participation
for Construction Services. The subcontractor identified and committed to
participate on BP-S00147 (GMP No. 7-S.1) for this subcontract modification is
MSE2, Inc. dba Mader Southeast (Non-MWBE/LDB/VBE). There is 34.2% MWBE
participation associated with this modification.
Agenda Item Nos. 2-A, 2-B, 2-C, 2-D, 2-E, 2-F, 2-G, 2-H, 2-I, 2-J, 2-K, 2-L,
2-M, 2-N, 2-O, 2-P, 2-Q, 2-R, 2-S, 2-T, 2-U, 2-V, 2-W, 2-X, 2-Y, 2-Z, 2-AA,
2-BB, 2-DD, 2-EE, 2-FF, 2-GG, 2-HH, 2-II, 2-JJ, and 2-KK were considered in
one motion.
Upon motion of Mr. Patterson, second by Mr. Hunt, vote carried by roll-call,
with all votes yea, to approve Turner-Kiewit Joint Venture to issue a
Subcontract Modification to MSE2, Inc. dba Mader Southeast on BP-S00147, South
Terminal C, Phase 1 - Landside Terminal Remaining Structure and Systems (GMP
Minutes of the Construction Committee Meeting, June 23, 2020
Page 25 of 47
No. 7-S.1), for the total amount of $12,185.00, with funding from Passenger
Facility Charges and General Airport Revenue Bonds.
U. Subcontract Modification for BP-S00147 (GMP No. 7-S.1) with MSE2, Inc. dba Mader Southeast for CR0967.1-LST-RFI 3873 Size of Security Grill Pocket Room.
Mr. Corthell presented the memorandum, requesting approval for Turner-Kiewit
Joint Venture (TKJV) to issue a Subcontract Modification on BP-S00147, South
Terminal C, Phase 1 - Landside Terminal Remaining Structure and Systems (GMP
No. 7-S.1), at the Orlando International Airport, in the total amount of
$8,730.00 to MSE2, Inc. dba Mader Southeast for CR0967.1-LST-RFI 3873 Size of
Security Grill Pocket Room. Bid Package 9.1.0 "Drywall and Framing" was
previously awarded within GMP No. 7-S.1 to MSE2, Inc., CC No. 20181002.009.
TKJV is proposing a subcontract modification to MSE2, Inc. dba Mader Southeast
in the total lump sum amount of $8,730.00 for CR0967.1-LST-RFI 3873 Size of
Security Grill Pocket Room. The additional scope of work consists of necessary
labor, material and equipment costs for the added Wall Type G1 4-inch stud at
the Bi-Parting Security Grille Storage Pocket, north and south of Gridline
L10.5 in Area 6, as captured in RFI 3873.
The approval of this subcontract modification to MSE2, Inc. dba Mader Southeast
resolves all requests for cost and time associated with RFI 3873 scope of work
in GMP No. 7-S.1. Cost impacts to GMP No. 7-S will be submitted for CCM review
under CR0967. There are no cost impacts to GMP Nos. 7-S.2, 7-S.3 and 7-S.4.
TKJV has submitted documentation including the subcontractor's proposal to
support their request. An independent cost estimate is included. By approving
this request, the Owner does not waive its right to enforce the contract
requirements for other requests for cost or time.
The effect of this Subcontract Modification for this project is as follows:
TKJV to issue a subcontract modification to MSE2,
Inc. dba Mader Southeast in the amount of: $ 8,730.00
Deduct from P1 Owner Contingency: $ (8,730.00)
Turner-Kiewit Joint Venture is committed to 20% MWBE and 4% LDB participation
for Construction Services. The subcontractor identified and committed to
participate on BP-S00147 (GMP No. 7-S.1) for this subcontract modification is
MSE2, Inc. dba Mader Southeast (Non-MWBE/LDB/VBE). There is 7.4% MWBE
participation associated with this modification.
Agenda Item Nos. 2-A, 2-B, 2-C, 2-D, 2-E, 2-F, 2-G, 2-H, 2-I, 2-J, 2-K, 2-L,
2-M, 2-N, 2-O, 2-P, 2-Q, 2-R, 2-S, 2-T, 2-U, 2-V, 2-W, 2-X, 2-Y, 2-Z, 2-AA,
2-BB, 2-DD, 2-EE, 2-FF, 2-GG, 2-HH, 2-II, 2-JJ, and 2-KK were considered in
one motion.
Upon motion of Mr. Patterson, second by Mr. Hunt, vote carried by roll-call,
with all votes yea, to approve Turner-Kiewit Joint Venture to issue a
Subcontract Modification to MSE2, Inc. dba Mader Southeast on BP-S00147, South
Terminal C, Phase 1 - Landside Terminal Remaining Structure and Systems (GMP
No. 7-S.1), for the total lump sum amount of $8,730.00, with funding from
Passenger Facility Charges and General Airport Revenue Bonds.
V. Subcontract Modification for BP-S00147 (GMP No. 7-S.1) with Hommes Masonry, Inc., dba Toltec Construction for CR0978-LST-RFIs 3898 and 3898.1 Filled Cell
Location for BHS. Mr. Corthell presented the memorandum, requesting approval
for Turner-Kiewit Joint Venture (TKJV) to issue a Subcontract Modification on
BP-S00147, South Terminal C, Phase 1 - Landside Terminal Remaining Structure
Minutes of the Construction Committee Meeting, June 23, 2020
Page 26 of 47
and Systems (GMP No. 7-S.1), at the Orlando International Airport, in the
total amount of $6,162.00 to Hommes Masonry, Inc., dba Toltec Construction for
CR0978-LST-RFIs 3898 and 3898.1 Filled Cell Location for BHS. Bid Package
4.0.0 for Masonry was previously awarded within GMP No. 7-S.1 to Hommes Masonry
Inc. dba Toltec Construction, CC No. 20181002.09
TKJV is proposing the following subcontract modifications to Hommes Masonry,
Inc., dba Toltec Construction in the total lump sum amount of $6,162.00 for
CR0978-LST-RFIs 3898 and 3898.1 Filled Cell Location for BHS. RFI 3898.1
response added embeds to support the BHS connections into the CMU walls, which
requires full grouting of the CMU walls at all embed locations. The additional
scope of work consists of labor, material and equipment costs associated with
grouting CMU wall cells at BHS embed in Areas 1, 2 and 10, Level 1, as captured
in RFIs 3898 and 3898.1.
The approval of this subcontract modification to Hommes Masonry Inc. dba Toltec
Construction resolves all requests for cost and time associated with RFIs 3898
and 3898.1 in GMP No. 7-S.1. There are no cost impacts to GMP Nos. 7-S, 7-S.2,
7-S.3 and 7-S.4.
TKJV has submitted documentation including the subcontractor's proposal to
support their request. An independent cost estimate is included. By approving
this request, the Owner does not waive its right to enforce the contract
requirements for other requests for cost or time
The effect of this Subcontract Modification for this project is as follows:
TKJV to issue a subcontract modification to Hommes
Masonry, Inc., dba Toltec Construction in the amount of: $ 6,162.00
Deduct from P1 Owner Contingency: $ ( 6,162.00)
Turner-Kiewit Joint Venture is committed to 20% MWBE and 4% LDB participation
for Construction Services. The subcontractor identified and committed to
participate on BP-S00147 (GMP No. 7-S.1) for this subcontract modification is
Hommes Masonry Inc. dba Toltec Construction (MWBE). There is 100% MWBE
participation associated with this modification.
Agenda Item Nos. 2-A, 2-B, 2-C, 2-D, 2-E, 2-F, 2-G, 2-H, 2-I, 2-J, 2-K, 2-L,
2-M, 2-N, 2-O, 2-P, 2-Q, 2-R, 2-S, 2-T, 2-U, 2-V, 2-W, 2-X, 2-Y, 2-Z, 2-AA,
2-BB, 2-DD, 2-EE, 2-FF, 2-GG, 2-HH, 2-II, 2-JJ, and 2-KK were considered in
one motion.
Upon motion of Mr. Patterson, second by Mr. Hunt, vote carried by roll-call,
with all votes yea, to approve Turner-Kiewit Joint Venture to issue a
Subcontract Modification to Hommes Masonry, Inc., dba Toltec Construction on
BP-S00147, South Terminal C, Phase 1 - Landside Terminal Remaining Structure
and Systems (GMP No. 7-S.1), for the total lump sum amount of $6,162.00, with
funding from Passenger Facility Charges.
W. Subcontract Modifications for BP-S00147 (GMP No. 7-S.1) with P&A Roofing & Sheet Metal, Inc.; Crown Corr, Inc.; and MSE2, Inc. dba Mader Southeast; for
CR0289.1 - LST-Final Value Engineering Reconciliation of VE Item 8.4 Skylight
Edge Fascia Detail and VE Item 14.1 Replace SS-01 and SS-05 with Acrylic Finish
- Multiple RFIs. Mr. Corthell presented the memorandum, requesting approval
for Turner-Kiewit Joint Venture (TKJV) to issue a Subcontract Modification on
BP-S00147, South Terminal C, Phase 1 - Landside Terminal Remaining Structure
and Systems (GMP No. 7-S.1), at the Orlando International Airport, in the
total amount of $1,347,795.00 to P&A Roofing & Sheet Metal, Inc.; Crown Corr,
Inc.; and MSE2, Inc. dba Mader Southeast; for CR0289.1 - LST-Final Value
Minutes of the Construction Committee Meeting, June 23, 2020
Page 27 of 47
Engineering Reconciliation of VE Item 8.4 Skylight Edge Fascia Detail and VE
Item 14.1 Replace SS-01 and SS-05 with Acrylic Finish - Multiple RFIs. Bid
Package 7.2.0 "Roofing", Bid Package 7.1.0 "Metal Wall Panels", and Bid Package
9.1.0 "Drywall and Framing" were previously awarded within GMP No. 7-S.1 to,
respectively, P&A Roofing & Sheet Metal, Inc.; Crown Corr, Inc.; and MSE2,
Inc. dba Mader Southeast; CC No. 20181002.009.
TKJV is proposing subcontract modifications for CR0289.1-LST-VE Item 8.4
"Skylight Edge Fascia Detail - Skylight Eave - Removing Top MCM Panel from
Skylight Eave and Replace with PVC Membrane - Multiple RFIs". The scope of
work consists of all costs associated with Value Engineering (VE) Item 8.4,
which includes work at Column Line L2 - L17, along both sides of the skylight
at the eaves. Roofing and panel revisions include all work associated with
RFIs 2058 and 2058.1, and removal of metal panel at the top of the eave and
replacement with a PVC roofing system and flashing to match panel the Centria
panel at the soffit, which satisfies the design intent for the approved PVC
roofing system to extend at the top panel from L17 - L19.2 for transition to
the prow. TKJV's proposal request includes subcontract modifications to:
P&A Roofing & Sheet Metal, Inc., in the lump sum amount of $200,547.00;
Crown Corr, Inc. in the deductive lump sum amount of ($199,727.00) for
a total realized VE proposal value of ($499,727.00), which includes the
top of eave panel credit and the added cost for the side panel revisions;
and,
MSE2, Inc. dba Mader Southeast in the lump sum amount of $21,000.00 for
scope not realized as part of the VE effort. Note that there were no
modifications to the light gage framing based on the RFI responses.
TKJV is proposing subcontract modifications for CR0289.1-LST- VE Item 14.1
"Replace SS-01 and SS-05 with Acrylic Finish - Multiple RFIs". The scope of
work consists of all costs associated with Value Engineering (VE) Item 14.1,
which includes work to replace the SS-01 and SS-05 exterior soffit systems
with acrylic finish on sheathing. The scope of the revisions and the components
of the acrylic system are identified in RFIs 1780, 1780.1 and 1780.2. TKJV's
proposal request includes subcontract modifications to:
Crown Corr, Inc. in the lump sum amount of $754,475.00 for a total
realized VE proposal value of ($1,150,525.00); and,
MSE2, Inc. dba Mader Southeast in the lump sum amount of $571,500.00 for
the additional acrylic finish that is currently identified in the MSE2,
Inc. dba Mader Southeast agreement as an allowance.
CR0289.1 - LST-Final Value Engineering Reconciliation of VE Item 8.4 Skylight
Edge Fascia Detail and VE Item 14.1 Replace SS-01 and SS-05 with Acrylic Finish
- Multiple RFIs resolves all requests for cost and time associated with the
final design incorporation via RFI or Bulletin and subsequent subcontractor
pricing for CM@R proposed Value Engineering (VE) Items 8.4 and 14.1, as well
as RFIs 1780, 1780.1, 1780.2, 2058, 2058.1 and 2077 under GMP No. 7-S.1
Associated Value Engineering (VE) savings are recognized in the approved GMP
No. 7-S.1 proposal.
The final design scope resulted in only the BOH SS05 flat ceilings being
revised to the acrylic finish, now identified as Ceiling Type SS05a. The
vertical soffits were not revised as part of the final VE 14.1 design.
Minutes of the Construction Committee Meeting, June 23, 2020
Page 28 of 47
A future CR0289.2 will be submitted to resolve Value Engineering (VE) Item 16
for the North and South Elevations, and it will include RFIs 1357, 1357.1,
1357.2, 1357.3, and 1357.4. By approving this request, the Owner does not
waive its right to enforce the contract requirements for other requests for
cost or time.
The effect of these Subcontract Modifications for this project is as follows:
Value Engineering Item 8.4 Skylight Edge Fascia Detail
TKJV to issue a subcontract modification to P&A
Roofing & Sheet Metal, Inc. in the amount of: $ 200,547.00
Deduct from Owner Contingency: $ (200,547.00)
Initial Crown Corr, Inc. Subcontract Modification
via CR0289 (CC. No. 20190219.002L)
$ (300,000.00)
Current TKJV request to issue a Subcontract
Modification to Crown Corr, Inc. in the deductive
lump sum amount of:
$ (199,727.00)
Total Crown Corr, Inc. Proposal for VE Item 8.4 (SOV
Line Item 24):
$ (499.727.00)
Add to Owner Contingency: $ 199,727.00
MSE2, Inc. dba Mader Southeast Initial Subcontract
Modification via CR0289 (CC. No. 20190219.002L) $ (21,000.00)
TKJV to issue a subcontract modification to MSE2,
Inc. dba Mader Southeast in the total lump sum
amount of: $ 21,000.00
Deduct from Owner Contingency: $ (21,000.00)
Value Engineering Item 14.1 Replace SS-01 and SS-05 with Acrylic Finish
Initial Crown Corr, Inc. Subcontract Modification
via CR0289 (CC. No. 20190219.002L): $ (1,905,000.00)
Current TKJV request to issue a Subcontract
Modification to Crown Corr, Inc. in the total lump
sum amount of: $ 754,475.00
Total Crown Corr, Inc. Proposal for VE Item 14.1
(SOV Line Item 29): $ (1,150,525.00)
Deduct from Owner Contingency: $ (754,475.00)
TKJV to issue a Subcontract Modification to MSE2,
Inc. dba Mader Southeast in the total lump sum
amount of: $ 571,500.00
Deduct from GMP No. 7-S.1 Allowance SOV Line Item 29: $ (571,500.00)
Remaining Balance for GMP No. 7-S.1 Allowance SOV
Line Item 29: $ 0.00
Turner-Kiewit Joint Venture is committed to 20% MWBE and 4% LDB participation
for Construction Services. The subcontractors identified and committed to
participate on BP-S00147 (GMP No. 7-S.1) for these subcontract modifications
are P&A Roofing & Sheet Metal, Inc. (Non-MWBE/LDB/VBE); Crown Corr, Inc. (Non-
MWBE/LDB/VBE); and MSE2, Inc. dba Mader Southeast (Non-MWBE/LDB/VBE). There
is no small business participation associated with the proposed modifications.
Agenda Item Nos. 2-A, 2-B, 2-C, 2-D, 2-E, 2-F, 2-G, 2-H, 2-I, 2-J, 2-K, 2-L,
2-M, 2-N, 2-O, 2-P, 2-Q, 2-R, 2-S, 2-T, 2-U, 2-V, 2-W, 2-X, 2-Y, 2-Z, 2-AA,
2-BB, 2-DD, 2-EE, 2-FF, 2-GG, 2-HH, 2-II, 2-JJ, and 2-KK were considered in
one motion.
Minutes of the Construction Committee Meeting, June 23, 2020
Page 29 of 47
Upon motion of Mr. Patterson, second by Mr. Hunt, vote carried by roll-call,
with all votes yea, to approve Turner-Kiewit Joint Venture to issue Subcontract
Modifications on BP-S00147, South Terminal C, Phase 1 - Landside Terminal
Remaining Structure and Systems (GMP No. 7-S.1), for the total amount of
$1,347,795.00, which includes the lump sum amount of $200,547.00 to P&A Roofing
& Sheet Metal, Inc.; the lump sum amount of $554,748.00 to Crown Corr, Inc.;
and the lump sum amount of $592,500.00 to MSE2, Inc. dba Mader Southeast; with
funding from Passenger Facility Charges and General Airport Revenue Bonds.
X. Subcontract Modification for BP-S00147 (GMP No. 7-S.1) with Hommes Masonry Inc. dba Toltec Construction for CR0493-LST-RFIs 2095 and 2095.1-CMU Bond Beam
Elevator Entryway and Bracing. Mr. Corthell presented the memorandum,
requesting approval for Turner-Kiewit Joint Venture (TKJV) to issue a
Subcontract Modification on BP-S00147, South Terminal C, Phase 1 - Landside
Terminal Remaining Structure and Systems (GMP No. 7-S.1), at the Orlando
International Airport, in the total amount of $37,604.00 to Hommes Masonry
Inc. dba Toltec Construction for CR0493-LST-RFIs 2095 and 2095.1-CMU Bond Beam
Elevator Entryway and Bracing. Bid Package 4.0.0 for Masonry was previously
awarded within GMP No. 7-S.1 to Hommes Masonry Inc. dba Toltec Construction,
CC No. 20181002.09
TKJV is proposing a subcontract modification to Hommes Masonry Inc. dba Toltec
Construction in the total lump sum amount of $37,604.00 for CR0493-LST-RFIs
2095 and 2095.1-CMU Bond Beam Elevator Entryway and Bracing. The modified
scope of work consists of all labor, material and equipment associated with
the installation of 8" reinforced bond beam across the entire course of CMU
back of house elevator thresholds per RFIs 2095 and 2095.1, CMU Bond Beam
Elevator Entryway and Bracing.
Approval of this subcontract modification to Hommes Masonry Inc. dba Toltec
Construction resolves all requests for cost and time associated with RFIs 2095
and 2095.1 for GMP No. 7-S.1 Concrete Masonry Unit Scope. CRs are forthcoming
for GMP No. 7-S Structural Steel scope and GMP No. 7-S.1 Drywall scope. There
are no cost impacts to GMP Nos. 7-S.2, 7-S.3 and 7-S.4.
TKJV has submitted documentation including the subcontractor's proposal to
support their request. An independent cost estimate is included. By approving
this request, the Owner does not waive its right to enforce the contract
requirements for other requests for cost or time.
The effect of this Subcontract Modification for this project is as follows:
TKJV to issue a subcontract modification to Hommes
Masonry Inc. dba Toltec Construction in the amount of: $ 37,604.00
Deduct from P1 CMAR Contingency: $ (37,604.00)
Turner-Kiewit Joint Venture is committed to 20% MWBE and 4% LDB participation
for Construction Services. The subcontractor identified and committed to
participate on BP-S00147 (GMP No. 7-S.1) for this subcontract modification is
Hommes Masonry Inc. dba Toltec Construction (MWBE). There is 100% MWBE
participation associated with this modification.
Agenda Item Nos. 2-A, 2-B, 2-C, 2-D, 2-E, 2-F, 2-G, 2-H, 2-I, 2-J, 2-K, 2-L,
2-M, 2-N, 2-O, 2-P, 2-Q, 2-R, 2-S, 2-T, 2-U, 2-V, 2-W, 2-X, 2-Y, 2-Z, 2-AA,
2-BB, 2-DD, 2-EE, 2-FF, 2-GG, 2-HH, 2-II, 2-JJ, and 2-KK were considered in
one motion.
Upon motion of Mr. Patterson, second by Mr. Hunt, vote carried by roll-call,
with all votes yea, to approve Turner-Kiewit Joint Venture to issue a
Minutes of the Construction Committee Meeting, June 23, 2020
Page 30 of 47
Subcontract Modification to Hommes Masonry Inc. dba Toltec Construction on
BP-S00147, South Terminal C, Phase 1 - Landside Terminal Remaining Structure
and Systems (GMP No. 7-S.1), for the total lump sum amount of $37,604.00, with
funding from General Airport Revenue Bonds.
Y. Subcontract Modification for BP-S00147 (GMP No. 7-S.1) with Hommes Masonry Inc. dba Toltec Construction for CR0810-LST-RFI 3581-Moved CMU Mechanical
Shaft Wall. Mr. Corthell presented the memorandum, requesting approval for
Turner-Kiewit Joint Venture (TKJV) to issue a Subcontract Modification on BP-
S00147, South Terminal C, Phase 1 - Landside Terminal Remaining Structure and
Systems (GMP No. 7-S.1), at the Orlando International Airport, in the total
amount of $761.00 to Hommes Masonry Inc. dba Toltec Construction for CR0810-
LST-RFI 3581-Moved CMU Mechanical Shaft Wall. Bid Packages 4.0.0 "Masonry"
and 9.1.0 "Drywall & Framing" were previously awarded within GMP No. 7-S.1 to,
respectively, Hommes Masonry Inc. dba Toltec Construction CC No. 20181002.09
TKJV is proposing a subcontract modification to Hommes Masonry Inc. dba Toltec
Construction in the total lump sum amount of $761.00 for CR0810-LST-RFI 3581-
Moved CMU Mechanical Shaft Wall. RFI 3581 confirmed a return to original
position of a wall at west side of prefabricated Electrical Room 02-0025 to
avoid rework to construction already completed, but at the same time confirmed
that the CMU wall of mechanical shaft needed to be relocated to the west to
assure it is sitting atop concrete wall below, and this direction resulted in
an enlargement of mechanical shaft size. The modified scope of work consists
of all labor, material and equipment costs associated with installing 8" CMU
mechanical shaft wall per the wall shift by 8" westward, as captured in RFI
3581 response.
Approval of this subcontract modifications to Hommes Masonry Inc. dba Toltec
Construction resolves all requests for cost and time associated with RFI 3581
for the Masonry scope in GMP No. 7-S.1. CRs are forthcoming for the following
scopes: GMP No. 7-S Structure; GMP No. 7-S.1 Drywall, Doors and Hardware; and,
GMP No. 7-S.3 Electrical. There will be no additional CRs associated with RFI
3581 other than the ones listed above.
TKJV has submitted documentation including the subcontractor's proposal to
support their request. An independent cost estimate is included. By approving
this request, the Owner does not waive its right to enforce the contract
requirements for other requests for cost or time.
The effect of this Subcontract Modification for this project is as follows:
TKJV to issue a subcontract modification to Hommes
Masonry Inc. dba Toltec Construction in the amount of: $ 761.00
Deduct from P1 CMAR Contingency: $ (761.00)
Turner-Kiewit Joint Venture is committed to 20% MWBE and 4% LDB participation
for Construction Services. The subcontractor identified and committed to
participate on BP-S00147 (GMP No. 7-S.1) for this subcontract modification is
Hommes Masonry Inc. dba Toltec Construction (MWBE). There is 100% MWBE
participation associated with this modification.
Agenda Item Nos. 2-A, 2-B, 2-C, 2-D, 2-E, 2-F, 2-G, 2-H, 2-I, 2-J, 2-K, 2-L,
2-M, 2-N, 2-O, 2-P, 2-Q, 2-R, 2-S, 2-T, 2-U, 2-V, 2-W, 2-X, 2-Y, 2-Z, 2-AA,
2-BB, 2-DD, 2-EE, 2-FF, 2-GG, 2-HH, 2-II, 2-JJ, and 2-KK were considered in
one motion.
Upon motion of Mr. Patterson, second by Mr. Hunt, vote carried by roll-call,
with all votes yea, to approve Turner-Kiewit Joint Venture to issue a
Minutes of the Construction Committee Meeting, June 23, 2020
Page 31 of 47
Subcontract Modification to Hommes Masonry Inc. dba Toltec Construction on
BP-S00147, South Terminal C, Phase 1 - Landside Terminal Remaining Structure
and Systems (GMP No. 7-S.1), for the total lump sum amount of $761.00, with
funding from Passenger Facility Charges and General Airport Revenue Bonds.
Z. Subcontract Modification for BP-S00150 (GMP No. 9-S) with Gulf Mechanical Contractors, LLC for CR0491.3-PKG-RFIs 1937, 1937.2 and 2444-Relocation of
Escalator Sump-Plumbing. Mr. Corthell presented the memorandum, requesting
approval for Turner-Kiewit Joint Venture (TKJV) to issue a Subcontract
Modification on BP-S00150, South Terminal C, Phase 1, Parking Facility - Phase
1 (GMP No. 9-S), at the Orlando International Airport, in the total amount of
$14,169.00 to Gulf Mechanical Contractors, LLC for CR0491.3-PKG-RFIs 1937,
1937.2 and 2444-Relocation of Escalator Sump-Plumbing. Bid Package 22.0.0
"Plumbing" was previously awarded within GMP No. 9-S to Gulf Mechanical
Contractors, LLC CC No. 20171010.16.
TKJV is proposing a subcontract modification to Gulf Mechanical Contractors,
LLC, in the total lump sum amount of $14,169.00 for CR0491.3-PKG-RFIs 1937,
1937.2 and 2444-Relocation of Escalator Sump-Plumbing. The modified scope of
work captured in this request consists of all material, labor and equipment
costs associated with excavating, dewatering, laying gravel base, installing
pit and backfill per RFIs 1937, 1937.2 and 2444 revisions.
The approval of this subcontract modification resolves all requests for cost
and time associated with PKG RFIs 1937, 1937.2 and 2444 for the plumbing scope.
The followings are all the remaining CRs and trades associated with these RFIs
that have been or will be submitted:
CR0491 Electrical and Fire Protection scope in GMP No. 9-S. Approved (CC
No. 20191217.03M).
CR0491.1 Door Frames and Hardware scope. Approved (CC No. 20191217.03M).
CR0491.2 Masonry scope in GMP No. 9-S.1. Voided.
CR0815 Masonry Final Negotiation in GMP No. 9-S.1. Approved (CC No.
20200310.03T).
TKJV has submitted documentation including the subcontractor's proposal to
support their request. An independent cost estimate is included.
By approving this request, the Owner does not waive its right to enforce the
contract requirements for other requests for cost or time.
The effect of this Subcontract Modification for this project is as follows:
TKJV to issue subcontract modification to Gulf
Mechanical Contractors, LLC in the lump sum amount of: $ 14,169.00
Deduct from P1 Owner Contingency: $ (14,169.00)
Turner-Kiewit Joint Venture is committed to 20% MWBE and 4% LDB participation
for Construction Services. The subcontractor identified and committed to
participate on BP-S00150 (GMP No. 9-S) for this subcontract modification is
Gulf Mechanical Contractors, LLC (Non-MWBE/LDB/VBE). There is no small business
participation associated with this modification.
Agenda Item Nos. 2-A, 2-B, 2-C, 2-D, 2-E, 2-F, 2-G, 2-H, 2-I, 2-J, 2-K, 2-L,
2-M, 2-N, 2-O, 2-P, 2-Q, 2-R, 2-S, 2-T, 2-U, 2-V, 2-W, 2-X, 2-Y, 2-Z, 2-AA,
2-BB, 2-DD, 2-EE, 2-FF, 2-GG, 2-HH, 2-II, 2-JJ, and 2-KK were considered in
one motion.
Minutes of the Construction Committee Meeting, June 23, 2020
Page 32 of 47
Upon motion of Mr. Patterson, second by Mr. Hunt, vote carried by roll-call,
with all votes yea, to approve Turner-Kiewit Joint Venture to issue a
Subcontract Modification to Gulf Mechanical Contractors, LLC on BP-S00150,
South Terminal C, Phase 1 - Parking Facility - Phase 1 (GMP No. 9-S), for the
total lump sum amount of $14,169.00, with funding from Customer Facility
Charges and General Airport Revenue Bonds.
AA. Subcontract Modification for BP-S00150 (GMP No. 9-S) with Gulf Mechanical
Contractors, LLC for CR0718.2-PKG-RFIs-2801.2 and 2801.3 - Elevator Machine
Room Level 7-Plumbing Changes. Mr. Corthell presented the memorandum,
requesting approval for Turner-Kiewit Joint Venture (TKJV) to issue a
Subcontract Modification on BP-S00150, South Terminal C, Phase 1, Parking
Facility - Phase 1 (GMP No. 9-S), at the Orlando International Airport, in the
total amount of $2,421.00 to Gulf Mechanical Contractors, LLC for CR0718.2-
PKG-RFIS-2801.2 and 2801.3 - Elevator Machine Room Level 7-Plumbing Changes.
Bid Package 22.0.0 "Plumbing" was previously awarded within GMP No. 9-S to
Gulf Mechanical Contractors, LLC CC No. 20171010.16.
TKJV is proposing a subcontract modification to Gulf Mechanical Contractors,
LLC, in the total lump sum amount of $2,421.00 for CR0718.2-PKG-RFIs-2801.2
and 2801.3 - Elevator Machine Room Level 7-Plumbing Changes. The modified
scope of work captured in this request consists of all material, labor and
equipment costs associated with relocating roof storm drains, condensate hub
drain and hose bib per RFI 2801.2 and 2801.3 responses.
The approval of this subcontract modification resolves all requests for cost
and time associated with PKG RFIs 2801.2 and 2801.3 for the plumbing scope.
The following are all the remaining CRs associated with these RFIs that have
been or will be submitted:
CR0718.Electrical Scope (Approved), CC No. 20200225.002K
CR0718.1-Drywall Scope (Approved), CC No. 20200310.003R
CR0718.3-Doors, Frames and Hardware Scope (Approved), CC No.
20200303.002Y
TKJV has submitted documentation including the subcontractor's proposal to
support their request. An independent cost estimate is included.
By approving this request, the Owner does not waive its right to enforce the
contract requirements for other requests for cost or time.
The effect of this Subcontract Modification for this project is as follows:
TKJV to issue subcontract modification to Gulf
Mechanical Contractors, LLC in the lump sum amount of: $ 2,421.00
Deduct from P1 Owner Contingency: $ (2,421.00)
Turner-Kiewit Joint Venture is committed to 20% MWBE and 4% LDB participation
for Construction Services. The subcontractor identified and committed to
participate on BP-S00150 (GMP No. 9-S) for this subcontract modification is
Gulf Mechanical Contractors, LLC (Non-MWBE/LDB/VBE). There is no small business
participation associated with this modification.
Agenda Item Nos. 2-A, 2-B, 2-C, 2-D, 2-E, 2-F, 2-G, 2-H, 2-I, 2-J, 2-K, 2-L,
2-M, 2-N, 2-O, 2-P, 2-Q, 2-R, 2-S, 2-T, 2-U, 2-V, 2-W, 2-X, 2-Y, 2-Z, 2-AA,
2-BB, 2-DD, 2-EE, 2-FF, 2-GG, 2-HH, 2-II, 2-JJ, and 2-KK were considered in
one motion.
Minutes of the Construction Committee Meeting, June 23, 2020
Page 33 of 47
Upon motion of Mr. Patterson, second by Mr. Hunt, vote carried by roll-call,
with all votes yea, to approve Turner-Kiewit Joint Venture to issue a
Subcontract Modification to Gulf Mechanical Contractors, LLC on BP-S00150,
South Terminal C, Phase 1 - Parking Facility - Phase 1 (GMP No. 9-S), for the
total lump sum amount of $2,421.00, with funding from Customer Facility Charges
and General Airport Revenue Bonds.
BB. Subcontract Award for BP-S00150 (GMP No. 9-S) with Percopo Coatings Company,
LLC for CR1042-9S-PKG-Canopy Painting -Award. Mr. Corthell presented the
memorandum, requesting approval for Turner-Kiewit Joint Venture (TKJV) to
issue a Subcontract Award on BP-S00150, South Terminal C, Phase 1, Parking
Facility - Phase 1 (GMP No. 9-S), at the Orlando International Airport, in the
total amount of $174,635.00 to Percopo Coatings Company, LLC for CR1042-9S-
PKG-Canopy Painting -Award. GMP No. 9-S was previously awarded to Turner-
Kiewit Joint Venture via Addendum No. 7, CC No. 20171010.016.
TKJV is proposing a subcontract award to Percopo Coatings Company, LLC in the
total lump sum amount of $174,635.00 for BP 9.7.0 Parking Garage "Canopy
Painting" scope of work. The subcontract will include all labor, material and
equipment as described on Percopo Coatings Company, LLC proposal, dated
February 19, 2020, TKJV's scope of work, dated April 9, 2020, and documents
through PKG Bulletin 11 and CWS Bulletin 16. The scope of work includes the
painting of the PKG Canopies including the exposed structure, underside of the
decks, and columns, of both the Upper Canopy (Level 6) and Lower Canopy
(Level 4).
The approval of this subcontract Award to Percopo Coatings Company, LLC
resolves all requests for cost and time associated with BP 9.7.0 PKG Canopy
Painting award.
TKJV has submitted documentation including the subcontractor's proposal to
support their request. An independent cost estimate is included. By approving
this request, the Owner does not waive its right to enforce the contract
requirements for other requests for cost or time.
The effect of this Subcontract Award for this project is as follows:
TKJV to issue subcontract award to Percopo Coatings
Company, LLC in the lump sum amount of: $ 174,635.00
Current GMP Line Item 13 balance: $ 361,305.00
Deduct from GMP Line Item 13: $ (174,635.00)
Add to CWE CM@R Contingency: $ 186,670.00
Turner-Kiewit Joint Venture is committed to 20% MWBE and 4% LDB participation
for Construction Services. The subcontractor identified and committed to
participate on BP-S00150 (GMP No. 9-S) for this subcontract modification is
Percopo Coatings Company, LLC (MWBE). There is 96% MWBE and 4% LDB
participation associated with this award.
Vice Chair Sharman asked if there is sufficient budget for this request
considering any potential reductions. Mr. Corthell answered yes, that there
is a line-item for the request.
Agenda Item Nos. 2-A, 2-B, 2-C, 2-D, 2-E, 2-F, 2-G, 2-H, 2-I, 2-J, 2-K, 2-L,
2-M, 2-N, 2-O, 2-P, 2-Q, 2-R, 2-S, 2-T, 2-U, 2-V, 2-W, 2-X, 2-Y, 2-Z, 2-AA,
2-BB, 2-DD, 2-EE, 2-FF, 2-GG, 2-HH, 2-II, 2-JJ, and 2-KK were considered in
one motion.
Minutes of the Construction Committee Meeting, June 23, 2020
Page 34 of 47
Upon motion of Mr. Patterson, second by Mr. Hunt, vote carried by roll-call,
with all votes yea, to approve Turner-Kiewit Joint Venture to issue a
Subcontract Award to Percopo Coatings Company, LLC on BP-S00150, South Terminal
C, Phase 1 - Parking Facility - Phase 1 (GMP No. 9-S), for the total lump sum
amount of $174,635.00, with funding from Customer Facility Charges.
CC. Subcontract Modification for BP-S00156 (GMP No. 14-S) with Kirlin Florida, LLC
for CR0767.1-CEP-CWS Bulletin No. 17-lnsulation Thickness for chilled Water
Piping. This item was deferred.
DD. Subcontractor Modifications for BP-S00168 (GMP No. 6-S.4) with M.C. Dean, Inc.
for CR0599.1-6S4-RFI 2440 Fire Alarm Relays for Physical Access Control System
(PACS) Panels. Mr. Corthell presented the memorandum, requesting approval for
Hensel Phelps Construction (HPC) to issue Subcontract Modifications on BP-
S00168, South Terminal C, Phase 1 - Interior Finishes and Specialties (GMP No.
6-S.4), at the Orlando International Airport, in the total amount of $844.00
to M.C. Dean, Inc., for CR0599.1-6S4-RFI 2440 Fire Alarm Relays for Physical
Access Control System (PACS) Panels. Bid Package for BP-S168 27.01 "Airside
Concourse Low Voltage Systems" has been previously awarded within GMP No.
6-S.4 to M. C. Dean, Inc., CC No. 20181002.010.
HPC is requesting to issue a Subcontractor Modification to M.C. Dean, Inc. in
the total Lump Sum amount of $844.00 for CR0599.1-6S4-RFI 2440 Fire Alarm
Relays for Physical Access Control System (PACS) Panels. The modified scope
of work consists of the costs associated with the added Fire Alarm Relay Type
AR5 at GOAA IDF Room 02.3385, per RFI 2440 response and sketches.
The approval of this Subcontract Modification to M.C. Dean, Inc. resolves all
requests for cost and time resulting from RFI 2440 in GMP No. 6-S.4. Cost
impact of RFI 2440 to GMP No. 6-S.6 will be submitted via CR0599.2 for a future
CCM approval.
HPC has submitted documentation including the subcontractor's proposal to
support this request. An independent cost estimate is included. By approving
this request, the Owner does not waive its right to enforce the contract
requirements for other requests for cost or time.
The effect of this Subcontractor Modification for this project is as follows:
HPC to issue a subcontract modification to M.C. Dean, Inc.
in the lump sum amount of: $ 844.00
Deduct from P1 Owner Contingency $ (844.00)
Hensel Phelps Construction is committed to 20% MWBE and 4% LDB participation
for Construction Services. The subcontractor identified and committed to
participate on BP-S00168 (GMP No. 6-S.4) for this subcontract modification is
M.C. Dean, Inc. (Non-MWBE/LDB/VBE). There is no small business participation
associated with this modification.
Agenda Item Nos. 2-A, 2-B, 2-C, 2-D, 2-E, 2-F, 2-G, 2-H, 2-I, 2-J, 2-K, 2-L,
2-M, 2-N, 2-O, 2-P, 2-Q, 2-R, 2-S, 2-T, 2-U, 2-V, 2-W, 2-X, 2-Y, 2-Z, 2-AA,
2-BB, 2-DD, 2-EE, 2-FF, 2-GG, 2-HH, 2-II, 2-JJ, and 2-KK were considered in
one motion.
Upon motion of Mr. Patterson, second by Mr. Hunt, vote carried by roll-call,
with all votes yea, to approve Hensel Phelps Construction to issue
Subcontractor Modifications to M.C. Dean, Inc., on BP-S00168, South Terminal
C, Phase 1 - Interior Finishes and Specialties (GMP No. 6-S.4), for the total
Minutes of the Construction Committee Meeting, June 23, 2020
Page 35 of 47
lump sum amount of $844.00, with funding from Passenger Facility Charges and
General Airport Revenue Bonds.
EE. Subcontractor Modifications for BP-S00168 (GMP No. 6-S.4) with Empire Office,
Inc.; Percopo Coatings Company, LLC; SkyBuilders USA, LLC; and M.C. Dean,
Inc.; for CR0387-6S4-ASC Bulletin 028 Updates. Mr. Corthell presented the
memorandum, requesting approval for Hensel Phelps Construction (HPC) to issue
Subcontract Modifications on BP-S00168, South Terminal C, Phase 1 - Interior
Finishes and Specialties (GMP No. 6-S.4), at the Orlando International Airport,
in the total deductive amount of ($128,891.00) to Empire Office, Inc.; Percopo
Coatings Company, LLC; SkyBuilders USA, LLC; and M.C. Dean, Inc.; for CR0387-
6S4-ASC Bulletin 028 Updates. Bid Package for BP-S168 09.08 "Tile", 09.11
"Painting", 10.01 "Interior Specialties", and 27.01 "ASC Low Voltage Systems"
were previously awarded within the GMP No. 6-S.4, respectively, to Empire
Office, Inc.; Percopo Coatings Company, LLC; SkyBuilders USA, LLC; and M.C.
Dean, Inc.; CC Reference No. 20181002.010.
HPC is proposing the following Subcontractors Modifications to;
1. Empire Office, Inc. in the deductive Lump Sum amount of ($15,303.00), for the deleted porcelain tiles, ceramic tiles and waterproofing at
restrooms and plumbing chases in tenant spaces, Areas 27, 28 and 29;
2. Percopo Coatings Company, LLC in the deductive Lump Sum amount of
($2,181.00), for the reduction of the painting works at restroom
ceilings, doors and frames in tenant spaces, Areas 27, 28 and 29;
3. SkyBuilders USA, LLC in the deductive Lump Sum amount of ($15,385.00), for the reduction of the Interior Specialties items such as Fire
Extinguishers, Dispensers, Mirrors, Grab Bars, and Toilet Partitions at
restrooms in tenant spaces, Areas 27, 28 and 29; and,
4. M.C. Dean, Inc. in the deductive Lump Sum amount of ($96,022.00), for the Electrical Low Voltage System deleted scope including conduit, wiring
and pathways, outlets, security, audio/visual, and fire alarm devices
throughout the tenant spaces, Areas 27, 28 and 29.
HPC will submit Time Impact Analysis (TIA 070) requesting additional time
associated with this scope of work for ASC Bulletin 028.
ASC Bulletin 028 affected the scope of work in GMP Nos. 6-S.1, 6-S.2, 6-S.3,
6-S.4, and 6-S.6. The approval of these Subcontractors Modifications to Empire
Office, Inc.; Percopo Coatings Company, LLC; SkyBuilders USA, LLC; and M.C.
Dean, Inc.; resolves all requests for cost resulting from ASC Bulletin 028;
RFIs 1317, 1477, 1546, 1795, 1175, 1176, 1177, 1356.1, 1477.1, 1681, 1681.1,
and 1684 and 1356 in GMP No. 6-S.4. Costs for patching of Fireproofing and
Insulation, and Testing and Inspection, if any, are excluded and will be
submitted in future CRs. Costs of RFIs 0818, 0818.1, 0818.2 and 0818.3 are
excluded and will be submitted in future CRs. Costs of RFI 1177 associated
with the "HVAC" scope of work were approved via CC No. 20191203.01A (CR0388-
6S1). Costs of RFI 1356 associated with the "Building Concrete" scope of work
were approved via CC No. 20200421.03E (CR0529). Impacts of ASC Bulletin 028
to GMP No. 6-S.2 were approved via CC No. 20200204.02G (CR0385-6S2). Impacts
of ASC Bulletin 028 to GMP No. 6-S.3 were approved via CC No. 20200421.03G
(CR0386-6S3). Impacts associated with RFI 1684.1 are included only for the
Doors, Frames and Hardware trade (CR0386-6S3). Impacts of ASC Bulletin 028 to
GMP No. 6-S.1 will be submitted via CR0384-6S4 for a future CCM approval.
Impacts to GMP No. 6-S.4 Low Voltage associated with RFI 1684.1 were approved
via CC No. 20200114.03P (CR0440.2-6S4). Impacts to GMP No. 6-S.1 Masonry
Minutes of the Construction Committee Meeting, June 23, 2020
Page 36 of 47
associated with RFI 1684.1 will be submitted for a future CCM approval
(CR0440.1-6S1). Impacts to GMP Nos. 6-S.4 and 6-S.6 associated with RFI 1672
were approved, respectively, via CC No. 20200303.02BB (CR0481) and CC No.
20200324.02PP (CR0509). All other trades impacted by RFI 1684.1 are to be
submitted in future CRs. There are no costs to GMP Nos. 6-S or 6-S.5. The OAR
will evaluate TIA-070 and any additional time recommended to be granted will
be submitted at a future CCM.
HPC has submitted documentation including the subcontractor's proposal to
support this request. An independent cost estimate is included. By approving
this request, the Owner does not waive its right to enforce the contract
requirements for other requests for cost or time.
The effect of this Subcontractor Modification for this project is as follows:
HPC to issue a subcontract modification to Empire Office,
Inc. in the deductive lump sum amount of:
$ (15,303.00)
HPC to issue a subcontract modification to Percopo
Coatings Company, LLC in the deductive lump sum amount of:
$ (2,181.00)
HPC to issue a subcontract modification to SkyBuilders
USA, LLC in the deductive lump sum amount of:
$ (15,385.00)
HPC to issue a subcontract modification to M.C. Dean, Inc.
in the deductive lump sum amount of:
$ (96,022.00)
Add to P1 Owner Contingency: $ 128,891.00
Hensel Phelps Construction is committed to 20% MWBE and 4% LDB participation
for Construction Services. The subcontractors identified and committed to
participate on BP-S00168 (GMP No. 6-S.4) for these subcontract modifications
are Empire Office, Inc. (Non-MWBE/LDB/VBE); Percopo Coatings Company, LLC (Not
MWBE at the time of the award of "Painting" Bid Package); SkyBuilders USA, LLC
(MWBE/LDB); and M.C. Dean, Inc. (Non-MWBE/LDB/VBE). There is an overall
reduction of 20.8% MWBE and 11.9% LDB participation associated with the
proposed modifications.
Agenda Item Nos. 2-A, 2-B, 2-C, 2-D, 2-E, 2-F, 2-G, 2-H, 2-I, 2-J, 2-K, 2-L,
2-M, 2-N, 2-O, 2-P, 2-Q, 2-R, 2-S, 2-T, 2-U, 2-V, 2-W, 2-X, 2-Y, 2-Z, 2-AA,
2-BB, 2-DD, 2-EE, 2-FF, 2-GG, 2-HH, 2-II, 2-JJ, and 2-KK were considered in
one motion.
Upon motion of Mr. Patterson, second by Mr. Hunt, vote carried by roll-call,
with all votes yea, to approve Hensel Phelps Construction to issue
Subcontractor Modifications to M.C. Dean, Inc., on BP-S00168, South Terminal
C, Phase 1 - Interior Finishes and Specialties (GMP No. 6-S.4), for the total
deductive amount of ($128,891.00), which includes the deductive lump sum amount
of ($15,303.00) to Empire Office, Inc.; the deductive lump sum amount of
($2,181.00) to Percopo Coatings Company, LLC; the deductive lump sum amount
of ($15,385.00) to SkyBuilders USA, LLC; and the deductive lump sum amount of
($96,022.00) to M.C. Dean, Inc.; with funding credited to Passenger Facility
Charges and General Airport Revenue Bonds.
FF. Subcontractor Modifications for BP-S00168 (GMP No. 6-S.4) with M.C. Dean, Inc.
for CR0491-6S4-RFI 1698.1 Monitoring of Added Fire Dampers. Mr. Corthell
presented the memorandum, requesting approval for Hensel Phelps Construction
(HPC) to issue Subcontract Modifications on BP-S00168, South Terminal C, Phase
1 - Interior Finishes and Specialties (GMP No. 6-S.4), at the Orlando
International Airport, in the total amount of $141,204.00 to M.C. Dean, Inc.,
for CR0491-6S4-RFI 1698.1 Monitoring of Added Fire Dampers. Bid Package for
Minutes of the Construction Committee Meeting, June 23, 2020
Page 37 of 47
BP-S168 27.01 "Airside Concourse Low Voltage Systems" has been previously
awarded within GMP No. 6-S.4 to M. C. Dean, Inc., CC No. 20181002.010.
HPC is requesting to issue a Subcontractor Modification to M.C. Dean, Inc. in
the total Lump Sum amount of $141,204.00 for CR0491-6S4-RFI 1698.1 Monitoring
of Added Fire Dampers. The modified scope of work consists of all material,
labor and equipment costs associated with monitoring the added Fire Dampers
that are required by the Florida Building Code. RFI 1698.1 response and
sketches confirmed the code requirements for protecting the ductwork
penetrating through 1-hour fire-rated walls with Fire Dampers (FD) and Fire
Smoke Dampers (FSD) and called out the Dampers at 86 locations in the Airside
Concourse Building.
The approval of this Subcontract Modification to M.C. Dean, Inc. resolves all
requests for cost and time resulting from RFI 1698.1 in GMP No. 6-S.4. Costs
for patching of Fireproofing and Testing & Inspection, if any, will be
submitted in a future CR. Cost impact of RFI 1698.1 to GMP Nos. 6-S.1, 6-S.2,
6-S.3 will be submitted in future CRs.
HPC has submitted documentation including the subcontractor's proposal to
support this request. An independent cost estimate is included. By approving
this request, the Owner does not waive its right to enforce the contract
requirements for other requests for cost or time.
The effect of this Subcontractor Modification for this project is as follows:
HPC to issue a subcontract modification to M.C. Dean, Inc.
in the lump sum amount of: $ 141,204.00
Deduct from P1 Owner Contingency $(141,204.00)
Hensel Phelps Construction is committed to 20% MWBE and 4% LDB participation
for Construction Services. The subcontractor identified and committed to
participate on BP-S00168 (GMP No. 6-S.4) for this subcontract modification is
M.C. Dean, Inc. (Non-MWBE/LDB/VBE). There is no small business participation
associated with this modification.
Agenda Item Nos. 2-A, 2-B, 2-C, 2-D, 2-E, 2-F, 2-G, 2-H, 2-I, 2-J, 2-K, 2-L,
2-M, 2-N, 2-O, 2-P, 2-Q, 2-R, 2-S, 2-T, 2-U, 2-V, 2-W, 2-X, 2-Y, 2-Z, 2-AA,
2-BB, 2-DD, 2-EE, 2-FF, 2-GG, 2-HH, 2-II, 2-JJ, and 2-KK were considered in
one motion.
Upon motion of Mr. Patterson, second by Mr. Hunt, vote carried by roll-call,
with all votes yea, to approve Hensel Phelps Construction to issue
Subcontractor Modifications to M.C. Dean, Inc., on BP-S00168, South Terminal
C, Phase 1 - Interior Finishes and Specialties (GMP No. 6-S.4), for the total
lump sum amount of $141,204.00, with funding from Passenger Facility Charges
and General Airport Revenue Bonds.
GG. Subcontractor Modification for BP-S00170 (GMP No. 5-S.6) with Kiewit
Infrastructure South Co. for CR0671.7-LSC-Hurricane Dorian Preparation and
Recovery. Mr. Corthell presented the memorandum, requesting approval for
Turner-Kiewit Joint Venture (TKJV) to issue a Subcontract Modification on BP-
S00170, South Terminal C, Phase 1 - Underground Electrical Distribution (GMP
No. 5-S.6), at the Orlando International Airport, in the total amount of
$36,249.00 to Kiewit Infrastructure South Co., for CR0671.7-LSC-Hurricane
Dorian Preparation and Recovery. Bid Package 26.0.0 "LSC Primary Power" was
previously awarded within GMP No. 5-S.6 to Kiewit Infrastructure South Co, CC
No. 20180605.008.
Minutes of the Construction Committee Meeting, June 23, 2020
Page 38 of 47
TKJV is requesting to issue a Subcontractor Modification to Kiewit
Infrastructure South Co. in the total lump sum amount of $36,249.00 for
CR0671.7-LSC-Hurricane Dorian Preparation and Recovery. The scope of Hurricane
Dorian preparatory work consists of all material, labor and equipment required
to secure or remove subcontractor owned equipment and materials. Work includes
the temporary removal of fencing, removal of MOT, backfilling open holes around
incomplete work; grading additional slopes for drainage, expediting disposal
of trash, emptying dumpsters to prepare for recovery; and preparing fuel pumps
for dewatering. The scope of Hurricane Dorian recovery work includes costs to
remobilize the jobsite including reinstalling MOT, repairing damaged slopes
and grades from heavy rains, reinstalling fence and wind susceptible materials,
recovering materials and removing bands; and removing pumps set up for
dewatering.
The approval of this subcontract modification to Kiewit Infrastructure South
Co. resolves all requests for costs and time associated with Hurricane Dorian
preparation and recovery for GMP No. 5-S.6.
TKJV has submitted documentation, including the subcontractor's proposal to
support their request. An independent cost review is included. By approving
this request, the Owner does not waive its right to enforce the contract
requirements for other requests for cost or time.
The effect of this Subcontractor Modification for this project is as follows:
TKJV to issue a subcontract modification to Kiewit
Infrastructure South Co. in the lump sum amount of: $ 36,249.00
Deduct from P1 CM@R Contingency: $(36,249.00)
Turner-Kiewit Joint Venture is committed to 20% MWBE and 4% LDB participation
for Construction Services. The subcontractor identified and committed to
participate on BP-S00170 (GMP No. 5-S.6) for this subcontract modification is
Kiewit Infrastructure South Co. (Non-MWBE/LDB/VBE). There is 20% MWBE and
participation and 8.5% LDB participation associated with this modification.
Ms. Schneider asked if this is the final request related to Hurricane Dorian.
Mr. Corthell replied no, that there are a couple of additional items
forthcoming. Vice Chair Sharman asked if the items in process now are the
last expected. Mr. Corthell answered yes.
Agenda Item Nos. 2-A, 2-B, 2-C, 2-D, 2-E, 2-F, 2-G, 2-H, 2-I, 2-J, 2-K, 2-L,
2-M, 2-N, 2-O, 2-P, 2-Q, 2-R, 2-S, 2-T, 2-U, 2-V, 2-W, 2-X, 2-Y, 2-Z, 2-AA,
2-BB, 2-DD, 2-EE, 2-FF, 2-GG, 2-HH, 2-II, 2-JJ, and 2-KK were considered in
one motion.
Upon motion of Mr. Patterson, second by Mr. Hunt, vote carried by roll-call,
with all votes yea, to approve Turner-Kiewit Joint Venture to issue a
Subcontractor Modification to Kiewit Infrastructure South Co., on BP-S00170,
South Terminal C, Phase 1 - Underground Electrical Distribution (GMP
No. 5-S.6), for the total lump sum amount of $36,249.00, with funding from
General Airport Revenue Bonds.
HH. Subcontractor Modification for BP-S00170 (GMP No. 5-S.6) with Kiewit
Infrastructure South Co. for CR0504-5S.6-LSC-Root Material Removal.
Mr. Corthell presented the memorandum, requesting approval for Turner-Kiewit
Joint Venture (TKJV) to issue a Subcontract Modification on BP-S00170, South
Terminal C, Phase 1 - Underground Electrical Distribution (GMP No. 5-S.6), at
the Orlando International Airport, in the total amount of $26,895.00 to Kiewit
Minutes of the Construction Committee Meeting, June 23, 2020
Page 39 of 47
Infrastructure South Co. for CR0504-5S.6-LSC-Root Material Removal. Bid
Package 26.0.0 "LSC Primary Power" was previously awarded within GMP No.
5-S.6 to Turner-Kiewit Joint Venture, CC No. 20180605.008.
TKJV is requesting to issue a Subcontractor Modification to Kiewit
Infrastructure South Co. in the total lump sum amount of $26,895.00 for CR0504-
5S.6-LSC-Root Material Removal. While Kiewit Infrastructure South Co. was
performing duct bank installation on Runs E03 and E04, root material was found
and subsequently removed. As unsuitable materials were found, these areas were
filled in with stone and filter fabric. Also, at Run E04 due to a sock drain
being ripped during excavation of roots that ran deeper than the planned
excavation, additional pump use was required for dewatering. The modified
scope of work captured in this request consists of all labor, material and
equipment costs associated with removing root material from demucked areas at
PPD that went beyond original scope of work. Scope includes costs for repairing
damaged sock drain and added well point pump time.
The approval of this subcontract modification to Kiewit Infrastructure South
Co. resolves all requests for cost and time associated with the additional
root material removal and scope of work as delineated in CR0504-5S.6-LSC-Root
Material Removal.
TKJV has submitted documentation including the subcontractor's proposal to
support their request. An independent cost estimate is included. By approving
this request, the Owner does not waive its right to enforce the contract
requirements for other requests for cost or time.
The effect of this Subcontractor Modification for this project is as follows:
TKJV to issue a subcontract modification to Kiewit
Infrastructure South Co. in the lump sum amount of: $ 26,895.00
Deduct from P1 CM@R Contingency: $ (26,895.00)
Turner-Kiewit Joint Venture is committed to 20% MWBE and 4% LDB participation
for Construction Services. The subcontractor identified and committed to
participate on BP-S00170 (GMP No. 5-S.6) for this subcontract modification is
Kiewit Infrastructure South Co. (Non-MWBE/LDB/VBE). There is 3.7% LDB
participation associated with this modification.
Agenda Item Nos. 2-A, 2-B, 2-C, 2-D, 2-E, 2-F, 2-G, 2-H, 2-I, 2-J, 2-K, 2-L,
2-M, 2-N, 2-O, 2-P, 2-Q, 2-R, 2-S, 2-T, 2-U, 2-V, 2-W, 2-X, 2-Y, 2-Z, 2-AA,
2-BB, 2-DD, 2-EE, 2-FF, 2-GG, 2-HH, 2-II, 2-JJ, and 2-KK were considered in
one motion.
Upon motion of Mr. Patterson, second by Mr. Hunt, vote carried by roll-call,
with all votes yea, to approve Turner-Kiewit Joint Venture to issue a
Subcontractor Modification to Kiewit Infrastructure South Co., on BP-S00170,
South Terminal C, Phase 1 - Underground Electrical Distribution (GMP
No. 5-S.6), for the total lump sum amount of $26,895.00, with funding from
General Airport Revenue Bonds.
II. Subcontractor Modification for BP-S00173 (GMP No. 7-S.3) with M.C. Dean, Inc.
for CR0916.1-LST-RFI 2983.1 Intermediate Distribution Frame (IDF) Rooms 01-
638AX and 01-638BX Layout (Electrical Scope). Mr. Corthell presented the
memorandum, requesting approval for Turner-Kiewit Joint Venture (TKJV) to
issue a Subcontract Modification on BP-S00173, South Terminal C, Phase 1,
Landside Terminal, MEP Systems - FDOT (GMP No. 7-S.3), at the Orlando
International Airport, in the total deductive amount of ($12,859.00) to M.C.
Dean, Inc. for CR0916.1-LST-RFI 2983.1 Intermediate Distribution Frame (IDF)
Minutes of the Construction Committee Meeting, June 23, 2020
Page 40 of 47
Rooms 01-638AX and 01-638BX Layout (Electrical Scope). Bid Package 26.0.0
"Electrical" was previously awarded within GMP No. 7-S.3 to MC Dean, Inc., CC
No. 20181002.11.
TKJV is requesting to issue a Subcontractor Modification to M.C. Dean, Inc.
in the total deductive lump sum amount of ($12,859.00) for CR0916.1-LST-RFI
2983.1 Intermediate Distribution Frame (IDF) Rooms 01-638AX and 01-638BX
Layout. The modified scope of work include updates to IDF rooms layout for 01-
638AX and 01-638BX, reducing quantity of equipment cabinet, revising camera
locations within the IDF rooms, revising the lighting and electrical design
according to updated room dimensions and equipment, and revising the Security
and Access Control Systems (SACS) at IDF room doors, as captured in RFI 2983.1.
The approval of this subcontract modification to M.C. Dean, Inc. resolves all
requests for cost and time associated with RFI 2983.1 scope of work in GMP No.
7-S.3. Cost impacts to GMP No. 7-S.1 were approved at CC No. 20200526.03V.
Initial P1X Electrical scope was added at CC No. 20190806.10. There are no
cost impacts to GMP Nos. 7-S, 7-S.2 and 7-S.4.
TKJV has submitted documentation including the subcontractor's proposal to
support their request. An independent cost estimate is included. By approving
this request, the Owner does not waive its right to enforce the contract
requirements for other requests for cost or time.
The effect of this Subcontractor Modification for this project is as follows:
TKJV to issue a subcontract modification to M.C.
Dean, Inc. in the deductive lump sum amount of: $ (12,859.00)
Add to P1X Owner Contingency: $ 12,859.00
Due to the funding source of this GMP No. 7-S.3, Turner-Kiewit Joint Venture
proposed a 10% DBE participation goal for Construction Services, in lieu of
MWBE and LDB participation goals. As such, Turner-Kiewit Joint Venture’s
committed MWBE and LDB Construction Services goals are not affected by this
modification. The subcontractor identified and committed to participate on
BP-S00173 (GMP No. 7-S.3) for this subcontract modification is M.C. Dean, Inc.
(Non-MWBE/LDB/VBE). There is no small business participation associated with
this modification.
Agenda Item Nos. 2-A, 2-B, 2-C, 2-D, 2-E, 2-F, 2-G, 2-H, 2-I, 2-J, 2-K, 2-L,
2-M, 2-N, 2-O, 2-P, 2-Q, 2-R, 2-S, 2-T, 2-U, 2-V, 2-W, 2-X, 2-Y, 2-Z, 2-AA,
2-BB, 2-DD, 2-EE, 2-FF, 2-GG, 2-HH, 2-II, 2-JJ, and 2-KK were considered in
one motion.
Upon motion of Mr. Patterson, second by Mr. Hunt, vote carried by roll-call,
with all votes yea, to approve Turner-Kiewit Joint Venture to issue a
Subcontractor Modification to M.C. Dean, Inc. on BP-S00173, South Terminal C,
Phase 1, Landside Terminal, MEP Systems - FDOT (GMP No. 7-S.3), for the total
deductive lump sum amount of ($12,859.00), with funding credited to Passenger
Facility Charges and General Airport Revenue Bonds.
JJ. Subcontractor Modification for BP-S00176 (GMP No. 18-S) with Kiewit
Infrastructure South Co. for CR1054-SLR and LSC-Change Request Reconciliation
and Budget Reallocation. [A handout was presented, which includes an Office
of Small Business Participation Memorandum.] Mr. Corthell presented the
memorandum, requesting approval for Turner-Kiewit Joint Venture (TKJV) to
issue a Subcontract Modification on BP-S00176, South Terminal C, Phase 1 -
Site Logistics Relocation (GMP No. 18-S), at the Orlando International Airport,
in the total amount of $877,443.00 to Kiewit Infrastructure South Co. for
Minutes of the Construction Committee Meeting, June 23, 2020
Page 41 of 47
CR1054-SLR and LSC-Change Request Reconciliation and Budget Reallocation. GMP
No. 18-S Bid Package S176 was previously awarded to Kiewit Infrastructure
South Co., CC No. 20190108.003.
TKJV is requesting to issue a Subcontractor Modification to Kiewit
Infrastructure South Co. in the total lump sum amount $877,443 for CR1054 SLR
and LSC Change Request Reconciliation. The costs included in CR1054 are for
all remaining buyout items and extended schedule duration for Site Logistics
Relocation (SLR) and Landside Civil (LSC) work as described on the TK CR1054
letter and TIA No. 41.1 for SLR Bulletin 5.
The approval of this subcontract modification to Kiewit Infrastructure South
Co. resolves all costs and time for all past and current Kiewit Infrastructure
South Co. change requests for GMP No. 18-S scope of work with the exception
of the following scope deferment items that will be addressed in an upcoming
GMP amendment: LSC QTA Bridge, LSC fabric form rip rap at the Pond 70 outfall,
and the Audio/Visual (AV) portion of SLR Bulletin 7.
TKJV is also proposing a budget reallocation to transfer remaining balances
of GMP Allowance line items to Owner Contingency.
TKJV has submitted documentation including the subcontractor's proposal to
support their request. An independent cost estimate is included. By approving
this request, the Owner does not waive its right to enforce the contract
requirements for other requests for cost or time.
The effect of this Subcontractor Modification for this project is as follows:
TKJV to issue a subcontract modification to Kiewit
Infrastructure South Co. in the lump sum amount of: $ 877,443.00
Deduct from P1 CMAR Contingency: $ (72,492.00)
Deduct from P1X CMAR Contingency: $ (217,350.00)
Deduct from P1X Owner Contingency: $ (285,327.00)
Deduct from CWE Owner Contingency: $ (189,611.00)
Deduct from P1X GMP Allowance Line Item 11 - AV: $ (85,002.00)
Deduct from P1X GMP Allowance Line Item 12 - Fiber: $ (23,605.00)
Deduct from CWE GMP Allowance Line Item 12 - Fiber: $ (4,056.00)
Transfer P1X GMP Allowance Line Item 11 to P1X Owner
Contingency:
$ (57,220.00)
Transfer CWE GMP Allowance Line Item 11 to CWE Owner
Contingency:
$ (17,778.00)
Transfer P1X Allowance Line Item 12 to P1X Owner
Contingency:
$ (16,395.00)
Transfer CWE GMP Allowance Line Item 12 to CWE Owner
Contingency:
$ (15,944.00)
Transfer P1X GMP Allowance Line Item 14 to P1X Owner
Contingency:
$ (200,000.00)
Add to P1X Owner Contingency: $ 273,615.00
Add to CWE Owner Contingency: $ 33,722.00
Turner-Kiewit Joint Venture is committed to 20% MWBE and 4% LDB participation
for Construction Services. The subcontractor identified and committed to
participate on BP-S00176 (GMP No. 18-S) for this subcontract modification is
Kiewit Infrastructure South Co. (Non-MWBE/LDB/VBE). . There is 42.5% MWBE and
13.8% LDB participation associated with this modification.
Agenda Item Nos. 2-A, 2-B, 2-C, 2-D, 2-E, 2-F, 2-G, 2-H, 2-I, 2-J, 2-K, 2-L,
2-M, 2-N, 2-O, 2-P, 2-Q, 2-R, 2-S, 2-T, 2-U, 2-V, 2-W, 2-X, 2-Y, 2-Z, 2-AA,
Minutes of the Construction Committee Meeting, June 23, 2020
Page 42 of 47
2-BB, 2-DD, 2-EE, 2-FF, 2-GG, 2-HH, 2-II, 2-JJ, and 2-KK were considered in
one motion.
Upon motion of Mr. Patterson, second by Mr. Hunt, vote carried by roll-call,
with all votes yea, to approve Turner-Kiewit Joint Venture to issue a
Subcontractor Modification to Kiewit Infrastructure South Co. on BP-S00176,
South Terminal C, Phase 1 - Site Logistics Relocation (GMP No. 18-S), for the
total lump sum amount of $877,443.00, with funding from General Airport Revenue
Bonds, Customer Facility Charges, and Aviation Authority Funds.
KK. Subcontractor Modification for BP-S00178 (GMP No. 19-S) with Kiewit
Infrastructure South Co. for CR0671.9-AFC-Hurricane Dorian Preparation and
Recovery. Mr. Corthell presented the memorandum, requesting approval for
Turner-Kiewit Joint Venture (TKJV) to issue a Subcontract Modification on BP-
S00178, South Terminal C, Phase 1 - Airfield Civil (GMP No. 19-S), at the
Orlando International Airport, in the total amount of $28,659.00 to Kiewit
Infrastructure South Co. for CR0671.9-AFC-Hurricane Dorian Preparation and
Recovery. Bid Package 34.10.1 "Site Electrical and Communications" was
previously awarded within GMP No. 19-S to Kiewit Infrastructure South Co., CC
No. 20190604.026.
TKJV is requesting to issue a Subcontractor Modification to Kiewit
Infrastructure South Co.in the total lump sum amount of $28,659.00 for
CR0671.9-AFC-Hurricane Dorian Preparation and Recovery.
The scope of Hurricane Dorian preparatory work consists of all material, labor
and equipment required to secure or remove subcontractor owned equipment and
materials. Work includes the temporary removal of fencing, removal of MOT,
backfilling open holes around incomplete work; grading additional slopes for
drainage, expediting disposal of trash, emptying dumpsters to prepare for
recovery; and preparing fuel pumps for dewatering. The scope of Hurricane
Dorian recovery work includes costs to remobilize the jobsite including
reinstalling MOT, repairing damaged slopes and grades from heavy rains,
reinstalling fence and wind susceptible materials, recovering materials and
removing bands; and removing pumps set up for dewatering.
The approval of this subcontract modification to Kiewit Infrastructure South
Co. resolves all requests for costs and time associated with Hurricane Dorian
preparation and recovery for GMP No. 19-S.
TKJV has submitted documentation, including the subcontractor's proposal to
support their request. An independent cost review is included. By approving
this request, the Owner does not waive its right to enforce the contract
requirements for other requests for cost or time.
The effect of this Subcontractor Modification for this project is as follows:
TKJV to issue a subcontract modification to Kiewit
Infrastructure South Co. in the lump sum amount of: $ 28,659.00
Deduct from P1 CMAR Contingency: $ (15,842.00)
Deduct from P1X CMAR Contingency: $ (12,817.00)
Turner-Kiewit Joint Venture is committed to 20% MWBE and 4% LDB participation
for Construction Services. The subcontractor identified and committed to
participate on BP-S00178 (GMP No. 19-S) for this subcontract modification is
Kiewit Infrastructure South Co. (Non-MWBE/LDB). There is no small business
participation associated with this modification.
Minutes of the Construction Committee Meeting, June 23, 2020
Page 43 of 47
Ms. Schneider asked if this is the final request related to Hurricane Dorian.
Mr. Corthell replied no, that there are a couple of additional items
forthcoming. Vice Chair Sharman asked if the items in process now are the
last expected. Mr. Corthell answered yes.
Agenda Item Nos. 2-A, 2-B, 2-C, 2-D, 2-E, 2-F, 2-G, 2-H, 2-I, 2-J, 2-K, 2-L,
2-M, 2-N, 2-O, 2-P, 2-Q, 2-R, 2-S, 2-T, 2-U, 2-V, 2-W, 2-X, 2-Y, 2-Z, 2-AA,
2-BB, 2-DD, 2-EE, 2-FF, 2-GG, 2-HH, 2-II, 2-JJ, and 2-KK were considered in
one motion.
Upon motion of Mr. Patterson, second by Mr. Hunt, vote carried by roll-call,
with all votes yea, to approve Turner-Kiewit Joint Venture to issue a
Subcontractor Modification to Kiewit Infrastructure South, Co. on BP-S00178,
South Terminal C, Phase 1 - Airfield Civil (GMP No. 19-S), for the total lump
sum amount of $28,659.00, with funding from General Airport Revenue Bonds.
SOUTH TERMINAL C
REQUEST FOR APPROVAL OF AN ADDENDUM TO THE TECHNOLOGY AND MULTI-MEDIA SYSTEMS
SPECIALTY ENGINEER FOR THE SOUTH TERMINAL C, PHASE 1 AGREEMENT WITH BURNS
ENGINEERING, INC. FOR DESIGN SERVICES FOR W-S00113 SOUTH TERMINAL C, PHASE 1 -
TECHNOLOGY AND MULTI-MEDIA SERVICES, AT THE ORLANDO INTERNATIONAL AIRPORT.
3. Mr. Corthell presented the memorandum, dated June 23, 2020, along with a
proposal from Burns Engineering, Inc., dated June 4, 2020, to provide design services related to the deferred scope on the Ground Transportation Facility.
Services include the technology, security, and fire alarm systems design effort
required to address the modified scope areas of the Ground Transportation Facility.
The scope of the work effort has been coordinated with HNTB, Rhodes + Brito, and
Turner-Kiewit Joint Venture (TKJV), and is based on the Scope Deferment Descriptions
developed by TKJV during STC P1/P1X Scope Alignment Meetings. The proposal includes
Burns Engineering’s staff and subconsultant personnel on a lump sum basis.
If approved, these services would be effective June 23, 2020.
Consultant shall, with each monthly invoice, certify that the assigned work and
services are on schedule to be completed within the contracted lump sum price, or
provide at time of certification a written notice to the Aviation Authority of any
deviations.
The Office of Small Business Development has reviewed the qualifications of the
subject contract’s MWBE/LDB/VBE specifications and determined that, due to the
limited and specialized scope of the required services, Burns Engineering, Inc. does
not propose any small business participation on this Addendum.
Vice Chair Sharman asked if Mr. Corthell was comfortable that the scope was defined
well enough for the lump sum funding. Mr. Corthell answered yes.
Upon motion of Ms. Schneider, second by Mr. Hunt, vote carried by roll-call, with
all votes yea, to approve an Addendum to the Technology and Multi-Media Systems
Specialty Engineer for the South Terminal C, Phase 1 Agreement with Burns
Engineering, Inc. for Design Services for W-S00113, South Terminal C, Phase 1 -
Technology and Multi-Media Services, for a total lump sum fee amount of $28,224.00,
with funding from General Airport Revenue Bonds.
Minutes of the Construction Committee Meeting, June 23, 2020
Page 44 of 47
GENERAL
REQUEST FOR APPROVAL OF AN AMENDMENT TO ADDENDUM NO. 81 TO THE GENERAL CONSULTING
SERVICES AGREEMENT WITH SCHENKEL & SHULTZ, INC. FOR ADDITIONAL ON-CALL GENERAL
CONSULTING SERVICES FOR THE POITRAS PROPERTY, AT THE ORLANDO INTERNATIONAL AIRPORT.
4. Mr. Sorondo presented the memorandum, dated June 23, 2020, along with a
proposal from Schenkel & Shultz, Inc., dated June 3, 2020, to provide Additional On-
Call General Consulting Services for the Poitras Property, at the Orlando
International Airport. On July 16, 2019, the Construction Committee approved
Addendum No. 81 in the amount of $20,000.00 to the above-referenced agreement.
Subsequently, on October 15, 2019, the Construction Committee approved Amendment
No. 1 to Addendum No. 81 in the amount of $20,000.00. Since that time, it has been
determined that additional meetings and coordination with the South Florida Water
Management District are required as furthered described in the Consultant's proposal,
dated June 3, 2020.
If approved, these services would be effective June 23, 2020.
The Office of Small Business Development has determined that due to the limited
scope of the required services, Schenkel & Shultz, Inc. does not propose any small
business participation on this Amendment.
Upon motion of Ms. Schneider, second by Mr. Hunt, vote carried by roll-call with all
votes yea, to approve an Amendment to Addendum No. 81 to the General Consulting
Services Agreement with Schenkel & Shultz, Inc. for Additional On-Call General
Consulting Services for the Poitras Property, for the total not-to-exceed fee amount
of $5,500.00, with funding from previously-approved Discretionary Funds.
REQUEST FOR APPROVAL OF AN ADDENDUM TO THE CONTINUING ENVIRONMENTAL ENGINEERING
SERVICES AGREEMENT WITH TERRACON CONSULTANTS, INC. TO CONDUCT A LIMITED SITE
INVESTIGATION (LSI) AT THE FORMER UNDERGROUND STORAGE TANK (UST) AT THE AIRSIDE 3
(AS3) AUTOMATED GUIDEWAY TRANSIT (AGT) SITE, AT THE ORLANDO INTERNATIONAL AIRPORT.
5. Mr. Carrington presented the memorandum, dated June 23, 2020, along with a
proposal from Terracon Consultants, Inc., dated May 26, 2020, to conduct additional
soil and groundwater samples at the former UST site that was located on AS3 AGT
site. During the Piping Closure Assessment, it was determined that soils and
groundwater were impacted above Cleanup Target Levels as outlined in 62-777 Florida
Administration Code (FAC). Orange County Environmental Protection Division is
requesting additional Site Investigation activities.
If approved, these services would be effective the date of Construction Committee
approval.
The Office of Small Business Development has reviewed the qualifications of the
subject contract's MWBE/LDB/VBE specifications and determined that Terracon
Consultants, Inc. proposes 26.7% MWBE participation on this Addendum.
Upon motion of Mr. Patterson, second by Ms. Schneider, vote carried by roll-call
with all votes yea, to approve an Addendum to the Continuing Environmental
Engineering Services Agreement with Terracon Consultants, Inc. to conduct a Limited
Site Investigation at the Former Underground Storage Tank at the Airside 3 Automated
Guideway Transit Site, for the total amount of $13,244.00, which includes the not-
to-exceed fee amount of $8,078.00 and the not-to-exceed expense amount of $5,166.00,
with funding from previously-approved Operation and Maintenance Funds.
Minutes of the Construction Committee Meeting, June 23, 2020
Page 45 of 47
REQUEST FOR APPROVAL OF CONTRACTOR’S FINAL PAYMENT TO GILBANE BUILDING COMPANY, FOR
V-00881, DAKTRONICS SIGN ON PARKING ENTRANCE AND EXIT TOLL BOOTHS, AT THE ORLANDO
INTERNATIONAL AIRPORT.
6. Mr. Patterson presented the memorandum, dated June 23, 2020, requesting the
Contractor’s Final Payment to Gilbane Building Company for V-00881, Daktronics Signs
on Parking Entrance and Exit Toll Booths, at the Orlando International Airport. The
Construction Contract for the referenced project has been completed and all issues
involving the Contractor have been addressed and resolved.
Upon motion of Mr. Hunt, second by Ms. Schneider, vote carried by roll-call, with
all votes yea, to approve the Contractor’s Final Payment Authorization to Gilbane
Building Company for V-00881, Daktronics Signs on Parking Entrance and Exit Toll
Booths, at the Orlando International Airport.
INFORMATION ITEMS
7. The following items were presented for information only:
A. Field Change Order (FCO) Log
B. COVID-19 CCM Item Log
C. Revised GMP Budget, Buyout & Contingency Form for Turner-Kiewit Joint
Venture to issue a Subcontract Modification to Kiewit Infrastructure
South, Co. for BP-S00178 (GMP No. 19-S) South Terminal C, Phase 1 -
Airfield Civil, at the Orlando International Airport. [From Construction
Committee on April 28, 2020, Item No. 2-Q].
D. Revised Change Order for V-00927-01, Upgrade Airside 4 Recheck/Transfer
System Controls (Design/Build) with The Collage Design & Construction,
Inc. dba The Collage Companies, at the Orlando International Airport.
[From Construction Committee on June 9, 2020, Item No. 2-B].
E. Revised Change Order for V-00950-01, Upgrade Airside 4 Glass Window
Replacement with Gomez Construction Company, at the Orlando International
Airport. [From Construction Committee on June 9, 2020, Item No. 2-D].
F. Office of Small Business Participation Memorandum for the Request for
Approval of a Budget Reallocation to the Construction Management at Risk
(CM@R) Entity Services for the South Terminal C, Phase 1 Agreement with
Turner-Kiewit Joint Venture for BP-S00163 (GMP No. 5-S.5), South Terminal
C, Phase 1 - Enplane/Deplane Bridge & Roadways Balance of Work - FDOT for
CR01106-5S.5-LSC- Budget Reallocations-Enplane/ Deplane Bridge and
Roadways Balance of Work, at the Orlando International Airport. [From
Construction Committee on June 9, 2020, Item No. 3-S].
G. Office of Small Business Participation Memorandum for the Request for
Approval of an Addendum to the Architect of Record Services for the South
Terminal C, Phase 1 Agreement with HNTB Corporation for Design Services
for W-S00110, South Terminal C, Phase 1 - Architect of Record Services (&
Major Subs), at the Orlando International Airport. [From Construction
Committee on June 9, 2020, Item No. 4].
H. Office of Small Business Participation Memorandum for the Request for
Approval of an Addendum to the Program and Project Management Services
for the South Terminal C, Phase 1 Agreement with Cost Management, Inc.
for Passive Optical Local Area Network (PON) Services for W-S00111 South
Terminal C, Phase 1 - Program & Project Management Services (OAR), at the
Orlando International Airport. [From Construction Committee on June 9,
2020, Item No. 5].
Minutes of the Construction Committee Meeting, June 23, 2020
Page 46 of 47
I. Office of Small Business Participation Memorandum for the Request for
Approval of an Addendum to the Technology and Multi-Media Systems
Specialty Engineer for the South Terminal C, Phase 1 Agreement with Burns
Engineering, Inc. for Passive Optical Local Area Network (PON) Services
for W-S00113 South Terminal C, Phase 1 - Technology and Multi-Media
Services, at the Orlando International Airport. [From Construction
Committee on June 9, 2020, Item No. 6].
J. [A handout was presented, which includes a revised Information Item.]
Information Item for Procurement Process Refinement for WS-00145, South
Terminal C, Phase 1 and Phase 1X Owner Furnished FF&E and IT Items, at
the Orlando International Airport.
Ms. Sharman asked if this item is appropriate as an Information Item.
Legal Counsel answered yes, because it is only providing additional
details and no substantive changes.
K. [Converted to New Agenda Item No. 8] Revised GMP Budget, Buyout &
Contingency Form for Hensel Phelps Construction to issue a Subcontract
Modification to Central Hauling and Excavating, Inc. for BP-S00179 (GMP
No. 6-S.6) South Terminal C, Phase 1 - Airside Concourse (P1X Remaining
Scope), at the Orlando International Airport. [From Construction
Committee on March 24, 2020, Item No. 2-NN].
Vice Chair Sharman asked if this item is appropriate as an Information
Item. Legal Counsel answered no, because the conversion to “not-to-
exceed” from “lump sum” is a substantive change. Vice Chair Sharman
stated that Information Item No. 7-K will be converted to an actionable
item as Agenda Item No. 8 for approval by the Construction Committee.
NEW ITEM
REQUEST FOR APPROVAL OF A REVISED GMP BUDGET, BUYOUT AND CONTINGENCY FORM FOR HENSEL
PHELPS CONSTRUCTION TO ISSUE A SUBCONTRACT MODIFICATION TO CENTRAL HAULING AND
EXCAVATING, INC. FOR BP-S00179, SOUTH TERMINAL C, PHASE 1 - AIRSIDE CONCOURSE P1X
REMAINING SCOPE (GMP NO. 6-S.6), AT THE ORLANDO INTERNATIONAL AIRPORT.
8. [Formerly Agenda Item No. 7-K] The GMP Budget, Buyout and Contingency Form
was presented to request a revision to the previously-approved Item No. 2-NN on the
March 24, 2020, Construction Committee, for the conversion of funding from lump sum
to not-to-exceed for Hensel Phelps Construction to issue a Subcontract Modification
to Central Hauling and Excavating, Inc. on BP-S00179, South Terminal C, Phase 1 -
Airside Concourse P1X Remaining Scope (GMP No. 6-S.6), at the Orlando International
Airport.
Legal Counsel stated that the conversion to “not-to-exceed” from “lump sum” funding
is a substantive change, and therefore, it should not be an Information Item. Vice
Chair Sharman stated that Information Item No. 7-K will be converted to an actionable
item as Agenda Item No. 8 for approval by the Construction Committee.
Upon motion of Ms. Schneider, second by Mr. Patterson, vote carried by roll-call,
with all votes yea, to approve a revision to the previously-approved Item No. 2-NN
on the March 24, 2020, Construction Committee, for the conversion of funding from
lump sum to not-to-exceed for Hensel Phelps Construction to issue a Subcontract
Modification to Central Hauling and Excavating, Inc. on BP-S00179, South Terminal
C, Phase 1 - Airside Concourse P1X Remaining Scope (GMP No. 6-S.6).
On TUESDAY, JULY 21, 2020, the PROFESSIONAL SERVICES COMMITTEE met in regular session virtually in accordance with the Greater Orlando Aviation Authority’s established business distancing operational plan. Chairman Thornton called the meeting to order at 9:37 a.m. The meeting was posted in accordance with Florida Statutes with a quorum participating. Office of the Governor, Executive Order Number 20-69 Participating Committee members: Stanley J. Thornton, Chairman Davin Ruohomaki, Senior Director of Planning, Engineering, and Construction Gary Hunt, Director of Maintenance
Pam L’Heureux, Director of Finance
Also participating: Karen Ryan, Legal Counsel (Nelson Mullins Broad & Cassel) Ian Brooks, GOAA IT Tara Ciaglia, Recording Secretary
LOBBYIST DISCLOSURE Parties present were reminded that for individuals who conduct lobbying activities with Aviation Authority employees or Board members, registration with the Aviation Authority is required each year prior to conducting any lobbying activities. A statement of expenditures incurred in connection with those lobbying instances should also be filed prior to April 1st of each year for the preceding year. As of January 16, 2013, lobbying any Aviation Authority Staff who are members of any committee responsible for ranking Proposals, Letters of Interest, Statements of Qualifications or Bids and thereafter forwarding those recommendations to the Board and/or Board Members is prohibited from the time that a Request for Proposals, Request for Letters of Interests, Request for Qualifications or Request for Bids is released to the time that the Board makes an award. The lobbyist shall file a Notice of Lobbying (Form 4) detailing each instance of lobbying to the Aviation Authority within seven calendar days of such lobbying. As of January 16, 2013, lobbyists will also provide a notice to the Aviation Authority when meeting with the Mayor of the City of Orlando or the Mayor of Orange County at their offices. The policy, forms, and instructions are available in the Aviation Authority’s offices and the website. Please contact the Director of Board Services with questions at (407) 825-2032. COVID-19 ANNOUNCEMENT Due to the COVID-19, the Aviation Authority is adhering to a business distancing operational plan. Please note that all Professional Services Committee meetings from today until further notice will be held telephonically. If you would like to speak at the meeting on an agenda item being considered, please contact the Recording Secretary, Tara Ciaglia ([email protected] -or- 407-825-4461) no less than 24 hours in advance of the meeting. Otherwise, the Professional Services Committee will be available via Live Stream at www.orlandoairports.net ANNOUNCEMENT Any appeals of decisions made by the Professional Services Committee (PSC) must be filed with the Chief Executive Officer within five business days (no later than 4:00 p.m. on the fifth business day) of the rendering of that decision. If a bidder or proposer is aggrieved by any of the proceedings of today’s meeting and wishes to appeal the results of actions made by this committee, they must file an appeal stating the item they wish to appeal and the basis for which they wish to appeal, and it must be received in writing by the Chief Executive Officer, Mr. Phillip N. Brown, via email [email protected], with a copy to [email protected] (emails will be accepted during the COVID-19 pandemic.)
Minutes of the Professional Services Committee July 21, 2020 Page 2 of 3 REQUEST FOR RECOMMENDATION OF APPROVAL TO THE CHIEF EXECUTIVE OFFICER OF AN ADDENDUM TO THE LAND DEVELOPMENT AND LAND MANAGEMENT CONSULTING SERVICES AGREEMENT WITH DYKES EVERETT & COMPANY, LLC FOR LAND MANAGEMENT SERVICES FOR THE DAETWYLER PROPERTY, AT THE ORLANDO INTERNATIONAL AIRPORT. 1. Chairman Thornton presented the memorandum, dated July 21, 2020, along with a proposal from Dykes Everett & Company, LLC, dated July 2, 2020, to provide Land Management Services for Daetwyler Property at the Orlando International Airport. Services will include land management consulting services for vacant land tracts and miscellaneous airfield properties at the Daetwyler Property, and will include, but are not limited to, mitigation of fire risks by reducing overgrowth, dead foliage and creating a fire line, the use and development of strategic resources, development of site security plans, development and implementation of programs for pasture development, and assistance with land planning, development, surveying, permitting and resource evaluation. Further details are included in the Consultant’s proposal, dated July 2, 2020. The Office of Small Business Development reviewed the proposal from Dykes Everett & Company, LLC and determined that, due to the limited and specialized scope of the required services, Dykes Everett & Company, LLC does not propose any small business participation on this Addendum. Upon motion of Mr. Ruohomaki, second by Mr. Hunt, vote carried by roll-call, with all votes yea, to recommend to the Chief Executive Officer approval of an Addendum to the Land Development and Land Management Consulting Services Agreement with Dykes Everett & Company, LLC for Land Management Services for the Daetwyler Property, at the Orlando International Airport, for the total lump sum fee amount of $31,803.00, with funding from previously-approved Capital Expenditure Funds. REQUEST FOR RECOMMENDATION OF APPROVAL TO THE CHIEF EXECUTIVE OFFICER OF AN AMENDMENT TO ADDENDUM NO. 13 TO THE INFORMATION TECHNOLOGY CONSULTING SERVICES AGREEMENT WITH FAITH GROUP CONSULTING, LLC FOR A REDUCTION OF SERVICES OF FISCAL YEAR (FY) 2020 INFORMATION SYSTEMS STAFF AUGMENTATION SUPPORT FOR THE MAINTENANCE DEPARMENT, AT THE ORLANDO INTERNATIONAL AIRPORT. 2. Mr. Brooks presented the memorandum, dated July 21, 2020, along with a proposal from Faith Consulting Group, LLC, dated June 18, 2020, a reduction of services for FY 2020 Information Systems Staff Augmentation Support to the Maintenance Department, at the Orlando International Airport. These services were to provide one temporary full-time staff augmentation Application Programmer/Analyst position for daily operational monitoring and maintenance support services to the Maintenance Department; however, due to COVID-19 impacts, anticipated work through the end of FY 2020 has been reduced. Further details are included in the Consultant’s proposal, dated June 18, 2020. The Office of Small Business Development reviewed the proposal from Faith Consulting Group, LLC and determined that Faith Consulting Group, LLC proposes a reduction of 96.1% MWBE business participation on this Amendment. Upon motion of Mr. Hunt, second by Ms. L’Heureux, vote carried by roll-call, with all votes yea, to recommend to the Chief Executive Officer approval of an Amendment to Addendum No. 13 to the Information Technology Consulting Services Agreement with Faith Consulting Group, LLC for Reduction of Services of FY 2020 Information Systems Staff Augmentation Support to the Maintenance Department, at the Orlando International Airport, for the total deductive not-to-exceed fee amount of ($171,119.00), with funding credited to previously-approved Operation and Maintenance Funds.
Minutes of the Professional Services Committee July 21, 2020 Page 3 of 3 ADJOURNMENT 3. There being no further business for discussion, the meeting was adjourned at 9:45 a.m.
____________________________ Stanley J. Thornton, Chairman Professional Services Committee Chief Operating Officer
Davin D. Ruohomaki
Digitally signed by Davin D. RuohomakiDate: 2020.09.24 13:47:24 -04'00'
On TUESDAY, JULY 28, 2020, the PROFESSIONAL SERVICES COMMITTEE met in regular session virtually in accordance with the Greater Orlando Aviation Authority’s established business distancing operational plan. Chairman Thornton called the meeting to order at 9:30 a.m. The meeting was posted in accordance with Florida Statutes with a quorum participating. Office of the Governor, Executive Order Number 20-69 Participating Committee members: Stanley J. Thornton, Chairman Davin Ruohomaki, Senior Director of Planning, Engineering, and Construction Mike Patterson, Director of Construction
Pam L’Heureux, Director of Finance Gary Hunt, Director of Maintenance
Also participating: Karen Ryan, Legal Counsel (Nelson Mullins Broad & Cassel) Denise Schneider, GOAA Purchasing Deborah McKeown, Recording Secretary
LOBBYIST DISCLOSURE Parties present were reminded that for individuals who conduct lobbying activities with Aviation Authority employees or Board members, registration with the Aviation Authority is required each year prior to conducting any lobbying activities. A statement of expenditures incurred in connection with those lobbying instances should also be filed prior to April 1st of each year for the preceding year. As of January 16, 2013, lobbying any Aviation Authority Staff who are members of any committee responsible for ranking Proposals, Letters of Interest, Statements of Qualifications or Bids and thereafter forwarding those recommendations to the Board and/or Board Members is prohibited from the time that a Request for Proposals, Request for Letters of Interests, Request for Qualifications or Request for Bids is released to the time that the Board makes an award. The lobbyist shall file a Notice of Lobbying (Form 4) detailing each instance of lobbying to the Aviation Authority within seven calendar days of such lobbying. As of January 16, 2013, lobbyists will also provide a notice to the Aviation Authority when meeting with the Mayor of the City of Orlando or the Mayor of Orange County at their offices. The policy, forms, and instructions are available in the Aviation Authority’s offices and the website. Please contact the Director of Board Services with questions at (407) 825-2032. COVID-19 ANNOUNCEMENT Due to the COVID-19, the Aviation Authority is adhering to a business distancing operational plan. Please note that all Professional Services Committee meetings from today until further notice will be held telephonically. If you would like to speak at the meeting on an agenda item being considered, please contact the Recording Secretary, Tara Ciaglia ([email protected] -or- 407-825-4461) no less than 24 hours in advance of the meeting. Otherwise, the Professional Services Committee will be available via Live Stream at www.orlandoairports.net ANNOUNCEMENT Any appeals of decisions made by the Professional Services Committee (PSC) must be filed with the Chief Executive Officer within five business days (no later than 4:00 p.m. on the fifth business day) of the rendering of that decision. If a bidder or proposer is aggrieved by any of the proceedings of today’s meeting and wishes to appeal the results of actions made by this committee, they must file an appeal stating the item they wish to appeal and the basis for which they wish to appeal, and it must be received in writing by the Chief Executive Officer, Mr. Phillip N. Brown, via email [email protected], with a copy to [email protected] (emails will be accepted during the COVID-19 pandemic.)
Minutes of the Professional Services Committee July 28, 2020 Page 2 of 2 CONSIDERATION OF MEETING MINUTES OF JUNE 30, 2020 (VARIOUS ITEMS) 1. Upon motion of Mr. Patterson, second by Mr. Hunt, vote carried by roll-call, with all votes yea, to approve the PSC Minutes from the meeting on June 30, 2020, with correction of the spelling of “Specification” on Page 2, Item 3. REQUEST FOR RECOMMENDATION OF APPROVAL TO THE CHIEF EXECUTIVE OFFICER OF AN INCREASE IN VALUE NO. 1 TO THE PURCHASING AGREEMENT PS-316, PARKING REVENUE CONTROL SYSTEMS (PARCS), WITH LUMIN ADVISORS, LLC, AT THE ORLANDO INTERNATIONAL AIRPORT. 2. Ms. Schneider presented the memorandum, dated July 22, 2020, for an Increase in Value No. 1 to the Purchasing Agreement PS-316, Parking Revenue Control Systems (PARCS), with Lumin Advisors, LLC, at the Orlando International Airport. These additional services will include, but are not limited to, module and related software development support through final acceptance of the PARCS Project. Services will include, but are not limited to, coordinating the work of all parties involved on the PARCS Project, including system design and writing of technical/performance specifications, acceptance testing, construction, demolition, installation, integration, testing, training, and final system acceptance; coordinating the efforts and activities of all involved Aviation Authority representatives, as required; preparation of needs analysis, project budgets, project schedules, cost estimates, change orders, modifications, shop drawings, and other project related documents as required; provision of activity reports, milestone payment reports, final system acceptance reports; schedule, attend and record minutes of scheduled project meetings; and other required management, administrative and specialized design development services required to control and monitor the schedule, cost and quality of project work. The Aviation Authority did not establish MWBE or LDB/VBE participation goals for this agreement. Upon motion of Mr. Patterson, second by Mr. Hunt, vote carried by roll-call, with all votes yea, to recommend to the Chief Executive Officer approval of an Increase in Value No. 1 to the Purchasing Agreement PS-316, Parking Revenue Control Systems (PARCS), with Lumin Advisors, LLC, at the Orlando International Airport, for the total not-to-exceed fee amount of $26,000.00, with funding from previously-approved Discretionary Funds from ZC-122. ADJOURNMENT 3. There being no further business for discussion, the meeting was adjourned at 9:38 a.m.
____________________________ Stanley J. Thornton, Chairman Professional Services Committee Chief Operating Officer
Davin D. Ruohomaki
Digitally signed by Davin D. RuohomakiDate: 2020.09.24 13:46:54 -04'00'
On TUESDAY, AUGUST 4, 2020, the PROFESSIONAL SERVICES COMMITTEE met in regular session virtually in accordance with the Greater Orlando Aviation Authority’s established business distancing operational plan. Chairman Thornton called the meeting to order at 9:15 a.m. The meeting was posted in accordance with Florida Statutes with a quorum participating. Office of the Governor, Executive Order Number 20-69 Participating Committee members: Stanley J. Thornton, Chairman Davin Ruohomaki, Senior Director of Planning, Engineering, and Construction Mike Patterson, Director of Construction
Gary Hunt, Director of Maintenance Pam L’Heureux, Director of Finance
Also participating: Karen Ryan, Legal Counsel (Nelson Mullins Broad & Cassel) Ian Brooks, GOAA IT Tara Ciaglia, Recording Secretary
LOBBYIST DISCLOSURE Parties present were reminded that for individuals who conduct lobbying activities with Aviation Authority employees or Board members, registration with the Aviation Authority is required each year prior to conducting any lobbying activities. A statement of expenditures incurred in connection with those lobbying instances should also be filed prior to April 1st of each year for the preceding year. As of January 16, 2013, lobbying any Aviation Authority Staff who are members of any committee responsible for ranking Proposals, Letters of Interest, Statements of Qualifications or Bids and thereafter forwarding those recommendations to the Board and/or Board Members is prohibited from the time that a Request for Proposals, Request for Letters of Interests, Request for Qualifications or Request for Bids is released to the time that the Board makes an award. The lobbyist shall file a Notice of Lobbying (Form 4) detailing each instance of lobbying to the Aviation Authority within seven calendar days of such lobbying. As of January 16, 2013, lobbyists will also provide a notice to the Aviation Authority when meeting with the Mayor of the City of Orlando or the Mayor of Orange County at their offices. The policy, forms, and instructions are available in the Aviation Authority’s offices and the website. Please contact the Director of Board Services with questions at (407) 825-2032. COVID-19 ANNOUNCEMENT Due to the COVID-19, the Aviation Authority is adhering to a business distancing operational plan. Please note that all Professional Services Committee meetings from today until further notice will be held telephonically. If you would like to speak at the meeting on an agenda item being considered, please contact the Recording Secretary, Tara Ciaglia ([email protected] -or- 407-825-4461) no less than 24 hours in advance of the meeting. Otherwise, the Professional Services Committee will be available via Live Stream at www.orlandoairports.net ANNOUNCEMENT Any appeals of decisions made by the Professional Services Committee (PSC) must be filed with the Chief Executive Officer within five business days (no later than 4:00 p.m. on the fifth business day) of the rendering of that decision. If a bidder or proposer is aggrieved by any of the proceedings of today’s meeting and wishes to appeal the results of actions made by this committee, they must file an appeal stating the item they wish to appeal and the basis for which they wish to appeal, and it must be received in writing by the Chief Executive Officer, Mr. Phillip N. Brown, via email [email protected], with a copy to [email protected] (emails will be accepted during the COVID-19 pandemic.)
Minutes of the Professional Services Committee August 4, 2020 Page 2 of 2 REQUEST FOR APPROVAL TO THE CHIEF EXECUTIVE OFFICER OF AN ADDENDUM TO THE INFORMATION TECHNOLOGY CONSULTING SERVICES AGREEMENT WITH TECHNOLOGY MANAGEMENT CORPORATION DBA TECHNOLOGY MANAGEMENT CORPORATION – 1 INCORPORATED FOR FISCAL YEAR (FY) 2020 DESIGN AND IMPLEMENTATION OF A MULTICAST ARCHITECTURE ON THE AVIATION AUTHORITY INTELLECTUAL PROPERTY (IP) DATA NETWORK, AT THE ORLANDO INTERNATIONAL AIRPORT. 1. Mr. Brooks presented the memorandum, dated August 4, 2020, along with a proposal from Technology Management Corporation dba Technology Management Corporation – 1 Incorporated, dated June 26, 2020, for FY 2020 Design and Implementation of a Multicast Architecture on the Aviation Authority IP Data Network, at the Orlando International Airport. These services will provide design and implementation to the Information Technology Development for the multicast architecture on the Aviation Authority IP data network to serve current and future campus-wide multicasting requirements, such as dynamic signage and Closed Circuit Television (CCTV). Further details are included in the Consultant’s proposal, dated June 26, 2020. The Office of Small Business Development reviewed the proposal from Technology Management Corporation dba Technology Management Corporation – 1 Incorporated, and determined that Technology Management Corporation dba Technology Management Corporation – 1 Incorporated does not propose any MWBE and LDB/VBE participation on this addendum. Mr. Patterson asked if there would be additional services after the implementation. Mr. Brooks replied no. Upon motion of Mr. Patterson, second by Mr. Hunt, vote carried by roll-call, with all votes yea, to recommend to the Chief Executive Officer approval of an Addendum to the Information Technology Consulting Services Agreement with Technology Management Corporation dba Technology Management Corporation – 1 Incorporated for FY 2020 Design and Implementation of a Multicast Architecture on the Aviation Authority IP Data Network, at the Orlando International Airport, for the total not-to-exceed fee amount of $21,812.00, with funding from previously-approved Operation and Maintenance Funds. INFORMATION ITEMS 2.
A. Revised Memorandum for the Request for Recommendation to Approve Increase in Value No. 1 for Purchasing Agreement PS-316, Parking Revenue Control System (PRCS) Project Consulting Services with Lumin Advisors, LLC. [From Professional Services Committee on July 28, 2020, Item No. 2].
ADJOURNMENT 3. There being no further business for discussion, the meeting was adjourned at 9:20 a.m.
____________________________ Stanley J. Thornton, Chairman Professional Services Committee Chief Operating Officer
Davin D. Ruohomaki
Digitally signed by Davin D. RuohomakiDate: 2020.09.24 13:46:21 -04'00'
On TUESDAY, AUGUST 11, 2020, the PROFESSIONAL SERVICES COMMITTEE met in regular session virtually in accordance with the Greater Orlando Aviation Authority’s established business distancing operational plan. Chairman Thornton called the meeting to order at 9:15 a.m. The meeting was posted in accordance with Florida Statutes with a quorum participating. Office of the Governor, Executive Order Number 20-69. Participating Committee members: Stanley J. Thornton, Chairman Davin Ruohomaki, Senior Director of Planning, Engineering, and Construction Gary Hunt, Director of Maintenance
Mike Patterson, Director of Construction
Also participating: Karen Ryan, Legal Counsel (Nelson Mullins Broad & Cassel) Dan Gerber, Legal Counsel (Rumberger, Kirk & Caldwell) Pete Pelletier, GOAA IT Ian Brooks, GOAA IT Tara Ciaglia, Recording Secretary
LOBBYIST DISCLOSURE Parties present were reminded that for individuals who conduct lobbying activities with Aviation Authority employees or Board members, registration with the Aviation Authority is required each year prior to conducting any lobbying activities. A statement of expenditures incurred in connection with those lobbying instances should also be filed prior to April 1st of each year for the preceding year. As of January 16, 2013, lobbying any Aviation Authority Staff who are members of any committee responsible for ranking Proposals, Letters of Interest, Statements of Qualifications or Bids and thereafter forwarding those recommendations to the Board and/or Board Members is prohibited from the time that a Request for Proposals, Request for Letters of Interests, Request for Qualifications or Request for Bids is released to the time that the Board makes an award. The lobbyist shall file a Notice of Lobbying (Form 4) detailing each instance of lobbying to the Aviation Authority within seven calendar days of such lobbying. As of January 16, 2013, lobbyists will also provide a notice to the Aviation Authority when meeting with the Mayor of the City of Orlando or the Mayor of Orange County at their offices. The policy, forms, and instructions are available in the Aviation Authority’s offices and the website. Please contact the Director of Board Services with questions at (407) 825-2032. COVID-19 ANNOUNCEMENT Due to the COVID-19, the Aviation Authority is adhering to a business distancing operational plan. Please note that all Professional Services Committee meetings from today until further notice will be held telephonically. If you would like to speak at the meeting on an agenda item being considered, please contact the Recording Secretary, Tara Ciaglia ([email protected] -or- 407-825-4461) no less than 24 hours in advance of the meeting. Otherwise, the Professional Services Committee will be available via Live Stream at www.orlandoairports.net ANNOUNCEMENT Any appeals of decisions made by the Professional Services Committee (PSC) must be filed with the Chief Executive Officer within five business days (no later than 4:00 p.m. on the fifth business day) of the rendering of that decision. If a bidder or proposer is aggrieved by any of the proceedings of today’s meeting and wishes to appeal the results of actions made by this committee, they must file an appeal stating the item they wish to appeal and the basis for which they wish to appeal, and it must be received in writing by the Chief Executive Officer, Mr. Phillip N. Brown, via email [email protected], with a copy to [email protected] (emails will be accepted during the COVID-19 pandemic.) CONFLICT OF INTEREST ANNOUNCEMENT Mr. Gerber announced that all committee members will be required to attend training regarding the Aviation Authority’s enhanced ethics program. The Aviation Authority is
Minutes of the Professional Services Committee August 11, 2020 Page 2 of 3 building upon its strong foundation and culture of ethics and transparency by improving and re-organizing the ethics program. Committee members will receive training on their obligations to confirm their ongoing compliance with conflicts of interest and sunshine law requirements, and the updated process will establish verifiable ways to confirm compliance with Aviation Authority policies. Invitations to the training will be sent to Committee members soon, within the next few weeks. REQUEST FOR RECOMMENDATION OF APPROVAL TO THE CHIEF EXECUTIVE OFFICER OF AN AMENDMENT TO ADDENDUM NO. 15 TO THE INFORMATION TECHNOLOGY CONSULTING SERVICES AGREEMENT WITH FAITH GROUP CONSULTING, LLC FOR A REDUCTION OF SERVICES OF FISCAL YEAR (FY) 2020 DIGITAL CONTENT AND INNOVATION CONSULTING SERVICES, AT THE ORLANDO INTERNATIONAL AIRPORT. 1. [A handout was presented, which includes a revised coversheet.] Mr. Brooks presented the memorandum, dated August 11, 2020, along with a proposal from Faith Consulting Group, LLC, dated June 19, 2020, to reduce the FY 2020 Digital Content and Innovation Consulting Services. On October 29, 2019, the Professional Services Committee recommended approval of Addendum No. 15 in the amount of $2,260,505.00 for FY 2020 Digital Content and Innovation Consulting Services. The Aviation Authority Board approved this action on November 13, 2019. Since that time, it has been determined that, due to COVID-19 impacts, anticipated work through the end of FY 2020 has been modified and reduced, as shown in the below table. Further details are included in the Consultant’s proposal dated June 19, 2020.
Original Addendum Amount
Deduction Amount
Amended Addendum Amount
Not-to-Exceed (NTE) Fees $ 400,000.00 ($348,750.00) $ 51,250.00 Lump Sum Fees $1,860,505.00 ($106,314.60) $1,754,190.40 NTE Expenses $ 0.00 $ 0.00 $ 0.00 TOTAL $2,260,505.00 ($455,064.60) $1,805,440.40
The Office of Small Business Development reviewed the proposal and determined that the proposed deductive Amendment to Addendum No. 1 does not have any impact on the small business participation. Upon motion of Mr. Ruohomaki, second by Mr. Hunt, vote carried by roll-call, with all votes yea, to recommend to the Chief Executive Officer approval of an Amendment to Addendum No. 15 to the Information Technology Consulting Services Agreement with Faith Consulting Group, LLC for Reduction of Services of FY 2020 Digital Content and Innovation Consulting Services, at the Orlando International Airport, for a total deductive amount of ($455,064.60), which includes a deductive amount of ($348,750.00) of Not-to-Exceed Fees and a deductive amount of ($106,314.60) of Lump Sum Fees, with funding credited to previously-approved Operation and Maintenance Funds. REQUEST FOR RECOMMENDATION OF APPROVAL TO THE CHIEF EXECUTIVE OFFICER TO AWARD HEALTH AND TRUST SPATIAL AWARENESS SYSTEM PROOF OF CONCEPT SERVICES TO SYNECT, LLC, AT THE ORLANDO INTERNATIONAL AIRPORT. 2. [A handout was presented, which includes revised and additional backup documentation.] Mr. Brooks presented the memorandum, dated August 11, 2020, along with a proposal from Synect, LLC, dated July 14, 2020, for Health and Trust Spatial Awareness System Proof of Concept (POC) Services, at the Orlando International Airport. The Health and Trust Spatial Awareness POC will measure key data in Airside Two, Gates 101 through 109. The Aviation Authority proposes to award the contract to Synect, LLC via a single source procurement to ensure that the Health and Trust Spatial Awareness POC will measure key data in Airside Two. This data will include information on occupancy and cleaning in the area, which will enable effective visual communication with passengers about the safest ways to move about the airport. This communication content will include visual representations of crowded areas, areas that have been
Minutes of the Professional Services Committee August 11, 2020 Page 3 of 3 visited by cleaning staff, and restroom occupancy. The Single Source Justification, dated July 20, 2020, was fully executed on July 23, 2020. The Office of Small Business Development reviewed the proposal from Synect, LLC, and determined that, due to the specialized scope of services, Synect, LLC does not propose any small business participation on this agreement. Mr. Patterson asked if these procedures will be supported by the Aviation Authority Maintenance cleaning crews. Mr. Hunt replied yes. Mr. Patterson asked if there was an issue with accessing power in the areas. Chairman Thornton replied no, in these areas, power was available in the floor, not the ceiling. Upon motion of Mr. Patterson, second by Mr. Ruohomaki, vote carried by roll-call, with all votes yea, to recommend to the Chief Executive Officer approval of the Award of Health and Trust Spatial Awareness System Proof Of Concept (POC) Services to Synect, LLC, at the Orlando International Airport, for a total not-to-exceed expenses amount of $241,691.00, with funding from previously-approved Capital Expenditure Funds. REQUEST FOR RECOMMENDATION OF APPROVAL TO THE AVIATION AUTHORITY BOARD OF AN ADDENDUM TO THE INFORMATION TECHNOLOGY CONSULTING SERVICES AGREEMENT WITH TECHNOLOGY MANAGEMENT CORPORATION DBA TECHNOLOGY MANAGEMENT CORPORATION - 1 INCORPORATED FOR FISCAL YEAR (FY) 2021 INFORMATION SYSTEMS STAFF AUGMENTATION SUPPORT, AT THE ORLANDO INTERNATIONAL AIRPORT. 3. Mr. Brooks presented the memorandum, dated August 11, 2020, along with a proposal from Technology Management Corporation dba Technology Management Corporation - 1 Incorporated, dated July 21, 2020, for FY 2021 Information Systems Staff Augmentation for Senior IT Systems Specialists/IT Systems Specialists, Telecom Engineer/Analysts, and Service Desk Representative Support Services. These services will provide ongoing staff augmentation support to the Aviation Authority’s IT Department. Services will be provided from October 1, 2020, through September 30, 2021. Further details are included in the Consultant’s proposal dated July 21, 2020. The Office of Small Business Development reviewed the proposal from Technology Management Corporation dba Technology Management Corporation - 1 Incorporated, and determined that Technology Management Corporation dba Technology Management Corporation - 1 Incorporated proposes 13.8% MWBE participation on this Addendum. Mr. Patterson asked if these services were similar to those provided in FY 2020. Mr. Brooks replied yes. Upon motion of Mr. Ruohomaki, second by Mr. Hunt, vote carried by roll-call, with all votes yea, to recommend to the Aviation Authority Board approval of an Addendum to the Information Technology Consulting Services Agreement with Technology Management Corporation dba Technology Management Corporation - 1 Incorporated for FY 2021 Information Systems Staff Augmentation Support, at the Orlando International Airport, for a total not-to-exceed fee amount of $1,925,580.00, with funding from Operation and Maintenance Funds (subject to adoption of the FY 2021 Aviation Authority Budget by the Aviation Authority Board). ADJOURNMENT 4. There being no further business for discussion, the meeting was adjourned at 9:27 a.m. ____________________________ Stanley J. Thornton, Chairman Professional Services Committee Chief Operating Officer
Davin D. Ruohomaki
Digitally signed by Davin D. RuohomakiDate: 2020.09.24 13:45:52 -04'00'